United States
           Environmental Protection
           Agency
                  Office of Water
                  (4503F)
EPA-841-S-96-002
September 1996
EPA
Section 319
National Monitoring Program
Projects
           1996 Summary Report
                                        Recycled/Recyclable
                                        Printed with Soy/Canola ink on paper that
                                        contains at least 50% recycled fiber

-------

-------
    1996  SUMMARY REPORT


                 SECTION 319

 NATIONAL MONITORING PROGRAM

                  PROJECTS


             Nonpoint Source Watershed Project Studies
                  NCSU Water Quality Group
          Biological and Agricultural Engineering Department
            North Carolina Cooperative Extension Service
     North Carolina State University, Raleigh, North Carolina 27695-7637
     Deanna L. Osmond      Daniel E. Line       Steven W. Coffey

Jo Beth Mullens     Judith A. Gale   Jill Saligoe-Simmel   Jean Spooner
          Jean Spooner, Group Leader - Co-Principal Investigator
        Frank J. Humenik, Program Director - Co-Principal Investigator
              U.S. EPA - NCSU-CES Grant No. X818397
                     Steven A. Dressing
                      Project Officer
               U.S. Environmental Protection Agency
                Nonpoint Source Control Branch
             Office of Wetlands, Oceans, and Watersheds
                     Washington, DC
                     September 1996

-------
Disclaimer

This publication was developed by the North Carolina State University Water Quality Group, a part of the
North Carolina Cooperative Extension Service, under U.S. Environmental Protection Agency (USEPA) Grant
No. X818397. The contents and views expressed in this document are those of the authors and do not
necessarily reflect the policies or positions of the North Carolina Cooperative Extension Service, the USEPA,
or other organizations named in this report. The mention of trade names for products or software does not
constitute their endorsement.

Acknowledgments

The authors would like to thank all project personnel of the 319 National Monitoring Program projects, who
have provided information, updated profiles, and reviewed documents. Additional thanks to Melinda Pfeiffer,
Cathy Akroyd, and Judith Gale, who edited this publication.


Citation

This publication should be cited as follows:  Osmond, D.L., D.E. Line, S.W. Coffey, J.B. Mullens, J.A. Gale,
J. Saligoe-Simmel, and J. Spooner.  1996.1996 Summary Report: Section 319 National Monitoring
Program Projects, Nonpoint Source Watershed Project Studies, NCSU Water Quality Group, Biological and
Agricultural Engineering Department, North Carolina State University, Raleigh, NC.
                                Desktop Publishing and Design by:

                                          Janet Young

-------
Table of  Contents
       Chapter 1: Introduction	1

       Chapter 2: Section 319 Nertional Monitoring Program Project Profiles	5

                   Alabama — Lightwood Knot Creek
                      Section 319
                      National Monitoring Program Project	7

                   Arizona — Oak Creek Canyon
                      Section 319
                      National Monitoring Program Project	15

                   California — Morro Bay Watershed
                      Section 319
                      National Monitoring Program Project	29

                   Connecticut — Jordan Cove Urban Watershed
                      Section 319
                      National Monitoring Program Project	43

                   Idaho — Eastern Snake River Plain
                      Section 319
                      National Monitoring Program Project	49

                   Illinois — Lake Pittsfield
                      Section 319
                      National Monitoring Program Project	63

                   Iowa — Sny Magill Watershed
                      Section 319
                      National Monitoring Program Project	73

                   Iowa — Walnut Creek
                      Section 319
                      National Monitoring Program Project	89

                   Maryland — Warner Creek Watershed
                      Section  319
                      National Monitoring Program Project	97

                   Michigan — Sycamore Creek Watershed
                      Section 319
                      National Monitoring Program Project	105

                   Nebraska — Elm Creek Watershed
                      Section 319
                      National Monitoring Program Project	117

                   North Carolina — Long Creek Watershed
                      Section 319
                      National Monitoring Program Project	129

                    Oklahoma — Peacheater Creek
                      Section 319
                       National Monitoring Program Project	141

                    Oregon — Upper Grande Ronde Basin
                       Section 319 Project
                       (Pending Section 319 National
                       Monitoring Program Project Approval)	151
                                             in

-------
             Pennsylvania — Pequea and Mill Creek Watershed
                Section 319
                National Monitoring Program Project	161

             Vermont — Lake Champlain Basin Watersheds
                Section 319
                National Monitoring Program Project	171

             Washington — Totten and Eld Inlet
                Section 319
                National Monitoring Program Project	183

             Wisconsin - Otter Creek
                Section 319
                National Monitoring Program Project....".	195


Appendices	.	205

             I.  Minimum Reporting Requirements for
                Section 319
                National Monitoring Program Projects	207

             II.  Abbreviations	209

             III. Glossary of Terms	213

             IV. Project Documents and Other Relevant Publications	219

             V.  Matrix for Section 319
                National Monitoring Program Projects	245
                                        IV

-------
List  of Figures
       Figure 1:

       Figure 2:


       Figure 3:

       Figure 4:


       Figure 5:


       Figure 6:


       Figure 7:


       Figure 8:


       Figure 9:


       Figure 10:


       Field Map

       Field Map

       Figure 11:

       Figure 12:


       Figure 13:


       Figure 14:


       Figure 15:

       Figure 16:


       Figure 17:


       Figure 18:


       Figure 19:

       Figure 20:


       Figure 21:
 Lightwood Knot Creek (Alabama) Project Location.

 Water Quality Monitoring Stations for
 Lightwood Knot Creek (Alabama)	
 Oak Creek Canyon (Arizona) Project Location

 Water Quality Monitoring Stations for
 Oak Creek Canyon (Arizona)	
 Morro Bay (California) Watershed
 Project Location	
 Paired Watersheds (Chorro Creek and
 Los Osos Creek) in Morro Bay (California)
 Jordan Cove Urban Watershed (Connecticut)
 Project Location	
 Water Quality Monitoring Stations for
 Jordan Cover Urban Watershed (Connecticut)

 Eastern Snake River Plain (Idaho)
 Demonstration Project Area Location	
 Eastern Snake River Plain (Idaho)
 USDA Demonstration Project Area
1: (Idaho)	

2: (Idaho)	

 Lake Pittsfield (Illinois) Location.
 Water Quality Monitoring Stations for Blue Creek
 Watershed and Lake Pittsfield (Illinois)	
 Sny Magill and Bloody Run (Iowa) Watershed
 Project Locations	
 Water Quality Monitoring Stations for Sny Magill
 and Bloody Run (Iowa) Watersheds	
 Walnut Creek (Iowa) Project Location

 Water Quality Monitoring Stations for
 Walnut Creek (Iowa)	
 Warner Creek (Maryland) Watershed
 Project Location	
...8

.15


.16


.29


.30


.43


.44


.49


.50

.61

.62

.63


.64


.73


.74

,.89


..90


..97
  Water Quality Monitoring Stations for
  Warner Creek (Maryland) Watershed.
  Sycamore Creek (Michigan) Project Location.

  Paired Water Quality Monitoring Stations for
  the Sycamore Creek (Michigan) Watershed...
  Elm Creek (Nebraska) Watershed
  Project Location	
..98

 105


,106


,117

-------
List of Figures (Continued)
Figure 22:  Water Quality Monitoring Stations for
           Elm Creek (Nebraska) Watershed	118

Figure 23:  Long Creek (North Carolina) Watershed
           Project Location	129

Figure 24:  Water Quality Monitoring Stations for
           Long Creek (North Carolina) Watershed	130

Figure 25:  Peacheater Creek (Oklahoma)
           Project Location	141

Figure 26:  Water Quality Monitoring Stations for
           Peacheater Creek (Oklahoma) Watershed	142

Figure 27:  Upper Grande Ronde Basin (Oregon) Project Location	151

Figure 28:  Water Quality Monitoring Stations for
           Upper Grande Ronde Basin (Oregon)	152

Figure 29:  Pequea and Mill Creek (Pennsylvania) Watershed
           Project Location	161

Figure 30:  Water Quality Monitoring Stations for Pequea and
           Mill Creek (Pennsylvania) Watershed	162

Figure 31:  Lake Champlain Basin (Vermont) Watersheds
           Project Location	,	171

Figure 32:  Water Quality Monitoring Stations for
           Lake Champlain Basin (Vermont) Watersheds	172

Figure 33:  Totten and Eld Inlet (Washington)
           Project Location	183

Figure 34:  Water Quality Monitoring Stations for
           Totten and Eld Inlet (Washington)	184

Figure 35:  Otter Creek (Wisconsin) Watershed
           Project Location	195

Figure 36:  Water Quality Monitoring Stations for
           Otter Creek (Wisconsin)	196
                                       VI

-------
  Chapter 1




Introduction

-------
                                                       Chapter 1: introduction
Monitoring of both land treatment and water quality is the best way to document
the effectiveness of nonpoint source (NFS) pollution control efforts. The purposes
of the United States Environmental Protection Agency (USEPA) Section 319
National Monitoring Program (NMP) are to provide credible documentation of the
feasibility of controlling nonpoint sources, and to improve the technical under-
standing of NFS pollution and the effectiveness of NPS control technology and
approaches. These objectives are to be achieved through intensive monitoring and
evaluation of a subset of watershed projects funded under section 319 (USEPA,
1991).

The Section 319 NMP projects comprise a small subset of NPS pollution control
projects funded under Section 319 of the Clean Water Act as amended in 1987.
The development of NMP projects has largely been accomplished through nego-
tiations among States, USEPA Regions, and USEPA Headquarters.

The selection criteria used by USEPA for Section 319 NMP projects are primarily
based on the components listed below. In addition to the specific criteria, empha-
sis is placed on projects that have a high probability of documenting water quality
improvements from NPS controls over a 5- to 10-year period.

    Documentation of the water quality problem, which includes identification of
    the pollutants of primary concern, the sources  of those pollutants, and the
    impact on designated uses of the water resources.

    Comprehensive watershed description.

    Well-defined critical area that encompasses the major sources of pollution
    being delivered to the impaired water resource. Delineation of a critical area
    should be based on the primary pollutants causing the impairment, the
    sources of the pollutants, and the delivery system of the pollutants to the
    impaired water resource.

    A watershed implementation plan that uses appropriate best management
    practice (BMP) systems.  A system of BMPs is a combination of individual
    BMPs designed to reduce a specific NPS problem in a given location. These
    BMP systems should address the primary pollutants of concern and should be
    installed and utilized on the critical area.

    Quantitative and realistic water quality and land treatment objectives and
    goals.

    High level of expected implementation and landowner participation.

    Clearly defined NPS monitoring program objectives.

    Water quality and land treatment monitoring designs that have a high
    probability of documenting changes in water quality that are associated with
    the implementation of land treatment.

    Well-established institutional arrangements and multi-year, up-front funding
    for project planning and implementation.

    Effective and ongoing information and education programs.

 •   Effective technology transfer mechanisms.

 Minimum tracking and reporting requirements for land treatment and surface
 water quality monitoring have been established by USEPA for the NMP projects
 (USEPA, 1991). These requirements (see Appendix 1) were set forth based upon
 past efforts (e.g. Rural Clean Water Program) to evaluate the effectiveness of
 watershed projects.

-------
                                                       Chapter 1: Introduction
USEPA developed a software package, the NonPoint Source Management System
(NPSMS), to help the 319 National Monitoring Program projects track and report
land management and water quality information (Dressing and Hill, 1996).
NPSMS has three data files: 1) a Management File for information regarding
water quality problems within the project area and plans to address those prob-
lems; 2) a Monitoring Plan File for the monitoring designs, stations, and param-
eters; and 3) an Annual Report File for annual implementation and water quality
data.'NPSMS version 3.01 is currently used by National Monitoring Program
projects, operating in a DOS™ environment. USEPA has recently developed a
beta-version 4.2 that runs under MS Windows™ Version 3.1 or better (USEPA,
1996a).

This publication is an annual report on seventeen Section 319 NMP projects
approved as of September 1,1996, and one Section 319 NMP project pending
approval. Project profiles (Chapter 2) were prepared by the North Carolina State
University (NCSU) Water Quality Group under the USEPA grant entitled
Nonpoint Source Watershed Project Studies, and by the Oregon State University
Water Resource Research Institute. Profiles have been reviewed and edited by
personnel associated with each project.

The sixteen surface water monitoring projects selected as Section 319 NMP
projects are Lightwood Knot Creek (Alabama), Oak Creek Canyon (Arizona),
Morro Bay (California), Jordan Cove Urban Watershed (Connecticut), Lake
Pittsfield (Illinois), Sny Magill (Iowa), Walnut Creek (Iowa), Warner Creek
Watershed (Maryland), Sycamore Creek (Michigan), Elm Creek (Nebraska), Long
 Creek (North Carolina), Peacheater Creek (Oklahoma), Pequea and Mill Creek
 (Pennsylvania), Lake Champlain (Vermont), Totten and Eld Inlet (Washington),
 and Otter Creek (Wisconsin). A report on the Upper Grande Ronde Basin (Or-
 egon) 319 project, which is pending Section 319 National Monitoring Program
 project approval, is also included. The seventeenth project, Snake River Plain,
 Idaho, is a pilot ground water project.

 One of the projects focuses on urban sources, while the others primarily address
 agricultural sources. Nearly all of the projects  address river or stream problems,
 while seven projects are intended to directly benefit a lake, estuary, or bay. One of
 the projects is focused on ground water protection. Most projects are still in the
 pre-implementation phase, but a few have begun to implement nonpoint source
 controls. The progress made by these projects  will be showcased in this report.

 Each project profile includes a project overview, project description, and maps
 showing the location of the project in the state and the location of water quality
 monitoring stations. In the project description section, water resources are identi-
 fied, water quality and project area characteristics are described, and the water
 quality monitoring program is outlined. Project budgets and project contacts are
 also presented.

 The Appendices include the minimum reporting requirements for Section 319
 NMP projects (Appendix I), a list of abbreviations (Appendix II), and a glossary
 of terms (Appendix III) used in the project profiles. A list of project documents
  and other relevant publications for each project is included in Appendix IV.
  Appendix V contains a matrix for the Section 319 NMP Projects.

-------
REFERENCES
                                                                                 Chapter 1:  Introduction
                             Dressing, S.A. and J. Hill. 1996. Nonpoint Source Management System Software: A
                             Tool for Tracking Water Quality and Land Treatment. IN: Proceedings Watershed
                             '96 Moving Ahead Together Technical Conference and Exposition. Water Environ-
                             ment Federation, Alexandria, VA, p. 560-562.

                             USEPA. 1991.  Watershed Monitoring  and Reporting for Section 319 National
                             Monitoring Program Projects. Assessment and Watershed Protection Division,
                             Office of Wetlands, Oceans, and Watersheds, Office of Water, U.S. Environmental
                             Protection Agency, Washington, DC.

                             USEPA. 1994. Section 319 National Monitoring Program Projects. EPA-841-S-94-
                             006, Office of Water, Washington, DC.

                             USEPA. 1996a. NonPoint Source Management System — NPSMS Version 4.0
                             User's Guide. Office of Water, Washington, DC.

                             USEPA. 1996b. Nonpoint Source Program and Grants Guidance for Fiscal Year
                             1997 and Future Years. Office of Water, Washington, DC.

-------
                  Chapter 2

                Section 319
National Monitoring Program
             Project Profiles

-------
                                                    i Chapter 2:  Project Profiles
This chapter contains a profile of each of the Section 319 National Monitoring
Program projects approved as of September 1,  1996, arranged in alphabetical
order by state. A profile of the Upper Grande Ronde Basin (Oregon) 319 project,
which is pending Section 319 National Moniotirng Program project approval, is
also included.

 Each profile begins with a brief project overview, followed by detailed informa-
tion about the project, including water resource description; project area charac-
teristics; information, education, and publicity; nonpoint source control strategy;
water quality monitoring program information; total project budget; impact of
other federal and state programs; other pertinent information; and project con-
tacts.

Sources used in preparation of the profiles include project documents and review
comments made by project coordinators and staff.
                                 i
Project budgets have been compiled from the best and most recent information
available.

Abbreviations used in the budget tables are as follows:

Proj Mgt	Project Management
I&E	Information and Education
LT	Land Treatment
WQ Monit	Water Quality Monitoring
NA	Information Not Available
 A list of project documents and other relevant publications for each project may be
 found in Appendix IV.

-------
                                   Alabama

                     Lightwood Knot Creek
                                Section 319
       National Monitoring Program Project
           Alabama
             Project Area
                    o
Figure 1: Lightwood Knot Creek (Alabama) Project Location

-------
                                                                          Lighwood Knot Creek, Alabama
                                                                                    .V •
           SCALE

            0
                                                  EXPLANATION

                                             Lightwood Knot Creek-     4-5,
                                             W. F. Jackson Lake       A.
                                             Watershed
                                                                    _J:c
                                             Specific project area      •  Control sampling site
                                                                         and number
1 MILES
               1 KILOMETERS
Figure 2: Water Quality Monitoring Stations for Lightwood Knot Creek (Alabama) Watershed

-------
                                                                              Lightwood Knot Creek, Alabama
PROJECT OVERVIEW
                               Lightwood Knot Creek is a tributary of the 1,100-acre W.F. Jackson Lake in
                               Southeastern Alabama (Figure 1). Jackson Lake was constructed for recreational
                               uses in 1987. The 47,300-acre watershed is approximately half forested and half
                               in agriculture. Pasture, hayland, cropland, and poultry production are the domi-
                               nant agricultural land uses.

                               Erosion in the Lightwood Knot Creek watershed and resulting sedimentation of
                               Jackson Lake are major water quality problems. Numerous agricultural fields have
                               been identified as sources of sediment. Types of erosion occurring include sheet,
                               rill, ephemeral, and erosion along unpaved roads. Nutrients and bacteria from
                               poultry operations are also potential sources of pollution.

                               Land treatment is scheduled to begin two years after the start of baseline monitor-
                               ing. Erosion control practices to be implemented include runoff and sediment
                               control structures, critical area planting, cover and green manure crops, and
                               pasture and hayland management. For animal waste management, practices
                               include poultry litter storage and waste utilization.

                               The Geological Survey of Alabama is conducting physical, chemical, and biologi-
                               cal monitoring at two sets of paired watersheds. Each of the watersheds has a
                               control and treatment watershed. These watersheds are small, ranging from 75 to
                               240 acres. Monitoring will be conducted weekly for all parameters (see Water
                               Quality Monitoring section below) from April through August. Only inorganic
                               parameters will be monitored for the remainder of the year.

                               A geographic information system (GIS) will be used to map soil, land use prac-
                               tices, underlying geology, slope, monitoring site, and best management practice
                               (BMP) implementation data for the two-paired watersheds that each consist of a
                               control watershed and treatment watershed
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
 Impairments
 Pre-Project
 Water Quality
Water resources of concern are Lightwood Knot Creek and other tributary streams
to Jackson Lake, a reservoir created in 1987. Four branches of Lightwood Knot
Creek will be monitored in this study. Median seven-day low flow of these
branches, sustained by ground water seepage, is approximately 0.32 cubic feet per
second per square mile of watershed.

Lightwood Knot Creek and Jackson Lake are used for recreation. Sedimentation
of tributaries and the lake is a primary concern. Excessive sediment impairs
aquatic life habitat, increases bridge maintenance costs, increases flooding poten-
tial, and reduces the capacity of Jackson Lake. Elevated levels of nitrogen and
phosphorus have been found in Lightwood Knot tributaries.  No lake quality data
were available.

Very little background water quality information is available; however, tributary
sampling in July of 1994 provides some indication of pre-project water quality.
Turbidity ranged from 41 to 55 NTU. Total nitrogen ranged from 0.8 to 5.0 mg/1
and total phosphorus ranged from 0.03 to 0.51 mg/1. Fecal coliform and fecal
streptococcus ranged from approximately 500 to nearly 9,000 counts per 100 ml.

-------
                                                                        Lighwood Knot Creek, Alabama
Current Water
Quality Objectives

Project Time Frame

Project Approval
Project monitoring started in April of 1996 and no pre-project data are presently
available on current water quality conditions.

Temporary project time frame is January to December, 1996.

Project will be eligible for consideration for long-term funding after monitoring in
1996 is completed. Background data at present is not sufficient for long-term
funding.
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorological Factors

Land Use
The Lightwood Knot watershed draining into Jackson Lake covers 47,300 acres.
Jackson Lake is 1,100 acres in size.

Soils consist of a thin sandy loam topsoil and a sandy clay subsoil with a depth of
six feet. Average annual rainfall is 56 inches and average annual runoff is 23
inches.
Land Use
Crop
Pasture/hay
Forest
Residential
Lake
Total
Percent
23
26
47
2
2
100
Pollutant Sources
Pollutant sources vary from agricultural fields and roads to confined animal
operations. Numerous fields have been identified for erosion control BMPs. There
are 15 poultry operations and one dairy that are potential sources of nonpoint
source pollution.
INFORMATION, EDUCATION, AND PUBLICITY
                            A program of educational outreach and information distribution was initiated in
                            April, 1996.
NONPOINT SOURCE CONTROL STRATEGY
Description
Many BMPs could be used for erosion control in the watershed, depending upon
site conditions. Runoff and sediment control structures, critical area planting,
cover and green manure crops, and pasture and hayland management are potential
erosion control practices.

For control of nutrients, poultry litter storage, mortality composting, and waste
utilization practices, such as adjusting the rate and timing of poultry litter applica-
tion to match realistic yields and crop uptake, are needed.
                                              10

-------
                                                                           Lightwood Knot Creek, Alabama
WATER QUALITY MONITORING
Design
Parameters
Measured
Two paired watershed studies being conducted on tributaries of Lightwood Knot
Creek (Figure 2). There are two control watersheds and two treatment watersheds.
No additional BMPs will be installed in the treatment watersheds for two years.
No additional BMPs will be installed in the control watersheds until the monitor-
ing study has been completed (approximately seven years).

Biological

Fecal coliform (FC)
Fecal streptococcus (FS)

Chemical

Aluminum (Al)
Ammonia (NHs)
Antimony (Sb)
Arsenic (As)
Barium (Ba)
Beryllium (Be)
Biochemical oxygen demand (BOD)
Boron (B)
Cadmium (Cd)
Calcium (Ca)
Chemical oxygen demand (COD)
Chloride (Cl)
Chromium (Cr)
Copper (Cu)
Iron (Fe)
Lead (Pb)
Magnesium (Mg)
Manganese (Ma)
Nickel (Ni)
Nitrite (NO2)
Nitrate + nitrite (NOs + N02)
Orthophosphate (OP)
pH
Selenium (Se)
Silica (Si)
Silver (Ag)
Sulfate (SO4~)
Tin (Sn)
Total dissolved phosphorus (TOP)
Total dissolved solids (TDS)
Total Kjeldahl nitrogen (TKN)
Total suspended solids (TSS)
Turbidity
Zinc (Zn)

Covariates

Bedload sediment
Flow
Precipitation
Specific conductance
                                                11

-------
                                                                         Lighwood Knot Creek, Alabama
Sampling Scheme
  Samples will be taken weekly for all parameters from April through August. Total
  dissolved solids, total suspended solids, and covariates will be monitored monthly
  during the remainder of the year.
  Monitoring Scheme for the Lightwood Knot Creek Section 319 National Monitoring Program Project
            Sites or
  Design   Activities
                                            Frequency of
 Primary                    Frequency of  Habitat/Biological
Parameters      Covariates   WQ Sampling     Assessment    Duration
Two paired Tributary
watersheds subwatersheds
NHs Discharge Weekly
NO2 Precipitation
N03 + N02
OP
TDP
Turbidity
TSS
FC
FS
Annual 1 year
Water Quality Data
Management and
Analysis
NPSMS Data
Summary
  Chemical monitoring results will be entered into the U.S. Environmental Protec-
  tion Agencies' (USEPA) STORET database and the Alabama Department of
  Environmental Management's database. Biological data will be stored in the
  USEPA BIOS database.

  The project intends to track water quality parameters and land use activities with
  the NonPoint Source Management System (NPSMS).
TOTAL PROJECT BUDGET
                             The estimated budget for the Lightwood Knot Creek Section 319 National Moni-
                             toring Program project for the life of the project is:
                             Project Element
                             Proj Mgt
                             I&E
                             LT
                             WQ Monit
                             TOTALS
                      Federal

                      120,693
                          NA
                      100,000
                      544,307
                      775,000
      Funding Source ($)
  State       Local
                                                                                      Sum
 59,305
    NA
    NA
715,695
775,000
NA
NA
NA
NA
NA
 179,998
     NA
     NA
1,270,002
1,550,000
                             Source: Geological Survey of Alabama, 1995
                                                12

-------
                                                                 Lightwood Knot Creek, Alabama
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                          In 1994, a Water Quality Incentive Project (WQIP) was approved for the Yellow
                          River basin. The project includes funding for BMPs in the Lightwood Knot Creek
                          watershed to improve erosion control and implementation of animal waste man-
                          agement practices.
OTHER PERTINENT INFORMATION
                          None.
PROJECT CONTACTS
Administration
Land Treatment
 Water Quality
 Monitoring
 Information and
 Education
Marlon Cook
Geological Survey of Alabama
420 Hackberry Lane
BoxO
Tuscaloosa, AL 35486-9780
(205) 349-2852

Steve Yelverton
USDA-NRCS
Box 1796
Andalusia, AL 36420
(205) 222-9451

Jack Goolsby
USDA-FSA
Box 1127
Andalusia, AL 36420

Marlon Cook
Geological Survey of Alabama
420 Hackberry Lane.
BoxO
Tuscaloosa, AL 35486-9780
(205) 349-2852

Chuck Simon
Covington County Extension Agent
Box 519
Andalusia, AL 36420
                                           13

-------
                               Lighwood Knot Creek, Alabama
14

-------
                                  Arizona

                       Oak Creek Canyon
                              Section 319
     National Monitoring Program Project
Figure 3: Oak Creek Canyon (Arizona) Project Location
              15

-------
                                                                       Oak Creek Canyon, Arizona
s.___^
~]
v_^'


s
	 /
^- /
1
J
„•>

X
\
1
1
\
\


•\
/
/













          Cocortlno County
          Yovapal County
                                                                                  /
                                                                                    \
                                                                        n
                                                                        \
                                              Legend
                                                     Sampling Site (Upstream)

                                                     Sampling Site (Downstream)

                                                     Stream
                                                     Watershed Boundaiy
Figure 4: Water Quality Monitoring Stations for Oak Creek Canyon (Arizona)
                                      16

-------
                                                                                   Oak Creek Canyon, Arizona
PROJECT OVERVIEW
                               Oak Creek flows through the southern rim of the Colorado Plateau (Figure 3). The
                               Oak Creek Canyon National Monitoring project focuses exclusively on that
                               segment of water located in the canyon portion of Oak Creek, a 13-mile steep-
                               walled area of the creek that extends from the city limits of Sedona to the
                               Mogollon Rim, thirteen miles northward. Although Oak Creek Canyon watershed
                               encompasses 5,833 acres, only 907 primarily recreational acres are considered to
                               impact the water quality of Oak Creek Canyon water.

                               The Oak Creek Section 319 National Monitoring Program project focuses on the
                               implementation and documentation of integrated best management practice
                               (BMP) systems for three locations: Slide Rock State Park, Pine Flats Campground,
                               and Slide Rock Parking Lot. The eleven-acre Slide Rock State Park is used by
                               more than 350,000 swimmers and sunbathers each season and Pine Flats Camp-
                               ground accommodates approximately 10,000 campers each season. Such heavy
                               use at both locations causes excess fecal coliform and nutrient levels in Oak
                               Creek. Slide Rock State Park parking lot accommodates over 90,000 vehicles each
                               season. Runoff of pollutants associated with automobiles drains into Oak Creek.

                               The BMPs implemented at Slide Rock  State Park and Pine Flats Campground
                               include enhanced restroom facilities, better litter control through more intense
                               monitoring by state park officials of park visitors, and the promotion of visitor
                               compliance with park and campground regulations on use of facilities, littering,
                               and waste disposal. The BMPs implemented at the Slide Rock parking lot include
                               periodic cleaning of the detention basin, promotion of an aerobic environment in
                               the basin, periodic sweeping of the parking lot, and, if necessary, retrofitting the
                               detention basin itself.

                               An upstream/downstream water quality monitoring design is used to evaluate the
                               effectiveness of BMPs for improving water quality at Slide Rock State Park.
                               Grasshopper Point, a managed water recreation area similar to Slide Rock State
                               Park, serves as the control. Water quality monitoring stations are located upstream
                               and downstream of swimming areas at both Slide Rock (treatment)  and Grasshop-
                               per Point (control). An upstream/downstream water quality monitoring design is
                               also being used for Pine Flats Campground and Manzanita Campground. Pine
                               Flats Campground is the treatment  site, while Manzanita serves as the control
                               site. Monitoring stations are upstream/downstream of campground sites. For these
                               two studies, weekly grab samples are taken from May 15 through September 15
                               for six years.

                               The Slide Rock parking lot study evaluates the effectiveness of a detention basin
                               designed to limit pollutants from entering Oak Creek. An event-based BMP-
                               effectiveness monitoring scheme is being used. Automatic samplers, triggered by
                               rainfall, have been installed at inflow and outflow points of the detention basin.
                               Each one collects samples of the first flush and composite periodic samples of the
                               runoff.
                                                   17

-------
                                                                                  Oak Creek Canyon, Arizona
PROJECT DESCRIPTION
Water Resource
Type and Size
Water Uses and
Impairments
 Pre-Project
 Water Quality
Oak Creek cuts deep into the southern rim of the Colorado Plateau. It drops
approximately 2,700 feet from its source along the Mogollon Rim to its conver-
gence with the Verde River. The Creek averages about 13 cubic feet per second
(cfs) at the study area, but increases to 60 cfs downstream at its confluence with
the Verde River.

The study sites for this project are located in Oak Creek Canyon. This portion of
the watershed is characterized by steep canyons and rapid water flows with sharp
drops forming waterfalls and deep, cold pools. Oak Creek Canyon is the primary
recreational area in the watershed.

Designated beneficial uses of Oak Creek include full body contact (primarily in
Oak Creek Canyon), cold water fishery and wildlife habitat (primarily Oak Creek
Canyon), drinking water (along the entire course), agriculture (the lower third), and
livestock watering (lower third).

Oak Creek was designated as a Unique Water by the Arizona State Legislature in
1991 on the basis of 1) its popularity and accessibility as a water recreation
resource; 2) its aesthetic, cultural, educational, and scientific importance; and 3)
its importance as an agricultural and domestic drinking water resource in the Verde
Valley. Two other criteria were considered in the designation: 1) Oak Creek
Canyon is susceptible to irreparable or irretrievable loss due to the ecological
fragility of its location and 2) it is a surface water segment that can be managed as
a unique water. Management considerations must include technical feasibility and
the availability of management resources.

Biological, nutrient, and vehicular pollutants pose the most serious and pressing
current threats to Oak Creek water quality. Oak Creek water quality is impaired
by high fecal coliform levels, probably resulting from residential septic systems
and the high usage of the campgrounds and day-use swimming areas by over
350,000 people from May through September. Excessive nutrients, particularly
phosphorus, which exceeds the 0.10 mg/1 standard, threaten the water integrity of
two impoundments located well below Oak Creek that provide a major source of
drinking water for the City of Phoenix. Vehicular pollution consisting of heavy
metals (such as lead and zinc), petroleum hydrocarbons, and total organic  carbons
originates from the estimated four million vehicles traveling along State Highway
89 A each year, as well as from drainage of numerous parking lots in the Oak
Creek Canyon area during rainstorms and snow melts. These sources of pollution
threaten all designated uses.

Water Recreation and Camping Areas

Human pathogens (bacteria and viruses) contaminate the Canyon segment of Oak
Creek. Most of the attention has focused upon Slide Rock State Park and Grass-
hopper Point, the two managed "swimming holes" in the area. Fecal coliform
counts peak in the summer during the height of the tourist season.
                                                    18

-------
                                                                               Oak Creek Canyon, Arizona
                             Fecal Coliform Levels During the Tourist Season (1993)
                                        Fecal Coliform Count fcfu)
                             Date              (#/100 ml)
                             July                  434
                             August               393
                             June                  61
                             September             54

                             Nutrient levels, especially phosphorus, are also of concern, as shown below:

                             Phosphorus (P) Concentrations  at Pine Flats Campground During
                             1993 (the annual average standard is 0.10 mg/l)
                             Date
                             February, 1993
                             March, 1993
                             April, 1993
                             June, 1993
                             July, 1993
                             August, 1993
                     P(mg/l)
                      0.12
                      0.20
                      0.12
                      0.14
                      0.28
                      0.41
                             Slide Rock Parking Lot

                             Preliminary data suggest that the Slide Rock Parking Lot detention basin (a large,
                             baffled concrete vault) is contributing to environmental damage rather than
                             reducing it. Approximately four feet of stagnant water remains in the vault at all
                             times. Preliminary data (see table below) indicates that heavy rainfall cleanses the
                             parking lot of pollutants and also flushes out significant amounts of pollutants
                             contained in the detention basin into Oak Creek.

                             Water Quality of the Detention Basin
                             Time
                             Before Rain (7/93)
                             After Rain (10/93)
                     DO(mg/I)
                        0.0
                        4.5
IlH
4.79
6.6
Znfug/1)
  222
   38
Current Water
Quality Objectives
Modifications Since
Project Initiation
Water Recreation Project Objectives

•   A 50% reduction in fecal coliform

•   A 20% reduction in nutrients, particularly ammonia

•   A 20% reduction in total organic carbons with a corresponding reduction in
    biochemical oxygen demand (BOD)

Camping Project Objectives

•   A 50% reduction in fecal coliforms

•   A 20% reduction in nutrients

Slide Rock Parking Lot Objectives
•   A 25% reduction of automobile-related pollutants that enter Oak Creek

None.
                                                 19

-------
                                                                            Oak Creek Canyon, Arizona
 Project Time Frame

 Project Approval
 1994 to 1999

 1994
PROJECT AREA  CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
The entire Oak Creek watershed contains 300,000 acres. The project area, Oak
Creek Canyon, encompasses 5,833 acres. However, the critical area comprises
only 907 acres.

Flow in Oak Creek ranges from an average 13 cfs, in the higher Oak Creek
Canyon area, to 60 cfs at its confluence with the Verde River.

Annual precipitation in the Oak Creek watershed varies from a six-inch average
in the Verde Valley to 20 inches per year on the higher elevations of the Mogollon
rim. The majority of rainfall occurs during July and August of the monsoon
season (July 4 to September 15). Summer rainfall storm events are short and
intense in nature (rarely lasting for more than a half-hour) and are separated by
long dry periods. In a normal summer season, over twenty rainfall events occur.

Perennial flow in Oak Creek is sustained by ground water, the main source of
which is the regional Coconino Aquifer. The majority of aquifers in the Oak
Creek watershed are confined or artesian. Within the Oak Creek watershed,
ground water flow is generally to the south, paralleling topography toward the low-
lying valley floor.
Land Use
Road
Campground and Parking Lots
Business and Residential
Floodplain
Undeveloped
TOTAL
                                                                            6
                                                                           14
                                                                           27
                                                                           32
                                                                           21
                                                                          100
                             Source: The Oak Creek 319(h) Demonstration Project National Monitoring Program Work
                             Plan, 1994
Pollutant Sources
Modifications Since
Project Started
Pollutants in Oak Creek addressed in this study originate mainly from swimmers,
campers, and motor vehicles.

None.
INFORMATION, EDUCATION, AND PUBLICITY
                             Numerous organizations and individuals perceive themselves as "owners" of Oak
                             Creek Canyon. It is in the best interest of the Oak Creek National Monitoring
                             Program project to fully involve these groups and individuals in informational and
                             educational activities.

                             The Oak Creek Advisory Committee, which was formed in 1992, involves federal,
                             state, and local government agencies and private organizations such as Keep
                             Sedona Beautiful and the Arizona River Coalition. The committee meets monthly
                                               20

-------
                                                                               Oak Creek Canyon, Arizona
Progress Towards
Meeting Goals
to keep participants informed of current project activities and results, gain in-
sights into areas of concern, and learn about the BMPs that are being imple-
mented as part of the 319 National Monitoring Program.

With respect to the proposed Public Education Campaign for the Oak Creek
Canyon Section 319 National Monitoring Program project, the following events
have transpired:

•   The U.S. Forest Service prepared a Public Education Plan for Slide Rock
    State Park and hired a public education specialist to continue and expand the
    public education effort.

•   The Arizona State Parks staff are developing signs and a brochure aimed at
    educating Slide Rock visitors.
NONPOINT SOURCE CONTROL STRATEGY
Modifications Since
Project Started

Progress Towards
Meeting Goals
Slide Rock and Grasshopper Point (Water Recreation Project)

The access to and ambience of restroom facilities located at the Slide Rock
swimming area are being enhanced. Park officials are attempting to reduce the
amount of trash disposal in unauthorized areas. Finally, social strategies have
been implemented to promote compliance with park regulations.

Pine Flats and Manzanita (Campgrounds Project)

The nonpoint source control strategy for the campground project targets the
upstream site of Pine Flats. Best management practices implemented at Pine Flats
are designed to reduce pollutants associated with human use of campground
facilities. The BMPs implemented include enforcement of a clean zone between
the creek and the campground and the promotion of the use of existing restroom
facilities. Direct contact by park personnel with visitors and the addition of more
visible signs help  accomplish these goals.

Slide Rock (Parking Lot Project)

The BMP strategy focuses on reducing runoff from the parking lot and parking
lot detention basin. The existing detention basin is cleaned out before and after
the rainy season. An aerobic environment within the basin has been promoted
and street sweeping of the parking lot is also occurring.

None.
The Oak Creek Task Force has implemented the following BMPs:

•   Erecting nearly one mile of permanent barricades on State Highway 89A,
    reducing the number of visitors having access by approximately one-half

•   Modernizing the single restroom located at the swimming area and
    constructing a more convenient path to the facility

Perhaps most significantly, the Oak Creek Task Force formed two subgroups. The
Management Team has assumed responsibility for planning and implementing
the BMPs. The Sampling Team has responsibility for identifying pollutant
sources and measuring the effectiveness of BMPs.
                                                 21

-------
                                                                              Oak Creek Canyon, Arizona
 WATER QUALITY MONITORING
Design
Modifications Since
Project Started

Parameters
Measured
The water recreation project, which is an upstream/downstream monitoring
design (Figure 4), is designed to document the change in water quality as a result
of the application of BMPs. The swimming sites at Slide Rock State Park (treat-
ment site) and Grasshopper Point (the control site) are compared. Water quality
monitoring stations are located above and below each swimming area.

The camping area project also uses an upstream/downstream monitoring design.
Water quality monitoring stations have been installed above and below both the
camping area at Pine Flats (treatment site) and the site at Manzanita (control
site).

A BMP effectiveness water quality monitoring design is being used for the Slide
Rock parking lot study. Sampling will take place at the inflow point and the
outflow point of the detention basin.

The three-year post-BMP implementation phase entails sampling protocols
identical to those instituted in the calibration and project sampling phase. The
objective of this monitoring phase is to demonstrate the extent to which land
treatment has reduced nonpoint source pollution.

None.
Slide Rock and Grasshopper Point (Water Recreation Project)
and Pine Flats and Manzanita (Campgrounds Project)

Biological

Fecal coliform (FC)

Chemical and Others

Ammonia (NHs)
Nitrate (NOs)
Phosphate (PO43")

Covariates

Water temperature
Stream velocity and level
Number of users of the sites
Weekly precipitation
Alkalinity
Calcium (Ca)
Chloride (Cl)
Conductivity
Dissolved oxygen (DO)
Magnesium (Mg)
pH
Potassium (K)
Sodium (Na)
Turbidity
                                                 22

-------
                                                                               Oak Creek Canyon, Arizona
                              Slide Rock Parking Lot Project

                              Chemical and Other

                              Total suspended solids (TSS)
                              Ammonia (NHs)
                              Nitrate (NOs)
                              Phosphate (PO43~)
                              Biochemical oxygen demand (BOD)
                              Lead (Pb)
                              Copper (Cu)
                              Zinc (Zn)
Sampling Scheme
Covariates

Precipitation (Amount and Duration)
Runoff:'velocity
PH
Park attendance

Slide Rock/Grasshopper Point (Water Recreation Project)
and Pine Flats/Manzanita (Campgrounds Project)

Grab samples are collected weekly from May 15 through September 15 and
monthly from November through April. Samples are taken in the deepest part of
the stream at each sampling site.

Slide Rock Parking Lot Project

An event-based scheme is used to monitor runoff from the parking lot. An auto-
matic sampler has been placed at the inflow and outflow points of the detention
basin. The samplers are triggered by rainfall events. A sample of the "first flush"
is deposited in the first bottle. Thereafter, a sample is taken every twenty minutes
and composited in the second bottle, "post flush." Sample bottles are collected
within five hours of each rain event.

The monitoring scheme for all three sites is presented as follows.
                                                 23

-------
                                                                                   Oak Creek Canyon, Arizona
Monitoring Scheme for the Oak Creek Canyon Section 319 National Monitoring Program Project
Activity/ Primary
Design Sites* Parameters**
— \VaterRecreation





Upstream/
downstream








BMP
effectiveness


Slide Rock (T)


Grasshopper
Point (C)

Outiplng
Pine Flats (T)


Manzanita (C)


—
~~ Parking Runoff
Slide Rock
Parking Lot


—

FC
NH3
NO3
PO43'
BOD










TSS, BOD,
N03.NH3,
PO^.Cu.Pb,
andZn

Covariates***

Alkalinity
Ca
Cl
Conductivity
DO
Mg
PH
K
Rainfall
Na
Streamflow
Turbidity
Visitor count
Water temperature

pH
Rainfall amount
Rainfall duration
Runoff velocity

Frequency Time

9/15-5/15 monthly 10 am -5pm
5/15-9/15 weekly Saturdays













Minimum of 20 event Event driven;
driven samples with usually in the
priority to: afternoon or
1 . 7/4 to 9/1 5 early evening
2. 9/1 5 to 7/4
Duration

2 years pre-BMP
1 year BMP
3 years post-BMP












2 years pre-BMP
1-2 years BMP
3 years post-BMP


* T "the treatment site; C" the control site
** Basic pollution parameters will remain constant throughout the 6-7 years ofthe project with the exception of the parking lot project. The number of
basic parameters will be reduced through Years I and II; those which are not detected in six sampling events will be discarded.
 ***AM covariato parameters will be sampled throughout the 6-7 years ofthe project in order to assure project credibility. However, those which do not
significantly vary with basic parameters will be dropped from statistical analysis after Year I ofthe project.
Modifications Since
Project Started

Water Quality Data
Management and
Analysis

 NPSMS Data
 Summary

Modifications Since
Project Started

Progress Towards
Meeting Goals
None.
The project team stores all raw data in STORET and reports the project results in
USEPA's Nonpoint Source Management System (NPSMS) software.
Currently unavailable.
None.
The DOS SYSTAT for Windows program (Wilkinson, Leland. SYSTAT: The
System for Statistics, Evanston, IL: SYSTAT, Inc., 1990) was used for statistical
analysis. Multiple correlations for each factor were obtained. Sufficient data points
(at least twenty for each factor) were available to provide valid and reliable data.
Generally, analysis revealed extremely high correlations for most water quality at
all locations.

Project personnel have concluded that a significant amount (30.79%) ofthe
ammonia recorded at the Slide Rock downstream is deposited in the water column
between the upstream and downstream location. The ammonia source is uncon-
firmed. The most probable source is visitors urinating in the water or on the
terrain nearby; however, other possibilities have not been eliminated. Perhaps the
"black water" vault at the restroom is leaking. Ammonia may be released into the
                                                    24

-------
                                                                                  Oak Creek Canyon, Arizona
                              water column from roiled sediments; however, the probability is slight since 1)
                              ammonia is highly soluble and retention in sediments is slight and 2) ammonia is
                              assimilated into the environment quite rapidly. Therefore, ammonia may be
                              produced from some other source. Efforts at ammonia source determination will
                              continue.

                              Approximately 98% of the time, fecal coliform is deposited in significant amounts
                              (88.2%) into the water column between upstream and downstream sites at Slide
                              Rock.

                              Identifying fecal coliform sources is difficult. Slide Rock visitors are, undoubtedly,
                              a source of pollution (i.e., discarding dirty diapers in the water and defecating in
                              the water or on land nearby). However, visitor behavior cannot account for the
                              cyclical nature of elevated fecals in this area. High levels of fecals (i.e., levels
                              approaching the current water quality standard of 800 cfu/100 ml for a single
                              measure) historically and in Year 1 of this project were only detected during the
                              "monsoon  season" — roughly between July 15 and September 15 of each year.
                              There are no exceptions. If visitors were the sole source of elevated fecals, then
                              high levels should have occurred between Memorial Day and July 4, when visitor
                              counts are  as high as during the monsoon season. This  has not occurred; there-
                              fore, there  must be one or more other sources of fecal coliform. Northern Arizona
                              University  personnel are currently exploring the monsoon season source of fecal
                              coliform in a project separate from the Oak Creek National Monitoring Program
                              project.

                              Personnel from the Oak Creek Section 319 National Monitoring Program project
                              continue to explore two possible sources of fecal pollution occurring at down-
                              stream. Slide Rock: 1) visitors pollute the water directly by depositing excrement
                              into the water or on the land nearby (which is washed into the water) and 2)
                              visitors pollute the water indirectly by roiling fecal-laden sediments washed
                              downstream to the Slide Rock area.
TOTAL PROJECT BUDGET
                               The estimated budget for the Oak Creek Canyon Section 319 National Monitoring
                               Program project for the life of the project is:
                               Project Element
                               Proj Mgt
                               LT
                               WQ Monit
                               TOTALS
                 Federal

                  70,000
                  30,200
                 424,800
                 525,000
       Funding Source (S)
  State          Local
 70,000
 65,000
    NA
135,000
 70,000
 35,500
608,140
713,640
    Total

 210,000
 130,700
1,032,940
1,373,640
                               Source: Tom Harrison (Personal Communication), 1994
Modifications Since
Project Started
None.
                                                   25

-------
                                                                        Oak Creek Canyon, Arizona
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
Modifications Since
Project Started
The Oak Creek Section 319 National Monitoring Program project complements
several other programs (federal, state, and local) located in the Verde Valley:

    The U.S. Geological Survey has initiated a comprehensive water use/water
    quality study focusing on the northcentral Arizona region extending from the
    City of Phoenix to the Verde Valley.

•   The Verde Watershed Watch Program, a 319(h)-funded program run by
    Northern Arizona University. The program is designed to train students and
    teachers from seven high schools (located within the river basin) in
    macroinvertebrate and water chemistry sampling to evaluate the effects of
    BMP implementation.

•   The Arizona Department of Environmental Quality has established the Verde
    Nonpoint Source Management Zone in the state.

•   The Colorado Plateau Biological Survey has established a major riparian
    study project focusing on the Beaver Creek/Montezuma Wells area of the
    Verde Valley.

None.
OTHER PERTINENT INFORMATION
                           None.
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Daniel Salzler
Arizona Department of Environmental Quality
Nonpoint Source Unit
3033 N. Central, 3rd Floor
Phoenix, AZ 85012-0600
(602) 207-4507; Fax: (602) 207-4467

Dr. Gordon Southam
Department of Biological Sciences
Northern Arizona University
Flagstaff, AZ 86011-5640
(520) 523-8034; Fax: (520) 523-7500
Internet: ggs@nauvax.ucc.nau.edu

Dr. Richard D. Foust
Department of Chemistry and Environmental Science
Northern Arizona University
Flagstaff, AZ 86011-5698
(520) 523-7077; Fax: (520) 523-2626
Internet: rdf@al.ucc.nau.edu
                                             26

-------
                                                                                 Oak Creek Canyon, Arizona
Information and
Education
Dr. Gordon Southam
Department of Biological Sciences
Northern Arizona University
Flagstaff, AZ  86011-5640
(520) 523-8034; Fax: (520) 523-7500
Internet: ggs@nauvax.ucc.nau.edu

Dr. Paul Trotta
Department of Civil and Environmental Engineering
Northern Arizona University
Flagstaff, AZ 86011-1560
(520) 523-4330; Fax: (520) 523-2300
Internet: pdt@pine.cse.nau.edu
                                                 27

-------
                                Oak Creek Canyon, Arizona
28

-------
                                   California

                      Morro Bay Watershed
                                 Section 319
       National Monitoring Program Project
Figure 5: Morro Bay (California) Watershed Project Location
                29

-------
                                                                     Morro Bay Watershed, California
                        Managed Grazing Project
                                                                           Camp:StQNRCS
                                                                           Management Plan
    Chorrb Flats
Floodplain/Sediment
 Retention Project
                                                                                         N
                                                                    Cattle Exclusion Projects
   Martinez
 Conservation
  Easement


      Legend

C = Chumash Station
W= Waiters Station
U = Chorro/Upstream station
D = Chorro/Downstream Station
                                                    BMP Plan Implementation
      Figure 6: Paired Watersheds (Chorro Creek and Los Osos Creek) in Morro Bay (California)
                                             30

-------
                                                                               Morro Bay Watershed, California
PROJECT OVERVIEW
                               The Morro Bay watershed is located on the central coast of California, 237 miles
                               south of San Francisco in San Luis Obispo County (Figure 5). This 76-square mile
                               watershed is an important biological and economic resource. Two creeks, Los
                               Osos and Chorro, drain the watershed into the Bay. Included within the watershed
                               boundaries are two urban areas, prime agricultural and grazing lands, and a wide
                               variety of natural habitats that support a diversity of animal and plant species.
                               Morro Bay estuary is considered to be one of the least altered estuaries on the
                               California coast. Heavy development activities, caused by an expanding popula-
                               tion in San Luis Obispo County, have placed increased pressures on water re-
                               sources in the watershed.

                               Various nonpoint source pollutants, including sediment, bacteria, metals, nutri-
                               ents, and organic chemicals, are entering streams in the area and threatening
                               beneficial uses of the streams  and estuary. The primary pollutant of concern is
                               sediment. Brushland and rangeland contribute the largest portion of this sediment,
                               and Chorro Creek contributes twice as much sediment to the Bay as does Los Osos
                               Creek. At present  rates of sedimentation, Morro Bay could be lost as an open
                               water estuary within 300 years unless remedial action is undertaken. The main
                               objective of the Morro Bay Nonpoint Source Pollution and Treatment Measure
                               Evaluation Program, of which the Morro Bay Watershed Section 319 National
                               Monitoring Program project is a subset, is to reduce the quantity of sediment
                               entering Morro Bay.

                               The U.S. Environmental Protection Agency (USEPA) Section 319 National
                               Monitoring Program project for the Morro Bay watershed was developed to
                               characterize the sedimentation rate and other water quality conditions in a portion
                               of Chorro Creek, to evaluate the effectiveness of several best management practice
                               (BMP) systems in improving  water quality and habitat quality, and to evaluate the
                               overall water quality at select sites in the Morro Bay watershed.

                               The Morro Bay Watershed  Section 319 National Monitoring Program project is a
                               paired watershed study on two subwatersheds of Chorro Creek (Chumash and
                               Walters Creeks). The purpose of the project is to evaluate the effectiveness of a
                               BMP system in improving water quality (Figure 6). BMP system effectiveness is
                               being evaluated for sites outside the paired watershed. These projects include a
                               managed grazing  system, cattle exclusion projects, and a flood plain sediment
                               retention project.  In addition, water quality samples taken throughout the water-
                               shed will document the changes in water quality during the life of the project.
 PROJECT DESCRIPTION
 Water Resource
 Type  and Size
The total drainage basin of the Morro Bay watershed is approximately 48,450
acres. The 319 project monitoring effort is focused on the Chorro Creek water-
shed. Chorro Creek and its tributaries originate along the southern flank of Cuesta
Pudge, at elevations of approximately 2,700 feet. Currently three stream gauges
are operational in the Chorro Creek watershed: one each on the San Luisito, San
Bernardo,  and Chorro creeks. Annual discharge is highly variable, ranging from
approximately 2,000 to over 20,000 acre-feet, and averaging about 5,600 acre-feet.
Flow in tributaries is intermittent in dry years and may disappear in all but the
uppermost areas of the watershed. In spite of the intermittent nature of these
creeks, both Chorro and Los Osos creeks are considered cold-water resources,
supporting anadromous fisheries (steelhead trout).

                    31

-------
                                                                                 Morro Bay Watershed, California
Pre-Project
Water Quality
Current Water
Quality Objectives
Morro Bay is one of the few relatively intact natural estuaries on the Pacific Coast
of North America. The beneficial uses of Morro Bay include recreation, industry,
navigation, marine life habitat, shellfish harvesting, commercial and sport fish-
ing, wildlife habitat, and rare and endangered species habitat.

A number offish species (including anadromous fish, which use the Bay during a
part of their life cycle) have been negatively affected by the increased amount of
sediment in the streams and the Bay. Sedimentation in anadromous fish streams
reduces the carrying capacity of the stream for steelhead and other fish species by
reducing macroinvertebrate productivity, spawning habitat, and egg and larval
survival rates, and increasing gill abrasion and stress on adult fish. Although trout
are still found in both streams, ocean-run fish have not been observed in a number
of years.

Accelerated sedimentation has also resulted in significant economic losses to the
oyster industry in the Bay. Approximately 100 acres of oyster beds have been lost
due to excessive sedimentation. Additionally, fecal coliform bacteria carried by
streams to the Bay have had a negative impact on the shellfish industry, resulting
in periodic closures of the area to shellfish harvesting (NRCS, 1992). Due to
continually elevated levels of total and fecal coliform, the California Department
of Health Services is considering reclassifying the Bay from "conditional" to
"restricted."  Reclassification to "restricted" would require changes in harvesting
practices, which would be cost prohibitive for existing operations. Elevated fecal
coliform counts have been detected in water quality samples taken from several
locations in the watershed and the Bay. Elevated fecal coliform detections, exceed-
ing 1,600 Most Probable Number/100 ml, have generally been found in areas
where cattle  impact on streams is heavy.

The Tidewater Goby, a federally  endangered brackish-water fish, has been elimi-
nated from the mouths of both Chorro and Los Osos creeks, most likely as a result
of sedimentation of pool habitat in combination with excessive water diversion.

The two creeks that flow into the estuary (Chorro Creek and Los Osos Creek) are
listed as impaired by sedimentation, temperature, and agricultural  nonpoint
source pollution by the State of California (Central Coast Regional Water Quality
Control Board, 1993).

Studies conducted within the watershed have identified sedimentation as a serious
threat in the watershed and estuary. Results of a U.S. Department of Agriculture
(USDA) Natural Resources Conservation Service (NRCS) Hydrologic Unit Areas
(HUA) project study show that the rate of sedimentation has increased tenfold
during the last 100 years (NRCS, 1989b). Recent studies indicate that the estuary
has lost 25% of its tidal volume in the last century as a result of accelerated
sedimentation, and has filled in with an average of two feet of sediment since
1935 (Haltiner, 1988). NRCS estimated the current quantity of sediment delivered
to Morro Bay to be 45,500 tons per year (NRCS, 1989b).

The overall goal of the Section 319 National Monitoring Program project is to
evaluate improvements in water quality resulting from implementation of BMPs.
The following objectives have been identified for this project:

    Identify sources, types, and amounts of nonpoint source pollutants (see the list
    of parameters that will be monitored under Water Quality Monitoring),
    originating in paired watersheds in the Chorro Creek watershed (Chumash
    and Walters creeks).

    Determine stream flow/sediment load relationships in the paired watersheds.
                                                    32

-------
                                                                              Morro Bay Watershed, California
Modifications Since
Project Initiation
Project Time Frame

Project Approval
    Evaluate the effectiveness of improving water quality in one of the paired
    subwatersheds (Chumash Creek) of a BMP system.

•   Evaluate the effectiveness of several BMP systems in improving water or
    habitat quality at selected Morro Bay watershed locations, including a
    managed grazing project, cattle exclusion projects, and a flood plain sediment
    retention project.

•   Monitor overall water quality in the Morro Bay watershed to identify problem
    areas for future work, detect improvements or changes, and contribute to the
    water quality database for watershed locations.

•   Develop a geographic information system (GIS) database to be used for this
    project and in future water quality monitoring efforts.

None.


August 1, 1993 - June 30, 2003

1993
PROJECT AREA  CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
The Morro Bay watershed drains an area of 48,450 acres into the Morro Bay
estuary on the central coast of California. The Bay is approximately 4 miles long
and 1.75 miles wide at its maximum width. The project area is located in the
northeast portion of the Morro Bay watershed.

Morro Bay was formed during the last 10,000 to 15,000 years (NRCS, 1989a). A
post-glacial rise in sea level of several hundred feet resulted in a submergence of
the confluence of Chorro and Los Osos creeks (Haltiner, 1988). A series of creeks
that originate in the steeper hillslopes to the east of the Bay drain westward into
Chorro and Los Osos creeks, which drain into the Bay. The 400-acre salt marsh
has developed in the central portion of the Bay in the delta of the two creeks. A
shallow ground water system is also present underneath the project .area.

The geology of the watershed is highly varied, consisting of complex igneous,
sedimentary, and metamorphic rock. Over fifty diverse soils, ranging from fine
sands to heavy clays, have been mapped in the area. Soils in the upper watershed
are predominantly coarse-textured, shallow, and weakly developed. Deeper me-
dium- or fine-textured soils are typically found in valley bottoms or on gently
rolling hills. Earthquake activity and intense  rain events increase landslide poten-
tial and severity in sensitive areas.

The climate of the watershed is Mediterranean: cool, wet winters and warm, dry
summers. The area receives about 95% of its  18-inch average annual precipitation
between the months of November and April. The mean air temperatures range
from lows around 45 degrees F in January to  highs of 75  degrees F in October,
with prevailing winds from the northwest averaging about  15 to 20 miles per hour.

Approximately 60% of the land in the watershed is classified as rangeland. Typi-
cal rangeland operations consist of approximately 1,000 acres of highly productive
grasslands supporting cow-calf enterprises. Brushlands make up another 19% of
the watershed area. Agricultural crops (truck, field, and grain crops), woodlands,
and urban areas encompass approximately equal amounts of the landscape in the
watershed.

                    33

-------
                                                                             Morro Bay Watershed, California
                              Land Use
                              Agricultural Crops
                              Woodland
                              Urban
                              Brushland
                              Rangeland
                              Total

                              Source:  NRCS, 1989a
                                  Acres
                                   3,149
                                   3,093
                                   3,389
                                   8,319
                                  26,162
                                  44,112
  7
  7
  8
 19
 59
100
Pollutant Sources
Modifications Since
Project Started
It has been estimated that 50% or more of the sediment entering the Bay results
from human activities. Sheet and rill erosion account for over 63% of the sedi-
ment reaching Morro Bay (NRCS, 1989b). An NRCS Erosion and Sediment Study
identified sources of sediment to the Bay, which include activities on rangeland,
cropland, and urban lands (NRCS, 1989b). The greatest contribution of sediment
to the Bay originates from upland brushlands (37%) because of the land's steep-
ness, parent material, and lack of undercover, as well as from rainfall. Rangelands
are the second largest source of sediment entering into streams (12%). Cattle
grazing has damaged riparian areas by stripping the land of vegetation and
breaking down bank stability. The unvegetated streambanks, as well as overgrazed
uplands, have resulted in accelerated erosion. Other watershed sources that
contribute to sediment transport into Morro Bay include abandoned mines, poorly
maintained roads, agricultural croplands, and urban activities.

In August, 1994, the "Highway 41 Fire" burned a significant portion (7,524 acres)
of the upper Chorro Creek watershed and its tributaries. The paired watersheds,
Chorro,  Churrash, and Walters, were not burned. Above average precipitation and
several periods of widespread flooding during the 1994-95 winter, following the
wildfires, resulted in significant erosion and sediment loading throughout the
watershed.
INFORMATION, EDUCATION, AND PUBLICITY
Progress Towards
Meeting Goals
Many formal and informal educational programs conveying information about the
319 National Monitoring Program project and the watershed are conducted each
year. Information and education programs include field tours, lectures, and
workshops about the water quality problems within the watershed (for landowners
and local agency personnel).

Public presentations about the Morro Bay 319 National Monitoring Program
project were made to groups such as Friends of the Estuary, as well as Cal Poly
State University (Cal Poly) and Cuesta Community College. Presentations on the
monitoring program were also made at a Regional Water Quality Control Board
public hearing and at the annual Soil and Water Conservation Society Conference
(California Chapter).

In addition, educational outreach efforts have been made at several Cooperative
Extension erosion control field tours and workshops, the Morro Bay Museum of
Natural History, a 4-H watershed education day, the California Biodiversity
Council, Morro Bay Task Force meeting, and Cal Poly Coastal Resources,  Soil
Science, Limnology, and Marine Biology classes. Publicity generated includes
excellent articles in the local newspaper, a radio program, and a featured spot on
the local evening news.
                                                   34

-------
                                                                            Morro Bay Watershed, California
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Paired Watershed
BMP Systems at Sites
within the Morro Bay
Watershed
 Modifications Since
 Project Started
 Progress Towards
 Meeting Goals
In the paired watershed, a BMP system is being used to reduce nonpoint source
pollutants. Cal Poly is responsible for implementing the BMP system on Chumash
Creek, which is one of the streams in the paired watershed, while Walters Creek
serves as the control. The implemented BMPs include 1) fencing the riparian
corridor, 2) creating smaller pastures for better management of cattle-grazing
activities, 3) providing appropriate water distribution to each of these smaller
pastures, 4) stabilizing and revegetating portions of the streambank, and 5)
installing water bars and culverts on farm roads where needed. During the project,
riparian vegetation is expected to increase from essentially zero to at least 50%
coverage. The project team has established a goal of a 50% reduction in sediment
following BMP implementation.

The NRCS has designed several BMP systems in the Morro Bay watershed. Three
of these systems are being evaluated for their effect on water and habitat quality:

•   A flood plain sediment retention project will be established at Chorro Flats to
    retain sediment (sediment retention project)

•   A riparian area along Dairy Creek, a tributary of Chorro Creek, has been
    fenced and revegetated (cattle exclusion project)

•   Fences have been installed to allow rotational grazing of pastures on the
    1,400-acre Maine ranch (managed grazing project)

The goals for these projects during the next 10 years are to achieve:

•   A 33.8% decrease in sediment yield from the sediment retention project

•   A 66% reduction in sediment yield from the cattle exclusion project

•   A 30% reduction in sediment as a result of the managed grazing project

Modifications occurred at Chorro Flats due to emergency post-fire concerns. An
existing level breech was widened so that the flood plain could serve as a sedi-
ment deposition area.

Paired Watershed Study: Funding has been acquired through CWA 319(h) for
implementation of improvements on the paired watershed. A Technical Advisory
Committee has been formed and has expanded its focus to include monitoring
projects throughout the entire Morro Bay watershed.  Implementation for land
improvements on the Chumash Creek watershed is underway. To date, implemen-
tation has included construction of riparian pastures,  additional upland pastures,
watering troughs, and culvert improvements. Revegetation and stabilization of
portions of the corridor was completed in the fall of 1996.

Flood Plain Sediment Retention Project: The Chorro Flats project has obtained
funding ($960,000) for implementation of the Flood Plain Restoration Project. All
 environmental documents and engineering designs have been completed.

 Cattle Exclusion Project: Dairy Creek fencing for riparian exclusion was com-
 pleted in the summer of 1995.

 Managed Grazing Project: In 1994, the Maino Ranch completed installation of
 watering devices and fencing and is being managed as planned in a timed grazing
 project.
                                                  35

-------
                                                                              Morro Bay Watershed, California
WATER QUALITY MONITORING
Design
Modifications Since
Project Started
Parameters
Measured
Two watersheds have been selected for a paired watershed study. Chumash Creek
(400 acres) and Walters Creek (480 acres) both drain into Chorro Creek. The
watersheds of the two creeks have similar soils, vegetative cover, elevation, slope,
and land use activities.  The property surrounding the two creeks is under the
management of Cal Poly. Because the rangeland being treated is owned by Cal
Poly, project personnel will be able to ensure continuity and control of land
management practices.

The paired watershed monitoring plan entails three specific monitoring tech-
niques: stream flow/climatic monitoring, water quality monitoring, and biologi-
cal/habitat monitoring.  The calibration period (the period during which the two
watersheds are monitored to establish statistical relationships between them) has
been completed (1994-1995). After the calibration period was completed, a BMP
system offences, watering troughs, and other improvements was installed in one
of the watersheds (Chumash Creek). The other watershed, Walters Creek, serves
as the control.

Other systems of BMPs will be or have been established at different locations in
the Morro Bay watershed. Water quality will be monitored using upstream/
downstream and single station designs to evaluate these systems. An upstream/
downstream design has been adopted to monitor the water quality effect of a flood
plain sediment retention project and a cattle exclusion project. A single station
design on a subdrainage is being used to evaluate changes in water quality from
implementation of a managed grazing program.

In addition to BMP effectiveness ihonitoring,  ongoing water quality sampling is
taking place at selected sites throughout the Morro Bay watershed to document
long-term changes in overall water quality and to discern problem areas in need of
further restoration efforts.

Because of very limited runoff during the 1993-1994 sampling year, only one
sampling event occurred. However, because of extreme wetness during the 1994-
1995 rainy season, sufficient data for baseline information were collected. Addi-
tional water quality and flow data were obtained in the 1995-1996 rainy season.
This will be characterized as a "during BMP implementation" year.

Biological

Total and fecal coliform (FC)
Riparian vegetation
Upland rangeland vegetation
Benthic invertebrates

Chemical and Other

Suspended solids  (SS) (total filterable solids)
Turbidity
Nitrate (NOs)
Phosphate (PO43~)
Conductivity
pH
Dissolved oxygen (DO)
Temperature
                                                   36

-------
                                                                                Morro Bay Watershed, California
Sampling Scheme
Covariates

Precipitation
Stream flow
Evaporation
Animal units

Weekly grab samples are taken for at least 20 weeks during the rainy season,
starting on November 15 of each year or after the first runoff event.

The samples from the paired watershed stations are analyzed for SS, turbidity,
NOa, PO43", total and fecal coliform, and other physical parameters.

The Dairy Creek cattle exclusion is being analyzed for SS, turbidity, nutrients,
total and fecal coliform, and other physical parameters.

Suspended sediment and turbidity are being monitored at the Chorro Flats sedi-
ment retention area.

In addition, year-round samples for pH, DO, turbidity, temperature, and total and
fecal coliform are conducted every two weeks at several additional sampling sites
throughout the Morro Bay Watershed.

In the paired watershed,  SS samples are collected during storm events using
automated sampling equipment set at even intervals (30-minute). The water
collected from each individual sample are analyzed for SS, turbidity, and conduc-
tivity. Streamflow and climatic data are also collected for hydrologic response of
watersheds

Vegetation is assessed via aerial photography conducted biannually in March and
September during the first, fifth, and tenth years of the project. On both the paired
watershed and the Maino property, four permanent vegetation transects are
monitored two times each year to sample upland and riparian vegetation and
document changes during the life of the project.

Cross-sectioned stream channel profiles are conducted once each year to docu-
ment stream channel shape, substrate particle size, and streambank vegetation.
Rapid BioAssessment (RBA) is used as a tool to assess water and habitat quality
of sites throughout the Chorro and Los Osos Watersheds.
                                                    37

-------
                                                                                Morro Bay Watershed, California
 Monitoring Scheme for the Morro Bay Watershed Section 319 National Monitoring Program Project


Design
Paired









Upstream/
downstream




Upstream/
downstream




Single
downstream







Sites or
Activities
Chumash
CreckTand
Walters Creek c







Chorro Flats
Sediment
Retention
Project


Dairy Creeks
Cattle Exclusion
Project



Maino Ranch
Managed
Grazing
Project





Primary
Parameters
Total &FC
Riparian vegetation
SS & bedload sediment
Turbidity
NO3
P043'
Conductivity
PH
DO

SS
Turbidity
Sediment deposition



SS
Turbidity
FC
NO3
PO43'
Physical parameters
SS
Turbidity
FC
Riparian vegetation






Covariates
Precipitation
Stream flow
Evaporation
Animal units






Precipitation
Stream flow
Evaporation
Animal units


Precipitation
Stream flow
Evaporation
Animal units


Precipitation
Stream flow
Evaporation
Animal units





Frequency for
WQ Sampling
Start after first run-
off arid weekly grab
samples thereafter
for 20 weeks.
Storm event based
monitoring
(every 30 minutes).



Storm event
monitoring
(hourly)



Weekly during
rainy season
starting around
Nov. 15.


Weekly during
the rainy season.






Frequency
for Vegetation
Sampling
March & Sept.
aerial photography
in 1st, 5th, &
10th year.
Vegetation transects
twice per year.
RBA once per year.
Cross-sectional
profiles once per year
(cross-sections).
March & Sept.
aerial photography
in 1st, 5th, &
10th year.
RBA once per year.
Cross-sections.
March & Sept.
aerial photography
in 1st, 5th, &
10th year.
RBA once per year.
Cross-sections.
March & Sept.
aerial photography
in 1st, 5th, &
10th year.
'Vegetation transects
twice per year.
RBA once per year.
Cross-sections.


Duration
2 yrs pre-BMP
2 yrs BMP
6 yrs post-BMP







4 yrs pre-BMP
1 yrBMP
4 yrs post-BMP



lyr pre-BMP
1/2 yrBMP
7 yrs post-BMP



0- lyr pre-BMP

8 yrs post-BMP





""Treatment watershed
'•Control watershed
Modifications Since
Project Started
Modifications have been made to sediment analysis techniques since project
inception. During the first year, evaporation was used to process suspended
sediment samples; however, dissolved solids are high in this watershed and
contribute significantly to the total weight of the samples. Presently, analysis is for
total filterable solids.  A relationship between conductivity and dissolved solids is
being developed to convert past years' data to filterable solids. In addition to
suspended solids and turbidity, conductivity is being measured for each suspended
sediment sample during event monitoring. However, composite samples from
event monitoring will no longer be analyzed for total N, total P, or pH. Grab
sampling continues unchanged for nitrate, phosphate, conductivity, turbidity,
dissolved oxygen, and water temperature.

The upper Chorro Flats station was moved downstream below the influence of the
Chorro Flats Sediment Retention Project. Bedload sampling has been discontin-
ued because of sampling difficulties. The Chorro Flats water quality stations were
redesigned in October, 1995. The "top down" removable intake pipes facilitate
improved functionality and accessibility.
                                                    38

-------
                                                                              Morro Bay Watershed, California
Water Quality Data
Management and
Analysis
The winter of 1993-1994 was relatively dry, with only two runoff events. In
contrast, the 1994-1995 rainy season was characterized by above average precipi-
tation and periods of flooding. The 1995-1996 winter was more representative of
normal rainfall events and streamflow levels in the watershed. Sediment, turbid-
ity, and flow data from storm events are collected. Even interval grab sampling is
obtained, with sampling conducted once every two weeks. During the rainy season
(20 weeks beginning after the first runoff event), grab samples were collected once
per week. Although the study design requires even-interval sampling year round,
this is not feasible in several locations (including the paired watersheds) because
the flow becomes intermittent or ceases entirely during summer months. The
Coshocton sampler experienced continual inundation with sediment and was
removed in 1995.

Data Management

Data and BMP implementation information are handled by the project team. As
required by the USEPA Section 319 National Monitoring Program Guidance, data
are entered into STORET and reported using the Nonpoint Source Management
System Software (NPSMS). A geographic information system (GIS), ARC/INFO,
is used to map nonpoint pollution sources, BMPs, and land uses, and to determine
resulting water quality problem areas.

A Quality Assurance Project Plan, for project water quality sampling and analysis,
has been developed by the Central Coast Regional Water Quality Control Board.
The plan is used to assure the reliability and accuracy of sampling, data recording,
and analytical measurements.
NPSMS Data
Summary

Modifications Since
Project Started

Progress Toward
Meeting Goals
Data Analysis

Recent analysis has focused on the baseline data collection period. Linear regres-
sion of Chumash flow on Walters flow demonstrates a close, though not entirely
linear, relationship (R=0.73). Current work includes development of minimum
detectable change limits for baseline data and integration of even interval and
event-based data.

Data will be entered into STORET and NPSMS as soon as upgraded software
versions are available.
None.
A revised Quality Assurance Plan has been developed, implemented, and submit-
ted to USEPA for review. It is available at the Regional Water Quality Control
Board office. GIS data layers entered this past year (using ARC/INFO) include
sample site locations, streams, flood zones, ground water basins, geology, soils,
vegetation, land use, and topography. Initial data analysis indicates that Chumash
and Walters Creek are well paired and that sufficient baseline data have been
collected.
                                                   39

-------
                                                                            Morro Bay Watershed, California
TOTAL PROJECT BUDGET
                             The estimated budget for the Morro Bay Watershed Section 319 National Moni-
                             toring Program project for the period of FY96 is:
                             Project Element
                             Proj Mgt
                             I&E
                             *LT
                             WQ Monit
                             TOTALS
                              Funding Source (S)
                     Federal            State
                      20,000
                      25,000
                     130,000
                      55,000
                     230,000
     N/A
     N/A
1,593,500
  20,000
1,613,500
   Sum

  20,000
  25,000
1,723,500
  75,000
1,843,500
Modifications Since
Project Started
                              * Land Treatment dollars are largely to be used for permanent structures. These funds will
                              be used for matching funds throughout the duration of the project, not just for the fiscal
                              year. The amounts shown will be utilized over the entire project period.

                              Source: Karen Worcester (Personal Communication), 1995
None.
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                              The Central Coast Regional Water Quality Board is conducting a study of the
                              abandoned mines in the watershed with USEPA 205(j) funds. The Board has also
                              obtained a USEPA Near Coastal Waters grant to develop a watershed work plan,
                              incorporate new USEPA nonpoint source management measures into an overall
                              basin plan, and develop guidance packages for the various agencies charged with
                              responsibility for water quality in the watershed.

                              The Department of Fish and Game Wildlife Conservation Board provided funding
                              ($48,000) for steelhead habitat enhancement on portions of Chorro Creek. The
                              State Department of Parks and Recreation funded studies on exotic plant inva-
                              sions in the delta as a result of sedimentation. The California Coastal Commission
                              used Morro Bay as a model watershed in development of a pilot study for a
                              nonpoint source management plan pursuant to Section 6217 of the Federal
                              Coastal Zone Management Act Reauthorization Amendments of 1990.

                              The California Assembly Bill 640 became law in January, 1995. The law estab-
                              lishes Morro Bay as the first "State Estuary," and mandates that a comprehensive
                              management plan be developed for the bay and its watershed by locally involved
                              agencies, organizations, and the general public.

                              On July 6, 1995, Morro Bay was accepted into the National Estuary Program
                              (NEP). This "National Estuary" designation provides 1.3 million from USEPA
                              dollars for planning over a three year period. Current efforts have been made by
                              the Morro Bay State Estuary Watershed Council to create the foundation for this
                              planning process. NEP issue groups have been meeting to discuss pollution
                              sources in the watershed and estuary and to explore management measures which
                              could be implemented. Action plans including strategies for reducing pollutants
                              such as sediment and bacteria are being developed by NEP staff through input
                              from the community and interested agencies.
                                                  40

-------
                                                                               Morro Bay Watershed, California
Modifications Since
Project Started
In addition to the USEPA 319 National Monitoring Program project being led by
the California Central Coast Regional Water Quality Control Board, several other
agencies are involved in various water quality activities in the watershed. The
California Coastal Conservancy contracted with the Coastal San Luis Resource
Conservation District in 1987 to inventory the sediment sources to the estuary, to
quantify the rates of sedimentation, and to develop a watershed enhancement plan
to address these problems. The Coastal Conservancy then provided $400,000 for
cost share for BMP implementation by landowners. USDA funding has been
obtained for technical assistance in the watershed ($140,000/year), Cooperative
Extension adult and youth watershed education programs ($100,000/year), and
cost share for farmers and ranchers ($ 100,000/year) for five years. An NRCS
range conservationist was hired with 319(h) funds ($163,000) to manage the
range and farm land improvement program. Cooperative Extension has also
received a grant to conduct detailed monitoring on a rangeland management
project in the watershed. The California National Guard, a major landowner in
the watershed, has contracted with the NRCS ($40,000) to develop a management
plan for grazing and road management on the base. State funding from the
Coastal Conservancy and the Department of Transportation has been used to
purchase a $1.45 million parcel of agricultural land on Chorro Creek, just up-
stream of the Morro Bay delta, which is being restored as a functioning flood
plain. Without the cooperation of these agencies and their financial resources, the
Section 319 project would be unable to implement BMPs or educate landowners
about nonpoint source pollution.

Twin Bridges, a major passage to Morro Bay which has undergone heavy sedi-
ment deposition and flooding, is being modified in conjunction with plans to
reroute South Bay Boulevard over Chorro Creek. Construction began in May of
1996 and will be completed before the winter rains.
OTHER PERTINENT INFORMATION
                               In addition to state and federal support, the Morro Bay watershed receives tremen-
                               dous support from local citizen groups. The Friends of the Estuary, a citizen
                               advocacy group, is invaluable in its political support of Morro Bay, including an
                               effort to nominate the Bay for the National Estuary Program. The Bay Founda-
                               tion, a nonprofit group dedicated to Bay research, funded a $45,000 study on the
                               freshwater influences on Morro Bay, developed a library collection on the Bay and
                               watershed at the local community college, and is actively cooperating with the
                               Morro Bay Section 319 National Monitoring Program project to develop a water-
                               shed GIS database. The Bay Foundation also recently purchased satellite photo-
                               graphs of the watershed, which will prove useful for the monitoring program
                               effort. The National Estuary Program, Friends of the Estuary, and the Bay Foun-
                               dation of Morro Bay are cooperating to develop a volunteer monitoring program
                               for the Bay itself. Ongoing volunteer efforts include water quality and habitat
                               monitoring.
                                                    41

-------
                                                                           Morro Bay Watershed, California
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Karen Worcester
Central Coast Regional Water Quality Control Board
81 Higuera St. Suite 200
San Luis Obispo, CA 93401-5427
(805) 549-3336, Fax (805) 543-0397

Thomas J. Rice
Soil Science Department
California Polytechnic State University
San Luis Obispo, CA 93407
(805) 756-2420, Fax (805) 756-5412
Internet: trice@oboe.calpoly.edu

Gary Ketcham
California Polytechnic State University
San Luis Obispo, CA 93407
(805) 756-2548

Scott Robbins
USDA-NRCS
545 Main Street, Suite Bl
Morro Bay, CA 93442
(805) 772-4391, Fax (805) 772-4398

Karen Worcester
Central Coast Regional Water Quality Control Board
81 Higuera St. Suite 200
San Luis Obispo, CA 93401-0397
(805) 549-3336, Fax (805) 543-0397

Thomas J. Rice
Soil Science Department
California Polytechnic State University
San Luis Obispo, CA 93407
(805) 756-2420, Fax (805) 756-5412
Internet: trice@oboe.calpoly.edu

Katie Kropp
Morro Bay National Estuary Program
81 Higuera Street, Suite 200
San Luis Obispo, CA 93401
(805) 549-3336, Fax (805) 543-0397
                                                 42

-------
                                   Connecticut

                Jordan Cove Urban Watershed
                                   Section 319
          National Monitoring  Program Project
Figure 7: Jordan Cove Urban Watershed (Connecticut) Project Location
                   43

-------
                                                    i Jordan Cove Urban Watershed, Connecticut
  D
 Legend
Building Square
Open Space
Slopes >20%
Wetland Boundary
Monitoring Locations
                                                     *&m«w\zjK.~.
                                                       •z^'jm.'*^

   URBAN WATERSHED PROJECT
          JOHN ALEXOPOOLOS
          ASSOC, PROF. Of LAND.  ARCH.
                        U OF CT
                                             AREA 8
                                              10- 56 ACRES
                                              17 UNITS
Figure 8: Water Quality Monitoring Stations for Jordan Cove Urban Watershed (Connecticut) Watershed

                                      44

-------
                                                                    Jordan Cover Urban Watershed, Connecticut
PROJECT OVERVIEW
                              The Jordan Cove watershed is located along the north or Connecticut side of the
                              Long Island Sound (Figure 7). Jordan Cove is a small estuary fed by Jordan
                              Brook; the estuary empties into Long Island Sound. Water quality sampling has
                              indicated that the Cove does not meet bacteriological standards for shellfish
                              growing and sediment sampling has revealed high concentrations (>20 ppm) of
                              arsenic. Also, short-term monitoring of bottom waters has documented depressed
                              levels of dissolved oxygen.

                              Land use in the 4,846-acre Jordan Brook watershed is mostly forests and wetlands
                              (74%) along with some urban (19%), and agricultural (7%) uses. The project is
                              located in a residential section of the watershed. The project plan is to develop a
                              10.6-acre area following traditional subdivision requirements and another 6.9-
                              acre area of housing using best management practices (BMPs). A third drainage
                              area consisting of 12 lots on 7 acre's, which was developed in 1988, will be used as
                              a control.

                              The project will incorporate the paired watershed monitoring design for the three
                              study areas. Monitoring will include precipitation, air temperature, and grab and
                              storm-event sampling for solids, nutrients, metals, fecal conform, and biochemical
                              oxygen demand (BOD). Additionally, monitoring of selected individual BMPs
                              will also be conducted.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
 Impairments
 Pre-Project
 Water Quality
 Current Water
 Quality Objectives
 Project Time Frame

 Project Approval
Water resources of concern are Jordan Brook, Jordan Cove estuary, and Long
Island Sound. The cove is a long and narrow estuary consisting of a 390-acre
inner cove and an 100-acre outer cove. Because the project will sample only
overland runoff, no water resource will be monitored.

The Jordan Cove estuary does not meet bacteriological standards for shellfish
growing. Sediment sampling has revealed high concentrations (>20 ppm) of
arsenic.

Semi-annual sampling at eight locations along Jordan Brook has documented
average concentrations  of total phosphorus less than 0.03 mg/1 and nitrate less
than 1 mg/1. Water samples from inner Jordan Cove have had fecal coliform
counts with a geometric mean ranging from 26 to 154 cfu/lOOml.

Retain sediment on site during construction and reduce nitrogen, bacteria, and
phosphorus export by 65, 85, and 40 percent, respectively. Maintain post-develop-
ment runoff peak rate and volume and total suspended solids load to pre-develop-
ment levels.

1996 to 2006

February, 1996
                                                   45

-------
                                                                  i Jordan Cove Urban Watershed, Connecticut
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorological Factors
Land Use
Pollutant Sources
The two developments designated as treatment watersheds combined cover about
17.5 acres and the residential control watershed is approximately 7 acres.

The average annual precipitation is 49.8 inches, including 35 inches of snowfall.
Soils on the study areas are mapped as Canton and Charlton, which are well-
drained soils (hydrologic soil group B). The surficial geology is glacial till and
stratified drift. Bedrock is composed of gneiss originating from Avelonia. Bedrock
is typically at a depth greater than 60 inches and the water table is located below
six feet.

Land use in the area to be developed using traditional requirements is currently
poultry farming; the area designated for development using BMPs is a closed-out
gravel pit. The control drainage area has  12 residential lots,  ranging in size from
15,000 square feet to 20,000 square feet, which were developed in 1988.

Primary pollutant sources are expected to be construction and later urban runoff
from residences.
INFORMATION, EDUCATION, AND PUBLICITY
                             Each household in the three study watersheds will be visited annually for the
                             purpose of obtaining survey information related to factors influencing nutrient and
                             bacteria losses. Interaction during these visits will help answer questions about
                             residents habits that affect nutrient and bacteria deposition and educate residents
                             about reducing nonpoint source pollution.
NONPOINT SOURCE CONTROL STRATEGY
Description
The management practices will be applied to the BMP treatment drainage area
only and will vary with two time phases. The first phase will be during construc-
tion (18 months). During this phase, nonstructural practices such as phased
grading, immediate seeding of stockpiled topsoil, maintenance of a vegetated open
space perimeter, and immediate temporary seeding of proposed lawn areas and
structural practices, including sediment detention basins and sediment detention
swales, will be employed.

Post-construction practices will include street sweeping, implementation of
fertilizer and pesticide management plans, animal (pets) waste management, and
plant waste pick-up. Structural practices such as grass swales, detention basins,
roof runoff dry wells, gravel pack shoulders on access roads, and the minimization
of impervious surfaces will be used. The goal is to implement BMPs on 100% of
the lots in the BMP study area.
                                                46

-------
                                                                  Jordan Cover Urban Watershed, Connecticut
WATER QUALITY MONITORING
Design
Parameters
Measured
The study design is the paired watershed approach using two treatment and one
control watersheds. The calibration period will last for about one year during
which time current land use management will be continued. The treatment period
will include two phases: an 18-month construction phase and a long-term post
implementation monitoring phase.

Biological

Fecal coliform (FC)
                              Chemical and Other

                              Total suspended solids (TSS)
                              Total phosphorus (TP)
                              Total Kjeldahl nitrogen (TKN)
                              Ammonia (NHs)
                              Nitrate + nitrite (NOs + Mh)
                              Biochemical oxygen demand (BOD)
                              Copper (Cu), lead (Pb), and zinc (Zn)
 Sampling Scheme
 Covariates

 Runoff
 Precipitation
 Air temperature

 Flow-weighted composite samples will be collected during storm-events and
 analyzed for solids and nutrients. Bacteria and BOD analyses will be conducted
 on grab samples collected manually when flow is occurring during a visit to the
 site. Portions of storm samples will be saved and combined into a monthly com-
 posite sample that will be analyzed for metals.
   Monitoring Scheme for the Jordan Cove Urban Watershed 319 National Monitoring Program Project
Sites or
Design Activities
Primary
Parameters
Covariates
Frequency of
WQ Sampling
Frequency of
Habitat/Biological
Assessment
Duration
   Paired    BMP watershed       TSS        Rainfall
            Traditional watershed   TP         Air temperature
            Control watershed     TKN       Runoff
                               NHs
                               NO3+NO2
                            Storm-event
1 yr calibration
1.5 yr construction
7.5 yr post-BMP
 Water Quality Data
 Management and
 Analysis
 NPSMS Data
 Summary
 Water quality and land treatment data will be entered into the NonPoint Source
 Management System (NPSMS) software. Quarterly and annual reports will be
 prepared and submitted according to Section 319 National Monitoring Program
 procedures. Raw water quality data will be entered into STORET.

 Unavailable.
                                                 47

-------
                                                          i Jordan Cove Urban Watershed, Connecticut
TOTAL PROJECT BUDGET
                          The estimated budget for several elements of the Jordan Cove Urban Watershed
                          National Monitoring Program project for the life of the project is:
                          Project Element
                          Proj Mgt
                          I&E
                          LT
                          WQ Monit
                          TOTALS
                   Federal

                      NA
                      NA
                      NA
                   535,400
                   535,400
    Funding Source ($)
State      Local
                                                                              Sum
NA
NA
NA
NA
NA
NA
NA
15,000
NA
15,000
NA
NA
15,000
535,400
550,400
                          Source: Jack Clausen, Personal Communication (1996)
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                          Unknown.
OTHER PERTINENT INFORMATION
                          None.
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Information and
Education
Bruce Morton
Aqua Solutions
60 Burnside Drive
East Hartford, CT 06108
(860) 289-7664; Fax: (860) 289-7664

Joe Neafsey
USDA-NRCS
16 Professional Park Road
Storrs, CT 06268-1299
(860) 487-4017; Fax: (860) 487-4017 '

Jack Clausen
Univ. of Connecticut
Dept. of Natural Resources
1376 Storrs Rd., U87, Room 228
Storrs, CT 06238
(860) 486-2840; Fax: (860) 486-5408
Internet: jclausen@canrl .cag.uconn.edu

Chester (Chet) Arnold
Univ. of Connecticut
Cooperative Extension Service
P.O. Box 70
Haddam, CT 06438
(860) 345-4511

                48

-------
                                               Idaho

                         Eastern Snake River Plain
                                        Section 319
             National Monitoring Program Project
Figure 9: Eastern Snake River Plain (Idaho) Demonstration Project Area Location
                       49

-------
                                                                            Eastern Snake River Plain, Idaho
10
                                                                                         N
       Nevada
         Figure 10: Eastern Snake River Plain (Idaho) USDA Demonstration Project Area
                                               50

-------
                                                                              Eastern Snake River Plain, Idaho
PROJECT OVERVIEW
                              The Idaho Eastern Snake River Plain is located in southcentral Idaho in an area
                              dominated by irrigated agricultural land (Figure 9). The Eastern Snake River
                              Plain aquifer system, which provides much of the drinking water for approxi-
                              mately 40,000 people living in the project area, underlies about 9,600 square
                              miles of basaltic desert terrain. The aquifer also serves as an important source of
                              water for irrigation. In 1990, this aquifer was designated by the U.S. Environmen-
                              tal Protection Agency (USEPA) as a sole source aquifer.

                              Many diverse crops are produced throughout the Eastern Snake River Plain
                              region. Excessive irrigation, a common practice in the area, creates the potential
                              for nitrate and pesticide leaching and/or runoff. Ground water monitoring indi-
                              cates the presence of elevated nitrate levels in the shallow aquifer underlying the
                              project area.

                              The objective of a seven-year United States Department of Agriculture (USD A)
                              Demonstration Project within the Eastern Snake River Plain (1,946,700 acres)
                              (Figure 10) is to reduce adverse agricultural impacts on ground water quality
                              through coordinated implementation of nutrient and irrigation water manage-
                              ment. As part of the project, two paired-field monitoring networks (constructed to
                              evaluate best management practices (BMPs) for nutrient and irrigation water
                              management effects) are funded under Section 319 of the Clean Water Act.
 PROJECT DESCRIPTION
Water Resource
Type and Size
 Water Uses and
 Impairments
 Pre-Project
 Water Quality
In the intensely irrigated areas overlying the Eastern Snake River Plain aquifer,
shallow, unconfined ground water systems have developed primarily from irriga-
tion water recharge. Domestic water is often supplied by the shallow systems.
Within the project area, the general flow direction of the shallow ground water
system is toward the north from the river; however, localized flow patterns due to
irrigation practices and pumping effects are very common. This ground water
system is very vulnerable to contamination because of the 1) proximity of the
shallow system to ground surface, 2) intensive land use overlying the system, and
3) dominant recharge source (irrigation water) of the ground water.

Some wells sampled for nitrate concentrations have exceeded state and federal
standards for allowable levels. This occurrence of elevated nitrate concentrations
in the ground water impairs the use  of the shallow aquifer as a source of drinking
water. Low-level pesticide concentrations in the ground water have been detected
in domestic wells and are of concern in the project area. Both nitrate and potential
pesticide concentrations threaten the present and future use of the aquifer system
for domestic water use.

Ground water data collected and analyzed within the project area indicate the
widespread occurrence of nitrate concentrations that exceed state and federal
drinking water standards. In a study conducted from May through October 1991,
195 samples taken from 54 area wells were analyzed for nitrate. Average nitrate
concentrations were around 6.5 milligrams per liter (mg/1), with a maximum of
28 mg/1. The  federal Maximum Contaminant Level (MCL) for nitrate concentra-
tions of 10 mg/1 was exceeded in 16 % of the wells at least once during the sam-
pling period. Five percent of the wells yielded samples that continuously exceeded
the MCL during the sampling period.
                                                   51

-------
                                                                               Eastern Snake River Plain, Idaho
Current Water
Quality Objectives
Ninety-eight samples collected from the same 54 wells were analyzed for the
presence of 107 pesticide compounds. Fourteen of the 54 wells yielded samples
with at least one detectable pesticide present, but all concentrations measured
were below the federal Safe Drinking Water MCL or Health Advisory for that
compound. Even though the well water currently meets MCL standards, pesticide
concentrations are still believed to be a future concern for the Eastern Snake River
Plain Aquifer.

The overall USDA Demonstration Project objective is to decrease nitrate and
pesticide concentrations through the adoption of BMPs on agricultural lands.

Specific project objectives for the USEPA 319 National Monitoring Program
project are to:

•   Evaluate the effects of irrigation water management on nitrate-nitrogen
    leaching to the ground water. A paired-field study, referred to as "M" (Figure
    10), will allow a comparison of ground water quality conditions between
    regular irrigation scheduling and the use of a 12-hour sprinkler duration.

    Evaluate the effects of crop rotation on nitrate-nitrogen leaching to the
    ground water. A paired-field study, referred to as "F" (Figure 10), will allow
    a comparison of the amount of nitrogen leached to ground water as a result of
    growing beans after alfalfa, a practice that generates nitrogen, and the
    amount of nitrogen leached to ground water as a result of growing grain after
    alfalfa, a practice that utilizes excess nitrogen in the soil.

Source:  James Osiensky (Personal communication), 1993.
Modifications Since
Project initiation

Project Time Frame

Project Approval
An original objective was to compare the effects of sprinkler versus gravity
applied irrigation water on ground water nitrate-nitrogen concentrations, but was
deleted because project personnel felt that this information was already available.

October 1991 - October 1997

1992
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
The USDA Demonstration Project encompasses over 1,946,000 acres. The ground
water quality monitoring activities are limited to a 30,000-acre area of south
Minidoka County. The 319 National Monitoring Program project consists of two
sets of paired five-acre plots (a total of four five-acre plots) located in this 30,000-
acre area (Fields "M" and "F," see Figure 10). The paired fields were located in
the eastern and western portions of the area to illustrate BMP effects in differing
soil textures. The "M" field soils are silty loams. The "F" field soils are fairly
clean, fine to medium sands. Due to the differences in soils and the traditional
irrigation methods employed on these fields (flood on "M" and furrow on "F"),
the "M" field has relatively lower spatial variability of existing water quality than
the "F' field. The "F" field also shows greater influences of water and nutrient
movement from adjacent fields.

The average annual rainfall is between 8 and 12 inches. Shallow and deep water
aquifers are found within the project area. Because of the hydrogeologic regime of
the project area, there is a wide range of depths to ground water. Soils in the
demonstration area have been formed as a result of wind and water deposition.
                                                  52

-------
                                                                                Eastern Snake River Plain, Idaho
Land Use
Pollutant Sources
Modifications Since
Project Started
Stratified loamy alluvial deposits and sandy wind deposits cover a permeable layer
of basalt. Soil textures vary from silty clay loams to fine sandy loams. These soils
are predominantly level, moderately deep, and well drained.

In the project area, over 99% of the land is irrigated. Of the irrigated cropland, at
least 85% is in sprinkler irrigation and the other 15% is in furrow. A diversity of
crops are grown in the area: beans, wheat, barley, potatoes, sugar beets, alfalfa,
and commercial seed.

Within the USDA project area, there are over 1,500 farms with an average size of
520 acres. Nutrient management on irrigated crops is intensive. Heavy nitrogen
application and excessive irrigation are the primary causes of water quality
problems in the shallow aquifer system. In addition, over 80 different agrochemi-
cals have been used within the project area. Excessive irrigation may cause some
leaching of these pesticides into ground water (Idaho Eastern Snake River Plain
Water Quality Demonstration Project, 1991).

None.
INFORMATION,  EDUCATION, AND  PUBLICITY
 Progress Toward
 Meeting Goals
Presently, there is no plan to implement a separate information and education (I &
E) campaign for the 319 National Monitoring Program project. I & E for the
Snake River Section 319 National Monitoring Program project is included in the
Demonstration Project I & E program.

Two Eastern Snake River Plain Demonstration Project brochures have been
published. One brochure, targeting the local public, was designed to provide a
general explanation of the project. The second explains results from the nitrate
sampling of the project area.

A survey was conducted to gain insight into the attitudes of both the general
public and farmers. The results of this survey have been published.

Farmstead Assessment System and Homestead Assessment System (Farm*A*Syst/
Home*A*Syst), a wellhead protection program, have been added to the demon-
stration project. These programs will aid in ground water risk assessment for the
rural homeowner.

The USDA Demonstration Project staff continue to provide the I&E program for
this project. Weekly university articles are produced on the demonstration project.
Project information is disseminated through university and producer conferences.
Presentations on the project are made to the public through local and regional
outlets, such as the American Association of Retired Persons, Future Farmers of
America, and primary and secondary education institutions. In addition, a public
information workshop is held annually within the project area for project partici-
pants, cooperators, and interested individuals.

Presentations have also been made to local and regional agricultural producers,
local irrigation districts and canal companies, industry representatives, and
industiy supply vendors.
                                                   53

-------
                                                                               Eastern Snake River Plain, Idaho
                               Cooperating farm operations performing improved management practices for
                               water quality are marked by project display boards to maximize exposure to the
                               local population. These operations are also visited and displayed during the
                               numerous project organized field trips for targeted audiences.

                               Information has been disseminated through local and regional television and radio
                               programs and newspaper articles. ,
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Description
Modifications Since
Project Started
Progress Toward
Meeting Goals
The nonpoint source control strategy for the USDA Demonstration Project focuses
on nitrogen, pesticide, and irrigation water management practices that will reduce
the amount of nutrients and pesticides reaching surface water and leaching into
the ground water. The following BMP strategies are being implemented:

    Fertilizer evaluations and recommendations based on soil tests, petiole
    analysis, crop growth stage, crop type, rotation, and water sampling are being
    adopted.

    Farmers have been asked to incorporate pesticide management strategies into
    their farming practices.

    An irrigation management program has been implemented for each
    participating farm in the Demonstration Project.

The NPS control strategy for the 319 National Monitoring Program project is to
reduce applied water in the "F" field and to plant grain in the "M" field. Sugar
beets, potatoes, and grains are grown in the "M" field. Alfalfa, dry beans,  and
grains are grown in the "F" field.

The "M" paired field is being used to establish existing ground water baseline
conditions under a "wheel line" sprinkler system. After baseline conditions have
been established, the application rate of irrigation water to the "BMP" side of the
paired field will be limited to approximately half that of the control side.

Baseline conditions under  sprinkler-irrigated alfalfa production are being estab-
lished on the "F" paired field. After baseline conditions have been established, the
"BMP" side of the paired field will be planted in grain, while the "control" side of
the field will be planted in beans.

The design of the project has changed since its inception. Originally, the objective
of the "M" paired field was to determine the effect of irrigation water manage-
ment on nitrate-nitrogen leaching into the ground water. One side of the field was
to have a sprinkler irrigation system, while the other side was to have furrow
irrigation. However, cost share negotiations with the "M" field land owner for
project participation lead to implementation of the same irrigation water supply
system (sprinkler irrigation) in both the BMP test field and the control field.

Seventy-five farms currently have received direct technical and financial assis-
tance for BMP installation on their farm.

Both fields that are part of the Eastern Snake River Plain National Monitoring
Program project were converted to sprinkler from furrow and flood irrigation in
1993. Comparison demonstrations between sprinkler and gravity irrigation
systems are not occurring because project personnel feel that this information is
already available.
                                                   54

-------
                                                                                Eastern Snake River Plain, Idaho
                               Nonpoint source control strategy and design problems in the paired-field water
                               quality monitoring design are associated with coordination between project
                               personnel and producers. This occurs because landowners lack long term commit-
                               ments to production activity scheduling. Also, project staff have encountered
                               difficulty interacting with producers during the growing season because of the
                               heavy daily schedule of producers.

                               Changes in the type of crops produced and the production methods employed
                               during baseline monitoring have been detrimental to the experimental design. The
                               original objective of the "F" paired field was to compare water quality conditions
                               under different cropping regimes (alfalfa vs. beans). However, scheduled crop
                               rotations have been changed to meet commodity market demands on the "F" field.
                               Due to the changes in experimental design, the duration of the monitoring project
                               has been extended in order to re-establish baseline water quality data.

                               Additionally, adequate monitoring has been difficult to achieve. Weather or
                               available labor or equipment may cause a producer to perform unscheduled field
                               activities during a scheduled ground water sampling event. Monitoring informa-
                               tion obtained on spatial soil variability has led to installation of additional infield
                               instrumentation. The number and arrangement of the field instrumentation has
                               complicated production field work as producers are forced to manipulate produc-
                               tion equipment around monitoring instrumentation.

                               The dynamics of ground water quality monitoring of land use changes have
                               presented significant challenges. As the monitoring project proceeds, new infor-
                               mation is obtained, analyzed, and applied. The original monitoring design was
                               based on the best available understanding of the local ground water system.
                               Ground water quality information gained during baseline monitoring demon-
                               strated a high degree of spatial variability in the paired fields. In order to address
                               the spatial variability of the system and document ground water quality changes
                               resulting from land use, the monitoring system has been expanded to provide a
                               more intensive monitoring system based on a geostatistical evaluation of data
                               obtained. Sampling and maintenance of this more intensive system has required
                               more time and resources than originally planned.
WATER QUALITY MONITORING
Design
Modifications Since
Project Started
The 319 National Monitoring Program portion of the USD A Demonstration
Project incorporates two paired-field networks consisting of a total of 24 con-
structed wells. Of the 12 wells on each paired field, 8 wells are centrally located
"permanent" wells and 4 are peripheral "temporary" wells.

The scope of work has been increased significantly since the project started in
1992. The changes were required to facilitate evaluation of the effects of spatial
variability within the two paired fields. In addition to the original ground water
sample collection scheme for the 12 wells in each field, soil water and additional
ground water samples are being collected. Geostatistically-based soil water and
ground water sampling programs have been initiated. Soil water samples, taken
with suction lysimeters (soil water samplers), have been collected monthly during
the growing season at both the "F" and "M" paired fields. Permanent, pressure-
vacuum lysimeters (12 inch length) are installed to a depth of one meter below
land surface at the "F" field. A seasonal (removed and replaced each growing
season) sampling network that includes both vacuum lysimeters (24 inch length)
and pressure-vacuum lysimeters (12 inch length) is installed in the "M" field.
                                                    55

-------
                                                                                 Eastern Snake River Plain, Idaho
                               These lysimeters are installed at a depth of 0.5 meters below land surface. The soil
                               water sampling program provides important information for the interpretation of
                               spatial and temporal variability of the ground water samples collected from in-
                               field monitoring wells.

                               Twenty-three lysimeters were installed in the "F" field during June, 1994. Six
                               lysimeters were installed in the "M" field during July, 1994. The area! distribution
                               of lysimeters installed in 1994 was based on grain size analyses of soil samples
                               collected in the "F" and "M" fields.
Progress Toward
Meeting Goals

Parameters
Measured
Nitrate samples were collected from the lysimeters for the months of July, August,
September, and October, 1994. Basic univariate statistics were computed and a
preliminary geostatistical analysis was conducted. Based on these results, the
following modifications to the sampling plan were implemented for the 1995
growing season:

    Reduce the length of the shortest lags

    Increase the overall number of short lags produced by the sampling
    configuration

    Include a greater number of the original soil sample locations as lysimeter
    installation locations

Total Kjeldahl nitrogen was detected in a few wells during the first three years of
the project but did not appear to correlate with the nitrate concentrations mea-
sured. Nitrate was chosen as the primary constituent of interest as the indicator
parameter for evaluation of BMP effectiveness.

Baseline data are still being collected.
Biological

None
                                Chemical and Other

                                Nitrate (NOs)
                                pH
                                Temperature
                                Conductivity
                                Dissolved oxygen (DO)
                                Total dissolved solids (TDS)
                                Total Kjeldahl nitrogen (TKN) and Ammonium (NH+4)
                                Organic scans for pesticide

                                Covariates

                                Precipitation
                                Crop
                                Soil texture
                                Nutrient content of the irrigation water
                                                    56

-------
                                                                                Eastern Snake River Plain, Idaho
Sampling Scheme
A number of covariate monitoring activities have been undertaken by some of the
other agencies participating in the project. In addition, vadose zone suction
lysimeters are being used to monitor NOs transport. Well monitoring consists of
monthly grab samples. Chemical and other parameters are analyzed monthly,
except for NH+4 and TKN, which are analyzed quarterly, and organics, which are
analyzed semi-annually.
        Monitoring Scheme for the Eastern Snake River Plain Section 319 National Monitoring
        Program Project
Design
                      Site
Paired field    "M" field
     Primary
   Parameters
Covariates
                                                               Frequency of
                                                               WQ Sampling
                                                                                  Duration
                                   NOs
                                   PH
                                   Temperature
                                   Conductivity
                                   DO
                                   TDS
                                   TKN
                                   Pesticides
                     Precipitation
                     Crop
                     Soil texture
                     Nutrient content of
                     the irrigation water
                 Monthly for primary
                 pollutants except
                 Pesticides (sampled)
                 semiannually)
                 and Nitrogen
                 (quarterly)
                                                                                  4 yrs pre-BMP
                                                                                  lyrBMP
                                                                                  2 yrs post-BMP
Paired field "F" field


N03
pH
Temperature
Conductivity
DO
TDS
TKN
NH+4
Pesticides
Precipitation
Crop
Soil texture
Nutrient content of
the irrigation water


4 yrs pre-BMP
lyrBMP
2 yrs post-BMP



Modifications Since
Project Started

Water Quality Data
Management and
Analysis
 NPSMS Data
 Summary
None.
The Idaho Division of Environmental Quality is entering raw water quality data
in the USEPA STORET system. Data is also entered into the USD A Water Quality
Project's Central Data Base, and the Idaho Environmental Data Management
System. Because this is a ground water project, the NonPoint Source Management
System (NPSMS) software has limited utility.

This project is using geostatistical analysis to evaluate the influence of land use
activities on ground water quality. Geostatistics is the branch of applied statistics
that focuses on the characterization of spatial dependence of attributes that vary in
value over space (or time) and the use  of that dependence to predict values at
unsampled locations. The usefulness of a geostatistical analysis is dependent upon
the adequate characterization of the spatial dependence and of the parameter of
interest in the given environment. The degree to which spatial dependence is
characterized is a function of the configuration of the sampling locations. Thus, a
geostatistic investigation centers around designing an area! distribution of sam-
pling locations which ensures that spatial dependence of the parameter of interest
can be recognized if it exists. Geostatistical factors, which must be considered in
the design of a sampling plan, include the number of samples and the magnitude
and density of separation distances provided by a given configuration.

Not applicable.
                                                    57

-------
                                                                      Eastern Snake River Plain, Idaho
Modifications Since
Project Started

Progress Toward
Meeting Goals
None.
Baseline data are still being collected.
 TOTAL PROJECT BUDGET
                           The estimated budget for the Eastern Snake River Plain Section 319 National
                           Monitoring Program project for the period of FY 92-95:
                           Project Element

                           Proj Mgt
                           I&E
                           LT
                           WQ Monit
                           TOTALS
                                Funding Source ($)
Federal
NA
NA
NA
278,291
278,291
State
NA
NA
NA
NA
NA
Local
NA
NA
NA
NA
NA
Sum
NA
NA
NA
278,291
278,291
Modifications Since
Project Started
                           Source: Osiensky and Long, 1992; John Cardwell (Personal Communication, 1995)
None.
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                           None.
OTHER PERTINENT INFORMATION
                           The Eastern Snake River Plain Demonstration Project is led by the USDA Natural
                           Resources Conservation Service (NRCS), the University of Idaho Cooperative
                           Extension Service (CES), and the USDA Farm Service Agency (FSA). In addition
                           to the three lead agencies, this project involves an extensive state and federal
                           interagency cooperative effort. Numerous agencies, including the Idaho Division
                           of Environmental Quality, the University of Idaho Water Resource Research
                           Institute, the USDA Agricultural Research Service, the Idaho Department of
                           Water Resources, the U.S. Geological Survey, and the Idaho Department of
                           Agriculture, have taken on various project tasks.

                           The Idaho Department of Environmental Quality and the Idaho Water Resource
                           Research Institute are responsible for the 319 National Monitoring Program
                           portion of the project.

                           An institutional advantage of this project i%that the NRCS and the CES are
                           located in the same office.
                                            58

-------
                                                  Eastern Snake River Plain, Idaho
Three local Soil and Water Conservation Districts, East Cassia, West Cassia, and
Minidoka, as well as the Minidoka and Cassia County FSA, county committees,
and the Cassia County Farm Bureau make up the USDA Demonstration Project
Steering Committee.

A regional well monitoring network consisting of existing domestic sandpoint
(driven) wells has also been established within the Demonstration Project Area.
The regional network is intended to augment the paired-field data and provide a
means to document the influence of the Demonstration Project on the quality of
the area's shallow ground water system. This network consists of 25 wells which
have been monitored for nitrogen-nitrate concentrations on a quarterly basis for
an average of 12 sampling events.

During implementation of the regional domestic well water quality monitoring
portion of the USDA project, agricultural chemicals and nitrate-nitrogen have
been detected at levels of concern and measured in samples collected from domes-
tic wells. The herbicide Dacthal has been detected at low levels in samples col-
lected from one well during each sampling event. The same well yielded a single
sample with 2,4-D measured at 195 ppb. Other wells have yielded samples con-
taining nitrate-nitrogen as high as 30 mg/1. Concern generated by these data has
led to site-specific ground water investigations by the Idaho Division of Environ-
mental Quality and Idaho Department of Agriculture. The site-specific investiga-
tion demonstrated that the Dacthal contamination in the ground water originated
on-site. The elevated nitrate-nitrogen levels measured in samples obtained from
the site's monitoring network indicate that the nitrate-nitrogen concentration
measured in the ground water decreases as ground water moves from the adjacent
agricultural production fields toward the homestead.

The Mann-Kendall nonparametric statistical trend test was used to determine if a
significant trend exists in the concentration of nitrate-nitrogen measured in the
samples collected from these wells. Each data set was evaluated for the existence
of outliers using a standard T-test. Data outliers were removed from data sets
prior to subjecting the data to trend analysis. At the 90% confidence level, 9
(36%) of the wells show a statistically significant decreasing trend and 6 (24%)
show a decreasing trend at the 95% confidence level. One well (4%) shows an     !
increasing trend in nitrate-nitrogen concentrations measured in collected samples
from the well at both the 90 and 95% confidence levels. The remaining wells do
not show a statistically significant trend at the 90 or 95% confidence levels. In the
future, when adequate data points are available, the Mann-Kendall statistical
trend analysis will be used to analyze these data.

In addition, limited sampling and analyses of ground water drainage systems,
irrigation return flows, and injection wells have identified nutrients and pesticides
in certain surface water bodies within the project area. Nitrate-nitrogen concentra-
tions in subsurface tile drain effluent as high as 8 mg/1 have been measured. The
herbicides MCPA and 2,4-D were detected in return flow irrigation water entering
into an injection well. The 2,4-D was measured at levels greater  than the  allow-
able Safe Drinking Water MCL of 70 ppb.
                     59

-------
                                                                          Eastern Snake River Plain, Idaho
PROJECT CONTACTS
Administration
Water Quality
Monitoring
Land Treatment
information and
Education
Jeff Bohr
USDANRCS
1369 East 16th St.
Burley, ID  83318
(208) 678-7946; Fax (208) 678-5750

Charlie Bidondo
319 Program Coordinator
Division of Environmental Quality
1410 Hilton
Boise, ID  83706
(208) 373-0274; Fax (208) 335-0576

Dean Yashon
319 Program Coordinator
Division of Environmental Quality
1410 Hilton
Boise, ID  83706
(208) 373-0319; Fax (208) 335-0576

Jim Osiensky
Boise State University
Dept. of Geosciences
Boise, ID  83725
(208) 385-1308; Fax (208) 385-4061
Internet: josiensk@trex.idbsu.edu

Jeff Bohr
USDANRCS
1369 East 16th St.
Boise, ID  83318
(208) 678-7946; Fax (208) 678-5750

Randall Brooks
University of Idaho
Cooperative Extension
1369 East  16th St.
Burley, ID 83318
(208) 678-7946; Fax (208) 678-5750

Reed Findlay
University of Idaho
Cooperative Extension
1369 East  16th St.
Burley, ID 83318
(208) 678-7946; Fax (208) 678-5750
                                               60

-------
                                                                   Eastern Snake River Plain, Idaho
                           Snake  River  Plain
               Water  Quality  Demonstration   Project
                 Forgeon  Test  Field:  Burley   Idaho
           Lysimeter and Monitoring Well  Location Map
                                          FPNE
                                            •
                                         . 21V
                          FW4    7X
                             SX A*
  I.8X

  ex
FPW
                          FW1
                           *     A3X
                          A  A A
                        7G   5B
   4D
                                                           FPNW
                                                       11X ..A.12X
                                                                          FE4
                                                                           FE3
                                                                   J3M   12L
                                                                      A  A
                                                                           FE2
                                                                           FBI
                                                    FPS
                                                               T
                                                     (Instnment locations surveyed)
  Monitoring  Wells
  cojnpJeted at a depth ojf 30 ft.
  PE1,  FE2, PE3, PE4,
  FW1,  FW2, PW3, PW4,
  PPS,  PPW, FPNE, FPHW
Lysimeters
installed at a deptn of 3 ft'
1A to 23W
IX to 13X
                                  Field Map 1.
                                       61

-------
                                                                      Eastern Snake River Plain, Idaho
                            Snake   River   Plain
                Water  Quality  Demonstration  Project
                  Honour  Test  Field:  Hurley,   Idaho
            Lysimeter  and Monitoring Well  Location Map
 MPWN
 MPWS
             2Z
                        MW4
                        MW3
                        MW2
                        MW1
                                           IS
                                                       ME4
                                                       ME3
                                                       ME2
                                                   A   ME,
                                                                         MPEN
                                                                         MPES
                                                 (Inslrument loco lions ore approximate]
• Monitoring  Wells       A Lysimeters
  ocapleted at a depth of 10 ft.    installed at a depth of l.S ft
  MH1, KW2,  KW3, KW4,             1Z to 25Z
  ME1, MB2,  ME3, MEt,
  MEE3, MPEN, MPWS, MPWN
                                   Field Map 2.
                                        62

-------
                                  Illinois

                          Lake Pittsfield
                             Section 319
  National Monitoring Program Project
Figure 11: Lake Pittsfield (Illinois) Location
            63

-------
                                                                                        Lake Pittsfield, Illinois
                                                                                       Lake Pittsfield
Figure 12: Water Quality Monitoring Stations for Blue Creek Watershed and Lake Pittsfield (Illinois)
                                                  64

-------
                                                                                     Lake Pittsfield, Illinois
 PROJECT OVERVIEW
                              Lake Pittsfield was constructed in 1961 to serve as both a flood control structure
                              and a public water supply for the city of Pittsfield, a western Illinois community of
                              approximately 4,000 people. The 6,956.2-acre watershed (Blue Creek watershed)
                              that drains into Lake Pittsfield is agricultural. Agricultural production consists
                              primarily of row crops (corn and soybeans), and small livestock operations: hog
                              production, generally on open lots, and some cattle on pasture.

                              Sedimentation is the major water quality problem in Lake Pittsfield. Sediment
                              from farming operations, gullies, and shoreline erosion has decreased the surface
                              area of Lake Pittsfield from 262 acres to 219.6 acres in the last 33 years. Other
                              water quality problems are excessive nutrients and atrazine contamination. The
                              lake is classified as hypereutrophic, a condition caused by excess nutrients.

                              The major land treatment strategy is to reduce sediment transport into Lake
                              Pittsfield by constructing settling basins throughout the watershed, including a
                              large basin at the upper end of Lake Pittsfield. Water Quality Incentive Project
                              (WQIP) money, provided through the United States Department of Agriculture
                              (USDA) Farm Service Agency (FSA), is being used to fund conservation tillage,
                              integrated crop management, livestock exclusion, filter strips, and wildlife habitat
                              management. An information and education program on the implementation of
                              best management practices (BMPs) used to control sediment, fertilizer, and
                              pesticides is being conducted by the Pike County Soil and Water Conservation
                              District (SWCD).

                              The Illinois State Water Survey (ISWS) is conducting the Lake Pittsfield Section
                              319 National Monitoring Program project in order to evaluate the effectiveness of
                              the settling basins. Water quality monitoring consists of storm event tributary
                              sampling, lake water quality monitoring, and lake sedimentation rate monitoring.

                              Land-based data are being used by the ISWS to develop watershed maps of sedi-
                              ment sources and sediment yields using a geographic information system (GIS).
                              The data for the different GIS layers consist of streams, land uses, soils, lake
                              boundary, sub-watersheds, topography, and roads.
PROJECT DESCRIPTION
Water Resource
Type and Size

Water Uses and
Impairments
Pre-Project
Water Quality
Lake Pittsfield is a 219.6-acre lake located near the city of Pittsfield in Pike
County (western Illinois) (Figure 11).

Lake Pittsfield serves as the primary drinking water source for the city of
Pittsfield. Secondarily, the lake is used for recreational purposes (fishing and
swimming). Decreased storage capacity in Lake Pittsfield, caused by excessive
sedimentation, is the primary water quality impairment. Lake eutrophication and
occasional concentrations of atrazine above the 3 ppb Maximum Contaminant
Level (MCL) also impair lake uses.

Lake sedimentation studies have been conducted  four times (1974, 1979, 1985,
and 1992). Almost 15% of Lake Pittsfield's volume was lost in its first 13 years
(see table below).  An additional 10% of the lake's volume was lost in the next 18
years (1974 to 1992), suggesting that the rate of sedimentation has slowed. The
majority of the lake volume that has been lost is at the Blue Creek inlet into the
lake, which is in the northern portion of the lake.

                   65

-------
                                                                                    Lake Pittsfield, Illinois
                              Lake Pittsfield Sedimentation Studies.
Current Water
Quality Objectives
Modifications Since
Project Initiated

Project Time Frame
Year of
Survey
1961
1974
1979
1985
1992
Lake Age
(Years)

13.5
18.3
24.3
31.5
Lake
Volume
ac-ft MG
3563
3069
2865
2760
2679
1161
1000
933
899
873
Sediment
Volume
ac-ft MG

494
697
803
884

161
227
262
288
Original
Volume
Loss (%)

13.9
19.6
22.5
24.8
                              Source: Illinois Environmental Protection Agency, 1993
Project Approval
Long-term water quality monitoring data demonstrate that the lake has been, and
continues to be, hypereutrophic. In 1993, Lake Pittsfield's water quality was found
to exceed the Illinois Pollution Control Board's general use water quality stan-
dards for total phosphorus (0.05 mg/1). Total phosphorus standards of 0.05 mg/1
were exceeded in 70% of the samples taken. The 0.3 mg/1 standard for inorganic
nitrogen was exceeded in 60% of the water samples. Water quality samples
collected in 1979 had similar concentrations in terms of phosphorus and nitrogen.

The objectives of the project are to

•   reduce sediment loads into Lake Pittsfield and

    evaluate the effectiveness of sediment retention basins.

None.
March 1, 1993 - September 30, 1995 (Watershed)
September 1, 1992 - 1994 (Monitoring Strategy)
Note: Money for monitoring is approved yearly. Contingent upon funding, moni-
toring is expected to be continued through 1999. This will allow monitoring for a
period of four years past installation of sediment retention basins.

Initial water quality funding began in 1992 as a 319 Watershed Project. In 1994,
the project was approved for the Section 319 National Monitoring Program.
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
The 7,000-acre Blue Creek watershed that drains into Lake Pittsfield is located in
western Illinois (Figure 11). The terrain is rolling with many narrow forested
draws in the lower portion of the watershed. The topography of the upper portion
of the watershed is more gentle and the draws are generally grassed.

The area surrounding Lake Pittsfield receives approximately 39.5 inches of
rainfall per year, most of which falls in the spring, summer, and early fall. Soils
are primarily loess derived. Soils in the upper portion of the watershed developed
under prairie vegetation, while those in the middle and lower portions of the
watershed were developed under forest vegetation.

Some sediment-reducing BMPs are currently being used by area farmers as a
result of a program (Special Water Quality Project) that was started in 1979.  Pike
County SWCD personnel encouraged the use of terraces, no-till cultivation,
contour plowing, and water control structures. Many terraces were constructed

                   66

-------
                                                                                 Lake Pittsfield, Illinois
                             contour plowing, and water control structures. Many terraces were constructed and
                             most farmers adopted contour plowing. However, greater adoption of no-till and
                             other soil conserving BMPs is still needed.
                             Land Use
                             Agricultural
                             Forest/Shrub
                             Pasture/Rangeland
                             Residential
                             Reserroir/Farm Ponds
                             Roads/Construction
                             Park
                             TOTAL
                                                 48
                                                 21
                                                 20
                                                  2
                                                  4
                                                  2
                                                  3
                                                100
Pollutant Sources

Modifications Since
Project Started
Source:  Illinois Environmental Protection Agency. 1993. Springfield, IL.


Cropland, pasture, shoreline, and streambanks

None.
INFORMATION, EDUCATION, AND PUBLICITY
Progress Towards
Meeting Goals
Information and education is being conducted by a private organization (Farm
Bureau) and the Pike County SWCD. Two public meetings have been held to
inform producers about the project. Articles about the project have appeared in the
local newspapers. Currently, farmers are being surveyed about their attitudes on
water quality. This survey is being conducted by University of Illinois Extension
personnel.

Information and education activities are ongoing.
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Description
 Modifications Since
 Project Started
The nonpoint source control strategy is based on reducing sediment movement off-
site and limiting the transport of sediment into the water resource, Lake Pittsfield.

Section 319(h) funds have been used to build 29 small (approximately two acres
each) sediment retention basins. These basins are used to limit the transport of
sediment into Lake Pittsfield. In addition, a larger basin, capable of trapping 90%
of the sediment entering Lake Pittsfield at the upper end, is being constructed with
319(h)funds.

Funds from the Water Quality Incentive Program were used to encourage the
adoption of BMPs that will reduce the movement off-site of sediment, fertilizer,
and pesticides. These BMPs include conservation tillage, integrated crop manage-
ment, livestock exclusion, filter strips, and wildlife habitat management.

In order to reduce shoreline erosion, shoreline stabilization BMPs will be imple-
mented using Section 314 Clean Lakes Program funds. Old rip rap will be re-
paired, and new rip rap will be installed along the shoreline.

The contract for building sediment basins was extended to August 20, 1996,  due to
design modification and the permit process for the large sediment basin.
                                                67

-------
                                                                                    Lake Pittsfield, Illinois
Progress Towards
Meeting Goals
A total of 29 sediment basins and the large riprap basin have been completed. It is
estimated that these basins are reducing sediment delivery by 25-40%. The large
sediment basin has also been completed. All WQIP projects have been imple-
mented.
 WATER  QUALITY MONITORING
Design
Modifications Since
Project Started

Parameters
Measured
    Storm sampling at four stations on the main channel into Lake Pittsfield
    (Blue Creek) and three stations at major tributaries to Blue Creek (Figure 12).

    Trend monitoring during baseflow of Blue Creek at one station.

    Trend monitoring at the three stations located in Lake Pittsfield.

    Lake sedimentation studies were conducted before and after dredging and will
    be conducted again.

    A shoreline severity survey isibeing conducted. The results of this survey
    allow shoreline to be evaluated for erosion.

None.


Biological

None
                              Chemical and Other

                              Lake
                              Orthophosphate (OP)
                              Total phosphorus (TP)
                              Dissolved phosphorus (DP)
                              Total Kjeldahl nitrogen (TKN)
                              Nitrate + nitrite (NOs + NC-2)
                              Total suspended solids (TSS)
                              Volatile suspended solids (VSS)
                              pH
                              Total alkalinity
                              Phenolphthalein alkalinity
                              Specific conductivity
                              Water temperature
                              Air temperature
                              Dissolved oxygen (DO)
                              Atrazine

                              Storm Sampling (Stream)
                              Total suspended solids (TSS)

                              Single Station (Stream-Station C)
                              Total suspended solids (TSS)

                              Covariates

                              Rainfall
                                                68

-------
                                                                                          Lake Pittsfield, Illinois
Sampling Scheme
Storm sampling is being conducted at four stations located on Blue Creek (sta-
tions B, C, D, and H — see Figure 12). These stations are equipped with ISCO
automatic samplers and manual DH-59 depth-integrated samplers. A pressure
transducer triggers sampling as the stream rises. The samplers measure stream
height. In addition, the streams are checked manually with a gauge during flood
events to determine the stage of the stream. During these flood events, the stream
is rated to determine flow in cubic feet per second. Stream stage is then correlated
with flow in order to construct a stream discharge curve. Water samples are
analyzed to determine sediment ibads.

Three stations located on tributaries of either Blue Creek or Lake Pittsfield (sta-
tions E, F, and I - see Figure 12) are also being monitored during storm events.
Station I is equipped with an ISCO automatic sampler, while stations E and F are
sampled manually. Base stream flow is sampled monthly on Blue Creek at Site C
(see Figure 12).

Three lake sampling stations have been established in the most shallow portion of
the lake, the middle of the lake, and the deepest part of the lake. Water quality
grab samples are taken monthly from April through October.

In-situ observations are made for Secchi disk transparency and temperature and
dissolved oxygen profiles at 2-foot intervals in Lake Pittsfield.

In addition, water chemistry samples are taken from the surface of all three lake
stations, as well as the lowest depth at the deepest station, and analyzed for the
chemical constituents listed above (see Parameters Measured).

Rain  gauges have been placed near sampling sites C, D, and H (see Figure 12).
      Monitoring Scheme for the Lake Pittsfield Section 319 National Monitoring Program Project
Design
Storm
sampling
Single station
Single
station
Sites or
Activities
Stations B, C,
D,E,F,H,&I
Station C
Lake stations
1,2,&3
Primary
Parameters
TSS
TSS
Secchi disk transparency
DO
Covariates
Rainfall
Rainfall
Rainfall
Frequency
During storms
Monthly
Monthly,
April through
Duration
2 yrs pre-BMP
lyrBMP
3 yrs post-BMP
2 yrs pre-BMP
lyrBMP
3 yrs post-BMP
2 yrs pre-BMP
lyrBMP
       Lake
       sedimentation
       study
       Shoreline erosion
       severity survey
   OP
   TP
   NH3+NHfrt
   Ammonia nitrogen
   TKN
   NO3 + NO2
   TSS
   VSS
   PH
   Total alkalinity
   Phenolphthalein alkalinity
   Specific conductivity
   Water temperature
   Air temperature
   DO
   Atrazine
   Lake depth
                                                                          October
Prior to
dredging

Once
                                                     69

-------
                                                                                   Lake Pittsfield, Illinois
Modifications Since
Project Started

Water Quality Data
Management and
Analysis
      None.
      The water quality monitoring data are entered into a database and then loaded into
      the USEPA (U.S. Environmental Protection Agency) water quality data base,
      STORET. Data are also stored and analyzed with the USEPA NonPoint Source
      Management System (NPSMS) software.
NPSMS Data
Summary
Monitoring Station Parameters Report

PERIOD: Spring Season, 1995
STATION TYPE: Upstream Station

CHEMICAL, PARAMETERS

Parameter Name

FLOW, STREAM, INSTANTANEOUS, CFS
INSTANTANEOUS YIELD
PRECIPITATION, TOTAL
SEDIMENT, PARTICLE SIZE FRACT.
< .0625 MM % dry wgt,

STATION TYPE: Downstream Station
                       Parameter Name

                       FLOW, STREAM, INSTANTANEOUS, CFS
                       INSTANTANEOUS YIELD
                       PRECIPITATION, TOTAL
                       SEDIMENT, PARTICLE SIZE FRACT.
                       < .0625 MM % dry wgt.
                                                              PRIMARY CODE: Station C
                                                              Farm  Reporting
                                                              Type     Units

                                                               S      cfs
                                                               S      Ibs/sec
                                                               S      in/day
                                                               S      mg/L
                    QUARTILE VALUES
                   -75-   -50-    -25-

                    6.3    3.6     2.8
                  0.025  0.005   0.002
                   0.05   0.00    0.00
                    60    27      14
PRIMARY CODE: Station B

Farm   Reporting       QUARTILE VALUES
Type     Units       -75-   -50-    -25-
S
S
S
S
cfs
Ibs/sec
in/day
mg/L
8.9
.0.081
0.08
112
5.0
0.023
0.00
64
3.0
0.008
0.00
44
 Modifications Since
 Project Started
Progress Towards
Meeting Goals
       Included NPS national monitoring [tpypvp; for spring season at monitoring sites
       B and C, which includes 2 years of pre-BMP data, 1 year during BMP implemen-
       tation, and 3 years of sampling after BMP implementation.

       Data has been entered and analyzed.
 TOTAL PROJECT BUDGET
                              The estimated budget for the Lake Pittsfield Section 319 National Monitoring
                              Program project for the period of FY 92-99 is:
                              Project Element

                              Proj Mgt
                              I&E
                              LT[319(h)]
                              WQ Monit
                              Cultural Practices (WQIP)
                              Dredge/Shoreline/
                                Aeration (314 Clean Lakes)
                              TOTALS
                                                Funding Source (S)
Federal
NA
NA
620,100
470,000
32,000
132,110
State
NA
NA
NA
NA
NA
NA
Local
NA
NA
NA
NA
NA
904,000
Sum
NA
NA
620,100
470,000
32,000
1,036,110
                                  1,254,210     NA  904,000   2,158,210
                              Source:  State of Illinois, 1993; State of Illinois, 1992; Gary Eicken (Personal
                              Communication), 1995
                                                 70

-------
                                                                               Lake Pittsfield, Illinois
Modifications Since
Project Started
None.
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
Modifications Since
Project Started
In 1979, the Pike County SWCD began a Special Water Quality Project that
encouraged the implementation of terraces, no-till cultivation, contour plowing,
and water control structures. This project was instrumental, along with drier
weather conditions, in reducing soil erosion from an average of 5.8 tons per acre
to 3.3 tons per acre (a 45% decrease) from 1979 to 1994.

Section 314 funds have been used to install sediment-reducing shoreline BMPs
and one destratifier (aerator) in Lake Pittsfield to increase oxygen concentrations
throughout the lake, thereby increasing fish habitat The lake will be dredged in
late 1996 to reclaim the original capacity of the lake.

None.
OTHER PERTINENT INFORMATION
                            Many organizations have combined resources and personnel in order to protect
                            Lake Pittsfield from agricultural nonpoint source pollution. These organizations
                            are listed below:

                            •   USDAFSA

                                City of Pittsfield

                            •   Farm Bureau

                                Illinois Environmental Protection Agency

                                Illinois State Water Survey

                                Landowners

                                Pike County Soil and Water Conservation District
PROJECT CONTACTS
Administration
Land Treatment
Scott Tomldns
Illinois Environmental Protection Agency
Division of Water Pollution Control
2200 Churchill Road
Springfield, DL 62794-9276
(217) 782-3362; Fax (217) 785-1225

Brad Smith
Pike County Soil and Water Conservation District
1319 W.Washington
Pittsfield, IL 62363
(217) 285-4480
                                              71

-------
                                                                                   Lake Pittsfield, Illinois
Water Quality
Monitoring
Information and
Education
Donald Roseboom
Illinois State Water Survey
Water Quality Management Office
P.O. Box 697
Peoria, DL  61652
(309) 671-3196; Fax (309) 671-3106

Brad Smith
Pike County Soil and Water Conservation District
1319 W.Washington
Pittsfield, IL 62363
(217) 285-4480
                                                  72

-------
                                            Iowa

                          Sny Magill Watershed
                                     Section 319
           National Monitoring Program Project
                      Project Area
                  Iowa
Figure 13: Sny Magill and Bloody Run (Iowa) Watershed Project Locations
                    73

-------
                                                                    Sny Magill Watershed, Iowa
                                       Bloody Run


                                       Watershed
f      V "N
'       \    >
I  Morara  \   I
 N.       N  l-


 V.  \
    N»	X   \
                 BRSC
                                 / //  BR2
                                                             '\
                                                                L



                                                          Morquelte \
                                                    I  I
                                                     ,\J
                                                            MCSlBOOT
Scale x. ]
/ *
g 	 i /i
kilometers AC- _

0 1

mBes
Sny Magill
Watershed
Legend

• Weekly Monitoring Site
^ Monthly Monitoring Site

	 Pejennta) Stream
~~ "~ ~ ~ Intermittent Stream

,
•"~" — " Watershed Drained by
Gage Station

, — 	 Watershed Drained by
'^^-^ X *•-— ^'' ^^ (I
**^ X 1 / 1 \ \
/ N N / / / \ \
/ ^ ^ ///-- l — —^ \
I r<**-±U*C\ ( If ( / \
x>— -' rv^rM4 \ /^ /
— ' S x-"Y1|LlW I.I
\ '" ^X -^V -- / --, /
. ' '^ SNWF jm OgJI,' /'•''' /
xX A-iVkSN2 / M /
) — x^^-iRx, / \ /
1 v 1/7 ^\\ !/ ,
• s ±-< J \ 	 - ^=kNi i /
/ \ s / ,\ \ ' /
i>.«.ii> '• ^Ay
x ^^^* J V
^-_ ^ / v\
"-1 ; .^/ A
V / ,.' A / \
•N- /• I / \
\ ' \
N \ \
\ \
— — "^ Clauten ^
   Sampling Locattons
Figure 14:  Water Quality Monitoring Stations for Sny Magill and Bloody Run (Iowa) Watersheds

-------
                                                                                  Sny Magill Watershed, Iowa
PROJECT OVERVIEW
                               The Sny Magill Watershed Section 319 National Monitoring Program project is an
                               interagency effort designed to monitor and assess improvements in water quality
                               (reductions in sedimentation) resulting from the implementation of two U.S.
                               Department of Agriculture (USD A) land treatment projects in the watershed: Sny
                               Magill Hydrologic Unit Area (HUA) and the North Cedar Creek Water Quality
                               Special Project. The project areas include Sny Magill Creek and North Cedar
                               Creek basins  (henceforth referred to as the Sny Magill watershed) (Figure 14). Sny
                               Magill and North Cedar creeks are Class "B" cold water streams located in north-
                               eastern Iowa  (Figure 13). North Cedar Creek is a tributary of Sny Magill Creek.
                               The creeks, managed for "put and take" trout fishing by the Iowa Department of
                               Natural Resources (IDNR), are two of the more widely used recreational fishing
                               streams in the state.

                               The entire Sny Magill watershed is agricultural, with no industrial or urban areas.
                               There are no  significant point sources of pollution in the watershed. Land use
                               consists primarily of row crop, cover crop, pasture, and forest. There are about 120
                               producers in  the watershed, with farms averaging 275 acres in size.

                               Water quality problems result primarily from agricultural nonpoint source (NFS)
                               pollution; sediment is the primary pollutant. Nutrients, pesticides, and animal
                               waste are also of concern.

                               Two USDA land treatment projects implemented in the watershed support produc-
                               ers making voluntary changes in farm management practices that will result in
                               improved water quality. The State of Iowa, through the Iowa Department of Agri-
                               culture and Land Stewardship (IDALS) and the EDNR, have agreed to work
                               through the local Clayton County Soil and Water Conservation District (SWCD) to
                               provide funds for the best management practice (BMP) implementation. Sediment
                               control measures, water and sediment control basins, animal waste management
                               systems, stream corridor management improvements, bank stabilization, and buffer
                               strip demonstrations around sinkholes are being implemented to reduce agricul-
                               tural NFS pollution. A long-term  goal of a 50% reduction in sediment delivery to
                               Sny Magill Creek has been established.

                               A paired watershed approach is being used with the Bloody Run Creek watershed
                               serving as the comparison watershed (Figure 14). Subbasins within the Sny Magill
                               watershed are being compared using upstream/downstream stations.

                               Primary monitoring sites, equipped with U.S. Geological Survey (USGS) stream
                               gauges to measure discharge and  suspended sediment, have been established on
                               both Sny Magill and Bloody Run creeks. The primary sites and several other sites
                               on both creeks are being sampled for chemical and physical water quality param-
                               eters on a weekly to monthly basis. Annual habitat assessments are being con-
                               ducted along stretches of both stream corridors. Biomonitoring of
                               macroinvertebrates occurs on a bimonthly basis and an annual fisheries survey are
                               conducted.
                                                   75

-------
                                                                                 Sny Magill Watershed, Iowa
PROJECT DESCRIPTION
Water Resource
Type and Size

Water Uses and
Impairments
Pre-Project
Water Quality
Sny Magill and North Cedar creeks are Class "B" cold water streams located in
northeastern Iowa.

Sny Magill and North Cedar creeks are managed for "put and take" trout fishing
by the IDNR and are two of the more widely used streams for recreational fishing
in Iowa. Sny Magill Creek ranks sixth in the state for angler usage.

The Sny Magill watershed drains an area of 35.6 square miles directly into the
Upper Mississippi River Wildlife and Fish Refuge. The refuge consists of islands,
backwaters, and wetlands of the Mississippi River. The creek also drains into part
of Effigy Mounds National Monument. These backwaters are heavily used for
fishing and also serve as an important nursery area for juvenile and young large-
mouth bass.

The creeks are designated by the state as "high quality waters" to be protected
against degradation of water quality. Only 17 streams in the state have received
this special designation. The state's Nonpoint Source Assessment Report indicates
that the present classifications of the creeks as protected for wildlife, fish, and
semiaquatic life and secondary aquatic usage are only partially supported. The
report cites impairment of water quality primarily by nonpoint agricultural pollut-
ants, particularly sediment, animal wastes, nutrients, and pesticides. There are no
significant point sources of pollution within the  Sny Magill watershed.

Sediment delivered to Sny Magill creek includes contributions from excessive
sheet and rill erosion on approximately 4,700 acres of cropland and 1,600 acres of
pasture and forest land in the watershed. Gully erosion problems have been
identified at nearly 50 locations.

There are more than 13 locations where livestock facilities need improved runoff
control and manure management systems to control solid and liquid animal
wastes. Grazing management is needed to control sediment and animal waste
runoff from over 750 acres of pasture and an additional 880 acres of grazed
woodland.

Streambank erosion has contributed to significant sedimentation in the creeks. In
order to mitigate animal waste and nutrient problems and improve bank stability
in critical areas, improved stream corridor management designed to repair ripar-
ian vegetation and keep cattle out of the stream is necessary.

Water quality evaluations conducted by the University Hygienic Laboratory (UHL)
in 1976 and 1978 during summer low-flow periods in Sny Magill and Bloody Run
creeks showed elevated water temperatures and fecal conform levels (from animal
wastes) in Sny Magill Creek. Downstream declines in nutrients were related to
algal growth and in-stream consumption. An inventory of macroinvertebrate
communities was conducted in several reaches of the streams (Seigley et al.,
1992).

Assessments in North Cedar Creek during the 1980s by IDNR and the USD A
Natural Resources Conservation Service (NRCS) located areas where sediment is
covering the gravel and bedrock substrata of the streams,  decreasing the depth of
existing pools, increasing turbidity, and degrading aquatic habitat. Animal waste
decomposition increases biochemical oxygen demand (BOD) in the streams to
levels that are unsuitable for trout survival at times of high water temperature and
                                                   76

-------
                                                                              Sny Magill Watershed, Iowa
Current Water
Quality Objectives
 Modifications Since
 Project Initiation

 Project Time Frame
 Project Approval
low stream flows. The IDNR has identified these as the most important factors
contributing to the failure of brook trout to establish a viable population (Seigley
etal., 1992).

Several reports summarize pre-project water quality studies conducted in the two
watersheds (i.e., water quality, including available data from STORET - Seigley
and Hallberg, 1994; habitat assessment - Wilton, 1994; benthic biomonitoring -
Schueller et al., 1994, and Birmingham and Kennedy, 1994; fish assessment -
Wunder and Stahl, 1994, and Hallberg and others, 1994) provide perspectives on
water quality monitoring in northeast Iowa.

Project objectives include the following:

    To quantitatively document the significance of water quality improvements
    resulting from the implementation of the Sny Magill HUA Project and North
    Cedar Creek WQSP;

    To develop the protocols and procedures for a collaborative interagency
    program to fulfill the U.S. Environmental Protection Agency (USEPA)
    standards for Nonpoint Source Monitoring and Reporting Requirements for
    Watershed Implementation Projects;

•   To refine monitoring protocols to define water quality impacts and the
    effectiveness of particular management practices;

    To develop Iowa's capacity for utilization of rapid habitat and biologic
    monitoring;

    To use water quality and habitat monitoring data interactively with imple-
    mentation programs to aid targeting of BMPs, and for public education to
    expand awareness of the need for NFS pollution prevention by fanners; and

    To provide Iowa and the USEPA with needed documentation for measures of
    success of NFS control implementation (Seigley et al., 1992).

 Specific quantitative water quality goals need to be developed that are directly
 related to the water quality impairment and the primary pollutants being ad-
 dressed by the land treatment implemented through the USDA projects.
 None.
 1991 - unknown
 (approximately 10 years, if funding allows)

 1992
 PROJECT AREA CHARACTERISTICS
 Project Area
 Relevant Hydrologic,
 Geologic, and
 Meteorologic Factors
 The watershed drains an area of 22,780 acres directly into the Upper Mississippi
 River Wildlife and Fish Refuge and part of Effigy Mounds National Monument.

 Average yearly rainfall in the area is 30.6 inches.

 The watershed is characterized by narrow, gently sloping uplands that break into
 steep slopes with abundant rock outcrops. Up to 550 feet of relief occurs across the
 watershed. The landscape is mantled with approximately 10-20 feet of loess,
                                                 77

-------
                                                                                   Sny Magill Watershed, Iowa
Land Use
overlying thin remnants of glacial till on upland interfluves, which in turn overlie
Paleozoic-age bedrock formations. The bedrock over much of the area is Ordovi-
cian Galena Group rocks, which compose the Galena aquifer, an important source
of ground water and also drinking water in the area. Some sinkholes and small
springs have developed in the Ordovician-age limestone and dolomite.

The creeks are marked by high proportions (70-80% or more of annual flow) of
ground water base flow, which provides the cold water characteristics of the
creeks. Hence, ground water quality is also important in the overall water resource
management considerations for area streams.

The stream bottom of Sny Magill and its tributaries is primarily rock and gravel
with frequent riffle areas. Along the lower reach of the creek where the gradient is
less steep, the stream bottom is generally silty. The upstream areas have been
degraded by sediment deposition.

The entire watershed is agricultural, with no industrial or urban areas. There are
no significant point sources in the watershed. Sixty-five percent of the cropland is
corn, with the rest primarily in oats and alfalfa in rotation with corn. There are
about 120 producers in the watershed, with farm sizes averaging 275 acres.

Land use is variable on the alluvial plain of Sny Magill Creek, ranging from row
cropped areas, to pasture and forest, to areas with an improved riparian right-of-
way where the IDNR owns and manages the land in the immediate stream corri-
dor. The IDNR owns approximately 1,800 acres of stream corridor along
approximately eight miles of the length of Sny Magill and North Cedar creeks.
Some of the land within the corridor is used for pasture and cropping through
management contracts with the IDNR.

Row crop acreage planted to corn has increased substantially over the past 20
years. Land use changes in the watershed have paralleled the changes elsewhere
in Clayton County, with increases in row crop acreage and fertilizer and chemical
use, and attendant increases in erosion, runoff, and nutrient concentrations. U.S.
Forest Service data show a 4% decline in woodland between 1974 and 1982.
Much of this conversion to more erosive row crop acreage occurred without
adequate installation of soil conservation practices.
Land Use
                               Rowcrop
                               Cover crop, pasture
                               Forest, forested pasture
                               Farmstead
                               Other
                               TOTALS

                               Source: Bettis et al., 1994
Snv Magill
Acres %
5,842 25.9
5,400 23.9
11,034 48.9
263 1.2
28 0.1
Bloody Run
Acres %
9,344 38.6
6,909 28.5
7,171 29.6
415 1.7
376 1.6
                               22,567     100    24,215
100
Pollutant Sources
Modifications Since
Project Started
Sediment — cropland erosion, streambank erosion, gully erosion, animal
  grazing
Nutrients — animal waste from livestock facilities (cattle), pasture, and
  grazed woodland; commercial fertilizers; crop rotations
Pesticides — cropland, brush cleaning

Federal funding from the Agricultural Conservation Program to encourage BMP
implementation was lost in 1993; however, applications for alternative funding
sources were filed in 1994. Funding for sediment reducing practices, such as
terraces, was secured through the Iowa Department of Agriculture and Land
                                                   78

-------
                                                                                Sny Magill Watershed, Iowa
                              Stewardship, Division of Soil Conservation, for Fiscal Years 1995-1997. An
                              application for funding was filed through the USEPA Section 319(h) Program for
                              animal manure structures, Integrated Crop Management (ICM), and streambank
                              stabilization practices. The USEPA Section 319(h) funding became available in
                              1995.
INFORMATION, EDUCATION, AND PUBLICITY
 Progress Towards
 Meeting Goals
The focus of information and education efforts in the watershed are

•   Demonstration and education efforts in improved alfalfa hay management
    (to reduce runoff potential on hayland and increase profitability and acreage
    of hay production);

    Improved crop rotation management and manure management (to reduce
    fertilizer and chemical use);

    Implementation of the Farmstead Assessment System [NRCS, Iowa State
    University Cooperative Extension Service (ISUE)];

    Woodland management programs (to enhance pollution-prevention efforts
    on marginal cropland, steep slopes, riparian corridors, and buffer areas in
    sinkhole basins);

 •   Expansion of interest in the environmental and economic benefits of ICM,
    BMPs, and sinkhole and wellhead protection; and

    Implementation of an educational program to bring information and results
    of the Sny Magill HUA project to the widest possible audience in the
    watershed and adjacent areas of the state.

 Information is also disseminated through newsletters, field days, special meetings,
 press/media releases, surveys of watershed project participants, and summaries of
 the project available on the Internet (http://www.igsb.viowa.edu/htmls/inforsh/
 sny.html)

 Additional resources for technical assistance and educational programs are
 provided in the area through the Northeast Iowa Demonstration Project, directed
 by ISUE, and the Big Spring Basin Demonstration Project, directed by IDNR.

 Sny Magill water quality data have been used by the U.S. Army Corps  of Engi-
 neers Cold Regions Research and Engineering Laboratory to calibrate Object-
 BAWSER, a temperature index snowmelt model that can be used to demonstrate
 watershed hydrology.  The model is applicable to watersheds with different levels
 of development and can be used to show the effect of development on watershed
 hydrology.

 Through FY95, the following had been completed in Sny Magill and North Cedar
 Creek watersheds:

 •  Various management plots, including manure, nitrogen, tillage, and weed,
    have been maintained for demonstration and educational purposes in the
    watershed area.
    Numerous field days were held at plot sites designed to be toured on a self-
     guided basis.
     A series of articles on wellhead protection was published in local newspa-
     pers.
                                                  79

-------
                                                Sny Magill Watershed, Iowa
A baseline survey of farming practices for farm operators in the Sny Magill
Creek area was completed during the winter of 1992. In late summer, 1994,
a mid-project survey of Sny Magill participants was completed, as was a
baseline survey of Bloody Run watershed residents.

ICM plans were developed for 44% of cropland in the project area through
one-on-one meetings with farmers.

A soil bioengineering demonstration was conducted on a stretch of Sny
Magill Creek. The initiative centers on comparing the long-term stabilizing
effectiveness of various lower cost, more aesthetically pleasing streambank
stabilizing practices with the effectiveness of traditional practices such as rip
rap. The initiative served as a training workshop for agency personnel.
Representatives from the NRCS Midwest Technical Center (Lincoln, NE)
and the NRCS state office (Des Moines) provided technical support. The
streambank stabilization activity received excellent media coverage. A video
featuring the streambank stabilization demonstration was produced and at
least four other projects in Iowa have adopted similar streambank stabiliza-
tion programs based on the demonstration.

Manure fertility demonstrations were conducted at seven new cooperators'
farms to encourage growers to take full nutrient credit for manure applied.

A Family Education Fun Day was conducted in the watershed to give
landowners in the Sny Magill watershed and the people living in the nearby
town of McGregor a chance to meet agency representatives of the demonstra-
tion project and water quality monitoring project, to learn more about each
agency's involvement in the project, and to see what their neighbors are
doing to improve the water quality of Sny Magill Creek.

Private sector training was provided by ISUE coordinators to ag-business
firms and other individuals in order to transfer ICM services from Coopera-
tive Extension to the private sector. A major goal of the training project is
the development of ICM service providers to ensure that this management
practice is available after the project is no longer directly providing the ICM
service. There are now five ICM service providers as a result of this pro-
gram; previously there were none.

The media outreach program has included preparation of demonstration plot
brochures, press releases, booklets for the "self-guided" tours of the water-
shed, and articles for local newspapers. Water Watch, a bimonthly newsletter
published by Cooperative Extension, is disseminated to over 1,750 subscrib-
ers. Article topics have included upcoming project activities, ongoing
demonstrations and  other conclusions or trends that develop from these
efforts, chemical and biological rootworm control, well-water analyses,
proper use of soil testing, how various agronomic practices affect yields,
water quality monitoring results, results of producer case studies where
various ICM practices have been applied, farmstead assessment, and nutrient
management of manure.

An additional outreach program has been developed in the watershed. As the
result of soil bioengineering activities, the NRCS has produced two videos
that cover both ongoing and future streambank stabilization installations.
These videos have been used by various agencies and levels of government to
promote this technology.

The Clayton County Register, circulation 12,000, publishes an annual
conservation issue. The 1994 issue centered on the various components of
the Sny Magill HUA project activities. The subjects covered included: the
ICM program, timber stand improvement practices, water monitoring
programs, manure management techniques, and the proper handling and
disposal of agricultural chemicals and waste.
                80

-------
                                                                               Sny Magill Watershed, Iowa
                                 A manure management workshop was conducted to assist interested produc-
                                 ers in quantifying the potential nutrient benefits provided by the manure
                                 generated from their livestock operations. A manure management work sheet
                                 was developed as a simple method for farmers to use to determine how well
                                 manure nutrients are being credited and managed.

                                 Tours of the Sny Magill watershed and presentations on the Sny Magill
                                 HUA have included information on the water quality monitoring, tillage and
                                 manure structures, ICM, manure management, and nutrient and pest
                                 management.

                                 Participation in the program "CONNECTIONS: Linking Science and
                                 Mathematics with Careers" (a partnership between The University of Iowa
                                 Department of Pediatrics and the Cedar Rapids Community School District)
                                 led to the development of a video to help motivate high school girls and
                                 minorities to take more science and mathematics. In the video,  several
                                 locations in both the Sny Magill and Bloody Run watersheds were included,
                                 along with discussions about the design of the water quality monitoring
                                 project and the land treatment projects.


NONPO1NT SOURCE CONTROL  STRATEGY AND DESIGN
Description
The Sny Magill HUA project contains 10,468 acres of Highly Erodible Land
(HEL); conservation plans have been developed for all of these acres. Of these
conservation plans, 7,303 acres, or 70%, are written to the Tolerable, or T, level.
Conseivation plans have been fully implemented on 4,174 acres, or 40% of the
HEL acres in the project area. There are 98 landowners in the Sny Magill HUA,
of which 81% have chosen to participate in the HUA project.

The Section 319 National Monitoring Program, project is intimately connected to
two ongoing land treatment projects in the watershed: the Sny Magill Hydrologic
Unit Area project and the North Cedar Creek Agricultural Conservation Program
- Water Quality Special Project. The HUA Project was a five-year project begun in
1991 and covering 19,560 acres (86%) of the Sny Magill watershed. There are
verbal assurances that the HUA will be extended through FY99. The remainder of
the watershed is included in the WQSP, which began in 1988 and was completed
in 1994. The purpose of these projects has been to provide technical and cost
sharing assistance and educational programs to assist farmers in the watershed in
implementing voluntary changes in farm management practices that will result in
improved water quality in Sny Magill Creek.

No special critical areas have been defined for the HUA Project. Highly credible
land has been defined and an attempt is being made to treat all farms, prioritizing
fields within each farm to be treated first. Structural practices, such as terracing
and a few animal waste systems, are being implemented, as well as a variety of
management practices such as crop residue management and contour
stripcropping. Extension staff are assisting farmers with farmstead assessment and
with ICM, in the hope of reducing fertilizer and pesticide inputs by at least 25%
while maintaining production levels.

The WQSP has been completed. Practices implemented were primarily structural
(terraces). No ICM or other information and education programs were imple-
mented. Farmer participation was 80-85%.

The long-term sediment delivery reduction goal for Sny Magill Creek is 50%.
Fertilizer and pesticide inputs are expected to be reduced by more than 25%.
                                                 81

-------
                                                                                   Sny Magill Watershed, Iowa
Modifications Since
Project Started

Progress Towards
Meeting Goals
None.
Through FY95, the following NFS pollution controls were completed in North
Cedar Creek and Sny Magill Creek watersheds:

    287,645 feet of terraces

•   90 grade stabilization structures

    48 water and sediment control basins

    2 agricultural waste structures

    Nitrogen, phosphorus, and pesticide management on 3,428 acres. The more
    effective use or application of nitrogen, phosphorus, and pesticides in the
    Sny Magill watershed has resulted in a reduction of 144,992 pounds of total
    nitrogen, 70,076 pounds of total phosphorus, and in the amount of alachlor
    and atrazine applied.

    Water testing of 151 private wells

    Crop consultant model of ICM. (The model included nutrient and pest
    management planning sessions with cooperators, intensive soil sampling,
    nutrient and insecticide application equipment calibration and maintenance,
    and regular field observations during the growing season to monitor insects,
    weeds, and crop development. Twelve cooperators enrolled 2,750 acres in
    1994.)

A coalition of various federal, state, and county agencies has decided to work
together to develop, install, maintain, and evaluate a series of diverse stabilization
practices along certain stretches of the stream. The goal of this initiative is to pool
resources to develop more cost-effective, aesthetically pleasing, lower mainte-
nance forms of streambank stabilization.

ISUE conducted a baseline survey of farming practices of farm operators in the
Sny Magill Creek area in the winter of 1992. A mid-project survey of the farm
operators was completed in the summer of 1994 as was an initial survey of farm
operators in the Bloody Run Creek area ("control" watershed).

The IDNR-Geological Survey Bureau (GSB) has established a coordinated process
for tracking the implementation of land treatment measures with NRCS, Farm
Service Agency (FSA), and ISUE. NRCS is utilizing the "CAMPS" database to
record annual progress for land treatment and may link this to a geographic
information system (GIS), as well. ISUE conducts baseline farm management
surveys and attitude surveys among watershed farmers and has implementation
data from ICM - Crop System records. IDNR-GSB is transferring the annual
implementation records to the project GIS, ARC/INFO, to facilitate the necessary
spatial comparisons with the water quality monitoring stations.

Participating agencies meet in work groups as needed, typically on a quarterly
basis, to review and coordinate needs and problems. Monitoring results are
reviewed annually by an interagency coordinating committee to assess needed
changes.

Funding restrictions in the Sny Magill HUA for FY94 affected cost-share funding
to assist cooperating producers in installing BMPs. The HUA was able to operate
in FY94 on limited funding that remained from previous years. In FY95, alterna-
tive funding for land treatment was received from the Iowa Department of Agri-
culture and Land Stewardship - Division of Soil Conservation and the Iowa
Department of Natural Resources.
                                                    82

-------
                                                                               Sny Magill Watershed, Iowa
WATER QUALITY MONITORING
Design
Modifications Since
Project Started
 Parameters
 Measured
The Sny Magill watershed is amenable to documentation of water quality re-
sponses to land treatment. The cold water stream has a high ground water
baseflow which provides year-round discharge, minimizing potential missing data
problems. These conditions also make possible analysis of both runoff and ground
water contributions to the water quality conditions. Because of the intimate
linkage of ground and surface water in the region, the watershed has a very
responsive hydrologic system and should be relatively sensitive to the changes
induced through the land treatment implementation programs.

A paired watershed study compares Sny Magill watershed to the (control) Bloody
Run Creek watershed (adjacent to the north and draining 24,064 acres). Water-
shed size, ground water hydrogeology, and surface hydrology are similar; both
watersheds receive baseflow from the Ordovician Galena aquifer. The watersheds
share surface and ground water divides and their proximity to one another mini-
mizes rainfall variation.  However, the large size of the two watersheds creates
significant challenges in conducting a true paired watershed study. Land treat-
ment and land use changes were to a minimum in the Bloody Run Creek water-
shed throughout the project period and for the first two years of water quality
monitoring in the Sny Magill watershed.

Within the Sny Magill watershed,' subbasins are compared using upstream/
downstream stations.

None.

Biological

Fecal coliform (FC)
Habitat assessment
Fisheries survey
Benthic macroinvertebrates

 Chemical and Other

 Suspended solids (SS)
 Nitrogen (N)-series (NOs+NO2-N, NEU-N, Organic-N)
 Anions
 Total phosphorus (TP)
 Biological oxygen demand (BOD)
 Immunoassay for triazine herbicides
 Water temperature
 Conductivity
 Dissolved oxygen (DO)
 Turbidity
  Sampling Scheme
 Covariates

 Stream discharge
 Precipitation

 Primary monitoring sites (SN1, BR1) (Figure 14) are established on both Sny
 Magill and Bloody Run creeks. The sites are equipped with USGS stream gauges
 to provide continuous stage measurements and daily discharge measurements.
 Suspended sediment samples are collected daily by local observers and weekly by
 water quality monitoring personnel when a significant rainfall event occurs.

                    83

-------
                                                                                Sny Magill Watershed, Iowa
                             Monthly measurements of stream discharge are made at seven supplemental sites
                             (NCC, SN2, SNT, SNWF, SN3, BRSC, and BR2) (Figure 14).

                             Baseline data were collected during the summer of 1991. A report documenting
                             these data was published (Seigley and Hallberg, 1994). The monitoring program,
                             as described below, began in October of 1991.

                             Weekly grab sampling is conducted at the primary surface water sites (SN1, BR1)
                             for fecal coliform bacteria, N-series (NO3 +NO2-N, NH4-N, Organic-N), anions,
                             TP, BOD, and immunoassay for triazine herbicides.

                             Four secondary sites are monitored weekly (three on Sny Magill: SN3, SNWF, and
                             NCC; and one on Bloody Run: BR2).* Grab sampling is conducted for fecal
                             coliform, partial N-series (NO3 + NO2-N, NH4-N), and anions.

                             Weekly sampling is conducted by the USGS (weeks 1  and 3) and IDNR-GSB
                             (weeks 2,4, and 5).

                             Three additional  sites are monitored on a monthly basis (two on Sny Magill: SN2,
                             SNT; and one on Bloody Run: BRSC).* These are grab sampled for FC, partial N-
                             series, and anions.

                             Temperature, conductivity, DO, and turbidity are measured at all sites when
                             sampling occurs.

                             An annual habitat assessment is conducted along stretches of stream corridor,
                             biomonitoring of macroinvertebrates occurs on a bimonthly basis, and an annual
                             fisheries survey is conducted.

                             * Note: Originally,  site BRSC was monitored  weekly and site BR2 was monitored monthly.
                             However, after one water-year of sampling, the invertebrate biomonitoring group requested
                             (in March of 1992) that the sites be switched. Thus, since October 1, 1992, BRSC is
                             monitored monthly and BR2 is monitored weekly.
Monitoring Scheme for the Sny Magill and Bloody Run Watershed Section 319 National Monitoring
Program Project
Design
Paired
watershed
with
upstream/
downstream
stations (for
each creek)








Primary
Sites Parameters
Sny MagillT Habitat assessment
and Bloody Runc Fishery survey
Benthio macro-
invertebrates
SS
Nitrogen series
Anions
TP*
BOD*
Triazine herbicides*
Water temperature
Conductivity
DO
Turbidity
FC
Covariates
Stream discharge
(daily at sites
SN1&BR1;
monthly at
sites NCC, SN2,
SNT, SNWF,
SN3, BRSC,
BR2)

Stage
(continuous
atSNl.BRl)

Precipitation

Frequency of
Frequency of Habitat/Biological
WQ Sampling Assessment Duration
Weekly (for SNl,
BR1, SN3, SNWF,
NCC, BR2)
Monthly
(forSN2,SNT,
BRSC)









Habitat and
fisheries data
collected annually.
Macroinvertebrate
data collected
every two months.









lyrpre-BMP
6yrsBMP
2 yrs post-BMP












""^Treatment watershed
cControl watershed
* These parameters are only sampled at sites SNl and BR1
                                                 84

-------
                                                                                Sny Magill Watershed, Iowa
Modifications Since
Project Started

Water Quality Data
Management and
Analysis
None.
Data Management

Data management and reporting is handled by the IDNR - GSB and follows the
Nonpoint Source Monitoring and Reporting Requirements for Watershed Imple-
mentation Grants.

USEPA Nonpoint Source Management System (NPSMS) software is used to track
and report data to USEPA using four information "files": the Waterbody System
File, the NFS Management File, the Monitoring Plan File, and the Annual Report
File.

All water quality data are entered in STORET. Biological monitoring data are
entered into BIOS. All U.S. Geological Survey (USGS) data are entered in
WATSTORE, the USGS national database.

Data transfer processes are already established between USGS, UHL, and IDNR-
GSB. Coordination is also established with NRCS and ISUE for reporting on
implementation progress.

Data Analysis

For annual reports, data are evaluated and summarized on a water-year basis;
monthly and seasonal summaries are presented, as well.

Statistical analysis and comparisons are performed as warranted using recom-
mended SAS packages and other methods for statistical significance and time-
series analysis.

Paired watershed analysis has begun. In addition to the pairing between Sny
Magill and Bloody Run, and the intra-basin watersheds, data are being compared
with the long-term watershed records from the Big Spring basin. This provides a
temporal perspective on monitoring and a valuable frame of reference for annual
variations.

Water Year 1994 represented the third year of water quality monitoring. Hydro-
logically, Water Year 1994 marked the return of more typical conditions after the
heavy rains of 1993. Precipitation during Water Year 1994 was 100% of normal.
Annual mean discharge was 23.4 cfs for Sny Magill Creek and 26.1 cfs for Bloody
Run Creek.

Total suspended sediment loads declined from 1993  levels; total suspended
sediment load was 4,775 tons at SN1 and 3,117 tons at BR1. Water Year 1994
marked the first time during the three-year monitoring period that the annual
sediment load was greater for SN1 than BR1. The annual suspended sediment
load per unit drainage area was also greater for SN1, nearly twice as great as BR1.

For the three-year monitoring period, average nitrate concentrations were the
highest for Water Year 1994, and average triazine herbicide concentrations
 declined from 1993 levels.

 The fish species sampled were similar to those sampled during previous years.
Each watershed was dominated by a single species. A 1994 survey of several trout
 streams in northeast Iowa reported natural trout reproduction, including natural
                                                  85

-------
                                                                                   Sny Magill Watershed, Iowa
                               brook trout reproduction in North Cedar Creek, a tributary to Sny Magill Creek
                               and site of one of the land treatment programs. The habitat assessment showed a
                               predictable response to the lower, more stable, flow rates of 1994.

                               Overall, the benthic macroinvertebrate communities being sampled have remained
                               relatively constant. The HilsenhofF Biotic Index (HBI) and percent dominant taxa
                               metrics showed consistent trends in Sny Magill but not in Bloody Run. A decline
                               in the overall annual HBI values in Sny Magill suggests some improvement in
                               water quality that may not be occurring in Bloody Run creek. It is too early to
                               conclude that this improvement is the result of land treatment activities in the Sny
                               Magill watershed.
NPSMS Data
Summary
 Monitoring Station Parameters Report (FY94)

 STATION TYPE: Control Station

 CHEMICAL PARAMETERS

 Parameter Name
 FECAL COLIFORM, MEMBR FILTER, M-FC BROTH, 44.5 C
 FLOW, STREAM, MEAN DAILY, CFS
 NITROGEN, AMMONIA, TOTAL (MG/L AS N)
 NITROGEN, ORGANIC, TOTAL (MG/L AS N)
 PHOSPHORUS, TOTAL (MG/L AS P)
 PRECIPITATION, TOTAL (INCHES PER DAY)
 TEMPERATURE, WATER (DEGREES CENTIGRADE)

. STATION TYPE: Study Station

 CHEMICAL PARAMETERS

 Parameter Name
 FECAL COLIFORM, MEMBR FILTER, M-FC BROTH, 44.5 C
 FLOW, STREAM, MEAN DAILY, CFS
 NITROGEN, AMMONIA, TOTAL (MG/L AS N)
 NITROGEN, ORGANIC, TOTAL (MG/L AS N)
 PHOSPHORUS, TOTAL (MG/L AS P)
 PRECIPITATION, TOTAL (INCHES PER DAY)
 TEMPERATURE, WATER (DEGREES CENTIGRADE)
                    Annual Reports Detail
                                                                       Farm Reporting  QUARTILE VALUES
                                                                       Type  Units        -75-   -50-  -25-
                                                                       S                275    85   10
                                                                       S    CFS          28    24   20

                                                                       S                 0.4    0.2  <0.1
                                                                       S                 0.2    0.1  <0.1
                                                                       S                0.03     0    0
                                                                       S                 14    10    5
                                                                       Farm Reporting   QUARTILE VALUES
                                                                       Type Units        -75-   -50-  -25-
                                                                       S                300   110   18
                                                                       S    CFS          18   15.5   13
                                                                       S                <0.1   <0.1  <0.1
                                                                       S                 0.2   0.2  <0.1
                                                                       S                 0.2   <0.1  <0.1
                                                                       S                0.03     0    0
                                                                       S                 15    10    5

                                                                       Year: 1994
    Water Quality Parameter
    FECAL COLIFORM, MEMBR FILTER, M-FC BROTH CNTL  S   N
    FLOW, STREAM, MEAN DAILY, CFS            CNTL  S   Y CFS
    NITROGEN, AMMONIA, TOTAL (MG/L AS N)     CNTL  S   N
    NITROGEN, ORGANIC, TOTAL (MG/L AS N)      CNTL  S   N
    PHOSPHORUS, TOTAL (MG/L ASP)            CNTL  S   N
    PRECIPITATION, TOTAL (INCHES PER DAY)      CNTL  S   Y
    TEMPERATURE, WATER (DEGREES CENTIGRADE) CNTL  S   N
    FECAL COLIFORM, MEMBR FILTER, M-FC BROTH STD Y  S   N
    FLOW, STREAM, MEAN DAILY, CFS            STDY  S   Y CFS
    NITROGEN, AMMONIA, TOTAL (MG/L AS N)     STDY  S   N
    NITROGEN, ORGANIC, TOTAL (MG/L AS N)      STDY  S   N
    PHOSPHORUS, TOTAL (MG/L ASP)            STDY  S   N
    PRECIPITATION, TOTAL (INCHES PER DAY)      STDY  S   Y
    TEMPERATURE, WATER (DEGREES CENTIGRADE) STDY  S   N
                         State Farm Exp     SEASON 1     SEASON2   SEASONS   SEASON4
                         Type Type Var Units <-High  Low->.  <-HjghLow-> <-High Low-> <-High Low->
62
13
2
3
15


82
13
7
1
15

1
23

3

77
3
1
4


12
77
3
12
5

8
10

8
8
5

6


8
1
2 12
13
1
3
21
2
4
1 44
13
2
2
21
2
27

3
5
69
2

15


10
69
1
11
21 30

9
5

4 7
2 11
27 4

11


2 10
6
9
13
1
4
24
9
4
78
13
5
4
24
8
2 5
33 44 5

7
3
67
2
1
13


9
67
3

5
6

1
6 2


8


2
5
13
13
1
1
26
11
8
56
13
5
2
26
12
6
28

5
2
66
2
3
20


10
66
1
2
50

7
9


2
16

8



                                                    86

-------
                                                                         Sny Magill Watershed, Iowa
Modifications Since
Project Started

Progress Towards
Meeting Goals
None.
The USEPA nonpoint source monitoring and reporting requirements for water-
shed implementation grants have been completed for the data from Water Years
1992,1993, and 1994. Technical reports on data from water years 1992 and 1993
(Seigley et al., 1994), and water year 1994 (Seigley et al., 1996) have been com-
pleted.
TOTAL PROJECT BUDGET
                            Estimated budget for the Sny Magill Watershed Section 319 National Monitoring
                            Program project for the period FY91-95:
                            Project Element

                            I&E
                            LT (cost share)
                            LT (technical assist.)
                            WQ Monit
                            TOTALS
                    Federal
                    250,000
                    374,000
                    500,000
                   *385,100
Funding Source (S)
    State     Local
  125,000       NA
   70,325       NA
      NA       NA
      NA
                  1,509,100    195,325
NA
   Sum
375,000
444,325
500,000
385,100
                NA    1,704,425
Modifications Since
Project Started
                            * from Section 319 National Monitoring Program funds
                            Source: Lynette Seigley (personal communication, 1996)
Funding restrictions in the Sny Magill HUA for FY94 affected cost-share funding
to assist cooperating producers in installing BMPs. The HUA was able to operate
in FY94 on limited funding that remained from previous years. The project
applied for alternate funding to meet the unmet needs of producers to install
BMPs and funding was received from the Iowa Department of Agriculture and
Land Stewardship - Division of Soil Conservation and the Iowa Department of
Natural Resources.
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
Modifications Since
Project Started
Please refer to the section entitled Nonpoint Source Control Strategy.

None.
OTHER PERTINENT INFORMATION
                            Agencies participating in the Sny Magill Section 319 National Monitoring Pro-
                            gram project and their roles are listed below:

                               Clayton County USDA Farm Service Agency Committee
                               Iowa State University Extension
                               Iowa Department of Agriculture and Land Stewardship
                               Iowa Department of Natural Resources
                                             87

-------
                                                                             Sny Magill Watershed, Iowa
                                University of Iowa Preventive Medicine

                                Natural Resources Conservation Service

                                University Hygienic Laboratory

                                U.S. Forest Service

                                U.S. Fish and Wildlife Service

                                U.S. Geological Survey

                                U.S. National Park Service

                                U.S. Environmental Protection Agency
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
 Information and
 Education
Lynette Seigley
Geological Survey Bureau
Iowa Department of Natural Resources
109 Trowbridge Hall
Iowa City, IA 52242-1319
(319) 335-1575; Fax (319) 335-2754
Internet: lseigley@gsbth-po.igsb.uiowa.edu

Jeff Tisl (Land Treatment for the HUA Project)
USDA-NRCS
Elkader Field Office
117 Gunder Road NE
P.O. Box 547
Elkader, IA 52043-0547
(319) 245-1048; Fax (319) 245-2634

Lynette Seigley
Geological Survey Bureau
Iowa Department of Natural Resources
109 Trowbridge Hall
Iowa City, IA 52242-1319
(319) 335-1575; Fax (319) 335-2754
Internet:  lseigley@gsbth-po.igsb.uiowa.edu

Eric Palas (I&E for the HUA Project)
Sny Magill Watershed Project
111 W. Greene Street
P.O. Box 417
Postville, IA 52162-0417
(319) 864-3999; Fax (319) 864-3992
                                                88

-------
                                       Iowa

                              Walnut Creek
                                Section 319
     National Monitoring Program Project
         Iowa
          Project Area
                 O
Figure 15: Walnut Creek (Section 319) Project Location
               89

-------
                                                                Walnut Creek, Iowa
                                        Colfax
        Squaw Greek
           Basin
      Legend
4i   Gaging stations and surface water sampling points
X   Surface water sampling points
©   Wells
Rl   BjOmonjtpring stations
Figure 16: Water Quality Monitoring Stations for Walnut Creek (Iowa)
                              90

-------
                                                                                       Walnut Creek, Iowa
PROJECT OVERVIEW
                               The Walnut Creek Watershed Restoration and Water Quality Monitoring Project
                               began in April, 1995, and is designed as a nonpoint source (NFS) monitoring
                               program in relation to the watershed habitat restoration and agricultural manage-
                               ment changes implemented by the U.S. Fish and Wildlife Service (USFWS) at
                               Walnut Creek National Wildlife Refuge and Prairie Learning Center (WNT) in
                               central Iowa. The watershed is being restored from row crop to native prairie.

                               There are two components to the land use changes being implemented by USFWS:
                               ecosystem resources restoration to prairie/savanna and mandatory (contractual) use
                               of improved agricultural management practices on farmlands prior to conversion.
                               The majority of the Refuge area will be seeded to tall-grass prairie with savanna
                               components where applicable. In the riparian areas, 100 foot-wide vegetative filter
                               strips will be seeded along all of the streams in the Refuge that are not allowed to
                               revert to wetlands. Riparian and upland wetlands will also be restored or allowed
                               to revert to wetlands by the elimination of tile lines.

                               Cropland management within the WNT Refuge is also controlled by the USFWS
                               management team. Farming is done on a contractual,  cash-rent basis, with various
                               management measures specified; some are flexible, some more prescriptive. The
                               measures include soil conservation practices; nutrient management through soil
                               testing, yield goals, and nutrient credit records; and integrated pest management.
                               Crop scouting for pest management is mandatory for all farms on Refuge lands, as
                               are no-till production methods. Insecticide use is highly restricted and herbicide
                               use is also controlled in order to minimize adverse impacts on non-target plants
                               and animals.

                               The project will use a paired watershed approach as well as an upstream/down-
                               stream assessment. The treatment watershed is Walnut Creek, the paired site is
                               Squaw Creek.  Both watersheds are primarily agricultural dominated by row crop,
                               mainly corn and soybeans. Although no specific water quality objectives have been
                               set for this project, the intent of the USFWS is to restore the area to pre-settlement
                               conditions. In general, the decrease in active row crop agriculture should lead to
                               reductions in nutrients and pesticides in Walnut Creek.

                               Three gaging stations for flow and sediment have been established, two on Walnut
                               Creek and one on Squaw Creek. Both creeks will be monitored for biological and
                               chemical parameters. Both the main creek and tributaries are included in the
                               sampling scheme.
PROJECT DESCRIPTION
Water Resource
Type and Size

Water Uses and
Impairments
Walnut Creek and Squaw Creek are warmwater streams located in central Iowa.
Walnut Creek and Squaw Creek are designated under the general use category. No
designated use classification has been assigned to Walnut Creek.

Walnut Creek drains into a segment of the Des Moines River that is classified as
Not Supporting its designated uses in the Iowa Department of Natural Resources'
(IDNR) water quality assessments; Squaw Creek and the Skunk River are classi-
fied as Partially Supporting. Assessments in this area cite agricultural NFS as the
principal concern.
                                                  91

-------
                                                                                       Walnut Creek, Iowa
Pre-Project
Water Quality
Current Water
Quality Objectives
Walnut and Squaw creeks are affected by many agricultural NFS water pollutants,
including sediment, nutrients, pesticides, and animal waste. Water quality in these
streams is typical for many of Iowa's small warmwater streams: water quality
varies significantly with changes in discharge and runoff. Streambank erosion has
contributed to significant sedimentation in the creeks.

Three pre-project water quality studies were completed. Data were collected
during the pre-implementation period by the US Fish and Wildlife Service in
1991. The Tri-State Monitoring Project collected data in the Walnut Creek basin
from 1992 to 1994. Two sets of storm event samples were collected in 1995.

In 1991, nitrate-nitrogen concentrations ranged from 14 to 19 mg/1 with a mean
of 16. Atrazine concentrations were from 0.24 to 1.2 ug/1.  The Tri-State data were
similar, with nitrogen from 5 to 44 mg/1, averaging 14.5 mg/1 and atrazine from
0.1 to 2.7 ug/1. The event sampling in 1994 had fewer samples, but nitrogen
ranged from 2.1 to 11.0 mg/1 (avg. 6.1) in Walnut Creek and from 0.1 to 20 (avg.
10.0) in the tributaries. Atrazine in the main stem of Walnut Creek ranged from
<0.1 to 0.3 ug/1 and was higher in the tributaries (up to 3.1 ug/1).

Primary biological productivity is low and the condition of the fish community is
poor.

Maintain or exceed water quality criteria for general use waters. The long-term
goal of the US Fish and Wildlife Service is to restore this area to pre-settlement
conditions.
Project Time Frame

Project Approval
April, 1995 to September, 1998

April, 1996
PROJECT AREA  CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorological Factors
 Land Use
The project area, located in central Iowa (Figure 15), consists of a total of 24,570
acres. The Walnut Creek Basin is the treatment watershed (12,860 acres) and the
Squaw Creek Basin (11,710) is the control watershed (Figure 16). Both creeks
have been channelized in part. Both are characterized by silty bottoms and high,
often vertical, banks. Deposition of up to 4 feet of post-settlement alluvium is not
uncommon.

The total project area is located in the Southern Iowa Drift Plain, an area charac-
terized by steeply rolling hills and well-developed drainage. Dominant soils are
silty clay loams, silt loams, or clay loams formed in loess and till. Average annual
rainfall for the project area is approximately 32 inches.
                               1995 land use data:
                                 Corn
                                 Beans
                                 Other harvested crops
                                 Grass
                                 Forest
                                 Other
                                                      Walnut Creek  Squaw Creek
37.3
28.4
 4.3
21.1
 2.4
 6.5
                                          42.3
                                          32.0
                                          11.3
                                           7.4
                                           2.3
                                           4.7
                                                   92

-------
                                                                                      Walnut Creek, Iowa
Pollutant Sources
Sediment — streambank erosion, cropland erosion, gully erosion, animal grazing
Nutrients — crop fertilizers, manure
Pesticides — cropland
INFORMATION, EDUCATION, AND PUBLICITY
                              The WNT's educational commitment and resources will allow for educational and
                              demonstration activities far beyond the scope of those that could typically be
                              accomplished by 319 projects. Of particular note, the linkages between land use
                              changes and water quality improvements will be an integral part of these educa-
                              tional efforts. In addition, existing curriculum creates opportunities for interested
                              visitors to acquire, enter, and interpret hydrologic and water quality data from the
                              watershed. Both streamside and visitor center-based activities and educational
                              stations are planned. Information presentations could readily be tailored to school,
                              environmental, or agricultural interest groups. It is anticipated that visitors to the
                              WNT will number in the tens of thousands annually, offering a uniquely wide
                              exposure of residents to the land use changes and monitoring activities in the
                              watershed.

                              USFWS will utilize the WNT as a demonstration area for landscape restoration
                              projects. Information will be disseminated to visitors and invited groups, the
                              public (through published reports), and the news media. Of broader interest, the
                              project is also serving as a demonstration site for riparian restoration and small
                              wetland restoration. Having a linked water quality evaluation program makes
                              these demonstrations more effective for general use and translation to a broader
                              audience.

                              Several tours were provided in 1996 to teacher groups, natural history organiza-
                              tions, and surrounding landowners. The visitor center will open in the spring of
                              1997.
 NONPOINT SOURCE CONTROL STRATEGY
 Description
 The best management practices (BMPs) for row crop production include specific
 erosion control measures along with nutrient and pesticide management. The
 primary land treatment activity, however, is to remove 5,000 acres of cropland
 from production by converting it to native tall grass prairie. Wetlands and riparian
 zones will also be restored. Limited nutrient and pesticide management is ex-
 pected for the remainder of the Walnut Creek watershed.
 WATER QUALITY MONITORING
 Design
 A paired monitoring design will be used (Figure 16). For the paired watershed
 design, the outlets of Walnut Creek (treatment) and Squaw Creek (control) water-
 sheds will be monitored. Each watershed also has stations upstream and down-
 stream in order to differentiate natural processes from land use changes. Water
 quality will be compared before and after treatment to evaluate land treatment
 effectiveness.
                                                  93

-------
                                                                                      Walnut Creek, Iowa
Parameters
Measured
Biological

Fecal coliform (FC)
Macroinvertebrates
Fisheries
Sampling Scheme
Chemical and Other

Alkalinity
Ammonia (NHs)
Bentazon
Biochemical oxygen demand (BOD)
Bromide (Br)
Calcium (Ca)
Chloride (Cl)
Common herbicides
Dicamba
Dissolved oxygen (DO)
Fluoride (Fl)
Magnesium (Mg)
Nitrate (NOs)
Orthophosphate (OP)

PH           3
Phosphate (PO4 ")
Potassium (K)
Sodium (Na)
Specific conductivity
Sulfate (SO/f)
Suspended solids (SS)
Turbidity

Covariates

Precipitation
Water Discharge

The outlets at Walnut and Squaw Creeks are gaged, as is an upstream station on
the main stem of Walnut Creek. At these three stations, water discharge and SS
will be monitored daily, and data compiled for storm event statistical evaluation.

Ten stations are monitoring biweekly to monthly in March through My and
September. Four stations are sampled once in August, October, December, and
February. Additional event sampling is done throughout the year.
                                                 94

-------
                                                                              Walnut Creek, Iowa
 Monitoring Scheme for the Walnut Creek Section 319 National Monitoring Program Project
Sites or
Design Activities
Paired Watershed



Upstream/ Tributary to
Downstream Des Moines River


Primary
Parameters
NOs
OP
Turbidity
SS
N03
OP
Turbidity
SS
Frequency of
Frequency of Habitat/Biological
Covariates WQ Sampling Assessment Duration
Precipitation Monthly Annual
Water
Discharge
Storm events
Precipitation Monthly Annual
Water
Discharge
Storm events
Unknown



Unknown



Water Quality Data
Management and
Analysis
NPSMS Data
Summary
All United States Geological Survey (USGS) data will be reported in
WATSTORE, the USGS national database. The project will use ARCINFO for
land use changes. Statistical analyses on water quality data for trend detection will
be completed as deemed necessary. Water quality parameters and land use activi-
ties will be tracked using the NonPoint Source Management System (NPSMS)
software.

"Data management and reporting is-handled~by the Iowa Department of Natural
Resources Geological Survey Bureau (IDNR-GSB) and follows the Nonpoint
Source Monitoring and Reporting Requirements for Watershed Implementation
Grants. All water quality data are entered into STORET.

Unavailable.
TOTAL PROJECT BUDGET
                            The estimated budget for the Walnut Creek Section 319 National Monitoring
                            Program project for the life of the project is:
                            Project Element
                            Proj Mgt
                            I&E
                            LT
                            WQ Monit
                            TOTALS
                                     Funding Source (S)
                   Federal*

                    102,029
                      3,000
                        NA
                    330,300
                    435,329
USFWS
NA
NA
500,000
NA
500,000
State
113,196
1,000
NA
NA
114,196
Sum
215,225
4,000
500,000
330,300
1,049,525
                            *from Section 319 NMP funds
                            Source: Carol Thompson, 1996 (personal communication)
 IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                            None.
                                              95

-------
                                                                                 Walnut Creek, Iowa
 OTHER PERTINENT INFORMATION
                            Participating Agencies and Organizations:

                                Iowa Department of Natural Resources

                                U.S. Fish and Wildlife Service

                                U.S. Geological Survey — Water Resources Division

                            •   University of Iowa Hygienic Laboratory

                            •   Farm Service Agency

                                Iowa Department of Natural Resources — Environmental Protection Division
                            •   U.S. Environmental Protection Agency
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Carol A. Thompson
Iowa Department of Natural Resources
Geological Survey Bureau
109 Trowbridge Hall
Iowa City, IA 52242
(319) 335-1581; Fax: (319) 335-2754
Internet: cthompson@gsbth-po.igsb.uiowa.edu

Richard Birger
Walnut Creek National Wildlife Refuge and Prairie Learning Center
P.O. Box 399
Prairie City, IA 50228
(515) 994-2415; Fax: (515) 994-2104

Carol A. Thompson
Iowa Department of Natural Resources
Geological Survey Bureau
109 Trowbridge Hall
Iowa City, IA 52242
(319) 335-1581; Fax:  (319) 335-2754
Internet: cthompson@gsbth-po.igsb.uiowa.edu
                                              96

-------
                                    Maryland

                   Warner Creek Watershed
                                 Section 319
       National Monitoring Program Project
 Maryland
Figure 17: Warner Creek (Maryland) Watershed Project Location
                 97

-------
                                                             i Warner Creek Watershed, Maryland
  Legend
                                                                                 N
                                                                                 t
Figure 18: Water Quality Monitoring Stations for Warner Creek (Maryland) Watershed
                                       98

-------
                                                                          «Warner Creek Watershed, Maryland
PROJECT OVERVIEW
                              The Warner Creek watershed is located in the Piedmont physiographic region of
                              northcentral Maryland (Figure 17). Land use in the 830-acre watershed is almost
                              exclusively agricultural, primarily beef and dairy production and associated
                              activities.

                              Agricultural activities related to dairy production are believed to be the major
                              nonpoint source of pollutants to the small stream draining the watershed. A
                              headwater subwatershed, in which the primary agricultural activity is dairy
                              farming (treatment), will be compared to another subwatershed, in which the
                              primary agricultural activity is beef production (control).

                              Proposed land treatment for the treatment watershed includes conversion of
                              cropland to pasture, installation of watering systems, fencing to exclude livestock
                              from tributary streams, and the proper use of newly constructed manure slurry
                               storage tanks.

                               Water quality monitoring involves both paired watershed and upstream/down-
                               stream experimental designs. Sampling will occur at the outlets of the paired
                               watersheds (stations 1A and IB) and at the upstream/downstream stations (1C
                               and 2A) once per week (Figure  18). Storm-event sampling by an automatic
                               sampler will  occur at station 2 A. Water samples will be analyzed for sediment,
                               nitrogen, and phosphorus.

                               Warner Creek is a subtributary of the Monocacy River basin. Monitoring data will
                               be used to  evaluate the suitability of a modified version of the CREAMS and/or
                               ANSWERS model for its use in the larger Monocacy River basin.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
  Impairments

 Pre-Project
 Water Quality
  Current Water
  Quality Objectives
Warner Creek is a small stream with a drainage area of about 830 acres, all of
which are included in the study area. Its average discharge is 30 gallons per
minute. Warner Creek drains into a tributary that drains into the Monocacy River
basin.

The water resource has no significant use, except for biological habitat.
Seven weeks of pre-project water quality monitoring at four stations yielded the
following data:
                                Nitrate
                                (mg/1)
                                3.3-6.7
           Nitrite
           (mg/1)
           .01-.05
Ammonia
  (mg/1)
  0-23.0
TKN
(mg/1)
0-73.0
TKP    Orthophosphorus
(mg/l)         (mg/1)
0-6.7         0-3.6
                                Source: Shirmohammadi and Magette, 1993
 The objectives of the project are to
     develop and validate a hydrologic and water quality model capable of
     predicting the effects of agricultural best management practices (BMPs) on
     water quality, both at the field and basin scale;
                                                   99

-------
                                                                      i Warner Creek Watershed, Maryland
Project Time Frame

Project Approval
    collect water quality data for use in the validation of the basin-scale
    hydrologic and water quality model; and

•   apply the validated model to illustrate relationships between agricultural
    BMPs and watershed water quality in support of the USD A Monocacy River
    Demonstration Project.

May, 1993 - June, 1997

June, 1995
PROJECT AREA CHARACTERISTICS
Project Area

Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
Pollutant Sources
Approximately 830 acres.

The watershed is in the Piedmont physiographic province. Geologically, bedrock
in this area has been metamorphosed. Upland soils in the watershed belong to the
Penn silt loam series with an average slope of three to eight percent. Average
annual rainfall near the watershed is 44-46 inches.

Land use in the upper part (upstream of 1C) of the watershed is mostly pasture
and cropland, with a few beef and dairy operators. The subwatershed upstream of
station IB contains a dairy operation, and a recent survey indicated that about
sixty-five percent of the land was used for corn silage production. Downstream of
station 1C, land use is also mostly pasture and cropland, which is used to support
dairy and beef production.

The major sources of pollutants are thought to be the dairy operations and the
associated cropland. Pastures in which cows have unlimited access to the tributary
streams also contribute significant amounts of pollutants.
INFORMATION, EDUCATION, AND PUBLICITY
                             The project will draw support from University of Maryland Cooperative Extension
                             Service (CES) agents, the Natural Resources Conservation Service (NRCS) and
                             Frederick Soil Conservation District offices in Frederick, Maryland, and project
                             specialists located in the Monocacy River Water Quality Demonstration offices,
                             several of whom have already established lines of communication between water-
                             shed farmers and the local personnel of the relevant USD A agencies. Education
                             and public awareness will be accomplished through the CES in the form of tours,
                             press releases, scientific articles, and oral presentations.
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Description
Upstream/Downstream Study Area (1C and 2A):
BMPs planned for this area include construction of watering systems for animals,
fencing animals from streams, and the proper use of newly constructed manure
slurry storage tanks. Conversion of cropland to pasture is also anticipated in this
                             area.
                                               100

-------
                                                                      «Warner Creek Watershed, Maryland
                             Paired Watershed (IA and IB):
                             The implementation of BMPs in the treatment (IB) watershed is uncertain;
                             however, a concerted effort will be made to install an animal waste management
                             system and cropland conservation practices in this watershed.
WATER QUALITY MONITORING
Design
Parameters
Measured
The water quality monitoring component incorporates the following two designs:

    Upstream/downstream on Warner Creek

    Paired watersheds in the uppermost areas of the watershed

Chemical and Other

Ammonia (NEfe)
Total Kjeldahl nitrogen (TKN)
Nitrate + nitrite (NOa+NOj)
Nitrite (NOa)
Orthophosphate (OP)
Total Kjeldahl phosphorus (TKP)
Sediment
                             Covariates

                             Rainfall
                             Discharge: instantaneous (1A, IB and 1C) continuous (2A)

Sampling Scheme          Upstream/Downstream Study Area (1C and 2A) (Figure 18):
                             Type: grab (1C and 2A); automated storm event (2A)              __
                             Frequency and season: weekly from February to June and biweekly for the remain-
                             der of the year

                             Paired Watershed (1A and IB) (Figure 18):
                             Type: grab (1A and IB)
                             Frequency and season: weekly from February to June and biweekly for the remain-
                             der of the year
  Monitoring Scheme for the Warner Creek Watershed  Section 319 National Monitoring Program Project

Sites or
Design Activities
Paired




Upstream/ Warner
Downstream Creek




Primary
Parameters
NH3
TKN



NO3+NO2
NOa
OP
TKP
Sediment

Frequency of
Covariates WQ Sampling
Rainfall Weekly Feb. to
discharge June and bi-
weekly the
remainder of
the year





Frequency of
Habitat/Biological
Assessment Duration
? yrs. pre-BMP
?yrs.BMP
? yrs. post-BMP







                                               101

-------
                                                                     i Warner Creek Watershed, Maryland
Water Quality Data
Management and
Analysis

NPSMS Data
Summary
Monitoring data are stored and analyzed at the University of Maryland. In addi-
tion, data will be entered into the STORET data base and reported using the
Nonpoint Source Management System (NPSMS) software.


Nof available.

Data currently available: Average annual concentrations (mg/L) and associated
standard deviations (mg/L) and coefficient of variations (%) for nitrogen and
phosphorus constituents measured from grab samples at different stations (1 A,
IB, 1C, and 2A) in the Warner watershed.


NOs-N


TKN


NH4-N


PO4-P


TKP



1A
4.07
1.23
30
0.81
2.26
278
0.04
0.10
259
0.04
0.12
353
0.09
1.00
1111

IB
3.22
1.54
48
11.70
15.9
136
5.75
6.10
106
0.96
1.06
111
2.46
0.82
35
1993
1C
3.58
1.31
37
6.57
9.11
139
3.33
3.89
117
0.55
0.60
109
1.39
0.99
71

2A
4.17
1.75
42
1.69
2.72
161
0.35
0.65
187
0.23
0.15
66
0.70
1.69
241

1A
3.24
0.90
28
1.90
6.94
366
0.05
0.11
204
0.10
0.40
404
0.10
0.27
260
1994
IB 1C
3.02 3.06
1.55 1.00
51 33
11.20 6.44
12.94 5.96
116 93
7.22 3.67
8.99 4.56
124 ..124.
1.60 0.89
2.06 1.32
129 149
2.40 1.61
2.88 2.11
120 130

2A
2.98
1.63
55
3.66
4.38
120
1.16
2.00
_T72
0.49
0.72
147
0.90
1.42
159
1995
1A
3.23
1.01
31
0.114
0.25
181
0.02
0.03
156
0.02
0.02
118
0.04
0.07
156
IB
3.97
2.02
0.51
7.77
5.70
73
5.42
5.75
106
1.70
2.01
119
1.96
2.62
134
1C
3.69
1.33
36
5.78
5.17
89
2.88
3.05
106
0.88
1.01
115
0.94
1.20
128
2A
3.76
1.58
42
1.72
2.11
123
0.83
1.37
166
0.43
0.48
111
8.45
0.60
134
                               n = 31
                             n = 31
n=13
TOTAL PROJECT BUDGET
                             Project Element
                                            Year 1   Year 2   Year 3   Year 4   Year 5   Year 6
                             Monitoring
                              Personnel     $41,600  $32,500 $45,000  $49,000  $51,500  $54,500
                              Equipment    10,000    3,000     NA      NA      NA      NA
                              Other         26,733   35,938   37,140   34,190   35,215   36,445
                             TOTALS
               78,333   71,438   82,140   83,190   86,715   90,945
                             Source: FFY94 Work Plan (6/23/94).
                                              102

-------
                                                                   ' Warner Creek Watershed, Maryland
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                            The USDA Monocacy River Demonstration Watershed Project will facilitate the
                            dissemination of information gained from the project and help provide cost-share
                            funds for implementing BMPs.
OTHER PERTINENT INFORMATION
                            None.
PROJECT CONTACTS
Administration
Land Treatment
Adel Shirmohammadi
University of Maryland
Dept. of Biological Resources Engineering
1419 ENAG/ANSC Building (#142)
College Park, MD 20742-5711
(301)405-1185; Fax (301) 314-9023
Internet: as31@umail.umd.edu

William Magette
University of Maryland
Dept. of Biological Resources Engineering
1423 ENAG/ANSC Building (#142)
College Park, MD 20742-5711
(301) 405-1190; Fax (301) 314-9023
Internet: vvm3@umail.umd.edu

Elyzabeth Bonar-Bouton
Maryland Department of Natural Resources
Chesapeake and Coastal Watershed Service
Tawes State Office Building, E-2
Annapolis, MD 21401
(410) 974-2784; Fax (410) 974-2833

Adel Shirmohammadi
University of Maryland
Dept. of Biological Resources Engineering
1419 ENAG/ANSC Building (#142)
College Park, MD 20742-5711
(301)405-1185; Fax (301) 314-9023
Internet: as31@umail.umd.edu

William Magette
University of Maryland
Dept. of Biological Resources Engineering
1423 ENAG/ANSC Building (#142)
College Park, MD 20742-5711
(301) 405-1190; Fax (301) 314-9023
Internet: wm3@umail.umd.edu
                                             103

-------
                                                                       i Warner Creek Watershed, Maryland
Water Quality
Monitoring
Adel Shirmoharnmadi
University of Maryland
Dept. of Biological Resources Engineering
1419 ENAG/ANSC Building (#142)
College Park, MD 20742-5711
(301)405-1185; Fax (301) 314-9023
Internet: as3 l@umail.umd.edu

William Magette
University of Maryland
Dept. of Biological Resources Engineering
1423 ENAG/ANSC Building (#142)
College Park, MD 20742-5711
(301) 405-1190; Fax (301) 314-9023
Internet: wm3@umail.umd.edu
                                                104

-------
                                 Michigan

              Sycamore Creek Watershed
                              Section 319
     National Monitoring Program Project
Figure 19: Sycamore Creek (Michigan) Project Location
              105

-------
                                                                         i Sycamore Creek Watershed, Michigan
                                       HoltRd.
                                                      Harper Rd,
                                                             HoweHRd.
               Mason WWIP
             CcHumbta Drain
                                                             City of Mason
                                                             Royner Creek
                                                                 Scale
                                                                kilometers
Figure 20:  Paired Water Quality Monitoring Stations for the Sycamore Creek (Michigan) Watershed
                                                 106

-------
                                                                       Sycamore Creek Watershed, Michigan
PROJECT OVERVIEW
                              Sycamore Creek is located in southcentral Michigan (Ingham County) (Figure
                              19). The creek has a drainage area of 67,740 acres, which includes the towns of
                              Holt and Mason, and part of the city of Lansing. The major commodities produced
                              in this primarily agricultural county are corn, wheat, soybeans, and some live-
                              stock. Sycamore Creek is a tributary to the Red Cedar River, which flows into the
                              Grand River. The Grand River discharges into Lake Michigan.

                              The major pollutants of Sycamore Creek are sediment, phosphorus, nitrogen, and
                              agricultural pesticides. Sediment deposits are adversely affecting fish and
                              macroinvertebrate habitat and are depleting oxygen in the water column. Sy-
                              camore Creek has been selected for monitoring, not because of any unique charac-
                              teristics, but rather because it is representative of creeks throughout lower
                              Michigan.

                              Water quality monitoring occurs in three subwatersheds: Haines Drain, Willow
                              Creek, and Marshall Drain (Figure 20). The Haines subwatershed, where best
                              management practices (BMPs) have been installed, serves as the control  and is
                              outside the Sycamore  Creek watershed. Stormflow and baseflow water quality
                              samples from each watershed are from March through July of each project year.
                              Water is sampled for turbidity, total suspended solids, chemical oxygen demand
                              (COD), nitrogen (N),  and phosphorus (P).

                              Land treatment consists primarily of sediment and nutrient-reducing BMPs on
                              cropland, pastureland, and hayland. Implementation BMPs is funded as part of
                              the U.S. Department of Agriculture (USDA) Sycamore Creek Hydrologic Unit
                              Area (HUA) project.
PROJECT DESCRIPTION
Water Resource
Type and Size

Water Uses and
Impairments
Pre-Project
Water Quality
Sycamore Creek is a tributary of the Red Cedar River. The Red Cedar River flows
into the Grand River, which flows into Lake Michigan.

Sycamore Creek is designated through Michigan State Water Quality Standards
for warm-water fish, body contact recreation, and navigation. Currently the
pollutant levels in the creek are greater than prescribed standards. In particular,
dissolved oxygen levels (the minimum standard level is 5 milligram per liter) are
below the minimum standard, primarily because of sediment but also, in some
cases, nutrients (Suppnick,  1992).

The primary pollutant is sediment. Widespread aquatic habitat destruction from
sedimentation has been documented. Nutrients (nitrogen and phosphorus) are
secondary pollutants. Pesticides may be polluting ground water; however, evi-
dence of contamination by pesticides is currently lacking. Low levels of dissolved
oxygen in the creek are a result of excess plant growth and organic matter associ-
ated with the sediment.
                                                 107

-------
                                                                       i Sycamore Creek Watershed, Michigan
Current Water
Quality Objectives
Modifications Since
Project Initiation

Project Time Frame
Project Approval
                              Sediment and Phosphorus Content of Sycamore Creek Under Routine (dry)
                              and Storm (wet) Flow Conditions
                                  DryP
                                  mg/1
                      WetP
                       mg/1
Dry Sediment   Wet Sediment
    mg/1            mg/1
                                0.01-0.09           0.04-0.71

                              Source: NRCS/CES/FSA, 1990
                                       4-28
                    6-348
A biological investigation of Sycamore Creek, conducted in 1989, revealed an
impaired fish and macroinvertebrate community. Fish and macroinvertebrate
numbers were low, suggesting lack of available habitat.

Channelization of Sycamore Creek is causing unstable flow discharge, significant
bank-slumping, and erosion at sites that have been dredged.

The water quality objective is to reduce the impact of agricultural nonpoint source
(NFS) pollutants on surface and ground water of Sycamore Creek.

The goal of the project is to reduce sediment delivery into Sycamore Creek by
52%.
None.
Monitoring will be conducted for a minimum of six years, contingent upon federal
funding.

1993
PROJECT AREA  CHARACTERISTICS
Project Area

Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
The project, located in southcentral Michigan, encompasses 67,740 acres.

The geology of the watershed consists of till plains, moraines, and eskers (gla-
cially deposited gravel and sand that form ridges 30 to 40 feet in height). The
Mason Esker and associated loamy sand and sandy loam soil areas are the major
ground water recharge areas in Ingham County. Eskers are the predominant
geologic feature near the stream. These grade into moraines that are approxi-
mately one-half to one mile in width. The moraines have sandy loam textures with
slopes of 6 -18%. The moraines grade into till plains. Interspersed within the area,
in depressional areas and drainageways, are organic soils.

Approximately 50% of the land in this primarily agricultural watershed is used
for crops, forage, and livestock.

Critical areas for targeting BMPs are agricultural fields (cropland, hayland, or
pasture) within one-half mile of a stream.

Major BMPs already implemented in the project area are pasture and hayland
planting, pasture and hayland management, diversions, cover and green manure
crops, critical area plantings, conservation tillage, grade stabilization structures,
grassed waterways, and integrated crop management.
                                                 108

-------
                                                                  Sycamore Creek Watershed, Michigan
Pollutant Sources

Modifications Since
Project Started
Crop and residue cover are recorded on a 10-acre cell basis in each of the three
monitored subwatersheds.
Land Use
Agricultural
Forest
Residential
Business/Industrial
Idle
Wetlands
Transportation
Open land
Gravel pits and wells
Water
Other
Total

Acres
35,453
8,017
9,336
2,562
6,381
2,324
1,349
826
806
359
325
67,738

f%)
52
12
14
4
10
3
2
1
1
0.5
0.5
100
Source: NRCS/CES/FSA, 1990


Streambanks, urban areas, agricultural fields

None.
INFORMATION,  EDUCATION, AND PUBLICITY
Progress Towards
Meeting Goals
The Ingham County Cooperative Extension Service (CES) is responsible for all
information and education (I&E) activities within the watershed. These I&E
activities have been developed and are being implemented as part of the Sycamore
Creek HUA project. Activities include public awareness campaigns, conservation
tours, media events such as news releases and radio shows, display set-ups, work-
shops, short courses, farmer-targeted newsletters, homeowner-targeted newsletters,
on-farm demonstrations, meetings, and presentations. Ingham County CES assists
producers with nutrient management plans and integrated pest management.

1994 activities include:

•   Ten on-farm demonstrations

•   One watershed tour

•   One watershed winter meeting

•   Monthly newsletters for area farmers

•   One homeowners' newsletter

•   Twenty-five farm plans for nutrient and pesticide management
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
 Description
The Sycamore Creek U.S. Environmental Protection Agency (USEPA) Section 319
National Monitoring Program project is nested within the Sycamore Creek HUA
project. The nonpoint source control strategy includes: 1) identification and
prioritization of significant nonpoint sources of water quality contamination in the
watershed and 2) promotion of the adoption of BMPs that significantly reduce the
affects of agriculture on surface water and ground water quality.

                 109

-------
                                                                         i Sycamore Creek Watershed, Michigan
Modifications Since
Project Started

Progress Toward
Meeting Goals
Selection of the BMPs depends on land use: cropland, hayland, pasture land, or
urban land. Cropland BMPs include conservation tillage, conservation cropping
sequence, crop residue use, pest management, nutrient management, waste
utilization, critical area planting, and erosion control structures. Hayland- area
BMPs consist of conservation cropping sequence, conservation tillage, pest
management, nutrient management, pasture/hayland management, and pasture/
hayland planting. BMPs to be utilized on pastureland are conservation cropping
sequence, conservation tillage, pasture/hayland management, pasture/hayland
planting, fencing, waste utilization, filter strips, and critical area planting. The
following practices are eligible for ACP funding:

•   Permanent vegetative cover establishment

•   Diversions

•   Cropland protective cover

•   Permanent vegetative cover on critical areas

•   Sediment retention erosion or water control structure

•   Sod waterways

•   Integrated crop management

Practice installation and the effect on water quality is tracked using the database
ADSWQ (Automatic Data System for Water Quality). The EPIC model (Erosion
Productivity Index Calculator) is being used to estimate changes in edge-of-field
delivery of sediment, nutrients, and bottom of root zone delivery of nutrients
resulting from BMP implementation.

None.
The Ingham County Drain Commission (ICDC) has received an implementation
grant under Section 319 of the Clean Water Act for the installation of streambank
stabilization in Willow Creek (Figure 20). Innovative and environmentally sensi-
tive techniques for streambank stabilization were selected to minimize the sedi-
ment load in Willow Creek. Measures were selected based on their effectiveness in
reducing ground water seepage and slope instability. The techniques chosen for
implementation on Willow Creek included brush mattresses, live fascines, fiber
rolls, biolunkers, riprap, underdrain, slope reduction, vegetative plantings, tree/
branch revetments, current deflectors, and rock cascades.

Priority areas for streambank stabilization were defined as those locations where
bank undercutting, coupled with bare channel banks and ground water seepage,
were visibly contributing to the sediment load. Priority areas were chosen by the
ICDC and consultants based on observations during several field visits.
WATER  QUALITY MONITORING
Design
A paired watershed design is being used to document water quality changes in
Sycamore Creek. Two subwatersheds within the project, Willow Creek and
Marshall Drain, have been compared to a control subwatershed, Raines Drain,
that lies outside the boundaries of the project (Figure 20). BMPs were installed in
the Haines Drain prior to the commencement of water quality monitoring in 1990.
                                                  110

-------
                                                                         Sycamore Creek Watershed, Michigan
Modifications Since
Project Started
The Willow Creek and Marshall Drain subwatersheds were selected among all
subwatersheds in the Sycamore Creek watershed because they contained the
highest sediment loads and the largest percentage of erodible land within one-
quarter mile of a channel.

An additional station was added in 1995 at the United States Geological Survey
(USGS) gauging station at Holt Road. Sampling is conducted year round using a
flow stratified strategy. The monitoring data from this station will be used to
determine the annual load of pollutants near the mouth of the stream and to
compare these loads with various models for estimating pollutant loads in the
watershed. Automatic sampling equipment is used to collect samples and the
USGS flow data are used to determine loads. The parameters tested for are the
same as the other three stations.
Parameters
Measured
Biological

 None
 Sampling Scheme
Chemical and Other

Total suspended solids (TSS)
Turbidity
Total phosphorus (TP)
Total Kjeldahl nitrogen (TKN)
Nitrate + nitrite (NOs + NC-2)
Chemical oxygen demand (COD)
Orthophosphate (OP)
Ammonia (Nffe)

Covariates

Rainfall
Flow
Erosion-intensity index

 Sampling during storm events is conducted from after snow melt (ground thaw)
through the appearance of a crop canopy (sometime in July). Samples are col-
 lected every one to two hours during storms. For each location and storm, six to
 twelve samples are selected for analysis. Automatic stormwater samplers equipped
 with liquid level actuators are used.

 Twenty evenly spaced weekly grab samples are also taken for trend determination.
 Sampling begins in March when the ground thaws and continues for the next 20
 weeks.

 A continuous record of river stage is being obtained with Isco model 2870 flow
 meters. The river stage converts to a continuous flow record using a stage dis-
 charge relationship which is periodically updated by field staff of the Land and
 Water Management Division of the Michigan Department of Environmental
 Quality.

 One recording rain gauge is installed in each agricultural subwatershed (Figure
 20).
                                                   Ill

-------
                                                                         I Sycamore Creek Watershed, Michigan
        Monitoring Scheme for the Sycamore Creek Section 319 National Monitoring Program Project
Design
Three-way
paired
Sites*
Willow Creek1
Haines Drainc
Marshall Drain T
Primary
Parameters**
TSS
Turbidity
TP
TKN
NO3 + NO2
COD
OP
NH3
Covariates***
Rainfall flow
Erosion-intensity
index
Frequency of
WQ Sampling
Weekly for 20
samples starting
after snow melt
Storm sampling
(from after snow melt
until canopy closure)
Duration
6 yrs pre-BMP
lyrBMP
lyr post-BMP
3 yrs pre-BMP
3 yrs BMP
1 yr post-BMP
       ^Treatment watersheds
       c Control watershed
Modifications Since
Project Started

Water Quality Data
Management and
Analysis
NPSMS Data
Summary
Prior to 1993, weekly grab samples were not collected, but occasional grab
samples during base flow were collected.

Preliminary exploratory analysis includes a linear regression of control values
versus target values for storm loads, storm event mean concentrations, storm
rainfall amounts, storm runoff volume, and storm runoff coefficients. Storm loads
were also compared to the AGNPS model for the first two years of data. Land use
and cover data are recorded each year on a 10 acre grid scale.

Summaries of quartile data from 1990 through 1993 are presented in the table
below. These summaries include all data including storm event data for 1990-
1993, base flow grab samples for 1990-1992, and weekly sampling in 1993.
Differences can be seen among the watersheds, for example, stable flow and
NOa+NOs levels in Willow Creek  compared to the other stations and the higher
flows in Haines Drain compared to the other stations.
                       Monitoring Station Parameters Report

                       CHEMICAL PARAMETERS

                       STATION NAME: Haines Drain (Control; 848 acres)

                       Parameter Name
                       FLOW.CFS
                       SUSPENDED SOLIDS
                       TOTAL PHOSPHORUS
                       NO3 + NO2
                       COD

                       STATION NAME: Haines Drain (Control; 848 acres)

                       Parameter Name
                       FLOW.CFS
                       SUSPENDED SOLIDS
                       TOTAL PHOSPHORUS
                       N03 + N02
                       COD

                       STATION NAME: Haines Drain (Control; 848 acres)

                       Parameter Name
                       FLOW.CFS
                       SUSPENDED SOLIDS
                       TOTAL PHOSPHORUS
                       NO3 + NO2
                       COD
                                 YEAR: 1990
                                 Reporting
                                  Units
                                 cfs
                                 mg/1
                                 mg/1
                                 mg/1
                                 mg/1

                                 YEAR: 1991
                                 Reporting
                                  Units
                                 cfs
                                 mg/1
                                 mg/1
                                 mg/1
                                 mg/1

                                 YEAR: 1992
                                 Reporting
                                  Units
                                 cfs
                                 mg/1
                                 mg/1
                                 mg/1
                                 mg/1
 N
85
84
84
84
84
 N
44
43
45
45
15
 N
31
31
31
31
31
       QUARTILE VALUES
-75-
  8
 38
0.196
 3.8
35.5
 -50-
   6
  15
0.107
  3.5
  29
 -25-
   2
   7
0.048
  2.9
  22
      QUARTILE VALUES
-75-
  8
147
0.64
36.
 55
 -50-
   5
  46
 0.34
 3.3
  36
 -25-
   4
  20
0.178
   3
  29
      QUARTILE VALUES
-75-
 14
270
0.8
4.2
 59
 -50-
   6
  95
 0.47
  3.4
  37
 -25-
  0.9
  24
0.126
  2.9
  20
                                                  112

-------
STATION NAME: Haines Drain (Control; 848 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
NO31-NO2
COD
STATION NAME: Marshall Drain (Target; 422 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
N03 + NO2
COD
STATION NAME: Marshall Drain (Target; 422 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
NO3 + NO2
COD
STATION NAME: Marshall Drain (Target; 422 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
NO3 + NO2
COD
STATION NAME: Marshall Drain (Target; 422 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
NO3 + NO2
COD
STATION NAME: Willow Creek (Target; 1087 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
NO3 + NO2
COD
STATION NAME: Willow Creek (Target; 1087 acres)

Parameter Name
FLOW.CFS
SUSPENDED SOLIDS
TOTAL PHOSPHORUS
NO3 + NO2
COD
YEAR: 1993
Reporting
Units
eft
mg/1
mg/1
mg/1
mg/1
YEAR: 1990
Reporting
Units
els
mg/1
mg/1
mg/1
mg/1
YEAR: 1991
Reporting
Units
cfs
mg/1
mg/1
mg/1
mg/1
YEAR: 1992
Reporting
Units
cfs
mg/l
mg/1
mg/1
mg/1
YEAR: 1993
Reporting
Units
els
mg/1
mg/1
mg/1
mg/1
YEAR: 1990
Reporting
Units
cfs
mg/1
mg/1
mg/1
mg/1
YEAR: 1991
Reporting
Units
cfs
mg/1
mg/1
mg/1
mg/1
;amore i

N
67
66
67
66
66


N
44
44
44
36
44


N
40
39
41
41
23


N
23
23
23
23
23


N
52
52
52
51
52


N
83
82
83
83
83


N
47
47
50
50
21
;reeK watersnea, Micniga
QUARTILE VALUES
-75- -50- -25-
8.3 2 1
91 45 15
0.48 0.24 0.105
7.4 2.9 1.82
45 31 23

QUARTILE VALUES
-75- -50- -25-
0.5 0.4 0.2
98.5 29 16.5
0.059 0.04 0.029
5.8 2.55 1.9
19 16 14

QUARTILE VALUES
-75- -50- -25-
2 1 0.8
115 29 17
0.35 0.118 0.062
7.5 6.4 5
40 31 17

QUARTILEVALUES
-75- -50- -25-
5 0.9 0.3
100 30 7
0.4 0.152 0.046
6.2 4.8 2.4
49 26 16

QUARTILE VALUES
-75- -50- -25-
4.87 0.57 0.32
60 26 7
0.27 0.177 0.06
12 3.9 3
32 22 12

QUARTILE VALUES
-75- -50- -25-
543
44 32 18
0.075 0.055 0.036
2.7 2.4 2.1
31 24 18

QUARTILE VALUES
-75- -50- -25-
443
197 80 44
0.36 0.137 0.066
3 2.3 2.3
67 51 32
113

-------
                                                                 i Sycamore Creek Watershed, Michigan
                    STATION NAME: Willow Creek (Target; 1087 acres)   YEAR: 1992
                                                          Reporting
                    Parameter Name                          Units         N
                    FLOW.CFS                               cfs           37
                    SUSPENDED SOLIDS                       mg/1          37
                    TOTAL PHOSPHORUS                      mg/1          37
                    NO3 + NO2                               mg/1          37
                    COD                                   mg/1          37

                    STATION NAME: Willow Creek (Target, 1087 acres)   YEAR: 1993
                                                          Reporting
                    Parameter Name                          Units         N

                    FLOW.CFS                               cfs           74
                    SUSPENDED SOLIDS                       mg/1          74
                    TOTAL PHOSPHORUS                      mg/1          73
                    NO3 + NO2                               mg/1          72
                    COD                                   mg/1          74
QUARTILE VALUES
-75-
6
150
0.26
3.5
82
-50-
4
70
0.135
1.94
45
-25-
3
28
0.052
1.75
27
                                                QUARTILE VALUES
                                                -75-   -50-    -25-

                                                7.36   4.98    4.14
                                                130     80     40
                                                0.21  0.128    0.069
                                                2.5     2.2     1.9
                                                 76     49     33
Modifications Since
Project Started

Progress Towards
Meeting Goals
None.
Six years of sampling have been completed in the paired watersheds.
TOTAL PROJECT BUDGET
Modifications Since
Project Started
                            The estimated budget for the Sycamore Creek Watershed Section 319 National
                            Monitoring Program project for the life of the project is:
                            Project Element
                            Project Mgt
                            I&E
                            LT
                            WQ Monit
                            TOTALS
               Federal

               129,370
               159,900
              1,078,300
               285,000
              1,652,570
Funding Source: (S)
   State          Local
 122,000
     NA
     NA
 222,000
 344,000
  3,130
  9,935
500,751
   NA
513,816
Source: John Suppnick (Personal Communication), 1993
None.
    Sum

 254,500
 169,835
1,579,051
 507,000
2,510,386
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
Modifications Since
Project Started
The funds for the 319 National Monitoring Program project provide for the water
quality monitoring in the HUA project area. The county Farm Service Agency
Committee has agreed to use Agricultural Conservation Program (ACP) funds for
land treatment (erosion control, water quality improvement, and agricultural
waste management).

None.
                                              114

-------
                                                               Sycamore Creek Watershed, Michigan
OTHER PERTINENT INFORMATION
                          Agencies involved in this project are as follows:

                          •   Farm Service Agency (FSA)

                          •   Michigan State University Extension - Ingham County

                          •   Ingham County Health Department (Environmental Division)

                          •   Ingham Conservation District

                          •   Landowners within the Sycamore Creek watershed

                          •   Michigan Department of Environmental Quality
PROJECT CONTACTS
Land Treatment
Water Quality
Monitoring
 Information and
 Education
Bob Hicks (Land Treatment for the HUA Project)
USDA-NRCS
521 N. Okemos Rd.
P.O. Box 236
Mason, MI 48554
(517) 676-5543

Brian McMasters (Land Treatment for the HUA Project)
USDA-NRCS
521 N. Okemos Rd.
P.O. Box 236
Mason, MI 48554
(517) 676-5543

John Suppnick
MI Department of Environmental Quality
Surface Water Quality
P.O. Box 30273
Lansing, MI  48909
(517) 335-4192; Fax (517) 373-9958

George Silba (I & E for the HUA Project)
Ingham County Extension Service
121 East Maple Street
P.O. Box 319
Mason, MI 48909
(517) 676-7301; Fax (517) 676-7230
                                            115

-------
                          i Sycamore Creek Watershed, Michigan
116

-------
                                    Nebraska

                       Elm Creek Watershed
                                 Section 319
       National Monitoring Program Project
           Nebraska
       Project Area
                       •o
Figure 21: Elm Creek (Nebraska) Watershed Project Location
                117

-------
                                                                    Elm Creek Watershed, Nebraska
                N
          Legend
                       Monitoring Station
                       Streams
                       Watershed Boundaiy
Figure 22: Water Quality Monitoring Stations for Elm Creek (Nebraska) Watershed
                                       118

-------
                                                                             Elm Creek Watershed, Nebraska
PROJECT OVERVIEW
                              Elm Creek is located in southcentral Nebraska, near the Kansas border (Figure
                              21). The creek flows in a southerly direction through agricultural lands of rolling
                              hills and gently sloping uplands. The creek has a drainage area of 35,800 acres,
                              consisting mainly of dryland crops of wheat and sorghum and pasture/rangelands
                              with some areas of irrigated corn production.

                              A primary water use of Elm Creek is recreation, particularly as a coldwater trout
                              stream. Sedimentation increases water temperatures and high peak flows, thus
                              impairing aquatic life by destroying habitat, which reduces the creek's recreational
                              use due to lowered trout productivity.

                              Land treatment for creek remediation includes non-conventional best management
                              practices (BMPs), water quality and runoff control structures, water quality land
                              treatment, and conventional water quality management practices (see section on
                              Nonpoint Source Control Strategy). Many of these BMPs are being funded as part
                              of a U.S.  Department of Agriculture (USD A) Hydrologic Unit Area (HUA)
                              project. Land use is being inventoried. Cropland and BMP implementation are
                              being tracked. Additionally, land treatment monitoring will include tracking land
                              use changes based on the 40-acre grid system of the Agricultural Nonpoint Source
                              (AGNPS) model at the end of the project.

                              Water quality monitoring includes an upstream/downstream design as well as a
                              single station downstream design for trend  detection. Grab samples are collected
                              weekly from March through September to provide water quality data. Additional
                              biological and habitat data are being collected on a seasonal basis.
PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
 Impairments
 Pre-Project
 Water Quality
 Current Water
 Quality Objectives
Elm Creek flows through cropland and pasture/range into the Republican River.
Flow in the creek is dominated by inflow springs. The average discharge of Elm
Creek is 21.4 cubic feet per second and the drainage area is 56 square miles.

Elm Creek is valued as a coldwater aquatic life stream, as an agricultural water
supply source, and for its aesthetic appeal. It is one of only two coldwater habitat
streams in southcentral Nebraska. Sedimentation, increased water temperatures,
and peak flows are impairing aquatic life by destroying stream habitat of the
macroinvertebrates and trout. These negative impacts  on the stream result from
farming practices that cause excessive erosion and overland water flow.

A thorough water quality analysis of Elm Creek conducted in the early 1980s
indicated that the water quality of Elm Creek was very good. There was, however,
short-term degradation of wate'r quality following storm events. The coldwater
habitat use assignment of Elm Creek appeared to be attainable if it was not im-
paired by nonpoint source (NPS) pollution, particularly sedimentation and scour-
ing of vegetation during  storm events.

The NPS management objective in the Elm Creek watershed is to implement
appropriate and feasible NPS pollution control measures for the protection and
enhancement of water quality in Elm Creek. Project goals are to:
                                                  119

-------
                                                                       Elm Creek Watershed, Nebraska
Modifications Since
Project Initiation

Project Time Frame
Project Approval
    Reduce maximum summer water temperature

    Reduce in-stream sedimentation

    Reduce peak flows

•   Improve in-stream aquatic habitat

None.
Monitoring activities began in April, 1992, and were scheduled to end in 1996.
Funds have been secured to continue post-BMP implementation monitoring until
1999.
1992
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
The project area, in southcentral Nebraska, consists of 35,800 acres of rolling
hills, gently sloping uplands, and moderately steep slopes.

The Elm Creek watershed, which receives 26.5 inches of rainfall per year, lies in
a sub-humid ecological region. Seventy-five percent of this rainfall occurs be-
tween April and September. The average temperature is 52 degrees Fahrenheit
with averages of 25 degrees in January and 79 degrees in July. The soils are
derived from loess and the predominant soil types are highly erosive.

Wheat and sorghum are the primary dryland crops produced. Corn is the primary
irrigated crop. Range and pasture dominate the more steeply sloping lands.
                            Land Use
                            Agricultural
                             Dryland
                             Irrigated
                             Pasture/Range
                            Forest
                            Other
                            Total
                      Acres

                      14,630
                       2,680
                      16,170
                        650
                       1,670
                      35,800
 "A

 42
  7
 44
  2
  5
100
                             Source: Elm Creek Project, 1992
 Pollutant Sources

 Modifications Since
 Project Started
 Streambank erosion, irrigation return flows, cattle access, cropland runoff

 None.
INFORMATION,  EDUCATION, AND PUBLICITY
                             Information and education (I&E) activities have been developed and are being
                             implemented as part of the Elm Creek HUA Project. The University of Nebraska
                             and Cooperative Extension in Webster County are in charge of I&E activities.
                             I&E activities include newsletters, an NFS video, slide shows, programs, ques-
                             tionnaires, fact sheets, demonstration sites, field days, and meetings.
                                              120

-------
                                                                            Elm Creek Watershed, Nebraska
Progress Toward          The process of addressing nonpoint source issues in the Elm Creek watershed
Meeting Goals              through information and education activities has been coordinated by the Univer-
                             sity of Nebraska Cooperative Extension as part of the USD A HUA effort. In
                             addition to those activities listed below, a newsletter promoting implementation of
                             NFS pollution prevention practices continues to be developed and delivered to
                             owners/operators in the watershed.

                             I&E activities implemented in the Elm Creek watershed include the following:

                                 Seven producers have agreed to host field days and BMP demonstration plots.

                                 To encourage no-till practices, a no-till drill is available for rent at $8.00 per
                                 acre.

                                 A videotape on no-till crop planting practices has been completed and a
                                 videotape on rotational grazing  is currently being produced.

                                 Two newsletters are currently being produced for the project. One newsletter
                                 is sent to all landowners and operators in the project area and includes articles
                                 on BMPs, cost share funds available, and updates on project progress and
                                 upcoming events. In addition, a quarterly project newsletter detailing relevant
                                 project activities (i.e., budget, progress, etc.) is mailed to all cooperators.

                                 A series of educational programs have been held to provide producers with
                                 background information to encourage the adoption of BMPs. Other program
                                 topics included new tools for pasture production, rotational grazing tour, and
                                 a prescribed burn workshop.

                              •   An eco-farming clinic was held where no-till drills were demonstrated. Topics
                                 of discussion for the program included winter wheat production and weed
                                 control, diseases, cultivar selection, insect control, and soil fertility.

                                 Eight demonstration plots exhibiting various BMPs are currently being used
                                 as an educational tool. Practices being demonstrated include: nitrogen
                                 management, integrated crop management - irrigated, integrated crop
                                 management - dryland, no-till milo production, no-till wheat production,
                                  conservation tillage wheat production, cedar revetments for streambank
                                 protection, and sediment retention basin restoration.

                              •   Numerous news stories, articles, meeting announcements and updates have
                                 been published in local newspapers.


NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Description
BMPs, both structural and non-structural, continue to be implemented throughout
the Elm Creek watershed. These BMPs have been divided into four BMP types.

Non-conventional

Vegetative Filter Strips
Permanent Vegetative Cover on
   Critical Areas
Streambank Stabilization
Livestock Access & Exclusion
Ground Water Recharge
Abandoned Well Plugging
Trickle Flow Outlets
Sediment Barriers
Grade Stabilization
                                                 121

-------
                                                                            Elm Creek Watershed, Nebraska
Modifications Since
Project Started
Progress Toward
Meeting Goals
Water Quality & Runoff Control Structures

Water Quality Land Treatment

Tree Planting
Permanent Vegetative Cover
Terraces
Stripcropping

Conventional Water Quality Management Programs

Irrigation Management
Conservation Tillage
Range Management
Integrated Pest Management

Non-conventional BMPs are being funded under the Section 319 National Moni-
toring Program. Other BMPs will be funded with 75% cost share funds from the
HUA project. Finally, selected BMPs will be cost shared at 100% [75% from the
Section 319 National Monitoring Program and 25% from Lower Republican
Natural Resource District (LRNRD)]. The number and types of BMPs imple-
mented will depend on voluntary farmer participation.

Land use will be inventoried. Cropland and BMP implementation will be tracked
over the life of the project. Tracking will be based on the 40-acre grid system used
for AGNPS modeling.

As originally proposed, land use and BMP implementation were to be tracked
based on a 40-acre grid system of the Agricultural Nonpoint Source (AGNPS)
model. This scheme was to be used since a pre-project inventory of current land
uses had been completed by the Natural Resource Conservation Service (NRCS) to
run the AGNPS model. The goal was to then rerun the model with updated land
use and BMP implementation data. However, once the Section 319 and HUA
projects were initiated, staff quickly realized that annual tracking of land use
changes and BMP implementation on a 40-acre basis in such a large watershed
could not be accomplished with the resources available. The NRCS plans to rerun
AGNPS with the updated information once the projects have been completed.

Currently, 56 applications have been processed for USEPA Section 319 funds.
Since 1990, when the HUA project was initiated, 178 cooperators have requested
technical funds for BMP cost-share. From 1991 through 1995, the practices and
activities outlined in the following table have been implemented primarily for
erosion control in the Elm Creek watershed.

Significant strides have also been made in implementing NFS control measures
throughout the watershed (see following table).
                                                 122

-------
                                                Elm Creek Watershed, Nebraska
 Application of Practices/Activities for Erosion Control in the Elm Creek
 Watershed (7-31-96).
NRCS PRACTICE/ACTIVITY
AND LD. #
Conservation Cropping Sequence (328)
Conservation Tillage (329)
Contour Farming (330)
Critical Area Planting (342)
Crop Residue Use (344)
Deferred Grazing (352)
Diversion (362)
Pond (378)
Fencing (382)
Field Border (386)
Filter Strip (393)
Grade Stabilization Structure (410)
Grassed Waterway (412)
Irrigation Water Management (449)
Livestock Exclusion (472)
Pasture and Hayland Management (510)
Pasture and Hayland Planting (512)
Pipeline (516)
Proper Grazing Use (528)
Range Seeding (550)
Planned Grazing System (556)
Streambank Protection/Habitat Restoration
Terrace (600)
Tree Planting (6 12)
Trough or Tank (614)
Underground Outlet (620)
Well (642)
Wildlife Upland Habitat Management (645)
UNITS
acres
acres
acres
acres
acres
acres
feet
number
feet
feet
acres
number
acres
acres
acres
acres
acres
feet
acres
acres
acres
feet
feet
acres
number
feet
number
acres
NUMBER
INSTALLED
5,550
3,795
2,661
40
3,389
163
4,236
17
45,028
31,777
5
5
8.3
2,262
212
313
105
2,732
4,345-
93
2,117
280
126,029
4
12
2,892
6
156
  Source: Scott Montgomery (personal communication, 1996)
Although significant progress has been made, a few problems have also been
encountered with monitoring efforts. Preliminary evaluation of the project moni-
toring design (upstream-downstream and single downstream) and water quality
data suggests that the large size of the watershed above the upstream monitoring
station (approximately 31,142 acres) inhibits documentation of water quality
improvements due to land treatment implementation. More specifically, this
problem can be attributed to the variability associated with regional and watershed
conditions. The majority of non-structural BMPs recommended by the NRCS
implemented in the Elm Creek watershed are designed only to control runoff from
one-in-ten year storm events. When such storm events occur in the watershed,
water quality (including in-stream habitat) remains good. However, with such a
large watershed area above the perennial stream reach (which starts within a mile
above the upstream monitoring station), even slightly larger storm events gener-
ally contribute to high flows, which degrade water and habitat quality, making it
difficult to detect improvements.
                   123

-------
                                                                              Elm Creek Watershed, Nebraska
 WATER QUALITY MONITORING
Design
Parameters
Measured
Upstream/downstream: The two sampling sites (sites 2 & 5) are located two miles
apart (Figure 22)
Single downstream, for trend detection (site 5) (Figure 22)

Biological

Qualitative and quantitative macroinvertebrate sampling
Fish collections
Creel survey
Modifications Since
Project Started
Sampling Scheme
Chemical and Other

Water temperature
Dissolved oxygen (DO)
Substrate samples (% Gravel, % Fines)
Total suspended solids  (TSS)
Atrazine/Alachlor
Stream morphological characteristics (width, depth, velocity) and habitat
Water temperature (June - September)

Covariates

Stream discharge (United States Geological Survey gauging station)

Artificial salmonid redds were initially used to monitor trout reproduction. How-
ever, the redds have been discontinued because initial monitoring results indicate
substrates are not suitable for .salmonid spawning.

(See Figure 22 for sampling site locations.)

Qualitative and quantitative macroinvertebrate sampling spring, summer, fall, and
winter (sites 2 and 5).

Fish collections spring and fall (sites 1, 2, 3, 4, 5, 6).

Creel survey (passive).

DO (sites 2, 5): Weekly grab samples from April through September. Monthly
samples from October through March.

Substrate samples spring and fall at sites 2, 4, 5.

TSS (sites 2,5): Weekly grab samples from April through September and monthly
samples, October through March. Selected runoff samples are collected April
through September.

Atrazine/Alachlor (sites 2,5): Grab and runoff samples are analyzed selectively in
the spring for these pesticides.

Stream morphological  characteristics  (width, depth, velocity) and habitat: spring/
summer (sites 2, 5).

Rainfall (recording rain gauge): The main rain gauge will be placed in the upper
or middle part of the watershed. A volunteer network for recording rainfall
amounts has also been established.
                                                   124

-------
                                                                            Elm Creek Watershed, Nebraska
                              Continuous recording thermograph (hourly water temperatures for at least 60% of
                              the period June through September and at least 80% of the period My through
                              August) (sites 2, 5).
  Monitoring Scheme for the Elm Creek Section 319 National Monitoring Program Project
Design
Upstream/
downstream

Single
downstream







Sites
2,5

1,2,3,4,5,6

2,5
2,4,5
2,5
2,5

2,5
2,5
2,5
Primary
Parameters Covariates
Macroinvertebrate Stream
survey discharge
Fish survey
Creel survey
Water temperature
Substrate samples
DO
TSS
Atrazine/alachlor
Stream moq>hological
characteristics
Water temperature
Frequency of
Frequency of Habitat/Biological
WQ Sampling Assessment





Spring & fall
Weekly (April-Sept.) &
monthly (Oct-March)
Spring & fall
Spring
Spring/summer

4times/yr
spring & fall
passive









Duration
0 yrs pre-BMP
SyrsBMP
3 yrs post-BMP










 Modifications Since
 Project Started
           Plans to place a recording rain gauge in the Elm Creek watershed have been
           cancelled because of the variability associated with its large size. For the same
           reason, the volunteer network for recording rainfall amounts has also been discon-
           tinued.
Water Quality Data
Management and
Analysis
           Ambient water quality data are entered into USEPA STORET. Biological data are
           stored in USEPA BIOS. Other data will be stored and analyzed using Microsoft
           Excel 5.0 spreadsheet program and USEPA NonPoint Source Management System
           (NPSMS). Water quality data are being analyzed using SAS statistical software.
           These data are being managed by the Nebraska Department of Environmental
           Quality (NDEQ).

           Data assessment and reporting consists of quarterly activity reports, yearly interim
           reports focusing on BMP implementation, and a final report that will assess and
           link water quality and land treatment results.
NPSMS Data
Summary
ANNUAL REPORT WQ PARAMETER FREQUENCIES

YEAR: 1994
STATION TYPE: Upstream Station
                   CHEMICAL PARAMETERS

                   Parameter Name
                   FLOW, STREAM, INSTANTANEOUS, CFS
                    OXYGEN, DISSOLVED (METER)
                                      QUARTILE VALUES
                                        -75-  -SO-  -25-
                                        13.3  12.0  10.7
                                                            8.7  7.75  6.9
Counts/Season:
Highest
High
Low
Lowest
Highest
High
Low
Lowest
 9
 6
 4
 3
 8
10
 6
 0
                                                  125

-------
                                                                                Elm Creek Watershed, Nebraska
                    SUSPENDED SOLIDS, TOTAL
                              51.0  16.5  2.0
                    TEMPERATURE, WATER (DEGREE CENTIGRADE)  15.7  14.3 11.5
                    BIOLOGICAL PARAMETERS (Non-Chemical)

                    Parameter Name                    Fully
                    INDEX OF BIOLOGICAL INTEGRITY     30
                    INVERTEBRATE COMMUNITY INDEX   31
                    TROUT HABITAT QUALITY INDEX

                    STATION TYPE: Downstream Station

                    CHEMICAL PARAMETERS

                    Parameter Name
                    FLOW, STREAM, INSTANTANEOUS, CFS
                    OXYGEN, DISSOLVED (METER)
                    SUSPENDED SOLIDS, TOTAL
                            INDICES
                           Threatened  Partially
                                       22
                                       1.7
                                              Highest
                                              High
                                              Low
                                              Lowest
                                              Highest
                                              High
                                              Low
                                              Lowest
Scores/Values
              1
             15
              8
              0
              2
              2
              3
              4
             1   2
            29   -
            18  30
                            QUARTILE VALUES
                              -75-  -50- -25-
                              13.3  12.0 10.7
                               9.9  8.85   8.5
                              65.3 20.75   6.0
Modifications Since
Project Started
 3   4
29   -
 -  32
4.1   -
Counts/Season:
Highest
High
Low
Lowest
Highest
High
Low
Lowest
Highest
High
Low
Lowest
Highest
High
Low
1
9
6
4
3
8
8
6
2
1
14
5
1
8
6
4
2
4
0
1
0
5
0
0
0
0
2
2
1
5
0
0
3
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
4
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
                    TEMPERATURE, WATER (DEGREE CENTIGRADE)   16.6  14.8 11.2
                                                                             Lowest         6000

                    BIOLOGICAL PARAMETERS (Non-Chemical)
                                                           INDICES
                    Parameter Name                    Fully   Threatened  Partially   Scores/Values   1234
                    INDEX OF BIOLOGICAL INTEGRITY     30        -       22                  35-31   -
                    INVERTEBRATE COMMUNITY INDEX    31        -       17                  28  26  32  32
                    TROUT HABITAT QUALITY INDEX      -        -       -                   -   -  2.2   -
Progress Towards
Meeting Goals
Quartile data for all chemical and physicochemical parameters indicate water
quality conditions are relatively good. The values presented are accurate for water
quality under baseflow conditions, but not necessarily reflective of impacts caused
by runoff events. After heavy rainfall events, the stream is often subject to high
flows and the associated NFS pollutants seemingly have only a short-term degrad-
ing impact on the in-stream chemical and physiochemical water quality. However,
long-lasting impacts not reflected in the data are the scouring and sedimentation
resulting from these events which impair designated aquatic life uses.

Metrics comprising the biological indices used to assess aquatic communities are
currently being refined for the State of Nebraska. Once this process is complete,
more definitive conclusions can be drawn from the data collected in Elm Creek.

The following water quality monitoring goals have been met:

    Ambient water quality data are currently being entered and stored in USEPA
    STORET.
    Biological data are currently being entered and stored in USEPA BIOS.
    Quarterly and yearly interim reports have been developed as planned.
                                                   126

-------
                                                                    Elm Creek Watershed, Nebraska
TOTAL PROJECT BUDGET
Modifications Since
Project Started
                           The estimated budget for the Elm Creek Watershed Section 319 National Moni-
                           toring Program project for the life of the project is:
                           Project Element
                                                  Federal
                               Funding Source (S)
                                      State    Local
Sum
HUA/WQIP
Proj Mgt
I&E
Reports
LT
WQ Initiative
Program (WQIP)
WQ Monit
Post-Project Monit
TOTALS
0
0
0
260,000
30,000

0
0
290,000
319
11,200
0
6,300
115,000 .
0

100,000
30,000
262,500

0
0
0
0
0

0
0
0

0
3,400
0
101,600
0

15,000
0
120,000

11,200
3,400
6,300
476,600
30,000

115,000
30,000
672,500
                           Source: Elm Creek Project, 1991
Time frame for funding sources:

    Section 319(h) funds in the amount of $30,000 have been secured to continue
    post-BMP implementation monitoring activities for an additional three years
    (1999)

•   Local/Section 319 — April, 1992 to October, 1996

    HUA — May, 1990 to October, 1997 (The HUA project was scheduled to end
    in September, 1995, but has received a three year extension)

    WQIP - Contracts were written for cropping years 1992,1993, and 1994. All
    funds were allocated in 1992

None.
 IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                            The Elm Creek Watershed Section 319 National Monitoring Program project
                            provides the water quality monitoring for the area HUA project. Agricultural
                            Conservation Program (a USDA program) funding will be used for approved,
                            conventional BMPs.
 Modifications Since
 Project Started
 None.
 OTHER PERTINENT INFORMATION
                            The HUA activities are jointly administered by the University of Nebraska Coop-
                            erative Extension and the USDA NRCS. Employees of these two agencies will
                            work with local landowners, Farm Service Agency (FSA) personnel, personnel of
                            the NDEQ, and personnel of the LRNRD. Section 319 National Monitoring
                            Program project activities are administered by the NDEQ.
                                             127

-------
                                                                          Elm Creek Watershed, Nebraska
                              Agencies or groups involved in the project are listed below.
                              •   USDAFSA
                                 Landowners
                                 Lower Republican Natural Resources District:
                                 Monitoring
                                 Little Blue Natural Resources District
                              •   Nebraska Game and Parks Commission
                              •   USDANRCS
                                 Nebraska Department of Environmental Quality
                                 Nebraska Natural Resources Commission
                                 U.S. Geological Survey
                                 University of Nebraska Cooperative Extension
                              •   U.S. Environmental Protection Agency
                                 Webster County Conservation Foundation (WCCF)
                                 Future Farmers of America Chapters and 4-H Clubs
                                 Center for Semi-Arid Agroforestry and Nebraska Forest Service
                                 Webster County Board of Commissioners
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Information and
Education
Dave Jensen
Nebraska Department of Environmental Quality
1200 N Street, Suite 400, The Atrium
P.O. Box 98922
Lincoln, NE 68509
(402) 471-4700; Fax (402) 471-2909
Scott Montgomery (Land Treatment for the project)
USDA-NRCS
20 N. Webster
Red Cloud, NE 68970-9990
(402) 746-2268; Fax (402) 746-2284
Dave Jensen / Greg Michl
Nebraska Department of Environmental Quality
1200 N Street, Suite 400, The Atrium
P.O. Box 98922
Lincoln, NE 68509
(402) 471-4700; Fax (402) 471-2909
Chuck Burr (I & E for the HUA project)
Webster County Cooperative Extension (CE)
621 Cedar
Red Cloud, NE 68970
(402) 746-3345; Fax (402) 746-3417
                                               128

-------
                                North Carolina

                       Long Creek Watershed
                                   Section 319
         National Monitoring Program Project
              North Carolina
                Project Area
Figure 23: Long Creek (North Carolina) Watershed Project Location
                  129

-------
                                                               Long Creek Watershed, North Carolina
                                                                 LEGEND
                                                              o  Daily
                                                              ASampling Location
                                                                Strip Mine
Figure 24:  Water Quality Monitoring Stations for Long Creek (North Carolina) Watershed
                                        130

-------
                                                                        ' Long Creek Watershed, North Carolina
PROJECT OVERVIEW
                              The Long Creek Watershed Section 319 National Monitoring Program project
                              (28,480 acres), located in the southwestern Piedmont of North Carolina, consists
                              of an area of mixed agricultural and urban/industrial land use (Figure 23). Long
                              Creek is a perennial stream that serves as the primary water supply for Bessemer
                              City, a municipality with a population of about 4,888 people (1994 estimate).

                              Agricultural activities related to crop and dairy production are believed to be the
                              major nonpoint sources of pollutants to Long Creek. Sediment from eroding
                              cropland is the major problem in the upper third of the watershed. Currently, the
                              water supply intake pool must be dredged annually to maintain adequate storage
                              volume, and quarterly prior to the project and land acquisition. Below the intake,
                              Long Creek is impaired primarily by bacteria and nutrients from urban areas and
                              animal-holding facilities.

                              Proposed land treatment upstream of the water supply intake includes implement-
                              ing the land use restrictions of the state water supply watershed protection law and
                              the soil conservation provisions of the Food Security Act.

                               Below the intake, land treatment will involve implementing a comprehensive
                               nutrient management plan on a large dairy farm and installing fence for livestock
                               exclusion from a tributary to Long Creek. Land treatment and land use tracking
                               will be based on a combination of voluntary farmer record-keeping and frequent
                               farm visits by extension personnel. Data will be stored and managed in a geo-
                               graphic information system (GIS) located at the county extension office.

                               Water quality monitoring includes a single-station, before-and-after-land treat-
                               ment design near the Bessemer City water intake (Figure 24), upstream and
                               downstream stations above and below an unnamed tributary on Long Creek (B
                               and C), stations upstream and downstream of a dairy farmstead on an unnamed
                               tributary to Long Creek (D and E), and monitoring stations on paired watersheds
                               at a cropland runoff site (F and G). Storm-event and weekly grab samples are
                               being collected at various sites to provide the chemical, biological, and hydrologic
                               data needed to assess the effectiveness of the land treatment program.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
 Impairments
The study area encompasses approximately seven miles of Long Creek (North
Carolina stream classification index # 11-129-16). Annual mean discharges at the
outlet of the study area (I) range between 17 and 59 cubic feet per second over a
40 year period of record.

Long Creek is the primary water supply for Bessemer City. Water quality impair-
ments include high sediment, bacteria, and nutrient levels. The stream channel
near the water supply intake in the headwaters area requires frequent dredging
due to sediment deposition. The section of Long Creek from the Bessemer City
water supply intake to near the watershed outlet sampling station (Figure 24) is
listed as support-threatened by the North Carolina Nonpoint Source Management
Program. Biological (macroinvertebrate) habitat is degraded in this section due to
the presence of fecal coliform, excessive sediment, and nutrient loading from
agricultural and urban nonpoint sources.
                                                   131

-------
                                                                      Long Creek Watershed, North Carolina
Pre-Project
Water Quality
Water quality parameters change with time and location along Long Creek, but
generally are close to the following averages:

    Fecal    BOD         TSS       TKN      NO3-N     TP
  Coliform   (mg/1)         (mg/1)     (mg/1)       (mg/1)    (mg/1)
  #/100ml
    2100       2             14         0.35       0.41     <0.17
                             Note: These average values were computed from the analyses of twelve monthly grab
                             samples taken from three locations along Long Creek.
Current Water
Quality Objectives
Modifications Since
Project Initiation

Project Time Frame

Project Approval
The objectives of the project are to quantify the effects of nonpoint source pollu-
tion controls on:

•   Bacteria, sediment, and nutrient loadings to a stream from a working dairy
    farm;

•   Sediment and nutrient loss from a field with a long history of manure
    application; and

•   Sediment loads from the water supply watershed (goal is to reduce sediment
    yield by 60  percent).

In addition, biological monitoring of streams will attempt to show improvements
in biological habitat associated with the implementation of nonpoint source
pollution controls.

None.
January, 1993 to September, 2001

1992
PROJECT AREA CHARACTERISTICS
Project Area

Relevant Hydrologic,
Geologic, and
Meteorologic Factors

Land Use
About 44.5 square miles or 28,480 acres

The average annual rainfall is about 43 inches. The watershed geology is typical
of the western Piedmont, with a saprolite layer of varying thickness overlaying
fractured igneous and metamorphic rock. Soils in the study area are well drained
and have a loamy surface layer underlain by a clay subsoil.

  Land Use           Acres       %_
  Agricultural         6,975       24
  Forest             15,289       54
  Residential          3,985       14
  Business/Industrial   1,842        6
  Mining               516        2
  Total              28,607      100
                             Source: Jennings et al., 1992
                                                132

-------
                                                                      ' Long Creek Watershed, North Carolina
Pollutant Sources
The monitored area contains the following dairy farms:
                             Dairy Name
                             Dairy 4

                             Dairy 3

                             Dairy 1
                Cows (if)
                     125

                     85

                     400
Feedlot Drainage
Open lot into
holding pond
Open lot across
pasture
Under roof and open
lot across grass buffer
                             Source: Jennings et al., 1992
Modifications Since
Project Started
Dairy 2 went out of business and was purchased by the city of Gastonia for conver-
sion to a biosolids application area.
INFORMATION, EDUCATION, AND  PUBLICITY
 Progress Towards
 Meeting Goals
Cooperative Extension Service (CES) personnel conducts public meetings and
media campaigns to inform the general public, elected officials, community
leaders, and school children about the project and water quality in general. In
addition, project personnel make many one-to-one visits to cooperating and non-
cooperating farmers in the watershed to inform them of project activities and
address any questions or concerns they may have.

An education plan developed for Gaston County includes activities in the Long
Creek watershed. Also, a Stream Watch group has been formed to 1) educate other
watershed residents and 2) conduct quality monitoring by volunteers. Project
overviews continue to be presented at state, local, and regional water-related
conferences.

The Gaston County Conservation District is continuing an extensive natural
resources education outreach program to local schools. Eighty-five percent of
schools (100% of elementary and junior high schools) located in the Long Creek
watershed participate in District programs.
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
 Description
 Water Supply Watershed (site H):
 Bessemer City has recently purchased 13 acres of cropland immediately upstream
 of the intake with the intention of implementing runoff and erosion controls. Also,
 to comply with the North Carolina Water Supply Watershed Protection Act, land
 use requirements are implemented on land within one-half mile of and draining to
 the intake. Less strict requirements such as the conservation provisions of the
 Food Security Act are implemented in the remainder of the  watershed.

 Up/downstream of Dairy 1 Tributary on Long Creek (sites B and C):
 In addition to the best management practices (BMPs) planned for the Dairy 1
 farmstead, the control strategy is to design and implement a comprehensive
 nutrient management plan on the land between the sampling stations.
                                                133

-------
                                                                         Long Creek Watershed, North Carolina
Modifications Since
Project Started

Progress Towards
Meeting Goals
Dairy 1 Farmstead (sites D and E):
A larger waste storage structure has been constructed. Improved pasture manage-
ment, livestock exclusion from the unnamed tributary, and stream bank stabiliza-
tion between sites D and E have been implemented.

Paired Cropland Watersheds (sites F and G):
The control strategy on the paired watersheds involves implementing improved
nutrient management on the treatment watershed while continuing current nutri-
ent management and cropping practices on the control watershed. The number
and types of BMPs implemented depends on voluntary farmer participation.

None.
Farm plans for more than 20 farms within the watershed have been developed.
Twenty-five Water Quality Incentive Project (WQIP) applications have been
submitted by landowners in the Long Creek watershed. Eight plans have been
prepared representing more than $50,000 of BMP installations to control NFS
pollution on these sites.

Water Supply Watershed (site H):
A land use survey of the agricultural portion of the water supply watershed has
been completed. These data were then used by the North Carolina Division of Soil
and Water Conservation (DSWC) to develop a Watershed Management Plan.
Along with developing the plan, DSWC staff used data from 1984 and 1994 to
estimate erosion and sediment delivery rates in the watershed. The comparison
indicated a 52% reduction in estimated annual erosion and a 51% reduction in
sediment delivery to stream channels. However, visual inspection of the watershed
tributaries indicates that considerable work remains in controlling stream channel
erosion. This will be the emphasis of future NFS control efforts. A watering
system was installed at a beef farm in order to exclude cows from the stream.

 Dairy  1 Farmstead (sites D and E):
The Conservation District and the landowner completed the installation of a
Waste Holding Pond in September, 1993. North Carolina Agriculture Cost Share
Funds were utilized for this project. In addition, an underground main and hy-
drant with a stationary gun for applying waste effluent on the pasture/hayland
areas was installed in July, 1994.

A solid waste storage structure was completed in July, 1993. A watering system
has been installed in the pastures of the watershed. Fencing for cattle exclusion
between monitoring sites D and E was completed and the streamside buffers have
been planted in pine and hardwood trees. Grass has been planted on severely
eroding streambanks.
 WATER QUALITY MONITORING
Design
The water quality monitoring effort incorporates the following four designs:

•   Single downstream station at water supply intake and watershed outlet

•   Upstream/downstream design on Long Creek and unnamed tributary

•   Paired watersheds on Dairy 1 cropland

•   Urban stream storm and grab sampling done on a tributary to Long Creek
    (Kaglor Branch)

                   134

-------
                                                                         ' Long Creek Watershed, North Carolina
Modifications Since
Project Started
Parameters
Measured
Sampling Scheme
A watershed screening study for pathogens began in April, 1996. Samples from
three current sites, as well as additional sites, were collected and analyzed for E.
coli, clostridium perfringens, and coliphages.

Biological

Percent canopy and aufwuchs (organisms growing on aquatic plants)

Invertebrate taxa richness: ephemeroptera, plecoptera, trichoptera, coleoptera,
odonata, megaloptera, diptera, oligochaeta, Crustacea, mollusca, and other taxa

Bacteria: Fecal coliform (FC) and fecal streptococci (FS)

Chemical and Other

Total suspended solids (TSS)
Total solids (TS)
Dissolved oxygen (DO)
Biochemical oxygen demand (BOD) (1991-92)
PH
Conductivity
Nitrate + nitrite (NOs + NO2)
Total Kjeldahl nitrogen (TKN)
Total phosphorus (TP)

Physical stream indicators: width, depth and bank erosion

Covariates

Rainfall, humidity, solar radiation, air temperature, and wind speed
Discharge rate of Long Creek and a tributary
Rainfall at paired watersheds and Dairy  1 farmstead

Water Supply Watershed (Figure 24):
Type: grab (site H)
Frequency and  season: weekly from December through May and monthly for the
remainder of the year for TS, TSS, FC, FS, temperature, conductivity, DO, patho-
gens, pH, and turbidity

Upstream/downstream of Dairy 1 Tributary on Long Creek (Figure 24):
Type: grab (sites B and C)
Frequency and  season: weekly from December through May and monthly for the
remainder of the-year for FC and FS, temperature, pH, conductivity, turbidity, DO,
TSS, TP, TKN, and NO2+NO3

Annual biological survey for sensitive species at station C only

Dairy 1 Farmstead Storm Event:
Type: grab (sites D and E)
Frequency and  season: weekly all year for FC and FS, temperature, pH, conductiv-
ity, DO, TSS, TS, TKN, NO2+NOs, and TP; storm events for TSS, TS, TKN,
NO2+NO3, and TP

Paired Cropland Watersheds (Figure 24):
Type: storm event (sites F and G)
Frequency and  season: stage-activated storm event for runoff, TS, TKN,
NO2+NO3, TP, and pathogens
                                                  135

-------
                                                                       Long Creek Watershed, North Carolina
                             Single Downstream Station at Watershed Outlet (Figure 24):
                             Type: grab (site I)
                             Frequency and season: weekly from December through May and monthly for the
                             rest of the year for temperature, pH, conductivity, turbidity, DO, TSS, TP, TS,
                             TKN, NOa+NOa, and FC and FS; annual biological for sensitive species
  Monitoring Scheme for the Long Creek Section 319 National Monitoring Program Project
Design
Single
downstream



Upstream/
downstream




Upstream/
downstream





Paired




Single
downstream




Sites or
Activities
Water supply
watershed



Long Creek




Dairy 1
Farmstead





Paired
cropland
watersheds


Watershed
outlet




Primary
Parameters
TS
TSS
FC
FS
Pathogens
TP
NO3 + NO2
TKN
TSS
FC
FS
TP
NO3 + NO2
TS
TSS
FC
FS
Pathogens
TP
NO3 + NO2
TS
TKN
Pathogens
TP
N03 + NO2
TKN
TSS
FC
FS
Covariates
Discharge
(weekly)



Discharge
(weekly)




Discharge
(continuous)
Rainfall
Water table



Discharge
(continuous)
Rainfall
Water table

Discharge
(continuous)




Frequency of
WQ Sampling
Weekly
(Dec.-May)

Monthly

Weekly
(Dec. - May)

Monthly
(June-Nov.)

Weekly
and storm event





Storm event




Weekly
(Dec.-May)

Monthly
(June-Nov.)

Frequency of
Habitat/Biological
Assessment Duration
Annually 2 yrs pre-BMP
6 yrs BMP



Annually 2 yrs pre-BMP
(downstream) 4 yrs BMP
2 yrs post-BMP



2 yrs pre-BMP
2 yrs post-BMP





2 yrs pre-BMP
6 yrs post-BMP



Annually 2 yrs pre-BMP
6 yrs BMP





Modifications Since
Project Started
Progress Towards
Meeting Goals
In May - June, 1994, four monitoring wells were installed at the paired water-
sheds to gain a better understanding of ground water movement. Approximately
16 wells above Site B are also being installed on a Biosolids Application site.

Also, storm-event sampling on a small stream draining an urban watershed has
been added. Assessment monitoring for the pathogens cryptosporidium and
giardia has been initiated at several locations in the watershed.

The water quality monitoring stations have been established and two years of data
have been collected. Also, climatic and flow  measurements are being made at
several points in the watershed, i
                                                 136

-------
                                                                               i Long Creek Watershed, North Carolina
Water Quality Data
Management and
Analysis
        Data are stored locally at the county Extension Service office. The data are also
        stored and analyzed at North Carolina State University using the U.S. Environ-
        mental Protection Agency's (USEPA) NonPoint Source Management System
        software. The North Carolina Division of Water Quality will also store the water
        quality data in the USEPA STORET system. Data will be shared among all
        participating agencies for use in their databases. Data analysis will involve
        performing statistical tests for detection of long term-trends in water quality.
NPSMS Data
Summary
STATION TYPE:  Upstream Station
Chemical Parameters
PRIMARY CODE:  SiteB
YEAR: 1995
                         Parameter Name
                         Fecal Coliform, Membr Filter, M-FC Broth, 44.5 C
                         Fecal Streptoccoci 9230C
                         Nitrate + Nitrite (353.1 EPA, 1983)
                         Nitrogen, Kjeldahl, Total (MG/L as N)
                         Phosphorus, Total (MG/L as P)
                         Total Suspended Solids (2540c 17th SMEWWW)

                         STATION TYPE: Downstream Station
                         Chemical Parameters

                         Parameter Name
                         Fecal Coliform, Membr Filter, M-FC Broth, 44.5 C
                         Fecal Streptoccoci 9230C
                         Nitrate + Nitrite (3 53.1 EPA, 1983)
                         Nitrogen, Kjeldahl, Total (MG/L as N)
                         Phosphorus, Total (MG/L as P)
                         Total Suspended Solids (2540C 17th SMEWWW)
                         STATION TYPE: Upstream Station
                         Chemical Parameters

                         Parameter Name
                         Fecal Coliform, Membr Filter, M-FC Broth, 44.5 C
                         Fecal Streptoccoci 9230C
                         Flow, Stream, Instantaneous, CFS
                         Nitrate + Nitrite (353.1 EPA, 1983)
                         Nitrogen, Kjeldahl, Total (MG/L as N)
                         Phosphorus, Total (MG/L as P)
                         Total Solids (Residue) 2540B (17th SMEWWW)
                         Total Suspended Solids (2540C 17th SMEWWW)
                         STATION TYPE: Downstream Station
                         Chemical Parameters

                         Parameter Name
                         Fecal Coliform, Membr Filter, M-FC Broth, 44.5 C
                         Fecal Streptoccoci 9230C
                         Flow, Stream, Instantaneous (CFS)
                         Nitrate + Nitrite (353.1 EPA, 1983)
                         Nitrogen, Kjeldahl, Total (MG/L as N)
                         Phosphorus, Total (MG/L as P)
                         Total Solids (Residue) 2540B (17th SMEWWW)
                         Total Suspended Solids


4.5 C




VW)
Farm
Type
S
U
u
S
S
u
PRIMARY CODE:


4.5 C




WW)
Parm
Type
S
U
u
S
S
u
PRIMARY CODE:


4.5 C





/W)
WW)
Parm
Type
S
U
S
u
S
S
u
u
Reporting
Units
CFU/100ML
CFU/100ML
MG/L


MG/L
SiteC
Reporting
Units
CFU/100ML
CFU/100ML
MG/L


MG/L
SiteD
Reporting
Units
CFU/100ML
CFU/100ML
CFS
MG/L


MG/L
MG/L
QUARTILE VALUES
.75- -so- -25-
3600 1700 810
3700 1400 270
.53 .49 .45
.3 .22 .15
.3 .18 .1
8 5.0 4.0

QUARTILE VALUES
-75- -50- -25-
3400 1350 940
4150 1650 495
.56 .51 .46
.35 .22 1.7
.29 .2 .13
11 7 3

QUARTILE VALUES
.75- -so- -25-
81000 31000 7700
28000 10000 2600
.169 .04 .018
2.7 2.085 1.405
3.2 1.3 .615
.745 .45 .285
145 102 90
44.5 12.5 2
PRIMARY CODE: SiteE

.
14.5 C





VW)

Parm
Type
S
U
S
u
S
S
u
u
Reporting
Units
CFU/100ML
CFU/100ML
CFS
MG/L


MG/L
MG/L
QUARTILE VALUES
-75. -so- -25-
485000 60000 21000
215000 42500 8150
.171 .075 .042
3.275 1.925 1.28
12.00 2.80 1.65
2.865 .815 .59
309 139 114
71.5 13 3
                                                      137

-------
                                                                   Long Creek Watershed, North Carolina
NPSMS Data Summary (Continued)
                     STATION TYPE: Upstream Station
                     Chemical Parameters
                       PRIMARY CODE:  SiteH
                     Parameter Name
                     Fecal Coliform, Membr Filter, M-FC Broth, 44.5 C
                     Fecal Streptococci 9230C
                     Total Solids (Residue) 2540B (17th SMEWWW)
                     Total Suspended Solids (2540C 17th SMEWWW)
Farm
Type
S
U
u
U
Reporting
Units
CFU/100ML
CFU/100ML
MG/L
MG/L
QUAR
-75-
910
1300
75
8
                                                         -50-   -25-
                                                         630   270
                                                         360   100
                                                          68    61
                                                           5     3
Modifications Since
Project Started
Several ground water monitoring wells have been added. Beginning in the spring
of 1996, selected grab samples will be analyzed for cryptosporidium, giardia, and
E. coli.
TOTAL  PROJECT BUDGET
                            The estimated budget for the Long Creek Watershed National Monitoring Pro-
                            gram project for the life of the project is:
                            Project Element
                                     Funding Source (S)
                    Federal       State        Local        Sum
                            Proj Mgt
                            I&E
                            LT
                            WQ Monit
                            TOTALS
                            Source: Jennings et al., 1992
340,300
0
0
561,186
901,486
147,360
20,000
370,000
0
537,360
                                             98,240    585,900
                                             80,000    100,000
                                             80,000    450,000
                                             12,000    573,186
                                            270,240   1,709,086
Modifications Since
Project Started
A 319(h) grant has been awarded to provide cost share for BMP implementation.
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                             State and probably federal United States Department of Agriculture (USD A) -
                             Agricultural Conservation Program cost share programs will be essential for the
                             implementation of BMPs. The provisions of the North Carolina Water Supply
                             Watershed Protection Act (see section below) and the threat of additional regula-
                             tion will motivate dairy farmers to implement animal waste management and
                             erosion control BMPs.
                                              138

-------
                                                                     " Long Creek Watershed, North Carolina
 OTHER PERTINENT INFORMATION
                             The North Carolina Water Supply Watershed Protection Act, as applied to this
                             class of watershed, requires that 1) agricultural activities within one-half mile of
                             and draining to a water intake maintain at least a 10-foot vegetated buffer or
                             equivalent control and 2) animal operations of more than 100 animal units use
                             BMPs as determined by the North Carolina Soil and Water Conservation Commis-
                             sion. Other regulations in the Act apply to activities such as forestry, transporta-
                             tion, residential development,  and sludge application.

                             Project contributors are listed below:

                             •   Landowners

                             •   North Carolina Cooperative Extension Service

                             •   Gaston County Cooperative Extension Service

                             •   USDA Natural Resources Conservation Service (NRCS)

                             •   Gaston Soil & Water Conservation District

                             •   North Carolina Division of Soil and Water Conservation

                             •   United States Geological Survey

                             •   Gaston County Quality of Natural Resources Commission

                             •   North Carolina Division of Water Quality

                             •   Farm Service Agency (FSA)
PROJECT CONTACTS
Administration
David Harding
DEHNR
Div. of Water Quality
P.O. Box 29535
Raleigh, NC  27626-0535
(919) 733-5083; Fax (919) 715-5637
Internet: david@dem.ehnr.state.nc.us

Martha A. Burris
County Extension Director
P.O. Box 476
Dallas, NC 28034-0476
(704) 922-0303; Fax (704) 922-3416
Internet: mburris@gaston.ces.ncsu.edu

William A. Harman
Extension Associate
NCSU Water Quality Group
Campus Box 7637
Raleigh, NC  27695-7637
(919) 515-8245; Fax (919) 515-7448
Internet: will_harman@ncsu.edu
                                               139

-------
                                                                        Long Creek Watershed, North Carolina
Land Treatment
Water Quality
Monitoring
 Information and
 Education
Glenda M. Jones, Administrator
Gaston Soil & Water Conservation District
1303 Cherryville Highway
Dallas, NC 28034-4181
(704) 922-4181

Garland Still
Natural Resources Conservation Service
1303 Cherryville Highway
Dallas, NC 28034-4181
(704)922-3104

Richard Farmer
Extension Associate
P.O. Box 476
Dallas, NC 28034-0476
(704) 922-0303; Fax (704) 922-3416
Internet: rfarmer@gaston.ces.ncsu.edu

Daniel E. Line
Extension Specialist
NCSU Water Quality Group
Campus Box 7637
Raleigh, NC  27695-7637
(919) 515-8243; Fax (919) 515-7448
Internet: dan_line@ncsu.edu

Sean Cronin
Extension Agent
Natural Resources
P.O.  Box 476
Dallas, NC 28034-0476
(704) 922-0303; Fax (704) 922-3416
Internet: scronin@gaston.ces.ncsu.edu
                                                 140

-------
                                Oklahoma

                         Peacheater Creek
                               Section 319
      National Monitoring Program Project
Figure 25: Peacheater Creek (Oklahoma) Project Location
               141

-------
                                                                    i Peacheater Creek, Oklahoma
                                                    Tyner Creek
  Legend
  •  Chemical Monitoring Site
  ^  Biological Monitoring Site
                                                                                  N
                                                                Peacheater Creek
Figure 26: Water Quality Monitoring Stations for Peacheater Creek (Oklahoma) Watershed
                                        142

-------
                                                                                 Peacheater Creek, Oklahoma
PROJECT OVERVIEW
                               Peacheater Creek is located in eastern Oklahoma (Figure 25). The watershed is
                               primarily pastureland and forestland with little cropland and rangeland. There are
                               51 poultry houses and 9 dairies in the watershed, along with 1200 beef cattle. Fish
                               and macroinvertebrate habitat quality is impaired by large gravel bars generated
                               from streambanlc erosion. Cattle traffic and forestry activities are thought to be
                               major contributors to streambank erosion. Baseflow monitoring shows intermit-
                               tent nutrient levels that contribute to creek eutrophication. Eutrophication impacts
                               downstream of Peacheater Creek include nuisance periphyton growth in the
                               Illinois River and phytoplankton blooms in Lake Tenkiller.

                               The project team has completed an extensive natural resource and stream corridor
                               inventory. Data from the inventory have been digitized and mapped in a geo-
                               graphic information system. A distributed parameter watershed model has been
                               used for determining critical areas for treatment. Critical areas are pasturelands,
                               riparian areas, and dairies. Nutrient management planning is underway to im-
                               prove poultry and dairy waste utilization on cropland and pasrureland. A paired
                               watershed study (Figure 26) is planned using chemical parameters. Biological and
                               habitat monitoring is planned for tributaries and the main stem stream.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
 Impairments
 Pre-Project
 Water Quality
Water resources of concern are the Illinois River and Lake Tenkiller, a down-
stream impoundment of the river. The project water resource is Peacheater Creek,
a fourth order stream, with baseflow ranging from 5 to 10 cubic feet per second.
Peacheater Creek flows into the Illinois River upstream of Lake Tenkiller.

Peacheater Creek is used for recreation and aquatic life support; however, such
uses are impaired by nutrient enrichment and loss of in-stream habitat. The
Illinois River has been degraded by loss of water clarity and nuisance periphyton
growth. Lake Tenkiller has had phytoplankton blooms and the hypolimnion
becomes anoxic during the summer.

Baseflow monitoring for both Peacheater Creek (treatment watershed) and Tyner
Creek (control watershed) for 1990-1992 shows that dissolved oxygen levels are
high (e.g. generally well above 5 mg/1), indicating little concern about oxygen
demanding pollutants. Turbidity was very low, with all samples taken less than 8
NTU. Specific conductivities range from 120 to 183. Nitrate-nitrogen concentra-
tions for Peacheater Creek range from 0.82 mg/1 to 5.66 mg/1. Nitrate-nitrogen
levels, if near 3 mg/1, may be  considered elevated if significantly above back-
ground for the area. Total Kjeldahl nitrogen  (TKN) levels range from the detec-
tion limit of 0.2 mg/1 to 1.5 mg/1. Eleven of the thirty TKN observations were
equal to or greater than 0.3 mg/1, which is sufficient organic nitrogen to promote
eutrophication. Generally, total Kjeldahl nitrogen (TKN) concentrations for Tyner
Creek were lower than for Peacheater Creek. Three of the thirty baseflow samples
showed total phosphorus (TP) levels were above 0.05  mg/1, which maybe consid-
ered a minimum level for eutrophication. Storm sample TP concentrations are
elevated.

Both Peacheater and Tyner Creeks have poor in-stream habitat. Large chert gravel
bars cover extensive portions  of the streambed in Peacheater Creek. These gravel
bars continue to grow and shift after major runoff events. The gravel covers
natural geologic and vegetative substrates, reducing habitat quality for
                                                   143

-------
                                                                            i Peacheater Creek, Oklahoma
Current Water
Quality Objectives

Modifications Since
Project Initiation

Project Time Frame

Project Approval
macroinvertebrates and fish. Peacheater Creek has extensive streambank erosion
due to forestry activities and cattle traffic. The streambank erosion is also believed
to be further accelerated by the destabilization of the stream channel by the
growing bed load.

Restore recreational and aquatic life beneficial uses in Peacheater Creek and
minimize eutrophication impacts on the Illinois River and Lake Tenkiller.

None.
1995 to 2000

Approved October, 1995
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorological Factors
Land Use
Pollutant Sources
Modifications Since
Project Started
The Peacheater Creek watershed area is 16,209 acres. The creek drains via the
Baron Fork River to the Illinois River, which then is impounded to form Tenkiller
Ferry Lake.

Average baseflow for Upper Tyner and Peacheater creeks is 5-10 cubic foot per
second.

Rocks in the project area are chert rubble. Surface rocks are from the Boone
Formation, the Osage Series, and the Mississippian Age.

Project area soils are generally sandy loams and silt loams with high infiltration
rates. Typical slopes range from 2-5%, and a large portion of the watershed is
steeply sloped land.

Land Use                94
Forest land               36
Grassed pastureland        14
Brushy pastureland         40
Cropland                   3
Rangeland                  7
TOTAL                   100

Primary sources of pollution include poultry houses and dairies in the treatment
and control watersheds. Other sources of nutrients could be from septic systems of
private residences. Peacheater Creek has 51 poultry houses and 9 dairies, along
with 176 private residences. Upper Tyner Creek has 65 poultry houses, 7 dairies,
and 150 private residences.

None.
INFORMATION, EDUCATION, AND PUBLICITY
                             Several methods are being used to educate the general public and the agricultural
                             community about pollution control and water quality management. A primary
                             concern in the watershed is animal waste and nutrient management. Producer
                             meetings are used to provide updates on regulations for concentrated animal
                                                144

-------
                                                                                  Peacheater Creek, Oklahoma
Progress Towards
Meeting Goals
feeding operations, which include egg laying poultry operations. Records must be
kept on waste cleanout operations and litter applications. Cooperative Extension
Service and U.S. Department of Agriculture (USDA) Natural Resources Conser-
vation Service (NRCS) personnel are working together to promote the use of
waste holding ponds for dairies in the watershed. Soil nutrient sampling is free
and is conducted to identify fields with excessive phosphorus levels. Litter testing
is also available for broiler and laying operations. Litter application demonstra-
tions are being used to illustrate nutrient management principles on bermuda
grass and fescue.

Rainfall simulator studies and demonstrations have been held to show the effect of
cropland best management practices (BMPs) on water quality. The effects of
nutrient application rate and filter strips were demonstrated during a summer field
day. Future rainfall simulator study demonstrations are planned.

Newsletters provide general information on agriculture and selected water quality
topics. Producers in the watershed receive newsletters from the Adair County
Extension Service and the Oklahoma Cooperative Extension Service Unit.

A three-day summer youth camp was held during the summer of 1996 to provide
water quality education. An inner-tubing excursion was used to show the extent
and effect of streambank erosion on stream habitat quality. Youth camp partici-
pants also tested the chemical quality of Peacheater Creek using portable water
quality kits.
NONPOINTSOURCE CONTROL STRATEGY
Description
Land treatment implemented through the project will be designed to 1) reduce
nutrient loading to the Illinois River system and Tenkiller Lake and 2) restore
streambanks with the objective of improving pool depth and reducing gravel
loading in the system. Implementation of land treatment is on hold until the
calibration phase has been completed.

In total, the eight dairies in the Peacheater Creek watershed have approximately
800 cows. Seven of the eight dairies have animal waste management plans. A
total of seven waste management systems, including waste storage structures, are
recommended, and three have been installed to date. Eight planned grazing
systems have been recommended, and one planned grazing and one cell grazing
system have been adopted under an earlier program. All implementation activities
are on hold until the calibration phase of the project is complete.

There are 59 poultry houses in the watershed with a total of approximately
1,300,000 birds. Types of poultry grown in the watershed include broilers, layers,
pullets, and breeder hens. Seventy-five percent of the producers have current
Conservation Plans of Operation. Fifteen mortality composters have been recom-
mended and five have been installed. Buffer zones along streams have been
recommended to reduce nutrient runoff from land applied manure.  The current
extent of buffers in the watershed is not reported. For the sole layer operation, a
waste holding pond has been recommended but has not yet been constructed.
Short term storage for litter is recommended when poultry house cleaning occurs
during wet weather or outside the crop growth season.
                                                   145

-------
                                                                               i Peacheater Creek, Oklahoma
Modifications Since
Project Started
There are approximately 1,200 beef cattle in the watershed. Recommended BMPs
include planned grazing systems, cell grazing systems, buffer zones adjacent to
streams, watering facilities, critical area vegetation, and soil testing to support
nutrient management planning in pastures receiving land applied litter.

Twelve critical riparian areas have been identified. Streambank erosion has been
caused by riparian area forestry practices, cattle traffic, and cattle grazing in
riparian areas. Recommended BMPs include fencing, no land application of litter
in riparian areas, off-site watering systems, and vegetative establishment. The
stream will also be classified following Rosgen Methodology for streambank and
channel restoration.

The implementation program for Peacheater Creek watershed is deferred until the
calibration phase of the project is complete. A final implementation plan will be
drafted based upon water quality, biological and habitat assessment results, as well
as nutrient reductions for the Illinois River and Tenkilier Ferry Lake.
WATER QUALITY MONITORING
Design
Modifications Since
Project Started

Parameters
Measured
The water quality design for the Peacheater Creek 319 National Monitoring
Program project is a paired design. Peacheater Creek watershed treatment is
paired with Tyner Creek watershed (control) (Figure 26). Water quality monitor-
ing occurs at each watershed outlet. Habitat and biological monitoring occurs in
both streams at appropriate locations.
None.
Biological

Periphyton productivity
Fisheries survey
Macroinvertebrate survey
Intensive and extensive habitat assessment
Bank erosion and soil bank sampling
                               Chemical

                               Dissolved oxygen (DO)
                               Specific conductivity
                               pH
                               Alkalinity
                               Turbidity
                               Total Kjeldahl nitrogen (TKN)
                               Nitrate + nitrite nitrogen (NOs +
                               Total phosphorus (TP)
                               Total suspended solids (TSS)
                               Sulfate (SO4~)
                               Chloride (Cl)
                               Hardness
                               Covariates

                               Stream discharge
                               Precipitation
                                                  146

-------
                                                                                i Peacheater Creek, Oklahoma
Sampling Scheme
                   Chemical parameters will be monitored weekly from My through January,
                   monthly during February through June, and during storm events, for a duration of
                   20 weeks. Storm event monitoring is stage-activated and samples are taken on the
                   rising and falling limbs of the hydrograph. Concentration samples are flow-
                   weighted composites.

                   Biological monitoring varies considerably with assemblage being sampled.
                   Periphyton productivity will be measured in the summer and the winter.
                   Macroinvertebrates will be monitored twice per year; once in the summer and
                   once in the winter. Fish will be monitored once per year. Intensive habitat will be
                   monitored annually. Extensive habitat will be monitored on alternate years. Bank
                   erosion and bank soil sampling will be monitored on alternate years.
  Monitoring Scheme for the Peacheater Creek Section 319 National Monitoring Program Project
  Design
 Sites or
Activities
   Primary
  Parameters
                                              Covariates
              Frequency of
             WQ Sampling
  Frequency of
Habitat/Biological
   Assessment    Duration
  Faked
Tyner Creekc
Peacheater CreekT
Periphyton productivity
Fisheries survey
Macroinvertebrate survey
Habitat assessment
Bank erosion

Turbidity
DO
TKN
NO3 + NO2
TP
TSS
Stream discharge
Precipitation
   Summer / winter
   Yearly
   Summer/winter
   Alternate years
   Alternate years
2 yrs. pre-BMP
1 yr. BMP
1 yr. post-BMP
                                                             Weekly (July-Jan.)
                                                             Monthly (Feb.-June)
                                                             Storm event
  GControl watershed
  TTreatment watershed
 Modifications Since
 Project Started

 Water Quality Data
 Management and
 Analysis
                    None.
                    Chemical parameters will be entered into the U.S. Environmental Protection
                    Agency (USEPA) STORET system, the Oklahoma Conservation Commission
                    (OCC) Fox Pro Water Quality Data Base and OCC office library. Biological
                    parameters will be entered into the OCC Fox Pro Water Quality Data Base and the
                    collections at the Oklahoma Museum of Natural History, and archived in the
                    BIOS data base.
 NPSMS Data
 Summary
                    The OCC will prepare data and summary statistics for entry into the USEPA
                    Nonpoint Management System Software (NPSMS).
 Modifications Since
 Project Started

 Progress Towards
 Meeting Goals
                    None.
                     The sampling program was initiated in December, 1995. An extensive habitat
                     assessment, based on transects every 100 meters over the stream length, has been
                     completed for both streams. Permanent transects have been established. Intensive
                     habitat assessments, consisting of transects every 20 meters at biological sites,
                                                   147

-------
                                                                        i Peacheater Creek, Oklahoma
                            have been completed and replicated for quality assurance. A fishery survey of both
                            streams has been completed. Measurements of high flow events continue to be
                            conducted on both Peacheater Creek and Tyner Creeks in order to update the
                            discharge curve. A depth/discharge curve for programming the auto-sampler in
                            order to collect flow-weighted high flow water samples has been completed for
                            both Peacheater and Tyner Creeks, and the samplers are fully operational. The
                            winter sets of periphytometer samples have been collected and processed, and are
                            awaiting laboratory analysis.
 TOTAL PROJECT BUDGET
Modifications Since
Project Started
                            The estimated budget for the Peacheater Creek National Monitoring Program
                            project for the life of the project is:

                            Project Element                         Funding Source ($)
                                                     Federal    Si
                            WQ Monitoring
                            Flow Monitoring
                            Implementation
                            TOTALS

                            Source:  Phillip Moershel (Personal Communication), 1996
None.
Federal
250,000
100,000
108,000
458,000
State
166,667
66,670
72,000
305,337
Local
NA
NA
NA
NA
Sum
416,667
166,670
180,000
763,337
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS


                            This project compliments a larger program to improve the water quality of the
                            Illinois Paver and Lake Tenkiller. An effort to establish a Total Maximum Daily
                            Load (TMDL) for the system has been initiated, which may build upon the results
                            in Peacheater Creek.
 Modifications Since
 Project Started
None.
OTHER PERTINENT INFORMATION
                           None.
PROJECT CONTACTS
Administration
John Hassell
Oklahoma Conservation Commission
1000 W. Wishire St. Suite 123
Oklahoma City, Oklahoma 73116-7026
(405) 858-2004; Fax (405) 858-2012
Internet: jhassell@occwq.state.ok.us
                                            148

-------
                                                                             1 Peacheater Creek, Oklahoma
Land Treatment
Water Quality
Monitoring
Information and
Education
Otis Bennett
Cherokee County Conservation District
1009 S. Muskogee Avenue
Tahlequah, OK 74464-4733
(918) 456-1919; Fax (918) 456-3147

Ann Colyer
USDA-NRCS
102 W. Pine St.
Stilwell, OK 74960-2652
(918) 696-7612; Fax (918) 696-6114

Andy Inman
USDA-NRCS
Sequoyah County Conservation District
10 IMcGee Drive
Sallisaw, OK 74955-5258
(918) 775-3045

Phillip Moershel
Oklahoma Conservation Commission
1000 W. Wishire St. Suite 123
Oklahoma City, Oklahoma 73116-7026
(405) 858-2008; Fax (405) 858-2012
Internet: phmoershel@occwq.state.ok.us

Dan Butler
Oklahoma Conservation Commission
1000 W. Wishire St. Suite 123
Oklahoma City, Oklahoma 73116-7026
(405) 858-2006;  Fax (405) 858-2012

Dean Jackson
Adair County Extension Service
Box 702
Stilwell, OK 74960
(918) 696-2253;  Fax (918) 696-6718

Mike Smolen
Oklahoma State University
218  Agricultural Hall
Box 702
Stillwater, OK 74078-0469
(405) 744-5653; Fax (405) 744-6059
Internet: srnolen@agen.okstate.edu
                                                149

-------
                                i Peacheater Creek, Oklahoma
150

-------
                                              Oregon

                        Upper Grande Ronde Basin
                                 Section 319 Project
(Pending Section 319 National Monitoring Program Project Approval)
                   Oregon
     Figure 27: Upper Grande Ronde Basin (Oregon) Project Location
                       151

-------
                                                                 Upper Grande Ronde Basin, Oregon
Legend of Monitoring Sites

2 - Meadow Creek - Starkey
3 - Dark Canyon Creek - Upper Reach
4 - McCoy Creek - Middle Reach
5 - Dark Canyon Creek - Lower Reach
6 - McCoy Creek - Lower Reach #1
7 - McCoy Creek - Lower Reach :#2
8 - Meadow Creek - Lower Reach
9 - Lookout Creek
10 - Limber Jim Creek - Upper Reach
11 - Limber Jim Creek - Lower Reach
      N
 Figure 28: Water Quality Monitoring Stations for Upper Grande Ronde Basin (Oregon) Watershed
                                           152

-------
                                                                           Upper Grande Ronde Basin, Oregon
PROJECT OVERVIEW
                               The Upper Grande Ronde Basin (695 square miles) is located in the Columbia
                               Intermontane Central Mountains of northeast Oregon (Figure 27). The Grande
                               Ronde River traverses primarily forest and grazing lands draining into the Snake
                               River, a major tributary of the Columbia River. The study area is included in the
                               ceded lands of the Confederated Tribes of the Umatilla Indian Reservation
                               (CTUIR), and is a culturally significant area.

                               The watershed has historically been important for anadromous fish production,
                               but from about 1970 to the present fish numbers have been declining. Land use
                               activities, such as grazing, timber harvest, road construction, and livestock pro-
                               duction, have been cited as contributing to fish and other aquatic species' habitat
                               degradation.

                               Water temperature and loss of physical habitat have been identified by the US
                               Forest Service (USFS) as the most important factors affecting spring Chinook
                               salmon and steelhead populations (Hafele, 1996).  An important cause of increased
                               stream temperature is the loss of riparian vegetation. It has been estimated that
                               land use activities have reduced stream shading from a potential of 80% to a total
                               of 28% (Hafele, 1996). As a result of these and other water quality violations
                               (primarily pH), the Grande Ronde has been listed by the Oregon Department of
                               Environmental Quality (ODEQ) as water quality limited.

                                Since 1993, a water quality monitoring program has been conducted by ODEQ to
                               evaluate the basin's biological communities and the physical and chemical factors
                               that affect them. This monitoring effort is pending formalization as a US Environ-
                               mental Protection Agency (USEPA) Section 319 National Monitoring Program
                               project. The monitoring effort targets five subbasins within the Upper Grande
                               Ronde Basin. Water quality monitoring is based on a paired watershed design for
                               two highly impacted basins, while other basins represent a range of less impacted
                               control sites. Additionally, an upstream/downstream approach is used to evaluate
                               changing land use along individual streams. The major monitoring components
                               include habitat, macroinvertebrates, fish and water quality. A significant measure
                               of success will be a reduction in maximum summer temperatures, improved
                               habitat for aquatic life,  and increased biotic index scores for fish and
                               macroinvertebrates.

                               The Upper Grande Ronde Basin 319 National Monitoring Program project (pend-
                               ing) has evolved from local, state, and tribal cooperation. In 1995, a watershed
                               assessment was completed by ODEQ under the Oregon Watershed Health Pro-
                               gram (Bach, 1995). ODEQ is currently carrying out a Total Maximum Daily Load
                               (TMDL) study and developing  waste load allocations for the basin. The USFS has
                               developed a restoration plan for anadromous fish  in the Upper Grande Ronde
                               Basin and identified desired future conditions (Hafele, 1996). Stream habitat
                               restoration activities aimed at improving habitat conditions will be implemented
                               on McCoy Creek in cooperation with the landowner and CTUIR.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
The total drainage area of the Upper Grande Ronde Basin is approximately 695
square miles with a stream density of 1.44 (miles/square miles). Ten sites from
five subbasins located in the upper southwest portion of the watershed have been
selected for this monitoring project. They are as follows:
                                                  153

-------
                                                                           Upper Grande Ronde Basin, Oregon
Water Uses and
Impairments
Pre-Project
Water Quality
Current Water
Quality Objectives
                               McCoy Creek
                               Dark Canyon Creek
                               Meadow Creek
                               Lookout Creek
                               Limber Jim Creek
                          55.3 sq. mi.
                          18.8 sq. mi.
                          56.2 sq. mi.
                          15 sq. mi.
                          18.8 sq. mi.
paired basin (3 sites)
paired basin
paired basin
single site
paired basin
 The designated beneficial uses of concern in the basin include anadromous
.populations of spring/summer Chinook salmon, summer steelhead, and resident
 populations of bull trout.

 Important beneficial uses of the streams that drain the watershed include cold
 water fish migration, spawning, and rearing; domestic and agricultural water
 supply, primary and secondary contact recreation; and wildlife habitat.

 Most water chemistry violations (mostly pH) in the Grande Ronde Basin have
 been shown to occur in the main stem of the Grande Ronde. Water chemistry
 results for 1993-95 indicate that no significant water chemistry problems were
 observed for the ten study sites based on sixteen separate parameters.

 Monitoring of habitat conditions indicates that Lookout Creek has the most stable
 and highest quality habitat with Dark Canyon Creek the lowest. Habitat condi-
 tions in McCoy Creek show impaired conditions at the two lower sites and moder-
 ately impaired at the upper site. Lower McCoy Creek is  characterized by
 channelized banks, little riparian vegetation, and shallow pools and riffles, and is
 the target of the stream restoration efforts. Habitat conditions are summarized in
 Figure 28.

 Water temperature has been identified as a significant factor affecting both water
 quality and biological communities in the Grande Ronde. Temperature in the
 basin has been characterized by placing continuous recording thermographs at the
 top and bottom of each stream reach selected for bioassessment. For the Grande
 Ronde Basin, the water temperature standard is based on the 7-day maximum
 mean and should not exceed 17.8°C for cold water species when salmonids are
 not spawning; water temperature should not exceed 12.8°C during salmonid
 spawning and incubation. The 17.8°C temperature maximum applies to the study
 sites during July, August and September. This maximum temperature was ex-
 ceeded at all sites except Limber Jim Creek in 1993 and Upper Limber Jim and
 Lookout Creeks in 1994. The sites on McCoy Creek, Dark Canyon Creek and
 Meadow Creek generally exceeded the standard throughout the sampling period.

 Project objectives include the following:

 •   To improve salmonid and aquatic macroinvertebrate communities in McCoy
    Creek by restoring habitat quality and lowering stream temperatures.

 •   To quantitatively document a cause-and-effect relationship between improved
    habitat, lower water temperatures and improved salmonid and
    macroinvertebrate communities.

 Differences in fish and macroinvertebrate communities and pre-project water
 quality results suggest that the above objectives can be achieved. The results of
 snorkel surveys for fish completed during the summers of 1994 and 1995 show
 two interesting factors

    Rainbow trout were present in all streams, including Meadow and McCoy
    Creeks, where summer temperatures exceed 25°C, well above the acceptable
    range for trout. Temperature measurements indicate a 5°C gradient was
    present in pools as shallow as 18 inches. These areas of temperature refugia
                                                  154

-------
                                                                          Upper Grande Ronde Basin, Oregon
Project Time Frame

Project Approval
    may be critical for fish survival under the temperature conditions of streams
    like Meadow and McCoy Creeks.

•   Fish communities at Meadow and McCoy creeks were dominated by warm
    water red-sided shiner and dace. These species were scarce or completely
    absent at the other study sites, presumably because of cooler water
    temperatures. It is expected that fish communities will shift from one
    dominated by red-sided shiner and dace to one dominated by trout in the
    McCoy reaches if water temperatures can be lowered by restoration work.

Macroinvertebrate results from 1993 show a similar pattern to the fish surveys
and temperature results. It is expected then that if temperatures in McCoy Creek
can be improved through habitat restoration, the macroinvertebrate and fish
communities will respond favorably and that these responses can be measured.

1993-2003 (if funding permits)

Pending.
PROJECT AREA CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorological Factors
Land Use
Pollutant Sources
The Upper Grande Ronde Basin Monitoring Project consists often study sites in
five subbasins located within the Blue Mountain eco-region (Omernick, 1987).
The total area of the Upper Basin is approximately 695 square miles, with 1,000
miles of stream (Bach, 1995).

The study region is characterized by a semi-arid climate and rugged mountains in
the headwater areas. Temperature and precipitation vary with elevation, which
ranges from approximately 2,300 feet to 7,800 feet. The climate is characterized
by warm, dry summers and cold, moist winters. At elevations above 5,000 feet,
average annual precipitation is greater than 50 inches, and usually occurs as snow
(Bach, 1995).

Slopes vary throughout the basin, with relatively gentle slopes in the valley and
steeper slopes  (as high as 90% in some areas) in the upper parts of the watershed
(Bach, 1995).  The combination of slope, rainfall, and snowpack can lead to large
runoff events in the mid and upper  elevations.

Approximately 60% of the land in the Grande Ronde Basin is devoted to forestry,
while approximately 36% is agricultural. Land use activities such as grazing,
timber harvesting, road construction, and livestock practices have been cited as
causes for beneficial use impairment. Land ownership in the Upper Basin is
approximately 53% private and 47% federal. The only two land use/cover types
present in the  study subbasins are range and evergreen forest.

The major sources of nonpoint source temperature pollution are loss of riparian
habitat through historic grazing practices and channel modifications.
                                                 155

-------
                                                                       Upper Grande Ronde Basin, Oregon
INFORMATION, EDUCATION, AND PUBLICITY
                             There has been little quantitative documentation of the effects of habitat restora-
                             tion on stream temperatures and aquatic communities. The Upper Grande Ronde
                             Basin Monitoring project will provide useful information on the effects of riparian
                             restoration on fish and macroinvertebrate habitat improvement for areas elsewhere
                             in the basin. This project will also enhance interagency coordination among other
                             agencies and watershed councils which have expressed interest in restoration
                             work. Interagency cooperation is reflected by the involvement in this project of
                             Oregon Department of Fish and Wildlife (ODF&W), NRCS, local Soil and Water
                             Conservation Districts (SWCD), USFS, USEPA, and the CTUIR.
NONPOINT SOURCE CONTROL STRATEGIES
Description
The nonpoint source treatment to be implemented in the study area will consist of
stream channel and riparian restoration activities on the lower reach of McCoy
Creek. Lower McCoy Creek is characterized by channelized banks, little riparian
vegetation, and shallow pools and riffles. Streambank stabilization and riparian
revegetation represent the minimal amount of restoration activities to be imple-
mented. Increasing the width-to-depth ratio and restoring the wet meadow condi-
tions should increase riparian canopy and shading. More intensive restoration
activities may be used to restore the old channel network and allow the stream to
meander along its old bed. The Confederated Tribes of the Umatilla Indian
Reservation will be coordinating the restoration work in cooperation with ODEQ
(ODEQ, 1995).
WATER QUALITY MONITORING
 Design
 Parameters
 Measured
A paired watershed approach is being used for the McCoy Creek (treatment) /
Dark Canyon (control) subbasins to document change in stream temperatures and
aquatic communities as a result of best management practice (BMP) implementa-
tion. Dark Canyon is the control subbasin, while McCoy Creek is the treatment
basin. Upstream / downstream monitoring sites of these subbasins will be imple-
mented in both. Three additional subbasins will be used as background subbasins
representing a range of water quality and habitat conditions.

Biological

Habitat
Macroinvertebrates
Fish
                              Chemical and Other

                              Continuous water temperature
                              Specific conductivity
                              Alkalinity
                              Dissolved oxygen (DO)
                              pH
                              Ammonia (NHs)
                              Biochemical oxygen demand (BOD)
                              Total organic carbon (TOC)
                              Turbidity

                                                156

-------
                                                                          Upper Grande Ronde Basin, Oregon
Sampling Scheme
Covariates

Continuous air temperature
Discharge
Precipitation (from nearby climate station)
Shading and solar input
Time of travel
Slope or gradient
Width/depth measurements.

Water quality monitoring is conducted from early April through early October. Air
and water temperature is measured continuously at each site throughout the
monitoring season. Water quality, habitat, and macroinvertebrate surveys are
conducted three times and fish snorkel surveys are done once during each moni-
toring season. The methods used for identifying sites are based on a modified
HanMn and Reeves procedure (Hafele, 1996). The habitat and macroinvertebrate
assessment procedures follow Oregon's biomonitoring protocols.

Time of travel data, to be used in temperature modeling, have been collected
during the 1996 monitoring season and will be collected again after restoration
work is completed. Pool volumes and detailed temperature refugia measurements
are being collected during the 1996 monitoring season. Photo and video documen-
tation taken at all study sites during summer low flows will provide before and
after documentation of habitat conditions.
 Monitoring Scheme for the Upper Grande Ronde Basin Section 319 National Monitoring Program
 Project
Design
Paired
Upstream/
downstream
Sites or
Activities
McCoy Creek
Dark Canyon
Creek
Primary
Parameters
Habitat
Macroinvertebrate
Fish
Water temperature
Frequency of
Frequency of Habitat/Biological
Covariates WQ Sampling Assessment Duration
Air temperature
Discharge
Precipitation
3 times yearly 2 years pre-BMP
5 years BMP
5 years post-BMP
Water Quality Data
Management and
Analysis
NPSMS Data
Summary
Water quality data are stored and maintained locally by ODEQ in spreadsheet
form and later will be transferred to USEPA's STORET and NonPoint Source
Management System (NPSMS) databases. Other reporting formats involve spread-
sheet tabulations and graphic presentation. Data will be shared among participat-
ing agencies. Data analysis will involve performing statistical tests for detecting
trends in water and habitat quality and aquatic communities.

Currently unavailable.
                                                 157

-------
                                                                  Upper Grande Ronde Basin, Oregon
TOTAL PROJECT BUDGET
                           The estimated budget for the Upper Grande Ronde National Monitoring Project
                           for the life of the project is based on 10 years of funding, with four years com-
                           pleted (1993-1996):
                           Project Element
                                        Federal
Proj Mgt
I&E
LT
WQ Monit
TOTALS
230,000
NA
185,000
470,000
885,000
92,000
NA
NA
188,000
280,000
                             Funding Source (S)
                         State      Local       Tribal      Total
                                                                NA         NA    322,000
                                                                NA         NA        NA
                                                                NA       70,000    255,000
                                                                NA         NA    658,000
                                                                NA       70,000   1,235,000
                           Source: Rick Hafele, personal communication (1996),
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                           The Upper Grande Ronde Basin Monitoring Project is a major component of the
                           Grande Ronde Watershed Enhancement Project, a cooperative effort between
                           ODEQ, EPA, NRCS and Union County SWCD.

                           The National Marine Fisheries Service (NMFS) listed the Snake River spring/
                           summer Chinook salmon as an endangered species under the Endangered Species
                           Act (ESA) in August 1994. The US Fish and Wildlife Service determined the Bull
                           trout to be warranted for ESA listing in February 1995. Bull trout are also on the
                           Oregon sensitive species list. Snake River summer steelhead are currently classi-
                           fied as a stock of concern by the Oregon Department of Fish and Wildlife, sensi-
                           tive by the USFS, and part of a region-wide review for potential listing under the
                           ESA (Bach 1995).
OTHER PERTINENT INFORMATION
                           None.
PROJECT CONTACTS
Administration
Rick Hafele
Oregon Department of Environmental Quality Labs
Biomonitoring Section
1712 S.W. llth Avenue
Portland, OR 97201
(503) 229-5983; Fax: (503) 229-6924
Internet: rick.hafele@state.or.us
                                            158

-------
                                                                          Upper Grande Ronde Basin, Oregon
Land Treatment
Water Quality
Monitoring
Mike Purser, DNR Forest Hydrologist/Watershed Management Specialist
Confederated Tribes of the Umatilla Indian Reservation
Department of Natural Resources
P.O. Box 638
Pendleton, OR 97801
(503) 278-5206; Fax: (503) 276-0540

Rick Hafele
Oregon Department of Environmental Quality Labs
Biomonitoring Section
1712 S.W. llth Avenue
Portland, OR 97201
(503) 229-5983; Fax: (503)229-6924
Internet: rick.hafele@state.or.us
                                                  159

-------
                           Upper Grande Ronde Basin, Oregon
160

-------
                                    Pennsylvania

               Pequea and Mill Creek Watershed
                                      Section 319
           National Monitoring Program Project
             Pennsylvania
             Project Area
Figure 29: Pequea and Mill Creek (Pennsylvania) Watershed Project Location
                     161

-------
                                                                  Pequea and Mill Creek Watershed, Pennsylvania

                                                                                                     \
                                                                                               N
                                                                                               t
           Kllomefejs
               0
.5
              Miles
Water Quality Site and
Continuous Flow Gage Station
Water Quality Site and
Intermittent Flow Station
Precipitation Gage
Nest of 4 Wells
Streams
Watershed Boundary
Figure 30:  Water Quality Monitoring Stations for Pequea and Mill Creek (Pennsylvania) Watershed
                                                 162

-------
                                                                 Pequea and Mill Creek Watershed, Pennsylvania
PROJECT OVERVIEW
                              The Big Spring Run is a spring-fed stream located in the Mill Creek Watershed of
                              southcentral Pennsylvania (Figure 29). Its primary uses are livestock watering,
                              aquatic life support, and fish and wildlife support. In addition, receiving streams
                              are used for recreation and public drinking water supply. Sampling of benthic
                              macroinvertebrate communities indicated poor water quality at five of six sites.
                              Other stream uses (recreation and drinking water supply) are impaired by elevated
                              bacteria and nutrient concentrations.

                              Uncontrolled access of more than 220 dairy cows and heifers to each of the two
                              watershed streams is considered to be a major source of pollutants. Pastures
                              adjacent to streams also are thought to contribute significant amounts of nonpoint
                              source (NFS) pollutants. Therefore, proposed land treatment will focus on
                              streambank fencing to exclude livestock from streams, except for cattle crossings,
                              which will also be used for drinking water access for the cattle. This will allow a
                              natural riparian buffer to become established,  which will stabilize streambanks
                              and potentially filter pollutants from pasture runoff.

                              Water quality monitoring is based on a paired watershed design in which the
                              proposed NPS control is to implement livestock exclusion fencing on nearly 100
                              percent of the stream miles in the treatment subwatershed (Figure 30). Grab
                               samples are collected every 10 days at the outlet of each paired subwatershed from
                               April through November. Storm event, ground water, biological, and other moni-
                               toring is planned to help document the effectiveness of fencing in the treatment
                               subwatershed.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
 Water Uses and
  Impairments
 Pre-Project
 Water Quality
The study area encompasses about 2.8 and 2.7 miles of tributary streams in the
treatment and control subwatersheds, respectively. Annual mean discharges for
the 1994 water year were 2.39 arid 4.06 cfs at the outlets of the treatment and
control subwatersheds, respectively.

Sampling of benthic macroinvertebrates at three sites in each subwatershed
indicated poor water quality (organic enrichment) except for the most upstream
site in the treatment subwatershed. The subwatershed streams have relatively high
nutrient and fecal coliform concentrations that contribute to use impairments of
receiving waters.

Onetime baseflow grab sampling at four and seven locations in the control and
treatment subwatershed are presented in tabular form:
                                  Treatment
                                  Control
                                               Fecal coliform
                1,100-38,000
                   10,000
  TP
(mg/0

.06-.25
.02-.04
 OP
(mg/1)

.03-. 15
.01-.03
                                                  TKN   NOa+NOi
                                                  (mg/1)     (mg/1)
.3-1.6
 .1-.3
10-18
4-12
  Current Water
  Quality Objectives
 The overall objective is to document the effectiveness of livestock exclusion
 fencing at reducing NPS pollutants in a stream. Another objective is to reduce
 annual total ammonia plus organic nitrogen and total phosphorus loads from the
 project watershed by 40 percent.
                                                   163

-------
                                                              Pequea and Mill Creek Watershed, Pennsylvania
 Modifications Since
 Project Initiated

 Project Time Frame

 Project Approval
 None.


 October, 1993 to September, 1998-2003

 July, 1993
 PROJECT AREA CHARACTERISTICS
 Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Total area is 3.2 square miles (mi2); Control = 1.8 mi2; Treatment =
1.4 mi2

The average annual precipitation is 43 inches. The watershed geology consists of
deep well-drained silt-loam soils underlain by carbonate rock. About five percent
of each subwatershed is underlain by noncarbonate rock.
Land Use
Pollutant Sources
Modifications Since
Project Started
                               Type

                               Agricultural
                               Urban
                               Commercial
                               Total
                    Control Watershed
                    Acres       %
                      922
                      150
                       80
                      1152
 80
 13
  7
100
Treatment Watershed
  Acres     %
    762     85
    116     13
     18      2
    896    100
Source: Pequea and Mill Creek Watersheds Project Proposal, 1993.


The primary source of pollutants is believed to be pastured dairy cows and heifers
with uncontrolled access to stream and streambanks. Approximately 260 and 220
animals are pastured in the treatment and control watersheds, respectively. It is
estimated that grazing animals deposit an average of 40 pounds of nitrogen and 8
pounds of phosphorus annually per animal.

Other (commercial and urban) sources of pollutants are considered insignificant.

A new residential community is being developed in the treatment subwatershed.
INFORMATION, EDUCATION, AND PUBLICITY
Progress Towards
Meeting Goals
The U.S. Department of Agriculture (USD A) Natural Resources Conservation
Service (NRCS) has had an important role in the information and education
(I&E) programs in the Pequea and Mill Creek watershed. NRCS provides an
employee to gather nutrient management data in the watershed. The Lancaster
Conservation District and the Pennsylvania State University Cooperative Exten-
sion Service maintain active I&E programs in the area. Also, as part of the
USDA-funded Pequea-Mill Creeks Hydrologic Unit Area (HUA), the landowners
in the watersheds will be targeted for additional educational programs.

The Pennsylvania State University Cooperative Extension Service has produced
an educational video which includes information about the project and participat-
ing farmers.
                                              164

-------
                                                             Pequea and Mill Creek Watershed, Pennsylvania
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Description
Modifications Since
Project Started

Progress Towards
Meeting Goals
The control strategy involves installing streambank fencing on nearly 100 percent
of the pasture land adjacent to the stream draining the treatment subwatershed.
All of the farmers in this watershed have agreed to install fencing. A stabilizing
vegetative buffer is expected to develop naturally soon after the fencing is in-
stalled.
None.
The project is still in pre-BMP phase.
WATER QUALITY MONITORING
Design
Modifications Since
Project Started

Parameters
Measured
The water quality monitoring effort is based on a paired watershed experimental
design (Figure 30).

A new biological site, water quality site, and continuous monitoring station were
added. A continuous water quality probe was installed.

Biological

Habitat survey
Benthic invertebrate monitoring
Algal mass
Fecal streptococcus (FS) (only during base flow)
                             Chemical and Other

                             Suspended solids (SS)
                             Total and dissolved ammonia (NHs) plus organic nitrogen
                             Dissolved ammonia (NHs)
                             Dissolved nitrate + nitrite (NOs + NC-2)
                             Dissolved nitrite (NO2)
                             Total and dissolved phosphorus (TP and DP)
                             Dissolved orthophosphate (OP)
 Sampling Scheme
 Covariates

 Continuous streamflow
 Continuous precipitation
 Ground water level

 Continuous Streamflow Sites (4):
 Type: grab and storm event composite
 Frequency and season: grab every 10 days from April through November. Monthly
 grab December through March. Fifteen to 20 composite storm flow samples per
 year will also be collected.
                                              165

-------
                                                                  Pequea and Mill Creek Watershed, Pennsylvania
                               Partial Streamflow Site f 1):
                               Type: grab
                               Frequency and season: every 10 days from April through November. Monthly grab
                               December through March.

                               Ground Water:
                               Type: grab
                               Frequency and season: monthly and analyzed for nitrate. On a quarterly basis,
                               analysis includes dissolved NO2, NOs + NO2, NHs, and phosphorus.

                               Habitat, benthic invertebrate, and algal mass surveys are conducted twice per year,
                               preferably during May and September, at the outlet of each subwatershed, at two
                               points upstream in the treatment subwatershed, and at one point upstream in the
                               control subwatershed.

                               Continuous streamflow at watershed outlets and one tributary site and partial
                               streamflow at one upstream site.
                               Continuous precipitation amount is recorded at one site.
                               Additionally, ground water level is continuously monitored in four to eight wells.
                               Continuous pH, DO, specific conductivity, and temperature are monitored at the
                               mouth of the treated subwatershed during the 10-day fixed sampling period.
  Monitoring Scheme for the Pequea and Mill Creek Section 319 National Monitoring Program Project
Sites or
Design Activities
Paired Treatment
watershed watershed

Control
watershed







Primary
Parameters
Habitat survey
Benthic invertebrate survey
Algal mass
SS
Total organic nitrogen
NH3
NO3 + NO2
NO2
TP
DP
OP
FS
Frequency of
Frequency of Habitat/Biological
Covariates WQ Sampling Assessment Duration
Sampling
Discharge every 10 days
Precipitation (Apr.-Nov.)
Ground water Monthly sampling
level from Dec. to March


Storm event
samples (15-20)



Twice per 3 yrs pre-BMP
year (May & 5 yrs post-BMP
August)










Modifications Since
Project Started
Water Quality Data
Management and
Analysis
A new biological site was added upstream in the control subwatershed. A continu-
ous water quality probe was installed at the mouth of the treated subwatershed. A
new continuous monitoring station and water quality site was added to the treat-
ment subwatershed to document effects of a new residential development upstream
of pasture land.

Data are stored and maintained locally by U.S. Geological Survey (USGS) and
entered into the USGS WATSTORE database and STORET. Data will also be
entered into the U.S. Environmental Protection Agency's (USEPA) NonPoint
Source Management System (NPSMS) software and submitted to USEPA Region
m.
                                                  166

-------

NPSMS Data STATION TYPE: control station PRIMARY CODE: 01576521 YEAR: 1995
Summary CHEMICAL PARAMETERS

Parameter Name
FECAL, STREP KF AGAR
FLOW, STREAM, INSTANTANEOUS, CFS
NITROGEN, AMMONIA+ORGANIC DISSOLVED
NITROGEN, KIEDAHL, TOTAL
NITROGEN, NITRITE DISSOLVED
NITROGEN, NO2 + NO3 DISSOLVED
NO. COWS IN PASTURE PER 24 HRS PER ACRE
OXYGEN, DISSOLVED
PASTURE STREAM MILES FENCED
PHOSPHORUS, DISSOLVED
PHOSPHORUS, DISSOLVED ORTHOPHOSPHATE
PHOSPHORUS, TOTAL
PRECIPITATION, TOTAL (INCHES PER DAY)
SUSPENDED SEDIMENT
Farm
Type
S
S
S
S
S
S
u
S
u
S
S
S
S
S
Reporting
Units
COLS/1 OOML
CFS
MG/L AS N
MGL/N

MG/L AS N
COWDAY/AC
MG/L
MI
MG/L ASP
MG/L ASP
MG/L ASP

MG/L
TEMPERATURE, WATER (DEGREES CENTIGRADE) S
TOTAL ALKALINITY AS CALCIUM CARBONATE
TOTAL NITROGEN APPLICATION/ACRE TO
WATERSHED
TOTAL P APPLICATION/ACRE FOR WATERSHED
TURBIDITY, HACK TURBIDIMETER
(FORMAZIN TURB UNIT)
S
u

u
S

MG/L CAC03
N/ACRE

P/ACRE


QUARTILE VALUES
-75-
5,720
2.2
0.30
0.05
0.40
0.04

10.8
0
0.04
0.03
0.08
0.64
107
15.9






-50-
3,580
1.8
<0.20
0.04
0.30
0.03

10.1
0
0.03
0.03
0.04
0.31
84
15.2






-25-
2,190
1.4
<0.20
0.02
<0.20
0.02

9.4
0
0.02
0.02
0.03
0.11
20
12.5






STATION TYPE: Study Station PRIMARY CODE: 01576529
CHEMICAL PARAMETERS

Parameter Name
FECAL, STREP KF AGAR
FLOW, STREAM, INSTANTANEOUS, CFS
NITROGEN, AMMONIA+ORGANIC DISSOLVED
NITROGEN, AMMONIA, DISSOLVED
NITROGEN, KJEDAHL, TOTAL
NITROGEN, NITRITE DISSOLVED
NITROGEN, NO2 + NO3 DISSOLVED
NO. COWS IN PASTURE PER 24 HRS PER ACRE
OXYGEN, DISSOLVED
PASTURE STREAM MILES FENCED
PHOSPHORUS, DISSOLVED
PHOSPHORUS, DISSOLVED ORTHOPHOSPHATE
PHOSPHORUS, TOTAL
PRECIPITATION, TOTAL (INCHES PER DAY)
SUSPENDED SEDIMENT

Farm
Type
S
S
S
S
S
S
S
u
S
u
S
S
S
S
S

Reporting
Units
COLS/100ML
CFS
MG/L AS N
MG/L AS N
MG/L AS N
MG/L AS N
MG/L AS N
COWDAY/AC
MG/L
MI
MG/L ASP
MG/L ASP
MG/L AS P

MG/L
TEMPERATURE, WATER (DEGREES CENTIGRADE) S
TOTAL ALKALINITY AS CALCIUM CARBONATE
TOTAL NITROGEN APPLICATION/ACRE TO
WATERSHED
TOTAL P APPLICATION/ACRE FOR WATERSHED
TURBIDITY, HACK TURBIDIMETER
(FORMAZIN TURB UNIT)
S
u

u
S

MG/L CAC03
N/ACRE

P/ACRE





QUARTILE VALUES
-75-
98,320
1.5
0.42
0.06
0.70
0.07
12.2

12.4
0
0.06
0.05
0.10
0.64
54
20.5






-50-
10,880
0.9
0.30
0.035
0.55
0.06
11.0

11.4
0
0.025
0.025
0.06
0.31
26
18.7






-25-
1,710
0.6
0.20
0.03
0.38
0.05
9.4

9.8
0
0.02
0.02
0.04
0.11
6
13.0






167

-------
                                                            Pequea and Mill Creek Watershed, Pennsylvania
NPSMS Data Summary (Continued)
  STATION TYPE: Control Station
  BIOLOGICAL PARAMETERS (Non-Chemical)
        PRIMARY CODE: 01576521
  Parameter Name
  EPT INDEX
  EPT/CHIRONOMIDE ABUNDANCE
  H1LSENHOFF BIOTIC INDEX (HBI)
  PERCENT DOMINANT TAXA
  SCRAPERS/FILTER COLLECTORS
  SPECIES RICHNESS
                              Farm   Reporting  Expl.
                               -INDICES-
                                                                            Max. Reason.  Ref7
  Type   Units
         Var.   Fully    Threatened Partially   Pot.   Attn.  BPJ
u
u
u
u
u
u
SCORE
RATIO
SCORE
PERCENT
RATIO
COUNT
N
N
N
N
N
N
6
2.0
0.00-6.5
20
0.8
20
4
0.6
6.51-8.5
35
0.4
11
1
0.2
8.51-10
50
0.2
10
11.00
13.00
0.00
10.00
3.00
30.00
6.00
2.00
5.00
20.00
0.80
20.00
B
B
B
B
B
B
STATION TYPE: Study Station PRIMARY
BIOLOGICAL PARAMETERS rNon-Chemican

Parameter Name
EPT INDEX
EPT/CHIRONOMIDE ABUNDANCE
H1LSENHOFF BIOTIC INDEX (HBI)
PERCENT DOMINANT TAXA
SCRAPERS/FILTER COLLECTORS
Parm
Type
U
U
U
u
u
Reporting
Units
SCORE
RATIO
SCORE
PERCENT
RATIO
CODE:
Expl.
Var.
N
N
N
N
N
01576529


	 INDICES 	
Fully
6
2.0
0.00-6.5
20
0.8
Threatened
4
0.6
6.51-8.5
35
0.4
Partially
1
0.2
8.51-10
50
0.2


Max. Reason.
Pot.
11.00
13.00
0.00
10.00
3.00
Attn.
6.00
2.00
5.00
20.00
0.80

Ref/
BPJ
B
B
B
B
B
  SPECIES RICHNESS
  U
COUNT   N
20
11
10
30.00   20.00
Modifications Since
Project Started

Progress Toward
Meeting Goals
None.
1994 water quality data have been entered into WATSTORE and NPSMS soft-
ware.
 TOTAL PROJECT BUDGET
                        Project Element               1993
                        Personnel                 $ 57,508
                        Equipment and Supplies       20,300
                        Contracted Services           16,200
                        USGS (lab and gauging)       25,100
                        USGS Overhead            115,192
                        Other                      2,000
                        TOTAL*                 $236,300
                                   Funding Required
                                    1994
                                 $ 91,970
                                   5,600
                                  14,200
                                  38,800
                                  139,834
                                   2,000
                                  292,404
                        *50% of total funds are USGS matching funds
                        Source: Pequea and Mill Creek Watersheds Project Proposal, 1993.
1995
$ 67,656
5,020
6,200
40,770
109,214
3,000
231,860
1996
$ 90,097
4,000
7,380
30,500
121,393
4,000
257,370
Modifications Since
Project Started
None.
                                              168

-------
                                                         Pequea and Mill Creek Watershed, Pennsylvania
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
Modifications Since
Project Started
The Chesapeake Bay Program, which has set a goal of a 40% reduction in annual
loads of total ammonia plus organic nitrogen and total phosphorus to the Bay,
should have a significant impact on the project. The Bay Program is expected to
provide up to 100% cost-share money to help landowners install streambank
fencing.

None.
OTHER PERTINENT INFORMATION
                           None.
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Barbara Lathrop
Water Quality Biologies
Pennsylvania Department of
Environmental Resources
Bureau of Land and Water Conservation
P.O. Box 8555
Harrisburg, PA  17105-8555
(717) 787-5259

Frank Lucas
Project Leader
USDA-NRCS
P.O. Box 207
311 B Airport Drive
Smoketown, PA 17576
(717) 396-9427; Fax (717) 396-9427

Robert Heidecker
USDA-NRCS
1 Credit Union Place, Suite 340
Harrisburg, PA 17110
(717) 782-3446; Fax (717) 782-4469

Daniel Galeone
U.S. Geological Survey
840 Market Street
Lemoyne.PA 17043-1586
(717) 730-6952; Fax (717) 730-6997

Edward Koerkle
U.S. Geological Survey
840 Market Street
Lemoyne, PA 17043-1586
(717) 730-6956; Fax (717) 730-6997
                                           169

-------
                 Pequeaand Mill Creek Watershed, Pennsylvania
170

-------
                                       Vermont

            Lake Champlain Basin Watersheds
                                   Section 319
          National Monitoring Program Project
Figure 31: Lake Champlain Basin (Vermont) Watersheds Project Location
                   171

-------
                                                              Lake Champlain Basin Watersheds, Vermont
                                                                        3 (Control Watershed)
   	Wateished Bouidaiy

0

0

Scale
i
KHometers
1
I

2

2
1
                Miles
Figure 32: Water Quality Monitoring Stations for Lake Champlain Basin (Vermont) Watersheds
                                             172

-------
                                                                     Lake Champlain Basin Watersheds, Vermont
PROJECT OVERVIEW
                               The Lake Champlain Basin Watersheds Section 319 National Monitoring Pro-
                               gram project (also known as the Lake Champlain Agricultural Watersheds Best
                               Management Practice Implementation and Effectiveness Monitoring Project) is
                               located in northcentral Vermont in an area of transition between the lowlands of
                               the Champlain Valley and the foothills of the Green Mountains (Figure 31).
                               Agricultural activity, primarily dairy farming, is the major land use in this area of
                               Vermont.

                               The streams in these project watersheds drain into the Missisquoi River, a major
                               tributary of Lake Champlain. The designated uses of many of the streams in this
                               region are impaired by agricultural nonpoint source (NPS) pollution. The pollut-
                               ants responsible for the water quality impairment are nutrients, particularly
                               phosphorus, E. coli, fecal streptococcus, fecal coliform bacteria, and organic
                               matter. The source of most of the agricultural NPS pollution is the manure gener-
                               ated from area dairy farms, livestock activity within streams and riparian areas,
                               and crop production. The Missisquoi River has the second largest discharge of
                               water and contributes the greatest NPS load  of phosphorus to Lake Champlain.

                               The Lake Champlain Basin Watersheds 319 National Monitoring Program project
                               is designed to evaluate two treatments to control the pollutants generated by
                               agricultural activities. Treatment #1  is a system of best management practices
                               (BMPs) to exclude  livestock from selected critical areas of streams and to protect
                               stream crossings and streambanks. Individual BMPs for treatment #1 include
                               watering systems, fencing, the minimization of livestock crossing areas in
                               streams, and the strengthening of the necessary crossing areas. Treatment #2
                               implements intensive grazing management through planned rotation of multiple
                               pastures.

                               The water quality monitoring program is based on a three-way paired design: one
                               control watershed and two treatment watersheds (treatment #1 and #2) (Figure
                               32). The watersheds are being monitored during a two-year  calibration period
                               prior to BMP implementation. Implementation monitoring will occur for one year
                               and post-treatment monitoring will extend for three years.

                               Biological, chemical, and covariates will be monitored during all three monitoring
                               phases. Fish, macroinvertebrates, fecal streptococcus, fecal coliform, and E. coli
                               bacteria are the monitored biological parameters. The  chemical parameters
                               monitored are total phosphorus, total Kjeldahl nitrogen, total suspended solids,
                                dissolved oxygen, conductivity, and temperature. Two  covariates, precipitation and
                                continuous discharge, are also being monitored.

                               Nutrients and sediment are monitored weekly in a flow-proportional composite
                                sample. Bacteria grab samples are collected twice weekly, with concurrent in-situ
                                measurements of temperature, dissolved oxygen, and conductivity.
                                Macroinvertebrate communities are being sampled annually and fish are evaluated
                                twice each year. Invertebrate and fish monitoring are also being conducted at an
                                unimpaired reference site.
                                                   173

-------
                                                                     Lake Champlain Basin Watersheds, Vermont
 PROJECT DESCRIPTION
Water Resource
Type and Size
Water Uses and
Impairments
Pre-Project
Water Quality
Current Water
Quality Objectives
 The study streams are small second- or third-order permanent streams that drain
 to the Missisquoi River, a major tributary of Lake Champlain. The streams are
 generally 10-15 feet wide at the monitoring stations. Historical stream flow data
 do not exist for these streams; discharge has ranged from 1-288 cubic feet per
 second (cfs) since May, 1993.

 Because of their size, the study streams themselves are subject to very limited use
 for agricultural purposes (livestock watering) and recreation (swimming and
 fishing). No historical data exist to document support or nonsupport of these or
 other uses. Initial project data indicate that Vermont water quality (bacteriologi-
 cal) criteria for body contact recreation are consistently violated in these streams.

 Early biological data for fish and macroinvertebrates indicate moderate to severe
 impact by nutrients and organic matter. These particular small watersheds were
 selected to represent agricultural watersheds in the Lake Champlain Basin, where
 streams often violate state water quality criteria (Clausen and Meals, 1989; Meals,
 1990; Vermont RCWP Coordinating Committee, 1991) and contribute nutrient
 concentrations and areal loads that generally exceed average values reported from
 across the United States (Omernik, 1977) and in the Great Lakes Region
 (PLUARG, 1978).

 The receiving waters for these streams — the Missisquoi River and Lake
 Champlain — have very high recreational use that is being impaired by agricul-
 tural runoff (Vermont Agency of Natural Resources, 1994). The Missisquoi River
 is the second largest tributary to Lake  Champlain in terms of discharge (mean
 flow =1450 cfs) and contributes the highest annual NFS phosphorus load to Lake
 Champlain among the major tributary watersheds (75.1 mt/yr) (VT and NY
 Departments of Environmental Conservation, 1994). Lake Champlain currently
 fails to meet state water quality standards for phosphorus, primarily due to exces-
 sive nonpoint source loads (Vermont Agency of Natural Resources, 1994). About
 66% of the NFS phosphorus load to Lake Champlain is attributed to agricultural
 land (Budd and Meals, 1994).

 No historical physical/chemical data exist for the study streams. Early pretreat-
 ment monitoring data show the following ranges:
                                  E. Coli

                                 10 - 66,000

                                 TP(mg/l)
                                 0.05 - 1.05
                Fecal Coliform
                  (#/100 ml)
                  2 - 49,000

                  TKN (mg/1)
                   0.32 - 2.08
Fecal Strep.

10 - 200,000

TSS (mg/1)
  2-150
(Note: these values represent the range observed in May, 1994 - June, 1995.)

The overall goal of the project is a quantitative assessment of the effectiveness of
two livestock/grazing management practices in reducing concentrations and loads
of nutrients, bacteria, and sediment from small agricultural watersheds. Major
water quality objectives are to  1) document changes in sediment, nutrient, and
bacteria concentrations and loads due to treatment at the watershed outlets and 2)
evaluate response of stream biota to treatment.
                                                 174

-------
                                                               Lake Champlain Basin Watersheds, Vermont
Modifications Since
Project Initiation

Project Time Frame

Project Approval
None.


September 1993 - September, 1999 (Approximate)

September 1993
PROJECT AREA  CHARACTERISTICS
Project Area

Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
1705 ac (WS 1) + 3513 ac (WS 2) + 2358 ac (WS 3) = 7576 ac

The project area is in northcentral Vermont (Franklin County) in an area of
transition between the lowlands of the Champlain Valley and the foothills of the
Green Mountains. Average annual precipitation is about 41 inches; average
annual temperature is about 42°F. Frost-free growing season averages 118 days.

Most of the watershed soils are till soils, loamy soils of widely variable drainage
characteristics. There are significant areas of somewhat poorly drained silt/clay
soils in the lower portions of the watersheds.

The three watersheds are generally similar in land use:
                                                  WS1
                                        WS2
Land Use
                                            Acres
                                  Acres
      WS3
Acres
Corn/hay
Pasture/
hay-pasture
Forest
Other
369
60
1135
141
22%
4%
67%
8%
860
426
2118
110
25%
12%
60%
3%
569
167
1408
213
24%
7%
60%
9%
 Pollutant Sources
 Modifications Since
 Project Started
 Source: 1993 CFSA aerial photography, unverified


 Nonpoint sources of pollutants are streambanks, degraded riparian zones, and
 dairy-related agricultural activities, such as field-spread and pasture-deposited
 manure and livestock access. Some agricultural point sources such as milkhouse
 waste or corn silage leachate are thought to exist.
 None.
 INFORMATION, EDUCATION, AND PUBLICITY
                             Pre-project activity included letters to all watershed agricultural landowners
                             followed by small "kitchen table" meetings with farmers in each watershed. The
                             purpose of these meetings was to assess landowner interest and acceptance of the
                             project.
                                              175

-------
                                                                    Lake Champlain Basin Watersheds, Vermont
Progress Towards
Meeting Goals
Two articles concerning the project have been published in the weekly county
newspaper. A semiannual project newsletter was initiated in the summer of 1995.

In July, 1994, a monitoring station "open-house" was held to present the project,
monitoring hardware, and some early monitoring results.

The first annual winter lunch meeting was held in February, 1995, where water-
shed farmers discussed the project and heard a talk by a local farmer engaged in
rotational grazing. A second such meeting was held in April, 1996.

The project includes a Project Advisory Committee with representatives from
United States Department of Agriculture-Natural Resources Conservation Service
(USDA-NRCS), Extension, Vermont Dept. of Agriculture, Vermont  Dept. of
Environmental Conservation, Vermont Natural Resources Conservation Council,
U.S. Fish and Wildlife Service, the Vermont Pasturelands Outreach Program, and
a watershed dairy farmer. The committee meets quarterly to review progress and
assist in program direction.

Information and education efforts  during the two-year pretreatment calibration
phase focus on laying the groundwork for treatment by presenting demonstrations
and information concerning rotational grazing and livestock access control.
Additional contact with farmers will occur through routine collection of agricul-
tural management data.
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Design
Modifications Since
Project Started
The project is designed to test two treatments: 1) livestock exclusion/streambank
protection and 2) intensive grazing management. In the first treatment watershed,
work will focus on selective exclusion of livestock from the streams, improvement
or elimination of heavily used stream crossings, and revegetation of streambanks.
This treatment requires fencing, watering systems, minimizing livestock crossing
areas, and strengthening necessary crossing areas.

In the second treatment watershed, intensive rotational grazing management is
being implemented as a means to minimize the time spent by livestock in or near
the streamcourse without complete exclusion.

During the two-year pretreatment monitoring period, treatment needs are being
assessed, specific plans and specifications are being developed, and agreements
with landowners are being pursued. It is anticipated that the project will provide
100% cost support for cooperating landowners. Agricultural management activity
— both routine and treatment implementation — is monitored by farmer record-
keeping and semiannual interviews.

It is also anticipated that some work will be done as necessary on agricultural
point sources if and when such pollutant sources are identified.

None.
                                                 176

-------
                                                                     Lake Champlain Basin Watersheds, Vermont
Progress Towards
Meeting Goals
The water quality monitoring component of the project is fully operational and is
currently meeting project goals. A severe drought and elevated temperatures
during June and July, 1995, have interfered slightly with chemical and physical
monitoring, and may have some lasting influence on biological communities in
the monitored streams.

Land use/agricultural activity monitoring is lagging somewhat behind schedule.  A
baseline farm inventory has been completed and .the watersheds were flown for
aerial videography in June, 1995, to update land use/land cover and to assess and
classify stream corridors as part of an evaluation of treatment needs. The process
of identifying specific treatment needs, designs, and negotiating agreements with
landowners began in the fall of 1995.

The principal impediment to project progress is funding, both mechanism and
quantity. While in principle, Section 319 National Monitoring Program funding is
intended to be set up for the entire project period, this has not been the case in this
project. The requirement to renew funding each year causes significant problems,
including accounting confusion over fiscal vs. project vs. monitoring "years",
inefficient expenditure of staff time, and, most importantly, difficulty in account-
ing for and documenting required match. This is a particular problem in the
implementation budget, since actual implementation (and associated match) will
not take place until project year 3, while funds have been allocated in project year
1 and 2 budgets. Budgeting over the entire project lifetime would substantially
alleviate these problems.

The other financial impediment to the project involves significant increases in
charges for sample analysis by the state Department of Environmental Conserva-
tion (DEC) laboratory. These costs have increased dramatically (on the order of
$11,000 - $16,500 per year) since the first funding year and, with no correspond-
ing increase in overall funding, other budget categories have had to be cut. In the
current FY96 budget, this has required elimination of all nonsignificant principal
investigator support, limiting available time commitment to the project. The
increase in analytical costs also reduces the previous match contributions from
DEC. Annual funding from U.S. Environmental Protection Agency (USEPA),
however, has been essentially level and nonnegotiable for the last two years. Some
flexibility in funding, such as increasing USEPA funding to cover such cost
increases, would be helpful.
WATER QUALITY MONITORING
Design
Modifications Since
Project Started
The study is based on a three-way paired watershed design, with a control water-
shed and one watershed for each of the two treatments to be evaluated (Figure 32).
The design calls for two years of pre-treatment calibration, one year of implemen-
tation, and three years of post-treatment monitoring.

None.
Parameters
Measured
 Biological

 E. coli bacteria
 Fecal coliform (FC)
 Fecal streptococcus (FS)
 Macroinvertebrates
 Fish
                                                  177

-------
                                                                     Lake Champlain Basin Watersheds, Vermont
Sampling Scheme
Chemical and Other

Total phosphorus (TP)
Total Kjeldahl nitrogen (TKN)
Total suspended solids (TSS)
Dissolved oxygen (DO)
Conductivity
Temperature

Covariates

Precipitation
Discharge (continuous)

Automated sampling stations are located at three watershed outlets for continuous
recording of streamflow, automatic flow-proportional sampling, and weekly
composite samples for sediment and nutrients. The watersheds are as follows:
WS1 is the rotational grazing (treatment #2), WS2 is the streambed protection
(treatment #1), and WS3 is the control (Figure 32). Twice-weekly grab samples
for bacteria are collected. Concurrent in-stream measurement of temperature,
dissolved oxygen, and conductivity also occur at the same time that the grab
samples are collected. Three precipitation gauges have been installed. All moni-
toring systems operate year-round.

The macroinvertebrate community at each site and a fourth "background refer-
ence" site are sampled annually using a kick net/timed effort technique. Methods
and analysis follow USEPA's Rapid Bioassessment Protocols (Protocol III). Fish
are sampled twice a year by electroshocking and evaluated according to Rapid
Bioassessment Protocols Protocol V.

Physical habitat assessments are performed during each sampling run.
  Monitoring Scheme for the Lake Champlain Basin Watersheds Section 319 National Monitoring
  Program Project
Design
Three-way
paired
watershed
Site or
Activities
Samsonville
BrookT
Godin Brook1"
Berry Brookc
Primary
Parameters
E. coli
FC
FS
Macroinvertebrates
Fish survey
TP
TKN
TSS
DO
Conductivity
Temperature
Frequency of
Covariates WQ Sampling
Precipitation \Veekly except
Discharge bacteria
(continuous) temperature,
dissolved oxygen,
and conductivity
which will be
twice weekly
Frequency of
Biological
Assessment
Fish sampled
twice per year
Macroinvertebrates
sampled once per
year
Duration
2 yrs pre-BMP
lyrBMP
3 yrs post-BMP
^Treatment watershed
cConlrol watershed
                                                   178

-------
                                                                 Lake Champlain Basin Watersheds, Vermont
Modifications Since
Project Started

Water Quality Data
Management and
Analysis
        None.
NPSMS Data
Summary
        Primary data management is done using an in-house spreadsheet system. The
        USEPA Nonpoint Source Management System (NPSMS) software will be used to
        track and report data to USEPA when it is upgraded to handle three watersheds
        and a version provided that runs on the available PC. Requisite data entry into
        STORET and BIOS has been completed through file transfer. Biological data are
        being formatted for transfer to BIOS.

        Water quality data are being compiled and reported for quarterly project advisory
        committee meetings, including basic plots and univariate statistics. For annual
        reports, data are analyzed on a water-year basis.

        Data analysis is being performed using both parametric and nonparametric
        statistical procedures in standard statistical software.

Monitoring Station Parameters Report

DATE: 08/04/95                   PERIOD: 5/94-6/95
                     STATION TYPE:  Treatment Watershed #1 (Samsonville Brook)
                     CHEMICAL PARAMETERS
                                                    Reporting
                     Parameter Name                 Units
                     CONDUCTANCE                 uS/CM
                     E. COLI                        CFU/100ML
                     FECAL COLIFORM               CFU/100ML
                     FECAL STREPTOCOCCUS         CFU/l.OOML
                     FLOW, STREAM, WEEKLY MEAN   CFS
                     OXYGEN, DISSOLVED            MG/L
                     PRECIPITATION, TOTAL           IN/WEEK
                     NITROGEN, TOTAL KJELDAHL     MG/L
                     PHOSPHORUS, TOTAL            MG/L
                     TEMPERATURE, WATER           oC
                     TOTAL SUSPENDED SOLIDS       MG/L

                     STATION TYPE: Treatment Watershed #2 (Godin Brook)

                     CHEMICAL PARAMETERS
                      Parameter Name
                      CONDUCTANCE

                      E. COLI
                      FECAL COLIFORM
                      FECAL STREPTOCOCCUS
                      FLOW, STREAM, WEEKLY MEAN
                      OXYGEN, DISSOLVED
                      PRECIPITATION, TOTAL
                      NITROGEN, TOTAL KJELDAHL
                      PHOSPHORUS, TOTAL
                      TEMPERATURE, WATER
                      TOTAL SUSPENDED SOLIDS
                                                     QUARTILE VALUES
                                                  -75-
                                                  120
                                                  200
                                                  180
                                                 1040
                                                  3.7
                                                  13.0
                                                  0.58
                                                  1.24
                                                 0.160
                                                  0.8
                                                  59.6
 -50-
  95
 120
  82
 300
  2.3
 11.8
 0.29
 1.00
0.076
  9.1
 26.8
 -25-
  80
  24
  26
  60
  1.4
  9.9
 0.07
 0.69
0.052
 17.1
 13.8
Reporting
Units
uS/CM
CFU/100ML
CFU/100ML
CFU/100ML
CFS
MG/L
IN/WEEK
MG/L
MG/L
oC
MG/L
QUARTILE VALUES
-75-
139
4500
4450
1200
7.7
13.1
0.76
1.15
0.185
18.0
36.0
-50-
117
610
600
520
4.8
11.5
0.40
0.89
0.088
10.4
14.4
-25-
90
39
41
50
3.1
9.7
0.09
0.66
0.037
2.3
5.2
                                                179

-------
                                                              Lake Champlain Basin Watersheds, Vermont
                NPSMS Data Summary (Continued)
                STATION TYPE:  Treatment Watershed #3 (Berry Brook)

                CHEMICAL PARAMETERS
                                             Reporting
                Parameter Name                Units             -75-
                CONDUCTANCE                uS/CM             130
                E. COLI                       CFU/100ML        3850
                FECAL COLIFORM              CFU/100ML        2800
                FECAL STREPTOCOCCUS        CFU/100ML        1900
                FLOW, STREAM, WEEKLY MEAN   CFS               9.2
                OXYGEN, DISSOLVED           MG/L             12.6
                PRECIPITATION, TOTAL          IN/WEEK          0.75
                NITROGEN, TOTAL KJELDAHL    MG/L             1.06
                PHOSPHORUS, TOTAL           MG/L            0.179
                TEMPERATURE, WATER          oC               17.4
                TOTAL SUSPENDED SOLIDS       MG/L             31.0
                                       QUARTILE VALUES
                                             -50-
                                              111
                                             490
                                             630
                                             405
                                              5.9
                                             10.6
                                             0.48
                                             0.77
                                            0.058
                                             10.6
                                              8.6
                       -25-
                        94
                        33
                        31
                        60
                        3.7
                        9.2
                       0.12
                       0.68
                      0.040
                        2.7
                        5.0
Modifications Since        None.
Project Started

Progress Towards
Meeting Goals
PROJECT BUDGET
Modifications Since
Project Started
                            The estimated budget for the Lake Champlain Basin Watersheds National Moni-
                            toring Program project for years 1-3 is:
                            Project Element
                            LT
                            WQ Monit
                            TOTALS
                    Federal

                    106,100
                    273,400
                    379,500
     Funding Source ($)
 State      University   Sum
 3,400
85,500
88,900
22,400
75,600
98,000
Source: Don Meals (Personal Communication), 1994
(Dollar figures are rounded.)

Project budget continues to be renewed yearly.
131,900
434,500
566,400
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                            The project area is within the area of the Lake Champlain Basin Program (a
                            program modeled after the Chesapeake Bay Program), directed toward the man-
                            agement of Lake Champlain and its watershed. Considerable effort on agricultural
                            NPS control is associated with this program, including funding for pollution
                            control/prevention demonstration projects.
                                             180

-------
                                                                Lake Champlain Basin Watersheds, Vermont
Modifications Since
Project Started
Additionally, the state of Vermont's phosphorus management strategy calls for
targeted reductions of phosphorus loads from selected subbasins of Lake
Champlain.

Because this 319 National Monitoring Program project contributes to two ongoing
projects (the Lake Champlain Basin Program and the phosphorus reduction
program), it is anticipated that some support — technical assistance, funding, or
other — will be actively sought from these programs.

Two other activities may contribute to this project. The U.S. Fish and Wildlife
Service has an active riparian zone restoration program, Partners in Wildlife, in
the area. The University of Vermont Extension Pasturelands Outreach Program is
engaged in active promotion and technical assistance in implementing rotational
grazing in northern Vermont. Individuals from other programs serve on the
Project Advisory Committee.
OTHER PERTINENT INFORMATION
                             None.
PROJECT CONTACTS
Administration
 Land Treatment
Water Quality
Monitoring
Richmond (Rick) Hopkins
Vermont Dept. of Environmental Conservation
Water Quality Division
Building 10 North 103 South Main Street
Waterbury, VT  05671
(802) 241-3770; Fax (802) 241-3287
Internet: rickh@waterq.anr.state.vt.us

Don Meals
School of Natural Resources
University of Vermont
UVM-Aiken Center
Burlington, VT  05405
(802) 656-4057; Fax (802) 656-8683
Internet: dmeals@moose.uvm.edu

Don Meals
School of Natural Resources
University of Vermont
UVM-Aiken Center
Burlington, VT  05405
 (802) 656-4057; Fax (802) 656-8683
Internet: dmeals@moose.uvm.edu
                                               181

-------
                    Lake Champlain Basin Watersheds, Vermont
182

-------
                                 Washington

                          Totten and Eld Inlet
                                 Section 319
       National Monitoring Program Project
Figure 33: Totteri and Eld Inlet (Washington) Project Location
                183

-------
                                                                  • Totten and Eld Inlet, Washington
   LEGEND
  Watershed Boundary
  Sample Site Location

   Scale
\
     Figure 34: Water Quality Monitoring Stations for Totten and Eld Inlet (Washington)
                                         184

-------
                                                                              i Totten and Eld Inlet, Washington
PROJECT OVERVIEW
                               Totten and Eld Inlets are located in southern Puget Sound (Figure 33). These
                               adjacent inlets are characterized by enriched marine waters that make them
                               exceptional shellfish production areas. The rural nature of the area makes it an
                               attractive place in which to live. Consequently, stream corridors and shoreline
                               areas have experienced considerable urban, suburban, and rural growth in the past
                               decade. Located in the area are many recreational, noncommercial farms that keep
                               varying numbers of large animals (primarily horses). Upland and lowland areas
                               are highly productive forest lands.

                               The most significant nonpoint source (NFS) pollution problem in these inlets is
                               bacterial contamination of shellfish production. Totten  Inlet is currently classified
                               as an approved shellfish harvest area but is considered  threatened due to bacterial
                               NFS pollution. The southern portion of Eld Inlet is currently classified as condi-
                               tional for shellfish harvest. This conditional classification means shellfish may
                               not be harvested for 3 days following rain events that are greater than 1.25 inches
                               in 24 hours. The major sources of fecal coliform (FC) bacteria are failing on-site
                               wastewater treatment systems and livestock-keeping practices along stream
                               corridors and marine shorelines.

                               The Totten and Eld Inlet Clean Water Projects have evolved from the combined
                               efforts and resources of local and state government. Watershed action plans were
                               completed in 1989 for both Totten and Eld Inlet. While a significant level of
                               public involvement and planning has occurred, material resources for implement-
                               ing ori-the-ground best management practices (BMPs)  have been scarce. In 1993,
                               substantial funding from property assessments and grants provided funds to
                               implement remedial actions in targeted areas within these watersheds. The goal of
                               the remedial efforts is to minimize the impacts of NPS  pollution by implementing
                               farm plans on priority farm sites and identifying and repairing failing on-site
                               wastewater treatment systems. These focused efforts are expected to last into 1999.

                               In 1993, a water quality monitoring program was initiated to evaluate the effec-
                               tiveness of remedial land treatment practices on water  quality. This monitoring
                               effort was formalized in 1995 into a U.S. Environmental Protection Agency
                               (USEPA) Section 319 National Monitoring Program project. The monitoring
                               effort targets six subbasins within the larger Totten and Eld Inlet watersheds. The
                               goals of water quality monitoring are to detect, over time 1) trends in water
                               quality and implementation of land treatment practices and 2) associated changes
                               in water quality to changes in land treatment practices. A paired watershed design
                               is being used for two basins while a single site approach will be used for four
                               basins. Water quality monitoring is conducted from November to April  on a
                               weekly basis for at least 20 consecutive weeks  each year. Fecal coliform bacteria,
                               suspended solids, turbidity, flow, and precipitation are  the main parameters of
                               interest. Best management practices are also being tracked.
 PROJECT DESCRIPTION
 Water Resource
 Type and Size
Totten/Little Skookum and Eld Inlets are estuaries separated by peninsulas in
southern Puget Sound. The total drainage basin for the two inlets is approximately
67,200 acres. Six subbasins have been selected for this monitoring project. They
are as follows:
                                                   185

-------
                                                                               • Totten and Eld Inlet, Washington
Water Uses and
Impairments
Pre-Project
Water Quality
Burns             82-acre single site
Kennedy       13,046-acre paired site
Pierre             65-acre single site
Schneider       4,588-acre paired site
McLane         7,425-acre single site
Perry           3,857-acre single site

Important beneficial uses of the Totten and Eld Inlet marine waters include
shellfish culturing, finfish migration and rearing, wildlife habitat, and primary
and secondary contact recreation.

Important beneficial uses of the freshwater streams that drain into the Totten and
Eld Inlets include finfish migration, spawning, and rearing; domestic and agricul-
tural water supply; primary and secondary contact recreation; and wildlife habitat.

Three of the six project streams (Burns, Pierre, and Schneider) failed to meet
water quality standards for fecal coliform bacteria for the 1992-93 and 1993-94
monitoring seasons. The water quality standard for fecal coliform (FC) bacteria
for these streams requires that the geometric mean value not exceed 50 cfu/100 ml
and that not more than 10% of samples exceed 100 cfu/100 ml.
Site

Burns
Kennedy
Pierre
Schneider
McLane
Perry
Class

AA
AA
AA
AA
A
A
GMV
92-93
94
5
52
24
37
14
93-94
206
6
55
17
27
10
% samples
Part 1 greater than Part
meet standard? 2 of standard
92-93
No
Yes
No
Yes
Yes
Yes
93-94
No
Yes
No
Yes
Yes
Yes
92-93
35
0
22
17
4
0
93-94
74
0
42
11
4
0
Part 2
meet standard?
92-93
No
Yes
No
No
Yes
Yes
93-94
No
Yes
No
No
Yes
Yes
            Class AA Standard:
            Class A Standard:
   Part 1—geometric mean value (GMV) shall not exceed 50 colonies/100ml.
   Part 2—not more than 10% of the samples used for calculating the GMV
   shall exceed 100 colonies/100ml.


   Part 1—geometric mean value shall not exceed 100 colonies/100ml.
   Part 2—not more than 10% of the samples used for calculating the GMV
   shall exceed 200 colonies/100ml,
Current Water
Quality Objectives
Pierre Creek
    reduce median FC concentration by 69% (reduce to 10 cfu/lOOml)

Burns Creek
    reduce median FC concentration by 63% (reduce to 20 cfu/100 ml)

Schneider Creek
    reduce median FC concentration by 50% (reduce to 10 cfu/100 ml)

McLane Creek
•   reduce median FC concentration by 44% (reduce to 22 cfu/100 ml)
                                                   186

-------
                                                                         i Totten and Eld Inlet, Washington
Modifications Since
Project Initiation

Project Time Frame

Project Approval
None.


1993 to 2002

1995
PROJECT AREA  CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorologic Factors
Land Use
The Totten and Eld Inlets Section 319 National Monitoring Program project area
consists of six subbasins within the Totten and Eld Inlets. The Totten watershed is
approximately 44,300 acres and the Eld Inlet watershed is approximately 22,900
acres.

The topography of the project area includes the rugged Black Hills area southwest
of the city of Olympia, upland prairies, fresh and estuarine wetlands, high and low
gradient stream reaches, and rolling hills. Pleistocene glacial activity was the
most recent major land-forming process.

The predominant till formations generally consist of compact silts and clays.
                           !
Wet, mild winters and warm, dry summers are characteristic of the Puget Sound
region. The climate and precipitation of the project area are similar. Rainfall
ranges from about 50 to 60 inches per year, depending on elevation and longitude.
The precipitation received in the areas mostly occurs between October and April.
                             Land Use
                             Forest
                             Residential
                             Agriculture
                             Public Use
                             Undeveloped
                             Other
                          Totten/Little Skookum Inlet     Eld Inlet
                                 82.0%                   63.0%
                                  4.3%                    6.3%
                                  5.0%                    5.1%
                                  0.3%                    5.1%
                                  7.5%                   19.8%
                                  0.9%                    0.7%
Pollutant Sources
Modifications Since
Project Started
The major sources of fecal coliform bacteria are failing on-site wastewater treat-
ment systems and livestock-keeping practices along stream corridors and marine
shorelines. Wet season (October-April) soil saturation hampers the ability of many
on-site systems to operate correctly. Saturated soils and stormwater runoff also
contribute to water quality problems associated with overgrazed pastures, manure-
contaminated runoff, and livestock access to streams. The major source of pollu-
tion in the monitoring subbasins is considered to be animal-keeping practices.

None.
INFORMATION, EDUCATION, AND PUBLICITY
                             There are a variety of educational and informational activities within the project
                             counties (Thurston and Mason counties) that address land and water stewardship.
                             Local and state initiatives over the past six years have resulted in stewardship
                             activities that cover the spectrum of personal commitment activities, including
                             awareness, learning, experience, and personal action programs. Many educators
                             involved with these activities share ideas, resources, and programs through a
                             stewardship-focused Regional Education Team.
                                               187

-------
                                                                           • Totten and Eld Inlet, Washington
Progress Towards
Meeting Goals
A Section 319 Clean Water Act grant funded a watershed resident survey in
August, 1994. The survey explored public awareness and opinions regarding
water quality and environmental issues. The survey targeted the Totten and Eld
Inlet watersheds in southern Puget Sound, as well as northern Puget Sound
watersheds in Whatcom, Skagit, and Snohomish counties. Approximately 1300
residents responded to the mail survey. The survey was designed to help state and
local governments evaluate levels of public awareness and effectiveness of current
educational programs, and determine where educational efforts, and efforts to
involve the public, should be directed (Elway Research, 1994).

The objective of the project's public involvement and education component is to
participate in and lend support to established public information and education
activities addressing environmental stewardship in the project areas and in the
larger South Puget Sound area.
      .                      I
Educational and informational activities are continuing.
NONPOINTSOURCE CONTROL STRATEGY
Description
 Modifications Since
 Project Started

 Progress Towards
 Meeting Goals
The NFS treatment in the project area is designed to minimize the impacts of NPS
pollution by repairing failing on-site wastewater treatment systems and imple-
menting farm plans on priority farm sites. Priority farm sites are those farms that
potentially threaten the quality of a receiving water due to a variety of physical
and managerial properties such as closeness to stream, numbers of animals, and
lack of pollution prevention practices. The NPS control strategy involves survey-
ing all potential pollution sources in critical areas, estimating the water quality
impact, and, finally, planning and implementing corrective actions.

Resource management plans (farm plans) are developed cooperatively by the
landowner and local conservation districts.  The farm planning process identifies
potential water quality impacts and recommends BMPs to mitigate those impacts.
Conservation district staff and the landowner discuss implementation costs and
schedules of BMPs and cost-share opportunities. The landowner then chooses
what he or she is willing to implement and agrees to implement the plan as
funding allows. Specific BMPs most likely to be employed for NPS control in
project watersheds include pasture and grazing management, stream fencing,
stream buffer zones, rainwater and runoff management, livestock density reduc-
tion, and animal waste management. Monies from the Farm Service Agency, State
Revolving Fund, U.S. Fish and Wildlife Service, and other sources may be avail-
able for cost-share or low interest loan contracts.

Voluntary participation (due to education/outreach activities and local ordinances)
is anticipated to be the major mechanism for implementation of farm plans. Farm
owners whose operations have impacts on water quality and who do not comply
with local ordinances become involved in a formal compliance procedure, which
is outlined by a memorandum of agreement between the Ecology Water Quality
Program and each conservation district. Legal recourse is seldom needed.

None.
 Since 1993, 16 farm plans were developed and over 130 BMPs were installed in 5
 of the 6 study basins. The most frequently used BMPs include fencing, livestock
 exclusion, livestock troughs, pasture and hayland management, and waste utiliza-
 tion. Other commonly employed practices are fish stream improvement, roof

                   188

-------
                                                                        i Totten and Eld Inlet, Washington
                           runoff management, pasture and hayland planting, deferred grazing, and
                           streambank protection. The number of individual practices installed per farm
                           ranged from 1 to 16. Thirty-four farms have farm plans, 20 have signed plans,
                           and 26 farms have implemented some BMPs. Within each basin, the average
                           number of BMPs per farm ranged from 6 to 11. Most farm planning and BMPs
                           will be completed in 1997 in the Totten basins, and continue into 1999 in the Eld
                           Basins.

                           Over 190 agricultural BMPs have been implemented on 26 sites in Schneider,
                           McLane, Perry, Burns, and Pierre basins since 1986. Most of the pollution con-
                           trols have been installed on noncommercial farms that keep livestock. About 70%
                           of the pollution controls were installed from 1993 to 1995.
TYPE AND NUMBER OF BMPS IMPLEMENTED IN STUDY BASINS.
BMP#  BMP Description
Units   Kennedy Schneider McLane Perry  Burns Pierre  Total
322     Channel Vegetation
352     Deferred Grazing
382     Fencing
393     Filter Strip
395     Fish Stream Improvement
412     Grassed Waterway
561     Heavy Use Area Protection
430     Irrigation Pipeline
575     Livestock Crossing
472     Livestock Exclusion
590     Nutrient Mgmt
510     Pasture & Hayland Mgmt
512     Pasture & Hayland Planting
516     Pipeline
556     Planned Grazing System
528     Prescribed Grazing
558     Roof Runoff Mgmt
570     Runoff Mgmt System
580     Streambank Protection
614     Trough
620     Underground Outlet
312     Waste Mgmt System
313     Waste Storage Structure
633     Waste Utilization
645     Wildlife Upland Habitat
644    Wildlife Wetland Habitat
654    Woodland Improved
666    Woodland Pruning
490    Woodland Site Preparation
        Total BMPs Installed
        Farms that Developed Farm Plans
        Farms that  Signed Farm Plans
        Farms that  Installed BMPs
        Average Number of BMPs per Farm
acres
acres
feet
acres
feet
acres
acres
feet
each
acres
acres
acres
acres
feet
acres
acres
system
system
feet
each
feet
system
structure
acres
acres
acres
acres
acres
acres

Plans
ns

erFarm
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
-
                      1
                      0
                      7
                      4
                      3
                      0
                      0
                      0
                      2
                      4
                      2
                      2
                      2
                      0
                      2
                      2
                      0
                      0
                      2
                      0
                      0
                      0
                      2
                      3
                      1
                      1
                      1
                      1
                      1

                      43
0
2
14
8
7
2
2
1
1
5
1
8
1
1
1
1
0
0
3
7
1
3
0
6
4
0
0
0
0
0
0
6
2
1
0
0
0
1
2
0
0
1
1
1
0
0
0
1
5
0
0
0
0
0
0
0
0
0
0
3
3
0
0
0
0
0
0
3
0
3
3
1
3
1
1
1
0
1
0
0
1
3
1
0
0
0
0
0
1
1
0
0
1
0
0
0
1
0
1
1
0
1
1
0
0
0
2
0
0
2
2'
0
0
0
0
0
1
6
31
14
11
3
2
1
4
15
3
14
8
3
8
5
1
1
6
15
1
3
5
14
6
1
1
1
1
83
22
29
15    192
6
4
4
10.8
10
9
13
6.4
7
4
4
5.5
3
2
3
9.7
2
1
2
7.5
34
20
26
7.4
                                              189

-------
                                                                           iTotten and Eld Inlet, Washington
WATER QUALITY MONITORING
Design                       A paired watershed approach is being used for the Kennedy/Schneider subbasins
                              to document the change in water quality as a result of BMP implementation.
                              Kennedy is a background (control) subbasin, while Schneider is the treatment
                              basin (Figure 34). A single site approach will be used for Burns, Pierre, Perry and
                              McLane subbasins (Figure 34).

                              None.
Modifications Since
Project Started

Parameters
Measured
                              Chemical and Other

                              Biological

                              Fecal coliform (FC)

                              Covariates

                              Conductivity
                              Daily precipitation
                              Flow
                              Temperature
                              Total suspended solids (TSS)
                              Turbidity

Sampling                    Water quality monitoring is conducted from early November through mid-April.
Scheme                     Grab samples are collected on a weekly schedule (Tuesdays) for at least 20 con-
                              secutive weeks each year of the project. Up to six additional samples are collected
                              each season during runoff events at each site. The rain-event sampling is based on
                              the criterion of previous 24-hour precipitation amounting to greater than 0.2
                              inches. The sample sites are located at the mouth of each stream. Historically,
                              sampling has occurred at this location.

                              The Puget Sound Protocols for freshwater and general quality assurance/quality
                              control (Tetra Tech, 1986) will be followed for water sample collection, identifica-
                              tion, preservation, storage, and transport. Replicate samples (two samples taken
                              from the same location at nearly the same time) for at least 10% of the total
                              number of laboratory samples will be taken and analyzed each week. All sample
                              sites are represented every sampling season.

    Monitoring Scheme for the Totten and Eld Inlet Section 319 National Monitoring Program Project
Design
Single
downstream





Paired
watershed





Sites or Primary
Activities Parameters
Bums FC
Pierre
Perry
McLane



Kennedy/ FC
Schneider





Covariates
Conductivity
Daily precipitation
Flow
Temperature
TSS
Turbidity








Frequency of Primary
Parameter Sampling
Weekly
(Nov. to mid-April)
during storms











Duration
Schneider
Burns
Pierre:
1 yr. pre-BMP
3 yrs BMP
2 yrs post-BMP
Perry:
3 yrs pre-BMP
3 yrs BMP
lyr post-BMP
McLane:
1 yr pre-BMP
5 yrs BMP
1 yr post-BMP

                                                 190

-------
                                                                             i Totten and Eld Inlet, Washington
Modifications Since
Project Started

Water Quality Data
Management and
Analysis
 NPSMS Data
 Summary

 Modifications Since
 Project Started

 Progress Towards
 Meeting Goals
None.
Water quality data will be stored and managed in spreadsheet formats and later
transferred to USEPA's STORET and NonPoint Source Management System
(NPSMS) databases. Other reporting formats for the Ecology Water Quality
Program and local use may involve spreadsheet tabulation and graphic presenta-
tions. Data evaluation and analysis strategies include the following:

•   Determining statistically significant temporal trends in water quality by
    comparison of 95% Confidence Interval about seasonal medians using
    notched boxplots (single site approach); linear regression of monthly or
    seasonal medians over time, and the significance of slope tested to indicate a
    decreasing trend of FC concentrations over time (single site approach);
    change in linear relationship of FC concentrations between paired basins
    (paired watershed approach); and, comparison of frequencies of water quality
    standards violations between years.

    Determining temporal trends in BMP implementation by bar graph of BMPs
    (individual or grouped) implemented over time and plot of cumulative
    histogram of BMPs implemented over time (individual measures or groups of
    measures).

    Evaluating combined water quality and BMP trends by linear regression of
    FC as a function of BMPs (individually or grouped) such as livestock
    management, acres treated, farm plans implemented, and streambank
    protected; and graphical expression of water quality and BMP information
    plotted over the same time scale (e.g. seasonal median FC values with
    cumulative histogram of fully implemented farm plans).

 Currently unavailable.
 None.
 The fecal coliform (FC) results are variable from year to year and no trends are
 apparent in the study basins, except perhaps for Schneider Creek. Schneider
 Creek's FC levels seem to be decreasing from high values between 220-280 cfu/
 100 ml (upper 25th percentile) during the 1989-90 wet season to 25-160 cfu/100
 ml in 1995. The increase of FC in the 1989-90 season maybe due to increases in
 livestock at horse ranches in the basin. Since 1989, farm plans have been devel-
 oped and BMPs implemented on these ranches, which are likely helping to lower
 FC concentrations. FC levels in Kennedy Creek have remained low for the length
 of the data record. The highest concentrations of FC have been found in Burns
 and Pierre Creeks. FC levels in Perry Creek over the past 4 years appear to be
 lower than previous years. However, analyses for determining trends in FC levels
 will not be performed until after BMP installation is complete.

 The results of linear regression analyses show that flow and Antecedent Precipita-
 tion Index (API) correlate poorly with FC. API slope, TSS, and turbidity correlate
 more strongly with FC but were generally inconsistent among the stations or
 between years. Results suggest that the hydrologic characteristics in the study
 basins will make poor covariates of FC data for use in trends analyses or pre-and
 post-BMP comparisons. API slope, TSS, and turbidity will be more closely exam-
 ined over the coming years for their possible use as covariates.
                                                   191

-------
                                                                   • Totten and Eld Inlet, Washington
TOTAL PROJECT BUDGET
                           The estimated budget for the Totten and Eld Inlet National Monitoring Program
                           project for the period of FY 1993 - 1999 (six years):
Modifications Since
Project Started
Project Element

Proj Mgt
I&E
LT
WQ Monit
TOTALS
None.
                                                             Funding Source (S)
                                         Federal          State         Local         Total
                                             NA           NA          NA          NA
                                             NA           NA          NA          NA
                                             NA        300,000       100,000       400,000
                                         250,000         50,000          NA       300,000
                                         250,000        350,000       100,000       700,000
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
                           In response to increased and persistent closures of shellfish harvest areas and
                           threats to close additional areas, state and local groups developed the Shellfish
                           Protection Initiative (SPI). This program provides $3 million from State Referen-
                           dum 39 funds for implementing BMPs in targeted watersheds. The Totten Basin,
                           a targeted watershed, will receive $1.3 million in grant funds as part of the SPI.
                           Eld Inlet, although not selected as an SPI project, will receive $260,000 from the
                           SPI program to augment ongoing NPS control efforts in specific areas. In addi-
                           tion, $331,000 will be targeted for farm planning and implementation activities in
                           the Eld watershed from 1996 to 1999.
Modifications Since
Project Started
None.
OTHER PERTINENT INFORMATION
                           None.
PROJECT CONTACTS
 Administration
Dan Filip
Washington State Dept. of Ecology
Ecology Water Quality Program
P.O. Box 47600
Olympia, WA 98504-7600
(360) 407-6406; Fax: (360) 407-6426

Marilou Pivirotto/Jeannette Barreca
Ecology Southwest Region Office
PO Box 47775
Olympia, WA 98594-7775
(360) 407-6787; Fax: (360) 407-6305
                                            192

-------
                                                                          i Totten and Eld Inlet, Washington
Land Treatment
Water Quality
Monitoring
Linda Hofstad/Jane Hedges
Thurston County Environmental Health Services
2000 Lakeridge Drive SW
Olympia, WA 98502-6045
(360) 754-4111; Fax: (360) 754-2954

Management Team
Thurston Conservation District
6128 Capitol Blvd.
Tumwater, WA 98501
(360) 754-3588; Fax: (360) 753-8085

Keith Seiders
Washington State Dept. of Ecology
Ecology Watershed Assessments Section
P.O. Box 47710
Olympia, WA 98504-7710
(360) 407-6689; Fax: (360) 407-6884
Internet: kese461@ecy.wa.gov
                                                 193

-------
                               • Totten and Eld Inlet, Washington
194

-------
                               Wisconsin

                              Otter Creek
                              Section 319
    National Monitoring Program Project
Figure 35: Otter Creek (Wisconsin) Project Location
              195

-------
                                                                        Otter Creek, Wisconsin
  Scale
1
1

1
1
.5
1
Miles
0
1
0
1

1
1
 Wtometeis
                                                                          OC-1
                                                                         i (Single Downstream
                                                                          Station) i.e. outlet
Figure 36: Water Quality Monitoring Stations for Otter Creek (Wisconsin)
                                   196

-------
                                                                                    i Otter Creek, Wisconsin
PROJECT OVERVIEW
                               The Otter Creek Section 319 National Monitoring Program project is in east
                               central Wisconsin (Figure 35), with a project area of 11 square miles. Otter Creek
                               drains into the Sheboygan River, which then drains into Lake Michigan. Land use
                               mainly consists of dairies and croplands.

                               Otter Creek has a warmwater forage fishery. The fish community is degraded by
                               lack of cover, disturbed streambanks, and siltation. Fecal conform levels fre-
                               quently exceed the state standard of 400 counts per 100 ml, and dissolved oxygen
                               often drops below 2 mg/1 during runoff events. Fifteen percent of all water
                               dioxide concentration samples fall below the state standard of 5 mg/L. Otter
                               Creek delivers high concentrations of phosphorus and fecal coliform to the
                               Sheboygan River. These pollutants then travel to the near shore waters of Lake
                               Michigan, which serves as a water supply for municipal use and also supports
                               recreational fisheries.          '

                               Streambed sediments originating from cropland erosion, eroding streambanks,
                               and overgrazed dairy pastures are reducing the reproductive potential for a high
                               quality fishery with abundant forage fish. Otter Creek is further degraded by total
                               phosphorus and fecal coliform export from dairy barnyards, pastures, cropland,
                               and alfalfa fields. The mean concentration of 22 runoff events is 104 mg/1 for
                               suspended solids and 0.39 mg/1 for total phosphorus.

                               Critical area criteria are being used to reduce phosphorus and sediment loading to
                               project area streams. Eight of the nine  dairy operations in the project area were
                               classified as critical; two of the eight critical dairy operations spread enough
                               manure that their cropland was classified as critical. Streambank critical areas are
                               the 6,200 feet of streambank trampled by cattle.

                               Land treatment design is based on the pollutant type and the source of the pollut-
                               ant. Upland fields will be treated with cropland erosion control practices to reduce
                               sediment loss. Streambanks are being fenced to limit cattle access, and barnyard
                               structural practices are being installed  to reduce nutrient runoff into Otter Creek.
PROJECT DESCRIPTION
Water Resource
Type and Size
Water Uses and
Impairments
Pre-Project
Water Quality
Otter Creek is 4.2 miles long with an average gradient of .0023 ft/ft or 12.4 ft/
mile (Figure 36). The creek flows into and out of a small spring-fed lake called
Gerber Lake.

Otter Creek is used for fishing and for secondary body contact recreation. The
fishery is impaired by degraded habitat, while contact recreation is impaired by
high fecal coliform counts. Both uses are also impaired by eutrophic conditions.

The Otter Creek project area is part of the larger Sheboygan River watershed,
identified as a Priority Watershed in 1985. The watershed is characterized by
streambank degradation due to cattle traffic. Excessive phosphorus, fecal coliform,
and sediment runoff originate from manure spreading and cropland. Fisheries are
impaired because of degraded aquatic habitat that limits reproduction. Recreation
is limited by degraded fisheries and highly eutrophic and organically enriched
stream waters.
                                                  197

-------
                                                                               i Otter Creek, Wisconsin
Current Water
Quality Objectives
Modifications Since
Project Initiation

Project Time Frame

Project Approval
The Otter Creek project water quality objectives are as follows:

    Increase the numbers of intolerant fish species by improving the fish habitat
    and water quality.

    Improve the recreational uses by reducing the bacteria levels.

    Reduce the loading of pollutants to the Sheboygan River and Lake Michigan
    by installation of best management practices (BMPs) in the Otter Creek
    watershed.

•   Improve the wildlife habitat by restoring riparian vegetation.

None.
Spring, 1994 through Spring, 2001

My, 1993
PROJECT AREA  CHARACTERISTICS
Project Area
Relevant Hydrologic,
Geologic, and
Meteorological Factors
The Otter Creek watershed area is about 11 square miles. The Meeme River
watershed is the control watershed, with an area of about 16 square miles.

Average annual precipitation is 29 inches. Fifteen inches of rain falls during the
growing season between May and September. About 42 inches of snow (five
inches of equivalent rain) falls during a typical winter.

The topography of the watershed ranges from rolling hills to nearly level. The
soils are clay loams or silty clay loams that have poor infiltration and poor perco-
lation but high fertility. Soils are glacial drift underlain by Niagara dolomite.
Land Use
Land Use
Agricultural
Forest
Suburban
Wetland
Water
Total
                                                         72
                                                         13
                                                         11
                                                          3
                                                          1
                                                         100
                              Best management practices are being installed on critical dairies. Livestock
                              exclusion practices are also being installed.

                              Source: Wisconsin Department of Natural Resources, 1993a
 Pollutant Sources
 Modifications Since
 Project Started
 There are eight critical dairy operations that serve as important pollutant sources.
 Trampled streambanks and cropland and pastureland receiving dairy manure are
 also critical sources. Some critical area cropland is in need of erosion control
 practice installation.

 None.
                                                198

-------
INFORMATION, EDUCATION,  AND PUBLICITY
                                                                              Otter Creek, Wisconsin
Progress Towards
Meeting Goals
The Sheboygan County Land Conservation Department has developed and imple-
mented an effective educational program to reach project dairymen. Project
personnel have achieved a high level of participation through education, technical
assistance, effective communication, and cost-share assistance.

•   Watershed tours are held for landowners.

•   Watershed newsletters are sent biannually to landowners.

•   Annual watershed advisory committee meetings are held.

•   Small group tours of BMP installation sites are given for landowners
    considering installing BMPs.
NONPOINT SOURCE CONTROL STRATEGY AND DESIGN
Description
Modifications Since
Project Started

Progress Towards
Meeting Goals
Streambank erosion and cattle exclusion practices include shoreline and
streambank fencing and stabilization; barnyard management includes barnyard
runoff management and manure storage facilities; and cropland practices include
grassed waterways, reduced tillage, and nutrient and pesticide management.

None.
Eight critical barnyards have installed runoff controls.
 WATER QUALITY MONITORING
Design
Two monitoring studies are being conducted in the Otter Creek National Monitor-
ing Program project. They include a paired watershed study and an above and
below study (Figure 36).

There are six sampling sites on Otter Creek, and one site each at the outlet of the
Meeme and Pigeon River watershed. One of the sampling sites on Otter Creek is
also an outlet station that serves as the site for the single station before and after
monitoring site. There are two mainstem sites above and below a critical area
dairy.

The above and below watershed study is being conducted using stations OC2 and
OC4. Station OC2 is below the dairy where BMPs are being installed. Station
OC4 (Figure 36) is above this dairy. Station OC5 is a background station, and
station OC6 is below a dairy where BMPs are being installed.

The paired watershed study is being conducted using stations OC1 and MR1, the
outlet for the Meeme River watershed. Station OC1 is the outlet of the Otter Creek
Watershed where animal waste management and nutrient management BMPs are
being installed. It also serves as the monitoring site for a single downstream
station study. MR1 is being used as the control site for the paired watershed study.
                                              199

-------
                                                                                   i Otter Creek, Wisconsin
Modifications Since
Project Started

Parameters
Measured
The paired watershed study is used to assess the overall impact of best manage-
ment practices on water quality. The treatment watershed is 11 square miles and is
being monitored at station OC1. The control watershed area is 16 square miles of
the Meeme River watershed being monitored at station MR1. Biological, bacte-
rial, and chemical parameters are being monitored; precipitation and water
discharge are covariates for the paired watershed study.

The following table provides details on the sampling design for the paired study,
the upstream/downstream, and the single downstream station. The monitoring
sites are listed for reference. The primary covariates are very similar for each
study except for methods used for macroinvertebrates. The frequency of sampling,
the covariates, and the duration of each study are also listed.

None.
Biological

Fisheries survey
Macroinvertebrate survey
Habitat assessment
Fecal coliform (FC)
 Sampling Scheme
 Chemical

 Total phosphorus (TP)
 Dissolved phosphorus (DP)
 Total Kjeldahl nitrogen (TKN)
 Ammonia (NHs)
 Nitrogen series (N02-N and NOa-N)
 Turbidity
 Total suspended solids (TSS)
 Dissolved oxygen (DO)

 Covariates

 Stream discharge
 Precipitation

 Automatic, continuous water chemistry sampling occurs on an event basis. The
 schedule for chemical grab sampling and biological and habitat monitoring varies
 by station and by year. Chemical grab sampling occurred at a time characterized
 as midsummer-fall for 1990 and 1994 and during spring-midsummer in 1991.
 Future plans are for spring-midsummer monitoring in 1995 and 1999 and mid-
 summer-fall monitoring for  1998. Fisheries, macroinvertebrate, and habitat
 monitoring has been scheduled for midsummer in 1990, 1994, and 1998, and for
 the spring of 1991, 1995, and 1999.

 Fisheries monitoring includes sampling fish species, frequencies, andbiomass.
 Fisheries data are summarized and interpreted based on the Index of Biotic
 Integrity (Lyons, 1992). Macroinvertebrate monitoring criteria includes
 macroinvertebrate species or genera and numbers. Macroinvertebrate data are
 summarized and interpreted using the Hilsenhoff Biotic Index (HilsenhofT, 1987).
 Habitat parameters include riparian buffer width, bank erosion, pool area, stream
 width to depth ratio, riffle-to-riffle or bend-to-bend rating, percent fine sediments,
 and cover for fish. Habitat information is rated using the fish habitat rating system
 established for Wisconsin streams by Simonson et al. (1994).
                                                   200

-------
                                                                                      Otter Creek, Wisconsin
                               Grab and event-flow samples are being used for water chemistry monitoring.
                               Parameters sampled include TP, FC, DO, and TSS.
       Monitoring Scheme for the Otter Creek Section 319 National Monitoring Program Project
Sites or
Design Activities

Paired Otter Creek7
watershed OC1
design Meeme Riverc
MR1










Primary Frequency of Primary
Parameters Covariates Parameter Sampling Duration
Biological
Fisheries index Precipitation
MacroinvertebratesH Discharge
Habitat
FC
Bacterial & Chemical
TP
DP
TKN
NH3
NOs
NO2
Turbidity
TSS
DO

Annually 1990-1999
Annually
Annually

30 samples per
monitoring season;
weekly April-Oct







       Upstream/    Above Dairyc
       downstream   OC4
                   Below DairyT
                   OC2
    Fisheries index
    MacroinvertebratesF
    Habitat
    Same bacterial & chemical
    parameters as paired
    watershed study
Precipitation
Discharge
Annually
Annually
Annually
30 samples per
monitoring season;
weekly April-Oct.
                                                               1990-1999
Single
downstream




Otter Creek
OC1




Fisheries index
MacroinvertebratesF
Habitat
Same bacterial & chemical
parameters as paired
watershed study
Precipitation
Discharge




Annually
Annually

30 samples per
monitoring season;
weekly April-Oct.
1990-1999





       Treatment AreaT
       Control Areac
       Hilsenhoff Biotic Index level; kick samples11
       Family level; kick samples'1
Modifications Since
Project Started

Water Quality Data
Management and
Analysis
None.
All water chemistry data are being entered into the Wisconsin Department of
Natural Resources (DNR) data management system, WATSTORE (the U.S.
Geological Survey national database), U.S. Environmental Protection Agency's
Nonpoint Source Management System software (NPSMS), and STORET.
                                                   201

-------
                                                                                i Otter Creek, Wisconsin
NPSMS Data
Summary
Monitoring Station Parameters Report (FY95)
CHEMICAL PARAMETERS

Parameter Name
FLOW, STREAM, INSTANTANEOUS, CFS
PRECIPITATION, TOTAL (INCHES PER DAY)
BOD, 5 DAY
FECAL COLIFORM, MF, M-FC, 0.7 UM
NITROGEN, AMMONIA, TOTAL (MG/L AS N)
PHOSPHORUS, TOTAL (MG/L AS P)
FLOW, STREAM, INSTANTANEOUS, CFS
PRECIPITATION, TOTAL (INCHES PER DAY)
BOD,5DAY,20DEGC
FECAL COLIFORM, MF, M-FC, 0.7 UM
NITROGEN, AMMONIA, TOTAL (MG/L AS N)
PHOSPHORUS, TOTAL (MG/L AS P)
PH, LAB, STANDARD UNITS
PH, LAB, STANDARD UNITS
FLOW, STREAM, INSTANTANEOUS, CFS
PRECIPITATION, TOTAL (INCHES PER DAY)
BOD,5DAY,20DEGC
FECAL COLIFORM, MF, M-FC, 0.7 UM
NITROGEN, AMMONIA, DISSOLVED (MG/L AS N)
PH, LAB, STANDARD UNITS
PHOSPHORUS, TOTAL (MG/L AS P)
FLOW, STREAM, INSTANTANEOUS, CFS
PRECIPITATION, TOTAL (INCHES PER DAY)
BOD, 5 DAY
FECAL COLIFORM, MF, M-FC, 0.7 UM
NITROGEN, AMMONIA, DISSOLVED (MG/L AS N)
PH, LAB, STANDARD UNITS
PHOSPHORUS, TOTAL (MG/L AS P)
FISH HABITAT CONDITION INDEX
INDEX OF BIOLOGICAL INTEGRITY
FISH HABITAT CONDITION INDEX
INDEX OF BIOLOGICAL INTEGRITY
SUSPENDED SEDIMENT TOTAL RESIDUE AT 105C
SUSPENDED SEDIMENT TOTAL RESIDUE AT 105C
SUSPENDED SEDIMENT TOTAL RESIDUE AT 105C
SUSPENDED SEDIMENT TOTAL RESIDUE AT 105C
FISH HABITAT CONDITION INDEX
INDEX OF BIOLOGICAL INTEGRITY
                                                                  Parm Reporting   QUARTILE VALUES
                                                                  Type  Units
                                                                  S    CFS
                                                                  S
                                                                  S    MG/L
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                                  -75-  -50-  -25-
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  S
                                                                  B
                                                                  B
                                                                  B
                                                                  B
                                                                  U
                                                                  u
                                                                  U
                                                                  u
                                                                  B
                                                                  B
CFS
MG/L
CFS

MG/L

MG/LN
           5.3    1.7
           370    175
           .056   .037
           .21   .158
           8.2
          5000
           .39
           .53
           8.3
           8.2
 4.0
1200
.147
 .25
 8.2
 8.1
            1.3
            30
            .02
            .08
            2.4
            490
           .073
            .13
            7.9
            7.9
  6.4   3.4  2.2
15000  2600 1000
 .104   .059 .032
  8.3   8.2  8.1
 .286   .17  .07
CFS
MG/L

MG/LN


SCORE
SCORE
SCORE
SCORE
MG/L
MG/L
MG/L
MG/L
SCORE
SCORE

7.3
69000
.257
8.4
.89
80
70
70
70
9
172
324
112
80
80

3.3
14000
.11
8.2
.34
50
50
50
50
7
41
60
45
40
40

2.2
3300
.042
8.1
.11
40
40
40
40
5
12
16
20
25
25
Modifications Since
Project Started
Progress Toward
Meeting Goals
           None.
           The water quality data are being collected and will be added to STORET.
TOTAL PROJECT BUDGET
                              The total estimated cost of needed land treatment practices is $221,000. Funds
                              through the state of Wisconsin Nonpoint Source Program will be used to fund
                              cost-share practices. The estimated budget for the Otter Creek National Monitor-
                              ing Program project for the period FY94-FY95 (2 years) is:
                              Project Element

                              Proj Mgt
                              LT
                              I&E
                              WQ Monit
                              TOTALS
                                                 Funding Source(S)
                           Federal          State          Local         Total
                               NA         30,000            NA        30,000
                               NA        221,000            NA       221,000
                               NA          2,000            NA         2,000
                           120,000            NA            NA       120,000
                           120,000     '   253,000            NA       373,000
                                                202

-------
                                                                            Otter Creek, Wisconsin
Modifications Since
Project Started
                            (Wisconsin DNR will spend approximately $60,000 in FY96-97 on monitoring and land
                            use quantification and pollutant loading-modeling.) Source: Wisconsin Department of
                            Natural Resources, 1993a (M. Miller, Personal Communication, 1994)
None.
IMPACT OF OTHER FEDERAL AND STATE PROGRAMS
Modifications Since
Project Started
State grants are being provided to cover the cost of land treatment technical
assistance and information and educational support.

None.
OTHER PERTINENT INFORMATION
                           Cooperating agencies include the Wisconsin Department of Natural Resources,
                           Department of Agriculture, Trade, and Consumer Protection, Sheboygan County
                           Land Conservation Department, and the U.S. Geological Survey.
PROJECT CONTACTS
Administration
Land Treatment
Water Quality
Monitoring
Roger Bannerman
Nonpoint Source Section
Wisconsin Department of Natural Resources
101 South Webster St., Box 7921
Madison. WI 53707
(608) 266-2621; Fax (608) 267-2800
Internet: banner@dnr.state.wi.us

Michael Miller
Surface Water Standards and Monitoring Section
Wisconsin Department of Natural Resources
101 South Webster St., Box 7921
Madison, WI 53707
(608) 267-2753; Fax (608) 267-2800

Patrick Miles
County Conservationist
Sheboygan County Land Conservation Dept.
650 Forest Ave.
Sheboygan Falls, WI 53805   ;
(414) 459-4360; Fax (414) 459-2942

Dave Graczyk
USGS Water Resources Division
6417 Normandy Lane
Madison, WI 53719
(608) 276-3833; Fax (608) 276-3817
                                            203

-------
                                                                                 Otter Creek, Wisconsin
Information and
Education
AndyYenscha
University of Wisconsin - Extension
1304 S. 70th St., Suite 228
WestAllis,WI  53214
(414) 475-2877
                                                 204

-------
               Appendices
205

-------

-------
                                             Appendix I

        Minimum  Reporting Requirements
     For Section 319 National Monitoring
                                   Program  Projects
The United States Environmental Protection Agency (USEPA) has developed the
NonPoint Source Management System (NPSMS) software to support the required
annual reporting of water quality and implementation data for Section 319 Na-
tional Monitoring Program projects (USEPA, 1991). The software tracks nonpoint
source (NPS) control measure implementation with respect to the pollutants
causing the water quality problem.

Currently, NPSMS can accept and track the following information (USEPA,
1991):

Management Area Description:
•  State, USEPA Region, and lead agency.

•  Watershed management area description (management area name,
   management area identification, participating agencies, area
   description narrative).

•  305(b) waterbody name and identification.

•  Designated use support for the waterbody.

•  Major pollutants causing water quality problems in waterbody and
   relative source contributions from point, nonpoint, and background sources.

Best Management Practices (BMPs) and NPS Pollution Control
Measures:
•  Best management practices (BMP name, reporting units,
   indication whether the life of the practice is annual or multi-year).

•  Land treatment implementation goals for management area.

•  Pollutant sources causing impaired uses that are controlled
   by each BMP. Each control practice must be linked directly to the
   control of one or more sources of pollutants causing impaired uses.

Funding Information:
•  Annual contributions from each funding source and use of funding
   for each management area.
                  207

-------
                                                                    Appendix I: Minimum Reporting Requirements
REFERENCES
                               Water Quality Monitoring Plan:
                               •   Choice of monitoring approach (chemical/physical or biological/habitat).

                               •   Monitoring design and monitoring station identification (paired watersheds,
                                  upstream-downstream, reference site for biological/habitat monitoring, single
                                  downstream station). The paired watershed approach is recommended; the
                                  single downstream station is discouraged.

                               •   Drainage area and land use for each water quality monitoring station.

                               •   Delineation of monitoring year, seasons, and monitoring program duration.

                               •   Parameters measured (parameter name; indication if the parameter is a
                                  covariate; STORET, BIOSTORET, or 305(b) Waterbody System code;
                                  reporting units).

                               •   Quartile values for chemical/physical parameters. Quartile values are
                                  established cutoffs based on historical or first-year data for each season and
                                  monitoring station.

                               •   Maximum potential and reasonable attainment scores for biological
                                  monitoring parameters. Indices scores that correspond to full, threatened, and
                                  partial use supports are required.

                               •   Monitoring frequency. Chemical/physical monitoring, with associated
                                  covariates, must be performed with at least 20 evenly-spaced grab samples in
                                  each season. Fishery surveys must be performed at least one to three times per
                                  year. Benthic macroinvertebrates must be performed at least once per season,
                                  with at least one to three replicates or composites per sample. Habitat
                                  monitoring and bioassays must be performed at least once per season.

                               Annual Reporting:
                               •   The NPSMS software is used to report annual summary information. The raw
                                  chemical/physical and biological/habitat data are required to be entered into
                                  STORET and BIOSTORET, respectively.

                               •   Annual chemical/physical and covariates. The frequency count for each
                                  quartile is reported for each monitoring station, season, and parameter.

                               •   Annual biological/habitat and covariates. The scores for each monitoring
                                  station and season are reported.

                               •   Implementation tracking in the watershed and/or subwatersheds that
                                  constitute the drainage areas for each monitoring station. Implementation
                                  reported corresponds to active practices in the reporting year and includes
                                  practices with a one-year life span and practices previously installed and still
                                  being maintained.
                               USEPA. 1991. Watershed Monitoring and Reporting for Section 319 National
                               Monitoring Program Projects. Assessment and Watershed Protection Division,
                               Office of Wetlands, Oceans, and Watersheds, USEPA, Washington, D.C.
                                                  208

-------
                                                 Appendix II
                                            Abbreviations
ACP	  Agricultural Conservation Program
ADSWQ	  Automatic Data System for Water Quality
Ag	  Silver
AGNPS	  Agricultural Nonpoint Source Pollution Model
Al	  Aluminum
ANSWERS 	  Area! Nonpoint Source Watershed
                                Environment Response Simulation
API	  Antecedent Precipitation Index
As	  Arsenic
ASCS	  Agricultural Stabilization and Conservation
                                Service, USDA
B	  Boron
Ba	•.  Barium
Be	  Beryllium
BMPs	  Best Management Practices
BIBI	  Biological Index of Biotic Integrity
BIOS	  USEPA Natural Biological Data Management
                                System
BOD	  BiochemicalOxygenDemand
Ca	  Calcium
Cal Poly	  California Polytechnic State University
Cd	  Cadmium
CES	  Cooperative Extension Service, USDA
cfs	  Cubic Feet per Second
cfu	  Colony Forming Units
Cl	  Chloride
COD 	  Chemical Oxygen Demand
Cr	  Chromium
CREAMS	  Chemicals, Runoff, and Erosion from
                                Agricultural Management Systems Model
                     209

-------
                                                     i Appendix II:  Abbreviations
CTUER.	  Confederated Tribes of the Umatilla Indian
                                   Reservation
Cu	  Copper
DEC	  Department of Environmental Conservation
DO	  Dissolved Oxygen
DP	  Dissolved Phosphorus
DNR	  Department of Natural Resources
DSWC	  Division of Soil and Water Conservation
DWQ	  Division of Water Quality
EPIC	  Erosion Productivity Index Calculator
FC	  Fecal Coliform
Fe	  Iron
FS	  Fecal Streptococcus
FSA	  Farm Service Agency (USDA)
GIS	  Geographic Information System
GMV	  Geometric Mean Value
GRASS	  Geographic Resources Analysis Support
                                    System
HBI	  Hilsenhoff Biotic Index
HEL	  Highly Erodible Land
HUA	  Hydrologic Unit Area
I&E	  Information and Education Programs
IBI	  Index of Biotic Integrity
ICM	  Integrated Crop Management
IDNR	  Iowa Department of Natural Resources
DDNR-GSB	  Iowa Department of Natural Resources
                                    Geological Survey Bureau
ISU-CES	  Iowa State University Cooperative Extension
                                    Service
ISUE	 Iowa State University Extension
K	 Potassium
LRNRD	 Lower Republican Natural Resource District
LT	 Land Treatment
Ma	 Manganese
MCL	  Maximum Contaminant Level
Mg	  Magnesium
Mg/1	  Milligrams Per Liter
N	  Nitrogen
Na	  Sodium
NA	  Information Not Available
                       210

-------
                                                     Appendix II: Abbreviations
NCSU	  North Carolina State University
NDEQ	  Nebraska Department of Environmental
                                   Quality
NHs	Ammonia-Nitrogen
NH"^	  Ammonium-Nitrogen
Ni	  Nickel
NMP	  National Monitoring Program
NO2	•	Nitrite-Nitrogen
NO3	Nitrate-Nitrogen
NFS	  Nonpoint Source
NPSMS	  NonPoint Source Management System
NRCS		  Natural Resources Conservation Service
                                   (USDA)
NTU	  Nephelometric Turbidity Units
OCC	  Oklahoma Conservation Commission
OP	  Orthophosphate
p	  Phosphorus
Pb	  Lead
Proj Mgt	  Project Management
QA/QC	  Quality Assurance/Quality Control
RCWP	  Rural Clean Water Program
 Se	  Selenium
 Section319	  Section319 ofthe Water Quality Act of 1987
 Si	  Silica
 Sn	  Tin
 SO4~	Sulfate
 SPI	  Shellfish Protection Initiative
 SS	  Suspended Solids
 STORET	  USEPA STOrage and RETrieval Data Base for
                                    Water Quality
 TDP	 Total Dissolved Phosphorus
 TDS	 Total Dissolved Solids
 TKN	 Total Kjeldahl Nitrogen
 TMDL	 Total Maximum Daily Load
 TOC	  Total Organic Carbon
 TP	  Total Phosphorus
 TS	  Total Solids
 TSS	  Total Suspended Solids
 Ug/1	  Micrograms Per Liter
                       211

-------
                                                       i Appendix II: Abbreviations
UHL	  University Hygienic Laboratory (Iowa)
USDA	  United States Department of Agriculture
USEPA	  United States Environmental Protection
                                    Agency
USGS	  United States Geologic Survey (U.S.
                                    Department of the Interior)
VSS	  Volatile Suspended Solids
WATSTORE	  USGS Water Data Storage System
WCCF	  Webster County Conservation Foundation
WQ	  Water Quality
WQIP	  Water Quality Incentive Project
WQ Monit	  Water Quality Monitoring
WQSP	  Water Quality Special Project
Zn	  Zinc
                       212

-------
                                              Appendix III

                                   Glossary of Terms
AGNPS (Agricultural Nonpoint Source Pollution Model) — an event-based,
watershed-scale model developed to simulate runoff, sediment, chemical oxygen
demand, and nutrient transport in surface runoff from ungauged agricultural
watersheds.

Animal unit (AU) — One mature cow weighing 454 kg or the equivalent. For
instance, a dairy cow is 1.4 AU because it weighs almost 1.5 times a mature beef
cow. The animal units of smaller animals than beef cows is less than one: pigs =
0.4 AU and chickens = 0.033 AU.

Anadromous —  Fish that return to their natal fresh water streams to spawn.
Once hatched, these fish swim to the ocean and remain in salt water until sexual
maturity.

Artificial redds — An artificial egg basket fabricated of extruded PVC netting
and placed in a constructed egg pocket. Artificial redds are used to measure the
development of fertilized fish eggs to the alevin stage (newly hatched fish).

Alachlor — Herbicide (trade name Lasso) that is used to control most annual
grasses and certain broadleaf weeds and yellow nutsedge in corn, soybeans,
peanuts, cotton, woody fruits, and certain ornamentals.

Atrazine — Herbicide (trade  name Atrex, Gesa prim, or Primatol) that is
widely used for control of broadleaf and grassy weeds in corn, sorghum, sugar
cane, macadamia orchards, pineapple, and turf grass sod.

Autocorrelation — The correlation between adjacent observations in time or
space.

Bedload — Sediment or other material that slides, rolls, or bounces along a
stream or channel bed of flowing water.

Before-after design — A term referring to monitoring designs that require
collection of data before and after BMP implementation.
                           !
Beneficial uses  — Desirable uses  of a water resource  such as recreation
(fishing, boating, swimming) and water supply.
                 213

-------
                                              Appendix III: Glossary of Terms
Best management practices (BMPs) — Management or structural practices
designed to reduce the quantities of pollutants — such as sediment, nitrogen,
phosphorus, bacteria, and pesticides — that are washed by rain and snow melt
from farms into nearby surface waters, such as lakes,  creeks,  streams, rivers,
and estuaries. Agricultural BMPs can include fairly simple changes in practices
such as fencing cows out of streams (to keep animal  waste out of streams),
planting grass in gullies where water flows off a planted field (to reduce the
amount of sediment that runoff water picks up as it flows to rivers and lakes),
and reducing  the amount of plowing in fields where row crops are planted (in
order to reduce soil erosion and loss of nitrogen and phosphorus from fertilizers
applied to the crop land). BMPs can also involve building  structures, such as
large animal waste storage tanks that allow farmers to choose  when to spread
manure on their fields as opposed to having to spread it based on the volume of
manure accumulated.

BMP system — A  combination  of individual  BMPs into a "system" that
functions to reduce the same pollutant.

Biochemical oxygen demand (BOD) — Quantitative  measure of the strength
of contamination by organic carbon materials.

Chemical oxygen demand (COD) — Quantitative measure of the strength of
contamination by organic and inorganic carbon materials.

Cost sharing — The practice of allocating project funds to pay a percentage of
the cost of constructing or implementing a BMP. The remainder of the costs are
paid by the producer.

County ASC Committee — County Agricultural Stabilization and Conserva-
tion Committee: a county-level committee, consisting of three elected members
of the farming community in a particular county, responsible for prioritizing and
approving practices to be cost shared and for overseeing dissemination of cost-
share funds by the local USDA-Agricultural Stabilization and Conservation
Service office.

Covariance — A measure of the relationship between two variables whose
values are observed at the same time.

Covariate — The parameter which is related to another parameter.

Critical area — Area or source of nonpoint source pollutants  identified in the
project area as having the most significant impact on  the impaired use of the
receiving waters.

Demonstration project — A project designed to  install or implement pollution
control practices primarily for educational or promotional purposes. These
projects often involve no (or very limited) evaluations of the effectiveness of the
control practices.

Designated use — Uses specified in terms of water quality standards for each
water body or segment.

Drainage area — An area of land that drains to  one point.
                  214

-------
                                               Appendix III: Glossary of Terms
Ecoregion — A physical region that is defined by its ecology, which includes
meteorological factors, elevation, plant and animal speciation, landscape posi-
tion, and soils.

EPIC (Erosion Productivity Index Calculator) —  A mechanistic computer
model that calculates erosion from field-size watersheds.

Erosion — Wearing away of rock or soil by the gradual detachment of soil or
rock fragments by water, wind, ice, and other mechanical or chemical forces.

Eskers — Glacially deposited gravel and sand that form ridges 30 to 40 feet in
height.

Explanatory variables — Explanatory variables, such as climatic, hydrologi-
cal, land use, or additional water quality variables, that change over time and
could affect the water quality variables related to the primary pollutant(s) of
concern or the use impairment being measured. Specific examples of explanato-
ry variables are season, precipitation, streamflow, ground  water table depth,
salinity, pH, animal units, cropping patterns, and impervious land surface.

Fecal coliform  (FC) — Colon bacteria that are released in fecal material.
Specifically, this group comprises all of the aerobic and facultative anaerobic,
gram-negative, nonspore-forming, rod-shaped bacteria that ferment lactose with
gas formation within 48 hours at 35 degrees Celsius.

Fertilizer management — A BMP designed to minimize the contamination of
surface and ground water by limiting the amount of nutrients (usually nitrogen)
applied to the soil to no more than the crop is expected to use. This may involve
changing fertilizer application techniques, placement, rate, and timing.

Geographic information systems (GIS) — Computer programs linking fea-
tures commonly seen on maps (such as roads, town boundaries, water bodies)
with related information not usually presented on maps, such as type of road
surface, population,  type of agriculture, type of vegetation, or water quality
information. A GIS is a unique information system in which individual observa-
tions can be spatially referenced to each other.

Goal—A narrowly focused measurable or quantitative milestone used to assess
progress toward attainment of an objective.

Interfluve — A flat area between streams.

Land treatment—The whole range of BMPs implemented to control or reduce
NFS pollution.

Loading — The influx of pollutants to a selected water body.

Macroinvertebrate — Any non-vertebrate organism that is large enough to be
seen without the aid of a microscope.

Mechanistic — Step-by-step path from cause to effect with ability to make
linkages at each step.
                  215

-------
                                              Appendix III: Glossary of Terms
Moraine — Glacial till (materials deposited directly by ice) which is generally
irregularly deposited.

Nitrogen — An element occurring in manure and chemical fertilizer that is
essential to the growth and development of plants, but which, in excess, can
cause water to become polluted and threaten aquatic animals.

Nonpoint source (NFS) pollution — Pollution originating from diffuse areas
(land surface or atmosphere) having no well-defined source.

Nonpoint source pollution controls — General phrase used to refer to all
methods employed to control or reduce nonpoint source pollution.

NonPoint Source Management System (NPSMS) — A software system de-
signed to facilitate information tracking and reporting for the USEPA 319
National Monitoring Program.

Objective — A focus and overall framework or purpose for a project or other
endeavor, which may be further defined by one or more goals.

Paired watershed design — In this design, two watersheds with similar physi-
cal characteristics and, ideally, land use are monitored for one to two years to
establish pollutant-runoff response relationships for each watershed. Following
this initial calibration period, one of the watersheds receives treatment while the
other (control) watershed does not. Monitoring of both watersheds continues for
one to three years. This experimental design accounts for many factors that may
affect the response to treatment; as a result, the treatment effect alone can be
isolated.

Parameter — A quantity or constant whose value varies with the circumstances
of its application.

Pesticide management—A BMP designed to minimize contamination of soil,
water, air, and nontarget organisms by controlling the amount, type, placement,
method, and timing of pesticide application necessary for crop production.

Phenolphthalein alkalinity — A measure of the bicarbonate content.

Phosphorus —An element occurring in animal manure and chemical fertilizer
that is essential to the growth and  development of plants, but which, in excess,
can cause water to become polluted and threaten aquatic animals.

Post-BMP implementation — The period of use and/or adherence to the BMP.

Pre-BMP implementation — The period prior to the use of a BMP.

Runoff— The portion of rainfall or snow melt that  drains off the land into
 ditches and streams.

Sediment—Particles and/or clumps of particles of sand, clay, silt, and plant or
 animal matter carried in water.
                  216

-------
                                               Appendix III: Glossary of Terms
Sedimentation — Deposition of sediment.

Single-station design — A water quality monitoring design that utilizes one
station at a point downstream from the area of BMP implementation to monitor
changes in water quality.

Subbasins — One of several basins that form a watershed.

Substrate sampling — Sampling of streambeds to determine the percent of fine
particled material and the percent of gravel.

Subwatershed — A  drainage area within the project watershed. It can be as
small as a single field or as large as almost the whole project area.

Tailwater management — The practice of collecting runoff, "tailwater," from
irrigated fields. Tailwater is reused to irrigate crops.

Targeting — The process of prioritizing pollutant sources for treatment with
BMPs or a specific  BMP to  maximize the water quality benefit from the
implemented BMPs.

Total alkalinity — A measure of the titratable bases, primarily carbonate,
bicarbonate, and hydroxide.

Total Kjeldahlnitrogen (TKN)—An oxidative procedure that converts organic
nitrogen forms to ammonia by digestion with an acid, catalyst, and heat.

Total Kjeldahl phosphorus  (TKP) — An oxidative procedure that converts
organic phosphorus forms to phosphate by digestion with an acid, catalyst, and
heat.

Tracking—Documenting/recording the location and timing of BMP implemen-
tation.

Turbidity — A unit of measurement quantifying the  degree to which light
traveling through a water column is scattered by the suspended organic (includ-
ing algae) and inorganic particles. The scattering  of  light increases with a
greater suspended load. Turbidity is commonly measured in Nephelometric
Turbidity Units (NTU), but may also be measured in Jackson Turbidity Units
(JTU).

Upstream/downstream  design — A water quality monitoring design that
utilizes two water quality monitoring  sites.  One station is placed directly
upstream from the area where the implementation will occur and the second is
placed directly downstream from that area.

Vadose zone — The  part of the soil solum that is generally unsaturated.

Variable—A water quality constituent (for example, total phosphorus pollutant
concentration) or other measured factors (such as stream flow, rainfall).
                 217

-------
                                               Appendix III: Glossary of Terms
Watershed — The area of land from which rainfall (and/or snow melt) drains
into a stream or other water body. Watersheds are also sometimes referred to as
drainage basins. Ridges of higher ground generally form the boundaries between
watersheds. At these boundaries, rain falling on one side flows toward the low
point of one watershed, while rain falling on the other side of the boundary flows
toward the low point of a different watershed.
                  218

-------
                                                                Appendix IV

                                               Project Documents And
                                         Other Relevant Publications
                                         This appendix contains publication references for the
                                         Section 319 National Monitoring Program projects. Project
                                         document lists appear in alphabetical order by state.
ALABAMA LIGHTWOOD KNOT CREEK

SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                         1996. NonpointSource Water Quality Monitoring Projectfor LightwoodKnot Creek
                         Watershed in Southeast Alabama: A Report to the Alabama Department of Environ-
                         mental Management for the Period January 1, 1996 to March 31, 1996. Tuscaloosa,
                         Alabama.

                         Geological Survey of Alabama. 1995. Project Proposal for Watershed Monitoring
                        for Section 319 National Monitoring Program. Nonpoint Source Water Quality
                         Monitoring Project for Lightwood Knot Creek Watershed in Southeast Alabama.
                         Tuscaloosa, Alabama. 30 p.


ARIZONA OAK CREEK CANYON

SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                         Spooner, J., D. Osmond.  1996. Memorandum to Gordon Southam.

                         Arizona Department of Environmental Quality. April, 1991. Oak Creek Watershed,
                         NFS 319 Project, Arizona Department of Environmental Quality Nonpoint Source
                         Program.

                         1994. Oak Creek National Monitoring Project Workplan (Revised), June. Work-
                         plan.

                         Dressing, S. A. 1994. Review of Project III (Camping) in Oak Creek Project, 7/13.
                         Memorandum from Steve Dressing to Chris Heppe.

                         Dressing, S. A. 1994. Approval oj'Project II of 'Oak Creek, AZ as National Monitor-
                         ing Project, 7/18. Memorandum from Steve Dressing to Jovita Pajarillo.

                         Dressing, S. A. 1993. Review of Proposal for Section 319 National Monitoring
                         Program, 11/16.
                                       219

-------
                                                                     i Appendix IV: Project Documents
                           Dressing,  S. A. 1994.  Oak Creek, AZ National Monitoring Project Proposal:
                           Review and Recommendations, 6/23. Memorandum from Steve Dressing to Chris
                           Heppe.

                           Dressing, S. A. 1994. Approval of Oak Creek, AZ as a National Monitoring Project,
                           7/7. Memorandum from Steve Dressing to Jovita Pajarillo.

                           Dressing, S. A. 1994. Oak Creek: Comments on the Slide Rock Parking Lot,  7/12.
                           Memorandum from Steve Dressing to Chris Heppe.

                           Dressing, S. A., E. Liu, andR. Frederick. 1994. Review of Proposal for Section 319
                           National Monitoring Program.

                           Harrison, T. D. 1994. Oak Creek, AZ National Monitoring Proposal: Response to
                           Steve Dressing's Memorandum of July 13, 1994, 7/15. Memorandum from Tom
                           Harrison to Chris Heppe.

                           Harrison, T. D. 1993. Equivalencies of Slide Rock and Grasshopper Point: Two
                           Popular Swimming Holes in Oak Creek Canyon,  10/7. Memorandum from Tom
                           Harrison to Benno Warkentin and Jean Spooner.

                           Harrison, T. D. 1993.  Slide Rock/Grasshopper Point Comparative Data, 10/11.
                           Memorandum from Tom Harrison to Jean Spooner and Benno Warkentin.

                           Harrison, T. D. 1993. Fecal Coliforms: Slide Rock and Grasshopper Point—1977 to
                           1980, 10/12. Memorandum from Tom Harrison to Jean Spooner.

                           Harrison, T.  D.  1994. The  Oak Creek 319(h) Demonstration Project: National
                           Monitoring Program Work Plan, February. Replaces 9AZ002. The Northern Arizo-
                           na University Oak Creek Watershed Team.

                           Harrison, T. D. 1994. Oak Creek, AZ National Monitoring Project Assurances, 7/5.
                           Memorandum from Tom Harrison to Chris Heppe.

                           Harrison, T.D., S. Salzler, J.B. Mullens, and D. Osmond. 1995. Oak Creek Canyon
                            (Arizona) Section 319 National Monitoring Program Project.  NWQEP NOTES
                            71:1-3, North Carolina  State University Water Quality Group, North Carolina
                            Cooperative Extension Service, Raleigh, NC.

                            Heppe, C. 1994. Approval letter for Project I, 7/12. Letter from Chris Heppe to Dan
                            Salzler.

                            Southam, G. 1996. The  Oak Creek Canyon Section 319(h) National Monitoring
                            Project. Summary of Two-Year Baseline Monitoring. Submitted to the USEPA.

                            Warkentin, B. P. 1993. Arizona Oak Creek Project, Recommendation for adoption
                            into the 319 National Monitoring Project, 10/1. Memorandum from Benno Warken-
                            tin to Ed Liu.


CALIFORNIA MO PRO BAY WATERSHED
SECTION 319 NATIONAL  MONITORING PROGRAM PROJECT


                            State of California: Regional Water Quality Control Boards. Morro Bay briefing
                            materials.

                             1987. Wastewater Treatment Facilities: Final Environmental Impact Report. The
                            Morro Bay Group, County of San Luis Obispo, Government Center.
                                              220

-------
                                               i Appendix IV: Project Documents
1989. Erosion and Sediment Study: Morro Bay Watershed, September. Soil Conser-
vation Service.

1989. Morro Bay Watershed Enhancement Plan, September. Soil Conservation
Service.

The Morro Bay Group. 1990. Freshwater Influences on Morro Bay, San Luis Obispo
County, The Morro Bay Group, Prepared for the Bay Foundation of Morro Bay, P.O.
Box 1020, Morro Bay, CA 93443.

1991. Proposed Monitoring Program, 7/1.

1991. Workplanfor Water Quality Management Planning Program [Section 205(j)J
on Non-Point Source Evaluation and Treatment Effectiveness for Land Treatment
Measures for the Morro Bay Watershed, Coastal San Luis Resource Conservation
District, 6/4. Workplan.

USEPA.  1991. California's High on Coastal Nonpoint Source Karma! In EPA
News-Notes, #14.

1992. Nonpoint Source Pollution Evaluation and Treatment Measures for the Morro
Bay Watershed, 2/18.

1992. Morro Bay Watershed Program, Watershed Educational Program, December.
Fact Sheet No. 1.

Morrow Bay HUA. 1992. FY-92: Annual Progress Report, Morro Bay HUA. Soil
Conservation Service.

Morro Bay HUA. 1993.  Workplanfor Non-Point Source Pollution and Treatment
Measure Evaluation for the Morro Bay  Watershed, Revised 3/15. Workplan.

Morro Bay HUA. 1993. Morro Bay Sedimentation Project Progress Report, 5/3.

1993. Approach for San Luis Obispo Creek, 8/21.

1993. Report on Morro Bay Project in California, 2/3, by Oregon.

Central Coast Regional Water Quality Control  Board. 1993.  Nonpoint Source
Pollution and Treatment Measure Evaluation for the Morro Bay  Watershed.

1994. Report on Visit to the California 319 Monitoring Site at Morro Bay, 3/14.

Dressing, S. A. 1992. Review of Proposal for Section 319 National Monitoring
Program (Morro Bay, CA),  9/11. Fax Transmittal to JovitaPajarillo.

Haltiner, J.  1988. Sedimentation Processes  in Morro Bay,   Prepared by Philip
Williams and Associates for the Coastal San Luis Resource Conservation District
with funding by the California Coastal Conservancy.

USEPA. 1991. California's High on Coastal Nonpoint Source Karma! In EPA
News-Notes, #14.

Worcester, K. 1994. Morro Bay,  California: Everyone's Pitching In. From Nonpoint
Source News-Notes, #35.

Worcester, K. T. J. Rice,  and  J. B. Mullens. 1994. Morro Bay Watershed 319
National Monitoring Program Project.  NWQEP NOTES 63:1- 3, North  Carolina
State University Water Quality Group, North  Carolina  Cooperative Extension
Service, Raleigh, NC.
                   221

-------
                                                                         Appendix IV:  Project Documents
IDAHO EASTERN SNAKE RIVER PLAIN
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                             Idaho Snake River Plain, USDA Demo Project Flyer.

                             Idaho Snake River Plain USDA Water Quality Demonstration Project Newsletter.
                             Newsletter, Vol. 1, 1-4 and Vol. 2,1-2.

                             Idaho Snake River Plain Water Quality Demonstration Project. 1991. Idaho Snake
                             River Plain Water Quality Demonstration Project Proposal, September.

                             Idaho Snake Paver Plain Water Quality Demonstration Project. 1991. Idaho Snake
                             River Plain USDA Water Quality Demonstration Project, September. Pamphlet.

                             Idaho Snake River Plain Water Quality Demonstration Project. 1991. FY1992 Plan
                             of Operations.

                             Idaho Snake River Plain Water Quality Demonstration Project. April, 1991. Plan of
                             Work.

                             Idaho Snake River Plain Water Quality Demonstration Project. October, 1991. FY
                             1991 Annual Report.

                             Idaho Snake River Plain Water Quality Demonstration Project. 1992. 1992 Annual
                             Progress Report.

                             Idaho Snake River Plain Water Quality Demonstration Project. 1992. FY 1993 Plan
                             of Operations.

                             Idaho Snake River Plain Water Quality Demonstration Project. October, 1992. FY
                             1992 Annual Report.

                             Brooks, R.  1994. Water Line: Idaho Snake River Plain USDA  Water  Quality
                             Demonstration Project Newsletter. Water Line, Vol. 3 No. 2.

                             Brooks, R. ed. April 1995. Water Line.

                             Brooks, R. H. 1993. Water Line: Idaho Snake River Plain USDA Water Quality
                             Demonstration Project Newsletter. Vol. 2 No. 4.

                             Brooks, R. H., ed. October 1994. Water Line.

                              Camp, S. and R. L.  Mahler. 1991. Idaho Snake River Plain:  USDA Water Quality
                             Demonstration Project. WQ-3 Brochure.

                              Camp, S. D. 1992. Urban Survey: Minidoka and Cassia County. Idaho Snake River
                              Plain Water Quality Demonstration Project.

                              Camp, S. D. 1992. Management Practices on Your Farm: A Survey of Minidoka and
                              Cassia  County Farmers About their Farming Practices.  The Idaho Snake River
                              Water Quality Demonstration Project.

                              Camp, S. D. 1993.  Idaho Snake-River Plain USDA Water Quality Demonstration
                              Project Newsletter. Water Line, Vol. 2 No. 1.

                              Cardwell, J. 1992. Idaho Snake River Plain USDA Water Quality Demonstration
                              Project Water Quality Monitoring Program DRAFT. Idaho Department of Environ-
                              mental Qualify.
                                                222

-------
                                                                          i Appendix IV: Project Documents
                             Mullens, J. B. 1993. Snake River Plain, Idaho, Section 319 National Monitoring
                             Program Project. NWQEP NOTES 61:5-6, North Carolina State University Water
                             Quality Group, North Carolina Cooperative Extension Service, Raleigh, NC.

                             Osiensky, J. 1992. Ground Water Monitoring Plan: Snake River Plain Water Quality
                             Demonstration Projects. University of Idaho and Idaho Water Resources Research
                             Institute.

                             Osiensky, J. and M. F. Long. 1992. Quarterly Progress Report for the Ground Water
                             Monitoring Plan: Idaho Snake River Plain Water Quality Demonstration Project.
                             University of Idaho Water Resources Research Institute.

                             Osiensky, J. L. and M. F. Baker. 1993. Annual Progress Report: Ground Water
                             Monitoring Program for the Snake River Plain  Water Quality Demonstration
                             Project, February 1, 1992 through January 31, 1993. University of Idaho and Idaho
                             Water Resources Research Institute.

                             Osiensky, J. L. and M. F. Baker. 1994. Annual Progress Report: Ground Water
                             Monitoring Program for the Snake River Plain  Water Quality Demonstration
                             Project.


ILLINOIS LAKE PITTSHELD
SECTION 319 NATIONAL MONITORING  PROGRAM PROJECT


                              1992. FY-92  319(h)  Workplan:  Illinois River Watershed Monitoring Program.
                             Workplan.

                              1992. Monitoring Lake Pittsfield to Determine the Effectiveness of Erosion and
                             Sediment Control Measures Adjacent to the Lake Shore.

                              1992. Quality Assurance Program Plan for the Lake Pittsfield Watershed Monitoring
                             Project, FY-1992.

                              1992. Revisions to Pittsfield Monitoring Project. Letter to EPA.

                              1992. Articles in the Pike Press Regarding Atrazine in the Water Supply.

                              1992. Lake Pittsfield Resource Plan (Draft).

                              1992. National Monitoring Contract.

                              Trutter, C., ed. 1993. Watershed  Watch. Vol. 1, No. 1.

                              1993. Lake Pittsfield Watershed Monitoring Project: Response to EPA Questions.

                              1993. Quality Assurance Program Plan for the Illinois EPA Grant to Perform a
                              Sedimentation and Water Quality Study at Lake Pittsfield, Pike County.

                              Trutter, C., ed. 1993. Lake Pittsfield. In Watershed Watch, Vol. 1, No. 1.

                              1993. Section 319 Implementation Contract.

                              1993. Effects of Land Management on Lake Pittsfield Sedimentation and Water
                              Quality: Annual Report, September.

                              1993. Lake Pittsfield: Watershed Monitoring Project. Illinois State Water Survey,
                              Peoria, Illinois.
                                                223

-------
                                                                          i Appendix IV: Project Documents
                             Trutter, C., ed.  Fall 1994.  Watershed Watch.  Illinois Environmental Protection
                             Agency Newsletter.

                             Trutter, C., ed. Spring 1995. Watershed Watch. Illinois Environmental Protection
                             Agency Newsletter.

                             Trutter, C., ed. Winter 1996. Watershed Watch. Illinois Environmental Protection
                             Agency Newsletter. Vol4., No. 1.

                             Trutter, C., ed.  Spring/Summer 1996. Watershed Watch. Illinois Environmental
                             Protection Agency Newsletter. Vol 4., No. 2.

                             Dressing,  S. A.  1992. Review of Proposal for Section 319 National Monitoring
                             Program.

                             Dressing,  S. A.  1993. Review of Proposal for Section 319 National Monitoring
                             Program (Revised).

                             Illinois Environmental Protection Agency. 1993. Lake Pittsfield Project Draws
                             International Attention. Watershed Watch, l(2):l-2.

                             Illinois Environmental Protection Agency. 1993. Lake Pittsfield. Watershed Watch
                              Illinois State Water Survey. 1995. Effects of Land Management on Lake Pittsfield
                              Sedimentation and Water Quality. National Monitoring Strategy on Lake Pittsfield
                              3rd Annual Report, prepared for the Illinois Environmental Protection Agency.

                              Osmond, D. L. 1994. Lake Pittsfield Meeting Notes, 7/6. Attendance Notes.

                              Roseboom, D.P., R. K. Raman, and R. Sinclair. Sept. 30, 1994. Effects of Land
                              Management on Lake Pittsfield Sedimentation and Water Quality.

                              Roseboom, D.P., G. Eicken, andD. Osmond. 1995. Lake Pittsfield (Illinois) Section
                              3 19 National Monitoring Program Project. NWQEP NOTES 70:4-6, North Carolina
                              State University Water Quality  Group, North Carolina  Cooperative  Extension
                              Service, Raleigh, NC.

                              Roseboom, D.P., R. Sinclair, and  G. Eicken. 1995. Are Erosion Control Programs
                              Reducing Sedimentation. Internal report.

                              State of Illinois. 1992. Environmental Protection Agency Intergovernmental Agree-
                              ment No. FWN-3019.

                              State of Illinois. 1993. Environmental Protection Agency Intergovernmental Agree-
                              ment No. FWN-3020.

                              Taylor, A. G.  1992. Illinois Water Quality Sampling Update: Pesticides.


IOWA SNYMAGILL WATERSHED
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                              Animal Waste Nutrient Inventories and Crop Fertilizer Needs for the Northeast
                              Iowa Demonstration Project and Sny Magill Watershed, Clayton County.

                              University of Iowa, State Hygienic Laboratory. 1977. Summer Water Quality of the
                              Upper Mississippi River Tributaries. University of Iowa, State Hygienic Laboratory,
                              p 77-90.

                                                224

-------
                                                i Appendix IV:  Project Documents
University of Iowa, State Hygienic Laboratory. 1977. Summer Water Quality Survey
of the Bloody Run Creek and Sny Magill Creek Basins. University of Iowa, State
Hygienic Laboratory, 24 p.

1986. North Cedar Creek Critical Area Treatment and Water Quality Improvement.
Clayton County Soil Conservation District, Iowa Department of Natural Resources,
the Upper Exploreland Resource Conservation and Development Area. 31 p.

1991. Proposal, 3/91 and 11/27.

USEPA. 1991. Summary of EPA-Headquarters Review Comments, 5/29.

1991. Big Spring Basin Water-Quality Monitoring Program: Design andlmplemen-
tation, July.

Soil Conservation Service. 1991. Sny Magill  Creek Cold Water Stream Water
Quality Improvement Agricultural Nonpoint Source Hydrologic  Unit Area: Fiscal
Year 1991. Soil Conservation Service, Iowa State University Cooperative Extension
Service, Iowa Agricultural Stabilization and Conservation Service, 15 p.

November, 1991.  Nonpoint Source Pollution Monitoring Project Workplan. Iowa
Department of Natural Resources, Geological Survey Bureau.

USEPA, 1992. Summary of EPA-Headquarters Review Comments, 5/29.

Wittman, C., ed. 1992. Water Watch: A newsletter for Big Spring Basin, Sny Magill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
40.

Wittman, C., ed. 1992. Water Watch: A newsletter for Big Spring Basin, Sny Magill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
41.

1992. Sny Magill CreekCold Water Stream Water Quality Improvement,  1992 HUA
AnnualReport.

1992. Sny Magill Creek Cold Water Stream Water Quality Improvement Agricultur-
al Nonpoint Source Hydrologic Unit Area: Fiscal Year 1992. Soil Conservation
Service, Iowa State University Cooperative Extension Service, Iowa Agricultural
Stabilization and Conservation Service, 35 p.

Wittman, C., ed. 1993. Water Watch: A newsletter for Big Spring Basin, Sny Magill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
45.

Wittman, C., ed. 1993. Water Watch: A newsletter for Big Spring Basin, Sny Magill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
46.

1993. Mailing List for Sny Magill, revised 10/18.

1993. Water Watch: A newsletter for Big Spring Basin, Sny Magill Watershed, and
Northeast Iowa Demonstration Project areas. Newsletter, Issue No. 47.

Soil Conservation Service. 1993. Sny Magill CreekCold Water Stream water quality
improvement (fiscal year 1993 hydrologic unit area annual report). Submitted by
the Soil Conservation, Iowa State University Cooperative Extension Service, and the
Agricultural Stabilization and Conservation Service, 53 p.
                   225

-------
                                               i Appendix IV: Project Documents
Wittman, C., ed. 1994. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
49.

Wittman, C., ed. 1994. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
48.

Siegley, L.S. 1994. Memo to Sny Magill Monitoring Project Cooperators. Memo-
randum.

1994. Summary of Sny Magill Annual Meeting Held June 24. Contains updated
project bibliography.

1994. Sny Magill Nonpoint Source Pollution Monitoring Project: Clayton County,
Iowa 1992 Annual Report for Water Year 1992, June. Report.

Wittman, C., ed. 1994. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
50.

Wittman, C., ed. 1994. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
51.

Soil Conservation Service. 1994. SnyMagill Creek Cold Water Stream water quality
improvement (fiscal year 1994 hydrologic unit area annual report). Submitted by
the Soil Conservation, Iowa State University Cooperative Extension Service, and the
Agricultural Stabilization and Conservation Service, 52 p.

NRCS.  1995. Sny Magill Creek Cold Water Stream -water quality improvement
(fiscal year 1995 hydrologic unit area annual report). Submitted by the Natural
Resources Conservation Service, Iowa State University Extension, and the Farm
Service Agency, 50 p.

Wittman, C., ed. 1995. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
59.

Wittman,  C., ed. Wittman, C., ed.  1996. Water Watch: A newsletter for Big Spring
Basin, Sny Magill Watershed, and Northeast Iowa Demonstration Project areas.
Newsletter, Issue No. 60.

Wittman, C., ed. 1996. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, and Northeast Iowa Demonstration Project areas. Newsletter, Issue No.
61.

Wittman, C., ed. 1996. Water Watch: A newsletter for Big Spring Basin, SnyMagill
Watershed, andNortheast Iowa Demonstration Project areas. Newsletter, Issue No.
62.

June  24,  1994. Status of Stream Habitat Assessment for the Sny Magill Creek
Monitoring Project.

July 27,1994. Sny Magill Nonpoint Source Pollution Monitoring Project Bibliogra-
phy.

Wittman,  C., ed.  October, 1994. Water Watch: A newsletter for Big Spring Basin,
SnyMagill Watershed, andNortheast Iowa Demonstration Project areas. Newslet-
ter, Issue No. 52.
                    226

-------
                                                1 Appendix IV: Project Documents
Wittman, C., ed. December, 1994. Water Watch: A newsletter for Big Spring Basin,
SnyMagill Watershed, and Northeast Iowa Demonstration Project areas. Newslet-
ter, Issue No. 53.

Wittman, C., ed. February, 1995. Water Watch: A newsletter for Big Spring Basin,
SnyMagill Watershed, and Northeast Iowa Demonstration Project areas. Newslet-
ter, Issue No. 54.

September, 1995. SnyMagill Watershed Project-Clayton County, Iowa (pamphlet),
4 p.

Bettis, E. A. III. 1994. Paleozoic Plateau erosion perspective. In: Seigley, L.S. (ed.),
Sny Magill watershed monitoring project: baseline data. Iowa Department of
Natural Resources, Geological Survey Bureau, Technical Information Series 32, p.
19-27.

Bettis, E. A. Ill, L. S. Seigley, G. R. Hallberg, and J. D. Giglierano. 1994. Geology,
hydrogeology, and landuse of Sny Magill and Bloody Run watershed. In: Seigley,
L.S. (ed.), Sny Magill watershed monitoring project: baseline data. Iowa Depart-
ment of Natural Resources, Geological Survey Bureau, Technical Information Series
32, p. 1-17.

Birmingham, M. W. and J. O. Kennedy.  1994. Historical biological water quality
data for Sny Magill and Bloody Run creeks. In: Seigley, L.S.  (ed.), Sny Magill
watershed monitoring project: baseline data. Iowa Department of Natural Resourc-
es, Geological Survey Bureau, Technical Information Series 32, p. 125-130.

Birmingham, M.W., M.D. Schueller, and J.O. Kennedy. 1995. Sny Magill Creek
Nonpoint Source Pollution Monitoring Project:  1994 Benthic Biomonitoring Re-
sults. University of Iowa Hygienic Laboratory, Limnology Section, Report No. 96-1,
141 p.

Hallberg, G. R., L. S. Seigley, R.  D. Libra, Z. J. Liu, R D. Rowden, K. D. Rex, M. R.
Craig, and K. O. Mann. 1994. Water quality monitoring perspectives for northeast
In: Seigley, L.S. (ed.), Sny Magill watershed monitoring project: baseline data. Iowa
Department of Natural Resources, Geological Survey Bureau, Technical Informa-
tion Series 32, p. 29-41.

Hallberg, G. R, R. D. Libra, Zhi-Jun Liu, R. D. Rowden, and K. D. Rex. 1993.
Watershed-scale water quality response to changes in landuse and nitrogen manage-
ment In: Proceedings, Agricultural Research to Protect Water Quality, Soil and
Water Conservation Society, Ankeny, IA, p. 80-84.

Iowa State University Extension.  1992.  Sny Magill  Watershed farm practices
survey.  Iowa State University Cooperative Extension, August 1992, 2 p.

Iowa State University Extension.  1995a.  Sny Magill  Watershed farm practices
survey.  Iowa State University Cooperative Extension, October 1995, 2 p.

Iowa State University Extension. 1995b. Bloody Run Watershed farm practices
survey.  Iowa State University Cooperative Extension, October 1995, 2 p.

Kalkhoff, S. J. and D. A. Eash.  1994. Suspended sediment and stream discharge in
Bloody Run and Sny Magill watersheds: water year 1992. In: Seigley, L.S. (ed.), Sny
Magill  watershed monitoring project: baseline data. Iowa Department of Natural
Resources, Geological Survey Bureau, Technical Information Series 32, p. 73-89.

Littke, J. P. and G. R. Hallberg. 1991. Big Spring Basin Water Quality Monitoring
Program: Design and Implementation. Open File Report 91-1, Iowa Department of
Natural Resources, Geological Survey Bureau, July, 1991,  19 p.

                    227

-------
                                               i Appendix IV: Project Documents
McKay, R. M. 1993. Selected Aspects of Lower Ordovician and Upper Cambrian
Geology in Allamakee and Northern Clayton Counties, 4/25.

Newbern, D. T. 1991. North Cedar Creek -watershed 1990 annual report.  Soil
Conservation Service, Elkader, IA, 3p.

Newbern, D. T. 1992. North Cedar Creek watershed 1991 annual report.  Soil
Conservation Service, Elkader, IA, 6p.

Newbern, D. T. 1993. North Cedar Creek watershed 1992 annual report.  Soil
Conservation Service, Elkader, IA, 3p.

Newbern, D. T. 1994. North Cedar Creek watershed 1993 annual report.  Soil
Conservation Service, Elkader, IA, 2 p.

Rodecap, J. and K. Bentley. 1994. Northeast Iowa Water Quality Demonstrations: A
Guide to 1994 Project Sites. Pamphlet.

Rolling, N. and K. Bentley. 1994. Integrated Crop Management. Fact Sheet.

Rolling, N. G. Hanson, andK. Bentley. 1994. Manure Management Workshop. Fact
Sheet.

Rowden, R. D., R. D. Libra, and  G.  R. Hallberg. January,  1995. Surface Water
Monitoring in the Big Spring Basin 1986-1992, A Summary Review.

Schueller, M.D., M.W. Birmingham, and ID. Kennedy.  1994. Sny Magill Creek
nonpoint source pollution monitoring project: 1993 benthic biomonitoring results.
University Hygienic Laboratory, Limnology Section, Report No. 94-1, 123 p.

Schueller, M. D., M.  C. Hausler, and J.  O.  Kennedy. 1992. Sny Magill Creek
Nonpoint Source Pollution Monitoring Project: 1991 Benthic Biomonitoring Pilot
Study Results. University of Iowa Hygienic Laboratory, Limnology Section, Report
No. 92-5, 78 p.

Schueller, M. D., M. C. Hausler, and I O. Kennedy. 1994.1991 benthic biomonitor-
ing pilot study  results. In: Seigley, L.S. (ed.), Sny Magill watershed monitoring
project: baseline data. Iowa Department of Natural Resources, Geological Survey
Bureau, Technical Information Series 32, p. 111-123.

Schueller, M. D., M. W. Birmingham, and J. O. Kennedy. 1993. Sny Magill Creek
Nonpoint Source Pollution Monitoring Project: 1992 Benthic Biomonitoring Re-
sults. University of Iowa Hygienic Laboratory, Limnology Section, Report No. 93-2.

Schueller, M. D., M.W. Birmingham,  and J.O. Kennedy. 1996. Sny Magill Creek
Nonpoint Source Pollution Monitoring Project: 1995 Benthic Biomonitoring Re-
sults. University of Iowa Hygienic Laboratory, Limnology Section, Report No. 96-2.

Seigley, L. 1994. Sny Magill Nonpoint Source Monitoring Project  1992  Annual
Report and Disk, 6/14. Report and diskette.

Seigley, L. 1994. Sny Magill Nonpoint Source Pollution Monitoring Project 1992
Annual Report for Water Year 1992, 6/14. Memorandum to Sny Magill Monitoring
Project Cooperators.

Seigley, L. July 6, 1994. Summary of Sny Magill annual meeting held June, 24,
1994.

Seigley, L.S.  1995. Monitoring Update on Sny Magill, Bloody Run Watersheds.
Water Watch, December 1995, p. 3-4.
                   228

-------
                                                i Appendix IV: Project Documents
Seigley, L.S. 1996. Water Sampling of private wells in SnyMagill watershed. Water
Watch, August 1996.

Seigley, L. S. and D. J. Quade. 1992. Northeast Iowa Well Inventory Completed.
Water Watch, December, 1992, p. 2-3.

Seigley, L. S. and G. R. Hallberg. 1994. Monitoring continues on Sny Magill and
Bloody Run Creeks.  Water Watch, No. 48, February, p. 1-2.

Seigley, L. S. and G. R. Hallberg.  1994. Summary of baseline water quality data for
Sny Magill and Bloody Run watersheds and surrounding locations. In: Seigley, L.S.
(ed.), Sny Magill watershed monitoring project: baseline data. Iowa Department of
Natural Resources, Geological Survey Bureau, Technical Information Series 32, p.
43-62.

Seigley, L. S. and G. R. Hallberg. 1994. Water quality of private water supplies in
Sny Magill and Bloody Run watersheds. In: Seigley, L.S. (ed.),  Sny Magill water-
shed monitoring project:  baseline data.  Iowa Department of Natural Resources,
Geological Survey Bureau, Technical Information Series 32, p. 63-72.

Seigley, L. S. and J. J. Wellman. 1993.  Sny Magill Watershed Nonpoint Source
Pollution Monitoring Project: an EPA Section 319 National Monitoring Program
Project. Geological Society of Iowa spring field trip, Stop 8, p. 46-54.

Seigley,L. S.andM.D. Schueller. 1993. Aquatic life and cold-water stream quality.
Iowa Geology, No. 18, Iowa Department of Natural Resources,  Geological Survey
Bureau, p. 22-23.

Seigley, L. S. (ed.). 1994.  Sny Magill watershed monitoring project: baseline data.
Iowa Department of Natural Resources, Geological Survey Bureau, Technical Infor-
mation Series 32, 143 p.

Seigley, L. S., G. R. Hallberg, T. Wilton, M. D. Schueller, M. C. Hausler, J. O.
Kennedy, G. Wunder, R.  V. Link, and S. S.  Brown. 1992. Sny Magill Watershed
Nonpoint Source Pollution Monitoring Project Workplan. Open File Report 92-1,
Iowa Department of Natural Resources, Geological Survey Bureau, August 1992.

Seigley, L. S., G. R. Hallberg, R. D. Rowden, R. D. Libra, J. D. Giglierano, D. I
Quade, and K. O. Mann.  1993. Agricultural landuse and nitrate cycling in surface
water in northeast In: Proceedings, Agricultural Research to Protect Water Quality,
Soil and Water Conservation Society, Ankeny, IA, p. 85-88.

Seigley, L. S., G. R. Hallberg, and J.  Gale. 1993. Shy Magill Watershed (Iowa)
Section 319 National Monitoring Program Project. NWQEP NOTES 58:5-7, North
Carolina State University Water Quality Group, Cooperative Extension Service,
Raleigh, NC.

Seigley, L. S., M. D. Schueller, M. W. Birmingham, G. Wunder, L. Stahl, T. F.
Wilton, G. R. Hallberg, R. D. Libra, and J. O. Kennedy. 1994. Sny Magill Nonpoint
Source Pollution Monitoring Project, Clayton County, Iowa: Water Years 1992 and
1993. Iowa Department of Natural Resources, Geological Survey Bureau, Technical
Information Series 31,103 p.

Seigley, L. S., G. Wunder, S.A. Gritters, T.F. Wilton, IE. May, M.W. Birmingham,
M.D. Schueller, N. Rolling, and J. Tisl. 1996. Sny Magill Nonpoint Source Pollution
Monitoring Project, Clayton County, Iowa: Water Year 1994. Iowa Department of
Natural Resources, Geological Survey Bureau, Technical Information Series 36, 85
P-
                    229

-------
                                                                    i Appendix IV:  Project Documents
                           Siegley, L. 1996. Summary of August 29, 1996 annual SnyMagill meeting.

                           Wittman, C., ed. August 1996. Water Watch: A newsletter for Big Spring Basin, Sny
                           Magill Watershed, and Northeast Iowa Demonstration Project areas. Newsletter,
                           Issue No. 63.

                           Wilton, T. F. 1994. 1991 habitat evaluation results - baseline  information. In:
                           Seigley, L.S. (ed), Sny Magill watershed monitoring project: baseline data. Iowa
                           Department of Natural Resources, Geological Survey Bureau, Technical Informa-
                           tion Series 32, p. 91-110.

                           Wittman, C. 1995. Farm visits are part of Sny Magill project annual meeting. Water
                           Watch, August 1995, p. 1-2.

                           Wunder, G. and S. Gritters. 1995. SnyMagill Creek fishery assessment 1994. Iowa
                           Department of Natural Resources, Fisheries Bureau, 5 p.

                           Wunder, G. and L. Stahl. 1994. 1991 fish assessment for Sny Magill Creek. In:
                           Seigley, L.S. (ed.), Sny Magill watershed monitoring project: baseline data. Iowa
                           Department of Natural Resources, Geological Survey Bureau, Technical Informa-
                           tion Series 32, p. 131- 135.

                           Wunder, G. and L. Stahl. 1994. 1992 fish assessment for Sny Magill Creek and
                           Bloody Run watersheds. In: Seigley, L.S. (ed.), Sny Magill watershed monitoring
                           project: baseline data. Iowa Department of Natural Resources, Geological Survey
                           Bureau, Technical Information Series 32, p. 137-143.


IOWA WALNUT CREEK
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                           Thompson, C.A. J. O. Kennedy, and G.R. Hallberg. 1995. Walnut Creek Watershed
                           Restoration  and Water Quality Monitoring Project Workplan Revision  1. Iowa
                           Department of Natural Resources, Geological Survey Bureau, 20pp.

                           Thompson, C.A. and R. Rowden. 1995. Walnut Creek Watershed Restoration and
                            Water Quality Monitoring Project. Annual Report. Iowa Department of Natural
                           Resources, Geological Survey Bureau. 28pp.


MARYLAND WARNER  CREEK WATERSHED
SECTION 319 NATIONAL  MONITORING  PROGRAM PROJECT


                           Living Resources Targeted Watersheds Project.

                            Final Work Plan, Bird River Watershed Water Quality Management Plan. Work-
                            plan.

                            Cooperators Communications and Audience Involvement Plans.

                            3.2 Living Resources Targeted Watersheds Project, pp. 44-48.

                            Living Resources Targeted Watershed Project.

                            Section II, Cooperators Communications and Audience Involvement Plans.
                                             230

-------
                                              ' Appendix IV: Project Documents
Living Resources Targeted Watershed Project.

1989. Sawmill Creek: Aquatic Resource Assessment and Water Monitoring Plan,
May.

1990. Aquatic Resource Assessment and Monitoring Plan: Targeted Watershed
Project Monitoring Team, April.

1990. Water Quality Demonstration Project, Monocacy River Watershed.

1990. Piney and Alloway Creeks—Aquatic Resource Assessment and Monitoring
Plan,  October.

State  of Maryland. 1991. State of Maryland Grant Application for Section 319
Federal FY 91 Funding—Appendices to  Work Plans, 5/31 (1989 National Water
Quality Special Project Request—Piney/Alloway Creek Project).

German Branch Water Quality Hydrologic Unit Area. 1991. German Branch Water
Quality Hydrologic Unit Area, Queen Anne's County, Maryland, FY 91 Plan of
Operations, 2/15.

Monocacy Watershed. 1991. RegionalMonitoringSet-Aside Grant Proposal, Monocacy
Watershed.

Monocacy Watershed. 1991. Monocacy  Watershed Demonstration Work Plan—
Supplemental Information on the Project Titled Modeling the Hydrologic and Water
Quality Response of the Mixed Land Use Basin, 12/30.

1991. Restoration Plan for Sawmill Creek Watershed (draft).

Mononcacy Watershed. 1991. Mononcacy Watershed Demonstration Project En-
courages Adoption of Agricultural Management Practices. In: EPA News-Notes,
#16.

Thoma, R. 1991.  Comments 8/29.

1992. Forestry Project Assists in Improving Water Quality in the Monocacy River
Watershed.  In: EPA News-Notes, #18.

1993. QAPJP Supplemental: Response to EPA Region Ill's Request Dated June 16,
1992. Revised January 25, 1993.

Dressing, S. A. 1991. Summary of EPA-Headquarters Review Comments, 8/13.

Dressing, S. A. 1991. Summary of EPA-Headquarters Review Comments, 8/8.

Dressing, S. A. 1993. Review of Proposal for Section 319 National Monitoring
Program.

Shirmohammadi, A. 1994. Project Information, 6/29. Memorandum from. A.  Shir-
mohammadi to D. Osmond.

Shirmohammadi, A. and W. L. Magette. 1993. Background Data and Revision to
the Monitoring Design for the Project Titled "Modeling the Hydrologic and Water
Quality Response of Mixed Land Use Basin."

Shirmohammadi, A. and W. L. Magette. 1993. Modeling the Hydrologic and Water
Quality Response of the Mixed Land Use Basin: Background Data and Revision to
the Monitoring Design.
                   231

-------
                                             i Appendix IV: Project Documents
Shirmohammadi, A. and W. L. Magette. 1994. FY1991 Annual Report on "Model-
ing and Monitoring the Hydrologic and Water Quality Response of the Mixed Land
Use Basin."

Shirmohammadi, A. and W. L. Magette.  1994. Work Plan for Monitoring and
Modeling Water Quality Response of the Mixed Land Use Basin.

Shirmohammadi, A. and W. L. Magette.  1994. Work Plan for Monitoring and
Modeling Water Quality Response of the Mixed Land Use Basin: FY 91 Annual
Report.

Shirmohammadi, A., W.L. Magette, andD.E. Line. 1994. Warner Creek Watershed
(Maryland) Section 319 Project. NWQEP NOTES 68:1-3. North Carolina State
University Water Quality Group, North Carolina Cooperative Extension Service,
Raleigh, NC.

Shirmohammadi, A. W. L. Magette, R. A. Weismiller, J. McCoy, and R. James.
1994. Monocacy River Watershed Initiative: Monitoring  and Modeling Water
Quality Response of the Mixed Land Use Basin, 6/23. Proposal.

A. Shirmohammadi and W.L. Magette. 1994. Modeling and Monitoring the Hydro-
logic and Water Quality Response  of the Mixed Land Use Basin: FY 1991 Annual
Report, 3/21. Report.

Shirmohammadi, A.  and W. L. Magette. 1992.  Supplemental Information on
QAPJP for Maryland's 319 Project Plan on Modeling the Hydrologic and Water
Quality Response of the Mixed Land Use Basin.

Shirmohammadi, A. and W. L. Magette. 1993. Quality and Assurance and Quality
Control Plan for the Project Titled "Modeling the Hydrologic and Water Quality
Response of the Mixed Land Use Basin."

Shirmohammadi, A. and W. L. Magette. 1993. Monocacy Watershed Demonstra-
tion Work Plan: Revised Workplan Information of the Project Titled "Modeling the
Hydrologic and Water Quality Response of the Mixed Land Use Basin."

Shirmohammadi, A.  and W. L.  Magette. 1993.  Supplemental Information on
QAPJP for Maryland's 319 Project Plan on "Modeling the Hydrologic and Water
Quality Response of the Mixed Land Use Basin" (Revised).

Shirmohammadi, A., K.S. Yoon, and W.L. Magette. 1996.  Status of Section 319
National Monitoring Project:  Water  Quality in a Mixed Land Use  Watershed-
Piedmont Region in Maryland. ASAE Presentation, Phoenix Civic Plaza, July 14-
18, 1996. ASAE Paper No. 96-2085.

Shirmohammadi, A., K.S. Yoon, and W.L. Magette. 1996. Water Quality in aMixed
Land Use Watershed-Piedmont Region. J. Environ. Sci. Health,  A31(2), 429-450.

Thoma, R. 1991. Region III Section 319 National Monitoring Program Proposal
Recommendations,  to Hank Zygmunt, 8/29.
                    232

-------
                                                                      i Appendix IV: Project Documents
MICHIGAN SYCAMORE CREEK WATERSHED
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                            Michigan Department of Environmental Quality. 1996. Surface Water Quality
                            Division Staff Report.

                            1989. Biological Investigation of Sycamore Creek and Tributaries, May-August.

                            1990. A Biological Investigation of Sycamore Creek and Tributaries, Ingham
                            County, Michigan, May -August, 1989. Michigan Department of Natural Resourc-
                            es.

                            January, 1990. Sycamore Creek Watershed Water Quality Plan. Soil Conservation
                            Service, Michigan Cooperative Extension Service, Agricultural Stabilization and
                            Conservation Service.

                            1992. Summary of EPA-Headquarters Review Comments, 6/5.

                            1992. Remaining Issues, 12/8.

                            1992. 1992 Section 319 Set-Aside.

                            1992. Revisions for Sycamore Creek, MI.

                            1992. Memo Response to Steve Dressing, 12/8. Memorandum.

                            1992. Annual Progress Report: Sycamore Creek Water Quality Program: Fiscal
                            Year 1992. Sycamore Creek Water Quality Program.

                            1992. Sycamore Creek Watershed Monitoring Program: FY-92.

                            1992. Revisions for the Sycamore Creek Watershed National Monitoring Project.

                            1992. Correspondence, 3/23.

                            1992. The Sycamore Creek Water Quality Program: A Model for the State TMDL
                            Case Study, Sycamore Creek,  EPA841-F-92-012.

                            1992. TMDL Case Study: Sycamore Creek, EPA 841-F-92-012, number 1.

                            1993. EPA Approval, 2/11.

                            Spring 1994. A Local, State and Federal Cooperative Effort to Restore and Protect
                            the Saginaw Bay Watershed.

                            Allen., D. 1993. Michigan's Response to Steve Dressing's 9/8/92 Memo Regarding
                            the Sycamore Creek Monitoring Plan. Letter.

                            Dressing, S. A. 1992. Sycamore Creek, MI—Remaining Issues. Fax transmittal.

                            Dressing, S.  A. 1992.  Review of Proposal for  Section 319 National Monitoring
                            Program.

                            Dressing, S. A. 1993. Approval of Sycamore  Creek, Michigan as National Monitor-
                            ing Project. Memorandum.

                            F.T.C.H. 1996.  Willow Creek Drain Final Report for 319 Implementation Project.
                             Ingham County Drain Commission.
                                              233

-------
                                                                        i Appendix IV: Project Documents
                             Shaffer, M. I, M. K. Brodahl, and B. K. Wylie. 1993. Integration and Use of the
                             Nitrate Leaching and Economic Analysis Package (NLEAP) in the GIS Environ-
                             ment. In: Proceedings of the Federal Inter agency Workshop on Hydrologic Model-
                             ing for the 90 's,  USGS Water Resources Investigations Report 93-4018.

                             Suppnick, J. D.  1993.  Sycamore Creek 319 Monitoring Grant Annual Report.
                             Michigan Department of Natural Resources, Surface Water Quality Division.

                             Suppnick, J. D. 1993. A Status Report on Michigan's Comprehensive Water Quality
                             Plan for Sycamore Creek. In: WATERSHED  '93 Proceedings: A National Confer-
                             ence on Watershed Management. EPA 840- R-94-002.

                             Suppnick, J. D.  and D. L. Osmond. 1993. Sycamore Creek Watershed, Michigan,
                             319 National Monitoring Program Project. NWQEP NOTES 61:5-6, North Carolina
                             State University Water Quality Group, North Carolina Cooperative Extension
                             Service, Raleigh, NC.

                             Suppnick, J. D.  1992. A Nonpoint Source Pollution Load Allocation for Sycamore
                             Creek, in Ingham County, In: The Proceedings of the WEF 65th Annual Conference,
                             Surface Water Quality Symposia, September 20-24,1992, New Orleans, p. 293-302.

                             Velleux, M. L.,  J. E. Rathbun, R. G. Kreis Jr, J. L. Martin, M. J. Mac, and M. L.
                             Tuchman. 1993. Investigation of Contaminant Transport from the Saginaw Con-
                             fined Disposal Facility. From"J. Great Lakes Res." 19(1): 158-174.


NEBRASKA ELM CREEK WATERSHED
SECTION 319 NATIONAL  MONITORING  PROGRAM PROJECT


                             Proposal.

                             Investigations of the Water Quality and Water Quality Related Beneficial Uses of
                             Elm Creek, NE. Elm Creek Project.

                             September, 1991a. Title 117-Nebraska Surface Water Quality Standards. Nebraska
                             Department of Environmental Control, Lincoln,

                             April, 1988. Surface Water Quality Monitoring Strategy. Surface Water Section,
                             Water Quality Division, Nebraska Department of Environmental Control, Lincoln,

                             1991. Summary of EPA-Headquarters Review Comments, 5/29.

                             1991. Proposal, October. Elm Creek Project.

                             1991. EPA-Headquarters Review Comments 8/27 and 5/29. Elm Creek Project.

                             1991. Elm Creek Water Quality Treatment Plan, 9/12. Elm Creek Project.

                             1991. Elm Creek Project, Annual Progress Report: FY91. Elm Creek Project.

                             1991.  Elm  Creek Watershed Section 319 Nonpoint Source Project: Overview and
                             Workplan. Lower Republican Natural Resource District, Nebraska Department of
                             Environmental Control, Soil Conservation Service, Nebraska Game and Park Com-
                             mission, Cooperative Extension Service, Lincoln, NE.

                             1991b. Nebraska Stream Inventory.  Surface Water Quality Division, Nebraska
                             Department of Environmental Control, Lincoln, Nebraska (Draft).
                                               234

-------
                                                                        ' Appendix IV: Project Documents
                             1992. Elm Creek Project, Annual Progress Report: FY 92. Elm Creek Project.

                             1992. Elm Creek Watershed Section 319 Nonpoint Source Project:  Monitoring
                             Project Plan. Nebraska Department of Environmental Control, Lincoln, Nebraska.

                             1992. Procedure Manual. Surface Water Section, Water Quality Division, Nebraska
                             Department of Environmental Control, Lincoln, Revised and Updated April, 1992.

                             1993. Elm Creek Project, Annual Progress Report: FY 93. Elm Creek Project.

                             1994. Elm Creek Project: Project Extension Request, 2/23. Elm Creek Project.

                             1994. Elm Creek HUA Field Tour Informational Packet and Handouts. Elm Creek
                             Project.

                             1994. Elm Creek Project, Annual Progress Report: FY 94. Elm Creek Project.

                             1995. Elm Creek Project, Annual Progress Report: FY95. Elm Creek Project.

                             Dressing, S. A. 1991. Review of Proposal for Section 319 National Monitoring
                             Program (Elm Creek, NE), 10/16.

                             Jensen, D. and C. Christiansen. 1983. Investigations of the Water Quality and Water
                             Quality Related Beneficial Uses of Elm Creek, Nebraska Department of Environ-
                             mental Control, Lincoln, Nebraska.

                             Jensen, D. G. Michl, and D. L. Osmond. 1993. Elm Creek Watershed, Nebraska,
                             Section 319 National Monitoring Program Project. NWQEP NOTES 60:4-6, North
                             Carolina State University Water Quality Group, North Carolina Cooperative Exten-
                             sion Service, Raleigh, NC.

                             Moreland, R. E., K. R. Bolen, and F. Johannsen. Feb. 23,1995. Elm Creek Hydrolog-
                             ic Unit Area Annual Progress Report.

                             Thoma, R.  1991. Nebraska Elm Creek Study, Monitoring Project Plan, 10/31.
                             Memorandum from Roger Thoma to Steve Dressing.

                             USEPA.  1991. Watershed Monitoring and Reporting for Section 319 National
                             Monitoring Program Projects.

                             Young, R A., C. A. Onstad, D. D. Bosch, and  W. P. Anderson. 1987. AGNPS,
                             Agricultural Non-Point Source Pollution Model: A Watershed Analysis Tool. U.S.
                             Department of Agricultural, Conservation Research Report 35, 80 p.


NORTH CAROLINA LONG CREEK WATERSHED
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT
                             Long Creek Watershed Project Kickoff Luncheon.

                             1992. Summary of EPA-Headquarters Review Comments, 3/12.

                             Danielson, L. E., L. S. Smutko, and G. D. Jennings. 1991. An Assessment of Air,
                             Surface Water, and Groundwater Quality in Gaston Comity, North Carolina. In:
                             Proceedings of the National Conference on Integrated Water Information Manage-
                             ment. USEPA, Office of Water, Washington, DC. p. 101-107.

                             Dressing, S. A. 1993. Potential Problems. Memorandum.
                                              235

-------
                                               i Appendix IV: Project Documents
Jennings, G. D. 1992. Appendix 4-Ground Water Analysis, p. 4.1-4.7. In: Natural
Resource Quality in Gaston County. Phase 2: Implementation of Natural Resource
Education and Policy Development Programs-Final Report. North Carolina Coop-
erative Extension Service, North Carolina State University, Raleigh, NC. 181 pp.

Jennings, G. D., D. E. Line, S. W. Coffey, J. Spooner, W. A. Harman, and M. A.
Burris. 1994. Nonpoint Source control in the Long Creek EPA National Monitoring
Project. ASAE Paper 942187. Am. Soc. Ag. Eng., St. Joseph, MI.

Jennings, G. D., D. E. Line, S. W. Coffey, J. Spooner, N. M. White, W. A. Harman,
and M. A. Burris. 1995. Water  quality and land treatment in the Long Creek
Watershed Project. In: Proceedings of the Clean Water - Clean Environment - 21st
Century Conference, Am. Soc. Ag. Eng., St. Joseph, MI.

Jennings, G. D., D. E. Line, S. W. Coffey, J. Spooner, N. M. White, W. A. Harman,
and M. A. Burris. 1995. Long  Creek Watershed Nonpoint Source Monitoring
Project. Poster presentation at the National Nonpoint Source Forum, Arlington, VA.

Jennings, G. D., W. A. Harman, M. A. Burns, and F. J. Humenik. March, 1992. Long
Creek Watershed Nonpoint Source Water Quality Monitoring Project Proposal.
With letters from processing agencies.

Jennings, G. D., W. A. Harman, M. A. Burris, and F. J. Humenik. June, 1992. Long
Creek Watershed Nonpoint Source Water Quality Monitoring Project Proposal
(Revision). North Carolina Cooperative Extension Service, Raleigh, NC, 21p.

Levi,  M. D. Adams, V. P. Aneja, L. Danielson, H. Devine, T.  J. Hoban,  S. L.
Brichford, M. D. Smolen. 1990. Natural Resource Quality in Gaston County -
Phase 1: Characterization of Air, Surface Water and Groundwater Quality - Final
Report.  North Carolina Agricultural Extension Service, North Carolina State Uni-
versity, Raleigh, NC. 174 p.

Levi,  M. G. Jennings,  D. E. Line, S. W. Coffey, L. S. Smutko, L. Danielson, S. S.
Qian, H. A. Devine, T. J. Hoban, V.  P. Aneja. 1992. Natural Resource Quality in
Gaston  County - Phase 2: Implementation  of Natural Resource Education and
Policy Development Programs - Final Report. North Carolina Cooperative Exten-
sion Service, North Carolina State University, Raleigh, NC. 181 p.

Line, D. E. 1993. Long Creek, North Carolina National 319 Monitoring Program
Project. NWQEP NOTES 59:4-6, North Carolina State University Water Quality
Group, North Carolina Cooperative Extension Service, Raleigh, NC.

Line, D. E. and S. W. Coffey. 1992. Targeting Critical Areas with Pollutant Runoff
Models and GIS. ASAE Paper No. 92-2015.  American Society of Agricultural
Engineers, St. Joseph, MI. 21 p.

Qian, S. S. 1992. Appendix 5-Confirmation of SWRRBWQ for Long Creek Water-
shed, 44pp. In: Natural Resource Quality in Gaston County. Phase 2: Implementa-
tion of Natural Resource Education  and  Policy Development Programs-Final
Report. North Carolina Cooperative Extension Service, North Carolina State Uni-
versity, Raleigh, NC. 112 pp.

Smolen, M. D.,  S. L. Brichford, W. Cooter, and L. Danielson.  1990. Appendix 4-
Water Quality, p. 4.11-4.96. In: Natural Resource Quality in Gaston County. Phase
1: Characterization of Air, Surface Water, and Groundwater  Quality-Final Report.
North Carolina Agricultural Extension Service, North Carolina  State University,
Raleigh, NC.
                    236

-------
                                                                          ' Appendix IV: Project Documents
                              Smutko, L. S., L. E. Danielson, and W.  A. Harman. 1992. Integration  of a
                              Geographic Information System in Extension Public Policy Education: A North
                              Carolina Pilot Program. In: Computers in Agricultural Extension Programs,  Pro-
                              ceedings of the Fourth International Conference. Florida Cooperative Extension
                              Service, University of Florida, Gainesville, FL. p. 658-663.

                              Smutko, L. S., L. E. Danielson, J. M. McManus, and H. A. Devine. 1992. Use of
                              Geographic Information System Technology in Delineating Wellhead Protection
                              Areas. In: Proceedings of the National Symposium on the Future Availability of
                              Ground Water Resources. American Water Resources Association, Bethesda,  MD.
                              p. 375-380.

                              White, N. M., D. E. Line, C. Stallings, and G. D. Jennings. 1995. GIS Procedures for
                              the spatial analysis of fecal coliform bacteria ecology, Phase I: Land form model
                              development. In: Proceedings of the ASAE International Water Quality Modeling
                              Conference. Am. Soc. Agr. Eng., St. Joseph, MI.

                              White, N. M., G. D. Jennings, and W. A. Harman. 1994. Ecological modeling of
                              riparian systems using a GIS: Data needs and processing. In: Computers in Agricul-
                              ture 1994: Proceedings of the Fifth International Conference. ASAE Pub. No. 03-
                              94, Am. Soc. Agr. Eng., St. Joseph, MI.

                              Line, D. E. 1992. Gaston County Water Quality Assessment. NWQEP NOTES, 54:3-
                              4, North Carolina State University Water Quality Group, North Carolina Coopera-
                              tive Extension Service, Raleigh, NC.

                              Line, D. E., S. W. Coffey, and S. S. Qian. 1992. Appendix 2-Surface Water Quality
                              Assessment, p. 2.1-2.35. In: Natural Resource Quality in Gaston County. Phase 2:
                              Implementation of Natural Resource Education and Policy Development Programs-
                              Final Report. North Carolina Cooperative Extension Service, North Carolina State
                              University, Raleigh, NC. 181 pp.


OKLAHOMA PEACHEATER CREEK
SECTION 319 NATIONAL MONITORING  PROGRAM PROJECT


                              1992. Second Workplan dated July 1992: FY-1992 Section 319 Work Program.
                              Workplan.

                              1993. Illinois River Watershed Monitoring Program. FromNonpoint Source Water-
                              shed Project Workshop, Gastonia and Charlotte, NC.

                              1993. Third Workplan Dated March 1993, Monitoring of 319 Project Watersheds
                              and Matched Pairs: Illinois River, OK.

                              1993. Monitoring of 319 Project Watersheds and Matched Pairs: Fourth Workplan
                              Dated May 1993. Workplan.

                              1993. FY-1992 Section 319 Work Program,  Illinois River Watershed Monitoring
                              Program: Monitoring of 319 Project Watersheds and Matched Pairs.

                              1993. FY1992 Section 319 Work Program for the Illinois River Watershed Monitor-
                              ing Program: Final Workplan, 5/11. Workplan and letters.

                              March 5,1993. Illinois River Watershed Monitoring Program. FY 1992 Section 319
                              Work Program for review.
                                               237

-------
                                               i Appendix IV: Project Documents
1994. FY1992 Section 319 Work Program for the IllinoisRiver Watershed Monitor-
ing Program: Approved Workplan, Revised 6/8. Workplan and letters.

June 8, 1994. Illinois River Watershed Monitoring Program.

1995. Quality Assurance Project Plan, approved October 20,1995. Oklahoma State
University, Stillwater, Oklahoma.

Dressing,  S.  1993.  Review of Proposal for Section  319 National Monitoring
Program, 4/13.

Dressing,  S.  1993.  Review of Proposal for Section  319 National Monitoring
Program, 7/20.

Dressing,  S.  1994.  Review of Proposal for Section  319 National Monitoring
Program, 7/13.

Dressing,  S. A. 1993. Review  of Proposal for Section 319 National Monitoring
Program: Illinois River Watershed, OK.

Dressing,  S. A. 1993. Headquarters Review of Proposal for Section 319 National
Monitoring Program: Review of March 1993 Workplan.

Dressing,  S. A. 1993. Review  of Proposal for Section 319 National Monitoring
Program: Headquarters Review of May 1993 Workplan.

Dressing,  S. A. 1993. Review  of Proposal for Section 319 National Monitoring
Program (IllinoisRiver), 1/25. Fax Transmittal to Wes McQuiddy.

Dressing,  Steve. April 13,  1993. Review of Proposal for Section  319 National
Monitoring Program.

Dressing,  Steve. July 20,  1993. Review of Proposal for  Section  319 National
Monitoring Program.

Dressing,  Steve. July 13,  1994. Review of Proposal for  Section  319 National
Monitoring Program, review of proposal.

Hassell, J. May 11, 1993. IllinoisRiver Watershed Monitoring Program, work plan
to be reviewed.

Hassell, J. June 8, 1994. IllinoisRiver Watershed Monitoring Program, review.

Knudson, M. O. 1993. Region  VI Approval Letter of May 1993 Workplan.  Letter.

McQuiddy, W. 1992. FY-1992 Section  319 Work Program: FY-92 319(h)  Work-
plan—Pollution Control Coordinating Board, Oklahoma Department of Pollution
Control, July. Fax Transmittal to Steve Dressing, 11/25/92.

Moershel, P. and S.  Coffey.  1996.  Peacheater Creek (Oklahoma) Section 319
National Monitoring Program Project, NWQEP NOTES 78:1-3.
                    238

-------
                                                                 ' Appendix IV: Project Documents
OREGON UPPER GRANDE RONDE BASIN

SECTION 319 PROJECT (Pending Section 319 National
Monitoring Program Project Approval)


                          Bach, L.B. 1995 River Basin Assessment: Upper/Middle Grande Ronde River and
                          Catherine Creek. Oregon Department of Environmental Quality and Oregon Water-
                          shed Health Program.

                          Hafele, R. 1996. National Monitoring Program Project Description and Prelimi-
                          nary Results for the Upper Grande Ronde River Nonpoint Source Study - Draft.
                          Oregon Department of Environmental Quality.

                          Kimmerling, A.J. and P.L. Jackson. 1985. Atlas of the Pacific Northwest (7th
                          edition). Oregon State University Press.

                          ODEQ. 1995. Proposal: Restoration of Stream Habitat in Grande Ronde Model
                          Watershed, Maclntyre and McCoy Creeks, Union County, Oregon. Oregon Depart-
                          ment of Environmental Quality.

                          Omernick, J.M. 1987. Ecoregions of the conterminous United States. Annals of the
                          Association of American Geographers 77:188-125.


PENNSYLVANIA PEQUEA  AND MILL  CREEK WATERSHED

SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                          Evaluation of Agricultural Best-Management Practices in the Conestoga River
                          Headwaters, PA. In: Water-Resources Investigations Report 90-4231.

                          1991. Work Plan for Characterizing Baseline Water Quality, and Evaluating the
                          Cause/Effect Relations of the Implementation of Agricultural Management Practic-
                          es on Surface- and Ground-Water Quality in the Mill Creek, May. Workplan.

                          1991. Summary of EPA-Headquarters Review Comments, 8/14.

                          Thoma, R. 1991. Comments 8/29.

                          Reichgott, T. 1992. Memo to S. Dressing, 6/11. Memorandum.

                          1992. Detailed Workplan, 6/2. Workplan.

                          1993. Project Application, 7/14.

                          1993. Approval ofPequea and Mill Creek Watersheds, 7/30.

                          1993. Draft Workplan, 1/15. Workplan.

                          1993. Pequea and Mill Creek Watershed Project Proposal. U.S. Geological Survey.

                          Beegle, D., L.E. Lanyon,  and D.D. Lingenfelter. 1996. Nutrient Management
                          Legislation in Pennsylvania: A Summary. Perm State College  of Agricultural
                          Sciences, Cooperative Extension, Agronomy Facts 40. 7 p.

                          Leitman, P. L. Evaluating Effects of Selected Agricultural-Management Practices
                          on Surface- and Ground-Water Quality  in the Pequea and Mill Creek Watersheds,
                          Lancaster and Chester Counties.
                                          239

-------
                                                                        i Appendix IV: Project Documents
                             Line, D. E. 1994. Pequea and Mill Creek Watershed Section 319 National Monitor-
                             ing Program Project. NWQEP NOTES 65:3-4, North Carolina State University
                             Water Quality Group, North Carolina Cooperative Extension Service, Raleigh, NC.

                             Martin, G.L. and L.E. Lanyon. 1995. Nutrient Management Planner Survey. Perm
                             State Cooperative Extension, Pequea-Mill Creek Project, Smoketown, PA. Pequea-
                             Mill Creek Information Series 25. 6 p.


VERMONT LAKE CHAM PLAIN WATERSHED
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                             Long-term Monitoring Projects, Memorandum from Bob Morehouse to Steve Dress-
                             ing.

                             1991.  St. Alban's Bay Rural Clean Water Program  Final Report,  1980-  1990.
                             Vermont RCWP Coordinating Committee, Vermont Water  Resources Research
                             Center, University of Vermont, Burlington, VT.

                             1992. EPA Review of Proposal 7/8.

                             March, 1992. Lake Champlain Agricultural Watersheds BMP Implementation and
                             Effectiveness Monitoring Project.

                             1993. EPA Review of the Lake Champlain Project, 5/26.

                             1993.  Clean Water Act Section 319 Nonpoint Source Project Summary: Lake
                             Champlain Agricultural Watersheds BMP Implementation and Effectiveness Moni-
                             toring Project (Draft).

                             1993. EPA-HQ Informational Needs for Lake Champlain Section 319 NFS Monitor-
                             ing Project.

                             May,  1993.  State of Vermont: Lake Champlain Agricultural Watersheds BMP
                             Implementation and Effectiveness Monitoring Project: Section 319 National Mon-
                             itoring Program.

                             1994. State of Vermont 1994 Water Quality Assessment,  305(b) Report. Vermont
                             Agency of Natural Resources, Department of Environmental Conservation, Water
                             Quality Division, Waterbury.

                             Budd, L. and D. W.  Meals. 1994. Lake Champlain Nonpoint Source Pollution
                             Assessment. Technical Report No. 6, Lake Champlain Basin Program, Grand Isle,

                             Clausen, J. C. andD. W. Meals. 1989. Water Quality Achievable with Agricultural
                             Best Management Practices. J. Soil and Water Cons. 44: 594-596.

                             Dressing, S. A. 1993. Approval of Lake Champlain, VT as  National Monitoring
                             Project. Memorandum.

                             Meals, D. W. 1990.  LaPlatte River Watershed Water Quality Monitoring  and
                             Analysis Program Comprehensive Final Report. Program Report No. 12, Vermont
                             Water Resources Research Center, University of Vermont, Burlington.

                             Meals, D.W. and D.L. Osmond. 1995.  Lake Champlain Basin Watersheds (Ver-
                             mont) Section319 National Monitoring Program Project. NWQEP NOTES 74:1-3.
                                                240

-------
                                                                         ' Appendix IV: Project Documents
                             Omernik, J. M. 1977. Nonpoint Source Stream Nutrient Level Relationship: A
                             Nationwide Study.  U.S. Environmental Protection Agency, Washington, DC, EPA-
                             600/3-77-105.

                             PLUARG. 1978. Environmental Management Strategy for the Great Lakes System.
                             Final Report to the International Joint Commission from the International Reference
                             Group on Great Lakes Pollution from Land Use Activities, Windsor, Ontario,
                             Canada.
WASHINGTON TOTTEN AND ELD INLET

SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                             1991. Review ofKamm Slough Proposal, 10/29.

                             1992. Draft Quality Assurance Project Plan for Washington State, 10/20.

                             Cleland, B.  1992. Review of Plan for Washington's National NFS Monitoring
                             Project (Puget Sound, WA), 11/6. Fax Transmittal to Keith Seiders.

                             Dressing, S. A. 1992. Review of Proposal for Section 319 National Monitoring
                             Program (Puget Sound, WA), 11/18. Fax Transmittal to Keith Seiders 11/18/92 and
                             Elbert Moore 11/20/92.

                             Seiders, K. 1991. 1988-1989 Data from the Kamm Slough Watershed Study, 11/4.
                             Fax Transmittal to Steve Dressing.

                             Seiders, K. 1991. Proposed Quality Assurance Project Plan for Kamm Watershed
                             BMP Evaluation Project, Environmental Investigations and Laboratory Services
                             Program Watershed Assessments Section, 9/26. Memorandum to Will Kendra.

                             Seiders, K. 1994. Screening Study Results and Quality Assurance Project Plan for
                             the National Monitoring Program in  Washington State (draft).

                             Seiders, K. 1994. Screening Study Results and Quality Assurance Project Plan for
                             the National Monitoring Program in  Washington State (Draft).

                             Seiders, K. Jan. 18, 1995. Screening Study Results and Final Quality Assurance
                             Project Plan.

                             Seiders, K. and J.B. Mullens. 1995. Tbtten and Eld Inlet (Washington) Section 319
                             National Monitoring Program Project. NWQEP NOTES 73:1-3, North Carolina
                             State University Water  Quality Group, North Carolina Cooperative Extension
                             Service, Raleigh, NC.

                             Seiders, K. andRJF. Cusimano. 1996. Totten and Eld Inlets Clean Water Projects:
                             Annual Report.
                                              241

-------
                                                                        i Appendix IV: Project Documents
WISCONSIN OTTER CREEK
SECTION 319 NATIONAL MONITORING PROGRAM PROJECT


                             Stuntebeck, T.D. 1995. Evaluating Barnyard Best Management Practices in Wis-
                             consin using Upstream-Downstream Monitoring. USGS Fact Sheet FS-221-95.

                             Wierl, J. A. K.F. Rappold, F.U. Amerson. 1996. Summary of the Land-Use Inventory
                             for the Nonpoint-Source Evaluation Monitoring Watersheds in Wisconsin. USGS
                             Open-File Report 96-123.

                             A Nonpoint Source Control Plan for the Sheboygan River Watershed.

                             1993. Otter Creek Evaluation Monitoring Program (Revised).

                             Bannerman, R. 1993.  Section 319  National Monitoring Proposal—Otter Creek
                             Evaluation Monitoring Project, 6/12 and Revised 6/15. Memorandum  to Steve
                             Dressing.

                             1993. Fields & Streams. April, Newsletter.

                             1993. Otter Creek Evaluation Monitoring Project. Wisconsin Department of Natu-
                             ral Resources, Bureau of Water Resources Management, Nonpoint  Sources and
                             Land Management Section, Madison, 27 p.

                             1993. Nonpoint Source Control Plan for the Sheboygan River Priority Watershed
                             Project. Wisconsin Department of Natural Resources, Bureau of Water Resources
                             Management, Nonpoint Sources and Land Management Section, Madison, 227 p.

                             1994. Section 319 National Monitoring Program Proposal: Lincoln Creek Evalua-
                             tion Monitoring Project.

                             Finlayson, C., ed. Dec. 1994. Farmstead Pollution Prevention Update.

                             Finlayson, C., ed. Oct.  1995. Farm and Home Pollution Prevention Update.
                             Newsletter about Voluntary Assessments for Water Pollution Prevention.  6p.

                             Finlayson, C., ed. Dec.  1995. Farm and Home Pollution Prevention Update.
                             Newsletter about Voluntary Assessments for Water Pollution Prevention. 6p.

                             Finlayson, C., ed. March 1996. Farm and Home Pollution Prevention Update.
                             Newsletter about Voluntary Assessments for Water Pollution Prevention. 8p.

                             Baker, B. 1992. Section 319 National Monitoring Program Proposal, 3 pp., 9/16.
                             Memorandum to Tom Davenport.

                             Baker, B. 1992. Section 319 National Monitoring Program Proposal,  9 p., 2/4.
                             Memorandum to Tom Davenport.

                             Bannerman, R. and M. Miller. 1995. Otter Creek (Wisconsin) Section 319 National
                             Monitoring Program Project. NWQEP NOTES 69:2-4, North Carolina State Univer-
                             sity Water Quality Group, North Carolina Cooperative Extension Service, Raleigh,
                             NC.

                             Besadny, C.  D. 1992. Grant Application for Section 319 National Monitoring
                             Program, 20 p., 9/29. Memorandum to Valdus Adamkus.
                                                242

-------
                                               «Appendix IV: Project Documents
Dressing, S. A. 1992. Review of Proposal for Section 319 National Monitoring
Program.

Dressing, S. A. 1993. Review of Proposal for Section 319 National Monitoring
Program.

Dressing, S. A. 1993. Review of Proposal for Section 319 National Monitoring
Program (Revised).

Dressing, S. A. 1993. Approval of Otter Creek, Wisconsin as National Monitoring
Project. Memorandum.

Dressing, S. A. 1993. Review of Proposal for Section 319 National Monitoring
Program (Bower Creek), 2/12. Fax Transmittal by Steve Dressing to Tom Daven-
port.

Dressing, S. A. 1993. Review of Proposal for Section 319 National Monitoring
Program (Eagle Creek and Joos Valley Creek), 2/12. Fax Transmittal from Steve
Dressing to Tom Davenport.

ffilsenhoff, W. L. 1982. Using a Biotic Index to Evaluate Water Quality in Streams.
Wisconsin Department of Natural Resources, Technical Bulletin No. 132, Madison,
WI. 22p.

Hilsenhoff, W. L. 1987. An improved Biotic Index of organic stream pollution. The
Great Lakes Entomologist, p. 31-39.

Lyons, J. 1992. Using the Index of Biotic Integrity (IBI) to Measure the Environmen-
tal Quality  of Warmwater Streams in  U.S. Department  of Agriculture, Forest
Service, North Central Forest Experiment Station, General Technical Report NC-
149. 51 p.

Nevers, L. March 1995. Farm and Home Pollution and Prevention Update.

Simonson, T. D., J. Lyons, and P. D. Kanehl. 1994. Guidelines for Evaluating Fish
Habitat in Wisconsin Streams. U.S. Department of Agriculture, Forest Service,
North Central Forest Experiment Station, General Technical Report NC-164. 36 p.

Stuntebeck, T.D. 1995. Evaluating Barnyard Best Management Practices in Wis-
consin using Upstream-Downstream Monitoring. U.S. Department of the Interior,
U.S. Geological Survey, Fact Sheet FS-221-95. 4p.

Wierl, J.A., K.F. Rappold, and F.U. Amerson. 1996. Summary of the Land-Use
Inventory for the Nonpoint-Source Evaluation Monitoring Watershed in Wisconsin.
U.S. Geological Survey Open-File Report 96-123, in cooperation with the Wiscon-
sin Department of Natural Resources, 23 p.
                    243

-------
                              Appendix IV: Project Documents
244

-------
                        Appendix V

               Matrix for Section 319
National Monitoring Program Projects
    245

-------
PROJECT
Alabama:
Lightwood Knot Creek
Arizona:
Oak Creek Canyon
California:
Morro Bay Watershed
Connecticut:
Jordan Cove Urban
Watershed
Idaho:
Eastern Snake
River Plain
Illinois:
Lake Pittsfield
Iowa:
Sny Magill Watershed
Iowa:
Walnut Creek
Maryland:
Warner Creek
Watershed
Michigan:
Sycamore Creek
Watershed
BASIN
SIZE
74
sq. miles
9
sq. miles
76
sq. miles
less than
1 sq. mile
9,600
sq. miles
(aquifer)
11
sq. miles
36
sq. miles
45
sq. miles
1
sq. miles
106
sq. miles
DESIGNATED
BENEFICIAL USES
'Recreation
»Aquatic life support
'Recreation (primary contact)
'Aquatic life support
'Drinking water supply
'Endangered species habitat
'Shellfish harvesting
'Recreation
(primary and secondary contact)
'Esturine and fresh water habitat
'Shellfish harvesting
'Drinking water supply
(ground water)
'Drinking water supply
'Recreation
(primary and secondary contact)
'Aquatic life support ("put and
take" recreational trout fishing)
'Aquatic life support
'Aquatic life support
'Aquatic life support
'Recreation (primary contact)
WATER QUALITY
PROBLEM
'Sediment
'Nutrients
'Bacteria
'Bacteria
'Nutrients
'Sediment
'Nutrients
'Sediment
'Fecal coliform
'Nutrients
'Nitrates
'Low-level pesticide
concentrations
'Sediment
'Nutrients
'Sediment
'Nutrients
'Animal wastes
'Pesticides
'Sediment
'Nutrients
'Herbicides
'Sediment
'Nitrogen
'Phosphorus
'Sediment
'Dissolved Oxygen
246

-------
                                                                                           Appendix V: Matrix
    SOURCE OF
    POLLUTANT
         WATER QUALITY
           OBJECTIVES
    WATER QUALITY
  MONITORING DESIGN
»Agricultural fields
» Poultry operations
• Erosion control
•2 Paired sites —
 2 control / 2 treatment
»Sediment
•Septic systems
•Reduce fecal coliform by 50%
*Reduce nutrient levels by 20%
•Reduce automobile-related pollutants by 25%
•Reduce BOD by 20%
'Upstream / downstream
•Cattle grazing
•Roads
•Streambank erosion and
  mass wasting
•Reduce sediment by 20-30%
•1 Paired site
   1 control / 1 treatment
•1 Single site
•2 Upstream/downstream
•Construction
•Urban runoff
•Retain sediment on site during construction
•Reduce nitrogen by 65%
•Reduce bacteria by 85%
•Reduce phosphorus by 40%
• 1 Paired site
  1 control / 2 treatment
^Irrigated cropland
•Evaluate the effects of irrigation water
 management on nitrate-N ground water leaching
•Evaluate the effects of crop rotation
 on nitrate-N ground water leaching
•Decrease nitrate and pesticide concentrations
•2 Paired 5 acre plots
   2 control / 2 treatment
•Cropland
•Small livestock operations
•Reduce sediment loads into lake
•Evaluate the effectiveness of
 sediment retention basins
•7 Single stations
•3 Lake stations
•Cropland
•Livestook operations
•Streambank erosion
•Reduce sediment by 50%
•Reduce nitrogen, phosphorus, and
  pesticide by 25%
•Paired watershed
   1 control /1 treatment
  •Upstream/downstream
   on subbasins
 'Cropland
 'Reduce sediment, nitrogen, and phosphorus
•Paired watershed
  1 control /1 treatment
 'Dairy operations
 •Develop and validate a hydrologic and water quality
  model capable of predicting effects of BMP on WQ
 •Collect WQ data for use in model validation
 •Illustrate relationships between BMP and WQ
 •Paired watershed
   1 control /1 treatment
 • Upstream/downstream
   on Warner Creek
 •Streambanks
 •Urban areas
 •Cropland
  and cattle access
 •Reduce impact of agricultural NPS pollutants on
  surface and ground water on Sycamore Creek
 •Reduce sediment in Sycamore Creek by 52%
 •Reduce peak flows
 •Improve instream aquatic habitat
 •Paired watersheds
   1 control / 2 treatment
                                                       247

-------
                                                                                            Appendix V: Matrix
      PROJECT
     SAMPLING SCHEME
      Alabama:         »Weekly April-August
Lightwood Knot Creek   *DS, TSS, and explanatory variables
                        monitored remainder of year
                                                                  PRIMARY WATER QUALITY
                                                                        PARAMETERS
                                       NH3, NO2, NO3 + NO2, OP, TP, Turbidity, TSS, FC,
                                       FS, TKN
      Arizona:         •Weekly grab samples
  Oak Creek Canyon      from May 15 - Sept.15
                                       FC, N03, OP, TN, TP, NH,, BOD
     California:
 Morro Bay Watershed
 »Storm events (30 min. intervals)
 •20 Weekly grab samples (start Nov.)
 »Macroinvertebrate and habitat monitoring
 SS, Turbidity, NO3, FC, Riparian Vegetation,
 Upland Rangeland Vegetation,
 Benthic Macroinvertebrate
    Connecticut:
    Jordan Cove
  Urban Watershed
 •Storm event (flow-weighted composite
  samples)
 •Grab samples (Bacteria & BOD)
 •Monthly composite samples
 TSS, TP, TKN, NH,, NO, + NO., FC
       Idaho:
   Eastern Snake
     River Plain
 •Monthly groundwater grab samples
 •Growing season soil water samples
 NO3, Organic Pesticides, DO, TKN
       Illinois:          •Storm events (automatic samplers)
   Lake Pittsfield       »Base flow sampled monthly
                       •Lake grab samples monthly from
                        April - October
                                       OP, TP, NH3, TKN, N03 + NO,, TSS, VSS,
                                       SS, DP
       Iowa:
Sny Magill Watershed
•Continuous stage, daily discharge and
 suspended sediment measurements
•Weekly grab samples
•Annual habitat assessment
•Annual fisheries survey
•Bi-monthly macroinvertebrates
FC, Habitat Assessment, Fisheries Survey,
Benthic Macroinvertebrates, Sediment, TP,
Nitrogen (N) Series, BOD, Herbicides
       Iowa:          •Water discharge and suspended sediment
    Walnut Creek         monitored daily at watershed outlets
                      •Six surface water stations monthly
                        (March, April, July, Sept.) and
                        twice per month (May, June)
     Maryland:        »Automated storm event - weekly from
   Warner Creek       Feb.-June; bi-weekly remainder of year
     Watershed        •Grab - weekly from Feb.-June; bi-weekly
                       remainder of year
                                       NO3, OP, Turbidity, SS, Pesticides,
                                       NH3, BOD, Macroinvertebrates, Fisheries
                                       NH3, TKN, N03 + NO,, NO3, OP, TKP, Sediment
     Michigan:
  Sycamore Creek
     Watershed
•Storm events (1-2 hr. intervals) using
 automated samplers March - July
•20 Evenly spaced weekly grab samples
Turbidity, TSS, TP, TKN, NO3+ NO  OP, NH,
                                                        248

-------
                                                                                             Appendix V: Matrix
            BMP
                                              MAJOR IMPLEMENTING INSTITUTIONS
                                                     PROJECT
                                                    TIME FRAME
 •Runoff and sediment control structures
 •Critical area planning
 »Cover and green manure crops
 »Pasture and hayland management
 •Geological Survey of Alabama
 •USDA NRCS
 •USDA FSA
 •Covington County Extension
     Jan. 1996-
     Dec. 1996

 319 Project Approval
        1996
 * Enhance rest room facilities
 * Install showers
 •Enforce litter laws
 » Upgrade septic systems
 «AZ Department of Environmental Quality
 » Northern Arizona University
     1994-2001

 319 Project Approval
        1994
 »Riparian cattle exclusion
 » Riparian pasture development
 * Rotational grazing of pasture
 •Floodplain restoration
 •California Polytechnic State University
 «Central Coast Regional Water Quality Control Board
 •USDA NRCS
     1993-2003
                                                319 Project Approval
                                                       1993
 •Phased grading
 »Seeding
 •Sediment detention basins and swales
 •Roof runoff dry wells
 •Gravel pack shoulders on access roads
 •Post-construction practices
 •Aqua Solutions
 •USDA NRCS
 •Univ. of Connecticut, Dept. of Natural Resources
 •Connecticut Cooperative Extension Service
 •Boise State University
     1996-2006

 319 Project Approval
        1996
•Decrease water use
•Pesticide management strategies
•Fertilizer evaluations and recommendations
•Crop rotations
•Division of Environmental Quality
•U. of Idaho Cooperative Extension Service
•USDA NRCS
     Oct. 1991 -
      Oct. 1997

 319 Project Approval
        1992
•Sediment retention basins
•Conservation tillage
•Integrated crop management
•Livestock exclusion
•Filter strips
•Wildlife habitat management
•IL Environmental Protection Agency
•IL State Water Survey
•Pike Co. Soil and Water Conservation District
     1994-1999

 319 Project Approval
        1994
•Structural erosion control practices
•Farmstead assessment
•Water and sediment control structures
•Animal waste management systems
•Education and assistance
•IA DNR-Geologic Survey Bureau
•IA State University Extension
•USDA NRCS
  (319 Project is part of the Sny Magill Hydrologic
  Unit Area Project and North Cedar Creek
  Ag. Conservation. Program-WQ Special Project)
   1991-unknown
(Approximately 10 yrs.
    with funding)
                                                                                          319 Project Approval
                                                                                                 1992
•Conversion of cropland to native tall
  grass prairie
•Restore wetlands and riparian zones
*IA DNR-Geological Survey Bureau
     Oct. 1994-
     Sept. 1998

319 Project Approval
       1996
•Conversion of cropland to pasture
•Installation of watering systems
•Fencing to exclude livestock from streams
•Manure slurry storage tanks
•MD Department of the Environment
•U. of Maryland Agricultural Engineering
     May 1993-
     June 1997

319 Project Approval
       1995
•Diversions
•Cropland protective cover
•Reduced tillage
•No-till systems
•Water and sediment control structures
•Ingham Co Soil Conservation District
•Michigan Department of Natural Resources
•Michigan State University Extension —
  Ingham County
•USDA NRCS
            249
    1993-1997

319 Project Approval
       1993

-------
     PROJECT
    BASIN
    SIZE
       DESIGNATED
     BENEFICIAL USES
                                                                                         Appendix V: Matrix
   WATER QUALITY
      PROBLEM
     Nebraska:             56
Elm Creek Watershed      sq. miles
                 * Recreation
                 «Aquatic life support
                  (coldwater trout habitat)
                                   »Sediment
                                   increased water temperatures
                                   'High peak flows
North Carolina:
Long Creek
Watershed
44
sq. miles
'Drinking water supply
'Aquatic life support
'Sediment
'Bacteria
'Nutrients
Oklahoma:
Peacheater Creek
Oregon:
Upper Grande
Ronde Basin
Pennsylvania:
Pequea and Mill
Creek Watersheds
Vermont:
Lake Champlain Basin
Watersheds
25
sq. miles
695
sq. miles
3.2
sq. miles
12
sq. miles
total
'Recreation
'Aquatic life support
'Aquatic life support
'Coldwater fish
'Drinking water supply
'Recreation (primary and secondary)
•Wildlife habitat
•Aquatic life support
'Wildlife habitat
'Agriculture
'Aquatic life support
'Lake Champlain recreation
and aesthetics ( NPS pollutant
loading)
'Nutrient enrichment
'Loss of in-stream habitat
'Loss of water clarity
'Nuisance periphyton growth
'Water temperature
'Loss of physical habitat
'Loss of riparian vegetation
'Nutrients
'Bacteria
'Organic enrichment
'Nutrients (particularly
phosphorus)
'Bacteria
'Organic matter
    Washington:
 Totten and Eld Inlet
Clean Water Projects
  Totten=69
   sq. miles

    Eld=36
   sq. miles
'Shellfish harvesting
'Recreation (primary and secondary)
'Bacteria
'Wildlife habitat
     Wisconsin:
     Otter Creek
 Otter Creek =
  11 sq. miles
Meeme Creek =
  16sq. miles
'Aquatic life support
'Recreation (secondary contact)
'Sediment
'Phosphorus
'Bacteria
                                                      250

-------
                                                                                             Appendix V: Matrix
    SOURCE OF
    POLLUTANT
         WATER QUALITY
           OBJECTIVES
     WATER QUALITY
  MONITORING DESIGN
» Cropland
'Rangeland
»Streambank erosion
»Irrigation return flows
implement appropriate and feasible NFS control
 measures for protection and enhancement of WQ
'Reduce summer max. water temperature
'Reduce instream sedimentation
» Upstream/downstream
* Single downstream station
'Cropland
'Dairy operations
* Pastures
'Streambank erosion
» Urbanization
'Quantify the effects of NFS pollution controls on:
   -Bacteria, sediment, and nutrient loading to a
   stream from a local dairy farm
   -Sediment and nutrient loss from field with a long
   history of manure application
   -Sediment loads from the water supply watershed
* Reduce sediment yield by 60%
'Paired watershed
   1 control /1 treatment
'Single downstream station
» Upstream/downstream
» Poultry houses
» Dairies
» Septic systems
»Restore recreational and aquatic life beneficial uses
'Minimize eutrophication impacts
'Paired watershed
  1 control /1 treatment
'Grazing practices
'Channel modifications
'Improve salmonid and aquatic macroinvertebrate
  communities
'Quantitatively document a cause & effect relationship
  between improved habitat, lower water temperatures, &
  improved salmonid & macroinvertebrate communities
'Paired watershed
   1 control /1 treatment
'Upstream/downstream
'3 Single stations
'Dairy operations
'Pastures
'Document the effectiveness of livestock exclusion
 fencing at reducing NPS pollution in a stream
'Reduce annual total ammonia plus organic
 nitrogen and total phosphorus loads by 40%
'Paired watershed
 1 control /1 treatment
'Streambanks
'Dairy operations
'Livestock activity within
 stream and riparian areas
'Cropland
'Quantitative assessment of the effectiveness of two
 livestock/grazing management practices
'Document changes in nutrients, bacteria, and
 sediment concentrations and loads due to treatment
'Evaluate response of stream biota to treatment
'Three-way paired
 watershed design
 1 control / 2 treatment
> Livestock operations
'Reduce median 1992-93 fecal coliform values on:
   -Pierre Creek by 69%
   -Burns Creek by 63%
   -Schneider Creek by 50%
   -McLane Creek by 44%
'Paired watershed
  1 control /1 treatment
»4 Single stations
'Cropland
'Dairy operations
'Streambank erosion
'Increase numbers of intolerant fish species
'Improve recreational uses
'Reduce loading to the Sheboygan River
 and Lake Michigan
'Restore riparian vegetation
'Paired watershed
  1 control /1 treatment
'Above and below
'Single station
                                                       251

-------
                                                                                              Appendix V: Matrix
      PROJECT
    SAMPLING SCHEME
    PRIMARY WATER QUALITY
          PARAMETERS
      Nebraska:
Elm Creek Watershed
»Weekly grab samples April - September
•Seasonal biological, habitat data
 collection, and stream morphology
Qualitative and Quantitative Macroinvertebrate
Sampling, Fish Collections, Creel Survey
Substrate Samples, TSS, Morphology Characteristics,
Water Temperature
   North Carolina:
     Long Creek
     Watershed
•Weekly grab Dec.- May and monthly
 remainder of year
•Stage activated storm event and weekly
 grab Dec. - May (year-round on trib.)
»AnnuaI biological survey
Percent Canopy and Aufwuchs, Invertebrate Taxa
Richness, FC, FS, TSS, TS, DO, NO3 + NO2, TKN,
TP, Temperature
     Oklahoma:
  Peacheater Creek
»Weekly July-Jan, and monthly Feb.-June
•During storm events
•Biological monitoring sampling
 scheme varies with parameter
Periphyton Productivity, Fisheries Survey, Macro-
invertebrate Survey, Habitat Assessment, Bank
Erosion, Turbidity, DO, TKN, TP, NO3 + NO2, TSS
       Oregon:          'Early April-early Oct.
    Upper Grande        Continuous water temperature
     Ronde Basin        *3 times during monitoring season for
                         habitat/biological/water chemistry
                                       Habitat, Macroinvertebrate, Fish, Water Temperature,
                                       pH
    Pennsylvania:
   Pequca and Mill
  Creek Watersheds
•Grab samples every 10 days April - Nov.
•Storm event composite
•Monthly grab Dec. - March
•Macroinvertebrate and habitat May
                         and Sept.
SS, Total and Dissolved Ammonia plus Organic
Nitrogen, Dissolved NH3, Dissolved NO3 + NO2,
Dissolved NO3, Dissolved OP, Total and
Dissolved P
      Vermont:
   Lake Champlain
     Watersheds
•Automated continuous sampling stations
•Weekly flow-proportional sampling
•Twice weekly grab sampling
•Macroinvertebrates once per year
FC, FS, E. Coli, Macroinvertebrates, Fish,
TKN, TSS, TP, DO
     Washington:
  Totten and Eld Inlet
 Clean Water Projects
•20 Weekly grab samples (Nov. to mid-April) FC
•6 Storm events
     Wisconsin:         »Storm event
     Otter Creek        *Grab samples (various timing)
                        •Fisheries, macroinvertebrate and
                         habitat monitoring yearly or every other
                         year
                                       Dissolved P, TKN, NH3, Nitrogen Series,
                                       Turbidity, TSS, DO, FC, TP
                                                          252

-------
                                                                                          Appendix V: Matrix
           BMP
  MAJOR IMPLEMENTING INSTITUTIONS
     PROJECT
    TIME FRAME
Conventional BMP
•WQ and runoff control structures
•WQ land treatment
» Conventional WQ management practices
•NE Department of Environmental Quality
•USDA NRCS
»Webster County Extension
 April 1992-1996
 (2 additional years
  contingent upon
     funding)
                                                                                        319 Project Approval
                                                                                               1992
•Land use requirements upstream of intake
Comprehensive nutrient management
»Waste holding structures
»Pasture management and livestock exclusion
•Gaston Co. Cooperative Extension
•NC Cooperative Extension Service
•NC Division of Water Quality
•USDA NRCS
   January 1993-
    Sept. 2001
319 Project Approval
       1992
»Buffer zones and fencing along streams
»Planned grazing systems
»Animal waste mgt. planning & structures
•Watering facilities
•Critical area vegetation
•Soil testing
•OK Conservation Commission
•Cherokee & Sequoyah Cty. Conservation Dist.
•USDA NRCS
•Adair County Extension Service
•Oklahoma State University
    1995-2000

319 Project Approval
       1995
•Streambank stabilization
•Riparian revegetation
•OR Dept. of Fish and Wildlife                          Pending
•USDA NRCS                                          319
•Local Soil & Water Conservation Districts (SWCDs)        Project
•Confederated Tribes of the Umatilla Indian                Approval
  Reservation (CTUIR)
•Streambank fencing on 100% of pasture
 land adjacent to the stream draining the
 treatment watershed
•PA Department of Environmental Protection-
 Bureau of Land and Water Conservation
•USDA NRCS
•USGS
•PA State University Coop. Extension Service
•Lancaster Conservation District
   October 1993 -
  Sept 1998-2001
                                                                                        319 Project Approval
                                                                                               1993
•Livestock exclusion/stream bank protection
•Intensive grazing management
•Franklin County Conservation District
•U. of Vermont School of Natural Resources
•USDA NRCS
•VT Department of Environmental Conservation
    Sept. 1993-
    Sept. 1999
                                                                                        319 Project Approval
                                                                                               1993
•Repair failing on-site sewage systems
•Implement farm plans on priority farm sites
•WA Department of Ecology
•Thurston County Environmental Health Services
•Thurston Conservation District
•USDA NRCS
    1993-2002
                                                                                        319 Project Approval
                                                                                               1995
•Shoreline and Streambank stabilization
•Barnyard runoff management and manure
 storage facilities
•Grassed waterways
•Reduced tillage
•Nutrient and pesticide management
•Sheboygan Co. Land Conservation Committees
•U. of Wisconsin Extension
•USGS
•Wl Department of Natural Resources
    Spring 1994-
    Spring 2001
319 Project Approval
       1993
                                                      253

-------
                                            Appendix V: Matrix
254

-------