Finaf Environmental Impact Report (EOEA File Number 8695)
 and
 Final Environmental Impact Statement
 Volume 2 of 3 - Comments and Responses to DEIR/S
 Boston  Harbor, Massachusetts
 Navigation Improvement Project and Berth Dredging Project
June 1995
US Army Corps
of Engineers
New England Division
Massachusetts
Port Authority
Maritime Department

-------

-------
                               FINAL
    ENVIRONMENTAL IMPACT REPORT/ENVIRONMENTAL IMPACT STATEMENT
                             (FEIR/S)
                           Volume  2  of 3

          BOSTON HARBOR NAVIGATION  IMPROVEMENT DREDGING
                               AND
                      BERTH DREDGING PROJECT
                  RESPONSIBLE LEAD AGENCIES ARE:
U.S. Army Corps of Engineers
Impact Analysis Division
424 Trapelo Road
Waltham, Massachusetts  02254
 Massachusetts Port Authority
 Maritime Department
 Boston Fish Pier II
 Boston, Massachusetts  02210
                  FEDERAL COOPERATING AGENCIES:

National Marine Fisheries Service, U.S.  Fish and Wildlife Service,
and the U.S. Environmental Protection Agency
                    DOCUMENT WAS PREPARED BY:
Normandeau Associates Inc.
25 Nashua Road
Bedford, New Hampshire  03310-5500
        for the
Massachusetts Port Authority
 U.S.  Army Corps of Engineers
 424 Trapelo Road
Waltham, Massachusetts  02254
     This joint  Federal and State document addresses the impacts
associated   with  the   Congressionally   authorized  navigation
improvement  dredging and disposal  of material from the Federal
navigation channel and associated berthing areas in Boston Harbor,
Massachusetts.   The Reserved  Channel and Mystic River  would be
deepened from  35 feet mean low water  (MLW) to 40  feet MLW.  The
Chelsea Creek would  be  deepened  from 35  feet  MLW to 38 feet MLW.
Disposal of the  underlying parent material  is  proposed  at the
Massachusetts  Bay Disposal Site.   Disposal alternatives for the
silt  material   (maintenance  material)  overtopping  the  parent
material are assessed and the preferred  alternative selected in
this FEIR/S.

     Comments should be sent to Colonel Richardson at the U.S Army
Corps of Engineers and Ms.  Trudy  Coxe,  Secretary, Executive Office
of Environmental Affairs, Commonwealth of Massachusetts by the date
indicated in the transmittal letter.  If  you would like further
information  on this  document,  Mr.  Peter  Jackson  of the U.S. Army
Corps of Engineers can be reached at (617)  647-8861 or contact Ms.
Janeen Hansen, Massport, at  (617) 973-5355.

-------

-------
BOSTON HARBOR NAVIGATION IMPROVEMENTS AND
           BERTH DREDGING PROJECT

         DEIR/S COMMENT LETTERS AND RESPONSE

-------

-------
COMMENT LETTERS RECEIVED ON THE DRAFT EIR/S
FEDERAL AGENCIES
                                    <,
Fl     Office of the Under Secretary for Oceans and Atmosphere,
       United States Department of Commerce
F2     United States Environmental Protection Agency, Region I
F3     Office of the Secretary, Office of Environmental Policy and
       Compliance, United States Department of the Interior
F4     Fish and Wildlife Service, United States Department of the
       Interior
F5     National Marine Fisheries service, Northeast Region, United
       States Department of Commerce
STATE AGENCIES
S1     Secretary, Executive Office of Environmental Affairs
S2     Massachusetts Water Resources Authority
S3     Department of Envioronmental Protection
S4     Division of Marine Fisheries
S5     Massachusetts Highway Department
S6     Massachusetts Coastal Zone Management Office
S7     Marine Fisheries Commission

LOCAL AGENCIES AND  OFFICES
LI     Public Works department, Boston
L2     Boston Redevelopment Authority
L3     Boston Water and Sewer Commission
c
L4     Cape Cod Commission, Executive Director
L5     Cape Cod Commission, Chair

-------
L6    Chelsea Department of Planning and Community Development
L7    City of Everett, Mayor
L8    City of Gloucester, Mayor
L9    Nahant, Board of Selectmen
L10   Nahant, Town Administrator
Lll   Swanpscott, Conservation Commission
L12   Swampscott, Board of Selectmen

ENVIRONMENTAL GROUPS,  ADVOCACY  GROUPS
El    The Boston Harbor Association
E2    Center for Coastal Studies
E3    Center for Maine Conservation
E4    Cetacean Research Unit
E5    Coastal Advocacy Network
E6    Conservation Law Foundation
E7    Green World Inc.
E8    Massachusetts Bays Program
E9    Massachusetts Sierra Club
E10   save the Harbor Save the Bay
Ell   Stop the Outfall Pipe (S.T.O.P.)
E12   Nahant SWIM, Inc.
COMMERCIAL
Cl    Boston Gas
C2    Boston Harbor Docking Pilots
C3    Boston Pilots
C4    The Boston Shipping Assocation, Inc.

-------
C5    Boston Towing and Transportation Company
C6    John T. Clark and Son
C7    Containership Agency, Inc.
C8    Decorative Specialties International Inc.
C9    LT.O. Corporation of New England
CIO   LADS System, Lie
Cl 1   Massachusetts Lobstermen's Association, Lie.
C12   Maesklnc.
CIS   F.Mirarchi
C14   Moran Shipping Agencies, Lie
CIS   NedUoyd Lines
C16   North Shore Recycled Fibers
C17   P&O Containers
CIS   Patterson, Wylde and Co., Inc.
C19   C.H. Powell Company
C20   Rexham
C21   Sea-Land Service, Inc.
C22   Boston Edison

PRIVATE CITIZENS
PI    B. Carney
P2    P. Codinha
PS    P.F. Murray

LETTERS RECEIVED AFTER THE COMMENT PERIOD
1.    P.O. Torkildson, Member of Congress
2.    Massachusetts Harbormasters Association (North Shore)

-------
3.    F.M. Valenti, Inc. and Association
4.    N. Wilson
5.    B.Lattimer
6.    Coastal Advocacy Network

-------
FEDERAL AGENCIES
COMMENTS AND RESPONSES

-------

-------
                               UNITED aTATES DEPAnTIWIElNTT OP
                               Off !M of «ho Under Sooroewy for
                               Oceans and AtmoapH
                               Washington. D.C. 30830


                                June 28, 1994
LTC Dwight S. Durham
Acting Division Engineer
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, Massachusetts  02254-9149

Dear Colonel Durham:

     The National Oceanic and Atmospheric Administration (NOAA)
has reviewed the Draft Environmental Impact Report/Statement
 (DBIR/S) for the Boston Harbor Navigation improvement and Berth
Dredging Project.  Enclosed are comments from the National Marine
Fisheries Service  (NMFS), the Stellwagen Bank National Marine
Sanctuary, and the National Ocean Service/Office of Coastal
Resource Management.

     NOAA has participated in the planning for this project over
the past few years, including participation on the Advisory
Group, the Sediment Characterization Technical Working Group,  and
the Disposal Octions Technical Working Group.  We recognise the
need to maintain adequate navigational access to Boston  Harbor,
and we acknowledge the potential economic benefits of the
•project.

     NOAA is interested in the project from five slightly
different perspectives.  First, we  are interested in the broad
 issue of the overall environmental  impacts of the full project on
all living marine  resources and their habitat.  Second,  pursuant
to the Endangered  Species Act of 1973, as amended, we are  _
particularly interested in the potential impacts of the  project
 (including dredging, vessel traffic, and dredged material
•disposal) on threatened and endangered species in Massachusetts
Bay.  Third, we have a specific and unique interest in the
 impacts of the project to NOAA's Stellwagen Bank National Marine
 Sanctuary.  Fourth, we are interested in ensuring the consistency
 of the project with the NOAA-approved Coastal Zone Management
 Plan for Massachusetts.  Finally, ptiggugntto_the Superf und J.aw,.
NOAA has a strong  interest in  seeing that the project is carried
 out in  a manner that ensures that NOAA trust resources > are not
 adversely affected by the  handling  of contaminated marine
 sediments, in order to minimize the need to pursue natural
 resource damage claims  in  the  future.   (NOAA may pursue
 potentially  responsible parties  -•  owners or operators  of
 facilities or vessels,  or  transporters or generators,  that
 release hazardous  substances  into the environment  --  for the

-------
     costs of restoring marine resources that have been adversely
     affected by contaminants.)

          If you have any questions regarding this letter, please
     contact Jonathan Kurland at 508/281-9204.               -  ;

                                     Sincerely,
                                     Donna Wieting
                                     Acting Director
                                     Ecology and Conservation Office
     Enclosure
     cc:  Trudy  Coxe, MEPA,  Boston, MA
          Ed Woo -  EPA,  Boston
          Vern Lang - USFWS,  Concord
          Deerin Babb-Brott  - MA CZM,  Boston
          Scotf Cassel  - MA  EOEA,  Boston
          Leigh  Bridges - MA DMF,  Boston
          Brad Barr - SBNMS,  Plymouth
          Cathy  Demos - ACOE, Waltham
          Pete Jackson  - ACOE, Waltham
          Tom Bruha - ACOE,  Waltham
          Pat Fiorelli  - NEFMC, Saugus
          Janeen Hanson - Massport
          Grace  Perez  - Conservation  Law Foundation
          Jodi  Sugerman - Save the Harbor / Save the  Bay
          Tim Eichenberg - Center for Marine Conservation
          NOAA                           ,  ,
          F/NE02 - Mantzaris, Beach,  Kurlanfl
          F/NEO - Jon Rittgers
          F/NEC - Jack Pearce
          F/NECscl - David Dow
          F/HP1 - Jim Burgess
          N/ORM3 - Patricia Scott
          N/ORCA - John Lindsay
           GCNE - Tony Giedt
           GCNE - Jack Moakley
10

-------
roposed project includes the removal and disposal of
ximately 1.3 million cubic yards of contaminated silty
ial, 2 million cubic yards of parent material  (primarily
n blue clay and gravel), and 132,000 cubic yards of rock.
ystic River Channel and Reserved Channel would be deepened
0 feet mean low.water, Chelsea Creek Channel would be
ned to -38 feet mean low water, and the Massport and private
 "areas would be dredged to the depth of their corresponding
s channels.  An additional'4.4 million cubic yards of silt
subsequent maintenance dredging of the harbor channels would
nerated over the 50-year life of the project.

nvironmental' impacts of the Boston Harbor navigation project
e separated into several categories: sediment quality,
ing operations, handling and transportation of dredged
ial, disposal operations, disposal site impacts over time,
hanges in vessel traffic as a result of the project.  NOAA
ncerned about.potential adverse effects to our. trust
rces within each of. these categories Of impacts.  However,
ost significant issues from our standpoint surround the
sal and management of contaminated dredged materials.

concurs with the Environmental Protection Agency's  (EPA's)
usion'that all 1.3 million cubic yards of the silt
tenance) material associated with the project is unsuitable
nconfined open water disposal.  Conversely, we disagree with
orps of Engineers' assessment that the silt material from
eserved Channel and from the berth areas of Gulf Oil, Army
 Conley Terminal, and the Boston Edison Barge Berth are
ble for unconfined disposal.  The sediments in these areas
in elevated levels of PCBs,  PAHs, and heavy metals, and
ent testing revealed statistically significant
cumulation of several contaminants and/or significant
lity of test organisms.  As we stated in an April 21, 1993
r from .NMFS to the Corps, NOAA believes that the sediments
these areas do not satisfy the Ocean Dumping Criteria for
water disposal.

se such a large volume of material is unsuitable for
[fined open water disposal, a thorough screening and
lation of potential disposal options is an essential
ment of the DEIR/S.  NOAA-participated in the disposal
ms screening process, and we agree with the general
•dology used to narrow the range of disposal alternatives.
•er, we are concerned with two aspects of the portrayal of
»sal options in the DEIR/S.

., the use of the Massachusetts Bay Disposal Site  (MBDS) as
:omparative standard for evaluating the .feasibility'of other
isal options is'fundamentally flawed.  The MBDS is formally
 F1-1
F1-2
                         13.

-------
f
 designated as a disposal  site for clean material only  (i.e.,
 material that satisfies the Ocean Dumping Criteria and is
 suitable "for unconfined ocean disposal) .  While MBDS would serve
 as a sound basis for comparison for the disposal of clean .
 material at other sites,  MBDS is not presently an option for
 disposal of unsuitable  (contaminated) material, and thus should
 not be used as a starting point against which to judge the costs,
 logistics,  or environmental impacts of other alternatives for
 contaminated material.

 Secondly,  in our view'the DEIR/S provides an insufficient
 analysis of the proposed  aquatic disposal sites to allow an
 informed 'decision regarding potential environmental impacts.
 Based on the information  available, it is difficult to determine
 the likely effects of disposal  (particularly of contaminated
 material)  on biological resources and habitat quality at the
 varibus disposal sites.   Substantial additional information is
 necessary to characterize the existing environmental conditions
 at the proposed aquatic sites before selecting a final
'alternative,  and will be  critical for evaluating the recovery of
 borrow pit sites should they be selected for the project.  We
 recommend that the Corps  and Massport document the.year-round use
 of the aquatic sites by fish,-shellfish, and'other organisms, anc
 for the Meisburger sites  and Spectacle Island CAD/ determine the
 relative geologic stability of the areas and evaluate the_
 potential for maintaining cap integrity over time.  -The Final
 EIR/S should include a minimum of one full year of data in
 support of these analyses.

 We are also concerned that -the DEIR/S does not describe how the
 contaminated (silt)  material can effectively be separated from
 the clean parent material during dredging operations, and thus
 how Massport and the Corps can insure that the parent material
 will not become contaminated as it is removed.  The DEIR/S
 suggests that all of the  silt material can be removed from the
 harbor bottom using a'modified "environmental" bucket, and that
 clean parent material could then be removed during a subsequent
 pass of the dredge using  a standard bucket.  In reality, a
 substantial fraction of contaminated material will likely remain
 on the surface'of the parent material due to hydrated bucket
 overflow,  sloughing of side slopes, the normal, dynamic movement.
 of silt on the harbor bottom from tidal and storm forces, and
 sediment resuspension due to vessel traffic and the dredging
 itself.  As a result, it  is highly likely that much of the
 dredged parent material,  on a barge-load basis, will become
 tainted by residual contaminated silt.  The Final EIR/S should
 evaluate in detail the degree of mixing between sediments during
 the dredging process, indluding -an analysis of whether the parent
 clays (especially "in the  most contaminated portions of the
 harbor) may ultimately be unsuitable for unconfined ocean
 disposal.
                                    13:
I*-

-------
 Executive Summary - Pages ES-6 and ES-7 describe the analysis of
 disposal options and' the process used to determine practicability
 of disposal alternatives.   The text here and the accompanying
 chart (Figure ES-3)  compare the costs of various disposal "options
 for the silty dredged material (i.e., that which is unsuitable
 for unrestricted ocean disposal)  with the cost for unrestricted
 disposal at MBDS.   This comparison implies that disposal of the
 contaminated material at MBDS is a viable option.   We strongly
 disagree with this characterization of the disposal options.
 Disposal at MBDS -- either confined or unconfined --is  not a
 viable alternative for the contaminated eilty material from the '
 project because  (1)  MBDS is. designated as a disposal site for
 materials that are suitable for unconfined disposal only,  and (2)
 the efficacy of  capping dredged materials at MBDS  remains
 unproven.

 Section 2.2.1 -  The discussion of sediment characterization
 contains a brief, description of the three tiered evaluation
 process,  and ends  with the'following sentence:  "The feasibility
 of capping dredged material not meeting the requirements for
 unconfined disposal can also be evaluated from the results"  [of
 the Tier I,  II,  and III analyses] .   A determination of capping
 feasibility does depend somewhat  on the nature  of  the  material,
 but other criteria are equally important,  such as  the  location of
 the proposed capping site,  its depth,  ambient hydrography,
 susceptibility to  storm-induced erosion,  etc.   In  other  words,
 dredged material testing is  only one step in evaluating  the
 feasibility of capping contaminated sediments.

 Section 2.2.4 -  NOAA disagrees with the Corps of Engineers'
 assessment  that  160,000  cubic yards of silt  from the Reserved
 Channel  and 200,000  cubic  yards of  silt from the berth areas of
 Gulf Oil, Army Base,  Conley Terminal,  and the Boston Edison  Barge
 Berth are  suitable  for unconfined open water disposal.   The  EPA
 has concluded that all of  the silt  material  is unsuitable for
 unconfined  open  water disposal, and NOAA concurs with  this
 assessment  (see  EPA's  September 9,  1993  letter to  the  Corps  and
 NMFS' April  21,  1993  letter  to the  Corps).   The Marine .
'Protection,  Research and Sanctuaries Act  (§103c) requires that  in
.cases where  the  EPA  disagrees  with  the' Corps' suitability
 determination, the determination  of EPA shall prevail.   We
 recommend clarifying this point in  the  Final EIR/S.

 Section 3.1  -  The DEIR/S briefly  mentions that various federal
 and state agencies have established a  goal of developing a. long
 term regional  dredged material management plan to help address
 recurring environmental review problems.  Although such  a plan
 will not be  complete and ready "for  implementation  for the Boston
 Harbor dredging project, we  recommend  that the involved  agencies
 redouble their efforts to develop such a. plan so that it is  in

                                •3
 F1-6
F1-7
F1-8
F1-9
                              ./if.

-------
 place for the next maintenance dredging cycle in Boston Harbor.
 NOAA ia committed to participating actively in this process.

 Section 3.2 - 'The DEIR/S refers to guidance in the June 7,  1991
 MSPA Scope stating that-unconfiried ocean disposal of dredged
 material at-MBDS is the option against which other alternatives
 should be judged.  This basis for comparison is appropriate for
 clean dredged material, but is not valid for contaminated
 materials, which may not be disposed at MBDS either with  or
 without capping.  Using MBDS--'as a standard by which to compare
 other disposal options is highly misleading, since it implies
 that the lowest attainable cost for disposal is lower than it
 realistically is, .and thus that other options are vastly  more
 expensive and in some cases impracticably so.

 This section incorrectly states that "the silt from the Reserved
 Channel area was the only material for which a consistent opinion
 was not reached" between the Corps and EPA on suitability for
 open water dispo.sal.  The Corps also disagreed with EPA's (and
 NOAA's) opinion that sediments from the berth areas of Gulf Oil,,
 Army Base,' Conley Terminal, and the Boston Edison Barge Berth  are
 unsuitable for open water disposal.

 Section 3.3.1 - Land-based disposal alternatives may be worth
 considering for a portion of the contaminated material.   We
 recommend that the Corps and Massport re-examine potential land-
 based sites prior to completing the Final EIR/S to determine
 whether any .new sites -are available or conditions have changed
 regarding the listed sites.

 Section 3:3.2 - W« agree that several of the aquatic disposal
 alternatives listed are worthy, of serious consideration.   Of the
'shoreline facilities, we recommend retaining in the Final EIR/S
 the partial and complete fill ' alternatives for Mystic Piers,
 Revere Sugar, and Amstar, plus the "shallowing" options for
 Little Mystic Channel and Reserved Channel . ' We recommend
 including additional details in the Final EIR/S on the proposal
 to establish salt marsh vegetation on dredged material as part or
 the Reserved Channel alternative.            "•         .

 We also recommend retaining in the Final SIR/S the in-channel  and
 borrow pit  (Spectacle, Island CAD and Meisburger sites 2 and 7)
 alternatives.  However, substantial ' additional information should
 be included in the Final EIR/S regarding the existing habitat  use
 and value of all three borrow pit sites, as well as the
 susceptibility of these sites to erosion from storm waves and
 other forces.   (See additional comments below regarding the
 description of the disposal sites in Attachment 1 to the  DEIR/S.^

 We are extremely concerned about the discussion -of the
" feasibility of capping .in this section of the DEIR/S, and
 particularly the suggestion- 'that the silty sediments from Boston
                                      15

-------
 Harbor could be' used for a demonstration project to test the
 .effectiveness of capping.-  The text in this section states that
 "the Corps has successfully demonstrated effective capping at
 sites with similar depths [to the Boston Lightship disposal site]
 elsewhere in New England."  This assertion presumably refers to
 the Portland Disposal Site.   However,  we know of no documentation
 regarding successful tests of capping at Portland or any other"
 New England disposal site with similar depths.   Although capping
 has been used successfully at shallower and more sheltered sites
 in Long Island Sound, NOAA is not convinced that capping is a
 proven technology for the Portland site,  or for Boston Lightship.
 Moreover, we are strongly opposed to the use of • contaminated'
 materials to test the efficacy of capping.   Jnstead,  we recommend
 that the Corps conduct a deep water capping-demonstration project
 using clean materials only,  marked with a distinct tracer to
 allow analysis of the entire disposal  process',  including cap
 placement and integrity over time.

 Additionally,  we recommend refraining  from'disposal activities at
 the Boston Lightship site until more detailed Information is
,available regarding the presence,  distribution,  and extent of
 radioactive and other contamination at the  site.   EPA studies
 indicate that  some hazardous chemical  and radioactive barrels may
•be concentrated in relatively small areas- at the Boston Lightship
 site (Keith,  et al.,  1992;  Carey,  e£ al.,  1992),  but it would be
 premature to cover the barrels with dredged material until one
 can verify their, presence and determine if  the  barrels pose an
 environmental  or human health risk.  For example,  the best
 management alternative for these barrels  might  be in situ
 isolation or retrieval.

 Section 3.4 -  The cost information.for disposal options,  which is
 displayed in Tables 3-13 through 3-18  and 3-20,  provides useful
 information,  including .the assumptions underlying all
 calculations.   In Table 3-20 (Cost Estimates for Using Existing
 Disposal Sites for Disposal  of Silts from BHNIP)  we recommend
 listing one additional assumption for  clarity:  the'estimates
 assume that capping is a viable technology  for  use at these
 sites,  including both environmental  and regulatory criteria.

 Sections 3.4.1 -  3.4.4 - The .range of  disposal  options discussed
 in these sections comprise a good array of possibilities for the
 project.   However,  in the Final EIR/S  we  recommend providing a
 better discussion of  possible combinations of alternatives which
 when used together could'meet  the  disposal needs  of the project.
 For example, although the land-based sites may  be too costly or
 impractical for disposal of  all of the project  materials,  they
 may be reasonable options for a portion of the  material.

 We also recommend adding a discussion  of  the  potential use of
 dredged material  filled geotextile containers in  conjunction with
 the in-channel,  subaqueous,  and borrow pit alternatives.   This
F1-17
F1-18
F1-19
                                5  ../(*

-------
 technology, which is currently under study by the  Corps of
 Engineers'  Waterways- Experiment Station,  could potentially
 alleviate water quality problems during disposal and  help contain
 contaminants at disposal sites (Fowler and Sprague, 1994} .

 Section 3.4.4 - 'C3ption D2 would involve disposal of the
 contaminated silty material at either MBDS or Boston  Lightship
 with capping.  The text mentions that the proposed project
 "overcomes a major stumbling block faced in the past  by proposals
 for capping at MBDS: availability (or lack thereof) of suitable
 capping material."  As we stated above, NOAA is strongly  opposed
 to the use of contaminated materials to test -the viability  of
 capping, and we recommend conducting a capping demonstration
 project at MBDS using clean materials only.

 Section 3.5.1 - We recognize that few treatment •technologies for
 contaminated sediments have been used beyond small scale  tests  on
 marine dredged materials.  Nevertheless,  we encourage the Corps
 and Massport 'to use a portion of the contaminated  material  from
 this project as a pilot test of promising treatment technologies.
 We recommend using the Disposal Options Technical  Working Group
 as a forum 'to discuss and refine an appropriate test  project.

 Section 3.5.2 - We recommend that the Final EIR/S  provide
 additional detail, including a range of specific potential
 projects, for beneficial uses of the clean parent  material  and
 rock from the Boston Harbor dredging project. The types  of
 beneficial uses listed in the DEIR/S are appropriate, with  the
 exception of cap material for contaminated silts disposed at _ MBDS
 or .Boston Lightship  (again, we are opposed to a test  of  capping
 using contaminated materials) .

 Section 3.6 - The Final BIR/S should explain why the  § screening
 process of practicability for disposal options used  in  the  DEIR/S
 considered costs greater than 4 times that of ocean  disposal's
 prohibitive.  What -is the basis for this standard?  How was it
 developed?  In particular, we are concerned with  the use of
 unconf ined ocean disposal at MBDS as the basis for cost
 comparisons with other alternative's for disposal  of -contaminated
 materials.  Dredged materials that are unsuitable  for unconf ined
 open water disposal may not be dumped at. MBDS, either with or
 without capping, as specified in the regulatory designation for
 the site'  (EPA,  1993; 40 CFR 228.12).  Therefore,  the use of
 unconfined disposal of contaminated sediments at  MBDS as a
 comparative standard for evaluating the cost effectiveness of
 other disposal  alternatives is inappropriate and highly
• misleading since MBDS is not  an option for these sediments.
 Section S.S.'l  -  This  section indicates that "sites wi*h
 costs greater  than 4  times and higher, than capping at MBDS, were
 considered excessive."  This statement appears to be inaccurate,
 since the  "practicable  alternatives" listed all would cost less
                                        II

-------
 than four times the cubic yard cost of uneonfined (no capping)
 disposal at MBDS,  and several of the sites deemed too expensive
 (Revere Sugar,  Amstar, Mystic Piers, Little Mystic Channel,  a-nd
 Reserved Channel B) would cost only 1.8 to 2.1 times  as much as
 confined disposal at MBDS.  We recommend.clarifying this" section
 in the Final EIR/S. ' Also, as noted above, we believe disposal at
 MBDS (with or without capping) should not be used as  the. basis
 for cost comparisons among alternatives.                          -

 Section 3.6.2.1 - The description of the proposed use of the
 Boston Lightship site mentions that capping has- occurred at
 similar depths at the Portland, Maine disposal site.   The Final
•EIR/S should note that capping is not an accepted management
 practice at the Portland site, and its efficacy remains in
 question.                                                         -

 The text states that the Boston Lightship site "is not known to
 be biologically unique..."  Even if this statement is true,  it is
 irrelevant for assessing potential environmental impacts from
 disposal at the site.  Many resources that are not "unique"
 nevertheless have substantial value that could be diminished or
 lost due to dredged material disposal.

 Information from the Massachusetts Division of Marine Fisheries •
 indicates  that the Boston Lightship site is heavily fished by .the
 commercial fishing industry.  The Final EIR/S should  evaluate the
 extent of  harvesting activity in this area,  as well as any
 anticipated impacts to the industry from use. of this  site.

•Section 3.6.2.2 -  This section states ithat .the only active
 breeding population of gray seals (SalichoeruB grrypus)  in the
 eastern United States is located southwest of Nantucket Island.
 Actually,  another gray seal pupping ground was identified this
 past year .off Mt.  Desert Island,  Maine.

 Sections 3.6.2.1 - 3.6.2.4 - These sections all refer to an
 ongoing consultation between NMFS and the Corps,  pursuant to
 Section 7  of the Endangered Species Act (ESA) ,  to evaluate the
 potential  impacts  of disposal at MBDS, Boston Lightship,
 Meisburger 2,  and Meisburger 7 on threatened and endangered
 species.   NMFS  has determined that the Biological Assessment of
 potential  impacts  submitted by the Corps  treprinted in Appendix
 A-4 of the DEIR/S)  is deficient,  and that additional  information
 is needed  for NMFS to formulate a Biological Opinion  under the
 ESA. "The  Corps has agreed to provide this information,  and
 consultation will  resume once NMFS receives the requested data.

 The DEIR/S .uses the Corps' ADDAMS model to predict no long term
 water quality or biological impacts from dumping dredged material
 at the offshore sites (MBDS, Boston Lightship,  and Meisburgers 2
 and 7.) .  The resulting risk analysis for biological resources is
 somewhat rudimentary and ^confined to the  near field area around

-------
       the dredged material disposal mound.  The Final SIR/S should have
       an adequate'baseline of information on the benthie and finfish
       resources that, are potentially at risk in both the- near field and
       far field areas..                                       "  -       :

       Use oi the ADDAMS model to predict the transport of sediment-
       bound contaminants, and elutriate tests to predict the transfer
       of contaminants from the particulate to dissolved phase, appears
       to be a crude approximation of reality, given the likelihood of
       dissolved organic matter from the Massachusetts Water Resources
       Authority outfall influencing the contaminant partitioning at tne
       Boston Lightship and Meisburger sites. -Also, event scale
       hydrologic transport resulting from storms and riverine peak.
       .discharges influence net water mass displacement  (and the
       transport of fluid dredge spoil plumes) more so than do the mean
       current events on which the ADDAMS result are based.

       Since most EPA water quality criteria for organic contaminants
       are based upon equilibrium partitioning, thus ignoring'food chain
       transport and bioaccumulation; it is not clear that the water
       quality levels at 'the site boundary after 4 hours are indeed
       "safe" if-they approximate the chronic toxicity critical
       concentration.  For instance,, copper, mercury, and lead, if
       methylated by bacteria in the dredge spoils  (Gadd, 1933}, have
       the potential for bioaecumulation.  In this regard if one
       examines radionuclide bioconcentration in the environment many
       metals appear to bioaccumulate, even though this does not often
       occur in bioaecumulation tests conducted in laboratory flasks
        (Forstner, 1980)-. • One should not confuse mathematical modelling
       simulations and elutriate tests with what will necessarily happen
       in the real world, since these models only approximate certain .
       aspects of the natural aquatic ecosystem.                        "

       Sections 3.6.2.3 - 3.6.2.5 -  In general,"it is difficult to
       assess the potential impacts of disposal at the- borrow pit sites
        {Meisburger 2, Meisburger 7, and Spectacle Island GAD  on fish
       stocks ol their habitat because the DEIR/S contains little site- -
       specific resource information.  The DEIR/S also does not evaluate"!
       iS detail'the capability of these sites to resist erosion and
       mSintatn a securf cap during  storm  events.   (Additional comments
       on the resource  information for the various disposa 1 «i|«; are
       included below,  in reference  to Attachment 1 to the DEIR/S.;

       -Dr. Gordon Wallace  (University of Massachusetts-Boston,
       Environmental Sciences Program) has shown that winter  flounder
        CPleuronectes americanus) from Georges  Bank  have  higher heavy
       metal levels in  their liver than do the same species from Boston
       Harbor,  in  spite of the much  higher heavy metal Concentrations  in
       the fine grained Boston Harbor sediments  compared to the coarse
       grained  Gorges  Bank sediments.  -This - seemingly counterintuitive
       finding  is  directly applicable to the  discussion  of  cap in teg rxty
       for the  borrow pit alternatives, since it may  be  difficult  to
                                        8
/9
it

-------
distinguish "background" heavy metal levels from contamination
due to dredged material disposal.  The Final EIR/S should
consider interacting factors including the heavy metal
concentration,  bioavailability, metallothionein binding capacity
for heavy metals,  and the depuration/clearance rate (Marguenie
and Tent, 1989; Roesijadi, 1992).

Section 3.6.2.5 -  The proposed Spectacle Island CAD site is
described as being in an area "having cleaner sediments" but the
text does not identify the. areas to which these sediments were
compared.                              .

Section 3.7 - The  discussion of cumulative impacts from the
project is extremely brief, and restricted primarily to impacts
from disposal operations  (disposal of clean material at MBDS and
associated barge traffic).  The Final EIR/S should include a more
expansive cumulative impacts assessment to address the effects of
the project in conjunction with other past and reasonably
foreseeable-future actions.  Pertinent topics include the -
potential for:  increases in the number of vessels using Boston
Harbor and Massachusetts'Bay, increases in the size of vessels
using Boston Harbor and Massachusetts Bay, increases in vessel
collisions with endangered humpback whales (J&egaptera
novaeangiaae) and/or northern right whales (Eubalaezia grlaeialis) ,
and increases in vessel impacts to fishing gear.

Additionally, this section should evaluate cumulative impacts at
the various disposal sites on the benthos, finfish, marine
mammals, and sea turtles. 'In order to increase the ability of
the Corps' Disposal Area Monitoring System program to detect
changes between baseline and dredge spoil disposal periods, the
Corps -needs information on population age and size structure for
finfish  (including estimates of age/length at maturity, .growth
rate, sex ratios,  etc.), as well as species identification and
numbers, size structure, and seasonal changes in composition for
benthic infaunal invertebrates.  Since finfish and benthic
invertebrates vary extensively in space and time, it is necessary
to define what constitutes an ecologically significant > level- of
change, since statistical significance may not be meaningful.   _.

Section' 3.10- The Final EIR/S should include a more detailed
explanation of the management measures that, will be used to
minimize fish mortalities during the blasting and removal of
rock.  For example, it may be necessary to use electronic fish
finders and/or to  station qualified observers in the blasting
area prior to detonation to verify that significant schools of
fish are not present.  Another option might be to use
hydroacoustics or  other technologies to deter fish from
congregating in the blast area.                               .  ~

The Final EIR/S should also provide a range of specific potential
mitigation projects '(including possible locations and conceptual

-------
plans) for losses of. subtidal habitat -due to the inshore harbor
filling options.

Final seasonal restrictions on dredging and other in-water work,
as well as appropriate operational measures (e.g., use of silt
curtains), should be coordinated with -NMFS and the Massachusetts
Division  of Marine Fisheries prior to the commencement of work.

Section 4.1,1 - We concur with the decision to use a modified_
"environmental" bucket to dredge the contaminated silty material.
This equipment should help to reduce turbidity and release of
contaminants at the dredge site.

Section 4.2.2 - -The fourth sentence in this section reads as
follows:  "Because much of the silt to be removed from Boston
Harbor is considered unsuitable for unconfined open water
disposal, these sediments will need to be separated from the
suitable  or parent material."  We recommend changing this
sentence  to read: "Because all of the silt..."  . •               -

.The DEIR/S suggests that all of the contaminated silt material
can be removed from the harbor bottom using a modified
"environmental"' bucket, and that underlying parent material could
then be removed" cleanly during subsequent dredging with a.  •
standard  bucket.  We believe this characterization is inaccurate.
Dredging  the silt material, even using a sealed "environmental"
bucket, cannot neatly vacuum all of the contaminated material
from the  harbor floor.  Instead, due to a variety of interacting
factors,-  it is highly likely that a substantial fraction of the
contaminated material will remain on the surface of the parent
clays.  Hydrated bucket overflow, sloughing of side slopes, the
normal dynamic movement of silt on the harbor bottom from tidal
and storm forces, and sediment resuapension due to vessel traffic
and the dredging itself will all tend to cause contaminated silt
material  to accumulate rapidly on top of the parent material
4uring the silt dredging, even if the top 0.5 feet of parent
material  is dredged with the silt as proposed.

NOAA is concerned that much of the parent material, despite its
being uncontaminated while it is in place, may become mixed with
contaminated silts during the dredging operation due to the
•movement  of fine sediments on the harbor bottom.  As a result, it
is highly likely that a major portion of the dredged parent
material, on a barge-load basis, will become tainted by residual
contaminated silt, and could be rendered unsuitable for
unconfined open water disposal.  This concern is especially actite
for parent material  in the most "contaminated portions of the
harbor.   The Final EIR/S should evaluate this issue in detail,
including the degree of mixing between sediments during the
dredging  process, any mitigative measures that might minimize
sediment  commingling, and an expanded suitability analysis for
                                10

-------
open water disposal to reevaluate the parent material in light of
likely commingling with contaminated silts.

Seetiea 4.3.5 - According to the DEIR/S, the dredge contractor
will carry an inspector aboard the tug, and may also use an
electronic "black box" recording device, to verify that open
water disposal takes place at the disposal site buoy.  The final
EIR/S should discuss what measures will be used to prevent "short
dumps" or otherwise dumping the dredged materials at a location
other than the prescribed disposal point, and should explain what
contingencies will be taken for disposal during storms, in rough
•eas, etc.      •                                                 ]

Section 4.5.1 - The DEIR/S tends to underestimate the
bioavailability of heavy metals and their potential for
bioaccumulation by benthic invertebrates and fish.  Methylation
of heavy metals increases their bioaccumulation potential {Gadd,
1993).  -The heavy metal levels in the pore water are a function
of 'the binding/complexing component concentrations, -hardness,
salinity, dissolved organic carbon concentrations, and the pore
water extraction method utilized.  The pore water heavy metal
concentrations appear to be related to the acute toxicity levels
measured in laboratory bioassays  (Ankley et al., 1994).

Section 4.S.2 - See the comments above under Section 3.10
regarding mitigation of potential blasting impacts to fish.

Sections 5.1 and 5.2.1 - The summary of pertinent federal
statutes and compliance requirements should reference the
Stellwagen Bank National-Marine Sanctuary provisions of the
Marine Protection, Research, and Sanctuaries Act, as amended
(MPRSA) .  Specifically, the MPRSA  (16 U.S.C. §1434 (e)) states
that "appropriate Federal agencies shall consult with the
Secretary  [of Commerce] on proposed agency actions in the
vicinity of the Sanctuary that.may affect sanctuary resources.".  _

The-text on the Coastal Zone Management Act of 1972, as amended
(CZMA), inaccurately reflects the CZMA consistency review
requirements.  In accordance with the 1990 amendments to the CZMA
(16 -U.S.C. S1451 et eeq.), the following language should be
included in- the Final EIR/S in lieu of the existing language
contained in the DEIR/S:

    . "Each Federal agency activity within or outside the coastal
     zone that affects any land or water use or natural resource
     of the coastal zone shall be carried out in a manner which
     is consistent to the maximum extent practicable with the
     enforceable policies of the Massachusetts Coastal Zone
     Management Program."   (See §307 (c) (1) (A) of the- CZMA.)-

Attachment 1 - In general, the DEIR/S does not contain sufficient
information on the use of the proposed aquatic disposal sites toy

                                11

-------
                             ^
 living marine resources.  Attachment 1 to the DEIR/S, which  _
 contains  more detailed environmental information than the main
 text  of the document,  presents only a general discussion on
 potential uses of the  sites by fish, shellfish, and other
 organisms.  We believe substantial additional data is necessary
 to  allow  an adequate comparisbli between sites, and, for tne
 proposed  borrow pit sites, to provide a baseline against which to
 evaluate  recovery after the project is complete.

 We  recommend that the  Corps and Massport gather sufficient data
 to  document the basic  biological characteristics of all the
 aquatic sites on a seasonal basis.  This documentation should
 include site-specific  data on use of the sites by fish  (both
•pelagic and demersal), shellfish, marine mammals, andJ^6*   __.
 biota, unfortunately, this type of information may not currently
 be  available (except perhaps for MBDS), so ne\£xoiosicai   /«
 investigations may be  necessary.  Regardless, the f*2aj-BJ*'S -,
 should include at least one full year of biological data for all
 aquatic sites.

 For the proposed borrow pit sites, we also recommend-providing
 additional data and analysis on the relative .geologic stability
 of  each site, including erosion and accretion patterns,
 susceptibility to storm induced erosion, and the ability to
 maintain  cap integrity over time.

 Cone IUB i'onB-

 In summary, NOAA has many outstanding concerns regarding  the
 Boston Harbor Navigation Improvement Project, most  of wnicn
 center on the management of contaminated sediments  during
 dredging, handling, and disposal,, and over the long te™ **?!€.
 selected disposal site(s) .  We urge you to seriously con^er  ur
 general  and specific comments on the DEIR/S, and we J°?* f^*3'*
 to working with you during the  continuing environmental  review of
 the project.                  .  -
                                 12

-------
References

Ankley, G.T., N.A. Thomas, D. Micro, D.J. Hansen, J.D: Mahony,
     W.J. Berry, R-.C. Swartz, -and R.A. Hoke. 1994. Assessing
     potential bioavailability of metals in sediments: a proposed
    • approach'. Environ. Managem. 18:331-337.

Carey, D.A., D. Keith, J. Schoenherr, and P. Matthias. 1992.
     Construction of a regional relational/CIS database in
     support of ocean disposal issues in Massachusetts Bay. pp.
     491-496 in Oceans 92-Mastering the Oceans Through
     Technology; Volume 1; 2EEE 92 CH3217-7.

Environmental Protection Agency.  1993.  Public Record of
     Decision on the Final Environmental Impact Statement 'for the
     Designation of an Ocean Dredged Material Disposal Site in
     Massachusetts Bay.  January 13, 1993.  12pp plus Appendices.

Porstner, U. 1980. Inorganic pollutants, particularly heavy
     metals in estuaries, pp.307-348 in Chemistry and
    ' BiogeoeheTnistry of Estuaries;• by E.Olausson and I. Cato;
     .John Wiley and Sons, Ltd.

Fowler, Jack, and C. Joel Sprague.  1994.  Dredged Material
     Filled Geotextile Containers.'  Unpublished (?) .
     Geotechnical -Laboratory, U.S. Army Waterways Experiment
     Station, 3909 Halls Ferry Road, Vicksburg, MS, 39180-6199. ,
     17pp.

Gadd, G.M. 1993. Microbial formation and transformation of
     organometallic and organometalloid compounds. FEMS
     Microbiol. Rev. 11:297-316.        .  '

Keith, D.J., G.S. Cook, D.N. Wiley, V. Capone, D.A. Carey, 'and
     J.P. Fish. 1992. Target detection and mapping of aquatic
     hazardous waste sites in Massachusetts Bay utilizing side
     scan sonar, pp. 497-502 in Oceans 92-Mastering the Oceans
     Through Technology.' Volume 1: IEEE 92 CH3217-7.

Marquenie, J.M. and L. Tent. 1989. Impact of contaminants
     mobilized from sediments upon disposal, pp.510-523 in
    • Pollution ef the North Sea-An Assessment ed. by W. Salomons,
     E.K. Duursma, B.L. Bayne and U.Forstner; Springer-Verlag.

Roesijadi, G. 1992. Metallothioneins in metal regulation and
     toxicity in aquatic animals. Aquatic Toxicol. 22:81-114.
                                13

-------
Unnumbered Comment

       1. 3rd para., 6th sent. -  Dredged material from Boston Harbor is not subject to
the Superfund law. Boston Harbor would have to be designated a Superfund site and
placed on the National Priority List to receive Superfund funding.  As this has not
happened, natural resource claims would not be applicable.

In addition, the Corps does not believe dredged material is subject to the Resource
Conservation and Recovery Act (RCRA).  Dredged material does not clearly fall
within the RCRA definition of solid waste or hazardous waste.  The Clean Water Act
and the Ocean Dumping Act provide the appropriate legal and regulatory regime for
dredged material disposal and these regimes are incompatible with regulation under
RCRA (33 CFR Parts 209, 335-338).

Although the Corps does not believe the material from Boston Harbor is subject to
Superfund or RCRA law, the Corps and Massport are committed to minimizing
damage to marine resources, in  a practicable manner.  Water quality modelling has
indicated that the proposed project would not have a significant effect on the aquatic
environment. Dredged material will be managed to minimize impacts to the environ-
ment
Fl-1

             Section 2.2.4 of the DEIR/S states that based on the Tier I-III evaluation
of sediments in the berth areas, "the US ACOE has determined that all maintenance
material (silt), except 160,000 cy from Reserved Channel, and 200,000 cy from the
berth areas of Gulf Barge berth, is unsuitable for unconfined open water disposal.
Conversely, all  of the  silt material is considered to be unsuitable for unconfined open
water disposal by the U.S. Environmental Protection Agency."

Given this USEPA consideration, BHNIP is not considering unconfined areas disposal
as a practicable alternative for any of the silt material at this time.
Fl-2

       The Massachusetts Bay Disposal Site (MBDS) has been removed from discus-
sion and charts as a point of reference for disposal of the silty dredged material.  This
site is not currently available for disposal of silty material until capping or other
technology to immobilize the contaminants has been demonstrated. The currently
viable sites will be used for comparison purposes.

-------
Fl-3

              Section 3.6 of the DEIR/S discusses the project team's reluctance to
identify "the single preferred disposal option" in this preliminary document.  The
selection of which will be based on several screening criteria identified as Figure 3-2.

       Several technical and environmental feasibility parameters are also identified in
Section 3,6 which must be evaluated against each alternative to establish the least
damaging option(s).

       As part of the EIS/R evaluation process, comments presented by viewers
indicated that  site and/or resource specific studies were required to address unresolved
issues.  Results of these studies were integrated into the impact evaluation to further
select suitable and specific disposal alternatives.

       These additional studies included lobster and finfish studies, sediment profiles
and benthic biological community sampling which are fully described hi this FEIS/R.

       Also, the DEIR/S stated, " Massport and the Corps select MBDS, BLS,
Meisburger 2 or 7 and Spectacle Island CAD as their preferred disposal alternatives.
These sites did not represent "the single preferred disposal option". Based on the
continued inputs of addition data and information, Section 4 of the FEIS/R identifies
In-channel disposal at Mystic River, Chelsea River and the Inner Confluence as the
current preferred disposal alternative.
Fl-4

       The silty dredged material will be removed by an environmental mechanical
bucket. The bucket will remove the silty material until it hits the parent material.  The
parent material, composed mostly of Boston blue clay, will provide resistance to the
toothless environmental bucket.  In this manner the environmental bucket will be able
to remove essentially all of the silty material.  A standard mechanical bucket (with
teeth) will be used to remove the parent material.  Some  silty material from other parts
of the  harbor may drift into the navigation channel after the silty material has been
removed and before the dredge has returned to remove the parent material.  The
amount of this material is not expected to be significant to change the suitability
characteristic of the parent material.
Fl-5

             Dredging of silts will be a distinctly different operation from the
dredging of parent material.  The consistency or compaction of the two layers will be
distinguishable by the dredge operator. The parent material will be relatively more
consolidated and therefore harder and more resistant to excavation. The dredge bucket
used for the removal of silts, will penetrate into the parent material,  estimated at up to

-------
approximately  6-in, due to the weight of the bucket. Therefore it can be expected that
some of the parent material will be removed during the excavation of the silts. This
anticipated overdredging of the silts will minimize the volume of those materials which
will be taken with the parent material. It can, however, be expected that some silt
material will be "left behind" after dredging of those sediments. Use of currently
available "environmental" buckets, which are capable of producing a relatively uniform
and consistent horizontal cut, will minimize the volume of silts which are missed. It is
highly unlikely that large volumes of silts, sufficient to contaminate the dredged parent
material, will be removed during dredging of the clays.
Fl-6

             Again, BHNIP is not considering unconfined ocean disposal as practica-
ble alternative for any of the silt material at this time.
Fl-7

       True, it is assumed that if dredged material needs to be capped, the conditions
for an appropriate disposal site will be met. The sentence will be clarified.
Fl-8

       Although the Corps and the U.S. EPA disagree on the suitability determination
for some areas in Boston Harbor, as a practical matter, all of the material is being
treated in the EIR/S as unsuitable.  This point will be clarified.
Fl-9

       The Corps and Massport agree wholeheartedly that a long term management
plan for Boston Harbor and other harbors needs to continue.  The Corps and Massport
are committed to working towards a solution for the disposal of contaminated material.
We appreciate the commitment of NOAA to actively participate in this project.
Fl-10
       See response to F1-2
Fl-11

       This sentence will be corrected. Again, BHNIP is not considering unconfined
ocean disposal as a practicable alternative for any of the silt material at this time.

-------
Fl-12

       Section 4.0 of the FEIS/R has re-examined the practicability of land based
disposal alternatives and concludes that Squantum Point provides the most viable land-
based location for disposal of a portion of the contaminated silts, however, no land-
based site was more reasonable than aquatic sites for disposal based on environmental
and practicability criteria.   BHNIP was not able to identify any new practicable land
based sites for disposal.
Fl-13

       Based on the addition evaluation of disposal area resources (Section 4.2 of the
FEIR), BHNIP currently considers both the Mystic Piers and Revere Sugar as likely
disposal  sites, as part of a multiple site/technology approach for disposal.  This
multiple site approach will serve to minimize concentrating disposal activities or
effects in any one location or resource type.

       BHNIP would suggest establishing appropriate estuarine conditions  (e.g.
hydrology, tidal exposure and sediment matrixes) for natural recruitment of typical salt
marsh species in Reserved Channel.
Fl-14

       Additional investigations on biological resources at all the potential aquatic
disposal sites were undertaken in fall 1994. This information was reported hi separate
technical documents and hi Attachment 1 of the FEIR/S.  These data were used to re-
evaluate the selection of the proposed preferred alternative site for disposal of silt from
the BHNIP.
Fl-15

       Responses from agencies and other organizations indicate that using contami-
nated material from Boston Harbor to demonstrate capping will not be considered
likely. Successful capping at Portland has been reported in the DAMOS 1984
Summary and report and draft publications.  Suitable silty material from another
project may be used for a capping demonstration at the MBDS.  Appropriate agencies
will be invited to give comments on the proposed monitoring plan.
Fl-16

             The status of the understanding of the distribution, character and
condition of hazardous materials was considered in the re-evaluation of the disposal
site selection process (Section 4 of the FEIR/S).

-------
Fl-17

       As suggested by NMFS, the assumption that capping is a viable technology
from both an environmental and a regulatory perspective has been added to cost
estimates.
Fl-18

       Section 3.6 of the DEIR/S clearly stated that it was not the intent of BHNIP to
identify "the single preferred disposal option".  Section 4 of the FEIS/R details the
targeted multiple site disposal alternatives which appear to be most practicable.
Fl-19

       Geotextile containers are discussed in more detail in Section 3 of the FEIR/S.
The use of these containers would be dependent on whether a disposal operation would
not pass water quality criteria or some other regulatory requirement. In addition the
cost and feasibility of using these containers have not been fully demonstrated for
contaminated silts and would need to be assessed in more detail for each particular
disposal site.
Fl-20

       Again, Section 2.0 of the FEIS/R states that the Corps is interested in conduct-
ing a demonstration project for capping in depths of >50m; such a project could occur
using clean non project silts and project parent material. BHNIP is not considering
capping of project silts at either MBDS or BLS at this time.
Fl-21
       Silt from the BHNIP will be made available for pilot tests upon request.
 Fl-22

              Section 3.5 of the FEIS/R detail all practicable potential beneficial uses
 and projects for clean parent material and rock from BHNIP.

       The BHNIP is not considering disposal of project silts at MBDS and BLS,
 therefore capping of contaminated materials at these sites is no longer a practicable
 disposal option.

-------
 Fl-23

       This approach was eliminated in the FEIR/S based on comments by reviewers
 (Section 4.0). The current practicability analysis considers direct costs for each
 disposal site.
Fl-24
       See comment Fl-23
Fl-25

       Capping has been successfully conducted at the Portland Disposal Site in
conjunction with dredging of the Federal Channel in 1980. Monitoring has shown
normal recovery of the benthic community.
Fl-26

       BLS is not biologically unique, and appears representative of the offshore
environment. This comment was not made to suggest minimal value of the area, only
to suggest that it is typical.

       Section 4.2 and Attachment I of the FEIS/R describe biological resources and
fishery usage very similar to the other offshore and inshore sites currently being
considered as potential disposal sites.
Fl-27
       Corrected.
Fl-28
       Additional information has been provided to NMFS.
Fl-29

       Section 4.2 and Attachment I of the FEIS/R present the findings of several
previous and on-going studies; and the results of a project sponsored sampling program
which evaluated the areal biological resources presented within the BHNIP project area
during the Fall  1994.  The FEIS/R states that lobster abundance and biomass were
greatest at the offshore stations during the Fall 1994 lobster sampling program (NAI

                                       «     "30

-------
1994). BLS was located within the offshore stations along with Meisburger 2 and 7,
and ranked slightly below both Meisburgers, according to these abundance and broman
data.  These data are also consistent with MADMF sampling data.  A review of
historical data indicate an overall consistency in inshore and offshore finfish communi-
ty structure during the past 10-15 years.  Whiter flounder are the most important
demersal fish species throughout the BHNIP project area. Other flatfish significant to
the project area include yellowtail flounder, American dab and windowpane flounders.
In less abundance than the flatfish, cod family appears to be significant, especially in
the offshore area where Atlantic cod, silver and red hake, and pollack were consistent-
ly present in all  catch results.  Data from our study indicated the abundance of pelagic
fish resources  was highest at some inner harbor stations and the offshore stations.
Abundance of pelagic fish resources was lowest at the remaining inner harbor stations
and the outer harbor stations.
Fl-30

       Water quality modelling was one of numerous factors taken into account to
evaluated the suitability of the aquatic sites for disposal of silts from the BHNIP
(Section 4 of the FEIR/S). As a result of the reevaluation of the alternatives, the
Boston Lightship and Meisburger sites were found not to be among the least environ-
mentally damaging aquatic alternatives.
Fl-31

       Section 4.2 and Attachment I of the FEIS/R present the findings of several
previous and on-going studies; and the results of a project sponsored sampling program
which evaluated areal finfish catch data during the Fall 1994. Again, a review of
historical data indicate an overall consistency in inshore and  offshore finfish communi-
ty structure during the past 10-15 years.  Whiter flounder are the most important
demersal fish species throughout the BHNIP project area.  Other flatfish significant to
the project area include yellowtail flounder, American dab and windowpane flounders.
In less abundance than the flatfish, cod family appears to be  significant, especially hi
the offshore area where the Atlantic cod, silver and red hake, and pollack were
consistently present in all catch results. Data from our study indicated that abundance
of pelagic fish resources were highest at some inner harbor stations and the offshore
stations.  Abundance of pelagic fish resources was lowest at  the remaining inner harbor
stations and the outer harbor stations.
 Fl-32

       Preliminary evaluations of wave induced bottom velocities (Roberge, 1995)
 have shown that relatively frequent storm events will generate bottom velocities
 sufficient to resuspend bottom sediments. While these analyses were not exhaustive,
 they certainly demonstrate that unprotected deposits of unconfined sediments would be
                                         7 '

-------
 resuspended at the Meisburger 2, Meisburger 7, and Spectacle Island CAD. Reference
 Section 4.0 and Appendix G of the FEIR/S.
 Fl-33

       The selection process for the least environmentally damaging alternative for
 disposal of silt included evaluation of potential for bioaccumulation during and after
 disposal, including the likelihood of catastrophic events causing future dispersion of
 the silt.
Fl-34

       The description of sediment quality in the vicinity of Spectacle Island CAD has
been clarified in Attachment I.
Fl-35

       The discussion on cumulative impacts from the project has been expanded hi
the FEIS/S as suggested.  A discussion of vessel traffic on whales is discussed hi the
Biological Assessment.  Vessel traffic is not expected to have a significant effect on
whales.

       Disposal of dredged material will have a temporary impact on biological
resources in the area. In addition silty material disposed in the nearshore and offshore
areas will be capped, thereby isolating this material from biological resources.
Monitoring would be focused on physical parameters of the disposal site (i.e. cap
integrity).

       Attachment I of the FEIS/R details the population,  age and size structure of the
area! finfish community and benthic community during the Fall 1994 season.  Findings
of which are also consistent with other previous and on-going studies
Fl-36

       Section 5.0 of the FEIR/S describes the Dredging Management Plan and
addresses specific mitigation techniques to minimize fish mortality during blasting
operations. These techniques include operation of sonic fish "startle" systems and
installation of other control systems around each blast site. Such systems could include
pneumatic barriers which effectively attenuate the pressure wave generated by the
blast. These systems are proven and effective. In addition, as described in Section
5.2.1.5, Seasonal Limitations, blasting will be seasonally restricted to minimize
                                                   2.
                                                                                             «M

-------
exposure of anadromous fish to those operations.  The actual mitigation measure will
be defined during the permitting process.
Fl-37

       Section 6.0 of the FEIR/S discusses the proposed mitigation approach to
address losses of subtidal habitat.  BHNIP commits to investigating compensatory
mitigation , if required.  However, as stated in Section 6.4.4, the BHNIP, as designed
and with in-channel disposal, provides significant enhancement of project specific
principal valuable functions (see Appendix K).  As such, no compensatory resource
mitigation should be required under either federal or state wetland regulations.

       As local sponsor, Massport is willing to work with state resource agencies to
identify resource enhancement opportunities in the Harbor area.  As examples, these
can include:

       1.     Assisting the Metropolitan District Commission (MDC) hi their on-
going efforts in coastal resource restoration hi the Boston Harbor ACECs. The MDC
is currently planning projects at the Rumney Marsh and Neponset River ACECs.

       2.     Massport is committed to increasing the number of vessel sewage pump-
out facilities hi the Harbor area and will work with the appropriate agencies on
specific details.

       3.     Massport will also consider coordinating with the  Department of
Environmental Management (DEM) to identify potential areas of cooperation and
assistance in DEM resource and facility enhancement projects on Harbor islands.

       4.     Massport will work with state and local resource agencies to identify
potential resource enhancement options such as supporting the development of an
"urban fishing park" through rehabilitation of water access structures (e.g.,
boat ramp in Little Mystic Channel) to enhance public use and access to  functional
recreational fishing areas.
 Fl-38

        Coordination with NMFS and the Massachusetts Division of Marine Fisheries
 has resulted in the environmental restrictions displayed in the FEIR/S.
 Fl-39

        The referenced sentence has been changed.  It should be noted, however, that
 for the purposes of identifying sufficient capacity for disposal, the DEIR/S considered

-------
all of the silt to be unsuitable for unconfined open water disposal.  The FEIR/S
continues to treat all the silt as unsuitable for unconfined open water disposal.
Fl-40

       A fraction of the contaminated silts will likely be resuspended due to any  of
several mechanisms. Use of the "environmental" bucket will significantly reduce the
loss of the silts due to bucket overflow, adhesion to the bucket fixtures, and spillage
during bucket haul. Operator sensitivity to minimizing bucket impact velocities,
dragging, and other operational functions will be stressed hi the contract documents
and continuously evaluated by the Project Manager during dredging activities. Un-
skilled operators will be replaced. The environmental bucket is approximately 40 %
lighter per  footprint area than conventional clamshell buckets. The footprint area of the
environmental bucket can be approximately 60% larger than conventional buckets with
the same capacity. In addition, the bucket includes a horizontal closing action which
produces a level bottom cut. These features provide an optimum cleanup mode. The
bucket can be fully instrumented, including video cameras,  seal alarms, and depth
sensors, to  fully monitor performance.

       Bottom silts can potentially be resuspended by environmental and vessel
influence. These events are of relatively low frequency.  Sediment  movement will be
monitored during all phases of the project.  Any deposition of such mobile materials
over parent clays which have already been  exposed by prior dredging will be identified
and quantified. Any significant quantities could be removed prior  to dredging the
parent material. This would minimize commingling of the silt and parent sediments.
Fl-41

       The on-board Inspector serves as an agent to the US Army Corps of Engineers.
His purpose on the dump runs is to verify the location of the dredged material
disposal. The coordinates, based upon Loran fixes and/or satellite global positioning
system (GPS), is recorded on the log sheet which is prepared by the Inspector and
submitted to the Project Manager. "Short dumps" will not be allowed as a condition of
the permitted work. Disposal runs will not be performed in weather which will not
allow access to the designated dump buoy site.
       Additional information is contained in the Dredged Material Management Plan
described in Section 5.
Fl-42
                                       10

-------
       As stated in the EIR/S, documentation showing evidence of significant bioac-
cumulation in finfish is varied and difficult to document.  As stated in comment Fl-33,
even in supposedly pristine areas, contamination of finfish was evident.
Fl-43
       Corrected.
Fl-44

       Attachment I of the FEIS/R present the findings of several previous and on-
going studies which evaluate the periodic and overall state of the Boston Harbor
biological resource.  Also, presented are the findings of the Fall 1994 sampling
program for benthic resources, lobster and finfish resources.  All studies indicate a
relatively significant (non-statistical) ecological resource .
Fl-45

       Substrate conditions at all potential aquatic disposal sites were evaluated using
sediment profile imagery (Attachment I).  This technique provides insight into recent
geologic history of the substrate. The susceptibility to various erosional forces was also
evaluated (Appendix G)  and considered hi overall site evaluations.
                                         11

-------
     OFFICE OF THE
  REGIONAL ADMINISTRATOR
      \       UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
       S                        REGION i
      $             JOHN F. KENNEDY FEDERAL BUILDING
                    BOSTON, MASSACHUSETTS 02203-0001
                               j»
June 27,  1994

Dwight S.  Durham
Lt. Colonel,  Corps of Engineers
U.S. Army Corps  of Engineers
424 Trapelo Road
Waltham,  MA   02254-9149       "

Dear Lt.  Colonel Durham:

In  accordance   with   our  responsibilities  under  the  National
Environmental Policy  Act (NEPA) and Section 309 of the Clean Air
Act, we  have reviewed the  Draft  Environmental  Impact Statement
(DEIS)  for  the  proposed  Boston  Harbor Navigation  Improvement
project  (BHNIP).

This project  proposes to remove and dispose of approximately 3.3
million  cubic yards  (mcy)  of sediment from the Reserved,  Mystic
River,  and Chelsea Creek  Channels,   portions  of  the Main Ship
Channel, and  associated berthing areas in Boston Harbor in order to
increase  the navigational  efficiency  of Boston Harbor  for deep
draft vessels.   In addition to the above volumes,  the Corps will
need to  dredge  another 4.4 mcy of material  from the main channel
for future maintenance over  the next 50  years.   Recognizing the
importance that  this  project will have to improving navigational
safety and enhancing the economic potential of Boston's port, EPA's
review of the DEIS focussed on potential environmental  impacts that
need to  be addressed now  to avoid possible future  delays.   We
appreciate the  opportunity to work with  the Corps to ensure that
this project  is conducted in the most environmentally  sound manner
possible.

The DEIS evaluates two sets of alternatives - dredging alternatives
and disposal  alternatives for the  dredged material.  Alternatives
to the proposed  dredging include:   maintenance dredging only; the
full project (maintenance  and improvement   dredging) ; a  reduced
project  (e.g., eliminating portions of the project,  such as channel
dredging);  a  delayed  project; and No Action  (no  maintenance or
improvement dredging) .   Alternatives  to disposal include a number
of land-based and aquatic-based options, alone and in combination
with each other, however the DEIS identifies the preferred options
to  include the  full  dredging project with disposal at  Boston
Lightship (BLS) ;  the  Massachusetts  Bay Disposal Site  (MBDS) ;
Meisburger 2; Meisburger 7; or Spectacle Island Confined Aquatic
Disposal  (CAD).

            iomments

Based on our  review of the DEIS, we believe  that the analysis does
not  provide  the  information  necessary  to  fully evaluate  the
> Recycl»d/Recyclable
  PnnieOwMftSoy/Canoialnx on paper i
  contains •: least 75% recycfedtoer

-------
practicability and potential environmental impacts of many of the
disposal site alternatives.  We do believe, however,  that while
more information is necessary, the analysis indicates that the
In-Channel disposal option is environmentally preferable over the
other options presented.   Further, EPA does not consider either
MBDS or BLS to be viable disposal options for contaminated
material and we thus would oppose the issuance of an ocean
dumping permit for disposal and capping of contaminated material
at these sites.  Also, this project provides an important
opportunity to investigate promising new dredged material
treatment technologies, to resolve issues surrounding capping in
deep ocean waters, to  implement beneficial uses of the clean
dredged material and to demonstrate new types of reuse to enhance
habitat, shorelines, or recreational opportunities.  Although
these issues are briefly discussed in the DEIS, the Final EIS
should fully examine and commit to specific actions to implement
these measures.  EPA is eager to assist in this regard.  Each of
these concerns are summarized below and, along with other
comments, detailed in  the Attachment to this letter.

•  The Final EIS must  present more information on, the site-
specific biological resources present at the proposed dredging
and disposal sites and a more rigorous evaluation and comparison
of the impacts to these resources.  Much of this information has
been generated by the  MWRA or other researchers as part  of
studies conducted for  the  Boston Harbor cleanup or the Central
Artery/Third Harbor Tunnel project, and should be presented  in
the Final EIS to provide the public an opportunity to understand
and weigh the potential costs and  benefits of disposal options.
Further, we believe the EIS should more thoroughly identify  and
evaluate potential mitigation measures at  both dredging  and
disposal sites.   For  example, the  Final EIS should discuss the
measures to be  used to prevent  cross-contamination of  clean
material,  and to  ensure that only  suitable material  is being
disposed of at  the MBDS.

 •  Based on the Ocean Disposal  Criteria regulations  at 40 C.F.R.
Part  227,  EPA believes that all of the  surface sediments from the
BHNIP and  its  associated berthing  areas do not meet  the discharge
criteria and therefore are not suitable for uncontrolled ocean
disposal.   Of the total volume to  be dredged,  our interpretation
of the data indicates that 1.3 mcy is contaminated with metals,
PAHs,  PCBs, and other chemicals and is thus unsuitable for
unconfined open water disposal, as regulated under the Marine
 Protection, Research and Sanctuaries Act (33  U.S.C.  §§ 1401 er
 seq.)  (MPRSA).   The contaminated material constitutes essentially
 thfiaintenance portion of this project,  while the remaining two
 mcy constitutes the improvement portion.   This position is
 outlined in our September 9, 1993, letter to Colonel Brink
 Miller, which reviews the chemical and biological data and the
 relevant regulatory provisions supporting our conclusion (copy
 attached).

                                  37

-------
•  EPA believes that capping of contaminated dredged material has
not been shown to be an effective, environmentally sound approach
to disposal of contaminated sediments at deep water sites -like the
MBDS  or the  Boston  Lightship  Site BLS.    Based  on this,  and
consistent  with   the  Massachusetts  Coastal   Zone  Management
certification  requirements,  EPA's  designation of  the MBDS  for
dredged  material  disposal prohibits  disposal  of  contaminated
dredged material at the site, with or without capping (58 Fed. Reg.
42496).     While  the  DEIS  acknowledges   this  prohibition,  it
identifies disposal and capping of  the contaminated materials at
either the MBDS  or the BLS as preferred alternatives.   The DEIS
also suggests that perhaps the BHNIP's contaminated sediments could
be used as a demonstration project at the MBDS.

EPA does not, believe that dumping-and-capping at the MBDS or BLS,
either as a legitimate disposal option or  as  a demonstration, is
acceptable.    As we  have  discussed previously, however,  we are
happy to participate in a demonstration project at the MBDS to help
settle  the scientific  uncertainty  surrounding  this  issue,  but
maintain that such a  project can  and should be  conducted with
uncontaminated material (perhaps  using tracers as  appropriate to
track material movement) .

•  We believe the near-shore disposal options are more promising,
however, more complete  information on  the existing  biological
resources and the  potential environmental  impacts  that disposal
would have on those resources must  be  provided to  fully evaluate
these  options.  As mentioned  above,  based  on the information
provided thus far,  we believe that the In-Channel alternative has
a number of logistical and  environmental advantages over the other
options considered — in particular its small footprint, or total
area  of  impact,  in  an area that has  already been  disturbed by
previous dredging operations.  We  realize that, as presented, this
alternative does not accommodate disposal  of  future maintenance
dredging material.   We recommend, therefore,  that  the Final EIS
evaluate alternatives that would combine the In-Channel  option with
another  option(s)  that can  accommodate all  or portions  of the
future maintenance material.

•   We also believe the EIS  should provide a more  rigorous and
thorough examination of alternatives that combine several disposal
options to meet current and future project needs. In our view, the
current analysis fails to  fully explore these options or provide
the detail necessary to sharply define and  fully evaluate whether
these  options are preferable  from either an  environmental or
practicability standpoint.   We further  believe  it is  inappropriate
to dismiss combination alternatives as not practicable based solely
on costs or the  inability  of  any  one  of the sites to accommodate
the  full volume of material.   For a dredging project  of this
magnitude, we believe that limiting  the final  list of disposal
options to those that will  accommodate  the  full volume  of material

-------
                  constrains
                                4

                               the
analysis   of   practicable
inappropriately
alternatives.                                          •  -

•  The Draft EIS discusses the potential  for  demonstrating some
experimental technologies for dredged material treatment, but- does
not go far enough in realizing the potential this Pr°3jff * Pose s for
demonstrating new techniques for dredged material m an agem «£•  *»
we embark on one of the largest dredging projects that New England
hasten  we must  seize this opportunity to  demonstrate creative
anl fnnovaSve technologies  and techniques that  may_be useful in
the future.   We strongly recommend that the Final  . EIS .outline »
series of demonstration projects to be conducted, including te*ts
of new technologies such as stabilization and *°d»
projects.

•  The Final  EIS should also more  fully  explore the traditional
options  for  beneficial reuse  of the  two mcy  of uncoijtaf^la^f
material and the 132,000 cy of rock material to be generated by the
B£XP.   We recommend that in  the Final EIS the Corps Commit to
specific  reuse goals  for  options  identified  in the  Draft EIS,
including  highwly  construction,   landfill  cover,  construction
aggregate and other commercial reuses.

For the  reasons discussed above, EPA- has  rated this EIS "EO-2 -
invironmental objections-Insufficient Information"  in accordance
with  EPA's national  rating system,  a description of  which is
atSched to 4is letter.   This rating is bas •* « »^~3TST
of the -preferred disposal options," — excluding the MBDS ajdj^,
whiS  ale environmentally unacceptable for contam inated d re dged
material disposal —  and  our  conclusion  that  the project  couia
cause  significant environmental impacts that must be avoided  and
that  additional  information  is required to  fully  "••«  ™
project's impacts,  alternatives, and mitigation.  We believe  the
concerns we have identified can be resolved and that we can,  in the
course of this project, demonstrate new technologies  and onions
for  dredged material  management that will serve us well in  the
future.   We look forward  to working  with the Corps to  that end.
Please feel  free to call  me  (617/565-3400) or Patience Whitten of
my staff  (617/165-3413)  if you wish to  discuss these comments
 further.

 Sincerely,
 fbhn P. DeVillars
 Regional Administrator

-------
                            Attachment

                        DETAILED COMMENTS
Dredging;  The DEIS states that an  environmental  bucket will be
used to dredge the contaminated silt material and a  standard dredge
will be used to  dredge  the clay.   What method will be used to
determine when it  is appropriate to change dredging equipment?

The DEIS acknowledges that the dredge operator will likely pick up
debris of a wide variety.  The document discusses briefly steps to
be taken by the dredge operator if he encounters debris that will
not  allow  the dredge  to close properly.   The  Final  EIS should
outline a contingency plan and proper disposal methodology if the
contractor picks up debris  (i.e.  unidentified  55 gallon drums,
etc.) inappropriate for  the designated disposal  site.

The  DEIS states  that  blasting of  rock material will be done, but
does not discuss potential strategies such as  timing restrictions,
bubble  curtains  or other techniques that  could be instituted to
minimize  fish mortality.    If these techniques  are  not  being
considered, please provide an explanation  as  to  why they are not.

Depending  on which disposal  option  is  selected,  the  Corps has
suggested  eelgrass and  saltmarsh planting  as  mitigation.   EPA
recommends  that in that instance,  the Corps  convene  a panel of
experts to  provide suggestions  on  the  specifics  of  any  such
planting efforts.  This is currently being  done for an eelgrass
planting project in Narragansett Bay to much  benefit.

suitability  Determination:  As  stated in our September 9,  1993
letter  to Colonel Brink  Miller,  EPA believes  that all  of the
surface sediments from the BHNIP and its  associated berthing areas
are  not suitable for uncontrolled ocean disposal  under  the Ocean
Disposal Criteria regulations at 40 C.F.R. Part 227.  We reiterate
those comments here.

The  Corps characterizes  the testing of materials for acceptability
for  ocean dumping as "not clearcut" owing to the need to interpret
"ecological  significance"  of  biological  test  results  (DEIS, p. 3-
5).    While  we   agree  that  there   is  a  great need  for better
understanding of the effects of pollution on complex coastal and
marine  ecosystems, EPA found numerous"concerns with the biological
test data for the maintenance material from the project leading us
to conclude  that  it  was  not suitable  for  ocean  dumping  (see
attached letter).  The sediments from the federal Reserved Channel,
however,  are insufficiently  described  to  allow  for  a   sound
determination of suitability  because of  the  high detection limits
achieved for organic contaminants.  EPA repeats its recommendation
that additional  bioaccumulation  testing  be  conducted  for  these
sediments  in order to assess compliance with EPA's Ocean Dumping

-------
Criteria  ("ODC").   EPA recommends that the  Final EIS  rank the
contamination levels of the sediments to be dredged from different
areas of the project,  discuss any uncertainties in the ranking and
explain the  level  of  contamination and type of potential impacts
that lead to an unsuitability determination.

Also note that the DEIS seems to confuse EPA's and the Army Corps'
positions on the suitability of  materials  of  uncontrolled ocean
disposal.  On page 2-14 the DEIS recognizes that EPA and the Corps
have interpreted the  test results differently for the  Army Base
berths, Conley Terminals, Boston Edison Barge Berth, and Gulf Oil,
however,  a  later statement  suggests that the material  from the
Reserved  Channel  is  the  only  material  for  which a  consistent
opinion was  not  reached (DEIS,  p. 3-5).   We share this confusion
given  what  seems  to  be  a change in  position  for the  Corps as
regards the sediments to be dredged from the Army Base Berths.  At
a   meeting   in  Portland,   Oregon   (minutes  attached   to  the
aforementioned letter)  it was EPA's understanding that the Corps
had agreed that  the Army Base Berths were not suitable for ocean
dumping because of the significant amphipod mortality exhibited in
the  toxicity  tests  (disposal  of  dredged  material  exhibiting
significant  toxicity  is not authorized under the MPRSA and EPA's
ODC regulations  at  40 C.F.R. Part 227).

Since the alternatives  analysis presented in the DEIS is based on
the Corps' interpretation of the  test data, EPA requests that the
Corps seek alternatives (other than disposal-and-capping  at either
the MBDS  or the BLS)  for the  dredged material  determined to be
unsuitable for ocean disposal by EPA.  Section  103 (c) of  the MPRSA
specifically states that w.. .In any case in which the Administrator
disagrees  with  the  determination of the  Secretary  as  to the
compliance with the criteria established pursuant to section 102 (a)
relating  to  the effects  of  the dumping  or  with the restrictions
established pursuant to section 102 (c), relating to critical areas,
the  determination  of   the  Administrator  shall  prevail....11
Moreover, Section 504(c)(3) of the Water Resources Development Act
of  1992 amended  this  section to make written concurrence from EPA
a mandatory  requirement prior to  permit issuance.

Disposal  Alternatives

The DEIS evaluates a  number  of  upland, nearshore,  and  aquatic
disposal  sites as a possible disposal solution(s) for the Boston
Harbor dredged material.  These  options  were evaluated for  both
their  practicability  and their feasibility  based   on  various
screening criteria.   In  phase one  of a three-phased  screening
process,  the number of potential options were  reduced from 326 to
24  sites.   Using  these  24  sites,  the  DEIS evaluates  potential
combinations of  land-based and  aquatic-based options,  based on the
understanding that few sites are large enough to  accommodate the
full volume of  proposed  dredged material.   Ultimately, the  DEIS
identifies   five  disposal options,   all  aquatic-based,  as  the

-------
"preferred"  set  of options.  We have  a number of  concerns with
regard  to the overall analysis and the  elimination of  various
disposal options, as follows.

Preferred Alternatives:  The five options identified in the DEIS as
the "preferred alternatives" - BLS; MBDS; Meisburger 2; Meisburger
7; and Spectacle Island CAD - are part of  a larger set of options
considered  practicable by  the  Corps and  evaluated in the DEIS
(these  other practicable sites  include In-Channel  Sites;  Little
Mystic Channel; Reserved Channel; Amstar; Mystic Piers; and Revere
Sugar).

Overall,  we believe the DEIS does  not provide the  information
necessary to fully evaluate the potential environmental impacts of
the practicable  disposal options.    Further,  with regard  to the
preferred options in particular, we are concerned that these sites
have  been  too  narrowly evaluated  based  on whether  they  can
individually  accommodate  the full  volume of  proposed  dredged
material.    The  DEIS  states  that other  constraints,  including
environmental  and  social impacts,  were factored  into the final
choice of preferred options, but it is unclear how they were used.
For example, the DEIS states (p.  ES-3) that combining more than one
site would cost at least $10 million  more  than using any one full
capacity site. The DEIS does not, however, provide cost projection
data to validate this  assertion.  Since it is not  at  all obvious
that multiple disposal site  options, whether  on  land or  in the
water, would always cost more than any single  site, the Final EIS
should explain the assumptions and calculations that  go  into the
cost comparisons and conclusions.

Finally, we believe the decision to advance only those options that
can accommodate the full volume of material skews the alternatives
analysis  and compounds  the difficulty  of  objectively  comparing
disposal  options.   Our  more  specific  comments on  the  Preferred .
Alternatives are as follows.                                     J

In-Channel Disposal (ICD^;   While a number  of concerns remain about
the feasibility of this disposal option, based on the information
presented,  we believe that  this  alternative  has a  number  of
logistical   and  environmental  advantages  over   other  options
considered that make it the most promising solution.

In-channel  disposal  sites  have the  advantage of  minimizing the
footprint or total area of impact.   Additionally, resources in
these  areas will  already   be impacted  due to  the dredging,  so
disposal activities will be affecting a disturbed community versus
an undisturbed biological  community  at  some other  disposal site.
Furthermore, these channels will be used for heavy shipping traffic
in the  future so  they will already  be subject to environmental
degradation.

-------
                                8

The DEIS states, however, that  the  In-Channel alternative cannot
accommodate all the silt from the BHNIP. The reasons for this need
to  be  explained,  the  amount  of  silt  left  over needs to  be
Quantified,  and  alternatives  for  this  material  need  to  be
evaluated.  While, according to the  DEIS,  we  understand that,  as
envisioned,  this alternative  does  not  accommodate disposal  of
future maintenance material, we believe the FEIS should evaluate
whether another option(s)  could be combined with this alternative
so  as  to  meet  all  or  portions  of  the  future  maintencince
requirements.

MSDS and Boston Lightship;  The DEIS is unclear about potential use
of the MBDS or BLS for contaminated material disposal.  According
to the DEIS, use of the MBDS is being considered only for the two
mcy of  "clean" material and only after first evaluating potential
beneficial uses  of the  dredged sediment.   While use  of the MBDS
with  capping  is  discussed  in relation  the  disposal  of  the
contaminated  silt, the  DEIS . acknowledges that this  option  is
H	not implementable at this  time..."  (DEIS, p. 3-11) based on
judgements  by EPA and the  MCZM that such  use as  proposed  is
prohibited without a  demonstration  of its effectiveness.  Later,
however,  the DEIS does seem to-indicate  a desire to  conduct a
demonstration project to test the efficacy  of  capping at  the MBDS
 (DEIS,  p.  3-11),  perhaps  utilizing  the entire  1.3  mcy  of
contaminated material.

Dumping of dredged material outside the territorial sea baseline is
subject to the MPRSA  and  EPA's ODC regulations at 40 C.F.R. Part
227    Two of the Corps'  alternative sites, the MBDS and  the BLS,
are located in MPRSA-regulated waters.  EPA believes that dumping-
and-capping has not been shown to be an effective,  environmentally
sound approach  to disposal  of contaminated sediments  at such
relatively deep water  sites.    Additionally,  for  the  MBDS,  the
Massachusetts  Coastal Zone Management (MCZM)  certified  the MBDS
designation with the  condition that no contaminated sediments be
dumped at the site, at least until capping was  proven  effective.
Accordingly, EPA's designation included this restriction and, thus,
dumping-and-capping  of  contaminated  sediments  is   currently
prohibited at  the  site.

We know  of no instances  where capping  has been  successfully
 demonstrated at depths similar  to the MBDS  or BLS elsewhere in New
 England,  as is claimed in the  DEIS  (DEIS,  p.  3-11).  The deepest
 sites where disposal-and-capping has shown  to be effective are the
 New London Disposal Site  (NLDS) and the Central Long Island Sound
 Disposal Site  (CLISDS), where depths average 70 feet.  We are aware
 that the Corps believes that capping is effective at the Portland
 Disposal Site  (where depths  average 140 feet)  but have not seen
 such studies despite  asking  for them on numerous occasions.  &iven
 that there is  generally greater dispersion with increasing depths,
 EPA  believes  that the studies at  the  NLDS  and the  CLISDS  are
 inconclusive in demonstrating the effectiveness of capping at the

-------
MBDS and  the BLS, where depths average  300  feet and  200 feet,
respectively.

The DEIS fails to  disclose the scientific and public controversy
surrounding both the technical feasibility and legality of dumping-
and-capping contaminated sediments.   In designating the MBDS for
dredged material  disposal,  EPA  received  many public  comments
opposing any disposal of contaminated dredged material at the site,
with or without  capping.   Capping  at  such a site was regarded by
commentors as infeasible or, at best,  unproven.  Commentors noted
that  the proximity  of  the  MBDS  to the  western  edge  of  the
Stellwagen  Bank  National  Marine Sanctuary  provides  further
justification for  taking a conservative approach to proposals to
dump-and-cap contaminated  sediments.    The view that capping is
unlikely to  be  effective  at a deep  water site, or  is  at least
unproven, is also  repeatedly reflected in  the comments  of other
federal and state agencies  and members of the public that have been
submitted on the BHNIP (DEIS, Appendix A-3).

While the  BLS  is  not  as  near  to  the Sanctuary,  we believe the
technical concerns regarding the feasibility of capping at the. BLS
to be virtually identical to  those for the MBDS (see 9-27-91 letter
to  Corps).   At  BLS,  however,  these  concerns  are heightened by
unknowns about the  locations  of drums of industrial  and radioactive
waste; a productive winter flounder fishery; its location within a
major traffic lane; and the need to go  through an EPA-approved site
designation  process.    Based  on  our experience  with  the  MBDS
designation, such a process would surely be lengthy, controversial,
and expensive.1

Finally, regarding a demonstration project, we do not believe that
the disposal of  1.3 mcy  of contaminated silt  from the BHNIP is an
appropriate vehicle with which to test the effectiveness of capping
in a deep ocean  environment.  We concur, however, and have stated
previously that  a  demonstration project - using dredged material
that meets the  requirements  of the ODC - would be useful to help
resolve the uncertainties  of this disposal  technique and we stand
ready to assist  the Corps  in its design and implementation.
     1  While the technical concerns are sufficient reason for EPA
to oppose dumping-and-capping of contaminated sediments at the MBDS
or the  BLS,  there are also  legal  issues.   Whether the MPRSA and
EPA's ODC regulations simply forbid the dumping  of any  dredged
materials that fail the biological  tests, regardless  of proposals
to cap  the materials, has  been  a matter of  some  controversy.  EPA
is presently evaluating  this legal issue to develop  a definitive
agency  position on it, but since we presently would oppose dumping
and capping  at the two proposed MPRSA-regulated sites on technical
grounds,  it  is not critical  that  we resolve this  legal  issue in
order to respond  to the proposed BHNIP  alternatives.

-------
                                        10

         It should  also be  noted that  a proposal to  dump contaminated
         sediments (i.e.,  unsuitable for ocean disposal)  at the MBDS, with
         or without capping, would clearly trigger the requirement of formal
         coordination with the  Secretary of Commerce regarding  potential
         effects  on  the  Stellwagen  Bank National  Marine  Sanctuary  as
         provided for in the October 1992 amendments to  Section 304 of  the
         MPRSA (DEIS, p. 3-31).   See Sections 2104 (d)  and 2202 (e) of  the
         National Marine Sanctuaries Program Amendments Act of 1992  (P.L.
         102-587).  Such a proposal  would also require EPA to modify  the
         MBDS site designation, which is  currently limited to disposal of
         dredged material meeting the requirements of  the  MPRSA  and  its
         accompanying regulations.   This would require  initiation  of  a
         formal  rulemaking  process,   and  MCZM  certification   of   the
         modification.   Finally, the National Marine Fisheries Service, in
         an April 19, 1993 letter, has indicated that  it believes dumping-
         and-capping at the  MBDS  has not been shown to  be effective, .and
         that such  an alternative  should be  dropped,  or further formal
         consultation and  analysis  will  be needed under the  Endangered
         Species  Act regarding potential effects of  such  an  action  on
         endangered species and their habitat.

         Aquatic Disposal Alternatives Governed by Section 404 of the  Clean
         Water Act:   In general, near-shore, relatively shallow water offers
         more controlled conditions  that are more conducive to  effective
         capping.  There has been notable experience with capping in such
         waters, some of it  successful  and some of it  unsuccessful.   Some
         failed  caps at  the  Central Long  Island Sound  Disposal  Site have
         exhibited  significant  mortality,  incomplete  covering  of  the
         contaminated   material,   partial   diffusion    of   contaminants,
         bioaccumulation in  biota recolonizing the  cap, and  significant
         erosion of the cap  from hurricanes.

         We believe the DEIS should discuss in detail both the failures and
         the  successes  in   capping  experiments so  that the  public  may
         accurately assess the efficacy of capping.  Given the uncertainty
         of  capping,  we would  require  detailed resource information and
         impact  analysis  before approving use of  any  of these  potential
         sites.

         Decisions  regarding sites  landward of the  territorial  sea are
         subject to the Clean Water Act Section 404(b)(1) Guidelines found
         in  EPA regulations at 40 C.F.R. Part 230.   Dumping-and-capping
         contaminated sediments are  not per se barred  in such waters, but
         the   404(b)(l)   Guidelines'  alternatives  analysis   tests  and
         environmental impact criteria must be satisfied.

         Combination Alternatives;  We believe the combination alternatives
         analysis fails  to  provide the  detail necessary to sharply define
         and fully evaluate  either the practicability or the environmental
         impacts of these alternatives as disposal  options.  In particular,
         we  believe this  discussion presents numerous conclusions  about
         logistics, cost, and other constraints that are unsupported  by the
>H

-------
                                11

analysis and that the basis for these conclusions need to be more
thoroughly documented in the Final  EIS.  While these instances are
too numerous to cite, the following example is illustrative.

With regard to Option A3, a land-based alternative, the DEIS states
that "(significant drawbacks include long-term management of three
sites along with  attendant  costs....and on-site and neighborhood
impacts  from  constructing the facilities and transporting  up to
55,000 truckloads of silt  to  the sites."  (DEIS,  p. 3-13).   No
analysis is provided, however, of what long-term management entails
and we are thus unable  to evaluate whether such a requirement is
preferable over the environmental or other impacts associated with
other disposal options.                                           '

In addition, while on its face, the truck traffic projected seems
potentially significant, no analysis  is provided of what the actual
impacts  may be (e.g.,  impact  on roadways, disruption  of normal
traffic patterns, alternative routes that may have less social and
environmental impacts,  air quality impacts).

Finally, while in some instances the DEIS states that alternatives
to truck transport exist (e.g., barging is feasible for Option A3) ,
it  does  not fully  evaluate those  alternatives.  We believe the
analysis  should  identify what  alternatives  to  truck   transport
exist, such as rail or barge, and what their relative environmental
and social  impacts would be.

Beneficial  Usest   We  believe the DEIS  provides an insufficient
analysis of the potential beneficial uses of the projected two mcy
of clean, "parent" material and 132,000 cy of  rock.   Failure to do
this does not meet  requirements under NEPA to fully evaluate such
options.   Statements such  as "Each  option assumes that dredged
parent material  and rock will be used for beneficial uses to the
maximum  extent possible and that these uses will be  identified and
expanded throughout the EIR/S process" are inadequate under NEPA
because  they  ignore  requirements  to  fully  disclose   potential
impacts,  both positive and negative, and fully inform the  public
and allow for public input  before  a decision  is finalized.

As the DEIS acknowledges, the significant volume of  clean sediment
from the BHNIP provides a rare opportunity to  realize  beneficial
uses.  The DEIS falls far short, however, of what is required under
NEPA to  fully examine  such options.

Treatment Technologies - While it  is evident  from the analysis  in
the DEIS that treatment technology cannot, at this time, provide a
practical solution  to  the disposal  of the BHNIP's contaminated
dredged   material,   we  believe this  project  does provide  an
opportunity to conduct  a demonstration project that may begin  to
resolve  some of the outstanding issues that such methods as these
present.  In particular, the Corps  should  investigate  the  use  of

-------
                                12

geotextile  bags to  isolate the  contaminated dredged  material;
solidification; and incineration to create construction aggregate.
CEQ regulations define indirect impacts as those effects that are
".... caused by the action and are  later in time or farther removed
in  distance,  but  are still  reasonably  foreseeable.11   Indirect
impacts  include "—.growth-indueing effects  and other  effects
related to induced changes in the pattern of land use, population
density or growth rate,  and  related  effects  on  air and water and
other  natural  systems,  including ecosystems."    (40 CFR,  Sec.
1508.8(b))

A cumulative  impact  is "....the impact on the  environment which
results from  the  incremental impact of the  action when  added to
other  past,  present,  and  reasonably foreseeable  future  actions
regardless  of  what  agency  (Federal or  non-Federal) or  person
undertakes such other actions." (40 CFR,  Sec. 1508.7)

The DEIS states that the purpose of the BHNIP is to "....increase
navigational  efficiency  and  safety of Boston Harbor for present
types  of  deep drafted vessels that  are  currently transiting the
project area." (DEIS, p.  1-2)  We believe  the  analysis also clearly
indicates an underlying project purpose,  which is to bring Boston
Harbor  up to the  future operational standards  of  a major U.S.
shipping port by dredging beyond maintenance  depths to accommodate
the future class of deep-draft, double-hulled tankers.  The DEIS in
fact states, "....not dredging the Port may mean not being able to
attract new shipping business.  The ability to bring  in additional
shipping lines with large container ships and frequent schedules is
important for the future growth of the Port." (DEIS,  p. 1-4)

Given  this, we believe the DEIS  does not  adequately identify or
evaluate  the  indirect  and cumulative impacts  that  will  likely
result from the changes in type, volume,  and  frequency of shipping
traffic.   In particular,  we believe the  EIS should more fully
evaluate   the  potential  impacts   to   the  Port   and  related
infrastructure  (e.g.,  inland transportation  networks that may be
effected,  such  as  rail or  trucking;   off-loading   and  storage
facilities)  from  the  potential  increase  in  both volume  and
frequency  of  shipping traffic.   This analysis should include the
relationship,  if  any, between the potential changes in shipping
traffic and the proposed "inland port," which is an already partly
operating venture  (on an interim basis) between the Port of Boston
and Fort Devens in Ayer, Massachusetts.  (This should  include, for
example,  whether the  change in shipping traffic will stimulate
development at the inland port.  If so, this  should be identified,
along  with potential  impacts  from induced  growth at the inland
port).

-------
                                13
Further, this  analysis should  examine  the potential  impacts to
biological   resources,   especially   endangered   species,   in
Massachusetts  Bay and  Boston  Harbor from the  change  in vessel
traffic, as well as the relationship between any increase in vessel
traffic and the likelihood of spills (fuel oil,  ect.)-

-------
POLICY AND PROCEDURES
                              SUMMARY OF RATING DEFINITIONS
                                   AND FOLLOW UP ACTION
Environmental Impact of the Action

LO-Lack of Objections                                              .              .        .  ..,.
The EPA review has not identified any potential environmental impacts recurring substantive changes to me
proposal.  The review may have. disclosed opportunities for application of mitigation measures thai could
be accomplished with no more than minor changes to the proposal.


The EPA review las identified environmental impact that should be avoided in order to fully protect the
environment.   Corrective measures may require changes to the preferred
mitigation measures that can reduce the environmental impact. EPA would like
to reduce these impacts.

EO-Environmental Objections                                              .    .          „„„;**
The EPA review has identified significant environmental impacts that must be avoided in order to provide
adequate protection for the environment.  Corrective measures may require substantial changes to tne
preferred alternative or consideration of some other project alternative (including the no action alternate
or a new alternative).  EPA intends to work with the lead agency to reduce these impacts.

EU-Environmentally Unsatisfactory                                                    ,«,„,, *,«„*«,
7776 EPA review has identified adverse environmental impacts that are of sufficient magnitude that tney are
unsatisfactory from the standpoint of public health or welfare or environmental quality. EPA intends to WOK
with the lead agency to reduce these impacts.  If the potential unsatisfactory impacts are not corrected ai
  * final EIS stage, this potential will be recommended for referral to the CEO.

                Impact statement
 Category 1— Adequate                                                                         _/
 EPA believes that draft EIS adequately sets forth the environmental impact(s)ofthe preferred alternatives ana
 those of the alternatives reasonably available to the project or action.  No further analysis or data collection
 is necessary, but the reviewer may suggest the addition of clarifying language or information.

 Category 2-lnsufficient Information                                             .
 7776 draft EIS does not contain sufficient information for EPA to full assess environmental impacts tna< snouic
 be avoided in order to fully protect the environment, or the EPA reviewer has identified new reasonably
 available  alternatives that are within the spectrum of alternatives analyzed in the draft EIS, which could
 reduce the environmental impacts of the action. The identified additional information, data, analyzes or
 discussion should be included in the final EIS.

 Category 3-lnadequate                                                       .         . .     .
 EPA does not believe that the draft EIS adequately assesses potentially significant environmental impacts
 of the action, or the EPA reviewer has identified new. reasonably available alternatives that are outside oi
 the spectrum of alternatives analyzed in the draft EIS, which should be analyzed in order to reduce the
 potentially significant environmental impacts.  EPA believes that the identified additional information, data,
 analyses, or discussion are of such a magnitude that they should have full public review at a draft stage.
 EPA does not believe that the draft EIS is adequate for the purpose of the NEPS and or/ Section 309 review^
 and thus should be formally revised and made available for public comment in a supplemental or revised
 draft EIS. On the basis of the potential significant impacts involved, this proposal could be a candidate for
 referral to the CEQ.
                                                        IJ1

-------
              UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                                        REGION I

               J.F. KENNEDY FEDERAL BUILDING. BOSTON. MASSACHUSETTS 02203-2211
 September 9, 1993

 Colonel Brink Miller
 Division Engineer
 U.S. Army Corps of Engineers
 New England Division
 424 Trapelo Road
 Waltham, MA 02254-9149

 Re: Boston Harbor Dredging                   x

 Dear Colonel Miller:

 In response to our meeting of June 17, 1993, this letter presents in writing EPA's concerns
 regarding the federal and non-federal portions of the Boston Harbor dredging project.

 To date, our agencies have agreed that 1.8 million cubic yards of native marine clays and
 bedrock is suitable for ocean disposal. We have also agreed that 440,000 cubic yards of
 surface sediments from Prolerized, Distrigas, Moran, Mystic Piers, North Jetty, Eastern
 Minerals, the Mystic River, and the Chelsea River are unsuitable  for ocean disposal at the
 Massachusetts Bay Disposal Site ("MBDS").

 This letter therefore focuses on the remaining  163,200 cubic yards of surface dredged
 material (Reserved Channel,  100.000; Army Base Berths, 31,200: Conley Terminals.
 23,500; Gulf Oil, 4.900; Boston Edison Barge Berth. 3,600). EPA need's to have reasonable
 assurance that disposal of a particular dredged material will not cause a significant
 undesirable effect, or else such material cannot be approved for dumping in the ocean in
 accordance with the applicable regulations. EPA has assessed the tissue residue data in
 accordance with the Green Book bioaccumulation evaluative factors. . Our detailed technical
 rationale in light of the regulations, national guidance, and supporting scientific evidence car.
be found in Attachment A. These analyses have raised a number  of serious concerns abou:
 the suitability of these sediments for ocean disposal at the MBDS  under the Marine
 Protection, Research, and Sanctuaries Act and the federal regulations at 40 CFR §§  227.6,
227.13, and 227.27.  Therefore, given the magnitude of our concerns, EPA recommends that
the Corps focus their efforts on thoroughly exploring alternative methods of disposal for the
sediments in question. EPA  remains willing to participate in future meetings and  discussions
regarding our analysis or additional information.

As agreed at our meeting of June 17, 1993, representatives of our respective headquarters,
regional, and research offices have met to discuss the areas where our views differ on the
Boston Harbor project.  Our  understanding of the results of the meeting  is as follows:  1) we
agreed that the amphipod mortality data from the Army Base Berths renders those sediments^ *j_:«.
                                  PBINTE: ON BEC»C-I-

-------
 unsuitable for ocean disposal at the MBDS; and 2) that we did not reach complete agreement
 regarding the bioaccumulation issues.  The first item indicates that EPA and the Corps have
 now agreed, in  effect, that the Army Base Berth sediments cannot be dumped at the MBDS
 because of the amphipod toxicity from exposure to them.  Although we did not reach  total
 agreement in interpreting the bioaccumulation data, EPA believes that significant concerns
 regarding the data from the other three Massport berthing areas and the Reserved Channel
 were raised by a number of EPA and Corps participants.  It was evident that a number of
 participants believed that a suitability determination could not be made on the existing
 bioaccumulation data from the Reserved  Channel and retesting should be required if the
 ocean disposal option for the surface sediments is still pursued.  EPA's summary of this
 meeting is included  in Attachment B.

 As added evidence to support our concerns, EPA .has also estimated effects to human health
 from the consumption of seafood from the MBDS feeding on benthos exposed to the four
 Massport berthing areas in question.  This conservative assessment is consistent with the risk
 assessment approach used in several EPA programs.  Our preliminary assessment indicates
 that disposal of the surface sediments from the Army Base Berths. Conley Terminals, Gulf
 Oil. and the Boston Edison Barge Berth could pose unacceptable cancer risks to human
 health. This information indicated another reason to be concerned regarding the suitability
 for ocean dumping. An explanation of our risk assessment can be found in Attachment  C.

 We  understand that the COE is currently preparing an Environmental Impact
 Report/Environmental  Impact Statement ("EIR/EIS") in accordance with the National
 Environmental Policy Act for the Boston Harbor dredging project.  EPA recognizes thai
 determining suitability of dredged material for ocean dumping is relevant to the EIS/EIR's
 evaluation of reasonable disposal  alternatives for the dredged material. EPA has beer,
 actively working with the COE during the preparation  of  the EIS/EIR. as part of an
 interagency workgroup, to help identify potential disposal options to be examined in the
 EIS/EIR. It is apparent through our participation on the workgroup  that alternatives other
 than disposal at the MBDS may be viable.  We look forward to the opportunity to reviev.
 and  comment on the full analysis  in the EIS/EIR once  complete.

 In summary, EPA and the COE have agreed that the surface sediments from the Army Base
 Berths are unsuitable for ocean dumping at the MBDS. EPA also  believes that a significant
 number of concerns regarding -Gulf Oil, Conley Terminals, and the Boston Edison Barge
 Berth have been raised to recommend that alternatives  for disposal - other than ocean
 dumping at the MBDS - should be investigated.   If ocean  dumping is pursued for the surface
 sediments of the federal portion of the Reserved Channel, EPA believes that the sediments
need to be further characterized.  In particular, we believe that additional bioaccumulation
 testing is needed.

 At the meeting between EPA and the COE in Portland, Oregon, the COE's Waterways
Experiment Station  offered to host an additional meeting among our agency experts to further
discuss interpretation of the Massport and  Reserved Channel data.  We are prepared to meet
with you and look forward to coordinating with  you on this project and to attaining a

-------
mutually' acceptable solution to the disposal issue.  Please do not hesitate to contact
Kymberlee Keckler of my staff at (617) 565-4432  should you have any questions.

Sincerely,
Paul G. Keough. Acting
Regional Administrator

Attachments

cc:    Thomas Fredette. USACOE, Waltham. MA
      John Catena. NMFS. Gloucester, MA
      Vern Lang.' USFWS. Concord, NH
      Judith Pederson. MCZM, Boston, MA

-------
                                   REFERENCES

 Biddinger, G.R., and Gloss, S.P.  1984.  The importance of trophic transfer in the
       bioaccumulation of chemical contaminants in aquatic ecosystems. Residue Rev.
       91:104-130.

 Clarke, Joan. Alfreda Gibson and Robert Engler. March 1987. Regulatory Identification of
       Hydrocarbon Contaminants in Dredged Material. Environmental Effects of Dredgir.g.
       Technical Notes. U.S. Army Ensineer Waterways Experiment Station. Vicksburs,
       MS.

 Dexter, Robert and Jay Field. September 1989. A Discussion of Sediment PCB Target
       Levels for the Protection of Aquatic Organisms. Seattle, WA.

 Field, L. Jay and Robert N. Dexter. January 1988. A Discussion of PCB Target Levels in
       Aquatic Sediments. Seattle. WA.

 Kay, S.H.  1984. Potential for biomagnification of contaminants within marine and freshwater
       food webs. Tech. Rep. D-84-7,  U.S. Army Ensineer Waterways Experiment Station.
       Vicksburg, MS.

 U.S. Environmental Protection Agency  (US EPA). September 1989. Assessing Human
       Health Risks from Chemically Contaminated Fish and Shellfish:  A  Guidance Manual.
       U.S. EPA Office of Marine and Estuarine^Protection, Office of Water Regulations
       and Standards. Washington. DC.

 U.S. Environmental Protection Agency. September  1989. Guidance Manual:  Bedded
       Sediment Bioaccumulation Tests. Newport. OR.

U.S. Environmental Protection Asencv  and U.S. Arrnv Corps of Ensineers.  February 1991.
                             »   *              «     I       W               *
       Evaluation of Dredged Material  Proposed for Ocean Disposal (Testing Manual).
       Washington. DC.

-------
ATTACHMENT A

-------
 A.  ANALYSIS OF MASSPORT BERTHING AREAS

 I. Summary of the Biological Testing

 Eight of the Massport berthing areas were subjected to the biological tests prescribed in the
 national and regional testing protocols. Of the original eighteen, three were already
 determined to be unsuitable for ocean disposal without further testing (Prolerized, Distrigas,
 and Revere Sugar), five no longer pursued ocean disposal as an alternative (BMIP Piers"s &.
 6, Boston Edison Intake, MBTA Power Plant. East Boston Pier 3, and East Boston Pier 5).
 and two groups of wo berthing areas were combined  for one test (Conley Terminal Berths
 11 to 13 was composited with Conley Terminal Berths 14 & 15; Boston Army Base Berths 1
 to 3 were  composited with Boston Army Base Berths 4 to 9). These sediments were assessed
 for their potential to cause toxicity, either mortality or bioaccumulation, if disposed at the
 MBDS.

 All of the berthing areas exhibited at least 90 %  survival  in both the clams and the worms-.
 All of the  berthing areas exhibited statistically significant differences between the dredged
 material and the reference material for the.amphipod bioassay.  Mystic Piers, Moran
 Terminals, North Jetty. Eastern Minerals, and the Army Base Berths all exhibited greater
 than 20%  mortality over the reference sediment in the amphipod, Ampelisca abdita,
 stipulated in both the national and regional testing protocols.  Gulf Oil, Conley, and the
 Boston Edison Barge Berth did not exhibit greater than 20 % mortality over the reference
 sediment in the amphipod.

 All of the  test sediments exhibited statistically significant bioaccumulanon over reference of
 either metals, polycyclic aromatic hydrocarbons ("PAHs"), or polychlorinated biphenyls
 ("PCBs") (varying  degrees of each) in either the clam, Macoma nasuta, or the polych'aete
 worm. Nereis virens.  Seven of the sixteen PAHs tested were carcinogenic (prohibited from
 ocean disposal in other than trace  amounts per 40 CFR § 227.6(a)(5)).

 II. Detailed Description of the Bioaccumulation Assessment

EPA  evaluated the  biological test data from  the Massport project in light of the eight factors
listed in the Green  Book (EPA/COE, 1991) in order to evaluate compliance with the
Limiting Permissible Concentration- (40 CFR Pan 227) criteria regarding acceptability for
ocean disposal.  The eight factors  are listed  on page 6-6 of the Green Book and summarized
below. A  brief description of how this factor was used in making a determination regarding
acceptability for ocean disposal of the four berthing areas in question (Gulf Oil, Army Bases.
Conley terminals, Boston Edison Barge Berth) follows each of the factors.

 •  Number and the phylogenetic diversify of the species in which bioaccumulation from
dredged material is statistically greater than bioaccumulation from the reference material
       Berthing areas that exhibited bioaccumulation in both the clams and the worms were
       of greater concern (e.g.,  Gulf Oil, Army Base Berths, and the Boston Edison Barge
       Berth).

-------
   • Toxicological importance of and the number of contaminants for'which bioaccumulation
  from dredged material is statistically greater than bioaccumulation from the reference
  material
         All of the berthing areas exhibited statistically significant bioaccumulation of at least
         five chemicals in at least one species.                               "   -

         Contaminants prohibited in other than trace amounts (e.g., cadmium, mercurv
         organohalogens, carcinogens, oil) were also assessed (40 CFR § 227.6).  All'four of
         these berthing areas were contaminated with carcinogenic compounds and
         contaminants that are likely to bioaccumulate (and persist)  in the marine environment
         Gult Oil, the Army Bases, and the Boston Edison Barge Berth exhibited
         bioaccumulation of mercury in  the.ivorms. Conley Terminals exhibited
         bioaccumulation of mercury in  the clams.  Cadmium was not detected in the test
         organisms from any berth. PCBs were detected in the clams from Gulf Oil  and the
         Army  Berths and in  both clams and worms in the Boston Edison Barge Berth.

        The levels of PCBs in the tissues of both the clam and the  worm indicate the poterr.iai
        lor chronic effects in fish feeding on the benthos.  Adverse effects from PCS
        exposure were exhibited at residue levels as low as 0.1 mH/ks (Field, et aL, 1988).
        These effects included egg mortality and reproductive failure." Based'upon a food  '
        chain multiplier approach developed by EPA's Duluth laboratory, tissue residues in
        demersal fish are projected to be three-fold higher than in the benthos. Assuming that
        steady-state PCB residues in the clam and worm were not underestimated in  the 28-
        day test,  the PCB bioaccumulation data (clams exposed to sediments from Gulf Oil
        Army Base Berths, and Conley; and both clams and worms from the Boston  Edison
        Barge Berth) suggest that fish feeding off the benthos exposed  to rhese sediments
        could experience chronic effects from PCB residues alone.

 • Propensity for the contaminants with statistical^ significant bioaccumulation to biomasnir.-
 within aquatic food webs                                                          "  "
        Sediments exhibiting  the presence jjf PCBs.. chlorinated pesticides, or methyl mercurv
        were considered to have the potential to biomagnify (Biddinger and Gloss. *1984; Kay.
        1984).  Chlorinated pesticides were not detected in the sediments, and therefore'not"
        measured in the tissues.  Mercury was measured as total mercury, and as discussed
       above, was detected in the worms from Gulf Oil,  the Army Bases, -and the Boston
       Edison Barge Berth; and clams from Conley Terminals.  PCBs were detected in the
    .   clams from Gulf Oil and the Army Berths and in both clams and worms in the Bosto-
       Edison Barge Berth.

 • Magnitude by which bioaccumulation from the dredged material exceeds bioaccumulation
from the reference material
       All of the levels of individual PAH compounds in the tissues were below 80
       pans per billion ("ppb") and were less than an order of magnitude higher that
       the detection limits achieved (20 ppb).  Because the concentrations of each of
       the PAHs in the reference material was less than the detection limit, the
       magnitude of the bioaccumulation over reference was difficult to judse. EPA

-------
                  considered "statistical significance of effects at the 95 percent confidence
                  level" (40 CFR §227.6(c)) between the detection limit and the concentration
                  detected in the dredged material to indicate a level of concern.  EPA believes
                  that the levels of PAHs in the sediments could exert adverse ecological-impacts
                  during long-term exposures or through interactions with other classes, of  -
                  contaminants.

           • Magnitude oftoxicity and number and phylogenetic diversity of species exhibiting greater
           mortality in the dredged material than in the reference material
                  All of the berthing areas exhibited statistically significant differences between the
                  dredged material and the reference material for the amphipod (Ampeiisca abdita)
                  bioassay.  The Army Base Berths exhibited greater than 20% mortality over the
                  reference sediment in the amphipod, stipulated in both the national and regional
                  testing protocols.  Gulf Oil, Conley, and the Boston Edison Barge Berth did not
                  exhibit greater than 20% mortality over the reference sediment in the amphipod.

           • Magnitude by which contaminants whose bioaccumulation from the dredged material
           exceeds that from the reference material also exceed the concentrations found in comparable
           species living in the vicinity of the proposed disposal site
                  Data from organisms in the vicinity of the MBDS that are similar to those
                  organisms used-in the bioaccumulation tests are not available.  As a result,  this
                  factor was not able to be considered in the analysis.

           HE. Data Discrepancies

           Sediment chemical concentrations were  remeasured in the  sediments used for the biological
           tests to determine if the chemical concentrations were consistent with those detected during
           Tier II. We note that the PAH concentrations from the Conley Terminals and the  PCB
         . concentrations from the Boston Edison Barge Berth were below the original range  measured
           during  the Tier II. Since PAHs and PCBs were major "contaminants of concern",  EPA
           questions whether the bioaccumulation tests from Conley Terminals and the Boston Edison
           Barge Berth areas accurately represent the sediment quality and its potential to cause toxicity.
           including bioaccumulation, in the organisms present in the environs of the MBDS.  EPA is
           aware that the statistical analysis  performed by Wade Research, Inc.  indicated that  the
           sediments used for the Conley Terminal bioaccumulaiion test were representative of the
           sediments measured during Tier II. EPA's environmental research laboratory in
           Narragansett, RI has reviewed this analysis and believes that the statistical methods used are
           not appropriate.  Given the substantial variability In Boston Harbor sediments, this
          information heightens EPA's concern regarding disposal of these sediments.

           IV.  Summary

          EPA and the COE have agreed that the surface sediments  from the Army Base Berths are
           unsuitable for ocean dumping at the MBDS.  EPA also  believes that a substantial number of
           concerns regarding Gulf Oil, Conley Terminals, and  the Boston Edison  Barge Berth have
£•(,

-------
 been raised to recommend that alternatives for disposal - other than ocean dumping at the
 MBDS - should be investigated.                                              c


 B.  ANALYSIS OF FEDERAL RESERVED CHANNEL

 EPA provided letters to the Corps regarding  EPA's suitability determination and testins
 recommendations for ocean disposal of the Reserved Channel sediments on June 1~>  1991
 August 4, 1992, and May 27, 1993.

 I.  Toxicity Assessment

 EPA believes that the original (1990) amphipod tests conducted for the Reserved Channel
 which indicated statistically significant differences from the reference sediment and greater
 than 20% mortality than in the reference sediment may be considered questionable because of
 the extended  holding time of the sediments (John Scott, personal communication). Based on
 the results of two subsequent  tests on sediments near the same site. EPA concurs that the
 whole sediment toxicity requirements meet the LPC for this pan of the project.

 II. Bioaccumulation Assessment

 EPA has stated that the detection limits'achieved "for PAHs were much  higher than those
jointly recommended by EPA  and the COE in the regional testing protocol. Since these
 detection limits were at concentrations several orders of magnitude over those jointly
 recommended  by EPA and the COE? it is possible that any bioaccumulation could have beer.
 concealed. As a result, EPA believes that the sediments from the Reserved Channel are
 inadequately characterized.  Dredged material that is insufficiently described cannot be
 approved for ocean dumping under any circumstances  per 40 CFR  § 227.5(c).  Until ne-.v
 bioaccumulation testing is conducted, EPA cannot make a determination regarding
acceptability for ocean dumping.

-------
ATTACHMENT B


-------
                       SUMMARY OF JUNE 23, 1993 MEETING
                           REGARDING BOSTON HARBOR
                                 PORTLAND, OREGON


 EPA and the Corps met at the national ocean disposal coordinator's meeting in Portland,
 Oregon to discuss the federal and non-federal portions of the Boston Harbor dredeinE
 project. The list of attendees included:  EPA HQ (Craig Vogt, John Lishman. Dave=
 Redford, Catherine Crane, Tom Chase); EPA Region I  (Dave Tomey, Kymberlee Keckler):
 EPA's national ocean dumping expert from Region III (Bill Muir); E'PA ORD (Norm
 Rubinstein)] Corps HQ (Joe Wilson, Dave Mathis); Corps NED (Tom Fredette); and Corps
 WES (Tom Wright, Bob Engler, Tom Dillon).  Keckier provided copies of .the data.

 The discussion started with agency interpretation of toxicity data. Fredette stated that the
 Green book does not provide clear guidance when there is toxicity in only one of three
 species tested (i.e., toxicity in the amphipod, but no toxicity in the clam or worm). Keckler
 stated that the clams and worms were appropriate species for bioaccumulation, but not
 toxicity. Therefore, toxicity exhibited in one species, the amphipod. is sufficient information
 to declare the material unsuitable for ocean dumping.  Wright and Engler concurred with
 Keckler for the toxicity data from the Army Base Berths.  Wright stated that the new 404
 inland manual does not list the clam and worm as toxicity organisms because we have
 learned something since the Green book was published.  Interpretation of toxicity data in this
 manner enabled EPA and the Corps to declare the Army Base Berths unsuitable for ocean
 dumping.  Wright, Engler, and Redford all agreed that the Green book should be revised to
 reflect this.

 Regarding bioaccumulation, Keckler stated that her interpretation of the ocean dumping
 regulations was  that if there is not 'sufficient information to provide reasonable assurance that
 disposal of the material  will not cause an adverse effect, it cannot be disposed.  Rubinstein
 and Dillon stated that there is not much information concerning what level of contaminants in
 the tissues elicits an effect in an organism.  Most people agreed  that there is a need for 1) a
 manual to use in interpreting the results and 2) more research on tissue residues.

 Rubinstein read  from a memo by Henry Lee of EPA ORD in  Newport. Oregon that showed
 the levels of PCBs in the tissues from several berths are  projected to cause reproductive
 impairment in fish.  Adverse effects from PCB exposure were exhibited at residue levels as
 low as 0.1 mg/kg (Field, et al., 1988). The likely effect would  be reduced egg survival or
 similar reproductive impairment.  The clam bioaccumulation data from Gulf Oil, Army Base
 Berths and  Conley Terminals, and the clam and worm bioaccumulation data from the Boston
 Edison Barge Berths suggest that fish feeding  off the benthos exposed to these sediments
could experience chronic effects from PCB residues alone. Rubinstein further explained  that
a food chain multiplier approach developed by EPA's Duluth laboratory was applied to the
bioaccumulation data.  Specifically, tissue residues in demersal fish are projected to be three-
fold higher than in the benthos. These projections could be underestimated  if steady-state
PCB residues in the clam and worm were underestimated in the 28-day test.

-------
  Muir and Keckler explained that, using the 8 factors in the Green book guidance for
  interpreting bioaccumulation data, a series of concerns (e.g., uptake of several contaminants.
  uptake of toxicologically important chemicals, uptake in both species in all berths except
  Conley, etc.) about the test results could lead to the conclusion that we should not. allow the
  surface dredged material from Gulf Oil, Army Base Berths, Conley Terminals, and the
  Boston Edison  Barge Berths to be disposed in the ocean.

  Keckler explained that the Reserved Channel was determined to be  unsuitable for ocean
  dumping because of 1) toxicity in one test and 2) the very high detection limits for PAHs in
  the tissue measurements could have concealed any bioaccumulation.  Muir stated that these
_ high detection limits renders the  Reserved  Channel  sediments to be  inadequately
  characterized, which prohibits them from  ocean disposal per 40 CFR § 227. 5(c).

  Keckler indicated that a  quick calculation  of human health risk assessment showed  that ail of
  the sediments could pose a cancer risk to  human health.

 Joe Wilson from Corps HQ stated that EPA's position  regarding dredged material suitability
 for ocean dumping prevails and that the Corps should not be proponents of dredging projects,
 only administrators of the program.  Keckler explained that Region  I is in the process of
 evaluating alternatives and that alternatives (other than  ocean dumping) for this material may
 exist. Keckler  also  explained that Stellwagen Bank has been recently designated as a
 National Marine Sanctuary and that conditions of only  clean dredged material disposal have
 been placed on  the MBDS designation.  EPA's actions  on this project will therefore be
 closely watched.

 Monte Greges from  the Corps NY District stated very strongly that  the New England
 Division should be looking for alternatives for all of the material first,  and only  seek ocean
 disposal if there are  no other alternatives.   Greges did not see the need for EPA  to write its
 letter regarding suitability until the Boston Harbor EIS  is out.  Keckler stated that the
 regulations also direct proponents of ocean dumping to  evaluate alternatives to  ocean
 dumping first.
 There was insufficient time to continue. discussions regarding  both the EPA, Region I and the
 Corps NED  approaches. Bob Engler from WES stated that WES's review had only beer, a
 "cursory" one.  Engler offered to pay travel to reconvene the group after everyone has had a
 chance to evaluate the data in detail.

-------
ATTACHMENT C

-------
          INCREASED CANCER RISKS TO HUMAN HEALTH FROM THE
                  CONSUMPTION OF CONTAMINATED SEAFOOD
              FROM MBDS IF MASSPORT SEDIMENTS ARE DUMPED
       Risk assessments are typically used to help make regulatory risk management
 decisions concerning the appropriate course of action to protect human health from exposure
 to toxic substances.  In a risk assessment, the chemicals of concern are identified, the rate of
 exposure  to populations of concern are estimated, the potential toxicological responses  to
 various doses of the chemicals are determined, and the potential risks of adverse health
 effects_ based on .dose-response data- and exposure data are estimated.  The resulting numbers
 represent  a potential upper-bound likelihood of adverse health  effects.

       Cancer risks are expressed  in terms of predicted additional  cases of cancer in an
 exposed population over a lifetime. For example, 2.7 additional cancer cases in  100,000
 individuals would be expressed as  2.7 x 10"5.  Various EPA regulatory programs define
 acceptable risk differently, with levels of acceptable risk ransins from a level of risk of 1 in
 10,000 (10-*) to 1 in 1,000.000
       The risk assessment procedure for seafood consumption consists of determining the
dose of a chemical that a human would be exposed  to during a lifetime, based oh a certain
consumption rate of seafood with observed tissue levels, and predicting the likelihood of
adverse health effects from this dose, based on EPA toxicity values.  EPA developed
guidelines for performing risk assessments and issued a guidance manual entitled Assessing
Human Health Risks from Chemically Contaminated Fish and  Shellfish (USEPA, 1989).
EPA evaluated potential human health risks associated with consumption of seafood harvested
from the Massachusetts Bay Disposal Site ("MBDS") as pan of its review of the Massport
bioaccumulation  data using this methodology. EPA used the 28-day bioaccumulation data
from Conley Terminals, Army Base Berths, Gulf Oil, and the  Boston Edison Barge Berth in
its risk assessment calculations.  EPA is concerned that disposal of surface dredged material
at the MBDS could  pose unacceptable cancer risks to public health. EPA also estimated the
potential for effects  other than cancer and-did not. identify any  non-cancer risks.  The
methods and results  of EPA' s. health risk assessment are discussed  below.

       Fish may accumulate toxic chemicals in their tissues through several routes of
exposure to contaminants,  including absorption through the water column, sediment contact.
or by consumption of contaminated prey. Since EPA only had data for clams and  worms
exposed to the dredged material, EPA estimated what the tissue concentrations in fish would
be if they were to feed on  clams and worms exposed to Massport sediments. EPA assumed
that polycyclic aromatic hydrocarbons ("PAHs") would be accumulated in fish to the same
level achieved in clams and worms and polychlorinated biphenyls ("PCBs") would be
accumulated to a higher level (Kay, 1984).  EPA assumed that the  benthos are a trophic level
of 2 and a demersal  fish feeding on them would have a trophic level of 3.  Based on a food
chain  multiplier approach developed by EPA's Duluth laboratory, tissue residues in trophic:
step trophic level 3 are projected to be three-fold higher than in trophic level 2 for a
compound with an octanol- water partitioning coefficient of 6 (estimate for PCBs).  EPA

-------
 therefore multiplied the PCB concentration in the clam and worm tissue by 3 in order to
 estimate the PCB tissue concentration in fish feeding on them.

        EPA assumed that the tissue residues measured in the 28-day test were representative
 of steady-state conditions.  It is possible that the levels of contaminants in the test" organisms
 would be higher if the exposure period was  longer. This would tend to underestimate the
 risks calculations.

        Average values for  fish and shellfish consumption for the U.S. population generally
 range from 6.5 to 20.4 g/day (USEPA,  1989).  Estimates of potential  risks were made for
 the average New England consumer for each species.  For this risk assessment,  EPA  used
 the. lower bound consumption rate of 6.5 grams per day of seafood harvested from the
 MBDS. Although 6.5 grams per day may be high for consumption of seafood from the
 MBDS, EPA found that even incidental  exposure to MBDS seafood could pose unacceptable
 health risks if Massport sediments were  to.be disposed.  EPA found that ineestion of seafood
 at a consumption rate as low as 0.014 grams per day,  or approximately one meal in 29
 years, could result in a 1 x 10'6 cancer risk.  •

        Benzo(a)pyrene is the only PAH compound that currently has a carcinogenic potency
 factor affiliated with it. EPA recognizes that the other six carcinogenic PAHs^lso pose a
 risk of developing cancer.  However, since these compounds do not currently have a
 carcinogenic potency factor associated with them, EPA applied the carcinogenicity potency
 factor for benzo(a)pyrene, the most potent PAH compound, to the total of toe seven
 carcinogenic PAHs measured.  This methodology is consistent with current EPA policy.
 EPA's cancer risk estimates from both benzo(a)pyrene alone and the sum of the seven'
 carcinogenic PAHs are presented in Table 1.

       EPA's calculations for cancer risk indicate that  the risk associated with the
 consumption of seafood harvested from the MBDS  if Massport sediments were to be disposed
 exceeds values  within the acceptable range.  The results of the cancer risk estimates are
 presented in Table 1.  The standard assumptions that were made include: i) exposure  over a
 70 year lifetime, ii) average human body weight of 70  kilograms, and iii) 100% of all of the
 chemicals ingested are absorbed.  The increased cancer risks calculated ranged from 1.4 x
 10*5 to 4.6 x  10"4.  These risk estimates indicate  that consumption of seafood harvested from
 the MBDS if Massport sediments were to-be  disposed could pose unacceptable cancer  risks.
 Unacceptable non-cancer risks from eating seafood  harvested at the MBDS were  not
detected.

-------
                            EXAMPLE CALCULATIONS




 Increased Cancer Risk = Dose x Cancer Potency Factor




 Dose = [Tissue concentration x Consumption Rate]/Average Body Weight






 Example for carcinogenic PAHs in worms from the Coniey Terminals:




   = (0.144 mg/kg)(6.5 g/day)(7.3 kg/mg-day)/(70 kg)(1000 g/kg)




__ f 9.8 x 1Q±	  -                  -   '   ' - "




 Example for PCBs in clams from the Army Base Berths:




   = (0.052 mg/kg)(3)(6.5 g/day)(7.7 kg/mg-day)/(70 kg)(1000 g/kg;




   = 1.1 x 10J

-------
  c/;
  I
  i
  z
  r-
  b:'
c/:
U
               vt
              C
 r~i
 S
 H s
 r-1 ^J
 5T ""^
 ec S

 c^ <

 w: Z
^ c
~ Si
< «=
U r-
IS
             a
             ea
 i
3
 C  j=
 «;  t:
<§£
            V
           I
                         ?

                        C
          v;
          C

          I

                               X
                              VC
                             cc
                                         X
                                        C
                           C

                           x
                           T
                                       X
                                       oc
                                                    0

                                                    X
                                                    c
                                                     X

                                                    cK
                                       X
                                       r-i
                                       r-'
                          X
                          rr
                                      x
                                      •^C
                                      x
                                      tN
                                     •T
                                     C
                                       X
                                      fN
O

 x
                                                   X
                                                  oo
                                SJ
                                      E  S
                                     fi£     CU,
                                                  "
                                                  -

-------
 F2-1

       Additional investigations on biological resources at all the potential disposal
 sites were undertaken in fall 1994. This information was reported in separate technical
 documents and summarized in Attachment 1 of the FEIR/S.  These data were used to
 reevaluate the  selection of the proposed preferred alternative site for the disposal of silt
 from the BHNIP.
 F2-2

       Section 5 of the FEIR/S describes proposed means to mitigate for impacts of
 the dredging and disposal of silt from the BHNIP.  This presentation includes methods
 to avoid and minimize potential impacts and suggests possible compensatory mitigation
 for unavoidable adverse impacts.  Many of the techniques and guidelines for avoiding
 and minimizing impacts are specified ha the Dredge Management Plan (Section 5 of
 the FEIR/S) and will become part of the dredging contract specifications.
,F2-3

       For the purposes of identifying sufficient disposal site capacity for the surface
 material (silt) to be dredged from Boston Harbor, the DEIR/S considered all silt to be
 unsuitable for unconfined open water disposal.  This interpretation is carried through
 into the FEIR/S.
 F2-4

       The FEIR/S does not select the MBDS or BLS for disposal of the silt to be
 dredged for the BHNIP, therefore, capping is not an issue at these sites.
 F2-5

       As indicated hi response to comment F2-1, additional biological investigations
 were conducted in the In-channel locations in the fall of 1994.  These studies were
 used hi the reevaluation of the site selection process for the FEIR/S.
 F2-6

        The site selection process has been reevaluated in the FEIR/S (Section 4.0) to
 separate the issues of "environmental damage" and "practicability" more clearly. In
 other words, the least environmentally damaging alternative(s) have been identified
 based on spatial and temporal impacts (nearfield and farfield) and risk of failure to
 isolate the contaminated sediments permanently prior to evaluating practicability.
                                        12
(el

-------
 Practicability includes capacity, cost, amount of structural engineering required, and
 ability to permit within the desired timeframe of the proposed project. Alternatives
 were screened based on both environmental and practicability criteria.
 F2-7

       Except for a few potential technologies, such as geotextile containers, few can
 accommodate the large volume of dredged material removed from the harbor and at a
 cost that is practicable.  The Corps and Massport will  consider accommodating new
 demonstration projects (Section 2.0), where authorized and feasible.  However, the
 Clean Water Act 404 (b) (1) guidelines do not encourage the filling of the aquatic
 environment for recreational opportunities.
 F2-8

       Massport and the ACOE are committed to making dredged materials available
 for beneficial uses if economically feasible and practical to do so. As stated hi Section
 3.5 of the FEIR/S, potential commercial uses for the uncontaminated clay, gravel and
 rock material have been considered as alternative beneficial uses. The clay material
 could be utilized for landfill cover material while the gravel and rock material could
 be used for construction aggregate or fill. The major limitation to committing to a
 specific beneficial use disposal options at this time is the varying market demand for
 these materials.  The local demand for clay, gravel and rock for construction purposes
 and landfill cover may be partially satisfied by the generation of such materials form
 the CA/T project which are expected to be available concurrently. The BHNIP FEIS
 explores the options of making clay available to landfills beyond the expected CA/T
 delivery range. The options for use of construction aggregate are also discussed hi
 greater detail.

       A portion of the rock will be used to  enhance areas susceptible to erosion from
 ship turning in the navigation channels.  The remaining rock will be used for fish
 enhancement habitat at the Massachusetts Bay Disposal Site (MBDS).
F2-9

       Dredging of the silts vs. dredging of the parent material will be distinct
operations. During the silt dredging operations, a small amount of parent material will
be removed due to overdredging. The consistencies of the two materials  are visually
and mechanically distinguishable. The dredge operator will sense by resistance to the
bucket "bite" and to bucket closure the location of the sediment interface. Coincidental
hydrographic surveys will verify digging depth and location to enable comparison with
geotechnical records. When the operator experience and survey data indicate that the
parent level has been reached, the dredging equipment will be changed. The silt from
                                       13

-------
an entire designated area or cell will be completely removed before the parent material
equipment will be utilized.
F2-10

       Trash and unknown materials such as drums will be handled and controlled in
accordance with the contingency operations described in Section 5.8.2.2, Trash and
Debris Management, of the FEIR/S.
F2-11

       All techniques to minimize fish mortality due to the proposed blasting opera-
tions have and will be considered. As noted in Section 5.0 of the FEIR/S, seasonal;
restrictions on blasting will be observed. Other mitigation procedures will include
employing fish "startle" devices.
F2-12

       General concepts for compensatory mitigation are discussed hi Section 6.0 of
the FEIR/S.  Detailed plans for compensatory mitigation will be developed during the
permitting phase of the BHNIP and will involve close coordination with the appropri-
ate agencies.
F2-13

       See response to comment F2-3. Material from Reserved Channel and the berth
areas (Army Base, Conley Terminal, Boston Edison, and Gulf Oil) are considered
sufficiently characterized and suitable for unconfined open water disposal by the
Corps.  This statement has been corrected hi the Final EIR/S.
 F2-14

       As indicated in responses to comments F2-1 and F2-6, additional studies have
 been conducted to aid in the revaluation of the potential disposal sites.  The process
 of selecting the least environmentally damaging alternative has been more clearly
 distinguished from the process of identifying practicable alternatives in the FEIR/S
 than the DEIR/S.  The possibility of using multiple sites to attain the needed capacity
 has  not been excluded in the analysis of environmental impacts.
                                        14

-------
 F2-15

        The revised alternatives analysis separates the evaluation of environmental
 impacts and practicability criteria (Section 4).  Therefore, the sites are compared on
 the basis of their environmental effects without regard to capacity, allowing the
 identification of the "least environmentally damaging alternatives" for the disposal of
 contaminated silts hi general.  Capacity is considered to be a practicability criterion.
 F2-16

        Subsequent to publication of the DEIR/S, the Corps reevaluated the capacity of
 the In-channel options. They determined that by expanding the footprint (while still
 remaining within the boundaries of the federal channels) and increasing the depth, the
 capacity of the in-channel alternative  is substantially higher than originally thought.
 The In-channel alternative assessed in the FEIR/S represents the larger design.
Unnumbered Comment

       17. page 9, 3rd para., last sentence - This sentence has been clarified.  If a
capping demonstration could prove the efficacy of capping then the entire 1.3 million
c.y. of silt could be disposed at MBDS. Since tune for a demonstration project is not
available for the improvement dredging, disposal at the MBDS is not viable.
Unnumbered Comment

       18. page 9, last para. - Studies conducted by SAIC have indicated the efficacy
of capping at the Portland Disposal Site.  These studies are available for review.
F2-17

       The Corps and Massport are and have been very much aware of public and
agency concerns regarding capping at the MBDS.  MBDS was not considered for silt
disposal for the BHNIP hi the FEIR/S.  Capping at the preferred disposal site is
discussed in Section 5.0.

F2-18

       See response to Comments F2-4 and F2-17. Should BLS become a selected
option the BHNIP will coordinate with EPA regarding the proported drums of
industrial and radioactive waste at this site. Disposal of dredged material at this site to
cover these drums may benefit the environment of this area. The EPA should play an
active role hi researching the locations and environmental status of any hazardous
                                       15
                                                                                          Iff

-------
materials at the BLS to determine whether it would be best to leave as is, remove, or
cover hi place.

       NED believes that a site designation process is not necessary if there is not an
U.S. EPA designated disposal site in the area.  Since MBDS is not currently available
for the disposal of unsuitable material, no site designation requirement is necessary, as
long as the site meets MPRSA requirements (40 CFR 228.4 (e)(2).
F2-19

       The Corps is investigating the use of clean silty material from another dredging
project to demonstrate capping at the MBDS.  This and other demonstration opportuni-
ties depend on the availability of suitable project material, authority and funding for
monitoring.
F2-20

       The manager of the Stellwagen Bank National Marine Sanctuary received a
copy of the Draft EIR/S.  His comments were incorporated into a NOAA response.
F2-21

       A draft biological assessment has been submitted to the National Marine
Fisheries Service for review. As a capping demonstration project can not performed in
time for the improvement dredging project, the biological assessment will drop the
capping alternative at the MBDS.
 F2-22

       As a capping demonstration project cannot be performed in tune for the
 navigation improvement project, this alternative will dropped for the silt material. A
 capping demonstration project may go forward to address questions for future mainte-
 nance of the navigation channels.  At that time, appropriate agencies will be brought
 forward to discuss the parameters of a demonstration project.
 F2-23

       The disposal site alternatives analysis thoroughly evaluates environmental
 impacts  of all sites.
                                        16


-------
F2-24

       In the DEIR/S, the impacts and practicability of using individual disposal sites
was discussed. The discussion of combination alternatives was based on the premise
that the impacts and practicability of using a site would be the same whether the site
was used by itself or in combination with one or more other sites.
F2-25

       Impacts and practicability of using land-based disposal sites (Option A3) were
Devaluated in the FEIR/S (Section 4.0).
F2-26

       If the entire quantity of dredged material was allowed to air dry in cells, then
approximately 30 truck trips per day for 275 weeks or over 5 years (5 days a week 8-5
daytime hours, 3750 cycles/day) would be required to dispose of the silty material at
an upland site. Additional noise, congestion and ah- quality impacts would be experi-
enced with land based disposal.  Coordination with local communities to minimise
truck traffic impact on local traffic would occur if a land based disposal site were
selected as the preferred disposal site.

       Disposal sites with possible barge access are described in the draft and final
EIR/S.  The only upland site with barge access would be Squatum Point;  a channel
would need to be dredged to provide this access.  Impacts from barge access are also
described.
F2-27
       See response to comment F2-8.
F2-28
       The Corps may investigate the use of geotextile bags at other projects for
dredged material.  Coordination with appropriate agencies would occur, as appropriate.
F2-29

       The statement of project purpose is partially correct, in that future vessels will
require deeper drafts. However, numerous port users have indicated that existing
channel clearances are insufficient for their efficient operations.  Letters from numer-
ous port users stating difficulties they have experienced waiting for tides to gain access
                                       17

-------
to the inner harbor are included in this volume (see letters under the Commercial
category).  Therefore, it is more correctly stated that the purpose of the improvement
dredging in Boston Harbor is to bring the facilities up to current competitive standards.
The purpose of the project is restated in Section of the FEIR/S.
F2-30

       EPA suggests that dredging could have far-reaching implications for port
terminals and for inland transportation because of the change in the type, frequency
and volume of traffic calling on the Port of Boston.

       In 1994, 53% of containers arrived in the Port of Boston by container vessels
calling on the Port directly, while 40% arrived via barges from New York, and 7% by
trucks over land.  At present, most of the container ships arriving in the Port of Boston
are either light-loaded or enter the harbor on the high tide due to the insufficient
depths in the navigation channel and at berths.  The BHNIP will enable the existing
container ships to operate regardless of tide conditions.  This should facilitate schedul-
ing and make the Port of Boston more attractive to shipping lines.

       With regard to type of traffic, the harbor dredging might increase the percent-
age of containers traveling on container ships to the Port of Boston compared to that
coming by barge from New York. But the number of vessels bringing cargo is low
enough so the shift in type would hardly be perceptible. At the present tune, three
overseas container vessels call on the Port of Boston weekly.  In addition, a barge
service calls twice a week from New York.

       As for frequency of vessel calls, if the container trade  remains  more or less
stable, showing no significant growth after the dredging is completed,  fewer direct
calls by large, fully loaded vessels would suffice to deliver the same amount of cargo.
If there is a steady 3% or more growth in the amount of containerized cargo moving
through the Port of Boston, there could be an increase hi container ships arriving in
the Port, but this increase is unlikely to trigger more than one or two additional
container ship calls per week.  Therefore,  the BHNIP will not significantly alter the
type of vessel, the number or the frequency of calls in the Port of Boston.

       As for the transport of petroleum products,  the BHNIP will enable the existing
fleet of Chelsea-class tankers to transit the Harbor more safely. Currently, these
tankers must frequently wait for tidal navigation. This poses  special problems hi
winter months when the daylight hours, which are  useful for navigating the bends hi
the waterway, are short. However, double-hulled tankers have recently been mandated
for new tankers carrying petroleum. The new tankers will have the carrying capacity
of the old tankers, but will draw more than the standard tankers because of the double-
hull and will be wider.  These  tankers, as stated hi the response to F2-29, will not be
able to call at the existing facilities upstream of the Harbor tunnels. Lightering is
unlikely to be eliminated even  with the BHNIP because of the double-hull requirement
and because the demand for petroleum products in the region continues to grow.
                                        18

-------
       The BHNIP will not dramatically change operations in the Port of Boston.
 Vessel traffic will continue to include a mix of large container ships, barges and
 tankers.  The volume of cargo will not change sigiiificantly as a result of dredging sine
 cargo volume depends on more than channel depth.  The Massachusetts Port Authority
 (Massport) has been continuously upgrading its container handling facilities to provide
 "state of the art" off-loading and storage at Moran and Conley Terminals.  Therefore,
 dredging need not trigger landside improvements at Moran and Conley Terminals.

       Inland transportation improvements have long been the subject of planning and
 investment. The  Seaport Access System, which is part of the Central Artery/Tunnel
 Project will result hi more direct and convenient connections for trucks between port
 terminals and the regional highway network. At the same time, through State and
 Massport effort, infrastructure changes to accommodate double-stacked trains are being
 promoted.  This latter effort is separate from the dredging project.  It is designed to
 encourage shippers to use the Port of Boston.

       EPA asks  if the proposed dredging  will result in the expansion of the "inland
 port" facility at Fort  Devens, thereby causing environmental impacts in the surrounding
 communities.  In  short, no.   Expansion at "Port Devens" will be more a function of the
 success of the referenced effort to accommodate "double-stacked" trains.

      In 1994, only 3% of all containers handled in the Port of Boston were moved
 by rail.  Of those containers, less than one third moved by rail between Moran
 Terminal and Ayer or beyond, with the rest going between Conley Terminal and
 inland destinations via Conrail.  The containers going through he "inland port" facility
 represented only 1%  of the  total container trade in the Port of Boston.  It is unlikely
 that this situation will change with the dredging of the harbor.   The rail route via Ayer
 is convenient for export cargo from New England and Canada, which represents only  a
 small portion of the total cargo handled by the Port.

      Boston's imports substantially exceed the export cargo reflecting the nature of
 industry int he region.  The New England textile and shoe industries which traditional-
 ly exported high volume cargo through the Port have given way to industries produc-
 ing low volume, high value cargo which is now shipped by air. The current ex-
 port/import balance is expected to continue hi the future regardless of the impact of
 dredging.  Thus Fort Devens is not going to become a major distribution facility as a
 result of dredging in  the Port of Boston. Growth at Fort Devens will be a function of
 the increase hi import cargoes being carried by rail from Moran Terminal. This would
 be totally separate from any dredging under the BHNIP.
F2-31

       The biological assessment of the EIR/S includes a discussion of future vessel
traffic on threatened and endangered species.
                                       19

-------
              United States Department of the Interior


                           OFFICE OF THE SECRETARY
                         Office of Environmental Polity and Compliance
                             40Ji Arlsmic Avenue - Room 142
                             Boston. .Ma.MJchu<.«« 022!0-3334
REF:  ER 94/0393
June 20, 1994
Colonel Brink P. Miller
Division Engineer
U.S. Array Corps of Engineers
424 Trapelo Road
Waltham, MA 02254

Dear Colonel Miller:

This  is in response to  your April 20,  1994  joint notice  with MassPort.
requesting  comments  on the draft environmental  impact report/statement.
 (DEIR/S) for  the Boston Harbor Navigation Improvement  and Berth Dredging'
Project  (ER 94/0393).

General Comments:

MassPort and the Corps have attempted to satisfy the procedural requirements
of  the National  Environmental  Policy  Act  (NEPA)   and  Massachusetts;
Environmental Policy Act  (MEPA)  in a combined environmental document.  This
has been done successfully in the past on major projects such as the Central
Artery/Tunnel (193/90) project.  However, in this instance, some basic NEPA
procedural standards have been integrated with MEPA requirements resulting
 in questionable compliance with NEPA regulations. The Massachusetts environ-
mental  standards  appear  to  be controlling  in portions  of this joint
NEPA/MEPA  document  and may explain  some of the procedural  irregularity
 concerning which alternative, no action or the Massachusetts Bay Disposal
 Site  (MBDS),  is  the standard of comparison.

A "rigorous"  analysis of design alternatives as contemplated under  Section
 1502.14 of NEPA is not provided  in Section 2  of the DEIR/S.  The DEIR/S does
 not contain sufficient information on the physical, chemical and  biological
 resources  of the' identified  aquatic disposal  sites  to differentiate  the
 environmentally  acceptable  sites from  the unacceptable sites.  Additional
 information is needed on most  aquatic sites before informed decisions can be
 made  about  environmental acceptability.

 Specific Comments:

 Section  2  of  the  DEIR/S  is  inadequate  in  terms  of  the  selection,
 presentation and analysis of design alternatives.  The purpose of an EIS is
 not limited to assessing environmental impacts,  but it must also serve to
 "inform decision makers and the public of the reasonable alternatives which
 would avoid or minimize adverse impacts or enhance the quality of the human
 environment" (40 CFR Section 1502.1). Only three actual design alternatives
 are presented; the "full project/preferred  alternative, and two variations
 on the  "no   action"  alternative,  which   include  no  action/maintenance
 dredging,  and no action/no maintenance.   The "reduced project" and "delayed
 project" alternatives are not presented as actions in and of themselves, ^but
 as consequences  or scenarios' under which  variations to the  full  project
 might occur.                '                      /-» ^
                                                   75

-------
                                   -2-
!
-------
                                    -3-
REF:  ER 94/0393

DEIR/S  should adopt  a consistent  approach to the evaluation of  future
maintenance dredging. Since future maintenance dredging was considered with
the  No  Action  alternative,  it should be considered  with  the  build
alternatives  also.   An evaluation  of the build  alternatives with- future
maintenance dredging and disposal would provide a more realistic projection
of  the  environmental 'consequences of  implementing the  Congressionally
authorized project.   Of the 376 disposal sites  evaluated,  only  MBDS and
Boston  Lightship Disposal  Site (BIDS)  have excess  capacity to  handle
improvement and 50-year maintenance dredging needs  (DEER/S Table 3-22a).

An  apparent  conflict  seems to  exist between NEPA and MEPA regulations
concerning which  alternative is the standard of comparison by which other
alternatives  are measured.  According to Question 3  of the Forty Most Asked
NEPA Questions  (46 FR  18027),  "This  analysis  (no  action)  provides  a
benchmark,   enabling  decision   makers  to  compare  the   magnitude  of
environmental effects of action alternatives." However, on page 3-5 of the
DEIR/S the following statement appears:  "As .stated in the MEPA scope, ocean
disposal  is  the  preferred  disposal  option for   uncontaminated  marine
sediments  of acceptable  quality and is the option against which other
alternatives  should be judged." In fact, this latter case seems to be the
prevailing view  in  this DEIR/S because the two ocean disposal sites, MBDS
and  BIDS, are used as the standards  of comparison for the other alternatives
including no  action.   No action is only included under design alternatives
 (Chapter 2).   It  is not included  under  the disposal  site alternative
analysis (Chapter 3).

The  disposal  site screening process described in Chapter 3 was an  effective
method of eliminating potential disposal sites from further  consideration.
A universe of 376 potential sites in Phase I were pared down to a short list
 of 24  sites  and one  treatment technique  (solidification)  in Phase  III.
While we are in  general  agreement with the  Corps and MassPort that many of
the  sites  were not reasonable, we  also  believe that some reasonable  sites
were dropped from further consideration and that several sites carried as
 reasonable alternatives,  should have  been dropped in  Phase  I  or II
 screening.  We also- believe that all reasonable disposal sites have not been
 identified nor evaluated.   This is especially true for the aquatic  sites
 which cannot be  identified nor  evaluated  as conveniently  as  terrestrial
 sites.   The universe of 376 disposal sites only contained 21 aquatic sites
• which demonstrates the inherent numerical inequity in the site selection and
 evaluation process.

 The Rowes Quarry  site was dropped from further consideration  during Phase _ II
 screening.  Rowes Quarry and other quarries received considerable discussion
 as the DEIR/S intimates on page 3-5.  Unfortunately, the document fails to
 divulge that the EPA found  the Rowes Quarry site to be an environmentally
 satisfactory disposal site for residuals from  the MWRA facility at Deer
 Island. This finding was  published in the March 30, 1990 Record of Decision
 for the MWRA Residuals Management EIS.  This  DEIR/S does not  provide  a
 convincing  argument to demonstrate that  Rowes Quarry  or other  similar
 quarries  are  not  reasonable  containment  sites  for  the  contaminated
 maintenance  dredge material.    The  information  on  pages  3-5  and  E-14
 indicates  that  the quarries  were  dropped as  reasonable sites  because
 Massport did not want to  disrupt existing businesses or use Eminent Domain
 authority to acquire the property.  None of these reasons would appear to be
 fatal  flaws  eliminating these or  other sites from the list of reasonable
 alternatives because these same impediments existed during the MWRA process.
                                             77

-------
                                    -4-
REF:  ER 94/0393

Several shoreline landfill sites such as Reserved Channel and Little Mystic
Channel were  carried forward as reasonable alternatives despite the fact
that Boston Harbor estuary has long .ago exceeded the significant degradation
threshold  for filling  and  creating  fastland  in  intertidal  and subtidal
habitat.   Over 3,000 acres  of  intertidal and subtidal habitat  have been
filled to  create  fastland and several hundred additional  acres  have been
degraded by dredging. Against this background of environmental degradation,
additional shoreline landfill projects should not be considered reasonable
alternatives  since they would likely be precluded by Clean Water Act and
other regulations.   It appears that  several of these in harbor shoreline
sites were chosen  because they are depositional areas containing Category II
or  III  sediments  and,  if  filled  above  MHW, could  be used for future
commercial  purposes.    Most  depositional  "areas in  Boston  Harbor contain
Category II or III sediments, hence this is not a valid reason for filling
these sites.  Additionally, as Boston Harbor water quality improves in the
future,  the natural sedimentation patterns will sequester these Class II and
III sediments with cleaner material.

The list of preferred alternatives was ultimately pared down from the short
list, of alternatives  by capacity and cost constraints.  Economics  (cost) was
the major determinative factor for developing  the final list of preferred
disposal alternatives   (DEIR/S pg.  3-25).   These five  preferred disposal
sites—MBDS,  BIDS, Meisberger 2  or 7, and Spectacle Island CAD—all have
similar cost estimates.

Unfortunately, spatial  and temporal information on living resources at the
preferred  sites and the other  reasonable aquatic sites was not  used to
develop and refine the list of potential sites nor the list of preferred
sites.  This critical information simply does not exist except possibly for
the MBDS.   Therefore,  the environmental acceptability of Spectacle Island
CAD, Meisberger 2  or  7,  Boston Lightship, and other reasonable aquatic sites
has not been demonstrated.  Additional data is needed to identify what the
spatial and temporal characteristics  of  living resources  are at each of
these sites on a  seasonal basis  before any determination can be made that
these are environmentally acceptable as disposal sites.  Existing uses need
to be determined at the Section 404 sites  to insure that these uses can and
will be protected in accordance with the State antidegradation policy if
used for disposal purposes.  The full disclosure provisions of NEPA cannot
be complied with in the absence of the spatial and temporal data on living
resources at these preferred and other reasonable sites.

During the planning process for this project and the  formal designation
process  for  the  MBDS,  considerable  attention was  focused  on  dredging,
transport,  and disposal of contaminated  sediments  at  offshore disposal
sites.  Many  of these concerns about contaminated sediments were expressed
in scoping  comments provided by PWS for this DEIR/S.   The questions raised
about mass balance,  chemical  and physical  changes to  contaminants  in
sediments  from the undisturbed  state until disposal,  percentage of fine
grained material and contaminant load dispersed during disposal, ability of
cohesive parent material (blue  clay) to  cap  fine grained unconsolidated
material, details of dredge management plans and other scoping  issues remain
unanswered  and unresolved in this DEIR/S.

Recent research by the  Waterways Experiment Station with the use of large,
barge size,  geotextile containers may provide the Corps/Massport with an
additional  treatment technology alternative for the disposal of the
  F3-8
 F3-9
F3-10
F3-11

-------
                                    -5-
REF:  ER 94/0393

contaminated  maintenance material.   However, the  DEER/S eliminated  all
treatment  technologies  except  solidification  from  the  short  list  o±
alternatives. If the Corps/Massport intend to pursue the use of geotextile
containers as a treatment technology option at one or more  of the listed
sites, a supplemental  ECR/S will need to be prepared which evaluates this;
technology and  the expected environmental effects at the various disposal
sites. Shis new technology appears to have the potential to address many at
the longstanding concerns identified  in the preceding paragraph about open_
water disposal  of  contaminated material.

•Conclusions

We recommend  that the Corps and MassPort initiate biological investigations
of the preferred  and other reasonable  disposal  sites  to  identify the
temporal and- spatial characteristics  of the  living resources at each site.
Ihis  should include data -for all seasons for at least a one-year period.
While the biological investigators are underway, the Corps should address
each  of the  other outstanding  issues raised by the FWS/DOI during ^the
scoping and review process,  including  new innovative treatment technologies.
After the requested data has been collected,  demonstrations conducted, and
other information gaps have been filled, the Corps should publish all of the
information in a  supplemental DETR/S so that interested parties have the
opportunity  to review and  comment on the  substantive issues  identified
during the review of the draft statement.

                                     Sincerely,
                                     Andrew L. Raddant
                                     Acting Regional Environmental Officer

-------
F3-1

       The no action alternative and the Massachusetts Bay Disposal Site (MBDS)
alternative involve two different assumptions. The no action alternative assumes the
project would not be built but maintenance of the navigation channels would continue
or no project and no maintenance would occur.  MBDS was used as a comparison for
dredged material disposal alternatives.  MEPA requested the use of MBDS  as a
standard for comparison.
F3-2

       Additional benthic, lobster, and finfish data has been collected for the disposal
sites.  This information is included in the final EIR/S.
F3-3

       The proposed project is the Congressionally authorized project, based on the
1988 feasibility study.  The reader may refer to this report and Environmental Assess-
ment prepared by the Corps in 1988 for a more detailed analysis of the various
channel depths and alignments investigated during the feasibility study.  The "reduced
project" and "delayed project" alternatives are within the range of reasonable alterna-
tives to be evaluated under NEPA. As stated in the draft and final EIR/S, a tributary
channel could be dropped from consideration if its economic benefit to cost ratio drops
below  1:1. A tributary channel would not be dropped as a potential alternative
otherwise, unless some other factor, such as a bridge replacement in Chelsea, delays
construction.

       A brief discussion on relocating the active port terminals to the main ship
channel is discussed hi Section 2.0. This alternative would have a significant impact
on the  amount of dredged material and capital to relocate the port  activity and its
supporting infrastructure.
F3-4

       If maintenance dredging does not occur within ten years, ship traffic in Boston
Harbor will continue to be forced to account for tidal delays.  This will be happening
concurrently with regulations effecting vessel design such as the double hull require-
ment for tankers. The combination of delays and cost of constructing vessels capable
of use in 33 - 35 foot channels will undoubtedly be passed on to consumers in the
form of higher prices particularly for home heating oil. Shoaling is currently affecting
ships transiting Boston Harbor due to the need for maintenance dredging in the Mystic
River and Chelsea Creek.
                                       20

-------
       An Environmental Impact Statement is being prepared for the Providence River
maintenance dredging project.  The U.S. Coast Guard has determined that restrictions
on vessel drafts, one way traffic and communication does not impose an economic
impact for the Providence port. The EIS will perform a needs  analysis to determine if
the Coast Guard rule has an impact. No maintenance dredging will be performed if
there is no need.  Future conditions will also be evaluated to assess when dredging
may need to occur if there is no maintenance dredging now. It also needs to be
recognized that the Providence River Harbor is used mostly by oil tankers while
Boston Harbor is used by container ships and oil vessels. The  benefit to cost ratio for
Boston Harbor has determined that their is an economic benefit to deepen the port.
This analysis implies that the current navigation channels are not optimal for Boston
Harbor.
F3-5
       The final EIR/S evaluates disposal sites for future maintenance hi Section 4.
F3-6
       The No Action alternative was discussed in Section 2.1 in the DEIR/S as well
as the environmental impacts and benefits. A No Action alternative is not possible for
disposal site selection if a project alternative is considered. The navigation improve-
ment project can not go forward without a disposal site.  This would bring the project
back to a No Action alternative.  The Final EIR/S does use the MBDS as a disposal
site for the parent material.  However, other uses for the material, such as landfill
cover, have been pursued and are discussed hi the FEIR/S. The MBDS is no longer
used as the standard of comparison for the silty material.
F3-7

       The selection of disposal sites was based on available information. The number
of upland vs. aquatic sites is based on what is available for disposal site alternatives.
While there may be disagreements over the designation of fatal flaws hi the DEIR
disposal site selection process, socioeconomic impacts are a consideration, and
Massport remains reluctant to acquire an  active business (such as Rowes Quarry)
through eminent domain.  Additional issues have been identified which make Rowes
Quarry and otiier upland disposal sites  impracticable, including compliance with the
current waste disposal facility siting requirements and permitting process, and the cost
and technical difficulty  of dewatering the sediments sufficiently for transport.  In
addition the site would need to be lined to prevent groundwater contamination. These
costs and engineering considerations were not discussed hi the Record of Decision for
the MWRA Residuals Management EIS.  In addition the site would need to be lined to
prevent groundwater contamination.  These costs and engineering considerations were
not discussed hi the Record of Decision for the MWRA Residuals Management EIS.
                                        21

-------
F3-8

       The shoreline sites were evaluated for two different disposal scenarios: partial
fill, in which the site would continue to be tidally submerged; and fill to fastland, in
which the site would be filled above the tideline. While recognizing the historical loss
of aquatic habitat in Boston Harbor, the project feels that these scenarios fit within the
definition of Designated Port Area, as provided by the state in its Wetlands Protection
Act.  Therefore, both scenarios were reexamined in the FEIR/S (Section 4).  The
partial-fill scenario was found to be among the least environmentally damaging
alternatives. Because of the permanent loss of aquatic habitat that would be caused by
the fastland scenario, however, this option was not found to be among the least
environmentally damaging alternatives.
F3-9

       Additional investigations on biological resources at all the potential aquatic
disposal sites were undertaken in fall 1994. This information was reported in separate
technical documents and in Attachment 1 of the FEIR/S. These data were used to
reevaluate the selection of the proposed preferred alternative site for the disposal of silt
from the BHNIP. There were data available on benthic resources for many of the
potential disposal sites from other surveys, including a survey conducted by Massport
in April 1993.  These results were reported in the DEIR/S and were used for compari-
sons to the fall 1994 data.
F3-10 .

       Disposal of contaminated sediment at MBDS will not occur for the navigation
improvement project. A demonstration at the MBDS may occur to illustrate the
effectiveness of capping. Coordination with other agencies would occur before a
demonstration project was initiated.  Many of the issues discussed in this comment will
be addressed during the pre-demonstration meetings.
F3-11

       The BHNIP team has investigated the potential use of geotextile bags for
sequestering contaminated silts. While it appears that this technology might have some
promise for the future, tests to date have indicated that large-scale use would be
problematic.  The physical integrity of high-volume bags, as would be necessary for a
project the size of the BHNIP, has not been proven.
                                       22

-------
F3-12

       As indicated in response to comment F3-9, additional biological investigations
have been conducted.  No response to SEIR/S request.
                                        23

-------
         United States Department of the Interior

                     FISH AND WDLDLJFE SERVICE
                        New England Held Offices
                        22 Bridge Street, Unit #1
                    Concord, New Hampshire 03301-4986
                                                       June 17,  1994
REF:   1992-00844

UTC Dwight Durham
Acting Division Engineer
U.S.  Amy Corps of Engineers
424 Trapelo Road
Waltham, MA. 02254
Dear Colonel Durham:

SiX?ssv-«fS£


 General Cuimients *

                                                                    I
 the^unacceptable sites.  Additional '"S^^Se  *5t  environmental
an
    adequate administrative record for
 Specific Comments:,






 roain ship channel vaterfront.   Act^J PJ^ ^_ s^p channel waterfront is.
 foot MLW tritutary channels and the -40 foot ^^ SSpose.   -Die EIR/S
 not beii^ utilized for it* ?r9E^fS^tS?Srt SSls to the sain
 should evaluate relocation of ^Jf^g^^S add^-Sl expense and


  and dredge niaterial disposal.

-------
                                   -2-

The  no action  alternative,  with and without 	_   	^_
evaluated as part of the project design analysis.  This section       .
2 of the EER/S provides a brief discussion of some of the consequences of
not dredging Boston Harbor in the present context.  The ««^vs?l£f<£*
attempt to oUitify the no action analysis, nor is the analysis bcttandcwn
by future target year scenarios such as 2005, 2015, 2025, etc.  LOJcewise,


                                        ™^IJ3^£S



impact  of its rule--imposing draft limitations  and one way  teafficwas
minimal.  This is in sharp contrast to a statement on page 2-1 oe me ius/s»
which states "Not maintaining the channels to authorized depths
       Harbor to a minor port unable to accommodate deeper drarc  ^
      and petroleum tankers."  These contrasting views from agencies with
	=_tion  responsibilities  help  demonstrate  the  shortcomings  in  t~e
evaluation of the no action alternative.                                —

The build alternatives  (Full Project, Reduced Project and Delayed Action) do
not  evaluate maintenance dredging as an alternative action  in  rne sa_e
Sshion as is done for  No Action. This is an important issue because futare
maintenance  dredging and disposal  could have major consequences  for tte
identification, evaluation and selection of alternative disposal sites as
well  as overall project viability.  The maintenance dredge
Boston  Harbor channels and berths is contaminated  with to
organics and is not  acceptable for unrestricted open water    _
ETR/S  should adopt  a  consistent  approach to  the evaluation
maintenance dredging. Since future maintenance dredging was
the  No  Action  alternative,  it  should  be  considered with
alternatives  also.   An evaluation of the build alternatives^
maintenance dredging and disposal would provide a more real
of  the  environmental  consequences of implementing  the
authorized project.  Of the 376 disposal  sites evaluated,
Boston  Lightship  Disposal Site  (BIDS)  have  ^cesLJ=afa5,,  , -
improvement and 50-year maintenance dredging needs (EER/S Table 3 ^
                                                                           the
                                                                    list
             Die disposal site screening process described in-Chapter 3 was an J
             meth^ofeliminating potential disposal sites from f^?1^^0"2
             A universe of 376 potential sites in Phase I were pared down to
             of^4  sites and  onTtreatment  technique (solidif ^^
             While we are in general agreement with the Corps and ^
             the sites were not reasonable, we also believe that same reasonable sites
             were dropped from further consideration and that several sites carried as
             reasonable  alternatives,  should  have been dropped  ^..pte^Ina?heE
             screening.  We also believe that  all reasonable disposal sites have not been
             identified  nor evaluated.  This is especially true f«v. ^
             which  cannot be identified nor  evaluated as o"**01^^ ."
             sites.  The universe of 376 disposal sites only contained 21
             which demonstrates the inherent numerical inequity in the site selection <-nd
             evaluation  process.
                                                95
it-f

-------
                                    -3-
The Rowes Quarry site was dropped from further consideration during Phase_II
screening.  Rowes Quarry and other quarries received considerable discussion
as the DEIR/S  intimates on page 3-5.  Unfortunately,  the document fails to
divulge that the EPA found the Rcwes Quarry  site to  be an environmentally
satisfactory disposal site for residuals from  the MWPA facility at _ Deer
Island   This finding was published in the March  30, 1990 Record of Decision
for  the MWRA  Residuals Management EIS.  This  ETR/S  does not provide a
convincing  argument  to demonstrate that Rowes Quarry  or other similar
quarries  are  not reasonable containment  sites  for  the  contaminated
maintenance dredge  material.   The  information  on  pages 3-5  and E-14
indicates  that  the  quarries were dropped  as  reasonable sites because
Massport did not want to disrupt existing businesses or use Enunent. Domain
authority to acquire the property.  None of these reasons would appear to be
fatal flaws eliminating these or other sites from the list of reasonable
alternatives because these £*™> impediments existed during the MWRA. process ._
Several shoreline landfill sites such as Reserved Channel and Little Mystic
Channel were carried forward as reasonable alternatives despite the  fact
that Boston Harbor estuary has long ago exceeded the significant degradation
threshold for filling  and creating fastland  in  intertidal  and  subtidal
habitat.   Over 3,000 acres of intertidal and subtidal habitat have  been
filled to create fastland and several hundred additional  acres have  been
degraded by dredging. Against this background of environmental degradation,
additional shoreline landf in projects should not be considered reasonable
alternatives since they would likely be precluded by Clean Water Act and
other regulations.   It appears that several of these  in harbor shoreline
sites were chosen because they are depositional areas containing Category U
or III sediments and,  if fined  above  MHW, could be  used for  future
commercial purposes.   Most depositional areas in Boston Harbor  contain
Category  II  or HI  sediments, hence this is not a valid reason for fining
these sites.  Additionally, as Boston Harbor water quality improves in the
future, the natural sedimentation patterns win sequester these Class H and
III sediments with cleaner  material.                                     ^

The list  of  preferred alternatives was ultimately pared down from the short
list of alternatives by capacity and cost constraints.  Economics (cost) was
the major determinative factor for developing the final list of preferred
disposal  alternatives  (DEIR/S pg.  3-25) .   These, five  f^^*?????*
sites— MBDS, BLDS,  Meisberger 2 or 7, and  Spectacle  Island CAD— an  have
similar cost estimates.
                                                                         r—
Unfortunately, spatial and temporal information on living  resources at the.
preferred sites and the other reasonable aquatic sites  was not used to
develop  and refine  the  list  of potential sites nor  the list of preferred
sites. This critical information simply does not exist except possibly for
the MBDS.  Therefore, the  environmental acceptability of  Spectacle Island
CAD  Meisberger 2 or 7, Boston Lightship, and other reasonable aquatic sites
has not been demonstrated.   Additional data is needed to identify what the
spatial and temporal  characteristics  of  living resources are  at  each of
these sites on a seasonal basis before any determination  can be made that
these are environmentally acceptable as disposal sites.   Existing uses need
to be determined at the Section 404 sites to insure that these uses can and
will be  protected  in accordance with  the State antidegradation policy if
used for disposal purposes.  The full  disclosure provisions of NEPA cannot
be complied with in the absence of the spatial and temporal data on living
resources at these preferred and other reasonable sites.

-------
                                    -4-


During  the planning process  for this project and the  formal  designation
process  for  the MBDS,  considerable attention was  focused on  dredging,
transport,  and  disposal of  contaminated sediments  at offshore  disposal
sites.  Many of  these  concerns about contaminated sediments were expressed
in scoping comments provided by IWS for this EIF/S.   The questions  raised
about  mass  balance,  chemical  and  physical changes to  contaminants  in
sediments  from the  undisturbed  state until disposal, percentage of  fine
grained material and contaminant load dispersed during disposal, ability of
cohesive  parent material  (blue  clay)  to cap  fine grained unconsolidated
material, details of dredge management plans and other scoping issues  remain
unanswered and unresolved  in  this DEER/S.

Recent research  by the Waterways Experiment Station with, the use of  large,
barge size, geotextile containers may provide the Corps/Massport with an
additional treatment  technology  alternative for  the  disposal of  the
contaminated maintenance material.   However, the  DETR/S eliminated  all
treatment  technologies  except  solidification from the  short  list  of
alternatives.  If the Corps/Massport  intend to pursue the use of geotextile
containers as a treatment technology option at one or more of  the  J^f?^1
sites, a supplemental  EER/S will need to be prepared which evaluates  this
technology and the expected  environmental effects at the various disposal
sites. This new technology appears to have the potential to address many of
the longstanding concerns  identified in the preceding paragraph about open
water disposal of  contaminated material.

Conclusions

We recommend that the Corps and MassPort initiate biological investigations"
of  the preferred and other reasonable  disposal sites  to identify  rae
temporal and spatial characteristics of the living resources at each site.
This should include data for all seasons for at  least  a  one-year period..
While the  biological investigators are underway,  the Corps should address
each of the other outstanding issues raised by the  FWS  during  tie scopirg
and review process, including new innovative treatment technologies.  After
the requested data has been collected, demonstrations conducted, and other
information gaps have been  filled, the  Corps should publish  all of  the
information in a supplemental DETR/S so  that interested  parties;  have the
opportunity to  review and comment  on the  substantive issues  identified
during the review of the draft statement. We believe this information arid
process" is necessary before the  least environmentally damaging  practicable
alternative can  be identified and selected.

Questions  concerning these comments  should be directed to Mr. Vern Lang of
this office at 603-225-1411.

                                          Sincerely yours,
                                           Gordon E. Beckett
                                           Supervisor
                                           New England Field Offices

-------
                                    -5-
CC:   Reading File
      P. Jackson, NED
      Ed Wbo, EPA
      C. Ifentzaris, NMFS
      N. Faramelli, MassPort
      L. Bridges, MA EMF
ES:   VLang: jd: 6-17-94:603-225-1411

-------
F4-1

       Additional investigations on biological resources at all the potential aquatic
disposal sites were undertaken in fall 1994.  This information was reported in separate
technical documents and in Attachment 1 of the FEIR/S.  These data were used to re-
evaluate the selection of the proposed preferred alternative site for disposal of silt from
the BHNIP.
F4-2

       The Department of Interior notes that some of the land abutting deep channels
ha Boston's Inner Harbor has been converted to uses unrelated to Port operations.  The
Department suggests that converting these parcels back to port terminal use might be
more cost-effective than the proposed dredging.  It is true that some of the former port
terminal locations served by deep channels have been converted to other land uses.
However, relocation  of active port terminals to these sites is not readily achievable
because of the rigorous regulatory process that such relocation would trigger.  There
are environmental regulations in place which protect the residents and businesses near
those deep water facilities. In addition, relocation of place which protect the residents
and businesses near those deep water facilities. In addition, relocation of port termi-
nals would require infrastructure including backland and roadway connections to the
regional highway system.  This would entail years for permitting, land assembly, and
right-of-way takings  alone.

       The controversy generated by the proposed land use change could entail
litigation delaying project implementation indefinitely.  Further, several communities
along Boston Harbor have carefully developed plans to enable the general public to
enjoy the waterfront as a precious recreational resource. While these plans, such as
the Municipal Harbor Plan of the City of Boston, recognize the importance of preserv-
ing portions of the coastline for maritime industry, they also have zoning hi place that
would require change to support the relocation of port facilities.  This would require
months, if not years, to accomplish.  The combined effect of environmental regula-
tions, infrastructure requirements and  the rezoning process will likely preclude
relocation to port facilities as a viable alternative to the dredging currently proposed.
F4-3

       If maintenance dredging does not occur within ten years, ship traffic hi Boston
Harbor will continue to be forced to account for tidal delays. This will be happening
concurrently with regulations effecting vessel design such as the double hull require-
ment for tankers. The combination of delays and cost of constructing vessels capable
of use hi 33 - 35 foot channels will undoubtedly be passed on to consumers in the
                                        24

-------
 form of higher prices particularly for home heating oil.  Shoaling is currently affecting
 ships transiting Boston Harbor due to the need for maintenance dredging in the Mystic
 River and Chelsea Creek.

       An Environmental Impact Statement is being prepared for the Providence River
 maintenance dredging project. The U.S. Coast Guard has determined that restrictions
 on vessel drafts, one way traffic and communication does not impose an economic
 impact for the Providence port.  The EIS will perform a needs analysis to determine if
 the Coast Guard rule has an impact.  No maintenance dredging will be performed if
 there is no need.  Future conditions will also  be evaluated to assess when dredging
 may need to occur if there is no maintenance dredging now. It also needs to be
 recognized that the Providence River Harbor is used mostly by oil tankers while
 Boston Harbor is used by container ships and oil vessels. The benefit to cost ratio for
 Boston Harbor has determined that their is  an economic benefit to deepen the port.
 This analysis implies that the current navigation channels are not optimal for Boston
 Harbor.
F4-4
       The final EIR/S evaluates disposal sites for future maintenance hi Section 4.
F4-5
       The site screening process was reviewed for the FEIR/S and it was concluded
that the criteria used were appropriate for defining the shortlist of potential disposal
sites that was described in the DEIR/S.  The Working Group process that took place
during the preparation of the DEIR/S was one mechanism used to identify sites that
should be examined. Every site that was suggested during this process was given due
consideration by the project.  The difference in the numbers of aquatic versus terrestri-
al sites that were initially examined reflects the difficulty hi procuring basic site
information, not a prejudice on  the part of the project. We believe that the sites
identified are reflective of what could be available and are a suitable representation of
the impacts that could be experienced under the proposed project.

       The status of Rowes Quarry was reevaluated for the FEIR/S.  While there may
be disagreements over the  designation of fatal flaws in the DEIR/S disposal site
selection process, socioeconomic impacts are a consideration, and Massport remains
reluctant to acquire  an active business (such as Rowes Quarry) through eminent
domain.Alth.ough it  is recognized that it is technically feasible to use Rowes Quarry, or
other quarries, for disposal of contaminated materials, it is not a permitable activity
under the state solid waste regulations. Therefore, this disposal option is not a
practicable solution  for the BHNIP.
                                       25

-------
F4-6

       The shoreline sites were evaluated for two different disposal scenarios: partial
fill, in which the site would continue to be tidally submerged; and fill to fastland, in
which the site would be filled above the tideline.  While recognizing the historical loss
of aquatic habitat in Boston Harbor, the project feels that these scenarios fit within the
definition of Designated Port Area, as provided by the state in its Wetlands Protection
Act  Therefore, both scenarios were reexamined hi the FEIR/S (Section 4).  The
partial-fill scenario was found to be among the least environmentally damaging
alternatives. Because of the permanent loss of aquatic habitat that would be caused by
the fastland scenario, however, this option was not found to be among the least
environmentally damaging alternatives.
F4-7

       Additional investigations on biological resources at all the potential aquatic
disposal sites were undertaken hi fall 1994.  This information was reported in separate
technical documents and in Attachment 1 of the FEIR/S. These data were used to
reevaluate the selection of the proposed preferred alternative site for the disposal of silt
from the BHNIP.  There were data available  on benthic resources for many of the
potential disposal sites from other surveys, including a survey conducted by Massport
hi April 1993.  These results were reported in the DEIR/S and were used for compari-
sons to the fall 1994 data.
F4-8

       Disposal of contaminated sediment at MBDS will not occur for the navigation
improvement project.  A demonstration at the MBDS may occur to illustrate the
effectiveness of capping. Coordination with other agencies would occur before a
demonstration project was initiated.  Many of the issues discussed in this comment will
be addressed during the pre-demonstration meetings.
F4-9

       The BHNIP team has investigated the potential use of geotextile bags for
sequestering contaminated' silts. While it appears that this technology might have some
promise for the future, tests to date have indicated that large-scale use would be
problematic.  The physical  integrity of high-volume bags, as would be necessary for a
project the size of the BHNIP, has not been proven.
                                       26

-------
F4-10

       As indicated in response to comments F4-1 and F4-7, additional site investiga-
tions were conducted in fall 1994. Results were used to augment the disposal site
selection analysis (Section 4).
                                       27

-------
APR-.19-94 TUE 14:33     N«FS HPRD               FAX NO. 15082819301
                                                                P. 01
                               UNITED STATES DEPARTMENT OF COMMERCE
                               National Oceanic and Atmospheric Administration
                               NATIONAL MARINE FISHERIES SERVICE
                               Northeast Region
                               One Blackburn Drive
                               Gloucester, MA 01930

                                  APR  I9I994


Colonel Brink P. Killer
Division Engineer
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, MA  02254-9149

Dear -Col. Miller:

We have reviewed the Corps1 Biological Assessment of potential
impacts to threatened and endangered species from the disposal of
dredged material from the Boston Harbor Navigation improvement
Project.  The National Marine Fisheries Service has determined,
pursuant to  50  CPR Part 4 02. 14 (f),  that additional information is
needed for us to formulate a Biological Opinion under Section
7 (a) (2) of the  Endangered Species Act.

The Corps1 Biological Assessment includes a discussion of the
disposal of  contaminated sediments at the Massachusetts Bay
Disposal Site  (MBDS) and three additional offshore sites.  The
dredged material  in question, silty sediment from future
maintenance  dredging of Boston Harbor/ is considered unsuitable
for unconfined ocean disposal.  MBDS is designated for disposal
of  "clean" material (suitable for unconfined ocean disposal)
only.  However, the Corps proposes to dispose of the silty Boston
Harbor material at MBDS with capping, the rationale being that
disposal  of  contaminated material with capping may be allowed in
the  future if capping can be proven to be viable at MBDS.

The  Biological Assessment provides scant justification for its
conclusion that capping can be used  successfully at MBDS or  other
offshore sites, and therefore that disposal of contaminated
materials with capping would not jeopardize the continued
existence of listed species.  The document states that "the  Corps
has technical evidence that capping  can work at MBDS, based  on   — .
previous experience," yet  it does not discuss or cite this
evidence.   Similarly, the  Biological Assessment does not discuss
the efficacy of capping under the environmental conditions
present at MBDS,  including waters up to 100 meters deep.  The
document also does not address the possible cumulative effects  of
specific contaminants from this and  other projects  (e.g., the
MWRA sewage outfall) on listed species, nor does it  substantiate
the , conclusion that capping at MBDS  or  other offshore sites  would
eliminate the potential for contaminants  to bioaccumulate or
transfer through  the food  chain.  Finally, the . Biological
Assessment does not specify the anticipated volume of material
 (clean or contaminated) proposed for future maintenance dredging.

-------
F5-1

       Additional information has been sent to the National Marine Fisheries Service
to help formulate a Biological Opinion.
F5-2

       Capping silty material at the MBDS for the navigation improvement project has
been eliminated as an alternative for BHNIP.
F5-3
       Refer to comment F5-2.
F5-4
       Refer to comment 75-2.
F5-5

       These figures are in the EIR/S.  They will be included in the Biological
Assessment.
F5-6
       Refer to comment F5-2.
F5-7

       The Corps will send a Biological Assessment which eliminates the disposal of
contaminated material at the MBDS.
                                      28
                                              0,5

-------
APR-.19-94 TUE 14:33
NHFS HPRD
FAX NO.  15082819301
P. 02
     Because of the deficiencies in the Biological Assessment, we
     request that the Corps provide additional data and analysis to
     help us determine the extent'of potential impacts from the
     project to listed species.  Specifically, NMFS, the Environmental
     Protection Agency, the U.S. Fish and Wildlife Service, and the
     Commonwealth of Massachusetts have all recommended in the past
     that the Corps conduct a capping demonstration project at MBOS
     using clean materials marked with a distinct signature to allow
     analysis of the entire disposal process, including cap placement
     and integrity over time.  Without this type of in situ study-
     using clean material, the environmental feasibility of confined
     ocean disposal at MBDS will likely remain in question.

     We recommend that the corps either agree to extend formal
     consultation until this data is available, or drop capping at
     offshore sites from further consideration (and revise the
     Biological Assessment accordingly) until the questions
     surrounding the feasibility of capping are resolved.  Extension
     of the consultation period for more than 60 days would require
     the consent of the applicant for the non-federal portion of the
     project.  Alternatively, if the Corps elects not to extend
     consultation or modify the proposed project, NMFS will issue a
     Biological Opinion using the best scientific and commercial data
     available, including a conservative presumption that capping at  _
     MBDS would not be successful.

     Please inform us at your earliest convenience as to how the Corps
     would like to proceed with this consultation.  If you have any
     questions in the interim, please contact me, or your staff may
     contact Chris Mantzaris, Acting Chief of my Habitat and Protected
     Resources Division, at 508/281-9346.

                                        Sincerely,
                                        Allen E. Peterson, Jr.
                                        Acting Regional Director
     cc:  John DeVillars, EPA Regional Administrator
          Ron Lambertson, USFWS Regional Director
          Trudy Coxe, Massachusetts Secretary of Environmental Affairs
          Janeen Hansen, Massachusetts Port Authority

-------
  STATE AGENCIES
COMMENTS AND RESPONSES

-------
iii.il	!<
                                                                     	'Ill


-------
  WILLJAM F. WELD
    GOVERNOR

ARGEO PAUL CELLUCCI
 • LIEUTENANT GOVERNOR

   TRUDY COXE '
    SECRETARY
                                    June 30,  1994
                                TeU (617)727-9800
                                Fax: (617) 727-2754
           CERTIFICATE OF THE SECRETARY OF ENVIRONMENTAL AFFAIRS
                                   ON THE   :
                     DRAFT ENVIRONMENTAL IMPACT REPORT
     PROJECT NAME

     PROJECT LOCATION
     EOEA NUMBER
     PROJECT PROPONENT
     DATE NOTICED IN MONITOR
Bos-ton Harbor Navigation Improvement
Project and Berth Dredging Project
Boston
8695
Massport
April 25, 1994
          The Secretary of Environmental Affairs hereby determines
     that the Draft Environmental  Impact Report submitted on the above
     project adequately and properly complies with the Massachusetts
     Environmental Policy Act  (G.  L.  c.  30,  s. 61-62H)  and with its
     implementing regulations  (301 CMR 11.00).


     Introduction              _

          The Boston Harbor Navigation Improvement and Berth Dredging
     project (BHNIP) is a major infrastructure betterment project that
     has been linked to this region's economic vitality.  The proposed
     dredging project will help facilitate the movement of goods by
     improving navigational efficiency and safety, and minimizing
     double-hauling of cargos  in the 47 square mile Port of Boston,
     which handles more than 25 million tons of cargo,  worth more than
     seven billion dollars annually.

          The BHNIP includes deepening of two areas in the Main Ship
     Channel (the Inner Confluence and the mouth of the Reserved
     Channel) and dredging of  three tributary channels (the Reserved
     Channel, the Mystic River Channel,  and the Chelsea Creek
     Channel).   Approximately  3.4  million cubic yards (c.y.) of marine
     sediment needs to be dredged, including 1.32 million c.y. of
     unconsolidated silty material that lies above 2.02 million c.y.

-------
EOEA. #8€95
DEIR Certificate
                                                    June 30, 1994
of 'uncontaminated clay material and 0.132 million c.y* of rocfc,
Boston Harbor was last dredged in -1S83.  The P^oj^t has two
proponents; Xassport and the U.S. Army Corps of &iguie«r* *^,«..i
rusACOEi    Accordingly, the documents revieved are both a federal
0?f ft InviroSental Impact Statement  (DEIS) and a state 'Draft
Environmental Impact Report  £IR) .  The project is scheduled to
begin early in 199*.         .           .

    •  The DSIR points out an overriding problem vith dredging
»W^e£ts  including the BHNIP: »(t)he lacfc  of suitable disposal,
ll?lr^llives hSvf !sic) delayed port improvements not^only in .Hew
InglSS *£. nafioniide.1-  Recognizing this, I ^v. mj
-------
                         DEZR .Certificate
.June 30,  1994
     The Draft.Environmental Impact Report »  These goals
can be divided into four discrete tasks, including: (1)   -
reconsideration of certain criteria used to identify practicable
alternatives arid, depending on the result, revisions to the. list
of disposal option alternatives; (2) comparative analysis of
environmental  impacts of the disposal option alternatives; (3)
more detailed  analysis of the preferred alternative (s>,
contingency alternative, and least impact alternative; and <4)
development of a Dredging Management and Monitoring Plan.  Later
sections of this Certificate provide specific guidance on these
tasks.                                            .
 standards for disposal at the KBDS.

                                 3

-------
EOEA #S695
DEIS. Certificate
June 30,
     The DEIR/DEIS indicates that the final selection of a
preferred disposal option(s) yill be made based upon agency and
public comments.  The consents, however, indicate, that there is
not yet sufficient analysis of the potential environmental
impacts of all of the disposal option alternatives at this point
to support selection of disposal options and demonstra t.e that
they are both environmentally sound and consistent vith the other
project requirements.  Moreover, reconsidering and reapplying the
screening criteria could result in an expansion of the list of
IrSctiSlle sites.  Consequently, the FSI* "Jftjg;?1^ .
Additional information about several. °* tt« diS2°KL.f2H0?,v   '
alternatives .{See "Practicable Alternatives" and -Potentially
SacScabie Alternatives" belov) to ensure a truly comparative
analysis of impacts at as consistent a level of detail as
possible.                          .              :
 •  •  The Final. EIR must explain clearly hov the. fnar ste       "
selection »rocess was accomplished.  The criteria, applied and the
Witt selection process should be discussed in sufficient detail
loal!SStre5ie1e^tf independently confirm that the selection
has been based on the established criteria and that the criteria
used are defensible. '                             :     .    .
     The report must also provide a more inTdepth; ana lysis of the
       ill  impacts of the preferred .altemative(s)-> and possibly
       alter?llivJs? vSch are idescf ibed in ther Preferred Disposal

                                      W
 comments and in this Certificate.
 and-Monitoring Plan.

  ••: '  Taking into consideration the ^eadth of the^requggents
 for the FSIR, it may become necessary to «£*« SLlf^heFEXR '






 SoniSring%lSngcoSd be developed as P«%«£ *%« **G™*
 installment  (or afterwards).'  The comment from the
"cotltal Zone Management Agency  (SCZM) plains how
 1p  treated in the F2IR and SFSIR, respectively.   ,
               - - c


-------
                          OZIR Certificate
June 30, 1S94
      While this two step final review process is not an absolute
.requirement, it aay be the best way to ensure that a more
 complete understanding of the alternatives and their
 environmental impacts will be developed before the preferred
.alternatives are selected, and also to help the agencies reach
 consensus sooner, rather than later*  This approach may also
 minimize the possibility of proceeding too far vith an
 .alternative that may ultimately be"'unacceptable or infeasible.
 In short, I believe this approach will provide the most
'predictability and efficiency*"    ...
         Pesar.jption
 .   .  'Characterization and quantification of the sediments is an
•-essential requirement of the proposed dredging project.
 •Understanding what this project 'is. yill establish basic
 .requirements of the disposal site.! 'According to the DZIR,  the
 quantities of sediment affect the duration of dredging,  the
 •duration of the turbidity plume, the amount of habitat affected/  1
 '•and the duration of interference vith navigation.   As part of the
 comparative analysis of the alternatives, the FZIR should provide
 a better understanding of the .impacts and explain the differences
 between the alternatives.          •*

      Through the SIR review it wili-. be important to Xeep track of
 .the changes in volumes of contaminated materials or those
. considered to be unsuitable for open ocean disposal, because of
 the critical balance that must be achieved between environmental
 impacts and project cost in the disposal site selection  process.  -
 The larger issue of finding a disposal site for this project and ^
 •the future maintenance dredging .required by this project has been
 confronted in the DEER.  Future -mafrxfcenance dredging over the 50
 year life of the project has been estimated at $.2 million c.y.  .
 of silt, exclusive of dredging that: will be required for the
 berthing areas..  While the proponent, agencies have not made it a
 goal of this project to find a disposal alternative(s) that will
 accommodate both present and future .dredging volumes, the DEiR
 :has identified and considered potentially practicable
 alternatives for the future dredge, disposal requirements.  To the
 extent that it is possible,, the future maintenance dredging and
 disposal needs should be taken into account in the FSZR analysis
 of disposal alternatives.           ,               .             -

      According to Kassport and the'^SACOE, the estimated volumes
 of dredged materials should not change significantly from the
 estimates in the DEIR.  Even so, the proposed project has been
                               /or
                                                                      oft

-------
r
        BOEA
                                •DEX5
                                  ..:  '  June 3O, id94
        Modified somewhat from the project "described in /the Environmental
        Notification Form (ENF) and., according to the DEIR, -It is
        anticipated that a number of these minor reductions and possible
        'enlargements to the project will occur as the design is
        finalised.-  -Originally, about 23 berths were to btf dredged
       •/about 0.8 million c-y!)  In Appendix C, Table 1, IS berths are
        novlisted for dredging, with a. total of about 570,-796 c.y.- of
        material.-   Has the DEIR accounted.for the maximum  volumes  of
        sediments from the berthing areas?-

        -" *   -Furthermore, the DEK, Oiyisioh of Waterways has recommended
        that the channel modifications, identified in Appendix D should be
        Scorporated into the project.  What increase in volumes yould
        •—?ulP  There is also a possibility that the dredge profile in
          1 cK^iaea CreS could be expanded*if the Chelsea Street Bridge
           rSlaSed S She city of Boston..:-;According to the DEIR, -There
              •interest in reviewing the navigation channel to consider
                 and deepening to accommodate larger vessels."  xr
        tsossible  estimates of the increase .in dredged sediment volume
        should be provided in the FEIR.  By providing this information,
        ft may be possible to avoid a separate Notice «* **2«* **«*•
        review.  Would it be necessary to r^test the sediments for an
        expansion of the Chelsea cree* dredge?          :             :
          ^^            •            .      ru" •             .           , .
          "   The project proposal includes^  0.5 foot overdredge, ^ij«


        •
        SvSdredge  in terms of project volumes and impacts.
according to
                                            the

         With 301 CMR 11.17.
            cover 15  sites

-------
JEOSA
D21R
                                                 ::   J\in« 30, 1994
 .-   The marine.sediaent characterization vas based :on a    •
>4«r^S «vaSation of the materials to determine the acceptability


















 ^ii^^J  »fiS^larly for in-haarbor and coastal containment
 sediment,  P5^1?^1***!,,^  VfiVeover. for these alternatives it




 time.                              .               .    .
 fi'j


                                                                 .

       • For upland reuse disposai, D» regulations and policies may

  require additional analysis.
                                                     d  SS:3"i

-------
EOZA #8695
DEIR-
'June 30,  1994
•include shoreline facilities, subaqueous depressions,, borrow
pits,  in-channel trenches, and open, water disposal sites.   The
•OEXR has thus provided a useful model that may be applicable to
other  dredging projects.  That being' said, this review would. b«
less than rigorous if it die .riot raise questions about the
criteria, the process of selecting among options, and the results
of that process.              ..     ..                   •        •  ...

  •'/ potentially practicable sites/-evaluated against'the
screening criteria, were eliminated based on either .a failure to
neet the minimua of 200,000 c.y. capacity and/or the comparative
cost;'exceeding 4 tines the cos.t per"cubic yard as compared to
ocean disposal .  Based .on comments received,  these
screening criteria need to be reconsidered.            •

     . in the-select ion of the preferred disposal alternatives,
 sites vith capacities less than 200,000 c.y. were .dropped.
However, as^he DEP and the KC3K comments point out, some of the
Sbleline filling and bul*heading alternatives could P°j;i*ly.
Seet this criterion when the volume between mean low water and
Setn Sgh v5er or fast land is included.  These alternatives
Slsb appearto^be promising because the wetlands resource
 pelforllnce standards are less restrictive in a ^*«g~i****
       in which a nuabir of these sites are located.  Therefore,
          shoSd reSnlider- those alternatives that would meet the
         volume reCTuirenents  by the  creation of new land.
             ?? theFSIR should reconsider whether  this is the
             lover  limit for-the disposal  needs of  the project,   .
    -  cost is a key screening criterion in the disposal
 screening analysil.  sites with disposal costs greater.
 SSetthl costof capping at the Kassachusetts Bay Disposal
  WW) verf considered excessive {p. 3-2 S)   However, as. has been.
 pointed  out in the DEP comment, there may be a more _*Pg>°
 basis  for establishing baseline costs.  Specifically;, the

 S!a!?y*£^
                                         ifSS SS>? fs could
 ?LuS in a SlSf icaltly different conclusion  as to which
  options are prlcticable.  The FBIR must address this, issue.

   "":  To address these issues, the potentially practicable sites  1
 i»ust-be reconsidered in the FEIR.                •                -41
                                  8

-------
 -19S4 13:27  FROH   HRSSPORT
                                       iu
EOEA #8695
                        P£2R Certificate
                                                    June 30, 1994
               Alternatives
 -, ,*   »
yielded a short
                  site screening.steps outlined in th* W* Jj*™
                     of "practicable" alternatives, which have

                                .t, *{a)re available and capable

                    takincr into consideration cost, ^existing

            and" logistics in light ctf overall project purposes"

(CFR 230:iO (a)(2».               >.             ':(
 project                                           .











 hazardous, mat^ia^a^/or^oactlvevaste^^^ ^^   :,


 coamenters have «V**'Md     s*'          because" of the -
                                                                s
  unsure about the Y^i;ii«Lblv^e concluded that the public has
               X* can                     the Massachusetts Bay

                                                           as-
  further.                      .
                                                        S:2T tSST—SE—"Fir
                                                                      J03

-------
EOEi #2655
DEIR. 'Certificate
sites,  the in^channel trenched cog-er options,  'the
30, 1994
                           Spectacle
 Island CAD,  the-Boston Lightship si€e,  the MBpS yith capping,  and
. the'JauiJcheading' opt ions..     •'   ;         ',';•'      j

   .'  Generally, the FZXR analysis oil; .the site specific impacts at
 the disposal site alternatives"should expand the; understanding of
 the potential for habitat loss 'or alteration, water .quality
 degradation, migration of contaminants from the disposal site, .
 and land based impacts on traffic, the built environment, and
 land, use*        •
  •'••.'••        '        *racticabl« ait^raativts

 ".""V* "The six practicable alteraatr^ax  identified : in the DBIR all
have" sufficient: capacity to accept the total volume .of dredged
material, except for the .in-channei»i:trench and coyer  .
'alternative. -This alternative "was »ot carried forward as a
.preferred Alternative because, it vis' determined tip have.
insufficient capacity.  However;,  there is sufficient public
interest in this alternative to warrant further consideration.

     -All of the. disposal alternatives  propose to release the
contaminated silts f roa barges .and iihen cover those Isediments
vith uncontaminated parent material';yhich is primarily. Boston
Blue Clay.  The difference in properties between these two
classes of sediments raises questions  relating to the technical
feasibility of covering adequately the f iner-graihed and less
consolidated silt materials with cohesive, dense .clays.  In
'addition, what period is required to' ensure that .the silts have
•settled and hov vill that be factored  into the project design?
To what extent vill- the crude operation of dumping clay
destabilize and displace the silts? How will this be addressed
in the project 'design?  The FSIR.should provide documentation to
deal with these questions and to support the plan that is
proposed.      "           .
   * •         *

Massachusetts' -Bay Disposal site.

  •  ." .'-Although, t&is is the only officially designated dredged
material disposal site under consideration, there are certain
"conditions for. dredged material at the MBDS that will affect the
BHNIP  proposal to dispose of the contaminated materials at this
site,   specifically, contaminated materials must be capped or
covered with suitable dredged materials and, before that can

                                -10

-------
                                                     June 30', 1994
 approved, a pilot project mustpbe undertaken to demo'nstrate' tho
 feasibility of the capping 'tecfiniqu*: at the      '
      The comments indicate that this: alternative is yidely
 disfavored, and many have suggested Vthat it be dropped "
 altogether.  Although I aa ncVaaJding that recommendation at this
 point, because or the potential utility of a pilot study in
 addressing some of the acre difficult, generic, a'nd '"unanswered
 questions about dredged material disposal, this alternative does
 not appear to be promising.  ' •    - •' •            : •  .   •
      If Massport and the CSACOfc pursue a pilot or demonstration
'study of capping at the KBDS, a proposed scope for that effort
aust be prepared and circulated for -'comment to those who
participated in the -Working Group and also to the commenters
listed at. the close of this Certificate.         ;   :       s
fiestas Lightship
                           ! -s:-?-.
   .   Capping has been-proposed- at tfife Lightship,  a's. well as: the
KBDS.  However, the feasibility of Capping at the Boston
Lightship site, vita depths of about: SO meters appears to be
questionable and needs to' be •demonstrated, if this alternative  is
•pursued.   There is evidence that the: rate of sediment transport
may  be significant during severe sto» events, with a 1*5 year
frequency, in the vicinity of the Boston Lightship site.  This
•raises questions about the long term ^effectiveness of capping due
to erosion, impacts.               ' r~-"               ;          .   -

. .'•  •  if this alternative -is pursued-jr :the FBIR must,- at a minimum,
provide documentation and dataT'fromComparable capping projects
to support the proposed plan' (see also the HCZK comment)  and
expand on the analysis 4n the referenced study to provide more
information about the effects and feasibility of  capping at the
Lightship site.  The FEZR should also consider whether there are
ways to design the project so as to.Censure that the contaminated
sediments would be isolated.  • Kitigation measures,' contingencies,
and  monitoring could also- be- considered to demonstrate long term
stability of the capped dredged, material.  An assessment of
potential impacts should be provided,  assuming (1)  that the
project succeeds as proposed and,  (2)  conversely, that the
           Chimin  Chian,  9aen-^Wateg-  Disposal  and  capping  of
Contaminated  Dredged  Kater^-al  at; '-the  Boston Liqhtsfrftj^ Site
(n.p. :n.p. ,n.d.)                   •              •••-.-.

-------
f
         20S& #8695
                         DEIR Certificate
June 30t, 1394
project is net. successful,., i.e.. contaminants are-hot isolated at
the disposal site.  What contingencies can be incorporated in the
project design for scenario (1)?

     While the. Boston Lightship site may hold some promise
because or the potential to use the" dredged materials as * cover
over contaminated areas where hazardous materials/or radioactive
wastes were disposed decades ago, this opportunity is off-set by
concerns about impacts to the marine environment; these concerns
will need to be dealt with in the FEIR.  Specifically, the area
supports commercially important fisheries resources, which would
be adversely impacted by the. selection of this disposal -
alternative,  if this alternative is pursued, a thorough analysis
of potential impacts to these resources will be required.
comments from KC2K and others can be of assistance in providing
scoping guidance.  In addition, a detailed scope of work must be
developed by the proponents in consultation with the WG and EOEA
agencies.  Such a scope should include a bathymetric survey of
the existing vaste materials, in order to optimize the
environmental benefit* of capping waste materials at the proposed
site*  'It will also be necessary to pinpoint a specific location
where it will be possible to minimize harm to marine resources*
The comment from the Division of karine Fisheries indicates that
comprehensive .benthic and contaminant studies should also be
done*           '            .      •. '•            .-'.-'.
         £&*C&a&nel, Treach and cover ."-•    -               *
            •          '.                .*                  -         • .  *
              The option, to dispose of .contaminated* materials within^
         channels that have been overdredged and then backfilled and-
         capped with uncontaminated parent materials has been well
         received, in concept.  However, the logistics arid ;technical
         feasibility of accomplishing this alternative are quite complex,
         and there appears to be significant opportunity for damage to the.
         environment.   •              __                     j

         The multiple steps, which include dredging of contaminated and
         parent material*, stockpiling of those sediments  :m order to
         Sequentially dispose of the contaminated silts to ensure
         isolation of these sediments will require exacting precision .Ln
         the dredging operations and careful timing to avoid environmental
         Impacts.  Realistically, the analysis of this alternative should
         probably factor in a certain degree of environmental fjmage in
         acknowledgement that this alternative will be difficult to
         accomplish without impacts.  Is there a point at  which the

                                         12

-------
 EOEA
              0EIR- Certificat*
                                                           30,  1994
 potential impacts of this alternative would be unacceptable?  Hov
 will potential -impacts be mitdgated>:-            * •  i  • •'-       '
   *   •     •      "              "*•••""*,
 •  -:  iapacts of barge tra'ffic'.qn existing boat traffic in the '
 harbor also need to be considered, opportunities !to aanase the
 project so. as to minimize navigation conflicts should be
 explored.                   •  •                   :   .

  .,. .'.;'Tf this alternative is" pursued^' a aore detailed scope of
•work/ including a aore in-depth assessaent of impacts"will need
 tM.be developed.  The WG would, be a reasonable forun for
 addressing the scope issues. . .State agencies will as'sist by
 providing guidance as well.   .    *

                               '*•''. .-
 Spectacle Island c&D          "X    '_."_- .

 . '.   This disposal alternative is a'.Shallow subtidal borrow pit.
 Based on the comments from EO2A agencies, this alternative should
•not. .be carried "forward.   Due to  the 'shallow depths of the site,
 storm-wave impacts to harbor resources is a significant concern.
 There is also a potential for impacts to the seawall and dike
 being constructed as part of the. Centx*1 Artery landfill closure
 project at .Spectacle Island.   "She artificial reef project could
 also  be iapacted by this disposal alternative.
                                                       J
Sites
                     and
   .'  Two areas, off Deer Island'-havei^een proposed .-as borrow" pit
disposal sites.  This alternative would require dredging at the
site to create the borrow pit/  reuse or disposal of the silts/
sand and gravel froa the site, 'disposal of contaminated aateriais
•in -the pit, • and covering of those materials with, .uncontaainated
parent material.  Based on the  preliminary information, this
alternative is considered promising,  A borrow pit appears to
offer an effective way of isolating .contaminated .sediments.
Moreover, the sites are shallow, enough  to* allow controlled
.placement of the materials/ but deep enough to reduce erosional
effects.  This option would provide sand and gravel aateriais
that could be used to renourish beaches,  and ultimately the site
would be restored to pre-exis.ting conditions.

  : . .However, the Division of Marine Fisheries has serious
concerns about the acceptability of. 'these alternatives because  of
likely impacts on fisheries. " That agency is concerned that these

                                13


-------
     #8695
DEI* certificate
•June 301 1994
alternatives  have been carried" forward because of- the lack >.ef
fisheries  samp.ling data in th« area,.  Therefore,  impacts on
marine resource* must be evaluated, in the-FEIR,  including the
effects on ground fish and commercial lobster ing.  Xcrexdetail€:d
information vill be required if this alternative is. pursued, as
explained  in  tbe Division of Marine Fisheries comment.  What
mitigation options~~are available to minimize damage to fisheries
resources?         .               :'

     The comment from the Kczk also, lays out the Issues that vill
need to be addressed more fully in.,the FEXR, if this  alternative
is  selected.   Existing information on-borrow pits, additional
site data, and borrow pit design, ctiteria should be developed to
better assess the feasibility of this alternative. % Environmental
impacts should be assessed,  furthermore, the scoping guidance
given above  for analysing impacts to resource areas at the Boston
Lightship  site should also be .used..for the  borrow pit sites.  The
FEIR must  also -consider the potential effects on the  KWRA ocean
outfall system and the monitoring program for that system.
               Potentially Practicable alternative*
                
-------
EOEA #8695
DZZR
; June 30, 1994
conditions, the dredged materials would be acceptable for
specific uses.   The requirements for daily cover material .were
only provided for the Fitchburg/Westminster and
Plainville/Laidlaw landfills. ' Are there  ether landfills that
could accept -this material?

      The CCR landfill site was .screened out.   Given  that :recent
Notice of Project Change filings wiifch KSPA indicate  that there
are'.-plans to extend the life of the landfill,  this alternative
may be worth reconsidering.  Hbre information  is needed  on the
wrentham site/ as.veil.      •     -. ,            •  :
  ""'••".                    - "  r~'              '          •' •
      Dewatering options and .di&watering  sites must be studied in
greater detail in the FSIR.  .Details, on a  dewatering .facility iat
Kystic Pier or .the North Jetty.should be provided.   An assessment
of  dewaterizig .technologies should focus on demonstrating that the
material will be acceptable for reuse in landfills.  \The impacts
of  increased truck traffic in the traffic  corridor serving the
dewater site should be analyzed also.   In  addition,  the  F£ZR  •
should address how the applicable irater quality standards (314
CUR 3.OO)  will be net.

      Castly, if aonofills or landfiil cover alternatives are to
be.pursued further, more site  specific information  will be
required and a scope of work will need  to  be developed.  The WG
and EOEA agencies should be included in that scoping process.
                                         S1-42
             aad Filling 
-------
        EOEA /3695
                         DEXR. Certificate
f
30, 1994
c
 '  . • The DSP regulatory requirements" for construction arid use o£
this type of site are being reconsidered and will probably be
changed in the. Comprehensive Dredging Regulations that are being
developed by DSP.  Until that time, however, as tine DEP comment"
points out, off-site disposal of dredged material^, not at a 2 IS
site'or an existing solid waste landfill would be regulated under
Beneficial Use Determination procedures and the Division of Solid
Waste Management siting and plan approval process.  With respect:
to the latter, siting requirements are quite rigorous.

   .. The potential impacts of disposal of contaminated materials
nearshere must"be addressed.  In addition, neighborhood impacts,
Including odor, noise, and traffic, "must also be Assessed.  In
areas outside  DPAs, consideration should be given to land use
opportunities  for created land that would improve the quality of
life "in affected neighborhoods.  The environmental equity issue
must be addressed, where applicable* .

     •An analysis of the potential impacts to fisheries, including
anadrombus fish runs in the Mystic River, and bentihic environment:
due to changes in the tidal prism, flushing and water quality
should also be provided in the FSIR*  Further, as = noted in the
DEIR, 'inshore  alternatives such as this will require-mitigation
to minimize the turbidity pluae.  An .analysis of the pluae before
and after mitigation should be supplied in the next' report.

     If this alternative is selected, more detailed Study will fee
required as indicated in the comment*.  Again, a scope for that
study must be  developed with agency guidance.   • .. •

   "  Two alternatives were not identified in the »EIR under the
category of nearshore filling and butfcheading.  They.are: Fort
Point'Channel, the upper -reach, whic&-may become u;aore
attractive alternative.^* a result-of potential changes to the
Third Harbor Tunnel project in this area; and Conley Terminal, in
areas where vork may be proposed under the .pier decking.  These
two 'alternatives appear to warrant further consideration and
analysis of impacts for the disposal "of contaminated dredged
materials.   •                                     .:
                                                                        •i
        .Innovative Treataent Technologies   •;"..
        * '  •                          '.*':.               •
            • "While significant questions need'to be answered, innovative
        technologies hold promise,  especially for highly contaminated.
        sediments, for "stabilization of contaminants, and for volume

                                        16  ...


-------
 EOEA #3655
DEIR Certificate
/June 30, 1994
 reduction of dredged materials. : Thus, potentially practicable
 treatment technologies should be pursued further in the FEIR a
-the following recommendation frba the MCZM should be  advanced,
 "The FEIR-should identify a practicable remedial technology that
 can be implemented as at least a demonstration project.   The
 USACOE and Kassport should work closely with commonwealth
 agencies to identify a funding mechanism to support this element
 of the SHNIP."                     .             .
                 Alternatives
    '  In developing the disposal options,  volume, sediment
 quality, environmental impact, and practicability were
 considered.  Many of the disposal options described  (p. 3-11
 through 3-17) included more than one disposal  site alternative.
 However/ as it turned out,  when the disposal options were
 screened further, based on  capacity, environmental benefits, and
 cost, only one disposal option with multiple disposal sites was
 deemed to be a "practicable alternative*.

   •.  There is considerable  support among  the SOS& agencies for
 reuse of the materials in landfills', new  land  creation, and
 innovative technologies. These additional disposal option
 alternatives must be reconsidered in -the  FEIR  to determine
 •whether they meet the criteria established for "practicable
 alternatives."  Specifically,  the information  provided in the 0£P
 comment about potential landfill, capacity and  additional reuse
 opportunities should be used in the reconsideration of Option XI.
 The shoreline containment areas in Option Bl,  and possibly Option
 BS, .should also be reconsidered because evidence has been
 provided that there may be  sufficient capacity at the shoreline
 sites, for disposal of significant volumes of dredged material.
 with respect to the Land-Based Aquatic Combinations under option
 category *c«, it is unclear whether a combination of landfills
 and aquatic shoreline sites would now meet the criteria
 established for "practicable sites."  While I  am not advocating
 the Inclusion of many additional sites, I believe that various
 combinations of disposal alternatives may offer flexibility 'and
 new disposal option combinations may present themselves, which
 achieve the necessary cost  benefit requirements while satisfying
 environmental protection standards..  For  this  reason, it may
 ultimately be wiser to carry forward an alternative (s) in this
^category into at least the  final screening step.  The FEIR should
 address this issue.
                                17


-------
 EQEA.
DEIR Certificate
                                                           30,  1994
 Preferred Disposal option    •'•"'"•            ':

    .  If the preferred disposal option selected has :not been
 ranked as. having the "least environmental impacts" from among the
 final list of "practicable alternatives", then the FEIR must
 carry forward, for comparative analysis purposes, both the
 preferred and the "least environmental impact alternative."  To
 the extent possible, the FEIR-.must, itlso show that the impacts of
 the preferred option will not be greater than the impacts of the
 "least environmental impact alternative,11 taking into account
 mitigation measures and any potential environmental benefits of
 the- chosen plan.                                  . :.

      'It may also be prudent "to carry forward a back- up
 alternative disposal option plan.  To a great extent* the
 decision to do so would be. based on the significance of the
 outstanding issues following further assessment of the disposal
 option alternatives.               .              :
                              •    *
      For the disposal option plan selected,  a Drtfft Section 61
 Finding should be provided to show that the impacts1 of the.chosen
 alternative(s) will be addressed in the project design, in dredge
 management,  or through mitigation/ and damage to the environment
 will be minimized to the greatest extent feasible.
          Management aneLJfonitorineLJPlan
      The DE1R .indicates (SS-5)  that •• procedures will : be developed
 in. greater detail for the preferred disposal alternative once rthe
'type and location of the preferred :site(s)  is identified. Ther;
 Plan must demonstrate that impacts .to the environment from the
 dredging project will be avoided and minimized.  The  comment from.-
 the MCZK should provide guidance for addressing this  issue.   That
 comment also considers the requirements of a monitoring plan that
 should be .included in the FEXR.    .              '  ,
               impacts on Water Quality

*     The following issues should'be..'considered in the FEIR in
order to demonstrate that the project design,  and dredge
management techniques will be utilized to minimise water quality
impacts:                            .              '.     ...

                             -  .' 18

-------
 EOEA #8695
DEIR Certificate
June 30, 1994
      o The rigorous turbidity controls identifie
-------
C
            EOZX #8695
DEIR. Certificat«
                           SO, 1994
                            is
                                         coamentary.
               SSSi^'SiSft.'SLiaS'S.SS gMT"!*?
               the confluence alon
-------
  £Q£A #8695
          OEIR Cert if icate
                                                      .June 30,  1994
       page 4-9.  There appear* to b« an error because" silt or
       day fractions are measured at; less than  .06." mm and. so
       are sand particles.
       DATE

  Comments  received:
                                               Coxe/ Secretary
  5/17/94
  5/12/94
  5/16/94
  5/17/94
  5/18/94
  5/17/94
  5/19/94
  5/19/34
  5/23/94
  5/26/94
  5/19/94
  5/26/94
  6/1/94
  6/13/94
  6/13/94
  6/14/94
  6/14/94
  6/15/94
  6/15/94
  6715/94
  6/16/94
  6/17/94
   6/17/94
   6/17/94
   6/20/94
   6/20/94
   6/20/94
   6/20/94
   6/21/94
   6/21/94
   6/21/94
  %6/21/94
   6/21/94
   6/21/94
   6/21/94
   6/21/94
 International Longshoremen ' s Association
 North Shor« Recycled Fibers
. Rexham
 City of Everett, Office of the Mayor
 Cape Cod Commission
 Frank Kirarchi
 Containership Agency, Inc.
 X.T.o. Corporation of Hev England
 Boston Water and Sever Coamission
 Jeffrey Hopkins
 Dr. Paul r. Hurray
 •Decorative Specialties International Inc.
 -Marine Fisheries Coaaission
 C. H. Powell Coapany
 Boston Harbor Docking Pilots
• Boston Toving and Transportation Company
 Kaersx Inc
 Hedlloyd Lines
 >&o containers
 Bev Carney
 Patterson, Wylde 4 Co. ,  inc.
 Sea-Land                         •-'.-.
- Town  of svampsoott, conservation Coaiaission
' Nahant SWIH, Inc.
 Tovn  of Mahant, Board of Selectmen
.-LADS  System, Inc.
 Boston Redevelopment Authority
 Massachusetts Highway Department, CA/T
 <5reenWorld Inc.
 Massachusetts Bays "Program
 . S.T.O.F.
 Massachusetts Sierra Club
 Center for Marine Conservation
 Coastal Advocacy Network
 CLP
 Save the Barber/Save -the Bay
                             Dl
TT'd   Z'SZL ZL.7 £2= t S
                                       :Tt

-------
                #8695
          DEIR Certificate
June 30, 1994
c
           620/94
           6/11/94

           P : bcsdr edg. dei
           TC/SB/nb
•John T.. Clark and Son
 Cetacean Research
                                            22
                          T £
        01
                                            3«" i J-' CtSW i

-------
Sl-1

       The BHNIP DEIR/S team appreciates the EOEA commendation for the
Working Group process utilized for this project.
Sl-2
       The criteria used to identify practicable alternatives were reexamined for the
FEIR/S.

Sl-3

       The comparison of environmental impacts of the potential disposal sites was
separated, in the alternatives analysis (Section 4.0), from the practicability analysis to
emphasize more clearly the logic behind the site selection process.  Additional data on
environmental conditions at these sites was collected and incorporated into the
analysis.
Sl-4

       The preferred alternative is the same as the least impact alternative and is fully
described hi the FEIR/S.
Sl-5

       A detailed Dredge Management and Monitoring Plan, specific to the preferred
alternative, is presented in Section 5.0 of the FEIR/S.
Sl-6

       The comparison of environmental impacts associated with the use of each of
the potential disposal sites has been expanded in the FEIR/S and provides sufficient
grounds for making the determination of the least environmentally damaging alterna-
tive.
Sl-7

       The screening criteria used to develop the shortlist of sites in the DEIR/S were
reconsidered and found to be appropriate for this purpose.  The analysis of the
shortlisted sites was altered by separating consideration of environmental impacts and
practicability factors. The least environmentally damaging alternatives were identified
before practicability criteria were applied.
                                        1

-------
                Sl-8

                      The alternatives analysis, Section 4 of the FEIR/S, provides sufficient detail to
                follow the logic of and reach the same conclusion as the site selection process.
                Sl-9

                      The restructuring of the alternatives analysis provides more detail on the
                environmental impacts of each of the disposal alternatives.
               Sl-10

                      No alternatives for reuse of contaminated sediments have been found to be
               environmentally acceptable.
               Sl-11

                      A detailed Dredge Management and Monitoring Plan is presented in Section 5
               of the FEIR/S.
                Sl-12

                      The BHNIP consulted extensively with the federal and state resource and
                regulatory agencies during the development of the FEIR/S.  The team believes that this
                process was successful in clarifying questions that the agencies had regarding the
                project and enabled us to develop a document that provides sufficient information for
                the selection of the preferred alternative. We believe that it will not be necessary to
                conduct additional environmental regulatory review after the FEIR/S.
                Sl-13
                      Alternative project designs are discussed in the FEIR/S.
tff
                Sl-14

                      The FEIR/S has assumed that all silts to be dredged during the BHNIP are
                unsuitable for open ocean disposal.  The schedule for completion of the FEIR/S has
                resulted in an approximately one-year delay in projected startup.  As a result, we
                anticipate that natural sedimentation patterns will accumulate additional material
                (contaminated) in the channels.  This additional volume has been accounted for in the

-------
designed disposal site capacity.  It is not expected that this additional volume would
have a detectable effect on the environmental impacts of dredging or disposal.
Sl-15

       The volume of material that could be maintenance dredged from the berthing
areas over the 50 years following the BHNIP can be estimated by the historic mainte-
nance dredging frequency for Boston Harbor. The volume of maintenance dredging
estimated to be required from the berth areas during the next 50 years is approximately
1.2 m cy.
Sl-16

       The volume of sediments (combined parent and maintenance material) expected
to be dredged from the 18 berth areas was calculated based on existing hydrographic
surveys available during the DEIS development period.  These estimates assumed the
silt material would be entirely removed along with an overdredge of 0.5 feet into the
underlying parent material.  Therefore, the silt portion may have been a slight overesti-
mation at the time this data was calculated. However, due to continuing siltation in
the dredge areas until the time when actual dredging occurs, there will be some
additional material; the resultant quantities should be fairly close to the estimates
provided in the DEIR.

       An additional factor the DEIR does not account for is the reduced dredge
volumes of berth areas that may be dredged before the BHNIP. For example, the
recent Moran terminal dredging  (approximately  10,000 cubic yards) and possible
dredging at Eastern Minerals and Gulf Oil would reduce the total estimated silt volume
for the BHNIP slightly.

       The volume of parent material to be dredged from the berth areas will not
change over time and is felt to be an accurate estimate.

       The amount of silty material to be dredged from the project includes the berth
areas.  Berths to be dredged are  described in Section 2.2.3 and summarized hi Table 2-
7. The volumes shown in the DEIR/S for the Federal channel were based on 1983
surveys.  These volumes accounted for the changes in channel layout at the Inner
Confluence.  This includes the extra dredging at the south end of the Inner Confluence
and the deletion of dredging near the McArdle Bridge on the East Boston side;
shortening of the Mystic Channel by Boston Edison and easing the transition into the
narrower channel by Exxon, and reducing the size of the area being dredged hi front
of the Army Pier and increasing the size of the notch across the Reserved Channel
mouth.

-------
Sl-17

       The 0.5 foot over dredge should not be confused with the standard practice of
overdepth dredging.  The meaning of the 0.5 foot was to allow a volume of parent
material that may inadvertently be included in the bucket as the silt is being removed.
This parent material will be mixed in with the silt and deposited with the silt.  Silt
disposal alternatives must allow capacity for this extra material.  The traditional
allowable overdepth of two feet hi parent material and three feet in rock are included
in the proposed project quantities.
Sl-18

       Section 4.0 of the final EIR/S discusses the disposal option for maintenance
dredging only.
Sl-19

       All of the silty material has been considered unacceptable for unconfined open
water disposal. Disposal of the silty material would only occur if it can be isolated
from more pristine areas.
Sl-20

       The alternatives analysis in the FEIR/S has been restructured to evaluate the
shortlisted sites on the basis of environmental impacts to select the least environmen-
tally damaging alternatives.  After this process, practicability criteria were applied to
the sites.  All sites were evaluated not only for their suitability for disposal of BHNIP
sediments, but also for unidentified future projects. While capacity has an effect on
the suitability of sites for the BHNIP, it may be less of a factor for other projects.
Therefore, the use of this criterion was modified for the analysis hi the FEIR/S.

       The suitability of the shoreline sites, as well as all other shortlisted sites, was
reconsidered.  While each of the shoreline sites evaluated lies within or directly
adjacent to the State's Designated Port Areas, federal agencies do not agree that this
designation enables them to make an exemption to the "no net loss" agreement
established relative to the 404(b)(l) guidelines.  The alternatives analysis rated
permanent losses of aquatic habitat as more severe than temporary losses. Coupled
with other, indirect, impacts, the fill-to-fastland scenarios were found not to be among
titie least environmentally damaging alternatives.  In addition to the environmental
effects, the costs of this scenario would be higher than many other alternatives, and the
period of time required to realize productive real estate value of the newly created land
would be lengthy.

-------
 Sl-21

       Section 4.0 evaluates the potential disposal sites based on numerous environ-
 mental and practicability criteria. Cost was one criterion, but it was not used alone to
 determine the preferred alternative.
 Sl-22

       As indicated in previous responses, the disposal site alternatives analysis has
 been restructured in the FEIR/S (Section 4).
Sl-23

       In accordance with this comment, the disposal site alternatives analysis has
been restructured to provide a clear separation between environmental and practicabili-
ty criteria.
Sl-24

       The referenced issues are covered in Attachment 1 and Section 4 (Disposal Site
Alternatives Analysis) in the FEIR/S.
Sl-25

       The in-channel disposal alternative has been redesigned, based on information
on subbottom conditions, so that it can accommodate the entire volume of silt pro-
posed for dredging from the BHNIP.
Sl-26

       The in-channel disposal site will use a sand cap. This will eliminate concerns
expressed by agencies over the use of a clay cap on silty material.
Sl-27

       Disposal of future maintenance material with capping at MBDS will be
considered.  Discussion is underway to determine if clean silty material from another
project would be suitable for a demonstration project.  Appropriate agencies would be
contacted for comment prior to demonstration.
                                                                                        ft*

-------
Sl-28

      A demonstration project would not necessarily be tied to this project.  All
appropriate agencies would be contacted for comment on the proposed demonstration
project
Sl-29

       This alternative has been dropped as a preferred alternative based on review of
envkonmental and practicability criteria.
Sl-30

       Additional biological investigations were conducted at the Boston Lightship site
during the fall of 1994.  The project did not do additional work locating and quantify-
ing existing waste material at the site because the EPA is in the process of doing that.
This information was used to reanalyze  the suitability of this site for disposal of
dredged materials.
Sl-31

       Reevaluation of the potential aquatic disposal sites indicates that the in-channel
disposal option would be among the least environmentally damaging alternatives.  The
description of this alternative has been clarified in the FEIR/S.  MEPA's expressed
concern regarding stockpiling of sediments during this process appears to be a
misunderstanding.  Careful coordination of the construction will be required, but it is
readily possible to minimize the duration of stockpiling.  In particular, stockpiling
would not occur landside, but "would be restricted to barge storage. The FEIR/S
describes the impacts associated with this disposal option.

       The reader should refer to the Dredged Material Management Plan for a
detailed analysis of the operational procedures for in-channel disposal.  All dredging
and disposal activities will have some impact to the environment. However impacts to
the environment will be temporary and cease when construction is completed.
Disposal impacts for the in-channel alternative would be  minimized as the dredged
material would be returned to the environment it was taken from. No significant
biological resources are expected to be impacted with this alternative. An environmen-
tal window has been established to minimize impacts to anadromous  finfish in the
Mystic River. Mitigation may be required if water quality impacts are anticipated.
The Dredged Material Management Plan discusses potential  operational mitigation
techniques.

-------
 Sl-32

       Dredge production rates are expected to generate two barges per day per dredge
 transiting the harbor channels.  The rug captains will be in radio contact with the
 larger vessels  entering or leaving the harbor and little impact is expected from the
 movement of barges.
Sl-33

       Additional biological investigations were conducted at the in-channel locations
during the fall of 1994. This information was used in the reevaluation of disposal site
alternatives.
Sl-34

       The issues raised in this comment on the Spectacle Island CAD site have been
thoroughly addressed in the FEIR/S.
Sl-35

       Additional biological investigations were conducted at the Meisburger sites
during the fall of 1994. Results were used in the reevaluation of the disposal site
alternatives analysis. These sites were determined not to be among the least environ-
mentally damaging alternatives.  The project considers the avoidance of impact to
Massachusetts' fishing  industry to be a high priority.
Sl-36

       The issues raised in this comment have been addressed in the FEIR/S (Section
4 and Attachment 1).
Sl-37

       The disposal site alternatives analysis (Section 4) has been restructured to
separate the evaluation of environmental impacts from practicability issues.
Sl-38

       The chemical and physical characteristics of the dredged material samples have
been compared to the DEP requirements for soil reuse at lined landfills (Bureau of
Waste Prevention Interim Policy #BWP-94-037 - Reuse and Disposal of Contaminated

-------
Soils at Landfills') and for capping materials (310CMR 19.000 Solid Waste Manage-
ment Regulations and Landfill Technical Guidance Manual). While silt samples from
some of the dredge sites may meet the chemical criteria for reuse at landfills, other
samples exceed the allowable limits for PCBs, Arsenic, and/or TPH and dewatering
sediments to meet the standard of no free draining liquid is currently impracticable.
Landfills have been dropped from consideration for disposal or reuse of silt material in
the Alternatives analysis (Section 4.0).  Clay is better suited to beneficial uses as
landfill capping material, and this option is discussed in the FEIS.  Several planned
demonstration projects may provide a wider variety of disposal options for future
maintenance dredging.  These are discussed hi the FEIS,
Sl-39
       See response to comment SI-38.
Sl-40
       The reuse or disposal of dredged silt from the BHNIP at landfills for daily
cover, contouring material, or disposal has been eliminated from consideration due
primarily to the impracticability of dewatering the quantities of material expected to be
generated.  Dewatering issues along with current site permitting requirements have led
to the elimination of other upland sites, including Wrentham-495 from further consid-
eration as practicable alternatives for the BHNIP.
Sl-41

       The dewatering of the dredged materials would only be required if upland
disposal or if the treatment of the dredged materials is required prior to it's disposal.
The dewatering would be performed on land depending upon the volume of dredged
material produced daily and the availability of land and/or barges.  Section 4.0 and
Appendix I discuss proposed dewatering operations.
 Sl-42
       See response to comment Sl-40.
 Sl-43
       The alternative of filling shoreline sites to fastland has been reconsidered in the
 FEIR/S (Section 4).  Under the Clean Water Act 404 (b)(l) guidelines, impacts must
 be avoided first, then minimized.  As there are other available alternatives, creating

-------
fast land has been determined not to be among the least environmentally damaging
alternatives.
Sl-44

       Thank you for your guidance on regulatory procedures for evaluating the
shoreline sites.
Sl-45

       Section 4.0 and Attachment 1 of the EIR/S addresses these impacts.  Dewater-
ing would occur in areas closest to the harbor.  Port areas would be considered first.
Sl-46

       The issues raised in this comment have been addressed in Section 4 and
Attachment 1 of the FEIR/S.  Biological resources of the shoreline sites were investi-
gated in fall 1994, in response to this and similar comments. An environmental
window has been  established to minimize  impacts to anadromous finfish in the Mystic
River.
Sl-47

       Thank you for suggesting additional potential disposal sites. Fort Point
Channel was evaluated and eliminated during the preparation of the DEIR/S, partially
because of its inaccessibility for barges.  Despite changes in the Central Artery project,
this area continues to be inaccessible.  In addition, there are concerns about the effect
this disposal would have on the structural integrity of the area.  The area on Conley
Terminal was found to be unsuitable for the proposed operation.
Sl-48

       In response to several of the comments on the DEIR, MASSPORT and the
Army Corps of Engineers developed a survey questionnaire to send to treatment
technology and disposal companies which could be contracted to handle, treat and or
dispose of the contaminated dredged materials (Appendix D). The survey utilized a
format originally developed by the USEPA and the Army Corps of Engineers as part
of the Assessment and Remediation of Contaminated Sediments (ARCS) Program
(Averitt 1990). The survey included questions on the effectiveness, implementability
and the cost of the technology for the treatment or disposal of contaminated dredged
materials.

-------
       Thirteen completed questionnaires were received in response to the 37 sent.
Results of this survey are detailed in Appendix D and summarized in Section 3.  In the
future Massport and the Corps will, where feasible, implement new technology that is
practicable for dredged material.  There is no new technology that can be applied to
the BHNIP that is practicable.
Sl-49

       Landfills, new land creation and innovative technologies were re-evaluated in
the FEIR/S (Sections 3.0 and 4.0).
Sl-50
       The least environmental damaging alternative is the preferred alternative.
Sl-51
       A Draft Section 61 Finding addressing the issues raised in this comment is
included with the FEIR/S.
Sl-52
       Refer to Section 5.0 of the final EIR/S for the Dredged Material Management
Plan.
Sl-53

       The Dredged Material Management Plan in Section 5.0 of the final EIR/S
describes the turbidity controls during dredging and disposal. The Cable Arm is a
brand name.  Corps contracting procedures make it difficult to specify  a brand name
product when other options are available. We can, however, specify certain perfor-
mance standards to be met by any equipment used in the dredging of silty material.
Sl-54

       No other significant resources in the harbor warrant timing considerations.  No
delays which would cause the dredging to occur during the environmental restriction is
anticipated.  If this were to occur, then coordination with the appropriate agencies
would occur.
                                       10

-------
       A scenario for dredge sequencing has been prepared to demonstrate the
 complexity of scheduling demands such as environmental restrictions will have on the
 proposed project. Both the Mystic River and the Inner Confluence are anticipated to
 be associated with dredging restrictions.  The likelihood of delays causing dredge
 operations to be pushed into the restricted period is open to chance. However, since
 dredging will be taking place for about 18  months it is more likely the dredge will be
 relocated to the Chelsea or Reserved Channel if more than about a week of extension
 was required.  A possible contingency for work required during the time restriction
 would be to confine work limits to only one  side of the Mystic River or Inner
 Confluence.
Sl-55

       There are several systems available that could be used to reduce fisheries
impacts.  This issue is discussed in the Dredging Management Plan (Section 5.0).
Sl-56

       Impacts from odor are discussed in Section 5.0 and Attachment 1 of the final
EIR/S. Dewatering is not required for the preferred plan.  Temporary barge storage
will be of a short duration (5 days) and will occur infrequently.
Sl-57

       Mechanical dewatering of the dredged sediments has been considered for at
least a portion of the material. Volume reduction and dewatering is effective when the
material can be disposed at upland facilities or has a commercial or beneficial upland
use. Upland disposal has not been identified as the preferred and least environmentally
damaging alternative. As a result, mechanical dewatering and subsequent upland
disposal has been considered as a contingency for sediments which could not be
placed at the in-water sites.
Sl-58

       The preferred alternative, in-channel, would have minimal damage to the
environment.
Sl-59
       The proposed dredging project is described in Section 2 of the FEIR/S.
                                       11

-------
Sl-60

       TCDD, the most toxic congener, was not detected in any of the Boston Harbor
sediment samples analyzed for this project. The congeners that were foundin detect-
able concentrations are not considered to occur at levels of concern to the marine
environment.
Sl-61

       Three berth areas were not included hi the sediment testing program along with
the 15 berths described hi the DEIR.  Those three locations are figured into the
benefit/cost analyses since it has been determined that those facilities could benefit
from the Federal channel deepening if it occurs. However, the three areas either don't
require dredging at this time or the facility operators did not wish to be part of the
BHNIP program.  Therefore it was not deemed necessary or feasible to characterize
those locations.
 Sl-62

       The superscripts 2 and 3 indicate that the concentration of the indicated
 parameter was hi category II or III under the Massachusetts classification of sediments
 for open-water disposal.
 Sl-63

       The prefix "J" means that the compound was present in trace amounts.  The
 concentration listed is an estimated value.
 Sl-64

        Cost for mobilization includes getting the necessary equipment and materials to
 the disposal site and finalizing site preparation plans.
                                        12
/3o

-------
             MASSACHUSETTS WATER RESOURCES AUTHORITY
                         Charlestown Navy Yard
                           100 First Avenue
                       Boston, Massachusetts 021 29
                                                    Tci.
                                        June 21, 1994

Colonel Brink P. Miller
Division Engineer
Department of the Army
New England Division, Corps of Engineers
424 Trapelo Road
Waltham, Massachusetts 02254-9149

     Re:  Boston Harbor Navigation Improvement Project
          Draft Environmental Impact Report/Statement
Dear Colonel Miller,
     The Massachusetts Water Resources Authority (MWRA) has
reviewed the above referenced draft document, and offers the
following comments.  Comments are presented by location, and
pertain to both the dredging and disposal aspects of the project.

Chelsea River

     Please note that the MWRA Waterworks Division maintains the
following pipelines in the Chelsea River, between the McArdle
Bridge and the Chelsea Street Bridge:
   Facility

Section 8, LSPL,
42" pipe in tunnel
Section  38, LSPL,
36" pipe in tunnel
Section  38,  LSPL,
36" pipe encased in
concrete
  Grade
Top
39'
of Tunnel
below MLW
Top of Tunnel
35' below MLW
Top of concrete
encasement, 43'
below MLW
  Location

About 800' east
of McArdle Bridge
                About 100'  west of
                Chelsea Street
                Bridge

                About 200 feet west
                of Chelsea Street
                Bridge
     Massport and/or the ACOE must submit  to the MWRA any
 dredging plans for  work which may impact these  structures.   Plans
 should be submitted to James Gillis,  MWRA  Waterworks Division.

     In addition, note that any work  within MWRA easements
 requires a Section  8M Permit.  Inquiries regarding permitting
 requirements may be mades to Owen McGarrahan, MWRA  Waterworks
                                   131

-------
                                                    June 21,  1994
                                                           Page 2
Division, at  (617) 242-6000, ext. 4626.

Chelsea Creek

     The MWRA maintains a number of sewer siphons in a relatively
small area of Chelsea Creek.  Two 60-rinch siphons connect the
I.N. Caruso Pump Station with the Chelsea Screen House and the
Chelsea Headworks.  The siphons are located 60 feet below the low
water mark  (MDC datum 38.47).  One siphon carries dry weather
flow from the Revere Extension and Chelsea Branch Sewer; the
other carries storm overflow from the Headworks to the Caruso
Station.

     The Caruso Station has no gates to shut down the siphons,
which enter directly into the station's wet well.  Therefore, if
for any reason a siphon breaks, there is no way to stop sea water
from entering the station.

Meisburger 2  & Meisburger 7

     As the DEIR/S states, Meisburger 2 is located at
42° 23.7' N, 70° 50.2' W., and Meisburger 7 is located at
42° 20.7' N, 70° 47.7' W.  The coordinates for the diffuser area
for the MWRA's Deer Island Outfall are as follows:

          R2  Diffuser:   42° 23.3' N, 70° 46.8' W

          R55 diffuser:  42° 23.1' N, 70° 48.2' W

     The Meisburger 2 site  is therefore located  approximately 1.2
miles west  of the diffuser  area, and the Meisburger  7 site  1.2
miles to the  south.

     Because  of this proximity to the  outfall  diffuser  area,  the
Authority  is  concerned that the  use of these sites will impact
the MWRA's  monitoring program near the outfall.   The sites  are
within the  nearfield depositional zone of the  outfall,  and  it
will be  very  difficult to distinguish  between  outfall impacts and
dredge disposal  impacts.  In addition, the Meisburger sites are
reasonably clean, and  it does not appear to be good  environmental
policy to  perturb them.   The Authority recommends using in-harbor
sites for  borrow pits  so that existing dirty sites could be
cleaned  up.
J

-------
                                                    June 21,  1994
                                                           Page 3
Little Mystic Channel and Reserved Channel
     In compliance with the court-ordered schedule for Boston
Harbor, the Authority is currently developing Combined Sewer
Overflow (CSO)  Control Alternatives as part of an overall
Wastewater System Master Plan.   Based on extensive data
collection and system characterization in conjunction with
development of a detailed system model, the Authority has
developed a number of alternatives for CSO Control.  A
recommended plan for CSO Control will be submitted to the court
in draft form in September 1994, and will be finalized by
December, 1994.

   ,  Two of the potential disposal areas identified in the draft
EIR/S  (Little Mystic Channel and the Reserved Channel)  are the
sites of active CSOs.  Accordingly, any work proposed within the
Little Mystic Channel or the Reserved Channel should be closely
coordinated with the Authority's CSO Control.planning for those
areas.  However, since a number of the CSO Control alternatives
are being addressed on a very site specific basis, coordination
with the MWRA should be maintained regarding any in-channel
disposal locations.

Revere Sugar and Amstar

     The Amstar site is adjacent to the Revere Sugar site, which
is currently leased by the MWRA for the transportation of workers
to Deer Island for the Boston Harbor Project.   The Authority is
aware of the potential conflict between this use and its possible
use as a disposal site, and is in negotiations with Massport to
reevaluate the lease termination date.

Everett site

     Note that the Everett Site is immediately adjacent to the
MWRA's New Charlestown Pump Station, which is a contaminated site
being investigated under Chapter 2IE.  In order to ensure that
possible disposal activities do not result in a release from the
site or in any way impede future remediation,  any use of this
location must be closely coordinated with MWRA and DEP.

Subag E

     Although the Subaq E site lies near the path of ferries
carrying MWRA construction personnel to Deer Island, it appears
                                133

-------
                                                    June 21,  1994
                                                           Page 4
to be located outside of the channel, and so will not impact
ferry traffic.
     Thank you for the opportunity to comment on the DEIR/S.  If
I can be of any assistance in clarifying these comments, please
call me at  (617) 242-0230, ext. 4335.

                                        Very Truly Yours
                                        Mark Radville
                                        Project Manager,
                                        Environmental Management
cc:  M. Debbie
     L. Lataille
     N. Kurtz
     R. Trubiano
     M. Connor
     J. Gillis
     M. White
     M. Connolly
     T. Coxe, MEPA
     J. Hansen,  Massport
     S. Lipman,  DEP/DWPC

-------
S2-1

       The Corps will continue to work closely with MWRA on plans to dredge the
channel on Chelsea River.  Close coordination should be maintained with the City of
Boston, Public Works Department, regarding their replacement of the Chelsea Street
Bridge - which may impact the utilities in that area.
S2-2

       During preparation of plans and specifications for the project, MWRA will be
informed of progress. Permit inquires will be made with the MWRA to keep all
parties aware of proposed plans.  However, it is understood that if utilities are to be
relocated then a Section 8M permit is moot.
S2-3

       The two 60-inch sewer siphons appear to be outside of the proposed dredging.
Coordination with MWRA should alert specification writers to any potential problems.
S2-4

       The potential use of the Meisburger sites for the disposal of dredged materials
has been reevaluated in the FEIR/S (Section 4). Compared to other sites being
considered for this project, these sites are not among the least environmentally
damaging alternatives  for the BNHIP. Their use may be reconsidered hi the future at
which point further coordination with MWRA would be appropriate.
S2-5

       In-channel disposal is not being proposed for either the Little Mystic Channel
or Reserved Channel. Continued coordination with MWRA regarding in-channel
disposal locations will consist of providing the FEIR/S for comment.
S2-6

       Because of its limited capacity, costs for partially filling 1he Amstar site are
higher than other, more preferred shoreline sites (e.g. Little Mystic Channel). It is
unlikely that the Amstar site will be used for disposal of sediments hi the near future.
                                        13
125

-------
S2-7

       The Everett site was not selected as a preferred alternative for disposal of silts
from the BHNIP.
S2-8

       The Subaqueous E site is currently used as a local channel.  Use of the site
would cause the MWRA ferry to deviate to the south from its existing route; bypassing
the lower middle shoal and then turning into the western edge of the President Roads
Anchorage.
                                        14

-------
 William F. Weld
    Govimof
  Trudy Coxa
  S*cratwy. EOEA
Thomas B. Power*
           Commonwealth of Massachusetts
           Executive Office of Environmental Affairs
           Department of
           Environmental  Protection
                                   June 21,  1994
                                        Massport/ACOE
                                        Draft EIR/S, EOEA No. 8695
                                        Boston Harbor Navigation
                                        Improvement and Berth
                                        Dredging Project
Trudy Coxe, Secretary              Re:
Massachusetts Executive Office of
 Environmental Affairs
100 Cambridge Street
Boston, MA   02202

  and

Brink P. Miller
Colonel, Corps of Engineers
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, MA   02254


                        ?
Dear Ms. Coxe and Mr. MiZler:


     The Massachusetts Department of Environmental Protection (DEP)
has reviewed the  Draft  Environmental  Impact Report/Statement for
the Boston Harbor, Massachusetts,  Navigation Improvement Project
and  Berth Dredging  Project  (EOEA File  Number  8695)   and  this
correspondence  includes DEP's consolidated  comments on the  two
volume April 1994 document.  This correspondence consists of four
sections:  the  first section (1)  includes  regulatory and policy
comments;  section  (2)  includes  a  listing  of major   comments;
section  (3)   includes  supplemental  page-by-page  comments;  and
section (4) includes miscellaneous comments.


     Initially,  DEP would like to indicate that it fully supports
the project  goal  of deepening  and then maintaining the various
channels throughout Boston Harbor and  also increasing the depth of
various berth in the harbor.   The ability of  the Port of  Boston to
handle the larger  cargo  and fuel vessels is critical to the overall
economic well being of the entire Metropolitan Boston area and the
standard  of  living  of  its residents.   In  this regard DEP,  in
cooperation  with  its  sister  agencies  within  the Massachusetts
Executive Office of Environmental Affairs (EOEA), has embarked on
On* Winter Street •  Boston, Ma*sachu»etts 02108
                                    FAX (617) 556-1049  • T«tephon« (617) 282-5500
                                    /37

-------
a regulatory development process to prepare and issue comprehensive
dredging regulations, with specific emphasis on reuse and disposal
of contaminated dredged materials.  Unfortunately, this process has
only recently been actively  initiated  and DEP  does not expect to
have final regulations in-place before early/mid 1995.   It is DEP_s
understanding that Massport's proposed schedule  for the EIR/S is
for the Final EIR/S to be filed with MEPA by the end of 1994, but
that actual initiation of dredging activities may not begin until
1996.  Assuming this  schedule is correct, DEP will not have its new
regulations promulgated before submission of the Final EIR/S, but
they  should  be  in-place during  project  permitting and  will
certainly be in-place prior to actual dredging operations.  In this
regard,  DEP will not  be  able  to definitely indicate  during the
project EIR/S phase all of the regulatory requirements  for dredged
materials  reuse/disposal  but we will  provide  Massport,  ACOE and
MEPA with as much guidance as possible regarding the likely path(s)
that  the  regulations will  travel.    DEP  will  provide periodic
updates  to the parties and will  be requesting that Massport arid
ACOE  actively  participate in the regulatory development process.
As indicated earlier, section (1)  of this correspondence will deal
with regulatory/policy issues and in this section  we will attempt
to  provide information  regarding  both the  existing regulatory
framework  and possible future procedures.

Section  1.  Regulatory and Policy  Issues

      During the past six  months a number of  regulatory and policy
actions  have   been   taken  by  DEP which   directly   affect the
reuse/disposal  of  dredged  sediments.  On October 1,  J-99?, me
Revised Massachusetts Contingency Plan (MCP)  at 310 CMR 40.000 took
effect which resulted in   major changes to how sites  contaminated
with Oil and Hazardous Materials  (OHM)  are assessed and cleaned-up.
One major  element was the development of Reportable Concentrations
 (RC)  and Cleanup Standards.  These regulations are implemented oy
DEP's Bureau of  Waste Site  Cleanup (BWSC)  and under  the  current
regulations BWSC would be the lead DEP agency for regulating all
activities related to contaminated sediments if  deemed to  be pare
of a 21E spill/release or at an  existing 21E  site.   In addition,
under the existing  regulations  the  placement   of  contaminated
dredged materials on an upland area might result  in the upland area
being deemed  a potential 21E  site if relevant RC's or  Cleanup
Standards are exceeded.   This regulatory situation is expected to
be rectified in  1994 when DEP issues  additional revisions to 310
CMR 40.0000, since it is DEP's intention to include an  exemption to
tiie 21E regulations for  dredged spoils reuse/disposal  which are
 adequately regulated by another section of DEP.  The Comprehensive
 Dredging  Regulations currently  being developed  would be_ that
 alternative regulatory procedure.  This would not  affect BWSC s
 regulatory control over dredged spoils taken from or placed onto an
 existing 2IE designated site.  Under this situation there would be
 joint reviews  and  coordination  by both BWSC  and DEP's Bureau of
 Resource .Protection  (BRP) , which will  implement the Comprehensive

-------
Dredging Regulations.  Appended as Attachment No. 1 is an excerpt
from 310 CMR 40.0000 which describes soil categories, and Cleanup
Standards.     "                                        '  •

     In addition,  on April 21, 1994, DEP issued Interim Remediation
Waste Management Policy for Petroleum Contaminated Soils. fWSC-94-
400  (Attachment No. 2)  which delineates  the management practices
for reuse,  recycling, disposal, storage, and transport of petroleum
contaminated soils.  At the  same  time, DEP issued Interim Policy
#BWP-94-037  (attachment No.  3)  titled  Reuse  and  Disposal  of
Contaminated Soils at Landfills.   This Policy is enforced by DEP's
Division of  Solid Waste Management (DSWM) which would regulate
dredged  sediments   proposed  to   be  reused  or   disposed  at
Massachusetts permitted solid waste landfills.  Policy fBWP-94-037
provides guidance on DEP's requirements,  standards  and approvals
for testing,  transport and reuse or disposal of contaminated soils
or dredged sediments at permitted landfills.
DSWM:
     The following activities will reguire prior approval from the


          Reuse  at lined  landfills  of contaminated  soils  and
          sediments that exceed the Table 1  (next page) contaminant
          levels   or   do   not   meet   the  Landfill   Operation
          Retirements, delineated in Section 6.0 of the Policy.

          Reuse  of contaminated soils  and sediments  at  unlined
          landfills.

     •    Disposal of  contaminated soils and sediments at lined or
          unlined landfills.

     The transportation of contaminated sediments not handled under
2IE through the use of a Bill of Lading must be transported via a
Material Shipping Record (MSR) signed by a Qualified Environmental
Professional,  if  the  materials  are  going to  a  DEP-regulated
landfill for reuse or  disposal.

     For use/disposal at landfills, sediments cannot have any "free
draining liquid"  as determined  by EPA  Method  9095  (a.k.a.  Paint
Filler Test) .

     The  policy  also  sets up  a  hierarchy  of  reuse/disposal
alternatives, and in this regard contaminated sediments cannot be
disposed of in a DSWM regulated landfill if a "feasible alternative
exists   that  involves  reuse,   recycle,   destruction,   and/or
detoxification of such soils".  It  is  incumbent upon the project
applicant to submit acceptable documentation to DEP.

     A Landfill  - Minor Modification.  BWP SW  22  permit or other
approval by DSWM must be obtained prior to landfill reuse of any
contaminated soils or  sediments which:

-------
                           BUREAU OF WASTE PREVENTION
                                   POLICY * BWP-94-037

                                          TABLE 1
ALLOWABLE CONTAMINANT LEVELS FOR SOIL REUSE AT LINED LANDFILLS'
^4^^i:^QSXJ^XKXK^ ^ z$k ^
Total Arsenic
Total Cadmium
Total Chromium .
Total Lead
Total Mercury
Total Petroleum Hydrocarbons (TPH)
Total PCBs*
Total PAHs'
Total VOCsr
Conductivity1 Oanhos/cm)
Listed or Characteristic Hazardous Waste
(TCLF")
•? %«. J*, f •. Sff "" % V «A A, fS- ; •, v ,
3$fc^t^**^j*^#
40
80
1,000
2,000
10
5,000
< 2
100
10
4,000
none
 NOTES:
 a Table 1 is reproduced in policy ifWSC-94-400.

 b Cootamfaaal concentrations are in mg/k«, dry weight. Other contaminants are as noted.

 e Lfeed tadfilb hare a DEP approTed, functioaine Hner with leachate aOtx&at aad are operated in
   Masacbnsetts DEP regulations and poBdes.  The criteria apply to reme of soils at fined landfiUs at da«j
   iBtemediate corer, and pre-cap contouring materiaL

         note that the methods specified in footnotes d, e,  aad f indicate the nairerse of chemfcak  to be a4deil
             the total csnceotratioas for these dasMS of innlimliiMlr  This PoBcy does not spedfy what
           to qoantify these ~-*«~*™.-**  For exaapfe, Method 8IM defines tibe 1st of chemicah to be
             total PAHs. Howerer, Methods 8270 or 8250 mxj be a»ed to qoanttfy PAH fcreli.
                                                                                               la
                                                                                               ii,
                                                                                               kiv
     d  Total concentrations of por/chiorinated ttphenyk fisted m EPA Method 8080.

                                         __.  «	j	»	•>_._^ • W>A md'»ithnrf S14tt
     £  TotftI copcrntrmitSpps of polymictey ATMBUKDC BvoFOCnViKHmt ntco ^B is* A IWCUHM* •*!«*•

     f  Total concentration of volatile organic compoonds ficted in EPA Method 8240 or eqinvafeat.
 g  Far soth or sediments which may be expected to be com^m ele^nted NaQ (e^. fedtoentt from marine ewiroa»
•   road-cab stockpile affected soils).

 a  TCLP «—*fa-cshould be performed formetab or orgaafc compoM.
    Gail Hanson, January 12,1993.

                                              Page 2 of 8
                                                                                            U-ZI,

-------
     1)   fail to meet criteria in Table 1; or

     2)   fail to meet the requirements in Section 6,0,  landfill
          Operation'Requirements, of Policy BWP-94-037; of

     3)   contain concentrations of oil or hazardous materials for
          which no threshold is specified in Table 1.

     Only  uncontaminated  soils  will  be allowed  for cover  and
grading purposes at unlined landfills, unless the landfill owner or
operator requests and DEP  approves  an application for Landfill -
Minor  Modification.  BWP SW22  or  other DEP  approval  is  granted.
Such an application would  need to be submitted to the applicable
DEP Regional Office with analytical soils  data and landfill site
data sufficient for DEP to make a determination.
     A  Special  Waste Determination  (BWP SW  14  or BWP SW  31)  or
other  approval  by  DSWM must  be obtained prior  to disposal  of
contaminated soils.

     DEP's  Division of Hazardous Materials  fDHM) would  regulate
under  C.21C and  310  CMR  30.000 any  sediments deemed  to be  a
hazardous waste f  unless the sediments  are elements of  the  work
being  performed  by BWSC  as  part   of  a  21E regulated , action.
Sediment  could  be  deemed  a hazardous  waste by  either being  a
Characteristic  Waste  (exceeds  Toxicity Characteristic  Leaching
Procedure (TCLP) criteria)  or being a Listed Hazardous Waste.
                                                         I
     The determination that sediments are a Hazardous Waste would
substantially complicate removal/disposal and would result in major
increases in project costs,  since there  are currently no hazardous
waste disposal facilities in Massachusetts.

     Disposal off-the-site of the dredging operations, but not at
a  2IE  site or  DSWM landfill  is  the  activity  for which there
currently is no  well defined DEP jurisdiction.  Historically, DSWM
has processed proposals for reuse of  mildly contaminated sediments
utilizing its Beneficial Use Determination procedures at 310 CMR
19.060, if the reuse plan conforms to the requirements included in
these regulations.   In addition, by  default,  it was assumed that
any other proposal would require siting and  plan approval under
DSWM at 310 CMR 16.000 and 19.000. DEP does not believe that this
current practice  is the appropriate  regulatory  solution and as a
result  the  Comprehensive Dredging Regulations  will specifically
delineate the siting and permit  procedures for such disposal.

                     Section 2, Ma*1or Comments

(1)  The document discussed the possibility of disposal of dredged
     materials at solid waste landfills. Please be  aware that DEP
     Interim  Policy  *  BWP-94-037  states  that  before  DEP  will
                           141

-------
(3)
(4)
consider allowing disposal of soil/sediments,, the options of
reuse,  recycle,  destruction,  and/or detoxication must  have
been considere4 and determined to be infeasible.  In the past,
large quantities of contaminated dredged spoils have not  been
disposed of at landfills, with  the majority being utilized as
grading material or intermediate cover.  This is not only due
to DEP's requirements that reuse options are preferable, but
due  to  the  limited  amount  of landfill  capacity  in  the
Commonwealth and the need to maintain this available capacity
for disposal  of  municipal  solid waste  and  resource recovery
ash.  DEP's most recent  solid  waste master  plan and related
planning  documents  indicate  that during  the  project's
anticipated dredging  period,  there would  not  be  available
capacity for  even  a substantial portions of the 1.3± MCY of
sediments without, significant negative impacts on capacity for
landfill disposal of Municipal Solid Waste.


Page  2-5,  Section  2.1.4:   DEP concurs with the statement,
"Each tributary channel can therefore be treated as a separate
project or  any combination with  other project tributaries."
In this regard,  DEP believes it is appropriate for the Final
EIR/S to consider  in greater  detail  the options  of spoils
disposal   from  a  particular  area   into   the   adjacent
bulkhead/nearshore alternative.  An example is to dispose of
all of the spoils from the Inner Confluence/Mystic River area
(approximately 500,000 c.y.)  into  the  Little Mystic Channel
Site.  If this site is filled to form "fast" land, ^ it may be
capable of handling the entire 500,000 c.y. of spoils.

Page 2.9. Section  2.2.2.1:  The DEIR/S refers to data from a
1983 Sasaki Associates report which indicates that in several
areas to be dredged there are  considerable quantities of gas,
predominately CO2,  CH4   and   H2S.    This  could result in
considerable  odor  problems during excavation, dewatering  (if
necessary) , and  transportation/disposal to upland sites.  If
dewatering or upland  disposal are to be recommended,  the Final
EIR/S will  need  to address potential odor problems.

Page 3-12.  Section 3.4.1;  The report assumed as part of the
disposal assessment that dewatering and compaction would only
reduce  the  1.3 MCY of as-excavated  spoils to its 1.1 MCY in-
situ volume.  The assumptions of dewatering efficiency are not
indicated   in the report  but DEP questions  the  1.1  MCY
estimate.   DEP  would anticipate that mechanical dewatering
(see  DEIR/S,  page  3-17,  Section  3.5.1)  could  result in
significantly better  solids production, thereby reducing the
volume  of sediments requiring final  disposal to well below 1 . 1
MCY.   This issue has major implications for the efficacy of
certain  reuse/disposal   options,   particularly   nearshore
bulkheading or upland landfilling.   The Final EIR/S must  fully
address "this  issue.

-------
     A i-elated issue which also needs to be more fully addressed in
     the FEIR/S  is an  assessment of  dredged spoils  dewatering
     technologies.  _. This  assessment should  not  only review  the
     basic technologies but analyze  the  siting and operation of
     such facilities.   Issues of concern include: how to  get  the
     dredged  spoils  to the  dewatering  facilities  (on  land  or
     possibly  a  barge) ;  how  to  deal  with  sidestreams  (i.e.
     pressate/centrate) ;  and  nature and extent  of  conditioning
     chemicals required to obtain proper  solids capture.

     It would be useful for -the FEIR/S to refer to and discuss  the
     results  of   full  scale   projects  at  which  a  dewatering
     technology was utilized.

(5)   Page 3-24. 1st column: Massport should indicate its rationale
     for choosing a site cutoff of 200,000 c.y. The determination
     of site capacity is based  on filling to MLW without taking
     into account the  potential for additional capacity if a site
     is filled to MHW or to form "fast" land.  This  entire issue
     should be discussed in greater detail  in the Final EIR/S.

(6)   Page 3-24 and  3-25:  DEP is concerned about the determination
     that options  with a benefit to cost ratio less than  1:1  are
     not  feasible  and  should  not  be assessed  further.    DEP
     understands  that  ACOE may be required to meet  such  specific
     ratios, whether or not they are realistic or feasible, but we
     question whether  the options analysis should be based on such
     an arbitrary criteria.  If  it is determined that an option
     with a 1 to 1.3 ratio has significant environmental and public
     health  benefits  over a 1  to 1  option, there  should be  a
     process to allow for such an option to continue to be assessed
     while financial  alternatives are  considered  (i.e. option of
     obtaining an  exemption to  the  ratio  or have  non-federal
     participating  agency, such  as Massport,  pay an  additional
     share of the  project  costs  to bring the  federally  eligible
     costs ratio up to 1:1).

(7)   Page 3-25. 1st column. 1st full paragraph:  DEP questions  the
     screening process  criteria whereby  options  with costs in
     excess of four times that of ocean disposal  at the  MBDS  are
     deemed "prohibitive", particularly since the MBDS option used
     as the base case  appears  to be for unconfined ocean disposal
     (see Figure ES-3),  a  situation everyone agrees is not legal.
     At a minimum,  confined ocean disposal should  be used as  the
     base case.

     Using the unconfined  disposal costs  results  in all  of  the
     shoreline sites being deemed "limited by cost", and placed on
     the lower level  "potentially practicable alternative" list.
     DEP believes  that  at a minimum,  costs  alone should not be
     utilized to place these  sites on a lower tier list.
                                  /
S3-1

-------
(8)   Page 3—28,  Proposed Use/Impacts:   The  report states that
     capping has occurred at a depth of 50 meters  at a .Portland,
     Maine site".  The technical feasibility of  such actions is a
     critical issue* and  the  Final EIR/S should include^ detailed
     documentation relative to the  Portland,  Maine Project.  If
     this information  is  not provided  to  DEP during  the EIR
     process, DEP will  not be able to assess and indicate to MEPA
     the technical feasibility of such options. DEP will require
     the  submission of  this  information  during  its permitting
     phase,  but it  would be  beneficial to all  concerned if this
     data is submitted now and not wait until the permitting phase.

(9)   Page 4-6. Section  4.3.2t

     a)    The Final  EIR/S should provide  more  documentation to
          support the statement,  "Disposal of parent material at
          these sites [subaqueous depressions and borrow pits] does
          not require containment."

     b)    The report states that material dredged from the borrow
          pits may have commercial value or would be disposed at an
          ocean disposal site.   This  assumes  all excavate is
          uncontaminated.   Applicant  would  need  to assess  the
          surficial  sediments to  verify  this   assumption.   If
          material  is  not  acceptable  for ocean   disposal,  the
          disposal of this sediment could result in a significant
          cost  increase  for  the  option  and timing impacts.  Is
          there any  information currently available relative to t3tie
          contaminant concentrations in these  surficial sediments?
          If  yes, this  information  should be  included  in Final
          EIR/S.  If not, at  some point  in time (prior  to^permit
          issuance), this information will need to be obtained.

(10)  Page 4-8. Section 4.3.5;  The report states  that at open water
     sites,  a three foot clay cap can be placed over the mound of
     silty material.  DEP  questions the technical feasibility of
     such a  procedure.  How will a "highly cohesive" clay  be placed
     on top of a more fluid silt material without the denser clay
     sinking through the silt? Additional  documentation  should be
     included in the Final EIR/S showing how unconf ined silt mounds
     can be capped with  clay dropped from a barge.

(11)  It is DEP's understanding that the CA/T Project will  be filing
     a  Project  Change  with MEPA  relative to the activities  MHD
     expects  to perform  within the  Fort Point  Channel as  part of
     the installation of its tunnel box.  DEP anticipates  that this

     Project Change will include additional temporary and possibly
     permanent  filling  within  the channel,  which may  make  the
     option  of  spoils  disposal  into  Fort  Point  Channel more
     attractive and cost effective.   DEP  believes that once MHD
     files  ±ts  Project Change  Massport should  reassess - the

-------
                                8

     feasibility of spoils disposal in  Fort  Point Channel,  based
     upon  that  new  plan,  and  report   the   results .  of   that
     reassessment in the FEIR/S.

(12)  a)    Relative to the use of the two Meisburger Sites, DEP is
          concerned  about the   adverse impact  to  the   current
          baseline development and  future  operational monitoring
          for the MWRA ocean outfall,  the sites being a couple of
          miles off either side  of the outfall diffuser.   MWRA, in
          coordination  with  an  Interagency   Effluent   Outfall
          Monitoring Task Force,  developed a multi-year monitoring
          plan, the collection  of  data  starting in 1992.    It
          appears that a number  of the existing nearfield  benthic,
          clostridium  sewage  traces,   and  nutrient/hydrography
          stations  are  located  in,  or  directly adjacent to  the
          Meisburger sites (Attachment No. 4), and use of either of
          the sites could result in impacts to the monitoring plan,
          the extent of that impact not being possible to determine
          at this time.  It is DEP's understanding that MWRA will
          be providing MEPA with comments which will address this
          issue in greater detail.  If  either  of these sites are
          carried forward into the FEIR/S stage, Massport should be
          required to assess the likely and  potential impacts to
          MWRA's monitoring program and develop mitigation measures
          if appropriate.

     b)    Another issue  of concern  to DEP, which also relates to
          MWRA activities, is how the use of various sites, such as
          Little Mystic River, might impact MWRA's Combined Sewer
          Overflows (CSO) Program activities; both its Short-term
          System  Optimization  Plan and  Long-term  CSO  Control
          Strategy.   Filling  of a number  of the potential  sites
          would result in impacts to existing CSO discharge pipes
          (i.e. may need  to  extent discharge line or  redirect
          flow) .  This is  not to say  that all interactions would
          necessarily result in  adverse impacts.   It is  possible
          that filling of  an area might fit  well into a  specific
          CSO recommendation for removal or redirection of the CSO
          discharge.  Again, it will be important for Massport to
          maintain  close coordination  with  MWRA  and report its-
          findings in the FEIR/S.

                   Section 3,  Specific Comments
(1)   Pace  2-8,   Section  2.2:
The  current   Water  Quality
     Classification for  those portions of  Boston Harbor in this
     project area is SB and not SC  (revised in 1990).

(2)   Page 2-10, right column:   The report  indicates that acetone
     was found in all samples at relatively high concentrations and
     that one possible reason was due to lab contamination.  The
     report does not  indicate whether  acetone was also found in
                                 1*15

-------
     trip or lab blanks, yet this type of information was utilized
     later  to  explain the  presence  of  the  pesticide  endrin
     aldehyde.  'Both the acetone and endrin aldehyde issues  need to
     be discussed in greater detail.

(3)   Tables 2-4 and 2-6:   Units need  to  be  added.

(4)   Table 2-8:  The table heading states that  it  includes  "Mass
     DEP  Classification  Levels", yet  the  information was not
     included.   Either the information should be included or the
     heading revised.

(5)   Table 2-10;  The table indicates  than mean values of PCB's for
     Berth Sediments  at  Distrigas,  North  Jetty,  Prolerized and
     Revere  Sugar  are  all  greater  than  2.0  mg/Kg.   This  is
     important  in that DEP's recently released Interim Policy fBWP-
     94-037 (attachment No. 3) includes a maximum concentration for
     PCB's of 2.0 for use as daily cover at lined landfill, unless
     the landfill obtains a "Minor Modification" from  DEP.   Based
     upon recent determinations by EPA (appended as  attachment
     No.5) regarding reuse/disposal of PCS  contaminated materials
     relative  to   TSCA requirements  [Section  6(e)(2)],   it  is
     questionable whether approval could be obtained  to reuse or
     dispose of spoils with PCB concentrations greater than 2.0
     mg/Kg.

(6)   Page 2-10, Section 2.2.2.2;

     a)   Discussion mentions  "Level III",  as "a  concentration
          similar to the MA DEP Category III (Table 2-5)".   MA DEP
          has  not  yet designated "Level  III Concentrations for
          PAHs".   In the future, DEP  is  likely to include  PAHs at
          this  level into its regulations, but to date this has not
          taken place.                                           ;

     b)   Discussions of pesticides says concentrations of x,y, and
          z were below detection limits.   It would be useful to
          relate this to toxicity (i.e.,  does this mean there is no
          risk of benthic toxicity at these detection levels?)

(7)   Page 3-6,  top  of page;  In the sediment/site matching section,
     the report states, "It was assumed that there were no sediment
     quality thresholds necessary for in-harbor containment...".
     Please  be aware that DEP intends  to  consider  inclusion ^ of
     maximum contaminant  limits into its  Comprehensive  Dredging
     Regulations if  it is determined necessary to keep risks  of
     containment failure acceptable.

(8)   Page 3-6.  paragraph 3;  The report assumes that contaminated
     sites  could  not  accept  other waste materials prior  to
     remediation.  It is possible that placement of the sediments
     on these sites could be an element of the remediation process, h

-------
                                10

     There seemed to be too little differentiation of contamination
     types in these sections  (i.e. physical vs. chemical and levels
     of chemical contamination).  Contaminated sediments going for
     ocean disposal are not necessarily "contaminated" when put on
     the land.                                                  .—

(9)  Page 3-7. Landfills;

     (a)  The option of use of the spoils as grading material was
          not included, nor  was intermediate cover.  Final cover
          would be the most valuable use if the clay sediments can
          be segregated from  other material.  It is stated that 114
          of the 122 landfills  open in 1993 will be closed by 1996.
          Based on information generated as a result of the Hynes
          Bill since 1993,  more landfills may remain open into the
          1996 to 1998 time-span.  Some of these landfills may be
          looking for material  to get  to grade prior to the time
          that they do close and this option should be considered
          in the FEIR/S.                                       —

     (b)  The first paragraph discusses the need for spoils to be"
          mixed with clean material to comply with DEP's regulatory
          thresholds for daily cover (as indicated in Table 3-3).
          The  information included in Table  3-3  is  actually
          outdated  and  should be replaced with  the  information
          included in Table 1 of DEP's  Interim Policy IBWP-94-037
          (attachment No. 3).   The  numbers in Table  3-3  are the
          criteria which were developed by DEP in  1992 specifically
          for excavate for  the  Central Artery/Tunnel Project.  You
          will notice  that Interim Policy fBWP-94-037 does not
          include any specific criteria for unlined landfills but
          the criteria for  use  at lined landfills is significantly
          higher for a number of contaminants.                 —

     (c)  DEP  believes  that  the  option  of  reuse  of  mildly
          contaminated spoils  as  daily  or  intermediate cover and
          grading material at landfills in Massachusetts should be
          continued forward into the FEIR/S.  The efficacy of such
          an  option will  depend in part on  the  assessment  of I
          dewatering technologies.                              -J

(10)  Page 3-7 and  3-8:   TCLP regulatory levels  is the incorrect!
     terminology to utilize.   The  levels  relate to  total  bulk!
     concentrationsf and not  TCLP results.

     In addition,  the  50 c.y./day figure  for Plainville/Laidlaw]
     should in fact be 5_p_p_ c.y./day (please see Table 3-7).

(11)  Page 3-g;  Discussion regarding the amount of material which!
     could be accepted by  a  landfill  is confusing.   This is the"
     amount which can be used at a landfill on any given day.  The|
     material atust  be  used within 90  days  of coming  to  a site;
                             m  '

-------
                               11

     therefore,  it  appears  that the  total volume which can be
     brought to a site for daily cover could be up to  90 times the
     stated amount.   This issue  needs  clarification.
(12)  Page 3-8, Landfills;   The  benefit of  using landfills for
     disposal  of  marine sediments  is  said to  be  "...weighted
     against  the  constraint  of  competing  uses  for  a  limited
   •  resource".  It is unclear what is meant by "limited resource".
     Are the landfills the  resource  or the marine  sediments?
(13)  Page 3.8. Section 3.3.2 and-Page 3-9. 2nd full paragraph;  DEP
     agrees with  the  statement  that disposal  of  sediment at
     shoreline sites would result in an environmental benefit by
     capping the existing contaminated sediments at those  sites.
     DEP  would  consider  this a  significant  secondary project  .
     benefit,  and  will take  this  into  account in  its overall
     project review.                                             J

(14)  Page 3-9.  Section 3.3.2;

     a)    It would be helpful  to present  areas  and  depths for the j
          Subaqueous B and E sites.

     b)    There needs to  be a better plan showing Winthrop  Site J
          location.

     c)    Discussions of  ADDAMS model results for Winthrop  Site
          should mention if it is  chronic or^acute  criterion that
          plume contaminants exceed by two times.

     d)    The report should explain what the federal  standard  is
          with respect to using ADDAMS model results,  i.e.,  what
          water quality values are considered acceptable  within
          what area and time.

     e)    It  would  also  be   helpful  to  the  reader  for  the
          information from the biological assessment (Appendix A-4,
          p.8)  concerning  the conservative assumptions made running
          the ADDAMS  model,  to be  included in  the  body  of the
          report to put the findings into perspective.

(15)  Page 3-10;

     a)    The report states that modeling results for the Spectacle
          Island CAD Site  indicate that water quality criteria will
          be reached in  approximately four hours.    The  report
          should indicate with isoplaths this area  within which
          water quality criteria would be exceeded.

     b)    The report states that the Meisburger sites both "support
          high  benthic productivity and  fisheries resources are
          relatively abundant." In the Final EIR/S  Massport should

-------
                                12
          attempt to quantify this situation and indicate whether
          either site has unusual or unique resources  that  would
          differentiate   it  from  other   "productive  .fishery
          resources-?1 within Massachusetts Bay.

     c)    Based upon recent comments from fishery agencies,  it  is
          unclear  whether  the  CA/T artificial  fish  reef will
          actually be placed in this vicinity.

     d)    Relative to In-channel and Borrow Pits,  where  will the
          sediments dredged to  create  these  disposal sites  be
          stored?   Will  it be possible  to keep clean and  dirty
          sediments segregated if the plan  is to alternately dig a
          cell and bury the contaminated sediments repeatedly?

(16)  Page 3-12, Section 3.4.1:  The report should not
     refer to TCLP results, but total bulk contaminants.

(17)  Page 3-12. Land-Based Options fA) :   Here, as in other places
     in the report, TCLP  is  used  incorrectly.  In addition, mixing
     is not likely to be needed  in most  cases.   Again, the  1,000
     cy/day does not include any stockpile ability at the landfill.
     On page  3-13, the figure  of 8,000 cy/day for each of two
     dredges over a 100 day period does  not appear to account for
     the time it will take to dewater the sediments.

(18)  Page 3-13;  The tipping fee of $28-$70/cy in Table 3-13 does
     not seem to differentiate between disposal and  use  as  daily
     cover,  grading  material,  intermediate  cover  or   capping
     material.   Also,  use  of the  dewatering costs based on the
     Moran Terminal project alone may not be typical.

(19)  Page 3-21, 2nd column:  The  figure of  50 c.y. for shortlisted
     sites is incorrect and should be  500.

(20)  Page 3-23:  The estimated 108 landfill closings prior to 1995
     is extremely  high.   For example,  in  the past 3^  years less
     than 10 landfills per year have closed on average.
(21)  Page 3—28  Section 3.6.2,  Description of  Possible  Disposal
     Sites — Boston Light Ship:

     a)  .  Does more  recent benthic assessment  information exist II
          than the 1977-79 data included in the report?          J1

     b)    Was the  ADDAMS model run  using parameters  for bottom jj
          water (below the thermocline)?

(22)  Page 3-29:    Early assessment  by the  Board  of  Underwater"
     Archeological Resources of  the  sensitivity  of  the Boston
     Lightship Site is critical to determining the potential use of

-------
                                      13

            this site.   Massport  should  attempt to  obtain  an  initial
            determination for inclusion  into the  FEIR/S.

       (23)  Page 3-33,  Section 3.6.2.3,  Meisburaer-2;

            a)    Does ACOE  experience include placing  a cap  on silty
                 contaminated sediment in 98  (ave)  to 105 (max)  feet of
                 water as exists at Meisburger-2? If  yes, documentation
                 should be included in Final EIR/S.

            b)    How could Meisburger-2  sand/gravel be used beneficially
                 as beach nourishment if it has a one  foot cover of silt
                 on  it?    Is  silt contaminated and  how  would  it  be
                 separated?
       (24)  Page 3-37,  Section 3 . 6.2.4 ,  Meisburcrer-7:

            a)
          A description of the use of "rigorous turbidity controls"
          indicated in the report during disposal  of  contaminated
          sediment at this site should be  included in document.

     b)    Does this site also presently have a one foot layer of
          silt as does Meisburger-2?
iff
       (25)  Page 3-55,  Section 3.10. Mitigation;

            a)    DEP has  information about a  very clean  environmental
                 dredge bucket  used in,  Great  Lakes  Cleanup by  Canada
                 (Cable Arm 100E) .   Use of this unit should be discussed
                 in FEIR.
            b)    Will dredging not be halted for winter flounder spawning? Jj

                          Revise landfill  category criteria  per'  prior Tl
(26.)  Table  3-3;
     comments.
       (27)  Pacre 4-2;

            a)    Report states  that a  15  cy bucket was  assumed to  be
                 utilized.   This sounds reasonable for removal of parent
                 material,   but  DEP  questions  whether  such  a ^large
                 "environmental bucket" for removal of the contaminated
                 silts is available.

            b)    For rock blasting mitigation may be required,  as was used
                 by MHD during blasting for the Third Harbor Tunnel.

       (28)  Page  4-4,  2nd  column,  top  paragraph;    DEP   questions the
            approveability of "holding the environmental bucket above the
            water surface to decant water off the top of the load."  This
                                        . ISO

-------
                                14
                                                                  J
     issue should' be discussed further in the Final EIR/S.

(29) Page 4-10:-  DEP  does  not consider  a  COD  of 80,509  ppm  a
     "moderate value".

(30) Page 4-14;  Is  the assumption that dredging work will proceed
     24 hours a day reasonable?

(31) Page 5-1, Regulatory Compliance:

     (a)  The  initial  item  is incorrect.   The main solid waste
          statutes  and regulations  are c.lll  §150A and 310  CMR
          16.000 and 19.000,and not  21H.

     (b)  Relative  to  the  Waterways  Regulation Program,  c.91,
          c.21A, s.14 and 310 CMR 9.00, certain activities within
          the port of Boston undertaken by the Massachusetts  Port
          Authority do not  require  individual written  approvals
          from the Waterways Program.  The transport or disposal of
          dredged materials  outside the  port  would require  the
          review and approval  of the program.  In addition, should
          a disposal option be ultimately selected that would  fill
          presently  flowed  tidelands  and confine the  material
          behind bulkheads,  the  future use of  the site must be
          dedicated  to  a  water-dependent-industrial   use   for
          Massport to qualify for the  exemption from licensing as
          provided by 310 CMR 9.03(3).

(32) Page 5-2;

     a)    Relative  to  the Mass.  Wetlands Protection  Act,   this
          statute  is  regulated  jointly  by  local  conservation
          commissions and DEP's Division of Wetlands and Waterways
          Regulation.

     b)    Relative to  Safe  Drinking Water Act,  the concern  for
          adverse impacts to water supplies includes more than  just
          Sole Source Aquifers.   The other major regulatory issue
          is that landfills are not allowed to be placed in Zone  1
          or II's of public water supplies, jurisdiction being  with
          DEP.

(33) Page Al-30:   Plainville Sanitary Landfill,  etc.  - The  TPH
     levels and the  liquid levels need to be updated as per Policy
     IBWP-94-037  for all  landfills  considered.   The  chloride
     considerations are  addressed in  the policy by testing  for 1
     conductivity on the  extract of  the dredged sediments.        J
Section f4> Miscellaneous Comments
(1)  Relative to  the ability  of the ADDAMS  Model  to correctly
                                                                  1
                          /'SI

-------
                               15
     predict water quality impacts, if  this model was  used to
     predict impacts  from  the  Black  Rock  Harbor,  Connecticut
     sediment disposal at the Central Long Island Sound  Disposal
     Site,  this information should be included as an appendix to
     the Final  EIR/S.   DEP is  particularly  interested  in this
     project,  due to the fact that actual measured results during
     this dumping operation concluded that 20 to 30%  of  the solids
     and 40 to 70% of the contaminants were dispersed to the water
     column.

(2)   In general it was unclear to DEP why only 3 lined landfills
     and one unlined  landfill were chosen out of the hundreds of
     active and inactive landfills in the Commonwealth.   When the
     report narrows the selection  down to  these 4 landfills and
     then states that there  isn't adequate capacity,  the reasoning
     is  confusing.    The   report  also  states  that   long  term
     maintenance of clay  caps is  a reason to  reject  using the
     dredged clay as capping material, yet this would not likely be
     a responsibility of the Project, as the responsibility goes to
     the landfill owner.

(3)   Relative to the option  oftconstruction and operation  of a new
     lined  sediment monofill at the Wrentham-495 Site, substantial
     additional  site specific information would need to be  obtained
     and provided to DEP before the agency could determine whether
     such a facility at  this specific site would  be  acceptable to
     .the agency.  This additional information would include at  a
     minimum:  (1) a thorough hydrogeologic assessment of the site;
     (2)  an analysis of  whether the facility  could be constructed
     and operated without filling or adversely impacting wetland
     resources  on or adjacent to the  site;  (3) an assessment of
     potential impacts to residential areas near the site  or along
     the truck route(s);  (4) analysis of public and  private water
     supplies  in the impact area, etc.

     If Massport decides to proceed forward with on-site  assessment
     of the Wrentham Site,  a draft scope  of services should be
     prepared  by Massport's  consultant and  submitted to DEP for
     review and  comment prior to any on-site activities being
     initiated.
                                                                 ««
(4)   Modeling  experts  from DEP's  Division  of  Water Pollution
     Control and Office of Watershed Management have been requested
     to review the ADDAMS Model developed  and utilized  by ACOE to
     assess water quality   impacts  due  to  in-water disposal of
     contaminated sediments.  Unfortunately, this review has not
     yet been  completed  by  DEP to  allow  for comments  to be
     incorporated into DEIR/S review.   As soon as this review is
     completed,  and if any  questions or concerns are raised, DEP
     will provide this  information to  Massport and ACOE so  that
     they can be addressed  in the Final EIR/S.  Copies of any such
     comments  will also • be provided to MEPA and other  relevant

                                /SI

-------
                               16

     agencies.

Conclusion
     Staff from DEP- will be available to work with Massport, ACOE
     and their various consultants to not only review and discuss
     DEP procedural and technical comments, but would be willing to
     participate  on  a  working  group   to   discuss   how DEP's
     regulations, policies and procedures interface with those of
     other applicable federal, state and local agencies.

     Feel free to contact me  if you have any questions regarding
this correspondence.
                                        Very truly yours,
                                        Steven G.  Lipman,  P.E.
                                        Boston Harbor Coordinator
SGL/wp:  miller.2
cc:  Norm Farrameli, Massport
     Joel Hartley, DEP/DSWM
     Carl Dierker, John Simpson,  Mitch Ziencina
     Bob Golledge, DEP/DWWR -
     Judy Perry,  Marcia Sherman,  Dave Ferris,  DWP/DWPC
     Beth Nicklas, Pam Harvey,  DEP/OGC
     Nancy Baker, EOEA/MEPA
     Scott Cassel, EOEA
     Leigh Bridges and Brad Chase,  DMF
     Margaret Brady and Deerin Babb-Brott (CZM)
     Peter Smith, Leslie Lewis, Eugene Cavanaugh, and
      Richard Thibedeau (DEM)
                              /53

-------
S3-1

       The need for permitting these activities has been considered hi evaluating
various disposal options for the BHNIP.
S3-2

       These regulatory requirements have been included in the evaluation of these
disposal options.
S3-3
       Please see response to comment S3-2.
S3-4
       Please see response to comment S3-2.
S3-5
       Please see response to comment S3-2.
 S3-6
       Bulk sediment analyses and TCLP testing indicate that the dredged materials do
 not meet-the criteria for classification of hazardous waste.
 S3-7

       Options for the upland disposal of the contaminated dredge materials would
 include the construction of disposal facilities (inland or coastal) or the utilization of
 existing landfills.  The construction of a monofill for the disposal of the contaminated
 dredge material would require the permitting of the facility through the DSWM. As
 the DSWM has commented, current solid and hazardous waste regulations may not
 address the concerns associated with dredged material.  It is our understanding that the
 DSWM is currently developing the Comprehensive Dredging Regulations which would
 establish the siting and plan approval process for upland disposal of these materials.
 The anticipated date of the promulgation of these regulations is the Summer of 1996.
 The BNHIP, therefore, has had to depend on existing regulations to evaluate upland
 options.

-------
S3-8

       Thank you for your guidance oh this issue^ The options of reuse, recycle,
destruction and detoxification have been investigated.  None of the landfill dispos-
al/reuse options for silt are practicable relative to the alternative disposal options which
have been carried forward in the FEIS.
S3-9

       The FEIR/S has developed the concept that sediments from a particular
tributary be disposed as close as possible to the source.  In the preferred alternative,
in-channel disposal, all sediments dredged from the Mystic Channel and berths would
be disposed hi the Mystic; all sediments from the Chelsea Channel and berths would
be disposed hi the Chelsea; and, all sediments  from the Inner Confluence would be
disposed hi the Inner Confluence.  The sediments from the Reserved Channel and
berths would be the only ones transported away from the dredging site. They would
be disposed hi the Chelsea. Although still considered to be too contaminated for
unconfined open water disposal, the Reserved Channel sediments have lower contami-
nant loads than the Chelsea, so they will not compromise the environmental conditions
at that  site. Use of the in-channel trench alternative would avoid the loss of aquatic
habitat that would be incurred with creation of fastland at Little Mystic Channel.
S3-10

       The preferred disposal alternative does not include upland sites; therefore,
dewatering will not be needed for the BNHIP.
S3-11

       See response to Comment S5-2 regarding reduced sediment volume with upland
dewatering.lt may be possible to reduce the dewatered sediment volume by a factor of
greater than 20%.However,the DEIR assumed a conservative volume to ensure that
there would be no question of the adequacy of disposal capacity for the disposal
alternatives remaining for consideration.

       Dewatering as  envisioned at the time the DEIR/S was written was to use ah
drying rather than mechanical means.  Comments from the Central Artery/Third
Harbor Tunnel staff have indicated that a greater volume reduction should be expected.
Appendix I of the FEIR/S addresses both air drying and mechanical means of dewater-
ing.
                                       16
I $5

-------
S3-12
       Dewatering techniques are discussed in Appendix I of the FEIR/S.
S3-13

       In the DEIR/S, the project team sought to avoid the permanent loss of any
aquatic habitat through disposal of dredged materials.  Therefore, the fastland scenarios
were found not be among the most promising alternatives, regardless of their capacity.
Site capacity has been eliminated as a practicability criterion.
S3-14

       The benefit to cost ratio is necessary to determine the feasibility of the
navigation improvement project. This ratio refers to the dredging and disposal of the
parent material.  Silt material disposal follows the operation and maintenance regula-
tions, which does not follow a strict benefit to cost ratio.  Maintenance material (silt)
is to be disposed of in the least costly manner that meets environmental regulations
and engineering requirements.
S3-15

       The base cost against which disposal options are measured has been revised to
that of the least environmentally damaging practicable alternative.  The FEIR/S section
describing the selection of the preferred alternative has been restructured to separate
environmental and practicability considerations. In Section 4, the least environmental-
ly damaging alternatives are identified prior to application of criteria related to cost,
logistics and capacity.
S3-16
       The Corps may, at a later date, demonstrate capping at the MBDS.
S3-17

       The DEIR/S statement about disposal of parent material for subaqueous
depression and borrow pit disposal needs clarification. Since the parent material is
considered to be clean and suitable  for "unconfined" open water disposal there is little
concern about its affects on the surrounding environment. However, disposal of the
parent material must still be conducted in a manner that does not physically affect
ecologically sensitive areas outside of the disposal site. The FEIR/S concluded that
parent material not designated for beneficial use would be disposed at the MBDS.
                                        17
/5C,

-------
S3-18

       The offshore borrow pit option has currently been eliminated from further
consideration due to significant resources (shellfish and finfish). Therefore, it is not
considered to be necessary to develop a sediment chemistry database for those areas at
this time. If this option becomes feasible hi the future for the BHNIP the chemical
composition of proposed borrow material will be determined and evaluated regarding
its disposal.
S3-19
       Capping over a disposal mound is not proposed in the FEIR/S.
S3-20
       Accessibility for barges would continue to be a problem with the Fort Point
Channel.
S3-21

       The Meisburger sites, along with all of the DEIR/S shortlisted sites were
reevaluated in the FEIR/S.  In addition to concerns about interference with the MWRA
monitoring program, biological data collected hi fall 1994 confirms the fact that these
areas support productive benthic communities and high densities of lobsters.  It was
determined that the Meisburger sites would not be among the least environmentally
damaging alternatives for disposal of silts from the BHNIP.
S3-22

       Massport received a letter dated June 21, 1994 commenting on the DEIR/S
from MWRA. Mr. Mark Radville (Project Manager, Environmental Management)
indicated that a final CSO control plan would be completed hi December of 1994.
Mr. Radville noted specifically which MWRA facilities would be affected by dredging
and disposal activities, and noted that coordination between Massport and MWRA was
important, since  some CSO alternatives are being addressed on a site-specific basis.
MWRA will be informed of project plans but as currently envisioned dredging and
disposal operations should not impact CSO's.
S3-23
       The text of the FEIR/S has been revised to reflect the correct Water Quality
Classification of Boston Inner Harbor.
                                       18
/S7

-------
S3-24
       Acetone was also found in the MBDS reference sample.
S3-25

       The units for parameter concentrations for Table 2-4 is ppm, and for Table 2-6
is ppb as noted at the beginning of each table.
S3-26

       The Massachusetts DEP Classification Levels are provided on Table 2-8 as
stated on the header. The levels are provided just to the right of each parameter as 1,11
or III.
S3-27

       Based upon a review of the USEPA letter dated December 22, 1993, no
sediments having detectable concentrations of PCBs could be transported to asphalt
batch plants for thermal processing and commercial use.  If insufficient volume exists
for the in channel disposal of all of the contaminated sediments, alternative disposal
options will have to be considered. Potentially, sediments having PCB concentrations
less than 2.0 mg/Kg could be reused at lined landfills.  Sediments having PCB
concentrations greater than 2.0 mg/Kg could be treated to remove the PCBs for
disposal (burial for stabilized waste or incineration) or separated (solvent extraction)
from the highly contaminated sediments and disposed of in bulk at a hazardous waste
disposal facility.
S3-28

       It is acknowledged that MADEP has not yet officially designated PAH levels
into its regulations. This is the primary reason for the DEIR/S in stating that the levels
established for the BHNIP are similar to the Massachusetts categories, the only
difference being the PAH levels that were established for the BHNIP.
S3-29

       Concentrations below detectionlimits are considered to be below levels that
would be of concern regarding toxicity to benthic life.
                                       19
ISt

-------
S3-30

       At the time of publication of the FEIR/S, the DEP's Comprehensive Dredging
Regulations have not been completed and were not available for review by this project.
S3-31

       The referenced paragraph states that "...areas that have received other waste
materials are not always suitable for disposal facility development without remediation
first" (emphasis added). The Woburn site is, hi fact, a discontinued landfill where
disposal of silts from the BHNIP would facilitate the final closure. Table 3-4 in the
DEIR/S applies the regulatory criteria (Table 3-3, DEIR/S) for contaminant levels
suitable for disposal in different environments.
S3-32

       The potential use of dredge spoils as landfill grading material or final cover has
been evaluated hi the FEIS.  Please see response to comment S3-27.
S3-33
       Thank you for this guidance.  Please see the response to comment S3-27.
S3-34

       Please see the response to comment S3-27.  The dewatering issue is discussed
further in the FEIR/S.
S3-35

       The text has been modified to include the current soil contaminant levels for
reuse at landfills and the correct terminology.
S3-36

       The error has been noted.  The text and tables describing landfill capacity and
impact analysis in the DEIR/S have been replaced hi the FEIR/S with a new discussion
describing the rationale for eliminating landfills from further consideration.
                                       20

-------
S3-37
       See response to comment S3-36.
S3-38
      The "limited responses" statement in the DEIS refers to landfill disposal
capacity.
S3-39

       The FEIR/S continues to consider capping existing contaminated sediments at
shoreline sites to be a benefit.
S3-40

      Areas and depths for Subaqueous B and E are referenced in Section 4 and
Attachment 1.
S3-41

       The Winthrop Harbor site has been dropped from the evaluation because of the
likelihood of significant environmental impacts associated with its use for disposal.
S3-42

       The ADDAMS model used the chronic criterion of 2.9 ppb for estimating the
plume for copper in the vicinity of the Winthrop Harbor site.
S3-43

       The structure of the ADDAMS model used for all sites modeled in the DEIR/S
was based on its historical application to the Massachusetts Bay Disposal Site
(MBDS).  Since the MBDS lies beyond the three mile limit, disposal activities are
regulated by the Marine Protection, Research, and Sanctuaries Act (MPRSA) of 1972.
Under the MPRSA, water column impacts due to disposal operations are evaluated
according to EPA water quality and toxicity criteria, with allowances made for initial
mixing. The mixing zone is defined in 40 CFR 227.29, as follows:

       (a)    Initial mixing is defined to be that dispersion or diffusion of liquid, sus-
pended particulate, and solid phases of a waste which occurs within four hours after
                                       21

-------
 dumping. The limiting permissible concentration shall not exceed beyond the bound-
 aries of the disposal site during initial mixing, and shall not be exceeded at any point
 in the marine environment after initial mixing.

       The "limiting permissible concentration" of the liquid phase is defined,
 according to 40 CFR 227.27(a)(l), as

       That concentration of a constituent -which, after allowance for initial mixing as
provided in Section 227.29, does not exceed applicable marine -water quality criteria.

       "Applicable marine water quality criteria" are defined in Section 227.31 as

       ... the criteria given for marine -waters in the EPA publication "Quality Criteria
for Water" as published in 1976 and amended by subsequent supplements or addition.

       Therefore, water column impacts at Subaqueous E were evaluated by compar-
 ing the predicted concentration of copper (the most conservative parameter) in the
 water column, over the  disposal site footprint and beyond, over the four hour initial
 mixing period following a 1000 cy disposal event to the  EPA  criterion for copper.
 Since the Subaqueous sites are within the three mile limit, they fall under the jurisdic-
 tion of Section 401 of the Clean Water Act  Should these sites be selected in the final
 analysis, the Massachusetts DEP would have to determine the  standards to  be met in
 order to obtain water quality certification.  Additional water quality modelling was
 conducted for the FEIR/S (Appendix F) using additional  parameters. At this time,
 however, the Subaqueous sites are no longer under consideration as the project's
 LEDPA choice.
S3-44

       Appendix F on water quality modeling provides graphics depicting isopleths
showing where water quality violations would occur during disposal activities at
Spectacle Island.
S3-45

       Data have been provided in the FEIR/S that quantify fisheries and benthic
resources at the Meisburger sites.
S3-46

       Because it has not yet been determined where the CA/T artificial reef will be
deployed, the BHNIP FEIR/S assumed that it would be located hi Sculpin Ledge
Channel, the most recent site under discussion.
                                       22
ILl

-------
S3-47

      Refer to the Dredged Material Management Plan in Section 5.0 of the final
EIR/S. The dredging and disposal operations are described in Section 5.4.1, Dredging
and Disposal Sequencing, of the FEIR/S. Silts will be temporarily stored in scows
while the in-channel cells are being excavated. Once a cell is available to receive
dredged silts, the material stored in the scows will be  dumped. "Clean" and "dirty"
sediments will be segregated by loads. Loading of scows will not typically alternate
from silt to parent material. Typically, scows used for silts will be maintained for that
purpose and scows used for parent material will be dedicated to that material.
S3-48

       Based upon a review of Interim Policy #BWP-94-037, the reuse and disposal of
contaminated soils at landfills is limited by the concentration of several organic and
inorganic contaminants.  Bulk (total) concentration-standards have been established for
arsenic, cadmium, chromium, lead, mercury, petroleum hydrocarbons (TPH), poly-
chlorinated biphenyls (PCBs), polynuclear aromatic hydrocarbons (PAH), volatile
organic compounds (VOCs) and conductivity.  In addition, no listed or characteristic
hazardous wastes may be present in the material. The presence of characteristic
hazardous waste in the contaminated material must be tested for using the Toxic
Characteristic Leaching Procedure (TCLP).  For the sediment samples collected by
Normandeau Associates in 1993, only  chromium and lead were detected in concentra-
tions which exceed the bulk soil limits. These samples were further analyzed using the
TCLP. Neither chromium or lead were found in the leachate at concentrations which
exceeded the standards.  Thus, mixing of the contaminated sediments with clean
material to meet the regulatory standard for characteristic hazardous wastes would not
be required.

       The proposed production value of 8,000 cy/d over a 100 day period (total of
800,000 cy) does not include the time required for dewatering.  The time required for
dewatering will be dependent upon the dewatering method selected. Mechanical
dewatering may require hours while passive dewatering may require a day to several
days.  If passive dewatering is selected the production schedule would be lengthened
and may allow for the use of a greater amount of the dredge materials as cover or
grading materials at landfills.
 S3-49

       Tipping fees are no longer directly factored into disposal alternative costs.  The
 current project plan is to make clay available for landfills at one or more stockpiling
 locations located beyond the expected Central Artery/Tunnel project clay distribution
 radius.  The estimated costs to landfills of loading, transport, stockpiling, and grading
 clay from the source were weighed against the costs of obtaining cover material
                                       23

-------
elsewhere to determine a market radius for this clay.  Dewatering costs were assessed
for an alternative dewatering technology and considered in the alternatives analysis.
S3-50
       See response to comment S3-36.
S3-51
       The number of landfills potentially willing to obtain final cover material
generated by the BHNIP has been reevaluated based on information provided by the
DEP. The quantity of clay generated by in-channel disposal is estimated to be
approximately 1.3 to 2.0 million cubic yards, depending on disposal option, an
increase over other disposal options.
S3-52

       The DEIR/S describes the only known available benthic information for the
BLS area. Recognizing the limited data for this area,the BHNIP recently conducted a
benthic reconnaissance of the area in fall 1994 to evaluate the existing conditions and
proposed impacts.  Results are reported in Appendix E.
S3-53
       The ADDAMS model was run on average conditions.
S3-54

       Although BLS is not currently considered a preferred disposal site, BHNIP has
followed up with the Board of Underwater Archeological Resources (BUAR) to
identify potentially sensitive historic resources.

       In summary, BUAR identified 48 site which they consider to be potential sub-
merged Cultural resources within the study site which fully encompassed the BLS site.
The vessel types and their percent representation on the list include:
                    Vessel Type

                    Mud scow
                    Barge
                    Schooner
                    Tug
Percentage of List

       2
       21
       15
       17
                                       24

-------
                    Dredge
                    Yacht
                    Lighter
                    Trawler
                    Gasoline Boat
                    Brig
                    Freighter
                    Eagle Boat
                    Cargo
                    Passenger (small)
                    Patrol
                    Bark
                    Steamer (passenger)
                    Unknown
4
2
4
6
4
2
6
2
2
2
2
2
2
2
       BUAR also stated that the database search may not have uncovered all losses or
purposeful abandonments in the area, and that BHNIP should conduct a more intensive
literature search to further identify significant resources, should Boston Lightship be
reconsidered as a BHNIP disposal site.
S3-55

       Capping has occurred ha approximately 240 feet of water at the Portland
Disposal Site. Silty material has been capped with silt/clay and sand at this disposal
site.
S3-56

       Section 2.4.3.1  of Attachment 1 hi the DEIR/S, describes the sediments as
being made up of coarse sand and gravel (42%); boulder covered drumlins (23%); fine
grained sediments (6%); and mud, sand, and gravel (29%).  Information collected on
the surface substrate conditions using sediment profile imagery at all the potential
aquatic disposal  sites in fall 1994 indicates that there are many areas of exposed sand
and gravel at the Meisburger sites.
       314 CMR 9.03 identifies only Category One, Type A materials suitable for
beach replenishment. Category One, Type A materials are low in levels of metals,
silts and clays, water, volatile constituents and oils and greases. No chemical analyses
have been conducted on this material to date.

       Further analyses would need to be conducted to clearly establish what percent-
age of the Meisburger 2 materials, and also which specific areas of borrow materials
may be suited for future beneficial uses.  At this time, beach nourishment is  only
considered as a potential use.  As also stated in this FEIPv/S, Meisburger 2 is not
                                        25

-------
presently considered a preferred disposal site for the currently proposed BHNIP
activities.
S3-57

       Refer to the Dredged Material Management Plan (Section 5.0).

       "Rigorous turbidity controls" refer to the deployment of silt curtains and/or
other equipment around the disposal site.  Silt curtains, used as turbidity barriers, can
be used to physically control fine-grained materials that are suspended in the water
column during the disposal activities. These curtains are impervious, floating barriers
that extend vertically from the water surface to a specified depth. The depth of the
curtain can be varied. The primary purpose of the curtain is to reduce turbidity in the
water column outside of the area bounded by the curtain. It is not intended to retain
fluidized sediments or to contain the suspended solids, but to influence local  flow
patterns so that sediment laden flows are restricted to the near channel bottom and
forced to exit under the curtain or settle on the bottom.
S3-58
       See response to comment S3-56.
S3-59

       The BHNIP EIR/S team appreciates the information on the Cable Arm 100E
"environmental" bucket. The FEIR/S includes a discussion of this and other similar
devices and its potential suitability in controlling sediment suspension during dredging.
It is beyond the control of the ACOE to specify any particular make of equipment
such as that mentioned by DEP. However, it is planned to require the dredging
contractor to utilize an environmental bucket of similar capabilities for the BHNIP.
 S3-60

       Dredging will not occur in the Mystic River and Inner Confluence to avoid the
 anadromous finfish spawning period.  This time frame overlaps the winter flounder
 spawning period.
 S3-61
       The landfill discussion and tables have been revised.
                                        26
/ts

-------
S3-62

       The "environmental" bucket is available in a broad range of sizes. A number of
dredging contractors currently have buckets of 15-CY capacity or greater. Projects
have been performed, utilizing 15-CY Cable Arm*™) buckets, by Powers Marine in
Bremerton, WA, Dutra Dredging Co. in Oakland, CA, Wood-Hawkins Dredging hi
Jacksonville, FL, and Norfolk Dredging Co.  of Chesapeake, VA recently added a 15-
CY "environmental" bucket to its fleet. These buckets are readily available.

       A 15 cy bucket was assumed to estimate production rates. Recent experience
with an environmental bucket at Moran Terminal indicates  contractors may modify an
existing bucket to meet performance standards.  Additionally, large (22-26 cy) buckets
are being manufactured by the Cable Arm Clamshell company.
S3-63

       The BHNIP will consider utilization of techniques to minimize impacts on fish
during blasting operations. The mitigation required by the MHD for the Third Harbor
Tunnel consisted of a startle-system.
S3-64

       Decanting of free water from the top of the loaded bucket sihould be mini-
mized. The "environmental" bucket is most effective by filling the bucket during the
cut and minimizing the volume of free-water that is captured in the bucket.

       Decanting the bucket prior to placing its load into a scow is not required for
the proposed in-channel disposal alternative. The concern of excess water in the scow
was related to a dewatering operation.
S3-65
       We concur.
S3-66

       Most contractors with dredge plants of the size necessary for the Boston Harbor
Navigation Improvement project will work 24 hours/day unless specifications indicate
otherwise.  At the present time, no known reason exists to limit the contractor's hours
of operation.
                                       27

-------
S3-67
       Thank your for the information.
S3-68
       The BHNIP team will discuss this issue with the Division of Wetlands and
Waterways during the permitting process.
S3-69
       The text has been revised to clarify this point.
S3-70

       This information was taken into account during the revised alternatives
analysis.
S3-71

       Please see response to S3-27.  Conductivity was not measured hi sediment
samples.  Conductivity and water content may be limiting parameters for sediment
transport and/or reuse at any landfill.
S3-72

       There are no known published studies that conclude that 20 to 30% of solids
are lost to the water column during dredged material disposal activities at the Central
Long Island Sound Disposal Site. The study cited by DEP relates to differences hi
sediment chemistry between the dredge and disposal areas and are not relevant to
water quality impacts.
S3-73

       The landfill disposal/beneficial use options were re-evaluated for the FEIS..
The text includes an assessment of the clay characteristics important to landfill
capping.
                                       28

-------
S3-74

       The difficulty of dewatering sediments adequately for upland transport and
disposal, as well as current disposal siting requirements were among the factors
resulting in the selection of in-channel disposal, rather than an upland disposal site
(including Wrentham-495) as the preferred alternative.
S3-75

       The BHNIP team has met with the state and federal resource and regulatory
agencies to discuss water quality modelling and other issues since the DEIR/S. The
assumptions and results of preliminary water quality models have been presented to
these agencies and the team has received guidance from them on additional models to
prepare. The information presented in Appendix F reflects these discussions.
                                        29

-------
                                      a£ isvlaxine' ^c^Ae^te^
PHILIP G. COATES
   DIRECTOR
                                                              "
                                                                  727-31 S
                                        June 20,  1994
     Colonel Brink P. Miller
     U.S. Army Corps of Engineers
     Northeast Division
     424 Trapelo Road
     Waltham, MA 02254
      ear Colonel Miller,
                                             RE:  EOEA File #8695
     The following  are  the Division's  comments  on the Boston  Harbor
     Navigation Improvement  Project.   These comments  center on  the
     potential adverse impacts on marine fishery resources.

     First,  it should be  noted that the Division does not  oppose  the
     Navigation Improvement dredging,  but  we are concerned  about  the
     marine disposal of contaminated sediments and their potential  for
     adversely affecting the fishery resources and fishing operations.
     We have  no objection  to clean  spoil disposal at  the Mass  Bay
     Disposal Site  and  we would support contaminated and  clean  spoil
     disposal at landfill sites.

     We are strongly opposed to spoil disposal at the Boston Lightship
     Ground  and  at  Meisburger Sites  #2  and #7  because  of  fishery
     impacts.  It  should be noted  that  the only reason that the  two
     Meisburger sites were carried forward into final site selection was
     because there was no existing  fish  or shellfish sampling data in
     either of these two locations.  In discussing these  sites with  the
     fishing industry all three sites are heavily fished for groundfish
     and lobster.   The EIR provides  no assurance that materials will be
     contained at any of these three  offshore disposal sites. Similarly,
     there is likely to be considerable  uptake of  contaminants  by  the
     fishery resources  during the one and one  half year period that
     spoils are left exposed and open to the environment.  There will be
     interference. with fishing operations at all three sites.

     It is the Division's strong recommendation  that if any or  all of
     the sites are carried forward to a final EIR,  a separate
     supplemental EIR should be required  to fully examine the  physical
     oceanography,  hydrography, contamination and biology of the sites.
     Physical oceanography and hydrography studies should at a minimum

-------
Page II/Secretary Coxe

examine at least one annual cycle of bottom and ™id;w;tjr currents
at the site  for speed and direction.   Supplemental oceanographic
studies may be necessary if  information currently being collected
bythe MWRA  is  not  sufficient  for  these  locations._  Comprhensive
benthic and  contaminant  studies at all offshore  sites  should be
requisite prior  to  any site  selection.   Similarly,_ detailed fish
sampling inventories should be done at all three sites seasonally
for at least  two years.  Further,  if  either the Meisburger sites
are the  preferred alternatives it  is our recommendation  that  a
formal site designation process be required from both the state and
federal  perspective  before  the   sites   could  be utilized  for
contaminated  spoil disposal.   This  process would be similar to the
process by which the  Cape Cod Disposal Site was designated.

Based  on information  developed by the  Central Artery  it would
appear that  the Spectacle Island  CAD would not  be suitable for
spbil disposal because it is both an erosional and  dispersal site.
The Division  is  strongly opposed to Spectacle Island CAD.

The  in-channel   sites  at the confluence  of the Mystic  River and
Chelsea Creek has been suggested for  disposal through the Process
of over dredging.   These sites however, are not without Problems
First, there is no  assurance  that the cover  material  would not
displace some'of the contaminated spoils.  Secondly,  the stockpiling
of Contaminated spoils during  the  dredging process on either  side
of the Channel  would present contamination problems to anadromous
fish runs in the Mystic River and possibly the Charles River.  .Both
the  Mystic  and Charles  Rivers support  large  runs of alewives
blueback  herring,  and rainbow smelt.   The Charles  *^er *^«b!!r*
herrinq  run  is  one  of the largest  in  Massachusetts Bay. There are
nS knSwn anadromous fish runs  in the  Chelsea River  We recommend
that  if  the  in-channel sites are carried  forward into a final EIR
that  silt curtains be required as a mitigating measure at all times
and  that  the  period for  dredging  be restricted so as  not . to
interfere with these important anadromous fish runs.  This Period
of  restriction - should  run  from   February 15th  to  June  jOth.
Similarly,  the proposed blasting of  rock should not be  conducted
upstream of  the MBTA Tunnel  from February 15th to June  30th_ The
fish startle device  employed  by  the Central Artery/Third Harbor
Tunnel blasting operations  should be deployed routinely  for all
blasting events connected with this  dredging  project.  It should
also be  noted that blasting during the summer period could affect
menhaden, and striped bass.   The  fish  startle device shjould  be
utilized to avoid mortality of these  species.  These problems have
to be addressed in either the final or supplemental EIR if the site
 is to be carried forward.
 The Division has no  objections  at this  time based
 information to disposal of contaminated  spoil  in the Little Mystic
 Channel, the Reserve Channel  and possibly, although not mentioned,
 the upper end of the Fort Point Channel.  Like the Little Mystic
                                     /7C

-------
Page Ill/Secretary Coxe                ;

Channel and the Reserve Channel, the Fort Point Channel should be
investigated for  possible disposal of contaminated spoils.   The
Little Mystic Channel and  Reserve Channel sites were proposed to be
filled only to mean low water.  Because of existing contamination
at these sites it would be far preferable if these sites could be
bulkheaded  and filled  to grade  to  make fast  land   for  marine
industrial purposes rather than just filling to mean low water.

The  Amstar,  Mystic  Piers,   and   Revere  Sugar  are  all  highly
contaminated and the Division would have no objections to filling
these  sites based on  current information as  long as  they  were
bulkheaded and the contamination could not escape. The subaquaeous,
sites B and E  and the Winthrop Harbor burrow pit site are not in
the  Division's view  suitable  for disposal of  either  clean or
contaminated spoils. Winthrop Harbor has been shown to be a highly
productive  nursery and spawning area for winter flounder, lobster
and smelt (Chase,  1993) .   The subaquaeous  sites B and E are highly
utilized  by lobster  fishermen and  are  exposed to severe  storm
action and  are highly productive marine resource areas.

It should be noted that  the  Foul  Area and Mass Bay Disposal Site
were closed to the disposal of contaminated spoils because  of a
possibility of contamination, uptake and dispersal affecting marine
resources.  If this deep water site is closed for this purpose, it
makes less  sense to dispose of contaminated spoil in shallow water
sites    where  marine  productivity  is  much  greater  and  the
interference  from fishing operations  is  also much greater than
would  occur at the Foul  Area.  Moreover,  there could be greater
dispersal problems with  shallow  water inshore  sites  than would.
occur at the offshore deeper water  sites.  Massport  has  done little
in the EIR to provide any  specific impact information on either the
fishery resources or the fishing  industry in any  of  the shallow
water  sites proposed.  There has been no discussion in the EIR of
the  possibility  or  the  potential for  a public  health fishery
closure at  any of  these offshore sites which might be  required if
the  fishery resources were contaminated  to  the extent where FDA
action levels were met or exceeded.  This potential  for any fishery
closure and mitigation for such closure should be fully documented^
in the final EIR.

The Division  is pleased to have the  opportunity  to comment on the
Draft  EIR and we hope that  the project  can be accomplished with
minimal  or  no impact  on the marine  fishery resources  of the
Commonwealth.

                                    Sincerely yours,
                                    Philip  G.  Coates
                                    Director

-------
S4-1

       Additional data on biological resources at the offshore sites were developed in
fall 1994. The results confirm that there are significant fisheries resources (primarily
lobsters) and productive benthic communities at these sites.  These sites were found
not to be among the least environmentally damaging alternatives in Section 4 of the
FEIR/S.
S4-2

       Additional investigations on biological resources and substrate conditions at all
the potential aquatic disposal sites were undertaken in fall 1994.  This information was
reported in separate technical documents that were distributed to the agencies for
review. The results are also reported in Attachment 1 of the FEIR/S and were used in
the reevaluation of alternative disposal site selection.

       Disposal will occur in Boston Inner Harbor which is protected from storms.
Adequate current and tidal information is currently available to determine that disposal
of dredged material in-channel will stay in the same area. No supplemental EIR/S is
needed.
S4-3

       Neither of the Meisburger sites was found to be among the least environmental-
ly damaging alternatives.
S4-4

       The Spectacle Island CAD site was not found to be among the least environ-
mentally damaging alternatives.
S4-5

       While it is agreed that handling the dredged silt has the potential to impact
biological resources in the inner harbor, it is important to remember that the sediments
proposed for disposal have been residing in this environment.  Passage of ships causes
resuspension of silts on a daily basis.

       The Dredge Management Plan (Section 5) provides details on the disposal
operation. Apparently the DEIR/S was unclear on the necessity to stockpile sediments
while the disposal cells are prepared. Under the in-channel scenario, silts would be
stored on barges not the shoreline or underwater and the lag time between initial
dredging and disposal would be on the order of a week.  Once the initial cells were
                                       30

-------
 constructed, the silts usually would be disposed immediately.  The Dredged Manage-
 ment Plan also discusses the merits of various methods for containing the disposal
 operations.

       A sand cap would be used to isolate the silty material from the surrounding
 silty material. Research and State  and Federal agencies have concurred that a sand cap
 would not displace the silty material.  An environmental window has been proposed
 for anadromous fish in the draft and  final EIR/S.
 S4-6

       The methods to prevent fish mortalities from blasting are presented in the
 Dredge Management Plan (Section 5).
S4-7

       The shoreline sites cited in this comment have been included in the FEIR/S,
with the exception of the Fort Point Channel. Fort Point Channel is not easily
accessible by barge and, therefore, unsuitable for this use. The disposal site alterna-
tives analysis concluded that partial filling of shoreline sites was among the least
environmentally damaging alternatives.
S4-8

       The disposal site alternatives analysis (Section 4) concluded that the Subaque-
ous B and E sites were not among the least environmentally damaging alternatives.
S4-9

       The effects on existing biological resources at and near the potential aquatic
disposal sites are described in Attachment 1 and used to compare the environmental
risks of silt disposal at these sites in Section 4.

       The Massachusetts Bay Disposal Site has been designated by EPA as a dredged
material disposal site.  Until capping or other management technique has been shown
to sequester contaminants, no disposal of dredged material can occur at the MBDS.
We agree that disposal of dredged material in an area designated for dredged material
disposal and where previous disposal has occurred would minimize impacts from
dredged material disposal.
                                       31
113

-------
S4-10

       Biological data, including fisheries resources, on each of the potential aquatic
disposal sites are presented in Attachment 1.
S4-11

       None of the offshore sites was found to be among the least environmentally
damaging alternatives.
                                      32
I If

-------
            Massachusetts Highway Department

            Central Artery/Tunnel
      June 20, 1994

      Colonel Miller
      U.S. Army Corps of Engineers, New England Division
      424 Trapelo Road
      Waltham, Massachusetts  02254

      RE:  Draft Environmental Impact Statement/Report for Boston Harbor
           Navigation^jjjroKpvement and Berth Dredging Projects

      Dear Colonel Miller:
      Enclosed  are  the  Massachusetts  Highway  Department's  Central
      Artery/Tunnel  (CA/T)  Project  comments on the  US Army  Corps  of
      Engineers and Massachusetts Port Authority (joint proponents)  Draft
      Environmental  Impact  Statement/Report  (DEIS/R)  for  proposed
      Navigation Improvement and Berth Dredging Projects (BHNIP).   The
      CA/T Project and the BHNIP team have  benefitted  from ongoing  close
      coordination over the past  year.  We  expect  to continue to work
      with the BHNIP team in relationship  to the CA/T Project immersed
      tube tunnel, Spectacle  Island,  and  artificial  reef construction
      activities.

      The DEIS/R briefly  discusses  interfaces  with these CA/T Project
      activities in various sections of the document.  Continued  close
      coordination of the  proposed BHNIP work with the CA/T Project will
      be required to ensure that  CA/T  Project costs are not increased,
      construction schedules are not delayed, and the Project's ability
      to meet Project commitments is not adversely affected by the BHNIP.

      If you have  any  questions,  please call Mr.  Ronald Killian, CA/T
      Project  Manager of Environmental Procedures  and Permits, at 951-
      6467.

      Sincerely,

      MASSACHUSETTS HIGHWAY DEPARTMENT
      Peter
      Proj ectdDirector

     .PMZ/EWI/nmm

      AL-1.3
      094-1970
      Attachment
      cc:   R.  Killian
           Massachusetts Port Authority, Maritime Department,  Boston, MA
           G.  Kelly,  U.S. Army Corps of Engineers, Waltham, MA
                                                       775
One South Station
Boston
Massachusetts
                                        02110
                                 Phone 617-951-6000
Fax 617-951-0897

-------
Colonel Miller
094-1970
                            ATTACHMENT
Massachusetts Highway  Department's  Central Artery/Tunnel Project
comments  on  EOEA #8695 Massachusetts Port Authority  and US Army
Corps of Engineers Draft Environmental Impact Report/Statement for
proposed  Boston  Harbor Navigation Improvement  and Berth Dredging
Proj ects

Interface  of Central  Artery/Tunnel  Project  and Boston  Harbor
Navigation Improvement and Berth Dredging Projects

The  proposed  Boston  Harbor Navigation   Improvement and  Berth
Dredging Projects (BHNIP) would deepen two areas in Boston Harbor's
Main  Ship Channel,  the Inner  Confluence and  the  mouth of  the
Reserved  Channel,  and three  tributary  channels,  the  Reserved
Channel,  the Mystic River, and the Chelsea Creek Channel.   The
deepening would  improve the channels and berthing facilities with
the aim of allowing the Boston  region to  remain competitive in a
global market.   The Draft  Environmental  Impact Report/Statement
(Draft EIR/S) estimates that the BHNIP will have a duration of 18
months  and  recommends commencement  of  the  work  in 1996  with
completion in 1998.

The Massachusetts Highway Department's (MHD) Central Artery/Tunnel
(CA/T) Project  is,  in part, being  constructed in Boston Harbor.
Construction activities in the Harbor include the Project's Third
Harbor Tunnel (an immersed  tube  tunnel)  and materials  disposal and
mitigation measures  at Spectacle Island.   While the Third Harbor
Tunnel has  been  placed and backfilled,  barging of  material to
Spectacle   Island   is   expected    to   continue  through   1996.
Construction activities on  Spectacle Island will continue for some
time after that, which include capping the landfill and developing
a park.  In connection with this work, a seawall cind  dike will be
constructed, utility lines  will be  located between Spectacle and
Long Islands, and an artificial  reef is  proposed to be constructed
(in 1996) in the Sculpin Ledge Channel between  Spectacle and Long
Islands.

Executive Summary
 *• .'                                             .
     1.   Page ES-2, Sediment Characterization

Page ES-2 states that  the  BHNIP will result in approximately 1.3
million cubic yards  (cy) of silt requiring disposal, and that this
quantity  includes a  post-dredging estimated expansion factor of

-------
 20%._  This statement should be clarified to indicate as set out  in
 Section 3.4, that  the expansion factor  is  expected for  aquatic
 disposal options.  Page 3-12  states that for land-based options,  it
 was assumed that dewatering and compaction would reduce the silt
 volume nearly to its in-situ  estimate of approximately i.i million
 cy. As an informational  note, the CA/T Project's experience with
 construction of the Third Harbor Tunnel found silt material, when
 deposited on land, to have a shrinkage factor of  approximately 20%.

     2.   Page  ES-5 and ES-6, Other  Actions

 Draft  EIR/S pages ES-5 and ES-6 indicate that the MHD expects that
 placement of the Third Harbor Tunnel excavate at Spectacle  Island
 will be complete in 1995.  As indicated above, barging of material
 to  Spectacle Island  is  expected to continue  through  1996,  and
 construction activities will continue for some  time  after that.

 Section 3.0, Disposal  Site Alternatives Analysis

 The Draft  EIR/S identifies  as one of  the preferred disposal
 alternatives, a Controlled  Area Disposal  (CAD)  site in the area
 immediately east of Spectacle Island.  The  Spectacle Island CAD
 would  be created by dredging a 22-  to  50-acre  disposal pit in a
 shallow,  subtidal flat area along the eastern side of the island,
 then filling the pit with  silty sediments  from the harbor dredging
 project,  and finally  capping it with some of the  removed native
 material.    Excess  native material  will  be disposed of  at  the
 Massachusetts  Bay  Disposal  Site  or  transported  elsewhere  for
 beneficial  reuse.

 At the  time the Spectacle  Island CAD  work  is anticipated, the CA/T
 Project site preparation  work for landfill  closure  on Spectacle
 Island  will be nearing completion,  including the seawall and dike
 construction.  Any  excavation  activities  in  the Spectacle Island
 CAD  must be carried out  to  minimize impact to the  stability  of
 these structures.  An evaluation should be done of the changes in
 wave run-up on  Spectacle Island due  to the   excavation  of  the
 Spectacle Island CAD.   In particular,  the effects of wave run-up on
 the CA/T Project's seawall and Spectacle Island beach nourishment
 work should be evaluated.   In addition,  the   health  effects  of
 Spectacle Island CAD sediment washing up on the  Spectacle Island's
 southern beach (a planned bathing beach) should be evaluated.

 Utility ^lines will  be located between Spectacle Island and Long
 Island  in the vicinity of the  Spectacle Island  CAD  (see attached
 Figure  A).  Care must be taken not to disturb these facilities.

Potential Impacts on the Artificial Reef               y-

The artificial reef to be constructed by the CA/T Project as part
of Spectacle Island mitigation will be located in the  Sculpin Ledge
Channel between Spectacle  Island and  Long  Island, in the same
S5-3
S5-4
                                    777

-------
general area as the Spectacle Island CAD (see attached Figure A) . -
As currently planned, the closest point within the. area sited for
the artificial reef would be approximately 100 to 200 yards from
the Spectacle  Island  CAD.   Any activity at the Spectacle. Island
CAD,  including  excavation,  placement  of  dredged material,  or
capping, must  be performed  in a manner that  will not impact the
structural integrity or performance of the artificial reef modules,
or decrease its potential as a fisheries resource area.

Based on the Draft EIR/S, we are particularly concerned with the
potential  impacts  of  total  suspended solids  (TSS)  from  the
Spectacle  Island CAD, which  could  affect  the  reef  performance.
High concentrations of TSS  in the water column could affect the
development of the  desired  blue mussel fouling community  on the
artificial  reef, by  interfering with the spawning  and  filter
feeding processes of these organisms.

Page 3-39  of the Draft EIR/S states  that,  based on disposal silt
plume modeling,  suspended solids  concentrations generated  by the
CAD activities should be low  (<30 mg/L).  The historic range of TSS
levels in  Boston Harbor  has  been 8-188 mg/L.   If TSS levels from
the Spectacle Island CAD can be maintained  below  30 mg/L, then we
would anticipate no significant impacts to  the  artificial reef.

TSS Sources and  Control Measures

Our  concerns  with  regard   to  minimizing TSS  impacts  to  the
artificial reef  from  the Spectacle Island  CAD center on:  1) the
timing  of  CAD  construction  and operations;   and  2)  the  BHNIP
materials handling techniques.

Construction of the Spectacle Island  CAD could affect  the proposed
artificial reef if the construction dredging takes place during  (or
shortly after) deployment of the reef modules,  and if  the dredging
creates heavy TSS plumes. Use of silt curtains and a  closed dredge
bucket during CAD construction may help to minimize the TSS plumes;
however, it is not known how effective these control measures could
be should  there  be a minimum of 100- to 200-yards between the two
proj ects.

Operation  (and closure) of  the Spectacle  Island CAD also could
affect the proposed artificial reef.  We therefore request that the
BHNIP team be  required to  conduct a siting study which  addresses
possible impacts of the CAD  operations to the Project's artificial
reef and the Spectacle Island dike and seawalls.  Disposal of fine-
grained sediments from the BHNIP over a  1-1/2 year  period could
create high TSS  levels in the water column.

We request that  the BHNIP minimize  TSS impacts  in Sculpin Ledge
Channel  through  the  use  of  adequate  control  measures  during
construction  and operation  of  the  Spectacle  Island  CAD.    TSS
control measures during  operation and  closure of the CAD could

-------
include  use of silt  curtains  and restrictions on the  timing of
disposal  operations to  avoid  periods  of  maximum ebb  and  flood
tides.   To  further ensure protection  of  the reef and  of  other
aquatic  resources  in Sculpin  Ledge Channel,  the BHNIP. should
include  a  TSS  monitoring  program,  with specified  exceedance
criteria, reporting' requirements, and contingency plans.

Section 4.0, Dredging Management Plan

     1.   Noise Impacts

Section  4.0 gives  an  overview of  the potential  environmental
impacts of the dredging operations and  likely mitigation measures
to be  employed (Page 4-1).   Potential noise  impacts and likely
mitigation measures are not discussed.  Dredging areas will be in
close  proximity  to buildings,  especially  dredging areas in  the
Reserve Channel, Mystic  River,  Chelsea  River,  and along the East
Boston  waterfront.    Residential  housing areas  and  a  school
(sensitive  noise receptors) are located  along the East Boston
waterfront.   In addition,  the  Squantum Point Disposal  Site is
adjacent  to a large  condominium complex  and  recreational  area.
Potential  noise  impacts  need  to  be identified,  and  mitigation
measures committed to for any expected  significant noise impacts.

     2.   Subsection 4.1.1, Mechanical  Dredge Plant

Subsection  4.1.1  of the Draft  EIR/S states that  a modified, or
environmental, bucket is planned to be used when dredging the silt
sediments.  The subsection also indicates that a scow size range of
2-3,000 cy is assumed.  While scows range between 4 and 5,000 ton
capacity  (4,000 tons roughly correlates to 2-3,000 cy),  depending
on the disposal option, bin barges may be required.  Bin barges are
used  when  mechanical removal   of  material  from the  barge  is
expected, and a typical  bin  barge holds only approximately 1,200
cy.   Thus,  if  bin barges  are  used, there  would be more  barge
traffic than indicated, which should be considered.

BHNIP  barging  operations that  overlap  the CA/T  Project barging
operations must  be carefully coordinated  to  minimize  impacts on
commercial and recreational traffic in  the area.

     3.   Rock Blasting

According to the  Draft EIR/S (Page 4-4),  rock is  expected  to be
encountered  at the mouth  of the Reserved Channel, in  the  Inner
Confluence  and  in  the  Mystic  River  Channel.   Rock blasting is
expected  to be required  to  remove the rock.   The blasting, in
particular any such activity planned at the mouth of the Reserved
Channel, should be reviewed by  the CA/T  Project to  ensure that the
integrity of the Third Harbor Tunnel is maintained.
S5-7
S5-8

-------
                S5-1

                      The preferred disposal alternative, in-channel, will not interfere with CA/T
                operations.
                S5-2

                      A 20% expansion factor was used to accommodate dredged material placed hi
                upland sites.  Additional analysis of dewatering has led to the conclusion that it is
                possible to reduce the volume capacity at upland sites to the in-situ volumes at the
                expense of time or mechanical dewatering.  The FEIR/S discusses the dewatering
                process and costs in Section 4.0 and Appendix I.
                S5-3

                      The references to MHD's construction schedule at Spectacle Island have been
                revised to reflect this information.
                S5-4

                      Modification of typical wave run-up at the Spectacle Island site would not be
                anticipated because the plan calls for pre-construction depths to be recreated following
                placement of the dredged materials. A relatively broad reach between the upland side
                of the proposed  CAD facility and the existing shoreline of Spectacle Island would be
                maintained. During construction of the CAD, it would be possible for waves which
                would normally break at or seaward of the offshore edge of the CAD to propagate
                towards the Island in an unbroken  state; the deeper water within the excavation would
                support longer period waves which would normally break offshore of the site. Howev-
                er, these waves would clearly break as they passed over the restricted existing depths
                shoreward of the proposed site. Some modest increase in wave run-up could be
                expected, but no serious threat would be posed to a properly designed seawall. A
                modest and temporary change to the  local wave climatology could impact the beach
                nourishment work,  depending upon the depth to which this nourishment will be
                extended.

                      The Spectacle Island CAD was not selected as the preferred disposal alternative
                for the BHNIP, although it may be reconsidered for future maintenance.
ffl
                                                      33

-------
 S5-5

        The likelihood of interfering with the CA/T's artificial reef in Sculpin Ledge
 Channel was evaluated for both the Spectacle Island and Subaqueous B alternatives.
 S5-6

       The Massachusetts Highway Department, Central Artery/Tunnel recommenda-
 tions for TSS control measures will be taken under advisement and considered fully
 should the associated construction and disposal activities go forward at Spectacle
 Island. Please keep in mind, however, that "closed"  dredge buckets do not necessarily
 assure that low TSS levels will result. Experience has shown that properly vented
 "environmental" buckets, operated by an experienced and skilled dredge operator can
 be much more effective than a closed bucket.

       See response to Comment S5-5.  Predicted water quality effects are described
 hi Appendix F. Note, however, that the Spectacle Island CAD was not selected as the
 preferred alternative (Section 4.0) for the BHNIP silt.
S5-7

       Noise impacts are discussed in Section 5.0 of the final EIR/S. No significant
noise impacts are expected from the dredging and disposal of dredged material.
S5-8

       It is not anticipated that bin barges will be typically used at this site. Bottom
dump scows will be the preferred method of disposal.

       The DEIR (subsection 4.1.1) recognizes the potential need for barge sizes
smaller than the 2-3,000 cy scow which would be used for ocean disposal.  Smaller
barges such as 1,200 cy bin barges will most likely be used if mechanical removal of
the dredged material  is expected.  The number of trips using barges this size would
increase proportionally.  While barging operations currently envisioned are on the
order of four barges per day, they will be coordinated among the harbor's commercial
users via marine radio. Negative impacts on recreational traffic will be nainimized as
much as possible but cannot be prevented entirely.

       The BHNIP will involve rock blasting in the vicinity of the Main Ship Channel
near the mouth of the Reserve Channel, based on the current dredging plan. Due to the
close proximity of this area to the Third Harbor Tunnel the blasting plan will be
coordinated with the  CA/T Project to ensure the integrity of the tunnel is maintained.
                                       34

-------
               S5-9

                     Review of blasting plans by CA/T staff is welcomed due to their recent
               experience in the harbor.
                                                     35
IVO

-------
COASTAL ZONE
MANAGEMENT
    To:
  From:
  Date:
    Re:
                              MEMORANDUM
Jan Reitsma, Director, MEPA UnitM,  //'
Margaret M. Brady, Director, C24et«U' •L
June 7, 1994                     '
EOEA   #   8695   Boston   Harbor
Dredging  (BHNIP) ; Boston
                                Navigation  Improvement
  The  Massachusetts  Coastal  Zone  Management   (MCZM)  Office  has
  completed its review  of  the  above-referenced  Draft Environmental
  Impact  Report -(DEIR), noticed in the  Environmental Monitor  dated
  May  10,  1994, and has the following comments.
  Project Description

  The  BHNIP proposes  to  improvement  dredge approximately 3,300,000
  cubic yards (cy) of material from three tributary channels (Mystic
  River,  Chelsea  Creek and the Reserved Channel) and twelve  berth
  areas  (see DEIR p.  ES-1)  in Boston Harbor.   The Mystic River  and
  Reserved Channel will be  dredged  to -40  mean low water  (mlw),
  Chelsea Creek to -38 mlw;  the berth  areas  will be dredged to  the
  depth of the channel on  which they rely  for access.   The US Army
  Corps   of  Engineers (USAGE)   is  the  project  proponent for  the
  improvement work in the channels; the Massachusetts Port Authority
  (Massport)  is the local sponsor for the improvement work, the sole
  proponent for Massport berths, and the project coordinator for  the
  private berths.   The purpose of the project is  to increase  the
  controlling  depths  in the harbor to  accommodate the  container
  ships,  bulk  carriers  and  tankers  that  service the  New England
  region  through the port of Boston.

  Of the  total project volume, 1,300,000 cy is silty, unconsolidated
  material that  overlies  approximately 2,000,000  cy  of  cohesive
  Boston  blue clay. An additional 132,000 cy of rock will be blasted
  from the  main  ship  channel.   Notwithstanding  their  potential
  beneficial use, the clay  and rock  are  suitable  for unconfined
  disposal at the Massachusetts Bay Disposal Site (MBDS).  Because
  the  silts are predominantly anthropogenic, they  contain moderate to
  high levels of  contaminants typical of an urban port,  and are  not
  suitable for unconfined ocean disposal.  (It is important to note
  that the  disposal  of  dredged material  is  governed  not by  the
  numerical value  of  a. given contaminant in a sample, but rather by
                          \

-------
an evaluation of the potential biological effects  of that material
as  evidenced by  test  organisms.   Biological testing  of Boston-
Harbor  sediments indicates that the potential  bioeffects of the
material  on  marine organisms vary by site; that is, the levels of
contaminants in Boston "Harbor  are  not distributed evenly.   See
Sediment  Characterization, below, for further discussion.)

In  addition  to the  volumes  of material  to be  dredged  by the
immediate project,  an estimated 5,800,000 cy  of  silts will need to
be  removed  over  the fifty-year life  of the project,  including
4,400,000 cy from the main ship channel and 1,800,000 cy from the
tributaries,. The DEIR has properly incorporated these volumes into
the evaluation  of potential disposal sites, and  review of the DEIR
and the selection of a preferred alternative should be based on the"
total volume of ^,100,000 cy of material unsuitable for unconfined
ocean disposal.

The  disposal  of  the   contaminated  sediments  from this  project
present  numerous  challenges  at both  the policy  and  regulatory
levels.   While the EOEA agencies have  agreed conceptually on the
utility  of  alternative disposal methods,  for  this  and previous
projects, the BHNIP represents the first major application of these
alternative  disposal methods in Commonwealth waters.

It  is   therefore  possible  that  the  disposal  alternative (s)
preferable to MCZM and/or the EOEA line  agencies will  not agree
with the  "preferred alternative" as identified  by the  USAGE.  To
determine the preferred alternative  the USAGE applies the "federal
standard," which  identifies the most appropriate disposal site as
that which is the least costly alternative consistent with sound
engineering  practices and which meets the environmental standards
of either the Clean Water Act or the Ocean Dumping Act.  The costs
associated   with  disposal  of  material  at  the  USAGE  preferred
alternative  set a ceiling of funding above which the non-federal
participant  (Massport)  must bear all additional costs.  Depending
on the  outcome of  the  MEPA process, disposal  expenses  above the
USAGE ceiling may be  significant.
      Regulatory  revision  and/or advances in  the -development or
application  of  alternative  disposal  technologies may  modify or
obviate  contemporary disposal  techniques.    However,  planning
efforts  cannot reasonably anticipate the  potential  reduction or
elimination  of the  need for disposal sites  as identified in the
DEIR.    MCZM  review of  the  DEIR  is  therefore based on  the
application  of the "best available technology" standard.
                                                               WWB*q
To  encourage the  continued technical evolution  of that standard]
MCZM  recommends  that the BHNIP incorporate  a  demonstration of
innovative  disposal  technology.  See Innovative Technology,  below]
for further  discussion.

-------
 Given the potential emergence in this project of what has, in the
 past, proved to be a  divisive  situation,  we encourage  both the
• USAGE and  the regulatory agencies  to approach the  comments and
 do.recta.on resulting from MEPA review of this preliminary document
 with an appreciation that both the regulatory oversight of natural
 resources and  the  technology of  dredged  material  disposal are in
 transition, moving towards better identification of resources and
 potential  impacts  and more precise methods of handling dredged
 material.  A project of this magnitude offers significant potential
 as a  laboratory of sorts with  benefits  to regional  and perhaps
 national resource management efforts, and warrants  some latitude in
 the application of traditional formulae.


 Comments

 MCZM offers the following comments on several elements of the DEIR,
 including   the  MEPA   process,   MCZM   jurisdiction,   sediment
 characterization,   the    alternatives    analysis,    innovative
 technologies,  the  dredging management plan,  and management  and
 monitoring of the disposal sites.
MEPA Process

While the  DEIR  presents  sufficient  information  to  generally
identify preferable disposal alternatives,  additional information
that more accurately and consistently characterizes the resources
present  at the proposed disposal sites and the potential impacts to
them,  is  necessary.   MCZM  therefore recommends  that the  FEIR
provide  sufficient information for reviewers to make a quantitative
distinction   among  the  proposed  disposal  site   alternatives
identified  in  the  DEIR as  "practicable,"  as  well  as  those
additional sites identified in our comments, below.

In  addition,  MC2ja__rgguires  detailed information to  evaluate  the"
potential impacts to the coastal zone of disposal of contaminated
sediments at the specific site(s) to be identified by the proponent
as  the preferred alternative.  While it has been proposed that the
evaluation of a  disposal site for the BHNIP silts  should proceed
under the assumption that disposal at that site will be a one-time
activity and should thus be subject to less conservative standards
than those applicable to a site that will experience continual use,
e.g.,  the  Cape  Cod Disposal Site,  MCZM  does  not  agree.    The
preferred alternatives identified in the DEIR have  been selected
largely   because  they  will  accommodate   material  from  future
maintenance work in Boston  harbor;  the site ultimately selected
will, in other words, experience continual use.  Furthermore, it is
entirely possible that once a site has been permitted  for  use by
the BHNIP, it may prove to  be the most practicable  site  for  the
disposal of material from unrelated projects.
n
«

-------
KCZM has  consistently required a minimum of one year  of baseline
data by which to evaluate the proposed ocean disposal of dredged
material,  in the  interest of evaluating  seasonal variations in
community   structures,   fisheries   resources,   wave and  current
regimes, and the long-term depositional nature  of the site.   MCZM
.will therefore require that the proponent produce  a SupplementaT
EIR (SEIR) to address the issues specific to the site(s) ultimately
selected,  e.g.,  one year baseline data, discussion of impacts to
resources  at  a specific site,  and a  plan for  management and
monitoring  of   operations,  in  order  to  complete our  federal
consistency review.                                             .

MCZM believes that this approach serves the purposes  of both the
EOEA agencies and the proponent: An SEIR based on one year of data
(see Attachment l)  should provide sufficient information for the
agencies  to evaluate  the potential  impacts  to  immediate and
regional resources given a specific project configuration, and will
also allow the proponent to address significant regulatory concerns
prior to permitting.
MCZM Jurisdiction
The DEIR states  in Section 5.1, Regulatory Compliance, that under
the provisions of the Coastal  Zone Management  Act (CZMA),

          the  Massachusetts  Coastal  Zone   Management  Program
          conducts reviews of all proposed federal projects, and
          other  projects  requiring  federal permits,  within the
          coastal  zone  to  determine  their consistency  with
          applicable CZM regulatory (13) and  non-regulatory  (14)
          policies.  [DEIR p.5-1;  emphasis  added]

That statement is inaccurate.  The CZMA, as amended in 1990, states
at Section  307  (c)(1)(A)  that

           [e]ach Federal agency activity within or outside the
          coastal zone  that affects  any  land or water  use or
          natural resource of the coastal zone  shall be carried out
          in a manner which is consistent  to the  maximum extent
          practicable with  the  enforceable program  policies of
          approved State management  programs.  *** [16  U.S.C.  1451
      See the MEPA Scope,  EOEA #3692, May 1, 1980  (initial scope
for the  designation of the Cape Cod Disposal Site  for which MCZM
was  the  proponent) ;  MCZM  comments  on the  Gurnet  Point  site
(proposed disposal site for dredged material from Duxbury harbor),
November  9,  1988; and  MCZM  comments  on  the  proposed USAGE
maintenance and improvement  dredging of the  approaches to Hyannis
harbor, dated March 22,  1994.

-------
           et  sag./  emphasis added]
The  USAGE and Massport  should  therefore be aware  that  they are
required to file a federal consistency determination that addresses
the  impacts  of  both the  dredging and  the disposal  of dredged
material at.any marine site(s) ultimately selected for this project
irrespective  of  the relationship of  the  disposal site to the
territorial waters of the Commonwealth.  Please note that federal
action  on the BHNIP is  contingent upon  receipt  of a concurrence
from this  office.

MCZM will  review the BHNIP for consistency with Policies 3,  4, 5,
13  and 19.    Policy 6  will  apply • if the Meisburger sites are
selected.   (See  Attachment 3 for MCZM Policies.)


Sediment  Characterization

MCZM   commends  Massport  on   their  commitment   to  obtaining
scientifically valid data regarding sediment characterization and
biological testing to determine suitability.  The historical data
sheets on the use of each berthing area were of value in evaluating
and interpreting data subsequently collected for sediment analyses.

MCZM concurs with  Massport and the USAGE  that the Boston blue clay
and  rock  material  are suitable  for  ocean  disposal  at  the
Massachusetts Bay Disposal Site.   Massport and the USAGE propose
that while the majority of the silts (approximately 1.1 million cy)
are  unsuitable  for  unconfined  ocean  disposal,   360,000  cy  of
material from the  Reserved Channel, Gulf  Oil, Army Base and Conley
Terminal  is suitable for unconfined ocean disposal.   MCZM does not
agree  and concurs with the  US Environmental  Protection  Agency
(USEPA) that the total 360,000 cy from these areas are not suitable
for unconfined ocean disposal.
      See  • the  MCZM   consistency  certification   of  the   US
Environmental Protection Agency's site designation  of the MBDS,
dated November 13, 1992.  See MBDS, page 7,  for further discussion.

The  upland '  disposal  of  dredged material  outside the  inland
delineation of the coastal zone generally does not fall under MCZM
jurisdiction, providing it does not affect  land uses or resources
of the coastal zone. MCZM will assert jurisdiction over activities
related to the upland disposal of  dredged material that take place
within the coastal zone e.g., dewatering facilities, staging areas,
transportation routing.  MCZM jurisdiction over the upland disposal
of dredged material within the coastal  zone 'is contingent upon the
nature of the federal  permits required .for  the activity.

-------
The basis for determining suitability is prescribed by the federal
protocols, Green Book, (Evaluation of Dredged Material Proposed for
Ocean  disposal  (Testing Manual), USEPA/USACE,  1991, Washington,
D.C.).   The Green  Book  establishes several criteria by which to
evaluate  the  results  of  the tests  that  measure  toxicity  or
mortality  and/or   bioaccumulation  of  contaminants  in selected
organism tissues.   These criteria include  applying  traditionally
accepted  methods  for  statistically  determining  differences  in
tissue residues of metals and organic chemicals such as polynuclear
aromatic hydrocarbons (PAH) and polychlorinated biphenyls (PCB) ,
evaluation of the degree of response (e.g. magnitudes of toxicity,
number  of  species,  involved,  magnitude  of  difference, numbers of
contaminants  demonstrating  significant  differences, toxicity of
compounds  and  the propensity  for  biomagnification within  food
webs) .   Based on the results  of  the  tests, one or more of these
criteria  have  been demonstrated for the  silty  portion  of  the
Reserved Channel and berthing areas.

Specifically, the berthing area toxicity test results demonstrated
mortality of amphipods at all sites exceeded mortality to amphipods
exposed to  reference (clean) sediments by more than  20%, the end
point  determined by Green Book protocol  (Tables 6 and 7 and 12 ,
EIR, 1994) .  Similarly, at each site one or more metals  and one or
more PAHs and/ or PCBs showed significant bioaccumulation in one or
both species in bioaccumulation tests  at the 95% or higher level of
certainty.   In other words,  more than one category  of chemicals
measured in tissues (metal or organic  compound)  were statistically
significantly higher  than  tissue  residue levels  of  organisms
exposed  to  reference  sediments  in  the two species used for the
tests .
                                                               ••^B
Interpreting  data  from the  Reserved Channel  is  more difficult
because  early  chemical analyses did  not  meet  the appropriate
detection limits.   The presentation of information in the EIR/S is
indecipherable.   However,  from other USAGE documents,  one of the
two toxicity  tests showed significant toxicity whereas the other
test was inconclusive.  In addition, significant bioaccumulation of
chromium  and lead  in tissue residues  from organisms exposed to
sediments  from  two  locations  in  the  Reserved  Channel  showed
significant  uptake.    Organic  chemical   analyses   cannot  be
interpreted because  the detection  limits were  not acceptable.
Based  on the application of  the Green Book criteria to the results
of the toxicity tests and the significant  bioaccumulation of two
metals,  these  sediments are  not suitable  for unconfined ocean
disposal.                                                       _
Alternatives Analysis

The following comments are presented in four sections: The first is
MCZM's   comments  on   the  sufficiency 'of  the   alternatives
                                     Jff

-------
 analysis/site screening process; the second  is our analysis of the
 "potentially practicable" sites  [Table ES-lb] and the "alternatives
 not found practicable" [Table ES-lc]; the third  is our analysis of
 S™,"PraCt:LCablelt  SiteS [Table E5-1*]; and  the fourth discusses
 MCZM's preferred alternatives for the disposal of the silts.

         lives Analysis/Site Screening Process
The  USAGE  and  Massport,  with  input  from  an  advisory  group
representing a  broad spectrum of  interests,  have engaged  in an
exhaustive  screening process  to  identify  potentially  suitable
disposal sites  for the dredged material not suitable for unconfined
ocean disposal.  For the purposes of examining a sizable universe
of  potential sites  and screening them down to a manageable number,
MCZM believes that  the  criteria  applied to, and  the conclusions
reached by,  the site screening process  articulated in the DEIR
reasonably narrow the universe of alternatives to those sites that
can most practically provide for the  environmentally responsible
disposal of contaminated sediments.

However, MCZM believes  that  the DEIR,  in  determining the  finaT
allocation  of   sites   as  either  "practicable,"   "potentially
practicable," or "not.. .practicable,"  has  in  some  cases either
ignored or arbitrarily  applied criteria  that are discussed in the
DEIR.   It should be further noted that the DEIR does identify the
proponent's preferred  alternatives outright,   and  with  greater
specificity than in Table ES-la: At  page 3-25 the statement is made
that

           [in compliance with the National Environmental Policy Act
           the  proponents]   "select   the...[MBDSJ,   the  Boston
           Lightship,  Meisburger sites 2 or 7, and Spectacle Island
           CAD as their preferred  alternatives."

Thus  we are presented a DEIR which on the one hand goes to great
lengths to  justify  or  eliminate potentially practicable sites,
while it simultaneously identifies the preferred alter native (s) as
a foregone conclusion.   Further review of the alternatives in the
FEIR  as discussed below should therefore be predicated on a more
careful and  accurate representation of costs  and  environmental
impacts than those presented  in the DEIR.
      If  the  proponents  take  the  concluding  language of  the
Executive  Summary seriously,  and the statement that the "[f]inal
selection  of a preferred disposal option will be made based upon
public comments received on this  DEIR/S" does  indeed control, the
identification of  preferred  alternatives  in the  FEIR must  be
expanded from those identified for the purposes of NEPA on page 3-
25 to include those that are recommended by the Commonwealth and/or
which meet the proponents' own screening  criteria  at page 3-26.
Otherwise,  the evaluation/screening process is a moot concern and

-------
  Tables ES-lb  &  Ic
  Page   3-26   of   the  DEIR  presents  a  six-strep   "practicability
  screening" for the final twenty-four sites under consideration.  In
  summary,  the steps  include an analysis of:

  1.   Habitat loss/ impact to resource function;
  2.   Water quality  impacts;
  3.   Socioeconomic  impacts;
  4.   200,000 cubic  yard minimum capacity;
  5 .   Cost greater  than  four  times  capping  at the  MBDS deemed
       excessive  [4 x $18 — $72]; and
  6.   Potential  to accommodate future maintenance material.
                                                                  •*•!.•
  MCZM believes that  the  200,000 cy minimum capacity is  an arbitrary
  figure:  Neither Amstar, the Mystic Piers, nor Revere Sugar would
  qualify   individually .under  that threshold,  but  they  offer  a
  cumulative capacity of at least 311,000 cy'and may thus provide one
  element  of. a disposal site "mix."

  Similarly;  the  cost and capacity criteria appear to be applied
  arbitrarily: Three  of the six least expensive alternatives fail the
  total-volume capacity test (in-channel,  Meisburger 2 and Spectacle
  Island CAD), while, conversely, Tables ES-lb  and  Ic contain sites
  that meet the 200,000  cy capacity test  and the $72/cy test, but
  which  are not elevated  to the final list.

  No  rationale is given, for example,  for the exclusion from the
  final  list of the Little Mystic site, which, at $33/cy,  a  capacity
  of  303,000  cy,  and  the benefit of Designated Port Area  (DPA)
  status appears  to meet  the criteria by which,  say,  the  in-channel
  alternative  was  judged.   If the Little Mystic were  filled to a
  greater  depth than proposed in the DEIR, £t could offer significant
  potential as an in-harbor disposal site.
  we ought to have been evaluating the USAGE preferred alternatives,
  exclusively,  from the outset.

        Regulations governing DPAs under that Wetlands Protection Act
   (WPA)  at 310 CMR 10.26 lower the performance standards to which the
  project will be held for some resource  areas.
<~  of
6The DEIR states at page 3-27 that the bulkheading and filling

     [a]11 aquatic shoreline sites [will mean] that existing
     sub-tidal habitat is lost to fast land if the sites are
     filled  to capacity.    Due to  the permanent loss  of
   •  sub-tidal  habitat in  the  total fill  option  only  the
     partial fill option,  which  provide for the establishment
     of intertidal habitat, was selected as potentially
     practicable.

                           8

-------
Additionally,  the Wrentham site, with a capacity of almost 800,000
cy and an estimated cost well below the $72/cy threshold, warrants
further  consideration.   Siting issues  aside,   the  logistics of
dewatering  and  transporting  that volume  of  material for  the
immediate   project  may  prove  too  onerous  in  light of  other
alternatives.  However, a site with that potential capacity could
provide  a  cost-effective disposal site fpr two or three or more
future   maintenance   cycles:   As  volume  per  cycle  decreases,
dewatering  and transportation effort decreases and capital costs
are amortized  over a greater period.

Carrying a monofill  site forward is  important to  address  two
uncertainties:  First,.it is possible—unlikely,  but possible—that
testing  for a future  maintenance  or improvement  project  in the
metro-Boston area could identify contamination so egregious that
permitted monofill would be the only disposal alternative.  (See,
for example, the National Park Service site at the Charlestown Navy
Yard with PAH counts in the thousands of parts per million.)  More
likely  is  a   scenario  in which  the  regulations governing  the
disposal of dredged material are revised to more  narrowly proscribe
the  disposal  alternatives available; in  that  case,  having  the
groundwork already complete for an  upland site would be of enormous
benefit  to  a project proponent facing any kind  of timeline.

• The FEIR should carry forward the filling of piers and secondary
waterways  as  practicable alternatives.   If the  FEIR selects an
aquatic  site as  the  preferred alternative,  it should demonstrate
that the environmental impacts of such disposal are not greater
than those  associated with filling in-harbor areas.

•  The FEIR should therefore discuss  the  potential  impacts of
filling  piers  and  secondary  waterways   on  the Boston  Harbor
environment, under both a partial  and  total  build-out scenario.
The    analysis   should   include   impacts   to    the   tidal
prism/flushing/water  quality,  impacts to  fisheries/benthos,  and
impacts  to  land use (see next) .

• The  FEIR should address Designated Port  Area (DPA)/Chapter 91
issues with greater specificity in regard to these areas.  If, for
example, filling the  Little Mystic was to be seriously pursued, and
given  the  requirement under  the DPA regulations  that fast land
would be available only for waterdependent industrial uses, could
Massport benefit by having land available on which to expand Moran
terminal operations?   How do the proposed revisions  to  the DPA
     However, note that the permanent loss  of sub-tidal habitat in
a DPA is not necessarily precluded under the WPA regulations, ibid.
Further, benefits accrued from, or mitigation for impacts to, in-
harbor  fill may render these sites practicable from a regulatory
perspective.

-------
r
          regulations affect this alternative?
J
               ^FEIR should address the benefits and costs  of  the Wrentham
          monofill site  as  one element  of the  disposal  mix for  future
          maintenance needs.

          • The FEIR should assess the potential use of the silts as landfill
          closure and/or  daily cover material within the Commonwealth.  This
          should  include an evaluation of total potential capacity and the
          timing  of landfill  closures vis a vis the  BHNIP schedule.  The
          proponent  should   work  closely   with  the  MA  Department  of
          Environmental Protection to assess the utility of  upland disposal
          for this project.                   ,

          Practicable Sites

          MBDS

          The unconfined or   confined  disposal  of  sediments  that  fail
          biological testing at the MBDS is prohibited under the terms of the
          USEPA's site designation, which imposes the restriction that

                   Disposal shall be limited to dredged material which meets
                   the requirements of the [Marine Protection,  Research and
                   Sanctuaries  Act]   and  its  accompanying   regulations.
                   Disposal-and-capping [is] prohibited at the MBDS until
                   its efficacy can  be effectively demonstrated. [58 FR
                   42496]

          Additionally, as noted above,  the  Commonwealth concurred with the
          prohibition on  capping through the MCZM consistency determination
          on  the  final site designation.  Under the CZMA, modifying the  site
          designation to permit  a  demonstration project  or to remove the
          prohibition on  capping would constitute a federal activity subject
          to  federal  consistency.

          • The  FEIR  should discuss  the regulatory framework  that governs
          disposal of  contaminated sediments in MPRSA waters under the Ocean
          pumping Act,  with particular emphasis on 40 CFR 227.6(f) and (g) as
          it  applies  to this  site.

          • If the FEIR identifies this site as the preferred  alternative,
          MCZM will request that an  SEIR be developed that identifies and
          addresses USEPA and MCZM criteria  for a demonstration project.

          Boston  Lightship

          The Lightship site  is shallower than the MBDS  ("ISO  feet v.  "300
          feet)  but it has not been  demonstrated to MCZM that capping has
          been successfully carried out at these depths.   Anecdotal evidence
          suggests that the site is susceptible to winter storms which result
          in  the movement of  large  volumes  of surficial sediments.  [MWRA,

                               ' '  •       10

-------
pers. comm.]   The MA  Division of Marine Fisheries has stated that
the Lightship site is an  important fisheries resource.

While the Lightship is not currently permitted  as a  disposal site,""
it is a historical disposal site for dredged material, construction
debris,  industrial  material  and  low-level   radioactive  waste.
[USEPA,  ±990]    The  remedial effect  of  disposal  at  this  site
(capping,  in effect,  the existing sources of  contamination)  has
been discussed as a potential benefit that may balance the short-
term impact of disposal on the fisheries  resource.  In order to
make such a management decision, the agencies need a survey of the
Lightship  area that  is detailed to  the point  of  providing  the
number  and   contents  of  units  of   anthropogenic  waste,  e.g.,
canisters or  coffins,  per given area.  With that information some
general criteria  could be established: for example,  at 10 units per
acre the environmental benefits might outweigh  the costs, but at 4
units per acre they might not.                                  —

• ,The  FEIR should provide a bathymetric  survey of the Lightship
site at a level of detail sufficient to identify the location and
general nature of anthropogenic waste.

• MCZM will require the proponent to provide one year of baseline
data for the  Lightship site, to be evaluated in  a Draft SEIR (see
Attachment  1) .

•  If  the  FEIR  does  identify the  Lightship  as   the  preferred
alternative,  the  SEIR should address, in addition to the baseline
data, technical issues specific to capping at the. site.  On review
of  the FEIR  MCZM may, following  discussion  with  the  state  and
federal agencies, require that the SEIR incorporate a demonstration
project.

• The  FEIR should include data from the USAGE that substantiates
that the  USAGE has the technical proficiency  to cap material at
these depths.  Documentation of capping at shallower depths that is
applicable  to this site and this depth  is not accessible.   Peer
review  of   USAGE  data  will  assist   in the  definition  and
interpretation of "successful" capping.                        —

• The  FEIR should discuss the  regulatory framework that governs
disposal of contaminated sediments in MPRSA waters under the Ocean
Dumping Act, with particular emphasis on 40 CFR 227.6(f)  and  (g) as
it  applies  to this site.

• The FEIR should assess the potential for, or  conditions required
to  induce, catastrophic failure of the disposal site after project
completion.   Include  an  assessment  of projected  impacts  to the
local and regional environment.
                                11

-------
Borrow Pits  (Meisburger 2(7)

The prospective  borrow pits (#2 and #7) are located approximately
7 and 8 miles off Deer Island, respectively, roughly bracketing the
MWRA  outfall pipe  in 80 to 100  feet  of  water.    (Note  that the
borrow pits  do not  yet exist.  They have been identified as areas
that  potentially contain significant  and recoverable  volumes of
sand  and  gravel.)     Silty  material   overlying  sand  and  gravel
resources would be removed and either stockpiled or disposed at the
MBDS, the  sand  and gravel would be removed  and put to beneficial
use,  the  BHNIP silts  would be placed  in the pit and capped with
clay  and  sand.    On. completion  of the  project the  artificial
substrate would  resemble original conditions. The borrow pits are
characterized in the DEIR as having capacities of between 780,000
cy and 4,600,000 cy for #2  and 6,100,000+ cy for #7.

• MCZM will  require the proponent to provide one year of baseline
data for the Meisburger sites, to be evaluated in  a Draft SEIR (see
Attachment 1).

• The USAGE  has  done a fair amount of  conceptual work with borrow
pits  and  some field testing.   The FEIR should  collate existing
information  on  this disposal alternative  and discuss both borrow
pit technology in general and the literature's application to this
project in particular in greater technical detail.

• The FEIR  should  include a technical evaluation  of geotextile
encapsulation of dredged material prior to  disposal, as has been
recently evaluated  by the USAGE Waterways Experiment Station.

• If the  FEIR  does identify the borrow pits as  the preferred
alternative,  the SEIR should address technical issues specific to
borrow pit disposal.  On review of the FEIR MCZM may, following
discussion with the state and federal agencies,  require that the
SEIR  incorporate a  demonstration project.
                                                                •••••
• The FEIR  should  determine,  through physical   sampling  of the
proposed  sites,  first, whether . the areas  are  predominantly
characterized by a  sand or sand/gravel substrate;  and second, what'
the  areal and volumetric dimensions of the  proposed borrow pits
actually  are.

• Once those dimensions are established,  the FEIR should address
the impacts of the proposed borrow pit to the physical resources of
the area in which it will be located.  For example, will the borrow
pit encompass the total area  identified as containing recoverable
sand  and  gravel  resources?  What amount of  the  resource will be
rendered unavailable by siting a borrow pit in that resource?  What
will  be the  dimensions of an  exclusion zone around the borrow pit
itself?
                                12

-------
 ocean surface-
                    exclusion distance from pit?
 ocean bottom-
                             borrow pit
                      volume of resource lost?
 •  The FEIR should assess the potential for, or conditions required
 to induce, catastrophic failure of the disposal site after project
 completion.   Include an assessment of  projected impacts to  the
 local and regional environment.

 In-channel Trench and Cover

 Under _this alternative the tributary channels themselves serve as
 the disposal site.   The silts would be  dredged  from the channels
 and be stockpiled in reserve.  The underlying clay  would then be
 dredged deeper than required for navigation, and a portion of that
 material would be stockpiled.  The silts  would then be replaced in
 the depression and capped with the clay held  in reserve.  Trench
 and cover would provide approximately 60% of the capacity of  the
 current project and no capacity  for  future maintenance work.

 This alternative  is conceptually attractive  because it has  the"
 benefit of  localizing  impacts in the area already most  heavily
 affected by contamination, and of not transporting those impacts to
 another  area.    However,  MCZM  has serious  concerns  about  the
 practicability of this  alternative given  the logistics  it would
 entail.   It  appears to  MCZM that further  evaluation of  this
 alternative  relies   on  the answer  to  the question:  Given  the
 multiple opportunities for impacts (double handling the material,
 relying on  the close coordination of dredging  and disposal,   an
 operational  area  the footprint,  by  definition,  of the  working
 watersheet, the high potential for transport of sediments off-site
.given current speed  and the volumetric exchange  of  water  at each
 tidal  cycle)  are  the  sum of the  potential impacts  from  this
 disposal technique mitigated  by  the  location  in  which they occur?

 MCZM  does ^ not believe  that  this alternative  merits  further
 consideration as a disposal option for the  current project. It  may
 be appropriate to consider as one element of a  disposal mix  for
 future maintenance work.                                        	

 •  The FEIR should discuss this alternative in  greater detail  if it"
 is carried  forward  as  a  potential  site  for future  maintenance
 material.                                                      _
                                13

-------
Spectacle Island CAD

This alternative would entail the removal of between 600,000 cy and
1,450,000 cy of material from a shallow subtidal flat immediately
east of Spectacle Island.  The site is located in depths of -4 to
-15 feet mlw,  with average depths of -9 mlw.  In all other respects
it is similar to the borrow pit alternative discussed above.

MCZM has serious concerns about the viability of this alternative.
While the shallow water location does give it a decided advantage
in terms of accurately placing the dredged material and the cap, it
also .appears  to  combine the  worst aspects  of borrow pits and
capping  by its  susceptibility  to storm-wave  activity and the
resultant  heightened  potential  for  impacts  to  outer  harbor
resources.  In addition,  information provided by the MA Department
of Environmental Protection indicates that  the site may  not be
geologically suited to a major excavate-and-fill operation.

MCZM does not believe  that the  CAD alternative  merits  further
consideration as a disposal option for either the  current project
or for future maintenance work.                                  —

MCZM Preferred Alternatives

MCZM presents these  alternatives  as a  preliminary ranking of
alternatives  based on information  from  the pre~MEPA workgroups,
review of existing literature,  discussions with the proponent, and
review  of  the  DEIR.    MCZM's  preferred  alternatives as  here
identified  are  likely  to  be  influenced  in  degree,  if  not in
substance, by information developed by the FEIR.  (For example, if
information developed on the  cumulative environmental impacts of
filling  piers  and  secondary  waterways  indicates  unacceptable
impacts not compensated for by  benefits or mitigation, MCZM  would
recommend that these alternatives  be  dropped from  consideration.)
                                                                 ^^«
Based on our program plan and enforceable program policies, MCZM|s
preferred alternative for the disposal of contaminated sediments is
upland  disposal, because this  approach  minimizes  the impacts of
dredging  and  disposal on the resources of  the coastal zone to the
greatest degree possible.  MCZM's analysis  of the practicability of
this alternative will rely on information developed by, and for,
the MADEP Bureau of Solid Waste Management.  Please see MADEP's
comments   for guidance.    We recognize  that the  volume--and
concomitant expense—of material to be generated from the immediate
project and  from future  maintenance work may  preclude upland
disposal  for  at  least the  1,300,000 cy at immediate issue.      —
                                                                ^•••H
MCZM's  second preferred  alternative  is  a combination of  filled
piers  and fill of the Little Mystic  and/or  the Reserved Channel.
As  noted above,  we  request that  the proponents  investigate the
feasibility of these sites  and the  impacts  of their use on the
Boston  Harbor environment in  greater detail.  We recognize that

                                14

-------
cost,
                  *ay alS° be realistically precluded by logistics,
                  ironmental impacts *                            f |
 MCZM's third preferred alternative are the Meisburger borrow ^^
 #2 and  #7.    Borrow pit disposal potentially offers a  range  of
 management benefits.   Depths  at the sites are  shallow  enough  to
 allow for the accurate placement of material,  and deep  enough  to
 minimize the erosional potential of storm-wave currents; borrow pit
 configuration conceptually provides an effective physical means  of
 sequestering  both  the  dredged  material  and  the  contaminants
 therein; impacts to ambient resources are (relatively) temporary;
 and post-disposal  site conditions can  be designed  to  replicat4
 original conditions.   As  an  additional benefit,  the Meisburger
 sites potentially afford  the communities along the North and South
 shore  with   a   source  of  much   needed  material  for   shore
 enhancement/protection projects  currently under  design.  .  MCZM
 believes that the Meisburger sites potentially represent the  most
 practicable  alternative for disposal  of  sediments from the  BHNIP.
                                                                •IMBM

 .Innovative Technologies

 •  The FEIR should identify a practicable remedial technology  that!
 can be  implemented  as  at least a demonstration project.   A
 demonstration  of remedial disposal technology may be an appropriate
 element ^ of a mitigation  package, and  should  be included in  that
 discussion at  the appropriate time.  The USAGE and Massport  should
 work  closely  with Commonwealth agencies  to  identify  a funding
 mechanism to support this element of the BHNIP.


 .Dredging Management Plan

 As required by the MEPA scope,  the DEIR presents a management plan
 tor the  dredging and disposal of dredged  material.  Because the
 DEIR  cannot,  before a final disposal  site(s)  has been selected,
 address the technical relationships between dredging and disposal,
 the plan  as presented is  necessarily generic.

 Note: The management plan  may be more  appropriately incorporated in
 the SEIR, where it can be crafted to reflect the specific elements
 of site conditions  and design.  See Attachment 1,  #5 and #6.

 •  The management plan  in the  FEIR should  be  very specific,  and!
 should address, as appropriate to the site ultimately selected: 1}
the technical  and operational  relationships between the dredging '
 and the disposal site; 2)  a discussion  of the criteria by which to
determine  the  need  for interim  capping; 3) a detailed  calendar
 schedule that illustrates  how long it will take to accomplish given
tasks; 4) what resource protection windows will control operations
and how they will be met;  5) how the selected alternatives address
future maintenance needs, and any operational requirements that

                               15

-------
future use of a given site will impose  on use of that site for the
immediate project (sequential  use  of a borrow  pit,  over multiple
maintenance cycles, for example); 6) how disposal will be monitored
to ensure  the integrity of the disposal capability of  the  site,
with contingency plans sufficient  to  address unexpected problems
encountered  with  disposal (evidence   of  significant  volumes  of
material outside disposal  site boundaries,  for example).        —

• The  FEIR should address,  in consultation with the USEPA,  the
regulatory  status of the  disposal  site.   If an aquatic  site is
selected—and particularly  if it  is  selected  for the  express
purpose of accommodating all future maintenance material—will the
site be required to be formally designated as  an active disposal
site?  Will projects not related to the BHNIP  have access to the
site?
Monitoring Plan

A monitoring plan for the  disposal  site constitutes an integral
aspect  of  the project.

• The FEIR should identify a technical protocol  for monitoring the
disposal site(s). The FEIR should identify a monitoring committee
composed of representatives from the state and federal agencies and
user  groups to evaluate monitoring data and  advise the USAGE on
management i s sues.

•  The  FEIR should  identify the  source of funding  for ongoing
monitoring  and  remedial  actions at the  disposal site(s) ,  if
necessary.                                                    __J

The proposed project is subject to MCZM federal consistency review;
the issues identified above will be evaluated during that review.
For further information on this process,  please contact Jane W.
Mead, MCZM Project Review Coordinator,  at 617-727-9530 x.418.

MMB/DBB

'cc:  Patricia Scott, OCRM
      Peter Jackson, USAGE
      Cathy Demos, USAGE
      Karen Kirk-Adams, USAGE
      Janeen Hansen, Massport
      Norman Faramelli, Massport
      John Simpson, MADEP Waterways
      Steve Lipman, MADEP Commissioner's Office
      Judy Perry, DEP/DWPC
      Eugene Cavanaugh, DEM/Waterways
      Leigh Bridges, MADMF
      Brad  Chase, MADMF
      Chris Mantzeris, NMFS

                                 16

-------
Jon Kurland,  NMFS
Ed Woo, USEPA
Kymberlee Keckler,  USEPA
Phil Colorusso,  USEPA
Ed Reiner, USEPA
Vernon Lang,  US  Fish & Wildlife
Brad Barr, Stellwagen Bank National Marine Sanctuary
City of Boston Environmental Department
Towns of Chelsea. Charlestown, Nahant, Hull, Winthrop,  Itecre,
Lynn
Conservation  Law Foundation
Save the Harbor/Save the Bay
Cape Cod Commission
Diane Gould,  Massachusetts Bays Program
                          17

-------
                           Attachment 1

                 Baseline Data .Required for SEIR

• For coastal or  ocean  sites,  MCZM requires  that the proponent
provide one year of baseline data, to include:
1. Physical and geological oceanography
1
     -Currents, surface and bottom, both ambient and storm-induced;J
     -Hydrography, including water column characteristics;
     —Wave regime, particularly considering the potential for
      sediment reworking under storm conditions; and             j
     -Regional geology and sediment characteristics.

2. Chemical oceanography                                     "~   I

     —Chemical analysis of the sediments;
     -bioaccumulation analysis of resident species, e.gr.,
      polychaetes.

3. Biological environment

     -Community structure within the area to be affected
     -General discussion of planktonic community
     -Fish and other nektonic species
     -Coastal birds
     -Marine mammals and turtles
     —Rare or endangered species

4. Socioeconomic  information

     -Impacts to  fisheries
     -Impacts to  human health
     -Beneficial  use of existing resources, e.g.,  sand and gravel;
      remedial benefits of sequestering existing contaminants,
      e.g., canisters at the Lightship.

5. Dredging and disposal management information                 —

     -Technical and operational relationships between the dredging
      and disposal site;
     -Detailed calendar schedule that illustrates how long it will
      take to accomplish given tasks;
     -What resource protection windows will control operations and
      how they will be met;
     -How the selected alternatives address future maintenance
      needs, and  any operational requirements that future use of a
      given site  will impose on that site for the  immediate
                                18

-------
      project, e.g., sequential use of a borrow pit, over multiple
      maintenance cycles;
     -Monitoring and contingency planning for disposal operations.7

6. Disposal site monitoring plan
     -Transport of contaminants off site;
     -Transport of material off site;
     -Stability of cap or mound.
S6-39
      The Draft Supplemental Environmental Impact Statement (DSEIS)
for the Use of Subaqueous Borrow Pits... [in] New York - New Jersey,
USAGE NYD, 1988, draws on the work of Irish and Bokuniewicz (1988)
and Bokuniewicz et.  al.  (1986) to provide management guidelines for
borrow pit disposal.  See Attachment 2 for an example of a disposal
management  process  that  integrates  disposal   monitoring  and
contingency planning.

While not directly applicable, this could also serve as a model for
monitoring/management of a capping operation.

                                19

-------
                               Attachment 2
             tit*
   jfera of  th«
   •deposit  froa
   Jt.-.e previous
 -;i snallovast
 • t«r b« within
3 f»«t of as*i*nt
«•• floor or
       5 f**t
       ri»?
                                                  !•  aouad within
                                                 ••• floor or witbin
                                                 5
  jcritica.1 VOIUM
                                      op,r«tion
                                 divert te
  H*» 100.OOO
  eenaition *urv«y?
                          ««• bar?*
                          Position?
su«p«nd
Operations
or Dlv«rt te
Mud Bump

-------
                           Attachment 3

                       HCZM Program Policies


Regulatory  Policies

Policy .1.
     Protect   ecologically  significant  resources  areas   (salt
     marshes,  shellfish beds,  dunes, beaches barrier beaches, and
     salt ponds) for their contributions to marine.productivity and
     value  as  natural habitats and storm buffers.

Policy 2.
     Protect   complexes  of  marine,  resource  areas  of  unique
     productivity    (Areas  of   Preservation    of    Restoration
     (APRs)/Areas   of Critical  Environmental   Concern  (ACECs));
     ensure that activities in or impacting such complexes are
     designed and carried out to minimize adverse effects on marine
     productivity,   habitat values,  water  quality,  and  storm
     buffering of the entire complex.


Policy 3.
     Support attainment of the  national water quality goals for all
     waters of the coastal zone through  coordination  with existing
     water  quality  planning and management agencies.   Ensure that
     all activities endorsed by CZM in its policies are consistent
     with federal and state effluent  limitations and  water quality
     standards.

Policy 4.
     Condition construction in water bodies and contiguous land
     areas  to minimize  interference  with water circulation and
     sediment  transport and to preserve water  quality and marine
     productivity.   Approve permits  for flood  or erosion control
     projects  only  when it has been determined that  there will be
     no significant adverse effects on the project site  or adjacent
     or downcoast areas.

Policy 5.
     Ensure that dredging and disposal of dredged material minimize
     adverse effects on water  quality, physical processes, marine
     productivity and public health.

Policy 6.
     Accommodate off-shore sand and  gravel  mining needs in areas
     and in ways that will not adversely affect marine  resources
     and navigation.

Policy 7.
     Encourage the location of  maritime commerce and development in
     segments  of  urban  waterfronts  designated  as port  areas.
     Within these  areas,  prevent the exclusion-  of  maritime-
     dependent  industrial  uses that require  the use  of  lands
     subject to tidelands licenses.

-------
Policy 8.
     For coastally-dependent energy facilities,  consider siting in
     alternative  coastal location.   For non-coastally-dependent
     energy  facilities,  consider siting in areas  outside of the
     coastal zones.  Weigh the environmental and safety impacts of
     locating proposed energy  facilities at alternative sites.

Policy 9(a).
     Accommodate   exploration,  development   and   production  of
     offshore oil and gas resources while minimising impacts on the
     marine environment,  especially on fisheries, water quality and
     wildlife,  and on the recreational values  of  the coast, and
     minimize  conflicts  with  other maritime  dependent  uses  of
     coastal  waters  and  lands.   Encourage  maritime-dependent
     facilities serving  supply,  support or transfer functions to
     locate in existing  developed ports.

Policy 9(b).
     Evaluate indigenous or alternative sources of energy (coal,
     wind, solar and tidal power) and offshore mining to minimize
     adverse  impacts  .on the marine environment,  especially with
     respect to fisheries, water quality, and wildlife, and on the
     recreational values of the  coast.

Policy 10.
     All development must conform to existing applicable state and
     federal requirements governing subsurface waster discharges,
     sources of air and  water pollution and protection of inland
     wetlands.

Policy 11.
     Protect designated scenic rivers in the coastal zone.   Support
     designation of areas for preservation  or restoration as "sign
     free areas."

Policy 12.
     Review  proposed  developments  in  or  near  designated  or
     registered historic districts or sites to  ensure that federal,
     state, and private  actions requiring  a state permit  respect
     their  preservation  intent and  minimize  potential   adverse
     impacts.

Policy 13.
     Review developments proposed near existing public recreation
     sites in order to minimize  their adverse impacts.
NQn-ReenJlatory Policies

Policy 14.
     Encourage  and  assist   commercial  fisheries  research  and
     development, restoration and management of fishery resources,
     development  of  extensive  and  intensive  aquaculture,  and

-------
     enhancement of anadromous fisheries, initiated at local, state
     and federal levels.

Policy  15.
     Ensure that state and federally funded public works projects
     proposed for location within the 100 year coastal  flood plan
     will:
           (a)  not exacerbate  existing hazards  or damage natural
          buffers?
           (b)  be reasonable safe  from flood  and erosion related
          damage; and
           (c)  not promote growth and development in damage prone or
          buffer areas, especially in undeveloped areas of APRs.

Policy  16.
     Encourage  acquisition of  undeveloped  hazard  prone  areas
     conservation  or  recreation  use,  and  provide  technical
     assistance for hazard area zoning and mitigation of erosion
     problems.

Policy  17.
     Provide  funding for  protection  from  tidal  flooding  and
     erosion,  emphasizing the use of non-structural measures where
     feasible.

Policy  18.                            .
     Encourage, through technical assistance and review of publicly
     funded development, compatibility of proposed development with
     local  community  character and scenic resources.

Policy  19.
     Promote  the  widest  possible public  benefit from  channel
     dredging, ensuring that designated ports and developed harbors
     are  given highest priority in the allocation of federal and
     state dredging funds.   Ensure  that this dredging is consistent
     with marine environmental policies.

Policy  20.
     Encourage,   through   technical  and  financial  assistance,
   •  expansion of water-dependent uses in designated  ports  and
     developed harbors,  redevelopment of urban  waterfronts,  and
     expansion of visual access.

Policy  21.
     Improve public access to coastal recreation facilities,  and
     alleviate  auto  traffic  and  parking  problems  through
     improvements in public transportation.  Link existing coastal
     recreation sites to each other  or to nearby coastal  inland
     facilities via trails  for bicyclists, hikers and equestrians
     and  via rivers for boaters.

Policy  22.
     Increase capacity of existing  recreation areas by facilitating
     multiple use and  by  improving  management,  maintenance  and

-------
     public support facilities.  Resolve conflicting uses whenever
     possible  through  improved  management  rather than  through
     exclusion of uses.

Policy 23.
     Provide  technical  assistance  to  developers   of  private
     recreational facilities and sties that increase public access
     to the shoreline.

Policy 24.
     Expand  existing  recreational,  facilities  and  acquire  and
     develop new public areas for coastal recreational activities.
     Give  highest priority to  expansion or new acquisitions in
     regions  of  high need  or  where site  availability  is  now
     limited.   Assure  that both  transportation  access and  the
     recreational  facilities  are  compatible  with  social  and
     environmental characteristics of surrounding communities.

Policy 25.
     Encourage  energy conservation  and the  use  of  alternative
     sources such  as solar and wind power in order to  assist in
     meeting the energy needs of the Commonwealth.

Policy 26.
     Ensure  that state and  federally funded transportation  and
     wastewater projects primarily serve existing developed areas,
     assigning highest priority to projects which meet the needs of
     urban community development centers.    j

Policy 27.
     Encourage  the  revitalization and  enhancement  of  existing
     development  centers  in  the coastal zone  through  technical
     assistance  and  federal  and  state financial  support  for
     residential, commercial and industrial development.

-------
S6-1

       Future maintenance dredging heeds were considered in the evaluation of
potential disposal sites.
S6-2

       The Army Corps is continuing testing of the suitability of geotextile bags for
disposal of contaminated sediments.
S6-3

       Additional data on biological resources at the potential aquatic disposal sites
were collected in fall 1994 and incorporated into the revised disposal site alternatives
analysis. This analysis was restructured to separate the environmental impacts and
practicability components. Section 4 of the FEIR/S  provides a logical comparison of
the potential disposal sites that will enable the reviewer to identify the least environ-
mentally damaging practicable alternative readily.
S6-4
use.
       Reevaluation of potential disposal sites includes the issue of repeated future
S6-5

       We apologize for the unintentionally misleading statement regarding MCZM's
jurisdiction in the DEIR/S and we fully understand that MCZM concurrence is
required for both the dredging and aquatic disposal of sediments from this project.  We
also understand that activities in terrestrial areas within the coastal zone (e.g. dewater-
ing, stockpiling, disposal) would also be subject to MCZM's review.
S6-6

       The DEIR/S team acknowledges CZM's response that the Boston blue clay and
rock material are suitable for disposal at the Massachusetts Bay Disposal Site (MBDS).
As discussed hi the DEIR/S, parent material not utilized for beneficial purposes would
be disposed at the MBDS.

       The DEIR/S team acknowledges the difference of opinion between EPA and
the Corps on the suitability of disposal of silt material from certain areas (Reserved
Channel (Conley, Army Base and Federal Channel) and Chelsea River (Gulf Oil) for

                                       36

-------
disposal at MBDS.  This difference of opinion is beyond the scope of this document
and as such cannot be resolved at this level.  However, the DEIR does evaluate the
option of disposal of the above described sediments at sites other than MBDS; this
ensures there will be suitable location for disposal of all project material.
S6-7

       The disposal site alternatives analysis has been restructured to separate environ-
mental and practicability issues (Section 4). This presentation more clearly distin-
guishes the application of the selection criteria than hi the DEIR/S.
S6-8

       The revised disposal site alternatives analysis eliminates the 200,000 cy
minimum capacity. Sites are compared on numerous environmental and practicability
issues.

       The state regulations regarding Designated Port Areas and the "no net loss"
policy of the 404(b)(l) guidelines are hi conflict with each other when applied to the
fastland scenario for the shoreline sites. The benefits of capping existing contaminated
sediments within the disposal sites would be accrued by either the partial-fill or the
fastland scenario.  The partial-fill scenario would avoid the permanent loss of aquatic
habitat although it could be more susceptible to structural failure than the fastland
scenario.  It was determined that the envkonmental impacts associated with the
fastland scenario would be greater than with the partial fill scenario, when the individ-
ual sites  are evaluated.  The unit costs would be lower and the capacity higher for the
fastland scenario, thereby making the fastland scenario more practicable.  Because
federal regulations focus on selection of the least environmentally damaging alterna-
tive, the  project believes that the fastland scenario would not be permittable at this
level since other alternatives are available.
S6-9

       The partial-fill and fastland scenarios were thoroughly analyzed in the FEIR/S
disposal site alternatives analysis(Section 4), including evaluation of the impacts listed
in this comment. The regulations governing Designated Port Areas were reviewed hi
regard to this application. A severe limitation on the suitability of the fastland
scenario is the fact that these areas would not be available as useable land for years
following their closure as disposal sites unless they were decked .over, with appropriate
structural  support for the proposed use. This would add substantial costs to the project
(or future site user) that would be unrealistic without considering other options for
increasing port facilities or making existing layouts more efficient.
                                        37

-------
       Clean Water Act 404 guidelines require avoidance of aquatic impacts if other
practicable alternatives are available.
S6-10
       See response to comment S6-8.
S6-11
       The chemical and physical characteristics of the dredged material samples have
been compared to the DEP requirements for soil reuse at lined landfills (Bureau of
Waste Prevention Interim Policy #BWP-94-037 - Reuse and Disposal of Contaminated
Soils at Landfills) and for capping materials (310CMR  19.000 Solid Waste Manage-
ment Regulations and Landfill Technical Guidance Manual). While silt samples from
some  of the dredge sites may meet the chemical criteria for reuse at landfills, other
samples exceed the allowable limits for PCBs, Arsenic, and/or  TPH and dewatering
sediments to meet the standard of no free draining liquid is currently impracticable.
Clay is better suited to beneficial uses as landfill capping material, and this option is
discussed hi the FEIR/S.  Several planned demonstration projects may provide a wider
variety of disposal options for future maintenance dredging.  These are discussed hi
the FEIR/S.
S6-12
       The MBDS is not considered for disposal of BHNIP silts hi the FEIR/S.
S6-13

       The MBDS has not been identified as the preferred alternative for disposal of
silt from the BHNIP.  However, it is considered to be the preferred alternative for
disposal of parent material that is not used beneficially.
S6-14

       The USEPA has been funding efforts to locate and characterize the previously
disposed materials at the Boston Lightship.  Biological investigations in the fall of
1994 by the BHNIP team indicated that this site supports a diverse and abundant fauna
hi its current conditions.  The disposal site alternatives analysis concluded that this site
is not among the least environmentally damaging alternatives.
                                       38

-------
S6-15
       See response to comment S6-14.
S6-16
       See response to Comment S6-14.
S6-17
       See response to Comment S6-14.
S6-18
       The likelihood and effects of failure of the Boston Lightship site (and all other
aquatic sites considered for this project) has been evaluated in Section 4 and Attach-
ment 1 oftheFEIR/S.
S6-19

       Biological investigations were carried out at the Meisburger sites during fall of
1994.  Results from these surveys were included in the reevaluation of the suitability
of the potential aquatic disposal sites for disposal of silts from the BHNIP.
S6-20

       The Corps of Engineers, in particular the New York Division, has studies and
experience with borrow pit engineering.  This infbrmation would be used if a borrow
pit site were to be selected for disposal of dredged material.
S6-21

       The current status of the investigations on the suitability of geotextile bags for
disposal of silts sediments is presented in the FEIR/S.
S6-22

       The reevaluation of the alternative aquatic disposal sites concluded that the
Meisburger sites were not among the least environmentally damaging alternatives.
                                       39

-------
       Borrow pits may be used as disposal site for future maintenance disposal sites.
If these sites are selected, then coordination with appropriate agencies will be initiated.
S6-23

       The physical character of the surficial material at the Meisburger sites was
characterized in the fall of 1994 using sediment profile imagery.  Because of the
potential severity of the environmental consequences  of using these sites, no addition
effort  has been made to quantify the recoverable sand and gravel resources.
S6-24

       The likelihood and effects of failure of the Meisburger disposal sites has been
discussed in Section 4 and Attachment 1 of the FEIR/S.
S6-25

       The MCZM recommendation not to pursue the In-channel Trench and Cover
alternative is acknowledged. The concerns expressed by MCZM on impacts during
sediment handling and disposal have been examined in more detail for the FEIR/S.
Particular emphasis has been placed on evaluating the potential environmental risks of
the various activities that will occur (i.e. contaminant impacts during the time of
dredging, material handling, rehandling and subsequent disposal and covering opera-
tions).  The estimated impacts are discussed in detail in Section 4.0 and Attachment 1
of the FEIR/S.

       The BHNIP team believes that the potential shortcomings of the  in-channel
disposal alternative have been thoroughly documented in the FEIR/S.  Although this
alternative would require extensive coordination in order to minimize environmental
damage, is can be accomplished using proven techniques, as is  indicated in the Dredge
Management Plan (Section 5).  Several of the concerns that MCZM cites in this
comment are of much lower magnitude than this comment suggests.  The silts would
not be  double handled; storage (in barges) would be necessary for a short period at the
beginning of the project until the first cells are constructed.  After that, dredged silts
would  generally be disposed within a day of being dredged. It would be possible to
isolate  the disposal area using silt curtains or a pneumatic barrier, therefore, the risk of
transport of sediments from the site is no greater than any other tidally-driven aquatic
site.  The reference to tidal exchange is unclear because all of the potential aquatic
sites would be affected by tidal currents.  These concerns are addressed  in various
sections of the FEIR/S.

       It is felt that this disposal alternative has a great potential for implementation
with minimal short and longterm impacts. Therefore, this alternative is being recom-
mended for the BHNIP.
                                       40      2.H

-------
S6-26
       See response to Comment S6-25.
S6-27
       The suitability of the Spectacle Island CAD site was reevaluated in the FEIR/S.
It was concluded that, due to its rich biological conditions and exposed physical
condition, this site was not among the least environmentally damaging alternatives.
S6-28

       The BHNIP team concurs that upland disposal of dredged materials could
rninirnize environmental consequences to aquatic resources and the coastal zone.
Several land-based sites were identified in the FEIR/S that could be developed for this
purpose. However, it is difficult to compare and contrast environmental impacts of
dissimilar environments (i.e., aquatic versus terrestrial).  Therefore, differentiating
between these types of sites must also rely on practicability considerations, including
the need for dewatering and double handling. Both upland and aquatic sites were
considered as among the least environmentally damaging alternatives.
S6-29

       The partial fill and fastland scenarios for the shoreline sites have been reevalu-
ated in the FEIR/S.
S6-30

       The suitability of the Meisburger sites has been reevaluated hi the disposal site
alternatives analysis hi the FEIR/S (Section 4).
S6-31

       While significant questions need to be answered, innovative technologies hold
promise, especially for highly contaminated sediments, for stabilization of contami-
nants, and for volume reduction of dredged materials.  Thus, potentially practicable
treatment technologies should be pursued further hi the FEIR and the following
recommendation from the MCZM should be advanced,  "The FEIR should identify a
practicable remedial technology that can be implemented as at least a demonstration
project.  The USACOE and Massport should work closely with Commonwealth
agencies to identify a funding mechanism to support this element of the BHNIP".
                                       41

-------
       In response to several of the comments on the DEIR, MASSPORT and the
Army Corps of Engineers developed a survey questionnaire to send| to treatment
technology and disposal companies which could Be contracted to handle, treat and or
dispose of the contaminated dredged materials.  The survey utilized1 a format originally
developed by the USEPA and the Army Corps of Engineers as part| of the Assessment
and Remediation of Contaminated Sediments (ARCS) Program (Avisritt 1990). The
survey included questions on the effectiveness, implementahility and the cost of the
technology for the treatment or disposal of contaminated dredged materials.
                                                              i
                                                              !
       Results are presented in Appendix D and Section 3.0 of the iFEIR/S.
S6-32
       The Dredging Management Plan is presented in Section 5.0 |of the FEIR/S.
       The FEIR/S includes as much specific information, relevant jto the Dredging
Management Plan and specific aspects of managing the project, as possible. The
dredging and disposal inter-relationship is discussed in Sections 5.2 and 5.3. No
discussion of interim capping is presented or anticipated. Capping qf the disposed silts
will be performed after each cell is filled with silt. The FEIR/S presents a proposed
project schedule in Section 5.2.3.3. Dredging and blasting operations will be restricted
as noted in Section 5.2.1.5. the capacity of the in-channel disposal cells will likely be
fully utilized by the proposed activities. It is not anticipated that future maintenance
dredging activities will be able to utilize these disposal cells. Monitoring issues are
described in Section 5.2.2.1.                                    ;
S6-33                                                         i
                                                              i
                                                              I
       All sites inside the territorial sea baseline are evaluated under Section 404 of
the Clean Water Act.  These sites are not required to be designated^ by U.S. EPA.
Other project which may wish to use the site would have to do an independent
evaluation.                                                    !
S6-34                                                        i

       The FEIR/S dredged management plan establishes the basis for a technical
protocol for monitoring the disposal site(s) that will be utilized for the BHNIP. The
actual monitoring plan is expected to become fully developed duririg the permit
application processes in cooperation with the regulatory agencies.
                                                              :
       The Corps' DAMOS program provides a majority of the funding for monitor-
ing open water dredged material disposal sites. Remedial actions wbuld generally fall
under the responsible party.                                    '
                                       42
2/3

-------
S6-35

       Physical oceanographic issues of all aquatic disposal sites are discussed in
Section 4.0, Attachment 1 and Appendix G of the FEIR/S.
S6-36
1.
       Chemical data on the sediments are presented, where available, hi Attachment
S6-37

       Biological characteristics of the sites are discussed hi Section 4.0, Attachment 1
and Appendix E of the FEIR/S.
S6-38

       Socioeconomic impacts, were considered hi evaluating potential disposal sites
(Section 4.0; Attachment 1).
S6-39
       See Section 5.0 of the FEIR/S.
                                       43

-------
                                         of
jl/lalvne

     tt SPaltvnolaM 
-------
scenario, the actual cost of disposal  at the Mass Bay Disposal Site
could be  far  greater than  other  alternatives. The contamination of
and loss of a valuable food source  for the Commonwealth has an     __
inestimable cost.
                                                                    ••^•^
It is also our opinion  that the process of capping the dredge material
is basically ineffectual and unproved. The process itself may  cause
additional  re-suspension  of dredge  material  toxins.  In  water  disposal
and capping tests within Boston Harbor  have already proven to  be
dismal  failures.                                                     —

This Commission has  as  its primary responsibility  the  regulatory
authority  to  protect and  enhance the all the finfish and shellfish
resources  of the Commonwealth. In our opinion  the use  of any
Massachusetts at  sea  disposal  site  for the contaminated  BHNIP
dredge  materials  does  not adequately protect 'the long  term  health  of
our  already  over  stressed resources.

We  strongly urge you to  investigate other potential disposal  methods.
The risk  of negatively impacting our valuable marine resources is too
great to use any  at sea disposal site.
      rely,
 Colin M. Cunningh
 Chairman

 cc: Senator John Kerry
     Senator Edward Kennedy
     Congressman Gerry Studds
      Congressman Peter Torkildsen
    Mr. John DeVillars, EPA

-------
S7-1

       The disposal site alternatives analysis has been restructured in the FEIR/S so
that environmental and practicability issues are more clearly distinguishable (Section
4).  Potential for biological exposure to contaminants was one of the criteria used in
this analysis.  The conclusion of this analysis is that the in-channel and partial-fill
shoreline scenarios are the least environmentally damaging aquatic alternatives. No
sites in Massachusetts Bay are being proposed for disposal of BHNIP silts. In regard
to the last  sentence in this comment, the estimate for material loss is based on
historical records of disposal operations and is accepted as accurate by the industry.
S7-2

       The MBDS is not being considered for the disposal of sediments found to be
unsuitable for unconfmed open water disposal through chemical, physical or biological
testing.
S7-3
       There have not been any dredged material disposal and capping hi Boston
Harbor.
                                         44

-------

-------
LOCAL AGENCIES AND OFFICES
     COMMENTS AND RESPONSES

-------
                                                                        	I	
                                                                        	I'll"
                    	            Ill II
III    I    I   II     111            111
                                  (11
                                                                         i IK

                                                                        (   111

-------
    Thomas M. Menino, Mayor

  Mr Charles P. Buckley
  Vice President, Engineering
  Boston Gas Company  .
  201 Kivermoor Street
  West Roxbury, Massachusetts 02132
                                                   February 15, 1994
  Dear Mr. Buckley:            •

        RE:   NEW CHELSEA STRKET BRIDGE OVER CHELSEA CRF.FK"

        Over a number of years, discussions have taken place with government agencies, utility
  companies and  abutters concerning the eventual replacement of the Chelsea St. Bridge and
  proposed dredging of Chelsea Creek.  Since one of the key utilities which could be impacted is
  the gas line under Chelsea Creek, this letter is intended to provide you with current information
  on the project.

        In 1992, the  U.S. Coast Guard issued an Order To Alter the Chelsea St. bridge to the
  City ^of Boston to correct an unreasonable obstruction to navigation.  The City was directed to
 provide a moveable span  with an unobstructed horizontal clearance of 380 feet which is
 obviously predicated on a proposed widening of the present 95 foot Chelsea Creek channel. In
 early  1993,  the City requested  Qualifications for design services from engineering firms and
 short-listed three firms for further consideration pending funding availability.  In late 1993, the
 U.S. Coast Guard notified the City mat funding authorization for design was approved and the
 City is currently accepting proposals from the previously short-listed engineering firms. It is
 expected that design  of the new Chelsea St. facility will-be underway in 1994.

        Should you have any .questions on the above information or have any issues which you
 feel need to be addressed during the bridge design phase, please can Peter'Scarpignato  of my
 staff at 625-4968. Thank you for your cooperation.
                                                                                               L1-1
                                                 sry Truly Yours,
JFC/PS/jjf
                                              JOSEPJE): F. CASAZzA M
                                              Commissioner of Public Works
                                                 y
:3S3
        PUBLIC WORKS DEPARTMENT / Boston City Hall / City Hall Plaza 02201
        Joseph F. Casazza, Commissioner, 635-4900
        Robert P. Mehecan. Executive Secretary, 635-4S01        *Oy Q
        FAX 635-7499                     ''              C^l  7

-------
Ll-1

       Since February 15, 1994, the Corps and Massport have coordinated project
activities with all involved utility owners and with the City of Boston and the U.S.
Coast Guard on the proposed replacement of the Chelsea Street Bridge.

-------
                                                            JUN 1 6 1334
Boston
Redevelopment
Authority

Thomas M. Menino, Mayo-
Clarence J. Jones, Chairman
Man'sa Logo, Doctor

Secretary Trudy Coxe
Executive  Office of
 Environmental Affairs
MEPA Unit
100 Cambridge Street
Boston, MA 02202

Colonel Brink P. Miller
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham,  MA 02254

Dear Secretary Coxe and Colonel Miller:

Re:  Boston Harbor,  Massachusetts Navigation Improvement
     and Berth Dredging Project fEOEA #8695)	

Pursuant to regulations implementing the Massachusetts Environmental Policy Act
(301 CMR 11.00) and the National Environmental Policy Act (42 USC 4321 et seg,),
the Boston Redevelopment Authority (BRA) has reviewed the Draft Environmental
Impact Report/Statement for the above-referenced project and would like to submit the
following comments.

The proposed Boston Harbor Navigation Improvement and Berth Dredging Project
encompasses the deepening of the tributary channels (Reserved Channel, Mystic
River Channel, and Chelsea Creek Channel) and two areas in the Main Ship Channel
(Inner Confluence and the mouth of the Reserved Channel) to provide sufficient ship
maneuvering area for the deepened channels and the dredging of associated berthing
areas along these channels.  The channels will be deepened to  -40 ft. MLW (except
Chelsea Creek, to -38 ft. MLW) to allow greater use of the hitherto underutilized
Entrance Channel and Main Ship Channel and to accommodate the newer generation
of deeper draft ships. The project will be carried out by the U.S. Army Corps of
Engineers and by Massport, the local sponsor of the project. Approximately 1.3
million cubic yards (cy) of silt, 2 million cy of parent  material (primarily Boston Blue
Clay), and 130,000 cy of rock will be removed.
One City Hall Square
Boston. MA 02201-1007
Tel (617)722-4300
Fax (617) 367-5916


Eqxol Opportunity/
A?>rrr.attve Azticr. Emplsye.-
Equci Housing Opportunity

-------
Disposal of the underlying parent material is proposed at the Massachusetts Bay
Disposal Site.  For the overtopping, contaminated sift material, several disposal
alternatives are identified, all of which involve aquatic sites within Boston Harbor or
Massachusetts Bay, including in-channel locations.  During the course of the study, a
considerable number of additional disposal sites, both land-based and aquatic, were
evaluated, but most were eliminated from consideration for environmental, cost, or
other reasons.

Overview

The proposed navigation improvement and dredging project is essential in order to
maintain the economic viability of Boston Harbor.  The greatest challenge of this
project is the proper disposal of the over one million cubic yards of silt which is
substantially contaminated with high levels of heavy metals, PCBs, and PAHs, thus
precluding unconfined ocean disposal, the traditional approach for the disposal of
dredge spoils. Tests undertaken during the preparation  of this Draft E1R/EIS to
characterize the extent of contamination have revealed levels higher than those known
to have an adverse effect on marine organisms. Therefore, the application of proper
dredging techniques as well as the appropriate disposal of these  polluted sediments is
vital to ensure the protection of the harbor's marine resources and the preservation of
the improving quality of the harbor's waters.

With respect to the extent of the proposed  navigation improvements,  it would appear  ~|
that the recommendations of the Shiphandling Simulation Study (or at least most of
them) have been incorporated into the project (one example is the expansion of the
-40 foot MLW dredging in the Main Ship Channel just south of the Inner Confluence).
This should be more specifically confirmed in the  Final E1R/E1S.

Preferred Disposal Options

The-six preferred practicable alternatives for the disposal of the contaminated silts
include the Massachusetts Bay Disposal Site (with capping), Boston Lightship (also
with  capping), Meisburger 2 and 7, Spectacle Island CAD, and capping in-place in
trenches within the tributary channels to be dredged.

Currently, the disposal of contaminated dredged material, with or without capping, is
prohibited of the Massachusetts Bay Disposal Site (MBDS), until such time as capping
can be shown to the effective. In spite of the fact that the Corps appears to believe
that capping at the MBDS can be successful, too many  uncertainties remain, including
the feasibility of capping at the great depth of the MBDS. Another important
consideration is the proximity of the MBDS to the Steliwagen  Bank National Marine
Sanctuary, which is visited  by numerous endangered and threatened marine species.
Therefore, until capping can be shown definitely to be effective, we are opposed to
any disposal of unsuitable silt material at the MBDS.
 SLTR/132/061594/2

-------
Similarly, we are opposed at this time to the dumping of contaminated sediments at
the Boston Lightship site, even with capping. The waters around this site are heavily
used by commercial fishermen, and dumping activities could severely impact
commercial fishing activities which already are suffering  major economic pressures.
Further, radioactive wastes previously were disposed of  in the area, and the -impact of
dumping on these wastes is not known. Consequently, we do not feel that Boston
Lightship would be an appropriate site for disposal.

Due to interpretation differences (Appendix G, pp G-2-G-3), the Corps believes that
the silt material from a number of berthing areas to be suitable for unconfined open
water disposal, whereas the EPA disagrees.  To be conservative, the EPA
determination should be followed and none of the silt material should be disposed of
at the MBDS or at Boston Lightship.
                                                                              ••
We do believe that the best and most environmentally-beneficial option of the
identified preferred alternatives would be in-channel disposal at the dredging sites.
This would allow the sediment essentially to remain where it is found, but be capped
by the underlying parent material.  With this option, the impacts of dredging and
disposal would be contained at the dredging site, and no impacts would need to occur
at one or more off-site locations. Extra care would need to be taken to minimize to
the maximum extent possible  turbidity and the dispersion of sediment, since most of
the dredging and disposal would take place at the same location.  We recognize that
in-channel disposal would accommodate only a little over half the 1.3 million cubic
yards of silt material requiring disposal. For the residual, we recommend disposal at
either Meisburger 2 or Meisburger 7, with capping with clean material.

We further recommend that whenever possible, and when not required for capping
purposes, the  project  proponents use the clean dredged materials for beneficial reuse
(e.g.. landfill closure) rather than disposing them at the Massachusetts Bay Disposal
Site.

New Technologies

We also encourage the investigation of new technologies for the remediation of
contaminated sediments. Studies by the EPA and the Corps of Engineers in the
Great Lakes region and elsewhere have demonstrated the technical effectiveness of
some new technologies,  some of which may be applicable to the Boston Harbor
sediments. The feasibility of  using any existing or new technologies developed
abroad, in Europe or Asia, also should be explored.  While the cost of treatment
technologies may be higher than the selected disposal alternatives, they are
comparable with some of the shoreline disposal options considered by Massport/Corps
to be potentially practicable.  Future costs could be considerably less as the
technologies are further developed.  Their applicability to future maintenance dredging
needs, therefore, should be kept open for consideration and possible implementation. _
 SLTR/132/061594/3

-------
  Lona-Term Maintenance Dredging

  In addition to addressing the disposal needs of the navigation improvement and berth
  dredging project, the DEIR/DEIS also addressed the disposition of future maintenance
  material from the deepened channels over a 50-year project life. It is estimated that
  4.4 million cy of material would be dredged and would consist primarily of silt.  For
  purposes of the disposal alternatives analyses, it was assumed that the material could
  contain elevated levels of contaminants and thus would require disposition in a
  confined site.  For the disposal of the maintenance dredging material, the project
  proponents determined that a number of additional sites (in addition to the six
  preferred alternatives) would be potentially practicable alternatives, including several
  shoreline sites in Chariestown and South Boston and lined landfills. Treatment
  technologies also were considered feasible.

  The shoreline sites include the Amstar, Little Mystic Channel, Mystic Piers, and
   Revere Sugar sites in Chariestown and the Reserved Channel (on the inner side of
  the Summer Street Bridge) in South Boston. The sites would be either filled (with
   capping) to equal the elevation of the adjacent land or be converted into a subtidal salt
   marsh area. While these sites may be appropriate for consideration as disposal
   areas, we strongly feel that only clean sediments should be  deposited at these sites.
   Because of the proximity of several of the sites to residential and other sensitive uses,
   as well as legitimate neighborhood concerns and perceptions, we would be opposed
   to the disposal of any contaminated sediments at these locations, even with capping.

   Although the environmental impacts of disposal at these shoreline  sites are evaluated
   in this DEIR/DEIS,  actual disposal at one or more of these sites will require several
   permit reviews, including Chapter 91 Waterways License, CZM consistency review,
   and an Order of Conditions from the Boston Conservation Commission, among others.
   Notwithstanding, we would recommend that when a decision is made in the future to
   use a particular site (or sites) for disposal, a Notice of Project Change be filed with the
   MEPA Office (and  any similar notification be filed by the Corps) to determine whether,
   in the light of any changes in  environmental conditions or other factors, any further
   environmental review would be necessary.

   With regard to specific sites under consideration, we note that in the discussion of the
   Little Mystic Channel (pp 3-41 ff and Attachment 1,  pp A1-51ff) there is no specific
   mention  of the several sensitive receptors adjacent to the proposed disposal site,
   including the Charles Newtowne public housing project, a City of Boston playground,
   and the Chariestown High School recreational field.  (The proposed future use of this
   site for the disposal of possibly  contaminated sediments also  raises the issue  of
   environmental equity, since a low-income public housing development is located
   adjacent to the proposed disposal area.)
    SLTR/132/061594/4
s"*»*

-------
Public Participation

We also feel that it is extremely important, and essential, that prior to the selection
and use of any shoreline site, there be adequate notification to and review with the
affected community.  The Corps and Massport must ensure that there be full/and
comprehensive public participation in the selection process and that all affected
parties, and particularly neighboring residents, have ample opportunity to express their
concerns and that these concerns be properly addressed.  This community review
must be undertaken as early in the evaluation process as possible.  To date, we are
not aware that any contact has been made with any of the communities near any of
these sites.

Cost/Benefit Analysis

Cost estimates of the various options may not be entirely valid or realistic, since
certain non-Federal costs (e.g.. acquisition costs of lands for disposal, costs of
construction of disposal sites) are not included. Similarly, in-channel disposal does not
include the disposal costs of the remaining parent material. While limiting costs of the
Federal share may be necessary to determine the cost/benefit ratio for Federal
funding purpose, the other costs must be borne by the local sponsor.  For a realistic
comparison of the options, total costs should be compared in the evaluation.

Furthermore, the costs of potential environmental harm and remediation, such as the
contamination of seafood and clean-up expenses from the disposal of containments
into the marine waters, and the likely effects of the dredging/disposal on other
segments of the economy, such as recreation (e.g.. whalewatching) and commercial
fishing, also should be factored into the cost/benefit analysis.

One specific comment with regard to cost/site selection. The screening process of
practicability determined that costs in excess of 4 times  that of ocean disposal would
be prohibitive. According to Figure ES-3, all of the Chariestown and South Boston
shoreline sites have cost ratios greater than this threshold. However, these same
sites also are listed in Table ES-1b as potentially practicable for future harbor
maintenance disposal needs (and the Little  Mystic Channel also for this dredging
project). This apparent discrepancy should be clarified in the Final EIR/EIS.

Dredging Operations

The avoidance of adverse environmental impacts, particularly on marine resources, is
of utmost importance in the implementation of this navigation improvement and berth
dredging project. Extreme care will need to be taken to minimize environmental
disruption, especially the resuspension and release of contaminants into the marine
waters.  Problems such as those which occurred at the  recent dredging by Massport
 at the Moran Terminal must not be tolerated. The most environmentally effective
 equipment for dredging and disposal must be used and this equipment must be
 operated properly by project personnel with adequate training. Further, we believe
 SLTR/132/061594/5

-------
that it is essential that an independent observer be present at each work site to
confirm that the work is being properly performed and that permit requirements are
being met at all times. This observer should have the authority to stop further work if
a violation is seen, until the violation is corrected.

The blasting of the bedrock has the potential for extensive mortality of fish and      I
invertebrates.  While this impact is identified (pg. 4-12), no mitigation measures are  '
proposed to limit the potential extent of the kills.  Means are available to keep fish
from the blasting area (e.g., the use of behavioral stimuli such as strobe lights, electri
fields; and bubble curtains, and physical barriers such as nets, steel mesh, and silt
curtains).  Appropriate mitigation measures should be described in the FEIR/FEIS and
specific commitments made to  employ such measures.

Noise and odor impacts also will occur from the dredging activities, and could
adversely impact residential areas located near the dredging operations. Again,
appropriate mitigation must be  committed to by the project proponents.  In addition,
there is no recognition of the odor impacts from disposal at a shoreline site (such as
Little Mystic Channel).  The foul smell of the dredged material could adversely affect
adjacent residences and other  sensitive receptors and must be evaluated and
mitigated.

Conclusion

The preparation of this Draft EIR/EIS has involved an extensive sediment sampling
and testing program to characterize the material to be dredged as well as a
comprehensive disposal alternatives analysis screening process to identify appropriate
and practicable options for the disposal of the silt material, the parent material and
rock, and the future maintenance material. To assist the Corps and Massport in the
design and planning of these studies and the environmental evaluation, a public
advisory process involving key agencies and interest groups (but lacking community
representation) was established and meetings were held throughout the course of the
study. Through this process, a considerable number of issues were reviewed and
resolved prior to the submission of the Draft EIR/EIS. We believe that on the whole
this has been a highly successful procedure.  Nonetheless, a number of issues do
remain for further resolution, which we have detailed above. We therefore anticipate
continued cooperation with the Corps and Massport  as this project further develops
and look forward to reviewing the Final EIR/EIS document.
 Sincerely, .
  Jnan DeLorey
 Assistant Director for Economic foevelopment

 cc:  Norman Faramelli, Massport (Environmental)
      Janeen Hansen, Massport (Maritime)
 SLTR/132/061594/6

-------
L2-1

       The preferred project design incorporates most of the recommendations from
the ship handling simulation study.

L2-2

       The MBDS is not being considered for the disposal of sediments found to be
unsuitable for unconfined open water disposal through chemical, physical or biological
testing. Because of the restriction placed on the MBDS, no disposal at the MBDS will
occur until the efficacy of capping  or other management technique has been demon-
strated.
L2-3

       The use of the Boston Lightship for disposal of contaminated sediments was
reevaluated in the FEIR/S (Section 4). It was not found to be among the least
environmentally damaging alternatives.
L2-4

       Although the difference in interpretation regarding the suitability of certain
sediments for unconfined open water disposal was discussed in the DEIR/S, all silt to
be dredged for the BHNIP was considered in the DEIR/S to be unsuitable for the
purposes of identifying sufficient disposal capacity.  The FEIR/S continues to consider
all silt from this project to be unsuitable for unconfined open water disposal.
L2-5

       The reevaluation of aquatic disposal sites concluded that the in-channel disposal
option was one of the least environmentally damaging alternatives.  This alternative
has been redesigned based on subbottom geological conditions so that it is capable of
containing the entire quantity of silt to be dredged in the BHNIP.  There is currently
no proposal to dispose of BHNIP silt at either of the Meisburger sites.
L2-6

       The BHNIP team agrees that beneficial use of the parent material is more
desirable than disposal at the MBDS.  The suitability of this material for landfill
closure is discussed hi Section 3.0.

-------
L2-7

       The BHNIP team is in agreement that innovative treatment and dredging
technologies be considered to the fullest practicable extent (Section 3.0 and Appendix
D). The future refinement of existing innovative treatment technologies and introduc-
tion of new concepts could be applied to future maintenance dredging activities in
Boston Harbor. This would be particularly important if the costs for treatment become
lower with further technological development. For this reason sediment remediation
holds a promising future.

       Exploitation of new dredging technologies will be a high priority in the
planning and implementation of future maintenance dredging projects. The proposed
current activities will employ the most effective, proven, and cost effective techniques
available.
L2-8

       The chemical quality of the shoreline sites under consideration for disposal of
dredged silt is similar to that of the adjacent water body, the areas proposed for
dredging.  Partially filling these sites with silt from nearby areas and then capping
them would not compromise the existing ecological conditions. The pier sites are
surrounded by maritime uses.  Although these sites were found to be among the least
environmentally damaging, none were selected as the preferred alternative.
L2-9

       Any future maintenance dredging would require an independent environmental
review process.  The purpose of discussing future maintenance activities in this
document are to insure that foreseeable cumulative impacts are accounted for.
L2-10

       While it is true that there are sensitive receptors including housing and recre-
ational areas adjacent to Little Mystic Channel, this site was not found to be the Least
Environmentally Damaging Practicable Alternative.  Therefore, there is no impact on
environmental equity.
L2-11

       NAI, Several notices and public meetings were held during and after the release
of the draft EIR/S for public comment.  Section 1.0 of the final EIR/S describes the
public process.

-------
L2-12

       Cost estimates for the various disposal sites include the cost of construction of
disposal sites.  Land acquisition costs are not included because their variability. Land
acquisition costs would increase the unit cost of an upland disposal site from $1 to $10
or more.  Parent material is anticipated to go to the MBDS for all alternatives  so that
would not alter the cost significantly between alternatives.  Total costs were used for
comparing alternatives.
L2-13

       The Corps is required to follow strict policy guidelines on determining the
cost/benefit ratio  for a civil works project. Impacts to the environment (except for
mitigation costs)  and the recreational industry, if any, are not included.  However the
purpose of an EIR/S is to address those concerns and discuss the impacts from various
alternatives, so that an informed decision is made regarding dredged material disposal.
Proper management techniques would be employed to avoid losses to fishing and
whale watching businesses.
L2-14

       The cost analysis presented in the DEIR/S was based on comparison to disposal
at the MBDS.  The cost analysis in the FEIR/S is based on comparison to the cost of
the least environmentally damaging alternative.  This is further described in Section 4.
L2-15

       The BHNIP preparation team agrees with this comment. The experience gained
from the Moran Terminal dredging project (as well as from others) is valuable in
recognizing potential problems that may be encountered during the BHNIP. This is
particularly applicable to the dredging of contaminated silt where the risk of environ-
mental impacts is greatest. Consequently, the BHNIP dredge management plan will
include dredging contractor requirements relating to operator training, This training
will emphasize appropriate dredging techniques involving contaminated sediments to
minimize environmental impacts as well as compliance with permit conditions. The
Dredge Management Plan is discussed in detail in Section 5.0.

       However, due to legal liabilities, the Corps can not allow an independent
observer on board a dredge with authority to stop dredging. Observers may inspect
the dredging and disposal operations.  If there is a concern during construction, it can
be brought to the attention of the Corps inspector who will take the necessary action.
                                                                                           .1

-------
L2-16

       The Dredge Management Plan discusses measures to protect fish during
blasting.
L2-17
       Odor issues are addressed in Section 5.8.3.3 of the FEIR/S.

-------
 Boston Water and
 Sewer Commission
 425 Summer Street
 Boston, MA 02210-1700
 617-330-9400
 Fax 617-330-5167
                                   May 23, 1994
Secretary Trudy Coxe
Executive Office of Environmental Affairs
20th Floor
100 Cambridge Street
Boston, MA  02202

Attention:  MEPA Unit

Re:  Boston Harbor Navigation Improvement and Berth  Dredging
     Project, DEIR, EOEA #8695

Dear Secretary Coxe:

     The Boston Water and Sewer Commission has  reviewed  the Draft
Environmental Impact Report for the proposed Boston  Harbor
Navigation Improvement and Berth Dredging Project.   This project
consists of dredging of three tributary channels  (the Mystic
River Channel, the Reserved Channel and the Chelsea  Creek
Channel) and two areas in the Main Ship Channel (Inner Confluence
and the mouth of the Reserved Channel) .  Twelve berth areas and
one intake structure will also be dredged as part of the project.
Massport and the U.S. Army Corps of Engineers are undertaking
this project to deepen the channels and berthing  areas for
improved navigation.

     The project also involves the disposal of  approximately  3.5
million cubic yards of sediments removed as part  of  the  proposed
Improvement Project, and the disposal  of 4.4 million cubic yards
of sediments which will be removed from the channels as  part  of
ongoing maintenance over the next 50 years.  Removal of  sediments
from the channels for maintenance purposes will be required
regardless of whether the Boston Harbor Navigation Improvement
Project is approved.

     Of the total 7.9 million cubic yards of sediments to be
removed for both projects, about 5.7 million cubic yards are
believed to be•contaminated.
                                 £31

-------
     Six alternatives for the disposal of the sediments are
identified in the DEIR with the Massachusetts Bay Disposal Site
(MBDS),  the Boston Lightship, Meisburger sites 2 or 7,  and
Spectacle Island CAD identified as the preferred disposal
alternatives.

     The Commission has the following comments regarding the
proposed Boston Harbor Navigation Improvement Project:


1.   The pre-dredge utility survey should include an inventory of
     all the Commission's CSOs and storm drain outlets in the
     vicinity of the proposed dredging.  Detailed plans which
     show the location of the proposed dredging and blasting in
     the vicinity of the Commission's CSO or storm drain outlets
     should be provided to the Commission.  The proponent should
     also provide the Commission with a written discussion as to
     how the CSO and storm drain outlets will be protected from
     damage or obstruction during dredging and blasting.         .

2.   Selection of any one of the preferred alternatives
     (Massachusetts Bay Disposal Site, the Boston Lightship,
     Meisburger sites 2 or 7, and Spectacle Island CAD) for the
     disposal of the dredged sediments will have no impact on
     BWSC facilities.  However, should the Little Mystic  Channel
     or Reserved Channel Aquatic Shoreline sediment disposal
     alternatives be selected, several CSOs and/or storm  drains
     will have to be relocated or diverted.  In the event that
     one or both of these alternatives is selected, the project
     proponent will be responsible for all aspects relating to
     the relocation and/or diversion  of  any Commission owned
     outlet.  In addition, detailed construction plans for the
     relocation and/or diversion  of any  Commission owned  outlet
     must be provided to the Commission  for review and approval
     prior to construction.   The  relocation or diversion  of any
     Commission outlet must  be constructed in  accordance  with the
     Commission's  Sewer Use  and Site  Plan requirements.

 3.   Relocation of MWRA  facilities will  be required as part  of
     the proposed  project.   These include relocation  of  a water
     tunnel  across the lower Chelsea  River and relocation of  two
     water tunnels' and a  sewer siphon across  the upper Chelsea
     River.   Copies  of the proposed  relocation/ construction
     plans  should  be provided to  the  Commission for review prior
     to construction.

 4.   The Final  EIR should include a  discussion of how and where
     the dewatering of the dredged sediments is to take place.
J

-------
     The information indicated above should be provided to the
Commission before  commencing work.

     Thank you for the opportunity to comment on this project.
                                   ohn P. Sullivan, Jr., P.E,
                                  Chief Engineer
JPS/AK/ak
cc:  B.  Miller, U.S.  Army Corps of Engineers
     L.  Blank,  BWSC
     S.  Shea, BWSC
     J.  Foley,  BWSC
     R.  Mertens,  BRA
     R.  Kobayashi,  MWRA
                            £.33

-------
L3-1

       A coordination meeting with MWRA was held and correspondence was
initiated to identify MWRA crossings, permit requirement schedules and construction
activities.  Close coordination between BWSC and Massport will ensure that the
BWSC facilities will receive adequate protection during dredging, blasting and disposal
operations.
L3-2

       The preferred disposal alternative for the BHNIP, In-channel, will avoid filling
shoreline areas and, so, will not impact CSOs or storm sewers.
L3-3

       A coordination meeting with MWRA was held and correspondence was
initiated to identify MWRA crossings, permit requirement schedules and construction
activities.
L3-4
       Dewatering is discussed in Section 4.0 and Appendix 1 of the DEIR/S.

-------
                      CAPE COD COMMISSION
                                 3225 MAIN STREET
                                    P.O. Box 226
                                BARNSTABLE, MA 02630
                                    £08-362-3828
                                  FAX: 508-362-3136
May 18,1994

Brink P. Miller, Colonel
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, Massachusetts 02254

Dear Colonel Miller:

      The staff of the Cape Cod Commission, a regional landuse planning and
regulatory agency serving the 15 towns of Barnstable County, have reviewed the
Draft Environmental  Impact Report/Statement (DIER/S) for the Boston Harbor
Navigation Improvement and Berth  Dredging Project, and offer the following
comments for your consideration.

      The Commission staff believes it is important to make navigational
improvements to Boston Harbor that will help to ensure safe passage of marine
vessel traffic.  This is particularly important given the fact that much of New
England's petroleum  supply is shipped into and out of the Port of  Boston. At the
same time, the project should be conducted in an environmentally sound manner,
and the disposal location for the dredged material should be chosen based primarily
on  the environmental costs and benefits.

      The Commission staff believes that the dredged materials from the Boston
Harbor project, almost one-half of which have been  identified as being
contaminated silts, should be disposed of  in-harbor  or as close to the harbor as
possible. This will decrease the possibility of transporting contaminants into the
larger Massachusetts and Cape Cod bays system.  The bays support resources of
national and state significance, not the least of which is the federally designated
Stellwagen Bank National Marine Sanctuary.  The conservation and management
of these resources should not be compromised by the Boston Harbor project.

       At the present time, neither the federal or state environmental agencies have
factual information on the stability of capped contaminated sediments in
oceanographically dynamic sites.  For these reasons, the Commission staff
recommends that the Massachusetts Bays Disposal Site (MBDS) and the Boston
Lightship site be dropped from further consideration for disposal of dredged
materials from the Boston Harbor project.

      The Commission staff recommends that the Army Corps of Engineers and
L4-1

-------
MASSPORT more fully evaluate the in-harbor and near harbor disposal options.
The staff recommends that the final EIR/S evaluate the options of contained
nearshore disposal sites, as well as more fully evaluate the use of  near harbor
borrow pits as a disposal option for contaminated materials from Boston Harbor.
The Commission staff recommends that the federal and state regulatory agencies
work cooperatively on identifying the legal and policy issues which need to be
addressed to allow one or more contained disposal sites within Boston Harbor.

      Finally, the Cape Cod Commission staff recommends that the final EIR/S
include an analysis of the management/monitoring needs for the preferred disposal
sites. This information is needed to fully evaluate the environmental costs and
benefits of each of the alternatives.

      Thank you for the opportunity to comment at this public meeting. _ If you
have any questions concerning these comments, please contact Commission stall
member Patricia Hughes.
 Sincerely,
 Armando J. Carbonell
 Executive Director
 cc
 County Commissioners
 Cape Cod Commission
 Assembly of Delegates
 Cape Cod Legislative Delegation
 Congressman Gerry Studds
 Senator Edward Kennedy
 Senator John Kerry
 Trudy Coxe, Secretary, EOEA
 Kymberlee Keckler, EPA
 Peg Brady, MCZM

-------
 L4-1

       The alternative disposal locations that were found to be among the least
 environmentally damaging included upland locations and locations within Boston inner
 harbor in the FEIR/S (Section 4).  In-channel disposal was identified as the preferred
 alternative.
L4-2

       Neither the MBDS nor the Boston Lightship has been identified as the pre-
ferred alternative for disposal of silts dredged during the BHNIP. Either site could be
reconsidered for future projects if capping is  demonstrated to be effective in these
water depths.
L4-3

       In the reevaluation of potential disposal sites, the in-channel and the partial-fill
shoreline scenarios were found to be the least environmentally damaging aquatic
alternatives (Section 4) and the In-channel alternative was identified as the preferred
alternative.
L4-4

       Section 5.7, Long Term Monitoring of Disposal Sites, addresses the monitoring
needs  of the preferred disposal site.

-------
                      CAPE COD COMMISSION

                                 3225 MAIN STREET
                                    P.O. Box 226
                               BARNSTABLE, MA 02630
                                    508-362-3828
                                  FAX: 508-362-3136
June 3,1994

Brink P. Miller, Colonel
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, Massachusetts 02254

Dear Colonel Miller:

      The Cape Cod Coastal Resources Committee, comprised of a representative
from each of the 15 Cape Cod towns and from relevant county and federal resource
management agencies, and advisory to the Barnstable County Commissioners and
the Cape Cod Commission, would like to offer the following comments for your
consideration regarding the Boston Harbor Navigational Improvement Project.

       Two years ago, the Committee urged the Cape Cod Commission to oppose
the designation of the Massachusetts Bays Disposal Site (MBDS) due to its potential
use for the disposal of contaminated dredged materials. In an October 1992 letter to
the Massachusetts Coastal Zone Management Office, the Commission said, " The
combination of the number of Boston Harbor projects, political pressures to expedite
permitting and reduce the costs for projects, and historic use and violations at the
site provide no assurances, in our opinion, that contaminated materials will be
prohibited from the MBDS." We are therefore very concerned that now, in 1994, the
Army Corps of Engineers has proposed this offshore site as a preferred alternative
for the disposal of contaminated dredged materials from the Boston Harbor project.

       The Committee supports the proposal to make navigational improvements
to Boston Harbor to ensure safe passage of marine traffic entering and exiting the
harbor. The Committee recognizes the importance of environmental safety in the
transport of materials, in particular chemicals and petroleum products. At the same
time, the Committee believes this project should be conducted in an
environmentally sound manner, and the disposal location for the dredged material
should be chosen based primarily on the environmental costs and benefits.

       The Committee opposes the disposal of dredged materials from the  Boston
Harbor project, almost one-half of which have been identified as being
contaminated silts, at the Massachusetts Bays Disposal Site or the Boston Lightship.
The Committee believes that the materials should be disposed of in-harbor or as
dose to the harbor as possible. Doing this will decrease the possibility of

-------
transporting contaminants into the larger Massachusetts and Cape Cod bays system.
The bays support resources of national and state significance/ in particular the
Stellwagen Bank National Marine Sanctuary. The conservation and management
of these resources should not be compromised by the Boston Harbor dredging
project.

      The Committee recommends that the Army Corps of Engineers and
MASSPORT more fully evaluate the in-harbor and near harbor disposal options.
The Committee recommends that the final EIR/S evaluate the options of contained
nearshore disposal sites, as well as more fully evaluate the use of near harbor
borrow pits as a disposal option for contaminated materials from Boston Harbor.  _J

       In addition, the Committee urges the mandated federal and state regulatory
agencies to work cooperatively  on identifying the legal and policy issues which need
to be addressed to allow one or more contained disposal sites within Boston Harbor.
These include the application of the Massachusetts Wetlands Protection Act and the
state tidelands licensing authority under Chapter 91 of Massachusetts General Law.
The Committe believes  it is important to address this issues now, to avoid revisiting  I
them in the future when considering  either a new, or maintenance dredging
project.

      Thank you for considering these comments.

Sincerely,
Mark Zivan
Chair
cc:
County Commissioners
Cape Cod Commission
Assembly of Delegates
Cape Cod Legislative Delegation
Congressman Gerry Studds
Senator Edward Kennedy
Senator John Kerry
Trudy Coxe, Secretary, EOEA
Kymberlee Keckler, EPA
Peg Brady, MCZM
Center for Coastal Studies
Association for the Preservation of Cape Cod

-------
L5-1

       The alternative disposal locations that were found to be among the least
environmentally damaging included upland locations and locations within Boston inner
harbor in the FEIR/S (Section 4).  The FEIR/S does not propose the disposal of silts at
MBDS or BLS from the BHNIP.
L5-2

       As stated in response to comment L5-1, the in-channel and shoreline (partial
fill)  sites were found to be the least environmentally damaging aquatic sites.  The
borrow pit sites were all found to support substantial biological resources and were,
therefore, considered to be less desirable alternatives.  Details regarding this analysis
are included hi Section 4.
L5-3

       The BHNIP team has worked closely with regulatory agencies during the
development of the FEIR/S to ensure that legal and policy issues were properly
addressed.
                                        8

-------
                    1 lie  v-/i£y of
June 28, 1994
Brink P. Miller, Colonel
Corps of Engineers
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, MA 02254
Dear Ms Coxe,
Re: DEIR/DEIS Boston Harbor, Massachusetts
   Navigation Improvement Project & Berth
   Dredging Project, EOEA 8695
The City of Chelsea is appreciative of the opportunity to comment on the Draft Environmental
Report/Draft  Environmental  Impact  Statement for the Boston  Harbor and  Berth Dredging
Projects. The City is aware of the important role that Boston Harbor and shipping play in the
region's economy and is pleased to play a role in planning for the proposed projects.
We have reviewed the DEER, and have comments relating to. the public participation process, the
potential blasting at the inner confluence, and the impact of the project on land based traffic.  Our
comments are as follows:
Public Participation Process
The City was not fully included in the public participation process.  The DEIR indicates that an
advisory committeee was established in 1992 to aid in the preparation of the report. A number of
organizations were invited to participate, including the City of Boston; however, the City of
(Sielsea was not included on the invitation list.  This oversight  is confusing because it conflicts
directly with Massport's stated reason for establishing the advisory committee, which is stated in
the DEIR as follows:                                                     '
    Chelsea Department of Planning and Community Development
                            Robert J. Luongo,  Executive Director
   City Hall, 500 Broadway, Chelsea, Massachusetts 02150 • Telephone: (617) 889-8233, Fax: (617) 889-8357

-------
Brink P. Miller
June 28, 1994
Page Two
       "Massport recognized that large projects which may impact the public can no longer be
      accomplished unilaterally There was a consensus that the success of the project depended
      on involving key groups effectively. ... Key parties needed to be identified which either had
      a stake in the outcome (regulatory agencies, environmental groups, and harbor users), or
      could provide useful information to Massport, its consultants and the Corps.  Effective
      involvement of these parties required that they be consulted early, that they be provided
      timely information on the progress of the project, and that they have the opportunity to
      present diverse points of view."


The report indicates that several sites in the City were considered for disposal of the dredged
material, that  dredging will occur within the City's boundaries, and that a permit will be required
from the Chelsea Conservation Commission.  It appears that Chelsea is very much a 'key party' in
this project.


The City has a duty and an interest in participating in all projects that affects the community or its
residents. We would very much like to be more fully involved in the advisory committee for this
project.
Blasting


The DEIR indicates that there will be blasting in the Inner Confluence for rock removal; however,
the impact  of this blasting on shipping or land based structures is not analyzed.  A water taxi
operates out of Chelsea from O'Malley Park/Admiral's Hill with connections to Charlestown, the
North End, Downtown Boston, Long Wharf and the airport. The impacts of the blasting on the
water taxi, other shipping activities,  and on land based structures should be addressed in the
report, with appropriate mitigation measures described in detail.
     Chelsea Department of Planning and Community Development
                              Robert]. Luongo, Executive Director
    City Hall, 500 Broadway, Chelsea, Massachusetts 02150  • Telephone: (617) 889-8233, Fax: (617) 889-8357

-------
Brink P. Miller
June 28, 1994
Page Three
Impact on Land Based Traffic
The report addresses the impact of the dredging on water activities only. There is little discussion  f
of the potential impacts on land side activities.  For example, the DEIR.indicates that the project
will cause delays to shipping traffic;  however, there is no assessment of the impact on land based
traffic. There is no indication in the report if the movement of the dredging ships and barges will
require opening of the Chelsea Street and McArdle Bridges.  These bridges carry a significant
amount of traffic between Chelsea, the North Shore and Logan Airport: frequent opening/closing
of the bridges will have a  significant impact on traffic'in  Chelsea and East Boston, causing traffic
delays and negatively impacting the regional economy.   This issue should be addressed in the
report with appropriate mitigation measures discussed in detail.
The City also wishes to reiterate a statement made earlier in the review process that we would be
opposed to movement of the dredged material by truck on the City's streets.  Chelsea is a densely
developed city that faces  severe impacts from heavy vehicles.  We wish to avoid any potential
impacts from trucking of dredged material.
The City is eager to work with the Commonwealth and the Army Corps of Engineers on this
project and to be involved with the environmental review.  If  you have any questions or seek
clarification of the statements made in this letter, please feel free to contact me.
Sincerely,
John W. DePriest, AICP
Project Manager, Traffic & Transportation
 Cy:  Trudy Coxe
    Chelsea Department of Planning and Community Development
                            Robert J. Luongo, Executive Director
   City Hall, 500 Broadway, Chelsea, Massachusetts 02150 • Telephone: (617) 889-8233,  Fax: (617) 889-8357

-------
L6-1

       The Advisory Committee, Working Group and public participation process for
the BHNIP is discussed in Section 1.0 and Appendices B and C.
L6-2

       Blasting would occur during a short period of time on an infrequent basis.
Prior to blasting, warnings would be given to other boats in the area.  Several minutes
would be needed between the warnings and the blast when all boat traffic would be
stopped in the area. The blasting schedule is anticipated to work around the ferry
schedule. No impacts to land based structures is expected. However, a pre-blast and
post-blast inventory will be conducted by the contractor who would be responsible for
any damages.
L6-3

       The following is an example of the anticipated opening and closing of the
Chelsea Street and McArdle Bridges.  Additional detail can be found in Appendix J.
The Chelsea Street Bridge is anticipated to open and close four times a day for the
first month of construction.  The following month and 1/2 the bridge is anticipated to
open and close eight times a day.  No bridge activity is expected for the next six
months. The following three months both the Chelsea Street and McArdle Bridges
would open and close four times a day. The last two months only the McArdle Bridge
is expected to open and close four times a day.

       As the bridge openings can occur within a 24 hour period, impacts to traffic are
expected to be minimal and temporary.

-------
                      of ^Eirerett, 3HasseicfjusEifs

                          ©fftrc nf ifyc 3Hagor
 PATRICK R. SCHEMA
ADMINISTRATIVE ASSISTANT
CITY HALL 02149
 (617) 394-2270
                                       May 17, 1994
  Brink P.  Miller,  Colonel, Corps of Engineers
  U.S.  Army Corps of Engineers
  424  Trapelo Road
  Waltham,  MA 02254

  Dear Colonel Miller:

       Having reviewed the Draft Environmental Impact  Report/State-
  ment including a draft evaluation of compliance with section 404
  (b)  (1)  of the Clean Water Act, for the Boston Harbor,  Massachu-
  setts Navigation Improvement and Berth Dredging Project,  I  would
  like to make the following comments.

   " "'  Given the alternatives presented in the study,  it  would
  appear the Everett site would be one of the least desirable.   As
  stated the cost would be over 10 times the cost of using  uncon-
  fined ocean space, in fact, only two land sites would be  more
  costly, Plainville and Fitchburg/Westminster.  The capacity which
  is only 55,000 cubic yards hardly makes a contribution  to the
  overall cubic yardage needed.

       I am also concerned with the environmental impact  on our
  shoreline and its affect on marine resources as indicated in
  table 3-7 and the significant and lasting impacts as projected
  in table 3-6.

       Lastly, I am concerned with the impact this project  might
  have on several potential projects in that area.  The rehabilita-
  tion of the Monsanto site for general development, proposed up-
  grading of the shoreline for recreation use by governmental
  agencies and the general development of that section of Everett
  for retail and light industry.

-------
Page 2
Ms. Trudy Coxe

     I will appreciate your making note of my' comments on the
Everett site and will make myself available for further dis-
cussion should you feel it appropriate in the future.
                                     Sincer
JRMibf

-------
L7-1

       The Everett site was not selected as the preferred alternative for disposal of
silts from the BHNIP (Section 4.0).
L7-2
       See response to comment L7-1.
L7-3
       See response to comment L7-1.
                                      10

-------
               CITY  OF GLOUCESTER
                    GLOUCESTER • MASSACHUSETTS • 01930
                                Office of the Mayor
Brink P. Miller
Colonel, Corps of Engineers
Division Engineer
424 Trapelo Road
Waltham, Massachusetts 02254-9149
June 3. 1994
  ear Coionel Miller,
I am writing relative to the Boston Harbor Navigation Improvement Project. I wish to be
recorded in opposition to the proposed dump sites for the disposal of contaminated dredge
spoil from  Boston Harbor,

As the Mayor of a major fishing port. I am fully aware of the necessity of harbor dredging in
order to facilitate the needs of the port in its day to day functions. My concerns however, are on
the potential permanent damage to the resource and its habitat. The sites as proposed, MBDS.
the Boston Lightship, Meisburger2, Meisburger 7, and Spectacle Island CAD, are in an area
where a great many lobster traps are set and a great deal of harvesting for both fish and lobster
is prosecuted.

The ongoing effort to dean Boston Harbor and the ocean would indeed be set back by the
proposed dumping of these contaminants.  There is an urgent need  to protect our environment
and not expose our  marine life to this danger that would have adverse effects on the echo
system. There appears to be too little concern for the important fisheries in the Bay State.
especially in view of all the recent happenings in the New England Fishery.

I would urge the powers to be, to reconsider the  proposal and seek a better alternative.

Thank you for the opportunity to respond on the proposal.
 Sincerely.	

 •4	AU.— \
 Bruce H. Tobey
 Mayor

-------
L8-1

       The BHNIP team developed equivalent resource data for each of the potential
aquatic disposal sites for evaluation in the FEIR/S. The results of these investigations
concur with your observation for the Boston Lightship, Meisburger 2 and Meisburger
7. While there was little lobstering activity in the vicinity of Spectacle Island CAD,
there was evidence of substantial biological activity.  The reevaluation  of potential
aquatic disposal sites concluded that the in-channel and partial-fill shoreline scenarios
were the least environmentally damaging aquatic alternatives (Section 4).
                                       n

-------
                               TOWN OF NAHANT, MASSACHUSETTS
                                           OFFICE OF THE
                                 Board of Selectmen
                                 BOARD OF HEALTH - PUBLIC WORKS DEPARTMENT
                                       CEMETERY COMMISSIONERS
RKJWUJI.LOMBAXD VKZCHARMAK
Robert JlMcIlvecn
                         TELEPHONE (61?) 5S1-CC3
                            FAX (617) 593-03-1
                                                  dune 3.  1994
       Brink P. Miller, Colonel
       Corps of Engineers
       Division of Engineers
       424 Trapelo Road
       Waitham, MA 02254-9149
                                     re
Impact Analysis Division
Planning Directorate
Boston Harbor Navigation
Improvement Project and
Berth Dredging Project
       Dear  Colonel  Miller:
             The Town of  Nahant  has  received a copy of the Public
       Notice concerning the above-named project to dredge Boston
       Harbor.  According to the notice,  any person who has an
       interest that may be affected by  this dredging and disposal
       may  request a public hearing. On  behalf of the Town of Nahant
       we are requesting a public hearing on the proposed project.

             In particular, the  Town is greatly concerned about  the
       proposed dumping  area for the dredged material. According  to
       the  Public Notice one of the proposed disposal sites  is
       directly off the  shores  of Nahant, in particular, Meisburger
       2. The Town is concerned that tidal movement and currents
       will carry the dredged material from Boston Harbor within  the
       confines of Nahant's territorial  waters. We are all aware
       that Boston Harbor is one to the most, polluted harbors  in  the
       Northeast even though at the present time the harbor  is
       undergoing a vast project to clear up the polluted waters.
       Nahant certainly  does not want someone else's trash dumped on
        its  doorstep which would affect the ecological balance  of  the
        fish and plant life of  its waters.

             Accordingly, Nahant requests  a public  hearing on this
         proposed project.
                              o
                             GT~
                                         Town  of  Nahant
                                         Board of Selectmen
 Robert N. Forman, Chairman
        RRR

-------
L9-1

       Environmental impacts and practicability of using the alternative disposal sites
were re-evaluated in the FEIR/S (Section 4.0).  The Meisburger sites are no longer
being considered for disposal of silts from the BHNIP.
L9-2
       A public hearing was held hi the Town Hall hi Nahant on July 28, 1994.
                                       12

                          TOWN OF  NAHANT. MASSACHUSETTS O19O8
Certified Return Receipt
                                    Office of the Town Administrator
                                         Michael C. Wood
                                          (617)581-9927
                                        June 1,1994
Brink P. Miller
Colonel, Army Corps of Engineers
Division Engineer
424 Trapelo Road
Waltham, MA 02254-9149

Dear Colonel Miller:

       I am responding on behalf of the Nahant Board of Selectmen relative to the Public
Notice dated May 13, 1994, entitled "Boston Harbor, Boston, Massachusetts Navigation
Improvement Project and Berth Dredging Project. "
       The Town of Nahant requests a public hearing in accordance with this public
notice. The Town was not directly notified of this project, and has not been advised of its
impact. As such, we did not have appropriate notice to attend the scheduled public
hearings of May 17 and 19.
       The Town of Nahant requests to be directly notified, through its Board of
Selectmen, of any and all projects involving Boston harbor and related waterways.
Nahant is a community on the North Shore surrounded by water. Any project initiated in
this vicinity may affect our community.
       Obviously, the depositing of materials taken from Boston harbor or its related
waterways as outlined in the aforementioned public notice may have an impact on our
town, and we would like to learn what the project entails and its potential repercussions.
       We look forward to your favorable response to our request for a presentation and
public hearing.

                                        Very truly yours,
                                         Michael C. Wood
                                         Town Administrator
 MCW/sev
 cc: Board of Selectmen
    SWIM
    Conservation Commission

-------
L10-1
      A public hearing was held in the Town Hall in Nahant on July 28, 1994.
L10-2

      The Corps will notify the Nahant Board of Selectmen of future dredging
projects that could affect the community.
                                   £53
                                     13

-------
 f
                                      JDie 'Eaton ai
QJcrmmtssum
                                    'Eiihu Ihotnmon AbminUJrjrticm JJuilbutg
                                          , JHassachuaetis 01907
                                                                 L11
                                              June 17, 1994
              Ms. Jansen  Hansen, Project Manager-Maritime
              Massachusetts  Port Authority
                       Re:  BOSTON HARBOR NAVIGATION IMPROVEMENT
                           AND BERTH DREDGING PROJECT #MEPA8695
                         HlH
              Dear Ms.  Hansen
                           This Commission has been alerted to the
              above-named project.  By unanimous vote of the Commission
              we wish to be  recorded as unalterably opposed to the
              use of site Meisburger 2 as a dumping area, as it is
              only about 5 miles off the coast of Swampscott.
                           Scientific tests have shown that dredging
              material  for Boston Harbor contains certain types of
              contaminants which would have a potential biological
              impact on these waters.
                           Please keep us informed of any further
              developments regarding this project.

                                       Yours truly,
                                        awrence Picariello, Chairman
               cc. Swampscott Board of Selectmen
                   Swampscott Board of Public Works
                   Representative Douglas Petersen
                   Senator Walter Boverini
                   Ms. Trudy Coxe, Secretary
                                   Executive Office Environmental Affairs
\.

-------
Lll-1

       The reevaluation of the potential disposal sites in the FEIR/S concluded that the
Meisburger 2 site would not be the preferred alternative for disposal of BHNIP silts
(Section 4).
                                        14

-------
(kifim of
        OFFICE OF THE
   Urnrrfl of jkiedmen
                                                                        L12
                           ELIHU THOMSON ADMINISTRATION BUILDING
                             SWAMPSCOTT. MASSACHUSETTS 01907
Robert W. Murphy, Chairman
Daniel U.  SantanelJo. Vice Chairman
Janet N- Baker
Douglas F. Allen
Peter J. Cassidy
      June 20, 1994
    Patricia E. George
Administrative Assistant
      (617)596-8850
  FAX (617) 596-8851
   Brink P. Miller, Colonel
   Army Corps of Engineers
   New Englarid Division
   424 Trapelo Road
   Waltham, MA  02154

   Dear Colonel Miller:

      . The Board of Selectmen is extremely concerned about the detrimental effect
   the  Boston Harbor  Dredging Project may  have on  the seaside community  of
   Swampscott.                                                                _

        In order for us to understand every aspect of this project, particularly the
   possible dumping of hazardous waste at the proposed dump site  referred to as
   "Seisburger Two",  we must be provided with all pertinent information as soon as_
   possible.                                                                   _

        We believe that a public hearing on this  matter is in order and wish to be
   directly notified of the date, time and location of the public hearing so that aJlj
   interested parties may attend.

        We look forward to receiving this important information from  you and thank
    you for your  attention to this matter.

                                Sincerely,

                                BOARD OF SELECTMEN
                                       W
                                 Chairman

    RWM/pg
    cc  Representative Douglas W. Petersen
        Congressman Peter Torkildsen
        Harbor Advisory Committee
        SWIM President William Coffey

-------
L12-1

       Environmental impacts and practicability of using the alternative disposal sites
were re-evaluated in the FEIR/S (Section 4.0). The Meisburger 2 site is no longer
being considered for disposal of silts from the BHNIP.
L12-2
       Swampscott participated in the public hearing in Nahant on July 28, 1994.
                                       15
£-57

-------

-------
ENVIRONMENTAL AND ADVOCACY GROUPS
          COMMENTS AND RESPONSES

-------
•in  i nil in i  in
      111 id	II	Ill
                   111   H        llllllllk
                                      	I
                                      !!!!
                                         111
|li    (I	Ill       	UNI    III      1	|i     I  II
                   in      n     ill	
                                                                       nil in
        III l|l
  I

•(ill

lllllll
                                                                                                                                         lilllll
                                                                                                                                                                    I"     I
                                  lllllll

                                 I.!1!,!

-------
the boston harbor association
               for o clean, olive and accessible Boston Harbor
   374 Congress Street
         Suite 609
  Boston. MA 02210-1807
Telephone (617) 482-1722
    Fax (617) 482-9750
                                                21 June 1994
      Colonel Brink P. Miller
      U.S. Army Corps of Engineers
      424 Trapelo Road
      Waltham, MA 02254-9149
      DeapCx>lonel Miller:
      The Boston Harbor Association is a non-profit, public interest group
      founded in 1973 to promote a clean, alive, and accessible Boston
      Harbor. TBHA was the first public interest group in the early 1970s
      to call for the clean up of Boston Harbor, and has closely monitored
      the clean up project for many years.

      TBHA supports an alive and accessible Boston Harbor: alive with
      people enjoying the harbor (hopefully in the not-too-distant future
      with thousands of people swimming in the Harbor) as well as an
      active working Port.

      More than 17 million tons of cargo come through the Port of Boston
      each year. Eighty percent of the cargo which comes through the Port
      are petroleum products, and more than 30,000 cars move through
      the Port's terminals.  Clearly, an active, viable working Port is key to
      the economic vitality of the region.

      Given the size of modern tankers, the Boston Harbor Navigation
      Improvement Project and Berth Dredging Project is needed so that
      basic goods such as food, fuel, and transport can continue to come
      through the Port of Boston. In addition, the Navigation Improvement
     - Project is needed to allow Boston to remain competitive with other
     7 ports in the country, and to continue  as a source of jobs for the
      region.
©

-------
 TBHA has reviewed the Draft Environmental Impact Report/   ;
 Statement for the Boston Navigation Improvement and Berth
 Dredging Project and offers the following comments:


 First, TBHA believes that this project can and must be done in an
 environmentally sensitive manner. Proper dredging techniques as
 well as the appropriate disposal of dredged materials need to be
 incorporated into the project.

 Our reading of the Draft Environmental Impact Report/ Statement as
 well as our participation on the Dredging Advisory Committee and in
 the 17 May 1994 Public Meeting indicate that Massport and the
 Army Corps of Engineers, the project proponents, intend to
 incorporate environmental standards and controls into the project.  __
                                                             ^—«^^™
 Second, additional attention must be given to new disposal and
 remediation alternatives.  In other parts of the country, alternative
 technologies have been developed which have been effective in the
 remediation of contaminated sediments. We commend Massport for
 its efforts to explore the possible use of these alternatives, and
 encourage them to continue to do so.

 Consistent with this, the "Green Ports" legislation recently filed in
 Congress provides funding for communities to incorporate alternative
 technologies into their dredging operations, and we urge continued
 support for passage of this legislation this session.

 Moreover, the U.S. Environmental Protection Agency needs to
 provide leadership in helping to examine alternative technologies
 and in helping to develop regional solutions, to dredge disposal.    _

 Third, the Draft EIR/S lists several practicable alternatives for
- .disposal. We make the following observations:

 Unconfined ocean dumping of contaminated sediments, a historic
 practice for which we are paying the price environmentally, is no
 longer permitted. The Draft EIR/S recognizes this reality.

-------
Disposal of contaminated sediments at the Mass Bay Disposal Site,
even with capping, may pose environmental problems, given the
depth of the site. Additional analysis and monitoring would be
needed before the permitting agencies would allow MBDS to be used
for contaminated sediments. Realistically, this option appears more
feasible for future harbor maintenance.

Based on the information we have reviewed, clean sediments appear
appropriate for disposal at the Mass Bay Disposal Site.

The Boston lightship site had previously been used for the disposal
of radioactive wastes. TBHA urges further study of the radioactivity
of the site before it is considered as a disposal site for this project.

TBHA urges that additional analysis occur of Meisburger 2 and 7,
specifically of the impacts to fish and shellfish. The Final EIR/S
should include additional information on impacts to the fishing and
shellfish industries.
TBHA urges further study of the Combined In-Channel locations ,
such as Chelsea Creek, Inner Confluence, and Mystic River In-
Channel. A major concern related to this option is how existing ship
traffic will be accommodated at these tributaries, which are actively.
used by ships. The Final EIR/S needs to clearly explain how ship
traffic will be maintained during disposal operations.           -—J

The Final EIR/S should address the land-based impacts of the
preferred option, such as traffic impacts from bridge openings and
closings, and land-based dredge material disposal.  We urge that the
Final EIR/S provide specific measures on how the project proponent
will handle both land and water side impacts.

Fourth, Massport, one of the project proponents, has had recent
experience with dredging at Moran Terminal. It found that the
environmental clamshell bucket required by the Boston Conservation
Commission  was not as effective as hoped due to the large number
of piles and amount of debris caught in the bucket, preventing it
from closing tightly. We support Massport's efforts to develop a

-------
 contingency plan to deal with this problem. Also, the development
 of performance standards for dredging, rather than specifying
 dredge equipment type, may be more appropriate for incorporation
 in permits and orders of conditions.                             j

 Fifth, TBHA supports the concept of an independent observer to
 monitor the dredging operation. Other major project proponents
 such as the Central Artery Project and the MWRA contribute to the
 cost of hiring independent observers within the City of Boston's
 Environment Department to monitor compliance with permit
 conditions, and we urge Massport to do likewise.

 In closing, we reiterate our strong support for the Boston Harbor
. Navigational Project, and look forward to receiving the additional
 information requested above in the Final EIR/S.

 Thank you for your consideration.
                                   Sincerely,
                                    Vivien-XT"
                                   Executive Director
 VL: pr

-------
 El-1

        A detailed Dredge Management and Monitoring Plan that identifies the procedures
 necessary to minimize environmental impacts during both dredging and disposal is presented in
 Section 5 of the FEIR/S.
 El-2

        Treatment technologies are discussed in Section 3.0 and Appendix D of the FEIR/S.
 The Corps is willing to look into practicable technological alternatives for the disposal of
 contaminated dredged material, when appropriate funding is available.  We will continue to
 work with the U.S. EPA on these new technologies.
EI-3

        The BHNIP is not considering disposal of silts at MBDS to be feasible for the current
project.  Any future use of that site for such materials would require prior demonstration of
successful capping. Where feasible, the Corps will investigate capping and other management
techniques for the MBDS site.
El-4

        BLS has not been selected as the preferred alternative for the BHNIP. Any future
proposals for using BLS for disposal would require coordination with EPA regarding the
proported drums of industrial and radioactive waste at this site. Disposal of dredged material at
this site to cover these drums may benefit the environment of this area. The EPA should play
an active role in researching the locations and environmental status of any hazardous materials
at the BLS to determine whether it would be best to leave as is, remove, or cover in place.


El-5

        The fisheries resources of the Meisburger sites were investigated and incorporated  into
the alternatives analysis.  It was determined that other disposal alternatives exist that would
have less environmental impact (Section 4).
El-6

        Please refer to the Dredged Material Management Plan in Section 5.0 of the final
EIR/S.  During the dredging and in-channel operations, normal harbor traffic will be
maintained to the maximum extent possible. The proposed in-channel disposal operations will
not obstruct the entire channel width at any location within the project. Partial obstruction will
be unavoidable.  Proper Notification to Mariners will be issued through the US Coast Guard
and all construction equipment, including dredges, scows and tugs, will display internationally
recognized signals.  Vessels will be directed away from active dredging and disposal sites into
unobstructed sections of the active channel. The dredges will likely be required to move to

-------
allow larger vessels to pass regardless of the disposal alternative.  In-channel disposal
operations can be worked around vessel movements since it is not required that a scow remain
on location for a lengthy period of time.
El-7

       The proposed disposal alternatives will have little impact on land based activities.
However, bridge openings on the Chelsea River will increase to accommodate tug and scow
cycles. The in-channel alternative would require additional scow traffic to transport of
dredged material from the Reserved Channel to the Chelsea River and Mystic River.
El-8

       The FEIR/S, Section 5.0 Dredging Management Plan and paragraph 5.8.2.2, Trash and
Debris Management, describe specific contingencies for trash and debris which may be
encountered. It is anticipated that specific minimum performance criteria will be incorporated
into the conditions of the permits.
El-9

        An independent observer present on board the dredge would not be allowed to control
the contract work. However, there may be a measure of liability for the contractor by
allowing an independent observer on board that is out of the control of the Corps. Any
problems observed can be reported to the Corps inspector who will determine the proper
action to be taken.  A Corps inspector would be responsible for permit compliance.

-------
             CENTER   FOR   COASTAL  STUDIES
             A Private Non-Profit Organization for Research, Education and Conservation in the Coastal & Manne Environments
             59 Commercial Street • P. O. Box 1036 • Provincetown. Massachusetts 02657 • Telephone: (503) 437-5622
18Mavl994
William C. Scully
Deputy Division Engineer
US Army Corps of Engineers
New England Division
424 Trapelo Rd.
Waltham.  MA 02254

Stephen P. Tocco
Executive Director &CEO
Massachusetts Port Authority
Maritime Department
Boston Fish Pier II
Boston, MA 02210

       Statement for the May 19,1994 Public Meeting
       Hyannis, Ma
Gentlemen,

Thank you for holding this meeting on Gape Cod and for the opportunity to comment the Draft
EIS/EIR for the Boston Harbor, MA Navigation Improvement Project and Berth Dredging Project.
As I anticipate submitting a more complete letter of comment on this project, please accept the
following brief observations from my initial review of the document.

I suppose I will echo the concerns of many here tonight by voicing opposition to the disposal of
contaminated sediments derived from this project at the Massachusetts Bay Disposal Site. I would
also caution against the disposal of any dredged materials within the Boston Lightship Area until the
EPA and other federal agencies have completed the assessment of past disposal of hazardous and
low-level radioactive wastes in Massachusetts Bay. As a member of the EPA's Advisory Committee
on Waste Disposal in Massachusetts Bays, I am not satisfied that this effort was ever completed in a
satisfactory manner.

ANALYSIS OF DISPOSAL SITE ALTERNATIVES (CHAPTERS)

Massachusetts Bay Disposal Site (MBDS)
The final designation of the MBDS prohibited the disposal of contaminated sediments, due in part to
the depths at the site and its close proximity to the Stellwagen Bank National Marine Sanctuary.
Early on, the Stellwagen Bank Coalition Steering Committee, of which I am a member, supported
gjving NOAA oversight over all disposal activities and the authority to certify (condition or deny)
permits to insure that there would be no destruction, loss, or injury to Sanctuary resources.  Since
the designation process resulted in a re-location of the MBDS, no portion of it falls within the
Sanctuary boundaries. However, its dose proximity has resulted in the MBDS being defined as an
                                                                                                 a

-------
Impact Category I Site (under ODA), which will require limitations on the use of the site, as necessary
 D reduce the impacts to acceptable levels.

Thus, as a Category I site, NOAA has the authority to certify disposal permits in order to avoid
potential harm to Sanctuary resources. We recommend that they use this authority to the fullest
extent to review the current project.

According to the ESA Section 7 Consultation (November 7,1991) on the designation of the MBDS,
the National Marine Fisheries Service's (NMFS) determined that "the final designation of the MBDS
wfll not jeopardize the continued existence of any endangered or threatened species _. However,
disposal activities associated with the MBDS may adversely effect some of these species."  Their
conservation recommendations at the time included the placement of NMFS-approved observers on
board disposal vessels and the collection of reliable ambient water quality data for the MBDS,
determination of toxin tissue levels in live, free-ranging endangered species, and the evaluation of
the long-term behavior of sediments disposed of at the MBDS. The Section 7 Consultation did not
evaluate the issue of capping at the site, presumably because the designation prohibited the disposal
of contaminated sediment at the MBDS.

Based on these conditions affecting the MBDS, ft is my opinion that it does not qualify as feasible
alternative for the disposal of contaminated dredged materials, and should not be considered as such
in the EIS process.

Meisburber Sites                                                                        —
lie borrow pits at both sites 2 and 7 appear to be attractive options for disposal of contaminated
 adiments, given the concerns at the MBDS and Boston Lightship sites. Both of the Meisburger sites
appear to be located roughly three miles from the proposed MWRA outfall diffusers. I am concerned
that their proximity to proposed outfall may influence the ability of these sites to be monitored
properly in the future. The MWRA's current outfall monitoring program has shown some
constituents of the current effluent discharges are detectable above expected background levels at the
proposed outfall location, gjving rise to the concern here that contamination of these two sites by the
new outfall may make it difficult to determine the success of capping of contaminated sediments.
The EIS should evaluate the potential  degradation (cross-contamination?) of the sedimentary
environment and benthic resources at these sites from the prosed outfall.

OTHER COMMENTS ON THE DRAFT  EIS/R                                          ~~
Note: The Gulf of Maine population of harbor porpoise, Fhocoenaphocoena, may be designated as
threatened under the ESA by July, 1994. This species is common in in Massachusetts and Cape Cod
Bays in late winter through early spring and is known to accumulate some  synthetic organic
contaminants.

The MBDS is an important feeding area for some species of endangered cetaceans, particular for
juvenile humpback whales.

 Confined ocean disposal, also called "capping", of contaminated materials is still under
 consideration by NMFS, USFWS, COE, EPA and the Commonwealth of Massachusetts to determine
 Hs environmental feasibility as a management alternative at the MBDS. Until such time as

-------
   iclusive tests prove the effectiveness of this technology at the site, it should not be considered as
an alternative for the Boston Harbor Project.
SHI
Russell A. DeConti
Director of Conservation

-------
E2-1

       MBDS is not being considered as a feasible alternative for disposal of silts from the
improvement and berth dredging project. If capping is demonstrated to confine contaminated
sediments successfully in the future, this site could be considered for future projects, including
the maintenance of Boston Harbor.
E2-2

       Biological investigations conducted at all potential aquatic disposal sites in fall 1994
demonstrated the high degree of biological activity at these sites. It was concluded that other
sites could be used for disposal with less environmental damage (see Section 4).
E2-3
       This species is also discussed in the Biological Assessment for this project.
E2-4
       A Biological Assessment was prepared for this project to discuss any impacts that may
occur to threatened and endangered species in the area of MBDS.
E2-5

       MBDS is not considered to be a feasible alternative for the disposal of silts from the
BHNEP in the FEffi/S.

-------
                   Center for Marine Conservation
                                 June  27,  1994
Brink P. Miller  .
;Colonel, Corps of Engineers
U.S. Army Corps' of Engineers
424 Trapelo Road
Waltham, MA • 02254
      Re:  Comments of the Center for Marine Conservation on the Draft
Environmental Impact Report/Statement  (DEIR/S) for the Boston Harbor,
Massachusetts Navigation Improvement and Berth Dredging Project (57 FR  27762,
June 22, 1992)         •            •                 •
Dear Colonel Miller:                          .                .      .

      The Center for Marine Conservation (CMC) submits the attached comments on
the dredging and disposal of material from the three tributary channels in Boston
Harbor and the associated berthing areas.

      Although  we do not oppose  the project goal  of improved navigation for
Boston Harbor,  CMC believes  that  the selection as a preferred alternative for
disposal of dredged materials,  including contaminated materials with capping, of
the Massachusetts  Bay Disposal Site  (MBDS):   (1)  fails to adequately consider~
the potential serious threats  to  the adjoining Stellwagen Bank National Marine_
Sanctuary  as required  by the National Marine  Sanctuaries  Act  (NMSA);   (2)
violates the consistency requirements of the Coastal Zone Management  Act  (CZMA)_
and is inconsistent with the  designation of the site;  (3)  does not sufficiently
develop  alternatives to the MBDS for  disposing  of contaminated sediments as_
required  by the National Environmental  Policy  Act   (NEPA) ;   (4)   • does not
adequately  protect  threatened and  endangered  species and marine  mammals -as
required by the Endangered Species Act:  (ESA);  and  (5)  poses a danger to human"
health due to the potential contamination by toxins of commercial fishing stocks.
CMC  therefore  requests that  the   DEIR/S  be  revised to comply with  these-
requirements,  indicate that the MBDS is not. the preferred alternative for the
disposal  of  contaminated   sediments,  and  adequately  develop  less  harmful
alternatives.    These concerns and  requests  are more  fully  discussed  in the
attached  comments.
                                                                               E3-!
                                                                               E3-2
                                                                               E3-3
                                                                               E3-4
                                                                                E3-5
       Thank you for your consideration.
                                                          //?/.
 Jack/Sbbel.               / ^ f
 Director, Habitat Conservation

 cc:  The Honorable Edward M.  Kennedy
 _    The.Honorable John F. Kerry
 & •;   The Honorable Gerry E; Studds
 ~    The Honorable Ron Brown
      The Honorable Carol Browner
      Judy Pederson, MCZM
      Francesca Cava, NOAA
      Trudy Coxe, Mass. OEA
                                         Margaret/M. Lytle   '     A
                                         Associate Counsel        ^
1 725 DeSales Street, NW, Ste. 500
                             Washington, D.C. 20036'    (202)429-5609  Telefax (202) 872-0619
                                           __
                                          » « Printed on 100% post-consumer, unbleached, recycled papa

-------
           Comments on the Draft Environmental Impact
        Report /Statement (DEIR/S)  for the Boston Harbor,
    Massachusetts  Navigation  Improvement and  Berth Dredging
              Project  (57  FR  27762, June 22,  1992)

                         Submitted by the

                 Center for Marine Conservation

                         June 21  , 1994
     The Center for Marine Conservation (CMC)  submits the following
comments to  the Massachusetts Port Authority  (Massport)  and the
United States Army Corps  of Engineers  (COE)  concerning the Draft
Environmental  Impact  Report /Statement  (DEIR/S)  for  the  Boston
Harbor, Massachusetts  Navigation Improvement and  Berth Dredging
Project.

     Massport and  COE, in this DEIR/S, outline plans for dredging
major shipping  lanes and  berths  in Boston Harbor and options for
disposing  of   3.5 million cubic  yards  of  clean  and  highly
contaminated  sediments from that  dredging.   They  also identify
potential  disposal sites  for  about 4.4  million cubic  yards of
contaminated sediments from future maintenance dredging.  Massport
and COE have selected the Massachusetts Bay Disposal Site (MBDS) as
a preferred  disposal alternative for contaminated sediments  from
the proposed dredging project and the future  maintenance dredging,
with the intent of capping  these sediments with clean  sediments.

     CMC believes  that the selection as a preferred alternative for
disposal   of   all   dredged  materials,   including  contaminated
materials,  of  the Massachusetts  Bay Disposal Site  (MBDS):  _  (1)
fails to adequately consider the potential threats to the adjoining
Stellwagen Bank National Marine Sanctuary as  is required by the
National  Marine  Sanctuaries  Act   (NMSA)1;    (2)    violates the
consistency  requirements  of the Coastal Zone Management Act (CZMA)
and  is inconsistent  with the designation of the site;   (3)   does
not  sufficiently develop alternatives to the MBDS for disposing of
contaminated sediments as  required by the National  Environmental
Policy Act (NEPA)3;   (4)    does not adequately protect _ threatened
     endangered species and marine  mammals  as  is required by the

      *16 USC §§ 1431-1445.

      216 USC § 1456(c).

      342 USC §§ 4321-4335.
£70

-------
Endangered Species Act  (ESA)4;   and  (5)   poses a danger to human
health due to the potential contamination by toxins of commercial
fishing stocks.  CMC therefore  requests that the DEIR/S be-revised
to comply with  these requirements,  indicate  that  the MBDS is not
the  preferred  alternative  for  the  disposal  of  contaminated
sediments, and adequately develop less harmful alternatives.

                                                                  ta

FAILURE TO CONSIDER  POTENTIAL THREATS TO STELLWAGEN BANK NATIONAL
MARINE SANCTUARY AS REQUIRED BY THE NATIONAL MARINE SANCTUARIES ACT

     Stellwagen Bank was designated as  a national marine sanctuary
on November  4,  19925.   Stellwagen  Bank is a uniquely configured,
nutrient-rich area that supports a  diverse fish, invertebrate, and
whale population.   Stellwagen Bank  is one of three Atlantic areas
critical to migrating humpback, minke,  right,  and fin whales.  The
area also contains  rich commercial; fisheries6.  Unfortunately,  of
the  five sites  detailed in the DEIR/S,  MBDS is  the  closest  to
Stellwagen Bank and its precious marine  resources.   Disposal  of
contaminated sediments  at MBDS, no matter what technology  is used,
threatens  the  very rare and  special  characteristics  that make
Stellwagen Bank valuable as a Marine Sanctuary.

     The   National   Marine  Sanctuaries  Act   requires  formal
consultation  with  the   National   Oceanic   and  Atmospheric
Administration (NOAA)  for federal agency  actions which may effect
marine sanctuaries,  including the effect of dumping of contaminated
sediment  and capping it.   Amendments  to  the Act adopted  in 1992
require  that  "federal  agency  actions  internal or external to  a
national marine sanctuary ...  likely to destroy, cause the loss of,
or injure any  sanctuary resources are subject to consultation with
the Secretary  [of Commerce] . "7  The federal agency must provide  to
the Secretary  of  Commerce a  written statement  describing the
potential  effects of its action on sanctuary resources.  If the
Secretary finds that the action is likely to injure a  sanctuary
resource,  the  Secretary must  recommend  reasonable and  prudent
alternatives  to  which the   agency   must  respond,  and   such
alternatives may include conduct of the  action elsewhere.   The
DEIR/S does  not reflect that  any such  consultation with NOAA took
place in  regard to the decision  to  dump  dredge material  near
 Stellwagen Bank.
      416  USC §§  1531-1543.
 Sf-"-
      5Pub.  L. tto. 102-587, § 2202 (a) ,  106 Stat .  5048, Nov. 4, 1992,
 codified at 16 USC § 1433 note.   !                .   .

      6Eldredge,  Maureen.  "Stellwagen Bank:   New England's First
 Sanctuary", Oceanus . Vol. 36, No. 3,  p. 72, Fall 93.

      716 USC § 1433 note.

-------
     Furthermore,   the   National  Marine  Sanctuaries  Act   also
 authorizes  NOAA  to  adopt management  plans  that  prohibit  the
 disposal  of  dredged material  if  deemed  necessary  to -protect
 sanctuary  resources8.    In regard  to  Stellwagen  Bank,  NOAA  has
'adopted regulations that prohibit the disposal of dredged material
 both within the  sanctuary and  outside  it  if  the materials  may
 "subsequently   enter  the  sanctuary"  and/or   injure   sanctuary
 resources or qualities9.   NOAA has  the authority to require terms
 and conditions necessary  to protect sanctuary  resources .   The
 failure of  Massport and COE to consult on the record with NOAA on
 the proposed   disposal  of  contaminated  sediments  in  an  area
 adioining a national marine sanctuary circumvents the protection of
 these regulations,  and  violates the National Marine Sanctuary Act
 Title III,  leaving Stellwagen Bank without adequate protection.

      The need  for consultation is manifest in this case.  Dumping
 sediments  that are contaminated with PCBs,  PAHs, heavy metals and
 other  toxic   substances   at  MBDS  could seriously damage  water
 duality,  and marine life  at  Stellwagen  Bank.   Toxic contaminants
 may  cause  undesirable  biological effects  to  organisms in  the
 environment.   Further,  toxic  contaminants may also accumulate in
 living marine resources  at  levels that pose  a threat  to  human
 consumers   of  these resources.   These  potential  threats  are not
 given adequate consideration in the DEIR/S.

      Serious concerns over the disposal of contaminated sediments
 'and the use of capping  were expressed by the Massachusetts Coastal
 Zone Management Office  (MCZM) and the U.S. Environmental Protection
 Agency  (EPA)  during the  process  of  designating MBDS.   Prior to
 selecting  the MBDS  as  the preferred alternative Massport and  the
 COE must conduct formal  consultation with  NOAA and the State of
 Massachusetts  regarding  the  potentially  dangerous effects  of
 disposing  of   contaminated  sediments at  MBDS.    The  final rule
 designating MBDS states  "  ...  EPA's  EIS  made  clear  that only
 materials  that satisfied EPA's ocean  dumping  criteria could be
 disposed  at   the MBDS  in accordance with Section 103(c)  of  the
 MPRSA, 33 U.S.C. 1413(c)  	 based on current information EPA did
 not accept that the environment  could effectively be protected from
 contaminated  dredged material by trying to cap the material  on the
 ocean floor at a site such as the MBDS."  Important concerns by the
 EPA and others in regard  to capping technology and feasibility are
 still unanswered.

       While Massport  and   COE  claim   that  the   threats   from
 icontaminated  sediments  can be overcome by the use of capping,  this
       816 USC § 1434(b);   15 CFR  §  922(a)(8).

       915 CFR § 940.5(a)(2).

       1015 CFR §§ 940.5 (f) & (g) ,  and § 940.10.

-------
                                4

is an unproven  and controversial technology.   We are especially
concerned about the  fate of the fine grained  fraction.of dumped
sediments which are the most likely to miss the targeted site and
to which contaminants readily adhere.   We would like to see more
analysis of the percentage of contaminants likely not to be covered
by capping.

     The  final  rule  designating MBDS  stated  that  disposal and
capping of  unsuitable materials at MBDS  is  prohibited until its
efficacy .can be  effectively demonstrated.    COE has  failed to
provide  any  convincing evidence  of  such  effectiveness.    The
discussion  of  capping  at  Appendix  G  of  the  DEIR/S  fails  to
adequately address concerns  over the technology.  It is admitted in
the discussion that fine particles  are the most likely to disperse
widely, and are also the  most  likely  to be  contaminated.   The
issues of suspension and resuspension of sediments is "not resolved
completely"  (DEIR/S G-17).   Another concern involves the statement
that in cases where remediation  of the capped area is necessary, it
could take months to accomplish (DEIR/S G-16).  Use  of capping is
particularly  risky  at MBDS  because the depth  of the water makes
dispersal uncertain.  Previous COE experience with capping involved
shallower, calmer waters, with less rocky  bottoms.  These specific
issues bring out only a  few of the concerns regarding capping.  Due
to  the lack of  demonstrated  safety and  effectiveness of the
technology, the DEIR/S must  be revised to eliminate the MBDS as the
preferred alternative for the disposal of contaminated sediments.


VIOLATION  OF THE  CONSISTENCY  REQUIREMENTS  OF THE COASTAL  ZONE
MANAGEMENT ACT

     The  MCZM  stated during the  designation  of MBDS  that the
disposal of contaminated sediments, under  any circumstances, would
not  be  consistent  with MCZM  policies11.    All  federal  agency
activities, whether in or outside the coastal zone,  are subject to
the  consistency requirements of the Coastal Zone Management Act.
The  Act provides:

     Each  Federal agency activity within or outside  the coastal
     zone that affects any land  or water use or natural resource of
     the  coastal  zone shall be carried out  in a manner which is
     consistent   to   the maximum   extent practicable  with the
E3-1
                                                               12
      enforceable policies  of approved State management programs

%n addition to these requirements, the Act also provides that  "Any
-Federal agency which shall undertake any development project in the
      "Letter from  Jeffrey R.  Benoit,  Director,  MCZM,  to  Julie
 Belaga,  Regional  Administrator,  EPA,  dated November 13,  1992.
      1216 USC § 1456 (c) (1)
                              £73

-------
 coastal  zone of  a state  shall insure  that the  project is  ...
 consistent with ... approved State management programs."13  Federal
 agency  activities and development  projects  are subject  to  state
 consistency  review if they are located  in or effect the coastal
 zone.    COE  and  EPA  activities  under  the  Ocean  Dumping Act14
 including the disposal of sediments from dredging activity at MBDS
 are  definitely subject  to the consistency  requirements of  the
 CZMA15.

     The   Massachusetts  Coastal   Zone   Management  Office   has
 determined that only the disposal of clean dredged material at MBDS
 is  consistent with the  state's program,  and  that disposal  of
 contaminated material, even if  capped, is prohibited16.  Any action
 by  COE  contrary to  this  consistency  determination,  such  as
 selection of MBDS for the disposal of contaminated sediments under
•any  circumstances, including  capping,  would  violate the CZMA17.
 As the disposal of contaminated materials and the use of capping at
 MBDS are clearly  not  consistent with the state's management  plan,
 the DEIR/S must be revised to  eliminate those options from the list
 of preferred alternatives.                                       	


 DEVELOPMENT  OF  ALTERNATIVES  FOR  THE  DISPOSAL OF  CONTAMINATED
 SEDIMENTS AS REQUIRED BY NEPA

     The   object   of  NEPA   is  to  incorporate   conscientious
 consideration of  environmental aspects  of proposed actions in the
 decision-making   processes  of  federal  agencies.    NEPA  clearly
 requires that federal agencies  discuss in detail alternatives to a
 proposed  action in an EIS, so  that a decision-maker can consider
 them along  with  the  proposed  action in determining a  course of
 action18.     Agencies  are  required to  explore  and evaluate  all
 reasonable alternatives, and devote substantial treatment to each
      1316 USC § 1456 (c) (2) .

      1433 USC §§ 1401 et seq.  (1988) .

      15Howorth, Laura  S.   "U.S. Army  Corps of  Engineers'  Ocean
 Dredging  Policy  and   its   Relationship  with  the  Coastal  Zone
 Management Act",  Our  Coastal Experience:   Assessing  the  Past,
 Confronting the Future. The Coastal Society, 1993.

  ~    "Letter  from Jeffrey  R. Benoit, Director,  MCZM;  to  Julie
 Belaga, Regional Administrator,  EPA, dated November 13, .1992 .  [See
 also note 11] .

      "See note 11.

      1842 USC § 4332(2) (c) (iii) .

-------
reasonable alternative19.   The examination of alternatives must go
beyond merely justifying decisions already made20.   Mas.sport and
COE  have failed  to  explore  sufficient alternatives  to /dumping
contaminated  sediments at MBDS.  All of the preferred alternatives
involve   ocean   dumping  within  a  fairly  restricted  area  of
Massachusetts Bay.  Land disposal and other options were  dismissed
as preferred  options  solely on the basis of cost.

     This undue  emphasis  on the costs of disposal constitutes an
inadequate  examination of alternatives.  Economic  arguments for
open  ocean disposal  do  not  adequately  consider  the  potential
environmental damage and related costs of disposing of  significant
amounts  of highly  toxic  contaminated  sediments.    The  COE must
adequately  consider  the  cost  of damage to  marine  habitat and
resources;  such  as  costs  to the fishing industry, and to tourism
 (e.g. whale watching) .

     The  DEIR/S  inappropriately  uses  the  cost of  unconfined
disposal  of  dredge  material as  the basis  for their  economic
comparisons of alternatives,  even though such disposal  involving
contaminated  sediments is  not permitted.   Additionally,  as the
DEIR/S itself acknowledges, caps may have to be replaced  every one
to four years due to storm damage, entailing additional expense.
The  DEIR/S should  be revised  to consider  the cost of confined
disposal, in order to provide  a more realistic and  balanced picture
of costs  involved in  disposing of material at MBDS.
 PROTECTION OF THREATENED AND ENDANGERED SPECIES AS REQUIRED BY ESA

     There are  a number of  species protected by the ESA which may
 occur  in the disposal  area.   They  include:   humpback whale, fin
 whale, northern right whale, sei whale, blue whale, leatherback sea
 turtle  (endangered),  loggerhead sea  turtle  (threatened),  and Gulf
 of Maine harbor porpoise  (proposed as threatened.)  In addition  to
 the  endangered/threatened  species  themselves, prey  species for
 endangered   whales  have   been  spotted  within   the  two   mile
 circumference  of MBDS,  increasing  the likelihood  of the whales
 entering  the area.   Under Section 7 of the ESA,  federal  agencies
 are prohibited from taking actions that adversely impact endangered
•or  threatened  species.  Specifically, federal agencies_must  "...
 insure  that  any action authorized, funded, or  carried out by such
 agency  ... is not  likely  to jeopardize the continued  existence  of
 any  endangered species or  threatened  species or  result in the
 destruction  or  adverse modification  of habitat of such
      "40 CFR § 1502.14.

      2040 CFR § 1502.11

-------
species  	"21  The disposal  of  contaminated sediments in an area
frequented by  endangered and threatened species has  an obvious
potential to cause the species serious harm  (e.g. direct exposure
to contaminants,  habitat degradation, decline in water  quality, and
entrainment of prey.)  The DEIR/S reflects inadequate consideration
by Massport  and  COE  of the potential effect of  their actions on
such species.

     The biological assessment conducted by the COE concluded that
there  would  be  no  adverse  impact  on endangered  and threatened
species  within MBDS from  the disposal  of  contaminated material
controlled by  capping.   However, it was admittedly based on the
Biological   Assessment  and   Technical   Appendices  prepared  by
Massachusetts  Department  of  Public Works  and  the  COE  for the
Federal Highway Administrations Central Artery/Third Harbor Tunnel
Project  (CA/T),  which  was alleged to have  similar impacts.   The
CA/T assessment  however, never discussed the potential effects of
capping  contaminated sediments.   The failure to give sufficient
consideration  to the  possible  effects  of  capping is  a serious
deficiency in  the COE biological assessment.

     Furthermore, the National Marine Fisheries Service (NMFS) did
not  concur  with the  COE  determination.    NMFS  felt  that the
assessment left  a number  of concerns unanswered, including:  the
efficacy of  capping  under the environmental  conditions present at
MBDS   (including waters  up  to  100 meters  deep) ; the possible
cumulative  effects  of specific  contaminants from this and  other
projects on  listed species;  and  the potential  for  contaminants to
bioaccumulate  or transfer through the food chain22. NMFS  concluded
that additional  information was necessary for the formulation of  a
biological opinion under Section 7 (a)(2)  of the Endangered Species
Act.

     NMFS then recommended that  COE either agree to extend  formal
consultation until sufficient data  (including an in situ study of
cap placement  over time using clean material) is available, or drop
capping at offshore  sites  from further  consideration. _ Any  action
contrary to this recommendation would be  a violation  of the
Endangered Species Act.  This is  an additional reason that disposal
of contaminants  at MBDS  should be dropped  as one of the preferred
alternatives.
 CONTAMINATION OF COMMERCIAL FISHING STOCKS
      2116 USC § 1536.

      22Letter from Allen E. Peterson, Jr., Acting Regional Director,
 NMFS, to Colonel  Brink P.  Miller, Division Engineer,  COE,  dated
 April 19, 1994.

-------
                                8

     The  DEIR/S does  not  give  adequate  consideration  to the
potential consequences  of dumping contaminated materials -in or.near
active  fishing  grounds.    Red  and  silver  hake  are abundant,
commercially important seasonal migrants  in the MBDS area,  along
with flounder and grey  sole.   The transfer of contaminants  through
the food chain is an acknowledged'health risk.

     In expressing  concerns  over the Boston  Harbor project, the
Environmental Protection Agency  (EPA)  stated their assessment of
the effects on human health  from the consumption of seafood from
MBDS exposed to contaminated  sediments indicated that  "disposal of
the surface sediments  ... could pose unacceptable cancer risks to
human health."23    EPA  found that  even  incidental  exposure of
contaminated sediments to MBDS  seafood  could  pose unacceptable
health risks.24  EPA's calculations: for cancer risk associated with
the consumption  of  seafood harvested  from the  MBDS  if Massport
sediments were to be disposed exceeds values within  the  acceptable
range.25   The  DEIR/S must be  revised to reflect consideration of
the  potential  public  health  risk  involved   in  disposing  of
contaminated sediments at MBDS.                                 	

For the foregoing reasons we  request  that  the DEIR/S be  revised to
comply with the National Marine Sanctuaries Act, the Coastal Zone
Management Act,  the National  Environmental Policy Act,  and the
Endangered Species  Act and to reflect public health concerns;  to
indicate that the MBDS is not the preferred' alternative for the
disposal of contaminated sediments;  and to adequately  develop less
harmful alternatives.

     Respectfully Submitted.
Jack/ Sobel        /
Director, Habitat Conservation
Ma:£garet M. Lytle"/)
Associate Counsel  ^
     23Letter from Paul  G.  Keough,  Acting Regional Administrator,
Environmental Protection Agency to Colonel Brink Miller, Division
Engineer, U.S.  Army Corps of Engineers, dated September 9, 1993.
     24Id., Appendix C.

     25Ibid.

-------
E3-1

       The disposal site alternatives analysis has been reevaluated for the FEIR/S (Section 4).
The MBDS is not considered to be a suitable site for the disposal of contaminated silts from
the BHNIP. It could be considered for future maintenance material only if capping is
successfully demonstrated to provide long-term isolation of these sediments from the
environment in waters of similar depths.

       The Corps has submitted a Biological Assessment to the NOAA, National Marine
Fisheries Service regarding disposal of dredged material at the MBDS.  The Biological
Assessment does not anticipate significant impacts to threatened and endangered species at
Stellwagen Bank. NMFS coordinates these activities with the manager of Stellwagen Bank
National Marine Sanctuary.  Any proposed capping demonstration at the MBDS would be
coordinated with the appropriate agencies.
E3-2

       Any proposed capping demonstration or project at the MBDS would be coordinated
with the MCZM office to determine consistency with their policies on a case-by-case basis.
E3-3

       Over 200 alternatives were initially examined for the disposal of dredged material.  A
systematic tiered system was used to narrow the list of alternatives to a reasonable number for
analysis. MBDS was selected as one of several alternatives for the disposal of silty dredged
material in the DEffi/S (although it was eliminated in the FEIR/S).  This certainly complies
with the intent of NEPA.  In addition, cost (or practicability) is recognized in NEPA and other
regulations affecting dredged material disposal as a means of comparing alternatives.  An
accurate environmental cost from disposal of silty dredged material, if any, is impossible to
analyze.  The purpose of an EIR/S is document environmental impacts from various
alternatives so that managers can make an informed decision on selection of an alternative.
E3-4

        The final Biological Assessment will drop capping contaminated sediments at MBDS
as an alternative.
E3-5

        The risk assessment conducted by U.S. EPA was based on very conservative estimates
because of the lack of information needed to make a more accurate assessment.  U.S. EPA's
MBDS site designation EIS concluded that disposal of dredged material at the MBDS has not
and is not likely to cause significant impact to aquatic resources.  This is after many years of
disposal of dredged material from Boston Harbor and other urban harbors.

-------
                                        APPENDIX B
2399S/R4.XS 1/31/97(2:46 PM)*PT/6

-------
                                                                                                                                                                                                                                                 in in  i    1 innin i     11 inngnlii n
   III   II  |  (III  Illl    I    111     II   N   i    (III
   in ill i   I  ill  i II    III i nil
                                                                                                                                                                                                                                                    111   i    I              ill
                                                                                                                                                                                                                                                                                                                                                                                            11      !
    I III  I  Illl  Illl I  111 Illl
 I  fiipiiiiiiiihii'iiiiiiiiiiiiiiiiiiiiniiiiiiiiiiiiiiiiiii'hiiiiiiiiiii'i1  f".'.,,';"/  "»ii,l  liiiiiiiiiiiiiiiuiiiiii'.iijiiiii.uiii'i "uf iiiiiiiiiiiiiiiiii!"':'iKii «' ,   iiii«i£ii! s'1

 |  ilLii'iailllliilllfllESiE;,'!111 Illpfllll':•  i";!11!!•;:'„'!'  tBblJIii  il!i;i!,!1!ll!!1,! ,;i  Bliii'M,:!.!i,i,,,,""ffj !™ :"'    mttR  '',	If ffi!1!,'"' .'''''i,11"111:!!1!;'!,:!"1!":^"'!!1!"''!;'^!!.!!!]!,11' ill'1:!.!!!!	  '•,llf'.'lf  f*1,1!!':1!11!1"  "it|l!J^^                               ijAaiiNjiS'iiiili'iiii'iii'lt.''/!!*111!!!1111 • 'lij^iiiiiliiliiilll'i'lnl!!1-''!,1,'! iWW'11,  '«:' ii!1:!1!11!1!'i'i'li1, '»!;;:'!:!,• i:!"'  • ' '/i1, ,:,'„ iil1"!'




•l l!!liyi!:'i«1!:;1n!iliK!i!lniiilU'i|l,nliti!l|i!lll  'iiiE'iip!	" >„!  lililllili1!,,!1'!!1:!   ,:i,i,i|i,ili!i,i  i,:*, "ifr?:!';;:  i|i,!  iillllllf  ,,,rS'S^ • <  ', i,  "il'"i'''i!',i, ill1 ,iH',i	NK  "S';1:!!!,!;!"'1!11:?!1!"-'!1;'Ji,:11.;;	,  'j'L'.ini,:	iijiWiXT',  Pi'.iliilrm1''frSSuni  Pll^l^K^^                         :U!lil!&^^^^              i   ,    I,:''-,"!'	, i;:,:1'1:,:.,''.,!'.,"    ,  '  :<•'!  P
                                                  "	ir	,,	' i<	i	innini  i  ii ',ii,,r,i;	„  " <  ,	I'l	ill 'ilmi,, t , •	•  <	in r   i	Ii, i,»ii» «i, niili	,i ',',1111,1,,	,,il,' ni	„ •	,	<	,,iii'f	,i|,, i	<•	,,, iiiilli, i|'i	I	V "	ill  ,   , n, ,„ <	 « M, „ „ „  • ,  l   	n",    	









                              IV'ilnlS'inni'!',,  inniniiiilhl	Pint  "It1!! .ilPdnnfnjhli'j,',!1!1	Ini,'"*!!!!*;:!;;;''!,"1 Jn;,,  l''l||!ji|jl!,ji, f'^'lfrifvSsilfV;!1,!,;^                    I*!!!!:,!;;!*;1'; "''lii!!,!1!1'',,;! f^'yf	II1!  ijAiiiiiPfl^JiiPllli^t:'1^   !| 'KlL 1J '*•• >:ll,>l'i!"!,  I'! 'f^f':  >!l "Ii"!"!' I1'!!	i;!,"!:,,1:1'!1:'", ' ^"'ElSJiPin,',,';: '"  !•! if"!1  ">i:"!!'«:  :ifi i  ,'   :',  I'!'',      :,!i',    '     ,   "t:,'}




                                                          iinii in,  [,' iiiiiiiTPiiiiii!!,in,"i"i,|i,i,,i,,i,i'iii:i!iiijiP: "in  ''im ,„, iiiiiijiilijiii,  ,  'Hti'it, cnii, ,i,iii	''iiiiiiiiiiiiiiiiini'Tiihiiiii1 liiii'iiiinr,' jijuiiniiiiiniiii ,,ii,' ,"ii	i,iiii,ii;i  ii,,  n,1,1111,,  »',ii sti"^'",^^^:'''^'!!!.;)!'1 iiiiiii'ihHiiiiiJiiiiiiMin1 iim,iii iinJMii,  iffiniiii,1!1, ,1':  i	: 1,1*  ..'''pi'iiij1,!  n   "r, iLiiiJiii,1,!'!;  ,, |MI ,,;' i,    ,	,:,  ,''•,"  ,,i,iii'', 11,,,-   ,1,1',,        , IM ,, •

                                                           asiSi:,,:," • ii1,,,; in, in • i, y f" :::rm /!,/  •,',: * i,  ,,diiiiiiiiii||i|ii i:' n  • ininiiiiii i, '* 71>"", 'si'siac!11" s VK n FSMI • 11  liai1,,!1 niiini1' ,Mi n yi tn i, „ 'IT • i ni!:1!1!! "'jhi:: ''Pn!!:,a' ''xipin s'lini1!11'yiii	ffjx ,,i • tnn i; i •'»,',',«,,  10IJ.V!!!,;" \  ni	n; nnn;,, i1'"' i • f,;	PI  .I'liiaii/ini1',',,; ,, i n  :• .'ip1, ,„ > 11, •' i 'i.'  i,  "   <; •>, •,;,",, n  •  ,        . i;  «


 | iiili: iiiiiiii liiiniiiiiiiiipi iiili 'niiiiiii^ iiii!l'i,('':'  fvm': Hi"','' m" •	: ,:!'ii'' 1 P1 •'' :''l	' iijiiN' 4'   i' i":i!,"  ii:1  '• "„: i	i    '''!"• :<"' ,i i <::  'I'  i"!!1         «  ,'t i  i"'







                                'i  i nn, li:, i,; l  < M >, nillllllllfilll'' Inw	I! l  ..PPi,,,,!,,!"'!'!'! Ii iliii ii!,p'i „ I	luliii m.ii' '  ' ,i!,i 11  "Illliilllill jjjlpll ri il'l |ll'P!li»	II'i ,,»l liljli', J li'lliJUlliii' 'I'nil'iliii In ,l,nl|| lii! illin,'   iiPiiillilliPillli'li11 IP1' ji'ii ' :iin",,i"i "il1 ' in I, inilmi iSVi' IIP lilPP'inilldl iliir Pi I	Phi,,'!: P|i« li|,l Jm l|i|iiil|i,,',|i  ''' d>' libiiln'milii'lui, II'V l,,,ii, llul, i1; 'f |i 'i:>lni'"li >, ;J|'; i ,,,iiiliil,iiip!i:,|i,i,  "K  i     ' |,'     ' «| ,».' I11  '    !'   'i  ,1, !,!',  iJI'    ,  '   , n'i  :  ii




                                 ,   ,;;:;;,;!,,-|::  •,:  -;:;;;;;,,,;,;;;:;,  ,,,;;', ;•:,  ,,  ,;,, „,, ;„,,;, „,,,,  •;, ,;•	,,, ,;,,,;   ,  ill|;||,||:|;|;|,,,,, „;,,;,,""  ,:;,;',:,  „„,,,,,;,	;;,;,;,;',;",;,;:,,;,;;,,„;,;,„;,  ,„!,,!::,:,:,,,;;;;;;! ,,;;„„;• • • „;;,	„  ,„;,,;;:, ,,;„;;,;  ..m;,;,;', i;;::,::|!j,i, ,::,„	•  ;,;,;',;,,;;	,,,:,:,;;::;;,;,,;;,! i i,|1;;;,,,,:,i::,:,,„:,;,;;,,:;,	;,„:;, ;,,,i;,, ,;,,;,;,;,, -   ,, „$$$•,;;;;;,    ,,,  ,   :,   ,,„;„,,,;:  ,,„,,,;:,',   ,„;;;"   ,'   „,,,",„„,




                                                                                                                                                                                                             	iHviipL'iii'ipi'in,;,,,:!;,^                                                   ' ,     i    ,'ii1'  i'   -  ,  ;   •    ,  ',!,•  JSP   ••     •   ,    ,

                                                                                                     ;:::p	:'.".'.:.::::::.:	::	:,"'	:::  :::;:\,::::::;::::::::;::',:	:::•..::	:;:,..;	±;:;	::   :„:;	,;:;:,'    :.:      .'    ...   ',      '    "
          ,,,„,,,  ,.	„,,     „          ,  ,,         ,.              ,,„	...	,	„„,    „    ,,„,,.	.	..	

  I  :„;,„;	,	I!	;	;,;	I,,/	;	:	,	,	'.	;	/.JjjjjJ	;	;	;	;	,	'	-	v	I!	;,:„;,„;,:	[,	,;„;„,„„;„„	\	'L;   	;,;,, ,  ,„	::;,„;,,,:;	\   (	  ,
  i  -J;;^^^                                           ^i;-;i ;• i	;;;"";;••  ;;•;;	i1-;:;;•  -'—" -Jjafl;  '!;	;:n;'";;	I	I"";;1"j';;j";	ITJIIJ;;	""''"il|ii|'  ;•„:	i['	;	;"";•"*' g^iini^niiij^^^

-------
E3-6

       The MBDS is not being proposed for the disposal of silts from the BHNIP. Capping
would, not occur at the MBDS until a demonstration to prove its efficacy has been completed.
E3-7

       The cost comparison for the disposal alternatives has been based on the cost for the
least environmentally damaging alternative, in-channel disposal in the FEIR/S.

-------
              Cetacean Research Unit
Col.  Brink Miller
Division Engineer
Army Corps of Engineers
424 Trapelo Rd.
Waltham, MA C2254-SI4S
                                        June  11,  1SS4
Dear Col. Kille
          Me thank you for the
                                           to offer
 :ne
 the la:
 » f  ^ v-, r*
 . e, oa^t-
.nee red
   nque
he
roxi;
Project.
project .

     •"he Cetacean Research Unit (CRU) is a non-profit orga
emphasizing research and conservation on whales  ana marine
InSland   For the past 15 years,  our work has  centerea on
Stellwagen Bank National Marine Sanctuary   ?« h£e c>?;^:
databases or the natural resources of that area  i~ ex-s.e..
c?e«" woreciate why the location is so special for enaa
whales  and" a mvriad of marine life.  It is Because of tna.
nature  that we" feel extreme care must be taken _in use of t
Massachusetts Bay Disposal Site (MEDS), locates  in c:ose ?
the  Bank and its marine resources.

      T  4. ^e sta-t by saying that we are not opposed  to  the  creasi
t^e  ha-bor cer se.  We  realize and appreciate the  importance  o=
c^rc-c?a^ traffic in Boston harbor to  the area's  economy   r.owev
Sr£lso~Uel that it must be done  in the safest, way  possible  for
environment.  For years the harbor 's sediments ,*»ve  oeer.  <=^--
from a myriad  of  abuses and much  of  the arecgea ir,etert«.:  espec-a
the  su-face  silts, contain toxic  levels of certain ppiiU-a...s.  ^
Because of  this,  e.xtreme  care  must be  taken when botn arecging  ,n
harbor and.  especially, disposing  of those sediments.

      The DEIS  is  inconsistent  in  its. classification of  the surfac
s^*s   In most  places,  they are  classified as  contaminated ma.e.
We'a^ee Si?h  this  classification,  but feel it  neecs to oe extenc
 throu^out the document.   As contaminated sediments  it wou, a oe_
 illegal to dump  them at the  disposa, site.  Wnen the EPA oes:g..^
 that site for  open ocean disposal, they stipulates it was on.y re
 "clean" sediments.
                                                                 ges'
                                                                 car.
                                                              ''.it"  t;o
                                                                 ng  *•

                                                                 e
                                                                 e
                                                                 ia.s
                                                                 ed
               P. O. Box 159 • Gloucester MA 0193O • 508 281-6351
         A non-profit organization emphasizing whale research and education

-------
      In several  cases  in  the DEIS there  is  a  recognition that
 be impossible  to dump  the surface silts  at  the MBDS without  a
 clean spoils placed  over  theft.   Before this can be considered.
 demonstration  of effective capping at that  site needs to take ?
 In order to be considered an "effective" cap, both the-amount o:
 coverage and the integrity of the cap would need to be shown in
 short run and  over a prolonged period of time (at least a numbe:
 years).   Given that  the schedule for the BHNIP calls for faster
 than  that, we  feel that such a demonstration  is unfeasible fo
 project.
                                                 it would
                                                 "cap" of
                                                  a
                                                  lace.
                                                   action
                                                  this
 there is little reason to believe that a cap can be
the deep waters of the MBDS,  which are typically over 20C
      Further,
 effective  in
 feet.   In  the  one  capping demonstration  attempted in the  early  iSSO's,
 no  effective caps  were  created at  the  site.  Given the swirling
 currents and mid-water  turbulence  at MBDS,  one  could only  expect  a
 wide  spreading of  any sediments dumped at  that  area.  The  suggestion
 in  the  DEIS that a cap  would be maintained by careful positioning of
 the dumping barge  is naive and laughable;  daily variation  in  tidal
 states  and wind conditions would obviously cause sediments dumped or.
 the same spot  to disperse in different directions.

      We feel the most insidious suggestion contained in the DEIS  is
 using the  sediments from the BHNIP itself  in order to test capping.  A
 capping demonstration must take place  using clean, marked  sediments
 capped  by  other clean sediments with a different marker;  the  idea of
 using the  surface  silts as any part of a capping test only risks
 environmental  disaster  if and when the cap is shown to fail.         .—

      Why do we need to  worry so much about dumping contaminated
 sediments  at the MBDS?   Contaminants such  as PCS's, which  are
 prominent  in the surface silts, have extremely  long half.-lives  in
 water.  Further, as they go up the food  chain,  they bio-accumulate
 potentially leading to  dramatic exposure levels in the marine life
 the area.  According to one recent report,  PCB  levels at  the  M3DS
 quadrupled since 198C.   Since much marine  life, including  marir.e
 mammals, are particularly vulnerable to  toxicant exposure, particu
 care  must  be taken to minimize this exposure.   This exposure  car.  t.
 place through  two  means.   Fin whales,  humpbacks, and right whales
 all shown  to use the area near the MBDS  in some frequency, as
 demonstrated by the plots from our data  presented in the  SPA's  Sec
 7 consultation (Appendix in Volume 2).  Further/ prey exposed to  t
 chemicals  can  leave the area and move  to Stellwagen Bank,  one of  t
 most  important areas for endangered whales in the northeast.

      We -strongly feel that dumping of  contaminated surface silts,
_any other  contaminated  sediments,  should not be allowed or even
Considered at  the  MBDS.  We encourage  you  to delete any and all
 reference  to this  possibility from the Final EIS.

      We also feel  that  the dumping of  toxic sediments in  the  open
 ocean is a situation which is less than  ideal.  We support using
 upland  disposal or disposing of the sediments in an already
 contaminated part  of the inner harbor, where marine wildlife  are  not
 likely  to  be affected.   While we realize these  options cost mere  in
 the economic analysis of dumping presented in the DEIS, that  analysis
 does  not take  into account the costs to  fishermen or whale watchers  of
 having  reduced levels of marine life in  the area, or the  non-.^.  .
                                                     .lave

                                                     1 ar
                                                     a>ie
                                                     are
                                                     or

-------
quantifiable costs to the environment which could result from sucr.
actions.

     While we are resigned to the dumping of non-toxic sediments at
the MBDS  (although we have felt all along that no dumping should take
place at  that site), we feel that rigorous testing of ail-dumping  ^ ^
materials must take t>lace.  The ocean works in a series of fine-sca.e
micro-habitats, and it is not safe to assume that even those seciments
in close  r>roximity to clean sediments are, themselves, clean.
Further,  even "clean" sediments can impact the ecosystem, since tney
are by no means pristine, and non-toxic levels can be accumu-i atec
through the food chain.

     Finally, we feel that it is important that care be taken in the
actual dredging process.  Much material is spilled during the crecging
•orocess,  resulting in re-suspension of toxins.  Because tidai fiusr.ing_
of the harbor takes place on a regular basis, this also offers tne
opportunity for introduction of toxins to the Massachusetts Bay
system."  We would suggest that performance standards be set for
dredging  operations, especially in the percentage of dredgec materia.
landed in the barge.

      In order to insure  compliance with both disposal and dredging
requirements, we ask that an independent  contractor  oversee anc
monitor all chases  of the BHXIP.  This contractor should a.so ccna^ct
training  sessions for all dredge and  barge operators, tnrcugr. wr.icr.—
environmental requirements  are detailed fcr  operators.
Inconsistencies in  past  disposal operations  necessitate  sucr.
independent review.

      Finally, we note  one omission  from the  DEIS.  The  designation of
the  Stellwagen  Bank National Marine  Sanctuary  by  Congress  requires
that  all  activities, which have the  potential  to  effect  sanctuary
»-*esources take  place  in  consultation  with the  sanctuary manager,  ir. _
th-=s  case Mr.  Brad  Barr.  We note  that  there is  no  reference  to  sucr.
consultation  taking place,  nor is  there  reference to them being  sent s
cony  of  the DEIS  fcr  comment.  This  consultation process siicuic.  necin
immediately.

      We hope  that  you find  these  comments helpful.   We  lock fcrwsra '
insurinc  that the harbor is dredged to the point which insures  a
viable economy fcr  the New  England region,  while insuring protection
fcr  New England's valuable  marine  resources.

Sincerely,
 Has on WejUrtJt-c"h
            i rect 03

-------
E4-1

       The FEIR/S considered all silts from the BHNIP to be unsuitable for unconfined open
water disposal.
E4-2

       Capping would not occur at the MBDS until a demonstration to prove its. efficacy has
been completed. MBDS was selected as a disposal site because of its deep depths and low
energy level.  Research (DAMOS) has shown that the material disposed at the MBDS forms a
mound, currents have minimal effect on sediment as it falls through the water column.  A
capping demonstration would be discussed with appropriate agencies before it was initiated.
E4-3

       DAMOS research has shown, as well as the U.S. EPA MBDS site designation EIS,
that the site does not cause a significant affect to the marine environments.  The EIS did not
find significant PCB concern at the MBDS.

       The disposal site alternatives analysis has been reevaluated for the FEIR/S (Section 4).
The MBDS is not considered to be a suitable site for the disposal of contaminated silts from
the BHNIP.  It could be considered for future maintenance material if capping is successfully
demonstrated to provide long-term isolation of these sediments from the environment in waters
of similar depths.
E4-4

       The silt portion of the dredged materials is considered unsuitable for unconfined ocean
disposal. The preferred option is now in-channel disposal, which is considered the least
environmentally damaging practicable alternative.
E4-5

       We acknowledge that the CRU accepts the decision to allow the clean parent material
to be dredged for the BHNIP with disposal at MBDS. This material has been tested and has
lower concentrations of parameters of interest than ambient conditions in Massachusetts Bay.
Therefore, its disposal at MBDS should pose no chemical threat to the surrounding ocean
environment.
E4-6

       Precautions will be used to minimize environmental impact to Boston Harbor.  The
proposed dredging and disposal activities will be performed in accordance with any conditions
established by the permit documents. Please refer to the Dredged Material Management Plan

-------
(Section 5.0) and the rest of the FEIR/S, including the model studies.  Also, contaminants are
attached to sediments and do not easily go into solution.
E4-7

       Observers may be allowed on board but can not control the operation. The concern
for the Corps is an issue of contract control.  The Corps cannot allow dredging contractors to
take orders from others without approval of the Contracting Officer.  The Corps inspector on
board can be made aware of any violations. Pre-construction meetings are held regularly with
new dredging contractors. At these meetings environmental permit compliance will be
emphasized.

       The FEIR/S has recognized the importance of operator qualifications to the successful
completion of the proposed work. Section 5.8.2.1, Operator Qualifications, addresses the
specific environmentally sensitive procedures which will require exceptional operator skills.
E4-8

        The manager of the Stellwagen Bank National Marine Sanctuary has received a copy
of the DEIR/S.  Coordination occurs through the National Marine Fisheries Service.

-------
COASTAL ADVOCACY NETWORK
c/o Massachusetts Bays Program. 100 Cambridge Street. Room 2006.
Boston, MA 02202. yHone: l-800-W7-BAYS.;iu::'.6l7} 727-2734
                                             June 21. 1994
                                          RECEIVED
                                         <4UN 2 1 1994
                                            MEPA
   Trudy Coxe. Secretary
   Executive Office of Environmental Affairs
   MEPA Unit
   100 Cambridge Streu
   Boston, MA  02202

   Brink P. Miller. Colonel
   U.S. Army Corps of Eng?  -  ::
   424 Trapelo Road
   Waltham, MA 02254

   Dear Secretary Coxe and Ce.cnsl Miller,

   The Coastal Advocacy Network, consisting of local  or  regional environmental  advocacy and
   educational non-governmenta! organizations, is dedicated to the protection and celebration of the
   marine and coastal resources of Massachusetts and Cape Cod Bays.  We are writing to express our
   common concerns about the draft environmental impact statement/report (DEIS/R) submitted by
   Massport and the Army Corps of Engineers for the Boston Harbor Navigation Improvement Project
   and Berth Dredging Project (BHNIP).

   Our major issues regarding the BHNIP are around the dredging process itself, and the handling and
   disposal of sediments, many of which are contaminated with heavy metals, PCBs, PAHs and other
   toxic materials.

   The Dredging Process

   From experiences at Moran Terminal,  we learned the dredging process can be very messy.  When
   debris prevented the clamshell dredge from closing properly, sediments spilled  into Boston Harbor.
 '  We would like to see the entire dredging process monitored by an impartial observer with the
   authority to bait dredging that is in violation of permit conditions or otherwise environmentally
   dangerous.  Also, we would like contingency language placed in any contracts for dredging and
   disposal which  would require work to halt should problems  occur. Also, we would  like to see
   performance standards for dredging put into the Dredging Management Plan (Section 4.0) rather
   than descriptions of equipment and methods. This would ensure a clean and safe dredging process.

fH Handling and Disposal of Contaminated pediments

   First, in regard to sediment characterization, the U.S. Army Corps of Engineers has found that all
   maintenance materials (silt), except 160,000 cy from Reserved Channel, and 200,000 cy from berth
   areas of Gulf Ofl. Army Base, Conley  terminal,  and the Edison  Barge berth, is unsuitable for
   unconfined  open water disposal. The  U.S. EPA has conversely found  that aH. sflt material is
   unsuitable for unconfmed open water disposal.  It is our opinion that the  sediment chemistry and

             Th« vww.of th» Couul Advocacr-Necwork do not o«co»*njy npraMnc the** of tfa* «MMcbu»«a» B«y» Program.
                                                                    'ft

-------
            bioaccumulation test results indicate that none of the silts are suitable for open water disposal.
                                                                                       J
r
We are absolutely opposed to any open water disposal - including disposal in borrow pits
of contaminated sediments. We would like to see a portion of the contaminated dredge spoils set
aside for a pilot project that would test the efficacy of alternative technologies in reducing toxiciry
of contaminated sediments.  GeneraDy, we would like to see clean sediment used  beneficially to
uperade habitats and already contaminated areas, wherever possible. Our goal is to minimize damage
to and exposure of contaminated sediments to the marine environment as much as possible. To that
end. we cannot support any of the preferred disposal alternatives delineated by Massport and  the
Corps in the DEIS/R. Therefore, we TTOVId like the final impact statement to reexamine tV
"potentially practicable" disposal  alternatives, especially the "shoreline" and "in-channel"
options.                                                                               —

In addition, we have  the following specific "-omments:

       - We absolutely will not suppoii ai/y disposal option which would require a waiver
       from  Section  103(d) of the Marine  Protection, Research,  and Sanctuaries Act
       (MPRSA), or any other legal waiver.  It is currently illegal to dump contaminated
       sediments at  the Massachusetts Bay Disposal Site (MBDS) without a waiver.  The
       Coastal  Advocacy Network is particularly concerned about this potential
       option and  will not  under any  circumstances  condone  disposal  of
       contaminated sediments  at  the  MBDS -  including capping with clean
       sediments. We oppose any pilot project at this location. The MBDS is adjacent to
       the Stellwagen Bank National Marine Sanctuary, one of our most important  natural
       resources  in Massachusetts and Cape Cod Bays and must be protected.

       -  At this  point, the DEIS/R is unclear in its  description of the MBDS as a disposal
       alternative. At some points it describes the MBDS as a preferred alternative for both
       clean and contaminated sediments and at other points it does not. The final impact
       statement must be very clear in its prohibition of disposal of contaminated sediments
       at the MBDS.

       -  Disposal sites  of both clean  and contaminated  sediments must be carefully
       monitored by an impartial observer(s) with contingency plans, should problems occur.
       The costs of this monitoring are not factored into the cosUbenefits analysis of the
       disposal options.  These costs must be considered in the final impact  statement.

        - In addition, the costs of using certain disposal alternatives to other resource  users
        (i.e.  fishermen, lobstermen) were  not considered  in the discussion  of disposal
        alternatives.  These costs should be considered-in the final impact statement.

        - The disposal site(s) chosen for the Boston Harbor Navigation Improvement Project
        must  not be used for future maintenance  dredging and other regional dredging
        projects until the sediment quality and environmental impact of those  projects are
        analyzed.

 Lastly, Massport and the U.S. Army Corps of Engineers should be conscious of the other projects
 and problems in  Boston Harbor in their planning and in  their preparation  of the final impact
 statement.  These include: the  Harbor Clean-up and the proximity of the sewage outfall to the

-------
proposed sites, tbe Central Artery Tunnel project, the recent designation of SteUwagen Bank as a
National Marine Sanctuary, the existence of highly contaminated - and sometimes radioactive -- 'hot
spots." and a very strained fisheries situation. All of these will affect, and be affected by, the dredging
project.   Massport and the  Corps should work  closely with other affected panics,  and the
organizations in the Coastal Advocacy Network, to devise creative solutions to deal with contaminated
sediments that will benefit Boston Harbor as both a natural and an economic resource.
Thank you for the opportunity to make these comments.  We  look forward to reviewing the final
impact statement.
 •
-------
E5-1

       Observers may be allowed on board but can not control the operation.  The concern
for the Corps is an issue of contract control.  The Corps cannot allow dredging contractors to
take orders from  others without approval of the Contracting Officer.  The Corps inspector on
board can be made aware of any violations. Pre-construction meetings are held regularly with
new dredging contractors.  At these meetings environmental permit compliance will be
emphasized.

       The FEIR/S  has recognized the importance of operator qualifications to the successful
completion of the proposed work. Section 5.8.2.1, Operator Qualifications, addresses the
specific environmentally sensitive procedures which will require exceptional operator skills.
E5-2

       The FEIR/S considered all silts from the BHNIP to be unsuitable for unconfined open
water disposal.
E5-3

        The silt portion of the dredged materials is considered unsuitable for unconfined ocean
disposal.  The preferred option is now in-channel disposal, which is considered the least
environmentally damaging practicable alternative.  Thank you for your comment. A dredge
material disposal pilot project is addressed in the FEIS/S., and beneficial use of clean dredged
material is also  described.
E5-4

        The disposal site alternatives analysis has been reevaluated for the FEIR/S (Section 4).
The MBDS is not considered to be a suitable site for the disposal of contaminated silts from
the BHNIP.  It could be considered for future maintenance material if capping is successfully
demonstrated to provide long-term isolation of these sediments from the environment in waters
of similar depths.

E5-5

        See response to comment E5-4.  MBDS is being considered the preferred alternative
for the disposal of any parent material (clay) that is not used for landfill closure.
 E5-6

        Observers may be allowed on board but can not control the operation.  The concern
 for the Corps is an issue of contract control.  The Corps cannot allow dredging contractors to
 take orders from others without approval of the Contracting Officer.  The Corps inspector on
 board can be made aware of any violations.  Pre-construction meetings are held regularly with

-------
new dredging contractors.  At these meetings environmental permit compliance will be
emphasized.
E5-7

       The impact to resource users was considered in the disposal site alternatives analysis
(Section 4).
E5-8

       All dredging projects are always analyzed for sediment quality and environmental
impacts to ensure compliance with appropriate environmental regulations.
E5-9

       The Corps has met with staff from the CA/T and MWRA projects. Massport and the
Corps have also met with several resource groups after the release of the draft EIR/S.  These
included lobsterman and fisherman groups.

-------
CLF
Conservation Law Foundation
                                                                             22 June 1994
       Brink P. Miller, Colonel
       U.S. Army Corps of Engineers
       424 Trapelo Road
       Waltham, MA  02254

       RE:   Draft Environmental Report/Statement for the Boston Harbor Navigation
       Improvement and Berth Dredging Project

       Dear Colonel Miller:

             The Conservation Law Foundation (CLF) would like to thank the U.S.. Army Corps
       of Engineers (Corps) for the opportunity to comment on the above-referenced Draft
      • Environmental  Impact Report/Statement (EIR/S) for the proposed Boston Harbor Navigation
       Improvement and Berth Dredging Project (BHNIP).

             Co-sponsored by the Corps and the state port authority (Massport), the BHNIP entails
       the maintenance and improvement dredging of nearly three million cubic yards of (cy) silt,
       clay and rock from federal navigation channels and non-federal berthing areas within Boston
       Harbor. Thirty-eight percent of the total material to be dredged is substantially contaminated
       with metals, PCBs and PAHs.

             While CLF is not opposed to maintaining the commercial viability of Boston Harbor,
       we are concerned that  a project of the scope of BHNIP could have serious deleterious effects
       not only on harbor biota, but also on the larger Massachusetts and Cape Cod Bays system.
       In addition, CLF believes that, improperly disposed, the large quantity of BHNIP
       contaminated sediments poses a human health threat, through the potential contamination of
       seafood.

              We therefore request that the Corps ensure that all phases of this project be conducted
       in a manner that:

              o  is verifiably environmentally sound
              o  maximizes mitigation and beneficial use, and
              o  addresses the potential long-term effects of disposal

-------
                          Conservation Law Foundation
       Before proceeding with our specific comments on the EIR/S, CLF would like to thank
both the Corps and Massport for your efforts to maintain open channels of communication
regarding this project with environmental advocacy and other non-governmental
organizations.  Including these groups on the Advisory Committee, and inviting Save the
Harbor/Save the Bay and CLF to present our views "officially" at the public comment
sessions, sends a positive message fo the public about both of your organizations.  Early
involvement also enables questions and concerns to be heard earlier in the process, an
obvious advantage when planning a major project such as this one.

       Our specific comments appear below.

Extent of Contamination

       It is our opinion that the sediment chemistry and  bioaccumulation test results indicate
none of the silts  should be considered suitable for open  ocean disposal under the Marine
Protection, Research, and Sanctuaries Act (MPRSA) and accompanying regulations. We
therefore  support the U.S. Environmental Protection Agency's (EPA) findings on this issue.
The high  spatial variability of contamination within the harbor,  as evidenced in this and
previous testing,  combined with the imprecise nature of  the dredging process make it
additionally imperative that attempts to differentiate levels of contamination in the silt be
avoided.  (Such attempts, by necessity, would need to be accompanied by additional testing
at the time of dredging to verify that what is actually dredged does not exceed the expected
contamination levels.)

       The Boston Harbor silts are substantially more contaminated than the underlying clay.    I
Again, since the  proposed alternative dredging technologies are not "surgical"  in nature, it is
vital that  any dredging, of silts close to the clay parent material  include overdredging of at
least one  to two feet of clay.  The six inches recommended in the EIR/S  (Sect. 3.4) is           i
insufficient to ensure that all the silts are dredged and that none are mixed with the clay and  	|
subsequently disposed of inappropriately.

       The EIR/S acknowledges that there is a difference of opinion between the Corps and
EPA regarding the suitability for open ocean disposal of 360,000 cy of silt from the
Reserved Channel and some berthing areas.  In fact, the EIR/S contradicts itself on what is
actually in dispute.  (See Sections 2.2.4 and 3.2.)
                                     ) PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
       Both sections, as well as Appendix G, are in conflict with a letter from the EPA to
the Corps, dated September 9,  1993, which states that:

  o    there was agreement among Corps and EPA staff that the Army Base Berths were
       unsuitable for unconfined ocean disposal, and,

  p    a total of 132,000 cy (including material from the Reserved Channel, Conley
       Terminal, Gulf Oil, and Boston Edison Barge Berth) were still in dispute regarding
       their suitability

       Discrepancies such as these should be explained and reconciled in the final EIR/S.

 Training and Methodology                                                           —

       Recent experience at the Moran Terminal highlighted the need for improved training
 on the part of'the dredging  contractor(s), something that should be addressed in the EIR/S.
 Dredge operators and other project personnel will be dealing with'contaminated materials.
 Permits should require that project personnel be properly trained and have a thorough
 understanding of the environmental permit requirements relevant to each employee's function
 prior to beeinning work.  Training and permits should also address specific practices, such as
 avoiding  dragging a dredge over harbor sediments and reducing the speed at which the
 bucket fs raised and lowered through the water column, that can lessen environmental
 disruption.                                                                         —-

 Dredging Equipment                                                                —

       CLF finds Section 4.1 of the EIR/S, the rationale for the selection of the
 recommended dredging method, to be inadequate. Although some possible criteria for
 comparing different types of dredging equipment are listed, no detailed comparison is
 actually made.  The selection of the mechanical dredge  as the single solution for this project
 is apparently arrived at through an incomplete, qualitative analysis.

       CLF believes that within reasonable economic parameters,  dredging equipment should
 be selected based on its ability to effectively minimize resuspension and release of
 contaminants into the marine environment, not simply on its easy availability. We urge the
 Corps to require a more in-depth analysis of the possible dredging technologies; and to
 include specific equipment requirements and explicit performance  criteria in Corps-permits.
                                     I PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
       Even the EIR/S recommendation to use a "modified, environmental, bucket" is too
generic.  More specific performance specifications should be included in the document,
including more thorough design and performance characteristics.  The Cable Arm 100E,
manufactured by L.B. Tanker Inc. of Pickering, Ontario, is one possible candidate for an
environmental clamshell dredge.  This dredge has been extensively studied by Environment
Canada as part of its Great Lakes program, and was found to be not only useful for dealing
with contaminated sediments, but also economical. A sensor on the Cable Arm 100E notifies
the operator of incomplete bucket closure, and a compressible seal around the mouth can
accommodate small debris without letting sediments escape.  Furthermore, its basic shape
and light weight are geared to minimize extraneous physical impact to the bottom and
resulting sediment resuspension.

       The  existence of pneumatic dredges is not mentioned in Section 4 of the EIR/S.  Yet,
they have been extensively and successfully used in Europe and Japan to remove
contaminated sediments.  Pneumatic dredges have a major advantage over hydraulic dredges:
the dredged material is much closer to the sediment's in situ density.  (The high water
content resulting from hydraulic dredging is listed in the EIR/S as a major reason for
discounting  this type of dredge.)  Papers published by the Center for Dredging Studies at
Texas A&M University classify "oozer"-type pneumatic pumps as having significantly higher
productivity than a modified (environmental) clamshell dredge, while maintaining low
sediment resuspension.  A more thorough analysis of other dredging technologies, such  as
the "oozer"  dredge, must be included in the Final EIR/S.                               __

Verification                                                                        	

       Past  dredging projects, including but not limited to the Moran Terminal dredging,
have encountered difficulties in successfully meeting permit conditions aimed at protecting
environmental resources. For example, when testing different types of dredges in the mid-
1980's, the  Corps identified a tendency for dredge operators to overload the receiving scow
in order to maximize economic benefits.  In theory, this may be prohibited by permit
requirements.  In practice, due to lack of training, perceived need for expediency or other
reasons, overloading has happened and has led to the release of contaminants back into the
water column.

       Another example is the practice known as "short-dumping," or releasing a load of
dredged material from a barge before reaching the designated disposal  site.  In the past, this
was regularly witnessed by area fishermen.   The Corps inspector program, whereby a
Corps-certified observer accompanies barges to a disposal site, has been a step in the right
direction. However, it is our understanding that under this program, the observer is paid
directly by the dredging contractor.
                                    I PRIMED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
       CLF believes there should be a trained, impartial observer not only during all
disposal operations, but also during dredging,  blasting, dewatering, and other project
activities.-  The observer must:

  o    be knowledgeable about dredging, disposal, threatened or endangered species and
       marine mammals that frequent the area, and navigation

  o    be familiar with all applicable local', state, and federal permits, orders of conditions,
       etc., especially environmental protection and mitigation requirements

  o    have the authority to halt dredging or disposal that is in violation of permit conditions
       or otherwise environmentally dangerous, and notify the relevant agency(ies)

  o    be the employee of an independent entity, i.e., one that is not a project .proponent (the
       proponent may ultimately be responsible for observer costs, but the hiring and payroll
       of observers should be handled by a separate entity)

       We also support the recommendation in Section 4.3.5 that in addition to an obseryer,
an electronic recording device be employed to confirm the location of the scow at disposal
time. •                                                                                ~~

Disposal Sites
                                                                                      *«™
       CLF does not support the use of any of the five preferred disposal alternatives listed
in the Executive Summary of the EIR/S. We urge that the Corps require the use of disposal
options that best facilitate the' confinement of  contaminants and that are near-shore or upland,
rather than in Massachusetts Bay.

       We believe the list of possible combinations of disposal sites hi the document should
 include a more in-depth and quantitative description of the process and assumptions used to
 arrive at the set of combinations listed in Section 3.4 of the EIR/S. What other combinations
 were examined and why were they discarded, specifically? The brief description of the
 factors considered is inadequate.  Other statements need to be more fully described as well.
 For example, how was the minimum additional $10 million cost for using multiple disposal
 sites rather than a single site arrived at?                                              __

        Any disposal site used as part of the BHNIP, whether it be land-based or aqueous,
 should be actively managed and monitored both  short- and long-term to ensure that the
 contaminants remain confined. We believe that  the cost of monitoring is far outweighed by
                                      I PRINTED ON RECYCLED PAPER

-------
                           Conservation Law Foundation
the potential for damage to the marine ecosystem, fishing, recreation, and public health, if
monitoring and site management is inadequate.

       CLF urges the Corps to require that a long-term monitoring plan, and contingency
planning in case of contaminant release, be included as part of the Final EIR/S.  An added
benefit of monitoring is that providing valuable information on the performance of the site(s)
may make it easier to choose sites and disposal methods in future -dredging projects.       _

       Use of sites that are already contaminated are of particular interest to CLF, as
capping with clean sediments should have a positive effect on the locale.  In addition, sites
between piers or in small channels lend themselves not only to the confinement of dredged
sediments, but also to the use of mitigation techniques such as silt curtains (assuming other
factors, e.g.,  currents, are appropriate).  It is unfortunate that shoreline facilities (such as
Mystic Pier and Amstar) alone are.insufficient to contain all the silty material.  CLF
nevertheless encourages the further study of these sites for a portion of the silty material.

       In-Channel disposal (the only alternative besides the preferred disposal alternatives
listed as "practicable"), and some of the "potentially practicable"  options, such as subtidal
disposal at Little Mystic Channel, are attractive disposal possibilities.

       We have questions about these sites, however.  For example, the EIR/S mentions the
resuspension resulting from effects such as  "prop wash" on existing contaminated sediments
in the harbor.  Yet, to what extent will ship traffic, currents and storms affect the capping
material at the In-Channel site?  This issue  (and, indeed, a more in-depth characterization of
all "potentially practicable" sites) should be more fully addressed prior to making the final
disposal choices.  The analysis and rationale should be included in the Final EIR/S.

       The geotextile bags briefly mentioned  in the EIR/S may be useful in reducing the
dispersal of contaminants during aqueous disposal.  We view these bags as a possible
additional environmental  safeguard, and suggest that this topic be further explored.

       Due to the state's-solid waste crisis, landfill use should be limited to daily cover or
final closure material  (see "Beneficial Use," below). In addition, the Moran Terminal
dewatering problems need to be fully understood and appropriate steps should be taken to
ensure that future dewatering efforts are not similarly hindered.

       Although listed as a "potentially practicable alternative," the use of treatment
technologies is discounted due mainly to the cost involved with treating the large volume of
material in this project.  We strongly suggest that the Corps and Massport demonstrate
                                     I PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
national leadership in this area by using one or more of these technologies (some of which
may not have been listed in the EIR/S) on a portion of the contaminated materials.  Such a
relatively small-scale experience would no doubt be useful in future dredging projects.

       In general, disposal that will result in the mounding of sediments on the ocean bottom
is not an acceptable solution. Maintaining the original bathymetry and restoring the native
surficial materials should help keep capping material in place, if a site is depositional.  Open
ocean disposal implies  some uncertainty about exactly where the sediments will end up. The
wide area (referred to by the Corps as an "apron") of sediments common around a disposal
mound can require unexpectedly large quantities of capping material for total coverage.
Finally, this form of disposal has the highest potential for the cap and underlying
contaminants to be eroded over time.

       CLF is strongly opposed to the dumping of contaminated sediments at the Mass. Bay
Disposal Site (MBDS), with or without capping.  We would actively oppose a request by  the
Corps for a waiver under Section 103(d) of the Marine, Protection, Research, and
Sanctuaries Act to proceed with disposal of contaminated sediments at the MBDS.

       Both the EPA and the Massachusetts Coastal Zone Management Office (CZM) have
made it clear that contaminated sediments should not be disposed  of at the MBDS. The
EPA's formal site designation for MBDS clearly  states that, until  capping is -adequately
demonstrated at the site, no contaminated sediments are to be dumped there.  (Any proposed
demonstration program would have to be carefully planned and undergo extensive agency and
public review;  the length of time required to complete such a program precludes
consideration for this project.)

       There are many inconsistencies throughout the EIR/S regarding the MBDS  and how it
is being viewed by project proponents. One example: If there must be a demonstration of
capping at MBDS prior to any disposal of contaminated materials, and the timeframe to
accomplish this makes it essentially impossible to use the site for the BHNIP (Section 3.3.2),
why is MBDS  one of the "practicable" and preferred alternatives for BHNIP silt (See Table
ES-la)?

       Capping,  or covering contaminated sediments with a layer of clean sediments, has
been used in the  U.S.  with mixed results. Although the Corps is very supportive of capping.
 some caps created in the early 1980's have not yet fully recolonized, indicating the possible
 long-term migration of contaminants. Recent  experience at the Mud Dump Site in the New
 York/New Jersey area further confirms that Corps expectations and projections regarding the
 fate of ocean-disposed sediments, are unrealistic. Instead of the  expected one million cubic
                                     I PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
yards of capping material, a total of 2.5 million cy was actually required to cover the
contaminated sediments, which were spread over a much wider area than the Corps had
predicted.

       The depth (approximately 100 meters) of the MBDS makes it a particularly poor
candidate for capping.  There is no substantial experience with capping at these depths.
Successfully predicting  where the sediments and capping  material  will end up will prove even
more difficult than in New York.  The large scale of the project means that, even under the
best of circumstances, contaminated sediments would be exposed to the marine environment
of Stellwagen Basin for long periods of time.  This is not the sort of chance we are willing to
take with Massachusetts Bay, especially given its location adjacent to the Stellwagen Bank
National Marine Sanctuary, its importance to the region's fishermen, and the fact that the
area is frequented by a  number of threatened  and endangered species.
       In addition to capping, the Corps has stated that, generally, approximately 5% of
ocean-disposed sediments will not reach the bottom, but will be dispersed in the water
column. For the BHNIP, this amounts to an additional load to Massachusetts Bay waters of
at least 65,000 cy of contaminated sediments if ocean disposal is used.  We believe the
atypical depths of the MBDS may result in an even higher load,  as additional sediments
remain in the water column.                                                           =

       One of the other "preferred alternatives" in the EIR/S is Boston Lightship (BL).  BL
is not currently a designated disposal site.  Its waters  are heavily used by commercial
fishermen.  In addition, radioactive and other wastes have .previously been dumped in the
area, although a thorough mapping of the wastes has not been completed.  Use of the BL site
for BHNIP disposal would be irresponsible, given the lack of data on the location and extent
of present contamination.  Once the area is better understood, disposal  of sediments at BL
may be a way to confine the contaminants already in  place.

       Like the other "preferred" sites (besides the Spectacle Island CAD), the Meisburger 2
and 7 sites are relatively far from shore.  The disposal of contaminated sediments at these
locations would pose a significant increase in the  loading of contaminants to Massachusetts
Bay should there be any problems with the cap, particularly since the surface areas  involved
are large.  The sites are also very close to the MWRA outfall. Since the outfall location was
chosen for its ability to disperse effluent,  the selection of such nearby sites for dredged
material disposal is questionable. In. addition, both projects may find it more difficult .to
interpret the results of monitoring efforts.                                 .
~l
                                     I PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
       The Spectacle Island CAD area is also used by fishermen and lobstermen.  According
to a paper by Harley Knebel at USGS, Wood's Hole, the area immediately to the east of
Spectacle Island, where disposal is proposed, appears to be erosional in nature.  The shallow
(~ 9-foot) waters at the site are also susceptible to tidal and storm activity. This is especially
of concern because of the relatively large surface area proposed for disposal (probably -45
acres).  Should a problem occur with  migration of contaminants, exposure of these
substances to aquatic life could be substantial.

Mitigation

       The BHNIP EIR/S does not adequately address mitigation and assumes that the only
impacts of this project  are short-term  and ephemeral. We disagree.  While the navigation
improvement project is commercially  critical to the Port of Boston,  the project does preclude
or compromise a number of uses of these waters that might flourish in the absence of
commercial traffic. Moreover, continued utilization  of Boston Harbor for commercial
traffic, as well as spills and accidents associated with marine  cargo .shipment and distribution
will result in new contaminant burdens for marine sediments in the harbor that will need to  —-
be managed in the future.  Finally, there will be unavoidable short-term losses associated
with the dredging process itself, including a potential for additional human exposure to
resuspended pollutants through fish or direct skin contact. Besides the mitigation measures
suggested elsewhere in these comments, we ask that  the following points be considered.

       CLF supports the suggestion hi the EIR/S that any existing  tidal or subtidal habitat
that is lost as a result of inshore filling associated with the project be replaced on a 2 to 1
basis and managed until it is reestablished.

       We make two additional suggestions that should be incorporated into this project in
order to mitigate the unavoidable short- and long-term impacts from the BHNIP.

       First, the Commonwealth of Massachusetts, Massachusetts Port Authority, and Corps
should investigate environmental dredging of contaminated sediments in areas that are outside
the boundaries, but adjacent to, the BHNIP.  The Corps is authorized under the Water
Resources Development Act of 1992  to Underwrite this work with a 50% federal cost share.

       The upper reaches of the Chelsea River and some of the areas of the Mystic River
receive extensive public use, both with direct  contact from children using these waters for
swimming and play and indirectly through fish consumption. An effort should be made to
determine the extent of contamination in these areas, and a mitigation project should be
developed and carried out that removes contamination and possibly even encourages
                                     I PRINTED ON RECYCLED PAPER

-------
                           Conservation Law Foundation
10
recreational use.  Such an effort would be a meaningful exchange for the poor communities
that are forced to find their recreational and fishing opportunities in these contaminated
waters.                                                                                J—

       The second mitigation measure we suggest is also forward-looking and relates to
source control.  Massport is not only the port authority, but also one of the principal
property owners in the harbor area.  Massport should develop a non-point source control
program that covers its properties as well as the private terminals that are being served by
this project.

       The control of pollutants from Deer Island will represent a substantial contribution to
reducing future contamination problems but needs to be combined with a non-point source
control program on pollution from port terminals and Massport properties.  This mitigation
measure will not only reduce the level of contamination that we experience in the future but
also increase the life of the disposal facilities that are developed for this project.           _

Beneficial Use
                                                                                      b^M.
       CLF applauds the suggestion in the EIR/S to put dredged sediments to beneficial use.
However, substantial work needs to be done to turn this theory into practice. We
recommend that, if they  have not already done so, the Corps, Massport and representatives
from the state Executive Office for Environmental Affairs immediately begin formal
discussions to help identify and contact communities and sites that could benefit from clean
dredged materials.  State agencies such as the Department of Environmental Protection and
the CZM office are the best candidates for a much-needed beneficial use "clearinghouse,"
and this project is an excellent place to start.
                                             !
       With 114 out of 122 landfills in Massachusetts scheduled to close by 1996 (Section
3.3.1), one possibility that should be studied is the  use of project clay and silts not only as
daily cover, but also as final closure material.

       Planning related to  beneficial use should be  completed prior to the release of the Final
EIR/S, and  specific recommendations should be included in the  document.                 	

Cost/Benefit Calculations

       CLF believes that federal and local sponsor cost-benefit analyses undertaken as pan of
this project  should be realistic, and should be included in the EIR/S.  Costs such as
reimbursement to fishermen for lost opportunity and equipment  damage as well as potential
                                     I PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
11
environmental harm including monitoring of disposal sites, clean-up expenses from leakage
of contaminants into marine waters or the contamination of seafood, and its likely effects on
other segments of the economy should be factored into the cost-benefit calculations.

       Current cost estimates in the EIR/S, especially-for relatively distant sites such as
MBDS, BL and the Meisburger 2 and 7, improperly underestimate the true cost associated
with disposal at these sites by failing to include monitoring and management costs.  (MBDS
receives some monitoring under the DAMOS program,  although these efforts may not be
sufficient for the  long term management of disposed BHNIP sediments.)

       CLF is also interested in understanding on a more quantitative basis the benefits of
this project for the regional  economy and for the local sponsor.  Section 4.5.5 of the EIR/S
touches on this topic too briefly.  A detailed analysis is essential when weighing the
environmental versus economic factors of the project.

       Massport  officials have said that no additional vessel traffic will result from the
BHNIP  The EIR/S states that the volume of cargo through the harbor is not expected to
increase due to this project.  In the past, when asked about the possible financial losses due
to current harbor conditions, the "passing over" of Boston Harbor by an undetermined
number of ships  was mentioned.  To our knowledge, however, details have not been made
publicly available.  How much additional revenue to the regional economy and to Massport
will result from the project? Conversely, how many dollars will be lost yearly if BHMP is
not implemented, or is delayed?  What are the costs of "lightering" and how often does it
occur now? A large organization such as Massport must have produced an assessment of
costs and benefits in order to justify the project internally. This information should be
included in the EIR/S.

Public Participation/Community Issues                                                    |

        The Corps and Massport must  ensure that all stakeholders, (e.g., fishermen,
 community representatives) are encouraged and have ample opportunity to state their
 concerns regarding the BHNIP- and that their concerns are properly addressed during
 project planning and implementation.

 Conclusion

        CLF sees the BHNIP not as an isolated project, but as part of a larger .question that
 must be addressed at state, regional and federal levels: the management of contaminated
 sediments.  The problem of how to safely dispose of dredged contaminated sediments has no
 easy solutions at the present time.  This makes dredging projects such as BHNIP more
                                     I PRINTED ON RECYCLED PAPER

-------
                          Conservation Law Foundation
                         12
complicated than they might otherwise be.  Nevertheless, until improved treatment
technologies are in wide use, it will be the responsibility of state and federal agencies to
ensure that existing environmental laws and regulations related to contaminated sediments are
adhered to.     .

       We thank you again for the opportunity to submit these comments.
                                                            Sincerely,
                           Grace I. Perez
                          • Science Fellow
Peter Shelley
Senior Attorney
                                    I PRINTED ON RECYCLED PAPER

-------
E6-1

       Massport and the Corps have taken the conservative approach that all of the silt will
be treated as unsuitable for unconfmed open water disposal.
E6-2

       As discussed in the DEIR (pg 4-6) the silt dredging will be conducted with a modified
(environmental) bucket having small or no teeth. This type of equipment is necessary to
optimize the containment of silt during the dredging process. This equipment is very effective
in removing silt and other unconsolidated material but is not capable of penetrating underlying
clay to any appreciable depth. For this reason the DEIR states that the silt portion of the
dredging will cut no more than approximately 6 inches into the underlying clay. This dredge
method will effectively remove the more contaminated silt and expose the cleaner clay, sand
and rock which will be removed by other equipment and methods more suitable to those
materials.  Overdredging the silt  into clay by one to two feet (as suggested by CLF) will not be
possible using a "silt" dredge bucket. Additionally, since the clay is uncontaminated, it would
not be prudent to include any large amounts of clay to the silt volume due to the expected
high costs of disposal of the silt fraction for the BHNIP.
E6-3

       The FEIR/S considers all silt from the BHNIP to be unsuitable for unconfined open
water disposal.
E6-4

       The BHNIP EIR/S preparation team agrees with this comment. The experience gained
from the Moran Terminal dredging project (as well as from others) is valuable in recognizing
potential problems that may be encountered during the BHNIP. This is particularly applicable
to the dredging of contaminated silt where the risk of environmental impacts is greatest.
Please refer to the Dredged Material Management Plan (Section 5.0) for detail on the dredging
and disposal operation. Experienced dredge contractors are likely to bid a large project such
as the BHNIP. Environmental conditions will be discussed with the dredging contractor
during the pre-construction meeting.
E6-5

       See response to E6-4.  The DEIR/S discusses the three commonly used type of
dredges - hopper, hydraulic and mechanical. Other types of dredges, such as the pneumatic
dredges, have limited production capacity and/or experimental and not proven for a large job
such as the BHNIP.  These types of dredged are unfamiliar to the majority of contractors and
would not be considered the primary dredge.
                                           10

-------
 E6-6

        The use of a Corps inspector on board the dredge decreases the risk of overloading
 and "short-dumping". No known cases of "short-dumping" are known to have occurred in
 several years.  As the preferred disposal alternative is in-channel, concerns about "short-
 dumping" are no longer a problem.  A trained impartial observer would be allowed to notify
 the Corps inspector of a violation but would not have the authority to control dredging and
 disposal operations.  The Corps can not fund observers other than a Corps inspector.  Agencies
 or groups interested in having an independent observer would be required to hire the person or
 accept volunteers.  All observers may be required to undergo training in order to board
 equipment.  Electronic recording device  would not be needed if the material  is staying in-
 channel.
 E6-7

        The disposal site alternatives analysis presented in Section 4.0 of the FEIR/S concludes
 that In-channel disposal is the preferred alternative.


 E6-8

        The revised disposal site alternatives analysis is presented in Section 4.0 of the FEIR/S
 and includes a discussion of combinations of sites.
E6-9

        The Corps's DAMOS program, would monitor the disposal site for physical,
biological, and chemical parameters, as needed.  Coordination with other agencies would
occur, as appropriate.  Contingency plans are part of the Dredged Material Disposal Plan in
Section 5.0 of the final EIR/S.
E6-10

       The revised disposal site alternatives analysis (FEIR/S Section 4) concludes that, of the
aquatic sites, the in-channel and the partial-fill shoreline scenarios are the least
environmentally damaging.  The upland disposal alternatives are also among the least
environmentally damaging.
E6-11

       The potential for resuspension of sediments after disposal at each of the potential
aquatic disposal sites has been analyzed (Appendices F and G, Attachment 1 and Section 4)
for the FEIR/S.
                                           11

-------
E6-12

       The BHNIP team has reviewed available information on the use of geotextile bags for
disposal of contaminated sediments.  At this time, there continue to be structural problems
with the use of bags that are large enough to be used efficiently for a project of this
magnitude.  We have worked closely with regulatory agencies to identify other control
methods that would minimize release of the silts to the environment during and after disposal.
After further research, geotextile bags may prove to be effective for this purpose in the future.
E6-13

       Policy BWP-94-037, Reuse and Disposal of Contaminated Soils at Landfills, makes
disposal of dredged material in landfills unacceptable if reuse, recycling, destruction or
detoxification are feasible alternatives.  The impracticability of dewatering 1.32 million cubic
yards of silty dredged material for reuse as daily cover or contouring material (or transport as
waste) has resulted in the elimination of landfill reuse options.  However, beneficial uses of
the clean dredged material is presented in the FEIR/S.
E6-14

       The Corps Boston Harbor project funds can not be used for a demonstration project.
However the Corps is committed to moving forward in resolving issues surrounding the
disposal of contaminated material. Refer to Section 3.0 of the FEIR/S for discussion of
treatment technologies investigated.
E6-15

       The disposal site alternatives analysis has been re-evaluated for the FEIR/S (Section
4).  The MBDS is not considered to be a suitable site for the disposal of contaminated silts
from the BHNIP.  It could be considered for future maintenance material only if capping is
successfully demonstrated to provide long-term isolation of these sediments from the
environment in waters of similar depths.  .
E6-16

       The U.S. EPA site designation study for the MBDS did not predict a level higher than
5% of the material leaving the site. Studies conducted for the MWRA and Mass Bays
Program show that this material is minor component of the Mass Bays system.  Since MBDS
is not being considered for disposal of the silt to be dredged for the BHNIP, the amount of silt
potentially lost to the water column during disposal is not an issue.

E6-17

       Boston Lightship has not been selected as the preferred alternative for disposal of silt
from the BHNIP (Section 4.0, FEIR/S).  Any future use would require coordination with EPA
regarding the proported drums of industrial and radioactive waste at this site. Disposal of
                                           12

-------
 dredged material at this site to cover these drums may benefit the environment of this area.
 The EPA should play an active role in researching the locations and environmental status of
 any hazardous materials at the BLS to determine whether it would be best to leave as is,
 remove, or cover in place.
 E6-18
 choice.
        The Meisburger sites are no longer under consideration as the project's LEDPA
E6-19

        The biological resources and the physical environment at the Spectacle Island CAD
site were reexamined for the FEIR/S. The revised disposal site alternatives analysis (Section
4) concluded that this site was not the least environmentally damaging practicable alternative
for disposal of the BHNIP silt.
E6-20

        Mitigation is discussed in Sections 5 and 6 of the FEIR/S. The project is not
anticipated to change the number of ships coming into the harbor.

        CLF asserts that the continued commercial shipping in Boston Harbor will result in
additional marine contamination because of spills and accidents.  CLF further suggests that
there are other uses of the Harbor that are compromised by the current commercial shipping.
It is important to note that there have been no major spills in Boston Harbor in part because of
the vigilance of the Coast Guard, harbor pilots, and Harbor advocacy  groups.  In addition in
over five years, there has not been a spill resulting from collision (per USCG Boston-Marine
Safety Office).  It is also important to recognize that spills occur not just from tankers and
container ships, but also smaller vessels including tugboats, barges and fishing boats and
recreational craft. These latter vessels would continue to use the Harbor even if no BHNIP
were undertaken. The region will continue to need petroleum products which are most
shipped over the water.  Lightering and use of barges will continue in Boston Harbor if there
is no maintenance dredging. Thus, the Harbor is not necessarily saved from spills by virtue  of
closing it to larger vessels. Further, closing the Harbor to commercial shipping, other than
petroleum products, could diminish the efforts of Harbor advocacy groups which currently
benefit from the resources and ideas of port operators.
E6-21

       Water quality models showing the distribution of contaminants during the dredging
process are presented in Appendix F. It is unlikely that contaminants released from the
operations will exceed chronic -water quality criteria.  Therefore, effects of exposure to biota
would be undetectable.
                                           13

-------
E6-22

       In-channel disposal has been identified (Section 4.0) as the Least Environmentally
Damaging Practicable Alternative, as well as the preferred alternative.

       The phrasing of this comment appears to exaggerate the DEIR/S commitment to
mitigation. Nowhere in the DEER/S does it suggest that BHNIP proposes to replace any lost
tidal or subtidal habitat on a 2 to 1 basis.  What is does state in Section 3.10 is "Loss of
subtidal or intertidal habitat could be replaced with intertidal habitat, salt marsh or eelgrass
plantings."

       BHNIP commits to investigating compensatory mitigation , if required. However, as
stated in Section 6.4.4, the BHNIP, as designed and with in-channel disposal, provides
significant enhancement of project specific principal valuable functions (see Appendix K). As
such, no compensatory resource mitigation should be required under either federal or state
wetland regulations.

       As local sponsor, Massport is willing to work with state resource agencies to identify
resource enhancement opportunities in the Harbor area.  As examples, these can include:

       1.      Assisting the Metropolitan District Commission (MDC) in  their on-going
efforts in coastal resource restoration in the Boston Harbor ACECs.  The MDC is currently
planning projects at the Rumney Marsh and Neponset River ACECs.

       2.      Massport is committed to increasing the  number of vessel sewage pump-out
facilities in the Harbor area and will work with the appropriate agencies on specific details.

       3.      Massport will also consider coordinating with the Department of
Environmental Management (DEM) to identify potential areas of cooperation and assistance in
DEM resource and facility enhancement projects on Harbor islands.

       4.      Massport will work with state and local resource agencies to identify potential
resource enhancement options such as supporting the development of an "urban fishing park"
through rehabilitation of water access structures (e.g., boat ramp in Little Mystic Channel) to
enhance public use and access to functional recreational  fishing areas.
E6-23

       Although the Corps has the authority to participate in environmental dredging, this
program  has not been well funded. The Corps supports environmental dredging of
contaminated sediments outside the channel limits.  As there have been many concerns
regarding the disposal of contaminated sediment from the dredging of Boston Harbor, it may
be prudent to continue coordination with the Commonwealth agencies and other groups to
resolve when, how, and where disposal of contaminated sediments can occur, considering the
large amount of dredged material this would generate.  Also the sources of pollution to the
harbor would need to be reduced to make this program effective. This may be possible in the
future when a containment site for contaminated sediments is available.  In addition, this
program would require a cost-sharing partner willing to provide the other 50% of the cost of
this study.
                                           14

-------
 E6-24

        Source control is an important aspect of reducing the contaminant load to Boston
 Harbor.  Several mechanisms are currently in place to address this issue. As noted by the
 CLF, the upgrade of the Deer Island facilities will continue to substantially improve water
 quality in Boston Harbor. The following table, summarizing information contained in Alber
 and Chan (1994;  MWRA Report 94-1) indicates that even though discharge of the sludge has
 ceased, the MWRA outfall is still the major source of most of Boston Harbor's contaminant
 load:
                PERCENT CONTRIBUTION OF VARIOUS SOURCES
                TO THE BOSTON HARBOR CONTAMINANT LOAD
Source

MWRA Effluent
CSO Flow

Stoimwater
Logan Airport

Tributaries*

Atmospheric

Groundwater
Other NPDES
Flow
39

<1
2

<1
48

8

3

<1
Cu
84

1
3

1
7

1

2

<1
Pb
63

7
ND

ND
23

6

1

ND
Zn
78

2
11

1
4

2

1

<1
PAH1
94

<1
<1

1
5

<1

ND

ND
PAH 2
31

1
7

ND
59

2

ND

ND
PAH 3
29

3
22

ND
36

11

ND

ND
N
89

<1
1

<1
7

2

1

ND
P
94

<1
1

<1
4

<1

<1

ND
BOD5
91

1
1

1
7

ND

ND

ND
TSS
88

2
2

<1
9

ND

ND

<1
  Above the Charles River and Amelia Earhart Dams.
ND = No Data
PAH 1 = 2-methylnaphthalene
PAH 2 = pyrene
PAH 3 = benzo(a)pyrene

       Alber and Chan (1994) conclude with the following comments:

       Despite the above reductions, effluent discharged from MWRA plants are still a major
source of all conventional contaminants, metals, and nutrients examined.  The exception is
individual PAH compounds, -which have large runoff and non-point sources.  The next big
change in contaminant loading to the Harbor will come once the treatment plant outfall is
moved. When the new effluent outfall tunnel is completed, the amount of contaminants
entering the Harbor will decrease dramatically.  This should result in a major improvement in
the water quality of Boston Harbor.
                                         15

-------
       Boston Edison, a project beneficiary, is the only other NPDES permitted discharge
directly entering the Harbor. Massport and other project beneficiaries are presumably
accounted for in the CSO estimates, since if they discharged stormwater directly to the Harbor
they would have an NPDES permit. Plans currently underway by MWRA to address CSOs
(Short-term System Optimization Plan and Long-term CSO Control Strategy) should also
contribute to source reductions over time.  Under the Clean Water Act (40 CFR 122.26),
stormwater discharges to CSOs (or municipal sanitary systems) do not require a NPDES
permit  However, these discharges may be subject to pretreatment requirements if the system
operator (MWRA) requires them.
E6-25

       The Department of Environmental Protection has been invaluable in providing
regulatory information, technical data, and guidance to identify specific beneficial uses of
dredged material generated by BHNIP and other projects.  The practicable beneficial uses
identified for this project are described in the FEIR/S.
E6-26

       In-channel disposal should result in no loss of any fisherman's equipment or
livelihood. As the material will be placed in the same area, no additional impact is
anticipated, based on water quality modelling.
E6-27

        CLF asks about the financial gains or losses sustained with and without dredging.
There are assumptions which must be incorporated in any answer to this question. If one
assumes that the dredging will be completed in 1998, and that the benefits of the dredging will
be reflected after that date, then the starting point for calculating benefits is the cargo forecast
to move through the Port in 1998. Massport projects cargo tonnage in 1998 to be 1,514,200
tons which yields about $1.73  billion in economic value to the region including 13,000 jobs.
If one assumes that dredging facilitates ships' transit in the Harbor and that tonnage grows 3%
per year, the total new cargo volume will be over 245,000 tons at the end of five years.
Massport calculates that the value of each ton of cargo to the region is over $1120.  At the
end of five years, the economic benefit of the additional tonnage will be $275  million (dollars
are not discounted).

        Alternatively, if the BHNIP does not go forward, large container ships will have
increasing difficulty transiting the Port of Boston. It is important to note that even barges will
have difficulty transiting the Harbor under the No-Build option since barges are getting wider
and deeper. Thus, barging is not the solution for bringing containerized cargo into a Harbor
with  insufficient draft. Further, the need to transfer cargo to barges and the slower travel time
for barges is a deterrent to shipping containers in this manner.  News of the No-Build decision
in Boston Harbor will affect the decisions of shipping lines and shippers, and will likely
decrease the volume of cargo coming into the Port. Once the decline in tonnage begins, it will
continue to the detriment of Port operations.  Using the 1998 base year with tonnage of
1,514,200 as a base, and assuming a tonnage decline of 5% annually, the total tonnage
                                            16

-------
reduction by 2003 would be 342,569. This represents $392 million in economic benefit lost to
the region.  Thus the decision to dredge, and allow today's fleet of container ships to transit
Boston Harbor easily, or not to dredge and reduce the cargo moving through the Port of
Boston has economic consequences ranging from a benefit of $275 million to a lost
opportunity of $392 million over a five year period from  1999 through 2003.  This is for
containerized cargo alone.

       CLF further asks about the cost of lightering. The latter is impossible to quantify
because the information is privileged. Each company has its own method of assessing costs.
Thus, Massport cannot total the figures given by individual companies to identify a "port"
lightering cost, since the figure given by each company may include more than the pure cost
to lighter.

       Massport projects that the gross revenues accruing to the Authority from 245,000
additional tons of cargo moving through the Port over the same five year period will be
approximately $3.5 million.
E6-28

       Several meetings were held with lobsterman and fishermen to obtain their views on the
project. These concerns are displayed in Appendix B of the final EIR/S.
                                          17

-------
C
                     GreenWorld  Inc.
                                                     Suite 193
                                              510 Commonwealth Avenue
                                                 Boston. MA 022 15
                   REQUEST FOR A SUPPLEMENTAL EIR/EIS ON VESSEL IMPACT ON \\ HALES IN
                    REG ARD I TO THE MEPA REVIEW OF THE BOSTON HARBOR NAVIGATION
                         '                    PROJECT (EOE A
TO-   '
                            Trudy Coxe. Secretary
                            Executive Office Of Environmental Affairs
                             100 Cambridge Street
                            Boston. MA 02202
                             COMMENTS ON DRAFT EIR/EIS
                             PROJECT (EOEA # 9865 )

                             June 20,1994
                                             . BOSTON HARBOR NAVIGATION
RE:


DATE:

Trudy.

       Having reviewed the Draft EIR/EIS on the proposal by Massachusetts Port Authority and
the Army Cor|s of Engineers to deepen the present ship channels m Boston Harbor, and to make_
otheVnavigatSn improvements, I discovered a major error of omission in the scope of the
revkw The WA/ACOE completely failed to review the environmental impact of the very thmg
Sanhe p^j« "being done to accommodate - ship traffic into and out of Boston Harbor.

       Ship traffic has a devastating impact on the marine environment  Ship collisions routinely
 kill endangered marine wildlife. Pollution from the discharging of plastic matenal and debris
 from sS seais a major source of coastal pollution. The number one cause of death for the
 worid's most endangered species of whale - the Northern Right whale - is ship stnkes. Yet.
 the DEIR/DEIS fails completely to even attempt to address this issue.                    _

       A review of the environmental impact of any project can be divided into two areas of
 potential impact; the effects of the construction (or alteration) of a ^™»«g* g£en S"e
 and then the Ions term consequence of the existence of that physical feature Therefore, the
 Svi^nSalS^of the construction of a dam consists of a review of the construction of not
 only the dam itself but also a review of the effects on the environment of the operation ot the
 dam and the creation of a massive lake behind it.
            *••-:'
       ' Concernins the
                                                      , the building of the "dam" (the dredging of ship
                  "no one ever told us that an analysis of sh.p traffic was to be included.

-------
       The survival of the Northern Right whale is now in question. The elimination of ship
strikes on this species may be the only thins that can prevent an otherwise imminent extinction
for this species of whales. All ship traffic into or out of Boston Harbor either crosses'areas that
have been proposed to be designated as critical habitat for the Northern Right whale (publication
of the final rule in the Federal Register is imminent) by the National Marine Fisheries Service or
other areas that are within the Stellwagon's Bank Marine Sanctuary. The United States is the
world's number one whale killing nation, mostly because of kills caused by ship traffic in U. S.
coastal waters.

       There is no simple solution to the failure to include an analysis of the impact of ship
traffic supported by this project on the marine environment and on species of endangered marine
wildlife. A complete analysis — and consideration of mitigation measures — would be extenshe
and generate a document equal to the present DEIR/DEIS. The very subject would have to be
scoped out to make sure it would be adequately addressed. Areas of impact should include strikes
on marine wildlife, chemical pollution from vessels, adequacy of law enforcement, plastic
pollution from ships, chances of accidents (e. g. oil spills in Massachusetts Bay), etc..

       Therefore. I request that a supplemental EIR/EIS be done of the impact on the marine
environment of the vessel traffic resulting from this project. I request that you recall your scoping
committee and have it prepare a scope on the effects of vessel impacts for a supplemental
EIR/EIS. I requests that the MPA/ACOE be then given the scope and requested to prepare a draft
supplemental EIR/EIS on the impact of vessel traffic resulting from the Boston Harbor
Navigation Project.                                                                     ~~

    '   The death of a single Northern Right whale has been determined by the federal  Northern
Right whale recovery team to be unacceptable. Unless the MPA/ACOE figure a way to insure
that no ship going into or coming out of Boston Harbor will ever again kill a Northern Right
whale. Northern Right whales will be absolutely threatened with extinction by this project. If the
MPA/ACOE refuse'to properly review and find a way to eliminate this threat, no federal  court
will allow them to hold any federal or state permit to conduct this project.

       This request has been made under the provision of the Massachusetts Administrative
Procedures Act and regulations adopted to implement it. Your formal reply in writing is expected
and required by statute. We wish to be informed of every meeting conducted to review and make
decisions on this petition.

       I  await your reply.                                                   '
                                                     Strafern
                                                National Campaign Director

-------
E7-1
       The proposed project is not expected to increase ship traffic into and out of Boston
Harbor.  The purpose of the project is to reduce tidal delays ships currently experience in
Boston Harbor.  Additional comments on ship traffic are discussed in the Biological
Assessment for this project.
E7-2

       The purpose of the project is not intended to increase ship traffic into and out of
Boston Harbor.  A scope to determine increased ship traffic would not be appropriate.  A
supplemental EIR/S is not needed for this purpose.  The EIR/S and Biological Assessment do
discuss impacts from the increased ship traffic out to the MBDS to dispose of clean parent
material.
                                          18
3/2-

-------
                    MASSACHUSETTS BAYS PROGRAM
                    100 Cambridge Street, Room 2006, Boston, Massachusetts 02202 (617) 727-9530 fax (617) 727-2754
June 21, 1994

Brink P. Miller, Colonel
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, MA 02254

     Colonel Miller,

The primary goal of the Massachusetts Bays Program (MBP) - a state, federal, and local partnership -is to maximize
protection of the marine environment Therefore, the MBP can only support those activities of the Boston Harbor
Navigation Improvement Project (BHNIP) which meet that goal.

Since extensive dredging will disrupt water quality in the harbor through increased turbidity and by triggering the
release of contaminants which have accumulated in marine sediments, the MBP can only support this project if
appropriate technologies are used to minimise the impacts from those sources, e.g. silt curtains and sealed dredginj
buckets. The DEIR/S should adequately examine these and other technologies which would minimize the impa<
  both the project area and at the preferred disposal sites on both water quality and the marine biota and habitat
  je MBP also recommends that the project provide for monitoring of the bays ecosystem to ensure that there are
no long term adverse impacts on the above resources.     '•                                                	

Use of the Massachusetts Bay Disposal Site (MBDS) for the dredged spoil raises concerns, as welL  The U.S. Army
Corps of Engineers and the U.S. Environmental Protection Agency have determined that at least 603,200 cubic yards
of surface sediments in the project area are not acceptable for unconfined ocean disposal; and the estimated extent
of contamination ranges from 25 to 40 percent To date, evidence has not been presented to show that capping tlTj
material wfll work at the depth of the MBDS.  If a pilot project is to be conducted at the MBDS  to demonstrate"
the feasibility of deep water capping, it must be done by capping clean sediment with clean sediment  The bays
ecosystem is a fragile resource and must not be used as an experiment If capping of clean sediment cannot be done,
the MBP must oppose the MBDS as a disposal option.    '-                                              _

Other specific recommendations  relating to the  BHNIP  and to disposal options are being developed by our
Management Committee as part of the Comprehensive Conservation and Management Plan (CCMP).  We will
submit them to you later this summer.

Thank you for your time and consideration of these concerns. If you have any questions, please feel free to call me
at (617) 727-9530 x406.
Sincerely,
 ''iane M. Gould, PhD
  xecutrve Director

cc: Carol Kilbride, USEPA
    Cathy Demos, USACOE
  The Massachusetts Bavs Proeram is soonsored bvthe Massachusetts Executive Office of Envirnnmpntal Affairs through the Coastal Zone Management Office

-------
E8-1

       The FEIR/S has identified specific proven technologies which will effectively
minimize impacts to the water quality and marine habitat. Section 5.0, Dredging Management
Plan, of the FEIR/S describes specific equipment and operating techniques to minimize
impacts to the aquatic environment.  In addition, it is noted that the construction operations,
specifically dredging and disposal, will  be required to meet certain minimum environmental
criteria which will be incorporated into the conditions of the project permits. Water quality
modelling has indicated that there will not be significant water quality violations from the
dredging and disposal of dredged material in Boston Harbor.  Refer to Appendix F for
additional water quality information.
E8-2

       The MBDS is not considered in the FEIR/S to be a suitable location for disposal of
silts from the BHNIP.  If a capping demonstration  is conducted, it will use clean silts.
                                            19

-------
     MASSACHUSETTS    SIERRA   CLUB
     3 Tov Street Boston Massachusetts 02108  (617) 227-5339 fax  (617)  742-8646"
                                                                       June 27, 1994
 Brink P. Miller, Colonel
 U.S. Army Corps of Engineers
 424 Trapelo Road
 Waltham, MA 02254                         :

 Re: Draft Environmental Impact Report/Statement for the Boston Harbor Navigation
 Improvement Project
*-*-'  /
 Dear Colonel Miller:


 We are writing to submit our comments on the above referenced DEIR/S for the proposed Boston
 Harbor Navigation Improvement and Berth Dredging Project (BHNIP). We have divided our
 comments into several areas of concern for items covered in the Draft EIR/S.  In addition, for
 reasons stated below, we are calling for a Supplemental EIR/S, to examine in  more detail, specific
 late appearing options and other topics not adequately reviewed in the Draft EIR/S.
  1.  PURPOSE OF THE BHNIP

  The Sierra Club questions whether the project purpose as stated in the Draft EIS will in fact be
  achieved by the proposed dredging.

  The Draft EIS states that the purpose of the BHNIP project is "to increase the navigational
  efficiency and safety of Boston Harbor for present types of deep drafted vessel traffic that are
  currently transiting the project area." It identifies the need for a depth of 40 feet mean low water to
  accommodate deep draft navigation. It asserts that the use of larger vessels for shipping reduces
  transportation costs, but that under current conditions in the harbor, these cost reductions are not
  fully realized because the vessels "either incur tidal delay, have to be lightered or are light loaded"
  (p. 1-3). According to the DEIS, these factors "discourage many ships from calling directly on the
  Port of Boston"  (page 1-4). The document cites specific examples of ships that schedule arrivals
  around the tide, or which do not call on Boston loaded to jthe maximum capacity.

  TWDEIS asserts that completion of the BHNIP will enable the utilization of "largervessels which
  wfll transit the harbor during a wider range of tidal stages." The project is also designed to
  accommodate the use of double-hull tankers as required by the Oil Pollution Act of 1990 and to
  accommodate increase in the number of size and container ships which is projected for the Port of
  Boston in the future (p. 1-3).

-------
Before incoming ships reach the Main Channel or the tributary channels (areas where the
improvements are proposed), they must pass through the North Channel. This channel is
characterized by rocky shoals, frequent easterly swells, a depth of 40 feet at mean low water and a
20 degree left turn at the entrance, near Finn's ledge.

Larger ships require greater clearances under the vessel when turning. Any contact with the rocky
bottom of the North Channel is likely to result in an accident, possibly a spill in open water which
would be very difficult to contain or mitigate.  In addition, when the port inside of Deer Island is
dredged to the standards proposed in the BHNIP, there will be more pressure for ships to enter
and traverse the North Channel under marginal conditions.

Unfortunately, the Draft EIS omits any discussion of the present conditions in the North Channel
and fails to consider critical questions. To what extent do those conditions currently restrict the
size of ships entering and the depth at which they can enter? Will there still be a need to schedule
arrivals around tidal cycles? Will ships still have to be light loaded to traverse the North Channel
even after the dredging in the Main and tributary channels is completed? Can larger ships than are
presently using the Port of Boston and double huU tankers safely use the North Channel?

Failure to consider future implications of the North Channel conditions could result in the
expenditure of millions of dollars of public funds for a project that will not fulfill the stated
purpose, i.e., to increase navigational efficiency by avoiding tidal delays, avoiding light loading and
enabling the use of larger vessels.

In order to avoid an indefensible waste of public money with potential damage to the environment
resulting as well, this project should NOT PROCEED until a Supplementary EIS has been
prepared which fully considers conditions in the North Channel and their implications on
navigational efficiency. Any improvements that would be needed in the North Channel must be
included in the project and especially in the cost/benefit analysis for the BHNIP.


2.  COST/BENEFIT ANALYSIS AND IMPACTS                                     —

The cost/benefit analysis in the DEIS does not take into account environmental costs relating to
public health issues or specific long term impacts to marine habitat and aquatic resources.  The
analysis gives precedence to costs over environmental impacts, without proper analysis of the
latter. Adverse impacts and potential environmental harm caused by the dredging are not
considered and costs to other resource users not included in the disposal alternatives, such as
fishermen, lobsterman, aquaculture, and tourism, should be included the SEIS.  In addition the
 economic impacts of the wastes on these and other resource users should also be included in the
 overall cost of the project.

 The DEIS itself admits that the cost of the preferred disposal options must demonstrate at least a
 l^Lbenefit-to-cost ratio to qualify for federal funding. The costs of restoring lost resources are not
 factored into this calculation, so there is unfortunately a predetermined limit on the price tag for
 disposal options that is unrelated to minimum needs to protect natural resources.

-------
3. PREFERRED ALTERNATIVES

In the Draft EIS, the Army Corps of Engineers and Massport have identified several "Preferred
Alternatives:" the Massachusetts Bay Disposal Site, the Boston Lightship site, an area off of.
Spectacle Island, and the Meisburger Sites 2 and 7. All of these are open water sites. Massport
has indicated that it will consider a sixth alternative, disposal of the contaminated material in one of
the inner channels.  The open water sites have clearly been chosen as the "preferred alternatives"
because they are among the least costly.

The value of the resources that are jeopardized by the open water disposal option have been
ignored. Sufficient information about the long term fate of contaminated material disposed of in
open water is not available at this time to justify placing the aquatic resources of Massachusetts bay
at further risk. The promise of long term monitoring does not insure that future commitment or
ability will exist to take remedial action if problems are detected at these disposal sites. Therefore
we strongly urge that the resources of Massachusetts Bay and Boston harbor not be jeopardized to
begin with.                                                                              _

Massachusetts Bay Disposal Site:
It is bewildering that the Corps and Massport would even list the Massachusetts Bay site, since the
Environmental Protection Agency has clearly prohibited disposal  of contaminated material with
capping unless and until it is shown that capping can isolate contaminated material from the
benthic community. To address EPA's questions about the efficacy of capping, the DEIS cites the
"Addam's Model Results" found in Appendix F. This model was used to "look at the short-term
fate of dredged material."  Model predictions about the short-term fate of dredged material do not
satisfy concerns about what happens to capped disposal material over periods of many years. It
should also be noted that capping has never occurred at the depth  of 80 to 100 meters; the studies
cited by the Corps of capping at the Portland site and in New York Harbor may have little
relevance to disposal at the Massachusetts Bay site.

We are further opposed to any disposal at the Massachusetts Bay  Disposal Site because of its
proximity to Stellwagen Bank. Marine mammals, including the endangered northern right whale,
migrate annually to this sight to feed, and to nurse their young, and are therefore dependent on the
ecological vitality of this region.

Use of the Massachusetts Bay disposal site for contaminated sediments is illegal without a waiver.
We would vehemently oppose the issuance of such a waiver.                                 	

Boston Lightship
Boston Lightship is about 9 nautical miles from Stellwagen Bank. It is reported to be a productive
fishery area inhabited by cod, sole, yellowtail, flounder and whiting, as well as lobster and
quahogs. Endangered whales and possibly endangered turtles are believed to frequent the area as
transients. The concerns about the fate of material disposed of in  open water over long periods of
1$me apply to this site as well. Because of the potential damage to fish, shellfish and endangered
species the Sierra Club believes that choice of the Boston Lightship site would violate the Section
404 (b)(l) Guidelines under the Clean Water ACL  Other less environmentally damaging
alternatives exist which offer a practicable solution to disposal of the dredged material.

Meisburger Sites 2 and 7
                                                  3J7

-------
Rounder and cod fisheries also exist within the vicinity of the two Meisburger sites, as well as
productive lobster beds.  These valuable areas should not be placed at risk by the possibility of
migration of contaminants from dredge disposal. Again, because other less environmentally
damaging alternatives exist, use of either of the Meisburger sites would violate the 404(b)(l).
Guidelines.

gpectacle Island                                                            .   .
Lobster fishing occurs in the area between Spectacle and Long Islands. In addition it is critical to
note that a containment facility is being constructed on the island to remediate the landfill and
dispose of material from the Central Artery project The integrity of the containment area is
already plagued with problems of slumping and subsiding of waste materials, and nearby dredging
could exacerbate this instability. Because of the potential damage to the lobster fishery and other
aquatic resources in this area, this site does not qualify under the Section 404(b)(l) Guidelines.

The Sierra Club believes that none of these "preferred alternatives" are environmentally sound
choices.
 4.  IN-CHANNEL DISPOSAL

 The only dredge methodology considered is described as longitudinally segmented, as the channel
 is dredged, with some temporary initial storage of sediments in barges (Vol I, page 4-7). The
 alternative exists, but was not covered adequately in the DEIS, to dredge the channel deep enough
 to provide space for berth sediments as well as channel sediments. This only shows up in the
 document as a late appearing option (Vol n Table E-18).

 Considering that the proposed Conditions/Impacts (Vol I, page 3-40) of in-channel dredging
 appears to have a more acceptable environmental impact analysis, we urge that the Corps and
 Massport should prepare a Supplemental Environmental Impact Statement which provides more
 in-depth analysis of options other than open water disposal including in-channel and shoreline
 disposal options.

 The Sierra Club believes that this option merits more in depth analysis.

 5.  SEDIMENT CONTAMINATION

 The U.S. Army Corps and the EPA have different findings for characterization of contaminated
 sediments.  The Sierra Club supports the EPA's findings mat all silt material is contaminated and
 must be disposed of properly. We urge Massport and the Corps to consider all silty material to be
 dredged as "unsuitable". The Sierra Club objects to any rectification of contaminated material
 as suitable, by mixing, matching, or any other methods.                                    —

 &, DREDGING PROCESSES

 Based on past experiences, the Sierra Club feels the dredging process should be carefully
 monitored and methodology and techniques used should be covered more thoroughly in the SEIS.
 At the Moran Terminal dredging last winter, the environmental "bucket" often did  not close
 properly on the way up due to debris on the bottom and trash in the sediments. We would like to
 see the entire dredging process monitored by an impartial observer and contingency language

-------
placed in any contracts for dredging and disposal which would require work to halt should
problems occur. Also, we would like to see performance standards for dredging put into the
Dredging Management Plan in addition to the descriptions of equipment and methods. Also
missing is pre-qualification of dredging contract bidders.                         .          	

7. FUTURE RE-SEDIMENTATION

Silt from future Maintenance dredging will continue to be a problem. The SEIS should develop a
50 year plan that examines more thoroughly what causes re-sedimentation, and how it can be
prevented. The source of most sediments MIGHT be the beaches found under many docks, and
holes in bulkheads. These beaches and bulkheads are strongly washed by waves caused by wakes,
which wash sediments into the berths and channels. The wakes are very intense during the boating
season.  Also, CSOs and various other drains into the harbor may have no grit retention
chambers.   We urge Massport and the Corps to work towards elimination of sources of
contamination in Boston Harbor so that future dredge wastes can be disposed of more safely and
economically.                                                                        —

8. CONCLUSIONS

Because of the reasons stated above the Sierra Club believes that a Supplemental Environmental
Impact Statement must be prepared and circulated for public comment for this project  If
conditions in the North Channel are not considered and addressed, millions of dollars of public
money may be wasted on a project which does not even fulfill its stated goals. In addition, the
project may result in significant environmental damage since none of the Preferred Alternatives
identified by Massport represent environmentally sound solutions for disposal of dredge material.
Circulation of a Supplemental EIS is necessary so that other alternatives can  be reexamined and
commented upon. We urge the Office of Environmental Affairs to reject all of the Preferred
Alternatives, and to require a Supplemental EIS for the Boston Harbor Navigation Improvement
Project.

Thank you for the opportunity to comment.

Respectfully submitted by the Massachusetts Sierra Club.

-------
E9-1

        Discussions with shippers during preparation of the Feasibility Report indicated that
additional underkeel clearance was not required to transit the North Broad sound channel;
project benefits are based on shippers actual operating practices.  They represent the difference
in transportation costs with and without improvements. The 1988 Feasibility Report found
that improvements to the north Broad Sound channel were not economically justified.  The
North channel is maintained at -40 feet MLW. With the BHNIP, vessels will have safe 40
foot access from deep water to the terminals in the Mystic, and Reserved channels and 38 feet
in the Chelsea River channel.  For additional information, please refer to the 1988 Main
Report and Appendix 1  of the Feasibility Report.
E9-2

        The disposal site alternatives analysis (Section 4.0) has been revised to separate
environmental and practicability issues more clearly.  The selection of the preferred alternative
focussed on the sites that had the lowest potential for environmental impacts.  To determine
the cost/benefit ratio, strict criteria are used to determine Federal participation in a navigation
improvement project.  This criteria does not include the environmental costs, except for
mitigation costs. However, the purpose of the EIR/S is to discuss the environmental impacts
for each disposal alternative so that an informed decision can be made in selecting the
appropriate disposal site for the silly material.  All of the impacts would be temporary. Also,
the 1:1 ratio  refers to the parent material (improvement project), the silty material is
considered a maintenance project for a project already authorized.  Benefit/cost ratios are not
performed for maintenance projects.
E9-3

        The disposal site alternatives analysis had been reevaluated for the FEIR/S (Section 4).
The offshore sites were determined not to be among the least environmentally damaging
alternatives and are no longer being considered as options for the current project.
 E9-4
        See response to comment E9-3.
 E9-5
        See response to comment E9-3.
                                            20

-------
E9-6
        See response to comment E9-3.
E9-7
        In the revised disposal site alternatives analysis, the Spectacle Island CAD site was not
selected as the preferred alternative for the silts from the BHNIP.
E9-8                                         i

        In-channel disposal was discussed in both the alternatives analysis (Vol. I) and
Attachment 1 of the DEIR/S. It has been reexamined, along with all other potential disposal
sites, in a revised alternatives analysis (Section 4 of the FEIR/S) and was determined to be the
least environmentally damaging practicable alternative (LEDPA).
E9-9
                                              i
       Both the DEIR/S and the FEIR/S assessed the selection of appropriate disposal sites
for the BHNIP silt assuming that all the silt was unsuitable for unconfined open water
disposal.
E9-10

       A Dredged Material Management Plan is discussed in Section 5.0 of the final EIR/S.
Pre-qualification is the "exception to the rule" in Corps contracting procedures.  Typically a
project is open to bids from all contractors. Before a contract is awarded, the apparent low
bidder is examined to determine his capability to be "responsive" to the specifications.  This
typical procedure is intended to allow more competition yet still provide scrutiny of a
contractor prior to award.

       The Massachusetts Sierra Club believes that there should be an impartial observer not
only during all disposal operations, but also during dredging, blasting, dewatering, and other
project activities. As noted in the FEIR/S, the Corps does not typically fund this type of
activity although it does contract with a dredge inspection firm which verifies disposal
locations. Independent observers can be accommodated, but the  independent observer can only
alert the Corps inspector of any perceived permit violations. However, only the Contracting
Officer can modify or halt dredging and disposal operations.

       The FEIR/S, Section 5.0, Dredging Management Plan, discusses specific equipment
and operational contingencies. Section 5.8.2.2, Trash and Debris, discusses specific
contingencies for potential problems related to those factors. In addition, it is noted that the
construction operations, specifically dredging and disposal, will  be required to meet certain
minimum environmental criteria which will be incorporated into the conditions of the project
permits.
                                           21
                                                -331

-------
E9-11

       Future maintenance dredging disposal needs are discussed in Sections 2.0 and 4.0 of
the FEIR/S.
                                          22
•3X2.

-------
                                                                                   E10
BOARD OF DIRECTORS
BETH NICHOLSON
Chairperson
BETSY JOHNSON
President
ROBMOIR
Vice President
PETER SHELLEY. ESQ.
Treasurer/Clerk
NANCY ANDERSON


RICH DELANEY


JOHNDINGA


	= FINDLAY


   .-OSTER


SHEILA LYNCH


ROBERT SPENCER


NANETTE TERRY


MARGIE TYRE




HONORARY DIRECTORS

PAUL GARRITY. ESQ.
Honorary Chairperson

WILLIAM B. GOLDEN. ESQ.


IAN MENZIES



STAFF
BRUCE BERMAN
BayWarch Director


JANEY KEOUGH
Operations Manager

JODISUQERMAN
Policy Director
                       Save the Harbor
                       Save the Bay
                       Founded 1986
June 28, 1994

Brink  P.  Miller                     •
Colonel, Corps  of Engineers
U.S. Army  Corps of  Engineers
424  Trapelo  Road
Waltham, MA  02254

Dear Colonel Miller:

Save the  Harbor/Save the Bay  (SHSB)  is  a non-profit, citizen-based
organization  dedicated to  the  protection  and  promotion of  Boston  Harbor
and  Massachusetts  Bay.   We are writing to  express  our concerns about the
draft  environmental  impact  statement/report (DEIS/R)  submitted  by
Massport  and the Army  Corps  of Engineers  for  the  Boston Harbor
Navigation  Improvement  Project  and  Berth  Dredging  Project (BHNIP).

Our major  issues  regarding  the BHNIP  concern the dredging process itself,
and  the handling and disposal  of sediments,  many  of  which  are
contaminated with  heavy  metals,  PCBs,  PAHs and other toxic materials.

The   Dredging   Process

From  experiences  at  Moran Terminal, we learned the  dredging process  can
be  very messy.   When  debris  prevented  the clamshell dredge  from  closing
properly, sediments  spilled into  Boston Harbor.  We  would like  to see the
entire  dredging  process   monitored  by  an impartial  observer  with  the
authority  to  halt  dredging that is in  violation of permit  conditions  or
otherwise  environmentally dangerous.    Also, we  would  like contingency
language  placed in  any  contracts for dredging   and  disposal  which  would
require work to halt  should problems  occur.   Finally,  we would like  to  see
performance standards  for dredging  put  into  the  Dredging Management
Plan (Section  4.0)  rather  than  descriptions  of equipment  and methods.   This
would  help ensure  a  cleaner  and  safer  dredging process.                   _

Disposal   and   Future  Dredging   Projects                              _

On  page  1-5 of the  DEIS/R,  one of the  three interests  associated with
efficient port operations  which  this  project  is designed  to  serve is    listed
as,  "Identify potential  disposal  options  to  serve future long-term
maintenance  requirements to  meet regional needs  including  Boston
Harbor."   Page  3.1  states, "...  future  maintenance of the  channels  is  closely
linked  to  the  BHNIP, therefore,  the;  disposal alternative  analysis also
identified  alternatives that could  be useful for  future  dredging."   Save  the
Harbor/Save the Bay wants  to ensure that the  disposal  site(s)  chosen for
the  Boston  Harbor  Navigation  Improvement Project (approximately  2:9
million cubic yards of material -  1.1  cubic yards of which are
contaminated)  shall  not  be  used  for future maintenance  dredging
(according  to  this  DEIS/R,  future maintenance  dredging  could  produce  as
              25 WEST STREET, FOURTH FLOOR • BOSTON, MASSACHUSETTS 02111 -TELEPHONE: (617) 451-2860 • FAX: (617) 451-O496  ©

-------
much as  6.2  million cubic yards of  contaminated  dredge spoil  over the next
fifty  years)  and  other  regional  dredging  projects  until  the  sediment  quality
and  environmental impact  for  those  projects  are  analyzed with  time for
public comment.  We would  like this stipulation to  be very clear in  the  final
impact   statement.                                                          -

Sediment    Characterization

First, the exact amount of material being  dredged-up as  a  result  of this
project is unclear in  DEIS/R.   In some places  the DEIS/R   states  that,  in total,
2.9 million  cubic yards will  be dredged, in  others, the document  says 3.5
million  cubic yards  will be dredged.   SHSB would like the final  impact
statement to be clear in regards to the amount of dredged material this
project   will  produce.

The U.S. Army Corps  of  Engineers  has  found that all maintenance material
(silt), except  160,000 cy from  Reserved Channel,  and 200,000  cy  from  the
berth areas  of Gulf  Oil, Army Base,  Conley terminal,  and the  Edison Barge
berth is unsuitable for unconfined open water  disposal.   The U.S. EPA has
conversely  found that  all silt  material is  unsuitable  for  unconfined  open
water disposal.   We support  the EPA's findings  and  oppose unconfined
ocean disposal  of any  silt material.

Disposal   Alternative   Analysis

The MEPA  scope for  the  DEIS/R identified ocean  disposal at  Massachusetts
Bay  Disposal  Site (MBDS) as the  preferred disposal  option for marine
sediments of  acceptable quality from  the dredging projects  and  the
alternative  against   which other alternatives would be judged.   We  believe
that using the MBDS as a basis for  comparison of all  disposal  options, for
both clean  and contaminated  sediments, skews the analysis as it is  illegal,
without  a waiver, to dump contaminated sediments  at this site.   W e
absolutely   will  not  support  any   disposal  option which  would
require a  waiver  from   Section   103(d)  of  the   Marine  Protection,
Research,   and  Sanctuaries  Act  (MPRSA),  or   any   other   legal
waiver.   Therefore,   disposal options  suitable  for  contaminated sediments
should  be  compared against  each  other  in the final  impact statement,  not
against  the  MBDS.                                                           —-

The  DEIS/R does not provide a full  costing  of disposal  alternatives.
Environmental  costs, such as  habitat  damage or  contamination,  are  not
 included.    Also, disposal sites of both  clean and contaminated  sediments
must  be carefully   monitored  by   impartial  observers  with  contingency
 plans should problems  occur.   This  is particularly important at  the MBDS,
 where it is likely that  clean  parent material will be disposed.  The MBDS is
 adjacent to the  Stellwagen Bank National  Marine Sanctuary,  one  of our
 most important natural  resources in  Massachusetts Bay  and  must be
 protected.   The  costs of this  monitoring  are  not  factored  into the
 cost/benefits  analysis of the disposal options.   These costs must  be

-------
considered  in  the final  impact  statement.

In addition,  the  costs  to  other resource users  of using certain  disposal
alternatives  (i.e.  Fishermen,  Lobstermen)  were  not  considered  in  the
discussion  of disposal  alternatives.     These costs  should be considered in  the
final  impact statement.

Although  cost/benefit analysis  is  not required  in the EIR, the Certificate of
the  Secretary  of  Environmental  Affairs  on  the Environmental  Notification
Form (EOEA #8695)  for  this project states,  "... the  cost/benefit issue appears
to be  germane  to agencies'  decisions with  respect to  this dredging  and
disposal project,"  and the regulations  (301  CMR  11.01  (4)) provide for it.

Lastly,  given  the constantly increasing pressures on  the resources  of
Massachusetts Bay, we would  like  the  final impact  statement to  analyze
cumulative  impacts.    In particular,  higher  levels  of  contaminants
introduced  into the  system  through ' dredging  projects (both BHNIP  and  the
Central Artery  Third  Tunnel Project),  non-point  sources  of  runoff,  and  the
MWRA outfall, for  instance, should be addressed in concert.

Disposal   Options

We  are  absolutely opposed to any  open ocean disposal of contaminated
sediments.    We would like to  see a portion  of  the contaminated dredge
spoils  set  aside for  a pilot  project  that would test the  efficacy of alternative
technologies in reducing  toxicity  of contaminated sediments.     Generally,
we would like  to see clean  sediment used beneficially to upgrade  habitats
and  already contaminated areas wherever possible.   Our  goal  is  to  minimize
damage to  and exposure  of  contaminated  sediments  to the marine
environment as  much as possible.    To that end, we have problems with
each  of   the  preferred  disposal  alternatives delineated by  Massport  and  the
Corps  in  the DEIS/R.   Therefore, we would like  the  final impact statement to
look  more  closely at the  "potentially  practicable"  disposal  alternatives.
                                     i     .                                    .

In addition,  we have  specific  comments about  several  of the
"preferred  alternatives":

•      It  is currently  illegal to dump  contaminated  sediments at the
       Massachusetts Bay  Disposal Site  (MBDS) without a legal  waiver.   Save
       the  Harbor/Save the  Bay  is  particularly  concerned about  this
       potential   option  and  will  ;not,  under  any  circumstance,
       condone   disposal   of  contaminated  sediments  at   the  MBDS
       including  capping  with clean; sediments.   We • oppose  any pilot
       project  at  the MBDS which  would  test the efficacy of  capping
       contaminated  sediments  at  this location.  At  this point,  the DEIS/R is
       unclear in its  description of  the  MBDS  as  a disposal alternative.   At
       some points it describes the MBDS  as a  preferred alternative for both
       clean and  contaminated  sediments  and  at  other points  it  does not.
       The final  impact  statement  must be  very  clear  in  its  prohibition of
E10

-------
      disposal  of contaminated sediments at the MBDS.  In  addition,
      Massport and the Corps should be  working  closely with  Brad Barr,
      manager  of the Stellwagen  Bank National  Marine  Sanctuary,
      regarding  any  disposal  of clean sediment  (parent material)  that
      might  occur at the MBDS.
      Save the Harbor/Save the  Bay will not  support  disposal of clean or
      contaminated  sediments  at the Boston Lightship  area  until the  U.S.
      Environmental Protection  Agency  completes  a  thorough  study  of the
      extent and  location of radioactive barrels in  the  area.    It is possible,
      once the location  of radioactive ban-els  is known, that  disposal  of
      clean sediment  at  the site could prove beneficial.    However, in
      addition to location  of  radioactive barrels, a  study on how they  will
     • be affected by  disposal of sediments  must also  be completed.
~l
                                                                             ~1
       Both of the  Meisburger sites  (#2  and  #7) listed as preferred
       alternatives are adjacent to the MWRA outfall.  That  site was  chosen
       for  the outfall because of  the  strong cross-currents  and potential  for
       "mixing."   It  seems these sites would not be  stable enough  for
       disposal of contaminated sediments.   In  addition, using  these  sites
       might  complicate the  outfall monitoring.

Massport and  the U.S. Army  Corps of Engineers should be conscious  of the
other projects and problems  in Boston Harbor in  their  planning  and   in
their  preparation  of the final  impact statement.    These include: the  Harbor
Clean-up,  the Central Artery  Tunnel project, the recent  designation  of
Stellwagen  Bank  as a  National  Marine  Sanctuary, the existence of  highly
contaminated  ~  and sometimes radioactive  — "hot spots,"  and  a very
strained  fisheries  situation.   All  of these will affect, and  be  affected by, the
dredging project.   Massport  and the Corps should continue  to  work  closely
with  other affected  parties to devise creative solutions to deal  with
contaminated  sediments  that  will  benefit Boston Harbor  as  both  a  natural
and  economic resource.    Save the Harbor/Save  the Bay  is committed to
working with Massport  and  the  Corps  throughout  this  process.

Lastly, although  Save  the  Harbor/Save  the  Bay  supports the  maintenance
dredging  of  Boston Harbor's  shipping  lanes  and  berths  to  perserve  the
port's economic  vitality,  we  would  not  support  any dredging that would
open  Boston Harbor to  "super-tankers."

Thank you for the opportunity to  make  these comments.   We look forward to
reviewing   the  final impact   statement.
 Jodi  Sugennan
 Policy  Director

-------
 E10-1

        Save the Harbor Save the Bay believes that there should be an impartial observer not
 only during all disposal operations, but also during dredging, blasting, dewatering, and other
 project activities. As noted in the FEIR/S, the Corps does not typically fund this type of
 activity although it does contract with a dredge inspection firm which verifies disposal
 locations. Independent observers can be accommodated, but the independent observer can only
 alert the Corps inspector of any perceived permit violations. However, only the Contracting
 Officer can modify or halt dredging and disposal operations.

        The FEIR/S, Section 5.0, Dredging Management Plan, discusses specific equipment
 and operational contingencies. Section 5.8.2.2, Trash and Debris, discusses specific
 contingencies for potential problems related to those factors. In addition, it is noted that the
 construction operations, specifically dredging and disposal, will  be required to meet certain
 minimum environmental criteria which will be incorporated into the conditions of the project
 permits.
E10-2

        Although the FEIR/S identifies disposal sites that would potentially be suitable for
disposal of contaminated sediments from future projects, future disposal could not take place
without following appropriate permitting procedures, including testing of sediment quality.


E10-3

        Inconsistencies in the DEIR stated amounts of material to be dredged have been
corrected for the FEIR/S. The expected silt volume is approximately 1.1 million cubic yards
(mcy) and parent material volume 2.1 mcy. Because the dredging process tends to expand the
silt, the disposal site may need to accommodate up to 1.3 mcy. Table 2-6 in the FEIR/S
shows the breakdown of these volumes.
E10-4

       Both the DEIR/S and FEIR/S considered all BHNIP silt to be unsuitable for
unconfined open water disposal for the purposes of identifying sufficient disposal capacity.
E10-5
       The MBDS is not considered for the disposal of silts from the BHNIP in the FEIR/S.
E10-6
       It is very difficult to estimate the environmental damage, if any, from a particular
disposal option. Management plans to reduce or minimize costs to fisherman can be
implemented, such as marking disposal traffic lanes. Disposal barges will be manned by a
                                           23

-------
Corps inspector familiar with NMFS guidelines for vessel traffic.  A detailed Dredge
Management Plan is included in the FEIR/S (Section 5.0).
E10-7

       As the silty sediments will be staying within Boston Harbor, no cumulative impact to
Massachusetts Bay is expected.
E10-8

        The potential disposal sites were reevaluated in the FEIR/S. It was determined that the
in-channel, partial-fill shoreline, and upland alternatives were the least environmentally
damaging alternatives.  Parent material will be made available for closure of municipal
landfills.  Rock will be used for armoring confined disposal sites.
E10-9
        The MBDS is not being considered for disposal of silts from the BHNIP.
        The Corps has not ruled out a demonstration project to test capping efficacy at the
MBDS to evaluate potential future use of this site for silt disposal. Coordination with
appropriate agencies would occur prior to initiation of a project.

E10-10

        Boston Lightship is not proposed for disposal of BHNIP silt in the FEIR/S (Section
4.0). Should interest in this site arise in the future, its use will require coordination with EPA
regarding the proported drums of industrial and radioactive waste at this site. Disposal of
dredged material at this site to cover these drums may benefit the environment of this area.
The EPA should play an active role in researching the locations and environmental status of
any hazardous materials at the BLS to determine whether  it would be best to leave as is,
remove, or cover in place.
 E10-11

        Neither Meisburger site was selected as the preferred alternative for disposal of BHNIP
 silt in the FEIR/S (Section 4.0).
 E10-12

        Massport and the Corps are very much aware of other significant projects occurring in
 out proposed project area. We have been and continue to work closely with the staff of these
 agencies.
                                            24

-------
E10-13

        The purpose of the proposed project is to reduce tidal delays for ships currently using
Boston Harbor.  Deepening the tributary channels may allow larger ships to transit Boston
Harbor, but would not be deep enough for "super-tankers". Also the tunnel crossings and
turns limit the use of "super-tankers" in Boston Harbor.
                                           25,

-------
06/23/1994 18:35    5087B01036
                                      STOP
                                                                  PAGE  02
                                                             E11
                                           S. T. O. P.
                                     (Stop the Outfall Pipe)
                                          530 Main Street
                                       West Dennis, MA 02670
                                    (508) 394-8964 * (5O8) 385-4209
        Colonel  Miller
        U.S.  Array Corps of Engineers
        Impact  Analysis Si^Lsion
        •4"2~4"" Trap's lo'Road
        Waltham,  Massachusetts  02254

        Dear  Colonel Miller:

             Stop The Outfall Pipe welcomes the opportunity to
        comment  on the DEIR/S for the Boston Harbor Dredging Project.
        Though we are not opposed to the dredging project, we are
        greatly concerned by a number of suggestions and proposals
        found throughout the DEIR/S, particularly concerning the
        disposal of dredge spoils.  Below you will find a list of our
        concerns:

        *          Under no circumstances should the MBDS or the two
              Meisburger sites be considered-suitable sites for an_y.
              contaminated spoils, today or in the future.   Capping
              should not be considered, a mitigation measure as it is
              not a proven technology, particularly given the depth
              of these sites.                 .
                   The proximity of these sites to the many
              endangered species that live on Stellwagen Bank and
              Stellwagen's stature as a National Sanctuary are of
              particular concern to our organi2ation.  In addition,
              we have many concerns about the cumulative impacts the
              dredge spoils will have with all of the other uses,
              past and future, to which this area of the Bay .is host
              These include but are not limited to the proposed
              outfall discharge from the 43 municipalities
              surrounding Boston and the existence 'of the barrels
              found in and around the "foul area,"
              species
     Given their proximity to the many endangered
        that live on Stellwagen Bank and Stellwagen's
stature as a National Sanctuary, even disposal of clean
sediments at these sites should require the strictest
oversight by the State as well as the National Marine
Fisheries Service and NOAA.
                                                                       i

-------
10:35
    5037581835
STOP
PAGE  Q3
        Determination of the "cleanliness" of  the
   sediments to be disposed of should be made  by an
   outside,.independent group of overseers who apply  the
   strictest, most consistent standards possible.  Based
   on past testing, it appears that none of  the silty
   material to be dredged is suitable for unconfined ocean
   disposal.  We would strongly oppose any attempt to
   reciassify thes.e materials.

        Section 4,5.1 of this document dwells  on studies
   which imply that various groups of pollutants are not
   as great a threat to biological systems as  previously
   believed.  We would suggest that much of  this research
   was performed by those invested in current  dredging
   technology and remind the State and the ACOE of the
   many studies which suggest that, to the contrary, these
   16xTcsT"se"f TousTy impair many biological functions in	
   marine ecosystems.
        One such study, "Pollution .and Development
   Abnormalities of Atlantic Fishes," (released by the
   National Marine Fisheries Service in 1991)  indicates
   that chromosomal abnormalities brought on by many of
   these toxics may account for significant  amounts of
   larval mortalities in the fisheries which thrive in
   Massachusetts Bay.                                 '"  . —

        Throughout this document, reference  is made to the
   "economic benefits" that will be derived  from the
   dredging project and, in fact, maintaining  the Harbor
   as a viable shipping port is important.  But to
   consider only those immediate costs incurred by the
   dredging without considering its long-term  impacts on
   natural resources, environmental integrity, and human
   health is to be "penny-wise and pound-foolish."
        The cost of $18.00 per cubic yard for disposal of
   silt at the MBDS is one of the lowest costs cited in
   this document,  yet it does not reflect the potential
   harm to other'industries and ecosystems from the
                 -bioaccumulat ive toxics at this site.
                 and EPA should redraft the economic
                 which decisions of this nature are made
                 reflect their long-term impacts on the
                                                        1
col lection of
     The ACOE
formulas upon
to accurately
   marine environment.                                    -

        We would urge the State, the Army Corps, and the
   Environmental Protection Agency to consider upland
   areas of disposal where monitoring and oversight would
   be most easily and efficiently accomplished.  Though
   the '"cost"  of this type of site appears quite high,  it
   must be weighed against long term monitoring costs
   (much more  easily done then any ocean site monitoring)
   and long term costs  to other economies including that
   of the fishing and shell fishing industries through


-------
06/28/1994 10:35   5087601036
                                      STOP
                                                                  PAGE 04
                                                                    1
*          If upland disposal is discarded, we would then
      urge the State, ACOE and EPA to consider those sites
      closest to shore and preferably within Boston Harbor.
      These areas are already subject to past and future
      accumulation of questionable sediments and due to their
      shallow nature are most easily monitored.

*          It would seem imperative, with  the valuable     -
      resources of Boston Harbor and Massachusetts Bay being
      placed at risk, that innovative treatment and dredging
      technologies would'be the truly economical solution  to
      the problems of dredging and disposal.  Again, though
      the "cost" of these types of technologies appear quite
      high on the surface, they must be weighed against long
      term monitoring costs and long term  costs to other
      economies including that of the fishing and
      shellfishing industries through contamination, lo.s_t	_
      habitat* e'tc.

*           We urge that these agencies be compelled to
      implement a monitoring plan during disposal and
      afterward which would require strict and  independent
      oversight.  Regardless of disposal options and sites
      these activities require continual management and
      possible remediation.                                  —I

     In conclusion, we would hope that the Army Corps  applies
the highest possible standards to this as  well  as other
activities being proposed for Massachusetts Bay.  We hope  the
federal agencies in  charge of the project  recognize that  the
 "least expensive" alternatives are often only  least expensive
 in the short  term: the potential  for'future expense and
degradation should be of utmost consideration.  Under  the
proposed  formulas, a "cost-effective" solution  today might
mean an expensive remediation project or reduced  economic
benefit from  the Bays  in the future.   We  hope  that  the  State
 and Federal overseers of this project will develop more
 effective cost analysis  formulas  which accurately  reflect
 these concerns.
                    c
 Sincerely,
       Mary E. Loebig,
       (508)385-4209  /
                 Cochair    w
                 (508)398-7632

-------
 Ell-1
        Capping has been proven in Long Island Sound in depths similar to the Meisburger
 sites.  There are several reports published by the Corps on the success of these projects.
 Capping of silts at the MBDS will not be used for this project.
 Ell-2

        Agencies have had the opportunity to comment on the proposed project. MBDS is an
 EPA designated dredged material disposal site.  Only the clean parent material will be
 disposed at the MBDS.
 Ell-3

        The sediment testing for the BHNIP was conducted as part of the Sediment Character-
 ization Work Group. This group, involving most major regulatory agencies and many
 environmental interest groups who played a very; active role in establishing high quality
 standards for all aspects of the sediment sampling and testing. The resultant data are felt to be
 of excellent quality and very representative of the material requiring dredging. Virtually every
 commenter to the DEIR/S agrees that the parent material to be dredged for this project is
 shown to be clean by the test results.

        We acknowledge S.T.O.P.S opinion that none of the silt to be dredged is suitable for
 unconfmed disposal.  Both the DEIR/S and FEIR/S treated BHNIP silt as unsuitable for
 unconfined open water disposal for purposes of selecting a disposal site.
Ell-4
        The disposal site selection process considered impacts to biological
                    resources.
Ell-5
        The Corps has specific guidelines in which to evaluate whether there is a Federal
interest in participating in a navigation improvement project. The environmental impacts are
evaluated in NEPA documents such as this EIS. All of the impacts from the proposed project
are expected to be temporary.  No significant long-term impacts are anticipated.


Ell-6

        Monitoring issues were considered during selection of the final preferred  alternative.
The "ease" of monitoring the integrity of landfill sediment disposal facilities may be out-
weighed by the difficulty of ascribing any "leakage" to one particular waste generator, thereby
making all generators potentially responsible for any future landfill integrity problems.  The
monitoring plan associated with the preferred alternative is described in the FEIR/S.
                                          26
333

-------
Ell-7

       The revised alternatives analysis for disposal of silts from the BHNIP concluded that
in-channel disposal was the least environmentally damaging practicable alternative (Section 4).
Ell-8

       Innovative treatment and dredging technologies are considered for the BHNIP in
Section 3.0 and Appendix D of the FEIR/S.
Ell-9

        S.T.CXP.urges the sponsoring agencies to utilize an impartial observer  during all
disposal operations. As noted in the FEER/S, the Corps does not typically fund this type of
independent activity although it does contract with a dredge inspection firm which verifies
disposal locations. Independent observers can be accommodated, but the independent observer
can only alert the Corps inspector of any perceived permit violations. However, only the
Contracting Officer can modify or halt dredging and disposal operations.

        Section 5.7, Long Term Monitoring of Disposal Sites, addresses the monitoring needs
of the preferred disposal site.
                                            27

-------
                                              Nahant SWIM, Inc.
                                              Safer Waters in Massachusetts
                                                     June 8, 1994
 Colonel Brink P. Miller
 Division Engineer
 U.S. Army Corps of Engineers
 424 Trapelo Road
 Waltham, MA 02254-9149
 Dear Colonel Miller:
                                                     Re: Boston Harbor, Boston Massachusetts
                                                         Navigation Improvement Project
                                                         and Berth Dredging Project
       The worst possible place to dump contaminated sediments from the oily depths of Boston"
 Harbor - laden with heavy metals, PCBs and PAHs - is the location between Nahant  and  the
 Massachusetts Water Resources Authority (MWRA) sewage outfall.  The North Shore will soon be
 the recipient of wastewater from the entire MWRA area, and although we were promised second;
 treatment, it is controversial and questionable whether full secondary treatment will actually occur,
 because of the economic situation.  At best, even if secondary treatment is eventually provided
 approximately  550 million gallons of partially treated sewage will be discharged from the outfall
 between 1995 and 1999, at the same time the dredging spoils would be disposed of. The synergistic
 effect of partially treated sewage plus dredging spoils needs to be addressed by the Corps.  We are
 talking large quantities of waste: the MWRA sewage outfall is as big as the Callahan Tunnel, and
 the dredged material's bulk is as large as the Prudential Building.                           _

       Nahant, Saugus, Lynn and Swampscott have already constructed our own secondary
 treatment plant, but  we  cannot protect oiir  communities  if both MWRA  sewage and
 contaminated  dredged material from Boston Harbor are dumped on the North Shore.

       Both  "Meisburger Two"  (North  Shore) and  "Meisburger Seven"  (South Shore)  are"
 outstanding fishing and lobstering locations, as is the area around the Boston Lightship.  The Foul
 Area (Massachusetts Bay Disposal Site) is much too close both to the North Shore and to Stellwagen
 Bank National Marine Sanctuary.  There should be no dumping at sea.  SWIM objects vehemently
 to disposing of contaminated sediments in clean ocean. Massachusetts Bay is prime lobster habitat:
 according to the Massachusetts Lobstermen's Association, "Approximately 6.5 million  of the  9.5
 million pounds of lobsters harvested in the Massachusetts territorial waters and just beyond  come
 from the general area from just below Gloucester, South through outer Boston Harbor and dowj
^along the Northern section of the South Shore."

       Your Draft Environmental Impact Report/Environmental Impact Statement (DEIR/S) say™
 that no endangered species will be affected. Just because lobsters are not yet endangered does  not
 mean that we should dump silt, especially contaminated silt,  on their habitat.  Finfish may not be
 endangered, but they are depleted, and their habitat should not be further harmed. The sediments
 to be dredged and dumped include "arsenic, chromium, lead and zinc...", "PCB's...", "PAH's...",
 and "acetone..." (DEIR/S, pp. 2-10).
         SWIM, c/o Northeastern University Marine Science Center, East Point, Nahant, MA 01908
                          Phone: C6171 581-0075 or (6VT) 581-1424

-------
       The DEIR/S points out that at Meisburger Two, "Any discernible currents are tidal" (p 3
33). This means that the pollution from Chelsea Creek, Mystic River, and Boston Harbor will b
brought towards shore. There is a multimillion dollar value both to the ocean front real estate an
to the tourist industry on the North Shore. Moreover, millions of people (many of whom come b
public transportation, which is readily available) use the beautiful beaches of Nahant, Lynn, Revere
Swampscott, and Marblehead. Also nearby are Egg Rock (the Henry Cabot Lodge bird sanctuary),
and the new Lodge Park now being developed in Nahant.

       The MWRA outfall and Meisburger Two are also close to the seawater intake o£the
Northeastern University Marine Science Center, a major marine biological research station.
seawater is vital to the experiments being performed  along the coast,  in the water, and in the
seawater tanks in the laboratory.

       The area of Meisburger Two is right in the middle of the lobster fisheries and is habitat nol
only for lobsters but for any migratory species, including bluefish, herring, and  pollack; the area
also is important for recruitment for fisheries (personal communication, Dr. Joseph Ayers, Director,!
Northeastern University Marine Science Center, Nahant).

       Your biological assessment found that the survival of clams in the Mystic River was 44%,
and there was an "exceedance of 20% threshold for amphipods at all proposed dredging locations."
We are talking here adult  animals  that  are relatively  resistant  to  death from  (though  no
contamination from) pollution. What about animals less resistant, that cannot live  in Boston Harbo
now? What about  the increased concentration of pollutants in animals higher on the food chain?
What about larval  forms and juveniles, which are known to be  more vulnerable to pollutants?

        "The development of marine offspring generally takes place in seawater, " according to Dr.
Jan Pechenik of the Tufts University Department of  Biology  (Hazardous Waste 1(2): 273-282
 1984). "Most  species have free-living developmental stage, termed a larva, which spends up tc
 several months swimming in the water prior to its metamorphosis to adult morphology and habitat
 These developmental  stages are particularly vulnerable to water-soluble pollutants,  due to a hig?
 ratio of exposed surface area to body volume. Larvae are approximately ten times more sensitiy
 to  a given pollutant  than are  the juvenile and  adult stages  of the same species.  Substan*«
 developmental  mortality results from low-level exposures in the range of parts per billion to p;
 per million for a variety of pollutants.

        "Sublethal  effects have also been well-documented for a number of developing marine
 animals.   Low levels of pollutants interfere with cleavage and morphogenesis in echinoderms
 arthropods, and fishes. Changes in developmental rate  may be one of the most sensitive and reliable
 indicators of toxicity. Depression of growth rates by direct exposure in water-soluble pollutants has
 been documented  for larvae  of marine gastropods, bivalves, crustaceans, and fishes.  Moreover,
 stressed adults may produce larvae which develop at abnormally slow rates." -

        Contaminating prime Massachusetts  Bay fishing  and  lobstering area  would  also  mean
 contaminating the people who eat fish and lobster. Silts that now pollute Boston Harbor would alsfi
 harm pollute Massachusetts Bay. As for the possibilities of successfully dumping, then capping, the
 site in Massachusetts Bay, the  technology is  simply not that sophisticated, and the process ol
 dredging would stir up contaminants in Boston Harbor.

-------
       The DEIR/S says,  "...the volume of cargo would not be projected to increase due to this
project..." (ES-4). The value of deepened the channels from 35 feet to 38 or 40 feet seems dubious.
SWIM would prefer to see maintenance dredging, not dredging of three to five feet of highly]
contaminated Chelsea Creek, Mystic River, and Boston Harbor channel. Dredging projects have!
typically been unjustified  in most of New England:   an excellent example is the New HavenJ
Connecticut,  harbor, which was dredged  with no increased'economic viability of the New Haven
harbor.

       SWIM requests a public hearing to give us an opportunity to defend Massachusetts Bay and
to inform you in more detail about the animals living off the Nahant Shore.  Do not permit one
environmental disaster to create another.

                                                     Sincerely yours,
                                                     Polly Bradley, SWIM

-------
E12-1

       The revised alternatives analysis for disposal of silts from the BHNIP concluded that
the In-channel alternative was the least environmentally damaging practicable alternative
(Section 4).
E12-2
E12-3
       See response to comment El2-1.
       The Meisburger 2 site will not be utilized as a disposal facility for this project.
E12-4
       The Meisburger sites are not proposed for disposal of the BHNIP silts in the FEIR/S
(Section 4.0).
E12-5
        See response to comment E12-4.
E12-6
        The bioassay and bioaccumulation testing for the BHNIP was conducted in accordance
with procedures established by the U.S. Environmental Protection Agency and Army Corps of
Engineers to evaluate suitability for disposal of dredged material in the ocean. These protocols
were developed to standardize the specific testing and evaluation methods used for assessing
disposal impacts. The protocol development took into consideration the various marine species
available for testing, then: sensitivity to contaminants, bioaccumulation ability, as well as other
factors. The regulatory agencies have determined that the marine crustacean amphipod is an
appropriate sensitive species for evaluating acute toxicity for ocean disposal.

        It is important to understand that the Ocean Dumping testing procedures are intended
to evaluate the impacts of disposal, not the dredging impacts. The bioaccumulation testing is
used to evaluate acceptable body burden levels (sublethal) in the immediate disposal area for
indigenous species as well  as the various food chain consumers of the  "impacted"  organisms.

        The bioassay testing conducted for the BHNIP used the whole sediment phase of the
proposed dredged material since this phase represents the majority of material at the disposal
site over the long term.
                                            28

-------
E12-7
        See response to comment E12-4.
E12-8

       The Corps has extensive experience with capping dredged material which is
documented in several DAMOS reports.
E12-9

       An economic analysis was conducted, and updated, to verify that there is a Federal
interest in deepening Boston Harbor.  As a matter of fact, it is the maintenance material (silt)
that is contaminated which needs to be removed first before the deeper layer of clean parent
material can be removed. Removing only the maintenance material will not solve the problem
of silt (maintenance) material disposal.  Your statement that most dredging projects in New
England are not justified does not appear to have any substance. For the past 30 years, all
navigation improvement projects are required to have a benefitcost analysis to confirm that
there  is a Federal interest in building a particular project.  Included  in this analysis is an
evaluation of the need and cost for maintenance dredging of the proposed project for the
economic life of the project. Such is the example of New Haven Harbor which is a vital and
critical harbor for New England.
E12-10
       A public hearing was held in Nahant on July 28, 1994.
                                          29
                                                 -33?

-------

-------
COMMERCIAL INTERESTS
  COMMENTS AND RESPONSES

-------

            'iiiii'ijni	hi i liiiliiiiiiiiipiiSiViiiiiiixiiiipV! iiiiiiiiiiiiniiiiiiiiiiiiiiiihiiii, < iiiiiiiiiiiiiiiiiiiiir Hwa ii'iiiiiiliiiiiiiiii  i<, iiii'iiliiiiiiiffiiiiiiiiiTRiiiniiiiiiiiiiiiii'iii'v'Viiiii'liiiiiHPH«JiiiiiiHiiiip iliiKiUiiiinKJiiiiJivii'iiiiiKi.iiiiTiii.iiSSiw^             iliiiirjiiiiiii'iiiinii 'siii'Siiiiniiiiirv liiii'iiiAiiiiiiiiBiiiiiiiiiiiiiniiiiiiiiiiiiiii iiiiiiiiiiiniii.1. iii'iikliiiiliiilii'iiiiiiii,' i, • i'» d iit' >i'»iiii	i!,1; '«'«• a1 < T ' i   • i«: v:'  '

                          	:   •                        ,                 ,    "   :'in
,„! i, i" zz", ,i zz,""",,", ^ijiiiiiii'iizi'""! ,1 zzz z,""... ~".. ~:. z",i zzijE1 r 'z' i,
                                                                                                                                                                                                                   .
                                                                                                                                            "•'  ""i,   •       HI'	,;  M;  ''•, •       "   •             •     " •.,  •   I-1!!!,:,:    '     •   •     ,	,                          •    ,
                                                                                                                                         -
                                                                                                                                                                                                ji!ii!!ii;!i!!y!!lii;:i!!iiii;iiiliillill!;ii                                                        tf:
                                      llliillli'i^^                              lllllllllllllllllini.iJi'liillllll'I'liilliillJilllll!!
                                                                                                                                                       iaiiiliiiiiiiiiiiiKiiiiiiiiiiiiliillliiiiiiiiN^                                           niK'niniijigiii!            -  '


                                                                                                              nwwi'WPiin'i'^	ii:»iiiii|Uli igii
                     	' •"'!!''!!'"";!	|!	"I	'"!""'""!	'	1'"1""''	"'	J •	I"!1'"]''"	"'!	'!
                                                                                                                                                                                                                                                                                                                                                          hill      III

            iJiiiiiiiEitiiiiiiijIiili                                                                                                             	iijiiiii!!ii:i:!,i!ii!jii!;;iiii'ii!iisi»!!!iigiii!iii»i!i^	^w^WQwyftwtWM*..


                                                   n	ppppi	Piiiiiraiiipiiiiiiiipiniii,: iiiiiiiiiiPiiiiiliiiii	raii'H	'PMP'PPIPIIIIIPIIUPI	ppupHpiTPtPinpiPppp"!	HIIHIIIFIP 'i;!!,: tni ni'ppiiiii'iiriii i ;i	niiipniiiiiiiiiiiiii iiiniPil'F'iB! n	PPP m\KR 't f

                                                                                                                                                                                                                                                           1'UI «#'  ! i4ffif'; •'•«'! \\", „;'"; i, i * i „,	!''" I ;,l,
                                                                                                                                        piini !i'iiiiiiF'ii,iiii	inppnPi	iiigiiiiiiEiiiii'iiiiEiiiiiiiiiiiiipiiPiiiiiiiiniii	iiiiiiiiPiiiiPiiiiiiiiiiiHi'i'liiiiiiiiiiiiiiiiPfHiii'Vi iiiiiiiiiiiiiiplipiiiE'iiPiiiiiiUiiiiii; iivniiPinii'iiiiniii" ^PI <\ ^i!
                                                                                                                                     i:9:ii|:::|ji:::^

-------
            Bostongas
                           Boston Gas Company
                           201 Rhcermoor Street
                           Boston. Massachusetts 02132
                           Telephone (617) 3234210
                                                  U. S. Army Corps of Engineers
                                                 .424 Trapeio Road
                                                  Waltham, MA 02254-9149
                                                  Attn: Coione! Brink P. Miller
                                                 June 15,1994
          Dear Colonel Miller
          Boston Gas has reviewed your Public Notice dated May 13,1994 concerning"
          your proposed Boston Harbor Navigation Improvement Project.

          We have a 24" steel, concrete encased gas line crossing the Chelsea River near
          and southwest of the Chelsea Street Bridge, that is the only feed to the 10,000
          residents of East Boston and the Massachusetts Port Authority's Logan Airport.

          The minimum elevation of our 24" line is - 40.3'

          We have received a letter from the City of Boston dated February 15,1994, cop}
          enclosed, that they are planning to replace the existing Chelsea Street Bridge
          which has a 95' span with a new structure that has a 380' span.

          Do you have any plans to widen the channel in this area?

          Ensuring the safety and continued service of this line are of the utmost concern
          to Boston Gas.

          I would appreciate it if you would keep me abreast of the progress and any
          changes to this project I may be reached at (617) 723-5512 extension 4247.
r B. Landin
sns Engineer
                                                Very truly yours,
                          «L
                  Bostongas
201 Wvemwor Street    \
West Roxeury. MA 02132
(617) 723-5512 Ext. 4247
FAX: (617) 323-9808
                               Walte^g. Landin
                               Operations Engineer

-------
Cl-1

       At this time the Corps of Engineers has no plans to widen the channel in the vicinity
of the Chelsea Street Bridge. However, if the City of Boston proceeds to replace the bridge,
the Federal channel will likely be widened to remove the current width restriction. The
location and alignment of the new bridge will determine the geometry of the channel modifica-
tions.

-------
                                   Boston Harbor Docking Pilots
                                   36 New St.
                                   East Boston, Ma.  02128
13 June, 1994

Col. Brink P. Miller
U.S. Army Corps of Engineers
424 Trapello Rd.
Waltham, Ma. 02254
 ear Col. Miller:
My  colleagues and  I  would like ito express  strong support  for the
Boston Harbor Navigation Improvement and Berth Dredging Project.  Swift
approval  is  urgently needed in order for Boston to  retain its ability
to serve the needs of today's ocean-going ships.

Due  to  economies of  scale and  advances in  technology,  larger  sized
ships are becoming the standard.

Often sharing  space among  two  or more  shipping  companies due to the
tremendous investment  required  to  build  and operate,  these vessels
carry much more  cargo,  at significantly  deeper drafts,  than  their
smaller predecessors.             :
Such  ships  operate  on tight  schedules where  timing is  critical
terms of berth availability and longshore labor commitments.
in
Moreover, dependable  on-time  delivery is one of the prime inducements
the  containership  lines  offer in; order  to  attract  shippers  to use
their particular  service.   In  the highly  competitive world of liner
shipping, these attributes are taken for granted by the customer.

If a  port  cannot accommodate the  needs  of the  steamship companies tc
get  in   and  out  of  port  without  any  delay  caused  by waiting  for
sufficient tide to safely float their ships, the port  will inevitably
sufler the  loss of  this  business with  all of  the attendant economic
dislocations.                      '

As docking  pilots,  our task  is to guide  these  huge vessels into an
out of their berths using the assistance  of  tugboats  provided by th
Boston Towing and Transportation Company.

At the increasingly deeper' drafts now common, we are being required t
handle ships with less and less under-keel clearance  in order to get
them in and out without tidal delays.

At best,  this makes the ships less maneuverable and reduces the margir
of safety inherent in having more water between the bottom of the ship
and the  harbor  floor. It  also causes a great dea-1 more turbulence due
to  increased  pressure  between  the  ship's  hull  and  the  bottom,
resulting in widespread resuspension of bottom silts.

-------
The worst case scenario is much less palatable.

There have been  numerous  instances where, faced with  delays  of up to
nine  or "ten  hours,  made  even  less  acceptable  by   the  fact  that
resulting dockings may occur during hours when longshore labor must be
hired at premium rates,  the shipowner has opted to bypass the Port of
Boston  entirely, proceed  to  the  next  scheduled  port . and  ship the
Boston cargo by truck.

Neither the  containership  company nor the Chipper or consignee of the
cargo  consider the resulting  delays and  increased costs acceptable
Both will soon find other, more dependable ways of meeting their  goals
of on-time, predictable shipment  of goods.

Tankers are subject to similar delays and restrictions. They  cope with
the  situation  by  lightering  cargo  to  barges  in  the  anchorage or
unloading  part of their  cargo elsewhere before  coming to Boston, in
order to reduce  their draft.

The result is  increased transits  of vessels  along the  coast and within
the  harbor and  additional  transfer of petroleum products, increasing
the costs of these products to all  of us  who drive  an  automobile, heat
our homes and  offices, or  turn on an  electric light or appliance.

Additionally,  we are required to accept  the statistical  inevitability
that  multiplying the number of  such evolutions increases the  risk of
an accident.

All of the above considerations  point  to the not-so-subtle conclusion
that  there are some genuine benefits  to the environment to be realized
by going forward with the dredging of Boston Harbor.

Clearly,  Boston's  ability to  continue as  a legitimate  port  of call
with  the  wherewithal  to  sustain  the  needs of  modern  ocean-borne
 commerce is  at risk.

 The threat  to  our  economic survival  is  not several years  down the
 road, but right now!

 Without dredging,  Boston will cease  to exist as  a viable  commercial
 seaport.


                               Sincerely yours,
                               The Bpston Harbor Docking Pilots
                                Captain  David P. Galman
                                Senior Docking Pilot

-------
C2-1

       Thank you for expressing your support of the BHNIP. The information you have
included is useful in demonstrating the need for the project.

-------
    BOSTON PILOTS, Pier 1, S. Bremen Street, East Boston. MA 02128, 617-569-4500
                                      June  08, 1994

    Colonel Brink P. Miller
    U. S. Army Corps of Engineers
    424 Trapelo Road
 JJlWaltham, MA 02254eet

VI  Dear Colonel Miller:

    Historically,, the Port of Boston has been  one  of  the major""
    shipping ports on the East coast.   It retains  that
    prominence to this day.

    However, as the vessels plying the  oceans  throughout the
    world get larger and deeper, Boston becomes  1-ess  attractive
    as a deep water port.  There are currently many vessels
    engaged in trade between Europe and the United State that
    can't call on Boston because of draft limitations.

    It is absolutely imperative that if Boston wishes to remain
    a major East coast shipping port, the navigable channels anc
    selected berths must be dredged to  accommodate deeper draft]
    vessels.

    To this end, the Boston Pilots wholeheartedly  endorse the
    Boston Harbor Navigation Improvement and Berth Dredging
    Project as jointly proposed by the  Massachusetts  Port
    Authority and the U. S. Army Corps  of Engineers.

    Without this dredging, it is safe to say that  the number of
    ships utilizing the port will decrease  over  the next few
    years.  Obviously, with a decrease  in the  number  of vessel
    movements comes a decrease in the number of  people employed
    to service these ships, including the Boston Pilots and the
    pilot vessel crews.                                        __

    •We strongly urge you to support the dredging of  Boston
    Harbor.

    Sincerely,
    A. G. Whittemore
    Representative

-------
C3-1
       Thank you for expressing your support of the &HNIP.
                                         3

-------
                       The BOSTON SHIPPING ASSOCIATION, Inc.

                       Cterlestown Navy Yard, 33 Third Awue, Suite 1. Boston, MA 02129-4515

                       Te/ephoue (617) 242-3303, FAX (617) 242-
-------
C4-1
      Thank you for expressing your support of the BHNIP.
                                            BV?

-------
                 BOSTON TOWING S TRANSPORTATION COMPANY
r
14 June,  1994

Secretary Trudy  Coxe
Mass.  Executive  Office
of Environmental Affairs
MEPA  Unit
100 Cambncce  St.
Boston,  Ma.  02202

Dear  Secretary Coxe:

Cur  company  operates a
                                                        JUH
                                 flee--  of  tugboats
        derived from these sectors  is  roughly equal.

              ntiv   the future of the  Port of Boston is in Deo?arcv due
        smaller  predecessors
         snLoer  whoie customers demand punctual  delivery of  gooes in or.e.
         contoi the high cost of excessive  inventories.






         high tide.




         ship's  next  port  of  call.
.Given the business constraints aescribea above

-"             JSHh.
  This  would seriously  impaot our
                                               *
                                                                     Boston.
                                                                    .  Jnd"
                                       TON. MASSACHUSETTS 02128 1617) 56~-9WC
                                         : TUGBOATSSOSTO* MX- 6.7

-------
The same  holds true for countless  other  businesses  serving the per:
Including  stevedores,  repair  services,  fuel  suppliers,  stear.sr.:
agencies, etc.

It is a  certainty that any further delay in dredging will  relegate
Boston  to  the  status  of  a backwater  port  as  shipping  lines abar.d:
direct  service through our ocean  freight terminals  in  favor of nc:
cost-effective and time-saving alternatives.

Dredging will  have a number of benefits for the environment also.

Deepening  the  channels will  reduce significantly the amount  of si:
disturbed  by  the passage of  deeply laden ships travelling very cio:
to  the bottom.   Also, ' removing the  contaminated silt  from  the ma:
channels throughout  the harbor by  dredging  and safely disposing^ of  :
through  capping or other  methods,:   will remove, once  and for all, t:
presence of'these materials  in areas where human activity  and seafcc
harvesting  are most  adversely impacted.  This  is due to the fact th;
the upstream  sources of  the  most harmful pollutants have already bei
eliminated,  and  new  ones,  thanks  to   our  enhanced  awareness  of t:
dangers they present,  will not be, allowed to take their place.

We really  are  making progress in, cleaning up the harbor, and the fa:
of  the  matter  is  that  dredging  will  actually  contribute  to t:
furtherance of  this goal.                                          —

Therefore,we hope your office will  take a balanced view of  the overall
issue,  and  act in such a way  as to  support the  timely approval of this
long overdue project before it is too late to rescue  the port from tr.e
effects  of the  commercial  obsolescence  that  is  already beginning  to
have a  negative  impact.
                      Sincerely yours.
                      Bos
tation Company
                       Jonathan  C.'Wales

-------
C5-1

       Thank you for expressing your support of the BHNIP. The information you have
included is useful in demonstrating the need for the project.
C5-2

        The BHNIP team concurs that the removal of contaminated silts from portions of
Boston Harbor will contribute to the cleanup of the harbor.  Although input of contaminants
has been decreased substantially, the dredging and sequestering of silts will result in "clean"
harbor bottom only temporarily because the remaining silts present in the rest of the harbor
would eventually be transported into the channels and berths (i.e., areas where there is ship
activity that is capable of disturbing the bottom).  However, the dredging and isolation of the
contaminated sediments that is proposed for the BHNIP will result in a net reduction of the
mass of contaminants that are in the harbor.

-------
                  JOHN T.  CLARK AND SON
               Contract Stevedores and Marine Terminal Operator^
BOSTON FISH-PIER, WEST BUILDING, SUITE 301. BOSTON. MA 02210 • 617-330-7810 FAX 617-345-0574
        555 MARKET STREET, PORTSMOUTH, NH 03801 • 603-431-8500  FAX 603-427-0771
                                                 June 20, 1994
 Colonel Miller
 U.S. Army Corps of Engineers
 424 Trapelo Road
 Waltham, Mass. 02254
                              Re: Dredging Boston Harbor
 Dear Colonel Miller:
 Our company is engaged in maritime commerce and (a) (represents steamship
 lines that call at the Port of Boston) (calls at the Port of  Boston)  (b)
 (to ship goods) (for passenger cruises) to and from the Commonwealth of
 Massachusetts and New England.

 For over twenty years the subject of dredging Boston Harbor has been
 studied by various Federal and State agencies and to date the channels have
 not been dredged.

 The Massachusetts  Port Authority and the  U.S. Army corps  of Engineers have
 filed a Draft Environmental Impact Report (DEIR)  and a  Draft Environmental
 Impact Statement (DEIS) for the Boston Harbor Navigation  Improvement Pro-
 ject and Berth Dredging Project.

 We  urge you to approve a permit to allow  the  dredging project to begin as
 soon as possible.   Recently container ships have bypassed the Port because
 the draft was insufficient at  low water.
Any  further delays  to  the  project will  cause harm to the economic stability
of the Port and affect our business and jobs.

                                  Sincerely,

                                  JOHN  T. CLARK AND SON OF BOSTON,  INC.
                                  William P. Horohoe
                                  President
WPH/mf
                      . \

-------
C6-1
       Thank you for expressing your support of the BHNIP.

-------
                  420 fifth Avenue, New York. NY 10018-2702
                  TEL (212) 764-4800 • FAX (212) 764-8592
                                                                     May 19, 1994
 Brink P. Miller, Colonel
 Corps of Engineers
 U.S. Anny Corps of Engineers
 424 Trapelo Road
 Whaltham, MA 02254
 Dear Colonel Miller:
 Containership Agency, Inc. through our subsidiary Peabody & Lane has maintained an
 agency representation for containerized shipping in the port of Boston since we were
 organized in 1971. For the past 23 years we have represented many major Principals in
 the hner trades connecting Boston with almost all the major trading areas of the world.

 Our mam-Principal, Mediterranean Shipping  Company 55
                                               Sincerely yours,

                                               Containership Agency, Inc.
                                               As agents
                                              Nicola Arena, President

-------
C7-1

       Thank you for expressing your support of the BHNIP.  The information you have
included is useful in demonstrating the need for the project.

-------
      May 26, 1994

      Colonel Brink P. Miller
      Corps of Engineers
      U.S. Army Corps of Engineers
      424 Trapelo Road
               , MA 02254  '
                                                                                       Decoratire

                                                                                       Specialties

                                                                                       International

                                                                                     '  Inrorjtorated
Dear Colonel Mill
                       ier:
      I am wnting in regards to the Boston HarKor Navigalion Improvement and Berth Dredging Project
      Our Company  Decorative Specialties International, Inc. (DSI) exports  to numerous locations
      around the world via the port of Boston,  We ship nearly 25 full shipments and at least 200 LCL
      shipments per year. At the present time, our export husiness represents in excess of 18% of our gross
      sales.                                                                                 *

      I don't douht that the environmentally concerned citizens of Massachusetts and the surrounding area
      should he conscious of the issues of the dredging project. The Massport and the Corps of Engineers
      are project partners and there is an ohvious commitment to safely and cost effectively dispose of the
      contaminated portion of the sediment.

      New England has lost and seems to continue to he losing johs and manufacturing husinesses  We
      are attempting to dig-ourselves out of the recession.  To many of us the only untapped markets where
      we can increase our husiness is overseas.  Please do not lose sight of the importance the port of
      Boston has to the entire New England economic health and future growth
                               J community is moving towards more deep draft vessels it is Boston s
                   N to mandate whatever is required to accommodate those vessels.  The over 9000 joh*
     directly or indirectly tied to the Port of Boston are a very small portion of the economic impact you
     may he risking in fighting or stopping this project.

     I petition you to do the right thing for your state and region - protect our environment hut do not
     lose sight of what will keep us economically strong.  With proper procedures and guidance, I am sure
     the project can he handled with care.
     Director of Sales & Marketing
     Pacific Rim
                                            357
1  Canal Street  South H«.
-------
C8-1

       Thank you for expressing your support of the BHNIP.  The information you have
included is useful in demonstrating the need for the project.

-------
P.O. BOX 65
SOUTH BOSTON. MA 02127
TEL. (617) 695-2920
FAX (617)695-2919
   May 19,  1994
   Brink P.  Miller,  Colonel
   Corps of  Engineers
   U.S.  Corps of Engineers
   425  Trapelo Road
   Waltham,  MA 02254
   Dear Colonel Miller,
  I'm  writing  to  express  an  opinion on behalf  of  the  company  that I
  represent, I.T.O.  of  New England and its employees  in support of
  choosing  a prudent dredging  and  disposal plan for Boston  Harbor and
  Massachusetts Bay.

  This  company and its  corporate ancestor have been providing
  stevedoring  services  for ocean carriers and  jobs for  local  residents
  in Boston for more  than seventy  years.  Unless the dredging  dilemma
  can  be  solved soon, I believe that Boston will  lose its status  as a
  credible major  seaport. As this  happens I can foresee  our business
  and  its employment opportunities disappearing.

  Vessels currently  handling containers  in the port are  prevented from
  Sai;inf at a11  Sta9es of the tide.  We  need to provide  a minimum depth
  of 40 feet in the  main and tributary channels and at  the container
  berths. Some vessel calls have already been aborted because the
  timetables of the modern containership  fleet doesn't  allow any  slack
  tor  idle time while waiting  for  the tide to change. Draft limits will
  become  more  severe  in the future  as the harbor  continues to silt up
  and  larger vessels  are built. Unless we put ourselves  in position to
  nandle  the traffic that is moving,  it  is obvious that  the traffic
  won't come.our  way.

  These are conditions  and facts that must be dealt with immediately
  Ocean carriers  which  are current  users  of the port have already been
  forced  to divert their ships. Unless, we  can provide the depth of
  water that vessels require we shall force them  to plan their future
  calls elsewhere.
                               3s;

-------
                                 -2-

with the reality of current civilization.

I plead for timely approval and implementation ot the Harbor
cost effective disposal measures
Very Truly Yours,
 Arthur  J.  Boyle
 Senior  Vice  President

-------
C9-1
                                           i
       Thank you for expressing your support of the BHNIP. The information you have
included is useful in demonstrating the need for the project.
                                                 367

-------
                                                        C10
June 20, 1994
LAPS SYSTBM, INC.

  810 - 3rd Avenue, Suite 408
     Seattle, WA 98104

       (206) 382-0388
     FAX (206) 382-0268
Colonel Brink P. Miller
Division Engineer
US Army Corps of Engineers
New England Division
424 Trapelo Road
Waltham, MA 02254-9149

Re:  Draft Environmental Impact Report (DEIR) and
      Draft Environmental Impact Statement (DEIS)
      Navigation Improvement Project and Berth Dredging Project
      Boston Harbor, Massachusetts
      April 1994
  tear Colonel Miller:
 Following are comments to the DEIR/DEIS referenced above and jointly issued by the U.S^
 Army Corps of Engineers and Massachusetts Port Authority.  Our OTBJCTS are focused
 on innovative treatment technologies and their assessment in the DEIR/DElb.

 We believe that overall handling of the alternatives analysis in the DEIR/DEIS is adequate
 provided the eventual decision is made to dispose of the sediment designated  as
 contaminated in  a confined aquatic disposal (CAD) site as identified by the preferred
 alternative.  However, should a determination be made that the contaminated sediment
 cannot be disposed of in this manner, then many of the initial screening requirements which
 eliminated a variety of treatment technologies and disposal options, need to be reevaluated.
 Effectively, unless this is done, the project as a whole may be in jeopardy.

 On page 2-7 of the DEIR/DEIS, it is indicated that the three major factors to differentiate
 the project alternatives are:

       4    quantities to be dredged
       4    areas to be maintained or improved
       4    timing

 A fourth factor, also of great concern is cost.

 The CAD alternative is  able to efficiently handle the entire quantity of contaminated
 sediment, is the most time efficient of the alternatives, and is the least costly option short
 of open water unconfined disposal. All other options will take greater time and cost more
 to implement.

-------
June 20, 1994
LADS SYSTEM, INC
Assuming that all of the contaminated sediment will not be approved for CAD, the project
needs to be evaluated in terms of higher costs, greater time periods to complete, and what
is possible.  Because of the difficulties associated with contaminated sediment disposal,
alternatives to consider may include:

       4     Smaller overall project in contaminated sediment area.

       4     Greater length of time to  process/treat  contaminated  sediment.   The
             additional time period required to implement a treatment technology relative
             to not being able to dredge an area at all and the associated impact on ship
             traffic needs in that area need to be balanced.

       4     Use  of control options and/or treatment  technologies which will  allow'
             dredging operations during the fish closure periods, such as silt curtains.

       4     Reanalysis of the overall project costs and cost sharing among local authorities
             for treatment  and disposal.    .

The DEIR/DEIS currently  has a construction schedule based upon dredging all the silt,
placing it in the ocean,  then dredging the native sediment under the silt and using that as
capping material. Total time to complete the project is approximately 1.5 years. Removing
the silt is the critical path to completing the dredging.  However, if only a portion of the silt
requires treatment, then that portion could be removed from the critical path and a longer
construction period allowed for treatment.

In evaluating treatment technologies, a reasonable estimate of the volume needing treatment
and the time available to complete the  treatment should be the basis of the screening
criteria.  To  effectively evaluate treatment technologies, a  project specific request for
proposals should be issued.  Available data in the literature on most treatment technologies
is not adequate to evaluate  and select a procedure for a specific project. The information
is too general in nature.

A significant issue regarding implementing treatment  technologies  for  contaminated
sediment is the potential cost. The sediment characterization studies, to date, have been
very general with a ratio of approximately 4(5,000  cubic yard (cy) per composite sample
which was chemically analyzed.  More definitive sampling, on tie  order of 4,000 cy per
sample, evaluating depth and location of contaminated  sediment  has high potential  to
further reduce the volume of sediment treatment.  Percentage reduction of the treatment
volume of less than 5% would easily pay for any additional sampling  and analysis efforts by
the reduced treatment/disposal costs for those sediment determined to be suitable for open
water disposal.                                                                  ~~
                                          363

-------
June 20, 1994
                                                            LADS SYSTEM, INC.
Finally  LADS System, Inc.  is a thermal remediation process for  contaminated silry
sediment. LADS is very interested in being considered for this project tf confined ocean
disposal is politically or environmentally unacceptable for disposal of a portion of the Boston
Harbor contaminated silly sediment.
Sincerely,
  Jancy L/Case, PE
President

-------
 C10-1

        The alternatives analysis presented in Section 4 of the FEIR/S concluded that it is
 feasible to isolate the silts dredged during the BHNIP by overdeepening several channel areas
 and capping the disposed material.

        MAS SPORT and the Army Corps of Engineers requested information on technologies
 for the handling, pre-treatment and treatment of the contaminated dredge materials from over
 thirty companies of which thirteen companies responded. The results of the treatment
 technology survey are presented in Section 3.0 and Appendix D.
 C10-2

        The contaminated silts will be placed at designated in-channel sites. It is currently
 projected that these facilities in the Mystic River, Chelsea River, and Inner Confluence
 channels will accept all of the silt material. Treatment of the silts is not anticipated. Section
 5.0, Dredging Management Plan, of the FEIR/S describes specific control techniques which
 will be employed.
C10-3

        The BHNEP EIR/S team appreciates this comment by LADS. In our interest in having
the best possible information on the potential treatment technologies we recently conducted a
survey of several known treatment companies. The responses were very helpful in refining the
technologies and associated costs that would be applicable to the BHNIP.

        At this time no further sediment sampling and testing is planned for the BHNIP. It  is
felt that sufficient sediment chemistry exists to evaluate the various treatment technologies still
under consideration.

        The BHNIP sediment test results show the proposed silts to be dredged from the berth
areas are chemically heterogeneous. These sediments are affected by a variety of harborwide
contaminant inputs, many of which are non-point sources. Our experience with sediments of
this nature indicates that a moderate increase in the number of samples would not substantially
reduce the amount of material that would require treatment.  Furthermore, all silt material is
considered to be unsuitable for unconfined open w:ater disposal. Therefore, additional testing of
the silt will not lead to any increase in the amount of sediment suitable for this disposal
alternative.

-------
                      Massachusetts Lobstermen's Association, Inc.
                      8 OTIS PLACE. P O BOX 600

                      SCITUATE MA 0?066-0006
TEL (61?) 545-69FW

FAX (61 ?i r>45 ~83T
                                                                 C11
                                          May 18,1994
Brink P. Miller
Colonel, Corps of Engineers
Division Engineer
424 Trapelo Road
Waltham, MA 02254-9149


Re:   Boston Harbor, Boston Massachusetts
      Navigation Improvement Project
             and
      Berth Dredging Project
Dear Colonel Miller:

The Massachusetts Lobstermen's Association, which represents the majority of lobster
fishermen in this State, opposes the use of the proposed at sea dump sites for the disposal
of the contaminated dredge spoil from inner Boston Harbor.

While we understand the need for the deepening of the waters of the Port, and we are not
opposed to the project, we can not support disposal of this admittedly contaminated
material into the waters where hundreds of fishermen earn their living. The sites as
proposed, the MBDS, the Boston Lightship, Meisburger 2, Meisburger 1, and Spectacle
Island CAD, are at or near where lobster fishermen set their traps.

Approximately 6.5 million of the 9.5 million pounds of lobsters harvested in the
 Massachusetts territorial waters and just beyond come from the general area fromjust
below Gloucester, South through outer Boston Harbor and down along the Northern
 section of the South Shore.  There is heavy fishing activity all through these areas and the
proposed sites lie within these general perimeters.  Should this material, once dumped,
 become exposed to the open ocean bottom or to current flows it could adversely affect the
 quality of fte marine environment in this whole area and possibly even further to the North
 and South. If this marine environment is in turn adulterated by the contaminates trom
 these dredge spoils, it could damage the high quality product that these fishermen land.
 (Statistics based on 1992 Mass. Lobster Fishery - Division of Marine Fisheries)

 Recently the lobsters from this general area were found to be of good quality and free of
 any harmful levels of contaminates.  We need to protect this marine environment and the
 lobsters and other sea life from becoming exposed to harmful elements.  We  consider the
 contaminates in this particular dredged material to be harmful elements.

 There has been an ongoing effort by everyone to clean up Boston Harbor and  the ocean as
 well in order to provide clean waters, and a healthy habitat for the marine resources we
 have.  We do not understand why, now in the heat of  an admittedly desirable project
 contaminated sludge which is buried under the surface of parts of the inner harbor should
 be excavated and dumped on our efforts to improve our environment.  Even if it were to be

-------
Brink P. Miller
Colonel, Corps of Engineers
Division Engineer
May 18,1994
Page 2
capped, or bagged for containment, the risks of its possible release are still too great.     	j

The disruption of fishing activity in these areas as you have referred to on page ES-5,
Column 2, Paragraph 1 of the Executive Summary is also unacceptable to the fishermen in
the area.

Rather than taking a chance that this project could undo the efforts and expense already
expended to clean the area of any contaminates, we would hope that a little more money
might be spent to properly dispose of this dredged material.

We appreciate the opportunity to comment on this important issue and we stand ready to
discuss this matter further with you.

                                          ; Very truly yours,
WAA/med

cc:    Senator Edward M. Kennedy
      Senator John Kerry
      Congressman Gerry Studds
      John DeVillas, EPA Regional Director
                                           , William A. Adler
                                           Executive Director

-------
Cll-1

       The alternatives analysis presented in Section 4 of the FEIR/S concludes that the in-
channel disposal is the least environmentally damaging practicable alternative for disposal of
silts from the BHNIP.
Cll-2

       The contaminated sediments currently reside on the surface of the harbor bottom and
are not buried.  By capping these sediments in the Mystic, Chelsea and Inner Confluence
portions of the channels, the BHNIP will keep the contaminated sediments as close to the
source as possible and isolate them from potential future exposure to biota.  The Dredge
Management and Monitoring Plan (Section 5) describes the precautions that are being planned
to ensure that risks to the environment are minimized.
Cll-3

        By restricting disposal activities to the inner harbor, the BHNIP will minimize
interference with fishing activities.  Disposal will occur in the same area where dredging
occurs; the two processes will be simultaneous.
                                            11

-------
                                 C J. w i
                      MAERSK  INC.
                                  MAERSK
                                                          C12
                                          June 14,  1994
Colonel Miller
U.S. Army Corps  of  Engineers
424 Trapelo Road
Waltham, MA  02254

Re:  Dredging Boston Harbor
Dear Colonel Miller:                  j

Our company is  engaged in maritime commerce and as an international
transportation  company has ships that call at the Port of Boston.

For over twenty years the subject of dredging Boston Harbor has been
studied by various Federal and State agencies and to date the
channels have not been dredged.

The Massachusetts Port Authority and the U.S. Army Corps of
Engineers have  filed  a Draft Environmental Impact Report (DEIR) and
a Draft Environmental Impact Statement (DEIS) for the Boston Harbor
Navigation Improvement Project and Berth Dredging Project.

We urge you to  approve a permit to allow the dredging project to
begin  as soon as possible.  Recently container ships have bypassed
the Port because the  draft was insufficient at low water.

Any further delays to the project will cause harm to the economic
stability of the Port and affect our business and jobs.
                                          Sincerely,
                                          Michael R. Walsh
                                          Regional General Manager
                 Suite 260, Edgewater Park, 401 Edgewater Place, Wakefield, MA 01880, USA
                 Telephone: 617-246-8211. Telex: Graphnet 3767534. Telecopier: 617-246-2906.

-------
C12-1

        Thank you for expressing your support of the BHNIP.
useful in demonstrating the need for the project.
          The information you have included is
12

-------
                                                       C13
 Comments  of Frank .Mirarchi         i
 Boston  Harbor 'Dredgi nq Project-Draft EIS
 May  17, 1994
My name  is  Frank  Mirarchi.
Scituate, MA,  02066.

I an a full  tine  commercial
operate  the  F  V Christopher
Scituate
                            I reside: at  67 Creel man Drive,
                             f isherrien.
                             Andrew a 60
Presently I
font st^rn
ovui :
an environmental ly  responsiblt? fashion.

My specific comments comprise two categories: 1. Dispersal  of
toxic substances into  the marine ecosystem and 2. Obstruct  • .;
advisories  is  the  toxicity  of the harbor sediments in which the?..-
     1s. due] 1 .
Once toxj<; subst&n<~-r*>  enter  the food choir, they are impossible
to eradicate.   For  example,  taking of lobsters-, shellfish, and
bottom fish  from waiters  in and  adjac-?ni  to New Bedford H.--«rl-.->r
is still prohibited over twenty y^ars after the disposal of PCI'
contaminated wv^st e  was stopped.

T am greatly concerned that  the problems of Boston Harbor nay
be spread into  the  Mass  Bay  Ecosystem by the sediment susperjH i«-r
caused by dredging  and by the unconfined ocean dispos.il of
contaminated spoil.  For this reason I  urge employment <->f th:-
best available  technology in minimizing the suspension and
dispersal of sediment  during dredging.   I oppose any un«.-onf
disposal of  contaminated sediment  irrespective of location.

If a site for disposal of clean material is considered I ur«jt= i- <>ij
to work closely with commercial fishermen's associations in tlv-
process of final selection.

Inadvertent obstruction  of the  seabed by debris such as riound^ <'^\_
clay, rocks, and pilings is  inevitable no mattt-r hou carfully
the project  is  supervised.   It  is  important to minimize 1 he
economic
ma t e r i a 1
         loss and safety risks  inflicted on fisherman by this
                            "377

-------
A number of fishing associations including,  but  not  limited
to, Mass Inshore  Dr.-igocrnien' s" Assoc ., Moss Gi 1 Inet.t er ' s Assr.c.,
Mass Lobsternen' s Assoc., and th-- Glc>ucester 3nsh'">re Fishermen'
Assoc. would bo pleased to evaluate- any proposed site on the-
basis of its importance to fishing.   I urge  you  to actively
solicit and carefully consider these-  cor.ments.

Thank you.

-------
C13-1

        The proposed project does not proposfe to utilize any unconfined ocean sites for disposal of
contaminated dredged materials. The best available technologies, as described in Section 5.6 of the
FEIR/S, will be employed to minimize suspension and potential dispersal of dredged materials. Dredged
silts will be placed at in-channel disposal facilities and capped following placement. Parent material will
be transported and dumped at the MBDS.
C13-2

        The MBDS was designated as a disposal site for "clean" dredged materials as the culmination
of an extensive designation process conducted by the USEPA.  Any dredged material from the BHNIP
that is considered suitable for unconfmed open water disposal would be permittable for disposal at
MBDS. The FEIR/S discusses potential beneficial uses of this clean material that would be considered a
higher priority than disposal  at MBDS,  if practicable.
C13-3

        Any disposal of dredged material from the BHNIP at the MBDS would be conducted in
accordance with the regulations governing that activity.  These regulations are geared towards defining
and controlling the size of the area at MBDS actually affected by disposal.
C13-4
        We appreciate your interest and concerns about the BHNIP.  The FEIR/S is available for public
review.
                                               13

-------
MORAN  SHIPPING  AGENCIES, INC.
451 D Street, Suite 814  Boston, Mass. 02210
Telephone: (617) 443-0616  Fax: (617) 443-0730
Cable: MORANCO-BSN  Telex: 298808
   AN MTI COMPANY
                           Offices from Maine to Texas
                                                   June 13, 1994
          Colonel Miller
          U.S. Army  Corps of Engineers
          424 Trapelo Road
          Waltham, MA 02254
                                                            C14
                          Re:   Dredging Boston Harbor

          bear  Colonel Miller:

          Our company is engaged in maritime commerce and
          represents many steamship lines, tanker vessels
          and their charterers, owners that call at the Port
          of Boston.   For over twenty years the subject of
          dredging Boston Harbor has been studied by various
          Federal  and State agencies and to date the channels
          have  not been dredged.

          The Massachusetts Port Authority and the U. S. Army
          Corps of Engineers have filed a Draft Environmental
          Impact Report (DEIR) and a Draft Environmental Impact
          Statement(DEIS) for the Boston Harbor Navigation
          Improvement Project and Berth Dredging Project.

          We  urge you to approve a permit to allow the dredging
          project to begin as soon as possible.  Recently
          container vessels have bypassed the port because  the
          draft was insufficient at low water.

          Any further delays to the project will cause harm to
          the economic stability of the Port and affect  our
          business and jobs.

                                        Very truly yours,

                                        MorXt*' Shippi#$ Agencies,  Inc.
                                         Ge
Dexter
  Manager
           RD/s

           cc - File

-------
ci4-i                                           ;

        Thank you for expressing your .support of the BHNIP. The information you have included is
useful in demonstrating the need for the project.
                                             14

-------
                                             •••'-
 North East Area
 Boston Office

 Nedlloyd Lines (U.S.A.) Corp
 451 D Street. Suite 804A
 Boston, Massachusetts 02210
 Telephone: (617) 737-1515
 Telexfax: (617) 737-1919
Nedlloyd
Lines
                                Region Directorate
                                North America
                                C15
                                 June 15, 1994
Colonel Miller
U.S. Army Corps of Engineers
424 Trapello Road
Waltham, MA  02254
IRE:  DREDGING BOSTON HARBOR

Dear Colonel Miller:
Nedlloyd Lines is engaged in maritime commerce and calls at the Port of Boston.'

For over twenty years the subject of dredging Boston Harbor has been studied
by various Federal and State agencies and to date the channels have not been
dredged.

The Massachusetts Port Authority and the U.S. Army Corps of Engineers have filed^
a Draft Environmental Impact Report (DEIR) and a Draft Environmental Impact
Statement  (DEIS) for the Boston Harbor Navigation Improvement Project and Berth
Dredging Project.

We urge you to approve a permit to allow the dredging project to begin as soon
as possible.  Recently our containerships have bypasses the Port because the
draft was  insufficient at low water.

Any further delays to the project will cause harm to the economic stability of
the Port of Boston and affect our business and jobs.
 Sincerely,

 NEDLLOYD LINES  USA  CORP.
 Paul Gaudes
 Manager,  Port Operations
                                      Nedlloyd
                  Nedlloyd Lines is
                  a company of the
                  Royal Nedlloyd Group

-------
C15-1
        Thank you for expressing your support of the BHNIP.  The information you have included is
useful in demonstrating the need for the project.
                                             15

-------
   North Shore Recycled Fibers
                                                    THE
                                                    NEWA
                                                    GROUP
   S3 Jefferson Avenue
   P.O. Box 3007
   Salem. MA 01970
   617/289-9400
   FAX50a744-S857
   TELEX 595955
May 12, 1994
A Newark Group. Inc. Company
Products from Recycled Fibers
                                         C16
Brink P. Miller, Colonel
Corps of Engineers
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham,MA 02254

Dear Colonel Miller:

I am writing to strongly support the continued dredging of the Boston Harbor.  As a local
business, we rely heavily on the movement of goods in and out of Boston Harbor.  It is
essential'to our business and the continued existence of our company to keep the Harbor
as viable as possible.

Currently, because of the inability of the Harbor to accept some of the larger deep draft
vessels that are calling on ports today, we have to barge our goods to New York for
 shipment from that port. Not only is this an added expense that we must incur, but we
 also have to play second when trying to get the proper equipment, i.e. containers, to do
 our shipments.

 As you are aware, paper related products comprise approximately 40% of the activities
 being exported from the Port of Boston. The number of jobs would be in the hundreds if
 people were displaced, as companies seek alternative means to move their cargo, such as
 trucks out of New England, or by train to the West Coast because of the additional
 expense of barging.

 It  is essential for our company to have the flexibility to continue shipping to Europe and
 the Far East via the Port of Boston, and to do so on a competitive basis with other larger
 East Coast Ports.

-------
May 12, 1994
Page 2 of2

I strongly urge you to actively support the Boston Harbor navigation improvement and
berth dredging project, and I thank you for your attention to this project.

Sincerely,
NORTH SHORE RECYCLED FIBERS
A Newark Group Inc., Co.
J
Robert F.
Vice President

RFHrlmm
                                 37?

-------
r
                     C16-1

                            Thank you for expressing your support of the BHNIP. The information you have included is
                     useful in demonstrating the need for the project.
                                                                   16

-------
  '&O Containers
         C17
       June 15,  1994
       Colonel Miller
       U.S. Army Corps of Engineers
       424 Trapelo Road
       Waltham, Ma 02254                 ;

            Re:  Dredging Boston Harbor

       Dear  Colonel Miller:

       Our company is engaged in maritime commerce and calls at the Port
       of Boston to ship goods to and from the Commonwealth of
       Massachusetts and New England.

       Our containerships,  which call Boston each week,  have recently
       had to bypass Boston due to draft restrictions.  As recently as
       today, the arrival of the vessel was restricted to arrive during
       high tide.  New England companies ibenefit because our ships make
       Boston the first inbound port of call (provides an excellent
       transit time)." In light of this the ship arrives at Boston fully
       loaded with a deep draft.  It is thus imperative  that the
       dredging be performed so that our ^ships can continue to serve the
       New England region on a direct call basis.  If the dredging is
       not performed there will be possible bypasses in  which New
       England cargo will be discharged in Newark, NJ and moved to
       Boston via barge.  This "feeder" service will reduce labor hours
       at Boston, incur additional transportation expenses and delay New
       England'bound cargo for an additional 5 days!
                                         :                               i
       The Massachusetts Port Authority and the U.S. Army Corps of      |
       Engineers have filed a Draft Environmental Impact Report (DEIR)  j
       and a Draft Environmental Impact Statement (DEIS) for the Boston
       Harbor Navigation Improvement Project and Berth Dredging Project.

       For over twenty years the subject ,of dredging Boston Harbor has
       been studied by various Federal and State agencies and to date
       the channels have not been dredged.
       We strongly urge you to approve a permit
       project to begin as soon as possible.
to allow the dredging
        Sincerely,
       Matthew A. Merkel
       P&O Containers - Boston, Ma


   Containers, Ltd.
ne Boston Fish Pier, West Building 2, Suite 305, Boston, Massachusetts 02210
nelephone: (617) 428-6035 Telex: 130126  Telefax: (617) 737-9978    _
egistered Office: Beagle House, Braham Street. London, El SEP Regfctered Number: 984922 England          v J  Y /
              P&O Group

-------
C17-1

        Thank you for expressing your support of the BHNIP.
useful in demonstrating the need for the project.
         The information you have included is
7

-------
                                                                  C18
  June 16,  1994
                                                         PATTERSON, WYLDE& CO., IN
                                        Agents and Brokers - F.M.C. No. 2
                                 The Boston Fish Pier - West Bldg. #2. Suite 2
                                             Boston, Massachusetts 022
                                  Phone: (617) 428-6000 - FAX (617) 737-95
                                             Cable: PATWYL • TLX 940E
 Ms. Trudy Coxe, Secretary
 Executive Office of
  Environmental Affairs
 Commonwealth of Massachusetts
 1C0 Cambridge Street
 Boston, MA  €2202                       :

 Dear Ms.  Coxes

 For over. 100 years  our company has been representing many of the various types
 of ships  engaged in'international transportation and calling  at  the Port of
 Boston.           .         •

 We can well remember the years when the depth of water  in the harbor was not an
 issue and, with the exception of some tankers,  vessels could arrive and depart
 without waiting for the  tide.   Today's vessels,  however, are much larger and
 require greater depth of water in order to navigate  safely.

 Container vessels cannot afford to "wait for the tide," and if such conditions
 occur, those -vessels will by-pass the port, which has in fact already occurred.

 The Port of Boston and the Commonwealth of Massachusetts cannot afford to lose
 this type  of activity and business;  and, if we are to remain  a "World  Class
 Port,   the harbor must be dredged.

 The Massachusetts Port Authority and the U.S. Army Corps of Engineers have  filed
 a Draft Environmental Impact  Report and a Draft Environmental Impact Statement
 for the Boston Harbor Navigation Improvement and Berth Dredging Project.

 We  urge you to approve a permit  to  allow  the dredging project to begin as soon
 as  possible.   Any further delay in this  already longstanding issue will  only
 cause  damage  to the economy of the Commonwealth and harm to the many businesses
 and work opportunities related to waterbourne transportation.
Sincerely,

PATTERSON,
,  INC.
A. R. Pq
Executive Vice president/
Treasurer

ARP/mg

cc.-  Colonel Brink Miller
                          - U.S. Army Corps of Engineers
                            _                    ^

-------
r
                      C18-1

                              Thank you for expressing your support of the BHNIP.  The information you have included is
                      useful in demonstrating the need for the project.
                                                                     18

-------
              Offices in:
 Telephone
508-535-7073
    FAX
508-535-7028
ATLANTA, GA
LOS ANGELES, CA
NORFOLK, VA
BALTIMORE, MD
MIAMI; FL
SAVANNAH, GA
CHARLESTON. SC
NEW ORLEANS, LA
SEATTLE, WA
GREER SC
NEW YORK, NY
ST. LOUIS, MO
                                C. H. POWELL COMPANY
                                                   F.M.C. No. 176
 INTERNATIONAL FREIGHT FORWARDERS AND CUSTOM HOUSE BROKERS
           1 INTERCONTINENTAL WAY, PEABODY, MA 01960
                                                       C19
       Colonel Miller
       U. S. Army Corps of Engineers
       424 Trapelo Road
       Waltham, MA  02254
                                  13 June, 1994
             Re: Dredging Boston Harbor

       Dear Colonel Miller,
       C. H. Powell Company is engaged in maritime commerce, in its capacity as an international
       frieght forwarder and customs broker. The ability of steamship lines to call directly at the Port of
       Boston is of vital interest to our company, and to our customers.

       For over twenty years the subject of dredging Boston Harbor has been studied by various federal
       and state agencies. To date, the channels have not been dredged.

       The Massachusetts Port Authority and the U. S. Army Corps of Engineers have filed a Draft
       Environmental Impact Report (DEIR) and a Draft Environmental Impact Statement (DEIS) for the
       Boston Harbor Navigation Improvement Project and Berth Dredging Project

       We urge you to approve a permit to allow the dredging project to begin as soon as possible.
       Recently container ships have bypassed the Port because the draft was insufficient at low water.

       Any further delays to the project will cause harm to the economic stability of the Port and affect
       our business and jobs.                                                           —
       Sincerely,

       C. H. POWELL COMPANY
       David E. Powell
               PRESIDENT'S "E" AWARD
                                EXCELLENCE IN EXPORTS

-------
C19-1
        Thank you for expressing your support of the BHNIP. The information you have included is
useful in demonstrating the need for the project.
                                                19

-------
                                                                      C20
   REXHAM
REXHAM INC
P.O. Box 811
South Hadley, MA 01075-OSH
Fax 413 539-5221
Telephone 413 539-5210
 May 16, 1994

 Brink P. Miller, Colonel
 Corps of Engineers                          :
 U.S. Army Corps of Engineers
 424 Trapelo Road
 Waltham,Ma 02254                         :

 Dear Colonel Miller,

 I am writing in regards to the Boston Harbor Navigation Improvement and Berth Dredging
 Project.  I represent a business who exports exclusively through the port of Boston.  Annually
 we ship nearly 50 containers and at least 100 LCL shipments.  This business represents nearly
 15% of our $100MM+ gross sales and our committed growth is nearly all in our international
 markets. By the end of 1994 we will have a European Distribution Center to service our new
 markets on the continent and will be supplying inventory to that DC over Boston.  My point
 being, Boston as a viable port is crucial to our business now and will be even more in the future.

 I don't doubt that the environmentally concerned citizens of Massachusetts and the surrounding
 area should be conscious of the issues of the dredging project.  The Massport and the Corps of
 Engineers are project partners and there is an obvious commitment to safely and cost effectively •
 dispose of the contaminated portion of the sediment.                                      '

 New England has lost and seems to continue to be losing jobs and manufacturing businesses.
 We  are attempting to  dig ourselves out of the recession.  To many of us the only untapped
 markets where we can increase our  business  is overseas.  Please do not  loss sight of the
 importance the port of Boston has to the entire New England economic health and future growth.

 If the international shipping community is moving towards more deep draft vessels it is Boston's
 OBLIGATION to mandate what ever is required to accommodate those vessels. The over 9000
jobs directly or indirectly tied to the Port of Boston are a very small portion of the economic
 impact you may be risking in fighting or stopping this project.

 I petition you to do the right thing for your state land region - protect our environment but do
 not lose sight of what will keep us economically strong. With proper procedures and guidance
 I am sure the project can be handled with care.
                                                                                    •M

 Respectfully, A,
Marge Patterson
Transportation Administrator
                                   6*7

-------
C20-1

       Thank you for expressing your support of the BHNIP.  The information you have
included is useful in demonstrating the need for the project.
                                            20

-------
                                                                C21
Sea-Land Service, Inc.
Berth 11
P.W Conley Marine Facility
South. Boston, Massachusetts 02127
(617) 269-5840
(617) 268-2962 (Fax)
                                           June 17,1994
 Colonel Miller
 U.S. Army Corps, of Engineers
 424 Trapelo Road
 Waltham, MA 02254

 RE: Dredging Boston Harbor
                                       i
 Dear Colonel Miller:

 Our company currently operates 950' container vessels which call directly at the Port of
 Boston from north Europe. This weekly service has been in existence for over 7 years
 and has become an integral part of the waterfront economy.

 On many occasions we have had to pay thousands of dollars in additional labor costs
 while waiting for a high tide to dock our vessel. On at least one occasion we had to
 bypass the Port of Boston because our schedule did not allow us to wait for a high tide.
 These additional expenses and delays restrict our ability to do business in Boston and
 have a wide ranging impact on businesses throughout New England.

 The Massachusetts Port Authority and the U.S. Army Corps, of Engineers have filed a
 Draft Environmental Impact Report (DEIR) and a Draft Environmental impact Statement
 (DEIS) for the Boston Harbor Navigation Improvement Project and Berth Dredging
 Project. We urge you to approve a permit to;allow the dredging project to begin as
 soon as possible.

 Further delays to the project will  cause harm to the economic stability of the Port and
 possibly jeopardize our direct service from Europe into Boston.

                                          Sincerely,

                                          SEA-LAND SERVICE, INC.
 DAS/klm
                                          Derrick A. Shirley
                                          Port Manager

-------
C21-1

       Thank you for expressing your support of the BHNIP.  The information you have
included is useful in demonstrating the need for the project.
                                            »i

-------
                                       BOSTON EDISON
                                        800 Boylston Street
                                    Boston, Massachusetts 02199
                                                                               C22
                                                     June 28, 1994
Brink P. Miller
Colonel, Corps of Engineers
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham, MA  02254

Dear Colonel Miller:                                ,

On behalf of Boston Edison Company (BECO), I submit comments on the Boston Harbor MA
Navigation Improvement Project and Berth Dredging Project Draft Environmental Impact Statement of
April, 1994. Our concerns essentially are for the integrity of buried cables, bulkheads, and cooling water
intake during the dredging phase, and for the integrity of buried cables and overhead transmission lines
should the disposal of dredge material be on BECO property.

I also attach a copy of my March 28, 1988 comment letter on the Draft Feasibility and Environmental
Assessment for deepening existing navigation channels in the Mystic and Chelsea Rivers and the Reserved
Channel in that potential adverse impacts on Company facilities described for the Reserved Channel,
Mystic River channel and Chelsea River remain essentially the same.

DEIS:

Figure 1-lb Boston Harbor Locus Map - Expansion of the President Roads Anchorage NNE-ward could
approach the undersea 115 kv cable originating from K Street Substation and extending the length of the
Reserved Channel across to Deer Island. In that location,  the cable is buried 15' below the sea floor. A
Key Plan and a Plan and Profile plotting the cable route and indicating depth of burial are attached. The  ,
cable route deviated from a straight path in order to avoid the submerged obstruction indicated on the    J
profile.

Figure 2-3 Navigation Improvement Project - Mystic River and Figure 2-6 Location of Federal Channel
and berth area dredging. The westward extent of Mystic Channel  deepening differs on these two figures  ^
at the bridge along Alford Street adjacent to BECO's Mystic Station.  A map of Everett is therefore
attached which indicates the path of our utility tunnel, with four pipe cables crossing under the Mystic   J
River from Station 250 (Mystic Station) paralleling the bridge.                                      -1
                                                                                             !•- *
Also shown on the Everett map are cables crossing Chemical Lane and passing thereafter toward Dexter
 Street. Cables also cross BECO property bordering Chemical Lane proceeding under the Mystic River
 due west into East Somerville.
C22-
                                                 5f/

-------
Page 2
June 28,1994
       BOSTON EDISON
       2.5 Chelsen Cr**k Upstrear* ~
                                           Street Bridze - We have a distribution cable for Logan
International Airport crossing in the vicinity of Cabot Paint.

Efa»«. 3-7 J^catio^^Pn^ial Disoo^nJ ^ites Extensively FvalnatedandFi91lre A1-1Genial





Boston map.
7-3 Site M"T fnr Potential
                                           * ~ Evereti~ indudes SOme 35 aCT6S °f BEC° ^^
 crossed by cables to and from Mystic Station as shown on the previous Everett map.

 FfrT.^ A M v<» a^, fnr Paienad! P*r™»/ **' - Woburn - "• indicating "power fines", involves
 BECO transmission^ of Way #14 and Right of Way #9 as shown on attached schema^ Our mam
 concernisthatanyin™^

                        i a transmission corridor/Right of Way, have additional safety issues as well.  .

                               inl Disposal Sif* - Ouincv - <™ (toptantum Point) was, until recently,
 BECO property taken by eminent domain for an MWRA parking facility/ferry service during Deer Island
 construction work.

 Additional Concerns:

 Reserved Channel and Mystic River dredging projects have the potential also for adver ^impacting  1
 cooling water intake at New Boston Station and Mystic Station, respectively. Adverse  mp** orfce
 structural integrity of the bulkheads at the two stations is also a consideration we bring to the Corps
 attention.

  As I indicated to you at the May 17th public meeting at the O'Neill Federal Building, we appreckte this
  o^pormmty to comment on the DEIS and would be happy to meet with the Corps or do a field walk-
  over, should you feel it necessary.
  Should there be any questions, I can be reached at 424-2975.
                                                        Very truly yours,
                                                        Lillian N. Morgenstern, Ph.D.
                                                        Principal Environmental Planner
   Attachments

-------

-------
CM
r*.

 l
Q

o
               'I
               Ti
            §i
            S'
                      i	. B5

                         H
                        I
                        I
                      L_J
                                $
TT
                                                       (Nl-AQ)        3Nli H31VW
•T—T
                                                     (HI*)
                                                      SIA
                                                      w
    !
  Ill
   ii
                                                 3 I
                                                  si


                                                Jl    i.
                                                   	-


                                                                        1
                                                                        e
                                                                        iiil
                                                                        I
                                 *• «n
                                 * **•



                                 I
                                                                      3NH
                                                                                               k

-------

-------An error occurred while trying to OCR this image.

-------
BY
CHKD. BY
   DATE
	DATE
SUBJECT..
                                       SHEET NO.  .    .OF.
                                       JOB NO	
                                           At  fif
                                     7%  -^ /,
                                                       /W
                                          ->•
                                                                          Sid
                  Wood pete- */i/7\
                                                                     .  2 -

-------
 BY
 CHKD. BY,
 .. ..DATE
	DATE
                               SUBJECT..
SHEET NO.
JOB NO	
                                                                                           .OF..
•WicA>/    /*?"*<
        \\Wilmir
                                                       Bt/^/trt '->   70
                                                - 3, 8
                                                        O  %
                                               X
                                                       250 '-
                                                                               s.<
                                 13.

-------
                                BOSTON EDISON
                                800 Boylston Street
                             Boston, Massachusetts 02199
                                       March 28, 1988
Division  Engineer
New England Division
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham,  MA  02254-9149

Dear Colonel Rhen:
                                         !

On behalf of Boston Edison Company, I submit comments on the Draft Feasibility
Report and Environmental Assessment for deepening existing navigation channels
in the Mystic and Chelsea Rivers and the Reserved Channel.  I congratulate you
in the thoroughness and clarity of the draft report and thank you for the
opportunity to review the proposed modifications.  We would welcome an
opportunity to meet with your staff as the project proceeds and to provide you
with details you may require.

I would in the interim offer the following specific comments on your
Recommended Plan of Improvement as they impact or have the potential to impact
the Company.

1.  Reserved Channel. South Boston, southside:
    a)
    b)
    c)
    d)
    e)
On a copy of report Figure 34,  Ihave indicated the approximate
dividing line between existing   Boston Edison Company property and
our east boundary neighbor, the MBTA.

Also indicated on that figure is  an area in front of the New Boston
Station screenwell  structure, last dredged in 1976, which the Company
has under consideration for future dredging.   We would hope that the
area could be considered in concert with your dredging.   A 1974 plan
and cross sections  are attached.  :

The Company also has a utility  tunnel extending approximately
northward from the  New Boston Station adjacent to the "L" Street
Bridge.

The report references Boston Edison Company,  as a "Beneficiary" and
recommends that the south side  of the channel be narrowed by some
15'±.  As is planned for the northside, we would anticipate
consideration of the structural  integrity of bulkheads on the
southside as well prior to dredging to 40' depth and of any deepening
of berthing areas.

Enclosed also is a  plan indicating two proposed cable routes from the
New Boston Station  (on JHsT'Street) out to Deer IslajQjlto provide
power for MWRA construction activities in aJ£Wtl99lTtimeframe.
                                       3-7?

-------
Colonel Rhen
March 28, 1988
Page  2
   BOSTON EDISON

2.  Mvstic River Channel:

    a)   On a copy of report Figure 34, I have indicated on the north_side of
         the river that Boston Edison property now includes that portion
         marked as "Belcher Petroleum".

    b)   From the Mystic Station, a utility tunnel containing lines 250-517
         and 329-511 is indicated approximately parallel to the Maiden
         Bridge.  A larger plan is available which provides more detail  of the
         area.  Lines 250-516, 329-510, 211-514 and a spare pipe are in  the
         Mystic River.

    c)   Boston Edison's Mystic Station outfall canal structure is presently
         under consideration for some repair/maintenance work.  If the -40'
         MLW deepening of the river is bounded by the Federal Channel line,
         the present structure is considered to be sound.  It is unclear
         presently what effect a berth deepening of -40 MLW right up to that
         bulkhead would have however.

3.  Chelsea River:

    a)   The report (page 60) references Company cables in need of burying 200
         + 300' downstream of the Chelsea St.  Bridge.

    b)   Page 60 also references sixteen five-inch electrical conduits 2,800'
         + upstream of the McArdle Bridge.  Those are Boston  Edison  conduits
         but it is not clear that they would not  be  impacted  by a deepening to
         -40' MLW.

4.  Wevmouth Fore River:

    a)   This week the Company issued  a  Request for  Proposal  for the
         revitalization  of our Edgar Generating Station on the Weymouth Fore
         River opposite  the former Quincy Shipyard.  It is anticipated  that
         reuse of the Edgar site for up  to  600 MW of power will be proposed
         over the next three to  four months.   I have enclosed two drawings:
         one a closeup of the site and the  second indicating  its location
         relative to Nantasket Roads.

    b)   The question I  would raise  is whether you have any plans to deepen
         the Weymouth Fore River in  view of the reuse of  the  Quincy  Shipyard
         by the MWRA?  We would  be interested  in  any plans for  deepening  the
         river between the Fore  River  Bridge  and  Nantasket Roads.

In  conclusion, thank you for  this  opportunity to  comment  on your
recommendations for Boston Harbor.   As your proposed project  becomes
finalized, we would welcome  the  opportunity to discuss  details  regarding  our
utilities  and generating station waterfront structures.  I  can  be  reached at
424-2975 should you have any  questions.
                                        Lillian N. Morgenstern, Ph.D.
                                        Principal Environmental Planner

-------
C22-1

       Expansion of president Roads Anchorage in the NEE direction is not presently
contemplated. Figure 1-lb (DEIR/S) is misleading in that it shows the original outline of the
anchorage and a 700-foot wide extension authorized in 1946 and constructed in the late 1950's.
C22-2
       Figures 2-la and 2-3 show the correct channel limits.
C22-3
       Cables shown on the map for Everett are not within the proposed dredging area.


C22-4

       The Design Memorandum which will be prepared after the FEIR/S contains a section on
utilities. This information has been incorporated into that document


C22-5

       These Everett and Cabot Paint sites are not preferred disposal alternatives. The cable
crossings will be noted if these sites are proposed for future use.
C22-6
       (see response to C22-5)
C22-7

       No work is proposed for the Woburn site under the "power lines". Equipment would use
existing roads if this site was used in the future.


C22-8

       Care will be taken to limit turbidity during dredging and disposal operations. It may be
necessary to dredge only during the portion of the tidal cycle which directs any plume away from
the intakes. Water quality modeling has shown that project operations will not violate water quality
standards.

       Bulkhead integrity was examined with respect to deepening of the Federal channel. Results
of our investigations indicate no significant loads are to be placed on the adjacent bulkheads.
                                          22

-------

-------
 PRIVATE CITIZENS
COMMENTS AND RESPONSES

-------
                         ™!™ri!J!!!!™
      !~™                                                                                                            	I!!'!!'"!!!"!!!!!!,!,!!!!::;!!'!!"
                                                                                                                                                                                                               Uliii'iBlljli lllljljljjjlljlilllillllllii	i11, i|	i,il	Illlii,,:, I' illijii J|i|!l'i""i 1! 'I ulili l!i, iMIii.i mil:	Ililli
                                                                                                                                                                                                              IIHII||iiRililF<;i|||| IllllllllllllllliniiiJIiiiili!:,; .aflliJiiailii!! JliiBa? i!  >!m 'A K !Q» •!!, ill '•,, „', IV,, "ftil n, ..H., i| '!J'.' Wll' '•>  i,'!',!"!,'ll!!lii'":!'"W If 'f, 'i11!'!" IffllUS' JHUllplllilDii' (:i\M\MK\ PI
                                                                                                                       illU!	il!l!l:!iililli!i!ll!lli!l!ll!iil illlkllllill flllllliai^                           	Ill
iaiaiiiii ii iiiiiijjiii!iil||!i!'" laaiiiiiiiiaiaiiiaiaiiaiiiK                                                                                   iiiihiiiiiiiJIiitiiLiiniiiiiiiijiiiijijiilpSiiii'iiiiii'']!! iiiiaaiailliaaN aiia I iII|Kiiiiaiii: iii' \ i' Hi,!!!11 'ia,! "fSa ii'aiaa'! r laal'' ii
                                                                                                                                                                                                                                                                                                                     M'tis,ailz''liiiin'!iiiii'i!iii!i!|i!i!!!h  i'iiiilliiiiiiiiiriii.!
                                                                                                                                                                                         f	;-'	••	:	•>:	:	•	•	

                                                                                                                                                                                                                                                            I'ifi	!iiliii;:i::f'M:i:i«i^                                  	IM^^^^
                                                                                                                                                                                                                                                                                   I'i'v'iM:111!!!1"	''I'  '	"iSJ1	fill!	iini'iinii	iri                     '
                                                                                                                                                                                                                                                                                  Ji!!',!l,1!,•!!'!:/?!. :|l""1' ,  'lli!1'!'H!f •!  i:1*!!!^
                                          ;;:;„	,	k:::r;;r	~	:::	
                                                                                                                                                                                                                 !' iitaiinlihiiiiiiiiillilnaii!! iiiiipniHi;1'1;!;! la*:; aiiT1: a u,!«-	tt\m\\t' < fJ <  .f11 •'»"\ ?K •"'''    : i(i '•'.  ^ 11«': iinulu,? i uliiiiiir; filiiiiiniinii	n;1!1!!
                                                                                                                                                                                 ailllailiiiai!!:1 i;|ai!aii!!ai!iaia                 "a"; aS I1 a!1 :; ai"1  i'   a i1" 'I, Slaaiiia Ilialaiiiiiiiia  aiiiiii!i|i!l:!iliiiiaia!'!ii

	„;	;„„;;	;; ,;ilni ;„	;;	i,,;^;,;,,,,;;	ililin;	;„;;,,;	;,; ^	a	
                                                                                                                                               alea||Ba|aa^                                                                 a,  aiMa  41.a jaa^aiaaaa.;:  : jjiji  ,   ; ;,,<  :a   i  ,  a   ,, /       iia,   /Maaa  a aiaaa!  aaaa.!  i1;:;;

-------
                             15 June 1994

Brink P.  Miller, Colonel
U.S. Army Corps of Engineers (COE)
424 Trapelo Road
Waltham,  Massachusetts  02254

Trudy Coxe, Executive Secretary
Executive Office of Environmental Affairs
100 Cambridge Street
Boston, Massachusetts  02202

Dear Colonel Miller and Secretary Coxe:
RE:   Draft Impact
      Statement
      DEIS dated
      April 1994

RE:   MEPA Unit
      Draft Report
      EOEA File
      No.  8695
Requirements mandate that any activity  having  significant, effect
upon  the  environment be  supported by  data is  gathered  in- one
place and necessary to make a decision,  including complex factors
outside   the authorities  scope.  ', The  Draft joint  Federal  and
State  document  and process  to  address  impacts  associated with
the  proposed  Boston  Harbor, and ! Berth, Navigation Improvement
Dredging  Projects (B-NIP)  are both INADEQUATE and NOT PRACTICAL.

Policy  acts  also mandate  that  the  public  must "be  informed  of
the  significance  of the environment  and the problems involved.
The repeal of a prohibition on capping is a  significant problem.

No one,  not even a branch  of the government,  is ever above the
law.   The  Environmental  Protection  Agency  (EPA)  must respond,
judge  violations,  and actively police  anti-pollution  rules  and
supplemental  federal   administrative  regulations.    The  more
complicated the  nature of the determinations  to be  made,  the
longer the period of investigation'' and deliberation required.

I DEMAND  an E.IS be initiated immediately regarding  all aspects
of capping  at  the Massachusetts Bay  Disposal  Site'  (I shall use
the  terms  "MBDS"  and  "Stellwagen  Basin"  and   "the  preferred
alternative" interchangeably throughout  my comments herein).

Capping is prohibited at MBDS.  This  prohibition was the product
of administrative  experience,  appreciation  of  the  complexities
of the problem,  realization of statutory policies and responsible
treatment of the uncontested facts.There can be no 100% efficient
physical  isolation  of all  contaminated,  unclean materials from
B-NIP.  Capping at the Basin is  not a  "potential" flaw in B-NIP's
proposal,  it is  a fatal flaw. Proponents and reviewers may have
placed  at  risk the proposal's  entire  scoping  and  consistency.

Capping   was prohibited in EPA's  MBDS  designation Record  of
Decision   (1/13/93)  which   "...expressly bars  the  disposal  of
(such) contaminated materials, even if they  were  to be capped..."
(p 10).    EPA  questioned  the viability  and efficacy of capping
at MBDS  when  it enacted  the  prohibition.   Mass Coastal  Zone
Management   concurred.   These  proposed  dredging documents  are
legal  challenges  not only to  that   MBDS designation but  also

-------
r
       INADEQUATE/NOT PRACTICAL
p. 2 of 6
       to designation of the Stellwagen National Marine Sanctuary  (NMS).

       MBDS  has  been used with and  remains the  marker for  comparing
       all  other practical B-NIP alternatives.   However,  when exception
       from  an   administrative regulation  or  existing prohibition is
       sought,  the  moving  party has  the burden of  proof ana the  cost
       of  going  forward to bear.  COE's-specific  responses  to Disposal
       and  capping  at  the Basin is presented  in  Appendix G  ('G   for
       "Generic?") yet  viability and  prohibition repeal are downplayed.
       Prohibition  repeal  has  not been clearly  and  simply  presented
       in documents, press reports or at public informational meetings.

       Instead,   capping  off  Portland,  Maine at  a water  depth  of 50
       meters  and in deeper, waters off the Pacific  coast and Long  Island
       Constitute "new  data."  Despite unspecified  "modeling" a  single
       reference  in Ms.   Lynch's comments  (p. A-2-9)  suggests  that a
       COE   experiment  to cap  FAILED  near  the  Basin  and  that  the
       sediments  ended  up in different areas  (something  about a  toggle
       buoy failing to  remain tight  and  taut in deep  waters...).  I
       don't believe reasonable  consideration  has  been  given  yet to
       the   duration, intensity  and  quality/quantity  issues of  B-NIP.
       While COE and MassPort may be  confident and more  than willing
       to  experimentally  test  in  Class SA  waters  adjacent  to  a  NMS,
       costs are relative in a migratory endangered  species  corridor.

       January  1993, upon formal  MBDS designation,  EPA's Belaga  and
       EOEA's  Tierney   set prerequisite for  repeal  of prohibitions on
       hazardous dumping and subsequent capping at  MBDS.  Other agencies
       were meant to be party to legal  prohibited uses challenge.  When
       need appears  to  outweigh due process and potential environmental
       consequences  then public review/comment can  be deemed reasonable^

       "Since  1974,  approximately  3  million  cubic  yards  (mcy) of
       trials  have  been placed  at MBDS.   Since  1977,  MBDS has  been
       used exclusively for dredged materials disposal. B-NIP proposes:
                       1.1  mcy   of contaminated materials
                       2   mcy   of  "parent"  or underlying materials
                       4.4   mcy   fbjcinvfuture  project dredge maintenance
       for a  conservative estimate of 7.5 mcy.  When will MBDS capacity
       be  exceeded?  When is  a Basin  no  longer  a basin?   Does  MBDS
       have COE's  "unlimited  capacity as  long as  there is sufficient
       capping material"  for this  a  single yet massive  input of known
       spoils   proposed  over the  next  3-10  years?   Are mega-projects
        (B-NIP, CA/T) why we designated a regional dredge disposal  site?___
                                                                       «^^——
       Boston, but  especially the Inner, Harbor is  an active sink trap
       for  particle   reactive   components.    There   are  significant
       accumulations of PCBs, PAHs,  cadmium,  chromium,  lead and   otner
       heavy  metals   (along  with   oil  and  other  "constituents of
       concern").    Top sediments  show lower  concentration of  metals
       than the  overlying water  columns.   Is  there a  diffusive  flux
       into the  harbors'  sediments?  Does  accumulation of excess  carbon

-------
INADEQUATE/NOT PRACTICAL
                                                    p. 3 of 6
and  nutrients  drive the redox  potential at  several  hund5e<*  h°t
spots  within  these  highly oxic  areas  proposed to  be  dredged?
scores of CSOs empty, factories line the shoreline. The sediments
have been ^ oxygen  depleted  for .100   to  200  years.  Upon  the
introduction of oxygen  and aromatic PAHs, even in massive debris
fields,   new  metabolic  conditions  have  occurred.    In  situ  ,
bioremediation  of  sediments  have  been  successful  despite  the
extent   of  systematic  degradation.  At the Charles town  Naval
Shipyard,  where  PAHs concentrate idue  to overly-treated creosote
wood pilings,  micro-organisms  that eat  carbon  have flourished.. I
Whv  aren't there specific references to cleaning sediments BEFORE
dredging  and  disposal?  Per  cubic yard cost  estimates  should
be based on remedial actions on site and driven by the resource.
                                                                 m
MPRSA  Title  I made it  unlawful  after  31  Dec  1991  for dumping
or transport for the purposes of dumping industrial waste without
a permit.  Will ALL proposed  dredging  materials, including clean
"parent"  (never before  dredged) materials,  be CONTINUALLY tested
up  to  disposal?   What  is  the  likelihood of known contaminated
upper  sediments and silt of Boston's harbors shifting, shoalling,
settling,  eroding,  becoming shaken out  of  buckets, resuspending
and  migrating onto "clean" underlying materials during operations
,or in  the interim?  Why won't all capping materials be marginal? _J
                                                                   >
At  a  proposed dredging  rate of  2-8  barges daily, 8-12  hours
to load  and  tow,  over l£-2 years, is it reasonable to anticipate
more than 4,000  barges  to  an  off-shore  site?  How much  time
 (in  days,  weeks,  months,  seasons,  and  years) will  pass between
-the  first shipment of spoils to full capping?  Based on B-NIP's
proposed: quality/quantity;  location/duration; technology/costs;
every  barge possesses high/less high degrees of hazardous spoils.

What could happen to the  integrity not  only of the product, but
the  permanent structure  COE proposes  to build at  MBDS?   What
will be the  backgrounds,  expertise and authority of these  COE
 inspectors on proposed MBDS  trips? Who monitors,  confirms  and
can  make adjustments to operations or the  MBDS  taut-wire moorea
buoy?    Why no monitoring during and around the descent phase?  —

The  US  Coast  Guard (CG)  regulates  all  vessel  traffic  control,
navigational and shipping activities, vessel design, construction
 and  operation,  and is  responsible  for. minimizing the likelihood
 of  accidents,  conducting routine  vessel  inspections  and  must
 ensure  safe  working  conditions  ,are  maintained  onboard  ships
 and  barges.   In addition, when harmful  discharges  do take place
 and  in  response to The  National Contingency Plan for the removal
 of  hazardous  substance discharges  (40  CFR  Part  300),  the  CG,
 in  cooperation with EPA, administers The Plan and  the  clean-up,
 CG  personnel must  investigate  all  reported  offshore spills  and
 supervise  all clean-up operations  including the hiring of private
 contractors  when  response is not prompt, and it is  the CG  that
 retains  final  authority over clean-up procedures  and equipment.
                                                                     \S

-------
r
INADEQUATE/NOT PRACTICAL
p. 4 of 6
        Taking  into account  that  the  CG may  be court-ordered to shut
        down  shipping  into  Boston  Harbor  until  CG  funds  and mounts
        effective monitoring  programs,  estimated at $5 million annually,
        to enforce  national  laws  protecting endangered whales  and other
        Sanctuary  resources,   does anyone  see an  expanded  role  for  CG
        in proposed dredging, transport, disposal, capping  & monitoring?^
                                                                         ^
        MBDS  is an Impact Category  I  Site.  MBDS still  remains  a site
        of  unknown  contamination.   Chemical,   nuclear,  munitions,' and
        dredged  disposal  has occurred in 'varied  containment.  Coffins
        of radioactive  containment,  ringers *  are only blips  on modeling
        side  scans. DAMOS/ADDAMS  didn't do  continuous coverage  of  the
        whole bay floor  only  reconnaissance surveys. The  burden of proof
        is NOW  on  discharger(s)   to  show that  area resources  will  not
        be further  damaged.    Before  a  permit is  issued and  in compliance
        with  40 CFR 228.10,  who  will vigorously pursue and  encourage
        the  best   available   management   practices   to  minimize  even
        relatively  small impacts  to an  Impact  Category  I  Site?   What
        are the boundaries and buffer zones to Impact Category I Sites? _

        'MBDS  is established   over a two-nautical-mile-diaraeter circle.
        The  Basin   touches  slightly  at  a  point  the  NMS.   Rather  than
        a holistic  approach,   NOAA appears  to be reactive about threats
        to" the  deepest  part of Mass  Bay  and the  Stellwagen System.  This
        general area has also  been called the Foul (not Fowl)  area and/or
        Marblehead,  which is  10 miles to shore. The preferred  alternative
        terminates  in Class SA waters, adjacent  to an  outstanding  area
        of national and regional  importance.   Water and habitat quality
        at this  Basin  affects  the Bank.  This is an  ecosystem that has
        maintained  its   integrity   for  at least  the  last .13,000  years.

        The Basin is surrounded by continental shelf,  banks and ledges.
        Water depths at  MBDS  average 90 meters plus and shrinking. While
        the  Basin   possess  deeper waters,  the coastal  shelf  does  not.
        Even relatively  small impacts  could  produce  significant changes
        to internal waves, currents  and other Sanctuary resources and
        qualities.  The eastern slope of the Basin is incredibly pristine.

        Sand  is the predominant  sediment  of  the  Bank and surrounding
        areas.  Sand on  top  of clayey-silt  covers most  of Stellwagen
        Basin and   is  mixed   by   currents  with  fine-grained materials.
        Bottom  currents  carry fine  sediments which  are then reworked
        in patches  with coarse grains that are the result of area erosion
        of exposed  substrate.  Deposition  is on-going.   Fine sediments
        don't build up.  They  appear  only  temporary.  Most deposition
        is available to be resuspended in the currents  and water columns.
        The Basin's sediments are  the  System's source  of  clean detritus
        and  change.  However,  in  the  center  of the  Stellwagen  Basin,
        sandy cover gives way  to sand-silt-clay bordering clayey silt.
                                                                       ^•^M
        Capping  may be  impossible  to attain,  establish or  repair.  The
        technical capability  to cap  soft,  unconsolidated  materials with

-------
 INADEQUATE/NOT PRACTICAL
p. 5 of 6
 Boston  blue clay has  not been- clearly  shown to be viable.  The
 structural  properties  needed  to support and form dense cohesive
 material,  especially considering the contamination  matrix,  may
 not  create a permanent capping barrier. Rock blasted from B-HIP
 may  sink to the  Basin area's  firm  substrate.  The most severely
 contaminated spoils won't go down first  (private berthing dredges
 not  in  sequence; soft  surficial. materials dispersed over larger
 than  anticipated  areas;   concentrations not  solely  a  function
 of  dilution).  Attempted  capping could  further  disturb  what  was
 last  disposed^ in  1983 and  could again move spoils  beyond  the
 site  boundaries.   Estimated  3-5% lost  during descent  phase  is
 the  unaccounted  for dissolved containment fraction  of  the most
 hazardous  "constituents  of  concern" possibly in   the  nation.
 Capping  presents  risks and  a  high failure potential that needs
 to be fully disclosed publicly, hopefully in a separate EIS/R.   	

 The Merrimac River is  the  dominant source of  fresh water tothe
 Basin.  Direction is in a rugged pattern driven by tides,  depth,
 cooling at the surface/ and a mean westerly wind. Severe weather
 events,  and I'm not  referring to Hurricane Gloria, have a higher
 occurrence probability  than  we have recently experienced.   We're
 overdue   100-250-500-year   storms.    Normal   circulation   is
 influenced  by  all  these  factors until an  established  current
 is hit.  Counterclockwise surface currents  flow over the system.
 Does  MassPort,   their   contractors or  COE proposed  any  volume
 or  weather  or  seasonal   restrictions  regarding  the  proposed
 dredging, transport,  disposal, capping and monitoring operations?

 Why doesn't this  information exist in the DEIR/S  for this  bench
 marker alternative? Don't  we need relevant background information
 to achieve  any reasonable  combination of logistics,  technology
 and cost within the given  time  constraints and regulatory  mazes?

 I  would like to comment on  the. Boston Lightship/Industrial Waste
 Site's fine grained substrate  to be borrow pitted  and Messburger
 Sites  2  and 7 being near  impossible to  model and monitor but
 it would  be premature to  prejudge  cumulative impacts  of the
 proposed MWRA outfall  dispersal system  so  near to these  sites.

 The  "rainy day"   introduction  of nearly  a  billion gallons of
 fresh  water to the salinity  levels and currents there, near-site
 impacts  to levels of pre-treatment  achieved at  Deer  Island prior
 to  discharge start-up at the mile-long "submerged killing fields"
 from  MWRA's own  "constituents of concern,"  and what  monitoring'
 and mitigation  will  be  judged  necessary and in  place   still
 remains  to be seen.  (Will you join me in pressing for the long
 overdue  permit application process and public  review?)

 Please give me  reasons why Boston doesn't deserve  another  island
monument  to "transport not treatment"  waste management practices.

 I have concerns about MassPort.  To whom  is MassPort responsive?
                P1-9

-------
 INADEQUATE/NOT PRACTICAL
                                                               p.  6 of 6
 I can  support dredging and disposal  alternatives for B-NIP that
 include:  sediment  bio-remediation  (fullest  extent achievable)
 prior  to public and  private dredging;  no barges (How do Truitt
 barges operate?   Got pictures?)  of  "unclean spoils"  but nearby
 placement  and capping  at shallow  depths;  reusing and recycling
 underlying  materials  in  already  degraded (Class  SB  and Class
 SC waters)  marine  environments;    suction technology to dredge;
 silt screens in place  for all  phases of  operations;  beneficial
 uses of  underlying substrate  for  sea walls/slope stabilization
 in areas prone to erosion  and estimated in proposed maintenance;
 use of MBDS  only  for low-volume,  clean materials following both
 in-depth report and  publicly-released-for-review MOUs  with EPA,
 Commerce/NOAA/Sanctuary Management and the  CG;   and proactive,
 beefed-up, safety  standards for transports to and from Boston.

 I'm a  little concerned that  what's proposed for federal channelT
 and  private/public  berths  may  not  be  deep enough.  Too  many
 container  vessels,  LNG  ships,  and  oil  tankers  calling Boston
 in 1991  were well  over 900  feet  in  length.   They  draw  as  much
 as 41 feet yet there  were no accidents or grounding upon turning.
 The navigational  realities of  fully loaded double-hulled vessels
 expected 1995-96 could  make the proposed dredge depths inadequate
 before it even finishes  review.   The  proposed  B-NIP bottom will
 be a little  deeper, a whole lot harder, and bigger will come.
 Are any  high-risk cargo restrictions planned  to follow B-NIP?

 There  are reasons to  believe  the spoils will  be  contaminated
 and unable to satisfy exclusion criteria (Tier I data review).
 There  is  potential  at  MBDS  for Toxicity/Bio-accumulation  as
 capping  at  90  meters  is  at  best  experimental  but  logistically
•can't not be impacts  to the marine ecosystem  (Tiers -II & III).
 Because  capping  is viable  in  shallow water  and  shallow  water s
 located  within an  economically/operationally feasible  distance,
 prohibitions for  incompatible  uses  exist  and  should exist  in
 sensitive  areas,   this  consistency  review   is  incomplete "and
 lacking.   Because  time limits  to  COE actions  exist, and it  is
 naive to think that we can  keep pollution at  bay or make changes
 later,  the preferred  alternative is NOT PRACTICAL as presented.

 Please reserve and present copies of any new EIS/Rs-or relative
 documents, any Supplemental EIS//R, the Final EIS/R, Consistency
 Reviews, MOUs, and  the  ROD  for my review and comment.  Thanks!
                                        NEWS BRIEFS
                         P.S.
          Bev Carney
          38  Longview Drive
          Orleans, MA  02653
Comment on Boston project invited today
 HYANNIS - A public meet-
ng J»"d workshop to discuss
he,  aosed improvements to
Sosiua Harbor •will begin at
:3Q bjn. today at the Tara
•lyannis Hotel.
 Offered by the Army Corps of
Engineers and the Massachu-
-erts Port Authority, the meet-
ng is designed to give the pub-
             The workshop will include a
            presentation on the major fea-
            tures of the improvement pro-
            ject and a forum where com-
            ments may be made. Recess
            will be held between 4 and 6
Really wanted to attend the Cape
public meeting of 19 May but
Demos never called back (16 May
0937 hours at (617) 647-8257).
Thought the repeal at the Basin
would have been significant to
Cape Codders but unable to make
needed reservations (see attached)
                                                          THURSDAY, MAY"
            particular time may be made by

-------
 Pl-l
        Use of MBDS for silt dredged from the ERNEF* is not proposed in the FEIR/S.
 Disposal of sediments considered unsuitable for unconfined open water disposal at MBDS
 could be considered in the future only if capping is successfully demonstrated.
Pl-2

        Your comment points to a need for a regional disposal site that can accommodate the
disposal of contaminated dredged material in a safe manner.  Support for a regional disposal
site is needed.
Pl-3

        Due to the volume of material contaminated, the types of contaminants present and the
proposed project schedule the in-situ bioremediation of the silt material is not a viable option.
Based upon a recent review of existing bioremediation technologies, as part of the Assessment
and Remediation of Contaminated Sediments (ARCS) Program, the USEPA has concluded that
"because of the complexity of the sediment-water ecosystem; the difficulties in  controlling
physical and chemical, as well as biological, processes in the sediment, and the  need to adjust
environmental conditions for various stages of the biodegradation process; limited effectiveness
has been demonstrated for in-situ bioremediation" (USEPA 1994).  In addition, in-situ
bioremediation is not effective in treating the inorganic contaminants present in the  Boston
Harbor sediments.
Pl-4

        Section 3.0 and Appendix D in the final EIR/S discusses the effectiveness of treatment
technologies. Factors considered for the various technologies include how fast the dredged
material can be processed, what contaminants are removed and to what levels, cost and
availability.
Pl-5

       Dredged material is not regulated as industrial waste. This project is not proposing to
discharge industrial waste in ocean waters nor any other location. This project is exclusively to
dredge and dispose of same material. There is no plan to continually test the clean parent
material. This material has  remained in its present condition since glacial times and is not
expected to become contaminated from continued accumulation of surficial silt. The dredging
of overlying silt will be conducted so as not to disturb the parent material before its removal.
Refer to Section 5.0 for details on the Dredge Management Plan. Therefore, upon its removal,
the parent material will be  clean for capping and other beneficial uses.

-------
Pl-6

       Approximately 1.6 million cubic yards of parent material will be disposed during the
navigation improvement project at the MBDS.  The average barge will carry between 3,000 to
12,000 cy of parent material per day to the MBDS. That means between about 130 and 530
trips would be made during construction of the project, not 4,000 trips. Only clean parent
material will be disposed at the MBDS.  Disposal of the clean parent material could actually
help cap other material previously disposed at the MBDS.

       There is no permanent structure proposed at the MBDS. The Corps of Engineers will
hire an independent dredge inspector to assure accurate placement of the dredged material.
The Corps determines the placement of the taut-wire moored  buoy.  No monitoring of the
MBDS site is needed as the material is clean, previously undisturbed parent material.
Pl-7

        The Coast Guard currently oversees harbor safety practices. There is a direct role
related to blasting safety and seaworthiness of the tugs and scows. An expanded role of the
Coast Guard related to dredging is not foreseen.  Also, dredged material from Boston Harbor
is not classified as hazardous material.
Pl-8

        The reader should refer to the U.S. EPA's site designation of the MBDS for additional
information.
 Pl-9
        No disposal of unsuitable material will occur at the MBDS for this project.
 Pl-10
        Severe weather events, regardless of the global position of the source, are relatively
 predictable by today's sophisticated equipment and meteorological modeling. The dredging
 contractor will be required to develop an Accident Prevention and site Emergency Plan as part
 of the required preliminary submittals for performing this work. This plan, as noted in Section
 5.8.3.1, Weather Related Issues, will include specific actions to be taken in the event of severe
 weather. Tug captains will make the decision whether to transport parent material into
 Massachusetts Bay during inclement weather. Dredging operations will not occur if the
 weather is too severe. Also, no dredging or disposal will occur during restricted periods in the
 Mystic River and  Inner Confluence.

-------
Pl-ll

        Information on the susceptibility of the potential aquatic disposal sites to storms (and
the resulting wave generated bottom currents) is included in Appendix G and was used in the
comparison of the aquatic alternatives (Section 4)..
Pl-12

       The DEIR/S did not propose to construct a. borrow pit at the Boston Lightship.
Neither the Boston Lightship nor the Meisburger sites was identified as the preferred disposal
alternative for the BHNIP.
Pl-13

       Because the Meisburger sites were found not to be the preferred alternative for
disposal of silts from the BHNIP, this project will not interfere with the monitoring of the
MWRA outfall.
Pl-14
       The BHNIP is not proposing to create an island for disposal of dredged materials.
Pl-15
       Massport has reviewed and responded to all comments received on the BHNIP.
Pl-16
       The selection of the in-channel alternative provides the least disruptive, most
environmentally benign scenario for disposal of silts dredged from Boston Harbor. The Dredge
Management and Monitoring Plan (Section 5) provides details on the techniques that are being
proposed to control both the dredging and disposal phases of the project. The feasibility of
bio-remediation has been examined, but it would be impracticable for this project, particularly
in situ, as the commenter suggests. The proposed disposal plan would not eliminate barges
but it would minimize their movements in the harbor.  Clay is being provided to municipalities
for  closure of landfills. Any not used for this purpose would be disposed at the MBDS. The
MBDS has been designated as dredged material disposal site for material suitable for
unconfined open water disposal, like the parent material from Boston Harbor.  No MOU's
between agencies are needed.  The EIR/S  acts as  vehicle for public comment.  Information has
been reviewed on several suction technology dredges such as the XETEX Corporations Eddy
Pump.  Specifications are expected to require contractors to meet certain production
requirements.  If these requirements can be meet  with a suction technology then it will be
considered. The Corps always requires appropriate safety standards for dredging and disposal
operations.

-------
Pl-17

       The 1988 Feasibility Report examined deeper channels but they were not economically
justified at that time. A new study to examine all or a part of Boston Harbor would have to
be requested by a local sponsor.

-------
                             PAUL P. CODINHA
                             70 FRIEND STREET
                          GLOUCESTER, MA. 01930
                  DAYS: (617) 274-4304  EVES: (508) 283-8886
            5TH ESSEX STATE REPRESENTATIVE CANDIDATE
                                JUNE 16, 1994
Ms. Janeen Hanson, Project Mgr. for Dredging
% Massachusetts Port Authority
Atlantic Ave.
Boston, MA. 02101                 .       :

Dear Ms. Hanson:

This letter is to publicly voice my opposition to the proposed dumping of about 1 million
cubic yards of contaminated material from Boston Harbor ( near one of the state's most
productive lobster fishery areas ).

After reading the article by David Olson in the June 9th issue of the Gloucester Daily
Times, I think its tune for the citizens of Essex, Gloucester, and Rockport to ban together
in opposition to such detrimental measures which could potentially affect the future of our
area's fishermen and their families, not to mention the health, economy, and environment
of the Cape Ann community. We have been bleissed with the beauty of the ocean, and its
up to us to keep it clean for its marine life and preserve our resources for future
generations.

There must be other alternatives that could be explored that would not have such a
devastating effect on our community and its quality of life. I would appreciate setting a
meeting for the Cape Ann citizens to express their concerns in my district since none was
arranged hi the past. I look forward to hearing from you .

                                             Sincerely yours,
P2-1
                                             Paul P. Codinha
                                             5th Essex State Representative
                                             Candidate

-------
                                              Paul P. Codinha
                                              5th Essex State Representative
                                              Candidate
CC: Mr. William Adler, Mass. Lobstermeris Assoc.
    Mr. Tom Bruha, Corp of Engineers *£&=>
    Mr. Philip Coates, Dir. Mass. Marine Fisheries
    Mr. Thomas Biggins, Mass. Dept. of Environmental Protection
    Letter to the Editor, Gloucester Daily Times

-------
P2-1

       The revised alternatives analysis (Section 4.0) has concluded that the in-channel,
partial-fill shoreline and upland sites are the least environmentally damaging alternatives for
disposal of silt from the BHNIP. Any of these alternatives would minimize impacts to the
lobster fishery.
                                                  4/5

-------
                               Dr.  Paul F.  Murray
                                   P.O. Box2107
                                Osterville, Ma. 02655
                                  (508) 428 - 7807
                                Fax (508) 428 - 8404
Ms. Trudy Coxe, Secretary
Massachusetts Executive Office of Environmental Affairs
MEPA Unit
100 Cambridge Street
Boston, MA 02202                                                       May 19, 1994

re: Boston  Harbor Dredging

Dear Ms. Coxe:

I attended the public meeting on May 19, 1994 in Hyannis,  MA, and spoke about the lack of
sufficient background material for the public to make an informed decision or to ask relevant
questions based on the executive summary of the draft environmental impact report/statement
*hat was provided.

The Corps of Engineers  representative provided me with a copy of the two  volume
environmental impact report that gives a great deal of information that was not covered in the
brief presentations made at the public meeting.

The basic public policy issue appears to me to be "Where and how should the 1.3 million cubic
yards of contaminated  silt materials be disposed  of to  minimize  environmental risks at  a
reasonable cost?"

Having an extensive background as an international developer of  real estate projects and
based on an analysis of the information provided in the reports furnished, I have come to the
conclusion that the contaminated materials  should  be disposed  of in a trench  in
the  little Mystic channel and  the  westerly portion of the Mystic River not being
deepened  to 40  feet.

While this alternative is slightly more  costly, there are advantages that make this the most
environmentally sound alternative in my judgment.  Some  advantages of this alternative are:

      1. Moving contaminated material out of the inner harbor runs the risk of spills and
         contamination of unintended areas containing marine life,

      2. Ocean disposal in the outer harbor has the potential of  creating future problems,  if
          contaminated materials escape into the water and effect the marine life, and

-------
      3.  The clean material, over excavated to make room for the contaminated material, may
         be put to good use in environmentally sound locations, such as clean fill to
         extend land areas, barriers for beach erosion, and possible commercial or other
         environmentally sound uses.

 iis placement of contaminated material should be at a depth to allow for future dredging to a
|epth of 40 feet to avoid conflicts with unknown future needs.  Any material not accommodated
[n site in the inner harbor should be capped in a location not subject to  excessive currents,
 lost likely at Spectacle Island.

   suggestion of the Conservative Law Foundation bf an independent observer with powers
  stop work  is an unnecessary, potentially costly, and dangerous precedence.

 ie future maintenance dredging of 4.4 million cubic yards of contaminated material over the
lext 50 years should be  evaluated over time. Perhaps environmentally and economically
[ound alternatives  will be available,  such as: chemical treatment and  other locations for
jisposal.                                        ;
                                                                                   -*,
 5 a tax payer, I was disturbed to see that it takes six:years of planning and considerable cost
  get this necessary project underway.  Let's hope you can finalize this environmental impact
 sport  soon and start construction.  No solution will satisfy everyone who has an interest.
 lake your best judgment.
                                                                                       P3-2
                                                                                       P3-3
 :ncerely,


)r. Paul F. Murray
   Brink P. Miller
    Colonel, Corps of Engineers
   424 Trapelo Road
   Waltham, MA 02254

-------
P3-1
       The BHNIP team concurs that in-channel disposal is an alternative that would
minimize impacts to the environment, although we believe that using **£""*?& * be
                     is preferable to expanding into areas not proposed for dredging.  Hie
              alternative incorporates extra depth to protect the silts from future maintenance
              >. parent material (primarily Boston blue clay) will be made available for closure
of municipal landfills.
P3-2
        Only the Corps of Engineers contracting officer or her representative can control the
contractor's work.  Independent observers can identify potential violations to Hie Corps
inspector on-site.
 P3-3
        Future maintenance dredging will have to follow applicable ^vironmental regulations
 at that time. Tie EIR/S attempts to predict an area that may be acceptable for future
 maintenance dredged material disposal.

-------
LETTERS RECEIVED AFTER THE COMMENT PERIOD

-------

-------
 ETS& G. 7QHK2LDSSM
I 6TH DISTRICT. MASSACHUSETTS

    ARMED SERVICES
       COMMITTEE   -
    SMALL BUSINESS
      COMMITTEE
   MERCHANT MARINE
     AND FISHERIES
       COMMITTEE
Congress of  tfje Hmteb
               of  &epre*entatt&e$


                  August 17, 1994
  T2C CANNCN SUU.DING
 WASHINGTON. DC 2OS15
   \2C2) 22S-8O2O

  70 WASHINGTON STREET
   SALEM, MA O197O
   (508)741-1600

156 BROAO STBCET. SUITE 106
   LYNN. MA 01901
   (617)599-2424

   160 MAIN STREET
  HAVERMILL. MA 01830
   (508)521-0111

   61 CENTER STREET
 BURLINGTON. MA 01803
   (617)273-4400
      The Honorable William F. Weld
      Office of the Governor
      State House
      Boston, MA 02133

      Dear

             I am writing at the request of Safe Waters in Massachusetts (SWIM) whose members I
      have been working with on an important environmental issue facing the Northshore.

             As  you may be aware,  the  U.S. Army Corps of Engineers  is planning to perform
      maintenance dredging to deepen a navigation channel in Boston Harbor. The dredging project
      should be a positive step toward increasing commercial shipping into the harbor which will help
      boost the Massachusetts economy.       -.       •           .

             The issue that SWIM and many others are concerned with is the proposal to dump the
      dredged material off the coast of the Northshore at an ocean site  known as "Meisberger 2."
      According to the information I have been provided, Meisberger 2 is a prime lobster habitat and
      especially an area where juvenile lobsters develop. SWIM has access to research .performed by
      scientists from Northeastern University which illustrates that the dredge material  has a toxic
      effect on lobsters. This information was presented to the Corps of Engineers at a public hearing
      on Thursday, July 28, in Nahant.

             It is my understanding that the Corps of Engineers performed a "Biological Assessment"
      while studying the Meisberger  2 proposal  which tested the effect of the ocean dumping on
       "threatened and endangered species." However, as the Massachusetts Lobstermen's Association
       pointed'out, just because lobsters are neither threatened  nor endangered, does not  mean we
       should pursue a disposal alternative that would harm the existing and future lobster population.

             I know you are aware of the incredible challenges currently facing the commercial fishing
       and lobster industries in Massachusetts.  Now is certainly not the time for the state and federal
       governments to be imposing additional hardship on these industries. As a member of the House
       Merchant Marine and Fisheries Committee I am very concerned about the quality of marine life
       and the future of the fishing industry.
                                             PRINTED ON RECYCLED PAPER

-------
Governor Weld,
August 17, 1994
Page 2 of 2
       As with most federal projects of this scope, the Corps of Engineers cannot begin work
without some form of consent from the proper state agencies.  While I do not want to do
anything to prevent or delay the dredging of Boston Harbor, I would like to make sure that
members of SWIM and other concerned citizens have the opportunity to provide information to
state officials with jurisdiction over this matter prior to  any decision being made.

       I would like to request that someone from your staff look into this matter further. If any
agencies are  planning public meetings or hearings on this issue  I would appreciate being
informed so that I can pass the information on to members of SWIM and others.  If you have
any questions regarding 'this issue please feel free to contact me.
                                       Very truly
                                       PjETER G. TORKILDSEN
                                        lember of Congress
PGT/maa
cc:    Mayor Patrick McManus, Lynn
       Colonel Earle C. Richardson, Corps of Engineers
       Nahant Board of Selectmen
      .Swampscott Board of Selectmen
       Safe Waters in Massachusetts (SWIM)

-------
                                          •%&
                             ASSOCIATION
                              (North Shore;
                            CF:
November 2, 1994
                                               Pete Jackson
                                               PAD
Ms. Trudy Coxe, Secretary
Massachusetts Executive Office
  of Environmental Affairs
MEPA Unit
100 Cambridge Street
Boston, MA  02202
     Subj ect:
Dear Ms. Coxe:
Boston Harbor, Massachusetts Navigation
Improvement and Berth Dredging Project
At its meeting of November 1, 1994, -the North Shore
Harbormaster's Association reviewed circumstances surrounding the
disposal of dredged material associated with the subject project
at sea, particularly at a site called Meisburger Two.  Following
protracted and detailed discussion, the association voted
unanimously to strenuously urge your own and other involved
agencies not to dump Boston's contaminated dredging spoils in
North Shore waters especially where the MWRA sewage outfall will
soon be located.  Indeed, we correspond to request that your
agency and others make certain that this dredged material is  not
disposed off our shores.            ;

We are particularly concerned about ;the potential effect on North
Shore harbors and on the fishermen and lobstermen who operate
their small businesses from those harbors.  Dr. Joseph Ayers,
Interim Director of the Northeastern University Marine Center,
has outlined the devastating effect jthat dumping of polluted
dredging spoils could have on the survival of young lobsters  at
Meisburger Two  (the area known locally as Rosie's hole).  Already
                         \

-------
the fishing and lobstering industries are in trouble.  If we
intentionally damage and pollute the habitat where fish and
lobster grow, the situation will only get worse.

No studies have been done of the combined effects of sewage and
dredging spoils disposed of so close together and it therefore
will be impossible to monitor pollution from either because each
will blame the other for any violations.  Now, the Massachusetts
Water Resources Authority is talking of not completing secondary
treatment and MWRA is also talking about placing an oil tanker
terminal offshore, somewhere in the vicinity of the sewage
outfall and the Meisburger Two site.  This would constitute a
"triple Whammy" which could deliver the final blow to our fragile
coastal environment where many earn their living, where tourists
pay to visit, and where we and our children live, play, and swim.

We urge you to work for the following goals:

     1.   That Meisburger Two be eliminated as a
          possible dumping site for dredging spoils.

     2.   That no contaminated materials of any kind be
          dumped anywhere at sea.

     3 .   That before any plans to pollute go forward,
          scientific studies be accomplished to
          determine the combined effects of dredging,
          sewage disposal, and oil spills from tankers.

     4.   That genuine solutions be found reducing
          pollution at its source, treating waste
          materials properly, and ultimately developing
          alternative forms of energy to reduce
          dependence upon fossile fuels.

It does not make sense to clean a dirty place such as Boston
Harbor by polluting a clean place such as Massachusetts Bay.

Very truly yours,
North  Shore Harbormasters Association
Joseph Dunn
President

-------
P.S. Harbormasters and Assistant Harbormasters of communities
     from Salisbury to Winthrop and all cities and towns in
     between comprise the membership of the North Shore
     Harbormasters Association.    •
cc:  Brink P.  Miller
     Colonel,  Corps, of Engineers
     U.S.  Army Corps, of Engineers
     424 Trapelo Road
     Waltham,  MA  02254

     National  Marine Fisheries Service
     One Blackburn Drive           •
     Gloucester, MA  01930-2298

-------
                                                                F/W
F. M. VALENTI, INCORPORATED & ASSOCIATES
                                                              ESTABLISHED IN 19(
    Colonel Brink P. Miller                                 September 15,1994
    Division Engineer
    U.S. Army Corps of Engineers
    424 Trapelo Road
    Waltham, MA 02254-9149

    Dear Colonel Miller,

    I'm sure that you've seen the enclosed effort by the Nahant SWIM group. I  am also
    certain you are aware of the plight that faces all ocean front communities, so I won't
    bore you with redundant pleas to do what is right.  It is painfully obvious that one can
    not clean house by sweeping  the dirt under the carpet nor can one take  polluted
    material from the harbor and dump it into the bay. This course of action will pollute the
    bay and, because of its proximity, find its way back to all the shores and the harbor too.

    Please do your best to ensure that the officials of the Commonwealth aren't accused of
    being so foolish as to spiUn the wind or shovel silt against the tide.

    If there are no landfills that can use the dredged materials, the least that could be done
    is to take the contaminants out a couple of hundred miles. This wider dispersion would
    do considerably less damage to the environment than that anticipated in the confined
    area closer to shore. Too often Massachusetts has taken the short term view, only to
    pay exponentially later on.  If you take the right steps up front, you and  we the voters
    won't suffer the consequences later on.

    The citizens of this environment will be watching and your actions will be rewarded at
    the polls.                   :
                                       Sincerely yours,

                                       FranValenti

    ps: The Japanese built an airport in Osaka Bay with landfill material. Boston's back
    bay was built on landfill.  Surely there is some future endeavor that could benefit from
    this fill, polluted of not.  Don't you politicians plan any further ahead than the next
    election? How about Logan Airport? Won't that facility need to expand in the future?
    Where does all of the "study money" go?  Pork barrels me thinks!
1 SAUNDERS LEDGE  •  NAHANT, MA   01908-1692   •   (617)  592-5300

-------

 RECEIVED
5EP i 9  i;D

-------

*

-------
                     COASTAL ADVOCACY NETWORK    	
                     c/o Massachusetts Bays Pro-am, 100 Cambridge Street, Room 2006,
                     Boston, MA 02202, phone: 1-8(XM47-BAYS, jax:(617) 727-2754
March 31, 1995                                 ;

Brink P. Miller, Colonel
U.S. Army Corps of Engineers
424 Trapelo Road
Waltham,  MA 02254                            ;

Dear Colonel Miller,

We are writing because of a concern among our membership regarding the ongoing possibility of
ocean disposal of contaminated sediments from the Boston Harbor Navigation Improvement
Project into Massachusetts Bay. We know that our opinion about this was expressed to you
thoroughly during the comment period for the Draft Environmental Impact Review process, and
our early indications suggest that you were listening to what we had to say. We hope that proves
to be the case when the Final statement is released.

However,  we are concerned that there has not been enough thought given to the potential
cumulative impact that may result, should ocean disposal of contaminated sediments occur,
especially  in light of the increased toxicant burdens placed on the Massachusetts Bay system by
the extended MWRA outfall pipe (now scheduled to begin operation in 1997). We feel that if
these two  major potential ecosystem impacts start in such close proximity to each other, more
thought and attention should be given to the  combined effects of the two projects.  Undoubtedly,
this would take place through a study modelling all 'aspects of these projects, but with special
attention to their effect on the biota of the system.

While we  realize that such a study may be time-consuming, we feel it is vital to step cautiously
before exposing this important  area to additional risks. The waters of Massachusetts Bay are used
by many commercially and recreationally important ;fish and shellfish, and by numerous
endangered species. These resources are too valuable to treat lightly, both for their inherent
worthiness and their commercial importance to the  region.

We  also want to take this opportunity to thank the| Army  Corps for the openness with which this
project has proceeded to this point.  We appreciate being invited to participate in the working
groups, and look forward to continuing to work with the Army Corps as this project moves to
fruition.

Sincerely,
 Mason Weinrich, Chair                         :

 Coastal Advocacy Network:                      :
 Susan Nickerson, Assoc. for the Preservation of Cape Cod
 Mason Weinrich, Cetacean Research Unit
         The views of the Coastal Advocacy Network do not necessarily represent those of the Massachusetts Bays Program.

-------
Bob Loring, Clean Water Action
Peter Shelley, Conservation Law Foundation
Robert Buchsbaum, Mass. Audubon Society
Paul Burns, MassPIRG
Roger Stern, Massachusetts Bay Marine Studies Consortium
Jonathan Kaledin, National Water Education/Funding Council
Polly Bradley, Safer Waters In Massachusetts
Jodi Sugerman, Save the Harbor/Save the Bay
Mary Loebig, Stop The Outfall Pipe
cc:     Secretary Trudy Coxe, EOEA
       Doug MacDonald, MWRA Executive Director
       Ralph Cox, MassPort, Maritime Director
       Diane Gould, MBP Executive Director

-------