600283110
     IRON AND STEEL PLANT OPEN SOURCE FUGITIVE- EMISSION CONTROL EVALUATION

                                    by

                Thomas Cuscino, Jr., Gregory E.  Muleski,  and
                           Chatten Cowherd,-Jr.
                        Midwest Research Institute
                           425 Volker Boulevard
                       Kansas City, Missouri   64110

                                 Notice

                  This document is aprel-.. -.; ry e.^a^t
                It has not been formally r  " ^asc-a by r '  •  -
                should not at this stage be co.vrtru"--:
                represent Agency policy.  It it beir -c	
                lated for comment on its techr.ic a.1 ^ocura.y
                and policy implications.


                                  DRAFT

                                FINAL REPORT

                EPA Contract No.  68-02-3177,  Assignment  No. 4
                          MRI Project No.  4862-L(4)

                       Date Prepared:  August 31, 1982


                                   
-------
                                  Abstract
      Open dust aources in the iron and steel industry vere estimated  to
 •nit 88,800 tons/year suspended particulate in 1978 based on a 10 plant
 survey. Of this,70,  13, and 122 were emitted by vehicular traffic on
 unpaved roads, vehicular traffic on paved roads, and storage pile wind
 erosion, respectively.  Emission measurements, utilizing the exposure  R
 profile technique, indicate a 17% solution of a petroleum resin (Coherex )
 in water on an unpaved road reduced heavy-duty vehicle emissions by
 95.71 for total particulate, 94.5Z for particulate <15um,and 94.IX for
 particulate <2.Sum (averaged over the first 48 hours after application).
 Plain water reduced emissions 951 for all particle sizes half an hour a/ter
 application. Four hours later, efficiency of watering had dropped to  552
 (total), 49.6% (<15pm),and 61.1Z (<2.5un). Coherex  on an unpaved road
 travelled by light-duty vehicles reduced emissions by 99.5%  (total),
 98.61 (<15pm),and 97.4% (<2.5wtt),25 hours after application.  Control
 efficiency decayed to S3.7Z (total), 91.41 (<15v»),«nd 93.7Z  (<2.5um),
 51 hours after application.

      On paved roads, vacuum sweeping reduced emissions 69.82  (total),
 50.92 (<15wm), and 49.22 (<2.5pm), 2.8 hours after vacuuming.  F«Aiy
 minutes after water flushing, emissions were reduced by 54.12  (total),
 48.82 (<15um), and 68.12 (<2.5um).  Combined flushing and broom oveaping
 reduced emissions by 69.32  (total), 78.02  (<15vjm), and 71.82  (<2.5wm), 40
 minutes after application.

      Control of emissions from coal storage piles varied from  902 to
 almost zero depending on the type of treatment, length of time since
 treatment was applied,and     windspeed.  Tests were performed using  a
 portable wind tunnel.

      Relationships were developed to determine relative cost  effectiveness
 „<• r.~r,^ cn.f-r? eMssIon controls.
I,S. Envlronmonta!  Protection

-------
                                  PREFACE


     This report was prepared by Midwest Research Institute for the Environ-
mental Protection Agency's Industrial Environmental Research Laboratory under
EPA Contract No. 68-02-3177,  Work Assignment No. 4.  Mr. Robert McCrillis
was the project officer.  The report was prepared in Midwest Research Insti-
tute's Air  Quality Assessment Section  (Dr.  Chatten Cowherd,  Head).   The
authors  of this  report  were Mr. Thomas  Cuscino, Jr.,  task  leader,
Dr. Gregory E.  Mules Id, and Dr. Chatten Cowherd.  Exposure profiling was con-
ducted in the  field under the direction of  Dr.  Mark Small  and Mr. Russel
Bohn with assistance from Mr. Frank Pendleton, Mr. David Griffin, Mr. Steve
Cummins,  Ms. Julia  Poythress, Mr. Stan Christ  and Mr.  Pat Reider.   Wind
tunnel testing  was  directed by Mr. Russel Bohn and Dr. Gregory Muleski.
Approved for:

MIDWEST RESEARCH INSTITUTE
M. P. Schrag, Director
Environmental Systems Department
August 31, 1982
                      _ _	* . _
                                    m

-------
                                 CONTENTS
Preface	,	iii

     Summary and Conclusions 	   xi
     1.0  Introduction 	    1
          1.1  Variables Affecting Control  Efficiency.  .  	    3
          1.2  Project Objectives	    6
          1.3  Report Structure	    6
     2.0  Selection of Sources, Sampling Methods, Sites
            and Control Techniques 	    7
          2.1  Survey of Open Dust Sources  and Controls	    7
          2.2  Selection of Test Sites	   13
          2.3  Open Dust Sampling Methods	   13
     3.0  Source Testing by Exposure Profiling 	   19
          3.1  Quality Assurance 	   19
          3.2  Air Sampling Techniques and  Equipment 	   22
          3.3  Particulate Sample Handling  and Analysis	   24
          3.4  Aggregate Material Sampling  and Analysis	   38
          3.5  Results for Vehicular Traffic on Unpaved Roads.  ...   40
          3.6  Results for Vehicular Traffic on Paved Roads	   57
          3.7  Comparison of Predicted and  Actual Uncontrolled
                 Emissions	   70
     4.0  Wind Erosion Testing by Portable  Wind Tunnel	   81
          4.1  Quality Assurance 	   81
          4.2  Air Sampling Technique and Equipment	   81
          4.3  Particulate Sample Handling  and Analysis	   83
          4.4  Aggregate Material Sampling  and Analysis	   91
          4.5  Results for Wind Erosion of  Coal Piles	   92
     5.0  Open Dust Control Design, Operation and
            Cost Parameters	105
          5.1  Design/Operation Parameters  	  .....  105
          5.2  Cost Parameters	105
          5.3  Theoretical Cost-Effectiveness Analysis  	  105
     ^.O  References	*	7	12?/>.r
     8.0  Glossary	-429-/*>
     8.0  English to Metric Unit Conversion Table	-133-/ 3/

     Appendices
          A.   Data Compilation from Materials Handling Flow Charts .   A-l
          B.   Example Open Dust Source Control  Survey Questionnaire.   B-l
          C.   Miscellaneous Design/Operation and Cost Data	C-l

-------
                                  FIGURES
Number
 1-1      Effect of vehicle speed, weight, and traffic density
            on control performance 	    5

 3-1      Map of plant F showing test sites	   20

 3-2      Map of plant B showing test sites	   21

 3-3      MRI exposure profiler	   23

 3-4      Equipment deployment for Runs F-27 through F-35	   25

 3-5      Equipment deployment for Runs F-36 through F-45
            and F-58 through F-74	   26

 3-6      Equipment deployment for Runs B-50 through B-60	   27

 3-7      Decay in control efficiency of watering on unpaved
            road under heavy-duty traffic	   53

 4-1      MRI portable wind tunnel	   82

 4-2      Equipment deployment for wind tunnel tests at plant F.  .  .   84

 4-3      Test site locations at plant H	   85

 4-4      Sampling pan detail	   86

 4-5      Decay in control efficiency of latex binder applied
            to coal storage piles	104

 5-1      Graphical presentation of open dust control costs	113

-------
                                  TABLES
Number                                                                Page

 1-1      Open Dust Emission Factors Experimentally Determined
            by MRI	    2

 1-2      Summary of Potential Open Dust Source Control
            Techniques 	    3

 2-1      Aggregate Materials Handled at Iron and Steel Plants
            in 1978	   10

 2-2      1978 Inventory of Open Dust Source Contributions to
            Suspended Particulate Emissions	   12

 2-3      Summary of Fugitive Emission Controls Used From 1978
            to Present (by plant)	   14

 3-1      Quality Control Procedures for Sampling Media	   28

 3-2      Quality Control Procedures for Sampling Flow Rates ....   29

 3-3      Quality Control Procedures for Sampling Equipment	   30

 3-4      Criteria for Suspending or Terminating an Exposure
            Profiling Test	   31

 3-5      Moisture Analysis Procedures 	   39

 3-6      Silt Analysis Procedures	   41

 3-7      Exposure Profiling Test Site Parameters	   42
                t
 3-8      Plume Sampling Data for Heavy-Duty Vehicles on
            Unpaved Roads	   44

 3-9      Particulate Concentration Measurements for Heavy-
            Duty Traffic on Unpaved Roads	   46

 3-10     Aerodynamic Particle Size Data - Heavy-Duty Traffic
            on Unpaved Roads	   47

 3-11     Isoldnetic Correction Parameters for Heavy-Duty
            Traffic on Unpaved Roads 	   48
                                    vn

-------
                            TABLES (Continued)


Number                                                                Page

 3-12     Vehicular Traffic Data and Emission Factors for
            Heavy-Duth Traffic on Unpaved Roads	   49

 3-13     Normalized Emission Factors for Heavy-Duty Traffic
            on Unpaved Roads	   51

 3-14     Control Efficiencies for Heavy-Outy Traffic on
            Unpaved Roads	   52

 3-15     Plume Sampling Data for Light-Duty Traffic on
            Unpaved Roads	   54

 3-16     Particulate Concentration Measurements for Light-
            Duty Traffic on Unpaved Roads	   56

 3-17     Aerodynamic Particle Size Data - Light-Duty
            Traffic on Unpaved Roads 	   58

 3-18     Isokinetic Correction Parameters for Light-
            Duty Traffic on Unpaved Roads	   59

 3-19     Vehicular Traffic Data and Emission Factors for
            Light-Duty Traffic on Unpaved Roads	   60

 3-20     Normalized Emission Factors for Light-Duty Traffic
            on Unpaved Roads	   61

 3-21     Control Efficiencies of Coherex for Light-Duty
            Traffic on Unpaved Roads 	   62

 3-22     Plume  Sampling Data for Paved Roads	   65

 3-23     Particulate Concentration Measurements for Paved
            Roads	   69

 3-24     Aerodynamic Particle Size Data - Paved Roads	   71

 3-25     Isokinetic Correction  Parameters for Paved Roads  	   72

 3-26     Road Surface Characteristics and Emission  Factors
            for  Paved Roads	   73

 3-27     Normalized  Emission Factors for Vehicular  Traffic
            on Paved  Roads	    74

 3-28     Control  Efficiencies'for  Paved  Roads	    75

 3-29     Predicted Versus  Actual  Emissions  (Unpaved Roads)	    77

                                    viii

-------
                            TABLES (Concluded)


Number                                                                Page

 3-30     Predicted Versus Actual Emissions (Paved Roads). .....   78

 4-1      Quality Control Procedures for Sampling Flow Rates ....   87

 4-2      Wind Erosion Test Site Parameters	   93

 4-3      Wind Erosion Sampling Parameters 	   94

 4-4      Threshold Velocities for Wind Erosion	   95

 4-5      Aerodynamic Particle Size Data - Wind Erosion	   96

 4-6      Properties of Surfaces Tested	  .   98

 4-7      Wind Erosion Test Results	   99

 4-8      Erosion Potentials for Coal	101

 4-9      Twenty-Minute Emission Rates for Cambria Coking
            Coal	102

 4-10     Control Efficiencies for Wind Erosion of Coal
            Storage Piles	103


 5-1      Design/Operation Parameters - Paved Roads	106

 5-2      Design/Operation Parameters - Unpaved Roads	  106

 5-3      Design/Operation Parameters - Unpaved Parking Lots
            and Exposed Areas	107

 5-4      Design/Operation Parameters—Storage Piles 	  108

 5-5      Summary of Open Dust Control Cost Data	109

 5-6      Open Dust Control Cost Comparison in Dollars Per
            Unit of Treated Source Extent	110

 5-7      Open Dust Control Cost Comparison in Dollars Per
            Unit of Actual Source Extent	Ill

-------
                                  Notice


                  This document is a preli:.. '.nc/ry draft.
                 It has not been formally released by T~"
                 .should not at this stage be cc;\ctru- ". -
                 represent Agency policy. Ioi£".:-3ir  cl
                 lated for  conr.nent on its tc;'-:tl.  "   ,cu
                 and poli " y i-rf<~ li "     "• = -
                          SUMMARY AND CONCLUSIONS
     The purpose of this study was to measure the control efficiency of vari-
ous techniques used to mitigate emissions from open dust sources  in the iron
and steel industry, such as vehicular traffic on unpaved and paved roads and
wind erosion  of  storage piles and exposed  areas.   The control  efficiency
was determined not only for  total  particulate  (TP),  but also  for inhalable
particulate (IP)--particles  less  than 15 urn in aerodynamic diameter,  and
for fine  particulate  (FP)—-particles  less than  2.5  urn in aerodynamic  diam-
eter.    In addition to control efficiency measurement, parameters defining
control design, operation, and cost were quantified.

     The methodology for achieving the above goals involved the measurement
of uncontrolled and controlled emission factors for emissions from vehicular
traffic on unpaved roads, vehicular traffic on paved  roads, and storage pile
wind erosion.  These  sources were selected based on an open dust source
emission  inventory for  the iron and steel  industry which showed  the above
three  sources  to  contribute  70.4%, 12.7%,  and 11.5%,  respectively, of the
88,800 T/yr of suspended particulate emitted by the  industry.

     The  exposure  profiling  method developed by MRI  was the technique  uti-
lized to measure uncontrolled and coatrolled emission  factors from vehicular
traffic on paved and unpaved roads.  Exposure profiling  of roadway emissions
involves  direct  isokinetic measurement of  the  total  passage  of open  dust
emissions approximately 5  m  downwind of the edge of the road by means of
simultaneous  sampling at four to five points  distributed vertically  over
the effective  height  of the  dust plume.  Size distributions were measured
at the  1 and  3 m  heights downwind  utilizing cyclone precollectors followed
by parallel  slot  cascade impactors.   During selected tests, size selective
inlets mounted on  high  volume samplers were also deployed downwind.

     Nineteen tests of  controlled and uncontrolled emissions from vehicular
traffic on unpaved roads were performed.  Ten tests were of heavy-duty traf-
fic  (greater  than 30 tons) and 9  were  of  light-duty  traffic  (less than
3 tons).

     In calculating the  efficiency of a control technique from emission fac-
tor measurements collected during controlled and uncontrolled tests, the ef-
fect of testing during  different periods in the lifetime of the control was
taken  into account.  The decay of control efficiency  with time after appli-
cation  has a number of  causes, such as track-on from  surrounding  integrated
surfaces and mechanical   abrasion of the treated road  surface.   Accordingly,
each value of control efficiency contained  in this report includes the time
after application  that  the measurement was  taken.

     Two  control  techniques  utilized to reduce emissions  from heavy-duty
traffic  on  unpaved roads were tested:   (1) a  17% solution  of Coherex® in
water  applied  at  an intensity of  0.86 £/m2 (0.19 gal/yd2), and (2) water

                                     xi

-------
applied at an intensity of 0.59 £/m2 (0.13 gal/yd2).  The control efficiency
for Coherex®, at  the  above application intensity, averaged over the first
48 hr after  application, was 95.7%  for TP, 94.5%  for  IP,  and  94.1%  for  FP.
The control efficiency for watering at the above application intensity, 4.4 hr
after application, was  55.0%  for TP, 49.6% for IP, and 61.1% for FP.  The
control efficiency of watering at the above application intensity was above
95% for all particle sizes 1/2 hr after application.

     Only one control  technique for emissions from light-duty vehicles trav-
elling on unpaved roads was tested.   The control measure was a 17% solution
of Coherex® in water at an application intensity of 0.86 £/m2 (0.19 gal/yd2).
The control efficiency of Coherex® at the above application intensity, 25 hr
after application, was  99.5% for TP,  98.6% for  IP,  and  97.4%  for FP.   This
road had  been closed  to traffic  for a day.   Fifty-one hours after applica-
tion, these  efficiencies  had  decayed to 93.7%  for  TP,  91.4% for IP, and
93.7% for FP.

     Three control techniques for mitigation of emissions from vehicles trav-
elling on paved roads were tested:   (1) vacuum sweeping,  (2) water flushing,
and  (3)  flushing  with broom sweeping.  The highest  measured values  for the
control  efficiency of vacuum  sweeping,  occurring 2.8 hr  after  vacuuming,
were 69.8%  for  TP, 50.9% for IP, and 49.2% for  FP.  The control  efficiency
for water  flushing  at 2.2 2/m2 (0.48 gal/yd2), approximately 40 min after
application, was 54.1%  for TP, 48.8% for IP, and 68.1%  for FP.  The control
efficiency for flushing and broom sweeping approximately  40 min after appli-
cation with water applied at 2.2 2/m2 (0.48 gal/yd2), was 69.3% for TP, 78.0%
for IP, and 71.8% for FP.

     Earlier MRI studies of open dust sources in the  iron and steel industry
produced  data bases  which were used to develop predictive emission factor
equations.  The precision factors associated with the paved and  unpaved road
equations were 2.20 and 1.48, respectively.  When the results of  the 18 tests
of  uncontrolled  particulate emissions from vehicular  traffic  on roads  per-
formed during this study were added to the data bases,  the precision factors
increased to 3.95 and 1.98, respectively.  These  increases indicate the need
for possible refinement of the paved  and unpaved  road equations  based on the
larger data  bases now available.

     The  portable wind  tunnel  method was  the technique  utilized to  measure
uncontrolled and controlled emission  factors from storage pile wind erosion.
The  wind tunnel  method  involves  the measurement of the  amount of emissions
eroded from  a given surface under a known wind  speed.   MRI's  portable open-
floored  wind tunnel was placed directly on the  surface  to be  tested and the
tunnel wind  flow  adjusted to predetermined center!ine speeds.  The  emissions
eroded  from the surface were measured isokinetically at  a single point in
the  sampling section  of the tunnel  with  a sampling train consisting of a
tapered  probe,  cyclone  precollector,  parallel slot  cascade impactor, backup
filter,  and  high  volume sampler.

     Wind erosion from storage piles was quantified during 29 tests of un-
controlled  and  controlled emission  factors.  Nearly  all  of the  tests  were
conducted on coal surfaces with  two control  techniques  being  studied  separ-
ately:   (1) a  17% solution of Coherex® in water applied at an intensity of

                                     xi i

-------
3.4 £/m2 (0.74 gal/yd2), and (2) a 2.8% solution of Dow Chemical M-167 Latex
Binder in water applied at an average  intensity of  6.8 £/m2  (1.5  gal/yd2).
The control  efficiency of Coherex® applied at the above intensity to an un-
disturbed steam coal surface approximately 60 days before the test, under a
wind of 15.0 m/s  (33.8 mph) at  15.2 cm (6  in.) above  the  ground,  was 89..6%
for TP and approximately 62% for  IP and FP.  The  control  efficiency of the
latex binder on a low volatility coking coal 2 days after application, under
a 14.3 m/s (32.0  mph) wind  speed at 15.2 cm (6 in.) above the ground, was
37.0% for TP and near zero for IP and FP.   However, when the wind speed was
increased to 17.2 m/s (38.5 mph), the control efficiency increased to 90.0%
for TP, 68.8% for IP, and 14.7% for FP.  The efficiency under the same wind
speed, 17.2 m/s,  decayed 4  days after application  to 43.2%  for TP, 48.1%
for IP, and 30.4% for FP.

     Three iron and steel  plants were surveyed to determine open source emis-
sion control design,  operation  and cost parameters.  Design and operation
parameters included application intensity, application frequency, life expec-
tancy, applicator equipment manufacturer,  normal  operating speed, capacity,
fuel consumption, vehicle weight,  number and capacity of  nozzles  at a spe-
cified pressure,  and  maintenance problems.   Cost data included operating,
maintenance and capital investment costs.   The operating  and maintenance
costs were further subdivided into labor,  gasoline and oil, maintenance and
repair, and depreciation costs.   The capital investment costs included pur-
chase and installation of primary and ancillary equipment.

     The conclusions gleaned from this study are as follows:

     1.   Open dust emissions from the entire integrated iron and steel
          industry for 1978 were estimated at 88,800 T/yr of suspended
          particulate.  The total can be subdivided into the following
          general categories:

          Category                                    Percent Contribution

     Vehicular traffic on unpaved roads                      70.4
     Wind erosion                                            15.0
     Vehicular traffic on paved roads                        12.7
     Continuous raw material handling operations              1.6
     Batch raw material  handling operations                   0.3

     2.   A decay in control efficiency with time after application was
          measured for most control techniques tested.  This means that
          a reported efficiency value has meaning only when given in
          conjunction with a time after a specified application.

     3.   There is some indication that, soon after application of some
          control measures, control efficiency varies as a function of
          particle size, with the efficiency decreasing with decreasing
          particle size.  However, in time this difference disappears
          and the control  efficiency then shows no dependence on particle
          size.
                                   xiii

-------
4.    Wind erosion from the coarse aggregate storage piles tested and ob-
     served at iron and steel plants is probably much less than previously
     thought.   Testing has shown that for typical storage pile surfaces,
     10 m wind speeds in excess of 14.8 m/s (33.2 mph) are necessary for
     wind erosion to even begin.  Also, crusts on piles and exposed sur-
     faces are very effective inhibitors of wind erosion as long as the
     crust remains unbroken.   Current thinking suggests that the major
     wind erosion problem is expected to exist on uncrusted areas sur-
     rounding the piles, on uncrusted exposed areas and on unpaved roads
     and uncrusted shoulders.  Also, piles which have dozer or scraper
     traffic on them (atypical in the iron and steel industry) are sus-
     ceptible to wind erosion.  Finally, as would be expected, uncrusted
     piles of fine, dry material are also susceptible to wind erosion.

5.    The control efficiency of the latex binder tested for effectiveness
     in reducing wind erosion increased with increasing wind speeds.  It
     is possible that this may apply to other wind erosion dust supres-
     sants and to a broader range of wind speeds than those tested, but
     the data are still too sparse to support that inference.

6.    The optimal  cost-effective  technique for applying open dust con-
     trols is  to  make the application and then reapply only after the
     initial application has decayed to zero control efficiency.  How-
     ever, this will yield only about 50% control efficiency, assuming
     the technique  started at 100%.   In  controlled emissions trading
     (such as offsets, banking and bubbles), much more than 50% reduc-
     tion in open dust source emissions may be needed.  Thus, optimiza-
     tion of cost-effectiveness in the control of open dust source emis-
     sions must always be considered in the context of a minimally ac-
     ceptable level of control.

     There  is  no clear-cut definition of  "best"  control  strategy for
     open dust source emissions.  Two possible definitions are:

     a.   That strategy which achieves the constraint of an acceptable
          level of emissions reduction at the least cost; and

     b.   That  strategy  which achieves the minimally acceptable level oi
          control and is the  least expensive per unit mass of emissions 0
          reduced.
     Although  the  cost of (b) cannot be less than that of (a),Ai£ may
     indeed prove to be more desirable in the long term because greater
     offsets  are possible and thus  represents  the  most efficient use
     of funds  possible.

-------
7.   Evaluation of the emission reduction effectiveness of an open  dust




     source control measure requires the acquisition of detailed performance




     data on the control measure.  The performance data gathered to date




     on open dust sources in the iron and steel industry has focused on




     the efficiencies of freshly applied control measures for given sets




     of application parameters.  Additional field test would be required




     to determine the long term efficiency decay.








8.   As with the initial control efficiency, the decay rate of a control




     measure should depend in part on the application parameters.   Also,




     there may be a residual effect of previous control applications




     which changes the shape of the decay of curve, although this residual




     effect may become less important after repeated reapplication-decay




     cycles. Theoretically, a mathematical relationship could be developed




     which expresses mean control efficiency (during the period between




     applications) as a function of the application parameters and  the




     frequency of application once a sufficiently large emissions data




     base has been obtained.









9.   A likely effectiveness parameter for an unpaved road treated with a




     chemical binder is the surface silt loading.   This parameter, which




     appears in the emission factor equation for paved roads, is a




     measure of the dust  entrainment potential of a paved road.   Limited




     measurements of loadings on chemically treated unpaved roads shows




     that the loadings correlate with controlled emissions.

-------
10.  The current open source emissions data base is quite limited compared




     to that for process sources.  Predicted emissions for open sources




     are thus subject to a greater uncertainty, perhaps as high as a




     factor of 2 or 3 compared to +50 percent for process sources.  This




     level of uncertainty leads to corresponding levels of uncertainty




     when implementing emissions trading policies.  There are several




     parameters affecting the overall efficiency of open source emission




     control technology.  Taking unpaved roads as an example, the frequency




     of application and the application rate, or intensity, of the




     chemical suppressant are of paramount importance.  The current data




     base does not include control efficiency decay measurements for any




     suppressant at even one set of these parameters.  This situation




     obviously leads to large uncertainties in any emission trade.

-------
                             1.0  INTRODUCTION


     Previous studies of  open  dust participate emissions from integrated
iron and steel plants have provided strong evidence that open dust sources
such as vehicular  traffic on unpaved and paved roads, aggregate material
handling,  and wind erosion should  occupy a prime position in control stra-
tegy development.1'2   These conclusions were based on comparability between
industry-wide uncontrolled emissions  from  open dust sources and typically
controlled fugitive emissions from major process sources  such as steel-making
furnaces,  blast furnaces, coke  ovens, and sinter machines.  Moreover, pre-
liminary cost-effectiveness  analysis  of promising control options for open
dust sources  indicated  that  control  of open dust sources might result in
significantly improved  air quality at a lower cost in relation to control
of process sources.  Cost-effectiveness is defined as dollars expended per
unit mass  of particulate emissions prevented by control.   These preliminary
conclusions warranted the gathering of more definitive data on control  per-
formance and costs for open dust sources in the steel  industry.

     The cost reduction potential  of  open dust  sources has  not been missed
by the  iron  and steel industry.  With the advent of the Bubble Policy (Al-
ternative  Emissions Reduction Options) on December 11, 1979, (revised April 7,
1982) the  industry has  recognized the economics of controlling open dust
sources as compared to  implementing more costly controls on stack and pro-
cess fugitive sources of  particulate  emissions.  However, as a requirement
of the Bubble Policy,  it must be demonstrated that no net gain in emissions
occurs from an imaginary bubble surrounding the plant.

     In order to  demonstrate that there is  no  net gain in  emissions as a
result of  a  proposed  controlled trading scenario,  the controlled emission
rate for an open dust source must be estimated using the  following equation:

                         R = Me(l-C)/2,000

where:     R = mass emission rate (tons/year)
          M = annual  source extent
          e = uncontrolled emission factor,  i.e.,  pounds  of uncontrolled
                emissions per unit of source extent
          C = overall  control efficiency expressed as a fraction.

Values for the uncontrolled emission factor (e) can be calculated using the
predictive emission factor equations  shown in Table 1-1.   These predictive
equations  are the outcomes of numerous prior MRI field tests.1'-2'3'4'5   Pa-
rameters which may affect particulate emission levels from open sources such
as moisture and silt  contents of the emitting material or equipment charac-
teristics  were identified and measured during the  testing process.   For those
sources wtth a sufficient number of tests,  multiple linear regression formed
the basis  upon which  significant variables were identified and then used in
developing the predictive equation.

-------
                      TABLE  1-1.   OPEN  DUST EMISSION  FACTORS  EXPERIMENTALLY DETERMINED BY  flRI

1.

2.



1



/|


5.


6.



7



n





Source category
Unpaved roads

Paved roads



Batch load- in (e ci front-
end loader, rallcar dump)



stacker, transfer station)

Active storage pile mainte-
nance and traffic


Active storage pile wind
erosion



end loader, railcar dump)








Measure of extent
Vehicle-miles traveled

Vehicle-miles traveled




loaded in



loaded in

Tons of material put
through storage


Tons of material put
through storage



loaded out




land



Emission factor3
(Ib/unit of source extent)
so (* \ Is \ fW\°-7 /w\°-B d
5'9 \W \W \3/ UJ 3T3

0.09 1 («) (4,) (rJjH,,) (S)0'7
\N7 Vlu/ \ I,UOu7 \ 3;


ooolg (1) (S) (S)
. 2 0-3.1
M M
\ Tfi \ r i
»2' to/

„ oolfl (I) (5) do)
2
/MV
(9
°-10K (o) (A)


0 05 IIT-) iTi^r) (tr) (!mi
M.b/ \?3j/ Vlb/ \907


/S\ /U\ /h\
0001P is) U; (s)
2 o..Tn
/M\ / V\
(5) (BY)

3100 &)&)&)

2
(P-E\
\5rj /




s
S

w
L

II

M


Y
K
d
t


h


D
e
P-E

N

I

w
h
Correction parameters
= Silt content of aggregate or road
surface material (%)
= Average vehicle speed (mph)

= Average vehicle weight (tons)
= Surface dust loading on traveled
portion of road (Ib/mile)
= Mean wind speed at 4 m above
ground (mph)
= Unbound moisture content of
aggregate or road surfarp
material (%)
= Dumping device capacity (yd3)
= Activily factorb
= Number of dry days per year
= Percentage of time wind speed ex-
ceeds 12 mph at 1 ft above ground

= Percentage of time unobstructed wind
speed exceeds 12 mph at mean pile
height
= Duration of material storage (days)
= Surface erodibility (tons/acre/year)
= Thorn thwaite's Precipitation-
Evaporation Index
- Number of active travel lanes

- Industrial road augmentation
factor
= Average number of vehicle wheels
= Drop height (ft)
a  Represents particulate smaller than 30 |im in diameter based on particle density of 2.5 g/cm1.

b  Equals  1.0 for front-end loader maintaining pile tidiness  and 50 round trips  of customer trucks  per day in the storage area.

c  *  Equals 7.0 for trucks coming from unpaved to paved roads and releasing dust from vehicle underbodies;
   *  Equals 3.5 when 20% of the vehicles are forced to travel temporarily with  one set of wheels on an unpaved road berm while passing on narrow
        roads;
   *  Equals 1.0 for tr?ffic entirely on paved surfaces.

-------
     The annual source  extent can be estimated  by  plant management from
plant records  and discussions with operating  personnel.   The  variable  with
the least accurate  data to support an estimate of controlled emissions is
the control efficiency.   Table  1-2  presents a summary of open dust source
controls that are or have been used in the iron and steel industry.  Control
efficiency values are  needed  for all the  techniques  shown  in Table 1-2.

   TABLE 1-2.   SUMMARY OF POTENTIAL OPEN DUST SOURCE CONTROL TECHNIQUES
          Source
      Control technique
I.    Unpaved roads and parking lots.
II.   Paved roads and parking lots.
III.  Material handling and storage
        pile wind erosion.

IV.   Conveyor transfer stations.
V.    Exposed area wind erosion.
A.   Watering
B.   Chemical treatment6
C.   Paving
D.   Oiling

A.   Sweeping
    1.  Broom
        a.  Wet
        b.  Dry
    2.  Vacuum
B.   Flushing

A.   Watering
B.   Chemical treatment11

A.   Enclosures
B.   Water sprays
C.   Chemical sprays

A.   Watering
B.   Chemical treatment'
C.   Vegetation
D.   Oiling
   For example:  (1) salts, (2) lignin sulfonates, (3) petroleum resins,
     (4) wetting agents, and (5) latex binders.

1.1  VARIABLES AFFECTING CONTROL EFFICIENCY

     Open dust source control efficiency values can be affected by four broad
categories of variables:  (a) time-related variables, (b) control application
variables, (c) equipment characteristics, and  (d) characteristics of surface
to be treated.

-------
1.1.1  Time-Related Variables

     Because of the finite durability of all surface-treatment control tech-
niques, ranging from hours (watering) to years (paving), it is essential to
tie an efficiency  value  to a frequency of  application  (or maintenance).
For measures of lengthy durability, the maintenance program required to sus-
tain control effectiveness  should  be indicated.   One likely pitfall to be
avoided is  the  use of field data  on a  freshly applied  control measure  to
represent the lifetime of the measure.

     The climate,  for the most part, accelerates the decay of control per-
formance adversely through weathering.  For  example,  freeze-thaw cycles
break up the crust formed by binding agents; precipitation washes away water-
soluble chemical  treatments like  lignin sulfonates, and  solar  radiation
dries out watered  surfaces.   On  the other hand,  light precipitation might
improve the  efficiency of  water  extenders and hygroscopic chemicals  like
calcium chloride,  and will  definitely  improve efficiency  of  watering.

1.1.2  Control  Application Variables

     The control application  variables  affecting  control  performance are:
(a) application  intensity;  (b) application  frequency;  (c) dilution ratio;
and (d) application procedure.  Application  intensity is the volume of solu-
tion placed on the surface per unit area of  surface.  The higher the inten-
sity, the better the  expected control efficiency.   However, this  relation-
ship applies only to a point, because too intense an application will begin
to run off the surface.   The point where runoff occurs depends on the slope
and porosity of the surface.

1.1.3  Equipment Characteristics

     The equipment  characteristics  that affect control  efficiency  values
are those involved in imparting  energy to the treated surface which might
break the adhesive bonds  keeping fine participate composing the surface from
becoming airborne.  For  example,  vehicle weight and speed can affect the
control efficiency for chemical  treatment of unpaved roads.  An increase in
either variable  serves to  accelerate the decay in efficiency.   Figure 1-1
is a general plot portraying the change in rate of decay of the control  ef-
ficiency for a  chemical  suppressant applied to an unpaved road as a func-
tion of vehicle speed, weight, and traffic volume.

1.1.4  Characteristics of Surface to be Treated

     Any surface characteristics which contribute to the breaking of a sur-
face crust  will  affect the control  efficiency.  For example, for unpaved
road controls,  road structure characteristics affect control efficiency.6
These characteristics are:  (a) combined subgrade and base bearing strength;
(b) amount  of fine material (silt  and clay)  on the surface of the road; and
(c)  the  friability of the road surface material.   Unacceptable values for
these  variables  mainly affect'the performance of  chemical controls.   Low
bearing strength causes  the road  to flex  and  rut in spots  with the  passage

-------
                                                Increasing Vehicle
                                                Speed, Weight, and
                                                Traffic Density
Figure 1-1
                    Time After Application
Effect of vehicle  speed, weight, and traffic  density
  on control performance.

-------
of heavy trucks; this destroys the compacted surface enhanced by the chemi-
cal treatment.   A lack of fine material in the wearing surface deprives the
chemical treatment  of  the increased particle  surface  area  necessary for
interparticle bonding.   Finally, the larger particles  of a  friable wearing
surface material simply break up under the weight of the vehicles and cover
the treated road with a layer of untreated dust.

1.2  PROJECT OBJECTIVES

     The overall objective  of this  project was to provide  data  that will
document quantities  of particulates generated from  controlled  open dust
sources at  steel plants  and the cost-effectiveness  of control procedures
for eliminating  or  reducing emissions.  The  separate  tasks necessary to
achieve the above objective were:

     1.   Conduct field tests to measure emissions from open dust
          sources in order to determine the efficiency of selected
          control procedures.

     2.   Evaluate data obtained in the test program in order to
          determine the change in efficiency over time.

     3.   Develop design and operating information on all control
          procedures evaluated, including optimum operating proce-
          dures; operator and material  requirements; design param-
          eters; capital, operating and maintenance costs;  and
          energy requirements.

1.3  REPORT STRUCTURE

     This report is  structured as  follows:   (a)  Section 2.0  contains  the
results of  a 10-plant  survey to determine the extent of open dust sources
and controls in  the iron and steel  industry; (b) Section 3.0 contains the
methodology and  results  of  source testing  via exposure profiling;  (c)  Sec-
tion 4.0 contains the  methodology and  result  of wind erosion  testing  via a
portable wind tunnel;  (d) Section 5.0 contains the  presentation of  cost,
design, and  operating  information  related to  control  techniques;  and  (e)
Sections 6.0 through 9.0 present additional research needs, references, glos-
sary and English to metric conversion units,  respectively.

     This report contains both metric and English units.   In the text, most
numbers are  reported in  metric units with  English  units in parentheses.
For numbers  commonly expressed in metric  units in the  air pollution  field,
no English equivalent  is given, i.e., particle size  is in urn, density is in
g/cro3,  and concentration is  in ug/m3.

     Numbers in this report  are generally rounded to three  significant fig-
ures;  therefore, columns of numbers  may not add  to  the exact  total  listed.
Rounding to three significant  figures produces a  rounding error  of less than
0.5%.

-------
                2.0  SELECTION OF SOURCES, SAMPLING METHODS,
                        SITES AND CONTROL TECHNIQUES


     In order to select the control techniques that should be tested, a sur-
vey was conducted  to ascertain the  most  important  open  dust  sources  as  de-
termined by their uncontrolled emission rates.  The survey was also designed
to determine the  control  techniques typically applied to these sources at
iron and steel  plants.   Finally,  surveyed plants utilizing the most typical
control techniques for the most important sources were selected as candidate
test sites.

2.1  SURVEY OF OPEN DUST SOURCES AND CONTROLS

     In order to  calculate an open dust emissions inventory and determine
what control techniques were being utilized in the iron and steel industry,
a survey of 10 plants  was  conducted.   The survey was  conducted  using mate-
rials handling flow charts to be completed by each plant.

     The flow charts displayed  several alternate handling schemes for the
following materials:

     1.  Coal
     2.  Iron ore pellets
     3.  Unagglomerated iron ore
     4.  Limestone/dolomite
     5.  Sinter,  nodules, and briquettes
     6.  Coke
     7.  Sinter input  (flux, iron ore, and coke fines)
     8.  Slag

     The completed  flow  charts  for a  specific plant  provided information
on:   (a) the materials handling routes used at the plant; (b) the amount of
material passing  through  each handling step; (c) physical characteristics
of the  handling  equipment (e.g.,  bucket size, drop height, etc.); and (d)
the handling steps  that  are controlled and  the type  of control  utilized.

     Through the assistance of the American Iron and Steel Institute (Mr.  John
Barker, Chairman  of the AISI  Fugitive  Emissions Committee, and  Mr. William
Benzer), the following companies  agreed  to complete the materials handling
flow charts for the indicated plants:

     Armco  Steel, Incorporated
          Middletown Works
          Houston Works

     Inter!ake,  Incorporated
          Chicago Plant (coke ovens and blast furnace)
          Works  at Riverdale (BOFs)

-------
     Bethlehem Steel Corporation
          Burns Harbor-
          Sparrows Point

     National Steel Corporation
          River Rouge Plant (coke ovens and blast furnaces)
          Works at Ecorse (BOFs and EAFs)

     U.S. Steel Corporation
          Geneva Works
          Gary Works

     Jones and Laugh!in Steel Corporation
          Aliquippa Works
          Indiana Harbor Works

Appendix A presents  materials  handling data compiled from the  charts  for
the above 10  plants (Inter!ake's Chicago plant and the works at Riverdale
are counted  as one  complete  facility,  National's  River  Rouge  Plant  and the
works at Ecorse are treated as one facility).

2.1.1  Updated Emissions Inventory

     The completed materials handling flow charts for the 10 plants provided
input data for an industry-wide emissions inventory of open dust sources.
An initial inventory was  developed in Reference 2  and  is  updated in this
report using  the  most current emission factors (Table 1-1) as well  as re-
vised (1978)  source extent data obtained from the 10-plant survey.   Details
of the inventory calculations are given in the following paragraphs.

2.1.1.1  Vehicular Traffic on Unpaved Surfaces-
     Emission factors  for  light, medium,  and  heavy  duty traffic on  unpaved
roads were calculated using the predictive equation  shown in Table 1-1.
Since the 4-plant survey report in Reference 2 contained more detailed traf-
fic data  than the 10-plant  survey  described in  Section  2.1, the values for
the correction parameters in the predictive emission factor equation as well
as the values for the source extent were calculated from the 4-plant survey.
Finally, it was assumed that there were 50 major plants in the nation, each
producing the emission rate calculated for the average plant.

     The emission  factor  for storage pile maintenance and related traffic
was developed  from the emission factors calculated in the 4-plant survey.
Separate weighted  emission  factors were determined for pellets and coal.
The weighted  emission factors were multiplied by the 1978 nationwide  ton-
nages of these materials received at iron and steel plants in order to cal-
culate the emission  rate.  Finally, the calculated emission rate for pellets
and coal was  linearly scaled by the weight ratio of all aggregate materials
handled  to the sum of coal  and pellets handled.   In this manner, the  total
nationwide emission rate  for pile  maintenance and other traffic associated
with storage  of all  aggregate material was calculated.

     An  emission  factor for vehicular traffic on unpaved parking lots was
calculated using  the  unpaved road equation in Table 1-1.  The following as-
sumptions were made  regarding  correction parameters and  source extent:
                                  8

-------
     1.   The 449,200 employees of the iron and steel industry involved with
the sale and production of iron and steel products in 1978 drive to work.

     2.   An average of two people travel in each car.

     3.   Each person works 250 days/year.

     4.   Fifty percent of cars use unpaved parking lots.

     5.   Cars travel an average of 200 ft in and 200 ft out of lots each day.

     6.   Cars travel at an average speed of 10 mph.

     7.   Silt content of unpaved parking lots aggregate = 12%.

2.1.1.2  Vehicular Traffic on Paved Roads—
     The emission  factor  for paved roads was calculated as the average of
eight tests  performed by MRI  at  iron  and steel plants.2  The  emission fac-
tor was  then multiplied by the average source extent (vehicle-miles  trav-
eled) calculated  from the  4-plant survey.  Finally, the emission rate for
paved road  traffic at  the average plant was multiplied  by  50 in  order to
extrapolate to nationwide emissions.

2.1.1.3  Batch and Continuous Drop Operations--
     The following average  values obtained from the  10-plant survey  were
used in  calculating emissions from batch and  continuous drop operations:

     1.   Sixty-five  percent  of the raw  aggregate  received  at the average
plant arrives by barge and 35% by rail.

     2.   The  35%  arriving  by rail is  unloaded in  100 ton batches and is
dropped an equivalent of 5 exposed feet.

     3.   Of  the  65% arriving by barge, half is batch unloaded by a 12 yd3
clamshell and dropped 24 ft, while half is continuously unloaded and  dropped
10 ft.

     4.   The average raw and  intermediate aggregate material passes through
seven transfer stations in its lifetime at the average iron and steel plant
and is dropped each time an average of 8 ft.

     5.   Eighty percent of the raw and waste material handled in iron and
steel plants is stored  in open piles.

     6.   Of  the  80% stored in the open,  50% is loaded  into  the  pile by
stacker, 25% by clamshell, and 5% by truck or scraper.

     7.   During  load-in of material  to  an  open  storage  pile,  the average
12 yd3 clamshell  drops  material  30 ft; the average stacker drops material
13 ft; and the average 35 ton capacity haul truck  or scraper drops material
5 ft.

-------
     8.   Of the  80% stored in the open, 35%  is  loaded  out  of  the  pile  by
clamshell,  30% by bucket-wheel, 10% by  front-end loader,  and 5%  by miscel-
laneous  techniques.

     9.   During load-out of material  from an open storage pile, the average
10 yd3 clamshell drops material 5 ft; the average bucket-wheel drops  mate-
rial 10 ft; and  the average 10 yd3  front-end  loader drops  material 5 ft.
     10.   The average plant with OHF or BOF shops produces most  of  its  own
coke and sinter and sends most of it directly to the blast furnace  without
open storage.

     The two aggregates  selected  as representative of all aggregate mate-
rials were coal and iron-bearing pellets.  These particular materials were
selected because:   (a)  they  include about 50% of the total  aggregate han-
dled at iron and steel  plants, and  (b) more data are available on the silt
and moisture of these  materials  than other aggregate materials  stored  in
iron and steel  plants.

     Silt and moisture  measurements obtained during the 4-plant  survey  and
during past MRI emission factor testing efforts were averaged in an attempt
to obtain representative nationwide values.   For coal,  the average silt and
moisture percentages were 5.0  and 4.8, respectively;  and for pellets, the
average silt  and  moisture percentages  were 4.9 and  2.1, respectively.

     Based on the  above assumptions and the average silt and moisture values,
1978 nationwide emission rates for coal and pellet batch and continuous drop
sources were calculated.  The  sum of these emission rates was then scaled
linearly by the weight  ratio  of total  aggregate placed in open storage to
the sum of coal  and pellets  handled.  (The amounts  of each material  handled
in 1978 are  shown  in  Table  21.)   In this fashion,  the emission rates for
total aggregate batch drop and continuous drop  operations were calculated.

            TABLE  2-1.   AGGREGATE  MATERIALS HANDLED AT IRON AND
                          STEEL PLANTS IN 1978
     Material
Aggregate type
Consumption in 1978
    (106 tons)
Coal
Pellets
Natural iron ore
Flux
Sinter
Coke
Slag
Raw
Raw
Raw
Raw
Intermediate
Intermediate
Waste
67.5
86.9
14.4
28.7
35.6
55.6
43.8
Source:  1978 Annual Statistics of the American Iron and Steel Institute.
                                  10

-------
2.1.1.4  Wind Erosion--
     The emission factors  for wind erosion  from pellet  and  coal piles were
calculated using the storage pile wind  erosion equation in  Table  1-1.  Jhe
correction parameters were obtained from both the 10-plant and the previous
4-plant surveys.

     The emission rates for coal and pellets were calculated by multiplying
the emission  factors by the 1978 nationwide  amounts  of coal and pellets
handled at iron and steel plants.  The total emission rate for wind erosion
from all raw  and waste aggregate piles was calculated by linearly scaling
the sum of  the emission rates for coal and pellets by the weight ratio of
the total raw and  waste aggregate handled to the sum of the coal  and pel-
lets handled.

     The emission factor for wind erosion of bare areas was calculated as a
weighted average of the emission factors  for  two of the four previous sur-
veyed plants reported in Reference 2.  These two plants were most represen-
tative of the climate experienced by the majority of the industry.  The plant
emission factors were weighted by source extent (acres exposed).

     The emission rate  for the  average  plant  was calculated by  multiplying
the weighted  average emission  factor by the arithmetic average source ex-
tent observed at the four previously surveyed plants.   Finally, the nation-
wide emission  rate  was  obtained by multiplying the emission rate for the
average plant by 50, which is the number of major plants estimated to exist
in the country.

2.1.1.5   Emissions Inventory Summary—
     The updated inventory, shown in Table 2-2, yields a source ranking simi-
lar to the inventory published earlier.2  Vehicular traffic on unpaved sur-
faces accounts  for 70%  of  the total  open  dust source  emissions  while batch
and continuous  drop operations  combine for less than  2%  of the  total.

     The data  base  on  the field performance  of control  measures  for open
dust sources  is small.   Therefore,  control measure testing should be dis-
tributed in relation to the magnitude of uncontrolled emissions.  According
to  Table 2-2,  testing   should  focus  on control measures applicable to:

               Unpaved  roads;
               Paved roads;
               Storage  pile maintenance;
               Storage  pile wind erosion;
               Exposed  area wind erosion;
               Unpaved  parking lots; and
               Conveyor transfer stations.

2.1.2  Summary of Current  Industry Control Practices

     Analysis of the materials handling flow charts for the 10 surveyed inte-
grated  iron and steel  plants indicate that a number of control techniques
were being applied in 1978 to open dust sources at several  locations.  These
                                  11

-------
        TABLE 2-2.  1978 INVENTORY OF OPEN DUST SOURCE CONTRIBUTIONS TO SUSPENDED PARTICULATE EMISSIONS
                                                    1978 Nationwide suspended
                                                    particulate emission rate
                                                    for the iron and steel  in-
                                                       dustry uncontrolled8              Percent of
               Source                                       (tons/yr)                 total emissions


   Vehicular traffic on unpaved surfaces                                                    70.4
     Unpaved roads                                           50,100
     Storage pile maintenance                                10,800
     Unpaved parking lots                                     1,600

   Vehicular traffic on paved surfaces                       11,300                         12.7

   Batch drop operations                                                                     0.3
     Barge unloading by clamshell                                75
     Railcar unloading                                           11
     Storage pile load-in by clamshell                          107
     Storage pile load-in by truck/scraper                        3
     Storage pile load-out by clamshell                           25
     Storage pile load-out by front-end  loader                    8

   Continuous drop operations                                                                1.6
     Barge unloading by bucket ladder or self unloader           48
     Conveyor transfer stations                               1,220
     Storage pile load-in by stacker                            117
     Storage pile load-out by bucket wheels                       53

   Wind erosion                                                                             15.0
     Storage piles                                           10,200
     Exposed areas                                            3 110
                                                             88,800
a  Except that natural control due to precipitation  is  included.

-------
are summarized in Table 2-3 along with control data gathered from other in-
formation sources.  Table  2-3  is  by no means  a complete  industry  survey,
but is a  complete summary of 10  of the approximately  50  major  integrated
plants in the country.

2.2  SELECTION OF TEST SITES

     Tables 2-2  and 2-3  formed the basis for test site selection by indi-
cating the largest open dust sources in the industry, the control techniques
in use, and some of the sites where these techniques are applied.

     It was decided to test unpaved and paved road control techniques (first
and second  largest sources)  at Armco's Middletown  and  Houston Works, since
many different techniques were available for testing at each site.   Armco's
Middletown and Bethlehem's Burns Harbor Plants were selected for testing of
controls for the third largest source, wind erosion.

     Testing at  Armco's  Middletown plant was  especially desirable  since  it
afforded the opportunity to  test  before and after  the  implementation of  an
extensive open dust source control program proposed under the Bubble Policy.
These controls were completely implemented by August 1980.

2.3  OPEN DUST SAMPLING METHODS

     Open dust  emissions are especially difficult to characterize for the
following reasons:

     1.  Emission rates  have a high degree of temporal variability.

     2.  Emissions are discharged from a wide variety  of  source configura-
tions.

     3.  Emissions are comprised  of a wide range of  particle size,  includ-
ing  coarse  particles  which  deposit  immediately  adjacent to the source.

     The scheme  for quantification of emission factors must effectively deal
with these  complications,  to yield  source-specific emission data needed  to
evaluate the priorities  for emission control  and the effectiveness of control
measures.

     Four basic  techniques have been utilized in testing open dust sources:

          1.  The upwind/downwind method involves measurement of concentra-
tions  upwind and downwind of the source,  utilizing  ground-based samplers
(usually hi-vol  samplers)  under known meteorological conditions.  Atmospheric
dispersion equations are used to back-calculate the emission rate which most
nearly produces  the measured concentrations.

          2.  MRI's exposure profiling  method involves direct measurement
of the total passage  of  open dust source emissions immediately  downwind  of
the source  by  means of simultaneous multipoint sampling over the effective-
cross-section of the  open  dust  source emission plume.  This technique  uses


                                  13

-------
            TABLE 2-3.   SUMMARY OF FUGITIVE EMISSION CONTROLS USED FROM 1978 TO PRESENT (BY PLANT)
          Source
Control practice
             Plant(s)
I.     Unpaved roads
II.    Paved roads
III.   Storage pile (maintenance
        and wind erosion)
IV.    Unpaved parking lots
A.  Watering

B.  Oiling



C.  Chemical dust suppressants

D.  Paving

A.  Flushing


B.  Wet broom sweeping

C.  Vacuum sweeping

A.  Watering
B.   Chemical sprays


A.   Paving

B.   Chemical dust suppressants
Armco - Houston Works

1.  National Steel - Granite City
      Steel Div.
2.  J&L Steel - Aliquippa Works

Armco - Middletown Works

Armco - Middletown Works

1.  Armco - Middletown Works
2.  Armco - Houston Works

Armco - Houston Works

Armco - Middletown Works

1.  Armco - Houston Works
2.  Bethlehem Steel - Burns Harbor
3.  U.S. Steel - Gary Works
4.  U.S. Steel - Geneva Works
5.  Armco - Middletown Works

1.  Bethlehem Steel - Burns Harbor
2.  National Steel - Great Lakes Div.

Armco - Middletown Works

Armco - Middletown Works

-------
                                            TABLE 2-3.   (concluded)
          Source
Control practice
Plant(s)
V.     Conveyor transfer stations    A.   Enclosures
                                    B.   Water sprays




                                    C.   Chemical sprays

VI.   Exposed area wind erosion     Vegetation
                                      1.   Armco - Middletown Works
                                      2.   Bethlehem Steel - Burns Harbor
                                      3.   Interlake Steel - Chicago
                                      4.   J&L Steel - Aliquippa Works
                                      5.   U.S. Steel - Geneva Works

                                      1.   Armco-Middletown Works
                                      2.   Bethlehem Steel - Burns Harbor
                                      3.   U.S. Steel - Geneva Works
                                      4.   Armco - Houston Works

                                      Bethlehem Steel - Sparrows Point

                                      Armco - Middletown Works

-------
a mass-balance  calculation  scheme  similar to EPA Method 5 rather than re-
quiring indirect calculation through the application of a generalized atmo-
spheric dispersion model.   Moreover,  based on MRI  field  tests  of  several
types of  open dust sources,  the  accuracy  of measurements  obtained  by  expo-
sure profiling is better than that achievable by the upwind/downwind method,
even with site-specific calibration of the dispersion model used in the lat-
ter method.

          3.  The tracer method  involves  the  controlled release of  a  known
amount of tracer  (e.g., SF6) at  the source.   Downwind  from the  source, the
tracer concentration  as well as  the dust  concentration from the source are
measured via colocated samplers.   Finally, the open dust source emission rate
is calculated using the following relationship:

          ER  _ C
          _E ~ _£
          ERt   Ct

where:     ER  = Particulate emission rate

          ER.  = Tracer emission rate
            i*
          C   = Particulate concentration

          C.  = Tracer concentration


The use of tracers is complicated by two factors:  (1) it is difficult to dis-
perse the tracer such that its  initial spread matches that of the open dust
source, and (2) the tracer is normally a gas or a fine particulate which does
not have  the  settling characteristics of the dust  from  the  open source.

     4.   The wind tunnel method for measuring wind erosion emission involves
the generation  of a  known wind speed and the measurement of the amount of
emissions blown from  a  given surface.  A  portable wind tunnel which can be
utilized to measure wind erosion emissions j_n situ is  preferable to collect-
ing a sample of the surface in  the field and conducting the experiment in a
laboratory wind tunnel.  The second technique creates  the problem that the
surface is  never  reconstructed in exactly the same  fashion as  it exists in
the field.  For example, a  surface crust which may  exist  in the field will
be almost completely destroyed  in the collection process,  making it impossible
to reconstruct in the laboratory.

     Several of the available fugitive emission factors for integrated iron
and steel plants  have resulted from estimation techniques rather than mea-
surement techniques.   Estimating techniques include:  (a)  use of fixed per-
cent of uncontrolled  stack  emissions;  (b) application  of  data  from  similar
processes; (c) engineering calculations; and (d) visual correlation of opa-
city and mass emissions.  Wide  use of estimating techniques has been employed
because of the difficulty of testing and the lack of recognized standardized
methods for measuring open dust emissons.

     The most suitable and accurate technique for quantifying open dust sour-
ces (materials  handling,  vehicular  traffic on unpaved roads,  etc.) in the
iron and steel industry has been shown to be exposure profiling.1  The method
is source-specific and its increased accuracy over the upwind/downwind method

                                  16

-------
and the tracer method is a result of the fact that emission factor calcula-
tion is based  on  direct measurement of the variable sought, i.e., mass of
emissions per unit time.

     For testing of  wind  erosion the portable wind tunnel method is MRI's
preferred technique  because  it  allows for j_n  situ measurement of erosion
rates under predetermined, controlled wind conditions.   In contrast to this,
the upwind/downwind method is beset with difficulties for wind erosion test-
ing because  the onset  of  natural erosion and  its intensity is beyond  the
control of the investigator; moreover when natural erosion is  occurring, in-
terference caused by erosion of  sources  located upwind of the test  sources
causes problems of background interference.   The main drawbacks of the por-
table wind tunnel method  are:   (a) that wind tunnel  turbulence is used to
simulate atmospheric turbulence; and (b) that subsequent development of emis-
sion factors requires independently determined patterns of wind flow around
typical storage pile shapes.  With  regard to the  first drawback, Gillette7
(after whose work the  MRI wind tunnel was designed) pointed out that  the
scale of vertical  motions  of the natural atmosphere and the wind tunnel are
similar near the critical  interface between the wind and the erodible surface,
making the wind tunnel  a useful  device for the study of wind erosion.  More-
over, relative to  the second drawback, physical modeling studies (e.g., Soo
et al.8) are underway to define storage pile wind flow patterns.
                                  17

-------
                 3.0  SOURCE TESTING BY EXPOSURE PROFILING
     This section describes  the  field testing program  using  the  exposure
profiling method to  determine  control efficiencies for open dust sources.
The following  field  tests  were performed at two integrated iron and steel
plants -  Armco's Middletown Works  (designated  as  Plant F)  and Armco's
Houston Works (designated as Plant B):

          Eleven tests of vehicular traffic on uncontrolled paved roads.

          Twelve tests of vehicular traffic on controlled paved roads.

          Four tests of light-duty vehicular traffic on uncontrolled un-
          paved roads.

          Five tests of light-duty vehicular traffic on controlled unpaved
          roads.

          Three tests of heavy-duty vehicular traffic on uncontrolled un-
          paved roads.

          Seven tests of heavy-duty vehicular traffic on controlled unpaved
          roads.


     Maps of plants F and B are shown in Figures 3-1 and 3-2, respectively,
and indicate the sites of the exposure profiling tests conducted.

3.1  QUALITY ASSURANCE

     The  sampling and analysis procedures followed in  this  field testing
program were  subject to certain quality  control  (QC)  guidelines.   These
guidelines will  be  discussed in conjunction with  the  activities  to which
they apply.   These procedures met or exceeded the requirements specified in
the reports entitled  "Quality Assurance Handbook for Air Pollution Measure-
ment Systems, Volume  II - Ambient Air Specific Methods" (EPA 600/4-77-027a)
and "Ambient Monitoring Guidelines for Prevention of Significant Deteriora-
tion" (EPA 450/2-78-019).

     As part  of the QC program for this study, routine audits of sampling
and analysis  procedures  were performed.   The purpose of the audits was to
demonstrate that measurements were made within acceptable control  conditions
for particulate source sampling and to assess the source testing data for pre-
cision and accuracy.  Examples of items audited include gravimetric analysis,
                                 19

-------
                                                                                                                        !L
Legend:
— •	J Jbw Piivcd Kouds
      Paved i
-------
ro
                         Mold and
                         Storage
                         Building
                          0    100   200 fee I
                                    Figure 3-2.   Map of plant  B  showing  test sites.

-------
flow rate calibration, data processing,  and emission factor and control ef-
ficiency calculation.  The  mandatory  use  of specially designed reporting
forms for sampling  and  analysis  data obtained in the field and laboratory
aided in the  auditing procedure.   Further detail on specific sampling and
analysis procedures are provided  in the  following sections.

3.2  AIR SAMPLING TECHNIQUES AND  EQUIPMENT

     The exposure profiling  technique utilized in this study  is based on
the isokinetic profiling concept that is  used  in conventional  source test-
ing.  The passage of  airborne pollutant immediately downwind of the source
is measured directly  by means of simultaneous  multipoint sampling over the
effective cross section of the open dust source plume.   This technique uses
a mass-balance calculation  scheme  similar to  EPA Method 5  stack  testing
rather than requiring indirect calculation through the application of a gen-
eralized atmospheric dispersion model.

     For measurement  of nonbuoyant open dust  source emissions, profiling
sampling heads are distributed over a vertical  network positioned  just down-
wind (usually about 5 m) from the source.   A vertical  line  grid of samplers
is sufficient for measurement of  emissions from line or moving point sources
while a two-dimensional array of  samplers  is required for quantification of
area source emissions.

     The MRI exposure profiler, developed  under EPA Contract No.  68-02-0619
as. reported in Reference 4, was used in  this study.   The profiler  (Figure 3-3)
consists of a portable tower (4 to 6 m height) supporting an array of sampling
heads.   During testing, each sampling head was  operated as an isokinetic
exposure sampler directing  passage of the flow  stream through a settling
chamber and then upward through a standard 20.3 cm by 25.4  cm (8 in.  by 10 in.)
glass fiber filter  positioned  horizontally.  Sampling  intakes  were pointed
into the wind, and sampling velocity of each  intake was adjusted  to match
the local mean wind speed,  as determined  by 15  min averages prior to  and
during the test.   Throughout each test,  wind speed was monitored by record-
ing anemometers at two heights, and the  vertical wind speed profile was de-
termined by assuming a logarithmic distribution.

     High volume parallel  slot cascade impactors with 34 m3/hr (20 cfm) flow
controllers were used to measure particle size distribution at two heights
along side of the exposure profiler.  The  impactor units were equipped with
a cyclone preseparator to remove  coarse  particles which otherwise  would tend
to  bounce off the  glass fiber impaction substrates, causing fine  particle
measurement bias.   To further reduce particle bounce problems, each stage
of  the  impactor  substrates  was sprayed with a stopcock grease solution.
The  stages  then  had  a sticky surface  which  inhibited particle bounce.

     Two other types  of equipment were used during  this  study:   (1) the
standard high  volume  (hi-vol) air  sampler and (2)  the  recently developed
EPA version of the  size selective  inlet (SSI)  mounted on an otherwise stand-
ard  high  volume  air  sampler. .The  standard  high-volume sampler measures
total suspended particulate matter  (TSP) which consists of particles smaller
than approximately  30 Mm in aerodynamic diameter.  When fitted with an SSI,


                                 22

-------
Figure 3-3.  MRI exposure profiler.
           23

-------
the high-volume air sampler measures  inhalable particulate  (IP) concentra-
tions consisting of particles  smaller than 15 urn in aerodynamic diameter.

     Three equipment deployment  schemes  shown in Figures 3-4 through 3-6
were employed during the course of this study.  The basic downwind equipment
included an  exposure profiling system with either  four  or  five sampling
heads spaced 1 m  (3.28  ft)  apart and high-volume cascade impactors fitted
with cyclone preseparators at  1  m  (3.28 ft) and  3 m (9.84 ft) heights.   In
addition, a  standard high-volume air sampler was operated  at a height of
2 m (6.56 ft).   The upwind  air sampling equipment consisted of a standard
high-volume  air sampler at a height  of 2 m (6.56  ft) and either one or two
hi-vols  fitted with SSIs,  operated at 2 m (6.56  ft) or  1 m (3.28  ft) and
3 m (9.84 ft),  respectively.

3.3  PARTICULATE SAMPLE HANDLING AND ANALYSIS

3.3.1  Preparation of Sample Collection Media

     Particulate samples were  collected  on Type A slotted glass fiber im-
pactor substrates and on Type AE glass fiber filters.  To minimize the prob-
lem of particle  bounce,  all  glass fiber cascade  impactor substrates were
greased.   The grease solution  was  prepared by dissolving 140 g of  stopcock
grease in 1  liter  of  reagent grade toluene.   No grease was applied to the
borders  and  backs  of  the  substrates.  The substrates were handled, trans-
ported and stored  in specially designed frames which protected the greased
surfaces.

     Prior to the initial  weighing, the greased substrates and filters were
equilibrated for 24 hr  at  constant temperature and  humidity in a  special
weighing room.   During weighing, the balance was checked at frequent inter-
vals with standard weights to  assure  accuracy.   The substrates and filters
remained in  the same controlled  environment for  another  24  hr, after which
a second analyst  reweighed  them as a precision  check.   If  a substrate or
filter could not pass audit limits, the entire lot was reweighed.   Ten per-
cent of  the  substrates  and filters taken to the  field were  used as blanks.
The quality  assurance  guidelines pertaining to preparation of sample col-
lection  media are presented in Table 3-1.

3.3.2  Pre-Test Procedures/Evaluation of Sampling Conditions

     Prior to equipment deployment,  a number of decisions were made as to
the potential for  acceptable source testing  conditions.  These decisions
were based on forecast information obtained from the local U.S.  Weather Ser-
vice office.   A specific sampling location was identified based on the pre-
dicted wind  direction.   Sampling was not planned if there was a high proba-
bility of measurable precipitation.
                                 24

-------
ro
                                                                         A Standard HiVol
                                                                         O HiVol with SSI
                                                                         O HiVol with Cyclone/lmpactor
                                                                         Q- Profiler Head
                                     Figure  3-4.   Equipment deployment for Runs  F-27
                                                    through  F-35.

-------
ro
en
                                                                         A Standard HiVol
                                                                         O HiVol with SSI
                                                                         O HiVol with Cyclone/lmpactor
                                                                         Q- Profiler Head
                                   Figure 3-5.   Equipment deployment for JJuns  F-36  through
                                                  F-45  and F-58 through F-74.

-------
ro
                                                                         A Standard H\Vo\
                                                                         O HWol with SSI
                                                                         O HiVol with Cyclone/lmpacror
                                                                         Q- Profiler Head
                                   Figure 3-6.  Equipment  deployment for Runs B-50
                                                  through  B-60.

-------
         TABLE 3-1.   QUALITY CONTROL PROCEDURES FOR SAMPLING MEDIA
Activity
     QC Check/Requirement
Preparation


Conditioning
Weighing
Auditing of weights
Correction for handling
  effects
Calibration of balance
Inspect and imprint glass fiber media with
identification numbers.

Equilibrate media for 24 hr in clean con-
trolled room with relative humidity of less
than 50% (variation of less than ± 5%) and
with temperature between 20 C and 25 C
(variation of less than ± 3%).

Weigh hi-vol filters and impactor substrates
to nearest 0.1 mg.

Independently verify final weights of 10% of
hi-vol filters and impactor substrates (at least
four from each batch).   Reweigh batch if
weights of any hi-vol filters or impactor
substrates deviate by more than ± 2.0 mg and
± 1.0 mg, respectively.  For tare weights,
follow the above procedures in a 100% audit.
Reweigh batch if tare weight of any hi-vol
filters or impactor substrates deviate by
more than ±1.0 mg, and ±0.5 mg, respec-
tively.

Weigh and handle at least one blank for each
1 to 10 hi-vol filters or impactor substrates
of each type for each test.

Balance to be calibrated once per year by
certified manufacturer's representative.
Check prior to each use with laboratory
Class S weights.
                                 28

-------
     If conditions were  considered  acceptable,  the sampling equipment was
transported to the site, and deployment was initiated.  The deployment pro-
cedure normally took 1 to 2 hr to complete.  During this time, the sampling
flow rates were set for  the various air  sampling  instruments.  The quality
control guidelines governing this activity are found in Table 3-2.

      TABLE 3-2.   QUALITY CONTROL PROCEDURES FOR SAMPLING FLOW RATES
Activity
     QC Check/Requirement
Calibration
  •   Profilers, hi-vols, and
       impactors
Single-point checks
  •   Profilers, hi-vols, and
       impactors
     Alternative
Orifice calibration
Calibrate flows in operating ranges using
calibration orifice upon arrival and every
2 weeks thereafter at each regional site
prior to testing.
Check 25% of units with rotameter, calibra-
tion orifice, or electronic calibrator once
at each site prior to testing (different
units each time).   If any flows deviate by
more than 7%, check all other units of
same type and recalibrate noncomplying
units.   (See alternative below.)

If flows cannot be checked at test site,
check all units every 2 weeks and recali-
brate units which deviate by more than 7%.

Calibrate against displaced volume test
meter annually.
     Once the source testing equipment was set up and the filters inserted,
air sampling commenced.   Information was recorded on specially designed re-
porting forms for quality assurance and included:

     a.   Exposure profiler - Start/stop times, wind speed profiles
          and sampler flow rates (15 min average), and wind direc-
          tion relative to the roadway perpendicular (15 min average).

     b.   Other samplers - Start/stop times and flow rates.

     c.   Traffic count by vehicle type and speed.

     d.   General meteorology - Wind speed, wind direction, and
          temperature.
                                 29

-------
     From the  information  in  (a), adjustments could be made to  insure  iso-
kinetic sampling of  both  profiler heads (by changing the intake velocity)
and cyclone preseparators (by changing intake nozzles).   Table 3-3 outlines
the pertinent QC procedures.

      TABLE 3-3.  QUALITY CONTROL PROCEDURES FOR SAMPLING EQUIPMENT
Activity
     QC Check/Requirements
Maintenance
  •   All samplers
Operation
  •   Timing
     Isokinetic sampling
       (profilers only)
     Prevention of static
       mode deposition
Check motors, gaskets, timers, and flow
measuring devices at each regional site
prior to testing.
Start and stop all samplers during time
spans not exceeding 1 min.

Adjust sampling intake orientation when-
ever mean (15 min average) wind direction
changes by more than 30°.

Adjust intake velocity whenever mean
(15 min average) wind speed approaching
sampler changes by more than 20%.

Cap sampler inlets prior to and immedi-
ately after sampling.
     Sampling time was  long  enough  to provide sufficient particulate mass
and to average over several  units of cyclic fluctuation in the emission rate
(e.g., vehicle passes on an unpaved road).  Sampling lasted from 13 min to
over 5 hr depending on the source and control  measure (if any).   Occasionally,
sampling was  interrupted  due  to  occurrence of unacceptable meteorological
conditions and then restarted when suitable conditions  returned.   Table 3-4
presents the  criteria used  for suspending or terminating  a  source test.

3.3.3  Sample Handling and Analysis

     To prevent particulate losses,  the exposed media were carefully trans-
ferred at the  end  of each run to protective containers within the MRI in-
strument van.  In the field laboratory, exposed filters were placed in indi-
vidual glassine  envelopes and  numbered file folders.   Impactor  substrates
were  replaced  in the protective  frames.   Particulate that  collected on the
interior surfaces  of  exposure  probes  and cyclone preseparators  was rinsed
with  distilled water  into  separate  sample jars which were then  capped and
taped shut.
                                 30

-------
      TABLE 3-4.   CRITERIA FOR SUSPENDING OR TERMINATING AN EXPOSURE
                              PROFILING TEST
A test may be suspended or terminated if:a

1.   Rainfall ensues during equipment setup or when sampling is in progress.

2.   Mean wind speed during sampling moves outside the 1.8 to 8.9 m/s (4 to
      20 mph) acceptable range for more than 20% of the sampling time.

3.   The angle between mean wind direction and the perpendicular to the path
      of the moving point source during sampling exceeds 45° for more than
       20% of the sampling time.

4.   Mean wind direction during sampling shifts by more than 30° from pro-
      filer intake direction.

5.   Mean wind speed approaching profiler sampling intake is less than 80%
      or greater than 120% of intake speed.

6.   Daylight is insufficient for safe equipment operation.

7.   Source condition deviates from predetermined criteria (e.g., occurrence
      of truck spill).
   "Mean" denotes a 15-min average.

     When exposed  substrates  and filters (and the associated blanks) were
returned to  the  MRI  laboratory,  they were equilibrated  under  the  same  con-
ditions as the  initial  weighing.  After reweighing,  10%  were audited to
check weighing accuracy.

     To determine the sample weight of particulate collected on the interior
surfaces of  samplers,  the entire wash solution was passed through a 47 mm
Buchner type funnel holding a glass fiber filter under suction.  This water
was passed through the  Buchner  funnel  ensuring  collection  of  all  suspended
material on  the  47 mm filter which was then dried in an oven at 100°C for
24 hr.  After drying,  the filters  were conditioned  at constant  temperature
and humidity for 24 hr.

     All wash filters  were weighed with a  100% audit of tared and a 10%
audit of exposed filters.   Blank values  were determined by washing  "clean"
(unexposed)  settling  chambers in the field  and  following  the  above  proced-
ures.
                                 31

-------
3.3.4-  Emission Factor Calculation Procedures

     To calculate emission rates  using the exposure profiling technique, a
conservation of mass approach was used.   The passage of airborne particulate,
i.e., the quantity of emissions per unit of source activity, is  obtained by
spatial integration of distributed measurements of exposure (mass/area) over
the effective  cross  section  of the plume.   Exposure is the point value of
the flux  (mass/area-time) of airborne particulate integrated over the  time
of measurement.  The steps in the calculation procedure are described below.
Finally, the following  definitions  for  particulate matter will  be used in
this report:

          TP   Total airborne particulate matter.
                                                                        i
          TSP  Total suspended particulate matter, as  measured by a
               standard high-volume (hi-vol)  sampler.

          IP   Inhalable particulate matter consisting of particles
               smaller than 15 urn in aerodynamic diameter.

          FP   Fine particulate matter consisting of particles
               smaller than 2.5 (jm in aerodynamic diameter.

3.3.4.1  Particulate Concentrations—
     The concentration of particulate matter measured  by a sampler is given
by:

                              C = 103 ^


where:     C = particulate concentration  (ug/m3)
          m = particulate sample weight  (mg)
          Q = sampler flow rate (mVmin)
          t = duration of sampling (min)

     The specific particulate  matter concentrations were determined from
the various particulate catches as follows:

          Size range                Particulate catches

             TP                Profiler  filter and intake catches or
                                 cyclone, impactor substrate,  and backup
                                 filter  catches

             TSP               Hi-Vol filter catch

             IP                SSI filter catch

             FP                Impactor  substrate and  backup filter
                               catches
                                 32

-------
To be consistent  with  the National Ambient Air Quality Standard for TSP,
all concentrations  and flow rates were expressed  in  standard conditions
(25°C and 101 kPa or 77°F and 29.92 in Hg).

3.3.4.2  Isokinetic Flow Ratio--
     The isokinetic flow ratio (IFR) is the ratio of a directional  sampler's in-
ake air speed to the mean wind speed approaching the sampler.   It is given by:
where:    Q = sampler flow rate (mVmin)
          a = intake area of sampler (m2)
          U = mean wind speed at height of sampler (m/min)

This  ratio  is of  interest in the sampling of TP,  since isokinetic sampling
assures that particles of all sizes are sampled without bias.   In this study,
profilers  and  cyclone preseparators were the  directional  samplers  used.

      If it was necessary to sample at a superisokinetic flow rate (IFR > 1.0),
to obtain sufficient sample under light wind conditions,  the following mul-
tiplicative factors were used  to correct measured exposures and concentra-
tions to corresponding isokinetic values:

                                  Small particles   Large particles
                                    (d < 5 pm)          (d > 50 urn)

      Exposure Multiplier               1/IFR                1
      Concentration Multiplier          I                   IFR

A separate  IFR  is calculated for each profiler head based on the measured
values of Q and U.

     These correction factors for nonisokinetic TP concentrations are based
on a  theoretical  relationship  developed by Davies.9  The  relationship as
applied  to  exposure profiling in the  ambient  atmosphere is as follows:

                          l - _i_   (1/IFR) -1
                            ~
                              __
                          Ct~  IFR     4Y + 1
where
     Cn = Nonisokinetic concentration of particles of diameter d

     Ct = True concentration of particles of diameter d

      Y = Inertia! impaction parameter = d2 c (p  - p) U/18u D
      D = Diameter of probe

      d = Diameter of particle

      p = Density of air

      u = Viscosity of air

     p  = Density of particle

      c = Cunningham correction factor
                                 33

-------
From Davies1  equation, it is clear that,  for very small  d,  C  = C., and that,
for large values of d, C  = Ct/IFR.   These observations  lead to tne simpli-
fied correction factors presented in the  above table.

     A more rigorous  value  for the average ratio (R) of nonisokinetic to
true concentration can be found by  integrating the product of the  particle
size distribution and Davies1  relationship over all possible particle dia-
meters.   An isokinetically  corrected  concentration  can  then be calculated
as


                                 Ct = Cn/"R

Using a  log-normal distribution  of particle diameters,  the isokinetically
corrected concentrations obtained  by  the R-method and by MRI's simplified
multiplicative correction factor method  are  within 20%  of one another for
IFR values between 0.2 and 1.5.  Only 8%  of the IFR values  reported in this
study lie outside of this range.

     Using the simplified MRI approach for a particle-size distribution con-
taining a mixture of small,  intermediate, and large particles,  the isokinetic
correction factor is an average of the above factors weighted by the relative
proportion of large and small particles.   For example, if the mass of small
particles in the distribution equals twice the mass of the large particles,
the weighted isokinetic correction for exposure would be:

                              (1 + 2/IFR)/3

Because the particle-size distribution and the isokinetic corrections are
interrelated,  isckinetic corrections  are of  an iterative nature.   In the
present study, two iterations were employed.

3.3.4.3  Downwind Particle-Size Distributions--
     Particle-size distributions were determined  from a cascade  impactor
using the proper 50% cutoff diameters for the cyclone precollector and each
impaction stage.  These data were fitted  to a log-normal mass size distribu-
tion after correction  for  particle bounce.  The distributions obtained at
two heights in  the source plume were  then  used to determine  the mass  frac-
tions corresponding to various particle-size ranges as a function of height.
The IP and  FP mass fractions were  assumed to vary linearly with height.

     The technique used in this study to  correct for the effects of particle
bounce has been  discussed in  earlier  MRI  studies.1'2  Simultaneous  cascade
impactor measurements of airborne particle-size distribution with and with-
out a cyclone precollector  indicate that the  cyclone  precollector is  some-
what effective  in  reducing  fine particle measurement bias.   However, even
with the  cyclone precollector, a monotonic decrease in  collected particle
weight on each  successive impaction stage  is  frequently followed  by a sev-
eral-fold increase in weight collected on the back-up filter.  But, because
the assumed value  (0.2 urn)  for the effective cutoff diameter of the glass
fiber back-up filter fits the progression of cutoff diameters for the impac-
tion stages,  the weight collected on the back-up filter should be consistent
with the  decreasing  pattern shown  by the weight collected on the impactor


                                 34

-------
stages.   The excess participate on the back-up filter is postulated to con-
sist of coarse particles that penetrated the cyclone (with small probability)
and bounced through the impactor.   Although particle bounce is further reduced
by greasing impaction substrates,  it is not completely eliminated.

     To correct  the measured particle  size  distribution  for the  effects  of
residual particle bounce, the following procedure was used:

     1.    The calibrated cutoff diameter  for the cyclone  preseparator  is
used to fix the upper end of the particle-size distribution.

     2.    The lower end  of  the particle size distribution is fixed by the
cutoff diameter of the last stage and the corrected mass fraction associated
with this stage.   The corrected fraction collected on the back-up filter is
calculated as the  average  of the fractions  measured on  the two  preceding
stages.

     Using the above procedure, mass is effectively removed from the back-up
filter.   However,  because  no  clear procedure existed for apportioning the
excess mass back onto the impaction stages, the size distribution determined
from tests with particle bounce problems was constructed using the log-normal
assumption and two  points—the mass fraction collected in the cyclone and
the corrected mass fraction collected on the back-up filter.

3.3.4.4  Particulate Exposures and Profile Integration—
     For directional  samplers  operated isokinetically, total particulate
exposures are calculated by:

                         E = 10"  x CUt

where:    E = total particulate exposure (mg/cm2)
          C = net TP concentration ((jg/m3)
          U = approaching wind speed (m/s)
          t = duration of sampling (s)

     The exposure values vary over the height of the plume.  If exposure is
integrated over  the height of  the plume,  then the quantity obtained repre-
sents the  total  passage  of airborne particulate matter  due to the source
per unit length of the line source.   This quantity is called the integrated
exposure A and is found by:
                               H
                         A = J
                             0
                       E dh
wnere:
A = integrated exposure (m-mg/cm2)
E = particulate exposure (mg/cm2)
h = vertical distance coordinate (m)
H = effective extent of plume above ground
                                                     (m)
                                 35

-------
The effective  height  of the plume is found by linear extrapolation of the
uppermost net TP concentrations to a value of zero.

     Because exposures are measured at discrete heights of the plume, a nu-
merical integration is  necessary  to 'determine A.   The exposure must equal
zero at the vertical extremes of the profile, i.e., at the ground where the
wind velocity  equals  zero and at the effective height of  the  plume where
the net concentration equals zero.  However, the maximum TP exposure usually
occurs below a height of 1 m, so that there is a sharp decay in TP exposure
near the ground.   To account for this sharp decay, the value of exposure  at
the ground level  is set equal to the value at a height of 1 m.   The integra-
tion is then performed using Simpson's rule.

3.3.4.5  Particulate Emission Rates--
     The emission rate for total airborne particulate generated by vehicular
traffic on a straight road  segment  expressed  in grams of emissions per ve-
hicle-kilometer-traveled (VKT) is given by:

                         . - in* {}


where:     e = total particulate emission rate (g/VKT)
          A = integrated exposure (m-mg/cm2)
          N = number of vehicle passes (dimensionless)


3.3.4.6  Other Emission Factors--
     Parti cul ate emission factors for other size ranges are found in a man-
ner analogous to that described above for TP.   The concentrations correspond-
ing to these size ranges are determined using the particle size distributions
described earlier.  A linear  fit  of the mass  fractions measured  at 1 m and
3 m is used to determine mass fractions at the other heights of the profile.
Once net concentrations are determined,  exposure values and emission factors
are obtained in a manner identical to that for TP.

3.3.5  Control  Efficiency Calculation Procedure

     Because of meteorological  conditions  and logistical  constraints, it
was not always possible to run both  controlled and  uncontrolled  tests at
the same site in a plant.  Furthermore,  it was often necessary to determine
normalized values  in  order to obtain meaningful  comparisons even between
tests at  the  same site.  This was  true simply because the vehicle mix on
test roads varied from day to day.  Therefore, the measured emission factor
values had to  be  normalized in order that a change in vehicle mix was not
mistakenly interpreted  as a  control  efficiency  for the technique being
tested.

     Thus, determination  of  the efficiency of a  control measure  required
that the  measured emission factors (from both controlled and uncontrolled
tests) be  scaled  using  mean  vehicle characteristics  at the very  least.   It
                                 36

-------
is important to realize that other variables which affect emission factors
(such as silt content and surface loadings) are themselves affected by the
control  measures applied,  while vehicle mix is not.   Therefore no normaliza-
tion for silt and surface loading was  necessary when controlled and uncon-
trolled tests were conducted at the  same site.-

     The methods used in this study to  normalize measured emission factors
are based on MRI's experimentally determined predictive emission factor equa-
tions for uncontrolled open dust sources.  The equations for paved and un-
paved roads  are presented  in  Table  1-1.  As can be seen from this table,
the emission factors may be scaled by:
for paved roads and

               en = e.rnYSn\f"n
                n    l{r7  ST  WT
^si/\"l/ vi
for unpaved roads where
          e_ = normalized value of the emission factor corresponding
               to run i

          e. = measured  emission factor from run i

          s  = normalizing value for silt content

          s. = silt content measured for run i

          S  = normalizing value for average vehicle speed

          S- = average vehicle speed during run i

          Ln = normalizing value for surface loading

          L.J = surface loading measured for run i

          Wn = normalizing value for average vehicle weight

          W^ = average vehicle weight during run i

          w  = normalizing value for average number of wheels per
               vehicle pass

          w- = average number of wheels per vehicle pass during run i
                                 37

-------
The control efficiency in percent (C) is found as



               c =  i -  -£    x 100%

                         5u
where          e  = geometric mean of normalized emission factors for
                    controlled roads

               e  = geometric mean of normalized emission factors for
                    uncontrolled roads

     The normalization procedure varied depending on whether both uncontrolled
and controlled tests at the same site were available.   If replicates of both
controlled and uncontrolled tests were available at one site, the normaliza-
tion process  for  controlled  and uncontrolled emission rates involved only
the traffic parameters (average  vehicle weight,  average vehicle  speed,  av-
erage number of wheels per vehicle).  If more than one controlled or uncon-
trolled test site had to be used, uncontrolled emission factors were norma-
lized using the average values  of both road  surface and traffic  parameters
from all uncontrolled  tests  at the plant.   The  controlled  emissions were
also scaled to  the  mean  traffic parameters  for  all uncontrolled tests  at
the plant.   Because control measures affect the road surface characteristics,
the above  equations  imply  a emission  reduction based on the  average uncon-
trolled surface parameters at the plant.


3.4  AGGREGATE MATERIAL SAMPLING AND ANALYSIS

     Samples of the  road  surface and  storage pile  aggregate  materials were
taken in the course of this study.   These were analyzed for silt (those par-
ticles passing  a  200 mesh screen) and moisture  contents  and to  determine
road surface  loading values.  These parameters are of  importance in deter-
mining normalized emission rates as described earlier.  Detailed steps  for
collection and analysis of samples for silt and moisture are given in a pre-
vious report.4  An abbreviated discussion is presented below.

     Paved roadway surface dust  samples were removed from the travelled portion
of the  road by  vacumming,  preceded  by broom  sweeping if a heavy  loading of
aggregate was present.   The samples were collected from the travelled portion
of the road which was determined by observing the traffic and the road  itself,
noting that the portions  of a  roadway that were  not travelled  (e.g., curbs
and center  strips)  usually exhibited a heavy loading of dust.   The vacuum
bags were equilibrated to the same constant temperature and humidity condi-
tions as the  air  sampling filters before both  tare  and final  weighings.

     Unpaved roadway dust samples were collected by sweeping the loose  layer
of soil or crushed rock from the hardpan road base with a broom and dust pan.
Sweeping was performed so that the road base was not abraided by the broom,
and so that only the naturally occurring loose dust was collected.  The sweep-
ing was performed slowly so that dust was not entrained into the atmosphere.


                                 38

-------
       Once the field sample was obtained, it was prepared for analysis.   The
  field sample was split with a riffle to a sample size amenable to laboratory
  analysis.   Laboratory analysis procedures  to determine silt  and moisture
  contents were then identical  for all samples regardless of origin.

       The basic procedure  for  moisture analysis is determination of weight
  loss on oven  drying.   Table  3-5 presents a step-by-step procedure for de-
  termining moisture content.  Exceptions to this general procedure were made
  for any material  composed of  hydrated minerals or organic materials.   Be-
  cause of the  danger of measuring chemically  bound moisture  for  these mate-
  rials if they are over-dried,  the drying time was lowered to only 1-1/2 hr.
  Coal and soil  are examples of materials that were analyzed by this latter
  procedure.   Moisture analysis was performed in the field laboratory, normally
  on the  same day as sample  collection.   In this fashion, the measured value
  was a more reliable estimate of the field conditions at the time of the test.

                 TABLE 3-5.   MOISTURE ANALYSIS PROCEDURES
1.   Preheat the oven to approximately 110°C (230°F).   Record oven temperature.

2.   Tare the laboratory sample containers which will  be placed in the oven.
      Tare the containers with the lids on if they have lids.   Record the tare
      weight(s).   Check zero before weighing.

3.   Record the make, capacity, smallest division, and accuracy of the scale.

4.   weigh the laboratory sample in the container(s).   Record the combined
      weight(s).   Check zero before weighing.

5.   Place sample in oven and dry overnight.3

6.   Remove sample container from oven and (a) weigh immediately if uncovered,
       being careful of the hot container; or (b) place tight-fitting lid on
       the container and let cool  before weighing.  Record the combined sam-
       ple and container weight(s).  Check zero before weighing.

7.   Calculate the moisture as the initial weight of the sample and container
      minus the oven-dried weight of the sample and container divided by the
      initial weight of the sample alone.  Record the value.

8.   Calculate the sample weight to be used in the silt analysis as the oven-dried
      weight of the sample and container minus the weight of the container.
      Record the value.
   Dry materials composed of hydrated minerals or organic materials like coal
     and certain soils for only 1-1/2 hr.  Because of this short drying time,
     material dried for only 1-1/2 hr must not be more than 2.5 cm (1 in.)
     deep in the container.
                                   39

-------
     The basic procedure for silt analysis was mechanical,  dry  sieving.   A
step-by-step procedure  is  given  in  Table 3-6.   The silt analysis was per-
formed upon return to the main MRI laboratories.


3.5  RESULTS FOR VEHICULAR TRAFFIC ON UNPAVED ROADS

          Nineteen tests of controlled and uncontrolled emissions  from  ve-
hicular traffic on  unpaved roads were performed.  Table 3-7 presents the
site parameters of  the  exposure  profiling tests conducted on both unpaved
and paved  roads.   Site  parameters for paved roads  will  be discussed in
Section 3.6.  Ten tests were  of  heavy-duty traffic on both controlled and
uncontrolled unpaved  roads.  Nine tests were of  light-duty  vehicular traf-
fic on both controlled and uncontrolled unpaved roads.  These sets of tests
will be discussed separately.   It should be noted that the test sites listed
in Table 3-7 can be found in Figures 3-1 and 3-2.

3.5.1  Heavy-Outy Traffic

     Three  uncontrolled tests  of fugitive dust emissions from  heavy-duty
vehicular traffic on  unpaved  roads  were performed.   Two control measures
for unpaved roads were  evaluated—(1) a 17% solution of Coherexi in water
applied at  an  intensity of 0.86  2/m2 (0.19 gal/yd2) and (2) water applied
at an  intensity of  0.59 £/m2  (0.13 gal/yd2).   These control measures were
applied by plant personnel.

          Table 3-8 lists,  for each run,  the individual point values of iso-
kinetically corrected exposure (net  mass  per sampling intake area) within
the open dust source plume as  measured by the exposure profiling equipment.
These point values were  integrated over the height of the plume to determine
emission factors.


     Table 3-9 compares particulate  concentrations  measured by the upwind
hi-vol and  by  three types  of downwind samplers  (exposure profiling head,
standard hi-vol, and high-volume  cascade impactor) located 5 m from the test
road and  near  the vertical center of the  plume  at a height of 2 m above
ground.  For the profiler concentrations,  both nonisokinetic and isokinetic
values are given.

     Table 3-10 summarizes the particle sizing data for the tests of heavy-
duty traffic on unpaved roads.   Particle size is expressed in terms of aero-
dynamic diameter.

     Table  3-11 gives the  wind speed  and  intake  velocity used to calculate
the isokinetic  ratios for  each run.   These values in conjunction with the
previous table, were  used  to determine isokinetically corrected concentra-
tions and exposures according to  the procedure described in Section 3.3.4.2.

     Table  3-12 presents the isokinetic emission  factors for total,  inhal-
able and  fine  particulate.   Also indicated in this  table are vehicle and
site parameters which have been  found to have a significant effect on the
emission rates from uncontrolled unpaved roads.

                                 40

-------
                   TABLE 3-6.   SILT ANALYSIS PROCEDURES
1.   Select the appropriate 8-in.  diameter, 2-in.  deep sieve sizes.  Recom-
      mended U.S.  Standard Series sizes are:   3/8-in., No. 4, No. 20, No. 40,
      No.  100, No.  140, No.  200,  and a pan.   Comparable Tyler Series sizes
      can also be utilized.   The  No. 20 and the No.  200 are mandatory.   The
      others can be varied if the recommended sieves are not available or if
      buildup on one particular sieve during sieving indicates that an inter-
      mediate sieve should be inserted.

2.   Obtain a mechanical sieving device such as a vibratory shaker or a Roto-
      Tap (without the tapping function).

3.   Clean the sieves with compressed air and/or a soft brush.  Material
      lodged in the sieve openings or adhering to the sides of the sieve
      should be removed (if possible) without handling the screen roughly.

4.   Attain a scale (capacity of at least 1,600 g) and record make, capacity,
      smallest division, date of last calibration, and accuracy.

5.   Tare sieves and pan.  Check the zero before every weighing.  Record
      weights.

6.   After nesting the sieves in decreasing order with pan at the bottom,
      dump dried laboratory sample (probably immediately after moisture
      analysis) into the top sieve.  The sample should weigh between 800
      and 1600 g (1.8 and 3.5 Ib).   Brush fine material adhering to the
      sides of the container into the top sieve and cover the top sieve
      with a special lid normally purchased with the pan.

7.   Place nested sieves into the mechanical  device and sieve for 10 min.
      Remove pan containing minus No. 200 and weigh.  Replace pan beneath
      the sieves and sieve for another 10 min.  Remove pan and weigh.  When
      the difference between two successive pan sample weighings (where the
      tare of the pan has been subtracted) is less than 3.0%, the sieving
      is complete.   Do not sieve longer than 40 min.

8.   Weigh each sieve and its contents and record the weight.  Check the zero
      before every weighing.

9.   Collect the laboratory sample and place the sample in a separate con-
      tainer if further analysis is expected.

10. Calculate the percent of mass less than the 200 mesh screen  (75 urn).
      This is the silt content.
   This amount will vary for finer textured materials;  100 to 300 grams may
     be sufficient when 90 percent of the sample passes a No. 8 (2.36 mm) sieve.

                                 41

-------
                               TABLE  3-7.  EXPOSURE  PROFILING  TEST  SITE  PARAMETERS
ro

Site
A
A
A
A
A
A
B
B
B
B
B
B
B
B
B
C
C
C
C
D
D
D
E
E
E
E
E
E
F
F

Source
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Light- duty unpaved road
Light-duty unpaved road
Light-duty unpaved road
Light- duty unpaved road
.light- duty unpaved road
Light-duty unpaved road
Light-duty unpaved road
Light-duty unpaved road
Light-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Paved road
Paved road
Paved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Heavy-duty unpaved road
Paved road
Paved road
Control3
measure
N
N
VS
VS
VS
VS
N
N
N
N
C
C
C
C
C
C
C
C
C
N
N
WF
W
W
W
N
N
N
N
N

Run
F-34
F-35
F-36
F-37
F-38
F-39
F-28
F-29
F-30
F-31
F-40
F-41
F-42
F-43
F-44
F-59
F-60
F-63
F-64
F-61
F-62
F-74
F-65
F-66
F-67
F-68
F-69
F-70
F-27
F-45

Dale
07/17/80
07/17/80
10/14/80
10/15/80
10/16/80
10/16/80
07/12/80
07/13/80
07/13/80
07/13/80
10/18/80
10/18/80
10/19/80
10/19/80
10/19/80
11/03/80
11/03/80
11/05/80
11/05/80
11/04/80
11/04/80
11/21/80
11/06/80
11/06/80
11/06/80
11/06/80
11/06/80
11/06/80
07/08/80
10/20/80
Test
start
10:20
11:46
11:00
9:24
9:49
12:10
10:55
10:12
11:17
13:17
14:38
17:22
10:39
14:36
17:09
11:45
14:32
10:05
13:18
11:56
13:58
9:58
9:18
10:33
13:36
14:30
15:30
16:26
14:19
12:06
Sampling
duration
(min)
62
127
335
241
127
215
45
34
17
40
133
100
128
120
55
125
123
107
121
108
77
205
57
20
17
17
13
13
91
135
No. of
vehicle
passes
79
130
263
199
141
190
101
50
50
33
300
255
294
300
200
61
84
118
136
93
94
67
64
41
30
21
14
10
158
172
Ambient air
temperature
pnr"
32
32
10
10
10
10
26
26
26
27
10
10
10
10
10
9.9
9.9
9.9
9.9
4.4
7.2
9.9
16
16
13
9.9
9.9
9.9
38
10
~T5FT
90
90
50
50
50
50
78
79
79
80
50
50
50
50
50
50
50
50
50
40
45
50
60
60
55
50
50
50
100
50
Mean .
wind speed
Ii7iy~
1.9
3.4
2.6
2.1
2.0
2.9
0.72
2.8
2.8
1.6
1.8
2.3
3.1
3.8
4.1
4.2
3.7
2.3
2.9
4.9
5.4
4.0
2.9
2.5
4.2
3.3
3.5
3.7
4.2
1.8
liSjTi.
4.2
7 5
5.9
4.8
4.5
6.4
1.6
6.2
6.2
3.5
4.0
5.1
7.0
8.5
9.1
9.2
8.2
5.2
6.5
11
12
9.0
6.4
5.5
9.5
7.4
7.9
8.2
9.5
4.0

-------
                                                             TABLE  3-7.   (concluded)

Site
J
K
L
L
L
L
L
L
M
M
M
M

Source
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Paved road
Control3
measure
N
FBS
FBS
FBS
WF
WF
WF
N
FBS
N
N
N

Run
F-41
B-52
B-50
B-51
B-54
B-55
B-56
B-58
B-53
B-57
B-59
B-60

Dale
07/15/80
06/25/81
06/24/81
06/24/81
06/29/81
06/29/80
06/30/81
07/09/81
06/26/81
07/01/81
07/10/81
07/10/81
Test
start
11:10
10:22
10: 12
12:15
10:35
13:29
10: 35
15:51
12:45
13:09
11:55
14:05
Sampling
duration
(min)
259
60
104
93
101
82
61
96
81
101
114
112
No. of
vehicle
passes
301
119
123
127
118
98
118
67
72
68
67
50
Ambient air
temperature
("C)
32
32
32
32
32
32
32
32
32
32
32
32
m
90
90
90
90
90
90
90
90
90
90
90
90
Mean .
wind speed
TinTsT
2.6r
1 3
2.5=
1.9=
? 4
3.8=
2.8C
3.0=
2.4=
1 6
2'7c
2.2C
(mph)
5.8r
3.0=

4 2°
5-4r
8.6=

6.6=
5.3=
3.6=
6.1=
5.0C
CO
The control measures are:   N = uncontrolled
                         VS = vacuum sweeping
                          C = Coherex
                         WF = water flushing
                          W = watering
                        FBS = water flushing and broom  sweeping

Arithmetic average of 1 in and 3 m  values, unless otherwise noted.

Average of 2 m and 4 m values.

-------
TABLE 3-8.   PLUME SAMPLING DATA FOR HEAVY-DUTY VEHICLES ON UNPAVED ROADS
Control
Site measure Run
C Coherex F-59




C Coherex F-60




C Coherex F-63




C Coherex F-64




E Watering F-65




E Watering F-66





E Watering F-67




Sampling
height
(m)
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
V
1
2
3
4
5 -
Sampling
(m-Vhr)
24
37
42
49
52
37
49
50
54
70
14
20
24
27
31
21
32
33
38
41
15
25
26
32
35
15
26
26
31
32

20
24
27
31
34
rate
(cfm)
14
22
25
29
30
22
29
29
32
41
8
12
14
16
18
12
19
20
22
24
9
14
15
18
20
9
15
16
18
19

12
14
16
18
20
Net TP
exposure
(mg/cm2)
2.09
2.02
2.38
2.00
0.00
2.44
1.83
1.34
1.16
0.00
2.58
3.09
2.62
2.31
1.64
9.20
5.57
4.23
2.84
2.64
3.83
2.73
2.74
2.37
1.11
8.70
8.14
6.06
4.71
2.25

17.8
19.0
17.4
12.7
6.92
                                     44

-------
                     TABLE 3-8 (concluded)
Sampling
Control height
Site measure Run (m)
E None F-68 1
2
3
4
5
E None F-69 1
2
3
4
5
E None F-70 1
2
3
4
5
Sampling
(nrVhr)
24
32
34
37
41
27
29
29
29
29
34
38
42
43
23
rate
(cfm)
14
19
20
22
24
16
17
17
17
17
20
23
25
25
14
Net TP
exposure
(mg/cm2)
12.0
15.3
14.6
12.7
9.6
10.7
10.5
10.8
6.82
4.44
8.60
7.52
6.00
5.76
3.63
Isokinetically corrected.
                                    45

-------
              TABLE 3-9.   PARTICULATE CONCENTRATION MEASUREMENTS FOR HEAVY-DUTY TRAFFIC ON UNPAVED ROADS
CTl
Particulate concentration (ug/m3) at
2 m above ground
Downwind

Site
C
C
C
C
E
E
E
E
E
E
Control
measure
Coherex
Coherex
Coherex
Coherex
Watering
Watering
Watering
None
None
None

Run
F-59
F-60
F-63
F-64
F-65
F-66
F-67
F-68
F-69
F-70
Upwind
background
550
550
65
65
206
206
280
280
280
280
Profi
Nonisokinetic
768
620
2,280
2,320
3,240
25,000
65,000
43,500
42,700
22,800
ler
Isokinetic
719
706
2,160
2,620
• 2,840
25,900
43,200
43,500
36,900
25,600
Cascade
impactor
846
806
2,040
2,420
3,660
26,900
43,700
38,600
38,000
34,300

Standard
hi-vol
412
848
N/A
2,280
2,060
18,700
45,600
27,800
29,600
19,100
       Interpolated from 1 m and 3 m concentrations.

-------
            TABLE 3-10.   AERODYNAMIC PARTICLE  SIZE DATA -  HEAVY-DUTY TRAFFIC ON UNPAVED ROADS
Mass median
Site
C
C
C
C
E
E
E
E
E
E
Control
measure
Coherex
Coherex
Coherex
Coherex
Watering
Watering
Watering
None
None
None
Run
F-59
F-60
F-63
F-64
F-65
F-66
F-67
F-68
F-69
F-70
diameter
Ht=lm
57
65
60
70
> 100
> 100
42
55
> 100
77
(urn)
Ht=3m
57
6.7
39
54
> 100
> 100
74
> 100
80
53
% < 50
Ht=lm
46
45
47
44
24
31
53
48
28
41

jjm
Ht=3m
46
84
56
49
26
33
42
28
40
49

% <
Ht=lm
27
23
26
23
11
15
29
26
18
22

15 urn
Ht=3m
27
65
30
28
13
16
21
13
21
28

% <
Ht=lm
14
10
12
10
4
6
13
12
12
10

5 pro
Ht=3m
14
44
13
14
6
7
8
6
9
14

% <
Ht-lm
8
5
6
6
2
3
7
6
9
5

2.5 pm
Ht-3m
8
31
7
8
3
4
4
3
5
8
These values are based on a large log-normal  extrapolation of measured data.

-------
TABLE 3-11.  ISOKINETIC CORRECTION PARAMETERS FOR HEAVY-DUTY TRAFFIC ON UNPAVED ROADS


Site
C
C
C
C
E
E
E
E
E
E

Control
measure
Coherex
Coherex
Coherex
Coherex
Watering
Watering
Watering
None
None
None


Run
F-59
F-60
F-63
F-64
F-65
F-66
F-67
F-68
F-69
F-70

Ht =
(cm/s)
338
306
199
248
212
216
394
268
291
353
Wind •
1m
(fpm)
665
603
392
489
417
426
776
528
572
695
speed
lit = 3m
TcraTIT
494
430
266
330
358
274
456
392
416
396


( fpm)
972
847
524
650
704
540
898
77?
818
779
Intake velocity
Ht =
(cm/s)
260
392
153
221
163
163
217
255
291
371
1m
(fpm)
512
772
302
435
321
320
427
502
572
730
Hnn
(cm/s)
454
529
256
360
275
282
292
365
307
491

IfpniT
894
1,040
503
709
542
556
575
718
605
966
Measured
isokinetic
Ht=lm
0.770
1.28
0.770
0.890
0.770
0,751
0.550
0.951
1.00
1.05
ratio
HFIiif
0.920
1.23
0.960
1.09
0.770
1.03
0.640
0.930
0.740
1.24

-------
                TABLE 3-12.  VEHICULAR TRAFFIC  DATA AND EMISSION FACTORS FOR  HEAVY-DUTY
                             TRAFFIC ON UNPAVED ROADS


Site
C
C
C
C
E
E
E
E
E
E
'- ~- ---- ---- --
Control
measure
Coherex
Cohere*
Coherex
Coherex
Watering
Watering
Watering
Hone
None
None
== — -

Run
F-59
F-60
F-63
F-64
F-65
F-66
F-67
F-68
F-69
F-70

Silt
(%)
5.4a
5.4a
2.5
-
4.5
-
5.1
14

16b
Mean \
sl
(Mi)
26
35
29
24
32
40
40
32
32
32
vehicle
>eed
(mph)
16
22
18
15
20
25
25
20
20
20
"Rei
vehicle
(tonnes)
17
42
49.
49
48
49
49
20
48
48
n
weight
ftmisT
19
46
54
54
53
54
54
29
53
53
Mean No. of
wheels per
vehicle pass
9.3
9.2
7.7
7.8
10
9.0
9.8
5.9
10
10
•„ r- - -

TJgTVKTr
1.51
1.01
1.19
2.30
2.33
8.29
28.0
36.4
37.5
36.9
_ ._ .. -^ „
TP
(In/Mr)
5.34
3.35
4.41
8.17
8.27
29.4
99.3
129
133
133
Emisilor
1
(kg/VKf)
0.406
0.392
0.327
0.575
0.280
1.33
7.28
9.45
7.50
9.25
i faclors
IP
(Ib/VHT)
1.44
1.39
1.18
2.04
0.992
4.70
25.8
33.5
25.9
32.9
	 ""-"- "
_. -n
TJgTvTTr
0.121
0.168
0.0773
0.150
0.0618
0.290
1.54
2.18
2.49
2.40

>
TWVM7}
0.428
0.594
0.274
0.531
0.219
1.03
5.46
7.74
8.84
8.52
Same sample.
Average of more than one sample.

-------
     In order to determine control efficiencies, it was necessary to deter-
mine normalized TP, IP, and FP emission factors, as discussed in Section 3.3.J
The range, geometric mean and geometric standard deviation of the normalized
emission factors are given in Table 3-13.   Following the procedure described
in  Section 3.3.5,  control  efficiencies were  found and are presented  in
Table 3-14.

     Watering of unpaved  roads  showed a noticeable decay in control effi-
ciency.   In Figure 3-7, control  efficiency is plotted as a function of time
after application.   As seen in this figure, watering has a high initial con-
trol efficiency in all size ranges, but the effects are short-lived.

     The result of the four tests of Coherex® are incorporated into one aver-
age control  efficiency in this table.   This is because no trend of efficiency
decay was noticed  during  these  tests.  Quite possibly, this is due to the
fact that precipitation  (over 0.1 in.) fell  between the  first and  second
test days.  Nevertheless, tests  F-63 and F-64 indicated evidence of control
efficiency decay as shown below:
                                         Control efficiency (%)
              Run                       TP         IP         FP
F-63
F-64
96.9
93.1
96.4%
92.6
96.9
92.9
Thus, there  is  reason  to believe that a decay in control efficiency would
also have  been  observed under more  favorable  meteorological  conditions.

3.5.2  Light-Duty Traffic

     Five tests  of  fugitive  emissions from captive, light-duty traffic on
controlled unpaved roads were performed.   The control measure was a 17% solu-
tion of Coherex® in water applied at an intensity 0.86 £/m2 (0.19 gal/ yd2).
Four uncontrolled tests  were performed at  the  same  site  in order  to deter-
mine the efficiency  of the control.  The captive vehicles traveling on the
road were mid-sized rental  cars driven by MRI personnel.

     Table 3-15  lists,  for each  run,  the individual  point values  of isoki-
netically corrected exposure (net mass per sampling intake area) within the
fugitive dust plume as measured by the exposure profiling equipment.   These
point values were integrated over the height of the plume to determine emis-
sion factors.

     Table 3-16  compares particulate  concentrations  measured by the upwind
hi-vol  and by three types  of  downwind samplers  (exposure profiling head,
standard hi-vol,  and high-volume cascade  impactor)  located  5  m  from  the
test road and near the vertical center of the plume at a height of 2 m above
ground.   For the profiler concentrations, both nonisokinetic and isokinetic
values are given.

                                  50

-------
                    TABLE 3-13.   NORMALIZED EMISSION FACTORS FOR HEAVY-DUTY TRAFFIC ON UNPAVED ROADS
Normalized3 Emi


Control
Measure
None
Coherex
Watering


No. of
Tests
3
4
3



Range
33.6-78.4
0.886-3.58
2.09-20.0
TP

Geometric
mean
44.5
1.92
6.37

Geometric
standard
deviation
1.63
1.94
3.09



Range
6.54-20.4
0.367-0.968
0.250-5.19
ssion Factors (kg/VKT)
IP

Geometric
mean
10.3
0.564
1.09

Geometric
standard
deviation
1.82
1.64
4.57



Range
2.15-4.71
0.0866-0.288
0.0553-1.10
FP

Geometric
mean
2.83
0.167
0.236

Geometric
standard
deviation
1.56
1.66
4.47
Normalizing values are:
Silt content
Vehicle speed
Vehicle weight
Number of wheels
10.4%
32 kph (20 mph)
55 tonnes (50 tons)
9

-------
                TABLE 3-14.  CONTROL EFFICIENCIES FOR HEAVY-DUTY TRAFFIC ON UNPAVED ROADS


Control
Coherex®

Watering
Watering
Watering


Application intensity
0.86 £/m2 (0.19 gal/yd2)
of 17% solution
0.59 £/m2 (0.13 gal /yd2)
0.59 j>/m2 (0.13 gal/yd2)
0.59 A/in2 (0.13 gal /yd2)
Time
after
Application
(hr)
0-48b

0.48d
1.4d
4.4d
Time
after
Rainfall3
(days)
2-6°

3
3
3



Control efficiency (%)
TP
95.7

95.3
86.1
55.0
IP
94.5

97.6
90.4
49.6
FP
94.1

98.0
92.3
61.1
0.1 inch or more.
No trend of decay noticed over this time.



The first two tests were run 6 days after rainfall, and the second pair 2 days after rainfall.



At the midpoint of the test.

-------
en

CO
                    100
                o
                c
                c
                o
                     80
               !H    60
                     40
                       o
                              0.59j?/m2 (0.13 gal/yd2)
                                                                     Vehicle Passes

                                                                     Per Hour
       2              3


Time After Application (hours)
                                                                                    Mean
                                      78
                                            Standard

                                            Deviation
25
Key:
- Q 	 .
,...,« n TP
— a IP
	 A FP
i I 1
1 I
                            Figure 3-7.  Decay  in  control  efficiency of watering

                                           on unpaved  road under heavy-duty traffic.

-------
TABLE 3-15.   PLUME SAMPLING DATA FOR LIGHT-DUTY TRAFFIC ON UNPAVED ROADS
Control
Site measure
B None



B None



B None



B None



B Coherex




B Coherex




B Coherex




B Coherex




Sampling
height
Run (m)
F-28 1
2
3
4
F-29 1
2
3
4
F-30 1
2
3
4
F-31 1
2
3
4
F-40 1
2
3
4
5
F-41 1
2
3
4
5
F-42 1
2
3
4
5
F-43 1
2
• 3
4
5
Sampling
(nrVhr)
12
12
15
15
14
19
24
25
12
12
17
17
12
12
17
17
22
23
24
25
25
16
23
25
28
30
17
27
31
36
40
29
39
45
54
60
rate
(cfm)
7
7
9
9
8
11
14
14
7
7
10
10
7
7
10
10
13
14
14
14
15
10
14
15
16
18
10
16
18
21
24
17
23
27
32
35
Net TP
exposure
(mg/cm2)
3.52
3.58
1.66
0.770
5.20
4.74
3.56
2.57
4.20
3.77
2.76
1.29
3.01
3.13
1.81
0.92
0.205
0.166
0.0595
0.0658
0.0263
1.73
0.929
0.480
0.310
0.222
3.69
2.06
1.10
0.632
0.507
4.63
2.22
0.71
0.11
0.00
                                   54

-------
                 TABLE 3-15.  (Concluded)
Control
Site measure Run
Sampling
height
(m)
Sampling
(m-Vhr)
rate
(cfm)
Net TP
exposure
(mg/cm2)
     Coherex
F-44
1
2
3
4
5
25
38
44
50
53
15
22
25
29
31
3.24
0.83
0.84
0.17
0.00
ison neti cany  corrected.
                                55

-------
              TABLE 3-16.   PARTICIPATE  CONCENTRATION MEASUREMENTS  FOR  LIGHT-DUTY TRAFFIC ON UNPAVED ROADS
en
en



Site
B
B
B
B
B
B
B
B
B


Control
measure
None
None
None
None
Coherex
.Coherex
Coherex
Coherex
Coherex



Run
F-28
F-29
F-30
F-31
F-40
F-41
F-42
F-43
F-44
Par

Upwind
background
161
32
32
49
91
74
111
111
111
ticulate concentration (|jg/m3) at 2

m above ground

Downwi nd
Profiler
Nonisokinetic
20,100
10,700
26,400
9,500
204
662
1,020
831
735
Isokinetic
38,000
8,220
20,500
8,880
204
662
971
870
735
Cascade
impactor3
16,000
16,400
22,000
6,830
294
807
1,450
1,260
2,560
Standard
hi-vol
14,200
4,710
13,300
5,690
217
575
535
770
1,290
       Interpolated from 1 m and 3 in concentrations

-------
     Table 3-17 summarizes the particle sizing data for the tests of light-
duty traffic on unpaved roads.   Particle size is expressed in terms of aero-
dynamic diameter.

     Table 3-18 gives the wind speed and intake velocity  used to  calculate
the isokinetic ratios for each run.  These values,  in  conjunction with the
previous table, were used to determine  isokinetically  corrected concentra-
tions and exposures.

     Table 3-19 presents the isokinetic emission factors for total particu-
late, inhalable particulate, and fine particulate.  Also  indicated  in this
table are vehicle and site parameters which have been found to have a signif-
icant effect on the emission rates from uncontrolled unpaved roads.

     In order to determine control  efficiencies, it was necessary to deter-
mine normalized TP, IP,  and FP emission factors, as discussed earlier.   The
range, geometric mean and  geometric standard deviation of the normalized
emission factors are given in Table 3-20.   Following the procedure described
earlier in  this  section,  the control efficiency of Coherex® on light-duty
unpaved roads as a function of time was found and is presented in Table 3-21.

     In contrast to  the results  for heavy-duty traffic on unpaved  roads,
these tests show evidence of control efficiency decay for Coherex®,  as shown
in Figure 3-8.  The  TP, IP and FP  control efficiencies all tended  toward
90%  during  the short time  over which  results were available.  Finally,
Figure 3-9 plots the control efficiency of Coherex® as a function of vehicle
passes after .application.

3.6  RESULTS FOR VEHICULAR TRAFFIC ON PAVED ROADS

     As shown  in Table  3-7,  23 tests of open  dust  emissions from  vehicular
traffic on  paved roads  in  integrated iron and steel plants were performed.
Of these, 12  were  tests of controlled  roads.  The control measures tested
were:  (a) vacuum sweeping, (b) water flushing,  and (c) flushing with broom
sweeping.   All tests  (except those of  vacuum sweeping) began immediately
after the application  of  the control and lasted  between  1 and 5-1/2 hr.
The  remaining  11 tests  were of uncontrolled  paved  roads in order  to deter-
mine the efficiency of  each control.

3.6.1  Emission Factors

     Table 3-22 lists the individual point values of isokinetically corrected
exposure (net mass per  sampling intake  area)  within the dust plume as measured
by the exposure profiling equipment.

     Table  3-23  compares particulate concentrations measured  by the upwind
hi-vol and  by  three  types of downwind  samplers  (exposure profiling head,
standard hi-vol, and high-volume cascade impactor) located 5 m from the test
road  and  near  the  vertical  center  of  the  plume at a height of 2 m above
ground.  For the profiler concentrations, both nonisokinetic and  isokinetic
values are given.
                                 57

-------
                     TABLE 3-17.  AERODYNAMIC PARTICLE SIZE DATA - LIGHT-DUTY TRAFFIC ON UNPAVED ROADS
01
Oo
Mass median
Site
B
B
B
B
B
B
B
B
B
Control
measure
None
None
None
None
Coherex
Coherex
Coherex
Coherex
Coherex
Run
F-28
F-29b
F-30
F-31
F-40
F-41
F-42
F-43r
F-44C
diameter
Ht=lm
> 100
-
49
58
64
> 100
> 100
72

(Mm)3
Ht-3m
> 100
-
47
14
1.4
18
20
26

% <
Ht-lm
17
-
51
48
96
30
26
44

50 jjni
Ht=3m
29
-
52
77
~ 100
71
72
69

% <
Ht=lm
8
-
29
26
76
16
16
24

15 urn
Ht=3m
14
-
31
51
~ 100
46
43
34

% <
Ht-lm
3
-
15
13
41
8
9
12

5 urn
Ht-3m
6
-
16
27
99
25
19
10

% <
Ht-lm
2
-
8
7
20
4
6
7

2.5 pin
Ht-3m
4
-
10
13
85
14
9
4

       These values are based on a large log-normal  extrapolation of measured data.
       Size distribution of F-30 used.
       Insufficient substrate loadings, F-43 data used.

-------
              TABLE 3-18.  ISOKINETIC CORRECTION PARAMETERS FOR LIGHT-DUTY TRAFFIC ON UNPAVED  ROADS

Site
B
B
B
B
B
B
B
B
B
Control
measure
None
None
None
None
Coherex
Coherex
Coherex
Coherex
Coherex


Wind speed
Ht = Ira
Run
F-28
F-29
F-30
F-31
F-40
F-41
F-42
F-43
F-44
(cm/s)
44
233
143
107
148
172
233
328
323
(fpm)
86
459
282
211
291
339
458
646
635
nr=
(cm/s)
79
313
201
163
207
263
358
434
439

3m
( fpm)
156
617
396
321
408
517
705
855
865
Intake velocity
Ht =
(cm/s)
128
144
128
126
256
186
184
305
268
1m
(fpm)
252
285
251
249
503
366
362
601
527
lit =
(cm/s)
174
254
181
183
294
281
323
482
470
3m
(fpra)
342
500
356
360
579
553
635
949
926
Measured
isokinetic ratio
Ht=lm
2.93
0.621
0.890
1.18
1.73
1.08
0.790
0.930
0.830
Hl=3nT
2.19
0.810
0.899
1.12
1.42
1.07
0.901
1.10
1.07
en

-------
            TABLE 3-19.  VEHICULAR TRAFFIC  DATA AND EMISSION FACTORS  FOR LIGHT-DUTY TRAFFIC3  ON UNPAVED ROADS
Site
B
B
b
b
B
B
B
b
b
Control
measure
None
None
None
None
Coherex
Coherex
Coherex
Coherex
Coherex
Run
F-28
F-29
F-30
F-31
F-40
F-41
F-42
F-43
F-44
"Mean vefiicTe
Silt speed v
(%) (kph) (raph) (t
24
24
24
24
0.015 40
0.075 40
0.99 40
40
1.8 40
15
15
15
15
25
25
25
25
25
Mean
'ehicle weight
.onnesj" [tons)
2.7
2.7
2.7
2.7
2.7
2.7
2.7
2.7
2.7
3
3
3
3
3
3
3
3
3
Hean No! of
wheels per
vehicle pas
4
4
4
4
4
4
4
4
4
s TJ^TVKTT""
3.02
4.00
2.81
3.50
0.0252
0.185
0.333
0.344
0.347

l>
TTE/VRH 1
10.7
14.2
9.98
12.4
0.0894
0.657
1.18
1.22
1.23
Emission
Tactors

_ .__.
IP FT
[kg/VKT)
0.296
1.20
0.843
1.10
0.0172
0.0533
0.104
0.102
0.108
(Ib/VMT)
1.05
4.25
2.99
3.90
0.0610
0.189
0.368
0.363
0.383
(kg/VKT)
0.0691
0.358
0.253
0.288
0.0089/
0.0165
0.0266
0.0205
0.0216
TWVHTT
0.245
1.27
0.898
1.02
0.0318
0.0584
0.0945
0.0726
0.0766
       Captive traffic.
cr>
o

-------
        TABLE 3-20.  NORMALIZED EMISSION FACTORS FOR LIGHT-DUTY TRAFFIC ON UNPAVED ROADS
Normalized Emission Factors (q/VKT)


Control
Measure
None
Coherex


No. of
Tests Range
4 2820-4010
5 15.1-208
TP

Geometric
mean
3300
108

Geometric
standard
deviation
1.17
3.09



Range
296-1200
10.3-64.9
IP

Geometric
mean
756
38.4

Geometric
standard
deviation Range
1.90 69.1-358
2.20 5.39-16.0
FP

Geometric
mean
206
10.6

Geometric
standard
deviation
2.10
1.52
Normalized to vehicle speed of 24 kph (15 mph)

-------
                       TABLE  3-21.   CONTROL  EFFICIENCIES  OF COIIEREX FOR LIGHT-DUTY TRAFFIC ON UNPAVED  ROADS
en
ro

Control
Coherex
Coherex
Coherex
Coherex
Coherex

Application intensity
0.86 A/in2 (0.19 gal/yd2)
of 17% solution
0.86 £/m2 (0.19 gal /yd2)
of 17% solution
0.86 £/m2 (0.19 gal /yd2)
of 17% solution
0.86 £/m2 (0.19 gal/yd2)
of 17% solution
0.86 £/m2 (0.19 gal /yd2)
of 17% solution
Time
after
Appl ication
(hr)
25
28
45
49
51
Time
after
Rainfall
(days)
16
16
1
1
1
Control efficiency (%)
TP IP FP
99.5 98.6 97.4
96.6 95.8 95.2
94.0 91.8 92.2
93.7 91.9 94.0
93.7 91.4 93.7
         0.1 inch or more.

-------
             100
crt
u>
        X
        o
        c
        
-------
                          100
en
                      x
                      u
                      c
                      0)

                     "o
LU

"o
-4—
c
o
u
     95
                          90 -
                           0
Key:

O	

a	
                    —oTP

                    	a IP

                    —A FP
                                                                      0.86 Vm2 (0.19 gal/yd2)

                                                                      of 17% solution in water
                                                      J_
                            0       200      400        600       800      1000


                                                Vehicle  Passes After Treatment
                                                              1200
                                                          1400
                   Figure  3-9.   Decay  in  control  efficiency of Coherex applied  to a light-duty

                                   unpaved road as a function of vehicular  passes.

-------
TABLE 3-22.  PLUME SAMPLING DATA FOR PAVED ROADS
Control
Site measure
A None



A None



A Vac. sweep.




A Vac. sweep.




A Vac. sweep.




A Vac. sweep.




D None




D None




Run
F-34



F-35



F-36




F-37




F-38




F-39




F-61




F-62




Sampling
height
On)
1
2
3
4
1
2
3
4
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
Sampling
(nrVhr)
12
12
17
17
21
28
37
36
21
26
31
33
35
15
21
25
. 28
30
15
24
27
31
34
23
30
33
38
38
31
42
45
54
56
35
45
51
60
62
rate
Ccfra)
7
7
10
10
12
17
22
21
13
15
18
19
21
9
12
15
17
18
9
14
16
18
20
14
18
20
22
22
18
24
27
32
33
20
27
30
35
36
Net TP
exposure
(mg/cm2)
1.24
0.82
0.66
0.42
3.18
2.02
1.12
0.00
0.406
0.420
0.254
0.116
0.192
1.04
0.592
0.435
0.340
0.303
0.748
0.562
0.330
0.351
0.267
1.14
0.985
0.844
0.738
0.825
2.95
2.60
1.97
1.66
0.987
2.66
2.58
2.07
1.29
0.00
                    65

-------
TABLE 3-22 (continued)
Control
Site measure Run
D Water Flush. F-74




F None F-27



F None F-45




J None F-32



K Flushing and B-52
broom sweeping



L Flushing and B-50
broom sweeping



L Flushing and B-51
broom sweeping



Sampling
height
(m)
1
2
3
4
5
1
2
3
4
1
2
3
4
5
1
2
3
4
1
2
3
4
5
1
2
3
4
5
1
2
3
4
5
Sampling
(m-Vhr)
36
40
44
47
50
20
30
40
41
15
20
23
25
28
15
24
28
29
15
24
26
19
35
16
26
29
22
35
15
25
28
21
35
rate
(cfm)
21
24
25
28
29
12
18
24
24
9
12
14
15
16
9
14
16
17
9
14
15
11
21
9
15
17
13
21
9
15
17
13
20
Net TP
exposure
(mg/cm2)
1.65
1.55
0.799
1.00
1.13
1.14
0.94
0.66
0.00
3.44
2.50
2.01
1.41
1.45
0.683
0.523
0.385
0.346
0.404
0.221
0.248
0.144
0.187
0.820
0.922
0.695
0.623
0.00
1.60
1.46
1.10
0.477
0.606
         66

-------
TABLE 3-22 (continued)
Site
I




L




L




L




M




M




M




Sampling
Control height
measure Run (m)
Flushing B-54 I
2
3
4
5
Flushing B-55 1
2
3
4
5
Flushing B-56 1
2
3
4
5
None B-58 1
2
3
4
5
Flushing and B-53 1
broom sweeping 2
3
4
5
None B-57 1
2
3
4
5
None B-59 1
2
3
4
5
Sampling
(nrVhr)
15
24
26
19
35
17
26
29
21
39
18
27
30
22
35
15
24
27
21
36
15
24
27
20
35
15
24
26
19
32
15
24
26
23
40
rate
(cfm)
9
14
15
11
21
10
15
17
12
23
10
16
18
13
21
9
14
16
12
21
9
14
16
12
20
9
14
15
11
19
9
14
15
14
24
Net TP
exposure
(mg/cm2)
1.21
0.682
0.592
0.145
0.183
1.28
1.00
0.601
0.514
0.257
0.549
0.420
0.282
0.186
0.179
2.00
0.569
0.805
0.431
0.300
0.661
0.462
0.240
0.0547
0.00
1.18
1.39
1.09
0.605
0.439
1.93
0.597
0.887
0.433
0.379
         67

-------
                           TABLE 3-22 (concluded)
Control
Site measure Run
Sampling
height
(m)
Sampling
(nrVhr)
rate
(cfm)
Net TP
exposure
(mg/cm2)
        None           B-60       1           20         12        1.34
                                  2           26         15        1.51
                                  3           26         15        0.803
                                  4           19         11        0.603
                                  5           30         18        0.430
a  Isokinetically corrected.
                                    68

-------
                         TABLE 3-23.  PARTICULATE CONCENTRATION MEASUREMENTS FOR PAVED  ROADS
en
Participate concentration (ug/m3) at
Site
A
A
A
A
A
A
D
D
D
F
F
J
K
L
L
L
L
L
L
M
M
M
M
Control measure
None
None
Vacuum sweeping
Vacuum sweeping
Vacuum sweeping
Vacuum sweeping
None
None
Water Flushing
None
None
None
Flushing and broom sweeping
Flushing and broom sweeping
Flushing and broom sweeping
Water Flushing
Water Flushing
Water Flushing
None
Flushing and broom sweeping
None
None
None
Run
F-34
F-35
F-36
F-37
F-38
F-39
F-61
F-62
F-74
F-27
F-45
F-32
B-52
B-50
B-51
B-54
B-55
B-56
B-58
B-53
B-57
B-59
B-60
Upwi nd
background
732
1,080
168
247
162
64
189
189
166
886
161
144
184
226
226
250
250
197
161
340
277
140
140

2 m above ground
Downwi nd
Profiler
Nonisokinetic
2,540
1,660
243
441
512
310
1,090
1,090
454
1,180
1,580
286
339
644
1,130
678
959
593
551
676
1,106
452
1,050
Isokinetic
1,840
1,520
243
466
549
322
1,090
1,090
454
1,180
1,860
276
683
804
1,640
780
843
654
514
769
1,990
451
1,210
Cascade
impactor
1,880
1,790
398
411
568
372
1,580
1,240
300
1,110
1,030
232
190
407
1,080
• 537
752
488
750
410
619
736
769
Standard
hi-vol
801
945
212
331
453
328
961
973
399
894
1,180
177
402
' 661
N/A
689
599
522
1,080
627
951
797
620
   a  Interpolated  from  1 m and 3 m concentrations.

-------
     Table 3-24 summarizes the particle sizing data for the tests of vehicu-
lar traffic on paved roads.  Particle size is expressed in terms of aerody-
namic diameter.

     Table 3-25 gives  the  wind  speed  and  intake  velocity  used  to  calculate
the isokinetic  ratios  for  each  run.   These values,  in  conjunction with  the
previous table, were used  to determine  isokinetically  corrected concentra-
tions and exposures according to the procedure described earlier.

     Table 3-26 presents the isokinetic emission factors for total particu-
late, inhalable particulate, and  fine particulate.  Also  indicated  in this
table are vehicle  and  site parameters which  have been  found to have a sig-
nificant effect on the emission rates from uncontrolled paved  roads.

3.6.2  Control Efficiencies

     In order to determine control efficiencies,  it was necessary to deter-
mine normalized TP, IP, and FP emission factors,  as discussed earlier.   The
range, geometric mean  and  geometric standard deviation of the normalized
emission factors are given in Table 3-27.   Following the procedure described
earlier in this section, efficiencies of the different control  measures were
found and are presented in Table 3-28.  Note that two tests were omitted in
the determination  of control  efficiencies.   Run F-74 was the only test of
water flushing  at  Plant F; because  no replicates were  available, these  re-
sults were not  incorporated in  an efficiency of  control.  Furthermore,  be-
cause only one test (F-32)  was performed at site J and no reliable silt con-
tent was available for this site,  F-32 was omitted.

     The results for vacuum sweeping of paved roads suggest that,  initially,
the control  efficiency decreases with decreasing particle size.  The effi-
ciency in all  size ranges  decays  with time.   In some cases,  negligible IP
and FP control efficiencies were found.

     The other  two control measures, water flushing and flushing and broom
sweeping, appear to be equally  effective in all size  ranges  considered.
Flushing and broom sweeping is more effective than flushing alone, although
the additional  benefit  is  less  pronounced for fine particulate emissions.
This is  believed to  be a  valid statement despite the  differences in time
after rainfall because both controls involve wetting the surface.

3.7  COMPARISON OF PREDICTED AND ACTUAL UNCONTROLLED EMISSIONS

     During  the course of this field testing program,  18 tests  of vehicular
traffic on uncontrolled roads were  performed.   Eleven of these tests  were
conducted on paved roads and the remainder on unpaved roads.   In addition to
providing baseline emission data for control  efficiency determination,  these
tests expanded  the data  bases  used in forming the MRI predictive emission
factor equations in Table 1-1.2

     Although the  purpose of this  study was the measurement of  control  effi-
ciency,  the uncontrolled tests were included in  the data base  to determine
how well the  MRI  equations predict measured emission  levels.   This is  of
particular interest because MRI  is currently in the process of  refining the

                                 70

-------
                        TABLE 3-24.  AERODYNAMIC PARTICLE  SIZE  DATA -  PAVED  ROADS
median diameter (Mm)
Site
A
A
A
A
A
A
D
D
0
F
F
,1
K

L

L

L
L
L
L
M

M
M
M
Control measure
None
None
Vacuum sweeping
Vacuum sweeping
Vacuum sweeping
Vacuum sweeping
None
None
Water flushing
None
None
None
Flushing and broom
sweeping
Flushing and broom
sweeping
Flushing and broom
sweeping
Water flushing
Water flushing
Water flushing
None
Flushing and broom
sweeping
None
None
None
Run
F-34
F-35
F-36
F-37
F-38
F-39
F-61
F-62
F-74
F-27
F-45
F-32
B-52

B-50

B-51

B-54
B-55
B-56
B-58
B-53

B-57
B-59
B-60
lit = 1m
45
27
18
18
35
18
55
60
> 100
30
> 100
20
> 100

> 100

65

> 100
30
40
29
> 100

> 100
40
57
Fit = 3m
42
23
8
85
7
10
47
50
100
12
65
13
> 100

> 100

38

29
19
18
20
> 100

100
33
56
% < 50 uma
FHmiii HlS~1i
52
64
74
74
57
73
48
46
25
60
34
67
26

38

44

27
64
55
64
26

33
54
47
54
68
98
42
90
85
56
50
44
79
45
78
30

30

55

63
77
78
72
30

39
56
48
%<
Ht = 1m
30
38
46
46
35
45
25
25
18
36
16
45
12

29

20

16
30
27
33
17

15
29
26
15 urn
Ht = 3ro
32
40
69
26
70
59
32
28
33
55
26
54
20

24

29

32
43
44
42
22

21
36
31
% < 5
Ht = 1m
14
18
22
22
18
21
11
11
13
18
6
25
5

14

7

9
9
10
12
10

6
13
13
urn
III = 3m
15
19
36
16
42
31
15
14
24
31
13
31
12

14

11

15
16
16
18
16

10
24
18
% < 2.5 urn
Ht = Im
e
10
12
12
11
11
6
6
10
10
3
16
3

8

2

6
2
5
5.
7

3
6
8
Ht = 3m
9
10
19 ,
10
25
17
8
8
20
18
8
18
9

10

4

8
4
6
9
13

6
16
12
TItese values are EaselTon sTTarge Tog-normal extrapolation oT^measured dala.

-------
TABLE 3-25.   ISOKINETIC CORRECTION PARAMETERS FOR PAVED ROADS
Wind speed
Site
A
A
A
A
A
A
D
D
D

F
F
J
K

L

L

L

L

L

L
M

M
M
M
Control
measure Run
None F-34
None F-35
Vac. sweep. F-36
Vac. sweep. F-37
Vac. sweep. F-38
Vac. sweep. F-39
None F-61
None F-62
Water F-74
flushing
None F-27
' None F-45
None F-32
Flushing & 6-52
broom sweep.
Flushing & B-50
broom sweep.
Flushing & B-51
broom sweep.
Water B-54
flushing
Water B-55
flushing
Water B-56
flushing
None B-58
Flushing & B-53
broom sweep.
None B-57
None B-59
None B-60
Ht =
(cm/s)
157
292
211
733
165
253
434
474
354

313
148
221
102

184

182

149

266

209

248
157

76
216
181
1m
(fpm)
310
574
416
262
324
498
855
933
696

617
291
436
201

362

358

294

523

411

488
309

150
425
357
Ht =
~ici7ir~
221
383
313
218
205
322
528
610
454

538
210
301
137

262

184

249

389

284

299
245

167
275
228
3m
IfpiJ
435
754
617
429
404
633
1,040
1,200
894

1.060
414
592
270

516

363

491

766

558

588
483

329
541
448

Ht =
(cm/s)
128
221
232
164
163
250
339
374
393

270
164
162
177

193

173

166

194

207

166
168

166
209
165
Intake velocity
1m
ffpmT
251
436
458
322
321
493
667
737
773

531
323
318
348

380

340

326

382

407

327
331

326
412
325
Ht =
Tclii7sT~
181
395
332
268
292
370
484
549
482

549
273
295
291

346

337

279

311

323

286
295

279
280
277
3m
I fpm)
357
777
654
528
574
728
952
1,080
948

1,080
538
580
572

681

664

550

613

636

564
580

549
552
546
Mea
isokine
flt^Tm
0.815
0.757
1.10
1.23
0.989
0.988
0.781
0.789
1.11

0.863
1.11
0.733
1.74

1.05

0.951

1.11

0.729

0.990

0.669
1.07

2.18
0.968
0.912
sured
tic ratio
llt=3m
0.819
1.03
1.06
1.23
1.42
1.15
0.917
0.900
1.06

1.02
1.30
0.980
2.12

1.32

1.83

1 12

0.799

1.14

0 957
1.20

1.67
1.02
1.21

-------
TABLE 3-26.   ROAD SURFACE  CHARACTERISTICS AND EMISSION FACTORS FOR PAVED ROADS



Control
Site measure
A
A
A
A
A
A
0
I)
U
F
F
J
K

L

L

L
L
L
L
M

M
M
M
a
b ,
None
None
Vacuum sweeping
Vacuum sweeping
Vacuum sweeping
Vacuum sweeping
None
None
Water flushing
None
None
None
Flushing and
broom sweeping
Flushing and
broom sweeping
Flushing and
broom sweeping
Water flushing
Water flushing
Water flushing
None
Flushing and
broom sweeping
None
None
None
Average of two or more

lane characteristics

Run
F-34
F-35
F-36
F-37
F-38
F-39
F-61
F-62
F-74
F-27
F-45
0-32
B-52

B-50

B-51

B-54
B-55
B-56
B-58
B-53

B-57
B-59
B-60
values.


No.
2
2
2
2
2
2
2
2
2
2
2
2
2

2

2

2
2
2
2
2

2
2
2


Widtli
(m)
2.59
2.59
3.72
3.11
4.02
3.11
4.72
4.72
4.72
3.B1
3.81
3.35
3.29

3.75

3.75

3.75
-
4.02
-
-

3.72
4.18
4.11


(ft)
8.5
8.5
12. 2a
10. 2a
13.2
10.2
15.5
15.5
15.5
12.5
12.5
111.0
10.8

12.3

12.3

12.3
-
13.2
-
-

12.2
13.7
13.5


Silt
(%)
16
10.4
18.3
26.4
27.9
19.6
21.0
20.3 ,
9.45a
35.7
28.4
13.4
34.3

28.2°
U
28. 2b

22.6
19. 6a
11.2
17.9
9.94

6 45a
14. Oa
13.5


Loading
(kg/M
90.0
101
8.21
9.84,
6.26a
14.0
804
671
558a
316
137
5.84
138

361

361

125
244a
172
440
-

268
123
194


( Ib/mi)
319
358
29.1
34.9
22.2
49.8
2,850
2,380a
l,980a
1,120
487
20.7
489

1,280

1,280

444
866a
611
1,560
-

949
435
688


Mean
vehicle weight
(tonnes)
25
23
7.5
15
16
16
36
33
26
13
15
13
11

8.5

10

9.1
10
8.3
16
18

11
10
11


(tons)
28
25
8.3
17
18
18
40
36
29
14
16
14
12

9.4

11

10
11
9.2
18
20

12
11
12


TP
< lcg/VI
-------
                     TABLE 3-27.   NORMALIZED  EMISSION  FACTORS  FOR  VEHICULAR  TRAFFIC  ON PAVED ROADS
Control
Measure Plant
None 0
None B
Vacuum Sweeping 0
Water Flushing B
•*> Flushing and B
Broom
Sweeping



TP
No. of Geometric
Tests Range mean
6 159-2930
4 234-1540
4 148-412
3 367-491
4 152-573

959
880
246
404
270

Normalized3 Emission Factors (g/VKT)
IP FP
Geometric Geometric
standard Geometric standard Geometric
deviation Range mean deviation Range mean
3.40 66.9-1140 221 3.59 19.6-278 53.8
2.44 86.9-516 260 2.18 15.8-174 72.4
1.52 77.3-244 126 1.70 23.0-72.2 38.5
1.18 90.8-182 133 1.42 21.5-24.0 23.1
1.83 28.2-138 57.1 2.12 12.4-37.5 20.4



Geometric
standard
deviation
.',.19
2.95
1.79
1.06
1.62

The normalizing values are:







Silt Content x Surface Loading



Mean Vehicle Weight
        Plant F
Plant B
350 kg/km (100 Ib/mile)   350 kg/km (100 Ib/mile)



  24 tonnes (22 tons)       14 tonnes (13 tons)

-------
                                     TABLE 3-28.   CONTROL EFFICIENCIES FOR PAVED ROADS
en


Application
Control frequency
Vacuum sweeping Every 2 days





Water Flushing Once per 3 days

Flushing and Once per 3 days
broom sweeping


Application
intensity
340 mVmin
(12,000 cfm)
vacuum blower
capacity


2.2 £/m2
(0.48 gal/yd2)
2.2 £/m2
(0.48 gal/yd2)
Time
after
appl ication
(hr)
2.8

24.4

2.1
4.1
0.68d

0.70d

Time
after
rainfall
(days)
12

13

14
14
3.3d

1.3d



Control
TP
69.8

51.8

47.8
16.1
54.1

69.3



efficiency (
IP FP
50.9 49.

57.7 51.

16.3 c
c c
48.8 68.

78'. 0 71.



o/\
/°.)

2

4



1

8

         0.1 inch or more.
         Control efficiencies based on same-site testing.
         No reduction in emissions observed.
         Average of three tests.

-------
predictive equations by  including  recent test results from  a  variety of
roads (industrial paved and unpaved, urban paved, and rural unpaved).  This
work is supported under EPA Contract No.  68-02-3158.

     The results of the  comparison  of predicted  and measured emissions are
presented in Tables 3-29 and 3-30 for unpaved and paved roads,  respectively.
The first entries in each table comprise the data base in Reference 2, while
the tests performed  in  this study begin with F-28 and F-27,  respectively.
It should be noted that F-32 is excluded from the data base for paved roads
for the same reasons given in Section 3.6.2, namely,  the lack of replicates
and unreliable silt content and surface loading values.

     The precision factors  (two  standard deviations) associated with the
predictive equations are shown in the following table:

                                    Precision factor as a
                                    Function of Data Base
                                                 Reference 2
                              Reference 2      and Present Study

         Unpaved Roads           1.48                1.98
         Paved Roads             2.20                3.95

The fact that  the  precision factors increase when predicting measurements
in the  larger  data base illustrates the need  for possible refinement of
MRI's predictive equations.  .As mentioned earlier, this process is underway.
                                 76

-------
       TABLE 3-29.   PREDICTED  VERSUS ACTUAL EMISSIONS  (UNPAVED ROADS)
Run
R-l
R-2
R-3
R-8
R-10
R-13
A- 14
A- 15
E-l
E-2
E-3
F-21
F-22
F-23
G-27
G-28
G-29
G-30
G-31
G-32
1-3
1-5
F-28
F-29
F-30
F-31
F-68
F-69
F-70
Silt
Average
vehicle speed
(%) (km/hr) (mph)
12
13
13
20
5
68
4.8
4.8
8.7
8.7
8.7
9.0
9.0
9.0
5.3
5.3
5.3
4.3
4.3
4.3
4.7
4.7
10C
10C
10C
10C
14r
15C
16
48
48
64
48
64
48
48
48
23
26
26
24
24
24
35
37
39
40
47
35
24
24
24
24
24
24
32
32
32
30
30
40
30
40
30
30
30
14
16
16
15
15
15
22
23
24
25
29
22
15
15
15
15
15
15
20
20
20
Avoraqe
vehicle weight
(tonnes) (tons)
3
3
3
3
3
3
64
64
31
31
21
3
3
4
15
11
8
13
7
27
61
142
3
3
3
3
20
48
48
3
3
3
3
3
3
70
70
34
34
23
3
3
4
17
12
9
14
8
30
67
157
3
3
3
3
29
53
53
[missjon factor
Averaije Ho.
vehicle wbee
4.0
4.0
4 0
4.5
4 0
4.0
4.0
4.0
9.4
8.3
6.4
4.0
4.0
4.1
11.0
9.5
7.8
8.5
6.2
13.0
C.O
6.0
4.0
4.0
4.0
4.0
5.9
10.0
10.0
of Predicted
Is 
-------
                          TABLE 3-30.   PREDICTED VERSUS  ACTUAL EMISSIONS (PAVED ROADS)
                     Koad surface dust
                                                                 Av/ct
CO
Run Type
P-9

P-10
Pulver-
ized .
topsoil"
P-14 I Gravel*1
E-7

E-8
P-3,
P-b,
P-6
P-15,
P-16
Iron and
steel
Plant
Urban
arterial
site le
Urban
arterial
site 2'-
F-13 \
1 Iron and
F-14 steel

F-15
F-16

F-17

plant


Iron and
steel
plant
F-18
F-27-
F-34
F-35

F-45
F-61
F-62


Iron and
'•steel
plant


loa
excludi
(ku7km)
1,990

809
1,890
225

225
45. lf


42. Of


57.2

57.2

57.2
629

629

629
316
90 0
101

137
804
671
ding
ny curbs
(ib7roilc)
7,060

2,870
6,700
800

800
160f


149f


203

203

203
2.230

2,230

2.230
1,120
319
358

487
2,850
2,380
No. of
traffic
lanes
4

4
4
2

2
4


4


2

2

2
2

2

2
2
2
2

2
2
2
Silt
45

92
23
5.1

5.J
10f


10f


13.2

13.2

13.2
6.8

6 8

6.8
35.7
16
10.4

28 4
21.0
20.3
1
( industrial )
uuil tip) ier)
1

1
1
/

7
1


1


1

1

1
3.5

3 5

I
1
1
1

t
1
1
vulijr l<;
wciubt
(tonnes)
3

3
3
6

1
3


3


7

5

5
12

11

b
13
25
23

15
36
13
( tons )
3

3
3
7

8
3


3


8

5

5
13

12

5
14
28
25

16
40
36
Lmiss ion
Predicted
(kg/VKI)
0.82

0.68
0.39
0.26

0.29
0 0039


0 0037


0.096

0.068

0.068
0. 76

0. 70

0.11
0.59
0.12
0.085

0.23
1.9
1.4
( Ib/VMI )
2.9

2.4
1.4
0.93

1.02
0.014


0.013


0.34

0.24

0.24
2.7

2.5

0.39
2.1
0.44
0.30

0.80
6.6
5.0
(act 01 s
Actual
(ku,/VKI)
1.0

0.59
0. 13
0.21

0.28
0.0042


0.0037


0. 16

O.ObG

0.045
0. 7(1

0.48

0.14
0. 16
0.26
0.39

0.31
0 60
0.48
(Ib/VMI)
3.7

2.1
0.46
0. /6

1.0
0.015


0.0130


0.58

0.20

0. 16
2.5

1.7

0.48
0.56
0. 92
1.4

l.l
2.4
1.7
Predict i
0. 78

1. 14
1.04
1.22

1.02
0.93


1.00


0.5'J

1.2U

1 . 50
1 08

1 '17

0.81
3.75
0.48
0 21

0.73
2 75
2.94

-------
                                                   TABLE  3-30.   (Concluded)
Road surface dust
I odd i in)
excluding curbs"
Run
B-57J
B-58 (
B-59 1
B-60 )
fypi.-


stool
plant
(kg/km)
268
440
123
1<)4
(Ib/mile)
949
1,560
435
688
N... of
traffic
lanes
2
2
2
2

Sill
m
6.5
17.9
14.0
13.5
1
AVP ratio
vphir le
( indusl rial ) woiglit
mul I ipl ier)
3.5
3.5
3.5
3.5
( lonnos)
11
16
10
II
(Ions)
12
18
Jl
12
1 in i s s i on
Predicted '
(k«/VKI)
0.28
i.;
0.27
0.42
(Ib/VMl)
1.0
6.2
0.95
1.5

factors


Actual
(kg/VKf)
0.31
0.56
0.45
0.54
(Ih/VMI)
1. I
2.0
1.6
1.9


Credit tod
= Actual
0.91
3. 10
0.59
0. 79
Loading distributed  over traveled portion  of  road,  i.e., traffic lanes.
Particles smaller  than JO put in Stokes diameter based on actual density of  sill  particles.
Based on revised MRI emission factor equation in Table 1-1.
Four-lane test  roadway artifically loaded.
Four-lane roadway  with traffic count of about 10,000 vehicles per day,  mostly  light-duty.
Estimated value.

-------
             4.0  WIND EROSION TESTING BY PORTABLE WIND TUNNEL


     This section describes the field testing program using the MRI portable
wind tunnel to determine the efficiency of control measures applied to stor-
age piles.  The  following  tests were performed at two integrated iron and
steel  plants - Armco's Middletown Works (designated as Plant F) and Bethlehem
Steel's Burns Harbor Plant (designated as Plant H):

          Fourteen tests of wind erosion from uncontrolled coal storage
          piles.

          Twelve tests of wind erosion from controlled coal storage piles.

          Two tests of wind erosion from an active exposed area.

          One test of wind erosion from an inactive exposed area.

4.1  QUALITY ASSURANCE

     The sampling  and  analysis procedures followed in this field testing
program were  subject  to certain quality control guidelines.   These guide-
lines  will  be  discussed in conjunction with the  activities to  which  they
apply.  These procedures met or exceeded the requirements specified in Sec-
tion 3.0.

     As part  of  the  QC program for this study, routine audits of sampling
and analysis  procedures  were  performed.   The purpose of the audits was to
demonstrate that measurements were made within acceptable control conditions
for particulate  source  sampling and to assess the source testing data for
precision and accuracy.  Examples of items audited include gravimetric ana-
lysis, flow rate calibration, data processing, and emission factor and con-
trol  efficiency  calculation.   The  mandatory use of specially designed re-
porting forms for sampling and analysis data obtained in the field and lab-
oratory aided in the auditing procedure.   Further detail  on specific sampling
and analysis procedures are provided in the following sections.

4.2  AIR SAMPLING TECHNIQUE AND EQUIPMENT

     The portable wind tunnel method allows i_ri situ measurement of emissions
from wind erosion of storage piles and exposed areas.   The MRI portable pull-
through wind tunnel (Figure 4-1) consists of an inlet contraction, a working
section, a  sampling section,  and a  power  system.   The open-floored working
section of  the tunnel  was  placed directly on the  surface  to be  tested, and
the tunnel  air  flow  was adjusted to values corresponding  to  the means of
the upper NOAA wind speed ranges.   Tunnel wind speed was measured by a pitot
tube  at  the downstream end of the working section and was related to wind
speed at the standard 10-m (30.5 ft) height by means of a logarithmic profile.


                                     81

-------
00
ro
                                         Figure 4-1.  MRI  portable  wind  tunnel.

-------
     To minimize the  dust  levels in the tunnel air intake stream, testing
was conducted only when ambient winds were below the threshold velocity for
erosion of the  exposed  material.  A portable  high  volume  sampler with  an
open-faced filter was  operated on top of the inlet contraction to measure
background dust levels.

     An emissions sampling section was used with the pull-through wind tunnel
in measuring particulate emissions  generated by wind erosion.  As shown in
Figure 4-1, the  sampling  section was located between the  working section
outlet hose and  the  blower inlet.  The sampling train,  which was operated
at 425 to 708 £/min (15 to 25 ftVmin) consisted of a tapered probe, cyclone
precollector,  parallel slot cascade impactor, backup filter, and high volume
sampler.   Interchangeable probe tips were sized for isokinetic sampling over
the desired tunnel  wind speed range.

     Test sites at the two plants were formed by plant personnel.  At plant
F, a small level area for uncontrolled testing (as shown in Figure 4-2) was
formed from the steam coal  storage pile with a bulldozer.   Controlled tests
were conducted directly on the treated pile.

     At plant H, test sites were prepared by having a front-end loader form
two piles  approximately 12 m x 15 m  x 0.15 m (40  ft x 50 ft x  6  in.)  in an
area of the coal yard which is not heavily traveled.   These test beds are
shown in Figure 4-3.

     The use of  a front-end loader  at plant  H  resulted  in  a compacted sur-
face which is  not  representative of piles in the plant.  For this reason,
some test  sites  were  also  prepared by turning the  surface with  a shovel.
Controlled and  uncontrolled tests were run on both compacted  and turned
surfaces.

     In order to adequately define the extent of the control measure at plant
H, provision was made to  measure application intensity.  The latex binder
(Dow Chemical  M-167)  regularly used at the plant was applied to the west test
bed, and provisions were  made to measure the  application  intensity.  Six
tared sampling  pans were placed  in  the test  bed prior to spraying and were
then reweighed.  Special  attention  was paid to the problems of the binder
running off the coal  into the pans and of the spray bouncing off the bottom
of the pan.  In  order to reduce  these potential errors, the lip  of the pan
was placed just  above the  coal surface and an absorbent material was used
to line the bottom.   A cross-sectional view of the sampling pan is shown in
Figure 4-4.

4.3  PARTICULATE SAMPLE HANDLING AND ANALYSIS

4.3.1  Preparation of Sample Collection Media

     Particulate samples were  collected  on  type A slotted glass fiber im-
pactor substrates and on type AE glass fiber filters.   To minimize the prob-
lem of particle  bounce,  the  glass fiber  cascade  impactor  substrates were
greased.
                                     83

-------
            •Tunnel Location for
            Controlled Tests
Level Area Formed
by Dozer for
Uncontrolled Tests

-------
                                                        North
                                                                                                To Coal Piles
                                                                                                and Coke Battery
00
en
   Location of
   Sampling Pans
   (See Figure 4-4)
                         W-4*
                             -X-
                         W-l
                                      W-3
                                             Surface Turned
                                             Before Application
                                             of Latex Binder
W-2
                                          -X-
                                          -x-
                                12m (40ft)-
 15m
(50ft)
 12m
(40ft)
                                      15m (50ft)-
                                                                Letters Indicate Test Site Location
                                                                                          1" = 20'
                                         Figure  4-3.   Test site locations at plant H.

-------
oo
                                                                                      ~1 cm (0.4 in)
                                                                                              No Scale
                                        Figure  4-4.   Sampling  pan detail

-------
The grease  solution was prepared by dissolving 140  g  of  stopcock  grease  in
1 liter of reagent grade toluene.   No grease was applied to the borders and
backs of the substrates.   The substrates were handled, transported and stored
in specially designed frames which protected the greased surfaces.

     Prior to the initial  weighing, the greased impactor substrates and hi-
vol filters were equilibrated for 24 hr at constant temperature and humidity
in a special weighing room.   During weighing, the balance was checked at fre-
quent intervals with  standard  weights to assure accuracy.   The substrates
and filters  remained  in the  same controlled  environment  for  another 24 hr,
after which  a  second  analyst reweighed them as a weighing accuracy check.
If substrates  or filters could not pass audit limits, the entire  batch was
reweighed.  Ten percent of  the substrates and filters taken to the field
were used as blanks.   The quality assurance guidelines are the same as those
presented in Table 3-1.

4.3.2  Pre-Test Procedures/Evaluation of Sampling Conditions

     Prior to equipment deployment, a number of decisions were made concern-
ing the potential  for acceptable testing conditions.  To reduce dust levels
in the tunnel air intake stream, testing would be conducted only if the am-
bient winds  were well  below the erosion threshold velocity of the surface
being tested.  Testing was  not performed on days of or after considerable
rainfall  unless provisions  were  made  to protect the test surface from the
weather.

     If conditions were deemed acceptable, equipment deployment began.   Dur-
ing this  2-hr  period,  both  high volume air samplers were calibrated using
the quality control guidelines of Table 4-1.

      TABLE 4-1.   QUALITY CONTROL PROCEDURES FOR SAMPLING FLOW RATES
Activity
      QC Check/Requirement
Calibration
     Impactors and background
       hi-vol
Orifice calibration
Calibrate flows in operating ranges
using calibration orifice each day
prior to testing.

Calibrate against displaced volume
test meter annually.
                                     87

-------
     Once the source  testing  equipment was in place, a threshold velocity
test was performed.   The purposes of this preliminary test were to determine
the minimum velocity at which wind erosion is initiated and to gather other
data needed for sampling and analysis.   The threshold velocity for a parti-
cular surface was determined by observing the onset of surface particle move-
ment as the wind velocity was gradually increased.   A subthreshold velocity
profile was then measured using the pi tot tube in the working section. This
subthreshold velocity  profile  allows the  calculation  of  the  surface  rough-
ness height.

     After these data were obtained, tunnel air speeds were determined cor-
responding  to the means of the first  three  upper  NOAA wind speed ranges
above the  threshold velocity  of the uncontrolled test surface.   A  sampling
train flow  rate  and probe  tip  were  selected  to  insure isokinetic sampling.
A test  series  consisted of runs at these three wind  speeds  (in  ascending
order) at the same site.

4-3.3  Sample Handling and Analysis

     To prevent particulate losses, the exposed media were carefully trans-
ferred  at  the  end of each run to protective containers within the MRI in-
strument van.  In the field laboratory, exposed filters were placed in indi-
vidual glassine envelopes and  numbered file  folders.  Substrates were replaced
in the protective frames. Particulate that collected  on the interior surface
of the cyclone preseparator was rinsed with  distilled water into sample jars
which were  then capped and taped shut.

     When exposed impactor substrates and  hi-vol filters (and the  associated
blanks)  were  returned to the  MRI laboratory, they were equilibrated under
the  same conditions  as the initial weighing.   After reweighing, 10% were
audited  to  check weighing accuracy.  To determine the sample weight of par-
ti cul ate collected on  the  interior surface of a sampler, the entire wash so-
lution was  passed through a 47 mm Buchner  type funnel holding a  glass fiber
filter  under suction.  The sample jar was  then rinsed twice with 10 to 20 ml
of deionized water.  This water was passed through the Buchner funnel ensur-
ing  collection of all  suspended material  on  the 47 mm filter which was then
dried  in an oven  at 100°C  for  24 hr.  After  drying, the  filters  were  condi-
tioned  at  constant temperature and humidity  for 24 hr.

     All wash filters  were weighed with a 100% audit  of  tared and  a  10% audit
of exposed  filters.   Blank values were determined by  washing "clean"  (unex-
posed)  settling  chambers in the field and following  the above procedures.
The  quality assurances  guidelines governing  sample  handling  and  analysis are
the  same as those presented  in Table 3-1.

4.3.4   Emission  Rate  Calculation Procedures

      To calculate emission rates from wind  tunnel  data, a conservation of
mass approach is used.  The  quantity  of  airborne particulate generated by
wind erosion of  the  test  surface  equals  the quantity leaving the tunnel
minus  the  quantity  (background)  entering  the tunnel.   The  steps  in the cal-
culation procedure  are described  below.

-------
4.3.4.1  Participate Concentrations--
     The definitions  of  participate matter (TP, TSP, IP, FP) are the same
as those given  earlier for  exposure profiling.   Participate  concentrations
are determined  in  a  manner  identical  (and  at  the same  standard  conditions) •
to that presented earlier.

4.3.4.2  Flow Rate in Wind Tunnel —
     During testing,  the  wind  speed profile along  the  vertical  bisector of
the tunnel  working  section  is measured with a standard pitot tube and  in-
clined manometer.  The velocity profile near the test surface (tunnel floor)
and the walls of the tunnel  is  found to  follow  a logarithmic distribution:
                                        0 -

where:    u = wind speed at z (cm/s)
          z = distance from test surface (or wall) (cm)
         u* = friction velocity (cm/sec)
         z  = roughness height (cm).

     The roughness height of the test surface is determined by extrapolation
of the velocity profile near the surface to u = 0.  The roughness height for
the plexiglass walls and ceiling of the tunnel has been measured as 6 x 10-4
cm.  These velocity profiles are integrated over the cross-sectional area of
the tunnel to yield the volumetric flow rate through the tunnel for a partic-
ular set of test conditions.

4.3.4.3  Isokinetic Flow Ratio—
     A pitot  tube  and  inclined manometer are  also  used  to measure the cen-
terline wind  speed in  the sampling duct at  the  point where the sampling
probe is  installed.  Because the ratio  of the centerline wind  speed  in the
sampling duct to the centerline wind speed in the working section is indepen-
dent of flow  rate, it  can be used to determine isokinetic sampling condi-
tions for any flow rate in the tunnel.

     The isokinetic flow ratio is the ratio of the sampler intake air speed
to the wind speed approaching the sampler.   It is given by:


                         IFR =
                               aUs
                                        f

where:     Qs = sampler flow rate (ms/s)
          a  = intake area of sampler (m2)
          U  = wind speed approaching the sampler (m/s).

IFR is  of interest in the sampling of TP,  since isokinetic sampling assures
that particles of all sizes are sampled without bias.   Because probe tips of
various intake areas were available for the cyclone preseparator, all tests
run were within ± 5% of isokinetic conditions.
                                     89

-------
4.3.4.4  Particle Size Distributions--
     Particle  size  distributions  were determined from a  cascade  impactor
using the proper 50% cutoff diameters for the cyclone precollector and each
impaction stage.  These data were fitted to a log-normal mass size distribu-
tion after  correction  for  particle  bounce  using  the  technique discussed  in
Section 3.3.4.3.  During controlled wind tunnel tests on coal surfaces, the
background concentration was a significant percentage of the measured down-
wind concentration, especially when testing on the same surface for a second
or third time.   Therefore,  microscopic  analyses  of the  upwind filters were
performed,  because  the size distribution of the  background  particulate was
important.   If  it had been  foreseen  that the upwind loading  was  going to  be
such a  large  portion  of the downwind loading, an impactor would have been
placed in the upwind hi-vol to directly measure the particle size distribu-
tion by mass.

4.3.4.5  Particulate Emission Rates--
     The emission  rate for airborne particulate of  a given  particle size
range generated by wind erosion of the test surface is given by:
where:    E = particulate emission rate (g/m2-sec)

         Cn = net particulate concentration (g/m3)

         Q.  = tunnel flow rate (ms/sec)

          A = exposed test area = 0.918 m2


4.3.4.6  Erosion Potential--
     If the emission rate is found to decay significantly (by more than 20%)
during back-to-back tests of a given surface at the same wind speed, due to
the presence of nonerodible elements on the surface, then an additional cal-
culation step must  be  performed to determine the erosion potential of the
test surface.   The erosion potential is the total quantity of erodible par-
ticles, in  any  specified particle size range, present on the surface (per
unit area)  prior  to the  onset of  erosion.   Because  wind  erosion  is  an  ava-
lanching process, it  is  reasonable to assume that  the  loss  rate  from  the
surface is  proportional  to  the  amount  of  erodible material  remaining.  The
amount remaining is  assumed to be of the form:

                         Mt = Moe'kt

where:    M, = quantity of erodible material present on the surface at any
                 time (g/m2)
          M  = erosion potential, i.e., quantity of erodible material pres-
                 ent on the surface before the onset of erosion (g/m2)
           k = constant (s x) •
           t = cumulative erosion time (s).
                                     90

-------
     Consistent with the above equation, the erosion potential may be calcu-
lated from  the  measured loss rates from  the  test  surface  for two erosion
times:
where:    Lj = E^ = measured loss rate during time period 0 to tx (g/m2)
          12=1!+ E2(t2 - ti) = measured loss rate during time period 0
               to t2 (g/m2)

4.3.5  Control Efficiency Calculation Procedure

     The control  efficiency  in percent (C) for these wind erosion studies
was found by:
          C = I 1 - y£Ll± \ X 100%

where         \     °'u(
          M    = erosion potential of the uncontrolled surface
          M '  = erosion potential of the controlled surface

     It should be  noted  that an erosion potential can be obtained only if
back-to-back tests at the same wind speed are available and if the emission
rate of the second test is lower than that of the first.   Should an erosion
potential  not be available, C was determined as:


                                       100%


where:     E  = emission rate of the uncontrolled surface
          E  = emission rate of the controlled surface

     These emission  rates  must  be based on the same wind speed and on the
same duration of erosion.  In order to determine emission rates from several
tests at  the  same  site,  it was assumed  that any  mass  eroded  on a  test  at
wind speed Uj, and of duration Tj. would also have been eroded at a subsequent
test if U2 ^ G! and T2 >_ Tj.   This approach will be discussed in greater de-
tail in Section 4.5.2.

4.4  AGGREGATE MATERIAL SAMPLING AND ANALYSIS

     Samples of the test surface were collected, where possible, before and
after each test.   When  several  tests were performed back-to-back, samples
could only be obtained before and after the series.   These samples were ana-
lyzed for silt and moisture content.
                                     91

-------
     Storage pile samples were removed from a known area using a dust pan and
wnisk broom.  The depth of the sample was based on the largest piece of raw
material in the  surface.   The silt ana  moisture  analysis procedures were
identical to those presented in Tables 3-5 and 3-6.

4.5  RESULTS FOR WIND EROSION OF COAL PILES

     As mentioned earlier  in  this  section, 26 tests of fugitive  dust emis-
sions generated  by wind  erosion of coal  piles were performed.   In  addition
to these tests,  three  tests of wind erosion  of exposed areas  in  integrated
iron and steel plants  were conducted.  These tests were preliminary checks
of the sampling equipment's performance.

4-5-1  Emission Rates

     Before presenting the results of the 29 wind erosion tests, the charac-
teristics of the  test  control techniques will  be discussed.  Two controls
were tested—(1) a 16.7% solution of Coherex® in water applied at an inten-
sity of  3.4 3,/m2  (0.74 gal/yd2)  at plant F and (2) a 2.8% solution of Dow
Chemical M-167 Latex Binder in water applied at an average intensity of 6.8
2/m2 (1.5 gal/yd2) at plant H.  These control measures were applied by either
plant personnel or a contractor retained by the plant.  The Coherex® at plant
0 was applied once in August 1980 and every 4 to 6 weeks thereafter while the
latex binder at plant H was applied approximately every week.

     The site  and sampling parameters for  the runs are shown  in  Tables 4-2
and 4-3, respectively.   The  tunnel  center!ine wind speeds  for  the uncon-
trolled tests  were  selected  to correspond to the means of the first three
upper NOAA wind speed ranges above the threshold velocity.   Threshold veloc-
ities for each run are presented in Table 4-4.

     In anticipation of a high control efficiency associated with the latex
binder, filters were not changed after some tests  at plant H in order to pro-
duce an acceptable mass on each substrate of the cascade impactor.   The sec-
ond (and sometimes the third) test was then run with the same filters as the
first, but at a higher tunnel velocity.   The second test was then denoted by
adding a letter suffix to the prior test number.

     Results for test series H-30 through H-30B will  not be reported because
of difficulties  experienced  in filter handling.   While the  testing was un-
derway, rainstorms entered the area.   When the impactor substrates were re-
moved, they were found to be fairly damp but some  appeared loaded.   However,
upon weighing, net catches were so small  as to be  beyond the accuracy of the
analysis techniques.   It is also possible that some of the wet filter material
became brittle upon drying and flaked off during handling.

     Table 4-5 summarizes the particle size data for the wind erosion tests.
Particle sizes  are  expressed in terms of aerodynamic diameter.  Note that
the very small portion of material collected on the interior surface of the
probe tip was  ignored  in the particle size analysis.
                                     92

-------
                                     TABLE  4-2.   WIND  EROSION  TEST  SITE  PARAMETERS
OJ
Runa
F-46
F-47
F-48
F-49
F-50
F-51
F-52
F-53
F-54
F-55
F-56
F-57
H-20
H-21
H-22
H-23
H-24
H-25
H-26
H-27
H-28
H-28A
H-29
H-30
H-30A
H-30B
H-31
H-31A
H-31B
Material
Exp. area
Exp. area
Exp. area
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Condition
Inactive
Active
Active
Active
Active
Active
Active
Active
Active
Active
Undisturbed
Undisturbed
Compacted
Compacted
Compacted
Turned
Turned
Turned
Turned
Compacted
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Control
measure
None
None
None
None
None
None
None
None
None
None
Coherex®
Coherex®
None
None
None
None
None
None
None
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Site
H-l
H-2
H-2
1-1
1-1
1-1
1-1
1-1
1-2
1-2
1-3
1-3
E-l
E-l
E-l
E-2
E-2
E-2
E-2
W-l
W-2
W-2
W-2
W-3
W-3
W-3
W-4
W-4
W-4
Date
10/21/80
10/21/80
10/21/80
10/22/80
10/22/80
10/22/80
10/22/80
10/22/80
10/23/80
10/23/80
10/23/80
10/23/80
10/13/81
10/13/81
10/13/81
10/15/81
10/15/81
10/15/81
10/15/81
10/16/81
10/16/81
10/16/81
10/16/81
10/17/81
10/17/81
10/17/81
10/18/81
10/18/81
10/18/81
Start
time
1500
1628
1701
1156
1217
1332
1419
1443
1026
1100
1355
1511
1622
1700
1747
1321
1340
1450
1542
1504
1600
1625
1718
1128
1158
1224
1127
1205
1243
Sampling
duration
(min)
30
10
3
20
10
40
15
60
20
30
60
60
20
20
20
2
18
20
20
20
20
20
20
20
20
20
20
20
20
Cross-sectional
1 velocity in
i test section
(m/s)
10.7
8.36
11.6
6.06
8.34
8.34
11.2
11.2
5.49
8.27
11.9
11.9
9.68
12.6
13.0
8.32
8.47
11.2
13.2
12.0
8.63
11.0
13.4
8.99
11.6
14.0
8.89
11.5
13.6
(mph)
23.9
18.7
25.9
13.6
18.7
18.7
25.1
25.1
12.3
18.5
26.6
26.6
21.7
28.1
29.0
18.6
19.0
24.9
29.5
26.9
19.3
24.7
30.0
20.1
25.9
31.2
19.9
25.6
30.5
Temperature
(°C)
21
21
21
21
21
21
21
18
18
18
18
18
12
12
• 12
17
17
17
17
16
16
16
16
12
12
12
8
8
8
      Runs with a  letter suffix indicate that filters were not changed from the prior run in order to obtain an
        acceptable sample on each substrate of the impactor.

-------
                              TABLE 4-3.   WIND EROSION SAMPLING PARAMETERS
Sampling module
Centerline
velocity
Run
F-46
F-47
F-48
F-49
F-50
F-51
F-52
F-53
F-54
F-55
F-56
F-57
H-20
H-21
H-22
H-23
H-24
H-25
H-26
H-27
H-28
H-28A
H-29
H-30
H-30A
H-30B
H-31
H-31A
H-31B
(m/sl
13.7
10.8
15.0
8.14
11.2
11.2
15.0
15.0
7.11
10.7
15.0
15.0
12.7
16.4
17.0
10.8
11.0
14.4
17.2
17.2
11.1
14.3
17.2
11.1
14.3
17.2
11.1
14.3
17.1
(mph)
30.6
24.2
33.5
18.2
25.0
25.0
33.5
33.5
15.9
24.0
33.5
33.5
28.4
36.7
38.0
24.2
24.6
32.2
38.5
38.5
24.8
32.0
38.5
24.8
32.0
38.5
24.8
32.0
38.3
Flow
rate
(nrVhr)
3,570
2,800
3,890
2,030
2,790
2,790
3,740
3,740
1,840
2,760
4,000
4,000
3,220
4,180
4,320
2,770
2,820
3,710
4,390
4,000
2,870
3,670
4,460
2,990
3,850
4,640
2,960
3,820
4,540
Probe
Diameter
(cm)
1.55
1.98
1.55
2.54
1.98
1.98
1.98
1.98
2.54
1.98
1.55
1.55
1.98
1.98
1.98
1.98
1.98
1.98
1.98
1.98
1.98
1.98
1.55
1.98
1.98
1.55
1.98
1.98
1.55
Area
(oF)
1.89
3.08
1.89
5.07
3.08
3.08
3.08
3.08
5.07
3.08
1.89
1.89
3.08
3.08
3.08
3.08
3.08
3.08
3.08
3.08
3.08
3.08
1.88
3.08
3.08
1.88
3.08
3.08
1.88
Velocity^
Approach
(m/s)
38.6
35.4
49.2
20.8
28.6
28.6
38.2
38.2
17.1
25.8
41.1
41.1
27.0
34.0
36.2
24.2
24.2
32.0
38.2
40.0
25.5
32.9
39.6
25.5
32.9
39.6
25.5
32.9
39.6
Inlet
38.2
35.7
49.2
20.7
27.9
27.9
37.4
37.4
17.0
25.7
40.3
40.3
26.6
35.4
36.2
24.0
24.0
32.7
38.4
38.4
24.5
32.7
39.4
24.5
32.7
39.4
25.4
32.7
39.4
IFRa
0.990
1.01
1.00
0.997
0.976
0.976
0.979
0.979
0.997
0.997
0.981
0.981
0.987
1.04
1.00
0.993
0.994
1.02
1.00
0.960
0.961
0.995
0.995
0.961
0.995
0.995
0.997
0.995
0.995

Volume
sampled
(m3)
13.0
6.60
1.68
12.6
5.15
20.6
10.4
41.5
10.4
14.3
27.4
27.4
9.85
13.1
13.4
0.889
8.00
12.1
14.2
14.2
9.06
12.1
8.89
9.06
12.1
8.89
9.40
12.1
8.89

Total mass
collected
(mg)
4.72
309
413
5.06
22.6
38.2
82.9
73.7
5.30
13.2
8.16
5.76
232
459
105
9.43
43.0
135
1,770
198
I
j
50.4

64.2

|
} 675
1
Isokinetic Flow Ratio = Inlet Velocity/Approach Velocity

-------
            TABLE 4-4.  THRESHOLD VELOCITIES  FOR WIND  EROSION
Threshold velocity
Tunne!

Run
F-46
F-47
F-48
F-49
F-50
F-51
F-52
F-53
F-54
F-55
F-56
F-57
H-20
H-21
H-22
H-23
H-24
H-25
H-26,
H-27°
H-28dd
H-28AQ
H-29a
H-30
H-30A
H-30B
H-31
H-31A
H-31B
3 Area
b T-

Materia!
Exp. area
Exp. area
Exp. area
Coal
Coal
Coal
Coa!
Coal
Coal
Coal
Coal
Coal
Coa!
Coa!
Coal
Coal
Coa!
Coa!
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coa!
was quite


Condition
Inactive3
Active?
Active
Active
Active
Active
Active
Active
Active^
Active
Undisturbed
Undisturbed
Compacted
Compacted
Compacted
Turned
Turned
Turned
Turned
Compacted
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Turned
crusted.
..._._ j_ . - _ _ _ t _ j_ __
Control
measure
None
None
None
None
None
None
None
None
None
None
Coherex®
Coherex®
None
None
None
None
None
None
None
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex

_ i

Site
H-l
H-2
H-2
1-1
1-1
1-1
1-1
1-1
1-2
1-2
1-3
1-3
E-l
E-l
E-l
E-2
E-2
E-2
E-2
W-l
W-2
W-2
W-2
W-3
W-3
W-3
W-4
W-4
W-4


center!
m/s
13.0
8.85
8.85
8.14
8.14
8.14
8.14
8.14
5.94
5.94
12.0
12.0
9.21
9.21
9.21
9.48
9.48
9.48
9.48
> 12.7 >
> 11.1 >
> 11.1 >
> 11.1 >
10.0
10.0
10.0
10.3
10.3
10.3


ine
mph
29.2
19.8
19.8
18.2
18.2
18.2
18.2
18.2
13.3
13.3
26.9
26.9
20.6
20.6
20.6
21.2
21.2
21.2
21.2
28.5
24.8
24.8
24.8
22.4
22.4
22.4
23.0
23.0
23.0


Equivalent at
10 m hei
m/s
21.8
15.3
15.3
16.4
16.4
16.4
16.4
16.4
10.4
10.4
18.1
18.1
16.9
16.9
16.9
16.6
16.6
16.6
16.6
> 24.0 >
> 19.5 >
> 19.5 >
> 19.5 >
14.8
14.8
14.8
15.6
15.6
15.6


qht
mph
48.8
34.3
34.3
36.7
36.7
36.7
36.7
36.7
23.4
23.4
40.6
40.6
37.8
37.8
37.8
37.2
37.2
37.2
37.2
53.6
43.6
43.6
43.6
33.2
33.2
33.2
34.8
34.8
34.8


      tests were run on coal that was dumped onto pile immediately before
  equipment deployment.

Once the lowest center!ine velocity of the corresponding uncontrolled test
  was reached, the search for a threshold velocity was abandoned.  Hence,
  lower bounds on the threshold velocity are given.
                                   95

-------
TABLE 4-5.   AERODYNAMIC PARTICLE SIZE DATA - WIND EROSION


Run
F-46
F-47
F-48
F-49
F-50
F-51
F-52
F-53
F-54
F-55
F-56
F-57
H-20
H-21
H-22
H-23
H-24
H-25
H-26
H-27
H-28
H-28A
H-29
H-30
H-30A
H-30B
H-31
H-31A
H-31B
, The values
Substrates
Mass median
diameter
(Mm)
90
> 100
> 100
30
> 100
> 100
> 100
> 100
9.0
71
16
27
> 100
> 100'
> 100
93
> 100
> 100
> 100
> 100
I > 100
, > 100
)
b
J

> 100

are based on
became wet,
i

% < 50 pm
41
20
13
60
25
22
1.2
9.5
85
64
71
60
32
16
19
37
11
11
5.2
8.0
I 14
} 16

b

»
6.1
J
a large log-normal
invalidating data.


%. -| r-
< 15 pin
24
11
6.5
36
14
11
0.60
5.0
62
24
48
40
15
7.5
9.5
18
4.9
3.3
1.7
3.5
I 6.4
v 8.2
\
b

)
1.9
I
extrapolation of measured

	

% < 5 HI"
13
5.5
3.5
18
7.0
5.5
0.32
1.6
37
12
28
24
6.0
3.3
4.5
7.0
2.2
0.90
0.45
0.76
I"
, 4.0
)
b
)
)
> 0.53
1
data.

	 	 	

% < 2.5 pin
8.0
3.5
2.2
11
4.5
3.4
0.21
0.80
23
7.0
17
16
4.0
1.9
2.5
3.8
1.3
0.32
0.20
0.85
} 1'4
v 2.5
\
b
)

0.22




-------
     Table 4-6 presents  data on the surface properties which are believed
to have  a  significant effect on emission  rate.  Table  4-7  summarizes  the
wind erosion test results.

4.5.2  Control Efficiencies

     As discussed earlier, the efficiency of control measures applied to  coal
storage piles are based  on either  erosion  potentials  or on  emission  rates.
The erosion potentials found in this study are presented in Table 4-8.   Note
that a  lower  bound  is given for the IP erosion potential for uncontrolled
steam coal.   This  is  due to the fact  that the measured emission  rate  for
F-53 did not decrease from that of run F-52.   In this case, an erosion poten-
tial cannot be determined.

     Combined emission rates for Cambria coal are given in Table 4-9.  These
are based  on  an  erosion time of 20 min.   A  control efficiency determined
from the ratio of  emission rates is based on the assumption that, after  a
suitably long erosion  time,  the total  mass  lost approximates the erosion
potential.   In  this case, the  ratio of  emission rates approximates the
ratio of erosion potentials.

     In order to substantiate  this approach, the total  mass  lost during
Runs H-23  and H-24  was  compared  to the erosion potential found using these
runs.   The results  are presented below:
                                Mass lost during H-23 and H-24
               Size range            -r erosion potential
                   TP                        0.783
                   IP                        1.00
                   FP                        0.969
     From these  values,  one  may see that 20 min of erosion can quite ade-
quately approximate the erosion potential.   This is especially true for in-
halable and  fine particulate emissions.   For total particulate emissions,
the approximation is not as good; however,  there is the complicating effect
of creeping motion.   Twenty minutes is a long enough time for large particles
to roll along the surface  until  they  finally enter  the tail section of the
wind tunnel.  These particles  are,  of  course, not  airborne.  Therefore,  it
is believed that the mass eroded after 20 min also approximates the erosion
potential  for TP.

     Analysis of  Runs H-23 and H-24 proves that the erosion potential was
approximated at  10.7 m/s  center!ine speed  (24 mph).  It  is reasonable to
assume that  this  approximation improves  as the wind  speed  is  increased.
Therefore, one can conclude  that the  other wind erosion  tests conducted  in
this study also  adequately approximated  the erosion potentials since they
all occurred at  a center! ine wind  speed greater  than  10.7  m/s  (24 mph).

                                     97

-------
                                                     TABLE  4-6.   PROPERTIES OF  SURFACES TESTED
to
00
. .
Run3
F-46
F-47
F-48
F-49
F-50
F-51
F-52
F-53
F-54
F-55
F-56
F-57
H-20
H-21
H-22
11-23
H-24
H-25
H-26
H-27
H-28
H-28A
H-29
H-30
H-30A
H-30B
H-31
H-31A
H-31B
Surface
Type
Exposed area
Exposed area
Exposed area
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal
Coal

Control
measure
None
None
None
None
None
None
None
None
None
None
Coherex®
Coherex®
None
None
None
None
None
None
None
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex
Latex

Site
H-l
H-2
H-2
-1
-1
-1
-1
-1
-2
-2
-3
-3
E-l
E-l
£-1
E-2
E-2
E-2
E-2
W-l
W-2
W-2
W-2
W-3
W-3
W-3
W-4
W-4
W-4
Before
Sill
5.50
8.26
-
4.25
-
-
-
-
-
-
3.02
-
-
-
-
6.5
-
-
-
4.0
2.8
-
-
5.3
-
-
4.6
-

erosion
Moisture
(%)
5.56
2.51
-
2.70
-
-
-
-
-
-
3.60
-
-
-
-
-
-
-
h
3-°h
3.5b
-
-
5.6
-
-
6.8
-

After
Silt
(*)
5.62
-
8.11
-
-
-
-
3.77
-
-
-
-
-
-
2.1
-
-
-
5.6
4.4
-
-
4.5
-
-
-
-
-
4.0
erosion
Moisture
(X)
3.75
-
3.26
-
-
-
-
1.99
-
-
-
-
-
-
3.4
-
-
-
8.1
4.9
-
-
5.9
-
-
-
-
h
5.2D
Average
Silt
(%)
5.6
8.2
8.2
4.0
4.0
4.0
4.0
4.0
-
-
3.0
3.0
2.1
2.1
2.1
6.0
6.0
6.0
6.0
4.2
3.6
3.6
3.6
5.3
5.3
5.3
4.3
4.3
4.3
erosion
Roisture
(X)
4.7
2.9
2.9
2.3
2.3
2.3
2.3
2.3
-
-
3.6
3.6
3.4
3.4
3.4
8.1
8.1
8.1
8.1
4.9
5.9
5.9
5.9
5.6
5.6
5.6
6.8
6.8
6.8
Roughness
height
(cm)
0.03
0.05
0.05
0.25
0.25
0.25
0.25
0.25
0.06
0.06
0.004
0.004
0.12
0.12
0.12
0.087
0.087
0.087
0. 087
0. 150
0.051
0.051
0.051
0.0010
0.0010
0.0010
0.0050
0.0050
0.0050
               Runs with a letter suffix indicate  that filters  were not changed  from the prior run  in order to obtain
                 an acceptable sample on each substrate of the  impactor.
               The sample depth in the pan was too great to allow proper ventilation; thus these moisture values  may
                 be too low.

-------
TABLE 4-7.  WIND EROSION TEST RESULTS
Cross- sectional
average
velocity in

Run
F-46
F-47
F-48
F-49
F-50
F-51
F-52
F-53
F-54
F-55
F-56
F-57
H-20
H-21
11-22
11-23
11-24
H-25
11-26
H-27
H-28
II-28A
11-29
11-30
H-30A
H-30B
11-31
H-31A
H-31B

Material
Exposed area
Exposed area
Exposed area
Steam coal
Steam coal
Steam coal
Steam coal
Steam coat
Steam coal
Steam coal
Steam coal
Steam coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal
Coking coal

Condition
Inactive
Active
Active
Active
Active
Active
Active
Active
Active
Active
Undisturbed
Undisturbed
Compacted
Compacted
Compacted
Turned
Turned
Turned
Turned
Compacted
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Turned
Control
measure
None
Hone
None
None
None
None
None
None
None
None
Coberex®
Cone rex©
None
None
None
None
None
None
None
Latex
Latex
Latex
latex
Latex
Latex
Latex
Latex
latex
Latex
test
(m/s)
10.7
8.41
11.7
6.09
8.38
8.38
11.2
11.2
5.52
8.31
12.0
12.0
9.68
12.6
13.0
8.32
8.47
11.2
13.2
12.0
8.63
11.0
13.4
8.99
11.6
14.0
8.89
11.5
13.6
section
(mpli)
24.0
18 8
26.1
13.6
18.8
18.8
25.2
25.2
12.3
18.6
26.9
26.9
21.6
28.1
29.0
18.6
19.0
24.9
29.5
26.9
19.3
24.7
30.0
20.1
25.9
31.2
19.9
25.6
30.5
Friction
velocity
(m/s)
0.878
0.757
1.05
0.792
1.09
1.09
1.46
1.46
0.514
0.775
0.727
0.727
1.05
1.36
1.41
0.837
0.852
1.12
1.33
1.25
0.780
1.00
1.21
0.462
0.595
0.716
0.554
0.713
0.853
Cumulative
erosion
time
(min)
30
10
13
20
30
70
85
145
20
50
60
120
20
40
60
2
20
40
60
20
20
40
60
20
40
60
20
40
60


jmg/raVs)
0.0843
39.1
288
0.215
3.65
5.14
9.06
2.01
0.258
0.753
0.303
0.199
2.14
43.9
9.96
8.89
4.47
12.4
166
16.7
-
10.9
7.38
-
-
-
-
-
104

7F
(Ib/acre/s)
0.00075
0.348
2.57
0.00192
0.0325
0.0458
0.0808
0 0179
0.00230
0.00671
0.00270
0.00177
0.0191
0.391
0.0888
0.0792
0.0398
0.110
1.48
0.149
-
0.0972
0.0658
-
-
-
-
-
0.927
Net emission rate
IP
(mg/mVs)
.
5.19
17.0
0.0685
0.489
0.569
0.0543
0.0806
0.163
0.166
0.144
0.0739
0.265
3.42
0.911
1.51
0.113
0.285
2.64
0.391
-
0.567
0.424
-
-
-
-
-
1.65
(Tb/acre7s)

0.0463
0.152
0.000611
0.00436
0.00507
0. 000484
0.000718
0.00145
0.00148
0.00128
0.000659
0.00236
0.0305
0.00812
0.0135
0.00101
0.00254
0.0235
0.00348
-
0.00505
0.00378
-
-
-
-
-
0.0147
FP
(mg/mVs)

1.75
5.31
0.0238
0.163
0.179
0.0181
0.0161
0.0635
0.0516
0.0573
0.0370
0.125
1.01
0.303
0.308
0.0844
0.140
0.319
0.176
-
0.267
0.216

-
-
-
-
0.394
(Ib/acre/s)

0.0156
0.0473
0.000212
0.00145
0.00160
0.000161
0. 000144
0.000566
0.000460
0.000511
0.000330
0.00111
0.00900
0.00270
0.00274
0.000752
0.00125
0.00284
0.00157
-
0.00238
0.00192
-
-
-
-
-
0.00351

-------
     From Tables 4-8 and 4-9, control efficiencies were  determined  and  are
presented in Table 4-10.   The efficiency of Coherex® in controlling IP emis-
sions from  active  steam coal  is expressed  in terms of  a  lower  bound.  This
was necessary because it was not possible to obtain an IP erosion potential,
as discussed earlier.

     The two chemicals applied to active (or turned) coal surfaces appear to
be less  effective  in controlling emissions  in the smaller size ranges.   In
the case of compacted  Cambria coking coal, the control  efficiency  of the
latex binder was fairly constant over the size ranges considered.

          Figure 4-5 shows the decay in control  efficiency that was observed
for the  latex binder.  The  TP control efficiency was reduced approximately
in half  from the  second to  the fourth day,  while the IP  control  efficiency
dropped  roughly one-third.   Note  that the  measured efficiency of control
for FP  emissions  showed  an increase over the same period.   However, these
values must be considered suspect because of light loadings on the impactor
substrates.   Further tests must be performed in order to adequately charac-
terize the control efficiency for fine particulate emissions.

          From the  data presented in  Table  4-10, it appears that the  latex
binder  is more  effective  in controlling emissions from the turned surface
as the wind speed increases.  In the uncontrolled case, the TP and IP emis-
sion rate increased approximately  1000% and 500%, respectively, when the
tunnel center!ine wind speed was raised from 14.4 m/s (32.2 mph) to 17.2 m/s
(38.5 mph).   The  corresponding  increases  for the controlled surface .were
70% and  80%,  respectively.   Thus  the measured control  efficiencies for TP
and IP were substantially higher for the greater wind speed.   The FP control
efficiency also shows this trend, but this  result should also be considered
suspect  in  light of the discussion above.
                                     100

-------
                                       TABLE 4-8.   EROSION POTENTIALS FOR COAL
o
Type
Steam Coal
Steam Coal
Coking (lo-vol)
Condition
Active
Undisturbed
Turned
Control
measure
None
Coherex®
None

(m/s)
15.0
15.0
11.0
Center! ine
wind speed
(mph)
33.5
33.5
24.6
Erosion
TP
30.6
3.18
7.53
potential
IP
> 2.08
0.788
0.303
(9/m2)
FP
0.908
0.343
0.135
     coal

-------
TABLE 4-9.   TWENTY-MINUTE EMISSION RATES FOR CAMBRIA COKING COAL

(m/s)
11
14
o 17
Center! ine
wind speed
(mph)
25
32
38


TP
4.91
17.3
183

Runs H-23 - 26
IP
0.253
0.538
3.18
Net emission

FP
0.107
0.247
0.566
rate frog/

TP
-
10.9
18.3
mVs)
Runs H-28 - 29
IP
-
0.567
0.991
— 	 ^ 	 , 	 _, 	

FP
-
0.267
0.483

-------
                             TABLE 4-10.  CONTROL EFFICIENCIES FOR WIND EROSION OF COAL STORAGE  PILES
o
CJ
Control
Measure
Coherex®
Latex
Latex
Latex
Latex
Time after
Surface application
Condition (days)
Undisturbed ~ 60
Compacted 2
Turned 2
Turned 2
Turned 4
Time after
rainfall
(days)
4
2
2
2
4d
Centerline
wind Control .
speed efficiency (%)
(m/s) TP IP FP
15.0 89.6 > 62.1 62.2
17.2 70.2 91,5 87.8
14.3 37.0 c c
17.2 90.0 68.8 14.7
17.1 43.2 48.1 30.4
      0.1 inch or more.


      Control efficiencies for the latex binder are based on 20-min erosion rates.
        on erosion potentials.

   C
      No reduction in emissions observed.


      The test sites at plant H were protected from rainfall by plastic covers.
Those for Coherex® are based

-------
                                                    Conlrol  Efficiency (%)
                                                                                           00
                                                                                           o
    c
    ft)
    I
    en
                                 D  O
    o
    re
BJ  n
-o  CD
-o  "<
fD 3
Q.
   O
«-t- O
O 3
   rt
n -5
O O
Q) —<
O  ->•
-5  O
BJ  _i.
IQ  fD
fD  3
    n
-o <<

—-  o
fD  ~t>
tn
    fD
    X
    3
    Q.
    fD
                                                      D  Q  00 —I
                                                      D	1- TO  C
                                                      o  _  n;  3
                                 D  O
                                                      n
                                                      a
                                                             CO
                                                             CD


                                                            -o
                                                             3-
               "ir
                o'
                3
                                                                                   L
                                                            O   D

-------
       5.0  OPEN DUST CONTROL DESIGN, OPERATION AND COST PARAMETERS


     A limited amount of design/operation and cost data were collected from
the three plants at which testing was performed during this study.  The ques-
tionnaires  shown  in Appendix B were completed  by personnel  representing
Armco-Middletown, Armco-Houston, and Bethlehem-Burns Harbor.   Since the di-
stinction between design and operational data is difficult to verify from a
questionnaire,  these  data will simply  be  designated  as design/operation
data.  Also shown on the questionnaire were cost data.

     This section contains  the results of the  questionnaire as well as a
theoretical treatment of fugitive dust control cost-effectiveness analysis.

5.1  DESIGN/OPERATION PARAMETERS

     The most  important  design/operation parameters are application  inten-
sity,  frequency and dilution ratio, if applicable.   These variables,  as
determined  from the questionnaire, are summarized  in Tables 5-1 through
5-4.   Many miscellaneous characteristics of the control system are presented
in Appendix C.

5.2  COST PARAMETERS

     Costs  associated with  purchase,  installation,  operation, and mainte-
nance  should  all be quantified in  order to evaluate the cost-effectiveness
of a given open dust control  technique.   These costs,  as  determined
from the  questionnaire,  are shown in  Table  5-5.  To  facilitate compari-
sons between control techniques, the cost data in Table 5-5 were placed on a
dollar per unit of treated source extent and on a dollar per unit of actual
source extent in Tables 5-6 and 5-7, respectively.

5.3  THEORETICAL COST-EFFECTIVENESS ANALYSIS

     The most informative method for comparing cost data is on a cost-effec-
tiveness basis.  Cost-effectiveness  in air pollution  control is defined as
dollars expended per mass of emissions reduced:

                            -  D
where:    CE = cost-effectiveness ($/lb of emissions reduced)
           D = control technique cost ($/year)
          ER = emissions reduction (pound of emissions reduced/year)
                                  105

-------
                TABLE 5-1.  DESIGN/OPERATION PARAMETERS - PAVED ROADS
  Plant
  Control
Application
 intensity
Application
 frequency
  Middletown Works
  Houston Works
  Vacuum sweeper
        or
  Plusher
  Broom sweeper
      and
  Plusher
12,000 cfm vacuum
  blower capacity
1,800 gal/mile at
  50 psig

NA

0.48 gal/yd2 under
  unknown pump
  pressure
Once per 2 or 3 days

Once per 2 or 3 days


Once per 3 days

Once per 3 days
               TABLE 5-2.   DESIGN/OPERATION PARAMETERS - UNPAVED ROADS
Plant
Control
Application
intensity
Dilution ratio
chemical: water
Application
frequency
Middletown Works    Coherex®
Houston Works
            0.19 gal/yd2
            (initial ap-
              plication)

            0.28 gal/yd2
            (remaining ap-
              plications)
Watering    0.48 gal/yd2
             1:5
                                                     1:8
                          Once every 2 days
                                  to
                          Once every 6 weeks

                          Once every 3 days
                                       106

-------
  TABLE 5-3.   DESIGN/OPERATION PARAMETERS - UNPAVED PARKING LOTS AND EXPOSED AREAS
Plant
Control
Application
intensity
Dilution ratio
chemical: water
Application
frequency
Middletown Works    Coherex®
910 gal/acre
(initial ap-
  plication)

1,364 gal/acre
(remaining ap-
  plications)
1:5
                                                     1:8
                                                                  2 or 3 times/year
                                       107

-------
                            TABLE 5-4.   DESIGN/OPERATION PARAMETERS—STORAGE PILES
Plant Control
Middletown Watering
Works


Houston Watering
Works
__j
o
CD
Material
Coal
Limestone
Taconite
Coal (main pile)
Coal (surge pile)
Application
intensity
0.8 gal /yd*
N/A
N/A
1.4 gal /yd2
1.4 gal /yd2
Dilution
ratio Application
chemical : water frequency
Once every 2 days
N/A
N/A
300 days/yr
(when rainfall < 1/4
300 days/yr
(when rainfal 1 < 1/4




in
in
Burns Harbor    Latex
Coal
1.5 gal/yd2
1:35
Once per week

-------
TABLE 5-5.   SUMMARY OF  OPEN DUST CONTROL  COST DATA
Plant
Middle town
Works






Houston
Works






Burns
Harbor
Source
Paved roads

Unpaved roads

Coal storage piles

Limestone and taconite
piles
Unpaved parking lots
and exposed areas
Paved roads

Unpaved roads
Main coal piles

Surge coal pile

Lo-vol coal pile
Control
2 Vacuum sweepers
Flusher
Coherex, dis-
tributor truck
and storage tanks
Stationary water
spray
Water truck
(1,500 gal. cap.)
Coherex, distribu-
tor truck
Broom sweeper
No. 1
Broom sweeper
No. 2
Flusher
Water truck
Stationary water
spray
Stationary water
spray
Latex binder
(sprayed by
Purchase and Estimated
installation Year of lifetime
cost ($) purchase (yrs)
144,000 1980
68,000 1976
100,000 1980

350,000 1980

J 33,000 | 1979
18,000 1978
20,000 1980
j 34,000 1978
217,000 1975

72,200 197b

58,100
(chemical only)
5
10
7

20

)'
5
5
7
20

20

-
1980
Operation and
maintenance
costs ($)
214,000
57,000
287,000

1,000

54,000
224,000
65,100
57,000
52,300
15,400
8,600

8,600

-
1980 Ireated
source extent
2,020 miles
5,080 miles
1,630 miles

1,650 acres

1,810 acres
NA
888 miles
888 miles
1,780 miles
448 miles
2,150 acres

110 acres

N/A
Actual
source extent
16.9 miles

7. I miles

9 acres

10 acres
NA
14.6 miles

4.3 miles
7.2 acres

0.4 acres

N/A
    subcontractor)

-------
               TABLE  5-6.   OPEN DUST CONTROL  COST COMPARISON  IN DOLLARS PER UNIT
                              OF TREATED SOURCE  EXTENT
	 — - ,
Plant
Middle town
Works










Houston
Works








Burns
Harbor
Source
Paved roads


Unpaved roads


Coal storage piles

Limestone and taconite
piles
Unpaved parking lots
and exposed areas
Paved roads




Unpaved roads
Main coal pi les

Surge coal pile

Lo-vol coal pile

Control
2 Vacuum sweepers

f lusher
Coherex, distributor
truck and storage
tanks
Stationary water
spray
Water truck
(1,500 gal. cap.)
Coherex

Broom sweeper
No. 1
Broom sweeper-
No. 2
n usher
Water truck
Stationary water
spray
Stationary water
spray
Latex Binder

1980 Annual ized
Unit of
treated
source extent
mile

mi Ic
mile


acre

acre

acre

mile

mile

mile
mile
acre

acre

acre

costs ($ per unit
Purchase and
instal lation
14.30

1.34
8.77


10.60

2.60

NA

4.05

4.50

2.13
2.49
5.07

32.70

N/A

of treated source
Operation
and
maintenance
106

117
176


0.61

29.8

NA

73

64

29
34
4

78

N/A

extent)
Total
120

118
185


11.2

31.1

NA

77.1

68.5

31.1
36.5
9.07

110

N/A


Not scaled to 1980 cost.

-------
               TABLE 5-7.   OPEN  DUST CONTROL COST  COMPARISON IN DOLLARS  PER UNIT
                              OF  ACTUAL SOURCE  EXTENT

Plant
Micldletown
Works





lloustbn
Works





Burns
Harbor-
Source
Paved roads

Unpaved roads
Coal storage pi les
Limestone and taconite
pi les
Unpaved parking lots
and exposed areas
Paved roads


Unpaved roads
Main coal piles
Surge coal pile
Lo-vol coal pile
Control
2 Vacuum sweepers
F lusher
Coherex, distributor
truck and storage
tanks
Stationary water
spray
Water truck
(1,500 gal. cap. )
Coherex
Broom sweeper
No. 1
Broom sweeper
No. 2
Flusher
Water truck
Stationary water
spray
Stationary water
spray
Latex Binder
($ per yi
Unit of
actual
source extent
mi le
mile
mile
acre
acre
acre
mile
mile
mile
mile
acre
acre
acre
1980 Annual! zed costs
>ar per unit of actual source extent)
Purchase and
installation
1,700
400
2,000
1,940
470
NA
240
270
260
260
1,510
9,000
N/A
Operation
and
maintenance
12,700
3,370
40,400
110
5,400
NA
4,460
3,900
3,580
3,580
1,190
21,500
N/A
Total
14,400
3,770
42,400
2,050
5,870
NA
4,700
4,170
3,840
3,840
2,700
30,500
N/A
Not scaled to 1980 cost.

-------
     Control  technique cost  includes  several  components shown graphically
in Figure 5-1.   Purchase and installation costs must also include costs for
freight,  tax  and borrowed money.   The operation and maintenance costs should
reflect increasing frequency of repair as the equipment ages along with in-
creased costs for parts,  energy  and labor.   Costs recovered from tax laws
should also be considered.   The slopes of the lines in Figure 5-1 have little
significance  except  to show an increasing or decreasing cost with time.  The
slope of the  loan interest tax deduction assumes the equipment was funded
by a loan to  be repaid on an installment basis beginning at the time of the
loan.  The equipment  could have  been funded  by  a  bond program with  bonds
maturing at a variety of times causing the interest paid to increase, remain
level, or decrease with time in a continuous or step fashion.

     Cost-effectiveness also includes the emissions reduction achieved.  Re-
sults from this study support the logical conclusion that the emissions re-
duction of a  specific control technique decays with time until the technique
finally yields  no reduction  over the uncontrolled state.  This can be de-
fined as the  life of the control  technique,  not to be confused with the life-
time of the equipment.

     The remaining portion of this section presents a simplified mathematical
model for  comparing  the  costs of one control technique with another.  The
question being  asked  determines  the basis on  which the cost  should  be  com-
pared.   The  following list  presents  six questions which  can be asked:

     1.   Given a specific source at a specific plant and given a specific
          control technique, what is the most cost-effective number of ap-
          plications that  should be made?

     2.   Given a specific source at a specific plant and given a specific
          control technique, what is the cost to achieve a given emission
          reduction?

     3.   Given a specific source at a specific plant, what  is the most
          cost-effective control  technique that can be used?

     4.   Given a specific source at a specific plant, what  is the  least
          expensive control  technique that can be  used to achieve a  given
          emission reduction?

     5.   Given a specific plant, what is the most  cost-effective source
          that  can be controlled?

     6.   Given a specific plant, what is the least expensive source which
          can be controlled  to achieve a given emission  reduction?

5.3.1  Cost-effectiveness  Optimization Analysis

     The answers  to questions 1, 3  and 5 require an optimization analysis.
The  following simplified mathematical model  can  be used  to answer questions
1,  3 and 5.
                                  112

-------
o
u
LLI


O
u

z
                Equipment, Installation,  Freight, Tax, and Interest
Depreciation Tax Deduction
                       LIFE OF  EQUIPMENT
                                                                                Scrap


                                                                                Value
          Figure  5-1.   Graphical presentation  of open dust control costs.
                                         113

-------
     As shown above,  the cost-effectiveness of any given combination of con-
trol  technique, equipment and  implementation  plan for a given source at a
given plant is:
                    «   •    V
     where     CE   =    cost-effectiveness ($/lb  of  emissions  reduced)
                D   =    control  technique cost ($/yr)
               ER   =    emissions reduction  (Ib  of  emissions reduced/yr)
The control technique cost can be written as follows
                    0    =    PI  + MO
     where     PI   =    annual  purchase  and  installation cost  ($/yr)
               MO   =    annual  operating  and  maintenance cost  ($/yr)
The annualized purchase and installation cost for a given device can be ex-
pressed
                    PI   =
     where     IPT  =    total purchase and installation cost ($)
               Y    =    estimated life of equipment (yr)
The annual operating cost can be expressed
               MO   =    AMO  x    TSE
     where     AMO  =    maintenance and operating cost per unit of
                          treated source extent ($/unit of treated
                          source extent)
               TSE  =    treated source extent per year (units of
                          treated source extent/yr)
     The  annual  treated source extent is  further  dependent  on  the  actual
amount of  source extent in the plant and the  number of treatments per year:
                    TSE  =    ASE  x  NT
     where     ASE  =    actual  source extent in plant (units of source
                          extent)
               NT   =    number  of treatments  per year (treatment/yr)
     The  intial  purchase  and .installation cost  can also be dependent
on the treated source  extent  as  follows
                     IPT  =     UPT  x    If
                                   114

-------
     where          UPT  =    initial purchase and installation cost per
                               device ($/device)

                    MSE  =    maximum source extent which can be treated
                               per device per- year (units of treated source
                               extent/device/yr)

     The generalized expression for control technique cost can now be written
as follows
                    D    =                     +  (AMO x ASE x NT)
     All the parameters in the generalized expression for control technique
cost can be fixed for a given technique and plant with the exception of the
number of  treatments  per  year which must be calculated.  The  lifetime of
the device  is  assumed a constant in this analysis.  The  validity of this
assumption is explored at the end of this analysis.

     The number  of  treatments per year can be calculated if one knows the
functional form  for  the decay of control efficiency for a given technique
with time.  The optimum number of treatments can then be calculated by mini
mizing the cost effectiveness for a given control technique.

     Before minimizing  the  cost-effectiveness  function,  one first writes
the generalized expression for emissions reduction which appears in the de-
nominator  of the cost effectiveness function.  The  emissions reduction can
be expressed as follows

               ER(t)     =    CEF(t) x EF x SE

     where     ER(t)     =    instantaneous emissions reduction as a
                               function of time (Ib/yr)

               CEF(t)    =    control  efficiency fraction as a function
                               of days after application

               EF        =    emission factor (Ib/unit of source extent)

               SE        =    source extent (units of source extent/yr)
                                                               i

The emission reduction can further be  defined as


                                         365/NT
                                  115

-------
     The cost-effectiveness  function  can  now  be minimized and  the  op-
timum number of  applications  per  year calculated.   It is obvious that  if
just emission reduction were to be maximized, an infinite number of treat-
ments would be  required.   If just cost were to  be  minimized,  then zero
treatments  per year would be required.

     The minimization  of CE  which  requires the  optimum concentration
of both cost and emission reduction  can then be determined assuming

                         d (CE)  _  o
                         d (NT)     u


Before the actual  calculations  to minimize CE can occur, the form of the
control efficiency decay function  must be determined.   The following  analyses
consider 3 different forms  of the control  efficiency  decay function:   (1)
linear decay (2) exponential decay,  and (3) exponential followed by linear
decay.

     If it is assumed that the control efficiency fraction decays linearly
from 1.0,  then
                    CEF(t)  =  -bt

          and
                                              365/NT
                    en   _    EF x SE x NT   i      f ,.  ,-,>,  ,+
                    ER   =	   o      (-bt +1)  dt
                              EF x SE x NT   /-b  /365\ 2 .  365
                                   35B\ 2  \~NT/      N

                         =    EFxSE        (l-^   ^65)

The cost-effectiveness function can then be written

                              A (NT)	
                    CE   =
                              EF x SE /1-b 365\
                                         2 "NT/
          where     A    =    UyTxx^gE  + (AMD x ASE)


The value of NT which yields the minimum cost-effectiveness function can be
derived as follows:

                       EF x SE/l-b 365\A - A(NT)(EF)(SE)b  365
          d (CE) _ n =        \  I "NT/          __     1
                 -
                                  116

-------
Solving for NT yields

                                             b 365
          A x EF x SE % Z£  =  EF x SE ti - 3 -^
                   b 365  _  ,   b 365
                   2 ""NT  '  l ~ 2 "NT

                     365  _  ,
                      NT  =  b  365
Then the minimum cost-effectiveness function is

          PP     _  A  365  b	
           -min  "  EF  x  SE /I - b 365 \
                                         1 /
          CE     _  365  A x b
            min     \ x  EF x SE


     One interesting conclusion is that the most cost-effective approach will
yield only a 50% reduction in emissions over the uncontrolled state.  Another
interesting conclusion is that the cost-effectiveness is minimized when the
control technique efficiency is allowed to decay to zero.  In order to prove
this, define the lifetime of the technique (LT) as the time at which CEF = 0.

Then one may write

                    0  =  -b  (LT)  +  1

                    LT =  \  (days)


But  the  optimum  time betewen applications  is 365/NT = 1/b.  Thus  the opti-
mum  time between applications  is  the  lifetime  of the control  technique and
the  optimum number of applications can be expressed

                    NTopt = 365/LT

     It is now assumed that the control efficiency decays exponentially
from 1:


                    CEF(t)  =  e ~bt
                                  117

-------
The emissions reduced can be expressed as

                    PR  -  EF x SE x NT    365/NTp -bt  ,,
                    cK  ~  - 365 -   /      e     dt
                                          0

                                                         " 365/NT
                                SE x NT /   1 exp  (-bt)
                               365      \   b
                                                          o
                              x SE x NT ( -1 exp (-b365/NT) + 1
                               365      ^  b                  b~
The cost effectiveness function can then be written

                       A x NT x 365
The value  of  NT which yields the miminum cost-effectiveness function can
then be derived as follows
     d (CE) _ Q _ A x EF x SE x NT /    1 avn    b365
     TTFTT ~u	jm	 \    E exp  "  irr
                                                        +  E
                - A x NT EF,X_SE ( - 1 NT ("b)_365  e ~b 365/NT    1 a ~b  365/NT .
                  n A 11 I    -jet;   I   K N I   _  KlT2	  e            ~  E
                       x SE x NT  /_  1 „„_  /-b  365\  ,  1
                         365



Solving for NT yields


A x NT x EF x SE   / 1 /  1
(4"P(^77T
                     1(1              \    -  b  365/NT  ,  1 \ _  A  x  EF  x  SE  x  NT
                     b\fiTxbx365 + lJe                EJ -- 3S5 -  x
                                                                  '  b/365     1
                                                                           +  E
                          b x 365   e  -b  365/NT  =  0


                               exp  (-b 365/NT)  =  0
     Since NT = «,  there is  no  finite  value  of  NT which yields a  solution  to
this equation.   This  is  because the  control  efficiency, when expressed  as  an
exponential  decay,  never goes to zero.  To put it another way,  the control
technique has an infinite lifetime.   In  order  to circumvent this  physical
implausibility,  assume that at some point in time called d,  the  functional


                                  118

-------
form of the decay changes to a straight line function with a slope equal to
the slope of exponential decay function at t = d.  The straight line function
must also pass through (0, LT).  The slope of the exponential decay function
at time d is:

                    c = -be'bd

The straight line function can then be defined as

                    CEF(t) = -be"bdt + f

Therefore                  ,  ,
                    f = be"bd (LT)
Consequently,
                    CEF(t) = -be"bd (t - LT)
Since the  values of the  CEF  for both  functions are  identical at d,  one may
solve for d

          e-W  =  -be-bd (d . LT)

             d  =  LT-i


Thus

       CEF(t)  =  -be-b + l t + be'b(LT) + l (LT)

Therefore both functions comprising the decay function are defined when the
decay constant, b, and  the life of the control technique,  LT, are  known.
For simplicity in the following solution,  the following definitions will  be
used:
               d  =  LT-1
The equation for the emission reduction can then be written
     ER = EF xE x NT  ;d e-btdt + j-365/NT (. ct + f) ^

             x SE x NT     1  -bd ,1   c  /365\2 .  cd2     .  . 365    f ,
                -   ' F e    + b " 2  hnv  + 1      + f -FT  ' fd
                                  119

-------
The cost-effectiveness function can now be written
          CE  =
                                           A (NT)
                 EF x SE x NT   /   1 -bd .  1   c  /365 \ *   cd* .  - 365
                 	355	   \"be    + b~2
The value of NT which minimizes the cost-effectiveness function can then be
calculated as follows
or
       365  _  _ 3652
       Iff2 ~  c "NT3
Therefore
Substitution of the definitions of c and f yields

                  ,  al - b(LT)
                - b e
          NT
            opt           1 - b(LT)
                  b  LT  e

          KIT    - 365
          NTopt - TT


The minimum value  of the  cost-effectiveness for the case where the control
efficiency decays  first in an exponential and then in a linear fashion can
be expressed as follows
                                A
                                    LI
                                                            365\

          EF x SE x       -   .         + 1 - I e1 '
               365

               + b .1 - b(LT)   LT   1  % b(LT) .1 - bCLT)
               - b(LT) e1 -       (LT -  )
                                  120

-------
This reduces to

                             A x b x 365
          CE
            min     EF x SE (1 - 1/2 exp (1 - b(LT)))


     From these analyses one can see that, in all three cases, the cost-effec-
tiveness function  is  minimized when  the  control  efficiency  of the  water or
chemical is  allowed  to decay to zero.  This is easily understood when  one
considers that  a  fixed amount of money  is  expended  for  each application of
water or chemical  dust suppressant.  The most cost-effective approach is to
gain all the  emission reduction possible for this fixed expenditure.   The
maximum aggregate  emission  reduction occurs when  the  lifetime of the tech-
nique is reached.   In other words,  when the control efficiency equals zero,
the maximum emission reduction has  been gained and no further emission  reduc-
tion will occur.

     While the  cost-effectiveness  function is minimal at the lifetime  of
the control technique in all three  cases, this does not mean that the value
of the minimum cost-effectiveness function is identical  in all three cases.
Indeed, this  value  depends  on all  the costs related to the equipment,  the
slope or decay  constant for the control efficiency function,  the  form  of
the control efficiency decay function, and the emissions from the source in
the uncontrolled  state.   Consequently,  while the user  of these equations
knows the most  cost-effective  number of applications to make for  a  given
control, he should still use the appropriate equation for minimum cost-effec-
tiveness to determine which combination of technique and equipment will  yield
the lowest minimum cost-effectiveness.

     A second level of complexity can be introduced to this analysis by as-
suming that there are some fixed costs which are not dependent on the number
of applications.  In this case,  the cost function can be written

               D  =  B (NT) + g

     where

               g  =  fixed cost which are not dependent on the number of
                      applications  ($/yr)

This may occur, for  example,  when  the equipment  is already purchased and
installed without  regard  for the optimum number of applications necessary.
For this case,  g  equals the purchase and installation cost while B equals
only the operating  and maintenance cost.   The cost-effectiveness function
in this case can also be minimized  but the minimum value will not be as  low
as the  case  where the size and number of the devices  were also optimized.

     It should be  pointed out,  however,  that one never need purchase equip-
ment without optimization in mind.   Given the lifetime of a control technique,
one can calculate  the number of applications per year.   Given the number of
applications, one  can calculate  the total  treated source extent per year (TSE).
Then one can  calculate the  number of devices of given size  that need to be
purchased by dividing TSE by MSE (the maximum source extent that can be  treated
per device per year).

                                 121

-------
     The life  of  the  equipment Y can be  calculated  using the following
equation

               v _ SEL x (TSE/MSE)   _ SEL
               T ~      TSE         " MSE

where       SEL  = source extent which can be treated over the lifetime of
                     the device (units of source extent per device).

The term TSE/MSE represents the number of devices needed assuming full  utili
zation.   From the above equation, one can see that at full utilization, the
lifetime of  each  device  is a constant.   Since this was the assumption in
all the previous  analyses, the previous calculations are  applicable to the
case of maximum utilization.

     Substituting the  above  expression  for the lifetime  of the equipment
into the previous expression for annual  cost yields

          D = UPT *£fSE x NT + (AMD x ASE x NT)


     For the case where one or more devices are desired at a utilization,  e,
which is less  than  100%, the lifetime of the devices can be calculated as

          v - SEL x (TSE/(e x MSE)) _   SEL _
          T ~         TSE             e x MSE

Again the  lifetime  of the devices is a constant and the previous analyses
apply.  The expression for the annual cost for this case  is
              UPT    SE X NT + AMO x ASE x NT
One can see that the annual cost is identical whether or not maximum utili-
zation occurs.  At less than maximum utilization, more devices are required
but each one  lasts longer, thus yielding the same annual cost.

     Finally,  consider  a  limiting case in which one device can accomplish
the job at less than maximum utilization.   The lifetime of this single device
can be calculated as follows:
                    Y = SEL x (TSE/(e x MSE))
                                TSE

However, it is  known that  in this case

                    TSE =  e x MSE
Therefore

                    v - SEL
                    Y -TSE   •
                                   122

-------
Substituting this expression in the equation for annual cost yields

          D = U"T "* X "SE" * AMD x ASE x NT
which reduces to
          D = UPT *SE x NT + AMD x ASE x NT
Again, this  is  the  same  expression  for  annual  cost  as when  several  devices
were selected at maximum and  less than  maximum utilization.  Assuming  that
all three  of these  options were applied to the same job (TSE = constant),
we can see that in the first two cases,  the annual cost would be identical,
but in the third case, the  single device would have  to  be larger or faster
in order to  accomplish  the same job for which many devices  were required.
This implies that UPT, SEL, and AMD would probably differ.   Using the mini-
mum cost-effectiveness equation  for a linear decay in control  efficiency,
one can see  that  for control  of a  given source at  a given  plant, cost is
minimized  when  the  value of (UPT/SEL) + AMD  is  a  minimum.   Cost-effective-
ness is minimized when the value of b(UPT/SEL + AMD) is a minimum.

     In conclusion,  the cost-effectiveness  equations developed in this sec-
tion can be  used in  analyzing costs  for a single  control technique  and for
comparing costs of various alternative control techniques for a given plant
and source.  The equations can also be used to compare the same control tech-
nique at two different  plants.   In the  first case,  the equations indicate
that cost should be  compared on the basis of dollars per unit of source ex-
tent treated.  In the second case,  the cost should be compared on the basis
of dollars per  actual  unit of source extent in the plant.   However, while
cost comparisons are informative, it is  the cost-effectiveness  values which
are most important in terms of decisions about which open dust control  tech-
nique is best.

5.3.2  Minimum Cost  Calculations

     The answer to questions 2,  4 and 6  listed in  Section 5.3 do not require
an optimization analysis,  but rather require  only  a  simple calculation.
The following analysis shows  how to determine the least expensive  control
technique to achieve a given emission reduction from a given source.

     The cost-effectiveness function for control of open dust emissions from
a given source at a  given plant is:

               TF -   D
               CE ~  ER


     where:    ER =  fixed value of  desired  emission  reduction (T/yr).
                                  123

-------
     From previous analyses, the cost per year can be expressed:

               n - UPT x ASE x NT ^ ,...,,   .cc   ..,.
               D   - Y x MSE -   (AM  x ASE x NT)


     Since the  emission  reduction  is  fixed in this  particular  problem,  the
number of applications necessary to achieve that reduction can be calculated
from the following equation:
               ER = EF x SE x
               hK   hh x bt x
                                365/NT

                                              dt
                                    365/NT
     For the case where the control efficiency fraction decays linearly from
1.0, the emission reduction is:

               ER = EF x SE x (1 -
     The number of applications per year necessary to achieve a given reduc
tion can then be expressed:
               NT ,   x 365 x (1 -
     Then the expression for the dollars expended per year is:

               D =  UTX£ + (AMO X ASE) x    x 365 x (1 -
     Thus, for all control techniques with  a  linear  decay  in  control  effi-
ciency, the cost  to  achieve  a given emission  reduction  can be  calculated
for each control  technique using the above equation.   The most cost-effective
technique is then the one with the lowest total annual cost (D).
                                  124

-------
                                SECTION 3m £ . O

                                REFERENCES


1.    Bonn, R.,  T. Cuscino, Jr., and C. Cowherd,  Jr.  Fugitive Emissions from
     Integrated Iron and Steel Plants.  EPA-600/2-78-050, U.S. Environmental
     Protection Agency, Research Triangle Park,  North Carolina, March 1978.
     276 pp.

2.    Cowherd, Chatten, Jr.,  Russel  Bohn,  and  Thomas  Cuscino,  Jr.   Iron  and
     Steel Plant Open  Source Fugitive Emission Evaluation.  EPA-600/2-79-
     103, U.S.  Environmental  Protection  Agency,  Research Triangle Park,
     North Carolina, May 1979.  139 pp.

3.    Cowherd, C. , Jr., C. M.  Maxwell,  and D.  W. Nelson.   Quantification of
     Dust Entrainment from Paved Roads.   EPA-450/3-77-027, U.S. Environmental
     Protection Agency,  Research Triangle Park, North Carolina, July  1977.
     89 pp.

4.    Cowherd, C. , Jr.,  K.  Axetell,  Jr.,  C.  M. Guenther  (Maxwell),  and  G.
     Jutze.   Development  of Emission  Factors for  Fugitive Dust Sources.
     EPA-450/3-74-037,  U.S.   Environmental  Protection Agency,  Research
     Triangle Park,  North Carolina,  June  1974.  190 pp.

5.    Cuscino, T., Jr.   Taconite Mining Fugitive  Emissions Study.   Final
     Report,  Midwest  Research Institute  for  Minnesota  Pollution Control
     Agency,  June 7, 1979.

6.    Bohn, R, T. Cuscino, Jr., D.  Lane, F. Pendleton, and R.  Hackney.   Dust
     Control  for Haul  Roads.  U.S.  Bureau of Mines, Minneapolis, Minnesota,
     February 1981.

7.    Gillette,  D.   Tests  with a Portable Wind Tunnel for Determining Wind
     Erosion  Threshold Velocities.   Atmospheric  Environment,  12:2309 (1978).

8.    Soo, S.  L., J.  C.  Perez, and S. Rezakhany.   Wind Velocity Distribution
     Over Storage Piles  and Use of Barriers.   Proceedings:   Symposium  on
     Iron and Steel  Pollution Abatement Technology for 1980 (Philadelphia",
     Nov~, 1980), EPA-60Q/9-81-Q17. U.S.  Environmental  Protection  Agency,
     Research Triangle Park, North Carolina, March 1981.

9.    Davies,  C.  N.  The  Entry of Aerosols  in Sampling  Heads and Tubes.
     British  Journal of Applied Physics, 2:921 (1968).
                                  i -X

-------
                                SECTION

                                 GLOSSARY


Activity Factor - Measure of the intensity of aggregate material disturbance
     by mechanical forces in relation to reference activity level defined as
     unity.

Application Frequency - Number  of  applications  of a control measure  to  a
     specific source per  unit  time;  equivalently, the inverse of time be-
     tween two applications.

Application Intensity - Volume  of  water or chemical solution applied per
     unit area of the treated surface.

Control Efficiency - Percent decrease  in controlled  emissions from  the un-
     controlled state.

Cost-Effectiveness - The cost of control per unit mass of  reduced particu-
     late emissions.

Dilution Ratio - Ratio  of the number of parts of chemical  to the number  of
     parts of solution,  expressed in percent (e.g.,  one part of chemical  to
     four parts of water corresponds to a 20% solution).

Dry Day - Day without measurable (0.01 in.  or more)  precipitation.

Dry Sieving - The sieving of  oven-dried aggregate by passing it through  a
     series of screens  of descending opening size.

Duration of Storage - The average  time that a unit  of aggregate material
     remains in open storage,  or the average pile turnover time.

Dust Suppressant - Water  or chemical  solution which, when  applied  to an
     aggregate material, binds suspendable particulate to larger particles.

Erosion Potential -  Total  quantity of erodible particles, in any size range,
     present on  the surface (per unit  area) prior to the onset  of erosion.

Exposed Area,  Effective  -  The total exposed area reduced by an amount which
     reflects the sheltering effect of buildings and other objects  that re-
     tard the wind.

Exposed Area,  Total  -  Outdoor ground area subject to the action of  wind and
     protected by little or  no vegetation.
                                  1-28-

-------
Exposure - The point value of the flux (mass/area-time) of airborne particu-
     late passing through the atmosphere, integrated over the time of mea-
     surement.

Exposure, Integrated - The result of mathematical integration of spatially
     distributed measurements of airborne particulate  exposure downwind of
     a fugitive emissions source.

Exposure Profiling - Direct measurement  of  the  total  passage of airborne
     particulate immediately downwind of the source  by means of simultaneous
     multipoint isokinetic sampling over the effective cross-section of the
     emissions plume.

Exposure Sampler - Directional  particulate sampler with settling chamber and
     backup filter, having variable flow control to provide for isokinetic
     sampling at wind speeds of 1.8 to 8.9 m/s (4 to 20 mph).

Friction Velocity - A measure of wind shear stress on  an exposed surface as
     determined from the slope of the logarithmic velocity profile  near the
     surface.

Fugitive Emissions - Emissions not originating from  a  stack, duct,  or flue.

Load-in - The addition of material  to a storage  pile.

Load-out - The removal of material  from a storage pile.

Materials Handling - The  receiving  and  transport of raw, intermediate and
     waste materials,  including barge/rail car unloading, conveyor transport
     and associated conveyor transfer and screening  stations.

Moisture Content - The mass portion of an aggregate  sample consisting of un-
     bound moisture as determined from weight loss in  oven drying.

Normalization - Procedure that  ensures that  emission reductions not  attri-
     butable to a control measure are excluded in determining an efficiency
     of control.

Particle Diameter, Aerodynamic  - The  diameter of a  hypothetical  sphere of
     unit density  (1  g/cm3)  having  the same terminal  settling velocity as
     the particle  in  question,  regardless of its geometric  size, shape and
     true density.

Particle Drift Distance - Horizontal distance from point of particle injec-
     tion into the atmosphere to point of removal by contact with the ground
     surface.

Particulate, Fine - Airborne particulate smaller than 2.5 urn in aerodynamic
     diameter.

Particulate,  Inhalable - Airborne particulate smaller than 15 urn in aerody-
     namic diameter.

-------
Participate,  Total - All airborne participate regardless of particle  size.

Particulate,  Total Suspended - Airborne particulate matter as measured by a
     standard high-volume (hi-vol) sampler.

Precipitation-Evaporation Index - A climatic  factor  equal  to 10 times the
     sum of 12  consecutive  monthly  ratios of precipitation in inches over
     evaporation in inches, which is used as a  measure of  the annual  aver-
     age moisture of  exposed  material  on a  flat surface of compacted ag-
     gregate.

Precision Factor  (two  standard  deviations)  - The precision factor (f) for
     an emission  factor  equation  is defined such that the 95% confidence
     interval  for a predicted emission factor value (P) extends  from P/f
     to Pf; the precision factor  is determined  by exponentiating  twice the
     standard deviation  of  the  differences  between the natural  logarithms
     of the predicted and observed emission factors.

Road,   Paved - A  roadway  constructed of rigid surface  materials,  such as
     asphalt,  cement,  concrete,  and brick.

Road,  Unpaved - A roadway constructed  of nonrigid surface materials  such
     as dirt, gravel  (crushed stone or slag),  and oil and chip surfaces.

Road Surface Dust Loading -  The mass of loose surface dust on a paved road-
     way, per length of roadway, as determined by dry vacuuming.

Road Surface Material  - Loose material  present on the surface of an unpaved
     road.

Roughness Height  - A  measure  of the roughness  of  an exposed surface or
     storage pile as  determined from the y-intercept  of  the logarithmic
     velocity profile near the surface.

Silt Content - The mass  portion of  an  aggregate sample smaller than 75 mi-
     crometers in diameter as determined by dry sieving.

Source, Open Dust - Any  source  from which emissions are generated by the
     forces of wind and  machinery acting on exposed aggregate materials.

Spray System - A  device  for applying a  liquid dust suppressant in the form
     of droplets  to an aggregate  material for the purposes of controlling
     the generation of dust.

Storage Pile Activities - Processes associated with aggregate storage piles,
     specifically, load-in,  vehicular  traffic  around storage piles,  wind
     erosion from storage piles, and load-out.

Surface Erodibility - Potential  for wind erosion losses from an unsheltered
     area,  based on the percentage of erodible particles  (smaller than 0.85 mm
     in diameter) in the surface material.
                                  333.

-------
Surface Stabilization - The formation of a resistive crust on an exposed ag-
     gregate surface through  the  action of a dust suppressant, which sup-
     presses the release of otherwise suspendable particles.

Vehicle, Heavy-Duty - A motor vehicle with a gross vehicle travelling weight
     exceeding 30 tons.

Vehicle, Light-Duty - A motor vehicle with a gross vehicle travelling weight
     of less than or equal to 3 tons.

Vehicle, Medium-Duty -  A motor vehicle with a gross vehicle travelling weight
     of greater than 3  tons, but less than 30 tons.

Windbreak - A natural or man-made object which reduces the ambient wind speed
     in the immediate locality.

-------
              SECTION a.o •
ENGLISH TO METRIC UNIT CONVERSION TABLE
English unit
gal /yd*
Ib/T
Ib/vehicle mile
Ib/acre yr
Ib
T
mph
mile
ft
acre
Multiplied by
4.53
0.500
0.282
112
0.454
0.907
0.447
1.61
0.305
0.00405
Metric unit
£/m2
kg/t
kg/vehicle km
kg/km2 year
kg
t
m/s
km
m
km2

-------

-------
                             APPENDIX A

        DATA COMPILATION FROM MATERIALS HANDLING FLOW CHARTS
     Tables A-l  through A-10 summarize material  handling operations  for
raw and intermediate materials  at the 10 surveyed plants.   Table A-ll
summarizes slag  handling operations  at the 10 surveyed plants.
                                A-l

-------
          TABLE  A-l.   RAW AND  INTERMEDIATE  MATERIAL HANDLING AT THE ARMCO  MIDDLETOWN  PLANT  IN 1978
Handling method and
Origination
Material mode
Coal Railcar unloading
by rotary dump
(1,123.000 ST)
Kailcar unloading
by bottom dump
(634,000 ST)
Coke Coke ovens
(1,460,000 ST)
Iron Ore Pellets (iailcar unloading
by rotary dump
(1,508,000 ST)
Unagglomerated Iron Railcar unloading
Ore ' by rotary dump
(14,000 ST)
I Limestone/Dolomite/ Railcar unloaded by
ro gravel bottom dump
Transfer
stations
1 transfer
station
(2.057,000 ST)
1 transfer
station
(1,007,000 ST)
2 transfer
stations
(1,508,000 ST)
2 transfer
stations
(14,000 ST)
Hone
Storage
load- in
Conveyor
stacker
(1,234,000 SF)
None
Clamshell
bucket
(1,508,000 SO
Clamshell
bucket
(14,000 SI)
Hone
Storage
Open storage
(1,234,000 SI)
None
Open storage
pile
(1.508,000 ST)
Open storage
pile
(14,000 ST)
None
amount of material handled
Storage
load-out
Bucket wheel
reclaimer
onto conveyor
(1,234,000 ST)
None
Clamshell
bucket to
conveyor
(1,508,000 ST)
Clamshell
bucket to
conveyor
(14,000 ST)
Hone
Transfer
stations
2 transfer
stations
(1.423,000 SO
1 transfer
station
(634,000 ST)
1 transfer
station
(after
screening)
2 transfer
stations
(1,357.000 SO
None
Hone
Screening
Screening
(2,057,000
Screening
(1,460,000
Screening
3 transfer
stations
(1,357,000
None
Hone
Crushing

ST)
Breaker and
1 1, mime r Mil)
(634,00(1 SI)
None
si)
and None
SO
None
Nune




                  to conveyor to
                  stock house bins
                  (228,000 ST)
Sinter
Sinter Input
(e.g., flux, iron
ore and coke fines)
Sinter plant 1 transfer
(566,000 ST) station
(566,000 ST)

Railcar unloading Hone
by bottom dump
(239,000 ST)
Undersized material
from screening
Conveyor
stacker
(17,000 ST)
Conveyor to
bins
(549,000 SI)
Clamshell
bucket
(48,000 SI)
(ruck dump
(298,000 SI)
Open storage
(17,000 ST)
Bins
(549,000 ST)
Open storage
pile
(346,000 ST)

Clamshell
bucket to
conveyor
(17,000 SI)
Bins to
conveyor
(549,000 SO
front end
loader to
conveyor
(346,000 ST)

2 transfer
stations
(566,000 SO

2 transfer
stations
(585,000 ST)

Screening and   None
3 transfer
stations
(566,000 ST)
                                                                                                             None
                                                                                                                          None
                  and crushing
                  (608,000 ST)
                  Truck
                  (346,000 ST)

-------
           TABLE A-2.   RAW AND  INTERMEDIATE MATERIAL  HANDLING  AT THE  ARMCO  HOUSTON  PLANT  IN 1978a

Material
Coal




Coke




Iron Ore Pellets




Unagglomerated
Iron Ore



limestone/
Do loin He



Sinter, Nodules
and Briquettes



Sinter Input
(Flux, Iron Ore
and Coke Fines)




j- — i — , — --. — _ 	
Ol iqinntlon
mode
Barge unloaded
by clamshell
(445,000 ST)


Railcar unloaded
by side dump
(100,000 ST)

-
Barge unloaded
by clamshell
(578,000 ST)


Barge unloaded
by clamshell
(18,300 ST)


Railcar unloaded
by bottom dump
(62,300 ST)


Sinter plant
(257,000 ST)



Barge unloaded
by clamshell
(119,000 ST)
Undersized mate-
rial from screen-
ing and crushing
(194,000 ST)

Transfer
stations
2 transfer-
stations
(445,000 ST)


2 transfer
stations
(100,000 ST)


2 transfer
stations
(578,000 ST)


2 transfer
stations
(18,300 ST)


2 transfer
stations
(62.300 ST)


None



2 transfer
stations
(313,000 ST)




llandlinq method and amount of material handled
Storage
load- in
Conveyor
stacker
(445,000 SI)


Conveyor
stacker
(100,000 ST)


Conveyor
stacker
(578,000 ST)


Conveyor
stacker
(18,300 ST)


Conveyor
stacker
(37,400 ST)


Conveyor
stacker
(257,000 ST)


Conveyor
stacker
(313,000 ST)





Storage
Open
storage
(445,000 SI)


Open
storage
(100,000 ST)


Open
storage
(578,000 ST)


Open
storage
(18,300 ST)


Open
storage
(37,400 ST)


Open
storage
(257,000 ST)


Open
storage
(313,000 ST)




Storage
load-out
Crane-clam-
shell bucket
transfer to
conveyor
(445,000 SI)
Crane-clam-
shell bucket
transfer to
conveyor
(100,000 ST)
Crane-clam-
shell bucket
transfer to
conveyor
(578,000 Sf)
Crane- clam-
she 11 bucket
transfer to
conveyor
(18,300 ST)
Crane-clam-
shell bucket
transfer to
conveyor
(37,400 ST)
Crane-clam-
shell bucket
transfer to
conveyor
(257,000 ST)
Bucket-wheel
reclaimer onto
underground
conveyor
(313,000 ST)


Transfer
stations
4 transfer
stations
(445,000 ST)


4 transfer
stations
(383,000 ST)


2 transfer
stations
(578,000 ST)


2 transfer
stations
(18,300 ST)


2 transfer
stations
(62,300 ST)


None



2 transfer
stations
(313,000 ST)





Screening
None




Screened - 94%
to coke ovens;
6% to sfnter plant


None




None




None




None



None






Coke plant was down most of 1978, so coal and coke data are listed for 1979.

-------
TABLE A-3.  RAW AND INTERMEDIATE MATERIAL HANDLING AT THE INTERLAKE CHICAGO PLANT IN 1978
lldndl ing method and
Material
Coal
Coke
Iron Ore Pellets
Dolomite
Limes Lone
Sinter, Nodules
and Briquette
Sinter Input
(flux, Iron Ore
and Coke Fines)
Origination
mode
Truck unloaded
(26.000 ST)
Railcar unloaded
by rotary dump
(495,000 ST)
Coke ovens
(315.000 ST)
Ship unloaded by
clamshell
(1.203,000 ST)
Truck unloaded
at storage pile
(35,300 ST)
Ship unloaded by
clamshell
(123.000 ST)
Sinter Plant
(302,000 ST)
Truck unloaded
at storage pile
(398,000 ST)
Transfer
stations
9 transfer
stations
end i rig in
bin storage
(521,000 ST)
2 transfer
stations
(345,000 SI)
None
None
None
1 transfer
station
(302,000 ST)
2 transfer
stations
(199,000 ST)
Storage
load-in
liii. to
scraper to
open storage
pile
(495,000 SI)
Conveyor
stacker
(17,000 ST)
Same cl dins he 11
used to unload
ships
(1.203,000 SO
Same truck used
to deliver
material lo
plant
(35.300 ST)
Same clamshell
used to unload
ships
(123,000 ST)
None
Same truck used
to deliver mate-
rial to plant
(199,000 ST)
Conveyor stacker
(199,000 ST)
Storaqe
Open storage
pile
(505.000 ST)
Open storage
pile
(17,000 ST)
Open storage
pile
(1.203,000 ST)
Open storage
pile
(35,300 SI)
Open storage
pile
(123,000 ST)
None
Open storage
pile
(498,000 ST)
amount of material
Storage
load-out
Scraper
(521,000 SI)
Front-end
loader; dump
into conveyor
hopper/feeder
(17,000 ST)
Bucket wheel
reclaimer onto
underground
conveyor
(1,203.000 SO
Crane-clam-
shell bucket
transfer to
conveyor
(35.000 ST)
Crane- clam-
shell bucket
transfer to
conveyor
(123,000 ST)
None
Front- end
loader dump
into conveyor
(398,000 ST)
handled
Transfer
stations
21 transfer
stations
(521,000 ST)
2 transfer-
stations
(345,000 ST)
2 transfer
stations
(1,203,000 ST)
2 transfer
stations
(35.300 ST)
2 transfer
stations
(123,000 ST)
15 transfer
stations
(362,000 ST)
3 transfer
stations
(398,000 ST)
	
Screening
None
Screened - 90%
to coke oven; 10%
to sinter plant
(345.000 ST)
None
None
None
Screened - 82% to
blast furnace;
18% recycled
(272,000 ST)
None

-------
TABLE A-4.  RAW AND INTERMEDIATE MATERIAL HANDLING AT THE BETHLEHEM STEEL BURNS HARBOR PLANT IN 1978C
Material
Coal



Coke (Produced
in Plant)









Coke (Purchased)




Iron Ore Pellets





Sinter






1 imes tone/Dolomite



Sinter Plant
(Slag fines)




Origination
mode
Rotary dump of rail-
car onto underground
conveyors
(2,046,000 ST)
Coke Ovens
(1,493,000 ST)









Barge
(338,000 SI)
Rotary dump of rail-
car
(167,000 ST)
Barge to
clamshell
(865,000 ST)
Barge to bucket-
ladder conveyor
(4,221,000 ST)
Sinter plant
(1,835,000 ST)





Barge (11,000 ST)



levy
(385,000 ST)



Handling^ method and amount of material
Transfer
stations
6 conveyor
transfer
stations
(2,046,000 ST)
Z conveyor
transfer
stations to
screening
station
(1,493,000 ST)





5 conveyor
transfer
stations
(505,000 SI)

6 conveyor
transfer
stations
(5,086,000 ST)


9 conveyor
transfer
stations
(1,835,000 ST)



5 conveyor
transfer
stations
(11,300 ST)
Hauled by truck
to material
haul ing stor-
age pile
(385,000 ST)
Storage
load- in
Stacker into
pile
(2,046,000 SI)

Truck to storage
pile
(98,000 ST)
Conveyor
(1,305,000 ST)
Coke breeze
hauled off-site
(18,000 SI)
Hut coke hauled
off-site
(72,000 ST)
Stacker into
pile
(505,000 ST)


Stacker into
pile
(5,086,000 ST)



Enclosed con-
veyor
(1,652,000 ST)
Stacker into
pile
(183,000 ST)

Stacker into
pile
(11,300 ST)

Dumped by truck
(385,000 ST)



Storage
Open storage pile
(2, 046,000' SI)


Open storage pile
(98.000 SI)
Conveyor
(1,305,000 ST)







Open storage pile
(505,000 ST)



Open storage pile
(5,086,000 ST)




Enclosed con-
veyor
(1,652,000 ST)
Open storage pile
(183.000 ST)


Open storage pile
(11,300 ST)


Open storage pile
(385,000 ST)



Storage
load- out
Bucket wheel
reclaimer
(2,046,000 ST)

Front-end load-
er to conveyor
(98,000 ST)
Conveyor
(1,305,000 ST)






Bucket wheel
reclaimer
onto conveyor
(505,000 ST)

Bucket wheel
reclaimer
to conveyor
(5,086,000 ST)


Enclosed con-
veyor
(1,652,000 ST)
Bucket wheel
reclaimer onto
conveyor
(183,000 ST)
Bucket wheel
reclaimer
onto conveyor
(11,300 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(385,000 ST)
handled
Transfer
stations
2 Conveyor trans-
fer stations
(2,046,000 ST)

3 conveyor trans-
fer stations
(1,403.000 ST)








3 conveyor
stations
(505,000 ST)


3 conveyor
transfer
stations
(5,086,000 ST)


Enclosed con-
veyor
(1,652,000 ST)
3 conveyor trans-
fer stations
(183,000 ST)

3 conveyor trans-
fer stations
(11,300 ST)

3 conveyor trans-
fer stations
(385,000 ST)



Screening
Hone



Screening
(1,403,000









Screening







ST)










(505,000 ST)



Screening
(5,086,000




Screening
(1,835,000





None



None








ST)





ST)















-------
                                                                             TABLE  4.    (continued)
CTl
Handling method and amount of material
Material
Sinter Plant
(Slag fines)
(continued)
Sinter Plant Input
(Coke Breeze)
Sinter Plant Input
(Dolomite)

Sinter Plant Input
(Calcite)

Origination
mode
Sinter mix bedding
plant
(385.000 ST)
From outside vendor
(69,000 ST)
Barge
(291,000 SI)
Sinter mix bedding
surge bin
(291,000 ST)
Barge
(169,000 ST)
Sinter mix bedding
plant
(169,000 ST)
Transfer
stations
3 conveyor
transfer
stations
(385,000 ST)
Transport by
truck
(69.000 ST)
5 conveyor
transfer
stations
(291.000 ST)
2 transfer
stations
(291,000 SI)
5 transfer
stations
(169.000 ST)
3 transfer
stations
(169,000 ST)
Storage
1 oad~ i n
Mobile or sta-
tionary stacker
into pile
(385,000 SI)
Transport by
truck
(1,380 ST)
Mobile or sta-
tionary stacker
into pile
(291,000 SI)
Enclosed con-
veyor
(291,000 ST)
Mobile or sta-
tionary stacker
pile
(169,000 ST)
Mobile or sta-
tionary stacker
onto pile
(169,000 SI)
Storage
Open storage pile
(385,000 SO
Transport by
truck
(1.380 ST)
Open storage pile
(291,000 ST)
Enclosed con-
veyor
(291,000 SI)
Open storage pile
(169,000 ST)
Open storage pile
(169.000 ST)
Storage
load-out
Bucket wheel
reclaimer onto
above-ground
conveyor
(385,000 ST)
Dumped by
truck into
conveyor bin
(1,380 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(291,000 ST)
Enclosed con-
veyor
(291,000 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(169,000 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(169,000 ST)
handled
Transfer
stations
1 conveyor trans-
fer stations
(385,000 ST)
5 transfer sta-
tions
(69,000 ST)
3 transfer sta-
tions
Enclosed conveyor
(291,000 SI)
3 transfer sta-
tions
4 transfer sta-
(169,000 SI)
	
Screening
None
None
None
None
None
None
               Sinter Plant Input
               (Mill Scale)
Purchased by outside  Transport by
vendor and generated  truck
in plant by hot  form- (267,000 SI)
ing and rolling  oper-
ations
(267,000 ST)
                                    Sinter mix bedding    3 transfer
                                    plant surge bin       stations
                                    (267,000 ST)          (267,000 ST)
Transport by
truck
(13,350 ST)        Open  storage pile
Truck dump onto   (253,650 ST)
pile (253,650 Sf)
Transport by  truck  Dumped by       Conveyor trans-
(13,350 ST)         truck into con- fer station
                   veyor bin       (267,000 ST)
                   (3.350 ST)
                   Front-end
                   loader dump into
                   conveyor bin
                   (253,650 ST)
                  Screening
                  (267,000 ST)
                                     Mobile or sta-
                                     tionary stacker
                                      into pile
                                     (267,000 SI)
                  Open  storage pile
                  (267,000 ST)
                   Bucket wheel
                   reclaimer onto
                   above-ground
                   conveyor1
                   (267,000 ST)
4 transfer
stations
(267,000 ST)
                                                                                                                                                      None

-------
                                                      TABLE  4.   (concluded)

Material
Sinter Plant Input
(Purchased Iron Ore
Fines)







Sinter Plant Input
(Iron Ore and Sinter
Fines Generated at
Plant)










Sinter Plant Input
(Blast FCE. Flue
Oust/Filter Cake)











	 . 	

Origination
mode
Barge
(1,121,000 ST)



Sinter mix bedding
plant
(1,121,000 ST)


Blast furnace
stockhouses
(375,000 ST)






Sinter mix bedding
plant
(375,000 ST)


Blast FCE, gas
cleaning systems
(193,000 ST)


From stock pile
(193,000 ST)



Sinter mix bedding
plant
(193,000 ST)

	

transfer
stations
5 transfer
stations
(1,121,000 ST)


3 transfer
stations
(1.121,000 ST)


Conveyor
transfers
(375,000 ST)






3 transfer
stations
(375,000 ST)


Transport by
(193,000 ST)


Transport by
truck
(193,000 ST)


3 transfer
stations
O93.000 ST)


Handling method and
Storage
load- in
Mobile or sta-
tionary stacker
into pile
(1,121,000 ST)

Mobile or sta-
tionary slacker
into pi le
(1,121,000 ST)

Transport by
truck
(37,500 ST)
Truck dump
onto pile
(337,500 ST)



Mobile or sta-
tionary stacker
onto pile
(375,000 ST)

Dumped by truck
onto storage
pile
(193,000 ST)

Truck dump onto
pile
(193,000 ST)


Mobile or sta-
tionary stacker
onto pi le
(193,000 ST)


Storage
Open storage pile
(1,121,000 ST)



Open storage pile
(1,121,000 ST)



Transport by
truck
(37,500 ST)
Open storage pile
(337,500 ST)




Open storage pile
(375,000 ST)



Open storage pile
(193,000 ST)


Open storage pile
(193,000 ST)



Open storage pile
(193,000 ST)



amount of material
Storage
load-out
Bucket wheel
reclaimer onto
above-ground
conveyor
(1,121,000 ST)
Ducket wheel
reclaimer onto
above-ground
conveyor
(1,121,000 ST)
Dumped by
truck into
conveyor bin
(37,500 ST)
Front-end
loader; dump
into conveyor
bin
(337,500 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(375,000 ST)
Loaded into
truck with
front-end
loader
(193,000 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(193,000 ST)
Bucket wheel
reclaimer onto
above-ground
conveyor
(193,000 ST)
handled
transfer
stations
3 transfer sta-
tions
(1,121,000 ST)


4 transfer
stations
(1,121,000 ST)


3 transfer
stations
(375,000 ST)
(375,000 ST)





4 transfer
stations
(375,000 ST)


Transport by
truck
(193,000 ST)


3 transfer
stations
(193,000 ST)


4 transfer
stations



	

Screening
None



None




None







None




None


None




None




Due  to coal  strike in 1978 and the resultant nonrepresentaUve handling methods, these data  are for 1979.

-------
TABLE A-5.   RAW AND INTERMEDIATE MATERIAL HANDLING AT THE  BETHLEHEM STEEL'S  SPARROWS POINT PLANT  IN 1978

Handling method and amount of material
Origination
Material mode
Coal Barge unloaded via
clamshell
(3,334.000 ST)
Coke Coke Ovens
(2.366.000 ST)
Vessels
(203,000 Sf)
Iron Ore Pellets Vessels
(3.253,000 ST)
Unaijglome rated Iron Barge unloaded via
Ore clamshell
(2,467,000 SO
-j-, Revert Material Sinter plant and
i screening operations
oo to trucks
(896.000 ST)
Gravel Iruck (85,800 SI)
Sinter Input Railcar unloaded
(Limestone as flux) via bottom dump
(651.000 ST)
Transfer
stations
5 transfer
stations
(3,334,000 ST)
6 transfer
stations
(82,000 ST)
5 transfer
stations
(3,253,000 ST)
5 transfer
(2,467,000 ST)
None
None
6 transfer
stations
Storage
load- in
Conveyor stacker
(3,334,000 SI)
Trucks to open
storage pi 4e
to truck to
bins
(385,000 SO
Conveyor stacker
to bins
(2,184,000 ST)
Conveyor slacker
(3,253,000 ST)
Conveyor stacker
(2,467.000 ST)
Truck to front-
end loader to
open storage
pile
(096,000 ST)
Truck dump to
open storage
pile (85,800 ST)
Conveyor to bins
to conveyor
stacker to open
Storage
Open storage pile
(3,334,000 ST)
Bins
(2, 569,000 ST)
Open storage pile
(3,253,000 ST)
Open storage Pile
(2,467,000 SO
Open storage pile
(896,000 ST)
Open storage pile
(85,800 ST)
Open storage pile
(651,000 ST)
Storage
load-out
Trout end
loader to
conveyors
(3,334,000 ST)
Bins to convey-
ors
(2.569,000 ST)
Bucket wheel
reclaimer
(3,253,000 ST)
Bucket wheel
reclaimer
(2.467,000 SO
Bucket wheel
reclaimer
(896,000 ST)
Clamshell to
conveyors
(85,500 ST)
Bucket wheel
reclaimer
(651.000 ST)
handled
Transfer
stations
/ transfer
stations
(3.334,000 SI)
None
8 transfer
stations
9 transfer
stations
(2.467.000 Sf)
9 transfer
stations
(896,000 ST)
9 transfer
stations
(85,800 SI)
9 transfer
stations
(651,000 SI)

Screening
Screening
(3,334,000 SI)
Screening
(2,569,000 SO
Screening
(3,253,000 ST)
Screening
(2,467.000 SI)
Screening
(896,000 ST)
None
None
                                        storage pile
                                        (651,000 ST)

-------
TABLE 5.  (concluded)


Material
Sinter Input
(Coke fines)





Sinter




j| Due to coal

Origination Transfer
mole stations
Truck (210,240 ST) 9 transfer
stations
(210,240 ST)




Truck 6 transfer
(3,299,000 ST) stations
(3.299.000 ST)



strike in 1978, these data are for 1979.
Handling method and amount of material handled
Storage
load- in Storage
Crusher to lied- Open storage pile
ding/blendinq (52,560 ST)
plant then by
stacker into pile
(52,560 ST)


Stacker into Open storage pile
pile (66,000 ST)
(66.000 ST)




Storage
load-out
Conveyor
transfer
station
(52,560 ST)
Crusher to
Transfer sta-
tions (157,680
Clamshell to
conveyor to
bin
(66,000 ST)
Truck to bin
(3,233,000 ST)

Transfer
stations Screening
9 transfer sta- None
lions to sinter
plant bins
(210,240 ST)


ST)
10 transfer Screening
stations (2,425,000 ST)
(3,299.000 ST)





-------
         TABLE A-6.   RAW AND  INTERMEDIATE MATERIAL HANDLING AT THE GREAT LAKES STEEL DIVISION OF NATIONAL STEEL
                        CORPORATION  IN  1978
O

Material
Coke
Coal

Iron Ore Pellets


Unaijlomerated Iron
Ore
Limestone/Dolomite
Sinter, Nodules
and Briquettes

Origination
mode
Coke ovens
(1,780,000 ST)
Barge unloaded
by clamshell
(1,986,000 ST)
Railcar unloaded
by rotary dump
(221,000 ST)
Barge unloaded
by clamshell
(2,067.000 ST)
Barge unloaded by
bucket ladder con-
veyor (1,267,000 ST)

Barge unloaded by
clamshell
(98,000 ST)
Barge unloaded by
bucket ladder
(88,000 ST)
Sinter plant
(1,334,000 SD
Handling method and amount of material
Transfer
stations
5 transfer
stations
(498,000 ST)
2 transfer
stations
(1,986,000 ST)
1 transfer
station
(221,000 ST)
5 transfer
stations
(467,000 ST)


1 transfer
station
(98,000 ST)
5 transfer
stations
(17,600 ST)
3 transfer
stations
(1,334.000 ST)
Storage
load* in
None
Conveyor
stacker
(1,986,000 ST)
Front end
loader
(221,000 SI)
Same clamshell
that unloaded
barge
(2,067,000 Sf)
Conveyor stacker
(467,000 SF)
Conveyor to
storage pile
(800,000 SI)
Same clamshell
that unloaded
barge (98,000 SI)
Conveyor to
storage pile
(70,400 SD
Conveyor stacker
(17,600 ST)
Conveyor slacker
(387,000 SI)
Storage
Hone
Open storage pile
(2,207,000 SI)

Open storage pile
(3.334,000 ST)


Open storage pile
(98,000 ST)
Open storage pile
(88,000 ST)
Open storage pile
(387,000 ST)
Storage
load-out
None
Front end
loader to
conveyor
(993,000 ST)
Clamshell
bucket
(1,214,000 ST)
Front end
loader to
conveyor
(467,000 ST)
Clamshell
bucket to
conveyor
(2.867.000 ST)

Clamshell
bucket to
conveyor
(98,000 ST)
Front end
loader to
conveyor
(17,600 ST)
Clamshell bucket
to conveyor
(70,400 ST)
Clamshell
bucket to
conveyor
(387,000 SI)
handled
Transfer
stations Screen IMC/
None Screened
(1. 780,000 SI)
1 transfer sta~ None
tion (2,207.000 ST)

5 transfer None
stations
(1.867,000 ST)


4 transfer None
stations
(98,000 ST)
None None
3 transfer Screened
stations (1,041,000 SI)
(387,000 SI)

-------
                                 TABLE  6.    (concluded)
Handling method and amount of material handled
Material
Sinter Input (Flux,
Iron Ore, and Coke
Fines)
Origination
mode
Barge unloaded by
clamshell
(721,000 ST)
Transfer
stations
9 transfer
stations
(721,000 ST)
Storage
load- in
Conveyor stacker
(724,000 ST)
Storage
Open storage pile
(1,575,000 ST)
Storage
load- out
Front end
loader to
conveyor
(850,000 ST)
Transfer
stations Screening
8 transfer sta- None
lions for flux
and coke; 11 for
iron ore
(1,575,000 ST)
Barge unloaded by
bucket ladder con-
veyor
(721,000 ST)

Coke breeze from
screening
(126,000 ST)
Front end loader
(126,000 ST)
Clamshell
bucket  to
conveyor
(724,000 ST)

-------
IABLE A-7.   RAW AND INTERMEDIATE  MATERIAL  HANDLING  AT  UNITED  STATES  STEEL'S  GENEVA  WORKS  IN  1978
Handling method and amount of material

Material
Coal





Coke


Iron Ore Pellets







*
Origination
mode
Railcar unloaded
by rotary dump
(1.540,000 ST)



Coke ovens
(1,150,000 ST)

Railcar unloaded
by rotary dump
(1.450,000 ST)






Transfer
stations
1 transfer
station
(1.150,000 SI)



1 transfer-
station
(1.150,000 SO
None








Storage
load- in
Conveyor to
open storage
(1.540,000 SI)



None


Conveyor stacker
(1.450,000 SI)








Storage
Open storage pi le
(1,540,000 SI)




None


Open storage pile
(1,450,000 ST)







Storage
load-out
Dozer pushes
onto under-
ground con-
veyor
(1,540,000 ST)

None


Rake reclaimer
and bottom
plow feeder
to underground
conveyor
(1,235.000 SI)
Bucket wheel
reclaimer
(145,000 ST)
handled
Iransfer
stations
Primary and sec-
ondary hammer mill
blending bins, 9
transfer and stor-
age bins
(1,540,000 ST)
3 transfer-
stations
(1,150,000 ST)
10 transfei-
stations
(1.450,000 ST)








Screening
None
t




Screening
(1.150,000

Screen imj
(1,450,000

















ST)


SO







Front end loader


Unagglomerated Iron
Ore

Limestone/ dolomite


Sinter



Sinter Input
(Coke Fines)


Sinter Input (flux
and iron ore)




Railcar unloaded
by rotary dump
(1,007,000 ST)
Railcar unloaded
by bottom dump
(645,000 ST)
Sinter plant
(863,000 ST)


Railcar unloaded
fay bottom dump
(64,000 ST)

See iron ore and
limestone/dolomite




6 transfer
stations
(1,007,000 Sf)
None


1 Drop box on-
to continuous
conveyor
(863,000 ST)
3 transfer
stations and
screening
(64,000 ST)
See iron ore &
limestone/dolo-
mite



Conveyor stacker
(1,007,000 ST)

Conveyor to bins
(645,000 ST)

None


Open storage pile
(1,007,000 ST)

Bins
(645,000 ST)

None
to conveyor
(72,500 ST)
Bottom plow
feeder
(1,007,000 ST)
Bins to scale
car
(645,000 ST)
None


5-10 transfer
stations
(1,007,000 SI)
None


None


Screening
(1,007,000

None


Screening



ST)





(863,000 ST)


Conveyor to bins
(57,400 ST)


See iron ore and
limestone/dolo-
mite



Bins
(57,400 ST)


Open storage piles
(1,061,000 Sf)




Bins to sinter
mix system
(57,400 ST)

Bottom plow
feeder to con-
veyor
(1,061,000 ST)


None outside
sinter bui Iding


5-10 transfer
stations
(1,061,000 Sf)



None



Screening
(1,061,000









SO



-------
         TABLE A-8.  RAW AND  INTERMEDIATE MATERIAL HANDLING AT UNITED STATES STEEL'S GARY WORKS  IN  1978
1



CO
Material
Coal










Coke



Sinter Input
(Coke fines)






Sinter





Iron Ore Pellets







Sinter Input
(Iron Ore)



Origination
mode
Rotary dump of rail-
car onto underground
conveyor
(4,700,000 ST)







Coke ovens
(3,290,000 ST)


Rail car side dump
(419,000 ST)
Bottom dump railcar
(419,000 ST)
Undersized material
from screening and
crushing
(3,350,000 ST)
Sinter plants
(4,375,000 ST)




Hulett unloading of
bulk vessel
(3,980,000 ST)
Vessel (self-
uuloader)
(1,400,000 SI)


Crane-clamshell
bucket transfer
from ore vessel
(4,190.000 SO

Transfer
stations
7 conveyor
transfer
stations
(4,700,000 ST)







Conveyor
transfer
station
(3,290,000 ST)
Truck
(4,190,000 ST)






None





Crane clamshell
bucket drop ore
bridge
(3,980,000 ST)
Conveyor trans-
fer station
(1,400,000 ST)

Conveyor trans-
fer station
(4,190,000 SI)

Handling method and amount of material
Storage
load- in
Truck trans-
ported from
stocking out
bin
(704,000 ST)
Coal preparation
and handling
(i.e. , screening.
pulverizing, and
proportioning
.(3,996.000 ST)
Transfer car
(3,290,000 ST)


Truck
(4.190,000 ST)






Conveyor
(4,375,000 ST)




Crane clamshell
(ore bridge)
onto pi le
(1,610,000 ST)
Stationary
stacker onto
pile
(3,770,000 ST)
Conveyor trans-
port
(4,190,000 ST)

Storage
Open storage pi le
(704,000 ST)
None
(3,996,000 ST)







Storage bin
(3,290,000 ST)


Storage bin
(4,190,000 ST)






Open storage pile
(656,000 ST)
Sinter load-out
bin building
(3,720,000 ST)

Open storage pile
(5.380,000 ST)






Open storage
(2,100,000 ST)


Storage
load-out
front-end
loader pickup
and trans-
ported to re-
claim hopper
(704,000 ST)





Vibrator
feeder
(3,290,000 ST)

Conveyor trans-
port
(4,190,000 ST)





Transfer car
(4,375,000 ST)




Truck and
conveyor
(1.775,000 ST)
Crane clam-
shell bucket
transfer to
hi-line bin
(3,600,000 ST)
Conveyor
transport
(4,190,000 ST)

handled
Transfer
stations
Conveyor trans-
fer station
(4,700,000 ST)








Conveyor trans-
fer station
(3,290,000 ST)

Conveyor trans-
port
(4,190,000 ST)





Hi -Line storage
bin
(2,930.000 ST)
Storage bin
(1,450,000 ST)

Truck and
conveyor
(1.775,000 ST)
Transfer car
(3,600,000 ST)



None




Screening
Conveyor screening station
(4,700,000 SI)









Conveyor screening station
(2,960,000 ST)
Emergency bins (not screened)
(330,000 ST)
None







No. 13 blast furnace
screening station
(1.440,000 ST)
Remaining blast furnaces
(No screening)
(2,930,000 ST)
No. 13 blast furnace
(1,775,000 Si)
No screening
Remaining blast furnaces
(3,600,000 ST)
No screening


None




-------
                                             TABLE A-8.  (concluded)

Material
Sinter Input
(Flux)
Limestone/Dolomite
Unagglomerated Iron
Ore

Origination
mode
Self-unloading
barge
(4,190,000 SI)
llulelt unloading of
bulk vessel
(452,000 ST)
Self-unloading vessel
(1.930.000 SI)
llulett unloading
of ore vessel
(3. 386,000 ST)

Transfer
stations
Conveyor trans-
port
(4.190,000 SI)
Ore bridge
(2,380.000 ST)
Ore bridge
(3,386,000 ST)
Handling method and amount of material
Storage
load' in
Conveyor trans-
port
(4.190,000 SI)
Ore bridge
(2,380.000 SI)
Crane-clamshell
bucket drop into
pile (Ore bridge)
(3,386,000 SI)
Sloraye
Hevert blenUing
piles
(4,190,000 ST)
Open storage pile
(2,380,000 SI)
Open storage pile
(3.38G.OOO ST)
Sloraye
load-out
transport
[ruck
(4.1'JO.OOO SI)
Crane- clcim-
shel 1 bucket
transfer to
bin
(2,380.000 ST)
Crane-clam-
shell bucket
transfer to
bin
(3,306,000 ST)
handled
Transfer
stations Screening
Conveyor trans- None
porl
(4,190,000 SI)
Transfer car None
(2,380,000 SI)
Transfer car None
(3,386.000 SI)
I
—>

-p>

-------
TABLE A-9.  RAW AND INTERMEDIATE  MATERIAL  HANDLING  AT THE  J  &  L  STEEL ALIQUIPPA  PLANT  IN  1978
	 , 	 	 — _ 	 	 _
Material
Coke


Coal for boilers
and storage








Coal for Coke
oven






Iron Ore Pellets









Unagglomerated Iron
Ore




Origination Transfer
mode stations
Railcar unloaded by Hone
bottom dump
(1,165,000 ST)
Barge unloaded by None
clamshell (34,600 SI)
Barge unloaded by
bucket-ladder con-
veyor (1,678.000 ST)
Truck unloaded
(17,300 ST)



Barge unloaded by 22 transfer
bucket- ladder stations
conveyor and fed (2,358,000 ST)
into bins
(2,358,000 ST)
Railcar unloaded
via rotary dump
(73,000 ST)
Railcar unloaded None
to transfer car
via rotary dump
(1,184,000 ST)
Railcar unloaded to
conveyor via bottom
dump
(1,184,000 ST)


Railcar unloaded None
to transfer car
via rotary dump
(62,200 ST)

Handling method and amount of material
Storage
load- in
Conveyors
(1,465,000 SI)

Conveyor to
temporary stor-
age to coal yard
pile via bucket
ladder conveyor
(623,000 SI)
Front-end loader
to stacker con-
veyor to bins
(644,000 ST)
Conveyors to
crusher to
bins
(2,431,000 ST)




Transfer car
to temporary
storage area
to ore yard pile
via clamshell
(1,184,000 ST)
Conveyors to
cast-house
storage bins
(1,184,000 ST)
Transfer car to
temporary stor-
age to ore yard
via clamshell
(62,200 ST)
Storage
Storage bins
(1,465,000 ST)

Open storage pile
(623,000 ST)




Bins
(661,000 ST)


Storage bins
(2,431.000 ST)






Open storage
(1,184,000 ST)








Open storage pi le
(62,200 ST)



Storage
load-out
Conveyors
(1,465,000 ST)

Ducket ladder
to conveyor
(623,000 ST)







Bins to con-
veyor to
crusher to
bins
(2,431,000 ST)



Clamshell to
transfer car
(1,184,000 ST)







Clamshell
bucket to
transfer car


handled
Transfer
stations Screening
None Screened - 95% to blast fur-
naces; 5% to sinter plants

None None








None None







Transfer car Screened
to cast house (1,018,000 ST)
storage bin
(1,184,000 ST)






Transfer car Screening
to bin (27.700 SO
(62,200 ST)



-------
TABLE A-9.  (concluded)
Handling method and amounl of material

Material
Limes tone/Do lomi le







Sinter








Sinter Input (Flux,
Iron ore and Coke
Fines)





Origination Transfer
mode stations
Rai Icar unloaded None
to transfer car
via rotary dump
(71.000 ST)
Railcar unloaded
to conveyor via
bottom dump
(30,000 ST)
Sinter plant 5 transfer
(1,548,000 ST) stations
(1,548,000 ST)






Railcar unloaded 2 transfer
to conveyor via stations
rotary dump (2,182,000 ST)
(1,527,000 ST)
Railcar unloaded to
conveyor via bottom
dump
(655,000 ST)
Storage
load- in
Transfer car to
temporary stor-
age to main
storage area via
clamshell
(71,000 SI)
Conveyor to bins
(30,000 ST)
Conveyor to bins
(1,548,000 ST)







Conveyor to
(2.182,000 ST)







Storage
Open storage pile
(71,000 SI)
Bins
(30,000 St)




Bins
(1,548,000 SI)







Dins
(2,182,000 ST)






Storage
load-out
Clamshell
bucket to
transfer car
(71,000 ST)




Bins to trans-
fer car
(1,548,000 ST)






Bins to con-
veyor
(2,182,000 ST)





handled
Transfer
stations Screening
transfer car to None
bin
(71,000 SI)





Transfer car Screening
to casthouse (666,000 SI)
bins to skip
cars (882,000 SI)
fransfer car to
casthouse bins
to 3 transfer
stations
(666.000 SI)
15 transfer None
stations
(2,182,000 SI)






-------
TABLE A-10.  RAW AND INTERMEDIATE  MATERIAL  HANDLING AT J  &  L  STEEL  INDIANA HARBOR PLANT IN 1978
Material
Coke


Coal





Pellets







Unagglomeraled
Iron Ore


Sinter, Nodules
and Briquettes






Sinter Input (flux,
Iron Ore and Coke
Fines)




Limestone/dolomite






Origination
mode
Coke ovens
(840,000 SI)

Unloaded from rail-
car via side dump
(1,260,000 ST)



Barge unloaded via
clamshell
(666,000 SI)

Barge unloaded via
bucket ladder con-
veyor
(3,775,000 ST)
Barge unloaded via
clamshell
(424,000 ST)

Sinter plant
(700,000 ST)






Barge unloaded
via clamshell
(609,000 ST)

Truck unloaded
(19,000 ST)

Barge unloaded
via bucket
ladder conveyor
(60,000 ST)
truck unloaded
(338,000 ST)

Transfer
stations
4 transfer
stations
(840,000 SI)
1 transfer
station
(1,260,000 ST)



None



None



None



None







6 transfer
stations
(19,000 ST)




None





Handling method and amount of material handled
Storage
load- in
Conveyors
(840,000 ST)

Clamshell bucket
to storage pile
(630,000 SI)
Clamshell bucket
to bin storage
(630,000 ST)
Clamshell bucket
to storage pile
(3,331.000 ST)

Conveyors to
bins
(1,110,000 ST)

Clamshell bucket
to storage pile
(424,000 ST)

Clamshell
stacker to open
storage pile
(105,000 ST)
Conveyors to
bins
(595,000 ST)

Clamshell bucket
to open storage
pile
(609,000 ST)
Conveyor stacker
(19,000 ST)

Clamshell bucket
to open storage
pile
(398,000 ST)


Storage
Bins
(840,000 ST)

Open storage pile
(630,000 ST)

Bins
(630,000 SI)

Open storage pile
(3,331,000 SO


Bins
(1,110,000 ST)


Open storage pile
(424,000 ST)


Open storage pile
(105,000 ST)


Bins
(595,000 ST)


Open storage pile
(609,000 ST)


Bins
(19,000 ST)

Open storage pi le
(398,000 ST)




Storage Transfer
load-out stations
Bin to None
conveyors

Clamshell 3 transfer
bucket to stations
conveyors (1,260,000 ST)
(1,260,000 ST)


Clamshell None
bucket to
conveyor
(3,331,000 ST)
Bridge crane to
conveyor
(1.110,000 ST)

Front end 5 transfer
loader to stations
conveyor (424,000 ST)
(424,000 ST)
Bins to con- None
veyors
(595,000 ST)

Clamshell
bucket to
conveyors
(105,000 SI)
Front end 5 transfer
loader to stations
conveyor (628,000 ST)
(609,000 ST)
Bins to con-
veyor
(19,000 ST)
Clamshell None
bucket to
conveyors
(398,000 ST)


Screening
None


None





None







Screened
(424,000 ST)


None







Screening
(628,000 SI)





None






-------
                             TABLE A-ll.    SLAG HANDLING AT  SURVEYED  IRON  AND  STEEL  PLANTS  IN  1978
Plant
Interlake-Chicago
Origination process
Blast furnaces
(297.000 ST)
Mullen slag
transport
Flows to pits along
side casthouse and
is quenched
(297.000 SD
Cooled slag
loading and
transport
(ronl-end loader to
haul truck
(2
-------
        I1.   Oprr.it ing and N.i int eit.nu e Costs:   I'lease complete  I lie  following table  Tor  eat h street sweeper  rurrmlly in service.
               The  costs indicated :;lioulil  he  in 19BO dollars.


                                             Annual  Operating anil Maintenance ('osls  lor  Strecl Cloaiiing	                             Approx. Annual
                              Type of                       Cost  of" Coiisiniialile SIIJHI|_^OB                                                     Down-Time  for
        M.ike 
-------
Cleaning Scsedule:   Please provide tile schedule used for cleaning all of the paved roads tnroughout cue plant.
  Tins schedule should include the frequency of cleaning, how this frequency was decided upon, and the method
  by which the various types of street sweepers described above are allocated to the cleaning of certain sec-
  tions of road.
Projections:  Please indicate below any of the sweepers mentioned above which are scheduled for retirement in the
  near future, the type of equipment being seriously considered as their replacement, and the reasons for such con-
  sideration.  Also provide below any proposed changes in the operating or cleaning schedule which may be imple-
  mented in the future or any equipment modifications or changes considered.
                                                 B-6

-------
III.  CONTROL TECHNOLOGY FOR UNPAVED ROADS, SHOULDERS, PARKING LOTS,  AND ACTIVE STORAGE PILES



A.  Controls for Unpaved Roads and Paved Road Shoulders:   Please complete the following information for your facility
      where applicable.

Treatment Method:  Watering 	   Chemical Dust Suppressants 	   Other 	
                                                                                                  (specify)
Type(s) of Chemical(s) Used:  (check one or more as applicable)
Lignin Sulfonate 	       Petroleum Resins ______       Salts ______       Wetting Agents
Other 	
          (specify)

Trade or Chemical Name(s) of Dust Suppressant(s) Used (if any) _____________________________

Type of Diluent(s) Used (if any) ^	
Application Rate 	 gal. of 	% solution per yd2 of surface treated

Dilution Ratio 	 parts of chemical to 	 parts _
                                                                      (type of diluent)

Concentration of Chemical Suppressant as Received 	°1, by ^	
                                                                       (weight or volume)

Frequency of Application 	
Basis for Frequency of Application
.kiethod of Application (e.g. ,  distributor truck)
Length of Road Which Is Treated Annually 	 miles/yr

Total Capacity of On-Site Chemical Storage 	 gal.   No.  and Capacity of Storage  Tanks
Cost of Concentrated Chemical Dust Suppressant(s) Delivered to Your Plant S	/gal.   (Chemical)

                                                                          $	/gal.   (Freight)

Gallons of Chemical Delivered Per Shipment 	 gal.

Gallons of Chemical Delivered Per Year	 gal.

Capital Cost for Storage Tanks S	 in 	 dollars
                                                           (year of purchase)

Line Items Included In Capital Cost for Storage Tanks:

                    5 	 for tanks

                    $ ____________________ for installation labor

                    S _________________ for accessories

                    $	for other

Construction Material for Storage TanKS (e.g. concrete  or metal) 	

Is Storage Tank Above or Below Ground 	

Is the Tank Heated	

Capital Equipment Cost for Method of Application (e.g.,  distributor truck) $	
  in 	 dollars                                            (year of purcnase)

Capacity of Distributor Truck	 gallons
                                                      B-7

-------
Annual Operating and  Maintenance Cost of Treatment $	 in _________ dollars
                                                                         (year)
                                                  $	 per mile of treated road
                                                  S	 per actual mile of road

(Please attach supporting  calculation for operating and maintenance costs)

Major Maintenance Problems  Encountered  (specify) ______________________________________
B.  Control Methods  for  Unpaved  Parking Lots and Other Exposed Areas:  Please complete the following  information  for
      your facility  where  applicable.
Treatment Method:   Watering  ________   Chemical Dust Suppressants 	   Other
                                                                                                 (specify)
Type(s) of Chemical(s)  Used:   (check  one or more as applicable)
Lignin Sulfonate 	       Petroleum Resins 	       Salts 	       Wetting Agents
Other 	
          (specify)

Trade or Chemical Name(s) of  Dust  Suppressant(s) Used (if any) ___________________________________

Type of Diluent(s) Used (if any) 	
Application Rate __________ gal.  of           \ solution per acre of surface treated

Dilution Ratio _________ parts  of chemical to _^_^^^^^ parts
                                                                     (type of diluent)

Concentration of Chemical  Suppressant  as Received           % by _
                                                                      (weight or volume)

Frequency of Application ___________________________________________________________
Basis for Frequency of Application
Method of Application (i.e.,  distributor  truck)
Area Which Is Treated Annually 	 acres/yr

Total Capacity of On-Site Chemical  Storage 	 gal.    No. and Capacity of Storage Tanks
Cost of Concentrated Chemical Dust  Suppressant(s) Delivered to Your Plant $	/gal.   (Chemical)

                                                                         $	/gal.   (Freight)

Gallons of Chemical Delivered Per Shipment 	 gal.

Gallons of Chemical Delivered Per Year 	gal.

Capital Cost for Storage Tanks $	  in 	 dollars
                                                           (year of purchase)

-------
Line Items Included in Capital Cost for Storage Tanks.

                  S	 for tanks

                  $              for installation labor

                  $   	 for accessories

                  S	 for other

Construction Material for Storage Tanks (e.g., concrete or metal) 	

Is Storage Tank Above or Below Ground ____________________

Is the Tank Heated 	

Capital Equipment Cost for Method of Application (e.g.  distributor truck) $	 in _______________ dollars
                                                                                             (year of purchase)

Capacity of distributor truck _______________ gal.

Annual Operating and Maintenance Cost of Treatment

                  $ 	 in _	 dollars
                                        (year)

                  S _______________ P" treated acre

                  $ 	 per actual acre

Major Maintenance Problems Encountered (specify) _________^_______^__^_
Approx.  Annual Operating and Maintenance Cost of Treatment $                per acre

Major Maintenance Problems Encountered (specify) 	


C.  Control Methods for Active Storage Piles:  Please complete the following information for each major active storage
      pile in your facility where applicable.  Use additional sheets as necessary.

   1.  Type of Material in Storage (e.g., coal, pellets)	   Surface Area of Storage Pile 	 ft2

   Is Stated Surface Area Projected Area or Actual Area ________________________

   Average Daily Material Throughput 	 tons/day  Average Material Reserve 	 tons

   Treatment Methods:
   Watering 	   Chemical Suppressants or Binders 	     Other 	
                                                                                                 (specify)
   Typefsl of Chemical(s) Used:   (check one or more as applicable)
   Lignin Salfonate ______       Petroleum Resins 	       Salts  	       Wetting Agents
   Other 	
          (specify)
                                                                 t
   Trade or Chemical Name(s) of  Dust Suppressant(s) Used (if any) 	

   Type of Diluent(s) Used (if any) ^	
   Application Rate 	 gal.  of 	    % solution per ft2  of surface treated

   Dilution Ratio 	 parts of chemical to 	 parts 	
                                                                      (type  of diluent)

   Concentration of Chemical  Suppressant as Received 	% by 	
                                                                       (weight or volume)
                                                      B-9

-------
Frequency of  Application
Basis for Frequency  of Application
Method of Application  (e.g. sprinkler system or mobile distributor truck)

Area Treated Annually  _ acres/yr

No. of Spray Nozzles in Operation _      Type of Spray  Pattern Generated

Sake of Spray Sozzle(s) _  Model No.(s)

Sozzle Capacity ____________ gpm @ _____________
Spray Angle _ °                             Maximum Area  of  Coverage of Spray Pattern _ ft2

Designer of Sprinkler  System ____________________  Address _

Phone No.  ( _ ) _ - _                    Est.  Life  Expectancy  of System _ yrs .

Total Capacity of On-Site  Chemical Storage _ gal.   No.  and Capacity of Storage Tanks _
Cost of Concentrated Chemical Dust Suppressant Delivered to Your Plant  $	/gal. (Chemical)

                                                                      $	/gal. (Freight)

Gallons of Chemical Delivered Per Shipment _______________________  gal-

Gallons of Chemical Delivered Per Year _________________________  gal.

Capital Cost for Storage Tanks $     	 in ________________ dollars
                                                         (year of purchase)

Line Items Included in Capital Cost for Storage TanKs.

               S ______________ for tanks

               $ 	 for installation labor

               $ 	 for accessories

               $ 	 for other

Construction Material for  Storage Tanks (e.g. concrete or metal) 	

Is Storage Tank Above or Below Ground _________________________

Is the Tank Heated 	

Capital Equipment Cost for Method of Application (e.g., distributor truck)  $	 in 	 dollars
                                                                                              (year of purchase)

Capacity of Distributor Truck 	 gal.

Annual Operating and Maintenance Cost of Treatment

               $ ______________ in 	 dollars
                                          (year)

               S 	 per treated acre

               5	 per actual acre

Major Maintenance Problems Encountered (e.g., freezing, clogging) ______________________

Source of Water _______________   Degree of Water Treatment ______________________
                                                 B-10

-------
2.  Type of Material  in Storage  (e.g.,  coal pellets) 	  Surface Area of Storage Pile 	 ft2

Is Stated Surface Area  Projected Area or Actual Area 	

Average Daily Material  Throughput 	 tons/day  Average Material Reserve __________________________ tons
Treatment Methods:
Watering 	   Chemical  Suppressants or Binders	   Other
                                                                                       (specify)
Type(s) of Chemical(s)  Used:   (check one or more as applicable)
Lignin Sulfonate 	       Petroleum Resins 	       Salts 	       Wetting Agents
Other 	
           (specify)

Trade or Chemical Name(s) of  Dust  Suppressant(s) Used (if any) 	

Type of Diluent(s) Used (if any) 	
Application Rate 	 gal.  of  	% solution per ft2 of surface treated

Dilution Ratio ________ parts  of chemical to 	 parts 	
                                                                               (type of diluent)

Concentration of Chemical  Suppressant  as Received           % by ____________________________
                                                                   (weight or volume)

Frequency of Application ________________________________________________________
Basis for Frequency of Application
Method of Application (e.g.,  sprinkler  system or mobile distributor truck)
No. of Spray Nozzles  in Operation _____________      Type of Spray Pattern Generated

Area Treated Annually __________________________ acres/yr

No. of Spray Nozzels  in Operation __________________     Type of Spray Pattern Generated

Make of Spray Nozzle(s) _  Model No.(s)

Nozzle Capacity ______________ gpm (? ____________
Spray Angle _ °                             Maximum Area of Coverage of Spray Pattern _ ___  ft2

Designer of Sprinkler System  _ _  Address ____________________ _ ___

Phone No.  ( _ ) _ ; _                    Est. Life Expectancy of System _ yrs.
Total Capacity of On-Site  Chemical  Storage 	 gal.    No. and Capacity of Storage  Tanks
Cost of Concentrated Chemical  Dust  Suppressant Delivered to Your Plant S	/gal.  (Chemical)

                                                                      S	/gal.  (Frequent)

Gallons of Chemical  Delivered  Per Shipment 	 gal.

Gallons of Chemical  Delivered  Per Year _______________________ gal.

Capital Cost for Storage  Tanks $                      in 	 dollars
                                                          (year of purchase)
                                                   B-n

-------
lir.e Items Included in Capital Cost for Storage  Tanks.




               $	 for tanks




               j                for installation labor




               $                for accesssones




               $	 for other




Construction Material for Storage Tanks (e.g.,  concrete or metal)  	




Is Storage Tank Above or Below Ground 	




Is the Tank Heated 	




Capital Equipment Cost for Method of Application (e.g., distributor truck)  $
Caoacitv of Distributor Truck
                                                 gal.
Annual Operating and Maintenance Cost of Treatment.



               S                    in
                                                          dollars
                                            (year)




                                    per treated acre




                                    per actual acre
Major Maintenance Problems Encountered (e.g.,  freezing,  clogging)  _____



Source of Water 	     Degree of Water Treatment
                                dollars
                                                                                             (year of purchase)
Xame of Party Supplying Above Information
                                                  (Name)
(Title)
(Telephone Number)
                                                  B-12

-------
                 APPENDIX C




MISCELLANEOUS DESIGN/OPERATION AND COST DATA
                     C-1

-------
TABLE C-l.  MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR VACUUM SWEEPING PAVED ROADS
    Name of Company:

    Make:   Vac-All
        Armco, Inc.
                           Model:    E10A
    Year Purchased and Est. Life Expectancy:   1980    5  yrs.

    Name of Manufacturer:   Central Engineering Company

    Phone Number:   (513) 681-2200

    Approx.  Annual Operating Cost:   $214,000

    Fuel Consumption:    4  mpg

    Cleaning Capacity:   150  ftVhr @	 mph

<~>   Vacuum Blower Capacity:   12,000  cfm/min

    Hopper Capacity:    10  yd3
'  Location  of  Plant:    Middletown,  Ohio

        Purchase  Price:    $72,000

  No.  of This  Model  Currently in Service:    two

  Address:   4429 W.  State St.,  Milwaukee,  WI   53208

  Sales  Representative:    Bode Finn Co.,  Cincinnati, OH

  Vehicle Weight:    32,000  Ib.
           f       	•—	

  Width  of  Area Cleaned per Pass:    5  ft.

  Normal  Sweeping Speed:    5  mph.

  Velocity  at  Suction Head:    N/A  fps.
                                                   Type of Dust Control System:   wet
                                                     (i.e.,  wet or dry)

-------
                TABLE C-2.  MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR FLUSHING PAVED ROADS
I
CO
Name of Company:   Annco, Inc.                                Location of Plant:   Mlddletown, Ohio

Make:   Tractor-Ford Tank-Etnyre                 Model:   DTR                 Purchase Price:   $68,000

Year Purchased and Est. Life Expectancy:   1976    10  yrs.   No. of This Model Currently in Service:   one

Name of Manufacturer:   Ford, Etnyre                          Address:   King Equip. Co., Street Rt 63 1-75, Monroe, OH

Phone Number:   (   )     	                              Sales Representative:   King Equip. Co., Street Rt 63 1-75
                                                                                     Monroe, OH

Was Original Unit Modified to Flushing Operation:   no         Cost to Modify:   $ N/A

Approx.  Annual Operating Cost:   $57,000                      Vehicle Weight: (wet)  N/A  Ib.

Vehicle Weight: (dry)  N/A  Ib.                                Fuel Consumption:   7  mpg

Water Tank Capacity:    8,000  gal.                             Water flow at Nozzles:   188  gpm

Normal Vehicle Speed:  	 mph                              Hopper Capacity:   40  yd3

Water Pressure at Nozzles:   50  psig                         Daily Water Consumption:   30.000  gal.

Source of Water:   Treated river water                        Degree of Water Treatment:   1,800 gal/mile

-------
                  TABLE C-3.  MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR BROOM SWEEPING PAVED ROADS
o
i
     Name of Company:   Armco, Inc.

     Make:   Versa-Sweeper


     Year Purchased and Est. Life Expectancy:

     Name of Manufacturer:   Terrain King

     Phone Number:   (512) 379-1480
     Approx. Annual Operating Cost:   $65,100 — #1
                                      $57,000 - #2
                                            Model:    6300
Fuel Consumption:   3  mpg

Hopper Capacity:    N/A  yd3

Water Tank Capacity:   N/A  gal.

Cleaning Capacity:   69,700  ftVhr @  3  mph.
                                                   5  yrs.
Location of Plant:   Houston, Texas

            Purchase Price:   $18,000 - Purch 8/78
                              $20,000 - Purch 4/80
No.  of This Model Currently in Service:   two

Address:   P.O.  Box 549, Seguin, Texas

Sales Representative:   Plains Machinery Co. (Houston)

Vehicle Weight:    5,000  Ib.


Width of Area Cleaned per Pass:   7.5  ft.

Normal Sweeping Speed:   3 to 5  mph.

Water Flow at Spray Bar:   N/A  gpm

-------
                               TABLE 04.   OPERATING  SCHEDULE  OF  PAVED ROAD CONTROL EQUIPMENT
Plant
Armco,
Armco,
Armco,
Middle town
Middletown
Houston
Make of sweeper
Vac-All
Etnyre
Versa-Sweeper
Model No.
E10A
DTR
6300
Type of sweeper
(i.e. , vacuum)
Vacuum
Flushing
Broom
Hours/Day
operated
12
8
6
Days/Month
operated
28
20
20 to 25
Length of
Road Cleaned
per day
6 miles
20 miles
3 to 5 miles3
          Sweeper must make multiple passes  on all  roads.   Thus,  although it travels 20 to 30 miles/day, only 3 to

            5 miles of plant roads are cleaned.
o
I
en

-------
                                        TABLE C-5.  CLEANING FREQUENCY FOR PAVED ROADS
       Armco, Middletown

                 All paved  road  segments which are located in zones A, B, and D  (entire plant excluding  the  hot
                 metals area)  are  to be swept or flushed of surface material once during every three consecutive
                 days.

                 All paved  road  segments which are located in zone C (the hot metals area) are to be swept or
                 flushed of surface materials once during every two consecutive  days.

                 Frequency  was determined by on-site observation, vehicle counts, and types of materials
                 transported on  these  roads.

                 Dispatcher allocates  street sweepers to various zones according to schedules.


       Armco, Houston

                 Only one sweeper  truck at a time is assigned to cleaning paved  roads in the plant.  The truck is
r>                staffed for one 8-hr  turn per day, giving about 6 hr/day available for use.
cr>
                 The sweeping  pattern  covers each paved road in the plant and takes approximately 3 days to
                 complete.   The  pattern is then repeated.

                 Deviations from the pattern are made as needed, based on observations and/or special requests,
                 to provide extra  coverage of dirtier roads.

-------
                              TABLE C-6.   BREAKDOWN OF ANNUAL OPERATING AND MAINTENANCE COSTS FOR
                                               PAVED  ROAD CONTROL  EQUIPMENT
Approx. annual totat operating
Plant
Armco,
Middle town
Armco ,
Middtetown
ftrmco ,
Middle town
Armco,
Houston
Armco,
Houston
Armco,
Houston
Make of Model
sweeper No.
Vac-All E10A
Vac-All E10A
Ford, Etnyre OTR
Versa- Sweeper 6300
(Purch. 8/78)
Versa-Sweeper 6300
(Purch. 4/80)
Water truck3
Type of sweeper Cost of
(i.e., vacuum) operator
vacuum $21.00/hr
vacuum $21.00/hr
flushing $21.QQ/hr
broom $42,630
broom $42,630
$42,630
and maintenance costs for street cleaning
Cost of consumable supplies Maintenance Approx.
Gasoline Water
and oil (if applic.)
$o'.30/mile N/A
$0.30/mile N/A
$0.17/mUe N/A
$3,066 N/A
$3,066 N/A
$3,066 -0-
Other and annual
(specify) repair costs depreciation
N/A $1.41/mile
N/A $1.41/mMe
N/A $2.13/m11e
N/A $16,400 $3,000
N/A $7,900 $3,333
N/A $16,300 $5,666
Approx. annual
down-time for
Total maintenance or
costs repairs (hr) '
$214,000
$214,000
$57,000
$65,100
$57,000
$67,700
240
240
380
570
270
342
a Watering truck must be operated along with sweepers to treat paved roads.  Since water truck Is also used on unpaved roads, it would be
    realistic to charge 14.6/18.9 of  Its operating cost (or $52,300) to paved road care, and the remainder to unpaved road care.

-------
          TABLE C-7.  MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR APPLICATION OF CHEMICAL  DUST  SUPPRESSANTS  TO
                       UNPAVED  ROADS AND  SHOULDERS.
o
i
CO
      Name of Company:   Armco,  Inc.                              Location of Plant:   Middletown, Ohio


      Trade or Chemical  Name(s)  of Dust Suppressant(s) Used (if any):   Coherex®


      Type of Diluent(s) Used  (if any):   water


      Initial Application  Rate:   0.19  gal. of  16.7  % solution/yd2 surface treated


      Follow-up Application  Rate:   0.28  gal. of  11 % solution per yd2 of surface treated


      Initial Dilution Ratio:    1  parts of chemical to  5  parts  water
                               (type of diluent)


      Follow-up Dilution Ratio:   1  parts of chemical to  8  parts  water


      Concentration of Chemical  Suppressant as Received:   N/A % by 	
                   (weight or volume)
             i

Frequency of Application:   Varies from once every 2 days to once every 6 weeks


Basis for Frequency of Application:    Periodic visual  inspection


Method of Application (i.e., distributor truck):    Mobile distributor truck


Length of Road Which Can Be Treated Per day:    6. 3  miles/day


Total Capacity of OtrSite Chemical Storage:    20,000  gal.      No.  and Capacity of Storage Tanks:    2 (12,000 - 8,000)


Cost of Concentrated Chemical Dust Suppressant(s) Delivered to Your Plant:    $1.06  gal.  _+ 0.30 frt/gal.


Capital Cost for Storage Tanks:    $30,000 (installed cost for metal tanks)  in  1980  dollars
                                                                               (year of purchase)



                                                  (continued)

-------
                                                   TABLE C-7  (concluded)
       Capital Equipment Cost for Method of Application:    $70,000 (4.500 gal, cap, truck) in  1980  dollars
                                                                                             (year of purchase)


       Approx. Annual Operating and Maintenance Cost of Treatment:   $175  per mile


       Major Maintenance Problems Encountered (specify):    Coherex® will jell at 32°F and below


       If Unpaved Roads Were to be Paved, What is Approx. Cost/Mile:   $140.000 = 30 ft x 6 in.


       Approx. Life Expectancy of a Typical Paved Road:   10  yrs.
o
I

-------
            TABLE C-8.   MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR WATERING OF UNPAVED ROADS AND SHOULDERS
       Name of Company:    Armco, Inc.                                         Location of Plant:    Houston, Texas

       Type(s) of Chemical(s) Used:   (check one or more as applicable) N/A
       Lignin Sulfonate:   	     Petroleum Resins:	     Salts:   	     Wetting Agents:   	
       Other: __^	^___
                 (specify)

       Trade or Chemical  Name(s) of Dust Suppressant(s) Used (if any):    N/A

       Type if Diluent(s) Used (if any):    N/A

       Application Rate:    0.48  gal.  of  0 % solution per yd2  of surface treated

       Dilution-Ratio:   	 parts of chemical to 	 parts
                                                                  (type of diluent)

       Concentration of Chemical Suppressant as Received ___   % by
0                                                                    (weight or volume)

o      Frequency of Application:    In general,  once  every  3  days

       Basis for Frequency of Application:    As needed based on  rainfall  and humidity, or  on request.

       Method of Application (i.e., distributor truck):    Watering  truck

       Length of Road Which Can Be Treated  Per  Day  2   miles/day3

       Total Capacity of Qn-Site Chemical  Storage:   N/A   gal.       No. and  Capacity  of  Storage  Tanks:    N/A

       Cost of Concentrated Chemical Dust  Suppressant(s) Delivered  to Your Plant:   $ N/A  /gal.

       Capital Cost for Storage Tanks:   $  N/A   in	dollars
                                                   (year of  purchase)

       Capital Equipment Cost for Method of Application:   $34,000   in 	1978	  dollars
                                                                      (year of purchase)


                                                        (continued)

-------
o
i
                                                  TABLE C-8  (concluded)
      Approx.  Annual Operating and Maintenance Cost of Treatment:    $3,580  per mile of unpaved road In plant


      Major Maintenance Problems Encountered (specify):    Replaced pump twice,  replaced clutch twice


      If Unpaved Roads Were to be Paved,  What is  Approx.  Cost/Mile:    $170,000  (est.)


      Approx.  Life Expectancy of a Typical  Paved  Road:    2  yrs.
         Watering truck is used to water paved roads  prior to their treatment by broom sweeper.   As time permits,

           the watering truck treats unpaved roads.

-------
    TABLE C-9.   MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR APPLICATION OF CHEMICAL DUST SUPPRESSANTS
                  TO UNPAVED PARKING LOTS AND EXPOSED AREAS.
Name of Company:    Armco, Inc.                                     Location of Plant:    Middletown, Ohio

Trade or Chemical Name(s) of Dust Suppressant(s) Used (if any):    Coherex®

Type of Oiluent(s) Used (if any):   water

Application Rate:   910  gal.  of  16.7 % solution per acre of surface treated up to 1,364 gal.  of 11.1%

Initial Dilution Ratio:   \  part of chemical  to  5  parts  water
                         (type of diluent)

Follow-up Dilution Ratio:   1  part of chemical  to  8  parts  water

Concentration of Chemical Suppressant as Received:    N/A % by 	
        (weight or volume)

Frequency of Application:   Two to three coats per year

Basis for Frequency of Application:   Periodic visual inspection

Method of Application (i.e., distributor truck):   Mobile distributor truck

Area Which Can be Treated Per Day:   6.1  acres/day

Approx. Annual Operating and Maintenance Cost  of Treatment:    $180  per acre

Major Maintenance Problems Encountered (specify):    Freezing - 32°F and below

If Unpaved Parking Lots or Other Exposed Areas Were to be Paved, What is Approx.  Cost/Acre:    $29^000
                                                ($6.00/yd2)

Approx. Life Expectancy of a Typical Paved Parking Lot:   N/A  yrs.

-------
             TABLE C-10.   MISCELLANEOUS OPERATION/DESIGN AND COST DATA FOR WATERING OF STORAGE PILES

Name of Company:    Armco, Inc.                                    Location of Plant:   Middletown, Ohio
1.   Type of Material in Storage:   Coal                        Surface Area of Storage Pile:   390,000  ft2
    Average Daily Material Throughput:  ^800.. tons/day       Average Material Reserve:   34,000  tons
    Treatment Methods:
    Watering:   %'          Chemical Suppressants or Binders:  	         Other:  	
    Frequency of Application:   Once every 2 days
    Basis for Frequency of Application:   Visual inspection
    Method of Application (i.e., sprinkler system):   Permanent sprinkler system
    No.  of Spray Nozzles in Operation:   10                    Type of Spray Pattern Generated:   N/A
    Make of Spray Nozzle(s):   Nelson                          Model No.(s):   Nelson Big Gun P-2.00T
    Nozzle Capacity:   500  gpm @  100  psig
    Spray Angle  27°  above horizontal                         Maximum Area of Coverage of Spray Pattern:   394,000   ft2
    Designer of Sprinkler System:   Old Field Equipment Co.    Address:   430 W.  Seymore Ave., Cincinnati, Ohio
    Phone No.:   (513) ,821-5582 (Bob Meier)                    Est. Life Expectancy of System:   20, years
    Capital Equipment Cost for Method of Application:   $350,000  in 	1980'        dollars
                                                                    (year of purchase)
    Approx. Annual Operating and Maintenance Cost of Treatment:  _$	 in  	N/A	  dollars
                                                                             (year of record)
    Maintenance Problems Encountered (i.e., freezing, clogging):   Clogging
    Source of Water:   Storm sewer run-off                     Degree of Water Treatment:    35,000 gal/total  area

Name of Company:    Armco, Inc.                                  Location of Plant:   Middletown, Ohio
2.   Type of Material in Storage:   Limestone                   Surface Area of Storage Pile:   Varies  ft2
    Average Daily Material Throughput:   Varies  tons/day      Average Material Reserve:   Varies  tons
    Treatment Methods:
    Watering:   V            Chemical Suppressants or Binders:  	         Other:  	
    Concentration of Chemical Suppressant as Received:       % by
                                                                    (weight or volume;
    Frequency of Application:   Based upon weather conditions
    Basis for Frequency of Application:   Periodic visual inspection
    Method of Application (i.e., sprinkler system):   Mobile water truck
    Capital Equipment Cost for Method of Application:   533,000 (1.500 gal, cap, truck)   in 	1979	  dollars
                                                                                            (year  of purchase)
    Approx. Annual Operating and Maintenance Cost of Treatment:   $173,000  in 	1980	 dollars
                                                                               (year of record)
    Maintenance Problems Encountered (i.e., freezing, clogging):   None
    Source of Water:    Treated river water                     Degree of Water Treatment:   None - general  plant  water
                                                   (continued)

-------
                                             TABLE C-10  (continued)
Name of Company:    Armco, Inc.
3.   Type of Material  in Storage:    Taconits pellets
    Average Daily Material Throughput:    2,979  tons/day
    Treatment Methods:
    Watering:  _j_
                       Chemical Suppressants or Binders:
Location of Plant:   Middletown. Ohio
Surface Araa of Storage Pile:   Varies  ft2
Average Material Reserve:    Varies  tons

               Other:
                                                                                             (specify)
    Frequency of Application:
    Basis for Frequency of Application:   Periodic visual inspection
    Method of Application (i.e., sprinkler system):   Mobile water truck
    Capital Equipment Cost for Method of Application:   $33,000  in 	
                                                                       1979
                        dollars
                                                                    (year of purchase)
    Approx.  Annual Operating and Maintenance Cost of Treatment:   S173.OOP  in
    Maintenance Problems Encountered (i.e., freezing, clogging):   None
                                                                                 1980
                                 dollars
                                                                           (year of record)
    Source of Water:   Treated river water
Name of Company:   Armco, Inc.
4.  Type of Material in Storage:   Coal (main pile)
    Average Daily Material Throughput:   1,110  tons/day
                                                           Degree  of Water Treatment:    None-general  plant water
                                                           Location of Plant:    Houston, Texas
                                                           Surface Area of Storage Pile:   app.  312,000  ft2
                                                           Average Material Reserve:    est.  55.000  tons
    Treatment Methods:
    Watering:   V
                        Chemical  Suppressants  or Binders:
               Other:
    Type(s) of Chemical(s) Used:  (check one or more as applicable) N/A
    Lignin Sulfonate:  	        Petroleum Resins:  	        Salts:  	
    Other:           _
               (specify)
    Trade or Chemical Name(s) of Oust Suppressant(s) Used  (if any):   N/A
    Type of Oiluent(s) Used (if any):   N/A
    Application Rate:   0.16  gal. of  0 % solution per ft8 of  surface treated
    Dilution Ratio:        .parts of chemical to _^___ parts 	
                                                                                        (specify)

                                                                                     Wetting Agents:
    Concentration of Chemical Suppressant as  Received:
    Frequency of Application:   As  needed
                                                            (type of diluent)
                                                        J- by       	
                                                                (weight or volume)
                                                                                               N/A
    Basis  for  Frequency  of  Application:   Operated  if  natural  rainfall  does  not provide 1/4 in.  of water
    Method of  Application (i.e.,  sprinkler  system):    Spray  system
                                          See  below              Type  of  Spray Pattern Generated:    Overlapping circular
                                                                Model  No.(s):    See below
                                                                NOZZLES:      Number
No.  of Spray Nozzles in Operation:
Make of Spray Nozzle(s):   Johns-ttenville
Nozzle Capacity:   100.4  gpm @  50  psig
                        Model  No_,
                         586G2E
                         886G2E
                                                    (continued)
                                                       C-14

-------
                                             TABLE C-1Q  (continued)
    Spray Angle:   .Std.  - 26". can tilt to 30 to 35°           Maximum Area of Coverage of Spray Pattern:   330.000   ft2
    Designer of Sprinkler System:    Watson Pi St. Co.,  Inc.     Address:   P.O. Box 36211, Houston, Texas  77036
    Phone No.:    (713) 771-5771                                Est. Life Expectancy of System:   20  years
    Total Capacity of On-Site Chemical Storage:   N/A  gal.    No. and Capacity of Storage Tanks:   1 - 76,500 gal.
    Cost of Concentrated Chemical  Dust Suppressant Delivered to Your Plant:   $ N/A /gal.
    Capital Cost for Storage Tanks:    $45,OOP  in        1975	 dollars
                                                   (year of purchase)
       (installed cost for underground concrete tank)
    Capital Equipment Cost for Method of Application:    $216,000  in        1975        dollars
                                                                     (year of purchase)
       (includes storage tank, pumps, controls, piping, motors, and spray system)
    Approx. Annual Operating and Maintenance Cost of Treatment:   $8,600  in  1980  dollars (estimated)
    Maintenance Problems Encountered (i.e., freezing,  clogging):  freezing, plugging
    Source of Water:   Cooling water blowdown                  Degree of Water Treatment:   None

Name of Company:    Armco. Inc.                                 Location of Plant:   Houston, Texas
5.   Type of Material in Storage:   0081(surge pile)           Surface Area of Storage Pile:   16,000  ft8
    Average Daily Material Throughput:   1,000  tons/day       Average Material Reserve:   12,OOP  tons
    Treatment Methods:
    Watering:  __j L          Chemical Suppressants or Binders:  _____          Other:
                                                                                           (soecTfy)
    Type(s) of Chem'cal(s) Used:   (check one or more as applicable) N/A
    Lignin Sulfonate:   	       Petroleum Resins:  	      Salts:  	      Wetting Agents:  _____
    Other:   ________^__
               (specify)
    Trade of Chemical  Name(s) of Dust Suppressant(s) Used (if any):   N/A
    Type of Diluent(s) Used (if any):   N/A
    Application Rate:    0.16  gal. of  0 % solution per ft2 of surface treated
    Dilution Ratio:   	 parts of chemical to 	 parts 	   ^	)
                                                               (type of diluent))
                                                                                        )           N/A
    Concentration of Chemical Suppressant as Received:       % by                       )
                                                                    (weight or volume)
    Frequency of Application:   As needed
    Basis for Frequency of Application:   Operated if natural rainfall does not provide I/a in. of water
    Method of Application (i.e., sprinkler system):   Spray system
    No. of Spray Nozzles in Operation:   6         Type of Spray Pattern Generated:  Overlapping half circles
    MaKe of Spray Nozzle(s):   Johns-Manville                  Model No.(s):   886G2E
    Nozzle Capacity:   100.4  gpra @  60  psig
    Spray Angle:    Std. 26°, can tilt to 30 to 35°             Maximum Area of Coverage of Spray Pattern:   ^0.700  ft2

                                                   (continued)
                                                       C-15

-------
                                        TABLE C-10.   (concluded)
Designer of Sprinkler System:    Armco, Inc.                 Address:   P.O.  Box 95120, Houston, Texas  77013
Phone No.:    (713)  96Q-6Q20                               Est.  Life Expectancy of System:   20  years
Total Capacity of On-Site Chemical  Storage:    N/A  gal.     No.  and Capacity of Storage Tanks:   1 - 10,000 gal.
Cost of Concentrated Chemical  Dust Suppressant Delivered to Your Plant:    £ N/A /gal.
Capital Cost for Storage Tanks:    $5,000  in 	1975	  dollars
                                             (year of purchase)
   (installed cost for underground concrete tank apportioned to  surge pile)
Capital Equipment Cost for Method of Application:   S72.20Q  in  	1975	  dollars
                                                                (year of purchase)
   (installed cost for storage tank, pumps, controls, piping, motors, and spray system)
Approx. Annual Operating and Maintenance Cost of Treatment:   $8,SOO  in  1980  dollars  (estimated)
Maintenance Problems Encountered (i.e., freezing, clogging):   Freezing,' plugging
Source of Water:   Cooling water blowdown                  Degree of Water Treatment:    None
                                                 C-16

-------
           TABLE C-ll.  MISCELLANEOUS OPERATION/DESIGN AND COST  DATA  FOR  APPLICATION OF CHEMICAL DUST
                          SUPPRESSANT TO STORAGE PILES
Name of Company:   Bethlehem Steel                           Location  of  Plant:    Burns  Harbor,  Indiana
Type of Material in Storage (e.g., coal, pellets):  Coal1    Surface Area of  Storage Pile:    2   ^
Is Stated Surface Area Projected Area or Actual Area:   2
Average Daily Material Throughput:   l.OOO1  tons/day        Average Material  Reserve:    88,OOP1  tons
Treatment Methods:
Watering:  	        Chemical Suppressants or Binders:    X          Other:
                                                                                      (specify)
Type(s) of Chemical(s) Used:  (check one or more as applicable)
Lignin Sulfonate:   	         Petroleum Resins:  	          Salts:   _____         Wetting Agents:   _____
Other:   X (latex binder)
            (specify)
Trade or Chemical Name(s) of Dust Suppressant(s) Used  (if  any):    Dow  Chemical  M-167  Chemical binder
Type of Diluent(s) Used (if any):   Water
Application Rate:  _____ gal. of ____% solution per ft2 of  surface  treated
Dilution Ratio:   55  parts of chemical to  2.000  parts      water
                                                         Itype~o f  d fTuent)
Concentration of Chemical Suppressant as Received:   100 % by        weight
                                                                (weight or volume)
Frequency of Application:   Once per week
Basis for Frequency of Application:   SUPjective evaluation of  effectiveness
Method of Application (e.g., sprinkler system or mobile  distributor  truck:    Mobi 1e distributor (spray)  truck
Area Treated Annually:   2  acres/year
No. of Spray Nozzles in Operation:   3                       Type of  Spray Pattern  Generated:    8
Make of Spray Nozzle(s):  _____                                Model  No.(s):   _____
Nozzle Capacity:   s  gpm @  3  psig
Spray Angle:  ___°                                           Maximum  Area  of Coverage of Spray Pattern:    3  ft2
Designer of Sprinkler System:  _____                           Address:   _____
Phone No.:   (   )  3   .                                     Est. Life  Expectancy of System:   _____ years
Total Capacity of On-Site Chemical Storage:  _____ gal.        No.  and  Capacity of Storage Tanks:  _____
  i
Cost of Concentrated Chemical Dust Suppressant  Delivered to Your Plant:    $4.40. /gal,   (chemical)
                                                                          _$	/gal.   (freight)
Gallons of Chemical Delivered per Shipment:   1,100 to 2,200 gal.
Gallons of Chemical Delivered per Year:   13,200   gal.5
Capital Cost for Storage Tanks:   S4   in 	*	    dollars
                                         (year  of  purchase)
                                                   (continued)
                                                       C-17

-------
                                             TABLE  C-ll   (concluded)
Line Items Included in Capital  Cost for Storage  Tanks:
         $	*	 for tanks
         S      *        for installation  labor
         $      *        for accessories
         S      *        for other
Construction Material  for Storage Tanks (e.g., concrete  or  metal):    4
Is Storage Tank Above  or Below  Ground:   4                  Is  the Tank  Heated:   4
Capital  Equipment Cost for Method of Application (e.g.,  distributor  truck):  S 3  in  	3	 dollars
                                                                                     (year of purchase)
Capacity of Distributor Truck:    3   gal.
Annual  Operating and Maintenance Cost of Treatment:
                        in       8	 dollars
                              (year)
         S  .    3	 per treated acre
         S      3       per actual  acre
Major Maintenance Problems Encountered (e.g.,  freezing,  clogging):    3
Source of Water:   Lake Michigan      Degree  of Water  Treatment:    Removal  of  solids by  screening  and  straining

1  The reported information is apolicable to low volatile  coal.
2  This information is not readily  available.
3  The mobile distributor truck used to  aoply  dust  suppressant  solution  to low  volatile  coal  piles  is owned
     and operated by Correct Maintenance  Corporation  (CMC),  2000  Dombey  Road, Portage,  Indiana  (219/762-2157).
     Reportadly,  technical information concerning this  vehicle  is considered  to be confidential by  CMC.
4  Oust suppressant material is received  and stored in  55  gal.  drums.
5  Volume purchased during the period July 1980 through August  1981.
5  This information is considered to be  confidential  by Bethlehem.
                 - •• .-  ;•,... i  Protection  Agency
                ',;.  "-'.'
               ..I...:  t.'  •-'
               i,  Illinois
                                Street
                                                    C-18

-------