jTTW

L/A-625/1-87-001
                           Center for Environmental
                           Research Information
                           Cincinnati OH 45268
             Technology Transfer
Research Laboratory
   ti OH 45268
                                        EPA 625 1-87 001
&EPA      Design Manual
             Phosphorus Removal

-------
                                      EPA/625/1-87/001
                                       September 1987
      Design Manual
  Phosphorus  Removal
   U.S. Environmental Protection Agency
    Office of Research and Development

Center for Environmental Research Information
          Cincinnati, OH 45268

   Water Engineering Research Laboratory
          Cincinnati, OH 45268
                       U.S. Environmental Protection Agency
                       Region 5, Library (PL-12J)
                       77 West Jackson Boulevard, IZth Floor
                       Chicago. IL  60604-3590

-------
                                       Notice
This document has been reviewed in  accordance with  the U.S. Environmental Protection
Agency's peer and administrative review  policies and approved for publication. Mention of trade
names or commercial products does not constitute endorsement or recommendation for use.

This document is  not intended to be a guidance or support document for a specific regulatory
program. Guidance  documents are  available from EPA and must be consulted to address
specific regulatory issues.
              -'C

-------
                                     Contents


Chapter                                                                       Page


1   INTRODUCTION  	   1

    1.1 Purpose  	   1
    1.2 Scope   	   1
    1.3 Using the Manual  	   1
    1.4 Reference	   2

2   SELECTING A PHOSPHORUS REMOVAL STRATEGY  	   3

    2.1 Description of Approach 	   3
    2.2 Information and Monitoring Data Required  	   3
       2.2.1 New System Data Requirements   	   3
       2.2.2 Existing System Data Requirements  	   5
    2.3 Possible Phosphorus Removal Alternatives  	   5
       2.3.1 Chemical Addition Alternatives  	   5
       2.3.2 Biological Phosphorus Removal Alternatives	   6
    2.4 Phosphorus Removal System Selection Strategy  	   8

3   PHOSPHORUS REMOVAL BY BIOLOGICAL PROCESSES  	   15

    3.1 Introduction and Theory 	   15
       3.1.1 Biological Phosphorus Removal Mechanism  	   16
    3.2 Applications   	   18
       3.2.1 Process Descriptions  	   19
    3.3 Performance  	   25
       3.3.1 Phostrip Performance  	   25
       3.3.2 Modified Bardenpho Process Performance   	   26
       3.3.3 A/O Process Performance   	   27
       3.3.4 Operationally Modified Activated Sludge Process  Performance   	   29
       3.3.5 Factors Affecting Performance  	   30
    3.4 Equipment Requirements   	   36
    3.5 Design Methodology   	   36
       3.5.1 Phostrip Process	   36
       3.5.2 Mainstream Biological Phosphorus  Removal Processes   	   38
    3.6 Process Modifications to Improve Performance	   43
    3.7 Retrofit Considerations 	   44
    3.8 Case Histories	   45
       3.8.1 Phostrip Process - Little Patuxent, Maryland   	   45
       3.8.2 Modified Bardenpho Process - Kelowna, Canada    	   46
       3.8.3 A/O Process - Pontiac, Michigan    	   47
    3.9 Costs 	   47
    3.10 References  	   50
                                         in

-------
                                       Contents (continued)


x      Chapter                                                                          Page

       4   PHOSPHORUS REMOVAL BY CHEMICAL ADDITION  	   55

           4.1  Introduction and Theory  	   55
               4.1.1 Aluminum Compounds  	   55
               4.1.2 Iron Compounds 	   56
           4.2 Application Points   	   57
               4.2.1 Mineral Addition Before Primary Clarification   	   58
               4.2.2 Mineral Addition to Secondary Processes  	   59
               4.2.3 Mineral Addition at Multiple Points	   60
           4.3 Performance  	   60
           4.4 Equipment Requirements  	   60
               4.4.1 Chemical Handling and Storage  	   60
               4.4.2 Dry Chemical Feeding and Dissolving   	   64
               4.4.3 Liquid Chemical and Solution Feeding  	   65
               4.4.4 Chemical Dosage Control   	   66
               4.4.5 Chemical Mixing and Flocculation  	   68
               4.4.6 Clarification   	   69
           4.5 Design Methodology  	   69
               4.5.1 Wastewater Characterization  	   69
               4.5.2 Determination of Chemical Doses  	   70
               4.5.3 Selection of Chemicals  	   70
               4.5.4 Evaluation of Existing Unit Processes   	  70
               4.5.5 Conduct of Full-Scale Trials   	  71
               4.5.6 Design of Chemical  Handling System   	  71
               4.5.7 Design of Liquid Processes  	  73
               4.5.8 Design of Sludge Handling System  	  74
               4.5.9 Design Example  	  75
           4.6 Retrofit Considerations  	  77
           4.7 Case Histories	  77
               4.7.1 Orillia, Ontario  	   77
               4.7.2 Elizabethtown, Pennsylvania	   78
               4.7.3 Little Hunting Creek, Virginia  	   79
           4.8 Costs  	   80
           4.9 References  	   80

        5  SLUDGE HANDLING   	   83

           5.1 Introduction  	   83
           5.2 Current Practice for Handling Chemical Sludges  	   83
               5.2.1 Introduction   	   83
               5.2.2 Points of Chemical Addition and Methods of Combining Sludges  	   83
               5.2.3 Sludge  Generation Rates and Characteristics   	   84
               5.2.4 Prevalence of Various Sludge Treatment and Disposal Options  	   87
           5.3 Sludge Derived from  Addition of Aluminum Salts   	   87
               5.3.1 Sludge  Characteristics 	   87
               5.3.2 Sludge  Generation Rates  	   88
               5.3.3 Thickening  	   92
               5.3.4 Stabilization  	   93
               5.3.5 Conditioning  	   95
               5.3.6 Dewatenng  	   95
               5.3.7 Incineration  	   99
               5.3.8 Disposal  	   99
                                                   IV

-------
                                Contents (continued)
Chapter                                                                          Page

    5.4 Sludge Derived from Addition of Iron Salts  	    100
       5.4.1  Sludge Characteristics 	    100
       5.4.2  Sludge Generation Rates  	    100
       5.4.3  Thickening  	    101
       5.4.4  Stabilization   	    103
       5.4.5  Conditioning   	    104
       5.4.6  Dewatering  	    104
       5.4.7  Incineration  	    107
       5.4.8  Disposal  	    107
    5.5 Sludges Derived From Biological Phosphorus Removal Processes  	    108
       5.5.1  Characteristics  	    108
       5.5.2  Sludge Generation Rates  	    108
       5.5.3  Thickening  	    108
       5.5.4  Stabilization   	    108
       5.5.5  Conditioning   	    109
       5.5.6  Dewatering  	    109
       5.5.7  Disposal  	    109
    5.6 Sludges Derived from Addition of Lime  	    109
    5.7 Case  Histories	    110
       5.7.1  Baltimore, Maryland	    110
       5.7.2  Lorton, Virginia  	    110
    5.8 Costs 	    112
    5.9 References  	    112

-------
                                       Figures


Number                                                                         Page

2-1    Phosphorus Removal System Selection Strategy  	   9

3-1    Biological phosphorus and BOD removal due to anaerobic-aerobic
       contacting	   16
3-2    Acetate assimilation and phosphorus release vs. anaerobic time   	   17
3-3    Schematic of biological phosphorus removal mechanism 	   19
3-4    Commercial biological phosphorus removal processes - Phostrip,
       Modified Bardenpho, A/0  	   20
3-5    Biological phosphorus removal - Sequencing Batch Reactor   	   23
3-6    UCT process flow schematics   	   24
3-7    Operationally modified activated sludge system for
       biological phosphorus  removal  	   24
3-8    Combination biological phosphorus removal system  	   24
3-9    Maximum effluent soluble P concentration for total effluent  P  < 1.0 mg/l  	   31
3-10   Effluent soluble P concentration vs. influent TBOD:TP ratio  	   32
3-11   Reported effects of pH on biological phosphorus removal   	   35
3-12   TBOD:TP removal vs. solids retention time (SRT)  	   40
3-13   Pre-denitrification and  post-denitrification schemes in  biological
       phosphorus removal systems 	   41
3-14   Specific denitrification rate  	   42
3-15   Primary sludge fermentation design schemes 	   44

4-1    Alternative schemes for mineral  addition for phosphorus removal  	   58
4-2    Impact of point of addition on effectiveness of phosphorus  removal
       using aluminum  	   59
4-3    Typical dry chemical feed  system  	   64
4-4    Liquid chemical feed alternatives for elevated storage  	   67
4-5    Liquid chemical feed alternatives for ground storage 	   67
4-6    Typical flash mix tank  	   69
4-7    Typical mechanically mixed flocculating clarifier  	   70

5-1    Volumetric sludge production from EPA survey   	   85
5-2    Mass sludge production from EPA survey  	   86
5-3    Range of thickener operating periods for  ferric-primary sludge   	   102
5-4     Range of thickener operating periods for  alum-primary sludge   	   102
5-5    Comparison of sludge quantities, conditioning costs, and
       hauling costs before and after phosphorus removal; Baltimore, MD   	   111
                                           VI

-------
                                        Tables
Number                                                                         Page

2-1     Information Required for Discharge Limits  	   4
2-2     Information Required for Influent Wastewater Characteristics  	   4
2-3     Advantages and Disadvantages of Metal Salt Addition for Phosphorus
        Removal  	   7
2-4     Advantages and Disadvantages of Lime Addition for Phosphorus Removal   	   7
2-5     Advantages and Disadvantages of Biological Phosphorus Removal Processes  ...   8
2-6     Application Criteria Matrix - New or Existing Facility; Type of Nutrient
        Removed  	   9
2-7     Application Criteria Matrix - Ability of Process to Meet Effluent Phosphorus
        Limitations  	   10
2-8     Application Criteria Matrix - Ability of Process to Remove NH4 or TN    	   10
2-9     Application Criteria Matrix - Effect of Plant Size on Process Applicability   	   12
2-10    Application Criteria Matrix - Effect of TBOD:TP Ratio <20 on Process
        Applicability	   12
2-11    Application Criteria Matrix - Effect of High Wastewater Alkalinity
        on Process Applicability 	   13
2-12    Application Criteria Matrix - Effect of Sludge Production  on Process
        Applicability	   13
2-13    Application Criteria Matrix - Effect of O&M Requirements on Process
        Applicability	   14
2-14    Application Criteria Matrix  - Effect of Short-Term  Life on Process
        Applicability	   14

3-1     Molar Ratios of Ions Co-Transported with Phosphorus	   18
3-2     Typical Operating Conditions for Biological Phosphorus Removal Processes  ....   21
3-3     SBR Operating Sequence - Biological Phosphorus Removal	   23
3-4     Basic Design Information for Full-Scale Phostrip Plants    	   26
3-5     Performance Data Summary for Full-scale Phostrip Plants	   26
3-6     Modified Bardenpho Process Full-scale Plant Design Summary	   27
3-7     Palmetto, FL Modified Bardenpho Performance
        (April  1981 - March 1982Monthly Averages)   	   28
3-8     Kelowna, Canada Modified Bardenpho Process Performance Results
        of Cumulative  Frequency Plot of Data  	   28
3-9     Summary of A/O Process Average Effluent Quality, Largo, FL  	   29
3-10    Pontiac, Ml A/O System Operating Conditions 	   29
3-11    Full-scale A/O Process Performance, Pontiac, Ml   	   29
3-12    Operating Conditions for Operationally Modified Activated Sludge Systems  	   30
3-13    Average Performance of Operationally Modified Activated Sludge Systems  	   30
3-14    Approximated  Mass of Phosphorus Storage Compounds	   39
3-15    Summary of Phostrip Process Treatment Performance for Little
        Patuxent Plant - April 1985	   46
3-16    Cost comparison - Case 1: Phosphorus removal (effluent TP  =  1 mg/l)   	   49
3-17    Comparison - Case 2: Phosphorus removal (effluent TP =  2 mg/l)   	   49
                                          VII

-------
                                 Tables (continued)
Number  	   Page

3-18   Cost comparison - Case 3: Phosphorus removal plus nitrification
       (effluent TP = 2 mg/l; NH4-N  = 1 mg/l)   	   49
3-19   Cost comparison - Case 4: Phosphorus removal plus nitrification
       (effluent TP = 2 mg/l; TN  = 3 mg/l) 	   49

4-1    Characteristics of Aluminum and Iron Salts   	   57
4-2    Distribution of Selected Phosphorus Removal Facilities by Point of Chemical
       Addition and Cation Used  	   59
4-3    Potential Effectiveness of Primary and Secondary Treatment With and
       Without Mineral Addition for Phosphorus Removal   	   59
4-4    Performance of Facilities Using Mineral Salts for Phosphorus Removal  	   61
4-5    Chemical Dosage Summary from Ontario Treatability Studies   	   63
4-6    Types of Chemical Feeders  	   66
4-7    Values of Ky for Determining Impeller Power Requirements	   73
4-8    Recommended Overflow Rates for Conventional Clarifiers
       Receiving Wastewater Coagulated with Mineral Salts  	   75
4-9    Summary of Plant Data During Single-Point and Dual-Point Alum  Addition     ...   78
4-10   Summary of Performance at Elizabethtown, PA  	   79
4-11   Summary of Performance at Little Hunting Creek, VA 	   80
4-12   Cost Estimates for Phosphorus Removal by Mineral Addition  	   80

5-1    Combination of Chemical Sludges with  Other Sludges for Processing as
       Practiced by Plants in EPA Survey  	   84
5-2    Combination of Chemical Sludges with  Other Sludges for Processing as
       Practiced by Plants in EPA Survey  	   88
5-3    Prevalence of Treatment and Disposal Processes for Chemical Sludges
       Among Plants in EPA Survey   	   89
5-4    Typical Gravity  Thickener Design Criteria	   92
5-5    Summary of Vacuum Filter Performance for Alum-Primary Sludge   	   97
5-6    Design vacuum filtration rates  for conventional sludges  	   97
5-7    Component vacuum filtration characteristics  	   97
5-8    Design Factors for Vacuum Filtration of Conventional Plus Aluminum
       Sludges  	   98
5-9    Potential Problems with Chemical Sludge Incineration 	   99
5-10   Typical Gravity Thickener Design Criteria	   102
5-11   Effect of Phosphorus Removal on Gravity Thickening Properties of
       Alum-Primary and Ferric-Primary Sludge	   102
5-12   Performance of Flotation Thickeners for Treating Iron Sludges	   103
5-13   Summary of Vacuum Filter Performance for Iron-Primary Sludge    	   105
5-14   Design Factors for Vacuum Filtration of Conventional Plus Iron Sludges  	   106
                                          VIII

-------
                               Acknowledgments


Many individuals contributed  to  the  preparation  and review of this  handbook.  Contract
administration was provided by the Center for Environmental Research Information, Cincinnati,
Ohio.

Major Authors:
Robert P. G. Bowker - J. M. Smith & Associates, PSC, Cincinnati, Ohio
H. David Stensel - University of Washington, Seattle, Washington

Contributing Authors:
George L.  Hartmann - J. M. Smith & Associates, PSC, Cincinnati,  Ohio
John M. Smith - J. M. Smith & Associates, PSC, Cincinnati, Ohio

Reviewers:
Walter  Gilbert  - EPA-OMPC,  Washington,  DC
Wen H. Huang - EPA-OMPC, Washington, DC
James  Wheeler - EPA-OMPC, Washington, DC
Richard C. Brenner - EPA-WERL,  Cincinnati, Ohio
Francis  Evans III - EPA-WERL,  Cincinnati, Ohio
Joseph B. Farrell - EPA-WERL,  Cincinnati, Ohio
James  F.  Kreissl -  EPA-WERL, Cincinnati, Ohio
James  A.  Heidman -  EPA-WERL, Cincinnati, Ohio
Sherwood  Reed - USACOE, Hanover, New Hampshire
Glen T. Daigger - CH2M/HMI,  Denver, Colorado

Contract Project Officer:
Denis J. Lussier -  EPA-CERI, Cincinnati,  Ohio
                                        IX

-------
                                             Chapter 1
                                           Introduction
1.1  Purpose

The  Environmental Protection Agency has sponsored
many research and demonstration studies at several
cities in the past few years to advance the knowledge
of phosphorus removal. Local and state governments
and  private  industries have  also contributed to this
work. This manual is intended to summarize process
design  information  for  the  best  developed
phosphorus-removal methods  that have resulted
from this governmental and private effort.


1.2  Scope
The   sources  and quantities of  phosphorus in
domestic  wastewaters  vary  significantly.  Industrial
contribution, non-point source  runoff, the  use or
nonuse of phosphate-bearing detergents, and  other
factors make generalization  of expected wastewater
phosphorus  concentration impossible.  The  manual
user should ascertain the phosphorus concentrations
(actual or expected) for  the specific  wastewater in
question.

This manual discusses several proven phosphorus-
removal  methods,  including phosphorus removal
obtainable through biological activity as  well  as
chemical precipitation techniques.

Biological phosphorus removal was not included in
the previous version of this manual and represents a
major addition.

Appropriate  chemistry for phosphorus removal  by
chemical addition is presented where appropriate for
illustrative purposes.

The  use  of  lime as  a  chemical  precipitant for
phosphorus removal, which received major treatment
in the previous version, is not covered  in this  manual
due  to its  loss  of  popularity as  a  phosphorus-
removal technique. The reasons for current infrequent
use of lime are discussed  in Chapter 4. The user can
refer to  several  other  documents   for detailed
information and  design  criteria  for lime addition,
including the previous version of this manual (1).
Treatment methods in which  phosphorus  removal
occurs,  but  is  not  a principal  objective,  are also
omitted. The latter group of processes includes such
technologies as ion  exchange,  reverse osmosis and
other demineralization treatments  which at present
are  more  closely  associated  with  wastewater
renovation and  reuse than  with  pollution  control.
These will be included in updated  versions of the
manual when appropriate.

The  information included  was obtained from the
available  literature,  progress  reports  from
demonstration  studies,  and  private  communications
with  investigators actively working in the field. Design
guidelines have  been developed from these sources.

The  information contained  in this manual is  oriented
toward design methods and operating procedures for
removal of phosphorus from wastewater.

Cost  information from  actual phosphorus-removing
installations is presented   when available.  Planning
level cost estimates are also included.
1.3 Using the Manual
Chapter 2  presents  a  recommended approach to
selecting a phosphorus  removal  strategy.  This
approach identifies the  required effluent  phosphorus
limits  and  screens  potential  phosphorus-removal
techniques  to  identify those processes  capable of
meeting the specified requirements.

The screening process is  a step-by-step procedure
that identifies the information required to make the
engineering judgements  necessary  at each step of
the process.  After  applying  the  screening
methodology, the manual user can go to  the specific
chapter  in  the  manual  dealing  with  the  potential
phosphorus-removal  processes  available  for his
specific case:

  Chapter 3 -  biological phosphorus removal.

  Chapter 4 -  phosphorus  removal by  mineral
              addition.

-------
Chapter 5 discusses all aspects of sludge handling
associated  with  sludges  generated  from
phosphorus-removing  facilities.


1.4 Reference
When an NTIS number is cited in a reference, that
reference is available from:

      National Technical Information Service
      5285 Port Royal Road
      Springfield, VA22161
      (703)  487-4650

1. Process  Design  Manual for  Phosphorus
   Removal.  EPA 625/1-76-001 a,  NTIS No.  PB-
   259150,  U.S.  Environmental Protection Agency,
   Center for  Environmental Research Information.
   Cincinnati, OH, 1976.

-------
                                            Chapter 2
                         Selecting a Phosphorus Removal Strategy
2.1 Description of Approach

The approach  described  herein for  selecting  a
phosphorus  removal  system  identifies the  required
effluent  phosphorus limits,  and  then  screens
phosphorus removal processes  to  identify  those
processes capable of meeting specified requirements.
All  alternative phosphorus removal technologies are
considered initially,  but  non-applicable  technologies
are  eliminated  through  a sequential  selective
screening process.

The selective screening  methodology is a  step-by-
step procedure that identifies information required to
make the necessary engineering judgements at each
step of the process. Brief descriptions of the various
chemical  and  biological  phosphorus  removal
processes and the advantages  and disadvantages of
each process have been provided. The effectiveness
of the selective screening process  is dependent upon
the amount and level of detail of the initial information
used.

For each specific phosphorus removal alternative
considered, the sections of the manual dealing with
that process should be  read  carefully before final
selection of a phosphorus  removal  system.  Other
sources  of background  information   include
manufacturers or  proprietors of phosphorus  removal
technologies, and site visits to  operating phosphorus
removal  plants.  The  process  should  not be
considered completely  rigorous,   since  some
subjective judgements are required. It is intended as
a comprehensive overall guide to the  selection of an
appropriate phosphorus removal process.

The selection procedure  must consider all aspects of
the  phosphorus removal  process including its impact
on  plant  performance, operations  and maintenance.
Important factors  are:  a) degree of  phosphorus
removal required, b) size of plant, c) impact on sludge
handling,  d) permanent or temporary nature  of
phosphorus removal requirement, e) total cost  and f)
impact on operation and maintenance.

The system  screening process  is  presented  in
Section 2.4. The  basic information needed  to apply
the  screening procedure is discussed  in Section 2.2,
and  a  brief description of  the  state-of-the-art
phosphorus  removal  technologies  is  presented in
Section 2.3.

2.2  Information  and  Monitoring  Data
Required

The  information  and monitoring  data required for
selecting a phosphorus removal system are described
below.  Information  required for  new  plants is
somewhat different than for  existing  facilities.  Most
phosphorus  removal  systems will  be retrofitted to
existing  systems due to  imposition of new permit
requirements. In either case, knowledge of  what
information  is  required to  make a  cost  effective
selection is critical  in being able  to  utilize  the
screening methodology presented  later.

2.2.7 New System Data Requirements

2.2.1.1 Effluent Discharge Requirements
The  first  step  taken in  evaluating  alternative
phosphorus removal  processes for a new facility is to
determine the  phosphorus  discharge limitations.
These limits should  be determined  in as  detailed  a
manner  as  possible to define  the  daily,  weekly,
monthly and possibly seasonal  phosphorus limits.
Determination of whether  an  existing facility  will be
phased  out due  to  regionalization  or  plant
consolidation should  also  be  ascertained  to  ensure
that the  time frame used in the cost analysis reflects
the expected plant lifetime.

Phosphorus limits may be set as  a  minimum percent
removal, as  a specific effluent concentration or  on  a
mass per day  basis. In addition  to the phosphorus
discharge limitations, the permit limits for BODs, TSS,
pH, NH4-N or total N must be known. The necessity
to remove  ammonia and/or  total-nitrogen from  the
effluent can have a significant impact on the selection
of the phosphorus removal process. The information
normally required is shown in  Table 2-1.

2.2.1.2 Wastewater Characteristics
Once effluent limitations have been determined, the
next  step is to develop the information on wastewater
characteristics  which may  affect  the  choice of
phosphorus  removal alternatives.  For a new  facility,

-------
Table 2-1.   Information Required for Discharge Limits

 Parameter	Weekly    Monthly    Seasonal

 Total P, mg/l

 Total P, kg/d

 Total P, % removal

 BOD5, mg/l

 TSS, mg/l

 NH4-N,  mg/l

 Total N, mg/l

 pH, units
Table 2-2.   Information Required for  Influent Wastewater
           Characteristics

  Parameter	Daily1     Weekly   Monthly

  Flow
   Average, m3/d
   Maximum, m3/d
   Peak/Average Ratio
  Total P, average, mg/l
  Soluble P, average, mg/l
  BOD5, average, mg/l
  SBOO, average, mg/l
  TSS, average, mg/l
  NH4-N, average, mg/l2
  Total N, average, mg/l2
  pH, units
  Temperature
  Alkalinity, average, mg/l
  TBOD:Total P ratio
  1 Seasonal column should be added for biological phosphorus
   removal facilities.
  2 Where effluent discharge permit limits Total N or NH4-N.
the  most  important  wastewater characteristics  are
listed  in Table 2-2.  In  addition, any  significant
contribution from individual  sources  should  be
characterized.  The  effect  of these  variables  on
alternative  phosphorus  removal processes  is
summarized in Section 2.4. Detailed explanations  are
provided in Chapters  3  and  4  for  the  specific
processes.

The  best  data on   anticipated  plant  flows  and
wastewater  characteristics are from  plant  influent
monitoring  data. If  data on  nutrients,  alkalinity,  etc.
are  not  available, it is recommended that data from
the literature be used for facilities of similiar size  and
service  characteristics. Actual characterization  data
from  the   wastewaters  to be treated  are much
preferred,  and  every effort should be expended to
collect representative information.  The importance of
adequate wastewater  characterization  cannot  be
over-emphasized. The cost of sampling  and analysis
required  for  proper wastewater  characterization  is
almost always offset by more efficient system design
and lower total costs for phosphorus removal.

Alkalinity and pH data are site specific and must be
determined for each facility. Where plant influent data
are not available, alkalinity can be  best obtained from
the water  supply sources serving  the contributing
wastewater generators.

2.2.1.3 Other Information Required
Other  information  that  may  have a significant
influence on the phosphorus removal alternatives are:

1.  Sludge disposal alternatives.
2.  Service  area  characteristics including  industrial
   contributions.
3.  Plant size and location;  available land.
4.  Facility design lifetime.
5.  Local availability and cost of chemicals.

Smaller plants in more rural settings generally offer a
wider  range  of  alternatives because of the reduced
constraints of sludge handling. Chemical alternatives
generally require  less  space  but  exhibit  higher
operation and  maintenance  costs. Biological
alternatives  require  more careful  analysis of total
treatment requirements including the  proper selection
of a basic BOD removal process.

Sludge  generation  can  be  a  significant  factor
influencing   the phosphorus  removal alternative
selected. Many communities are  limited in their
choice of  sludge disposal  options due to local or
state regulations, air quality requirements or biases on
the  part of local  decision  makers and/or  local
concerned citizens.  Because of  the importance of
sludge handling cost as a part of the total treatment
costs,  new  phosphorus removal  projects  must
consider sludge handling as an  intergal part  of  the
total system analysis.

The typical  planning  period  for new  wastewater
treatment facilities is 20 years. However, phosphorus
removal standards may be  established  for different
time frames. Chemical alternatives may be more cost
effective for shorter  term  design   periods,  while
biological alternatives with higher capital costs  may
be more appropriate for longer term projects.

Wastewater characteristics are determined  to a large
degree by the composition of the contributing  sewer
dischargers.   The  breakdown  of  the  system
wastewater contributors into  residential, commercial
and  industrial  discharges  can  be  made  from
community  records and/or planning  studies.  Where
significant industrial  contributors  are  identified,  the
impact of their wastes on the wastewater composition

-------
should be  reviewed for  its effect  on the  various
phosphorus  removal  alternatives  selected  for
consideration.

2.2.2 Existing System Data Requirements
Incorporation of phosphorus removal technology into
existing  facilities  presents  a  somewhat more
complicated initial analysis than that  required  for new
systems. Existing  systems may offer opportunities for
cost effective incorporation of some of the available
phosphorus removal technologies,  but at  the same
time may present severe constraints  to the use of
others. The more  important considerations for existing
facilities are:

1. Whether or  not the  existing facility  is meeting or
  can be easily  upgraded  to meet  the  non-
  phosphorus effluent limits.

2. Whether or  not the  existing hydraulic capacity is
  adequate for the proposed design flows.

3. Whether or not  the age and condition  of the
  existing  plant  justifies the  inclusion  of  a  new
  phosphorus removal technology.

4. Whether or  not the  existing facility  must be
  upgraded (to improve effluent quality) or expanded,
  or both.

5. Whether or  not the  basic  form  of  biological
  treatment, i.e.,  fixed film or  suspended growth, is
  compatible with phosphorus removal technologies
  capable of meeting the  required  effluent
  phosphorus limitations.

Once these basic questions have been addressed,
the analysis  may  proceed in  the same  manner
described earlier for new facilities.

1. Type,  capacity  and efficiency  of  existing  unit
  operations in service:

  a. Liquid stream
     hydraulic capacity
     biological  capacity
     aeration capacity
     modifications planned or underway

  b. Solids stream
     thickening and dewatering capacity
     stabilization capacity and efficiency
     ultimate disposal capacity
     compatibility  of sludge handling with applicable
       phosphorus removal technologies

2. Unit operation performance for specific parameters,
  including:

  Total P
  TSS
  BOD5
  Total N
  NH4-N

3. Unit operations known to be obsolete or to require
  replacement.

4. Unused or abandoned plant capacity that could be
  brought into service.

5. Discharge points of recycle  streams from  existing
  sludge handling systems; and loadings associated
  with these streams for the above parameters.

6. Sludge disposal options available  with existing
  sludge  handling system; loading capacities  and
  efficiency  of all  sludge  handling  processes.
  Capacity  analysis  of  solids  handling systems
  should note  the percent of time units are in service
  and the percent of existing  operating  capacity that
  is being used.

Personnel requirements  for  operation  of existing
equipment should be developed so  that  effects  of
adding new operations or expanding operating hours
of existing equipment can  be  used in evaluating the
additional costs  of  various  phosphorus  removal
alternatives.  The level of sophistication of operations
for  the applicable phosphorus removal  technologies
should be compared to  the existing  plant operation
requirements.  For  example,  if  existing plant
performance   is inadequate due to  deficient
operations,  the incorporation  of  a  biological
phosphorus  removal  technology requires substantial
upgrading of operator staffing and competence level.


2.3 Possible Phosphorus Removal
Alternatives

Detailed   descriptions  of  phosphorus removal
technologies and  the attendant sludge handling
alternatives are presented  in Chapters 3 through  5.
This  section   briefly summarizes  the  various
phosphorus removal technologies.  Simplified process
flow schematics,  along  with  expected  performance
ranges and the major advantages and disadvantages
of each process, are discussed below.

2.3.7 Chemical Addition Alternatives

2.3.1.1 Metal Salt Addition (Aluminum and Iron)
Metal  salts of aluminum and iron added to wastewater
react with phosphates to form insoluble aluminum  or
iron phosphate precipitates.  These  compounds
include aluminum sulfate (alum), sodium aluminate,
ferric  chloride, ferrous chloride, and ferrous  sulfate.
They  are generally  added  upstream of  either the
primary clarifier or the secondary clanfier.  In some
cases  metal salts  are added  to  both  primary  and
secondary processes. Figure  4-1  shows alternative

-------
metal salt addition  flow schematics. The  chemicals
may also  be added separately  to a  tertiary  clarifier.
The quantity of metal salt added is determined by the
concentration  of phosphorus species in the influent
wastewater  and  effluent   discharge  permit
requirements.

Systems with  metal salt addition can achieve  80-95
percent  total  phosphorus  removal.  For  effluent
limitations of  1.0 mg/l total phosphorus,  metal  salt
addition with  conventionally designed  clarifiers is
acceptable. Effluent  limitations  of  1.0  mg/l  total
phosphorus  can be met with metal  salt  addition  and
efficient clarification to assure  effluent TSS of  less
than 15 mg/l.  To consistently meet total phosphorus
discharge limitations  of 0.5  mg/l,  filtration  of
secondary effluent will most likely be necessary.

Determination  of the best  point or points of chemical
addition  is  best determined  by  full-scale  plant
testing. Jar  tests using the  different metal salts  can
provide sufficient information needed to conduct cost
estimating and evaluation of the relative  impact of
sludge production on  sludge  handling and  disposal
processes.  Pilot  or  full-scale  testing  is
recommended  to develop  detailed  design criteria
where stringent discharge  requirements  (e.g.,  0.5
mg/l total  phosphorus) are imposed.

Advantages and disadvantages of metal salt addition
for phosphorus removal are summarized in  Table 2-
3.

2.3.1.2 Lime Addition
Lime is used to remove phosphorus by addition either
to  the primary clarifier or to the effluent from the
secondary clarifier in a separate tertiary unit.

Phosphorus removal  with lime is basically  a water
softening  process and the quantity of lime  required to
remove the phosphorus is dependent on the alkalinity
of  the  wastewater  rather than on  the phosphorus
content.

Lime removal systems are  either  low-lime (single
stage) where  pH is kept  below 10.0 and  which can
achieve 1.0 mg/l effluent total phosphorus levels or  a
two-stage high-lime process that raises  the  pH to
 11.0-11.5 and is used to  achieve  very  low  (<1.0
mg/l) effluent  total  phosphorus concentrations.  High-
lime  treatment  uses more  lime and  also  requires
recarbonation to reduce  the  wastewater  pH  before
discharge  to a  downstream biological  unit or
discharge from the plant.  The effluent  phosphorus
 levels from  a two-stage  tertiary  lime  process  with
filtration can meet total phosphorus  effluent limits as
 low as 0.1.

 The  lime addition  process  produces a  substantial
 amount  of additional sludge, even greater than with
 metal salt addition.
Lime addition systems are usually pH controlled  and
entail  lime storage,  feed,  and  mixing units.  This
equipment often requires considerable maintenance.

Lime can be reused by calcining the lime sludge. This
step is only applicable at larger plants due to the high
capital  and operating  costs for the recalcining
process. Even with recalcining, about 20-30 percent
of make-up  lime is required.

Lime addition is seldom practiced in the United States
today due to  the high chemical usage,   problems
associated with handling lime, and the large volume
of sludge generated from lime  addition  systems.
Advantages  and disadvantages of lime addition  for
phosphorus  removal are summarized in Table 2-4.
2.3.2 Biological Phosphorus Removal Alternatives
Biological  phosphorus  removal  is  a  recently
developed technique of designing suspended growth
activated sludge  systems  to  remove  soluble
phosphorus  from wastewater.  Six  variations  on this
phenomenon are described  in  Chapter  3  of  this
manual. These alternatives are:

   Phostrip process
   Modified Bardenpho process
   A/0 process
   UCT (University of Capetown) process
   Sequencing Batch Reactor (SBR) process
   Operationally modified activated sludge processes

Figures 3-4, 3-5,  3-6   and  3-7 are  flow  diagrams
of  these  processes.  Detailed descriptions of the
various biological processes and  the theories  and
mechanisms of operation can be found in  Chapter 3.
Case histories of various facilities are also presented.

Phostrip is  the  only biological phosphorus  removal
process that incorporates an  anaerobic zone in  the
sludge  recycle system.  The Phostrip process takes a
sidestream  from the  return  activated sludge  and
subjects it  to  anaerobic  conditions  in  a  separate
anaerobic tank  before  returning  the sludge to  the
aeration basin. Maintenance of the  activated sludge in
the anaerobic state leads to phosphorus release, and
when the sludge is returned to the aeration basin or
reaerated,  the  activated  sludge biota take up  an
excess amount of phosphorus during  the growth
process. Lime  is used  to precipitate the phosphorus
released in  the  anaerobic tank.  Since only 20  to  30
percent of  the plant flow  passes  through  the
anaerobic tank,  the quantity of lime required is  much
less than in  a mainstream lime addition system, and
 less sludge  is produced.

 The  Modified   Bardenpho  process  and  the  UCT
 process are designed   to remove  both nitrogen and
 phosphorus.

-------
Table 2-3.   Advantages and Disadvantages of Metal Salt Addition for Phosphorus Removal
                         Advantages
                    Disadvantages
   1. Reliable, well documented phosphorus removal  technique.
      Most popular process used in the United States.

   2. Chemical costs can be reduced substantially if wasle pickle
      liquors (ferrous chloride or ferrous sulfate) are available and
      can be used.
   3.  Chemical usage requirement is basically dependent on total
      phosphorus concentration of wastewater and required effluent
      levels.

   4.  Controls required for phosphorus removal are fairly simple and
      straightforward.

   5.  Relatively easy and inexpensive to install at existing facilities

   6.  Sludge produced  can  be processed  in same manner as in
      non-phosphorus removal systems.

   7.  Primary clanfier metal addition can reduce organic  load to
      secondary unit by 25-35 percent.

   8.  Effluent phosphorus levels can be controlled by metal  salt
      dosages to maximum efficiency levels.
1.  Chemical costs higher than for biological phosphorus removal
   systems which require little or no metal salt addition

2.  Significantly more sludge produced than with  wastewater
   treatment process  without metal  addition; may  overload
   existing  sludge handling equipment; higher  sludge  treatment
   and disposal costs.

3.  Sludge produced generally does not dewater as well or as
   easily as conventional wastewater  treatment plant sludges
   where metal salts are not added.
Table 2-4.   Advantages and Disadvantages of Lime Addition for Phosphorus Removal

                         Advantages                                             Disadvantages
   1.  Simple process control, as lime dosage paced by pH control
      Lime dosage  required  does not  vary  with  phosphorus
      concentrations, only alkalinity of wastewater.

   2.  Very high phosphorus removals achievable with high lime
      process.

   3.  Many heavy  metals,  such  as chrome,  nickel, etc.,  are
      effectively removed.

   4.  Primary lime  addition reduces  organic  load  to biological
      treatment units.
1  High chemical costs for wastewater facility with  hard (high
   alkalinity) waters.


2.  More sludge produced than for any other phosphorus removal
   process.

3.  Equipment requirements and  maintenance costs for  lime
   storage, feeding, and handling equipment are extremely high.

4.  High capital and operating costs; not widely used in the United
   Stales today.

5.  Additional recarbonation step required for high lime process.
The A/O process is primarily designed for phosphorus
removal but  it can also be designed to accomplish
both phosphorus removal and nitrification.

Biological  phosphorus  removal has been achieved in
existing plug  flow activated sludge plants by modifying
the  aeration  practice at the head end of the aeration
tanks. This modification consists  of shutting off the air
or aerators  at the  head of  the  tank  to promote an
anoxic  or  anaerobic zone before the wastewater and
return sludge are aerated.

Phosphorus  removal  in  an  SBR   has  been
accomplished in limited  full-scale tests  by  modifying
the  sequencing  periods and  aeration  schedules  to
provide the needed anaerobic/aerobic mixing periods.

The sludge  quantities  produced  by  all the  biological
phosphorus  removal processes,  with the exception of
 Phostrip, are  not any greater  than  those  produced
 from  conventional   suspended  growth   systems.
 Processing  of the  biological phosphorus  sludges,
 however,  requires care  that the  sludge processing
 steps do not result in  phosphorus resolubilization, and
 return of soluble phosphorus to the system.

 The  degree  of phosphorus  removal  from  biological
 phosphorus removal  processes (except Phostrip) is
 dependent  on  the  influent  BOD:P  ratio  of  the
 wastewater. Within  the  proper  BOD:P  ranges,  the
 Modified Bardenpho,  A/0,  UCT  and  operationally
 modified activated  sludge  processes  can  achieve
 1.0-2.0  mg/l total phosphorus (TP)  level in the final
 effluent.  A  TBOD:TP  ratio  of   at  least  20:1
 (SBOD:soluble P  of 12:1 to 15:1)  is usually required
 to  meet these limitations.  Achievement  of  lower
 effluent  total  phosphorus  concentrations  normally
 requires efficient clarification  to achieve less than  20

-------
Table 2-5.    Advantages and Disadvantages of Biological Phosphorus Removal Processes
                       Advantages
                   Disadvantages
   1. Sludge quantities generated by biological phosphorus removal
     processes  are  comparable to sludge  production  from
     conventional activated sludge systems.

   2. Can  be implemented directly at existing plug flow activated
     sludge plants with little or no equipment changes or additions,
     provided that the plant has sufficient capacity.

   3. Can  utilize existing sludge  handling equipment  for plants
     retrofitted  with biological phosphorus  removal process  if
     phosphorus is not solubilized and returned to the plant during
     sludge handling.

   4. Little or no chemicals or chemical handling equipment required
     except for Phostnp process or for effluent polishing.

   5. Phosphorus  removal can be accomplished together with
     ammonia nitrogen or total nitrogen  removal  at virtually  no
     additional operating cost with some of the processes.

   6. For some of the processes,  better control of filamentous
     organisms in the activated sludge system is possible.
1.  In all but Phostrip, phosphorus  removal performance  is
   controlled by the BOD:TP ratio of the wastewater.


2.  Requires highly efficient secondary clanfier performance  to
   achieve 1 mg/l total phosphorus.


3.  Not easily retrofitted into fixed film biological systems.
4.  Potential for phosphorus release in sludge handling system.
   Recycle streams must be low in phosphorus content.

5.  Standby chemical feed equipment may be necessary in case
   of loss of biological phosphorus removal efficiency.
mg/l TSS concentrations or the use of tertiary filters.
Discussion  of  the effect of BOD:P ratios and other
factors  on  phosphorus  removal is  contained  in
Section 3.3.5.

In  all  these  systems,  pilot  testing  is  highly
recommended to determine what performance levels
can be  achieved for the specific wastewater to  be
treated.  Advantages and disadvantages of biological
phosphorus  removal systems are  summarized  in
Table 2-5.
2.4 Phosphorus Removal  System
Selection Strategy

The strategy that is described below for  selecting a
phosphorus  removal system is a selective screening
process whereby all phosphorus removal  alternatives
are initially considered, and then are screened against
various sets  of  criteria that impact  the choice of a
system. At  each  step  in  the  four step  process,
alternatives  are  evaluated  against  a corresponding
application  matrix (or set of  matrices) which  shows
the  applicability  of  the  process for various sets of
conditions.  Non-applicable technologies are rejected
at  each  step with  the  selected  alternative  being
chosen as a result  of the fourth  step of the process,
which is the final cost-effectiveness analysis.  A flow
diagram of the overall selection strategy is depicted in
Figure  2-1.

It  should  be emphasized  that this approach is
intended as a guide for  assisting the engineer  in the
overall  selection  process.  The approach  is  not
rigorous, since subjective information is  used  in the
selection/rejection  process  and   procedures  for
reiterating through the process are not provided.
 The four steps of the selective screening process are
 described below.

 Step 1:
 Categorize  the facility as to  whether it is an existing
 or  a new  plant,  and whether the  effluent nutrient
 discharge  limitations  are for  phosphorus only,  or for
 phosphorus  plus nitrogen.  In  general,  for  new
 facilities,  all  possible alternatives  should  initially be
 considered,  although  some  may  have  greater
 apparent  applicability   than others.  For  existing
 facilities, some alternatives can justifiably be removed
 from further consideration.

 For example, for  a trickling filter plant with sufficient
 design  capacity  that must meet  a new phosphorus
 limitation,  it is   unlikely  that  a  new  biological
 phosphorus removal system would be  competitive
 with  metal salt  addition to  the  primary  clarifier.
 However,  if the  same  plant  were  required  to meet
 both phosphorus  and  nitrogen  limitations,  a  new
 biological suspended growth  system designed for N
 and  P  removal  may be more  cost effective  than
 modifying  the  existing plant  to  achieve  nutrient
 removal.  The applicability criteria  matrix for  Step  1
 screening  is  shown  as  Table 2-6.

 Step 2:
 Apply P-removal  process capabilities and determine
 which processes can meet phosphorus limitations.

 For  those plants  with phosphorus  and nitrogen
 limitations,  the ability of  the process to meet nitrogen
 limitations  will also  be  considered.  In conducting  a
 study of plants having both phosphorus  and nitrogen
 effluent limitations,  an  additional  screening  step
 should  be  made  to  include  other nitrogen removal
 processes  that  can  be used independent of  the

-------
Figure 2-1.    Phosphorus Removal System Selection Strategy.
          All Alternatives
                                                                                         Selected
                                                                                         Alternatives
       CRITERIA:
Evaluate according to
criteria in Table 2-6
Evaluate according to
criteria in Tables 2-7
and 2-8
Evaluate according to
criteria in Tables 2-9
thru 2-11
Evaluate according to
cost-effectiveness
analysis
       STEP:                   1
                       Application criteria
                       New plant
                       Existing plant
                        Suspended growth
                        Fixed film
                       P removal only
                       P and N removal
                        Application criteria
                        Effluent P limitations
                        Effluent P and N
                          limitations
                        Application criteria
                        BOD:TP ratio
                        Sludge production
                        O&M
                         Application criteria
                         Total present worth
                         Site requirements
                         Reliability
                         Environmental impact
Table 2-6.    Application Criteria Matrix - New or Existing Facility; Type of Nutrient Removed
                                               P Removal Only
                                                                      P plus NH4 or N Removal
Process
(A) Phostnp
(B) Mod. Bardenpho
(C) A/O
(D) SBR
(E) UCT
(F) Mod. A.S.
(G) Metal Salt
(H) 1 -Stage Lime
(I) 2-Stage Lime
Y - Applicable
N - Not Applicable
Existing Susp.
New Facility Growth
Y
E
Y
Y
E
Y
Y
Y
Y
E
M
Y*
Y
E
Y
Y
E
Y
Y
Y
Y
Existing Fixed
Growth
N
N
N
N
N
N
Y
Y
Y
New Facility
Y
Y
Y
Y
Y
Y
Y
Y
Y
Existing Susp.
Growth
M
Y
M
Y
Y
M
M
M
M
Existing Fixed
Growth
Y*
N
Y"
N
N
Y*
M
Y"
Y*
- May be Applicable, but exceeds treatment requirements.
- May be Applicable, but N or NH4 removal step required.
- Applicable where existing fixed film unit can be used for nitrification.

-------
phosphorus  removal process,  i.e. consider alum  for
phosphorus  removal and breakpoint  chlorination, or a
separate nitrification tower to  meet  the  P  and  N
limitations.

In  addition,  effluent limitations such  as BOD5  and
suspended  solids  as  well as  other site  specific
requirements not specifically  listed  as "application
criteria" may lead to  rejection  or inclusion of some
P-removal  processes.

To  help select the processes  which can meet the
various  phosphorus,  or  phosphorus  and nitrogen
limitations,  Tables  2-7  and  2-8 are  used.  These
tables are matrices  showing the ability of the systems
to  meet various phosphorus  limits  as  well as being
able to  meet effluent nitrogen limits. These matrices
are intended to be used as  guidelines and are not
intended for rigid process selection.   Specific data on
the nitrogen removal/conversion characteristics of the
biological  phosphorus  removal processes  must  be
studied  carefully  before  determining  whether  a
specific process should be included or eliminated as
a possible alternative.

Step 3:
Step  3 consists  of  screening  the  alternative
processes  that have  been found  to be capable  of
meeting the effluent phosphorus or phosphorus and
nitrogen limitations with  the  applicability  criteria  in
Tables  2-9  through 2-11. The  objectives  of  this
screening are to eliminate those processes which are
not suitable for further   consideration. Where  a
process is shown to be marginal and other processes
are shown  to  be  capable of  meeting the effluent
limitations,  the marginal processes should  also be
carried  through to step 4.

The Application Criteria  Matrices  shown as Tables
2-9 through 2-11  have been developed  to  provide
a means of quickly determining the  factors which are
pertinent for  screening the different phosphorus
removal processes. As in  the previous tables, these
matrices  are  intended to  provide  a means  of
evaluating   the  impact of various factors  on the
different phosphorus removal  processes. In using the
matrices the user should read the applicable sections
of the manual which describe the processes in detail.
A brief description of the use of the  matrices follows.

Table  2-9,  Effect  of  Influent TBOD:TP  Ratio on
Process Applicability, is  based on  research  that
indicates plants with  a  TBOD:TP ratio less than 20
may  have  difficulty  achieving final  effluent total
phosphorus concentrations of  1.0-2.0 mg/l. Specific
sampling data on  the  variation  of TBOD:TP  ratio
and/or  pilot-plant studies  for  a specific facility  may
be necessary  to  define  the  capabilities  of  the
biological  phosphorus removal   process  under
consideration.
Table 2-10,  Sludge Production,  indicates the effect
on  sludge  production  of  the  different phosphorus
removal systems for  typical process applications.
Operation  and maintenance  requirements  for
increased  sludge  production  are  included  in  the
ratings for  the processes.  More  specific data  on
sludge production  for  the specific processes  are
presented in Chapter 5.

Table 2-11,  O & M Effects, shows the difference in
O & M requirements for the different processes. The
0 & M comparison does not include sludge handling
and disposal since this aspect is covered in Table 2-
10.

Step 4:
Step four consists of developing the capital, operation
and maintenance, and total present worth  costs for all
applicable alternatives.  Non-monetary factors  are
also considered at this point, including:

1. Site requirements.
2. Reliability.
3. Environmental Impacts.
4. Operator  skill  level  required  for successful
  operation.

The results of the comprehensive  cost effectiveness
analysis,  which  evaluates  costs   of  screened
alternatives  against  appropriate non-monetary
factors, results in  the selection of a  system which
meets project objectives at the lowest present  worth
cost.
                                                   10

-------
Table 2-7.    Application Criteria Matrix - Ability of Process to Meet Effluent Phosphorus Limitations
Process
(A) Phostrip
(B) Bardenpho
(C) A/O
(D) SBR
(E) UCT
(F) Mod. A.S.
(G) Metal Salt
(H) 1 -Stage Lime
(I) 2-Stage Lime

Alone
N
N
N
N
N
N
N
N
N
0.5 mg/l 1 .0 mg/l 2.0 mg/l
Effluent TP Effluent TP Effluent TP
w/M.S. w/M.S. w/M.S.
w/M.S. w/F & F Alone w/M.S. w/F & F Alone w/M.S. w/F & F
NNYYYYYYYYY
NNYMY'MYYYYY
NNYMY-MYYYYY
NNYMY'MYYYYY
NNYMY*MYYYYY
NNYMY*MY Y YYY
Y - Y" - Y - Y - Y -
NYYY'MYY Y YYY
MYYY'MYYY- Y-

  Ability of alternatives (B)-(F) to meet effluent limits alone based on TBOD:TP ratio being above 20.
  N - Can not meet effluent limits.
  M - Marginal for meeting effluent limits.
  Y - Will meet effluent limits.
  Y* - Will meet effluent limits with highly efficient clarification.
  M.S. -  Metal  salt  addition to secondary clanfier.
  F -  Filtration of secondary clanfier effluent.
  M.S. & F - Metal  salt addition to secondary clanfier and secondary clanfier effluent filtration
Table 2-8.
Application  Criteria Matrix - Ability of  Process
to Remove NH4 or TN
Process
(A) Phostrip
(B) Bardenpho
(C) A/O
(D) SBR
(E) UCT
(F) Mod A.S
(G) Metal Salt
(H) 1 -Stage Lime
(I) 2-Stage Lime
0.5 mg/l
Effluent TP
NH4 TN
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N N
N N
N N

1 .0 mg/l
Effluent TP
NH4 TN
Y N
Y Y
Y N
Y Y
Y Y
Y N
N N
N N
N N

2.0 mg/l
Effluent TP
NH4 TN
Y N
Y Y
Y
Y Y
Y Y
Y N
N N
N N
N N

  Y - Can remove NH4 or total N.
  N -  Need  separate process or modification for NH4  or  total  N
       removal.
  N/A - Not applicable for effluent P limitation  shown.
                                                                11

-------
Table 2-9.    Application Criteria Matrix - Effect of TBOD:TP Ratio < 20 on Process Applicability
Process
(A) Phostnp
(B) Mod. Bardenpho
(C) A/O
(D) SBR
(E) UCT
(F) Mod. A.S.
(G) Metal Salt
(H) 1 -Stage Lime
(I) 2-Stage Lime
0.5 mg/l
Effluent TP
Application
N/A
N/A
N/A
N/A
N/A
N/A
L
L
L
1 .0 mg/l
Effluent TP
Application
L
N
N
N
N
N
L
L
L
2.0 mg/l
Effluent TP
Application
L
M
M
M
M
M
L
L
L
  L -  No effect.
  M -  Marginal; may not meet effluent TP limitations without metal salt addition.
  N -  Cannot meet effluent phosphorus limits without metal salt addition.
  N/A - Not applicable for effluent TP limitation shown.
Table 2-10. Application Criteria
Process
(A) Phostnp
(B) Mod. Bardenpho
(C) A/O
(D) SBR
(E) UCT
(F) Mod. A.S.
(G) Metal Salt
(H) 1 -Stage Lime
(I) 2-Stage Lime
Matrix - Effect of Sludge
0.5 mg/l
Effluent TP
Application
M
L
L
L
L
L
H
H
H
Production on Process Applicability
1 .0 mg/l
Effluent TP
Application
M
L
L
L
L
L
M
H
H

2.0 mg/l
Effluent TP
Application
M
L
L
L
L
L
M
H
H
  L - Little or no increase in sludge production or handling (< 30%).
  M - Increased sludge production and/or handling (30 - 100%).
  H -  Substantial increase in sludge production and handling (>  100%).
                                                               12

-------
Table 2-11. Application
Process
(A) Phostrip
(B) Mod. Bardenpho
(C) A/O
(D) SBR
(E) UCT
(F) Mod. A.S.
(G) Metal Salt
(H) 1 -Stage Lime
(I) 2-Stage Lime
Criteria Matrix • Effect of O&M Requirements
0.5 mg/l
Effluent TP
Application
N/A
N/A
N/A
N/A
N/A
N/A
M
S
S
on Process Applicability1
1.0 mg/l
Effluent TP
Application
M
M
M
M
M
M
L
M
S

2.0 mg/l
Effluent TP
Application
M
L
L
L
L
M
L
M
S
L -  Little or no increase in O&M (0  - 10%).
M - Some increase  in O&M (10 - 30%).
S -  Substantial increase in O&M (>  30%).
N/A - Not applicable for effluent TP limitation shown.
1 O&M - For process control, monitoring and operations excluding sludge handling.
                                                          13

-------
                                            CHAPTERS
                         Phosphorus Removal by Biological Processes
3.1 Introduction and Theory

Conventional  secondary biological treatment systems
accomplish phosphorus removal by using phosphorus
for biomass synthesis  during BOD  removal.
Phosphorus  is   an  important   element  in
microorganisms for energy transfer and for such cell
components  as phospholipids,  nucleotides,  and
nucleic  acids. Attachment of  a  phosphate radical
bond  to adenosine triphosphate (ATP) results in the
storage of energy (7.4  Kcal/mole  P),  which is
available upon conversion of ATP back to adenosine
diphosphate (ADP).  Phosphorus is also contained in
nucleotides  such  as  nicotinamide  adenine
dinucleotide (NAD)  and flavin   adenine dinucleotide
(FAD) which  are used for hydrogen  transfer during
substrate  oxidation-reduction reactions.  Ribonucleic
acid (RNA) and deoxyribonucleic acid (DMA) are
composed  of a deoxyribose  sugar  structure with
attached amino acids  of adenine, cytosine,  guanine,
and thymine or uracil. The deoxyribose molecules are
attached by  phosphorus bonds.  Phosphorus may
account for 10-12 percent of the RNA or DNA mass.

A  typical  phosphorus  content  of  microbial  solids is
1.5-2 percent  based  on  dry  weight.  Wasting of
excess biological solids with  this phosphorus content
may result in a total  phosphorus removal of 10-30
percent, depending  on  the  BOD-to-phosphorus
ratio,  the  system  sludge  age,  sludge  handling
techniques, and sidestream return flows.

In  1955, Greenburg  et a/. (1) proposed that activated
sludge could take up phosphorus at a  level beyond its
normal  microbial growth  requirements.  In  1959,
Srinath (2)  reported  on   batch experiments  to
conclude that vigorous aeration of activated sludge
could cause the concentration of soluble phosphorus
in  mixed liquor to decrease rapidly to below 1  mg/l. In
1965, Levin and Shapiro (3) reported on enhanced
biological phosphorus removal using activated sludge
from the District of  Columbia activated sludge plant.
Over 80 percent phosphorus removal was observed
by vigorous aeration of the  sludge and without the
addition of  chemicals. They  termed  the  high
phosphorus  removal  "luxury  uptake"  by  the
microorganisms.  In  some  experiments,  a small
amount of 2-4 di-nitrophenol  was  added  that
inhibited  phosphorus uptake,  indicating the removal
was  of biological  origin. They also observed volutin
granules  in the bacterial cells, which  are reported in
the microbial  literature to contain polyphosphates.
Acidification  of the sludge resulted in the release of
phosphorus, which led to a proposed treatment flow
scheme of exposing return sludge to acidic conditions
and stripping of phosphorus. Shapiro et a/. (4)  later
observed high phosphorus uptake at the  Baltimore
sewage treatment plant and release in the  bottom of
the secondary clarifiers under conditions of zero or
low dissolved oxygen (DO). Theyt proposed that the
return sludge could  be  intentionally exposed to such
conditions prior to return to the aeration basin to strip
out phosphorus. This work led to the development of
the Phostrip  process (5,6).

High levels of phosphorus removal  were observed at
various full-scale  activated sludge  plants  in  the
United States, including the Rillings  Road plant in San
Antonio,  Texas  (7),  the Hyperion  plant in  Los
Angeles,  California (8), and the Back  River plant in
Baltimore, Maryland (9).  The three plants  reported
total  phosphorus removals of 85-95 percent, and the
phosphorus  content of  the waste sludge was  2-7.3
percent on a dry weight basis. All of the plants were
of the plug flow configuration using diffused aeration,
and  the  following  operating characteristics  were
judged important  in all or some  of  the  plants  to
maximize phosphorus removal:

1. Require a DO concentration of 2.0  mg/l or greater
   from the middle to end of  the plug  flow aeration
   basins.

2. Prevent the recycle  of phosphorus  back to  the
   activated  sludge system  via sludge  handling
   streams.

3. Maintain  aerobic conditions  in the secondary
   clarifiers to prevent the  release of phosphorus into
   the effluent.

Both Vacker  (7) and Milbury  (9)  noted phosphorus
release by the mixed liquor and an increase  in soluble
phosphorus  concentration near  the  inlet  of the
activated  sludge tanks at the Rillings Road  and  Back
River  plants,  respectively. During the  late  1960s  to
                                                 15

-------
early  1970s there were varying opinions  as  to
whether the excess phosphorus removal observed at
these plants was due  to chemical precipitation. In an
attempt  to  provide a  rational  chemical  removal
explanation, one hypothesis was that the high  pH, as
a result  of  high aeration rates and  carbon dioxide
stripping  at the  end  of  the  plug  flow basins,
encouraged the formation of a calcium hydroxyapatite
precipitate (10).

In addition  to the development  of  the  Phostrip
biological  phosphorus removal process  in the early
1970s in  the  United  States, biological  phosphorus
removal was observed during the development of the
Bardenpho four-stage  biological  nitrification-
denitrification system  by Barnard (11).  The system
consists  of  sequential anoxic-aerobic-anoxic-
aerobic stages with an  internal  mixed liquor recycle
from the first aerobic  stage to the first anoxic stage.
During a  period of high  phosphorus removal  in a
100-m3/d (18-gpm) pilot-plant  operation, Barnard
observed a  soluble phosphorus concentration  of 0.3
mg/l in the  final aerobic basin.  He recognized that
phosphorus was  being  released  in the designated
second  "anoxic" basin,  which  was  actually
experiencing anaerobic  conditions (absence of  both
nitrate nitrogen and DO) and that it was being taken
up in the final aerobic  stage. This led him to conclude
that  biological  phosphorus removal  was possible in
activated  sludge systems provided  that an aerobic
stage was preceded  by an anaerobic  stage  where
phosphorus release occurred. It was  also noted that
when  a high   level of  phosphorus  removal  was
reported in plug flow U.S. plants, phosphorus release
occurred near  the  inlet of the aeration basin followed
by phosphorus uptake along the length  of the basin
where the DO  concentration increased.

In a later paper, Barnard (12) proposed  the use of a
separate anaerobic basin ahead  of  the Bardenpho
nitrogen  removal system or ahead of  aerobic  basins
when  nitrogen removal was  not necessary.  The
former was called the Modified  Bardenpho process
and the  latter  the  Phoredox process.  Phoredox was
derived from  "phosphorus"  and  "redox potential,"
which is at a lower level in the anaerobic phosphorus
release zone.  Figure  3-1 shows  phophorus release
and  uptake  characteristics  of  such biological
phosphorus removal systems that employ sequential
anaerobic-aerobic  contacting.

Following  Barnard's  pilot-plant  work,  full-scale
plants were modified  at Johannesburg, South Africa,
to investigate  the  feasibility of biological phosphorus
removal. At the Alexander plant, surface aerators near
the inlet of an activated sludge basin were turned off
to create an anaerobic zone (13). An overall nitrogen
removal of 85 percent  and a total  phosphorus
removal  of  46  percent were  reported.  At  the
Olifantsvlei  plant,  various combinations of  surface
aerators were  turned  off in  the four-stage  system
Figure 3-1.   Biological phosphorus and BOD removal due to
           anaerobic-aerobic  contacting.

      Return Sludge
                        Time

and an effluent soluble phosphorus  concentration of
0.9 mg/l  was reported  (14). Based  on this work,  a
modified  Bardenpho system was  designed for  a
I50,000-m3/d   (39-mgd)  facility   at  the
Johannesburg  Goudkuppies wastewater plant  that
became operational in 1978 (15). In the late 1970s, a
modified Bardenpho plant was started up at Palmetto,
Florida (16), and a portion of the Largo, Florida facility
was converted to  the  A/O  process  (17),   an
anaerobic-aerobic  biological  phosphorus  removal
system to be discussed later.

3.1.1 Biological Phosphorus Removal Mechanism
The generally  accepted theory   for  biological
phophorus  removal  is  that  anaerobic-aerobic
contacting results in a competitive substrate utilization
and  selection  of  phophorus-storing   microorganisms
(18,19). An understanding of the steps involved in the
biological phosphorus removal mechanism provides a
useful  insight  into the factors  that  can affect  the
performance  of  biological  phosphorus  removal
systems.  The  following  observations  by various
investigators are presented as a background to the
proposed mechanism.

Funs and Chen (20)  examined activated sludge  from
the Baltimore Back River and the Seneca Falls,  New
York treatment  plants when the plants were exibiting
high levels of  phosphorus removal.  They concluded
that the organism  asssociated  with  phosphorus
removal belonged to  the Acinetobacter genus. These
bacteria are short,  plump, gram-negative rods with a
size of 1-1.5 pm. They appear in pairs, short chains,
or clusters. They also subjected  a  pure  culture to
                                                  16

-------
batch anaerobic-aerobic  cycles  and  noted excess
phosphorus  removal when acetate was  fed  to  the
system. They postulated  that the anaerobic phase in
excess  phosphorus removal systems  was  important
for  the  production of  simple  carbohydrates such as
ethanol,  acetate,  and succinate,  which  serve as
carbon  sources  for Acinetobacter.  Contrary to  later
findings, they felt that  the simple carbohydrates were
assimilated by the Acinetobacter in  the aerobic phase
of the  cycle.  Fuhs and  Chen  also  found  that a
significant  phosphorus  release   rate  could  be
promoted by the addition  of carbon  dioxide during the
anaerobic phase, which  also lowered the  pH.  This
was also observed by Deinema (21).

Other investigators also reported observing significant
levels  of  Acinetobacter  in  biological  excess
phosphorus  removal systems (22-24).  Letter  (24)
also found  significant  levels of  Aeromonas  and
Pseudomonas which  are capable  of  polyphosphate
accumulation.  Hascoet et al. (25) also  noted  the
presence  of  Bacillus  cereus  in addition to
Acinetobacter  and Suresh et al.  (26) found  small
amounts  of  Pseudomonas vesiculcris,  besides
Acinetobacter,  in  samples  cultured  from  an
anaerobic-aerobic  phosphorus removing  pilot plant.
Brodich (27) noted that the removal of phosphorus in
a system containing Acinetobacter became significant
only  after  the  development  of  an Aeromonas
population.  He  postulated  that  the Aeromonas
bacteria  served  the important function of producing
fermentation products  in the anaerobic phase for the
Acinetobacter.  Letter and Murphy  (28)  noted an
increase of Pseudomonas  and  Aeromonas  in
biological phosphorus removal  systems.  They  also
found that these species of bacteria and a species of
Acinetobacter accomplished denitrification in  anoxic
zones of biological nitrogen removal systems. Osborn
and Nicholls (15) reported rapid biological phosphorus
uptake during nitrate reduction in  the absence of DO,
indicating that phosphorus uptake  may be  occurring
with denitrifying  bacteria. Hascoet (25) also reported
phosphorus release in anoxic zones by Acinetobacter
provided that there was  a  relatively  high level  of
substrate availability.

Various investigators have observed a decrease in
soluble  substrate and  an increase  in orthophosphate
concentrations in the  anaerobic  zone of anaerobic-
aerobic  sequenced biological phosphorus removal
systems. Hong  (29) showed a soluble BODs (SBOD)
concentration decrease from  45  to 15 mg/l and an
orthophosphorus concentration increase from 6 to 24
mg/l in the anaerobic zone. Ekama  et al. (30)  related
phosphorus  release in the  anaerobic zone  to  the
presence of  a  soluble,  readily biodegradable
substrate. The  concentration  of  a soluble  readily
biodegradable substrate can  be determined from the
increase in the  oxygen uptake rate  measurements of
a batch activated sludge  sample after the addition of
influent.  Rensink's (31)  work on Acinetobacter  led
him to investigate the change in acetate and soluble
phosphorus concentrations in the anaerobic phase.

Figure  3-2  shows  the  decrease  in  acetate
concentration  and  increase  in  orthophosphate
concentration as a  function of the anaerobic time.
The  molar ratio of acetate utilization to phosphorus
release was 1.3.
Figure 3-2.   Acetate assimilation and phosphorus release
           vs. anaerobic time (31).
                           Orthophosphorus   *
                 20           40
                  Anaerobic Time, min.
60
Fukase  (32), using fill-and-draw reactors, observed
an  acetate  utilization  to  phosphorus  release  molar
ratio of  1.0.  Arvin (33) reported 0.7, Rabinowitz (34)
0.6,  and Wentzel (35) 1.0 from batch studies using
sludge from excess biological  phosphorus removal
systems.  Rabinowitz (34)  also  found that the
phosphorus release magnitude and rate were affected
by the type  of substrate.  The amount  of phosphorus
release  for each substrate  in decreasing order was
sodium  acetate, propionic acid,  glucose, acetic acid,
and  butyric  acid. On the other hand,  Jones  (36)
observed a  greater phosphorus release  in declining
order of butyric acid,  ethanol, acetic acid, methanol,
and sodium acetate.

Release and  uptake  of metal  ions  have  been
observed during phosphorus release in  biological
phosphorus removal systems. A summary of the data
has been presented by Comeau (37) and is shown in
Table 3-1.

The understanding of the  biological phosphorus
removal  mechanism was  significantly advanced with
the observations on  storage of carbohydrate products
within biological cells in  the anaerobic zone and
phosphorus-containing  volutin granules  in the
aerobic  zone.  The   most  commonly  reported
                                                 17

-------
Table 3-1.   Molar Ratios  of  Ions Co-Transported  with
           Phosphorus.

           Ref. 38   Ref.  39   Ref. 37  Ref. 37   Ref. 37
Mg + 2/p
K + /P
Ca + 2/P
Na+/P
charges/P
0.26
0.27
0.00
-
0.79
0.32
0.23
-
-
0.87
0.24
0.34
0.06
0.00
0.94
0.28
0.20
0.09
0.00
0.94
0.27
0.23
0.12
0.00
1.01
anaerobic intracellular storage  product  has  been
polyhydroxybutyrate (PHB).

PHB  has  been found  in  biologically-removed
phosphorus sludges  by Timmerman  (40)  and  in
Acinetobacter by Nicholls and Osborn (41).  Lawson
and Tonhazy (23) isolated Acinetobacter and  showed
that  these  bacteria could  accumulate  PHB  and
polyphosphates.  Deinema (42) also observed  PHB in
a  strain of phosphorus-removing Acinetobacter.
Senior (43) hypothesized  that certain  bacteria will
accumulate  PHB during temporary  deprivation  of
oxygen. Buchan  (22) reported  that  PHB increased in
bacterial  cells  while polyphosphate  granules
decreased  in size or disappeared  in the  anaerobic
zone of biological phosphorus removal systems.

PHB  synthesis  and  degradation are described by
Gaudy  (44).  PHB is  formed  in the  cell  under
anaerobic conditions from acetoacetate  serving as a
hydrogen  acceptor. Acetate  entering the bacterial
cells under anaerobic conditions can be converted to
acetyl-COA provided energy  is  available,  and
acetyl-COA can  be converted to acetoacetate  since
the cell has a limited  supply  of the enzyme  COA.
During  oxidative conditions,  PHB is  oxidized  to
acetyl-COA, which enters  the  Krebs  cycle.  PHB
oxidation  does  not occur  until  nearly  all  of the
endogenous carbon is used  up according to Gaudy.

As described  previously, Levin  (3) reported finding
volutin granules  in sludge samples during biological
phosphorus removal.  In an extensive evaluation  of
biological phosphorus removal, Harold (45) stated that
phosphorus was likely stored  as polyphosphates
within volutin granules. Volutin granules contain  lipids,
protein, RNA,  and  magnesium  in  addition  to
polyphosphates.  The granules are  visible  under the
light microscope and can also be identified by  staining
with either toludine dye, which results in a  reddish-
purple color, or with a methylene blue  technique,
which results in  a dark purple color. A  high  electron
beam  directed  on the  microorganisms  will  also
volatilize the polyphosphate contained in  the volutin
granules leaving  holes in the cells.

Sell  (46) photographed   large  masses  of
polyphosphate   granules contained  in phosphorus
removing sludge during a cold temperature laboratory
investigation  of biological  phosphorus  removal.
Buchan  (22) analyzed the biological species obtained
from aerobic zones of various South African activated
sludge plants  accomplishing biological phosphorus
removal.  His  analysis showed  that  the intracellular
polyphosphate granules  contained an  excess of 25
percent  phosphorus. In the anaerobic zone, the large
polyphosphate granules  had dispersed into  smaller
granules and  some cells had released virtually all of
their accumulated phosphorus.

The proposed biological  phosphorus  removal
mechanism (18,19) is  summarized in Figure  3-3.
Acetate  and  other fermentation  products  are
produced  from fermentation reactions  by  normally-
occurring facultative organisms in the anaerobic zone.
A  generally   accepted  concept  is  that  these
fermentation products are derived from the soluble
portion of the influent  BOD and  that  there  is not
sufficient time for the hydrolysis and  conversion of
the  influent  paniculate  BOD.  The  fermentation
products are  preferred and  readily  assimilated and
stored  by the microorganisms  capable of  excess
biological phosphorus removal.  This  assimilation and
storage  is aided by the  energy made  available from
the hydrolysis of  the stored polyphosphates  during
the  anaerobic  period.  The stored  polyphosphate
provides energy for active transport of substrate and
for  formation  of acetoacetate, which is converted to
PHB.  The  fact  that  phosphorus-removing
microorganisms  can  assimilate  the  fermentation
products in  the  anaerobic  phase means  that  they
have  a  competitive advantage  compared  to  other
normally-occurring microorganisms   in  activated
sludge systems. Thus, the anaerobic phase results in
a  population  selection  and  development of
phosphorus-storing  microorganisms.  Rensink  (31)
has pointed out that Acinetobacter are relatively slow
growing  bacteria and  that they  prefer  simple
carbohydrate  substrates. Thus,  without the  anaerobic
phase, they may not be present at  significant levels in
conventional activated sludge systems.

During  the  aerobic  phase, the  stored  substrate
products are depleted (22) and soluble phosphorus is
taken  up,  with  excess  amounts  stored  as
polyphosphates. An  increase in  the  population of
phosphorus-storing bacteria  is also expected as a
result of substrate utilization. The  above mechanism
indicates  that the level of biological  phosphorus
removal achieved  is directly related to  the amount of
substrate  that can be fermented  by  normally-
occurring microorganisms in the anaerobic phase and
subsequently assimilated  and stored as fermentation
products by  phosphorus-removing microorganisms,
also in the anaerobic phase.


3.2 Applications
The  recent  developments  leading  to  a  better
understanding  of  the  conditions causing  excess
                                                 18

-------
Figure 3-3.   Scxhematic of  biological phosphorus removal
           mechanism.

            Substrate
                   Facultative
                   Bacteria
                                   Anaerobic
            Acetate plus
            Fermentation
            Products
                              Phosphorus-
                              Removing
                              Bacteria
   CO2 + H2O
biological phosphorus removal help to  explain the
earlier observations  on excess phosphorus removal
reported for  full-scale facilities. It  is  apparent  now
that sufficient  BOD was present and oxygen  was
limiting  so that fermentation conditions  likely occurred
at the front end of the relatively long, narrow aeration
basins  of these  plants.  Since these  observations,
three major proprietary biological phosphorus removal
processes  that employ  more definitive  anaerobic
fermentation zones have been commercialized. These
processes are, in order of development,  the Phostrip
process, the  modified Bardenpho process, and the
A/O process. These processes as well as other non-
proprietary systems  will be described in  this section.
Other options  used are the UCT process, sequencing
batch reactors (SBRs),  and  operationally modified
activated sludge systems.

3.2.7 Process Descriptions
The three commercial biological phosphorus removal
processes  are shown in Figure 3-4.  The Phostrip
process was first proposed by Levin in 1965 (3). Pilot
plant data were  collected  at a  number  of municipal
plants  from  1970  to  1973 and demonstrated high
levels of phosphorus  removal.  In 1973, the Seneca
Falls, New York activated sludge plant was converted
to the  Phostrip process  and  evaluated  (6). The
process  combines both  biological and chemical
phosphorus removal and has been referred to as a
sidestream process since  a  portion  of the  return
activated sludge  flow is  diverted for  phosphorus
stripping  and subsequent  precipitation with lime.  An
advantage of the Phostrip  process  is that an effluent
concentration of less  than 1 mg/l  total  phosphorus
can be achieved with less dependence  on the BOD
strength  of  the  influent  wastewater.  A  large
percentage of the phosphorus removed  is tied up as
a  lime  sludge,  which  causes  less  concern than
handling  a phosphorus-rich waste  biological  sludge.
Compared to chemical addition to an activated  sludge
aeration  basin  for phosphorus  precipitation,  the
Phostrip process  may require a lower  chemical
dosage and cost, since the lime dosage is a function
of the  alkalinity and not the amount of phosphorus to
be removed,  as is the case for alum and iron salts.
This potential advantage is a function of wastewater
alkalinity, phosphorus  concentration,  and relative
chemical costs.  The process may require more
operator  skill and control relative to the  stripper tank
operation and lime feeding. In addition, as discussed
in Chapter 4, significant problems have been reported
for lime storage and handling systems.

The sidestream  flow diverted to the  anaerobic
phosphorus  stripper tank  is normally 10-30 percent
of the  influent flow. The stripper tank also functions
as  a gravity sludge  thickener.  The  average solids
detention time (SDT)  in the stripper tank can be 5-
20 hours, with 8-12 hours being typical  (47,48). The
SDT equals the mass of solids  in the sludge blanket
divided by the mass of solids removed per day in  the
tank underflow. Soluble phosphorus is released in  the
anaerobic  stripper tank. It  is not  known  if  the
phosphorus  release  is due   to  the  exact  same
mechanism  as described for  the   anaerobic-aerobic
activated sludge contacting  sequence.  Fermentation
products for  the biological phosphorus-removing
organisms  may  be derived  from the metabolism of
hydrolyzed solids  and from organics released from
lysed bacteria in the stripper.  The released soluble
phosphorus  may  be from biological  phosphorus-
removing microorganisms and  from  lysed  bacteria.
Soluble phosphorus is transferred  to the supernatant
either  by recycling the stripper  underflow  to  the
stripper  influent or by passing  an  elutriation  stream
through  the stripper.  The elutriation stream may  be
primary  effluent,  secondary effluent,  or supernatant
from the lime precipitation reactor.

The overflow from the  stripper tank  is continuously
fed to  the  chemical  treatment tank where  lime is
added  for phosphorus removal.  Two approaches have
                                                  19

-------
Figure 3-4.  Commercial biological phosphorus removal processes.
     Influent
                                       Aeration
                                        Basin
                                                                                               Effluent
                                          _Direct_Retu_rn_ Sludge	|_	> waste AS

                                                                                     Sidestream Feed Sludge
                            Phosphorus Stripped Return Sludge
          Reactor-clarifier for
          chemical precipitation
                                    Phosphorus Rich Supernatant
                                Supernatant Return
         Anaerobic \      |
         Phosphorus H-	
          Stripper
Elutnant:
Stripped Sludge Recycle
Primary Effluent
Secondary Effluent
Supernatant Return
                          Reactor-Clarifier for
                          Chemical Precipitation
                                                                      Waste Chemical Sludge
                                               Phostrip Process

Influent f "


Anoxic
t
Aerobic
t

Anoxic
Aerobic
Internal Recycle
                                          _ Return jSludge


                                           Modified Bardenpho Process
                                                                                                Effluent
                                        Waste AS

Influent '


\ '




i
i
Anaerobic
Stages
i







i
i
Oxic Stages
(Aerobic)




^


                                            Return Sludge


                                                 A/O Process
                                                                                                Effluent
                                        Waste AS
been proposed for the precipitation  and  removal of
the chemical sludge. The first, as shown in Figure 3-
4, is to  use a  separate  reactor-clarifier  unit for
treatment of  the stripper  overflow. The second  is to
add the lime to the overflow but to settle the chemical
precipitate  in the  primary  clarifier. The separate
treatment is  the more  common   approach.  The
underflow solids from the  stripper tank are returned to
the  aeration tank  where  biological  uptake  of
phosphorus  occurs.  Control of the  sidestream  feed
rate to  the  stripper  tank  affects  the distribution
between  phosphorus  removal  by   chemical
precipitation or in the waste biological sludge.

A  summary of typical  recommended  design criteria
for the  Phostrip,  Modified  Bardenpho,  and  A/O
processes  is  shown  in  Table  3-2.  A  significant
design  feature  for  the  three  processes  is  the
operating organic loading. The Phostrip process is not
confined to a  narrow range  of loadings as  are the
other two processes and has been recommended for
a wide  range of  activated sludge  operations. This  is
                                                     20

-------
Table 3-2.   Typical Operating Conditions for Biological Phosphorus Removal Processes (22,44,49,50,).
Phostrip
Parameter Value
AS System
F/M, kg TBOD/ --1
kg MLVSS/d
SRT, days2 --1
MLSS, mg/l 600-5,000
HRT.hr3 1-10






Modified
Parameter

F/M, kg TBOD/
kg MLVSS/d
SRT, days2
MLSS, mg/l
HRT, hr3
Anaerobic
Anoxic 1
Nitrification
(Aerobic 1 )
Anoxic 2
Aerobic 2
Bardenpho
Value

0.1-0.2

10-30
2,000-4,000

1-2
2-4
4-12

2-4
0.5-1.0
A/O
Parameter

F/M, kg TBOD/
kg MLVSS/d
SRT, days2
MLSS, mg/l
HRT, hr3
Anaerobic
Aerobic





Value

0.2-0.7

2-6
2,000-4,000

0.5-1.5
1-3




A/O plus
Parameter

F/M, kg TBOD/
kg MLVSS/d
SRT, days2
MLSS, mg/l
HRT, hr3
Anaerobic
Anoxic
Nitrification



Nitrification
Value

0.15-0.25

4-8
3,000-5,000

0.5-1.5
0.5-1.0
3.5-6.0



Phostrip Stripper
Feed,
% of inf. flow
SDT, hr
Sidewater
Depth, m
Elutriation Flow,
% of stripper
feed flow
Underflow,
% of inf. flow
P Release,
g P/g VSS
Reactor-Clarifier
Overflow Rate,
m3/m2/d
PH
Lime Dosage,
mg/l

20-30 Return Sludge, 100 Return Sludge, 25-40 Return Sludge, 20-50
% of inf. flow % of inf. flow % of inf. flow
5-20 Int. Recycle, 400 Int. Recycle, 100-300
% of inf. flow % of inf. flow
6.1
50-100
10-20
0.005-0.02

48
9-9.5
100-300
1 Based on activated sludge system design.
2 Average mass of solids in the system divided by average mass of solids wasted daily.
3 Hydraulic retention time, volume divided by influent flow rate.
due  to the fact that Phostrip performance is related
more to the stripper operation and chemical treatment
step. The  A/O  process is  generally designed  as a
high-rate  activated  sludge  system,  while  the
Modified Bardenpho  process is generally designed at
relatively low  overall  loading  rates due  to  the
detention   time  required  for  nitrification  and
denitrification.

The  Modified Bardenpho process, marketed by  the
Eimco Process Equipment  Company of Salt  Lake
City,  Utah,  is  both  a  nitrogen  and  a  phosphorus
removal  system.  As  Figure 3-4  illustrates,  the
influent  and  return  sludge  are contacted in  an
anaerobic tank to promote fermentation reactions and
phosphorus release prior to passing the  mixed liquor
through  the four-stage  Bardenpho  system.  The
original  development of the  four-stage  Bardenpho
process was described by  Barnard (50) to provide
more than 90 percent nitrogen removal without using
an  exogenous  carbon  source.  In the  first  anoxic
stage,  nitrate  nitrogen contained  in the  internal
recycle  from the  nitrification stage  is  reduced to
nitrogen gas (denitrification)  by  metabolizing influent
BOD using  nitrate oxygen instead of  DO. About 70
percent of the nitrate nitrogen produced in the system
is removed in the first anoxic stage. In  the nitrification
(first  aerobic)  stage,  BOD  removal,  ammonium
nitrogen oxidation,  and phosphorus uptake occurs.
The second anoxic stage provides  sufficient detention
time for  additional denitrification  by mixed  liquor
endogenous respiration, again  using  nitrate oxygen
instead of  DO.  The final aerobic stage  provides a
short period  of  mixed  liquor aeration  prior to
clarification  to  minimize  anaerobic  conditions  and
phosphorus  release in the  secondary clarifier.
                                                   21

-------
The  resultant  Modified  Bardenpho design  solids
retention time (SRT), based on the solids inventory in
all the aerobic  and anoxic  stages, is typically  10-20
days depending on the wastewater  temperature and
influent nitrogen concentration. In some designs, the
tank  volumes  have  been increased  above  the
nitrogen removal requirements to provide an extended
SRT  of 20-30  days for  the  purpose  of  sludge
stabilization. In  this way, further sludge  digestion is
not included in the facility design. As will be described
in Section  3.3,  this design approach results in less
sludge production and phosphorus removal per unit of
influent BOD removed.

The A/O process shown in  Figure 3-4 is marketed in
the United States by Air Products and Chemicals, Inc.
(17) and is similar to the Phoredox concept described
by  Barnard (12), except  that  the  anaerobic and
aerobic stages  are divided into a number of  equal
size  complete  mix compartments.  Typically,  three
compartments  have been  used  for the  anaerobic
stage and four for the  aerobic stage. The key features
of the A/O process are its relatively short design SRT
and high design organic  loading rates. Compared to
the Modified  Bardenpho  process,  this results in
greater sludge  production and  more  phosphorus
removal  per unit  of  BOD  removed in the  system.
However,  the  use  of  further  sludge  stabilization
methods, such  as anaerobic  or aerobic  digestion,
must  consider  the amount of  phosphorus released
during stabilization and the effect of recycle  streams
from the stabilization units on facility performance.

As shown in Table  3-2, the A/O  process can also be
used  where nitrification  and/or denitnfication  are
required. The modified flow scheme incorporates an
anoxic stage for denitrification between the anaerobic
and aerobic stages and  is called the A2/0 process.
The anoxic stage  is  also  divided into three  equal-
size,  complete  mix compartments. Mixed  liquor is
recycled from the end of the nitrification stage to feed
nitrate  nitrogen into  the  anoxic  stage  for
denitrification.  Internal  recycle  flows of  100-300
percent have been  used. Nitrate nitrogen removals of
40-70 percent can  be accomplished this way.

The use of SBR systems for secondary treatment has
gained increased popularity  in the United  States
during the late  1970s and early 1980s. An evaluation
of SBR treatment  capabilities, design  aspects,  full-
scale  installations,  and  advantages  has  been
documented  for  conventional activated  sludge
treatment  applications   (51).  Though  not a new
treatment  concept, with reported operations  dating
back  to the early 1900s, the recent surge of interest
has  been  related  to new and improved hardware
devices and to the successful  EPA-funded,  full-
scale, 20-month demonstration  and evaluation of a
1,330-m3/d (0.35-mgd)  facility at Culver, Indiana
(52).   Unique hardware for the system consists of
motorized  or  pneumatically-actuated  valves,  level
sensors,  automatic  timers,  microprocessor
controllers,  and  effluent withdrawal decanters.  The
SBR treatment concept  and  operational  flexibility
makes  it  an obvious candidate for  employing
anaerobic-aerobic  contacting   for  biological
phosphorus removal. Biological phosphorus  removal
was  demonstrated in the full-scale Culver, Indiana
facility during  June and July 1984 (53).

A  schematic  of  an  SBR  operation  for  biological
phosphorus removal is  shown in  Figure  3-5.  The
SBR  system  is  a  fill-and-draw activated sludge
system. A  single tank  provides for activated sludge
aeration, settling, effluent  withdrawal,  and sludge
recycle.  Biological  phosphorus  removal  was
accomplished in two SBR basins at the Culver facility
that were operating  at substantially different average
food-to-microorganism (F/M) loadings  of  0.16 and
0.42  kg  total  BODs  (TBOD)/kg  MLVSS/d,
respectively. The  operation steps consist first of a fill
period where  flow is diverted to one of the SBR tanks
while the other tank(s) operates in the reaction, settle,
effluent  withdrawal, or idle operation sequences.  After
the fill period, the reactor contents  are mixed but not
aerated  to provide the anaerobic fermentation period
for phosphorus  release  and  uptake of  soluble
fermentation products. The next step  is the react or
aeration  period followed by  a  selected  settling  time
when both aeration  and mixing are  stopped.  The
effluent  is  then  withdrawn and, depending on the
influent  flow  rate, a variable  length  idle  time  may
occur.  The  operating times  for this  biological
phosphorus removal sequence in the  two  differently-
loaded SBR basins  at Culver,  Indiana, are shown in
Table 3-3  (53).

Figure  3-6  shows  a  further  modification of the
Modified Bardenpho  process.  This  modification was
developed  at the University of  Capetown in South
Africa (30)  and has been  termed the UCT  process.
As shown,  the return activated sludge is directed to
the anoxic stage instead of the anaerobic stage  as in
the Modified  Bardenpho process. The basis for this
development  was  previous work with  biological
phosphorus removal systems  that indicated   initial
phosphorus removal efficiency could  be  negatively
affected by nitrate  nitrogen entering  the anaerobic
stage (16,54,55). Nitrate will  serve as an  electron
acceptor  during  the biological oxidation  of  BOD
entering  the anaerobic  stage.  This  results  in
competition for  the  soluble, readily  biodegradable
BOD  that  would  normally  be  converted  to
fermentation  products  for  use  by  the  biological
phosphorus-removing  bacteria  in the anaerobic  zone
in the absence of nitrate nitrogen. The relative ratio
between the  nitrate  nitrogen in the  sludge recycled to
the anaerobic stage in a Modified  Bardenpho or A/O
process and  the available, readily degradable soluble
BOD in the  influent  to that zone will determine if
sufficient  BOD  will  remain  after  denitrification
reactions occur  to produce a  necessary  level of
                                                  22

-------
Figure 3-5.   Biological phosphorus removal using a Sequencing Batch Reactor.


               	Time	
               i
               Fill
                           Anaerobic Mix
                                               Aerate
                                                               Settle
                                                                              Withdraw
Table 3-3.   SBR  Operating  Sequence -  Biological
           Phosphorus Removal.

 Period                    Low Loaded    High Loaded

Fill and Anaerobic Mix
Aerate
Settle
Withdraw
Idle
hr
1.8
1.0
1.0
0.4
0.6
hr
3.0
0.4
0.7
0.7
0.0
fermentation products  for  biological  phosphorus
removal.  For wastewaters  with a relatively  high
TKN:BOD ratio,  the  effect of  nitrate nitrogen in the
return sludge on anaerobic zone fermentation may be
significant for these two processes.

In contrast,  the anoxic stage of the UCT  process  is
designed and operated to produce a very  low nitrate
nitrogen  concentration. The  recycle of  mixed liquor
from the anoxic stage to  the anaerobic stage thereby
provides  optimum  conditions  for conversion of
available soluble BOD to fermentation products.  The
mixed  liquor recycle from the  aerobic  stage to the
anoxic stage (recycle 2) can  be controlled to assure a
minimal nitrate nitrogen  concentration  in  recycle  1,
while acheiving some level of nitrogen removal in the
anoxic  zone. The  process  has  generally  been
recommended for wastewaters with influent TKN:COD
ratios of greater than 0.08 or influent COD:TKN ratios
of less than  12.0 for South  African  applications.
Gerber et al.  (56)  compared  UCT and Modified
Bardenpho  process  performance  in  pilot-scale
studies. At  a  COD:TKN   ratio  of 9.5,  he found no
performance difference.

A modified UCT process  is  also  shown in Figure 3-
6. In this case,  the  first  anoxic zone is designed to
reduce only  the nitrate nitrogen in the return activated
sludge. The second anoxic  zone is designed for a
much  higher quantity of  nitrate nitrogen removal as
mixed  liquor is  recycled  to  it from the  nitrification
zone.
Another  approach  to  accomplish  biological
phosphorus removal is to  make operational changes
in  existing activated sludge  systems to create  an
anaerobic fermentation zone  ahead  of  the  aeration
zone. Figure 3-7 indicates this approach. In practice,
it typically involves turning off air  flow or aerators in
the front of the activated sludge basin. As described
in  Section 3.1,  this technique  was demonstrated
during the  earlier  investigations  of  phosphorus
removal with the  Bardenpho process. The plug flow
plants in the United States, for which high levels of
phosphorus removal  were   reported,  likely had
insufficient aeration  at  the front end of the  aeration
basins and  inadvertently  promoted  the anaerobic-
aerobic  contacting  sequence. Full-scale U.S. plant
operation  modifications  that  have  been  shown  to
accomplish biological  phosphorus removal  are  the
18,130-m3/d (4.8-mgd) Walt  Disney  World  resort
complex  wastewater treatment facility  in  Orlando,
Florida,  and  the 13,250-m.3/d (3.5-mgd) DePere,
Wisconsin  wastewater treatment  facility (47).  Both
plants had about half of their original aeration volume
converted to non-aerated  zones.

In   addition  to  the   designs   presented,  other
modifications  have been  proposed that  combine
chemical  treatment  with  anaerobic-aerobic  staged
activated  sludge  systems. Alum  can  be added  to
biological phosphorus removal  systems as a polishing
step to reduce the total phosphorus  concentration to
less  than 1  mg/l where  insufficient  biological
phosphorus  removal occurs.  Alum  is  added  to the
mixed liquor prior to  the secondary clarifier  at the
Palmetto Bardenpho facility (49). The addition  results
in  an effluent total phosphorus concentration of less
than 1 mg/l vs. 2-3  mg/l when no  alum is added.

Figure  3-8  shows   a  combination  biological
anaerobic-aerobic system  used by Rensink (54) that
also incorporates a  stripper for phosphorus  removal.
The stripper consisted  of a  complete  mix  tank  for
anaerobic  contacting  of  a  sidestream  of  return
activated sludge followed by a clarifier for separation
of the stripped  sludge.  This  combination achieved
                                                  23

-------
Figure 3-6.   UCT process flow schematics.


                                Recycle 1            Recycle 2
      Influent
                         Anaerobic
                                                               Aerobic
                                                           _ ReturnJ5ludge


                                                       UCT Process
                                                                                                             Effluent
                                    Recycle 1
Recycle 2

Influent "^
|
Anaerobic
i
Anoxic
T
Anoxi

r

Aerobic

                                                                                 	W  Clanfier  j-
                                          [	  _ r^eturn_SJudge	^


                                                   Modified UCT Process



Figure 3-7.   Operationally modified activated sludge system for biological phosphorus removal.

Influent ^ ""

Anoxic/
Anaerobic



Return Sludge
f~^
x__^
T
1
	 1
                                                                                                             Effluent
                                                                                                             Effluent
Figure 3-8.   Combination biological phosphorus removal system.


                            Anaerobic                     Aerobic

Influent "
	 >
L
1
2
3
4
5
1
2
3
4
5
4 L__
Return Sludge j

_^. Waste
Sludge
Clarifier
v
1
1
1 ~ 1
                                                     Phosphorus
                                                        Rich
                                                     Supernatant
                                                                    Settling
                                                Stripped Return Sludge
                               Mixed

                              XX
                              Stripper
                                                                                                            Effluent
                                                            24

-------
more than 97 percent  total phosphorus  removal
compared to  40-50 percent  removal  for  the
anaerobic-aerobic sequence  without  the  stripper.
The  activated sludge system was operated with a
relatively low  organic loading and nitrification  was also
occurring. High nitrate production may  have affected
the phosphorus removal  efficiency of the anaerobic-
aerobic system without the stripper.


3.3  Performance
An inventory of full-scale biological  phosphorus
removal facilities  was identified as of April  1984 by
Tetreault  et  a/.  (47). Thirty biological phosphorus
removal facilities were identified as being in operation,
construction,  or design with 28 of these being either a
Phostrip, Modified Bardenpho, or A/0 process. At that
time, 11  of the facilities  were in operation  with five
being Phostrip installations. Three were  modified
Bardenpho  installations,  two were  operationally
modified  activated sludge systems, and one was an
A/O system.

3.3.1 Phostrip Performance
Table 3-4  summarizes the  basic design  information
for  full-scale  Phostrip  plants,  and  Table  3-5
provides performance data summaries for phosphorus
removal by the  Phostrip  plants.  The Seneca  Falls,
New  York plant was a  full-scale demonstration
project, and the performance data are for one  month
of intensive plant monitoring. The Phostrip process is
used in the first-stage activated  sludge system of a
two-stage  nitrification  system  at the  Lansdale,
Pennsylvania  plant.  The  second-stage  nitrification
system  consists  of  trickling filters and  clarification.
Primary treatment is not  provided at this  plant,  but a
24-hour detention,  in-line flow equalization  basin is
used. For the June  to August 1984 test  period,  the
Lansdale  effluent contained an average  of  0.8 mg/l
total phosphorus.  This  performance illustrates  the
ability of the Phostrip process to  produce low effluent
phosphorus concentrations  with  weak wastewaters,
as the influent TBOD averaged only 41 mg/l. Reactor
clarifier  overflow  from the lime  treatment step and
secondary effluent  were used as  the stripper tank
elutriant sources.  The secondary effluent was nitrified
and  the stripper  overflow contained up  to  3.0 mg/l
nitrate  nitrogen  (47).  The   orthophosphorus
concentration  in the stripper overflow averaged 20.0
mg/l,  and  the  stripper  SDT  was  20 hours.  Lime
scaling occurred  in the  reactor-clarifier elutriation
return line.

The  effluent  phosphorus  concentrations  shown  for
Adrian, Michigan, are for  samples after the second-
stage nitrification step and filtration.  A  first-stage
activated  sludge  system  incorporating the  Phostrip
process is preceded by  primary  treatment and  in-
line equalization. For the  performance data shown in
Table 3-5, the plant  influent TBOD averaged only 78
mg/l. The  upset problems noted were associated with
mechanical problems with  the anaerobic digesters.
During these periods sludge was temporarily stored in
the treatment  system and  the stripper tank  was
overloaded.

The Savage, Maryland plant (also  referred to as  the
Little  Patuxent  plant) is a  two-stage  nitrification
activated sludge system following primary  clarification.
The  Phostrip process is operated within the  high-
rate  first-stage  activated  sludge  system.  Partial
nitrification occurs in this stage. The nitrification  stage
is  followed by  filtration and  chemical polishing  to
consistently  produce  effluent  total phosphorus
concentrations  below  1.0  mg/l.  The  effluent
phosphorus concentration values  shown  in Table 3-
5  are for samples taken  after the  first-stage
activated  sludge system.  The improved  effluent
phosphorus  concentration  for April  1985  reflects
operating changes  made at  the  plant.  These
consisted of  changing  the  first-stage activated
sludge system from a step feed to a plug flow  mode
and reducing the reactor-clarifier  elutriation overflow
rate to the stripper tank. Stripper underflow was used
to supplement  the  reduced   reactor-clarifier
elutriation flow. The  reduced reactor-clarifier elutriant
flow rate was thought to be responsible for improved
stripper  performance, resulting  in  an  overflow
orthophosphorus concentration  of  17.6 mg/l in April
1985  compared  to 7.2 mg/l  for the  July   1984
operation.

The Southtowns, New York facility has a relatively  low
influent phosphorus  concentration, and the  Phostrip
system is reportedly not operated continuously  when
the effluent  phosphorus  limit  is met by secondary
treatment and filtration alone (59). The Amherst, New
York facility is not operating its Phostrip  system, as
two-point  ferric chloride addition has  been found to
effectively treat  a  presently  lower  influent  total
phosphorus concentration  of  3-4 mg/l. Prior to this
the plant  experienced a number of mechanical and
operating  problems.  Mechanical problems  included
scaling in the lime feed line, malfunction of lime feed
pumps,  and  freezing in  the lime slurry  line.
Operational problems were  encountered when  the
activated  sludge system MLSS concentration  was
increased to  provide extended  aeration  conditions,
which resulted  in overloading the stripper tank.

The  full-scale  Reno-Sparks,  Nevada facility  used
the Phostrip process for phosphorus removal as part
of a  plant expansion design after  successful results
with  a 23,000-m3/d  (6-mgd)  plant-scale evaluation
(61).  The 113,700-m3/d  (30-mgd) expanded facility
employs  five parallel anaerobic stripper  units.
Elutriation is accomplished  by recycling sludge from
the bottom of the  stripper  to the stripper inlet to
release phosphorus  into the  stripper supernatant.
During portions  of  the  initial startup  phase,  the
effluent total  phosphorus  exceeded 1-3 mg/l.  This
was   attributed  to  colloidal  carry-over  of   lime-
                                                  25

-------
Table 3-4. Basic Design Information for Full-Scale Phostrip Plants
Seneca Falls, Landsdale,
NY PA Adrian, Ml
Design flow, m3/d
Final eff. TP std., mg/l
Aeration by Oxygen or Air
Aeration mode
Nitrification, 1 - or 2-
stage sec. treatment
Equalization
Final filtration
Sludge handling
Strippers, no.
Reactor-Clanfiers or
Mxer/Flocculators, no
Elutriation source2
3,400
1.0
A
Complete Mix
1
No
No
Thickening,
Anaer. Dig.
1
MF 1
SR
9,500
2.0
A
Plug Flow
2
Yes
No
Thickening,
Vac Fill.
1
RC 1
RC/SEC
26,500
1.0
A
Conv.
2
Yes
Yes
Thickening,
Anaer. Dig.
1
MF 1
PRI
(57).
Savage, MD
56,800
0.31
A
Plug Flow or
Step Feed
2
Yes
Yes
Thickening,
Anaer. Dtg
2
RC 2
RC
Southtowns,
NY
60,600
1.0
O
Plug Flow
1
No
Yes
Filter Press,
Incineration
4
RC4
RC
Amherst, NY
90,900
1.0
O
High Rate
2
Yes
Yes
DAF
Thickening
2
RC 1
RC
Reno-
Sparks, NV
113,700
0.51
A
Plug Flow
1
No
Planned
Anaer Dig.
5
MF 2
SR
1 With final final filtration; chemical polishing available but not utilized
2 Sludge Recycle elutnation; Reactor-Clanfier overflow elutnation, PRInnary effluent supplement; SECondary effluent.
Table 3-5.   Performance Data Summary for Full-scale Phostrip Plants.
                                                    Total Phosphorus, mg/l
Plant

Seneca Falls, NY
Landsdale, PA
Adrian, Ml
Savage, MD
Southtowns, NY
Amherst, NY
Reno, NV
Design
Flow
m3/d
3,400
9,500
26,500
56,800
60,600
90,900
113,700
Startup
Date

1973
1982
1981
1982
1982
1982
1981
Data
Period
mo.
1
12
11
6
1
1
4
12
4
Influent Averages
mm. mo. ave. mo. max. mo.
6.3
4.0 5.2 6.4
3.4 4 4 5.3
5.7 8 1 9.3
66
7.0
2.3 32 4.1
2.9 5.2 14.3
70-73
Effluent Averages
mm. mo. ave. mo. max. mo.
0.6
0.6 1.2 2.0
<0.1 0.4 0.6
05 1.2 1.7
1.7
0.5
0.3 0.5 0.9
04 1.3 2.5
0.8 1.1
Notes

Full-scale demo

Excludes periods
of upset due to
other plant
problems
July 1984
April 1985


9/82-12/82
Ref.

6
58
59
58
47
47
59
59
60
precipitated solids  from  a  sludge  lagoon  (58).
Advanced  control instrumentation and  problems with
the lime feeder also added to startup difficulties. The
method  of introducing  the  recycle  sludge to  the
stripper tank  inlet was  modified  to  prevent  the
entrainment of air that would counteract anaerobic
conditions in the stripper. A distributor was devised to
introduce the return sludge at a depth of 1.8 m (6 ft.).

3.3.2 Modified Bardenpho Process Performance
Table 3-6  summarizes  basic design parameters  for
the  first two  full-scale  North American  Modified
Bardenpho facilities operating in the United States at
Palmetto,  Florida, and in Canada at Kelowna,  British
Columbia, respectively.  Both plants are operated with
relatively long  detention  times  to provide sufficient
volume for nitrification  and denitrification  as  well  as
biological phosphorus removal.  The  design SRT  for
the Kelowna  plant  is  1.5-2.0  times  the Palmetto
plant  due to  the  need to operate  at  much colder
wastewater temperatures.  Both  plants have polishing
filters to meet stringent  effluent requirements for BOD
and suspended solids as well as nutrients. Required
effluent limits for the Palmetto  plant are equal to or
less than  5,  5,  3,  and 1  mg/l for  TBOD,  total
suspended solids (TSS), total  nitrogen,  and  total
phosphorus,  respectively. The   allowable  limits  for
TBOD,  TSS, total nitrogen, and total phosphorus  for
                                                    26

-------
Table 3-6.
Modified Bardenpho Process  Full-Scale  Plant
Design Summary.
                            Palmetto, FL
                               (64)
                              Kelowna,
                              Canada
                              (62,63)
 Startup date                    10/79         5/82
 Flow, rrvVd                     5,300        22,700
 Detention time, hr (no. cells)
  Anaerobic zone                i.O(i)        2.0(1)
  Anoxic 1 zone                 2.7 (1)        4.0 (4)
  Nitrification zone               4 7 (1)        9.0 (9)
  Anoxic 2 zone                 2.2 (1)        40 (4)
  Reaeration zone               1.1 (1)        2.0(2)
  Total, hr                     116         21.0
 SRT, days                      20         30-40
 MLSS, mg/l                    3,500        3,000
 Temperature, °C                18-25        9-20
 Sec. clanfier application rate,        22.3         14.0
  m3/m2/d
 Polishing filter application rate,       93 7         23.4
  m3/m2/d
 Primary treatment                No          Yes
 Biological sludge handling        Drying Beds   DAF Thick.,
                                        Composting
the  Kelowna  plant are  8,  7,  6,  and  2  mg/l,
respectively.

By  coincidence, both plants use  submerged  turbine
devices for aeration. Other Modified Bardenpho plants
are  using  different  aeration devices  such  as  fine
bubble  diffusion  at  Payson, Arizona, and  at some
South African plants (57,65) . The  Carrousel oxidation
ditch  system  has been  used  in  the Modified
Bardenpho  designs at Fort  Meyers  and  Orange
County, Florida. The Kelowna plant was designed  with
submerged  turbine mixers  and/or aerators in each of
the  multiple cells  used in the  various anaerobic,
anoxic  or  aerobic zones  to  provide maximum
operating  flexibility.  The  nitrification zone,  for
example,  has  nine  cells  with  each stage having  a
design detention  time of  1  hour.  The last four cells
can  be  operated  with or without air  addition with the
turbine mixers,  so that the  nitrification detention times
and  second anoxic zone detention times  can be
varied. The  second anoxic zone also can be operated
with air addition to provide additional nitrification time,
if needed.

Both plants shown in  Table  3-6 use low-head,
automatic  backwash  filtration  to  meet  effluent
suspended  solids requirements.  Both  plants were
designed  with  primary  clarification, but the  Palmetto
plant modified  its  operation  after  startup  (16) by
introducing the  return activated sludge to the primary
tank to  effectively use the tank to provide additional
anaerobic fermentation  time.  At  the  Kelowna plant
some of the organic material in the solids removed in
primary treatment can also be  used to support the
biological   phosphorus  removal  process.  The
supernatant from the primary sludge gravity thickener
can be  returned to the anaerobic fermentation  zone
or first anoxic  zone.  This supernatant  contains
fermentation products when  the solids are held in the
thickener long enough.

Another similarity with  the two plants is that they do
not employ either aerobic or anaerobic  digestion of
the waste  activated sludge.  The practice of sludge
digestion has not been  recommended for Modified
Bardenpho  biological phosphorus removal plants (12)
since  the  recycle  of  phosphorus  expected to  be
released during sludge destruction would overload the
phosphorus removal capacity of the activated sludge
system. At Palmetto,  the sludge is wasted from the
sludge  recycle  line directly to drying   beds.  The
recycle  flow from the drying bed underdrains results
in a minimal additional phosphorus load  to the  plant
(66). The ultimate disposal of the drying bed sludge is
by land  application.  At  Kelowna, dissolved air flotation
thickening  of the waste activated sludge is used to
prevent anaerobic conditions and phosphorus release.
The  sludge is further composted  prior  to  ultimate
disposal.

One  year  of  plant performance data (April  1981-
March  1982)  is shown  for  the  Palmetto  facility in
Table 3-7.  The data are monthly average summaries
of influent  wastewater  and  filtered effluent  quality
obtained from  plant records. Due to the relatively
weak  influent  wastewater,  biological phosphorus
removal capacity was  limited. As shown, alum  was
added prior to the secondary clarifier during 5 months
of the  1-year  period to reduce  the  orthophosphorus
concentration  and  to achieve an  effluent  total
phosphorus concentration generally less than  1  mg/l.
The  plant  also  consistently  achieved effluent  total
nitrogen concentrations of less than  3 mg/l.

Table 3-8  shows  a 2-year  performance  summary
for the  Kelowna plant from January  1983 through
December  1984. During this period,  a  number of
operating  conditions  were  investigated  and  the
influent  load was at about 54 percent of the design
load. The final  filter effluent  summary  for  the 2-year
operation includes results for a two-train  operation, a
single-train  operation, thickener  supernatant feeding,
and  splitting  of  the  return sludge  between  the
fermentation  zone and first  anoxic  zone. The  plant
effluent  was well within the treatment requirements for
nitrogen  and phosphorus removal.  During the  one-
train  operation  period  (May  - November,  1984), the
single train  was loaded at about 120  percent of its
design loading and effluent requirements were met.

3.3.3 A/O Process  Performance
The  first  full-scale   demonstration  of  the  A/0
biological phosphorus removal process occurred with
the conversion of one-third of the 34,000-m3/d
(9-mgd)  Largo,  Florida contact  stabilization system
                                                   27

-------
fable 3-7. Palmetto, FL Modified Bardenpho Process Performance (April 1981
April May June July Aug. Sept. Oct
Influent
Flow, m3/d
TBOD, mg/l
TSS, mg/l
Temperature, °C
TKN, mg/l
NH4-N, mg/l
Total P, mg/l
Ortho P, mg/l
Alkalinity, mg/l
Filtered effluent
TBOD
TSS, mg/l
Total N, mg/l
NO3-N, mg/l
NH4-N, mg/l
Total P, mg/l
Ortho P, mg/l

3,200
164
155
25
31.8
25.0
9.2
6.5
174

2
3
2.1
1.0
0.4
2.5
2.2

3,000
159
157
27
40.8
25.2
6.4
6.1
169

1
2
2.1
1 3
0.3
3.4
1.4

3,500
124
144
29.5
30.1
20.4
7.0
5.3
156

1
2
1.9
1.0
0.3
2.6
2.5

3,600
104
112
30.5
25.0
18.7
5.6
4.5
154

1
2
2.8
1.9
0.2
1.8
1.7

5,500
74
76
29.5
19.7
12.7
4.1
2.8
143

1
2
2.0
1.2
0.2
1.5
1.1

5,900
67
76
29
21.9
12.7
4.9
35
140

1
1
1.7
1 1
0.2
1.2
1.3

3,700
113
116
28
28.1
17.8
6.3
4.7
144

1
2
1.9
1.1
0.2
1 1
0.9
- March 1982 Monthly Averages) (49).
Nov. Dec. Jan. Feb. March

3,300
157
160
27
40.0
22.6
8.5
5.9
171

1
2
2.1
1.3
0.2
0.7
0.7

3,200
182
182
24
38.2
27.2
8.8
5.9
198

1
2
2.5
1.5
0.4
1.6
1.0

3,600
160
141
23
37.7
28.0
8.7
5.4
191

1
1
2.7
1.9
0.3
0.6
0.5

3,700
163
167
23
42.4
25.8
8.0
5.2
201

1
2
2.6
1 8
0.1
0.8
0.7

4,500
150
128
23
32.4
23.7
6.6
4.4
187

1
3
2.8
2.1
0.2
0.9
0.8
' Minimal alum dose applied prior to secondary clarification.
Table 3-8.   Kelowna, Canada Modified Bardenpho Process
           Performance Results of Cumulative Frequency
           Plot of Data (62).

                      Median    Lower 5%   Upper 5%
Influent
(1/83 - 12/84)
Flow, m3/d
COD, mg/l
TKN, mg/l
NH4-N, mg/l
Total P, mg/l
Ortho P, mg/l
Final Effluent
(1/83 - 12/84)
TKN, mg/l
NO3-N, mg/l
NH4-N, mg/l
Total P, mg/l
Ortho P, mg/l
Final Effluent - 1 Train
(5/22/84-11/9/84)
Flow, m3/d
NO3-N, mg/l
NH4-N, mg/l
Ortho P, mg/l
12,400
3.3
24.5
17.5
4.5
3.8

1.5
1.8
0.1
0.8
0.77
14,000
2.0
<0.1
1.1
10,400
2.7
19.0
15.0
3.3
3.0

0.2
0.8
<0.1
0.2
0.15
12,000
1.2
<0.1
0.08
10,000
2.6
33.5
21.1
5.8
4.3

1.8
4.2
6.0
1.8
2.25
17,000
3.4
0.75
1.75
to an A/0 system treating primary effluent. The total
average hydraulic detention time  was 4.1  hours with
0.9 hour in three anaerobic stages,  0.6 hour in two
anoxic stages, and  2.6  hours in  five aerobic stages
(29). The A/O system had its  own secondary  clarifier.
During nitrification operating conditions, mixed liquor
from the fifth  stage  of the aerobic zone was recycled
back  to  the  first  anoxic  stage.  The   MLSS
concentration and SRT  were  decreased to provide a
non-nitrifying  operation.  At that  condition,  the two
anoxic stages were operated as additional anaerobic
stages and internal  recycle of  mixed liquor was not
practiced.

Table 3-9  summarizes effluent  concentrations
reported for  nitrifying and non-nitrifying  conditions.
Slightly lower TBOD and  higher TSS concentrations
are shown for the  nitrification operating period. The
orthophosphorus  and  total  phosphorus  effluent
concentrations  were also  higher.  Unfortunately,
insufficient  data  were  presented  to allow  a
determination  of   whether  the  difference  in
performance  was related to the nitrification operation
or changes in  the  primary  effluent fed  to the A/O
system. Data on influent characteristics for  another
time  period (August  1979-July 1980)  indicated that
the TBOD, total phosphorus, and TKN ranges were
81-127 mg/l, 7.0-9.4  mg/l,  and  21.4-30.5  mg/l,
respectively (29). The influent  SBOD  was about  50
percent of the influent TBOD.
                                                  28

-------
Table 3-9.
 Parameter
Summary of A/O  Process  Effluent  Quality
(Average Monthly and  Monthly Range), Largo,
FL (29).
        Non-Nitrification
Nitrification
Data period
TBOD, mg/l
TSS, mg/l
Total P, mg/l
Ortho P, mg/l
2/81 - 6/81
7 (6-8)
10(8-13)
1.4 (1.2-1.5)
0.6 (0.5-0.8)
9/81 - 2/82
5 (4-7)
18(10-22)
1.7 (1.3-2.2)
1.0(0.5-2.0)
The phosphorus content  measured for the  waste
activated sludge was reported to be  4.2-6.0 percent
(17). The sludge handling method proposed  for the
Largo  facility  consisted of dewatering, drying,  and
palletizing for use as a soil conditioner/fertilizer.

Table  3-10 describes  operating  conditions  for  a
two-train A/0  process  at  a Pontiac,  Michigan EPA
demonstration  site. The  original  activated  sludge
system consisted of four plug flow trains with coarse
bubble diffusion. Two of the trains were converted  to
the A/O process to allow a performance comparison
of  biological phosphorus  removal  to  conventional
activated sludge treatment. The existing tankage was
divided into  desired  stages  by the  installation  of
wooden  baffles.  Side-mounted  submersible  mixers
were  installed  to provide mixing  in  the  anaerobic
stages after  plugging  the diffuser lines. The
demonstration  project  also allowed an  evaluation  of
the A/O process under cold  temperature operation,
during  nitrification, and with  anaerobic digestion
supernatant return (67).

Table 3-10.  Pontiac, Ml  A/O System Operating Conditions
           (67).
  Operating dates
  Average flow, m3/d
  Average detention time, hr (no. cells)
   Anaerobic zone
   Aerobic zone
  SRT, days
  Temperature, °C
  Primary treatment
  Biological sludge handling
                      7/13/84 -3/31/85

                           12,200


                           1.8(3)
                           6.7 (4)
                           16-24

                           10-17

                            Yes

                      Anaerobic Digestion
The treatment performance for different operating
phases is  summarized in Table 3-11. Effluent total
phosphorus concentrations averaged less than 1.0
mg/l during the study period, with complete or partial
nitrification. Influent  phosphorus concentrations were
relatively low,  and a comparison of performance with
a  parallel  conventional  activated  sludge  system
showed  an increased  total  phosphorus  removal of
1.2-1.6 mg/l  for  the A/0 process  operation.  Other
factors  that could have potentially  limited biological
phosphorus removal performance at Pontiac were the
relatively long SRT for an A/O system and the recycle
of nitrate  nitrogen in  the  return  sludge  to  the
anaerobic zone. It appears there was sufficient BOD
in the  influent  to offset  these  considerations.
Evaluation  of  the digester  supernatant during  this
study indicated a minimal level of soluble phosphorus
was  released  during  anaerobic  digestion.
Consequently, the impact of supernatant recycle on
system  performance was minimal.  One explanation
offered for  this was the  possibility  of  the formation  of
a magnesium  ammonium phosphate precipitate, but
further study was suggested. Average effluent TSS
concentrations  from the secondary  clarifier  ranged
from 6  to  10  mg/l,  thereby  minimizing  the
concentration  of  particulate  phosphorus in the  final
effluent.

Table 3-11.  Full-scale A/O Process Performance,  Pontiac,
           Ml  (67).
Influent
Influent
Flow, m3/d
TBOD, mg/l
SBOD, mg/l
NH4-N, mg/l
Total P, mg/l
Soluble P, mg/l
Temperature, °C
Reactor
MLSS, mg/l
MLVSS, mg/l
SRT, days
Effluent
TBOD, mg/l
SBOD, mg/l
NH4-N, mg/l
NO3-N, mg/l
Total P, mg/l
Soluble P, mg/l
TSS, mg/l
VSS, mg/l
Phase I

11,300
110
65
15.2
3.2
1.9
17

2,820
1,800
24

6.2
1.8
0.9
10.4
0.8
0.7
6
4
Phase II*

10,800
137
65
17.8
4.1
2.2
16

2,410
1,670
21

9.4
3.0
2.8
11.6
0.7
0.6
7
4
Phase III

12,070
143
87
16.1
3.7
2.2
11

2,340
1,640
19

12.9
2.6
5.9
6.7
0.4
0.3
8
5
Phase IV"

14,680
112
65
18.5
3.0
1.6
10

2,360
1,590
16

12.7
2.0
4.5
8.8
0.7
0.5
10
6
                * Anaerobic digester supernatant returned during these phases.
                3.3.4  Operationally  Modified  Activated  Sludge
                Process Performance
                An  operationally  modified  activated  sludge  system
                involves turning  off aerators  at the front end of the
                activated  sludge basin  to  create   anaerobic
                fermentation conditions to  provide  the preferred
                substrate for the  phosphorus-removing bacteria.  The
                early reports on  "luxury uptake" of phosphorus  were
                for  plug  flow plants  at Baltimore,  Maryland;   San
                Antonio, Texas; and Los Angeles, California. Oxygen
                transfer with the diffused aeration  systems at the front
                end of these activated sludge systems was apparently
                sufficiently limited to stimulate anaerobic  fermentation
                conditions.  Unaerated  conditions  were  purposefully
                                                   29

-------
created at the front end of activated sludge aeration
basins at DePere, Wisconsin, and at the Reedy Creek
Improvement District main plant in  Lake  Buena Vista,
Florida.  The  performance  of these  operationally
modified plants has  been evaluated and the results
reported (47).

The Reedy Creek plant serves the  Walt Disney World
resort complex. Operating  conditions for  the plant are
shown in Table 3-12. The  plant  uses  four  parallel
plug flow aeration basins following  primary treatment.
The  initial  third  of  each  basin  is  unaerated.
Backmixing  provides  sufficient agitation to maintain
suspension  of solids in  the  unaerated   zone.
Nitrification  and  denitrification  also occur  in  the
system.
Table 3-12.  Operating Conditions for Operationally Modified
           Activated Sludge Systems (47).
Table 3-13.   Average Performance of Operationally Modified
           Activated Sludge Systems (47).

Design flow, m3/d
Detention time, hr
Unaerated zone
Aerated zone
Sec. clar. overflow rate,
m3/m2/d
SRT, days
MLSS, mg/l
Return sludge ratio
Primary treatment
Sludge handling
Reedy
Creek
22,700

3.0
6.0
14.7
7.2
2,100
0.59
Yes
DAF Thick.,
Aerobic Dig.,
Land Spread
DePere
53,750

7.5
15.0
17.9
10.6
3,000
0.81
No
DAF Thick.,
Filter Press,
Incineration
The DePere  operation involved modifying a contact-
stabilization activated sludge system. The stabilization
tank  air  supply was  stopped,  and  mixing  was
accomplished in the basin with turbine aerator mixers.
A complete mix aerated contact basin was then used
for  the  aerobic  treatment step. The detention times
are given in  Table 3-12. The  plant was operating  at
about 50 percent of its design capacity, resulting  in
the relatively  long detention times shown.

Table  3-13  indicates  that both   plants  achieved
relatively low  effluent phosphorus  concentrations
during the three-month summer test  period.  Effluent
suspended solids concentrations were low enough  to
minimize the contribution of paniculate phosphorus  to
the final effluent. Nitrification  was  occurring  in  both
plants,  but  apparently  the  biological phosphorus
removal levels were not limited by the nitrate nitrogen
present in the return activated  sludge. This may have
been due to the level of BOD in  the influent, warm
wastewater  temperatures,  and  relatively  long
unaerated detention times.

Test dates: June - August 1984
Influent
TBOD, mg/l
SBOD, mg/l
Total P, mg/l
Ortho P, mg/l
Effluent
TBOD, mg/l
TSS, mg/l
Total P, mg/l
Ortho P, mg/l
NH4-N, mg/l
Reedy
Creek


155
85
6.7
5.3

3
13
0.9
0.4
0.7
DePere


150
86
5.1
1.9

7
7
0.3
0.1
1.4
3.3.5 Factors Affecting Performance

3.3.5.1  Phostrip Process Solids  Detention  Time
and Elutriant Quality
In evaluating  effects  on  performance,  one  must
distinguish  between the sidestream operation  of  the
Phostrip system and  the  mainstream  systems. The
Phostrip system has  shown  the highest degree  of
treatment flexibility and treatment  effectiveness with
low  organic  strength wastewaters  because a
substantial  amount of  the  total  phosphorus removal
can occur via  the stripper and chemical  precipitation
operations.  For  example,  effluent total  phosphorus
concentrations of less  than 1  mg/l  were obtained at
Lansdale, Maryland,  in  spite  of  an average influent
TBOD of only 41 mg/l and  an influent total TBOD:total
phosphorus (TP) ratio of only about 8.1.  Under such
conditions  the  mainstream  biological  phosphorus
removal processes would be expected to achieve less
efficient phosphorus removal.

The critical design and operating  parameters that
affect performance  in  the  Phostrip process are  the
stripper SDT,  the  elutriation  rate,  and the elutriant
source.  The  proposed  mechanism for biological
phosphorus removal suggests that  sufficient SDT is
needed in the  stripper  to form substrate fermentation
products from  lysed bacteria. Successful performance
has been observed for stripper SDT  values  in  the
range shown in Table 3-2. Longer SDT values  are
suggested for  operations with a significant quantity of
oxidized nitrogen entering  the  stripper, either via the
return activated sludge stream  or the elutriant stream.
For  such  cases,  a  50-percent  increase in  the
stripper SDT has been recommended (48).

The elutriant source can affect the SDT design  of the
stripper and overall performance. The least  desirable
elutriant source would be a nitrified secondary effluent
with a  significant  DO  level.  Some  of the  available
substrate in the stripper operation would be needed to
reduce the DO and  nitrate  oxygen  before  the
                                                  30

-------
necessary organic fermentation activity could occur.
As conditions change in  the plant, the SDT may be
adjusted in the stripper by varying the sludge blanket
depth. The chemical treatment system overflow has
been  frequently  used as a  stripper  elutriant source
because of its  low phosphorus  content.  Another
potential elutriant  source is primary effluent.  The
readily available  organic  material  in  primary effluent
could  result  in  a lower SDT, since  less organic
material is needed from the lyzing of biological solids
in  the return activated sludge. This  elutriant source
should  contain  little,  if any,  DO  and no  oxidized
nitrogen.

3.3.5.2 Effluent Suspended Solids
An important plant performance consideration for both
the Phostrip and  mainstream processes  is  the
secondary  effluent suspended solids concentration
and phosphorus  content of those solids. This is even
more  critical for  the mainstream processes  because
they normally produce mixed liquor suspended solids
higher  in  phosphorus  content than  the  Phostrip
process. Phosphorus contents of MLSS on  a dry
solids  basis of  2.3-5.8 percent have been  reported
for  Phostrip  and  mainstream systems   (47),  with
values in the lower portion of  this range  reported for
the Phostrip process.

Many  of the nutrient removal facilities,  including
Palmetto,  Kelowna, and Payson,  have required  final
filtration to meet very low effluent suspended  solids
and   BOD limits  as  well  as  nutrient  removal
requirements. In  other cases, low effluent suspended
solids  may  not  be  required.  In  these  cases,  the
necessity of effluent filtration may be evaluated as a
means to meet the required  effluent total  phosphorus
concentration. This  consideration  is  illustrated in
Fiqure 3-9.  An effluent   total  phosphorus
concentration requirement of 1.0 mg/l is  assumed. If
the effluent soluble phosphorus concentration  is 0.5
mg/l and the  phosphorus content of the MLSS  is 5
percent, the effluent TSS concentration has to  be 10
mg/l or less to meet the 1.0-mg/l  effluent  total
phosphorus limit.  If the  solids phosphorus content
were 3 or 4 percent, the effluent TSS would have to
be equal to or less than 17 or 12.5 mg/l, respectively.
Thus,  unless   excellent  secondary  clarifier
performance  is  achieved  or  the  effluent soluble
phosphorus concentration is very  low (e.g.,  0.2  mg/l
or less), a  polishing filter would be required to  meet
an effluent total  phosphorus level of 1.0 mg/l. With
the exception of  the  Largo  nitrification operating
condition,  the  full-scale  plants  described in  the
performance  section were  able to produce effluent
TSS concentrations of less than 15 mg/l. The effluent
suspended solids data shown for Palmetto were after
filtration, but effluent TSS concentrations  of  4-8  mg/l
from the secondary clarifier have been reported (16).
It appears that a conservatively designed secondary
clarifier could produce  effluent  suspended  solids
concentrations low enough to  meet a typical effluent
total phosphorus  requirement  of  1.0  mg/l, provided
the soluble phosphorus  concentration  in the effluent
stream does not exceed 0.4-0.6 mg/l.
Figure 3-9.   Maximum effluent soluble P concentration for
           effluent total P < 1.0 mg/l.
 Eff. Sol. P, mg/l
   1.0
  0.8
  0.6
  0.4
  0.2
                               2 % P in solids
                  10      15     20
                   Effluent TSS, mg/l
                                      25
                                            30
3.3.5.3 Available  Organics  for  Phosphorus
Removal
Effluent soluble phosphorus concentrations as low as
0.1-0.2  mg/l  have been achieved  in  the  Modified
Bardenpho, A/O, and operationally modified activated
sludge processes  (47,62,68).  However,  this is not
achieved at all plants and for all  operating conditions
because of  the   dependence on  the availability of
fermentation  substrate products   needed  by  the
phosphorus-storing bacteria  relative to the  amount
of phosphorus that must be  removed in the system.
In addition, as will be discussed  further, the  required
ratio of fermentation substrate per unit of  phosphorus
removed is affected by  the amount of nitrate nitrogen
entering the fermentation zone and  also by the SRT
of the system.

Based  on  the  biological  phosphorus  removal
mechanism described in Section  3.1, a given amount
of fermentation products, such as acetate, consumed
by the phosphorus-removing organisms  will yield  a
certain  quantity of new  organisms.  A significant
fraction  of the dry weight of  these  organisms will be
phosphorus,  and  phosphorus  removal  eventually
occurs  in  the  system by  the wasting of  these
organisms. Fundamental studies working with  pure
cultures  of  Acinetobacter have  determined  a
synthesis  yield  of 0.42 g  solids/g  acetate and  a
phosphorus content of  6-10 percent (69,70). Thus, if
                                                  31

-------
the amount  of acetate  or similar  fermentation
products that  could  be consumed in a  biological
phosphorus  system  were  known, the  quantity of
phosphorus  that  could  be  removed  could  be
estimated.  Unfortunately,  the  complexity  of the
process has thus far prevented the determination of
the amount of  fermentation  products produced, and
then  consumed,  by  the  phosphorus-storing
organisms.  The fermentation products  used by the
phosphorus-storing organisms will be generated in
the anaerobic zone and  some may be present in the
influent  of more septic wastewaters. Due to the rapid
assimilation of  the  fermentation products in the
anaerobic zone, it has not been possible to measure
their production rate (70).
Since the amount of fermentation products produced
in the  system can  not  be measured, other indirect
methods  have  been proposed  in  an  attempt  to
quantify  the phosphorus  removal  potential  of a
system. Siebritz  et al. (71)  recognized that municipal
wastewater is  made up  of  slowly  biodegradable
subtrate  and a subtrate fraction  that is  biodegraded
more rapidly. They  measured  the immediate oxygen
uptake  of  a mixed liquor  upon  addition  of a
wastewater sample  to quantify what they termed the
readily degradable  portion of the  substrate.  They
established a  minimum  influent  concentration  of
readily degradable substrate of 25 mg/l for biological
phosphorus removal to  proceed.  Nicholls et al. (70)
had difficulty relating such measurements to biological
phosphorus removal performance. They  proposed an
alternate method  using  nitrate  as the  electron
acceptor. In this method, the initial zero-order nitrate
reduction rate after addition of a wastewater sample
to the mixed liquor is  measured.  The amount of
nitrate nitrogen  used during the time that  a  zero-
order reduction  occurs  is  then  related  to  a readily
biodegradable  substrate by   a  stoichiometric
conversion. The  basic  concept  in  both methods is
that the more readily biodegradable substrate may be
the  source  of  the fermentation products in  the
anaerobic  zone of biological phosphorus  removal
systems.
 As an alternate to these special tests, Hong et al. (29)
 have used  the soluble  BOD concentration  of  the
 influent wastewater as an indication of the amount of
 substrate  readily  available  for  the formation  of
 fermentation products. They  have recommended  an
 influent SBOD: soluble phosphorus  (SP) ratio of at
 least 15 to produce  an  effluent soluble  phosphorus
 concentration  below  1.0 mg/l  for  A/0  systems
 operating at F/M  loadings above  0.15 kg  TBOD/kg
 MLVSS/d.  Data presented by Tetreault  et al. (47)
 from the  full-scale  Largo A/0  system operation
 supported this  recommendation. At influent SBOD:SP
 ratios  below  12,  effluent  soluble phosphorus
 concentrations varied from 0.5 to 4.5 mg/l.
Influent SBOD has not been measured at many of the
full-scale biological phosphorus removal  plants for a
variety of possible reasons. Such  reasons include the
facts  that the mechanism of biological  phosphorus
removal has only recently begun to be unraveled and
the relative degrees of soluble and particulate BOD
fermentation are not known. It has been recognized
that  more phosphorus removals  and  lower  effluent
soluble   phosphorus  concentrations  occur  for
wastewaters  with higher influent  TBOD:TP  ratios.
Figure 3-10  summarizes  data  showing  effluent
soluble  phosphorus concentrations  and TBOD:TP
ratios. Tetreault et  al. (47) have  recommended a
TBOD:TP ratio  of greater than 20-25  to achieve an
effluent  soluble phosphorus concentration below 1.0
mg/l.
Figure 3-10.  Effluent soluble  P  concentration  vs. influent
           TBOO-.TP ratio.
 Eff. Sol. P, mg/l
    6
• Palmetto (49)
O Kelowna (62)
X Tokyo Pilot-Plant (72)
D Pontiac (67)
A Baltimore Pilot-Plant (68)
A A/O Pilot-Plants (29)
• De Pere (47)
o Reedy Creek (47)
                 vl
           10     20     30     40
                 Effluent TBOD:TP Ratio
                                     50
                                            60
 3.3.5.4 Effect of Solids Retention Time
 Fiqure  3-10 shows  that  higher effluent  soluble
 phosphorus concentrations  occurred for the Modified
 Bardenpho facilities operated within the same range
 of  influent TBOD:TP  ratios as other  biological
 phosphorus removal  designs.  The  Bardenpho
 systems were operated, as  expected, at longer SRTs
 to  accomplish  nitrification  and  denitrification.  Lower
 sludge yields associated with the longer SRTs would
 logically  decrease the phosphorus removal capacity
 for the system.

 Assuming a 4.5-percent  waste  activated  sludge
 phosphorus content, Barth   and  Stensel  (66)
 suggested a TBOD removal:TP removal ratio of 33 at
 an SRT  of 25 days and a ratio of 25 at an SRT of 8
 days.  Fukase ef al.  (72) found, in  an A'O  system
                                                  32

-------
pilot-plant study treating municipal wastewater,  that
the TBOD removal:TP removal ratio increased from
19 to 26 as SRT was increased from 4.3 to 8.0 days.
At the  same  time,  the  phosphorus content  of the
activated sludge decreased from 5.4 to 3.7 percent.

Maier et al.  (73) found in pilot-plant studies that the
rate  of  phosphorus  uptake  per unit of  mixed liquor
solids decreased by a factor of 2.6 as the F/M loading
was  decreased  from   0.2 to   0.1  kg  TBOD/kg
MLVSS/d. Tracy and Flammino (74) showed  that for
identical influent TBOD:TP  ratios of 16, the rate of
phosphorus uptake in the aerobic  zone decreased by
a factor of 3 as the F/M  loading was decreased from
0.44  to  0.24  TBOD/kg  MLVSS/d  in  bench-scale
studies.

These results indicate that  operation  at longer SRT
values will decrease the efficiency of phosphorus
removal  per  unit of BOD  removed. To maximize
biological phosphorus removal, systems should not
be  operated  with  SRT  values   in excess  of  that
required  for overall  treatment needs.  Systems  that
require  nitrification  and  denitrification,  such  as the
Modified Bardenpho  system or  extended  aeration
systems promoting   sludge  stabilization, will  require
much higher  influent TBOD:TP  ratios to  produce
soluble phosphorus concentrations below 1.0 mg/l.

3.3.5.5 Nitrate Nitrogen  in the Anaerobic Zone
Barnard  (12) was  the first  to point out that  nitrate
nitrogen  entering the anaerobic  zone  of biological
phosphorus  removal systems  could  reduce  the
phosphorus  removal  capability of  the  system.  He
attributed this to an increase in the  redox potential of
the reactor and a reduction in the degree of anaerobic
stress to induce  phosphorus  release.  However,  an
improved understanding  of  the phosphorus removal
mechanism  indicates that  nitrate reduction  in the
anaerobic zone utilizes substrate that would otherwise
be available  for  assimilation by the  phosphorus-
storing organisms. Thus, nitrate   has  the effect of
reducing the net influent  BOD/P ratio for the system.
Because of this, variable  results have been observed
for systems with nitrate nitrogen present. The degree
of variability depends on the system influent BOD and
phosphorus concentrations and the system SRT. The
return  activated sludge  recirculation  ratio  is also
important as  this  affects  the  amount  of  nitrate
nitrogen fed to the anaerobic zone.

Simpkins and  McClaren  (55)  reported  a  total
phosphorus removal  efficiency reduction from 90 to
55  percent  when  the  effluent  nitrate  nitrogen
concentration increased from 4.0 mg/l to 6.7 mg/l in a
Modified Bardenpho  pilot-plant   study. During  the
Palmetto Modified Bardenpho  operation  (16),  the
internal  recycle pumps   were  stopped,  causing the
effluent  nitrate  nitrogen concentration to increase to
about 10 mg/l and  the  effluent  total  phosphorus
concentration to increase from 2.3 to 7.1 mg/l. These
two examples illustrate the sensitivity of phosphorus
removal  efficiency to nitrate nitrogen entering the
anaerobic zone  of long-SRT  biological  phosphorus
removal systems treating relatively weak wastewaters.

Similar  effects  of nitrate  nitrogen  on  biological
phosphorus  removal have been  reported  in  an
operationally  modified activated sludge system (13).
Vinconneau et al. (75) also showed that nitrate could
significantly   affect biological  phosphorus  removal
performance  for  a lightly  loaded  A/O system.  At
similar  influent  BOD:P  ratios and  operating  F/M
loadings, the effluent total phosphorus concentration
decreased from 2.0 to 0.9 mg/l as the effluent nitrate
nitrogen  concentration  decreased from  3.4 to 0.6
mg/l. The effluent soluble phosphorus conentration at
Pontiac  (67)  was  consistently below  1.0  mg/l even
though   the  average  effluent   nitrate  nitrogen
concentration ranged from 6.7  to 11.6  mg/l for the
four study   periods  reported.  The  low  effluent
phosphorus  concentration  was  attributed  to  a
relatively high influent  BOD:P ratio so that excess
BOD  was  available  to  reduce   the nitrate. The
operationally  modified activated  sludge systems at
Reedy Creek and  De Pere (47) also had a  relatively
high influent  BOD:P  ratio  and  produced low effluent
soluble  phosphorus  concentrations in spite of the
occurrence  of nitrification. In the  Reedy  Creek
system, nitrate nitrogen was also fed to the anaerobic
zone by internal circulation of the nitrified mixed liquor
as well as via the return activated  sludge. Nitrification
and  denitrification were  occurring concurrently  as
indicated by  effluent nitrate nitrogen concentrations of
less  than   4  mg/l and  ammonium  nitrogen
concentrations of less than 1 mg/l.

Rabinowitz (34) studied the  effect of  nitrate  nitrogen
concentration on  phosphorus release in  batch tests
using activated sludge developed  in a UCT system
pilot plant. Sodium acetate was used for the substrate
source. He found that with excess substrate available,
the phosphorus release during  anaerobic  contacting
was inversely proportional  to the  amount of  nitrate
nitrogen  present.  He   further  found  that  the
denitrification of  nitrate in the  anaerobic  batch tests
had the effect of reducing the availability of substrate
for  phosphorus release. The substrate  consumption
for  denitrification  was found to be  3.6 mg  COD/mg
nitrate nitrogen  reduced. This  ratio  is in  close
agreement with a ratio of  3.53 developed by  McCarty
(76) for  denitrification  using acetate.  The  ratio in
actual wastewater  treatment systems  will depend on
the  characteristics of  the  substrate  used for
denitrification in the anaerobic zone. With  nitrate
nitrogen  present, substrate would not necessarily be
converted to  volatile fatty acids by fermentation but
could be used for denitrification directly. A substrate
consumption  ratio determined  from  an  anoxic-
aerobic  pilot-plant  system  treating  domestic
wastewater was about 5.0  mg  soluble  COD/ mg
nitrate  nitrogen reduced  for complete denitrification
                                                  33

-------
(49).  The same  reference  reported  on substrate
consumption  for  anoxic-aerobic  system
denitrification  using  eleven  different  industrial
wastewater substrate sources.  The  mean  substrate
consumption  ratio  was  5.3 mg COD/mg  nitrate
nitrogen reduced, with reported values of 2.2-10.2.

Some  investigators  have  also  reported   on
experiments  that suggested biological  phosphorus-
removing  organisms are  capable of denitrification.
Under substrate limiting conditions,  phosphorus
uptake and nitrate reduction  occurred simultaneously
in  an anoxic  reactor (15,34). Nitrate reduction was
also observed  in a pure culture  experiment with
Acinetobacter 21OA (69).  The nitrate nitrogen was
reduced only  to nitrite  nitrogen,  which  was toxic at
about a 500 mg/l concentration.

3.3.5.6 Wastewater Temperature
The  Phostrip,  Modified  Bardenpho,  and A/O
processes have been applied  successfully for both
cold and  warm  wastewater  temperature conditions.
Reported data on the operation and performance of
operationally modified activated sludge systems  for
biological phosphorus removal during cold wastewater
temperature conditions are limited.

Peirano et  al.  (77)  reported that  wastewater
temperature  had no significant  effect  on Phostrip
process efficiency  during  plant-scale testing  at
Reno-Sparks. This  is  likely  the result of having  an
adequate size stripper to  handle  lower activity levels
at cold temperatures.  Shapiro  et  al.  (4)  showed
specific phosphorus release rates for activated  sludge
ranging from  0.63  mg/l-hr/g of  volatile suspended
solids at 10°C (50°F) to 3.15 at 30°C (86°F).

Modified Bardenpho systems have been designed at
about  twice the  total  hydraulic  detention time  for
treatment of  10°C (50°F) wastewater vs.  2Q°C
(68°F) wastewater (63,64). This difference is  due to
the  effect of   temperature on the  nitrification-
denitrification  design  and  is  not  related  to  the
phosphorus  removal design. Prior  to the Kelowna
plant  design, bench-scale  studies  showed  that  90
percent biological phosphorus removal  was possible
over a temperature  range from 18°C (64°F) down to
6°C (43°F) (78). The study did  exhibit a decreased
nitrogen removal efficiency below 10°C (50°F),
however.

The full-scale A/0 system operation demonstrated at
Pontiac,  Michigan,  revealed  that biological
phosphorus removal was not affected by wastewater
temperatures  as low as 10°C (50°F) (67). Biological
phosphorus removal was studied in laboratory batch
units  over a  temperature  range  of  5-15°C (41-
60 °F) by  Sell et al. (46). The amount of phosphorus
removed at 5°C (41 °F) vs. 15°C (60°F) was  greater
by more  than  40  percent.  The  improvement was
credited to a population  shift to more  slow growing
psychrophihc bacteria with  a higher  cell  yield.
Groenestijn  and Deinema  (69)  reported  that  the
phosphorus content of a pure culture of Acinetobacter
decreased from 10.1 percent  at 5°C (41 °F) to 1.4
percent at 35°C (95°F). An A/0 system operating at
a low organic  loading rate of 0.032  kg  COD/kg
MLSS/d  produced its  lowest  effluent  soluble
phosphorus  concentrations  of  0.9  mg/l  during  the
coldest  operating  month   when  wastewater
temperature  was  5°C  (41 °F).  The  phosphorus
content of the sludge was 4.7 percent compared to a
range of 3.5 to 4.9 percent for five other months (75).

3.3.5.7 pH
Two different laboratory experiments using synthetic
wastewater to evaluate the effect  of  pH have been
reported.  Groenestijn and Deinema (69)  studied the
effect of  pH  at a  wastewater  temperature  of 25 °C
(77°F) on the  maximum  specific  growth rate of a
strain of  Acinetobacter.  As shown  in Figure 3-11,
the  maximum specific growth  rate was  42 percent
higher at a pH of 8.5 compared to that at a pH of 7.0.
Below a pH of 7.0, a steady decline in the maximum
specific growth  rate occurred.  Below a pH of 6.0 the
organisms did not grow. Between  pH values of  6.5-
8.0, the phosphorus content of the culture remained
constant  at  about  6.0 percent. It increased to 7.5
percent  at  a pH  of 6.0.  Tracy and  Flammino  (74)
studied the effect of pH on the specific  phosphorus
uptake rate (g P/g VSS/hr) in the aerobic phase of an
anoxic-aerobic  lab reactor. Their results  are also
normalized  to a pH of  7.0 in Figure 3-11. They
claimed little difference in the phosphorus uptake rate
from a pH of 6.5 to a  pH of 7.0. Below a pH of 6.5,
the  phosphorus uptake rate declined steadily. They
further stated that all activity was lost at a pH of 5.2.
As  they  increased  the pH, they  claimed  that the
phosphorus uptake activity was essentially duplicated.

Nagashima et al. (79) found that  total   phosphorus
removal in the  Modified Bardenpho  process  was
improved  from  42 to 92  percent as the  pH  was
increased from  5 to 8. These results suggest that the
efficiency of biolgical phosphorus  removal may
decline significantly below a pH of 6.5.

3.3.5.8  DO  Concentration  in  the Phosphorus
Uptake Zone
No  specific studies have been reported that address
the effect  of the  DO concentration  on biological
phosphorus  removal. The biological  phosphorus
removal  mechanism  suggests  that  the  DO
concentration may  affect  the rate of phosphorus
uptake in  the aerobic zone, but not the  amount  of
phosphorus  removal possible,  provided that  sufficient
aerobic  time is available.  The mechanism teaches
that  the  oxidation  of  stored or  exogenous
carbonaceous  materials  produces  energy for the
incorporation of  soluble  phosphorus  into  cellular
polyphosphate  compounds. In the treatment  of an
acetate wastewater in  an  anaerobic-aerobic fill-
                                                 34

-------
Figure 3-11.  Reported effects of  pH on  biological
           phosphorus removal.
Ratio of Parameter Rate to the
Same Rate at pH = 7.0
    1.6 r
    1,2 -
                               Maximum Specific
                               Growth Rate (69)
                            Aerobic Zone Specific
                            Phosphorus Uptake
                            Rate (74)
                  6.5
7.0
pH
                               7.5
                                     8.8
                                            8.5
and-draw  system,  Fukase  et  al. (32) showed that
aerobic detention  times  required  for maximum
phosphorus uptake were  1-2  hours.  Tracy and
Flammino  (74) showed that 80 minutes was required
for the A/0  process treating a municipal wastewater
and  160  minutes  for  treating  a municipal-food
processing wastewater combination.
Miyamoto-Mills  et al.  (38)  obtained effluent  total
phophorus concentrations below 1 mg/l in a Phostrip
system pilot-plant  study  with the  aerobic  stage
operating at DO concentrations of either 2.5  or 0.5
mg/l.  The lower DO concentration was set to  limit
nitrification  during  the study. At the  higher   DO
concentration,  the  system  was  operated  with
nitrification occurring.
Ekama ef al.  (80)  state that  biological phosphorus
removal  will be  adversely affected  in  biological
combined nitrogen and phosphorus removal systems
unless the  DO concentration  in  the aerobic zone
remains  1.5-3.0 mg/l.  If the DO  is too  low,  they
claim that phosphorus  removal may  be reduced,
nitrification will be limited,  and  a poor settling sludge
may  be  developed.  If  too  high, denitrification
performance could be limited due to the increase in
DO  recycled to the first  anoxic zone. A resultant
higher nitrate nitrogen concentration could then affect
the phosphorus release performance of  the anaerobic
zone.
3.3.5.9 Anaerobic Fermentator Zone
Considerations
The  anaerobic  zone  contact time  for Modified
Bardenpho  and  A/0 systems  has ranged from  0.9
hour for the Largo  A/O facility  to  2.0 hours  for
Modified  Bardenpho facilities  at the  Payson and
Kelowna  plants.  Early  full-scale plant investigations
at Palmetto, Florida,  found  that  increasing  the
anaerobic detention time  from  1.1  to  2.6  hours
increased the percent total phosphorus removal from
59 to  71 percent  (16).  In a Bardenpho pilot-plant
study,  McLaren  and Wood  (81)   found  that  the
effluent soluble  phosphorus concentration decreased
from 3 to less than 1 mg/l as the anaerobic detention
time was doubled from 2 to 4 hours. However, after
establishing removal at  the 4-hour detention time, an
effluent soluble phosphorus concentration of less than
1 mg/l  was maintained  under variable anaerobic
detention times.  During investigations using  an A/O
pilot plant  at the  Saint Mars La  Jaille,  France
wastewater facility, the anaerobic contact zone mixers
were  periodically turned off  during  the day and
improved phosphorus  removal was  reported (75).
With the mixers off,  improved  performance was
attributed to a greater SDT.  In  these cases, it appears
that the longer  contact  time results  in  the
fermentation of particulates or  materials that are more
slowly converted to fatty acids. The necessity for and
success  of longer anaerobic contact times may vary
depending  on   the  strength  and  nature  of  the
wastewater.  Methods to  increase the production of
fatty acids to improve biological phosphorus  removal
performance will  be discussed in Section 3.6.

Another  important  aspect  of  anaerobic contactor
design and  performance is to limit  the  amount of
oxygen  entering the  zone.  Any  DO present  will
deplete readily-available  substrate and thus  reduce
the amount  of fatty acids that will be produced for
biological phosphorus  removal.  The  presence  of
excess  DO was  identified as  causing  poor
performance for biological phosphorus removal at  a
number  of  full-scale South African  facilities (57).
This was also suspected, in combination with a weak
wastewater, of causing  poor phosphorus removal  and
filamentous  sludge  growth  during a portion of  the
operating period of a  U.S.  Modified   Bardenpho
system (65). Possible sources of high DO input to the
anaerobic  zone have  included  high influent  DO
concentrations  in the  wastewater associated with
infiltration, the use of  Archimedes screw pumps for
the return  sludge or  influent feed,  cascading  of
wastewater through  the  influent  channel flow
measurement or grit removal  systems, and  vortices
created by  stirrers  in  the  anaerobic basins.  Such
conditions should be avoided as much as possible in
the design of biological phosphorus removal  systems
using the anaerobic fermentation step.

Anaerobic fermentation  zones  have been designed as
single-stage, complete  mixed  basins or three to four
                                                 35

-------
basins in series  as in the  A/O process designs.
Experiments by Ekama et al.  (30) support a multiple-
stage design. They claimed improved  phosphorus
release  and  improved  phosphorus removal  for  a
multiple-stage system  compared to a  single-stage
fermentation  reactor  operation.  They  explain  this
difference by a model that  describes fermentation of
readily-available substrate  as a  first-order reaction.


3.4 Equipment Requirements
Three major areas of equipment  requirements for the
Phostrip  system are the stripper tank, the lime feed
system,  and  the  chemical  precipitation  tank.  Piping
and necessary pumping designs are also required to
route  a portion of the return sludge to the stripper, to
provide  elutriant to the  stripper,  to  transport stripper
underflow sludge  to the aeration basin,  to convey
stripper  overflow to the chemical treatment unit, and
to feed lime to the chemical treatment step.

Stripper  tanks are typically sludge  thickening  tanks
with  modifications for  sludge inventory control and
elutriation.  The tank  has  a  center  well  for sludge
feeding,  a  scum  baffle and overflow weir, a sludge
rake mechanism,  and sludge  blanket level indicators.
Underflow  solids  density  probes  have also  been
recommended by the Phostrip process supplier.

The  lime feed system  will  normally include a  lime
storage  tank, a slaking operation, and a  lime  slurry
feed and control system. Mixing of  the lime  with the
stripper supernatant may be  accomplished by  using
static in-line  mixers or  a  flash mix  chamber with a
mechanical  stirrer. The flash mix  chamber  should
have  about a 1-minute  detention  time.

The chemical treatment units in the Phostrip process
are typically  solids  contact  units.  In  these   units,
relatively large,  cone-shaped  skirts  form  mixing
zones in the center of  the circular  tanks to  promote
flocculation. With  lime treatment,  previously
precipitated solids provide  a  seed  for  newly formed
precipitates and floe growth.  Heavier floe solids that
fall out of the mixed zone settle out  in the clarification
area below and around the skirt. A raking mechanism
is used to move settled solids to a  center withdrawal
point.

Equipment requirements for the mainstream biological
phosphorus removal  system   are minimal  and
relatively simple.  Mixers are  needed to suspend  the
mixed liquor solids in  the anaerobic and/or  anoxic
zones of the various  designs.  Such  mixers  have
typically been designed with  an energy input per unit
volume of  about  10 W/m3 (0.4  hp/1,000  ft3).  Lower
values  than this  may be  desirable  to minimize
induced air  entrainment by  the mixers  (57). Anti-
vortex baffles are  also used for this  purpose. Internal
recycle  of sludge to  anoxic or  anaerobic zones is
accomplished with low head,  high capacity pumps.
3.5 Design Methodology

3.5.1 Phostrip Process
The  major design considerations  for  the Phostrip
process are the size of the stripper and  solids contact
tanks and the lime feed rate. The size of the solids
contact  tank  will  be  a function of the stripper tank
supernatant overflow  rate. This will  be determined by
the return sludge feed rate to the stripper, the degree
of solids thickening achieved, and the elutriation rate
if the elutriant is composed of an outside flow  instead
of recycled stripper sludge. The lime feed rate will be
affected by  the   stripper  tank  supernatant
characteristics,  which impact  the ability to raise the
pH for  phosphorus  precipitation,  as well as the
stripper  tank supernatant overflow rate. Typical values
for stripper and reactor-clarifier design  were given  in
Table 3-2.

The  stripper design  procedure involves the following
steps:

1. Determine  or select the amount  of  return sludge
   that will pass through the stripper.

2. Select the stripper underflow sludge concentration.

3. Select the stripper SDT.

4. Based  on  the above,  calculate  the  volume  of
   sludge necessary in the stripper.

5. Using a solids flux analysis  (82)  or  appropriate
   solids  loadings,  calculate the  stripper  area
   requirements.

6. Using information  from  steps  4  and 5, determine
   the sludge depth in the stripper.

7. Provide a  selected supernatant  water  depth  to
   obtain  the total  stripper  sidewater  depth.  A
   supernatant water depth of  1.5 m (5 ft) has been
   recommended  (77). The  stripper depth  may  be
   increased  to  provide additional sludge  inventory
   and operating flexibility.

The  amount of the return sludge passing  through the
stripper is usually selected based on pilot-plant work
or previous  full-scale plant  operating information.
Another approach, presented by Peirano  et. al. (77),
was  developed  from  plant-scale  Phostrip
performance   testing  at  Reno-Sparks.  The
phosphorus  removal  efficiency was correlated with
three main  operating parameters:  the  amount  of
return sludge passing through the stripper relative to
the  plant flow,  the  stripper  SDT,  and the  stripper
supernatant flow. The correlation developed  can  be
expressed as follows:

   1.85  - [log (100 -  E)]/2.11  =  (SL x  D)1/2 (SU)
                                           (3-1)
                                                  36

-------
where,

   E   = percent phosphorus removal
   SL  = return sludge passing through stripper tank,
         100 Ib dry  solids/mil  gal  of system influent
         flow
   D   = SDT, hr
   SU  = stripper supernatant flow  as ratio of influent
         flow

This relationship indicates that  phosphorus removal is
affected  by the solids loading to the stripper and  the
stripper  SDT. The following example  illustrates  the
design procedure.

Wastewater and Plant Design Assumptions:

Influent flow =  10,000 m3/d  (2.6  rngd)
Primary effluent TBOD = 120 mg/l
Primary effluent TP = 8 mg/l
Activated sludge recycle flow rate as percentage
    of influent flow rate = 80 percent
Activated sludge recycle solids
    concentration = 6,000 mg/l

Stripper Design Assumptions:

SDT = 10 hr
Underflow solids concentration  = 9,000 mg/l
Return sludge flow rate to stripper
    as percentage  of influent flow rate = 25 percent

Design Steps:

1.  Return sludge flow rate to stripper:

   0.25 (10,000 m3/d) = 2,500 m3/d

   Recycle sludge  passed through stripper:

   (0.25/0.8) x 100 = 31 percent   (based  on  total
                                 return sludge flow
                                 rate)

2.  Stripper underflow solids
   concentration = 9,000 mg/l

3.  Stripper SDT =  10 hr

4.  Stripper sludge  volume produced/day (i.e., stripper
   underflow rate):

   (2,500 m3/d) (6,000 mg/l -f 9,000 mg/l)
    =  1,667m3/d

   Net  stripper tank sludge volume:

   (1,667 m3/d  -f 0.8 ) (10 hr) (d/24 hr)=  868 m3
                                      (30,650 ft3)
  This net estimate of stripper  tank  sludge volume
  required is based on the  stripper underflow solids
  rate (or concentration) and an assumed density
  factor  of  0.8  to  account for  the  possibility of a
  lower  thickened sludge  concentration due  to
  variations in the stripper operation.

5. Solids loading to stripper:

  (6,000 mg/l) (2,500 m3/d) (0.001 kg/mg)
        = 15,000 kg/d (33,070 Ib/d)

  Assume allowable solids  flux   rate  for 9,000-mg/l
  underflow solids concentration  = 50 kg/m2/d

  Stripper area req'd   =  15,000  kg/d -r  50 kg/m2/d
                      =  300 m2 (3,230 ft2)

  Overflow rate   = (2500 m3/d * 300 m2)(d/24 hr)
                 = 0.35 m/hr (205 gpd/ft2)

6. Stripper sludge depth:

  868 m3 * 300 m2 =  2.9 m (9.6 ft)

7. Minimum stripper depth:

  1.5 m  + 2.9 m  = 4.4m (14ft.)

  [use total stripper depth of 5.5  m (18 ft) for added
  inventory flexibility]

8. Supernatant  flow  assuming   primary  effluent
  elutriation at 50 percent of stripper feed flow:

  (2,500 m3/d)(0.50)
     + (2,500 m3/d)[1  -  (6,000 mg/l 4 9,000 mg/l)]
   = 2,083 m3/d

9. Solids contact unit for lime precipitation:

  Assume:  Overflow rate = 49 m3/m2/d
            Area   = 2,083 m3/d  •=• 49 m3/m2/d
                   = 42.5 rn2
            Diameter =  7.4 m (24 ft)

  Lime feed at dose of 200 mg/l:

  (2,083 m3/d) (200 mg/l)  (0.001)  =417 kg/d
                                 (919 Ib/d)

10.  Check phosphorus removal; use  phosphorus
    release in stripper of 0.01 g P/g VSS  (see Table
    3-2);  assume 70 percent volatile solids:

  (15,000 kg/d) (0.70) (0.01 g/g)  = 105 kg/d
                                 (236 Ib/d)

  Phosphorus  removed  by stripper  supernatant
  treatment:
                                                  37

-------
  (105 kg/d x 2,083 m3/d)  -5- [2,500 m3/d  +  2,500
  m3/d (0.5)] = 58.3 kg/d (126 Ib/d)

11.  Determine phosphorus content of waste sludge:

  Total  phosphorus  in influent  to  activated sludge
  system:

  (10,000 m3/d)(8 mg/l) (0.001) = 80 kg/d (176 Ib/d)

  Assume TP in effluent = 0.5 mg/l

  Phosphorus in activated sludge waste solids:

  (80 -  58.3) kg/d - 0.5 mg/l (10,000  rr»3/d) (0.001)
    = 16.7 kg/d (37 Ib/d)

  Assume  net sludge yield  for biological system
  following primary treatment  =  0.55 g TSS/g  TBOD
  removed

  TBOD removed  = 120 mg/l - 10 mg/l  = 110 mg/l

  Net sludge produced

    = (110 mg/l) (0.55 g/g) (10,000 m3/d) (0.001)
    = 605 kg/d (1,334 Ib/d)

  P in waste sludge

    = (16.7 kg/d -f  605 kg/d)  x 100 =  2.8 percent

  This is a  relatively low sludge  phosphorus content
  compared  to mainstream  biological phosphorus
  removal systems.

3.5.2 Mainstream Biological  Phosphorus Removal
Processes
A  variety  of  process configurations have  been
presented  for  mainstream  biological phosphorus
removal.  While  the  aerobic zones may be designed
for  different treatment  objectives  or the internal
recycle  and nitrate reduction   schemes  may  be
different, there are common design  considerations
that  apply  to  all  of these  systems. These
considerations include the  design of  the  anaerobic
zone, the need for  sufficient time  and DO  in the
aerobic zone, the denitrification  reactor design when
needed, and  sludge handling.  Another  major
consideration is the effluent phosphorus level that can
be  achieved and  whether  chemical addition  and/or
effluent  filtration  is necessary  to  meet  required
treatment  levels.  In  many  cases,  pilot-plant  or
bench-scale studies  should be recommended to
determine  the  final design  since  treatment
performance is very sensitive to individual wastewater
characteristics.

The anaerobic zone contact time is presently  based
on  pilot-plant studies or previous  experience  and
has ranged from  0.9 to  2.0 hours. Staging  of the
anaerobic  zone  should  theoretically decrease the
required detention time for the fermentation of soluble
organics. This has to be balanced against the higher
cost for an increased number of mixers and the use
of more divider  walls. A DO concentration of greater
than 2.0 mg/l   is commonly  recommended in the
aerobic zone. The size of the aerobic zone should be
kept as  small  as  is  consistent with  the  overall
treatment  objective  of maximizing  phosphorus
removal. Sufficient  aerobic  time  is  needed for
phosphorus uptake.

Waste  sludge  from biological  phosphorus  removal
systems  is  handled  in  a  manner  to  minimize any
recycle of released phosphorus back to the activated
sludge  system.  As gravity thickening normally results
in substantial release of phosphorus from the sludge,
dissolved air flotation thickening has been used where
sludge  thickening  is  needed. Provisions  may  be
required to chemically treat any recycle  streams from
digestion of  the phosphorus laden sludge.  As solids
are lysed and  destroyed  in aerobic  digestion,  a
proportional amount of phosphorus is released to the
liquor.  The  same phenomenon  is expected with
anaerobic digestion, but the Pontiac, Michigan  study
(67) did not note significant levels of phosphorus  in
the  digester   supernatant.  An   ammonium-
magnesium-phosphate precipitate  may  have formed
in the digester, and further  studies are needed in this
area.

3.5.2.1  Sludge Production
No significant  differences  in  sludge  production  for
biological phosphorus removal systems compared  to
typical  sludge  yield values  are reported  in the
literature for the  operating  conditions  employed.
However, if mixed liquor solids are capable of storing
phosphorus, some increase in net sludge yield should
be  expected. To calculate  the increase, an estimate
of the mass of  the associated chemical constiutents
is needed.  This  may  be  approximated  from the
constiutents reported in solution  during phosphorus
release  (Section 3.1.1).  Table 3-14  summarizes the
total expected stored mass/unit of phosphorus stored.

The following  example  illustrates the  increase  in
sludge  mass associated with biological phosphorus
removal:

Assume:

   Net solids yield = 0.70 g TSS/g TBOD removed
   Normal phosphorus content = 2 percent
   Biological phosphorus removal raises the
    phosphorus content in the dry solids to 4 percent

Calculate:

   Solids yield/100 mg TBOD removed = 70 mg
   Normal P removed/100 mg TBOD removed
    = 0.02(70) = 1.4mg
                                                 38

-------
Table 3-14.  Approximated Mass of  Phosphorus Storage
           Compounds.
function of the net sludge production, the phosphorus
content  of  the  sludge,  and  the  amount of BOD
removed. This is shown as follows:
Constituent
Mg
K
Ca
O
P
Total
Molecular
Weight
24.3
39.1
40
16
31

Mole per
Mole of P
0.28
0.20
0.09
4
1

g/gP
0.22
0.25
0.12
2.06
1.0
3.65
  PB   = additional P removed by biological
           phosphorus removal

      (1.4  +  PB) -5- (70 + 3.65 PB)  = 0.04

  PB = 1.64 mg/100 mg TBOD removed

  Amount of  sludge  produced  with biological
  phosphorus removal/100 mg TBOD removed:

    70 + 3.65 (1.64) = 76 mg

  Ratio  of biological  phosphorus  process  sludge
  production  to  conventional  process  sludge
  production:

    76/70 = 1.085

The sludge yield increased by  8.5 percent for  this
example. If the  phosphorus content of the waste
sludge increased to 5 percent,  the net sludge yield
increase is estimated to be  13 percent. Thus, an
increase in the mass of waste solids is expected for
biological phosphorus removal systems. However, the
overall  impact  on  sludge handling  may  not  be
negative due  to  the excellent  sludge  thickening  and
dewatering characteristics  reported  for  these
systems. Mixed  liquuor SVI values generally less than
80  ml/g have been  reported for Modified Bardenpho
and A/O systems (12,16,29).

3.5.2.2 Phosphorus Removal Efficiency
In  the  absence  of  bench-scale  or  pilot-plant
studies, estimates of biological  phosphorus  removal
efficiency can be made to determine if chemical
addition and/or filtration  may be necessary to meet
the  effluent requirement. The  selection of  filtration
during the design phase may also be affected by the
assumed  secondary  clarification efficiency.  If an
effluent  TSS  concentration  of less than 10-12  mg/l
must be attained  to  achieve an  effluent total
phosphorus concentration of  less  than 1  mg/l,
filtration would generally be required.

The amount of phosphorus that may be removed  in  a
biological phosphorus  removal system  will  be  a
                                                                 (Yn) (Fp)  = DP/DBOD
                                          (3-2)
                                                    where,
  Yn        = net solids  yield,  g TSS/g  TBOD
              removed
  Fp        = fraction of P in dry solids, g P g TSS
  DP/DBOD = total phosphorus  removed/unit  of
              TBOD removed, g TP/g TBOD

The  net  solids yield is  a function  of  the system
operating SRT  value  and  influent   wastewater
characteristics. The use of primary treatment will also
lower the net solids yield since much of the  influent
inert solids will be removed  during primary settling.
The fraction of phosphorus in the solids has been
shown  to be  quite variable  depending  on influent
wastewater characteristics and operating conditions.
A value  for Fp can  be selected based on  results
reported  for other  facilities. Figure 3-12 shows  the
TBOD:TP removal ratio as a function of SRT and an
assumed Fp  value of 0.05  for a  system with  no
primary  treatment  (83).  The net  solids  yield as  a
function of SRT  was taken from a  curve  given  for
municipal  wastewaters  in  WPCF MOP 8  (84). A
system with primary treatment would have a lower Yn
but  a higher Fp value since less inert material would
be contained in the mixed liquor solids.

Example:

Assume:

  Fp =  0.05 g P/g TSS
  Influent TBOD  = 160 mg/l
  Influent TP = 7.5 mg/l
  Influent TBOD:TP = 21.3
  Effluent TSS =  12 mg/l
  Effluent TBOD = 5 mg/l
  No primary treatment
  T  =  20°C

Calculate:

  Design SRT, days     5        10       20
  Yn (MOP 8), g/g       0.92      0.81      0.70
  DP/DBOD (Eq. 3-2)    0.046     0.041     0.035
  DBOD, mg/l        155       155      155
  DP, mg/l             7.1        6.4       5.4
  Eff. SP
    (7.5 - DP), mg/l     0.4       1.1       2.1
  Eff. part. P, mg/l       0.6       0.6       0.6
  Eff. TP, mg/l          1.0       1.7       2.7
  TP removal, percent  87        77       64

The  above example  shows  the  effect  of  SRT  on
estimated total phosphorus removal efficiency. If  an
                                                39

-------
Figure 3-12.  TBOD:TP removal vs.  solids retention time
           (SRT).
    TBOD:TP

     35 i—
     30
     25
     20
     15
                       Fp = 0.05 g P/g TSS (assumed)
                          I
                          10
                       SRT, days
                                   15
                                            20
effluent total phosphorus concentration of 1.0  mg/l is
required,  the 5-day  SRT operation  may  meet
performance standards without  chemical addition or
filtration. The longer SRT operating  systems  would
require chemical addition  to further  reduce effluent
soluble phosphorus concentrations. The example is
based on  a  relatively  low influent TBOD:TP  ratio
compared to some of the ratios  observed in the plant
performance  section.  However, the  ratio used is
within the  range  of values that  can be  expected for
some domestic wastewaters (82).

The  effect  of nitrate nitrogen  can be estimated  by
calculating  the  reduction  in available BOD  due to
dentrification.

Assume:

   Effective  nitrate  nitrogen concentration  to
   anaerobic zone  = 5 mg/l after  mixing  of  recycle
   sludge and influent.

TBOD consumed for denitrification:

   (4 mg TBOD/mg NOa-N) (5  mg/l)  = 20 mg/l

 For SRT  =  5  days,  remaining influent TBOD (i.e.,
 TBOD available for biological phosphorus removal)
     = 160 mg/l  -  20 mg/l  = 140  mg/l

 DBOD =  140 mg/l - 5 mg/l  =   135 mg/l

 DP = 0.046 (135 mg/l) =  6.2 mg/l

 Effluent SP  = 7.5 mg/l  - 6.2 mg/l
             = 1.3 mg/l vs. 0.4 mg/l previously
Thus, for She low influent TBOD:TP ratio used for this
example, nitrification and the presence of nitrates in
the return sludge could significantly affect the effluent
soluble and total phosphorus concentrations.

3.5.2-3 iJ|t??t.e Mitrogsn Rernov?! Design
Figure   3-13  illustrates  the two  modes   of
denitrification operation used in biological phosphorus
removal systems. Nitrified  mixed liquor is recycled to
a pre-denitrification  ?one in the Modified  Bardenpho
process and also in  ihe A/O process when nitrification
occurs.  The recycle ratio is generally  in the range of
4:1 based on  the  influent flow. In  this  zone,  the
incoming  substrate  drives  the denitrification reaction
as  the  facultative  organisms  use  nitrate-released
oxygen  as the  electron acceptor in lieu of  DO. The
oxygen  equivalent of the nitrate radical is 2.86 g O2/g
NOa-N.   The Modified  Bardenpho  process  has  a
second  enoxic  tank, or post-denitrification  zone, in
addition to the  pre-denitrification zone. In the second
anoxic zone, the  denitrification rate is driven  by the
endogenous respiration  oxygen demand of the mixed
liquor since the influent  substrate is depleted after the
nitrification step.

The  design objectives for  biological phosphorus
removal systems incorporating  denitrification  are to
first determine the amount  of nitrate nitrogen entering
the pre-denitrification and  post-denitrification  zones
and (hen  to determine the  volume  of the  anoxic
zones.  A critical  design aspect is the mixed liquor
denitnficfition ie>to occurring  in  each type of  anoxic
zone. A  design  approach for  denitrification  will  be
bnefiy presented  here, since nitrate reduction can be
an important consideration in  biological phosphorus
removal systems.

The first step  in the design is the  preparation of  a
mass balance  to  determine the amount ot  influent
nitrogen that will  be oxidized to nitrate  nitrogen.  It is
generally assumed  that the  distribution  of influent
nitrogen  is to  nitrate  nitrogen,  effluent  ammonium
nitrogen, and solids synthesis:
NO
                     ;.> - NHe - N
                               syn
(3-3)
   NO  ™ amount of  influent nitrogen converted  to
          oxidized nitrogen, rng/l
   N0  - influent total nitrogen, mg/l
   NHe " effluent ammonium nitrogen, mg/l
   Npyn - smount of influent nitrogen used  in solids
          synthe?is, mg/l

 The  amount  of  nitrogen used  in  synthesis  can  be
 estimated from the amount of BOD removed, the net
 solids yield as a function of SRT, and the nitrogen
 content of Ihe mixed  liquor. The  nitrogen content of
 becteria is 10-12  percent,  but a  lower value  will
 f'-p"~- -Uy l-e- me^'Torl 'f"-r mixed liquor solids because
                                                   40

-------
Figure 3-13.  Pre-denitrification and post-denitrification schemes in biological phosphorus removal systems.
Q,S0,N0 ^
i
t
i
Anaerobic
nii '»
r
Pre-
Denitrification
>• 	
Anoxic 1
Ne
Nitrification
N
-> —
Return Sludge
(from Sec. Clanfier)


•^ 	 Bardenpho Addition 	 >
Posl-
Denitrification
> 	
Anoxic 2
V2
Aerobic
>
Or to Clanfier
To Clanfier


of the presence  of  inerts  and non-biological  solids.
Values of 5-8 percent may be more  appropriate:
              Nsyn  = Yn (DBOD) Fn
                                     (3-4)
where,
   Fn   = fraction  of nitrogen in mixed liquor solids,
          9/9

Once NO is determined, the next step is to perform a
mass balance describing the  distribution of the nitrate
produced in the nitrification zone,  which results in the
following:
               N =  NO/(R +  r +  1)
                                     (3-5)
where,

   N

   R

   r
= nitrate  nitrogen  concentration  in  the
  nitrification zone, mg/l
= ratio of internal recycle flow (to  the pre-
  denitrification zone) to influent flow
= ratio of return sludge flow to influent flow
Equation 3-5 is applicable to both A/0 and Modified
Bardenpho system designs.  The  rate of  nitrate
nitrogen addition to either denitrification zone  can  be
calculated  once  the value of N  is determined. The
design  approach assumes that  all  of  the  nitrate
nitrogen entering the  anoxic  zones  is  completely
reduced even  though a  residual  nitrate  nitrogen
concentration  of 0.3-0.5 mg/l may exist. The  volume
of the denitrification zones is then determined based
on the  amount  of nitrate  nitrogen entering  the zone
and the specific denitrification rate:

Anoxic  1  Volume (applies to both A/0 and Modified
Bardenpho):
                                     (3-6)
                                     (3-7)
             V! =  RQN/[(X)

Anoxic 2 Volume (Modified Bardenpho)

         V2  = [{1  + r) NQ]/[(X) (SDNR2)]
where,

  Vi      = volume  of pre-denitrification zone, m3
  \/2      = volume  of post-denitrification zone, m3
  Q      = influent flow, m3/d
  X      = MLSS concentration, mg/l
  SDNRi = specific denitrification rate  in  pre-
            denitrification zone, g NOs-N/g X/d.
  SDNR2 = specific  denitrification  rate in  post-
            denitrification zone, g NOa-N/g X/d.

The SDNR  has  been predicted from  the specific
oxygen uptake rate as follows:
                                                                   SDNR  = Fd SOUR/2.86
                                                                                           (3-8)
                                                      where,
   Fd     = fraction of  substrate reaction rate when
            nitrogen-released  oxygen   is  the
            electron  acceptor  vs.  when  DO is the
            electron acceptor, g/g.
   SOUR  = specific  oxygen  uptake  rate,  g  02/g
            TSS/d

Previous investigators have found  values  for  F^ of
0.41-0.55 for systems in which the mixed liquor was
subject to  both aerobic and anoxic  conditions (85-
87).  The  reduced  reaction  rate  during  nitrate
reduction is attributed to the possibility that the entire
biological population cannot use nitrate as an electron
acceptor in the absence of DO, and that the  biological
reaction rate  may  be  slower  when  nitrate is the
electron acceptor.

With  this  approach,  good  agreement  has  been
observed for pre-denitrification  SDNR reaction  rates
predicted from  treatment of a tannery wastewater in
the  presence of plentiful substrate  (87) and  post-
denitrification  SDNR  reaction rates predicted  from
endogenous respiration  for domestic wastewater with
limited available substrate (85).  The SDNR prediction
for pre-denitrification  with domestic wastewater has
not been  demonstrated and is limited by  unknown
reaction rates  for paniculate and  soluble  BOD. An
                                                   41

-------
SDNR  relationship based  on the  F/M loading to  the
pre-denitrification zone  has been demonstrated  for
piiot- and  full-scale  plant  data (64):
SDNR,  = 0.03 (F/M)!  + 0.029

            = QSo/XVt
                                          (3-9)

                                         (3-10)
where,
  (F/M)i = food-to-mass   loading  in   pre-
          demtrification zone, g TBOD/g MLSS/d
  S0     = influent TBOD, mg/l

The (F/M) | value can  be  calculated for staged  or
completely mixed  pre-denitrification  zone  as a
function of the volume (Vi ) selected for the zone.
The  SDNR for the  post-denitrification  zone can be
calculated as follows using an F
-------
  Predicted SDNRi  = 0.03 (0.57) + 0.029
                   = 0.046 g NOa-N/g TSS/d

  OK - Assumed SDNRi lower than predicted

  Try: V!  =  800 m3

  Assumed SDNRi  = 40  •=- 800
                   = 0.05 g NOa-N/g TSS/d

  (F/M)i    = 571.4 -5- 800
           = 0.71 g TBOD/g MLSS/d

  Predicted SDNR!  = 0.03(0.71) + 0.029
                   = 0.05 g NOa-N/g TSS/d
                         -  OK
       =  (800 m3 * 10,000 m3/d)(24 hr/d)
       =  1.92hr
Step 3: Determine \/2  using  Equations 3-7 and 3-
12.

   V2 =  [(1 + 1)(3.5mg/l)(1 0,000 m3/d)]
       4- [(3,500 mg/l)(SDNR2)]
      =  20/SDNR2

   SDNR2  = 0.175 (1.25 g/g^0.70 g/g)(!/20 d)
           = 0.0156 g NOa-N/g TSS/d

   V2  = 20 4- 0.0156 = 1,280 m3

   V2/Q  = (1,280m3  -f 1 0,000 m3/d)(24 hr/d)
         = 3.1 hr

The design procedure should  also check  the
TBOD:NO ratio to determine  that there is sufficient
TBOD available for the amount of nitrate nitrogen to
be reduced. A ratio of  at least 4:1 is recommended.
In this case, there  is  sufficient TBOD available for
denitrification.
3.6  Process  Modifications  to  Improve
Performance

The  major  performance  limitation  of  biological
phosphorus removal systems is the amount of volatile
fatty  acids  available relative  to  the amount  of
phosphorus  that  must  be  removed  by the
phosphorus-storing microoganisms. As described in
Section  3.3.5.3,  wastewaters  with  lower  influent
BOD-to-phosphorus  ratios  may  not produce  a
sufficient level  of volatile  fatty  acids  (VFAs)  in the
fermentation zone  to fully trigger  the  biological
phosphorus  removal   mechanisms.  In  some
installations, it has been  necessary to add chemicals
to reduce the effluent total phosphorus concentration
to discharge requirement  levels. Another means of
improving performance is to increase the  amount of
VFAs available to the microorganisms.
It is generally accepted that the major contribution of
VFAs  produced in mainstream biological phosphorus
removal systems is from readily-degradable  soluble
BOD  entering  the  fermentation  zone.  For  many
wastewaters this may only  represent 30-60 percent
of the influent  TBOD. Osborn  and  Nicholls  (15),
suspecting  that VFAs were important substrates for
biological phosphorus removal,  operated  a primary
sludge treatment  digester at a  high loading  to
encourage  only acid fermentation.  The fermentated
sludge was then  fed to the  anaerobic  zone  of  a
Modified Bardenpho system. The phosphorus removal
was excellent, but the sludge  addition  increased the
aeration energy requirements of the plant.  Eventually
methane fermentation developed in the digester and
phosphorus removal efficiency declined.

Oldham and Stevens  (62) presented data showing the
benefits  of  using  primary  sludge  fermentation
products at the Kelowna Modified Bardenpho facility.
The primary  sludge  at this facility is  directed to  a
gravity thickener where it is held long enough for acid
fermentation to develop. The  thickened sludge was
passed through a 2.5-mm  screen,  and the screened
liquid  containing fine  solids was directed to the plant
fermentation  zones.  The fermentation stream was
alternately  directed  to both  and   one of the two
modules to compare  performance  with and  without
the fermentation product addition.  When  added  to
both  modules, the  effluent soluble phosphorus
concentration was  generally below 0.5 mg/l. During
the alternating  operation, the module receiving the
fermenter  liquor  immediately exhibited   a  higher
degree of  phosphorus release  in  the fermentation
zone  and effluent soluble phosphorus concentrations
well below 0.5 mg/l within about 3  days. The module
not receiving the  fermenter liquor produced  effluent
soluble phosphorus concentrations  generally between
2  and  3  mg/l.  During  these  tests,   the  VFA
concentration of the  thickener  liquor  was 110-140
mg/l.  Since the fermenter liquor flow  rate was only
8-10  percent of the influent flow rate, the  increased
VFA concentration  in the influent was 9-10 mg/l. The
sludge depth of the thickener was later increased to
promote additional solids  detention time  and VFA
production. The VFA  concentration of the  fermenter
liquor increased  to  200-300  mg/l,  but  this was
followed  by a decline  in  phosphorus removal
efficiency.  The pH  of  the thickener liquor also
decreased. Barnard (88)  postulated  that the lower pH
resulted in fermentation products that were not readily
available to the phosphorus-storing  microorganisms.
Rabmowitz and Oldham  (89) carried  out  UCT pilot-
plant  studies  that were  also fed settled  supernatant
from  primary sludge  fermentation.  The sludge was
fermented in  a two-stage, completely  mixed reactor
followed by a clarifier for solids separation and sludge
return to   the  first-stage  sludge  fermenter. The
settled liquid contained  VFAs in the range of 150-
185 mg/l. The phosphorus removal  in two  sets of
experiments increased by 100 percent and  47 percent
                                                43

-------
after  the  fermented  liquid  addition.  The  VFA
production  averaged 0,09 mg/mg COD applied to the
fermenter.

Figure 3-15  shows possible  design  schemes  for
primary sludge fermentation. The first  is termed the
activated primary sedimentation tank by Barnard (90).
The recycling of thickened fermented solids serves a
number of  purposes. First, it provides mixing of the
newly settled solids with the fermentation  organisms.
The  acids  produced  in  the  thickener are also
elutriated in the primary tank and then directed to the
activated  sludge  process. In  this  way,  primary
treatment is also used to decrease the loading to the
secondary   treatment step and  the size  of  the
activated sludge system. Another advantage  claimed
by Barnard  is that  the  pH  of  the  solids  in the
fermenter   is  better  buffered,  resulting  in  the
production  of  the  preferred   VFAs.  The
settler/thickener (deep tank) design  can accomplish
the same   objectives as  the activated  primary
sedimentation tank.  Deep  tank  designs have  been
used   previously  to  provide both  settling  and
thickening.  Rabinowitz (34) proposed a design similar
to the activated primary sedimentation tank,  but the
pumping rate out of  the thickener  is controlled  to
maintain the desired  sludge detention  time  for
fermentation.
3.7  Retrofit Considerations
The  sidestream treatment feature of the  Phostrip
process  makes it  readily  adaptable  for  retrofitting
existing facilities.  Separate tankage and  piping  are
added to strip phosphorus from a portion of the return
sludge,  return  the stripped sludge to the  activated
sludge system, and lime  treat the supernatant from
the stripper tank.  The design features for  retrofitting
are thus similar to  the design aspects discussed for a
new facility. The source of the elutriant flow and  the
organic loading to the  activated sludge  system  are
important  design  considerations. An elutriant source
that  is high in  nitrates  will  require a longer stripper
solids detention time  and could  negatively impact
stripper  performance.  Activated   sludge  systems
operated  at  longer  SRTs will  have a  less  active
sludge, which can impact the stripper detention time
and/or performance.  For  example,  the  Phostrip
process has not  been  applied to  systems  operating
with an extended  aeration  sludge  age. As  discussed
in Chapter  5,  additional sludge resulting  from  lime
treatment  of the  stripper  supernatant  must   be
considered.

For mainstream retrofit alternatives, the design choice
could be  an operationally  modified activated sludge
system,  an A/O  system,  or  a Modified  Bardenpho
system. In all three cases, an anaerobic fermentation
zone must be  provided  at the  head end of  the
activated  sludge facility. The  retrofit design involves
determining the volume  requirements of the anaerobic
Figure 3-15.  Primary sludge fermentation design schemes.

   Influent
               I
             Primary
             Settling
Primary
Effluent
                                 Thickener/
                                 Fermenter
             Supernatant


                                      ' Waste Sludge
          Fermented_ Sludge_Recy_cl_e	^ tto digester)


         Activated Primary Sedimentation Scheme
     Influent
+





1
T
Primary
Settling
(deep
tank)
k Primary
Effluent




 Fermented Sludge Recycle
                                 Waste Sludge
                                 (to digester)
               Settlern'hickener Scheme
zones and  anoxic zones where used. Some or all of
the additional volume requirements may be available
in the existing plant tankage or they may have to be
added. In the  latter case,  the hydraulic and physical
arrangements of the specific  plant will be  a factor in
selecting the most economical modification.

Excess  tank volume may  be available for  retrofitting
for the following reasons:

1. The plant is  underloaded,  and anticipated future
   loading increases are less than originally expected.

2. The  better  SVI  associated  with  biological
   phosphorus removal will allow operation with  a
   much  higher MLSS concentration than the present
   operation.

3. The system operating SRT can be reduced  from
   the original design without a loss in effluent quality.
   A lower  SRT value has been shown to improve the
   performance  of  biological  phosphorus removal
   processes.
                                                  44

-------
In the case of the A/O process without nitrification,
the retrofit requirement may require  additional tank
volume of  only  45-minutes  detention  time.  This
small volume may frequently  be available  in  the
existing system, especially when the improved sludge
thickening characteristics are considered.

For  all  of  the mainstream  processes,  the  retrofit
design must consider the  processing of the  waste
activated sludge and the potential release and recycle
of phosphorus to the activated sludge system. Further
work  is needed to investigate  the fate  of released
phosphorus in anaerobic digesters. Aerobic digestion
will result in a phosphorus release that is proportional
to the sludge mass reduction. Removal of the sludge
for land application is a favored alternative that also
takes advantage of the higher nutrient content  of the
waste sludge.

The choice of the retrofit system will  depend  on
treatment objectives, wastewater characteristics, and
economics.  In  all  cases,  the  biological  phosphorus
removal retrofit design  should  be compared to the
chemical  treatment  alternative  for phosphorus
removal. Compared  to the  biological methods,
chemical alternatives will have a higher operating cost
due to chemical  addition  and  increased sludge
handling. As discussed in Section  3.5.2.1,  sludge
production  from a biological  phosphorus removal
system  is expected to be only slightly  greater than
that from a conventional activated sludge system. The
biological  phosphorus  removal  alternatives  may
require  a higher initial capital  investment for facility
modifications but, in the long term, a net savings may
result from the savings in operating costs.

Retrofit economic  comparisons  are site specific.
Numerous factors  are involved, and it is difficult to
make general  statements  concerning  these
comparisons. As shown at  Pontiac, Michigan  (67), it
was extremely simple to modify the existing system to
operate in the A/O process mode and the capital cost
was minimal.  The  high  influent  BOD:P ratio also
favored the selection of a  mainstream biological
phosphorus  removal  process. On the  other  hand,
weak wastewaters with a low  influent  BOD:P ratio
generally favor the selection of  a  chemical treatment
alternative,  the Phostrip process,  or  perhaps  a
mainstream  biological phosphorus removal process
coupled with primary sludge fermentation.

Treatment needs  will  also affect the retrofit process
selection and design. If a  high level   of nitrogen
removal in addition to BOD and phosphorus removal
are required, the Modified  Bardenpho process is  a
prime candidate.  If  a  lesser  degree   of nitrogen
removal is  desired along with  BOD and  phosphorus
removal, the A2/O and UCT processes should also  be
considered.  If  only nitrification and BOD removal are
required, the A/O process with  or without an anoxic
zone, the  UCT process,  an operationally modified
activated sludge system, and the Phostrip  process
are all  candidates.  If  BOD  removal  only  is  the
objective, all  of the  above  processes with  the
exception of the  Modified Bardenpho, UCT, and A2/O
processes should be considered.

An  operationally modified activated  sludge  system
may be  considered a higher risk alternative for
retrofitting since it generally  lacks  the  well defined
anaerobic-aerobic  zones of  the  UCT, A/O, and
Modified  Bardenpho  processes.  However,  with
favorable wastewater characterisitics and a relatively
large anaerobic zone, such systems have been able
to  achieve effluent  phosphorus   concentrations
equivalent to those of the staged  systems. The plug
flow systems reporting "luxury uptake"  in the early
literature also  showed  that  operationally  modified
systems  could  achieve good phosphorus removal
even though coarse  bubble  aeration was applied to
the anaerobic fermentation zone.

Many plants can  be  easily modified to  create
fermentation zones. This can be done by turning off
selected aerators,  decreasing  the air supply  to
sparged air headers at  the head of the aeration tank,
turning off aerators and adding mixers at the head of
the aeration  tank, or by recycling the return activated
sludge though existing primary clarifiers for anaerobic
contacting with raw wastewater. In the latter case, the
entire primary solids inventory would then be directed
to the activated  sludge aeration tank. For a modified
operation of this type, existing oxygen  transfer and
organic   treatment capacities would  have  to be
carefully evaluated.

Operationally modified activated sludge  systems may
also be  used  with chemical  treatment  phosphorus
removal  systems,  where appropriate,  to decrease
chemical  treatment  costs.  An  advantage of  the
operationally modified activated sludge alternative is
that it can usually be easily tested in  the existing plant
before final process design decisions are developed.

In summary, biological  phosphorus  removal  process
options  generally  are  easily adaptable for  plant
retrofitting.  The  process  choice,  design,  and
economics,  however, will be  extremely  site specific.
All  the  design  considerations described  for new
facilities apply also to retrofit designs.


3.8 Case Histories
3.8.1   Phostrip  Process   •  Little   Patuxent,
Maryland
The Little Patuxent (Savage,  Maryland) wastewater
treatment plant has a  design treatment capacity of
56,800 m3/d (15 mgd)  and was  started up in  1982.
The plant  treatment  scheme  includes  primary
treatment; a first-stage,  high-rate activated  sludge
process;  separate-stage  nitrification; and chemical
coagulation/flocculation with  filtration  for residual
                                                 45

-------
phosphorus  and suspended  solids removal.  Primary
and waste biological sludges are aerobically digested
before being  gravity  thickened  with the  waste
chemical sludge. The thickened sludge is dewatered
with a belt filter press before final disposal.

The Phostrip process is incorporated within the  first-
stage  activated sludge system. Partial nitrification also
occurs in the first-stage system. System operation
and performance were  studied in 1984 and 1985 as
part  of  a U.S.  EPA-sponsored evaluation  of  full-
scale  biological phosphorus removal  installations. The
information given here is from that study (48).

Operating changes were made in the first-stage
activated sludge system in  April 1985 to improve
treatment performance. The first-stage  activated
sludge operation was changed from  step feed to plug
flow to improve phosphorus uptake.  During the step-
feed  operating  mode,  the mixed  liquor  DO
concentration  was normally  less than  2  mg/l  and
phosphorus  release occurred  in  the  secondary
clarifiers. During these operating  conditions, the
effluent total phosphorus  concentration averaged  2
mg/l.

Other changes made concurrently with the switch to  a
plug flow operating mode were to increase the mixed
liquor DO concentration to 4 mg/l at the effluent end
of the aeration basin to  prevent phosphorus release in
the secondary  clarifiers and  to  increase the return
sludge  ratio to decrease  the  secondary  clarifier
blanket  level.  Other  changes  were  also
simultaneously made in the stripper  operation. During
April  1985, the first-stage activated  sludge operating
parameters were reported as follows:

   F/M loading = 0.5 kg TBOD/kg MLVSS/d
   MLSS  = 2,000 mg/l
   SRT  = 4.6 days
   HRT  =  3.0 hr
   Return sludge ratio = 0.57

The elutriation  rate to  the stripper was decreased in
April 1985 from 121 to  50 percent of the stripper feed
flow rate. Recycled stripper underflow was also  used
as an elutriant source  in  addition to  the previously-
used  reactor-clarifier  overflow.  The SDT  in the
stripper was maintained at 7  hours. The return sludge
flow to the stripper was increased from 22 to 34
percent of the system influent flow rate.

The orthophosphorous  concentration  of the stripper
liquor increased from 7.2 to 17.6 mg/l  after the above
changes.As  shown  previously  in  Table  3-5, the
average  monthly effluent phosphorus concentration
from  the  first-stage  activated  sludge  system
decreased from 1.7 to 0.5 mg/l.

The overflow rate  of  the  reactor-clarifier  used for
chemical treatment of  the  stripper  overflow was 34
m.3/d/m2  (840  gpd/ft2). The lime dosage was  about
100  mg/l to maintain a pH of 9.5 for phosphorus
precipitation.  About  50-60 percent  of  the total
amount of phosphorus removed  in the  system was
removed  in the stripper operation. The remainder was
removed  via  the  waste  activated  sludge.  The
phosphorus  content  of the waste solids  on  a  dry
weight basis  was about 3.9 percent.

April 1985 treatment performance for  the  first-stage
activated  sludge system is summarized in  Table 3-
15. Total  phosphorus removal efficiency  averaged 94
percent in spite of  a relatively weak influent TBOD
concentration that  resulted in  an influent  TBOD:TP
ratio of 13.1. Effluent TBOD and  TSS concentrations
were also very good.
Table 3-15.   Summary  of  Phostrip Process  Treatment
           Performance for Little Patuxent Plant -  April
           1985.
Flow, m3/d
Influent
Total P, mg/l
1 st-Staqe AS Influent
TBOD, mg/l
Total P, mg/l
Ortho P, mg/l
TBOD:TP
1 st-Staqe AS Effluent
TBOD, mg/l
TSS, mg/l
Total P, mg/l
Ortho P, mg/l
NH4-N, mg/l
Total N
40,900

8.8

92
7.0
4.8
13.1

6
11
0.5
0.1
9.5
21
3.8.2 Modified Bardenpho Process - Kelowna,
Canada
The city  of  Kelowna, Canada,  is located  in  the
Okanagen Valley in the Province of  British Columbia.
Okanagen Lake  is generally considered to be in an
oligotrophic state, and, in the late 1960s, algal blooms
on several areas of the lake caused  concern. A water
basin  study recommended   80  percent  total
phosphorus  reduction  from   sewerage  system
discharge  points.  In addition,  nitrogen  was  also
considered limiting  in certain   areas  of the lake.
Several  treatment  schemes  were  considered
including  land application and   advanced  physical-
chemical  treatment  before  selecting  the Modified
Bardenpho process on the basis of lowest cost.

The existing  facility had a design capacity of 11,400
m.3/d (3.0 mgd)  and consisted of primary treatment,
                                                  46

-------
conventional  activated sludge, and trickling filters for
a portion of the flow. The existing inlet works, primary
clarifiers, and secondary clarifiers were incorporated
in the  new plant. The upgraded plant design flow is
22,700 m3/d  (6.0 mgd), with a maximum hourly flow
of twice the  average flow.  Raw wastewater  flows
through  conventional headworks  consisting  of a
barminnutor,  grit  chambers, and Parshall  flumes for
flow measurement.  The  three  existing  primary
clarifiers are  now operated in  a high-rate mode prior
to the  Modified Bardenpho system reactor.

During the design  phase,  the  Modified Bardenpho
process was  in its early period of application and an
effort  was made to  provide  maximum  operational
flexibility. The process was  divided into two modules
with 21  square cells  in each  module. The design
loadings  have been given  in Table 3-6  in  Section
3.3.2.  Following  secondary  clarification,  polishing
filters  and  chlorination are employed before effluent
discharge. The primary sludge is directed to a gravity
thickener, and the waste activated sludge is thickened
with dissolved air  flotation  to  prevent phosphorus
release.  The  thickened  sludge is  combined   in a
sludge storage vault prior  to disposal by composting.
As discussed in  Section  3.6,  the  thickened sludge
liquor  has  been  used  to   enhance  biological
phosphorus removal performance.

Turbine  aerators were  selected  for the  process
reactor. Air is supplied to these turbines by centrifugal
blowers.  The  aerators are equipped with  two-speed
motors so that  certain cells  can  be operated as
anoxic cells  (mixing  only) or  aerated  cells.  The
maximum design power consumption is about 280 kW
(375 hp) for  the  blowers  and an  additional 250 kW
(335 hp) for the turbine aerators, stirrers, and recycle
pumps. DO probes are used to control the air supply.

The startup  date for  the  Kelowna  plant was  May
1982.  The  total construction  cost  for  the  plant
installation  was  about $12,000,000 (U.S.  $).  The
cost reflects  some  unique geotechnical problems  at
the site, which is underlain by sedimentary and deltaic
deposits.

The floors of the new structures were laid in a 3-m
(10-ft)  thick layer of soft silt that is contained in sand
and  gravel.  Since  a high  water table  was  also
present, extensive dewatering was required and  sheet
piling was used during construction (63).

The treatment performance of  the Kelowna plant,
described previously in Section 3.3.2, indicates the
facility  is able to  meet its discharge requirements  of
8, 7, 6 and 2 mg/l for TBOD, TSS, total nitrogen, and
total phosphorus, respectiveley. In Section  3.6, the
benefits of using primary sludge thickener  liquor  to
enhance fermentation  were described, showing that
this  operating procedure  resulted  in much  lower
effluent soluble phosphorus concentrations.
3.8.3 A/O Process - Pontiac,  Michigan
The  process design  and performance of  the  A/O
system installed  at  the Pontiac,  Michigan  East
Boulevard  Plant have been described in Section
3.3.3. The  existing facility provided many advantages
for the investigation of an A/O  system in a full-scale
facility.  Two  of  four activated  sludge trains  were
converted  to the  A/0 process mode  to allow a
comparison of  treatment  performance  with   the
conventional system. The A/O  system was operated
at cold wastewater temperatures and under nitrifying
conditions,  contrary  to  the  Largo,  Florida  A/O
operation. However, the system was  also operated at
a relatively long  SRT for an  A/O  system. Waste
activated sludge was anaerobically digested, and  this
provided  an  opportunity  to  evaluate  potential
phosphorus release  back  to the digester recycle
stream. The design and  performance summaries for
the  facility were  shown  previously  in  Tables  3-10
and  3-11,  respectively.

Significant  conclusions from this full-scale  evaluation
were  that an effluent total phosphorus concentration
of less than 1 mg/l could  be  achieved without effluent
filtration and that the anaerobic digester supernatant
did not present a significant recycle phosphorus  load
to the plant. The latter needs further investigation to
explore  why phosphorus was not solubilized during
digestion.

It should be noted  that the wastewater characteristics
were very favorable  for  biological  phosphorus
removal, which tended to offset the relatively  long
SRT  needed for nitrification. The  influent  TBOD:TP
ratio  was generally  between 30 and 40.

The  project also illustrated that an existing  activated
sludge facility could be easily upgraded for biological
phosphorus removal at  minimal  cost and  within a
relatively short time period. The retrofit effort involved
the  allocation of 21  percent  of the existing aeration
basin to  a  three-stage anaerobic fermentation zone.
This   involved  the  addition  of  wooden baffles  and
mechanical mixers. The  retrofit  operation   was
completed  in 2  months  at  a cost  of approximately
$57,000 (1984 $) for conversion of 13,250  m3/d (3.5
mgd) of treatment  capacity  to  biological phosphorus
removal (67). The existing aeration  basin  treatment
capacity   and   air  supply  were   sufficient  to
accommodate the plant modification.


3.9 Costs
The   costs for biological   phosphorus   removal
processes are sensitive to wastewater characteristics,
treatment  level  needs, and  existing  equipment  and
site considerations. Where only phosphorus removal
is required  and  nitrification  is  not  occurring,
reasonable  retrofit  treatment  alternatives include
chemical addition to  existing biological  systems and
the  Phostrip  and  A/O processes. If nitrification is
                                                  47

-------
occurring  or  is required, the UCT  process  and the
A/0 process with  an anoxic zone and internal recycle
(i.e., the A2/O  process)  are  candidates as  well. An
anoxic zone  for  partial denitrification is not strictly
needed to achieve nitrification with the A/0  process,
but it  is recommended to minimize the amount of
nitrate nitrogen  recycled to the anaerobic zone in the
return  sludge and  its adverse effect  on biological
phosphorus release  in  that  zone.  For  both
phosphorus  removal  and a  high  level of  nitrogen
removal, the  Modified Bardenpho  process is a viable
alternative along with a variety of advanced treatment
designs  using  chemical addition  for  phosphorus
removal.

An  analysis  was  performed  to  compare  the cost of
biological  phosphorus  removal  to that for  chemical
addition to activated  sludge for  retrofitting  existing
facilities (91). Effluent total phosphorus limits of 1.0
and 0.3 mg/l  were considered. Nitrogen removal was
not a  requirement in the  analysis.  The  analysis
concluded that  chemical  addition  to activated sludge
was more cost-effective to  meet  a 1.0-mg/l  total
phosphorus effluent and was also  more cost  effective
for  meeting  an  effluent  total   phosphorus
concentration of  0.3  mg/l for flows of up  to 4,500
m3/d (1.2  mgd). The A/0 process was  determined to
be more cost effective for flows of  13,600 m3/d (3.6
mgd) or more.

On the other hand, the  cost  of  the A/0 retrofit  for
Pontiac,  Michigan,  was well  below these  cost
predictions.  The  Phostrip process was selected  for
the   Reno-Sparks  150,000-m3/d  (40-mgd)
phosphorus removal retrofit after it was  estimated that
a total  annual  cost savings  of $500,000 would  be
realized compared  to chemical addition to activated
sludge (77).  It  appears,  therefore, that the  potential
for realizing retrofit  cost savings with biological
phosphorus removal will likely be very site specific.

A key economic factor in the above cost analysis and
in  other cost  analyses  is the decision to  include
polishing filters  to   meet  effluent  phosphorus
concentrations  of less than 1.0 mg/l for the A/0,  UCT,
and Modified Bardenpho systems.  This would also
apply  to  operationally  modified  activated  sludge
processes. Some chemical addition may be required
in  the above  processes where  unfavorable BOD:P
ratios exist.  Cost considerations for external acetate
production may also have to be developed.  Previous
plant  performance data indicate that effluent filtration
may not always be required. This  will be a function of
the influent BOD:P  ratio or availability of fermentation
products,  the secondary clarifier  design, the system
SRT,  and other parameters that affect  activated
sludge flocculation and clarification properties.

Cost curves for new plants have been presented in a
report entitled  Emerging Technology Assessment of
Biological Removal of Phosphorus  (48).  Tables 3-16
through 3-19  summarize  the  updated  capital  and
O&M  costs developed  for four basic  cases.  The
updated capital costs are based on an Engineering
News Record  Construction Cost Index of 4367 (May
1987). The updated  O&M costs are based  on an
EPA Escalation Index of 3.83. The four cases are:

Case 1:
Phosphorus removal only with a required effluent total
phosphorus concentration of 1  mg/l. A comparison is
made  between  a single-stage  activated  sludge
system with alum addition, a Phostrip system, and an
A/0 system.  Effluent filtration is assumed  with the
A/0 system.

Case 2.
Same as  Case  1  except the  required  effluent  total
phosphorus concentration is 2 mg/l.  Without effluent
filtration, in this case, the A/O system is shown to be
most  cost-effective.

Case 3:
Same as  Case 2 with the  addition  of nitrification.  In
this case, a two-stage  nitrification system with alum
addition is assumed  for  the conventional  alternative
and is compared to a single-sludge A/O system. The
two-stage  system has a much higher capital cost.

Case 4:
Same as Case 3 with the addition of denitrification to
achieve an effluent total nitrogen concentration  of 3
mg/l.  In this   case,  a  three-stage activated sludge
system with alum addition is compared to  a Modified
Bardenpho system.  The  three-stage  system has
significantly higher capital and operating costs.

In summary, the cost comparisons  illustrate that the
biological  phosphorus removal alternatives  may be
competitive with  conventional chemical methods. The
use of effluent filtration  is  a critical  economic factor
and any final  cost comparison will be extremely site
specific and affected  by wastewater characteristics.
                                                  48

-------
Table 3-16.   Cost comparison - Case 1: Phosphorus removal (effluent TP = 1 mg/l)
Alternative
1 -stage AS with alum addition
Phostnp
A/O (4-hr detention) with effluent
filters
Table 3-17. Cost comparison -
Alternative
1 -stage AS with alum addition
Phostrip
A/O (4-hr detention)
Table 3-18. Cost comparison -
Alternative
2-stage AS with alum addition
A/O (6-hr detention) for nitrification
and partial denitriflcation to
total N = 10 mg/l
Table 3-19. Cost comparison -
3 mg/l)
Alternative
3-stage AS with alum addition
Modified Bardenpho
Costs-
Capital, $
O&M, $/yr
Total present worth, $
Capital, $
O&M, $/yr
Total present worth, $
Capital, $
O&M, $/yr
Total present worth, $
Case 2: Phosphorus removal
Costs*
Capital, $
O&M, $/yr
Total present worth, $
Capital, $
O&M, $/yr
Total present worth, $
Capital, $
O&M, $/yr
Total present worth, $
Case 3: Phosphorus removal
Costs"
Capital, $
O&M, $/yr
Total present worth, $
Capital, $
O&M, $/yr
Total present worth, $
Case 4: Phosphorus removal
Costs*
Capital, $
O&M, $/yr
Total present worth, $
Capital, $
O&M, $/yr
Total present worth, $

1,890
2,774,000
218,000
4,782,000
3,801,000
273,000
6,315,000
3,370,000
227,000
5,461,000
(effluent TP = 2

1,890
2,762,000
213,000
4,724,000
3,801,000
273,000
6,315,000
2,813,000
197,000
4,627,000
plus nitrification

1,890
3,370,000
245,000
5,627,000
3,142,000
210,000
5,076,000
plus nitrification

1,890
3,869,000
296,000
6,595,000
3,321,000
205,000
5,209,000
Plant Size, nA'd
18,900
10,851,000
868,000
18,846,000
12,602,000
744,000
19,455,000
13,257,000
836,000
20,957,000
mg/l)
Plant Size, m3d
18,900
10,821,000
835,000
18,512,000
12,602,000
744,000
19,455,000
10,819,000
692,000
17,193,000
(effluent TP = 2 mg/l; NH4-N
Plant Size, m3d
18,900
12,820,000
921,000
21,303,000
1 1 ,942,000
764,000
18,979,000
and denitriflcation (effluent TP
Plant Size, m3d
18,900
14,553,000
1 ,200,000
25,605,000
13,553,000
756,000
20,516,000

189,200
55,568,000
5,611,000
107,248,000
59,073,000
3,956,000
95,509,000
63,472,000
4,545,000
105,333,000


189,200
55,350,000
5,276,000
103,944,000
59,073,000
3,956,000
95,509,000
52,314,000
3,820,000
87,498,000
= 1 ma/I)

189,200
63,381,000
5,793,090
116,737,000
59,169,000
4,264,000
98,442,000
= 2 mg/l; TN =

189,200
72,777,000
8,059,000
147,004,000
77,472,000
4,:>52,000
1 19,398,000
 * Total present worth calculated assuming a 20-year life and a discount factor of 8-7/8 percent (PWF =-  9.2104)
                                                          49

-------
3.10 References
When an NTIS  number is cited  in a reference,  that
reference is available from:

      National Technical Information Service
      5285 Port Royal Road
      Springfield, VA22161
      (703)  487-4650

1.  Greenburg, A.E.,  Levin,  G. and W.J. Kauffman.
   Effect of Phosphorus Removal on the Activated
   Sludge  Process.  Sewage  and Industrial Wastes
   27: 227, 1955.

2.  Srinath, E.G. et al. Rapid Removal of Phosphorus
   from  Sewage  by Activated  Sludge. Experientia
   (Switzerland), 15:339, 1959.
3.  Levin, G.V. and J. Shapiro. Metabolic Uptake of
   Phosphorus by Wastewater Organisms. JWPCF
   37: 800, 1965.

4.  Shapiro,  J., Levin, G.V.  and Z.G. Humberto.
   Anoxically Induced Release of Phosphate in
   Wastewater Treatment. JWPCF 39: 1810, 1967.

5.  Levin, G.V., Topol,  G.J., Tarnay, A.G. and R.B.
   Samworth. Pilot  Plant Tests  of  a Phosphate
   Removal Process. JWPCF  47(6): 1940, 1972.

6  Levin, G.V., Topol,  G.J. and A.G.  Tarnay.
   Operation of Full  Scale Biological  Phosphorus
   Removal Plant. JWPCF 47(3): 1940, 1975.

7.  Vacker,  D.  et  al.  Phosphate Removal  through
   Municipal Wastewater  Treatment at San Antonio,
   Texas. JWPCF 39:750, 1967.

8.  Bargman, R.D.  et al. Continuous Studies  in the
   Removal of Phosphorus by the Activated Sludge
   Process. Chem. Engr. Prog. Symp. Ser., 67: 117,
   1970.

9.  Milbury,  W.F.  et  al. Operation  of  Conventional
   Activated Sludge for  Maximum  Phosphorus
   Removal.  JWPCF 43:1890,  1971.

10. Menar,  A.B.  and  D.  Jenkins.  The  Fate  of
   Phosphorus in  Waste Treatment Processes:  The
   Enhanced Removal of Phosphate  by  Activated
   Sludge. Proceedings of the 24th  Purdue Industrial
   Waste Conference, Lafayette, Indiana. 1969.

11. Barnard, J.L. Cut  P and  N  Without Chemicals.
   Water and Wastes Engineering. 7, 1974.

12. Barnard, J.L. A Review of  Biological Phosphorus
   Removal in the Activated Sludge Process. Water
   SA, 2:136, 1976.
13. Nicholls,  H.A. Full Scale Experimentation on the
   New Johannesburg  Extended  Aeration  Plants.
   Water S.A., 1:121, 1975.

14. Venter,  S.L.V.  et al.  Optimization  of  the
   Johannesburg Olifantsvlei  Extended  Aeration
   Plant for Phosphorus  Removal.  Prog,  in  Wat.
   Technology 10:279, 1978.

15. Osborn, D.W. and H.A. Nicholls.  Optimization of
   the Activated Sludge Process  for the Biological
   Removal of Phosphorus. Int.  Conf. on Advanced
   Treatment  and  Reclamation  of Wastewater,
   Johannesburg, South Aafrica,  June 1977.

16. Stensel, H.D. et al. Performance of First U.S. Full
   Scale Bardenpho Facility.  Proceedings of EPA
   International  Seminar on Control  of Nutrients in
   Municipal Wastewater Effluents,  San Diego, Calif.,
   September 1980.

17. Hong,  S.N.  et  al.  A  Biological  Wastewater
   Treatment  System  for  Nutrient  Removal.
   Presented at the  54th Annual WPCF Conference,
   Detroit, Michigan, October  4-9,  1981.

18. Marais, G.vR., Loewanthal,  R.E. and I.P. Siebritz.
   Review:  Observations  Supporting  Phosphate
   Removal  by Biological Excess  Uptake. Selected
   Papers on Activated Sludge  Process  Research,
   University of Capetown, South Africa, April 1982.

19. Stensel,  H.D.  Fundamental  Principles  of
   Biological Phosphorus Removal. Presented at the
   Workshop on Biological Phosphorus Removal in
   Municipal Wastewater  Treatment,  Annapolis,
   Maryland, June  22-24, 1982.

20. Fuhs, G.W.  and M. Chen. Microbial Basis  for
   Phosphate  Removal in the Activated  Sludge
   Process for the Treatment of Wastewater.  Microb.
   Ecol., 2:119, 1975.

21. Deinema,  H.,  Van  Loosdrecht,  M.  and  A.
   Scholten. Some  Physiological Characteristics of
   Acinetobacter Spp Accumulating  Large Amounts
   of Phosphate. Enhanced Biological Phosphorus
   Removal  from Wastewater, Vol. I. IAWPRC Post
   Conference  Seminar, p. 154,  Sept. 24,  1984,
   Paris, France.

22. Buchan,  L.  The  Location  and  Nature  of
   Accumulated  Phosphorus in Seven Sludges from
   Activated  Sludge  Plants  which  Exhibited
   Enhanced Phosphorus Removal.  Water SA,  7:1,
   1981.

23. Lawson,  E.N. and  N.E. Tonhazy.  Changes in
   Morphology  and Phosphate-Uptake Patterns of
                                               50

-------
    Acmetobacter Calcoaceticus Strains. Water  SA,
    6:105, 1980.

24. Letter,  L.H.  The Role of Bacterial Phosphate
    Metabolisms  in  Enhanced Phosphorus Removal
    from the  Activated Sludge Process.  Enhanced
    Biological Phosphorus Removal from Wastewater,
    Vol. I., IAWPRC Post Conference Seminar, p.
    173, September 24, 1984, Paris, France.

25. Hascoet,  M.C.,  Florent,  M.  and  P.  Granger.
    Biochemical  Aspects of Biological Phosphorus
    Removal from Wastewater. Enhanced Biological
    Phosphorus Removal from Wastewater,  Vol. I.,
    IAWPRC  Post  Conference  Seminar,   p.  33,
    September 24, 1984, Paris, France.

26. Suresh, N., Warburg, M., Timmerman, M., Wells,
    J., Coccia, M., Roberts, M.F. and H.O. Halvorson.
    New  Strategies   for  the  Isolation   of
    Microorganisms  Responsible  for Phosphate
    Accumulation. Enhanced Biological Phosphorus
    Removal from Wastewater, Vol. I.,  IAWPRC Post
    Conference Seminar,  p.  131,  September  24,
    1984, Pans, France.

27. Brodisch, K.E.U.  Interaction of Different Groups of
    Micro-organisms  in  Biological Phosphate
    Removal.  Enhanced  Biological  Phosphorus
    Removal from Wastewater, Vol. I.,  IAWPRC Post
    Conference Seminar,  p.  121,  September  24,
    1984, Pans, France.

28. Lotter, L.H. and  M. Murphy. The Identification of
    Heterotrophic Bacteria in  an  Activated   Sludge
    Plant with Particular Reference  to Polyphosphate
    Accumulation. Water  SA, 11 (4): 172,  October
    1985.

29. Hong,  S.N.  et  al. A Biological  Wastewater
    Treatment  System  for  Nutrient  Removal.
    Presented at EPA Workshop  on Biological
    Phosphorus Removal  in  Municipal Wastewater
    Treatment, Annapolis, Maryland,  June  22-24,
    1982.

30. Ekama, G.A.,  Marais,  G.vR. and  I.P.  Siebritz.
    Biological Excess Phosphorus Removal. Chapter
    7,  Theory, Design, and  Operation of  Nutrient
    Removal  Activated Sludge  Processes,  Water
    Research  Commission,  Pretoria,  South  Africa,
    1984.

31. Rensmk, J.H., Donker,  H.J.G.W.  and  H.P.  de
    Vries.  Biological  P  Removal  in  Domestic
    Wastewater by the Activated Sludge  Process.
    Presented at  5th European Sewage and  Refuse
    Symposium, Munich, West Germany, June 1981,
    Procs.  487-502.
32. Fukase, T., Shibeta, M., and X. Mijayi. Studies on
    the  Mechanism  of  Biological  Phosphorus
    Removal.  Japan  Journal Water  Pollution
    Research 5, 309, 1982.

33. Arvin, E. Biological Removal of Phosphorus from
    Wastewater. CRC Critical  Rev.  Environmental
    Control,  15:25-69, 1985.

34. Rabinowitz, B.  The Role of Specific Substrates in
    Excess  Biological Phosphorus Removal.  Ph.D.
    Thesis,  The  University  of British Colombia,
    Vancouver, British Columbia,  Canada,  October
    1985.

35. Wentzel, M.C.,  Dold, P.L., Ekama,  G.A.  and
    G.vR. Marais.  Kinetics of Biological Phosphorus
    Release. Enhanced  Biological  Phosphorus
    Removal from  Wastewater, Vol. I., IAWPRC Post
    Conference Seminar, p. 89,  September 24, 1984,
    Paris, France.

36. Jones, P.H., Tadwalker, A. and C.L. Hsu. Studies
    in the  Enhanced Uptake  of  Phosphorus  by
    Activated Sludge:  Effect of Substrate  Addition.
    Proceedings,  New Directions  and Research in
    Waste Treatment and  Residuals Management,
    The  University of  British  Columbia,  Vancouver,
    British Columbia,  Canada, June 23-28, 1985, p.
    324.

37. Comeau, Y.,  Hall, K.J., Hancock,  R.E.W.  and
    W.K.  Oldham.  Biochemical  Model for Enhanced
    Biological Phosphorus  Removal. Proceedings,
    New  Directions  and  Research   in  Waste
    Treatment  and  Residuals  Management,  The
    University of British Columbia, Vancouver,  B.C.
    Canada, June  23-28, 1985,  p. 324.

38. Miyamoto-Mills, J.  et al. Design and Operation
    of a Pilot-Scale Biological  Phosphate  Removal
    Plant at the  Central Contra  Costa  Sanitary
    District.  Water  Science  Technology,  15:153,
    1983.

39. Arvin,  E.  and  G.H. Kristensen. Exchange of
    Organics, Phosphate  and  Cations  Between
    Sludge and Water in Biological Phosphorus and
    Nitrogen  Removal Processes.  Enhanced
    Biological Phosphorus Removal from  Wastewater,
    Vol.  I.,  IAWPRC  Post Conference  Seminar,  p.
    183,  September 24, 1984, Paris, France.

40. Timmerman, M.W. Biological Phosphate Removal
    from   Domestic   Wastewater   Using
    Anerobic/Aerobic  Treatment.  Chapter  26  in
    Development in  Industrial  Microbiology,  p.  285,
    1979.
                                               51

-------
41.  Nicholls, H.A. and D.W. Osborn. Bacterial Stress:
    Prerequisite  for  Biological  Removal  of
    Phosphorus. JWPCF 51(3).557, 1979.

42.  Deinema,  M.H. et al.  The  Accumulation  of
    Polyphosphate  in   Acmetobacter  Spp.
    Microbiology Letters, Federation of Microbiological
    Societies, 273-279, 1980.

43.  Senior,  P.J. et al. The Role of Oxygen Limitation
    in the Formation of Poly B Hydroxybutyrate during
    Batch  and  Continuous  Culture of Azotobacter
    beijerincku. Biochem, Jour., 128:1193,  1972.

44.  Gaudy,  A.  and  E.  Gaudy.  Microbiology  for
    Environmental Scientists and  Engineers.McGraw
    Hill, 1980.

45.  Harold,  P.M. Inorganic  Polyphosphates in Biology:
    Structure Metabolism  and  Function.  Bacteriol.
    Reviews, 30:772, 1966.

46.  Sell, R.L.  et  al.  Low  Temperature  Biological
    Phosphorus  Removal.  Presented  at the  54th
    Annual  WPCF  Conference,  Detroit,  Michigan,
    October 1981.

47.  Tetreault, M.J., Benedict, A.H., Kaempfer, C. and
    E.F. Barth. Biological  Phosphorus  Removal - A
    Technology Evaluation.  JWPCF 58(8):8232-837,
    1986.

48.  Emerging Technology  Assessment of Biological
    Removal of Phosphorus.  EPA-600/2-85-008,
    NTIS No. PB-85-165744,  U.S. Environmental
    Protection Agency, Cincinnati,  Ohio.

49.  Nutrient  Control. Manual of  Practice  FD-7.
    Facilities  Design, Water  Pollution  Control
    Federation, 1983.

50.  Barnard,  J.C. Biological Denitrification.  Journal
    International Water  Pollution Control  Federation,
    72:6, 1973.

51.  Arora,   M.L., Barth, E.F. and  M.B.  Umphres.
    Technology  Evaluation of Sequencing  Batch
    Reators. JWPCF 57:807, 1985.

52.  Irvine,  R.L.  et al.  Municipal Application  of
    Sequencing Batch Treatment at Culver,  Indiana.
    JWPCF 55:484, 1983.

53.  Irvine, R.L. et al.  Organic Loading  Study of Full-
    Scale  Sequencing  Batch  Reators.  JWPCF
    57:847,  1985.

54. Rensink, J.H.,  Donker, H.J.G.W. and  T.S.J.
    Simons.  Phosphorus  Removal at Low Sludge
    Loadings.  Enhanced  Biological Phosphorus
    Removal From Wastewater, Vol. I,  IAWPRC Post
   Conference  Seminar,  Sept. 24,  1984,  p.  217,
   Paris, France.

55. Simpkins,  M.J.  and A.R.  McLaren. Consistent
   Biological  Phosphate and Nitrate Removal in an
   Activated  Sludge  Plant. Progr.  Water Technol.
   (G.B.) 10 (5/6):433, 1978.

56. Gerber,  A., Simpkins, M.J., Winter, C.T. and  J.A.
   Scheepers.  Biological Nutrient  Removal  from
   Wastewater  Effluents:  Performance  Evaluation of
   the  Full  PHOREDOX and  UCT  Processes.
   Contract Report 52, Council  for Scientific  and
   Industrial Research, Pretoria, South Africa, 1982.

57. Paepcke,  B.H.  Introduction  to  Biological
   Phosphorus Removal.  Proceedings   of  the
   Seminar on Biological Phosphorus Removal in
   Municipal  Wastewater Treatment,  Penticton,
   British Columbia, April  17 and 18,  1985.

58. Irvine,  R.L., Stensel,  H.D.  and J.F. Alleman.
   Summary  Report,  Workshop  on  Biological
   Phosphorus  Removal  in  Municipal Wastewater
   Treatment,  Annapolis, Maryland,  June 22-24,
   1982.   Sponsored  by  U.S.  EPA  Municipal
   Environmental  Research  Laboratory,  Cincinnati,
   Ohio, September 1982.

59. Levin, G.V.  Presented at  the  EPA Workshop on
   Biological Phosphorus Removal in  Municipal
   Wastewater  Treatment, San  Francisco,  Calif.,
   1983.

60. Inventory of Full Scale  Biological Phosphorus and
   Nitrogen Removal Facilities. Report submitted to
   the U.S. Environmental Protcetion Agency, Brown
   and  Caldwell Engineers, March 1984.

61. Peirano, L.E. Low Cost Phosphorus Removal at
   Reno-Sparks, Nevada. JWPCF 49:1568,  1977.

62. Oldham,  W.K.  and G.M.  Stevens.  Operating
   Experiences with  the  Kelowna  Pollution Control
   Centre.  Proceedings of the Seminar on Biological
   Phosphorus Removal  in  Municipal Wastewater
   Treatment, Penticton,  British Columbia,  Canada,
   April 17 and 18, 1985.

63. Leslie,  P.J. Design  of the Kelowna Pollution
   Control  Centre. Proceedings of the Seminar on
   Biological  Phosphorus  Removal in  Municipal
   Wastewater Treatment,  Penticton,  British
   Columbia, Canada, April 17 and 18,  1985.

64. Burdick, C.R.,  Refling, D.R.  and H.D. Stensel.
   Advanced  Biological Treatment to  Achieve
   Nutrient Control. JWPCF 54(7):1078, 1982.

65.  Stensel,  H.D.  et  al. Evaluation  of  Nutrient
    Removal  at Payson, Arizona. Proceedings,  New
                                                52

-------
    Directions and Research in Waste Treatment and
    Residuals Management, The University of British
    Columbia,  Vancouver, B.C.,  Canada, June 23-
    28, 1985, p. 476.

66. Barth,  E.F.  and  H.D.  Stensel.  Internationa!
    Nutrient  Control  Technology  for  Municipal
    Effluents. JWPCF 53(12):1691,  1981.

67. Kang, S.J.  et  al.  A  Year's  Low Temperature
    Operation in Michigan  of the A/0 System for
    Nutrient Removal.  Presented at the 58th  Annual
    Water Pollution  Control  Federation Conference,
    Kansas City, Missouri, October 1985.

68. Deakyne, C.W., Patel, M.A.  and D.J.  Krichten.
    Pilot  Plant  Demonstration  of Biological
    Phosphorus Removal. JWPCF 56(7):867, 1984.

69. Groenestijn, J.W.  and M.H. Demema. Effects  of
    Cultural  Conditions on Phosphate Accumulation
    and  Release by  Acinetobacter Strain  210A.
    Proceedings of the  International Conference,
    Management Strategies for Phosphorus  in the
    Environment, Lisbon,  Portugal, July 1-4, 1985.

70. Nicholls, H.A.,  Pitman, A.R.  and D.W. Osborn.
    The Readily Biodegradable Fraction of Sewage;
    Its Influence on  Phosphorus   Removal  and
    Measurement. Enhanced  Biological Phosphorus
    Removal from Wastewater, Vol. I, IAWPRC  Post
    Conference  Seminar,  September  24, 1984, Paris,
    France, 105.

71. Siebntz,  I.P.,  Ekama,  G.A.  and  G.vR.  Marais.
    Biological Phosphorus Removal in the Activated
    Sludge  Process.  Research  Report  W46,
    Department  of Civil   Engineering,  University  of
    Capetown, South Africa, 1983.

72. Fukase, T.,  Shibata,   M. and  V.  Mayaji. Factors
    Affecting  Biological   Removal of  Phosphorus.
    Enhanced Biological   Phosphorus  Removal from
    Wastewater-,  Vol.  I,  IAWPRC  Post Conference
    Seminar, Sept. 24,  1984, Pans, France, p. 239.

73. Maier, W. et al. Pilot  Scale Studies on Enhanced
    Phosphorus Removal in a  Single  Stage Activated
    Sludge Treatment Plant.  Enhanced  Biological
    Phosphorus  Removal from Wastewater,  Vol.  II
    IAWPRC Post Conference Seminar, S^pL  24,
    1984, Pans,  Fiance, p. 51.

74. Tracy,  K.D.  and A. Flammmo. Kinetics of
    Biological Phosphorus Removal. Presented at the
    58th  Annual  Water Pollution  Control Federation
    Conference,  Kansas  Citv,  Missouri,  October
    1985.

75. Vinconneau, J.O., Haseoet, M.C. and M. Horentz.
    The  First Applications of Biological Phosphorus
    Removal  in  France.  Proceedings  of  the
    International Conference, Management Strategies
    for  Phosphorus  in  the Environment,  Lisbon,
    Portugal, July 1-4,  1985.

76. McCarty, P.L.,  Beck,  L.  and  P.  St.  Arnant.
    Biological  Denitrification  of  Wastewaters  by
    Addition of Organic Materials.  Proceedings 24th
    Industrial Waste  Conference, Purdue Univ., West
    Lafayette, Indiana, 1969.

77. Peirano, L.E. et al. Full Scale Experiences with
    the Phostrip Process.  Presented at the Workshop
    on Biological Phosphorus Removal  in Municipal
    Wastewater  Treatment, Annapolis, Maryland,
    June 22-24,  1982.

78. Oldham, W.R. and H.P. Dew.  Cold  Temperature
    Operation of the Bardenpho Process.  Presented
    at  the  14th Canadian Symposium on  Water
    Pollution Research, 1979.

79. Nagashima,  M. et al.  A Nitrification/Denitrification
    Recycling System  for Nitrogen and  Phosphorus
    Removal  from  Fermentation  Wastewater.
    Fermentation Technology, 57:2, 1979.

80. Ekama, G.A.,  Siebritz,  I.P.  and  G.vR.  Marais.
    Considerations in the  Process  Design of Nutrient
    Removal Activated Sludge  Processes.  Selected
    Papers  on Activated Sludge Process  Research at
    the  University of Capetown, Capetown,  South
    Africa, April 1982.

81. McLaren,  A.R.  and  R.J.  Wood.  Effective
    Phosphorus Removal  from Sewage by Biological
    Means.  Water SA, 2, 47, 1976.

82. Wastewater  Engineering:  Treatment,  Disposal,
    Reuse.  Metcalf &  Eddy, Inc. McGraw-Hill, New
    York, New York,  1979.

83. Stensel, H.D.  Design  of Biological  Nutrient
    Removal Systems by Graphical Procedures. Civil
    Engineering  for Practicing and  Design  Engineers
    2(1), 1982.

84. Wastewater Treatment  Plant  Design.  Water
    Pollution Control Federation Manual of Practice
    MOP 8,  Washington, DC, 1977.

85. Stensel, H.D.   Biological  Nitrogen  Removal
    System  Design. Water 70(209),  1980.

86. Wuhrman, K. Nitrogen Relationships in Biological
    Treatment Processes  -  III.  Denitrification  in  the
    Modified Activated Sludge Process.    Water
    Research  3:177,1969.

87. Panzer,  C.C. Substrate Utilization Approach  for
    Design  of Nitrogen  Control.  Journal  of the
                                                53

-------
   Environmental  Engineering Division, ASCE, 110
   (2):369, April 1984.

88. Barnard, J.L. The  Role of Full Scale Research in
   Biological  Phosphate  Removal. Proceedings,
   New  Directions  and  Research  in  Waste
   Treatment  and Residulals Management,  The
   University of British Columbia, Vancouver, B.C.,
   Canada, June  23-28, 1985.

89. Rabinowizx, B. and W.K. Oldham.  The use  of
   Primary Sludge Fermentation  in  the  Enhanced
   Biological  Phosphorus Removal  Process.
   Proceedings,  New Directions  and Research  in
   Waste  Treatment and  Residuals Management,
   The University of British Columbia,  Vancouver,
   B.C.,  Canada,  June 23-28, 1985.

90. Barnard,  J.L., Activated Primary  Tanks  for
   Phosphate  Removal. Water SA, 10 (3):July 1984.

91. Nutt,  S.G.  and N.W. Schmidtke. Technical and
   Economical Feasibility  of Retrofitting Existing
   Municipal  Wastewater  Treatment Plants  in
   Canada for Biological  Phosphorus  Removal.
   Proceedings  of  the Seminar on  Biological
   Phosphorus Removal  in  Municipal  Wastewater
   Treatment,  Penticton, British  Columbia, Canada,
   April 17 and 18, 1985.
                                               54

-------
                                            Chapter 4
                         Phosphorus Removal by Chemical Addition
4.1 Introduction and Theory

Many wastewater treatment plants that are required to
remove phosphorus do  so by adding chemicals to
precipitate the phosphate present in the  wastewater.
As described in Section 4.2, chemicals may be added
to primary,  secondary, or tertiary  processes, or at
multiple locations in  the plant.  Chemicals used for
phosphorus  precipitation include metal  salts such as
ferric chloride and aluminum sulfate (alum), and lime.

This chapter:  1)  describes the characteristics of
chemicals used for  phosphorus  removal and  the
reactions  which  occur  during  phosphorus
precipitation, 2) discusses the alternative points for
chemical addition,  3)  assesses the performance of
chemical addition systems in removing  phosphorus,
and  4) provides  design procedures  for chemical
storage and feed facilities.

A variety  of metal  salts are used for  removal of
phosphorus  from municipal  wastewater.  The most
common chemicals are aluminum  sulfate (alum)  and
ferric  chloride.  Ferrous  sulfate and  ferrous chloride
solutions, which are available  as byproducts of
steelmaking  operations (pickle liquor) are also used.
Sodium aluminate addition is sometimes  practiced at
facilities with low alkalinity wastewaters.  Two other
chemical compounds that have been investigated for
phosphorus  removal are aluminum chlorohydrate  and
polyaluminum  chloride.  In  many  cases, anionic
polymers are used in addition to the mineral salt to
assist in solids separation.

Mineral salts are by far the most common chemicals
used  for phosphorus  removal. A number of  plants
originally designed for use of lime are currently using
alum or ferric chloride. In a 1979 survey of 104 plants
removing phosphorus in the lower Great Lakes basin,
53 facilities used iron  salts, 49 used aluminum salts,
and only 2 used lime (1).

The reasons for infrequent use of lime for phosphorus
removal include: 1) the substantial increase  in the
mass of sludge to be handled compared  to that from
use  of metal  salts,  and  2)  the  operation  and
maintenance problems associated with the handling,
storage, and feeding  of lime.  Due  to the fact  that
aluminum and iron salts have all but replaced lime as
a phosphorus  precipitant,  a detailed  discussion of
lime use is  not  presented  in this  Manual.  Detailed
information  and design  criteria for  lime  addition
facilities are contained in References 2 through 5.

The reactions  between phosphorus  and metal salts
are complex. For purposes of this discussion,  it  is
assumed that the primary mechanism of phosphorus
removal is  interaction  of  the metal ion  with
orthophosphate to form an insoluble precipitate.  The
reactions presented below are for illustrative purposes
and  may not represent the true mechanisms which
take place  due to the  variations in  wastewater
characteristics  and forms of phosphorus present. It is
recommended  that any engineering examination of
chemical addition for phosphorus removal include a
jar  test of  the actual  wastewater  of  concern  (see
Section 4.5.2). This will avoid  the common error of
assuming a required dosage when actual dosage can
vary substantially between facilities  (see Section 4-
3) and  at a given facility at different times of day and
season of the year (see Section 4.5).

4.1.1 Aluminum Compounds
Aluminum ions combine with phosphate ions to form
aluminum phosphate, as shown by:
AI3
                    P043~ -» AIPO4
(4-1)
On a mole basis,  1 mole of Al will react with 1 mole
of P04, or 1 mole of P. On a weight basis, 27 g of Al
will react with 95 g of P04 (or 31 g as P) to form 122
g of AIPO4. The AI:P weight ratio is thus 27 Al to 31
P or 0.87:1 (2).

The most common form  of  aluminum in  use  for
phosphorus precipitation is "alum" or "filter alum," a
hydrated  aluminum  sulfate   with the  approximate
formula Al2(S04)3»14H2O. Alum contains about  9.1
percent soluble aluminum  as Al and 17  percent
soluble aluminum as
The reaction of  alum  with phosphate  can  be
described by:

AI2(S04)3»1 4H2O + 2P043--H.2AIP04 i + 3S042" + 1 4H20
                                          (4-2)
                                                 55

-------
One mole (594 g) of alum will react with 2 moles (190
g) of phosphate containing 62 g phosphorus to form 2
moles  (244 g) of AIPO4.  Thus, the weight ratio of
alum to phosphorus is 594 to 62 or 9.6:1.

In practice, the quantities of alum required are higher
than the  stoichiometry would predict. This  is due to
competing reactions,  which vary  with the wastewater.
Among the most notable factors that affect the actual
quantity  of  alum  required  to attain a  specific  P
concentration  are: the alkalinity  and final  pH of the
wastewater;  ionic constituents such  as  sulfate,
flouride,   sodium,  etc.;  quantity and  nature  of
suspended solids, e.g., kaolin  vs. montmorillomite
clays;  microorganisms, and other colloidal  species;
the actual ratio of Al  to P;  and the intensity of mixing
and other physical conditions extant in the  treatment
facilities.  For the  purposes of engineering design the
following  stoichiometric reaction is provided:

AI2(SO4)3»14H20 + 6HC03--»2AI(OH)3 i + 6CO2 + 14H2O
                             + 3S043-
                                          (4-3)

The optimum pH  for  phosphorus removal using  alum
is in the  range  of  5.5-6.5. The extent  of pH
depression resulting  from  alum  addition will depend
on  the alkalinity  of  the  wastewater and the  alum
dosage.  In  unusual  cases  in  which the  buffering
capacity  (alkalinity) of the wastewater is very low,
addition  of  alkaline  chemicals may be required  to
offset the pH depression resulting from alum addition.
Although  strong acids could  be used  to lower the
wastewater  pH to the  optimum  point,  it  may  be
simpler to use a  higher alum dosage to depress the
pH.  The  relative  economics  of  the two  approaches
should be evaluated by  the engineer  during the
planning  process.

Alum can be purchased as dry alum in bags, drums,
or in bulk, or as liquid alum in  tank cars or trucks.
Characteristics of alum are given in Table 4-1 (3,4).

Sodium aluminate is  sometimes  used for  phosphorus
precipitation.  The  chemical formula  for sodium
aluminate is Na2Al204 or NaAI02- The  commercial
granular  trihydrate is written as Na2O»Al203»3H2O.
The  reaction between  sodium aluminate  and
phosphate may be expressed as  (6):
Na2O«AI203  + 2P043- -» 2AIP04 i
                                   2NaOH + 60H"
                                           (4-4)
Note the presence  of  NaOH  as a product of the
reaction, which will tend to increase pH rather than
lower it. This allows sodium aluminate to be used with
low alkalinity wastewaters in which use  of alum would
cause excessive depression of pH.

The mole ratio of Al to P is 1:1. The weight ratio  of
AI:P  is 0.87:1,  while  the  weight ratio of  sodium
aluminate to  phosphorus  is  approximately  3.6:1.
Characteristics  of  sodium  aluminate are  given  in
Table 4-1 (3,4).

Aluminum chlorohydrate  and polyaluminum chloride
are other potentially useful chemicals for phosphorus
precipitation. In jar test studies with  raw  wastewater
samples from four treatment plants, it was found that
polyaluminum  chloride was superior to  aluminum
sulfate in removing total  phosphate,  while  aluminum
chlorohydrate gave poorer results than the  other two
chemicals (7). If available at a cost competitive  with
the more common chemicals  used  for phosphorus
precipitation, further investigation of their use may be
justified.

A  "sewage grade" granular alum has been used  in
Scandanavia for 15-20 years and has been tested  at
several  wastewater treatment  plants in  the  United
States. This material  is a mixture of aluminum and
iron  sulfates, containing  approximately 13.7 percent
aluminum as AI2O3 and  4.3 percent iron  as  Fe2C-3.
The wastewater treatment plant serving Geneva,  New
York  is currently  using  this chemical, which  was
imported from Sweden.  However, its distribution  in
the United States has  been discontinued.

4.7.2 Iron Compounds
Iron  salts are  commonly  used in the precipitation  of
phosphorus from municipal wastewater. Both ferrous
(Fe2 + )  and ferric  (Fe3 + ) ions  can  be  used  in the
form of ferric chloride, ferrous  chloride, ferric sulfate,
and  ferrous sulfate.  Ferrous  chloride and  ferrous
sulfate  are  also available   as  byproducts  of
steelmaking operations (waste  pickle  liquor), although
these solutions may contain large quantities of free
hydrochloric  or sulfuric acid  which  can  cause
destruction  of alkalinity  and  pH  depression.
Characteristics of  iron salts used  for  phosphorus
precipitation are given in  Table 4-1 (3,4).

A  typical reaction  between   ferric chloride  and
phosphate can be approximated by (8):
         FeCI3  + PO43- -» FePO4 i + 3CI'
                                                                                               (4-5)
The mole ratio of Fe to P is 1:1. 162.3 g of FeCIa will
react with 95 g of  PC>4 to form  150.8  g of  FePC-4.
Stoichiometric weight ratio of Fe:P is 1.8:1, while the
weight ratio  of FeCIs to P  is 5.2:1. As with alum, the
reaction mechanism  is  more  complex  than  the
equation shown above.

The reaction between  ferrous salts (ferrous chloride
and  ferrous  sulfate)  and  phosphate can  be
approximated by:

      3FeCI2 + 2P043- -» Fe3(PO4)2 i + 6Cf  (4-6)

      3FeS04 + 2PO43- -» Fe3(PO4)2 i  +  3S042-
                                           (4-7)
                                                  56

-------
Table 4-1.   Characteristics of Aluminum and Iron Salts (3,4)
Common Name and
Formula
Dry alum
AI2(SO4)3»14H2O
Liquid alum
AI2(SO4)3»14H2O
Dry sodium aluminate
Na2AI204
Liq. sodium aluminate
Na2AI2O4
Liq. ferric chloride
FeCI3
Liq. ferrous chloride
FeCI2
Dry ferrous sulfate
FeSO4*7H2O
Shipping Data
Available
Forms
Lump
Ground
Rice
Powdered




Commercial;
waste pickle
liquor
Commercial;
waste pickle
liquor
Containers and
Requirements
Bags: 45,90 kg;
Bbl.: 135,180kg;
Drums: 11,45,110 kg;
Bulk - Car loads
Tank trucks
Store dry
Bulk - Car loads
Tank trucks
Bags: 23,45,68 kg;
Bulk: not available.
6 month max. storage.
Drums: 170 kg;
Tank truck;
Tank car;
2-3 month max. storage.
Carboys: 19,49 I;
Tank truks: 1 1 ,500-
15,000 I;
Tank cars: 1 5,000-
38,000 I
Drums: 1 90 I;
Tank trucks: 15,0001
Tank cars

Physical and Chemical Characteristics
Appearance and
Properties
White/cream color.
pH: 3.0-3.5 for 1-10%
solution.
Dust is irritant to mucous
membranes.
Will begin to crystalize @
-1°C;
Crystalizes @ -8°C.
Corrosive.
pH: 1 1 .9 for 1 % solution.
Non-corrosive.
Dust is irritant.
Strong alkali.
Handle as caustic.
Dark brown, oily.
pH: 2.0 for 1 % solution.
Very corrosive., stains
concrete and other
materials.
Dark brown, oily.
Free acid content typically
1 -1 .5% but may reach
10%.
Slightly less corrosive
than FeCI3
Acidic when dissolved.
Composition is variable.
Oxidizes in moist air.
Cakes @ storage temp.
above 20°C.
Bulk Density
(kg/cm)
600-1,200
1,330 @ 16°C
640-800

1,340-1,490
1,190-1,250
990-1,060
Commercial Strength
17% AI2O3 by wt.
8.3% AI2O3 by wt.
41-46% AI2O3 by
wt.
4.9-26.7% AI203
by wt.
35-45% FeCI3 by
wt.
20-25% FeCI2 by
wt.
55-58% FeSO4 by
wt.
In reality these reactions are more complex. The mole
ratio of Fe to P is 3:2. Weight ratio of ferrous ion to
phosphorus is 3.2:1.

Addition of iron salts will result in the  destruction of
alkalinity as described by:
     FeCI3 + 3HCO3' -» Fe(OH)3
+ 3CO2 + 3d'
            (4-8)
Iron salts  are most  effective  for  phosphorus
precipitation within  a certain  pH  range.  For ferric
(Fe3 + ) ion, the optimum  pH range is 4.5-5.0.
However,  significant removal of phosphorus can  be
achieved at higher  pH. For ferrous (Fe2 + )  ion, the
optimum pH is  approximately 8.  Good phosphorus
removal can be achieved between pM values of 7 and
8.  Canadian  studies  have  shown that effective
phosphorus precipitation does not occur until  the
ferrous ion is oxidized to ferric ion, and for this reason
do  not  support  the  use of  ferrous salts  in  primary
treatment  (9). However, both ferrous  chloride and
ferrous sulfate have  been  used effectively in primary
treatment (3,10).
4.2 Application Points

The most common points for addition of aluminum
and  iron  salts for  phosphorus  removal  are:  1)
immediately upstream of the  primary clarifier, 2) in or
immediately  after  the aeration  basins  prior to final
clarification,  and 3)  at  both  points  simultaneously.
Another option is  use of separate, tertiary chemical
clarification.  Such a  scheme  would  only  be justified
for very stringent effluent discharge standards,  as for
reuse.

Figure  4-1  shows  the  common  schemes  for
chemical addition  in  an activated sludge plant. The
advantages of addition to primary treatment include
greater  opportunity for adequate  mixing and
flocculation,  and reduced loadings  to downstream
processes as  a result  of improved BOD and  SS
removal. The major disadvantage of chemical addition
to the  primaries  is that incomplete phosphorus
precipitation  may result  because of  the presence of
phosphorus forms other  than orthophosphate that are
not easily precipitated.
                                                 57

-------
Figure 4-1.   Alternative schemes for mineral addition for phosphorus removal.
                    Flocculant
                       Aid

Influent "^
Rapid
Mix
^ hi

         Al or Fe I                   ±
                        ^	Y.
                   Sludge to Processing
                                                        Aeration
                                                         Basin
                                         a. Mineral addition in primary treatment
    Influent
                                                                         Flocculant
                                                                           Aid

t '
A
l
Item
t
1
ative
Aeration
Basin
t
t
Ki
t
1 1
mineral addition points
H
                                      Effluent
                   Sludge to Processing
                    Flocculant
                       Aid
                                         b. Mineral addition in secondary treatment

Influent ""
Alor

Rapid
Mix

i
Fe i
T ^/ Pnmarv ] ^
"\ Clanfier / ^ i
i
k


t
1
[ Alternative
^ 	 _t 	 . 	
Aeration
Basin
t
1

t
1
J s
t

"\ Cl<
V
mineral addition points


                                                                                   Sec.
                                                                                            Effluent
                   Sludge to Processing
                                         c. Multiple point mineral addition
In general, higher levels of phosphorus  removal can
be  achieved by chemical  addition to  the  secondary
process  or by  addition  at  multiple  points  in the
treatment train.

As  discussed  in  Chapter 2, adequate wastewater
characterization and jar testing are essential before
implementing a chemical addition program.

Table  4-2,  compiled  based on  a  survey of  104
plants in the U.S. and Canada, shows a breakdown of
plants by location of chemical addition and by cation
used for precipitation (1).

4.2.1 Mineral Addition Before Primary
Clarification
Phosphorus removal  by addition  of  mineral salts  in
primary  treatment  requires   good  mixing  and
flocculation in order to  ensure optimum  results. With
proper design and operation of mixing and flocculation
systems, 70-90 percent phosphorus removal can  be
achieved in primary treatment. Significant increases in
BOD  and  SS removal efficiencies  can  also  be
expected from  mineral salt addition. Table  4-3
provides a  summary of potential removal efficiencies
of P,  BOD,  and SS  in  primary  and secondary
treatment with and without mineral addition (3).

For mineral addition to primary treatment, provision of
a  separate  rapid  mix tank  may be necessary.  As
discussed   in  Section  4.2.4,  existing  hydraulic
structures   such  as  Parshall  flumes and   drop
manholes have  been used,  but  may  not provide
sufficient turbulence  to ensure complete and intimate
mixing of the chemical  with  the  wastewater.  Good
performance  has  been reported  in  Canada  by
injection into  the discharge side  of  raw  sewage
pumps, addition to aerated grit chambers, preaeration
                                                   58

-------
Table 4-2.   Distribution of Selected Phosphorus Removal Facilities by Point of Chemical Addition and Cation Used (1)

                                                       Number of Plants
Point of
Addition
Primary
Secondary
Tertiary
Total
United States
Al
1
26
2
29
Fe
16
6
2
24
Total
17
32
4
53
Al
2
17
1
20
Canada
Fe
20
8
0
28

Total
22
25
1
48

Al
3
43
3
49
Total
Fe
36
14
2
531

Total
39
57
5
102
 1 One plant does not specify point of addition.
Table 4-3.    Potential effectiveness of Primary and Secondary Treatment With and Without Mineral Addition for Phosphorus
            Removal
                         Phosphorus Removal (%)
 SS Removal (%)
   BOD Removal (%)

Primary Treatment
Secondary Treatment
Trickling Filter
Activated Sludge
Without
5-10
10-20
10-20
With
70-90
80-95
80-95
Without
40-70
80-90
80-95
With
60-75
85-95
85-95
Without
25-40
75-90
85-95
With
40-65
80-95
85-95
channels, or Parshall flumes, and addition to pipes or
channels between  primary  clarifiers  and  aeration
tanks if  supplemented with  mechanical or air mixing
(11,12).

Initial mixing intensity is  very important for complete
dispersal  of  the  coagulant  and,  thus,  maximum
efficiency. Flocculation  normally occurs  naturally in
the  primary  clarifier,  particularly in the center  feed
well, which may  preclude the  need for a  separate
flocculation basin. New clarifiers can be designed with
mixers and a center flocculation well with as  much as
30  minutes  detention time.  If necessary,  existing
clarifiers  can be  modified  to  provide  a designated
flocculation zone.

Due to competing reactions  and variation in coagulant
demand,  more chemical  will generally be required for
phosphorus precipitation  in  primary treatment than in
secondary or tertiary treatment. This can be seen in
Figure 4-2, which shows phosphorus  removed  per
mole of aluminum added  for three different application
points (3).

4.2.2 Mineral Addition to Secondary Processes
Addition   of aluminum or iron  salts directly to  the
aeration  basins or between the aeration basins and
final  clarifiers  is  common practice for chemical
precipitation  of  phosphorus.  This  alternative  has
considerable  flexibility  in  the point  of chemical
addition,  allowing  modifications  of the injection point
to ensure use  of the best available conditions for
coagulation and flocculation to  occur.  Unfortunately,
the  approach has some drawbacks, in that velocity
Figure 4-2.  Impact of point of addition on effectiveness of
           phosphorus removal using aluminum (3).
 Moles Tot. Sol. P Rem. per
 Mole Aluminum Added

    1-2 i-
    1.0
    0.8
    0.6
    0.4
   0.2
A Final Effluent
O Aerator
• Raw Wastewater
                   Moles Aluminum Added per
                     Mole Initial Tot. Sol. P
                                                    59

-------
gradients or turbulence levels  are  likely to be less
than ideal for proper mixing and flocculation to occur.
Since the optimal point of chemical addition will vary
depending  on the choice of chemicals,  velocity
gradients in  the  aeration  basin  and  inter-basin
channels, and wastewater characteristics,  full scale
experimentation  with  various points of addition will
likely be necessary. If a high degree of  phosphorus
removal  is  required,  mineral addition  should  occur
downstream of any return streams  such  as digester
supernatant.   Addition of  minerals  to  secondary
processes  may  result in an increase in  dissolved
solids in the effluent, particularly when pickling liquors
or other "impure" chemical sources are used.

4.2.3 Mineral Addition at Multiple Points
Addition of mineral salts at  multiple locations in the
treatment plant has been found  to be an efficient and
cost-effective means  of  chemical  addition  for
phosphorus control. Advantages of this approach are
overall reduction in  chemical requirements to achieve
a given effluent  phosphorus objective and  increased
operational  flexibility.  In  design of  new  facilities,
provision of  multiple chemical  addition  points  is
recommended to allow optimization of the chemical
feed system  to achieve  the most economical and
reliable solution.

It should be noted that, when aluminum or iron salts
are  used for  phosphorus  precipitation,  addition  of
small amounts of a coagulant aid  such as anionic
polyelectrolytes may  be  necessary before  the final
clarifier  to  assist  in  removing  dispersed metal-
phosphate floe. A typical polymer dose when used as
a coagulant aid is 0.1-0.25 mg/l (8).


4.3 Performance
Table 4-4  shows  performance data  from  selected
facilities  using various  mineral salts  and  points  of
addition  to achieve  phosphorus  removal  (13).   In
general,  70-90 percent  phosphorus removal can  be
expected  in  primary  treatment, with   removal
efficiencies in secondary treatment ranging from 80 to
95 percent.

Dosages can  be  expected to vary  widely depending
on choice of chemical and wastewater characteristics,
as  well as other factors  such  as degree  of mixing
intensity  at the point  of addition  and opportunity  for
flocculation. Table 4-5 shows a summary of dosages
employed  during  full-scale  studies  at  numerous
wastewater treatment  plants (14). The  dosages cited
are  those  required to achieve a  total  phosphorus
concentration of 1 mg/l in the plant effluent.


4.4 Equipment Requirements
4.4.1 Chemical Handling and Storage
As  seen in Table  4-1,  a variety of chemicals are
available for  precipitation of  phosphorus  from
wastewater.  Each  chemical  has  characteristic
requirements regarding type and maximum duration of
storage,  choice  of piping  and  transport  systems,
chemical feeding equipment, and safety precautions.
Chemical handling and storage  requirements  for
common chemicals used in phosphorus control  are
described below.

a. Aluminum Salts
Aluminum sulfate is available in dry or liquid  form. Dry
alum  or  "filter  alum" can  be  purchased  in  lump,
ground,  rice, or powdered  grades. Water utilities
prefer ground or rice  alum  because of superior flow
characteristics.  Bulk  alum should  be  stored in  mild
steel or concrete bins with dust collection equipment.
Gates should be provided on bulk  storage vessels to
allow isolation of feed equipment.

A typical bulk storage tank for dry chemicals is shown
in Figure 4-3. Bulk dry alum can be transferred with
screw  conveyors,  bucket elevators,  or pneumatic
conveyors.  Bags and drums of  alum should  be stored
in  dry locations. Day hoppers receiving alum  from
bags  or  drums  should have   a  minimum storage
capacity  of eight  hours at the maximum  expected
feed rate. Hopper  bottoms should have a  minimum
wall slope of 60 degrees to prevent arching.

Dry alum is not corrosive unless it absorbs  moisture.
Alum dust,  however,  can cause minor irritation of the
eyes and respiratory tract.

Liquid  alum is  available in  11-19 m3  (3,000-5,000
gal) tank truck  lots or 26-68 m3  (7,000-18,000 gal)
tank car lots. Transportation  costs  are greater for
liquid  alum since it  is nearly  half water by weight.
Liquid alum will generally be more economical  than
dry alum if the point of use is within 160 km (100 mi)
of  the manufacturing  location.  However, because of
the ease of handling, storage,  and feeding in  liquid
form,  the practical  limit for transport may be 320 km
(200 mi)  or more (3).

Alum is typically stored without  dilution at the shipping
concentration received  at the  plant.  Storage  tanks
located  outside should  be  closed and  vented,  with
provisions for heating to maintain temperatures above
-4°C  (25°F)  to  prevent crystallization.  Materials of
construction for  liquid alum  storage vessels include
type 316 stainless steel, fiberglass-reinforced plastic
(FRP), or steel lined with rubber, polyvinyl chloride
(PVC), or lead. Liquid alum can be stored indefinitely.
Storage  tanks should be  sized to accommodate a
10-day to 2-week  supply and  should be capable of
handling  1-1/2 times  the maximum quantity shipped.

Liquid  alum is  moderately  corrosive,  and  hand and
face protection should  be worn  when  working on
leaking equipment. Any  spills should be immediately
flushed  with  water as  liquid  alum becomes   very
slippery upon evaporation (3).
                                                  60

-------
Table 4-4. Performance of Facilities Using Mineral Salts for Phosphorus Removal (11)
Plant Type
and Location


Plug Flow AS
Waupaca, Wl
East Chicago, IN

Mason, Ml

Flushing, Ml

Appleton, Wl
Grand Ledge, Ml
Bowling Green, OH

Kenosha, Wl
Toledo, OH

Clintonville, Wl
Complete Mix AS
Thiensville, Wl

Two Harbors, MN
Escanaba, Ml

Sheboygan, Wl
Lima, OH

Miles, Ml
Crown Point, IN

Cedarburg, Wl

Contact Stabilization AS
Neenah, Wl
Neenah, Wl
Algoma, Wl

Grafton, Wl
Port Washington, Wl
Port Clinton, OH
Oberlin, OH
North Olmstead, OH
Pure Oxygen AS
Fon du Lac, Wl

Extended Aeration AS
Aurora, MN
Upper Allen, PA

Corunna, Ontario
Saukville, Wl
Plymouth, Wl
Trenton, OH
Seneca, MD

Design
Flow
m3/d


4,760
75,700

5,700

4,400

62,500
5,700
30,300

106,000
386,100

3,800

900

4,500
8,300

69,600
70,000

22,000
13,600

11,400


5,700
14,800
2,800

8,100
4,700
5,700
5,700
34,000

41,600


1,900
1,800

3,800
7,600
6,200
13,200
18,900

Average
Flow
m3/d


2,200
59,800

5,000

6,000

52,200
3,000
20,100

90,500
310,400

2,700

3,300

3,400
7,600

46,600
15,100

12,100
8,700

7,600


4,000
16,700
3,000

3,600
5,800
6,400
5,700
21,200

26,900


1,700
1,200

2,000
2,400
5,800
9,600
15,100


Chemicals



Alum
Alum
Polymer
Ferric Chloride
Polymer
Ferric Chloride

Ferrous Chloride
Ferrous Chloride
Ferrous Chloride
Polymer
Ferrous Sulfate
Ferrous Sulfate
Polymer
Ferrous Sulfate

Alum
Polymer
Alum
Feme Chloride
Polymer
Ferric Chloride
Ferrous Chloride
Polymer
Ferrous Chloride
Ferrous Chloride
Polymer
Ferrous Sulfate
Polymer

Alum
Alum
Ferric Chloride
Polymer
Ferrous Chloride
Ferrous Chloride
Ferrous Chloride
Ferrous Chloride
Sodium Alummate

Alum
Polymer

Alum
Alum
Polymer
Alum
Ferrous Chloride
Ferrous Chloride
Ferrous Chloride
Sodium Alummate
Polymer
Chemical
Feed Point



Sec. Clarifier
Sec. Clarifier
Sec. Clarifier
Prim. Clarifier
Prim. Clanfier
Sec. Biol. Process
Sec. Biol. Process
Plant Influent
Sec. Biol. Process
Sec. Clarifier
Sec. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Sec. Clarifier

Sec. Biol. Process
Sec. Biol. Process
Sec. Clarifier
Prim. Clanfier
Prim. Clanfier
Sec. Clarifier
Prim. Clarifier
Prim. Clarifier
Sec. Biol. Process
Sec. Clarifier
Sec. Clarifier
Sec. Clarifier
Sec. Clarifier

Prim. Clanfier
Sec. Biol. Process
Prim. Clanfier
Prim. Clanfier
Prim. Clarifier
Prim. Clarifier
Sec. Biol. Process
Prim. Clarifier
Sec. Biol. Process

Sec. Clarifier
Sec. Clarifier

Prim. Clarifier
Sec. Biol. Process
Sec. Biol. Process
Sec. Clarifier
Prim. Clanfier
Sec. Biol. Process
Sec. Biol. Process
Plant Influent
Sec. Clarifier
Chemical
Dosage
mg/l as
Metal Ion

24.6
7.7
1.0
9.1
0.05
5.3
0.15
16.8
5.6
5.2

5.35
3.6

5.3

9.3
0.82
9.6
4.7
0.35
10.2
13.2
0.07
10.9
11.0
0.94
9.9


7.7
4.1
33.0
0.07
16.2
8.5
10.2
6.4
8.3

8.5
0.75

16.9
8.2
0.37
5.0
10.3
7.7
2.56
4.3
2.4
Metal Ion:
Inf. TP



3.25
3.99

1.4

1.56

1.6
1.24
0.62

1.43
1.3

1.47

2.46

1.6
1.04

1.6
3.38

2.66
2.0

2.99


2.2
1.0
10.0

2.31
1.44
1.96
1.08
2.86

1.18


5.83
0.92

0.65
1.61
1.15
0.42
0.61

Inf.
TP
mg/1


7.56
1.93

6.5

3.4

10.5
4.5
8.4

3.74
2.76

3.6

3.78

6.0
4.5

6.38
3.9

4.1
5.5

3.31


3.5
4.1
3.3

7.0
5.9
5.2
5.9
2.9

7.2


2.9
8.9

7.74
6.4
6.7
6.1
7.1

Eff.
TP
mg/l


0.86
0.38

0.88

0.48

0.8
0.7
0.75

0.36
0.35

0.75

0.29

0.25
0.82

0.9
0.5

0.7
0.7

0.67


0.7
0.8
0.23

0.69
1.0
0.5
1.0
0.7

0.73


0.76
2.0

0.36
0.59
0.77
0.65
1.6

61

-------
Table 4-4. Performance of Facilities Using Mineral Salts for Phosphorus Removal (continued)
Plant Type
and Location


Step Aeration AS
Fort Wayne, IN
East Lansing, Ml

Oak Creek, Wl
Elkhart, IN
2-Stage Nitrification AS
Piscataway, MD

High Rate TF
Geneva, OH
Coldwater, Ml

Oconto Falls, Wl
Kendalville, IN

Standard Rate TF
Willard, OH

Elizabethtown, PA

Durand, Ml
Saglnaw, Ml

Little Hunting Creek, VA

Bay City, Ml

Coloma, Ml
RBC
Romeo, Ml

Chesaning, Ml

Negaunee, Ml

Dexter, Ml

Hartford, Ml

St Johns, Ml

Charlotte, Ml

Oxidation Ditch
Lapeer, Ml
Portage, IN
Design
Flow
m3/d


227,100
71,200

454,200
75,700

113,600


7,600
8,700

1,900
10,100


5,100

11,400

3,000
16,700

17,000

75,700

8,300

6,100

2,200

6,100

2,200

1,300

7,200

4,500


7,000
13,200
Average
Flow
m3/d


170,100
42,800

340,650
60,200

54,900


3,900
7,400

1,400
7,600


4,800

6,500

2,700
6,400

14,400

33,300

5,300

3,300

2,000

3,300

800

800

6,300

2,700


7,200
8,400

Chemicals



Ferrous Chloride
Ferrous Chloride
Polymer
Ferrous Sulfate
Ferrous Sulfate

Alum
Polymer

Alum
Ferric Chloride
Polymer
Ferric Chloride
Feme Chloride
Polymer

Alum
Polymer
Alum
Polymer
Ferric Chloride
Ferric Chloride
Polymer
Ferric Chloride
Polymer
Ferric Chloride
Polymer
Ferrous Chloride

Alum
Polymer
Ferric Chloride
Polymer
Ferric Chloride
Polymer
Ferric Chloride
Polymer
Ferrous Chloride
Polymer
Ferrous Chloride
Polymer
Ferrous Chloride
Polymer

Ferric Chloride
Ferrous Chloride
Chemical
Feed Point



Sec. Biol. Process
Sec. Clarifier
Sec. Clarifier
Sec. Biol. Process
Sec. Clarifier

Sec. Clarifier
Sec. Clarifier

Sec. Clarifier
Sec. Clarifier
Sec. Clarifier
Sec. Biol. Process
Sec. Biol. Process
Sec. Biol. Process

Prim. Clarifier
Prim. Clarifier
Sec. Clarifier
Sec. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Sec. Clarifier
Sec. Clarifier
Prim. Clarifier

Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Sec. Clarifier
Sec. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Prim. Clarifier
Sec. Clanfier

Sec. Clarifier
Sec. Clarifier
Chemical
Dosage
mg/l as
Metal Ion

4.3
5.9
0.05
4.4
1.6

8.8
3.8

12.1
8.3
0.1
8.81
14.7
0.25

6.3
0.14
12.8
0.4
11.2
9.6
0.1
42.5
2.8
9.5
0.29
4.1

7.1
0.77
9.0
0.4
7.5
1.0
10.2
0.5
13.0
0.6
5.01
0.04
13.7
0.18

4.65
9.9
Metal Ion:
Inf. TP



0.54
1.11

0.96
0.63

1.44


4.03
2.02

2.4
4.05


1.21

2.51

2.2
0.99

4.57

2.07

1.71

2.4

3.46

3.75

2.0

3.25

1.38

2.45


0.88
1.65
Inf.
TP
mg/l


7.9
5.3

4.6
2.56

6.13


3.0
4.1

3.67
3.63


5.2

5.1

5.1
9.7

9.3

4.6

2.4

2.96

2.6

2.0

5.11

4.0

3.7

5.6


5.3
6.0
Eff.
TP
mg/l


0.67
0.9

0.54
0.83

0.2


0.4
0.88

0.45
0.35


0.82

1.7

0.83
1.5

0.2

0.5

0.65

0.46

0.6

0.95

0.46

0.75

0.5

0.68


1.2
1.5
62

-------
Table 4-5.
 Point of
 Addition
Chemical  Dosage Summary  from Ontario
Treatability Studies (14)
     Chemical
               Ave. Metal
Number    Ave.    lon/TP
of Plants Dosage a.b   Ratio
                                     mg/l
Raw
wastewater
Mixed liquor

Feme chloride
Alum
Ferric chloride
Alum
7
5
20
15
14.2
10.3
9.5
7.5
2.7
1.7
1.5
1.6
 a Dosage required to achieve effluent TP of 1 mg/l.
 b Expressed as Fe or Al.
Sodium aluminate is  available  in both dry and liquid
forms (see Table 4-1). Dry sodium aluminate should
be stored for a maximum  of six months at 16-32°C
(60-80° F) and will  deteriorate  with  exposure to the
atmosphere.  Hopper agitation  may be required to
prevent caking and bridging. Storage vessels may be
mild or stainless  steel, FRP,  or concrete. Use of
copper and its alloys, rubber,  and aluminum should
be avoided. Maximum recommended storage time for
liquid sodium aluminate is two to three months (4).

Sodium aluminate  should  be  treated  as a caustic
similar to  sodium hydroxide. Body contact should be
prevented, and hand and  face  protection must be
worn when working on sodium aluminate storage or
feed equipment.

b. Iron Salts
Iron  salts  discussed  here include ferric chloride,
ferrous  chloride,  and  ferrous sulfate,  which are the
most common iron compounds used for phosphorus
removal. Other iron salts such as ferric sulfate  can
also be employed for  precipitation of phosphorus.

Ferric chloride is available  as a liquid in carboys  and
in bulk, as shown in Table 4-1. Tank trucks and tank
cars are usually unloaded  pneumatically. Designated
safety  procedures should be closely followed during
loading  and  unloading  operations. Ferric chloride
storage tanks may  be constructed of steel lined  with
rubber or plastic, FRP,  or  synthetic resins.  In most
cases, ferric  chloride should  be stored  in heated
buildings or in heated tanks to  prevent crystallization.
Liquid ferric chloride can be stored indefinitely without
deterioration. Ten to  14 days of storage capacity is
recommended, with the  ability  to handle 1-1/2 times
the largest anticipated shipment (3).

Ferric chloride is a  corrosive material.  When working
on  ferric  chloride handling  equipment, workmen
should  wear  rubber  gloves,  rubber  aprons,   and
goggles or a  face  shield.  Any contact with eyes or
skin  should be flushed with running water. If ingested,
vomiting should be induced.
Ferric chloride will stain concrete and other materials.
To  prevent staining in areas where ferric chloride is
handled, rubber mats or resistant coatings should be
used.

Ferrous chloride, or  waste  pickle  liquor,  is a
byproduct of steelmaking operations and is available
in bulk  tank car or tank truck lots.  The free  acid
content may vary from 1 to  10 percent but is usually
1-2 percent. Although  slightly  less  corrosive than
ferric  chloride,  ferrous chloride generally  has  the
same  storage  and handling  requirements.  Since
pickle liquor  may  not  be available on a continuous
basis,  storage  and  handling  facilities  should  be
suitable  for accommodating  ferric chloride  as  an
alternate chemical.

Ferrous  sulfate  is also a byproduct of steelmaking
operations, although the product is normally  sold in
the dry  form as granules, crystals, powder, or lumps.
Composition  may  be variable  but  typically contains
55-58  percent  FeS04-  Dry  ferrous  sulfate  will
oxidize  and hydrate  in  moist air  and  will cake  at
temperatures above 20°C (68°F). In  the dry form, it
should   be  stored  in  cool  dry  areas.  Storage
containers may be constructed of concrete, synthetic
resin, or steel  lined  with asphalt, rubber,  PVC,  or
chemically resistant resins (3,4). Ferrous sulfate dust
is irritating to the eyes and respiratory tract.

Ferrous  sulfate solution  is  acidic and should  be
handled with the same precautions that apply to ferric
chloride. Construction  materials for storage vessels
for ferrous sulfate solutions are the  same as those for
ferric chloride solutions.

c. Polymer
While polymer is not used specifically for phosphorus
precipitation, its use in  conjunction with aluminum and
iron salts is  so common as  to warrant a separate
discussion. Small  quantities of  polymer are  typically
added just downstream of the metal addition point to
assist in the agglomeration and  settling of the  metal-
phosphate floe.  A minimum lag time of 10 seconds
(flow time)  is  recommended  between  the point  of
metal addition  and the polymer injection point (14).
Some designers have  suggested lag  times of two to
five minutes (15).

A multitude of polymers are available in dry or liquid
form. Dry polymer is shipped in a variety of packages
and  containers,  depending on the  manufacturer.
Bagged  dry polymer  should be stored  in cool, low
humidity areas.  Bags  should  be removed in proper
rotation  to prevent excessive storage times. Polymers
are generally low in toxicity and are  not irritating.

Polymer is  added  to a process in  the solution form,
requiring blending of dry polymer with water to form a
stock solution, followed by an aging period. The stock
solution is usually diluted prior to use.  Liquid polymers
                                                   63

-------
Figure 4-3.  Typical dry chemical feed system.
Dust
Collector
n
Bulk
Fill Pif
(Pneume
Storage
Bin
                                                                                      Dust
                                                                                     Collector
                                                                           Screen
                                                                             with
                                                                           Breaker
                             Flexible
                            Connection
                                                                                                 Bag
                                                                                                /Fill
                                                                                        Day Hopper for
                                                                                        Dry Chemical
                                                                                         from Bags
                                                                                          or Drums
                                                                                                _LJ
                                      Alternative Supplies Depending on Storage
                                Control  Solenoid
                                Valve   Valve
require no aging  but are normally diluted with  water
before application.

Polymer  solutions are  typically stored in FRP,  type
316  stainless  steel,  or plastic  lined steel tanks. To
prevent deterioration,  polymer  solutions  should be
stored no longer than 1-3  days.  Check with the
manufacturer  for recommendations  for  the  specific
product.

Instantaneous  blending polymer systems may have
application for  temporary or intermittent  use
situations. These systems automatically meter, dilute,
activate,  and feed liquid polymer and water  and do
not require separate storage,  holding,  and mixing
tanks.
4.4.2 Dry Chemical Feeding and Dissolving
Dry chemical feed equipment can be of three types:

• volumetric
•  loss-in-weight  gravimetric
• belt gravimetric

Volumetric  feeders are the least expensive and can
be used where cost is a concern, chemical delivery
rates  are  low,  and great accuracy  is not required.
Volumetric  feeders  generally employ  a  screw  feed
mechanism.

Loss-in-weight  gravimetric  feeders  provide  a  high
degree  of  accuracy   (1  percent)  and  are
recommended  where close  control of  chemical
                                                  64

-------
dosages can result in substantial savings in chemical
costs.  Maximum  feed  rates of  such  units are
approximately 1,800 kg (4,000 lb)/hr.

Belt gravimetric feeders  are intermediate in cost
between volumetric and  loss-in-weight gravimetric
feeders, and can provide  accurate  and reliable
service.

In general, closed construction  is  preferable  for
chemical feeders,  since this exposes a minimum  of
operating components to  the corrosive vapors from
the dissolving or solution  tank. The various types  of
chemical feeders  available  are shown  in Table 4-6
(4).

Gravimetric feeders offer the following advantages
over volumetric feeders:

1. Calibration is normally not required.
2. Greater accuracy and dependability.
3. Incorporation  of  totalizer  to allow maintenance  of
   accurate records and inventories.
4. Automatic proportioning.
5. Low maintenance; simple  operation.

When dry chemicals are used, a working solution is
made up by blending  water with the chemical in a
mechanically-agitated  dissolving  tank or  solution
tank.  With  bulk chemicals,  such  systems  employ a
water meter in conjunction with a variable rate feeder
to achieve  a continuous stream of the solution at the
proper strength. With bags or containers,  the  proper
solution is made up manually on a batch basis.

With  alum  or sodium  aluminate, the recommended
minimum solution strength is 6 percent or 0.06 kg/liter
of water (0.5 Ib/gal). The  detention  time  in the
dissolver should be 5 minutes at the maximum feed
rate.  The  same  recommendations  are  made  for
dissolution  of dry  ferrous sulfate.  For ferric  sulfate,
feed solutions are  made up at a water to chemical
weight ratio of 2:1 to 8:1, with a typical ratio being 4:1
or 0.25  kg Fe2SC>4/liter of water (2.1 Ib/gal). Solutions
having strengths less than  1  percent are subject  to
hydrolysis and deposition of ferric hydroxide.

A typical arrangement for the feeding and dissolving
of dry chemicals is shown in Figure 4-3. It should be
noted that the degree of automation in  dry chemical
dissolution  systems will depend on  the size  of the
plant and daily chemical usage.

For plants  less than 3,785  m3/d  (1 mgd),  manual
preparation of the chemical solution on a batch basis
may be  indicated.  This is  typically accomplished in a
day  tank  in  which  dry,  bagged  chemical   is
mechanically mixed with  water to  reach the  desired
concentration. For  larger  facilities,  the  chemical
solution  is  prepared automatically  using a controller
which adjusts  feed  rate of dry chemical in proportion
to potable water flowrate (16). A system of this type is
depicted in  Figure 4-3.

4.4.3 Liquid Chemical and Solution Feeding
Several alternatives  are  available for  feeding  liquid
chemicals or chemical solutions.  The pressure head
often  determines the type  of  system  to  be  used.
Rotary  dipper feeders or  rotameters  with  control
valves  are  commonly  used  for gravity  feed
applications,  while  metering pumps are  used  for
feeding  chemical solutions under pressure.

Although provision is sometimes made for dilution of
liquid  alum or ferric chloride prior to feeding  into  the
process, this is generally unnecessary, and  may be
undesirable  due to the  occurrence  of  hydrolysis at
dilute  concentrations.  It has been found that  feeding
undiluted liquid alum results  in better coagulation and
settling (3).  For  polymers, dilution  of  the  stock
solution is  generally  practiced  to  allow  better
dispersion of the polymer in the wastewater.

Figure  4-4  shows  typical  chemical  feed
arrangements for elevated chemical  storage systems,
while  Figure 4-5  shows  alternatives for  ground
storage.  Rotary  dipper feeders are reliable  feeders
that are commonly used for gravity  flow applications.
Feed  rates can be  varied based  on a signal from a
mainstream  flow meter (flow proportional control) as
discussed  later  in  this  section.   Rotameters  in
conjunction with  control valves may also be used for
small  applications  where  frequent  variation  in
chemical feed rate is not required. Rotameters should
not be used with ferric chloride or other iron solutions
since the sight glass will become stained and opaque.

Centrifugal transfer pumps,  as shown in Figure 4-5a,
should be direct connected  but not close-coupled to
prevent leakage into the motor. Pump components for
liquid  alum  service should  be constructed  of 316
stainless steel,  FRP, or plastics.  For ferric chloride,
graphite or rubber  lined pumps  with Teflon seals  are
recommended. Metering  pumps are typically of  the
positive  displacement type, either  diaphragm or
plunger. Diaphragm pumps  protected with internal or
external relief valves are  preferred.  A back pressure
valve is recommended to provide positive check valve
operation  (3). Materials of construction for chemical
feed  service include 316  stainless  steel,  FRP,
plastics, and rubber. Manufacturers recommendations
should  be followed  regarding  selection  of pump
materials for the specific chemical of interest.

For pipes transporting alum solution, use of  FRP,
PVC,  or other  plastics  is recommended.  Valves
should be plastic, 316 stainless steel, or rubber-lined
iron or  steel. For  ferric chloride  conveyance,  pipes
should be constructed of steel lined  with rubber  or
Saran, FRP, or plastics.  Valves should be rubber- or
resin-lined diaphragm valves, Saran-lined  valves
with  Teflon diaphragms,  rubber-sleeved  pinch
                                                  65

-------
Table 4-6.    Types of Chemical Feeders (4)
 Type of Feeder
                                                                                           Limitations
                     Use
                                                   Capacity
                                                                                                     Range
 Dry feeders
   Volumetric:
     Oscillating plate
     Oscillating throat (universal)
     Rotating disc
     Rotating cylinder (star)


     Screw
     Ribbon
     Belt


   Gravimetric:
     Continuous - belt and scale
     Loss in weight
 Solution feeders
   Nonpositive displacement:
     Decanter (lowering pipe)
     Orifice
     Rotameter (calibrated value)
     Loss in weigth (tank w/control
     valve)
   Positive displacement:
     Rotating dipper
   Proportional pump:
     Diaphragm
     Piston
Any material, granules or powder.
Any material, any particle size.
Most materials including NaF, granules or powder.
Any material, granules or powder.
Dry, free flowing material, powder or granular.
Dry, free flowing material, powder, granular or lumps.
Dry, free flowing material up to 1.5-in size, powder or
granular.
Dry, free flowing granular material, or floodable material.
Most materials, powder, granular or lumps.
Most solutions or light slurries.
Most solutions.
Clear solutions.


Most solutions.



Most solutions or slurries.


Most solutions. Special unit for 5% slurries.1
Most solutions, light slurries.
                                                                                     liters/h
 0.3 - 1,000

0.06 - 2,800

  0.3 - 28

230 - 57,000
     or
 200 - 8,500
  1.4 - 510

 0.06 - 4.5

2.8 - 85,000
  0.6 - 57

 0.6 - 2,300
  0.3 - 280

  4.5 - 142

  0.1 - 4.5
     or
  0.3 - 570

  0.06 - 5.7
  2.8 - 850


  0.1 - 4.2
 0.3 - 4,800
40 to 1

40 to 1

20 to 1

10 to 1
  or
100 to 1

20 to 1

10 to 1

10 to 1
  to
100 to 1


100to 1

10010 1
10010 1
 10 to 1
 10 to 1


 30 to 1



100 to 1


100 to 1
 20 to 1
  1 Use special heads and valves for slurries.
valves, or plastic ball valves (3,4). Pipe selection for
polymer service  should  be made after  the type  of
polymer has been determined. Plastic pipe or  type
316 stainless steel is normally used.

4.4.4 Chemical Dosage Control
Control of chemical  feeding is  a  critical part of any
phosphorus  removal  system.  Control of  chemical
dosages is important not only to ensure that effluent
phosphorus  requirements  are consistently  met,  but
also to keep chemical use and operating costs  to  a
minimum.  As discussed  in  Chapter 2, phosphorus
loadings  to  a  plant can  be  expected to  fluctuate
significantly  on  an hourly, daily, and even seasonal
basis.

The type and complexity of selected control systems
are  dependent  on  plant size  and  sophistication  of
operations, as well as daily chemical  usage. For small
plants  with  low  chemical  requirements,  a  complex
                         automated control system cannot be justified on  the
                         basis of either economics or  practicality. For  large
                         plants,  however,  close  control  of chemical  dosage
                         can  result in substantial savings  in  chemical costs,
                         and  a more sophisticated  control  system would be
                         within the  operation and maintenance  capabilities of
                         the plant staff. Several control options  are discussed
                         below.

                         a. Manual  Control
                         Manual dosage control may be appropriate for plants
                         less than 3,785 m3/d (1 mgd).  Manual  operation of  a
                         chemical  feed   system  would  involve:  1)  daily
                         preparation of  the chemical solution on a  batch  basis
                         (if dry  chemicals are  purchased), and  2)  manual
                         setting of a control valve or the stroke of a diaphragm
                         metering  pump  to establish  proper flowrate  of
                         chemical solution. Although such a system is reliable
                         and requires  little  maintenance,  it  has  a  major
                         disadvantage in  that chemical  feed rate  is constant
                                                       66

-------
Figure 4-4.  Liquid chemical feed alternatives for elevated
           storage.
     Rotary dipper feeder

a. Rotary dipper feeder
                                    Figure 4-5.   Liquid chemical feed alternatives for  ground
                                                storage.


Recirculation
Ground
chemical
storage
tank

JS

r
*ft|4
Rotary dipper
feeder

To process
(gravity
feed)
                                                                           a Rotary dipper feeder
        Elevated
        chemical
        tank
                               Control
                               valve
                                         To process
                             1
                Rotameter (or mag meter)

                   b. Rotameter with control valve
        Elevated
        chemical
        storage
        tank
           Relief
           valve
                                Y
                                nr
                                 ,
Back pressure
valve
                      To process
  Metering pump

c. Metering pump
                                                                  Rotameter (or mag meter)
                                                                         Control
                                                                         valve
                                                                     I—Xh-
                                                                                To process
                                                                                (pressure
                                                                                feed)
                                                        Centrifugal transfer pump

                                             Centrifugal pump with rotameter and control valve
                                                                       Back pressure
                                                                       valve
                                                                      tx-
t
                                                                                                   To process
                                                                                                   (pressure
                                                                                                   feed)
                                                                           c. Metering pump
 and plant flow  is variable,  resulting in variation in
 dosages. This  problem  can  be overcome  to  some
 degree by manually varying the chemical feed rate at
 specified  intervals  based on historical flow and
 performance  data (17).  However,  the  potential for
 overdosing or  underdosing  exists.  At  plants  where
 flows  are  generally  predictable,  this  problem is
 minimal.  At others,  such as those with significant
 infiltration/inflow, operational  schedules should  reflect
 the need to adjust rates during initial periods.

 b. Flow Proportional and Programmed Control
 Flow  proportional  control involves  automatic
 adjustment of chemical feed rate in proportion to plant
 flow. This  is accomplished  by transmitting a  signal
                                     from a flow measuring device to a controller, which
                                     then adjusts the speed of a rotary dipper feeder,  the
                                     stroke  of a  metering pump,  or the  opening  of a
                                     control valve. Such  devices are well  demonstrated
                                     and  reliable  for  a variety  of  chemical  feed
                                     applications.  Unfortunately, the  resulting  chemical
                                     feed rate will be  proportional to  plant flowrate, which
                                     may bear little correlation  to the actual  phosphorus
                                     loadings  to the facility.

                                     An  alternative  to  flow   proportional  control  is
                                     programmed  control  in which chemical feed rate is
                                     programmed  in relation to  historical  data  on  mass
                                     phosphorus loading  patterns  (product of plant flow
                                     and  phosphorus  concentration).  The  use   of
                                                     67

-------
programmable controllers  is a  relatively  simple  and
effective technique  which  has been successfully
implemented  at full scale  facilities.  This  requires an
accurate  knowledge  of  incoming  phosphorus
loadings, preferably on an hourly basis over a period
of  one  week.  Chemical  feed  rates  are thus
programmed  to  coincide  with intervals  of  known
phosphorus  loadings. For automated systems,  this
approach is superior to flow proportional control since
it provides for more efficient and  specific application
of chemicals.  However, it still  suffers  from the  fact
that chemical  dose is based on  historical flow  and
phosphorus  data.  During wet weather  flows,  the
programmed dosing schedule may not be applicable.

c. Feed Forward and Feedback Control
A more sophisticated approach for control  of chemical
dosage is  the  use  of  feed-forward  or feedback
control, in which the chemical  feed  rate is controlled
in proportion  to a combined  signal of  wastewater
flowrate and some wastewater characteristic such as
pH, conductivity, or  phosphate  concentration
(16,18,19).  In  Norwegian  studies, it was  found  that
alkalinity was the predominant variable affecting alum
dosage. Since field proven instruments that provided
on-line  analysis  of alkalinity were  not  available,  it
was decided to base chemical dosage on  conductivity
measurements.  Interestingly,  good  long-term
correlation  was  found  between  alkalinity   and
conductivity. As a  result, a conductivity feed forward,
open loop control  system  was  implemented to allow
variation of chemical feed  rate based on a combined
signal  of wastewater flowrate  and  primary  effluent
conductivity. This system  was found to be effective,
resulting in  savings in  chemical costs  over other
control alternatives. As of February,  1985, six plants
in Norway  using alum  for  phosphorus control  had
implemented  the conductivity  feed  forward  control
system (18).

In-line  phosphate  analyzers  have been  investigated
for use in automated  chemical  control  systems  (17).
Unfortunately,  operation   and  maintenance
requirements are high, and  skilled  technicians must
be  available to service such units.  Particularly when
used  for raw  wastewater or  primary effluent
applications, the devices are subject to plugging  and
fouling. Overall, their use in  chemical dosage control
applications has been  unsuccessful.

4.4.5 Chemical Mixing and  Flocculation
It  is important that chemicals  used for  phosphorus
precipitation  be intimately  mixed with the wastewater
to ensure uniform  dispersion and  efficient application
of the  chemicals.  Where  existing plants have been
modified to remove phosphorus by chemical addition,
it  has  been  standard  practice  to  use existing
structures and facilities  to  provide mixing  of  the
chemical with  the wastewater. Points of addition have
included Parshall flumes, drop  manholes,  aerated grit
chambers, the discharge side of raw sewage pumps,
90° pipe bends, hydraulic jumps, and aeration basins,
where the turbulence levels were typically higher than
for other locations at the plant.

Although chemical addition at  such  locations  has
been  reported to  be effective, it  is  unlikely  that
optimum mixing conditions  existed.  Poor  or
inadequate mixing can result in inefficient chemical
use  and  greater  chemical  consumption.  Where
viscous chemicals such as polymers are added to the
waste stream, provision of intense mixing is essential.
It has been recommended that polymer  be added at a
concentration of 0.01-0.05 percent, and never above
0.1  percent (14). This allows reduction in  required
mixing power by  providing for improved dispersion
upon  injection  into the main stream. Manufacturers'
recommendations should  be followed  for  polymer
addition, since "overmixing" is  possible, resulting  in
reduced performance.

The most important parameters used in the design  of
mixing and flocculation processes are detention time,
t, and velocity  gradient, G.  Velocity  gradient is  a
measure of the shear intensity  imparted to  a fluid.
The equation for velocity gradient is given in  Section
4.5. For  chemical mixing processes, detention times
are  approximately 30  sec,  and  G values are on the
order  of 300 m/sec/m although velocity gradients  of
up to 1,000 m/sec/m have  been recommended (20).
A typical flash mix tank is shown in  Figure 4-6.

The  flocculation  process  allows contact between
coagulated solids so that they  agglomerate to form
solids with  improved  settling characteristics. Whether
for a  new plant or for a  retrofit application,  separate
basins  are  seldom  constructed  specifically for
flocculation.  Rather, existing plant components such
as  aerated grit  chambers,  aerated  distribution
channels, or feed  wells of clarifiers  are used, often
after  some  modification. Although  use of existing
tankage  may be effective for flocculation,  tank  size
and configuration  should be carefully evaluated, and
velocity gradients calculated to  ensure presence  of
conditions that will promote good flocculation.

A common  approach is the use of  a flocculating
clarifier,  in which  an expanded center well  provides
the desired detention  time for flocculation.  The
contents of  the flocculation well can be agitated by
mechanical mixers  or  diffused air,  although  the
hydraulic regime in the center well may be such that
mechanical or air mixing does not provide additional
benefit (21). A typical flocculating clarifier is shown  in
Figure  4-7.

Velocity gradients for flocculation processes generally
are 20-80  m/sec/m,  depending  on the chemicals
added and point  of addition.  Velocity  gradients  less
than 50 m/sec/m  may  yield  floe particles  with too
much  trapped  water, whereas  velocity  gradients
above 80 m/sec/m may  cause  excessive floe shear
                                                  68

-------
Figure 4-6.   Typical flash mix tank.
                                 Support Beams
    Overflow
               Impeller
                           Shaft
Impeller
                       I  I   I
                          Feed
and  floe deterioration. In many cases, mineral  salts
are  added directly to the  aeration  basin  to allow
mixing  and  flocculation to  occur.  Although  this
practice is effective, it  represents  less  than  ideal
conditions  for  flocculation,  as velocity gradients in
aeration basins result in  floe shear. In one study,  air
flowrates in the downstream end of the aeration basin
were reduced  to  achieve a velocity gradient of  60
m/sec/m,  which  was  found  to be optimum for
flocculation using ferric  chloride (22).  Addition  of
anionic polymer  prior to clarification  assists in the
agglomeration of sheared floe.

Other  parameters used  in the design of  flocculation
processes  are Gt, the product of velocity gradient and
detention time,  and  GCt, where C  is the  ratio of
volume of floe to total volume of suspension.  In water
treatment applications using aluminum or iron salts,
Gt  values  are typically   30,000-150,000, with  GCt
values  of  10-100 (23).

4.4.6 Clarification
Since  clarifiers  are  used in  virtually  all  wastewater
treatment plants  and are not specific to  phosphorus
removal systems, the  following  discussion   will  be
limited  to how their application or design  differs from
conventional  practice when mineral salts are added to
precipitate  phosphorus.

The two most common points of  mineral addition are:
1)  prior to  primary clarification  and 2)  prior  to
secondary  clarification. Consequently, clarifier design
is critical to ensure adequate  removal of suspended
solids and consistent  achievement of  phosphorus
discharge limitations.

Clarifiers used in chemical precipitation systems differ
little  from those employed in  conventional biological
treatment,  although use of  flocculation zones is
recommended  to  allow  flocculation to  occur after
addition of coagulants.

Provision  of  distinct flocculation  zones  is
recommended for either  primary  or  secondary
clarifiers depending on the point of chemical addition.
This is  particularly important  for primary clarifiers,
since there may be little opportunity for flocculation to
occur in existing processes.

For secondary mineral addition, flocculation can occur
in aeration basins  or channels preceding clarification,
but  the use  of flocculation  zones  in  secondary
clarifiers is recommended practice  to  allow flexibility
in  the  point of chemical addition and to provide  a
zone in  which direct  control can be exercised over
velocity gradients in  order  to achieve optimum
flocculation.


4.5  Design  Methodology
The  approach  to design  of facilities  for  phosphorus
removal using  mineral salts follows the basic steps
outlined below.

1. Characterization  of  the   wastewater (raw
   wastewater, primary effluent,  mixed   liquor,
   secondary effluent).

2. Determination of chemical doses required  to meet
   effluent  phosphorus  requirements  based  on
   addition to primary or secondary treatment.

3. Selection of chemicals and points of addition.

4. Evaluation  of existing unit processes  (retrofit
   applications).

5. Conduct of full-scale trials (retrofit applications).

6. Sizing  and  design  of chemical storage, handling,
   and feed systems.

7. Sizing and design of liquid processes such as rapid
   mix  and flocculation facilities,  clarifiers,  and
   aeration basins.

8. Sizing and design of sludge handling facilities.

4.5.7 Wastewater Characterization
A thorough knowledge of wastewater characteristics
is required  in order  to proceed  with chemical
selection  and process  design.  The  following
information is essential:
                                                   69

-------
Figure 4-7.   Typical mechanically mixed flocculating clarifier.
                                              Axial Flow  -
                                             " Slow Stirrers
                                                 t
                                                                                          Effluent
                                                     Flocculation
                                                     Chamber
                                                     (slow mix)
Influent
1. Average dry weather and wet weather flows.

2. Diurnal flow variation.

3. Characterization parameters.

  a. BOD and COD
  b. SS and VSS
  c. Total and soluble phosphorus
  d. Orthophosphate
  e. pH
  f. Alkalinity

4. Diurnal (hourly) variation in phosphorus loadings.

4.5.2 Determination of Chemical Doses
Jar tests should  be conducted with  the specific
wastewater to  be treated if possible.  Such  tests
should be conducted over an extended period of time
to  obtain representative wastewater  characteristics.
Grab samples are collected  at various times of the
day and  days of the week,  and a range of dosages
established for each  chemical to  be  tested.  A
minimum  of  10 data points  should be gathered for
each  chemical  dose on  each  waste  stream
investigated.  Jar test  procedures are  described  in
Reference 24.  Probability   plots should then be
developed which show percent  of time that effluent
phosphorus is  less  than a  stated value for  each
dosage. These plots are valuable in determining the
reliability of a  particular coagulant  over a  range  of
dosages.

4.5.3 Selection of Chemicals
Chemical selection is made based on:  1) performance
and  reliability (results  of jar tests)  and  2)  costs.
Factors included in  the  selection  decision  include
whether to purchase chemicals in dry or liquid form,
in bulk or in small lots. Consideration should be given
to  whether secondary  chemicals (e.g.  polymers for
 flocculation  aids, bases  for  pH  adjustment)  will  be
 required, and in what quantities.

 When  mineral  salts are  used  for  phosphorus
 precipitation, anionic polymers may be  required, and
 prudent design  should  include  polymer addition
 facilities. Adjustment of pH through addition of lime or
 other alkaline materials may be necessary, particularly
 with low-alkalinity  wastewaters.

 If waste products such as pickle liquor  are available,
 jar  testing  should include  investigation  of such
 chemicals at various  times to quantify variability of
 these chemicals. Also, the engineer  should  quantify
 their  availability over long  periods to determine
 storage requirements.

 Assuming  that  more  than  one  chemical  or
 combination of chemicals yields  acceptable results in
 terms of performance and  reliability, the selection of
 chemicals  is then  an economic  decision. A cost-
 effectiveness  analysis should be conducted  which
 addresses capital costs of chemical storage, handling,
 and feeding equipment,  considering  both  dry
 chemicals and liquid chemicals  in bulk and  in small
 lots; as well as  operational costs, including costs of
 chemicals, labor and power.

 4.5.4 Evaluation of Existing Unit Processes
 For  retrofit  applications  the  existing  process train
 should be evaluated with  respect to:

 1. Potential  points of chemical addition.

 2. Degree  of  mixing  at  identified points of  addition
    (e.g., raw  sewage pumps,  Parshall flumes  or
    hydraulic jumps, aerated grit chambers, etc.).

 3. Opportunities for flocculation  (e.g., preaeration
    basins,  clarifier feed  wells,  connection  piping,
    weirs, aeration basins, etc.).
                                                  70

-------
4. Adequacy of existing clarifiers (existing vs. required
   design overflow rates).

Potential points  of chemical addition include: 1) prior
to  primary  clarification,  2)  prior to  secondary
clarification, 3) in aeration basin at turbulent  locations,
and 4) at several of  these  points  simultaneously.
When evaluating existing  structures or  equipment to
provide mixing of the coagulant with the wastewater,
velocity gradients  should be  calculated  where
possible to determine  if  the level  of  turbulence is
sufficient  for  adequate mixing.  A minimum velocity
gradient of 300  m/sec/m  is recommended.  Canadian
studies showed that efficient mixing could be obtained
in full scale facilities by the following approaches (11):

1. Injection of the chemical into the discharge side of
   raw sewage pumps.

2. Chemical  addition  into  a preaeration  tank  or
   aerated grit chamber.

3. Addition of chemical at a Parshall flume  or similar
   turbulent constriction.

4. Chemical  addition  to pipe or  channel  between
   aeration tank and final clarifier with  supplemental
   mechanical or air mixing at the point of addition.

If  existing  structures are  inadequate for  providing
good mixing,  separate  mixing basins or modification
of existing structures will be required.  For  example,
existing preaeration basins can be  modified to provide
for intense mixing in  the  upstream end, followed  by
gentle mixing to  promote flocculation.  It is  important
to note that phosphorus removal efficiency can  suffer
significantly if intense mixing of  the coagulant and
wastewater is not provided.  During the  Canadian
studies,  it  was  found  that,  in several cases,
phosphorus  removal  efficiency  was  doubled  by
increasing  the intensity of mixing at  the  point  of
chemical addition (11).

In most cases, existing structures of the  facility can
be used, perhaps with some modification,  to promote
flocculation  of the coagulated wastewater. Some
flocculation  will  occur  naturally  during  passage
through the clarifier feed well, although  consideration
may be given to use of an enlarged center  feed well
in the clarifier to provide approximately 20 minutes of
gently agitated flocculation.

The existing and design overflow rates in primary and
secondary  clarifiers  must be  compared   with
recommended designs for  chemical  precipitation
systems. If necessary, additional clarification capacity
should be provided. New primary clarifiers should be
equipped  with   center flocculation  zones.  For
secondary clarifiers preceded by chemical addition to
the  aeration  basins,  specially  designed flocculation
wells may  be unnecessary,  as  air  flowrates in the
downstream end of the  aeration  basins  can  be
adjusted to  provide  near  optimum conditions  for
flocculation.

4.5.5 Conduct of Full-Scale Trials
Where  existing  plants  are  to  be  retrofitted  for
phosphorus  removal,  full  scale  trials   are
recommended.  Full-scale  trials  of  6 weeks  for
primary treatment plants and 8 weeks for  secondary
treatment plants  have been used (25). Such  trials
offer the following advantages:

1. Determination  of  optimum point(s)  of chemical
   addition.

2. Optimization of chemical dosages.

3. Evaluation of  impacts  on aeration  requirements,
   SRT, F/M and other key process variables.

4. Direct observation of impacts of  variables  on
   effluent quality.

5. Estimation of the quantity (volumetric and mass) of
   additional sludge to be processed.

6. Observation and  determination  of  impacts  on
   sludge thickening,  stabilization, and dewatering
   characteristics; chemical  requirements for sludge
   conditioning; equipment modifications; and  disposal
   limitations.

4.5.6 Design of Chemical Handling System
The main components of a chemical handling system
include: 1) chemical storage facilities, 2) dry chemical
feed and dissolution equipment (if dry  chemicals are
used), and 3) chemical solution feed systems.

a. Chemical Storage
Bulk storage facilities for either dry or liquid  chemicals
should be sized for capacities of at least 50  percent
greater  than the  largest  anticipated  shipment,  and
should provide a minimum  capacity of a ten  day
supply,  and  preferably  a two week  supply.  Where
chemicals are delivered  by rail, it may be prudent to
provide additional capacity to compensate for late or
intermittent deliveries.

Dry  chemical storage vessels should  be  designed
with bottom  hoppers having slopes of 60 degrees to
help present bridging of the chemical.  Vibrators are
also used for this  purpose.  Dust  collection equipment
is recommended  to control  fugitive dust  emissions
during  loading  operations.  Choice  of  materials  is
dependent on the particular chemical  to be stored.
For dry  iron compounds,  steel lined  with  rubber,
asphalt,  or plastic, synthetic resins, or  concrete  may
be  used. Dry alum can be  stored in mild steel  or
concrete  bins. Where  dry chemicals are purchased in
small lots such as bags or drums, the  chemicals
should be stored in enclosed, dry areas.
                                                  71

-------
Liquid alum should be stored in tanks constructed of
FRP, 316 stainless steel, or steel lined with rubber or
PVC.  Storage vessels  for liquid sodium aluminate
should be constructed of mild or stainless steel, FRP,
or concrete. Use of copper and its alloys, rubber,  and
aluminum should be avoided.  If located outside, tanks
should be closed and vented,  with heaters to maintain
temperatures  above -4°C  (25°F).  Polyurethane
insulation  between  the  tank  and  the  pad is
recommended.

Liquid  iron  solutions  such  as ferric  chloride  and
ferrous  chloride  should  be stored  in vessels
constructed of FRP, synthetic resins, or  steel lined
with rubber or  plastic.  Tank  heaters and  insulation
may be required, as ferric chloride will  crystallize at
temperatures ranging from  -12°C  (10°F)  for a 35
percent solution to 10°C  (50°F)  for a  45 percent
solution. To prevent freezing during shipment, weaker
solutions with lower freezing points are shipped
during the winter.

Liquid  chemical  storage tanks should be equipped
with a strip or float gauge to determine volume of tank
contents, an access manhole, a filling hose with quick
disconnect  coupling, and a drain that is flush with the
tank bottom.

b. Dry Chemical  Feed and Dissolution Systems
Dry chemical feeder selection will be dependent on
the chemical used.  For dry  alum,  either open or
enclosed construction is permissible.  However,  with
dry iron compounds such as  ferric or ferrous sulfate,
belt type feeders  are rarely  used  because of their
open construction  and exposure to corrosive  vapors
from the dissolving tank. Provision of water jets for
vapor removal is recommended to protect equipment
and operating personnel.

Selection of a  volumetric  vs.  gravimetric  feeder is
dependent  upon  total chemical demand and degree of
accuracy required. For plants larger than 3,785 m3/d
(1 mgd),  gravimetric feeders are recommended, since
the additional cost over a volumetric feeder is likely to
be offset by the  savings in chemical costs during the
useful  life  of the equipment. Capacity  ranges of
feeders should  be a minimum of 10 to 1. Sufficient
capacity  should exist  to handle peak chemical
demands. For some feeders, the  capacity range  can
be significantly expanded by  modification of the gear
box or  by use of variable speed drives.

For small plants using bagged chemicals, the feeder
can be attached to a  "day hopper," which is filled
manually each day and  which has  a capacity for  one
day's  supply of  chemical.  In larger  plants,  the
chemical feeder  is charged  directly  from the  bulk
storage silo.

Dry chemicals must be added to water in a dissolving
tank to form a chemical solution prior to introduction
into  the  wastewater stream.  For alum,  dissolving
tanks should be constructed of FRP, plastics, or 316
stainless  steel.  The  most dilute  alum solution
recommended is a 6 percent solution (0.06 kg/I). For
dry sodium aluminate,  dissolving  chambers may be
mild  steel  or  stainless steel.  Preparation of  a  6
percent solution is  standard practice. Iron solutions
are actively corrosive, so  care  must  be  taken  in
selecting materials. Ferric sulfate dissolvers should be
constructed  of type 316  stainless  steel, plastics,
rubber, or  ceramics. Minimum solution  strength for
ferric  sulfate is one percent, and the typical water  to
chemical weight ratio  is 4:1.  Ferrous sulfate
dissolution tanks  should be  constructed of type 304
stainless  steel,  plastics,  rubber,  or  iron.
Recommended solution strength is 6 percent.

For most dry chemicals, dissolving chambers should
be designed for a detention  time of 5 minutes at the
maximum feed rate. The exception  to this is  ferric
sulfate,  for which  a  20-minute  detention time  is
recommended (3). The dissolving tanks must be large
enough to provide the necessary detention time at the
maximum rate of  feed of  water  and  chemical.
Dissolvers should be mechanically mixed and should
be equipped with a water meter  so that the proper
solution strength can be determined and maintained.

c. Chemical Solution Feeding
As discussed in Section 4.4, rotary dipper feeders  or
metering  pumps are  commonly  used  to provide
positive control  over  chemical feed  rates.  Other
options are rotameters with  control  valves, or orifice
plates. Flow control devices should be sized for the
maximum expected flowrate of chemical solution.

Centrifugal pumps can  be  used  for the transfer  of
chemical solutions  from dissolving  tanks to  other
vessels, or for direct feeding to the process through a
flow  measurement device such  as a rotameter. To
achieve uniform  flow  rates with  centrifugal  pumps,
pumping  head must be constant. Centrifugal pumps
should be direct connected  but not close-coupled  to
prevent leakage into the motor. Pump components for
liquid alum service should  be constructed  of  316
stainless steel, FRP, or plastics.  For ferric chloride,
graphite or rubber lined pumps with Teflon seals are
recommended.

Metering pumps  are  typically  of the  positive
displacement  type, either  diaphragm  or plunger.
Diaphragm pumps protected with internal or external
relief  valves are preferred.  A back pressure valve  is
recommended to  provide positive check valve
operation (3).

Materials  of construction for chemical feed  service
include 316 stainless steel,  FRP,  plastics, and rubber.
Manufacturers' recommendations  should  be followed
regarding selection of pump materials for the  specific
chemical of choice.
                                                  72

-------
For pipes  transporting  alum  solution,  use of  FRP,
PVC,  or  other plastics  is  recommended.  Valves
should be plastic,  316 stainless steel, or rubber-lined
iron or steel.

For ferric  chloride  conveyance, pipes  should  be
constructed of  steel  lined with rubber or Saran,  FRP,
or plastics. Valves should be rubber-  or  resin-lined
diaphragm valves, Saran-lined valves  with  Teflon
diaphragms,  rubber-sleeved  pinch valves, or plastic
ball valves (3,4).

Pipe selection  for polymer service  should  be made
after the  type of polymer  has  been  determined.
Plastic pipe  or type  316 stainless  steel  is normally
used.

4.5.7 Design of Liquid Processes
Design of chemical phosphorus precipitation systems
requires  consideration of not only  chemical  storage
and  feed equipment, but also mainstream process
equipment such as  aeration basins and clarifiers as
well  as  sludge  handling   equipment  used  for
thickening, stabilization, dewatering and disposal.  For
example,  where phosphorus is removed by chemical
precipitation  in primary treatment,  primary  clarifier
design will  likely vary  from  standard practice  to
provide for flocculation. Since BOD and SS removal
efficiencies will be significantly improved, loadings to
downstream  biological  processes  will  be  reduced,
while  sludge generation  rate  will  be  increased.  In
addition, sludge characteristics  may be considerably
different than if no chemicals were added.

a. Rapid Mixing
In the design of new facilities incorporating chemical
phosphorus  precipitation, provision  of separate rapid
mixing basin(s) is  recommended for  complete contact
of the chemical with the wastewater. Rapid mix tanks
may  be  designed  for detention  times  of  20-60
seconds,  although 30 seconds is  recommended for
metal salts. Velocity  gradients (G) on the order of 300
m/sec/m are generally  sufficient, although values  as
high as  1,000 m/sec/m  have  been  recommended
(15).   The power required  to  maintain  turbulent
conditions (Reynolds > 105) in  a flash mix basin with
an impeller mixer can be calculated from (26):
                  P  =pKTn3Da5/g
where,
   P   = power requirement, ft-lb/sec
   p   = mass density of the fluid, Ib/ft3
   n   = impeller revolutions per second, rps
   Da  = diameter of impeller, ft
   g   = acceleration due to gravity, 32.2 ft/sec2
   KT  = constant

   Values of KT for various mixing devices are shown
   in  Table  4-7).
Table 4-7.   Values of KT for Determining  Impeller Power
           Requirements (26)

 Type of Impeller	     Kj	

 Propeller (square pitch, 3 blades)
 Propeller (pitch of 2, 3 blades)
 Turbine (6 flat blades)
 Turbine (6 curved blades)
 Turbine (6 arrowhead blades)
 Fan turbine (6 blades)
 Flat paddle (2 blades)
 Shrouded turbine (6 curved blades)
 Shrouded turbine (with stator, no baffles)
                                         0.32

                                         1.00

                                         6.30

                                         4.80

                                         4.00

                                         1.65

                                         1.70

                                         1.08

                                         1.12
Velocity gradient can be calculated from  the general
equation (26):
                  G = [P/Vp]l/2
where,
   G   = velocity gradient, ft/sec/ft
   p   = absolute  fluid  viscosity,  Ib-sec/ft2;
         approximately 2  x  10-5  ib-sec/ft2 @ 20 °C
   V   = basin volume, ft3

For an electrically driven mechanical mixer,

                  P = (WHP)(550)

where,

   WHP  = delivered water horsepower or
           (KVA)x(Motor Eff.)x(Power Factor)/0.746
   KVA  = apparent power, kVA

b. Flocculation
As discussed in  Section  4.4.5,  numerous devices
have  been  used  to promote  flocculation, including
preaeration  basins,  interprocess  channels,  aeration
basins,  and  enlarged   feed wells of  clarifiers.
Maintenance of velocity gradients in  the range  of  50
to  80 m/sec/m  for no  more than  15  minutes  is
recommended for  good flocculation where  metal salts
are used.  Some  have recommended high  energy
flocculation  for  5 minutes  followed  by  gentle
flocculation for  15 minutes  (15).  Such "tapered
flocculation"  can  occur naturally  in  clarifiers and  in
aeration basins in  which  air flows are decreased  at
the downstream end.

The degree of flocculation is difficult to predict, since
it will  vary with wastewater characteristics and choice
of chemicals, as well as with hydraulic characteristics
and energy dissipation in the basin.  For this reason,
design  of new facilities should provide for maximum
flexibility in  order  to achieve  optimum conditions  for
flocculation.
                                                   73

-------
Flocculation can be  accomplished by  mechanical
(paddle or turbine) mixers, air  diffusers, or baffles.
Velocity gradient can be determined by substituting
the appropriate value of P into  the general equation
below:
Paddles:
where,
 G = [P/Vu]i/2



P =  CouAv3/2g
   P   = power  requirement, ft-lb/sec
   CD  = coefficient of drag  of flocculator  paddles,
         dimensionless
   co   = mass fluid density, slugs/ft3
   A   = area of paddles, ft2
   v   = relative  velocity  of  paddles in fluid,  ft/sec
         (about 0.7-0.8 of  paddle tip speed)
Turbines:
where,
                  P =
   P   = power  requirement, ft-lb/sec
   Kj  = constant
   Da  = diameter of impeller, ft
Air:
where,
            P = 82 Qa log [(H + 34)734]
   P   = power imparted to water,  ft-lb/sec
   Qa  = air supplied, scfm
   H   = head of water above air diffusers, ft
Baffles:
where,
                     P = Qtohf
   P   = power  imparted to water, ft-lb/sec
   Q   = flow, ft3/sec
   hf   = head loss due to friction, ft

Important considerations in the design of flocculation
basins include:

1. Transport conditions  -- minimize transport  time
   (<1  minute) from  rapid mix  tank to flocculator.
   Keep  velocities  low and  avoid  turbulence  from
   flocculator to clarifier.

2. Flow   distribution  --  maintain   good  flow
   distribution at flocculator  inlet  by designing  for
  headloss through inlet ports  of  10 times transport
  headless from first to last port.

3. Short  circuiting  -  install baffle  walls  between
  multiple  paddle  units in  rectangular  basins; in
  circular units with rotary flocculators, place baffles
  along  wall to  prevent entire tank  contents  from
  rotating with mechanism.

4. Tapered  flocculation  -  provide  compartments
  which  increase in volume from the inlet end to the
  outlet end of the tank. Reduce slow mix power with
  each downstream stage.

5. Separate  vs.  combined  units  --   consider
  combined flocculator-clarifier for lime  precipitation
  systems;  compare  costs, reliability, flexibility of
  separate vs. combined unit processes.

When flocculation is carried out in an aeration  basin
or  separate  structure,  the  velocity in  conduits
conveying  the  floe to the  clarifier should be  kept
between  0.15  and 0.30 m/sec  (0.5-1.0 ft/sec) so as
to prevent destruction of the floe (8).

c. Clarification
If not preceded by a  flocculation  process, clarifiers
receiving  a chemically  dosed effluent  should  be
designed  with  a  flocculation  zone.  Several
manufacturers provide circular clarifiers with center
flocculation wells which incorporate a detention time
of 20-30  minutes.  Generally,  flocculation wells are
30-40 percent of the tank diameter. The walls of the
feedwell  generally extend down to 60-75 percent of
the tank depth (14).

The principal design criterion for chemical clarification
is  overflow rate. Table 4-8 provides  a summary of
recommended  design overflow  rates for primary,
secondary, and tertiary clarifiers receiving wastewater
coagulated with  mineral salts (14). These values are
generally conservative.

Minimum  bottom slopes  of clarifiers should   be  8
percent.  All clarifiers  should be equipped with  scum
removal mechanisms. A minimum sidewater depth of
3.6 m (12 ft) is recommended (14).
                                     4.5.8 Design of Sludge Handling System
                                     Addition of  mineral salts for phosphorus precipitation
                                     may  significantly  increase the  quantity  of sludge
                                     generated due to the production of metal-phosphate
                                     precipitates  and  metal  hydroxides  as  well  as  the
                                     improved removal of suspended solids.

                                     Addition of  metals upstream  of the  primary clarifier
                                     will result in a primary sludge mass increase of 50-
                                     100 percent. This increase is  normally  due almost
                                     equally to improved capture of suspended solids and
                                     additional chemical  sludge (3). Overall  plant sludge
                                                   74

-------
Table 4-8.   Recommended Overflow Rates for Conventional
           Clarifiers Receiving Wastewater Coagulated
           with Mineral Salts (14)

                            Design Overflow Rates
                               (Average Flow)
Type of Clanfier

Primary
Secondary
Tertiary
w/o Polymer
m3/m2/d
(gpoVfl2)
24
(600)
24
(600)
24
(600)
w/Polymer
m3/m2/d
(gpd/ft2)
49
(1,200)
-
49
(1,200)
  samples should be collected at various times of the
  day and on various days of the week. Mixed liquor
  samples should  be collected at different operating
  conditions  (e.g.  SRT)  where possible. Evaluate
  effectiveness  of  coagulants  including  ferric
  chloride,  alum, and  ferrous  sulfate  over  a
  prescribed range of dosages. If waste pickle liquor
  is available locally or at a reasonable cost, include
  in jar tests.

  Plot effluent total phosphorus vs. chemical dose on
  a  probability plot  for  each  chemical.  Determine
  dosages  that  will  meet  effluent  phosphorus
  requirements at the  desired  level  of  probability
  (e.g.,  90 percent or 95 percent).
mass increase is much  smaller owing to reduced
secondary  sludge production from improved primary
removals, e.g., 60-70 percent increase across  the
entire plant.

For  metal  addition to secondary  processes, waste
mixed liquor  sludge  mass can  be  expected  to
increase by  35-45  percent.  Overall  plant sludge
mass increase  will  be  5-25  percent  (11). Metal
addition to  either  primary or secondary treatment will
not only increase  sludge mass, but sludge volume will
be increased since settled sludge concentration in the
clarifiers may decrease by up to  20 percent (11). A
detailed  discussion  of  characteristics, generation
rates, and treatment alternatives for sludges resulting
from  chemical  phosphorus  removal  systems  is
presented in Chapter 5.

4.5.9 Design Example
Develop a  preliminary process design  for  retrofitting
an existing 11,350 m3/d (3.0  mgd) activated sludge
facility for chemical precipitation of phosphorus.  The
following effluent requirements are imposed:

BOD = 15 mg/l
SS = 15 mg/l
Total P  = 0.8 mg/l

1. Characterize wastewater

  BOD = 200 mg/l
  SS = 210 mg/l
  Total P = 7 mg/l
  Ortho P  =  4 mg/l
  Alkalinity =  220 mg/l
  pH =  7.1
  Design ave. daily dry weather flow  = 11,350 m3/d
  Current ave. daily dry weather flow =  9,500 m3/d
  Peak:average daily flow ratio  =  2.5:1

2. Determine chemical dosages

  Conduct jar tests  using samples  of  both  raw
  wastewater and  mixed  liquor.  Raw  wastewater
3. Select chemical

  Chemicals  should be selected  based on the
  following criteria:

  a. Performance and   reliability  (from  probability
     plots)

  b. Unit costs

  c. Reliability of supply

  d. Operation  and  maintenance of  chemical feed
     equipment

  e. Safety in handling

  Based on  analysis of  the  above criteria, assume
  ferric chloride is selected as the  most economical
  and reliable chemical.


4. Evaluate existing liquid stream processes

  An evaluation of  existing liquid stream processes
  resulted  in  the  following observations  and
  conclusions:

  a. Potential points of chemical addition

  Two identified points of possible chemical addition
  to the  existing activated sludge  facility are:  1)
  upstream of the  primary clarifiers and 2)  in  or
  immediately after the aeration basis.

  b. Degree of mixing

  Inspection  and evaluation  of hydraulic structures
  upstream  of  primary clarification indicate  that
  sufficient mixing and turbulence do not exist, thus
  requiring construction of  a separate  rapid mix
  basin.  For  chemical addition  to   secondary
  treatment,  it is concluded  that  direct  chemical
  addition to the aeration basins is feasible without
  modification of the basins.
                                                  75

-------
  c. Opportunities for flocculation

  Evaluation  of  the  hydraulic characteristics of the
  existing primary clarifiers indicates that adequate
  flocculation  will occur in the  feed  well and  other
  portions of  the clarifier.  This  will be  confirmed  in
  full-scale  trials.

  For addition to the aeration  basin, it is determined
  that  air flowrates through  the  diffusers in the
  downstream portions  of the basins can be readily
  throttled to yield desired velocity gradients for good
  flocculation.  Existing  velocity  gradients  are
  approximately 120 m/sec/m.  Full-scale  trials are
  necessary to determine optimum velocity gradients
  in the aeration basin.

  d. Adequacy of existing clarifiers
  The  existing facility has 2 primary clarifiers,  each
  15 m (50 ft) in diameter. Design  overflow rate  at
  11,350 m3/d (3 mgd) average daily design flow is
  32 m3/d/m2 (800 gpd/ft2),  and approximately 27
  m3/d/m2 (670 gpd/ft2) at present raw wastewater
  flow.  Comparison with design  overflow rates for
  chemical precipitation systems  indicates that the
  current overflow  rate is only about  10 percent
  greater than  recommended  [24  m3/d/m2  (600
  gpd/ft2)].   Since   the recommended  rates are
  conservative,  expansion  of  existing  clarifier
  hydraulic capacity is not warranted at this time.

  The  existing final clarifiers  were designed for an
  overflow rate  of 24 m3/d/m2 (600 gpd/ft2)  at
  average  flow.  Current  overflow  rates  are
  approximately 20 m3/d/m2  (500  gpd/ft2). These
  rates are  within  recommended guidelines  of 24
  m3/d/m2 (600  gpd/ft2) for  chemical clarification.
  Thus,  expansion  of  secondary clarifier hydraulic
  capacity is not justified.

5. Conduct full-scale trials

  Full-scale trials were conducted  over  period  of
  eight weeks using ferric chloride as a coagulant.
  Key  findings from the studies are as follows:

  a. Split addition of ferric chloride  to primary and
     secondary treatment produced optimum results.

  b. Optimum dosages  were  8 mg/l  to primary
     treatment and 32 mg/l to secondary.

  c. Addition  of a rapid mix basin ahead of primary
     treatment is necessary. For the trials, temporary
     mixing facilities were constructed.

  d. Good flocculation  occurs naturally prior to the
     primary  clarifier.

  e. Injection of ferric  chloride at  a point  halfway
     down the  aeration  basin was found  to  be
     effective when air flows in the downstream third
     of  the  basin were reduced to yield velocity
     gradients of approximately 70 m/sec/m.

  f.  Effluent suspended solids  were generally less
     than 10 mg/l.

  g. Effluent total phosphorus concentrations ranged
     from 0.5 to 0.8 mg/l.

  h. Modification of existng clarifiers is unnecessary.

6. Design chemical handling system

  From full-scale  trials,  it  was found  that  split
  addition of ferric chloride to  primary and  secondary
  treatment was  the most economical  and reliable
  approach, with  20 percent of the chemical added
  upstream  of the  primary clarifiers and 80 percent
  added directly  to the aeration basins.  Optimum
  dosages were approximately 8 mg/l and  32 mg/l to
  primary and secondary treatment,  respectively.
  Ferric chloride is available locally in liquid form.

  Total FeCIa  requirements at average design flow:
  40 mg/l x  11,350  m3/d x  0.001  = 454 kg/d
  Average volumetric  requirements for  40%
  solution:
   (454 kg/d) -5- (0.40 x 1,400 kg/m3) =  0.81 m3/d
                                     (215gal/d)

   Peak volumetric requirements:

   2.5 x 0.81 m3/d = 2.02 m3/d (535 gal/d)

   Size  ferric chloride storage tanks based on  1-1/2
   times  largest anticipated  shipment or  10  days
   storage at maximum feed rate:

   1.5 x 15 m3  = 22.5 m3 (5,940 gal)

   10 days x 2.02 m3/d =  20.2 m3 (5,340 gal)

   Use 2 storage tanks for total of 23 m3 (6,000 gal)
   storage capacity.

   Select  2 metering pumps (1   standby);  positive
   displacement diaphragm type.  Size  each pump at
   twice the anticipated  maximum  chemical feed rate
   -  85  l/hr (22.3 gph).  Since data collected indicate
   a relatively  constant  diurnal   phosphorus
   concentration in the raw  wastewater, design  for
   flow  proportional control  of  chemical  metering
   pumps.

7. Design liquid stream processes

   Full-scale trials indicate that no existing hydraulic
   components upstream of primary treatment  provide
                                                   76

-------
   sufficient turbulence  to  achieve  adequate mixing.
   Therefore, a  separate rapid mix tank  is required
   upstream of the primary clarifiers. Existing primary
   and secondary clarifiers do not require modification
   to achieve desired performance.

   Rapid Mix Tank

   Size for detention time of 30 sec at average flow:

   Volume = 3.3 m3 (870 gal)
   Dimensions = 1.5 m  x 1.5 m x 1.5 m deep
   Use propeller mixer with Kj  = 1.00 (Table 4-7)

   Power required for mixing:

   P = pKTn3Da5/g

   Use p = 62.4lb/ft3
       KT = 1.00
       n = 600 rpm (10 rps)
       Da = 1 ft
       g = 32.2 ft/sec2

   P  = 62.4(1.00)(10)3(1)5/32.2
      = 1,940ft-lb/sec
      = 1,940 * 550  =  3.5 hp (use 4 hp)

   Check velocity gradient, G:

   G  = [PA/p]l/2
      = [(4 x 550) * (3.3 x 35.31 )(2 x 10-5)] 1/2
      = 974 sec*1 (within the range discussed in
                  Section 4.5.7)

8. Design sludge stream processes

   Although  techniques  are  available  to calculate
   additional sludge production from chemical addition
   (see Chapter 5),  the  most reliable  method  is
   through full-scale trials. In  addition, such  trials
   allow  determination  of  the  impact  of chemical
   addition on sludge thickening,  stabilization,  and
   dewatering characteristics. A design example for
   sludge handling in chemical phosphorus removal
   systems is presented  in Chapter 5.


4.6 Retrofit Considerations
In general, existing wastewater treatment plants can
be  retrofitted  for chemical phosphorus  precipitation
relatively  easily  and inexpensively,  provided  that
sufficient  hydraulic and  solids handling capacity  is
available.  Design considerations include:

1. Existing vs. design flows  and loadings (including
   phosphorus); average and peak.

2. Existing and design overflow rates for primary and
   secondary clarifiers,  compared to  recommended
   values for chemical precipitation systems.
3. Current  loadings  to  secondary  biological
   processes.

4. Solids  loadings  to sludge  thickeners  and
   dewatering equipment,  compared to  expected
   loadings with chemical precipitation.

5. Impacts of chemical addition on sludge thickening,
   stabilization, and dewatering characteristics.

6. Impacts on volume of sludge for final disposal.

7. Availability of turbulent zones for chemical addition
   points.

8. Availability of gently mixed zones for flocculation of
   chemically coagulated wastewater.

The two variables which have  the greatest  impact on
the cost  and complexity of  retrofitting  plants for
chemical phosphorus removal  are the existing  solids
handling and clarification capacity.

For  any  chemical  precipitation  system, sludge
production can be expected to increase substantially,
requiring  a thorough  capacity analysis  of sludge
handling processes and equipment.  In some  cases,
existing equipment  may be  sufficient, requiring only
longer operating times for such sludge processing
operations such as  dewatering.  In other  situations,
expansion  of existing processing  capability through
construction of additional tankage  or installation of
new  equipment may be  necessary,   involving
potentially large capital investments.

Design of clarifiers for precipitation of phosphorus by
mineral  addition is  typically  conservative,   although
when polymer is used as a flocculant aid,  allowable
hydraulic loadings can often be significantly  increased
without degradation of effluent  quality.


In order to achieve  low levels  of phosphorus in  plant
effluents,  suspended  solids  concentrations  must be
correspondingly low.  It  is generally true that,  unless
effluent  suspended  solids  concentrations can be
reduced  to  below about 15  mg/l,  it is impossible to
achieve an effluent total phosphorus concentration of
less than 1 mg/l,  even though soluble  phosphorus
may be as low as 0.1  mg/l (11).
4.7 Case Histories

4.7.1 Orillia, Ontario
This case history is included  to  document  the
capabilities of  a dual  point chemical  addition system
to achieve  low  effluent phosphorus  levels.  The
information has been extracted from the final report of
a  study  funded by  the Ontario Ministry  of  the
Environment (27).
                                                  77

-------
The Orillia,  Ontario  wastewater treatment plant
employs  the  conventional activated sludge process.
Unit operations include preliminary treatment,  primary
clarification, aeration,  secondary clarification,  and
chlorination.  Primary  and  secondary sludge is
pumped  to a two-stage anaerobic digestion system.
The digested  sludge is discharged  to lagoons  for
storage  during  winter months, and spread  on
agricultural land  during other times  of  the year.
Phosphorus removal is  normally practiced by adding
alum to the outlet of the aeration tanks at a dosage of
approximately  65  mg/l. Target effluent phosphorus
levels  are  1  mg/l. Design flow is 18,000 m.3/d  (4.8
mgd).  Plant  performance data are  summarized in
Table  4-9.

Table 4-9.   Summary of  Plant  Data During Single-Point
           and Dual-Point Alum Addition (27)
Parameter
Flow, m3/d
Raw sewage
BOD, mg/l
SS,mg/l
T-P, mg/l
Soluble P, mg/l
Primary effluent
BOD, mg/l
SS,mg/l
T-P, mg/l
Soluble P, mg/l
Final effluent, mg/l
BOD, mg/l
SS,mg/l
T-P, mg/l
Soluble P, mg/l
Alum dosage, mg/l
Primary process
Secondary
mg/l A|3+/mg/l P rem.
Single-Point
Alum Addition
14,000

115
197
8.4
2.9

62
89
4.5
2.0

11
10
0.65
0.18

0
64
1.3
Dual-Point
Alum Addition
17,000

138
182
5.2
1.8

52
64
2.7
0.9

17
14
0.36
0.06

16
32
1.1
A study was initiated in 1981 to assess the feasibility
of achieving effluent total phosphorus  concentrations
of 0.3 mg/l. It was originally intended that this would
be achieved through chemical  addition plus tertiary
filtration. However, initial jar tests indicated that  the
effluent P objective of 0.3 mg/l might be obtained by
dual point chemical addition without tertiary filters.
The first phase of the study involved  optimizing
existing  operations.  To  improve   mixing  and
flocculation, the point of chemical addition was moved
from a manhole between the aeration basins and final
clarifiers to a point near the  last air  diffuser in  the
aeration  basin.  This  allowed  reduction in the alum
dosage to 60 mg/l.

Full-scale  performance of dual  point  alum  addition
for phosphorus removal was  then investigated. The
scheme  involved  simultaneous  addition  of
approximately 20 mg/l of alum to the raw wastewater
at the aerated grit chamber and approximately 40 mg/l
of alum  to  the  tail  end of the  aeration  basin.  A
sampling program  was conducted  during the  period
September 1981 through June  1982 to  evaluate the
impact of dual chemical dosage  points. Data collected
during this period are also summarized in Table 4-9.

Comparison  of data  for the two periods shows  that
the use of dual point chemical addition improved the
removal of phosphorus  significantly without increasing
the overall alum dosage. Average  effluent P of 0.36
mg/l was achieved at an overall dosage of 48 mg/l
during dual  point addition,  whereas a dosage of 64
mg/l to the secondary process alone only achieved an
effluent P of  0.65 mg/l.  With  dual point  addition,
average soluble  P  in the effluent  was 0.06 mg/l,  vs.
0.18 mg/l with  single point chemical addition. Most of
the  phosphorus  leaving  the system during  either
period was  associated with suspended  solids. Note
that effluent SS and  BOD were  somewhat  higher
during this period,  possibly  due to the  fact that the
average  wastewater  flow  was  21  percent  greater.
Secondary clarifier average overflow rates were  also
higher at 35 m3/d/m2  (860  gpd/ft2) vs. 30 m3/d/m2
(750  gpd/ft2)  during single point  addition.  It  was
concluded that the  0.3  mg/l  P standard  could  be
consistently  met  with  dual   point,  flow-paced
chemical addition  with no  tertiary filtration. Clarifier
overflow rates are  critical  in maintaining low effluent
SS and total P levels.

4.7.2 Elizabethtown, Pennsylvania (13)
The wastewater treatment  plant serving the  City  of
Elizabethtown  consists  of  screening,  grit  removal,
flow  equalization,  primary  clarification, two  stage
trickling filter system,  rapid mix chambers, polymer
mix chambers, final clarification using clariflocculators,
and chlorination.  Primary and  secondary  sludge  is
blended,  thickened,  anaerobically digested,  and
applied to agricultural land. Alum or ferric chloride is
added to the rapid mix  chamber for phosphorus
removal.  Polymer  can  be   added  immediately
downstream of the rapid mix chamber in a separate
mixing  chamber. The  NPDES permit  requires the
plant to achieve the  following effluent quality:  BOD -
30 mg/l, SS - 30 mg/l, and total P - 2 mg/l.

Table 4-10 summarizes the performance of the plant
from July,  1985  through  April,  1986. Alum  and
polymer were  used  for phosphorus removal through
January of 1986, at which time  plant personnel began
using ferric  chloride  because of its anticipated lower
cost. When ferric  chloride  addition began, polymer
was no longer used.

During the  period  of  alum addition, average alum
dosage was 9.9 mg/l  as  Al, and average polymer
dosage was 0.4 mg/l.  The ratio of aluminum applied
to  phosphorus removed (AI:P) was 1.35. When alum
                                                  78

-------
Table 4-10.  Summary of Performance at Elizabethtown, PA (13)
                                                       30-Day Average Values
                                    BOD
         SS
Month

July, 19851
August1
September1
October1
November1
December1
January, 19861
February2
March2
April2
Ave. July-Jan1
Ave. Feb-Apnl2
Flow
m3/d
5,870
5,830
6,130
6,020
6,960
7,420
7,270
10,600
8,590
7,000
6,510
8,740
In
mg/l
157
175
140
142
106
91
120
66
88
110
133
88
Out
mg/l
7
18
8
6
3
4
5
7
6
8
7
7
In
mg/l
189
220
202
243
279
249
179
119
171
207
223
166
Out
mg/l
14
32
10
9
12
15
14
16
15
12
15
14
In
mg/l
7.03
7.03
7.03
9.5
8.1
6.0
6.6
3.6
6.0
5.6
7.3
5.1
Out
mg/l
2.2
2.0
0.7
0.9
0.9
0.8
1.0
1.4
1.9
1.8
1.2
1.7
1 Alum and polymer used for P removal. Alum dose = 9.9 mg/l as Al (AI:P = 1.35). Polymer dose = 0.4 mg/l.
2 Ferric chloride used for P removal. FeCIa dose = 7.1 mg/l as Fe (Fe:P = 1.39).
3 Estimated values.
and  polymer  were  replaced  by  ferric  chloride  in
February of 1986, average ferric chloride  dosage was
7.1 mg/l  as Fe, for an  AI:P  ratio of  1.39.  Plant
performance was similar  with  alum and  polymer vs.
ferric chloride. Concentrations  of BOD, SS, and P in
the  plant  effluent were  well within   discharge
requirements.

Data on sludge production (dry  solids basis) were not
available.  It  was estimated that  approximately 40
percent of  the  sludge  was chemical sludge  when
alum  and polymer were used,  and approximately 30
percent of  the  sludge  was chemical sludge  when
ferric chloride was used.

Estimated  unit  costs for  phosphorus  removal,
including  chemicals and  chemical sludge  disposal
were $3.52/kg ($1.60/lb) of P removed with alum and
polymer, and $2.73/kg  ($1.24/lb) of P removed using
ferric chloride (1986 costs).

4.7.3 Little Hunting Creek, Virginia (13)
The  Little Hunting Creek  wastewater treatment plant
provides  advanced secondary  treatment  using
single-stage  trickling filters. Unit  processes  consist
of raw  wastewater  screens, grit  chamber, primary
clarifiers,  trickling  filters,  secondary  clarifiers,  and
chlorine contact tanks. Secondary  sludge is returned
to the headworks for co-settling with primary sludge.
Waste sludge is conditioned with lime, dewatered by
vacuum filters, and hauled to  the Lower Potomac
Pollution Control Plant for  incineration.  Phosphorus is
removed by ferric chloride addition to a  manhole at
the  headworks, and  polymer addition:  1)  just
downstream of the Parshall flume and 2) between the
trickling filters and final clarifiers.  Effluent  discharge
goals are 20 mg/l BOD, 20 mg/l SS,  and 0.2 mg/l P
(voluntary).

Performance data  for the period  July 1984 through
June  1985  are  shown in Table 4-11. The  plant
effluent was  consistently  within NPDES  permit
requirements for  BOD  and SS.  Based on  30-day
average values, the plant met the  voluntary  effluent P
limit of 0.2 mg/l for nine of the twelve months.

Chemical requirements for the plant are high. Ferric
chloride dosage is approximately 125 mg/l (43 mg/l as
Fe), corresponding to a  Fe:P ratio of 4.7.  Total
dosage of  polymer  (two points of  addition)  is
approximately 2.8  mg/l.  The high dosages   are
indicative of difficulties involved in  retrofitting the plant
for phosphorus removal.

Physical restrictions which  prevent reduction of
chemical  dosages include:  1)  limited points  for
chemical addition,  2) non-ideal  conditions for mixing
and flocculation, 3) absence of a tertiary filter, and 4)
inability to accurately split the flow between the  two
trickling filters.  Dual  point chemical  addition  is  not
possible  because  the  shallow  depths of   the
secondary clarifiers are  insufficient to handle excess
chemical sludge.

Data on sludge production were not collected. It was
estimated that approximately 44 percent of the sludge
handled was  chemical  sludge  from  phosphorus
removal.
                                                  79

-------
Table 4-11.  Summary of Performance at Little Hunting Creek, VA (13)

                                                       30-Day Average Values
BOD
Month

July, 1984
August
September
October
November
December
January, 1985
February
March
April
May
June
Average
Flow
m3/d
16,200
15,200
14,100
13,900
13,700
13,900
14,100
17,300
14,500
13,400
13,600
13,200
14,400
In
mg/l
169
167
183
180
186
196
202
153
160
164
162
169
175
Out
mg/l
10
10
8
8
11
11
11
14
14
11
9
13
11
SS
In
mg/l
190
183
200
188
191
169
197
147
149
149
179
177
177
Out
mg/l
8.6
6.6
7.6
7.0
6.5
6.8
8.1
9.3
8.8
9.3
10.0
10.3
8.3
P
In
mg/l
9.9
10.0
9.4
10.1
9.7
10.1
9.0
8.3
8.9
8.6
8.4
9.2
9.3
Out
mg/l
0.22
0.16
0.15
0.16
0.15
0.17
0.20
0.22
0.19
0.16
0.20
0.26
0.19
The  unit  cost of  phosphorus  removal  including
chemicals, sludge conditioning, and chemical sludge
handling was estimated to  be $13.39/kg P removed
($6.08/lb  P).  Approximately 68 percent of this cost
was attributed to sludge handling.
 Table 4-12.   Cost  Estimates for Phosphorus Removal by
            Mineral Addition.
Flow Rate
m3/d
3,785
37,850
Chemical

Liquid alum
Liquid FeCI3
Liquid alum
Liquid FeCI3
Chemical
Dose8
mg/l
65
50
65
50
Installed
Equipment
Costb.c
$
75,60Qd
65,700
122,800
116,800
Annual
O&M
Costb>d
$/yr
44,000
40,000
328,000
369,000
  a Alum as AI2(S04)3«14H20
   Dosages are average values from Reference 23 for mineral
   addition to secondary processes to meet effluent TP = 1.0 mg/t.
  bCost estimates from EPA report,  Costs of Chemical
   Clarification of Wastewater, 1976, updated to May 1987.
  c Includes chemical storage and transfer  facilities, chemical feed
   pumps and piping,  and  rapid mix basin.  Does not include
   additional sludge handling equipment.
  «J Includes O&M  costs for  labor,  power  @  $0.06/kWh,
   maintenance materials and chemicals. Does not include O&M for
   handling additional sludge generated. Chemical costs based on:
     Liquid alum in bulk: $0.l7/kg
     Liquid FeCI3 in bulk: $0.20/kg
4.8 Costs
Table  4-12  summarizes  cost estimates  for  a
chemical addition  system  for  phosphorus  removal.
Capital  and operation  and  maintenance costs  are
presented for chemical feed systems for 3,785-m3/d
(1-mgd)  and   37,850-m3/d  (10-mgd)   plants.
Sludge handling costs are not included.  These costs
are planning level cost estimates (± 30 percent).
                                                      4.9 References
                                                      When an NTIS number is cited
                                                      reference is available from:
                               in a reference,  that
2.
  National Technical Information Service
  5285 Port Royal Road
  Springfield, VA 22161
  (703)  487-4650

DePinto, J.V., Switzenbaum, M.S., Young, T.C.
and J.K. Edzwald. Phosphorus Removal in  Lower
Great  Lakes  Municipal  Treatment  Plants.
Proceedings of International Seminar on Control
of Nutrients in Municipal Wastewater Effluents,
Volume  1:  Phosphorus.  San  Diego, CA.
September   9,   10,  and  11,  1980,   U.S.
Environmental Protection Agency, Cincinnati, OH,
1980.

Parker,  D.S.,  de  la  Fuente,  E.,  Britt,   L.O.,
Spealman, M.L.,  Stenquist, R.J. and F.J. Zadick.
Lime Use in  Wastewater Treatment: Design and
Cost  Data.  EPA-600/2-75-038, NTIS  No.
                                                   80

-------
    PB-248181,  U.S.  Environmental  Protection
    Agency, Cincinnati, OH, 1976.
    Proceedings No. 1,  Toronto,  Canada, May  28-
    29, 1973.
3.  Process  Design  Manual  for  Phosphorus
    Removal.  EPA-625/1-76-001a,  NTIS  No.
    PB-259150,  U.S.  Environmental  Protection
    Agency,  Center for  Environmental  Research
    Information. Cincinnati, OH, 1976.

4.  Heim,  N.E. and B.E.  Burris.  Chemical Aids
    Manual for Wastewater Treatment  Facilities.
    EPA-430/9-79-018,  NTIS   No.  PB-116816,
    U.S. Environmental  Protection Agency, Office of
    Water  Program  Operations,  Washington,  DC,
    1979.

5.  Lime  Handling Systems  - Problems  and
    Remedies.  U.S.  Environmental  Protection
    Agency,  Office  of  Municipal  Pollution Control,
    Washington, DC.

6.  Rupke, J.W.G. Operational  Experience  in
    Phosphorus  Removal.   In:  Phosphorus
    Management  Strategies  for  Lakes,  eds: R.C.
    Loehr,  C.S. Martin,  W. Rast. Ann Arbor Science
    Publishers,  Inc.,  Ann Arbor, Ml, 1980.

7.  Hatton, W.  and A.M. Simpson. Use of Alternative
    Aluminum Based Chemicals  in Coagulation with
    Particular Reference to  Phosphorus Removal.
    Environmental Technology  Letters  6:225-230,
    1985.

8.  Gulp,  R.L.,  Wesner, G.M. and G.L.  Gulp.
    Handbook of  Advanced  Wastewater  Treatment,
    Second  Edition.  Van  Nostrand  Reinhold
    Company, New York, 1978.

9.  Boyko,  B.I. and J.W.G. Rupke.  Phosphorus
    Removal Within Existing  Wastewater Treatment
    Facilities. Canada-Ontario Agreement on Great
    Lakes  Water Quality,  Project  No. 71-1-1,
    Ontario  Ministry of the  Environment, August,
    1976.

10.  Convery,  J.J.   Treatment  Techniques  for
    Removing  Phosphorus  from Municipal
    Wastewaters.  NTIS  No.   PB-199072,  U.S.
    Environmental Protection Agency, Water Pollution
    Control Research Series, 1970.

11.  Black, S.A.  Experience with Phosphorus Removal
    at  Existing Ontario Municipal  Wastewater
    Treatment Plants.  In: Phosphorus Management
    Strategies  for Lakes,  eds:  R.C. Loehr, C.S.
    Martin,  W.  Rast. Ann Arbor Science Publishers,
    Inc. Ann Arbor, Ml, 1980.

12.  Wilkes, W.  Phosphorus  Removal  by Chemical
   Addition Using Primary Treatment. In: Phosphorus
    Removal  Design Seminar,   Conference
13. Retrofitting POTWs for Phosphorus  Removal in
    the Chesapeake Drainage Area.

14. Nutrient Control. WPCF Manual of  Practice  No.
    FD-7,  Water  Pollution  Control  Federation,
    Washington, DC, 1983.

15. Laughlin, J.E. Designing to  Remove  Phosphorus
    by  Using  Metal  Salts  and  Polymers  in
    Conventional Plants. Presented at  EPA  Design
    Seminar  for Wastewater  Treatment Facilities,
    Denver, CO, October  31-November 2, 1972.

16. Daniels,  S.L.  Instrumentation and Automatic
    Control of Phosphorus Removal  Processes.  In:
    Phosphorus  Removal   Design  Seminar,
    Conference Proceedings No. 1, Toronto, Canada,
    May 28-29,  1973.

17. Culver,  R.H. and  D.  Chaplick. Programming
    Phosphate Treatment  Saves Money. Water and
    Sewage Works, March:84-87, 1978.

18. Damhaug, T.  and  K.T. Nedland.  Alkalinity Feed
    Forward Control of Alum Addition in  Wastewater
    Treatment-Field Experience.  In: Management
    Strategies for  Phosphorus  in the Environment,
    Proceedings of the  International  Conference.
    Lisbon,  Portugal.  Edited  by J.N.  Lester and
    P.W.W. Kirk. Selper Ltd., London,  1985.

19. Damhaug, T.,  Ferguson,  J.F.  and H.  Buset.
    Control  of  Alum  Addition  in  Wastewater
    Treatment. Water  Science  Technology  13:531-
    537, 1981.

20. Barth,  E.F.  and  H.D. Stensel. International
    Nutrient  Control  Technology for  Municipal
    Effluents. JWPCF 53(12):1691-1701,  1981.

21. Clarifier  Design. WPCF Manual of Practice No.
    FD-8,  Water  Pollution  Control  Federation,
    Washington, DC, 19xx.

22. Singhal, A.K. Phosphorus and Nitrogen Removal
    at Cadillac,  Michigan. JWPCF 52(11):2762-
    2770, 1980.

23. Process Design Manual  for Suspended Solids
    Removal.  EPA-625/1-75-003a,   NTIS  No.
    PB-259147,  U.S.  Environmental  Protection
    Agency,  Center  for  Environmental  Research
    Information, Cincinnati, OH, 1975.

24. Simplified  Procedures for  Water Examination.
    AWWA Manual M12,  American Water  Works
    Association.
                                              81

-------
25. Archer, J.D.  Summary  Report  on phosphorus
   removal. Canada-Ontario Agreement on  Great
   Lakes  Water  Quality,  Project No.  75-1-42,
   Ontario Ministry of the  Environment, Toronto,
   1975.

26. Wastewater  Treatment Plant  Design. ASCE
   Manual No. 36, WPCF Manual of Practice No. 8,
   American Society of Civil Engineers,  New York,
   NY  and Water Pollution Control Federation,
   Washington, DC, 1977.

27. High Level Phosphorus  Removal from W.P.C.P.
   Effluent; City of Orillia; Final Report. Prepared by
   Ainley and Assoc.  for  Ontario  Ministry of the
   Environment, Rexdale, Ontario, September, 1982.
                                                82

-------
                                            CHAPTER S
                                         Sludge Handling
5.1  Introduction
The importance of  sludge handling in the design of
new facilities or in the retrofitting of existing plants for
phosphorus removal cannot be over emphasized. The
difficulty  in predicting  generation  rates  and
characteristics of sludges derived from phosphorus
removal operations  is further complicated by the wide
variability  of data  and  the  inconsistent information
reported from operating phosphorus removal facilities.

Retrofitting of existing facilities to achieve phosphorus
removal  presents  difficult  design  challenges  with
respect to sludge handling. For example, addition of
chemicals  to precipitate  phosphorus from  the liquid
stream is relatively  straightforward and  can  be
implemented with relatively  small capital expenditure.
However,  the additional  sludge generated  and  the
impact on  sludge characteristics can easily result in
overloading of  existing  thickening, stabilization, and
dewatering equipment, or require significant increases
in operational staff time to operate and maintain this
equipment.  Installation  of new  capital-intensive
equipment may be required  to effectively process the
additional  sludge.  On  the  other hand,  at some
facilities, implementation of  a  phosphorus  removal
system may not significantly  impact  the existing
sludge handling  operation.  Such variability  of
experience with  sludge handling at plants removing
phosphorus  makes development  of  firm  design
recommendations difficult.

The objectives of this chapter are to:

1. Present  information on  the quantities  and
   characteristics of sludges derived from chemical
   and biological phosphorus removal processes.

2. Provide specific recommendations for the design of
   sludge handling processes and  equipment used in
   plants removing phosphorus.

3. Summarize the  experience  with  sludge  handling
   processes at  full-scale phosphorus  removal
   facilities.

It  should  be noted that, in some  cases,  specific
design criteria cannot be presented because  of the
wide variability  in sludge characteristics,  resulting in
variations  in  performance of  sludge handling
processes  and  equipment. In these instances, full-
scale  experience is summarized  and  a  design
approach is outlined.


5.2  Current  Practice  for  Handling
Chemical Sludges

5.2.7 Introduction
In 1976 and 1977,  an  extensive EPA-sponsored
survey was conducted of 174 municipal  wastewater
treatment  plants  in the  United States and  Canada
which used chemicals to remove phosphorus  (1). The
purpose of this  survey was to quantify the effects of
chemical addition on the sludge handling and  disposal
operations  at full-scale plants.

This section  summarizes  the results of  this survey
with regard  to the  types  of  facilities,  points  of
chemical  addition,  sludge  generation  rates,  and
prevalence of various sludge treatment and  disposal
methods.  Information regarding  the  impacts  of
chemical addition on  unit sludge handling processes
is provided under those sections of this chapter which
deal with  sludges  derived  from  use  of  specific
chemicals.
5.2.2 Points of Chemical Addition and Methods of
Combining Sludges
Table 5-1  shows a  breakdown of the  174 plants  by
point(s) of chemical  addition and by how the chemical
sludges are  combined  with  organic sludges  at
different locations within the plant.

Chemical  addition to  secondary treatment was  the
most common  option practiced,  accounting for  62
percent of the  plants surveyed. Twenty-six  percent
of the plants added chemicals to primary treatment, 5
percent of the plants added chemicals to both primary
and secondary treatment, and 6 percent of the plants
added chemicals to tertiary facilities.

Of the plants practicing  chemical addition to  primary
treatment and generating both primary and secondary
sludges, 94  percent of the plants  combined  their
                                                 83

-------
Table 5-1.   Combination of Chemical Sludges with Other Sludges for Processing as Practiced by Plants in EPA Survey (1).
 Point at Which Chemical
 Sludges and Other
 Sludges were Comvined
                                            Number of Plants by Point(s) of Chemical Addition
Primary
Addition
Secondary
 Addition
Tertiary
Addition
Primary and
Sec. Addition
 Primary and
Tert. Addition
Sec. and Tert.
  Addition
Total
 Plants w/o primary or
 secondary clarification
 No primary clarifier
 No secondary clarifier
  NA1
   13
    28
    NA
    1
   NA
     NA
     NA
     NA
     NA
      1
     NA
 30
 13
Plants with primary and
secondary clarification
Sludges not combined
Combined in or before
primary clarifier
Combined in or before
thickener
Combined in or before
digester
Combined in or before
dewatering device
Total


2
12

13

6

0

46


10
26

14

24

6

108


6
0

2

2

0

11


1
3

1

3

0

8


0
0

1

0

0

1


0
0

0

0

0

1


19
41

31

35

6

1752
  1 Not applicable.
  2 One plant with tertiary addition is counted twice because it has no primary sludge and it has secondary and tertiary sludges which are not
   combined.
chemical  primary  sludges with  organic  secondary
sludge before processing. Of these plants combining
their  sludges, 39 percent  accomplished this  by
returning secondary sludge to the primary clarifiers.
The  remainder combined their sludges in or before
thickening, stabilization, or dewatering processes.

Of  the  plants practicing  chemical  addition  to
secondary  treatment and  which generated  both
primary and secondary sludges, 88 percent combined
their  sludges  before  processing.  Of  the  plants
combining  their sludges, 37 percent practiced this by
returning secondary sludge to the primary  clarifier.
5.2.3   Sludge   Generation  Rates   and
Characteristics
The  additional  sludge  generated  from  use  of
chemicals  for  phosphorus precipitation is a  key
design  consideration.  Although chemical addition to
the liquid stream is easily implemented, the impacts
on thickening,  stabilization, dewatering, and  disposal
operations are often severe. This is due to  both the
additional mass and volume of sludge generated as
well  as the effects  on  thickening and  dewatering
characteristics.

Figure  5-1  summarizes volumes of sludge produced
(before thickening) per cubic meter of  influent flow as
reported in the EPA  survey of  174 plants  (1).  It is
apparent that  lime addition  produced significantly
greater volumes of sludge than mineral salt addition.
Chemical addition  to  secondary  processes produced
greater volumes of sludge than  chemical addition to
the primary when considering  primary and secondary
processes separately.  However, on a total plant basis,
the additional sludge volumes resulting from  chemical
                              addition  were  approximately  equivalent for  both
                              primary and secondary chemical addition.

                              Average increases in sludge volume before thickening
                              were 25 percent for iron salt addition, 58 percent for
                              aluminum  salt addition,  and several hundred percent
                              for lime addition (1). Bear in mind that  these figures
                              are volumes  before thickening, and as such do not
                              take  into  account  the  relative   thickening
                              characteristics of sludge which  will  affect  volumes
                              requiring dewatering; nor do they  consider dewatering
                              characteristics which will affect volumes  requiring final
                              disposal.

                              It  is important to  note  that  the  reported  sludge
                              volumes represent a diverse array of plants with wide
                              ranges  of wastewater  characteristics,  treatment
                              process configurations, operating  modes, and effluent
                              quality, all  of which  significantly impact  sludge
                              generation rates. Therefore, these figures  are  for
                              illustrative purposes only, and should not be  used for
                              design.

                              Figure 5-2 summarizes  mass sludge production data
                              from the  EPA survey (1). Values are  expressed as
                              kilograms of dry solids  per cubic  meter  of influent
                              flow.  Again,  it should  be noted that  these figures
                              represent plants with wide ranges of wastewater and
                              process characteristics,  which can significantly impact
                              the mass of sludge  generated. Use of these figures
                              for design  purposes or  chemical  selection is  not
                              recommended.

                              Table  5-2 summarizes  data on solids content  of
                              chemical  sludges at  the  174 plants surveyed in  the
                              EPA-sponsored  study.  The  total and  volatile  solids
                              content are for the sludges prior to thickening or other
                                                   84

-------
Figure 5-1    Volumetric sludge production from EPA survey - m3 sludge/m3 plant influent (1).
       Chemical Added
       to Primary-
       Primary
       Sludge
       Only
                 35,200
      4,190
            2,710
Chemical Added
to Secondary-
Secondary
Sludge
Only
                             17,080
                                   8,300
                                                                    60,350
Chemical Added to Primary -
Total Plant Sludge
                                              5.88C
                                                   4,710 4.750
                                                               3,000
   |	I    Iron Salt Addition Plants


   ^^m    Iron Salt Addition Plants Prior to P Removal


   E%%1    Lime Addition Plants
Chemical Added to Secondary •
Total Plant Sludge
                                                      4,650 4,640
                                                                                            5.71C
                                                                                                  5.110
                                       Aluminum Salt Addition Plants


                                       Aluminum Salt Addition Plants Prior to P Removal
                                                       85

-------
Figure 5-2   Mass sludge production from EPA survey - kg sludge/m3 plant influent (1).
       Chemical Added
       to Primary-
       Primary
       Sludge
       Only
                  0.44
       0.18
             0.12
Chemical Added
to Secondary-
Secondary
Sludge
Only
                              0.10
                                    0.09
Chemical Added to Primary -
Total Plant Sludge
                                                                       0.54
                                                           0.34
                                                0.27
                                                      0.17
                                                                 0.29
                                                                       I
                                           I
Chemical Added to Secondary
Total Plant Sludge
                                                       0.22
                                                                                              0.21
                                                                                        0.18
                                                                                                    0.17
   I      1     Iron Salt Addition Plants
              Iron Salt Addition Plants Prior to P Removal


              Lime Addition Plants
                                       Aluminum Salt Addition Plants


                                       Aluminum Salt Addition Plants Prior to P Removal
                                                        86

-------
 processing.  For chemical  addition  to  primary
 treatment, iron sludges had the highest  average total
 solids content at 5.26 percent compared  to  alum
 sludge at  3.95  percent  and lime  sludge at 1.1
 percent.   For chemical  addition   to  secondary
 treatment, secondary  biological-iron   sludge had  an
 average total  solids content of 0.93 percent vs. 1.41
 percent  for  biological-aluminum  sludge. When
 combined  with primary sludges, the sludge  solids
 contents for iron  and aluminum addition  to secondary
 treatment  were similar at 4.13 and 3.82  percent,
 respectively.  Although these data   are  useful for
 illustrative purposes, the  values  are averages
 obtained  from plants  with different  wastewater and
 process  characteristics.  This may  explain  some
 inconsistencies in the data.  For example,  for  iron
 addition to primary treatment,  total solids for primary
 sludge is  5.26  percent,  while total  solids for the
 combined  (total  plant) sludge is  5.73  percent.  In
 practice,  this  would  not occur,  since  secondary
 sludge always has a  significantly lower total  solids
 content than primary sludge.

 5.2.4 Prevalence of Various Sludge  Treatment and
 Disposal Options
 Table 5-3 summarizes the responses  from plants
 contacted  in the  EPA  survey  regarding  the  types  of
 processes  employed  for thickening,  stabilization,
 conditioning,  dewatering, drying,  reduction, and
 disposal of sludge.

 Of the thickening options, gravity thickening was by
 far the most prevalent,  as  would be expected. In most
 cases,  flotation thickening was  used for secondary
 sludge only. The five  plants which used centrifuges
 for thickening added  lime to primary treatment for
 phosphorus removal.

 Aerobic and  anaerobic  digestion  were the  most
 prevalent  stabilization techniques. Of the plants using
 iron salts,  20  percent used aerobic digestion. Of the
 plants using aluminum  salts, 46 percent used aerobic
 digestion,  while 54 percent used anaerobic digestion.

 Chemical conditioning was the  most prevalent method
 of  conditioning,  followed  by  thermal conditioning.
 Seventy-five percent of the  plants  using iron  salts
 and 74 percent of the plants using  aluminum  salts
 employed  chemical conditioning.

 Sand drying beds and  vacuum filters  were the  most
 prevalent dewatering  techniques. Of the  plants using
 iron salts, 49 percent used sand drying beds and 34
 percent used  vacuum  filters.  Of the plants  using
 aluminum  salts, 44 percent used sand drying  beds,
24 percent used vacuum filters, and 11 percent  used
centrifuges. None of  the plants using iron employed
centrifuges for dewatering.
 Three plants in the survey reported using heat dryers
 for further sludge volume  reduction,  and 22 plants
 employed multiple hearth or fluidized bed incineration.

 The most  prevalent  means of final  sludge  disposal
 was application to agricultural land, lawns, or gardens,
 accounting  for 52 percent  of  the  plants surveyed.
 This  was followed by sanitary landfill (27 percent),
 private  or  authority-owned dump site (16 percent),
 and land reclamation (5 percent).


 5.3  Sludge  Derived  from  Addition  of
 Aluminum Salts

 5.3.7 Sludge Characteristics
 Aluminum  salts may be employed for phosphorus
 removal by  addition to primary, secondary, or tertiary
 treatment processes.  Secondary addition is the most
 common, accounting for approximately 82  percent of
 the plants using aluminum salts as determined by  the
 EPA  survey (1).  Addition  of  aluminum  to  primary
 treatment accounted  for only about 14 percent of  the
 plants using aluminum salts. The few remaining plants
 added aluminum salts to tertiary treatment (3 percent)
 or  to  both  primary  and  secondary  treatment  (1
 percent).

 Sludge  characteristics are  dependent  on  numerous
 factors  including  wastewater composition,  chemical
 dosage, point  of chemical  addition  (primary,
 secondary  or tertiary), whether the various  sludges
 are  combined  before  processing  and  in  what
 proportions, detention time  in  clarifiers  or   holding
 tanks,  and  other factors. Although it  is  difficult to
 predict the impact of chemical addition on  thickening
 and dewatering characteristics, two conclusions can
 be drawn with some certainty:

 1. That the addition of aluminum salts will result in an
  increase in sludge volume and mass, and

 2. The thickening and dewatering characteristics  will
  likely be different than if no chemical were added.

 Actual  experience  with processing  chemical -
 biological  sludges has been extremely variable.  In
 some  cases,  chemical  addition  has  improved
thickening and dewatering  characteristics,  while  in
other  cases chemical  addition  has had a detrimental
impact. Many problems can be traced to overloading
of unit processes  due to increased volumes of sludge
from chemical addition.

Knowledge  of general  sludge characteristics and
chemical dosages is generally  of  little  value  in
predicting  the amenability of sludges  to thickening,
dewatering, and stabilization processes. This is due to
the interaction and impact of the host of factors which
affect performance of sludge processing operations.
Design of sludge handling systems must therefore  be
                                                 87

-------
Table 5-2.   Combination of Chemical Sludges with Other Sludges for Processing as Practiced by Plants in EPA Survey (1).

                                                    Sludge Characteristics (before processing)
Type of Chemical Sludge and Whether
Combined with Other Plant Sludge(s)
Iron addition to primary
Primary sludge
Total plant sludge
Iron addition to secondary
Secondary sludge
Total plant sludge
Iron addition to tertiary
Tertiary sludge
Total plant sludge
Alum addition to primary
Pnmary sludge
Total plant sludge
Alum addition to secondary
Secondary sludge
Total plant sludge
Lime addition to primary
Primary sludge
Total plant sludge
Lime addition to tertiary
Tertiary sludge
Total plant sludge
i oiai ooiio
Range

3.4 - 8.0
2.31 - 10.0

0.2 - 4.0
0.5 - 7.75

4.0
4.64 - 5.0

3.3 - 43.5
3.96 - 5.0

0.4 - 4.4
1.0 -7.0

0.7 - 1.5
0.64 - 0.82

2.5 - 4.0
1.95
s, percent
Average

5.26
5.73

0.93
4.13

4.0
4.82

3.95
4.49

1.41
3.82

1.1
0.73

3.3
1.95
voiatue s>(
Range

45-69
40 -70

50-70
45 - 72

35
62

61 -67
46-70

60-78
52-70

N/A1
N/A

11-30
39
anas, percent ot 1 1>
Average

57
57

62
62

35
62

65
59

67
59

N/A
N/A

21
39
  1 Not available.
based, at a  minimum, on laboratory tests such  as
settlometer  tests,  specific  resistance, filterleaf,
capillary suction  time,  and  other  tests.  Where
possible, pilot-  or full-scale units should  be used to
establish design  criteria  for  full-scale  sludge
thickening and dewatering devices.  Specific tests
used to characterize sludges resulting from chemical
phosphorus  precipitation  processes are discussed in
subsequent sections of this manual.

5.3.2 Sludge Generation Rates
As  previously  discussed, addition  of chemicals  to
remove phosphorus will increase the mass of sludge
generated.  This increase can  be attributed to three
components (2):

1. Formation  and  removal of chemical solids such as
  metal phosphates and  metal hydroxides,

2. Improved  removals  of  organic  solids  during
  clarification, and

3. Removal of dissolved solids.

Several methods are  available  to estimate  sludge
generation  rates  for  design  purposes. When  an
existing  plant is  to  be upgraded for  chemical
phosphorus  removal, the preferred approach is to
conduct  full-scale trials  at the facility and measure
sludge  production  under  expected   operating
conditions.  This allows optimization of  chemical
dosages  and determination  of the  impact  of
operational changes  such as modification of sludge
age. For new facilities, pilot plant tests  are the best
approach to estimate  sludge generation  rates.
However, such studies are costly and  may  not  be
economically feasible for  small plants. In such cases,
jar  tests should be  performed  to  provide  data to
estimate additional sludge  generation resulting from
chemical addition,  although such tests  may  not  be
representative  of  full-scale,  dynamic  conditions.
Procedures  are also  available to allow calculation of
the  theoretical  mass of  solids  generated  from
wastewater  treatment schemes  employing chemical
phosphorus precipitation  (2-4).  An  approach is
described  below  for  estimating  the  quantity  of
additional sludge  resulting from  use  of  alum  for
phosphorus  removal. A  procedure  for calculating
baseline sludge production (no chemical  addition) has
not been shown, since this is described in detail in
Reference  4 for  several types of  treatment  (e.g.
processes activated sludge, trickling filter, etc.).

Additional sludge  generated  as a  result of  alum
addition is due to formation and  removal of chemical
solids, improved removal of  suspended solids,  and
removal  of dissolved solids. Another  consideration in
estimating sludge  production is  that the quantity of
biological sludge which is generated may be affected
by  selection of the  point  of chemical  addition. For
example, while alum addition to the primary  clarifier
will  increase  the  production  of  primary  sludge,
improved BOD and SS removal  in primary treatment
will  reduce the  organic  loading  to  downstream
                                                  88

-------
 Table 5-3.    Prevalence of Treatment and Disposal Processes for Chemical Sludges Among Plants in EPA Survey (1)*.

                                           Major Chemical Used and Point of Addition
Sludge Treatment
and Disposal Unit
Thickening
Gravity
Flotation
Centrifuge
Stabilization
Composting
Aerobic digestion
Anaerobic digestion
Lime stabilization
Conditioning
Chemical conditioning
Elutriation
Thermal conditioning
Dewatering
Pressure filter
Sand drying bed
Centrifuge
Vacuum filter
Lagoon
Hor. moving screen
concentrator
Cylindrical rotating
gravity filter
Heat Drying
Flash dryer
Multiple hearth dryer
Reduction
Incineration
Final Disposal
Land reclamation
Sanitary landfill
Agricultural fields
lawns, gardens
Private- or authority-
owned dump site

Primary

18
1
0

1
4
27
0

11
1
2

1
17
0
12
4
0

0


0
0

7

0
16
18

8

Iron Salt
Sec.

25
4
0

0
11
37
0

12
2
4

3
20
0
13
4
0

0


0
1

5

1
18
39

10

Aluminum Salt
Tertiary

2
0
0

0
1
1
0

1
0
0

0
0
0
1
1
0

0


0
0

0

0
1
1

0

Primary

4
0
0

1
1
5
1

2
0
1

1
2
1
1
1
0

0


0
0

0

1
1
7

2

Sec.

18
5
0

0
24
25
0

12
0
4

1
18
4
10
3
2

1


1
1

5

6
13
30

8

Tertiary

1
0
0

0
0
1
0

0
0
0

0
0
0
0
1
0

0


0
0

0

0
0
1

0

Primary

8
0
5

0
0
1
0

2
0
0

2
1
0
0
0
0

0


0
0

5

1
4
5

2

Lime
Sec.

0
0
0

0
0
0
0

0
0
0

0
0
0
0
0
0

0


0
0

0

0
0
0

0


Tertiary

0
0
0

0
0
0
0

0
0
0

1
0
1
0
2
1

0


0
0

0

0
0
1

1

Total

76
10
5

2
41
97
1

40
3
11

8
58
6
37
16
3

1


1
2

22

9
53
102

31

  * One plant may use more than one method of thickening, dewatenng, etc.
biological processes and, hence, reduce the quantity
of biological  solids  generated.  A  procedure  for
estimating quantities  of additional sludge  resulting
from alum addition is given below.

a. Chemical sludge
This calculation assumes  that the aluminum reacts
with  phosphorus compounds first, and  that excess
aluminum forms aluminum hydroxide.

Given:

Pin = 8 mg/l
pout = 1  mg/l
AI:Pdose = 2.2:1
Atomic weight of P  =  31
Atomic weight of Al = 27
Atomic weight of AIPO4 =122
Atomic weight of AI(OH)3
Al dose =  2.2 x 8 x (27/31)  = 15 mg/l

Stoichiometry:

Al + P04 = Al PO4
Al + 3 OH = AI(OH)3

(8 - 1 mg/l P)  v  31  = 0.23 mmole/l AIPO4
                              produced

(15  mg/l Al)  * 27 =  0.56 mmole/l Al added

0.56 - 0.23 =  0.33  mmole/l Al in  excess to AI(OH)3

AIPO4 sludge: 0.23 mmole/l x 122 = 28.1 mg/l AIPO4

AI(OH)3 sludge: 0.33 mmole/l  x 78 = 25.7 mg/l
                                    AI(OH)3

Total chemical sludge:    28.1 mg/l AIPO4
                        25.7 mg/l AI(OH)3
                                                  89

-------
                        53.8 mg/l Al sludge

Chemical sludge produced = 53.8 mg sludge/liter of
wastewater treated (449 lb/106 gallons).

Because the stoichiometry is only an approximation of
the chemical reactions  which  occur,  and because
some data indicate greater  quantities  of  chemical
sludge than predicted,  it has been recommended that
the calculated sludge  production value be  increased
by 35 percent (2).

Design estimate of chemical sludge production:

1.35 x 53.8 mg/l = 72.6 mg sludge/liter of wastewater
                  treated (605 !b/106 gallons)

b. Sludge  from improved removal  of suspended
solids
Additional  sludge resulting from  improved suspended
solids removal  is calculated by assuming  a  greater
removal  efficiency.  For  example,  in primary
clarification without chemical addition,  removals of
suspended solids are typically 50 percent. With alum
addition, however, removal efficiencies may be 75
percent or greater.  The additional sludge  generated
by  chemical  addition  to  the  primaries can  be
calculated as shown below.

Given:

SSjn  =  200 mg/l
SS removal efficiency (no chemicals) = 50  percent
SS removal efficiency (with alum) = 75 percent

Additional  sludge generated:

(0.75 - 0.50)  x 200 mg/l = 50 mg  sludge/liter  of
                        wastewater treated
                        (417 lb/106 gallons)

When aluminum is added to the secondary biological
process such as the activated sludge basin, additional
sludge production from improved SS removal may not
be evident.  However, generation  of chemical solids
(AIPO4 and  AI(OH)3)  can be assumed  to  be
approximately  equal  regardless of  the point of
chemical addition.  For  a well operated  standard rate
activated sludge plant, addition  of aluminum  salts to
the  aeration basin  may have little  impact  on
clarification efficiency.  However, for some high rate
activated  sludge  or trickling filter plants,  secondary
clarification  efficiency  may  improve  significantly,
resulting  in  additional  sludge  production.  An
improvement  in  effluent  suspended  solids
concentration from 20 to 10 mg/l will  result in 10 mg
of additional sludge per liter of wastewater treated (83
Ib per million gallons).

For tertiary  applications  of   aluminum  following
secondary  biological  treatment, additional  sludge
resulting from improved removal of SS will generally
be small. Estimates of tertiary sludge production from
SS  removal  are   based  on  anticipated  SS
concentrations in secondary and tertiary effluents.

c.  Sludge from removal of dissolved solids
Data exist to show that dissolved solids are removed
as  a result of  chemical addition (2).  Reported
removals of soluble  TOG are about  30%  percent
using alum. Removal of  soluble  COD  has  been
reported to be approximately 40  percent.  The sludge
mass resulting from removal of dissolved  solids must
be  estimated indirectly from  soluble TOG, COD, or
BOD  loadings.  The  following relationships  can  be
used  for  this  purpose.  The derivation of  these
relationships may be found in Reference 2.

Sludge  mass resulting  from  removal  of dissolved
solids  (assuming 30 percent  removal  of  soluble
organics)

   = STOCjn (mg/l) x 0.30 x 2.5 x 1.18
   = SCODjn (mg/l) x 0.30 x 1.1  x 1.18
   = SBODjn (mg/l) x 0.30 x 1.6 x 1.18

where:

   STOCjn  = soluble  TOG in influent
   SCODjn  = soluble  COD in  influent
   SBOD,n  = soluble  BOD in influent

The latter two  equations  are only  applicable to
influents prior to biological oxidation processes (2).

d. Design example
Estimate the  sludge  production  from  a  3,785-m3/d
(1-mgd) conventional  activated sludge  plant with and
without alum addition  to the primary clarifier.

Given:

Pin = 8 mg/l
BODjn = 200 mg/l
SSjn  =  220 mg/l
VSS  =  0.75 x SS
STOCjn =  50 mg/l

Sludge from primary treatment without alum addition:

Assume 50 percent  SS  removal,  30  percent BOD
removal;

0.5 x 220 mg/l x 3,785 m3/d x 0.001 =416 kg/d
                                    (917lb/d)

Sludge from primary treatment with  alum addition:

Assume 90  percent P  removal, 75 percent  SS
removal, 50 percent BOD removal, 30  percent STOC
                                                 90

-------
removal (from test results); assume AI:P dosage ratio
of 2.0 (from test results)

Al dose =  (2.0 x 8 mg/l) x (27/31) = 13.9 mg/l Al
P removed = 0.90 x 8 mg/l = 7.2 mg/l P
AIPO4 sludge = 7.2/31  = 0.23 mmole/l AIPO4
Total Al added =  13.9/27 = 0.51 mmole/l Al
Excess Al =  0.51 - 0.23 = 0.28 mmole/l  Al
AIPO4 sludge = 0.23 x  122 = 28.1 mg/l AIP04
AI(OH)3 sludge = 0.28  x 78 =  21.8 mg/l AI(OH)3

Total chemical sludge produced:
28.1 mg/l  +  21.8 mg/l  = 49.9 mg/l

Design chemical sludge production:
49.9 mg/l x 1.35 = 67.4 mg/l
       or
67.4 mg/l x 3,785 m3/d x 0.001  = 255 kg/d (562 Ib/d)

Sludge from SS removal:
0.75 x 220 mg/l x 3,785 m3/d x 0.001 =  625 kg/d
                                   (1,375 Ib/d)

Sludge from removal of dissolved solids  (DS):
50 mg/l x 0.30 x 2.5 x 1.18 = 44.2 mg/l
      or
44.2 mg/l x 3,785 m3/d x 0.001 = 167 kg/d (368 Ib/d)

Secondary sludge - no  alum addition to primary
(from reference 4):
WAST =  PX  +
                nv
Px  = Y (Sr) -  Kd (M)
    =  (Y) (Sr) /(1  + Kd SRT)

where:

  WASj = waste activated sludge production, kg/d
  Px     = net growth of biological solids (VSS), kg/d
  lnv     = inert SS fed to process, kg/d
  ET    = effluent SS, kg/d
  Y     = gross yield coefficient, kg/kg
  Sr     = BOD removed, kg/d
  Kd     = decay coefficient,  day1
  M     = system  inventory  of microbial solids
           (VSS), kg
  SRT   = solids retention time, days

Assume:

Y = 0.67 kg/kg  from test data
Kd  =  0.06 day-1 from test data
BODout = 15 mg/l
SRT =  10 days

BODm - BODout = (1 - 0.3) (200 mg/l) - 15 mg/l
Sr = 125 mg/l x 3,785 m3/d x 0.001
   = 473 kg/d

Px =  (0.67 kg/kg x 473 kg/d)/[1 + (.06 d-1) (10 d)]
   = 198 kg/d

Inert SS feed = (1  - 0.5) (1 - 0.75) (220 mg/l)
            = 27.5 mg/l

lnv  = 27.5 mg/l x 3,785 m3/d x 0.001
    = 104 kg/d

Assume effluent SS = 20 mg/l;

ET  = 20 mg/l x 3,785m3/d x 0.001
    = 76 kg/d

WAST =  Px +  lnv - ET
      =  198 kg/d  +104  kg/d - 76  kg/d
      = 226 kg/d (498  Ib/d)

Secondary sludge - alum  addition to primary:

Calculate reduced BOD loading due  to improved BOD
removal in primaries;

BODjn =  (1 - 0.5) (200 mg/l) (3,785 m3/d)  (0.001)
       =  379 kg/d

BODout =  15 mg/l x 3,785 m3/d x 0.001
       =  57 kg/d

(assumes  no  improvement in secondary effluent
quality)

Sr =  379  kg/d - 57 kg/d  =  322 kg/d

Px =  (0.67 kg/kg x 322 kg/d)/[1 + (.06 d-1) (10 d)]
   = 135 kg/d

Inert SS feed = (1  - 0.75) (1 - 0.75) (220 mg/l)
            = 13.8 mg/l

lnv  = 13.8 mg/l x 3,785 m3/d x 0.001
    = 52 kg/d

Assume effluent SS = 20 mg/l;

ET  = 20 mg/l x 3,785m3/d x 0.001
    = 76 kg/d

(assumes  no  improvement in secondary effluent
quality)

WAST = Px +  lnv  -  ET
      = 135 kg/d  +52 kg/d - 76 kg/d
      = 111 kg/d (224 Ib/d)
                                                91

-------
Summary of sludge production calculations:
                      Table 5-4.   Typical Gravity Thickener Design Criteria.
                           Sludge production, kq/d
                            w/o alum      w/alum
Primary clarifier
SS sludge
DS sludge
Chemical Sludge
Total

Secondary clarifier
WAS

Total sludge

5.3.3 Thickening
416
  0
  0
416
226
642
  625
  167
  255
1,047
  111
1,158
5.3.3.1 Gravity Thickening
Relatively little definitive design  and  performance
information  is available  in the  literature  for  gravity
thickening of alum sludges. Thickening characteristics
of sludges generated from plants practicing chemical
phosphorus  precipitation  will vary  depending  on
wastewater characteristics, point of chemical addition,
chemical  dosage, wastewater treatment  processes
employed,  whether  sludges  are  combined  before
thickening,  relative  proportions of  chemical  and
biological sludges,  sludge  characteristics   before
thickening, and  other factors.  Because of the wide
variability in thickening characteristics,  thickening
tests  should  be  conducted  whenever  the  actual
sludge is available,  as  in the case  of retrofitting  or
expanding existing facilities. In such  cases, full-scale
trials  with  chemical  addition  are  recommended  to
generate representative  samples   of  sludge  for
conducting thickening  tests.  Procedures  for
conducting  such tests  may be  found elsewhere (5-
8).

In some cases where new treatment facilities are to
be designed, the design engineer does not have the
benefit of  having  existing  sludges  on which  to
conduct  thickening tests, and  must rely on published
design guidelines. Table 5-4 provides design  criteria
for  thickeners  receiving  various types  and
combinations of alum and  non-chemical sludges.

In addition  to mass  loading  criteria  shown  in Table
5-4, hydraulic  loading  must  also be considered in
the design of gravity thickeners. For  primary sludges,
typical maximum  overflow rates are 24-30 m3/m2/d
(600-720 gpd/ft2).  However, for  waste activated
sludge  or  combinations of primary  and  waste
activated sludges, hydraulic loadings  rates should  be
lower than  this, 4-8  m3/m2/d (100-200 gpd/ft2) (4).

Experience  with  thickening of  alum  sludges  in
combination with  non-chemical sludges has been
highly  variable.  Some  reports  indicate   an
improvement in thickening characteristics of sludges
Sludge Type

Primary
Primary w/alum1
Primary + WAS
(Primary w/alum)
+ WAS
Primary + (WAS
w/alum)
WAS
WAS w/alum
Tertiary w/alum2
Influent
Solids
Cone.
percent
2-7
2.1-3.7
0.5-1.5
-
0.2-0.4
0.5-1.5
0.5-1.5
0.5-1.5
Expected
Underflow
Cone.
percent
5-10
2.5-6.7
4-6
-
4.6-6.5
2-3
1.5-2.0
2.5-3.0
Mass
Loading
kg/m2/hr
3.9-5.9
0.4-1.0
1.0-2.9
-
2.4-3.4
0.5-1.5
0.6-0.8
0.6-1.0
Ref.

g
10
8
-
8
9
11
12
                       1 Data reflect use of anionic polymer to assist in thickening.
                       2 From water treatment  plant  sludge containing alum  and
                        powdered activated carbon.

                      when alum  addition  was  initiated; others show
                      detrimental impacts on thickener performance (1,3).
                      Unfortunately,  in  the  latter cases,  it is difficult  to
                      determine whether poor  performance was due to  the
                      change  in sludge characteristics or  the  additional
                      solids loading from increased sludge production.

                      In  pilot-studies  on alum-primary sludges,  it was
                      found that underflow  solids  concentration  generally
                      decreased as the amount of chemical  solids in  the
                      feed sludge  increased (10).  Note that  in Table  5-4
                      recommended  mass  loadings to gravity thickeners
                      decrease substantially for primary sludge with alum
                      vs. primary sludge alone.

                      Several  investigators have noted an  improvement in
                      the  settlability (decrease in SVI) of mixed liquor solids
                      where aluminum  salts are dosed directly into  the
                      aeration  basin (14-16). Little  data are  available
                      regarding  thickening characteristics  of  the resulting
                      sludges, however. In general,  where alum is added to
                      the  aeration basin of  the activated  sludge process,
                      recommended  loadings  to  gravity  thickeners  are
                      similar to those for which no chemicals are added.

                      No  data  were  found  for   thickening of  tertiary
                      wastewater sludges resulting from alum addition. In
                      many cases, alum is added to the secondary  effluent
                      immediately  prior to  tertiary  filtration  without
                      intermediate clarification.  Tertiary alum sludges would
                      be expected to behave similarly to alum  sludges from
                      potable water treatment.

                      Addition of polymer to the influent sludge of a gravity
                      thickener  has  been found to improve solids  capture
                      and increase underflow solids concentrations (1, 10).

                      5.3.3.2 Flotation  Thickening
                      Flotation thickening is often employed for thickening
                      of  waste  activated sludge from extended  aeration
                                                   92

-------
 plants without primary  clarification, or for secondary
 sludges where primary and secondary sludges are
 thickened separately.  In  the  majority of  cases,
 flotation thickening is not applied to primary sludges
 or  combined  primary-secondary  sludges.  Where
 chemicals are  added  to the  primary clarifier for
 phosphorus removal, organic loadings to downstream
 biological processes are  reduced substantially, thus
 reducing  the quantity of biological sludge generated.
 In such cases, separate thickening  of primary  and
 secondary sludges  is  not justified and the sludges
 would most likely  be combined prior to thickening by
 gravity.

 In the  EPA-sponsored survey  of plants  removing
 phosphorus,  it was found that  6  percent  of  the
 facilities employed flotation thickening (1).  In all but
 one of these plants, flotation thickening was used on
 iron or aluminum  waste activated sludge alone.  Half
 of these facilities aerobically  digested the  sludge
 before thickening. Of the nine plants surveyed,  four
 reported  significant changes  in flotation  thickener
 performance when processing chemical sludges;  four
 reported  no  change at all. The ninth  plant did not
 comment on the impacts of chemical sludge handling.
 Of the four plants reporting significant impacts, three
 reported negative impacts, which included:

 1. The need to reduce hydraulic loading  rate,

 2. The  need  to  use  both anionic  and  cationic
   polymers, and

 3. A  decrease  in  float  (thickened) solids
   concentration.

 The plant reporting a  positive  impact  indicated an
 increase  in float  solids concentration.  Some plants
 noted improved performance with polymer addition.

 Of the nine plants that  used flotation thickening, four
 added alum to the aeration  basins, and two of these
 plants  aerobically  digested  the  sludge  prior  to
 thickening. Feed solids concentrations  were 0.5-1.5
 percent,  while float solids  were  typically  3.5-5
 percent (1).

 In batch  laboratory  flotation tests  on  aerobically
 digested  waste activated sludge from a  contact-
 stabilization plant,  no difference was  found between
 the thickening  properties  of the  control digester and
 alum  digester sludge. The sludge was  concentrated
 from 0.75 percent TSS to 3.5 percent TSS without
 polymer addition at an air:  solids ratio of 0.03 (17).

 Mass  loadings  of waste activated  sludge   (no
chemicals) to dissolved air flotation thickeners  vary
widely in  practice, ranging from 2.8 to 34.0 kg/m2/hr
 (0.6-6.9  Ib/ft2/hr)  (4).  Typical  design  loadings  for
flotation  thickeners  receiving  non-chemical  waste
activated sludge  are  2.4-3.9  kg/m2/hr  (0.5-0.8
 Ib/ft2/hr) without  polymer and 4.9-7.3 kg/m2/hr (1.0-
 1.5  Ib/ft2/hr)  with polymer  (8)  [In  Chapter  4 of
 Reference 8,  Sludge  Thickening,  WPCF MOP No.
 FD-1,  all solids loadings shown in  metric  units are
 calculated incorrectly;  use  only values  shown in
 English units; kg/m2/hr = 4.9 x Ib/ft2/hr].

 For  dissolved air flotation  thickening  of waste
 activated sludge  with  alum, solids  loading  rates of
 10-24  kg/m2/hr  (2-5  Ib/ft2/hr)  with  polymer  have
 been recommended (11).

 Pilot-studies  have been  conducted on  flotation
 thickening of  chemical primary  sludges  alone  (10).
 Unfortunately,  flotation thickening is  seldom used for
 primary sludge. Solids loadings for alum sludges were
 6.8-24.9  kg/m2/hr (1.4-5.1  Ib/ft2/hr). Feed  solids
 (TSS)  were 0.8-2.7 percent,  and float solids  (TSS)
 were typically  2.5-5.0 percent. Polymer addition  was
 necessary to achieve good performance (10).

 5.3.4 Stabilization

 5.3.4.1 Aerobic Digestion
 In  the  EPA  survey  of  174  plants  removing
 phosphorus, 41 plants (24 percent) employed aerobic
 sludge  digestion (1).  Only  four  plants  reported
 problems with  stabilization  of chemical sludge; the
 majority of these  problems were directly attributed to
 increased sludge  volumes  from  chemical  addition. In
 some  cases,  generation of  a  more  concentrated
 sludge  as a  result  of alum  addition necessitated
 increasing the air supply to maintain adequate mixing
 of the digester contents.

 No deterioration of supernatant  quality was reported
 as a result of  increased sludge  volumes or changed
 sludge characteristics upon chemical addition (1).

 Laboratory studies on  waste activated sludge  with
 alum showed  little  impact  of the presence of
 aluminum  precipitates on the  aerobic  digestion
 process (18,19).

 In a full-scale study of alum  addition at  a  1.7 mgd
 contact-stabilization plant,  TSS  reduction in  that
 alum sludge during  aerobic digestion  was only 12
 percent vs.  31 percent  in the  control sludge.  This
 does not provide an adequate  measure of  the degree
 of organics oxidation which occurred, however, since
 the alum sludge would be expected to have a higher
 percentage  of  non-volatile solids. Data on volatile
 solids  reduction  were  not  provided.  The  digested
 alum sludge thickened  significantly  better  than  the
 control when subjected to laboratory tests (17).

There has been some concern regarding the possible
 release  of phosphorus  from the solid to the  liquid
phase during anoxic storage of aerobically disgested
phosphorus-laden   sludges. Laboratory studies were
conducted on  untreated primary sludge  and mixed
                                                  93

-------
primary-chemical sludges to address this issue (20).
It was found that during storage of primary  sludge at
different degrees  of  stability (digestion times),
phosphorus was always released from the solid  phase
to the  liquid  phase. Orthophosphorus  concentration
increased from an initial 5-10 mg/l P to 25-50 mg/l
P after  10-12  days of anoxic storage.  However, for
mixed primary  and alum secondary  sludge, no release
of orthophosphate  took  place during anoxic storage,
regardless  of  the  degree  of stability  and  digester
temperature (20).

5.3.4.2 Anaerobic  Digestion
Review  of the literature on anaerobic digestion of
alum sludges  indicates  mixed  results  regarding the
impact of aluminum addition on the digestion process.
In one  laboratory  study,  it  was  found  that  alum-
precipitated phosphorus  concentrated in the sludge of
the digester and was not released during  anaerobic
digestion.  Phosphorus  concentrations in  the
supernatant from the digester receiving alum  sludge
were less than in the control. No toxic  effects  of the
alum sludge were noted, as evidenced by volatile acid
and  gas production characteristics  (21). Similar
results were found  in another laboratory study (22).

However, in a closely controlled laboratory study, it
was found  that  chemical coagulation  of organic
materials with  alum caused a significant  decrease  in
the anaerobic  digestibility of the resulting sludge as
measured by  gas  production  per  mass of organic
solids in the feed.  This was attributed to "association
of substrate with coagulant  floe, rendering a portion  of
the  organics  less  accessible  and/or reactive to
microorganisms or their extracellular enzymes"  (23).

Other  laboratory-scale  studies  showed   digester
performance,   as  measured  by   gas production,
methane  production, volatile  solids reduction, and
COD reduction,  decreased  with  increasing alum
dosages. At an alum dosage  of 200  mg/l, digester
performance was  92 percent  of  the  control  value,
decreasing to  82 percent at an alum dosage  of 400
mg/l.  Reduced alkalinity in  the digesters   receiving
alum sludge was noted  (24). At the plant from which
the sludges were derived  for the above  laboratory
tests, gas production decreased to about 50 percent
of normal levels upon addition of 250 mg/l of alum to
the raw wastewater (24).

In the EPA survey of plants removing phosphorus, 56
percent  of plants  employed anaerobic digestion. Of
these, 22 percent reported  that chemical addition was
having a significant impact  on their digestion process.
Negative impacts reported included (1):

1. Increased energy requirements  for sludge  mixing,
   pumping, and heating,

2. Difficultly in achieving  adequate digester  mixing
   and heating,
3. Increased labor requirements for sludge pumping,

4. Poor  solids-liquid separation, and

5. Reduction in digester efficiency.

At  Richardson,  Texas,  solids  stratification  and
digester upset occurred when alum was added to the
raw wastewater. When the point of alum addition was
moved  to  the  secondary  process, no digestion
problems were observed.  At Ashland,  Wisconsin,
alum  was added  to the secondary  treatment  stage
(step  aeration activated  sludge), and  sludge  was
stabilized  with  two   stage   digestion.  After
commencement  of alum  addition,  solids-liquid
separation no longer occurred. Polymer  addition did
not solve the problem.  Similar  problems in  solids-
liquid  separation occurred in the  secondary digesters
at Three Rivers, Michigan and Gladstone, Michigan.
Several plants reported significant increases in sludge
volume  which reduced detention  times and exceeded
heat exchanger capacity (1).

Special  considerations should be  given to the design
of anaerobic digesters  receiving chemical  sludges.
The  most  important is  the  capability to  handle
increased sludge volumes  resulting from  chemical
addition. Procedures for estimating sludge mass have
been  provided  in  this chapter.  Sludge   volume
estimates require knowledge of sludge concentrations
resulting from clarification and thickening, which can
be  best determined from pilot or full-scale  trials.  In
existing plants, expansion of thickener capacity and/or
addition  of  polymer to  thickeners  can  reduce the
volume  of sludge fed to the digesters. In addition  to
sludge  volume increases,  consideration should be
given to potential  performance  inhibition from alum
addition, which may justify longer detention times.

Mixing  is also  very important in order to  achieve
optimal  volatile solids destruction  and gas production.
Mixing maintains contact between the active biomass
and the substrate;  creates  physical, chemical, and
biological  uniformity  throughout the digester;
disperses metabolic end products and toxic materials;
and prevents formation of scum  layer and deposition
of suspended matter (4). Even in digesters  receiving
conventional non-chemical  sludges, mixing  is often
inadequate (1). Unfortunately, little design guidance is
available to  define  "adequate"   mixing.  In  general,
strong mixing can be achieved if the  power dissipated
in the  tank  is 5-8  W/m3  (0.2-0.3  hp/1,000 ft3)  of
digester  volume.   Velocity  gradients of  50-85
m/sec/m have been recommended (4). Use  of values
in the  high  end  of these  ranges  is  prudent when
digesting chemical sludges.

Poor  liquid-solids separation in  secondary  digesters
may  occur when  handling alum  sludges. This results
in a high BOD and  SS load in the return supernatant
and  potentially a  thin  sludge  for dewatering  or
                                                  94

-------
disposal. Polymer addition to  the  feed  sludge  or  in
conjunction  with  the primary  coagulant may  be  of
some  value. Poor liquid-solids  separation  may  be
the result of digester "crowding."  Thickening of raw
sludges can reduce the volume for digestion.  More
rapid removal of sludge from the  digester can also
reduce crowding.  However,  this requires  sufficient
dewatering and disposal capability, and  consideration
must be given  to  reduced detention time  and the
potential impacts on sludge stability. In  some cases,
changing the primary coagulant or modifying the point
of  chemical  addition  can  improve  liquid-solids
separation (1).

5.3.5 Conditioning

5.3.5.1 Chemical Conditioning
Chemical  conditioning is frequently used to improve
the dewaterability of organic sludges. Addition of alum
to primary or secondary processes will  likely change
the dewatering characteristics of the sludges and the
resulting conditioning requirements.  Unfortunately, it
is virtually  impossible  to provide  specific design
criteria for chemical conditioning of alum sludges due
to the  numerous  factors which affect  conditioning
requirements  and dewatering   characteristics.
Polymers have become  increasingly  popular  as
conditioning agents  for dewatering  combinations  of
chemical and organic sludges, although ferric chloride
and  ferric chloride  plus lime are also used for this
purpose.

The only generalization  that can be made  regarding
conditioning requirements  of chemical-organic
sludges is that conditioner dosages can  be expected
to be higher  than  for conventional non-chemical
sludges. Farrell  predicted that costs of conditioning
may be as much as 40 percent higher when alum  is
used as a coagulant compared to the baseline cost  of
conditioning anaerobically  digested primary  plus
waste activated  sludge  without chemical addition  to
the  wastewater  (25). In  some  cases,  conditioning
costs per unit weight of dry solids  have more than
tripled (2). In general, sludges should be conditioned
and  dewatered  when "fresh," as  storage has  been
shown to  greatly increase conditioning  requirements
and adversely affect dewatering characteristics (26).

For  conventional  non-chemical  sludges, typical
conditioner dosages of  ferric  chloride and lime are
20-63 kg/Mg  (40-125  Ib/ton)  and 75-277 kg/Mg
(150-550  Ib/ton) of dry  solids,  respectively.  For
polymer, typical dosages are 0.3-5 kg/Mg (0.5-10
Ib/ton) of dry solids (4).  Novak and O'Brien studied
polymer conditioning of  chemical  sludges  in  the
laboratory. It was found that for the near neutral pH
range,  anionic  polymers  with  a   range  of 15-30
percent hydrolysis  require the  least dose  and
significantly  reduce  specific resistance. For neutral
and slightly acidic sludges, cationic polymers function
effectively, although dosage requirements are greater
than  for anionic  and  nonionic  polymers.  For
conditioning of  sludges prior to vacuum or pressure
filtration, results indicated that  the benefit of polymer
conditioning is  improvement in the  filtering rate and
not by increasing the cake solids concentration (27).

Proper dosages of chemical conditioners can only be
determined through trial and error procedures  using
the actual sludge to be dewatered. Where possible,
results  of laboratory  tests  should  be confirmed at
pilot- or  full-scale.

5.3.5.2 Thermal Conditioning
Thermal conditioning is a process by which sludge is
subjected  to  temperatures  of  177-240°C  (350-
465°F)  in a reaction vessel at pressures of 1,720-
2,760 kn/m2 (250-400 psig)  for  a  period  of  15-40
minutes.  One  variation  of the  process  involves
injection of  a  small  amount of air  into the system.
Thermal conditioning changes the cellular structure of
the sludge,  allowing  the resulting  material to  be
readily thickened and dewatered.

There is evidence  in the  literature  to indicate that
sludges  resulting from  chemical  precipitation of
phosphorus  have an adverse impact on  thermal
sludge  conditioning  processes (1,28).  At  Midland,
Michigan, ferric chloride addition to primary treatment
was  initiated  to  reduce effluent  phosphorus
concentrations.  When no ferric chloride was added,
the thermally  conditioned  sludge  thickened to  13
percent  solids.  Upon addition of 19 mg/l FeCl3 to  the
raw wastewater, thickening  to  only  9 percent solids
was  possible.  However,   by  increasing   the
temperature of the  thermal conditioning  unit  from
185°C (365°F) to 202°C (395°F), the sludge could
be thickened to 22.5 percent  solids. Full-scale  trials
with alum addition  were  also conducted. When
operated at  202°C (395°F), the thermal conditioning
unit produced a sludge which could only be thickened
to 16 percent solids. Percent  solids of the  vacuum
filter  cake  was  41 percent for  the thermally
conditioned  alum  sludge  vs.  56  percent  for the
thermally conditioned ferric chloride sludge.

5.3.5.3 Freezing
Subjecting  alum  sludge  to freezing  conditions is
another  conditioning technique that may be applicable
in cold climates. In experiments at Ely, Minnesota, it
was  found that   alum  sludges  with  solids
concentrations  of 0.25-0.32,  after  subjecting  to a
natural  freeze  thaw cycle, dewatered to  16.8-18
percent  solids.  Freezing  rates  of alum  sludges  were
similar  to that of  water  (29). Reed  et  al   have
proposed design  criteria  and  procedures for sludge
dewatering systems utilizing natural freezing in cold
climate (30).

5.3.6 Dewatering
The following sections address dewatering systems
for  sludges resulting from chemical phosphorus
                                                 95

-------
removal  processes.  Much of  the research on
dewatering of chemical sludges was conducted during
the  1970s.  Since  that  time, there  have  been
significant  developments  in  sludge  dewatering
equipment, including  displacement  of traditional
vacuum   filters  with  belt filter  presses,  and
improvements in  centrifuge  design.  Unfortunately,
little data  have  been  published recently  on  the
performance of  these devices  when  processing
chemical-laden  sludges.  For  this  reason,   it is
recommended  that  the engineer  approach  such
designs  cautiously.  Manufacturers  should be
contacted for additional data and a list of facilities that
are dewatering chemical sludges prior to process or
equipment  selection.

5.3.6.1 Drying Beds
Of the 174 plants practicing phosphorus  removal and
which respond to  the EPA survey, 58 (33 percent) of
the plants  dewatered their  sludges  on  sand drying
beds.  Twenty of  these  plants used  alum  for
phosphorus precipitation,  three of which  reported
problems  with dewatering.  Problems  ranged  from
longer drying times  to  complete  failure to dewater,
requiring  use of alternative dewatering methods (1).

Novak and  Montgomery  investigated sand   bed
dewatering on a  variety of  chemical sludges  from
water treatment plants (31).

Little  design information is available for  sand  bed
dewatering of sludges  from plants  using alum for
phosphorus removal.  For  that  matter,  there is  little
published design  criteria for any sludge other  than
anaerobically digested.  For anaerobically digested,
unconditioned sludge,  recommended solids loadings
are 134  kg/m2/yr  (27.3 Ib/ft2/yr)  for "primary",  110
kg/m2/yr  (22.4 Ib/ft2/yr) for "primary plus chemicals"
and "primary plus  low-rate trickling filter",  and  73
kg/m2/yr  (14.9  Ib/ft2/yr)  for  "primary  plus waste
activated sludge" (4,32). Other design criteria are in
terms  of bed surface area per capita, which  is of
limited value and has no rational design basis.

Addition  of polymer to sludge prior to  application to
drying beds has been shown to improve dewatering
and shorten  drying  time  (1).  Conclusions  from the
EPA survey suggested the following  modifications to
improve drying bed performance (1):

1. Improving  performance  of upstream facilities  (e.g.
   thickeners, digesters).

2. Adding  chemicals to  improve   dewatering
   characteristics.

3. Optimizing sludge loading rates and  bed turnover
   rates.

4. Changing the drying bed filter material.
5. Covering  open beds where  climatic conditions
  adversely affect performance.

5.3.6.2 Vacuum Filtration
Many existing wastewater  treatment plants employ
vacuum filtration for  sludge dewatering. In  the EPA
survey, 21 percent of the plants removing phosphorus
used vacuum filtration.  Most plants  reported
significant increases in sludge generation rates upon
alum addition for  phosphorus removal,  which
necessitated longer operating times for the  vacuum
filters (1).

Reports in the literature vary widely regarding  the
impact of alum addition to the wastewater on vacuum
filter dewatering.  Laboratory  Buchner  funnel tests
showed that alum addition  to  secondary treatment
produced a waste activated sludge that  was easier to
dewater,  measured as specific  resistance.  Improved
dewaterability  was  also found  for  combined  raw
primary and  alum waste  activated  sludge.  These
sludges also required  less ferric chloride to  condition
(22). In another laboratory  study, specific resistance
and  filter  leaf tests  were  conducted on aerobically
digested  waste activated  sludge with  and without
alum addition prior to  secondary clarification. Results
showed that the alum digested sludge filtered slightly
better  than the  control  sludge.  Filter  leaf  tests
indicated  that  the conditioned alum waste  activated
sludge could be dewatered from 1.6 percent TSS  to a
cake concentration of 16 percent TSS at a filtration
rate of 15 kg/m2/hr (3.0 Ib/ft2/hr) (17).

In  laboratory  studies investigating dewatering of
primary sludges,  alum-primary  sludge derived  by
addition of 200 mg/l alum to raw wastewater exhibited
lower resistivity and capillary suction time (improved
dewatering)  compared to the control;  however, filter
leaf  cake solids were 24.0  percent for the  alum-
primary sludge vs.  32.5  percent  for  the  control.
Required filter area for the  alum sludge was  projected
to  be  2.73  times  that  required for primary sludge
without chemicals (33). Required  filter area  was
calculated based on estimated sludge production  rate
as well as dewatering characteristics (Buchner  funnel
data) (32).

Pilot studies  were  conducted  by  Envirotech
Corporation on thickening and dewatering of chemical
primary  sludges.  Data from vacuum filtration of
alum-primary and primary  sludge indicated that alum
addition to  the raw  wastewater adversely  affected
vacuum filtration of the resulting sludge. The required
lime conditioning dose increased and the filtration  rate
decreased as the alum dosage increased. Cake solids
were approximately the same for the alum  dosages
investigated, although were lower than primary sludge
with no chemicals. Vacuum filtration performance for
the alum-primary  sludge is  summarized in Table 5-
5 (10).
                                                  96

-------
Table 5-5.   Summary  of Vacuum Filter  Performance for
           Alum-Primary Sludge.

                           Percent P Removal with Alum
Criterion
Lime conditioning dose, percent
Filter yield, kg/m2/hri
Cake solids content, percent2
Solids capture, percent
80
25
13.5
25.5
97-99
90
25
8.6
25.6
97-99
 1 Excluding chemicals.
 2 Including chemicals.
Table 5-6.   Design  Vacuum  Filtration  Rates  for
           Conventional Sludges (35).
Type of Sludge

Raw Primary
Raw (primary + WAS)
Raw (primary + TF)
WAS
Anaerobically dig. (primary + WAS)
Anaerobically dig. (primary + TF)
Filtration
Rate
kg/m2/hr
24-48
10-24
15-29
5-10
15-24
20-29
Cake
Solids
percent
25-30
16-24
20-26
12-18
20-24
20-28
At  the  91,000-m3/d  (24-mgd)  West  Windsor
primary plant in Windsor, Ontario, effluent phosphorus
levels of 1  mg/l were achieved with 90 mg/l alum and
0.4 mg/l  polymer.  Sludge  production  (dry  solids)
increased from 115 to 259 kg/1,000 m.3 (960 to 2,160
lb/106  gal), while the  solids content of the primary
sludge  dropped from  11.5  to 7.6 percent. Vacuum
filter yield  dropped  from 55 to 28 kg/m2/hr (11.3 to
5.8 Ib/ft2/hr), and cake solids were reduced from 31.1
to  19.2 percent.  Sludge  conditioning  with  ferric
chloride and lime became  more  difficult, increasing
the costs for conditioning chemicals threefold (34).

At  Windsor's  15,000-m3/d (4.0-mgd) Little  River
conventional activated sludge plant, 150  mg/l  alum
was added to  the  raw wastewater. Primary sludge,
containing  a small amount of waste activated sludge,
showed a  reduction in solids  concentration from 6.2
to 5.7 percent,  while sludge  production rose from 189
to 293 kg/1,000 m.3 (1,580 to  2,440 lb/106 gal).  Filter
yield dropped  from 25  to  22 kg/m.2/hr  (5.2  to 4.6
Ib/ft2/hr). Filter cake solids  were  15.9  percent when
dewatering alum sludge (34).

At  Lakewood,  Ohio prior  to   alum  addition to
secondary  treatment,   average  total  solids in
anaerobically digested  sludge (vacuum  filter feed)
was 4.45 percent. Sludge dewatered to 23.8 percent
solids.  After alum  addition,  digested  sludge  feed
solids concentration increased to 6.5 percent,  but the
dewatered cake solids dropped to 21.4 percent.

Although the dry mass of sludge generated increased
from 590 Mg/yr (650 tons/yr)  in 1974 to 1,650 Mg/yr
(1,820  tons/yr) in 1976, vacuum  filter  operation and
maintenance costs  per unit mass  of dry solids
increased only  14 percent (4).

Design filtration  rates and  cake  solids  for various
types of conventional sludges are shown in Table 5-
6  (35). Relative  vacuum filtration  characteristics for
various components of wastewater sludges are shown
in  Table  5-7.  Composite characteristics  are  a
function  of the proportionate  amount  of  each
component in the total mixture. This is based on the
assumption that the accumulative effects on vacuum
Table 5-7.   Component Vacuum Filtration Characteristics
           (31).
 Sludge Component
Filtration
 Rate*
 Cake
 Solids
 Primary
 WAS
 TF
 AL(OH)3»AIPO4
 Fe(OH)3»FeP04
kg/m2/hr

29-48

 1-2

 7-10

 5-7

 7-10
percent

28-30
12-18
12-15
14-16
12-15
 " Values shown are indicative only of the relative effects of various
   components  on  the dewatering characteristics  of a sludge
   mixture.
filtration are a  function of the sum of the individual
effects (35).

Table 5-8  lists  estimated  design  factors  for
conventional  and  alum  sludges,  using  vacuum
filtration of anaerobically digested primary  plus waste
activated sludge as a baseline (2).  The factors in  the
table can then  be used  to predict  other yields. If no
actual data are available  on which to predict yields for
other sludges,  a baseline value of  20 kg/m2/hr  (4
Ib/ft2/hr) can be used (2).

5.3.6.3 Centrifugation
Several  studies  have  investigated  centrifugal
dewatering of  sludges  from  plants using  aluminum
salts for  phosphorus control  (10,17,32,36-38).  In
general, such sludges are amenable to centrifugation.
However, decreased cake solids and  deterioration in
centrate quality  may  be expected.  Polymer  is
effective in increasing solids  capture, although often
with a corresponding decrease in cake solids.

Studies by Envirotech using  a pilot-scale  solid bowl
centrifuge showed that as the fraction of alum solids
in the alum-primary  sludge  increased,  both  cake
solids and  maximum  percent   solids   recovery
decreased for  any given  hydraulic loading rate.  As
percent  solids  capture  improved  with  polymer
                                                   97

-------
Table 5-8.   Design factors  for  Vacuum  Filtration of
           Conventional Plus Aluminum Sludges (2).
Sludge Type

Al to primary
Digested primary + WAS
Raw primary + WAS
Raw primary + TF
Digested primary + TF
Digested primary
Raw primary
Al to aeration
Raw primary + WAS
Digested primary + WAS
Relative
Yield
kg/m2/hr

1.2
0.85
1.35
1.0
1.05
1.5

1.2
0.85
Rel. Cost of
Conditonmg*
percent

1.3
1.4
1.2
1.3
1.0
0.9

1.3
1.4
 " Yield and cost factors related to yield and costs obtained with
   digested primary +  WAS  when no chemicals are  added to
   wastewater.
addition,  cake solids decreased. For solids  captures
greater than 80 percent, cake solids were typically 15
to 18 percent (10).

Baillod   et  a/,  investigated  pilot-scale  basket
centrifugation of aerobically digested  sludge from a
contact  stabilization  plant with  alum addition  to the
raw  wastewater. Using the manufacturer's  scale-up
procedure, results  indicated that  a full size 1.2-m
(4-ft) diameter  basket centrifuge could dewater the
digested  alum-biological  sludge  at  1.6  percent TSS
to a 16  percent IS cake at  a rate  of 159 kg dry
solids/hr  (350 Ib/hr) with  no chemical addition. Solids
capture was 96 percent (17).

Canadian researchers  investigated use  of solid bowl
and  basket centrifuges  for dewatering of  several
different  sludges  from pilot- and full-scale  facilities.
Increasing  polymer  dosages  at  the  solid  bowl
centrifuge resulted in increased solids recovery for all
sludges tested with the basket centrifuge. Recoveries
in excess  of  90  percent were  possible  without
polymer  addition  for  all  waste activated  sludges
investigated. However, for the anaerobically digested
alum sludge,  polymer  addition was  necessary  to
obtain high  solids recoveries.  For  alum  waste
activated sludges,  an optimum polymer dosage of 1
kg/Mg  (2 Ib/ton)  was suggested, resulting in cake
solids  concentrations of  10-11  percent. Waste
activated sludge with alum dewatered slightly better
than the  control sludge. It was also found that particle
size impacted  centrifuge  performance,  with
decreasing particle size resulting in decreased solids
recovery and cake solids (33,36,37).

Mininni  et  a/,  investigated dewatering of aerobically
digested waste activated sludge from  a plant with no
primary  clarification. When alum was added to  the
raw  wastewater, centrifuge cake solids dropped from
15.8  to  11.3 percent.  Polymer  was  used as a
conditioning agent in both cases, at dosages of 0.3-
0.5 percent dry weight. Conditioner dosage increased
during alum addition. The  most significant machine
variables affecting cake  solids content were beach
residence time and  liquid  ring  height  (38). It  was
estimated  that   costs  for  sludge  conditioning,
dewatering,  and  disposal (including  amortization  of
capital) would increase by 63-74 percent, depending
on  plant size, when alum  was added  to  the  raw
wastewater for phosphorus removal (39).

There are many variables which affect performance of
centrifuges.  Some of  the  more important process
variables include  source and type of  sludge,  feed
solids content, percentage of chemical  solids,  feed
rate, and conditioner dosage. Machine variables for a
solid  bowl  centrifuge include  bowl design,  bowl
speed, pool volume, conveyor  speed, and conveyor
pitch (35).

Because of the  variability  in sludge  characteristics,
pilot  testing  is  recommended  where  feasible.
Procedures  are available  from  the  various
manufacturers for scale-up  of  pilot-test  results.

5.3.6.4 Pressure  Filtration
Less than 5 percent of the phosphorus removal plants
contacted in the  EPA  survey  practiced pressure
filtration  for sludge  dewatering.  None  of these
facilities  used alum  as  the  primary  coagulant for
phosphorus  removal  (1).  Plate  and  frame  filter
presses  are often  used when it is  desirable  to
produce  a  cake  with  a  high solids  content, as in
preparing sludge for incineration.

Information  on pressure filtration  of sludges from
plants using  alum for  phosphorus removal  is scant.
Envirotech  evaluated pressure  filtration  during  the
investigation  of chemical-primary sludge dewatering.
Results  for alum-primary and  primary  sludge  are
summarized below (10):

1. Filtration  rates for alum-primary  sludge  were
   approximately  double   those for  primary sludge.
   Filtration  rates for alum-primary sludges  typically
   are  1.0-4.5  kg/m2/hr  (0.2-0.9   Ib/ft2/hr),
   depending on conditioner (lime) dosage and cake
   thickness.

2. Cake  solids were  higher for primary sludge, 20-40
   percent  vs.   15-30  percent  for alum-primary
   sludge.

3. Conditioning requirements using lime were 24-25
   percent  by weight  for alum-primary  sludge vs.
   37-65 percent  for primary  sludges

4. Decreasing the  cake  thickness   significantly
   increased  filtration rate  and  cake solids for  the
   primary sludge. This effect was less  pronounced
                                                  98

-------
  as  the percentage  of  alum solids in  the sludge
  increased.

Minnini  et at.  studied  pressure filtration of  waste
activated sludge  (no  primary clarification)  using
aluminum chlorohydrate as  the  conditioning agent.
When alum  was used for phosphorus removal, cake
solids concentrations averaged 24.5 percent. With no
chemical  addition  to the  wastewater, cake  solids
concentrations  averaged  32.1 percent. Conditioner
dosages ranged from 1.1 to 1.5 percent by weight as
A^Os- Operating pressure in the filter press averaged
6 kg/cm2 (85 psi),  with cycle times of approximately 3
hours (38,39).

Additional information  on experiences  with pressure
filtration of  chemical  sludges  may  be found in
Sections 5.4 and 5.5.

5.3.6.5 Belt Press Filtration
Belt filter presses have  become  quite  popular in
recent years for dewatering  sewage  sludges, since
they are capable of  producing dryer cakes  than
vacuum filters or centrifuges, and are less costly than
plate and frame filter presses. Unfortunately, there is
little information  on their  use at  plants removing
phosphorus  by  chemical addition.

The EPA survey makes reference to the use of a belt
filter press  for dewatering  alum  waste  activated
sludge at Westfield, New  York (1).  Since  the  plant
was designed for  phosphorus removal  using alum, it
is  not   possible  to  compare belt  filter  press
performance  without  alum  addition. The waste
activated sludge is reported to be difficult to dewater,
as there is  no  primary  treatment. Cake produced by
the belt filter  press has  an average total  solids
content  of  11.5 percent. Polymer conditioning  with
polymer  was  found  to be   more   successful  than
conditioning with ferric chloride and  lime (1).

Data  on performance  of  belt  filter presses  for
dewatering of conventional sludges  may be  found in
the  EPA  Process  Design  Manual  on  Sludge
Treatment and  Disposal (4).

5.3.7 Incineration
Thirteen  percent of phosphorus removal plants which
responded  to  the  EPA survey  incinerated  their
chemical  sludges.  Of  these  22 plants,  6 reported
significant impacts on  incineration  as a  result of
chemical addition  for phosphorus removal. All  plants
incinerated a combination of  primary and  secondary
sludges.  Three of the plants  that reported  problems
used alum for  phosphorus precipitation. These were
Warren, Michigan;  Coloma,   Michigan;  and
Richardson,  Texas (1).

Critical  variables for incineration of sewage sludge
include:
1. Moisture content of the sludge,

2. Calorific value of the sludge, and

3. Relative proportion of volatile and inert material.

It is evident that the addition of  alum for phosphorus
removal can  significantly impact these  variables due
to deterioration in  sludge dewaterability  (higher cake
moisture content),  and a higher concentration of inert
chemical solids, which reduces the calorific value on
a unit mass  basis, thus  increasing auxiliary  fuel
requirements. Table 5-9 lists the  potential  problems
associated with chemical  sludge  incineration,  and
recommended solutions (40).
Table 5-9.   Potential  Problems with  Chemical Sludge
           Incineration (40).

 Problem                          Solution
 Greater sludge volume

 Lower caloric value

 Increased cake moisture
 content
 Formation of clinkers
 More inert solids
Increase incinerator capacity or run
time.
Increase supplementary fuel
requirements.
Improve dewatering by:
1) modifying dewatering operation
  or sludge conditioning;
2) changing primary precipitating
  chemical or point of addition;
3) changing dewatering equipment
or
Increase supplemental fuel
requirements.
Decrease incineration temperature
to below flash point; decrease
residence time.
Increase ash disposal capacity.
Specific  information regarding  the impacts  of alum
addition  on  incineration  processes  is  not  available,
although additional information on  the  impacts  of
other chemicals such as ferric chloride  and lime may
be found in Sections 5.4 and 5.5.

5.3.8 Disposal
Implementation of  phosphorus removal  by addition of
alum  to the wastewater  has  several implications
regarding sludge   disposal.  The  most  significant
impact is on the volumes  of sludge for disposal.  As
discussed earlier,   addition of  alum  for  phosphorus
removal will  likely cause a significant increase in both
the mass and volume of sludge to be transported and
disposed. This will  result in increased disposal costs.

Another  concern is the  increased metal content  of
sludges  due to addition  of  precipitant.  Addition  of
alum  will increase  the metal content of  the  sludge.
Considerable  research  has  been conducted   in
Canada regarding the potential impacts  on crop yield,
                                                   99

-------
organic matter  degradation,  nitrogen availability,  and
other soil parameters (41-44).

From  review  of the available literature  on  land
application of alum sludges, it appears that addition of
alum  for  phosphorus removal  does  not adversely
affect  the agricultural value of the resulting sludge
compared to non-chemical  sludges. Although some
reduction of crop yield was noted with alum sludge in
the Canadian studies, this was believed to be due to
the high content of petroleum  hydrocarbons, which
was 14-30  times  higher  than the  other  sludges
investigated (44). Kirkham and Dotson found that the
presence  of  aluminum  and  iron  phosphate
precipitates did not affect the growth of barley in loam
soil irrigated with wet primary sludges (45).

Increased metal content in alum sludges  may impact
sludge loading rates on agricultural land. Heavy metal
analyses  must  be conducted  on  a  case-by-case
basis for the sludge to be applied.  Application rates,
whether governed  by  nitrogen  or  heavy  metal
loadings,  will  be determined by state and  federal
regulations.

Alum addition is unlikely to  affect the suitability of a
sludge for disposal at  a sanitary  landfill.  However,
many  landfills require that organic  materials  meet a
maximum moisture  content criterion. As alum addition
may  increase  moisture  content  in  cakes resulting
from  dewatering  processes,  this may  limit  the
suitability for landfill disposal.


5.4 Sludge Derived from Addition of  Iron
Salts

5.4.1 Sludge Characteristics
Iron salts may be employed for phosphorus removal
by  addition  to primary,  secondary,  or  tertiary
treatment processes. Of those plants that  used iron
and responded to the EPA survey,  32 percent added
iron to primary treatment, and 57 percent added iron
to secondary treatment.  A small number of plants  (3
percent)  added  iron  to tertiary  processes,  while
several plants used iron in combination with  other
chemicals such as lime. Four  percent of the plants
added  iron  to both primary and secondary treatment
(1). Iron  salts are employed more frequently  on  a
percentage basis  than  aluminum  salts in  primary
treatment.

Knowledge  of  sludge  characteristics,  as defined by
conventional characterization parameters,  is of little
value in predicting the amenability  of iron sludges to
thickening and dewatering operations, since so many
variables interact to affect performance. As discussed
in  Section  5.3.1 design of sludge  handling systems
must be based on  laboratory tests at a minimum, and
 preferably on  pilot- or full-scale tests.
5.4.2 Sludge Generation Rates
As  with  aluminum  addition,  increased  solids
production during iron addition to wastewater results
from (2):

1. Formation and removal of chemical solids such as
  metal phosphates and metal hydroxides,

2. Improved  removals of  organic  solids  during
  clarification, and

3. Removal of dissolved solids.

Although procedures  are  available to estimate the
quantities  of additional solids resulting from chemical
addition, these estimates may not  be accurate for a
particular  wastewater  and  treatment  plant.  For
upgrading  of existing  plants,  full-scale trials  under
controlled  conditions  will provide  the best data
regarding  sludge production.  For new facilities, pilot-
plant  tests are preferred  for accurate  prediction  of
sludge production.

The procedure for estimating  sludge generation  is
very similar  to that described in  Section  5.3.2 for
alum  sludge, and consists of determining production
of  chemical  solids,  generation  of  additional  solids
removed during clarification, and removal of dissolved
solids.

a. Chemical Sludge
This calculation  assumes  that the iron reacts  with
phosphorus compounds  first, and  that  excess iron
forms iron hydroxide.

Given:

Pjn =  8 mg/l
Pout = 1  mo/1
Fe: P dose = 2.2:1
Atomic weight of Fe  = 56
Atomic weight of P  = 31
Atomic weight of FePCU = 151
Atomic weight of Fe(OH)3 =  107
Fe dose =  2.2 x 8 mg/l x (56/31)
         =  32 mg/l as Fe

Stoichiometry:

Fe + PO4 = FePO4
Fe + 30H = Fe(OH)3

(8  - 1  mg/l P) T  31  = 0.23  mmole added/I FePC>4
                                     produced

32 mg/l Fe * 56 = 0.57 mmole/l Fe added

0.57 - 0.23 = 0.34 mmole/l Fe in  excess to
                                 Fe(OH)3
                                                  100

-------
FePO4 sludge: 0.23 mmole/l x 151 = 34.7 mg/l
                                     FePO4

Fe(OH)3 sludge: 0.34 mmole/l x 107 = 36.4 mg/l
                                      Fe(OH)3

Total chemical sludge:    34.7 mg/l FeP04
                        36.4 mg/l Fe(OH)3
                        71.1 mg/l Fe sludge

Chemical sludge produced  = 71.1 mg sludge/liter of
wastewater treated (592  lb/106 gallons).  Adjust
estimate by factor of 1.35 to account for  additional
chemical solids not predicted by equation (2):

Design estimate of chemical sludge production:

1.35 x 71.1 mg/l = 96.0 mg sludge/liter of
                  wastewater (800 lb/106  gallons)

b. Sludge  from improved removal of suspended
solids (primary clarifier)
Given:

SSjn =  200 mg/l
SS removal efficiency (no chemicals) = 50 percent
SS removal efficiency (with  iron)  = 75 percent
Additional Sludge Generated:

(0.75 - 0.50) x 200 mg/l  =
50 mg sludge/liter of
wastewater treated (417
lb/106 gallons)
c. Sludge from removal of dissolved solids
Additional sludge mass (assuming 30%  removal of
soluble organics using iron salts)

   = STOCjr, (mg/l) x 0.30 x 2.5 x 1.18
   = SCODjp (mg/l) x 0.30 x 1.1 x 1.18
   = SBODjn (mg/l) x 0.30 x 1.6 x 1.18

The latter two equations  are  only applicable to
influents prior to biological oxidation processes.

Given:

STOCjn = 50 mg/l

Additional sludge generated:

50 mg/l x 0.30 x 2.5 x 1.18 = 44.2  mg sludge/liter of
                            wastewater (369  lb/106
                            gallons)

If iron salts are added to primary treatment, improved
BOD  removals  will  result  in reduced  loadings to
secondary biological processes, and thus reduced
secondary  sludge production.  This  must be
accounted for  in calculating estimates  of  total  plant
sludge production.  Where  iron  salts are  added to
secondary processes, additional sludge resulting from
improved removal of  SS in the secondary clarifier will
probably be small for well operated activated sludge
plants. However, for plants  producing  effluents with
SS concentrations  greater  than 25-30 mg/l,  an
improved effluent quality from iron salt addition may
result in significant quantities of additional sludge.

A  design example  is  shown in  Section 5.3.2  for
calculating  sludge production with and without  alum
addition. The same  approach can be  used for iron
salt  addition.  The  major   difference  is  in  the
stoichiometry used to  predict  chemical sludge
production.

5.4.3 Thickening

5.4.3.1 Gravity Thickening
As with alum sludges, reported impacts of primary or
secondary  iron  addition  on  sludge  thickening
characteristics have  been variable.  In the survey of
phosphorus removal  plants  that was conducted  for
EPA,   respondents  indicated both positive  and
negative  impacts  on  thickener  performance.
Unfortunately, it was impossible to determine from the
information provided  in  this  report whether negative
impacts were due directly to  the addition of iron  or to
the additional  sludge  volumes  which  may  have
overloaded  the  thickener.  Because of  the  many
factors  which affect thickening  characteristics  of
sludges, thickening tests should be conducted on the
actual  sludges  if available.  For  retrofit  applications,
full-scale trials  should be conducted to  generated
representative samples of sludge  upon which proper
thickening tests can  be run.  Design criteria can then
be established with confidence.

For design  of gravity thickeners for new facilities, the
designer does not have the benefit of having existing
sludges on  which  to conduct thickening  tests, and
must  rely on published design guidelines. Table 5-
10 provides design  criteria  for thickeners receiving
various types  and combinations  of  iron  and  non-
chemical sludges.

In  addition  to  mass  loading  criteria shown in  Table
5-10,  hydraulic loading  must also be considered in
the design  of gravity  thickeners. For primary sludges,
typical maximum  overflow rates  range  from 1,000-
1,200 l/m2/hr (25-30 gal/ft2/hr). However, for waste
activated sludge or  combinations  of  primary and
waste  activated  sludges,  hydraulic  loadings  rates
should be  considerably  lower,  160-320 l/m2/hr (4-8
gal/ft2/hr) (4).

In  pilot-studies  of  ferric-primary sludges, it  was
found that  underflow solids concentration  decreased
as the amount of chemical solids in the feed sludge
increased (10). This is  shown  graphically in Figure
5-3.  Ferric-primary  sludge   was found  to exhibit
superior  thickening  characteristics to  alum-primary
                                                 101

-------
Table 5-10.   Typical Gravity Thickener Design Criteria.
Sludge Type

Primary
Primary w/Fe*
Primary + WAS
Primary + TF
(Primary w/Fe) +
WAS
(Primary w/Fe) +
TF
Primary + (WAS
w/Fe)
WAS
WAS w/Fe
Tertiary w/Fe
Influent
Solids
Cone.
percent
2-7
1.8-5.2
0.5-1.5
2-6
1.8
0.4-0.6
1.5
0.5-1.5
0.5-1.5
0.5-1.5
Expected
Underflow
Cone.
percent
5-10
2.2-6.4
4-6
5-9
3.6
6.5-8.5
3
2-3
1.5-2.0
3-4
Mass
Loading
kg/m2/hr
3.9-5.9
0.3-1.3
1.0-2.9
2.5-4.2
1.3
2.9-4.2
1.3
0.5-1.5
0.6-0.8
0.4-2.1
Ref.

9
10
8
8
8
8
8
9
11
8
   Data reflects use of anionic polymer to assist in thickening.
Figure 5-3   Range  of thickener operating  periods  for
            ferric-primary sludge (10).

  Max. Thickener
  Underflow Solids, g/l
     90 r-
             10     20    30     40    50
            Chemical Solids in Sludge, weight percent
                                              60
 sludge  (see  Figure 5-4).  Table 5-11   shows  a
 summary  of  the  results at  a  loading  rate  of
 approximately 0.83 kg/m.2/hr (0.17 Ib/ft2/hr).

 Canadian studies on mineral addition to an extended
 aeration  plant found  that  addition of ferric chloride
 deteriorated  the settleability  of  the  mixed  liquor
Figure 5-4   Range of thickener  operating periods  for
           alum-primary sludge (10).

  Max. Thickener
  Underflow Solids, g/l
                                                             90 i-
                                                             80
             10    20     30     40    50

           Chemical Solids in Sludge, weight percent
                                              60
                                                         Table 5-11
            Effect of  Phosphorus Removal on  Gravity
            Thickening Properties of Alum-Primary and
            Ferric-Primary Sludge (10).
Alum-Primary Sludge

T-P
Removal
percent
80
90
95
Chemical
Sludge
Weight
percent
18
23
32

Underflow
TS
percent
4.7
4.1
3.3
Ferric-Primary Sludge
Chemical
Sludge
Weight
percent
22
28
3.8

Underflow
TS
percent
5.5
5.4
5.3
                                                          Basis:  Raw wastewater with 100 mg/l TSS and TP of 5 mg/l.
                                                                 Solids loading rate: 0.83 kg/m2/hr (0.17 Ib/ft2/hr).
 suspended  solids.  Secondary  clarifier  underflow
 sludge was 1.1-1.3  percent solids with iron  addition
 to  the  aerator vs. 1.7-1.8 percent with alum  addition
 and 2.0 percent with no chemical addition (32).

 In  general,  limited data  are  available  on thickening
 characteristics  of combined  primary and secondary
 sludges with iron addition to  the secondary process.
 Lower  thickened sludge  concentrations  may  be
 expected, and solids loading rates are generally lower
 than  for  combined  sludges  without  chemicals.
 Polymer addition to the influent sludge may  improve
 thickener performance.
                                                     102

-------
5.4.3.2 Flotation Thickening
Flotation thickening is most often applied  to  waste
activated sludges.  Seldom is  it used for thickening
primary or combined  primary-secondary  sludges. In
the EPA survey of plants removing  phosphorus,  6
percent of the facilities employed flotation thickening.
Of  the  four  plants which flotation-thickened  iron-
secondary sludge,  three reported no  impact of  iron
addition on thickener  performance. The fourth plant,
which  aerobically digested   the  iron-secondary
sludge prior  to thickening, had always treated  iron
sludge and could not make a comparison with non-
chemical sludge  (1).  One plant reported use of
flotation thickening for a combination  of  iron-primary
and aerobically digested secondary sludges.

Table 5-12  summarizes the results  reported  from
the six  plants responding to  the EPA survey.  For
iron-secondary sludges,  the   maximum  thickened
solids concentration  achieved  was  approximately  5
percent (1).

Table 5-12.  Performance of Flotation  Thickeners for
           Treating Iron Sludges (1)
Type of Sludge

Iron-secondary
Iron-secondary
Iron-secondary
Iron-secondary
(aer. digested)
Iron-primary +
aer. digested
secondary
Feed
Solids
Cone.
percent
0.9
1.0-1.5
1.0
1.5

Thickened
Solids
Cone.
percent
5.1
3.5-4.0
2.5
2.5
5-6
Comments

Polymer added.
Polymer used
when loadings
high.
Polymer did not
improve.
Plant has no
primary
treatment.
Both cationic and
anionic polymer
added.
For flotation  thickening of  non-chemical  activated
sludge,  typical  design  loadings are 2.4-3.S kg/m2/hr
(0.5-0.8 Ib/ft2/hr without  polymer  and  4.9-7.3
kg//m.2/hr  (1.0-1.5  lb/«2/hr)  with  polymer (8).
Hydraulic loading rates are typically 29-117 m3/m2/s
(0.5-2 gpm/ft2)  (8). For iron-activated  sludge,  solids
loadings of  10-24  kg/m2/hr  (2-5 Ib/ft2/hr)  with
polymer   have  been   recommended   (11).
Recommended  hydraulic  loading  rates are  58-88
m3/m2/s (1.0-1.5 gpm/ft2) (11).

5.4.4 Stabilization

5.4.4.1 Aerobic Digestion
Twenty-four  percent of  the  phosphorus-removal
plants contacted in the EPA survey reported use of
aerobic  digestion for chemical sludge stabilization (1).
Few problems were reported, although  several  plants
indicated problems due  to increased volumes  of
sludge that  exceeded  the design  capacity  of the
digesters.

A Canadian  laboratory  study investigated the impact
of chemical addition to  the  aeration basin  on the
aerobic  digestion of the  resulting  waste  activated
sludge.  The  major  conclusion  was  that  the
performance of the aerobic digestion process did not
differ  in any practical degree when iron  or aluminum
precipitates  were  present in the  sludge  (18).  In
addition,  the  release of soluble  organic carbon and
nutrients  into the liquid phase  was not enhanced by
the presence of iron and aluminum precipitates. Batch
digester operation  resulted in  greater destruction  of
volatile solids  and  a lower oxygen  uptake  rate than
semi-continuous  operation.  However,  semi-
continuous operation at a loading rate of 1  kg volatile
solids/m3/d (0.06 Ib/ft3/d)  provided digested sludges
with better supernatant quality as  well as  superior
settling and dewatering  characteristics (18).

Relatively little  information is  available regarding the
impact of iron salt addition  to  wastewater  on the
aerobic  digestion  of  the resulting  sludges.  More
information is  available on alum sludges (1,17-20).
Dick  suggests that   "Chemical  precipitation   of
phosphorus  would  be  expected to affect aerobic
stabilization  processes  (aerobic  digestion  and
composting)  the same  way  it affects anaerobic
processes. That is, changes in the amount of organic
solids removed, their  concentration  in  sludge,  and
their  availability  in   sludge  would  influence
performance (13)."

5.4.4.2. Anaerobic Digestion
Anaerobic digestion is a common sludge stabilization
technique, particularly for plants larger  than 19,000
m3/d  (5 mgd). In the EPA survey of  plants  removing
phosphorus, 5.6  percent of   the  plants  employed
anaerobic digestion. Of these, 22 percent  reported
that chemical addition was having a significant impact
on their digestion process. Negative impacts reported
included (1):

1. Increased energy requirements for sludge mixing,
  pumping, and heating,

2. Difficulty in achieving adequate digester mixing and
  heating,

3. Increased labor requirements for sludge pumping,

4. Poor solids  - liquid separation, and

5. Reduction in digester efficiency.

Process-related problems  reported  with  iron sludges
included  poor  digestion, accompanied by decreased
digester  pH,   reduced  gas  production,  and/or
decreased  gas  production;  digester  upsets
characterized by loss of methane production, low pH,
                                                 103

-------
and  low volatile solids destruction;  and  digester
foaming (1). On the other hand, positive effects have
been  reported,  such as improved digester sludge
settleability and supernatant quality,  and increased
volatile solids destruction  (1).  Such  conflicting
information is similar to that reported for alum sludge
(see Section 5.3.4.2).

Malhotra et al. investigated anaerobic digestion of iron
phosphate sludges on a laboratory scale. Conclusions
from this study are as follows (46).

1. For  conventional  activated sludge plants  using
   ferrous  iron  for  phosphorus   precipitation,
   phosphorus  removal efficiency  will  not  be
   drastically reduced by the return of phosphorus in
   anaerobic digester supernatant.

2. The  pH,  alkalinity of volatile acids  and volatile
   solids destruction  were similar in both the control
   digesters and test  digesters receiving iron sludge.

3. The ferrous iron present  in the feed sludge did  not
   cause digester upset up to a maximum level of  5.5
   percent Fe by weight dry solids.

4. The quantity and quality of the gas  was not altered
   significantly with iron sludge digestion.

5. With primary sludge  containing ferrous-iron
   precipitated phosphorus, significant uptake of total
   soluble phosphorus was observed during digestion.
   With thickened waste  activated sludges containing
   iron-precipitated  phosphorus,  significant
   phosphorus release was observed during digestion.
   This was possibly due to the conversion of  ferric
   phosphate to ferrous phosphate  plus phosphate
   ions during anaerobic digestion.

Other  laboratory  studies  by  Dentel and  Gosset
concluded  that chemical   coagulation  of  organic
materials  with  alum or ferric  chloride  caused a
decrease  in  anaerobic  digestibility of the  resulting
sludge. The effect was  distinct  from any effects of
increased  loading  or differences  in pH or  alkalinity,
and  was not  attributable to  toxicity,  increased fixed
solids  concentration, or phosphate limitation. Results
suggested  that the mechanism  responsible  for
decreased  digestibility was association of  substrate
with coagulant floe,  rendering  a  portion  of  the
organics less  accessible  and/or less  reactive  to
microorganisms (23).

In another  study, Gossett et al. found that, at  ferric
chloride doses of 150 mg/l  to wastewater, anaerobic
digester performance was 90 percent of the control;
at 200 mg/l, it was 78 percent. For chemical sludges,
organic nitrogen decomposition was about 50 percent
less than  for  the  control sludge,  lowering  ammonia
production  which  in  turn reduced alkalinity. During
plant-scale studies,  addition of 150  mg/l   of  ferric
chloride to raw wastewater resulted in a 25 percent
reduction in digester gas production (24).

The  most  important consideration in digestion  of
chemical sludges is the large volumes  of sludges
generated during  chemical  precipitation. Provision of
adequate  digester mixing  is  also  critical. Further
discussion of  these criteria is  found  in Section
5.3.4.2.

5.4.5 Conditioning
Chemical conditioning requirements for iron sludges
can be expected  to be higher than for non-chemical
sludges (1). However, because of the  many variables
which   affect  conditioning  requirements  and
dewatering characteristics, specific design  criteria
cannot  be provided.  Laboratory tests  should be
conducted using samples of the actual sludge to be
dewatered  in  order  to  determine  chemical
requirements. Where possible, such results  should be
confirmed at pilot  or full scale.

Thermal  conditioning  may  also  be affected  by  the
presence  of  iron or  aluminum  precipitates   (1,28).
Because of the similarities in the results of studies on
conditioning of aluminum and iron sludges,  reference
is  made to Section 5.3.5  for further discussion  of
conditioning of chemical sludges.

5.4.6 Dewatering
As described in  Section 5.3.6, significant  advances
have occurred in  dewatering wastewater sludge,
including introduction of the  belt  filter press  and
improvements  in  centrifuge  design.   Much   of  the
performance data and design criteria  decribed below
resulted from work conducted in the 1970s.  Little data
are available  on  dewatering  chemical-laden sludges
using  state-of-the-art (1987)  technology. For  this
reason, the engineer should proceed  cautiously with
regard  to selection  and  sizing of  dewatering
equipment.  Manufacturers  should  be  contacted
regarding  design  criteria  for  dewatering  chemical-
laden sludges.

5.4.6.1 Drying Beds
Sand drying  beds  are  a  popular  and  economical
technique for sludge dewatering at  small wastewater
treatment plants.  A third of the phosphorus removal
plants  responding to the  EPA survey used  drying
beds for dewatering sludge (1). Only  15 percent of
the plants using drying beds reported problems with
dewatering chemical sludges.  Many of the problems
were directly related to handling the  increased volume
of sludge generated by  the addition of chemicals for
phosphorus control. However,  several  plants reported
that the sludge was  more difficult to dewater (1).

Novak  and  Montgomery studied the use of sand
drying  beds for  dewatering  chemical sludges  from
water  treatment  plants  (31).  Conclusions  from  this
work are discussed  in Section 5.3.6.1.
                                                  104

-------
Rational  design  criteria for other  than  anaerobically
digested  sludge are  virtually non  existent  (4).  As
discussed  in  Section  5.3.6.1,  recommended solids
loadings  for anaerobically  digested sludges  are  73-
134  kg/m2/yr  (15-27  Ib/ft2/yr).

Conclusions from  the  EPA survey  suggested  the
following modifications to improve the performance of
sand drying beds (1):

1. Improving performance of upstream facilities (e.g.
   thickeners, digesters).

2. Adding chemicals  such  as  polymer  to improve
   dewatering characteristics.

3. Optimizing sludge loading rates  and  bed turnover
   rates.

4. Changing the  drying bed filter material.

5. Covering open  beds where climatic conditions
   affect  performance.

5.4.6.2 Vacuum Filtration
Twenty-one  percent  of  the  phosphorus removal
plants responding  to the EPA survey  reported use of
vacuum  filters for sludge  dewatering.   Most plants
indicated significant increases  in  sludge  generation
rates which required longer operating times for  the
vacuum filters (1).

As with alum sludges (Section 5.3.6.2), reports in the
literature vary widely regarding  the impact of iron  salt
addition of wastewater on vacuum filter dewatering of
the resulting sludge. In the EPA survey,  some plants
reported significant increases in filter yield and cake
solids content, while  others reported  decreased filter
yields  when dewatering iron sludges (1).  Campbell
and  LeClair reported deteriorated dewaterability when
ferric chloride was used to remove phosphorus,  but
improved dewaterability with alum  (36).  However,
Mininni ef a/, found that both ferrous iron or aluminum
deteriorated dewaterability, with aluminum having  a
more deleterious effect (38).

Envirotech  Corporation conducted  comprehensive
pilot studies  on  dewatering  of  chemical-primary
sludge (10). Vacuum filter  performance, as measured
by conditioner dose and filtration rate, was adversely
affected  by the presence  of iron  chemical solids in
the  feed sludge.  Conditioner  dose  increased  and
filtration  rate  decreased  as the  proportion of  iron
chemical solids in the feed sludge increased. Cake
solids  content  in  dewatered  ferric-primary  sludge
was insensitive to  the proportion of chemical solids in
the feed sludge; however,  vacuum filter dewatering of
ferric-primary  sludge  produced  sludge  cakes of
higher solids than with non-chemical primary sludge.
Performance  of vacuum  filters for dewatering  iron-
primary sludge was slightly better than for  dewatering
alum-primary sludge.  Vacuum filter  performance for
iron-primary sludge is summarized  in  Table  5-13
(10).
Table 5-13.  Summary of Vacuum  Filter Performance for
           Iron-Primary Sludge (10).

                          Percent P Removal with FeCI3
Criterion
Lime conditioning dose, percent
Filter yield, kg/m2/hr1
Cake solids content, percent2
Solids capture, percent
80
30
10.2
34.5
97-99
90
30
8.6
34.5
97-99
  1 Excluding chemicals.
  2 Including chemicals.
           *
At  Sheboygan,  Wisconsin,  the secondary  trickling
filter plant began adding ferric chloride in 1972 to the
effluent of  the trickling filters  in order to accomplish
phosphorus removal.  Degritted  primary  sludge  is
blended  with  secondary  sludge,  gravity  thickened,
and dewatered  by  vacuum  filtration. Comparison  of
vacuum  filter  data for  1970  and 1976  showed  a
decrease in filter yield from 20.3 to 12.8 kg/m2/hr (4.2
to 2.6 Ib/ft2/yr).

Filter feed solids dropped from 8.6  to 7.0 percent, and
cake solids were reduced from 25.5 to 21.5 percent.
Filtrate quality improved  from 658 ppm to  442 ppm
SS. While only polymer was used  for conditioning 80
percent of  the time in 1970, both  polymer and  ferric
chloride were required for conditioning after chemical
phosphorus removal was implemented (1).

The City of Midland,  Michigan, operates a high rate
trickling filter plant with  vacuum  filtration of  primary
and secondary sludge. Prior to installation  of  thermal
conditioning units, raw  sludge was  conditioned  with
polymers. Vacuum filter  yields were 24 kg/m2/hr  (5
Ib/ft2/hr). When  19 mg/l FeCIa was added  to  primary
treatment  for   phosphorus  removal  yields  were
reduced  to 15  kg/m.2/hr  (3 Ib/ft2/hr),  although  cake
solids increased from  25.5 to 39.3  percent TS. During
a period of time when thermal conditioning  was on-
line but when chemical phosphorus  removal was not
being  practiced, filter yields  were  39 kg/m2/hr  (8
Ib/ft2/hr), and cake solids  were  48 percent. Upon
ferric chloride  addition to the primaries,  filter  yield
dropped  to 20  kg/m2/hr  (4 Ib/ft2/hr), and cake solids
were reduced to 44  percent.  Raising  the  operating
temperature of  the  thermal  conditioning  units  from
185°C (365 °F)  to 202 °C (395 °F)  resulted  in filter
yields of 78 kg/m.2/hr  (16 Ib/ft2/hr), and  cake solids  of
54 percent (1).

Design vacuum  filter loading rates  for various types  of
conventional  sludges are shown  in Table  5-6  (35).
                                                  105

-------
Relative  vacuum filtration characteristics  for various
components  of  wastewater sludges are  shown  in
Table 5-7. Composite characteristics are a function
of the proportionate amount of each component in the
total mixture. This is based on the assumption that
the accumulative effects  on vacuum filtration  are  a
function of the sum of the individual effects (35).

Table 5-14 lists design factors for conventional and
iron  sludges  using  vacuum  filtration of anaerobically
digested primary plus waste  activated sludge as  a
baseline (2). The factors in the table  can then be
used to  predict other yields. If  no actual  data  are
available on which to predict yields for other sludges,
a baseline value of  20 kg/m^/hr (4 Ib/ft2/hr) can be
used (2).
Table 5-14.  Design factors for Vacuum Filtration  of
           Conventional Plus Iron Sludges (2).
 Sludge Type
Relative
 Yield
Rel. Cost of
Cond toning*
                               kg/m2/hr     percent
Fe to primary
Raw primary + WAS
Raw primary + TF
Digested primary + WAS
Digested pnmary + TF
Digested primary
Raw primary
Fe to aeration
Raw primary + WAS
Digested primary + WAS

.3
.5
3.95
.1
.2
.6

1.3
3.95

1.1
1.0
1.2
1.1
0.8
0.7

1.1
1.2
 * Factors related to yield and costs obtained with digested primary
   + WAS when no chemicals are added to wastewater.
Another important design consideration is corrosion of
metal  components due  to  the corrosive  nature  of
ferric chloride. Use of stainless  steel components
may be justified if ferric chloride is to be employed for
phosphorus removal.

5.4.6.3 Centrifugation
Data from  the  literature indicate that sludges derived
from processes employing iron salts for phosphorus
removal  are amenable   to  dewatering  by
centrifugation.  However, decreased  cake solids and
poorer centrate quality  compared  to  conventional
non-chemical  sludges may  be  expected  in  some
cases.

Envirotech conducted extensive pilot studies on
dewatering  of  chemical  primary  sludges.  For  alum-
primary  sludges  centrifuge performance  relative  to
polymer  requirements and cake solids concentrations
was adversely affected as the quantity of aluminum
solids  in the  feed sludge  increased.  However, for
ferric-primary  sludge,  cake  solids  concentrations
increased  as  the amount of  iron  chemical  solids
present in the feed  sludge  increased,  and were
significantly  higher  than for  alum  primary  sludges.
Polymer requirements  and  machine  capacity  to
achieve a  given  level  of  solids capture  were  not
affected as the quantity  of iron chemical solids in the
feed sludge increased.  At total  solids capture of  95
percent, centrifugal  dewatering  of ferric-primary.
sludge produced  cakes of 22-25  percent  solids vs.
20-21  percent  solids  for the control primary sludge
with no iron (10).

Campbell  and LeClair  reported  on  pilot  scale
centrifugal dewatering of waste  sludge generated  by
an extended aeration  pilot plant  (36). Using a basket
centrifuge, it was  found  that the ferric chloride sludge
was more  difficult to dewater than either the alum
sludge or  the control  sludge with no chemical. Cake
solids for  the iron sludge  were 8.4-12.0  percent TS.
With a solid bowl centrifuge, cake  solids  achieved
with the iron sludge were essentially the same as the
control sludge,  but consistently  lower than  the alum
sludge. Cake  solids  with iron sludge were  3.4-8.4
percent TS. Polymer  addition was required  to obtain
solids recoveries in excess of 9.5 percent (36).

Centrifugation  of  anaerobically digested primary and
iron- secondary from the  North Toronto plant was
also investigated. A  feed  sludge of 6.6  percent TS
was dewatered  to  17.3-24.0  percent  TS with
polymer  dosages   of  4.4-6.5 kg/Mg  (8.8-13.0
Ib/ton). Solids recoveries were 98-99 percent (33).

Mininni et a/,   investigated centrifuge dewatering  of
aerobically digested  waste activated sludge from a
plant  with  no  primary  clarification. When ferrous
sulfate was added to the raw wastewater,  sludge cake
concentrations  dropped from  15.8  percent  to  13.0
percent. Cationic  polymer was used as a conditioning
agent  at similar  dosages in  both cases. The most
significant machine  variables were beach  residence
time and  liquid ring  height  (38).  Estimated sludge
handling costs  were  slightly lower  for iron  addition
than for aluminum addition (39).

As  discussed   in  Section  5.3.6.3, process  variables
affecting centrifuge  performance include source and
type of sludge, feed solids  content,  percentage  of
chemical  solids,  feed rate,  and conditioner  dosage.
Machine variables for a solid bowl centrifuge include
bowl  design and speed, pool volume,  conveyor
speed, and conveyor pitch (35).

Pilot testing is strongly recommended where possible,
as  the variability in  sludge characteristics  makes
performance impossible to  predict.  Procedures  are
available from  the various manufacturers  for  scale-
up  of  pilot-test results.

5.4.6.4 Pressure  Filtration
Limited information  is available  on pressure filtration
of iron  sludges. In the  EPA  survey,  plants reporting
                                                  106

-------
use of plate and frame filter presses on iron sludges
or combinations of  iron and conventional  sludges
included Saline, Michigan;  Kenosha, Wisconsin; and
Brookfield, Wisconsin  (1).  At Saline,  anaerobically
digested iron-primary plus secondary sludge  at  9
percent TS was dewatered  to  41  percent  TS; at
Kenosha,  anaerobically digested primary  plus  iron-
secondary sludge at 4.8 percent TS was  dewatered
to 40  percent TS;  and  at Brookfield  aerobically
digested primary plus iron-secondary sludge  at 7 to
8 percent TS was dewatered to 43 percent TS (1).

At Brookfield,  Wisconsin,  filter  press performance
improved  substantially  upon addition of pickle liquor
(ferrous sulfate) to the aeration basins for phosphorus
removal. The  sludge mass feed rate  (not including
admixtures) increased 70 percent from 227 to 384 kg
TS/hr  (500  to 845  Ib/hr);  average run  length
decreased by  40 percent from 2.8 to 1.7 hr/run; and
the percentage of solids fed  to the filter which  were
recovered  in  the  cake increased from  75 to  90
percent. The cake solids content remained essentially
constant at 43 percent TS (1).

Mininni et al. investigated pressure  filtration of waste
activated  sludge  from a  plant  with  no  primary
clarification. Upon addition  of ferrous chloride to raw
wastewater for phosphorus control,  cake solids
decreased from 32.1 to 30.0 percent TS. Aluminum
chlorohydrate  was used as a conditioner at dosages
of 12.7 and 12.1 g AI2C>3/kg (25.4 and 24.2 Ib/ton) of
dry solids during the periods  of no  chemical addition
and  during ferrous sulfate  addition, respectively
(38,39).

For further general information on pressure filtration of
sludge the reader is referred to  the  EPA  Process
Design  Manual on  Sludge Treatment  and Disposal
(4).

5.4.6.5 Belt Pressure Filtration
Many plants  are now  using belt filter presses for
sludge dewatering,  since,  in general, dryer sludge
cakes are  possible  compared to vacuum  filters and
centrifuges,  and  the  devices  are economically
competitive  with other   dewatering  equipment.
Unfortunately,  virtually  no  information is available in
the literature  regarding their performance on sludges
derived  from the addition of iron  salts for phosphorus
removal.

Performance  data  and  design  criteria for belt filter
presses  used  for  dewatering of  non-chemical
sludges may be found  in  Reference 4. Pilot-testing
is recommended if  belt  filter  presses   are  under
consideration for dewatering of sludges from chemical
phosphorus removal systems.

5.4.7 Incineration
Of  22  plants  contacted  in  the  EPA   survey of
phosphorus  removal  facilities which   employed
incineration,  six  reported significant  impacts  on
incineration  as a  result  of  chemical  addition  for
phosphorus  removal. Two of these plants used iron
salts for phosphorus removal. These were Wyandotte,
Michigan and Sheboygan, Wisconsin.

Wyandotte  reported  major problems  with  clinker
buildup in  the  multiple  hearth incinerator.  This
increased the time required for cleaning drop holes in
the hearth, and increased wear on the rabble arms.

Sheboygan operates a fluidized bed incinerator, which
receives  sludge cake  from a  vacuum  filter.  Ferric
chloride is added to the effluent of the trickling filters
for  phosphorus removal.  Phosphorus  removal  has
adversely affected incinerator capacity  due  to the
increased moisture content of the sludge cake from
the vacuum filter.  Cake solids dropped from 25.5  to
21.5 percent after  phosphorus removal was initiated.
The volatile  fraction  was  reduced  from  73-74
percent to 65  percent. The overall impact  was  a
reduction  in incinerator feed rate from 755 to 475 kg
dry solids/hr (1,660 to 1,050 Ib/hr), and an increase in
fuel consumption  from 246 to 517 l/Mg (59  to 124
gal/ton) (1).

Other  problems  associated  with incineration  of
chemical sludge have  been reported at  Sheboygan.
Slag formation  has caused plugging of tuyeres and
clogging of exhaust lines, increasing the frequency  of
inspections  and  maintenance. In addition, the  plant
manager believes that the ferric chloride in the sludge
is  responsible for  a  high  rate of corrosion of metal
ductwork (1).

It is apparent from the Sheboygan experience  that
ferric  chloride addition for phosphorus  removal can
impact critical incineration parameters  such as:  1)
cake  moisture content, 2)  calorific value  of the
sludge, and  3) relative  proportion of volatile and inert
material.  Table 5-9  lists  the  potential problems
associated with  chemical  sludge  incineration,  and
recommended solutions (40).

5.4.8 Disposal
As  discussed  in Section 5.3.8 for disposal  of  alum
sludges,  the most significant  impact  of chemical
addition on  sludge disposal  considerations  is the
increased sludge  mass  and  volume  for disposal,
resulting in increased disposal costs.

Information  in the  literature  indicates that  the
presence  of iron  precipitates  does  not adversely
affect the  agricultural value of the sludge with respect
to  crop yield, organic matter degradation,  nitrogen
availability,  and  other  soil  parameters (41-45).
However,  an increase in metal content of the sludge
may be expected as a result of precipitation with iron.
This may impact allowable loading rates to agricultural
land. Heavy metal  analyses must be conducted on a
case-by-case basis for the sludge  to  be  applied.
                                                 107

-------
Application rates, whether governed  by nitrogen or
heavy  metal  loadings,  will  be determined by  state
regulations.

Iron addition  is unlikely to affect the suitability of a
sludge for disposal at a sanitary  landfill.  However,
mass  landfills require that organic  materials  comply
with a maximum  moisture content  criterion.  As iron
addition may  increase moisture content in  sludge
cakes from dewatering processes,  this  may limit the
suitability for landfill disposal.
5.5 Sludges  Derived from  Biological
Phosphorus Removal Processes

5.5.7 Characteristics
Sludges derived from biological phosphorus removal
systems  exhibit properties  similar  to  conventional
biological  sludges.  The only possible  exception  is
sludge derived from the Phostrip process in which a
portion of the total sludge results from lime addition to
the anaerobic stripper vessel. Even with the Phostrip
process, the  volume of lime  sludge is relatively small
compared to the combined  volume of  primary and
waste activated sludge.

Because of  the mechanism of  excess phosphorus
uptake in biological phosphorus  removal systems,
resulting waste activated sludges tend to have higher
phosphorus  concentrations  than  conventional
sludges. Typical phosphorus concentrations in waste
activated  sludge  from  the Bardenpho  and  A/0
processes are 4-6  percent  by  weight  vs. 2-3
percent for conventional waste activated sludges.

Resolubilization of  phosphorus  during anaerobic
storage of lime- precipitated sludge in  the Phostrip
process is unlikely to occur, since the phosphorus is
bound to  the calcium  ion.  However, with A/O,
Bardenpho,  and other "pure" biological phosphorus
removal  systems,  it is  recommended that waste
activated sludge be kept aerobic  in order to prevent
phosphorus solubilization.

5.5.2 Sludge Generation Rates
Sludge generation  rates from biological phosphorus
removal systems are not expected to be significantly
different  than for conventional activated  sludge
systems,  and  solids production  will vary  with
wastewater characteristics  and  operational
parameters such as SRT.

The Phostrip process will likely generate somewhat
greater masses of sludge because of lime addition to
the anaerobic  stripper  supernatant.  Knowing  the
 characteristics of the supernatant and the necessary
 pH to remove the  desired quantity of phosphorus, the
 quantity  of  lime sludge  produced can be estimated
 using the procedure described in Section 5.6.
Theoretically, some increase in  sludge production
would be expected for biological phosphorus removal
systems due to the increased mass of phosphorus
taken up by the organisms. This will be dependent on
the phosphorus content of the waste activated sludge
(WAS). As shown  in Section 3.5.2.1, the theoretical
waste activated sludge yield  would  increase by 8.5
percent if the phosphorus  content  of the  WAS
increased  from 2  to  4 percent by weight.  If the
phosphorus content increased to 5 percent by weight,
the  theoretical mass  of  WAS  production  would
increase by  13 percent. It should be noted that on a
volumetric basis, the increased sludge mass may be
counteracted  by  an  improvement  in  settling
characteristics, as SVI values of  less than 80  ml/g
have been reported for the Modified Bardenpho and
A/O processes.

5.5.3 Thickening
Because of the potential release of phosphorus during
gravity thickening  of  waste  activated  sludge from
biological phosphorus removal  systems,  use  of
dissolved  air  flotation  thickening  is  recommended.
This would apply to the purely biological systems, and
would not be a concern with lime sludges derived
from treatment of the anaerobic stripper supernatant
in  the  Phostrip  process.   Lime  sludges can be
combined with  other sludges  and  handled by
conventional  sludge  handling processes  without
special  consideration  for phosphorus release.  With
"pure" biological systems, however, choice of sludge
handling  processes  must account  for potential
phosphorus  resolubilization  if thickened, stored,  or
stabilized  in  the absence of  oxygen.

5.5.4 Stabilization
Little data  are  available  regarding  the  fate  of
phosphorus  during aerobic or anaerobic stabilization
of  sludges  from  biological  phosphorus  removal
systems.  Phosphorus resolubilization would be
anticipated during anaerobic digestion.  However, at
Pontiac, Michigan, significant levels  of phosphorus in
anaerobic digester supernatant were  not observed,
possibly  due to  formation of  an  ammonium-
magnesium-phosphate precipitate  in the digester.

Phosphorus  release may  also be possible  during
aerobic digestion  due to destruction and  lysing of
biological solids.

Because  of the lack  of information on this subject,
consideration  may have to  be  given  to  chemical
treatment of  digester  supernatants for phosphorus
removal in order to minimize return of phosphorus to
the head  of the plant. Further studies are needed to
assess the  magnitude of  phosphorus release  during
stabilization of biological phosphorus removal sludges.

 In  some biological  phosphorus  removal systems
 employing long solids retention times, phosphorus-
 laden sludges are subjected to  dewatering  without
                                                 108

-------
separate  stabilization.  The acceptability  of  this
practice is dependent on regulations  as to  whether
such  sludges are considered stabilized  or  whether
separate  stabilization  is  required  prior to  land
disposal.

5.5.5  Conditioning
Sludges from biological phosphorus  removal systems
are   expected  to have  similar  conditioning
requirements  to  conventional non-phosphorus
sludges. Blending of lime sludge with other sludges in
the Phostrip process may reduce overall conditioning
requirements.

5.5.6  Dewatering
Sludges from biological phosphorus  removal systems
are expected  to  have  dewatering characteristics
similar to those from conventional  activated  sludge
systems. The lime sludge from  the  Phostrip  process
is not be expected to  adversely affect  dewatering,
and,  based  on experience  with dewatering  of  lime
sludges  alone,  may  improve  dewatering
characteristics when blended with other  sludges. No
specific design  information regarding loading  rates to
dewatering  equipment  is  available  for  biological
phosphorus  removal sludges.  Design   criteria for
conventional  primary and waste activated sludges
should be used  to  size  dewatering  equipment for
sludges  from  biological  phosphorus removal
processes if pilot-  or  full-scale performance  data
are not available.

5.5.7  Incineration
No unique problems are associated with incineration
of sludges  from  biological phosphorus  removal
systems. Sludges from "pure" biological  phosphorus
removal prcesses  will  have volatile solids contents
and  Btu values  similar to those  of conventional
biological  wastewater treatment sludges.  Phostrip
sludges, if lime sludge from  treatment  of the stripper
supernatant  is  included,  may  have  slightly lower
volatile solids contents  and Btu values  due  to the
addition of inert solids from the lime  addition step.
However, the overall impact is expected to be small.

5.5.8  Disposal
Sludges from biological phosphorus  removal systems
can be disposed of in the same manner as  sludges
from  conventional  biological  systems.  Higher
phosphorus  contents  may make sludges  from
biological  phosphorus removal  systems  particularly
attractive for agricultural utilization.


5.6   Sludges Derived  from  Addition  of
Lime

Lime  may be employed  for phosphorus  removal by
addition to the  primary  clarifier or  tertiary treatment
process.  Lime  is also  used to  remove  phosphorus
from the effluent of the  phosphorus  stripper tanks in
the Phostrip biological phosphorus removal systems
(47). The characteristics of the  sludge produced are
dependent on where the lime is added,  whether the
low lime or high lime process is  used, the alkalinity of
the water, and whether the various wastewater plant
sludges are combined with  the lime  sludge  before
processing  and  in  what  proportions they   are
combined.

As discussed in  Section 4.1, very few plants in the
United States use lime for phosphorus removal. Many
plants originally designed to use  lime have abandoned
the lime systems  in favor  of aluminum or iron salts.
The major disadvantages of  lime compared to metal
salts are significant  increase in sludge mass,  and
greater operation  and maintenance requirements for
cleaning  and maintaining  lime  handling equipment.
The following is  a brief discussion  of lime sludges
with references provided if further detail is desired.

Two general statements about  lime sludges can be
made. One is that use of lime for phosphorus removal
results in larger volumes of sludge before thickening
than does  the  use of metal salts  for  phosphorus
removal (1,48). Secondly, lime sludges  generally
improve the thickening and dewatering properties of
wastewater  treatment sludges when  lime sludge and
non-lime wastewater sludges are mixed  (13).

Due to the fact that the nature of the sludge produced
will vary  with the specific wastewater being treated
and the composition of the sludge, the design of the
sludge handling system must be based at a minimum
on  laboratory  tests such as  settleometer  tests,
specific resistance,  filter leaf, capillary suction  time
and other tests.  Where  possible,  pilot-  or  full-scale
sludge thickening  and dewatering devices should be
used to establish  design criteria for full-scale  sludge
thickening and dewatering devices.

Specific differences expected to  be  found  in   the
different lime treatment systems  are listed below.

A. Low Lime Treatment - Primary Addition.

   1. The sludge  contains a  smaller  percentage  of
    organics than does high lime treatment (49).

  2. The sludge  contains  no magnesium hydroxide,
    which  is a gelatinous precipitate that is difficult
    to settle (13,49).

B. High Lime Treatment  -  Primary Addition

   1. Sludge removed from high  lime treatment has a
    higher solids content than that from  low  lime
    treatment (50).

  2. The sludge  contains  magnesium  hydroxide, a
    gelatinous precipitate.
                                                 109

-------
C. Tertiary Lime Process (11).

   1. Tertiary lime sludges are similar to primary  lime
     sludges but do not contain nearly the quantity of
     organic materials as  primary  sludge.

   2. The high lime tertiary  process will  produce a
     sludge  that behaves much  like sludge from a
     water  softening  process. The thickening  and
     dewaterability  of this  sludge  decreases  with
     increasing  magnesium  concentration in  the
     sludge.

   3. High alkalinity waters,  (greater than 200  mg/l
     CaCOa)  require special  consideration  for
     thickening  of the   sludge  as  the  thickening
     operations can become unmanageable.

   4. Recycle  of  sludge  from  the settling  unit
     improves thickening  of the sludge.

Specific  data  on  the thickening,  dewatering  and
disposal of lime sludges are contained in the following
sections. Recommended reading  for primary  lime
sludges are articles by Minton and  Carlson (48), who
did a number of studies on these sludges  in the early
1970's, and Parker (50,51).

Theoretical calculations   of  sludge  generation  rates
appear to give good correlation with observed sludge
volumes  in plant studies  for tertiary lime addition but
underestimate the quantity  for primary lime addition
(48). The quantity of sludge produced by lime addition
depends not  only on   the degree of  phosphate
removal desired,  but  also  on  the magnesium
concentration, alkalinity  and other characteristics of
the  wastewater  (52). In fact, both  the  amount of
sludge produced  and  the  degree  of  phosphorus
removal  achieved  by  raising the  pH  to a given  level
depends on the nature of the wastewater.

Increases in the mass of sludge solids produced by
lime addition  systems  have been  reported to be
double the mass  produced by conventional primary
and secondary treatment systems  (53).  Minton  and
Carlson have reported the mass of lime sludges to be
as much  as two to  three  times  the  mass  of
conventional  primary   and secondary  treatment
systems when lime is added to raw wastewater.

An important factor that  must be kept in mind is that
while  the  sludge  mass increases, lime  sludges
generally thicken and dewater to high solids content
and the volume of dewatered sludge that needs to be
processed  is  not necessarily two to three  times the
volume  of sludge  from  a  wastewater plant  without
chemical phosphorus removal.

Procedures have been  developed for calculating the
sludge quantity  produced from  lime sludges. These
procedures  were  developed  for tertiary  lime
applications but can be used for raw sewage or other
applications. The procedure is  described in detail in
the 1976 EPA Phosphorus Design Manual (4).


5.7 Case Histories
5.7.7 Baltimore, Maryland (54)
The Back River Wastewater Treatment Plant provides
secondary  treatment  of   municipal-industrial
wastewater from Baltimore City and  Baltimore County,
Maryland.   Liquid stream  processes  include
preliminary  treatment,  primary clarification, biological
treatment  by parallel  trickling  filters and  activated
sludge  process,  secondary  clarification,  and
chlorination. Primary and waste activated sludges are
thickened  by  gravity,  anaerobically  digested,
chemically  conditioned with polymer, and dewatered
using vacuum  filters.  Phosphorus is  removed  by
addition of iron as waste pickle liquor to the activated
sludge aeration  basins at a dosage of approximately 5
mg/l as Fe. Full-time  addition of waste pickle liquor
began in June, 1981.

Data on sludge handling operations  were  compared
for periods  with  and without  waste  pickle  liquor
addition. Prior to waste pickle liquor addition, average
daily sludge production  was 62 Mg  (69 tons)/d dry
solids, and  353 Mg   (390 tons)/d  wet.  After  pickle
liquor addition,  average  daily  sludge production was
80 Mg  (88 tons)/d dry  solids,  and 414  Mg  (456
tons)/d  wet. This  amounted  to an  increase  of  29
percent on a dry  solids basis, and 17 percent on a
wet  solids  basis  following initiation  of  phosphorus
removal. The  smaller percentage  increase  in  wet
sludge  production  was due to  generation  of  a drier
vacuum filter cake as a result of waste pickle liquor
addition. Cake solids increased from 17.6  percent to
19.1 percent, an improvement of 9 percent.

Coupled with an increase in vacuum filter cake solids
was  reduction in polymer  required for  sludge
conditioning.  Prior to iron addition,  polymer  dose
based on  dry solids,  was  34  kg/Mg (68 Ib/ton); after
iron addition, polymer  dose was 30 kg/Mg (60 Ib/ton),
a decrease of approximately 11 percent.

Thickening characteristics of combined raw  primary
and secondary sludges  did  not appear to  change
significantly as a  result  of  pickle  liquor addition.
Changes were attributed to operational modifications.

Figure  5-5  summarizes  the costs  of  sludge
conditioning and hauling before and after phosphorus
removal. It should  be  noted that these costs are only
for  chemical  conditioning  and dewatered  sludge
hauling, and do not  account for additional operation
and maintenance labor or energy requirements.

5.7.2 Lorton, Virginia (55)
The Lower Potomac Water Pollution Control Plant is a
 136,000-m3/d  (36-mgd)  activated  sludge  facility
                                                 110

-------
 Figure 5-5   Comparison of sludge quantities, conditioning costs, and hauling costs before and after phosphorus removal;
            Baltimore, MD.
          62 dry t/d
                                         2,110 hg/d polymer
                                         @$0.15/kg
                                         = $320/d

                                      Before Phosphorus Removal
                   353 wet t/d hauled
                   @ $38.31/t
                   = $l3,520/d
                     Total Cost
                     = $l3,840/d
          80 dry t/d
                                         2,400 hg/d polymer
                                         @$0.15/kg
                                         = $360/d

                                      After Phosphorus Removal
                   414 wet t/d hauled
                   @ $38.31/1
                   = $15,860/d
                     Total Cost
                     = $16,220/d
with advanced wastewater treatment for  phosphorus
removal.  Liquid  stream  processes  consist  of bar
screens,  primary clarifier,  activated  sludge  basins,
secondary clarifier,  flow  equalization basins,  tertiary
chemical  clarifiers for  phosphorus precipitation, and
tertiary filters. Primary  sludge is degritted and gravity
thickened. Waste activated sludge  is  thickened by
dissolved air flotation.  Primary  and  waste activated
sludges are blended in  a storage  tank,  chemically
conditioned with  lime  and  ferric chloride,  and
dewatered by  vacuum filtration.  Dewatered  sludge
cake,  at 16-18  percent  solids, is incinerated  in
multiple-hearth  furnaces.  The  tertiary chemical
sludge  is conditioned with  lime, gravity thickened  to
2-3 percent  solids, conditioned with  anionic polymer,
and  dewatered  in solid bowl centrifuges.  Dewatered
sludge  cake, at a solids content of 15-16  percent,  is
mixed  with incinerated  sludge ash and disposed of  in
a sanitary landfill.

Originally the plant  was  designed  for  phosphorus
removal in a tertiary process using a two-stage  lime
and  recarbonation system. Because of  numerous
design, operation,  and maintenance problems  and
high operating  costs,  the plant was  modified to
remove phosphorus using ferric chloride.  Ferric
chloride is  normally added  to  the plant influent,
activated  sludge  process, and  influent  to  tertiary
clarification.  Ferrous sulfate  addition to  the return
activated  sludge was investigated during the  period
April  through  July of 1983.  During  this  time,  ferric
chloride addition to the  plant influent and influent to
tertiary clarification was  maintained.  From  June
through October,  1984,  ferrous sulfate was added to
the plant  influent  while ferric chloride addition  to  the
activated  sludge  process and  tertiary clarifiers was
maintained.  Results  of these investigations with
respect to impact on solids  handling  are discussed
below.

Ferrous sulfate addition to return activated sludge
Total  suspended  solids  removal in the secondary
clarifier improved significantly during ferrous sulfate
addition to the return activated sludge. TSS removal
efficiencies  were  87 percent during ferrous sulfate
addition and 80 percent during ferric chloride addition.
Performance of dissolved  air flotation thickening  of
waste activated sludge was slightly  improved  during
ferrous  sulfate  addition,  with  thickened solids
concentrations  increasing from  4.4 to 4.9 percent by
weight. However,  the improved performance was  not
solely attributed to ferrous sulfate addition.

Ferrous sulfate addition to plant influent
Gravity thickening  of primary sludge improved with
addition of ferrous sulfate to the plant influent, with
average thickened  solids concentrations increasing
from 6.6 to 8.7 percent.
                                                   111

-------
Performance of vacuum filters improved during  the
period of ferrous sulfate addition to the plant influent.
Average total solids concentration in the vacuum filter
sludge cake increased from 16.4 percent during ferric
chloride addition to 18.7 percent during ferrous sulfate
addition.  There was  no  change in  chemical
requirements for conditioning.

Another observation  was that the chemical "ferric"
sludge from the tertiary clarifier dewatered to a higher
cake solids content  when ferrous sulfate was added
to the  influent,  increasing  from 15-16  percent  to
approximately  19 percent. Although no  explanation
was provided as to  the reason for the improvement,
the same phenomenon was observed when ferrous
sulfate  addition was temporarily  suspended and then
restarted.

The  major conclusion  from the study  was that,
although ferrous sulfate  was more costly  than ferric
chloride per unit  of phosphorus removed, the savings
resulting from improved thickening  and dewatering
characteristics may  make  its use cost-effective for
this application.


5.8 Costs
No estimates  have been  provided  for  the  costs
incurred in handling  additional sludge associated with
phosphorus removal processes.  This is partly due to
the wide  variability  in sludge generation rates as  a
result  of variation  in  process  types,  operating
strategies, chemical used for  phosphorus  removal (if
any),  effluent  discharge  limitations,  wastewater
characteristics,  and  other factors.  Costs  are
dependent not only on the  additional  quantity of
sludge  to  be  processed,  but also  on changes in
thickening and  dewatering  characteristics of  the
sludge,   types  of  sludge  handling  processes
employed, existing  sludge  handling capacity, labor
and  energy costs,  and  available sludge  disposal
options.

Estimates of the additional costs for sludge handling
upon implementation of phosphorus removal can only
be made  on a site-specific basis. Sludge generation
rates can be estimated using the procedures outlined
in this  chapter. Laboratory  tests can  be  used to
estimate  the  impact of  phosphorus  removal  on
thickening and dewatering  characteristics. A capacity
analysis  of sludge handling equipment must  be
conducted in order  to determine if more  tankage or
equipment will be required to process the additional
sludge. A similar analysis of manpower schedules and
requirements must  also  be made. Finally, the overall
impact  on the volume of  sludge to be  disposed of
must be  assessed  in order to estimate  additional
disposal  costs. For  chemical precipitation of
phosphorus, cost for sludge handling and disposal is
likely to account for a major portion of the additional
costs associated with phosphorus  removal,
cannot be ignored.
and
5.9 References
When an NTIS  number is cited in a reference, that
reference is available from:

      National Technical Information Service
      5285 Port Royal Road
      Springfield, VA22161
      (703)  487-4650

1.  Schmidt, C.J., Hammer, L.E. and M.D. Swayne.
    Review of Techniques for Treatment and Disposal
    of  Phosphorus  - Laden  Chemical Sludges.
    EPA-600/2-79-083,  NTIS   No.  PB80-117542,
    U.S. Environmental Protection Agency, Municipal
    Environmental Research Laboratory, Cincinnati,
    OH, 1979.

2.  Process Design Manual for Phosphorus
    Removal.  EPA-625/1-76-001a,   NTIS  No.
    PB-259150, U.S. Environmental  Protection
    Agency, Center  for  Environmental  Research
    Information,  Cincinnati, OH,  1976.

3.  Knight, C.H.,  Mondoux, R.G.  and  B. Hambley.
    Thickening and Dewatering Sludges Produced in
    Phosphate  Removal. In Phosphorus  Removal
    Design Seminar Conference Proceedings No. 1,
    Canada- Ontario Agreement, Toronto, 1973.

4.  Process Design Manual: Sludge Treatment and
    Disposal.  EPA   625/1-79-011,   U.S.
    Environmental  Protection  Agency,  Center for
    Environmental Research Information,  Cincinnati,
    OH, 1979.

5.  Wastewater Engineering. Metcalf and Eddy, Inc.,
    McGraw-Hill Book Co.,  New York,  1972.

6.  Keinath, T.M.,  Ryckman, M.D.,  Dana, C.H.  and
    D.A.  Hofer. Design  and Operational Criteria  for
    Thickening of Biological Sludges, Parts I, II,  III,
    IV. Water Resources Research Institute, Clemson
    University. September, 1976.

7.  Gravity  Thickening.  In:  Process  Design
    Techniques for Industrial Waste Treatment. Edited
    by C.E. A
-------
    PB-299593,  U.S.  Environmental  Protection
    Agency, Center  for  Environmental  Research
    Information, Cincinnati, OH, 1978.

10. DiQregorio,  D., Ainsworth,  J.B.  and  K.J,
    Mounteer. Chemical  Primary Sludge  Thickening
    and  Dewatering.  EPA-600/2-79-055,  U.S.
    Environmental  Protection  Agency,  Municipal
    Environmental Research Laboratory, Cincinnati,
    OH, 1979.

11. Nutrient Control. Manual of Practice FD-7. Water
    Pollution Control  Federation, Washington,  D.C.,
    1983.

12. Kos,  P.  Gravity Thickening of  Water Treatment
    Plant Sludge. JAWWA,  Research Edition,  272-
    279, May, 1977.

13. Dick, R.I. Management of Phosphorus-Laden
    Sludges. In:  Proceedings of the  International
    Conference:  Management  Strategies  for
    Phosphorus  in  the Environment.  Edited  by  J.N.
    Lester and  P.W. Kirk, Lisbon,  Portugal,  July,
    1985.

14. Long, D.A. and J.B. Nesbitt. Removal of Soluble
    Phosphorus in an Activated Sludge Plant. JWPCF
    47(1 ):170-184,  1975.

15. Martel,  C.J.,  DiGiano, F.A. and  R.E. Pariseau.
    Phosphorus  Removal in  Extended Aeration
    Systems by Chemical Clarification. JWPCF
    51(1):140-149,  1979.

16. Lin, S.S. and D.A. Carlson. Phosphorus Removal
    by  the  Addition of Aluminum to the Activated
    Sludge  Process. JWPCF  47(7): 1978-1986,
    1975.

17. Baillod,  C.R., Cressey, G.M. and R.T. Beaupre.
    Influence of Phosphorus  Removal on Solids
    Budget. JWPCF 49(1):131-145, 1977.

18. Ganczarczyk, J. and  M.F.D. Hamoda. Aerobic
    Digestion of Organic Sludge Containing Inorganic
    Phosphorus  Precipitates,  Phase  1.  Canada -
    Ontario Agreement on Great Lakes Water Quality,
    Research Report No. 3,  Environment Canada,
    Ottawa, June, 1973.

19. Mitchell,  G.F., Seyfarth,  R.H.  and F.R.  Wilson.
    Effect of Alum Addition on Aerobic  Digestion of
    Activated Sludge. Water  and  Sewage Works
    124(7):58-62,  1977.

20. Eikum,  A.S.,  Carton, D.A.  and  A.  Lundar.
    Phosphorus  Release  During  Storage of
    Aerobically  Digested  Sludge.  JWPCF,
    47(2):330-337,  1975.
21. Grigoropoulos, S.G., Vedder, R.C. and D.W. Max.
    Fate of Aluminum  - Precipitated Phosphorus in
    Activated Sludge  and  Anaerobic  Digestion.
    JWPCF 43(12):2366-2382, 1971.

22. O'Shaughnessy,  J.C.,  Nesbitt,  J.B.,  Long,  D.A.
    and R.R.  Kountz.  Digestion and Dewatering of
    Phosphorus-Enriched  Sludges.  JWPCF
    46(8):1941-1962,  1974.

23. Dentel, S.K.  and J.M. Gossett. Effect of Chemical
    Coagulation  on Anaerobic Digestibility of Organic
    Materials. Water  Research 16:707-718, 1982.

24. Gossett,  J.M., McCarthy,  P.L.,  Wilson,  J.C. and
    D.S. Evans.  Anaerobic Digestion of Sludge  from
    Chemical Treatment.  JWPCF  50(3):533-542,
    1978.

25. Farrell, J.B.  Design Information on Dewatering
    Properties  of Wastewater  Sludges.  Sludge
    Handling  and Disposal  Seminar  Conference
    Proceedings  No.  2,  Environment  Canada,
    Toronto, Ontario,  1974.

26. Williamson, D.J. and G. Wheale. The Influence of
    Sludge Storage on  Chemical Conditioning Costs.
    Water Pollution Control, 80:529-536, 1981.

27. Novak,  J.T.  and J.H.  O'Brien.  Polymer
    Conditioning  of Chemical  Sludges.  JWPCF
    47(10):2397-2410,  1975.

28. Hudgins,  R.R. and  P.L. Silveston.  Wet  Air
    Oxidation of  Chemical Sludges.  Research Report
    No.  12,  Canada-Ontario  Agreement  on Great
    Lakes  Water  Quality, Environment  Canada,
    Ottawa, Ontario, 1973.

29. Farrell, J.B.,  Smith, J.E.,  Dean,  R.B., Grossman,
    E.  and  O.L. Grant.  Natural Freezing  for
    Dewatering  of Aluminum Hydroxide Sludges.
    JAWWA  62(12):787-791,  1970.

30. Reed,  S.,  Bouzoun,  J.  and W.  Medding.  A
    Rational  Method  for  Sludge  Dewatering  Via
    Freezing. JWPCF 50(9):911-916, 1986.

 31.Novak, J.T.  and G.E.  Montgomery.  Chemical
    Sludge  Dewatering on  Sand  Beds.  Journal
    ASCE-EED  101(2):1-14,  1975.

32. Sludge Dewatering. Manual of  Practice  No.  20.
    Water Pollution Control Federation, Washington,
    D.C., 1983.

33. Stickney,  R.  and  B.P.  LeClair.  The  Use  of
    Physicochemical Sludge  Characteristics  and
    Bench Dewatering Tests in   Predicting  the
    Efficiency  of Thickening and  Dewatering
    Processes.  Sludge  Handling  and  Disposal
                                              113

-------
   Seminar  Conference  Proceedings  No.  2,
   Environment Canada, Ottawa, 1974.

34. Van Fleet,  G.L., Barr,  J.R. and  AJ.  Harris.
   Treatment and Disposal of Phosphate Sludges in
   Ontario. Presented at the Annual Conference of
   WPCF, Atlanta, GA, 1972.

35. Wastewater  Treatment  Plant Design.  WPCF
   Manual of Practice No. 8, Water Pollution Control
   Federation, Washington, D.C., 1977.

36. Campbell,  H.W. and   B.P.  LeClair.  Sludge
   Dewatering Alternatives for  Waste  Activated
   Sludges  from Phosphorus  Removal  Facilities.
   JWPCF 51(5):991-998,   1979.

37. Campbell, H. and B.P. LeClair. Effects of Control
   Variables  and  Sludge  Characteristics on  the
   Performance of  Dewatering and Thickening
   Devices.  In: Sludge Handling  and  Disposal
   Seminar  Conference  Proceedings  No.  2.
   Environment Canada, Ottawa, 1974.

38. Mininni, G.,  Passino, Ft.,  Santori, M. and  L.
   Spinosa. Sludge  Dewatering  in  A  Conventional
   Plant with  Phosphorus  Removal-ll:  Study  on
   Centrifuge and  Filter Press Performance. Water
   Research  19(2): 151-156, 1985.

39. Mininni, G.,  Passino, R.,  Santori, M. and  L.
   Spinosa. Sludge  Dewatering  in a  Conventional
   Plant with Phosphorus  Removal-l: Analysis of
   Additional  Costs. Water  Research  19(2):143-
   149, 1985.

40. Shannon,  E.E., Plummer, D.  and P.J.A. Fowlie.
   Aspects of Incinerating  Chemical Sludges.  In:
   Sludge  Handling   and  Disposal  Seminar,
   Conference  Proceedings No. 2.  Environment
   Canada, Ottawa, 1974.

41. Gaynor,  J.D.  Soil Degradation of Wastewater
   Sludges  Containing Chemical Precipitants.
   Environmental Pollution:57-64, 1979.

42. Soon, Y.K.,  Bates,  I.E., Beauchans,  E.G.  and
   J.R.  Moyer. Land  Application  of Chemically
   Treated Sludge:  I.  Effects  on Crop  Yield and
   Nitrogen Availability. J.  Environmental  Quality
   7(2):264-269, 1978.

43. Soon, Y.K.,  Bates,  I.E.  and J.R.  Moyer.  Land
   Application  of Chemically  Treated Sewage
   Sludge: II. Effects on Plant and Soil Phosphorus,
   Potassium,  Calcium, and Magnesium and  Soil
   pH. J. Environmental   Quality 7(2):269-273,
    1978.

44. Chawla, V.K., Bryant, D.N.  and  D.  Liu.  Disposal
   of Chemical Sewage Sludges on Land and Their
   Effects on Plants, Leachate, and Soil Systems. In:
   Sludge  Handling  and  Disposal  Seminar,
   Conference  Proceedings  No.  2.  Environment
   Canada, Ottawa, 1974.

45. Kirkham, M.B. and G.K. Dotson. Growth of Barley
   Irrigated with  Wastewater Sludge  Containing
   Phosphorus  Precipitants. In: Proceedings of the
   National Conference  on  Municipal  Sludge
   Management, Pittsburgh, PA, June 11-13, 1974.

46. Malhotra,   S.K.,  Parrillo,  T.P.  and  A.G.
   Hartenstein. Anaerobic Digestion of Sludges
   Containing   Iron  Phosphates.  Journal ASCE,
   Sanitary  Engineering Division  97(SA5):629-645,
   1971.

47. Heim, C.J., The Phostrip Process for Phosphorus
   Removal. Proceedings of  the  International
   Seminar  on  Control  of  Nutrients  in Municipal
   Wastewater Effluents, Volume 1:Phosphorus.  San
   Diego, CA, 1980.

48. Minton, G.R. and D.A. Carlson. Effects of Lime
   Addition  on  Treatment  Plant Operation. JWPCF
   48(7):1697-1727,  1976.

49. Mulbarger, M.C., Grossman, E.,  Dean, R.B.  and
   O.L. Grant.  Lime Clarification  Recovery, Reuse,
   and Sludge  Dewatering Characteristics. JWPCF
   41(12):2070-2085,  1969.

50. Parker, D.S., Zadich, F.J. and K.E. Train. Sludge
   Processing  for  Combined Physical-Chemical-
   Biological   Sludges.  EPA-R2-73-250,  NTIS
   No.  PB-223334,  U.S. Environmental  Protection
   Agency, 1973.

51. Parker,  D.S.,  de  la  Fuente,  E., Britt,  L.O.,
   Spealman, M.L.,  Stenquist, R.J. and F.J. Zadich.
   Lime Use in Wastewater Treatment:  Design  and
   Cost  Data.  EPA-600/2-75-038,  NTIS   No.
   PB-248181, U.S.  Environmental  Protection
   Agency, Municipal  Environmental  Research
   Laboratory, Cincinnati, OH,  1975.

52. Farrell, J.B. Interim  Report of Task Force on
   Phosphate  Removal  Sludges.  NTIS No.  PB-
   238317,  U.S.  Environmental Protection Agency,
   National Environmental  Research  Center,
   Cincinnati, OH, 1975.

53. Minton, G.R. and D.A. Carlson. Primary Sludges
   Produced by the Addition of Lime  to Raw Waste
    Water. Water Research 7:1821-  1847,  1973.

54.  The Effect of a Ban on Phosphates in Household
   Detergents on  the  Treatment  of  Municipal
    Wastewater. A report prepared for the Soap and
                                               114

-------
    Detergent Association  by Gannett Fleming
    Environmental Engineers, Inc., February, 1985.

55. Hogge,  A.H., Jenkins,  J.D. and  I.A.  Khan.  Full
    Scale  Evaluation of Ferrous  Sulfate  for
    Phosphorus Removal  and Its Impact on  Solids
    Handling.  Paper presented at  the 58th  Annual
    Conference of the WPCF, Kansas City, Missouri,
    October, 1985.
                                               115

-------
                                             Terms
BOD        biochemical oxygen demand
BODs       5-day BOD
COD        chemical oxygen demand
DO         dissolved oxygen
F/M         food-to-microorganism loading
gpd         gallons per day
gpm        gallons per minute
HOT        hydraulic detention time
HRT        hydraulic retention time
mgd        million gallons per day
mg/l        milligrams per liter
MLSS       mixed liquor suspended solids
MLVSS     mixed liquor volatile suspended solids
NH4-N      ammonium nitrogen
NOa-N      nitrate nitrogen
SBOD      soluble 5-day BOD
SDT        stripper detention time
SP         soluble phosphorus
SRT        solids retention time
SS         suspended solids
TBOD      total 5-day BOD
TKN        total Kjeldahl nitrogen
TN         TKN plus oxidized nitrogen
TP         total phosphorus
TSS        total suspended solids
VSS        volatile suspended solids
                                                116
                                                    U.S. GOVERNMENT PRINTING OFFICE: 1987- 748-121/67006

-------