xvEPA
           United States
           Environmental Protection
           Agency
          Hazardous Waste Engineering
          Research Laboratory
          Washington DC 20460
EPA/600/2-87/065
August 1 987
           Research and Development
Construction Quality
Control and
Post-Construction
Performance
Verification for the
Gilson Road
Hazardous Waste Site
Cutoff Wall

-------
                                               EPA/600/2-87/065
                                               August 1987
CONSTRUCTION QUALITY CONTROL AND POST-CONSTRUCTION
          PERFORMANCE VERIFICATION FOR  THE
   GILSON ROAD HAZARDOUS WASTE SITE CUTOFF WALL
                         by

        Matthew J.  Barvenik  &  John E. Ayres
         Goldberg-Zoino & Associates, Inc.
                 320 Needham  Street
     Newton  Upper Falls, Massachusetts  02164
                   Project Officer

                    Stephen  James
           Land Pollution Control Division
  Hazardous Waste Engineering Research Laboratory
               Cincinnati, Ohio  45268
   WATER SUPPLY  AND POLLUTION  CONTROL COMMISSION
               STATE OF NEW HAMPSHIRE
           CONCORD, NEW HAMPSHIRE  03301
  HAZARDOUS WASTE ENGINEERING  RESEARCH LABORATORY
       U.S. ENVIRONMENTAL PROTECTION AGENCY
              CINCINNATI, OHIO  45268
                U.S. Environmental Protection Agency
                Region 5, Library (PL-12J)
                77 West Jackson Boulevard, 12th Floor
                Chicago,  IL 60604-3590

-------
                          NOTICE


     The  information in this document has been funded by the U.S.
Environmental Protection  Agency  and  the New Hampshire  Water
Supply and  Pollution Control  Commission  under  cooperative
agreement Contract No.  CR811130-01 with  Goldberg-Zoi no &
Associates,  Inc.   It  has been  subjected to the Agency's peer
review and administrative  review,  and  it has been approved for
publication  as a U.S.  EPA document.   Mention of trade names or
commercial products does not  constitute  an endorsement  or
recommendation for use.
                             11

-------
                            FOREWARD
    Today's rapidly developing and changing  technologies  and
industrial  products and practices frequently carry  with  them the
increased generation of solid and hazardous  wastes.   These
materials,  when improperly dealt  with,  can  threaten  both  public
health and  environment.  Abandoned waste sites  and  accidental
releases of toxic and hazardous substances  to the environment
also have important environmental and public health  implications.
The Hazardous Waste Engineering Research Laboratory  helps  provide
an authoritative and defensible engineering  basis for assessing
and solving these problems.   Its  products support the policies,
programs, and regulations of the  Environmental  Protection  Agency;
the granting of permits and  other responsibilities  of State  and
local  governments;  and the needs  of both large  and  small
businesses  in handling their wastes responsibly and  economically.

     This report describe assessment activities undertaken to
evaluate the effectiveness of a soil/bentonite  backfilled  cutoff
wall (slurry trench) installed for the  purpose  of hazardous  waste
containment.  The work includes development  and revaluation of
field  quality control  tests, evaluation of  electronic piezocone
instrumentation for post-construction verification  of backfill
homogeneity, and evaluation  of cutoff wall  bulk hydraulic
conductivity via hydraulic stress testing.   This  information in
this report is useful  to those involved in  the  feasibility study,
design and/or construction of cutoff walls  as a hazardous  waste
remediation technology.

     For further information, please contact the  Land Pollution
Control  Division of the Hazardous Waste Engineering  Research
Laboratory.
                            Thomas  R.  Hauser,  Director
                            Hazardous  Waste  Engineering
                            Research  Laboratory
                                       11

-------
                          ABSTRACT


     This  report is intended to provide a  critical assessment of
the construction and effectiveness of a soil/bentonite backfilled
cutoff wall (slurry  trench)  installed  for the purpose of
hazardous waste containment.  The wall was designed, constructed,
and monitored as part  of  the  remediation  action implemented on
the Gilson Road site in  Nashua, New Hampshire (National Priority
List  [NPL]  #23).   This work  was conducted in three distinct
phases.

     The first phase consisted of an evaluation of the accuracy,
precision, and applicability  of two new field quality control
tests  developed  specifically to be used for control of wall
construction.  The  API  fixed  ring test and the methylsne blue
titration  test allowed  real  time  determination of backfill
hydraulic conductivity and  percent bentonite, respectively.  The
resulting field data were assessed with respect to cutoff wall
specification requirements  and guidelines were developed.

     The second phase of the work  encompassed field  testing of
electronic piezocone instrumentation to determine feasibility for
post-construction  verification of backfill homogeneity.  This
entailed evaluation  of  piezocone response  characteristics with
respect to intact  backfill versus non-backfill materials in  a
specially constructed full  scale  test  section.    Response
signatures were  then  used to evaluate the homogeneity  of the
Gilson Road containment wall followed by verification via  direct
sampling.

     The primary objective  of  the  third phase  of  the project was
to hydraulically stress the containment wall to assess its bulk
hydraulic conductivity and thus its overall effectiveness with
respect to hazardous  waste  containment.   This   work  was
supplemented with documentation of the spacial and temporal
variation in contaminant  concentrations  as they reflect the
behavior of  the hydrologic system in response to containment wall
installation.

     This report  is intended  to document actual site specific
data with  respect to the effectiveness of a  soil/bentonite  cutoff
wall used for hazardous waste  containment.  The data can then  be
used by those formulating and reviewing remedial action plans  to
rationally assess the suitability of cutoff walls  incorporated  as
part of the overall site remediation proposed for other  sites.
                              IV

-------
                            CONTENTS
NOTICE	  i i
FOREWORD	  iii
ABSTRACT	  i V
CONTENTS	  V
FIGURES	  ix
TABLES	  xi i
ACKNOWLEDGEMENTS	  xiv

1.   INTRODUCTION	  1-1
1.1  Overview	  1-1
1. 2  Background	  1-3
     1.2.1  Site Description and Geology	  1-3
     1.2.2  Remedial Measures	  1-4
     1.2.3  Design and Construction	  1-5
1.3  Report Organization	  1-5

2.   FIELD QUALITY CONTROL TESTING PROCEDURES	  2-1
2.1  Evaluation of Backfill Hydraulic Conductivity
     Using the Fixed Ring Apparatus	  2-2
     2.1.1  API Fixed Ring Test	  2-4
     2.1.2  Testing Program	  2-6
            2.1.2.1  API Fixed-Ring Test Precision	  2-6
            2.1.2.2  API Fixed-Ring Test Accuracy	  2-8
     2.1.3  Guidelines for Field use of the API Fixed-
            Ring Test	  2-13
            2.1.3.1  Verification Testing	  2-14
            2.1.3.2  Production Testing	  2-14
2.2  Evaluation of Backfill Bentonite Content Using
     Methylene Blue Titration	  2-17
     2.2.1  Methylene Blue Titration	  2-18
     2.2.2  Testing Program	  2-20
            2.2.2.1  Distilled Water Matrix	  2-20
            2.2.2.2  Ottawa Sand/Distilled Water Matrix...  2-23
            2.2.2.3  Contaminated Water Matrix	  2-25
            2.2.2.4  Gilson Road Backfill Matrix	  2-27
     2.2.3  Field Use of the Methylene Blue Test	  2-31
2.3  Effect of Backfill Gradation on Hydraulic
     Conductivity	  2-33
     2.3.1  Data Base	  2-34
     2.3.2  Statistical Evaluation	  2-35
     2.3.3  Importance of  Statistical Correlation	  2-37
2.4  Assessment of  Gilson  Road QC Data	  2-38
     2.4.1  Review of QC Data	  2-39
            2.4.1.1  QC Data from Construction Samples....  2-39
                                v

-------
                   CONTENTS (continued)
            2.4.1.2  QC Data from Post-Construction
                     Samples	   2-43
            2.4.1.3  Evaluation of the Validity of  the
                     QC Construction Data	   2-47
            2.4.1.4  Implication of QC Data on Containment
                     Perf ormance	   2-47
2.5  Quality Control Guidelines	   2-50
     2.5.1  General Quality Control Guidelines	   2-50
            2.5.1.1  Test Requirements	   2-50
            2.5.1.2  Quality Control Execution	   2-51
     2.5.2  QC Guidelines for Support Slurry	   2-53
            2.5.2.1  Unit Weight	   2-54
            2.5.2.2  Viscosity	   2-55
            2.5.2.3  Filtrate Loss	   2-55
     2.5.3  QC Guidelines for Trench Excavation	   2-56
            2.5.3.1  Verticality	   2-56
            2.5.3.2  Continuity	   2-57
            2.5.3.3  Key Penetration	   2-57
            2.5.3.4  Key Cleaning	   2-58
            2.5.3.5  Stability	   2-59
     2.5.4  QC Guidelines for Backfill	   2-60
            2.5.4.1  Unit Weight	   2-60
            2.5.4.2  Slump	   2-61
            2.5.4.3  API Fixed-Ring Hydraulic Conductivity
                     Testing	   2-61
            2.5.4.4  Methylene Blue Titration for
                     Bentonite Content	   2-62
            2.5.4.5  Gradation	   2-62
2.6  Conclusions	   2-62

3 .    WINDOW DETECTION VIA PIEZOCONE SOUNDING	   3-1
3.1  Piezocone Operating Principles	   3-3
     3.1.1  Standard Instrument Configuration	   3-3
     3.1.2  Instrument Modification	   3-5
     3.1.3  Sounding Procedure	   3-7
     3.1.4  Data Manipulation and Output Format	   3-9
3.2  Material Identification	   3-10
     3.2.1  Point Resistance	   3-11
     3.2.2  Local Friction	   3-12
     3.2.3  Excess Pore Pressure	   3-12
     3.2.4  Relative Hydraulic Conductivity Index	   3-15
     3.2.5  Empirical Correlations	   3-17
     3.2.6  Window Identification	   3-21
            3.2.6.1  Intact Soil/Bentonite Backfill	   3-22
            3.2.6.2  Clean Granular Window	   3-25
            3.2.6.3  Slurry Filled Granular Window	   3-27
            3.2.6.4  Bentonite Support Slurry Filled
                     Window	   3-28

                               vi

-------
                   CONTENTS (continued)
3.3  Cutoff Wall Test Section	   3-29
     3.3.1  Test Section Construction	   3-30
            3.3.1.1  Excavation	   3-30
            3.3.1.2  Backfilling	   3-33
            3.3.1.3  Window Emplacement	   3-34
     3.3.2  Test Section Window Verification	   3-37
            3.3.2.1  High Density Clean Granular Window...   3-38
            3.3.2.2  Low Density Clean Granular Window....   3-40
            3.3.2.3  Slurry Filled Granular Window	   3-40
            3.3.2.4  Support Slurry Filled Window	   3-40
     3.3.3  Test Section Soundings	   3-42
            3.3.3.1  Intact Backfill Analysis	   3-53
            3.3.3.2  High Density Clean Granular Window...   3-58
            3.3.3.3  Low Density Clean Granular Window....   3-61
            3.3.3.4  Slurry Filled Granular Window	   3-65
            3.3.3.5  Support Slurry Filled Window	   3-69
     3.3.4  Window Identification Guidelines	   3-69
            3.3.4.1  High Density Clean Granular Window...   3-70
            3.3.4.2  Low Density Clean Granular Window....   3-70
            3.3.4.3  Slurry Filled Granular Window	   3-71
            3.3.4.4  Support Slurry Filled Window	   3-71
3 . 4  Containment Wall Soundings	   3-71
     3.4.1  Intact Backfill; Sounding GZ-13	   3-73
     3.4.2  Potential Window Locations, GZ-13	   3-76
3 . 5  Window Verification	   3-81
     3.5.1  Sample Classification	   3-82
            3.5.1.1  Boring GZA-13, 43 to 48 Feet	   3-83
            3.5.1.2  Boring TBF-lA, 39 to 46 Feet	   3-84
            3.5.1.3  Boring SU-7, 30.5 to 35.5 Feet,
                     45.5 to 48 Feet, and 49.5 to
                     52.0 Feet	   3-84
            3.5.1.4  Boring SU-4, 21 to 26 Feet	   3-85
     3.5.2  Sample Hydraulic Conductivity Testing	   3-86
     3.5.3  Containment Wall Homogeneity	   3-86
3.6  Conclusions	   3-87

4.    EVALUATION OF CONTAINMENT LEAKAGE	   4-1
4 .1  Bedrock Pumping Test	   4-2
     4.1.1  Pumping Well Location and Installation	   4-3
     4.1.2  Recharge Trenches	   4-5
     4.1.3  Monitoring Points	   4-7
            4.1.3.1  Existing Points	   4-7
            4.1.3.2  New Installations	   4-9
     4.1.4  Execution of Pump Test	   4-10
            4.1.4.1  General Conditions	   4-10
            4.1.4.2  Data Discussion	   4-13
     4.1.5  Analysis	   4-18
     4.1.6  Conclusions	   4-26

                               vii

-------
                   CONTENTS (continued)
4.2  Cutoff Wall Hydraulic Efficiency	  4-27
     4.2.1  Test Constraints	  4-28
     4.2.2  Reference Data Set	  4-29
     4.2.3  Numerical Methodology	  4-33
            4.2.3.1  Model Description	  4-34
            4.2.3.2  Model Calibration	  4-37
     4.2.4  Sensitivity Analysis	  4-39
     4.2.5  Cutoff Wall Efficiency	  4-47
     4.2.6  Summary	  4-49
4.3  Groundwater Quality Monitoring	  4-50
     4.3.1  Location and Installation of Groundwater
            Monitoring Wells	  4-50
     4.3.2  Sampling and Analysis	  4-52
            4.3.2.1  Sampling of Monitoring Points	  4-52
            4.3.2.2  Analysis of Groundwater Samples	  4-52
     4.3.3  Results of Groundwater Quality Monitoring	  4-53
            4.3.3.1  Selection of Pertinent Groundwater
                     Monitoring Points	  4-53
            4.3.3.2  Selection of an Indicator VOC
                     Compound	  4-55
            4.3.3.3  Data Discussion	  4-57
            4.3.3.4  Contaminant Degradation of the
                     Cutoff Wall	  4-61
4.4  Conclusions	  4-64

5.   CONCLUSIONS	  5-1

REFERENCES	  6-1

APPENDICES                                                  7-1

     A.  API FIXED-RING PROCEDURE	  7-1
     B.  METHYLENE BLUE TEST PROCEDURE	  8-1
     C.  GEOPHYSICAL METHODS FOR WINDOW DETECTION	  9-1
                              vill

-------
                         LIST OF FIGURES


Number                                                       Page

 2-1     API Apparatus for Hydraulic Conductivity
           Testing	    2-5

 2-2     Hydraulic Conductivity:  API vs. Triaxial
           (Remixed)	    2-11

 2-3     Triaxial Hydraulic Conductivity Results:
           "Undisturbed" vs. "Remixed" Samples	    2-16

 2-4     Methylene Blue Test Results:  Bentonite in
           Distilled Water	    2-22

 2-5     Methylene Blue Test Results:  Bentonite in
           Ottawa Sand/Distilled Water	    2-24

 2-6     Methylene Blue Test Results:  Bentonite in
           Contaminated Water	    2-26

 2-7     Methylene Blue Test Results:  Bentonite in
           Borrow/Trench Spoil/Distilled Water	    2-30

 2-8     Hydraulic Conductivity vs.  Time - Bentonite
           Content vs. Time	    2-40

 2-9     Hydraulic Conductivity vs.  Station - Bentonite
           Content vs. Station	    2-42

 2-10    Apparent Zones of Backfill  with Hydraulic
           Conductivity Greater than 1 x 10-7 cm/sec	    2-49

 3-1     Schematic of  Piezocone Instrument	    3-4

 3-2     Schematic of  Permeameter	    3-6

 3-3     Permeameter Pressuri?ation/Flow Measurement
           System	    3-8

 3-4     Excess Pore Pressure Dissipation (Wissa,  1975)...    3-16

 3-5     Material Identification-Friction Ratio	    3-18

 3-6     Material Identification-Friction Ratio	    3-19

 3-7     Material Identification-Excess Pore Pressure	    3-20

                               ix

-------
                  LIST OF FIGURES (continued)








3-8     Relative Piezocone Response	    3-23



3-9     Location Plan	    3-32



3-10    Test Section Construction Profile	    3-35



3-11    Post-Construction Test Section Profile	    3-39



3-12    Piezocone Test—Sounding No.  GZl	    3-43



3-13    Piezocone Test—Sounding No.  GZ2	    3-44




3-14    Piezocone Test—Sounding No.  GZ3	    3-45



3-15    Piezocone Test—Sounding No.  GZ4	    3-46



3-16    Piezocone Test—Sounding No.  GZ5	    3-47



3-17    Piezocone Test—Sounding No.  GZ6	    3-48



3-18    Piezocone Test—Sounding No.  GZ7	    3-49



3-19    Piezocone Test—Sounding No.  GZ8	    3-50



3-20    Piezocone Test—Sounding No.  GZ9	    3-51



3-21    Piezocone Test—Sounding No.  GZlO	    3-52



3-22a   Piezocone Test—Sounding No.  GZ13	    3-74



3-22b   Piezocone Test—Sounding No.  GZ13	    3-75



4-1     Pumping Test Monitoring Network	    4-4



4-2     Pumping Well Installation	    4-6



4-3     Typical Existing Multilevel Installation	    4-8



4-4     Typical Pumping Test Multilevel Installation	    4-11



4-5     PT-2 Time-Drawdown Curve	    4-14



4-6     M-14 Time-Drawdown Curve	    4-15



4-7     M-3-4/M-3-5 Time-Drawdown Curve	    4-17



4-8     Measured Bedrock Drawdown Contours	    4-19

-------
LIST OF FIGURES  (continued)
4-9
4-10
4-11
4-12
4-13
4-14

4-15
4-16
4-17
4-18
4-19
4-20
4-21

4-22
4-23

4-24a
4-24b

Pumping Test Idealized Geometry 	
Modeled Bedrock Drawdown Contours 	

Measured Water Table Contours, June, 1983 	
Vertical Head Distribution at M-10R 1 M-14,
June, 1983 	
Cutaway View of Numerical Model 	
Plan View of Top Layer of Model 	
Jan. 82 Scenario Calibration 	

Oct. 83 Scenario Calibration 	
Sept. 85 Scenario Calibration 	
Modeled Vertical Head Distributions for
Different Wall Conductivities 	
Location of Groundwater Monitoring Points 	
Location of Selected Groundwater Monitoring
Points 	
Variations in Contaminant Distribution 	
Variations in Contaminant Distribution 	
4-20
4-21
4-24
4-25
4-30

4-32
4-35
4-36
4-40
4-41
4-42
4-43

4-45
4-51

4-56
4-58
4-59
            XI

-------
                         LIST OF TABLES


Number                                                       Page

 2-1     Results of Hydraulic Conductivity Tests in
            API Fixed-Ring Apparatus:   Precision
            Series	   2-7

 2-2     Hydraulic Conductivity Testing:   API Fixed-
            Ring Vs. Triaxial (Remixed)	   2-10

 2-3     Effect of Varying Gradient in API Fixed-
            Ring Test	   2-13

 2-4     Triaxial Hydraulic Conductivity:  "Undisturbed"
            vs. "Remixed" Samples	   2-15

 2-5     Methylene Blue Test Results On-Site (Trench
            Spoil)	   2-28

 2-6     Methylene Blue Test Results Off-Site Borrow	   2-29

 2-7     Correlation Coefficients - Hydraulic Conductivity
            vs. Gradation Parameters	   2-36

 2-8     Hydraulic Conductivity:  "Undisturbed" vs.
            "Remixed" Samples	   2-45

 3-1     Support Slurry QC Data	   3-31

 3-2     Soil/Bentonite Backfill QC Data	   3-33

 3-3     Intact Backfill	   3-54

 3-4     Relative Hydraulic Conductivity Index	   3-55

 3-5     High Density Clean Granular Window	   3-59

 3-6     Low Density Clean Granular Window	   3-62

 3-7     Slurry Filled Granular Window	   3-66

 4-1     Daily Precipitation During Pumping Test (9/85)...   4-13

 4-2     Stress Scenarios and Simulation Fluxes	   4-38

 4-3     Calibration Deviation  Statistics	   4-39
                               xn

-------
                  LIST OF TABLES (continued)



4-4     Modeled Outward Fluxes	    4-48

4-5     Sensitivity Run Fluxes	    4-49

4-6     Concentrations of Tetrahydrofuran in Parts
           Per Million	    4-57
                             XHL

-------
                       ACKNOWLEDGEMENTS
     This document was prepared  by Goldberg-Zoino &  Associates,
Inc.  in partial  fulfillment of contract No. CR811130-01, which
was  funded under  a cooperative  agreement between  the New
Hampshire Water  Supply and Pollutant Control Commission and the
U.S.  EPA's  Hazardous Waste Engineering Research  Laboratory.  The
state of New Hampshire's project officer was Michael Donahue with
major  input from  Michael Sills.  The EPA project officer was
Stephen James.   Initial input was provided by Dr. Walter Grube
and  Jon  Herrmann,  also  of  the U.S.  EPA's Hazardous  Waste
Engineering  Research Laboratory.

     The Principal-in-Charge  of  the project for  Goldberg-Zoino &
Associates, Inc. was John Ayres; Matthew Barvenik was Project
Manager  and principal author.  Other GZA contributing authors
included  William Badge,  David Brown,  Thomas Kern,  and  Brian
Dorwart.

     The  following  individuals  provided direct input to the
project via  laboratory work, field observation,  data analysis,
etc.,  during the  design  and construction of  the Gilson Road
cutoff wall  and/or during execution  of the project:
     Michael Powers
     Charles Lindberg
     Donald Schulze
     Katrina Grundstrom
     John Forde
     Tim Cady
     Paul Hertzlier
     Ralph Wickson
     Bob Ostrofsky
     Dan Tiltgis

     Joe Lewis
     James Handly
GZA
GZA
GZA
GZA
GZA
GZA
State of New Hampshire
State of New Hampshire
State of New Hampshire
Case International
(now with Recosol, Tnc,
Case International
James Handly Company
                              xiv

-------
                          SECTION 1

                         INTRODUCTION
     The work performed under this contract was  funded  under a
cooperative agreement between the New Hampshire  Water Supply and
Pollution Control Commission  and  the U.S.  EPA Hazardous Waste
Engineering Research Laboratory.   As a cooperatively  funded
project,  two separate  but complementary  objectives  were
established.  The first,  and primary,  objective was to evaluate
the design, construction,  operation, and  monitoring of the Gilson
Road National Priority  List  site  remediation.  As  such,  this
information enhanced the overall effectiveness  of the passive and
active barrier containment  system.   The second  objective was to
conduct an evaluation which would lead to a better understanding
of containment technologies  in  general.  This knowledge could
then  be  incorporated  into  the  design and  construction of
hazardous  waste remediation actions on other NPL sites.
1.1  Overview


     Soil/bentonite backfilled  cutoff  walls have successfully
been used  as an adjunct to  pumping for excavation dewatering and
general groundwater control for over forty years.  The procedure
of adding  bentonite to excavated in-situ soil and then placing
the  low  hydraulic  conductivity  mixture  back in  the
slurry-supported trench to  form a barrier was initially used in
Europe and then in the United States.   Specifications governing
this work  typically fell under the dewatering  section of contract
construction documents and, as  such, were performance oriented.
In many cases, success was judged solely on  the ability of the
barrier to limit  fluid flux to  quantities that could reasonably
be pumped.  Due to the magnitude of the overall construction
effort typically involved, the addition of pumping to remove
leakage from the  excavation with off-site disposal  was  often
considered insignificant.

     More  recently,  soil/bentonite  (S/B)  cutoff  technology has
been  used as part  of  remedial actions  at United States
Environmental Protection Agency National Priority List (NPL)
sites, as well as private industrial  sites. (JRB, 1984).  For
these more critical applications,  leakage must be reduced to a


                            1-1

-------
far greater extent than typically  associated  with construction
dewatering.

     The successful construction of  a hazardous waste cutoff wall
containment is  largely  dependent  on the  quality of  the
contractor's workmanship.  As  such,  specifications must remain
generally performance oriented  with the  primary requirement of
attaining  a long-term hydraulic  conductivity less than  some
specified value;  typically  less than 1 x 10~7  cm/sec for waste
containment.   However, in  recognition  of  the difficulties
involved in performance verification and the consequences of
detecting substandard  construction only after wall completion,
contract documents must also  include minimum  design standards.
These center around a  number of  design  and construction issues
such as  minimum bentonite and fines content in  the backfill,  for
example (Ayres,  1983).  This allows quality control (QC) testing
to be executed in the  field  during construction as a check on
attainment of the minimum  standards specified.  "Learning Curve"
problems can therefore be  detected and  addressed early in the
construction process before they become  pervasive and jeopardize
the overall effectiveness of the barrier.  Adequate specification
and quality control of  such  minimum design standards requires
intimate knowledge of  the  technology underlying cutoff  wall
construction as  tempered with  practical empiricism gained via
construction experience.

     As  is often the case with initial  technology transfer,
cutoff walls have been  designed and specified  by professionals
associated with the hazardous waste field,  rather than those
experienced in cutoff wall  design/construction.  Environmental
professionals, although familiar with the hydrogeologic
constraints of the application,  generally lack expertise  and
experience in cutoff wall  specific technology.  Specifications
have therefore been strictly performance based in some cases,
thus allowing contractors  to execute  the  work  in  a manner
consistent with past dewatering practices.   Unfortunately,  fluid
flux rates associated  with standard construction practices for
dewatering purposes are  unacceptable with respect to hazardous
waste containment.  As a result, some of  these containments have
not performed up to expectation.   Cutoff  walls  have thus fallen
from favor with  respect to hazardous waste remediation due to
poor implementation rather than limitations  inherent  in  the
technology.

     Use of procedures, such as field QC,  to prevent cutoff wall
deficiencies before they occur is not only highly desirable but
necessary for hazardous waste containment applications.   However,
it must  also be recognized  that the specifications under which
these walls are  constructed  are principally  performance based.
The performance clauses  incorporated in  the specifications can
only be meaningful to  the  extent that equipment and methods are

                            1-2

-------
available  to enforce them, should  post-construction  verification
become  necessary.   A demonstrated capability  for  performance
verification also instills added incentive to achieve the highest
quality of  workmanship possible during construction.   As  such,
instrumentation  and procedures should be developed to identify
unsatisfactory  zones in  completed  cutoff walls  as well  as
hydraulically test their post-construction performance.


1.2  Background


     The Gilson Road uncontrolled hazardous waste  site in Nashua,
New Hampshire was  the subject of  the  first site  remediation
cooperatively funded under EPA's Superfund program.  Clandestine
dumping  of  toxic volatile organic compounds into an  abandoned
gravel  pit  resulted  in  a contaminant plume which degraded
residential air quality as the contaminants volatilized  following
recharge to  a local stream and threatened downstream municipal
drinking water supplies (Barvenik, 1986).


     1.2.1   Site Description and  Geology


     The site is  underlain by glacial soils  consisting  of
primarily granular ice-contact and glacial lake  deposits.   These
include  fine to  coarse sands and gravels, with  layers and lenses
of silts and  silty fine sands.  Below the stratified drift is a
granular basal till.  This, in turn, is underlain  by  a moderately
fractured  schist bedrock,  with a weathered, highly fractured
upper zone  (Koteff,   1973).

     The sand and  sand/gravel deposits  exhibit  an average
hydraulic  conductivity of  10~2  cm/sec  based  on pumping test
results.   However, these  deposits  vary  over a  range from
10~5 cm/sec for the  silts  and silty fine sands to an  estimated
10-1  cm/sec  for open work gravel  seams found in the  esker
deposits.   The glacial till  deposits are typically  less  permeable
(10~5 cm/sec)  than  the  average values  for  the overlying
stratified drift.   However,  the till  is  generally  thin and
discontinuous in nature,  thus constituting a  relatively imperfect
aquitard.   The hydraulic conductivity of the upper  50  feet of the
bedrock was  estimated to  range between 10~5  an
-------
     1.2.2  Remedial  Measures


     Final  designed remedation  for the  site  consisted  of
complementary active and passive physical  barriers  to control
groundwater flow, and treatment of the  captured contaminant plume.
This interactive system was  adopted  because neither a purely
passive barrier nor  a purely active  barrier alone could eliminate
off-site contaminant migration.  A cutoff  wall to the top  of
bedrock  and a synthetic cap form  the passive  elements of the
system.  The cutoff wall was 4,000 feet in length, up to  110  feet
deep,  and  completely  encompassed the entire 20 acre  site.
Extending the passive barrier through the fractured  portion  of
the bedrock was evaluated during initial design  phases.   This
could be accomplished by  excavating through  the bedrock  or
grouting the rock fractures.  Albeit feasible, neither method was
found to be a cost-efficient  solution for limiting contaminant
flux through the bottom of the containment.

     The  active component  of the total containment vessel is a
hydrodynamic isolation system which accounts for the inadequacies
of the bedrock as an aquiclude.  This system redistributes the
groundwater within  the containment area and eliminates  head
differences across the  cutoff  wall to achieve a  no leakage
condition (zero gradient).  The groundwater  extraction/recharge
associated  with the hydrodynamic isolation  also  allows for
treatment of  the recirculated water,  resulting in  aquifer
restoration.   The  restoration  process requires a number  of
flushing cycles for complete contaminant removal.

     A  purely active system  of  plume control via hydrodynamic
extraction/recharge was also found to be unacceptable  during the
feasibility study  due  to the  heterogeneity  of the  aquifer.
Groundwater extraction at a  rate necessary  to  eliminate  plume
migration would necessarily  entail the  pumping of significant
volumes of  clean  water  from regions  of high hydraulic
conductivity outside the plume  and nearby surface waters.  This
dilution  of the plume at the  point  of   recharge  and the
concomitant spreading quickly  results  in  a contaminant  plume
width greater than the extraction  system's radius  of  influence.
Even  in  a  homogeneous aquifer,  contaminants can still escape
active containment if the recharge  point does not lie  directly
upstream  of the extraction well  (i.e.,  along  a flow line).
Finally, even with a  perfect  recirculation  system, contaminant
dispersion across the flow lines at  the edge of the containment
results in a further  loss of contaminant mass  from the  system.

     Although the  cutoff  wall  provides enhanced  hydraulic
control, no practical hydrodynamic isolation system incorporating
a finite number of extraction and recharge points,  can completely

                            1-4

-------
eliminate  all  gradients across  the physical barrier.  Therefore/
to preclude off-site contaminant migration,  the system  is
operated with  a  conservative bias by forcing an  inward gradient
everywhere along the cutoff wall.  The required  net recharge
deficit, relative to extraction, necessitates an  external purge
stream (discharged outside of the containment).  The purge  stream
volume is,  in  part,  a function of the hydraulic  conductivity  of
the containment perimeter (cutoff wall).  To attain an extremely
high water quality  in the purge stream, as mandated  for off-site
disposal  at this  CERCLA site, -this portion of  the pumpage must
undergo  additional treatment steps as compared to the  total
recirculation flow.  Therefore, the hydraulic  efficiency  of the
cutoff wall directly affects purge stream treatment  costs, which
are a considerable  fraction of the  two  million dollar/year
overall operation and maintenance cost of the on-site treatment
f ac i 1 i ty.


     1.2.3   Design and Construction


     In recognition of  the  importance of  the cutoff wall to the
successful  operation of the hydrodynamic isolation/recirculation
system,  a  rigorous  design phase was implemented including  an
advanced soil/bentonite backfill design methodology (Schulze,
1984) and  development of new equipment and procedures for quality
control field  testing.   This work was  incorporated into the
specifications  as  minimum design standards  keyed  to  specific
aspects of  the  actual construction process (Ayres,  1983).  The
Gilson Road project  therefore represents perhaps  the first case
where the  level  of  cutoff  wall design,  specification, and
construction  quality control  (Q/C)  were  commensurate with
application to  hazardous waste containment.  As such, this site
was considered ideal for use in evaluation of the  suitability  of
soil/bentonite cutoff  wall technology  as part of  an  overall
containment strategy for hazardous waste remediation.


1.3  Report Organization


     The  scope  of this work was separated into  three major phases.
The first  phase  (Section 2)  encompassed evaluation of two new
testing techniques used  for quality control  during construction
of the Gilson Road containment.   The methylene  blue  titration and
the API fixed  ring hydraulic conductivity tests were employed  to
determine the bentonite content and hydraulic conductivity of the
intact soil/bentonite  cutoff wall backfill,   respectively.  The
project  described  herein  demonstrated the  applicability,
accuracy,  precision,  and practicality of these tests for quality
control.

                             1-5

-------
     The  second phase of this project (Section 3) was directed at
investigation of the feasibility of piezocone instrumentation for
verification of cutoff wall backfill homogeneity.  This  entailed
evaluation of piezocone response characteristics with respect to
intact backfill versus non-backfill materials in a specially
constructed full scale  test  section.   Response signatures were
then used  to evaluate  the homogeneity of  the Gilson road
containment wall followed by verification  via direct sampling.

     The primary  objective  of  third phase of the  project
(Section  4) was to hydraulically stress the containment wall to
assess  its  bulk hydraulic  conductivity  and thus its overall
effectiveness with respect  to hazardous waste  containment.  This
work  was supplemented with documentation  of the spacial and
temporal  variation in contaminant concentrations as they reflect
the behavior of the  hydrologic system in response to containment
wall installation.

     Each of  the  three  above  described major sections are
organized to be independent, self-contained  documents.  The
conclusions derived  from  the work are therefore presented after
each  individual section.  The  report concludes with  a  final
section  summarizing  the general  conclusions which can  be drawn
from this project.
                             1-6

-------
                           SECTION 2

           FIELD QUALITY CONTROL TESTING PROCEDURES
     Quality control testing of  soil/bentonite backfill  during
cutoff  wall  construction is  essential from two perspectives:  1)
it allows an on-going  evaluation of construction procedures; and
2) test  results  form the basis of  evaluating  future  wall
performance.  QC  testing provides a means of assessing whether
minimum design standards have been met for a discrete number of
representative backfill samples obtained prior to placement in
the trench.  From this set of  data, future performance of the
wall as a whole is  extrapolated.  While recognizing that wall
performance may be  significantly impaired by anomalies in the
backfill not revealed  by the QC  data, QC testing imposes control
over a construction procedure  for which there are  few visual
indicators of quality.   Emphasis of  QC testing during
construction thus allows for the timely and efficient correction
of deficiencies.   Over   the  long-term,  QC testing during
construction also reduces the need for post-construction
verification of backfill parameters—which is costly—and the
reliance on post-construction  "leakage  data"--which can be
circumstantial and  subject to  varied interpretation.  Moreover,
even if deficiencies can be  detected  in the  completed wall,  their
correction  is generally neither simple nor inexpensive.

     An effective QC program involves frequent  testing of primary
backfill parameters,  including unit weight, slump, gradation,
fines content, bentonite content, and hydraulic conductivity.
The real time data  obtained through field QC testing  are made
available  to the  contractor to allow modification of component
proportioning and mixing effort  at the outset of the project to
achieve specified requirements.   Standard methods for determining
unit weight, slump,  fines  content,  and overall gradation are
easily executed in  the field within a time period commensurate
with real time QC of field operations (typically  within one day).
However, long periods  of  time  are  required for triaxial testing
for hydraulic conductivity  (greater  than one week) and  standard
hydrometer  testing  of  bentonite  content (typically three to four
days).  In  recognition of these limitations, new S/B backfill QC
techniques, including  API  fixed-ring permeation, and methylene
blue hitration, were utilized  on the Gilson Road project for
bentonite  content  and hydraulic conductivity determinations,


                             2-1

-------
respectively.   This work  demonstrated the applicability  and
practicality of these new methods for field control.

     The first phase of the project,  presented  in this chapter,
focused on the refinement  of  these two new QC procedures  and
evaluation of their precision and accuracy using  samples obtained
from the Gilson Road site (Sections 2.1 and 2.2).  Guidelines  for
field use were developed.   To better assess the role of gradation
parameters on hydraulic conductivity, a statistical evaluation of
the  QC  data obtained  from the Gilson Road project was also
performed  (Section  2.3).  The  QC data obtained  from  the  Gilson
Road project were  then  reviewed to assess the conformance of  the
completed wall to project specifications (Section  2.4).  Finally,
quality control guidelines for cutoff wall construction were
developed, encompassing trench excavation and backfill placement
as well  as backfill preparation  (Section 2.5).


2.1  Evaluation of Backfill  Hydraulic Conductivity Using the
     Fixed-Ring Apparatus


     The primary hydrologic feature  of  a cutoff wall is its  low
hydraulic conductivity and  thus high impedance with  respect to
groundwater  flow.  This characteristic  results  in  the
effectiveness of cutoff walls as physical barriers to contaminant
migration.  In recognition of  the importance of the hydraulic
conductivity actually attained  during cutoff construction, this
key parameter is subject to a high degree of specification in
project contract documents.   For most  hazardous  waste
containments, an upper  bound  hydraulic conductivity  of 1 x 10~7
cm/sec is typically required, as was the case for  the Gilson Road
site.

     A number of criteria must be met during  construction to
achieve  a soil/bentonite cutoff wall with the specified hydraulic
conductivity.  The types and  percentages of backfill components
have a large effect on hydraulic conductivity and are typically
determined via laboratory  testing undertaken during the design
phase (Schulze, 1984).  These data are generally reflected  in  the
project specifications as minimum design standards.   (For
example, the Gilson Road specifications  required a  minimum of
30 percent fines and 5  percent minimum bentonite content for  the
backfill).  Even if these minimum criteria  are met, however,  the
proper  hydraulic  conductivity is  not guaranteed  due  to  the
importance of uniform  mixing of  the backfill  components,
particularly with respect to dispersion of  the  bentonite.
Inasmuch as proper proportioning of  backfill  components  and
sufficient mixing  effort are primarily related to the quality of
workmanship on the part of the contractor, the  required hydraulic


                             2-2

-------
conductivity for the cutoff appears  as a  performance
specification in the project documents.

     To have any  impact as  a specification  requirement,
performance criteria should be subject to immediate  verification.
However, in  the strictest sense, the actual long-term hydraulic
conductivity of the  cutoff wall can only be evaluated through
post-construction  monitoring.   This is a costly endeavor due to
the requirement for closely-spaced multilevel piezometric  head
and groundwater quality  monitoring installations  located around
the containment perimeter, both  on the outside and  inside  of  the
wall.  In all but  the simplest  cases, the data thus obtained also
require interpretational  techniques based on three-dimensional
computer  simulation.

     Beyond  the high cost,  the major drawback associated  with
post-construction  monitoring  is that  zones of  unacceptable
hydraulic conductivity  are detected only after it is too late for
prevention and/or  cost-efficient repair.   Therefore,  while
performance  criteria are still necessary for specification of
hydraulic conductivity, a  more cost-effective and  timely
procedure is  required  for  prediction, and thus construction
control,  of the hydraulic conductivity finally achieved  by  the
barrier.   This  function can  be fulfilled via  QC  testing as
demonstrated  on the Gilson Road  project.

     Though  not an  absolute  determinant  of the  long term,
in-place  performance  of  the overall  cutoff,  hydraulic
conductivity testing of  the  backfill prior  to placement in the
trench provides a good indicator of the eventual intact hydraulic
conductivity  of  the barrier.  Standard triaxial testing  has
therefore been  routinely employed to provide  these data despite
its  limitations.  Due to the  sophistication of  the equipment
required,  the tests are costly  (typically greater than  several
hundred dollars/test)  and cannot easily be performed in the field.
As such, a statistically insignificant number  of  tests  are
generally undertaken  (normally not more  than  one test  per
multiple thousands of  cubic  yards of  backfill)  and the data
become available only  after  several weeks have elapsed since the
samples were  obtained.  This procedure suffers from the syndrome
of "too little and too late" with respect  to influence  on  the
eventual  performance of  the cutoff barrier.   Hence, it can  only
be viewed as  a  token post-construction verification  effort.

     An alternate  procedure  for obtaining hydraulic conductivity
data employs  fixed-ring  equipment.  Although,  in general,  not as
accurate as  triaxial testing,  fixed-ring tests yield acceptable
data  if  the  correct  procedures are followed to limit boundary
leakage and  the samples are conformal and initially saturated, or
nearly so (Schulze, 1984).


                             2-3

-------
     Fixed-ring  equipment was  used  to provide hydraulic
conductivity data during construction  of  the Gilson  Road cutoff
wall.  This inexpensive, easily-operated equipment allowed field
testing of numerous samples prior to permanent  incorporation of
the  backfill into  the  cutoff.   The one day  availability of
hydraulic conductivity  data allowed  real-time quality control of
the  construction  process.  In  light of the high degree of
usefulness and practicality of the API  fixed-ring hydraulic
conductivity testing as shown on the  Gilson  Road project, a
testing program was undertaken to:

     0   Assess the precision of  the test

     0   Assess the accuracy of of  the  test.

     0   Refine  and  standardize  the  test  procedure  for
        incorporation in general  guidelines for  QC testing of
        S/B cutoff walls.

     The  test program and  test  results  are  described in the
following subsections.


     2.1.1  API Fixed-Ring Test


     Various  equipment  configurations based on  fixed-ring
confinement of a  test  sample for evaluation of   hydraulic
conductivity have been in use for many  years  (U.S.  Army Corps
manual,  1970 and Lambe, 1951).  In most cases,  however,  the
equipment  is meant  for laboratory  use  and  not designed to
withstand the "environment" associated  with field testing.

     In  an effort to standardize procedures  around equipment
which would survive repeated field  use and also  be  readily
obtainable, the conventional American Petroleum Institute  (API)
filter press  was adopted for use as a  fixed-ring  permeameter
(see Figure 2-1).  As a filter press, this equipment is already
routinely used on cutoff wall projects to  test  the  filter cake
forming  capacity  of bentonite slurries used  for  trench
stabilization.

     To  allow accurate  testing  of  S/B backfill  samples at
stresses commensurate with in-situ  conditions, a  number  of minor
equipment and procedural modifications  are required, including:

     0    The pressure system  should be  modified  to  accept a
        regulator for each cell along with a  gage  which has a
        range of 1 to  15 psi for application of  low pressure.


                            2-4

-------
FIG.  2-1  API.  APPARATUS  FOR HYDRAULIC CONDUCTIVITY TESTING
                                                                  DIAL GAUGE
                                                           BASE CAP

                                                           STEEL MESH SCREEN
                                                           SUPPORT ROD


                                                           GRADUATED CYLINDER
                                                                      GAS LINE


                                                                        REGULATOR
                                                                        COMPRESSED
                                                                        AIR SOURCE
   (APPARATUS AS SHOWN MANUFACTURED BY BAROID)
                                    2-5

-------
     0    Bentonite "paste" should be  applied to  the inside
         diameter of the rigid wall  and trimmed to a  uniform
         thickness of  1/32 inch using a trimming jig.  This will
         limit boundary flux  along  the backfi11-rigid  wall
         interface.

     0    Test samples should be fabricated on a thin  bed of sand
         underlain by a porous screen  to  prevent plugging of the
         bottom outlet port.

     0    The test samples should be  sieved through a standard 1/2
         mesh prior to placement  in the cell to limit the maximum
         particle size to less than 1/6 of the cell diameter.

     In basic terms, API hydraulic  conductivity testing  involves
placing a sample  in the cell/ covering  it with water,  and forcing
the  water through  the  sample  using  pneumatic pressure.   Once
consolidation of  the sample  is complete,  the steady  state
hydraulic conductivity  is  computed  based on standard  Darcy's Law
relationships assuming 100 percent saturation.   For typical S/B
backfill samples,  approximate  values of hydraulic conductivity
can be  obtained in several hours  and  final values in less than 24
hours.   As such,  the  procedure is  ideal for  real  time quality
control of the construction  process.

     A  detailed description of  the  standardized test procedure,
which directly reflects the  results of  efforts performed  for this
project,  is presented in Appendix A.


     2.1.2  Testing Program


     The overall program objective  was  to determine the  inherent
reliability of  the API  fixed-ring test  for measuring  the
hydraulic conductivity of S/B backfill samples.  This  information
could  then be used  to evaluate the  validity of the  QC  data
obtained during  construction of the Gilson Road cutoff  and, from
a more  general standpoint, form  a basis for standardization of QC
procedures for use  on other projects.   More  specifically, the
project was  structured to first evaluate  the precision of the
test and then assess test accuracy.   These two phases  of  the work
are described in  the following subsections.


          2.1.2.1  API Fixed-Ring Test  Precision


     The precision  testing  was  directed towards determining if
equipment and procedures as simple  as the API-fixed ring-based QC


                             2-6

-------
testing performed on  the Gilson Road
repeatable  hydraulic conductivity values.
       project would  provide
     Five batches  of  the Gilson Road  backfill were selected  from
record samples obtained during  construction.   Selection
emphasized encompassing  the full  range  of  gradations and
hydraulic conductivities encountered during  construction of the
actual cutoff  wall.   After thorough  remixing in the laboratory,
three  "identical"  aliquots of each  sample  were tested at a
gradient of 40 (driving pressure of  3 psi - all  pressures
reported  as  gage).  The results are  presented in Table 2-1.
                           TABLE 2-1

    RESULTS OF  HYDRAULIC CONDUCTIVITY  TESTS IN API FIXED-RING
                 APPARATUS:  PRECISION  SERIES
   Sample
Hydraulic  Conductivity cm/sec
  (3 splits  of each sample)
Station 0+50
Station 7+75
Station 14+75
Station 20+25
Station 35+00
        0.48 x 10-7
        0.38 x 10-7
        0.46 x 10-7

        4.02 x 10-7
        4.02 x 10-7
        4.44 x 10-7

        0.80 x 10-7
        1.86 x 10-7
        0.79 x 10-7

        0.63 x 10-7
        0.25 x 10-7
        0.25 x 10-7

        0.69 x 10-7
        0.28 x 10-7
        0.33 x 10-7
     The data  indicate  a worst case precision  of +57 percent
within one  standard deviation of  the mean value  for any group of
three tests.  Although this initially appears as a large degree
                             2-7

-------
of scatter, it is actually quite small  when compared to the  five
orders of magnitude  (100,000 times)  reduction in hydraulic
conductivity of the  initial in-situ soils.  Further inspection of
the data  also reveals that in all five groups  of tests,  at least
two of the three tests  in each group agreed to ^10 percent within
one standard deviation of the mean.   Hence,  some of the  scatter
reflected in the worst case precision of  ±51 percent may be
attributable to variations  in aliquots  of the same sample  that
were not eliminated  by mixing.   It must be  recognized that the
degree  to which the precision of a  test  procedure  can be
established is highly dependent on  how  identical  the  test
specimens are prepared.  This  is  problematic  for API fixed-ring
hydraulic conductivity testing  in  that a single specimen cannot
be set up more than  once.  Therefore,  multiple specimens  were
required to evaluate  the  degree of variability in the entire
procedure, from set-up  through permeation.   Unfortunately, the
coarseness of granular  based backfills such as used on the Gilson
Road project can result  in a somewhat heterogeneous sample  from
which  the individual  aliquots are taken  for the comparison
testing.   Therefore,  uniform mixing,  to  the  extent practical in
the  laboratory, was emphasized during sample  preparation.
However,  it is likely  that some degree of  heterogeneity still
existed  among the comparison samples.

     This hypothesis is supported by field data obtained during
subsequent QC testing for other cutoff walls  utilizing primarily
clayey mixes.  For  these finer grained backfills, the probability
of obtaining identical  samples  is significantly enhanced.   API
fixed-ring tests  run  on  "identical"  samples of clayey mixes
yielded  closer precision than for the Gilson Road backfill.


          2.1.2.2 API Fixed-Ring Test Accuracy


     The accuracy of the API fixed-ring  test  was  evaluated via
comparison  with triaxial  tests.   Inasmuch  as the  value of
hydraulic conductivity attributed to a backfill specimen is
dependent on the method of measurement,  determination of the
accuracy  of a specific  testing procedure suffers from the lack of
an absolute value of  hydraulic conductivity for comparison.   Even
triaxial  testing, which is one  of  the  most  well developed and
flexible  testing  techniques for  determining  hydraulic
conductivity, can yield a  wide  range of  values for the same S/B
backfill sample.  This variability stems  primarily from the  lack
of standardization  of  physical  testing parameters such as  state
of stress, degree of saturation,  gradient,  etc., to which the
sample is highly sensitive (Schulze, 1984).
                            2-8

-------
     The accuracy evaluations  made herein are therefore based on
"absolute"  values determined via triaxial procedures  in  which  the
physical testing  parameters were standardized  to  model in-situ
conditions  at  the  top of the cutoff wall  (upper  5  to  10  feet).
As such, these  "absolute" values of hydraulic conductivity would
be conservative  (high)  relative to those  expected  for the  same
sample  tested  under conditions simulating  greater  depths or
incomplete  saturation.  The philosophy of modeling  the worst  case
condition  of  "top of wall" recognizes the indeterminancy of the
final  vertical  location of a specific batch of  backfill
represented by a QC sample taken prior to backfill  placement.

     During construction of the Gilson  Road cutoff  wall,  ten
samples  of  the backfill were obtained specifically  for triaxial
testing.   Each  sample  was remixed to improve  uniformity  and
consistency and then split to  permit field testing in the  API
fixed-ring apparatus as part of the QC program.   In  addition,
five samples of backfill were obtained from the  completed wall
via conventional stationary-piston, tube sampling techniques for
both API fixed-ring and triaxial hydraulic  conductivity testing.
Each of these samples was remixed prior to triaxial testing and
then a  split of the triaxial sample was used for  API fixed-ring
testing.   Therefore,  to  the degree that the fifteen  samples taken
were homogeneous, the  value  of hydraulic conductivity  was
determined by both  triaxial and API fixed-ring procedures on
"identical"  specimens.   These data are presented on Figure  2-2
and are  summarized in  Table 2-2.
                            2-9

-------
                          TABLE 2-2


                HYDRAULIC CONDUCTIVITY TESTING:
             API FIXED-RING VS TRIAXIAL  (REMIXED)
Station          API  x  10~7 cm/sec        Triaxial x 10~7 cm/sec
0+00
1+00
1+00
3+45
3+45
4+75
9+00
11+00
12+50
16+50
20+50
24+50
28+50
32+50
36+50
0.93
0.50
0.80
1.0
0.80
0.38
2.1
0.70
0.50
0.40
0.57
0.76
1.3
0.16
0.30
1.1
1.0
0.80
4.0
1.5
0.34
3.0
0.30
0.34
0.42
0.56
0.75
0.90
0.48
0.50
     The data indicate that the API fixed-ring values match the
triaxial values to within  +66  percent in fourteen out  of the
fifteen cases, with  one case  of  the  API fixed ring value 133
percent higher than the triaxial.   This  error band  not only
encompasses the accuracy  of  the  API  fixed-ring test but also
incorporates errors  associated  with heterogeneity between
"identical"  samples and precisional errors  inherent in both the
                             2-10

-------
               TT-Z
API HYDRAULIC CONDUCTIVITY x I0-7cm./sec.
ro
 i
ro
                                                c
                                                I-
                                                o

                                                o
                                                o
                                                o
                                                c
                                                o
                                                H
                                                >
                                                -o
                                                2
                                                >
                                                X
                                                m
                                                2
                                                X
                                                m
                                                o

-------
API fixed-ring and triaxial procedures.   The error associated
with heterogenity between "identical" samples could  not be
quantified.  Precisional  error  for  API fixed-ring testing was
found to be +57 percent.  Precisional  error  for triaxial testing
was  not quantified,  but experience suggests an  error of
+50 percent.  As such,  the data indicate  a very good level of
agreement between the simple  field  API fixed-ring test  and the
more sophisticated laboratory triaxial test.

     It should be noted that the applied pressure in thirteen of
the fifteen API fixed-ring  tests described above was 10 psi.  The
other  two  tests were run at  2  psi.  Ten  psi is considered an
upper  limit for applied pressure.   A higher applied  pressure
would  result in consolidation of  the sample  to  levels not
commensurate with  "top of wall"  conditions.   As  such,
artificially low  (unconservative) values  of  hydraulic
conductivity could be  obtained.  A higher applied pressure could
also  lead  to piping  and thus  unrealistically high values of
hydraulic conductivity.

     It was  further found  that  API fixed-ring  hydraulic
conductivity did not decrease  significantly as applied pressure
was increased from 2 psi  to  10  psi.  This  trend was observed in
three of the samples cited  above  which were initially subjected
to 2 psi and  subsequently increased to 3  psi, 5 psi, 7 psi, and
10 psi  as well as in four other samples in which gradient was
varied  (refer to Table  2-3 for summary of results).  The increase
in  applied pressure  over this range appeared  to have an
insignificant effect  on  consolidation of the granular Gilson  Road
backfill (this conclusion might not be true for a more clayey
backfill in which sample consolidation would be a larger factor).
Test  results indicated  that  increasing the  pressure by
400 percent  (from 2 to  10 psi)  caused a decrease in hydraulic
conductivity of less than 50 percent.
                             2-12

-------
                           TABLE 2-3

        EFFECT OF VARYING GRADIENT IN API  FIXED-RING TEST
Station
Depth
Hydraulic  Conductivity
    x 10-7 cm/Sec

1+00
1+00
3+45
3+45
3 + 45
3 + 45
11+00

20'-22'
41'-43'
3.5'-5.5'
ll'-13'
22'-24'
32--341
9--10.51
28
0.45
2.1
1.5
0.88
0.55
1.5
3.9
41
0.58
1.4
1.4
2.0
0.78
1.0
3.1
Gradient
69
0.64
0.82
1.2
1.1
0.73
0.9
2.8
97
0.56
0.67
1.1
0.99
0.27
0.8
2.3
138
0.55
0.52
0.8
0.97
—
0.8
2.3

     2.1.3  Guidelines for Field Use of  the API Fixed-Ring Test


     Based on the data  presented herein, and the field data  from
actual cutoff  wall projects  undertaken  to date,  the  API
fixed-ring  test appears to yield reliable and accurate values  of
hydraulic conductivity.   The reliability  and accuracy  combined
with the  relative simplicity, short testing time, and low cost  of
the test make  it ideal for field  quality control.   The  test can
therefore be  used  as the primary field measure  (production test)
of backfill  hydraulic conductivity provided  accuracy is  verified
for each new project.

     Verification testing  and  production testing of backfill are
described in the following subsections.  It will be seen  that the
key to  verification testing is  obtaining an API fixed-ring sample
as representative  of  the  corresponding triaxial  sample  as
possible, while the key to production testing is obtaining a
sample  as representative  of  the  in-place  wall backfill  as
possible.   This difference reflects the different objectives  of
                             2-13

-------
the two series of  tests:   verification testing validates  test
accuracy;  production testing  validates  backfill  hydraulic
conductivity.


          2.1.3.1  Verification Testing


     Verification testing  should begin during  the design phase of
a project  and continue during construction.  During  the design
phase, a limited number of  triaxial tests should be run to verify
the site specific accuracy  of  the API fixed ring procedure.   This
check between API  fixed-ring and triaxial data should be  made
after  backfill  component  selection  and proportioning  are
established.  As part of  the verification program,  the driving
pressure used for  API fixed-ring testing should be  varied  to
determine which value yields the  best API/triaxial match.
Samples selected for testing  should represent the contract design
mix (or mixes).  Backfill  samples from which aliquots will be
taken for  API/triaxial comparisons should be throughly mixed to
be as homogeneous  as  possible to yield aliquots as identical as
possible.   Splits of a poorly  mixed sample may  reveal significant
variations in gradation which will lead to different hydraulic
conductivities.  The variation in hydraulic conductivity would
then be misinterpreted as testing inaccuracy.

     This   design testing  should then be followed by triaxial
testing of  actual backfill  samples obtained during construction.
Samples selected for  testing should cover the complete range of
hydraulic  conductivities and backfill types encountered on the
project  as well as   represent the entire wall perimeter.   To
enhance  the usefulness of  triaxial  data  obtained  during
construction, samples should also be tested  as soon  as they are
taken.   Hence, the site specific validity of the API  fixed  ring
data can be established well  before the end of construction.   The
field samples from which aliquots are taken for the API/triaxial
comparisons must also be  as  homogeneous as possible.  Therefore,
additional  mixing far beyond  that actually attained in the  field
is mandatory prior to testing.


          2.1.3.2  Production  Testing


     Although  a  high degree of additional backfill mixing is
required for the API/triaxial comparison samples, mixing of  field
samples taken for QC production  testing in excess of  that
achieved during  construction may yield  unconse rvat i vely  low
values of  hydraulic  conductivity.  Hydraulic conductivity is a
function not only of the proportions in which backfill  components


                             2-14

-------
are  mixed,  but also  of the  degree to  which they are mixed.
Therefore, additional mixing of a sample  obtained for QC testing
may  improve  the degree of blending to the point where the  sample
is no  longer  representative of  the field  mix and  yields a
falsely low value of hydraulic conductivity

     Triaxial  data  from five undisturbed tube  samples obtained
from the completed wall  indicate that up  to an order of magnitude
reduction  in hydraulic  conductivity can  occur after the
undisturbed sample is mixed thoroughly and  retested.  Results are
illustrated  on Figure  2-3 and summarized in Table 2-4. In each
of the five cases, the remixed  sample yielded  a lower hydraulic
conductivity than the undisturbed  samples.   Therefore, in some
cases,  the backfill may  have been mixed uniformly in the field to
a scale  similar to  that of sample size  but not to the grain size
scale which controls hydraulic conductivity.
                           TABLE 2-4

                TRIAXIAL HYDRAULIC CONDUCTIVITY:
               "UNDISTURBED" VS "REMIXED" SAMPLES
Station
Depth
    Hydraulic Conductivity
        x 10-7 cm/sec
Undisturbed           Remixed
1+00
1+00
3+45
3 + 45
11+00
20-22
80-82
11-13
22-24
22-24
2.
10.
12.
3.
5.
1
0
0
6
0
1.0
0.8
4.0
1.5
0.3

     To obtain  the most representative  values of  hydraulic
conductivity,  samples for QC production testing  should be taken
and placed in the  test chamber with as little additional mixing
as possible while still removing air voids.  Failure  to observe
this  procedural  "detail"  can result  in  artificially  low
(unconservative) values of hydraulic  conductivity.   It also
                             2-15

-------
N)
I
                      FIG. 2-3 TRIAXIAL HYDRAULIC  CONDUCTIVITY   RESULTS
                              "UNDISTURBED" vs.  "REMIXED"  SAMPLES
                                        i.o                 10.0

                           TRIAXIAL HYDRAULIC CONDUCTIVITY x I0"7cm./sec.

                                       (REMIXED SAMPLE)

-------
follows  directly from this  discussion  that both  the API
fixed-ring and  triaxial  data  sets obtained for verification
testing do not  qualify as QC production  data.  As indicated, the
sole purpose of  these tests  is  to demonstrate the site specific
accuracy of the  API fixed-ring procedure.

     The driving pressure used  during API fixed-ring QC testing
should be  that value which,  based on the verification testing,
yields  a hydraulic conductivity closest to that derived from
triaxial  testing.  It  is emphasized  that,  for the  reasons
discussed previously, significantly higher driving pressures
should  not be used  in an effort to increase the flow per unit
time so as to make  effluent volume measurements easier.   Rather,
smaller graduated  cylinders  should be employed to increase the
reading accuracy  for the small  effluent volumes resulting from
particularly low hydraulic conductivity backfills.


2.2  Evaluation  of Backfill Bentonite Content  Using Methylene
     Blue  Titration
     The cutoff  wall at  the  Gilson  Road site was constructed
using a  backfill  consisting  of  on-site  soils,  off-site borrow,
and bentonite.  The on-site  soils were highly permeable  sands and
gravelly sands  excavated  from the trench (trench  spoil).
Off-site borrow  consisted of  a quartz  based fine sandy silt and
was mixed with  the trench spoil to  reduce its  hydraulic
conductivity.  Additional reduction of  the mix hydraulic
conductivity to design values «1 x 10~7  cm/sec) was accomplished
via bentonite addition, first as a dry powder and then as a
bentdnite/water slurry.

     For QC of backfill proportioning  and mixing  in the  field,
testing of percent  bentonite  is second in importance  only  to
measurement  of  the actual  hydraulic conductivity.   For
predominantly granular backfills  in particular,  bentonite is the
singularly most  significant component  responsible for  reduction
in hydraulic conductivity of  the mix.   Up to a critical level
(previously determined  by  laboratory  testing) the higher the
bentonite content  in  the backfill,  the  lower and thus more
desirable the overall hydraulic conductivity.  For this  reason,
project  specifications for  S/B cutoff wall construction typically
include a minimum  requirement  for percent bentonite (5%  for the
Gilson Road wall).  In recognition of the above, the magnitude of
percent bentonite  in a backfill sample  is  the first indicator to
be evaluated in  the  event that the  API fixed-ring hydraulic
conductivity testing yields unacceptable  values.
                            2-17

-------
     In the  past, field measurements of  bulk quantities  of
backfill soils  and bentonite have  been used  to determine
bentonite percent by applying  basic weight/volume relationships.
This method  is approximate due to the limited accuracy of the
bulk  weight/volume  estimates, and optimistically assumes the
bentonite is  evenly mixed throughout the backfill.  Thus, bulk
measurements  can  be  used as a gross check on the percentage  of
bentonite in  the  backfill,  but are inadequate for quantitative
field control.

     As an alternative,  the use  of  conventional hydrometer test
procedures have been attempted  for bentonite determination.  This
procedure is  routinely used to determine the  amount of silt and
clay size particles  in  samples  of natural soils.   Inherent
limitations  in the test, however,  restrict its use for backfill
QC testing.   Lambe (1951) reports that the hydrometer  test can
measure colloidal factors  to  an  accuracy of only +3 percent,  an
unacceptable  error band when compared to the specified bentonite
content of 5  percent.   Moreover, the test cannot differentiate
bentonite from other naturally occurring clay-size particles,
necessitating additional hydrometer tests on the other components
of the mix.   Equally restrictive is  the  three to  four days
required to  complete each  group  of tests.  This time period  is
excessive relative to the  rate at which backfill is mixed and
placed.  Hence,  the  test is considered unsuitable for real time
quality control of the construction process.

     A laboratory testing  program was  therefore carried out  to
investigate the applicability of the quicker and potentially more
accurate methylene blue  test for determination  of percent
bentonite in  S/B backfill.  A primary objective of this  work was
to verify the accuracy and precision of the methylene blue test
procedures previously adopted for evaluation of  bentonite content
on the Gilson Road project.  As such, primarily granular mixes  in
which the bentonite additive is the predominant clay component
were used during  the testing  to  simulate the backfill used  at
Gilson Road.   In addition,  evaluations  of  the  test's
applicability for general  use in field control of other  sites
employing S/B cutoff walls were  made.   The test and  testing
program are described in the following sections.


     2.2.1  Methylene Blue Titration


     Methylene blue titration is a laboratory  technique commonly
used to determine bentonite  content in bentonite/water  slurries
(Alther,  undated).  Primary applications in  the past have been  in
the oil  drilling industry  for  testing drilling  mud.   The
procedure is  based on  the  proportionality between clay content


                            2-18

-------
and ion exchange capacity.   In  a  suitable  aqueous environment,
such as an electrolytic clay- water  suspension,  clay materials
are associated with naturally occurring  adsorbed cations of a
fixed total charge  (typically sodium,  calcium,  magnesium,  or
potassium).   These cations are  either  retained  by the clay or
exchanged for other cations subsequently  introduced into solution.
The degree  to which  this exchange  may  occur,  referred to as
cation exchange capacity, increases with  the proportion  and
activity of the clay in  suspension.

     The determination of bentonite  content  via the methylene
blue test therefore relies on the proportionality between the
amount  of  methylene blue cations exchanged  and the amount of
bentonite in the backfill  sample  tested.   The  introduction of a
methylene blue solution  into a  bentonite-water  suspension will
cause such an exchange.  Bentonite content  can then be determined
by quantifying the amount of cations exchanged.  In a similar
sense, bentonite content in  a suspension of  S/B backfill  and
water  can  also be  determined  using the proportionality with
exchanged cations.

     The quantity  of methylene blue cations exchanged  is
determined by titration.  The titration procedure involves the
incremental addition of  methylene blue solution  to a suspension
consisting of the backfill sample and  a  predetermined volume of
distilled water and dispersent until  the cation exchange capacity
of the suspension is exceeded  (end point).  Methylene blue
consumption at the end point is then used  to determine  the dry
weight  of  bentonite  in the sample via a  pre-established
correlation.

     The correlation is based on  a  series  of methylene blue tests
performed  on laboratory  prepared  samples  with  known
concentrations of the individual backfill components (bentonite,
trench spoil, and borrow).  The test results  indicate the  cation
exchange capacity of  each component over  the  range  of
concentrations anticipated in the backfill.  The correlation
curve for the backfill is then  established via the superposition
of these results.  As  bentonite  has a high cation exchange
capacity relative to the  granular trench spoil and borrow,  cation
exchange  capacity  of  the backfill is  highly  dependent  on
bentonite  content and only marginally affected by changes in
spoil and borrow content.

     The methylene blue test is  well suited for  quality  control
of S/B backfills due  to the relatively  short testing  time
(approximately 30  minutes per  test),  low  cost, and minimal
laboratory  requirements.   A detailed  description of  the
standardized test procedure, which directly reflects the  results
of efforts performed for this project,  is described in Appendix B.


                            2-19

-------
The procedure  is  based  on general bentonite titration  methods
(Alther,  undated and Baroid,  undated), but includes modifications
necessary for  specific application to quality control of  S/B
cutoff wall construction.  These modifications affected  primarily
sample preparation and computational techniques.


     2.2.2 Testing Program


     Evaluation of the  accuracy  and  precision of the methylene
blue test for quality control of S/B backfill was separated  into
four distinct  phases.   Phasing was implemented to progressively
assess the impact attributable to increasingly more  complicated
soil/water matrices  accompanying the bentonite.  These matrices
encompassed the simplest  case of distilled water without  soil  to
more  realistic  combinations approximating actual backfill
samples,  including  natural soils with  non-bentonite related
cation exchange capacity and interstitial water contaminated with
hazardous wastes.  The applicability of linear proportionality,
matrixing effects  and  superposition were thus investigated.
Testing  accuracy  was assessed through comparisons  of measured
bentonite content  with that actually added to the laboratory
prepared  samples.

     The  four phases were:

     0 Bentonite in a distilled water matrix;

     0 Bentonite in an Ottawa sand and distilled water  matrix;

     0 Bentonite in a contaminated water matrix;

     0   Bentonite  in an off-site borrow, trench spoil and
       distilled water matrix.

     The  rationale  leading to the selection of the above  four
matrices, as well  as  the results of the work, are presented  in
the following subsections.


          2.2.2.1  Distilled Water Matrix
     Bentonite in a matrix of distilled water and dispersant was
chosen for the  first  phase  of  testing  to assess  the
proportionality and  inherent accuracy/precision of the methylene
blue titration for bentonite  content.   This  series of tests
allowed  evaluation  of the basic  test procedure without the
                             2-20

-------
complicating  effects that additional backfill  components might
present.

     Three to four aliquots  each  of ten slurries containing from
0.0  to 0.9 grams bentonite  were prepared.  These bentonite
amounts  represented  0 to 9 percent bentonite by dry  weight in
10-gram backfill samples.  Standardization  of a 10-gram sample
size  reflects sampling,  testing, and typical backfill gradation
considerations.   Designed S/B  backfill mixes  for  hazardous waste
containment generally require 2 to 5 percent bentonits and as
such  fall well  within the range of tests performed.   The same
bentonite was used  throughout the testing  and  conformed to the
American Petroleum  Institute's API grade,  minimum 91 barrel
yield.

     For each of  the 36 individual tests, the volume  of methylene
blue solution  added  to reach the  end  point of titration
(completion  of cation exchange) was plotted versus  the known
percent bentonite referenced to a  10-gram sample (see  Figure 2-4).
(Although the titration  volume actually corresponds to the dry
weight of bentonite, the data  are  presented herein as  an
equivalent bentonite percent in  the sample.   This format is used
in recognition of the ultimate objective of  standardizing this
procedure for  QC of S/B backfill mixes).

     The trend  portrayed by  the data not only demonstrates
proportionality  but also indicates  a linear relationship  between
methylene blue  titration volume and percent bentonite.  Linear
regression analysis performed  on the data yields  a  line  referred
to as the "bentonite calibration curve" which fits  the data set
to a high degree as reflected  by a coefficient of  determination
equal to  0.999.

     Assumption of  linearity,  as  supported by the  physical
processes involved in the  titration as well  as the data,  allows
evaluation of the test's  precision and accuracy.   Inasmuch as the
calibration curve itself is determined by the data, accuracy  and
precision of  the calibration are synonomous and  defined as the
degree to which an  individual data point would  be  expected to
correspond to the relationship defined by  the  entire data  set
(the regression  line).  Standard statistical methods were  used to
establish 95  percent confidence limits about  the  mean response of
the data set  (also  shown on  Figure 2-4).   The  resulting  0.2
percent  offset of upper and lower bound error  bands  from  the
calibration curve is therefore  the primary measure of both
accuracy and  precision.   Hence, given a slurry sample containing
an unknown amount of bentonite,  it would be expected that  the
titration volume in  conjunction  with the previously established
calibration curve would yield the correct percent bentonite to
within +0.2 percent with a 95  percent degree of  confidence.


                             2-21

-------
              FIG. 2-4  METHYLENE  BLUE  TEST RESULTS:  BENTONITE IN  DISTILLED WATER
NJ
I
IV)
NJ
IW
QO
_j ao
*»
w 7O-
-3 ru
. i fin.
Ill OW
z
UJ
v 50
X
h-
!= AO-
^ *rW
3O-
20-
Ifi"









1-11 1




95% C


(3)-— i
\S^
(3) — —j*
^1
o • ,




DNFIDENCE


(4) 	 •» «
•^
1





: INTERVA

• 	 BENTC
CURVI

•a ^






.2).^. —~"
K
)NITE CALI






(3)—^I

K

BRATION


L ^ e

H



•^





! 1

.0.2ml.
S~
rf
1





r t

(2) 	 1
10.2%






» n
                                % BENTONITE IN DISTILLED WATER

-------
     The bentonite/distilled  water samples used to  establish the
basic relationship between titration volume and percent bentonite
excluded all  other  possible backfill components.   This "best
case" condition is therefore expected to yield the highest degree
of accuracy.  The curve defined by this data  is  the baseline
calibration  against which the results of subsequent tests on more
realistic backfill  samples are compared and  testing accuracy
assessed.


          2.2.2.2  Ottawa Sand/Distilled Water Matrix


     For the second  phase  of  testing, known amounts of  bentonite
were added to a matrix composed of Ottawa  sand,  distilled water,
and dispersant.   These samples were one degree more complex than
those used  for Phase I testing and also one  step  closer  to a
typical backfill  sample.  Ottawa sand was selected  in that it is
almost  entirely quartz  with no  clay  minerals  present.
Furthermore, quartz  is the most prevalent mineral  in the Gilson
Road backfill  due to the silica base of the  on-site soils and
off-site borrow used as  the predominant  mix components
(determined  via x-ray diffraction).   As would  be expected based
on cation exchange principles, quartz, and thus the Ottawa sand,
has no exchange capacity.  The specific objective of  this testing
phase was therefore  to determine whether the presence of backfill
components  having no cation exchange capacity  would interfere
with the bentonite/methylene blue  cation  exchange.   This
interference, referred to as "matrixing  effect," would include
any physical,  chemical, or electrical phenomena which alter the
surface activity of the bentonite clay mineral.

     Three identical  samples  were  individually prepared at each
of five bentonite  contents:  0, 2,  4, 6, and  8  percent (by dry
weight) .  Each sample contained appropriate dry weights of Ottawa
sand and bentonite to yield 10-gram "backfill"  samples with the
specified bentonite  percentage. These samples were added to the
standardized volume of distilled water/dispersant  and slurried
for  testing.  For  each of the 15  tests,  the methylene blue
titration volume  at  end point was plotted  versus  the  known
bentonite percentage (Figure  2-5).  The previously determined
calibration curve and  95  percent confidence  interval  (from
Figure 2-4)  are also  presented with  the data for comparison.

     The data indicate  that,  within  the +0.2 percent error band
established  via the  95 percent  confidence  interval, the Ottawa
sand  has no effect on the methylene blue/bentonite cation
exchange process.  Therefore, matrixing problems are  not probable
due to  the  presence  of quartz-based backfill components with no
cation exchange capacity.


                             2-23

-------
         FIG. 2-5  METHYLENE  BLUE  TEST RESULTS! BENTONITE  IN OTTAWA SAND/DISTILLED WATER
ro
I
K)
                                         BENTONITE CALIBRATION CURVE
                              95% CONFIDENCE INTERVAL
                        12345678

                           % BENTONITE IN OTTAWA SAND/DISTILLED WATER

-------
          2.2.2.3  Contaminated Water Matrix


     During methylene blue testing, backfill samples are,  in all
cases,  mixed with distilled water to create a suspension which is
then titrated.   Hence, the  water used during the testing is
always  contaminant free.   However,  contaminants may be added to
the suspension via  the  backfill sample itself.  Where the  cutoff
wall is excavated through contaminated portions of the aquifer,
trench spoil incorporated  into  the backfill will contribute
contaminants carried  in its  interstitial  fluid.  Furthermore,
trench  slurry is typically added to the backfill during mixing to
increase the slump.  Water added  in this way typically accounts
for over  50 percent of  the backfill water  content.  While the
slurry may also  pick  up contaminants from the  aquifer's
interstitial fluid  via  osmosis  and/or entrainment, of greater
importance is the chemical make-up  of the water used to produce
the slurry.

     In light of the above, addition of contaminants to the test
suspension may be more  the norm rather than  the exception.   This
was in  fact the case  for the  Gilson Road site where the primary
aquifer contaminants  consisted  of volatile organic industrial
solvents, and the  slurry makeup water exhibited significant
hardness.  To assess  the possible matrixing effects  of  these
contaminants on the accuracy of the methylene blue test, a worst
case scenario was utilized for  sample preparation.  In addition
to  incorporation  of  contaminants  via the backfill itself,
contaminated water was  used  to  form the test suspension instead
of distilled water.

     Contaminated water from three different sources  on the
Gilson  Road site were obtained  for  this phase of the work.  The
first  two, designated well water  and stream water, were sources
actually used during construction for slurry makeup water.  The
third  and  most contaminated  source was leachate as taken from
monitoring installations on  the site.  Backfill samples were
prepared  at 0, 2, 5,  and 8 percent bentonite in a manner similar
to Phase I testing.  Two  aliquots were tested for each bentonite
content using the stream and  well water (total of 16 samples).
Only one series  was  performed using leachate  at the four
bentonite  contents (4 samples).

     Test  results,  presented  in Figure 2-6,  indicate that the
contaminants tested had no significant effect on the test results.
All but one of the individual data points fall within +0.2
percent of the original  bentonite  calibration curve.  As such,
the initial calibration accuracy  of +0.2 percent with a 95
percent confidence level was  maintained in  spite of the  Gilson
Road contaminants introduced into the matrix  tested.
                             2-25

-------
               FIG. 2-6  METHYLENE  BLUE TEST  RESULTS! BENTONITE  IN CONTAMINATED  WATER
I
ro
  100



   90



   80
U  70
GO

UJ
z
UJ
              Ul
                 60
   30



   20



   10
                    (2)
                        •  WELL WATER

                        *  STREAM WATER


                        •  LEACHATE  	
                                      -(2)
                         -(2
                                                                      (2)
                                                                        (2)-
                                                BENTONITE CALIBRATION-
                                                CURVE
                                              95% CONFIDENCE INTERVAL
                                 234567

                                 % BENTONITE IN CONTAMINATED WATER
                                                              8

-------
     For volatile organic contaminants,  noninterference would  be
expected inasmuch as they are non-ionic and therefore should not
exhibit a high  cation exchange capacity.  In addition, the
backfill  sample  is  dried  in an  oven  at 105°C  and  the
backfill/water/dispersant matrix is boiled prior to titration.
The temperature involved in the above procedural steps would  be
expected to remove the volatiles.

     For other sites, particularly those containing highly ionic
contaminants, the  cation exchange potential of the  species
present  should be compared to  that of methylene blue with respect
to affinity for the bentonite clay mineral.  In cases where high
non-volatile solvent concentrations  exist, reduced solvent
(water)  polarity effects,  as they relate to methylene blue
solubility,  should  also be  investigated.  This can be done on a
theoretical basis or by utilizing the simple testing procedure
described herein.   It should be recognized however that this
testing  procedure  can yield "false positives" in  that the
quantity of  contaminants introduced into the matrix far exceeds
that which is likely to be added via an actual backfill sample.


          2.2,2.4  Gilson Road  Backfill Matrix


     The fourth  phase  of  testing  employed  prepared samples
duplicating the backfill used  for the Gilson Road project.   As
previously discussed, the Gilson Road backfill consisted  of
approximately equal proportions of trench  spoil (sand and gravel)
and off-site borrow (sandy  silt) with 3 to 5 percent bentonite
added.   The  objectives of this series of tests were to  1)
evaluate the impact of a cation exchange  capacity attributable  to
non-bentonite backfill components  on the determination of percent
bentonite  in the  backfill;  2) determine if the  bentonite
calibration  could  be corrected to account for non-bentonite
cation exchange capacity utilizing superposition; and 3) based  on
the above, evaluate the accuracy of the methylene  blue test
results previously obtained for the Gilson Road project.

     The on-site soils  (trench  spoil component of the backfill)
used for testing were obtained  during a post-construction  boring
program.  Samples were selected from various locations, both with
respect  to wall  perimeter and aquifer depth.  They  exhibited
gradations ranging from fine sand and silt to fine to coarse sand
and gravel and represent the full  variation of soils encountered
during cutoff construction.   The ten samples were mixed with
distilled water and  dispersant in a manner  similar to Phase  II
testing  except that no bentonite was added.  The on-site soils
exhibited average cation exchange capacities equivalent  to 0.2
                             2-27

-------
percent bentonite with a  range  of 0.1 to 0.4 percent.  Results
are summarized  in  Table  2-5.
                           TABLE 2-5

                   METHYLENE BLUE TEST RESULTS
                    ON-SITE (TRENCH SPOIL)

Station
2+50
9+30
9+30
13+00
13+00
34+70
34+70
25+30
25+30
38 + 50
Offset
20'S
50'N
50 "N
0
0
60'NW
60'NW
20 'NE
20 'NE
40'E
Depth
Feet
0-2
33-37
11-13
24-26
44-46
54-55.5
79-80.5
29-31
69-71
24-26
Description
fine sand and silt
fine sand
fine to coarse sand
fine to medium sand
fine to coarse sand
glacial till
glacial till
fine to coarse sand
and gravel
fine to medium sand
fine to coarse sand
sand gravel
Methylene
Blue, Ml
4
3
1
2
4
1
1
2
2
3

     Nine samples  of  the off-site borrow were also  selected from
record samples  taken during construction.   Again the  objective of
sample  selection was to encompass the full  variability of the
materials.   Eight of these samples yielded bentonite equivalents
of 0.6  to 0.7  percent with one sample yielding 0.4 percent.  Test
results are  summarized in Table 2-6.
                             2-28

-------
                           TABLE 2-6

                  METHYLENE BLUE TEST RESULTS
                        OFF-SITE BORROW
Station From Which
Borrow Was Obtained
Millileters of Methylene
Blue Required to Complete
         Titration
4+45
9+00
12 + 50
18+00
25+50
28+00
32+00
35+00
38 + 50
7
7
6
7
4
6
7
6
6
     This preliminary  testing  for the exchange capacity  of
individual non-bentonite backfill  components provided a basis for
prediction of  the bias  expected  relative  to  the bentonite
calibration  previously  developed.   An anticipated ' offset
equivalent  to 0.4  percent bentonite was derived using a weighted
average of  the  individual exchange capacities  based on the
relative amounts of borrow and  trench spoil in the backfill.

     Fifteen  splits  of  backfill were then prepared containing
equal proportions  of the on-site soil and the off-site borrow
(ratio  used  during construction of the Gilson  Road cutoff).
Bentonite  was  added to the resulting mixture  (a silty sand and
gravel) to  obtain  three samples  at each of 5 bentonite contents:
1, 3, 5,  7, and 9  percent by dry weight.   The  samples were
titrated  with methylene blue solution until endpoint; the data
are plotted  on Figure 2-7.
                             2-29

-------
                    FIG. 2-7  METHYLENE  BLUE TEST RESULTS!
                             BENTONITE  IN BORROW/TRENCH SPOIL/DISTILLED WATER
i
U)
o
ID
_l
03
UJ
Z
          X
          h-
          UJ
                                         BENTONITE CALIBRATION CURVE
                                         CORRECTED FOR BORROW
                                         a SPOIL
BENTONITE
CALIBRATION
CURVE
                                      = BENTONITE EQUIVALENT
                                         IN BORROW a SPOIL
                                         (0.4%)
                       I       2      3      45       6      7       8

                    % BENTONITE IN BORROW/TRENCH  SPOIL/DISTILLED WATER

-------
     Test results exhibited a  linear  trend,  but,  as  expected,
also demonstrated bias reflecting greater  exchange capacity than
attributable to  the bentonite alone.   Superposition of the
previously predicted 0.4 percent non-bentonite derived off-set on
the original calibration curve yielded  a  "corrected calibration
curve"  presented as  a dashed line  on Figure  2-7.   The original
bentonite calibration curve developed during the first  phase of
testing is also presented for comparison.

     Although this corrected -calibration  does not exactly match
the best fit line through the actual data,  it  does agree  to +0.3
percent bentonite.  These data therefore support the validity of
superposition in that the small discrepancy  obtained corresponds
to inaccuracies incurred by averaging the data upon  which the
corrected calibration curve was based.   These results indicate
that the procedure  of superimposing average exchange  capacities
of non-bentonite backfill components on  the  bentonite calibration
curve,  as  was used on  the Gilson Road project,  yields a new
corrected calibration curve with  an expected accuracy  of +0.3
percent bentonite.  This error band represents less  than
+6 percent of the specified bentonite content (5 percent of
backfill,  by dry  weight)  and verifies that the data  amassed
during  the cutoff wall construction at  Gilson Road were  in fact
sufficiently accurate for field QC use.

     It should  be emphasized  at this  point  that unless the
bentonite calibration curve is corrected for the cation exchange
capacity attributable to non-bentonite backfill components, the
bentonite  contents measured during QC  testing  will  be
unconservatively  high.   In addition,  the accuracy  of this
superposition-based correction is directly  dependent  on  the
uniformity of the cation exchange capacities of the  individual
components and the  proportioning  of  these  components  in  the
backfill  mix.  Therefore, if either of  these parameters are
varied during construction of the  cutoff,  then  separate
calibration curve corrections representing  individual sections of
the wall would be required for QC testing.


     2.2.3  Field Use of the Methylene Blue  Test


     The laboratory program described herein was used to assess
the accuracy of the methylene blue  test  and was therefore
structured  to measure the unknown quantity of methylene blue
required to  titrate backfill  samples with  known bentonite
contents.  The data thus developed demonstrated the accuracy of
the test for field QC in cases similar to  the Gilson Road  project.
During actual use for QC in the field,  however,  the  methylene
blue consumption would be measured and  used to determine  the


                            2-31

-------
unknown bentonite content in the backfill  via  pre-established
calibrations.  Thus,  the  testing  methodology  used in field
applications initially would  follow a logic  similar  to  the
laboratory program for  establishment  of  a calibration  curve,  but
thereafter utilizes  methylene blue consumption as the  independent
variable and bentonite  content as the dependent variable.

     Implementation of the  methylene blue test for  quality
control therefore consists of the following procedure:

     0    Establish a bentonite calibration curve representing the
        relationship  between methylene blue  consumption  and
        bentonite  content  for ben tonite/distilied water
        suspensions.   The  same  bentonite  to  be used during
        construction  must be  used  during  this step.   The
        procedure  would  be similar  to the  Phase  I testing
        described  herein  except that  the  methylene blue
        consumption  would be plotted on  the  x-axis as  the
        independent  variable.

     0    Determine whether contaminants are likely to be present
        in the backfill samples and  evaluate the probable  effect
        on the calibration.

     0    Determine average cation exchange capacity  (methylene
        blue consumption) of the non-bentonite backfill  soils
        combined  in the same proportions they will  be mixed in
        the  field.  Use the bentonite calibration curve  to
        determine the  bentonite equivalent for this volume.

     0    Offset the  initially determined bentonite  calibration
        curve  to  account  for the bentonite equivalent of  the
        non-bentonite soils  and/or contaminants to  establish a
        field  calibration  curve.   Note that  multiple field
        calibration  curves may be  required  if significant
        variation in  the offset  values are anticipated  due to
        variations  in the  site  geology  or construction
        procedures.

     0    Perform the methylene blue test on backfill  samples and
        enter  the field calibration curve  with the  volume  of
        methylene blue  consumed  at   the  end  point  to
        determine bentonite content.

     It  should be pointed out that although the  test is quick,
inexpensive, and  accurate,  an  initial level  of practice  is
required  to accurately assess  the  end point of  titration.
Therefore, only technicians having experience with the titration
procedure should be  allowed to perform  the tests under the rigors
imposed by field quality control of fast track construction.


                             2-32

-------
     Finally,  the procedures presented herein are not directly
applicable to predominantly clay-based backfills.   For  this class
of cutoff, the high proportion  of  non-bentonite clay components
and the variability of  their total percentage in the backfill can
make  correction  of  the bentonite calibration curve  "sample
specific."  Therefore,  at  the very  least,  independent knowledge
of the amount of  non-bentonite  clay in  the  sample would be
required.  A procedure  has been developed for this case allowing
determination  of bentonite  content  through solution  of
simultaneous equations.  This work will  be  presented in a  future
report once the precision and accuracy  of  the procedure have been
established.


2.3  Effect of Backfill  Gradation on Hydraulic Conductivity


     As discussed in  the previous sections,  the addition of
relatively small percentages of bentonite to  a granular soil will
reduce its hydraulic conductivity  several  orders of magnitude.
This  effect  is  widely recognized and has  been clearly
demonstrated in  laboratory  tests (Schulze,  1984)  and field
applications.   It is also  recognized,  though  less well
understood, that  the overall gradation of a backfill  sample also
effects  its  hydraulic conductivity.   Inherently, the  more
"well-graded" the  sample, the denser  the particle packing and
hence,  the lower  the hydraulic conductivity.  It is  not  clear,
however,  what effect various  gradation  parameters have on
hydraulic conductivity.

     As part  of  this project,  therefore,  backfill data collected
both during and after construction were  statistically analyzed to
determine to what  extent gradation characteristics of a backfill
sample could be  used to  predict hydraulic  conductivity.   The
ultimate objective of  this effort  was to identify which aspects
of backfill gradation  play the  greatest role  in determining
backfill hydraulic conductivity.   This information  would then
serve  to enhance  quality control procedures by  providing
additional  insight  into a backfill  mix which  API  fixed-ring
testing indicates has an unacceptably high  hydraulic conductivity.
With such a correlation, gradation analyses  of  backfill could
become a more integral  part of  the  quality control program.   At
the present,  gradation  parameters are typically used  only to
control the percentage of fines within a minimum and maximum
value.   No further  criteria to  control,  much  less optimize,
backfill gradation are included in specifications because the
influence of varying  gradation characteristics  is  not
sufficiently understood.
                            2-33

-------
     The method used to evaluate the correlation consisted of the
following:

     0    Establish  a  data base  of gradation parameters  for  a
         statistically meaningful number of backfill  samples.
         For each of  these  samples, determine hydraulic
         conductivity.

     0    Perform  linear regression analyses on the individual
         parameters to establish the degree of dependency of
         hydraulic conductivity on each.

     0    Evaluate the interaction  of the  individual parameters
         using multiple polynomial regression  analyses.

     0    Establish confidence envelopes for  the relation between
         hydraulic conductivity and the soil parameters.

     This procedure and the results of the  analyses are described
in the  following sections.


     2.3.1  Data Base


     A  body of gradation parameters  and hydraulic conductivity
data was collected for eighty-six backfill samples obtained from
the Gilson Road site  both during and after construction.   The
primary backfill  parameters  for use in the correlation  were
percent bentonite,  percent  clay sizes, and percent silt  sizes
since hydraulic conductivity  is  considered most dependent upon
percentage and nature of  fines  (material passing no. 200 sieve).
Additional gradation  parameters were included to describe the
overall distribution  of particle sizes and the grain size curve.
Several density parameters  were also included since hydraulic
conductivity  is seen as a secondary function of backfill density.

     The backfill gradation and  density parameters used in the
analyses are  listed below:

     0    Percentage of  material  passing the No. 4 sieve (by dry
         weight).

     0    Percentage  of material  passing  the  No. 200  sieve,
         i.e., silt and clay sizes (by dry weight).

     0    Percentage of  material  finer than 2 microns, i.e., clay
         sizes  (by dry weight).
                             2-34

-------
     0   Percentage of bentonite (by dry weight; determined  using
         methylene blue titration).

     0   Grain  size at which 60 percent  of  the sample, by dry
         weight,  is finer (D60).

     0   Uniformity coefficient (D60/D10).

     0   Coefficient of curvature (D30)2/(D/10)  (D60).

     0   Unit Weight.

     0   Water content  (wt.  water/wt.  dry soil).

     0   Void ratio  (volume of voids/volume of soil).

     Values of hydraulic conductivity used  in the analysis were
determined  by API fixed-ring testing.


     2.3.2   Statistical Evaluation
     As the second  step  in  the development of a correlation, the
dependence of  hydraulic conductivity  on  each  backfill parameter
was evaluated.   Using standard statistical  methods, regression
lines defining  the mean  response  of  each  gradation/density
parameter  and hydraulic  conductivity were determined.   For each
set of data, the  correlation coefficient describing the scatter
of the data about the regression line  was also calculated as an
index of the degree  of dependency.   With  a  correlation
coefficient  of  1.0  (plus or minus)  indicative  of  perfect
correlation (i.e., all data points  located on  regression line),  a
correlation  coefficient of 0.75 was initially chosen to
distinguish those backfill parameters having  "primary" influence
from  those having  "secondary"  influence, for  later use in
performing polynomial regression analyses.

     Correlation  coefficients were first calculated based on an
arithmetic scale  plotting of hydraulic conductivity versus each
soil parameter.   Results are tabulated in Table 2-7.  None of the
soil parameters produced a correlation coefficient greater than
0.75; the highest coefficient was  0.42.   The correlation
coefficient between  percent bentonite and hydraulic conductivity
was 0.36;  the correlation coefficient for percent clay  sizes was
also 0.36.   For  total percent fines, the coefficient was 0.27.
Thus, the  parameters thought to be  most important to  hydraulic
conductivity did  not emerge as  such  in  the  statistical
evaluation.
                             2-35

-------
                        TABLE 2-7

                 CORRELATION COEFFICIENTS
        HYDRAULIC CONDUCTIVITY VS. GRADATION PARAMETERS
Y = CON-API
X vs. Y  X vs. LOG(Y)  LOG(X) vs. Y LOG(X)  vs. LOG(Y)
X = %-No.4
X = %-Nb.200
X = %-2u
X = DIG
X = D30
X = D60
X = Cu
X = Cz
X = GAMMA T
X = W
X = e
X = % Bent
X = CON-API
0.048
-0.274
-0.355
0.187
0.422
0.141
-0.314
0.047
0.311
-0.347
-0.363
-0.359
1.000
0.095
-0.240
-0.420
0.231
0.388
0.089
-0.393
-0.004
0.352
-0.380
-0.399
-0.440
0.894
0.049
-0.309
-0.362
0.376
0.387
0.130
-0.300
0.094
0.310
-0.351
-0.368
-0.400
0.894
0.097
-0.269
-0.418
0.438
0.382
0.091
-0.362
0.074
0.353
-0.376
-0.395
-0.471
1.000
NOTES:

CON-API = API fixed-ring hydraulic conductivity.
%-No.4 = Percentage of material passing the No. 4  sieve  (by dry
  weight); similar for "%-No.200" and "%-2u".
D10 = Grain size at which 10 percent of the sample (by  dry weight) is
     finer; similar for "D30" and "D60".
Cu = D6o/Di0
C2 = 
GAMMA T = Unit weight.
W = Water Content.
e = Void ratio.
% Bent = Percent bentonite determined using methylene blue test.
       Correlation coefficients were then calculated  based  on
  combined arithmetic-logarithmic  ("semi-log") scale plottings and
  on a  logarithmic  ("log-log")  scale plotting  to seek  a
  correlation.  None of  these relationships  exhibited a
  coefficient in  excess of  0.5.   Results  are also
  Table 2-7.
                                                  better
                                             correlation
                                          summarized  in
       As none  of the  individual parameters  was statistically  found
  to be a primary determinant of hydraulic  conductivity,  additional
                                 2-36

-------
statistical evaluation  to  determine interaction of individual
parameters and then  confidence  envelopes was not pursued.  The
lack of a predominant dependency of hydraulic conductivity on
percent bentonite, percent clay sizes or percent fines and lesser
dependency on other parameters indicated that  the overall
correlation between hydraulic  conductivity and soil gradation
parameters may  be  extremely  complex  and might not be fully
reflected by the available data set.   This may be due  to the
variable degree of blending of backfill components in the  samples
tested.   Increased blending  of field  samples was  found to
decrease hydraulic  conductivity  (see Section 2.1.3.2),  but it is
not known  to what degree  the field samples were homogeneous on a
grain-size scale.   In addition, the correlation is affected by
the previously observed variations in hydraulic conductivity
measurements of  identical backfill  samples.  The worst case
precision of the test was  found to be +57 percent within one
standard deviation  of the  mean value; this degree of  variation
would partially mask the  existence of a close correlation.

     The poor statistical correlation does not, however, alter or
invalidate the premise  that hydraulic conductivity is largely
determined  by  percent  bentonite  or percent clay  sizes.
Experience has demonstrated  the key roles played by these factors.
Therefore, it is simply  concluded that the underlying correlation
between the key soil parameters and hydraulic conductivity may
have been  obscured by  the  inherent  precision of the API
fixed-ring test.


     2.3.3  Importance of Statistical Correlation


     The establishment of a statistical correlation between
gradation  parameters and  hydraulic conductivity was investigated
primarily to gain further insight into the relative importance of
the various parameters  on  backfill  hydraulic conductivity.
Better  correlations would have rendered gradation analyses a more
integral component of field  quality control testing than at the
present.  As a supplement  to methylene blue testing,  gradation
analyses might have provided several key indicators of  potential
deficiencies in  a backfill sample having an unacceptably high
hydraulic  conductivity.

     In the  absence of such a  correlation, however, quality
control capabilities are  not seriously impaired.  API fixed-ring
and  methylene blue testing remain the primary and  secondary
quality control tests. Both tests are more direct indicators of
backfill quality than gradation analyses and both are quicker to
run.
                             2-37

-------
     The greater value in establishing a statistical correlation
between  quality control and  hydraulic  conductivity is for
backfill design.   If  the effect of various gradation parameters
on hydraulic conductivity could b^e quantified, preliminary
backfill  design could consist  of assessing  gradation
characteristics  of on-site  soils  and determining  via the
correlation the various  changes  in gradation required to achieve
desired  hydraulic conductivity.


2.4  Assessment of Gilson  Road QC  Data


     The use of  the API fixed-ring and methylene blue  tests
during construction of the Gilson  Road cutoff wall reflected the
current  state of the  art in  field quality control procedures.
Although the precision and  accuracy of  these tests  were not
assessed at the time of construction, the tests were used because
of their respective advantages over alternative test procedures.
Moreover,  the data generated during construction ultimately
played a vital role in the construction control program.   Tests
were run on a daily basis to assess the success of the contractor
in attaining design standards; deficiencies thus identified were
brought  to the contractor's  attention and immediate corrective
measures were typically taken  to remedy the problem.  It should
be emphasized, however, that evaluation of the overall quality  of
the final product at the end of  construction was based to a  large
degree on test procedures for  which reliability had not yet been
determined.  As a result,  in spite of the state of the art  field
control  program, the  degree  to which the quality control data
represented the quality of wall  construction, and therefore, the
degree  to which the  completed  wall  satisfied  project
specifications, was not known.

     The present effort intended  to achieve two major objectives:
1) assess the reliability  of QC  procedures used at Gilson  Road;
and 2) evaluate the data from  wall construction in the light  of
this new information.   In previous  sections, both  the API
fixed-ring  test  and methylene blue  test were found  to  be
sufficiently accurate and repeatable to validate their use  at
Gilson Road.  In this section, the QC data generated during  and
after construction are reviewed to assess the degree  to  which
project  specifications were satisfied.  Where specifications were
not satisfied, the impact on  cutoff wall performance  has been
evaluated.  Further,  the rationale for accepting backfill  which
does not meet specifications is  discussed.
                             2-38

-------
     2.4.1  Review of QC Data
     Effectively two bodies of QC data were collected at  Gilson
Road.  The first set  represented  tests performed  on  "grab"
samples obtained during  construction.  The second set consisted
of tests performed  on  "undisturbed"  tube  samples obtained from
the completed wall  one to  three  years  after  construction.  The
first set of data  indicated  that the hydraulic conductivity
specification was  generally  satisfied  once initial "Contractor
Learning Curve" problems with  backfill proportioning and mixing
were overcome.  The second set of data,  however, indicated that
the in-situ hydraulic  conductivity was  potentially an order of
magnitude higher than  that  determined on the "grab" samples.  The
results of the QC testing  are described below and evaluated with
respect to specification requirements.


         2.4.1.1  QC Data From Construction  Samples


     Seventy-five  backfill samples  were  collected during wall
construction.  The  samples were  collected immediately  after
completion of the field mixing effort, just  prior to placement of
the backfill in the trench.  Typically, each  sample consisted of
approximately 25  pounds  of  backfill to  provide  splits for
hydraulic conductivity  testing, methylene blue testing, gradation
testing,  and record samples.  Prior to  splitting, each sample
received additional mixing by hand to  improve the homogeneity of
the mix and thus the similarity of splits.

     API  fixed-ring hydraulic conductivity tests were run on each
of the seventy-five  samples.   In  addition,  triaxial tests were
run on ten of the samples.

     The  results  of the eighty-five  tests  ranged  from
9.9 x 10~9 cm/sec  to  4.3 x 10~7  cm/sec.    The mean  value was
5 x 10-8  qm/sec.   Sixty-six tests (78 percent) satisfied project
specifications for hydraulic conductivity, yielding values less
than or equal to 1.0 x 10~7 cm/sec.   Of the  nineteen samples that
yielded hydraulic  conductivities greater  than the  specified
maximum value,  eleven  were  between  1.0  x  10-7  and
2.0 x 10~7 cm/sec,  eight were between  2.0 x  10~7 cm/sec and
4.3 x 10-7 cm/sec.

     A  chronological  plot of hydraulic conductivity versus
construction date  (Figure  2.8a)  reveals  that six of the eight
highest  values were recorded during the  initial days of
construction (9/11/82  - 9/17/82). Throughout the remainder of
                            2-39

-------
          FIG. 2-8   a.  HYDRAULIC  CONDUCTIVITY  vs. TIME
lu.o

1.0
O.I



i
(J

•
® •
* •
4
(
»
f> ®
TRIAXIAL/
(TYR)
I
^MAXIMUM t
/ PER SPECI
/ 1.0 x 10 C

• <
i
•l.& "
'
I
ALLOWABLE
FICATION
m!?sec.
:
* 0
FIXED RING/
(TYR)
1
.

* / *
•

>
E
o
O

O


O
o
DC
Q
          10    15    20

           SEPTEMBER
25   30    5

    (1982)
10    15   20

 OCTOBER
30
                b. BENTONITE  CONTENT  vs. TIME
PERCENT BENTONITE
O f° * 0» OB C



1



A
» * • <
•

•
•
t
» • 4

«

•
• ^
' i *
i


i <
.. .[ -v
i

.
: i
r
L«.
» •
i
10 15 20 25 30 5 10 15 20 25 3
SEPTEMBER (1982) OCTOBER
                              2-40

-------
the  project,  values  in  excess of  the specification  were
encountered  on five construction  days spaced over the  first three
weeks  in October.   A plot of hydraulic conductivity versus
station along  the wall alignment  (Figure 2-9a)  indicates that the
higher values were  found between  stations 0+00 and 3+00,  between
stations 6+00  and 12+00,  and between stations 25+00  and  29+00.

     The primary cause  of the higher hydraulic conductivities
measured during  construction appears to be insufficient  bentonite
content.  On  a  time  plot illustrating percent bentonite versus
construction  date  (Figure 2-8b),  the lowest  percent  bentonite
(1.3 percent) was  recorded on 9/11/82 (start of  construction).
The time plot further illustrates that percent bentonite was
gradually increased  over the first few weeks of construction to
values as high as 7 and 8 percent bentonite before leveling off
at a range  of 2 to  5 percent.  The gradual  increase  in  percent
bentonite  at the  beginning of  construction  reflects  the
contractor's  response to the initially low  values.   These low
values  resulted from "Learning Curve  Problems"!  associated
with  the inaccuracies  of bentonite determination  via bulk
measurements.   The  increase  in  percent  bentonite  from
approximately  9/11/85  to 9/24/85 is directly reflected in a
steady decrease  in  hydraulic conductivity over the  same period
(refer  to Figure  2-8a).   Beyond 9/24/85, the occurrence of the
lowest values  of percent bentonite  occurred between  10/2 and 10/4
and between 10/12  and 10/18, coinciding with the  occurrence (in
both time and  location) of hydraulic conductivities in  excess of
specifications.

     A  secondary  cause  of  the  high values  of hydraulic
conductivity,  particularly during early stages of  construction,
may have been inadequate mixing  effort.  While bentonite contents
of  2  percent or  lower  were measured during three periods
throughout construction, high  values of  backfill  hydraulic
conductivity  were  most  frequently measured  during  the initial
days of  construction.  This situation is also reflective of a
learning period  that  construction personnel typically experience
during  initial  days  of  backfill preparation  as they  adjust to
site specific  conditions.
    cutoff  wall construction is a specialty contracting  job,
commonly executed by local equipment  operators working under the
supervision of two or three experienced cutoff wall personnel, a
certain period of time is required for "operator education" at
the initial stage of construction. The "learning curve"
phenomenon  can result in erratic quality for the first several
hundred feet of a wall.  Therefore, during initial project
start-up, additional conservatism with respect to bentonite
content and mixing effort should be executed.
                             2-41

-------
              PERCENT BENTONITE
                                                   HYDRAULIC CONDUCTIVITY  x IO"7 cm./sec.
ro
I
              ro
                               CO
o
•f
o
0
o
4.
o
o
to
H
HO
Oo
g
o
o




•
*




4
'


•• 4
• *



1 0


m a

t
•

•
^ • <
.;•*•
•
• •
*
•
\.
i





















•


                                                                                                   O

                                                                                                   ro
                                                                                                   i
                                                                                                   to
c
n
o

o
o
                                                                                                   o
                                                                                                   d
                                                                                                  5
                                                                                                  o

-------
     The results of the  hydraulic conductivity and methylene blue
tests run on grab samples  thus  indicated that,  in general,  the
hydraulic  conductivity specification  was  satisfied while the
bentonite specification was not.  Although hydraulic conductivity
data  indicated that approximately  22 percent of the samples
tested had a hydraulic  conductivity  in excess  of the maximum
specified  value of  1.0 x 10~7  cm/sec, the higher values were
judged to have little impact on wall performance.  The impact of
lower than specified  bentonite  values  was  also limited as the
specified value of  5.0 percent  bentonite incorporated a safety
factor of 1.67 over  the value  required based on design testing
(3.0).   This factor of safety was adopted to  account for the less
than  "laboratory  perfect"  proportioning  and  mixing expected
during actual construction.  Therefore, the mean value of 3.5
value reflected a technically acceptable  level.


         2.4.1.2  QC Data  From Post-Construction Samples


     Eleven  backfill samples were obtained  in 1983 and 1985 from
the completed wall.   The  samples were  obtained from various
depths at three stations  along the wall alignment, station 1+00,
station 3+45, and station 11+00.  These locations were chosen on
the basis  of the  relatively  high hydraulic conductivities
measured on backfill  samples  obtained  from these areas during
construction (refer  to  Figure  2-9a).   It was intended that the
post-construction samples would represent "worst  case" backfill.
The samples were obtained  using a stationary-piston tube sampler,
commonly used to obtain "undisturbed"  samples  of fine-grained
soils.  Sample depths ranged  from 2  to 82  feet.  The tubes were
x-rayed prior to sample extrusion to determine the relative
gradation of the backfill samples (predominantly coarse versus
fine)  as well as the location  of  gravel  pieces within the tube.
The primary objective was to  test a  variety of backfill samples
while at the same time avoiding  specimens with  large pieces of
gravel.   A  large piece  of  gravel would  result in  an
unrepresentatively low hydraulic  conductivity as it would block
off a large percentage  of the cross-sectional area of the sample
and the hydraulic  conductivity  of the  gravel itself is nearly
zero.   The  total  area  is used  in the hydraulic conductivity
computation.

     Each  of  the eleven  samples was tested  "undisturbed" in the
triaxial apparatus immediately upon extrusion from the sampling
tube.   The  tests  were  first  run at  low  confining pressures
commensurate with top  of wall  conditions although eight of the
samples were taken  from  depths  below  10 feet.  "Top of wall"
stresses were selected to  correlate with the stress range used
for  API fixed-ring  testing executed  during construction.


                            2-43

-------
Quality control  testing  during construction was  conducted using
"top of wall" stresses inasmuch  as the final vertical  location  of
backfill  in the wall cannot be predicted when  the  sample  is
obtained prior to backfill placement (see Section 2.1.2.2).

     It was recognized that  the  undisturbed samples taken from
the  completed  wall  would  have undergone consolidation
commensurate with depth  in  the wall.   Therefore,  the soil fabric
of these samples would correspond to the API fixed-ring  samples
only to the extent  that  the  sample swelled in response to stress
relief.  The samples would thus  be tested in an overconsolidated
state.   The significance of overconsolidation is discussed below.

     Seven of  the eleven samples were  subsequently tested at a
second,  higher stress level,  commensurate with the  approximate
vertical effective  stress at  the depth from which  the sample was
taken.   This higher stress level yields hydraulic conductivities
representative of the actual performance of the wall.  The lower
stress  levels would be expected to  yield  higher and thus
conservative hydraulic conductivity values.

     The  eleven  tests  at  low stresses  yielded hydraulic
conductivities ranging from 6.6 x 10~8  to 1.2 x 10~6 cm/sec
(refer  to Table  2-8).   The mean value was 5.6 x 10~7  cm/sec.
Only two of the eleven tests  satisfied project specifications  for
hydraulic conductivity.  However,  seven of  the  tests  yielded
hydraulic  conductivities less than 5.5 x 10~7  cm/sec.   Thus,  as
hydraulic conductivities of the construction samples taken from
these areas ranged from 9.9  x 10~9 to 4.3 x 10~7  cm/sec,  these
"undisturbed,"  triaxial  results  appear consistent with
construction results.  The  remaining  four test results  are
notably higher,  exceeding  the previous maximum by half an order
of magnitude and the specified  limit by one order of magnitude.
                             2-44

-------
                                TABLE 2-8

           HYDRAULIC CONDUCTIVITY:  "UNDISTURBED" VS "REMIXED" SAMPLES
Station
       Depth
       (ft.)
 Triaxial Hydraulic Conductivity,
        K(x 10~7 citv/sec)
Undisturbed   Undisturbed  Remixed
                  low stress   high stress  low stress
               API Fixed-Ring
            Hydraulic Conductivity
               (x 10~7 cm/sec)
 1+00
 1+00
 1+00
 1+00
 1+00
 3+45
 3+45
 3+45
 3+45
11+00
11+00
9.5-9.9
20.6-21.1
31.0-31.4
42.5-42.9
80.6-81.0
4.5-5.0
12.5-12.9
22.4-22.8
33.0-33.5
9.2-9.7
22.4-22.9
0.66
2.1
1.5
0.85
10.0
12.0
12.0
3.6
5.5
10.0
5.0
                       5
                       5
                       5
                       5
                       3
                       5
                       5
                       5
                       5
                       5
                       3
            0.47
            1.3
            3.8

            7.8
            2.5
            1.7

            2.5
10
20
1.0
37  0.8
10
20
40
4.0
1.5
5
5
13   0.26
0.28
0.78
1.0
0.82
0.8
1.2
1.1
0.78
0.90
2.8
0.7
d = effective confining pressure (psi).
       When  seven  of the tests were  further consolidated  to
  approximate  in-situ  stress  levels,  the  result in each  case was a
  reduction in  hydraulic  conductivity.   Within  this  subset  of  seven
  tests,  hydraulic  conductivity  ranged from  4.7  x 1 0 ~ ^  to
  7.8 'x 10~'  cm/sec at the  higher  stress  levels, with a
  of 2.9  x 1017  cm/sec.  The  range for the lower stress
                                 cm/sec,  with a  mean
                    Results  are  summarized in  Table  2-8.
6.6  x 10~8  to 1.2 x  10~6
5.6 xlO~7 cm/sec.
                                        mean value
                                         level was
                                         value  of
       This data indicates  that the Gilson Road  QC  results  are
  likely  to be  conservative  relative to  actual in-situ conditions
  due to the lower  than  in-situ  stresses  used for  QC testing.   The
  data  indicates  a reduction in  hydraulic conductivity  by a factor
  of  two.   The actual reduction  is  probably  even greater than  this
  since the low  stress data  was obtained from samples which  had
  previously  been consolidated to  higher in-situ  stresses.
  Although  the  stresses were lowered  to  "top of wall" levels prior
  to  testing,  the  soil  fabric should still have reflected  the
  previously higher   stresses  (i.e.,  the  sample  was
  overconsolidated ) .   It  would  therefore yield  hydraulic
  conductivities  lower than  those  associated with  identical samples
  which had not  previously experienced the  higher stress level.
                                2-45

-------
Thus, the change in hydraulic conductivity with stress  is likely
to be greater than the  above data indicates.

     Five of the eleven "undisturbed"  triaxial samples  were then
remixed  and  retested in the triaxial apparatus to assess whether
the higher  hydraulic conductivities measured  in the "undisturbed"
samples  were related to the lesser degree  of mixing when compared
to the construction samples.   Each sample  was mixed thoroughly
and retested in a "disturbed" state, modeling the triaxial tests
performed during  construction.   The  tests were  run at low
confining stresses.   Test results, summarized in Table  2-8,
indicated that  the additional  mixing lead to lower hydraulic
conductivities in all five cases and by approximately one order
of magnitude in  three of the cases. Furthermore, the results on
the remixed samples were consistent with the results from the
samples obtained during construction, ranging from 2.6 x 10~8
cm/sec to  4.0 x 10~1 cm/sec.

     API fixed-ring tests were subsequently  performed on each of
the eleven  samples after remixing. These  tests also  yielded
values  consistent with those obtained during construction.
Results  ranged from 2.8 x 10~8 cm/sec to 2.8 x 10"' cm/sec with a
mean  value of  1.0 x  10~7 cm/sec (refer to Table 2-8).   Once
again,  remixing resulted  in  significantly  lower hydraulic
conductivities  as  compared to  the undisturbed triaxial tests.
Furthermore, remixed API fixed-ring tests yielded results very
compatible to  remixed, low stress triaxial tests (within an
average factor  of  two).   The  additional  mixing utilized to
prepare the API fixed-ring  samples from the remixed triaxial
samples  resulted in  a  further  reduction  in hydraulic
conductivity.

     Therefore, the  results from the  triaxial tests and API
fixed-ring  tests  on  the remixed post-construction  samples
indicate  that remixing  beyond the level  achieved in the field to
obtain duplicate sample  splits  may result in a lower hydraulic
conductivity than that which exists in  the field.  This  reduction
in hydraulic conductivity for  the Gilson Road site was nearly
one-half an order of magnitude as based on the five backfill
samples which were  tested in  the triaxial apparatus,  first
"undisturbed"  and  then  remixed.  (The  average hydraulic
conductivity of  the "undisturbed"  samples was 6.5 x 10~? cm/sec
and the  remixed  samples was 1.5 x 10~7 cm/sec.)
                             2-46

-------
          2.4.1.3  Evaluation of the Validity of the QC
                  Construction Data


     The  primary  purpose  of the  data  obtained from
post-construction  samples  is  to  validate  the  use of  QC
construction  data  for evaluating  wall performance.  Although the
API fixed-ring  test  has been established as  a reliable  and
accurate  quality control procedure (Section 2.1), the validity of
the QC construction  data at the Gilson  Road  site also depends
upon a viable comparison of test procedures and conditions with
actual  field conditions (i.e., in-situ stresses,  no remixing),
which are  more closely reflected in the post-construction  testing.
Based on  the post-construction data, two quality  control testing
procedural details  have been identified which may result in the
hydraulic  conductivity of the Gilson Road QC construction samples
being unrepresentative of that actually attained in the field.

     The  first  such  detail  is  the  additional  mixing of the
backfill  after sampling  to increase homogeneity  prior  to
splitting   the  sample  for  duplicate  testing.   The
post-construction data indicate that this may have resulted in
nearly a  one-half order of  magnitude, unconservative error in the
Gilson Road QC  construction data.   This error can be  easily
avoided in future  projects by eliminating the remixing  step and
accepting  some variability in the duplicate sample aliquots.   The
second procedural  step involves testing the  samples at  "top of
wall" stresses  in  recognition of the indeterminancy of  final
backfill  vertical location during sampling.   The above data
indicate  that  this procedure resulted  in greater than  a
one-quarter order  of magnitude conservative error in the Gilson
Road* QC data.   This  conservative bias  is an unavoidable  but
desirable  facet  of the QC testing program.

     The  combination of  the above two factors indicates  that the
Gilson  Road construction QC data is likely unconservative by a
factor  of approximately  two.   Again,  it  is  emphasized the
elimination of the remixing  step on future projects should result
in a somewhat conservative bias to  the QC data.


          2.4.1.4  Implication  of QC Data on Containment
                  Performance


     The  quality control  data obtained during  construction
indicated  at  the time  that the  hydraulic conductivity
specification was generally satisfied while the percent bentonite
specification was not.  Although  the hydraulic  conductivity data
indicated that  approximately 22  percent of the samples tested had


                             2-47

-------
a hydraulic conductivity  in excess of the maximum specified value
of 1.0 x 10~7 cm/sec, the higher  values were  judged  to  have
little impact  on  wall  performance.   The  most important
considerations  in  assessing  the impact of  the higher  than
specified  hydraulic conductivities were  the  magnitude of the
variation from the  specified  limit and the  location along the
wall alignment of the higher  hydraulic conductivity zones.  The
average hydraulic conductivity  of the nineteen tests  above
1.0 x 10~7cm/Sec was 2.1 x 10~7  cm/sec.   This  margin is small
relative to the  four  to  five  order of magnitude difference
between  backfill  hydraulic  conductivity  and the  hydraulic
conductivity of the  natural soil  deposits  (2 x  10"? cm/sec vs.
1 x 10~3 to 1 x  10~2 cm/sec).  It should also be recognized that
the samples were tested at conservatively low  confining stresses,
corresponding to "top of wall" conditions.   It is likely that
some of  these samples  reflected backfill which ultimately
advanced to a deeper location  in  the wall  and  was subjected to
higher stresses in-situ than those  in the  test.  Since an
increase in confining  stress would cause a reduction in hydraulic
conductivity, the in-situ  hydraulic conductivity  is likely lower
than the  tested values.

     The  major impact of the higher  permeability  zones is that
groundwater flow into the  containment area,  induced by pumping,
will be marginally  greater in  these areas.   Overall, however, as
the average wall hydraulic conductivity was 5  x 10~8  cm/sec,
groundwater inflow through the  wall would be less  than
anticipated for a wall with an average hydraulic  conductivity of
1 x 10~7 cm/sec.  The  presence  of the bentonite filter cake along
trench  walls, not  previously mentioned  should  also  help
compensate for marginally high hydraulic  conductivity  zones in
the backfill.

     In addition to the  relatively small  degree by which the
backfill  exceeded the specification limit,  the higher hydraulic
conductivity zones  appear to  be located in  areas of relatively
low hydrologic impact.  As indicated, these  areas include from
station  0+00 to 3+00, 6+00  to 12+00, and  25+00 to 29+00 (see
Figure 2-10).  The direction of  groundwater flow is predominantly
parallel  to  these sections of  the wall, resulting  in
comparatively low gradients across  the wall.   (Areas of largest
gradients would  be  those  sections perpendicular or nearly  so to
flow,  approximately from  station 13+00 to 19 + 00  and from station
32+00 to 0+00).  The low gradients would result in comparatively
low flow  quantities across  the wall.

     The subsequent quality control  testing program on samples
obtained  from the completed wall indicated that the construction
                             2-48

-------
     FIGURE 2-10  APPARENT ZONES OF BACKFILL  WITH
                  HYDRAULIC CONDUCTIVITY GREATER
NO
I
-V
                  THAN
                             "7
X
                                                                                          00
         LYLE REED
           BROOK
                                                                                 0' 50' 100'
                  200'

-------
QC data may be  somewhat  unconservative.   Average hydraulic
conductivity of "undisturbed" backfill samples tested at in-situ
stresses was approximately two times greater than that of  the
same  sample remixed, suggesting  that the hydraulic conductivities
of samples obtained  during construction may be half the  actual
hydraulic conductivity  of  in-situ backfill.   Thus, the average
hydraulic conductivity of  the  wall backfill  may be approximately
1 x 10~7 cm/sec,  the specified maximum,  rather than  5 x 10~^
cm/sec  as indicated  by the construction  data.  In addition,  the
percentage of data above 1  x 10~7 cm/sec is likely greater than
the 22  percent indicated  during construction.  Nevertheless,  the
somewhat higher average backfill hydraulic  conductivity is judged
to have little impact on wall performance.


2.5  Quality Control Guidelines


     The previous  sections have focused  on the use of  API
fixed-ring testing  and methylene blue titration for  quality
control of  soi1/bentonite  backfill.   These tests,  however,
represent only part  of  the  quality control effort required  for
cutoff  wall construction.  In  addition to further testing  of  the
backfill, the quality  control  program must also address  the
support slurry,  trench excavation,  and backfill placement,
because all of these aspects will affect  the quality of  the
finished product.   Specific  guidelines for each of these  areas
are presented in  the sections  following a discussion  of broad
guidelines to quality control testing in general.


     2.5.1  General Quality  Control Guidelines


         2.5.1.1  Test Requirements


     The quality control program  should  be  based  on  measurable
indices of. wall construction for which minimum design standards
have  been  established in the project  specifications.   The
contractor's workmanship can  then be evaluated on the  basis of
conformance to  these  standards.   Field tests used to measure
these indices must meet four criteria to be acceptable for field
quality control:

     1.  Timeliness;  QC testing must be "real  time" in nature to
        allow the timely modification of contractor1s procedures
        early  in the construction process, before inadequacies
        become pervasive and jeopardize the effectiveness of  the
        wall.   Tests  which require  several days to yield a


                            2-50

-------
         result do  not allow  early detection of a potential
         problem.

     2.   Ac curacy/Freei si on;   The tests  specified  must be
         sufficiently accurate and precise (repeatable)  to yield
         a  meaningful representation of  the measured parameter or
         property.

     3.   Simplici ty :   QC testing must be based  on simple
         equipment and procedures to allow execution in the
         field.

     4.   Low  Cost;   Testing must be inexpensive enough to allow  a
         statistically significant  number of  tests  to be
         performed.

     As  discussed in  previous  sections,  the  API fixed-ring
hydraulic conductivity test  and methylene blue tests both meet
these criteria.   Other quality control tests discussed  in the
following sections meet these criteria as well.


         2.5.1.2  Quality Control Execution


     In   the  past,  field control  has often been  the sole
responsibility  of the contractor.   This was a reflection, in
part, of performance-based specifications which indiscriminately
assign all  responsibility for satisfactory cutoff construction to
the  contractor.   However,  because the contractor's primary
interest is  in getting  the  job done,  QC  testing is  often
relegated to  a  secondary importance.   With  limited construction
staffing  when  a  construction schedule slips,  the priority  of the
contractor  shifts to increasing  production rather than quality.

     QC  testing performed by the  contractor tends to serve  as  a
check on work completed rather than a  control over work to be
done, analogous  to the  testing of concrete cylinders  during
building construction.   Therefore,  tests are often  performed
after a  substantial  portion  of work is done, too late to have  a
significant  impact  on construction.  Because the objective of
quality  control  testing is  not so much to document construction
as to identify deficiencies in  construction procedures  as early
as possible,  "check"  testing is an insufficient means of quality
control.  For quality control  testing to effectively serve as  a
control  over  construction procedures, the tests must be performed
and  reviewed on  a  timely basis,  ideally by  a  qualified
representative of the owner  (the design  engineer) rather than the
                             2-51

-------
contractor.  The engineer  as  quality  control agent provides a
number of  important advantages as compared to the contractor:

     A.  Understanding  of  Relationship  between Design and QC
        Data:

        The design engineer  has  the highest  degree  of
        understanding of  the assumptions  and  constraints under
        which  the  project was designed.  As such, he is  the most
        capable of assessing the meaning of the QC testing data.
        In addition, unanticipated  variability in subsurface
        conditions,  etc.,  which  can only be determined  via
        construction  observation,  may in  themselves appear
        inconsequential  (to the contractor) but may have a major
        impact on  overall  performance if not accounted for in
        design.  Again,  the design engineer  is best equipped to
        evaluate  this  information as it affects the specific
        construction at hand  and/or  subsequent construction
        phases.   The contractor  may  not have full knowledge of
        all  the design  considerations and  may not as  readily
        appreciate the  significance  of seemingly aberrant test
        results.

     B.  Modifications:

        Modification  of QC procedures is  relatively easily
        accomplished  by the  engineer  in  response  to
        unanticipated  contingencies.  On  the other hand, a
        contractor following QC  procedures outlined  in  the
        specifications  may not be in a position to judge what
        modifications are necessary if  unexpected contingencies
        arise.

     C.  Responsiveness:

        Inasmuch as  a  QC team of engineers is not burdened with
        responsibility for the  actual construction,  their
        efforts can be concentrated on  taking samples,
        performing tests,  and providing real time data.   If
        difficulties develop during construction, the contractor
        may  try to reallocate QC testing  manpower to activities
        directly  related  to  "getting  the  job done."  Hence,
        during precisely the period when  QC  testing may be most
        important, its emphasis may be  reduced.

     D.  Objectivity:

        If the  contractor is  responsible for QC testing,
        objectivity during  sample  selection  and test execution
        may  not exist to a sufficient degree.


                            2-52

-------
         Quality:

         If the contractor  is responsible for QC  testing,
         obtaining quality  testing equipment and  adequately
         experienced technicians  are not guaranteed.
     The contractor should do limited testing of his own,  but  it
should not be  incorporated  in  the engineer's quality  control
program.  The
use should
data.
               contractor's data should be gathered for his own
           a dispute  arise with the engineer's quality  control
     2.5.2  QC Guidelines for  Support Slurry
     During cutoff wall construction, the stability of the trench
excavation depends to a large  part on maintaining a positive head
of a bentonite slurry within the  trench.
     Design  parameters

         Unit Weight -
                      for  the slurry include:

                       the  slurry density  is  an  indirect
                       indicator  of bentonite content;  the
                       density  should be slightly higher than
                       that  of  water,  while not being so heavy
                       as  to  impede  the  movement of  the
                       advancing backfill  face.
         Viscosity
         Filtrate
         Loss
                       the  viscosity  of  the slurry  is an
                       indicator of the rate  at which the filter
                       cake  will develop  along trench walls; the
                       higher the  viscosity  the  faster  the
                       filter  cake  will  form due  to  higher
                       bentonite concentration in the slurry.

                       filtrate  loss is also an indicator of the
                       capacity  of the slurry to form a filter
                       cake  of  bentonite particles  along  the
                       trench walls.
     Because the support  slurry is ultimately displaced and  not a
permanent element of  the  completed cutoff,  its impact on wall
performance is  significantly  less than that of, say, backfill
preparation or  placement.   The  filter cake which remains does
contribute  to overall wall  impermeability,  typically having a
hydraulic conductivity of  1 x 10"^ cm/sec or less.  However, the
contribution of  the filter  cake  is  not accounted for when
                            2-53

-------
evaluating wall performance and is thus regarded as a  safety
factor.  The primary  impact of an inadequate slurry is  trench
collapse, which poses  construction problems  (i.e., delays),  but
does not necessarily  have  a long-term effect if the collapsed
section is reexcavated  properly.  Thus, the contractor will be
more concerned with a trench collapse, or the potential for one,
than the  engineer.

     Accordingly,  quality  control of the support slurry is often
the contractor's highest priority during  construction.   The
frequency of his slurry testing typically far exceeds that of
other quality control tests  because the consequence of inadequate
slurry is costly in terms  of  time lost for  reexcavation.   At  the
same time, because of the contractor's concern with construction
delays and the comparatively  low impact of  slurry quality on  the
completed wall, the engineer need not place great emphasis on
slurry testing when planning his  quality control program.

     The engineer should  include  within his quality control
program a series of tests  on slurry, but the required testing
frequency can usually be less than that adopted by the contractor.
Slurry quality control  tests include:  unit weight, viscosity,
and  filtrate loss.   Their use is described in the following
paragraphs.


         2.5.2.1  Unit Weight


     Unit weight  of  the  slurry may be determined by numerous
means of weight/volume measurements.  However, unit weight is
commonly determined using the  mud balance test, which consists of
a specially designed scale  calibrated to indicate density when
loaded with a prescribed  volume of slurry.  As indicated,  the
slurry should always have a density greater than that of water
while not being so dense as  to  impede backfill placement.

     Execution of the test is  straightforward, and  the
verification of a  minimum  unit weight  relatively  simple.   A
slurry sample obtained from the top of the trench is sufficient
to establish whether the slurry density is higher than 62.4 pcf.
Slurry unit weight  generally increases with depth, however,  due
to the slow sedimentation  of entrained  sand and,  in  certain
cases,  the  settling  of   flocculated  bentonite  particles.
Determination of maximum slurry unit weight must  then be based on
a sample obtained from the  bottom of the trench.  Collecting such
a sample  can be difficult.

     The use  of  a backhoe bucket to obtain a sample  from  the
bottom of the  trench  is generally inadequate.  By the  time  the


                             2-54

-------
bucket emerges  from the trench bottom, the slurry  in the bucket
is  most  representative  of slurry  from  the  top of  trench,
particularly  if the bucket is designed with holes to drain water,
as is common.  Therefore, alternative means  of sample  collection
must  be  used.  A  sampling device which traps  slurry  from the
trench bottom  is necessary.  Groundwater samplers with ballcheck
valves are  commercially available, but are typically inadequate
for this use.   A  slurry sample which contains  entrained  sand
particles may interfere with proper seating of the  valve.  In
addition,  if the slurry is heavy and highly  viscous,  it  will not
pass  the sampler  orifice and the  sampler will displace  the heavy
slurry.


          2.5.2.2  Viscosity


     Viscosity is determined using the Marsh Funnel test which
measures  the time  for a fixed volume of slurry  to  empty  from a
standard Marsh  Funnel.   Typically,  a minimum time  of forty
seconds  is specified  to achieve  the proper  viscosity.   A
contractor  will  try to maintain a Marsh Funnel  time as close to
forty seconds  as possible without dropping  below forty  seconds.
Because viscosity  is proportional to the  bentonite content and
barrel yield^ of  the slurry, a viscosity significantly  in
excess of the specified value is  indicative of  excess bentonite.
Because the  cost of  bentonite generally represents the highest
materials  cost,  the  contractor will seek  to  use the minimum
bentonite required.


          2.5.2.3  Filtrate Loss


     Filtrate loss  tests  are run  in  the API filter press cell.
The standard criteria for support slurry are  less than  30 cc  of
filtrate loss when  subjected to a 100 psi pressure  for  thirty
minutes.   The  tests are typically run on fresh mixed  slurry prior
to the introduction into the trench.  A test on a  sample of the
same slurry  taken from the trench would yield a  lower volume  of
filtrate due  to filtrate loss occurring in the trench.   It should
also  be added,  however,  that the filtrate loss test  is  a good
indicator of  adverse chemical effects on the slurry.  Groundwater
contaminants resulting in bentonite flocculation  would lead to a
slurry with  a  relatively high value for filtrate  loss.
^Barrel  yield is defined as the  number of 55-gallon drums of
bentonite  slurry produced by one ton of dry bentonite.
                             2-55

-------
    2.5.3  QC Guidelines for Trench Excavation
     Control aspects of slurry  trench excavation  include:

     0   trench verticality
     0   trench continuity
     0   depth of penetration  into key (aquiclude)
     0   bottom cleaning
     0   trench stability

     Quality control  of trench excavation generally receives
little  emphasis, particularly when compared with quality control
testing of slurry  and backfill.  To some degree, this is  because
the excavation process is regarded as  a relatively  common
construction operation.   This attitude also reflects the  fact
that slurry trench excavation is performed "blindly:"  there  is
no way to observe  the sides or bottom of the trench.  Another
reason is that quality control of the  trench excavation  is
largely subjective.  Aside from trench width and depth, there are
no distinct, measurable parameters.

     As compared  with  quality control of slurry or backfill,
quality control of  excavation  consists  more of a  series  of
measurements than  tests.   Methods of  evaluating  trench
verticality, continuity,  depth of penetration into key, the
condition of the bottom,  and  trench stability are discussed  in
the following paragraphs.


          2.5.3.1  Verticality


     Verticality  of  the trench  is  assessed by measuring  the
verticality of the excavation equipment.  The measurement is  best
made using a 4-foot level on  the backhoe boom or on the  backhoe
tracks.   (The backhoe typically sits on a compacted clay working
pad constructed along the trench alignment.   The pad is primarily
intended to provide stable walls at the top of  the trench).

     Verticality is not generally  regarded as a critical  aspect
of wall construction, particularly to the contractor, since the
wall does not have to be  perfectly  vertical to function  as
designed.   However,  wall  verticality  is  essential  to
post-construction investigation, particularly  if backfill  samples
are required from  the completed wall and the wall is deep.  A
small deviation of  several  degrees from the vertical at ground
surface can result in deviation of several feet at the bottom  of
a 50-foot trench.   The time  and money spent in  "finding" the wall
                             2-56

-------
at depth via  borings can be a major obstacle to post-construction
verification.

     Therefore,  a  horizontal working pad  should be maintained
during construction.   If the excavating equipment deviates by
more than  1 degree from vertical, the pad should be regroomed to
restore levelness.  If the pad is  properly established,  however,
there  should  be  little need to  regroom because there  should be
little construction activity along the wall  alignment  prior to
excavation.


          2.5.3.2  Continuity


     Continuity of the trench is  largely verified by the sweep of
the backhoe stick.  Especially along relatively straight  sections
of wall, the  action of the backhoe should indicate the continuity
of the excavation.   Problems are most likely  to arise  at sharp
bends  in the  wall  alignment.  The continuity of the trench may
be affected by  a  discontinuous, or  interrupted,excavation
procedure.  The  contractor may have to reposition his backhoe
several times  to negotiate the bend.  Each repositioning creates
a potential for a discontinuity.

     To reduce  the risk of discontinuity,  the contractor can
overexcavate one  leg  of the trench and then  start a new trench
angled anywhere  from 45 to 90 degrees from  the old.   The new
trench should  be  started sufficiently behind  the old trench to
intersect  at  full  depth.  The main disadvantage associated with
this type  of overexcavation is that backfill  placement is more
difficult  to accomplish properly.

     The quality control  engineer can  monitor trench continuity
by dragging a  rigid, vertical probe along the  trench bottom.   A
break in trench continuity will  block the advance of the  probe.


          2.5.3.3  Key Penetration


     Adequate penetration  of  the trench  into a naturally
occurring  aquiclude is fundamental to the performance of  a cutoff
wall.  Thus,  it  is critical to know at what depth the  aquiclude
is first encountered in order to determine the minimum acceptable
depth  of trench  to satisfy required penetration.  The contractor
typically  relies  on his backhoe operator to determine  when the
aquiclude is encountered and when sufficient penetration is
achieved.   The depth of the trench is then commonly checked by
                             2-57

-------
the  contractor  using  a weighted rope  calibrated  in foot
increments.

     The quality  control engineer must employ a more precise
method of measurement.  The measurement tool should be a  rigid
probe calibrated  in  foot  increments.   When the backhoe operator
indicates he has encountered the aquiclude,  a depth measurement
should  be  taken.   Verification  that the aquiclude has been
reached is a  simple  matter of  checking the trench spoil.  The
aquiclude, when probed,  should also "feel" different than the
generally coarser  soils  which  overly  it,  particularly  if the
aquiclude  is a clay or  silt.  This  first measurement  should
become the record depth to top of aquiclude even if the backhoe
may  have  penetrated 6 to 12 inches into it.  Key penetration
should be referenced to this depth.  As  the contractor continues
to excavate into the aquiclude,  subsequent measurements should  be
taken until  the minimum  specified depth of penetration  is
achieved.   The depth measurements  should be  referenced  to
pre-established stations along the wall alignment to maintain a
record of excavation depth and key penetration  depth.


         2.5.3.4  Key Cleaning


     The removal of  sediment from the  key  zone prior to backfill
placement  is important  for two  reasons.   First, the key
penetration is effectively reduced if a portion of the key zone
contains coarse sands which have sedimented out of the slurry.
The  reduced  penetration  may  jeopardize the integrity  of the
cutoff.  Second, sediment  at the trench  bottom can be pushed  as a
wave by the toe of  the advancing backfill slope to the  extent
that the sediment mounds and becomes incorporated in the backfill.
The  advancing backfill  pushes this pile of sediment until  it
becomes too heavy  to move.  The backfill then rides  over the
mound of sediment,  leaving a "window"  within the backfill.  This
is most likely to occur at a bend in the wall alignment.

     The removal  of  sediment from the  trench  bottom  is
most-commonly  accomplished by the backhoe bucket.  The quality
control engineer,  however, must have  the ability to "feel"  the
trench bottom  himself to assess  the  effectiveness of the cleaning.
This evaluation can generally be made using  a rigid probe.   Also,
the variation  in the vibration of the probe as it passes through
the  slurry and sediment  can be detected.   It is unlikely  that
this determination  can be  made by the contractor  using the
backhoe bucket because  the heavy equipment is not  sensitive
enough to detect the transition  from slurry  to sediment.
                             2-58

-------
     The probe technique can also be used to detect the build-up
of sediment  at the toe of the advancing backfill  slope.  Frequent
probing for this problem  should be incorporated into quality
control procedures.  As required,  the contractor should excavate
the mound of sediment before  it  becomes trapped within  the
backfill.
          2.5.3.5  Stability


     Stability  of  the  uppermost section of the  trench  is
relatively easy  to monitor.   Typically, a  failure  of the
excavation will be signaled  by the development  of tension cracks,
roughly parallel  to  the  trench  alignment.  The failure  itself
will consist of  a conchoidal wedge of soil which slides into the
trench.  The remedy  in  such a  case is simply  to excavate the
fallen  soil.

     Stability of the trench at greater depths,  when there may  be
no signs of failure  at  ground  surface,  is more difficult  to
assess.   The  sloughing of a  trench wall can occur below the
slurry  level and may involve  no visible movement of soil  at the
surface.  If the  sloughing occurs in a section  of the trench that
has not been completely excavated or cleaned, the  sloughed
material will  most  likely be excavated.   If the sloughing occurs
in a section of trench through which the backfill is advancing,
however, the sloughed soil  will get trapped within the backfill,
leaving a  high  hydraulic  conductivity window.

     Though  there  are  no  direct means  of assessing trench
stability  below the  slurry  level,  the quality  control  engineer
can detect sloughing  failures using an indirect approach.  This
consists of frequently  monitoring the profile of the  backfill
slope.   The backfill  should normally slump forward in the trench
on a relatively  consistent slope.  This can be verified  by
probing at intervals  along  the  trench alignment.  The frequency
of probing and  spacing will be determined on a case-by-case basis.
A sloughing failure  would deposit soil on the  backfill slope and
alter  its profile.   The  mound of  soil created by the  failure
should be detectable by  probing, showing up as  an irregularity  in
the backfill profile.  Profiling at the beginning and end of  each
working  day will allow the  timely  detection of a sloughing
failure.
                             2-59

-------
     2.5.4  QC Guidelines for Backfill


     The focal point of  the engineer's quality control program
should be the backfill.   Further,  QC  of backfill should involve a
series of tests  which  address aspects of both backfill placement
and long-term performance.

     QC tests  related to backfill  placement include:

     0   Unit Weight -  the backfill must  be sufficiently dense
                       to displace the support slurry.

     0   Slump       -  the  backfill  must  have  a high  enough
                       slump to  "flow"  into the  trench without
                       being  too fluid  and  thus  mixing with  the
                       support slurry.

     QC tests  related to long-term backfill performance include:

     0   Hydraulic   -  API fixed-ring testing is  the most direct
         Conductivity   quality control measure  to assess wall
                       performance.

     0   Methylene   -  bentonite content determination  should be
         Blue           used to supplement API fixed-ring  results
         Titration      particularly if hydraulic  conductivity is
                       too high.

     0   Gradation   -  gradation testing  during  construction is
                       perhaps  the least  critical  quality
                       control  test since  backfill components
                       and proportioning should have already
                       been  determined during design testing;
                       gradation  testing does,  however,  provide
                       an ongoing check on fines content.


         2.5.4.1  Unit Weight


     Determining the  unit weight  of  the  backfill involves a
straightforward  weight-volume calculation.   Most critical is
obtaining a large  enough sample to yield a representative unit
weight.  Thus, the size of the sample must be large relative to
the largest particle  size in the backfill.  A standard concrete
cylinder should generally suffice.

     Unit weight testing rarely has an impact  on construction
procedures.  Most backfill mixes,  whether granular or clay-based,


                             2-60

-------
will easily  satisfy  the minimum unit weight requirement with no
special effort.


          2.5.4.2  Slump


     Slump testing  of  backfill  is  performed using  the  same
procedure as  slump  testing of concrete (ASTM C-143-78).   The
minimum and  maximum slump values should be selected  based on
backfill placement  considerations.  A low  slump mix will  not
"flow"  easily into the trench  and will result in  relatively steep
backfill slopes within the trench.   The steeper the  slope,  the
greater  the probability of  a  slope  failure which could
potentially trap a pocket of slurry.  A high  slump mix will  move
easily  into  the trench  and result in a relatively flat backfill
slope.   The greatest risk of a  high slump mix  is  that  the  slurry
will not be  positively  displaced and there may  be some mixing of
the slurry and backfill.   A secondary risk is that a  relatively
flat backfill slope  will result and thus long sections of trench
will be open  for  an  inordinately long time,   increasing  the
potential for a sloughing failure.  The deeper the trench, the
more likely the chance of a failure.

     Assuming that the contractor has prepared the backfill using
the proper proportions  of backfill components, results  of  the
slump test should be used as  the main determinant of whether the
backfill  is   ready  for placement in  the trench.   It is  not
practical to wait  (even  several hours)  for  the  results of
hydraulic  conductivity results  on the backfill.  Therefore,  once
the  backfill has  achieved  an  acceptable slump  and visual
homogeneity, placement is allowed.


          2.5.4.3  API Fixed-Ring Hydraulic  Conductivity Testing


     Guidelines for use  of  the API fixed-ring  test  for quality
control  were outlined in Section 2.1.3.  To  summarize:

     0   At  the design stage and during the  early stages of
        construction the  site  specific  accuracy  of  the  API
        fixed-ring  test  should  be  assessed by comparing  APA
        fixed-ring  test  results  to triaxial   hydraulic
        conductivity results on identical backfill samples.

     0   During  construction,  samples obtained for API fixed-ring
        testing  should be transported and  placed in the test
        apparatus with as little disturbance as  possible.
        Specifically, no additional mixing  should take place.


                            2-61

-------
          2.5.4.4  Methylene  Blue Titration for Bentonite Content


     Guidelines for use of  the methylene blue test were outlined
in Section 2.2.3.   Besides  its obvious  value of determining
conformance with  specifications,  the methylene blue test should
be used to complement  API  fixed-ring  testing.  If  backfill
hydraulic conductivity  is  too high, it is necessary to identify
the reason.  Because insufficient bentonite content is the most
probable cause  of  a high  hydraulic conductivity, methylene blue
testing can be used to verify bentonite content.


          2.5.4.5  Gradation


     Gradation testing of backfill samples involves conventional
soil testing procedures.   Because  gradation specifications for
backfill are of necessity  broad,  the primary value of gradation
testing is in the  determination  of percent  fines.   As with
methylene blue  testing, gradation testing should be considered a
complement to API  fixed-ring hydraulic conductivity  testing,
particularly where API fixed-ring  tests yield unacceptable
results.
2.6  Conclusions


     The first phase of  this project focused  on the evaluation  of
two quality control procedures  for soil/bentonite cutoff walls:
API fixed-ring hydraulic  conductivity testing and methylene blue
titration for determination of bentonite content.   These
procedures were adapted for use at the Gilson Road site in 1982.
As part of the project, testing procedures were refined and
standardized for  future use.   Following assessment of  these
procedures, the quality control data obtained at Gilson Road was
reviewed  to assess conformance to specifications.  Based  on
experiences gained at the Gilson  Road site and other subsequent
cutoff  wall projects, guidelines  for  additional aspects  of
quality  control were developed.

     Major conclusions of this  phase of the research effort are:

     0   Both the API fixed-ring  hydraulic conductivity test and
        methylene blue test  are suitable  for field  quality
        control of cutoff  wall  construction; they are
        sufficiently accurate  and precise to allow a meaningful
                             2-62

-------
evaluation of future wall performance, they require
relatively short testing times,  they are relatively
simple to perform and they are relatively inexpensive on
a per-test basis.

A quantitative correlation between hydraulic conductivity
and backfill gradation characteristics did not  emerge
from a statistical  evaluation of the data obtained  at the
Gilson  Road site;  the importance of such a correlation,
however,  diminished  -over the  course of the research
effort  as the suitability of API fixed-ring testing and
methylene blue testing  was confirmed.

Hydraulic conductivity data obtained  at the Gilson Road
site indicate that project  specifications for  the
completed wall were generally satisfied; approximately
20 percent of the data were in  excess of the maximum
allowable  limit,  but by a margin deemed to have minor
impact on  overall  wall performance; the  bentonite
contents  for these samples  were generally below the
minimum specification limit, but were generally above the
required minimum based  on a design testing.
                     2-63

-------
                          SECTION 3

            WINDOW DETECTION VIA PIEZOCONE  SOUNDING
     Appropriate use of quality control field  testing allows a
high degree of  certainty  to be developed  with respect  to  the
adequacy of soil/bentonite backfill proportioning and mixing
during cutoff wall construction  (Section 2).   This,  coupled with
data obtained  during  the backfill design phase prior to
construction (Schulze,  1984),  provides confidence that the intact
backfill  will  meet  the long  term hydraulic conductivity
specifications  once  it  is  placed in the  trench.  However,
placement of the  backfill  in the trench results in a set of
inherent conditions  which  can allow entrapment of  non-backfill
material ("windows") in  the  cutoff wall.  While the intact
backfill may meet specification,  the windows are typically of a
higher  hydraulic  conductivity and  thus  degrade the overall
performance of the containment.

     The formation of windows may  result from various scenarios
such as:

     0   Sloughing of in-situ soils from the sides  of  the trench
        onto the advancing  backfill face.

     0   Sedimentation  of  relatively course material, temporarily
        suspended in the support slurry during  excavation,  onto
        the backfill face.

     0   Inclusion of pockets of bentonite support  slurry during
        slurry displacement by the backfill and

     0   Failure  of  the excavation tools to remove all the in-situ
        material and/or trench  sediment from the key profile,
        particularly when keying to the top of bedrock.

     These occurrences can be due to either geologic conditions,
such as  highly pervious open worked  in-situ  soils causing local
instabilities and thus sloughing,  or construction inadequacies
such as  insufficient or excessive backfill fluidity.

     Based  on   the  probable  mechanisms  leading to window
formation, they  are expected to  be relatively small in  size;


                             3-1

-------
hypothesized  order of magnitude less  than 10 to 100 square  feet
in profile dimension.  Despite their small size, windows can  have
a significant impact on the overall efficiency of the cutoff  wall
barrier.   This is a direct result of the groundwater mounding and
thus increased  gradient  in the vicinity  of the  barrierl
(Powers 1981).

     The  ability to  cost-effectively detect such defects is
instrumental to the verification of  successful  adherence to the
performance  specification for backfill  homogeneity should a
post-construction verification  program  become  necessary.
Furthermore,  the  demonstration of   a  capability  for
post-construction window detection may provide added incentive to
the contractor to  strive for the  highest quality of workmanship
during construction.

     The  most direct  method of window detection is to obtain
undisturbed samples of the completed cutoff wall.  A quantitative
assessment of the  hydraulic conductivity of the window material
can then be obtained via laboratory  testing.   However, due to the
anticipated small  size of a typical window as compared to the
cross  sectional  area of the cutoff wall,2 a  large  number of
samples are  required  to detect  a statistically significant
percentage of the windows.   The high unit cost  of  sample
retrieval  and laboratory testing  therefore render this solution
impractical3.

     As an alternative to direct  sampling,  the feasibility of
remote sensing geophysical techniques was considered.  Down-hole
and cross-hole techniques have gained wide acceptance by the oil
related industries.  More recently,  surface  techniques have  been
developed  for hazardous waste investigative work.  However,  much
of the current technology was  judged  to be  unacceptable  for
detection  of  anomalies in soil/bentonite cutoff walls as based on
•••The mounding and increased gradient  caused by the intact portions
of the barrier  elevate the flux through  the windows above that
which would be  calculated based on the cross-section of the
window and the  gradient which existed before barrier
construction.

^For the Gilson Road project, a 100 square foot window would
account for less than five one-hundredths of one percent of the
cross sectional area of the 4,000-foot long wall.

^Undisturbed shelby tube samples taken at 10-foot depth intervals
at 50-foot centers along the Gilson Road cutoff wall would cost
approximately $400,000 including triaxial testing.  This figure
approaches one-half the cost of wall  construction.


                             3-2

-------
theoretical  considerations.  Limitations of these techniques  are
discussed in  Appendix C.

     The  considerable experience existing in the geotechnical
exploration and  geophysical testing fields indicated that
piezocone equipment might be ideally suited for window detection.
Commercially  available instruments have been  routinely used  for
over fifteen years for foundation  design  and off-shore  work in
soft soils.   Originally developed  for stratigraphic
identification,  these instruments  provide continuous soil ..index
data as they  are advanced from the ground  surface.   Their rapid
penetration rate also offer the potential  for cost-efficient
continuous soundings at many locations along a cutoff wall.   The
primary  objective of  Phase Two was  therefore, to evaluate  the
suitability of  electronic piezocone  instrumentation for window
detection.

     The  first step in  this phase was to evaluate  the need  for
modification  of existing equipment to make  it more suitable  for
detection of windows in soil/bentonite cutoff walls (Sections  3.1
and 3.2).  The  second  step was to construct  a cutoff wall test
section  incorporating various types  of windows at known locations
(Section 3.3).  The ability of the  piezocone to detect windows in
the  test  section was then evaluated as  the third  step  in  the
research (Section  3.3).  Steps four  and five  encompassed  use of
the piezocone  in  the actual Gilson Road containment wall (Section
3.4)  and obtaining undisturbed samples of materials identified as
potential windows  (Section 3.5).


3.1  Piezocone  Operating Principles


     3.1.1 Standard Instrument Configuration


     Current electronic piezocone  instrumentation is  an outgrowth
of the  mechanical  Dutch Cone equipment used  in Europe for many
years  (Sanglerat  1972)  and the piezoprobe developed  in the early
1970's  (Wissa  1975).   The piezocone used  for this  project was
developed by Geotechniques International, Inc. and is depicted in
Figure  3-1.  The  instrument has a 60  degree  apex  angle conical
point,   3.56  cm in diameter, with a  projected area  of 10 cm2 as
based on the  Fugro design.   Overall probe length is approximately
50 cm.

     The conical point of  the instrument is connected to a load
cell  which allows measurement of the  point  resistance developed
during   sounding.   The  end of the point houses a  porous  section
                             3-3

-------
                                  FIG. 3-1  SCHEMATIC OF PIEZOCONE INSTRUMENT
U)
 I
                                            I. CONICAL  POINT  (10 cm2)
                                            2. POROUS TIP
                                            3. STRAIN  GAGES; a = POINT, b = SLEEVE
                                            4. FRICTION  SLEEVE (225cm2)
                                            5. ADJUSTMENT  RING
                                            6. WATERPROOF  BUSHING
                                            7. CABLE
                                            8. CONNECTION WITH PERMEAMETER
                                            a PRESSURE TRANSDUCER

-------
which is hydraulically connected to a pressure  transducer for
measuring excess  pore pressures generated during  the  sounding.
The  frictional and/or adhesion force on the side of  the
instrument  is measured by an independent load cell.   The load
cell is connected  to a 225 cm2 area friction sleeve which is 20
cm long and  is positioned immediately behind the point.   The data
generated   by these transducers are  transmitted  to the data
acquisition system at the  surface via  an electrical cable.
Additional description  of  the  standard piezocone,  its
development, and  application can be found in Sanglerat 1972.


     3.1.2   Instrument Modification


     As part of  this  effort,  the  piezocone was modified to
include an additional data channel for measurement  of  a  "relative
hydraulic  conductivity  index."   The rationale for  this
modification was  based on recognition that the backfill  hydraulic
conductivity was the primary parameter of interest. Furthermore,
the standard piezocone data channels for point resistance,  excess
pore pressure, and side friction primarily  respond to material
density, consistency,  and shear characteristics, rather  than
hydraulic conductivity.   Therefore, a more direct indication of
hydraulic conductivity was sought to custom tailor  the  piezocone
to soil/bentonite backfill sounding.   Inasmuch  as a  direct
measure of  in-situ backfill hydraulic  conductivity was  not
possible,  a relative quantitative  index was  considered
appropriate.

     The "permeameter"  consisted  of  a  50 micron  pore  size ultra
high molecular weight polyethylene porous  stone.   The  stone was
23 cm2  in exposed  area and was  located approximately  60 cm behind
the point  (see Figure 3-2).  It was hydraulically  isolated from
the pore pressure  transducer at the point  of the piezocone and
also from the annular space within the drill rods.   The  stone was
maintained  at a constant driving  pressure4  via a  1/4-inch
diameter nylon tube which connected the  stone to  a  pressurized
water  reservoir  at the surface.  The reservoir  was pressurized
via a precision regulator and a  tank of compressed  gas.
4The total driving pressure in the  stone was increased  as the
depth of the  instrument increased during a sounding.  The total
piezometric head  in the stone was thus maintained at  a  constant
preset level  above the total piezometric head in the  in-situ
soils surrounding the cutoff wall as  based on steady  state
hydrostatic conditions.


                             3-5

-------
                                          FIG. 3-2 SCHEMATIC OF PERMEAMETER
OJ
I
                                                 KEY:
                                                    I. PIEZOCONE
                                                    2. BOND BREAKER
                                                    3. PERMEAMETER
                                                    4. POROUS STONE
                                                    5. FITTING FOR WATER ENTRY  TO  STONE
                                                    6. 0.25 INCH  NVLON  TUBE
                                                    7. N W COUPLING TO DRILL STRING
                                                    8. PIEZOCONE  CABLE
                         NOTE: DASHED LINE INDICATES INITIAL PROFILE.

-------
     During a  sounding,  the  volume of water which exited the
stone into  the soil/bentonite backfill was monitored versus depth
of probe penetration.   Flow volume monitoring for the low  flow
rates associated with  the relatively impermeable backfill was
accomplished using a commercially  available unit which is
commonly employed for triaxial  testing  (manufactured by
Geotechniques International,  Inc., see Figure 3-3).   This  unit
records  the volume  of water which is expelled from the surface
reservoir  via a sliding  piston.  The piston travel, which is
directly proportional  to  volume, was monitored with  a  linear
direct current displacement transducer (DCDT).  The output of the
DCDT was fed into the data  acquisition system.  The rate of  flow
into the backfill  at various depths provided an index indicating
relative backfill hydraulic conductivity.  An auxiliary pressure
application/flow measuring system was also incorporated into the
equipment to monitor higher flow rates but at a reduced accuracy.
This portion of the equipment was not used due to limitations in
the rate of flow which  could be  transmitted through the porous
stone.


     3.1.3  Sounding Procedure


     To execute a  sounding, the  piezocone was pushed into the
formation via a drill rig at a constant rate of penetration (1 to
2 cm/sec).  The sounding  was  stopped at 5-foot intervals to add
drill rod.  The depth  of  the piezocone  was monitored by an
external transducer which  is connected to the drill string.   Data
output  from this transducer was  fed  to  the data acquisition
system.  The drilling  procedure  utilized during this project was
in accordance with ASTM 3441.

     Inasmuch as the permeameter portion  of the  instrument was
not  standard, procedures  for  its operation  are not covered by
ASTM.   The procedure  used is therefore described as follows.
Initially,  a determination  of the  magnitude of driving pressure
to be applied to the  stone was made.  Selection of this pressure
represents  a tradeoff between two  mutually exclusive objectives;
1) a high  pressure provides high volume flow into the backfill
which increases measurement  accuracy  and 2) a low  pressure
reduces  the probability of hydraulically fracturing the formation
or creating boundary flow along the drill string, particularly at
shallow depths.   The pressure utilized during  the project
described  her,ein was  generally  2.5 psi  for the test section
soundings and and 15  psi for the containment wall soundings.
This driving pressure  was applied to the stone prior to each
sounding  to ensure that  the  porous stone,  pressurization and
volume measuring systems were operating correctly.  The  rate of
                             3-7

-------
                    FIG. 3-3  PERMEAMETER  PRESSURIZ AT I ON/FLOW MEASUREMENT SYSTEM
             TO
        PERMEAMETER
U)
I
00
                                                                            TO COMPUTER
                                                                                TO PRESSURIZED GAS SUPPLY
                                           5  (TYPICAL)
                                                          KEY'
                            TO
WATER RECHARGE
  SUPPLY
I. 0-100 PSI REGULATOR
2. DCDT TRANSDUCER ON PISTON
3. 2X INTENSIFIER (LOW FLOW)
4. VISUAL  FLOW METER (HIGH FLOW)
5. VALVES
6. HIGH VOLUME WATER RESERVOIR

-------
flow  was recorded and compared to previous data during  each
sounding.  The  driving  pressure was maintained at  a constant
value throughout  the  sounding.   During each drill rod addition
(5-foot  intervals),  flow  to the stone was terminated and the
surface water  supply reservoir was refilled.

     Data from the three  internal  piezocone transducers (point
resistance, dynamic pore  pressure and side friction) and  the two
external transducers (permeameter flow and instrument depth)  were
transmitted  through  electrical cables  as independent 4  to
20 milliamp  analogue signals.   The signals were processed  to
digital  format  by an  Analog Devices A  to D converter.  The
digitized data  was stored directly in memory and subsequently  on
floppy disk using  an Analog Devices Mac Sym 150 Computer.


     3.1.4  Data Manipulation and Output Format


     The telemetry  data  for  point resistance,  excess pore
pressure,  local  friction and permeameter  volume  flow was
initially in  chronological format.  A data  reduction  program
then  transformed  the  data  into a depth  correlated format5-
The program also  subtracted the value of the steady  state pore
pressure at each  point  in the  formation surrounding the wall
(computed assuming hydrostatic conditions)  from the  total pore
pressure measured at  the  point of the piezocone.  Excess  pore
pressure, as  generated  by quasi-static penetration6f was  thus
computed.  In  addition, the program manipulated the independent
transducer outputs to develop composite  parameters.  These
included friction ratio (side friction  divided  by point
resistance) and A factor  (excess pore pressure divided by point
resistance).  The input data  used for these  computations was
depth correlated  and, as  such,  represented  transducer response
for the material at a given depth.
5The individual piezocone sensors, located along the  60 cm length
of the instrument, transmit data  immediately as it is taken.
Therefore,  at any instant of time, each sensor is responding to
backfill characteristics at a different depth.  To be useful, the
data from the individual sensors  must be shifted in time such
that the individual parameter values correspond to the same
backfill depth.

6As the cone penetrates the material of interest, it  generates an
excess pore pressure (a pore pressure different from  that which
existed before the sounding) due  to cavity expansion  displacement
and shearing processes.  This excess pore pressure varies in
magnitude and can be either positive or negative depending on the
material characteristics.
                             3-9

-------
     The data acquisition  system performed the above described
data reduction  on a real time basis.  As  such,  the  output was
displayed directly on  a  CRT screen to allow  the operator to
monitor piezocone  operation during the sounding.   The following
data was presented on the CRT as plotted against a depth axis:
         Point  resistance in kg/cm2
         Local  friction in kg/cm2
         Excess pore pressure in kg/cm2
         Friction ratio in percent
         A-factor in percent
     0   Permeameter volume displacement in cm3/ft

     At the end of the  sounding, a paper copy of these plots was
generated.
     Each time the sounding was  stopped to add another length of
drill rod  (5-foot  intervals),  the excess pore pressure  at  the
piezocone point  was monitored with time?.  The  excess  pore
                                          generated provided
                                         characteristics.  These
                                         on the CRT  and  then as
                                         these data  collected at
                                         when desired  by  the
pressure equilibration  behavior  thus
additional data with  respect  to material
data were initially presented in real time
hard copy.  The sounding  was  stopped and
points  other than drill  rod addition
operator.
3.2  Material Identification
     Electrical  piezocone  equipment  is well suited  for
differentiating between various soil types and thus determining
the  geologic stratigraphy  encountered during a  sounding.
Material identification is accomplished through  the use of
empirical correlations which relate transducer output to material
properties.  The  following  sections first discuss the  expected
response for  each  individual  transducer when sounding various
soil types.  It is  recognized  that each such  index, by itself,
does not provide definitive  soil identification.  However, the
discussion serves to demonstrate the characteristics and  range of
responses  to be  expected.   The  relative  output of  multiple
transducers,  producing indices such as  friction ratio and A
factor is then presented  as  related to empirical correlations
which have been developed for soil type identification.   Finally,
'The excess pore pressure is  generated by piezocone  penetration of
the material.  Therefore, once  penetration is stopped, the excess
pore pressure decays to the steady state value which existed
prior to the sounding.
                             3-10

-------
the expected  response of the piezocone  to  intact soil/bentonite
backfill and various potential window types is discussed.


     3.2.1  Point Resistance


     During  the development of  the electrical piezocone,  the
first index measured was point resistance.   This is defined as
the load required  to penetrate the point  into the material of
interest** divided  by the projected area  of the  point
(typically 10  cm2).   in addition  to the  standardization of point
area, the  point apex angle  has also been  standardized at  60°.
Penetration is controlled to a constant,  relatively  slow  rate
(1 to 2 cm/sec)  and is therefore considered quasi-static.   As
such,  dynamic  inertia effects are assumed  to  be  zero.

     The penetration  resistance  encountered by the point is
primarily  related  to the  density and  shear  strength of  the
material  penetrated.   The greater the  density and/or  shear
strength,  the  greater the magnitude of point  resistance.  This is
true for both cohesive  (clayey)  soils and cohesionless  (granular,
non-plastic)  soils.  As  such, point resistance by itself  cannot
be used to distinguish soil type.   A loose/dense sand can yield
the same point resistance as  a soft/stiff clay depending  on the
relative degree of the material density/consistency.

     In soils with  a  significant  percentage  of gravel  size
constituents,  erratic and artificially high  readings may be
obtained locally.  This typically  occurs  when the point engages a
piece of gravel, particularly one  with a  projected area greater
than 10 cm2 f  an<3 pushes it through the soil  matrix.  This problem
is alleviated  to some extent by averaging  algorithms contained in
the data reduction program9.
°The load generated  by point penetration is measured by a
transducer connected directly to, and positioned immediately
behind, the point.   In this way, forces generated by side
friction/adhesion on the aides of the instrument and the drill
string is not measured.
      the system used during this project,  the analog transducer
output is digitized at 60 hertz.  The individual digital values
are then averaged over a one-quarter second time span
(penetration depth of 1/4 to 1/2 cm) for data presentation.


                             3-11

-------
    3.2.2  Local Friction
     The  second  parameter  to be  incorporated into cone
penetrometer  instruments was measurement of local friction.
Local friction  is  defined as the vertical shear load engaged by
the friction sleeve during penetration divided  by  the  friction
sleeve area (typically 150 cm2f but 225  cm2  for the instrument
used during this project in recognition of the probable  low shear
values).  The friction sleeve is approximately 20 cm long and is
the same diameter  as the  base of the  conical  point.   It  is
located immediately behind the point as shown in Figure 3-1.   In
practice, adhesion forces are measured  as well as  purely
frictional forces.  Viscous drag forces are limited  to the extent
possible via the quasi-static rate of penetration.

     For granular,  cohesionless soils, the magnitude  of local
friction encountered during a sounding is related  primarily  to
the lateral effective stresslO and the  friction  angle  of  the
material.   The  greater the  lateral effective  stress  and/or
friction  angle,  the  larger the value of  local friction.   In
addition,  the elasto-plastic behavior of the soil affects local
friction measurements  to the extent that the lateral effective
stress is  increased via cavity  expansion upon  penetration.

    For  fine-grained clayey (cohesive)  soils,  the measured local
friction is a function of the undrained shear  strength as well  as
frictional forces to the varying extent that  the  material behaves
undrained  (shear strength)  versus drained (frictional).   For a
given point resistance, it is typically expected that a cohesive
soil will yield higher local friction values as compared to a
cohesionless soil.  As for the case of  point  resistance,  the
value of  local  friction,  in and of itself,  cannot be  used  for
definitive soil type identification.


     3.2.3  Excess Pore Pressure


    Measurement of  the excess pore pressure generated  as  the
piezocone penetrates  the  formation  is  a  relatively  recent
development.  Initially,  the  pore pressure transducer and porous
stone  system was placed in an 18° apex angle probe  and  used  for
measurement  of  steady  state pore  pressures  only.   This
instrument,  the  piezoprobe  (Wissa  1975),  incorporated  no
luThe lateral effective stress  is that portion of  the total lateral
stress that is due to forces  transmitted via inter-granular
contact.  Pore water fluid pressures are therefore not included
in effective stress (Lambe, 1969, Pg. 241).


                            3-12

-------
provisions  for measurement of point resistance or  local friction.
In fact,  no  effort was made to measure the instantaneous values
of excess pore pressure generated as the probe  was  inserted to
the depth of interest.  The probe was therefore a  reusable,  very
rapidly  responding piezometer.   The high stiffness  value for the
system allowed it to equilibrate with the formation  very  quickly
and also minimized the change  in  formation  pore  pressure in the
vicinity of  the piezometer due to  the act of  measuring  the  pore
pressure11.   This  characteristic  made it ideal  for  measurement
of rapidly  varying pore pressures  such  as exist  in  clay
formations subject  to embankment loading.

     After  initial problems with  transducer overload  from too
fast an insertion rate in soft clays, pore pressure was monitored
during insertion  to protect the transducer.   It was then noticed
that the pore pressure generated  during insertion was highly
sensitive to material type, particularly sand senses in a clay
formation or the converse.  Piezoprobe capability was therefore
expanded for use  as an aid in  stratification identification and
then incorporated  in the standard  cone penetrometer  (point and
side resistance only) to form the piezocone.

     The excess pore  pressure generated due to constant  rate
penetration  depends  on three general soil characteristics.   The
first  is the soils elasto-plastic response  to cavity expansion,
the second  is the  degree of dilatancy12 exhibited by  the  soil
in response to shear strain and the third is  the soil's hydraulic
conductivity.   While the soil's behavior is  actually a  complex
composite of the   interrelationship between these  effects, each
^Stiffness is a measure of the volume of water which must flow
into/out of the measurement system for it to respond to  a given
change in formation  pore pressure.  The larger the  volume
required, the longer the equilibration time required.  This is
particularly critical  in clayey formations where the low
inherent hydraulic conductivity places severe limits on  the rate
of flow to the piezometer.  This constraint not only applies to
equilibration time following installation, but also to the time
for the piezometer to  respond to a change in formation pore
pressure.  If the volume required for system response is high
(low stiffness) as compared to formation hydraulic  conductivity,
the response time may  be greater than the duration  of the change
in formation pore pressure.  As such, the act of measurement
changes the parameter  being measured and a true reading  is never
obtained.

12An increase in soil  volume upon shearing due to the geometric
interlocking of individual soil grains in dense soils (Lambe,
1969 Pg. 129).


                             3-13

-------
will be treated  as  if  independent in the following  paragraphs to
demonstrate  general trends (Lexadoux 1980).

     As the piezocone  instrument  penetrates a soil  mass, it
compresses  it  due  to volume displacement.   The total stress
therefore   increases in the local vicinity of the sounding.  The
magnitude  of  the  increase in total  stress  depends on  the
elasto-plastic response of the soil to  the  volume displacement
(cavity expansion).   An increase in the total stress  tends to
increase the pore  pressure above the steady state value  which
existed prior to  the  sounding.   The trend is therefore towards
positive excess  pore pressure  generation for all soil types, but
the magnitude is  soil type dependent.

     During penetration, the soil experiences severe shear strain
as well as  compression.   Shear strain also tends to  change the
pore pressure.   For  this case  however, not only is  the  magnitude
of the change soil type dependent, but so is the direction of the
change  (positive vs. negative).  The shearing process in loose
sands and  soft  normally consolidated*3 clays  tends  to drive the
excess pore pressure in a positive direction and thus  complements
compressional effects.  As such, penetration  of these materials
generates a positive excess pore pressure which is superimposed
on the previously existing steady state  conditions.  For  dense
sands  and  stiff overconsolidatedll clays, dilatancy effects
drive the  shear related  pore pressure in a negative  direction.
Hence, the  shear component of the excess pore pressure opposes
the compressional component.   The total excess pore  pressure can
therefore be either  positive or negative depending primarily on
the degree  of dilatancy exhibited by the soil  (density of sands,
degree of  overconsolidation of clays).

     As excess pore  pressure is generated due to cavity  expansion
and shearing processes, it immediately begins to dissipate to the
soil mass  surrounding the sounding.  The rate of  drainage, as
compared  to the rate of penetration,  directly  affects  the
magnitude  of excess  pore pressure attained.   Therefore,  given
that  other parameters  remain constant, a lower  hydraulic
conductivity  soil  (clays), will typically generate  a higher
excess pore pressure than a high hydraulic  conductivity  soil
(sands).    This  is  true for both positive and negative pore
pressure generation.
13A normally  consolidated soil is  one which currently  exists in
equilibrium at  a state of stress equivalent to the maximum stress
state it has  ever been subjected to.  An overconsolidated soil
currently exists at a state of stress less than that which has
previously existed  (Lambe 1969, pg. 74).


                             3-14

-------
    The  rate  of  excess pore pressure dissipation is  indicative
of soil hydraulic conductivity.   Low  hydraulic conductivity soils
drain  slower  than  high hydraulic  conductivity soils and thus the
rate of  excess  pore pressure decay  is slower.   A relative
indication of  soil hydraulic conductivity  can  therefore be
obtained by  monitoring excess  pore  pressure decay when
penetration is stopped.  This is typically done when drill rod is
added (at 5-foot  increments).   Figure 3-4 presents typical  curves
showing  excess pore pressure and rate of decay for various soil
types (Baligh, 1980).


     3.2.4 Relative Hydraulic Conductivity Index


     As indicated  in Section 3.1.2, the standard piezocone was
modified  to include a  permeameter  for evaluating  the  relative
hydraulic conductivity  of  the  cutoff wall  backfill.   This
technique had  not been used prior to this project and,  as such,
expected response could  not be determined  based on past
experience.   The following discussion  is  therefore based  on
theoretical considerations,  and is presented  in the context of
window identification.

     If  the  permeameter penetrates  a  material  of constant
hydraulic conductivity with depth, the water  take14 would  be
constant.  This  is because the driving pressure to the stone is
maintained at  a constant preset value above  the  formation  pore
pressure, independent  of  depth.  For homogenous backfill placed
as a vertical  cutoff wall,  it  would be expected that  the  in-place
backfill hydraulic conductivity  would decrease somewhat with
depth.  The decrease in hydraulic  conductivity results from
increased consolidation  stresses  and thus  density  due  to  the
weight of the  overlying backfill.  Therefore,  water take  would  be
expected  to decrease with depth in the absence of windows.   The
rate of decrease with depth would be  backfill  type dependent.

     The  response  obtained  when  penetrating  a  window depends
primarily on three  variables; 1) the hydraulic  conductivity  of
the window, 2) the degree  of  communication between the window and
the in-situ formation surrounding the cutoff wall and 3)  the  size
of the window.   As the  hydraulic conductivity of  the  window
increases, the water take would  be expected to increase.   If  the
window  is  in direct  communication  with  a  highly pervious
•^Defined  as  the volume of flow  into the formation per unit depth
penetrated.   Inasmuch as time  is not incorporated in this
correlation,  the rate of penetration must be held constant.


                             3-15

-------
                                      EXCESS PORE PRESSURE-METERS OF WATER
              co
              O
              o
              -o
              r
              o
              o
o
o
CO
m
                  3
                  CO
10
I
              X

              o
              X

              5

              TJ
              (-
              >
              CO


              o
              o
                  o
m
CO
                      s
                      CO
                      ~   rn
    m
    z
    CO
    m

    co
    CO
                                                                                            O
                                                                                            Ut
                                                                        _
                                                                        en o
                                                                        CD m
                                                                        > co
                                                                       ~_ co

                                                                        Jo "o
                                                                        ->1 O
                                                                        01 10
                                                                        — ' m
                                                                                            m
                                                                                            co
                                                                                            co
                                                                                            c
                                                                                            7)
                                                                                            m

                                                                                            o
                                                                                            co
                                                                                            co
                                                                                            TJ
                                                                          O
                                                                          z
                               DENSE/STIFF
                                        LOOSE/SOFT

-------
formation surrounding the cutoff wall, then the water taken would
increase in proportion  to the window hydraulic conductivity
(within the constraints that the hydraulic conductivity of  the
window remains  low  as compared to the formation and  the flow
required does not cause significant head loss in the permeameter
system).  However, if the window is totally contained within  the
backfill, then  water take will be limited by the rate at which
water can flow out of the window into the surrounding backfill.
In this  case,  water taken will  increase in proportion  to  the
surface area of  the window and thus window size  (within  the
constraints that the backfill hydraulic conductivity is low in
comparison to that of the window).


     3.2.5  Empirical Correlations


     Empirical correlations have been developed between piezocone
response and soil type.   These correlations are typically  based
on the relationship between a "secondary" index (local friction
or excess  pore  pressure)  and the  primary  index of  point
resistance.  These  relationships are generally expressed in a
normalized fashion.

     The  first  correlation to be developed was between  local
friction and point resistance.  In this case, the value of  local
friction was normalized  with  respect  to point  resistance
resulting in the friction ratio  index (computed as  the local
friction divided by point resistance and reported in percent).
Figures  3-5 and 3-6  present two  such  correlations  which
demonstrate that:   1) for a given point resistance, increasing
friction ratio indicates  a finer grained,  more cohesive soil  and
2) an  increasing point resistance at a given friction  ratio,
indicates a coarser  grained more cohesionless soil.

     The  second major  correlation of interest is between  the
excess pore pressure  generated  during  a sounding  and point
resistance.  One such example is presented in Figure 3-7.   In
this case, excess pore pressure has been normalized with  respect
to  steady  state  hydrostatic  pore pressure and  the point
resistance has been  normalized with respect to the total vertical
stress.  This correlation demonstrates that 1) for a given point
resistance, increasing  excess pore pressure generation indicates
a finer grained, more cohesive soil and 2) an increasing point
resistance, for a given excess pore pressure,  indicates a coarser
grained, more cohesionless soil.

     The  above correlations can be used  to define soil type on a
general basis,  only.  The standard correlations are typically
                            3-17

-------
      FIG. 3-5 MATERIAL IDENTIFICATION-FRICTION RATIO
               (DOUGLAS, 1981)
10,000
                    SENSITIVE MIXEQ
                        SOILS
   10 •*
                        2                 4
                         FRICTION RATIO{%)
             NONCOHESIVE
             COARSE GRAINED
             NONCOHESIVE COARSE
             AND FINE GRAINED
COHESIVE-NONCOHESIVE
FINE GRAINED


COHESIVE
FINE GRAINED
                               3-18

-------
     FIG. 3-6MATERIAL IDENTIFICATION-FRICTION RATIO

             (SCHMERTMANN.I977)

CM
 6
 u
UJ
o
h-
(O

(O
UJ
o:
o
a.
   100 "V
     6 i
                            345

                       FRICTION RATIO (%)
              VERY SHELLY SANDS,
              LIMEROCKS
              SAND
              SILT-SAND MIXTURES
              CLAYEY SANDS 8 SILTS
SANDY a SILTY CLAYS
INSENSITIVE, NON-FISSURED
INORGANIC CLAY
ORGANIC CLAYS a MIXED
SOILS
      NOTE: BASED ON CORRELATIONS DEVELOPED FOR THE NORTH CENTRAL
            FLORIDA GEOLOGY.
                               3-19

-------
    FIG. 3-7 MATERIAL IDENTIFICATION-EXCESS  PORE PRESSURE

             (JONES,VANZYL, 1981)
   6 nrr
 o
ZD
 I


rj
                              Ut = TOTAL PORE PRESSURE


                              Uo = HYDROSTATIC PORE PRESSURE
                              
-------
modified based on empirical  data generated for  a  local's specific
geology.   Hence  the soil  identification  curves can  vary
significantly  as  demonstrated  by Figures  3-5 and  3-6,
particularly  at low point resistance.  Therefore,  caution must  be
exercised when applying the general correlations to deposits for
which no prior data exists.


     3.2.6  Window Identification


     The occurrence of windows in completed cutoff walls and
their characterization is poorly documented.  As  such, not  only
is  there  a  lack  of  empirical  correlations  for window
identification,  but  the composition of actual  windows has not
been  investigated.   Therefore,  the following discussion  of
expected piezocone response  is based on the probable composition
and  behavior of  windows  as based on hypothesized mechanisms
leading to their formation.   An  understanding of  the response  to
be expected, as  based  on theoretical considerations, is critical
to the interpretation of field data obtained during sounding  of
the  test  section  and the  Gilson Road containment  wall  as
presented in  subsequent sections.

     The three most likely types of windows of concern are:

   '  1. Clean  granular window  -  Composed  of  either  1)
        unexcavated in-situ  formation  soils,   or  2)  on-site
        formation  soils which  sloughed off the trench wall,
        remained intact, and became entrapped in the backfill.
        In  the  first instance, it is expected that the material
        would remain unaltered with  respect  to  the  parent
        formation and thus  retain it's density and strength.   In
        the  second  case, it is anticipated that the  material
        would show  a decrease  in density  and strength.   In
        either  case,  the  window  would  contain original
        groundwater as the  pore fluid.

     2. Slurry-filled granular window - Composed of on-site
        formation  soils  entrained in  the  slurry during
        excavation  which  sediment out and contain bentonite
        support slurry as the pore fluid.

     3. Bentonite slurry window - Composed of bentonite support
        slurry  entrapped during slurry displacement  by the
        backfill.

     For each of the above windows, the expected  response  for the
four piezocone transducers will  be discussed individually in the
following sections.   This is  preceded by a discussion of expected


                             3-21

-------
response for  intact soil/bentonite backfill.  Figure 3-8  presents
a schematic representation of the expected  relative piezocone
response to backfill and windows.


          3.2.6.1  Intact Soil/Bentonite Backfill


     The soil/bentonite backfill specified for  the  Gilson Road
site consisted of a primarily sand and gravel  mixture augmented
to contain not  less  than  30 percent fines and not less than 5
percent bentonite.   The material was blended and wetted  with
trench  support  slurry until it reached a  slump of  4  to 6
inches^5.  This  plastic material was placed  in the trench with
a consistency of  toothpaste and it consolidated with time to a
soft to medium consistencyl6.

     A.   Point Resistance

         The  soil/bentonite backfill used at the Gilson Road site
         was far less dense than the existing in-situ  granular
         formations.   Point  resistance should therefore  be
         relatively low.  It was also expected  that the  material
         would behave as a plastic, rather than granular, matrix
         further reducing expected point resistance.

         With depth,  the  backfill  is  subjected  to  greater
         stresses and point resistance was  therefore expected to
         increase.   However, it  should  still remain well below
         values associated  with  the  in-situ  formation.
         Localized,  higher  point  resistance  "spikes",
         superimposed on this general trend, would be anticipated
         due to  cobbles and gravel in the plastic soil  matrix.

     B.   Local Friction

         The  absolute value of  local friction attributable to  the
         soil/bentonite backfill is again expected  to  be  much
         lower  than  that  of  the existing in-situ formation.
         Although  the backfill is plastic,  thus  indicating
         relatively  high  local  friction  due  to adhesion
         characteristics, the much greater density of the  in-situ
         granular formation results in greater frictional  forces.
-'•-'Slump was measured with a standard  concrete slump cone in
accordance with ASTM Standard C 143-78.
      consistency of plastic soil deposits are standardly rated
from very soft  to hard in accordance with data presented in  Lambe
1969, pg. 72.


                             3-22

-------
                                 FIG. 3-8 RELATIVE PIEZOCONE  RESPONSE
                    POINT
     0  PROFILE  0  RESISTANCE
                       LOCAL
                      FRICTION
FRICTION
  RATIO
U)
I
CO
EXCESS PORE
  PRESSURE
WATER
 FLOW

                                                                          m
                                                                                    «?/«
                                                                                    -.iX>*>.
                                                                                 Hi
                                                                                   & si
       S.F. 6.  -
       S.S.F.  -
SLURRY FILLED GRANULAR WINDOW
SUPPORT SLURRY FILLED WINDOW
      -  LOW DENSITY CLEAN GRANULAR WINtfOW

         HIGH DENSITY CLEAN GRANULAR WINDOW

-------
        With depth,  local  friction should increase due to the
        associated  higher state  of stress  and thus  higher
        undrained shear strength.   Although  the magnitude of
        local shear is  expected to be less  for the backfill than
        for the  in-situ  granular formation, the  value of
        friction  ratio should  be more  consistent  with the
        plastic nature of  the backfill.   Hence, the friction
        ratio  would be anticipated to  be greater for the
        backfill than the granular native formation.

     C.  Excess Pore Pressure

        The  soil/bentonite backfill is both almost completely
        granular and relatively  plastic  at the same time.  As
        such,  it  is atypical of  most natural soil deposits.
        This behavior  is due  to  the  exceptionally  high
        activity!?  of the bentonite  component.  However, by
        separating  the  two characteristics,  it can be shown that
        the  excess pore pressure generated  while penetrating the
        backfill should generally be positive.   If a completely
        cohesionless  soil  existed at  the same density as the
        backfill,  it would be considered  loose.  As  such it
        would  not exhibit dilatant behavior and thus would
        generate positive  excess pore pressures.  A  totally
        cohesive material mixed  and placed  under  the  same
        conditions  as the backfill,  would  exist under normally
        consolidated  conditions.   Again, this would indicate
        that positive excess pore pressures should be expected.
        While  the  prediction  of  positive  excess pore pressure
        generation is straight forward  as  based on theoretical
        considerations,  the magnitude  of  the expected pressures
        cannot be quantitatively  defined.   However, the excess
        pore pressures generated should be  greater for the
        backfill as compared to the formations  existing in-situ
        at  the Gilson Road  site.

        If  the  sounding is stopped, such  as during drill string
        addition,  it is expected  that the  excess pore pressure
        will dissipate at  a slow rate.  The rate of dissipation
        should be consistent with the low hydraulic conductivity
        of  the backfill  (1 x  1Q-7 cm/sec).
17Activity  is a standard  soil mechanics parameter which indicates
the degree  of plasticity  a given soil component  (typically clay
sizes)  will impart to a soil mixture, as related to the
percentage  of that component in the soil;  Lambe, 1969, pg. 34.


                            3-24

-------
    D.   Relative Hydraulic  Conductivity

        By  definition,  the water take  in  the backfill is
        expected to be consistent  with  the backfill hydraulic
        conductivity  (1  x 10~7 cm/sec).   Given the backfill
        hydraulic conductivity,  the applied driving pressure,
        and the appropriate geometries,  it is possible to
        determine,  quantitatively, the expected flow  rate.
        However, this analysis  was not performed in that the
        scope of the project was  directed toward investigation
        of  the  suitability of this  index for window detection in
        the cutoff  wall.   As  such, the effort was limited to
        establishing relative values of water take.


          3.2.6.2  Clean Granular Window


     Material composing a clean granular window would retain the
original  formation gradation.  The hydraulic  conductivity and
strength  of the window would  be  dependent  on the mechanism
leading to  its  formation.  However,  the magnitude of  each of
these parameters is  expected to remain significantly greater than
exhibited  by the intact backfill.

     A.  Point Resistance

        Point resistance  is  proportional to the strength  of the
        material penetrated.  Therefore,  it  is  expected to show
        an  increase  when  penetrating a clean granular window.
        The magnitude of  the  increase  is dependent on whether
        the window is of  low density,  such as that formed by
        material sloughing off the trench side  wall and falling
        onto the backfill, or high  density, as would be expected
        for unexcavated material.

     B.  Local Friction

        The decreased adhesion  and coarse grained nature  of the
        window,  as  compared to  the backfill,  would  tend to
        decrease the value of  local friction.   However, the
        increased strength of the window  material would increase
        the value of local  friction.  Therefore, the direction
        of  the  change in  local  friction cannot be predicted.
        However, the friction  ratio (local friction  divided by
        point resistance)  would  be expected to decrease when
        encountering  the window.
                            3-25

-------
     C.   Excess Pore Pressure

         To  the extent  that  the hydraulic conductivity  of  the
         in-situ materials are  preserved in the window,  it would
         be  expected  that excess pore pressure would  decrease
         when entering the window.  The magnitude of  the  decrease
         should be  dependent on the dilatant nature  of  the
         materials.   Therefore,  the decrease in  excess pore
         pressure  should be greater for high density windows than
         for low density  windows.

     D.   Relative Hydraulic Conductivity

         Water  take  would typically be expected to  show a marked
         increase when the sounding penetrates the window. This
         is  directly  due  to  the large  increase  in hydraulic
         conductivity for the clean granular materials  as
         compared  to  the backfill  (10-7 cm/sec).   If  a
         significant portion of  the window  is in  direct
         communication with the in-situ formation  (no separation
         by intact backfill or  filter cake), then the water take
         will be  limited only  by head loss within the permeameter
         system.  This is a direct result of the high hydraulic
         conductivity associated with the in-situ deposits at  the
         site.  However,  if the window is totally  encapsulated
         within intact  backfill, then the actual  magnitude of
         water take will  be a function of the size of the window.
         In this  case, the water take is  limited by the  flux at
         the window/backfill  interface.   Therefore, the  window
         becomes  analogous to  having a porous permeameter stone
         with an  area equal to that of  the window.   This  is
         attributable  to the disparity between window  and
         backfill hydraulic conductivities.  Even in the  case of
         a  totally encapsulated window,  water take  is expected to
         increase significantly as compared to the  intact
         backfilllS.

     Based on  the above discussion, it is anticipated  that a
clean,  granular window would most easily be discriminated using
the  parameters  of  point resistance  and relative hydraulic
conductivity.  Both indexes are expected to exhibit significant
increases in magnitude  when  the sounding encounters a window of
this type.
18The surface area of even a small window 1 Ft2 in dimension
(1,728 in2)  is over four orders  of magnitude greater  than the
permeameter  stone area (3.6 in2).
                             3-26

-------
         3.2.6.3  Slurry Filled Granular Window


     The sedimentation mechanism leading to the  formation of this
type of window should result  in uniformly graded  (poorly  sorted),
low density material with support slurry filling the void spaces.
The actual grain size of the  material comprising  the window  would
be dependent on the  gradation  of  the in-situ materials  being
excavated, the viscosity of the  support slurry,  and  the time
period between excavation and backfilling.

     A.   Point Resistance

         Due  to  the low density of the window,  it is anticipated
         that point resistance will be low.   However, inasmuch as
         the  resistance to penetration in  the  backfill is also
         inherently  low, the point resistance  may  show an
         increase  relative to intact backfill.  The magnitude of
         point  resistance in such a window is expected to be
         highly grain size  dependent.   (Slurry deposited fine
         sand would  be expected  to  exhibit  a  very  loose
         structure,  where  as a  gravel filled window  would be
         relatively difficult to penetrate.)   Therefore, the
         point  resistance for  the  window may actually be much
         greater  than  that for the  backfill  in  specific
         instances.

     B.   Local Friction

         The  slurry filled granular window is  expected to be an
         essentially granular deposit.   However, the slurry
         filling the  voids  may  impart  significant adhesion,
         depending  on its consistency and thixotropy!^.  As
         such,   local  friction  could not be predicted.  As
         indicated  above, point resistance,  as well  as  local
         friction,  cannot be predicted.   Therefore,  friction
         ratio can not be predicted.

     C.   Excess Pore Pressure

         The  low density of  the material should preclude dilatant
         behavior.   Therefore, it is  anticipated that a  positive
         excess  pore  pressure would be generated when  sounding
         through a slurry filled granular window.   The  relative
         magnitude  of  the excess  pressure compared to  that for
         the  backfill, as well  as the absolute magnitude,  is
-^Strength increase with  time at constant  composition and stress
(Lambe,  1969, Pg. 458).


                            3-27

-------
         indeterminate  with  the  existing  theoretical
         understanding.

     D.   Relative Hydraulic Conductivity

         It  is expected that  the water take for this type  of
         window would be similar to that for  a  support slurry
         filled window  (see  Section 3.2.6.4).  However,  for a
         given viscosity slurry in  the window, it  would  be
         expected  that  the water take  for the slurry filled
         granular window  would be  somewhat less than the support
         slurry filled  window.   This  results from the  added
         resistance  to  flow commensurate with the  increase
         tortuosity associated with the small  intergranular pore
         size.  In any case, the water take  is still expected  to
         be greater in the window  than in the intact backfill.

     Based on the above criteria,  it  is  expected  that a  slurry
filled  granular window will be  the most difficult to detect  of
the  three types of  windows  discussed.  However, this type  of
window is also expected to have a relatively low hydraulic
conductivity, high  stability,  and thus the least detrimental
affect  on the  overall efficiency  of the cutoff wall; except  in
special  cases.   (If the window  is  filled with gravel size
material  and  is adjacent  to a very coarse in-situ deposit, a high
gradient can  remove  the slurry  via piping20>  This will leave a
very high hydraulic conductivity  window which totally breaches
the barrier.)


          3.2.6.4  Bentonite Support Slurry Filled Window


     The  window in this  case is composed of  the bentonite support
slurry  which  has become entrapped  by the advancing backfill.   It
is hypothesized that this condition could result  if the slurry  is
allowed  to  become  too  heavy  and is  overridden rather than
displaced by  the backfill.

     A.   Point Resistance

         Inasmuch as  the window  is a  fluid, point resistance  is
         expected to be zero.  However,  a small point resistance
         may  be measured due to  the thixotropic behavior of  the
         bentonite slurry.
^uFor a definition and mechanisms leading to piping, the reader is
referred to  Middlebrooks,  (1953), and Cedergren,  (1967).


                             3-28

-------
    B.   Local Friction

         Local  friction values within a fluid are also zero.  A
         small value may be measured due to viscous drag forces
         if  the  slurry is very thick.  Adhesion forces may  also
         develop due to thixotropic effects.

     C.   Excess Pore Pressure

         Assuming  the backfill, has totally consolidated and the
         slurry window remains  intact,  the fluid pressure in the
         window  will be consistent with hydrostatic conditions.
         Inasmuch  as the slurry  is a fluid,  shear  generated
         excess  pore pressure would be zero.  Therefore,  excess
         pore pressure generation would  be  consistent with
         volumetric  displacement of the  slurry as the probe
         penetrates the window  and therefore should be positive.
         The magnitude of the  excess pore  pressure would be
         dependent on the rate  at which the "compressed" slurry
         could  permeate out of the window.  Factors influencing
         this behavior include surface area of  the window and
         thus its  size, viscosity of the slurry,  and hydraulic
         conductivity of the sides  of the  window  (either
         soi1/bentonite backfill, slurry trench filter  cake
         and/or natural formation).

     D.   Relative Hydraulic Conductivity

         The water take would typically be expected to increase
         when penetrating a slurry filled window from an intact
         backfill.   The water introduced into the window would
         pressurize the slurry  and cause the slurry to permeate
         into the  backfill.  While the viscosity of the slurry as
         a permeant is greater  than that of water, it is likely
         that the  increased  surface area (of the  window as
         compared  to permeameter stone in  direct  contact with
         backfill)  would more than offset this factor.

     Based  on the  above discussion, it is  expected that the  most
definitive indicators of a slurry filled window would be severely
reduced  point resistance and  local shear as compared to intact
backfill.
3.3  Cutoff Wall Test Section


     While the  standard  piezocone  has been  widely used for
stratigraphic investigation over the past 10  years, its technical
and economic feasibility  has  not been demonstrated for cutoff


                            3-29

-------
wall anomaly detection.   To evaluate technical  feasibility,  a
full scale cutoff  wall test  section  was constructed.   The
objective  of test section construction was to incorporate windows
of known type  and  location such  that the  response  of  the
instrument, when probing a known  condition, could be evaluated.


     3.3.1  Test Section Construction


     The test section was constructed in the northwest corner of
the  Gilson  Road containment  (see Figure  3-9)  and was
approximately  3.5  feet  wide by 24 feet long  by 21  feet deep.
Construction followed the  same methodology  as  used  during
construction of the containment cutoff wall with the exception
that windows were purposely incorporated into the backfill.


         3.3.1.1  Excavation


     Prior  to excavation, the bentonite support slurry was mixed
using Baroid National Premium  sodium bentonite,  a 90 barrel yield
Premium Grade^l bentonite (as  specified for construction of the
Gilson Road containment  wall).   The  mixing proportions  were
7 percent  bentonite in  water,  by weight.  The  water  used was
drinking water  quality spring  water.  The  support  slurry  was
placed  in a holding pond after mixing to allow complete hydration.
Marsh funnel viscosity and unit  weight quality  control  data are
presented in Table 3-1.
21In accordance with testing standards developed by  the American
Petroleum Industry, Method 13A and B  (API, 1981 and  API, 1982).


                             3-30

-------
                             TABLE  3-1

                     SUPPORT SLURRY QC DATA

Marsh Funnel Unit Weight
Sample #
1
2
3
4
Sample Location
SE Corner
NE Corner
NW Corner
SW Corner
Viscosity (sec.)
38
42
37
45
(PCF)
65.5
—
—
66.5
Notes
1
1
1
1
1.  Sample taken from hydration pond  just  prior  to  excavation,
2.  — indicates not tested.
                              3-31

-------
\
         FI6. 3-9 LOCATION PLAN
                                 I
                             3'
* — -




/\
«-*/ \
*sA
XV
\
\
\
is^oo
1
1
1
/
            \.    T*  BTEST
             X.  Sj,  | SECTION

               ^^X
            	*""V^   \ «


            ^^\ \
       LYLE REED  \ \   >• _ 
-------
     Trench excavation was  completed under slurry stabilization.
The trench remained open for only  one hour between excavation and
backfilling.   Therefore,  full  filter cake  development was
unlikely.
          3.3.1.2  Backfilling
     The backfill was composed-of  a mixture of the excavated sand
and gravel  (trench  spoil),  imported  sandy  silt borrow,  dry
powdered bentonite  and support slurry in  the same proportions
used for the Gilson  Road containment.  The mixture was blended
via  bulldozer until it  reached a uniform  consistency,  as
determined visually.   Quality control testing  data is  presented
in Table 3-2.
                            TABLE  3-2

                SOIL/BENTONITE BACKFILL QC DATA

Hydraulic4

Sample
No.
1
2
3

Slumpl
( inches)
5.5
5.5
5.0
Unit
Weight
(PCF)
123.2
124.0
125.0
Fines2
Content
(percent)
24
22
25
Bentonite^
Content
(percent)
2.8
2.6
2.4
Conduct-
ivity

(cm/sec)
1.7 x
2.0 x
2.0 x
10-7
10-7
10-7

Notes
5,6
5,7
5,8
1.  ASTM Method C-143-78
2.  Percent  passing number 200  sieve
3.  Determined using methylene  blue titration
4.  Determined using API Fixed  Ring Test
5.  Samples  taken prior to backfill placement
6.  Placed in bottom 3 foot of  trench
7.  Placed between 10 and 15 foot depth
8.  Placed at top of trench
     The backfill was placed  in  the trench one bucket at a time.
The backhoe  lowered the filled  bucket into the  slurry  to  the  top
of the backfill  surface.   The bucket was then slowly rotated to
deposit the backfill.   This  method was similar  to backfill
placement at the beginning of actual containment  construction
                             3-33

-------
(initial backfill placement until it rose above slurry surface).
However,  it does not simulate the lateral movement characteristic
of production backfill  placement  during most of the Gilson  Road
containment wall construction.  The associated backfill placement
techniques could not  be simulated on the small scale of the  test
section wall.
          3.3.1.3  Window Emplacement


     Four different types of windows were  emplaced in the test
section.   These were:  1)  a  high density clean granular window,
2) a  low density  clean granular window, 3) a slurry filled
granular window, and  4)  support slurry  filled windows.   The
design location and dimensions of these windows is depicted  in
Figure 3-10.  These dimensions were verified by measurements
along the trench axis with  a weighted  tape after placement  of
each  layer.

     It is emphasized  that the  mechanisms leading  to window
formation and  their  composition has not been  previously
documented.   The  objective of  this  effort was therefore  to
simulate  windows which  were  judged  likely to occur during actual
cutoff wall construction as  based on previous  field observations
and theoretical considerations.   These windows were constructed
using the following techniques.

     A.   High density clean granular window (HDCG)

         This  window was meant  to  simulate the  characteristics  of
         clean granular unexcavated material  (Section 3.2.6).
         The  high  density was required  to be consistent with the
         character of the in-situ formations  encountered on-site.
         This  window was the easiest to create, inasmuch as the
         unexcavated material below the bottom of  the  trench
         matches this  hypothesized type  of window perfectly.  The
         materials comprising  the window  were in direct  hydraulic
         communication  with  the  in-situ  granular  materials
         on-site.  The  profile of the trench bottom and thus the
         top of this window  is shown on Figure 3-10.

     B.   Low Density Clean Granular Window (LDCG)

         A low density counterpart to the window described above
         was also emplaced in  the test section.  The objective  in
         this  case was to  simulate  a  window formed  due  to
         sloughing of  intact portions  of  the  trench side wall
                             3-34

-------
        FIG. 3-10 TEST SECTION CONSTRUCTION PROFILE
WEST
                      EAST
       INTACT SOIL/BENTONITE
       BACKFILL

       HIGH DENSITY CLEAN
       GRANULAR WINDOW

       LOW DENSITY CLEAN
       GRANULAR WINDOW
   SLURRY FILLED
   GRANULAR WINDOW

   SUPPORT SLURRY
   FILLED WINDOW
 HORIZONTAL SCALE
SSa55HSiZ!—3
 2'   4'    6'    6'    10'
NOTE: HIGH DENSITY CLEAN GRANULAR WINDOW IS MATERIAL IN WHICH
     TRENCH WAS EXCAVATED.
                             3-35

-------
    which  retained the  existing  pore fluid  but  not  the
    existing  density.   This window would be hydraulically
    isolated from the  in-situ parent formation by the filter
    cake.

    The window  was  constructed  after  the  trench  was
    partially filled with  soil/bentonite  backfill by  1)
    placing concrete  sand  in the backhoe  bucket,  2)
    saturating  the sand with water,  3) lowering it to  the
    surface of the in place backfill,  and  4)  rotating the
    bucket  to deposit the sand.  This process was repeated
    until  a layer of material, as shown in  Figure 3-10,  was
    created.   Subsequent to sand  placement,  additional
    soil/bentonite backfill was placed over  this window
    using the same placement technique.

C.  Slurry  Filled Granular Window (SFG)

    The slurry filled granular window was meant to  simulate
    a window formed via the  sedimentation of  coarse material
    out of the  slurry  (see Section 3.2.6  for   further
    description).  In this case,  concrete sand  was  dropped
    into the top of the  slurry filled trench and allowed to
    settle  to  the  top  of  the  previously  placed
    soil/bentonite backfill.  After an appropriate volume of
    material  was placed and allowed  to settle, additional
    soil/bentonite backfill  was placed as described above.

    It is  also likely that a similar slurry  filled window
    incorporating the  in-situ granular formation material
    was, to varying extents, created at the  bottom of  the
    trench.  In all cases, a filter cake of bentonite slurry
    would  form at the trench bottom.   However, this filter
    cake would only be  about 1/4-inch thick.  A much  thicker
    slurry  filled granular  window would be created where the
    backhoe  teeth scarified the  trench  bottom  during
    excavation  and thus mixed support slurry with those
    deposits.  Where this occurred,  the window may  be 6  to
    12 inches  thick  in  vertical  dimension.   The exact
    locations of these  areas along the bottom of the trench
    were not known.

D.  Support Slurry Filled  Window (SSF)

    The slurry filled window was installed after  the test
    section was completely backfilled.   Although  this format
    does not chronologically correspond to  that anticipated
    during  actual containment construction,  it was the  only
    way window location could be controlled.
                        3-36

-------
         Two slurry filled windows were constructed, one at each
         end of  the test  section (see  Figure 3-10).   The
         installation procedure  consisted of driving a casing to
         the depth of the window and then washing out  the casing.
         A side  ported washing  bit was then inserted into the
         backfill below the casing.   Slurry was pumped out of the
         bit under high pressure to erode the intact backfill.
         The slurry,  carrying the  cuttings,  was brought to the
         surface through the annular  space between the  jetting
         tool and  the casing.   The  slurry  was recirculated
         through a sedimentation tub  and  the cuttings  removed.
         The cuttings consisted  primarily of  coarse to fine sand
         and  silt with about  10  percent  fine gravel.   The
         gravelly backfill fractions  could  not be suspended in
         the return slurry and were thus  left at the bottom of
         the cavity.

         The vertical thickness  of the windows ranged  between 12
         and 18  inches as determined  by measurement below  the
         casing.   The cavities were  expanded until no further
         cuttings were removed by  the slurry.  The lateral extent
         of the  cavities, as shown on Figure 3-10, was  estimated
         by evaluating the erosional capabilities of the slurry
         jet in the backfill at  the  surface of the test  section.


     3.3.2  Test  Section Window  Verification


     As previously stated,  the objective of the test section was
to provide a known  condition with which  to  evaluate  piezocone
response.   As such,  numerous measurements were taken  before and
after each lift of material was  placed.  These data were used to
generate  Figure  3-10.  However, once a lift was placed,  there was
no method available to ensure that it remained in position as  the
subsequent lifts were placed on  top.  Displacement of  previously
placed lifts was possible due to:

     0   Inability of the backhoe operator to "feel"  the  material
         as he rotated the bucket  to add new material.

     0   Low unit weight, low stability materials (slurry filled
         granular window)  placed below  higher unit weight
         backfill.

     0   Unknown long-term  stability  of the  window (support
         slurry filled window).

     Ideally, an independent verification method would be used to
document actual in-place conditions  in the  test  section  after  it


                             3-37

-------
had  stabilized.   Such verification  methods would include
continuous undisturbed sampling at close spacings along  the
trench alignment or complete  excavation.  While  these methods are
feasible  if performed  after piezocone sounding, the  associated
costs placed them outside the  scope of this project.

     To the extent that the piezocone response to intact backfill
and windows is unknown,  the  sounding  data cannot be used to
verify window location.   In  fact, it is  the piezocone response
which was being investigated.  However, while piezocones  have  not
previously been employed to investigate soil/bentonite backfilled
cutoff walls, theoretical considerations and empirical data from
other  applications provided  insight into expected  response
(Section  3.2.6).  The piezocone data was therefore used to  verify
window location as based on expected trends.

     The  piezocone sounding  data  was  analyzed, correlated, and
then used to construct a post-construction, as-built  test section
profile.   (The individual soundings  and window types  are
discussed in detail in Section 3.3.3.)  This profile, presented
in Figure  3-11,  reveals  some significant discrepancies when
compared  to the profile developed from construction  measurements
(Figure  3-10).  These discrepancies are discussed individually in
the following sections along with potential explanations for  the
deviations.


         3.3.2.1  High Density Clean Granular Window


     The high density  clean granular,  H.D.C.G.,  window  was
simulated by the unexcavated materials below  the trench bottom.
As such, the backfill/window interface was  the trench bottom.
The only  discrepancy found in  this case, existed at the extreme
west end of the  trench.   It  appears that the initially vertical
west end  of the trench may have sloughed off or been  dragged down
by the backhoe bucket.  The material thus raised the elevation of
the trench bottom.   This hypothesis  is supported by  point
resistance data  from  soundings GZ-9 and  GZ-10.  In  both  cases,
the magnitude of point  resistance nearly doubles at depths
corresponding to the  predicted  trench bottom.  Another  plausible
explanation is that  the trench was not excavated  to the full
depth.   However, this is not supported by the measurements taken
during construction.
                             3-38

-------
   FIG. 3-11 POST-CONSTRUCTION TEST SECTION  PROFILE
       INTACT SOIL/BENTONITE
       BACKFILL


       HIGH DENSITY CLEAN
       GRANULAR WINDOW
        LOW DENSITY CLEAN
        GRANULAR WINDOW
JPgpp$ POSSIBLE LOW DENSITY
MJS&&I CLEAN GRANULAR WINDC
               WINDOW


SLURRY FILLED GRANULAR
WINDOW
                                  0'
     HORIZONTAL  SCALE


     2'   4'   6'    8'
                 10'
NOTE I. HIGH DENSITY CLEAN GRANULAR WINDOW IS MATERIAL IN WHICH TRENCH
       WAS EXCAVATED.
     2. *  INDICATES NO DATA
                             3-39

-------
          3.3.2.2  Low Density Clean Granular Window


     The low density clean granular,  L.D.C.G., window appears to
have been successfully constructed  in  general  accordance with
Figure  3-10.  The top of  the window  is located at  the correct
elevation.  However,  it is  somewhat thicker than anticipated over
the center and eastern portions of the  trench and nonexistent at
the extreme west end  of  the trench.  It is likely that  the
material slid down  the apparently steep slope at the west end of
the trench (Section 3.3.2.1) and  increased  the window thickness
over the rest of the trench.


          3.3.2.3  Slurry Filled Granular Window


     The piezocone soundings did not detect a consistent layer
corresponding to the  slurry filled  granular,  S.F.G. window
anywhere within the trench profile.   The data indicated that the
window material probably exists as discrete  pockets located in a
random manner.

     It is hypothesized that the  layer of window material  was
displaced when the backfill was placed  on top  of  it.  The  S.F.G.
window would be more prone to  instability than the  L.D.C.G.
window because 1) it had a lower  unit weight than the  L.D.C.G.
window (probably also lower  than the backfill)  and  2)  the
material would behave  in  a  more  cohesive  manner  due to  the
bentonite slurry in the voids.   The second property  may have
allowed  the  material  to  behave  as  a  viscous  liquid during
placement of subsequent backfill lifts.


         3.3.2.4  Support Slurry Filled  Window


     Behavior of  undisturbed soil/bentonite samples  from the
completed Gilson Road containment  wall indicated that  the
material  exhibited  significant strength.  This  was further
documented during post-construction  excavation  into the  top 5
feet of the containment wall.  In this case, the backfill would
easily support a person's weight.   Based on these observations,
it was  judged that a support slurry  filled, S.S.F.,  window could
exist  in  the containment wall  and thus could probably  be
constructed in the test  section.   As described  in  Section
3.3.1.3,  two such windows were constructed  in the test  section.
Measurements made during window  installation verified that the
slurry filled cavities  were, in fact,  created.


                            3-40

-------
     Upon completion  of  the soundings, however,  it was evident
that  the  two S.S.F.  windows were  not detected in the trench
profile  at  all.  These  windows would have been easily
differentiated from other materials  in that  fluids provide no
point resistance or  local friction.  The  complete absence of
these windows elicited additional laboratory  work to arrive at a
plausible explanation.

     Laboratory  testing  indicated  that  the  soil/bentonite
backfill  does  in fact  exhibit significant  strength in  the
undrained  condition22.  However,  as drained conditions are
approached  over time, the backfill loses most  of its cohesive
strength.   The drained cohesive strength of the backfill does not
appear high  enough to  support a cavity  in the  wall via arching.
It  is therefore probable that after  the cavity was created, it
remained stable for a  short time as supported  by the relatively
high  undrained strength.  With time, the  backfill approached
drained conditions with a resulting  loss in strength.   The  top of
the cavity  then progressively failed until the original cavity
became filled.  The cavity thus propagated towards the surface of
the  trench.   Evidence  from sounding GZ-5 indicates that the
failure zone may never have reached the surface.   An  anomalous
zone was  detected extending from 5  to  8 feet deep.   In  this zone,
the friction ratio was very low for  intact backfill.  In fact,  it
corresponds to that  indicative of  a L.D.C.G window.  However, no
significant  deviation  in point resistance was  obtained as  would
be the case for a L.D.C.G. window (See Section 3.3.3.3).   This
response may indicate the presence of a very  coarse and very  low
density material  as would be anticipated based on the revealing
scenario.

     In summary,  laboratory testing of the strength properties of
the granular soil/bentoinite backfill and  field  measurements
taken during construction indicate  that the support slurry filled
windows were created during test section construction.   However,
they  would  be  expected to be a transient phenomenon.   It is
therefore  likely that they did not exist intact  at the time  the
soundings  were executed.
22Cohesive  soils behave differently depending on the  rate of load
application as compared to the rate at which the pore pressure
within the  soil can change in response to the loading.  The two
extremes  in this behavior are referred to as undrained  (rapid
loading)  and drained (slow loading).  Additional discussion can
be found  in Lambe 1969, pg.  423.
                             3-41

-------
    3.3.3  Test Section Soundings


     Prior to sounding,  the  test section was  allowed to stabilize
for a period of  three months after its construction.  In  this
way, full consolidation  of the backfill materials under their own
weight  was ensured.  In addition,  it was anticipated that creep
effects were sufficiently accounted for via this time period23.
As such, the test section should adequately model the conditions
existing in the two year  old  Gilson Road containment wall.

     Ten  soundings were conducted  in  the test  section spaced at
approximately 2 foot  intervals along the trench alignment  (see
Figure 3-11).  The soundings were executed in two phases.   The
objective of the  first  phase,  consisting of soundings GZ-1  to
GZ-6 ,  was to establish baseline data for the three  standard
piezocone  indices; point resistance, local friction and excess
pore pressure.  The second phase objective was to investigate the
behavior of the relative  hydraulic conductivity  index during  the
remaining four  soundings;  GZ-1  to GZ-10 inclusive.   The  data
obtained  for each sounding  is included herein as Figures  3-12
through 3-21.

     Before  the index values  could be established for the intact
backfill and windows,  the location of these materials within  the
test section needed  to  be established.  Depth measurements alone
were expected to provide  sufficient information  for this task as
based on  the construction profile (Figure 3-10).  However, the
discrepancies encountered between the actual  as-built profile
(sounding  data) and the  anticipated  construction profile
complicated this  process.   As discussed in Section 3.3.2,  the
test section did not  provide the expected  known condition
pursuant to window location.  Therefore, window locations  were
determined  based  on  the  sounding data and the  expected
qualitative piezocone response for the individual  window
materials.  The  piezocone response values were then quantified
once window locations were established.

     The   following subsections are organized  to first present
data for piezocone response  in the intact backfill followed by
evaluation of window induced  deviations from the  backfill indices.
The data from each sounding was correlated into a profile view of
the  test  section which summarizes detected  window  locations
(Figure 3-11).   The  variation  between  the window  locations
detected  by the  piezocone and the  initial  placement  of  the
windows during test section construction was previously  discussed
in Section 3.3.2.
        effects following consolidation typically follow an
exponential decay function.   See Lambe 1969,  pg. 419.
                             3-42

-------
SOUNDING DEPTH, FEET
 *        •        u
                                                  ro

                                                  -o
                                                  ui
                                              .' a o
                                                  g


                                                  R
                                                9

                                             Li "

-------
                                              FIG.3-13 PIEZOCONE TEST—SOUNDING NO.  GZ2
                          POINT 5TRESS-OC .K6/CH1    LOCflL FRiaiON-F ,KG/CH"  EXCESS PORE PRESS.  KG/CM1     FRICTION RRTIO-FR ,1
                                                                                                                                     H-FBCTOR ,1
                                                                                                                                                             MTER FLOV    OC
CO
 I

-------
         Sfr-E
SOUNDING DEPTH, FEET

•?•••-I-•••?
                                       'a
                                        3
          1
                                        a n

-------
SOUNDING DEPTH, FEET
•*.  • -iT-  • •  '?
                                             m
                                            ,r

-------
                                               FI6.3-I6  PIEZOCONE  TEST—SOUNDING NO.  GZ5
                            POINT STRESS-K ,«C6/CMJ   LOCH. FRiaiON-F ,K£/QP ', EXCESS PORE PRESS. KG/CM1     FRICTION RDTIO-FR .X

                                                »    •                   i   -.1         I          .1    I                   U
                                                                                                                                                              WTER FLOW    CM1
U)
 I
                        X
                        I—
                        Q_

                        a'

                        in

-------
                                       FK5.3-I7  PIEZOCONE  TEST—SOUNDING NO.  GZ6
U)
 I
CO
                     POINT STRESS-QC .KB/CM1    LOCAL FRICTION-F .KG/CM1  EXCESS PORE PRESS.  K6/CM3     FRICTION RRTIO-FR ,1
                                                                                                                                B-FRCTOR .X
                                                                                                                                                       WTER FLOW   CM1
                IDS-
,
                                                                                                                         I

-------
LJ
 I
                                                   FIG.3-18   PIEZOCONE TEST—SOUNDING NO.  GZ7

                                 POINT STRESS-OC ,KS/Ot'   LOCAL FRICTIOH-F .K/Of  EXCESS PORE PRESS. Kf/Of     FRiaiON RATIO-FR .X
                                                    It    I                   3   -.<        I         .1
R-FRCTOR «Z
                       VOTER FLOW   CM*

-------
     os-e
SOUNDING DEPTH, FEET
                                  a*
                                 .5s

-------
                                             FIG.3-20  PIEZOCONE TEST—SOUNDING  NO.  GZ9
                           POINT STRESS-OC .KG/CM1    LOOL FRiaiON-F .KE/CM1  EXCESS PORE PRESS. KG/CM9     FRICTION RRTIO-FR .X
                                                                                                                                     fl-FBCTOR
VOTER FLOW    CM'
 I
l/l

-------
        ss-e
SOUNDING DEPTH, FEET
                                     3
                                     5
                                     r "D
                                     3 R
                                     as
                                      o
                                      z
                                      in
                                      z
                                      o
                                     3

                                     3

-------
          3.3.3.1  Intact Backfill Analysis


     The first step in  analysis of the sounding data encompassed
identification  of  zones of intact backfill.   Zones  of intact
backfill were identified via visual inspection of the sounding
data as based on the following guidelines:

     0   Depth of  the  sounding as compared to  the anticipated
         placement of materials in the  test  section (Figure
         3-10).

     0   Consistency of the data with  trends  expected based on
         theoretical considerations  (Section 3.2.6.I)/ and

     0   General uniformity of the data over a given zone.

     The locations  of  intact backfill zones are summarized in
Figure  3-11.   Piezocone  response in  the backfill  was then
evaluated and average  response values for the  individual indices
parameters of point resistance,  local  friction, excess pore
pressure,  and relative hydraulic conductivity were established.

     Average  response values were determined via linear
interpolation performed directly on the graphs.  These  data  are
summarized in Tables  3-3 and 3-4.   Deviations  from these values
formed the basis for subsequent window identification.
                            3-53

-------
Notes:  1.
        2.
        3.
                             TABLE  3-3

                         INTACT BACKFILL


Sounding
Number
GZ-1
GZ-2
GZ-3
GZ-4
GZ-5
GZ-6
GZ-7
GZ-8
GZ-9
GZ-10
Average
Average
Point
Resistance
(kg/cm2)
1.3
1.2
2.0
1.3
1.3
1.2
1.0
1.3
2.8
2.1
1.5
Average
Frictional
Ratio
(%)
2.6
2.8
3.1
2.9
1.8
1.5
2.8
2.0
1.1
0.9
2.2
Excess
Pore
Pressure
(kg/cm2)
+0.2
0
—
0
+0.2
+0.1
—
—
0
0
+0.1

Notes




1






Abnormally low friction ratio (0.3)  encountered  above
zone of attempted support slurry window.   This value
omitted in average for GZ-5.
Highest and lowest values omitted from average.
— indicates data not taken.
                              3-54

-------
               TABLE 3-4




RELATIVE HYDRAULIC CONDUCTIVITY  INDEX

Material
Type
Intact
Intact
Intact
Intact
Intact
Intact
Intact
I ntact
Intact
Intact
Intact
Intact
I nt'act
Weighted
H.D.C.G.
H.D.C.G.
H.D.C.G.
H.D.C.G.
Weighted
L.D.C.G.
L.D.C.G.
L.D.C.G.
L.D.C.G.
Weighted
S.F.G.
Weiahted
Sounding
Number
GZ-7
GZ-7
GZ-7
GZ-7
GZ-8
GZ-8
GZ-8
GZ-8
GZ-9
GZ-9
GZ-9
GZ-9
GZ-9
Average
GZ-9
GZ-9
GZ-9
GZ-9
Average
GZ-7
GZ-8
GZ-8
GZ-8
Average
GZ-8
Average
Depth
(ft.)
0.
4.
8.
12.
1.
7.
9.
11.
0.
3.
6.
8.
12.

13.
14.
16.
18.

15.
15.
15.
17.

2.

5- 2
0- 7
4-11
0-13
3- 2
1- 9
8-11
2-14
0- 3
6- 6
2- 7
0-12
8-13

8-14
9-15
4-17
4-19

4-16
8-15
9-16
0-17

7- 3

.3
.4
.4
.0
.8
.7
.0
.0
.0
.2
.9
.0
.8

.7
.8
.8
.1

.4
.9
.8
.6

.3

Average
Water
Takel
cm3/ft Notes
4.
10.
15.
29.
2.
23.
20.
18.
8.
9.
2.
8.
11.
12.
111.
71.
62.
52.
74.
90.
166.
125.
166.
123.
71.
71.
9
1
9
4
9
3
4
9
2
0
6
4
8
2
1
4
5
6
0
9
7
0
7
1
4
4
                 3-55

-------
Notes:  1.  Defined as  the volume of flow  into the formation per
           unit depth  penetrated.
        2.   Weighted  average computed based  on material
           thickness.
        3.  2.5 psi driving pressure (above  hydrostatic) used for
           testing.
        4.  H.D.C.G. -  High Density Clean  Granular Window
        5.  L.D.C.G. -  Low Density Clean Granular Window
        6.  S.F.G. - Slurry Filled Granular  Window
     A.  Point Resistance

        In general,  point  resistance in  the intact backfill was
        nearly constant with depth  for  a given sounding.   The
        only exception was sounding GZ-3 (Figure 3-14) where
        point resistance increased somewhat with depth.

        The  magnitude  of average point resistance from sounding
        to sounding ranged from 1.0 kg/cm2 to  2.8 kg/cm2.  When
        the  individual averages for each sounding were again
        averaged, the value obtained for point resistance in the
        backfill was  1.5  kg/cm2.   This value fell below the
        range of  point  resistance  given  on empirical
        correlations (see  Figures 3-5 and 3-6).  As  such, the
        very low point resistance indicated  that the backfill
        was very  soft.

     B.  Local Friction

        The  values  of  local friction measured in the intact
        backfill  were very low,  typically  less than 0.05 kg/cm2.
        As can be seen on the figures,  the  standard software
        scaling factors could not provide adequate resolution
        for  measurements  in the intact backfill while still
        remaining within  scale for  the entire  sounding.
        However,  the graph of  friction ratio did  provide
        adequate  resolution.

        The magnitude  of average friction ratio for each of the
        ten soundings ranged from 0.9 percent to 3.1 percent.
        The  average friction  ratio for the ten soundings
        combined  was  2.2 percent.  The very  low value of point
        resistance  (1.5 kg/cm2)  combined  with the friction ratio
        indicated  that, although the backfill was primarily
        granular  (by dry  weight),  it behaved as a  plastic
        material  due  to the bentonite.  This  is demonstrated on
        Figure 3-6 which indicates that the backfill  is a very
        soft clayey sand/silt.
                            3-56

-------
     C.   Excess- Pore Pressure

         The excess pore pressures generated  while sounding the
         backfill were small in comparison  to the operational
         range of the transducer incorporated in the piezocone (7
         kg/cm^).   In particular,  the data magnitude was  small
         when compared  to possible errors in  establishing the
         zero point for  the transducer.  As such, the data was
         interpreted in a qualitative sense only.

         The  soundings yielded  excess pore  pressures  that
         averaged near zero or slightly  positive  (up to  +0.2
         kg/cm2)e   Spikes in the  data ranged  from a +0.6  to  a
         -0.2 kg/cm^.  Based on  theoretical considerations,  it is
         unlikely that the intact backfill should yield negative
         excess pore pressures (see Section 3.2.6.1).   It  is
         therefore probable  that either the  value used  for
         hydrostatic pore  pressure24  was too  high  or  the
         transducer zero stability was not  adequate  due to its
         high range.  However,  if an average excess pore pressure
         of +0.1 to +0.2 kg/cm2 is used  for  the backfill,  then
         the data indicate that the material  is a clayey  sand
         (see Figure 3-7).

     D.   Relative Hydraulic Conductivity

         The permeameter equipment was employed to obtain water
         take values in the backfill  as  an index of  relative
         permeability.   This equipment was used for soundings
         GZ-7 through GZ-10,  only.   The graph of water take vs.
         depth for each sounding was  divided  into regions where
         the intact backfill exhibited a uniform  rate of  flow.
         In all cases, data from the upper 12  inches of the test
         section soundings was disregarded.  This procedure was
         followed  in recognition  of the preferential boundary
         flow conditions which may have existed between  the
         piezocone drill string and the  backfill25>   The water
^4Hydrostatic pore pressure is  subtracted from the total pore
pressure measured by the transducer to compute excess pore
pressure.

25gpon insertion, it is likely  that a preferential flow channel
would form along the drill string due to boundary effects.
Higher water takes would therefore be expected due to the
communication of this flow channel with the surface.  This effect
can be seen in soundings GZ-7 and GZ-8.  Based on this data, a
12 inch zone was established where the values obtained were
considered inaccurate.
                             3-57

-------
         take  value for each zone was then established by visual
         linearization of  the curve.  This data is summarized on
         Table  3-4.   The  water take values ranged from 2.6 cm3/ft
         to  29.4  cm^/ft.   A weighted average (based  on  zone
         thickness)  of 12.2 cm3/ft was computed when all the
         intact backfill was considered.


          3.3.3.2  High Density Clean Granular Window


     The high  density granular window (H.D.C.G.) was simulated by
the unexcavated  sand  and gravel  formation  remaining below the
trench  bottom.   The data  (summarized in  Tables 3-4 and 3-5)
indicatedthat  point resistance  and relative  hydraulic
conductivity were  the  most  useful parameters  for detecting this
type of window.  The  high value  of local  friction and the low
friction  ratio also allowed discrimination between the window and
the backfill.  The response was  less abrupt,  however.  This was
probably  due to  the  20 cm length of the friction sleeve.  Excess
pore pressure, although  qualitatively useful as corroboratory
data,  provided  little  quantitative  identification.  It is
expected  that a  more  sensitive  transducer  (lower operational
range)  would provide better  performance.   The locations of
H.D.C.G.  windows within the test section are summarized in Figure
3-11.  The  following  subsections treat these  parameters in more
detail  on an individual basis.
                             3-58

-------
                            TABLE 3-5

              HIGH DENSITY CLEAN GRANULAR  WINDOW


Sounding
Number
GZ-1
GZ-2
GZ-3
GZ-4
GZ-5
GZ-6
GZ-7
GZ-8
GZ-9
GZ-10
Average^



Depth
(Ft.)
19.0-23.2
19.0-20.5
18.8-20.0
20.0-21.0
19.0-21.0
19.6-20.1
—
18.8-19.4
13.8-21.2
11.3-20.0


Point
Resist-
ance^
kg /cm ^
100
45
65
65
90
100
—
40
90
100
69


Excess

Frictional Pore
Ratio
(%)
1.0
0.6
1.0
1.0
0.6
—
—
—
0.7
1.0
0.9

Pressure Water
(kg/cm^) Take
+0.1
-0.3
_ —
-0.2
-0.1
-0.3
_ —
—
-0 . 3 Yes
-0.2
-0.1 to
-0.2

Notes






1,2,3
1,2




Notes:   1.   Friction sleeve did not penetrate window.
        2.   Permeameter did not penetrate  window.
        3.   Sounding stopped before window.
        4.   Average computed with omission of highest and lowest
            values.
        5.   Point resistance greater  than 10 kg/cm2 is off-scale
            on  figures.  Peak data taken from digital output.
        6.   —  indicates data not taken.
     A.   Point Resistance

         Point  resistance  provided a clear indicator when this
         window was encountered.  The values of point  resistance
         ranged from 40 kg/cm2 to over 100  kg/cm2.  The lower end
         of  this range is considered artificially reduced  in that
         penetration was typically terminated before full point
         resistance was reached so  as to protect the  transducer
         from an overload  condition.  The  average value of point
         resistance for the  H.D.C.G. window  was 69  kg/cm^  as
         compared to 1.5 kg/cm2 for the intact  backfill.
                             3-59

-------
B.  Local Friction

    Local  friction values for the H.D.C.G. window can only
    be established in cases where the entire friction sleeve
    penetrated  the window.   This  required  a  point
    penetration distance  of nearly  1  foot.   Therefore,
    soundings  GZ-6, GZ-7,  and GZ-8 did not provide  local
    friction data.  The average value  of local  friction
    obtained from the remaining soundings  (0.44 kg/cm2) was
    significantly above that yielded by the intact  backfill
    «0.05 kg/cm*).

    Friction  ratio  values were also computed  for the
    H.D.C.G.  window.  They ranged from 0.6 percent to 1.0
    percent  with an average 0.9 percent.  This value is less
    than one-half that exhibited by  the intact  backfill
    (average  =  2.2 percent)  and,  along  with  point
    resistance, is  indicative of a dense, coarse  grained
    noncohesive material   (Figure  3-6).    This
    classification,based  on piezocone data, agrees well with
    the visual  identification of the material.

C.  Excess Pore Pressure

    The magnitude of excess pore pressure generated when an
    H.D.C.G. window was encountered was small as compared to
    the transducer range.  In general/  however,  they were
    negative  as would be expected for a dense noncohesive
    material.  The sounding data indicated that a reasonable
    average  value was -0.1 to -0.2 kg/cm2.  This  was best
    exemplified by soundings GZ-9 and GZ-10 where over  7
    feet of  the window were penetrated.  This  value was
    further  corroborated by the other soundings with lesser
    penetration distances.  However, GZ-1, which penetrated
    over 4 feet into the window, yielded positive excess
    pore pressures.   This anomalous behavior could not be
    explained based on the available data.  A value of -0.1
    to -0.2  kg/cm2 for excess pore  pressure and  a point
    resistance of 69 kg/cm2, indicated  that the material is
    noncohesive as based  on Figure 3-7.  Again this matches
    the visual classification.

    From the  standpoint  of  window detection, it is also
    useful to examine at  the change in excess pore  pressure
    as compared to that  for intact backfill.  While the
    average value for the intact backfill (+0.1 kg/cm2) was
    not greatly different from the average window generated
    value  (-0.1 to -0.2  kg/cm2)*  the differences  for each
    sounding were more significant.  The typical  response
    was a  significant decrease in excess pore pressure at
                        3-60

-------
         the interface between  the backfill and the window.  On
         average,  this change amounted to  -0.4 to -0.5 kg/cm^ in
         the cases where the window was located immediately  below
         the backfill.  Other cases were  less definitive due to
         intervening windows of different  types.

     D.   Relative  Hydraulic Conductivity

         The permeameter  stone  penetrated the H.D.C.G.  window in
         only one  sounding.  Penetration into  the window required
         over  2  feet of  point penetration due to permeameter
         location on the  instrument.  In general,  significant
         point penetration  of  the window was not possible due to
         limited point resistance transducer  capacity.

         As shown on sounding GZ-9, the  hydraulic  conductivity
         index increased  significantly upon encountering the
         window.   Four separate determinations of water  take were
         made.  As summarized on Table 3-4, the average value was
         74.0 cm3/ft.  This  is  significantly above  the average
         value for intact backfill  of 12.2 cm3/ft.


          3.3.3.3  Low Density Clean Granular Window


     As for  the H.D.C.G.  window,  point  resistance  and relative
hydraulic  conductivity were the  most dramatic parameters with
respect  to change when encountering a low density clean granular
window.   However,  point resistance  was not  as definitive as for
the H.D.C.G.  window due to the lower density and lack  of gravel
size constituents.  While change  in friction  ratio provided good
correlation  with  point resistance  determined window location,
local friction values were too low for  discrimination  on the
graphs.  Excess  pore pressure was  useful  only in a qualitative
sense,  as was the  case for the H.D.C.G. window.

     The data  for the above parameters are  summarized  in Tables
3-4 and 3-6.   The  locations of the  L.D.C.G.  windows are  shown in
Figure  3-11.   The following subsections discuss each parameter in
more detail.
                             3-61

-------
                            TABLE 3-6

                LOW DENSITY CLEAN GRANULAR WINDOW
Sounding  Depth
Number    (Ft.)
                     Excess
Point       Friction  Pore
Resistance  Ratio     Pressure  Water
(kg/cm2)     (%>       (kg/cm2)  Take   Notes
GZ-1
GZ-1
GZ-2
GZ-3
GZ-4
GZ-4
GZ-4
GZ-5
GZ-5
GZ-6
GZ-7
GZ-7
GZ-8
GZ-9
GZ-9
GZ-9
GZ-9
GZ-10
Average

Notes :
14.7-16.2 16
16.2-17.8 4
15.3-16.2 8
14.5-16.8 17
4.4- 5.0 4
13.6-14.3 7
15.2-16.5 11
10.7-11.2 4
15.5-16.1 4
14.3-18.5 16
1.0- 1.5 5
15.4-16.8 16
15.8-17.7 19
2.3-2.8 5
4.0- 4.5 4
5.2-5.8 4
12.9-13.4 4
3.0- 4.0 6
10.3

0.4 -.1
1.0 -.1 — 1
0.2 -.2
0.7
0.9 -.3 ~ 1
0.4 -.4
0.3 - . 2
0.4 -.1 — 1
<0.2 +.4 — 1
<0 . 2 - . 2
0.9 — No 1,3
0.4 — Yes
0.5 — Yes
0.4 — No . 1,3
1.2 ~ No 1,2,3
1.2 ~ No 1/2,3
1.1 -- — 1,2,3
0.6 — ~ 1,2
0.4 0. to
-0.2
1. Potential window - does not meet point resistance
criteria, but point resistance significantly above



intact backfill.
2. Window ruled out based
3. Window ruled out based

on friction ratio criteria.
on water take criteria.
4. Average computed with omission of highest and lowest
values. Windows ruled out based on notes 2) and 3)


above also omitted.
5. — indicates data not

taken.

     A.   Point  Resistance

         Due to  the lower density and lack of gravel  sizes in
         this window, point resistance was not expected  to be as
         high  as  for the  H.D.C.G. window.  Guidelines  were
                             3-62

-------
    therefore  established  to  discriminate between a
    potential window and  the  intact backfill as based on
    point resistance alone.   Final determination of window
    existence was then based on confirmatory data  from the
    other parameters.

    Point resistance magnitudes  greater than 7  kg/cm2 were
    considered indicative of L.D.C.G. window material.   This
    boundary was established,  via  inspection of the  sounding
    data,  at five times  the magnitude previously established
    for intact backfill.   Values of point resistance which
    were less  than 7 kg/cm2,  but  were  still significantly
    greater  than the response in  the  backfill, were also
    considered subject to confirmatory  data from the  other
    piezocone parameters.

    As shown in Table 3-6,  the average point resistance was
    10.3 kg/cm2.  This value incorporated  data from  windows
    with point resistances  less  than the cutoff point of 7
    kg/cm2, but which could not be  ruled out based  on  other
    piezocone parameters.   This average is thus considered a
    lower bound average but was used  in recognition  that the
    7 kg/cm2 cutoff point  was  somewhat arbitrary.  The lower
    bound average of 10.3  kg/cm2  is still significantly
    above that generated by the intact backfill.  The abrupt
    development of these relatively  high point resistances,
    as  compared to intact backfill, provided significant
    confidence that the  L.D.C.G. windows locations  could be
    identified.

B.   Local  Friction

    The values of local friction  measured in the  L.D.C.G.
    windows were quite low,  typically  less  than 0.1  kg/cm2.
    At this  magnitude of  response,  the difference .between
    the backfill and the window could not be resolved on the
    graphs.   However, the  friction ratio provided  a better
    index  of window presence.   Average  friction ratio for
    the L.D.C.G. window was 0.4  percent as compared to 2.2
    percent for the intact  backfill.  A friction ratio  upper
    limit of 1.1 percent (one-half the average intact value)
    was  established  as  a  guideline for  L.D.C.G.
    windowidentification.

    The average value of  friction ratio,  for the  L.D.C.G.
    window combined with  an average point resistance  of  10.3
    kg/cm2,  indicated that the  material was   a loose
    noncohesive soil type(Figures 3-5  and 3-6).   This
    description,  from  the empirical correlations, agrees
                        3-63

-------
    well  with  the actual  material  type placed  as  the
    windows.

C.  Excess Pore Pressure

    The excess pore pressures generated while penetrating
    the L.D.C.G.  window  materials were typically slightly
    negative; average magnitudes ranged between -0.1  to -0.2
    kg/cm2 as was the case for the H.D.C.G. window.   It
    would  not  be  expected  that sands  existing  at  low
    relative  densities would  produce  negative excess pore
    pressures.  In fact, very loose sands, such as would be
    probable  for the L.D.C.G.  window  (deposited in a
    submerged condition),  would be  expected to generate
    slightly  positive or zero excess  pore pressures.  The
    low magnitude of the data, as compared to the transducer
    operating  range, may  have introduced a zero shift error.
    This  hypothesis would  result  in  zero excess pore
    pressure which would  be more consistent with theoretical
    considerations and past empirical data.

    Independent of the actual magnitude of excess pore
    pressure generated, the change in  this parameter at  the
    transition  from the backfill to a  L.D.C.G.  window
    provided  useful window identification data.   In  all
    cases,  the trend  was for an abrupt decrease in  excess
    pore pressure when  entering the window as would  be
    expected.   The average decrease was 0.3 kg/cm2.

    The actual  values  of negative  excess pore pressure
    generated during the soundings  indicated that  the
    material fell outside  the range  of the empirical
    material identification chart (Figure 3-7).  However,  if
    the excess pore pressures are adjusted slightly  in the
    positive direction, to account for  the hypothesized zero
    shift,  then  the empirical correlation correctly
    identifies the  sandy composition  of  the window.  Even
    without adjustment,  the  correlation indicates that the
    material is likely to be noncohesive.

D.  Relative Hydraulic Conductivity

    The permeameter was  operational  during penetration of
    two windows satisfying the point resistance and friction
    ratio guidelines previously established to identify
    L.D.C.G.  material.    In  both  cases,  the  relative
    hydraulic conductivity index increased markedly.  Four
    separate determinations of water take were made in those
    two windows as summarized on Table 3-4.  The water take
                        3-64

-------
        values ranged from 90.9 to  166.7 cm3/ft. with a weighted
        average of  123.1 cm3/ft.

        The  average value of  relative hydraulic conductivity
        obtained for the  L.D.C.G. windows were an order of
        magnitude  greater  than that  representing the backfill
        (12.2 cm^/ft.).  As such, identification of  these more
        permeable zones  was  straight forward.  The  relative
        hydraulic conductivity index was therefore also used to
        rule out marginal spikes in  point resistance from
        further consideration as potential windows.


         3.3.3.4  Slurry Filled Granular Window


     The slurry filled  granular windows were most easily
identified based on  the combination of  high point resistance and
high local friction, as compared to  the intact backfill.  The
relative hydraulic conductivity  index  increased markedly  in the
S.F.G. window, but only one determination of its magnitude was
made.   Excess pore pressures typically  exhibited negative  trends
but the magnitudes were low compared to the operating range of
the  transducer.   Excess pore pressure was thus   used as a
qualitative index only.

     The individual sounding data  for the S.F.G.  windows is
summarized on Table 3-7.   The  locations of the windows are
presented  on Figure  3-11.   The response of  the   individual
piezocone indices is described in further detail in the following
sections.
                            3-65

-------
                            TABLE  3-7


                 SLURRY FILLED  GRANULAR WINDOW
Sounding  Depth
Number    (Ft.)
                     Excess
Point      Friction  Pore
Resistance  Ratio     Pressure  Water
(kg/cm2)    (%)       (kg/cm2)  Take   Notes
GZ-1
GZ-1
GZ-2
GZ-2
GZ-2
GZ-4
GZ-5
GZ-6
GZ-6
GZ-8
GZ-8
GZ-8
GZ-9
GZ-10
Average*
10.8-12.4
18.2-19.0
4.3- 5.3
5.7- 6.0
7.5- 8.7
3.4- 4.0
3.4- 3.9
3.7- 4.8
18.5-19.5
2.7- 3.6
4.7- 5.2
17.9-18.6
11.3-12.5
10.2-11.1

25
12
5
4
6
10
5
17
18
7
5
30
10
10
11.4
>10
>10
>10
1.5
7
>10
>10
>10
6
8
7
>10
5
9
7.9
-.3
0
-.2
-.1
-.1
-.1
-.5
-.2
-.2
—
—
—
-.4
-.3
-0.2

3
1
1,2
1
—
1
—
3
Yes
1
3
—
3

Notes:   1.  Potential window - does not meet point resistance
           criteria.
        2.  Window ruled  out based on friction  ratio criteria.
        3.  Filter  cake  and/or formation soil mixed with slurry
           by bucket teeth  at trench bottom.
        4.  Average computed  with omission  of highest and lowest
           values.   Windows  ruled out based  on Note  2) above
           also omitted.
        5.  — indicates  data  not taken.
     A.   Point Resistance

         The  point resistance encountered when  penetrating the
         S.F.G.  window was similar to  that for  the  L.D.C.G.
         window.   The average value computed was  11.4 kg/cm2 as
         compared  to  10.3  kg/cm2 for the L.D.C.G. window.   The
         range  of  point resistance obtained from  the individual
         windows was also comparable.   This result was expected
         based on  the similar  composition and  depositional
                             3-66

-------
        methods  used to construct the windows.  The same point
        resistance guidelines established to identify L.D.C.G.
        windows were therefore also adopted for this  window
        type.

     B.  Local Friction

        The magnitude of  local  friction generated when
        penetrating the S.F.G. window was often greater than 0.1
        kg/cm2 with an average value of 0.2  kg/cm2.  This value
        was high as compared  to that for intact backfill and the
        L.D.C.G.  window.  The high average  local  friction for
        the  S.F.G.  windows  did  not produce friction  ratios
        significantly greater than the  intact backfill  at the
        point of maximum point resistance.  In fact, the average
        point resistance and  average  local friction  values
        combine to  yield an  average  friction ratio  of 1.8
        percent.   This is  identical  to  that for the  intact
        backfill  (2.2 percent) to within  the accuracy  of the
        data.  However, high  friction ratios were typically
        detected immediately  above and below the peak in  point
        resistance.   This behavior was  not  evident  for  any  of
        the other  test section materials.   It is hypothesized
        that the  point resistance,  when initially entering a
        S.F.G. window, was  low due to lack of  confinement  by the
        soft,  plastic backfill.  This would also  be true when
        the point  approaches the bottom of the window26.  The
        local friction, however, would  be high over the  entire
        window thickness due  to the adhesion attributed  to the
        bentonite  filling the soil voids.   Therefore,  friction
        ratios would be high entering and exiting  the  S.F.G.
        windows.

        A  friction ratio of greater than 5 percent was  required
        for  high point resistance to  be considered a  S.F.G.
        window.   The friction  ratio reported  for this window was
        the highest value recorded when the window was entered
        and  exited.   The thickness of the window summarized  on
        Table 3-7 also reflected the occurrence of high friction
        ratio in the context  of the above hypothesis.

        The  above  data yielded an average friction ratio  of
        7.9 percent for the top and bottom of the window  and  an
        average  value of 1.8 percent at the  location of maximum
        point resistance.   An average  friction ratio  of 7.9
        percent,  in conjunction with an average point resistance
        of 11.4 kg/cm2, indicated that the window material is a
       hypothesis is supported by the behavior  of end bearing piles
in multilayered systems (Poulos, 1980).


                            3-67

-------
    mixed soil type as per Figure 3-6.  The lower average
    friction ratio (1.8 kg/cm^) yields a loose sand material
    identification.  Both classifications are supported by
    the material type used to construct the window.   The
    important point,  however, is that a S.F.G. window yields
    a consistent piezocone signature  and thus can  be
    identified.

C.  Excess Pore Pressure

    Excess  pore pressures generated when sounding a S.F.G.
    were  similar to those representing  the L.D.C.G. window,
    but somewhat more negative.  The average value was -0.2
    kg/cm^.   The change  in  excess pore pressure at  the
    transition from the  backfill to  the window was also
    typically abrupt and in the negative direction.   The
    average  change was -0.5 kg/cm^.  Again, the magnitude of
    the change was greater for the S.F.G. window than the
    L.D.C.G. window.

    General discussion  of  the excess pore pressure
    generation behavior  in loose sand  materials applies to
    the S.F.G. window as well as the L.D.C.G. window.  This
    discussion is found in  Section 3.3.3.3.  An explanation
    for the  greater negative response in the S.F.G. is not
    possible given the available data.

D.  Relative Hydraulic Conductivity

    The permeameter penetrated only  one slurry filled
    granular window.  Upon entering the window,  from  the
    intact  backfill above, the water take abruptly increased
    from 2.9 cm3/ft. to 74 cm3/ft.  As  shown  in  the  GZ-8
    sounding data (Figure  3-19), the water take maintained a
    constant rate until  the permeameter pressurization
    reservoir emptied and required refilling.

    The water take obtained in the S.F.G. window was high as
    compared to the intact backfill  as would be expected.
    However,  it was  also approximately 60 percent of the
    value obtained for the  L.D.C.G. window.  Given that both
    windows  were constructed of the  same soil material
    (concrete sand), the difference in water  take can be
    attributed to two differing conditions.  The first
    concerns  pore fluid.   The  S.F.G.  window contains
    bentonite slurry in the void spaces which  is  about 40
                        3-68

-------
         percent  more viscous than clean water27^   qi^e  second
         condition  relates  to window  size.   As previously
         indicated,  the water take for a window totally entrapped
         in  intact backfill will be related to  the flux through
         the window/backfill  interface  (Section 3.2.6.3).  The
         available data, as summarized on Figure 3-11,  indicated
         that the L.D.C.G.  window was probably  significantly
         larger than the  S.F.G. window.   Both  of  the  above
         conditions  should result in a  decreased relative
         hydraulic conductivity index for the  S.F.G.  window as
         compared  to the L.D.C.G.  window.


          3.3.3.5  Support Slurry  Filled Window


     As discussed in  Section 3.3.2.4,  the  support slurry filled
window was  not  detected.  It is hypothesized  that the slurry
filled cavity collapsed prior  to the piezocone soundings.


     3.3.4  Window Identification  Guidelines


     Based on the data obtained  from the test section soundings,
a set of  general  guidelines  were developed to quantitatively
model the  signature corresponding to  each  type  of window
investigated.  These guidelines were formulated  as  deviations in
the piezocone indices obtained when sounding a window as compared
to average  values  obtained in  the intact backfill.   These
guidelines,  summarized below  by individual window type, were used
to analyze the containment wall soundings for  potential window
locations.

     It is emphasized that zones labeled as "potential windows"
were identified based solely on deviations in piezocone indices
as  compared to values  associated with intact backfill.  Without
confirmatory data, the existence  of an actual  window  cannot be
determined.  Furthermore, the impact of the potential windows on
overall containment  wall effectiveness cannot  be evaluated as
based on  piezocone data.  Such evaluations can only be made by
hydraulically stressing the cutoff wall and analyzing  its effect
on the hydrologic response of the aquifer/aquiclude system.   This
work is discussed in Section 4.
  As determined via marsh funnel testing.  The support slurry used
exhibited a marsh funnel of  approximately 41 seconds, where as
clean water has a marsh funnel viscosity of 29 seconds.


                            3-69

-------
     It  should  also be recognized that  the test section upon
which the following guidelines were  based  was constructed to
model the type  of  backfill used at the  Gilson Road site.  The
test section backfill was therefore  a granular soil/bentonite
type mix^S.  other types of soil/bentonite mixes, or different
backfill types all together (cement/bentonite for example), would
not be  expected  to follow the same guidelines.


          3.3.4.1  High Density Clean Granular Window

     0    Point  resistance greater  than twenty times that for the
         intact  backfill.

     0    Point  resistance  consistent with the known material
         type,  strength,  and density of  the in-situ native
         formation  (values > 30 kg/cm^  for the Gilson Road site).

     0    Friction ratio  less  than  one-half  the value obtained  in
         the  intact backfill.

     0    Reduction in excess pore pressure from values associated
         with the intact backfill (to near zero or negative).

     0    Relative hydraulic  conductivity index greater than  five
         times that for the intact backfill.


          3.3.4.2   Low Density Clean Granular Window


     0    Point resistance greater  than five times  that for the
         intact  backfill.

     0    Friction ratio  less  than  one-half  that corresponding  to
         the  intact backfill.

     0    Reduction  in  excess pore  pressure to  a  near  zero
         magnitude.

     0    Relative hydraulic  conductivity index greater than five
         times that  for the intact  backfill.

^8Soil/bentonite backfills can be separated into granular or clayey
type mixes.   Granular  mixes are those composed primarily of
noncohesive materials  (by dry weight) which rely heavily on small
percentages of bentonite  to achieve  low hydraulic conductivity.
Clayey mixes  contain high percentages of plastic materials which
reduce the backfill hydraulic conductivity to low values prior to
bentonite augmentation.


                             3-70

-------
          3.3.4.3  Slurry Filled Granular Window


     0    Point  resistance greater than five times  that  for the
         intact backfill.

     0    Relatively  high local  friction values, greater  than
         twice the intact backfill magnitude.

     0    Friction ratio greater than twice the  intact backfill
         value upon entering and exiting the window.

     0    Reduction  in excess  pore pressure to  a  near  zero
         magnitude.

     0    Relative hydraulic conductivity index greater than five
         times that for the  intact backfill.


          3.3.4.4  Support Slurry Filled Window


     This type of window is not expected to remain stable in  a
granular  type soil/bentonite backfill such as  used at the Gilson
Road site.  However,  this  window  type, if  existing in a cutoff
wall, would be easily identified  through a  lack of significant
point resistance or local friction.


3.4  Containment Wall  Soundings


     Thirteen soundings  were  executed in  the Gilson Road
containment wall  after completion of the test section trial
soundings.  Five of the soundings (GZ-11, GZ-12, GZ-13, S-2E,  and
S-10) were concentrated in two  areas where  windows  were most
likely to exist.  The  first area (Station 1+00) was the location
                            3-71

-------
of the deepest part  of the containment wall.   The second area
(Station 3+45) coincided with the occurrence  of a localized
trench  instability encountered  during construction^.  The
remaining eight soundings were distributed along the downgradient
portion of the containment wall.  The individual locations of
these soundings are provided in Figure 3-9.

     The containment wall  soundings were executed in two phases.
The first phase  (GZ-11, GZ-12, and GZ-13) followed immediately
after the test section soundings.  The second phase was delayed
for  approximately one  month to  allow modification of  the
permeameter equipment^.

     In  general, the containment wall soundings exhibited  trends
similar  to those  corresponding to the intact  backfill zones in
the  test  section.   Deviations  in piezocone  response from the
intact backfill values were also noted in some  cases.  At depths
where deviations were  noted in  one piezocone index, the other
indices  were examined to identify signatures  resembling window
data from the test  section.  The windows were analyzed based on
the guidelines established during the test section soundings
(Section 3.3.4).

     An  example sounding is analyzed in the following subsections.
This sounding corresponded to the deepest portion of the cutoff
wall  (Section 1+00).  This area was selected for investigation
due to  the  100  foot depth of  the wall and  thus  the  higher
potential for windows.  Of the three soundings performed in  this
         excavation, a 2 inch wide,  50 foot long, conchoidal  shaped
crack developed at the surface 15 to 20 feet behind the trench.
It is hypothesized that this resulted from slurry loss into an
esker deposit  with the associated local instability at depth.
Slurry was pumped to the trench from the two slurry ponds
constructed in recognition of the esker deposits.  The excess
slurry head and overall stability was thus maintained.
Thirty-six inch diameter pipes were  then inserted into the trench
to provide added support.  The trench bottom was recleaned and
the trench was backfilled.

^Initially, the permeameter porous  stone was the same diameter  as
the drill string.  The potential for preferencing boundary flow
along the drill string was recognized during test section work.
A step taper was therefore added to  the design  (Figure 3-2).   In
addition, it was found that a large  permeameter
pressurization/volume measurement reservoir was required.  This
equipment was  also modified prior to the final phase of
soundings.


                             3-72

-------
area, GZ-13 exhibited the most complete  record31  ana also
provided the greatest  variety of  response.   The record  for
sounding GZ-13 is provided as Figures 3-22a and 3-22b.


     3.4.1   Intact Backfill; Sounding GZ-13


     The point  resistance  encountered  in  the soil/bentonite
backfill exhibited a nearly constant trend at 2 kg/cm2  to a depth
of 50 feet.  From  50 feet to  the bottom  of  the sounding at 95
feet, a linearly increasing point  resistance to 4 kg/cm2  was
evident.  This data compared favorably with that developed  during
soundings in the test section  (test section  point resistance =
1.5 kg/cm2).  In fact, a trend of  increasing point  resistance
with depth  better  follows the theoretical  trend for a uniform
material.

     Local  friction typically  averaged 0.1 kg/cm2 with a slightly
increasing trend towards the bottom of the  sounding.  This value
is somewhat higher than that  established during the test section
soundings «0.05 kg/cm2).   The  proportionally higher  local
friction,  as compared to point resistance, also  yielded a
somewhat higher friction  ratio  of 3.0 to  3.5 percent  (test
section = 2.2 kg/cm2).  The point  resistance and friction ratio
values indicate that the material is a sandy/silty clay as based
on the empirical identification charts (Figure  3-6).

     Excess pore pressures generated  during  sounding GZ-13 were
significantly higher than observed in the  test section (0.2
kg/cm2).  The average  magnitude  ranged from 0.6 kg/cm2 to 1.0
kg/cm2, with the higher  values  encountered over the bottom
section of  the wall.   These larger excess pore pressures  are in
better agreement with theoretical considerations than the data
from the test section.  This lends a higher degree of  credibility
to the hypothesis  that the  low,  sometimes  negative,  average
excess pore pressures  may have been due  to an inaccurate zero
value.  Figure  3-7 indicates  that  the material behaves as a
clayey sand or a silty  clay, as based on the excess pore pressure
and point resistance indices.

     Relative  hydraulic conductivity values  for  the  intact
backfill averaged 7.6  cm3/ft.,  within a range of 4.5  cm3/ft. to
11.5  cm3/ft.  With  the exception of a  few higher hydraulic
conductivity ?ones,  (potential windows)  the water take values
31The excess pore pressure  transducer failed during sounding  S2E
and the point resistance transducer failed  in sounding S-10.


                            3-73

-------
                                          FIG. 3-22o   PIEZOCONE TEST—SOUNDING  NO.  GZ13

POINT STRESS-OC .KG/CH1     POINT STRESS-OC -KG/CM3    LOCAL FRICTION-F .KG/CM*    PORE PRESSURE-U .KB/CM1    FRICTION RBTIO-FR ,Z

                                          .	y
                                                                                                                                             fl-fRCTOR
    UJS
    UJ
    U_
CO    ».
                                                                                                                                                                    WRTER FLOW    CM*
                                                                                                                                                                \

-------
                                                   FK3.3-22b PIEZOCONE TEST—SOUNDING  NO.  GZ13
       POINT STRESS-OC .KG/CM1    POINT STRESS-OC .KB/CM*   LOCH. FRICTIOM-F .KG/CM'    PORE PRESSURE-U .KG/CM*     FRICTION RRTIO-FR ,Z
                                                                                                                                            A-FACTOR .1
                                                                                                                                                                   VRTER FLOV   Or
m z
   Si

-------
were relatively  consistent.  It should  be noted that the  head
loss across  the porous stone increased during the test section
and containment  wall soundings.   The increase was due to smearing
of the high  density polyethylene  stone and  internal  surface
loading due  to suspended solids (iron precipitate) in the water.
Driving pressures were therefore  increased after the test section
soundings to maintain adequate flow rates.   As such, the water
take values  are  comparable within a  given  sounding  but  not
generally from sounding to sounding (the  same driving pressure
was used for  all  test section soundings).


     3.4.2   Potential Window Locations, GZ-13


     Sounding GZ-13 exhibited signatures  which  corresponded to
all three types of potential windows detected in the test section.
These are the high  density clean  granular  (H.D.C.G.) window, the
low density  clean  granular (L.D.C.G.)  window and  the  slurry
filled granular (S.F.G.) window.  Each window type will be
discussed individually below.

     A.  High Density Clean Granular Window

         The occurrence of  this window type is most likely to be
         the  result of incomplete excavation of native formation
         materials.  This is particularly true of sites where the
         cutoff wall has been keyed  to the top  of bedrock  as was
         the case at Gilson Road.   Incomplete excavation to the
         top of  bedrock typically results when the scale  of
         bedrock  surface convolutions  is  small  relative  to the
         size of  the excavation
         As based on the previously established guidelines,  it
         appears that sounding GZ-13 encountered native formation
J^At the Gilson Road site a great deal of  quality control was
exercised to ensure excavation to the top  of bedrock.  Quality
control procedures included excavation until no additional
material could be removed, verification as based on borings at
100 to 250 foot spacing, and re-excavation just ahead of the
advancing backfill face to clean the key (Ayres, 1983).  During
excavation,  bedrock, as identified via fracture plane and
lithology, was typically removed from the  bottom of the trench
for visual inspection.  However, it is likely that occasional
small pockets of glacial till remained in  the smaller bedrock
convolutions after backfilling.  The specification required air
lifting to clean these pockets but it was  not enforced due to the
enhanced potential for side wall instability which air lifting
would induce.
                             3-76

-------
        material at  a  depth  of  88.5 feet.  In this  location the
        point  resistance increased  to over  50 kg/cm2  and
        friction ratio  decreased to  about  1  percent (intact
        backfill values of 2 to 4 kg/cm2 and 3.0 to 3.5 percent,
        respectively).  Excess  pore pressure  dropped from an
        average value  of +1.0 kg/cm2^ in the  backfill  to an
        instantaneous low of <  -0.6 kg/cm2  upon encountering
        this zone.  The  relative hydraulic conductivity index
        peaked in this  zone at  a maximum value  of 40 cm3/ft.
        (average value  in intact  backfill of 7.6 cm3/ft.).  With
        further penetration, the  point resistance fell off
        dramatically (8  kg/cm2)  the  relative  hydraulic
        conductivity  index decreased  (7.4  cm^/foot) and the
        excess pore pressure increased to positive values (+1
        kg/cm2).   After  three additional feet of penetration,
        this trend was  again  followed by  high point resistance
        (40  kg/cm2),  markedly  increased relative hydraulic
        conductivity  (100  cm^/ft.)  and decreased excess pore
        pressure  (+0.2 kg/cm2).   The only inconsistent parameter
        was  friction  ratio  which continued  to decrease in a
        linear fashion.

        The  piezocone  data,  in  and  of  themselves, indicate  that
        the  cutoff wall was not constructed to the  top of
        bedrock.   As  based  on a penetration of this material of
        over 6 feet,  the  data further indicated that bedrock is
        at  least-33 that distance  below the  wall.  However,
        another explanation  for  the data exists  which is more
        consistent with  the quality  control data obtained during
        construction  as  well as the  piezocone  data.   It is
        hypothesized  that the sounding penetrated the  side of
        the  cutoff wall  and then proceeded into the  native
        formation.   It is further hypothesized that this  was due
        resistance did not indicate bedrock was encountered.  The
sounding was terminated when enough down pressure was applied to
lift the drill rig off the ground.  This is not reflected  in the
point loads because a significant portion of the penetration
resistance was likely to have been mobilized at the enlarged
shoulder corresponding to the drill string (see Figure 3-2).


                            3-77

-------
        to a  non-vertical cutoff wall rather than  an inclined
        sounding-^.   The  following  data  support  this
        conclusion:

        After excavation, the  slurry  trench was  sounded  to
        determine its depth  and  a measurement of 102  feet was
        obtained  at  station 1+00.  This depth  corresponded  to
        the top of bedrock as  verified via the above  mentioned
        quality control measures.  These data indicate that the
        trench was in fact excavated to the top of bedrock.

        Post-construction verification  borings also penetrated
        the sidewall  of  the trench prior to reaching  the  bottom
        of the wall.  It is highly likely that these boreholes
        are very nearly  vertical  (see Section  3.5).

        A  general  trend of  the linearly  increasing point
        resistance and linearly decreasing friction  ratio  are,
        as would  be  expected, based on exit  of  the side wall  at
        a high penetration angle  (slow increase in confinement
        with distance from the  cutoff wall).

        The  two high peaks  in the point resistance,  relative
        hydraulic conductivity and excess pore pressure, along
        with  the  intervening more moderate zone, are postulated
        to indicate that the piezocone was moving in  and  out  of
        the  backfill/filter cake/native  formation due  to
        irregularities in the  side wall.

        Approximately 3  feet prior  to encountering a point
        resistance indicative  of  a H.D.C.G. window, the relative
        hydraulic conductivity index increased somewhat  from
        values associated with  the  intact  backfill.  It  is
        postulated that this  reflects the proximity  or partial
        contact of the porous  stone with the native formation.

        Most of the other  containment wall  soundings  also
        encountered native formation materials prior  to reaching
        bedrock depth.
        special procedures were  followed to obtain vertical
soundings, wall verticality was  only specified to within  1
percent.  This could result in a translation of about  1 foot at
the bottom of the wall.  However, the actual verticality  of the
wall was  governed by how level the backhoe tracks were positioned
on the working surface.  A 6 inch error in the level of the
working mat, over the track width, would result in a translation
of 2.5 feet at the bottom of the wall.
                             3-78

-------
    The above data does not support  the conclusion that the
    material  encountered  below  88.5  feet  represents
    unexcavated native material.   However, it is recognized
    that another possible  explanation encompasses a window
    composed of native material which sloughed off the side
    wall "in mass" and  filled the bottom of the trench prior
    to backfill placement.  However,  the available data also
    does not support this  scenario  to  an  extent which would
    render it plausible.

    Independent  of the exact nature  and cause  of  the
    "potential window"/sidewall penetration identified below
    88.5 feet in sounding GZ-13,  the individual  piezocone
    indices obtained from  this  location exhibit  a
    significant degree of  consistency.   In addition,  the
    magnitude and direction  (positive vs. negative) of the
    deviations from intact  backfill  indices agree with
    theoretical trends  that  would be  expected  for  a
    noncohesive,  highly permeable material.  This data
    demonstrates the potential usefulness of the piezocone
    for window detection.

B.   Low Density Clean Granular Window

    The occurrence of  this  type of window is most likely to
    be the result of side  wall material  which had sloughed
    onto the advancing backfill face.  Two such zones were
    initially identified in sounding GZ-13.  The first zone,
    located from 17.5  to  18.5  feet  deep  in  the wall
    exhibited the point  resistance, friction  ratio  and
    excess  pore  pressure  signature  characteristics
    indicative  of  the  L.D.C.G. windows  encountered in the
    test  section.   However the  relative hydraulic
    conductivity index  did not support the classification of
    this zone  as a potential window.   It was therefore
    dropped from further  consideration  due to  the
    definitiveness of this index.

    The second potential  L.D.C.G.  window was encountered at
    a  depth  of 43 to 48  feet.  In  this  case,  the point
    resistance abruptly  increased to  about 20 kg/cm2 and
    remained relatively  constant at an  average value of 10
    to 15 kg/cm2.   Average  point  resistances immediately
    proceeding and following this zone were commensurate
    with intact backfill (2  kg/cm2).   The friction ratio
    decreased from about 3 percent  to values approaching 1
    percent  in this zone.  Excess pore pressure  decreased
    abruptly from an average of +1.0 kg/cm2 to an average of
    0.0 kg/cm2 and then restabilized  at 1.0 kg/cm2 upon
    exiting  this zone.   Finally,  the relative  hydraulic
                       3-79

-------
    conductivity index increased to about  30 cm3/ft. in this
    zone.   This index yielded values of  8.7  cm^/ft.  and
    11.5 cm^/ft. prior to and after encountering this zone,
    respectively.

    The above  data is  internally consistent and  follows
    trends exhibited  in  the test  section.   As  such,  it
    indicates the presence of a potential L.D.C.G. window.
    Interpretation  in  this instance is not complicated  by
    other  significantly plausible explanations  for the data.
    In fact,  the identification of  intact backfill both
    above  and below the potential window  add credibility  to
    this interpretation.

C.  Slurry Filled Granular  Window

    Three zones were  encountered in sounding GZ-13  which
    initially indicated the potential for the presence of a
    S.F.G. window.   The first case  occurred  at  a depth  of
    28.0 to 29.5 feet.   This zone yielded a characteristic
    signature  with respect to point  resistance,  local
    friction,  friction ratio and excess pore     pressure.
    However,  no deviation  in relative hydraulic conductivity
    from intact backfill values was detected.  This  zone was
    therefore omitted from further investigation.

    The second zone occurred at a  depth  of 88.5 feet, just
    above  the potential H.D.C.G. window previously discussed.
    It  is likely  that the  response is indicative  of
    penetration of the  filter cake at the side of the cutoff
    wall as indicated  by the very high friction ratio spike.
    This zone is also not considered  in more detail  herein,
    due to  the  complications addressed above  for the
    H.D.C.G. window.

    The third  zone of interest was located at a depth  of
    58.5 to 59.5 feet.   This  zone yielded piezocone  indices
    which were nearly identical to the signature observed
    during test section soundings.  The local friction value
    increased  to about 0.4 kg/cm2.  The point resistance
    peaked at about 15 kg/cm2 in the middle of this zone.
    This yielded the double peak in friction  ratio  (6 to  10
    percent)  encountered  in the test section soundings.
    Excess pore pressure  dropped  to a  near  zero  magnitude
    and relative hydraulic conductivity peaked at 40  cm^/ft.
    These indices  yielded values commensurate with the
    intact backfill both  before and after  penetration  of
    this zone.  As such, this zone has a high probability  of
    being  a slurry filled granular window.
                        3-80

-------
3.5  Window Verification


     The primary piezocone  indices of point resistance, local
friction and excess pore  pressure indicated that a significant
number  of potential windows  existed in the containment wall.
However, a relative hydraulic conductivity index commensurate
with intact backfill allowed  most of these potential windows  to
be dropped from further  consideration.  The next step in the
window verification procedure encompassed obtaining samples  of
the remaining potential  windows for visual classification and
laboratory testing.  These  samples were obtained using standard
split spoon and Osterberg  undisturbed Shelby tubes in boreholes
supported with heavy weight drilling fluid^S.

     A. total  of twelve borings  were  executed in the containment
wall.  These borings were  located  in areas exhibiting the highest
probability of containing windows  as based on  the QC data
obtained during construction and the post-construction piezocone
soundings.   The  locations of these borings are presented  on
Figure  3-9.  As shown  on the  figure,  some locations  contain
multiple borings  in  a  relatively  concentrated  area.  This
reflects two basic problems that were encountered when attempting
to obtain samples from the wall.  The first concerns locating the
boring at the centerline of the wall.  Although the  as-built
survey of wall location  was sufficiently accurate for subsequent
construction at the site,  it  was not accurate enough  for wall
sampling.  Initially,  ground penetrating radar (GPR) was employed
to find wall centerline.  The location of the top of the  wall was
easily  identified.  However,  the top of the wall was often  8  to
10 feet  wide for  the  first  5  to 10  feet of  depth  and then
narrowed to the standard 3 to 4 foot
     The GPR  could not  penetrate through this upper  zone  and
therefore could not accurately identify wall centerline.  Hence,
the  borings  sometimes  missed the  cutoff wall  and required
relocation.  The second difficulty concerns  wall verticality.   As
discussed in  Section  3.4.2,  it is hypothesized that the cutoff
wall is not completely vertical.   This has  no impact on  the
effectiveness of  the  wall.   However, due  to the verticality of


^Additional information on sampling and drilling techniques  can be
found in Winterkorn, 1975, Pgs.  15 and 44.

3*>During excavation, the top 5 to 10 feet of the trench was
typically sloped back on a 30 to 45 degree angle from vertical.
This was done to prevent surface materials at the edge of the
trench from raveling in and potentially resulting in windows.


                             3-81

-------
the borings37,  many of them penetrated the side of  the  trench
and proceeded  into the native  formation  before reaching  the
bottom of the  containment wall.   This  also resulted  in the
requirement for  additional borings.

     During  the sampling program,  a  total of fifty-four split
spoon  samples  and fifty six tube samples  were obtained.   The
split  spoon  samples were used for visual classification and as an
aid in determination of  tube  sampling intervals.   The  tube
samples were used to provide undisturbed  material for triaxial
hydraulic  conductivity testing as well  as visual classification.
Prior  to  sample designation for  triaxial  testing, the unopened
tubes  were radiographed to ensure  that representative  samples
were selected-^.
     3.5.1  Sample Classification


     Six of the samples retrieved from potential window locations
yielded material  which, if continuous through the wall,  would
result in  actual windows.  These locations are:

     0  Boring GZU-13,  cutoff wall station  1+00 at a depth of 43
        to 48  feet.

     0  Boring TBF-1A,  cutoff wall station  3 + 45 at a depth of 39
        to 46  feet.
      borings were  advanced using drilling fluid  supported,
open-hole techniques.  Large diameter drill rods  (NX) were used
and the rigs were precision leveled prior to and  during the
drilling.  The combination of the leveling, the weight of the
rods, and the soft  consistency of the cutoff wall backfill foster
a high degree of verticality.  These techniques,  as used on other
projects where the  boreholes were surveyed with inclinometers,
typically result in a maximum error of 3 to 6 inches  at the
bottom of 100 foot  deep bore holes.

^Radiography allows general classification of the soil in the
Shelby tubes prior  to opening them.  The method is based on x-ray
transmission characteristics of the tube contents. The procedure
proved valuable as  a tool to identify representative  portions of
the samples for triaxial testing, particularly with respect to
intact backfill.  Samples containing large pieces of  gravel could
thus be rejected from testing even when the gravel was not
visible at the surface of the sample.  Samples containing large
pieces of gravel (greater than one-sixth the sample diameter) can
yield artificially  low values of hydraulic conductivity.


                             3-82

-------
    0   Boring  SU-7,  cutoff wall Station  33+30 at depths of  30.5
       to 35.5 feet, 45.5  to 48 feet,  and 49.5 to 52 feet.

     0  Boring SU-4, cutoff wall Station 37+50 at a depth  of 21
       to 26  feet.

     Each of  the above  potential  windows  are  discussed
individually in the  following  subsections.   In  addition to the
above  enumerated potential  window  samples,  two  cases were
encountered  where  a sample  could not be retrieved from a
potential window  location.  These  were  boring GZ-13U, 58.5 feet
to 59.5 feet,  boring TBF-lA,  9.5 feet  to  10.5 feet.  As such, a
final determination of material classification could not be  made.
In cases  where the borehole  encountered  dense native formation
materials above bedrock,  the  available  data indicate that this
was  the result  of  trench  sid e w all  penetration due  to
non-vert icali ty  of the  cutoff wall rather than unexcavated
material  at the bottom of the wall.  Samples  of this material are
therefore not  treated further herein.


         3.5.1.1  Boring GZU-13, 43 to 48 Feet


     This potential  window was identified at  station 1 + 00 in
sounding  GZ-13.  The boring,  located 5 feet down-station from the
sounding, encountered the  potential window at a depth of 48  feet.
Two samples of the  potential  window were obtained.   The  first
sample was a  split  spoon  from 48 to 50 feet and the second  was a
tube from 50 to 52 feet. The samples were classified as a loose,
light  brown,  coarse to fine sand, trace  fine gravel, trace  silt,
in accordance with  the Burmister  system.  This material is
consistent with the piezocone identification as a low density
clean granular window.

     After  the above  two  samples were obtained,  the boring was
advanced and  remained in  granular  deposits until refusal was
encountered at a  depth of 90  feet.  The  deeper granular deposits
appear to be the result of penetration of the trench  sidewall.
Inasmuch as additional backfill was  not encountered  below the
potential window,  the identification of this  material as a window
is inconclusive.   In fact,  this material may also correspond to
sidewall  penetration rather than the zone  identified in sounding
GZ-13.
                             3-83

-------
          3.5.1.2  Boring TBF-lA, 39 to 46 Feet


     This potential window was identified  at station 3+45.   The
window consisted of two separate materials.   The upper  4.5  feet
contained a loose,  light  brown,  coarse sand, trace medium sand,
trace silt.  The material exhibited a uniform grain size and  the
voids were filled with  bentonite slurry. As such, this material
corresponded to a slurry  filled granular window which was  caused
by sedimentation of material suspended in the support slurry.

     The lower 2.6 feet of this window contained a medium dense,
gray, fine to coarse sand,  trace gravel, trace silt.  It appears
that  this material was  glacial till  which was located  in  a
bedrock surface convolution and therefore could not be excavated.

     Boring TBF-1,  located  5  feet down-station of TFB-lA  also
encountered this window.   In  this  case, the  window was  6.5  feet
thick.   Sounding GZ-12,  located an additional 5 feet down-station
of TBF-lA, did not  encounter  the window.   In  the up-station
direction,  sounding  GZ-11,  located 5  feet from TBF-lA,
encountered the window over a  thickness of 3.5 feet.   This  data
indicates that the  window is  greater than  10 feet long  in  the
direction of the cutoff wall alignment.


          3.5.1.3   Boring SU-7,  30.5 to 35.5 Feet, 45.5 to 48
                  Feet and 49.5 to 52.0 Feet


     These three potential windows  were initially identified at
station 33+30 in sounding S-7.  The piezocone signatures  for  each
of the three windows were  very similar.  They each  exhibited
significant point  resistance  similar to a  L.D.C.G.  or  S.F.G.
window  (15 to 20  kg/cm^ as  compared to 5 kg/cm2 for the intact
backfill). Local  friction values were also relatively high as
would be  expected for a S.F.G. window (0.4 to 0.6 kg/cm2).   These
indices  yielded friction ratios which  averaged  from  3 to  5
percent with local peaks as  high as 7 percent.  Although  the
magnitude of the  indices are  similar to those expected for  a
S.F.G.  window as based  on  the test  section  soundings,  the
friction ratio signature did not exhibit the  characteristic shape.
Instead  of the well defined  friction ratio spikes upon entering
and  exiting the window, friction ratio  in this case yielded
consistently high values.  This behavior would be expected if the
piezocone encountered the  filter  cake at trench  sidewall
irregularities.   This hypothesis can not be further supported by
the  piezocone data  in that  excess pore pressure and  relative
hydraulic conductivity data was not available.
                             3-84

-------
     Boring SU-7 was located  5 feet down-station of the sounding.
Sampling confirmed two zones corresponding to  the above potential
windows.  The depths  of  these  zones were 29.0 to 35 feet and  48
to 50 feet.  As  such,  they are  somewhat  displaced  from that
indicated by the sounding.  The samples were  classified as loose,
brown,  coarse to  fine  sand,  little fine  gravel, trace silt.
Bentonite slurry  was  not noted  in the soil pore space.  These
samples were obtained via  split spoon.   Tube samples were
attempted but they yielded no  recovery.

     The  samples  support classification as a L.D.C.G. window.
However, this window type is  not  corroborated by the piezocone
data.   As with the  piezocone sounding, it is probable that the
boring penetrated into native  formation material at locations  of
irregularities  in  the  trench  sidewall.  This hypothesis  is
supported by:

     0   A material  type which corresponds  to native  formation
         deposits.

     0   Penetration of the sidewall below  a depth of  52 feet.
         The boring  thereafter  remained  in native  formation
         material until refusal at 60 feet.

     0   Piezocone  response uncharacteristic of window types
         anticipated in the  cutoff wall  but consistent with
         partial sidewall  penetration.

     0   An  identical piezocone response in  sounding S-9 from  23
         to  28 feet.   Boring SU-9 encountered  the same zone at  22
         feet but remained in the native formation until refusal
         at  30 feet.

     The data is inconclusive as to the cause of the non-backfill
material encountered.  While the existence of  some type of  window
not modeled in the test section is certainly  possible,  it is more
likely  that the  sounding  and  boring  both  penetrated
irregularities  in  the sidewalls  of the trench.   Such
irregularities are often observed  in concrete backfilled  slurry
trenches  when the soil  is  removed from the  walls.  Irregularity
magnitudes of 1  to  3  feet  are not uncommon,  particularly  in
granular formations.


          3.5.1.4 Boring SU-4, 21 to 26 Feet


     This potential window was  identified at Station 37+50  in
Sounding S-4.  The piezocone signature in this case was identical
to the three zones  described in  Section 3.5.1.3 (Sounding S-7).


                            3-85

-------
As such, it is hypothesized that Sounding S-4 also penetrated an
irregularity in the trench sidewall  or  initially penetrated the
sidewall and was deflected back  into  the  soft backfill by the
denser native deposits.   Boring  SU-4,  located  5  feet
down-station, did not encounter these potential window materials.
Continuous samples were taken starting 3  feet above the top of
the potential window and proceeded 4 feet below it's bottom.
Only intact backfill was recovered therefore  indicating that the
boring  did not encounter the trench sidewall.


     3.5.2  Sample Hydraulic Conductivity Testing


     In only two cases could undisturbed  samples of potential
windows be obtained.  These were  from boring GZU-13 and TBF-1A.
While  triaxial hydraulic conductivity  tests could have been
performed on those  samples, the  effort was  judged unnecessary.
The grain  size distribution  of the  material in the samples
indicated a probable hydraulic  conductivity of 10~^  to 10~^
cm/sec.  Further  refinement  of  this estimate provides no
significant information in that this value is high as compared to
the design specification for the cutoff wall  of 1 x 10"'  cm/sec.
Therefore,  if these  materials  exist in  a  continuous state
transecting the cutoff wall, then a window would certainly exist.

     Investigation with respect to the hydraulic conductivity of
undisturbed  intact  backfill samples was  considered  a more
valuable endeavor. As such, representative tube samples of intact
backfill were subjected to triaxial testing.  The results of this
work and the conclusions drawn  from the  data are presented in
Section 2.
     3.5.3  Containment Wall Homogeneity


     One of the objectives of the containment wall soundings  was
to provide an  estimate of the  probable  frequency  of  window
occurrence in  the cutoff  wall.  Nearly 1,500 feet of sounding  and
borehole installation  yielded only two  cases  where  the
probability of the  existence of a window was high.  The first
case was boring GZU-13 as  described in Section 3.5.1.1.   In this
case, window identification  although probable, was inconclusive
due to the  lack of an intact backfill sample below the potential
window.  However, it  is  believed that the second case  (boring
TBF-lA,  section  3.5.1.2) was  conclusively identified as a
non-backfill deposit  located between the bottom of the cutoff
wall and the bedrock.   In this case, the same undisturbed tube
sample  contained  intact  backfill directly above S.F.G. window


                             3-86

-------
material.   It is  unlikely that  this data  fits a plausible
non-window explanation.

     The above data indicated that few windows  are  likely  to
exist in the Gilson Road  containment wall.   However, it  is
recognized that much of the sounding data was inconclusive due  to
complications arising from trench side  wall  penetration.  While
this  hypothesis is probable, it can not be  proven  with the
available data.  The inability to adequately sound and sample the
containment wall was a direct result  of the unknown location  of
exact wall center line and the probable non-verticality  of the
wall.   While these issues do not result in  deficiencies with
respect  to containment  performance,  they  do render
post-construction  verification a  very difficult, expensive  and
inclusive undertaking.  As such, greater quality control  should
be exercised in these areas.

     Finally,  it  is emphasized that even in the case where  the
existence of a window was highly  probable, its impact on the
efficiency of the  cutoff wall can not be determined via sample
retrieval.  Sampling provides no  indication  of the degree  to
which the window material is continuous through  the wall.   In
fact, it is probable that under the worst  case conditions,  a
filter cake exists  between the window material and the  native
formation.  A filter cake, such as would be anticipated, would
render the  hydraulic conductivity of  the overall wall
cross-section orders of  magnitude below that of  the native
formation.  The effectiveness of the overall  cutoff wall can  only
be evaluated by hydraulically stressing the wall  and  observing
the piezometric response of the system.  This  task is treated  in
Section 4.
3.6  Conclusions


     The following conclusions can  be drawn  from the data
presented herein:

     0   The  test section did not provide the known  condition
        expected for  piezocone performance evaluation.   The  lack
        of  support  slurry filled window long-term  stability
        provided valuable  insight into the improbability  of  the
        existence of  such a window  in the containment wall.
        However, the  inability to  construct other window types  to
        a known geometery impaired verification of  piezocone
        suitability for  window detection  in soi1/bentonite
        backfilled cutoff  walls.
                            3-87

-------
The response of the piezocone when  encountering windows
in the  test section was in general accordance with that
anticipated based on prior empirical  data and theoretical
considerations.   As such, window locations  could be
identified in the test section.  The windows  produced
repeatable and identifiable signatures in the piezocone
indices.  Based on the test section soundings, it appears
that the piezocone  is  capable of  window detection in
soil/bentonite backfilled  cutoff walls.

As an  adjunct to the standard piezocone indices, the
relative hydraulic conductivity index provided  valuable
additional insight with respect to potential window
identification.  To enhance the utility of this system,
redesign should be  undertaken to allow high flow volumes
at low  driving pressures.  This would better allow
evaluation of the hydraulic  significance of a potential
window  while minimizing preferential boundary  flow and
hydraulic fracturing.

Potential window identification must  utilize  a
multi-index analysis.  Many cases were found in which one
or two indices indicate  window  existence  but  the  other
indices did not.  In particular, the relative hydraulic
conductivity index  often  demonstrated that a high
hydraulic conductivity  zone was not present in locations
initially  identified  as  potential windows  based on the
other indices.

While  anomalies in   the cutoff wall backfill were
relatively easy  to identify  as based  on  piezocone
response,  significant  judgment  was  required to identify
characteristic  responses  which were  likely  to be
associated with potential windows.  This  judgment must  be
based  on  a thorough understanding  of  piezocone
operational principles  as well as  the stress,  strain,
hydraulic conductivity  characteristics of  soil deposits.

Based  on  the data  acquired  during  this portion of  the
project, it appears that the piezocone could provide  a
useful, routine post-construction verification capability.
However, additional work must  be conducted to build up  a
data base upon  which empirical correlations can  be
constructed.   This  magnitude of data generation  would
likely require  use of  the  instrument on  a  number  of
different  cutoff  wall projects following  additional
controlled  test section sounding.

For  piezocone  sounding  to be  viable  as  a
post-construction verification tool, construction quality
                     3-88

-------
control of the  cutoff  wall must include wall  alignment
and verticality provisions.  The accuracy of  as-built
wall alignment  documentation and actual wall verticality
must be increased significantly  above that required for
hydraulic  performance only.

The piezocone soundings and undisturbed sampling of the
Gilson  Road cutoff wall encountered windows in only a few
instances.   These investigations  were concentrated  in
areas with the highest  probability  of window occurrence
as based  on construction quality control data.  This data
therefore  reinforces the conclusion  that the cutoff wall
behaves essentially as an intact barrier.  However,  it  is
recognized that  the data is  somewhat  inconclusive due  to
complicating factors associated  with  the trench side wall
penetration issue.  Sidewall penetration was likely due
to the  probable  non-verticality of the cutoff wall.
                     3-89

-------
                           SECTION 4

               EVALUATION OF CONTAINMENT LEAKAGE
     Passive physical containment (in-situ impervious barriers)
forms an  integral  part of  the overall  containment strategy
adopted for  the  remediation of the Gilson Road site.  The three
major components  of the passive containment system are:

     1.    The synthetic surface cap which  acts as a barrier to
          the vertical infiltration of precipitation and thus
          forms the top of the containment vessel,

     2.    The soi1/bentonite cutoff wall which impedes  the
          horizontal flow of groundwater into and out  of  the  site
          and acts as the sides of  the containment,  and

     3.    The natural glacial  till/bedrock aquiclude which forms
          the bottom of the containment.

     Imperfections  in  any one of  these three  components  may
result in  leakage and thus off-site migration  of  contaminants.
From  the  standpoint of environmental damage  and human  health
risk, if  there is  a  breach in the containment,  it  may not be
particularly important  which element is leaking.  However,  from
the standpoint of evaluating the inherent viability  of  a  specific
containment  technology or determining an appropriate hydrodynamic
isolation  system  (active physical barrier)  to augment  the passive
containment, as was the case for the Gilson  Road  site, it is
critical to assess the integrity of each component  individually.

     The  objective of this,  the third phase of the project,  was
to evaluate  the  hydraulic effectiveness of the  soil/bentonite
cutoff wall.  The  construction quality control  testing and the
post-construction wall sampling/testing (Phase  One,  as  reported
in  Section  2.0)  demonstrated that the intact hydraulic
conductivity of  the  cutoff  wall  generally met  the contract
specification of 1 x 10~7  cm/sec (3 x 10~4  ft/day).  However,  the
effectiveness of  the barrier is proportional to the  cutoff wall
bulk  hydraulic  conductivity,  of  which intact hydraulic
conductivity  is  only a  part.   Ideally,  the evaluation of bulk
cutoff wall  hydraulic conductivity  would be independent of  the
influence  of  the other barriers.  Inasmuch as the cap  is located


                             4-1

-------
in the vadose  zone,  it  only indirectly influences groundwater
flow.   Its effect on the "analysis of  bulk  cutoff  wall
conductivity can  therefore be easily addressed.  Unfortunately,
both the  cutoff wall  and aquiclude directly impact groundwater
movement,  and  component  separation  in  this case is more
difficult.

     Two approaches  were used to separate the cutoff wall  and
aquiclude,  such that the  effectiveness of the cutoff wall alone
could be evaluated.  The first approach was based on the use  of  a
3-dimensional numerical  model of the site which was previously
used to design the hydrodynamic isolation/recirculation system
for the project.  The first step in this approach was  to better
evaluate the  aquiclude  hydraulic conductivity via  a bedrock
pumping test (Section 4.1).   The second step was  to  employ  a
numerical  sensitivity analysis based on vertical piezometric  head
distributions to evaluate bulk cutoff wall hydraulic conductivity
(Section 4.2)  The second approach consisted of evaluation of
contaminant concentration versus  time and depth  (Section 4.3).


4.1  Bedrock Pumping Test


     The primary  objective of the bedrock pumping test was to
evaluate  the hydraulic conductivity of the fractured rock which
forms  the bottom of the  containment  below the cutoff wall.
Direct determination of bedrock hydraulic conductivity was an
essential step  in the evaluation of the bulk  hydraulic
conductivity of the cutoff wall.  Particular emphasis was placed
on  determining  the bedrock  hydraulic  conductivity  in  the
direction  perpendicular to the cutoff wall.  This value would
control the leakage  under the wall should the bedrock fracture
pattern exhibit anisotropic characteristics.

     Documentation of the  hydraulic conductivity of the rock has
also increased confidence in the calibration of the  numerical
model which was  used to  design the hydrodynamic isolation system.
During model calibration, it was  necessary to use conductivities
for  the  bedrock  which  were significantly greater than those
measured  during packer testing.   The "unjustifiably" high values
were required  to  match  vertical heads simulated by the model to
the field observations.   The pumping test has demonstrated  that
these higher conductivities were  essentially correct.

     The  secondary objective  of the  pumping test  was to assess
the degree  of  hydraulic interconnection between the  fractured
rock and the high  hydraulic conductivity sand and gravel deposits
                             4-2

-------
of  the  upper aquifer.  This was achieved  via  evaluation of an
effective homogeneous  leakancel for  the glacial till aquitard.


     4.1.1  Pumping Well Location and Installation


     The pumping well,  PT-1,  was located at the western end of
the site as  shown  in Figure 4-1.   There were  several
considerations involved in this selection.  First,  this portion
of  the site experiences the greatest head  loss across the cutoff
wall.   Therefore,  the bedrock hydraulic  conductivity at this
location more strongly affects  leakage out  of  the containment,
particularly because this is the  downgradient  end.   Second, the
glacial till thickness increases in  this area, providing greater
isolation between  the bedrock and  overburden aquifers.
Therefore,  evaluation of bedrock hydraulic  conductivity is
simplified  and confidence in the evaluation is increased.  Third,
the downgradient  portion of the cutoff  wall would  be  the most
highly  stressed during the subsequent overburden test, thereby
allowing  better comparison between the  two tests.   Finally,  a
greater abundance  of monitoring instrumentation  was already in
place in the vicinity of the  downgradient portion of the wall.

     The pumping well was placed inside the cutoff  wall so as not
to  draw contaminants outside  of the  containment  during execution
of  the  test.   At  the  downgradient  portion  of  the site, the
bedrock dips sharply in the direction perpendicular to the wall.
Therefore  the  well  was placed close to the cutoff wall so as to
stress those materials which  most directly affect leakage rates,
i.e.,  those  immediately  below the  bottom of the wall.    In
addition,  the  horizontal  component  of flow  induced in  the
overburden  would be roughly  radial, and therefore parallel to the
low hydraulic conductivity barrier.   This  minimized  the
inaccuracies associated with approximating the overburden.aquifer
as homogeneous  in the mathematical analysis.

     The objective of  the well installation was to allow pumping
from the bedrock only, and therefore the  overburden  and  glacial
till  were  sealed  off.   The entire  column of rock was  to be
stressed, down to  at least 50 feet below the  glacial  till, in
order to  include  the major fracture zones.   Earlier drilling at
well R-l,  including continuous coring and classification by RQD
^Hydraulic  resistance to vertical flow between aquifers separated
by an aquitard.
                             4-3

-------
FIG. 4-1   PUMPING TEST MONITORING NETWORK
                                                      4
      LYLE REED
         BROOK
o
o
PUMPING WELL
MULTI-LEVEL
MONITORING INSTALLATION
SURFACE WATER POINT
                                                RECIRCULATION WELL
                                       "	i  RECIRCULATION TRENCH
                                          6
                                                                                   o'   so'  too1
                                        200'

-------
(rock quality designation2)f  had shown that,  in addition to a
highly fractured upper zone, a  5 foot thick  highly fractured zone
(RQD  =  20%) existed at a depth of  50  feet.  Therefore the
possibility existed  that  leakage was occurring at significant
depths, and not merely  in  the highly fractured upper portion of
the bedrock.  The depth of  the  borehole was  therefore established
to penetrate 100 feet into  the  bedrock.

     A 6-inch  casing was  installed through  the overburden,
including the glacial  till,  and  drilling of the bedrock began
using the air-rotary  method.   However, the top 10 feet of the
highly fractured  rock  was  unstable and would  not remain open.
Therefore the casing  was driven through this layer as well.  The
hole  was then advanced uncased through 89  feet  of mostly
competent rock.   Finally,  the  lower  10 feet of  casing was
perforated to reestablish  hydraulic connection with the upper
portion of the bedrock.

     The hole was tested  several  times during  the drilling
process  for its water yield.  The water yield, or water make, was
estimated by forcing  air  into the bottom of the borehole, and
measuring  the flow rate of water which was forced out of the top
of the casing at steady state.  Before the  casing was perforated,
the yield was approximately  10 gpm (gallons per minute),  but
after perforation  the  yield  increased to about 150 gpm.  This
demonstrated the dominance of the upper  zone regarding the
transmi ssi vity of  the  formation.   In addition, the yield of 150
gpm  indicated that  the upper fractured zone was far  more
permeable than had been inferred from the previous packer test
data.

     After drilling and development  operations  were completed,
the pump was placed  in  the casing at a depth of 75  feet.   A
piezometer was also  included  to provide water level measurements
in the  well.   Details of the  installation are shown  in
Figure 4-2.


     4.1.2  Recharge Trenches


     Water pumped during the  test had  to  remain on the site due
to its contamination.   Therefore, the water  was  recharged to the
overburden via three  recharge trenches already in place.  These
trenches, numbers  4,  5, and  6 as shown  in Figure  4-1,  were
    index used to quantify rock mass integrity with respect to
degree of fracturing.
                            4-5

-------
FIG. 4-2 PUMPING WELL INSTALLATION
fl-
IC •
20-

30-
40-
50-

«- 60-
o>
*"„ 70-
X
»-
LU
O
90-

100-
*•
4.
150-
160-
170-

180-


•
CASING LEFT
IN PLACE
^_^

t
EL. 55 	

EL 7' —
PERFORATED ,
CASING ^
PUMP^ 	
EL 83

SLOTTED PVC^-^
PIEZOMETER


'f t
OPEN HOLE — +-

EL, 172










J









,
/
/



\


*^^— .




SAND 8 GRAVEL


_
GLACIAL
TILL
HIGHLY FRACTURED
BEDROCK



MODERATELY
FRACTURED
2^ BEDROCK


J BOTTOM OF
BOREHOLE

              4-6

-------
already operating as  part  of  the hydrodynamic isolation  system.
The pumpage from the  bedrock  pumping test  was added  to the
existing flow.

     4.1.3  Monitoring  Points


     Drawdown resulting from pumping the  bedrock well was
measured in the pumping  well  and 72  pre-existing and recently
installed piezometers and observation wells.  Observation points
were  divided among 24 borings, most  of them multi-level
installations (see  Figure  4-1).  Specific  emphasis was placed on
measurements in the upper  rock  layer  and  in the overburden just
above the glacial till.  The  upper,  highly fractured portion of
the bedrock was of primary interest in that  it controlled leakage
under the cutoff wall.   Measurements just  above the glacial till
were also emphasized  inasmuch as the difference in  drawdowns
across the glacial  till  controls the amount  of induced  leakage
through the aquitard and thus recharge to the bedrock.

     The  locations of monitoring points ranged horizontally from
as close as 10 feet to  as  far as 500  feet  away from the pumping
well, and vertically  from  the water  table to 100 feet below the
top of bedrock.  In addition, water levels were monitored at five
points in nearby surface waters.


         4.1.3.1  Existing Points


     Prior  to  the pumping test,  numerous  observation wells and
gas-drive sampler/piezometers (Barvenik,  1983)  existed at the
site as the result  of previous engineering studies (e.g., design
and operation of hydrodynamic isolation  systems for emergency
response  and final remediation).   In particular, there were
numerous multi-level installations both  inside and outside the
cutoff wall for the purpose of estimating leakage through the
site.  These monitoring installations  typically included a 1-1/2
inch  PVC observation well  at  the water table, one  or two
sampler/piezometers in  the stratified  drift, and one in the top
10  to 15 feet  of  the bedrock.  A typical  installation  is
presented as Figure 4-3.

     The  method used to construct  these installations was
typically as follows.  The casing was  driven and washed out with
a roller bit down to  the top  of  the  bedrock.   The hole was then
advanced by  coring  10  to  15  feet  into  the bedrock.   A
sampler/piezometer was  placed in the bedrock inside a sand  filter.
The casing was then extracted  incrementally  as a  compacted
                            4-7

-------
FIG. 4-3 TYPICAL EXISTING MULTILEVEL  INSTALLATION
o


10

9f\



30
•^

I
00 *•
o> 40'
•2?


JE 50-
A
*^
UJ
Q

60'




70-

80-
9O-




STRATIFIED
DRIFT

T-

>








EL. 53


/*** A /* I A 1
GLACIAL
TILL
1 1 LL


EL-72

BEDROCK
EL. 82

•v:
'•%?
•"';
'* V-
~5

fijj
K?
.:-:;
<&
C'*-'-

iS
^•ii



1

/


•'."•".
(^ ^
'• ".'.


'/
/
1
;•.•!







=
~

s
r.t:

'.
$'
*.*t


i
/
/
• .-


^ ^
-.•


^
/
1


\ r
*.«;
•v>
5^
r •*
^
:'."•
*Vv
^
•"^
«k^j
»•£
>*;
•\?:


'•*•*
^
/







/
/
,/
^V-



COLLAPSED
FORMATION


l'/2" PVC OBSERVATION
WELL WITH SAND PACK


p/\i i ADCtrn
w WLL. Ar O C U
FORMATION


-BENTONITE SEAL

GAS-DRIVE
MONITORING INTERVAL
DFRITtf^MITC OP A 1
OC.N IUNI 1 t, OCAL


-COLLAPSED FORMATION

WITH BENTONITE SEALS


	 BENTONITE SEAL

GAS-DRIVE
MONITORING INTERVAL

                                                — CONCENTRIC
                                                  SAMPLING TUBES
                                                        -BENTONITE
                                                           SEAL
                                                         SANO PACK
                                                         POROUS STONE
                                                           SAMPLER
                                                        -OPEN HOLE
                                                        -BENTONITE
                                                           SEAL

-------
bentonite  seal  was placed to seal the borehole  at the  level of
the glacial till aquitard.  This process was  repeated for each
sampler/piezometer with intermediate seals placed such  that the
vertical hydraulic  conductivity of  the installation was less than
that  of the  parent formation.  An observation well was then
installed with the  screen positioned so as  to  straddle existing
and projected  water table elevations.

     To  allow groundwater samples to be extracted from the
formation,  the  gas-drive sampler/piezometers include  one-way
check-valves, which allow unrestricted flow  from the formation
into  the access tube but which restrict,  without completely
preventing,  flow in the opposite direction during  sampling.  They
are therefore not  capable of responding adequately to  rapid
drawdowns  associated with pumping tests in confined aquifers.
If, however,  drawdowns are occurring more slowly,  the instrument
response to decreasing piezometric head is consistent with that
of  the  aquifer.   In  particular,  the check-valve  does  not
interfere  at  all with  steady state water  level  measurements in
that transient effects are, by  definition, absent.  This  will be
documented  in a   subsequent section.   In  addition,  the
sampler/piezometers are considered satisfactory for recovery
responses,  where heads are rising  and the check-valve is  open and
thus  unrestrictive .   In  fact,  response   time for  the
sampler/piezometers is better  than for standard observation wells
when  heads  are  increasing, due to the  lower storage volume
associated with  the small diameter  riser tubes  (Barvenik 1984).
          4.1.3.2  New Installations
     Three new monitoring  installations (PT-2, PT-3, and PT-4)
were constructed specifically for this study.  The primary reason
for the new  installations was to provide rapid response .drawdown
data at small distances from the pumping well.  In addition,  they
were drilled to  about the same depths as PT-1 in order to obtain
an understanding of the importance of the deeper zones of  flow in
the bedrock.  Two of the wells, PT-3 and PT-4, were lined up with
PT-1 perpendicular to the cutoff wall, because  that directional
hydraulic  conductivity controls  the specific discharge  from the
containment.  PT-4 was located just outside of the cutoff  wall in
order to  better isolate  the  section of bedrock directly
underneath  the wall.  PT-2 was included to estimate the degree of
horizontal  anisotropy.

     The instrumentation differed from that in the pre-existing
installations in  that each sampler/piezometer  was supplemented
with a separate  small-diameter PVC piezometer.   The access tubes
for those piezometers were designed specifically to accommodate


                             4-9

-------
pressure transducers to measure the small-time transient response
of the aquifer.  Transducers  were  required because/ due to the
semi-confined nature of the  bedrock aquifer,  drawdowns were
expected to occur too quickly  for manual water level measurement
techniques.  In addition, problems associated with the time lags
due to  the check-valves  in the sampler/piezometers  were thus
bypassed.

     There were  several objectives to be met in locating the
piezometers within the new installations.   The piezometers in the
bedrock were to be  located in  the most densely fractured  zones.
They also required  a  minimum vertical separation  in  order to
avoid  redundancy  and allow  adequate  vertical distance to
establish an effective seal.  Finally, measurement points were
desired directly above and below  the glacial  till in order to
assess the amount of  induced  leakage through the aquitard.  In
order to meet these  objectives, one point was placed as deep as
possible into the bedrock such that it coincided with a zone
exhibiting a high fracture density.  The second monitoring point
was located in the highly  fractured upper 10 feet of the bedrock.
A bentonite/cement  grout seal  at least 20 feet long was situated
in the more competent rock between these two locations.  A third
monitoring location  was  placed in the sand/gravel aquifer just
above the glacial till,  with  a seal placed  over  the entire
glacial till thickness.  Finally  a 1-1/2-inch PVC observation
well was screened in the upper portions of the  stratified drift
phreatic aquifer.   A typical installation  is  presented in
Figure  4-4.  Additional  details regarding bedrock  monitoring
installations of this type can be found in Barvenik  (1983).


     4.1.4  Execution of Pump  Test


         4.1.4.1  General Conditions


     Due to the high  water yield  observed in  the pumping well
during drilling, it  was anticipated that the transmissivity of
the bedrock might be higher than had been estimated from previous
packer  test results.   Therefore,  prior  to execution of the
full-scale test, a preliminary  test was executed to determine the
response time and degree of  drawdown which might be expected.
The response time was quite  fast,  indicating  that transducers
should be used.  However,  the  amount of drawdown observed (less
than 3  feet) was much lower  than  expected.  The accuracy  of the
transducers was determined to  be insufficient for monitoring the
full scale test.  Therefore,  water level readings had to be taken
manually.  Electric water  level  readers, typically dedicated to
                             4-10

-------
 FIG. 4-4  TYPICAL PUMPING TEST MULTILEVEL INSTALLATION
20-
30'
40' •
50
60-
70-•
80-
90- •
   STRATI-
    FIED
    DRIFT
        -38—
    GLACIAL
      TILL
        •71-
     BEDROCK
                        OBSERVATION
                  WELL WITH PEASTONE
                  PACK
COLLAPSED
FORMATION
GAS-DRIVE
MONITORING
INTERVAL
GROUT
 SEAL
GAS-DRIVE
MONITORING
INTERVAL
                    GROUT SEAL
                                      IOOT
                                      IIO--
                   BEDROCK
                    120"
                                      130- •
                    140"
150- •
160-
                    I70--
                                      I80-1-
                                  GROUT
                                  SEAL
                                            172 I
              GAS-DRIVE
              MONITORING
              INTERVAL

                                                             CONCENTRIC
                                                             SAMPLING TUBES
                                          Jfi-GROUT
                                              SEAL

                                             SAND
                                             PLUG
t.1 "
3/4  PVC
PIEZOMETER

FILTER BAG
                                                                                    POROUS STONE
                                                                                     SAMPLER
                                                                                    SAND PACK
                                              PEASTONE
                                              BACKFILL
                                                                                    GROUT SEAL

-------
each monitoring point,  allowed readings as often as every five
seconds.  Readings were taken to within + 0.01 feet,  but  the
final  accuracy was  probably + 0.05  feet when all potential
reading errors are accounted  for.

     The pumping  test  in the bedrock was run from  September  6
through September 16,  1985,  for a total of ten days.  Water  was
extracted from the pumping  well in the bedrock and returned to
the  overburden via  recharge trenches 4, 5,  and 6  located
approximately 700 feet  upgradient.  These trenches were already
operating  as part  of  the recirculation system, and  the  pumpage
was added to the  existing flow.  Please note, however, that the
system had been operating for several months prior  to  the  test,
and had achieved approximate steady state.  Therefore, changes in
piezometric head were attributed  to the increment  in  recharge.

     The pumping rate was constant throughout the test at 88 gpm.
This rate  was measured by adding the flows through  two  parallel
flow meters, and  was  verified by Doppler ultrasonic measurements
of fluid velocity in the pipe between the meters and  the trenches.
The pump was run  on  a  direct three-phase 220-volt  line, thereby
eliminating the attendant problems of using a portable generator.

     At the beginning of the test, emphasis was placed on reading
water levels at those  points closest to the pumping well.   For
these  points, readings  were initially taken about  every  ten
seconds.  As will be  discussed subsequently, even this  rapid
reading schedule proved  to be too  slow to capture  the full
transient  drawdown curve due  to the rapid response of  the bedrock
aquifer.  This shortcoming  in the data was primarily limited to
the points in the highly fractured upper zone of  the bedrock
immediately adjacent to the  pumping well.  As time progressed and
the monitoring wells  closest to the  pumping well approached
steady  state, emphasis  shifted to the points further away, both
horizontally and vertically.   Some of the furthest points did  not
show significant  drawdowns  for more than one hour  after pumping
began.  Thus, numerous readings at the early  times were  not
justified  for these locations.

     The  occurrence  of heavy  rains during execution of  the
pumping test affected the drawdowns measured in the monitoring
wells.  Table 4-1 shows the  daily total precipitation at a nearby
NOAA weather data station (Pennichuck Water Works).  During  the
test,  fluctuations  of up to 0.4 feet in the water  level of Lyle
Reed Brook rendered  transient response data  for the system
unsuitable for analysis, as will be discussed  in  the  following
sections.
                             4-12

-------
                          TABLE 4-1

        DAILY PRECIPITATION DURING PUMPING TEST (9/85)
      Date
Precipitation (in.)
9/06/85
9/07/85
9/08/85
9/09/85
9/10/85
9/11/85
9/12/85
9/13/185
9/14/85
9/15/85
9/16/85
1.30
1.06
0.00
trace
0.45
0.01
0.00
0.00
0.00
0.00
0.00
          4.1.4.2  Data Discussion
     Once pumping began,  steady-state conditions in the rock
layers were achieved  in  about  two days.   In  the overburden,
achievement of steady-state conditions took longer, typically on
the order  of seven days.   At  some  points however, the drawdown
was still increasing  slowly after ten days.  Figures 4-5  and 4-6
show the time-drawdown history at two multi-level installations.
The first, PT-2,  is  representative of the majority of the data.
The second, M-14, demonstrates anomalous behavior  due  to a
previous  error  in  location of  the  seal between  monitoring
intervals.

     At PT-2,  drawdowns were higher  in  the bedrock  than in the
stratified drift.   The highest  drawdown  occurred  in  the
upper  bedrock (PT-2-3).  At  this point, the majority of the
drawdown took place before measurements could be made (less than
5 seconds), indicating a low storage coefficient.  The deep rock
piezometer (PT-2-4) ultimately developed a drawdown near that of
PT-2-3.  However, the response time was two  to three orders of
magnitude larger.  This  indicates that the connection between
points deep  in the  bedrock  is  quite tortuous, with a  low
hydraulic  conductivity.
                            4-13

-------
                                     FIG. 4-5  PT-2 TIME-DRAWDOWN CURVE
         2.4
         1.8
I
M
*>.
      4)
      V
      O
      O

      <
      oc
      Q
          1.2
• PT-2-1
A PT-2-2
• PT-2-3
+ PT-2-4
WATER TABLE
TOP OF TILL
TOP OF ROCK
DEEP ROCK
-/•
         0.6
         0.0
                                              TIME, minutes

-------
                                 FIG. 4-6 M-14 TIME-DRAWDOWN CURVE
I
H
un
      Q)
      0>
      o
      o
      tr.
      o
                                              TIME, min utes

-------
     At PT-2-2  (above the glacial till),  the drawdown was
generally 2 feet  less  than that at PT-2-3.   The  small-time
response  for  this  point was  not observed.   The water table
(PT-2-1)  was  the slowest to  respond,  since  its storage
coefficient is  equal  to the  specific yield of the sands and
gravels, and thus much larger than that of the lower points.  The
water table also  experienced  the least drawdown of any point  in
PT-2.

     The  induced components of flow in the  aquifer near PT-2 can
be deduced from  the  differences  in drawdowns between  various
measurement points.  The  induced flow occurs from regions of low
drawdown to those of high drawdown.  For example, in the vicinity
of PT-2, flow  is  occurring  upwards in the  bedrock and downwards
in the overburden.  Note that  the difference in final drawdown
between PT-2-1 and PT-2-2  (both  in the stratified drift) is 0.3
feet, while the difference between PT-2-2 and PT-2-3 (spanning
the glacial till)  is 1.6  feet.   This illustrates the fact  that
the till is much less permeable than the sands above it.

     The  drawdown history for M-14 illustrates the importance  of
seal location and integrity.  M-14-4 was placed in the fractured
rock  zone, while M-14-3 was placed in the sand and gravel aquifer
just above the  glacial  till.   However,  both points  show nearly
identical drawdowns.   This  is  because the  lower seal separating
the two monitoring points was placed in the top of the bedrock,
as is standard practice,  and  not in the less permeable glacial
till.  Another seal  was placed  below M-14-3 in the  top of the
glacial till.  However, a  significant section of the installation
through the glacial  till was not  sealed.  Figure 4-6 therefore
illustrates the  consequence of  breaching the aquitard and  thus
establishing a connection between the two points.   This small
artificial leak  through the aquitard probably has little effect
on the overall  response  of  the two aquifer system.  However, its
local effect in the vicinity of the monitoring point  is
significant enough to render this data misleading.  This isolated
case  is  highlighted because  future sections will  address the
vertical head profiles at this installation.

     Figure  4-7  shows  the  time-drawdown plot for  the two
monitoring  points M-3-4 and  M-3-5.   The  former  is  a
sampler/piezometer  and the  latter is a piezometer  only.  Both
were installed  in  the same  borehole at the same depth.  Note that
due  to its check valve,  the  sampler/piezometer responds more
slowly at early times,  but  that  the two  points  respond
identically  (within  reading accuracy) at large times.  This  plot
illustrates the accuracy of the gas-drive sampler/piezometers  in
providing  steady-state hydraulic information.
                             4-16

-------
                         FIG. 4-7  M-3-4/M-3-5 TIME-DRAWDOWN CURVE
    0.8
    0.6
 I
I-1
•^1
o>
o
o

<
tr
Q
    0.2
    o.o
•


• M-3-4 GAS-DRIVE SAMPLER
A M-3-5 PVC PIEZOMETER





t
A
1 1 1 1 1 1 II







^W
^A- — ~H_»*
A A, A ^^ ^— — *"•
' 	 * y
•^
1 1 1 1 1 1 II
^

1 1 1 1 1 1 II





^:^



i 1 1 1 1 1 ii



.A
/v
<:?



1 1 1 1 1 1 II



0
K




1 1 1 1 1 1 II
      10"
                           IOU
10'
JO*
I03
                                           TIME, minutes

-------
     Figure  4-8 shows  horizontal  contours  of the measured
steady-state drawdowns  in  the  fractured bedrock layer.   Three
features  of this plot  are  significant.  First, note that the
maximum drawdown, occurring  at the  pumping well (PT-1),  is only
2.98  feet.   This is unexpectedly low,  indicating a very high
hydraulic conductivity.   Second,  the contours  are  nearly
circular,  indicating that  the  hydraulic conductivity is  nearly
isotropic in the horizontal plane.   Both  features strongly
support the representation  of  this  uppermost  fractured bedrock
zone as an equivalent porous medium (Brown and Gelhar,  1986).
Third  the existence  of the cutoff wall  appears not  to have
affected drawdowns in the bedrock.

     Steady-state drawdowns in the  overburden were vertically
averaged and contoured in Figure 4-9.  Drawdowns were less  than 1
foot and near the recharge  trenches were negative, due  to the
incremental mounding. The effect of  the  cutoff wall is  seen in
the 0.4 foot contour, which  is  skewed towards the northwest.  The
skewing likely  occurs for  two  reasons.   First, flow from the
northwest experiences  greater resistance,  thereby developing
larger drawdowns.  Second, the recharge  from the trenches  is more
likely  to be felt inside than outside of  the wall.  Nevertheless,
the former effect may have been  partly  ameliorated by placement
of  the pumping well close to the cutoff wall so that the
(ideally)  radial flow paths would be parallel to the wall.


     4.1.5  Analysis


     Hantush (1967)  presented  closed-form analytical solutions
for the drawdowns in  two  aquifers,  separated by a semi-pervious
layer,  due to pumping from one  of the aquifers.  This solution is
inherently unsteady,  because  all of the pumpage must ultimately
come from storage in the aquifers.  Therefore, for large time,
drawdowns will diverge.   However, during the pumping test,  all of
the pumped water was recharged to the  overburden via trenches 4,
5, and 6.  This  recharge provides  the  source of water allowing
the  system to  reach  steady-state, both in the field and, by
superposition, in the analysis.

     Figure 4-10 shows  the  idealized  geometry for the  pumping
test analysis.  The aquifers are  assumed to be infinite, with
homogeneous and isotropic  (but distinct) transmissivities  T^ and
T2, and uniform  storativities Si and 82-  (Here, as elsewhere,
subscripts 1 and 2  will refer  to the overburden and the bedrock,
respectively).  The aquitard  is also  infinite, with uniform
thickness, b',  and  homogeneous vertical hydraulic conductivity,
K'.  Flow is assumed  to be horizontal  in the aquifers and
                             4-18

-------
-]!—"-'
i!
II
                „.,

-------
I
ro
o
                                                                                     °o  _
              FIG. 4-9 MEASURED OVERBURDEN DRAWDOWN CONTOURS
                    LYLE  REED

                      BROOK
                                                             r
                                                            J-L.
                                                                                                \
                                                                                                  \
p
1
1
1
1
1
1




•
\
1
15 +00
1 '
1 1
1 '
1
/
                                                                                   0'  50'  100'   200'

-------
             OD
             m
             o
             %
             o
             o
inimii
       nnTTrmmnr
         en
k
                                       rn
                              t
                        iiiiniiiniiiiiiiniiiiiiiiiinn
                                                  *> Nl!
o 5;'

  ™
                                                  3>
                                                  z
                                                  m
     98

     Is
     O H
     m o

     H£

     m
     z
     o
     X
     m
     V)
                   p


                    i

                   O

                   TJ
                   C
                                                                m
                                                                c/>
                                                                H

                                                                6
                                                                m
                    N
                    m
                    o
                    o
                    m
                    o
                    z
                    m

-------
vertical in  the aquitard.  The  amount of leakage through  the
aquitard is  proportional to the difference in heads between  the
two aquifers.   In addition, storage in the aquitard is neglected.

     The actual elevations  of  the  stratigraphic units vary
considerably  throughout  the site.   For  example,  the top  of
bedrock  under the recharge trenches  is higher than the top of
till near the  pumping well.  However,  approximating these units
as horizontal is reasonable due  to  the semi-confining nature of
the till.

     The recharge trenches have been replaced mathematically  by a
single fully-penetrating (through the stratified drift)  recharge
well,  as shown in Figure 4-10.  While the recharge  trenches
actually add  water only at the water table,  approximating  the
trenches with a fully-penetrating well results in insignificant
errors when  calculating drawdowns near the pumping well.

     Let s^j  be the drawdown in  aquifer i due to pumping at a
rate Qj in aquifer j.   Then, Hantush's solution for large time
due to the pumping in the bedrock may be expressed as:
          92 =
            = 92 { In(ar2) + K0(0r2) }

            = 92 { In(ar2) - (Ti/r2) K0(/3r,) }

                Qi
                   r,)

                        1/2
               l\LlO


             b'
where  *2 is  the horizontal distance from the bedrock  pumping
well, t is the time  since pumping began,  and K(X) is the Modified
Bessel Function  of  the second kind and order zero, of argument x.
By symmetry,
          su = 91

          s12 = 9! (In(ari) + K0((3ri) }

                Qi
          91  ~27r(7\
                             4-22

-------
where r-^  is  the horizontal distance  from the overburden  well
The total  drawdowns  s^ and 82 are then  given  by
           = q (In(r2/n) + K0(0r2) +- (T./T,)
           = 9 { In(r2/n) - (Ti/rj) K0(0r2) -
     These solutions were evaluated numerically and contoured for
varying values of  the parameters T^, T2»  and   > commonly  known as
the leakance of the aquitard.  This procedure was iterative.  For
example,  if  the  calculated  drawdowns in the bedrock  were  too
large,  then  either the  transmissivity  of  the bedrock  was
increased, or the  leakance of  the  till  was increased,  or  both.
The values of these parameters which produced analytical contours
providing the best fit to the measured drawdown contours  (Figures
4-8 and 4-9)  are:

     0  overburden transmissivity = 3,500

     0  bedrock transmissivity    = 6,500

     0  glacial till leakance     =0.33  d~l

     The  analytical  drawdown  contours calculated using  these
parameters are shown in Figures  4-11  and 4-12 for the fractured
rock  layer and the overburden, respectively.  There appears to be
good correspondence between the  measured and computed drawdowns
in the bedrock.   The overburden match is  less accurate.   However,
consideration must be accorded  the heterogeneous nature of  the
geologic  setting   (especially  the  existence  of the cutoff wall),
the surface  water boundaries  nearby,  and the highly idealized
geometrical assumptions which were made.

     The  parameters  thus  calculated  in  this analysis  are
effective homogeneous values.   As such,  the analytical model  can
only  represent  a kind  of mean behavior  of the  system.   In
particular,  the   irregularities  in the overburden  must  be
neglected.
                             4-23

-------
I
(0
     FIG. 4-11  MODELED BEDROCK DRAWDOWN CONTOURS
                                                                           .V-
                                                 °0

                                                 •X
           LYLE  REED

              BROOK
                                                     5
o
o
                                                                          0' 50' 100'   200'

-------
     FIG. 4-12  MODELED OVERBURDEN DRAWDOWN CONTOURS
I
t>o
                                                       4
                                                    .J.J	
           LYLE REED

              BROOK
8
-H
m
                                                                            O1  50'  100'    200'

-------
     In the bedrock,  the calculated transmissivity is higher than
had previously been recognized.  Assuming  the  transmissivity is
concentrated in  the upper 10  feet of the  bedrock, as  is
consistent with  the logs of the pumping  well, PT-1,   and
observation wells  PT-2,  -3, and -4, then this zone has a
hydraulic conductivity of 650  ft/d.  The high  bedrock  hydraulic
conductivity and its  observed isotropy are mutually consistent
and agree with the observed  high  level of  fracturing in  that
stratum.

     The effective homogeneous transmissivity (3,500  ft2/<=i)
calculated  for the  overburden,  however, has probably  been
strongly  affected by the presence of  the  cutoff wall, and
therefore,  is considered to  be somewhat lower  than  the
transmissivity of the native material alone.   Therefore, the
calculated transmissivity  is considered  to be  useful  only for
lumping the behavior  of the  overburden as  it affects  the other
stratigraphic units in the analysis.

     Near  the pumping well, the  glacial till is  approximately 15
feet thick.  Given this thickness  and the computed leakance, the
glacial  till would  have an effective  homogeneous  vertical
hydraulic  conductivity of  5.0  ft/d.   This  is reasonable
considering the discontinuous nature  of  this stratum, and the
relatively small percentage of fines found  in the glacial  till
underlying the site.


     4.1.6  Conclusions


     Based  on a comparison  between the  measured  drawdowns in the
bedrock and stratified drift during a pumping test and analytical
drawdowns  similarly calculated  using  a mathematical  model,
effective homogeneous  transmissivities  have been evaluated for
both aquifers.  An effective homogeneous leakance for the glacial
till aquitard was also derived.   These calculated parameters
compared favorably with descriptive field data.

     The transmissivity of  the bedrock  was  found to  be 6,500
ft^/d.   Based on data  obtained during  drilling,  it is  apparent
that the upper ten feet of the bedrock  is highly  fractured and is
probably responsible  for the bulk  of  the  transmissivity.   The
hydraulic conductivity of  this layer  is  therefore calculated to
be 650  ft/d.

     The calculated transmissivity of  the overburden  was  3,500
ft2/d.   However, the existence of  the cutoff wall  has undoubtedly
affected this calculation.   Therefore, this  transmissivity is
                            4-26

-------
useful only  for  lumping the behavior of the stratified drift as
it affects  the other stratigraphic units.

     The leakance  of the  glacial till  was estimated to  be
0.33 d~l,  a value  which has  probably  been affected by  the
discontinuous nature  of this stratum.  Nevertheless, if the till
is considered to be fifteen feet thick (on average),  then  the
vertical hydraulic  conductivity of the till can be estimated to
be 5 ft/d.


4.2  Cutoff Wall Hydraulic Efficiency


     The  objective of this  portion  of  the work was to evaluate
the hydraulic efficiency of the  cutoff wall.  Cutoff efficiency
is  dependent upon  the wall's bulk,  as opposed  to intact,
hydraulic  conductivity.  The  intact  hydraulic conductivity
represents the in-place backfill material alone, whereas the bulk
hydraulic conductivity incorporates the combined effects of  the
intact material  and  any possible cracks and/or windows in  the
backfill and  inadequacies of  the  key to bedrock.  It  is  the bulk
hydraulic  conductivity which determines the large-scale hydraulic
behavior of the wall.

     The cutoff  wall  bulk  hydraulic conductivity can only  be
evaluated  indirectly,  by hydraulically  stressing  the upper
aquifer and  cutoff  wall while observing the hydrologic response.
Ideally, the  hydrologic response would be directly related only
to cutoff  wall hydraulic conductivity.   At the  Gilson Road  site,
however,both the  cutoff wall  in the  upper aquifer and the
underlying bedrock  aquifer  affect the flow of groundwater.   In
addition, the glacial till aquitard separating the two  aquifers
is relatively permeable, rendering it impossible to stress  one
aquifer without stressing the other.  Therefore,  it was ne.cessary
to separate multi-aquifer effects upon the groundwater system
before the performance  of the  cutoff wall could be  assessed.
Data yielded by the bedrock  pumping test (Section 4.1) provided a
good estimate of  the  bulk,  large-scale transmissivi ty of the
bedrock aquifer  and  the leakance of the glacial aquitard.   Thus,
the effects of these units could  be accounted for in the overall
response of the upper aquifer.

     A  three-dimensional finite-difference flow model of the site
had previously been calibrated for the design of  the hydrodynamic
isolation  system.   In  addition, numerous multilevel monitoring
installations existed at the  site, both inside  and outside of  the
cutoff wall.  Therefore,  cutoff wall bulk hydraulic conductivity
could  be  evaluated by  artificially  increasing  the  cutoff
hydraulic  conductivity  in the  numerical model and performing a


                            4-27

-------
sensitivity analysis comparing  simulated  vertical  piezometric
head distributions to the actual field heads.   The  actual  bulk
hydraulic  conductivity of  the cutoff wall was  taken  to  fall
within the range of conductivities  for which  the computed and
measured heads matched.

     Based  upon the above defined range of bulk conductivities,
it was possible to assess  the efficiency  of the  cutoff wall.
Cutoff efficiency was defined as  the ratio of  flux through the
overburden which had been  cut  off  to  that which would  have
occurred without the wall.   These fluxes  were  also determined
using the model.


     4.2.1  Test Constraints


     The investigation of post-construction cutoff  wall
efficiency  should encompass  the entire cutoff wall.  The impact
of design/construction issues such as  varying wall  depth,
overburden type,  magnitude and  direction of bedrock slope
relative to backfilling direction, etc. could then be addressed.
However, the large effort associated with  this  work required a
limited scope.  As such, the effort  concentrated on  a 1,000 foot
section of  the downgradient  wall.   This portion  of the wall was
judged likely  to provide the most salient data with respect to
containment performance for  a number of reasons.  First,  the
large  depth of the  wall  in this location  (up to 105  feet)
increased  the  potential for  imperfections and thus  for  bulk
conductivities exceeding specification limits.   Second,  under
non-pumping conditions, this area exhibited the  greatest  head
loss  across the wall and  thus  the  highest gradients  to drive
leakage through windows, if  they  existed.  Third,  the  highest
contaminant concentrations were found in the downgradient portion
of the site.   As such,  a given  degree of  leakage in  this  area
would  result  in the  most significant environmental  impact.
Fourth, the greatest degree  of groundwater manipulation  was to be
implemented in this area via the  hydrodynamic  isolation system.
Additional advantages  associated with  investigation of  the
downgradient wall from  a programmatic standpoint were previously
presented in Section 4.1.1.

     To evaluate  cutoff wall bulk  hydraulic  conductivity via
sensitivity analysis, the  cutoff  wall  must be hydraul ically
stressed  such that  the variation  in piezometric  head in the
vicinity of the cutoff  is large in comparison to  the  calibration
accuracy of the numerical  model.  To create this condition, the
head difference across  the cutoff wall must exceed two feet.
Initially, it  was envisioned that the 5 pumping wells associated
with the existing hydrodynamic isolation system  (see  Figure  4-1)


                             4-28

-------
could be over-pumped  to  stress the downgradient wall.  However,
the large bedrock  transmissivity,  as documented by the bedrock
pumping test  (Section 4.1),  precluded the development of adequate
drawdown in  the vicinity of  the wall.

     The criterion  that testing should  not cause  off-site
contaminant  migration  eliminated the possibility of increasing
the internal  heads as compared to the heads outside the wall.
This  could have  been  accomplished by  shutting  down  the
hydrodynamic  isolation  system and allowing the groundwater to
mound against the inside face of  the downgradient  wall.   If
necessary,  the head difference  could have been further augmented
by dewatering  Lyle Reed Brook.

     The above constraints  eliminated potential mechanisms which
could significantly stress  the downgradient  cutoff  wall.
Fortunately,  previous water  level monitoring data included  rounds
conducted  after cutoff  wall construction  but  prior to
implementation of the hydrodynamic isolation system.  One  such
data set, taken in June 1983, showed head differences across the
wall of over  3 feet.   This  data set was therefore adopted  as the
reference data set for the sensitivity analysis.


     4.2.2   Reference  Data Set


     The June 1983 reference data set includes piezometric heads
obtained at  117  points in 56  multi-level and single  level
monitoring  installations.   The  observation  wells and piezometers
used were installed according to  the methods  outlined in Section
4.1.3.1  In  addition,  water levels were  taken at 16 surface
stations along Lyle Reed Brook.  This  data set predates  the
bedrock pumping test,  and  as  such,  the monitoring installations
installed for  that test were  not in place.  However, the.re were
enough  multi-level  installations  to  adequately define the
vertical piezometric head  distribution inside and outside of the
downgradient cutoff wall.

     Figure  4-13   shows contours of water table elevations  during
the June, 1983 reference period.   The piezometric heads were
measured over a three-day  period, from June 3 to June 5, 1983.
This  data  was taken after a very  wet spring season,  and
represents  the highest internal/external head  differences
measured at  the site since cutoff wall construction.  At the time
the data was  taken, the  cutoff wall had just been installed and
the recirculation system was  not  yet in operation.   Near  the
eastern (upgradient)  end of the containment, the heads outside
the wall built up  in response to the low hydraulic conductivity
                             4-29

-------
   '983
 83
T
 83
                 o'

-------
of the barrier.   The  total drop across the upgradient wall was
approximately  2.5  feet.   Along the north and south sides,  flow
was inward, although  the head differences were typically  less
than one  foot.  At the downgradient end of the containment,  the
levels inside the wall were over 3.0 feet higher than outside the
containment  in response to mounding associated with flux through
the site.   Here the water levels outside the wall were largely
determined  by Lyle Reed Brook,  which has an average  slope of
0.002  in  this  section.

     The vertical head distributions near  the downgradient
portion of  the cutoff wall are  illustrated by wells  M-14  and
M-10R.  Installation  M-14 is located inside  the containment and
M-10R  is  located outside of the containment (see Figure 4-1  for
location).   The  head distributions are shown in Figure 4-14.
Note that due to  an error in seal placement, as discussed in
Section 4.1.4.2,  the  data points for M-14-3 and M-10R-3 were not
used.   However, the shapes of the head distributions presented
reflect a compilation  of data from other multilevel installations
adjacent  to  this location.

    A number of trends  in  this data should be noted.   First, in
the upper aquifer,  the data indicates a head drop of over 3  feet
across the  wall.  The  mounding on the inside of the wall reflects
the impedance generated  by the wall to  flux  through   the
containment.  Second,  on the inside of the wall, piezometric
heads  decrease with depth indicating downward flow.  The converse
is true outside of the  wall.  Note that if both the wall and the
bottom aquiclude  were totally impervious (no flow),  the head
distribution would be  vertical on both sides of the wall (no  head
loss with depth).  Third, the vertical gradient  is greater in  the
glacial till  than in  the sand and gravel  overburden as would be
expected based on the disparity in hydraulic conductivity of  the
deposits.   Finally,  the  head in  the bedrock inside  the
containment  is nearly identical to that outside the containment.
This is consistent with a bedrock of high  hydraulic conductivity
(low  head   loss with  flow)  confined by a  lower  hydraulic
conductivity glacial  till,  as defined during  the bedrock pumping
test (Section 4.1).   The above  data indicates that flux from
upgradient  in the containment mounds when it encounters the low
hydraulic conductivity  cutoff wall,  the mounding drives flow
through  the glacial  till  aquitard,  and the flow out of  the
containment  is then concentrated in the fractured rock below  the
wall.
                            4-31

-------
                  FIG. 4-14  VERTICAL HEAD DISTRIBUTIONS AT M-IOR 8 M-14, JUNE , 1983
>£>
I
00
NJ
   90--





   70-





   SO-





ia  30 +
«^-

•z.
o
       Ul
       _l
       U)
           .0 +
          -10--
         -30-1-
                     PIEZOMETRIC  HEAD (ft.)

                 76        77        78        79
                     OUTSIDE CONTAINMENT
                                                   M-IOR
              PIEZOMETRIC  HEAD  (ft.)

          78       79        80       81
M-14
               INSIDE CONTAINMENT

-------
     4.2.3  Numerical  Methodology


     The complexity of the hydrologic system at the Gilson Road
site renders closed-form  solutions  unsuitable  for  analysis of
cutoff bulk hydraulic conductivity.  This  is particularly true
because the distribution  of piezomenric heads reflects  the
geologic heterogeneity in both the vertical and horizontal planes.
In this case, over 1,000  lineal  feet of  cutoff wall  was  to be
investigated.  Therefore,  a three-dimensional numerical model was
required to correlate the  piezometric head  data generated when
stress  testing  the  wall.   Such a model  had  previously been
calibrated to the site for  design  of  the hydrodynamic  isolation
system and thus, this  capability was readily available.

     As previously discussed, the Gilson Road site  represents a
coupled system where response  to hydraulic stress is a function
of not only the cutoff wall bulk hydraulic conductivity, but also
the  characteristics of  the glacial till  aquitard  and  the
underlying bedrock  aquifer.  The first  step in isolating the
behavior of the  cutoff wall  from the  rest  of  the  hydrologic
system was to better define  the  transmissivity and leakance of
the bedrock aquifer  and glacial  till aquitard,  respectively.
This was accomplished via a  bedrock pumping test as outlined in
Section 4.1.  The hydrologic  parameters for  the upper sand and
gravel aquifer were  known from pumping tests executed as part of
the Remedial Investigation/Feasibility Study.   Therefore,  the
only  remaining  hydrologic unit  for which  the  parameters were
unknown was the cutoff wall itself.

     Under hydrologic stress  conditions,  the horizontal vs.
vertical flux through the upper  aquifer  is  a function of  the
unknown bulk hydraulic  conductivity of  the  cutoff wall as
compared  to the  known conductivities of the underlying
aquiclude/aquifer  system.  The  distribution of  vertical
piezometric heads  reflects the  flux  vector.   For high  wall
conductivities,  relative  to  conductivities  below the wall, the
flux would primarily be horizontal  through  the upper aquifer,
yielding little  variation in head with depth.   For low relative
wall hydraulic conductivities,  flux  would be more  vertical
commensurate with  flow under the wall.  This condition would be
reflected in varying piezometric head  with depth.   Naturally,  the
degree of variation  in the vertical heads  is also dependent on
the relative conductivities of the units  adjacent to  and  below
the wall.  The multi-level monitoring network established at the
site allowed measurement of the vertical  head distribution for
various stress  states.   This  data,  in conjunction  with the
numerical model, provided the capability for cutoff  wall bulk
hydraulic  conductivity  evaluation via  numerical  sensitivity
analysis.


                            4-33

-------
     A range of  bulk  conductivities were input into the
calibrated model and the vertical heads generated were compared
to the actual field  head  distribution for  a given stress state,
the June  1983 scenario.   Bulk  conductivities  which produced heads
matching  the field data,  to  within  the model calibration
accuracy, were taken to be  possible representations of  the actual
state of  the cutoff  wall.   Conversely, simulated  bulk
conductivities which did not generate matching heads were  assumed
to be invalid.


         4.2.3.1  Model Description


     The  sensitivity  analysis  was performed using  a
three-dimensional  finite-difference  program (described  in
Trescott (1975) and Torak  (1982)).  Features of this code include
aquifer  heterogeneity and  anisotropy, steady or  transient
simulations, variable  grid spacing and a phreatic surface in the
uppermost layer.   The  solution is  found  using the strongly
implicit  procedure.3

     A cutaway view of  the model is shown in Figure 4-15.   A  plan
view of the top layer  is  shown  in Figure 4-16,  with the nodes
representing the  cutoff wall, Lyle  Reed Brook,  and Trout Brook
indicated.  The model has five layers vertically, and a  48  x  50
grid horizontally.   The horizontal  grid spacing varies from 180
feet near the boundaries to 40 feet in the vicinity of  the cutoff
wall.  The bottom layer of the  model is 50 feet thick, with its
center at elevation -28  feet (with respect to the City of Nashua
datum).   The next layers are  30,  20, 20, and 50 feet thick,
respectively.  The top layer is artificially thick to allow the
water table to vary  without  restraint.  This extra thickness  is
not shown in Figure 4-15.

     Most  of the borders  of  the  model, including  those
representing constant heads,  were no-flow boundaries.  The one
exception is at the  downgradient end of the model, where a fixed
constant  flux was  simulated by a  series of virtual pumping wells.
Precipitation-generated  recharge  was applied uniformly  as a
source to the nodes in the  top layer,  except   in areas  covered  by
the impermeable surface cap.  The recharge  which would have  been
applied in these  areas was added to nodes   around the cap,  in
accordance with the known cap  contours.
3A numerical technique used  to  solve the piezometric head matrix
                             4-34

-------
           ELEVATION,feet
Ul
o
1


LAYER
o

oj en -si to
O 0 O 0
i i i i
r r r r
$55$
3333
   r-O
   .o
   *^o
    o
X

o
5

M

O
CO
o
m
(O
    ro
   _o
   ^
    OJ
   _o
    o
    o
   o
   o
   o
2)
p


 i

oi

O
c


i

5

<

m


o
-n
z
c
S
m

o
                                                     o
                                                     O
                                                     m

-------
                            FIG. 4-16  PLAN VIEW OF TOP LAYER OF MODEL
I
CO
                                                                        MARSHES
                      o1

-------
     During the calibration  procedure, the cutoff  wall hydraulic
conductivity  simulated was the design hydraulic conductivity of 1
x 10-7 cm/sec, as based on quality control test data  (Section 2).
The actual conductivities of the model nodes  representing the
wall were, however, ten times greater in order to account for the
40 foot node width as compared to  the 3 to 4 foot wall thickness.

     In order to  reduce  complexity,  the model was used  to
simulate steady-state conditions only.  No transient  simulations
were performed for  this effort.   Each simulation  treated all of
its boundary  conditions as constant, although  the  values  of the
boundary parameters were changed from simulation  to simulation.
In cases where a  condition was actually time-varying, it  was
replaced by  an  equivalent  steady-state condition.   The most
obvious example of  this  is the  areal  recharge due  to
precipitation.  For example, in the calibration  for  the  June,
1983,  scenario, the  applied recharge was 42  inches/year.   This
value  exceeds the probable yearly average recharge  to the area by
a factor of  two.   However, it is reasonable  as  an effective
steady-state  recharge  for the three-month period  preceding that
date,  as based on meteorological data.

     The other transient  conditions  simulated by  the model were
judged to be  changing  slowly enough that their values at  any
point  in time could be (and  were)  used as steady-state  input.
For example,  constant head nodes were used to represent  Lyle Reed
Brook and  Trout  Brook,  as  well as  the  swamps and marshes
upgradient of  the site.   The specified heads varied  spatially and
between simulations, but were constant at any one node during any
one simulation.
          4.2.3.2  Model Calibration

     The model had originally  been calibrated for  two water level
data sets,  representing the system's state in January,  1982,  and
June, 1983.   The  current effort included further calibration to
reproduce two  additional water  level data sets,  (October 1983  and
September  1985),  for a total of  four different stress conditions.
(The four data sets will be abbreviated as JAN82, JUN83,  OCT83,
and  SEP85).   The  stress conditions which these  scenarios
represent  are shown in Table  4-2.   The additional calibration
effort  incorporated improved understandings of system behavior as
well as  new, better and/or more extensive data.   In particular,
the bedrock transmissivity which was determined from the bedrock
pumping  test  was  explicitly  incorporated.  Also, further data
regarding seasonal variations in surface water levels  proved
helpful  in improving the ability of the model to represent  the
behavior of  the  aquifer/cutoff wall  system  in  response to
different recharge rates.


                            4-37

-------
     Parameters varied  during model calibration  included the
hydraulic conductivities and anisotropies of  the soils,  the
amount and distribution of recharge, and the amount  of subsurface
drainage  (constant flux) out of  the model at the downgradient end.
The  values of  recharge  and constant flux used  in each of the
calibrated simulations are shown in Table 4-2.  In all cases,
parameter variation remained within ranges previously established
based on  the subsurface data amassed for the site.
                           TABLE  4-2

             STRESS SCENARIOS AND  SIMULATION FLUXES
Date
Wall &
Cap
H.I.
On
1
Sys.
Constant2
Flux (cfs)
Recharge
(in/yr) Descriptive
 JANS 2
 JUN83
 OCT83
 SEP85
 no
yes
yes
yes
 no
 no
 no
yes
0.240
0.363
0.128
0.240
20
42
 6
 8
medium
high
low
low
1    Hydrodynamic isolation system
2    Flux  rate for downgradient  boundary condition
     Three measures  of  the degree of calibration  were used.
First, statistics  were calculated for the deviations between
measured piezometric heads and  those calculated at  the homologous
nodes in  the model.   This provided a quantitative estimator of
the degree of  calibration as a whole.  Second, visual comparison
of water table  elevation contours  ensured that  important
qualitative features were preserved.  Finally,  care was exercised
to see that the vertical distributions of modeled  heads  matched
well with the field data.

     The  statistical  measures  used were the maximum  and minimum
deviations between measured  and modeled heads,  the average
deviation, the average of the absolute deviation, and  the RMS
deviation.  The latter measure  is  equal to the standard deviation
when  the average  deviation  is  zero.   These statistics are
presented for each calibration  run in Table 4.3  and  indicate that
all of the runs are calibrated to  a high degree.
                             4-38

-------
                           TABLE  4-3

               CALIBRATION DEVIATION STATISTICSl
  Date    Maximum     Minimum    Average     Ave. ABS     RMS
JANS 2
JUN83
OCT83
SEP 8 5
0.84
1.11
0.75
1.33
-0.77
-0.70
-0.87
-0.64
-0.08
0.06
0.04
0.17
0.27
0.33
0.30
0.29
0.35
0.41
0.36
0.43
     1A11 values in feet.   Data  analysis included the piezometric
head data from all five layers.
     Figures 4-17, 4-18,  4-19,  and 4-20 show the measured water
table contours  for  the four  calibrated scenarios and  their
modeled counterparts.  In general,  the calibration was quite good
as demonstrated  by the figures,  although there  were some minor
discrepancies which could not  be resolved.  In JAN82, most of the
contours match,  although the modeled heads were somewhat lower
than the measured heads in the southern portion of the site.  The
OCT83 attempt however, suffers  with  respect to  the contours from
78 to 80 feet.   In  SEP85, the field data shows a steep gradient
from trenches 4,  5, and 6 towards pumping wells A through  E,  but
then  a  very flat gradient from the wells  to  the  wall.  This
abrupt  change  in slope was difficult to capture in the  model,
resulting in  a high maximum deviation for the  run.   It is
hypothesized  that  the  mismatch  was due to the  effects  of
simulating  the wells and trenches with the relatively  coarse grid.
Nevertheless, the discrepancy should not  strongly affect leakage
estimates  because it is located away from the  highly  sensitive
upgradient and  downgradient ends  of the site.   Note that  the
modeled head differences across the downgradient portion of the
wall are similar to those shown by the field data.


     4.2.4   Sensitivity Analysis


     The sensitivity analysis  was performed by varying the cutoff
wall bulk hydraulic conductivity  (the  parameter under
investigation)  in the  model  and  evaluating the degree of
correspondence between  the   numerically generated head
                             4-39

-------
FIG. 4-17  JAN. 82 SCENARIO CALIBRAT ION

-------
Oo,
          ,0

-------
          FIG. 4-19  OCT. 83 SCENARIO CALIBRATION
       76
    \
I
^
CO
                                                                                                    83
                           78
                                         79
                            MEASURED

                            MODELED
                                                                                       0'  50' 100'   200'

-------
       FIG.4-20SEPT. 85 SCENARIO CALIBRATION
   \
i
*»
u>
                                                                        8]  81
                                        82   82   83
            76
                                                                                                       83
                   77
                               '78





                            MEASURED


                            MODELED
79
                                                                                          o1  so1 100'    200'

-------
distributions and  the actual field measured data.   The  bulk
hydraulic conductivity was varied over four  orders  of  magnitude
in five equal steps.  The initial  value input for bulk hydraulic
conductivity was 1 x 10~7 cm/sec.   This value, equal to  the
specification criterion, was used  during  model calibration^.
The next four sensitivity runs used precisely the same input
data, except that the cutoff wall  bulk hydraulic conductivity in
each run was increased by a factor  of  ten over  the previous  run.
The  greatest bulk hydraulic conductivity used during  the
sensitivity analysis  was 1 x 10"3 cm/sec.  This value  is within
one order of magnitude of the average hydraulic conductivity of
the upper sand and gravel aquifer (10~2 cm/sec).

     The results of the  sensitivity  analysis are  shown  in
Figure 4-21.  For each run, the computed heads at the nodes
corresponding to multilevel wells  M-14 and M-10R were plotted and
compared to the field data.  The  first run  (1 x 10~7 cm/sec)
generated a head distribution which matched  the field data to
within about one quarter of a foot.  On the  inside of  the  wall
the  simulated heads were somewhat higher  than, but closely
followed  the trend  of,  the measured  heads.    Outside  the
containment, the simulated heads  again  followed the  trend
exhibited by the measured heads, but  were  not consistently
greater or  less than the measured  heads.  This  data  set
represents the calibration accuracy  of the numerical  model in the
vicinity of the downgradient wall.  As previously  indicated, it
was generated as the final run used  to calibrate the  numerical
model for the JUN83 scenario.  The  second run (1 x 10-6 cm/sec)
generated heads that  were nearly identical to  the first run.  A
single piezometric head distribution was therefore presented on
Figure 4-21 for both  runs.

     For  the third run, the bulk hydraulic conductivity of the
cutoff wall was increased to 1 x  10~5 cm/sec.  The generated
heads in this case diverged noticeably from the first  two runs.
However, they still correlated with the  field measurements to
within  the error band defined by the accuracy of the initial
calibration.  Therefore, 1 x 10~5 cm/sec, as  well as lOx 1~6 and
1  x  10~7  cm/sec,  represents a possible  cutoff wall  bulk
hydraulic  conductivity  to the  extent that  it meets  the
constraints imposed  by the sensitivity  analysis.  Further
increases in bulk hydraulic conductivity  (runs  4 and 5)  resulted
in head distributions which no longer matched the field  data.  As
such,  these values  (1 x 10~4  and  1 x  1Q-3 cm/sec)  do  not
4The value  of 1 x 10~7  cm/sec used for model calibration was
selected as based on quality control field data obtained during
cutoff wall construction; see Section 2.
                            4-44

-------
         FIG. 4-21 MODELED VERTICAL HEAD  DISTRIBUTIONS FOR DIFFERENT WALL CONDUCTIVITIES
                       PIEZOMETRIC  HEAD (ft.)

                   76        77       78        79
                                                               PIEZOMETRIC HEAD (ft.)

                                                           78        79       80       81
           90 -r
            70--
           50--
 I
£>
Ul
         OJ
30--
         UJ  I0-|-
           -10--
          -30-1-
                        OUTSIDE CONTAINMENT
                                                                  INSIDE CONTAINMENT
                       SIMULATED  BULK
                        CONDUCTIVITY
                       I07, I06 CM/SEC

                          10s CM/SEC
                             VERTICAL HEAD
                             DISTRIBUTION
                          10 CM/SEC      —-.<
SIMULATED BULK
 CONDUCTIVITY
   103 CM/SEC
                                                                 MEASURED, 6/83
VERTICAL HEAD
 DISTRIBUTION

-------
represent valid possibilities  for the bulk hydraulic conductivity
of the cutoff wall.

     The above analysis indicates that bulk conductivities lower
than  1 x 10~5 cm/sec  are  all, to the extent definable by the
sensitivity analysis,  plausible representations of the  cutoff
wall's impedance to flux.   The  analysis also indicates that bulk
conductivities in  excess  of 1 x 10~5 Cm/sec  begin to yield head
distributions which no longer match the field condition and are
thus  considered invalid.   It is  emphasized that  the analysis only
demonstrates that the value of  1  x 10~5 cm/sec is an upper bound
on the cutoff wall  hydraulic conductivity.  This should not  be
misinterpreted  to  mean  that the actual bulk  hydraulic
conductivity of the cutoff wall is 1 x 10~5 cm/sec.  In fact,
significant data indicates  that the actual value is much  lower,
in the range of 1 x 10"7 cm/sec (see Sections 2 and 3).

     The inability of  the sensitivity analysis to provide a
definitive evaluation of the cutoff wall bulk  hydraulic
conductivity, with  respect to the specification criterion of  1 x
10~7 cm/sec, is a direct result of the much higher conductivities
associated with the containment bottom (glacial till and bedrock).
This is due to the coupled  hydraulic behavior  of the containment
system which  is analogous to an electrical  circuit containing
resistors in parallel.  As such, the sensitivity analysis can
only  resolve the  hydraulic conductivity of a specific individual
hydraulic  element  to a  degree proportional to the  highest
hydraulic conductivity exhibited by any element in the  system.
This is demonstrated by the data in Figure 4-21.  As the  cutoff
wall  hydraulic conductivity is increased from 10-7 cm/sec,  the
bedrock flux continues to dominate the heads,  and thus the  amount
of fluid flux through the wall increases roughly linearly with
it's hydraulic conductivity.  The increase  in  flux through  the
wall  is small enough, however,  that  it has no discernable effect
on the heads.  As  the wall flux eventually becomes  significant
with  respect  to  the bedrock flux, a concomitant decrease in the
overall gradient  occurs as reflected  in  the vertical head
distribution.   The  high bedrock  transmissivity, therefore
effectively masks  the cutoff wall hydraulic  conductivity below
10~5  cm/sec.  If  the bedrock had a  lower  transmissivity,  then
this critical  masking level  would occur at  a  lower wall
hydraulic conductivity.  An upper bound could then be established
which would be more  consistent with the value specified  for  the
cutoff  wall bulk  hydraulic conductivity  (1 x 10-7 cm/sec).  This
limitation is  inherent  in any hydraulic  stress  analysis.
Furthermore,  in  as  much as hydraulic analysis  is the only
mechanism available  to evaluate bulk hydraulic conductivity,  the
limitation  applies to  the viability  of  post-construction
verification in general.
                             4-46

-------
     4.2.5  Cutoff Wall Efficiency


     The effectiveness of the cutoff wall as a barrier technology
is a  function  of  its ability  to  arrest fluid flux.   It is
therefore  necessary to determine the  amount  of flux before  and
after  the  installation of the wall.   The  effectiveness of  the
wall  may  then  be quantified as the ratio of flux through  the
overburden which has been eliminated  by  the  cutoff wall, to that
which  would have existed without the wall.  This ratio is  defined
herein as the "wall efficiency".

     An  alternative  definition of efficiency is the ratio of
total flux through  the entire site  (overburden and rock) which
has been cut off to total flux through  the  entire site before  the
installation of  the wall.  However,  this ratio  is suited only to
an  evaluation  of  the effectiveness of the entire passive
containment system (cap,  cutoff  wall and bottom aquiclude)  and
not the  effectiveness of the wall  as  a technology per se.  This
ratio is termed  the "containment efficiency".

     The flux values  required to compute  the  above  ratios were
determined using a postprocessor  adjunct  to the flow model.  In
this program,  the  transmissivity and  head matrixes are  used to
calculate the fluid flux out of the  site through each node in or
under  the  simulated  cutoff wall.   The  resulting fluxes  are
reported by layer, by horizontal node, and by  element type (wall
or rock).

     In  addition to the three calibration runs5 JAN82,  JUN83,
and OCT83,  six more runs were performed  on the  model.   These  six
runs represented the system under the combined conditions  of low,
medium, and high recharge,  with and  without the cutoff wall.  A
cutoff wall hydraulic conductivity of 1 x 10~7 cm/sec was used
for the wall.  The postprocessor was  used  to calculate the fluid
fluxes through  the  rock and overburden/cutoff wall nodes  in each
of these runs.   The results are shown in Table 4-4.
5The SEP85  run  is not included herein  because it models a scenario
with the hydrodynamic isolation system in operation.  As such,
flux through  the site/wall is a function of pumping rates as well
as barrier  conductivities.
                             4-47

-------
                         TABLE 4-4


                    MODELED OUTWARD FLUXESl
                     No Containment            Wall and Cap
 Recharge             Wall2     Rock            Wall3    Rock
low
medium
high
74,386
89,248
121,982
29,635
32,833
39,116
73
79
93
65,001
66,578
73,668
     values in gallons per day
2native  overburden permeabilities
3wall hydraulic conductivity = 1 x 10~7  cm/sec
     Table 4-4  shows that,  before  installation of the cutoff
wall, the  flux through the  rock is about one-fourth of the total
flux through the site.  After cutoff installation, the rock flux
is roughly doubled,  due to  the increased gradients created by the
wall.  However, the  flux  through the overburden is effectively
eliminated.  Therefore, the containment efficiency of the passive
physical  barriers  at the Gilson Road  site is approximately
55 percent under  worst  case  precipitation induced stress
conditions.  Please note,  however, that this does not include the
effects of  the hydrodynamic  isolation  system,  (the  active
component  of the  total  containment) which is  designed to
completely eliminate off-site migration  of  contaminated
groundwater.

     The  sensitivity runs  used  to  establish an estimate for
cutoff wall bulk hydraulic  conductivity were also passed through
the  postprocessor.   The calculated  fluxes out of the site for
these runs are shown in Table  4-5.  Based on these fluxes and the
entry  in  Table  4-4 for  high  recharge^ no  containment, it is
possible to calculate the wall efficiency for each run.  Based on
the  sensitivity analysis, the cutoff  wall bulk  hydraulic
conductivity was determined  to be less then 1 x 10~5  cm/sec.
Therefore,  Table  4-5 shows that the wall  efficiency must be
greater than 93 percent.
6The high recharge data for  the no containment  case was selected
to match the JUN83 scenario  upon which the sensitivity analysis,
and thus the data in Table  4-5, was based.
                             4-48

-------
                          TABLE 4-5

                    SENSITIVITY RUN FLUXES

Cutoff Wall
Bulk K
(cm/ sec)
10-7
10-6
10-5
10-4
10-3
Flux through the Site
(
Total
73,761
74,117
77,417
95,800
126,165
gallons per
• Wall
93
830
8,361
45,036
90,814
day)
Rock
73,668
73,287
69,056
50,764
35,351
Wall
Efficiency
99.92%
99.32%
93.15%
63.08%
25.55%

     4.2.6  Summary


     The bulk hydraulic conductivity of the downgradient section
of the Gilson Road cutoff wall  was  evaluated using a numerical
sensitivity analysis.  Three-dimensional finite-difference flow
modeling provided comparison  of simulated vertical piezometric
head distributions to  actual  field measures head distributions
for varying values of cutoff  wall bulk hydraulic conductivity.
An upper bound of 1 x  10~5 cm/sec  was thus  established, for the
cutoff wall.  Further  definition of the actual bulk hydraulic
conductivity below  this value was not possible using  stress
testing due to the large bedrock tramsmissivity and the practical
limits  on  the  calibration  of  the model.   However,  the
considerable quality control  data obtained during construction
(Section 2) indicates  that the  hydraulic conductivity of the wall
is approximately 1 x 10"^ cm/sec.  This value  is  consistent with
the  stress testing results  in that stress  testing yielded an
upper bound only.

     Inasmuch as  only an upper bound  value  for  the  cutoff wall
bulk hydraulic conductivity could be determined via stress
testing,  evaluation  of  the  wall efficiency (ratio of  the
overburden flux  eliminated to  the  overburden flux without the
containment) was  limited to a lower  bound solution.  Based on the
                            4-49

-------
results of the sensitivity analysis,  the wall efficiency for the
cutoff wall was found to be greater  than  93  percent.   This is
based  solely upon  the  upper  bound value  for  bulk hydraulic
conductivity established by the sensitivity analysis,  and as such
is a worst case  condition.   A  more probable  value for wall
efficiency  is over 99%  as obtained based  on the quality control
data  which  indicates a  wall  hydraulic  conductivity  of
approximately 1 x 10~7  cm/sec.


4.3  Groundwater Quality Monitoring


     As part  of  the  evaluation of  the  effectiveness of the cutoff
containment wall installed at the Gilson  Road  site,  groundwater
samples were obtained and analyzed.  The  data generated by the
groundwater  sampling and  analysis  program provided direct
evidence  of  remedial action performance by establishing
contaminant location in temporal and spatial dimensions.   The
groundwater quality  data, when used  in concert with the  hydraulic
evaluations (Sections 4.1 and 4.2), aided  in  the evaluation of
the long-term environmental impact and overall effectiveness of
the cutoff wall containment.

     Useful information, such as the determination of  containment
flow paths, was gained by comparing  groundwater contamination
data from monitoring points located within  the same geologic
strata but  on opposite  sides  of the  containment wall.
Additionally,  groundwater quality  data  collected over a
relatively long  period of time  allowed evaluation of  the
effectiveness of milestone events which  have occurred at the
Gilson  Road site.


     4.3.1  Location  and Installation of Groundwater Monitoring
           Wells


     The installation of groundwater monitoring wells on the
Gilson  Road site dates back to 1979.  Since that time both single
and multi-level monitoring wells have been  placed at  strategic
locations to provide data on  the horizontal  and vertical
distribution of contaminants (see Figure  4-22). Monitoring wells
installed by the  state of New  Hampshire in  1984 were placed
primarily on the  downgradient,  or western, end of the site.  The
location of the monitoring points were  selected so as to provide
water quality data in  similar geologic formations  but on opposite
sides of the cutoff wall.  The geologic formations consist of a
relatively thick sand  and gravel deposit  overlying a glacial till
                            4-50

-------
                                                      20'
FIG. 4-22 LOCATION OF GROUNDWATER MONITORING POINTS



                                           M-




                                  +       _^r
                                      	&
                    o
                    o


                    8
_f_

 -+-
                   -+-
                    Ae
                 +  +*
                                   -f
                                  -f
                                    -4-
       LYLE REED

        BROOK
  A     EXTRACTION WELL



r™_T_rr RECHARGE TRENCH




        MULTI-LEVEL MONITORING POINT

                                                       it'OO'
                                    -f-  SINGLE-LEVEL MONITORING POINT




                                        STREAM SAMPLING POINT
                                                                                           200'

-------
which, in turn,  overlies  fractured bedrock.  Monitoring points
were placed within  the sand  and gravel  deposits  and at the
interface of the  sand  and gravel and till deposits and  at the
till-bedrock interface.

     Installation of the monitoring  points  was consistent with
the  methodology  discussed  in Section  4.1.3.   A  typical
installation is depicted in Figure 4-3.


     4.3.2  Sampling and Analysis


         4.3.2.1  Sampling of  Monitoring Points


     The  sampling of the monitoring points to obtain groundwater
samples has occurred since  1979.   Samples were collected  over  a
series of  milestone events  which have occurred on the site.
These  events include  the  initial site assessment period, the
installation of an  emergency  recirculation system, the
emplacement  of  a cutoff  wall  and  impermeable cap,  and the
operation  of   a  permanent  groundwater  hydrodynamic
isolation/recirculation system.  Over  330 chemical analyses were
completed for  the site during this period.  Sampling rounds just
prior to  and subsequent to  cutoff wall installation have  included
70 analyses.

     Observation  wells were sampled  using  1-inch stainless steel
bailers.  Three times the  initial volume of  the well was
evacuated prior  to collection of groundwater quality  samples.
Gas-driven sampling points  were sampled using ultra-high  purity
nitrogen gas  in accordance  with the methodology  outlined  in
Barvenik, 1984.  Groundwater samples collected from the site were
placed in  ice-filled  coolers and  delivered to EPA certified
analytical laboratories for chemical analyses.


         4.3.2.2  Analysis of  Groundwater Samples


     Groundwater  samples collected  from The Gilson Road  site were
initially analyzed for the  full range  of priority pollutants.   In
addition,  a  number  of   non-priority pollutants were  also
identified.  This  data indicated  the primary contaminants on-site
were volatile  organic compounds  (VOCs).  VOCs were therefore used
to characterize and monitor contaminant levels both spacially and
temporally.  VOC  analyses were  executed using EPA Method  624 for
priority  list pollutants and equivalent methodologies  for VOCs
                             4-52

-------
not found on the priority pollutant  listing but known to exist
on-site.


     4.3.3  Results of Groundwater Quality Monitoring


         4.3.3.1  Selection of Pertinent Groundwater Monitoring
                  Points
     As previously mentioned, a large  number of  groundwater
monitoring points have been  installed  on  the  Gilson Road site.
These points were  sampled for  groundwater  quality  information
since 1979.  As a result, a large volume of data exists regarding
the  distribution  of  contaminants on the site.   In order to
evaluate changes in groundwater  quality  in  response  to  the
installation of  the cutoff wall,  a subset of  all  of  the
groundwater monitoring points was chosen for detailed analysis.
The monitoring points selected for  this  analysis satisfied the
following criteria:

     0   The  monitoring  points were located at  the  downgradient
        portion  of  the  site  where  head loss across  the  cutoff
        wall,  and therefore  resulting  contaminant migration out
        of the site, is greatest;

     0   The  monitoring  points were composed of  multi-level
        installations located  within the  three major geologic
        strata present  on  the  site,  whenever possible, in order
        to  provide vertical  contamination distribution
        information, and

     0   The monitoring points were  sampled  over  an extended
        period of  time  covering  the  major milestone  events
        which occurred during remediation of  the site.

     Based  upon the  above requirements, five groundwater
monitoring points were chosen for detailed  analysis.   These five
monitoring  points show contaminant  concentrations which  are
representative of the general trend in  contaminant distribution
of the downgradient portion of the site.  In addition, a  surface
water sampling point located downgradient of  the cutoff wall  and
along the monitoring point cross-section line was included in the
                            4-53

-------
analysis?,  Tt  should  be  noted that while the monitoring  well
concentrations are  representative of the site in general,  data
gaps do exist throughout  the sampling history.  These data gaps
were typically  the result of changing conditions  on the  site
during the remediation effort.  Monitoring well placement and
sample selection were  primarily in response to specific  data
needs associated with  remediation and as such were  not  always
compatible with  the cutoff  wall  evaluation effort.

     The  location  of monitoring wells, as they ultimately relate
to the cutoff  wall  evaluation,  were  influenced by several
factors:

     0  As monitoring wells were destroyed and replaced over the
       relatively  long history of the site, new locations for
       wells were  selected  so as  to  reflect crucial  data
       requirements at the  time of  installation.   As such,
       destroyed monitoring locations were not always  replaced.

     0  Prior  to the installation of  the cutoff wall, there was
       no reason to place  monitoring wells in close  proximity to
       each  other.   Such an alignment  only became  productive
       once  the wall was  in  place  to  allow comparison  of
       contaminant levels  inside and outside of the  containment.

     Given the  large number of sampling points located  on the
Gilson Road site,  not  all monitoring points could be sampled
during each round  of data collection.  The selection  of sampling
points was also  influenced  by several factors:

     0  The selection of  sample locations was in response to the
       historic location of the contaminant plume  on the site.
       The dynamics of the plume meant  that different sampling
       points would be monitored so as to track plume  movement;

     0  The  selection of  sample locations under the  current
       contract was performed under a limited budget  and  was to
       meet multiple objectives.  The  groundwater quality data
       was collected for the purpose of  cutoff wall  evaluation
       and also to supply data to the State of New  Hampshire for
       performance evaluation of the groundwater extraction and
       treatment system.
'In order  to bridge the milestone  events, data from two surface
water sampling points were combined into one point.   The two
surface water monitoring points  are located in close proximity to
each other and show similar concentration levels and trends on
dates where analyses were performed on both sample  points.
                             4-54

-------
    The  result of  the  competing factors for monitoring well
placement  and sampling location yields a history of groundwater
quality on the site which contains some data gaps.  However,  the
monitoring points chosen  for detailed analysis give a general
trend in contaminant distribution which can be used to evaluate
the effectiveness of the  cutoff wall.   The  monitoring  point
cross-section line is shown in  Figure 4-23.


          4.3.3.2  Selection of an Indicator VOC Compound


     The  selection of a  single compound as an indicator for total
VOCs allows for accurate  comparison of data collected over an
extended  period  of time.   This allows the data  to be less
sensitive  to changes in the priority and non-priority pollutant
VOC list  for which the samples were analyzed.  Since a large
percentage of the   total VOCs detected  on the  site  were
non-priority pollutant  VOCs,  the groundwater samples were  not
always analyzed for the same suite of compounds.  Therefore,  the
comparison of data  collected over a long period of time is more
accurate in th'is case through the use of an indicator compound
than through comparison of  total VOC concentrations.

     The  results  of the  chemical analyses for VOCs on groundwater
samples from the Gilson Road  site indicated the presence of  one
VOC at very high  levels in almost all samples.  Tetrahydrofuran
(THF)  comprised more than 90 percent of the VOCs present in most
of  the groundwater samples  collected from the  site.   This
compound was selected an  an indicator for total VOC distribution
on the site for the following  reasons:

     0 Tetrahydrofuran,  in  most samples,  comprises a large
       percentage of the total VOCs present in the sample.  In
       most  cases it is present in excess of 90 percent  of  the
       total VOCs;
     o
        THF is relatively  soluble in water and is not readily
        absorbed by soil particles; and

     0   THF is not significantly biodegradable in the subsurface
        environment.

     As a  result,  the compound makes a  good indicator for
contaminant distribution and allows for comparison of groundwater
quality data  over  relatively long periods of time.  This data is
summarized  in  Table 4-6.
                            4-55

-------
                      FIG. 4-23 LOCATION OF SELECTED GROUNDWTER MONITORING POINTS
i
171
        A   EXTRACTION WELL


            MULT I-LEVEL MON ITORING POINT


            SINGLE-LEVEL MONITORING POINT


       •+•  STREAM SAMPLING POINT
LYLE REED
  BROOK-
0'  SO'  100'    200'

-------
                           TABLE 4-6

     CONCENTRATIONS OF TETRAHYDROFURAN IN PARTS PER MILLION
Well                         Sampling Late
Location  7/81   1/82  3/82  5/82  7/82  11/82  4/83  1/85* 10/85
A-10
M-23-1
M-23-2
M-23-4
M-3-1
M-3-2
M-3-3
M-3-4
NHDB-04
M-4-1
M-4-2
M-4-3
M-4-4
M-7-2
M-7-4
850
16
26
68
170
12
54
34
— ' 4.4
— —
— —
— —
572 46
3.2 5.0
25.1 17.8
34.2 —
— —
1.2 1.3
— —
— —
— —
— —
10
5.2 —
178 55
0.89 —
1.8 ~
2.2 12
68
0.4 0.9
3.7
33
1.3
46
8.8
— —
59
150
83
84
17
1.4
1.9
—
110
—
110
76
10
0.04
0.69
5.0
0.3
—
—
ND
35
—
—
0.045
10.0
80
ND
—
—
—
—
0.06
80
85
80
— Indicates data  not taken
*QA/QC data indicates a possible laboratory dilution error.
          4.3.3.3  Data Discussion


     The  distribution  of  THF  for the selected groundwater
monitoring points  is displayed both  spatially and temporally  in
Figures  4-24  a and b.  An examination of  the data contained  in
the figures  reveals several trends in the distribution  of the
contaminants  in response to the milestone events which occurred
on the site.

     A.   Contaminant Distribution During Initial Site Assessment

         Contaminant distribution  on the  site, as indicated  by
         the  initial site assessment data,  shows the movement  of
         contaminants from the  center of  the site towards Lyle
                             4-57

-------
           T5
it*
 I
Ln
CO
          45
       CO
       Z  J,
       o
       t-
          -15
                                            FIG. 4-24b VARIATIONS IN CONTAMINANT DISTRIBUTION

                                                                                 M-4-
LEGEND:

       SAND ft GRAVEL
       GLACIAL TILL
                                                                                                 BEDROCK
                                                                                                    20'     40*
                                                                                                    HORIZONTAL SCALE
                                                                                                                       •0'
SAMPLE
DESIGNATION
1
t
3

4
s
,

T
•


SAMPLE
DATE
T/SI •
l/St f
S/U /
j
ft/tt y
r/M /
^
^
4/«S
I/W

IO/S9
MILESTONE
EVENT
INITIAL IITE
ASSEMIIENT
CMIt«ENCT
• ECI*CULATION
SYSTEM

CUTOrP WALL
INSTALLATION

PERMANENT
RECIKCULATION
srsTE*
                                                                                           CONCENTRATIONS OF TETRAHYDROFURAN (THF)INPARTS
                                                                                           PER MILLION (•«/!). ND INDICATES NO THF DETECTED.

-------
 85
        43-
      W 35
 I
U1

  5


  0-


 -s-






 -IS'





-29-





-35..
                                             FIG. 4-24b VARIATIONS IN CONTAMINANT DISTRIBUTION

                                             CUTOFF  *
                                               WALL —     	                      M-23-
                                                                                                                   A'
                  M-3-
                                                                                               20'     40'

                                                                                              HORIZONTAL SCALE
                                                                                                                 80'
                                                                                                              A-10-

-------
    Reed Brook,  on the northwest boundary of the site.  This
    movement  is  reflected  in increasing concentrations of
    contaminants in water samples collected both from the
    brook and in the vicinity of the  future cutoff wall.

    Concentrations in Lyle Reed Brook peaked at  12 parts per
    million  during the  July  1981  sampling  round.
    Concentrations  of  THF  at M-3  also showed peak
    concentrations during this time frame ranging from 16 to
    170 parts  per million  at the various sample levels
    (concentrations at M-3 increased  with depth).

B.   Contaminant Distribution in Response to  Emergency
    Recirculation System

    Concentrations at  the downgradient portion of the site
    began to  decrease after  the start-up of the Emergency
    Recirculation System.  Levels decreased during operation
    of  the system (February, 1982 through November, 1982)  in
    the stream  sampling point,  NHDB-04,  and  in  the
    downgradient wells,  M-3  and A-10.   This response  in
    concentrations to  recirculation system operation shows
    the system retarded the advance of the contaminant plume
    by  recirculating water back to the central portion of
    the site.

C.   Contaminant Distribution in Response to Installation of
    Cutoff Wall

    The response of  contaminant distribution  to  the
    installation of the  cutoff wall were  twofold.  Just
    prior  to installation  of the  cutoff wall  at  the
    downgradient portion  of  the  site,  the  emergency
    recirculation system  was shut down in order to allow
    grading,  pumping well extension,  and impermeable  cap
    placement.   As a result, the advancement of the plume,
    which  had  been halted  and reversed  during  the
    functioning of the system, once  again began.   This plume
    movement  was reflected in contaminant levels  at  the
    downgradient monitoring wells.

    The cutoff  wall  was completed  in  November,  1982.
    Monitoring points located downgradient of the wall
    continued to show  an increase in concentration.  This
    increase  was in response to movement of contaminants
    beyond the  cutoff wall location  while the emergency
    recirculation system  was shut down.   This pulse  of
    contaminants continued to be observed over  time as it
    moved downgradient.   In general,  at  the time  of  the
                       4-60

-------
        completion of  the  cutoff  wall, the  levels of
        contaminants were  highest within the bedrock.

        With  the  completion of the wall, contaminant levels in
        the area  of  the stream again decreased.  In addition,
        concentrations  inside the cutoff wall remained higher
        than levels outside  the cutoff wall.  Contaminant  levels
        in  the  vicinity of the cutoff wall were highest in the
        bedrock.  These  levels  indicate flow in the vicinity of
        the cutoff  wall  was  occurring  within the fractured
        bedrock and not  through the wall itself.

     D.  Contaminant Distribution in Response to the  Permanent
        Recirculation System

        Currently,  contaminant  levels within the cutoff  wall
        have decreased as  compared to levels measured subsequent
        to  cutoff wall  completion.  This decrease is primarily
        due to  the  functioning of the permanent recirculation
        system.  Pumping  of groundwater within the cutoff wall
        has had  the effect of  mixing  or  homogenizing the
        groundwater. As  a  result, levels within the cutoff wall
        have  dropped as highly contaminated  zones were mixed
        with  zones exhibiting lower concentrations.   However,
        even  with the homogenizing effect, levels within  the
        cutoff  wall are  higher  than those outside of the wall.


          4.3.3.4  Contaminant Degradation of the Cutoff Wall


    -The cutoff wall installed at Gilson Road  has performed as  a
multi-functional  containment  structure.  Initially,  the  wall
served as a temporary measure to impede the off-site migration of
contaminants.  With  the  start  up of the permanent hydrodynamic
isolation system,  the cutoff wall now functions as a clean water
exclusion  barrier  to inhibit the flux of clean water back  onto
the site  in response to groundwater pumping.  While performing
the initial containment function, the  wall was exposed to
contaminants.   As a  result,  the  potential for  chemical
degradation  of the wall was investigated.

     Two major  factors control the time required for cutoff wall
degradation:

     0   The  number  of pore volume displacements required to
        affect a chemically mediated change in  the wall hydraulic
        conductivity;

     0   The  rate at which leachate flows through the wall.


                            4-61

-------
     Long-term hydraulic conductivity testing of the Gilson Road
backfill  with worst  case  leachate from the site indicated  that
displacement of two  to three pore volumes are required to effect
changes in  the cutoff wall hydraulic conductivity  (Schulze, 1984).
The  testing, which  simulated  in-situ conditions, indicated  a
maximum increase to twice  the initial hydraulic conductivity  (1.2
x 10~8  to 2.5 x  10~8  cm/sec).   These results agree with
literature  documentation  on  chemical degradation of clay based
barriers.

     The  flow of contaminated groundwater through the cutoff wall
intact backfill  is  dependent  upon the hydraulic gradient  (j.)
across the wall and the intact hydraulic conductivity of the wall
(fc).   The hydraulic  gradient  is  determined by the ratio of  the
total head difference across the wall as compared to the width of
the  wall  (L).  The intact  hydraulic conductivity of the wall  was
determined by  hydraulic conductivity testing of cutoff  wall
samples (Section 2).

     Flow through a porous medium is governed by Darcy's Law (Q  =
kiA)  where  Q  is  the volume  of  water  flowing  through  a
cross-sectional area of  the medium  (A).  The average velocity of
the flow through the medium  is  described by the equation  Vs  =
ki/n  ,  where n is  the  porosity of  the material.   The  time
required to displace one pore  volume can be determined by  the
equation t = W/Vs,  where W  is  the width of the medium  through
which flow  is occurring.

     In order to determine the  time to displace one pore volume
of water  through the wall, certain conservative, or worst-case,
assumptions were made in  the selection of parameter values.

     The greater the hydraulic  gradient (^) across the wall, the
faster the wall will degrade.   The maximum head difference
observed on the  site was  three feet.   This  condition  only
occurred during one period  of  particularly high precipitation
without  hydrodynamic controls.   A minimum width  of the wall would
be equal to the  width  of  the bucket used to  excavate  the
cutoff wall trench.  A 3  foot bucket was used.   This results in  a
maximum hydraulic gradient of j_ = 1.

     The greater  the hydraulic conductivity of the  wall,  the
faster degradation should  occur.   The hydraulic conductivity of
the wall is inversely proportional  to the level  of stress on the
wall.  The  stress on the wall  increases with depth to  a  maximum
of 50 pounds per square  inch  (psi) at the bottom of the wall  (105
feet).   In order to simulate  worst case conditions,  hydraulic
conductivity testing of the  cutoff wall was conducted  using
stress conditions corresponding to the top of the  cutoff wall, or


                            4-62

-------
3 to  5  psi.  Although design phase  laboratory  testing and
construction QC testing  in  the  field yielded an average cutoff
wall hydraulic conductivity of  5 x 10~8  cm/s, a more conservative
value of 1 x 10"7 cm/s  was used for determining pore  volume
displacement rates as based  on work completed under phase one
(Section 2) of this contract.

     The porosity (n)  of  a  material  is that  portion of the
material not occupied by  solid matter relative to  its total
volume.  If all other factors  remain constant, a lower porosity
will result in a higher flow velocity, which will cause a faster
degradation of the cutoff wall.  Based on  QC  data, a conservative
value of n = 0.4 was chosen.

     A computation of the time  to displace  a single pore volume
is determined using the equations stated previously:

              t = W;  where
                  Vs

              Vs = ki
                   n

     Using the conservative, or worst case,  values stated above,
the form of  the equations becomes:

              Vs = 1 x 10-7 cm/s (i) - 2.5 x  10~7 cm/s.
                           0.4

              t = 91.44  cm	 = 3.7 x  108 seconds;
                  2.5 x  10-/  cm/s

              t = 11.6 years

     The time to displace one  volume of  pore  water using  worst
case parameters is calculated  to be approximately eleven years.
However, under  the average conditions which  have actually
occurred on  the site,  the time required to displace a single pore
volume is approximately  fifty years.  As the testing of the
degradation of the  cutoff  wall material  has  shown,  chemical
degradation of  the  material was complete only after two pore
volume displacements,  thereby  doubling the likely time estimates
quoted above.

     It is realized  that chemical  degradation of the wall  would
begin immediately  at  the surface in contact with the  leachate.
As a  result, the  hydraulic conductivity of the backfill at the
surface, over a  thickness  dx,  would increase.  Assuming as  a
worst case that  the increase  was infinite, then the gradient
across the wall would increase commensurate with the decrease  in
                             4-63

-------
effective wall width.  Integration  of  the appropriate equations
demonstrates that the rate of chemical degradation would  increase
by a factor of two as compared to that computed assuming constant
gradient.  The assumption of  infinite  increase in hydraulic
conductivity due to chemical  degradation, however,  is
conservative  in that  actual  testing indicates  only a  two fold
increase.  As such,  the increase in  rate of degradation due to a
changing  gradient would be less than two.

     Given the  data and computations performed  above,  it is
unlikely that the Gilson Road cutoff  wall  has  undergone
significant chemical degradation  in  the  2.5  years since its
construction began.   The calculation of potential cutoff wall
degradation assumed  a hydraulic  gradient  of  1.   However, the
operation of the hydrodynamic  isolation system,  in place  since
April 1985, has acted  to balance  the hydraulic heads inside and
outside  the wall,  thereby reducing  the hydraulic  gradient  to
essentially zero.   In  addition, the  operation of the groundwater
treatment plant under construction at  the  site includes a
treatment purge stream located  outside the  cutoff wall.   As a
result, pumping of groundwater within  the wall will cause  a  water
deficit within the  cutoff wall and result in flux into the  site.
This flux into the site will cause  relatively clean groundwater
to  flow  through  the wall,  thereby reversing  the degradation
caused by the flow  of  leachate through  the wall if any has
actually  occurred.


4.4  Conclusions


     The  hydraulic stress testing  and contaminant migration
analyses both indicate  that the cutoff wall  appears  to be
functioning as an  essentially  intact barrier.   However,  it is
apparent  that the fractured bedrock  which forms the bottom of the
containment is highly pervious  and would result in  a  major
leakage  path without the hydrodynamic  isolation  systems
incorporated in the  overall  containment design.   The following
more specific conclusions can be drawn from  the  Phase Three work
as summarized herein.

     0   The three-dimensional  numerical  modeling of  the site
       predicted that  the bedrock located  at  the  downgradient
       portion  of  the  containment was more  pervious  than
       initially indicated via packer testing data.   The  bedrock
       pumping  test verified this prediction,  yielding bedrock
       hydraulic  conductivities in  the range of 10~1 cm/sec.
       This value  is large as compared to that specified for the
       cutoff wall (1 x  10~7 cm/sec).  The pumping test  also
       demonstrated that  the glacial till existing just above


                            4-64

-------
the  bedrock was  also  quite  pervious  and probably
discontinuous.   This data supports conclusions  reached
during the RI/FS.

The cutoff wall and bottom aquitard/aquifer units form a
hydraulically coupled system.  Analysis of cutoff wall
bulk  hydraulic conductivity  therefore  must  rely  on
numerical modeling to correlate the stress  test data  and
separate  the behavior of the  wall from that of  the
bedrock.  The accuracy  of  the bulk hydraulic conductivity
computed  via the  sensitivity  analysis  is  therefore
inherently limited  to  the calibration  accuracy of the
numerical model.  As such, post-construction verification
efforts are based on somewhat circumstantial data in  the
form of piezometric head distributions  and thus could be
opened to varying interpretations.

Analyses of cutoff wall  bulk hydraulic  conductivity must
be based on hydraulic stress testing of  the containment.
The value obtained will  therefore  inevitably be in the
form of an  upper bound solution.  The  proximity of  the
upper bound value obtained via analysis  to  that specified
for the cutoff wall  will be limited  by  not only the
success of the cutoff  wall construction effort, but also
by the hydraulic conductivity of the containment  bottom.
The  very  cases  which  are likely  to require
post-construction  verification studies  (containment
leakage) are therefore those for which hydraulic stress
analysis  may  be  the least conclusive.   In these
instances,  specifications based solely on performance
criteria may prove difficult to enforce.

The bulk hydraulic conductivity of the Gilson  Road cutoff
wall was found to be less than 10~5 cm/sec.   The degree
to which the actual value falls below  this  upper  bound
cannot be  determined  due to the high hydraulic
conductivity of the containment bottom.  However, a  worst
case value of 10~5 cm/sec  yields a cutoff wall  efficiency
of greater than 93%.   The actual value  of  wall hydraulic
conductivity is probably approximately  1  x 10"^ cm/sec  as
based on quality control  testing (Section 2).  This  value
yields a cutoff wall efficiency in excess of 99%.

The  overall  passive containment efficiency,  including
bedrock leakage,  is also  important.   The  overall
efficiency of the  passive containment  elements (cutoff
wall,  cap  and  fractured bedrock)  was  found to  be
approximately 55% (under worst case  precipitation induced
stress  conditions)  with the major loss flowing out
through the bedrock aquifer.  It was recognized during
                     4-65

-------
   the RI/FS  phases  of the  project  that the  glacial
   till/bedrock aquitard/aquifer containment bottom would
   leak.  However, additional passive barriers such as
   grouting  to stop such  leakage were not found  to be
   economically feasible.  Hydrodynamic isolation systems
   were therefore  incorporated  in the overall containment
   design.   Hydrodynamic  isolation not only proved more cost
   efficient than additional physical barriers,  such as
   grouting  the  bedrock,  but  also provided  for
   recirculation/treatment capabilities.  Following this
   approach, a purge stream pumpage  was instituted in 1986
   when the groundwater  treatment system  went on line.  At
   this  time, over 72,000 GPD are being discharged outside
   the cutoff wall  in order to  implement the hydrodynamic
   system elements.

0  The contaminant migration analysis supported the overall
   conclusions derived  form the hydraulic stress testing.
   The data  indicated that contaminant flux,  in the absence
   of  hydrodynamic isolation,  would be through the bedrock
   below the wall.  However,  the contaminant  data was
   inconclusive when analyzed independently.  This  stems
   from the  lack  of  sufficient data due to  cost and
   conflicting objectives  governing sample selection as well
   as  delays in the start-up of the  hydrodynamic isolation
   system due to construction contract  difficulties.

0  The data  obtained and the computations executed  during
   this  study in  combination   with  long-term
   leachate/backfill compatibility testing  undertaken as
   part  of  the cutoff wall design process indicate that
   significant chemical degradation  of  the cutoff wall is
   unlikely over the 2.5 years since its construction.  The
   two pore  volume exchanges required  for  chemical
   degradation are computed to take  over  20 years  under
   worst  case conditions.  Leachate/backf ill compatibility
   testing indicates that  the  worst case  leachate found at
   the Gilson  Road site  only increases the hydraulic
   conductivity of  the intact backfill  by  a factor  of two.
                       4-66

-------
                           SECTION 5

                          CONCLUSIONS
     The following general  conclusions can be drawn from the work
executed  under this  contract.   More  specific and detailed
conclusions with  respect  to the individual work phases  can be
found at the end of their respective sections.

     0  Work  on the Gilson Road project demonstrated  that a high
        degree of emphasis  on field quality control  procedures
        was  required to achieve and document satisfactory cutoff
        wall  installation.   To be meaningful, the groundwork for
        the  field QC testing should be initiated during backfill
        mix  design and leachate compatibility testing.   The
        results of this design phase work should be reflected in
        the  project construction specifications  as minimum
        design standards.   QC testing should then be  executed in
        the field during construction with emphasis on immediate
        data  availability such that it can be used to guide the
        construction on a day to day basis.

     0  The  API fixed-ring  hydraulic conductivity and methylene
        blue  titration procedures, developed for quality control
        of  the Gilson Road cutoff wall, proved to be  highly
        applicable and practical testing methods.  The hydraulic
        conductivity and  percent bentonite  content data  that
        these tests provided were sufficiently precise  and
        accurate for evaluation of conformance  to  the  project
        specifications.    As  such,  these  tests   should  be
        routinely incorporated into the quality control program
        for  soil/bentonite cutoff  walls  used  to contain
        hazardous wastes.

     0  Modified piezocone  instruments  appear to be capable of
        detecting  windows  in soil/bentonite  backfilled  cutoff
        walls.   However,  the present state of the art requires
        significant judgment  with respect to data interpretation.
        This  judgment  must  be based on a thorough understanding
        of the equipment used and general soil  mechanics theory.
        Prior to routine use as a post-construction verification
        tool,  a  significant amount of additional work must be
        completed to build up a data base upon which empirical
        correlations can be constructed.
                             5-1

-------
For piezocone sounding or direct  sampling to be viable
as post-construction' verification tools, construction
quality  control of the cutoff wall must include  wall
alignment and verticality provisions.  The accuracy  of
as-built wall alignment documentation and  actual  wall
verticality must be increased significantly  above  that
required for hydraulic  performance only.

Post-construction  verification  of  cutoff wall  bulk
hydraulic conductivity  is an inherently  costly endeavor.
Under  most  actual field  conditions  of  interest/
sensitivity analyses, based on calibrated  3-dimensional
numerical models, will be required to evaluate hydraulic
stress  testing  data.  The value of bulk  hydraulic
conductivity obtained  for the cutoff  wall  will therefore
typically  be derived from somewhat circumstantial
evidence  and will be inconclusive  in cases where the
bottom  aquiclude is pervious as compared to the value
specified  for the  cutoff wall.   Therefore, use  of
quality control testing during construction is typically
preferable to reliance on post-construction verification
for enforcement of project specifications.

Based on  the work performed under  this  contract, the
Gilson  Road cutoff wall appears  to  behave as  an
essentially intact barrier to flow.  As such, it  is
performing as intended  with a lower bound  efficiency  of
greater than 93 percent (an actual efficiency of over  99
percent  is probable as based on hydraulic conductivity
values obtained from quality control  testing).  However,
the fractured bedrock, which  forms  the  bottom of the
containment, appears  to be more pervious  than initially
anticipated.    As  such, pumping  rates for  the
hydrodynamic  iso1 ation/recircu1ation  system,
incorporated as part of the overall  containment system
to account for the  fractured  rock,  will  likely have  to
be increased relative to initially predicted values.

Work on the Gilson  Road project  has demonstrated that
cutoff  walls can  be  successfully constructed for
hazardous waste  containment.   These physical  barriers
can prove highly cost efficient as an  integral component
of the overall permanent containment  system.   This  is
particularly true for sites where the objective  is  to
eliminate, rather than just reduce, off-site  contaminant
migration.   In these cases,  the cutoff wall should  be
viewed  as  a clean  water exclusion  barrier  used  to
increase hydrodynamic  isolation/recircu1 ati o n
effectiveness and reduce treatment costs.
                    5-2

-------
                           REFERENCES
Alther, George.   Design,  Testing & Construction of Bentonite
      Liners.  International Minerals & Chemical Corporation,
      (undated).

API.  American Petroleum  Institute.  API Recommended Practice:
      Standard Procedure  for Testing Drilling Fluids.  API RP13B.
      American Petroleum  Institute, Dallas, Texas, 1982.

API.  American Petroleum  Institute.  API Specification for Oil
      Well Drilling Fluid Materials.   API Spec.  13A  American
      Petroleum Institute,  Dallas, Texas, 1981.

Ayres, J. E., and M.  J. Barvenik, and D. C. Lager.  The First EPA
      Superfund  Cutoff  Wall;  Design  and  Specifications.
      Proceedings of the 3rd  National Symposium and Exposition  on
      Aquifer Restoration and  Groundwater Monitoring, sponsored
      by NWWA, Columbus,  OH, May 1983.

Baligh, M. M., and J. N.  Levadoux.  Pore Pressure Dissipation
      After Cone Penetration.  Publication No.  R80-11, Order No.
      662, Department of Civil Engineering, MIT,  Cambridge, MA,
      April 1980.

Bafoid/HL Industries. Field Testing of Drilling Muds, NL
      Baroid/NL Industries, Inc., Houston, Texas (undated).

Barvenik, M.  J.   Dedicated  Gas-Drive Groundwater Sampling
      Instruments,  Lecture and Notes  presented as  part of  the
      Design,  Installation,  and Sampling  of  Groundwater
      Monitoring Wells  Short Course  sponsored by  the  National
      Water Well  Association,  multiple courses in 1984.

Barvenik, M.  J.   Methods  for Passive Physical Containment of
      Groundwater Contamination and Field Applications of Active
      and Passive  Physical  Containment  of  Contaminated
      Groundwater.  Lectures and  notes presented  as part of the
      Short  Course  entitled:   Corrective Action for Containing
      and Controlling Groundwater Contamination, sponsored by the
      National Water Well Association;  multiple courses in 1985
      and 1986.

Barvenik, M.  J.  and  R. M. Cadwgan.  Multi-level Gas-Drive
      Sampling of Deep Fractured  Rock  Aquifers  in Virginia,
      Groundwater Monitoring Review, Vol. 3,  No. 4,  Fall  1983.

Brown, D. M., and L.  W. Gelhar.  The Hydrology of Fractured
      Rocks:  A  Literature  Review.  MIT  Parsons Laboratory
      Technical  Report #304, 1986.
                             6-1

-------
Cedergren, H.  R.   Seepage,  Drainage,  and  Flow Nets.  John Wiley &
      Sons, Inc.,  NY,  NY,  pp.  6,  1967.

Douglas, B. J. and R.  S.  Olsen.   Soil Classification Using
      Electric Cone Penetrometer.   Sym.  on  Cone Penetration
      Testing and Experience.   Geot.  Eng.  Div., ASCE, St. Louis,
      Missouri,  Oct. 1981.

Hantush, M. S.  Flow to Wells  in  Aquifers Separated by a
      Semi-pervious Layer,  Journal  of Geophysical Research,  72
      (6), 1709-1720,  1967.

JRB.  Slurry Trench Construction  for  Pollution Migration Control.
      U.S. EPA Document EPA-540/2-84-001, Cincinnati, OH, 1984.

Jones, G. A.,  and D. Van Zyle,  and E. Rust.  Mine Tailings
      Characterization by Piezometer Cone.   Sym.  on Cone
      Penetration Testing  and Experience.   Geot. Eng. Div., ASCE,
      Oct. 1981.

Koteff,  C. and R.  P. Volchman.  Surficial Geologic Map of the
      Pepperell  Quadrangle.  USGS, GP-1118,  1973.

Lambe, T. W.,  and R. V. Whitman.   Soil Mechanics.  John Wiley &
      Sons, Inc.,  NY,  NY,  1969.

Levadous, J. N.  and M.  M.  Baligh.   Pore Pressures During Cone
      Penetration in Clays,  Research  Report.  Department  of Civil
      Engineering, MIT, Cambridge, MA,  1980  (in  preparation).

Middlebrooks,  T.  A.  Earth  Dam Practice in the United States.
      Trans. ASCE (centennial  volume),  pp. 697,  1953.

Poulos,  H. G.  and E. H. Davis.  Pile  Foundation  Analysis and
      Design.   John Wiley &  Sons,  Inc., NY,  NY,  1980.

Powers,  M. A., and P.  P.  Virgadamo, and W. E. Kelly.  Groundwater
      Control  at  Hazardous Waste  Sites.   ASCE National Convention
      on Hazardous Waste,  St.  Louis,  Missouri, 1981.

Sanglerat, G.   The Penetrometer and Soil  Exploration.  Elsevier
      Publishing  Company, Amsterdam-London-New York, 1972.

Schmertmann, J.  H.  Guidelines for CPT Performance and Design.
      U.S. Dept.  of Transportation, FHWA-T5-78-209, Feb. 1977.
                              6-2

-------
Schulze, D., and M.  J.  Barvenik, and J. E. Ayres.   Design of the
      Soil/Bentonite Backfill Mix  for  the First EPA Superfund
      Cutoff Wall.   Presented at the Fourth National  Symposium on
      Aquifer Restoration  and  Groundwater Monitoring,  sponsored
      by NWWA,  Columbus, OH, 1984.

Torak, L. J.  Modifications and Corrections to the
      Finite-Difference Model for Simulation of Three-Dimensional
      Groundwater  Flow.  USGS  Water Resources Investigation,
      82-4025,  1982.

Trescott, P. C.  Documentation of Finite-Difference Model for
      Simulation of  Three-Dimensional  Groundwater Flow.   USGS
      Open File Report  75-438, 1975.

U.S. Army.  Laboratory  Soils Testing.  Department  of the Army,
      Manual EM 1110-2-1906, November 1970.

Winterkorn, H.  F.,  and  H.  Y. Fang.  Foundation Engineering
      Handbook.  Van  Nostrand Reinhold Company, NY, NY, 1975.

Wissa, A. E. Z.,  and  R. T. Martin, and J. E. Garlanger.  The
      Piezo Probe,  Proceedings.  ASCE  Specialty Conference on
      In-Situ  Measurement of Soil  Properties, Raleigh, NC, Vol.
      I, pp. 536-545,  1975.
                             6-3

-------
                          APPENDIX A

                   API FIXED-RING PROCEDURE
Purpose

The purpose of  this procedure is to determine  the hydraulic
conductivity of  a sample of backfill  using  the  standard API
filter press apparatus.

Materials

1.   Standard filter press and mud  cell assembly (as  manufactured
     by Baroid, refer to Figure 2-1  of text)
2.   Pressure source and feed lines
3.   Pressure gage
4.   Pressure regulator
5.   Graduated cylinder  (10  millileter capacity marked at 0.1 ml
     intervals)
6.   Dry bentonite
7.   Saturated Ottawa sand
8.   Paste  trimmer
9.   Spatula
10.  Analytical scale (accuracy:   0.01 grams)
11.'  Drying oven
12.  Approximately 600 grams of backfill sample

Test Procedure

1.   With a spatula, smear  a paste consisting of bentonite and
     water  on the inside of the API cell.   The paste should be
     dry enough  to adhere  to  the sides  of  the  cell,  but wet
     enough to saturate the dry bentonite.  The purpose of the
     paste is to create  a  seal between the edge of  the  backfill
     sample and  the inner  surface  of the cell.  Be  careful to
     fully cover  the wall  over  the  2-inch  high  area  to be
     occupied by  the backfill.

2.   Place the cell in  the  paste trimmer.  Adjust  the  trimming
     edge so a bentonite seal of approximately  1/32-inch  will be
     obtained.    Evenly  rotate the  cell in the trimmer to remove
     the excess bentonite paste from the cell walls.   Remove the
     cell  from  the trimmer  and check  if a 2-inch high zone
     starting 1/4-inch up from the bottom of the cell  is  entirely
     covered by  a smooth,  1/32-inch bentonite seal.  The  paste
     will line the inside of the cell over  the section  occupied
     by the backfill sample.
                             7-1

-------
3.    With a spatula and paper  towel, remove any excess bentonite
     on the cell wall,  outside'of the area to be  in  contact with
     the backfill.

4.    Assemble the base cap with  filtrate tube, rubber gaskets,
     steel mesh screen, and cell.

5.    Carefully place saturated  Ottawa sand in the cell to a depth
     of 1/4-inch.   The sand should just be  in  contact with the
     bottom edge of the bentonite seal.  This  sand  will act as a
     lower  filter.   Sand  is most evenly spread  by  blocking the
     drainage  channel with a finger, submerging  the  sand (in
     water),  and  tapping  the outside of the cell to  smooth the
     surface.  Outlet is  then  opened  to let excess water drain
     off.  If backfill mix is such that migration  of  fines and
     possible subsequent  "blow-through"  is a  concern, carefully
     place a  2-inch diameter filter paper on top of sand.   (Fines
     on the filter paper  are  also  a good indicator of migration
     after  test is completed).

6.    Prepare the backfill sample  for testing.   Pass  the wet
     backfill  sample  through the  1/2-inch  sieve.   On  an
     analytical scale, weigh the test sample which should consist
     only of material passing  the  1/2-inch sieve.  Using the
     spatula,  place  the  sample material  into the  cell.  The
     sample  should be placed  so  as  to leave no air voids and
     without scraping the bentonite paste seal. After 2  inches
     of material has been  placed, smooth the sample surface using
     the spatula.

7.    Weigh the portion of backfill  test material  not placed in
     the cell and record the number of grams of  backfill  placed
     in the  cell.   With  the remaining material, determine the
     moisture content of the sample at preparation.

8.    Place the cell with  the prepared soil sample into the  filter
     press  frame.   Slowly, fill the cell above  the soil  sample
     with water.  Do not  disturb the fine materials  at the  sample
     surface  while adding  the water.  This can  be facilitated by
     placing a piece  of filter paper on top of the  backfill mix,
     then slowly adding water with a  lab squeeze bottle on  top of
     the filter  paper.   This will reduce  the  chance of  sample
     degradation by scouring.   Be  sure to remove  filter  paper
     when cell is  full (it should  float to the top).  The  water
     in the  cell should remain clear.

9.    Place the top cap and its rubber gasket on the cell.   Clamp
     the unit in place with the T-screw.

10.  Set an  empty graduated cylinder  under the filtrate tube.


                             7-2

-------
11.   Apply a "seating" pressure to the  sample  corresponding to
     the  lowest setting of  the regulator (typically 1-1.5 psi).

12.   Increase the pressure  to  2 psi.   Let  sit for thirty
     minutes, then increase to 3 psi.

13.   Read the water  level in  the  graduated cylinder every two
     hours for six  to eight hours.   Record the  time,  the water
     level,  the time increment  since the  last reading (in
     minutes),  and the change  in  water level  since  the last
     reading (in cubic centimeters).   Calculate the permeability
     for  each time  increment (using change in water volume and
     elapsed time since last reading).  Also, calculate flow and
     volume of water in head space to determine when sample must
     be refilled (i.e.,  particularly important for overnight
     testing).

14.   If the permeability  has  stabilized after  the initial two
     hours water level readings, take readings  every  eight  to
     fourteen hours.  If  the  permeability is fluctuating,
     continue to take water level readings frequently (every two
     hours) until stabilization.

15.   Run  the test for a minimum of twenty-four  hours.

16.   If test data at a higher pressure desired, increase the cell
     pressure and repeat steps 13-15.

17.   Keep a  record of the  total volume  of  water  permeating the
     soil  sample.  Refill  the  cell  above the  soil sample with
     additional water when  needed.
                            7-3

-------
                          APPENDIX B

                 METHYLENE BLUE TEST PROCEDURE
I.    PURPOSE OF TEST

     The methylene blue test  is  a  technique used  to measure the
cation exchange  capacity of  a soi1/bentonite mixture.  The
purpose of the  test  is  to me-asure bentonite content  in soil/
bentonite backfill  utilizing  the proportionality which  exists
between bentonite content  and cation exchange capacity.

II.   GENERAL PROCEDURE

     A sample of soil and bentonite  weighing 10 grams is mixed
with a solution  of  the dispersant tetrasodium pyrophosphate
(TSPP).   The TSPP  disperses the bentonite  and replaces
exchangeable cations of bentonite with sodium which facilitates
the exchange  process. A solution of methylene blue in distilled
water is added to the slurry  of soil/bentonite and dispersant  in
measured volumes until the  exchange capacity of  the sample  is
exceeded.  At each  increment  in the titration, a drop of the
slurry/methylene blue mixture is placed on a piece of  filter
paper.   Prior  to reaching  the exchange capacity of  the bentonite
(endpoint), the  drop  appears  as a uniformly dark blue circle.
The end point  is indicated by the  appearance of a  light blue halo
around the dark blue dot.  At  this point, the exchange process  is
complete and free methylene blue cations are in solution  (causing
the halo).

III.  PREPARATION OF METHYLENE BLUE SOLUTION

     A.   Materials and Apparati

         1.   Methylene  blue  crystals:  U.S.P. grade, formula
              weight  of  373.9, zinc free (available  from  EM
              Science)

         2.   Distilled water

         3.   Analytical  balance  (accuracy:  0.01 grams)

         4.   1000 - milliliter volumetric flask

         5.   Funnel

         6.   Magnetic stirrer and stirring bar
                             8-1

-------
         7.   Dark  brown  glass bottle with air-tight  screw-on
              cap

     B.   Procedure

         1.   Weigh out  3.74 grams of  methylene  blue  (MB)
              crystals,

         2.   Transfer the  crystals to  a 1000  - milliliter
              volumetric flask  using a funnel,

         3.   Add  approximately 500 milliliters  of distilled
              water to the flask,

         4.   Stir  the  MB solution for  one-half hour using the
              magnetic stirrer  and stirring bar.

         5.   Remove the  stirring bar  from the  solution  and
              carefully  fill  the  flask to the 1000  - milliliter
              calibration  mark  with distilled water,

         6.   Stir the MB  solution for another half  hour,

         7.   Transfer the  solution to a dark  brown glass
              storage container,

         8.   Repeat steps  1-7 for additional methylene  blue
              solution (if desired),

         9.   Continuously stir  the MB solution  for twelve hours
              using the  magnetic  stirrer,

         10.  Label  the storage  container, including the date of
              preparation;  store  the  MB  solution  at room
              temperature and  out of direct light; the storage
              life is approximately three months.

IV.   PREPARATION OF DISPERSANT SOLUTION OF TETRASODIUM
     PYROPHOSPHATE

     A.   Materials

         1.   Tetrasodium pyrophosphate  (TSPP) crystals:  spe-
              cifically  Na4 P2  07  . 10H20

         2.   Distilled  water

         3.   One liter  flask

         4.   Analytical balance  (accuracy:  0.01 grams)


                             8-2

-------
     B.   Procedure

          1.    Weigh  out 33.30 grams of the TSPP  crystals,

          2.    Transfer the  crystals to a flask containing one
               liter  of distilled water,

          3.    Shake flask for  five to  ten minutes, until
               crystals are  completely dissolved  (determined
               visually).

V.   PREPARATION OF SOIL SAMPLES

     A.   Materials

          1.    Soil sample and tare

          2.    Drying oven

          3.    Mortar and rubber pestle

          4.    No. 10 sieve

          5.    Analytical flask

          6.    250 millimeter erlenmeyer flask

          7.    2 percent  solution  of TSPP (prepared per
               Section IV)

          8.    Magnetic stirrer

          9.    Glass  stirring rod

          10.   Hotplate

     B.   Procedure

          1.    Weigh  a representative backfill  sample,

          2.    Oven dry the sample,

          3.    Weigh  the dry sample,

          4.    Using a  mortar and  rubber  pestle,  break  up
               hardened clumps of dry soil,

          5.    Pass the sample through a No.  10 sieve,
                             8-3

-------
          6.    Weigh the portion  of the dry sample  passing the
               No.  10 sieve.

          7.    Weight out 10.00 grams  of the sample  which passes
               the  No. 10 sieve in a 250-ml erlenmeyer flask,

          8.    Add  one  hundred milliliters of  2  percent hydrated
               tetrasodium pyrophosphate  (TSPP)  solution  to the
               10.00 gram sample,

          9.    Mix  the  resultant  slurry with a magnetic stirrer.
               Use  a glass stirring  rod  to force  any  clay
               sticking to the flask walls into  the  solution,

          10.   On a hotplate, heat  the sample to  a  slow rolling
               boil and maintain  for  five minutes.   Swirl the
               flask and again use a glass stirring rod to remove
               any  clay clinging to the flask walls.

          11.   Bring the slurry to room temperature.

VI.  TITRATION WITH METHYLENE BLUE

     A.    Materials

          1.    Soil sample dispersed with TSPP solution

          2.    Magnetic stirrer and stirring bar

          3.    Methylene blue solution

          4.    Whatman's filter paper (hardened  No.  50)

          5.    1 -  50-ml beaker

          6.    1 -  50-ml glass syringe with needle

          7.    1 -  3-ml glass syringe with needle

     B.    Procedure

          1.    Stir the MB solution in its storage container for
               thirty minutes before  titration  (this  should be
               done once at the start of each day  of testing),

          2.    Transfer a portion of  the MB solution  to  a wide
               mouthed glass jar,

          3.    Mix  the  slurry of  soil  and dispersant  for thirty
               seconds to one minute,
                             8-4

-------
4.    Place a piece of filter  paper  atop of a beaker,
     such that the paper's  edge is  overhanging  the
     beaker  (label the paper by test number,  date).

5.    Titrate  the MB  solution by syringe.   Using  the
     50-ml glass  syringe,  transfer enough MB solution
     to the slurry so the color of the mix turns from a
     greenish-blue to a dark blue,

6.    Mix the slurry with  the  magnetic  stirrer for two
     minutes,

7.    Dip a glass stirring rod  into the slurry  and place
     a drop  of the dark blue mixture  onto the edge of
     the filter paper.   Watch  for  a light blue halo
     around the circumference of the resulting dark
     blue dot.   If a halo  does not appear, add an
     additional 1 milliliter  of MB  solution to  the
     sample using the 3-ml syringe.  Mix for thirty
     seconds and repeat Step 7,

8.    When a blue-green halo appears,  do not add more MB
     solution.  Stir the  sample for another two to
     three  minutes.  Check  for the  halo again by
     placing another drop  on the  filter  paper.  If  the
     halo does  not appear, repeat  Step 7, but  after
     each 1 milliliter addition of MB solution,  mix  the
     slurry for two minutes.  When the halo appears on
     both the  initial drop and a check,  the end  point
     is reached.  Record  the test result as  milliliters
     of MB solution required to reach the end point.

9.    The test  result  (ml MB) is then  entered on  t-he
     bentonite calibration  cure to  yield a percent
     bentonite.   This is  the  percent bentonite in the
     material  passing the No.  10 sieve.   The  percent
     bentonite in the total backfill sample would then
     be

       (percent bentonite  in minus No.  10 material)
       (percent of total sample passing No.  10  sieve).
                   8-5

-------
                          APPENDIX C

           GEOPHYSICAL METHODS FOR WINDOW DETECTION


     A number  of geophysical methods currently exist which
potentially could  be used to detect windows in soil/bentonite
backfilled cutoff  walls.   A  number of these methods were briefly
investigated on a theoretical  basis.


     For a remote sensing  investigatory method to be feasible for
window detection, its signal must respond differently to a window
as compared to the intact  backfill.  Furthermore, the signal must
first reach the window and  then, in its altered state, propagate
to  the instrument  for detection.  This  requires  that the
backfill,  or formation surrounding the backfill, be relatively
transparent to the investigatory signal.   In addition, the window
of interest must exhibit  parameters that  are significantly
different  from the backfill with respect to signal propagation.


C.I  Investigation Methodology


     Two general investigative  approaches exist for window
detection.  The first, defined as  "PROBE" methods,  continuously
detect physical parameters of  the backfill in the immediate
vicinity of a probe  as  it is inserted  through the backfill.
These methods have resolution  similar to direct sampling of the
wall, but  are much faster and  less expensive than actual sampling.
These methods, however, will not  detect windows which fall in
between probe hole location.  Hence, the frequency of windows
would be based on statistical  analyses.

     The second  type or  "SCAN"  methods, pick up changes in
physical  parameters as electromagnetic waves pass  between
tranmission/relieving stations and thus through the wall.  These
methods "sample" the entire wall  but do not have the resolution
of  the probe methods.   They  also tend  to require  more
sophisticated equipment and data  reduction.  Based on work done
to date,  potential  candidates  of  each type will be treated
individually below.


C.2  Probe Methods


     The three primary classes of probe methods are soil borings
with undisturbed sampling, down-hole geophysical methods and
piezocone  sounding.

                             9-1

-------
     C.2.1  Borings/Sampling


     This method provides  the most definitive evaluation  of
window characteristics once they have been located.  This  results
directly from the  sample retrieval capability.  However,  the
process is very slow and costly.  Past experience indicates  that
the  wall sampling and sample  testing  effort needed  to
statistically evaluate  window occurrence can easily cost up  to
50 percent of the construction  cost  of the wall.


     C.2.2  Down-Hole Geophysics


     A number  of  individual sensing  mechanisms  can  be
incorporated in  a down-hole probe such as acoustical  fracture
mapping, nuclear density, conductivity, etc.   While some of these
mechanisms may respond well to differences in windows vs.  intact
backfill, they all  require  borehole installation prior to use.
As such,  these methods were ruled as impractical  due to  the costs
associated with  the required boring program as above.  However,
these methods may become practical  for  window detection  if
packaged  in a direct insertion  probe.


     C.2.3  Piezocone Soundings


     The standard configuration of probe simultaneously detects
point  resistance,  side friction,  and  excess pore  pressure
generation during insertion into the wall.  Correlation of the
three parameters indicates the  type  of material  penetrated.   The
probe is inserted by a drill rig at 1 to 2 cm/sec.   About 250
linear feet of probing can be done a day, and as  such, the method
is reasonable from a cost standpoint.

     The low density and strength  of the backfill in conjunction
with rigid push rods result in vertical penetration.   The  small
diameter of the probe and rods (less  than 2.5 inches) renders the
size of these vertical holes  unimportant to the  integrity of the
wall.  In addition, it is  expected  that upon  extraction of the
probe, the hole  will close  due to the  plastic nature of  the
backfill.
                             9-2

-------
C.3  Scan Methods


     A number  of  "scan  type"  methods  exist.  The  following
discussion will be limited to surface methods in that cross-hole
geophysics was  judged  too costly due  to the requirement for
borehole installation.   Surface  geophysical methods include:
ground penetrating  radar,  various  seismic techniques, acoustic
monitoring, terrain conductivity, and resistivity. The  following
sections  provide  a brief outline of these methods  and their
probable limitations.


     C.3.1  Ground Penetrating Radar  (GPR)


     Initial work  indicated that  radar  would probably  not be
applicable  in soil/bentonite cutoff wall because the  backfill has
a very  high conductivity, thus  resulting in high attenuation
rates.  In  addition,  the verticality  of  the wall relative  to the
horizontal' antenna  array  yields  poor  backscattering
characteristics.  These observations  were  confirmed  when  GPR was
used  to locate the  centerline  of the  cutoff wall  at  the Gilson
Road site.  While the  wall  was  easily  distinguishable from the
native  sand and gravel  formation, penetration was limited to
approximately 10 to 15  feet.


     C.3.2  Seismic


     Seismic methods were easily  ruled out in that the wave
velocity through intact  backfill  and windows is expected to be
nearly identical.   This  is a direct result  of the high influence
of water on wave velocity and the  fully saturated nature  of all
backfill materials including windows.


     C.3.3  Acoustic Emission


     Standard acoustic  emission  monitoring techniques  are not
appropriate for window detection because  differences  in
intergranular. shear strain are not expected in the backfill due
to the presence of  windows.  In  addition,  even though  seepage
velocities through  windows in  the wall would be much higher than
those through intact  backfill,  it is not expected that the
stresses  induced  would  generate  significant emissions.
Furthermore, the natural soil on  either  side of the wall would


                            9-3

-------
typically preclude piping and  the  associated highly turbulent
flow (large emission potential).

     More recent developments center  around monitoring the
acoustic emissions generated  by probe  induced  material
displacement during a sounding.  Equipment packaging is similar
to the piezoconeinstrument.  This  probe  technique may  offer
potential for anomaly detection  in soil/bentonite cutoff walls,
but was  not yet available during execution of this research.


     C.3.4  Terrain Conductivity


     Terrain conductivity has been  shown  effective  in locating
changes  in  the  conductivity  caused by  contaminant plumes.
However, a number of constraints render this method inappropriate
for investigation of the occurrence of windows  in the Gilson Road
cutoff wall.

     0  This  method will  not respond to  the physical differences
        between windows and the  intact backfill due to .the same
        limitations discussed under "GPR" methods and standard
        resistivity sounding methods.

     0  Cutoff walls  are constructed to contain typically the
        most highly contaminated portion  of a plume and not the
        entire  plume.  As such, contaminated water exists on both
        sides of  the wall thus, it is difficult to locate windows
        via detection of contaminants escaping  through wall.

     0  It is  not likely that the detection range associated with
        terrain conductivity methods would allow detection of
        contaminated  water  escaping from  windows located at
        depth,  even if the water outside  the wall was clean.
        This  is  particularly true for contaminant plumes which
        contain only organic  chemicals in the parts per million
        concentration range.

     0  Windows  located near the top of the wall could not be
        detected via differences in the  conductivity of the
        groundwater in areas  (1) where clean water exists on both
        sides of  the wall  (upgradient) and  (2) where there is no
        gradient  across the wall.


     C.3.5  Resistivity


     Resistivity  methods  using  a  standard electrode
configurations  for sounding  with depth  such  as Wenner  &

                             9-4

-------
Schlumberger arrays,  appear  to encompass too large a mass outside
the wall at trench depths  approaching 100 feet.  This is  a direct
result of  the wall geometry;  disproportionate depth  to width
distances.   These geometrical  limitations  tend to  mask the
potential  perturbation  caused by small windows.  Therefore,  it  is
anticipated that probes  would have to be inserted inside  the wall
and current flow between electrodes measured directly.

     While  this  method  appeared  feasible, it  would require
significant development  work  and as such, was  considered outside
the scope of this effort.
 
-------