-------
and emission factors have been presented in Table 4-4 only when they were the predominant
method used.
It was uncommon for facilities to have access to monitoring data for fugitive
releases. However, it was used when available (typically in the form of periodic leak tests).
Emission factors were used by several facilities (except in SIC Code 25). The type of emission
factors used and a subsequent discussion is presented below. Mass balances were also used by
many facilities to determine fugitive releases from at least one process line or unit operation
when a material balance around the entire facility resulted in a quantity of chemical that was
unaccounted for.
Most facilities reported a stack release. Although facilities had difficulty in
estimating these releases, they typically indicated less difficulty in identifying and quantifying
these releases than observed with fugitives. Engineering calculations and mass balances were the
most often used methods. However, the use of emission factors (including emission factors for
releases from storage tanks and facility-derived factors for releases from stacks) and monitoring
data (actual releases from stack tests) were often observed. Facilities with sophisticated
monitoring equipment associated with large stack emissions, such as chemical manufacturers and
pulp and paper mills, were more likely to use monitoring data and/or associated emission factors
than smaller facilities, such as paint manufacturers which typically used mass balances or
engineering judgement.
Table 4-4 and the corresponding figures also show that most facilities used
monitoring data and/or hazardous waste manifests in conjunction with engineering calculations
to estimate transfers off-site for further waste management. There were two main sources of
these data. One was from periodic facility sampling of the waste that was collected prior to
shipment. The second was from sampling conducted by the receiving facility. Documentation
for this data was typically more prevalent and more complete (and therefore, presumably more
accurate) than methods used to estimate releases to most other sources.
4-39
-------
Figure 4-5. Frequency the Facility Used the Best Methodology to Estimate Releases
and Other Waste Management Activities
-t^
o
100%
90%
80% - -
70%
60% -
50% -
40%
30%
20%
10%
SIC Code 25 SIC Code 281 SIC Code 285 SIC Code 30 SIC Code 26 SIC Code 286
-------
Some facilities reported discharges to POTWs and/or receiving streams
(predominantly organic chemical manufacturer and pulp and paper mills, which have large water
releases). A mass balance and/or engineering judgement were the primary methods used for
POTW discharges. Facilities typically used a mass balance around the entire facility to
determine the quantity of EPCRA Section 313 chemical that could not be accounted for. Then,
engineering judgement (usually based on knowledge of chemical volatility and solubility) was
used to estimate a partition factor between releases of the unaccounted quantity that would be
lost to fugitive air vs. that sent to a POTW. This method was also used to determine discharges
to receiving streams, when applicable. However, discharges to receiving streams were often
monitored for compliance with various local, state, or other federal regulations, resulting in a
more accurate estimate.
Figure 4-5 presents the frequency that site surveyors felt the method used by the
facility would result in the most accurate estimate of release or other waste management quantity
based on information and data available to the surveyor at the time of the site visit. It does not
present the frequency that the facility correctly calculated the quantity of release or other waste
management activity. This figure shows concurrence with the selected method in most cases. It
should be noted that during many visits the surveyor identified another, more accurate method
that could have been used to estimate releases and other waste management quantities, if a
particular variable had been tracked for the reporting year. In many cases, the facility contact
indicated that it would have been fairly easy for the facility to implement the suggestion and that
they planned to take the surveyors advice for subsequent years. However, there was no way to
recreate the required variable for the reporting year(s) surveyed. Another limitation to this
analysis is the fact that surveyors often identified a more accurate method that could be used
based on data the facility claimed to have. However, the facility stated that they could not gather
the information in a reasonable time period for use by the site surveyor.
Emission factors were frequently used to estimate fugitive and stack releases.
EPA instructed site surveyors to determine the type of emission factors used, when applicable.
The potential types were designated as facility-derived, EPA-approved or published, trade
4-41
-------
Table 4-5
Types of Emission Factors Used for Fugitive and Stack Releases
RY1994 and RY1995
Release and Other Waste
Management Activity Type
Fugitive
Stack
Release and Other Waste
Management Activity Source
Facility Derived
EPA Derived
Trade Association Derived
Other
TOTAL:
Facility Derived
EPA Derived
Trade Association Derived
Other
TOTAL:
Percent (weighted by chemical)
sic
Code 25
93.9%
0.0%
0.0%
6.1%
100.0%
0.0%
61.6%
0.0%
38.4%
100.0%
SIC
Code 281
26.9%
8.4%
51.8%
12.9%
100.0%
53.2%
38.4%
0.0%
8.4%
100.0%
SIC
Code 285
38.7%
61.3%
0.0%
0.0%
100.0%
82.7%
17.3%
0.0%
0.0%
100.0%
SIC
Code 30
35.3%
27.6%
37.1%
0.0%
100.0%
81.9%
12.9%
5.2%
0.0%
100.0%
SIC
Code 26
5.0%
0.0%
90.0%
5.0%
100.0%
10.7%
3.6%
85.7%
0.0%
100.0%
SIC
Code 286
13.9%
41.7%
36.1%
8.3%
100.0%
33.3%
56.7%
10.0%
0.0%
100.0%
-------
Figure 4-6a. Type of Emission Factors Used (Fugitive)
RY1994 and RY1995
12.9%
26.9%
8.3%
38.7%
13.9%
51.8%
SIC Code 281 (RY
6.1%
'8.4%
93.9%
SIC Code 25 (RY 1994)
61.3%
SIC Code 285 (RY 1994)
37.1%
35.3%
27.6%
SIC Code 30 (RY 1994)
41.7%
36.1%
SIC Code 286 (RY 1995)
5.0% 5.0%
90.0%
SI C Code 26 (RY 1995)
rj Facility Derived
I EPA Derived
I Trade Association Derived
I Other
-------
Figure 4-6b. Type of Emission Factors Used (Stack)
RY1994 and RY1995
8.4%
38.4%
SIC Code 281 (RY
53.2%
10.6%
SIC Code 285 (RY 1994)
35.4%
53.9%
SIC Code 286 (RY 1995)
38.4%
5.2%
61.6%
SIC Code 25 (RY 1994)
12.9%
81.9%
SIC Code 30 (RY 1994)
10.7%
3.6%
85.7%
SIC Code 26 (RY 1995)
rj Facility Derived
EPA Derived
i Trade Association Derived
I Other
-------
association-derived, and other. Table 4-5 and Figures 4-6a and 4-6b present the percentage of
use for each type of emission factor (weighted).
These factors were typically employed to estimate fugitive releases of volatile
chemicals from process areas (open mix tanks or vats) or piping (leaks from pumps, valves,
flanges, etc.) or to estimate stack releases from storage tanks and stack releases from gasses
generated by unit operations that were channeled through stacks (typically stacks from various
air pollution control devices).
4.5 On-Site Waste Management Activities frecvcling. treatment and energy
recovery)
Quantities of the toxic chemicals in waste managed by on-site waste management
activities (recycling, treatment, and energy recovery) were rarely observed during the site visits.
Table 4-2 and Figure 4-2 show that a considerable number of facilities in SIC Codes 26 and 286
incorrectly identified these releases. It should be noted that there may be considerable
uncertainty in the quantitative values presented because most facilities were confused by the
definition of "recycling". EPA recognized, before the RY 1994 and RY 1995 site surveys were
initiated, that this potential might exist and instructed site surveyors only to analyze releases to
recycling activities if the facility reported them. Therefore, site surveyors only recorded on-site
waste management activities as incorrect if such activities were claimed but did not exist.
Facilities typically correctly identified on-site treatment activities when they existed. However,
there was considerable confusion and error when the releases and other waste management
activities were quantified for Section 8 of the Form R.
Additionally, for the site visits completed through May 1997 (those pertaining to
RY94) EPA only asked site surveyors to compile the data for source reduction and on-site
recycling. Site surveyors were not requested to investigate these issues further or discuss them
with the facility contacts. Therefore, specific, quantitative input from these visits cannot be
provided, other than raw data based on what was reported by each facility.
4-45
-------
Additionally, EPA was concerned that facilities may incorrectly report the
quantity of EPCRA Section 313 Chemicals to on-site treatment in Section 8 of the Form R due to
potential confusion between requirements for Section 7 and Section 8. Site surveyors
specifically determined whether the quantities reported were quantities sent to treatment or
quantities actually treated. Figure 4-7 presents the weighted percent of facilities that incorrectly
reported the quantity sent to treatment rather than that actually treated. A significant number of
facilities in SIC Codes 26 and 286 incorrectly reported this quantity (25.8% and 48.6%,
respectively) while only one facility incorrectly reported from SIC Code 281 (representing 1.2%)
and no facilities from SIC Codes 25, 30, or 281 incorrectly reported.
Figure 4-7. Facilities Incorrectly Reporting the Quantity sent to Treatment
Rather than that Actually Treated (Weighted)
60%
50%
40%
30%
o
o
20%
§
ffi
Q.
10%
0%
48.6%
0.0%
0.0%
1.2%
0.0%
SIC Code 25 SIC Code 281 SIC Code 285 SIC Code 30 SIC Code 26 SIC Code 286
It was observed that many facilities in the organic chemical and the paper
manufacturing SIC Codes, 286 and 26, respectively, had large on-site wastewater treatment
plants. Several EPCRA Section 313 chemicals (such as ammonia, sulfuric acid, and chlorine)
were used in the treatment process. Several facilities incorrectly reported that these chemicals
were treated themselves because they were destroyed during the treatment process. EPCRA
Section 313 chemicals added to waste treatment units are not considered to be treated
themselves. This situation was never observed at facilities in SIC Codes 25, 281, 285, or 30
because these facilities did not typically have on-site wastewater treatment plants or the quantity
of treatment chemical used was below the threshold.
4-46
-------
EPA requested site surveyors to discuss source reduction and on-site recycling
issues and acquire feedback from facility contacts during visits to SIC Codes 26 and 286 (those
pertaining to RY 1995).
The following points were raised by facility contacts during the 20 visits to Paper
and/or Organic Chemical facilities for RY 1995.
• Facilities tend to only claim source reduction or recycling if they
implement a procedure for the specific purpose of reducing releases.
Often a facility implements one or more of the items that EPA considers
source reduction, but they do not bother to go through the entire list to see
if they can claim it. For example, a facility may change their raw material
transfer operations due to a management decision. This change may result
in source reduction as a side effect, but the facility does not claim it
because the purpose was not source reduction.
• Facilities often do not claim source reduction or recycling activities due to
what they consider to be a lack of detailed definitions. For example,
facilities believe that many of the codes and corresponding descriptions
are vague and they do not feel comfortable claiming an activity without
better guidance.
• Facilities have stated that they would rather be conservative and only
claim a source reduction or recycling activity if they can verify and
document it. For example, some categories such as "better management
practices" are vague and facilities do not claim it because they do not
know how to verify it.
• Some trade associations instruct their members not to claim a source
reduction activity unless they can document a corresponding reduction in
releases - even if the facility specifically installs a unit or practice that is
intended to serve as recovery or recycling.
• Facilities have stated that there are so many codes that they do not bother
to analyze each code every year to see if any changes in their processes
apply.
Tables 4-6 through 4-11 summarize data that was collected for on-site recycling
that was observed during site visits pertaining to RY 1994 and RY 1995. Table 4-11 presents the
frequency that each chemical was recycled, as reported by these facilities.
4-47
-------
Table 4-6
Observed On-Site Recycling Activities
(SIC Code 281)
# Of Facilities
Reporting
1
1
1
2
3
1
1
Type of Recycling
Claimed
Cleaning Waste
Spent Process Solvent
Other
Other
Other
Other
Other
Description of Recycling Stream
Not Specified
Not Specified
Scrubber Water
Dust Collector Waste
Off-Spec. Product
Ion Exchange Waste
Vapor Recovery Unit
Table 4-7
Observed On-Site Recycling Activities
(SIC Code 285)
# Of Faculties
Reporting
5
5
Type of Recycling
Claimed
Cleaning Waste
Spent Process Solvent
Description of Recycling Stream
Not Specified
Not Specified
4-48
-------
Table 4-8
Observed On-Site Recycling Activities
(SIC Code 25)
# Of Facilities
Reporting
1
1
1
1
1
1
Type of Recycling
Claimed
Spent Process Solvent
Spent Process Solvent
Spent Process Solvent
Other (obsolete material)
Cleaning Waste
Cleaning Waste
Description of Recycling Stream
Distillation Unit
Not Specified
Batch Still and Thin-Film Evaporation
Batch Still
Not Specified
Batch Still and Thin-Film Evaporation
Table 4-9
Observed On-Site Recycling Activities
(SIC Code 30)
# Of Facilities
Reporting
1
1
1
Type of Recycling
Claimed
Spent Process Solvent
Other
Other (off-spec product)
Description of Recycling Stream
Not Specified
Resin from waste plastic
Reuse in subsequent batch
4-49
-------
Table 4-10
Observed On-Site Recycling Activities
(SIC Code 286)
# Of Faculties
Reporting
1
4
1
3
Type of Recycling
Claimed
Not specified
Spent Process Solvent
Other
Other (unreacted raw
materials)
Description of Recycling Stream
Removed Stack Emissions
Not Specified
Scrubber Water
Process Waste (off-spec product)
4-50
-------
Table 4-11
Chemicals For Which Recycling Was Claimed
(SIC Codes 281,285,25,30, and 286 Combined)
CHEMICAL
Xylene
Toluene
Methanol
MffiK
1,3 -Butadiene
Ammonia
Ethylbenzene
Ethylene glycol
Glycol enters
2-ethoxyethanol
4,4'-isopropylidenediphenol
Ammonium Nitrate
Aniline
Chlorine
Copper Compounds
Cyanide Compounds
Di-(2-ethylhexyl)Phthalate
Dichloromethane
Freon
HC1
Mercury
N-butyl alcohol
N-butyl alcohol
Nitric Acid
N-N-Dimethylaniline
Phosphoric Acid
# CW FACILITIES 8EFOHHNG
7
5
3
3
2
2
2
2
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
4-51
-------
-------
5.0 RELEASES AND OTHER WASTE MANAGEMENT ACTIVITIES
5.1 On-Site Release and Transfers Off-Site for Waste Management Estimates
Release and other waste management estimates are the most highly scrutinized
and publicized data in the TRI program. This section and section 5.2 discuss release estimates
and other waste management activities made by facilities and by site surveyors. Major
differences in these estimates between the facilities and the site surveyors are noted and, if
possible, the reasons for the differences are explained. A discussion of the methodology used by
the site surveyors to gather the data necessary to estimate these quantities is contained in Section
2. A discussion of the specific techniques used by the facilities and by the site surveyors when
estimating releases and other waste management quantities is contained in Section 4.
Releases and transfers off-site for waste management estimates are reported by
chemical and by the medium to which the chemical was released or transferred. When
completing the Form R, facilities must assign on-site releases to one of the following five
categories:
— Fugitive or non-point air emissions;
— Stack or point air emissions;
— Discharges to receiving streams or water bodies;
— Underground injections on site; or
— Releases to land on site.
Transfers to other off-site locations for other waste management practices are further subdivided
into:
— Discharges to Publicly Owned Treatment Works (POTWs);
— Off-site transfer for disposal;
— Off-site transfer for treatment;
— Off-site transfer for recycling; and
— Off-site transfer for energy recovery.
This section also contains a discussion of releases and other waste management practices to each
medium, how facility estimates compared to site surveyors estimates for that medium, and how
estimates for reporting years 1994 and 1995 compared to estimates from reporting years 1987
and 1988.
5-1
-------
When comparing the release and other waste management activity estimates of a facility to the
estimate of a site surveyor, the percent difference between the two estimates is used. The percent
difference between the facility estimate and the site surveyor estimate is calculated as follows:
Percent Difference = (Fa - SS)/SS x 100
where: Fa = Facility Estimate
SS = Site Surveyor Estimate
5.1.1 Overview of Oil-Site Releases and Transfers Off-Site for Waste Management
as Reported by Facilities and by Site Surveyors
On-site releases and transfers off-site for waste management quantities as reported
by the facilities and the site surveyors were summed for all chemicals to get total facility
estimates. Total facility estimates were scaled and summed for all facilities to get total releases
and other waste management quantities for each SIC Code. The total quantity for each SIC Code
are presented by medium in Tables 5-1, 5-3, 5-5, 5-7, 5-9, and 5-11. Facility estimates were
lower than site surveyor estimates in all SIC Codes for fugitive air releases, transfers to off-site
recycling, and transfers to off-site energy recovery. In general, facility estimates were higher
than site surveyor estimates in each SIC Code for stack air releases. For all SIC Codes surveyed
for reporting year (RY) 1994, total quantities for the SIC Code as estimated by the facility are
lower than total quantities for the SIC Code as estimated by the site surveyor. Total on-site
releases and transfers off-site for waste management for SIC Codes 26 and 286, surveyed for RY
1995, as estimated by the facility are within 2% of the total quantities estimated by the site
surveyor.
5-2
-------
Table 5-1 is a summary of SIC Code 25 TRI on-site releases and transfers off-site
for waste management quantities for the RY 1994. The greatest percent difference in estimates
by facility and by site surveyor are for off-site transfers to treatment, where facility estimates
were 250% greater than site surveyor estimates. The overall impact of this difference in off-site
treatment is not significant, as transfer to off-site treatment makes up only a small portion of the
total quantity. None of the facilities surveyed in SIC Code 25 had releases to receiving streams,
performed underground injection, or had releases to land on site. Total on-site releases and
transfers off-site for waste management estimated by facilities and site surveyors were in close
agreement.
Table 5-1
Summary of SIC Code 25 TRI On-Site Releases and Transfers Off-Site for
Waste Management for Reporting Year 1994 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
Total
Quantity of Chemicals as
Reported by the Facilities
3.72
37.9
0.00
0.00
0.00
0.647
0.00
1.13
0.733
9.12
53.3
Quantity of Chemicals as
Reported by the Site
Surveyors
4.54
36.9
0.00
0.00
0.00
0.783
0.437
0.319
1.20
10.6
54.8
Percent Difference*
-18%
2.8%
NA
NA
NA
-17%
-100%
250%
-39%
-14%
-2.8%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to this medium at the facilities surveyed in this SIC Code.
5-3
-------
Table 5-2 presents two forms of the 1994 on-site releases and transfers off-site for
waste management for SIC Code 25. In the second column, on-site releases and transfers off-site
for waste management as reported by the facilities surveyed were scaled-up to represent the total
releases and transfers off-site for waste management for SIC Code 25 for those facilities with less
than 16 Form Rs. Thus, each facility surveyed represents a group of facilities in the TRIS
database to determine the scaled-up total. The third column is the total on-site releases and
transfers off-site for waste management amount for SIC Code 25 as reported by SIC Code 25
facilities with less than 16 Form Rs taken from the TRIS database. This comparison examines
how closely the surveyed facilities match the overall SIC Code 25 release profile. (Site
surveyors estimates are not presented on this table). As discussed in Section 2, facility site
selection excluded facilities that reported more than 15 chemicals. Most facilities that
manufacture, process, or otherwise use more than 15 chemicals would have larger quantities than
the average facility. The percent difference in total on-site releases and transfers off-site for
waste management quantities between the scaled-up estimate and the TRI database totals is -
17%.
Table 5-2
1994 Reported TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Code 25 (millions of Ibs.)
Medium
Fugitive and Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Scaled Quantity of
Chemicals as Reported
by the Facilities Surveyed
41.6
0.00
0.00
0.00
0.647
11
53.3
Quantity of Chemicals as
Reported by All Facilities
in the TRIS Database
51.5
0.000266
0.00
0.0637
0.145
12.6
64.3
Percent Difference*
-19%
-100%
0.0%
-100%
346%
-13%
-17%
*Percent Difference = (Sea - TRI)/TRI x 100, where Sea = Scaled Facility Estimate Total and TRI = Facility
Estimate Total as Reported to TRI.
5-4
-------
Table 5-3 is a summary of SIC Code 281 TRI on-site releases and transfers off-
site for waste management for RY 1994. In SIC Code 281, the most significant difference
between facility estimates and site surveyor estimates is in underground injection. This
difference is attributed to errors made by two facilities surveyed. These two facilities perform
manufacturing process operations that are not typical in chemical manufacturing facilities. If
these two facilities are not considered in the sum of on-site releases and transfers off-site for
waste management, the total percent difference for total on-site releases and transfers off-site for
waste management quantities in SIC Code 281 releases drops to -1.1 percent.
Table 5-3
Summary of SIC Code 281 TRI On-Site Releases and Transfers Off-Site for
Waste Management for RY 1994 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
Total
Quantity of Chemicals as
Reported by the Facilities
15.4
126
1.73
15.0
0.00440
0.0644
29.9
9.97
1.18
0.304
200
Quantity of Chemicals as
Reported by the Site
Surveyors
16.1
126
1.65
38.0
0.00440
0.0641
30.0
10.1
1.48
2.00
225
Percent Difference*
-4.3%
0.53%
5.1%
-61%
0.0%
0.47%
-0.17%
-1.5%
-21%
-85%
-11%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to this medium at the facilities surveyed in this SIC Code.
5-5
-------
Table 5-4 presents two forms of the 1994 on-site releases and transfers off-site for
waste management for SIC Code 281. In the second column, on-site releases and transfers off-
site for waste management as reported by the facilities surveyed were scaled-up to represent the
total on-site releases and transfers off-site for waste management quantities for SIC Code 281 for
those facilities with less than 16 Form Rs. The third column is the total on-site releases and
transfers off-site for waste management amount for SIC Code 281 as reported by all SIC Code
281 facilities with less than 16 Form Rs taken from the TRIS database. This comparison
examines how closely the surveyed facilities match the overall SIC Code 281 release profile.
(Site surveyors estimates are not presented on this table). The percent difference in total on-site
releases and transfers off-site for waste management quantities between the scaled-up estimate
and the TRI database totals is -51%.
Table 5-4
1994 Reported TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Code 281 (millions of Ibs.)
Medium
Fugitive and Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Scaled Quantity of
Chemicals as Reported
fcy the Facilities Surveyed
141
1.73
15.0
0.004
0.064
41.1
200
Quantity of Chemicals AS
Reported by All Facilities
ill the TRIS Database
90.8
25.4
153
68.2
31.4
41.1
410
Percent Difference*
36%
-94%
-90%
-100%
-100%
0.7%
-51%
*Percent Difference = (Sea - TRI)/TRI x 100, where Sea = Scaled Facility Estimate Total and TRI = Facility
Estimate Total as Reported to TRI.
5-6
-------
Table 5-5 is a summary of SIC Code 285 TRI on-site releases and transfers off-
site for waste management for the reporting year 1994. The most significant difference in on-site
releases and transfers off-site for waste management activity estimates by facility and by site
surveyor are for transfers to off-site recycling. None of the facilities surveyed in SIC Code 285
had releases to receiving streams, underground injection, or to land on site. One of the surveyed
facilities in this SIC Code put release values under the wrong release type and grossly
underestimated all on-site releases and transfers off-site for waste management. If this facility is
not considered in the total sum, the total percent difference between facility estimates and site
surveyor estimates in SIC Code 285 drops to -20%.
Table 5-5
Summary of SIC Code 285 TRI On-Site Releases and Transfer Off-Site for
Waste Management for RY1994 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
Total
Quantity of Chemicals as
Reported by the Facilities
2.23
0.654
0.00
0,00
0.00
0.0615
0.0874
0.101
2.75
2.67
8.55
Quantity of Chemicals as
Reported by the Site
Surveyors
3.15
0.533
0.00
0.00
0.00
0.0157
0.219
0.462
5.08
2.87
12.3
Percent Difference*
-29%
23%
NA
NA
NA
290%
-60%
-78%
-46%
-7.0%
-31%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to this medium at the facilities surveyed in this SIC Code.
5-7
-------
Table 5-6 presents two forms of the 1994 on-site releases and transfers off-site for
waste management for SIC Code 285. In the second column, on-site releases and transfers off-
site for waste management quantities as reported by the facilities surveyed were scaled-up to
represent the total on-site releases and transfers off-site for waste management quantities for SIC
Code 285 for those facilities with less than 16 Form Rs. The third column is the total on-site
releases and transfers off-site for waste management amount for SIC Code 285 as reported by all
SIC Code 285 facilities with less than 16 Form Rs taken from the TRIS database. This
comparison examines how closely the surveyed facilities match the overall SIC Code 285 release
profile. (Site surveyors estimates are not presented on this table). The percent difference in total
on-site releases and transfers off-site for waste management releases and other waste
management quantities between the scaled-up estimate and the TRI database totals is -92%.
Table 5-6
1994 Reported TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Code 285 (millions of Ibs.)
Medium
Fugitive and Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Scaled Quantity of
Chemicals as Reported
by the Facilities Surveyed
2.88
0.00
0.00
0.00
0.0615
5.61
8.55
Quantity of Chemicals as
Reported by All Facilities
in the TRIS Database
13.5
0.00
0.00
0.055
1.63
95.5
111
Percent Difference*
-79%
0.0%
0.0%
-100%
-96%
-94%
-92%
*Percent Difference = (Sea - TRI)/TRI x 100, where Sea = Scaled Facility Estimate Total and TRI = Facility
Estimate Total as Reported to TRI.
5-8
-------
Table 5-7 is a summary of SIC Code 30 TRI on-site releases and transfers off-site
for waste management quantities for the reporting year 1994. Many facilities in this SIC Code
reported fugitive emissions as stack emissions. Even so, the sum of the fugitive and stack
emissions estimated by the facilities and site surveyors was in close agreement. The greatest
percent difference in estimates by facility and by site surveyor are for discharges to POTWs,
where facility estimates were 100% less than site surveyor estimates. However, discharges to
POTWs account for much less than 0.1 percent of all quantities. None of the facilities surveyed
in SIC Code 30 had on-site releases to receiving streams, underground injection, or to land on
site. Total on-site releases and transfers off-site for waste management quantities estimated by
facilities and site surveyors were in close agreement.
Table 5-7
Summary of SIC Code 30 TRI On-Site Releases and Transfers Off-Site for
Waste Management for RY1994 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
Total
Quantity of Chemicals as
Reported by the Facilities
26.0
182
0.00
0.00
0.00
0.00
7.13
21.6
10.9
0.332
248
Quantity of Chemicals as
Reported by the Site
Surveyors
69.3
138
0.00
0.00
0.00
0.00145
5.84
23.5
17.2
0.347
254
Percent Difference*
-63%
31%
NA
NA
NA
-100%
22%
-8.1%
-37%
-4.3%
-2.4%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to this medium at the facilities surveyed in this SIC Code.
5-9
-------
Table 5-8 presents two forms of the 1994 on-site releases and transfers off-site for
waste management quantities for SIC Code 30. In the second column, on-site releases and
transfers off-site for waste management quantities as reported by the facilities surveyed were
scaled-up to represent the total on-site releases and transfers off-site for waste management
quantities for SIC Code 30 for those facilities with less than 16 Form Rs. The third column is the
total on-site releases and transfers off-site for waste management amount for SIC Code 30 as
reported by all SIC Code 30 facilities with less than 16 Form Rs taken from the TRIS database.
This comparison examines how closely the surveyed facilities match the overall SIC 30 release
profile. The percent difference in total on-site releases and transfers off-site for waste
management quantities between the scaled-up estimate and the TRI database totals is 7.4%.
Table 5-8
1994 Reported TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Code 30 (millions of Ibs.)
Medium
Fugitive and Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Scaled Quantity of
Chemicals as Reported
by the Facilities Surveyed
208
0.00
0.00
0.00
0.00
40.0
248
Quantity of Chemicals as
Reported fay All Facilities
in the TRIS Database
154
0.230
0.00
0.357
2.22
73.7
231
Percent difference*
35%
-100%
0.0%
-100%
-100%
-46%
7.4%
*Percent Difference = (Sea - TRI)/TRI x 100, where Sea = Scaled Facility Estimate Total and TRI = Facility
Estimate Total as Reported to TRI.
5-10
-------
Table 5-9 is a summary of SIC Code 26 TRI on-site releases and transfers off-site
for waste management for RY 1995. None of the facilities surveyed in SIC Code 26 had releases
to underground injection, off-site treatment, off-site recycling, or off-site energy recovery.
Facility and site surveyor estimates are in close agreement. The close agreement between the
facility and surveyor estimates in SIC Code 26 can be attributed to the step-by-step procedures
listed in the NCASI Handbook of Chemical Specific Information for SARA 313 Form R
Reporting which most paper and paperboard facilities use as guidance for filling out Form Rs.
This manual is distributed by NCASI, and has not been through EPA approval. However, it is
still a good source for documentation and calculations needed to complete the Form Rs.
Table 5-9
Summary of SIC Code 26 TRI On-Site Releases and Transfers Off-Site for
Waste Management for RY 1995 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
Total
Quantity of Chemicals as
Reported by the Facilities
12.6
69.9
2.03
0
0.189
0.00421
0.761
0
0
0
85
Quantity of Chemicals as
Reported by the Site
Surveyors
12.9
69.1
1.85
0
0.119
0.00421
0.767
0
0
0
85
Percent Difference*
-2.5%
1.2%
9.6%
NA
59%
0.0%
-0.74%
NA
NA
NA
0.8%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to this medium at the facilities surveyed in this SIC Code.
5-11
-------
Table 5-10 presents two forms of the 1995 on-site releases and transfers off-site
for waste management for SIC Code 26. In the second column, on-site releases and transfers off-
site for waste management as reported by the facilities surveyed were scaled-up to represent the
total on-site releases and transfers off-site for waste management for SIC Code 26 for those
facilities with less than 16 Form Rs. The third column is the total on-site releases and transfers
off-site for waste management amount for SIC Code 26 as reported by SIC Code 26 facilities
with less than 16 Form Rs taken from the TRIS database. This comparison examines how
closely the surveyed facilities match the overall SIC Code 26 release profile. (Site surveyors
estimates are not presented on this table). The percent difference in total on-site releases and
transfers off-site for waste management between the scaled-up estimate and the TRI database
totals is -66%.
Table 5-10
1995 Reported TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Code 26 (millions of Ibs.)
Medium
Fugitive and Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Scaled Quantity of
Chemicals as Reported
by the Facilities Surveyed
82.5
2.03
0.00
0.189
0.00421
0.761
85
Quantity of Chemicals as
Reported by All Facilities
in the TRIS Database
166
7.01
0.00
3.39
41.0
29.9
247
Percent Difference*
-50%
-71%
0.0%
-94%
-100%
-97%
-66%
*Percent Difference = (Sea - TRI)/TRI x 100, where Sea = Scaled Facility Estimate Total and TRI = Facility
Estimate Total as Reported to TRI.
5-12
-------
Table 5-11 is a summary of SIC Code 286 TRI on-site releases and transfers off-
site for waste management quantities for the reporting year 1995. None of the facilities
surveyed in SIC Code 286 had on-site releases to underground injection. The close agreement
between the facility and surveyor estimates SIC Code 286 can be attributed to the relatively large
environmental staff and explicit corporate policies followed by the large organic chemical
companies visited.
Table 5-11
Summary of SIC Code 286 TRI On-Site Releases and Transfers Off-Site for
Waste Management for RY1995 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
Total
Quantity of Chemicals as
Reported by the Facilities
7.80
18.0
0.0958
0
0.000136
125
0.0910
36.4
5.11
127
320
Quantity of Chemicals as
Reported by the Site
Surveyors
9.15
16.7
0.123
0
0.000180
128
0.100
36.4
5.11
129
325
Percent Difference*
-15%
7.6%
-22%
NA
-24%
-2.2%
-9.3%
-0.04%
0.0%
-1.4%
-1.5%
'Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to this medium at the facilities surveyed in this SIC Code.
5-13
-------
Table 5-12 presents two forms of the 1995 on-site releases and transfers off-site
for waste management for SIC Code 286. In the second column, on-site releases and transfers
off-site for waste management as reported by the facilities surveyed were scaled-up to represent
the total on-site releases and transfers off-site for waste management for SIC Code 286 for those
facilities with less than 16 Form Rs. The third column is the total on-site releases and transfers
off-site for waste management amount for SIC Code 286 as reported by SIC Code 286 facilities
with less than 16 Form Rs taken from the TRIS database. This comparison examines how
closely the surveyed facilities match the overall SIC Code 286 release profile. (Site surveyors
estimates are not presented on this table). The percent difference in total on-site releases and
transfers off-site for waste management between the scaled-up estimate and the TRI database
totals is 8.0%.
Table 5-12
1995 Reported TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Code 286 (millions of Ibs.)
Medium
Fugitive and Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Scaled Quantity of
Chemicals as Reported
by the Facilities Surveyed
25.8
0.0958
0.00
0.00
125
169
320
Quantity of Chemicals as
Reported by All Facilities
in the TRIS Database
77.9
4.07
33.1
0.926
68.8
163
348
Percent Difference*
-67%
-98%
-100%
-100%
82%
3.7%
-8.0%
*Percent Difference = (Sea - TRI)/TRI x 100, where Sea = Scaled Facility Estimate Total and TRI = Facility
Estimate Total as Reported to TRI.
5-14
-------
Figure 5-1 presents estimates of total on-site releases and transfers off-site for
waste management calculated by facilities and site surveyors for each SIC Code surveyed for RY
1994 and RY 1995. The total on-site releases and transfers off-site for waste management were
in good agreement, calculated to be within +3% for most SIC Codes. Estimates of total on-site
releases and transfers off-site for waste management calculated by facilities and site surveyors
for all SIC Codes surveyed in RY 1994 and RY 1995 differed by 4%.
Figures 5-2, 5-3, and 5-4 present the relative percent differences in estimates of
on-site releases and transfers off-site for waste management between facilities and site surveyors
for each SIC Code. In all SIC Codes, fugitive emissions tend to be incorrectly reported as stack
emissions, leading to overestimates of stack emissions and underestimates of fugitive emissions.
Another trend in SIC Codes 25, 281, 285, and 30 for RY 1994 is the misreporting of chemical
transfers off-site for purposes of disposal, treatment, recycling, or energy recovery. Many
facilities do not record the actual fate of chemicals transferred off-site when filling out the Form
Rs. Most facilities check the off-site disposal or off-site treatment boxes without considering the
possibility of recycling or energy recovery. Facilities in these same SIC Codes tend to have
container residue that was overlooked. The container residue is usually treated, recycled, or
disposed of by the vendor collecting the drums, and not incorporated into the product as reported
by the facilities.
5.1.2 Comparison of RY 1994 and RY 1995 On-Site Releases and Transfers Off-
Site for Waste Management to RY 1987 and RY 1988 On-Site Releases and
Transfers Off-Site for Waste Management
Tables 5-13 through 5-16 contain the TRI on-site releases and transfers off-site for
waste management for the surveys conducted for RY 1995, 1994, 1988, and 1987 data,
respectively. Different SIC Codes were surveyed in each reporting year of the site survey
program, so caution should be exercised when comparing data from one reporting year to the
next. The tables present a comparison between the quantity of chemicals released on-site or
transferred off-site for waste management as reported by the facilities and the quantity of
chemicals released on-site or transferred off-site for waste management as reported by the site
surveyor. The percent difference between the estimates are also provided. The percent
differences for each reporting year are summarized on Figures 5-5 and 5-6.
5-15
-------
Figure 5-1. Comparison of Facility and Site Surveyor Estimates of Total On-Site Releases
and Transfers Off-Site for Waste Management
350
Facility
Site Surveyor
SIC Code 25 SIC Code 281 SIC Code 285 SIC Code 30
(RY 1994) (RY 1994) (RY 1994) (RY 1994)
Industry Sector
SIC Code 26
(RY 1995)
SIC Code 286
(RY 1995)
Data for this figure can be found on Tables 5-1 through 5-12.
-------
Ll-S
I
3
5'
O-
O
Percent Difference *
I
V
Stream (NA)
Underground Inje ction (NA)
(Q
c
8 £
ff !°
2 O
II
11.
3 to
(D O
2- =
5- a
O
8 S
10 3,
01 _|
fi> O
as
to JiJ
•5
«< 2.
(D W
o. 5"
II
O H
II
(Q (A
-------
Figure 5-3. Comparison of Estimates of Total On-Site Releases and Transfers Off-Site for
Waste Management in SIC Codes 285 and 30 Surveyed for Reporting Year 1994
290.0%5
00
290.0%
80.0%
-80.0%
-100.0%
Fugitive Air
Q Stack Air
Receiving Stream
Underground Injection
Land On-Site
PO7W
Off-Site Disposal
Off-Site Treatment
Off-Site Recycling
Off-Site Energy Recovery
SIC Code 285
SIC Code 30
* Percent Difference = (Fa-SS)/SS x 100, w here Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There w ere no releases to this medium at the facilities surveyed in this SIC Code.
Data for this figure can be found on Tables Tables 5-5 and 5-6.
-------
Figure 5-4. Comparison of Estimates of Total On-Site Releases and Transfers Off-Site for
Waste Management in SIC Codes 26 and 286 Surveyed for Reporting Year 1995
120.0%
100.0%
-80.0%
-100.0%
SIC Code 25
SIC Code 281
H Fugitive Air
n Stack Air
gg Receiving Stream
B Underground Injection
m Land On-Site
QPOTW
B Off-Site Disposal
H Off-Site Treatment
B Off-Site Recycling
B Off-Site Energy Recovery
* Percent Dfference = (Fa-SS)/SS x 100, w here Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There w ere no releases to this medium at the facilities surveyed in this SIC Code.
Data for this figure can be found on Tables 5-9 and 5-11.
-------
Table 5-13
Summary of RY 1995 TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Codes 26 and 286 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Quantity of Chemicals as
Reported by the Facilities
20
88
2.1
NA
0.19
125
169
405
Quantity of Chemicals as
Reported by the Site
Surveyors
22
86
2.0
NA
0.12
128
171
410
Percent Bifference*
-7.6%
2.4%
7.7%
NA
59%
-2.2%
-1.2%
-1.2%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
Table 5-14
Summary of RY 1994 TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Codes 25,281,285, and 30 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Quantity of Chemicals as
Reported by the Facilities
47
350
1.7
15
0.0044
0.77
98
510
Quantity of Chemicals as
Reported by the Site
Surveyors
93
300
1.7
38
0.0044
0.86
110
550
Percent Difference*
-49%
15%
5.1%
-61%
0.0%
-11%
-13%
-6.7%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
5-20
-------
Table 5-15
Summary of RY 1988 TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Codes 28,291, and 34 Through 38 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Quantity of Chemicals as
Reported by the Facilities
470
850
30
0.00
60
550
530
2,490
Quantity of Chemicals as
Reported by the Site
Surveyors
480
740
3
0.00
70
750
420
2,463
Percent Difference*
-2.1%
15%
900%
NA
-14%
-27%
26%
1.1%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
Table 5-16
Summary of RY 1987 TRI On-Site Releases and Transfers Off-Site for Waste
Management for SIC Codes 20 Through 39 (millions of Ibs.)
Medium
Fugitive Air
Stack Air
Receiving Stream
Underground Injection
Land On Site
POTW
Off-Site Transfers
Total
Quantity of Chemicals as
Reported by the Facilities
800
1,800
9,600
3,200
2,400
2,200
2,600
22,500
Quantity of Chemicals as
Reported by the Site
Surveyors
800
1,900
9,900
3,200
2,700
2,000
2,700
23,000
Percent Difference*
0.0%
-5.3%
-3.0%
0.0%
-11%
10%
3.7%
-2.2%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
5-21
-------
zz-s
o
0)
5T
-K -7 "
? if »
Percent Difference'
I
O
§
Cr
s-
CD
en
s
co
Q.
£
•tv
o> o
CD
O X
33
^ p
V) <
il
o S
3 >?
- B"
II
3* sr
O CD
CD C/)
•< 7=f
CD CD
II
CD S.
' C?
(Q
Ol
O
o
•o
fi>
55'
o
=
73
(Q CO
(O Q)
01 3
Q) $2.
to
to
CO
I
(A
ff
3
Q)
(Q
-------
to
LO
Figure 5-6. Comparison of On-Site Releases and Transfers Off-Site for Waste Management
from Reporting Years 1988 and 1987
900.0%
100.0%
-40.0%
1988 (SIC Codes 28, 291, 34-38)
1987 (SC Codes 25, 30, 281, 285)
* Percent Difference = (Fa-SS)/SS x 100, w here Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There w ere no releases to this medium at the facilities surveyed in this SIC Code.
B Fugitive Air
rj Stack Air
m Receiving Stream
g Underground Injection
H Land On-Site
• POTW
• Off-Site Transfers
Data for this figure can be found on Tables 5-11 and 5-12.
-------
The percent differences in facility and site surveyor total estimates for RY 1987,
RY 1988, RY 1994, and RY 1995 are presented in Table 5-17. The percent differences for each
reporting year were less than 7 percent.
Table 5-17
Percent Difference of Facility Estimated and Site Surveyor
Estimated Total TRI On-Site Releases and Transfers Off-Site for Waste
Management for RY 1995, RY 1994, RY 1988, and RY 1987 (millions of Ibs.)
TRI Reporting Year
1995
1994
1988
1987
Percent Difference*
-1.2%
-6.7%
1.1%
-2.2%
5.1.3
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site
Surveyor Estimate.
Analysis of Specific Releases
Analyses of specific on-site releases and transfers off-site for waste management
are presented in this section. These analyses only apply to facilities that correctly reported
chemical on-site releases and transfers off-site for waste management. Facilities that incorrectly
reported an on-site release or transfer off-site for waste management, incorrectly did not report an
on-site release or transfer off-site for waste management, or correctly did not report an on-site
release or transfer off-site for waste management are not included in the analyses in section 5.1.3.
On-site releases and transfers off-site for waste management in this section are analyzed on a
total facility basis. For example, if a facility underestimated the release of a chemical by 1,000,
but overestimated the release of another chemical by 1,000 Ibs, the errors would cancel and
would not be identified in this analysis.
5-24
-------
5.1.3.1
Fugitive Air Releases
A comparison of the percent difference between facility estimates and site
surveyor estimates for fugitive air releases is presented in Table 5-18. It is notable that in SIC
Code 30, over half the facilities estimates differed by more than 50 percent from the site surveyor
estimate.
Table 5-18
Comparison of the Percent Difference (PD)1 Between Facility and Site
Surveyor Estimates for Fugitive Air Emissions
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
21%
0%
7%
17%
43%
0%
% Facilities
Where
PD<1%
39%
13%
7%
17%
43%
0%
% Facilities
Where
PD<10%
47%
38%
12%
28%
43%
50%
% Facilities
Where
PD<50%
79%
67%
69%
40%
57%
83%
% Facilities
Where
PD>50%
21%
33%
31%
60%
43%
17%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Release Estimate, and SS = Site Surveyor Release Estimate.
Percentages are based on survey weighted data.
In Figure 5-7, the facility fugitive air emissions estimates are again compared to
the site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
5-25
-------
Figure 5-7. Comparison of Facility Estimates and Site Surveyor Estimates
for Fugitive Air Emissions
50%
24%
50%
17%
69%
SIC Code 281 (RY
SIC Code 285 (RY 1994)
83%
SIC Code 286 (RY 1995)
21%
17%
34%
28%
51%
49%
SIC Code 25 (RY 1994)
SIC Code 30 (RY 1994)
29%
29%
SIC Code 26 (RY 1995)
I Facility Estimate Equal to Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
Facility Estimate Less Than Site Surveyor Estimate
-------
5.1.3.2
Stack Air Releases
A comparison of the percent difference between facility estimates and site
surveyor estimates for stack air releases is presented in Table 5-19. It is notable that in SIC Code
285, over half the facilities' estimated releases differed by more than 50 percent from the site
surveyor estimate.
Table 5-19
Comparison of the Percent Difference (PD)1 Between Facility and Site
Surveyor Estimates for Stack Air Emissions
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
10%
0%
0%
31%
38%
0%
% Facilities
Where
PD<1%
25%
22%
28%
35%
50%
14%
% Facilities
Where
PD<10%
55%
78%
28%
58%
75%
14%
% Facilities
Where
PD<50%
97%
92%
37%
75%
75%
57%
% Facilities
Where
PD>50%
3%
8%
63%
25%
25%
43%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Release Estimate, and SS = Site Surveyor Release Estimate.
In Figure 5-8, the facility stack air emissions estimates are again compared to the
site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
In SIC Codes 25,281,285, and 286, facility estimates were higher than site
surveyors estimates more often than they were equal to or lower than site surveyor estimates. In
SIC Codes 26 and 30, facility estimates were equal to, greater than, and less than site surveyor
estimates in approximately equal proportions. Site surveyors often encountered facilities that did
5-27
-------
Figure 5-8. Comparison of Facility Estimates and Site Surveyor Estimates
for Stack Air Emissions
3%
29%
71%
SIC Code 281 (RY
97%
SIC Code 285 (RY 1994)
57%
43%
SIC Code 286 (RY 1995)
to
oo
10%
53%
37%
SIC Code 25 (RY 1994)
31%
32%
37%
SIC Code 30 (RY 1994)
24%
38%
38%
SIC Code 26 (RY 1995)
I Facility Estimate Equal to Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
I Facility Estimate Less Than Site Surveyor Estimate
-------
not understand the definition of stack air releases and misclassified fugitive emissions as stack
emissions. This appears to be the primary reason most of the SIC Codes surveyed showed an
inclination to overestimate stack releases.
5.1.3.3
Discharges to Receiving Streams
A comparison of the percent difference between facility estimates and site
surveyor estimates for receiving stream discharges is presented in Table 5-20. SIC Codes 25,
285, and 30 did not have any surveyed facilities with discharges to receiving streams. SIC Code
285 had two facilities which reported discharges to receiving streams. One facility overestimated
emissions by 90 percent, and the other facility underestimated emissions by 55 percent.
Table 5-20
Comparison of the Percent Difference (PD)1 Between Facility and Site
Surveyor Estimates for Discharges to Receiving Streams
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
NA
42%
NA
NA
43%
0%
%Fa««itie$
Where
HK1%
NA
73%
NA
NA
43%
0%
% Facilities
Where
H>50%
NA
13%
NA
NA
14%
100%
'PD = The absolute value of the percent Difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Release Estimate, and SS = Site Surveyor Release Estimate.
NA - Not applicable. There were no releases to receiving streams at the facilities surveyed for this SIC Code.
In Figure 5-9, the facility receiving stream release estimates are again compared to
the site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
5-29
-------
Figure 5-9. Comparison of Facility Estimates and Site Surveyor Estimates
for Receiving Streams
42%
50%
58%
50%
SIC Code 281 (RY 1994)
SIC Code 286 (RY 1995)
OJ
O
43%
43%
14%
SIC Code 26 (RY 1995)
I Facility Estimate Equal to Site
Surveyor Estimate
I Facility Estimate Less Than Site
Surveyor Estimate
I Facility Estimate Greater Than Site
Surveyor Estimate
-------
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
5.1.3.4
Underground Injection
A comparison of the percent difference between facility estimates and site
surveyor estimates for underground injection quantities is presented in Table 5-21.
Only two facilities surveyed in SIC Code 281 had releases by underground injection. The
facility estimates for these quantities is between 10% and 50% less than the site surveyor
estimates. No facilities surveyed in SIC Codes 25,26, 30, 285, or 286 had underground injection
releases.
Table 5-21
Comparison of the Percent Difference (PD)1 Between Facility and Site
Surveyor Estimates for Underground Injection
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD-0
NA
0%
NA
NA
NA
NA
% Facilities
Where
PD<1%
NA
0%
NA
NA
NA
NA
% Facilities
Where
PB50%
NA
0%
NA
NA
NA
NA
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
NA - Not applicable. There were no underground injection amounts at the facilities surveyed for this SIC Code.
5.1.3.5
Releases and Other Waste Management Quantities to Land On Site
A comparison of the percent difference between facility estimates and site
surveyor estimates for releases to land on site is presented in Table 5-22. Releases to land on-site
occurred at only one site surveyed in SIC Codes 281 and 286, and at three sites surveyed in SIC
5-31
-------
Code 26. No sites surveyed in SIC Codes 25, 30, and 285 had releases to land on-site. In Figure
5-10, the facility releases to land on-site are again compared to the site surveyor estimates, but
now the difference in facility and site surveyor estimates were equal, whether the facility
estimates were less than the site surveyor estimates, or whether the facility estimates were greater
than the site surveyor estimates.
Table 5-22
Comparison of the Percent Difference (PD)1 Between Facility and Site
Surveyor Release Estimates to Land On Site
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
NA
100%
NA
NA
33%
0%
% Facilities
Where
PD<1%
NA
100%
NA
NA
33%
0%
% Facilities
Where
PD<10%
NA
100%
NA
NA
33%
0%
% Facilities
Where
PB<50%
NA
100%
NA
NA
33%
100%
% Facilities
Where
PI>>50%
NA
0%
NA
NA
67%
0%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
NA - Not applicable. There were no releases to land on site at the facilities surveyed for this SIC Code.
5.1.3.6
Discharges to POTWs
A comparison of the percent difference between facility estimates and site
surveyor estimates for discharges to POTWs is presented in Table 5-23. The number of facilities
surveyed in SIC Codes 25, 26, 30, 281, 285, and 286 that reported discharges to a POTW are
two, zero, four, one, one, and seven, respectively.
5-32
-------
Figure 5-10. Comparison of Facility Estimates and Site Surveyor Estimates
to Land On-Site
100%
SIC Code 281 (RY1994)
100%
SIC Code 286 (RY 1995)
U)
U)
67%
33%
SIC Code 26 (RY 1995)
I Facility Estimate Equal to Site
Surveyor Estimate
I Facility Estimate Less Than Site
Surveyor Estimate
I Facility Estimate Greater Than Site
Surveyor Estimate
-------
Table 5-23
Comparison of the Percent Difference (PD)1 Between Facility and Site
Surveyor Estimates for Discharges to POTWs
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
0%
0%
0%
NA
100%
17%
% Facilities
Where
PD<1%
73%
0%
0%
NA
100%
50%
% Facilities
Where
PB<10%
73%
27%
0%
NA
100%
67%
% Facilities
Where
PD<50%
73%
65%
0%
NA
100%
83%
% Facilities
Where
W>>50%
27%
35%
100%
NA
0%
17%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
NA - Not applicable. There were no discharges to POTWs at the facilities surveyed for this SIC Code.
In Figure 5-11, the facility discharge to POTW estimates are again compared to
the site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
5.1.3.7
Off-Site Transfers for Disposal
A comparison of the percent difference between facility estimates and site
surveyor estimates for off-site transfers for disposal is presented in Table 5-24. SIC Code 285,
representing paint manufacturing facilities, had a high percentage of facilities which disagreed
with the site surveyors estimates because most facilities overlooked container residue and other
forms of off-site disposal.
5-34
-------
Figure 5-11. Comparison of Facility Estimates and Site Surveyor Estimates
for Discharges to POTWs
35%
65%
SIC Code 281 (RY
27%
33%
100%
SIC Code 285 (RY 1994)
17%
73%
SIC Code 25 (RY 1994)
50%
SIC Code 286 (RY 1995)
Facility Estimate Equal to Site
Surveyor Estimate
Facility Estimate Less Than Site
Surveyor Estimate
Facility Estimate Greater Than Site
Surveyor Estimate
-------
Table 5-24
Comparison of the Percent Difference (PD)1 Between Facility Transfer
Estimates and Site Surveyor Transfer Estimates for Off-Site Disposal
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
NA
15%
0%
0%
50%
50%
% Facilities
Where
PD<1%
NA
78%
0%
0%
100%
50%
% Facilities
Where
PD<10%
NA
78%
0%
0%
100%
100%
% FacUities
Where
PD«50%
NA
100%
4%
59%
100%
100%
% Facilities
Where
FD>50%
NA
0%
96%
41%
0%
0%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
NA - Not applicable. There were no off-site transfers for disposal at the facilities surveyed for this SIC Code.
In Figure 5-12, the facility off-site transfers for disposal estimates are again
compared to the site surveyor estimates, but now the difference in facility and site surveyor
estimates are classified according to whether the facility and the site surveyor estimates were
equal, whether the facility estimates were less than the site surveyor estimates, or whether the
facility estimates were greater than the site surveyor estimates.
5.1.3.8
Off-Site Transfers for Treatment
A comparison of the percent difference between facility estimates and site
surveyor estimates for off-site transfers for treatment is presented in Table 5-25. SIC Code 285,
representing paint manufacturing facilities, had a total of two facilities with off-site transfers for
treatment. These facilities overlooked many of these transfers. Container residue and bad
process batches made up the bulk of off-site treatment transfers. As shown in Table 5-21, these
two facility estimates were greater than 50% different than the site surveyor estimate. SIC Code
25, representing furniture manufacturing facilities, had three facilities which reported off-site
transfers for treatment. These transfers were mainly disposed or recycled by off-site vendors
5-36
-------
Figure 5-12. Comparison of Facility Estimates and Site Surveyor Estimates
for Transfers Off-Site for Disposal
15%
39%
46%
SIC Code 281 (RY
96%
SIC Code 285 (RY 1994)
50%
50%
SIC Code 286 (RY 1995)
41%
50%
59%
50%
SIC Code 30 (RY 1994)
SIC Code 26 (RY 1995)
I Facility Estimate Equal to Site Surveyor Estimate g Facility Estimate Less Than Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
-------
instead of treated. Therefore, these facility estimates were greater than 50% different than the
site surveyors estimates.
Table 5-25
Comparison of the Percent Difference (PD)1 Between Facility Transfer
Estimates and Site Surveyor Transfer Estimates for Off-Site Treatment
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD-0
0%
22%
0%
24%
NA
40%
% Facilities
Where
PD<1%
0%
38%
0%
27%
NA
80%
% Facilities
Where
PD<10%
0%
65%
0%
35%
NA
100%
% Facilities
Where
PD<50%
0%
65%
0%
73%
NA
100%
% Facilities
Where
PD>50%
100%
35%
100%
27%
NA
0%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
In Figure 5-13, the facility off-site transfers for treatment estimates are again
compared to the site surveyor estimates, but now the difference in facility and site surveyor
estimates are classified according to whether the facility and the site surveyor estimates were
equal, whether the facility estimates were less than the site surveyor estimates, or whether the
facility estimates were greater than the site surveyor estimates.
5.1.3.9
Off-Site Transfers for Recycling
A comparison of the percent difference between facility estimates and site
surveyor estimates for off-site transfers for recycling is presented in Table 5-26.
5-38
-------
Figure 5-13. Comparison of Facility Estimates and Site Surveyor Estimates
for Transfers Off-Site for Treatment
56%
22%
2%
SIC Code 281 (RY
20%
40%
100%
SIC Code 285 (RY 1994)
40%
SIC Code 286 (RY 1995)
24%
100%
SIC Code 25 (RY 1994)
76%
SIC Code 30 (RY 1994)
I Facility Estimate Equal to Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
I Facility Estimate Less Than Site Surveyor Estimate
-------
Table 5-26
Comparison of the Percent Difference (PD)1 Between Facility Transfer
Estimates and Site Surveyor Transfer Estimates for Off-Site Recycling
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
3%
0%
0%
0%
NA
100%
% Facilities
Where
PD<1%
3%
0%
8%
0%
NA
100%
% Facilities
Where
PD<10%
50%
0%
24%
0%
NA
100%
% Facilities
Where
PD<50%
84%
100%
62%
100%
NA
100%
% Facilities
Where
PD>50%
16%
0%
38%
0%
NA
0%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
In Figure 5-14, the facility off-site transfers for recycling estimates are again
compared to the site surveyor estimates, but now the difference in facility and site surveyor
estimates are classified according to whether the facility and the site surveyor estimates were
equal, whether the facility estimates were less than the site surveyor estimates, or whether the
facility estimates were greater than the site surveyor estimates. There is a general tendency
among SIC Codes 25, 281, and 285 for facility estimates to be less than site surveyor estimates.
Facilities in these SIC Codes tend to overlook solvent remaining in container residue that can be
recycled by some off-site vendors.
5-40
-------
Figure 5-14. Comparison of Facility Estimates and Site Surveyor Estimates
for Off-Site Recycling
24%
100%
SIC Code 281 (RY 1994)
76%
SIC Code 285 (RY 1994)
16%
52%
81%
SIC Code 25 {RY 1994)
48%
SIC Code 30 (RY 1994)
I Facility Estimate Equal to Site
Surveyor Estimate
I Facility Estimate Less Than Site
Surveyor Estimate
I Facility Estimate Greater Than Site
Surveyor Estimate
-------
5.1.3.10
Off-Site Transfers for Energy Recovery
A comparison of the percent difference between facility estimates and site
surveyor estimates for off-site transfers for energy recovery is presented in Table 5-27.
Table 5-27
Comparison of the Percent Difference (PD)1 Between
Facility Transfer Estimates and Site Surveyor
Transfer Estimates for Off-Site Energy Recovery
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
20%
0%
0%
0%
NA
40%
% Facilities
Where
PD<1%
39%
0%
0%
0%
NA
40%
% Facilities
Where
PD<10%
59%
0%
34%
100%
NA
80%
% FacUities
Where
PD<50%
77%
0%
100%
100%
NA
100%
% Facilities
Where
PD>50%
23%
100%
0%
0%
NA
0%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
In Figure 5-15, the facility off-site transfers for energy recovery estimates are
again compared to the site surveyor estimates, but now the difference in facility and site surveyor
estimates are classified according to whether the facility and the site surveyor estimates were
equal, whether the facility estimates were less than the site surveyor estimates, or whether the
facility estimates were greater than the site surveyor estimates. Over half the facilities in SIC
Codes 25, 30, 281, and 286 had off-site transfer for energy recovery estimates less than the site
surveyor estimates.
5-42
-------
Figure 5-15. Comparison of Facility Estimates and Site Surveyor Estimates
for Off-Site Energy Recovery
34%
21%
66%
40%
79%
60%
SIC Code 281 (RY
SIC Code 285 (RY 1994)
SIC Code 286 (RY 1995)
19%
20%
61%
SIC Code 25 (RY 1994)
100%
SIC Code 30 (RY 1994)
I Facility Estimate Equal to Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
I Facility Estimate Less Than Site Surveyor Estimate
-------
5.2 On-Site Waste Management Activities
5.2.1 On-Site Waste Management Activities by SIC Code
On-site waste management activity quantities as reported by the facilities and the
site surveyors were summed for all chemicals to get total facility on-site waste management
activity quantities. Total facility on-site activity quantities were scaled and summed for all
facilities to get total on-site activity quantities for each SIC Code. The total on-site activity
quantities for SIC Codes are presented by activity in Tables 5-28 through 5-33. In general,
facility and site surveyor estimates showed better agreement for on-site treatment than on-site
recycling for each SIC Code.
Facilities in SIC Code 286 tend to be much larger than those in the other SIC
Codes surveyed. The process operations performed in these facilities and the many uses for
solvents in these processes create many opportunities for on-site recycling, treatment, and energy
recovery, as shown by the large amount of chemicals in Table 5-33.
5-44
-------
Table 5-28
Summary of SIC Code 25 TRI On-Site Waste Management Activity
Quantities for RY1994 (millions of Ibs.)
On-Site Waste
Management Activity
Recycling
Treatment
Energy Recovery
Quantity of Chemicals as
Reported by the Facilities
2.36
5.54
0.00
Quantity of Chemicals as
Reported by the Site
Surveyors
3.23
5.26
0.00
Percent Difference*
-27%
5.3%
NA
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
Table 5-29
Summary of SIC Code 281 TRI On-Site Waste Management Activity
Quantities for RY 1994 (millions of Ibs.)
On-Site Waste
Management Activity
Recycling
Treatment
Energy Recovery
Quantity of Chemicals as
Reported by the Facilities
332
79.7
0.00
Quantity of Chemicals as
Reported by tbe Site
Surveyors
328
78.9
0.00
Percent Difference*
1.2%
1.0%
NA
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
5-45
-------
Table 5-30
Summary of SIC Code 285 TRI Oil-Site Waste Management Activity
Quantities for RY 1994 (millions of Ibs.)
On-Site Waste
Management Activity
Recycling
Treatment
Energy Recovery
Quantity of Chemicals as
Reported fay the Facilities
3.48
0.00
0.00
Quantity of Chemicals as
Reported by the Site
Surveyors
2.95
0.00
0.00
Percent Difference*
18%
NA
NA
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
Table 5-31
Summary of SIC Code 30 TRI On-Site Waste Management Activity
Quantities for RY 1994 (millions of Ibs.)
On-Site Waste
Management Activity
Recycling
Treatment
Energy Recovery
Quantity of Chemicals as
Reported by the Facilities
160
32.6
0.00
Quantity of Chemicals as
Reported by the Site
Surveyors
160
33.1
0.00
Percent Difference*
-0.09%
-1.36%
NA
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
5-46
-------
Table 5-32
Summary of SIC Code 26 TRI On-Site Waste Management Activity
Quantities for Reporting Year 1995 (millions of Ibs.)
On-Site Waste
Management Activity
Recycling
Treatment
Energy Recovery
Quantity of Chemicals as
Reported by the Facilities
0
258
65.6
Quantity of Chemicals as
Reported by the Site
Surveyors
0
287
75.9
Percent Difference*
NA
-10%
-14%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
Table 5-33
Summary of SIC Code 286 TRI On-Site Waste Management Activity
Quantities for Reporting Year 1995 (millions of Ibs.)
On-Site Waste
Management Activity
Recycling
Treatment
Energy Recovery
Quantity of Chemicals as
Reported by the Facilities
702
144
222
Quantity of Chemicals as
Reported by the Site
Surveyors
3,821
223
222
Percent Difference*
-82%
-35%
0.0%
*Percent Difference = (Fa-SS)/SS x 100, where Fa = Facility Estimate and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
The large percent difference in on-site recycling activities in SIC Code 286 is due
to one facility misreporting recycling activities. If this facility was excluded from the analysis,
the percent difference would be less than 1%.
5-47
-------
5.2.2
Oil-Site Recycling
A comparison of the percent difference between facility estimates and site
surveyor estimates for on-site recycling is presented in Table 5-34. SIC Codes 281 and 30 had
the best agreement between facility on-site recycling estimates and site surveyor on-site
recycling estimates.
Table 5-34
Comparison of the Percent Difference (PD)1 Between Facility On-Site
Recycling Estimates and Site Surveyor On-Site Recycling Estimates
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
49%
49%
0%
21%
NA
60%
% Facilities
Where
PD<1%
49%
49%
3%
100%
NA
80%
% Facilities
Where
PD<10%
49%
87%
3%
100%
NA
80%
% Facilities
Where
PD<50%
80%
100%
100%
100%
NA
80%
% Facilities
Where
PD>50%
20%
0%
0%
0%
NA
20%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
In Figure 5-16, the facility on-site recycling estimates are again compared to the
site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
5-48
-------
Figure 5-16. Comparison of Facility Estimates and Site Surveyor Estimates
for On-Site Recycling
29%
49%
22%
SIC Code 281 (RY 1994)
20%
20%
60%
20%
80%
SIC Code 285 (RY 1994)
SIC Code 286 (RY 1995)
21%
51%
79%
SIC Code 25 (RY 1994)
SIC Code 30 (RY 1994)
I Facility Estimate Equal to Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
I Facility Estimate Less Than Site Surveyor Estimate
-------
5.2.3
On-Site Treatment
A comparison of the percent difference between facility estimates and site
surveyor estimates for on-site treatment is presented in Table 5-35.
Table 5-35
Comparison of the Percent Difference (PD)1 Between Facility On-Site
Treatment Estimates and Site Surveyor On-Site Treatment Estimates
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
0%
54%
100%
0%
13%
20%
% Facilities
Where
PEK1%
0%
63%
100%
0%
25%
80%
% Facilities
Where
PD<10%
100%
100%
100%
100%
38%
80%
% Facilities
Where
PD<50%
100%
100%
100%
100%
63%
80%
% Facilities
Where
PD>50%
0%
0%
0%
0%
37%
20%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
In Figure 5-17, the facility on-site treatment estimates are again compared to the
site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
5.2.4
On-Site Energy Recovery
A comparison of the percent difference between facility estimates and site
surveyor estimates for on-site energy recovery is presented in Table 5-36. Only six facilities
surveyed in SIC Code 281, 286, and 26 performed on-site energy recovery. All facility
5-50
-------
Figure 5-17. Comparison of Facility Estimates and Site Surveyor Estimates
for On-Site Treatment
20%
55%
12%
25%
SIC Code 281 (RY
100%
SIC Code 285 (RY 1994)
25%
63%
SIC Code 286 (RY 1995)
20%
20%
100%
SIC Code 25 (RY 1994)
100%
SIC Code 30 (RY 1994)
60%
SIC Code 26 (RY 1995)
I Facility Estimate Equal to Site Surveyor Estimate
I Facility Estimate Greater Than Site Surveyor Estimate
I Facility Estimate Less Than Site Surveyor Estimate
-------
estimates were equal to the site surveyor estimates except for one facility in SIC Code 26. No
facilities surveyed in SIC Codes 25, 285, or 30 performed on-site energy recovery.
Table 5-36
Comparison of the Percent Difference (PD)1 Between
Facility On-Site Energy Recovery Estimates and
Site Surveyor On-Site Energy Recovery Estimates
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
% Facilities
Where
PD=0
NA
100%
NA
NA
75%
100%
% Facilities
Where
PD<1%
NA
100%
NA
NA
75%
100%
% Facilities
Where
PD<10%
NA
100%
NA
NA
75%
100%
% Facilities
Where
PD<50%
NA
100%
NA
NA
100%
100%
% Facilities
Where
PD>50%
NA
0%
NA
NA
0%
0%
'PD = The absolute value of the percent difference, where percent difference = (Fa - SS)/SS x 100, Fa = Facility
Estimate, and SS = Site Surveyor Estimate.
NA - Not applicable. There were no on-site activities of this kind at the facilities surveyed in this SIC Code.
In Figure 5-18, the facility on-site energy recovery estimates are again compared
to the site surveyor estimates, but now the difference in facility and site surveyor estimates are
classified according to whether the facility and the site surveyor estimates were equal, whether
the facility estimates were less than the site surveyor estimates, or whether the facility estimates
were greater than the site surveyor estimates.
5-52
-------
Figure 5-18. Comparison of Facility Estimates and Site Surveyor Estimates
for On-Site Energy Recovery
100%
SIC Code 281 (RY 1994}
100%
SIC Code 286 (RY 1995)
U)
25%
75%
SIC Code 26 (RY 1995)
Facility Estimate Equal to Site
Surveyor Estimate
Facility Estimate Less Than Site
Surveyor Estimate
Facility Estimate Greater Than Site
Surveyor Estimate
-------
5.3 Production Ratio/Activity Index
The production ratio/activity index is a pollutant specific measure that relates the
changes in business activity between subsequent reporting years. The production ratio/activity
index can be estimated using several methods. The methods are presented below:
TCM - the ratio of the amount of the chemical manufactured in the current
reporting year to the previous reporting year;
TCPV - the ratio of production volume in the current reporting year to the
previous reporting year;
TCU - an activity index of the amount of the toxic chemical used in the current
reporting year to the previous reporting year;
HR - an activity index of the amount of operating hours for an activity in the
current reporting year to the previous reporting year;
WT - an activity index or production ratio based on a weighted average of data
from several processes; and
OTH - any other estimation method.
Figure 5-19 and Table 5-37 present the distribution of use for each method that
was reported by the facilities, by SIC Code. Site surveyors reviewed the method used by each
facility to determine whether it was the most appropriate. Table 5-38 presents the frequency that
site surveyor's agreed with the facility's choice of method. As shown on the table, facilities
which used a method not listed (as noted by the "other" category), could have used a better
method to determine the production ratio. Table 5-39 presents the distribution of the most
appropriate method as observed by site surveyors.
As shown on Table 5-38, the site surveyor disagreed most often with the "other"
basis of estimate. Most production ratios can be accurately accounted for using the amount of
chemical manufactured or used from one year to the next, or the change in production volume.
Facilities would have more accurate activity indices if one of these three bases was used for ratio
estimation.
5-54
-------
Table 5-37
Method of Estimate Used by Facilities to Calculate
Production Ratio
SIC Code
25 (RY 1994)
.281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
Percent of
FacUitles
Using TCM
0%
5.4%
2.9%
0%
4.8%
19.6%
Percent of
Facilities
Using TCPV
52.1%
53.6%
67.7%
14.9%
78.6%
57.4%
Percent of
Facilities
Using TCU
4.8%
31.7%
14.0%
52.3%
9.5%
11.5%
Percent of
Facilities
Using HR
21.5%
0.0%
0%
0%
0%
1.6%
Percent of
Facilities
Using WT
0%
0%
0%
5.7%
4.7%
6.6%
Percent of
Facilities
Using OTH
21.6%
9.3%
15.4%
27.1%
2.4%
3.3%
TCM - the ratio of the amount of the chemical manufactured in the current reporting year to the previous reporting year.
TCPV - the ratio of production volume in the current reporting year to the previous reporting year.
TCU - an activity index of the amount of the toxic chemical used in the current reporting year to the previous reporting year.
HR - an activity index of the amount of operating hours for an activity in the current reporting year to the previous reporting year.
WT - an activity index or production ratio based on a weighted average of data from several processes.
OTH - any other estimation method.
5-55
-------
Figure 5-19. Method of Estimate used by Facilities to Calculate PR/AI
1.0%
9-2% 5.3%
15.4%
2.9%
14.0%
31.4%
53.1%
SIC Code 281 (RY 1994)
52.1%
27%
21.
4.8%
1.6%
6.6%
3.3%
19.6%
11.5%
67.7%
SIC Code 285 (RY 1994)
15%
52%
SIC Code 25 (RY 1994)
SIC Code 30 (RY 1994)
SIC Code 286 (RY 1995)
4.7%2.4% 4.8%
9.5%
.6%
SIC Code 26 (RY 1995)
The data for this Figure is shown in Table 5-37.
]TCM i|TCPV i)TCU
IHR • WT «OTH
-------
Table 5-38
Percent of Time Surveyor Agreed with Facility Basis of
Production Ratio Estimate
SIC Code
25 (RY 1994)
25 (RY 1994)
25 (RY 1994)
25 (RY 1994)
281 (RY 1994)
281 (RY 1994)
281 (RY 1994)
281 (RY 1994)
281 (RY 1994)
285 (RY 1994)
285 (RY 1994)
285 (RY 1994)
285 (RY 1994)
30 (RY 1994)
30 (RY 1994)
30 (RY 1994)
30 (RY 1994)
26 (RY 1995)
26 (RY 1995)
26 (RY 1995)
26 (RY 1995)
26 (RY 1995)
Facility Basis of Estimate
TCPV
TCU
HR
OTH
TCM
TCPV
TCU
HR
OTH
TCM
TCPV
TCU
OTH
TCPV
TCU
WT
OTH
TCM
TCPV
TCU
WT
OTH
Percent of Time Surveyor
Agreed with Basis
61%
100%
100%
51%
100%
99%
100%
100%
15%
100%
100%
100%
0%
89%
100%
0%
48%
100%
91%
100%
100%
0%
5-57
-------
Table 5-38 (Continued)
Percent of Time Surveyor Agreed with Facility Basis of
Production Ratio Estimate
SIC Code
286 (RY 1995)
286 (RY 1995)
286 (RY 1995)
286 (RY 1995)
286 (RY 1995)
286 (RY 1995)
Facility Basis of Estimate
TCM
TCPV
TCU
HR
WT
OTH
Percent of Time Surveyor
Agreed with Basis
100%
100%
100%
0%
100%
50%
TCM - the ratio of the amount of the chemical manufactured in the current reporting year to the previous reporting year.
TCPV - the ratio of production volume in the current reporting year to the previous reporting year.
TCU - an activity index of the amount of the toxic chemical used in the current reporting year to the previous reporting year.
HR - an activity index of the amount of operating hours for an activity in the current reporting year to the previous reporting year.
WT - an activity index or production ratio based on a weighted average of data from several processes.
OTH - any other estimation method.
Table 5-39
Method of Estimate That Should Have been Used by Facilities to
Calculate Production Ratio
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
Percent of
Facilities
that Should
Use TCM
0%
5.8%
2.9%
0%
7.0%
19.4%
Percent of
Facilities
that Should
Use TCPV
31.7%
53.2%
83.1%
13.3%
72.0%
58.0%
Percent of
Facilities
that Should
Use TCU
31.0%
39.5%
14.0%
73.6%
16.3%
14.5%
Percent of
Facilities
that Should
UseHR
21.5%
0.0%
0%
0%
0%
0%
Percent of
Facilities
that Should
UseWT
4.8%
0%
0%
0%
0%
0%
Percent of
Facilities that
Should Use
OTH
11.0%
1.5%
0%
13.1%
0%
1.6%
TCM - the ratio of the amount of the chemical manufactured in the current reporting year to the previous reporting year.
TCPV - the ratio of production volume in the current reporting year to the previous reporting year.
TCU - an activity index of the amount of the toxic chemical used in the current reporting year to the previous reporting year.
HR - an activity index of the amount of operating hours for an activity in the current reporting year to the previous reporting year.
WT - an activity index or production ratio based on a weighted average of data from several processes.
OTH - any other estimation method.
5-58
-------
5.4 Source Reduction Activities
The following discussion reviews how accurately facilities indicate source
reduction activities on Form Rs. Starting in reporting year 1991, EPA required facilities to
include on their Form R reports information describing source reduction activities that were
implemented to reduce the quantity of Section 313 chemicals in waste. This information offers
users of the data insight into how often industrial facilities reduce pollution at the sources. To
assess the accuracy of source reduction entries in the TRI database, analyses in this section
address three questions:
• Are the source reduction activities that facilities indicate on Form Rs
legitimate?
• Why do facilities make errors when claiming source reduction?
• Do facilities consistently report source reduction activities on Form Rs?
It should be noted that this section focuses only on source reduction activities that
facilities indicate on "Form Rs." Form As do not include fields for reporting source reduction.
5.4.1 Errors in Classifying Source Reduction
To identify errors commonly made by facilities and reasons why facilities made
these errors, site surveyors determined during each visit whether facilities indicate source
reduction activities that were consistent with definitions of source reduction presented in the
EPCRA Section 313 reporting instructions. In cases where facilities did not claim source
reduction activities, site surveyors generally did not determine whether facilities overlooked
source reduction activities. Accordingly, the most recent site survey data are sufficient for
evaluating whether source reduction activities currently loaded in the TRI database are
legitimate, but the data are not sufficient for determining the total number of source reduction
activities that should have been reported.
5-59
-------
Table 5-40 summarizes how often source reduction activities were used on
EPCRA Section 313 chemicals and how often these claims were made in error. For reference,
Table 5-41 indicates the source reduction activities most commonly used on EPCRA Section 313
chemicals in the selected SIC Codes. The data in these tables suggest that facilities in the
furniture manufacturing industry (SIC Code 25), organic chemicals industry (SIC Code 286) and
plastics manufacturing industry (SIC Code 30) claim source reduction much more frequently
than facilities in the inorganic chemical manufacturing industry (SIC Code 281), paper industry
(SIC Code 26), and paint manufacturing industry (SIC Code 285). Modifications to spray
application and surface coating processes account for a majority of the source reduction activities
claimed by furniture manufacturers. Employee training and improved maintenance account for a
majority of the source reduction activities claimed by organic chemical manufacturers. No
specific group of source reduction activities were as prevalent for the other industries.
The data also indicate that, of the source reduction activities claimed by rubber
and plastic manufacturing facilities, nearly three fourths were claimed in error. Many rubber and
plastic manufacturing facilities claimed that a reduction in the number of toxic chemical supplies
was source reduction even though the reduction in suppliers did not decrease the amount of toxic
chemicals purchased or used. The frequency of errors was notably lower for furniture
manufacturers and inorganic chemical manufacturers, and no errors were identified in the source
reduction activities claimed by paint manufacturers, organic chemical manufacturers, and
paperboard facilities.
5.4.2 Sources of Errors Made When Claiming Source Reduction
Specific reasons for erroneously classifying source reduction activities differ from
one facility to the next. In general, however, most errors resulted from facilities not
understanding exactly what activities constitute source reduction. Site surveyors noted several
examples supporting this hypothesis:
5-60
-------
Table 5-40
Errors in Source Reduction Activity Classifications
Reporting
Year
1994
1995
SIC
Code
25
281
285
30
26
286
Frequency with which facilities claim source
reduction activities
Total number of source
reduction activities
claimed by the selected
facilities
48
24
30
21
3
36
Estimated percent of
Form Rs submitted by
facilities in SIC Code
with source reduction
claimed3
33%
14%
21%
32%
5.9%
30.1%
Frequency with which facilities make errors when
claiming source reduction
Number of source
reduction activities
claimed in error by the
selected facilities
8
6
0
14
0
0
Estimated percent of
source reduction
activities that are
claimed, but in error8
27%
22%
0%
78%
0%
0%
1 Percents in this column were calculated using the weighting factors discussed in Section 2.6.3.
-------
Table 5-41
Most Common Source Reduction Activities
Claimed by the Selected Facilities
SIC
Code
25
281
285
30
26
286
Source
Reduction
Code
W72
W73
W74
W39
7 others
W21
6 others
W25
W39
W82
W52
3 others
W42
W13
W39
W14
W52
5 others
W32
W58
W13
5 others
W36
W51
W19
Description
Modified spray systems for coating applications
Substituted materials used for coating applications
Improved application techniques for surface coating
Miscellaneous spill and leak prevention
Many different descriptions
Ensuring materials are used before reaching their shelf-life
Many different descriptions
Instituted programs to exchange unwanted materials
Miscellaneous spill and leak prevention
Modified composition of products
Modified equipment, layout, or piping
Many different descriptions
Substituted raw materials
Improved maintenance scheduling and recordkeeping
Miscellaneous spill and leak prevention
Changed production schedule to minimize changeovers
Modified process equipment, layout, or piping
Many different descriptions
Improved practices for loading and unloading chemicals
Process modifications
Employee training and improved maintenance
Many different descriptions
Spill and leak detection program
Recirculation within processes
Reuse of materials
Percent of Chemicals
at Selected Facilities
that used this Code
16.9%
10.0%
9.5%
9.0%
8.5%
0.5%
6.2%
4.0%
4.0%
4.0%
3.0%
13.3%
10.9%
7.1%
7.1%
5.5%
5.5%
12.6%
0.7%
5.9%
23.3%
9.6%
5.5%
5.5%
5.5%
5-62
-------
• An organic chemical manufacturing facility installed a new pollution
control mechanism to remove ammonia from a waste stream. The facility
considered the new device as source reduction, but the site surveyor noted
that the facility already accounted for the new device as "treatment" and
should not have claimed the device as source reduction.
• Due to decreased demand for a particular product, a paint manufacturing
facility purchased less of a glycol ether solvent. The facility claimed this
reduced usage of raw materials as source reduction, but the site surveyor
did not consider decline in production demand as source reduction.
• A furniture manufacturing facility claimed source reduction after installing
a new software system to track purchases of Section 313 chemicals.
Although this system helped the facility make more accurate threshold
determinations, the site surveyor noted that the software did not reduce
amounts of hazardous chemicals that were purchased. Therefore, the site
surveyor concluded that installing the new software was not source
reduction.
Because errors in claiming source reduction resulted primarily from facilities
misinterpreting definitions, EPA can help minimize similar errors in future reporting years by
preparing revised reporting instructions that clarify which activities should, and should not, be
classified as source reduction.
5.4.3 Feedback from Facilities
The accuracy of source reduction data depends to a great extent on how facilities
choose to implement the reporting requirements. Although the survey instrument did not include
explicit fields for documenting feedback from facilities regarding source reduction, site
surveyors noted several relevant comments made by facility contacts:
Some facilities noted that source reduction codes do not inform those who
access TRI data of the extent to which emissions are reduced by source
reduction. These facilities, therefore, saw little benefit from claiming
source reduction activities on their Form Rs.
Some facilities found the list of source reduction codes cumbersome,
noting that the list contains too many codes or that definitions of specific
codes are too vague.
5-63
-------
• Some facilities chose to not claim on their Form Rs legitimate source
reduction activities because the activities caused only marginal reductions
in overall releases.
• Facilities seem confused about whether source reduction activities should
be reported only for the first year in which they were implemented or for
every year thereafter. This confusion leads to inconsistent reporting
practices among the facilities that claim source reduction. This confusion
stems from discrepancies in Agency guidance. The agency guidance
document states that source reduction activities should be reported only in
the first year of implementation while the Pollution Prevention Act states
that each annual report will identify the source reduction practices used
with respect to each chemical for which the report is submitted.
These comments from facilities stress that, for a variety of reasons, facilities often
choose to not report legitimate source reduction activities. Therefore, the total number of source
reduction activities currently logged in the TRI database may understate the extent of pollution
prevention efforts adopted by industrial facilities.
5.4.4 Overall Accuracy of Source Reduction Data
Site surveyors found that facilities in the selected industries frequently
misinterpreted definitions of source reduction and should not have claimed roughly 30 percent of
all source reduction activities reported to TRI in 1994 and 1995. Observations made by site
surveyors and feedback provided by facilities both suggest that many facilities did not claim
legitimate source reduction activities on their Form Rs, but the current site survey data are
insufficient for evaluating how often this occurs. Accordingly, the quality of source reduction
data in the TRI database is compromised by omissions and erroneous submissions of source
reduction information, and TRI data, therefore, may not be an accurate measure of the extent of
pollution prevention efforts for many industries.
Because the primary cause of errors in reporting source reduction seems to be due
to facilities misinterpreting definitions, EPA can help improve the accuracy of source reduction
data by preparing TRI reporting instructions that clearly define which activities are, and are not,
considered to be source reduction.
5-64
-------
6.0 PREPARATION OF THE FORM R
Site surveyors interviewed facility personnel during each site visit to obtain
general information regarding completion of the Form R reports and to identify trends among the
surveyed facilities. The information obtained during these interviews included quantitative
information such as facility size (the number of employees at the facility), time to complete Form
Rs, the types of personnel primarily responsible for preparing the Form R reports, and the types
of references used by these personnel. In addition, qualitative feedback was obtained on the
Form R Instructions, the Automated Form R (AFR), the TRI Hotline, use of the Form A
beginning in RY 1995, and suggestions for additional guidance that EPA should develop to assist
facilities in release and other waste management quantities estimation and Form R preparation.
6.1 Facility Personnel and References
Table 6-1 identifies the percentage of facilities visited in a particular size range (based on number
of employees) for each SIC Code group. As can be seen from the table, most of the inorganic
chemical and paint manufacturing facilities had fewer than 50 employees, while the furniture,
paper, organic chemicals, and plastics related industries had between 50-499 employees on
average. In general, the size of the facilities visited for the RY 1994 and RY 1995 analysis were
smaller than those visited in the RY 1987 and RY 1988 site visits.
Table 6-2 lists the types of personnel identified by the facility as being primarily
responsible for preparing the Form R reports for each SIC Code group included in this analysis.
As can be seen on the table, facility and corporate environmental staff most often completed the
reports for each of the source categories visited. A brief description of each staff type identified
in the table follows:
Facility Environmental - In most cases, this is a full-time position for an
on-site employee whose primary responsibility is dealing with
environmental issues.
6-1
-------
Corporate Environmental - This person would have environmentally-
related responsibilities for more than one individual facility and may or
may not be physically located at the facility.
Facility Staff- This is an employee whose responsibilities extend beyond
the environmental arena. This staff type was primarily found to be
preparing the Form R reports at facilities that had fewer than 50
employees.
Consultant/Contractor - This includes personnel contracted outside the
company to prepare the facility's Form R report.
Safety Personnel - This staff type is similar to Facility Environmental.
This person may have responsibilities including complying with
Environmental Health and Safety issues as well.
Other - This is anyone who filled out the Form R that does not belong to
one of the previously described staff types.
Table 6-1
Number of Employees at Visited Facilities
Percentage of Facilities with a given Number of Employees"
Employee
Range
10-49 employees
50-499
employees
>500 employees
RY 1987
SIC
Code
20-39
17
62
21
RY 1988
SIC
Code
28, 291
45
48
7
SIC
Code
34-38
7
42
51
RY1994
SIC
Code
25
4
82
14
SIC
Code
281
77
23
0
SIC
Code
285
61
39
0
SIC
Code
30
19
81
0
RY 1995
SIC
Code
26
0
70
30
SIC
Code
286
40
60
0
"The 1987 and 1988 data are raw percentages of the facilities actually surveyed and are not scaled up to represent the entire SIC Code. The
1994 and 1995 data are scaled data which are weighted to represent the entire SIC Code.
6-2
-------
Table 6-2
Types of Personnel Completing the Form R
Percentage of Facilities using a Particular Staff Type to Prepare their form &•
Staff Type
Facility Environmental
Corporate Environmental
Facility Staff
Consultant/Contractor
Safety Personnel
Other
3987
SIC
Code
20-39
47
29
11
10
2
1
1988
SIC
Code
28, 291
29
28
37
1
5
0.00
SIC
Code
34-58
38
11
21
15
15
0.00
1994
SIC
Code
25
31
31
25
12
8
0.00
SIC
Code
281
53
17
38
12
14
6
SIC
Code
285
24
25
67
18
1
8
SIC
Code
30
43
14
36
13
9
0.00
199S
SIC
Code
2$
80
10
10
0
0
0
SIC
Code
28$
60
0
50
0
0
0
Totals may equal more than 100 percent due to facility personnel identifying themselves as more than one staff type. The 1987 data are raw
percentages of the facilities actually surveyed and are not scaled up to represent the entire SIC Code. The 1988,1994, and 1995 data are scaled
data which are weighted to represent the entire SIC Code.
Table 6-3, Figure 6-1, and Figure 6-2 identify the references most commonly used
by facilities to prepare their Form R reports. As can be seen on Table 6-3, more than 90 percent
of the facilities visited used the TRI Reporting Form R instructions for RY 1994 and RY 1995 as
compared to less than half who used the reference for preparing their RY 1988 Form R reports.
In addition, a higher percentage of facilities are now using Trade Association Materials, Privately
Sponsored Seminar Materials, computer programs, and EPA Sponsored Training Workshops
than were used in the past. SIC Code 26, sampled for RY 1995, relies heavily on guidance from
NCASI, a pulp and paper research organization, in completing Form Rs and documenting release
calculations. EPA Sponsored Training Workshops have also contributed to increased use of
EPA's compilation of air pollutant emission factors document, AP-42. The increased use in
workshop or other training materials and computer programs is due to the greater availability of
such resources than were available in the past.
6-3
-------
Table 6-3
Common References Used to Compile the Form Rs
Percentage of Facilities using a Particular Reference*
Reference
TRI Reporting Form R
Instructions
The Emergency Planning and
Community Right-to Know
Act, Section 3 13
Estimating Releases and
Waste Treatment Efficiencies
for TRI
EPCRA Section 313 Release
Reporting Guidance,
Estimating Chemical
Releases
Compilation of Air Pollution
Emission Factors, AP-42
Toxic Chemical Release
Reporting Proposed Rule, 52
FR 21152, June 4, 1987
Industry Trade Association
Materials
Privately Sponsored Seminar
Materials
EPA Sponsored Training
Workshop
Computer Programs
1987
SIC
Code
20-39
90
26
24
15
11
10
10
9
N/A
N/A
1988
SIC
Code
28, 291
44
9
17
0
12
3
10
5
N/A
3
SIC
Code
34-38
44
13
9
8
3
7
9
7
N/A
3
1994
SIC
Code
25
91
N/A
22
10
15
N/A
12
16
13
30
SIC
Code
281
93
N/A
8
9
17
N/A
13
7
32
23
SIC
Code
285
96
N/A
22
1
33
N/A
24
26
27
15
SIC
Code
30
100
N/A
11
0
5
N/A
9
7
38
39
1995
SIC
Code
26
90
N/A
20
10
20
N/A
90
0
20
40
SIC
Code
286
100
N/A
10
10
60
N/A
20
10
10
40
"Totals may equal more than 100% as facilities often used more than one reference. The 1987 data are raw percentages of the facilities actually
surveyed and are not scaled up to represent the entire SIC Code. The 1988, 1994, and 1995 data are scaled data which are weighted to
represent the entire SIC Code N/A means the reference was not listed in the questionnaire in this reporting year and was not specifically listed
by any of the facilities.
6-4
-------
S-9
t
§
I
S1
Q.
O
I
05
CO
Form R Instructions
Estimating Releases and Waste Treatment
Efficiencies for the Toxic Chemical Release
Inventory Form
EPCRA Section 313 Release Reporting Guidance,
a through q, Estimating Chemical Releases
AP-42
Trade Association Guidance
Privately Sponsored Seminar Materials
Computer Programs
The Emergency Planning and Community
Right-to-Know Act, Section 313
Toxic Chemical Release Reporting Proposed
Rule, 52 FR 21152, June 4, 1987
I
o
•< 3
£ 3
(O
I
O)
o
o
3
o
•3
7J
CD
§
O
CD
(A
CD
a
O
o
•D_
cb~
•n
o
>
31
00
-J
fl)
3
a.
3
oo
oo
-------
9-9
o
OJ
3
I
CL
§
5-
o>
CO
Form R Instructions
Estimating Releases and Waste Treatment
Efficiencies tor the Toxic Chemical Release
Inventory Form
Title III Section 313 Release Reporting Guidance,
a through q, Estimating Chemical Releases
AP-42
Trade Association Guidance
Privately Sponsored Seminar Materials
Computer Programs
EPA Sponsored Training Workshop
r+
-------
6.2 Amount Of Time Needed To Prepare Form R Reports
Tables 6-4, 6-5, and 6-6, and Figures 6-3, 6-4, and 6-5 show the number of hours
required to collect the necessary data and complete all the Form Rs for facilities surveyed in RY
1988, RY 1994, and RY 1995, respectively. Section 8 of the Form R was added after RY 1987
and RY 1988 Form Rs were completed. Thus, one would expect an increase in the amount of
time needed to collect the necessary data and complete the Form Rs in the 1994 and 1995
reporting years. Even so, as was the case with the RY 1988, in RY 1994 the majority of facilities
reported taking less than 24 hours to complete all of their Form Rs. There was even an observed
decrease in the percentage of facilities reporting taking over 100 hours to complete their Form Rs
in RY 1994. Facilities surveyed in RY 1995 tended to be larger and had more Form Rs than the
facilities surveyed in previous years. Thus, the amount of time needed to fill out all Form Rs
was greater in RY 1995, as shown in Table 6-6.
In order to take the number of Form Rs filled out by the facilities surveyed into
consideration when calculating the average time required by facilities to fill out Form Rs, an
analysis was done which divided the maximum number of hours in the range checked by the
number of Form Rs filled out by the facility. The number of hours needed to fill out each Form
R is presented by SIC Code and reporting year in Table 6-7.
6-7
-------
Table 6-4
Number of Hours Required to Complete all the Form Rs for RY 1988
Time Estimate
^8 hours
9-24 hours
25-40 hours
4 1-1 60 hours
>160 hours
Percentage of Facilities
SIC Codes 28 and 291"
32
6
6
25
15
SIC Codes 34-38
71
5
24
Totals do not equal 100% because not all facilities reported the time estimate. These data are scaled data which are weighted to represent the
entire SIC Code.
Table 6-5
Number of Hours Required to Complete all the Form Rs for RY 1994
Time Estimate
^20 hours
2 1-50 hours
5 1-1 00 hours
100-200 hours
>200 hours
Percentage of Facilities
SIC Code 25'
42
48
6
0
0
SIC Code 281
63
19
12
6
0
SIC Code 285
61
38
0
1
0
SIC Code 30
56
42
2
0
0
* Totals do not equal 100% because not all facilities reported the time estimate. These data are scaled data which are weighted to represent the
entire SIC Code.
6-8
-------
6-9
o
CO
5T
f
o
01
3
O-
CD
S1
Q.
Percent of Facilities
S 8
(Q
C
0>
CO
(D
Z
(D
S 8-
§ 8.
"S s1
ro o
-•* -n
fi) O
Q. 3
^
i 3
(O
00
00
0)
o
o
o
a
A
-------
01-9
Percent of Facilities
0>
Q.
O.
c
•a
5
"O
S° to
is 5
ft) O
3 g
71
(O
to
o
o
O
Q.
(D
-------
Table 6-6
Number of Hours Required to Complete all the Form Rs for RY 1995
Time Estimate
s8 hours
9-20 hours
2 1-40 hours
41-100 hours
> 100 hours
Percentage of Facilities
SIC Code 26
20
10
40
20
10
SIC Code 286
20
0
10
60
10
These data are scaled data which are weighted to represent the entire SIC Code.
Table 6-7
Average Number of Hours Needed to Complete a Form R
SIC Code
25 (RY 1994)
281 (RY 1994)
285 (RY 1994)
30 (RY 1994)
26 (RY 1995)
286 (RY 1995)
RY1 994 Overall
RY 1995 Overall
Time Estimate (Hours)
12.9
9.9
11.5
13.4
9.4
8.8
11.7
9.0
These data are scaled data which are weighted to represent the entire SIC Code.
6-11
-------
f
O
21-9
o-
CD
C
Q.
g
5"
O)
O)
Percent of Facilities
CD
a
SL
I
Q.
CD
I
CD
_^ K> W
o o o
vP vg ^S
0s* 0s- o^
? # * * * f
•n
to'
c
3
o>
0,
(D
•z.
a>
(D
a
(D
a
O o
o o
-£ °
^ 3
-I
o> g.
B) (D
2 •"
Q. o
ro
7J
_i.
-------
It is recognized that the average time needed per Form R is a function of the
maximum number of hours in the lowest range checked. (The lowest range is different for
facilities surveyed in RY 1994 and RY 1995.) However, the time estimates listed represent an
average range, and are significantly lower than the 43 hours needed per Form R listed in the 1995
EPCRA Section 313 reporting instructions.
6.3 Use of the Hotline
For RY 1994 and RY 1995, 33 percent and 50 percent, respectively, of the
facilities visited reported calling the hotline. Figure 6-6 shows the percentage of facilities calling
the hotline for each of the SIC Codes included in this analysis.
As can be seen by Figure 6-6, personnel at approximately half of the inorganic
chemical (SIC Code 281) and paint and allied products (SIC Code 285), paperboard (SIC Code
26), and organic chemical (SIC Code 286), facilities called the hotline, compared to
approximately one-fourth for the furniture (SIC Code 25) and plastics manufacturing facilities
(SIC Code 30).
Most of the respondents in RY 1994 and RY 1995 (86 percent) indicated that the
hotline response was helpful. However, several facilities stated that they had difficulty in getting
through to speak to an operator, and in some cases the answers provided were not consistent.
The majority of facilities stating that the hotline was not helpful reported being unable to get
through to an operator.
6.4 Comments on the Form R Instructions
Surveyors also interviewed facility personnel in an effort to gain general
comments on the Form R instructions. One commenter suggested that tabs or a "quick reference
guide" be included in the instructions to allow for easy navigation through the separate sections
of the report. Other areas of the report which were stated as being unclear included how to
6-13
-------
submit a revised form and how to distinguish or document off-site transfers for repackaged
materials.
Table 6-8 shows the number of respondents who identified a particular aspect of
the chemical specification information as being unclear.
Table 6-8
Comments on the Form R Chemical Specific Instructions for RY 1994
Subject Area
Toxic Chemical Identity
Mixture Component Identity
Activities and Uses of the Toxic
Chemical
Releases to the Environment On-Site
Transfers in Waste to Off-Site
Locations
On-Site Waste Treatment Methods
and Efficiency and On-Site Energy
Recovery and Recycling Methods
Source Reduction and Recycling
Activities
Number of Respondents stating a Subject Area
was unclear
RY 1994
SIC
Code
25
0
1
1
1
1
0
1
SIC
Code
281
1
0
2
1
1
1
1
SIC
Code
285
0
0
1
0
0
1
0
SIC
Code
30
1
0
0
0
0
0
1
RY 1995
SIC
Code
26
1
0
1
0
0
2
2
SIC
Code
286
0
0
1
0
0
3
2
The general comments received on the Form R instructions are summarized for
each SIC Code as follows:
6-14
-------
SIC Code 25 - Furniture Manufacturing (RY 1994)
• One facility needed more information on estimating pollutant releases for
a material when only a range of concentration is provided on the MSDS.
• The definitions for material usage type (manufactured, processed,
otherwise used) are unclear. In addition, more clarification is needed on
estimating production ratio.
SIC Code 281 - Inorganic Chemicals Manufacturing (RY 1994)
• Several facilities requested more details on identifying and quantifying
treatment, recycling, and repackaging activities. More examples would be
helpful.
• More guidance is needed on estimating future releases needed for Section
8.
SIC Code 285 - Paint Manufacturing (RY 1994)
• Need assistance in estimating releases associated with wastewater
treatment plant discharges.
SIC Code 30 - Rubber and Plastics Manufacturing (RY 1994)
• Several facilities had questions on how to determine production
ratio/activity index.
SIC Code 26 - Paper and Paperboard Manufacturing (RY 1995)
• Many facilities reported that the guidance for ammonia threshold and
release calculations are unclear.
• One facility would like clarification on the definitions of energy recovery,
treatment and recycling.
SIC Code 286 - Organic Chemicals Manufacturing (RY 1995)
• The definitions for material usage type (manufactured, process, otherwise
used) are unclear.
6-15
-------
6.5 Comments on the Automated Form R (AFR)
Approximately half of the facilities surveyed for RY 1994 and RY 1995 used the
AFR to help them prepare their Form R's. The majority of those that used the form stated that it
was helpful, with only a handful stating that it was not helpful. This information is shown
graphically in Figure 6-6.
The types of feedback provided on the AFR is summarized as follows:
In general, the AFR is easy to use and does help minimize errors. In
particular, it's nice that the common data (such as facility name) is
maintained from year to year and only the release information needs to be
updated. Several commenters stated that it seems to be getting better with
each release version.
Several commenters who attempted to use the AFR could not get it
running on their systems. This was more common with Windows NT
users. Windows NT does not seem to properly interface with the AFR.
There were numerous instances of individuals having difficulties in
printing their reports once finished.
One commenter stated that it took 6 weeks for a phone call requesting
assistance in using the AFR to be returned.
The AFR could use more range checks, error checks, and look up tables.
In addition, transcription errors cannot be caught using the AFR.
6-16
-------
Figure 6-6. Percent of Facilities Calling the Hotline by
Industry for RY 1994 and RY 1995
70%
0%
SIC Code 25
(RY1994)
SICCodeSO
(RY1994)
SIC Code 26
(RY1995)
SIC Code 286
(RY1995)
Industry
Figure 6-7. Percent of Facilities using the Automated Form R
for RY 1994 and RY 1995
D'd not
Use APR
46%
Used APR (found it
helpful)
51%
Used APR (found it
not helpful)
3%
6-17
-------
6.6 Comments on Use of the Form A
In general, facilities like the new Form A and found it easy to use. However,
results show that some facilities incorrectly used the Form A when they should have used the
Form R. Facilities must use the Form R if they manufacture, process, or otherwise use at least 1
million pounds of the toxic chemical. Some facilities did not realize this upper limit existed.
Also, facilities must use the Form R if their total annual reportable amount is greater than 500
pounds. The annual reportable amount includes those quantities released, including disposed or
treated, recovered at the facility from recycle operations, combusted at the facility for the
purpose of energy recovery, and transferred off-site for purposes of recycle, energy recovery
treatment, or disposal. Some facilities interpreted annual reportable amount to be releases only,
and therefore incorrectly used the Form A even when their actual reportable amount was greater
than 500 pounds. Some facilities did comment that since they have to estimate their releases and
other waste management quantities regardless of which form they use, they might as well
complete the full Form R.
6-18
-------
7.0 CONCLUSIONS
Overall, the agreement between facility and surveyor estimates was good.
General trends noted in the RY 1994 data were that the total releases claimed by the facility for
all SIC Codes surveyed were less than the total releases claimed by the site surveyors. RY 1995
data showed that the total releases and other waste management quantities claimed by the facility
approximately equaled those quantities claimed by the site surveyors. The percent difference in
total releases and other waste management quantities between the facility calculations and the
surveyor calculations ranged from 0.8% different in SIC Code 26 (paper and paperboard
manufacturing) to 31% different in SIC Code 285 (paint manufacturing). The relatively high
percent difference for total releases and other waste management quantities in SIC Code 285 is
due to two facilities which did not understand on-site recycling quantities, and, therefore, did not
report them. If these two facilities are excluded from the analysis, the percent difference is 20%.
Total aggregate releases and other waste management quantities calculated by facilities and site
surveyors for all SIC Codes surveyed in RY 1994 and RY 1995 differed by 4%. Engineering
calculations and mass balances were the most common methodologies used by facilities to
determine releases.
Facilities in all SIC Codes tended to overestimate stack emissions and
underestimate fugitive emissions. Many facilities were confused by the definitions of these
emissions and misclassified fugitive emissions as stack emissions. Surveyors also identified
frequent errors to the classification of transfers to off-site disposal/treatment/energy
recovery/recycling.
Significant differences were observed between the quantity of chemicals reported
released and otherwise managed by surveyed facilities, scaled to the entire SIC Code, and the
quantity of chemicals released and otherwise managed by all facilities in that SIC Code reported
in the TRIS database. While the results of the site survey program are useful to identify trends in
the data, common errors, and the relative accuracy of the data, this finding suggests the absolute
magnitude of releases and other quantities managed as waste or errors in these estimates at the
surveyed facilities should not be used to represent the entire SIC Code.
7-1
-------
TRI site survey results apply to aggregate data only, that is, some of the apparent
data accuracy comes from the cancellation effects of under- and over-reporting of releases. The
accuracy referred to here is not "true accuracy" but a measure of how well facilities used best
available data and estimation techniques. The results of the site survey, therefore, should not be
used to evaluate the accuracy of the data from an individual facility or a single release stream.
Evaluation of the threshold calculations performed revealed that for 90% of the
chemicals across all SIC Codes surveyed threshold determinations were correctly determined.
Five percent were incorrectly reported as exceeding thresholds, and five percent were incorrectly
omitted from Form R reporting. Comparison of the 6 SIC Codes surveyed for RY 1994 and RY
1995 reveal that SIC Codes 25 (furniture manufacturing), 26 (paper manufacturing), and 30
(rubber and plastic manufacturing) facilities had the best accuracy for determining thresholds, as
98% of the toxic chemicals thresholds were correctly determined. SIC Code 281 (inorganic
chemical manufacturing) facilities were the least accurate in correctly determining thresholds, as
84% of the toxic chemicals were correctly determined.
Evaluation of on-site activities revealed that organic chemical manufacturing
facilities (SIC Code 286) do much more on-site treatment and recycling than facilities in the
other SIC Codes surveyed. In general, the site surveyors agreed with the facilities releases and
other waste management estimates for most on-site activities.
The increasing number of trade association conferences and amount of EPA and
trade association guidance has increased the quality of TRI reporting. Some industries, like the
pulp and paper industry, have developed their own guidance manuals for facilities in their
association to use in filling out the TRI reports. Other industries, such as the paint manufacturing
industry, seem to know less about TRI reporting, estimation techniques, and the documentation
requirements. In such industries, additional guidance on the amount and types of documentation
needed for accurate TRI reporting, and the methodologies used to estimate releases and other
waste management activities would help reduce the number of errors in threshold determinations
and release estimates.
7-2
-------
8.0 RECOMMENDATIONS
This section presents several recommendations for the EPCRA Section 313
program based on the results and conclusions of the RY 1994 and RY 1995 data quality
assessment based on site surveys. Improvements in reporting guidance and in the reporting
instructions, as well as facilities' experience in completing Form R reports for the previous
reporting years will continue to improve the data quality in the TRI database. Recommendations
for continued improvement of the TRI database are listed below.
8.1 Additional Guidance Concerning Form R Instruction and Documentation
General recommendations noted by site surveyors for all SIC Codes include
introducing and explaining the Question/Answer document and sixteen guidance documents
currently available from EPA in the front of the TRI instructions. Many facilities and trade
associations did not read the entire TRI instruction booklet and, therefore, were not aware these
documents existed. Specific comments from facilities in each of the SIC Codes visited are as
follows:
SIC Code 25 - Furniture Manufacturing (RY 19941
• Better definitions are needed in order to distinguish between manufacture,
process, and otherwise use activities.
• There were several comments with the general sentiment that the EPA and
State and Local agencies should attempt to consolidate environmental
reporting and standardize acronyms and definitions for terms such as
"fugitive" emission sources. One specific suggestion was for a "Dummies
guide to environmental reporting."
8-1
-------
SIC Code 30 - Rubber and Plastics Manufacturing (RY 1994)
EPA should develop "a good, clean web-site" for TRI data. The
commenter stated that the TRI CD-ROM was helpful and possibly could
serve as the structure for a web site.
More information was requested on determining production ratio. This
was specifically requested for those EPCRA Section 313 Chemicals
produced as by-products or where the production ratio is determined by
something other than the annual production ratio of the final product.
SIC Code 281 - Inorganic Chemicals Manufacturing (RY 1994)
One commenter stated that much of the information reported as part of the
Form R could be obtained by EPA from other sources such as Title V Air
Pollution permits.
One general comment from several commenters was that more
information is needed on estimating fugitive emissions from sources such
as wastewater treatment and mixing tanks.
Facility Personnel also requested more guidance on classifying and
quantifying recycling and source reduction activities.
SIC Code 285 - Paint Manufacturing (RY 1994)
An industry-specific guidance manual was requested, including examples
specific to chemicals and release types associated with paint
manufacturing.
One consultant who worked on the Form R preparation felt that the
estimation release guidance could be geared to a more technical audience.
The guidance is not clear on what "working losses" are for storage tanks.
Another commenter felt that the range of loss factors for paint mixing was
too wide.
8-2
-------
SIC Code 26 - Paper and Paperboard Manufacturing CRY 1995)
• Some facility contacts said they would have benefited from published
treatment or removal efficiencies as well as published partition
coefficients.
• Many facilities requested more definitive ammonia reporting guidance.
SIC Code 286 - Organic Chemicals Manufacturing (RY 1995)
One general comment from some facilities was that greater availability of
the guidance manuals was needed. Facility contacts suggested industry
specific guidance, targeting (and listing) specific SIC Codes be posted on
the Internet.
8.2 Additional Guidance Concerning Threshold Determinations
Although the nature and extent of threshold determinations varies from
one industry to the next, some general lessons can be learned from the mistakes identified by the
site surveyors. Table 8-1 lists common errors made by facilities when determining thresholds
and offers several recommendations to avoid making such errors in the future. These
recommendations may also be useful to EPA when developing future releases of TRI reporting
instructions.
8.3 Additional Guidance Concerning Release and Other Waste Management
Quantity Estimates
Table 8-2 lists common errors made by facilities in all SIC Codes surveyed when
estimating releases and other quantities managed as waste, and offers several recommendations
to avoid making such errors in the future.
8-3
-------
Table 8-1
Recommendations for Avoiding Errors in Threshold Determinations
Error Observed in
Determining Thresholds
Recommendation for Avoiding Error in
Future TM Reporting Years
Facility did not document results of threshold
determinations.
Reporting instructions should emphasize that
documentation requirements apply to both
threshold determinations and release
estimates.
Facility assumed Section 313 chemicals
exceeded thresholds, rather than calculating
annual usages and comparing these to
reporting thresholds.
Facilities should be informed that assuming
thresholds are exceeded, rather than
calculating annual usages for Section 313
chemicals, is a common source of errors in
TRI reporting. Reporting instructions should
encourage facilities not to assume thresholds
are exceeded, even for chemicals used in very
large or very small quantities.
Facility overlooked Section 313 chemicals
that were purchased in mixtures.
Facilities should carefully review the most
recent MSDS for every mixture brought on
site to identify all Section 313 chemicals used
during a reporting year.
Facility considered only raw materials used
for production and overlooked chemicals used
for other purposes.
Facilities should take a systematic approach to
identify all chemicals and mixtures used in
production and non-production capacities,
including catalysts, underground injection
well treatment chemicals, wastewater
treatment chemicals, and the like.
Facility environmental staff was unaware that
certain Section 313 chemicals were used at the
plant.
Facilities should implement measures, such as
chemical usage logs or hazardous chemical
inventories, to ensure that environmental staff
are aware of all Section 313 chemicals used in
industrial applications.
Facility did not account for EPA's most recent
releases of threshold determination guidance.
EPA should enhance outreach efforts to
ensure that all facilities are aware of revised
reporting guidelines well in advance of
submission deadlines.
8-4
-------
Table 8-2
Recommendations for Avoiding Errors in
Identifying Release Types and Sources
Observed Error
Recommendation for Avoiding Error in
Future TRI Reporting Years
Fugitive emissions from general indoor air
reported as stack emissions when released
from a single building vent
Stack and fugitive releases need to be better
defined, especially regarding general room
air that is simply moved to one release point
on top of the building (without air pollution
control devices). Note: Many state
definitions are exactly opposite the TRI
definition in this instance.
Use of outdated SOCMI emission factors
Instructions should note that SOCMI factors
have been updated.
Overlooked stack emissions from storage
tanks, or reporting these emissions as
fugitives.
Instructions should emphasize this potential
release source and briefly discuss the
definition of loading, working, and breathing
losses from tanks (and the methodology to
calculate them).
Overlooked container residue
Instructions should emphasize that even a
"RCRA empty" drum is expected to contain a
residual (possibly up to two inches) and that
it must be considered for TRI reporting.
Also, note that on-site drum rinsing and
disposal of the rinsate will result in a release.
Overlooked coincidental manufacturing
Instructions should indicate that if coal
and/or fuel oil are used in boilers/burners
there is a potential for coincidental
manufacture (and release) of various EPCRA
Section 313 Chemicals (such as H2SO4, HC1,
and HF).
Incorrectly reporting release disposition for
off-site transfers
Instructions should emphasize that facilities
should attempt to determine the type of
receiving facility that is accepting the
transfers.
8-5
-------
Table 8-2 (Continued)
Recommendations for Avoiding Errors in
Identifying Release Types and Sources
Observed Error
Recommendation for Avoiding Error in
Future TRI Reporting Years
Questions over catastrophic releases
EPA should provide guidance as to what
quantity and frequency designate a release for
Section 8.8.
Questions over on-site recycling
EPA should provide a definition of recycling
and include examples of streams that can be
considered as being recycled in Sections 7
and 8. An example would be used solvents.
Specifically, is a "used" solvent that is
collected and processed in the next batch
considered recycled/reused, or does it have to
be separated first (e.g., distilled or filtered).
This is not clear in the current guidance.
Questions over source reduction
EPA should consider shortening the list of
codes for source reduction and should
provide definitions for each code.
Questions over on-site treatment
EPA should provide definitions for each code
and clarify whether separation technologies
should be considered (for example, many
facilities were unsure if a water scrubber that
simply moved a EPCRA Section 313
Chemical from the air to a water stream
should be considered as treatment).
Questions over energy recovery
EPA needs to define situations for energy
recovery. Examples that came up included
pulp mills which use Kraft recovery boilers.
The main purpose is to generate stream, but
at the same time waste material that contains
EPCRA Section 313 Chemicals is being
burned and destroyed. Some people argued
that the BTU value was high enough to claim
energy recovery. Other people argued that
the intent for throwing certain wastes into the
boiler was to destroy (and treat) the EPCRA
Section 313 Chemicals.
8-6
-------
Table 8-2 (Continued)
Recommendations for Avoiding Errors in
Identifying Release Types and Sources
Observed Error
Recommendation for Avoiding Error in
Future TRI Reporting Years
Overlooking On-Site Recycling: One facility
noted that although they employ considerable
on-site recycling activities (to recover/reuse
expensive raw materials that contain EPCRA
Section 313 Chemicals); they do not report
them for TRI because claiming recycling
would require them to register as a hazardous
waste treatment facility for their state.
There needs to be a consistent definition
between states and TRI for recycling. EPA
and state agencies should discuss this
situation and provide appropriate guidance.
Questions over Section 8 amounts.
Facilities would like a simple formula for
releases in each block of Section 8. (e.g.,
Section 8.1 = 5.1 + 5.2 + 5.3 + 6.2 (disposal
only)). This will cut down on errors and
double counting.
There needs to be clarification of the
treatment definitions in Sections 7 and 8 of
the Form R.
The definitions in the two sections are
currently different, and this can cause
problems when reporting. Confusion occurs
when: 1) chemicals go through a treatment
system but are not destroyed - facilities need
direct guidance to claim "0" efficiency, and
then what to put in Section 8 (0 or NA); 2)
facilities may report the amount sent to
treatment vs the amount treated. This is
confusing because facilities are supposed to
report the amount sent to energy recovery
and the amount sent to recycling, but not the
amount sent to treatment (they should
correctly report the amount treated instead).
There needs to be clarification on how to
calculate production ratio for "otherwise
used" chemicals.
Facilities often used quantities purchased or
released from year to year rather than an
activity index, even though the guidance
specifically states not to do this.
8-7
-------
-------
Appendix A
-------
-------
SURVEY INSTRUMENT
CEB.TRI\1030.nh
-------
-------
FacilitylD: _______ HJ_U
1997
(TRI REPORTING YEAR 1995)
TRI DATA QUALITY
SURVEY INSTRUMENT
CEB.TRI\1030.nh
-------
-------
Facility ID:
FACILITY FACT SHEET
Date of Visit: through.
Facility Name:
Facility Address:
City:
State: Zip Code:
Mailing Address (if different from street address):
Telephone: Fax:
Facility Contact:
Site Surveyors:
Pre-visit Telephone Contact:
Reviewers:
CEB.TRIM030.nh A-l
-------
Facility ID: |_|_|_|-|_l_l_|-|_l_l_l
PRE-VISIT
TELEPHONE CONTACT
TECHNICAL REVIEW
\. How many Form R (reporting year 1995) chemical reports were submitted for this facility?
2. How many 313 chemicals were identified by this facility, but not reported, for reporting year 1995?
3. Did the facility submit any revised Form R chemical reports for reporting year 1995?
YES....D NO...D (StiptoQ.5)
4. List the chemicals which had revised chemical reports.
5. Did the facility submit any withdrawal requests to EPA for the reporting year 1995?
YES....D NO...D (ShptoQ.7)
6. List the chemicals which had withdrawal requests.
Approved D Denied D
Approved D Denied CD
Approved D Denied d
Approved CH Denied U
7. How many full-time equivalent employees did the facility have in 1995?
NOTE: If there were less than 10 fall-time equivalent employees in 1995, do not visit this facility.
Terminate discussion with facility at this time.
CEB.TRIM030.nh A-2
-------
FacilitylD: |_|J_|-|_LL|-|_LI_I
8. Briefly describe the industrial processes performed at this facility in 1995.
9. Has the facility's process operations significantly changed since 1995 (including equipment, chemicals,
feedstock, etc.)?
YES D NO....D (SkiptoQ.n)
10. Briefly describe any process changes.
11. Has the facility implemented any new treatment, disposal, energy recovery, recycling or source reduction
activities since 1995?
YES D NO D (SkiptoQ.13)
12. Briefly describe any new treatment, disposal, energy recovery, recycling or source reduction activities.
LOGISTICS
13. Will the facility be operating under typical conditions at the time of the visit?
YES....D NO D
CEB.TRI\1030.nh A-3
-------
Facility ID: |_|_|_|
14. What personal protective equipment will be needed to participate in a facility tour?
Hard Hat D
Safety Boots
Safety Glasses
Respirator
Other:
D
a
a
15. How long is a typical tour? If unknown, how many square feet does the facility occupy?
(Consider this information when planning the type and duration of tour that would be most useful).
16. Hotel recommendation:
17. Directions to facility:
18. Time to meet:
19.1 Is a confidentiality agreement required to be completed for this facility?
YES...D NO....D (Skip to Q. 20)
19.2 Has a confidentiality agreement been completed?
YES...D NO....D
20. Will the person who completed the Form R and all supporting materials be available during the site visit?
YES...D NO....D Alternate Contact:
CEB.TRI\1030.nh A-4
-------
Facility ID: |_|_|_|-|_|_|
21. Describe the type and quantity of supporting material available for the Form R calculations.
CEB.TRA1030.nh A-5
-------
Facility ID: |_|_|_|-'
SECTION 1.0
REPORT PREPARATION
1.1 Who prepared the release estimates in the facility's Form R chemical reports? (Check all that apply)
Facility Environmental Staff LJ
Corporate Environmental Staff LJ
Facility Staff D
Consultant/Contractor LJ
Safety Department Staff D
Other, specify LJ
1.2 Check all EPA documents and other references used to estimate releases and control efficiencies.
NONE D
TRI Reporting Form R and Instructions, 1995 Version
(EPA 745-K-95-051) D
Estimating Releases and Waste Treatment Efficiencies for the TRI ("Green Book")
EPA 560/4-88-002 D
Title III Section 313 Release Reporting Guidance
EPA/560-4-88-004 a through q, Estimating Chemical Releases D
Compilation of Air Pollution Emission Factors, AP-42 I—I
Industry Trade Association Materials/Seminars I—I
Privately Sponsored Seminar Materials LJ
EPA-Sponsored Training Workshops LJ
MSDSs D
CEB.TRI\1030.nh A-6
-------
FacilitylD: |_|_|_|-|_|_|_|-|_|_|_|
Computer Programs (list) O
Other D
1.3 What is your estimate of the time needed to fulfill the reporting requirements of Section 313 for 1995?
Please include familiarization with the regulation and reporting instructions, completion and internal
review of the reporting forms, and documentation of all information in your reports.
<, 8 Hours D
9 - 20 Hours D
21 - 40 Hours D
41 - 100 Hours D
> 100 Hours D
1.4 Did you find the 1995 Form R reporting instructions useful?
YES D NO....D
1.5 Did you feel any section of the instructions provided with the Form R were unclear?
YES....D NO D (Go to Q. 1.6) NA....D (Skip to Q.1.6)
1.5.1 Check the appropriate section below and briefly explain the difficulty encountered.
Facility Reporting Determination d
Part I. Facility Identification Information CD
CEB.TRI\1030.nh A-7
-------
FacilitylD: L|_L|-|_|_|_|-|_|_|_|
Part II. Chemical Specific Information (Circle number of all that apply) EH
1. Toxic Chemical Identity
2. Mixture Component Identity
3. Activities and Uses of the Toxic Chemical
4. Maximum Amount On-Site
5. Releases to the Environment On-Site
6. Transfers in Waste to Off-Site Locations
7. On-Site Waste Treatment Methods and Efficiency and On-Site Energy
Recovery and Recycling Methods
8. Source Reduction and Recycling Activities
1.6 Did you call the Emergency Planning and Community Right-to-Know Hotline?
YES....D NO....D (SkiptoQ.1.7)
1.6.1 Did you find the operator's response helpful?
YES....D NO....D
If no, explain
1.7 Have you ever received any assistance from EPA Regional or headquarters staff to prepare the
Form R reports?
YES....D NO....D
1.8 Has EPA or your state ever contacted you with questions about any of the reported estimates
(excluding computer generated notices)?
YES....D NO....D
1.9 Has the facility received any Notices of Significant Error, Notices of Noncompliance, or Notices
of Technical Error from EPA or the state for any 1995 reports?
YES....D NO....D
1.10 Does the facility use any computer software to track toxic chemicals brought on site, used, or
identified in MSDSs?
YES....D NO....D
If yes, identify:
CEB.TRI\1030.nh A-8
-------
FacilitylD: |_|_L|-|_LI_|-|.
1.11 Did you use the Automated Form R (APR) electronic reporting to submit your Form Rs?
YES....D NO....D (Skip to Q.I. 12)
1.11.1 Did you feel the AFR helped to reduce any errors on the Form R?
YES....D NO....D
1.11.2 Describe any comments on the use of the AFR.
1.12 Are there additional guidance manuals that EPA should develop to provide more clarification on
Form R reporting?
YES....D NO....D
1-13 If a Form R was completed and the total annual reportable amount was less than 500 pounds,
why did the facility not complete the short form for the alternate threshold reporting?
CEB.TR]\1030.nh A-9
-------
FacilitylD: |_|_|_|-|_|J_|-|J_|_|
SECTION 2.0
INTRODUCTION AND FACILITY TOUR
(313 CHEMICALS PRESENT ON-SITE)
2.1 List all chemicals reported on the facility's Form R Chemical Reports.
Chemical Name CAS # Not a Section 313 Chemical
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
CEB.TRI\1030.nh A-10
-------
FacilitylD: |_|_|_|.|_|_|_|-|_|_|J
2.2 List all Section 313 chemicals not reported on the facility's Form R chemical reports, but
documented by the facility.
NONE....D
Chemical Name CAS # Not a Section
313 Chemical
D
D
D
D
D
D
D
2.3 List ALL other Section 313 chemicals not reported or documented, but identified by the
surveyor during the site visit.
NONE....D
Chemical Name CAS #
CEB.TRlM030.nh A-11
-------
2.4
FacilitylD: |_|_|_|-|_LI_|-|_|_|
List all mixtures identified during the facility tour which may contain Section 313 chemicals.
(a)
Mixture Name
(b)
Identify Section
313 Chemical
Present
(c)
Concentration of
Chemical1
(d)
Amount of Mixture
Used in 19952
(e)
Amount of Section
3 13 Chemical
Used2
'If concentration of chemical is below de minimis (0.1 wt.% for carcinogens, 1.0 wt.% for all others), do not
include mixture in threshold determination.
2 Complete columns d and e during threshold determination.
CEB.rRI\1030.nh
A-12
-------
Facility ID:
Process Diagram(s):
(identify release points and chemicals)
CEB.TRI\1030.nh A-13
-------
Facility ID:
Treatment Unit, Disposal, Energy Recovery, Recycling or Source Reduction Operations):
(identify release points and chemicals)
CEB.TRI\1030.nh A-14
-------
FacilitylD: _U-H-LI-H---!
Facility Tour Notes:
CEB.TIU\1030.nh A-15
-------
Facility ID:
Facility Tour Notes (Cont'd):
CEB.TRI\1030.nh A-16
-------
Chemical Name: Facility ID:
CAS#| I III J-LLI-U
SECTION 3.0
REVIEW OF THRESHOLD DETERMINATION
3.1 How is this chemical employed at the facility? (Check all that apply)
Facility Reviewer Facility Reviewer
3.1.1 D D Manufacture
a. Produced at the facility LJ LJ
b. Imported by the facility LJ LJ
c. For on-site use/processing LJ CD
d. For sale/distribution D d
e. By-product D D
f. Impurity1 (% = ) D D
3.1.2 LJ LJ Process (incorporative activity)
a. Chemical reactant (raw materials,
intermediates, etc.) LJ LJ
b. Formulation component LJ LJ
c. Article component LD LJ
d. Repackaging LJ LJ
'If impurity is present below de minimis concentrations (0.1% for carcinogens, 1% for others), it is exempt from
reporting.
CEB.TRI\1030.nh A-17
-------
Chemical Name: Facility ID:
Facility Reviewer Facility Reviewer
3.1.3 CD CU Otherwise Use (nonincorporative activity)
a. Chemical processing aid (added to reaction
mixture) CD CU
b. Manufacturing aid (process lubricants,
coolants, etc.) CD CD
c. Ancillary use (cleaners, degreasers, lubricants) CD CD
3.1.4 D D Exempt Uses
a. Used in laboratory activities CD CD
b. Structural component CD CD
c. Routine janitorial/facility grounds maintenance CD CD
d. Personal employee use CD CD
e. Motor vehicle maintenance CD CD
f. Intake water component CD CD
g. Contained in an article CD CD
3.2 Was the chemical reported by the facility?
YES....D (GotoQ.3.3) NO....CD
3.2.1 If no, why did the facility decide this chemical was not reportable?
a. Below threshold CD
b. Exempt CD
c. Overlooked chemical LD
d. Other (specify) CD
CEB.TRI\1030.nh A-18
-------
Chemical Name: Facility ID:
CEB.TRI\1030jih A-19
-------
Chemical Name: Facility ID:
3.3 Are all uses of the chemical exempt from reporting according to the surveyor or are all uses of
the chemical a non-aerosol form of sulfuric acid or hydrochloric acid?
YES....D (GotoQ.3.10) NO....D (Continue)
3.4 Does documentation which supports the threshold determination exist?
(Documentation is defined as any type of data available at the facility in any form which
can be used to recalculate the estimate)
YES....D NO....D
3.4.1 If no, why not?
a. Documentation cannot be located CD
b. Documentation was not retained by facility CD
c. Facility unaware that documentation is required CD
d. Facility overlooked the chemical (Skip to Q.3.6) CD
e. Other (specify) CD
3.5 What was the basis of estimate used by the facility for the amount manufactured, processed, or
otherwise used in 1995? Check all that apply.
a. Purchase/inventory records CJ
b. Emission Factors CD
c. Mass balance CD
d. Assumed threshold exceeded (no calculations completed) LJ
e. Process recipes CD
f. Monitoring data CJ
g. Production data CD
h. Other (specify) CD
CEB.TRI\1030.nh A-20
-------
Chemical Name: Facility ID:
CEB.TRI\1030.nh A-21
-------
Chemical Name: Facility ID: |_|_|_|-|_|_|_|-|_|_|_|
3.6 How much chemical did the facility manufacture, process, or otherwise use in 1995?2
Facility Reviewer
a. Manufactured Ibs Ibs
b. Processed Ibs Ibs
c. Otherwise used Ibs Ibs
d. Facility did not estimate these quantities LJ
3.7 Was the reviewer's estimate of the amount of chemical manufactured, processed, or otherwise
used recalculated using available documentation or recreated using other facility data?
a. Recalculated, with no error U
b. Recalculated, within a factor of 2 L_l
c. Recalculated, within a factor of 10 LI
d. Recalculated, greater than a factor of 10 EH
e. Recreated, with no error CH
f. Recreated, within a factor of 2 I—I
g. Recreated, within a factor of 10 I—I
h. Recreated, greater than a factor of 10 I—I
i. Facility did not estimate these quantities I—I
3.8 Was a threshold exceeded for this chemical in 1995?
YES....CD (This chemical should have been reported. Continue)
NO LJ (This chemical should not have been reported. Skip to Q 3.10)
2Record calculations and assumptions for the threshold determination on the worksheet in Section 6.0.
CEB.TRI\1030.nh A-22
-------
Chemical Name: Facility ID:
3r9 What was the maximum amount of this chemical on-site at any time?*
Pacttity
Reviewer
a. Maximum on site Ibs Ibs
3.10 This chemical was:
a. Correctly reported (Go to Section 4.0) CD
b. Correctly not reported (Skip to next chemical) D
c. Incorrectly reported (Go to Q.3.11) CD
d. Incorrectly not reported (Go to Q.3.12)CH
3.11 Why was this chemical incorrectly reported?
a. Facility reported, although amount used was below threshold CD
b. Facility incorrectly assumed threshold was exceeded D
c. Chemical activity was misclassified LJ
d. Threshold quantity was miscalculated LJ
e. Chemical was exempt CD
f. Chemical has been delisted/modified CD
g. Other (specify) CD
(Skip to next chemical)
3Record calculations and assumptions for the maximum on-site quantity on the worksheet in Section 6.0.
CEB.TRlM030.nh A-23
-------
Chemical Name: Facility ID: |_|_|_|-|_|_|_|-|_|_|_|
3.12 Why was this chemical incorrectly not reported?
a. Chemical activity was overlooked Q
b. Chemical activity was misclassified LJ
c. Threshold quantity was miscalculated LJ
d. Other (specify) D
(Continue to Section 4.0)
3.13 If the facility completed a short form for this chemical, are the releases less than 500 pounds?
YES....UJ (Skip to the next chemical and document the release calculations)
NO D (Go to Section 4.0)
CEB.TRI\1030.nh A-24
-------
FacilitylD: _-----_----
SECTION 4.0
REVIEW OF RELEASE TYPES
CEB.TRI\1030.nh A-25
-------
FacilitylD: |_|_|_|-|_|_|_|-|_|_|_|
Section 4.1 Sources of Chemical Releases and Transfers
In the reviewers opinion, document whether or not the facility should have included releases from the following sources (1):
Chemical Name
cAs#LLLL_l-LLI-LI
SOURCE
B. Pumps/valves/flanges
C. Volatilization from process areas
D. Volatilization from treatment areas
E. Storage tank/stock pile losses
F. Accidental spills/releases
G. Waste treatment discharge streams
H. Storm water runoff
I. Process discharge streams
J. Housekeeping practices/clean-up wastes (i.e., solvent)
K. Container residue
L. Treatment sludges, recycling or energy recovery by-products
M. Combustion by-products
N. Other
Fugitive Air
Stack Air
Receiving
Stream
Under-
Ground
Injection
Land On-
Site
POTW
Off-Site
Transfer
NOTE: COMPLETE ALL ROWS AND COLUMNS.
If a Form R was completed:
(1) Y = Yes, release source should be included in release estimate that surveyor
calculates in Section 5 and facility identified this release type.
N = No, release should be included in release estimate but facility overlooked
this release type.
NA = This source was not present at the facility for this chemical
If a Form R was not completed (overlooked chemical):
Y = Release source should be included
NA = Release source was not present at the facility for this chemical
CEB.TRI\1030.nh
A-26
-------
SECTION 4.2 (a) and (b)
CODE LIST
Qi
Q2
Q3
Y = Yes
N = No
NA = Facility overlooked this chemical
FE = Fugitive air
PS = Stack air
RS = Receiving stream
UI = Underground injection
LA = Land on site
PW = POTW
TOSD = Off-site transfer (disposal)
TOST = Off-site transfer (treatment)
TOSR = Off-site transfer (recycling)
TOSE = Off-site transfer (energy recovery)
NA = Facility does not have a release to this
medium
Y = Yes
N = No
NA = Facility overlooked this chemical
Q4
FES = Releases are only fugitive releases and
are not released to a stack.
SFE = Releases are to a stack and not released
as fugitives.
VPC = Chemical is a volatile organic chemical
(VOC) and was not reported as an air
release.
ACID = Mineral acids, which were neutralized,
were included.
POTW = Wastewater discharge is to a POTW
and not a receiving stream.
RECS = Wastewater discharge is to a receiving
stream and not to a POTW.
ONLAND = Releases are to an on-site landfill, not
to an off-site landfill.
OFFLAND = Releases are to an off-site landfill, not
to an on-site landfill.
NOER = Off-site energy recovery does not take
place in a legitimate energy recovery
system.
NOCOMB = Toxic chemical does not have a heating
value high enough to sustain
combustion.
NR = Site visit concluded that chemical is not
released to this medium.
OTH = Other
NA =
Facility correctly identified release type
or facility overlooked chemical
CEB.TRI\I030.nh
A-27
-------
CODE LIST (Continued)
Q5
Q7
Y
Yl
Y2
Nl
N2
N3
N4
N5
N6
NA
^f—
-*f2-
-NA-
1
2
3
4
NA
-N-
Yes
Yes, but facility incorrectly identified release type
Yes, but documentation is unclear or incomplete
Documentation cannot be located
Documentation was not retained by facility
Facility unaware that documentation required
Facility overlooked chemical
Facility overlooked this release type
Other
Facility does not have a release for this medium
Facility unable to locate data
Facility did not retain data
Monitoring data not used
Facility derived factors
EPA published emission factors
Trade association factors
Other
Emission factors not used
-Yes
\£7 1 ~
Ml _
JN1 "
NO «E
MA m
Y
N_
MA _
Ol 1 Y ~
N_
~
MA D
rJA ™
Q12 Y
N
NA =
Q13 MP =
CW =
WTS =
SC =
SPS =
OTH =
1CS
r1 •!•* • • l j ... *
raciiity misiiucrpretca ac minimis rule
OfVuii-
\JUIGI
r> •!•* J * u J ... » i_
XT f -ft. 1 1 J *
No, facility overlooked treatment
No on-site treatment of this chemical for this release
medium occurred
V/10
ICS
XT
iNO
•XT t A £C * * A J
INO treatment efficiencies were not used
Yes
No
Facility does not have a release for this medium
Spent metal plating bath
Cleaning waste
Waste treatment sludge
Spent catalyst
Spent process solvent
Other:
NA =
Facility does not have recycling releases
Note: This code list refers to the questions for the Section 4.2(a) and (b) table on page 27 and 28.
CEB.TRr\1030.nh
A-28
-------
FacilitylD: |_|_|_|-|_|JJ-|_|_|_|
Section 4.2a Review of Release Types (On-Site Releases)
Chemical Name
CAS#| | | | | |-| | |-| |
1. Did the facility identify a release type on the Form R?
2. Enter surveyor's release types.
3. Did the facility correctly identify the release type?
4. If Q.3 is NO, identify the reason that the release type was incorrectly
identified, otherwise enter NA.
5. Is documentation on the facility's release estimate available for review?
IF Q.5 IS NO OR NA, SKIP TO QUESTION 12
6. If monitoring data were used, is it available for review?
7. If emission factors were used, what is the source of the factors?
8. Was each air or waste stream counted only once in release estimates? (1)
9. Were all air or waste streams containing > 1% or aO.1% (carcinogens) of
the chemical included in release calculations?
10. Was on-site treatment of this chemical included in release estimates?
1 1 . Were treatment efficiencies reported consistent with measurement data,
vendor specs, or EPA-published efficiencies? (2)
12. Does the facility have information available to estimate the amount of this
chemical released during 1 995?
Fugitive Air
§5.1
Stack Air
§5.2
Receiving
Stream
§5.3
Underground
Injection
§5.4
Land On Site
§5.5
(+Hf no, document all streams double counted in release calculations in Section 6.0
(2^ If no, document inconsistency of treatment efficiencies used in Section 6.0
CEB.TRI\1030.nh
A-29
-------
Facility ID:
Section 4.2b Review of Release Types (Off-Site)
Chemical Name
CAS# _LJJ_-LLI-LI
1 . Did the facility identify a release type on the Form R?
2. Enter surveyor's release types.
3. Did the facility correctly identify the release type?
4. If Q.3 is NO, identify the reason that the release type was incorrectly
identified, otherwise enter NA.
5. Is documentation on the facility's release estimate available for review?
IF Q.5 IS NO OR NA, SKIP TO QUESTION 12
6. If monitoring data were used, is it available for review?
7. If emission factors were used, what is the source of the factors?
8. Was each air or waste stream counted only once in release estimates? (1)
9. Were all air or waste streams containing k 1% or >0.1% (carcinogens) of
the chemical included in release calculations?
10. Was on-site treatment of this chemical included in release estimates?
1 1 . Were treatment efficiencies reported consistent with measurement data,
vendor specs, or EPA-published efficiencies? (2)
12. Does the facility have information available to estimate the amount of this
chemical released during 1995?
13. If appropriate, characterize the recycling stream (use multiple codes if
necessary).
POTW
§6.1
Off-Site
Transfer
(disposal)
§6.2
Off-Site
Transfer
(treatment)
§6.2
Off-Site
Transfer
(recycling)
§6.2
Off-Site
Transfer
(energy
recovery)
§6.2
(1) If no, document all streams double counted in release calculations in Section 6.0
(2) If no, document inconsistency of treatment efficiencies used in Section 6.0
CEB.TRI\1030.nh
A-30
-------
Facility ID: |_|_|_|-|_|_|_|
Section 4.2c Review of Release Types (On-Site Treatment, Energy Recovery or Recycling)
Chemical Name
CAS#LLLLU-LIJ-LI
1 . Did the facility identify an on-site treatment, energy recovery, or recycling method in §7 on the Form
R?(l)
2. Enter surveyor's identification of on-site methods. (2)
3. Did the facility correctly identify the on-site method? (1)
4. If Q.3 is NO, identify the reason that the method was incorrectly identified, otherwise enter NA. (3)
5. For on-site treatment in §8.6B, did the facility only report the quantity of chemical destroyed during
treatment? (4)
6. For on-site recycling in §8.4B, did the facility report the quantity of chemical recovered from
recycling? (4)
7. If appropriate, characterize the recycling stream (use multiple codes if necessary): (5)
8. Describe the type of recycling unit: (6)
On-Site
Treatment
(§7A or 8.6B)
On-Site
Energy
Recovery
(§7B or 8.2B)
On-Site
Recycling
(§7Cor
8.4B)
(1) Y = Yes
N = No
NA = Facility overlooked this chemical
(2) TR = On-site treatment
ER = On-site energy recovery
REC = On-site recycling
NA = Facility does not use this on-site method
(3) OFFLAND = Releases are to an off-site landfill, not an on-site
landfill
NOER = Off-site energy recovery does not take place in a
legitimate energy recovery system
NOCOMB = Toxic chemical does not have a heating value high
enough to sustain combustion
NR = Toxic chemical is not recycled
OTH = Other:
NA = Facility correctly identified on-site method or facility
overlooked chemical.
(4) Y = Yes
N = No
NA = Facility did not identify this on-site method
(5) MP = Spent metal plating bath
CW = Cleaning waste
WTS = Waste treatment sludge
SC = Spent catalyst
SPS = Spent process solvent
OTH = Other:
NA = Facility did not estimate recycling releases
(6) Identify type of on-site recycling unit used. See §7.C of
FormR.
CEB.TRI\1030.nh
A-31
-------
Facility ID:
SECTION 5.0
REVIEW OF RELEASE ESTIMATES
CEB.TRI\1030.nh A-32
-------
FacilitylD: |_|_|J-|_|_|J-|_|_|_|
Section 5.1 Review of Release Estimates (On-Site Releases)
For each on-site release identified in Section 4.2a (Question 2), complete the following table:
Chemical Name
CAS#|_| | | | |-| | |-| |
1 . Enter facility's release estimate (in Ibs) (1)
2. What method(s) did the facility use to estimate their release? (2)
3. Based on data available to the facility, is this the most accurate
method to determine a release estimate? (3)
IF Q.3 IS YES, SKIP TO QUESTION 6
4. What is a better method(s) which could be used to calculate a more
accurate release estimate? (2) (4)
5. Enter the reviewer's release estimate using a more accurate
method(s) (5)
6. Enter the reviewer's release estimate using the same method(s) as the
facility. (5)
Fugitive Air
§5.1
ABC
ABC
ABC
Stack Air
§5.2
ABC
ABC
ABC
Receiving
Stream
§5J
ABC
ABC
ABC
Underground
Injection
§5.4
ABC
ABC
ABC
Land On Site
§5.5
ABC
ABC
ABC
(1) Range Codes:
A = 1-10 Ibs
B = 11-499 Ibs
C = 500-999 Ibs
Nl = Release estimate was not
included on Form R but should
have been, skip to Question 4
N2 = Facility overlooked this chemical,
skip to Question 4
NA = Facility does not have a
release to this medium, do not
continue with this medium
N3 = Release estimate was included but should not (3)
have been, do not continue with this medium
but enter facility release (i.e, N3,100)
(4)
(2) M = Monitoring data or direct measurements
C = Mass balance calculations
E = Published emission factors
OC = Engineering calculations ("minor calcs")
OJ = Engineering judgement ("guess")
OH = Hazardous waste manifests
O = Other
NA = Facility did not estimate release
Y =Yes
N =No
Document why this method is more
accurate in Section 6.0
(5)
NA = Facility did not estimate release
[Note: Enter the number that was calculated. Only enter
a range, if a range is the most accurate quantity that can
be calculated.]
Document release calculations in Section 6.0
CEB.TRI\1030.nh
A-33
-------
Facility ID:
Section 5.2 Review of Release Estimates (Off-Site)
For each off-site release identified in Section 4.2b (Question 2), complete the following table:
Chemical Name
cAs#LL_LLI- -LI-LI
1. Enter facility's release estimate (in Ibs) (1)
2. What method(s) did the facility use to estimate their release? (2)
3. Based on data available to the facility, is this the most accurate
method to determine a release estimate? (3)
IF Q.3 IS YES, SKIP TO QUESTION 6
4. What is a better method(s) which could be used to calculate a more
accurate release estimate? (2) (4)
5. Enter the reviewer's release estimate using a more accurate
method(s) (5)
6. Enter the reviewer's release estimate using the same method(s) as the
facility. (5)
POTW
§6.1
ABC
ABC
ABC
Off-Site
Transfer
(disposal)
§6.2
ABC
ABC
ABC
Off-Site
Transfer
(treatment)
§6.2
ABC
ABC
ABC
Off-Site
Transfer
(recycling)
§6.2
ABC
ABC
ABC
Off-Site Transfer
(energy recovery)
§6.2
ABC
ABC
ABC
(1) Range Codes: (2) M
A = 1-10 Ibs C
B = 11-499 Ibs E
C = 500-999 Ibs OC
Nl = Release estimate was not OJ
included on Form R but should OH
have been, skip to Question 4 O
N2 = Facility overlooked this chemical, NA
skip to Question 4
NA = Facility does not have a
release to this medium, do not
continue with this medium
= Monitoring data or direct measurements
= Mass balance calculations
= Published emission factors
= Engineering calculations ("minor calcs")
= Engineering judgement ("guess")
= Hazardous waste manifests
= Other (5)
= Facility did not estimate release
(3) Y = Yes
N =No
(4) Document why this method is more
accurate in Section 6.0
NA = Facility did not estimate release
[Note: Enter the number that was calculated. Only enter
a range, if a range is the most accurate quantity that can
be calculated. 1
Document release calculations in Section 6.0
CEB.TRl\!030.nh
A-34
-------
Facility ID:
Section 5.3 Review of Form R §8 Data
(On-Site Releases or Off-Site Transfers)
Chemical Name
cAs#LLLLLI-LLI-LI
1. Enter facility's estimate from §8, Column B, on
the Form R. {Enter NA if facility did not estimate)
2. Enter facility's basis of estimate. (1)
3. Calculate the quantity released or transferred
using the method in footnote (2).
4. Are the facility's estimate (Q.I) and the quantity
released or transferred from Q.3 the same? (3)
5. If Q.4 is NO, provide notes or an explanation
detailing any differences in the calculation of
Section 8 data.
Quantity Released
§8.16
Quantity Used for Energy
Recovery Off Site
§8JB
Quantity Recycled Off Site
§8.5B
Quantity Treated Off Site
§8.7B
(1) TECH = Used the following technique:
- Form R §8.IB = [§5.1 + §5.2 + §5.3 + §5.4 + §5.5 + §6.2 (disposal only) - §8.8]
- Form R §8.3B = §6.2 (energy recovery only) - §8.8
- Form R §8.5B = §6.2 (recycled only) - §8.8
- Form R §8.7B = §6.1 + §6.2 (treated only) - §8.8
(3) Y
N
NA
Yes
No
Facility did not estimate
NOBASE =
OTH
Data for Section 8 was estimated, basis not provided
Other:
NA
= Facility did not estimate; do not continue with this medium.
(2) [Note: Use the best release estimate from Section 5.1 and 5.2 of this survey
to calculate these quantities.]
Document the calculations in Section 6.0.
CEB.TRI\1030.nh
A-35
-------
FacilitylD: |__|_|- _U-|-|-U-I
Section 5.4 Review of Form R §8 Data
(On-Site Treatment, Energy Recovery, or Recycling)
For the on-site treatment or energy recovery method(s) identified in Section 4.2c (Question 2), complete the following table.
Only recreate on-site recycling estimates that were provided by the facility. Do not estimate on-site recycling releases NOT
identified by the facility.
Chemical Name
CAS#|_J_U_-I_U-U
1. Enter the facility's estimate of quantity from §8,
Column B, of the Form R. (1)
2. What method did the facility use to estimate the
amount treated, sent to energy recovery, or recovered from
recycling? (2)
3. Based on data available to the facility, is this the most
accurate method to estimate the amount treated, sent to
energy recovery, or recovered from recycling? (3)
IF Q.3 IS YES, SKIP TO QUESTION 6
4. What is a better method which could be used to
calculate a more accurate estimate? (2)
5. Enter the reviewer's estimate using a more accurate
method. (4)
6. Enter the reviewer's estimate using the same method.
(4)
On-Site Treatment
(§7Aor8.6B)
On-Site Energy
Recovery
(§7B or 8.2B)
On-Site Recycling
(§7C or 8.4B)
(1)
(2)
Estimate was not included on Form R but should have been, skip to Question 4.
Facility overlooked this chemical, skip to Question 4.
Facility does not have this on-site method, do not continue with this medium.
Monitoring data or direct measurements
Mass balance calculations
Published emission factors
Engineering calculations
Engineering judgement
Hazardous waste manifests
Other ___^___
(3)
(4)
Y = Yes
N = No
NA = Facility does not have this on-site method
Document calculations in Section 6.0.
NA = Facility did not estimate release.
CEB.TRI\1030.nh
A-36
-------
FacilitylD: |_|_|_|-|_L|_|-L|_|_|
Section 5.5 Review of Form R §8 Data
(Production Ratio/Activity Index and Source Reduction Activities)
Chemical Name
cAs#U_--U-__l-U
Production Ratio/Activity Index
1. Enter the facility's estimate from §8.9
of the Form R. (Enter NO if facility did
not estimate)
2. Enter facility's basis of estimate (1).
3a. Is this estimate based on a variable
that most directly affects the quantities of
the toxic chemical generated as "waste"
quantities? (2)
3b. If Q.3a is NO, enter surveyor's choice
for alternate basis.
Source Reduction Activities
4a. Enter the source reduction activity
codes from Section 8.10 of the Form R.
4b. Provide a text description of the
source reduction activity.
4c. Is this activity "source reduction"
(i.e., not recycling, treatment, energy
recovery, or disposal) (2)?
Production Ratio/Activity Index (§8.9)
and Source Reduction Activities (§8.10)
3a.
3b.
Activity #1
4a-l.
4b-l.
4c-l.
Activity #2
4a-2.
4b-2.
4c-2.
Activity #3
4a-3.
4b-3.
4c-3.
(1)
TCM
TCPV
TCU
HR
WT
OTH
NA
(2)
Y
N
Ratio of amount of the toxic chemical manufactured in 1995 to 1993
Ratio of production volume in 1995 to 1993
An activity index of the amount of toxic chemical used in 1995 to 1993
An activity index of the amount of operating hours for an activity in 1995 to 1993
An activity index or production ratio based on a weighted average of data from several processes
Other:
The manufacture or use of the chemical began in 1995.
Yes
No
CEB.TRI\1030.nh
A-37
-------
Facility ID:
SECTION 6.0
CALCULATION WORKSHEETS
CEB.TRI\1030.nh A-38
-------
Facility ID:
THRESHOLD DETERMINATION WORKSHEET
Chemical Name:
Description of Use
TOTALS
Amount
Manufactured
Amount Processed
Amount Otherwise
Used
Calculations:
CEB.TRI\1030.nh
A-39
-------
FacilitylD: UJ_H-U-|-|-I-U
MAXIMUM AMOUNT ONSITE WORKSHEET
Chemical Name:
INSTRUCTIONS:—Calculate the maximum amount of the chemical onsite at any one time during the
reporting year. Keep in mind the following:
• All storage areas where this chemical may be kept;
• The amount of chemical being used at any time; and
• The amount of chemical in each waste stream.
Storage Areas:
Total:
Chemical in Use:
Total:
Chemical in Waste Streams:
Total:
CEB.TRI\1030.nh
A-40
-------
FacilitylD: |_U_|-|_U_H_U-
Total On-Site:
CEB.TRI\1030.nh A-41
-------
FacilitylD: |_L|_|-|_|_|_|-|_|_|_|
RELEASE ESTIMATE WORKSHEET
Chemical Name: Release Type
CAS# _____-__-_ SIPage# Question^
INSTRUCTIONS: Record all calculations for release estimates below, in the appropriate sections. Be sure
to identify if calculations use the same method as the facility or a more accurate method.
CEB.TRI\1030.nh A-42
-------
Appendix B
-------
-------
Introduction
The TRI Site Visit study has two primary objectives. The first objective is to estimate the number
of facilities that have made an error in Form R filing. The second objective is to estimate the key
reasons for errors among those facilities with one or more filing errors. Rather than sampling
from all facilities that have filed a Form R, the sample design focused on three major industry
groups ~ 1) Chemical manufacturing facilities, refined specifically to SIC codes 286 (Industrial
Organic Chemicals), 282 (Plastics Materials and Synthetic Resins, Synthetic Rubber, Cellulosic
and Other Manmade Fibers), 281 (Industrial Inorganic Chemicals), and 285 (Paints, Varnishes,
Lacquers, Enamels and Allied Products); 2) Rubber and Plastic Products which are covered by
SIC code 30; and 3) Furniture and Fixtures which are covered by SIC code 25. Facilities
reporting multiple SIC codes will be considered in scope only if all reported SIC codes fall within
one of the SIC code-defined industries selected for study. As discussed below, these three
industry groups were used as the primary stratifier of the facility sample.
The target sample size is 90 completed facility site visits. This total sample size is allocated to the
three primary strata. Because the chemical group is the most important of the three groups, EPA
has decided to have an allocation of 40 site visits from this group, and 25 from each of the
remaining two groups. While the sampling work has been conducted for all three groups, the
initial set of site visits are expected to be restricted to the chemical sector.
-------
-------
Sampling Frame
The sampling frame for the sample was constructed from the 1994 TRI data files (TRIPQUICK).
Those firms with more than fifteen Forms R were eliminated from the sampling frame at Radian's
request because the site visit to verify the Form R information would be too resource intensive.
For SIC codes 25 and 30 none of the facilities were eliminated for this reason, for SIC code 28 six
percent of the facilities were removed. The population size of facilities in each SIC code group (
after removal of facilities with more than fifteen Forms R) is:
Chemical 1274
Furniture 535
Rubber and Plastics 1872
Use of Two-Stage Cluster Sampling
It would be quite costly to draw a national stratified random sample of facilities, because the
facilities would be fairly well scattered across the U.S. In other words, the cost traveling to each
of the selected facilities would be high. The more cost-effective approach used here entailed
selecting a two-stage cluster sample of facilities. The specifics of the sample selection are
outlined below.
The most readily available geographic identification variable in the TRI data file is the three-digit
Zip code sectional center of the facility. Three-digit Zip codes cover relatively small areas in
urban locations and considerably larger areas in rural locations. Using the TRI data file
(eliminating facilities above the Form R threshold), it was possible to sort all of the eligible
facilities by three-digit Zip code. Two-stage cluster sampling involves the following steps:
1) Order all of the three-digit Zip codes in ascending Zip code order to introduce some implicit
geographic stratification.
2) Determine if any three-digit Zip codes are too small and must be combined with one or more
geographically adjacent Zip codes to form a cluster of sufficient size. This was done so that each
Zip code cluster included at least two facilities from each of the three SIC codes. Some areas of
the U.S. do not have any furniture manufacturing facilities. In order to avoid forming clusters
containing a large number of Zip codes, the rule was modified in these areas of the country to
allow for the formation of clusters with no furniture manufacturing facilities. A total of 178
clusters were formed.
3) After creating the sampling frame of clusters, it was determined that the cluster consisting of
Zips 286-287 in North Carolina contained 61 (11.4%) of the 535 furniture manufacturing facilities
in the U.S. This cluster was included in the sample with certainty since it contained more than 10
percent of the total industry facilities, and it was determined that 3 site visits with furniture'
-------
manufacturing facilities should take place in this cluster based on its size.
4) A measure of size was assigned to each of the remaining 177 clusters. The composite measure
of size, MOSj, for the i-th cluster was computed using the equation
where N^ is the number of facilities in the i-th cluster in SIC code group j, and Fj is the overall
desired sampling fraction for SIC code group j.
5) A systematic probability proportional to size (PPS) sample of 40 noncertainty clusters was
drawn from the sampling frame of 177 clusters. The first step in the systematic PPS sample was
to cumulate the measure of size, MOSt over the 177 clusters. The total cumulative sum of MOS;
for the 177 clusters was then divided by 40, the sample size of clusters, to form a PPS selection
interval, K. A random start, R, between one and K was then generated. Forty selection numbers
were computed as R, R+K, R+2K, R+3K, ,R+39K. A cluster was selected if the selection
number fell into its sequence of numbers; that is, the selection number was greater than the
cumulative sum of all previous clusters, but less than or equal to the cumulative sum including the
designated cluster.
6) Overall, the sample consists of 41 clusters ~ the 40 noncertainty clusters plus the Zip 286-287
cluster in North Carolina.
Sampling Facilities Within Clusters
After drawing the first-stage sample of geographic clusters, the second-stage sample of facilities
was drawn. For each of the 40 clusters, one chemical facility was selected as the primary
selection. A minimum of one reserve chemical facility was also drawn from each of the 40
clusters. For rubber and plastics, it was first necessary to draw a random subsample of 25 of the
40 clusters. For each of the 25 clusters, one primary rubber and plastics facility was randomly
drawn, and a minimum of one reserve rubber and plastics facility was also drawn. For furniture, it
was first necessary to draw a random subsample of 22 of the 40 clusters containing furniture
manufacturing facilities. For each of the 22 clusters, one primary furniture facility was randomly
drawn, and a minimum of one reserve furniture facility was also drawn. Recall that 3 primary
furniture facilities were also drawn from the cluster consisting of Zips 286-287 in North Carolina,
making a total of 25 primary selections.
Expected 95-Percent Confidence Intervals
The above design will yield about 40 completed site visits for the chemical group, and 25 from the
other two groups. If we assume that 50% of facilities in the chemical group made a filing error,
then the 90-percent confidence interval would be approximately plus or minus 13.0 percentage
-------
points for the chemical group. In other words, the chances are 9 out of 10 that the true
population percent of facilities with a filing error would be between 37% and 63%. Continuing
with this assumption, 20 of the 40 facilities in the chemical group would have a filing error. For
estimates of key reasons for filing errors, the 90-percent confidence intervals could be as large as
plus or minus 18 percentage points.
For each of the other two groups, if we again assume that 50% of facilities in each of the two
groups made a filing error, then the 90-percent confidence interval would be approximately plus
or minus 16.5 percentage points for each group. In other words, the chances are 9 out of 10 that
the true population percent of facilities with a filing error would be between 33.5% and 66.5%.
Continuing with this assumption, 12 or 13 of the 25 facilities in each of the two groups would
have a filing error. Using this smaller number of facilities as the basis for estimates of key reasons
for filing errors, the 90-percent confidence intervals could be as large as plus or minus 23.7
percentage points for each group.
-------
-------
Appendix C
-------
-------
Dear:
Your facility has been randomly selected by the U.S. Environmental Protection Agency
(EPA) to participate in a data quality survey of facilities that submitted 1994 reporting
year Form Rs for the Toxic Chemical Release Inventory (TRI) under Section 313 of the
Emergency Planning and Community Right-to-Know Act (EPCRA). The purpose of the
survey is to evaluate the quality of the data submitted on the Form R chemical reports and
to provide feedback to EPA that can be used to improve the reporting instructions,
guidance, or the reporting form. Eastern Research Group, Inc. (ERG) is working with
EPA to conduct survey visits to approximately 90 facilities randomly selected from the
1994 TRI database in the following SIC Codes: 25,281,282,285,286, and 30.
Participation in this program is voluntary. However, we believe your participation will
provide a valuable evaluation of the threshold calculations and release and transfer
estimates for your facility, which will assist you in future Form R reporting.
ERG technical staff members will visit your facility at a date between April and May
1997. Most visits will last 1 to 2 days, depending on the number of chemical reports you
submitted and the number of Section 313 chemicals on site. Site surveyors will spend the
majority of that time reviewing the methodology and data that your facility used to make
threshold calculations and release and transfer estimates for the 1994 reporting year.
During the site visit, site surveyors will need your assistance to tour the plant in enough
depth to allow them to understand your manufacturing processes and to identify potential
release points. The site surveyors will make every effort to minimize disruptions to your
schedule while they are on site.
You will be contacted by telephone within the next week to arrange a date for the site
visit. The name and location of your facility will not be released to EPA in order to ensure
confidentiality of your facility's information. All data collected on this project will be
tabulated and reported to EPA in summary form only. At the project conclusion, facility
identification information will be destroyed.
-------
-------
Appendix D
-------
-------
0
DAt-rA
C S€«l*»h»«iJ4"l ^fo«nx*.i^l ^ C
s 7 .M^cr*naf C /^ocoo^-c f 7 ,
L. ^ *- M*P*
-------
Tmi.ttM.oy>
CovP*r4C€
Of-
TO
-------
A ^IXTU/LC d»K)rmi^iHr 1W
OX.IPC i* oseo -TO
i 10,000 VWs.
I^TTM 1^,000 \b$.
v\oS.
A-$ OPP»*FO TT> \
-.«.... .^ .-_ » «. . . ^> A t <
-------
-------
Facility ID: | _ | _
RELEASE ESTIMATE WORKSHEET
Chemical Name: \\i\-Lf\es Release Type Pu.«y,' f/^g. /r?r
CAS# |_|L|2|2|fi|-Ul2H2| SIPage* Question *
INSTRUCTIONS: Record all calculations for release estimates below, in the appropriate sections. Be
sure to identify if calculations use the same method as the facility or a more accurate
method.
\ 1 2 OOO
t\
I — ^ Assume y //«£
for>s 0
of
yr
It
s.
4 August 1997 - Revision 3
CEB2\1108-02.ip H-39
-------
Facility ID: |_L|_|-|_|_|
RELEASE ESTIMATE WORKSHEET
f\\t\e^e^ Release Type S~ntc<
Chemical Name: y gflg- Release Type
CAS# |_|1|2P£-S2Z SIPage* _ Question #
INSTRUCTIONS: Record all calculations for release estimates below, in the appropriate sections. Be
sure to identify if calculations use the same method as the facility or a more accurate
method.
yeir
processed « T- mro Xy/die, --c«?i\T-«fni^a
Its
Iks p*-tf>Au-CT
Ibs -Puifivyt
4 August 1997 - Revision 3
CEB2M 108-02. ip H-39
ce 1/2000 « y^n^ -^Oo t A a
c^i /A^»' V
een c« ^»xi /«-f efe; P^cilt^ e^/via^ecJ 'V^O |l,s.
P"'
J ;'
po->5» fc/e. -fc? re 00,1 ei le. fl^e
-------
Facility ID: | _ |.
RELEASE ESTIMATE WORKSHEET
Chemical Name: Le-*o-
CAS# |!|H|i|2|_|-|-l---
Release Type
SIPage*
Question #
INSTRUCTIONS: Record all calculations for release estimates below, in the appropriate sections. Be
sure to identify if calculations use the same method as the facility or a more accurate
method.
O 1
KVO
+
reuse
V
O.
/L- I
L-/yr.
O.
^V\ / aq, ooo cx?o L~\/\ k<\ \ /"
^v C - F: - Al^J I "
. fo
4 August 1997 - Revision 3
CEB2M 108-02 ip
H-39
-------