xvEPA
            United States
            Environmental Protection
            Agency
             Office of Emergency and
             Remedial Response
             Washington DC 20460
—*•» EPA 540 P-90 003
   May 1990
             Superfund
Removal Cost
Management System:
Version 3.2

-------
                                            EPA/540/P-90/003
                                     OSWER Directive 9360.0-02C
Removal Cost Management System:
                 Version  3.2
         Office of Solid Waste and Emergency Response
          Office of Emergency and Remedial Response
            U.S. Environmental Protection Agency
                 Washington, DC 20460
                               U.S. Environmental Pr
                               Rogion 5, Library (;.":_
                               230 N. Dearborn St-etc
                               CVio. ,*•;:>, IL  60604

-------
                              Notice

This document has been reviewed in accordance with the U.S. Environmen-
tal Protection Agency's peer and administrative review policies and ap-
proved for publication. Mention of trade names or commercial products does
not constitute endorsement or recommendation for use.
                                   11

-------
                              TABLE OF CONTENTS

INTRODUCTION                                                                       iv

1.0    COST PROJECTION                                                            1-1
1.1    INITIATING A COST PROJECTION                                              1-2
1.2    COST PROJECTION MAIN MENU                                               1-5
              A.     Cost  Projection Information                                          1-6
              B.     Update Project Scope                                               1-6
              C     Update Contractor Name and Rate File                                1-9
              D.     Update Contractor Personnel File                                    1-13
              E.     Update Contractor Equipment File                                   1-21
              F.     Update Contractor Expendable Materials File                          1-26
              G.     Update Subcontractor File                                          1-33
              H.     Update Transportation and Disposal Files                             1-35
              I.      Update EPA Cost File                                             1-40
              J.      Update TAT Cost Files                                            1-44
              K.     Update Federal and  State Agency Cost File         .                   1-51
              L.     Update Additional Cost File                                        1-52
              M.     Update Project Contingency Factors                                  1-53
              N.     Calculate and Print the Cost Projection                               1-54

2.0    COST TRACKING                                                              2-1
2.1    INITIATING COST TRACKING                                                   2-2
2.2    1900-55 FORM AND DAILY COST SUMMARY                                    2-9
              A.     Update General Site Information                                    2-10
              B.     Update Prime Contractor Information                                 2-10
              C     1900-55 Form                                                    2-10
              D.     Daily Cost Summary                                               2-10
              E.     Incident Obligation Log (IOL)                                       2-10
              F.     Contractor Daily Cost Log (IOL)                                    2-11
              G.     Archive and Backup date                                           2-11
              H.     RCMS Utilities                                                   2-11

3.0    1900-55 OVERVIEW                                                            3-1
3.1    PREPARING THE 1900-55 FORM                                                 3-2
3.2    1900-55 MAIN MENU                                                            3-3
              A.     Update Contractor Code and Rate Information                          3-3
              B.     Update Contractor Personnel Files                                    3-6
              C     Update Contractor Equipment Files                                   3-13
              D.     Update Contractor Expendable Materials File                          3-21
              E.     Update Subcontractor File                                          3-26
              F.      Update Comments and Adjustment to 1900-55 Totals                    3-28
              G.     Calculate and Print 1900-55 Form                                    3-31

4.0    DAILY COST SUMMARY                                                        4-1
4.1    PREPARING THE DAILY  COST SUMMARY  (DCS)                                 4-1
4.2    DAILY COST SUMMARY  MAIN MENU OPTIONS                                  4-3
              A.     Update Project Ceilings                                              4-3
              B.      Update EPA Costs                                                 4-4
              C    '  Update Other Federal Agency Costs                                  4-10

                                           iii

-------
             D.    Update TAT Costs
             E.    Update Other Costs
             F.    Update Daily Cost Summary Adjustments and Comments
             O.    Print Dairy Cost Summary
4.3     SAMPLE DAILY COST SUMMARY AND DAILY COST LISTING

5.0     INCIDENT OBLIGATION LOG OVERVIEW
5.1     PREPARING THE INCIDENT OBLIGATION LOG (IOL)
5.2     CONTRACTOR  DAILY COST LOG
5.3     PREPARING THE CONTRACTOR DAILY COST LOG

6.0     ARCHIVE AND BACKUP DATA OVERVIEW
6.1     ARCHIVING PROCEDURE

7.0     RCMS UnLITIES OVERVIEW
             A.    Prepare Archive Disks and Backup Archive Disks
             B.    Print Supplemental 1900-55 Reports
             C.    Transfer Interface Data
             D.    Restore Last Day's Final Data from the Hard Disk

8.0     SITE SUMMARY REPORTS OVERVIEW
8.1     PREPARING THE SITE SUMMARY DATA FILES
8.2     PRODUCING SITE SUMMARY REPORTS
             A.    Facsimile of 1900-55 Form of Daily Cost Summary
             B.    Site Cost Reports: Site Summaries
             C    Site Cost Reports: Component Summaries
             D.    Change printer escape sequences for output
APPENDICES
             A.     Edit/View/Delete Option
             B.     User Support
             C     Electronic Report Transmission
             D.     Telenet Numbers
GLOSSARY
INDEX
4-11
4-19
4-21
4-22
4-23

 5-1
 5-1
 5-2
 5-2

 6-1
 6-2

 7-1
 7-1
 7-2
 7-3
 7-4

 8-1
 8-2
 8-4
 8-4
 8-5
 8-8
8-13
A-l
B-l
C-l
D-l

G-l
 1-1
                                        IV

-------
                                     INTRODUCTION
Welcome to the Removal Cost Management System (RCMS), Version 3.2. This User's Guide for RCMS
has been specifically designed  to serve as  a reference manual for the use of software to perform cost
projections and daily cost tracking, as well as to create the following documents:

        •   •   Cost Projection Reports
              1900-55 Form
        •      Daily Cost Summary
        •      Incident Obligation Log
        •      Site Summary Reports

The User's Guide assumes familiarity with both the policies and procedures for cost management as found
in the Removal Cost Management Manual and with a computer keyboard and basic Disk Operating System
(DOS) functions.  Extensive computer knowledge however, is not necessary for effective operation of RCMS.

A.     Structure  of RCMS

       The Removal Cost Management System consists of three (3) separate computer modules:

       1.     Cost Projection module
       2.     Cost Tracking module (1900-55 Form  and Daily Cost Summary)
       3.     Site Summary Report module


       Within each of these three modules, a hierarchy of menus exists permitting the user to enter, edit
       and erase  information, as necessary.  Certain functions remain constant throughout all three RCMS
       modules.  These include:

       1.     A standard menu for updating the data within a file (e.g., personnel names and positions,
              materials, equipment rates).

       2.     A standard  screen,  and accompanying  menu, for editing data within a file (for a basic
              explanation  of this screen, and the Edit Menu, see  pages  1-18 of this User's Guide. For
              an in-depth discussion of this function, see Appendix A).

       3.     A standard option to  delete all  information  (collectively)  from a file.

       The chapters of this User's Guide that follow provide detailed step-by-step instructions for the use
       of all  three RCMS main modules.   This includes instructions for the use of  the standardized
       functions listed above.

-------
B.     Tips For Using RCMS

       1.      By entering the number "1", or any number greater than "1", you will be able to progress
               further into any individual RCMS program or menu.  Entering a zero (0), , or
               in certain instances , will return you to a previous menu.

       2.      Selected information has been pre-entered into RCMS for your benefit.  This pre-entered
               information  is known  as "default  data" and  represents standardized  figures  and facts
               necessary for use of RCMS.  For example, whenever  you request the "EPA Headquarters
               Hours" percentage, it will automatically be displayed on your computer screen as 10%, as
               this figure is required by the Comptroller's Office.  In every instance where you encounter
               default data in RCMS, you have the option of either accepting or changing that information.
               This is most apparent when you encounter questions requiring a "yes"  or "no" response.
               RCMS is designed to protect you from mistakes (particularly when  it comes to erasing data)
               by requiring you to confirm the default response (either "yes"  or "no" depending on  the
               particular question) or  modifying it to obtain the desired result.

       3.      Personnel costs are calculated in RCMS by multiplying hourly rates by hours worked. Rates
               should always be entered first, followed by hours charged.

       4.      When entering personnel names, it is recommended that you enter the individual's last name
               first, followed by either their full first name or a first initial.  Use of punctuation is not
               required.  Thus, any of these four entries would be correct:

               a.      Doe, John
               b.      Doe John
               c      Doe, J.
               d.      Doe J

               Choose whatever format is most comfortable for you, but remember to remain consistent
               with your format choice throughout all RCMS entries.

       5.      Throughout the Cost Projection and Cost Tracking modules of RCMS you will be required
               to enter unique "codes" to  identify the contractor, subcontractors,  vendors, equipment,
               personnel, etc., used for a specific cleanup action. In the case of listed contract equipment
               types and standard personnel categories, you will discover that the identifying codes have
               been pre-entered  into  RCMS.   You need  only find  the  equipment  or job and  its
               accompanying code on a displayed list, and then enter that code into the system.

               It will be necessary for  you to create codes for any non-listed equipment or jobs, as well
               as for all contractors, subcontractors, and vendors. These codes consist of a series of letters,
               numbers, or a combination of both unique to  the item or company you are entering into
               RCMS.  Explanations of each code can be found in  this Guide as they are encountered
               in your use of RCMS.

               It is important to recognize that these codes should be more than just a randomly chosen
               series of letters and/or numbers. Rather, by carefully creating codes for related objects, jobs
               and  companies (e.g., by  giving them all the same first  letter or number), you can organize
               logical groupings of associated items within RCMS. This allows  for easier access to this
               information at a later time, particularly when printing reports.  Thus, by carefully
                                              VI

-------
considering the  codes you create, you could, for example, access all related costs  for a
contractor, or trace equipment or materials to their point of purchase.

Each option within the 1900-55 Form module has the capability to print an entire draft
copy of the 1900-55 Form, or any portion of it (just the pages for ERCS  personnel or
subcontractor Await Bills, for example).
                               VII

-------
        Installing RCMS

        To install RCMS onto the hard disk, you must make sure that at least 2 megabytes (2,000,000 bytes)
        of free space exist on the disk.  The next step is the creation of a directory, to be titled "RCMS".
        This is accomplished by typing the following boldface commands and then pressing the < ENTER >
        key.
       CD\
       MD \RCMS
to return to the root directory
to make a directory called RCMS
       Once this  directory is established you can proceed to the  installation  of the RCMS  software.
       RCMS, Version 3.2, is contained on three (3) double-density  disks (360K), each containing one of
       the three main RCMS modules (Cost Projection, Cost Tracking, and Site Summary Reports). Each
       of these modules  can be installed separately into the newly created RCMS directory on  the
       computer's hard disk.  To install a module, type the following command:
       CD \RCMS
       A:INSTALL
this permits entry to the RCMS directory
installs the module onto your hard disk drive
       The same installation procedure is used for all three modules.

D.     Getting Started

       To begin RCMS from the DOS prompt at the root directory level (C:\>), simply type RCMS.  The
       following title screen will appear after a few seconds.
                                  REMOVAL
                                           COST
                                                   MANAGEMENT
                                                            SYSTEM
                                                                   VERSION 3.2
                                                                    JUNE, 1989
                                             Vlll

-------
~"7  j      Note: There may be alternate methods of starting RCMS depending on the particular computer
 ~)>        system you are using.   Consult the individual responsible for this system if you are having
            difficulty.
     Press  to display the RCMS Version 3.2 Main Menu.  This menu is illustrated below:
             Version 3.2    I     Removal  Cost Management System     I    System Menu
                                    1.  Cost Tracking  (1900-55/DCS)

                                    2.  Site Sunmary

                                    3.  Cost Projection

                                    4.  Invoice Verification

                                    0.  Exit
          Please enter your selection:'
    This menu permits you to begin any one of the three RCMS main modules.  The following chapters
    in the User's Guide correspond to each of these modules and provide detailed instructions in their
    use.  Each chapter assumes you are proceeding from this Main Menu.  Material and instructions
    common to all three RCMS main modules is contained in the User's Guide's Glossary, Appendices,
    and Index.
                                            IX

-------

-------
                                CHAPTER 1
                           COST  PROJECTION
 1.0  COST PROJECTION OVERVIEW

 The RCMS Cost Projection module is designed to help you accurately estimate the cost of
 a removal action.  Through a series of menus, data entries and editing screens, the program
 will guide you through the cost estimation process. The module will prompt you for the
 relevant information needed to estimate costs for cleanup contractor personnel, equipment,
 and expendable  materials.  You will also be requested  to enter related fees, such as
 subcontractor costs and waste transportation and disposal  costs.  In addition, you will be
 asked to enter the estimated costs for EPA, TAT, plus any  other major costs associated
 with the removal action.
               Note: Contingency factors generally are 10 to 30 percent.
Once provided with this information, the computer will calculate the cost for each category
or item specified, and will provide the total estimated cost for the removal action. The
program will automatically apply the contingency factors to the proper subtotals and
calculate the total estimated cost of the removal action.
               Note: The Cost Projection Summary Page format in this RCMS module has
               been changed to be consistent with the format given in the Removal Cost
               Management Procedures Manual.

Several new features have been added to the Cost Projection software.  The system can
now accommodate multiple team contractor personnel and equipment rates (similar to the
1900-55 Form module).  The software also has the capability to  swap various contractor
rates in and out of the current equipment and personnel files, permitting a comparison of
contractors' costs.

In addition, RCMS can store and retrieve Cost Projections.  This enables you to build a
reference  library of Cost Projection scenarios.  Thus, each time you perform  a Cost
Projection you can call up a  similar stored scenario, make the necessary modifications, and
print your new scenario.

Before you sit down at the computer to generate a Cost Projection, you must have a clear
idea of the activities that you will  be undertaking in the removal response. The computer
will prompt you for the required information and will perform  the necessary calculations;
                                       1-1

-------
however, you must perform the preliminary planning.

Perfonning the following steps will prepare you with the information the computer will
require from you.

       1.      Develop the scope of work, based on the response objectives of
               the removal action including  the specific tasks needed to meet
               the response objectives.

       2.      Develop a time frame for the project

       3.      Estimate the total number of ERCS personnel and equipment
               categories required on the site, the amount of time each will be
               needed as well  as the total amount of expendable materials for
               ERCS.  The data entered into the computer should reflect the
               total requirement for each personnel, equipment, and expendable
               material category estimated as accurately as possible.

       4.      Estimate ERCS subcontractor costs.

       5.      Estimate the costs of waste transportation and disposal.

       6.      Estimate the ERCS contingency factor (10-30%)  to reflect the
               amount of uncertainty that exists  in the scope of work for the
               cleanup contractor.

       7.      Estimate direct EPA and TAT personnel costs along with all
               other major costs associated with the removal action.
                                                                                                  '
               Note: Be aware that although this User's Guide explains the Cost Projection
               module in a sequential order, according to the numbered options on the Cost
               Projection Main Menu, you may not be using it in that way. This module is
               designed so that you can access and use any option on the Main Menu in any
               order.  Thus, you can enter data as it is  collected, in any  category (Le.,
               personnel, equipment,  etc.).   Unless specifically  noted,  no option from the
               Main Menu is dependent on any other for your use.

1.1   INITIATING A  COST PROJECTION

Select  Option 3 (Cost  Projection) from the RCMS Main Menu to initiate the Cost
Projection software.  The first screen displayed is the Projection Scenario Data Options
Menu.
                                       1-2

-------
          COST PROJECTION
PROJECTION SCENARIO DATA OPTIONS
06/01/89
                   1. Use Current Scenario Data

                   2. Access Scenario Data Stored on Hard Disk

                   3. Access Scenario Data Stored on Floppy Disk

                   4. Store Current Scenario Data

                   5. Start a new Scenario (Erase Current Files)

                   6. Access Contractor Rate Files

                   0. Return to Previous Menu

                      Your Choice:
This menu screen lists six options for using or manipulating the Cost Projection data, each
explained below, plus an option to return to the previous menu.  RCMS software will hold
only one "current" scenario at a time, others can be stored on the hard or floppy disks.
If you wish to start a new Cost Projection scenario begin with Option 5.

A.     Option  1: Use  Current Scenario Data

        This Option enables you to use the current Cost Projection data found on the hard
        disk.  Select this Option if a scenario is currently loaded into  the Cost Projection
        module or if you wish to display the Cost Projection Main Menu and resume work
        on the current scenario.

        If you exit RCMS, you can return to your Cost Projection scenario with all the data
        intact by choosing this Option (assuming  no one has erased your data).

B.     Option 2:  Access  Scenario Data Stored on Hard  Disk

        This displays a listing of all scenarios stored  on the hard disk.  After reviewing the
        list, select and enter "L" (from the keyboard) if you wish to load a scenario into
        the current files.   You will then be prompted to  enter the identifier  of this
        scenario.  The identifier consists of four alphanumeric characters. You may erase
        scenarios from your hard disk by entering "E", followed by the scenario identifier
        when prompted by the computer.

C.      Option 3:  Access Scenario Data Stored on Floppy Disk

        Floppy disk scenarios may  be loaded or erased by following the same procedure
        described above for the hard disk.  After selecting this Option, you will be asked
        to insert a Cost Projection Storage Disk in the floppy drive.  A list of all scenarios
        stored on that disk will be  then displayed.   You may load or  erase scenarios by
                                       1-3

-------
       selecting either "L" or "E" from the keyboard and entering the scenario ID when
       prompted.

D.    Option 4:  Store Current  Scenario Data

       Select this Option to store Cost Projection scenarios on either the hard drive or
       floppy disks.  If you wish to keep  the current scenario for reference, be sure to
       store it before you begin to work on any other Cost Projection scenarios.  You may
       want to adopt some sort of regional identification scheme for scenario ID numbers
       to allow easier retrieval.   -

E.    Option 5:  Start a  New Scenario  (Erase Current Files)

     .  Select this Option if this is your first time using RCMS, or if you are starting a
       new Cost Projection scenario.  This  will prepare the necessary file on the  hard disk
       for initiating  new scenarios and will  erase  any  existing data from  a  previous
       scenarios. After erasing data, the program will display the Cost Projection Main
       Menu from  which your Cost Projection activities are centered. See page 1-5 for
       instructions  in the use of this Menu.

F.    Option 6:  Access  Contractor Rate Files

       This Option enables you to access  the reference personnel and equipment  rates
       for the Cleanup Contractor. The following menu will be displayed offering a choice
       of four options:
         COST PROJECTION
ACCESS CONTRACTOR RATE FILES
06/01/89
                  1. Load Contractor Rate Data from Floppy Disk

                  2. Erase Contractor Rate Files on Hard Disk

                  3. Update Contractor Rates in all Current Scenario Files

                  0. Return to Previous Menu


                     Your Choice:
       1.      Option 1: Load Contractor Rate Data from Floppy Disk

              This enables you to  load reference contractor personnel and equipment
              rates  from a floppy  disk to  the Cost Projection Rate Files.  The same
              contractor rate floppy disks that are used to load rates into the  1900-55
                                       1-4

-------
                Form module can be used to load these Cost Projection Files.  This Cost
                Projection software is capable of storing multiple team contractors rates,
                similar to the 1900-55 Form module.

        2.      Option 2: Erase Contractor Rate Files on Hard Disk

                This Option erases the contractor reference personnel and equipment rate
                files from the hard disk.

        3.      Option 3: Update Contractor Rates in all Current Scenario Files

                This Option enables you to load another set of contractor rates into all
                current cleanup contractor files.   Use this Option to update personnel,
                equipment, expendable materials, subcontractors, waste transportation, and
                waste disposal files.

        4.      Option 0: Return to Previous Menu

                Use this Option to return to the Projection Scenario Data Options Menu.

1.2  COST  PROJECTION MAIN MENU

Selecting either Option 1 (Use Current Scenario Data) or  Option 5 (Starting A  New
Scenario) from the Projection Scenario Data Options Menu (shown on page 1-3 and 1-4)
will display the  Cost Projection  Main Menu:
          COST PROJECTION
MAIN MENU
06/01/89
               1.  Update General Cost  Projection Information
               2.  Update Project Scope
               3.  Update Contractor Name and Rate File
               4.  Update Contractor Personnel File
               5.  Update Contractor Equipment Files
               6.  Update Contractor Expendable Materials File
               7.  Update Subcontractor File
               8.  Update Transportation .and Disposal Files
               9.  Update EPA Cost File
               10. Update TAT Cost Files
               11. Update Federal and State Agency Cost File
               12. Update Additional Cost File
               13. Update Project Contingency Factors
               14. Calculate and Print  the Cost Projection
               0.  Return to Previous Menu
                  Your Choice: I
The activities involved with producing a Cost Projection center on this Menu (which also
serves as an excellent outline for building a Cost Projection once your preliminary planning
is  complete).   This RCMS module always returns  to this Menu  upon  completion of
subsequent options.
                                        1-5

-------
A.     Option 1: Cost Projection Information

        This Option displays the Update General Projection Data screen, allowing you to
        enter and/or edit this information. The computer prompts you for the following:

        •      Projection Scenario ID Number
        •      Scenario Name
        •      Date
        •      Estimated Project Duration
        •      Prime Contractor Code
        •      Prime Contractor Name
        The Projection  Scenario ID Number,  which you create, (see  page v-vi of the
        Introduction) is used to catalog the Cost Projection scenarios stored on the hard
        drive or floppy disks.

        The Prime Contractor Code and Name is  selected from the list of contractors
        previously loaded  into RCMS from a Contractor Rate Disk (see pages  1-4) or
        entered using Option 3 from the Cost Projection Main Menu.  Please note, this
        information must be entered before you can proceed with this Option. The prime
        contractor's name  appears on the Cost  Projection summary page.
          COST PROJECTION
UPDATE GENERAL PROJECTION DATA
06/01/89
                       Current Projection Information:

              Projection Scenario ID No.:       E901
              Scenario Name:
              Date:
              Estimated Project Duration:

              Prime  Contractor Code:
              Prime  Contractor Name:
            ABC DRUM
            12/17/88
            120 Days

            0001
            ACHE ENTERPRISES
              Is the above information correct? (Y/N] |
       After entering the requested  information and verifying that it is correct,  the
       computer returns to the Cost Projection Main Menu.

B.     Option 2:  Update Project Scope

       Select this Option to  enter and/or update the Project Scope.  Once chosen, the
       computer will display the Project Scope  Menu, offering you several options of
       action.
                                       1-6

-------
    COST PROJECTION
                                 PROJECT SCOPE MENU
                            06/01/89
             1. Add/Edit/View Project Scope

             2. Delete All Project Scope Entries

             0. Return to Previous Menu


                Your Choice:
1.       Option 1: Add/Edit/Viw Project Scope

        To add and/or modify entries for the Project Scope use this Option.  The
        computer will prompt  you to  list the  individual steps,  or milestones,
        involved  with your particular project and to estimate the number of days
        required  to accomplish each one.
  COST PROJECTION
PROJECT SCOPE
06/01/89
Rec
                  Step/Milestone
                 Estimated
               Duration (Days)
                MOBILIZE SITE
                INSTALL FENCE
                DEFINE BURIED DRUM AREA
                SAMPLE EXPOSED DRUMS
                           Enter new record
       If there are currently no records within this file, the computer will inquire
       whether you wish  to add one  at  this time.  If so, press "Y" and then
        to  display the Edit Menu at the bottom of the screen. By first
       pressing the "Add a new record"  Action Key and then the "Edit Key" (both
       on the Edit Menu) the Step/Milestone field and Estimated Duration  (days)
                                 1-7

-------
        field will be highlighted, allowing you to add new data.  If, when you select
        this Option records do  exist within  the file,  the computer will shift
        immediately to the Edit Menu.
COST
Rec
*
1
2
3
4
5
Action
PROJECTION PROJECT SCOPE
06/01/89
Estimated
Step/Milestone Duration (Days)
MOBLIZE SITE 1
INSTALL FENCE .3
DEFINE BURIED DRUM AREA 3
SAMPLE EXPOSED DRUMS 3
SAMPLE TANKERS 4

keys: [<*} Edit [I] Previous record [PgUp] Previous page
[D] Delete [1] Next record [PgDn] Next page
[U] Undelete [-] Add a new record [Esc] Quit
        To edit existing data in the file, position the cursor next to the entry to
        be modified and press the Edit  Action Key (from the Edit  Menu).  This
        will highlight the Step/Milestone  and Estimated Duration  (days) fields,
        allowing you to type your new data over the displayed information.  The
        Editing Mode is identified by a  display at the bottom of the screen.

        The Edit Menu also offers the option of deleting an entry entirely.  To do
        so, position the cursor on the line  of data you wish to eliminate and press
        "D" (the Delete  Action Key from the Edit Menu).  The computer will
        prompt you to validate this action  with an entry of TT (or "N" should you
        change your mind regarding the deletion). Three asterisks will replace the
        entry's record number, indicating that this file entry is marked for deletion.
        To complete  this action,  press  the  key to leave the Edit/View
        section and completely delete the chosen data.  Up until the point that you
        leave the Edit/View section you  can restore data by pressing "U" (the
        "Undelete" Action Key from the Edit Menu).

REMEMBER!   Once  you   leave  the Edit/View/Delete section  data cannot be
restored to the file without  reentering it manually.
       NOTE:   The Edit Menu section that appears within this file is standard
       throughout RCMS, and will appear in every option titled Edit/ViewlDelete.
       The Edit Menu and its available choices are always the same.  For an in-
       depth explanation  of the  mechanics of the Edit/View/Delete Option,  see
       Appendix A in this User's Manual
                                 1-8

-------
               Option 2: Delete All Project Scope Entries

               This Option allows you to delete all Project Scope entries at once, rather
               than removing them one at a time in the Add/Edit/View mode. Once you
               have entered a response, ("Y" or "N") you will be returned to the Project
               Scope Menu.
         COST PROJECTION
PROJECT SCOPE MENU
06/01/89
         Are you sure you want to delete all Project Scope entries? [Y/M]  N
C.     Option 3: Update Contractor Name and  Rate File

       This Option permits you  to edit information pertaining to the current  list of
       Cleanup Contractors in this file or to add new contractors to  that list.  The
       Add/Edit Contractor Data screen will be displayed and you will be prompted to
       enter a Contractor Code.
                                      1-9

-------
COST PROJECTION
                           ADO/EDIT CONTRACTOR DATA
            06/01/89
              Enter the Contractor Nuifcer or hit
                 to list available Contractors:
                      (Enter a blank to exit)
F1
     Option 1:  Add/Edit Contractor Data

     Press    to view the current list of contractors.   A small  window
     containing this list will appear  in the upper  right hand corner of this
     screen.  If this list is too large to display in its entirety, the  program will
     tell you that additional contractors exist.  By pressing < ENTER > you can
     display the rest of the contractor list Press  at the end of the
     list to exit this window.
     Note: If you have previously loaded rates into the system from a Contractor
     Rate Disk, (Option 6 from the Projection Scenario Data Options Menu, page
     1-4) the contractors loaded into the system will appear on this screen.
                               1-10

-------
COST PROJECTION
                           ADD/EDIT
              Enter  the Contractor Mu
 CURRENT CONTRACTOR LIST  —

Code   Name

0001  ACHE
0002  WESS CORP.

 Note the Contractor Code and
  hit ENTER to continue.
                 to list available Contractors:
                     (Enter a blank to exit)
       a.      Adding Contractors

              To add a new contractor enter a unique contractor code consisting
              of any  combination  of characters  or  numerals  (maximum 4
              characters). Once this code is entered, a window appearing in the
              upper right hand corner of the screen will indicate data for this
              contractor code does not exist  Enter a "V to begin the data entry
              process. The  program  will  prompt  you  for  the  following
              information:

               •       Contractor Name
               •       G&A Percentage
               •       Standby Rate  (for equipment)
               •       Decon Rate (for equipment)

       Note: The G&A Percentage, Standby Rate, and Decon Rate are described in
       the Glossary.
                               Ml

-------
COST PROJECTION
AD
              Enter the Contra
                 to list avail
                     (Enter •
                                    EDIT THIS CONTRACTOR'S DATA
                               Code:
                               Name:
                               G4A Percentage:
                               Standby Rate:
                               Decon Rate:
                    ACME ENTERPRISES
                     HP
       Is this correct?  CY/N]  f
             Enter the requested information using "0" for any non-applicable
             rate information.  When completed, confirm that the information
             is correct.  Exit the Add/Edit Contractor Data screen, by simply
             pressing  in the empty field.

     b.      Editing Contractor Data

             To  edit  Cleanup Contractor  information,  enter  the specific
             contractor code.  (Remember, you can press   to review a list
             of all the contractor codes.)  A window will appear  in the upper
             right hand corner of the screen,  displaying current data pertinent
             to the specific contractor selected.  You  may type  over  the
             displayed data to enter new information. Once editing is complete,
             confirm that the information is correct by entering a *Y".  You may
             then continue  to add to and  edit the contractor list.   When
             finished, press < ENTER > while in an empty field to return to the
             Cost Projection Main  Menu.
                              1-12

-------
D.     Option 4:   Update Contractor Personnel  File

        Select this Option to update the Cleanup Contractor personnel file. Once chosen,
        the Cost Projection Personnel Menu will be displayed:
          COST PROJECTION
                                         PERSONNEL MENU
06/01/89
               1. Add Listed Personnel  to the Personnel File

               2. Add Non-Listed Personnel to the Personnel File

               3. Edit/View/Delete Entries in the Personnel File

               A. Update Current Scenario Personnel Rates

               5. Delete All Personnel  Entries

               0. Return to Previous Menu


                 Your Choice: I
       You now have the option of adding, editing, reviewing, or deleting entries in this
       Personnel File.  You can add job categories to the Personnel File as either Listed
       or Non-Listed Personnel.

       1.      Option  1:  Add Listed  Personnel

               This Option will display a screen consisting of code numbers, together with
               corresponding job categories.
                                        1-13

-------
COST PROJECTION ADDING LISTED
Code Job Category
001-1 SUPERVISOR
001-2 SUPERVISOR
002-1 FOREMAN
003-1 CLEANUP TECH-HAZ
003-2 CLEANUP TECH-HAZ
004-1 LABORERS
005-1 EQUIP OPERATOR
005-2 EQUIP OPERATOR
006-1 TRUCK DRIVER
006-2 TRUCK DRIVER
007-1 WELDER
007-2 WELDER
008-1 ELECTRICIAN
008-2 ELECTRICIAN
Select personnel by code and
more entries, use the PgUp or
Code
009-1
009-2
010-1
010-2
013-1
013-2
013-3
OH-1
015-1
015-2
015-3
016-1
016-2
016-3
level (use
PgDn keys.
PERSONNEL 06/01/89
Job Category
MECHANIC
MECHANIC
CARPENTER
CARPENTER
FLD CLERK/TYPIST
FLD CLERK/TYPIST
FLD CLERK/TYPIST
ENGINEER CHEMICAL
CHEMIST ORGANIC
CHEMIST ORGANIC
CHEMIST ORGANIC
IND HYG/SAFE ENGR
IND HYG/SAFE ENGR
IND HYG/SAFE ENGR
4 digits). To see more
To exit, hit CEsc].
Search the list to find, the desired job category. This is accomplished by
using the   and  keys.  If you find the job title you are
seeking, enter its four digit code and press the < ENTER > key.  If the job
category you require is not listed, you will have to enter it, using Option
2: Adding  Non-Listed Personnel, explained on page 1-16.  Once you have
entered the job category, code, the  computer will prompt you to enter a
contractor code. The computer will then display the contractor name that
corresponds to this code, and request  that you verify the data.
                        1-14

-------
 COST PROJECTION
 ADDING LISTED PERSONNEL
 06/01/89
      Job Code and Category: 001-3  SUPERVISOR
      Contractor Code:      0002
      Contractor Name:      WESS CORP.
      Is the contractor information correct? CY/N]  Y
      Once verified, the computer will inquire whether you wish to enter or edit
      data. Depending on your answer, RCMS will continue to prompt you for
      the following rate information:

       •       Regular rate
       •       Overtime rate
COST PROJECTION
ADDING  LISTED PERSONNEL
06/01/89
     Job Code and Category: 002-1   FOREMAN
     Contractor Code:       0001
     Contractor Name:
     Enter the applicable rates below:
     Regular Rate :                  0.00
     Overtime Rate:                  0.00
      Your validation of these rates, continues the prompting process.  You will
      now be requested to enter information regarding G&A charges:
         /
      •       Are labor charges subject to G&A Charges?
      •       Are other direct charges subject to G&A Charges?
                               1-15

-------
                               Once this  information  has  been entered you  will be prompted  for the
                               following data:

                               •       Number of Employees
                               •       Number of Days on Site
                               •       Hours per Day
                               •       Per Diem, Lodging, Travel (per day, per employee)
                          COST PROJECTION
                                                    ADDING LISTED PERSONNEL
                                                     06/01/89
                              Job Code and Category: 001-1  SUPERVISOR
                              Contractor Code:      0001
                              Contractor Name:      ACME ENTERPRISES
                              Enter the following information for this job category

                              Number of Employees:                   jjf\
                              Number of Days on site:                |2(S_
                              Hours per Day:                        |B«$i
                              Per Diem, Lodging, Travel:             W$$Q
                              (per day per employee)

                              Is the above information correct?  [Y/N]  |
                       2.
Verify that  your entries are correct.  If not, enter "N* and correct the
information. If entries are right, press "Y" returning the screen to the job
category listing. The computer will now prompt you for a new job code.
When you have finished entering  listed personnel, press  to exit
this screen and return to the Cost Projection Personnel Menu.

Option 2: Add Non-Listed Personnel

Select this Option to add job categories that do not appear on the pre-
loaded list displayed in Option 1.  The following screen will be displayed:
\
                                                       1-16

-------
COST
PROJECTION
ADDING
NON-LISTED
PERSONNEL
06/01/89
   Code  Job Category               Code   Job Category
   899-9  PLUMBER
   900-0  SECURITY
   901-1  CHEMIST,TYPE 3
 This module allows you to add job categories that are NOT on the
 ERCS Personnel List.  Codes for these items are  from  1 to 999.
 Enter the code and level for the item you wish to add.  If this  code
 has been previously entered, the rates that have been entered will
 be displayed.  To see more items, use the PgUp or PgDn keys.
 To exit, hit [Esc].
      To enter a non-listed job category, begin by creating a unique three digit
      job code within the range of 1 - 999.  Enter this number, along with the
      level  for this position.   The computer will now prompt you to enter a
      contractor code.   If you are unsure of the particular code, you can review
      the list of contractors by pressing  (the list will appear in the upper
      right  hand corner of the screen). Once you have entered the appropriate
      contractor code, the computer will respond by displaying the corresponding
      contractor name, and requesting validation.  In response to your entry, the
      computer will prompt you (with  a highlighted field) to enter the Job
      Category that corresponds to your newly created Job Code.
COST PROJECTION
ADDING NON-LISTED PERSONNEL
06/01/89
     Job Code and Category: 909-9
     Contractor Code:      0001
     Contractor Name:      ACME

     Enter or edit the job class above:
                                1-17

-------
        You will now be prompted to complete the data entry required for this
        individual.  This procedure  is identical to  that described in Option  1:
        Add Listed Personnel, page 1-13, beginning with the computer prompts for
        Regular and Overtime Rates.

3.      Option 3:  Edit/View/Delete Personnel

        Select this Option to modify, review or erase individual records within the
        contractor personnel file. The program will list all the personnel records
        you have entered, along with  the appropriate projection information.  The
        Edit Menu, described briefly on page 1-8, and in greater detail in Appendix
        A, will appear at the bottom of your screen.  By choosing the appropriate
        Action Keys from this Edit Menu, and by positioning the cursor on the
        appropriate  line  of data, you  can  modify or  delete  the  displayed
        information.
COST PROJECTION
Rec
*
1
2
3
4
5
6
•• 7
Job
Code
001-1
003-1
004-1
005-1
006-1
013-1
015-1
Action keys:
Ctr
Cod*
0001
0001
0001
0001
0001
0001
0001
t*J]
• CD]
CU]

PERSONNEL
Job

Category
SUPERVISOR
CLEANUP TECH
-HAZ
LABORERS
EQUIP OPERATOR
TRUCK DRIVER
FLO CLERK/TYPIST
CHEMIST ORGANIC
Edit [T]
Delete in
Undelete IF2]
No.
Employees
1
5
2
2
2
1
1
Previous record
Next record
Extended edit
Days
06/01/89
Hours
on Site per
10
10
10
10
8
10
4
[PgUp]
[PgDn]
CEscl
10.
10.
10.
10.
8.
10.
10.
Day
0
0
0
0
0
0
0
PD, Lodge
Travel
45.00
45.00
45.00
0.00
0.00
45.00
45.00
Previous page
Next page
Quit
       a.
               Extended Edit
               The  Edit  Menu  displayed  here,  and  in  most  subsequent
               Edit/View/Delete  Options within the Cost  Projection module,
               contains an Extended Edit function, accessed by pressing .
               This function enables you to view and modify data not shown on
               the main edit screen.  Pressing  will result in the Extended
               Edit Options Menu being displayed in the upper right hand comer
               of the screen.  You now have a choice of editing options.

               1.      Option 1: Edit Contractor Code and Rates

                      Accessing this Option allows  you to manually edit the
                      personnel rates.
                                1-18

-------
  COST PROJECTION
Rec
 *
Job
Code
Ctr
Cod«
  Job
Category
  1  001-1   0001    SUPERVISOR
  2  009-1   0002    MECHANIC
  3  899-9   0002    PLUMBER
  4  900-0   0002    SECURITY
  5  901-1   0002    CHEMIST,TYPE 3
                                    i—  PERSONNEL RATE EDITING
Edit the following rate
information  if you ui*h:
                                Contractor Code:
                                Regular Rate  :
                                Overtime Rate:
                                G I A rate:

                                G I A on labor?  [Y/N]
                                G t A on other costs? [Y/N]
                                                       ACME
                                                      43.00
                                                      64.00

                                                      10.00 X
                                          Is  this correct? [Y/N]  Y
                           EXTENDED EDITING MODE
               2.       Option 2: Load Contractor Rates

                        This Option enables you to substitute rates from a different
                        contractor.  A list of contractor codes and the associated
                        rates for the selected personnel category will be displayed.
                        Enter the contractor code that corresponds to the desired
                        rate set, or simply press < ENTER > to exit without making
                        changes.

       Note: This Option will change the rates for the selected personnel category
       onfy.  Other entries in the current personnel list will not be affected.
                                 1-19

-------
   COST PROJECTION
 Rec  Job
  *   Code
CtP
Code
  Job
Catego
   1  001-1
   2  009-1
   3  899-9
   4  900-0
   5  901-1
0001   SUPERV1
0002   MEGHANI
0002   PLUMBER
0002   SECURIT
0002   CHEMIST
                                      -CONTRACTOR RATE SELECT
Ctr
Code

ACME
DRUM
Regular
 Rate

 76.17
 90.24
Overtim
 Rate

 76.17
 90.24
           Enter Contractor Code:
           Enter a blank to exit
        b.      Delete a Personnel Entry

                The delete function is explained on page 1-8.  To review, position
                the cursor on the line of the personnel category you wish to delete,
                and press  "D".  You will be prompted to verify this choice. You
                have the capability to restore an individual (or any data) to the file
                by pressing "U" (the "Undelete" response) providing you have not
                left the Edit/View/Delete section.

        REMEMBER!  Once you press the  key to exit the Edit/ViewlDelete
        section, data cannot be restored to the file using the Undelete Option.  Data
        must be re-entered manually.
                                                                                   •'-*
                                                                                   •I
4.      Option 4: Update Current Scenario Personnel Rates

        This Option allows you to load different sets of personnel rates into your
        current personnel file and thus update all entries in the personnel list with
        the selected contractor rates.  The computer will prompt you for the code
        that corresponds to the contractor whose rates you wish to load into  the
        current personnel list
                                 1-20

-------
COST
PROJECTION
UPDATE
PERSONNEL
LIST
RATES
06/01/89
                    Contractor selected: 1001   UASTEBUSTERS

            The rates for the contractor listed above will be loaded into the
                           current scenario personnel file

                            Do you wish to continue ? [Y/N] f
            Note: This Option and the corresponding one for contractor equipment provide
            a simple means for preparing multiple cost projections for one scenario using
            different cleanup contractors.
        5.      Option 5: Delete All Personnel Entries

               This Option allows you to delete all personnel category entries at once,
               rather than having to delete each individually while in the Edit/View/Delete
               Option.  You  will be prompted for the necessary information.


E.      Option  5:  Update Contractor Equipment File

        Select this Option for updating the Cleanup Contractor Equipment Files.  The
        program will respond by displaying the Cost Projection Equipment Menu.

        This Menu provides you with the option of adding, editing, viewing, or deleting
        entries within the Equipment File.  Equipment can be added as either Listed or
        Non-Listed.
                                       1-21

-------
  COST PROJECTION
EQUIPMENT MENU
06/01/89
       1.  Add Listed Equipment

       2.  Add Non-Listed Equipment

       3.  Edit/View/Delete Equipment

       4.  Update Current Scenario Equipment Rates

       5.  Delete All Equipment Entries

       0.  Return to the Previous Menu

          Your Choice:
I.       Option 1: Add Listed Equipment

        The computer will respond  to  this Option with a list of code numbers
        accompanied by a corresponding equipment type.
                                                                                               •A
                                                                                                t
                                                                                               V
COST PROJECTION ADDING
Code Item Name
040 TRUCK VAC 5000 GAL
041 TRUCK VAC 3500 GAL
042 TRUCK VAC 1800 GAL
043 TRUCK PICK UP
044 TRUCK 4 WHEEL DR
045 TRUCK STAKEBED 2 TON
046 TRUCK STAKEBED 1 TON
047 TRUCK TANK 5000 GAL
048 TRUCK WELDER
049 TRUCK BOX 2 TON
050 TRUCK LIFT 30 FT
051 TRUCK DUMP/VAC 3800G
052 TRUCK DUMP HWY 5-10Y
053 TRUCK DUMP HWY 10-20
Select equipment by code (use 3
items use the PgUp or PgDn keys
LISTED EQUIPMENT
Code Item Name
06/01/89

057 TRLR EMERGENCY RES
061 TRLR DECON 8X40
062 TRLR DECON 8X25
063 TRLR OFF 8X40 EQUIP
064 TRLR OFF 8X40
065 TRLR OFF/STOR 8X20
066 TRLR STORAGE
068 TRLR FLATBED 42 FT
069 TRLR WATER 500 GAL
070 TRLR TK GALV 5000G
071 TRLR TK 5000G GLASS
072 TRLR TK 5000G RUBBE
073 TRLR TK GLV 7500G
074 TRLR TK 7500G RUBBE
digits). To see more,
. To exit, hit [Esc].
m
       Search this list to locate the equipment desired.  If the list is too extensive
       to display on a single screen, you can access it in its entirety by using the
         and    keys.   Once  you have located the  correct
       equipment type, enter its  three digit code. The  computer will respond by
       requesting entry of a contractor code.  Remember, you can access a list of
       contractor codes by pressing .  Once you have entered the contractor
                                                              S
                                1-22

-------
       code the computer screen will display the corresponding contractor name
       and require your validation of this data.
COST PROJECTION
                          ADDING LISTED EQUIPMENT
     Equipment Code and Name Selected: 975  TOW TRUCK
     Contractor Code: 0001
     Contractor Name: ACME
     la the contractor information correct?  [Y/N] Y
06/01/89
      You will now be prompted to enter the number of equipment items.
COST PROJECTION
                         ADDING LISTED EQUIPMENT
06/01/89
     Enter the category name below:
      Equipment Code: 975  Category Name:  TOW TRUCK
     Contractor Code: 0001
     Enter number of Equipment Items  1
     (Enter zero [0] if you do not wish to add this  item.)
      Next, you will be prompted for the following:

      •       Hourly, Daily, Weekly, & Monthly Rate
      •       Purchase Price
      •       Mileage Charge
      •       Mob/Demob Rate
      •       Standby Rate
      •       Decon Rate

      The computer will display any default rates that exist for this item. If there
      is no default value for a particular rate, a zero will be displayed.
                               1-23

-------
COST PROJECTION
199 DRILL RIG
ADDING LISTED EQUIPMENT
Ctr Code:
Please enter the appropriate
If a particular rate does not
Hourly Rate :
Weekly Rate:
Purchase Price:
Nob/Demob Rate:
Decon Rate:
43.00
1500.00
45000.00
3 X
10 X
Is the above information
06/01/89
0001 Ctr Name: SMITHON INC.
rates below for this item
apply - Leave as zero [0]
Daily Rate: 400.00
Monthly Rate: 5000.00
Mileage Charge: 0.78 per mile
Standby Rate:

correct? [Y/N] Y
10 X


2.
After the above information has been entered the computer will request
the number of regular and standby days you expect the item to be used.

Once all required information  is entered and verified, the program will
return to the Adding Listed Equipment screen. When you have finished
adding items to the equipment  file, press   to exit.

If you are entering an equipment type that has previously been entered, its
rates will appear  on the screen. You will then have the option of using
those rates by entering "U", or editing them by entering "E".

Note: Some rates  or charges may not be applicable for a particular piece of
equipment.  In that instance, the proper response is to enter the default value
of'O.'

Option 2: Adding Non-Listed Equipment

Select this Option to add equipment that is not already on the contractor
equipment list.  The Adding Non-Listed Equipment screen will be displayed.
                                                                                                 I
                                                                                                 •p
                                                                                                 I
                                                                                                 •£
                                                                                                 '£•*?
                                                                                                 Si
                                1-24
                                                                                                t
                                                                                                i

-------
COST
PROJECTION
ADDING
NON-LISTED
EQUIPMENT
06/01/89
       Code Item Name                 Code Item Name
       800  LH SMOKE SHIFTER
   This module allows you to add equipment items that are not on the
   ERCS equipment  list.  Codes for these items are from   1 to 999.
   Enter the code  for the item you wish to add.  If this code has
   been previously entered, the rates that have been entered will
   be displayed.   To see More items, use the PgUp or PgDn keys.
   Otherwise, hit  [Esc] to exit.                        "'"••
        To enter a non-listed piece of equipment, first create and enter a unique
        three digit equipment category code within the range of 1 - 999.  You
        will then be prompted to enter a contractor code, as well as the name of
        the particular equipment type. The remainder of the procedure is the
        same as that described  on page 1-22  for  Option  1:   Adding Listed
        Equipment

        The  first time you add a non-listed  item,  its default rates will be  zero.
        The  next time it is selected, the rates you have entered will be  displayed
        as the default rates.

3.      Option 3: Edit/View/Delete Equipment

        Elect this Option to modify, review, or erase individual records within the
        Contractor Equipment File entries.

        Note:   The Edit Menu  is  described briefly on page 1-8.   An in-depth
        explanation of the mechanics of the Edit/ViewIDelete  Option is  found in
        Appendix A.
                                 1-25

-------
                                                                                                    .$•
                                                                                                    •w
COST PROJECTION
EQUIPMENT
Rec Item Ctr Reg
* Code Code Name Days
1 124 0002 ANYL OVA- FID 1
2 043 0002 TRUCK PICK UP 10
Action keys: I*1] Edit [T] Previous record
[D] Delete [1] Next record
[U] Undelete [F2] Extended edit
Stby M/Dmob
Days Hrs
06/01/89
Decon Total
Hrs Miles
0 0.0 2.0 45
2 0.0 10.0 220
[PgUp] Previous page
[PgDn] Next page
[Esc] Quit
                                                                                                    I
               Extended Edit

               This function is explained and illustrated on page 1-18.  To review the Ex-
               tended Edit function, accessed by pressing , allows you to view and
               modify data not shown on the main edit screen.  Data will be displayed in
               the upper right hand corner of the  screen.  The  options are similar to
               those  described for editing personnel entries.   Equipment  rates can be
               edited  manually, or you can load in rates for a specific contractor by
               entering the appropriate three-digit contractor code.

               Option 4: Update Current Scenario Equipment Rates

               This Option enables you to substitute a different  set of contractor rates
               into all the entries in your current equipment list. It operates in a manner
               similar to the procedure described for loading rates into the personnel file.
               The computer will  prompt you for the  necessary information.

               Option 5: Delete All Equipment Entries

               Select this Option to delete all  equipment entries at once,  instead of
               deleting each one individually in the  Edit/View/Delete  section.
F.     Option 6:   Update Contractor Expendable  Materials  File

       Option 6 allows you to update the Expendable Materials File. The computer will
       respond to  this Option  by  displaying the Update Expendable Materials  Menu
       which  gives  you the choice of updating either the Rate Materials File or the At
       Cost Materials  File.
                                       1-26

-------
   COST PROJECTION
UPDATE EXPENDABLE MATERIALS MENU
06/01/89
       1. Update Unit Rate Materials File

       2. Update At Cost Materials File

       0. Return to Previous Menu

          Your Choice:
The Unit Rate Materials File is recommended for items expended in units on a
periodic basis (e.g., Tyvek suits, filter cartridges, disposable gloves, etc).  The At
Cost Materials File is appropriate for one time or infrequent purchases (e.g., cinder
blocks, lumber, coolers, etc.).

1.      Option 1:  Update Unit Rate Materials File

        This Menu within Option 6 allows you to add, view, edit, or delete entries
        within the Unit Rate Materials File.
     COST PROJECTION
                                 UNIT RATE MATERIALS MENU
                                      06/01/89
          1.  Add Entries to Unit Rate Materials File

          2.  Edit/View/Delete Unit Rate Materials Entries

          3.  Update G ft A Rate for all Entries

          4.  Delete All Current Unit Rate Materials Entries

          0.  Return to Previous Menu


             Your Choice:
                                 1-27

-------
      a.      Option 1: Add Entries to Unit Rate Materials File

             You will be prompted to provide the following information:

             •       Name of Material
             •       Contractor Code
             •       Purpose
             •       Unit Name (gal., Ibs., etc)
             •       Number of Units
                     Unit Cost
                     G&A Charge
COST PROJECTION
ADDING UNIT RATE MATERIALS
06/01/89
              Please Enter the Following  Information
     Name of Material:
     Contractor:

     Purpose:
     Unit Name (gal,Ibs, etc.):
     Number of Units:
     Unit Cost:

     G&A Charge:

     Cost for this entry:
     G A A Charge:
     Total Cost:
      VISQUEEN
      0001     ACHE ENTERPRISES

      DECON
      ROLLS
      50.0
      $ 27.50

      YES, AT 5.65X

      $ 1375.00
      $ 77.69
      $ 1452.69
     Is the above information correct? tY/N]  Y
                                    .!,-
                                    • . *,i

                                    If
             The RCMS program then will calculate the total cost and display
             the result

             The prompting will now begin again requesting 'Name of Material".
             If you are through entering material, press  to return
             to the Unit Rates Material Menu.

     b.      Option 2:  Edit/View/Delete Unit Rate Materials File

             Select this  Option to modify, review or delete individual records
             within the  Unit Rate Materials File.  By using the appropriate
             Action Keys from the Edit Menu, and by placing the cursor on the
             appropriate line of  information,  you can modify or  delete the
             displayed information. The Edit Menu is explained briefly on page
             1-8. The Extended Edit function is explained on page 1-18.  Both
             are discussed  in greater detail in Appendix A.
                              1-28

-------
   COST PROJECTION
                               UNIT
 Rec
       Expendable
                 Use
   1   10 C NAILS
   2   25 C NAILS
   3   SOUND BOARD
   4   VISQUEEN
                 BUILDING
                 BUILDING
                 SOUND PROOFI
                 DECON
                                            CONTRACTOR/EDITING
    Edit the following for this
       item if  you wish:

Contractor code:  0001

G & A rate:        5.65  X
                           EXTENDED EDITING MODE
2.
 c.      Option 3:  Update G&A Rates For All Entries

        This Option allows you to substitute another contractor's rates for
   ;     the current entry within the Unit  Rate Materials File.   This
        procedure will update  all Unit Rate Materials in the current  list
        with the contractor  G&A you specify.  If you wish  to  modify
        individual entries, use Option 2:  Edit/View/Delete.  The computer
        will prompt you for the needed data.

 d.      Option 4: Delete All Current Unit Rate Material Entries

        This Option allows you to delete all Unit Rate Material entries at
        once, rather than using Option 2: Edit/View/Delete to delete each
        entry individually.  This Option does not have a separate screen.
        Instead the computer prompt will appear beneath  the  Unit  Rate
        Materials Menu.

Option 2:  At Cost Materials Menu

This Menu offers you the option of adding, editing, reviewing or deleting
entries within the At Cost Materials File.  The structure of this section is
similar to that  of the Unit Rate Materials section (see Option 1  above,
page  1-28).  It differs  only in the specific prompts requested by the
computer.
                                1-29

-------
COST PROJECTION
UPDATE AT COST MATERIALS MENU
06/01/89
     1. Add Entries to At Cost Materials File

     2. Edit/View/Delete At Cost Materials Entries

     3. Update G A A Rate for all Entries

     4. Delete All Current At Cost Materials Entries

     0. Return to Previous Menu


     Your Choice:
   a.      Option 1: Add Entries to At Cost Materials File

   ;       The computer will prompt you for the following information when
          you chose this Option:

          •      Name of Material
          •      Contractor Code
          •      Purpose
          •      Quantity/Amount
          •      Purchase Cost
          •      G&A Charge

          As in the Unit Rates Materials File mode, the RCMS system will
          compute  total cost
                                                                  •t.
                           1-30

-------
COST PROJECTION
ADDING AT COST MATERIALS
06/01/89
              Please Enter the Following Information:
              (Enter a blank to exit)

     Name of material:            $*$&**£   7:%
     Contractor:                  $$f     ACNE ENTERPRISES

     Purpose:
     Ouant i ty/Amount:
    Purchase Cost:

    G t A Charge:                YES,  AT  10.00X

    Total Charge:                $ 880.00

    Is the above  information correct? [Y/N] $
             To return to the At Cost Materials File, simply press 
             when the prompts begin again.

     b.      Option 2: Edit/View/Delete At Cost Materials File

             Select this Option to modify, review or delete individual records
             within the At Cost Materials File.  By using the appropriate Action
             Keys  from the Edit  Menu, and by placing  the cursor on the
             appropriate  line of information, you can  modify or delete the
             displayed information.  The Edit Menu is explained briefly on
             page 1-8.  The Extended Edit function is explained on page 1-18.
             Both are discussed in greater detail in Appendix A.
                              1-31

-------
  COST PROJECTION
                            EDITING
Rec
 f  Item Name
                     Use
  1 CINDER BLOCKS
  2 COOLER
BUILDING
REFRIGERATION
                                           CONTRACTOR/EDITING
    Edit the following for this
       item if you wish:

Contractor code:  0001

G & A rate:         5.65  X
                    ***   EXTENDED EDITING MODE   ***
                                                                                               •-&
               Option 3: Update G&A Rates For All Entries

               This Option allows you to substitute another contractor's rates for
               the current entry within the At Cost Material File. This procedure
               will update all Unit Rate Materials in the current  list with the
               contractor G&A you specify.   If you wish to  modify individual
               entries, use Option 2: Edit/View/Delete. The computer will prompt
               you for the needed data.

               Option 4: Delete All Current At Cost Material Entries

               This Option allows you to delete all At Cost Material File entries
               at once, rather than using Option 2: Edit/View/Delete to delete each
               entry individually.  This Option does not have a separate  screen.
               Instead the computer prompt will appear beneath the Unit Rate
               Materials Menu.
                               1-32

-------
G.    Option 7:  Update Subcontractor File

       When you select Option 7, the Update Subcontractor Menu will be displayed.
            COST PROJECTION
UPDATE SUBCONTRACTORS MENU
06/01/89
                 1. Add Subcontractor Entries

                 2. Edit/View/Delete Subcontractor Entries

                 3. Update G I A Rate for all Entries

                 4. Delete All Subcontractor Entries

                 0. Return to Previous Menu


                   Your Choice:
               Note: It is recommended that you enter transportation and disposal costs, even
               when these rates are provided by a subcontractor in the Update Transportation
               and Disposal File.
       This menu provides you with the option of adding, editing, viewing or deleting
       entries within the subcontractor file by choosing one of two menu options.

       1.      Option 1: Add Subcontractor Entries

               The computer will prompt you for the following information:

               •      Subcontractor Name
               •      Contractor Code
               •      Subcontractor Service
               •      G&A Charge (requires a "Y" or "N" response)
               •      Subcontractor Cost
                                       1-33

-------
                                                                                                I
  COST PROJECTION
ADDING SUBCONTRACTORS
06/01/89
                Please Enter the Following Information
                (Enter a Blank to Exit):
       Subcontractor Name:

       Contractor:

       Subcontractor Service:

       Subcontractor Cost:
     RED ROOF INN

     0001      ACNE ENTERPRISES

     LODGING

       4450.00
       Is there a G & A charge on this subcontractor cost? [Y/N]   Y
                                                                                                •;.t

                                                                                                 ?l
                                                                                                 jV
                                                                                                vi:"
        Once this information is completed, the RCMS system will compute the
        total charges.

        After this information is entered and verified, the program will respond by
        returning to the "Subcontractor Name" prompt screen.   Once finished
        adding entries to the file, press  to exit this Option and return
        to the Update Subcontractors Menu.

2.      Option 2: Edit/View/Delete Subcontractor Entries

        Select this Option to modify, review or erase individual records within the
        subcontractor site. The program will list all subcontractor records previously
        entered, along with the appropriate projection information.
        Note: This Option is explained briefly on page 1-8, and in detail in Appendix
        A. An explanation of the Extended Edit Option can be found on page 1-18.
                                                                                                'I-
                                                                                                •4-
                                                                                                 '
                                                                  :&
                                                                  $
        Option 3: Update G&A Rate For All Entries

        This Option allows you to substitute another contractor's rates for those
        in the current subcontractor file.  This procedure updates all subcontractors
        in the current file with the contractor G&A specified by you.  Entries can
        be modified individually using Option 2, above. The computer will prompt
        you for all necessary data.

        Remember!  If you are unsure of a contractor's code, press  to display
        the complete contractor list in the upper right hand comer of the screen.
                                 1-34

-------
        4.      Option 4: Delete All Subcontractor Entries

               This Option allows you to delete all subcontractor entries at one time,
               rather  than using Option  2, above, to delete each individually.  The
               computer will  prompt you for the necessary data.  This Option does not
               have a separate screen, rather the prompt will appear beneath the Update
               Subcontractors Menu.

H.     Option 8:  Update Transportation and Disposal Files

        Select this Option to enter or update the Transportation and Disposal Files.  The
        Transportation and Disposal Menu is displayed when you choose this Option, and
        offers you the  choice  of updating the Waste Transportation File or the Waste
        Disposal  File.   Select the desired option and the appropriate menu will be
        displayed.
            COST PROJECTION
TRANSPORTATION AND DISPOSAL MENU
06/01/89
                 1. Update Waste Transportation File

                 2. Update Waste Disposal File

                 0. Return to Previous Menu


                   Your Choice:
       1.      Option 1:  Update Waste Transportation Menu

               This  Menu gives you the option of adding, editing, viewing or deleting
               waste transportation entries.
                                       1-35

-------
COST PROJECTION
                       UPDATE WASTE TRANSPORTATION MENU
06/01/89
     1. Add Transportation Entries

     2. Edit/View/Delete Transportation Entries

     3. Update G I A Rate for all  Entries

     4. Delete All Transportation  Entries

     0. Return to Previous Menu


       Your Choice:
   a.      Option 1: Adding Transportation Subcontractors Entries

          You will be prompted for the following information:

          •       Waste "type (name of material)
          •       Contractor Code
          •       Waste Amount/Quantity
          •       Cost per Loaded Mile
          •       Transport Distance (miles)
          •       Number of Loads

          RCMS  will  calculate  and display  Transport  Cost" from  this
          information.   You  will  then be asked if G&A applies.   The
          computer will  calculate  the Total Charge* based upon your
          response.

          After you have finished adding transportation entries position the
          cursor  on a  blank response, and press the < ENTER>  key to
          return to the Update Waste Transportation Menu.
                           1-36

-------
COST PROJECTION
ADDING TRANSPORTATION SUBCONTRACTORS    06/01/69
              Please Enter the Following Information:
              (Enter a blank to exit)

     Uaste Type:                 SOULVENTS
     Contractor:                 0001      ACME ENTERPRISES

     Uaste Amount/Quantity:       2498 GA
     Cost per Loaded Mile:          0.52
     Transport Distance (miles):     23
     Nunber of Loads:               4

     Transport Cost:              $47.84
    G & A Charge:                5.65X
    Total Charge:                $ 50.54

    Is the above information correct? [Y/N] Y
     b.      Option 2:  Edit/View/Delete Transportation Entries

             Select this Option to modify, review or erase individual records
             within the Waste Transportation File.  The program will list all
             file entries.  The Edit  Menu is  explained on  page 1-8.  The
             Extended Edit function is defined on page 1-18. Both are discussed
             in detail in Appendix A.

     c.      Option 3:  Update G&A  Rates For All Entries

             This Option allows you to substitute another contractor's rates for
             the current entry within the Waste Transportation list.   This
             procedure will update all entries with the G&A Rate you specify.
             If you   wish   to  modify individual  entries,  use  Option  2:
             Edit/View/Delete Transportation Entries.    The computer will
             prompt you for the necessary information.

     Remember!  If you are  unsure of a contractor code, by pressing  the
     computer will display the contractor list in the upper right hand comer.
     d.       Option 4:  Delete All Transportation Entries

             This Option  allows you to eliminate all  Waste  Transportation
             entries at  once, rather than deleting  each individually using the
             Edit Option (Option 2, above).  The computer will prompt you for
             the  necessary information.  This Option does not have a separate
             screen, rather the computer prompt will appear beneath the Update
             Waste Transportation.
                              1-37

-------
   Option 2: Waste Disposal Options Menu

   This menu offers the option of adding, viewing, editing, or deleting waste
   disposal entries.
                                                                 i
COST PROJECTION
WASTE DISPOSAL OPTIONS MENU
06/01/89
     1. Add Entries to Haste Disposal  File

     2. Edit/Viw/Delete Waste Disposal Entries

     3. Update G t A Rate for all Entries

     4. Delete all Current Waste Disposal Entries

     0. Return to Previous Menu


       Your Choice:
          Option 1: Add Entries to Waste Disposal File

          You will be prompted for the following information:

          •       Waste Type (name of material)
          •       Contractor Code
          •       Disposal Method
          •       Unit Name (gal, Ibs., drums, etc.)
          •       Number of Units
          •       Unit Cost
          •       G&A Charge
                           1-38

-------
COST PROJECTION
                           ADDING DISPOSAL OPTIONS
06/01/89
              Please Enter the Following Information
     Waste Type:
     Contractor:                 jiHfl      ACHE ENTERPRISES
     Disposal Method:
     Unit Name (gal.lbs, druns, etc.):  GftL       .. ;  "
     Nuifcer of Units:                  20QOO
     Unit Cost:                       * 6.^5

     G&A Charge:                     YES,  AT  10.00X

     Cost for this  entry:              $ 19000.00
     G&A Charge:                     $ 1900.00
     Total Cost:                       $ 20900.00

     Is the above information correct? [Y/N]   If
             RCMS will then calculate and display:

             •  Cost  for this entry
             •  G&A Charge
             •  Total cost

             After you have finished adding waste disposal entries, position the
             computer on a blank field and press the < ENTER > key to return
             to the Waste Disposal Options Menu.

     b.      Option 2:  Edit/View/Delete Waste Disposal File

             Select this Option to modify, review or delete individual entries
             within the Waste Disposal Options File. This program will display
             all current entries in the file.  The Edit Menu is explained on
             page  1-8.   The Extended Edit function is defined  on page  1-18.
             Both  are discussed in greater detail in Appendix A.

     c.       Option 3:  Update G&A Rate For All Entries

             This Option allows you to  substitute another contractor's  G&A
             rate  for  the current rate  in  the  Waste Disposal  File.   This
             procedure will update all disposal entries in the current file with
             the rate you specify. To modify entries individually, use Option 2,
             Edit/View/Delete Waste  Disposal File. The computer will prompt
             you for all necessary information.
                              1-39

-------
r               Remember! If you are unsure of a contractor's code, press  to display
               the complete contractor list in the screen's upper right hand comer.
               d.      Option 4:  Delete All Current Waste Disposal Entries

                       This Option allows you to eliminate  all current Waste Disposal
                       entries at one time, rather than using  the edit function in Option
                       2, above, to delete each individually.  The computer will prompt
                       you for the necessary information. This Option does not have its
                       own screen, rather the computer  prompt will appear beneath the
                       Waste Disposal Options Menu.

I.      Option 9:  Update EPA Cost File

        Select Option 9 to update projected EPA costs. The computer will respond to this
        selection by displaying the EPA Personnel Menu.
               Note: The program will continue to remind you to enter the EPA hourly labor
               rates until you have done so by using Option 3: Update EPA Rates.
       From this screen you have the option of adding, editing, viewing and deleting
       information regarding EPA personnel rates. Rates must be entered first to provide
       the program with the default information required for calculating EPA costs.
                                                               Sr'

                                                               ~.i
                                                                                                     .&

          COST PROJECTION
EPA PERSONNEL MENU
06/01/89
                  1. Update Regional  EPA Personnel

                  2. Update Non-Regional EPA Personnel

                  3. Update EPA Rates

                  0. Return to Previous Menu

                     Tour Choice:
                                       1-40

-------
1.      Option 3: Update EPA Rates

       Choosing this Option will result in the computer prompting you for the
       following information:

       •       Regional Direct Hourly Rate
       •       Regional Indirect Hourly Rate
       •       Headquarters Hours Percentage
       •       Headquarters Hourly Rate
  COST PROJECTION
UPDATE EPA RATES
06/01/89
      Current  EPA Rates:
      Regional Direct Hourly Rate:
      Regional Indirect Hourly Rate:

      Headquarters Hours Percent:
      Headquarters Hourly Rate:
           Do you wish to edit this  information? tY/N]  |
       The Comptroller's Office has instructed the Superfund program to project
       EPA Headquarters Direct Costs for any removal action as equal to 10%
       of total Regional Direct Costs.  This percentage should be verified with the
       Regional Financial Management Office (FMO).

       The Regional Direct and Indirect Rates are determined on a periodic basis.
       The  Regional Indirect Hourly Rate  is  used  to account for  Regional
       administrative and overhead costs charged to the site.  As these rates are
       subject to change by the Comptroller's office, they should be periodically
       verified with the FMO.

       Option 1: Update Regional  EPA Personnel

       This  Option  allows you  to update projected  Regional  EPA  personnel
       information within the EPA cost files.   The computer  will respond by
       displaying the Regional EPA Personnel Menu.
                               1-41

-------
COST PROJECTION
REGIONAL EPA PERSONNEL MENU
06/01/89
         1.  Add Regional EPA Personnel

         2.  Edit/View/Delete Regional EPA Personnel

         3.  Delete All  Regional EPA Personnel Entries

         0.  Return to Previous Menu

            Your Choice:
     a.      Option 1:  Add Regional EPA Personnel Menu

             Select Option  1 from the Regional EPA Personnel Menu to add
             projected Regional EPA personnel to the EPA cost files. You will
             be prompted to enter the following information:

                    Job Title
             •      Hourly Rate
             •      Hours per Day
             •      Number of days charged
             •      Per diem, lodging, travel (per day)

             Once all data has been entered, press  to return to the
             Regional EPA Personnel Menu.
                              1-42

-------
      COST PROJECTION
                              ADDING REGIONAL EPA PERSONNEL
06/01/89
                   Please Enter the Following Information
          OSC                                  OSC

          Hourly Rate:                          45.00
          Hours per day                         10.0
          No. Days charged to Project:            23
          Per Diem, Lodging,Travel:              46.00
          (per day)
          Is the above information correct? [Y/N]  Y
        b.      Option 2: Edit/View/Delete EPA Personnel

                Select this Option to modify, review or erase individual records
                within the Regional EPA Personnel file. The program will display
                all current file entries.  The Edit Menu is explained on page 1-8.
                The Extended Edit function is defined on page  1-18. Both are
                discussed in  Appendix A.

        c.       Option 3: Delete All Regional EPA Personnel Entries

                This function allows you to eliminate all entries within the Non-
                Regional EPA Personnel file at once, rather than deleting each
                individually using the Edit/View/Delete Option. The computer will
                prompt you  for all necessary information.

3.      Option 2: Update Non-Regional EPA Personnel

        Select this Option from the  EPA Personnel Menu to update projected
        Non-Regional  EPA personnel in the EPA cost files.  The Non-Regional
        EPA Personnel Menu will be displayed.
                                1-43

-------
             COST  PROJECTION
                                   NON-REGIONAL EPA PERSONNEL MENU
06/01/89
                      1.  Add Non-Regional EPA Personnel

                      2.  Edit/View/Delete Non-Regional EPA Personnel

                      3.  Delete All Regional EPA Personnel Entries

                      0.  Return to Previous Menu

                         Your Choice:
                a.      Option 1: Add Non-Regional EPA Personnel

                       Select this Option  to  add Non-Regional  EPA Personnel (e.g.,
                       Environmental Response Team [ERTJ) to the EPA cost files. The
                       information requested is the same as for Option 1: Add Regional
                       EPA Personnel, page 1-42.

                b.      Option 2: Edit/View/Delete Non-Regional EPA Personnel

                       Select this Option to modify, review or delete individual records
                       within the Non-Regional EPA Personnel file. The program will
                       display all current file entries.  The  Edit Menu functions  are
                       described on page 1-8.  The Extended Edit  function is defined on
                       page 1-18.  Both are discussed in detail in  Appendix A

               c.      Option 3: Delete All Non-Regional EPA Personnel Entries

                       This function allows you to eliminate all entries within the Non-
                       Regional EPA Personnel file at  once, rather  than deleting each
                       individually using the Edit/View/Delete Option. The computer will
                       prompt you for all necessary information.

J.      Option 10:   Update TAT Cost  Files

        Select this Option to update  projected TAT (Technical  Assistance Team) costs,
        including those for personnel, special projects, and analytical services. This Option
        will display the Cost Projection, TAT Main Menu.
                               *«

                               f
                                       1-44

-------
      Note: The program will continue to remind you to enter the TAT rates until you
      have done so by using Option 4, Update TAT Rates, from the TAT Main Menu.
   COST PROJECTION
          UPDATE TAT RATES
06/01/89
                       Current TAT  Information:
TAT Contractor:
Admin Multiplier:

Hourly Rates:

Tech 1:
Tech 2:
PL 1:
PL 2:
PL 3:
PL 4:
Adm. Staff:
Fully Loaded:
                                            ICGtOfiY
                                        mtm

               Do you wish to edit  these Rates? [Y/N]  N
From this screen you may choose to update the TAT personnel, special projects,
and/or the analytical services files. An additional option allows you to update the
TAT rates. It is suggested that these rates be entered first to supply the program
default  information required for calculating TAT costs.
                                 1-45

-------
        Option 4: Update TAT Rates

        The computer will prompt you for the following information:

        •      TAT Contractor Name
        •      Administrative Multiplier
        •      Tech Staff hourly  rates
        •      PL hourly rates
        •      Administrative Staff hourly rates
        •      Fully Loaded rates

        Note:   The administrative  multiplier,  PL rates, and /ulty loaded rates are
        explained in detail in Chapter 4, Daify Cost Summary, the ROMS glossary
        and the Removal Cost Management Manual

        You only need to enter rates for the level of TAT personnel you  expect
        to use at the projected site.   As per  the Removal Cost Management
        Manual, PL rates  should be used over the fully loaded rates to give a more
        accurate cost projection.
  COST PROJECTION
UPDATE TAT RATES
06/01/89
                      Current TAT  Information:

                      TAT Contractor:
                      Admin Multiplier: 1.0000
                       Hourly Rates:

                       Tech 1:
                       Tech 2:
                       PL 1:
                       PL 2:
                       PL 3:
                       PL 4:
                       Adm. Staff:
                       Fully Loaded:
        0.00
        0.00
        0.00
        0.00
        0.00
        0.00
        0.00
        0.00
              Do you with to edit  these Rates? [Y/N]  M
2.      Option 1: Update TAT Personnel

        Select this  Option to update projected TAT personnel within the TAT
        costs files.  This Option will display the TAT Personnel Menu.
                                1-46

-------
COST  PROJECTION
                             TAT PERSONNEL MENU
06/01/89
         1. Add TAT Personnel

         2. Edit TAT Personnel

         3. Delete All  TAT Personnel Entries

         0. Return to Previous Menu

            Your Choice:
     8.      Option 1: Add TAT Personnel

             Option 1 permits you to add projected personnel to the TAT
             personnel  file.    You  will  be prompted  for the  following
             information:

                    TAT Level
                    Number of TATs
             •      Number of days  charged to project
             •      Hours per day
             •      PL  rate (P) or Fully Loaded rate (F)

             If you choose the PL  rate the computer will prompt you to enter
             projected values for:

             •      Hourly Rate
             •      Per Diem, Lodging, Travel
                             1-47

-------
   COST PROJECTION
                        ADDING TAT PERSONNEL
06/01/89
                 Please Enter the Following Information
       PL1
       Member of  TATs:
       Number of  Days charged to Project:
       Hours per  Day:

       Hourly Rate:
       Per Diem,Lodge,Travel:
                                      14.00
                                      46.00
       Is the above information correct? [Y/NJ  Y
                                             1
                                            20
                                            10
3.
b.      Option 2:  Edit TAT Personnel

        Select this Option to edit, review or erase individual entries within
        the TAT Personnel File. This program will display all current file
        entries. The Edit Menu functions are explained on page 1-8. The
        Extended Edit functions defined on page 1-18.   For a detailed
        explanation of both, see Appendix A.

c.      Option 3:  Delete All TAT Personnel Entries

        This function  allows you to eliminate  all the  entries in  the TAT
        Personnel file at once, rather than deleting each individually using
        the Edit Option, above.  The computer will  prompt you for all
        necessary information.

Option 2: Update TAT Special Projects

The TAT Special Projects  Menu will be displayed.  This Option permits
you to add projected TAT special projects.
                                 1-48

-------
   COST PROJECTION
TAT SPECIAL PROJECTS MENU
06/01/89
            1. Add TAT Special Projects

            2. Edit TAT Special Projects

            3. Delete All TAT Special  Project Entries

            0. Return to Previous Menu


              Your Choice:
        a.      Option 1: Add TAT Special Projects

                Select Option 1 to add TAT Special Projects. The computer will
                prompt you for the following:

                •      Special Project Description
                •      Special Project Amount

                Once all  data is entered, press < ENTER > to return to the TAT
                Special Projects Menu.

        b.      Option 2: Edit TAT Special Projects

                Select this Option to edit, review or erase individual entries within
                the  TAT Special  Projects  File.   This program will  display all
                current file entries. The Edit Menu functions  are explained on
                page 1-8.  For a detailed explanation, see  Appendix A

        c.       Option 3:  Delete  All TAT Special Project  Entries

                This function allows you to eliminate all the entries in the TAT
                Special Projects file at once, rather than deleting each individually
                using the Edit Option.  The computer will prompt you for the
                necessary information.

4.       Option 3: Update TAT Analytical Services

        Choosing this Option will display the TAT Analytical Services Menu.
                                1-49

-------
COST PROJECTION
TAT ANALYTICAL SERVICES MENU
06/01/89
         1. Add TAT Analytical Services

         2. Edit TAT Analytical Services

         3. Delete all TAT Analytical Service Entries

         0. Return to Previous Menu


            Your Choice:
     a.      Option 1:  Add TAT Analytical Services

             This Option allows you to add projected TAT Analytical Services.
             You will be prompted for the following information:

             •       Analytical Services Description
             •       Analytical Services Amount

             Once all data is entered, press  to return to the TAT
             Analytical Services Menu.

     b.      Option 2:  Edit TAT Analytical Services

             Select this Option to edit, review or erase individual entries within
             the TAT Analytical  Services file.   This program will display all
             current file entries. The Edit Menu functions are briefly  explained
             on page 1-8.   For a  detailed explanation, see Appendix A.

     c.      Option 3:  Delete All TAT Analytical Services

             This function  allows you to eliminate all entries within the TAT
             Analytical  Services  file at once,  rather  than  deleting  each
             individually using  the  Edit  Option, above.  The computer  will
             prompt you for all necessary information.
                              1-50

-------
K.    Option 11:  Update Federal  and State Agency Cost File

       Select this  Option to update the  Federal and  State Agency Cost file.  The
       computer will display the Federal and State Agency Costs Menu.
         COST PROJECTION
FEDERAL AND STATE AGENCY COSTS MENU
06/01/89
                  1. Add Federal and State Agency Costs

                  2. Edit Federal and State Agency Costs

                  3. Delete all Federal and State Agency Entries

                  0. Return to Previous Menu

                     Your Choice:
       1.       Option 1:  Add Federal and State Agency Costs

               This Option allows you to add projected additional Federal Agency Costs.
               You will be prompted for the following information:

               •       Agency Name
               •       Service
               •       Cost
                                      1-51

-------
          COST PROJECTION
                                 ADDING FEDERAL AND STATE COSTS
06/01/89
              Enter Agency Name:                    US COAST GUARD

              Service:                             TRANSPORTATION

              Cost:                                 4754.00
              Is the above information correct? [Y/N3  Y
               Once all data is entered, press  to return to the Federal and
               State Agency Costs Menu.

        2.      Option 2: Edit Federal and State Costs

               Select this Option to modify, review or delete individual entries within the
               Federal and State Costs File.   The program  will display all current file
               entries.  The Edit Menu that appears at the bottom of the screen is briefly
               explained on page 1-8.  For a more detailed explanation, see Appendix A

        3.      Option 3: Delete all Federal and State Agency Entries

               This function allows you to eliminate all entries within the Additional Costs
               file at once, rather than using the Edit Option  to delete each individually.
               The computer will prompt you for the necessary information.

L.      Option  12:   Update Additional Cost File

        Select this Option to update the Additional Cost File.  The Other Costs Menu will
        be displayed.
                                        1-52

-------
          COST PROJECTION
                                       OTHER COSTS MENU
06/01/89
                   1. Add Other Costs

                   2. Edit Other Costs

                   3. Delete All Other Costs Entries

                   0. Return to Previous Menu


                      Your Choice:
        1.      Option  1: Add Other Costs

               Select this Option to add projected Other Costs. You will be prompted for
               the following information:

               •       Cost Description
               •       Amount

        2.      Option  2: Edit Other Costs

               Select this Option to modify, review or erase individual entries within the
               Additional  Costs file.   The program will  display all current  file entries.
               The Edit Menu that appears at  the bottom of the screen is briefly
               explained on page 1-8.  For a more detailed explanation, see Appendix A

        3.      Option 3: Delete Other Costs

               This function allows you to eliminate all entries within the Other Costs file
               at once, rather than using the Edit Option to delete each individually.
               The computer will prompt you for  the necessary information.

               Once you have entered all data, press the < ENTER > key to return to the
               Other Costs Menu.

M.     Option  13:   Update  Project Contingency Factors

        Select this Option to update Project Contingency Factors.  As previously mentioned
        RCMS uses two contingency factors. The first is applied to the cleanup contractor
        sub-total (e.g., ERCS, Regional ERCS, In teragency Agreements [lAGs], Cooperative
        Agreements [CAs], and letter contracts.)  The second contingency factor is applied
        to all extramural costs (except EPA).
                                       1-53

-------
        A 10 to 30% contingency factor for the cleanup contractor is recommended.

        To account for other unanticipated costs, an overall extramural contingency factor
        of 15% should be used unless otherwise directed by the Comptroller's office.

        Enter the new contingency factor in the highlighted space when prompted by the
        computer.


N.     Option  14:   Calculate and Print the Cost Projection

        Once you have entered data that accurately reflects the resources projected for a
        particular site into all 13 Cost Projection files, (corresponding  to  the first  13
        Options  on the Cost  Projection, Main  Menu), a Cost Projection can be printed.

        Select Option 14 to display the Printing menu.
          COST PROJECTION
                                           PRINTING
06/01/89
                       1. Print Cost Projection Scope and Surmary Pages

                       2. Print Entire Cost Projection

                       0. Return to Main Menu

                          Your Choice:  |
       1.       Option 1:  Print Cost Projection Scope and Summary Paces

               Selecting this Option will produce a report that contains a summary page,
               with subtotals for major cost categories, and the project scope.

       2.       Option 2:  Print Entire Cost Projection

               Selecting this Option will produce a report that contains the summary, the
               project scope,  and  a detailed cost projection listing all projected cost
               entries grouped according to major cost categories.

               Exhibit I-A that follows shows an entire Cost Projection Report.
                                       1-54

-------
                                   Exhibit I-A
                       Cost Projection Scenario:  ABC DRUM                Page:  1
        Projection ID No.: E901                 Date:  01/01/88
        Cleanup Contractor: ACME ENTERPRISES        TAT Contractor: ROY F ECOLOGY
Cost Projection Summary
          Contractor Personnel                               276,242.00
          Contractor Equipment                                56,719.00
          Unit Rate Materials                                 13,862.50
          At Cost Materials                                    4,180.00
          Subcontractors                                     116,820.00
          Waste Transportation                                13,805.00
          Waste Disposal                                      33,990.00
                                      1-55
          Cleanup Contractor Subtotal                         515,618.50

          Federal and State Agencies                          11,500.00
          Extramural Subtotal                                527,118.50
          20 % Extramural Contingency                        105,423.70
          Extramural Subtotal                                632,542.20
          TAT Personnel                                       94,720.00
          TAT Special Projects                                 3,000.00
          TAT Analytical Services                              4,000.00
          Total TAT Costs                                    101,720.00

          Other Cost Items                                       100.00
          Extramural Subtotal                                734,362.20
          15 X Project Contingency                           110,154.33
          Total Extramural  Cost                              844,516.53
          EPA Regional  Personnel                               38,700.00

          EPA Non-Regional  Personnel                            9,900.00
          EPA Headquarters  Direct                               2,880.00
          (10 X of Regional Hours)
          EPA Indirect                                         28,800.00
          EPA Total                                            80^280.00
          Project Total                                       924,796.53

-------
                            Exhibit I-A (continued)
                       Coat Projection Scenario:  ABC DRUN
                        Page: 2
        Projection ID No.: E901
        Cleanup Contractor: ACNE ENTERPRISES
Date: 01/01/88
    TAT Contractor:  ROY F ECOLOGY
Project Scope
     Nunfcer                  Step/Milestone

       1          MOBILIZE SITE
       2          INSTALL FENCE
       3          DEFINE BURIED DRUN AREA
       4          EXCAVATE AND STAGE DRUMS
       5        - SAMPLE DRUM CONTENTS
       6          CONDUCT SOIL SAMPLING
       7          EXCAVATE CONTAMINATED  SOIL
       8          BULK SOLVENTS
       9          BACKFILL EXCAVATED AREAS
      10          INSTALL MONITORING WELLS
      11          TRANSPORT AND DISPOSE  WASTE
      12          GRADE AND LANDSCAPE
      13          DEMOBILIZE
              E*tiMted
             Duration (Days)

                  1
                  3
                  3
                 60
                 15
                  3
                  5
                  3
                  3
                 H
                  2
                  3
                  2
                                     1-56

-------
                             Exhibit I-A (continued)
                       Cost Projection Scenario: ABC DRUM
                                            Page:
        Projection ID No.: E901
        Cleanup Contractor: ACME ENTERPRISES
                    Date: 01/01/88
                        TAT Contractor:  ROY  F ECOLOGY
Contractor Personnel
•SXSSSSSSSSS33SSSSSS

       Job           No.       No.   Hrs per
Category      Emplyes   Days     day       Labor
                           Travel
                         PO,Lodge
                                Charge
SUPERVISOR           1
FOREMAN              1
CLEANUP TECH-HAZ     4
LABORERS             2
EQUIP OPERATOR       2
TRUCK DRIVER    -     1
FLO CLERK/TYPIST     1
CHEMIST ORGANIC      1
LAB TECHNICIAN       1
 60
 90
 80
 80
 80
 14
100
 20
 20
8.0
9.0
8.0
8.0
8.0
8.0
8.0
8.0
9.0
20640.00
22230.00
55040.00
27520.00
32000.00
 2632.00
18400.00
 4880.00
 5510.00
 5940.00
 8910.00
28800.00
14400.00
14400.00
 1260.00
 9900.00
 1800.00
 1980.00
                              Total Personnel  Cost:
 26580.00
 31140.00
 83840.00
 41920.00
 46400.00
  3892.00
 28300.00
  6680.00
  7490.00

276242.00
Contractor Equipment
Equipment
Item
TRUCK PICK UP
TRUCK TANK 5000 GAL
TRUCK BOX 2 TON
Reg
Days
120
10
120
Stby
Days
0
0
0
Mob/Dmob
Hours
8
0
0
Dec on
Hours
0
0
0
Mi leage
N/A
N/A
N/A
Total
Charge
1646.00
860.00
0.00
                                     1-57

-------
                                     Exhibit I-A (continued)
                                                  ESSSSSSESSS
                        Cost Projection Scenario:  ABC DRUM
                        Page:  4
         Projection 10 No.: E901
         Cleanup Contractor:  ACNE ENTERPRISES
Date: 01/01/88
    TAT Contractor:  ROY  F ECOLOGY
 Contractor Equipment
Equipment
Item
TRLR DECON 8X40
TRLR OFF 8X40
BACKHOE CASE 580
GC GAS CHROMATOGRAPH
EMERGENCY LIGHTING
PUMP ACID
DRUM GRAPPLER 360
AIR COMPRESSOR
TRLR OFFICE/STORAGE
LN SMOKE SHIFTER
COMPUTER
Reg
Days
120
120
90
30
0
120
120
120
120
120
120
Stby
Days
0
0
30
0
120
10
10
0
0
0
0
Mob/Dmob
Hours
0
0
0
0
0
0
0
0
0
0
0
Decon
Hours
0
0
0
0
0
0
0
0
0
0
0 '

Mi leage
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Total
Charge
11504.00
3800.00
5764.00
700.00
1740.00
5996.20
6538.80
4800.00
8570.00
3600.00
1200.00
                              Total Equipment Cost:
                      56719.00
Unit Rate Material
Material
Name
AIR CARTRIDGES
OVERPACKS
SAMPLING JARS
SORBENT PADS
TYVEC SUITS
VISQUEEN
Use
BREATHING
OVERPACK DRUMS
HOLD SAMPLES
CLEANUP
WEAR
DECON
Unit
Cost
2.50
70.00
50.00
25.00
3.00
27.50
No.
Units
300.0 EACH
100.0 EACH
5.0 CASE
20.0 BALE
1000.0 SUIT
50.0 ROLLS
Total
Charge
825.00
7700.00
275.00
550.00
3000.00
1512.50
                              Total Unit Rate Material  Cost:
                      13862.50
At Cost Material
                                      1-58

-------
                             Exhibit I-A (continued)
                       Cost Projection Scenario: ABC DRUM
                       Page: 5
        Projection  ID No.: E901
        Cleanup Contractor: ACNE ENTERPRISES
Date: 01/01/88
    TAT Contractor: ROY F ECOLOGY
At Cost Material
Material
Name
LIME
Use
NEUTRALIZE
Total At Cost
Quantity/Amount
15 TONS
Material Cost:
Total
Charge
2200.00
4180.00
Subcontractors
Subcontractor
C&P TELEPHONE
PUBLIC SERVICE
SANITATION CO
SHIPMAN INC
STAR SECURITY
Service
TELEPHONE
ELECTRICTY
PORT-A-JOHNS
DRILL WELLS
SECURITY GUARDS
Total
Charge
770.00
1100.00
550.00
110000.00
4400.00
                              Total Subcontractor  Cost:
                     116820.00
Waste Transportation
Waste
Type
CONT. SOIL
EMPTY DRUMS
SOLVENTS
BSSXS
Amount
100 CU YDS
240 DRUMS
20,000 GAL
No.
Loads
5
2
4
Cost per
Ld. Mile
6.50
6.50
4.50
No.
Miles
200
50
300
Total
Charge
7150.00
715.00
5940.00
                              Total  Waste Transportation Cost:
                      13805.00
                                     1-59

-------
                            Exhibit I-A  (continued)
                       Cost Projection Scenario:  ABC  DRUM
                        Page: 6
        Projection ID No.: E901
        Cleanup Contractor: ACME ENTERPRISES
Date: 01/01/88
    TAT Contractor:  ROY  F ECOLOGY
Waste Disposal
Waste Disposal No. Unit
Type Method Units Units Cost
CONT. SOIL LANDFILL CU YD 100 95.00
EMPTY DRUMS LANDFILL DRUM 240 10.00
SOLVENTS INCINERATION GAL 20000 0.95

Total Waste Disposal Cost:
Total
Charge
10450.00
2640.00
20900.00
33990.00
TAT Personnel
Level
PL1
PL2
PL3
No. No. Hrs per Hr PD, Lodge
TATMs Days day Rate Labor Travel
1 90 9.0 16.00 25920.00 16200.00
2 45 9.0 20.00 32400.00 16200.00
1 10 8.0 25.00 4000.00 0.00
Total
Charge
42120.00
48600.00
4000.00
                              Total  TAT Personnel Cost:
                       94720.00
TAT Special Projects
                      Description
                         Total
                         Charge
               GRAPHICS SUPPORT
               MAGNOTOHETER SURVEY
                              Total  TAT  Special Project Cost:
                        2000.00
                        1000.00

                        3000.00
                                      1-60

-------
                             Exhibit I-A (continued)
                        Cost Projection Scenario: ABC DRUM
                                                     Page: 7
         Projection ID No.: E901                Date: 01/01/88
         Cleanup Contractor: ACNE ENTERPRISES        TAT Contractor: ROY F ECOLOGY
 TAT Analytical Services
                       Description
                                                      Total
                                                      Charge
                ANALYSE SAMPLES
                               Total TAT Analytical Services Cost:
                                                     4000.00

                                                     4000.00
 Federal  and State Agencies
Agency
FEMA
US COAST GUARD
Service
RELOCATION SUPPORT
COST MONITORING
Total
Charge
1500.00
10000.00
                              Total Other Federal Agency Cost:
                                                    11500.00
Additional  Ite
Description
EXPRESS MAIL
Total Additional Cost:
Total
Charge
100.00
100.00
EPA REGIONAL PERSONNEL COSTS
   Title
 No.   Hrs per      Hr                PD,Lodge      Total
Days    Day        Rate      Labor     Travel        Charge
ATTORNEY
 20      4.0      30.00     2400.00
                                                            0.00
2400.00
                                      1-61

-------
                            Exhibit I-A (continued)
                       Cost Projection Scenario:  ABC DRUM
                        Page: 8
        Projection ID No.: E901
        Cleanup Contractor: ACME ENTERPRISES
Date: 01/01/88
    TAT Contractor: ROY F ECOLOGY
EPA REGIONAL PERSONNEL COSTS
Title
CHEMIST
OSC


NO.
Days
10
100


t**m
Hrs per Hr PD, Lodge
Day Rate Labor Travel
8.0 30.00 2400.00 900.00
8.0 30.00 24000.00 9000.00
EPA Regional Personnel Cost:
EPA Headquarters Cost:
Total
Charge
3300.00
33000.00
38700.00
2880.00
                              (Based on  10  X  of Regional hours)

                              EPA Indirect  Cost:
                              (Based on  960 hours a $30 per hour)
                       28800.00
EPA NON-REGIONAL PERSONNEL COSTS
No.
Title Days
ERT ENGINEER 30

Hrs per Hr PD, Lodge
Day Rate Labor Travel
8.0 30.00 7200.00 2700.00
EPA Non-Regional Personnel Cost:
Total
Charge
9900.00
9900.00
                              Total EPA Cost:
                       80280.00
                                     1-62

-------
                                       CHAPTER 2
                                   COST TRACKING

                      1900-55 Form and Daily Cost  Summaiy


2.0  COST TRACKING  OVERVIEW

This section of RCMS has been developed to serve as a tracking system for costs incurred at removal sites,
and to allow the user  to produce EPA approved and required cost report forms (specifically the 1900-55
Form and the Daily Cost Summary). Once final versions of these reports have been produced, the program
will archive the cost report information on floppy disks for later retrieval. This archived information is used
for producing site summary reports, invoice .verification, and contract definitization.

Under the ERCS contracts, a prime contractor can enlist the services of other  listed cleanup contractors.
The prime contractor is defined as the company that receives the delivery order.  Listed cleanup contractors
are those companies listed within the ERCS  zone contract.   These cleanup contractors  have their own
specific, negotiated personnel and equipment rates. The prime contractor, and any listed cleanup contractor,
can also have unique equipment standby, G&A percentage and decontamination rates.

RCMS allows multiple cleanup contractor cost information to be entered and printed on a single 1900-55
Form.  This is accomplished by entering specific contractor codes into RCMS.  The computer will prompt
you for this code for every cost entry in the 1900-55 section.  This allows the program to separate costs by
contractor.   The program manages all of the  multiple  contractor data by requesting rate information on
each contractor.  Initially, RCMS asks for information on only the prime contractor.  If you  enter new
contractor codes, you will then have the opportunity to  enter  the rates specific to that cleanup contractor.

RCMS, Version 3.2, has the  ability to track costs for  multiple prime contractors working on  the same
removal action.  A 1900-55 Form is produced  for each prime  contractor  (and any associated team
contractors).  The Daily Cost Summary lists the daily cost for each prime contractor working on the site.
Prime contractors can be added to RCMS at any time during the course of the removal action. Each prime
contractor must be assigned a  unique contractor code.


              Note: Each prime contractor can have its own set of team contractors. The total cost for the
              prime and any team subcontractors will appear on the 1900-55 Form and Daify Cost Summary
              listed under the prime contractor.
                                             2-1

-------
               NotK An option exists for loading prime and listed cleanup contractor rates into RCMS from
               a floppy disk.  See the section under Loading Cleanup Contractor Data.
 Yet another important feature of the  RCMS Cost Tracking  module is its  ability to interface  with the
 cleanup  contractor's computer system.   When this Option is implemented, RCMS uses daily cost data
 provided by the contractor system to produce the 1900-55 Form.  If multiple prime contractors exist, the
 interface portion can function independently with the computer systems of each prime contractor. The
 interface option is explained more fully in Chapter 7, RCMS Utilities.

 When entering data to create the 1900-55 Form, the computer will prompt you for vendor and use codes
 within the Expendable Materials section; subcontractor and use codes within the Subcontractor section. You
 have the option of adopting your own set of codes for a particular site, or coordinating codes throughout
 the region. The latter option will aid in improving data analysis and in simplifying references to data. Wise
 use  of these codes when entering data for the  1900-55 Form will allow you  to extract  specific cost            tjf
 information when it comes time to produce summary reports.                                                    ;ifi;

 The Cost Tracking section of RCMS is subtitled 1900-55 Form and Daily Cost Summary for a specific             ^|
 reason.  The 1900-55 Form is the contractors' daily cost report to the EPA.  In the past it was produced             
-------
The first step is to access the Cost Tracking module by choosing Option 1:  Cost Tracking (1900-55/DCS)
from the RCMS System Menu.  This Option will display the 1900-55/and Daily Cost Summary Main Menu.
This menu allows you to list, use, load, and/or erase cost report information in RCMS.  The various options
and their appropriate uses are explained in detail on the following page.
                 RCMS VERSION 3.2
1900-55 AND MILT COST SUMART
06/01/89
                          1.  List Cost Report Status

                          2.  UM Currant Cost Data on the Hard Disk

                          3.  Load Last Final Data fro* Archive Disk

                          4.  Start Men Site (Erase Current Files on Hard Disk)

                          5.  Initiate an Additional Cleara? Contractor

                          0.  Return to Previous Menu

                             Your Choice:  I
      1—i       Note: If you are starting a new site choose Option 4: Start New Site, first After following the
      jj         set-up procedures outlined in Option 4, select Option 2: Use Current Oat Data on the Hard
               Disk to continue with RCMS Cost Tracking.

The daily cost tracking routine  requires that a final 1900-55 Form and a final Daily Cost Summary be
produced each day.  The program will only store one draft version of each report; after final versions are
prepared, they are stored on the archive disk.

A.     Option 1: List  Cost Report Status

        This Option allows you to look at the status of the cost report for a current site.  The screen will
        display a  list of the last dates  for which final  1900-55 Forms and Daily Cost Summaries were
        produced  and archived.   It will also list  any draft reports stored, along with  the date  of current
        1900-55 Form and Daily Cost Summary data.

B.     Option 2: Use Current Cost Data  on the  Hard Disk

        This Option allows you to use the current data on the hard disk to prepare the 1900-55 Forms and
        DCS.  Select this Option to enter your daily data. The previous day's data should still be loaded
        in the current hard disk files.

        In response to this Option, the computer will display the 1900-55/Daily Cost Summary Subsidiary
        Menu. This  menu is explained  in detail  in section 2.2, page 2-9.

C.     Option 3: Load Last Final Data from the Archive Disk

        This Option allows you to transfer the last day's 1900-55 Form and Daily Cost Summary information
                                              2-3

-------
        from the archive disk to the current hard disk files.  This Option should be used only when the
        hard disk files are erased or become unusable.   The program will request the insertion of the
        archive disk into Drive A.  The information stored on this disk will be displayed on screen and the
        computer will inquire if you wish to load the displayed information.

               Note: To  guard against the possible loss of valuable data the program will request two
               confirmations of this selection.
D.     Option  4: Start  New Site (Erase Current Files on  Hard Disk)

        Choose this Option to enter new site data into the RCMS files. This will prepare any cost tracking
        files on the hard disk needed to begin a new site and will erase any already existing current data.
               Note: Because of the potential loss of valuable data, the program will request two confirmations
               of this selection.


        After  the files  are prepared,  the  program will inquire  if you now wish  to enter  initial site
        information.  If you answer no ("N") you can return to  the site information data entry screen
        through an option on  the following menu. If you choose yes ("₯") ,  the General Site Data screen
        will be displayed.

               1.      Entering General Site Data

                       The general site data screen will prompt you for the following data:

                       •      Site Name
                              Site Identifier #
                       •      City and State
                       •      Appropriation #
                       *      Object Class
                       •      Project Approval Date

                       It is important that you enter the correct  ID number for the site as this number
                       is used to catalog the cost data during the archive procedure.
                                                2-4

-------
    COST TRACKING
                                GENERAL SITE DATA
                               06/01/99
                  Site
           Site Identifier *
              City and State

             Appropriation ff
                Object Class
       Project Approval Date
swaw**
R^WK"*%'% f A
                 Is this correct? [Y/H
        Once these entries have been validated, the Prime Contractor Data screen will be
        displayed.

2.      Entering Prime Contractor Data

        The computer will prompt you to enter the  following information  for the site's
        prime contractor:

        •      Prime Contractor Name
        •      Prime Contractor Code
        •    .  Delivery Order #
        •      Contract #
        •      Document Control  #
  COST TRACKING
                             PRIME CONTRACTOR DATA
                             06/01/89
      Priae Contractor Haw:  ACME ENTERPRISES
      PriMe Contractor Code:  0001

           Delivery Order f:  2334-56-703
                Contract ff:  68-92-2334
        Docuaent Control ff:  20X45234

         You aust enter the Raae, Code, and Delivery Order ff.
               Is this correct?  [Y/N]  Y
                                2-5

-------
Note: You must enter the prime contractor name, code, and delivery order number.  You will
be unable to exit this screen if they are left blank.

        Once you enter the requested information, the computer will inquire if you wish
        to load contract rates from a disk.
1900-55 FORM |
CONTRACTOR DATA LOADING
06/01/89
    This option Mill let you load general  (i.e., decon and standby),
    equipment, and personnel rates for a specific prims contractor and
    its subcontractors,   ly doing so, you  will overwrite any existing
    rate data.  You Hill be asked to insert a pre-aade contractor-
    specific rate disk.

                Are you sure you want to  continue? [Y/W   Y
        A response of yes ("Y") to this inquiry enables you to load contractor rates into
        the system from a prepared disk. The data on the disk must match both the prime
        contractor name and code previously entered in the general site data. If the rate
        disk loaded into the system does not match the prime contractor name and code,
        the following  message will appear:
            1900-55 FORM
CONTRACTOR RATE LOADING
06/01/89
               The data on the disk does not Match the prime contractor
               naae and/or code you entered in the general site data.

               The following rate data is contained on the disk you inserted:

                        Pri«e Contractor Home: DRUM ENVIRONMENTAL
                        Prime Contractor Code: DRUM

               Do you wish to:

                         1) Insert a new contractor rate disk
                         2) Load these contractor rates
                         0) Exit

               Your Choice
        RCMS will review the information contained on the rate disk and compare that
        information with the data entered manually.  If the data does not match, you have
                                  2-6

-------
                       the choice of inserting a new contractor rate disk, loading the present contractor
                       rate disk or exiting the Contractor Rate Loading Option entirely.

                       The 'Contractor Rate Disk" will normally be supplied with RCMS and contains
                       rates pertaining to the applicable zone ERCS contract  Because many zone ERCS
                       contracts use "team"  cleanup contractors (i.e., ERCS subcontractors), additional
                       contractor rate disks can be customized for those particular zone ERCS contracts
                       or even for a particular site.  These  disks can contain an unlimited number of
                       equipment and personnel  rates for both the prime contractor and  the ERCS
                       subcontractors' team.  Please consult with RCMS User Support, (phone 1-201-321-
                       6746) or the zone ERCS contractor for  assistance in creating these disks.

                       A  no ("N") response will prompt  a request for the following prime contractor
                       information:

                       •      Prime G&A Percentage
                       •      On-Site Standby Percentage
                       •      Off-Site Standby Percentage
                       •      On-Site Decon  Percentage
                       •      Off-Site Decon Percentage
                  COST TRACKING
                                            PRIME CONTRACTOR DATA
                                              06/01/89
                      Pri
                      Pri
Contractor MMK:
Contractor Code:
ACHE ENTERPRISES
0001
                          Delivery Order f:  2334-56-703
                                Contract f:  68-92-2334
                        DocuMnt Control f:  20X45234
                     Pri«e G I A Percentage:
                           On-Site Standby:
                          Off -Site Standby:
                             On-Site Decon:
                            Off-Site Decon:
                 10 JM
                 !HM>;X
                 40,0  X
                 »*«; «
                               Is this correct? [Y/N]  \
E.     Option 5:  Initiate an Additional Cleanup Contractor

       This Option enables you to enter cost data for another prime contractor into the system.  You will
       be shown the  current list of prime contractors and asked if you wish to add to it.
                                               2-7

-------
tots
VERSION
3
•' 1
ADD
ANOTHER
PRIME
CONTRACTOR
06/01/89
          This option allow you to track coat data for another prime contractor.

             The following fa a liat of priae contractors currently being used:

                                  1. ACME ENTERPRISES

                     Do you want to add another priae contractor? [Y/N]   |
A response of yes ("Y") will allow you to add another prime contractor to the system.  A series of
screens, similar to those  that appear after the Start New Site Option, will guide you through the
process  of entering the appropriate new prime contractor information (see Option 4: Start New
Site, p. 2-4).

The following is the first screen and the accompanying prompts you will encounter:
           COST TRACKING
PRIME CONTRACTOR DATA
06/01/89
               Priae Contractor
               Priae Contractor Code:  '-

                   Delivery Order f: ""'
                         Contract f: -'
                 Document Control f:
                           A blank contractor code will  abort.
You  then have  the option  of loading rates for this  prime  contractor  (and associated team
contractors) from a prepared Contractor Rate Disk.  If the loaded rate disk does not match the
previously entered prime contractor's name and code, RCMS will offer you  the choice of inserting
a new rate disk, loading the present contractor rate disk, or exiting the Contractor Rate Loading
Option.
                                         2-8

-------
        If the prepared contractor rate disk is not available, a series of computer prompts, as shown on the
        following screen, will assist you with the manual input of contractor rates.
                  COST TRACKING
                                             PRIME CONTRACTOR DATA
                         06/01/89
                      Priae Contractor Mane:
                      Prime Contractor Code:  9003

                          Delivery Order ff:  WOO-M-WO
                                Contract*:  60-06-0000
                        Document Control *:  90000000
                           ENTER IN THE APPROPRIATE RATE
                     Prime G I A Percentage:
                           On-Site Standby:   0.0  X
                          Off-Site Standby:   0.0  X
                             On-Site Decon:   0.0  X
                            Off-Site Decon:   0.0  X
     INFORMATION
2.2    1900-55 FORM AND DAILY COST SUMMARY  MENU
                       RCHS VERSION 3.2
1900-55 AND DAILY COST SUNMRT
06/01/89
                                   1. Update General Site Information
                                   2. Update Prime Contractor Information

                                   3. 1900-55 Fora
                                   4. Daily Coat Suaaary

                                   5..Incident Obligation Log (IOL)
                                   6. Contractor Daily Cost Log

                                   7. Archive and Backup Data

                                   8. RCNS Utilities

                                   0. Return to Previous Menu


                                     Tour Choice:
During the process of producing cost reports, your activities will center around the 1900-55 and Daily Cost
Summary Menu.  This menu outlines all of the major options for data entry, cost report production, and
archiving of data.  Unlike the Cost Projection module, the Cost Tracking program requires you to follow
a sequential order of data entry, preparing forms in the order listed on this Menu (i.e., a 1900-55 Form
before the Daily Cost Summary).  In addition, you must prepare and finalize both a 1900-55 Form and DCS
before you can archive the data.
                                                2-9

-------
 The menu choices for the 1900-55 Form and Dally Cost Summary are summarized below. For a detailed
 explanation of each section, refer to the appropriate chapters that follow this introduction.

 A.     Option 1: Update General Site Information

        This Option returns to the General Site Data screen allowing you to update or edit of information.
        See Entering General Site Data, page 2-4, for an explanation of this screen.


 B.     Option 2: Update Prime Contractor Information

        This Option enables you to update information on the prime contractors loaded into the system.
        If the system contains more than one prime contractor, you will be asked to select the one that you
        wish to update from the list displayed on-screen. You have the option of updating the prime rates
        for the prime contractor either manually, or via a  contractor rate disk.   See Entering Prime
        Contractor Data, page 2-5, for an  explanation of this function.

 C.     Option 3: 1900-55 Form

        This Option allows  you  to enter  the 1900-55 section of RCMS to add, view,  and edit cleanup
        contractor cost information.  If the system contains more than one prime contractor you will be
        asked to select the prime contractor for whom you wish to prepare the 1900-55 Form.  You will
        then be prompted for the date of the 1900-55 Form you wish  to prepare or edit.  See Chapter 3:
        1900-55 Form, for detailed information on preparing the 1900-55 Form.

              Note: If you are using a contractor interface to load the daify 1900-55 cost data, please refer
              to Chapter 7: RCMS  Utilities.


 D.     Option 4: Daily Cost  Summary

        This Option enables you to enter the Daily Cost Summary section of RCMS to update costs other
        than those incurred by the cleanup contractor during a removal action (e.g., EPA, TAT). The Daily
        Cost Summary provides a listing of all daily costs, and tracks  these costs against the site ceiling.
        The computer will begin by prompting you for the date of the Daily Cost Summary you wish to
        prepare or edit See Chapter 4: Daily  Cost Summary, for detailed information on preparing the
        Daily Cost Summary.
              Note:  You will not be able to enter the DCS program until a final 1900-55 Form has been
              prepared and printed for at least one prime contractor.
E.     Option 5:  Incident Obligation Log  (IOL)

       This Option allows you to print an IOL from the current data on the hard disk. See Chapter 5:
       Incident Obligation Log for detailed information on preparing the IOL.
                                            2-10

-------
F.     Option  6:  Contractor Daily Cost Log

       This Option allows you to print the Contractor's Daily Expense Log from the current data on the
       hard disk.  See chapter 5 for detailed information on preparing this Log.

G.     Option  7: Archive and Backup Data

       This Option allows you to archive the data on previously prepared archive and backup archive disks.
       Once  you  have completed the final cost reports for the day (1900-55 Form and Daily  Cost
       Summary).  See Chapter 6 for detailed information.
              Note:  The system will prevent you from preparing a new 1900-55 Form or DCS until the
              current day's data has been archived.
H.    Option  8: RCMS Utilities

       This Option enables you to do the following:
       •      Prepare Archive and Backup Disks
       •      Print Supplemental 1900-55 Forms
       •      Transfer Cleanup Contractor Data via the Interface
       •      Restore Last Day's Final Data From the Hard Disk

       See Chapter 7: RCMS Utilities, for more information.
                                            2-11

-------

-------
                                 CHAPTER 3

                                 1900-55 Form
3.0  1900-55 FORM OVERVIEW

The 1900-55 Form records the estimated time and material costs incurred by the cleanup
contractor each day.  The 1900-55 module enables you to enter this daily cost information
and then print the required 1900-55 Form. This printed report contains separate sections
for personnel, equipment, expendable materials (both Unit Rate and At Cost Materials),
as well as subcontractors (i.e., vendors).  In addition, there is a section for comments and
adjustments. The number of pages in a printed 1900-55 Form is dependent on the amount
and types of resources used  during that particular day.   For example, if no  expendable
materials  were purchased or expended on  a particular day there would then be no
corresponding section within  the printed 1900-55 Form.   An example of a final 1900-55
Form is shown at the end of this chapter (Exhibit m-A).

               Note: A separate 1900-55 Form is prepared for each prime contractor working
               on a site.  The 1900-55 Form will list the costs for the prime contractor as
               well as any team contractors working for that prime contractor. If the system
               contains  more than one prime contractor, you will be asked to select the
               contractor for whom the 1900-55 Form is to be prepared.
         RCMS VERSION 3.2
SELECT PRIME CONTRACTOR
06/01/89
                Multiple prime contractors are being used at this site.
                In order to use the proper cost data, you must select
                one of the prime contractors listed below:

                                1. ACME ENTERPRISES
                                2. BAGGERTS

                                  Your choice:  1
This chapter explains how to begin preparing a 1900-55 Form, outlining all of the options
available within this RCMS module.
                                        3-1

-------
Ej>
                Note: Chapter 7: RCMS Utilities, provides instructions for using the contractor
                interface option to load the daify 1900-55 Form data.
3.1  PREPARING  THE 1900-55 FORM

To begin your 1900-55 Form, select Option 3: 1900-55 Form from the 1900-55 and Daily
Cost Summary Menu (accessed by choosing Option 2: Use Current Cost Data on the Hard
Disk from the 1900-55 And Daily Cost Summary Main Menu). The 1900-55 Form Date
Input screen will be displayed.  If multiple prime contractors are being used at the site, the
computer will display a list of these contractors and require that you select one for your
1900-55 Form before you can proceed with this Option.

Once you have entered a prime contractor, the screen will display the dates of the last final
1900-55 Form printed, and the  last final one archived.  If a draft copy of a 1900-55 Form
exists within the hard disk files,  the date of its entry will also be displayed.  If you  are
beginning your first 1900-55 Form, these dates will be blank. At the bottom of the screen
a prompt will  appear requesting the date of the  1900-55 Form that you wish to prepare or
edit. You can enter a date for  either a draft copy of a 1900-55 Form, or a date for a new
1900-55 Form. The 1900-55 Forms shown must be prepared in chronological order.
            ACME ENTERPRISES
                                      DATE INPUT
06/01/89
                        Last Final  1900-55 printed:    /  /
                        Last Final  1900-55 archived:   /  /
                        Current 1900-55 data stored:   /  /
             Enter the date of the 1900-55 that
                       Enter a blank to exit  i
                                                    wish to prepare
Once you enter the date of the 1900-55 Form you wish to prepare or edit, the 1900-55
Form Main Menu will be displayed.
                                        3-2

-------
3.2  1900-55 MAIN MENU
         ACME ENTERPRISES
                                         MAIN MENU
                                           06/01/89
             Select an option below:

                  1. Update Contractor Code and Rate  Information
         1900-55
       Data  Inputs
2. Update Contractor Personnel  File
3. Update Contractor Equipment  Files
4. Update Contractor Expendable Materials File
5. Update Subcontractor File
6. Update Conments and Adjustments to the 1900-55 Totals
                   7. Calculate and Print 1900-55 Form

                   0. Return to Previous Menu

                     Your Choice:  !|
The procedures for completing a 1900-55 Form include adding and editing entries within
the 1900-55 Files.  The contents of each file can be updated by entering the appropriate
Option number from the  1900-55 Main Menu.  You will notice that a number of these
listed Options are preceded by an asterisk, indicating that they represent the 1900-55 data
inputs for time and materials.  These options allow you to enter and edit cost entries for
a chosen category.
               Note:  The prime contractor's name is in the left-hand comer of the Main
               Menu screen.
The explanations that follow include general discussions of each option on the 1900-55
Main Menu, together with examples of the computer screens encountered when a particular
activity is chosen.  Please note that the Expendable Materials Option is divided into Unit
Rate Materials and At Cost Materials.

A.     Option  1:   Update Contractor  Code and  Rate  Information

       Select this Option to update the Emergency Response Cleanup Services  (ERCS)
       contractor file. You can edit information pertaining to cleanup contractors already
       in the current file or you can add new cleanup contractors to the file list. When
       you choose this Option the Add/Edit Contractor Data screen will be displayed and
       you will  be prompted to  enter a contractor code.
                                       3-3

-------
  ACME ENTERPRISES
ADD/EDIT CONTRACTOR DATA
06/01/89
                Enter the Contractor Number or hit
                   to list available Contractors:
                        (Enter a blank  to exit)
                   F1
If you are unsure of a contractor's code you may view the list of contractors in the
RCMS  file by pressing .   A  small window  displaying the current list of
contractors will appear on the right hand side of the  screen.  If there are more
cleanup contractors in the file than can be listed in a single window, the program
will inform you that additional contractors exist. By pressing < ENTER > you can
display the remaining contractors.  Once the list is completed and you have noted
the code for the contractor you are using, press < ENTER > to exit this window and
return to the Add/Edit Contractor Data screen.
  ACHE ENTERPRISES
                             ADO/EDIT
                Enter the Contractor Nu
              CURRENT CONTRACTOR LIST   -

              Code   Name

              0001  ACME
              0002  UESS

             Note the Contractor Code and
               hit ENTER to continue.
                  to list available Contractors:
                       (Enter a blank to exit)
                                 3-4

-------
1.
Option 1:  Adding Contractors
        To  add a  new  contractor to  RCMS,  enter  a  unique  contractor code
        consisting of any combination  of characters or  numerals (4 maximum).
        After entering this new contractor code,  a window will appear in the upper
        right of the screen noting a lack of data for this contractor and will inquire
        if you wish to add this missing data.  If so, enter yes ("Y").  The program
        will now prompt you for the  following information:

        •      Contractor Name
        •      G&A Percentage
        •      On-Site  Standby Percentage
        •      Off-Site  Standby Percentage
        •      On-Site  Decontamination Percentage
        •      Off-Site  Decontamination Percentage

        Note: For  definitions of  the G&A percentage,  standby  percentage,  and
        decontamination percentage, see the Glossary.
  ACME ENTERPRISES
                     AD
               Enter the Contra
                  to list avail
                       (Enter a
                                     EDIT THIS CONTRACTOR'S DATA
                         Code:             0009
                         Name:             WESS
                         G&A Percentage:    20.00
                         Standby On Rate:    0.0
                         Standby Off Rate:   0.0
                         Decon  On Rate:     0.0
                         Decon  Off Rate:     0.0

                            Is  this correct? [Y/NJ  Y
                              0009
2.
Enter the requested information. Enter "0" for any rate information that
does not apply.  When completed, confirm that the information is correct.
To exit  the Add/Edit Contractor  Data screen, enter a  blank at  the
contractor code prompt. A blank response is equivalent to simply pressing
 in the empty field.

Option 2:  Editing Listed Contractor Data

To edit listed cleanup contractor for a cleanup contractor listed in  the
RCMS file, enter the desired contractor code. The "Edit This Contractor's
Data" window will appear in the upper right corner of the screen displaying
                                 3-5

-------
               the current contractor data. To enter new information simply type over
               the displayed data, or simply press < ENTER > if the data is correct as
               displayed.  After you have finished editing, the computer will request
               confirmation of your  data.  If it is correct, enter a "Y".  You may now
               continue to edit the contractor list from the Add/Edit Contractor Data
               screen.   When finished updating  the contractor information file, press
                 to return to the 1900-55 Main Menu.
B.      Option  2:  Update Contractor Personnel File

        Select this Option to update the 1900-55 Form's Contractor Personnel File.  The
        program will respond by displaying the Personnel Menu screen.

        This  Menu offers you the option  of adding, editing, viewing or deleting entries
        within the  Cleanup Contractor Personnel File. It also enables you to print a draft
        copy  of the 1900-55 Form's personnel page.

        There are  two options for  adding personnel.  Option  1: Add  Listed Personnel
        allows you to add personnel with job categories already listed in the appropriate
        ERCS contract.  Choose Option 2: Add Non-Listed Personnel to add job categories
        not listed in the ERCS contract.
          ACME ENTERPRISES
PERSONNEL MENU
06/01/89
              1. Add Listed Personnel to the Personnel File

              2. Add Non-Listed Personnel to the Personnel File

              3. Edit/View/Delete Entries in the Personnel File

              4. Delete All Personnel Entries

              5. Print Draft 1900-55 Personnel Page

              0. Return to Previous Menu


                 Your Choice:

       1.      Option i: Add Listed Personnel

               By choosing this Option you  will display the Adding Listed Personnel
               screen consisting of job categories and their corresponding code numbers.
               Search this list to find the job category you desire.  Remember, you can
               scroll through this list by using the  or  keys.  If you find
               the correct job title, simply enter the corresponding four digit code. If the
               desired job category is not on this list, you will have to enter it using
               Option 2: Add Non-Listed Personnel, page 3-10.
                                       3-6

-------
                last digit of the job title code is used to represent the position level
       of the job category (such as level T or level "2").  You may edit this number
       by entering the EditlViewlDelete mode.  (Option 3, page 3-11.)
ACME ENTERPRISES ADO
Code Job Category
001-1 SUPERVISOR
002-1 FOREMAN
003-1 CLEANUP TECN-HAZ
004- LABORERS
005- EQUIP OPERATOR
006- TRUCK DRIVER
007- WELDER
008- ELECTRICIAN
009- MECHANIC
010- CARPENTER
011- EXPLOSIVES SPEC
013- FLO CLERK/TYPIST
OU- ENGINEER CHEMICAL
015- CHEMIST ORGANIC
Select personnel by code and
more entries, use the PgUp or
ING LISTED
Code
016-1
017-1
018-1
020-1
021-1
022-
023-
024-
025-
026-
027-
028-
029-
030-
level (use
PgDn keys
PERSONNEL 06/01/89
Job Category
IND HYG/SAFE ENGR
HYDROGO/GEOLOGIST
LAB TECHNICIAN
FORMAN-OIL SPILL
CLEANUP TECH-OIL
ENGINEER CIVIL
PLUMBER
PIPESETTER
PIPEFITTER
IRON WORKER
CONCRETE LABORER
MASON( FINISHER)
ELECTRICIAN APPRE
DATA ENTRY CLERK
4 digits). To see
. To exit, hit [Esc]. |||;-|
      After  you have found  and entered  the desired  job category code, the
      program  will  respond  with  a screen  that  displays your selection  and
      prompts you for the following:

       •       Contractor Code
ACME ENTERPRISES
ADDING LISTED PERSONNEL
06/01/89
     Job Code and Category:  007-1  WELDER
     Contractor Code:

     Enter the above information or F1 for a  list of contractors.
      If necessary, you can  review the  current  Cleanup Contractor  List  by
      pressing .  Once you have entered the correct contractor code for
                                3-7

-------
      this employee the program will respond by displaying the contractor name
      on the following line. If the employee you are entering is the first cost
      entry for a new cleanup contractor, you may enter the new contractor code
      here. The program will request the required rate information for this new
      contractor and will add it to  the contractor list, (see Option 2: Adding
      Contractors, page 3-5.)

      Note: It  is important to enter the correct  contractor code, as different
      contractors have different rates for the same job category.
      The program will now prompt you for the following:

      •       Employee Name   (The  recommended form for entering  an
              employee name  is last name first,  followed  by a first  name or
              initial).
      •       Employee ID Number
ACME ENTERPRISES
ADDING LISTED PERSONNEL
06/01/89
     Job Code and Category:  007-1  WELDER
     .Contractor Code:       ACME
     Contractor Name:       ACME ENTERPRISES
     Efiployee Name:         JIM BOEW
     Enployee ID No.:       6752

     Enter or edit the job class above:
                                                               'f£tr
      The program will then allow you to edit the job category for this employee,
      if necessary.

      You will then be requested to verify this information.  You can either re-
      enter the information by entering a no response ("N"), or continue with the
      program by entering yes ("Y").

      Next, the computer will prompt you to enter the following rate information:

      •       Regular Rate
      •       Overtime Rate
      •       Sunday/Holiday Rate
      •       Breathing Air Surcharge Rate
      •       Fixed or Provisional Rates
                               3-8

-------
  ACME  ENTERPRISES
ADDING LISTED PERSONNEL
06/01/89
       Job Code and Category: 007-1  WELDER
       Contractor Code:       ACME
       Contractor Name:       ACME ENTERPRISES
       Employee Name:         JOHN BOEU
       Employee ID No.:       423


       Enter the applicable rates below:

       Regular Rate :                 40.94
       Overtime Rate:                 58.57
       Sunday/Holiday Rate:            0.00 (Enter 0 if not applicable)
       Breathing Air Surcharge Rate:    0.00 (Enter 0 if not applicable)
   Fixed or Provisional Rates? IF/P]   F
If a contractor rate file has been previously loaded, the program may display default
rates for listed employees. If the listed rates are correct simply press < ENTER >
at each prompt to accept them, otherwise type the correct rates over the incorrect
information.

After requesting and receiving verification of this rate information, the program will
respond with two prompts regarding G&A rates. Specifically, you will be asked
whether labor and other direct charges are subject to G&A charges.

G&A charges are calculated on the basis of a negotiated percent defined in the
ERCS contract.  They are charged by the contractor on items that do not have a
negotiated rate determined in the contract.  In general, personnel labor charges are
negotiated rates. For a more detailed explanation, see the Glossary.
  ACME  ENTERPRISES
                              ADDING LISTED PERSONNEL
                                06/01/89
       Job Code and Category:  007-1  WELDER
       Contractor Code:       ACME
       Contractor Name:       ACME ENTERPRISES
       Employee Name:         JOHN BOEU
       Employee ID No.:       423
      Enter the applicable rates below:

      Regular Rate :                40.94
      Overtime Rate:                58.57
      Sunday/Holiday Rate:          NOT APPLICABLE
      Breathing Air Surcharge Rate:  NOT APPLICABLE
      Fixed or Provisional Rates:    FIXED RATES
      Are labor charges subject to G and A charges?  [Y/N]  N
      Are other direct charges subject to G and A charges? [Y/N]

      Is the above G and A information correct? [Y/N]  Y
                                  3-9

-------
After verifying the accuracy of the G&A information, the program will prompt you
for the next page following daily charge information.

        •       Regular Hours (hours worked that day)
        •       Overtime Hours (overtime worked that day)
        •       Per Diem
        •       Lodging
        •       Travel
  ACME ENTERPRISES
ADDING LISTED PERSONNEL
06/01/89
       Job Code and Category: 007-1  WELDER
       Contractor Code:       ACME
       Contractor Name:       ACME ENTERPRISES
       Employee Name:         JOHN BOEW
       Employee ID No.:       423

       Enter Hours,  Per Diem and Travel Expenses for today:

       Regular Hours:                 10.00
       Overtime Hours:                 1.00
       Per Diem:                     25.00
       Lodging:                      46.00
       Travel:                      259.00
       Is the above  information correct? CY/N]  Y
        Verification of  this  information  will  return  the program to  the  Job
        Category List screen.  You can either continue to add listed personnel in
        this fashion or, if you have finished entering listed personnel, press 
        to exit this section and return to the 1900-55 Form Personnel Menu.

2.      Option 2: Add Non-Listed Personnel

        Select this Option to add employees whose job categories are not listed in
        the negotiated ERCS  contract.  The program responds to  the selection of
        this Option by displaying the Adding Non-Listed Personnel screen.  To
        enter a non-listed job  category, first enter a three digit job code, within the
        range of 31 - 999 as  well as a fourth number, representing the position
        level of the job. The  computer prompts, and corresponding screens  that
        follow the entry of this new job category code are identical to  those in
        Option 1: Add Listed Personnel,  page  3-6.
                                 3-10

-------
\
ACME
ENTERPRISES
ADDING
NON-LISTED
PERSONNEL
06/01/89
                              Code  Job Category
Code   Job Category
                              101-2    ACCOUNTANT
                            This module allows you to add job categories that are NOT on the
                            ERCS Personnel  List.  Codes for these items are from  31 to 999.
                            Enter the code  and level for the item you wish to add.  If this code
                            has been previously entered, the rates that have been entered will
                            be displayed.   To see more items, use the PgUp or PgDn keys.
                            To exit,  hit [Esc].
                                 The first time that you enter a non-listed job category, the default hourly
                                 rates will be zero. Once you enter the applicable rates for this job category
                                 they will be displayed as the default rates anytime this job category is called
                                 up.  You then have the option of using or editing these default rates.

                 3.      Option 3: Edit/View/Delete Entries

                                 Select this Option to modify, view, and delete  entries within the current
                                 contractor personnel file.  The program will display the current Contractor
                                 Personnel File in list form. By using the "Action Keys* displayed on the
                                 Edit Menu at the bottom of your screen  you can access edit, view, or
                                 delete functions  for individual entries.
ACME ENTERPRISES
PERSONNEL
06/01/89
Rec Job Cont Emp Job Reg. O.T. Sun/Hoi 8. Air
* Code Code I Of Category Name Hours Hours Hours Hours
1 101-1 ACME 423 ACCOUNTANT JOHN BOEW 10.00 1.00
n/a n/a
Action keys: O>] Edit [T] Previous record [PgUp] Previous page
[D] Delete [i] Next record [PgDn] Next page
[U] Undelete [F2] Extended edit [Esc] Quit
                                                          3-11

-------OCR error (C:\Conversion\JobRoot\0000038R\tiff\2000A5YC.tif): Saving image to "C:\Conversion\JobRoot\0000038R\tiff\2000A5YC.T$F.T$F" failed.

-------
Remember!     Once you leave the EdulViewtDelete mode the onfy way to reestablish the
                employee is by manual input. You can no longer restore an individual to the
               file with the Undelete Option.

                Note:  If a person is leaving a site temporarily, it is more advantageous to
                enter a  "0" (zero) for their hours than to delete their record.
                Note: Remember to use the Extended Edit Option to remove and/or add
                transportation charges, as well as to remove and/or add per diem and lodging
                charges when an employee leaves a site for a weekend, holiday, etc.

        4.       Option 4: Delete All Personnel Entries

                Select this  Option to delete all contractor personnel  entries  from the
                Contractor  Personnel   File  at  one  time,   rather   than using  the
                Edit/View/Delete Option to delete each entry individually.  Choose this
                Option only if your intent is to delete all entries.  This Option deletes all
                personnel, regardless of their contractor affiliation.
          ACME ENTERPRISES
PERSONNEL MENU
06/01/89
               Are you cure you want to delete all personnel entries?  [Y/M]  N
C.     Option  3:  Update  Contractor Equipment  File

        Select this Option  to  update the Cleanup Contractor Equipment  File.  The
        program will respond to this choice by displaying the Equipment Menu screen.
                                       3-13

-------
\
                      ACME ENTERPRISES
EQUIPMENT MENU
06/01/89
                            1. Add Listed Equipment

                            2. Add Non-Listed Equipment

                            3. Edit/View/Oetete Equipment

                            4. Print Draft 1900-55 Equipment Page

                            0. Return to  the Previous Menu


                              Your Choice:
                            This Menu  gives you the option of adding, editing, viewing or deleting
                            entries in the Cleanup Contractor Equipment File.  It also enables you to
                            print a draft copy of the 1900-55 Equipment Page.

                            There are two options available for adding equipment.  Option 1:  Add
                            Listed Equipment, allows you to enter equipment  that is  listed  in the
                            ERCS contract.  Option 2: Add Non-Listed Equipment permits you to add
                            equipment that is not in the ERCS contract.

                            Option 1: Add Listed Equipment

                            When you choose this Option the computer will respond by displaying the
                            Adding Listed Equipment screen. This screen consists of a list of equipment
                            items and corresponding code numbers. Search this list to find the desired
                            equipment item.  You can scroll through the  list by using the  or
                             keys.   Once  you  find the correct equipment,  type in  the
                            corresponding three digit code and press < ENTER >. If you can not find
                            the desired  equipment, refer to  Option 2:  Add Non-Listed Equipment,
                            explained on page 3-19.

                            Note: A particular piece of equipment can have several names.  If you cannot
                            find the particular piece of equipment you need on the list, you may wish to
                            consult someone familiar with the ERCS equipment list to find out if the
                            desired item  is listed under a different name.
                                                    3-14

-------
ACME ENTERPRISES ADDING
Code Item Name
040 TRUCK VAC 5000 GAL
041 TRUCK VAC 3500 GAL
042 TRUCK VAC 1800 GAL
043 TRUCK PICK UP
044 TRUCK 4 WHEEL OR
045 TRUCK STAKEBED 2 TON
046 TRUCK STAKEBED 1 TON
047 TRUCK TANK 5000 GAL
048 TRUCK WELDER
049 TRUCK BOX 2 TON
050 TRUCK LIFT 30 FT
051 TRUCK DUMP/VAC 3800G
052 TRUCK DUMP HWY 5-10Y
053 TRUCK DUMP HWY 10-20
Select equipment by code (use 3
items use the PgUp or PgDn keys
LISTED EQUIPMENT 06/01/89
Code Item Name
057 TRLR EMERGENCY RES
061 TRLR DECON 8X40
062 TRLR DECON 8X25
063 TRLR OFF 8X40 EQUIP
064 TRLR OFF 8X40
065 TRLR OFF/STOR 8X20
066 TRLR STORAGE
068 TRLR FLATBED 42 FT
069 TRLR WATER 500 GAL
070 TRLR TK GALV 5000G
071 TRLR TK 5000G GLASS
072 TRLR TK 5000G RUBBE
073 TRLR TK GLV 7500G
074 TRLR TK 7500G RUBBE
digits). To see more
. To exit, hit [Esc]. Hi
After you have found and entered the desired equipment code, the program
will respond with a  screen that displays your selection. You will then be
prompted the enter  the following information:

 •      Contractor Code

When prompted for the  contractor code you  can refer to the Current
Cleanup Contractor  List by pressing .  Once you enter the correct
contractor code, the program will  display the contractor name on the
following line.  If the piece of equipment being entered is  the first cost
entry for a new cleanup  contractor, you may  enter the new contractor
code here.   The  program will request the required rate information
pertinent to this new contractor and will add it to the contractor list.

Note: It is important to  enter the correct  contractor code, as different
contractors have different rates for the same piece of equipment.

Next, the following prompt will appear on the screen:

•       Is this item rented

Note: It is important to answer the rented question correctly, as owned and
rented equipment are  treated differently during the cost definitization process.

The program will now ask if the contractor information is correct  You
can  reenter  the above information by  entering  a no  ("N")  response.
Otherwise, press  to accept the yes ("Y") default and continue.

You will now be prompted for the following:

•       Enter number of Equipment Items
                        3-15

-------
                                                               v-
                                                               ,-s.
 The program has a default value of "1* for the number of Equipment Items.
 At this point you may enter the actual number of items you will be using.
 If you do not wish to enter a number for this equipment item, enter a "0"
 and you will return to the Adding Listed Equipment screen.

 The program now allows you to edit the equipment name, if so desired,
 for clarification.  You will then be prompted for the following:

 •      Equipment ID Code

 The equipment ID code is a set identifier assigned by you,  or by the
 contractor, to the piece of  equipment you are currently entering.   The
 number could be a license plate number, a serial number, or an arbitrarily
 assigned Dumber.  The  program uses this number to  track the total-to-
 date cost of this piece of equipment.  If this equipment item is removed
 from the site for a period of time and then returned, you should enter the
 same ID code used when it was previously on-site.  You will have to enter
 any previous cost-to-date when prompted.

 The program will prompt you for the following rate information:

 •      Hourly Rate
 •      Dairy Rate
 •      Weekly Rate
 •      Monthly Rate

 Note: The program may display default rates for listed equipment items if a                  is
 contractor rate file has been previously loaded. If the listed rates are correct                   J?
 simply press  at each prompt to accept them; otherwise, type over                   ?
 the incorrect information  with the correct rates.                                             $

 Once this data is verified, you will be required  to enter the following:

 •       Purchase Price                                                                 /;,

The purchase price is the contractor's acquisition cost for that  particular
item and is available from the ERCS response  manager or field clerk.                      "-':•

The system will continue to prompt you for the following data:

 •       Mileage Charge
 •       Mob/Demob Rate                                                              .;
 •       Standby On Rate                                                               ^
 •       Standby Off Rate                                                               f
 •       Fixed or Provisional  Rates                                                      5
3-16

-------
      ACME ENTERPRISES
                                ADDING LISTED EQUIPMENT
                                      06/01/89
    049  TRUCK BOX 2 TON
    ID: 123456   Ctr Code: 0001
            Please enter the appropriate rates below  for this item
            If a particular rate does not apply -  Leave as zero [0]
         Hourly Rate :
         Weekly Rate:

         Purchase Price:
         Nob/Demob Rate:
                Daily Rate:
                Monthly Rate:

                Mileage Charge:
         Standby On Rate:        S5 X       Standby Off Rate:
         Fixed or Provisional Rates? CF/P]:   |
                 Is  the  above information correct?  [Y/NJ
                         per idle


                         X
          Some  of the  requested information may  not be applicable for your
          particular piece of equipment In that case, the proper response is to enter
          the default value of "6" for that prompt. If you have selected an equipment
          item that has previously been entered, all previously entered rates will be
          displayed.  You will then have the option of either using those rates (by
          entering a "U") or editing them (by entering "E").

          After verifying the above information, you will  be prompted for:

          •       Previous Cost to Date
ACME
ENTERPRISES
ADDING
LISTED
EQUIPMENT
06/01/89
   045  TRUCK STAKEBED  2 TON   ID: 3454
                Ctr Code: ACME
           Please enter  the appropriate rates below for this item
           If a particular rate does not apply  - Leave as zero [0]
        Hourly Rate  :
        Weekly Rate:

        Purchase Price:
        Mob/Demob Rate:
  8.04
402.22

  0.00
     0 X
Daily Rate:
Monthly Rate:
  80.44
1206.65
Mileage Charge:     0.00 per Mile
        Standby On Rate:        20 X       Standby Off Rate:      0 X
        Fixed or Provisional Rates? [F/P]:   F
Enter any previous total cost to date for  this specific Item:       0.00
If item has not previously been on the job,  leave as zero [0].
 Enter this charge only if the particular piece of equipment has been previously
 on-site under the current delivery order number.  The  "previous cost to date" is
                                   3-17

-------
 used to assure that  the  EPA does not pay more than the acquisition cost for
 equipment on any particular delivery order.

 The computer will next inquire if this particular equipment is subject to a G&A
 surcharge.  In general, equipment items that have a negotiated price  under the
 ERCS  contract  and are  owned  by the contractor, are  not subject  to G&A.
 However, rented equipment items are subject to such charges.

 After  entering verification of your data entries, you will  be prompted for the
 following daily charge information  for  the  particular 1900-55  Form you  are
 preparing:

 If you enter stand-by hours, you will be requested to identify whether the stand-
 by is on- or off-site.

 If a  mobilization/demobilization rate and/or mileage rate pertains to this piece of
 equipment you will be prompted for one, or both, of the following items:

 •       Number of Mobilization Hours
 •       Mobilization Mileage
ACHE ENTERPRISES
ADDING LISTED
EQUIPMENT
06/01/89
  077  BACKHOE CASE 580
ID: 954      Ctr Code:  ACME
       This Equipment Item is subject to a Mobilization Charge.
       Please enter Mobilization Hours and Mileage (if applicable).

              . Enter Number of Mobilization Hours:   4.0

          Enter Mobilization Mileage for this item:    450.0

                   Is this information correct?   Y
The program will then prompt you for the following:

•       Regular Hours
•       Standby Hours
                                3-18

-------
ACNE
ENTERPRISES
ADDING
LISTED
EQUIPMENT
06/01/89
  077  BACKHOE CASE 580       ID: 954     Ctr Code: ACME




       Enter Regular and Standby Hours incurred today for this  Item:

       Regular Hours    8.0                 Standby Hours     0.0
        If a mileage rate pertains to this piece of equipment you will be prompted
        for:

        •       Daily mileage

        The program will now return to the Adding Listed Equipment screen. You
        can continue to add listed equipment items in this fashion until all listed
        contractor equipment  resources have been added for that day, or you can
        press  the  key to exit this section and  return  to the  1900-55
        Equipment Menu.

2.      Option 2: Add Non-Listed Equipment

        This Option allows you to add equipment items that are not listed in the
        negotiated ERCS contract The program will display the Adding Non-Listed
        Equipment screen. To enter a non-listed piece of equipment, first enter
        a three digit equipment code within the range of 343 - 999. You will then
        be prompted for a contractor code, equipment identification, rate, and daily
        charge information similar to Option 1: Adding Listed Equipment, above.

        The next time  this equipment is selected, the rates that you have entered
        will be displayed as the default rates. These  rates become associated with
        the piece of equipment you choose to assign.

3.      Option 3: Edit/View/Delete Equipment

        Select this Option to save, view  or delete entries  within the  current
        Contractor Personnel File. The program will display the current Contractor
        Equipment File in list form.  Use one of the "Action Keys" from the Edit
        Menu to edit, view, or delete individual entries in this file.
                                3-19

-------
        Note:  See pages 3-11 and 12 for instructions on using the Edit
        Menu.  An  in-depth  explanation   of the  mechanics   of  the
        Edit/ViewlDelete Option is found in Appendix A.

 a.      Deleting  Equipment Items

        Deleting  equipment  items  differs  from the process of deleting
        personnel and expendable material items.  The ERCS contracts
        prohibit EPA from paying more than the acquisition cost for an
        equipment item.  RCMS tracks the daily charges on each piece of
        equipment and  notifies you when  these charges  reach  the
        acquisition cost.  If you delete an item from the equipment file and
        then restore it in a subsequent 1900-55 Form, RCMS will treat
        it as a  new item and its rate tracking clock is set back to Day  1.
        Thus, exercise caution when you are considering deleting an item.
        You can restore deleted equipment  items up until you print a final
        1900-55 Form for a particular day. Once a final 1900-55 Form has
        been printed, a deleted item cannot be restored.

 Note: If you wish  to delete an  equipment item because of a data  entry error,
 be sure to zero all hourly charges including mobilization, demobilization, and
 decontamination, otherwise the printed 1900-55 Form will list these charges
for the equipment item.

        When you mark an equipment item for deletion, and confirm your
        action,  RCMS will prompt you to  enter decontamination and
        demobilization charges for the item, if applicable.  In response to
        this action, the computer will respond to the "Delete" function by
        displaying three (3) asterisks in the place of the record number
        free #"), however,  the  item will continue  to  appear in  the
        equipment list.  If there are any charges  for a deleted item, the
        item will  appear  on  the  1900-55  Form for that day, but  will not
        appear  on following days. If there are no charges for an item that
        has  been marked for deletion, the item will not appear on the
        current 1900-55 Form.
                        3-20

-------
ACME ENTERPRISES
Rec
*
1
2
3
4
•• 5
6
Item Coot Item
Code Code ID *
043 0001 654321
049 0001 123456
062 0001 342355
064 0001 124755
075 0001 744323
084 0001 643443

Name
TRUCK PICK UP
TRUCK BOX 2 TO
TRLR OECON 8X2
TRLR OFF 8X40
TRUCK ROAD TRA
LDR FT CAT 955/
Demobilization charges are not
applicable to this item or
this item has not been deleted
from the equipment list.
Hit ENTER to continue.
IH 17 8.0 0.0 n/a
n/a
Are you sure you want to delete this entry? [Y/N] $
       4.      Option 4:  Print Draft 1900-55 Equipment Page

               By choosing this  Option, you can  print and  review a draft  of the
               Equipment Page for your particular 1900-55 Form. You will be prompted
               for all necessary information. Remember, a printer must be connected and
               filled with paper before you can proceed.
D.    Update Contractor Expendable Materials File

       Select this Option to update the Expendable Materials File.  The computer will
       respond to this Option by displaying the Update Expendable Materials Menu.

       This menu offers  you the option of updating either the Unit Rate Materials file
       or the At Cost Materials file.

       Under the new ERCS contracts, all expendable materials are considered "at cost,"
       meaning  that the  charge to the EPA is for  the cost of materials plus G&A (as
       opposed  to earlier ERCS contracts that negotiated unit charges for "inventory"
       items.)  For convenience, RCMS allows you  to enter expendable materials under
       either the "Unit Rate"  or "At Cost"  category.  However, the Unit Rate file is
       recommended  for items expended periodically in units  (e.g., Tyvek suits,  filter
       cartridges, disposable gloves, etc.). The At Cost file is more appropriate for one
       time or infrequent purchases (e.g., cinder blocks, lumber, coolers, etc.).
                                      3-21  '

-------
  ACHE ENTERPRISES
UPDATE EXPENDABLE MATERIALS MENU
01/01/89
       1.  Update Unit Rate Materials File

       2.  Update At Cost Materials File

       0.  Return to 1900-55 Menu


          Your Choice:
1.      Unit Rate Materials Menu

       This Menu offers you the option of adding, editing, viewing or deleting
       entries within the Unit Rate Materials file.

       a.      Option 1:  Add Entries to Unit Rate Materials File

               This  Option will prompt you for the following information:

               •      Name of Material
               •      Contractor Code
               •      Vendor  Code

               The Vendor Code is useful for organizing material costs according
               to vendor.  If you are using a new vendor, enter a unique (4)
               character (numbers and/or letters), identification vendor code and
               press . The program will ask for the vendor name and
               then  return you  to the data  entry screen.  Remember to use this
               code  anytime there are purchases from this vendor.

               The  computer will  now  prompt  you  for further information
               regarding the type of material you have entered into RCMS:

               •      Purpose
               •      Use or Type Code

              The Use or Type Code  is  used to organize materials by their
              purpose. If necessary, you can press  to display the current
              use or type code list.  If you  are entering a new use for a piece of
              equipment, you will have to create a Use Code.  Enter a  unique
              one  (1)  character (number  or letter) code to  distinguish  this
                               3-22

-------
                purpose, then press the < ENTER > key.  RCMS will now ask for
                a description of code.  Once entered, RCMS will return  to the
                Data Entry screen.

                The program will now continue by requiring the following:

                •       Unit Name
                •       Number of Units
                •       Unit Cost
                        G&A Charge

                RCMS will now calculate and display the following:

                •       Cost for this entry
                •       G&A Charge
                •       Total Cost
     ACME ENTERPRISES
                     ADDING UNIT RATE MATERIALS
06/01/89
                Please Enter the Following Information:
       Name of Material:
       Contractor Code:
       Vendor Code:

       Purpose:
       Use or Type Code:
       Unit Name (gal,Its, etc.):
       Number of Units:
       Unit Cost:
       G t A Charge:

       Cost for this entry:
       G t A Charge:
       Total Cost:
                                    SACME* ENTERPRISES
                                    HAZ MAT CO.
                           $ 1098.75
                           $ 109.88
                           S 1208.63
       Is the above information correct? [Y/N]  |
b.
Once you have verified all information, the system will return you to the
"Name of Material* prompt You can now either continue to enter material
or return to the Unit Rate Materials Menu by pressing .

Materials entered on previous days will remain within  the Unit Rates
Materials File, but the number of units used will automatically be re-set
to zero  ("0") each day.  It is for this reason that the Unit Rates Materials
File is ideal for tracking  items used on a recurring basis  (e.g., disposable
gloves, tyveks, etc).

Option 2: Edit/View/Delete Unit Rate Materials Entries

Select this Option to modify, review or erase individual records within the
Unit Rates Materials File.  The Action Keys, displayed in the Edit Menu
                                3-23

-------
               at the bottom of this screen, will assist you in making use of the available
               functions.

               Note: See pages 3-11 for an explanation of the Edit Menu and its Action
               Keys.  A more in-depth discussion of the EdufViewlDelete Section  can be
               found in Appendix A.
       c.      Option 3:  Delete All Current Unit Rate Materials Entries

               This Option  enables you to delete  all entries within the Unit  Rates
               Materials File at a single time, rather than deleting each entry individually
               using the Delete function offered in Option 2:  Edit/View/Delete Unit Rate
               Materials Entries (see above).

               You will be  prompted for all necessary information.  Please note, this
               Option does not have a separate screen. Instead, the RCMS prompts will
               appear below the Unit Rate  Materials Menu  listing.

       d.      Option 4:  Print Draft 1900-55 Unit Rate  Materials Page

               This Option allows you to print and review a  draft copy of the Unit Rate
               Materials page of the 1900-55 Form you are preparing.

               Note:  A printer must be connected and loaded with paper before you can
               proceed.
2.      Option 2: At Cost Materials Menu

       This menu offers you  the option of adding, editing, viewing or deleting entries
       within the At Cost Materials file. The structure of this section is similar to Unit
       Rate Materials except for the different prompts encountered when adding entries.

       a.      Option 1: Add  Entries to At Cost Materials File

               You will be prompted for the following information in a format similar
               to that encountered in Option 1: Add Entries to the Unit Rates Materials
               File, page 3-22:

               •      Name of Material purchased
               •      Contractor Code
               •      Vendor Code (see page 3-22)
               •      Purpose
               •      Use or Type Code (see page 3-22)
               •      Quantity/Amount
               •      Purchase Cost
               •      G&A Charge

              RCMS will calculate and display the Total Charge" for this material.
                                      3-24

-------
    ACME ENTERPRISES
                      ADDING AT COST MATERIALS
                                                      06/01/89
                Please Enter  the Following  Information:
                (Enter a blank to exit)
Name of material purchased:

Contractor code:

Vendor Code:

Purpose:
Use or Type Code:

Quantity/Amount:
Purchase Cost:
G & A Charge:

Total Charge:
                           |%


                           *
                           YES. AT

                           * 19.78
                                            ACME ENTERPRISES

                                            BEST CO.
                                            SAMPLfNG/SHPNC
       Is the above information correct?  [Y/N] |
b.
You will now be prompted to verify the displayed information. Once you
have done so, you will be returned to  the "Name of material purchased*
prompt. You can now either continue  to enter new material, or, you can
press < ENTER> to return to the Update At Cost Materials Menu.

Option 2:  Edit/View/Delete At Cost Materials Entries

Select  this Option to modify, review or  eliminate individual records within
the At Cost Materials  File. The Action Keys, displayed in the Edit Menu
at the  bottom of the screen, will assist  you in making use of this Options
available functions.

Note:  See pages 3-11  and 12 far an explanation of the Edit Menu and its
Action Keys. A more in-depth discussion of the EditfViewlDelete Section can
be found in Appendix A.

Option 3:  Delete All Current At Cost Materials Entries

This Option enables you to delete all entries within the At Cost Materials
File at a single time, rather than deleting each entry individually using the
Delete function offered in Option 2: Edit/View/Delete At Cost Materials
Entries (see above).

You will  be prompted for all necessary  information.  Please note, this
Option does not have a separate screen. Instead, the RCMS prompts will
appear below the At Cost Materials Menu.
                                3-25

-------
        d.      Option 4:  Print Draft 1900-55 At Cost Materials Page

               This Option allows you to print and review a draft copy of the At Cost
               Materials page of the 1900-55 Form you are preparing.

               Note:  A printer must be  connected and filled with paper before you can
               proceed.
E.     Option 5:  Update  Subcontractor File

        Select  this Option to update  the subcontractor file  and display  the  Update
        Subcontractors Menu.

        Generally, subcontractors constitute the majority of the total cleanup cost  at a
        removal site. Thus, careful tracking of these subcontractors is vital to accurate cost
        management.  Frequently, when  a subcontractor service is provided, the exact cost
        of the service will not be known. In that instance, the estimated amount is entered
        as an  "Await Bill" entry, (meaning the cost is only an estimate). All Await Bills
        remain in the  Subcontractor File until  finalized.  When a Final Bill  is obtained,
        the  actual cost can be entered by editing the Await Bill entry and marking the
        entry as "Final."  This Final Bill entry will be listed on the  1900-55 Form for the
        day  it was deemed  final, and then deleted from the subcontractor file.

        Often, final costs for entries are unknown and Await Bills are carried for a long
        time.  As a result, the number  of Await Bills in the system can increase to an
        unwieldy amount. RCMS helps  mitigate this situation in two ways: 1) only Await
        Bills entered or edited on a particular day ("new" Await Bills) will appear on  that
        day's 1900-55 Form; and 2) when editing subcontractor entries, you can limit the
        entries  that  appear on  the edit screen to a particular  date  range and/or
        subcontractor.  RCMS also allows you to print a list of all outstanding Await Bills.
        The total outstanding Await Bills estimate will appear on both the 1900-55 Form
        and  the Daily Cost Summary.

        The Update Subcontractors Menu gives you the option of adding, editing,  viewing
        or deleting entries  within the subcontractors file. It also enables you to print a
        draft copy of the 1900-55 subcontractor page.

1.       Option 1: Add  Subcontractor Entries

        Select  this Option  to add subcontractor entries.   You  will be prompted for the
        following information:
                                       3-26

-------
 •       Listed Contractor Code

Enter the contractor code that corresponds to the contractor who is enlisting the
subcontractor's services.  Do not confuse this code with the  subcontractor code
which follows. Now the computer will request the following:

 •       Subcontractor Code

Enter a unique four (4) character (numbers and/or letters) code to designate this
particular subcontractor.

        Note:  This code is not to be confused with the code for ERCS contractors or
        the vendor code used in  the Expendable Materials section.
The program will now prompt you for the name of the new subcontractor.  Once
entered, you will be returned to the data  entry screen.   The program will now
display the subcontractor name, and continue by prompting you for the following:

•       Invoice Number
•       Subcontractor Service
•       Date of Service
•       Subcontractor Service Type

The Subcontractor Service Type is a code used to organize subcontractor entries
by the type of service performed. To enter this data, either press  to display
a list of all subcontractor Service Type codes currently in RCMS, and choose a
code from this list, or establish a new code to designate the type of service.  The
program will then continue by prompting you for the following:

•       Subcontractor Cost
•       Final  [F] or Awaiting Bill [A]
•       G&A Charge
    ACME ENTERPRISES
ADDING SUBCONTRACTORS
06/01/89
       Please Enter the Following Information (Enter a Blank to Exit):

       Listed Contractor Code:       0001:
       Contractor Name:             ACME ENTERPRISES

       Subcontractor Code:           
-------
        The computer will calculate and display the "Total Charges' from the data you have
        entered.  Once you verify the entered data, you will be returned to  the 'Listed
        Contractor Code' prompt  You can now either continue to make entries, or return
        to the "Update Subcontractors Menu" by pressing < ENTER >.

 2.      Option 2: Edit/View Subcontractor Entries

        Select this Option  to modify and review individual entries within the current
        Subcontractors  File.  Unlike other Edit/View/Delete sections within RCMS,  the
        system responds to  this particular Option with  a pair of prompts. You will be
        asked if you wish to limit the list of subcontractors to be edited by either: 1: a date
        range, or  2:  a particular  subcontractor. Once you enter a  response  to  these
        prompts, this Option returns to  the standard RCMS Edit/View/ functions.

               Note:  Subcontractors can not be deleted from the system.
               Note:  See pages 3-11 and 12 for an explanation of the displayed Edit Menu
               and  its  available  functions.    A  more  in-depth  discussion  of  the
               EditlViewlDelete Option can be found in Appendix. A.

        This Option also allows you  to enter the  type of operation performed  by  the
        subcontraaor. You also have the  capability to change the status of bills from
        Await to Final if necessary.

3.      Option 3:  Print Draft 1900-55 Subcontractor Page

        This Option allows you to  print and review a draft copy of the Subcontractors
        page of the 1900-55 Form you are  preparing.
               Note:  A printer must be connected and filled with paper before you can
               proceed.
4.      Option 4:  Print All Outstanding Subcontractor Await Bills

        Select this Option to  obtain a printout  of the complete  Await Bill list.  The
        program will prompt you to ready the printer before printing.


F.      Option 6:  Update Comments and Adjustments To  1900-55
        Totals

        Select this Option to update the Adjustments/Comments File. The program will
        respond  to this Option by  displaying the Update  Adjustments and  Comments
        Menu.
                                      3-28

-------
         ACME ENTERPRISES
UPDATE ADJUSTMENTS AND COMMENTS MENU    06/01/89
              1. Add Entries to Adjustments/Comments

              2. Edit/View/Delete Adjustments/Comments Entries

              3. Delete All Current Adjustments/Comments Entries

              4. Print Draft 1900-55 Adjustments Page

              0. Return to 1900-55 Nain Menu


                 Your Choice:
       You can enter adjustments to any section of the 1900-55  Form to account for
       errors or omissions made in the previous day.  You can also use this section to
       clarify a cost entry.

       The menu gives you the  option of adding, editing, viewing  or deleting entries in
       the Adjustments/Comments file. You will also be able to print a draft copy of the
       1900-55 Adjustments and Comments page.

1.      Option 1: Add Entries to Adjustments/Comments

       Select this Option to add entries to the Adjustments/Comments file.  The program
       will prompt  you for information about the Adjustment and/or Comment you wish
       to make with  long  highlighted  fields.   RCMS allows up to  five lines  for a
       Comment.  If you choose to enter a Comment of less than five lines, simply press
       the < ENTER > key when you complete your entry, making sure the cursor is at
       the beginning of the next blank line.

       Once you have entered your Comment, you will be  prompted  to  enter  the
       corresponding contractor code. You can  review the complete contractor list  by
       pressing the  key.   Next, the computer will prompt you for the Adjustment
       amount.  Enter a zero ("0") or press < ENTER > at a blank line if your Comment
       does not have a corresponding Adjustment.

       If you  do wish to enter an Adjustment, RCMS will now prompt you  for  the
       Adjustment  Category. The computer will display a list of categories from which
       to choose your entry. After entering the appropriate response you will be returned
       to a  blank comment line. You can continue  to enter Comments in this  fashion,
       or you can press  when the cursor is at the start of a  blank line to
       return to the Update Adjustments and Comments Menu.
                                      3-29

-------
ACME ENTERPRISES
ADDING ADJUSTMENTS/COMMENTS
06/01/89
                         Please Enter the Following Information


           Adjustment/Comnent:     OSC 9J$fuTE« iAfitY ARRIVAL G? CAT '954

           Listed Contractor  Code: 9001
           Contractor Name:        ACME ENTERPRISES
           Adjustment Amount:                Comment
           Adjustment Category:    |

           Adjustment Categories:  (P) Personnel             (A) At Cost Materials
                                 (E) Equipment             (S) Subcontractors
                                 
-------
G.     Option  7:   Calculate and Print 1900-55 Form

       Select this Option to print a copy of the complete 1900-55 Form.  The program
       will inquire if you would like to print a draft (*D") or final ("F") version of the
       1900-55 Form.
             ALWAYS PRINT A DRAFT 1900-55 FORM FIRST TO VERIFY ITS
             ACCURACY AND TO CHECK YOUR WORK

             YOU CANNOT RETURN TO THE 1900-55 DATA AFTER PRINTING A
             FINAL FOR THAT DAY.

       After printing a Final 1900-55  Form, RCMS will inquire  if a valid  copy was
       printed. If you do not have a valid copy the program will return to the 1900-55
       Form Main Menu, from which you can try again. If a valid copy has been printed,
       the program will return to the 1900-55 and Daily Cost Summary menu.
      Exhibit m-A shows a final 1900-55 Form.
                                  3-31

-------
Exhibit m-A

HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 1
US ENVIRONMENTAL PROTECTION AGENCY [CONTRACTOR: CONTRACT #
SITE NAME: ABC DRUM ACME ENTERPRISES 43-92-2334
CONTRACTOR PERSONNEL REPORT (DELIVERY ORDER * DATE
EPA STANDARD FORM 1900-55 2334-56-703 01/01/89
1
1.

EMPLOYEES
ice f eycn
nO9i URCw

2.

WORK


i
3.
HOURLY
LABOR RATES

REG

ERCS CONTRACTOR 0001: ACME ENTERPRISES
WAGNER, JIM | 001: SUPERVISOR
G and A Charge
HEART, G. j 003: CLEANUP TECH-HAZ
G and A Charge
ROE, DONNA j 003: CLEANUP TECH-HAZ
G and A Charge
CHAPMAN, MARK J004: LABORERS
G and A Charge
MORRIS, JIM J005:EQUIP OPERATOR
G and A Charge
LARES, LYNN J006: TRUCK DRIVER
G and A Char
K1NGLE, DON
G and A Char

e
014:ENGINEER CHEMICAL
e

43.00

21.50

21.50

21.50

25.00

23.50

43.00

	 1
OT


64.50

32.00

32.00

32.00

37.50

35.50

63.00

I
4.
TOTAL
HOURS

REG


8.00

8.00

8.00

8.00

8.00

8.00

8.00

1
OT


0.00

0.00

0.00

0.00

0.00

4.00

0.00

1
5.
TRAVEL,
LODGE,
»DCD
rcR
DIEM


232.00

232.00

232.00

232.00

232.00

83.00

232.00

1
6.
TOTAL
PERSONNL




576.00
23.20
404.00
23.20
404.00
23.20
404.00
23.20
432.00
23.20
413.00
8.30
576.00
23.20
3356.50
7. \ 8.
TOTAL PERSONNEL COST TO DATE: TOTAL PERSONNEL COST FOR TODAY:
* 6713.00 S 3356.50
   3-32

-------
Exhibit m-A (continued)
HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 2
US ENVIRONMENTAL PROTECTION AGENCY {CONTRACTOR: CONTRACT *
SITE NAME: ABC DRUM ACME ENTERPRISES 43-92-2334
CONTRACTOR EQUIPMENT REPORT {DELIVERY ORDER * DATE
EPA STANDARD FORM 1900-55 2334-56-703 01/01/89

9.

EQUIPMENT
ITEM

10.

EQ
ID

11.

TOT
DAY

12.


HOURS

ERCS CONTRACTOR 0001: ACME ENTERPRISES
043 .-TRUCK PICK UP
049: TRUCK BOX 2 TON

Mob Mileage Charge
Mileage Charge
062:TRLR DECON 8X25
064:TRLR OFF 8X40

075: TRUCK ROAD TRACTOR
084:LDR FT CAT 955/IH 17

ERCS CONTRACTOR 0001: AD.
(1) OSC DISPUTES EARLY t

654321
123456
2 8.0
1 8.0
4.0
410.0 Miles a J
13.

WORK
STATUS

REG
MOB
REG
14.


RATE

DL
DL
HR
0.33/Mite
12.0 Miles a $ 0.33/HUe
342355
124755

744323
643443

USTMEN
ARRIVAL
i
2
1

2
2

s/co
OF D
i
8.0
8.0
8.0
8.0
8.0

MENTS
T 955
i
REG
MOB
REG
REG
REG



i
DL
DL
DL
DL
DL




15.
COSTS

TODAY'S
COST
32.00
36.75
56.00
135.30
3.96
55.50
25.73
47.77
200.00
468.00
1061.01


i
TOTAL TO
DATE
64.00

92.75


111.00

73.50
400.00
936.00




16. ' 17.
TOTAL EQUIPMENT COST TO DATE: TOTAL EQUIPMENT COST FOR TODAY:
% 1816.51 % 1061.01
'
         3-33

-------
Exhibit in-A (continued)
1 	
HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 3
US ENVIRONMENTAL PROTECTION AGENCY '.CONTRACTOR: CONTRACT *
SITE NAME: ABC DRUM JACME ENTERPRISES 43-92-2334
CONTRACTOR UNIT RATE MATERIALS .'DELIVERY ORDER * DATE
EPA STANDARD FORM 1900-55 J2334-56-703 01/01/89
i i —
18.
MATERIAL
19.
PURPOSE
20.
UNITS
ERCS CONTRACTOR 0001: ACME ENTERPRISES
OVERPACKS
G and A Charge
OVERPAYING
EA
21. -
QUANTITY
75.0
22.
UNIT
COST
14.650
23.
COST
1098.75
109.88
1208.63
— - —
24. ' 25.
TOTAL U.R. MATERIAL COST TO DATE: TOTAL U.R. MATERIAL COST FOR TODAY:
$ 1208.63 * 1208.63
          3-34

-------
Exhibit m-A (continued)
	 — 	 	 1
HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 4
US ENVIRONMENTAL PROTECTION AGENCY j CONTRACTOR:
SITE NAME: ABC DRUM ACME ENTERPRISES
CONTRACTOR AT COST MATERIALS (DELIVERY ORDER «
EPA STANDARD FORM 1900-55 J2334-56-703
26.
MATERIAL
PURCHASED
ERCS CONTRACTOR OCX
COOLER
G and A Charge
27.
PURPOSE
28.
AMOUNT/
QUANTITY
1: ACME ENTERPRISES
SAMPLE SHIPMEN
1
29.
VENDOR
BEST CO.
CONTRACT #
43-92-2334
DATE
01/01/89
30.
VEN
CODE
BEST
31.
COST
17.98
1.80
==s=s=3=
19.78
32. 33.
TOTAL A.C. MATERIAL COST TO DATE: TOTAL A.C. MATERIAL COST FOR TODAY:
$ 19.78 $ 19.78
         3-35

-------
Exhibit m-A (continued)
- - 1
HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 5
US ENVIRONMENTAL PROTECTION AGENCY {CONTRACTOR: CONTRACT *
SITE NAME: ABC DRUM ACME ENTERPRISES 43-92-2334
SUBCONTRACTOR NEW AWAITING BILL REPORT {DELIVERY ORDER * DATE
EPA STANDARD FORM 1900-55 J2334-56-703 01/01/89
43.
SUBCONTRACTOR
44.
INVOICE
45.
SUB
CODE
SUBCONTRACTOR BILLS EDITED TODAY:
ERCS CONTRACTOR 0001: ACME ENTERPR
QUALITY LABS
G and A Charge

ERCS CONTRACTOR 0001
JERSEY CENTRAL P&L
G and A Charge

SUBCONTRACTOR SERVICE
S - SAMPLING AND A»
U - UTILITIES

34324312

ACME EN
12345678

CODES:
IALYSIS
I
0004

47. j-
SERVICE
SES
CYANIDE ANALYSIS

ERPR I SES
JCPL



ELECTRIC HOOKUP



51.
NEW SUBCONTRACTOR CHARGES AWAITING FINAL BILLING ADDE
(NOT INCLUDED IN 1900-55 TOTALS) $ 1
18
T
Y
P
E
S

U


_l
D
02
! 49.
SERVICE
DATE
12/31/88

01/01/89


I
I
I
50.
COST
400.00
40.00
440.00
935.00
93.50
1028.50


TODAY:
8.50
52.
TOTAL SUBCONTRACTOR CHARGES AWAITING FINAL BILLING AS OF THIS DATE:
(TOTAL NOT INCLUDED IN 1900-55 TOTALS) $ 1468.50
— 	 	 _ ., ,. .. ... _. 	 . .1
        3-36

-------
Exhibit IH-A (continued)
HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 6
US ENVIRONMENTAL PROTECTION AGENCY [CONTRACTOR: CONTRACT *
SITE NAME: ABC DRUM ACNE ENTERPRISES 43-92-2334
COMMENTS AND ADJUSTMENTS {DELIVERY ORDER * DATE
EPA STANDARD FORM 1900-55 j 2334 -56 -703 01/01/89
i >
53.
ADJUSTMENT/COMMENT
ERCS CONTRACTOR 0001: ACME ENTERPRISES
(1) OSC DISPUTES EARLY ARRIVAL OF CAT 955
54.
ADJ
TYPE
EQIP
55.
PLUS
OR
MINUS

56.
AMOUNT

57. 58.
TOTAL NET ADJUSTMENTS TO DATE: TOTAL NET ADJUSTMENTS FOR TODAY:
* 0.00 * 0.00
TOTAL ERCS COSTS TO DATE: TOTAL DAILY ERCS COSTS:
$ 9757.92 $ 5645.92

SIGNATURE OF OSC DATE SIGNATURE OF CONTRACTOR'S DATE
REPRESENTATIVE AUTHORIZED REPRESENTATIVE
i
         3-37

-------
                               CHAPTER 4
                       DAILY COST SUMMARY
4.0   DAILY COST SUMMARY OVERVIEW

The Daily Cost Summary (DCS) provides a complete listing of the cost components for a
particular removal action. This includes costs for all cleanup contractors (e.g., ERCS), as
well  as EPA, TAT, and other Federal agencies (such as  the U.S. Coast  Guard).  In
producing the Daily Cost Summary, RCMS uses the cleanup contractor's costs from  the
1900-55 Form.  Other costs, such as EPA and TAT, are entered by you through use of the
DCS module. This module contains an option for making adjustments for costs other than
those related to the 1900-55 Form. Once all cost data is entered, the DCS module enables
you to produce the required  Daily Cost Summary Form as well as  an optional Detailed
Cost Listing of non-cleanup contractor's related costs.

Samples of  a Daily Cost Summary and a Detailed Cost Listing are illustrated in Exhibits
IV-A and IV-B, at the end of this chapter.

4.1   PREPARING THE DAILY COST SUMMARY (DCS)

To begin preparing your Daily Cost Summary, select Option 4:  Daily Cost Summary from
the 1900-55 and Daily Cost Summary Menu.
       RCMS VERSION 3.2
1900-55 AND DAILY COST SUMMARY
06/01/89
                1. List Cost Report Status

                2. Use Current Cost Data on the Hard Disk

                3. Load Last Final Data from Archive Disk

                4. Start New Site (Erase Current Files on Hard Disk)

                5. Initiate an Additional Cleanup Contractor

                0. Return to Previous Menu

                  Your Choice:
The computer will respond to this choice by displaying the Daily Cost Summary Date Input
screen.
                                     4-1

-------
The computer will prompt you to enter the date of the DCS you want to prepare.
                Note: Before you can enter the Daity Cost Summary program, a 1900-55 Form
                must be printed for the day. If there is more than one prime contractor in
                the  system, a 1900-55 Form  must be printed for at least one  of them.
                However, if a prime contractor did not incur costs on a particular day, it is
                not  necessary to produce a 1900-55 Form for that contractor.   Remember,
                once a final DCS has been printed, you will not be able to prepare any further
                1900-55 Forms for that day.
         DAILY COST SUMMARY
DATE INPUT
06/01/89
               Last Final Dally Cost  Summary printed:  12/31/68
               Last Final Daily Cost  Sunnary archived: 12/31/88
               Current Daily Cost Sunnary data stored: 01/01/8°
                  Enter the date of  the DCS that you wish to prepare
                   If a draft DCS for that date is already stored,
                     the data will  be loaded into the current  files
                            Enter a blank to exit  MtfftM

Once you  enter the date of the  DCS to be prepared,  the computer will  respond by
displaying the Daily Cost Summary Main Menu.
         DAILY COST SUMMARY
MAIM MENU
06/01/89
               Select an Option below:
                   1. Update Project Ceilings
                   2. update EPA Costs
                   3. Update Other Federal  Agency Costs
                   4. Update TAT Costs
                   5. Update Other Costs
                   6. Update DCS Adjustments
                   7. Print Daily Cost Sumary
                   0. Exit
                 Your Choice:  H
                                         4-2

-------
The  procedures for completing a Daily Cost Summary form  are similar  to  those  for
completing a 1900-55 Form. The program relies on the user to  keep the files up to date.
This updating process includes adding, editing, and deleting entries from the various files.
As with the 1900-55 software, the contents of each file can be updated by entering  the
appropriate number from the Main Menu. The paragraphs that follow include a general
discussion of each of the options on the Daily  Cost Summary  Main Menu, and present
examples of the screens encountered when a particular option is chosen.

4.2   DAILY COST SUMMARY MAIN MENU OPTIONS

A.     Option 1:  Update Project Ceilings

       Select  this Option from the Daily Cost Summary Main Menu to update project
       cost ceilings. The computer will respond by displaying the Update Project Ceilings
       screen.

       To enter the total Site, Prime Cleanup Contractor(s), and TAT ceilings, choose the
       appropriate  option from the Update Project Ceilings screen.
         DAILY COST SUMMARY
                                   UPDATE PROJECT CEILINGS
06/01/89
                  1. Update Total Site Ceiling

                  2. Update Prime Cleanup Contractor Ceiling(s)

                  3. Update TAT Ceiling

                  0. Exit


                     Your Choice: p
       The various cost ceilings for your particular project should be entered before any
       other data is introduced into the Daily Cost Summary files. RCMS will not allow
       you to print a Daily Cost Summary until the project ceilings have been entered.
       If there are multiple prime contractors for your project, each  contractor will have
       its own cost ceilings.

       To change a ceiling within any of the three Update Project Ceiling options, simply
       type in a new amount over the currently displayed one. The remaining balance will
       be adjusted automatically.

       Below, you will find an example of the screen displayed when you choose Option
       2: Update Prime Cleanup Contractor Ceiling(s). A response of yes ("Y") to the
       RCMS prompt will enable you to enter your new ceiling amount. The screens for
       updating Total Site and TAT Ceilings are virtually identical to  this one.
                                       4-3

-------
          DAILY COST SUMMARY
UPDATE  CONTRACTOR CEILINGS
                                                                     06/01/89
               Priiw Contractor Code: 0001
               Prime Contractor Name: ACME ENTERPRISES

               Ceiling for this contractor:                   250,000


               Do you wish to update this ceiling? [Y/N]  f
                Note: On the printed Daify Cost Summary any changes to the ceilings will be
                noted within the body of the DCS as a ceiling increase or decrease.   The
                resulting ceilings and balances will be shown at the top of the DCS on  the
               following day.
B.     Option 2:   Update  EPA  Costs

        Select this Option to display the EPA Main Menu.
         DAILY COST SUMMARY
                                          EPA MAIN MENU
                                06/01/89
                    1. Update On-Site Regional EPA Personnel

                    2. Update Off-Site Regional EPA Personnel

                    3. Update Non-Regional EPA Personnel  Hours

                    4. Update Regional and Non-Regional EPA Loaded Cost Rates

                    0. Exit
                      Your Choice:
       To update the different types of EPA costs directly incurred for a particular site,
       select the appropriate  number  from this menu.  The distinctions between these
       types of EPA costs are summarized as follows:
                                         4-4

-------
On-Site  Regional  EPA Personnel:   Direct  costs  incurred by  Regional EPA
personnel charging time to the site while working on-site.

Off-Site  Regional  EPA Personnel:   Direct  costs  incurred by  Regional EPA
personnel charging time to the site while working off-site (e.g., in the office or at
another site).

Non-Regional  EPA Personnel:  Direct costs incurred by Non-Regional EPA
personnel (e.g., ERT) charging time to the site while working either on or off- site.

        Note: Before adding entries to the EPA personnel files (Options 1 and 2) you
        should use Option 4 to enter the Regional and Non-Regional EPA Loaded
        Cost Rates. If you have not entered these rates, the computer will prompt you
        to do so each time you select the Update EPA Costs Option from the DCS
        Main Menu.

1.       Option 4: Update Regional and Non-Regional Loaded Cost Rates

        Select this Option to enter the Regional and Non-Regional EPA Loaded
        Cost Rates.  The computer will be prompt you for the following hourly
        rates:

        •      Direct  Regional On-site
        •      Direct  Regional Off-site
        •      Regional Indirect
        •      Non-Regional

        Regional On-site, Regional Off-site, and Non-Regional rates are all direct
        cost rates.  The Regional Indirect Hourly Rate is determined on  a periodic
        basis for each Region, and  is  used to account for Regional administrative
        and overhead costs charged to a site.  These rates are subject  to change
        by the Comptroller's office and should be periodically verified with the
        Financial Management Office  (FMO).

        Note: For further information on the EPA Hourly Cost Rate see the Removal
        Cost Management Manual
       After these rates are entered and verified, RCMS will return you to the
       EPA Main Menu.  There is no need to return to this section of the Daily
       Cost Summary unless these rates need to be changed.
                                4-5

-------
2.      Option 1: Update On-Site Regional Personnel

        Select this Option to display the On-Site Regional EPA Menu.
 DAILY COST SUMMARY
                           ON-SITE REGIONAL EPA MENU
           1. Add On-Site Regional  EPA Personnel

           2. Edit On-Site Regional EPA Personnel

           3. Delete All On-Site Regional EPA Personnel

           0. Exit


              Your Choice: I
06/01/89
                                   'Ar
                                   &
                                   $*
                                                                                            •
       a.      Option 1: Add On-Site Regional EPA Personnel

               Select this Option to enter On-Site Regional EPA personnel.  The
               program will respond by prompting you for the following:

               .•      EPA Personnel Name
                      Title
               •      Employee ID Number
               •      GS Level

               The job title, employee ID number, and GS level information are
               not required to print a DCS, however it is recommended that you
               include them.

               Once you have entered this data, the computer screen will display
               the Loaded Hourly Rate (previously entered using Option 4 from
               the EPA Main Menu). Press < ENTER > to verify this information.
               You will now  be prompted for  the following:

               •      Daily  Hours (hours worked  that day)
               •      Per Diem
                      Lodging
               •      Transportation
               •      Other Costs
                                   ..*
                               4-6

-------
  DAILY COST SUMMARY
ADDING ON-SITE REGIONAL EPA
06/01/89
        Enter EPA Personnel Name:              GREHiR, SON
        Title:                               OSC
        Employee ID Number:                   1234
        GS Level:                            H '

        Loaded Hourly Rate:                   $&$

        Daily Hours:
        Per Diem:
        Lodging:                              :58.«)
        Transportation:

        Other Costs:
        Cost Description:
        Is the above information correct? [Y/N]  f
                If data is entered in response to the "Other Costs" prompt, you will
                be requested to enter a description of these costs. Once you have
                entered and verified all necessary information, the program will
                return to the prompt requesting  an  EPA personnel name.  The
                program will continue in this cycle until you exit the screen with
                a blank response.

        b.   ,   Option 2: Edit On-Site Regional EPA Personnel

                Select this Option from the On-Site  Regional  EPA Menu to edit
                On-Site Regional EPA  Personnel data that has been previously
                entered into RCMS.  Personnel data should be edited on a  daily
                basis  to track the hours  charged to a site by individual  EPA
                personnel, as well as to change other personnel charges  (e.g. per
                diem, lodging, transportation).  Use the Extended  Edit Option,
                accessed by pressing  , for this purpose.

        Note: Remember to  use the Extended Edit  Option  to remove  and add
        transportation  charges, and also to remove and  add per diem and lodging
        charges when an EPA employee leaves the site for the  weekend, etc.

        Note: Data editing is standard through-out RCMS.  The Edit Menu and its
        /unctions are described on pages 3-11 and 12.  For a detailed explanation of
        the Edit Option, see Appendix A.

        c.       Option 3: Delete All On-Site Regional EPA Personnel

               This Option enables  you to erase all entries within the On-Site
               Regional EPA Personnel File at  a single  time.

3.      Option 2: Update Off-Site Regional EPA Personnel

        Choose  this Option from the EPA  Main Menu  to  update the Off-Site
        Regional EPA Personnel File. The use of this Option is virtually identical
        to  the Option for updating On-Site Regional EPA  Personnel (See Option
                                 4-7

-------
        1:  Update On-Slte Regional Personnel, pages 4-6 to 7), although certain
        prompts differ (this Option has no  per diem, lodging or transportation
        cost prompts).

        The hours for Off-Site Regional EPA Personnel are often difficult to track                    :;
        on a daily basis, so this Option allows you to accumulate them for a longer
        span of time, and then enter them accordingly.                                           4"

        a.      Option  1: Add Off-Site Regional EPA Personnel                                 .;'

               Select this Option to enter Off-Site Regional EPA Personnel into                   1
               the RCMS  File.   See Option 1:  Add On-Site  Regional EPA                   Jl
               Personnel, pages 4-6, for an explanation of the use of this Option.                   ;|
               Please remember, while they are quite similar, certain prompts may                   '$
               differ between these two Options.

        b.      Option 2: Edit Off-Site Regional EPA Personnel
                                                                                             . •£?.
               This Option allows you  to  modify entries  within the  Off-Site                   -."..
               Regional EPA Personnel File.  Unlike Option 2:   Edit On-Site                   ,^
               Regional EPA Personnel (page 4-7), you  may  choose to enter                   ; t
               hours based on a time span  longer than a single day.                              , "|f
                                                                                             :|
        Note: See pages  3-11 and 12 for an explanation of the standard RCMS Edit                   ;|;
       functions.  For  a detailed discussion of the EditlDeletelVlew Option,  see                   ;|
       Appendix A.                                                                           "$

        c.      Option 3: Delete All Off-Site Regional EPA Personnel                            -

               This Option enables you  to  erase all entries within the Off-Site
               Regional EPA Personnel File at a single time, rather than deleting                    •'
               each individually using the Edit Option. You will be prompted for
               all necessary information.

4.      Option 4: Update Non-Regional EPA Personnel Hours

        Select  this Option from the EPA Main Menu to update the Non-Regional
        EPA Personnel Hours File.  The Non-Regional EPA Personnel Menu will
        be  displayed.
                                4-8

-------
DAILY COST SUHMARY
NON-REGIONAL EPA PERSONNEL MENU
06/01/89
          1.  Add Non-Regional EPA Personnel

          2.  Edit Non-Regional EPA Personnel

          3.  Delete All  Non-Regional EPA Personnel

          0.  Exit


             Your Choice:
              Option 1:  Add Non-Regional Personnel

              This Option allows you to make entries to The Non-Regional EPA
              Personnel File.  The program will prompt for the following:

              •      EPA Personnel Name
              •      Organization
                     Title
                     GS Level

              The organization, title, and GS level are optional entries. Once
              all required and, if desired, optional entries are made, RCMS will
              display the loaded hourly rate previously entered through Option
              4 from the EPA Main Menu, (Update Regional And Non-Regional
              Loaded Rates, page 4-5). Press < ENTER > to accept this value
              and continue the program.

              You will now be prompted  to enter the following information:

              •      Daily Hours (hours worked that day)
              •      Per Diem
              •      Lodging
              •      Transportation
              •      Other Costs
                               4-9

-------
         DAILY COST SUMMARY
ADDING NON-REGIONAL EPA PERSONNEL
06/01/89
              Enter EPA Personnel Name:
              Organization:
              Title:
              GS Level:

              Loaded Hourly Rate:

              Daily Hours:

              Per Diem:
              Lodging:
              Transportation:

              Other Costs:
              Is the above information correct? [Y/N]
                      Once you have verified that the entered  information is correct,
                      RCMS will return to the "EPA Personnel Names" prompt.  You
                      can now either continue entering data, or exit this  Option by
                      pressing .

               b.      Option 2:  Edit Non-Regional EPA Personnel

                      This Option functions similarly to the Edit Options for On-Site
                      and Off-Site Regional EPA Personnel (pages 4-7 and  4-8).

        ,       Note:  See pages 3-11 and 12 for an explanation of the Edit Menu.  For a
      7         more detailed discussion of the standard RCMS Edit/View'/Delete  Option, see
               Appendix A.

               c.      Option 3:  Delete All Non-Regional EPA Personnel

                      Like the delete Options for On-Site and Off-Site Regional EPA
                      Personnel  (pages 4-7 and 4-8), this Option allows you to erase all
                      entries within a file (in this case, the Non-Regional EPA Personnel
                      File) at a single time, rather than deleting each entry individually
                      using  the Edit Option.  You will be prompted for all necessary
                      information.

C.     Option 3:  Update  Other Federal  Agency Costs

       Select  this Option from  the Daily  Cost Summary  Main Menu to display the
       Federal Agency Costs  Menu.

       1.       Option 1:  Add Other Federal Agency Costs

               Select  this Option to enter costs for Federal Agencies other than the EPA
               (e.g., US Coast Guard, FEMA).  The  program will prompt you for the
               following:
                                      4-10
                                                               r .-*,
                                                               .r&sllsi-
                                                             •sftjT

-------
                       Federal Agency Name
                       Service
                       Cost
         DAILY COST SUMMARY
                                   ADDING OTHER FEDERAL COSTS
      06/01/89
               Enter Federal Agency Name:            BSCC
               service.-
               Cost:
••"S '  - *
* f, •j'-tf •*
               Is the above information correct? [Y/N]
               After verifying this information, RCMS will return to the "Enter Federal
               Agency Name" prompt  You can now either continue to make entries, or
               you can exit this Option by pressing  < ENTER >.

        2.      Option 2: Edit/View/Delete Other Federal Agency Costs

               Select this Option to modify, review or delete individual entries within the
               Other Federal Agency Costs file.

    ~~l  \       Note: See pages 3-11 and 12 for an explanation of the standard Edit Menu,
    Zl)         found at  the bottom of the screen.  For a more detailed discussion of the
               RCMS Edit/ViewlDeletc Option, see Appendix A.

        3.      Option 3: Delete All Other Federal Agency Cost

               Use this Option to erase all entries within the Other Federal Agency Costs
               File  at a single  time, rather-than deleting each individually, using the
               Edit/View/Delete Option.   You will  be prompted for  all necessary
               information.

D.     Option 4:  Update TAT Costs

        To enter TAT-related costs into RCMS files, select this option from the Dally Cost
        Summary Main Menu,  The computer will respond to this choice by displaying the
        TAT Main Menu.
                                       4-11

-------
      DAILY COST SUMMARY
     TAT MAIN MENU
                                                                 06/01/89
            1. Update TAT Personnel

            2. Update TAT Special Projects

            3. Update TAT Analytical Services

            4. Update TAT Contractor Name and Administrative Multiplier

            0. Exit

              Your Choice:  i
~~l   >    Note: Before entering any TAT costs, use Option 4 from this Menu to enter the
~i      TAT Contractor Name and Administrative Multiplier.
    1.      Option 4: Update TAT Contractor Name and Administrative Multiplier

            Select this Option from the TAT Main Menu to enter the TAT Contractor
            Name and Administrative Multiplier into the RCMS files.  The Update
            TAT Information screen will be displayed.
     DAILY COST SUMMARY
UPDATE  TAT INFORMATION
                                                                06/01/89
           TAT Contractor:

           TAT Administrative Multiplier:          Illill

           Do you wish to edit this information? [Y/N]  |
           The Administrative Multiplier accounts for the administrative costs of the
           TAT programs. This multiplier is specific for each EPA Region  and is
           based upon a periodic determination of the administrative costs incurred
           by that  Regional TAT office. To arrive at that total cost to be charged to
           the site, TAT costs are multiplied by this figure. To obtain this Multiplier,
           contact the regional TAT Leader.
                                    4-12

-------
        After entering these two items, and verifying the information, you will be
        returned to the TAT Main Menu.

2.       Option 1: Update TAT Personnel

        Select this Option from the TAT Main Menu to enter TAT personnel, and
        the costs related with them.  The computer will respond to this choice by
        displaying the TAT Personnel Menu.
 DAILY COST SUMMARY
TAT PERSONNEL MENU
06/01/89
           1. Add TAT Personnel

           2. Edit TAT Personnel

           3. Update TAT Personnel Rates

           4. Delete All TAT Personnel  Entries

           0. Exit


              Your Choice:
       Before entering any TAT personnel names, use this Option to enter the
       TAT Personnel Rates.

       a.      Option 3: Update TAT Personnel Rates

               When you select this Option, the Update TAT Rates screen will
               be displayed.

               There are two types of TAT rates:

               •       PL, or professional level

               •       Fully Loaded

               PL rates represent regional or national cost averages for a given
               TAT level, while  Fully Loaded  rates are averaged hourly costs.
               Fully Loaded figures include such costs as  travel, per diem and
               lodging, which must be added to  any PL rate figures you use. Yet
               another difference between the rates concerns the Administrative
               Multiplier.   A figure applied to all PL rates, but not to Fully
               Loaded ones.
                               4-13

-------
DAILY COST SUMMARY
                              UPDATE TAT RATES
06/01/89
                      Current TAT Hourly Rates:
                    Tech 1:           'ejftf
                    Tech 2:          , 9M.
                    PL 1:           " 6.W
                    PL 2:           **«J»
                    PL 3:           x-fiJM
                    PL 4:           S; 8J
                    Mm. Staff:      ,s, 6,
                    Fully Loaded:
            Do you wish to edit these Rates? [Y/N]  N
             Once you  have entered  and verified  all rate  information, the
             program will return to the TAT Personnel Menu.

      b.      Option 1: Add TAT Personnel

             Select this  Option from the TAT Personnel Menu  to add  TAT
             Personnel to the RCMS files.  The computer will respond to your
             choice of  this  Option  by  prompting you  for the following
             information:

             •      TAT Personnel Name

             Once you have entered this information, the TAT Contractor Name
             (previously  entered via Option 4:  Update TAT Contractor Name
             and Administrative Multiplier, pages 4-12  from the TAT Main
             Menu) will be displayed on  the computer screen.   If the name
             displayed is correct, simply press < ENTER > to verify it, and the
             RCMS program will continue by prompting you for the following:

             •      Employee ID Number
             •      TDD Number
             •      TDD Type
             •      TAT Level (a list of choices will be displayed)

             Once you have entered and verified this data, you will  be requested
             to identify whether Professional Level rates ("P"), or Fully Loaded
             rates ("P) are to be used in the calculation  of TAT personnel
             costs.

             Once you have entered  this data, the Hourly Rate (previously
             entered via  Option 1: Update TAT Personnel Rates pages 4-13)
             will be displayed on the computer screen.  If this rate is correct,
             simply press < ENTER >  to verify it, and the RCMS program will
             continue by prompting you for the following:
                             4-14

-------
                     Hourly Rates
              •      Daily Hours

              If PL rates are being used, the program will prompt you for the
              following additional cost information:

              •      Per Diem
                     Lodging
              •      Transportation
                     Other Costs
              •      Cost Description
DAILY COST SUMMARY
                             ADDING TAT PERSONNEL
06/01/89
     Enter TAT Personnel  Name:              ttOftOtt, JOE
     TAT Contractor Name:
     Employee 10 Number:                    1994

     TDD Number:
     TDD Type:

     TAT Level:

     Hourly Rate:
     Daily Hours:

     Per Diem:
     Lodging:
     Transportation:

     Other Costs:
     Cost Description:
     Is the above information correct? [Y/N]
              After entering and verifying this  information, the program  will
              return to the "Enter TAT Personnel Name" prompt. You can now
              either continue to make entries in this File, or you can exit  this
              Option by pressing < ENTER >.

      c.      Option 2: Edit TAT  Personnel

              This Option allows you to modify, review and delete entries within
              the TAT Personnel File.  You should use this Option on a daily
              basis to change the amount of hours charged to a site by individual
              TAT members, as well as to charge other personnel costs.

              Remember, the  Extended  Edit  function, accessed by pressing
              , allows you to add and remove transportation, per diem and
              lodging charges when a TAT member leaves the site (e.g., for the
              weekend).

      Note:  See pages 3-11  and 12 for an explanation of the Edit Menu, and its
      functions.  For a more  detailed  discussion  of the standard  RCMS
      EditlView/Delete Option, see Appendix A.
                              4-15

-------
      d.      Option 4:  Delete all TAT Personnel

              This  Option allows you to eliminate all entries within the TAT
              Personnel file at a single time, rather than erasing each individually
              using the Edit Option.  You will be prompted  for all necessary
              information.

      Option 2: Update TAT Special Projects

      This Option from the TAT Main Menu allows you to add costs for TAT
      Special Projects to the RCMS files.  The computer will respond to your
      choice of this Option by displaying the TAT Special Projects Menu.
DAILY COST SUMMARY
TAT SPECIAL PROJECTS MENU
06/01/89
          1. Add TAT Special  Projects

          2. Edit TAT Special Projects

          3. Delete All TAT Special Project Entries

          0. Exit


            Your Choice:
      a.      Option 1: Add TAT Special Projects

             This Option from the Update TAT Special Projects Menu allows
             you to make new entries to the RCMS files.  The computer will
             respond to your choice of this Option by prompting you for the
             following:

             •      Special Project TDD No.

             Once entered  and verified,  the screen will  display the TAT
             Contractor name previously entered (via Option 4: Update TAT
             Contractor Name and Administrative Multiplier, page 4-12, from
             the TAT Main Menu).

             If the displayed name  is correct, simply press < ENTER >  to verify
             it,  and the program will  continue by  prompting you  for  the
             following:

             •      TDD Type
                             4-16

-------
         Note: As of publication of this Guide, the nationwide TDD Type for Special
        Projects is 'Off. Please confirm this information with the TAT Project Leader.

                •      Date of Special Project Authorization

                Verification of this data will continue the program prompts, which
                will now  request the following:

                •      Special Project Amount
                •      Description
  DAILY COST SUMMARY
ADDING TAT SPECIAL PROJECTS
06/01/89
       Enter Special Project TDD No.

       TAT Contractor:

       TDD Type:                             gg

       Date of  Special Project Authorization:

       Special  Project Amount:

       Description:
       Is the above information correct?  [Y/N]   |
        Once you have entered and verified this information, the screen will return
        to the "Enter Special  Project TDD No." prompt.  You can now either
        continue to make entries into this File, or you can exit  this Option by
        pressing  < ENTER >.

4.      Option 3: Update TAT Analytical Services

        Select this  Option from  the TAT Main Menu  to update  TAT analytical
        services costs. The computer will respond to your choice of this Option
        by displaying the  TAT Analytical Services Menu.
                                4-17

-------
       DAILY COST SUMMARY
TAT ANALYTICAL  SERVICES MENU
06/01/89
                 1.  Add TAT Analytical Services

                 2.  Edit TAT Analytical Services

                 3.  Delete All  TAT Analytical Services Entries

                 0.  Exit


                    Your Choice:
             a.      Option 1:  Add TAT Analytical Services

                    Select Option 1 from this Menu to add TAT Analytical Services.
                    You will be prompted for the following:

                    •       Analytical Services TDD Number

                    Once this  information is entered, the computer will display the
                    TAT Contractor name (previously entered via Option 4:  Update
                    TAT Contractor Name and Administrative Multiplier, page 4-12).
                    If the displayed name is correct, press < ENTER > to verify it,
                    and the program will continue by prompting you for the following:

                            TDD Type

~~>   i       Note:  As of publication of this  Guide, the nationwide TDD Type for all
 fc—1        Analytical services is '16*.  Please confirm his with the TAT Project Leader.

                    •       Date of Authorization

                    Once you have verified this data (or changed the date if necessary),
                    the prompts will continue, requesting:

                    •       Analytical  Services Amount
                    •       Description
                                     4-18

-------
         DAILY COST SUMMARY
                          ADDING TAT ANALYTICAL SERVICES
06/01/89
b.
              Enter Analytical Services TDD No.

              TAT Contractor:

              TDD Type:

              Date of Authorization:

              Analytical Services Amount:

              Description:
              Is the above information correct? [Y/N]
               Once you have entered and verified this information,  the program will
               return to the 'Enter Analytical Services TDD no.' prompt.  You can now
               either continue to make entries to this File, or you can exit  this Option
               by pressing < ENTER >.

               Option 2:  Edit TAT Analytical Services

               This Option  allows you to modify, review and erase individual entries
               within the TAT Analytical Services File.

               Note: See pages 3-11 and 12 for an explanation of the Edit Menu, found at
               the bottom of the screen. For an in-depth discussion of the standard RCMS
               Edit/ViewlDelete Option, see Appendix A
E.      Option 5:  Update Other Costs

        Select this Option from the Dally Cost Summary Main Menu to enter any other
        costs that may be associated with a removal project  The Other Costs Menu will
        be displayed.
                                       4-19

-------
   DAILY COST SUMMARY
    OTHER COSTS MENU
   06/01/89
             1. Add Other Costs

             2. Edit Other Costs

             3. Delete All Other Costs Entries

             0. Exit


                Your Choice:
  1.      Option 1:  Add Other Costs

         This Option from the Other Costs Menu allows you to make new entries
         to the RCMS files.  The computer will respond to your choice of this
         Option by prompting you for the following:

         •       Cost Description
         •       Amount
         •       Cost Category Type  (a list of options will be displayed).

         After verifying this information, the program will return to the "Enter Cost
         Description" prompt  You can now either continue to make entries  into
         the File, or exit the Option by pressing  < ENTER >.
DAILY COST SUMMARY
ADDING OTHER COSTS
06/01/89
      Enter Cost Description:

      Amount:

      Cost Category Type:
     Cost Categories: Sampling and Analysis (S)
                     Utilities (U)
                     State or Local Gov't Support (G)
                     Express Mail (E)
                     Other (0)
      Is the above information correct? [Y/N]  |
                                  4-20

-------
       2.      Option 2: Edit Other Costs

               This Option allows you to modify, review or eliminate individual entries
               within the Other costs File.

               Note:  See pages 3-11 and 12 for an explanation of the Edit Menu, found at
               the bottom of the screen, and its  available functions.  For  an in-depth
               discussion of the standard RCMS Edit [View[Delete Option, see Appendix A.

       3.      Option 3: Delete All Other Cost Entries

               This Option allows you to erase all entries within the Other Costs File at
               once, rather than deleting each individually using the Edit Option.  You
               will be prompted for all necessary information.

F.     Option 6:  Update Daily Cost Summary Adjustments and
       Comments

       Adjustments and comments to the Daily Cost Summary  can be entered using this
       Option 6 from the Daily Cost Summary Main Menu.  Adjustments and comments
       to the DCS are updated in a  manner similar to the procedure used for the 1900-
       55 Form.  The program will respond to your choice of  this Option by displaying
       the Update Adjustments and Comments Menu.

       1.      Option 1: Add  Entries to Adjustments/Comments

               By choosing this Option, you  can  enter comments  and adjustments for
               EPA, TAT or other federal  costs. The program will prompt you for the
               following information:

               •      Description of the Adjustment/Comment
                     (up to five lines of text can be entered)
               •      Adjustment amount
               •      Is amount added or subtracted
               •      Adjustment category (The screen will display a list of categories
                     from which to choose from).

              Once you have entered and verified this data, the program will return to
              the 'Adjustment* prompt  You can now either continue to make entries,
              or you can exit  this Option by  pressing < ENTER >.
                                     4-21

-------
                                                                                                    1
                                                                                                    I
QAILY COST SUMMARY
ADDING ADJUSTMENTS/COMMENTS
06/01/89
                                  15S.OO To be Subtracted
              Please Enter the Following Information

 Adjustment/Conment:     t&MtSFJ fcJfc fAT fSBOJWEU €»TRTf «l«TAK€ OH


.Adjustment Amount:

 Adjustment Category:    :|j»

 Adjustment Categories: (EN) EPA Region Onsite   (TP) TAT Personnel
                     (EF) EPA Region Offsite  (TS) TAT Special Project
                     (EO) EPA Other Direct    (TA) TAT Analytical
                     (El) EPA Indirect
                     (FD) Other Federal
                                                    (OT) Other Costs
                                                    (GO Gen. Comment
          Is the information  listed above correct? [Y/N]  :f
               Adjustment amounts will appear on the Daily Cost Summary under the
               appropriate cost category.  Adjustments and comment descriptions appear
               on the Daily Cost Summary Detailed Report.

       2.      Option 2:  Edit/View/Delete Adjustments/Comments Entries

               This Option allows you to  modify, review or eliminate individual entries
               within the Adjustments/Comments  File.

               Note:  See pages 3-11 and 12 for an explanation of the Edit Menu, found at
               the bottom of he screen. For an in-depth discussion of the standard RCMS
               Edit/View/Delete Option, see Appendix A

       3.      Option 3:  Delete All Current Adjustments/Comments Entries

               This   Option   allows  you   to   erase   all   entries  within   the
               Adjustments/Comments File at once, rather than deleting each individually
               using the Edit Option.  You will be prompted for all necessary information.

G.    Option 7:  Print Daily Cost Summary

       Once the Daily Cost Summary Files contain information that accurately reflects the
       resources used on site for that particular date, a DCS can be printed.

       This Option from the Daily Cost Summary Main Menu enables you to print either
       a draft or a final copy of the Daily  Cost Summary. The computer will respond to
       your choice of this Option by inquiring if you want to print detailed reports of the
       EPA, TAT, and  adjustment costs for the day.  Answer yes ("Y") to print these
       Reports, along with  the Daily Cost Summary. Finally, the program will  inquire
       whether a draft or final copy is desired, and the number of copies to be printed.

       NOTE: ALWAYS PRINT A DRAFT DAILY COST SUMMARY FIRST TO VERIFY THE
       ACCURACY OF YOUR DATA.
                                                                                                    I
                                                                                             -
                                                                                           I
                                      4-22

-------
               REMEMBERS YOU CANNOT RETURN TO THE DAILY COST SUMMARY
               DATA AFTER PRINTING A FINAL DCS FOR A PARTICULAR DATE.

        If a final copy has been printed you will be required  to confirm that  this is a
        report for the particular date.  Once a draft or a final DCS is printed, the program
        will return to the 1900-55 and Daily Cost Summary menu; at this point, the data
        can be modified (after printing a draft) or archive (if you have printed a final
        DCS).


4.3    SAMPLE  DAILY  COST SUMMARY AND DAILY  COST
        LISTING

See Exhibit IV-A, page 4-25, for  an example of a Daily Cost Summary.

At the top of the DCS you will find the date, page number, and site name. Immediately
below this is a space for the cost ceilings and  balances.  A ceiling and balance will be
shown  for all Prime  Contractors  and  TAT.  The total  site ceiling and balance  will also
appear.  Please note  that the balances reflect the amount of money left before any costs
for  that day were incurred.

The body  of the DCS lists the major cost categories in the left column, each divided into
their component costs. The first column of figures lists the costs incurred for  that day,
followed, to the right, by the total-to-date costs. The balances remaining after costs were
incurred for that day are noted in the extreme right column (for those major cost categories
with associated ceilings). The percentage of funds remaining are listed below the balances
remaining.

In the 1900-55 Costs  section, there are two 1900-55 totals.  One reflects the total without
the estimated portion (Await Bills) of the subcontractor costs; the other accounts for the
change  in  the estimated portion of  the subcontractor costs.   This breakdown of the
subcontractor costs allows for an easier determination of daily  site  costs that cannot be
made definite at the time they are incurred.

TAT costs are broken down into Personnel, Special Projects,  and Analytical  Services.
These subcategories will only be listed  if a costs were entered for them.  These costs reflect
the Administrative Multiplier entered  for that Region.

EPA costs are broken down into Regional On-Site Personnel, Regional Off-Site Personnel,
and Non-Regional Personnel. There will be an Indirect Costs figure that relates directly
to all Regional direct hours charged.  These subcategories will only be listed if there are
associated costs for them.   However,  Indirect Costs should always be listed if there are
Regional direct costs.

Costs incurred for US Coast Guard, or FEMA services appear under the heading of "Other
Federal Agency Costs." Costs for local government  agencies and miscellaneous costs are
listed in a section labeled "Other Costs".

Adjustments made to  any of the  cost  categories will appear as the final line item in the
printout for that category.
                                      4-23

-------
A sample Daily Cost Summary Detailed Report is given in Exhibit FV-B. The Detailed
Report is an optional  form that can be printed  when you print the DCS.   The form
provides a detailed listing of the non-cleanup contractor costs (EPA, TAT, other federal),
as well as a listing of any DCS adjustments or comments.
                                      4-24

-------
Exhibit IV-A
DAILY COST SUMMARY FOR 01/01/89 Page 1
ABC DRUM
Ceilings Balances
(As of 12/31/88) (As of 12/31/88)
Site Total 1,000,000 830,185
ERCS: CORNUCOPIA INC. 500,000 397,605
ERCS: ACME ENTERPRISES 100,000 84,869
TAT: ROY F. ECOLOGY 100,000 76,465
Cost Categories
1900-55 Costs:
CORNUCOPIA INC.
Personnel
Equipment
Unit Rate Materials
At Cost Materials
Subcontractors (Final Bills)
Adjustments
Total CORNUCOPIA INC. Cost
. (Includes Adjustments)
(Less Await Bills)
' Change in Subcontractor
Await Bill Total
Subcontractor Await Bill Total
Total CORNUCOPIA INC. Cost
CORNUCOPIA INC. Ceiling Balance
X CORNUCOPIA INC. Funds Remaining
ACME ENTERPRISES
Personnel
Equipment
Unit Rate Materials
At Cost Materials
Subcontractors (Final Bills)
Adjustments
Total ACME ENTERPRISES Cost
(Includes Adjustments)
(Less Await Bills)
Today
7,266.59
878.90
0.00
0.00
0.00
0.00
8,145.49
0.00
8.145.49
1,348.40
809.35
0.00
0.00
0.00
0.00
2,157.75
Total to Date
51,964.17
13,444.69
0.00
34,242.76
8,088.94
107,740.56
2,799.50
110,540.06
7,909.02
4,135.82
4,090.50
141.31
495.00
16,771.65
Balance
(X Remaining)
389,459.94
78 X

   4-25

-------
                                              Exhibit IV-A (continued)
\
DAILY COST SUMMARY FOR 01/01/89 Page 2
ABC DRUM
Cost Categories
Change in Subcontractor
Await BUI Total
Subcontractor Await Bill Total
Total ACME ENTERPRISES Cost
ACME ENTERPRISES Ceiling Balance
X ACME ENTERPRISES Funds Remainini
TAT Costs:
Personnel
Special Projects
Analytical Services
Total TAT Costs
TAT Cost Adjustment
TAT Remaining Balance
X TAT Funds Remaining
EPA Costs:
Regional On-site Personnel
Indirect
Total EPA Cost
Other Federal Agency Costs:
US COAST GUARD
Total Other Federal Costs
Other Costs:
Total Other Costs
Project Total Coats:
Today
0.00
2,157.75
1,599.99
536.30
692.00
2,828.29
300.00
663.00
1,110.00
XBXXXSrBXXCX
1,773.00
2,272.00
2,272.00
0.00
17.176.53
Total to Date
517.00
17,288.65
25,134.73
536.30
692.00
26,353.03
26,653.03
6,449.30
1,110.00
S3ESSKXSSSZSS
7,559.30

16,920.49
mmm*mm*mmm*mm
8,320.00
187,281.53
Balance
(X Remaining)
82,711.35
83 X
73,646.97
74 X




                                                       4-26

-------
Exhibit IV-A (continaed)
DAILY COST SUMMARY FOR 01/01/89 Page 3
ABC DRUM
Coat Categories
Project Balance Rennining
X Project Funda Remaining
Today

Total to Date
. 	
Balance
(X Remaining)
812,718.47
81 X
         4-27

-------
                                Exhibit FV-B
           DAILY COST SUMMARY - DETAILED REPORT FOR 01/01/89       Page 4
                            ABC DRUM
                                EPA Costs
                                XXBXXBBBB

EPA Regional On-Site Personnel:

Item   Name            ID*   Title/GS Level        Hours   Category Costs
SXSS  BXXBrXSBBBSXSSE  BXSB  BSBXXBXXBBXBXXBSS=SS  8SSBS  X=S5X==SS=Sr=5S5Z
(1)   DOE, J           2343  SR. OSC/GS13           8.00     Labor:  240.00
                                                          Per diem:   2S.OO
                                                           Lodging:   29.00

                                                             Total:  294.00

(2)   SMITH, J         3223  OSC/GS12              10.50     Labor:  315.00
                                                          Per diem:   25.00
                                                           Lodging:   29.00
                                                          S=3SSS=SS=SS5SSS5
                                                             Total:  369.00

                                        Total EPA Regional On-Site:  663.00


EPA Indirect Costs:

Total Direct Regional Hours                             Total Indirect Cost

          18.50                                                     1110.00


                        Other Federal Agency Costs
Item      Agency              Service                            Total Cost
SBSS  ====I===I======        BXSBXS«SSXSBSS=XSSS                XSSSSSSZSZ
(1)   US COAST GUARD         SAFETY/SUPPORT                         2272.00
                              Total Other Federal Agency Costs:      2272.00
                       TAT Costs For ROY F. UESTON
                       BSBsssxsrsBEBxrBBBBxsBxsExs

TAT Personnel:

Item   Name            ID*  Level  TDD Number Type Hours    Category Costs
                                    4-28

-------
\
                                                   Exhibit IV-B  (continued)
                                     DAILY  COST  SUMMARY  • DETAILED REPORT FOR 01/01/89
                                                     ABC DRUM
                                           Page 5
1007  PL1    128812-01    11   9.50     Labor:  185.06
                                  Per diem:   25.00
                                   Lodging:   48.00
                          (1)    DOE, D
                                                                                      Total:  258.06

                          (2)    JONES, B          1001  PL2   128812-01   11   9.50     Labor:  262.77
                                                                                   Per diem:   12.50
                                                                                   S33333S333S333S33
                                                                                      Total:  275.27

                                  Total TAT Personnel (Includes Administrative Multiplier):  1599.99



                          TAT Special Projects:

                          Item     Date       TDD*      Type    Description                Total Cost

                          (1)    08/18/88   128812-S1    06     GRAPHICS                       536.30

                                                              TAT Special Project Total:      536.30

                          TAT Analytical Services:

                          Item     Date       TDD*      Type    Description                Total Cost
                          BSBS   S3S33XXS   BXBS338SSS  S33X    838B3S3B8S33333S333S       S3333333S3
                          (1)    08/18/88   128812-L1    16     GRID 56 SAMPLES                692.00
                                                                                          83K3KKX33
                                                          TAT Analytical Services Total:      692.00



                                               Daily Cost Summary Adjustments
                                               BB3SSS38BK33S*38S338SacS3SS3S3S


                          Item   Adjustment/Comment                               Type  +/-    Amount

                         (1)  ADJUSTMENT FOR TAT PERSONNEL COSTS                 TAT   (*)      300.00
                                                            4-29

-------
                              CHAPTERS
                   INCIDENT OBLIGATION LOG
             AND CONTRACTOR DAILY COST LOG
5.0  INCIDENT OBLIGATION LOG OVERVIEW
The Incident Obligation Log (IOL) is used to track cumulative costs over any specified
period of time during the course of a project. It offers daily tracking of all the major cost
categories counted towards the Project Ceiling.  The computer will automatically prepare
the IOL from data in the Final Daily Cost Summary files.

The date range selected along with the page number are shown at the top of the IOL.
Below, a section containing the site name and the total project ceiling will appear.  If the
ceiling was  changed during the time range reflected in the IOL, the date of change,
together with the new ceiling, will be noted here.  The rest of the IOL lists the major costs
by category, total costs, and the resulting project funds balance for each day in the specified
date range.
              Note:  The totals reflected on the IOL are the sum of the charges for att of
              the prime contractors on the site if multiple prime contractors are used.
The 1900-55 costs are separated into two columns, the first column labeled 1900-55 Costs,
accounts for all cleanup contractor costs except those awaiting final billing. The second
column, labeled Await Bill Change, accounts for the change in the Cleanup Contractor
Await Bill total.  This breakdown permits a quick determination of the status of each day's
estimated costs.

This daily cost accounting, in addition to the ERCS estimated costs, should help to improve
tracking of expenses against the ceiling.


5.1   PREPARING THE INCIDENT OBLIGATION LOG (IOL)
To prepare an Incident Obligation Log, select Option 5 from the 1900-55 and Daily Cost
Summaiy Menu. The program will display the range of dates that are available from the
data currently on the hard drive. You will be able to select any time span that falls within
these dates.
                                    5-1

-------
RCHS
VERSION
3
.2
INCIDENT
OBLIGATION
LOG
06/01/89
                     Final Daily Cost SurmaHes have be«n produced for the following date range:

                                First Date: 09/01/88         Last Date: 09/09/88

                     You can print an Incident Obligation Log for any date window in this range

                                 Do you wish to continue with printing? [Y/H]  f
              Select and enter a date range.  The computer will request verification.

              The program will now prompt you to ready the printer, and then will print the IOL. Once
              the IOL is printed, the program will return to the 1900-55 and Daily Cost Summary Menu.
              A sample IOL is shown in Exhibit V-A.
                            Note:  An IOL cannot be printed until you have completed a final Daify Cost
                            Summary.
              5.2    CONTRACTOR  DAILY COST LOG


              The Contractor Daily Cost Log, like the Incident Obligation Log, allows you to track costs
              over a specified period of time. In this instance, these costs are for the contractor. The
              Contractor Daily Cost Log provides a listing of daily contractor costs  and tracks  these
              against the site ceiling.


              5.3    PREPARING THE CONTRACTOR DAILY COST LOG
              To prepare this Log, choose Option 6 from the 1900-55 and Daily Cost Summary* Menu.
              The program will display the range of dates that are available from the cost data currently
              stored in the system.  You will then be prompted to select a specific date range within this
              time span.  The screen for this Option is similar to the screen encountered when preparing
              an Incident Obligation Log (see above).  As on  that screen, the  next prompt on the
              contractor daily cost screen alerts you to ready the printer. Once a Contractor Daily Cost
              Log is printed, the program will return to the 1900-55 Form.
\
                                                   5-2

-------
Exhibit V-A
	 _. _. 	 _ .... !
INCIDENT OBLIGATION LOG Page 1
From: 09/01/88 To: 09/11/88
Site Name: ABC DRUM Project Ceiling:
09/01/88 100000
09/09/88 125000
Date/
TTO
09/01/88
09/02/88
09/03/88
09/04/88
09/05/88
09/06/88
09/07/88
09/08/88
09/09/88
09/10/88
09/11/88
1900-55
Costs
4037
4037
2168
6206
3687
9892
4501
14394
3001
17395
1259
18654
1259
19914
4252
24165
2973
27138
4553
31691
4240
35930
Await
Bill
Change
176
176
165
341
0
341
-22
319
258
577
-22
555
72
627
0
627
110
737
-498
239
-239
0
EPA
Costs
806
806
818
1624
806
2430
806
3236
806
4042
806
4848
806
5654
806
6460
806
7266
806
8072
806
8878
I
0. Fed
Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
TAT
Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
I
Add'nl
Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
I
Total
Costs
5019
5019
3151
8171
4493
12663
5285
17949
4065
22014
2043
24057
2137
26195
5058
31252
3889
35141
4861
40002
4807
44808
Balance
94981
91829
87337
82051
77986
75943
73805
68748
89859
84998
80192
    5-3

-------

-------
                                        CHAPTER 6
                      ARCHIVE AND BACKUP PROCEDURE
6.0  ARCHIVE AND BACKUP DATA OVERVIEW

The Archive and Backup Data procedure is an integral part of the cost tracking system.  This procedure
concludes all daily computer cost tracking activities by transferring daily cost data from the hard drive to
a floppy disk.  The Archive and Backup Data procedure is not only important but mandatory. RCMS
requires that you complete this procedure before proceeding to prepare a new 1900-55 Form and Daily Cost
Summary.

By archiving data on a daily basis, an electronic cost history of the site is produced.  The Archive Disk can
then be used to reproduce 1900-55 Forms and produce Site Summary Reports for any date within the time
span of a project.  See Chapter 8: Site Summary Reports, for details on  the type of reports that can be
produced from  the Archive  Disk.

The Archive Disk  and Backup Archive Disk contain the same data; the program requires both for data
security purposes.  These disks can be erased  accidentally as a result of careless storage and/or handling
(they are easily  damaged from storage in close proximity to  portable radio charging units, portable phones,
and other electronic devices with speakers or electromagnetic coils).

Storing data on Archive Disks minimizes the risk of data lose in the event of major computer problems.
Even a worst  case scenario can be remedied by reinstalling RCMS on a new computer, and  retrieving your
stored  data using Option 3: Load Last Final Data from Archive Disk from the Cost Report Data Menu.
(This option is  explained in Chapter 2, Introduction to Cost Tracking, page 2-3).

In addition, archived data plays  an important role in automating and improving the Cleanup Contractor
invoice verification and contract  definitization procedures. This results in major time and labor savings  for
all personnel  involved in  these procedures.

There are two widely used storage capacity standards for 5.25  inch disks and drives.  The  360K standard
(also known as double density) is found on all Compaq Plus  portable computers and can store 360 kilobytes
of information.  The 1.2M standard (also known as high density) is found on the newer Compaq Portable
III computers and can store  1.2 megabytes (approx. 1,200 kilobytes). The 1.2M floppies are  more desirable
because of their larger storage capacity, but limited access to the 1.2M drives may make the 360K floppies
a better choice.

The type of disk  used becomes important when you  want to  transfer to, or use a disk  in, a different
computer system.  The 1.2M drives are "upwardly  compatible" because they will read either type of disk. A
360K drive can only read 360K formatted floppies. If you were to create and use a 1.2M Archive Disk on
a Compaq Portable III in the field and then  go back to the office and prepare site summary reports from
your Archive Disk  on an  IBM XT, (which usually have 360K drives) you would run  into difficulty.   Keep
this information in mind when using your Archive Disks.
                                              6-1

-------
 THE IMPORTANCE OF HAVING UP-TO-DATE, ACCURATE, AND SECURE ARCHIVE AND BACKUP DISKS
 CANNOT BE OVERSTATED.

 ALSO, IT IS REQUIRED THAT YOU HAVE TWO COPIES OF YOUR ARCHIVED DATA AT ALL TIMES!
              Note: If one of your Archive Disks should become damaged or un-usable, make a second copy
              of the intact disk IMMEDIATELY!
6.1  ARCHIVING PROCEDURE

After you have completed both a final 1900-55 Form and a Daily Cost Summary, you may perform the
archive and backup data procedures.  Before you begin, you must have two formatted, blank, disks.  To
prepare these disks, see Option 1: Prepare Archive and Backup Archive Disks, page 7-1.

With the prepared Archive and Backup Archive Disks in hand, select Option 6: Archive and Backup Data
from the 1900-55 and Daily Cost Summary Menu. The program will display the following archive procedure
information screen:
                                                               j
                RCHS VERSION 3.2
ARCHIVE AND BACKUP PROCEDURE
06/01/89
                           This procedure will save the current data on
                               the ARCHIVE and BACKUP ARCHIVE disk*.

                     This is a very important step in the cost tracking process.

                          It is important that you complete the entire
                              ARCHIVE and BACKUP procedure correctly.

                             Please follow the instructions carefully.

                                   Press ENTER to continue.
Press < ENTER > to continue with the archive procedure:
                                            6-2

-------
RCMS
VERSION
3
.2
ARCHIVE
AND
BACKUP
PROCEDURE
06/01/89
                       The following cost data Mill  be saved on the
                            ARCHIVE and BACKUP ARCHIVE disks:

                Site Name:                        ABC DRUM

                Site Number:                      E142857

                Current Cost Data to be archived:   09/01/88


                You must have two disks that have been prepared as ARCHIVE and
               BACKUP ARCHIVE disks before proceeding with the Archive procedure.

                  These disks can be prepared using  the utilities option
                               on the 1900-55/DCS Menu.

        If you need to prepare these disks, please exit and use the utilities option.

                Do you want to continue with the ARCHIVE procedure? [Y/H]  |
After verifying that you wish to continue with the archive procedure, you will be instructed to insert
the Archive Disk in Drive A and press .  RCMS will confirm that the disk you have
inserted is in fact an Archive Disk, and that sufficient space exists on this disk to store the current
day's cost data.  If the disk you have inserted does not have sufficient space to hold another day
of cost data, the screen will display the following:
RCMS
VERSION
3
.2
ARCHIVE
AND
BACKUP
PROCEDURE
06/01/89
                                 Archive Disk Sequence

              The Archive Disk  in Drive A does not have enough space  to hold

                                     the current data
                                Please use a new Archive disk
                 If you need to prepare a new Archive disk, exit  from the
                        Archive procedure and use the Utilities option
                    1. Continue with Archive procedure
                    0. Exit

                         Your Choice:
If this message appears, exit the archiving procedure and prepare the necessary disk(s) (see page
7-1, Option 1: Prepare Archive and Backup Archive Disks).

If the above requirements are met, RCMS will copy the current data onto the Archive Disk and
the following screen will be displayed:
                                          6-3

-------
                RCMS VERSION 3.2
ARCHIVE AND BACKUP PROCEDURE
06/01/89
                                            Archive Disk Sequence

                                         Data being copied to Drive A
                              Other DCS Files
             1900-55 Personnel

             1900-55 Equipment

             1900-55 Materials

             Other 1900-55 Files
        The screen will display several categories of information to be archived.  As information
        is being copied onto the Archive Disk, the individual categories will blink.  When copying
        is completed, the categories will appear in reverse video on the screen, indicating that these
        files have been correctly archived.

        If, by mistake, you have inserted an improperly prepared Archive Disk, RCMS will display
        the following:
           RCMS VERSION 3.2
                                    ARCHIVE AND BACKUP PROCEDURE
                          06/01/89
                                 Archive Disk Sequence

                         Drive A does not contain an ARCHIVE DISK

                    Please insert an ARCHIVE DISK into Drive A

                 If you need to prepare a new Archive disk, exit from the
                        Archive procedure and use the Utility option
                    1. Continue with Archive procedure
                    0. Exit

                         Your Choice:  |
1.       Option 1:  Continue with Archive Procedure

        Select this Option when you wish to insert  another Archive  Disk into drive A.  Once
        inserted, the program will check the disk and, if acceptable, will continue archiving in the
        same manner as previously discussed.  RCMS will only accept the newly inserted disk if
        that disk'has been previously prepared as an  Archive Disk,  (see RCMS Utilities,  Option
        1:  Prepare Archive and Backup Archive Disks p. 7-1).
                                          6-4

-------
2.      Option  to return to the 1900-55/DCS menu.
        After the first disk has been successfully archived, the following screen will be displayed:
                RCMS VERSION 3.2
ARCHIVE AND BACKUP PROCEDURE
06/01/89
                                       Backup Archive Sequence
                            Current data has been copied to the Archive disk
                       Current data will now be copied to the Backup Archive disk
                            Please insert the BACKUP ARCHIVE DISK in drive A
                                       Press ENTER to continue
       Insert the Backup Archive Disk in drive A and press  to continue.
       The program will check the disk in drive A and if accepted as a Backup Archive Disk, will
                                         6-5

-------
 proceed to archive data in the same manner as previously done  for the Archive Disk.
 If you have inserted the wrong disk or an improperly prepared disk, RCMS will display
 the following:
         RCMS VERSION 3.2
ARCHIVE AND BACKUP PROCEDURE
06/01/89
                                Backup Archive Sequence

                      This is not the BACKUP ARCHIVE DISK  in Drive A:\

                                    Do you wish to :
                    1. Continue with Archive procedure
                    0. Exit

                         Your Choice:  1
You have the option to of continuing the archive procedure and entering a new disk or
exiting to the 1900-55/DaiJy Cost Summary Menu.

If the Backup Archive Disk does not correspond with the current data on the hard disk,
the site name and number of the Backup Disk inserted in drive A will be displayed on the
screen.
RCMS
VERSION
3
.2
ARCHIVE
AND
BACKUP
PROCEDURE
06/01/89
                                Backup Archive Sequence


               The Site Name and Number for current data on the hard disk
                do not correspond with those on the BACKUP ARCHIVE DISK  in Drive A.


                        Current data to be saved    BACKUP ARCHIVE DISK

            Site Number        TFA1NEC1               D823

            Site Name          PUTNAM FIRE SITE       NEWPORT DUMP SITE II


                               Press ENTER to continue.
Press  to continue with the archiving procedure and the following screen will
be displayed:
                                  6-6

-------
                      RCMS VERSION  3.2
ARCHIVE AND BACKUP PROCEDURE
06/01/89
                                              Backup Archive Sequence

                             Please  insert the correct BACKUP ARCHIVE DISK for this  site


                               If  you need to prepare a new Archive disk, exit from  the

                                    Archive routine and use the Utility option.
                                  1. Continue with Archive  procedure
                                  0. Exit

                                      Your Choice:  1
             Choose Option 1 and insert the correct Backup Archive Disk in drive A to complete the
             archiving procedure, or choose Option 0 to exit to the 1900-55/Daily Cost Summary Menu.
~"~?   )       NOTE:  You must make a backup of your Archive Disk before you can start a new 1900-55
 —1         or DCS, If you exit the archive procedure before the backup has been archived, you will have
             to re-archive both disks.  If you  attempt to exit without archiving data on the Backup Disk,
             the following warning will be displayed:
RCMS
VERSION
3
.2.
ARCHIVE
AND
BACKUP
PROCEDURE
06/01/89
                      You are exiting from the archive procedure without copying  the data to the
                       backup archive disk.  Before you can start a new 1900-55 or DCS you will
                                   be directed to archive the data for this day.

                      Note: You will be asked to copy the data to both archive disks even though
                                  the data has already been copied to one archive disk.

                                  You will now be returned to the 1900-55/DCS menu

                                              Press ENTER to continue.
                                                6-7

-------
After both the Archive and Backup Archive Disk have been copied, RCMS will update the
hard drive and display the space status of both disks.
        RCMS VERSION 3.2
ARCHIVE AND BACKUP  PROCEDURE
06/01/89
                    Archive and Backup procedure has been completed

                       Archive Space Status:

                           Archive Disk:         19 X  full
                           Backup Archive Disk:   19 X  full
                           Please remove Backup Archive Disk
                               Press ENTER  to continue
Press  to return to the 1900-55/DCS Menu.
                                 6-8

-------
                                       CHAPTER?
                                   RCMS UTILITIES
 7.0  RCMS UTILITIES  OVERVIEW
The RCMS Utilities Option (Option 7 on the 1900-55 And Daily Cost Summary Menu) allows you to access
additional features within the Cost Tracking section of RCMS.  Select this option to display the Utilities
Menu.
                 RCMS VERSION 3.2
UTILITIES MENU
06/01/89
                          1. Prepare Archive and Backup Archive Disks

                          2. Print Supplemental 1900-55 Reports

                          3. Transfer Interface Data

                          4. Restore Last Day's Final Data From the Hard Disk

                          0. Return to Previous Menu

                            Your Choice:  :|
This Menu offers you the option of preparing floppy disks for archiving, printing supplemental reports from
the 1900-55 Form information, transferring dairy 1900-55 Form information from a contractor computer
system into RCMS, or restoring data from the previous day once you have begun entering the current day's
data.  Select the desired option from the Menu to continue.


A.     Option 1: Prepare  Archive  Disks and Backup Archive Disks

       This Option allows you to prepare the Archive and Backup Disks that are used to save daily cost
       tracking data. The preparation entails copying the data structures used in the Cost Tracking section
       of RCMS onto these disks.  These data structures must be on the disks so that they can receive
       daily cost information during the archive and backup procedure. New disks are prepared only when
       you are starting a new site, or when current Archive and Backup Disks do not contain sufficient
       space to  hold additional cost information.
                                             7-1

-------
                Note:  Before you begin the daify archive procedure (page 6-2), you should always have two
               prepared archive disks.
        When you select this Option, the following screen will appear:
                  ROMS VERSION 3.2
PREPARE ARCHIVE AND BACKUP DISKS
06/01/89
                   This utility allows you to prepare archive and backup archive disks.
                       These disks must be prepared prior to archiving the daily
                                 1900-55 and Daily Cost Surmary data.
                     Always prepare a backup disk when you prepare an archive disk.
                            You must have blank, formatted disks in order to
                                    continue with this procedure.
                     If you do not have formatted disks, please exit this routine.
                          Do you wish to continue with this procedure?  [Y/N]  |
        The computer will prompt you to insert a blank, formatted disk into drive A. Disk preparation will
        then begin.  When this procedure is complete, you will be asked if you wish to prepare another
        Archive Disk.  You should always prepare Archive Disks in pairs, as two are required for the
        Archiving procedure.
B.     Option 2:  Print  Supplemental 1900-55 Reports
        Select this Option to print supplemental 1900-55 reports.  If multiple contractors are being used
        at the site, you will be asked to select just one.  The Supplementary Report Menu will then  be
        displayed.
                                                7-2

-------
                          1900-55 FORM
SUPPLEMENTARY REPORT MENU
06/01/89
                             1.  Print LUt of ERCS Contractors

                             2.  Print List of ERCS Equipment

                             3.  Print LUt of ERCS Personnel

                             4.  Print List of Vendors

                             5.  Print List of Subcontractors

                             0.  Return to the Previous Menu

                                Your Choice:
       Select the Option number that corresponds to the report desired. The screen for that Option will
       prompt you to ready your printer, and RCMS will then print the report.

               Note: A printer must be connected and fUled with paper before you can proceed with any of
               these Options.
C.     Option 3: Transfer Interface  Data

       An important feature of RCMS is the ability to import cost data generated from other computer
       systems.   Several ERCS  contractors have developed their own computerized cost management
       systems.  The EPA has worked closely with these contractors to develop an interface program that
       allows for the transfer of daily cost information from their computer systems to RCMS. The data
       transfer takes  place via a floppy disk containing the daily cost information generated by the
       contractor's computer system, in a format consistent  with RCMS files.

       If multiple prime contractors are being used at the site, the screen will prompt you to select the
       one you wish to interface with. You will then be prompted to insert the Data Transfer Disk into
       drive  A.  The data will subsequently be  copied into  the proper RCMS files.  After the data has
       been copied into RCMS, it can be edited, if necessary, using the options on the 1900-55 Form Main
       Menu Options.  A single Transfer  Disk is generated each day by the ERCS contractor.  The
       procedures for  the  Daily Cost Summary and archiving of data remain exactly the same.  The
       Transfer Disk should be used only once  for any given day of cost tracking.
                                              7-3

-------
                  ROMS VERSION 3.2
LOADING DATA DISK
06/01/89
                                  Insert Interface Data Disk into Drive A:

                                   Press ENTER uhen read/ to continue.
        If a problem occurs while the data is being transferred, select Option 4, Restore Last Day's Final
        Data from the Hard Disk from the Utilities Menu.  This  Option will reset the data files back to
        the previous day.  After the files have been reset, you can  repeat the interface transfer procedure.

                Note: If there are  multiple prime contractors in the system, the interface transfer can be
               performed independently for each contractor.

                If you restore  the last day's data from the hard disk, you will need to prepare 1900-55 Forms
               for all prime contractors, including any that had been prepared before the restore option was
                selected.

                It is  important to remember  that the  same basic cost tracking procedure is followed when
                utilizing the contractor interface option. After finalizing a 1900-55 Form, you must finalize a
                Daify Cost Summary and then archive the data.  You cannot run several interface disks through
                the program to generate a series of 1900-55 Forms without first completing the Daify Cost
                Summary and archive procedures.


D.     Option 4:  Restore  Last Day's Final Data from  the Hard Disk

        As explained above,  this Option will set  the data files back to the previous day.  Running this
        Option  is equivalent  to loading  the previous  day's data  from an  Archive Disk (assuming the
        computer's hard  disk  has not been damaged).
                                                7-4

-------
ROMS
VERSION
3.
2
RESTORE
PREVIOUS
DAY
06/01/89
                This utility allows you to restore the previous  day's final
                data from the hard disk.  This utility will  only work if you
                have not archived the current data.  This procedure will
                also require you to reenter any Daily Cost Surmary data
                you may have entered.  This utility can be used  if you wish
                to reinput data  via the contractor data transfer disk.

                          Are you sure you want to proceed?  [Y/M]  |
After this Option has been completed, you can re-transfer contractor data via the interface option.
This Option can also be used in cases not involving the contractor interface option, but where you
still need to reset the Cost files.
                                           7-5

-------

-------
                              CHAPTERS
                     SITE SUMMARY REPORTS
8.0   SITE SUMMARY REPORTS OVERVIEW

The  third major module of RCMS provides you with the  capability  to produce Site
Summary Reports. Using the Archive Disk as a source of information, these reports can
be generated periodically (e.g., weekly or monthly), to provide on-going, easy to analyze cost
information. Site Summary Reports can also be produced at the conclusion of a removal
action to provide a complete summary of costs. RCMS allows you to produce the following
types of reports:

       •      Facsimiles of 1900-55 Forms and Daily Cost Summaries
       •      Project Cost Summaries
       •      Detailed Project Cost Summaries
       •      Incident Obligation Logs
       •      ERCS Daily Expense Log

RCMS also allows you to produce the following cost component summaries:

       •      ERCS Personnel
       •      ERCS Equipment
       •      ERCS Expendable Materials
       •      ERCS Subcontractors
       •      1900-55 Adjustments
       •      ERCS Disputed Costs

       •      EPA Costs
              TAT Costs
       •      Federal Agency Costs
       •      Additional Costs
       •      Daily Cost Summary Adjustments

Cost data manipulated in this section of RCMS is totally independent of the Cost Tracking
and Cost  Projection sections. Therefore, it is possible to produce  Site Summary Reports
for one site while performing cost  tracking for another. In addition, you can work with
historical  data for a site without disturbing the current cost tracking information for that
site.
                                    8-1

-------
8.1  PREPARING THE SITE SUMMARY  DATA FILES
To use the Site Summary module, select Option 2: Site Summary from the RCMS Main
Menu. The program will respond to your choice  of this Option by displaying the Drive
Specification screen.
            SITE SUMMARY
DRIVE SPECIFICATION
06/01/89
                   Please select the drive where the Site Summary Archive
                   data is to be loaded from.  fcTvr	
                              Is A: the correct drive/path?  Y
You will be prompted to enter the drive where the Site Summary Archive information can
be found and to confirm your choice. The program will then display the Data Loading
Options Menu.
SITE SUMMARY
DATA LOADING OPTIONS
06/01/89
              1. Use site summary data currently stored on the hard disk
              2. Add site summary data from an archive disk to the existing
                 site summary data currently on the hard disk  (Hard disk
                 must already contain data)
              3. Erase any existing site Burmary data on the hard disk and
                 load new data from an archive disk (Start up or new site)
              4. Erase any existing site summary data on the hard disk
              5. View site Information on an archive disk
              0. Exit Site Summary Reports
                 Your Choice:  i
                                       8-2

-------
A.    Option 1: Use Site Summary data currently stored on the
       hard disk

       Select this Option to produce a Site Summary Report from the data currently
       stored on the hard disk. The computer will respond by displaying first information
       relating to the Site Summary Data on the hard disk; then the Site Summary Main
       Menu (see page 8-4).

B.    Option 2: Add Site Summary data from an archive disk  to
       the existing site summary data  currently on the hard disk
       This Option is particularly useful for the production of on-going summary reports
       throughout the course of a removal action. Each day, new data from the archive
       disk can be added to the hard disk files.

       The computer will respond  to your choice of this  Option by displaying the site
       number corresponding to the data currently on the hard disk and by prompting you
       to insert the Archive Disk in Drive A.  The computer will then load the data from
       the Archive Disk that corresponds to the  hard disk's site number. It is essential
       that the hard  disk already contain Site Summary data.  Once this data has been
       loaded, the program will inquire  if you wish to add data from another Archive
       Disk.  When  the loading process is  complete, RCMS will return  to the  Site
       Summary Main Menu.

C.     Option  3:  Erase any existing  Site  Summary data  on the
       hard disk  and load new  data from an archive disk.

       This Option is used when you wish to prepare the hard disk files to  receive new
       Site Summary  information. This will occur when you produce the initial Summary
       Reports for a  particular site.

              Note:  This Option will erase any-Site Summary data currently stored on the
              hard disk.
       The system will respond to your choice of this Option by prompting you to insert
       an Archive Disk into  Drive A.  The screen will then display the  site numbers
       corresponding to the archive data.  If there is more than one site number on the
       Archive disk, you will  be  asked to enter the one you desire.  Once the loading
       procedure is complete, the system will inquire if you wish to add data from an
       additional Archive Disk.   After all the Archive data has been transferred to the
       hard disk, the  screen will return to the Site Summary Main Menu.
                                     8-3

-------
 D.    Option 4: Erase any  existing Site  Summary data  on the
       hard disk.

       This Option allows you to erase all current Site Summary files on the hard disk.
       It is useful when you need to allocate more space for data on the hard disk. After
       using this Option, you will need to add data from an Archive Disk before Site
       Summary Reports can again be produced.

 E.    Option 5: View site  information on an Archive disk

       This Option allows you to view general site information contained on an Archive
       Disk. The screen will display  the name, number, and the date range for the cost
       data stored on that disk.  You can then choose the specific date's information you
       wish to view.
8.2  PRODUCING  SITE SUMMARY REPORTS

After selecting and confirming one of the data loading Options above, the Site Summary
Main Menu will be displayed.
SITE SUMMARY
MAIN
MENU
06/01/89
              1. Facsimile of 1900-55 or Daily Cost Summary for previous dates

              2. Site Cost Report:  Site Surmaries

              3. Site Cost Reports:  Component Summaries

              4. Change printer escape sequences for output

              0. Return to the previous menu

                Tour Choice:
A.     Option  1:  Facsimile  of a 1900-55  Form  or  Daily  Cost
       Summary

       This Option allows you to create a copy of a 1900-55  Form or a Daily Cost
       Summary for any particular date.  These facsimile reports contain the exact same
       data as  the  originals, however, they will be  clearly identified with the word
       "Archive."  Because facsimile reports are only duplicates of originals, the last page
       of the facsimile 1900-55 Form will not contain contractor or OSC signature blocks.
                                                                                               I
                                                                                               I
                                                                                               i
                                     8-4

-------
SITE
SUMMARY
1900-55
AND
DCS
SUMMARY
REPORTS
06/01/89
              1. Reproduce a 1900-55 For* the currently loaded files

              2. Reproduce a Daily Cost Sumary from the currently loaded files

              0. Return to the previous menu

                 Your Choice:  I
       The procedures for producing facsimiles of 1900-55 Forms or Daily Cost Summaries
       are similar. If multiple prime contractors were used at a site, you will be asked
       to choose  the  specific contractor  whose 1900-55 Form you  wish  to print.  The
       computer will then display the available time span of the 1900-55 Form or DCS
       data files. You will then be prompted to choose a specific date range from within
       this  time span and  to put a printer on-line.

B.    Option  2:   Site Cost Report:  Site Summary

       This Option allows you to produce several summary reports.  The Site Summary
       Reports Menu will be displayed when you choose this Option.
           SITE SUMMARY
SITE SUMMARY REPORTS
06/01/89
                           1. Project  Cost Summary

                           2. Incident Obligation Log

                           3. Contractor Daily Expense Log

                           0. Return to the previous menu

                             Your Choice:
                                       8-5

-------
       Once you have selected one of the Report Options shown, the program will display
       the date range of the cost data stored in the system.  You will then be prompted
       to choose a specific date range from within this time span. These reports can span
       any length of time within that listed, from a single day to the entire length of the
       removal project
SITE
SUMMARY
SPECIFY
REPORT
DATE
RANGE
06/01/89
             The ARCHIVE data for this site covers the following period:
                         FROM:  mmm  TO:  mm&
         Enter the dates within the above range you want the report to cover.


                         FROM:  V>mm  TO:  OWf/M
       An example of a Project Cost Summary is shown in Exhibit Vffl-A.

C.     Option 3:  Site Cost Reports - Component Summaries

       This  Option allows you to produce reports  detailing the cost components of a
       removal action.   The computer will respond to your choice of this Option by
       displaying the  Component Summary Menu.
           SITE SUMMARY
COMPONENT SUMMARY
06/01/89
                          1. Cleanup Contractor Costs

                          2. EPA, TAT, and Other Costs

                          0. Return to the previous menu

                             Your Choice:  I
                                     8-6
                                                                                               '-:!
                                                                                                «

-------
The Cost  Component Report Menu  is  divided into  two parts:   1. Cleanup
Contractor Cost Reports and 2. Non-Cleanup Contractor Cost Reports.  The latter
includes costs for EPA, TAT, and other federal agencies.

1.     Option 1: Cleanup Contractor Costs

       When you select this Option, the Cleanup Contractor Menu is displayed.
       Note that the contractor name is displayed in the upper left-hand corner
       of the screen.
  ACME ENTERPRISES
SITE SUMMARY
06/01/89
                    1. Personnel
                    2. Equipment
                    3. Unit Rate Materials
                    4. At  Cost Materials
                    5. Subcontractor Final Bills
                    6. Subcontractor Auait Bills
                    7. 1900-55 Adjustment/Comments

                    0. List selected report's Disputed costs
                    P. Specify Date Range and Print Reports
                    H. Help Screen for Selection

                    0. Return to previous menu
                       Your Choice:
               Option 1:  Personnel

               Select this Option to produce reports detailing contractor personnel
               records. The computer will respond to your choice of this Option
               by displaying the Personnel Reports Menu.
                                 8-7

-------
ACME









SITE SUMMARY

PERSONNEL REPORTS
06/01/89


1. Categorical Personnel Summary
2. Individual Personnel Sunnary
3. Detailed Personnel Sumary (Indiv. or Cat.)
4. Contractor Component Report
Choose report to print...
Enter a blank to quit








 1.      Option 1:  Categorical Personnel Summary

        Select this Option to print a personnel report detailed by
        job  category.   Once you have chosen this Option, the
        program will return you to the Personnel Reports Menu
        where Option 1: Personnel, will be highlighted, indicating
        this report has  been selected for printing. To de-select a
        highlighted category, simply enter the number Option again.

2.      Option 2:  Individual Personnel Summary

        Select this Option to produce a list of all ERCS employees
        on a removal project   This report furnishes a history of
        each employee from the beginning of a removal action to
        the present  Once you choose this Option, the program
        will return you to the Cleanup Contractor Menu where the
        personnel category will be highlighted.
3.
Option 3:
Category)
Detailed  Personnel Summary (Individual or
       Select  this  Option  to  produce a  Detailed  Personnel
       Summary  Report   You  have the option of  tracking
       personnel either by name or by job category. To  track an
       individual, input the person's CODE and ID numbers. To
       track a job category, input the category CODE and leave
       the ID number blank. To exit leave both the CODE and
       ID numbers blank.
                                                                        I
                 8-8

-------
ACME ENTERPRISES
Code ID Name
PERSONNEL TRACKING 06/01/89
Code ID
001 067 DRIVER, 0. 005 Oil
001 22 MORROW, T. 005 026
001 470 SNYDER, D 005 055
004 001 GORMAN, C. 005 18
004 055 LEE, G.
005 54
004 08 MARLOU, G. 005 64
004 095 REYNOLDS, A. 005 66
004 098 BROUN, R.
004 329 KING, J.
004 333 CHASE, D.
006 08
006 095
006 54
004 54 CORMAN, J. 006 555
004 66 HALL, R.
006 64
005 001 CORMAN, C. 006 66
CODE*
'' H>*A
 to Backup,  to Advance, 
Name
SAVAGE, R.
RICHIE, R
LEE, G.
THORTON, D.
CORMAN, J.
O'BANNON, J.
HALL, R.
MARLOU, G.
REYNOLDS, A.
CORMAN, J.
SHERROU, U.
O'BANNON, J.
HALL, R.

for Kelp
4.       Option 1:  Contractor Component Report

        Select this Option  to print  the Contractor Component  Report.
        This report provides a subtotal of the costs for each employee as
        well as total costs for all personnel.  The computer will ask if you
        wish to print personnel with zero hours.  After entering either "Y"
        or "N", the computer will return to the Cleanup Contractor Main
        Menu.
ACME ENTERPRISES SITE SUMMARY

06/01/89

PERSONNEL REPORTS
1. ERCS Personnel Component Report
Print Personnel with zero hours?
CY/N] N
Choose report to print... 1
Enter a blank to quit
r Cat.)


                        8-9

-------
NOTE:  If you wish to print more than one personnel report, they must be
printed singularly.
b.      Option 2:  Equipment

        Select this Option to produce reports detailing equipment records.
        The computer will respond to this selection by displaying the
        Equipment Reports Menu.

        1.      Option 1: Categorical Equipment Summary

               This Option reports the history of categories of equipment items.
               When you choose this Option, the computer will return to the Cleanup
               Contractor Menu where the equipment category will be highlighted.

        2.      Option 2: Individual Equipment Summary

               Select this Option to produce a list of all equipment on a removal
            .   project, as well as a history of individual equipment items from  the
               beginning of a removal action  to the present.

        3.      Option 3: Detailed Equipment Summary (Individual or  Categorical)

               Select this Option to track an individual piece of equipment, or to
               track an  entire equipment category.   In  the first instance input  the
               equipment CODE and ED numbers, in the second case, input only  the
               CODE. Each piece of equipment utilized will be reported separately
               on the Site Summary Report.  To exit  to the Cleanup Contractor
               Menu enter a blank response.
ACME
Code
043
043
043
043
043
044
075
075
075
076
084
096
165

ID
001
3018
AR001
K118
K126
K125
301
K301
K302
K911
602
C01
CEN01

 to
Name
TRUCK
TRUCK
TRUCK
TRUCK
TRUCK
TRUCK
TRUCK
TRUCK
TRUCK
EQUIPMENT

PICKUP 1/2
PICK UP
PICKUP 1/2
PICKUP 1/2
PICKUP 1/2
4 WHEEL DR

TON

TON
TON
TON

ROAD TRACTOR
ROAD TRACTOR
ROAD TRACTOR
BACKHOE CAT 225
LDR CAT955,IH 175
CRANE
20 TON

GENERATOR 5KW
COOEJf
I">*H
Backup,  for Help
                       8-10

-------
        4.      Option 4:  Contractor Equipment Component Report

                Select this Option to produce a Contractor Equipment Component
                Summary.  After selecting this Option, the computer will return to the
                Cleanup Contractor Menu with the equipment category highlighted.

 To produce a  report for Option 3 through Option 7 on  the Site Summary Menu,
 simply choose the cost component desired, and enter the corresponding option number
 from the menu.  To de-select the item, enter the corresponding number again.
 Note:  All reports selected for printing appear on the screen in a highlighted field.  Once
you have finished selecting reports, enter a *P" to initiate printing.  You will be asked to
 confirm your selections before printing.
c.      Option D:  List selected report's Disputed Costs

        Select this Option to print only the disputed costs of the reports highlighted.
        Any costs not in question will not be included in the Disputed Costs Report

d.      Option P: Specify Date Range and  Print Reports

        Select this Option to print highlighted reports. The computer will display the
        available time range and the computer will prompt you to choose a specific date
        range within this time span and to put the printer on-line. The computer will
        then prompt you  to confirm your choice(s).
   SITE SUMMARY
PRINT REPORTS
06/01/89
          Are you sure you want to print the following
          ERCS Cost Component Sunmary reports?  [Y/N]

              Personnel with hours only > 0
              At Cost Materials
              Subcontractor Final Bills
For an example of an Contractor Component Report, see Exhibit VHI-B.
                        8-11

-------
                Option H:  Help Screen for Selection
2.
        This Option will provide assistance in selected areas of the Site Summary
        module. By pressing "H", you can receive instructional hints for producing Site
        Cost Reports.

Option 2:  EPA, TAT, and Other Costs
SITE
SUMMARY
EPA,
TAT,
AND OTHER
COSTS
06/01/89
               5. TAT  Special Projects
                                               .,,...,.,.,,,, .
                                               7. Other Federal Agency
                                               8. Additional Costs
                                               9. DCS Adjustment/Garments
                            0. Return to previous menu
                            P. Specify Date Range and Print  Reports
                   To  select a report to print,  enter the nuriber of the selection
                   (the choice will be highlighted).  You can choose more than one.
                   To  deselect a highlighted choice, enter the number again.
                              Enter "P" when you are ready to print.
                               Your Choice:
        To produce a report for a  particular cost component, simply choose and enter the
        corresponding number from the Menu. You can select as many of the listed choices
        as you require.  If you decide that you do not want to print a selected report, simply
        re-enter the number corresponding to that cost report. All the reports you have chosen
        to print will appear on the screen in a highlighted field. If you have selected more than
        one report, this Option allows you to "chain" print  these reports over a specified date
        range.  Once you have finished your report selections, enter a "P" to initiate printing.
        You will first be shown a list of the reports you selected and prompted to confirm your
        choices.
                                                                                                w
                                8-12

-------
D.    Option 4:   Change  printer escape  sequences for output
       If you are using a printer other than a dot matrix printer, select this Option to change the
       default printer codes within the Site Summary module, otherwise you will be unable to correctly
       print the compressed type needed for the Site Summary Reports.
                       SITE SUMMARY
PRINTER ESCAPE SELECTION
06/01/89
                         The default printer escape sequence is:
                         Compressed....chr(15)
                         Normal	chr (18)
                                  Compressed....!
                                  Normal	

                                  Are these the correct sequences?  Y
                         Enter a new escape sequence or a BLANK to use the default.
       Default rates are set as chr(15) for compressed printing and chr(18) for normal printing. Please
       consult your printer manual  to determine the proper print codes, or sequences, needed to
       override the default values.  You will need to enter codes  for both compressed and normal
       printing.  If you wish to use the default values, simply enter a BLANK

              Note:  Even if you are using a dot matrix printer, you may need to override the default
              values  to correctly print a Site Summary Report Please consult your printer manual for
              new codes.
                                      8-13

-------
  Exhibit Vm-A
• * SUMMARY * * SUMMARY * * SUMMARY • * SUMMARY * * SUMMARY * * SUMMARY • • •
PROJECT COST SUMMARY Page 1
OLD HENLEY II
FROM: 10/14/88 TO: 10/29/88
10/14/88 10/29/88 10/14/88 10/29/88
Ceilings Ceilings Balances Balances
Site Total 1,904,000 0 1,903,834 0
ERCS: RIEDEL ENV. SVCS.
TAT: ECOL. I ENVIRON 170,000 0 170,000 0
i i i
Cost Categories
1900-55 Costs: RIEDEL ENV. SVCS.
Personnel
Equipment
Unit Rate Materials
At Cost Materials
Subcontractors (Final Bills)
Adjustments
Total 1900-55 Cost (Less Awaiting Bills)
Total Awaiting Bills
Total 1900-55 Cost: RIEOEL ENV. SVCS.
TAT Costs:
Personnel
Special Projects
Analytical Services
Total TAT Cost
EPA Costs:
Regional On-site Personnel
Regional Off -site Personnel
Indirect
Non-Regional Personnel:
Total EPA Cost
Other Federal Agency Costs:
Total Other Federal Agency Cost
Additional Costs:
Total Additional Cost
Total Site Cost (Includes Await Bills)
Cost
4,137.59
4.25
0.00
17.43
144.63
0.00

0.00
0.00
0.00
0.00
0.00
0.00


Totals
4,303.90
0.00
4,303.90
0.00
0.00
0.00
0.00
4,303.90
8-14

-------
  Exhibit VTII-B
• * SUMMARY * " SUMMARY • * SUMMARY • • SUMMARY * " SUMMARY * * SUMMARY " * *!
HAZARDOUS SUBSTANCE RESPONSE FUND CONTRACTOR COST REPORT PAGE 1
US ENVIRONMENTAL PROTECTION AGENCY {CONTRACTOR: CONTRACT #
SITE NAME: OLD HENLEY II JRIEDEL ENV. SVCS. 68-01-7334
SITE NUMBER: E3
«
CONTRACTOR PERSONNEL [DELIVERY ORDER # DATE RANGE
SITE SUMMARY REPORT 7334-06-029 10/14/88 TO
j 10/29/88
CODE
JOB CATEGORY
NAME AND
1900-55 DATE
i
HOURS
REG ! OT
ERCS CONTRACTOR RESN: RES - New Or
001-1
INI
SUf
CA
SUI
013-1
INC
SUI
CA'
SUE
016-1
INI
SUI
INC
SUB
J
SUE

RESPONSE MGR
R.KOENTOP
10/14/88
10/18/88
10/19/88
) I VI DUAL
ITOTALS:
EGORY
JTOTALS:
FIELD CLERK-
N.B.HENRICI
10/14/88
10/18/88
10/19/88
JIV1DUAL
ITOTALS:
EGORY
ITOTALS:
I NO HYGEN/SAI
JAY EDWARD!
10/18/88
10/19/88
IVIOUAL
TOTALS:
JAY .EDWARD!
10/19/88
IVIDUAL
TOTALS:
EGORY
TOTALS:
-LEVE
0077)
2.0
4.5
8.0
14.5
14.5
[EVEL
CLE (0051
0.5
1.0
1.0
2.5
2.5
•ETY
i (0035)
5.0
8.0
13.0
(035A)
5.0
5.0
18.0
0.0
0.0
2.0
2.0
2.0
0.0
0.0
0.0
0.0
0.0
0.0
1.0
1.0
0.0
0.0
1.0
S/H
cans
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
B/A
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
i iii
TRAVEL
LODGE &
PER DIEM
0.00
50.75
25.00
75.75
75.75
0.00
0.00
0.00
0.00
0.00
330.75
25.00
355.75
6.00
6.00
361.75

TOTAL
G&A
0.00
2.87
1.41
4.28
4.28
0.00
0.00
0.00
0.00
0.00
18.69
1.41
20.10
0.34
0.34
20.44
TOTAL
COST
152.34
396.39
788.11
1336.84
1336.84
12.87
25.74
25.74
64.35
64.35
553.64
393.97
947.61
210.54
210.54
1158.15
1 ^
8-15

-------
Exhibit mV-B (continued)
CONTRACTOR PERSONNEL j DATE RANGE | PAGE 2
SITE SUMMARY REPORT 10/H/88 TO 10/29/88
CODE
017-1
INI
SUI
CA1
SUI
COI
T(
	 1
JOB CATEGORY
NAME AND
1900-55 DATE
HYDRO-/GEOLCX
ED NICOLET
10/18/88
10/19/88
)IVIDUAL
(TOTALS:
EGORY
(TOTALS:
(TRACTOR
DIALS:
	 1
HOURS
REG
3 1ST
(0248)
8.0
8.0
16.0
16.0
51.0
OT
2.0
7.0
9.0
9.0
12.0
S/H
0.0
0.0
0.0
0.0
0.0
B/A
0.0
0.0
0.0
0.0
0.0
TRAVEL
LODGE I
PER DIEM
138.75
25.00
163.75
163.75
601.25
TOTAL
G4A
7.84
1.41
XXSSZXK
9.25
9.25
33.97
i
TOTAL
COST
708.69
869.56
1578.25
SSXVXXSXX
1578.25
4137.59
-"
    8-16

-------
                               APPENDIX A
                    EDIT/VIEW/DELETE  OPTION
Throughout  RCMS, a standard program structure and editing procedure is used for
updating the records  in individual files. The editing screen is  referred  to as  the
Edit/View/Delete screen  throughout this User's Guide.  Only the standard features are
explained in  here; features that are applicable only to a particular file are explained within
that specific  section of the User's Guide.  For reference, an Edit/View/Delete screen for
the ERCS personnel file is shown below:
ACHE ENTERPRISES
Rec
*
> 1
2
3
4
5
6
7
Job
Code
001-
003-
003-
004-
005-
006-
014-
Cont
Code
886.1
0001
0001
0001
0001
0001
0001
Emp
ID*
1988
1987
1969
2334
1967
1956
0246
PERSONNEL
Job
Category
Name
Reg.
Hours
06/01/89
O.T. Sun/Hoi
Hours
Hours
B.Air
Hours
SUPERVISOR JWltSOI^ iBuflfc M3& ;:aOlOO ;;0.«0
CLEANUP
CLEANUP
TECH
TECH
LABORERS
EQUIP OPERAT
TRUCK DRIVER
ENGINEER
Action keys: [*J] Edit
CD] Delete
[U] Undelete
CHE
[t]
W
[F2]
HEART, G.
ROE, D.
CHAP, H.
MORRIS, J.
LARES, L.
KING, J.
Previous record
Next record
Extended edit
8.00
8.00
8.00
8.00
8.00
8.00
[PgUp]
[PgDn]
[Esc]
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Previous page
Next page
Quit
The available "Action Keys" always appear at the bottom of the screen.

A.     Viewing Records

       Records appear on the screen ten at a time.  Additional entries in the file can be
       displayed by pressing the    key.  To view previous  entries, press  the
        key.

B.     Moving the Cursor

       Press the up and down arrow keys to move the cursor from record to record.

C.     Editing Records

       Once the cursor has been positioned next to the desired record, you can enter the
       editing mode simply by pressing  .  The fields that may be edited  will
       be highlighted.  By continuing to press  you can to move from field to
       field.  Once you choose a  field to edit, simply type the new data over the old  and
       press  . When you press  in the last field on the screen that
                                      A-l

-------
        can be edited, the cursor automatically returns to the left of the current record.
        You may now reposition the cursor to edit another record.

D.      Extended Edit

        The  key activates the Extended Editing mode.  The Extended Editing mode
        allows you  to edit related information not listed on the main edit screen.  When
        you press  and activate the Extended Edit mode a window will appear in the
        top right corner of the screen. Prompts will be displayed to assist you with gaining
        access to this related information.
ACME ENTERPRISES

Rec
H

1
2
3
4
» e
6
7

Job
Code

001-
003-
003-
004-
fine
006-
014-

Cont
Code

0001
0001
0001
0001
AAA4
0001
0001

Emp
ID*

1988
1987
1969
2334
1967
1956
0246

PERS
Job
Category


SUPERVISOR
CLEANUP TECH
CLEANUP TECH
LABORERS
FQt
I1D ADCDAT
TRUCK DRIVER
ENGINEER CHE
Name

SMITH, JI
HEART, G.
ROE, DONN
CHAP, MAR
itfttfrj '{*-fr-:-'$ji

Edit the following
information if you


Lodging:
Travel:


rate
wish:

25 00
58.00
' 149.00

Is this correct? [Y/N] V.

LARES.'LYNN 8.00 4.oo o.
KING, JUNE 8.00 0.00 0.

00 0.00
00 0.00
*•* EXTENDED EDITING MODE •**

E.
Deleting Entries

For  most Mies, excluding the ERCS equipment and subcontractors  Mies, entries
may be deleted by pressing the "D* key when the cursor is positioned to the left
of the desired record.  A prompt will require you  to  confirm  your choice.  A
deleted record will continue to appear on the screen with a series of asterisks
replacing the record  number.  It will remain on the screen until you  exit the
Edit/View/Delete screen.  Before exiting the Edit/View/Delete screen, any record
marked for deletion can be restored by pressing the  "U" key.

        Note: For an  explanation on deleting ERCS equipment see page 3-20.
                                        A-2

-------
ACME ENTERPRISES
Rec
f
1
***
3
4
5
» 6
7

Job
Code
001-1
003-
003-
004-
005-
006-
014-

Cont
Code
0001
0001
0001
0001
0001
0001
0001
Are
Emp
ID*
1988
1987
1969
2334
1967
1956
0246
you
PERSONNEL
Job
Category
SUPERVISOR
CLEANUP TECH
CLEANUP TECH
LABORERS
EQUIP OPERAT
TRUCK DRIVER
ENGINEER CHE
sure you want
Name
SMITH, JIM
HEART, G.
ROE, DONNA
CHAP, MARK
MORRIS, JIM
LARES, LYNN
KING, JUNE
to delete this
Reg.
Hours
8.00
.00
.00
.00
.00
.00
.00
entry?
06/01/89
O.T. Sun/Hot
Hours
0
0
0
0
0
4
0
.00
.00
.00
.00
.00
.00
.00
Hours
0.00
0.00
0.00
0.00
0.00
0.00
0.00
B.Air
Hours
0.00
0.00
0.00
0.00
0.00
0.00
0.00
IY/N] |
F.      Exiting the Edit/View/Delete screen




        To exit the Edit screen, press the  key.
                                       A-3

-------
f
w
1

-------
                             APPENDIX B
                     USER SUPPORT SYSTEMS
As an adjunct to this User's Guide, a support system to aid you in your use of RCMS has
been developed.

EPA's Environmental  Response Team (ERT), maintains an  electronic bulletin board
containing up-to-date information on the use of RCMS, as well as other EPA utilized
computer systems. You are encouraged to log on to, and use this bulletin  board by calling:

                                1-201-906-6968

For direct assistance in the use of RCMS, dial:

                                1-201-225-6266

By calling this number you can receive immediate aid involving a problem or clarifying a
procedure encountered in your use of RCMS.
                                   B-l

-------
                             APPENDIX C
            ELECTRONIC REPORT TRANSMISSION

RCMS has the capability to electronically transmit copies of 1900-55 Forms, Daily Cost
Summaries, Incident Obligation Logs, Site Summary Reports and any portion of those
printed reports.  Every time you produce these reports, a copy suitable for electronic
transmission is also created. By using CrossTalk, SmartComm, Close-Up or any other data
communication software, these reports can be forwarded to remote systems.  By using EPA
E-Mail, copies can be sent to any EPA office (Regional or Headquarters).

On  the  page that  follows  you will find a  listing  of RCMS  reports for  electronic
transmission.
                                  C-l

-------
      Form

Cost Projection Reports

      Cost Projection

Cost Tracking Reports
RCMS Reports for Electronic Transmission

             Text File Name



             COSTPROJ.TXT
      1900-55
           . (for  ERCS  contractor
            #1, for other contractors,
            use  the  appropriate
            subdirectory)
      Daily Cost Summary
      IOL

Summary Reports

      Facsimilie 1900-55 Form
      Facsimile DCS

      Project Cost Summary
      Detailed Project Summary
      IOL (From Site Summary)
      Contractor Daily Expense Log
             FORM1955.TXT
             FORMDCS.TXT
             FORMIOL.TXT
             FORM(MMDD).TXT
             where MMDD  is the
             date   of  the  report
             (month,day)
             DCS(MMDD).TXT

             SCMSITE.TXT
             SCMCOST.TXT
             FORMIOL.TXT
             CDEL.TXT
 Subdirectory
\RCMS\COSTPROJ
\RCMS\ERCS1
\RCMS
\RCMS
\RCMS\SUMMARY
\RCMS\SUMMARY

\RCMS\SUMMARY
\RCMSVSUMMARY
\RCMS\SUMMARY
\RCMS\SUMMARY
      Contractor   Personnel
      Component Report
      Contractor   Equipment
      Component Report
      Unit Rate Materials
      At Cost Materials
      Final Subcontractor
      Await Subcontractor
      1900-55 Adjustments/Comments

      EPA On-Site Regional
      EPA Off-Site Regional
      EPA Non-Regional

      TAT Personnel
      TAT Special Projects
      TAT Analytical Services

      Other Federal Agencies
             SUPER.TXT

             SUEQIP.TXT

             SFINV.TXT
             SFFLPA.TXT
             SUSUBF.TXT
             SUSUBA.TXT
             SUADJ.TXT

             SUEPNPER.TXT
             SUEPFPER.TXT
             SUEPOTHR.TXT

             SCTATPER.TXT
             SUTATSP.TXT
             SUTATAN.TXT

             SUFEDAGY.TXT
\RCMS\SUMMARY

\RCMS\SUMMARY

\RCMS\SUMMARY
\RCMS\SUMMARY
\RCMS\SUMMARY
\RCMS\SUMMARY
\RCMS\SUMMARY

\RCMS\SUMMARY
\RCMS\SUMMARY
\RCMS\SUMMARY

\RCMS\SUMMARY
\RCMS\SUMMARY
\RCMS\SUMMARY

\RCMSVSUMMARY
                                      C-2

-------
Additional Costs                  SUOTCOST.TXT          \RCMS\SUMMARY
DCS Adjustments                 SUDADJ.TXT             \RCMS\SUMMARY
Detailed Personnel (category)        PERDTCAT.TXT          \RCMS\SUMMARY
Detailed Personnel (individual)       PERDTIND.TXT          \RCMS\SUMMARY
Individual Personnel Summary       PERISUM.TXT            \RCMS\SUMMARY
Category   Personnel  Summary     PERCSUM.TXT           \RCMSVSUMMARY
Equipment Summary (individual)     EQISUM.TXT             \RCMS\SUMMARY
Equipment Summary (category)      EQCSUM.TXT            NRCM^UMMARY
Detailed Equipment (category)       EQDTCAT.TXT           \RCMSVSUMMARY
Detailed Equipment (individual)     EQDTIND.TXT           \RCMS\SUMMARY
                                 C-3

-------
        :
       -
•  •*1

-------
                                  APPENDIX  D
                             TELENET NUMBERS
    TELENETS Dial Access Services provide you with 24 hour access to the TELENET public
    data network for reliable data transmission across town and worldwide. You can access the
    TELENET public data network nationwide with a local phone call from thousands of cities
    and towns or by using TELENETs IN-WATS service. The network is also accessible from
    over 75 international locations.

    Depend on TELENETs dial access services for:

    •  Dial up flexibility with access on demand
    •  Error protected network transmission
    •  24-hour customer service support and network management

    For customer service, call  toll-free 1-800-336-0437.   From overseas locations  with
    non-WATS access,  call 1-703-689-6400.

    IN-WATS access is available in all U.S. locations:

    •  For 300-1200 EPS  (baud) service, dial 1-800-424-9494
    •  For 2400 EPS (baud)  service and local error protection, dial 1-800-238-0631

SERVICE REQUIREMENTS:

SPEED:                  MODEM TYPE:
300 EPS                  BELL 103 compatible
1200 EPS                 BELL 212A compatible
2400 EPS                 V.22 BIS compatible

When using local error protection, your modems must be MNP-compatible, or you can use MNP-
compatible software in your PC

Note:  Dial the 2400 bps access number when using local error protection at 300, 1200 or 2400
       bps.
                                        D-l

-------
TELENET Numbers

SI
AL
AL
AL
AL
AL
AL
AL
AL
AL
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK
AK


AK
AK
AK
AR
AR
AZ
AZ
Area
Code
205
205
205
205
205
205
205
205
205
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907
907


907
907
907
501
501
602
602

Cltv
ANNISTON
BIRMINGHAM
DECATUR
DOTHAN
FLORENCE
HUNTSVILLE
MOBILE
MONTGOMERY
TUSCALOOSA
ANCHORAGE
BARROW
BETHEL
COLD BAY
CORDOVA
DEADHORSE
DELTA JUNCTION
DILLINGHAM
FAIRBANKS
GLENNALLEN
HOMER
ILIAMNA
JUNEAU
KETCHIKAN
KING SALMON
KODIAK
KOTZEBUE
MCGRATH
NOME
NORTHWAY
PALMER
PRUDHOE BAY
ST PAUL
SEWARD
SITKA
SOLDOTNA
TALKEETNA
TANANA


VALDEZ
WHITTIER
YAKUTAT
FT SMITH
LITTLE ROCK
PHOENIX
TUCSON
300/
1200 BPS
236-9711
328-2310
355-0206
793-5034
767-7960
539-2281
432-1680
269-0090
345-2077
258-7222
852-2425
543-2411
532-2371
424-3744
659-2777
895-5070
842-2688
456-3282
822-5231
235-5239
571-1364
789-7009
225-1871
246-3049
486-4061
442-2602
524-3256
443-2256
778-2301
745-0200
659-2777
546-2320
224-3126
747-5887
262-1990
733-2227
366-7167
(300 BPS
ONLY)
835-4987
472-2467
784-3453
782-2852
372-4616
254-0244
747-0107
             2400 BPS    Class
             251-1885
             438-6881
             832-4314
              374-2861
              256-6955
              747-9395
B
B
B
B
B
B
B
B
C
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
C
B
A
B
      D-2

-------
TELENET Numbers

si
CA
CA
CA*
CA
CA
CA
CA*
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CA
CO
CO
CO
CO
CO
Area
Code
805
916
714
213
415
619
707
209
714
818
415
213
213
213
209
209
408
213
415
619
415
714
916
408
415
619
415
408
213
415
415
714
805
408
707
209
707
805
209
818
818
303
303
303
303
303

Citv
BAKERSFIELD
CHI CO
COLTON
COMPTON
CONCORD
ESCONDIDO
EUREKA
FRESNO
GARDEN GROVE
GLENDALE
HAYWARD
LOS ANGELES
LOS ANGELES
MARINA DEL REY
MERCED
MODESTO
MONTEREY
NORWALK
OAKLAND
OCEANS IDE
PALO ALTO
POMONA
SACRAMENTO
SALINAS
SAN CARLOS
SAN DIEGO
SAN FRANCISCO
SAN JOSE
SAN PEDRO
SAN RAFAEL
SAN RAMON
SANTA ANA
SANTA BARBARA
SANTA CRUZ
SANTA ROSA
STOCKTON
VALLEJO
VENTURA
VISALIA
WEST COVINA
WOODLAND HILLS
COLORADO SPRINGS
DENVER
FT COLLINS
GRAND JUNCTION
GREELEY
300/
1200 BPS
327-8146
894-6882
824-9000
516-1007
827-3960
741-7756
444-3091
233-0961
898-9820
507-0909
881-1382
624-2251
937-3580
306-2984
383-2557
576-2852
646-9092
404-2237
836-4911
430-0613
856-9995
626-1284
448-6262
443-4940
591-0726
233-0233
956-5777
294-9119
548-6141
472-5360
829-6705
558-7078
682-5361
429-6937
578-4447
957-7610
552-6656
656-6760
627-1201
915-5151
887-3160
635-5361
337-6060
493-9131
241-3004
352-8563
             2400 BPS    Class

                         B
                         B
             824-8976    B
                         C
             674-0127    C
                         B
                         B
             441-1861    B
             895-1207    B
             246-3886    B
                         B
             622-1138    A
             622-1138    A
             306-4922    B
                         B
                         B
                         C
                         C
             834-3194    B
                         C
             856-0484    B
                         C
             443-7434    B
                         B
             595-8870    B
             231-1703    B
             788-0825    A
             286-6340    B
             514-1590    B
                         C
                         B
             550-4625    B
                         B
                         C
                         C
                         C
                         C
                         B
                         B
                         C
             348-7141    B
             578-0950    B
             696-0159    A
                         B
                         C
                         B
     D-3

-------
CO    303   PUEBLO            542-4053                C
                             TELENET Numbers

      Area                     300/
SI    Code  Cltv	       1200 BPS    2400 BPS    Class

CT    203   BRIDGEPORT        335-5055    367-9130    B
CT    203   DANBURY           794-9075                B
CT    203   HARTFORD          247-9479    724-9396    B
CT*   203   MIDDLETOWN        344-8217                B
CT*   203   NEW BRITAIN       225-7027                B
CT    203   NEW HAVEN         624-5954    773-3569    B                          <
CT    203   NEW LONDON        447-8455                C                          ..>.
CT    203   NORWALK           866-7404                B                          $
CT    203   STAMFORD          348-0787    359-9404    B
CT    203   WATERBURY         753-4512                C                          £
DC    202   WASHINGTON        429-7896    429-0956    A
DC    202   WASHINGTON        429-7800    429-0956    A                          •>,.
DE    302   DOVER             678-8328                B                           *
DE    302   NEWARK            454-7710    737-4340    B                          j
FL    305   BOCA RATON        338-3701                C
FL    813   CAPE CORAL        275-7924                C                          ^
FL    305   COCOA BEACH       267-0800                B                          t
FL    904   DAYTONA BEACH     255-2629                C                           |
FL    305   FT LAUDERDALE     764-4505    524-5304    B                           *»
FL    904   GAINESVILLE       338-0220                C
FL    904   JACKSONVILLE      353-1818    791-9201    B
FL    813   LAKELAND          688-4366                C
FL    305   MELBOURNE         242-8247                C
FL    305   MIAMI             372-0230    372-1355    A
FL    813   NAPLES            263-3033                C
FL    904   OCALA             351-3790                C
FL    305   ORLANDO           422-4088    422-8858    B
FL    904   PENSACOLA         432-1335                C
FL    305   POMPANO BEACH     941-5445                C
FL    813   ST PETERSBURG     323-4026    327-1163    B
FL    813   SARASOTA          923-4563                C
FL    904   TALLAHASSEE       681-1902                B
FL    813   TAMPA             224-9920    223-5859    B
FL    305   WEST PALM BEACH   833-6691    655-2993    B
GA    912   ALBANY            888-3011                C
GA    404   ATHENS            548-5590                C
GA    404   ATLANTA           523-0834    584-0212    A
GA*   404   AUGUSTA           724-2752    724-4494    C
GA    404   COLUMBUS          571-0556                C
GA    912   MACON             743-8844                C
GA    404   ROME              234-1428                B
GA    912   SAVANNAH          236-2605                B
HI    808   OAHU              528-0200                2
HI    800   OTHER ISLANDS     272-5299                2
IA    515   AMES              233-6300                C
                                   D-4

-------
                             TELENET Numbers

      Area                     300/
SJ    Code  Cltv              1200 BPS    2400 BPS    Class

IA    319   CEDAR RAPIDS      364-0911    362-2764    B
IA    319   DAVENPORT         324-2445    C
IA    515   DES KOINES        288-4403    288-6206    B
IA    319   DUBUQUE           556-0783                C
IA    319   IOWA CITY         351-1421                C
IA    712   SIOUX CITY        255-1545                C
IA    319   WATERLOO          232-5441                C
ID    208   BOISE             343-0611                B
ID    208   LEWISTON          743-0099                C
IL    312   AURORA            896-0620                C
IL    309   BLOOMINGTON       827-7000                B
IL    312   CHICAGO           938-0600    938-8725    A
IL    217   DECATUR           429-0235                C
IL    815   DEKALB            758-2623                C
IL    815   JOLIET            726-0070                C
IL    309   PEORIA            637-8570    637-8582    B
IL    815   ROCKFORD          965-0400    965-0696    B
IL    217   SPRINGFIELD       753-1373            ,    B
IL    217   URBANA            384-6428    328-0317    B
IN    812   BLOOMINGTON       332-1344                C
IN    812   EVANSVILLE        424-7693    428-2522    B
IN    219   FT WAYNE          426-2268    422-3431    B
IN    219   GARY              882-8800                B
IN    317   INDIANAPOLIS      299-0024    299-6766    B
IN    317   KOKOMO            455-2460                C
IN    317   LAFAYETTE         742-6000                C
IN    317   MUNCIE            289-5068                C
IN    219   SOUTH BEND        233-7104    233-4031    B
IN    812   TERRE HAUTE       232-5329                C
KS    913   LAWRENCE          843-8124                B
KS    913   MANHATTAN         537-0948                B
KS    913   SALINA            825-7900                B
KS    913   TOPEKA            233-9B80                B
KS    316   WICHITA           262-5669    262-7961    B
KY    502   BOWLING GREEN     782-7941                B
KY    502   FRANKFORT         875-4654                B
KY    606   LEXINGTON         233-0312    233-7217    B-~^
KY    502   LOUISVILLE        589-5580    583-1006    B
KY    502   OWENSBORO         686-8107      .          B
LA    318   ALEXANDRIA        445-1053                B
LA    504   BATON ROUGE       343-0753    343-0771    A
LA    318   LAFAYETTE         233-0002    234-8451    C
LA    318   LAKE CHARLES      436-0518                C
LA    318   MONROE            387-6330                B
LA    504   NEW ORLEANS       524-4094    522-3967    A
LA    318   SHREVEPORT        221-5833                B
                                   D-5

-------
                             TELENET Numbers

      Area                     300/
5T    Code  C1tv	       1200 BPS    2400 BPS    Class

ME    207   AUGUSTA           622-3123                B
ME    207   BREWER            989-3081                C
ME    207   LEWISTON          784-0105                C
ME    207   PORTLAND          761-4000                C
MD    301   ANNAPOLIS         224-8550                B
MD    301   BALTIMORE         727-6060    752-5555    A
MD    301   FREDERICK         293-9596                B
MA    617   BOSTON            292-0662    574-9244    A
MA    617   BROCKTON          580-0721                C
MA    617   FRAMINGHAM        879-6798                C
MA    617   LAWRENCE          975-2273                C
MA    617   LEXINGTON         863-1550    863-1745    B
MA    617   LOWELL            937-5214                C
MA    617   NEW BEDFORD       999-2915                C
MA    413   NORTHAMPTON       586-0510                C
MA    413   PITTSFIELD        499-7741                B
MA    617   SALEM             744-1559       .         B
MA    413   SPRINGFIELD       781-3811        .        B
MA    617   WOODS HOLE        540-7500                C
MA    617   WORCESTER         755-4740                B
MI    313   ANN ARBOR         996-5995    665-2900    A
MI    616   BATTLE CREEK      968-0929                B
MI    313   DETROIT           964-2988    963-2274    A
MI    313   FLINT             235-8517                B
MI    616   GRAND RAPIDS      774-0966                B
MI    517   JACKSON           782-8111                C
MI    616   KALAMAZOO         345-3088    345-3122    B
MI    517   LANSING           484-0062    484-6301    B
MI    517   MIDLAND           832-7068                C
MI    616   MUSKEGON          726-5723                C
MI    313   PONTIAC           332-5120                C
MI    313   PORT HURON        982-8364                B
MI    517   SAGINAW           790-5166    799-3190    B
MI    313   SOUTHFIELD        827-4710                C
MI    616   TRAVERSE CITY     946-2121                C
MI    313   WARREN            575-9152                B
MN    218   DULUTH            722-1719                B
MN    612   MINNEAPOLIS       341-2459    338-1661    A
MN    507   ROCHESTER         282-5917                C
MN    612   ST CLOUD          253-2064                C
MO    314   COLUMBIA          449-4404                B
MO    314   JEFFERSON CITY    634-5178                C
MO    816   KANSAS CITY       221-9900    472-1430    A
MO    816   ST JOSEPH         279-4797                C
MO    314   ST LOUIS          421-4990    421-0381    A
MO    417   SPRINGFIELD       864-4814                B
                                   D-6

-------
                             TELENET Numbers

      Area                     300/
SI    Code  C1tv              1200 BPS    2400 BPS    Class

MS    601   GULFPORT          863-0024                B
MS    601   JACKSON           969-0036                B
MS    601   MERIDIAN          482-2210                B
MS*   601   STARKVILLE        324-2155                B
MT    406   BILLINGS          245-7649                C
MT    406   GREAT FALLS       771-0067                B
MT    406   HELENA            443-0000                B
MT    406   MISSOULA          721-5900                C
NE    402   LINCOLN           475-4964    475-3839    B
NE    402   OMAHA             341-7733    346-6419    B
NH    603   CONCORD           224-1024                B
NH    603   DURHAM            868-2924                B
NH    603   MANCHESTER        627-8725    625-8088    C
NH    603   NASHUA            880-6241                C
NH    603   PORTSMOUTH        431-2302                B
NV*   702   LAS VEGAS         737-6861    737-5466    B
NV    702   RENO              827-6900    827-5290    B
NJ    609   ATLANTIC CITY     348-0561                B
NJ    201   FREEHOLD          780-5030                B
NJ    201   HACKENSACK        488-6567    488-2063    B
NJ    609   MARLTON           596-1500    596-8659    B
NJ    609   MERCHANTVILLE     663-9297    665-6860    B
NJ    201   MORRISTOWN        455-0275    644-4745    B
NJ    201   NEW BRUNSWICK     745-2900    745-7010    B
NJ    201   NEWARK            623-0469    623-7122    A
NJ    201   PASSAIC           778-5600    773-3674    B
NJ    201   PATERSON          684-7560    742-4415    B
NJ    609   PRINCETON         799-5587                A
NJ    201   RAHWAY            815-1885                B
NJ    201   REDBANK           571-0003                B
NJ    201   ROSELAND          227-5277    227-6722    B
NJ    201   SAYREVILLE        525-9507                B
NJ    609   TRENTON           989-8847                B
NM    505   ALBUQUERQUE       243-4479    242-1742    B
NM    505   LAS CRUCES        526-9191                B
NM    505   SANTA FE          473-3403                C
NY    518   ALBANY            465-8444    465-8632    B
NY    607   BINGHAMTON        772-6642                B
NY    716   BUFFALO           847-1440    847-1825    B
NY*   516   DEER PARK         667-5566    243-1105    B
NY    516   HEMPSTEAD         292-3800    485-3380    B
NY    607   ITHACA            277-2142                C
NY    212   NEW YORK CITY     741-8100    645-0560    A
NY    212   NEW YORK CITY     741-4950    645-0560    A
NY    212   NEW YORK CITY     620-6000    645-0560    A
NY    716   NIAGARA FALLS     282-1462                C
                                   D-7

-------
TELENET Numbers

SI
NY
NY
NY
NY
NY
NY
NC
NC
NC
NC
NC
NC
NC
NC
NC
NC
NC
NO*
NO
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OK
OK
OK
OK
OK
OR
OR
OR
OR
OR
OR
PA
Area
Code
518
914
716
315
315
914
704
704
919
704
919
919
919
919
919
919
919
701
701
216
513
216
614
513
216
513
216
216
419
419
513
419
216
216
918
405
405
405
918
503
503
503
503
503
503
215

C1tv
PLATTSBURGH
POUGHKEEPSIE
ROCHESTER
SYRACUSE
UTICA
WHITE PLAINS
ASHEVILLE
CHARLOTTE
FAYETTEVILLE
GASTONIA
GREENSBORO
HIGH POINT
NORTH WILKESBORO
RES TRI PARK
TARBORO
WILMINGTON
WINSTON -SALEM
FARGO
MANOAN
CANTON
CINCINNATI
CLEVELAND
COLUMBUS
DAYTON
ELYRIA
HAMILTON
KENT
LORAIN
MANSFIELD
SANDUSKY
SPRINGFIELD
TOLEDO
WARREN
YOUNGSTOWN
BARTLESVILLE
LAWTON
OKLAHOMA CITY
STILLWATER
TULSA
CORVALLIS
EUGENE
HOOD RIVER
MEDFORD
PORTLAND
SALEM
ALLENTOWN
300/
1200 BPS
562-1890
473-2240
454-1020
472-5583
797-0920
328-9199
252-9134
332-3131
323-8165
865-4708
273-2851
889-7494
838-9034
549-8139
823-0578
763-8313
725-2126
235-7717
663-2256
452-0903
579-0390
575-1658
463-9340
461-5254
323-5059
863-4116
678-5115
960-1771
526-0686
627-0050
324-1520
255-7881
394-0041
743-1296
336-3675
353-0333
232-4546
624-1112
584-3247
754-9273
683-1460
386-4405
779-6343
295-3028
378-7712
435-3330
             2400 BPS    Class

                         C
             473-3200    B
             454-5730    B
             479-5445    B
                         B
             682-3505    B
                         B
             333-6204    A
                         C
                         B
             275-1251    B
                         B
                         C
             541-9096    B
                         C
                         C
             777-0312    B
                         r
                         R
                         o
                         B
             241-8008    A
             771-6480    A
             461-9044    A
             461-0755    B
                         C
                         B
             678-5043    A
                         C
                         c
                         B
                         C
             255-1906    B
                         C
             743-6843    B
                         C
                         B
             232-9513    B
                         B
             587-2774    B
                         C
                         C
                         c
                         B
             241-0496    A
                         B
             770-1405    B
      D-8

-------
TELENET Numbers

si
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
PA
RI
SC
SC*
SC
SC
SO
SD
SO
TN
TN
TN
TN
TN
TN
TN
TN
TX
TX
TX
TX
TX
TX
TX
TX
TX
TX
TX
TX
TX
TX
Area
Code
717
717
814
717
814
215
717
215
412
412
215
717
814
717
717
717
401
803
803
803
803
605
605
605
615
615
615
615
615
901
615
615
915
806
214
512
512
409
512
214
915
817
409
713
512
214

Citv
CARLISLE
DANVILLE
ERIE
HARRISBURG
JOHNSTOWN
KING OF PRUSSIA
LANCASTER
PHILADELPHIA
PITTSBURGH
PITTSBURGH
READING
SCRANTON
STATE COLLEGE
WILKES-BARRE
WILLIAMSPORT
YORK
PROVIDENCE
CHARLESTON
COLUMBIA
GREENVILLE
SPARTANBURG
PIERRE
RAPID CITY
SIOUX FALLS
BRISTOL
CHATTANOOGA
CLARKSVILLE
JOHNSON CITY
KNOXVILLE
MEMPHIS
NASHVILLE
OAK RIDGE
ABILENE
AMARILLO
ATHENS
AUSTIN
BROWNSVILLE
BRYAN
CORPUS CHRIST I
DALLAS
EL PASO
FT WORTH
GALVESTON
HOUSTON
LAREDO
LONGVIEW
300/
1200 BPS
249-9311
271-0102
899-2241
236-6882
535-7576
337-4300
295-5405
574-9462
288-9950
288-9974
376-8750
961-5321
231-1510
829-3108
494-1796
846-6550
751-7912
722-4303
254-0695
233-3486
585-1637
224-0481
348-2621
336-8593
968-1130
756-1161
552-0032
282-6645
523-5500
521-0215
244-3702
481-3590
676-9151
373-0458
677-1712
928-1130
542-0367
822-0159
884-9030
748-6371
532-7907
332-4307
762-4382
227-1018
724-1791
236-4205
             2400 BPS    Class

                         C
                         C
                         B
             236-2007    B
                         B
             337-2850    B
                         C
             574-0990    A
             471-6430    A
             471-6430    A
                         C
                         B
                         C
                         C
                         C
                         B
             831-3990    B
                         B
             252-0328    B
             271-0231    B
                         C
                         B
                         C
             336-6438    C
                         C
             265-7929    B
                         B
                         C
             521-5072    B
             527-5175    B
             255-2608    B
                         C
                         B
             373-1833    C
                         C
             929-3622    B
                         C
                         C
             684-6946    B
             745-1359    A
                         B
             332-6794    A
                         B
             227-8208    A
                         C
                         C
      D-9

-------
                             TELENET Numbers                                 - y

      Area                     300/
SI    Code  Citv	       1200 BPS    2400 BPS    Class

TX    806   LUBBOCK           747-4121                C
TX    512   MCALLEN           686-5360                C
TX    915   MIDLAND           561-9811    561-8597    B
TX    409   NEDERLAND         722-3720                B
TX    915   SAN ANGELO        944-7621                B                     /:;„?
TX    512   SAN ANTONIO       225-8004    225-3444    B                     W
TX*   214   SHERMAN           893-4995                B                    ^|.
TX    817   TEMPLE            773-9723                C                    *$&
TX    214   TYLER             597-8925                C                    *j^:
TX    817   WACO              752-9743                C                    ;<^
TX*   817   WICHITA FALLS     322-3774                B                      i>
UT    801   OGDEN             627-1630                C                    : %
UT    801   PROVO             373-0542                C                    - £
UT    801   SALT LAKE CITY    359-0149    359-0578    B                   •&$£:}
VA    703   BLACKSBURG        552-9181                C                  '->&
VA    804   CHARLOTTESVILLE   977-5330                C                   -.^r<
VA    703   COVINGTON         962-2217                C                    /Hi
VA*   703   FREDERICKSBURG    371-0188                B                   .
VA    703   HARRISONBURG      434-7121                C                    ,%^
VA*   703   HERNDON           435-1800    481-6807    B                    'v|f§
VA    804   LYNCHBURG         845-0010                C                    ,r$Sf-
VA    804   NEWPORT NEWS      596-6600                B                   ,.,:^
VA    804   NORFOLK           625-1186    625-2408    B                     '-':>
VA    804   RICHMOND          788-9902    353-0219    B
VA    703   ROANOKE           344-2036    344-2404    C
VT    802   BURLINGTON        864-0808                B
VT    802   MONTPELIER        229-4966                B
VT    802   RUTLAND           775-1676                C
VT    802   WHITE RIVER JCT   295-7631                C                       r
WA    206   AUBURN            939-9982                B
WA    206   BELLINGHAM        733-2720                C
WA    206   EVERETT           775-9929                C
WA    206   LON6VIEW          577-5835                B
WA    206   OLYMPIA           754-0460                C
WA*   509   RICHLAND          943-0649                B                       y
WA    206   SEATTLE           625-9612    623-9951    A
WA    509   SPOKANE           455-4071    838-9065    B
WA    206   TACOMA            627-1791                B                      Vv
WA*   206   VANCOUVER         693-6914                B
WA    509   WENATCHEE         663-6227                B
WA*   509   YAKIMA            575-1060                B
WI    608   BELOIT            362-5287                B
WI    715   EAU CLAIRE        836-9295                C
WI    414   GREEN BAY         432-2815    432-0346    C
WI    414   KENOSHA           552-9242                C
WI    608   LA CROSSE         784-0560                B
                                                                              - 4" ,

                                                                              >*"•
                                                                              tli-
                                  D-10

-------
                               TELENET  Numbers

       Area                       300/
SI     Code  City	        1200 BPS    2400  BPS    Class

WI     608   MADISON            257-5010    257-8472    B
WI     414   MILWAUKEE          271-3914    278-8007    A
WI     414   NEENAH             722-7636                 C
WI     414   RACINE             632-6166                 C
WI     414   SHEBOYGAN          452-3995                 C
WI*    715   WAUSAU             845-9589                 B
WI     414   WEST  BEND          334-2206                 B
WV*    304   CHARLESTON         345-6471    345-7140    B
WV     304   HUNTINGTON         523-2802                 C
WV     304   MORGANTOWN         292-0104                 C
WV*    304   WHEELING           233-7732                 B
WY     307   CASPER             265-5167                 C
WY     307   CHEYENNE           638-4421                 B
WY     307   LARAMIE            721-5878                 C

       800   IN-WATS            424-9494    238-0631
1  Access in Alaska is provided by ALASCOM, Inc. for sign-on information, call ALASCOM
   customer service at 907-264-7391 (inside Alaska) or 1-800-544-2233 (outside Alaska).

2  Hawaii service is provided by TELENET under FCC Tariff No. 1

*  An asterisk between a state and area code indicates a change in number, an upgrade to
   2400 bps service, or a new city. Refer to the 'new* listing
                                     D-ll

-------
p",-

-------
                                  GLOSSARY

 1900-55 Form - Report completed dairy for the cleanup contractor. The 1900-55 Form lists
 all charges for personnel, equipment, materials, and subcontractors billed to the site that
 day.

 Abort • The process of terminating a program  in an orderly fashion and then returning
 control to an operator or operating system.                                          .,

 Address - A memory location, usually designated by a number, where you can store a unit
 of information.

 Administrative Multiplier  -   A multiplier  applied to  TAT costs  to account for the
 administrative costs of the TAT contract.

 Archive Disk - A floppy disk used to store information  in a chronological fashion.

 Archiving • The process of transferring data from the hard drive to a floppy disk.

 ASCII • American Standard Code for Information Interchange. The coding scheme whereby
 every character the computer can access is assigned an integer code between 0 and 255.

 Await BUI  - An estimate of subcontractor costs not yet billed.

 Backup Copy -  A separate disk containing a duplicate copy of a file or group of  files,
 usually saved for  use if the original disk is lost

 Batch File -   An ASCII file that executes from the operating system when you type its
 name.  All batch files have the file extension  "BAT".

 Baud Rate •  The  speed of data transmission, usually in bits per second.

 Binary - A numbering  system that uses powers of 2 to generate all other numbers.

 Booting Up •  The  process that copies a program into RAM and begins the execution of the
 program upon computer "power up".

 Buffer • An area in memory set aside to speed up the transfer of data allowing blocks of
 data to  be  transferred at once.

 Bug - An error in a computer program.

 Central Processing Unit (CPU) - The part of the computer that allows the transmission of
data over telephone lines.

Contingency Factor -   An  allowance added to a  cost estimate to  cover  unforeseen or
unexpected costs.  Contingency factors generally  range from 10 to 30%.
                                       G-l

-------
 Cost Projection Reports • A report produced by RCMS which estimates the projected cost
 of a removal action based upon user input

 Cost Tracking Reports •  Reports generated by RCMS to serve as a tracking system for
 costs incurred at removal site (specifically the 1900-55 Form and the Daily Cost Summary).

 Cursor • A shaded, blinking, or underlined character that  indicates your position on the
 screen.

 Data Base • A collection of information, organized according to certain common elements,
 and stored in a computer.

 Decon rate -  A rate charged by the ERCS contractor for time spent on the decontamina-
 tion of an equipment item. The decon rate is a percentage of the regular use rate for this
 item.

 Default Parameters - The  standard value of a variable of system parameter. This value may
 be changed by the user.

 Deflnitization - The process whereby EPA verifies contractor charges and rates, and resolves
 billing discrepancies thus  facilitating final  payment for services rendered.

 Direct Costs - Employee salaries, per  diem,  lodging and  travel  costs  that are directly
 attributable to a removal  site.

 Directory • A grouping of files on a disk. These files are displayed together and may offer
 access to other directories (subdirectories).

 Disk Drive -  A hardware device that accesses the data stored on  a disk.

 Diskette • A flexible, oxide-coated disk used to store data.  Also called a floppy diskette.

 DOS - Disk Operating System. This software directs the flow of data between disk drives
 and your computer.  Without such an operating system, your computer can not function.

 Dot Matrix Printer -  A printer that forms characters from an array of dots rather than
 solid lines.

 DCS - Daily Cost Summary.  This report provides a complete listing of cost  components
 for a removal action.

 Edit - The process of changing or modifying a program or a  file of information.  Common
editing operations include find, move, and  copy.

Electronic Bulletin Board  (BBS) - A system which allows microcomputer users to dial up
and exchange  information without an operator at the  other end.  The BBS allows the
transmittal of computer programs, spreadsheets, and databases, as  well as plain text.

ERCS  -  Emergency Response  Cleanup  Services  consisting  of  removal site  cleanup
contractors.
                                       G-2

-------
 ERT - Environmental Response Team,  a national response team utilized  by the U.S.
 Environmental Protection Agency (EPA), to provide technological  assistance to the EPA
 Regional offices.

 Expendable Materials - Materials that are purchased or used on a  one time basis.

 Extramural Costs - Costs other than  internal EPA costs, including contractors and other
 agencies.

 File -  A collection of bytes, representing a program or data, organized into records and
 stored as a named group on a disk.

 Fixed  Rate -  An EPA audited and approved personnel or equipment rate.

 Flow Chart - A symbolic representation of a computer program sequence.

 Format - The process of preparing a blank  disk to receive information by dividing its
 surface into tracks or sectors.

 G&A Charge - General & Administrative Charge. A charge levied by the ERCS contractor
 to cover general and administrative overhead.  The charge is applied, as a percent, to
 selected services and materials provided by the contractor.

 Hard Copy -  A printout or Listing from a printer.

 Hard Disk • A rigid disk that  stores  large amounts of information.  This type of disk is
 usually permanently installed as part of a computer system.

 Headquarters Hours Percent -  A factor used during cost projection to account for EPA
 headquarters hours.  The default value used by the RCMS is 10% of the direct Regional
 hours.

 Indirect costs • Costs, such as building utilities, clerical and administrative support, and
 office equipment, that are not directly attributable to a particular removal site.

 Input/Output (I/O) - The transfer of information to and from a computer.

 Interface - The boundary between two things, such as the computer and a peripheral.

 Intramural Costs - Internal EPA costs.

 Incident Obligation Log (IOL) - A report generated by RCMS
 to track cumulative costs over any specified period of time during a project.

Kilobyte (K) - 1024 bytes.

Load - The transference of information from a peripheral device to a computer's  main
memory.

Loop -  A group of instructions  that are continually executed, until interrupted.
                                       G-3

-------
 Megabyte (Mb) - 1024 kilobytes.

 Memory - A computer's temporary data storage area.

 Menu •  A list of options, such as add or delete, displayed on the computer screen from
 which the user can choose a course of action.

 Mob/Demob  - A charge for equipment when it is being mobilized or demobilized.  The
 mob/demob rate is expressed as a percentage of the item's regular use rate.

 Modem (Modulator/Demodulator) - A device that transmits digital data (in tones) over a
 phone line.

 Monitor - The device used to display images, (e.g., a display screen).

 MS-DOS •  A widely used disk operating system developed by Microsoft Corporation.

 Peripheral - Any physical device connected to a computer.

 Port • A connection device between a computer and another component such as a printer
 or modem.  For example, a printer cable  is plugged into the printer port on the computer
 so information can be sent to the printer

 Project Scope - A course of action in which  each  step,  or milestone involved has an
 estimated number of days required for completion.

 Prompt -  A symbol used by a  particular software package or program to  let the user
 know that the computer is awaiting instructions or data.

 Provisional Rate - A rate in the ERCS contract for personnel or equipment  that has not
 been  audited or approved by EPA.  Provisional rates are subject to change during the
 definitization process.

 RAM » Random Access Memory. The working space or temporary storage area for the
 program you are using and the document on your screen. RAM is erased when the power
 is turned off.

 Rate Rollover • ERCS equipment items are charged at hourly, daily, weekly, and monthly
 rates depending on the number of days the item is used and is on site.  As the use period
 and total cost to date increase, the item "rolls over" to the next highest rate.

 Removal Cost Management System (RCMS)  •  A software package designed to project,
 track  and summarize costs for a removal  action.

Root Directory •  The first directory on any disk.

Scroll • The movement of the contents of the monitor screen up or down by one or more
lines.   Some word processing packages allow scrolling right or left also.

Site Summary Reports • Reports generated periodically to provide on-going, easy to analyze
cost summary information based on a specific clean-up action.
                                       G-4

-------
Standby Charge - A charge for equipment that is available for use, but not actively being
used.  Standby rates are expressed as a percentage of the item's regular use rate.

Subcontractors - A contractor engaged by the ERCS contractor.

Subdirectories - A directory contained within another directory. Technically, all directories
other than the root directory are subdirectories.

Suspended Days • Days for which an equipment item's rate is suspended, if the item
becomes nonfunctional (see rate rollover).

Technical Assistance Team (TAT)  - A team of field  professionals who  assist with the
technical aspects of a removal action.

TAT Fully Loaded Rate - An estimated hourly rate for TAT personnel that accounts for
the total cost associated with the TAT contract This rate includes salary, per diem, travel,
and overhead.

TAT Professional Level Rate - An hourly rate for TAT personnel based on professional
level (PL).  The rate does not include per diem,  lodging, or travel.

Tractor Feed - An attachment to a printer that allows  for the use of fan-fold continuous
sheet paper.

Use Codes - Codes supplied to RCMS by the user to classify costs according to material,
vendor, service, etc.

Utilities  - A supplemental routine or program designed to carry out a  specific operation,
usually to modify the system environment or perform housekeeping tasks.

Write Protection - A means of giving a disk read-only status  by covering the write-protect
notch (found on the upper right-hand corner of the disk).
                                        G-5

-------

-------
                                            INDEX
Adding contractors
Additional costs
Administrative multiplier
Analytical services
Archive and backup procedure
At cost materials
Await bills
3-5
1-52
1-46, 4-12
1-50, 4-17
Chapter 6
1-29, 3-24
3-26
B
Backup copy

c
6-2
Contingency costs
Contractor code
Contractor daily cost log
Contractor personnel
Cost Projection
       Additional costs
       At cost materials
       Calculate and print
       Contingency costs
       Contractor data
       Contractor equipment file
       Contractor expendable material
       Contractor personnel
       Contractor rates
       Cost projection information
       EPA costs
       EPA non-regional personnel
       EPA regional  personnel
       Exhibit I-A (Cost Projection)
       Extended edit
       Federal and state agency costs
       General project information
       Listed  equipment
       Listed  personnel
       Main menu
       Non-listed equipment
1-54
1-18, 2-5
2-11
1-13, 3-6
Chapter 1
1-52
1-29
1-54
1-53
1-9, 1-13
1-21
1-26
1-13
1-18
1-6
1-40
1-43
1-41
1-55
1-18
1-51
1-6
1-22
1-13
1-5
1-24
                                                   1-1

-------
        Non-listed personnel                                                1-16
        Other costs                                                         1-52
        Personnel rates                                                     1-20
        Project scope                                                       1-6
        Printing options                                                    1-54
        Project contingency factor                                           1-53
        Project scope                                                       1-6
        Subcontractors                                                      1-33
        TAT analytical services                                              1-49
        TAT costs                                                          1-44
        TAT special projects                                                1-48
        Transportation and disposal costs                                     1-35
        Unit rate materials                                                  1-27
        Waste disposal                                              .        1-38
        Waste transportation                                                1-35

Cost Tracking                                                .              Chapter 2
        1099-55 Form                                                      2-9, 2-10
        Additional cleanup contractor              •     .                     2-7
        Archive and backup                                                 2-11
        Contractor Daily Cost Log                                           2-11
       -.Daily Cost Summary                                     .           2-9,2-10
        General site data                                                    2-4
        Incident Obligation Log                                             2-10
       , RCMS utilities                                '          -            2-11
D
Daily cost listing                                                           4-23
Daily Cost Summary                                                .       Chapter 4
        Adjustment and comments                  .             '      •      4-21
      ,  Daily cost listing                                                    4-23
        EPA costs                                                   .       4-4
       .Exhibit IV-A (Daily Cost Summary)                                  4-25
        Exhibit IV-B  (Daily Cost Summary)                                  4-28
        Federal agency costs                                                 4-10
        Other costs                                                         4-19
        Printing options                                                     4-22
        Project ceilings                                                      4-3
        TAT administrative multiplier                                        4-12
        TAT analytical services                                              4-17
        TAT contractor name                                               4-12
        TAT costs                                                          4-11
        TAT personnel                                                      4-13
        TAT rates                                                 .         4-13
        TAT special projects                                                4-16
Decon rate                                                                 3-5, 3-20
Demobilization charge                                                      3-16, 3-18
Definitizaton                                     .                 .         2-1,3-15
Direct costs          '                                                     4-5

                                                   1-2

-------
Dispute flag


E
3-12
Edit/View/Delete
Emergency Response Cleanup Contractor
EPA costs
Expendable materials
Extended edit
1-18, Appendix A
3-3
1-40,4-4
3-1, 3-3
1-18, Appendix A
Federal agency costs
Final bills
Form, 1900-55
        Adding contractors
        At cost materials
        Calculate and print
        Comment and adjustments
        Contractor equipment
        Contractor expendable materials
        Contractor personnel
        Dispute flag
        Exhibit III-A (1900-55 Form)
        Listed equipment
        Non-listed equipment
        Subcontractor file
        Unit rate materials
Fully loaded rate
1-51, 4-10
3-26
Chapter 3
3-5
3-24
3-31
3-28
3-13
3-21
3-6
3-12
3-22
3-14
3-19
3-26
3-22
1-47, 3-11
G&A percentage
General project  information
General site data
1-15, 1-39
1-6
2-4
H
Headquarters hours percentage
1-41
                                                   1-3

-------
Incident Obligation Log                                                     5-1
     Preparing the IOL                                                      5-1
Indirect costs                                                               4-23
Install                                                                      v
Interface data                                                               7-3
List status report                                                            2-3
Listed equipment                                                            1-22, 3-14
Listed personnel                                                            1-16
M   '  :•     :



Mob/Demob                                                     '           1-16


                                                                    i*
N
Non-listed equipment                                                        1-24, 3-19
Non-listed personnel                                                         1-16
o

Other costs                                                                 1-52, 4-19
Personnel rates                                                              1-20
Print Cost Projection                                                        1-54
Print Daily Cost Summary                                                   4-22
Project contingency factor                                                    1-53
Project ceiling                                                               4-3
Project scope                                                                1-6
Provisional rate equipment                                                   1-46, 3-8, 3-16
                                                   1-4

-------
 R
 RCMS utilities
        Prepare archive disks
        Transfer interface data
        Supplemental reports
        Restore data from hard disk
 2-11, Chapter 7
        7-1
        7-3
        7-2
        7-4
 Site Summary reports
 Standby charge
 Subcontractors
 Supplemental reports
Chapter 8
1-23
1-32, 3-26
7-2
TAT administrative multiplier
TAT analytical services
TAT contractor name
TAT costs
TAT personnel
TAT rates
TAT special projects
Transfer interface data
Transportation costs
        4-12
1-49, 4-17
4-12
1-44, 4-11
4-13
4-13
1-48, 4-16
7-3
1-35
u
Unit rate materials
Use codes
Utilities  (see RCMS Utilities)
1-27, 3-22
3-22
w
Waste disposal
Waste transportation
1-35
1-35
                                                    1-5