United States
Environmental Protection
Agency
Office of Air Quality
Planning and Standards
Washington DC 20460
EPA-340/1-83-019
April 1983
.Stationary Source Compliance Series
Envirotech/
Chemico Pushing
Emissions
Control System
Analysis
Final Report

-------
                                            EPA-340/1-83-019
Envirotech/Chemico Pushing Emissions
            Control System Analysis

                       Final Report
                          Prepared by

                          Peter Spawn
                         Michael Jasinski

                        GCA CORPORATION
                     GCA/TECHNOLOGY DIVISION
                       Bedford, Massachusetts
                      Contract No. 68-01-6316
                      Technical Service Area 3
                         Assignment No. 8
                    John R. Busik, EPA Project Officer
                  Laxmi Kesari, EPA Assignment Manager
                          Prepared for

                U.S. ENVIRONMENTAL PROTECTION AGENCY
                  Stationary Source Compliance Division
                      Washington, D.C. 20460
                           April 1983        U.S. Environmental Protection Sgencj
                                         Region 5, Library (5PL-16)
                                         230 S. Dearborn Street, Room 1670
                                         Chicago, XL  60604

-------
                                   DISCLAIMER
     This Final Report was furnished to the U.S. Environmental Protection
Agency by GCA Corporation, GCA/Technology Division, Bedford, Massachusetts
01730, in partial fulfillment of Contract No. 68-01-6316, Technical Service
Area 3, Assignment No. 8, Change No. 1.  The opinions, findings, and
conclusions expressed are those of the authors and not necessarily those of
the Environmental Protection Agency or of cooperating agencies.  Mention of
company or product names is not to be considered as an endorsement by  the
Environmental Protection Agency.
                             CONFIDENTIALITY STATUS
     This report was reviewed by each steel company mentioned herein—
Bethlehem Steel, U.S. Steel, Republic Steel, J&L Steel and Shenango.  No
confidential claims were asserted on any information contained  in  this  report,
                                   PEER REVIEW
     This report was peer  reviewed by  several EPA  personnel,  and  each
individual's comments were addressed by GCA and/or  the Assignment Manager
during preparation of this Final Report.

-------
                                    ABSTRACT
     This report summarizes a 3-month study of the 21 Envirotech/Chemico
one-spot, mobile pushing emissions control systems currently installed at coke
plants operated by five domestic steel companies.  The study investigated;
(1) design differences between cars; (2) startup, operational and maintenance
problems reported by each steel company; (3) mass and visible emissions test
data; (4) car availability; and (5) solutions to operating problems
implemented and/or under consideration.  Information in the report was
developed through detailed discussions and field inspections at four steel
companies; discussions with EPA engineers and review of EPA, state and local
regulatory agency files; office discussions with the equipment vendor; and
review of the technical literature.  The objective of this report is to
factually present information available through the above sources.
                                       111

-------
                                    CONTENTS
Abstract	   ill
Figures	     v
Tables	    vi
Acknowledgment 	   viii

     1.   Introduction	     1
               Project Background and Approach 	     1
               Report Organization 	     2
     2.   Envirotech/Chemico Push Control Car Development and History.     3
               Halcon Car Development 	      3
               Car Orders	      5
               Background and Current Status of Envirotech/Chemico. .      5
     3.   System Description	      9
               Introduction 	      9
               General System Description . 	     12
               Scrubber Car Design and Operation	     13
               Description of H-III Land-Based Hot Water System ...     15
               Description of the H-II Land-Based System	     16
     4.   Emissions Data Summary	     17
               Mass Emissions Data	     17
               Visible Emissions Data Summary 	     17
     5.   Summary of H-III Problems and Solutions Reported by Steel
            Companies	     41
               Introduction 	     41
               H-III Land-Base Problem Summary  	     42
               H-III Quench Car and Coke Guide Problems	     46
               H-III Scrubber Car Problem Summary	     52
     6.   Maintenance Programs and Availability Data	     59
               Maintenance Programs 	     59
               Availability Data	     63

References	     82
Appendices

     A-E  Tables From Trip Reports Listing H-II and H-III System
            Problems Reported by Steel Companies  	     83
      F   Method D:  Procedure for Observing Visible Emissions Equal
            to or Greater than 20% Opacity During Pushing ......    101

-------
                                    FIGURES
Number
   1      Availability data for H-III serving Batteries 1,  2 and 3
             at U.S. Steel/Clairton.   Average shown for 7 months
             operation, March 1981 through December 1981, excluding
             hot idle downtime	     64

   2      Availability data for H-III serving Batteries 7,8 and 9 at
             U.S. Steel/Clairton	     65

   3      Availability data for H-III serving Battery 15 at U.S.
             Steel/Clairton 	     66

   4      Availability data for H-III serving Batteries 19 and 20 at
             U.S. Steel/Clairton	     67

   5      Availability data for H-III serving Batteries 21 and 22 at
             U.S. Steel/Clairton	     68

   6      Availability of all operating H-III systems (combined) at
             U.S. Steel/Clairton  (supplied by U.S. Steel)  	     69

   7      Plant production at Clairton Works (supplied by  U.S. Steel)     70

   8      Availability data for H-III at J&L/Indiana Harbor Works
             (two cars, two batteries)	     71

   9      Availability data for H-III at Republic/Warren (two cars
             serve  one battery)	     72

   10      Availability data for H-II at Bethlehem  Steel's  battery
             No. 5  at Bethlehem (one car, one battery)	     73

   11      Availability data for H-II at Shenango  (one car,  two
             batteries)	     74

   12      Availability data for H-II at J&L/Pittsburgh  Battery  P-4
             (one car, one battery)	     75

-------
                                     TABLES


Number                                                                   Pa6e

   1      H-II and H-III Car Order Summary	     6

   2      Description of Batteries Served by Envirotech/Chemico Push
             Control Systems 	    10

   3      Summary of Particulate Mass Emissions Data For the
             Envirotech/Chemico H-II Push Control Cars	    18

   4      Additional Mass Emissions Data for the Envirotech/Chemico
             H-II Cars	    21

   5      Particulate Mass Emissions Test Data for H-III Cars (Push and
             Travel Combined)	    23

   6      Summary of Visible Emissions Data for the Envirotech/Chemico
             H-II Cars	    26

   7      Summary of Visible Emissions Data for the Envirotech/Chemico
             H-III Cars	    34

   8      H-III Land-Based Hot Water System Problems and Corrective
             Action Taken, as Reported by Companies Visited	    43

   9      Status of H-III Land-Base Problem Resolution  	    47

   10      H-III Quench Car and Coke Guide Problems and Corrective
             Action Taken, as Reported by Companies Visited	    48

   11      Status of H-III Quench  Car and Coke Guide Problem Resolution    51

   12      H-III Scrubber Car Problems and Corrective Action Taken, as
             Reported by Companies Visited  	    53

   13      Status of H-III Scrubber Car Problem Resolution	    58

   14      Maintenance Program Details Obtained From Plant  Visits  ...    60
                                   VII

-------
                               TABLES (continued)

Number

 15       H-II Downtime Reported for Bethlehem/Bethlehem Battery No. 5
             in April and May 1979	   77

 16       H-II Downtime Reported by Bethlehem/Bethlehem Battery No. 5
             in 1980 (entire year)	   78

 17       Monthly Availability Data for H-II on Battery No. 5 at
             Beth lehem/Beth lehem	   79

 18       J&L/Pittsburgh Chemico H-II Breakdown Report Summary for
             2/14/80 - 2/23/81 on Battery P-4	   80

-------
                                 ACKNOWLEDGMENT
     A number of individuals within EPA and the steel industry contributed to
this study.  A high level of cooperation from staff members of each steel
company visited is gratefully acknowledged.  Messrs. T. Maslany, E.
Wojciechowski, R. Ida, R. Craig, R. McCrillis  and D. Hlustick, all with EPA,
reviewed the report, and provided comments which have been incorporated into
this Final Report.
                                      IX

-------
                                    SECTION 1

                                  INTRODUCTION
PROJECT BACKGROUND AND APPROACH

     At the request of EPA1s Division of Stationary Source Enforcement  in
Washington, D.C.  (DSSE), GCA/Technology Division conducted an engineering
•assessment of the 21 Envirotech/Chemico pushing emissions control cars
operated by five  domestic  steel companies.  The study objectives were defined
by EPA as follows:

     •    Investigate design and construction parameters of  the cars;

     •    Investigate startup, operational and maintenance problems
          encountered by each company;

     •    Document  solutions to problems implemented by Envirotech/Chemico  and
          each  steel company;

     •    Review  maintenance programs at each company;

     •    Summarize available mass  and visible emissions test data;

     •    Assemble  data to describe car availability; i.e.,  number  of pushes
          caught  and scrubbed divided by total number of pushes occurring
          during  the same  period.

     The primary  source of information in  this report was office discussions
and  field inspections held between  GCA and four of  the  five  steel companies
that operate Envirotech/Chemico cars.  Office discussions were also held
between GCA and Envirotech's Vice President  and one of  their Project
Engineers.  Bethlehem Steel Corporation declined  to participate in  the  plant
visits due to pending litigation.   Some data for  the Bethlehem plant were
available from  regulatory  agencies.

     Each EPA engineer responsible  for steel mills  in Regions II,  III and  V
 (all Envirotech/Chemico cars are  in these  three EPA regions) was contacted  to
obtain all available information  relative  to study  objectives.  Additionally,
the  technical  literature  including  published and  informal EPA reports were
reviewed, especially for  emissions  test data.

-------
     The overall study objective was to provide a factual reporting of problem
areas and solutions as described to GCA by each steel company.  Two companies,
Republic Steel and Shenango, reviewed GCA's trip reports describing
discussions held at the plants, and their review comments were incorporated
into this report.  Trip report review comments were not  received from U.S.
Steel and J&L Steel.

REPORT ORGANIZATION

     The background and development history of the Envirotech/Chemico push
control cars are described in Section 2.  A process description and status of
each installed system as of Spring 1982 appears in Section 3.  Mass and
visible emissions data appear in Section 4.

     A summary of problem areas described by the steel companies visited
appears in Section 5, based on the detailed trip reports prepared  for each
plant visit.  Section 6 provides available information on car availability and
maintenance programs.

-------
                                   SECTION  2

                      ENVIROTECH/CHEMICO  PUSH  CONTROL  CAR
                            DEVELOPMENT AND HISTORY
HALCON CAR DEVELOPMENT

Early History

     The American Iron and Steel Institute (AISl) commissioned J.E. Allen
Associates in the early 1970s to investigate pushing emissions control
techniques.  The so-called Allen hooded quench car/trailer control car concept
was developed which eventually evolved into the current Envirotech/Chemico
Halcon-II (H-Il) and Halcon-III (H-III) designs.1

     The original concept called for a three-car train consisting of:  (1) a
conventional electric locomotive, (2) an enclosed quench car, and (3) an
equipment (scrubbing) car.  The equipment car was envisioned to contain large
rotating exhaust fans and conventional wet scrubbers.  AISI did not readily
accept this early design concept because gyrational and vibrating effects
inherent to large rotating fans were not considered practical for continuous
shuttle service.

Development of Halcon Car

     The direct forerunner of the current design was developed in 1972 by John
Allen and John Hanley (Hanley-Allen Pollution Control Services) in conjunction
with Interlake Inc.'s technical center and the Aeronetics Division of
Thermotics, Inc.  Interlake suggested that the original concept be redesigned
to use Aeronetic's Adtec static, jet-type exhauster/air cleaner device instead
of conventional fans and scrubbers.  The Aeronetics exhauster, developed
during the NASA program, was operating at a ferroalloy electric furnace at
Chromasco, Inc. in Memphis, TN with apparent success.  Interlake agreed in
April 1972 to finance development and testing of the new concept at
Interlake's Chicago coke plant.

     A prototype unit, termed the Halcon system, was designed and tested  at
Interlake during the summer and  fall of 1973.   Initial tests suggested the
concept was viable but significant difficulties  still existed.  Modifications
to the entrainment separator and quench car design during the winter  of
1973-74 led to a demonstration of the system to  EPA  in November 1974.  In
December  1974, the system became the property of Chemico Air Pollution Control
Corporation which became a division of Envirotech Corporation in 1978.

-------
     Design details of the Halcon prototype demonstrated at Interlake in 1974
appear in a technical paper by R.S.  Patton of Interlake.1  Major design
differences between this prototype and the commercial Envirotech/Chemico H-II
and H-III configurations are as follows:

     •    Flat water sprays were provided in the prototype to curtain the hood
          opening where coke first enters the system.  The commercial version
          does not use water sprays.

     •    Equipment (scrubber) car was not enclosed at Interlake, while the
          commercial installations placed equipment inside an enclosed car.

     •    Interlake prototype was designed to quench coke in hooded quench
          car, eliminating the quench tower.  This concept was eliminated in
          the commercial version, and a conventional quench tower with
          modified water sprays was used.

     •    An electric locomotive was used to propel the Interlake prototype,
          while the existing H-II and H-III cars are self propelled via
          on-board electric motors.

     •    Conventional quench car (not one-spot) on prototype was used with a
          plenum-type hood and exhaust duct.  A one-spot quench car was
          developed by Chemico for  the commercial installations.

Development of the Envirotech/Chemico H-II Car

     After acquiring the Halcon design  in 1974, Chemico further developed the
system into the H-II configuration.  The H-II is described in detail  later  in
Section  3.  Refinements to the Halcon prototype included the following:^

     •    Duplicates of key equipment were added, except  for large and  heavy
          components such as  the diesel generator, water heater  and  separator.

     •    Equipment car was enclosed, pressurized and heated.

     •    Self-powering of control  car  eliminated need  for locomotive and
          reduced overall system  length from  165 to  100 feet.

     •    Onboard sump pumps  were eliminated  by providing  gravity drain of
          dirty  scrubber  water.

     •    Number of wheel trucks were increased to reduce  track  loading.

     •    Diesel generator was  isolated and  soundproofed.

     •    Stainless  steel ducts  and rubber-lined pipe were added.

     •     Integral  cab  and control  room were  air conditioned with  filtered  air.

     •    One-spot  quench car was developed.

     •     Coke guide  hood configuration was  improved.

                                        4

-------
Development of the H-III

     The H-III car was developed in the late 1970s in response to concerns
over fuel oil consumption of the H-1I.  The primary differences between the
H-II and H-III cars are the elimination of the onboard diesel generator and
fuel oil fired hot water heaters (H-Il), relying instead on hot rail electric
power and a land-based water heater designed to fire coke oven gas and water
transfer system (H-III).  Details are provided in Section 3, System
Description.  In discussions with GCA, Envirotech/Chemico emphasized that the
H-III cars were sold and installed without the benefit of a prototype unit
upon which to base final design.

CAR ORDERS

     In November 1975, negotiations between EPA Region III and J&L Steel led
to a commitment by J&L to select a push emissions control system by January
1976.  On 1 February 1976, J&L became the first buyer of the Chemico H-II
system when J&L announced selection of the H-II for battery P-4 at the
Pittsburgh Works.

     Also in 1976, the Pennsylvania DER was engaged in litigation with
Bethlehem Steel relative to pushing emissions at the Johnstown and Bethlehem
plants, among other issues.  In February 1977, Bethlehem Steel ordered four
Envirotech/Chemico H-II cars for the Bethlehem, Lackawanna and Sparrows Point
plants.  By 1978,  26 cars were sold; however, the last five car orders placed
by Bethlehem Steel were cancelled before car delivery.

     Table 1 summarizes H-II and H-III car orders as described by
Envirotech/Chemico.

BACKGROUND AND CURRENT STATUS OF ENVIROTECH/CHEMICO

     The Halcon system was acquired from John Hanley by Chemico Air Pollution
Corporation in December 1974.  At that time, 15 to 20 Chemico staff members
were assigned to the task of commercializing the prototype system demonstrated
at Interlake.  In February 1975, John Hanley, the co-developer, became an
independent representative of Chemico.  Mr. Hanley was involved in development
work, and later, marketing and car startup.

     Chemico became a division of Envirotech Corporation in 1978.  Mr. Anthony
Fazio,  the current (1982) Envirotech Vice President, became involved with the
program in April 1978.  By the summer of 1978, 200 Envirotech/Chemico
employees were working on the project, of which about 75 were employed in
Envirotech/Chemico1s assembly shop.  (Some construction was subcontracted to
other organizations.)

     In January 1980, Envirotech/Chemico announced they were withdrawing from
the pushing emissions control market and no new orders would be accepted.  The
company announced  they would continue to fulfill existing contract obligations.

-------
TABLE 1.  H-II AND H-III CAR ORDER SUMMARY
Company
J&L/Pittsburgh (P4)a>b
Bethlehem/Bethlehem (No. 5)
U.S. Steel/Clairton (Nos. 19,20)
Bethlehem/Lackawanna (Nos. 7,8)
Bethlehem/Sparrows Pt.
(Nos. 11,12)
Shenango/Neville Island
Republic/Warren (No. 4)
U.S. Steel/Clairton (Nos. 21,22)
Bethlehem/Bethlehem (Nos. 2,3)
J&L/Ind. Harbor (Nos. 3,4)
Republic/Youngstown (Nos. B,C)
U.S. Steel/Clairton (Nos. 1,2,3)
No. of
cars
1
1
1
1
1
1
2
1
1
1
1
1
Type
H-II
H-II
H-II
H-II
H-II
H-II
H-III
H-III
H-II
H-III
H-III
H-III
Order
date
2-76
2-77
3-77
4-77
4-77
9-77
10-77
1-78
2-78
2-78
6-78
6-78
Delivery
date
10-77
9-77
5-79
6-79
6-79
9-79
7-79
9-79
12-79
12-79
9-79
11-79
Chemico
job
No.
3014-W
3086-W
309 3-W
3100-W
309 7-W
3121-W
3124-W
3154-W
3150-W
3152-W
3124-Y
3154-W
Assembly
location
Buell
Atlas
Buell
Buell
Buell
Buell
Niles
Niles
Atlas
Niles
Niles
Niles
Frame
builder
Atlas
Atlas
Easton
Maxson
Max son
Maxson
Atlas
USS
Atlas
Maxson
Atlas
USS
                (continued)

-------
                                               TABLE 1 (continued)
Company
U.S. Steel/Clairton (Nos. 13,
14,15)
Republic /Cleveland (Nos. 6,7)
J&L/Ind. Harbor (No. 9)
U.S. Steel/Clairton (Nos. 19,20)
Beth lehem/Lackawanna (No. 9)
U.S. Steel/Clairton (Nos. 1,2,3)
U.S. Steel/Clairton (Nos. 7,8,9)-
Bethlehem/Bethlehem
Bethlehem/Sparrows Pt. (Nos. 1,
2,4,5)
No. of
cars
2
2
1
1
lc
1
1
lc
30
Type
H-III
H-III
H-III
H-III
H-II
H-III
H-III
H-II
H-II
Order
date
11-78
11-78
2-79
2-79
2-79
4-79
5-79
6-79
6-79
Delivery
date
1-80
3-80
2-80
3-80
12-80
6-80
6-80
1-81
3-81
Chemico
job
No.
3154-W
3198-W
3152-W
3154-W
3219-W
3154-W
3154-W
-
323-1
Assembly
location
Niles
Niles
Niles
Niles
-
Niles
Niles
-
™"
Frame
builder
USS
Morgan
Maxson
USS
-
USS
USS
Maxson
Maxson
aBatteries served shown in parenthesis.




bH-II on P-4 replaced with Minister Stein in 1981.




cCancelled orders; cars never completed.

-------
     In 1981, General Electric Company purchased ongoing business of the
Chemico and Buell Divisions of Envirotech Corporation in order to enter the
pollution control equipment market.   However,  the new company, General
Electric Environmental Services Inc. (GEESl) does not have responsibility for
the push control project according to Mr. Fazio, Envirotech Vice President,
and a Project Engineer, Mr. Sandor Kaldor who were the only two personnel
assigned to the project in 1982.  Messrs. Fazio and Kaldor continue to work
out of GEESI's New York offices in order to complete Envirotech/Chemico1s push
control car contracts.

-------
                                   SECTION  3

                               SYSTEM DESCRIPTION
INTRODUCTION

     Background data describing each battery served by an H-II or H-III system
appears in Table 2.  The basic operating principles of the scrubbing system
are equivalent between the H-II and H-III cars since each design uses the
Aeronetics hot water scrubber.  The primary differences between the H-II and
H-III systems are as follows:

     •    The H-II has an on-board hot water heater, while the H-III cars
          receive hot water from a land-based heating system.

     •    The H-II has an on-board diesel AC generator to power scrubber
          system equipment and the traction drive motors.  The H-III is
          powered by DC current drawn from battery hot rails.

     •    The H-II is substantially heavier than the H-III due to the above
          differences.

All H-III systems were originally designed to use coke oven gas (COG) in the
land-based heating building to heat hot water, except at Clairton.  The
Clairton system uses plant steam heating in lieu of COG heaters.  Water
treatment systems for land-based removal of solids were supplied to all steel
companies as part of the Envirotech/Chemico package, except at Clairton where
U.S. Steel provided their own water treatment facilities.

     Coke guide hoods and one-spot quench cars are essentially identical
between the H-II and H-III systems, except for minor design changes made prior
or subsequent to startup.

     Envirotech/Chemico indicated to GCA that design and construction details
of each H-II and H-III system were essentially identical.  Scrubber car
frames, wheel truck assemblies, and the basic cab structure were purchased
from suppliers by Envirotech/Chemico with the exception of the eight Clairton
cars.  U.S. Steel built their own frames and operator's cab structures for
Clairton and Envirotech/Chemico installed the internal equipment.  For all
other H-II and H-III cars, Chemico or their subcontractor(s) built the system
internals into the purchased car frames and wheel assemblies.  All single-spot
quench cars were built to Envirotech/Chemico"s specifications by
subcontractors except for the Clairton quench cars which were designed and
built by U.S. Steel.

-------
TABLE 2.  DESCRIPTION  OF  BATTERIES  SERVED BY ENVIROTECH/CHEMICO  PUSH CONTROL SYSTEMS'
No. of
cars
1
2
1
1
1
1
1
2
2
1
18
Facility/
location
Bethlehem Steel
Bethlehem, PA
Bethlehem Steel
Bethlehem, PA
Bethlehem Steel
Lackawanna, NY
Bethlehem Steel
Sparrows Pt. , MD
J&L Steel/
E. Chicago, IN
J&L Steel
E. Chicago, IN
J&L Steel
Pittsburgh, PA
Republic Steel
Cleveland, OH
Republic Steel
Warren, OH
Republic Steel
Youngstown, OH
Shenango Inc .
Neville Isl. , PA
Battery
served
Nos. 2,3
No. 5
No. 7
No. 8
No. 11
No. 12
No. 4a
No. 9a
P-4C
No. 6
No. 7
No. 4
B
C
No. 3f
No. 4
Most recent
Battery battery
startup rehabilitation
date date
1941
1942
1953
1952
1961
1955
1957
1956
1961
1953
1952
1952
1979
1950
1960
1948
1951
-
1977 (rebuilt)
1979 (rebuilt)
-
1976b
1979b
1977b
1979d
1981d
-
1962 (rebuilt)
1971-19726
1974-19756
Battery
design
Koppers-Becker
Koppers-Becker
Koppers-Becker
Wilputte
Wilputte
Koppers-Becker
Koppers-Becker
Koppers-Becker
Koppers-Becker
Koppers-Becker
Koppers-Becker
Koppers-Becker
Koppers
Koppers
Koppers
Koppers
Koppers
Battery Total
heating number
system of ovens
Gun-flue
Gun-flue
Gun-flue
Underjet
Underjet
Underjet
Underjet
Underjet
Underjet
Underjet
Gun-flue
Gun-flue
Gun-flue
Gun-flue
Gun-flue
Underj e t
Underjet
102
80
7b
76
65
65
75
87 '
79
63
63
85
65
59
35
35
Oven height
3-meter
4-meter
(12 ft. -6 in.)
12 ft. -2 in.
4-meter
13 ft-0 in.
13 ft-0 in.
13 ft-0 in.
13 ft-2 in.
(4-meter)
13 ft-0 in.
(4-meter)
13 ft-2 in.
(4-meter)
4-meter
Number of
pushes per Tons of
day (all coke per
units listed) push
? :
96 (avg.) 11
210 11
143 11
105 i:.l
110 11. i
(116-max)
111 ?
126 11.7
(174-max)
110 12.7
(120-max)
120 11.5
(144-max)
808 15
                                           (cont inued)

-------
                                                       TABLE 2  (continued)
                                               Most recent                                                          Number of
                                      Battery    battery                      Battery    Total                      pushes per     Tons of
No. of     Facility/        Battery    startup rehabilitation     Battery      heating    number                     day  (all      coke per
 cars      location         served      date       date         manufacturer   system    of ovens     Oven height    units  listed)     push
2

1

2

2

1

U.S. Steel
Clairton, PA
U.S. Steel
Clairton, PA
U.S. Steel
Clairton, PA
U.S. Steel
Clairton, PA
U.S. Steel
Clairton, PA
Nos.

Nos.

No.

No.
No.
No.
No.
1,2,3

7,8,9

15

19
20
21
22
1955

1954

1953

1951
1951
1947
1946
1979h

-

1979 (rebuilt)

1977
1978 (rebuilt)
1972b
19731
Wilputte

Koppers

Koppers

Koppers-Becker
Koppers-Becker
Koppers-Becker
Koppers-Becker
Gun- flue

1

?

Underjet
Underjet
Underjet
Underjet
192

192

61

87
87
87
87
13 ft-0 in.

4-meter

4-meter

5-meter
5-meter
5-meter
5-meter
240 11.3

? ?

? ?

171 14.5

201 14.4

aBattery No. 4 pushed empty in October  1981, Battery No. 9 pushed empty in March 1982.

^End-flue rehabilitation.

cH-2 car was permanently removed  from service July 3, 1981.

dEnd-flue, and some through-wall  rehabilitation.

eEnd-flue, and some end-wall rehabilitation.

fBattery No. 3 scheduled for replacement with new 56 oven battery in June-July 1982.  H-II car will then serve only Battery No. 4 (shed on
 new battery).

^System designed for three battery  operation (Nos. 1, 3 and 4)—total of  105 ovens, 140 pushes/day.

hPartial rehabilitation (standpipes, doors, etc.)

'•Complete rebuild from the bench  up.

-------
     Although both Envirotech/Chemico and the steel companies visited reported
all cars are identical, several minor differences were noted by GCA during
plant inspections.  The impact of the following differences on car reliability
is further described later in Section 5.

     •    The U.S. Steel-supplied car frames at Clairton, and Republic's
          Warren car (all H-III) use wooden power pick-up arms.  The cars
          supplied to J&L at Indiana Harbor use a steel pickup arm arrangement.

     •    The U.S. Steel-supplied scrubber car and quench car frames at
          Clairton, and the two cars at Republic/Cleveland were supplied with
          "stucki bearings".  The other, Chemico-supplied car frames at plants
          visited by GCA used solid wear plates instead of stucki bearings.

     •    GCA was informed by Envirotech/Chemico  that minor changes were made
          by Envirotech/Chemico during  car production.  Some changes were  also
          made based on field experience with  systems already on-line.  Other
          minor differences may have resulted  from the  fact that cars were
          assembled at several different locations.

     •    All systems have been modified by each  steel  company, accounting for
          additional minor differences.

Design and operation details are discussed below, drawn primarily from a
Chemico paper published in Iron and Steel Engineer magazine.^  Differences
between H-II and H-III systems are also described.

GENERAL SYSTEM DESCRIPTION

     Both H-II and H-III systems consist of a  control car that houses
scrubbing equipment, a one-spot, enclosed quench  car, a hooded coke guide  and
a  land-based water treatment and transfer station.  The heart of the scrubber
car  is the Aeronetics hot water scrubber which also provides the draft for gas
movement.  The H-II scrubber car contains an AC diesel  generator to power
on-board equipment, and an oil-fired hot water heater to supply the Aeronetics
scrubber jets.  The H—III cars are powered by  DC  current from bench—mounted
hot  rails, eliminating the onboard diesel generator.  Additionally, the H-III
draws hot water from a land-based heating and  transfer  system, eliminating the
on-board heater used on the H-II.

     For both H-II and H-III systems,  a one-spot  enclosed quench car travels
with the scrubber  car.  The tilting  stainless  steel coke box  (original
Chemico-supplied coke  boxes were stainless  steel) is  enclosed  on three  sides
and  the top  to contain emissions.  The side  facing the  oven  is partially  open
to receive coke.   After the push, quench water is introduced  through this
opening via  modified quench tower nozzles.

     Closure plates added  to the plant's existing coke  guide  on both sides of
the  coke discharge opening align with  the quench  car  opening  to contain
emissions.   Other guide modifications  in the H-II and H-III design close  small
openings on  both  sides,  the  top and  the bottom of the guides.
                                        12

-------
     A land-based water treatment system and gravity feed transfer system
supply cold (or slightly heated) water to the H-II.  The H-III receives
heated, pressurized water from a land-based heating and transfer station.
Quench tower portals (openings) and water spray nozzles usually required
modifications to accomodate the one-spot quench cars.  The water treatment
system processes the raw water supply to a quality level required by  the
scrubber.  Scrubber water is blown-down from the car at the quench tower and
discharged to plant wastewater handling systems.

SCRUBBER CAR DESIGN AND OPERATION

     Basic scrubbing functions are similar for the H-II and H-III cars.  Two
Aeronetics jet nozzles operating in parallel receive 400°F, 400 psi water  from
the onboard storage tank on the H-III, and either from an onboard storage  tank
or directly from the onboard heater on the H-II.  The nozzles exhaust  gas  from
the coke guide hood and quench car, through the scrubbing section, into an
entrainment separator and out a short, rectangular, vertical stack at  the  same
elevation as the battery top level.

     A temperature sensor upstream of the Aeronetics jets controls hot water
flow to the jets, thus regulating exhaust flowrates.  The system was
originally designed to operate at approximately 60,000 scfm during a  "normal"
push, with up to 90,000 scfm available for green pushes.  Quench sprays in  the
duct between the quench car and the scrubber car were designed to prevent
excessive temperatures during very green pushes.  Exhaust flow is
automatically reduced to 35,000 scfm during travel to the quench tower.

     As designed, approximately 40 to 50 percent of the water supplied to  the
Aeronetics jets evaporates.  The remaining water is removed in the
multicyclone entrainment separator.  Dirty water drains by gravity at  the
quench tower.

     The scrubber car consists of two integrated sections on both the  H-II  and
H-III, an operators cab and the equipment room.  The entire scrubber  car is
air conditioned and pressurized to prevent dust entry.  The H-II is propelled
by two 150-hp, DC traction drive motors mounted on wheel trucks under  the
scrubber car.  DC from hot rails can be used for emergency movement of the
H-II in the event of generator failure.  The H-III is propelled by four 75-hp
DC traction drive motors, supplied with DC current from hot rails mounted
along  the battery bench.  The H-III cannot propel itself if DC power  is lost.

Onboard Equipment - H-II and H-III

     The scrubber car houses all AC starters, DC contactors, switch gear,
overload protection devices, relays, programmable control devices and  a
rectifier.

     Two onboard rotary air compressors (one operating, one spare) rated at
125 cfm and 100 psig discharge pressure provide air for the brakes,
instruments and in the case of the H-II only, fuel atomization in the  water
heater.  Brake and instrument air is cooled; only instrument air is dried  via
a water separator and twin-tower, regenerative air dryer.


                                      13

-------
     Two onbbard hydraulic pumps (one operating, one spare) provide pressure
for the twin hydraulic dump cylinders that tilt the coke box for dumping to
the wharf.  The prime hydraulic pumps and air compressors are AC powered.  On
some li-II and H-III cars, the spares are L)C powered so if one power source
fails, the other maintains braking and coke box dump capability.  (The U.S.
Steel quench cars use air cylinders to empty the coke box; all
Envirotech/Chemico-supplied quench cars use hydraulic cylinders).

     Programmable controllers consisting of banks of removable, printed
circuit boards control car sequence operations, i.e. , the scrubbing cycle and
safety interlocks.  For example, the car was designed so the car won't move
when the coke box is in the dump position, hot water transfer won't occur
unless the car is properly aligned at the charge station, etc.

     The onboard AC diesel generator on the H-II cars is rated at 400 kw
prime, and provides 460V, 3-phase, 60 Hz power at 1200 rpm for scrubbing
system equipment.  The standard 400 kw generator can move the scrubber car
with gas cleaning equipment turned off if DC hot rail power is lost.
Envirotech/Chemico also offered a 600 kw generator capable of scrubbing and
moving the car simultaneously, eliminating the need for hot rail power.

     The water heaters in the H-II cars are fired with No. 2 fuel oil and
sized at 8, 10 or 12 mm Btu/hr depending on length of duty cycle (i.e.,
elapsed time between pushes).  The larger heater sizes fill much of the
available space inside the H-II car.

     After the scrubbing section, scrubbing liquor and particulate are removed
from the exhaust gas in a two-chamber entrainment separator.  Exhaust gas
first enters an open chamber in the separator where the gas decelerates and
water droplets and particulate drop out by contact with internal surfaces.
The gas then enters a bank of small cyclones in the second section of the
separator for final gas/liquid separation.  Design pressure drop across the
entire separator at maximum exhaust gas flow is 8 in. WC.

Exhaust Flow Rate Selection

     The  6 to 9 inch gap between the coke guide closure plates and the quench
car was selected to handle elevation differences between  the  track and ovens.
No  sealing material was originally envisioned  for this 6  to  9  inch gap,
although  some steel companies have attempted to find a suitable  sealing
material.  A seal was provided by Envirotech/Chemico for  at  least one system
(Shenango).

     Exhaust flow rate selection was based on  achieving adequate  fume capture
and maintaining combustion of volatiles and  fixed carbon  contained in  the
exhaust stream.  Design  intake velocity at the  6 to  9  inch gap between  the
coke guide closure plates and  the quench  car opening is  20,000 fpm at  the
maximum design  flowrate  of 90,000 scfm.   Chemico selected  this  indraft
velocity  to contain emissions based  on  the Interlake prototype and  fume
capture design  principles.

-------
     Maintaining combustion of volatiles and fixed carbon provided another
basis for design flowrates.  Envirotech/Chemico reports that discussions with
coke oven experts indicated that 10 Ib of fixed carbon and 5 Ib of volatile
matter per ton of coke are typically evolved.  The total amount of air
necessary for complete combustion was determined stoichiometrically at 60,000
scfm for a 30-second push duration.  A maximum design flowrate of 90,000 scfm
was selected to handle green pushes.

Aeronetics Scrubber Details

     The jet ejector effect of expanding water through the Aeronetics nozzles
transfers momentum from the water to the gas, thereby increasing gas pressure.
This provides a particulate removal capability that Chemico reported to be
equivalent to a venturi scrubber operating at over 100 inches WC pressure
drop.  Because of the momentum transfer, the Aeronetics scrubber only has to
overcome duct and separator pressure drops of approximately 12 in WC.

     Scrubbing efficiency  is proportional to water velocity and droplet size.
The greater the velocity difference between  the water and particulate, and  the
more droplets available, the higher the  scrubbing efficiency.  The water
velocity is dependent on hot water  temperature (and pressure), i.e., higher
velocities (and better scrubbing) are achieved with hotter water and
pressure.  Also, finer droplets are formed with higher water velocity,
enhancing scrubbing efficiency.  The H-III system has interlocks to prevent
hot water transfer to the  car if temperature and pressure are  too  low, thus
maximizing control device  efficiency.

DESCRIPTION OF H-III LAND-BASED HOT WATER SYSTEM

     The Envirotech/Chemico-supplied land-based equipment for  the  H-III system
consists of a water treatment system, hot water heaters and storage  tanks,  and
the  transfer mechanism which  feeds  hot water to the control car.   (The only
exception is Clairton Works where  U.S. Steel provided water treatment.)

      Incoming river or  lake water  is filtered  to  remove  suspended  solids,
softened to remove hardness,  and chemically  treated.  Chemical treatment
consists of:  (a) oxygen  scavenging; (b) dispersant addition  to  prevent
scaling  in  the heat exchanger;  and  (c) corrosion  inhibitor  addition  to protect
all  steel components.  Treated  water,  stored in a  service water  tank,  is
pumped  into the  heater  system via  one  of two high  pressure  pumps  that
maintains system pressure.  A portion  of the water passes  through  the  heater;
a by-pass picks  up heat  from  the charge  tank cooling  loop.  Both streams  are
mixed  and discharged  to a  4400  gallon  hot water charge  tank located  in  the
 transfer building.  When  the  charge tank is  full,  flow  through the heater
stops  and the heater  goes  into  a low fire,  "soak" mode.

     When full,  charge  tank water  is at  460°F  and  the  equilibrium vapor
pressure  is 467  psig.   The pressure differential  between the  land-based  charge
tank and  the H-III car  tank  provides  the driving  force  for  water transfer to
the  car.  Prior  to entering  the H-III, water from the  charge  tank is cooled to
approximately 430°F  in  a  second tank containing a  shell  and tube heat


                                        15

-------
exchanger.  This is necessary to prevent flashing in the transfer line since
water in the charge tank is at its equilibrium vapor pressure.  The system was
designed to transfer water to the car every other quench (push) cycle.

     Hot water transfer is accomplished during quenching when the H-III car is
aligned with the transfer station located at the side of the transfer
building.  The charge arm on the car extends outward and mates with a nozzle
on the transfer building.  A number of limit switches must be satisfied by
precise charge and alignment before transfer can occur.  The transfer line is
pressurized with water from the land-base cooler tank, and isolation valves on
either side of the coupling open to allow water transfer.  After transfer, the
isolation valves vent and drain the coupling prior to disengagement.

     Vapor pressure in the car tank provides the driving force for water  flow
through the jets when the jet isolation valves are opened.  When full, car
tank water is at approximately 430°F and 366 psia.  To prevent flashing in the
line between the jets and the car tank, water flows through a heat exchanger
for subcooling prior to entering the jets.

DESCRIPTION OF THE H-II LAND-BASED SYSTEM

     The H-II land-based system is simple relative to the H-III land-base
because the water is unheated and unpressurized when transferred to the car.
The H-II water treatment system discharges to an overhead storage tank near
the quench tower.  Cold or slightly preheated scrubber water fills the H-II
during the quench via a simple gravity flow arrangement.
                                      16

-------
                                    SECTION  4

                             EMISSIONS DATA SUMMARY
     This section summarizes mass and visible emissions (VE) data available
through regulatory agencies.  When available, information useful for
interpreting test results is included herein; i.e., coking time, VE observer
position and observation techniques, deviations from test procedures and
problems.  However, it is important to note that background information was
often not available in the test reports.

MASS EMISSIONS DATA

     Mass emissions data available for H-II cars appears in Tables 3 and 4.
Mass data for the H-III cars appears in Table 5.  Generally, pushing and
travel emissions were measured together.  Front-half and back-half catches
were reported for most H-II tests, while only front-half data were reported
for the H-III cars.  Additionally, it should be noted  that all  front-half
results for both H-II and H-III cars were performed in accordance with EPA
Reference Method 5.  Back-half analysis must be performed in accordance with
the requirements of the Pennsylvania Department of Environmental Resources
(PADER) for all H-II and H-III cars located in the State of Pennsylvania.  All
mass data were drawn from stack test reports unless otherwise noted.
Information contained in test reports pertinent to interpreting test results
appear in the comments section of each table, if available.

VISIBLE EMISSIONS DATA SUMMARY

     Available VE data for emissions escaping capture  by the hot car - coke
guide hood assembly appears in Tables 6 and 7 for the  H-II and  H-III,
respectively.  Most data were collected by recording the number of seconds of
VE >20 percent opacity escaping the hood during the push using  a cumulative
stopwatch.  A typical methodology appears in Appendix  F.  Unless otherwise
noted, all data represent emissions during the push itself, defined as the
time period between start of ram movement and the time all coke is in hot car.

     The background used for observing VE is listed in the comments section  if
this information was available.  Most of the VE data were compiled from  test
reports or letters and reports to regulatory agencies  from steel companies.
Often, data describing the observation background (i.e., sky, collector main,
battery) were not available.  The table headings vary  somewhat  between pages,
reflecting the different types of VE data summaries available from EPA.
                                        17

-------
                            TABLE  3.  SUMMARY OF PARTICULATE MASS EMISSIONS DATA FOR THE
                                      ENVIROTECH/CHEMICO H-II PUSH CONTROL CARS
                                 Exhaust flow
                                  rate mea-
                                 sured during
                                    push3
        Push and travel
      emissions, combined
r acuity/
location
Bethlehem Steel/
Bethlehem, PA
Battery No. 5
iest 	
date(s) ACFM
7/27/78
8/15/78
8/16/78
	 i«ront— nair
°F (gr/dscf)
0.043
0.034
0.017
Da.CK.-na.il.
(gr/dscf)
0.038 ^
0.036
0.015 J
Comments
1 • Tests by Bethlehem Steel
S» Particulate exiting the cyclonic
' separator noted by test crew.
oo
                        8/30/78
152
153
                        10/11/78  120,700  151

                        10/12/78  120,700  150

                        10/26/78  100,000  147

                        10/27/78  105,000  150
0.0327
0.0226
       0.051

       0.031

       0.021

       0.026
0.0305
0.0445
            0.058
            0.083
 • Tests by Buell

   Modifications by Buell (before these
   tests) included false bottom to
   prevent creeping of separated
   water.

 • Tests by Buell during the following
   modifications:  stabilizing system
   pressure cycling and modifying
\  heater controls to allow higher
   water temperature and prevent
   local pipeline flashing.
                                                    (continued)

-------
                                             TABLE 3 (continued)
       Facility/
       location
 Test
date(s)
                               Exhaust  flow
                                rate mea-
                               sured during
                                  pusha
ACFM
                          Push  and  travel
                        emissions,  combined
—  Front-half  Back-half
 °F  (gr/dscf)   (gr/dscf)
                                                    Comment s
   Bethlehem Steel   11/1/78   105,700   148     0.0318
   Bethlehem, PA
   Battery No. 5     11/2/78   116,900   150     0.017
                     11/3/78   123,500   150     0.013
\e>
                     11/14/78  107,000   151     0.0206
                     11/15/78   99,500   149     0.0144


                     1/16/79   122,000   139     0.0424

                     1/17/79   132,000   127     0.0316

                     1/18/79   122,000   107     0.0274
                                     0.037

                                     0.057


                                     0.041
                                     0.104
                                     0.103
                                    • All following tests after above
                                      mentioned changes made.

                                    • Tests by Buell with unheated probe
                                      (11/1/78).

                                    • Tests by Buell with two high
                                      pressure pumps to scrubber nozzles
                                      operating simultaneously
                                      (11/2-3/78).

                                    • Each test consisted of ~15 push-
                                      travel cycles per run.

                                    • Tests by Buell

                                    • Each test consisted of ~15 push-
                                   1   travel cycles per run.

                                    • Stopcock grease noted in back-
                                      half samples  (first time checked).

                                    • Tests by Betz-Converse-Murdoch

                                    • Results questionable according to
                                      test report.
                                                 (continued)

-------
                                             TABLE 3 (continued)
                               Exhaust  flow
                                rate mea-
                               sured during
                 Push and travel
               emissions, combined
Facility/
location
pusu
date(s) ACFM

°F (gr/dscf)
Back-half
(gr/dscf)
Comment s
   Bethlehem Steel,   3/7/79
   Bethlehem,  PA
   Battery No.  5
                     3/8/79

                     3/9/79
to
O
126,000  150    0.0423


122,000  150    0.0295

122,000  150    0.0319
0.079
0.100
• Compliance tests by Betz-Converse-
  Murdoch.

• Each test consisted of 16 push-
  travel cycles per run.  Average
  coking time = 20 hours.  Approxi-
  mately 11.3 tons coke pushed per
  oven.

• No detectable stopcock grease in
  back-half.
   *Test data at saturated conditions.

-------
TABLE 4.  ADDITIONAL  MASS EMISSIONS DATA FOR THE ENVIROTECH/CHEMICO H-II CARS
Push emissions
Exhaust
Facility/ Test Front-half flow rate, Temp.
location date(s) (gr/dscf) acfm °F
Bethlehem Steel/ 10/13-17/ 0.016
Sparrows Ft., MD 1980
(Batteries 11
and 12) 0.008* 134,029 150


0.011 128,275 148




0.010 133,145 153






J&L Steel/ 8 - 9/ - 166,646 149
Pittsburgh, PA 1979
Battery P-4
159,993 149

164,868 151
163,517 154

173,580 142

178,792 125
190,963 140
Travel emissions Push and travel combined
Exhaust
Front-half flow rate Temp. Front-half Back-half Full-train
(gr/dscf) acfm °F (gr/dscf) (gr/dscf) (gr/dscf)
0.025 - - (0.0154 lb/
ton coke)

0.013 43,660 143 (0.0140 lb/
ton coke)

0.018** 44,754 143 (0.0179 lb/
ton coke)



0.016 58,362 143 (0.0179 lb/
ton coke)





85,385 145 0.0855 0.0158*


100,827 146 0.0373 0.0110

98,344 147 0.0210 0.0059
98,466 150 0.0187 0.0063

100,666 139 0.0253 0.0425

88,619 122 0.0234 0.0354
92,856 138 0.0209** 0.0405**

Convents
• Compliance tests by Bets-
Converse-Murdoch.
• First run conducted over I days.

• 48 pushes per run, 532. S cons
coke pushed/test run tnassd or.
11.1 tons coke/oven).

• *Percent Lsokinetics = 1..1.0-+.
• **Percent isokineti<-s * U0.92.
• Allowable concentration v:xish) =
0.015 gr/dscf.

• Allowable concentration ^travel)
= 0.010 gr/dsc£.
• Allowable emission rate vpusn
and travel combined) = 0.015 lb>'
ton coke pushed.
• Compliance tests by Betr-
' Converse-Murdoch.

• Each test consisted of If push-
travel cycles per run.

• *Back-half results represent
back-naif catch minus Jack-naif
sulfates. Back-half sulfates
ranged from 0. 0000-0. Oi*J
gr/dscf.
• **Percent isokinetics = J9.o5.
                                        (continued)

-------
                                                                    TABLE  4  (continued)
           Facility/
           location
                                            Push  emissions
                                                                        Travel emissions
                                                                                                     Push and  travel combined
                     Test
                    date(s)
                       Exhaust                        Exhaust
          Front-half  flow rate  Temp.    Front-half   flow  rate, Temp.   Front-half  Back-half  Full-train
          (gr/dscf)     acfm       °F    (gr/dscf)      acfm        °F    (gr/dscf)   (gr/dscf)  (gr/dscf)
                                                                                                                                               Comments
S3
S3
        Shenango,  Inc./
        Neville Is.,  PA
        Batteries  3
        and 4)
U.S. Steel/
Clairton, PA
(Batteries 19a
and 20)
                   2/10-13/
                   1981
08/30/79

09/05/79


09/06/79
                         08/23/79
                         08/29/79
                         08/31/79
82,844  (dscfm)

81,276  (dscfm)


80,043  (dscfm)
                                          77,630  (dscfm)
50,148  (dscfm)   0.061

50,892  (dscfm)   J.015


49,371  (dscfm)   0.091
                                                     51,092  (dscfm)    0.032

                                                                       0.056
3.144

0.593


1.078
                                                                                                            0.286
                                                                                                     0.955

                                                                                                     2.200
                                                                                             0.0194* -\


                                                                                             0.0234

                                                                                             0.0098
3.205

0.608


1.169
                                                                                                                       0.310
  • Compliance tests  by  Betz-
    Converse-Murdoch.

  • First run consisted  of  48  push-
    travel cycles,  remaining two
    runs consisted  of  24 push-travel
    cycles per test.

  • First run isokinetics »  115.+1

  • *Full-train results  consist of
     front-half, and filterable
     back-half catch.

  •  Allowable concentration (push-
     travel combined)  »  0.020
     gr/dscf.

  • Compliance tests by  U.S. Steel.

  • 1st  and 3rd  run consisted  ot 24
    push-travel  cycles per test
    run,  2nd  run consisted of  <»8
    push-travel cycles.

  • Allowable  tull-train  = 0.020
    gr/dscf (July 10,  1979 Consent
    Decree) .

  • Additional  tests conducted by
    U.S.  Steel.

  • 1st  run isokinetics = 75.5*.

\» 2nd  run isokinetics = 124.5*.

    1st  and 2nd runs consists of Z~
    push-travel cycles per test
    run,  3rd run consisted of  13
    push-travel cycles.
        Car also tested in April 1980;  results were not available.

-------
           TABLE  5.   PARTICULATE MASS  EMISSIONS TEST DATA FOR H-III  CARS  (PUSH AND  TRAVEL COMBINED)
                    Facility/Location
                      Test       Front-half   Front-half
                     date(s)      (gr/dscf)    Ib/ton coke
                                                                                                  Comments
<*>
                    JiL Steel/          04/30/81
                    E. Chicago,  IN
                    (Battery 4)         05/01/81
J&L Steel/
E. Chicago,  IN
(Battery 9)
                    Republic Steel/
                    Cleveland,  OH
                    (Batteries  6&7)
                    Republic Steel/
                    Cleveland,  OH
                    (Batteries  6&7)
05/05/81


11/06/80

01/20/81

03/17/81

03/25/81

03/26/81



3/27/81


04/07/81


04/08/81



04/09/81


04/14/81


04/15/81



04/16/81
0.025

0.066



0.105


  NA

  NA

  NA

0.012

0.024



0.032


0.014


0.019



0.017


0.012


0.011



0.015
0.040

0.099



0.158


0.080

0.093

0.052

0.024

0.040



0.068


0.026


0.032



0.028


0.020


0.021



0.027
                                                              Compliance tests run by Betz-Converse-
                                                              Murdoch.
                                                              Each run  consisted of 24 push-travel cycles
                                                              per test  run,  12 tons coke per push, and
                                                              288 tons  coke  per test run.

                                                             i Allowable front-half emission rate (push and
                                                              travel combined) = 0.040 Ib/ton coke.
                                                                                • No additional data available
                                                            • Complaince tests  run by Betz-Converse-
                                                              Murdoch.
                                                            • Each run consisted  of  24 push-travel cycles
                                                              per test run,  12  tons  coke per push,
                                                              288 tons coke  per test run.

                                                            • Allowable front-half emission rate (push and
                                                              travel combined)  =  0.040 Ib/ton coke.

                                                            • Compliance tests  run by Betz-Converse-
                                                              Murdoch on car No.  21.

                                                            • Each run consisted  of  24 push-travel cycles
                                                              per test run,  11.7  tons coke per push, 280.8
                                                              tons coke pushed  per test run.

                                                            • Allowable front-half emission rate (push and
                                                              travel combined)  =  0.03 Ib/ton coke.

                                                            • Compliance tests  run by Betz-Converse-
                                                              Murdoch on car No.  22.

                                                            •  Each run consisted of 24 push-travel cycles
                                                               per test run, 11.7 tons coke per push, 280.8
                                                               tons coke pushed per  test  run.

                                                            •  Allowable front-half  emission rate  (push
                                                               and travel combined)  - 0.03  Ib/ton  coke.
                                                                    (continued)

-------
                                                   TABLE 5  (continued)
NJ
•P-
Facility /Location
Republic Steel/
Warren, OH
(Battery 4)

Republic Steel/
Warren, OH
(Battery 4)


Republic Steel/
Youngstown, OH
(Batteries B&C)

Test Front-half Front-half
date(s) (gr/dscf) Ib/ton coke Comments
10/13/81 0.0302 0.0586
10/14/81 0.0106 0.0206
10/15/81 0.0122 0.0254
>
10/20/81 0.0147 0.0258 ""
10/21/81 0.0152 0.0271
10/22/31 0.0141 0.02^8
10/27/81 0.0149 0.0370 •>
10/28/81 0.0117 0.0309
10/29/31 0.0107 0.0293
^
» Compliance tests run by Betz-Converse-
Murdoch on car No. 1.
• Each run consisted of 24 push-travel cycles
' per test run, 12.65 tons coke per push,
303.6 tons coke per test run.
• Allowable front-half emission rate (push and
travel combined) = 0.03 Ib/ton coke.
• Compliance tests run by Betz-Converse-
Murdoch on car No. 2.
. • Lach run consisted of 2t push-travel cycles
' per test run, 12.65 tons coke per push,
303.6 tons coke per test run.
• Allowable front-half emission rate (push and
travel combined) = 0.03 Ib/ton coke.
• Compliance tests run by Betz-Converse-
Murdoch.
• Each run consisted of 2-* push-travel cycles
\ per test run, 11.5 tons coke per push, 275.5
tons coke per test run.
• Allowable front-half emission rate (push and
travel cotabined) = 0.03 Ib/ton coke.
                                                           (continued)

-------
                                                         TABLE  5 (continued)
NS
Facility /Locations
United States Steel/
Clairton, PA
(Batteries 19 and 20)
Test
date(s)
03/24/81
03/26/81
04/04/81
Back-half
Front-half insoluble
(gr/dscf) (gr/dscf)
0.0248 0.0022
0.0416 0.0077
0.0380 0.0016
Front-half plus
Back-half back-half
soluble insoluble
(gr/dscf) (gr/dscf) •Comments
0.0957 0.0270 >
0.0846 0.0493
0.0877 0.0396
s
• Compliance tests by Betz-Converse-
Murdoch.
• Runs No. 1 and 3 each consisted of 16
push-travel cycles per test run,
i 14.25 tons coke per push, 228 tons
coke per test run.
• Run No. 2 consisted of 24 push-
travel cycles per test run, 14.25
tons coke per push, 342 tons coke
per test run.
TABLE 5 (continued)
Facility /Location
United States Steel/
Clairton, PA
(Battery 15)
Test
date(s)
08/17-
19/81
08/20-
21/81
08/24-
27/81
Full-train
(gr/dscf)
0.026
0.025
0.042
Full-train
(Ib/ton coke) Comments
0.070
0.066
0.114
• Compliance tests by U.S. Steel on
H3-6 car.
• 24 pushes per test run, one
) traverse point per push
• Isokinetic range: 90.9 - 95.3%
                                                                                        • Average composite gas flowrate -
                                                                                          84,445 dscfm.

-------
     TABLE  6.   SUMMARY  OF  VISIBLE  EMISSIONS  DATA  FOR THE  ENVIROTECH/CHEMICO H-II  CARS

Facility /Location
Bethlehem Steel
Bethlehem, PA
Battery 5





No. of
pushes
Date observed
01/16/79
2
Range of
seconds
VE >202
14-26
Avg. seconds
per push
VE ^20%
20.
0
Maximum
opacity
(Z)
50
Avg . max .
opacity
(Z)
40.0



Comments
- Observations by
EPA
inspectors
} during stack tests.
01/17/79
01/30/79

01/31/79
03/08/79
8
4

2
11*
0-7
0-2

0-12
0-11
2.
0.

6.
1.
5
75

0
9
30
30

-
75
13.1
15.0

- J
26.8
- Push data only.
- Observations by
^ during nonstack
- Push data -only.

EPA
test

- Observations during

inspectors
periods.

BCM stack
                   03/08/79
                                         0-5
                                                      1.7
                                                                   70
                                                                            33.7
                   03/09/79     13*
                                         0-6
                   03/09/79
                                3+
                                                      1.1
                                                      1.0
                                                                   70
                                                                   30
                                                                            19.2
                                                                           18.3
  tests (7  out of 11 pushes  showed
  VEs _>20%).
- ^Observations during nonstack
  test periods (2 out of 4 pushes
  showed VEs ^20%).
- Sun visible (40% cloud cover).
- Observations by PADER;3 back-
  ground unknown.
- Push data only (20-hr coke)
- Company reported scrubber  valve
  problems during tests.

- Observations during BCM stack
  tests (5 out of 13 pushes  showed
  VEs 2:20%).
- ^Observations during nonstack test
  periods (2 out of  3 pushes showed
  VEs Z20Z).
- Sun visible - clear sky.
- Observations by PADER; background
  unknown.
- Push data only (20-hr coke).
- Scrubber valves adjusted before
  tests.
04/02/79
04/03/79
04/06/79
04/09/79


05/21/79
05/29/79
05/30/79
14(13)
3(3)
17(17)
1(1)


22
24
19
0-6(0-19)
0(0-5)
0-3(0-13)
0(0)


0-37
0-50
0-36
0.711.2.0)
0.(2.67)
0.41(2.18)
0(0)



- JACA observations during
^ test periods. (Data in

7.73
12.0
6.53 - - J
theses represent VEs >0%
~ Sky used for background.
- Push data only.




nonstack
paren-
opac ity)



Pennsylvania Department  of Environmental Resources.
                                                       (continued)

-------
                                                   TABLE  6 (continued)


Facility/Location
Bethlehem Steel/
Bethlehem, PA
(Battery 5)
(continued)
Bethlehem Steel/
Sparrows Pt . , MD
(Batteries 11
and 12)




Date
05/21/79

05/29/79
05/30/79
10/U/80

10/15/80
10/10/80
10/17 -'SO

No. of
pushes
observed
r

25
19
18---

11*
21*
7-

Range ot
seconds
VE >20°,
0-32

0-42
0-19
0-45

0-90
0-106
3-12

Avg. seconds Maximum Avg. max.
per push opacity opacity
VE >20X (%) CO
- ]
I
5.b - >
- J
13.2 - - -|

36.5 - - I
23.1 - - >
6.0 - -
J


Corame n t s
- JACA observations during nonstack
test periods.
- Coke guide hood tor background.
- Push data only.
- BCM observations during stack
cests.
-*Push and travel VE data combined.
- Slue sky for background.
- Sun in front of observer during
all observations.
                                                           t.cont inued)
ISJ

-------
                                                           TABLE 6  (continued)


Facility /Location
Bethlehem Steel/
Lackawanna, N.Y.
(Battery 7)




Bethlehem Steel/
Lackawanna, N.Y.
(Battery 8)



Dateb
02/20-21/80
08/12/80
12/02/80
03/16/81
09/15/81
02/09/82
05/11/82
02/20-21/80
09/15/81
02/09/82
05/11/82
Average of 24
consecutive opacity
readings3 (%) Comments^'0
32.1
12.6
9.6
14.2
15.6
57.1 - H-car inoperative
7.9
31.9
12.7
42.7 - H-car inoperative
17.5
        Observations were recorded at 15-second intervals,  for a minimum of 24 consecutive opacity observations, at the point of
NJ        greatest opacity and only during the coke pushing and transport periods.
00
        ^Visible emissions recorded in February and August 1980 were observed and documented in accordance with 6NYCRR, Part 21-t,
         By~Product Coke Oven Batteries, effective August 23,  1979.  Visible emissions recorded in December 1980 and in 1981-1982
         were observed and documented in accordance with the Delayed Compliance Orders signed May 28, 1979 and proposed policies
         submitted to the U.S. EPA, as required by the conditional approval of the New York State Implementation Plan.

        cBoth the 6NYCRR, Part 214.2(b) regulation and the Delayed Compliance Order requires that visible emissions from coke
         pushing and transport of coke to the quench tower shall be less than 20 percent opacity; determined by averaging the results
         of a minimum of 24 consecutive opacity observations made at 15-second intervals.

                                                             (continued)

-------
TABLE 6 (continued)
No. of Range of
pushes seconds
Facility/Location Date observed VE >0%
J&L Steel 8/16/79 16
Pittsburgh, PA (5)
(Battery P-4)
8/18/79 16
8/20/79 16
(10)
8/22/79 16
(12)
Note: VEs observed by Weston emanated
emissions also observed during
to
vO
0-30
(0-24)
0-17
0-20
(0-6)
0-45
(0-22)
Avg. seconds
per push
VE >0%
13.2
(8.4)
3.2
5.5
(1.1)
12.3
(7.8)
from between quench car and
stack tests


(not summarized

C cont i rvu
Range of
maximum
opacity
(%) Comments

0-90 "\ • Data taken by Weston Environmental during
(0-100) BCM stack testing.
\ • Data in ( ) taken by County for VEs ^20%.
0-65 J • Data by Weston only during BCM stack tests.
0-20 ^ • Data taken by Weston during BCM stack
(0-40) J • Data in ( ) taken by County for VE ^2(
0-80 ^ • Data taken by Weston during BCM stack
(0-100) 1 • Data in ( ) taken by County for VE >2(
the capture hood. Background - coke oven battery.
above). VEs observed by Allegheny County.

Pdl
tests.
)S.
tests.
)i.
Travel




-------
                                            TABLE 6 (continued)
Facility/
Location
J&L Steel/
Pittsburgh,
PA (Battery
P-4)




No. of
pushes
Date observed
09/19/79 9
(9)

Range of
seconds
VE j>20%
0-3
(0-7)

Avg. seconds
per push
VE >20%
0.56
(1.1)

Range of
maximum
opacity
0-35 ^|
(80)

Comments
• Data taken by BCM
tests.
y • Data in ( ) taken

during stack

by County
( simultaneously with BCM

09/20/79 12
(12)


0-9
(0-14)


1.4
(1.8)

J
0-30 ""
(30)

observations.
I • Data taken by BCM
tests.
)• Data in ( ) taken

during stack

by County
f simultaneously with BCM







11/05/79 11

11/06/79 11

11/07/79 32

0

0-3*

0-1**

0

0.27*

0.03**
s
0-10 ""

0-30*

0-20**
1 observations.
• BCM observations,
stack tests.
y • *0nly one push had
scrubber turned on

not during

VEs >20%,
late.
• **0nly one push had VEs _>20%.
Note:  Travel emissions also observed during above  dates (not summarized above)
       tions during observations not included with  data.

                                                (continued)
Background and condi-

-------
                                          TABLE  6  (continued)
Facility/
Location
Shenango Inc. ,
Neville Isl.
(Batteries
3&4)

No. of No. of
pushes pushes
Date(s) observed ' >20%
2/10-11/81

2/12

2/13
31 19(61.

23 10(43.

24 14(58.
Total Avg. sec.
sec. >2Q'i >_20%
per test per push Comments
3%) 229 7.4 -\ • Data taken by BCM during
1 stack tests (Method 9 VE
5%) 455 19.8 \ copies difficult to read).
{
3%) 243 10.1 J
Note:  From February 9 to July 1,  1981 a total of 130 pushes were observed at Shenango by EPA and Allegheny
county inspectors; average seconds VEs >_20% opacity = 12.9.

                                                          (continued)

-------
                                         TABLE 6 (continued)



Facility/
Location
USS/Clairton, PA
(Batteries #19
and 20)














Date(s)
08/30/79

09/05/79

09/06/79

08/23/79

08/29/79

08/31/79




Test No./
Battery
3/19
3/20

5/19
5/20
6/19
6/20
1/19
1/20
2/19
2/20
4/19
4/20

Avg . sec a
per push,
fugitive
VEs >20%a
20.5
18.1

3.7
3.5
3.8
15.2
2.3
10.8
12.0
10.2
11.9
13.0
Avg. sees
per push,
scrubber
stack
VEs >20%b Comments
^•1 (No details available)
8.8

0.4
0.1
0.5
6.5
2.6
4.5
6.3
22.4
2.8
6.1
aFugitive emissions observed from quench car and/or door machine during push only.




"Scrubber stack emissions averaged for push and  travel combined.




                                           (continued)

-------
TABLE 6 (continued)
Facility/
Location
USS/Clairton, PA
(Battery 19)




Avg. maximum
No. of Range of Avg. sees Maximum opacity
pushes seconds per push opacity per push
Date observed VEs J»20% VEs >20% U) ' (%) Comments
4/02/80 2 7-19 13 25 22.5
4/07/80 4 0-30 19 65 31.25
4/08/80 6 12-37 26.8 85 56.7
4/28/80 12 20-3b 28.2 100 81.7
4/29/80 11 22-39 31.6 100 93.2 )
• Observations by County
during testing of car.
• Travel data also avail
able, but not sum-
\ marized in this taole.




-------
         TABLE  7.   SUMMARY OF VISIBLE  EMISSIONS  DATA FOR THE  ENVIROTECH/CHEMICO H-III  CARS
  Facility/
  Location
Date(s)
           Total
 No.  of    No. of    No. of
 pushes   Method 9   readings
observed   readings    <20%
   No. of         No. of       No.  of
  readings       readings     readings
>20%,but <40%  >40%,but <60%    ^60%
                                                                                              Comment s
J&L Steel/     11/05/80      18        105
E. Chicago,  IN
(Battery 9)
               01/20/81      16          80
                                61(58.1%)*     23(21.9%)
                                48(60.0%)
                                   10(12.5%)
                 13(12.4%)     8(7.6%) -v • BCM observations.
                                      I • Clear sky (background unknown).
                                      /• 15 of 18 pushes  observed during
                                     J   stack tests.

                  6(7.5%)    . 16(20.0%)~\ • BCM observations.

01/20/81 15
03/17/81 24
03/26/81 2
• Clear sky (7 obs.); 100Z clouds
I (9 obs.)
/• 15 of 16 pushes observed during
stack test.
I • Unknown background.
53 36(67.9%) 8(15.1%) 2(3.8%) 7(13.2%)^ • BCM observations during stack
1 tests.
)• Generally clear (some clouds).
(• All observations - background
J unknown.
212 182(85.9%) 19(9.0%) 3(1.4%) 8(3.8%) ^ • BCM observations during stack
1 tests.
>• Overcast sky.
1 • All observations - background
J unknown.
11 8(72.7%) 3(27.3%) 0(0.0%) 0(0.0%) <\ • BCM observations during stack
I tests.
/• Conditions/background unknown.
J • Emissions from top of hot car.
aData in parentheses represents  the percentage of readings (of the  total number of Method  9 readings) that  were  in the category shown.

                                                             (continued)

-------
                                                   TABLE 7 (continued)
u>
Ol

Facility/
Location Oate(s)
J&L Steel/ 3/26/81
E. Chicago, IN
(Battery 9)

3/27/81



Facility/
Location
J&L Steel/
E. Chicago, IN
(Battery 4)


J&L Steel/
E. Chicago, IN
(Battery 9)



No. of
pushes
observed
23*



24*




Date
4/30/81

5/1/81


3/25/81

3/26/81

3/27/81

Range of Avg. seconds Maximum
seconds per push opacity
>.220% U)
0-35 13.1



4-60 19.9 100

TABLE 7 (continued)
No. of Range of Avg. seconds
pushes seconds per push
observed >20% >20%
15 8-80 29.0 "^

14 4-108 37.0 }
1
J
22 0-29 17.4 ^

25* 0-38 16.9 \
f
21* 9-62 26.0
J
Avg. max.
opacity
(%) Comments
"^ • BCM observations during stack
I tests.
I • VEs observed from top of hot car
/ • *Includes VE data from three (3)
76.0 pushes noted as "green" coke on
\ each day.



Comments
>• EPA observer.
• Background: overcast sky on 4/30;
battery on 5/1.
• Observations taken during stack
tests.
EPA observer.
During stack tests.
Excludes one sticker on 3/26.
Overcast sky background.
*0bserver noted two (2) pushes
were "green" coke on each day.
                                                         (continued)

-------
                                                        TABLE  7  (continued)
u>
Facility.'
Location
J&L Steel/
£. Cnicago, IN
(Battery 4)
No of
pushes
Date(s) observed
i/JO/.Sl 24

Range of
seconds
>20%
1-59

Avg. seconds
per push
>20%
27.0

Max iraura
opacity
U)
-

Avg . max .
opacity
U)
-

Comments
1« BCM observations during stack
tests.
• Observer on top of ovens.
                             5/01/81    1-
                             5.'05.81    2-
                                                  5-6-+
                                                             J7.0
                                                             32.8
• Overcast skies.
• Background unknown.
• 15 of 24 pushes used a
  conventional open coke guide.

• HOI observations during stacK.
  tests.
• Partly cloudy skies.
• Background - position unknown.
• 9 of 14 pushes used  a conventional
  open coke guide.

• BCM observations during stacK
  tests.
• Overcast skies, background
  unknown.
• Observer positioned  on ovens.
• 15 of 24 pushes used a
  conventional open coke guiJe.
                                                                  (continued)

-------
TABLE  7  (continued)
Total
No. of No. of No. of No. of
Facility/ pushes Method-9 readings readings
Location Date(s) observed readings <20% >20% Comments
Republic Steel/ 04/07/81 24* 12 12 0
Cleveland, OH
(Car No. 21) 04/08/81 25** 6t 64 0
04/09/81 25+ 81 81 0
J
Republic Steel/ - 04/15/81 24 14-* 144 0 ^
Cleveland, 0*il
(Car No. 22) OA/lo/81 23 U2 U2 0
^
• BCM observations during stack tests.
• *0nly 3 out of 24 pushes observed with
sun obscured or in correct Method-9
position.
• **0nly 9 out of 25 pushes observed
with sun obscured or in correct
Method-9 position.
• +-0nly 17 out of 25 pushes observed
with sun obscured or in correct
Method-9 position.
• Skies generally clear; observation
background unknown.
• BCM observations during stack tests.
• Observations recorded from above coke
> ovens using blue sky for background.
| • Clear skies prevailed throughout
1 observations.
        (cont inued)

-------
                                                          TABLE 7  (continued)
oo


Facility/
Location Date(s)
Republic Steel/ 10/13/81
Warren, OH
(Car No. 1) 10/14/81



10/15/81




No. of Range of
pushes seconds
observed >20%
22 0-29.1

19 0-34.8



20 0-14.1




Avg. seconds
per push
>20%
9.5

7.1



3.0



Average
Maximum maximum
opacity opacity
(%) (%) Comments




45 20.5 ] • BCM observations during stack tests.
• Skies relatively clear (0-10'i c
35 20.3 V cover).
f • Sun in observer eyes during all
observations.
j • Observation background. unknown.
25 16.0 A • Same as above, except 90% cloud
I with drizzle.
/ • Observations taken from top of
J collector main.
loud




cover



        Republic  Steel/
        Warren, OH
        (Car No.  2)
10/20/813



10/21,/81a

10/22/813
21



21

22
0-8



0-lb

0-13
3.0



1.9

2.0
25       25.7  1   •  BCM  observations  during  stack tests.
                  •  Background  unknown,  50%  cloud cover.
                  •  Sun  in  observers'  eyes when out.

90       17.1 ^   •  Same  as above,  except  10/, cloud cover.

23       13.9  /   •  Same  as above,  except  100X cloud cover,
              J     (white/gray clouds).
        aNote:   VE data  labeled  in test report indicates seconds  of  Vbs  _30 ',  opacity,  however, maximum opacities do not reflect these
         data.
                                                                 (continued).

-------
TABLE 7 (continued)


Facility/
Locat ion
Republic Steel/
Youngstown, OH







Date(s)
10/27/81

10/28/81

10/29/81


No. of
pushes
observed
23

22

21

Total
No. of
Method-9
readings
110

105

112


No. of
readings
<20%
110

105

109


No. of
readings
>20%
° 1

0 \
1
3
J

.

Comments
>• BCM observations during stack tests.
• Sky conditions generally cloudy in
morning with clearing, blue skies in
afternoon.
• Sun in observers' eyes when out.
• Background unknown.

-------
                                    SECTION 5

                     SUMMARY OF H-III PROBLEMS AND SOLUTIONS
                           REPORTED BY STEEL COMPANIES
INTRODUCTION

     Frequently-reported problems affecting H-III system availability are
summarized in this section.  Problems that were reported by only one plant are
not generally included herein, but are described in the Trip Reports.  Tables
listing each problem described in the Trip Reports appear in Appendices A-E.
Trip reports are on file at EPA.

     Available data describing H-II problems appears later in Section 6 and in
the Shenango Trip Report.  Detailed analysis of H-II problems was not
conducted primarily because GCA was able to discuss H-II problems with only
one plant (Shenango).  However, company-supplied malfunction data are
•available from Bethlehem/Bethlehem and J&L/Pittsburgh.

     The data shows that many problems affecting H-III car availability are
either solved, or being brought under control as plants gain operating
experience.  However, several major problems affecting car reliability were
.reported as only partly solved.  Several companies noted that as existing
problems are solved and the cars operate longer, new problems are expected as
equipment ages and wears.

     Overall, the steel companies visited indicated that the Envirotech/
Chemico cars are inherently difficult to maintain.  Envirotech/Chemico
responded (to GCA) by stating that the cars are not complicated compared to
other steel mill equipment, but are complicated compared to the relatively
unsophisticated process equipment in a coke plant.  Envirotech/Chemico felt
strongly that the primary problem was the reluctance of the steel companies to
assign experienced technical personnel to assist car maintenance crews.

     Several important points to consider when reviewing the data in this
section became evident during this study, i.e.:

     •    Steel companies were responsible for supplying Envirotech/Chemico
          with up-to-date plant drawings (for clearance and design work), raw
          water samples for water treatment system design (except for U.S.
          Steel who supplied their own water treatment).  Steel companies were
          also responsible for modifications to quench car tracks and hot
          rails prior to car installation.
                                        •41

-------
     •    Envirotech/Chemico  designed  and  installed  the  H-car (scrubber and
          control  car),  the one-spot quench car and  modified the  coke guide
          (installed  hooding).

     •    Subcontractors to Envirotech/Chemico built all one-spot quench cars,
          based on Envirotech/Chemico1s design specifications,  except at
          Clairton where U.S.  Steel  designed and constructed the  quench cars.

     •    Envirotech/Chemico  purchased H-car frames, wheel truck and basic cab
          assemblies  from vendors  except the Clairton frames and  cabs which
          were supplied by U.S.  Steel.   Envirotech/Chemico or their
          subcontractors constructed the internal components of each car.

     Several additional observations should also be  considered when reviewing
these data,  i.e. :

     •    USS/Clairton attempted to  debug seven H-III cars almost
          simultaneously; the company  reported in September 1981 that the
          overwhelming number of cars  and problems led them to conclude that
          debugging efforts should be  confined to one car at a time.  During
          an April 1982 status meeting held at Clairton, U.S. Steel reported
          that solutions to all but  two problems (drive motor bore elongation
          and ductwork erosion) were developed and would be implemented on all
          cars when currently idle batteries returned to service.

     •    Republic Steel had previous experience with H-III cars at the Warren
          and Youngstown plant prior to starting-up and debugging the
          Cleveland cars, where less problems were reported for  Cleveland.

     •    Availability data submitted to EPA by  J&L, Indiana Harbor Works
          shows very  low availability of their  two H-III systems, and  thus,
          these systems have not been operated  as long as others.

H-III LAND-BASE PROBLEM SUMMARY

     Table  8  summarizes problems reported  by  each company for  the H-III
land-based  hot  water  heater  system and  transfer station.  Frequently-reported
land-base problems that reduced car availability may be  summarized  as:

      •    Coke  oven  gas combustion problems in the  land-based  heater;

      •    Heater  system malfunctions  (generally, heater  controls);

      •    Scrubber water  treatment  system  malfunctions;

      •    Hot water  transfer (to  car)  failures.
                                     42

-------
                TABLE  8.  H-III  LAND-BASED  HOT WATER  SYSTEM PROBLEMS AND CORRECTIVE ACTION  TAKEN,  AS
                            REPORTED BY  COMPANIES  VISITED
u>
Problem
Poor COG combustion
Heater controls malfcn.
Undersized combustion
air fans
No water flow through
tubes during low-fire
Water treatment
malfunction
Water line corrosion
Transfer arm failure
Transfer line valve
failure
Charge arm support
bolt failure
Steam hammer in lines
FEMCO radio coramunicat ion
difficulty
Pressure sensor failure
Effect
Low heat , burner
flame-outs
Back-up heater failure
Low heater output
Poor temperature control
tube damage
Filter and piping
plugging
Pitting, corrosion of
lines, valves
Water transfer failure
Accidental discharge,
leakage
Alignment problems
Damaged valves
Water transfer failure
Water transfer failure
U.S. Steel
Clairton
NAa
NAa
NAa
, NAa
Adding
deaerator
Adding
deaerator
Varied problems
(see text)
NR
Stainless bolts
and keepers
modified
NR
Many problems
Testing new
sensor
Republic Steel,
Warren, Youngstovn
Switched to natural gas,
improved controls
NRb
Installed larger fans
Installed recirculation
line
Switched to city water
Added nitrogen
Varied problems
(see text)
NR
Air motor modified
NR
Some problems
NR
Republic Steel,
Cleveland
Switched to natural gas,
improved controls
Redesigned controls
Installed larger fans
Installed recirculation
line
New system controls
installed
NR
Limit switch failures
corrected by moisture
control
Valves upgraded
NR
Installed bypass line
Some problems
NR
J&L Steel,
Indiana Harbor
Switched to natural gas,
improved controls
Redesigned controls
Installed larger fans
Installed recirculation
line
Planning system
improvements
NR
Varied problems
(see text)
Additional limit awitche
installed
NR
NR
Minor problems, typical
of other plant machinery
NR
       aNA = Not Applicable - i.e., U.S. Steel uses different  system (plant steam) for hot water  treatment and heating.

       °NR = Plant did not report this problem area.

       Note:  Problems not listed in any order.

-------
Note that U.S. Steel uses plant steam to provide hot water heating, and not
the gas burners and heaters used at all other plants.  Also, U.S. Steel
supplied their own water treatment capability whereas all other plants
purchased a system supplied by Envirotech/Chemico.

     Many land-base problems have been either completely or partially solved
during start-up and debugging.  However, several minor problems, and the
general problem of hot water heating and transfer still affect car
availability at several plants as discussed below.  More details are available
in the Trip Report for each company.

COG Combustion Problems

     All three plants using gas-fired hot water heaters reported that
maintaining steady COG combustion in the hot water heaters was nearly
impossible.  Poor gas flow and burner/pilot flameouts restricted hot water
availability.  A pressure sensor prevents hot water  transfer to  the car at
temperatures below about 450°F.  (Water pressure  and temperature are directly
proportional).  Each company reported that heater systems were designed to
burn COG, and noted that few problems were encountered with other  COG-burning
equipment at their plants.  (Recall that Clairton uses steam heating and
reported no problems).

     After 6 months of attempting to solve COG combustion problems, RSC/Warren
and Youngstown converted to natural gas (NG).  RSC/Cleveland also  converted  to
NG, and J&L is planning NG conversion.  Although  NG  was originally intended  as
a backup fuel at all three plants, the conversion to a primary  fuel reportedly
requires changing gas lines and process controls  and instrumentation to
accomodate the higher Btu content and  lower  feed  pressures  associated with NG.

Heater System Malfunctions

     The hot water heater switches to  a low-fire  mode  ("soak")  once the charge
tank in the transfer building  is  full.  The Envirotech/Chemico-supplied system
did not provide  for water circulation  in heater tube bundles during soak
periods, according to steel companies, and overheating problems  were reported
by  all three plants using this system.  RSC/Cleveland  reported  that two tube
bundles were  destroyed due  to  this problem.   (The Clairton  steam heat  system
does not have  these hot water  heaters).

     Recirculation  lines  installed  at  Republic's  three plants  reportedly
solved most overheating problems.   However,  hot spots  from  flame impingement
on  heater  tubes  remains  a major concern relative  to  tube  life.   J&L also
installed  a recirculation line to  control overheating  and also  increase the
low water  temperature encountered  during normal fire periods.   The
newly-installed  line was  untested  in actual  operation  as  of January  1982  since
the push control systems  were  out  of service.

     All  three companies  using the  COG heater system reported  that undersized
combustion air fans prevented  attaining adequate  water temperature.  Larger,
new fans were installed  which partially corrected the  problem.
                                        44

-------
     Backup heater control system failures were reported for three of four
plants using this system.  The control system either failed to start the
backup unit upon failure of the primary heater, or else both heaters were
fired simultaneously.  Each company reporting these problems redesigned
controls to correct the situation.

Water Quality Problems

     All three companies using the Envirotech/Chemico-supplied water treatment
system reported serious operational problems.  Filter plugging with influent
solids, carbonate plugging of water lines, and pipe/valve corrosion were
reported.  Treatment system design was based on water samples supplied by each
steel company.

     After attempts by Envirotech/Chemico and Republic to improve system
performance failed, Republic switched to city water at Warren and Youngatown.
New process controls were installed at Cleveland, which reportedly solved
water quality problems.  J&L was planning to improve their existing system
sometime in 1982.

     U.S. Steel reported plugging and corrosion of the water system in the
transfer building and onboard the H-III car.  Solutions to sparger tube
plugging were reportedly developed by April 1982, and a deaerator was to be
installed to eliminate storage tank corrosion onboard the H-III car.  U.S.
Steel supplied their own water treatment for the push control system

     Republic/Cleveland has what appears to be a unique hot water supply
problem because their hot water charge system was supplied without a building,
and the heat tracing on water lines didn't prevent freezing.  RSC/Cleveland
installed a lean-to and applied "torches" to points prone to freezing.

Hot Water Transfer Problems

     Maintaining charging arm alignment and poor limit switch performance were
commonly reported problems.  Between 9 and 17 limit switches (depending on
plant) must be satisfied by proper positioning of the charge arm relative to
the land base transfer hub.  Frequent switch malfunction was commonly
reported, causing inability to transfer hot water.

     RSC/Cleveland reported limit switch problems consisting of winter
freeze-ups were solved by enclosing (the unenclosed) charge station and
adding a vent stack to divert steam discharges away from switches.
RSC/Cleveland was the only plant with an unenclosed charge station.  No major
limit switch problems were reported by RSC/Warren and Youngstown.  J&L
reported limit switch failures usually occurred once per shift, requiring
about 30 minutes to correct.  USS/Clairton reported frequent limit switch
failures often caused downtime on the order of an hour or two.  In April 1982,
Clairton also reported failures of the water pressure sensor that caused
inability of water transfer.  A new sensor design was undergoing tests.
                                        45

-------
Charge Arm Alignment Problems

     Charge arm alignment problems occur between the horizontal faces of the
land-based hub and the car-based charge arm.  These two faces must be aligned
to within 0.010 to 0.030 inches.  Several inches of "misalignment" in the
vertical direction can be handled by the land-based guide rollers.
Misalignment is caused by track wear/deterioration, stucki bearing wear, weak
car springs, and wheel wear.  Generally, the problem is differential wear
causing an elevation difference between the two sides of a car.

     U.S. Steel reported major problems with charge arm alignment when  the
cars were new.  U.S. Steel developed an optical alignment technique that
reduced alignment time to less than 8 hours compared to a day or more for the
Envirotech/Chemico procedure.  USS noted that total realignments are
infrequently required; i.e., only in cases such as total failure and major
repairs on a land-base system.  Before a new car is placed in service at
Clairton, it is prealigned on the set-up tracks using reference points, and
checked at the land-base station.  USS is planning to build a "dummy"
land-base station for standardizing car alignments between batteries and to
facilitate prealignment.

     RSC/Cleveland installed a "dummy" charge station in their maintenance
shed to allow alignment  (of  the spare car) prior to returning to service.
RSC/Warren and Youngstown reported alignment problems of a minor nature have
largely been solved.  J&L indicated that their charging arms  required
realignment about once every three months.

     Charge arm alignment is aggravated by serious track deterioration  which
was reported by all plants.  The heavy H-III combined with poor drainage of
quench water from battery tracks due to coke spillage from the coke box were
cited by  several steel companies as the cause.  Track improvements made by
each plant prior to H-III installation ranged from simple ballast cleaning
(Battery  4 at J&L)  to installing an 18 inch thick concrete pad along  the
entire battery length (RSC/Cleveland).  Regardless of track modifications
already made, all companies  report frequent track maintenance has been
required  and  they anticipate  replacement in the near  future.

Status of Land-Base Problem Resolution

     Transfer arm failures,  FEMCO problems  and water  treatment problems are
still  affecting availability at  some plants.  Table  9 summarizes  the  status  of
land-base problems  as described  by each company interviewed.

H-III  QUENCH  CAR AND  COKE GUIDE  PROBLEMS

     Commonly reported  quench car and  coke  guide  problems  are  summarized  in
Table  10.  A  few additional,  apparently  isolated  problem  areas  at  certain
plants  are  listed in  the Appendix.  Three  continuing  problems are  apparently
only  partially  solved,  i.e.:
                                     46

-------
                   TABLE 9.   STATUS  OF  H-III LAND-BASE PROBLEM RESOLUTION
          Problem
Status of resolution1"
                                                             Solved byc
                                                        Comments
 Poor  COG combustion (3)a


 Soak  period overheating (3)


 Undersized combustion air
 fans  (3)

 Backup heater failures (2)

 Water treatment problems (4)
Transfer arm failures (4)
FEMCO radio communication
difficulty (3)
Charge arm support bolt
failure (2)

Water line freeze-up, steam
hammer (1)
Mostly solved


Mostly solved


Mostly solved


Solved

Partly solved




Partly solved





Partly solved
Solved
Solved
Steel mills; some   Poor performance of burners  and  controls
Chemico assistance  used in system.
Steel mills and
Chemico

Steel mills
Steel mills

Steel mills
Steel mills, some
Chemico assistance
Steel mills, some
Chemico assistance
Steel mills
Steel mill
(occurred at one
plant only)
Equipment or design problem.


Equipment or design problem.


Equipment or design problem.

Mills supplied raw vater samples for
system design.  Chemico implied that
same companies ignored recommended O&M
procedures.

Aggravated by track deterioration,
moisture.  Chemico suggests more
experienced maintenance personnel
needed; companies claim system is in-
herently difficult to maintain.

Some companies report FEMCO malfunc-
tions, others report problems no
greater than with other FEMCO
equipment.  Chemico reports all
companies specified that FEMCO equip-
ment be used.

Original design; operational problems
likely aggravate problems.

Company reports Chemico advised en-
closure was not needed, winter
operations no problem.
aNumber of plants experiencing problems  shown in parentheses;  counting  RSC/Warren  and  Cleveland  as  one,  four  plants
 total.

"Terms "mostly, partly and solved"  assigned  by GCA based  on  comments made by  steel companies  during plant visits.

cBased on discussions between GCA and  each steel company  visited.   Specific solutions  were  presented previously  in
 this section, and details appear in  the  Trip Reports.

-------
     TABLE 10.   H-III QUENCH CAR  AND COKE  GUIDE PROBLEMS AND  CORRECTIVE ACTION TAKEN,  AS REPORTED
                  BY COMPANIES VISITED
Problem
Car rocking - track
deterioration, weak
springs
Coke spillage
Coke box warpage
Tilt limit switch
failure
Dump cylinder failure
•t-
00
TV camera failure
Running light failure
Brake shoe wear
Effect
Derailment, collisions
Poor track drainage,
increased car
maintenance, damage
Repairs, possible
clearance problems
Clearance, dump
problems
Frequent malfunctions,
maintenance
Poor operator vision
Poor operator vision
Frequent replacement
U.S. Steel Republic Steel,
Clairton Warren, Youngs town
Installed sta- Track improvements and
bi liters, track maintenance
improvement 8 ,
new stuck! s
Enlarged box, Modified guide, hot box,
for better ram
distribution
Convert channel- Reinforced frame
floor to solid
plate
New switch Installed timer
design mechanism
Several NR
problems
Improved pro- NR
tection, purge
air, wire relo-
cation
Installed steel NR
shields
Converted to NR
conventional
design
Republic Steel,
Cleveland
Track improvements and
maintenance
Modified guide and ram
NR
Added backup switches,
third-rail control
Replace seals
NR
Installed plexiglass
enclosures
Installed pressure sensor
J&L Steel,
Indiana Harbor
Installed shock absorbers
track maintenance
Coke distribution improve-
ments, extended push ram
Unspecified design change
Reworked switches
Continued maintenance
Improved weatherproof ing
NR
New shoe design
*NR = Plant did not report this problem area.

Note:  Problems not listed in any order.

-------
     •    Coke spillage (also affects H-II) (all four plants);

     •    Track deterioration, car rocking, potential derailment  (also affects
          H-II) (all four plants);

     •    Coke box warpage (two of four plants).

Other quench car and coke guide problems reported by the mills substantially
affected car reliability during start-up periods but appear to be  largely
solved or under control.  Each problem area is discussed below, and additional
details are available in the Trip Reports.

Quench Car Rocking, Track Deterioration

     All companies reported excessive quench car and H-car rocking due to weak
car springs and/or track deterioration.  USS and J&L added stabilizers and
springs respectively to better support the car.  USS is replacing  the "stucki
bearings" that support cars on wheel trucks with a solid design.   The stucki
bearings are a cylindrical roller-type bearing which lies between  the wheel
trucks and the railroad car body with its primary axis in a horizontal plane.
The bearing supports the car on either side of the wheel truck vertical axis
while allowing for wheel truck movement on curves relative to the  car body.

     Quench car rocking and track deterioration problems cause potential for
car derailment and collisions with the coke guide, quench tower or combustion
stack due to close clearances.  Track deflections exceeding one inch have been
observed (by GCA).  The companies identified the cause as car weight and soggy
track beds due to poor water drainage from spilled coke.  Track deterioration
problems have apparently not been solved by any steel company and  remain a
problem.  Details of track modifications already made at each plant appear in
the Trip Reports.

Coke Spillage

     Coke spillage during the push was reported by all companies as a severe
problem when cars were first placed in operation.  Substantial spillage during
the push resulted in daily track cleanup to prevent derailments and control
soggy track ballast.  Coke spillage also damages the cars with burning coke
(i.e. hydraulic and electrical cable deterioration).  Only USS reported
spillage problems were solved, although all other companies visited indicated
spillage had been reduced and brought under control.  Spillage rates and track
cleaning frequency during conventional quench car operation were not provided
to GCA.

     J&L reported the spillage problem was solved by extending the push ram
head, removing deflector plates inside the quench car, and other unspecified
improvements.  Some improvements were reportedly made by Envirotech/Chemico
while others were made by J&L.

     RSC/Warren reported that coke guide and quench car deflector  plate
modifications by Envirotech/Chemico were ineffective.  RSC extended the push

-------
ram face by 8 inches, affixed a shovel-type wedge to the ram bottom, and added
a tilting lip to the coke box.  Some improvements were achieved, but daily
track cleaning is still required.

     RSC/Cleveland1s experience was similar to RSC/Warren, except
Envirotech/Chemico's modifications (similar to those at RSC/Warren) reduced,
but didn't eliminate spillage.  Track cleaning for 3 days per week is still
required.

     RSC/Youngstown1s spillage problems occur primarily at the wharf, since
the quench car discharge is slightly misaligned with the wharf.

     USS/Clairton reported severe spillage problems were not solved by adding
deflector beams and baffles to the quench car.  A portion of the horizontal
plate covering the car opening was removed as an interim measure.  Spillage
required track cleaning once every one or two days compared to weekly with a
conventional car.  Spillage problems were reported to be solved at the April
1982 status meeting by enlarging the coke box by 50 cubic feet to achieve
better coke distribution during the push.

Coke Box Warpage

     Three plants reported coke box warpage was eliminated by design changes
and reconstruction.  One plant did not report warpage problems.  Warpage was
due to thermal stresses from the pushing-quench cycle, sometimes aggravated by
a malfunction causing coke to be held in the quench car for a longer than
normal time.

Coke Box Tilt Limit  Switches

     The Envirotech/Chemico-supplied quench car contained two mechanical
switches to prevent  car movement with a tilted box.  This was important to
avoid hitting a tilted box on an adjacent stack or other  structure.

     All companies  reported  frequent limit switch  failures contributing to  car
immobility and/or concern over inadvertent dump problems  and collisions.
Various modifications to limit switch design  reported by  each company  solved
these problems.

Other Quench  Car Problems Reported

     Failure  of the  coke box  dump cylinder, TV camera,  and running  lights,  and
rapid brake shoe wear were commonly  reported.  Dump cylinders  are  replaced
and/or given  increased maintenance.  TV cameras and running  lights  necessary
for operator's vision suffer  damage  from water and coke  spillage.   Physical
protection, shielding and weatherproofing reportedly  solves  these  problems.
Other minor problems that contribute to downtime  appear  in  the  Trip Reports.

Status of  Quench Car and Coke Guide  Problem Resolution

     Table  11 summarizes the  status  of quench car and coke guide  problems.
With the  exception  of  the Clairton  quench cars supplied  by U.S.  Steel,  all

                                      50

-------
                 TABLE  11.   STATUS OF H-III QUENCH CAR AND  COKE GUIDE PROBLEM RESOLUTION
          Problem
Status of resolution
                                                             Solved byc
                                 Comments0
 Car rocking  due  to springs,
 stuckis  (all 4)a
 Track deterioration (all 4)
 Coke  spillage  (all 4)
 Coke box warpage (3)
Dump cylinder failure (2)
TV camera, running light (2)
failure

Brake shoe wear (3)
Mostly solvedb
Partially solved;
high maintenance
Partially solved


Partially solved
Limit switch-box tilt (all 4)     Mostly solved
Mostly solved; high
maintenance

Mostly solved
Mostly solved
Steel mills
Steel mills
responsibility
Chemico, partly;
Mills, primarily

Steel mills
                        Steel mills
Steel mills
Steel mills
Steel mills
USS designed, built Clairton boxes-
Other mills - Chemico subcontractor
supplied cars.  Problem aggravated by
track deterioration.

Companies responsible for track
modifications.  One company (RSC)
stated Chemico advised conventional
track ballast adequate.

Related to guide and box design/
construction.

Increased by equipment malfunctions
causing coke to be held for extended
periods.  Original boxes of stainless
steel

USS supplied Clairton quench cars.
Chemico subcontractor supplied others.
Problems aggravated by quench and land
base moisture, coke spillage.

Supplied by Chemico except for
USS/Clairton.

Supplied by Chemico except for
USS/Clairton.

Supplied by Chemico except for
USS/Clairton.
aNumber of plants reporting problems shown in parentheses;  counting RSC/Warren and Youngstown as one,  four plants
 total.

"Terms "mostly, partly and solved" assigned by GCA based on comments made by steel companies during plant visits.

cBased on discussions between GCA and each steel company visited.   Specific  solutions were presented previously in
 this section, and details appear in the Trip Reports.

-------
quench cars were built to Envirotech/Chemico1s specifications by
subcontractors, according to Envirotech's Vice President.

H-III SCRUBBER CAR PROBLEM SUMMARY

     Table 12 summarizes commonly-reported problems with the H-III scrubber
car.

     The only two remaining problems for which no solution has yet been
developed at USS/Clairton involve the H-III car.  Elongation of the bores in
the electric traction drive motors is accelerating.  The supplier (General
Electric) is working on the problem but is reportedly unable to identify the
cause.  Erosion and development of holes in the scrubber ductwork is the other
unresolved problem at Clairton.

     At other plants, a multitude of problems seriously affecting car
reliability during startup and debugging were reported, as shown in Table 12
and in the Trip Reports.  Most of these problems appear to be solved or under
control as discussed below.

Charge Arm Alignment/Track Deterioration

     These problems affect the H-III scrubber car and were discussed
previously in the land base section and Table 8.

Jet Valve Leakage

     Jet valve leakage and substantial water  loss was reported by USS/Clairton
and RSC/Cleveland.  Leakage developed at Clairton when Envirotech/Chemico
changed the 1.4 inch diameter  jet valve needles to  2.0 inches to provide more
scrubbing water to the jets and improve gas cleaning.  U.S.  Steel was working
with Envirotech/Chemico in September 1981 to  solve  the problems, and reported
in April 1982  that their jet valve problem appears  solved.   The nature of the
solution was not disclosed by  USS at the April  1982 meeting.

     RSC/Cleveland reported in March 1982 that  valve  leakage is becoming
serious, approaching a quarter million gallons  per  week.  No solution had yet
been developed at that time.

FEMCO Radio Communication System

     FEMCO units are commonly  used in coke plants  to  provide process-related
signals  for coordinating machinery.  Clairton reported serious  problems with
all FEMCO  units due  to an inadequate number of  transformer  couplings  in the
original units.  New couplings were on order  in September  1981  and  planned  for
installation.

     RSC/Cleveland reported unreliable FEMCO  operation relative  to
coordinating quench  car alignment with the coke guide.   RSC solved  the  problem
by  installing  an  infrared  spotting device and a radio interlock mechanism.
                                     52

-------
TABLE 12.  H-III  SCRUBBER CAR PROBLEMS AND CORRECTIVE ACTION TAKEN, AS REPORTED BY
           COMPANIES VISITED
Problem
Charge arm alignment
Track deterioration
Jet valve leakage
FEMCO communications
Tract ion drive motors
Power pickup ara damage
Ul
U>
Electrical inverter
failure
Air compressor overheat
Air dryers

Stucki bearing/wear
plate
Exposed, mixed wiring
Effect
(described in Table 11)
(described in Table 11)
Water loss
Occasional poor
conuunications
Car ionobility
Am, shoe failure, car
immbolity
Trip-out, car shutdown
Car shutdown
Weak air supply to
instruments
Excessive moisture,
freeze-up
Failure, car
instability
Damaged by coke,
troubleshooting diffi-
cult, shutdowns
U.S. Steel Republic Steel,
Clairton Warren, Youngstown
-

Appears solved as NR*
of 4/82
Increased number Increased signal
of transformer strength
couplings
Several serious Unspecified serious
problems; most problems at Youngstown
resolved
Redesigned arma, NR
added second set
Added additional NR
units to allow
repair while online
Manually open Installed exhaust fans
car vents
Converted pneuma- NR
tic controls to
electrical
Adding new NR
separator
Converting stuck- NR
is to solid
supports
Isolated, insu- Isolated and insulated
lated wiring
Republic Steel,
Cleveland
-

Rewelded flanges
Only affects quench car
spotting; infrared spot-
ting and radio interlock
added
Coil failure; unspecified
changes
Covered exposed wires
Delay installed to reduce
power surges
NR
Installed larger dryers
NR
Converting stuckis to
solid supports
NR
J&L Steel,
Indiana Harbor
-

NR
No changes; problems same
as other in-plant FEMCO
NR
Hot rail redesign to reduce
shoe wear
One failure; unit replaced
Installed cooling fans
Installed larger air dryer
NR
Teflon pads replaced
NR
                                           (continued)

-------
                                                    TABLE  12  (continued)
Problem Effect
Hot rail icing Car shutdown

Oxygen release from Corrosion, pitting
hot water
TV camera reliability Poor/lack of vision

Water leakage into cab Control panel, wiring
malfunction
U.S. Steel
Clairton
Automatic car
restart equipment
added; steam
tracing of rails
successful
Adding deaerator
Protected, sealed
cameras. Cannot
operate without
cameras
NR
Republic Steel, Republic Steel,
Warren, Youngs town Cleveland
NR NR

Observed in linea, NR
valves. Added N£
NR NR

Attempting to seal cab Attempting to seal cab
J&L Steel,
Indiana Harbor
Heat tape; restart button
moved to operators cab.

NU
Improved weatherproofing.
Can operate without
cameras.

NR
aNR « Plant  did not report this problem area.




Note:  Problems not listed in any order.

-------
    '.RSC/Warren and Youngstown reported weak FEMCO contact between the land
base and H-car sometimes prevented water transfer.  Hot rail power was used to
increase FEMCO signal strength, with some improvement, but problems are still
experienced.

     J&L reported some FEMCO problems but noted that the problems experienced
were no greater than problems encountered with other coke plant FEMCO units
already in use.

     Envirotech/Chemico noted that FEMCO systems were requested by the mills
for the push control cars since mill personnel are familiar with the FEMCO
system.

Air Compressor Overheating

     Overheating air compressors and car shutdown due to high cabin
temperatures were commonly reported.  Installation of cooling fans and opening
car sides/louvers were reportedly partially effective, but problems
occasionally still develop in warm months.

Traction Drive Motors

     Several serious, debilitating problems experienced at Clairton were
traced to defective motor manufacture.  Minor problems with an electrical coil
were reported by RSC/Cleveland.  Serious, unspecified problems with drive
motors were reported for RSC/Youngstown.  The other companies reported no
traction motor problems.

     According to Envirotech/Chemico, the GE motors used at Clairton are
somewhat different than at other plants because U.S. Steel designed and built
the H-III frames and wheel assemblies.

     An update of the Clairton motor problems was provided at the April 1982
status meeting.  Remachining of motor housings by GE to eliminate field coil
shorting was complete on 60 percent of the 28 drive motors (four motors per
H-III car).  USS reported 3 days are required to remove four defective motors
and replace four new (repaired) units.

     Motor power lead shorting from rubbing on wheels was eliminated on all
Clairton cars by fixing leads to the car frame and reducing wire length.  USS
indicated that their Johnstown shop designed the leads and Envirotech/Chemico
was responsible for the motors.

     USS reported (April 1982) working with GE for 2 months attempting to
solve a serious motor "load problem".  Motor bores which hold the motor main
shafts are elongating (wearing) much more quickly than normal due to high
mechanical strain from unknown causes.  GE reportedly claims the motors are
well suited to the application, and has not yet discovered the cause or
solution.  USS does not know when this problem will be solved.
                                     55

-------
Electrical Inverter Failures

     Three plants reported failure of the inverters which convert hot rail DC
power to AC for onboard equipment.  J&L and RSC/Warren, and Youngstown each
reported one inverter failure.  J&L replaced the inverter unit:  RSC reported
long delivery time from the New Jersey-based supplier was experienced.

     RSC/Cleveland reported that power surges frequently caused inverter
failure and car shutdown.  A delay mechanism in the electrical line reportedly
solved the problem.

     USS/Clairton reported electrical congestion in inverters  frequently
caused failure of onboard AC equipment.  Also, loss of hot rail power from ice
buildup caused inverters to trip-out and shut down the car.  U.S. Steel noted
difficulty in working on inverters due to restricted access.   In April 1982,
U.S. Steel reported that a third inverter unit was being added to each car to
allow repairs to a malfunctioning unit while the car remains in service.  U.S.
Steel stated that the back-up unit supplied with the car could not be operated
while repairs were underway on the primary unit due to the wiring setup.

Power Pick-Up Arms

     Broken power pick-up arms, excessive pick-up shoe wear and damaged wiring
from spilled coke caused downtime at three plants.  These problems were
reportedly solved by various modifications.

     According to Envirotech/Chemico, U.S. Steel built the power pick-up
system for the Clairton cars.  GCA1s September 1981 inspection at Clairton
noted that the U.S. Steel design being retrofit to all cars at that time
appeared less complicated, less prone to damage, and easier to repair than the
original design.

     J&L encountered excessive shoe wear with their Envirotech/Chemico-
supplied pick-ups.  J&L redesigned the hot rails, and  shoes are  frequently
replaced.  The pick-up arms were supplied with a steel housing for protection
against spilled coke.

     RSC/Cleveland reported their  system was  supplied  without  a  protective
shield, and unprotected wiring was exposed to spilled  coke.  The wiring and
pick-up arms were enclosed and shielded to solve the problem.

Stucki Bearing/Wear Plate Failure

     Stucki bearings on  the USS-supplied H-III car  frames  and  quench  cars at
Clairton wore rapidly, causing car instability, charge arm alignment  problems
and  potential for  derailment.  The company was replacing  the  roller-type
stucki bearings with a solid  design  in September  1981.  The Envirotech/-
Chemico-supplied cars at RSC/Cleveland also had stucki bearings  that  wore
quickly and were replaced by  RSC with  solid supports.

     No problems were reported at  RSC/Warren  and Youngstown.   J&L  reported
that  the Envirotech/Chemico-supplied Teflon wear plates used  on  their cars

                                     56

-------
wore quickly and required replacement.  These systems were originally supplied
with solid-type wear plates instead of stucki bearings.

Summary of H-III Scrubber Car Problem Resolution

     Table 13 summarizes the status of H-III car problems reported by the
steel companies.  In assessing responsibility for problem areas, several
thoughts should be kept in mind when reviewing this table.


     •    U.S. Steel designed and built the H-III frames, wheel assemblies,
          drive motor supports, power pick-up assemblies and cab structures
          while Envirotech/Chemico added the internal components, according to
          Envirotech/Chemic o.

     •    H-III frames and wheel truck assemblies for all other plants were
          purchased by Envirotech/Chemico from a supplier, based on Chemico's
          general specifications.  The car internal components were added at
          Envirotech/Chemico's or a subcontractor's shop.  This arrangement
          partially accounts for minor differences observed in car
          construction.
                                    57

-------
                               TABLE 13.   STATUS OF H-III  SCRUBBER CAR  PROBLEM RESOLUTION
                 Problem
Status of resolution     Solved byc
                                                                                                  Comments0
oo
       FEMCO  communications  (4)a
        Jet valve  leakage  (2)
       Traction drive motors  (3)
Partly solved
Mostly solved
Partly solved
       Air compressor overheating (3)  Continuing problem

       Inverter failure (3)            Mostly solved

       Stucki/wear plate failure (3)   Solved
       Air dryers inadequate (3)

       Exposed, mixed wiring (2)

       Hot rail icing (2)

       Piping, tank corrosion (2)

       TV camera reliability (2)

       Water leakage into cab (2)
Solved

Solved

Partly solved

Partly solved

Under solution

Unsolved
Steel mills
Chemico, mills
investigating

Motor manufacturer
at Clairton; Repub-
lic at Cleveland

Steel mills

Steel mills

Steel mills


Steel mills

Steel mills

Steel mills

Steel mills

Steel mills
Chemico reports FEMCO systems specified
by mills.  Mills state units supplied
were inadequate.

Possible machining problems with valves.
Motor vendor (Clairton).  Unspecified
at RSC.
                                              Original  units  inadequate

                                              USS  supplied  Clairton  car  frames.
                                              Chemico1s vendor  supplied  others.
Mills responsible for hot rails
       aNumber of plants experiencing problems shown in parentheses (4 plants total,  counting  RSC/Warren,  Youngstown  as
        one.
       bTerms "mostly, partly and solved" assigned by GCA based on comments made by steel  companies  during  plant  visits.

       cBased on discussions between GCA and each steel  company visited.   Specific  solutions were presented previously
        in this section, and details appear in the Trip  Reports.

-------
                                    SECTION  6

                   MAINTENANCE PROGRAMS AND AVAILABILITY DATA

MAINTENANCE PROGRAMS

     Table 14 summarizes car maintenance program information obtained during
the plant visits.  Each program is described below.  Additional details appear
in the Trip Report for each plant visit.

     All information presented below was obtained through discussions with
representatives of each company during the GCA plant visits.  Representatives
of Envirotech/Chemico Corporation attended one meeting, the April 1982 status
meeting at USS/Clairton.  All other discussions were held between GCA and
steel company representatives.

U.S. Steel/Clairton - Maintenance Program Described to GCA
During September 1981 Inspection

     Checklists used for routine maintenance inspections at Clairton appear in
the Trip Report.  The company was beginning to record malfunction and repair
data by computer in September 1981.  An example computer printout also appears
in the Trip Report.

     One maintenance foreman is assigned full time to manage the 20-member
maintenance crew that handles the cars.  This foreman also has responsibility
for Clairton1s door program, but he stated that virtually all his time was
spent on the cars since experienced foremen in the door shop handled door
repair duties.

     Four locations are used for maintenance of the Clairton cars.  Sidings
near each battery are used for routine efforts; little permanent repair
equipment is available.  A car set-up area near the maintenance office is used
for in-plant repairs.  A concrete jacking pad/pit arrangement was under
construction at another location in September 1981.  Finally, major repairs
are made off-site at a U.S. Steel car shop.

     In September 1981, maintenance was reportedly conducted on an "as needed"
basis since the cars frequently broke down.   GCA spoke with a number of people
involved with the cars at Clairton in September 1981, including maintenance
workers, operations foremen, the maintenance general foreman, environmental
control personnel and the plant general superintendent.  All levels of U.S.
Steel personnel, including the general superintendent, impressed on GCA that
the company had made an honest commitment to debugging the cars and improving
car availability.


                                        59

-------
                            TABLE  14.    MAINTENANCE  PROGRAM  DETAILS  OBTAINED FROM  PLANT  VISITS


(No.

Plant
of cars)3
Maintenance Maintenance Work area
frequency workers assigned description Spare parts
to cars

Comments

Clairton
(7 H-III, 1 H-2 cars,
several spares)
J&L/Indiana Harbor
(2 H-3 cars)
(no spare)
As needed,  day
turns,  7 days/week
                       One 8-hr turn/week
                                           20, total full-time
                                           assigned to car
                                           maintenance
                                           Maintenance  supervisor,
                                           1 mechanical foreman,
                                           1 electrical foreman,
                                           Millwrights,  motor
                                           inspectors on rotating
                                           basis.
                         Battery area, set up          Inventory  and  orders
                         area.  Concrete jacking pads  tracked  on computer.
                         under construction (out-      spread around  plant.
                         doors).  Offsite car shop.
                         Proposed bui Id ing .
                                                                                               Parts
                        Outdoor siding.  Designing
                        "pit" with utilities,
                        storage*
                                                                          Company  reported extensive
                                                                          inventory.   "Everything
                                                                          recommended  by Chemico."
                                                                                                                              Computer listing of  repairs
                                                                                                                              planned.  Management  appears
                                                                                                                              fully supportive of main-
                                                                                                                              taining cars.
                                                                                                                              Experienced maintenance
                                                                                                                              personnel assigned  only
                                                                                                                              to day turns.
Republic/Cleve land
(2 H-3 cars)
(one spare )
Republic /Warren
(2 H-3 cars)
(one spare )
                       Revolving ,  10-day
                       schedule
                       Revolving, 14-day
                       schedule
Day turn — 4 mechanical ,
2-4 electrical,  4 mill-
wrights,  2 pipefitters.
Backturns — 2-3 workers
available.

6 maintenance
workers assigned to
entire  coke plant .
Additional  workers
available as needed.
                                            Enclosed building with
                                            jacking pad and mock trans-
                                            fer station for alignment.
                                            Additional jacking pad
                                            on battery siding.

                                            Outdoor siding with
                                            utilities.
                                                                                                 Extensive ,  reportedly much
                                                                                                 greater  than  recommended
                                                                                                 by  Chemico.
                                                                                                 Not  reported
Republic /Youngs town     One  8-hr turn /week
( 1 H-3 car,  no  spare)

Shenango               One  8-hr turn/week
(1 H-2 car,  no  spare)
Not specified  by
company.

18-worker  crew, many
involved in  startup.
                                            Outdoor siding with
                                            utilities available.

                                            Outdoor siding with
                                            utilities, some storage.
                                                                                                 Not  reported
                                                                                                 All  parts recommended by
                                                                                                 Chemico.
aNuraber of spare  cars  a  function of number of batteries on-line.

-------
U.S. Steel/Clairton - Maintenance Program Described to GCA
During April 1982 Status Meeting

     USS described the recently-implemented Maintenance Information Management
(MIM) system for tracking car maintenance and repair.  USS felt the
programmable controls were especially troublesome, but their ability to keep
the controllers operating was improving as the plant gained more experience.
USS commented that they (at Clairton) had no previous experience with
programmable control equipment which hindered troubleshooting during the first
year or so of operation.

     Tony Fazio, Envirotech Vice President, noted that the Chemico system
components are interrelated and somewhat complicated relative to other coke
battery equipment.  Envirotech/Chemico had always recommended that USS assign
one individual to be responsible for overall car maintenance and training of
operators and maintenance workers.  Mr. Fazio also indicated they have always
recommended that problems be addressed immediately to insure spare car
availability.

     The USS Maintenance Superintendent described the maintenance organization
as consisting of two departments, both reporting to himself.  The water
treatment system and heating plant are maintained by the boiler house
maintenance department while the land base transfer unit and the cars are
maintained by another department.  The two Department Heads reportedly meet
daily to plan work and coordinate outages.

    • The Envirotech/Chemico onsite coordinator left the plant in November
1981.  The monthly car review meetings between Envirotech/Chemico and USS
reportedly stopped in August 1981.

J&L/Indiana Harbor

     Each car (no spares) is scheduled for one 8-hour preventative maintenance
turn per week.  Major problems that sideline the car are addressed on an as
needed basis during the week.

     One maintenance supervisor was reportedly responsible for the two cars.
One mechanical foreman and one electrical foreman assigned to the cars on a
semi-permanent basis are assisted by several millwrights and motor inspectors
assigned on a rotating basis.  J&L reported that the most experienced
maintenance workers are assigned to the day turn, and they usually work on
major problems that occur during second or third shifts.  Minor problems
occurring during the second and third shift are usually addressed quickly, if
the cause of the problem can be found according to J&L.  However, major
problems that develop during second and third shifts usually sideline the car
until the more experienced day turn workers are on duty.

     Car maintenance is performed on a siding adjacent to the batteries.  J&L
reported their engineering department was designing an unenclosed "pit" to
facilitate work underneath the car.
                                       61

-------
Repub1ic/Cleve land

     The maintenance area is enclosed with a building ("the barn") housing
utilities and repair equipment.  A jacking pad system enables lifting the cars
for access underneath.  Another jacking pad system is installed in the turnout
near the battery.  A "dummy" transfer station in the barn allows prealignment
of the charging arm prior to set-out on the battery.

     Routine maintenance to each car in the barn occurs on a revolving 10-day
schedule.  Normal preventive maintenance is performed according to an
established checklist.  Corrective maintenance of problems experienced during
recent car operation is also conducted.

     Daylight turn maintenance personnel consist of four mechanical, two to
four electrical, four millwrights, and two pipefitters.  Generally, at least
two to three maintenance personnel are available during back turns.  Republic
noted that approximately 5 to 7 days (three people) are required to pre-stage
charging arm alignment with the "dummy" transfer station in the barn.  Minor
maintenance is performed at the turnout area near the battery which has a
second jacking system.

     Republic indicated that their spare part inventory is quite extensive,
containing far more spare parts than recommended by Envirotech/Chemico.

Republic/Warren, Youngstown

     Limited maintenance information was available from RSC/Youngstown for
their single car.  Generally, the car is run until a disabling breakdown
occurs according to plant representatives.  The frequency of such breakdowns
was not reported by the company.

     At Warren, Republic stated that six maintenance workers per turn inspect
and lubricate all coke plant machinery including the cars.  After performing
these routine duties, all six are assigned to problem areas around the plant,
including the cars.  The following additional maintenance workers are
available for the day turn as needed (for the cars or other plant equipment):
maintenance general foreman, electrical and mechanical foreman, millwrights
and pipe fitters.

     Republic stated that during the two week period the spare car is off-line
at Warren, 2 to 4 coke plant maintenance workers generally spend approximately
2 to 4 hours per turn exclusively on the car.

Shenango

     Routine maintenance on Shenango1s single H-II car is performed during one
8-hour turn per week  (Wednesday) and involves examining each car system using
a check-list.  Shenango indicated that if routine maintenance is not performed
weekly, disabling problems develop.  The routine program consists of the
following:
                                      62

-------
      *   Brakes  and  hydraulic  system inspection;

      •   Cleaning jets  of  foreign matter,  inspecting jet  isolation valves;

      •   Debris  removal from traction drives;

      •   Tamping track  ballast,  removing  spilled  coke from rails;

      •   Examining all  electrical, mechanical,  and  instrumentation systems;

      •   Check engine oil,  filters,  belts,  etc.

 The 18-worker maintenance crew  available for car work consists  of three
 instrumentation personnel (two  for the cars,  one for water treatment system),
 four millwirghts,  two pipe  fitters, two garage mechanics,  two electricians,
 and two to  five laborers.   Shenango indicated that many of the  same people
 involved in car startup  currently perform  car maintenance.   The company  noted
 that maintenance  worker  turn-over was very low.

      Car maintenance  is  performed in  an open area  to the northwest  of battery
 No. 4.  The area  contains a pit for access  underneath the  car.   Utilities
 (water,  air,  and  electricity),  and some storage  are  available at the site.
 Shenango reported that their spare part inventory  includes  all  parts
 recommended by Chemico,  excluding expensive  items  such as  the heater coils and
 diesel generator.

      During the plant visit,  Shenango emphasized that  their maintenance
 program was designed  to  maximize  car  availability  in order  to demonstrate that
 a spare  car was unnecessary.

 AVAILABILITY DATA

      Data describing  car availability were  requested  from each  company,  and
 EPA,  state  and local  regulatory agencies.  The data  summarized  herein are
 based, on the  number of pushes caught  and scrubbed  divided by the number  of
 pushes during that time  period.

 H-III Availability Data

      Availability data for each Clairton H-III system  appears in Figures 1
 through  5.  Monthly averages of all operating Clairton batteries combined
 appears  in  Figure 6.  Figure 7  shows production of the Clairton plant.

      Availability data for H-III cars  at J&L/Indiana Harbor and
Republic/Warren appear in Figures 8 and 9,  respectively.  All H-III
availability  data were supplied by the  respective steel company.

H-II  Availability Data

     Availability data for H-II cars for Bethlehem/Bethlehem Battery 5
Shenango and J&L/Pittsburgh Battery P-4 appear in Figures 10, 11 and 12
respectively.  Consistent with the H-III data, the  H-II data are based on the
number of pushes caught and  scrubbed divided by  the total number of  pushes.

                                        63

-------
X
(9
  0
UJ
>
o

u.
o
z <
UJ
o
OL
UJ
0.
100


 90


 80


 70

 60


 50


 40


 30

 20


 10
                                             BATTERIES 1,2 ond 3 OFF-LINE
                                             STARTING JANUARY, 1982
                                HOT  IDLE
AVERAGE AVAILABILITY
       = 42%
                    o
                    o
   00
                                                                    _L
                      M
                        M
                J   J

                1981 -
N
J   F
 1982
M
       Figure 1.  Availability data for H-III serving Batteries 1, 2 and 3 at
                 U.S.  Steel/Clairton.   Average shown for  7 months operation,
                 March 1981 through December 1981, excluding hot idle downtime.

-------
                         PERCENT  OF  OVENS  CAUGHT
                                AND SCRUBBED
  n
  ro
co w
•  CT1
  H-
c/a M
n- H-
n> rt
(D «<
O PJ
H rt
P) pi
H-

rt o
O M
  M
  M
  CO
  (D
  H
  00

  W
  P
  rt
  rt
  (D
  CO

  »j
  V

  oo
  vo

-------
                               99
                        PERCENT  OF  OVENS  CAUGHT

                              AND  SCRUBBED
                     —   ro   o*
                     o   o   o
  •n
  H-
  CM
rt <
  01
<=! H-
CO M
rt H-
fD rt
  (U
H Hi
rt O
  PC
  I
  CD
  n>
  t-t
  (D
  i-i
  V!
             i...

-------
                            PERCENT  OF  OVENS  CAUGHT

                                    AND  SCRUBBED
—   rv>   oi   4.
oooo
a*
o

o
                                               
  rt
  rt
  H-
  (D
  cn
  V£>


  B
  Cu
                •«- c.
                  •n
09
   



   O



   z
(O
00
ro

-------
                                   89
                         PERCENT  OF  OVENS   CAUGHT

                                AND  SCRUBBED
  H-
  OP

  i-i
  n>
pj >
rt <
  (a
G H-
•  M
CO P
•  
  OQ

  bd
  (13
  rt
  rt
  (D
  en

  NJ
  N3
  Is3

-------
   100-1

g  90-
at
a  80-
g  70-
to
«  60-
5  50-
o
u.
o
%
40-

30-

20-

10-
                POSHING EMISSION CONTROL CARS

                 PLANT TOTAL AVAILABILITY

                          1981
                                                                  POSHING EMISSION CONTROL CARS

                                                                    PLANT TOTAL AVAILABILITY
                                              (69.1)
                                                                             1982
       J^N  FE
              FEB MAR APR MAY JUN JUL AUG SEP OCT NOV  DEC  JAN FEB MAR APR MAY JUN  JUL AUG  SEP OCT NOV DEC
                                                            ,   »
             Figure  6.   Availability of all operating H-III systems (combined) at
                         U.S. Steel/Clairton (supplied by  U.S. Steel).

-------
                                          NUMBER  OF  OVENS
09
C

fD

~j
Pi
3
rt
O
CL

O
rt
H-
O
3

Co
rt
rt
O
3
o
^
!^
cn
CO
fD



V



CJ
rt
fD
fD
    M   fr
    O   O
o  o   o
    I   I
                                                    ™"  —   "•  ~  mm   IM
                                                09  O  IS>   *  *  09   O
                                                o  o  o   o  o  o   o
                                                O  O  O   O  O  O   O
                              C-
                                      O  H

-------
                  u
+
Oi >£*
o n
0 0
0 H-
n d"
a. n>
H- 3
3 rt
09 CO
rt Oi
O rt

c-i a-
(^ o
f rt


*r3 O"*
h-1 01
pi rt
n rt
H- (D
0 ^
00 H-
ro
Cf CD
o
rt O
Zf O
o
o c
01 i-i
>-t i-!
CD (I)
o-
o
C H-
rt 3

O C_
Hi C
co n
n t-'
< \O
H- 00
0 t-
n>

' 1

rt
o
o

fl>
h^
01
rt
O
il
n>
^
h{
o
i-i
u




H-
OQ
H
fD
OO
p. <^
(X 01
H- H-
rt M
H* 01
o cr
3 H-
01 M
M H-
D--5

rt pa
Oi 01
rt
3 Oi
O
rt HI
O
Oi il
 (11
rt
Hi
11 C_H
O (?^
S f*
•'^^
M M
i-tf 3
> a.
H-
O 01
1 3
01
ffi p3
t-H 0)
jj-
O
H

5£J
O
n
CO
^v
rt
o

r>
01
hf
CD

rt
s:
o

cr
0)
rt
n>
H-
CO
to
00
(C
oo
       PERCENT OF OVENS CAUGHT AND SCRUBBED


        0080080008
        1
             1
                 1
                     1
                          1
                              1
                                  1
                                       1
                                           i
                                               i
ox

£u>
                      VDu>
     \
     \
    - k

           x>
           i -i
                                       mx

                                       »*
                                     P
                                     ?5

                                     Si
                         -

                          •s

-------
                                 ZL
               PERCENT OF OVENS CAUGHT AND SCRUBBED
H-
(TO
P5
cr
D-
Hi
O
M
M
(D
•O
o
*r
fD
0
CT
«!
o

n
CO
n>
i-i

rt>

o
P
m
                      ro
                      O
                    OJ
                    O
tn
O
CD
O
00
0?
00
no
                                                       0)

-------
  H-
  •s
PERCENT OF OVENS  CAUGHT AND SCRUBBED
              *    «•    01    -«i    a
              o    O    o    o    c

                                                T

                                                        T
                                  T
                                                                   ID
                                                                   o
                                                                           5
                                                                           o
                                                                                  w-o

                                                                                  8S

                                                                                  5*0
                                                                                  x>
                                                                                  • c
o
3
tt>

O
CO
  p.
                                                                                      >
                                                                                      z
                                                                                      o
o
P *
-------
PERCENT  OF OVENS CAUGHT AND SCRUBBED
                                  §-
                                  c
                              ro
                              O
                                         O
                                                   OB
                                                   O
                      

OQ C 3) C C U> 0> X ro o cr H- u> 00 o a. rt 05 t-h O CO S34 fD 0 01 3 00 O O 0 fD O B) i-t cr 03 rt rt fD t-l H- fD cn J ^_ /1 oo


-------
                        PERCENT OF OVENS CAUGHT AND SCRUBBED
  H-
  OQ
  e
s
n>
sa
(B

D4 ^
PJ rt
rt PJ
rt
n> MI
  M
  M


  Pi
  rt
  rt
  rt
  (D

-------
     The Bethlehem data were compiled from daily plant records supplied to EPA
by the company.  Some entries in the Bethlehem data package were illegible.
However, it was possible to fairly accurately compile a list of ovens not
caught and scrubbed, and the causes as shown in Tables 15 and 16 for 1979 and
1980, respectively.  In addition, Table 17, supplied by Bethlehem Steel,
provides more car availability details for 1980.

     Car breakdown data compiled from J&L reports to EPA regarding the H-II on
Battery P-4 in Pittsburgh appear in Table 18.  Note that substantial downtime
was incurred from construction of the new Minister Stein system and
unspecified work on the door machine.  For the 1-year period from 2/14/80
through 2/23/81, J&L reported an average availability of 22 percent based on
total operating hours.

     Problem areas at Shenango are described in the Trip Report, and
summarized in tables shown in this report Appendix.
                                        76

-------
TABLE 15.  H-II DOWNTIME REPORTED FOR BETHLEHEM/BETHLEHEM
           BATTERY NO.  5 IN APRIL AND MAY 1979.
            Reason
Total pushes
not scrubbed3
       Accumulator leaks
       Isolation valve problems
       Diesel fuel pump change

       Seal pump and A/C problems

       Leak in temperature well

       Junction box ground

       Heater flame failure

       Air regulator line break

       Low water levels

       High storage tank level

       Low water temperature

          TOTAL DOWNTIME,
            April-May 1979
     947


     173

      22

      15

      12

       8

       4

       3

    	2

    1186 pushes
       aTotal number of ovens pushed during the
        2-month period not supplied by company.
                              77

-------
     TABLE 16.  li-II DOWNTIME REPORTED BY BETHLEHEM/
                BETHLEHEM BATTERY NO. 5 IN  1980
                (entire year)
Number of
Cause of downtime occurrences
High pressure pump failure
Diesel overheating
(radiator problem)
Brake failure, problems
Jet and high pressure pump
leaks
Isolation valve problems
Wheel bearing problems
Drive motor problem
Heater flame failure
Limit switch problem
TV camera problem
OVERALL 1980 DOWNTIME =
Total pushes, 1980 =
16
9
8
2
7
2
4
12
84
3

Total pushes
not scrubbed
1,110
769
643
393
312
236
194
163
2
80
4,081 pushes3
28,296 pushes
Note:  85% availability, subtracting out ovens not scheduled
       to be scrubbed.

aDoes not agree with Table 17; data are reported herein as
 supplied by company.
                              78

-------
      TABLE 17.  MONTHLY AVAILABILITY DATA FOR H-II ON
                 BATTERY NO. 5 AT BETHLEHEM/BETHLEHEM
Month
1980
January
February
March
April
May
June
July
August
September
October
November
December
TOTALS
# ovens
pushed
2,848
2,749
2,916
2,690
2,711
2,098
2,039
2,046
1,953
2,046
1,980
2,220
28,296
# ovens
scrubbed
1,770
2,038
2,650
2,357
2,463
1,827
1,858
1,846
1,640
1,865
976
1,682
22,972
% ovens
scrubbed
62.1
74.1
90.9
87.6
90.9
87.1
91.1
90.2
84.0
91.2
49.3
75.8
81.2
# ovens
planned
"No Scrub"
64
74
124
185
195
95
77
79
120
80
22
167
1,282
# Ovens Not Scrubbed = # ovens pushed - # ovens scrubbed
                           28,296     -      22,972
                            5,324

# Unscheduled "No Scrub" = # ovens not scrubbed - # planned "no scrub"
                                  5,324         -      1,282
                                  4,042

(Planned "no scrub" represents ovens for which use of the system
was not planned for a variety of reasons).
                              79

-------
TABLE 18.  J&L/PITTSBURGH CHEMICO H-II BREAKDOWN REPORT SUMMARY
           FOR 2/14/80 - 2/23/81 ON BATTERY P-4
Date
2/15/80
2/16
2/21
2/22
3/6
3/7
3/9
3/11
3/14
3/15
3/16
3/17
3/18
3/19-20
3/21-22
3/22-23
3/22-23
3/24-28
3/30
3/31-4/4
4/5-7
4/8
4/8-12
4/13-15
4/16-17
4/18
4/20
4/20
4/21-5/1
5/2
5/2-3
5/3-4
5/4
5/5-6
5/6-7
5/7-7/18

7/18-19
7/20-26
7/28-29
7/30-8/2
8/2-6
8/6
8/8-9
8/9-10
8/11
Reason
Broken wire
Broken hydraulic line
Broken hose
Flame failure
(#5 door machine-broken shaft J
[#5 door machine-motor limit short]
Replace hydraulic fluid
Hydraulic problems
Maintenance '
[#5 door machine-straighten coke guide]
[#5 door machine-repairs]
Heater coil problem
Hydraulic & electrical short problem
[#5 door machine]
High pressure pump seal
[#5 door machine-burnt wiring)
Bad dump plungers
High pressure pump breakdown
Hydraulic pump problem
[#5 door machine-OSHA mods]
Diesel engine overheating
[#5 door machine]
Recirculatory pump failure
[#5 door machine]
Flame problem in heater
[#5 door machine]
[#5 door machine-OSHA J
I #5 door machine-door jack]
[#5 door machine-OSHA]
[#5 door machine-coke guide]
Water supply problem
Lost motor on diesel
[#5 door machine-coke guide]
Broken hydraulic line
Electrical failure
A.C. generator failure

Car travel problem
Tilt box trouble
Problem with quench
Work on P-4 Wharf
Broken air line
Broken hydraulic pipe
Work on l'-4 Wharf
Clean-up coke spillage P-4 Wharf
Broken hydraulic pipe
Total outage time, hrsa
0.5
120
4.5
13
6.75
0.75
1
2
11
6
2
6.2-S
11
18.25
25
26.5
26
80
14
50
46
17
88
46.23
37.5
8.75
11.75
2
134.5
12
11
6.25
5.5
17
39. 5
1781
(1.5 months)
23.5
155
32
71.25
82
4.75
12
19
15.5
                             (cont iuued)
                               80

-------
                          TABLE  18 (continued)
Date
8/12
8/12-14

8/15
8/16
8/16
8/21
8/22-23
8/24-28


8/29-30
8/30
8/31
9/1
9/3
9/4
9/5
9/6
9/7-8
9/9
9/10
9/11
9/11-27
9/29
9/29-30
10/3-5
10/10-14
10/14-11/14

11/15-19

11/19-22
11/22-23
11/24-27
11/27-2/18

2/18-20/81

2/20-21/81
TOTAL OUTAGE
Reason
Work on P-4 Wharf for Min. Stein system
Trouble with haul cable & R.R. switch
P-4 Screening Station
Broken hydraulic pipe
Trouble with dump box
[#5 door machine-air compressor]
Work on P-4 Wharf for M. S.
Work on P-4 Screen Station
[Battery problem-repair door on diesel
room struck by coke guide & repair #5
door machine]
Bad coil on dump box
l#5 door machine breakdown]
Flame failure
Clean-up P-4 Screen Station
Would not dump
Work on #5 door machine
Work on P-4 Screen Station
Pusher off tracks
High pressure pump failure
Work on P-4 Wharf Screen Station
Broken hydraulic pipe
Work on M.S. Push Control Station
Hole in heater tube & bad combustion fan
Work on #5 door machine
Problem w/ temperature control on heater
Track work
Hydraulic cylinder bearing
M.S. System work

Clearance problem with pillar at P-4
Wharf of M.S. System
[#5 door machine]
Broken hydraulic line
Flame failure
Flame failure, rec irculatory pump
problem, broken hydraulic cylinder
Water sprays, AC recirculat ing pump &
track problem
Hydraulic leak
REPORTED
TOTAL OPERATING TIME
AVAILABILITY

Total outage time, hrs.
9.5
46.75

4.25
22.25
17.5
8
24
96


5.5
6.5
14.25
8.5
1.5
10
9.5
6.5
23
8
11.5
8
382.5
10
9.5
63
96
744
(1 month)
99.5

57
19
64
2010

36.75

2b
7084 hrs
9072 hrs
22 percent
aActual ovens  not  caught  and scrubbed is not available; battery P-4 is
 normally operated at  approximate 111 push/day, i.e., 4.6 pushes/hr, average,
                                      81

-------
                                  REFERENCES
1.  Patton, R. S.  Hooded Coke Quenching System for Air Quality  Control.
    Iron and Steel Engineer.  50(9):37.  August 1973.

2.  Rudolph, H. and S. Sawyer.  Engineering Criteria for a Hooded Quench  Car
    System.  Iron and Steel Engineer.  54(3):27.  March 1977.

3.  Hooded Quench Car System Controls Coke Pushing Emissions.  Iron  and Steel
    Engineer.  55(3):83.  March 1978.

4.  Car order summary sheet provided by Envirotech/Chemico.
                                     82

-------
                 APPENDICES A-E

TABLES FROM TRIP REPORTS LISTING  H-II  and  H-III
  SYSTEM PROBLEMS REPORTED BY  STEEL  COMPANIES
                      83

-------
           TABLE  A-l.   HOT  CAR PROBLEM  SUMMARY DESCRIBED BY U.S. STEEL
                       IN SEPTEMBER  1981
       Problem
        Result
      Solution
Coke spillage


SS clearance



TV camera reliability



Stucki bearing failure

Box tilt limit switch
Frequent track cleaning,
potential derailment

Lack of combustion stack
clearance  limits inter-
changeability

Lack of vision, downtime
Excessive car rocking

Switch failure-operator can't
determine box position
Increase SS volume
(tests underway)

Remove portion of pro-
truding beam on SS
Increased physical pro-
tection, purge air lens
cleaning, wire relocation.

New design

New switch design
Weak springs

Ross valve modification


Standardize wiring


Dump cylinder line


Straight brake shoe


Separate 110 supply


Cover air receivers

Air receiver gauge
Excessive rocking

Poor performance of box
dump cylinders

DC circuit wiring plugs not
all interchangeable

Poor hose design, failure
of box dump cylinders

Excessive brake wear
TV and light wires in ex-
posed position, shorted

Falling coke damage

SS box dump cylinders
Install stabilizers

Modify cylinder controls
to improve reliability

Standardized plugs
Redesigned hose and
connections.

Convert to conventional
design; i.e., wrap-
around brake shoe
Moved wires inside
chassis for protection

Partial solution

Air pressure gauge in
operator's cab
 Note:   Items above double line were described to GCA/EPA by coke plant
        management at 15 September meeting.  Items below double line were
        discussed on 16 and 17 September during plant inspection.
                                      84

-------
           TABLE A-2.   H CAR PROBLEM SUMMARY DESCRIBED  BY  U.S.  STEEL
                       IN SEPTEMBER 1981
        Problem
        Result
    Solution
 Quench  tower  limit  switch
 positions vary

 Jet valve leakage
 Electric inverter mal-
 functions
 Femco signal malfunction
Power rail icing
Power pick-up problems
Traction drive motors
Stucki bearing failure
Charging station
alignment

Track deterioration
Onboard hot water tank
corrosion
 Different  positions,  poor.
 interchangeability
 Standardize  switch
 location
 New  valve  to  increase  scrub-  Ongoing discussion with
 her  flow are  malfunctioning   Chemico
 Electric  congestion  causes
 failure of AC-powered  equip-
 ment.  Quick  troubleshooting
 and  repairs difficult.

 Pusher can't  communicate
 with hot  car

 Dead spots cause power loss
 and  inverter  malfunction
Broken arms, long replace-
ment time, shoe wear

Several problems with motor
design-see text
Bearing failure causes car
rocking-charging arm mis-
alignment

Multitude of charging
station problems
 New  inverters  on  order
 Increased number of
 transformer couplings

 Add second power pick-up,
 steam trace rails
 automatic inverter re-
 activation equipment

 Add pick-up arm, new
 design

 Motor supplier accepted
 responsibility for
 repairs

 New design being tested
See text
Due to car weight, de-        New track on 13, 14, and
railment possible, dif-       15 - temporary repairs
ficult to align charging arm  on rest of plant
Ultimate tank failure
Investigating anti-
corrosion additive
Air compressor belt
covers

Set screw spring
cannisters
Poor access to onboard com-
pressor belts

Spring cannisters on hot
water transfer arm would
loose setting
Simplified cover removal
Teflon insert with set
screw added
                                 (continued)

                                     85

-------
                             TABLE A-2 (continued)
       Problem
        Result
     Solution
Standardize hydraulic
hoses
Insulate air lines
Different lengths on
charging arm caused break-
age, difficult replacement

Freezing-plugging
Convert to uniform length
for easier maintenance,
less wear

Temporary insulation to
be replaced with perm-
anent
Revise spotting lights
Malfunctioning air dryer
controls
Damaged by coke, difficult
location for replacement

Current pneumatic controls
unreliable
Lowered lights for better
access, steel shields

Converting to electric
controls
Electric timers-air
tanks
Pneumatic tank drains not
reliable
Converting to electric
controls
Duct expansion joint
Controls to avoid
stacks
Problems in maintaining
neoprene joint

Cars programmed to stop
if SS box tilted, but
need final hardware
Working with Chemico-
no immediate solution

Install hardware
Pivot bearing bolts
Bolts holding charging arm
loosen, loose alignment
Stronger bolts plus
keepers
Note:  Items above double line were described to GCA/EPA by coke plant
       management at 15 September meeting.  Items below double line were
       discussed on 16 and 17 September plant inspection.
                                      86

-------
        TABLE A-3.   STATUS OF H-III CAR PROBLEMS  AS  REPORTED BY  U.S.  STEEL3 IN  APRIL  1982  STATUS MEETING
                      Problem
                                                  Effect
                                     Solution
                                   Status  as of
                                     4/20/82
              Traction drive motors
00
              Power pickup problems
              Inverter failure
             Charge Ana Hoses/Cables
             Hydraulic system solenoid
             Hydraulic syste
             Moisture in air lines
             Hot rail freeze-up
             Expansion duct
             deterioration
Lead wire shorting


Field coil shorting

Bore elongation

Excessive shoe wear,
2-hr arm replacement  time

Car must be removed from
service to repair
Damage from reversed
set-out cables

Too long,  wore,  non-
standard lengths,
custom fabricating

Solenoid failure
prevented  fluid  return
to reservoir

Difficult  due to lack
of schematic, isolation
valves

Brake line and coke box
duxp cylinder freeze-up
Car shutdown due to
power loss

Safety problem,
car off-line for
replacement
Shorten wires,
fix to frame

Repairs by supplier

Unknown

Simplified 6-wire
design to 2-wire

Added 3rd inverter to
allow repairs while car
in service

Added diode to prevent
failure

Standardized hose lengths
to reduce replacement time


Rewired circuitry
Hew system schematics
drawn, valves installed
New filters,  coalescers
only partially effective;
will add mechanical
separator

Steam tracing proven
effective

Working with Chemico
Complete


60 percent complete

Working with GE

Complete
                                                                                                  Complete on one car -
                                                                                                  Inverters back-ordered
Complete


Complete



Complete - two cars



Complete
                                                                                                  Mechanical separator
                                                                                                  tested,  not yet installed
Complete
Several ideas,  untested,
still a problem
                                                                (continued)

-------
                                                        TABLE  A-3  (continued)
                        Problem
                                      Effect
                                     Solution
                                   Status as of
                                     4/20/82
               Separator support failure    Fatigue due  to  vibrations
00
CO
               Brake shoe wear
               Charge arm alignment
               Valve leakage
Land base pressure
sensor failure

Water quality problems
               Jet valve leakage
                             Excessive  wear,  frequent
                             replacement

                             Excessive  downtime
                             for realignment

                             Split body valves -  poor
                             sealing
Cannot transfer water,
downtime to repair

Sparger tube plugging,
onboard tank corrosion,
valve problem
                             Water  loss
                                                          Adding stiffners,
                                                          repairing supports
Converted to larger,
wraparound shoe

Developed quicker
realignment procedure

New gasket material,
improved torquing
procedure

Plan to test new pressure
sensor on LB No. 7

Will add deaerator for
corrosion control.
Other problem solutions
not discussed

Problem appears solved,
although early to tell
                                                          Complete - one car working
                                                          on two cars,  will repair
                                                          rest

                                                          Complete
                                                          Complete
                                                                                                     Future improvement
                                                                                                     Future improvement
                                                                                                     (dearator onsite)
                                                          (Complete)
               aProblems appear in order of discussion at meeting.

-------
                 TABLE  B-l.   LAND  BASE  PROBLEM SUMMARY
           H-III PROBLEMS DESCRIBED  BY J&L/INDIANA HARBOR
                            IN JANUARY  1982
    Problem
       Result
     Solution
Maintaining COG
combustion in
central heating
plant

Low water temperature
Intermittent water
overheating

Poor control of treated
water hardness
Ruptured boiler tubes
Poor control of
water temperature,
burner flameout
and overfiring

Controls prevent
transfer to H car
if temperature and
pressure are too
low

System shuts down
Occasional carbonate
plugging of sparger
tubes in land base
mixing tank
North boiler damaged
by freezing; south
boiler tube failure
under investigation
Switching to
natural gas
Installed recircu-
lation line
Recirulation line
(see above)

Planning to improve
coagulation system
controls, install
hardness monitor and
increase sparger
tube openings

Recent problem,
under study
                              89

-------
            TABLE B-2.  HOT CAR AND COKE GUIDE HOOD  PROBLEM  SUMMARY

                 H-III PROBLEMS DESCRIBED BY J&L/INDIANA HARBOR
                                IN JANUARY  1982
        Problem
        Result
   Solution
Excessive car rocking
Coke guide hood warpage
Coke spillage
Hot box dump cylinder
High moisture coke -
poor hot car drainage

Hot car warpage
 Hot car  limit  switch
 tilt malfunctions
Hot car hit coke guide


Occasional repairs


Frequent track cleanup,
damage to cables, wires,
hoses

High maintenance of
valves and solenoid

Coke quality affected


Distortion of box


Box does not return
to proper position
Installed shock
absorbers

Designing water
cooling sprays

Extended push ram
head, coke distri-
bution improvement

Continued
maintenance

None reported
Unspecified design
changes

Reworked  limit
switches
                                        90

-------
                      TABLE B-3.   H-CAR PROBLEM SUMMARY
               H-III  PROBLEMS DESCRIBED BY J&L/INDIANA HARBOR
                               IN JANUARY 1982
        Problem
       Effect
                                                          Solution
Charging arm alignment
and limit switch
Track deterioration
Brake shoe wear
Pickup arm shoe wear
Air dryer controls
malfunction
Realignment approxi-
mately 3 months.
Short-duration mal-
function approxi-
mately every turn
Charge arm alignment
problems, potential
car derailment
Original shoes
lasted 2 to 4 weeks

Rapid shoe wear
Moisture in system
Air compressor overheat   Car shutdown
FEMCO communication
Power rail icing
Occasinal poor
communication
Power interruption
shuts car down
TV camera electrical
problems due  to poor
sealing of protective
boxes
Poor camera
operation
Realign as necessary.
Improve limit switch
operation.  Operator
and maintenance per-
sonnel improving
troubleshooting ability

Frequent rail shimming and
ballast tamping.  In-
vestigating rail welding
and ballast impregnation
to stabilize

New shoes, last approxi-
mately 1-1/2 months

Hot rail redesign,
frequent shoe re-
placement

Installed larger
capacity dryer

Installed cooling fans,
some problems remain

None - problem no more
severe than with other
FEMCO units in coke
plant

Heat tape installed on
rails near quench tower.
Still a problem during
severe weather.  Car
restart buttons moved
into operator's cab

Improve weatherproofing.
Can operate car without
cameras (according to
plant representatives)
                                  91

-------
                            TABLE C-l.   LAND  BASE PROBLEM SUMMARY AS  REPORTED BY RSC/CLEVELAND
                                  Problem
                                                                     Result
                                                                                                 Solution
                        No water circulation  in heater
                        tubes during  low  fire
                                   Destroyed two sets of
                                   heater bundles,  flame
                                   impingement
                                Partial solution,
                                blowdown system
                                with recirculation
                                installed
10
ro
                        Unreliable  heater  system
                        controls
                        Poor COG firing
Undersized combustion
air fans

Heater system control panel
melting

Standby air compressor
malfunction

Water treatment system
                        Temperature  loss  in
                        water linos
                                   Simultaneous heater firing;
                                   poor flame-out  detection,
                                   constant  monitoring

                                   Btu content  of  OOG low;
                                   poor heating control
                                                          Low heater output
                                                          Heater inoperative
Failure to automatically
actuate; heater inoperative

Constant maintenance,
intermittent water
hardness problem

Difficulty in maintaining
design water temperature
Interlock system
installed, new
process controls

Converted to natural
gas, instrumentation
changes

New fans with increased
hp (partial solution)

Partial solution,
insulation added

Redesign, rewiring
interlock system

Micro-processor
controls installed
                                                                  Discontinued use
                                                                  of thermo-siphon
                        Steam hammer  problems
                                   Piping  shifted,  damaged
                                   block valve  flange  and
                                   seals
                                Installed bypass
                                valve
                        Charging  arm  limit switches
                        FEMCO  communication system,
                        noise  and  heat
                                   Limit  switch  freeze-up
                                   from moisture fallout

                                   Water  transfer problems,
                                   constant maintenance
                                Vent stack and lean-to
                                installed—still problems.

                                Cooling and shield
                                protection installed

-------
    TABLE C-2.   HOT CAR AND  COKE  GUIDE  HOOD PROBLEM SUMMARY AS  REPORTED BY R3C/CLEVELAND
       Problem
           Result
          Solution
Coke spillage
Frequent track cleaning,
damage to hydraulic and
electrical cables
Partial solutions (see text)
Track deterioration
Hot box dump limit
switch failure

Brake shoe wear
Hot car TV camera
reliability

Running lights
poorly sealed
Potential car rocking,
increased charging arm
alignment

Inaccurate dump box position,
recurring maintenance

Numerous brake shoe
replacements

Difficult to maintain in
constant operation

Bulb life reduced, frequent
burn-outs
Partial solution, tie plates
redesigned and splice joints
constantly shimmed

Installed additional hot rail,
added back-up limit switches

Pressure sensor installed
None, considering new housing
Plexiglass enclosures
installed
Hot box dump cylinders
Seals worn
Replacement

-------
                  TABLE C-3.  H-CAR PROBLEM SUMMARY AS REPORTED BY RSC/CLEVELAND
        Problem
                                       Result
                                                 Solution
Power pick-up arm and
shoe damage

Inverter failure

Resistor bank panel
failure
FEMCO communication
Operator cab water
leakage

Stucki bearing
failure
Traction drive motors
failure

Air compressor and
hydraulic motors

Jet isolation valves
Air dryers undersized
Power losses (coke production),
exposed wire destroyed
Protective cover added, conduit
installed
Power surge caused malfunctions     Delay mechanism installed
Resistor shortcircuiting from
water and coke breeze
infiltration

Verbal communication inadequate
for hot box spotting

Damage to control panels and
cables/wiring

Inability to roll,  flat spots
developed
Numerous holdout coil
replacement

Maintenance access to brushes
difficult

Intermittent,  considerable
water leakage

Fluidic control of air valves
difficult
Redesigned seal and ventilation
added
Infrared spotting device and radio
interlock mechanism added

Continual problem
Partial solution; upper set
replaced with steel pads, lower
set to be replaced

Unspecified changes
None reported, continual problem
Rewelded flanges
New, larger dryers to be installed

-------
   TABLE D-l.  H-III LAND BASE SYSTEM PROBLEM SUMMARY FOR REPUBLIC STEEL/
               WARREN AND YOUNGSTOWN
         Problem
         Result
         Solution
Insufficient gas flow
and heat output with
COG combustion
Heater failures, burner
flameouts.
Converted to natural gas,
changed all gas lines and
instrumentation.
No water flow through
tubes during low fire
("soak")

Oxygen release with
high temperature water
Hot spots and tube
warpage.
Water lines and valves
became pitted and
corroded.
Installed recirculation
line.
Currently use nitrogen
purge.
Plugged filters; poor
control of water
hardness with river
water

Transfer mechanism
failure
Heater tube bundles
"blew-up", piping
deteriorated.
Bent hydraulic
cylinders, mechanism
drift.
Partial solution using
city water; scaling still
problem.
Installed additional limit
switches.
Isolation valve
leakage
By-pass valve leakage
Accidental turn-on.
Water loss.
Installed check valves;
replaced seat, stems, and
air operated valve.

Replaced valve seals.
                                      95

-------
     TABLE D-2.  H-III HOT CAR AND COKE GUIDE HOOD PROBLEM SUMMARY FOR
                  REPUBLIC STEEL/WARREN AND YOUNGSTOWN


         Problem                   Result                    Solution


Coke spillage             Daily track cleaning,      Partial solution; modifica-
                          equipraent damage,  track   tions to coke guide, hot
                          deteriorating.             box,  and pusher ram.  (See
                                                    text  for plant differences.)

Coke box warpage          Excessive distortion to   Partial solution; reinforce
                          box lines.                 frame.   Experiments with
                                                    various liners-little
                                                    success.

Excessive car rocking     Potential for collision   Redesigned rail splicings
                          and charge arm alignment  (Warren).  Replaced steel
                          problems.                 pads  on trucks (Youngstown).

Long hydraulic hoses      Rubbed on car; coke       Reduced hose lengths.
                          abrasion damage.

Hot box limit switch      False indication to       Changed limit switch to
tilt modifications        operator, premature       override timer mechanism.
                          tripping of switch.
                                      96

-------
           TABLE  D-3.   H-CAR  PROBLEM  SUMMARY  FOR WARREN  AND  YOUNGSl'OWN
         Problem
         Result
         Solution
Oxygen release from
water

Track deterioration
Charging arm alignment
Exposed wiring-junction
boxes
Water lines and valves
became pitted and eroded.

Charge arm alignment
problems.
Clamping mechnism
failure; storage tank
water shifting.

Moisture and coke
abrasion, failure.
Mixed wiring at junction  Troubleshooting was time
boxes                     consuming; difficult to
                          interpret wiring
                          diagrams.
FEMCO communications
Cyclone separator
replacement
Water leakage into cab
Air compressors over-
heating
Weak signal from H-car
to land-based station.

Deterioration and
cracks developed.
Control panel, elec-
trical cable mal-
function.

Continuous maintenance.
Added nitrogen purge.
Replaced tracks twice;
reduced coke spillage (see
text).

Provided balance thrust to
feed air motor base; shimmed
battery side of car.

Placed junction boxes inside
car; replaced wiring with
covering material.

Isolated wiring; installed
fuses at key locations.
Increased signal strength.
FEMCO units still problem.

Converted unit into multi-
piece construction for
quicker maintenance.

None reported.
Installed exhaust fans.
                                       97

-------
                      TABLE E-l.  H CAR PROBLEM SUMMARY
           SHENANGO H-II PROBLEM SUMMARY BASED ON GCA INSPECTION OF
                                 FEBRUARY  1982
       Problem
        Result
        Solution
High-pressure pump
cavitation

Jet isolation valve
wear

Jet plugging
Brake shoe holder/hanger
assembly failure

Spatial confinement
Heater failure
Erosion of pump housings
and seals.

Jet wear, and continued
leakage.

Poor scrubbing, can't
shut off water.

Broken assemblies,
derailment occurred.

Maintenance access
difficult.

Frequent flame-outs,
other malfunction causes
car shutdown.
None apparent.  Using
stainless steel housing.

Partial solution, higher
maintenance (see text).

Remove bugles, blow out
jets.

New design installed.
Careful scheduling of
maintenance crews.

Increased pilot tube
length, added third
scanner for increased
detection.
High oxygen content of
water
Teflon pad wear

Radiator clogging

Poor location of traction
drives

FEMCO signal malfunction
Electric hot water
transfer valve

Ductwork abrasion
Pipe and high-pressure
pump corrosion.
Car rocking.

Diesel overheating.
Stainless steel pipe
now used, caustic added
to water, 02 scavengers.

Modified pads.

Steam clean radiator.
Clogging from coke breeze. Routine cleaning.
Slight communication
problems.  Occasionally
prevents quench water
transfer.

Valve failure, numerous
rebuilds.

Buildup of coke breeze.
None reported.
Replaced with an air
valve system.

Frequent cleaning and
patching, complete
rebuild anticipated in
future.
                                   (continued)

                                        98

-------
                            TABLE E-l  (continued)
       Problem
        Result
        Solution
Camera and wire exposure
to heat

High influent solids
content to treatment
system
Duct expansion joint
Weather proofing
deterioration.
Replaced, and added
wrapping material.
Increased filter plugging. Additional maintenance
                           above normal.  Changed
                           filters, added activated
                           carbon before main
                           filter.
Deteriorated seal.
Replaced neoprene seal.
altems above single line were described by Shenango as major, and those below
 as minor areas of concern.
                                      99

-------
                     TABLE E-2.  HOT CAR PROBLEM SUMMARY

           SHENANGO PUSHING PROBLEM SUMMARY BASED ON GCA INSPECTION
                               OF FEBRUARY 1982
        Problem
        Result
        Solution
Brake shoe holder/hanger   Broken assemblies,
assembly failure           derailment occurred.
Coke guide hood/hot box
seal material
Destruction of original
material, escape of
emissions.
                           New design installed.
New material installed,
problem not solved.
Teflon pad design

Moisture on box limit
switch

Dump cylinder hoses
Brake cylinders
Wear of original pads.     Modified pads.

Freeze-up in winter.       Considering new switch
Broken hydraulic hoses     Frequent hose replace-
from coke and vibration.   ment.
Pin wear, freezing.
Replacement, maintenance.
altems above single line were described by Shenango as major, and those
 below as minor areas of concern.
                                      100

-------
                                   APPENDIX F

                   METHOD D:   PROCEDURE  FOR OBSERVING  VISIBLE
                     EMISSIONS EQUAL TO  OR GREATER THAN 20%
                             OPACITY DURING PUSHING
PRINCIPLE

     The visible emissions equal to or greater than 20 percent opacity emitted
during the push cycle are timed by an observer located on the cokeside of the
battery.  In addition, the maximum opacity observed during the coke fall
period is recorded.

DEFINITIONS

Push Cycle

     The period of time commencing when the cokeside oven door is removed and
ending when the coke is quenched.  Further, the push cycle is divided into
three periods, as follows:
          A to B = 1:   Period from time door comes off to time start of ram
                       movement.

          B to C = 2:   Period from time start of ram movement to time all coke
                       is in hot car.

          C to D = 3:   Period from time all coke is in hot car to time of
                       quench.

Coke Fall Period

     The period of time B to C or 2, above.  .

Quench

     Cooling the red hot coke to a temperature below its ignition temperature
at the quench tower.
                                      101

-------
Quench Tower

     The structure where the quench is carried out,  normally made of wood or
brick and designed to conduct the steam plume generated during the quench into
the a tmo sphe re.

Hot Car

     The railroad car into which the coke is pushed; sometimes called the
quench car.

Opacity

     The degree to which emissions reduce the transmission of light and
obscure the view of an object in the background.

PROCEDURE

Position

     The observer makes the observation from the cokeside of the battery,
where a clear view of the push can be obtained.  In general, a location on the
ground, in the cokeside yard, outside the hot car tracks approximately
perpendicular to  the observed oven is acceptable.  However, the observer is
not restricted to being on the ground level, but may make the observation from
some elevated level.  If multiple observers are recording the same emissions,
the observers should be positioned as closely to each other as feasible.
Observer position is recorded on the data sheet.

Observations

     During the push cycle, the observer watches all the potential emission
sources.  These include the oven and  the hot car.  Upon observing any visible
emission with an  opacity equal to or greater than 20 percent opacity, as
determined against any contrasting background,  an accumulative stopwatch is
started.  The watch  is stopped when the visible emission goes below  20 percent
and is  restarted  when a visible emission equal  to or greater than 20 percent
reappears.  The observer continues this procedure for  the entire push cycle;
using either  separate stopwatches  for each  of  the three periods  of  the cycle
or noting  the time of each period  and recording on the data sheet while
employing one or  two stopwatches.  The time recorded on the data sheet at the
end of  each period is the  total  time  on the stopwatch  for that period.   In
addition to  the above,  the observer also mentally notes the densest  opacity
occuring during the  coke fall period  and at the end of the  push  cycle records
on  the  data  sheet the maximum opacity observed.

      The following visible  emissions  are not  timed:

      •     Steam vapor;

      •     Visible emissions  generated from  jamb cleaning;


                                    102

-------
     •    Visible emissions  from the  removed  door; or

     •    Visible emissions  from the  pushside of  the oven.
     In some cases, coke battery operators  will  keep  the  standpipe  cap open
during the push cycle.  These emissions should be  regarded  as  pushing
emissions.  However, on some inspections emissions from the standpipe caps
will not be observed.  In this situation,  a note should be  placed on the  data
sheet indicating that the standpipe cap was open and  not  read.
                                     103

-------
                                  TECHNICAL REPORT DATA
                           (Please read Instructions on the reverse before completing)
1  REPORT NO.
 EPA-340/1-83-019
                                                          3. RECIPIENT'S ACCESSION NO.
4. TITLE AND SUBTITLE
     Envirotech/Chemico  Pushing Emissions
     Control System  Analysis
            6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
         Peter D.  Spawn and Michael R. Jasinski
            8. PERFORMING ORGANIZATION REPORT NO.

               GCA-TR-82-32-G
9 PERFORMING ORGANIZATION NAME AND ADDRESS
        GCA Corporation
        GCA/Technology Division
        213 Burlington Road
        Bedford, MA  01730
 2. SPONSORING ACFNCY NAME AND ADDRESS
        U.S. Environmental Protection Agency
        Stationary  Source Compliance Division
        401 M.  Street, S.W.
        Washington, D.C.   20460
                                                            REPORT DATE
                                                                        April  1983
                                        	1
                                                           10. PROGRAM ELEMENT NO.
            11. CONTRACT/GRANT NO.
                   68-01-6316
                   ISA 1,  WA 8
            13. TYPE OF REPORT AND PERIOD COVERED
                      Final
            14. SPONSORING AGENCY CODE
 5. SUPPLEMENTARY NOTES
 6. ABSTRACT
        This  report summarizes a 3-month  study of the 21 Envirotech/Chemico one-spot,
   mobile  pushing emissions control systems  currently installed  at  coke plants
   operated by five domestic steel companies.   The study investigated;  (1) design
   differences between cars; (2) startup,  operational and maintenance problems reported
   by each steel company; (3) mass and visible emissions test  data;  (4) car avail-
   ability; and (5) solutions to operating problems implemented  and/or under consi-
   deration.   Information in the report was  developed through  detailed discussions
   and  field  inspections at four steel companies; discussions  with  EPA engineers
   and  review of EPA, state and local regulatory agency files; office discussions
   with the equipment vendor; and review  of the technical literature.  The objective
   of this report is to factually present information available  through the above
   sources.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
    Iron and Steel Industry
    Air Pollution
    Coking
    Performance Tests
    Availability
    Maintenance
                                              b.lDENTIFIERS/OPEN ENDED TERMS
Pollution Control
Envirotech/Chemico
                             COSATl Field/Group
 18. DISTRIBUTION STATEMENT
    Release to Public
19. SECURITY CLASS (This Report)
      Unclassified
21. NO. OF PAGES
           114
                                               20. SECURITY CLASS (This page)
                                                     Unclassified
                                                                          22. PRICE
 EPA Form 2220-1 (R«y. 4-77)
                       PREVIOUS EDITION IS OBSOLETE

-------