United States
            Environmental Protection
            Agency
Region V
230 South Dearborn Street
Chicago, Illinois 60604
EPA-905/2-79-002
June 1979
            Air Programs Branch
            Management and
            Technical Procedures
            for Operation and
            Maintenance of Air
            Pollution Control
            Equipment
Do not WEED. This document
should be retained in the EPA
Region 5 Library Collection.

-------
  MANAGEMENT AND TECHNICAL PROCEDURES
     FOR OPERATION AND MAINTENANCE
  OF AIR POLLUTION CONTROL EQUIPMENT
                  by

       PEDCo Environmental, Inc.
          11499 Chester Roagl
        Cincinnati, Ohio  45246
        Contract No. 68-02-2535
              Task No. 7
           Principal Author
        David B. Rimberg, PH.D.
      North American PEMCO, Inc.
       Bardonia, New York  10954
           Project Officers

Dr. Indur Goklany and Mr. Henry Onsgard
          Air Programs Branch
 U.S. ENVIRONMENTAL PROTECTION AGENCY
           REGIONAL OFFICE V
           CHICAGO, ILLINOIS
               June 1979

-------
              DISTRIBUTION AND DISCLAIMER STATEMENT


     This  report  is issued  by the United  States Environmental
Protection Agency  (U.S.  EPA)  to  report technical  data  of in-
terest  to  a  limited  number  of  readers.   Copies are available
free  of charge to  grantees,  selected contractors,  and Federal
employees in limited quantities from the Library  Services Office
(MD-35), Research Triangle Park,  North Carolina  27711 or for a
fee  from  NTIS  5285   Port  Royal  Road,  Springfield,  Virginia
22161.

     This report was furnished to the U.S. EPA by PEDCo Environ-
mental, Inc., 11499 Chester Road, Cincinnati, Ohio  45246 and by
subcontractor,  North   American   PEMCO,   Inc.,    P.O.  Box  655,
Bardonia,  New  York   10954   in   fulfillment  of Contract  No.
68-02-2535, Task No.  7.   The contents of this report are repro-
duced  herein as received from  PEDCo Environmental,  Inc.   The
opinions,  findings,  and conclusions  expressed  are those of the
authors and  are not necessarily  those of the U.S. EPA.  Mention
of company or product name is not to be  considered as an endorse-
ment by the U.S. EPA.
                  U,S. Environmental  Protection Agency
                                11

-------
                            CONTENTS
Figures                                                       v
Tables                                                       vi
Acknowledgement                                             vii

1.   Introduction                                             1

     1.1  Background                                          1
     1.2  Scope of the report                                 2

2.   Maintenance Management of Air Pollution Control
       Equipment                                              4

     2.1  Definitions                                         4
     2.2  The maintenance organization                        5
     2.3  Maintenance planning, scheduling,  and work
            measurement                                       7
     2.4  Preventive maintenance                              9
     2.5  Maintenance performance evaluation                 12
     2.6  Spare parts and material control                   13
     2.7  Maintenance budgets                                14
     2.8  Training and education                             14
     2.9  Contract maintenance services                      16
     2.10 Vendor contribution to poor equipment
            performance                                      16
     2.11 Conclusions                                        17

3.   Technical Aspects of the Design, Operation, and
       Maintenance of Baghouses                              18

     3.1  Background                                         18
     3.2  Baghouse components and operational
            parameters                                       18
     3.3  Baghouse operation and maintenance                 24

4.   Technical Aspects of the Design, Operation, and
       Maintenance of Electrostatic Precipitators            46

     4.1  Electrostatic precipitator components and
            operational parameters                           47
                                111

-------
                      CONTENTS (continued)
     4.2  Electrostatic precipitator operation
            and maintenance                                  55
     4.3  Wet electrostatic precipitators                    75
     4.4  Wet electrostatic precipitator operation
            and maintenance                                  75

5.   Technical Aspects of the Design,  Operation,  and
       Maintenance of Scrubbers                              78

     5.1  Scrubber components and operational
            parameters                                       81
     5.2  Scrubber operation and maintenance                 87

6.   Technical Aspects of the Design,  Operation,  and
       Maintenance of Items Common to All Air Pollution
       Control Equipment                                     95

     6.1  Introduction                                       95
     6.2  Exhaust ducts                                      95
     6.3  Gas pretreatment                                   96
     6.4  Inlet baffles                                      96
     6.5  Hoppers                                            96
     6.6  Fans                                               97
     6.7  Exhaust stacks                                     99
     6.8  Conclusions                                       100

7.   Inspection, Safety, and Maintenance Equipment          101

8.   Summary                                                105

Bibliography                                                106

Appendix A                                                  109
                               IV

-------
                             FIGURES
Number                                                      Page
  1       Typical Organizational Chart for a Small- or
            Medium-Sized Plant                                 6

  2       Sample of Routine Daily Inspection Report for
            Shaker Baghouse                                   27

  3       Sample of Maintenance Checklist for Shaker
            Mechanism                                         28

  4       Sample of Routine Daily Inspection Report for
            Pulse-Jet Baghouse                                29

  5       Sample of Internal Inspection Report for
            Shaker Baghouse                                   31

  6       Preoperation and Inspection Checklist for
            Electrostatic Precipitator                        56

  7       Operating Inspection and Maintenance Checklist
            for Electrostatic Precipitator                    59

  8       Preoperation and Inspection Checklist for
            Scrubber                                          88

  9       Operating Inspection and Maintenance Checklist
            for Scrubber                                      91

-------
                             TABLES


Number                                                      Page

  1       Baghouse Troubleshooting Guide                      36

  2       Replacement Parts for Baghouse Filters              44

  3       Summary of Problems Associated with Electro-
            static Precipitators                              63

  4       Replacement Parts for Electrostatic Precipi-
            tators                                            69

  5       Typical Troubleshooting Chart for an Electro-
            static Precipitator                               70

  6       Guide for Interpreting Abnormal Meter
            Readings                                          74

  7       Scrubber Classifications                            79

  8       Replacement Parts for Scrubbers                     92

  9       Typical Troubleshooting Chart for Scrubbers         93

 10       Basic Inspection and Safoty Equipment              101

 11       Basic Testing Equipment                            102

 12       Maintenance Tools                                  102

 13       Power Tools                                        103

 14       General Equipment                                  103
                               VI

-------
                         ACKNOWLEDGEMENT


     This  report  was prepared  for the U.S.  Environmental  Pro-
tection Agency  by PEDCo Environmental,  Inc.,  Cincinnati,  Ohio.
The EPA  project officers were  Indur  Goklany, Ph.D.,  and  Henry
Onsgard.   The project director was Mr. Donald J.  Henz, P.E., and
the project manager was Mr.  Thomas A.  Janszen.  Principal author
was  David  B.  Rimberg,  Ph.D.,  North  American  PEMCO,  Inc.,
Bardonia, New York.
                                VI1

-------
                            SECTION 1

                          INTRODUCTION
I.1  BACKGROUND

     Regardless of its type and function,  processing or manufac-
turing equipment that is electric or mechanical requires service
and maintenance to some degree, and air pollution control equip-
ment is  no exception.  With  the adoption of  the  Clean Air Act
Amendments in  1970  and  1977,  not only have the capital expendi-
tures for  this equipment grown  exponentially, but the costs to
operate and maintain it have also skyrocketed.  To emphasize the
importance of  operation  and maintenance (O&M), the Ninth Annual
Report  (December  1978)  of the  Council  of Environmental Quality
indicated that 1977 expenditure for O&M was 3.1 billion dollars.
This figure includes  both  public and private sectors,  exclusive
of  mobile  sources.   Projected costs  for 1985 are  9.4 billion
dollars, with  cumulative • costs  from  1977 to  1985  estimated at
76.2 billion  dollars.  The cost of lost production,  caused by
defects  and deterioration  through wear and  tear,  is calculated
at  three  to  four  times  the  O&M amount.  By 'no  means  are these
conditions inevitable;  many  can be averted  or  retarded,  along
with  their costly consequences.   Preventive maintenance  is  a
means to this  end.

     Air pollution abatement  equipment is purchased,  operated,
and maintained under conditions quite  dissimilar to processing
and manufacturing  equipment.   Unless  the  abatement equipment is
being  used for  product  recovery,  it  is procured because  of
government regulations.  Besides requiring  large capital expen-
ditures, with the associated O&M costs, it produces no return on
investment  (ROI).   In  the   absence  of  strong   regulatory  and
managerial enforcement,  there is a  strong  tendency to minimize
O&M even if a  quality piece of control equipment was purchased.
In  the  event  that a source is cited for an emissions violation,
subsequent  enforcement  of  the  regulations  could  result  in
derating,  curtailment,  or even  shutdown  of  the  process equip-
ment.

     Following  the  initial  startup  period,  the  new  abatement
equipment  is   frequently  neglected  because  of   the  overriding
demands  of production.  The  maintenance department  thus finds
itself with a rapidly deteriorating piece of equipment.  Because

-------
government regulations required the procurement of the abatement
equipment, it was probably purchased on a low bid basis,  thereby
resulting in  an  inferior quality  product.   In due  course,  the
user  blames  the  vendor  for  selling  him  inferior  and  poorly
designed  equipment,  and the vendor  blames  the user  for  inade-
quate preventive  maintenance.   Both parties  usually have valid
arguments.   It is  under  these  conditions  that  air  pollution
control equipment is  usually purchased and  operated.  The ulti-
mate solution for both government and industry is for the abate-
ment equipment to be  considered  an integral part of the process
and treated with equal respect.


1.2  SCOPE OF THE REPORT

     With the  aforementioned costs and considerations surround-
ing the procurement, operation, and maintenance of air pollution
abatement equipment, this report will supply agencies and indus-
trial users with  management and  technical guidelines for effec-
tive  operation and maintenance of air pollution control equip-
ment.  The report is divided into  four major topics:

     Section 2
     Maintenance  management of air  pollution  control equipment

     Sections 3 through 5
     Technical aspects of the design, operation, and maintenance
     of  air  pollution  control  equipment  (baghouses,  electro-
     static precipitators,  scrubbers)

     Section 6
     Technical aspects of the design, operation, and maintenance
     of  items common to  all  air pollution  control equipment

     Section 7
     Inspection, safety, and maintenance equipment

     Section 2 includes  discussions on organizing a maintenance
operation, maintenance  job  planning and scheduling,  maintenance
work  measurement,   preventive  maintenance  (PM),  maintenance
material  control, budgets,  and training,  emphasizing air pollu-
tion control equipment.

     Sections  3 through 5 include  discussions of the three major
types  of air  pollution control equipment:   baghouse,  electro-
static precipitator (ESP),  and scrubber.   Emphasis is placed on
simplified startup, operating,  and shutdown procedures.  Routine
inspection procedures are supplemented with detailed checklists.
A general program is presented for troubleshooting air pollution
control equipment.  Case histories  for a pulse-jet baghouse, dry

-------
and  wet  electrostatic  precipitators,  venturi  scrubber,  and
packed tower  are  included in  the appendix to  provide  the user
with a sample program for improving equipment performance relia-
bility.

     Section  6  discusses  equipment  and  components  that  are
common to all  types  of air pollution control equipment,  such as
hoods, ducts, fans,  and stacks.

     Section 7  provides the details of  the  tools  and equipment
required to  satisfactorily perform  inspections  and maintenance.

     The ultimate purpose of this report  is  to provide  manage-
rial  and  technical  methods and  procedures for the  user of air
pollution control equipment  to maintain his  equipment,  service
it on  a periodic  basis,  and to keep it within emissions  limita-
tion  and  opacity standards.   It will  provide details  for the
hypothetical user,  regardless  of the type of equipment  used or
the type of maintenance performed.

     It would not be possible in a work of this size to cover in
detail every management  and technical  aspect  of  air pollution
control equipment maintenance.   An  attempt has been made,  how-
ever,   to  highlight  and develop in appropriate  detail the prob-
lems most commonly encountered.

-------
                            SECTION 2

                    MAINTENANCE MANAGEMENT OF
                 AIR POLLUTION CONTROL EQUIPMENT
2.1  DEFINITIONS
     Within the scop of this report,  a standard terminology will
be used.  In some cases,  these definitions may not coincide with
either national or international plant engineering standards,  or
with state or Federal guidelines:

     Deterioration:  Unfavorable and  undesirable  changes  in the
     condition  of  any  electrical  or  mechanical  components,
     assemblies,  or subassemblies.

     Defects:  The maximum amount of deterioration that could be
     tolerated.

     Drift defect:  Gradual development of defects.

     Random defect:  Sudden development of defects.

     Maintenance:  Actions that are performed to restore an item
     to an acceptable  condition and,  therefore,  to enable it to
     continue  to  reach its required  operating capacity.   Note:
     The  "acceptable  condition" can  be  set  by the organization
     executing the maintenance,  and  will probably vary from one
     company to another.   (Maintenance should not necessarily be
     equated wit-h  any  work  undertaken by a maintenance worker).

     Emergency maintenance:  Maintenance activities that must be
     performed  immediately,   or in  the near  future,  to  avoid
     serious consequences.

     Planned maintenance:  Maintenance carried out in accordance
     with a well-devised plan.

     Corrective maintenance:  Maintenance  specifically employed
     to restore equipment to its acceptable condition.

     Preventive maintenance (PM);   Maintenance  carried out  in
     accordance with  a planned  schedule  to  make  sure  that the
     equipment  adheres  to  an  acceptable standard.   Unfortun-
     ately,  the  word "preventive"  attracts  attention to  the

-------
     apparent goal of  the activity  (prevention)  instead  of the
     activity  itself  (periodic/predetermined  interval/planned
     schedule).

     Breakdown:   Any  sudden unavoidable failure of air pollution
     control equipment or  process  equipment to  operate  in  a
     normal and usual manner.

     Excess emissions:   An emission rate that exceeds any appli-
     cable standard of performance prescribed by Federal,  state,
     or local rules,  or that violates any condition in a permit.

     Malfunction:  Any  failure  of air  pollution control  equip-
     ment or process equipment  to operate in a normal and usual
     manner that is caused entirely,  or in part,  by poor mainte-
     nance,  careless  operation,   or  other  preventable  upset
     condition or preventable process equipment failure.


2.2  THE MAINTENANCE  ORGANIZATION

     The  single  most important ingredient  in effective mainte-
nance management  is  identification  of  qualified individuals to
effect  and  implement the maintenance  function.   Although plant
management  is  usually  well  aware of  the need  for maintenance
management, few programs  are  operating as they were intended to
operate.   Because  nearly  all  maintenance activities  are human
activities,  and are,  for the  most part,  controlled  by those
individuals  doing  the  work,  even the most  explicit inspection
checklists  and  well-written  procedures  (including  this report)
will not  achieve  the desired  goal unless the persons performing
the  work have  the  willingness  and integrity  to   execute  the
defined tasks.

     In  manufacturing  operation,  performance  output  can  be
measured through careful production control systems.  A malfunc-
tion of the system is immediately apparent, and often results in
poor production  quality,  reduced  product output, and failure to
meet a delivery date.  There is no reason to assume that mainte-
nance  operations  for   air  pollution  control equipment  cannot
similarly be  formalized.   The  job or  task being done,  however,
is usually  not  as  obvious,  and thus more attention must be paid
to the  routine requirements of the  maintenance  control system.

     The  O&M  of air pollution  control  equipment must generally
be included within the framework of an  existing  in-house pro-
gram.   Thus management must,  as  it  may  appear,  intrude upon an
already  overworked,  understaffed,  and  underfunded maintenance
department to integrate the new functions into the program.  The
equipment is  typically viewed  with  (a)  suspicion,  (b) caution,

-------
and  (c)  annoyance;  occasionally  it  is treated as  important and
primary to  the  overall manufacturing process  because its break-
down or  malfunction could  dictate the  level  of production for
the plant.

     To effect a viable maintenance program,  a support organiza-
tion must be available.   A typical  organizational chart  for  a
small- or medium-sized plant is shown in Figure 1.
                           PLANT MANAGER
                           PLANT ENGINEER
             MAINTENANCE
               MANAGER
PLANNING AND
 SCHEDULING
               FOREMAN
  CLERICAL
                                                     UTILITIES
                                                    SUPERVISION
               Figure  1.  Typical  organizational chart for a
                     small- or medium-sized plant.
     The  plant  manager's  primary  function  is  to  operate the
plant for maximum profits and minimum costs.   The plant engineer
has  the responsibility  to  see that  the plant  operates effec-
tively  and  continues  to  produce goods.   He is often also respon-
sible   for   environmental  matters:    noise,   OSHA  regulations,
in-plant  fumes,  dust and  odors,  air emissions, water effluents,
permit  applications,  and  codes  and  standards.   To  meet this
immense  responsibility,   which  includes  the performance  of air
pollution control  equipment, he must  create  a supporting organ-
ization around him.

     As indicated  in Figure  1,  the  plant engineer usually  finds
it  necessary to delegate the  maintenance function  to an  indi-
vidual  who,  for all practical purposes,  will  be  called the
maintenance manager  and  may,   in  fact,  be  an  engineer.   The
maintenance manager  must have a sound knowledge of manufacturing
machines  and  adapt  himself  to  include  air  pollution control
equipment.   The  maintenance manager must also possess management

-------
abilities,  since most of  his  working hours are spent in getting
the job  done  through people.   His most  critical  subordinate is
his foreman,  whose job it is to see that the workers are proper-
ly instructed and competent to maintain the plant.  The foreman
is the vital  link between management and job execution.  He must
know  his  workers and their respective  capabilities  to perform
certain jobs.

     Throughout this discussion,  the emphasis  has been directed
towards people  and  how they  could contribute  to  equipment per-
formance.   Prior  to  equipment  operation,  however,  in-house
support, such  as engineering  and purchasing,  becomes involved.
It has  proven to be extremely beneficial  to  the  performance of
air pollution control equipment to involve from the outset those
individuals who  can contribute to  its success—engineers, line
workers, and  others.  Sudden  changes in organization and opera-
tions  due  to  equipment acquisition  can be interpreted  by em-
ployees as actions  to  tighten management controls, produce more
work, and hence reduce job  satisfaction.

     The  installation  and  operation  of air  pollution control
equipment may precipitate the redesign or modification of either
a  formal or  informal maintenance  management information system.
Should  this  be  the case,  it is  incumbent on the maintenance
manager to:

          Clearly  define  and  identify  the  objectives  of the
          system

          Determine  effective  methods  of  work  planning  and
          scheduling

          Determine  methods of measuring and appraising mainte-
          nance performance

          Determine  the personnel required

          Adopt budget  and  financial control procedures

     Although  these are some  ingredients  of a maintenance man-
agement  system,  it  should  not be construed  as  a magic  formula
that  will  provide  the  best maintenance  organization for a par-
ticular plant.


2.3  MAINTENANCE  PLANNING,   SCHEDULING,  AND  WORK  MEASUREMENT

2.3.1  Planning  and Scheduling

     The  function of maintenance planning and scheduling  is as
follows:

-------
     Minimization  of idle  time.  (Only  30  to 40  percent of  a
     worker's time  is  spent using  his  tools; the  remainder  is
     spent  traveling to and  from the job,  acquiring  materials
     and supplies, waiting  for  other  phases  to be completed and
     for production equipment to be shut down.)

     Maximizing  the  efficient  use  of worktime,  materials,  and
     equipment

     Operating  at a level  that  is responsive to the  needs  of
     manufacturing production

     Before  a  maintenance  work order is  scheduled to  be  exe-
cuted,   it   must  be  planned according to  its scope,  priority,
sequence  of performance,   methods  and  materials  to  be  used,
safety  requirements, manpower,  time estimate,  and site availa-
bility.  The work order form,  which  usually emanates  from  the
production department,  is the mechanism that requests work to be
performed.    It  must  include   sufficient  information  for  the
planner and  scheduler to  determine  the  resources needed for the
project.   The  replacements  of  bags,  solenoid valves,  scrubber
nozzles, and ventilation  filters  for  ESP insulator compartments
are simple  requests  that can be  implemented with  little  addi-
tional  explanation.   More  complicated   situations,   such  as
troubleshooting  baghouse  high  pressure  drops,  require  greater
effort.

     The individual  who plans and schedules  the work order must
be  familiar not only with the  productive  system,  but  also  with
the major   components  of  the   air  pollution  control  equipment
(i.e.  pumps, blowers, conveyors).   He  should perform site visits
to  make periodic equipment  reviews.  Because of the  nature  of
maintenance,  this  person  must  be  able  to  modify plans  and
schedules  -frequently, and  see that  adequate  materials and spare
parts  are  available to execute the work order.  He should not be
restricted  to  the way things have  always been  done:   new pro-
cedures, standards, and equipment may  be appropriate.

     The time  for the  work to be performed may  be  scheduled
while  the  equipment  is  operating  or shut down.  It is desirable
to  perform  the  work  during regular  equipment  shutdown,  with
priority work  being  scheduled  first.   When  work schedules  must
be  changed,  substitute work orders  may  be necessary, thus maxi-
mizing available resources and hence the requirement for backlog
work orders.  Although there are scheduling techniques available
to maintenance management, such as the Gantt Charts and Critical
Path Methods  (CPM),  they will  not be discussed  in this report.

     Safety  provisions  must be planned  should  the work  order
require it.  Special clothing  (goggles,  masks,  boots,  gloves),
fire  and   electrical  protection,  ventilation,   barricades,  and
                                 8

-------
lights must  be  specified.  As an  example,  personnel performing
bag  changes  must  use  respirators,  hard  hats,  and  goggles.
Should it be  necessary to enter any type of  air pollution con-
trol equipment,  the worker  must  be accompanied by another indi-
vidual .

2.3.2  Work Measurement

     Regardless  of  the  type  or extent  of  the  work  being per-
formed by an individual or team,  or the materials used, a method
to  estimate  costs accurately must  be  available  to  the  mainte-
nance manager.  A method of measurement is needed as a basis for
product  pricing  and  costing,  improvement  of  worker effective-
ness, more efficient  manpower  utilization,  reduced costs of new
and/or improved  facilities,  efficient scheduling of preventive
maintenance,  and  identification  of worker education require-
ments .

     With  the ultimate  goal  of  reducing  costs  and improving
quality,   the methods  that  maintenance  management  can  use  to
measure  work  are  experience, historical  information,  and stan-
dard  data.    For  example,  experience  has  taught that  12 bags
require  replacement every month.   Therefore,  once  a  month the
manager  can estimate  the cost,  manpower,  and  materials  to  be
devoted  to  a specific task.   The  primary  disadvantage  of this
form  of  work measurement is  that periods of inefficiency and
ineptitude  are  not usually identified  since  "experience"  has
taught maintenance  management  that  "it has  always  been done
'that  way1."   With  new air  pollution  control  equipment,  no
experience  is available  to estimate the  time  required for pre-
ventive maintenance and repair.

     If  a particular  job  has been  performed  numerous times,
historical data may be available to estimate the  average perfor-
mance time.   If  the work is being  performed  in a manner satis-
factory to management, this may be considered  standard.


2.4  PREVENTIVE MAINTENANCE

2.4.1  Benefits of Preventive Maintenance

     In  addition  to  maintaining compliance with air pollution
emission regulations,  an air pollution control equipment preven-
tive maintenance  program will  enable  the user to accomplish the
following:

     Assure that production levels are not  affected

     Minimize maintenance cost

-------
     Maximize scheduled shutdown periods

     Significantly reduce  equipment  breakdowns,  downtime,  and
     malfunction

     Extend equipment life

     Reduce emergency repairs

     Reduce overtime

     Reduce overall maintenance and attendant repair costs

     Minimize spare parts inventory

     The more a plant  is oriented toward capital  equipment,  the
more it  can reap  the benefits of  a preventive  maintenance pro-
gram.  This  is true  because this  type  of plant requires more
maintenance than does a labor-intensive plant.

     By definition, preventive maintenance  refers  to activities
that fight  defects in existing  equipment without changing the
design of the equipment.   In the field of air pollution control,
however,   additional  onsite  and  in-house engineering  is  often
performed on the equipment to reduce user costs of operation and
maintenance.  Vendor  unfamiliarity with  the process,  or inade-
quate preventive  maintenance,  will often necessitate  equipment
modifications  and  redesign  to  accommodate  actual  operating
conditions.

2.4.2  Reasons for Minimum Preventive Maintenance

     In spite of the  tangible and intangible benefits of preven-
tive maintenance,  air pollution control  equipment nonetheless
remains  neglected.   Typical  reasons  given  for minimum mainte-
nance are summarized as follows:

     Attention and effort are better spent on process equipment.

     Pollution  equipment  and associated  components are of poor
     quality  because  they  were  purchased  on  a low bid basis.

     Plant personnel are not inclined to maintain equipment that
     is  dirty,  dusty, potentially hazardous,  and   inaccessible
     for service.

     Equipment  is  located  outside the plant building and  there-
     fore  often  goes  unnoticed  and  unattended  until  problems
     exist.

     Defects  and   obsolescence  of  the electric  and mechanical
     components are inevitable occurrences.
                                 10

-------
     Plant personnel  are  unwilling to  stock replacement parts,
     supplies,  and accessories.

     There are  not enough maintenance personnel and funds.

     Corporate  engineering  incorrectly specified  equipment and
     should have consulted the plant.

     No one  individual  is willing to manage and coordinate the
     maintenance function.

     Insufficient technical knowledge is present to diagnose and
     troubleshoot problems.

     Management  views preventive  maintenance  as  nothing  more
     than lubrication and cleaning on a scheduled basis.  *

     The position of  management  is  typically not to spend money
unless  the  return  on investment can  be realized  in  the  near
future.   The   acquisition   of   additional   skilled   workers,
materials,  spare parts,  and  power  tools  is  looked upon  with
great  caution  and skepticism, especially since the ROI  is not
likely to be felt for as long as 2 years.

     A  PM program  must  be   appropriately  introduced  to plant
management if  it  is  to  be enlarged and expanded.  At this junc-
ture, the attitude  of plant  management to maintenance could be:
"We  bought  it,  now you  take care of it."   The task of selling
the  preventive maintenance program  to  management should be well
thought out; especially regarding costs and advantages.   Some of
the  elements  critical  to   selling  the  program are  described
below:

     Identify  the  individuals in management and operations who
     have the  authority  to  make decisions, either  directly or
     indirectly.   (Do not avoid those persons who you think will
     not be responsive.)

     Discuss program  with maintenance workers  and  supervisors,
     because their  cooperation  and enthusiasm are  essential.

     Define a  means  to evaluate  the  effectiveness of  the  pro-
     gram.

     Estimate  project cost  savings,  man-hours, materials,  and
     similar items.

     Goals  and objectives should  be realistic; therefore,  the
     scope of the program should be small before a more compre-
     hensive one is planned.
                                 11

-------
     Clearly define  the equipment  and  components that must  be
     inspected and  maintained.   (Equipment instruction  manuals
     must be supplemented by worker information.)

     Compile checklists  that include not only  items to be  in-
     spected or maintained,  but  also  the  sequence of events  and
     operations.

     Estimate the frequency of inspection.

     These  ingredients,  plus a  presentation  of  the  overall
benefits of  the  program (as given  in 2.4.1), are essential  for
selling the  PM program.  If management wants to  streamline  the
proposed program,  it is generally  advisable to adhere  to  their
requests in order to initiate the program.   After  a given period
of  time/  with  the  necessary  appraisals  of  performance,  the
program will  probably  need  expansion and modification.   By  its
nature,  preventive  maintenance  is  dynamic and  constantly  in
flux,  and  close  monitoring  is needed to see that  management and
operations requirements are being fulfilled.

     The primary considerations in having the preventive mainte-
nance  program  approved  are  financial  ones.   When  the program is
developed,  budgets  must  be  estimated  with the  awareness  that
maintenance competes with production  for  funds.   The production
budget  is  usually based on  demand for  services,  and successful
competition  with production requires  the  use of  a method  to
calculate ROI.
2.5  MAINTENANCE PERFORMANCE EVALUATION

     The  resources  that  are  available to maintenance  are man-
power, material,  and equipment.  Of the  three,  the most diffi-
cult to  control  is  manpower,  as reflected in wage rates.  Labor
control can easily be effected through careful administration of
how, when,  and  where the work is to be performed.  The simplest
and  most  direct method  to measure manpower production  is  to
compare the man-hours  actually consumed to perform a particular
task with that  originally  estimated.   Significant and frequent
deviations from  the estimates require investigation.

     The  maintenance report is the most important mechanism for
effective  maintenance  control,  i.e.,  control of labor produc-
tivity.   It  should contain such  ingredients  as  the skills used
to  effect the work, associated labor  costs,  and comparison of
actual vs.  estimated man-hours.   It may also contain a compari-
son of the maintenance costs for a particular period or job with
comparable  costs derived from  some  base  period.  Although they
are indicators,  and not maintenance control functions, open work
                                 12

-------
orders  help  management monitor  the progress of the maintenance
function.  A  comparison between man-hours spent on planned work
and  those  on  unplanned maintenance, and the ability to forecast
the  completion of jobs  on schedule,  are additional maintenance
control indicators.

     As  an example  of the  use of  some of these  controls and
indicators, a  particular  baghouse  was having frequent bag fail-
ures;  the  cause was attributed  to  hot  cinders  being carried to
the  bags.  Excessive man-hours and bag replacement were obvious
consequences.    Emergency  baghouse  shutdowns,   coupled  with
several community complaints,  forced management to find a way to
solve  the  problem.   Spark arrestors were subsequently installed
and  the ROI  realized within 1  year.  The motivation to install
equipment  was  primarily  one   of  cost  savings;  air  pollution
abatement was  secondary.


2.6  SPARE PARTS AND MATERIAL CONTROL

     The introduction of air pollution control equipment (or any
equipment) to  a plant requires  the purchase of spare  parts and
supplies.  The types,  quality,  and costs incurred are but a few
of  the considerations to  be  reviewed.   The spare  parts  needed
are  those  typically associated  with  moving  and rotating parts.

     At the  outset,  critical  spare parts  should be identified.
This information is usually available  from  the equipment manu-
facturer.   With  equipment use,  plant  experience  is  acquired
thereby further identifying spare  parts  requirements.   In this
regard,  a  critical  part  is one that could  slow down  or  abort
production.  For  instance,  a  clogged scribber  nozzle may affect
emissions  somewhat,   but  substantial  mist  eliminator  buildup
would diminish  system flow rate.  An available spare set of mist
eliminator media  would immediately alleviate  the  problem,  thus
minimizing system shutdown.

     Replacement bags, nozzles,  gaskets,  hose  clamps,  and other
items  that are  changed  frequently should  be  in  ample  supply.
The  storeroom  personnel must be responsible  for this supply and
must maintain  an inventory information  system  to  provide  lead-
time to procure replacements.

     The materials  and spare parts inventory  for  air  pollution
control equipment may  vary according  to season, plant shutdown,
and  process  modification.  For  instance,  during winter  months
the  entrained  moisture  in compressed  air  lines to  pulse-jet
baghouse valves may  freeze and  cause unit disfunction.   Exces-
sive demand for replacement valves  and  bags  may occur,  necessi-
tating rebagging and process shutdown.
                                 13

-------
     Suppliers in  remote  locations and long  leadtime  items  are
problems  of great  concern to  maintenance.   Noncritical  items
must be  procured with  sufficient leadtime  to  avoid  emergency
situations.   It  is,  however,  difficult  to  justify  ordering
expensive  supplies  and equipment  when there  is  only  a  possi-
bility  that they may be  needed.   An  example  is  a  spare  high-
horsepower motor for a venturi scrubber fan.

     Cost considerations often  overlooked  are those  incurred to
store  spare  parts  and  materials.   Space,  recordkeeping,  and
additional  taxes  and insurance are also  significant  contribu-
tions to  the  overall  maintenance  cost picture.   Inventory costs
can  be  reduced  if  replacement items  can be procured locally.


2.7  MAINTENANCE BUDGETS

     A  financial  plan  for   the  procurement of  air  pollution
control equipment is usually thoroughly prepared.   Annual opera-
tion and maintenance budgets for air pollution control equipment
are estimated at 10 to 12 percent of the capital equipment cost.
This guideline  is reasonably accurate, but more  of  the details
pertinent  to  maintenance  supplies, labor,  and  equipment should
be  analyzed.   The  most  important element  of the  maintenance
budget  is  the  man-hour   estimate.   Man-hours may  be  further
subdivided  into  such  categories  as  inspection,  lubrication,
particular  process  equipment,  and air  pollution  control equip-
ment.  A major advantage of this method of budgeting is expendi-
ture visibility,  i.e.,  cost  control  and  the  ability to monitor
the flow of funds.

     In addition  to manpower  and  material budgets, the procure-
ment  of capital  equipment (high-power industrial vacuum clea-
ners,  for  example) should be  included in each  annual budget.
Since capital  equipment programs  can be  expressed  in terms of
ROI, management  is  more likely to approve these budget requests
than others.
2.8  TRAINING AND EDUCATION

     Regardless  of   the   type  of  equipment,  a  well-planned
training and education program is crucial to production improve-
ment  and  reliable  equipment  operation.   Management  usually
resists  these  programs  unless  excessive  operating  problems
arise.   In the case of operating and maintaining air pollution
control  equipment,  even  less attention  is given  to training.
Maintenance  management  often thinks  that the  line workers will
acquire the necessary knowledge "on the job."
                                 14

-------
     Besides the  maintenance workers, the  personnel who should
be familiar with  the  operation and maintenance of air pollution
control equipment are supervisors, planners, and schedulers.  At
startup,  the  operation  and  maintenance  department  should see
that  the  original  equipment  manufacturers provide  a  suitable
training program,  supported by the necessary instruction manuals
for  service  and  maintenance.   For intensive  training,  several
equipment manufacturers have  prepared video tapes in support of
classroom instruction.

     Instruction  at  the  training  sessions  should also  be given
by the  manufacturers  of  the subassembly components and systems.
For  example,   the  supplier  of   an  electrostatic  precipitator
should  include  the manufacturers of  the  transformer/rectifier
and  ash handling  systems at the  training  sessions.   If the air
pollution control  equipment contains  opacity  measurement capa-
bility, a  representative from the  instrumentation manufacturer
should also be present.

     The  training program  should be  devised  by both  user and
equipment manufacturer.   The  user must identify  the personnel
(skilled workers,  engineers) who  will  have some responsibility
for the equipment, and the manufacturers must gear their presen-
tation to this audience.

     Although this  approach appears to be  elaborate, it is the
only  reasonable  way  to  guarantee that the  equipment  will  be
operated  and  maintained  satisfactorily.    Unless  a  training
program is  defined  during  original  contractual  agreement,  it
usually does  not fall  within the  framework  of the  original
equipment capital  cost.   In this  case, plant  management may be
reluctant to fund it at a later date.

     Air pollution  control  equipment  usually  develops  problems
before management becomes more conscientious  about the  need for
training  and  preventive  maintenance.  If  management  does not
endorse an extensive training program, it is incumbent on opera-
tion  and  maintenance  management  to   measure  and evaluate the
long-range  outcome  of the  training  program,  especially  with
respect to ROI.

     Another consideration  in developing a training program is
the  amount  and  complexity of  the  abatement equipment.   A small
plant may have  only  one  piece of equipment, whereas a large one
could have numerous types and amounts.
                                 15

-------
2.9  CONTRACT MAINTENANCE SERVICES

     In  recent  years,  the  concept of  contract management  has
become  more  and  more  acceptable,  especially in  new  plants.
Plants  use  contract  maintenance  to  buy know-how  and  reduce
costs, while  still retaining  flexibility.   In-house  maintenance
functions,  however,   cannot  be  eliminated.   The  benefits  of
contract  maintenance,  with  emphasis on  air pollution  control
equipment, are given below:

     Plant  personnel  do not  have to  be thoroughly trained in
     equipment maintenance,  thus  allowing them to  devote their
     time to process equipment.

     Technological troubleshooting and problem diagnosis are not
     usually in-house resources.

     Plant personnel do not have the knowledge to improve equip-
     ment performance.

     Plant personnel may lack awareness of alternative supplies
     and suppliers.

     Expenditures for  larger crews,  repair  facilities,  tools,
     and measurement instruments are reduced.

     Previous experience  on similar equipment  and  applications
     can be used.

     Interpretations  of  causes  of component  failure   can be
     provided.

     Contract maintenance  programs  are more  effectively regu-
     lated and administered than are in-house programs.

     Dirty  and  hazardous  jobs  do not  have to be  performed by
     plant personnel.

     Fluctuating  workloads  due  to startup  and seasonal varia-
     tions can easily be handled.


2.10 VENDOR CONTRIBUTION TO POOR EQUIPMENT PERFORMANCE

     Even  the most  explicit procedures, guidelines, and  inspec-
tion checklists will not achieve desired goals unless the person
or organization performing the work has willingness, motivation,
and  resources to  do the job.  Because  nearly all operating and
maintenance activities are human activities, they are controlled
by  those  individuals  doing  the  work.   On  the  other  hand,  the
                                 16

-------
reader should not assume that the users of air pollution control
equipment are solely responsible for poor equipment performance.
Vendors also contribute in the following ways:

     Misapplication  of  equipment  due  to  unfamiliarity  with
     contaminants and process parameters

     A highly competitive  marketplace,  resulting in cost reduc-
     tion methods  that often have  a  negative effect on product
     reliability and component quality

     Inadequate and  inept  design for  ease of maintenance (i.e.,
     access  doors,  blind flanges,  internal  catwalks,  component
     accessibility)

     Insufficient performance monitoring instrumentation

     Improperly located pressure taps,  leading  to dust buildup
     and clogged air lines.

     Insufficient stock and inventory of component replacements.

     Primary interest  in product sales  (flange  to flange),  not
     total system design and installation.

     New  equipment  designs  that  are  inadequately tested  and
     evaluated in the field
2.11 CONCLUSIONS

     The  installation  and  operation  of air  pollution control
equipment covers a wide range of disciplines, from management to
technical aspects, plant  managers  to skilled workers, emergency
to preventive maintenance, and budgets to training.  Much of the
attention  in  this  field has  been  devoted  to  the  technical
phases, not  the  managerial  and administrative.  The reader with
sufficient  background should now  be familiar with  the overall
scope  of  the management aspect of the operation and maintenance
of air pollution control equipment.
                                 17

-------
                            SECTION 3

                TECHNICAL ASPECTS OF THE DESIGN,
             OPERATION,  AND MAINTENANCE OF BAGHOUSES
3.1  BACKGROUND

     This section  of the report provides the  user  of baghouses
with  sufficient  guidelines  and  procedures  to  enable  him  to
operate,  service,  and maintain this equipment in order to comply
with air  pollution emissions regulations.   It provides  details
on special equipment components;  procedures  for startup,  routine
operation,  shutdown,  inspection,  and maintenance;  and  recom-
mendations  for  spare parts  and materials.   A  sample  trouble-
shooting  case  history  is  presented in  Appendix A to give  the
user a program  for improving equipment performance reliability.
The principles of air pollution control equipment and mechanisms
of  contaminant  collection will  be discussed  only in terms  of
operation and maintenance.
3.2  BAGHOUSE COMPONENTS AND OPERATIONAL PARAMETERS

     Baghouses  are  categorized  according  to  their  cleaning
mechanisms:   shaker,  pulse  jet,  and reverse  air.   The  ingre-
dients common to all types of baghouses are:  air-to-cloth ratio
(filter rate),  pressure drop, cleaning  mechanism,  frequency of
cleaning,   filter  cloth  characteristics,   number  of  baghouse
modules, materials  of construction, and method  of handling the
collected contaminant.

     The  discussion  that  follows  describes  the  engineering
principles  and  comments  on components  that  cause problems  in
equipment operation and maintenance.

3.2.1  Air-to-Cloth Ratio (Filter Rate)

     The quantity  of  gas  (acfm)  passing  through  a  given area
(ft2)  of   filter  cloth  is  defined  as  the air-to-cloth  ratio,
filter  rate,  or   superficial face velocity.   Units  for  this
parameter are cubic feet per minute per square foot, or feet per
minute.   Physically,  the  air-to-cloth  ratio  represents  the
average velocity  with  which the  gas  passes  through the cloth
                                 18

-------
without regard to  the  fact that much of the area is occupied by
fibers.  For  this  reason, the  term "superficial face velocity"
is often used.

     Depending on the type of fabric and cleaning method, fabric
filters can  operate at air-to-cloth  ratios  of  15:1  and less.
Upon startup  with  new  and clean filter media, the pressure loss
may be  less than 0.5 in. H20.  After initial operation  (season-
ing or  conditioning),  the pressure loss may approach 2 to 3 in.
H20.  At some time, the collected particulates (filter cake) and
cloth must be cleaned,  by one or a combination of mechanisms, to
return  the  cloth  to  a  significantly  lower  pressure  loss.
Typical air-to-cloth ratio  for  shaker and reverse air baghouses
can range  from <1:1 to 4:1 with woven filter media.  Pulse-jet
cleaning can  use  5:1  to  15:1  air-to-cloth  ratios  with felted
filter media.

     The  air-to-cloth   ratio  is  a calculated  number  used for
design  and discussion  purposes,   and the  ratio should  not be
assumed to  exist throughout  the baghouse  media.  For instance,
the gas flow  entering  the baghouse may not be uniformly distri-
buted  and  may be channeled in  a preferential direction, resul-
ting in a  higher  ratio  in one section of  the  baghouse than in
another.   This  problem  may  be overcome  by providing turning
vanes,   flow splitters,  and baffle plates.

     From  an  aerodynamic point of  view,  the baghouse  does not
approach,   or  even come  close  to,  an  ideal  geometric shape for
gas flow.   It should also  not be  assumed  that all particulate
follows the air  streamlines  in the baghouse.  Gravity and other
forces  can  cause particulates  to  digress  from  the streamlines,
resulting  in  more  particulate being  filtered in one portion of
the baghouse than another.  Particulates measuring 5 pm or less,
however, will follow the air streamlines and behave similarly to
gas molecules.

3.2.2  Pressure Drop

     The resistance  to  airflow (pressure  drop)  provided  by  a
clean filter  cloth  is  determined  by the configuration and char-
acteristics of the  cloth and  filtering  velocity.  One  of the
characteristics  of  clean  fabrics  frequently specified  is  the
permeability,  which  is  defined  as  the air volume (ft3/min) that
will pass  through a square  foot  (ft2) of filter media  with  a
pressure differential of  0.5  in.  H20.  According to the type of
fabric  (yarn,  weave,  weight,  etc.), the permeability could range
from 15 to 100.   This  parameter is useful only in comparing one
type of media with another.
                                 19

-------
     In normal filter operation,  the  pressure loss is primarily
attributed   to   the  dust   filter  cake   and   cloth-entrapped
particles, with a  small  portion  of the pressure drop due to the
cloth  alone.  Other  than  collection  efficiency,-  the  primary
consideration in maintaining  normal operating  pressure  drop is
the energy cost to drive the  air-moving blower:  the higher the
pressure  drop, the more energy  consumed.   Continuous operation
at high pressure drops  also  seriously weakens the filter integ-
rity  and  structure.  In an attempt,  to alleviate some  of this
high pressure drop,  much attention has been  given to the cloth
characteristics  (fiber  diameter,  fiber  construction,  porosity,
cloth finishes,  backings, coatings).

     Although the  resistance  to the cloth  filter  arid dust cake
cannot  be separated  from  the total  resistance of  the  exhaust
system, the  operating characteristics  of the exhaust blower and
the duct  resistance will determine the overall baghouse resis-
tance.   If  possible,  the  user  of the equipment  should obtain
information  from  the vendor  regarding the pressure  losses in-
curred  because of  the system  ductwork,  without bags  being in-
stalled.   This   information  may  be  valuable  when  comparing
several equipment  designs,  because duct pressure  drop does not
contribute to filtration, only energy consumption,

     Typical operating pressures,  according to  the application,
can vary  from 3  to 10 in. H20.  As a rule of thumb, the pressure
drop squares as  air-to-cloth ratio (velocity) doubles.  Attempts
to  increase  the blower  flow  rate to  exhaust  contaminant more
rapidly  will seriously  affect  system pressure  drop.   By in-
creasing  the intensity  or  frequency of cleaning, it. is possible
to  reduce pressure  drops  to  levels  approaching those  of the
clean fabrics.  If this concept is carried too  far,, however, the
collection efficiency may be  adversely affected by damaging the
fabric  and  consuming additional  costs in  driving  the cleaning
mechanism.   The  selection  of an  operating pressure  loss is  a
matter  of trade-offs, and  may not necessarily  conform to  origi-
nal  design  values.   It  is  obvious,  therefore,  that monitoring
the pressure drop  across the  baghouse  is the single most  impor-
tant parameter indicating system performance*

3 •2 •3  General Design

     The  basic  difference between  one generic  type of baghouse
and  another is  the  cleaning mechanism (shaker,  reverse  air,
pulse  jet).  There are,  however, common components for each and
the  following  remarks  will  thus  apply regardless  of cleaning
mechanism.

     The  baghouse  casing  is  usually  fabricated of  light-gauge
mild  steel,  and  may  be  insulated to  prevent temperature  drops
                              20

-------
during operation.   In  applications handling  abrasive  materials
or corrosive gases,  a lining of corrosion-resistant material may
be necessary.  The filter bags within the housing are mounted to
a  tube sheet  with  hose,  ring,  or  spring-loaded  clamps.   The
clamps are mounted  at  the  bottom on shaker and reverse air bag-
houses, at  the top on pulse  jet baghouses.   The replacement of
bags having  hose clamps, which is extremely  time consuming,  is
prevalent in older  applications.   Quick disconnect  clamps and
steel  snap rings  sewn  into shaker  bag cuffs are being specified
more often.

     The particulate-laden gas  is  usually introduced  into the
upper  portion of  the  hopper.   This  allows  the  entering  gas
velocity to  be  reduced suddenly,  thereby  enabling the  coarse
particles to settle directly into the hopper.   The  finer par-
ticles, along  with the  gas,  pass  upward to  the fabric filters
(typically cylindrically shaped).  According to the generic type
of baghouse,  filtration may occur on  either  the inner or outer
surfaces of  the  bag.   The  cleaned  gas is subsequently passed to
a plenum before being discharged into a common manifold.  As the
amount  of  collected  dust accumulates,  the  thickness of  the
filter cake  also increases on the bags, thus producing a corres-
ponding  increase in the  pressure drop  across  the  collector.
Periodically,  either with  a  programmed timer or by  monitoring
the  pressure  loss  with  a differential  pressure switch,  the
collector will go into its cleaning cycle.

     The proper  installation  of  bags  with accessory hardware is
one of the  most  important  aspects  of baghouse performance.  The
intention  of  the  manufacturer is   to  provide  efficient  bag
arrangement with proper bag clearances.  The most common type of
arrangement  is bags  that form straight rows.  Sufficient clear-
ance between bags  avoids the  possibility of rubbing,  and speci-
fications for tensioning should be provided by the manufacturer.

     The most  prevalent problem in  baghouse design,  regardless
of type,  is  ease of access to bags  for maintenance.   Cost con-
siderations  often  result   in walkways,  internal  ladders,  and
access doors being omitted.  Walkways between banks of bags must
be provided;  if the bags  are long,   catwalks  are needed  at the
top and bottom of the  bags.  The manufacturer often designs the
housing so  that  it is  impossible to  reach  bags  beyond an arm's
length.  A  walkway should  be provided around the  bags to make
them easily  accessible.  Top access doors are also necessary for
proper inspection and bag maintenance.

3.2.4  Cleaning Mechanism

Shaker—
     A baghouse  with mechanical shaking consists  of  a housing
divided into an  upper  and  lower portion by the tube sheet.  The
                               21

-------
upper portion  usually contains woven  fabric tubular bags,  and
the lower contains pyramidal hoppers,  each with its own  valve or
with a  long,  trough-type hopper emptied by  a  sealed  screw con-
veyor.   The upper  ends  of the bags (which are flexibly  mounted,
often from a common  support structure)  are shaken by mechanical
or pneumatic means.  During cleaning,  the shaking dislodges the
filter  cake  from  the  inner surface of  the  bag and  causes the
cake to fall into the hopper.  The shaking energy is transmitted
most effectively  next  to the  shaker  bars and  diminishes  grad-
ually to  the  thimble.   Hence, occasions may  arise  in which the
bags are cleaner at the top than at the bottom.

     Upon conclusion  of the cleaning cycle  (1  or  2 minutes per
hour; 1 to  5  cycles  per second; amplitude up to 2 inches;  10 to
100 cycles) the  damper  opens,  thereby returning the compartment
or system  to  the  filtering  mode.   In  large  systems,  individual
compartments are cleaned one at a time to keep the pressure loss
across the collector at a nominal value.

     The  mechanical  shaker mechanism  consists of  an  electric
motor coupled to a cam or eccentric, which translates the rotary
motion of the motor into an oscillation through a connecting rod
assembly.  Bags  may  be  shaken  horizontally  or vertically.  The
shaker motor drives  an  eccentric  crankshaft via pulley belts to
the frame from  which the bags are hung.  A pillow block bearing
supports the crank shaft on one end of the shaker assembly and  a
shaker hanger on the other.  Good design practice has the shaker
mechanism  mounted  outside  the baghpuse  housing  for  ease  of
maintenance, lubrication, and inspection.

     No  inflating pressure  is  permitted within the bags during
shaking, because  such a  condition would impede fabric movement
and  hinder  cake  release.   Butterfly  and  guillotine  dampers,
unless  sealed properly,  could contribute to air leakage and bag
inflation; poppet valves are therefore recommended.  Bag tension
is  also critical to  proper cleaning.   For instance,   a   9-ft,
seamed  bag  will  move  approximately  3  in. off  the center line
during  shaking;  longer bags will  move  somewhat more, and  seam-
less bags require  less movement.

     The following situations could directly affect bag cleaning
performance while  operating shaker baghouses:

     As  a  result  of housing deformity,  either from heat  stress
     warpage,   poor   fabrication,   or  installation,  bags  are
     stretched  or  collapsed.

     Housing deformity, with its associated  dimensional changes,
     produces  excessive  wear  on  shaker assembly  (crankshaft
     becomes misaligned  and produces excessive wear  on bearings
     and shaker hanger).

     Dimensions  of  replacement bags  may  not  coincide  with the
     actual dimensions.

                                22

-------
     The bags are  fastened  to  the shaker bars by various means.
An older method consists of attaching the bag to a steel disc or
cap  (disposable  caps  are available) from which  a threaded bolt
is coupled to a  shaker bar.  A newer design  consists  of a sewn
loop placed over a J-hook.  Another fastening method consists of
sewing  the  end  of the  bag  into  a  flat strap, which  is looped
back and forth over a special hanger.

     During  cleaning,  the  pressure  across the  entire baghouse
may  increase  somewhat.   This  increase  usually occurs  when mod-
ules  or sections  are  isolated  to  allow for  cleaning;  overall
performance is not usually  affected.

Reverse Air--
     This baghouse has a configuration similar to that of the
shaker.  The dirty gas can be passed through a single inlet into
the  trough-type  hopper,  or  through a common inlet manifold that
serves many pyramidal hoppers.  Each tubular bag is clamped to a
thimble  at  its  lower  end and to a  flexibly  mounted  cap at the
upper end.  Filtration occurs  from the  inside of the tube to the
outside.

     During  the  cleaning  cycle,  a valve  at  the  compartment
outlet  is closed.   Simultaneously,  a  small  air-vent  valve is
opened,  allowing  atmospheric  air to  rush  in  and collapse the
bags.   The  air rushes in because the  housing is under negative
pressure.   According  to the  cleaning  requirements,  a secondary
blower providing the reverse air  may be necessary.

     Bag  collapse  breaks the  filter cake and allows  it to drop
into  the hopper.   The  reverse  airflow  is  maintained  by the
suction  through  the common inlet manifold,  which remains open.
Upon  conclusion  of the cleaning  cycle, the valve  is opened, and
the  air  vent and/or  secondary  blower is  closed.    Individual
compartments  are cleaned  one at a time  on a predetermined sched-
ule  activated by  a programmer or by  a monitoring of the draft
loss.

      Some  filter tubes are equipped with  rings spaced at given
intervals  along  their vertical  height.   When  the air  is re-
versed,  the  bags  collapse inward,  but  the  rings  prevent the
cloth  from  rubbing against itself and permit  the cake to  fall
without  interference.

Pulse Jet--
      Like the shaker,  the pulse-jet baghouse  is  divided into an
upper  and  lower  portion by a tube sheet.   The  gas  is  usually
introduced  to the lower  part  of  the housing, often through the
hopper.   The hopper   serves  as  a  settling chamber  and allows
large  particles  to be  removed without needing  to be  filtered.
                               23

-------
The  gas  flow  is  directed  upward  and  around  the  cylindrical
filter tubes  and  then  through  the  filters from  the  outside
direction.   In contrast  to  the  shaker,  the filter cake is built
up  from  the outside,  not the  inside.   The cleaned  gas  passes
upward through the tube sheet and out the outlet manifold.

     The  bags  are  cleaned periodically  when sets  of compressed
air jets are actuated, blowing  air at high pressure through the
individual  tubes.  This flow is  superimposed on  the system flow.
The filter  bags  are fabricated from  felted  media  and supported
by  a  wire  cage  or  retainer.   A venturi-shaped nozzle is often
provided  to improve the  efficiency of the air pulse.  The force
of  the pulse  jet snaps the bag outward,  thereby  partially dis-
lodging the accumulated filter cake.  The system flow then snaps
the bag onto the retainer and completes the cleaning.

     The  cleaning pulse  usually  cleans  several  bags in a row at
one time.   This  procedure occurs  through  sets  of  manifolds and
is controlled by a timer that activates a solenoid and diaphragm
valve that  releases the air pressure provided  by  a compressor.
The dislodged  contaminant falls to a hopper and  is disposed of
by  an  airlock,  screw conveyor,  or by pneumatic means.   A vari-
ation  in pulse  cleaning design  is  the compartment  or  plenum
pulse.   In  this  case,  an entire compartment is  subjected to the
cleaning  pulse  instead  of  a row  of bags  as  in  the pulse-jet
situation.

     Although  other baghouse designs  are available,  the indi-
vidual cleaning  mechanisms  are  similar  and may be  used in con-
junction  with  one  another  for more  effective cleaning.  Accor-
ding to  the application  and manufacturer,  the  filter configur-
ation may  range  from  an  envelope  shape to  a disposable filter
cartridge,   the  most common  type  being  the  cylindrical filter.


3.3  BAGHOUSE OPERATION AND MAINTENANCE

     For  a baghouse  operation  and maintenance  program  to be
highly effective,  a logical  sequence  of  events  should  occur.
Guidelines   to  be  followed  before startup  and  inspection are
given below along  with routine  startup, operating, and shutdown
procedures.  The scope of the inspection procedure varies accor-
ding to  whether  the unit  is operating  or  shut down.  When the
unit  is  shut,  down,  the  condition of  bags  and hoppers  can be
viewed.   The  unit  is  otherwise   inaccessible,   with  only such
parameters   as  operating  pressure  and  temperature  and external
cleaning and dust handling system components open to  inspection.

3.3.1  Pre-Startup Inspection

     If  a new  baghouse has  been installed, or if one has under-
gone  internal  service and  maintenance,  it must  be thoroughly
inspected before it is  "buttoned  up."  The inspection should
include the following steps:

                               24

-------
     Remove such debris as nuts,  bolts,  tools,  welding rods,  and
     other items that may  become  airborne  and behave as projec-
     tiles,  puncturing  bags   or  getting  caught  in  operating
     mechanisms.

     Remove  all  contaminant and  inspect  the hoppers  for  leaks
     and debris.

     If  single  bags were  replaced,  inspect  adjacent  ones  for
     damage.

     Check bag connection and tension.

     If entire unit was  rebagged,  check again after a few hours
     of operation.

     Inspect walls  for cracked, chipped coatings.

     Inspect  instrument  monitoring locations,  especially  pres-
     sure taps.

     Check valve seals on inlet and outlet ducts.

     If  possible  before  the  unit is  buttoned up,  operate  the
various components  to check their operation.   It may be feasible
to perform this work while workers are in the unit.  If not,  the
unit should  be  closed up, operated without  flow,  and then shut
down and inspected again.

3.3.2  Routine Startup

     One of  the most  important items  to consider in starting up
a baghouse is the  condition of the process air.   If the air is
moist,  it  is  necessary  to preheat the baghouse to avoid conden-
sation,  especially on the bags.  Ideally,  purging  the system
with warm,  dry  air will  abort  this  problem; however,  appli-
cations  may  arise  where hot,  clean  air may  not  be available
because  by virtue  of being hot it may  already contain contami-
nants.    In this case,  external  means  of preheating are recom-
mended,  such  as strip heaters.  Even if the  baghouse is insul-
ated and out of service for only several hours,  preheat may be
required.

     The outline procedure given below for  routine startup  can
be used for shakers, reverse-air, and pulse-jet units.

     1.   Secure  doors  and hatches  and  notify  personnel  of
          startup.

     2.   Operate  material  handling  system  (airlocks,  screw
          conveyors, etc.).
                               25

-------
     3.    Open bypass dampers to allow hot,  "clean"  air  to enter
          system for preheat.

     4.    Before starting blower, verify zero  settings  on moni-
          toring instrumentation.

     5.    Start blower.

     6.    Engage cleaning circuit.

     7.    Record data from monitoring instrumentation (fan motor
          amperage  and  voltage,   temperature   and   pressures).

     8.    Allow  contaminant  to  pass  baghouse  and  note  and
          changes in monitoring data.

3.3.3  Routine Inspection and Maintenance During Operation

     During routine operation, an inspection procedure recording
baghouse operational data should be used.  A sample  of a routine
daily inspection report  for a shaker  baghouse is  provided in
Figure  2.   This  document may be  used  to give  the  maintenance
department a  continuous  record of  system performance.   The two
columns headed "CHECKED" are to be filled in by the  inspector to
verify  that  he  observed  the  condition  of the  component.   The
column  "REQ.  ATTN." is provided to  alert  maintenance personnel
that a problem exists.  In addition to the inspection, a mainte-
nance checklist  for  a  shaker mechanism  is  given in Figure 3.
Figure 4 provides an inspection report for a pulse-jet baghouse.

3.3.4  Routine Shutdown

     The most  important aspect of  shutting down a  baghouse is
the  prevention of  condensation.   A  general procedure  includes
the following steps:

     When the  process  is  shut down, it is advisable to continue
     to operate  the baghouse  for  one complete cycle (including
     cleaning).   This operation  purges  it with  clean  air to
     avoid  condensation  and ensure  that  bag  contaminants are
     removed.   (In applications where  a filter cake  is needed
     upon startup, cleaning  is not recommended.)

     Shut down the fan.

     If possible, isolate the baghouse by closing dampers.

     Continue  to operate dust  removal  system  until hoppers are
     clear and then shut off the system.
                               26

-------
                             SHAKER BAGHOUSE INSPECTION FEPORT
           APPLICATION:
           DATE/TIME:   	               CHECKED
           FEPORT BY:        	            *ES        NO         ATTN.
           OPERATION OF MATERIAL HANDLING SYSTEM

                NOISES                                a        n          D
                AIR LEAKS                             CD        CD          d
                LUBRICATION LEAKS                     CD        D          CD
                GASKETING                             O        CD          O
                COMMENTS

           DUCTS  (rNLET/OUTLET)

                NOISES                                a        a          a
                AIR LEAKS                             O        D          O
                GASKETS                               d        O          O
                COMMENTS

           BAGHOUSE
                SHAKER OPERATING                      CD        O          C3
                SHAKER SEQUENCE                       CD        CD          CD
                AIR LEAKS                             O        CD          a
                COMMENTS

                                                    OPERATING   DESIGN  •

           COLLECTOR MEASUREMENTS

                TEMPERATURE:  IN                     	    	        d
                TEMPERATURE:  OUT                    	    	        D
                PRESSURE DROP                        	    	        CD
                STATIC PRESSURE:  IN                 	    	        D
                STATIC PRESSURE:  OUT                 	    	        D
                FLOW RATE                            	    	        D
                COMMENTS
           BLOWER
                CURRENT                              	    	        D
                TOLTAGE                              	    	        C3
                BELT TENSION                          O         O          CD
                BEARING LUBRICATION                   Da          CD
                COtHENTS
           STACK APPEARANCE
                COM-1ENTS
Figure 2.   Sample  of  routine daily  inspection report for  shaker baghouse.

                                            27

-------
                  SHAKER MECHANISM MAINTENANCE CHECKLIST
    APPLICATION:


    DATE/TIME:


    REPORT BY:
  CHECKED


 YES      NO
         KEQ.

         ATTN.
                                                                       LUBRICATE
    SHAKER NO.
         MOTOR

         ECCENTRIC BEARINGS

         PILLOW BLOCK BEARING

         SHAKER FRAME SUPPORT

         PULLEY/BELTS

         COMMENTS
CD
O
a
a
a
a
a
a
a
a
a
n
a
D
 n
 a
 a
 a
 o
    INLET/OUTLET VALVES AND ACTUATORS


         MOTOR

         DRIVE FDD

         DRIVE SCREW

         COMMENTS
a
a
a
O
a
a
n
a
a
n
a
a
    SCREW CONVEYORS
         MOTOR

         SCREW DRIVE

         HANCZR BEARING

         TAIL SHAFT BEARING
a
a
a
o
a
a
a
n
a
a
CD
a
a
D
D
Figure 3.   Sample  of maintenance  checklist for  shaker mechanism.
                                      28

-------
PULSE- JET BAGHOUSE
APPLICATION:
DATE/TIME:
INSPECTION RE

JORT



( VkY 'KH k

FEPORT BY:
OPERATION OF MATERIAL HANDLING SYSTEM
NOISES
AIR LEAKS
LUBRICATION LEAKS
DRIVE ASSEMBLY
GEAR REDUCER
DRIVE SHAFT
BEARINGS
ACCESS DOORS
GASKETING
COMMENTS
DUCTS (INLET/OUTLET)
NOISES
AIR LEAKS
GASKETS
DAMPERS
COMMENTS
CLEANING MECHANISM
WATER TRAP
AIR REGULATOR
MANIFOLD PIPES
DIAPHRAGM VALVES
SOLENOID VALVES
WIRE CONNECTIONS
HOSE CONNECTIONS
COMMENTS
BLOWER
BELT TENSION
BEARING LUBRICATION
MOTOR
SHEAVES
DAMPER
COMMENTS
COLLECTOR MEASUREMENTS
TEMP. IN
TEMP. OUT
PRESSURE DROP
STATIC PRESSURE IN
STATIC PRESSURE OUT
HEADER AIR PRESSURE
TIMER SETTINGS
STACK OBSERVATIONS
COMMENTS
YES

a
a
o
CD
CD
a
a
a
o


a
a
a
a


D
o
CD
a
n
a
0


a
a
a
a
13











NO

n
a
a
a
a
n
C3
a
a


a
a
a
a


0
o
m
a
a
n
o


a
a
n
o
a








» ••••^••i
•. •••MBVUII

REQ.
ATTN.

a
a
a
O
o
a
a
a
CD


a
n
a
a


o
a
a
a
a
a
a


a
n
a
o
o











Figure 4.   Sample of routine daily  inspection  report  for  pulse-jet baghouse.




                                     29

-------
     Baghouses  are  usually shut  down  for routine  or  emergency
process shutdown,  or  for routine or emergency  baghouse  mainte-
nance.

3.3.5  Maintenance During Shutdown

     Maintenance of a baghouse  must  also  occur  within the hous-
ing when  the  baghouse  is shut down and entry is  possible.   All
necessary  safety  precautions must  be  followed before  entering
the baghouse.   At this time,  the items  requiring greatest atten-
tion  are  the  bags  and  any moving mechanism on the dirty side of
the  baghouse.  Figure  5 details  an  internal  inspection of  a
shaker baghouse.  Other checklists can  be  prepared for different
baghouses, components, and other  types of dust removal systems.
The checklist provided in Figure  5  could  be used in conjunction
with  that  shown in  Figure 2  as an excellent mechanism for main-
tenance recordkeeping.

3.3.6  Common Malfunctions

     Most  baghouse  maintenance,  regardless  of cleaning mecha-
nism,  focuses  on  the  bags  and moving mechanical  parts,  espe-
cially  those  parts on  the  dirty side of  the filters.   High-
maintenance   items  also  vary  according  to  the  application.
Commonly observed malfunctions are discussed below.

     The  highest-maintenance  item of  a  baghouse is  the  bags.
The most  common problems are tears  or pinholes,  blinding (cake
buildup),  and bleeding (seepage).  These problems  can be diag-
nosed  and subsequently  minimized with frequent:  inspection  and
preventive  maintenance.   It  should  not be  construed,  however,
that  such a  program will eliminate  bag  failure.   Variations in
fabric quality, sewing techniques, quality control, and gas flow
distribution  within the baghouse also  contribute  to bag failure.
A  small  number  of  bag  failures may occur  during  the  first
several months  of operation,  generally because of manufacturing
or  installation defects.   Under  normal  operating conditions,   a
sudden  increase in  frequency of failure indicates that the bags
have  reached  the end of their operating life.

     Visible  stack  emissions  usually  indicate  bag   failure.
Where  a stack  monitor is used, increased  readings are further
indicators.   In either case,  three  methods can be used  to iden-
tify  leaking  bags:   1)  inspection of  bags for holes, 2) examin-
ation  of bags  for excessive  dust  accumulation,  3)  use of bag
leak  detection  device.

     Valves that  are  used to isloate  individual  bag chambers in
a  shaker  baghouse often  experience  sealing problems.  An indi-
cation  of a poor bag seal is a slight flow and presurization in
the  isolated  compartment.  This  condition  can be determined by
viewing  the  shaking  process  and observing  that  the  bags  are
inflated.
                               30

-------
                           SHAKER BAGHOUSE:  INTERNAL INSPECTION
         APPLICATION:
          DATE/TIME:	CHECKED

          REPORT BY:   	           *ES       NO        ATTN.



          FILTER BAGS
            MOUNTING AND CLAMP ACCESSORIES

               CORROSION                            a       a         a
               WARPAGE                              a       a         a
               BROKEN                               Odd
               CUFFS                                a       a         a
               COMMENTS

            BAGS
               VJDRN                                 CUdd
               ABRADED                              CH       O         O
               DAMAGED                              CD       d         d
               PIN HOLES                            CUdd
               BURNS                                O       C3         O
               TENSION                              d       d         d
               BLINDING                             CD       D         d
               SEEPING                              d       d         d
               FLEXURE WEAR                         ODD
               COMMENTS

          DUST REMOVAL SYSTEM (TYPE;  SCREW CONVEYOR)

               WORN BEARINGS                        d       d         d
               LOOSE MOUNTINGS                      Odd
               DEFORMED PARTS                       D       H]         D
               WORN OR LOOSE DRIVE MECHANISMS        d       d         d
               CONTAMINANT BUILDUP                  HI       D         d
               DEBRIS                               d       d         a
               COMMENTS

          DUCTS (INLET/OUTLET)
               BUTXOOP                              d       d         d
               ABRASION                             d       d         d
               CORROSION                            ddd
               LEAKAGE                              d       d         d
               GASKETING                            O       d         d
               BOLTS                                CD       O         O
               WELDS   •                             d       C3         O
               COMMENTS
                                    Page 1 of 2





Figure  5.   Sample  of  internal  inspection report  for  a shaker  baghouse.

                                          31

-------


VALVES/DAMPERS
BUILDUP
CORROSION
CLEARANCE
COMMENTS
CLEANING MECHANISM (SHAKER)
SHAKER FRAME
SHAKER HANGER
LINKAGE
CONNECTING BCD ASSEMBLY
CRANKSHAFT
DRIVE MOTOR
PILLOW BLOCK BEARING
SHAKER DRIVE SUPPORT
BELTS
COMMENTS
TUBE SHEET
WARPAGE
CORROSION
BUILDUP
COMMENTS
ACCESS DOORS
SEALS
GASKETING
LEAKAGE
COMMENTS
BAGHOUSE HOUSING
WARPAGE
CRACKS
CORROSION
GASKETING
NUTS AND BOLTS
LINING OWCKED
COMMENTS
Page 2 of 2
CHECKED
YES

o
D
D


a
a
a
a
en
a
a
a
a


n
a
n


o
a
a


a
a
a
a
a
a



MO

a
D
a


a
n
a
a
a
n
CD
a
a


a
a
o


a
a
a


a
a
a
a
CD
a


FEQ.
ATTN.

n
a
CD


o
a
a
a
a
a
a
a
o


a
a
a


a
a
a


o
o
a
a
0
C3


Figure 5 (continued)



                                      32

-------
     If the push rod from poppet valves is subjected to dust,  it
can  affect air  cylinder  operation.   The  push  rod  should  be
mounted  in the vertical  position,  because  horizontal  mounting
may cause warpage and malfunction.

3.3.7  Troubleshooting Procedures

     Recommendations for  troubleshooting  a shaker  and  a  pulse-
jet baghouse are provided below.

Recommendations for Troubleshooting a Shaker Baghouse—

     1.   Check wear  pattern before  removing old  bags.   These
          patterns may  indicate a  diffuser  problem if abrasion
          is causing  bag  failure.   If chemical  attack is  the
          problem, the  pattern  may indicate  where  the  moisture
          originates.

     2.   Account for shrinkage  rate  of new bags when adjusting
          bag tension.

     3.   Be sure that  the  entire  clamp  (bag and screw) is of a
          noncorrosive  material (preferably  stainless  steel).

     4.   Use stainless  steel,  hex-head  screws on  the  bands  so
          that ratchet  wrenches or air guns  can be  used.   Air
          wrenches with pressure regulators  can be  calibrated
          with a torque wrench to ensure proper band tightening.

     5.   Keep bag  seams  straight  and do  not torsionally  twist
          the bags.

     6.   Visually recheck  bag  tension after the first 8  or  10
          hours,  sooner if  the  shaker motor overloads or  if the
          belts break or squeal.

     7.   Check availability of  other  bag  materials,  especially
          if sufficient  leadtime is  available.   This may  bring
          significant savings  and  better  performance.  Current
          trend is to  purchase  polyester  or  glass  material  for
          most applications.   Other  materials,   such  as  poly-
          propylene  or nylon, should  be considered  because they
          may perform better and be  less expensive.

     8.   Place tight-fitting washer  on  shaker pins  if present
          holes approach  the  size  of the   retaining clip on  the
          pin (shaker)  mechanism.
                               33

-------
Recommendations for Troubleshooting a Pulse-Jet Baghouse—

     1.   Stiffen tube  sheet  if it flexes in  order  to  minimize
          bag-to-bag abrasion.

     2.   Align bags  to prevent them from touching  each other.

     3.   Check  the coefficient  of thermal  expansion  and  the
          rate  of  fabric  shrinkage  so  that  the bags  do  not
          deform  retainer.   If bags are  too  small  for  the  re-
          tainer, they will tear.

     4.   Align  jet in  center  of  bags and make  sure it is per-
          pendicular to the tube sheet.

     5.   Use  venturi  nozzle,   if  possible.   Although  it has a
          higher  initial  cost, savings  in  energy   and better
          cleaning  compensate;  it  also  minimizes  the  shear
          effect  on the upper  portion of the bags caused by the
          cleaning  jet  pulse.   Avoid bag lengths greater than 8
          ft.,  especially  if   the  diameter  is  not  over  4  in.
          Long  bags cause a problem of  overcleaning at the top
          and lack  of cleaning  at the bottom.

     6.   Change  the diaphragm  in the right angle valves  as part
          of  routine maintenance.   Replace  pilot valves  if they
          have  a  history of failing or sticking.

     7.   If  undercleaning  is  a problem, minimize the number of
          transitions  in the  blow tube  piping.  Ream  out the
          blow  tube orifices  to prevent burrs caused by cutting
          from  restricting the  flow.

     8.   Use headers having at least a  6-in.  diameter,  with the
          last  valve being at  least one  diameter from the end of
          the headers.

     9.   Lubricate or  replace all seals and worn  bearings as
          necessary in  all rotating equipment.

     10.   Install a water trap on the  compressed  air  line  up-
          stream of the solenoid valve.

     11.   Check  housing  for  stress  cracks  caused  by  pulsing.

     12.   Weld   or  braise  any  loose wires   on the  retainers.
          Replace badly bent retainers.
                                34

-------
    13.    Replace all gaskets  or other parts when  appropriate.

    14.    Follow the unit  through a  full  cycle to ensure  that
          all valves are operating in a proper  sequence.

    15.    Observe  that   the  seal  on  the  hopper  discharge  is
          preventing reentrainment from fan suction or  pressure
          of  air  conveying  system.   Use  double  airlocks,  if
          necessary.  Leakage  in this component has  the  effect
          of  creating  a higher  grain loading,  especially  with
          submicrometer   particles.   Air  leakage  could be  ob-
          served by  "whistling"  air rushing into the system or
          dust patterns  forming at infiltration locations.

    16.    Do not use a  woven material in  a pulse-jet  collector;
          use only felted material.

    17.    If  tube  sheet  leakage  is  a problem,  apply  sealer
          between  the  bag  retainer  and  the  top  of  the  tube
          sheet.  When intermittent puffing occurs,  it is  usual-
          ly  caused by  overcleaning.   If  all  are not  puffing,
          check  the  row by sychronizing a  stop watch with the
          cleaning  timer.   If  possible,  check dump rate  of the
          conveying system.

    18.    Ensure that hopper operates  fast  enough  to  prevent it
          from becoming more than two-thirds full.

General Troubleshooting Guide—
     An  extensive  list  of procedures  for troubleshooting  and
correcting  baghouse malfunctions  is  given  in  Table 1.   This
table should be  consulted when troubleshooting and  diagnosing
operational  problems  (i.e.,  when a  symptom arises  from various
causes during equipment  operation).   In the  absence of symptoms
or malfunction,  internal inspection  may reveal  such problems as
bag tears  or pinholes,   and  the  subsequent development or  mal-
function is  speculative.   For  instance, bag tears  may result in
low pressure drop,  high opacity, high  air-to-cloth ratio,  or
other problems.

3.3.8  Spare Parts

     The manufacturer of the equipment usually provides  a  recom-
mended spare parts list.  The most  important item to  stock is
bags,  preferably a full replacement  set.   Although there  is a
bag life expectancy and delivery time,  emergencies could  arise.
Caution should  be  exercised  when inexpensive  bags  are quoted by
a bag  fabricator.   Poor quality control  is usually  the  reason
for cost  cutting.   A list of  replacement parts is provided in
Table 2.
                               35

-------
                  TABLE 1.   BAGHOUSE  TROUBLESHOOTING GUIDE
The following chart lists the most common  problems  found  in  a  baghouse
air pollution control  system and offers  general  solutions.   In some
instances, the solution is to consult the  manufacturer.   This  may  not
be necessary in plants that have sufficient engineering know-how
available.
Where the information applies to a specific type  of  baghouse,
following code is used:

                    RP	Reverse pulse
                    PP	Plenum pulse
                     S	Shaker
                    RF	Reverse flow
                                     the
     Symptom
     Cause
     Remedy
High baghouse pressure
 drop
Baghouse undersized
                         Bag cleaning mechanism
                          not adjusted properly
                         Compressed air pressure
                          too low (RP, PP)
                         Repressuring pressure
                          too low (RF)
                         Shaking not vigorous
Consult manufacturer
 Install double bags
 Add more compartments
 or modules

Increase cleaning fre-
 quency
Clean for longer duration
Clean more vigorously
 (must check with manu-
 facturer before implemen-
 ting)

Increase pressure
Decrease duration and/or
 frequency
Check dryer and clean
 if necessary
Check for obstruction
 in piping

Speed up repressuring fan
Check for leaks
Check damper valve  seals

Increase shaker speed
(check with manufacturer)
 (continued)
                                     36

-------
Table 1 (continued)
     Symptom
     Cause
     Remedy
Low fan motor amperage/
 low air volume

(continued)
                         Isolation damper
                          valves not closing
                          (S, RF, PP)
                         Isolation damper valves
                          not opening (S, RF, PP)
                         Bag tension too loose
                          (S)

                         Pulsing valves failed
                          (RP)

                         Air volume greater than
                          design
                         Cleaning timer failure
                         Not capable of removing
                          dust from bags
                         Excessive reentrain-
                          ment of dust
                         Incorrect pressure
                          reading
High baghouse pressure
                         Check linkage
                         Check seals
                         Check air supply of
                          pneumatic operators

                         Check linkage
                         Check air supply on
                          pneumatic operators

                         Tighten bags
Check diaphragm valves
Check solenoid valves

Damper system to design
 point
Install fan amperage controls

Check to see if timer is
 indexing to all contacts
Check output on all terminals

Condensation on bags (see
 below)
Send sample of dust to
 manufacturer
Send bag to lab for analysis
 for blinding
Dryclean or replace bags
Reduce air flow

Continously empty hopper
Clean rows of bags randomly,
 instead of sequentially
 (PP, RP)

Clean out pressure taps
Check hoses for leaks
Check for proper fluid in
 manometer
Check diaphragm in gauge

See above
                                     37

-------
Table I (continued)
     Symptom
     Cause
     Remedy
Dust escaping at
 source
Dirty discharge at
 stack
                         Fan and  motor  sheaves
                          reversed

                         Ducts  plugged  with
                          dust

                         Fan damper closed
                         System static  pressure
                          too high
                         Fan not operating per
                          design
Belts slipping

Low air volume


Ducts leaking
                         Improper duct flow
                          balancing

                         Improper hood design
Bags leaking
                         Bag clamps not sealing
Check drawings and reverse
 sheaves

Clean out ducts and check
 duct velocities

Open damper and lock in
 position

Measure static on both sides
 and compare with design
 pressure
Duct velocity too high
Duct design not proper

Check fan inlet configuration
 and be sure even airflow
 exists

Check tension and adjust

See above
Patch leaks so air
 does not bypass source

Adjust, blast gates in
 branch ducts

Close open areas around
 dust source
Check for cross drafts that
 overcome suction
Check for dust being
 thrown away from hood
 by belt, etc.

Replace bags
Tie off bags and replace
 at a later date
Isolate leaking compart-
 ment if allowable without
 upsetting system

Check and tighten clamps
Smooth out cloth under
 clamp and reel amp
(continued)
                                     38

-------
Table 1 (continued)
     Symptom
     Cause
     Remedy
Excessive fan wear
Excessive fan
 vibration
High compressed air
 consumption (RP,  PP)
                         Failure of seals in
                          joints at clean/dirty
                          air connection

                         Insufficient filter
                          cake
                         Bags too porous
Fan handling too much
 dust

Improper fan
Fan speed too high

Buildup of dust on
 blades
                         Wrong fan wheel  for
                          application

                         Sheaves not balanced
Bearings worn

Cleaning cycle too
 frequent

Pulse too long
                         Pressure too  high
Caulk and tighten clamps
Smooth out cloth under
 clamp and reel amp

Allow more dust to build up
 on bags by cleaning less
 frequently
Use a precoating of dust on
 bags (S, RF)

Send bag in for permeability
 test and review with
 manufacturer

See above
check with fan manufacturer
 to see if fan is correct for
 application

Check with manufacturer

Clean off and check to see
 if fan is handling too much
 dust (see above)
Do not allow any water in
 fan (check drain, look for
 condensation, etc.)

Check with manufacturer
Have sheaves dynamically
 balanced

Replace bearings

Reduce cleaning cycle if
 possible

Reduce duration (after
 initial shock all  other
 compressed air is  wasted)

Reduce supply pressure if
 possible
(continued)
                                     39

-------
Table 1 (continued)
     Symptom
     Cause
     Remedy
Reduced compressed
 air pressure (RP, PP)
Premature bag failure:
 decomposition
Moisure in baghouse
 High  screw  conveyor
 wear

 (continued)
Damper valves not
 sealing (PP)

Diaphragm valve
 failure

Compressed air
 consumption too high

Restrictions in piping

Dryer plugged


Supply line too small

Compressor worn

Bag material improper
 for chemical coposi-
 tion of gas or dust
Operating below acid
 dew point

System not purged after
 shutdown
                         Wall temperature below
                          dew point
                         Cold spots at struc-
                          ural members

                         Compressed air intro-
                          ducing water (RP, PP)
 Repressuring  air
  causing  condensation
  (RF,  PP)

 Screw  conveyor  under-
  sized
Check linkage
Check seals

Check diaphragms and springs
Check solenoid valve

See above
Check piping

Replace desiccant or
 bypass dryer if allowed

Consult design

Replace rings

Analyze gas and dust and
 check with manufacturer
Treat with neutralizer before
 baghouse

Increase gas temperature
Bypass and startup

Keep fan running for 5 to
10 minutes after process is
 shut down

Raise gas temperature
Insulate unit
Lower dew point by  keeping
 moisture out of  system

Fully  insulate  structural
 members

Check automatic drains
Install  aftercooler
Install  dryer

Preheat  repressuring  air
Use  process  gas as  source  of
  repressuring  air

Measure  hourly  collection  of
  dust  and  consult manufacturer
                                      40

-------
Table 1 (continued)
     Symptom
     Cause
          Remedy
High air lock wear
Material bridging in
 hopper
Frequent screw
 conveyor/air lock
 failure
High pneumatic
 conveyor wear
Pneumatic coneyor
 pipes plugging
(continued)
Conveyor speed too high

Air lock undersized


Thermal expansion



Speed too high

Moisture in baghouse
Dust being stored in
 hopper

Hopper slope insuffi-
 cient

Conveyor opening too
 small

Equipment undersized

Screw conveyor
 misaligned

Overloading components
Pneumatic blower too
 fast

Piping undersized
Elbow radius too
 short

Overloading pneumatic
 conveyor

Slug loading of dust
Slow down speed

Measure hourly collection of
 dust and consult manufacturer

Consult manufacturer to see if
 design allowed for thermal
 expansion

Slow down

See above
Add hopper heaters

Remove dust continuously
Rework or replace hoppers


Use a wide-flared trough


Consult manufacturer

Align conveyor
Check sizing to see that each
 component is capable of handling
 a 100% delivery from the
 previous component

Slow down blower
Review design and slow
 blower or increase pipe size

Replace with long radius
 elbows

Review design
                                                  See  above
                                     41

-------
Table 1 (continued)
     Symptom
     Cause
     Remedy
Fan motor overloading
Air volume too
 high
Reduced compressed
 air consumption
 (RP, PP)
 High bag failure:
 wearing out
 High bag failure:
  burning

 (continued)
Moisture in dust

Air volume too high

Motor not sized for
 cold start



Ducts leaking


Insufficient static
 pressure

Pulsing valves not
 working


Timer failed

Baffle plate worn out

Too much dust

Cleaning cycle too
 frequent

Inlet air  not properly
 baffled from bags

Shaking too  violent  (S)
 Repressuring  pressure
  too high  (RF)

 Pulsing pressure  too
  high (RP,  PP)

 Cages have  barbs
  (RP, PP)

 Stratification  of hot
  and cold  gases
See below

See below

Damper fan at startup
Reduce fan speed
Provide heat faster
Replace motor

Patch leaks


Close damper valve
Slow down fan

Check diaphragms
Check springs
Check solenoid valves

Check terminal outputs

Replace baffle plate

Install primary collector

Slow down cleaning


Consult manufacturer
                                                  Slow down shaking mechanism
                                                   (consult manufacturer)

                                                  Reduce pressure
                                                  Reduce pressure
                                                   Remove  and  smooth  out  barbs
 Force turbulence in duct with
  baffles
                                      42

-------
Table 1 (continued)
     Symptom
Cause
Remedy
                         Sparks entering bag-
                          house

                         Thermocouple failed
                         Failure of cooling
                          device
                    Install  spark arrester
                    Replace and determine cause
                     of failure

                    Review design and work with
                     manufacturer
                                     43

-------
              TABLE 2.   REPLACEMENT PARTS FOR BAGHOUSE FILTERS
Bags and accessories:   clamps,  nuts,  bolts,  hangers

Bag retainers (pulse jet)

Cleaning mechanism

  Shaker:   bearings, hangers, crankshaft, connecting
           rod, motor belts

  Pulse jet:   Venturis, solenoid and diaphragm valves,
              tubing

Timing mechanism

Screw conveyor:  belts, hanger bearings, coupling bolts.

Air locks:  bearing and seals

Pneumatic:  see manufacturer's recommendations

Damper valves:  solenoids, seals, cylinders

Magnahelic gauges

Gasketing, caulking, lubricants, special tools

Electrical switches, relays, fuses
                                     44

-------
     The user  of the  equipment  should supplement  the  manufac-
turer's recommendations with a spare  parts  inventory reflecting
the particular  application.   Spare parts for baghouses  are  not
costly, but shipping time is often excessive.
                               45

-------
                            SECTION 4

           TECHNICAL ASPECTS OF THE DESIGN,  OPERATION,
         AND MAINTENANCE OF ELECTROSTATIC PRECIPITATORS
     Electrostatic precipitators  are available  in  single-stage
and two-stage  units.   In single-stage  units,  particle charging
and collection are done  simultaneously,  and in two-stage units,
particle  charging  is followed  by  a separate  collection stage.
Because most industrial ESP's are single-stage, this report will
discuss  this  type  only.  Two-stage  systems  are  used  for  low
grain  loading  and  low flow  and find application in commercial
and small industrial situations.

     Other classifications of ESP's are designated by the method
of  removing   precipitated   dust   from   the  collector  surface
(rapper:  dry;  water  spray:  wet),   shape  of collecting  surface
(plate  or cylindrical),   and direction of  gas  flow  within the
unit (horizontal or vertical).

     Most industrial  ESP's  are of  the  rapper,  plate,  and hori-
zontal  gas  flow type.   In operation,  the  ESP  allows the dust-
laden  gas to  flow  between  negatively  charged  wire  electrodes
(discharge  electrodes)   and   nearby grounded  plate  electrodes
(collector  electrodes).   The wire  electrodes  are  charged  to a
high  electrical  potential by an  unfiltered d.c.  power supply
mounted  outside  the  precipitator housing.   The applied voltage
is high  enough to  produce a  visible corona discharge in the gas
immediately surrounding the wire electrodes.  Electrons set free
in the  discharge collide with gas  molecules, producing gas ions
that  in turn collide with dust particles and  give  them a nega-
tive charge.   In the strong  electric field between the wire and
plate  electrodes,  the electrically charged dust particles mi-
grate  to the  plate  where they are deposited,  giving up their
charge.   Eventually,  the thick dust layer  can be  conveniently
removed  from the plate by periodic rapping.  The dislodged dust
falls  into  the hoppers in the  bottom  of  the precipitator hous-
ing, from which it is removed for disposal.

     As  with baghouses,  the  operation  and  maintenance of EPS' s
will  be  discussed  according to  functioning  components,  with
emphasis  on design  deficiencies that may  accentuate O&M prob-
lems.   The  components to be  examined  are  the discharge elec-
                               46

-------
trodes,   collector  electrodes,  rappers,  dust  removal  system,
electric  power  supply,  and  ancillary  equipment.   Safety  will
also  be  discussed.   General  procedures  for  routine  startup,
inspection,  shutdown, and  troubleshooting  are  provided.   Actual
case histories for a dry and a wet ESP are presented in Appendix
A  to give  the user a method  for  troubleshooting  performance
problems.


4.1  ELECTROSTATIC PRECIPITATOR COMPONENTS AND OPERATIONAL
     PARAMETERS

4.1.1  Discharge Electrode System

     The discharge electrode ionizes the gas and establishes the
electric field for particle charging.  The electrodes are metal-
lic and are supplied in cylindrical, square, starred, and barbed
wires,  in stamped or formed strips.  The size and  shape of the
electrodes is governed  by  the corona current required.  Regard-
less of  the number of fields, the ESP usually contains the same
type of  wires per field.   This may not be totally satisfactory,
however,  since  high  concentrations of  contaminant  are  present
mostly  in the  first field.  Under these  conditions,  the  high
concentration of  particulates  limits  space charge  and  current
flow.   Electrodes producing higher  currents in  the  first field
should  thus be  used to achieve higher  power  density and reduce
the  load on the  power supply  in  the first field.   This' power
supply  could  be allowed to operate  at  less than rated voltage,
thereby  subjecting  the  other  fields to higher concentrations of
dust while  not  affecting  overall  system performance.  Manufac-
turers  typically  use one  field for  up  to  90  percent collection
efficiency,  two fields  for up to 97 percent,  three fields up to
99 percent,  and four fields for greater than 99 percent.

     The discharge electrodes commonly used for industrial ESP's
are  weighted  wire.   Rigid wire  frame  electrodes  are becoming
more and more prevalent.

Weighted Wire—
     The  most  common  configuration of  discharge electrodes is
the weighted wire,  which  is typical of most U.S. manufacturers.
The  material  is  usually 12-gauge  (approximately 0.10-in. diam-
eter) steel  spring wire.   (The  choice of  materials  is  usually
dictated  by  the   requirements  of  corrosion  resistance.)   The
wires are suspended from  a support  frame at the  top of the ESP
and held taut by  cast iron weights at the bottom.  The structure
supporting  the  wire  varies from  one manufacturer  to another.
The weights are spaced by a guide frame (typically an eye bolt)
and are  loosely retained in the guides to allow for wire
                               47

-------
expansion.  The  guide  frame  has been a source of  problems:   if
not properly  supported,  it may  resonate  and swing in  the  air-
stream,  thus  affecting dimensional  clearance  to  collector elec-
trodes and  putting  mechanical stress on  the  support  structure.
The guide frames are  mounted to  the hoppers  or ESP  housing,
usually  by  a ceramic  insulator.   Dust buildup  and  moisture
condensation on the insulator can provide a  source of  electrical
leakage to ground.

     Wires  in the first field are  often  subjected to localized
sparking, especially in regions near the ends of the electrodes.
The  excessive sparking  in  this  region  may  come during plate
rapping from exposure to high concentrations of falling dust.  A
shroud surrounding  the  lower portion  (and  sometimes  the upper)
of  the wire is  provided  to  reduce this  effect  and protect the
wire.

     Each of the wire support frames is integrally fastened by a
crossmember,  which  in turn is connected to  a vertical hanger by
supports  to two   (or more) electrical  insulators  mounted on the
ESP roof.  Maintenance workers have limited accessibility to the
wire supports for wire replacement.

Rigid Frame—
     Frame-type  electrodes  have  been  commonplace in  European
designs  and  are  now  becoming  more  prevalent  in  the  United
States.  Unlike  the weighted wire system, rigid frame electrodes
require  a significantly higher  degree  of quality control,  both
in  fabrication  and  erection,  and  are  more  costly.   The rigid
wire frames are  usually shop-assembled and shipped and installed
in  one piece.  Poor handling of the frames has often resulted in
deformation  and deflection  of  the   assembly,  distorting  the
dimensional  alignment  that  is  critical to proper  electrical
performance.   Better quality  control and  shipping precautions
are now being taken by manufacturers.

     Several  designs of   rigid  frame discharge  electrodes are
available:   the   rigid  discharge frame  with integrally  mounted
rigid electrodes, mast support discharge  wires, and self-suppor-
ting rigid  discharge electrodes.  The first of these  is the most
popular.

     The  perimeter of the rigid discharge  frame  and horizontal
frame supports is comprised  of pipe or 1-in.-square tubing.  The
discharge wires  are frequently star shaped in cross-section and
contain  extended points or  edges.   The wire span between  adja-
cent,  interior horizontal frames ranges  from 6  to 8 feet.  The
wires  are fastened to the frames by  several  means:   inserting  a
pair  of  serrated wedges   from  opposite  sides  of the  frame to
                               48

-------
wedge  the  wire  securely,   threaded studs  with  washers,  tack
welded bolts, or welded studs only.

4.1.2  Collector Electrode System

     The  charged  particulate  matter  is  removed  from  the gas
stream  by  grounded collector  electrodes.  The  particles that
have been  charged  by the discharge  electrode are  negative; upon
deposition  on  the grounded  (positive) collector plates,  they
become electrically inert and are removed  by rapping.

     The  electrodes are  available  in  many shapes  and  are de-
signed  to  maximize the  electric  field  while  minimizing dust
reentrainment during  rapping.   Flat plates  have the best  elec-
trical characteristics  and  induce the least turbulence to  flow,
but  excessive  reentrainment tends  to  occur during rapping.  In
practice,  all  collector  electrodes  have  some  sort  of baffle
arrangement  (aerodynamic  shape)  to minimize gas velocities near
the  dust surface as well as to provide stiffness to the plate.
Opzel,  rod  curtain,  zigzag,  V,   V-pocket,  channel,  offset,
shielded,  and  tulip  designs  are  typically  used for baffles.

     Plate  deformation  and distortion  are frequently observed.
They  occur  during  fabrication,   shipment,  and  site  storage.
Proper  quality  control methods  must be  followed during fabri-
cation, and electrodes must be carefully handled during shipment
and  storage.    The plates  should  be  stored  on  edge,  closely
spaced with appropriate  dunnage,  to remove direct weight from
the  shipping frames.   During  operation,  thermal  and chemical
stresses  can  also result  in  plate deterioration.   Excessive
sparking can similarly produce localized plate distortion.

     The  plate  support structure  must be  rugged enough,   espe-
cially at welded seams, to withstand mechnical impulse, fatigue,
and the  vibration  provided  by the rappers.  Facility for align-
ment at  erection  and realignment  after the shakedown operation
must also be provided, especially since thermal stresses contri-
bute to misalignment.

4.1.3  Rappers

     Rapping systems for both collector and discharge electrodes
are  of  the  electromagnetic impulse,   electric   vibratory,  or
pneumatic  type.   Regardless  of the  type of  dust to be removed,
successful removal from the plates depends upon the formation of
a congruent  dust layer that, upon  rapping, will  fall in sheets
or  large agglomerates  into  the  hoppers.   (Dust  layers  on the
collection plate can approach 1 inch in thickness before rapping
occurs.)  Although dust deposits on the wires are usually small,
accumulated  dust  may  seriously   affect  the  current  density,
especially  since  the electrical  forces  tend  to  hold  the dust
more tenaciously to the discharge electrode than to the collection
plate.
                               49

-------
     Each manufacturer  prescribes  a particular type  of rapper,
based on the  application  and  the  compatibility with the suspen-
sion system,  the  requirements of the rapping  interval,  and the
intensity and length of  each cycle.   Pneumatic  rappers  impart
more  energy  than either  electromagnetic  rappers  or  electric
vibrators and are prescribed for  removal  of  tenacious  dusts.

     Rapper shafts that penetrate  the  ESP housing must be elec-
trically and  thermally insulated  to avoid electrical and air
leakage.  Thermal expansion  shaft  couplings  must also be  pro-
vided,  in addition to having positive heated air ventilation for
the rapper insulators.

     As  with  discharge  electrodes, rapping  systems  have  dif-
ferent designs in the United States and Europe.  The U.S.  design
is dominated by pneumatic and electrically operated vibrators or
impactors,   and  the European  design includes  mechanical rapping
systems.   In  the latter  case,  the rapper drive mechanism is
externally  mounted with a shaft that penetrates  the  ESP shell.
The shaft contains a series of hammers designed to hit anvils at
the lower end of  the collector plate electrodes and the center,
or  lower end, of  the discharge wire frame.   The  hammers  may be
staggered,   as in  single-frame  rapping,   or in parallel  groups
wherein  a  section or group of  frames  is rapped simultaneously.

4.1.4  Dust Removal Systems

     Hoppers  are  used to  collect  and store particulates removed
from the  electrodes.   In ESP applications  (in contrast to bag-
houses), center  dividing baffles  are  used to  prevent gas   from
bypassing  electrical  charging  zones.   Methods  available  to
remove  dusts   accumulated in hoppers  include containers,  dry
vacuum,  wet  vacuum,  screw,   and   drag   conveyors.   Vibrators,
thermal  insulation,  heating  cables,  and  steam tracing  may be
used to  make  the  contaminant fluid for  easy  removal.   For  con-
venience  in  removing  buildup and  excessive  dust accumulation,
poke holes  should  be provided.

     The hopper interiors must be free from all physical projec-
tions,   even  ladders,  that  may provide surfaces  for buildup.
Access  doors  to  hoppers must be  key interlocked.  Level alarms
should be installed;   if center hopper dividing baffles are  used,
a  level indicator is  needed  for  each  section.   If  only one
indicator  is  available,  the  side  that   is evacuated  would not
alarm even  if the  adjacent one was  full.

     Two-thirds of the dust collected by  the ESP is deposited in
the inlet hopper.  These  hoppers  also act  as settling chambers,
collecting  large  particulates  not  exposed   to  the  electrode
system,  and must  therefore be  properly  sized.   The hopper  sec-
tion and conveyor trough of the  ESP  must also  be  designed to
accommodate thermal expansion.
                               50

-------
4.1.5  Electric Power Supply

     Electrostatic  precipitators  operate  on  high-voltage  d.c.
power which is supplied with negative potential impressed on the
discharge electrodes.  The  power  supply consists of the voltage
control system (which varies the unfiltered voltage wave form as
applied  to  the  discharge  electrode);  the  step-up  transformer
(which  steps  up  line  voltage  to  required  precipitator  poten-
tial);  and  the rectifier (which converts  a.c.  to  d.c.,  full or
half  wave).    The  control  system  can  be  operated manually or
automatically  and  should be  operated with  the  largest voltage
possible  with minimum  arcing.  The  automatic  voltage  control
prevents  the  arcing potential from varying  as  the  type of gas,
composition,  humidity,   temperature,   and  dust  concentrations
change.   If excessive arcing  is allowed to occur,  the effective
potential to  the  ESP  is lowered,  collector  electrode  dust is
loosened  (assists  reentrainment),   and  the  discharge  electrode
wires tend to fatigue,  erode,  and melt.   When arcing does occur,
the  applied  voltage must be  rapidly  reduced  to extinguish the
arc.   This  is  the  function  of the  automatic  voltage  control
system.

     The  number  of  times per minute that electrical  breakdown
occurs  between the  discharge wire and collector  electrode is
called  the  spark  rate.   It  depends on the applied voltage for a
given set of precipitator conditions.   Increasing the spark rate
results  in  a  greater  percentage  of  input  power  being wasted.
Typically, a range of 50 to 150 sparks/min is considered normal.
Some  precipitators operate at the maximum voltage or  current
settings on the power supply with no sparking.  In collection of
low-resistant  dusts,  where the  electric  fiel'd  and  ash deposit
are insufficient to initiate sparking, no  sparking condition may
arise.  A precipitator not  sparking does not mean that the unit
is underworked.

     The behavior of both clean and dirty  electrodes is measured
by the  primary and secondary  voltage/current relationships from
the  transformer/  rectifier  (T/R) set.   Clean plate data should
be  acquired  after  process  shutdown  and  after completion of
sufficient rapping  to remove  plate and  wire dust accumulations.
This information provides a basis for comparison with subsequent
operational performance and is especially useful for identifying
electrical problems and equipment deterioration.

     Dirty plate  data  should  be acquired  during process opera-
tion and when rappers are off.

     Ideally the control panel should contain display meters to
monitor primary and  secondary voltage and secondary current and
spark  rate.   Although highly recommended,  a  secondary voltage
                               51

-------
meter is often not installed on the transformer.   This situation
can  be  alleviated by  the  temporary  installation of  a  voltage
divider  network.   The  control  cabinet  contains  all  required
devices and  instruments  needed to monitor  (display  meters)  and
control the  operation of  the ESP.   Positive air  ventilation,
provided by  a  filtered intake air fan,  helps to  protect the in-
ternal components of the  control cabinet.

     The T/R set,  which  is mounted on the  ESP roof,  is  usually
hermetically  sealed.  These components are  submerged  in a tank
filled  with   dielectric  fluid used  for  cooling.   The  tank  is
equipped with  high-voltage bushings,  liquid  level  gauge,  drain
valve, ground plug, filling plug,  lifting lugs,  and surge arres-
tors  (which  discharge any harmful transients appearing across
the d.c. metering circuit to ground).

     An electrical conductor in the form of a pipe transmits the
voltage output  to the support insulator  bushing,  which  is con-
nected  to  the  high-tension support  frame  from which  the dis-
charge  wires  are  suspended.  The  insulators are  housed  in  a
casing or compartment that must be kept clean and dry to prevent
ESP  dust and moisture  from accumulating.   Warm,  filtered, pres-
sured  air  is thus supplied to avoid  these  problems.   The pres-
sure  of the  air  delivered  to  the insulator housings  must  be
sufficiently  positive  to  override  the  pressure   in   the  ESP
casing.

4.1.6  Gas Distribution

     The overall  performance of the ESP, like that  of the bag-
house,  depends  on the  uniformity  of the gas distribution within
the  casing.   Adequate distribution of  flow is  provided by in-
stalling baffle plates or screens in the inlet transition to the
ESP.   Laboratory model studies  of flow  distribution  are often
performed to assist in the design of the baffles and the casing.

     The  ESP  provides  an  inlet  transition that  slows  flow
velocity  to  values  that  are  difficult to  measure  by  standard
pitot  tube  methods,  thus  requiring  hot-wire anemometry.  Non-
uniform  flow can  seriously  affect  performance.   If  it  is sus-
pected,  the   system  may  need  to  be  deenergized,  so  that flow
distribution can be measured.  Nonuniform flow may be identified
during  a period set  aside in the construction schedule  to allow
these measurements to be taken before startup.

4.1.7   Safety

     The  ESP and  its  associated components  require an unusual
set  of  safety precautions  compared  with  other  types  of air
pollution  control  equipment.   The high voltage  impressed on the
system  exposes workers to the danger of electrocution.   For this
reason, safety procedures must be developed.
                               52

-------
Safety Key Interlock System--
     A mechanical  safety interlock system must  be  designed for
all access  doors  and must  be  retrofitted on  older ESP's.   The
system  should be  an  integrally coupled  series of keys  that
performs the following sequence of controls:   when the system is
activated,  the  power  supply is  deenergized,  the  power  supply
load  for  the  ESP  is grounded by  a high-voltage  switch;  and all
power supplies on  a  given segment or subdivision of the ESP are
appropriately  grounded.   Interlock  keys are  obtained to  gain
access  to  that   particular  subdivision  only.   Good  design
practice includes the rapping and conveyor components within the
interlock system.

Grounding Hooks—
     Every ESP should be equipped with grounding hooks or chains
at usual maintenance access points.   The hooks are to be applied
to components within the reach of a worker from the  access door.
This precaution ensures that the high-voltage system is' grounded
and that  any  residual  or extraneous  electric charge is removed.

Grounding Network--
     The  grounding conductor  should  be sized according  to the
national  electric  code and  scaled according to  the capacity of
the maximum feeder cable feeding the power supply.  If the power
supply  contains  isolable  subassemblies,  it  will  have  short
circuit capability.  The grounding conductor must, therefore, be
continuous, starting  at the feeder  and forming  a  network  com-
bining all  points  of the power  supply  (control  cabinets,  regu-
lating components,  T/R set).  The ground should also extend to
the ESP structures (hopper junctions).

     During sparking and  arcing,  high currents flow in the form
of  pulses.   These  currents  flow on  the surface of conductors
rather than  through them, and the ground conductor should thus
be  adequately sized  for  the  available  surface.   Jumpers and
conductors  of  the  appropriate   size  are necessary to  ensure
electrical  integrity between  key components.   For  example,  a
lack of electrical  integrity could  arise in the components from
the power  supply to  the ESP.  The typical procedure is to use a
coaxial pipe  and  a grounded cylindrical  duct  known as  a guard.
The  guard  is  composed  of  individual  sections  with  bolted
flanges.   At  the  interface  of  each  flange,  a  jumper must be
provided to allow and maintain continuity of ground.

T/R Sets —
     The  T/R  components are immersed in  an  oil  bath of mineral
oil or  askarel fireproof oil.   If  askarel  oil  is  subjected to
arcing,  hydrogen  chloride   may  be  generated,   and  maintenance
personnel  should exercise extreme caution when  servicing these
components.   It  should  be  noted that  askarel  contains  poly-
chlorinated biphenyl  (PCB);  disposal of  this  oil thus requires
special consideration.
                               53

-------
Mechanical—
     The  ESP  has moving  parts that  are usually  controlled by
timers.  A worker could be injured if he enters a component when
the drive is  operating,  or if the drive is started  while  he is
inside  the  system.   Coupling  these  drives  (rappers and  con-
veyors) to  the  interlock  system is therefore recommended.   Dust
buildup on  uncleaned  collector electrodes  could break loose and
liberate  large  amounts of dust,  seriously  affecting vision and
breathing.

4.1.8  Conclusions

     It is  poor economy to shut down a plant  to repair  or ser-
vice  a poorly  designed  ESP.   The  following  are some of the
features  of modern  design that  contribute directly  to  opera-
tional reliability.

     High-voltage   support  insulators   mounted  in  individual
     roof-mounted,  insulator  housings  provide  several operation
     advantages:

          Insulators  are far removed from gas stream.

          Insulators  can be inspected, cleaned,  or replaced from
          above without entering casing.

          Insulator  compartment ventilation system  can  be ser-
          viced easily.

     Discharge  and collector  electrode  field  must be suspended
     from   shop-fabricated grids.

     Discharge  electrode wires  must be especially  fitted on both
     ends to  ensure good electrical contact, eliminating arcing
     and  extending  life.

     Casing roof,  walls,  and  hoppers  must be  of  clean exterior
     design to  facilitate application and  continuity  of thermal
     insulation.

     Pyramidal  hoppers must be equipped with flush access doors,
     poke holes,  steep valley  angles, and  large  flanged outlets.
     Hoppers  can  be  equipped with  heating  coils,  vibrators,
     hammers, and  dust level  indicators.

     Safety-key-interlocked,   quick-opening doors  provide  easy
     access through roof  and  sides of casing into  suitably  sized
     access  passages  above,   below,  and  between  every   high-
     voltage  discharge electric field.
                                54

-------
4.2  ELECTROSTATIC PRECIPITATOR OPERATION AND MAINTENANCE

     The previous  sections provided  background information  on
the various operational  components  of the ESP,  particularly the
design  features  that will improve  performance  and reduce main-
tenance.  Proper  operation and maintenance  of  an EPS  also re-
quires  familiarity with  procedures  for equipment startup, shut-
down,  inspection, recognition of common malfunctions,  and trouble-
shooting.  These  procedures  are concisely  prepared  to simplify
the inspection, observations,  and interpretations of the various
components.   Discussion of the cause and effect relationship and
the impact on performance is also provided.

4.2.1  Pre-Startup Inspection

     The inspection  performed before  startup is critical to the
performance of an  ESP.   The  precipitator may not be operational
for one of three reasons:

     New installation requiring shakedown and debugging

     Process shutdown resulting in ESP shutdown

     ESP shutdown for maintenance

     Regardless  of  the  reason  for   shutdown,  an  opportunity
exists  while the  unit  is down to perform a thorough inspection.
An example  of  a checklist for  visual and mechanical  inspection
is provided in Figure 6.

     This checklist  is a guideline only.  A specific list should
be tailored  for  each ESP  system.   The inspection  survey during
shutdown  should  include  all  ductwork  and  components  from the
upstream emissions source to the stack.

4.2.2  Routine Startup

     After the precipitator  has been thoroughly inspected, the
unit  should  be  buttoned up  (following  all  safety procedures).
An outline procedure for routine startup is given below.  Power
on/off  buttons with green and  red lights  are  usually provided
for components.

     1.   Follow  key  interlock procedures  for closing access
          doors.

     2.   Preheat   insulator  compartments   for  several  hours
          before energizing system.

     3.   Activate  dust handling  system (air  lock,  screw con-
          veyors, etc.).
                               55

-------
ISP WEOPERATION AND INSPECTION CHECKLIST
APPLICATION '-
DATE/TIME1

REPORT BY:
DISCHARGE ELECTRODES
UPPER SUPPORT FRAME
LOWER SUPPORT FRAME
HANGER SUPPORTS
ANTISWING SUPPORTS
HEIGHTS
WIRES
ALIGNMENT
CORROSION
BUILDUP
COMMENTS
COLLECTOR ELECTRODE
WARPAGE
SUPPORT
SPACERS
GUIDES
ALIGNMENT
CORROSION
BUILDUP
COMMENTS
GAS SNEAKAGE BAFFLES
COMMENTS
RAPPERS (COLLECTOR/DISCHARGE)
MECHANICAL/ELECTRICAL CONNECTIONS
BUILDUP
CORROSION
COMMENTS
HOPPER
DUST LEVEL INDICATORS
OUTLET CONNECTIONS
ACCESS DOORS
POKE HOLES
HEATERS
INSULATORS
OOCMENTS
Page 1 of 2


CHECKED
YES

a
a
a
a
D
a
a
a
a


a
a
a
a
a
a
a




a
a
tn


a
a
a
a
a
a


NO

D
a
a
a
a
a
a
D
a


a
o
a
a
a
a
CD




a
D
a


a
a
a
a
a
a



KBQ.
ATTN.

a
a
0
a
a
n
a
a
a


a
a
a
a
a
a
a




n
a
i=i


a
a
a
a
CD
O


Figure 6.   Preoperation and inspection  checklist  for  electrostatic  precipitator.




                                      56

-------
CHECKED


SCREW CONVEYOR
DEBRIS
BUILDUP
CORROSION
MOTOR
SCREW DRIVE
HANGER BEARINGS
TAIL SHAFT BEARING
COMMENTS
T/R SET
SURGE ARRESTOR GAP
TRANSFORMER LIQUID LEVEL
GROUND CONNECTIONS
HIGH TENSION BUS DUCT
CONDUITS
FULL WAVE SWITCH BOX
ALARM CONNECTIONS
GROUND SVJTTCH OPERATION
HIGH VOLTAGE CONNECTIONS
REGISTER BOARD
COMMENTS
INSULATOR COMPARTMENT
FILTER COMPARTMENT
DUCTS/INSULATION
FLOW
TEMPERATURE
MOTOR
PRESSURE
HEATER
COMMENTS
GAS DISTRIBUTION
INLET/OUTLET TRANSITION
JOINTS
BUILDUP
CORROSION
COMMENTS
BAFFLES
VIBRATORS
JOINTS
WARP AGE
BUILDUP
CORROSION
COMMENTS
PUCTS (INLET/DUT/STACK)
LEAKAGE
JOINTS
GASKECTNG
DAMPERS
COMMENTS
Page 2 of 2

YES

a
a
CD
CD
CD
m
CD


a
a
CD
CD
n
a
CD
a
n
a


CD
CD
CD
a
a
CD
a


a
a
a
a


a
CD
CD
a
CD


D
a
a
a



NO

a
a
a
a
a
a
a


a
a
a
a
a
a
a
a
D
o


a
a
a
a
a
CD
D


a
o
a
0


n
a
a
n
0


n
CD
a
P



REQ.
MTN.

a
a
a
a
a
CD
0


a
a
CD
CD
a
O
CD
CD
a
a


a
CD
a
a
ID
a
a


n
O
a
a


CD
CD
CD
CD
ED


D
CD
CD
n


Figure 6 (continued)




                                      57

-------
    4.   Operate  discharge  and  collector  electrode  rapping
         system.

    5.   Operate gas distribution baffle plate vibrators.

    6.   Turn  on high  voltage  (manual  mode)  for  one section
         only  and bring  up input  voltage slowly  (10 percent
         increments)  to  rated  voltage or  rated current while
         recording  panel  meter readings.   This  procedure is
         commonly  referred to  as   an  airload test.   The  test
         establishes reference  readings and checks  operation of
         electrical  equipment,  clearances,  etc.   After these
         readings  are  recorded, turn  down high voltage on the
         field  and similarly  perform an  airload  test  on the
         next  field.    If excessive sparking  or d.c. readings
         are  obtained,   another internal  inspection may be
         necessary.

    7.   If system operates satisfactorily, turn off  T/R sets.

    8.   Open bypass dampers.

    9.   Start  blower

    10.    If possible,  preheat  the ESP  by pulling hot,  clean air
         through  the  system,  thus  avoiding  condensation of
         moisture  and contaminant  gases.  Buildup  of  condensed
         material  on electrodes is difficult  to remove:  ener-
         gize one  field only  to minimize the  effect.

    11.   Allow   contaminant gases  to pass through  the unit.

    12.   Record data  from monitoring instrumentation (fan motor
          amperage   and  voltage;  temperatures;   a.c.   voltage/
          current;  d.c.  voltage/current;  spark rate).

4.2.3   Routine  Inspection and  Maintenance During Operation

    During  routine  operation,  an inspection  procedure  that
includes a  recording  of  ESP operation data should be used.   A
sample  of  a routine  daily inspection checklist for  an  ESP  is
provided in Figure 7.   Only  visual inspection  of the  unit  is
possible, and therefore only instrumented operational parameters
can be  obtained.  The  checklist gives  direction and guidance to
a maintenance worker for  items  to  observe  and check.   A tailor-
made checklist should be prepared by the user and vendor that is
based  on the specific components and monitors.
                               58

-------
                   ESP OPERATING INSPECTION AND MAINTENANCE CHECKLIST
     APPLICATION:
     DATE/TIME:   	           CHECKED
                                                                  REQ.
     REPORT BY:                                 YES       NO        ATTN
     T/R SET

          LIQUID LEVEL                          O       CD        O
          TEMPERATURE                           C3       Q        O
          NOISES                               a       CD        a
          LEAKS                                d       D        CD
          COMMENTS

     HIRE RAPPERS
          MOTOR/LUBRICATION                     ODD
          SEQUENCING                           D       O        a
          NOISE                                D       D        CD
          COMMENTS

     COLLECTOR RAPPERS  '

          MOTOR/LUBRICATION                     CD       O        D
          SEQUENCING                           D       d        CD
          NOISE                                C3       D        CD
          COMMENTS

     INSULATOR COMPARTMENT

          MDTOR/BLOWER                          a       D        d
          FILTER                               O       d        O
          DUCTS                                a       a        a
          DAMPER                               ODD
          INSULATION                           D       a        a
          PRESSURE                             D       d        D
          TEMPERATURE                           C3       D        CD
          OBMENTS
     HOPPERS
          NOISES                               an
          AIR LEAKS                            C3       D
          GASKETS                              CD       D
          HEATERS                              C3       CD
          ACCESS DOORS                         O       D
          COMMENTS
                                Page 1 of  2
Figure 7.   Operating inspection and maintenance  checklist  for  an
                       electrostatic  precipitator.

                                     59

-------
                                                               CHECKED
                                                                                 REQ.
                                                            YES       NO         ATTN.
                 MATERIAL HANDLING SYSTEM

                      OPERATING                             D        D         C3
                      NOISES                                D        D         D
                      LUBRICATION                           CD        D         D
                      AIR LEAKS                             OD         D
                      MOTORS                                O        D         O
                      BEARINGS                              Od         O
                      COMMENTS

                 DUCTS  (INLET/OOTLET)

                      NOISES                                o        a         a
                      LEAKS                                 EDO         O
                      COMMENTS

                 TRANSITIONS  (INLET/OUTLET)

                      NOISE                                 D        a         tn
                      LEAKS                                 a        D         a
                      COMMENTS

                 STACK APPEARANCE

                      COMMENTS
                                                         OPERATING  DESIGM

                 COLLECTOR MEASUPEMENT

                      TEMP:  IN                          ;	    '.	       D
                      TEMP:  OUT                         	    	       Q
                      PRESSURE DROP                      	    	     •  a
                      STATIC PRESSURE:  IN               	    	       d
                      STATIC PRESSURE:  OUT              	    	       a
                      FLOW RATE                          	    	       £3
                      PRIMARY VOLTAGE                    	    	       CD
                      PRIMARY CURRENT                    	    	       Q
                      SECONDARY VOLTAGE                  	    	       1-1
                      SPARK RATE                         	    	       CD
                      COMMENTS
                 BLOWER
                      CURRENT                            	    ______      n
                      VOLTAGE                            	    	       D
                      RPM      .                          	    	       a
                      STATIC PRESSURE                    	    	       r~l
                      BELT TENSION                         D        CD         O
                      BEARING. LUBRICATION                  D        D         d
                      DAMPER   -                            D        O         D
                      COMMENTS
                                            Page  2 of  2
Figure  7  (continued)

                                                 60

-------
4.2.4  Routine Shutdown

     An ESP  is  shut down primarily because of  routine  or emer-
gency  process  shutdown,  routine  ESP maintenance,  or  emergency
ESP malfunction.   In these situations, the ESP should  continue
to be operated until it is purged with clean air.  The following
steps are then taken:

     1.   Stop blower.

     2.   If  possible,  isolate  ESP  by  closing  inlet/outlet
          dampers.

     3.   Shut down T/R set.

     4.   Continue  to operate  rapping  and dust  removal  system
          until wires  and  plates  are believed to be clean; then
          shut down rappers and dust removal  system (make sure
          that hoppers are clean).

     5.   Open access doors following interlock procedure.
          Note:  Hopper access doors should be opened with
                 care ' because  hot  dust may  be  packed against
                 them.

     6.   Use ground  hooks  to remove extraneous electric charge
          buildup.

     7.   Allow system to  cool  and  dust to settle before enter-
          ing.

     8.   Allow  insulator  compartment  vent  system  to  operate.

4.2.5  Maintenance During Shutdown

     When  the ESP  can be  entered,  internal  inspection  can be
commenced.   It  is   advisable  to leave  the  insulator compartment
vent heaters  on during  shutdown  to prevent moisture  from con-
densing  on the  high-voltage  insulators.  The high-maintenance
items,  in decreasing order of prevalence, are:

     Discharge electrode breakage

     Plugged hoppers

     Insufficient rapping

     Insulator bushing failure

     Electrical component breakdown.
                               61

-------
     The checklists provided  in  Figures  6 and 7 can be  used to
provide  a  methodical  program  of  inspection  during  shutdown.
These  checklists  will also provide an excellent mechanism  for
maintenance recordkeeping.

4.2.6  Common Malfunctions

     Other  than  changes  in process  conditions,  the  most common
malfunction  associated  with   ESP  performance   is  from  broken
discharge  wires  and plugged  hoppers.  A detailed list  of  the
causes  and effects  of  malfunctions,  categorized according to
functioning component, is given in the following pages.  In some
cases, solutions to the problems are provided.   Table 3 provides
a summary of common ESP malfunctions.

Discharge Electrodes-
     In  a  weighted wire design,   a  broken wire  may  swing freely
and  cause  shorting between discharge  and collector electrodes,
usually  immobilizing  an entire  field.   Wire  breakage  results
from electrical, mechanical, or chemical problems.

     Electrical:

          Electric  erosion (arcing)  is  the principal  cause of
           failure.

          Minimum  clearance between  electrodes results  in  re-
          peated  sparkover,  causing  local heating  and  vapori-
           zation  of  metal.   The  tension  from  the  suspension
          weights causes ultimate failure.

           Breakage  can  occur on shroud  as  well  as wire  and
           usually occurs  on the lower portion of wire.

     Mechanical:

           Excessive rapping breaks  wire.

           Crimps  and bends are  sources  of fatigue with  rapping
           and vibration.

           Poor  electrical  alignment causes  the wire  frame  to
           oscillate,  fatiguing  wires and increasing sparking.

           Swinging  wire  frames  can  often be  detected  by  lis-
           tening for  the regular  snap of  the arc-over.

      Chemical;

           Acid  gases  corrode  wires.  Material  flakes  off during
           rapping,  thus  exposing  new  surfaces  to  additional
           corrosion attack.
                                62

-------
                          TABLE  3.    SUMMARY OF  PROBLEMS ASSOCIATED  WITH  ELECTROSTATIC  PRECIPITATORS
            Malfunction
                                                 Cause
                                           Effect on
                                          ESP efficiency
                                                                                                           Corrective action
                                                                                                                                     Preventive measures
            Poor electrode alignment
            Broken electrodes
U>
            Distorted  or  skewed
             electrode plates
            Vibrating or  swinging
             electrodes
Poor design
Ash buildup on  frame hoppers
Poor gas flow

Hire not rapped clean, causes an arc
 which embrittles and burns through
 the wire.
Clinkered wire.  Causes:  a) poor
 flow area, distribution through unit
 is uneven; b)  excess free carbon due
 to excess  combustion air or fan
 capacity Insufficient for demand
 required;  c) wires not properly
 centered;  d) ash buildup resulting
 in bent frame,  same as c); e) clinker
 bridges the plates and wire shorts
 out; f) ash buildup, pushes bottle
 weight up  causing sag In the wire;
 g) J hooks have improper clearances
 to the hanging wire; h) bottle
 weight hangs up during cooling,
 causing a  buckled wire; 1) ash build-
 up on bottle weight to the frame
 forms a clinker and burns off the
 wire.

Ash buildup In  hoppers
Gas flow Irregularities
High temperatures
Uneven gas  flow
Broken electrodes
Can drastically  affect
 performance and lower
 efficiency

Reduction 1n efficiency due
 to reduced power input,
 bus section unavailability
                                                                                                           Realign electrodes
                                                                                                           Correct gas  flow
                                                                                                           Replace electrode
Reduced efficiency
Decreases  1n  efficiency due
 to reduced power Input
Repair or replace plates
Correct qas  flow
Repair electrode
                          Check hoppers frequently
                           for proper  operation
                          Boiler problems; check
                           space between recording
                           steam and  air flow pens,
                           oressure gauges; fouled
                           screen tubes.

                          Inspect hoppers
                          Check electrodes frequently
                           for wear
                          Inspect rappers frequently
Check hoppers frequently
 for proper  operation;
Check electrode plates
 during outages

Check electrodes fre-
 quently for wear
       (continued)

-------
TABLE 3 (continued)
Malfunction
Inadequate level of power
Input (voltage too low)






Back corona



Broken or cracked
Insulator or flower pot
bushing leakage


A1r leaks 1n through
hoppers


Air leaks in through
ESP shell
Gas bypass around ESP:
-dead passage
above plates
-around high tension
frame
Cause
High dust resistivity
Excessive ash on electrodes
Unusually fine particle size
Inadequate power supply
Inadequate sectionalizatlon
Improper rectifier and control
operation
Misalignment of electrodes
Ash accumulated on electrodes
causing excessive sparking.
requiring reduction in voltage
charge
Ash buildup during operation
causes leakage to ground
Moisture gathered during shut-
down or low load operation

From dust conveyor



Flange expansion

Poor design - Improper isolation
of active portion of ESP



Effect on
ESP efficiency
Reduction in efficiency

1





Reduction 1n efficiency



Reduction in efficiency




Lower efficiency; dust
reentrained
through ESP

Same as above, also causes
intense sparking
Only small percentage drop
in efficiency unless
severe


Corrective action
Clean electrodes;
gas conditioning or
alterations in
temperature to reduce
resistivity;
Increase section-
alization

Same as above



Clean or replace
insulators and
bushings


Seal leaks





Baffling to direct
gas into active ESP
section


Preventive measures
Check range of voltages
frequently to make sure
it is correct in situ
resistivity measure-
ments



Same as above



Check frequently
Clean and dry as needed;
Check for adequate
pressurization on top
housing
Identify early by
increase in ash con-
centration at bottom of
exit to ESP


Identify early by measure-
ment of gas flow in sus-
pected areas


(continued)

-------
       TABLE  3  (continued)
             Malfunction
                                                   Cause
                                            Effect on
                                          ESP efficiency
                                                                                                              Corrective action
                                                                                                                                         Preventive measures
             Corrosion
             Hopper pluggage
CTi
Ul
              Inadequate rapping,
              vibrators fall
             Too Intense rapping
Temperature goes  below dewpolnt
Wires, plates,  Insulators fouled
 becaused of low temperature
Inadequate hopper insulation
Improper maintenance
Boiler leaks causing excess
 moisture
Ash conveying system malfunction:
 gasket leakage, blow malfunction,
 or solenoid valves
Misadjustment of hopper  vibrators
Material dropped into hopper from
 bottle weights
Solenoid, timer malfunction
Suction blower filter not changed

Ash buildup
Poor design
Rappers misadjusted
Poor design
Rappers misadjusted
Improper rapping force
Negligible until  pre-
 cipitation Interior plugs
 or plates are eaten away;
 air leaks may develop,
 causing significant drops
 in performance

Reduction 1n efficiency
Maintain flue gas
 temperature above
 dewpoint
Provide proper flow
 of ash
Resulting buildup on
 electrodes may reduce
 efficiency
Reentralns ash, reduces
 efficiency
Adjust rappers with
 optical dust measure-
 ing instrument in ESP
 exit stream

Same as above
Energize precipltator
 after boiler  system has
 been on line  for ample
 period to raise flue gas
 temperature above  acid
 dewpoint

Frequent checks for ade-
 quate operation of hoppers
Provide heater thermal
 Insulation to avoid
 moisture condensation
Frequent checks for ade-
 quate operation of
 rappers
Same as above
Reduce vibrating or impact
 force
        (continued)

-------
TABLE 3 (continued)
Malfunction
Control failures








Sparking




Cause
Power failure 1n primary system
Transformer or rectifier failure:
a) Insulation breakdown In trans-
former
b) arcing In transformer between
high voltage switch contacts
c) leaks or shorts 1n high voltage
structure
d) Insulating field contamination
Inspection door ajar
Boiler leaks
Plugging of hoppers
Dirty insulators

Effect on
ESP efficiency
Reduced efficiency








Reduced efficiency




Corrective action
Find source of failure
and repair or replace







Close inspection
doors; repair
leaks in boiler;
unplug hoppers; clean
insulators
Preventive measures
Pay close attention to
daily readings of control
room instrumentation to
spot deviations from
normal readings




Regular preventive main-
tenance will alleviate
these problems



-------
     Wire buildup is not usually due to insufficient rapping but
to  some  other factor,  such  as  process change.   Uniform buildup
can  have the effect  of  creating  a  larger diameter  wire and
requiring higher  voltage to  initiate  ground current.   A sudden
failure  or  rash of  failures  can occur from process changes or
extreme malfunction in the ESP.

     In a rigid frame design, one broken wire does not result in
the  failure  of  the  entire  bus  section.   High "G"  forces  in
rapping  rigid  wire  frames   can  lead  to premature  mechanical
failure near  the impact point, at connection to support members,
sharp bends,  and welded connections.  High resistivity dusts are
very  tenacious and need  high rapping  forces,  thus  requiring
European design.

Rappers (Vibrators/Impulse)—
     Impulse  electric  or pneumatic rappers  are more successful
in  difficult  rapping applications  than  are  electric vibrators.

     Pneumatic  rappers  are  beneficial  in  warm,  high-moisture
ambient environments.   If  the temperature falls below freezing,
however,   pneumatic  is  not  recommended  because the  entrapped
moisture in the air lines  may freeze unless adequate air dryers
are installed.

Rappers (Mechanical Failures)—
     Failures  occur in the transmission  hardware at the inter-
     face of  a high-strength alloy and mild  steel  components.

     Poor  quality  of  welds  from  rapper  to support  frame may
     result  in cracks;  frequently encountered weld  types are
     butt joint, cup joint, gusset joint.   Good welding practice
     is to preheat and postheat.

     Rapper binds  due to misalignment during installation.

     Rapper rod  seizure occurs  from  the  leakage and improper
     seals and dust accumulation.

Collector Electrodes—
     Plate  corrosion  results  from  gas temperature  going below
dew point and allowing condensation to occur on lower portion of
plate.   Air leakage into hopper also  produces  condensation and
corrosion on electrodes.

     Mechanical failure  at supports  can  occur from  poor  con-
struction or assembly and overrapping.
                               67

-------
Dust Removal System--
     Plugging is the main problem and could result from moisture
condensation, with  its  associated  dust  agglomeration and caking
within the  hopper.   Dust buildup  will  eventually contact high-
voltage electrode frame and short out high-voltage bus sections,
misalign electrodes,  and form clinkers by ash fusion  from  the
high-voltage  current.   Hopper  and  heaters  should be  operated
continuously to avoid buildup.

Housing and Casing—
     Air leaks and infiltration (causing corrosion) can occur at
expansion joints,  slip joints,  and  inlet/outlet  ducts.   Should
acid/gas temperature  go below dew point,  condensation can also
result in corrosion.

     Coupons of  aluminum,  corten,  and stainless steel are often
placed  inside the  unit  to  study the  corrosion  resistance  of
these materials.   Coatings such as  coal  tar epoxy  are  used to
eliminate corrosion.

Insulators--
     Dust and/or moisture  accumulation  on the insulator surface
could  lead   to  electrical  arc-over   as  evidenced by tracking.
Excessive arc-over  could  result  in insulator cracking or break-
age.   Filtered  and heated purge  air  prevents fouling  of  the
insulators,  bus bars, and bus ducts.

4.2.7  Spare Parts

     The ESP manufacturer should  supply  a  list  of  recommended
spare parts.   The  spare parts required are  usually  those asso-
ciated with moving and rotating components.  A summary list of
replacement  parts   is  provided  in  Table  4.   The user  of  the
equipment will develop  a spare  parts inventory according to the
type and frequency of part failure.

4.2.8  Troubleshooting Program

     Should  a major problem bring the  need  for a thorough sur-
vey, a multiphase  troubleshooting  program as outlined is recom-
mended.  An  actual case history of such a program is provided in
Appendix A.

4.2.9  Troubleshooting Procedures

     Guidelines  for troubleshooting  and correcting ESP malfunc-
tions  are provided in  Table  5.    This chart is used as a diag-
nostic aid  to troubleshoot specific symptoms.   A supplementary
approach to  evaluate operational problems  is to interpret abnor-
mal  electrical  meter  readings  from the  ESP  control cabinet.
Table 6 is  a general guide prepared  for this purpose.
                               68

-------
         TABLE 4.  REPLACEMENT PARTS FOR ELECTROSTATIC PRECIPITATORS
Discharge electrodes:

Collector electrodes:

T/R set:

Voltage controller:


Dust handling system:
Insulator compartment
 ventilation system:

General supplies:
Wires, weights, fastening hardware

Antisway insulator

Insulators, rectifiers

Printed circuit boards, switches, relays,
fuses.

Level indicators, motor bearings, seals,
solenoids.


Filters, motors, heating elements

Gasketing,  silicone grease, chamois
cloth, lubricants, special tools
                                     69

-------
               TABLE 5.   TYPICAL TROUBLESHOOTING  CHART FOR  AN
                         ELECTROSTATIC  PRECIPITATOR
Symptom
     Cause
     Remedy
No primary voltage.
No primary current.
No precipitator
 current.
Vent fan on.
Alarm energized.
No primary voltage.
No primary current.
No precipitator
 current.
Vent fan off.
Alarm energized.

Control  unit trips out
 on overcurrent when
 sparking occurs at
 high currents.
High primary current.
No precipitator
 current.

No primary voltage
No primary current.
No precipitator
 current.
Vent fan on.
Alarm  not energized.

Same as above, even
 after replacing  com-
 ponents or subpanels,
 changing wires,  or
 repair.
Overload condition
Misadjustment of
 current limit control

Overdrive of SCR's
Relay panel fuse blown

Circuit breaker tripped

Loss of supply power
Circuit breaker defec-
 tive or incorrectly
 sized
Overload circuit in-
 correctly set
Short circuit condition
 in primary

Transformer or recti-
 fier short
 SCR  and/or diode
  failure
 No firing pulse from
  firing circuit and/or
  amplifier
 SCR's  being  fired  out
  of  phase
Check overload relay settings.
Check wiring components.

Check adjustment of current
 limit control setting.

Check signal from firing
 circuit module.

Replace.

Reset circuit breaker.

Check supply to control unit.


Check circuit breaker.
Reset overload circuit.
Check primary power wiring.
Check transformer and
 rectifiers.
 Replace.

 Check  signal  from  firing
  circuit  and/or  amplifier.
 Reverse  input wires.
 (continued)
                                      70

-------
Table 5 (continued)
Symptom
     Cause
Remedy
Low primary voltage.
High secondary
 current.
Abnormally low pre-
 cipitator current and
 primary voltage with
 no sparking.
Spark meter reads
 high -- off scale.
Low primary voltage
 and current.
No spark rate indi-
 cation.
Spark meter reads
 high; primary
 voltage and current
 very unstable.

Neither spark rate,
 current, nor voltage
 at maximum.
Short circuit in
 secondary circuit or
 precipitator
Misadjustment of cur-
 rent and/or voltage
 limit controls

Misadjustment of firing
 circuit control
Continuous conduction
 of spark counting
 circuit

Spark counter counting
 60 cycles peak

Failure

Misadjustment of PC-501

Loss of limiting con-
 trol

Misadjustment of PC-501

Failure

Failure of signal
 circuits.
Check wiring and components
 in H.V.  circuit and pipe
 and guard.
Check precipitator for:
 Interior dust buildup
 full hoppers
 Broken wires
 Ground switch left on
 Ground jumper left on
 Foreign material on H.V.
  frame or wires
 Broken insulators.

Check settings of current
 and voltage limit controls.
Turn to maximum (clockwise)
 and check setting of current
 and voltage limit controls.

Deenergize, allow inte-
 grating capacitor to dis-
 charge, and reenergize.

Readjust.
Replace.

Readjust.

Replace.


Readjust setting.

Replace.

Check signal circuits.
(continued)
                                     71

-------
Table 5 (continued)
Symptom
     Cause
Remedy
No spark rate
 indication;
 voltmeter and am-
 meter unstable,
 indicating sparking.
No response to current
 limit adjustment;
 however, does respond
 to other adjustments.
No response to voltage
 limit adjustment;
 however, does respond
 to current adjustment.
No  response to spark
  rate  adjustment;
  however, does respond
  to other adjustment.
Failure of spark meter

Failure of integrating
 capacitor

Spark counter sensi-
 tivity too low

Controlling on spark
 rate or voltage limit
Failure

Current signal defec-
 tive

Controlling on current
 limit or spark rate
Voltage signal defec-
 tive

Failure

Controlling on voltage
 or current
                          Failure
Replace spark meter.

Replace capacitor.


Readjust.


None needed if unit is
 operating at maximum
 spark rate or voltage
 adjustment.
 Reset voltage or spark
 rate if neither is at
 maximum.

Replace.

Check signal circuit.
None needed if unit is
 operating at maximum
 current or spark rate.
 Reset current and spark
 rate adjustment if
 neither is at maximum

Check voltage signal circuit.
 Replace.

 None  needed  if  unit  is
  operating at maximum
  voltage  or  current.
  Reset  voltage  and current
  adjustment  if  neither  is
  at maximum.

 Replace.
 (continued)
                                      72

-------
Table 5 (continued)
Symptom
     Cause
Remedy
Precipitator current
 low with respect to
 primary current.
Low or no voltage
 across ground return
 resistors.
Surge arresters shorted


H.V.  rectifiers failed

H.V.  transformer failed

Ground or partial ground
 in the ground return
 circuit.
Reset or replace surge
 arresters.

Replace H.V.  rectifiers.

Replace H.V.  transformer.

Repair ground return
 circuit.
                                     73

-------
     TABLE 6.  GUIDE FOR INTERPRETING ABNORMAL  METER  READINGS
 1.   Increasing gas temperature  results  in  a  corresponding volt-
     age increase and current decrease  (arcing can develop).
     Conversely, decreasing  gas  temperature will result  in volt-
     age diminution and current  increase.

 2.   An increase in moisture content  at  given process conditions
     will  result in a relatively small  increase  in current and
     voltage levels,

 3.   Excessive sparkover may result from additional moisture and
     is indicated by a voltage increase.

 4.   Grain loading increase  will  somewhat  elevate voltages and
     reduce current.

 5.   A particle size decrease will be reflected  in a voltage
     rise and diminished current.

 6.   Gas velocity (flow rate) increase  will tend to  increase
     voltages and depress current.

 7.   Air leakage may cause additional sparkover  and  reduced
     voltage.

 8.   During normal operation for individual power  supplies,  the
     voltage/current ratio will  decrease in the  direction  of gas
     flow.

 9.   Hopper overflow will result in  shorting  and drastically
     reduced voltage and current increase.

10.   Broken, swinging discharge electrode  wires  result  in  violent
     arcing and extreme and erratic  meter  behavior.

11.   A T/R short results in zero voltage and  high  current.

12.   Buildup on wires is accompanied  by a  voltage  increase to
     maintain same current level.

13.   Buildup on plates is accompanied by a voltage decrease to
     maintain same current level.
                                  74

-------
4.3  WET ELECTROSTATIC PRECIPITATORS

     The functional  design  of wet  ESP's  is similar  to  that of
the dry ESP's; the  main difference  is that the collected parti-
culates are dislodged  from  the  collecting surface by continuous
water  spray  or by  a  cascading  water sheet.   The  wet  electro-
static precipitators (WEP) now in use are of the plate-,  concen-
tric-plate-,  or pipe-type design.  Wet precipitators find appli-
cation in the aluminum, iron,  steel, and glass industries.

     According to   the application,  the  WEP  is  an  attractive
alternative to the  wet scrubber, ESP,  and  baghouse.   For exam-
ple, a condensible,  submicron hydrocarbon emission can easily be
removed  by  WEP  rather  than  by  using  a  high-energy  venturi
scrubber.  The problem of high or low dust resistivity is elimi-
nated  in WEP's  because the collector electrode  is continuously
flushed.  The resistivity of  the water film (which is very low)
is the governing factor in the dust discharging process,  not the
resistivity  of  a dust layer formed  by  collected particulate.

     The gas to be treated by a WEP must be saturated with water
vapor before it enters the  unit.  Consequently,  the performance
of  the  WEP is not very sensitive to  gas  temperature.  Further,
since  the  internal  components are  continuously  washed,  the WEP
will  also  remove  gaseous pollution so  long as  the gaseous com-
ponent is soluble in the washing liquor.

     Many of the components  of  a WEP are similar  to  those of a
dry ESP; therefore,  many of the remarks  made  in Sections 4.1.1
through 4.1.7 are also applicable.


4.4   WET  ELECTROSTATIC  PRECIPITATOR  OPERATION  AND MAINTENANCE

     As  one  would  expect,   the  WEP  has a  high  potential  for
corrosion and scaling  and requires a water treatment system.  If
the wash liquor is to be recycled through the WEP, which in most
cases  is necessary  to  save  on water consumption, the same water
treatment  methods   used  with scrubbers  must  be  applied (see
Section  5).   Concentration  of  suspended and dissolved solids
must  be maintained,  in addition to  pH  control.   The  clarifi-
cation  of  solids must be  sufficient to minimize  spray nozzle
plugging and buildup  of recycled materials  on the internal mem-
bers  of the precipitator.   If  condensible materials  are being
collected,  means  for  removing  them  must be provided  (such as
skimming devices or methods for sludge removal).

     The dissolved  solids concentration must  be maintained at a
steady  and acceptable level,  either  by the  right amount  of
purging, by chemical treatment,  or both.
                               75

-------
4.4.1  Pre-Startup Inspection

     Before starting  up  the WEP,  a  thorough inspection of  the
system is  required.   The procedure  and  checklist to  follow  is
provided in 4.2.1,  with  the exception of items applying to  the
water cleaning system.

     Water Cleaning System:

          Turn  on  water cleaning  system  and check  all  pipe
          connections for leaks.

          Check for adequate water flow.

          Check individual water line pressure

          Check angles and  direction of nozzle spray.   Correct
          nozzle positioning is  necessary to  obtain coverage of
          precipitator internals.

          Inspect drain  system to  ensure that wastewater drains
          freely.     {

          Check for  adequate clearance between piping and high
          voltage system.

     A WEP preoperation and inspection checklist can be compiled
from Figures 6 (page 56)  and 8 (page 88).

4.4.2  Routine Startup

     Follow procedure in 4.2.2, except replace-Items 3, 4,  and 5
with  activation of  spray  system as  given  in  5.2.2,  Items  1
through 6.

4.4.3  Routine Inspection and Maintenance During Operation

     Only  visual  inspection of  the  external components of  the
system is  possible  during  operation.  Therefore,  only instru-
mented operational  parameters can  be observed,   along  with  in-
spection  of  electromechanical  equipment  and  structural  com-
ponents.   A routine  daily inspection checklist for a WEP can be
made from Figure 7 (page 59) excluding the entry for Rappers and
Figure  9  (page  91)  excluding the  entry  for Mist Eliminator.
Since  actual   inspection and  maintenance practices  are  quite
specific to the particular  system used, a  tailormade checklist
should be prepared by the user and vendor.
                                76

-------
4.4.4  Routine Shutdown

     Follow 4.2.4, Items  I,  2  and 3; replace 4 with Items 3, 4,
5,  and  6  from  5.2.4;  then  proceed with  5,  6,  7, and  8 from
4.2.4.

4.4.5  Common Malfunctions

     Scaling, buildup,  and corrosion are  commonplace  in WEP's.
These conditions are prevalent not only within the liquor recir-
culating  system,   but  also  in  the electrostatic  precipitator
housing.   Liquor  clarification   and   chemical   treatment  are
critical to WEP performance.   Thorough familiarity with scrubber
and dry ESP troubleshooting procedures are necessary in order to
properly diagnose WEP malfunction and poor performance.

     A  case  history  of a  WEP  is provided  in  Appendix A, which
outlines  the  use of  the multiphase  troubleshooting  program.
                               77

-------
                            SECTION 5

                TECHNICAL ASPECTS OF THE DESIGN,
             OPERATION,  AND MAINTENANCE OF SCRUBBERS
     Wet scrubbers  are  air pollution control  devices  that pro-
vide an  environment to enable flue gas  contaminants  to contact
impaction targets, generally water droplets.   The wetted contam-
inant impinges  on collection surfaces  (entrainment  separators)
and removes the  contaminant-laden  droplets  from the  gas stream.
Although there  are devices  that  use  mechanisms such  as  steam
condensation,  electrostatic charging, or sonic agglomeration in
conjunction with conventional scrubber mechanisms, they will not
be  discussed  here  because  applications  are  few and  the  tech-
nology  is  still  in  the  early  stages of  development.    The
emphasis in this section is also focused on particulate removal,
not gaseous removal.

     The collection efficiency of wet scrubbers varies according
to  design  and  total  power expended  both in  forcing  the  gases
through the collector and in  generating liquid contact surfaces
(droplets).   Scrubber  manufacturers  promote  their product ac-
cording  to such  parameters  as  particle size  collection  effi-
ciency and mass collection efficiency.

     The scrubbing liquid  is  introduced  into the scrubber in
many ways,  the most frequent of which are listed below:

     Fine spray nozzles
     Coarse spray nozzles
     Very coarse spray nozzles (>3/4-in. pipe)
     Overflow weir
     Impingement of gas onto liquid pool
     Introduction of gas under surface of liquid pool

     The liquid sprays  can be operated  at  low or high pressure
and introduced  into the airstream countercurrent, cocurrent, or
across the direction of gas flow.

     The  classification  of  scrubbers  is difficult  because so
many designs  are available.   As an example,  a list  is given in
Table 7.
                              78

-------
                     TABLE 7.   SCRUBBER CLASSIFICATIONS
     Basic type
          Specific type
Impingement baffle
Packed tower
Submerged orifice
Venturi
 (Preformed spray)
 (Gas-atomized spray)
Miscellaneous and combination
 scrubbers
Tangential inlet wet cyclone
Spiral baffle wet cyclone
Single plate
Multiple plate

Fixed bed
Moving bed
Flooded bed
Multiple bed

Wide slot
Circular slot
Multiple slot

High pressure
Medium spray
Low pressure
Flooded disc

Crossflow packed
Centrifugal fan
Multiple venturi
Combination venturi
Combination fan
                                     79

-------
     Other designs  are  presently in use or being  marketed that
may  not  have been  mentioned in  this table.   One of  the most
popular  devices  available is  the high  pressure  drop  venturi,
because  of  its  ability  to  control  emissions  of  submicron
particle size distribution.

     When  the  airstream  emerges  from the  scrubber vessel,  it
contains billions of contaminant-laden droplets,  which must be
removed  from  the  airstream before being  emitted  to the atmos-
phere.  For this purpose, entrainment separators (demisters) are
supplied,  which come  in  numerous  designs and  configurations.
Frequently encountered types  are listed below:

     Centrifugal
     Vane axial centrifugal
     Zigzag baffle
     Chevron
     Staggered channel
     Knitted wire mesh
     Geometric woven mesh

     The droplets captured in the entrainment separator coalesce
and  run  off  into  a  liquid  reservoir  (sump).   This liquid is
usually  chemically  or physically  treated for  stabilization;  a
portion  is recycled  back to  the  scrubber,  and  a portion is
removed  (blowdown).   Makeup  liquid is provided  somewhere in the
liquid circuit to compensate  for blowdown.
     The  collected  contaminant  in  the  spent  liquors  must be
concentrated  before  final  disposal   is  performed.  The common
types of waste disposal equipment are listed below:

     Settling tank
     Settling pond
     Clarifier
     Thickener
     Vacuum filtration
     Liquid cyclone
     Continuous centrifugal

     The contaminant-laden liquors  are further  concentrated by
such treatments as  coagulation,  flocculation,  chemical precipi-
tation,  ion  exchange, and desalting.   The degree of  treatment
depends upon the methods of disposal  or recycling and upon state
and Federal regulations.   The relative merits  of the wastewater
disposal  system are  beyond  the scope  of  this  report,  but the
user of  scrubbers must be sure that  these  systems are operated
and maintained in an appropriate fashion.
                              80

-------
5.1  SCRUBBER COMPONENTS AND OPERATIONAL PARAMETERS

     The scrubbing system is composed of exhaust hoods and ducts
handling airborne  contaminant.   Gas pretreatment  equipment may
be  required  for  coarse  contaminant  removal  and for  cooling
before the contaminant enters the scrubber vessel.   The contami-
nant-laden droplets  are removed by  the entrainment separators.
The clean gas is then passed through an induced-draft fan and up
the stack.  Forced-draft  fans  upstream of the scrubber are also
used.    The  associated  components  for  liquor  handling  are the
pumps,  piping,   valves,  motor,  and fans.   The key  parameters
affecting the particulate collection are:

     Velocity/gas flow rate
     Liquid-to-gas ratio
     Particle size distribution
     Pressure drop

5.1.1  Velocity/Gas Flow Rate

     The collection  efficiency  of  most scrubbers depends on the
velocity of the  gas stream through the liquid-contacting section
of  the  scrubber vessel.  The  relative velocity between washing
liquids  (droplets)  and particulates is  critical to contaminant
collection.   In the  case of  high-energy venturi  scrubbers,  a
velocity of  40,000 ft/min can  be  delivered.   Fine droplet size
and high density lead to increased removal efficiency.

     When a high-temperature gas stream enters the scrubber, the
volumetric  flow rate diminishes accordingly  (based on the tem-
perature of the  scrubber liquid) because the gas is being cooled
by  the  scrubber  liquors.   In  poorly  designed  systems,  as the
particulate  laden droplets enter  from the recycled  liquors or
the impaction process  and traverse the vessel, the particulates
may  become  airborne  again  if  sufficient evaporative  cooling
takes place.  Should this occur, pretreatment with clean liquors
(for quenching)  may be required.

     When the system flow rate decreases, the resulting relative
velocity may  not be sufficient to collect the prescribed amount
of  contaminant  and  emissions  wi^l  increase.   Similarly,  a
decrease in  liquid flow  rate  could produce insufficient clean-
ing.

5.1.2  Liquid-to-Gas Ratio

     The  liquid-tp-gas flow rate  (L/G) is a  calculated value,
reflecting  the   liquid  recycling rate  (gal/min) for  every 1000
ft3 of  gas  cleaned.   Typical values range from 2 to 40, and are
a  function  of  inlet gas  temperature,  inlet solids content, and
                                81

-------
method  of water  introduction.   High  L/G ratios  are used  for
high-temperature and high-grain loadings.  Should  the L/G ratio
fall below  design  values,  collection  efficiency will diminish.

5.1.3  Pressure Drop

     The  pressure  drop  across  a scrubber  includes  the  energy
loss  across  the liquid  gas  contacting section and entrainment
separator, with  the former accounting for most of the pressure
loss.  A low pressure drop scrubber ranges from 2  to 10 in. H20;
a medium  from  10 to 30 in. H20; and a high,  30  and above.  The
higher the pressure  drop,  the greater  the collection efficiency
for both particle size and concentration.

5.1.4  Particle Size Distribution

     Performance  of  a  scrubber  depends  on  the  gas  stream
particle  size  distribution.   Efficient collection of submicron
contaminant  challenges  the application  of any type  of control
equipment.   High-energy  venturi  scrubbers  .are  designed  for
submicron contaminant collection.

5.1.5  Scrubber Vessel

     The  ultimate  goal  of  the  scrubber,   regardless  of  its
design,  is  to  provide the greatest number of droplets  to the
contaminant stream in as optimum a fashion as possible.  Regard-
less of the method used to introduce the liquid into the vessel,
the  wet scrubber requires a  uniform and  consistent liquid dis-
tribution  pattern.    One method  to  accomplish this  is  with  a
spray  nozzle.   The  spray nozzle used  in wet scrubbers may be of
the  pressure  type  (hollow   and  solid  cone, impingement,  and
impact);  rotating  (spinning  atomizers);  or  other miscellaneous
configurations.  Spray nozzles  frequently wear or clog, produc-
ing  an uneven  liquid pattern  and requiring replacement.  Carbide
nozzle tips,  which  are abrasion resistant, can be supplied with
standard  stainless  steel nozzles.   Titanium and ceramic nozzles
are  now becoming more prevalent  in  scrubber vessels.  Weir box
distribution,  on  the other  hand,  requires  little maintenance
after  initial  leveling.

     Other  than nozzle  abrasion,  the  presence of dry/wet zones
at the inlet to the vessel or in some  other part produces  build-
up   and   eventually   causes   malfunction.   Liquid distribution
components  (nozzles, weirs) must be provided  at the interface to
avoid  this problem.

     When  the vessel  is  operated under high negative pressure,
the  liquid  within  the associated components  rises an equivalent
height.   Therefore,  all  joints must be sealed to  withstand  this
pressure; gasketing  and  hardware must  also be corrosion
                                82

-------
resistant, especially since the single most prevalent problem in
scrubbers  is  material  failure  due  to  corrosion.   Corrosion
occurs  because most  scrubber applications  are  associated with
acid  gas  streams and, upon contact  with  the scrubbing liquors,
form  corrosive liquids.   The scrubber vessel  is  thus  usually
fabricated with  special alloy  steels  (stainless 304/316,  Hast-
alloy,  Inconel)   or  fiberglass,  or  it  may  contain  liners  of
rubber  or plastic.   Should  high velocities  exist  within the
vessel, as  with  the Venturis,  the abrasion-resistant qualities
of the materials must also be considered.

     Another  frequently  encountered  problem  in   scrubbers  is
scaling.  Scaling results  from  improper  chemical balance in the
system and is usually corrected by the proper chemical treatment
of the washing liquors, most often by pH control.

5.1.6  Entrainment Separators

     Upon  leaving  the  contaminant  washing section,  the  gas
stream  contains  contaminant-laden droplets.   The  droplets are
removed from the gas stream by an "entrainment separator," which
provides  the  droplets  with impingement surface  or imparts cen-
trifugal  forces  that remove  the  droplets from  the gas  stream.
The  common  types available  are  listed  on  page 80.  The  most
important  factor  in  choosing  and  designing  an  entrainment
separator is  droplet  size  removal efficiency.   Other than for
centrifugal separation,  the  droplet velocity is not especially
critical because the droplets usually possess sufficient inertia
and  thus  do  not  change direction  or follow  the  air streamlines
through  the  separator;   instead   they  collide  on  one  of the
numerous  obstructions  (baffles, wires, chevrons) in their path.
The  droplets  coalesce  upon collision  in  the separator and form
sheets  of liquid,  which  drain off into liquid  reservoirs  or
sumps.

     Because   the  droplets   contain  contaminant,  particulate
buildup is likely to occur in the mist eliminator.  This condi-
tion  is  often avoided by using  an intermittent  or continuous
liquid  wash  for  the mesh, channel,  chevron,  or  baffles.   The
wash  system  is  usually  composed  of low-pressure  nozzles  with
cocurrent  and/or  countercurrent  flow,   and  the  system  uses
recycled  liquors  or fresh water  for cleansing.   An increasing
pressure drop across the separator is usually caused by buildup.
Mesh  separators  are  most prone to plugging;  channel, chevrons,
and baffles  are  next;  and the  centrifugal  separators are  least
likely to plug.   Materials of construction of the separator are
usually steel or plastic.   A major factor when considering using
plastic is the possibility of meltdown should the scrubber lose
liquid pumping capability,  thus exposing the mist media to the
high-temperature   gas stream.   Although temperature controllers
upstream  of  the  scrubber can  shut the blower down,  the blower
                               83

-------
slowly diminishes  rotating,  therefore pulling the  unwanted  hot
gases through  the media.   Hence the  use of  plastic media  in
high-temperature  applications   should be  carefully  evaluated.

     The centrifugal  separators allow the droplet-laden  gas  to
enter tangentially,  which  imparts  a centrifugal  force on  the
droplets.  As  the gas spins through the  unit, the  liquid drop-
lets  are forced  outward  toward the  wall.   The performance  of
this  type  of separator is extremely dependent on the flow rate
within  the  unit.  A  decrease  in  flow could  result  in  liquid
droplet carryover to the fan and stack.

5.1.7  Liquor Reservoir (Sump)

     Liquid runoff from the entrainment separator is captured in
the  sump,  which is integrally  mounted  to the scrubber vessel.
It  may  have  a pyramidal shape  or  some  other suitable design.
The  contaminant within the sump settles  and is  pumped away for
additional treatment.   Some  sump designs  incorporate the scrub-
ber  pump liquid pickup from the sump itself.   In this case,  the
piping pickup  points  should be  of  sufficient elevation to avoid
entraining the high solids  content  of  the liquors  in the sump
bottom.  Excessive sludge  buildup  in  the  sump often leads  to
system shutdown and supplementary cleaning.

5.1.8  Pumps

      Scrubber pumps (usually centrifugal) may be operated at low
or  high pressure  and  flow  according to  the  required means of
producing  droplets.   Pump  failure  is  usually attributed  to  a
combination  of abrasion  and corrosion,  and  may be  reduced by
using  appropriate materials  of construction  for  impellers and
housing.   Some pump protection  is  provided  by inlet  strainers;
the  lower  the  suspended solids  concentration and the more chem-
ically  stable  the liquids,  the more  protection  is provided.

      High-rpm  pumps  will  fail more  frequently.    Since  pumps
contain  moving parts,  they  are items of  high maintenance.  The
bearings must  be  lubricated and  inspected  regularly,  and the
pump seals  must  also  be checked  frequently.   Most pumps  are
directly  coupled  to  the motor  shaft.   Belt drives  may  be re-
quired,  however,  to vary pump rotation  (flow).

      Insufficient pump suction can  cause severe problems.  Too
high a  negative  pressure  at the eye of  the  impeller can cause
"boiling"  of   the  liquid,   cavitation,  and   severe   vibration,
leading  to erosion of the  impeller, noise,  and shaking of  the
pipework.  This is especially true with hot or volatile liquids.
Under the conditions  of maximum flow, the system must have a net
positive suction head  (NPSH) greater than  the NPSH  required by
the  pump.   If  insufficient  NPSH is  available  from the  system,
cavitation will occur.
                               84

-------
5.1.9  Piping

     The piping in  scrubber  systems handles high solids concen-
trations and  chemically corrosive  materials.   Erosion and wear
tend to occur  at  sudden changes in pipe cross sections (elbows,
reducers).   The  required elbows and  reducers  should have thick
walls and,  in  the case of elbows,  a  wide  radius.   Materials of
construction  must  provide  corrosion  and  erosion  protection.
High-pressure piping must  also  be  specified where high-pressure
pumps are used.   Blind flanges  allow for ease of pipe cleanout.
Flanged pipe  sections  and unions  also facilitate  maintenance.
The gasketing  material for the  flanges must  be compatible with
the liquors.

5.1.10  Valves

     Valves are also subjected to corrosion and erosion.  Unless
specifically  designed  for throttling,  most  valves  should  be
operated  in a  fully  opened  or closed position.   Valves  that
experience  pressure   drop  should  contain  abrasion-resistant
linings,  especially if  the  liquors  contain  a  high  level  of
suspended  solids.   Should valve  throttling  be necessary,  to
alleviate wear  in the valves  and  compensate  for the change in
pressure in the line,  orifice plates are  installed upstream of
the valve to reduce the pressure rise due to throttling.

5.1.11  Fans

     Scrubber  fans  can  be positioned  either  upstream (forced
draft) or downstream (induced draft) of the vessel.   Centrifugal
fans are typically used, and experience corrosion and mechanical
stress.   When  the  fan is used  in a forced-draft  capacity,  it
handles high  concentrations  of  contaminant and  can experience
abrasion,  caking,  and  buildup.   Most scrubber applications use
the  fan in an induced-draft configuration,  therefore handling
moisture-saturated  air.    Some  buildup  does   occur  in the  fan
wheel;  should  contaminant flake  off,  imbalance and vibration
could occur.  High negative pressure fans,  especially those used
for venturi scrubbers,  exhibit extreme mechanical stress because
of  the  high  fan  tip  speeds.   The  high  mechanical  stresses,
coupled with  corrosive gases, often  result  in stress corrosion
and cracking.   Abrasion and  corrosion  resistant fan wheels and
linings must be used in such an environment.  Fan drains must be
provided to remove captured liquid.

5.1.12  Instrumentation

     The two  types  of  instrumentation necessary  for scrubber
systems are safety and performance monitoring:
                              85

-------
     Safety:

          High temperature interlocks,  which  actuate pumps  for
          auxiliary recycling and for  additional water

          High temperature  controls  to activate  the  scrubber
          bypass  system

          Low liquid level  alarms and control systems  for  aux-
          iliary  pumps

          Automatic fan controls  to activate the bypass  system
          if the  blower fails

          Fan vibration indicator and  alarm shutoff  system

          Fan and  bearing  high  temperature  alarm  and  shutoff

     Performance  monitoring:

          Discharge pressures and flows on  all pumps

          Recycle blowdown and makeup  flow

          Pressure drop across scrubber, cleansing section,  mist
          eliminator,  and entire scrubber

          Inlet  static fan pressure, voltage,  and  amperage

          pH meters/recorder and low level  alarm

          Inlet  and saturated gas temperatures

          Suspended solids monitor

     The safety  interlocks protect  equipment  and  personnel, and
the  performance   monitoring  instrumentation  effects  reliable
operation and forecast malfunctions.

5.1.13  Conclusions

     Because  all  component   surfaces  are   wetted,  in  scrubber
applications corrosion can become a substantial  problem.  There-
fore, corrosion-resistant materials must be used  in the piping,
pumps, and blowers; indeed,  most of the scrubber system must use
these materials.    In the  scrubber vessel,  where high velocities
are  present,  erosion  may occur,  requiring  the  use of  proper
materials  of  construction.    Properly  irrigated  entrainment
separators  are   also  necessary,  and  will   effectively  minimize
contaminant  buildup.    Adequate  monitoring  instrumentation is
crucial  to  equipment   operation and  performance.    If  not in
place, it should be procured and installed.
                               86

-------
5.2  SCRUBBER OPERATION AND MAINTENANCE

     Regardless  of  the  reason  for  scrubber  shutdown,  a  well-
defined inspection program  should  be followed before commencing
startup.   Preoperation  and  inspection  guidelines  are  given
below,  followed  by procedures  for  routine  startup,  inspection
and maintenance  during  operation,  and routine shutdown.  Guide-
lines  for  maintenance during shutdown  and  for detecting common
malfunctions are also described.

5.2.1  Pre-Startup Inspection

     Whether  the scrubber  has  recently been installed or  has
undergone  internal   service  and   maintenance,   before  it  is
"buttoned up" it must be thoroughly inspected.  A checklist for
preoperation  and  inspection is  provided  in  Figure  8.   This
checklist  is to be  used  as a guideline  only,  and  should  be
tailored for each specific system.   The inspection survey during
shutdown should  include  internal and external observations from
the  ducts  up through the  stack.    If  possible,  as part of  the
pre-startup  inspection  before the  unit is  put into service,  it
is advisable  to  operate pumps  and other components  to observe
their performance.

5.2.2  Routine Startup

     After  the  scrubber has  been thoroughly  inspected,  the
following general startup procedure should be followed:

     1.   Close all drain valves.

     2.   Fill vessels to normal level.

     3.   Activate circuit  breakers  for  all  controls  and com-
          ponents .

     4.   Open pump suction valves.

     5.   Start pumps.

     6.   Open discharge valves  slowly.

     7.   Open isolation dampers.

     8.   Start  fan   (if  fan has  an  inlet  control  damper,  it
          should normally  be closed until  fan  reaches speed).

     9.   Record data from monitoring instrumentation.

    10.   Note changes in monitoring data as  gases pass through
          system.
                               87

-------
                 SCRUBBER PHEOPERATION AND INSPECTION CHECKLIST
     APPLICATION:

     DATE/TIME:
     REPORT BY:    	            YES    NO       ATTN.
     DUCTS

          WARPAGE                                 O     D        D
          CORROSION                               a     D        a
          ABRASION                                D     C3        CJ
          GASKETING                               D     D        O
          SLIP JOINT                              DP        C3
          BUILDUP                                 an        D
          COMMENTS

     GAS PRETREATMEOT? EQUIPMENT

          NOZZLES                                 a     a        a
          BUILDUP                                 a     D        a
          GASKETTNG                               d     O        D
          CORROSION                               CD     Q        D
          VALVE OPERATION                          CD     D        D
          SUMP SLUDGE                             tD     D        D
          COMMENTS

     SCRUBBER

          NOZZLES                                 an        cu
          - CLOGGING                              an        a
          - WEARING                               D     d        d
          - ABRASION                              a     a        D
          ABRASION                                a     a        a
          BUILDUP                                 an        a
          CORROSION                               a     a        a
          PIPING                                  an        a
          - SCALING                               C3     C3        O
          - RUSTING                               an        a
          - FITTINGS                              an        a
          - LEAKAGE                               a     D        C3
          SUMP SLUDGE                             a     O        CD
          COMMENTS
                                Page  I of 2
Figure 8.   Preoperation and  inspection checklist  for  scrubbers.


                                    88

-------
CHECKED


MIST ELIMINATOR
NOZZLES
- CLOGGING
- WEARING
- ABRASION
PIPING
- RUSTING
- PITTING '
- LEAKAGE
VALVE OPERATION
CORROSION
CCfWENTS
MIST ELIMINATOR MEDIA
BUILDUP
CLEANED
REPLACED
COMMENTS
LIQUOR TREATMENT
pH CONTROL
- CALIBRATION CHECK
- PROBE BUILDUP
CAUSTIC HOLD TANK
SLUDGE BUILDUP
VALVE OPERATION
PIPING LEAKAGE
CCfMENTS


YES

0
a
a
a
a
a
D
a
D
ID


n
a
a


n
n
a
a
a
a
a

Page 2 of 2

NO

n
a
n
a
Q
n
a
a
CD
a


tn
a
tu


D
n
n
n
a
D
a



REQ.
A3TN

D
a
a
a
a
a
a
a
n
a


a
a
a


n
a
o
n
a
n
a


Figure 8 (continued)




                                      89

-------
5.2.3  Routine Inspection and Maintenance During Operation

     During normal operation, the preoperation checklist (Figure
8) can  be  used with  the instrumentation measurements  noted  in
5.1.12.  A  checklist  for inspecting an  operational  scrubber  is
given in Figure 9.  A tailormade operational checklist should be
prepared for each specific type of equipment.

5.2.4  Routine Shutdown

     A  general  procedure for  scheduled  shutdown  is  outlined
below:

     1.   Stop blower.

     2.   Isolate scrubber vessel by closing dampers.

     3.   Shut down makeup water.

     4.   Allow system to cool.

     5.   Continue  to blow  down  at normal  rate until  liquid
          levels  reach  pump inlet,  and  then  shut  pumps  off.

     6.   Stop all other pumps.

     7.   Deactivate all circuit breakers.

     8.   Open access  door  and  use necessary safety procedures
          for inspection.

5.2.5   Common Malfunctions

     Areas  on which to focus attention are:

     Buildup in wet/dry  zones

     Clogged nozzles

     Abrasion  in  areas  of  high  velocity,  throats,   orifices,
     elbows, etc.

     Corrosion in ducts, piping, scrubber  vessel

     Entrainment  separator buildup

     Fan vibration

     Pump wear
                                90

-------
                   SCRUBBER OPERATING INSPECTION AND MAINTENANCE CHECKLISTS
           APPLICATION:

           DATE/TIME:
                        	            CHECKED            RBQ_

           BEPORT BY:    	              YES     NO          ATTN.
              PKt-TKEATMENT EQUIPMENT

                PIPING LEAKAGE                        CD      CD          CD
                VALVE OPERATION                       CD      CD          CD
                LEVEL CONTROL                         CD      CD          CD
                PUMP/LUB.                             CD      CD          CD
                COMMENTS
           SCRUBBER
                PIPING LEAKAGE                        CD      CD          CD
                VALVE OPERATION                       CD      CD          CD
                LEVEL CONTROL                         CD      CD          r~l
                PUMP/LUB.                             CD      CD          CD
                COMMENTS
          MIST ELIMINATOR
                PIPING LEAKAGE                        CD      CD         CD
                VALVE OPERATION                       d      CD         CD
                PUMP/LUB.                             CD      CD         CD
                COMMENTS

          LIQUOR TREATMENT

                PIPING LEAKAGE                        CD      CD      'CD
                VALVE OPERATION                       CD      D         CD
                LEVEL CONTROL                         tD      CD         CD
                PUMP/LUB.                             a      a         a
                COMMENTS

                                                    OPERATING   DESIGN

          COLLECTOR MEASUREMENTS

                TEMP. IN                             	     	   d
                TEMP. OUT                            	     	   CD
                FLOWRATE                             	     	   ED
                STATIC PRESSURE IN                    	     	   CD
                STATIC PRESSURE OUT                   	     	   CD
                PRETREATMENT PUMP PRESSURE            	     	   CD
                SCRUBBER PUMP PRESSURE                	     	   [D
                MIST ELIMINATOR PUMP PRESSURE         	     	   O
                pH PUMP PRESSURE                      	     	   C3
                BLOWER CURRENT                       	     	    Q
                BLOWER VOLTAGE                       	     	    CD
                STACK APPEARANCE                      	     	    pj
                COMMENTS
Figure  9.   Operating  inspection and maintenance checklist  for  scrubbers.

                                            91

-------
     Most  scrubber  malfunctions  do  not  in fact  occur  in  the
scrubber vessel,  but in  the interconnecting ductwork,  dampers,
fans,  centrifugal  pumps,  valves,  and piping.  Alarms  are often
used to  signal malfunction  of  scrubber pressure drop,  pump and
blower  failure,  and  liquid levels.   Changes in process  condi-
tions usually affect  scrubber performance.

5.2.6  Spare Parts

     Scrubber  manufacturers supply  a list  of  recommended spare
parts.    Spare parts for  auxiliary  equipment,  such  as  pumps,
fans,  piping,  dampers,  valves,  and  instrumentation,   are  also
required.   Table  8  shows  the  spare  parts inventory that  is
recommended.

               TABLE 8.  REPLACEMENT PARTS FOR SCRUBBERS
                 Motor (fan, pump, seals, bearings, impeller)

                 Mist eliminator media (full set)

                 Gauges (temperature, pressure)

                 pH probe and required reagent

                 Piping


5.2.7  Troubleshooting  Program and Procedures

     The  multiphase program to diagnose and troubleshoot  opera-
tion  problems  is  provided in Appendix A.   The troubleshooting
chart present in Table  9 gives guidelines for cause and  remedies
of problems  in scrubbers.  Although there is some discussion of
pumps in  this chart,  it is by no  means exhaustive.  Fans are  not
mentioned because  of  the  extensive  scope  of troubleshooting
guides from  manufacturers.  The probable cause  of fan noise,  low
or  high  flow rates,  and static  pressure  are  too  numerous  to
itemize.
                                92

-------
              TABLE  9.   TYPICAL  TROUBLESHOOTING  CHART  FOR SCRUBBERS
 Symptom
      Cause
Remedy
 Low pressure drop
  (scrubber  section)
 High  pressure  drop
  (scrubber  section)
 Low  pressure  drop
  (mist  eliminator)
High  pressure drop
  (mist eliminator)
High temperature
 in stack
Pump leaks
Pump pressure
 increase

Pump flow rate/
 pressure
 diminished
Pump noise/heat



Corrosion


Erosion



(continued)
 Low  airflow  rate
 Low  liquid flow rate
 Eroded  cleaning section
 Meters  plugged

 High airflow rate
 Plugging  in  ducts
 or  scrubber

 Low  airflow  rate
 Low  liquid flow rate
 Media dislocated

 High airflow rate
 High liquid  flow rate
 Clogging
 Flooding

 Insufficient wash
 liquor
 Liquid  temperature too
 hot

 Packing or seals
 Nozzle plugging
 Valves closed

 Impeller wear
 Nozzle abraded
 Speed too low
 Defective packing
 Obstruction  in piping
Misalignment
Bearing damage
Cavitation

Inadequate
 neutralization

Incompatible materials
High recycled solids
 content
Check blower
Check pump/nozzles
Inspect
Clean lines

Check blower
Inspect
Check blower
Check pump/nozzles
Inspect

Check blower
Check pump/nozzles
Inspect/clean
Inspect/drain

Check pump/nozzle

Check sump tempera-
 ture

Replace
Reduce nozzles
Open valves

Replace
Replace
Check motor
Replace
Check pipes, strainer,
 and impeller

Check
Replace
Check

Check pH control
Replace materials
Wastewater system
                                      93

-------
TABLE 9   (continued)
Symptom
     Cause
Remedy
Scaling


Pipe plugging
Improper chemical
 treatment

High solids content
Abrupt expansion/con-
 traction/bends
Change treatment
Cleaning
Change pipe fittings
                                      94

-------
                            SECTION 6

 TECHNICAL ASPECTS OF THE DESIGN, OPERATIONS, AND MAINTENANCE OF
       ITEMS COMMON TO ALL AIR POLLUTION CONTROL EQUIPMENT


6.1  INTRODUCTION

     Regardless of the  nature of the process that generates the
airborne contaminant and the method used to clean and filter the
gas  stream  before it is emitted  to  the atmosphere,  the contam-
inant  must  be  captured  and  transported  efficiently to  the
control  equipment.   The hoods,  enclosures,  and interconnecting
ducts used to exhaust contaminant are common to all types of air
pollution control  equipment.   Therefore,  exhaust  system design
is critical to effective control equipment performance.


6.2  EXHAUST DUCTS

     Problems often encountered  with exhaust systems are insuf-
ficient  contaminant  capture velocity,  abrupt  duct transitions,
long horizontal  runs,  and incompatible materials  of construc-
tion.  Access  doors  for cleanout  and inspection  are  often not
provided.   Door  fastening  hardware  and  gasketing  should  be
corrosion  resistant  and  compatible  with  other  materials  of
construction.  Thermal insulation is also necessary if condensa-
tion is expected to occur,  otherwise corrosion may result.

     The presence of duct elbows or shape transitions could lead
to  abrasion.   Duct  redesign  coupled  with baffle  plates  to
achieve  a  more uniform flow  distribution could  alleviate  the
problem  along  with   the  installation  of  appropriate  abrasive
resistant linings.  Flanged ducts are also recommended to facil-
itate duct cleaning and replacement.

     Dampers  are  sometimes  necessary  upstream of  the control
equipment.    In this  condition,  the damper is exposed  to  the
contaminant stream.   Buildup  in  the damper mechanism is likely,
and would  adversely  affect its  operation.   Abrasion and corro-
sion are frequently  observed.   Turbulent  flow with  its skewed
velocity profile created by the  damper can seriously affect the
performance  of downstream  blowers  and control equipment.   If
dampers are necessary,  flow straighteners  may be required prior
to allowing the gas stream to enter any sort of operating equip-
ment.
                               95

-------
     Control equipment ductwork is  usually  operated  under nega-
tive pressure.   As  a consequence,  any  extraneous  air  infiltra-
tion through cracks,  seams,  joints,  or welds can produce buildup
and corrosion due to  acid/gas  condensation.   Proper  location of
pressure taps and temperature  probes  with a suitable method for
avoiding buildup  and clogging is  critical  for these  measure-
ments.   The preferred arrangement of these two probes is the use
of  strip chart  recorders.   Regular maintenance of the  taps and
probes  is necessary.


6.3  GAS PRETREATMENT

     Cyclones may be  provided  to  remove the large particulates,
thus  reducing  contaminant  loading  to  the  respective  control
equipment.   The cyclone produces  a  pressure drop in the system,
which  (according  to  the designed collection  efficiency)  may be
substantial.  Materials of  construction must  be compatible with
the gas stream.

     Temperature reductions  of the contaminant  stream  entering
the control  equipment can be  accomplished  by evaporative cool-
ing.   Among the  configurations  available are  tangential inlet
nozzle sprays,  in-line  high pressure  countercurrent sprays, and
sonic  nozzle  water  atomization.   Regardless of  the configura-
tion,   extreme  caution  must   be  exercised  in  maintaining the
designated  liquid flow  (and gas  temperature)  to avoid the aq,id/
gas dewpoint.   The  existence  of  dry/wet zones  within treatment
equipment can produce buildup  and flow choking.
6.4  INLET BAFFLES

     Baffles  are often  installed at  the  inlet  to  the control
equipment  to  achieve  a more  uniform  flow  distribution.   On
occasion,  the baffles behave as  impaction surfaces  and accumu-
late material or exhibit abrasion.  If the baffle is not adjust-
able  and  these  problems   occur,  the  baffle  may  have  to  be
removed.
6.5  HOPPERS

     In  either a baghouse or  ESP,  the collected contaminant is
dislodged  from the bags or collector  plates  and falls into the
hopper.  The hoppers are emptied according to the amount collec-
ted.   Some type of automatic  or  semiautomatic  method is advis-
able.   The design of  the  hopper  slope and contaminant handling
system  is  based on the physical  and chemical properties of the
dust.   Dust bridging,  agglomeration,  and mudding  can occur in
the  hopper.   Methods  for  alleviating  these problems are hopper
                               96

-------
vibrators,  heaters,  fluidizing air, rappers, poke holes, housing
insulation, and  access doors.  Materials  of  construction are a
prime  consideration,  not  only  to  avoid  corrosion but  also to
ensure structural integrity.  Workers frequently rap the hoppers
with  hammers  and pipes  to assist the  flow  of  collected dust.

     Hoppers  are  usually  operated under  negative  pressure and
need appropriate valving at the bottom apex to allow hopper dust
to be removed without admitting air to reentrain dust.  A rotary
airlock valve suits  this  purpose;  it consists of a paddle wheel
that  rotates  at a  given rpm and  can discharge materials  to a
screw  conveyor  or  storage  container.   New installations should
have  air  locks  with wiper  blades  for  each vane to ensure air-
tight  sealing and cleaning.   Packing glands and bearings should
be set away from the housing to avoid contact with high tempera-
tures .

     For low  solids flow  and  nonautomatic installations, slide
gates  may  be  used.   These gates are used only when the compart-
ment  is  offline.   Air leakage into  the  hoppers and  the asso-
ciated problems of  condensation are prevalent with this method,
which  is thus not recommended for new installations.

     Although  costly,   the  new,   larger   capacity  hoppers  are
specified  with  air  conveying  materials  handling systems.  These
are  used when the  contaminant is  easily handled and  has a high
solids  content.   One  of  the  major  problems  experienced with
these  systems  is  moisture condensation  and  icing in  the air
lines.  Heat  tracing,   insulation,  and moisture separation can
alleviate  these problems.

     When  inspecting  the  hopper,  the presence   of  excessive
buildup or bridging may  be attributed to a malfunctioning level
indicator,   nonexistent   or  inoperative   hopper  heaters,  and
vibrators.
6.6  FANS

     The  fan,  along  with the  ducts,  hoods,  and  air pollution
control  equipment,  make  up  the pollution  control  system.   The
fan  generates  the  suction  in the  system  that draws  the  air
contaminants from the  process  and passes them to the air pollu-
tion control equipment.

     The ducts before and after the fan can almost be considered
part of  the fan itself.   These ducts establish smooth airflow
into and out  of  the  fan so  the  fan can  do the  maximum work
moving air.   Poor  design of these ducts  can lead to turbulence
and  uneven  flow  pattern  at  the fan inlets  and  outlet,  and the
fan capacity will be lower than expected.
                               97

-------
     Air density  is  critical to flow performance.   The  primary
factors affecting density are air temperature and plant altitude
above sea level.  In either case, the volume capacity of the fan
varies with the air density.   If the air temperature or altitude
increases,   the air  becomes  less  dense.   For  example,  a  fan
moving 20,000 ft3/min of less dense air is moving less mass than
a fan moving the same quantity of "standard air."  Consequently,
the fan does not have to develop as much static pressure when it
is moving less  dense  air.   The  horsepower requirements are also
lower, because less air mass is  being moved.

     Fan  ratings  are  developed under  ideal  laboratory  condi-
tions, and  typically  do  not  perform as well as the manufacturer
predicts.   Therefore,  fan  curves should be heavily relied upon;
pitot or S-type velocity probes should be used.  Fan blades are
designed to be most  efficient  when air  enters  in  a  straight
line.  Elbows  and  fan inlet boxes  that  impart  a  spin  to air
entering the  fan  in the direction of  fan rotation decrease the
amount of  air  moved,  because the fan blades  have  to "catch up"
to the air  before  acting on it.  If the air spin is opposite to
the fan rotation,  the output will also be reduced.

     Ideally, the fan outlet should be a straight duct length of
5 to  10  duct  diameters  with no elbows  or other interferences.
Air  discharged from  a fan outlet does  not normally have  a uni-
form  velocity  distribution  because  the mass  of  air discharged
experiences  a  centrifugal  force from  the spinning  fan  wheel,
resulting in  higher velocities  at the  outer  edge  of the outlet
than at  the inner  edge.   Several duct diameters downstream from
the fan outlet ensure the air velocity returning to near uniform
distribution across the duct.

     The centrifugal  fan (of the radial  blade type) is  used in
systems handling contaminants that are likely to clog and result
in fan buildup.  The flat radial blades tend to be  self cleaning
and  are  built  with  thick blades to withstand erosion and impact
damage from airborne solids.  When the material being handled is
explosive  or  flammable,  the fan  should  be  manufactured  of  a
nonsparking component and material.

     The motors  that drive  the  fans can  be direct drive  (motor
shaft  directly coupled  to  fan  shaft)  or  belt driven.   Direct
drive  fans  are more compact   and  assure  constant  fan  speed
because  they  eliminate belt  slippage.   Slippage may occur when
belt-driven fan drives  are not  maintained.  Fan speeds are thus
limited  to  available  motor speeds  when the direct  drive  config-
uration  is  used.    Belt-drive  fans  are more  flexible  when in-
creases  (or decreases) in fan speed  are required.

     The fan  may  be  the only moving part in the  air pollution
control  system; therefore,  it requires a  great deal  of scrutiny
                               98

-------
during  operation  and maintenance.   If a problem  is  suspected,
duct  pressure  and  velocity  readings  should  be  obtained  and
compared  to  design  specifications.   Visual  inspection  of  the
ducts  may  reveal  closed  dampers   or open  inspection  parts.
Problems  such  as  loose  fan  belts,  dirty  fan  blades,  plugged
ducts,  and  overheating  fan shaft  bearings  are frequently  en-
countered in air pollution control equipment systems.

     According  to  the  application,  space  requirements,  and
costs,  the  fan  may be  located either upstream (forced draft) or
downstream  (induced  draft) of  the  control  equipment.   Forced-
draft fans  push air  through the system; induced-draft fans draw
air through the control equipment.  Forced-draft fans experience
corrosion and abrasion because they are  exposed  to  heavy dust
concentrations.   When   the  contaminant accumulates  on  the  fan
blades  and  a portion then  breaks off, vibration  and imbalance
occur.   These  fans  are  usually  present in  older systems  (10
years and greater) where the air pollution control equipment was
added to  the system and  the  fan remained  the  same  or  was  up-
graded.    This  configuration  is  noticeably  present  in  utility
boiler ESP applications.  Induced-draft fans are operated on the
clean side  of  the pollution control equipment where  they  are
subject  to  less   contaminant.   This  configuration   is  usually
present in scrubbers and baghouses.


6.7  EXHAUST STACKS

     An exhaust stack  on a pollution control  system  serves  two
purposes:   it helps  to disperse  the gas stream by  discharging
the exhausted air above roof level,  and it improves fan perform-
ance because  the  uneven velocity  distribution at the fan outlet
causes a high velocity pressure at the outlet.

     All systems should have at least a short, straight stack on
the  fan.    A  high  stack  discharge  velocity  (3000  ft/min  or
higher)   helps  to  disperse contaminants,  because  the  air  jet
action  can   increase  the  effective  stack  height except under
severe wind conditions.

     If rain  entering  the  stack  is a problem,  a  vertical dis-
charge  sleeve  that induces ambient airflow and does not block
the stack opening is effective in keeping rain out of the stack.
The old-style weather cap deflects exhausted air downward and is
no  longer  recommended.  Fan  discharges should not be  directed
horizontally to keep rain  out because contaminant dispersion is
hindered.   When the fan is operating, rain entering the stack is
not a problem.
                               99

-------
6.8  CONCLUSIONS

     The simplest way to diagnose a system problem is to inspect
and  to take  pressure  and  velocity  measurements at  strategic
locations.  The  visual  inspection  will reveal  closed  dampers,
open inspection ports,  damaged  hood and ducts,  and malfunction-
ing  components  related  to  the control  equipment.   Loose  fan
belts,  dirty filters,  plugged ducts,  or dirty fan blades may be
present.  Static pressure measurements  at  hoods,  elbows, and on
both sides  of  the control equipment will  show  the contribution
of each to the overall pressure  drop in the system and should be
compared  with  previous  data.   The  primary  problems  usually
encountered in  systems is insufficient  airflow and excessively
high contaminant levels.
                               100

-------
                             SECTION 7

           INSPECTION,  SAFETY, AND MAINTENANCE EQUIPMENT


     Various  tools and  equipment are required for the efficient
performance  of  inspection and  maintenance.  Table  10 lists the
items that are basic to an inspection.

            TABLE 10.  BASIC INSPECTION AND SAFETY EQUIPMENT	

     Hard hat                        Safety shoes

     Safety glasses or goggles         Dust and gas respirators
      (nonfogging, no vents)           (disposable)

     Suitable gloves                  Tape measure (50 ft)

     Flashlight                      Paper pad, pen (inspection checklist)
     Ear protection                  Camera

     Body protection  (disposable garments, chemical/fire-resistant clothing)


     Table 11  lists the testing equipment  that should be readily
available,  and  Table  12  lists  the hand  tools that are needed.

     For  more  extensive  maintenance,   air-operated power  tools
are  recommended, especially  when maintenance  is  to be performed
within  the  pollution  control  equipment  housing  or  vessel.
Air-operated  tools are  lighter  in weight  and more convenient to
use.   Electrical  tools  can  spark  and possibly  cause  fires or
explosions when working  inside  dusty environments.    Table 13
lists  the power tools that are  recommended, and  Table  14  lists
items  that  are  required  to support   the maintenance  efforts.

     A  relatively new  way  to  identify  leaking  or  poorly  in-
stalled bags   is  to inject  a quantity  of fluorescent or highly
reflective powder into  the  baghouse,  and then  inspect  with
either black light or a high-intensity  lamp.   This technique can
reveal very small  leaks although the need  to span large areas is
time consuming.   Use  of the powder is also effective in spotting
broken welds or other leaks at joints and  seams.
                                101

-------
      TABLE 11.   BASIC TESTING EQUIPMENT
Dial  thermometer (50° to 1000°F,  12-in.  stem)
LJ-tube manometer (flexible)
Stopwatch
pH (litmis) paper
Pi tot tube (S-type for contaminant streams,  600 ft/min
  and greater)
Velometer (25 ft/min and greater)
Plastic sample bottles (wide mouth)
Grab sampling detector tubes (Draeger type)
Photo tachometer
Amprobe (a.c. clamp on volt-ohm-ammeter)
Multimeter.

         TABLE 12.  MAINTENANCE TOOLS
          Open-end wrenches
          Socket wrenches
          Adjustable wrenches
          Pipe wrenches
          Locking pliers
          Pliers (side cutters, slip joint)
          Screwdrivers
          Hex keys
          Hammers
          Hacksaw
          Knife and shears
          Scissors
          Calipers
          Carpenter's  rule
          Scraper
          Wire brushes
          Toolbag and  canvas bucket.
                      102

-------
                 TABLE 13.   POWER TOOLS
Air screwdriver
Power scissor shears
Impact wrench
Air nut wrench
Air-driven hacksaw
Hydraulic cutters
Pneumatic chisel
Heavy-duty drain cleaner
Blowgun
Air-operated vacuum cleaner (hand held and 55-gal  drum type)
Portable air compressor with in-line pressure regulator;  filter and
  moisture trap.
           TABLE 14.   GENERAL EQUIPMENT
          Ladders (wood or fiberglass)
          Electric extension cords
          Safety (fluorescent) drop lights
          Tool  pouches
          Penetrating lubricant
          Fire  extinguisher
          First aid kit
          Protective hand creams
          Wood  platform truck
                           103

-------
     In scrubber applications,  high-pressure,  hot-water cleaning
equipment may  be used  periodically  to rejuvenate vessel  walls
and housing.   Rapping equipment may  also  be  required  to  elim-
inate pipe scale and buildup.

     Stack monitoring instrumentation often  utilized  for  con-
tinuous and  reliable  pollution equipment  operation  are opacity
meters and/or  broken  bag detectors.   This  type  of instrumenta-
tion is usually found in large, high-capacity  systems.
                               104

-------
                            SECTION 8

                             SUMMARY


     When  management is  prevailed  upon  to purchase,  install,
operate, and  maintain air pollution  control  equipment,  resist-
ance often arises.   Regardless  of the aesthetic values derived,
management considers the equipment to be a large capital expend-
iture and,  after installation,  to be  a significant contributor
to  plant  overhead.    These  factors  are  often coupled  with in-
ferior quality hardware that  leads ultimately to poor equipment
performance,   resulting  in conflicts between  government,  indus-
try, and equipment manufacturers.

     Management's best  approach  to  reconciling this  apparent
dilemma is to analyze critically  the possibility of a return on
the  investment  in   the   equipment.   Although  the  ROI  is  not
obvious  at  the   outset,  management  should  explore direct  or
indirect ways within its  operation to effect savings.  A return
on  investment is  also calculable  for operation and maintenance,
by  preventing equipment breakdown and loss of production with a
well-planned  and  controlled preventive  maintenance  program.  In
this regard,  nearly  all maintenance  activities are human activ-
ities,  and  for the  most  part,  controlled by  those individuals
executing  the work.  Even  the  most explicit  inspection check-
lists,  charts,  guidelines,  methods,  and  training  will  not
achieve the  desired goal  unless  plant management,  engineering,
and  labor  have  the  commitment and  willingness  to  include  an
effective operation and maintenance program.

     With the understanding that air pollution control equipment
is  an  integral  part of  the process  equipment, discussion  of
operation  and maintenance procedures becomes  more  palatable  to
those responsible for its  performance.
                              105

-------
                          BIBLIOGRAPHY
Maintenance Management

Corder, A. S.  Maintenance Management Techniques.   McGraw-Hill
     Co. (United Kingdom), 1976.

Cotz, V. J.  Plant Engineering Manual and Guide.   Prentice-Hall
     Inc., Englewood Cliffs,  New Jersey,  1973.

Grothus, H.  Total Preventive Maintenance of Plant Equipment,
     Executive Enterprises Publications Co., Inc., 1976.


Baghouses

Billings, C. E., and J. Wilder.  Handbook of Fabric Filter
     Technology.  CGA Corp.  PB 200 648,  NTIS,  Springfield,
     Virginia, 1970.

Gushing, K. M., and W. B. Smith.  Procedures Manual for Fabric
     Filter Evaluation.  EPA-600/7-78-113, June 1978.

Reigel, S. S., R. P. Bundy, and C. D. Doyle.  Baghouses:  What
     to Know Before You Buy.  Pollution Engineering, May 1973.

Rullman, D. H.  The User and Fabric Filtration Equipment.
     Journal of the Air Pollution Control Association, 26(1),
     January 1976.

Vandenhoeck, P.  Cooling Hot Gases Before Baghouse Filtration.
     Chemical Engineering, May 1, 1972.

Walling, J. C.  Ins and Outs of Gas Filter Bags.  Chemical
     Engineering, October 19, 1970.


Electrostatic Precipitators

Air  Pollution Control Association.  TC-1  Particulate  Committee.
     Electrostatic Precipitator Maintenance  Survey.   Journal of
     the Air Pollution Control Association,  25(11), November
     1976.
                               106

-------
Air Pollution Control Association.  TC-1 Participate Committee.
     Information Required for Selection and Application of
     Electrostatic Precipitators for the Collection of Dry
     Particulate Material.  Journal of the Air Pollution Control
     Association, 26(4), April 1975.

Bump, R. L.  Electrostatic Precipitators in Industry.  Chemical
     Engineering, January 17, 1977.

Katz, J.  Maintenance Program and Procedures to Optimize Elec-
     trostatic Precipitators.  IEEE Transactions on Industry
     Applications, I-A-11(5), November 1975.

Oglesby, S., and G. B. Nichols.  A Manual of Electrostatic
     Precipitators Technology.  Southern Research Institute.
     PB-196380, NTIS, Sprinfield, Virginia, 1970.

Operational Monitoring and Maintenance of Industrial Electro-
     static Precipitators for Optimum Performance.  IEEE Con-
     ference Record (No. 76 - CH 1122-11A).  IAS Annual Meeting,
     Chicago, October 11-14, 1976.

Operation and Maintenance of Electrostatic Precipitators.
     Proceedings of Specialty Conference, APCA/East Central
     Section, April 1978.

Schneider, G. S., T. I. Horzella, J. Copper, and P. J. Striegl.
     Selecting and Specifying Electrostatic Precipitators.
     Chemical Engineering, May 26, 1975.


Scrubbers

Calvert, S., et al.  Scrubber Handbook.  APT Inc.  PB-213016,
     NTIS, Springfield, Virginia, 1972.


General

Cross,  F. L., and H. E. Hesketh,  eds.  Handbook for the Opera-
     tion and Maintenance of Air Pollution Control Equipment.
     Technomic, Westport, Connecticut, 1975.

PEDCo Environmental, Inc.  Industrial Guide for Air Pollution
     Control Handbook.  EPA 625/6-73-004, Technology Transfer,
     June 1978.

Richards, J. R.  Plant Inspection and Evaluation Workshop Ref-
     erence Material.   Appendix 1-1, 1-2, 1-3.  PEDCo Environ-
     mental, Inc.  USEPA, Div. of Stationary Source Enforcement,
     Washington,  D.C., November 1978.
                               107

-------
Richards, J. R.  Reference Material for Technical Workshop on
     Plant Inspection and Evaluation.   Vols.  1-2.  PEDCo Envir-
     onmental, Inc.  USEPA, Div.  of Stationary Source Enforce-
     ment, Washington, D.C., November 1978.

Szabo, M. F., and R. W. Gerstle.   Operation and Maintenance of
     Particulate Control Devices  on Coal-Fired Utility Boilers.
     EPA 600/2-77-120, July 1977.

Szabo, M. F., and R. W. Gerstle.   Operation and Maintenance of
     Particulate Control Devices  on Selected Steel and Ferro-
     alloy Processes.  EPA 600/2-78-037, March 1978.

U.S. Environmental Protection Agency.   Seminar on Operation and
     Maintenance of Air Pollution Equipment for Particulate
     Control.  Sponsored by USEPA, Cincinnati, and Pollution
     Engineering Magazine, Harrington, Illinois, 1979.
                               108

-------
                           APPENDIX A

                     TROUBLESHOOTING PROGRAM
INTRODUCTION

     Frequent  equipment malfunction,  breakdown,  and excessive
emissions indicate improper equipment performance.  A multiphase
program must be  implemented to diagnose system problems (hoods,
ducts, control equipment, and fan).  As a guideline, the follow-
ing program should be followed:

Phase 1.  Problem Identification

     This phase  should  incorporate a detailed inspection of the
system during operation and shutdown and culminate with a report
listing  all  observations   (positive  and  negative),  providing
interpretations  of  these observations  (why  things were the way
they  were);  and recommending methods  and  items  to improve per-
formance.   Pressure  and  velocity  measurements  may  also  be
needed.

Phase 2.  Implementation

     The  recommendations  provided  in  Phase  1 should be imple-
mented  after  thorough  cost and technical analysis  and discus-
sion.  These  recommendations may be in  the  form of engineering
design and  modification,  component  and  accessory part replace-
ment, or fabrication of new equipment.   Following this aspect of
the  program,  repair and replacement of  the  procured and fabri-
cated components  must be executed.  Finally,  the entire system
must be started up and debugged.

Phase 3.   Sampling and Testing

     A test must now be performed to evaluate  the work.   This
may  be  stack  sampling  or,  more often,  a  pressure and velocity
measurement program coupled with close observation of the opera-
tion of the system.

     Case histories using the multiphase program for a pulse-jet
baghouse,  dry and wet precipitator, venturi scrubber, and packed
tower are presented in this appendix.   It should be emphasized
                               109

-------
that  the  most effective  approach  to troubleshooting  and  diag-
nosing problems  is  familiarity  with the  process and detailed
knowledge of the  contents  of the various troubleshooting guides
provided herein and by the equipment manufacturer.
                                110

-------
                          CASE HISTORY

                       PULSE-JET BAGHOUSE
INTRODUCTION

     Excessive emissions from two pulse-jet baghouses on fly ash
storage silos  were  frequently observed.   Internal  observations
of the  units  indicated bridging of the dust  between bags.   The
conclusion  drawn  by  the  user was  that the  filter  medium  was
incorrectly specified and that the majority of the particle size
distribution was submicrometer.  Rebagging  with different types
of media  was  tried several  times,  to no  avail.   The baghouses
under  consideration  were  an internal part of  an  experimental
sludge fixation process  (see Figure  A-l),  and their malfunction
thus  had  serious economic implications for  the utility.   The
operators  of  the  fixation  process  contracted  an  independent
pollution control equipment  services  and maintenance company to
troubleshoot the problem.

Phase 1.  Problem Identification
General Comments--
     Design,  construction,  and  installation  of  the  two  units
     appeared to be more than satisfactory.

     A conscientious housekeeping and maintenance program on the
     units was obvious.
Observations--
     The following  observations  were made both  while  the units
were operating and while they were shut down.

     Airflow, static pressure, temperature,  and dimensional data
     were recorded (Tables A-l,  A-2,  and A-3).

     The baghouses  were cleaning air that is  discharged from a
     pneumatic  conveying system,  which  is  delivering  fly  ash
     from electrostatic precipitator hoppers.

     Both  systems  operate   identically   and  exhibit  identical
     symptoms.

     The baghouses  operate  for  up  to  50  days  with new bags
     before plugging.

                               ill

-------
             GASES TO
            ATMOSPHERE
                ESP
STEAM


 COAL
            AIR HEATER
            ECONOMIZER
SUPERHEATER
  FIREBOX
WATER
AIR
                                    BAGHOUSE
                                                  SILO
BAGHOUSE
                       SLUDGE  FIXATION
                                                  SILO
                                                    SLUDGE
                                                    FIXATION
                                                    SLUDGE
                                                    FIXATION
           Figure A-l.   Application  of  pulse-jet  baghouse.
                                 112

-------
       TABLE A-l.   SYSTEM PARAMETERS:   EAST UNIT (FAN NOT OPERATING)'
Ambient air temperature



Ambient air humidity



Barometer



Inlet air temperature:   dry



Inlet air temperature:   wet



Outlet air temperature:  dry



Inlet air pressure



Outlet air pressure



Bag AP



Outlet air velocity



Outlet dia./area



Outlet air flow
42°F



Approximately 95% (raining)



29.91 in.  Hg



62°F



48° F



62°F



3.4 in.  H20 (silo pressure)



1.1 in.  H20



2.3 in.  H20



3200 ft/min



16 in./I.4 ft2



4480 ftVmin
  Pressure relief vent on this silo is leaking.
                                     113

-------
        TABLE A-2.   SYSTEM PARAMETERS:   WEST UNIT (FAN  NOT  OPERATING)
Ambient air temperature



Ambient air humidity



Barometer



Inlet air temperature:   dry



Inlet air temperature:   wet



Outlet air temperature:  dry



Inlet air pressure



Outlet air pressure



Bag AP



Outlet air velocity



Outlet dia./area



Outlet airflow
42°F



Approximately 95% (raining)



29.91 in.  Hg



62°F



49°F



62°F



5.2 in.  H20 (silo pressure)



3.7 in.  H20



1.5 in.  H20



2700 ft/min



18  in./I.77 ft2



4780 ftVmin
                                     114

-------
                        TABLE A-3.   DIMENSIONAL DATA
Header pressure static
Header pressure firing
Header diameter
Header length
Silo diameter
Free space in silo
Particle size distribution
Contaminant
Diaphragm valve
Solenoid valve
Blow tube diameter
Port diameter
Bags (glazed polyester)
100 lb/in2
90 to 95 (adjusted timer to obtain)
3-in.  pipe
8 to 10 ft.
26 ft
8 to 10 ft minimum
Not applicable
Fly ash from ESP hopper
2009 - 3
30
3/4 in.
5/16 in. (no measured)
4Jrin. diameter, 99 in. long
                                     115

-------
One discharge  fan  has  been removed,  and the other  was  not
operated.  The operator had found that the  conveyor  blowers
alone provide adequate airflow  to  transport  the fly ash to
the baghouse,  thus enabling  the discharge  blowers to  be
shut down.

The bag dimensions and media were correct for this applica-
tion.    The  bags fitted  properly.   The inside  surfaces  of
the bags are  very clean,  indicating excellent  filtering
operation and performance.

The bags  were well  sealed into  the tube sheet;  no evidence
of leaking was observed.

Airflow was adequate and within specifications.

No  moisture/dewpoint  problems   were   evident   on  the  bag
surface  although  the  operator  indicated previous  moisture
problems  on the housing walls.

Air  supply  to  the  pulse-jet cleaning system is  adequate.
The timer design and operation are excellent.

Bag wear  is  not a problem at this time; previous bag leaks
were  attributed  to punctures  made  while  knocking  caked
contaminant off the bags during manual cleaning.

Review  of a particle size  data report suggested  that col-
lection  and  sizing methods  used were not proper  for air-
borne  fly ash  and probably  indicate a size  distribution
much larger than actually present.

The  pulse-jet  bag cleaning  system  is  not  generating an
adequate  shock wave in the bag when it fires.

The bags  were not releasing contaminant during  the cleaning
pulse.   The  contaminant  agglomerated  in large  lumps on the
dirty  side  of the bag media  (approximately  3/16 inch thick
at time  of visit).

The  buildup  on  the bags  was dry and  exhibited  no caking
characteristics.   It  released well when the bag was tapped
with  a  finger,  leaving  a  2-inch-diameter  area  of clean
media.

A  spare  diaphragm  valve  and a spare  solenoid valve were
disassembled  and  inspected.   The size and porting  of these
valves  appeared to be inadequate  to  obtain a proper shock
pulse  in the  cleaning air  jets.
                          116

-------
     The  timer was adjusted to provide  a shorter  "on"  time  than
     previously operated,  thus  resulting  in a plenum  pressure
     drop of 5 to  10  lb/in.2


Interpretations—
     The  following conclusions were made:

     The   baghouses  were  properly sized for this  application.

     The  bag media were appropriate.

     The   air  supply  to the cleaning valve  system  was  adequate.

     The   bags  were not  releasing contaminant because  a  suffi-
     cient shock  wave  was not being  generated by  the  cleaning
     pulse.

     A shock wave  was  not  being generated  because the  valve
     system  was  not  opening fast  enough.   The  peak-induced
     pressure  was  sufficient; however,  a  quick  rise   time  was
     needed to generate the necessary shock wave.

     The   valve system was  slow  operating because  the  internal
     porting in the valve  system  configuration created too much
     restriction and thus  prevented the right angle valves from
     "dumping" fast enough.

     To  create the  required shock  wave  during   the  cleaning
     pulse,   a rise  time  of  approximately  5 milliseconds  was
     required from valve opening to maximum pressure measured in
     the  blowtube.
Recommendations—
     The following corrective actions were recommended.

     Replace 3-inch-diameter header with 6-inch.

     Replace  the  diaphragm  valves  with properly  sized,  faster
     acting units.

     Replace the solenoid  (pilot)  valves with units providing a
     large release port.

     Mount the  solenoid valves directly on  the diaphragm valve
     release ports.

     Rework  porting on new  valves  if  necessary  to obtain  a
     pressure rise time of approximately 5 milliseconds.
                               117

-------
     Insulate housings to minimize  condensation  on inside walls
     during cold weather operation.   (During  the inspection,  no
     moisture problem  was  observed.   If  the  process  air drops
     below 44°F—the present  dewpoint—condensation  will occur,
     and thus heaters are required.)

Phase 2.   Implementation

     The following recommendations were implemented:

     A 6-inch header was installed.

     Diaphragm and solenoid valves were replaced.

     Insulation and strip heaters were installed.

Phase 3.   Sampling and Testing

     Visual observation of the units indicated no opacity.

     No velocity measurements were made on the system.

     Followup discussions with the operator indicated continuous
     and reliable performance.
                                118

-------
                          CASE HISTORY

                 DRY ELECTROSTATIC PRECIPITATOR
INTRODUCTION

     A  fertilizer  company  owned  a weighted  wire  electrostatic
precipitator  (see  Figure A-2) that  frequently exhibited exces-
sive  sparking and reduced  operating voltage.   When  operating,
the system was  in  compliance for  mass particle emission but not
for opacity;  intermittent "puffing"  from the stack was noticed.
Several vendors recommended replacement of the existing unit for
an  approximate  installed cost of  $500,000.   Before the fertil-
izer  manufacturer  appropriated this  large  capital expenditure,
the  previously  described  multiphase program  was  instituted.

Phase 1.  Problem Identification


Observations/Interpretations—

     The  pretreatment  simple  cyclone  was  not  significantly
     reducing  particulate  loading  to  fan  and  precipitator.
      Indication  of this  was apparent from  previously obtained
     particle  size  sampling  data,  which  revealed  particles
     approximately 50  percent by  weight larger than  10 micro-
     meters .

     The product elevator duct bleeds ambient air to the exhaust
     fan.  Aside from  the  duct handling  particulate  emissions
     from  the conveyor  system, the ambient  air with  entrained
     moisture may promote sporadic condensation with subsequent
     contaminant buildup in the fan and precipitator.

     Previous  information  and  onsite  observations  indicated
     correlation of  stream  moisture  and  opacity.   A major por-
     tion  of the  moisture  entered  the  stream  through cooling
     water injection nozzles.  The excess moisture was believed
     to affect particle resistivity.

     Frequent temperature changes  in process were  thought to be
     reaching dewpoint in the precipitator.

     Nine  of  the  17  rappers  (vibrators)  were   inoperative,
     malfunctioning,   or missing.   The  complete  rapper  system
     contained many inoperable components.
                               119

-------
FEED
                                     CYCLONE
                         CYCLONE
CALCINER
                     WATER
                    INJECTION	*
                                                                 1
                                                                 ESP
                                                                     TO ASH
                                                                     STORAGE
                                                      CYCLONE
                                     AFTERCOOLER
                                                  -»-  PRODUCT
        Figure A-2.  Application of dry electrostatic precipitator.
                                    120

-------
     Rappers were not sequenced or timed properly.
     One high-voltage insulator was cracked.
     The wire frame stabilizer insulator was  loose.
     Gasketing on  three  bus duct  hatches  was missing,  as  were
     some of the bolts.
     Insulator  compartment  ventilation  system  contained  air
     leaks and dirty  filters;  the  blower was incapable of over-
     coming positive pressure in the precipitator housing.
     No  temperature monitor  was  present  at the  inlet  of  the
     precipitator.

Recommendations—
     A sampling  and  testing program was devised to characterize
the cyclones and precipitator  inlet and outlet streams.   Param-
eters measured included  grain  loading,  particle size,  moisture,
temperature, opacity, and pertinent process variables.
     Observe  stack  opacity while manually  controlling  water
     injection.
     Renovate,  repair, and replace old rappers.
     Replace broken insulator.
     Secure stabilizer insulators.
     Install new gaskets  and  insulator compartment blower  and
     filter.
     Install thermocouple probe upstream of precipitator.
Phase 2.  Implementation
     Replacement parts and components were requisitioned.
     Onsite supervision of repairs was arranged.
     Components were repaired or replaced.
     Individual   precipitator   components  were   operated   and
     tested.
Phase 3.  Sampling and Testing
     A  definite   correlation  between moisture  and opacity  was
observed.   An  automatically  controlled water  cooling  system
                               121

-------
coupled to  the  inlet precipitator temperature monitor was  sub-
sequently installed.

     Air load testing  was performed to obtain a  reference  data
     base.

     Inlet and outlet of the precipitator were sampled to deter-
     mine  if the  equipment  could  adequately  control  process
     emissions.

     Results of  testing indicated a reduction in average grain
loading from  0.152  gr/dscf to  0.010 gr/dscf.  The  cost of the
overall program was $20,000, thereby saving the company $480,000
in  the purchase  of new equipment.   A preventive  maintenance
program was subsequently executed as the final phase.
                                122

-------
                          CASE HISTORY

                 WET ELECTROSTATIC PRECIPITATOR
INTRODUCTION

     A wet  electrostatic precipitator  was installed  to  remove
suspended participate  from  the vent  gases of a  phosphate  rock
dryer (see Figure A-3).   The  electrostatically collected mater-
ial was washed  from the plates by water  from  spray nozzles.   A
collecting hopper received the  effluent,  which was carried to a
liquor treatment system through a drain system.

     The  operator   of  the system  experienced frequent  opacity
violations  and  attributed  the problem  to insufficient  system
voltage.    Dry/wet   zones produced  contaminant  buildup,  which
would occasionally  dislodge and either  clog drains or short out
wires  and collector  electrodes.  The  operator  of the  system
asked that an independent survey be made.

Phase 1.   Problem Identification
Observations--

     Duct buildup in dry/wet zone

     Inlet ducts not sloped enough with evidence of pretreatment
     tangential spray liquid backing upstream into system

     Buildup  on dry/wet  zones  in upper  WEP  support  structure
     adjacent to nozzles

     Dry/wet areas on collector electrodes

     Spray nozzle clogging

     Pipe and housing scale

     Sump  drains  partially  clogged  with dislodged  contaminant

     Large amounts of buildup in outlet duct transition
                               123

-------
FEED
AMMONIA
t
DCArTflR


WASH
LIQUORS -
FLUORIDES
AMMONIA ~*t 	 1
AMMONIA
\
•^ AMMAN T ATf

— »••
)R






t
WEP

—
SCRUBBER
/•

SPENT
h n •• LIQUORS
t
M. 5CRUBRER

\

DRYER


f
FUEL
                    Figure A-3.  Application of wet electrostatic precipitator.

-------
Recommendations—

     Wide  angle,  high-capacity  cocurrent  nozzles  should  be
     installed to  prevent  buildup,  cleanse  ducts  properly,  and
     avoid liquid runoff upstream.

     Spray nozzle  pattern  did not  coincide  with manufacturer's
     specifications; new,  wide-angle,  solid cone  nozzles  were
     specified.

     Pump  strainers  containing openings  slightly  smaller  than
     the nozzle orifice should be installed.

     pH probe  should be  relocated  to provide a more representa-
     tive sample of the liquor.

     Outlet duct transition cleaning is required.

Phase 2.  Implementation

     All  nozzles  and  strainers  were procured and  installed.

     pH  probe  was  relocated  adjacent  to  recirculating  pump
     suction side.

     Outlet duct transition was cleaned.

Phase 3.  Sampling and Testing

     Opacity was substantially improved.

     Pump  pressures and flows  remained  constant  for  3  months.
                                125 ,

-------
                          CASE HISTORY

                        VENTURI SCRUBBER
INTRODUCTION

     A fiberglass manufacturer owned a venturi scrubber that was
installed to  control  the emissions  from  the forming  line  (see
Figure A-4).  Submicrometer emissions  produced  an opacity of 40
percent and  greater.   The system was  in compliance  for  grain-
loading.  Recommendations to  improve  system  performance  varied
from  ionizing the water droplets to replacing the  system  with
wet electrostatic precipitators.   Before a major capital invest-
ment  program was  embarked  upon,  the multiphase  program  was
executed.

Phase 1.  Problem Identification
Observations—

     Upstream   cooling   water  nozzles,   which  were   mounted
     tangentially  in  the  ducts,  produced a  dry/wet zone  with
     large amounts of contaminant buildup.

     Venturi spray nozzles were abraded.

     Venturi pump impellers were abrading.

     High solids content present in recirculating liquors.

     Velocity through  mesh mist eliminator media was too high.


Recommendations—

     Redesign nozzle arrangement to minimize buildup.

     Install carbide tip nozzles for venturi spray.

     Electroplate  abrasive resistant  lining  on pump impeller.

     Perform more frequent sump blowdown and fresh water makeup;
     install efficient pump strainers.
                                126

-------
                             GASES TO
                            ATMOSPHERE
            BAGHOUSE
               I
        SCRUBBER
INCINERATOR
FEED
             FURNACE
                   FUEL
                       _J
         FORMING
 CURING
PRODUCT
      FUEL
BINDER
             Figure A-4.  Application of venturi  scrubber.
                                 127

-------
     Closed  sections  of  mist eliminator  should  be opened  to
     decrease air velocity, and  freshwater wash used instead of
     contaminant-laden water wash.
Phase 2.   Implementation
     Install countercurrent nozzles.
     Replace  stainless  steel  nozzle  tips  with carbide  tips.
     Install impellers with abrasion-resistant plating.
     Provide  freshwater  makeup  for  sump and mist  eliminator
     spray nozzles.
     Open appropriate mist eliminator- sections.
Phase 3.   Sampling and Testing
     Opacity observations indicated 20 percent or less.
     More  conscientious  preventive maintenance  alleviated dust
     buildup and abrasion within operating components.
                                128

-------
                          CASE HISTORY

                      PACKED TOWER SCRUBBER
INTRODUCTION

     Odor complaints from local residents and in-plant employees
were  being received  by  a  company that was refining  precious
metals  (see Figure  A-5).   A countercurrent  packed tower  was
being utilized to absorb the acid vapors emitted within numerous
laboratory  hoods.   Occasionally, a plume was noticed  that  was
attributed  to  the contaminant  gas  being condensed.  The  main-
tenance department  checked  the  functioning  components,  and  all
seemed  operational.   It  was  then  decided  to  recruit  outside
assistance to troubleshoot the program.

Phase 1.  Problem Identification
Observations—

     Plant under high negative pressure.

     Hood velocity below  Occupational  Safety and Health Admini-
     stration standard of 100 ft/min.

     No evacuation slot at hood benchtop.

     Hood  exhaust ducts  were  not  located  properly to  effect
     proper ventilation.

     Packed  tower nozzle  orifices were partially  clogged with
     plastic chips from the packing.

     Pump impeller shaft broken.

     Blower belt slippage.


Recommendations—

     Increase makeup air to plant.

     Extend  hood baffle  plate  to  benchtop  and provide  slot.
                                129

-------
                     GASES TO
                    ATMOSPHERE
                        i
       WASH
      LIQUOR
PACKED
TOWER
    SPENT
"*"" LIQUOR
                                   HOOD
           GASES
            GASES
Figure A-5.   Application of packed  tower scrubber.
                        130

-------
     Provide in-line strainers upstream of pump.
     Replace impeller shaft.
     Tighten pulley belts.
Phase 2.   Implementation
     Canvas makeup duct installed in two plant locations.
     Fiberglass baffle plate extended to benchtop.
     Strainer  with  holes  slightly  smaller than nozzle orifice
     installed.
     Impeller shaft replaced.
     New blower pulley belts installed.
Phase 3.   Sampling and Testing
     Hood face velocity measured at 100 ft/min.
     Exhaust duct flowrate increased 30 percent.
     No apparent odor at stack.
                                131

-------
TECHNICAL REPORT DATA
(Please read Instructions on the reverse before i ompleliUKl
1 REPORT NO 2
EPA-905/2-79-002
4 TITLE AND SUBTITLE
Management and Technical Procedures for
Operation and Maintenance of Air Pollution
Control Equipment
7. AUTHOR(S)
Dr. David B. Rimberg
North America PEMCO, Inc.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
PEDCo Environmental, Inc.
11499 Chester Road
Cincinnati, Ohio 45246
12 SPONSORING AGENCY NAME AND ADDRESS
U.S. EPA Region V
Air Programs Branch
230 S. Dearborn
Chicago, Illinois 60604
3 RECIPIENT'S ACCESSION NO
5 REPORT DATE
June 1979
6 PERFORMING ORGANIZATION CODE
8 PERFORMING ORGANIZATION REPORT NO
PN 3280-G
10 PROGRAM ELEMENT NO. 1
11 CONTRACT/GRANT NO
68-02-2535, Task No. 7
13. TYPE OF REPORT AND PERIOD COVERED
14. SPONSORING AGENCY CODE
15. SUPPLEMENTARY NOTES
Project Officers: Dr. Indur Goklany and Mr. Henry Onsgard
16 ABSTRACT
This manual supplies agencies and industrial users with management and technical
Guidelines for effective operation and maintenance of air pollution control
 equipment.  The  manual  covers four major topics.  Section 1 discusses organization
 of maintenance operation,  maintenance job planning and scheduling, maintenance
 work measurement,  preventive maintenance, maintenance material control, budgets,
 and training.  Sections 2  through 4 discuss the three major types of air pollution
 control  equipment:   baghouses, electrostatic precipitators, and scrubbers.
 Emphasis is placed on simplified startup, operating, and shutdown procedures.
 Routine  inspection procedures are supplemented with detailed checklists.  A
 general  program  is presented for troubleshooting air pollution control equipment.
 Case  histories for a pulse-jet baghouse, dry and wet electrostatic precipitators,
 venturi  scrubber,  and packed tower are included in the appendix to provide the
 user  with a sample program for improving equipment performance reliability.
 Section  5 discusses equipment and components common to all types of air pollution
 control  equipment, such as hoods, ducts, fans, and stacks.  Section 6  provides
 the details of  the tools and equipment required to perform inspection  and
 maintenance satisfactorily.
                               KEY WORDS AND DOCUMENT ANALYSIS
                 DESCRIPTORS
                                             b.IDENTIFIERS/OPEN ENDED TERMS
                                                                          COSATI Field/Group
  Air Pollution

  Dust
  Filters
  Scrubbers
  Electrostatic Precipitators
Air Pollution Control
Stationary Sources
Particulate
 13B

 11G
 13K
 07A
 131
18. DISTRIBUTION STATEMENT

  Unlimited
16. SECURITY CLASS (This Report)
      None
21. NO. OF PAGES
  140
                                             20. SECURITY CLASS (This page)
                                                    None
                          22. PRICE
EPA Form 2220-1 (»-73)
                                          132

-------