United States
            Environmental Protection
            Agency
vEPA
            Great Lakes National
            Program Office
            536 South Clark Street
            Chicago, Illinois 60605
EPA-905/2-85-001 -A
September 1985
In-System Storage
Controls For Reduction
Of Combined Sewer
Overflow - Saginaw, Michigan

Executive Summary
                     Do not WEED. This document
                         retained in the EPA
                        5 Library CoB.ect.on.

-------
                                                               EPA-905/2-85-001-A
                                                                 September 1985
                            IN-SYSTEM STORAGE
                         CONTROLS FOR REDUCTION
                       Of COMBINED SEWER  OVERFLOW
                            SAGINAW, MICHIGAN
                      William C. Pisano,  P.E.
                        Daniel J. Connick
                        Gerald L. Aronson
               ENVIRONMENTAL  DESIGN &  PLANNING,  INC.
                        369 Winter Street
                   Hanover, Massachusetts  02339
                           Grant  No. S005359


                                  for
                    DEPARTMENT OF PUBLIC  UTILITIES
                           CITY OF SAGINAW
                          SAGINAW, MICHIGAN
Ralph G. Christensen                         Richard  Traver
Project Officer                              Technical  Assistance
                   U.S. Environmental Protection Agency
                   Region 5, Library (PL-12J)
                   77 West Jackson Boulevard, 12th floor
                   Chicago, II  60604-3590
                   GREAT LAKES NATIONAL  PROGRAM  OFFICE
                 U.S. ENVIRONMENTAL  PROTECTION AGENCY
                        536 South Clark  Street
                       Chicago,  Illinois  60605

-------
                           Disclaimer

     This  report  has been reviewed by the Great Lakes   National
Program Office, U.S. Environmental Protection Agency and  approved
for  publication.  Approval  does not signify that  the   contents
necessarily reflect the views and policy of the USEPA,  nor   does
mention   of  trade  names  or  commercial  products   constitute
endorsement or recommendation for use.
                            ij*$l 4H^
                                                 -ft

-------
                            FOREWORD

          This   report  overviews  the  results  of  a  recently
completed five-year combined sewer overflow (CSO) control program
in Saginaw,  Michigan (10,000 acres,  pop. 85,000) funded by City
of  Saginaw/U.S.   EPA  108  Great  Lakes  National  Program  and
conducted by the engineering contractor. Environmental Design and
Planning,  Inc.,  Hanover, Mass.  The implemented control program
entailed  modification  of 13 combined sewer regulation  chambers
together with construction of one new in-line control chamber  to
maximize   transient  system  storage  of  wet  weather  combined
sewerage for later bleedback to a well-operated Wastewater Treat-
ment Plant (WWTP) having phosphorous removal and ample  treatment
capacity.   These  improvements,  "the  reduced  Best  Management
Practices   (BMP)  plan",  represent a partial completion of  the
first  of  two  phases of the  City's  CSO  Facility  Plan.   The
objective  of  Phase  I was to maximize WWTP  processing  of  wet
weather  combined  sewage generated using  inexpensive  transient
system  storage  (less  than  $l/cu.ft.) so as  to  minimize  the
extent,  scale  and  cost of satellite CSO  treatment  facilities
(Phase II).  The swirl concentrator technology was recommended to
treat  residual overflows remaining after Phase  I  improvements.
Six  major facilities were recommended and adopted as part of the
CSO Facility Plan.

          The  total  cost of the implemented  program  including
engineering  was  $.504  million  (1984).   A  post  construction
evaluation  measurement/modeling  program was conducted   in  the
Fall,  1984 to verify preproject design conditions.   It has been
determined  that  implementation  of the  reduced  BMP  plan  has
increased  the  percentage  of  total  annual  wet  weather  flow
directed  to the WWTP by 14.6%  (from a previous  "as is" level  of
37.7%)  and  has  incrementally reduced (beyond  "as  is"  levels)
suspended solids loadings to the Saginaw River by 16%, BOD by 20%
and  total  phosphorous by 8.5%  (secondary  treatment).   During
periods  of advanced wastewater treatment  (AWT)(pickling  liquor
addition) at the WWTP,  total phosphorous removals have increased
to 12.6% above pre-implementation levels.   Implementation of the
remaining  elements of the complete BMP plan (Phase I) will  pro-
duce  an  overall incremental wet weather flow   increase  of  30%
(increasing  the  total wet weather flow treated at the  WWTP  to
67.7%).

          This project was funded by U.S.  EPA in part, to demon-
strate  new innovative full scale approaches for  mitigating  CSO
impacts  on the Great Lakes.   The primary project  justification
was to develop and document an innovative,  inexpensive and cost-
effective   management   approach  for  mitigating  wet   weather
phosphorous loadings to Saginaw Bay (Lake Huron). The results are
currently  being used as part of U.S.  EPA's joint  efforts  with
Canada  to develop phosphorous limitation management  strategies.
                                111

-------
In  addition,  the  results  of this demonstration  project  will
provide valuable insights for a number of projects in the  forma-
tive preliminary phase investigating in-system storage management
to  "clip" or eliminate CSO from small intensity,  high frequency
events as an inexpensive and cost effective control measure.

           This  report was submitted in partial  fulfillment  of
Grant No.  S005359 by Environmental Design & Planning, Inc. spon-
sored  by  a  Section  108 grant from the  Great  Lakes  National
Program Office,  Region V, U.S. EPA with funds also from the City
of Saginaw.   This report covers a period of September,  1979  to
December, 1984 and work was completed as of April, 1985.
                                 IV

-------
                        TABLE OF CONTENTS
Foreward 	iii


Chapter 1:     Description of City of Saginaw Sewerage
                           Conveyance and Treatment Facilities

      1.1      Introduction	  1
      1.2      Sewerage System Overview.....	  1
      1.3      WWTP Details	  5


Chapter 2:  Combined Sewer Overflow Control (1960-1978)

      2.1      Prior CSO Facility Plan	 7
      2.2      Hancock Street Storage/Treatment Facility	 7


Chapter 3:  Combined Sewer Overflow Control (1979-1985)

      3.1      Rationale for Replacement of
                 CSO Facility Plan	 11
      3.2      Overview:  108 Demonstration Grant	 11
      3.3      Phase 1: 108 Demonstration Project	 12
      3.3.1    New CSO Facility Plan - Phase 1	 14
      3.4      Description of Three Efforts to Develop
                 the Demonstration Project - Phase 1	 18
      3.5      Phase 2: 108 Demonstration Project	 22
      3.6      Phase 3: 108 Demonstration Project	 27


Appendix A: 108 Demonstration Project Conclusions	 29


Appendix B: 108 Demonstration Project Recommendations	 33
References.
35

-------
                    LIST OF FIGURES AND TABLE
Figure

   1   Location of Saginaw,  Michigan	   2
   2   Saginaw Combined Sewer Service Area	   3
   3   General Plan of Interceptor Sewer System	   4
   4   Location of CSO Storage/Treatment Basins	   8
   5   Hancock Street Storage/Treatment Facility
          Implementation	  10
   6   Effectiveness of Overall Preliminary Plans	  13
   7   Proposed EDP CSP Plan	  15
   8   Layout of Weiss Street Combined Sewer
          Overflow Treatment Complex	  19
   9   Weiss Street Overflow Water Storage
          Facility	•	  21
  10   Webber Street Swirl Facility	  23
  11   Details of Reduced BMP Plan	  25
  12   Salt and Vermont Streets Chamber	  26


Table

  1    Comparison of Recommended Plan and
          Alternative Plan	  16
                                VI

-------
                        ACKNOWLEDG EMENTS
         The  authors  would like to commend the  EDP  staff  who
worked  so  hard  to make this program  a  success.  Through  the
diligent   efforts of many,  a study has been prepared  assessing
the  viability  of  a  relatively new technology  for  solving  a
complex combined sewer management problem in the City of Saginaw.

         We  would  like  to thank the  City  of  Saginaw  Public
Utilities Department for their extreme cooperation and good will,
including  Robert Dust,  Executive Director of Public  Utilities,
Mr.  Jim  Anderson,  Superintendent and Fred  Schulze,  Assistant
Superintendent, Wastewater Treatment Division.

         We  would like to also thank Mr.  Ralph G.  Christensen,
U.S.  EPA Region V,  Great Lakes National Program Office, for his
support and assistance.   The Great Lakes Program provided  funds
for this project.   In addition, Mr. Richard P. Traver, U.S. EPA,
Edison,  New  Jersey  was extremely helpful in  coordinating  the
early phases of the project.

         Finally.   we   would  like  to  express  our  sincerest
appreciation to Ms. Eunice Harris for her patience in typing this
report.

         Environmental   Design   &  Planning,   Inc.   was   the
engineering contractor for his project.   Dr.  William C. Pisano,
P.E., President, EDP, was the principal investigator.  Mr. Daniel
J.  Connick,  Sr.  Design Engineer, was the project manager.  Mr.
Gerald  L.  Aronson,  Executive Vice President,  EDP,  supervised
field monitoring and evaluation efforts.
                               Vll

-------
                            CHAPTER 1

             DESCRIPTION OF CITY OF SAGINAW SEWERAGE
               CONVEYANCE AND TREATMENT FACILITIES


Section 1.1 Introduction

          Saginaw  is  located  in the eastern  part  of  central
Michigan,  north  of Detroit,  as shown in Figure 1.  The Saginaw
River  is  a short section of a major drainage  area  leading  to
Saginaw  Bay,  Lake Huron.   The topography of the area is  flat.
The  Saginaw  River about evenly divides the 10,437 acre area  of
the City of Saginaw.   The Saginaw River drainage basin above the
City has an area of 6,200 sg. mi.

          The area which is surrounded by the Great Lakes,  has a
quasi-marine environment.  Saginaw1s normal annual  precipitation
is  about  28.6  in.,  over 50% of which falls during the  summer
between March and September. Beginning in March or April, melting
snow combined with rainfall can produce high overflow volumes  to
the  river.   Most  of the storms that occur are of  low  average
intensity.   Over 90% of the time, the average intensity of rain-
fall which produces runoff is less than 0.10 in./h.

          The  City  of Saginaw is serviced by a  combined  sewer
system.   Combined  sewer overflows (CSO) during rain events  are
contributors  of pollutants to the Saginaw River.  Overflows  may
occur  at 34 regulator chambers.  Five pump stations are designed
to relieve the system during flooding conditions.  See Figure  2.
It is estimated that over 60 overflows occur per year.

          Impacts on the Saginaw River from CSO include dissolved
oxygen  depletion  in the downstream segments of  the  river  and
floatable   material  may  create  visual   problems.    Nutrient
emissions,   particularly  dissolved  phosphorous,  are  critical
concerns to Saginaw Bay and Lake Huron.


Section 1.2 Sewerage System Overview

         The intercepting sewer shown in Figure 3 runs along both
banks of the Saginaw River. The West Side Interceptor crosses the
river  at Weiss Street to join the East Side  Interceptor,  which
continues to the WWTP at the northeast limits of the City.

         Because  a  number of the sewers are below  flood  river
stage,  the  problem of collecting sewage may involve  stormwater
pumping  during periods of high river level.   During flood river
levels,  storm  flows will discharge over the  regulator  chamber
weirs  into  the intercepting system.   Backwater gates   prevent

-------
•ILIAUKEC
   CM ICICt
  ILLINOIS
i         i
1  INDUNM

\
                          OH I 0
 Figure 1   Location of Saginaw, Michigan.

-------
OJ
                                                                                                              LEGEND.


                                                                                                                9  EXISTING pyMPiNr. STATION



                                                                                                                A  CHAMBER


                                                                                                                    EXISTING INTERCEPTOR
            EXISTING COMBINED SEWER
             *NQ OVERFLOW TYPICAL)
                                                                                                              — .—  CITY LIMITS
                                                                                                                     LIMITS Of SERV'CP *»CA
                                                                                                                     OUTSIDE ft* i
                                                                  HANCOCK ST PUMPING
                                                                       STATION
                                                                                       see
                                                                                  INTERCEPTOR
V»EB8E" 51
     STATION
WEISS si.PUMPING
    STATION
                                                      EMERSON si PUMPING
                                                           STATION
                                                                    EA'.T SIDE
                                                                  INTERCEPTOR
                                                                                         EXISTING
                                                                                        W*STE
                                                                                    PUMPING STATION
                             Figure  2    Soginow combined ttwtr tarviee oreo.

-------
                                                             SCALE (fh«MM4ieffort)


                                                           0123
Swoga pumping stati
andtrwtfmntplont
EAST SIDE INTERCEPTOR
                                                              Enwrwn St
                                                              pumping station
                                                      WEST SIDE INTERCEPTOR
                           nnVSS 9t<
                           pumping station
   Figure  3  General plan of interceptor sewer system.

-------
discharge of flood river water into the sewerage  system.   Flood
pumping stations are located at Webber,  Emerson,  and Fourteenth
Streets  on the East Side,  and Hancock and Weiss Streets on  the
West Side.

         The  interceptor  system   serves the  dual  purpose  of
collecting sewage and carrying storm flows and consists of tunnel
sewers  ranging from 42 to 78  inches in diameter.   The  tunnels
are approximately 40 feet below ground level.


Section 1.3 Wastewater Treatment Plant (WWTP) Details

          The  City's 32.7 rogd secondary  WWTP is located on  the
east bank of the Saginaw  River. Wastewater enters the plant in a
72-inch interceptor sewer.  After screening and grit removal, the
wastewater  is  settled  in  four  primary  sedimentation  tanks.
Primary  effluent  passes into the conventional activated  sludge
system where ferrous sulfate or waste pickle liquor can be added,
for  phosphorus removal as necessary to meet  effluent  discharge
standards.  Final effluent is chlorinated before discharge to the
Saginaw River.   The current NPDES permit for the  plant requires
that  monthly average BOD and suspended solids concentrations not
exceed 25 and  30 mg/1,  respectively. Effluent total phosphorous
concentrations must be less than 1 mg/1.

          Prior  to  1968  sewage discharging from  the  City  of
Saginaw  was  given  primary  treatment  with  chlorination.  The
primary plant was then upgraded to secondary treatment  including
biological  activated sludge with phosphorous removal.   Although
the  modified plant is designed for a nominal flow of 50 cfs  and
an  estimated maximum flow of 128 cfs,  the  secondary  treatment
unit operations are sized for about 160 cfs discharge.  All storm
flows  entering  the WWTP in excess of 108 cfs are split  at  the
grit chamber with bypass receiving only chlorination.  Currently,
bypass  beyond  108  cfs  occurs at a spillover  weir  such  that
increasing influent flow rates results in simultaneous  increased
flow  through  the plant and increased bypass.  The  average  dry
weather flow is  about 32 cfs.

          All   flow  beyond  the  grit  chambers  receives  full
treatment.  There are four secondary aeration tanks following the
primary  clarifiers.   Normally two aeration basins are used  for
dry  weather flow and wet weather discharges up to about 84  cfs.
The  two other aeration basins are used as storage  (0.5  million
cubic  feet)  for wet weather discharges above 84 cfs.   If these
basins are filled, flow-  through conditions result.  The storage
contents  after  an event (or when  influent  rate  significantly
decreases)  of these two tanks containing primary treated  wastes
then  receive  full primary/secondary treatment as these  volumes
are pumped back to the headworks.  Any flows beyond 84 cfs and in

-------
excess  of  the  two aeration tank storage  volume  will  receive
primary treatment,  limited aeration with phosphorous removal (if
necessary), secondary clarification and disinfection.

          Average    suspended    solids   and    BOD    influent
concentrations  are reduced by 93% and 89%  respectively.   Total
phosphorous  effluent  concentrations  do  not  exceed  1   mg/1.
Analysis  of  long-term plant efficiency records indicate  little
deviation from average removals during wet periods.

-------
                            CHAPTER 2

           COMBINED SEWER OVERFLOW CONTROL  (1960-1978)


Section 2.1  Prior CSO Facility £lan

          Abatement of CSO pollution was  required to comply  with
order  issued  by State  of Michigan  Water  Resources   Commission
 (1960) .   Several   studies  focusing  on the CSO  problems  were
completed (1) to meet the requirements of the order.    A   control
plan was accepted in 1969.  The basic concept consisted of utili-
zing   to its maximum the existing system  together with  seven   new
storage  and treatment facilities at locations determined  by   the
hydraulics of the system.  See Figure 4.  The  intent was  to make
the  best use of existing facilities,  and  to preserve  the  flood
protection  function  of  the existing  interecepting   and  flood
pumping system.  The storage and treatment  concept was  considered
to be  the state-of-the-art CSO technology at that time.

          The   CSO  control plan entailed  the  following  design
parameters:   a) every overflow would be disinfected;  b) the pro-
posed  facilities would provide the equivalent of primary  treat-
ment for events up to design storm (1 year) conditions;  c) after
storms  the  stored  sewage and settled solids  would   slowly  be
bledback  to  the  WWTP for final treatment;  and d)  the  entire
system  would  revert  to its normal  flood  protection function
during river flood stage.

          The   plan  focused on utilizing  in-line  and  off-line
storage.   Approximately  18  million gallons (mg)  of  in-system
storage was determined to be available for  retention/attenuation
of combined sewage through modification of  regulators,  construc-
tion   of weirs,  restraining of tide gates  and other  means.   In
addition,  over  18 mg of off-line storage  at seven locations was
recommended  to  be constructed to retain and treat  wet  weather
flows  in  excess  of the collection  and   transmission  system's
hydraulic capacity.    Disinfection was recommended to be provided
by  injection  of  chlorine into the influent  conduits  of  each
storage basin with a minimum contact time of 15  minutes.   Costs
for  construction of seven off-line storage/treatment   facilities
(excluding  multi-purpose  use considerations)  and including  in-
line  storage control improvements are estimated to  equal  $80.6
million (ENR=4500)(2).


Section 2.2   Hancpck Street Storage/Treatment Facility

         During  the mid 70's the first element of the  CSO  plan
was  implemented.   In  1977  the existing Hancock  Street  Flood
Pumping  Station was modified to include a 3.6 mg  storage/treat-

-------
                                                                                                exisriNO PUMPING STATION
                                                                                             .  EXISTING REGULATION
                                                                                             A  CHAMBER
                                                                                                EXISTING INTERCEPTOR
                                                                                          _._  CITY LIMITS
                           EXISTING COMBINED SEWER

                            AND OVERFLOW(TYPICAL)
                                                                                                      Of SERVICE AREA

                                                                                                 OUTSIDE CITY LIMITS
                                              EXISTING HANCOCK ST
                                              STORAGE BASIN
                                                                                                STORAGE BASINS
HANCOCK ST
     STATION
                                                                                                EXISTING STORAGE
                                                                                                BASIN
               WEBBER si PUMPING
                    STATION
                  WEISS ST PUMPING
                      STATION
                                  EMERSON ST PUMPING
                                       STATION
  EAST SIDE
INTERCEPTOR
                                                                                                       EXISTING
                                                                                                      WASTE WATER
                                                                                                       TREATMENT
                                                                                                         PLANT
                    FOURTEENTH si
                   PUMPING STATION
Figure 4  Location of CSO  storage/treatment basins.

-------
ment  facility.  The  existing  pumping station was  upgraded  to
include electric-driven pumps.  A multi-purpose underground stor-
age/treatment   facility with above ground municipal parking  was
constructed. Excluding garage and in-system modification improve-
ments,  the  capital  costs (ENR=4500) of the  facility  equalled
$10.4 million.   In-line storage potential of the combined sewers
in  the  Hancock  Street  area was  increased  by  modifying  the
existing   static  regulators  in  the  system.    Capital  costs
(ENR=4500)  of  the in-line control improvements in  the  Hancock
Street  catchment  area equalled $.56  million.   See  Figure  5.
Modifications to the regulators included replacing the tide gates
at  the outfall with motor-operated sluice gates to increase  the
maximum storage capacity of the system.

          During the storm events, combined flows diverted to the
interceptor by the regulators activate the Hancock Street pumping
station  as the interceptor flow level increases.   Sluice  gates
between  the  interceptor and the pumping station wet  well  open
automatically  and pumping is sequentially controlled by  sensing
the  wet well water elevations.   All flows to the storage/treat-
ment  basins  are pumped.   During extreme  river  flooding,  the
station  can  be  pumped  directly to  the  river  bypassing  the
retention basin.

          Combined  flows pumped to the Hancock  Street  facility
sequentially  fill  a series of paired  basins.   The  facilities
operate under two types of storm flow conditions:  a)  for 1 year
design storm,  the flow will be captured and totally stored, with
subsequent   release  to  the  interceptor  as  capacity  becomes
available;  and b) for storm events producing flow exceeding  the
basin  storage  capacity,  the system will store and  treat   the
combined  flow  by  sedimentation with disinfection  of  overflow
before discharge to the river.

          To date, the success of the overall detention/chlorina-
tion facility concept has been mixed.  Construction costs for the
Hancock Street facility exceeded estimates by roughly one million
dollars. Suspended solids treatment efficiencies have ranged from
35  to  92%.   Chlorination equipment has been inoperative  since
construction.   Recently,  severe  operating difficulties  during
intense  rainstorms have arisen due to the motor-operated  sluice
gates  in the Hancock Street catchment area.   The  sluice  gates
open  or close in a finite period of time.   If the gates do  not
open  to permit rapidly developing peak flows to  overflow,  then
severe surcharge problems result.

-------
                                                                            EXISTINO PUMPWO STATION


                                                                            EXISTWC REGULATION
                                                                            CHAMBER


                                                                            CXItTINO  IMTCTCfPTO*
                                                                      _._ CITY LIMITS
                                                                            LIMITS OF SCftVICC AREA
                                                                            OUTSIDE CITY LIMITS
                                                                                PROPOSED
                                                                            STORAGE BASINS
                                                                            Elements  completed
                                                                              in 1977
           EXISTING COMBINED  SEWER
            AND OVERFLOWCTYWCAL)
     . HANCOCK ST.
STORAOE IASIN
                             HANCOCK ST. PUMPING
                                  STATION
WEBBER ST
     STATION
                WEISS ST. PUMPING
                    STATION
                  EMERSON ST. PUMPING
                       STATION
                                EAST SIDE
                              INTERCEPTOR
                                                     EXISTINO
                                                    WASTE  WATER
                                                     TREATMENT
                                                       PLANT
;                                                FOURTEENTH ST.
                                                LIMPING
Hancock  Street  Storage/Treatment  Facility  Implementation

-------
                            CHAPTER 3

          COMBINED SEWER OVERFLOW CONTROL: 1979 - 1985


Section 3.1  Rationale for Replacement of CSQ Facility  Plan

          During  the  late 70's developments  in  CSO  abatement
technology  indicated the potential for treatment of excess  wet-
weather flows through application of high-rate processes.   These
high-rate  processes  were  shown  to result in  the  removal  of
pollutants  (especially  solids) at an efficiency  equivalent  to
"low  end"  primary  treatment  at a  fraction  of  the  cost  of
conventional   facilities.    One   such  device  is  the   swirl
concentrator,  which  has been demonstrated to achieve  over  40%
"first flush" suspended solids removal and a significantly larger
fraction of floatables (3).

          In view of these new technological developments and the
rising  inflationary  costs  of both the envisioned  storage  and
treatment  construction  programs and the ensuing high  degree  of
operational requirements already experienced, the City  of Saginaw
applied for,  and received a Section 108 grant from the U.S.  EPA
108  Great  Lakes  National Program,  Region  V.   The  grant  is
entitled,  "Demonstration  Grant  for Control  and  Treatment  of
Stormwater  from  Combined  Sewer Overflows in Saginaw"  and  was
funded to implement and evaluate on a full-scale basis  new  inno-
vative low-cost technologies for mitigating CSO  discharging from
the City of Saginaw sewerage system into the Saginaw River.   The
108  Program  and subsequent funding was established when  Public
Law  92-500 came into existence for the purpose of  demonstrating
promising  technologies for abating CSO and stormwater  pollution
impacting the Great Lakes.   Approximately $1.1 million was allo-
cated  to the project.   Environmental Design  &  Planning,  Inc.
(EDP) was the engineer for the project.


Section 3.2 Overview: 108 Demonstration Grant

       The project progressed from 1979 until  1985,  culminating
with   implementation  and  evaluation  of  a  number  of  system
improvements.      The  overall  work effort  consisted  of  three
separate phases.  Within Phase 1 EDP prepared a feasibility study
in  which the most cost effective .means of treating CSO using new
state-of-the-art technology were established.   During this phase
a  CSO  Facility  Plan  was developed  and  adopted  as  well  as
recommendations   for   implementing a   demonstration   project.
Several   promising  demonstration  projects  were  proposed  and
detailed but the costs exceeded available grant monies.   In 1983
(Phase 2) a further investigation was prepared  due to a lack  of
supportive 201 funds to implement several elements of the adopted


                               11

-------
CSO  Facility  Program.    Phase  2  efforts  were  directed   at
optimizing  a reduced scope of work plan for implementation using
available  funds.  In  Phase 3 these proposed  improvements  were
designed, implemented and evaluated.


Section 3.3  Phase lj  108 pemonstration Project

          The  objectives  of the Phase 1 (1979-1981)  EDP  study
were twofold:  a) preparation of an alternative overall framework
plan  for  the  management  of CSO   from  the  City  of  Saginaw
considering, but not limited to, the existing concepts of storage/
treatment/chlorination  facilities;   and  b)  preparation  of  a
detailed  preliminary plan for a portion of the envisioned  city-
wide plan, entailing implementation of a full-scale demonstration
treatment  facility  devised in such a way that it would  form  a
logical element of the overall CSO  Facility Plan.

          Runoff  simulation studies indicated that the two  most
effective  measures for handling CSO were increased  wet  weather
loadings  to  the  City's WWTP and inclusion of   actions  termed,
"Best  Management Practices"  (BMP).  The BMP program consists  of
extensive  in-line storage and system modifications  to   increase
hydraulic  capacity  so that the WWTP can handle more wet  weather
combined  sewage.  Roughly  2 million cubic feet  of  new   in-line
system   storage  would  be generated as a result   of  this  plan.
Estimated    capital  cost  of  BMP plan  equalled  $2.7  million
ENR=4500) .

       After  implementation of the complete BMP plan,  CSO's   for
heavy  to  moderate  storm  events would   still   remain   at   six
locations:  Weiss Street Pump Station, Weiss Street  gravity line,
Emerson  Street Pump  Station,  Fourteenth Street Pump Station   and
gravity  line   (handled as a composite),  Webber   Street   Pumping
Station   and    the  Fraser  Street   Regulator.   Swirl    solids
concentrating  facilities were  recommended  at  these  locations  as
the  most cost-effective technology for treating  these overflows.
Optimization analysis of various  swirl  configurations/sizes  at
the  various overflow  points  (after implementing  the BMP  program)
resulted in pin-pointing  the Weiss Street   area  as  the  most
significant  location for  a major  swirl  concentrator  facility.

       Although   the proposed BMP program  elements were the  most
cost-effective   means  for  abating  CSO  in Saginaw  (see Figure   6),
U.   S.   EPA  desired  at that time  to implement  and to conclusively
evaluate  the effectiveness of  the swirl concentrator  technology
for  reducing CSO pollutant  loadings.    The  24-foot diameter  swirl
concentrator (design flow  - 40  cfs) in  Lancaster,  Penn.  showed
significant  promise  as a  new  inexpensive technology  in comparison
to sedimentation/detention for  reducing CSO settleable  solids  and
floatables.   Although  the   suspended   solids  removal   results,


                                12

-------
   % REMOVALS *
100-
80-
60 -
40 -
 20 -
      * % Removals based on
      totol wet weather load to
      river assuming WWTP
      handled only DWF.
                          • Swirl plans
                          O TSS]
                          O 8001
                          A Other system improvements
                                                                itaroge basin plan
                                                                                                  O
                                                                                                  O
                  "RT"- WWTP Handling Wet Weather Flows
                  "RTH"- Addition of Hancock  St. Facility
                  "BMP"- Addition of In-Line  Storage  Program
                         to "RTH"
                  "S./.."-  Addition of  various  Swirl  Configur.
                            to "BMP"
                  "H"  - Prior Storage/Treatment Plan (Complete
               "Low Rainf: Total rainfall per event less than or equal to 0.5 inch
               "High Rain":  Total rainfall per event greater than 0.5 inch
                            ( 1979 rainfall data: 78 events )
            T~
             RT
RTH
BMP
	\	
 SI /SID
S2/S20
	1	
 S3/S3D
	1	
 S4/S40
	1	
 S5/S50
S6/S60
                                              Plans
               Figure 6   Effectiveness of overall preliminary plans.

-------
particularly  during  "first flush"  conditions,   were  extremely
favorable  the evaluation program was plagued with numerous  flow
measurement  instrumentation problems.   Since a number of  swirl
concentrators were being incorporated into designs throughout the
U.  S.  at  that  time,  U.S.  EPA  believed  that  the  proposed
evaluation  program  at  Saginaw  would  answer  any   unresolved
questions  remaining from the Lancaster experience.   It was also
desired  by  U.S.  EPA at that time to construct and  evaluate  a
swirl concentrator of larger physical dimensions than the  device
at  Lancaster   to  expand  the evaluation  experience  for  this
emerging technology.

          The  Phase  1 study (4) recommended  three  alternative
swirl  concentrator demonstration facilities located at the Weiss
Street  gravity  overflow,  at   the Weiss  Street  Pump  Station
discharge and at the gravity discharge at Fourteenth Street.  The
facility at the Weiss Street gravity overflow was preferred.

Section 3.3.1 New CSQ Facility Plan r. Phase 1

       Because  of  the significant cost savings associated  with
the  City-wide  CSO control program reported during the  Phase  1
feasibility  study and as a mechanism to facilitate  Section  201
Construction Grants funding to partially support the costs of the
proposed   demonstration  project  at  Weiss  Street,   EDP   was
instructed  in  mid  1980  to expand the Phase  1  study  into  a
proposed  CSO  Facility  Plan for the City  of  Saginaw  (5).  In
January,  1981  the proposed CSO Facility Plan was adopted by the
City  of  Saginaw and is depicted in  Figure  7.   A  comparative
overview   of   the  new  CSO  Facility  Plan  with   the   prior
storage/treatment program is depicted in Table 1.

       The major components of the adopted CSO Facility abatement
program are as follows:

       A:   BMP program implementation

       B:   Swirl Concentrator Facilities at:
                                              Design Capacity

               Weiss  Street Pump Station           300 cfs
               Weiss Street Gravity Line            100 cfs
               Emerson Street Pump Station          300 cfs
               Fourteenth Street Pump Station*       50 cfs
               Webber Street Pump Station            50 cfs
               Fraser Street                         50 cfs


               * Also Gravity Discharge Line
                               14

-------
               LEGEND

                     EXISTING INTCMCCPTON
                      LIMITS OF SEKVICC
                      OUTSIDE CITY LIMITS
                      PROPOSED REGULATOR
                      MODIFICATIONS:
                      PROPOSED INUNC FLOW
                      CONTROL/STORAGE DEVICE
                                                   I Imi r nrW
                                                   noncocK
                                            Storage/Treatment Facility
                                                  ^
                   •  TYPE A

                   A  TYPES
                  Proposed
                  Webber SI
                  Swirl Facility
              St. pumping station
     r->  weir increase

    *|*-Prooosed Weiw
         twirl facility (swirl dtgrittv)
                             EXISTING
                            WASTE WATEM
                             TREATMENT
                               PLANT
Proposed Fourteenth St
swirl focilily
               	TYPICAL EXISTING
                      SEWER LINE
Figure  7        Proposed EDP CSO ptan.

-------
                                         TABLE 1
                              COMPARISON OF RECOMMENDED PLAN
                                   AND ALTERNATIVE PLAN
Basic
Technologies
Description
Swirl Concentrator
Swirl Degritter

Chlorine/Chlorine doioxide
  Sequential Disinfection

In-line Flow Control
  for In-system Storage

BMP Plan  (1980)
  Management practices
  System modifications
  In-line  storage

Swirl/Disinfection Facilities
  at 6 overflow locations
Storage/Sedimentation
Basin

Chlorine
                                                      In-line Flow Control for
                                                        In-system Storage
                                                      In-line storage (1974)

                                                      Storage Basins/Disinfection
                                                        facilities at 7 overflow
                                                        locations
Effectiveness
Capitol Costs
(Million  $)
(ENR=4500)
TOTAL
Swirl Degritter at Weiss Complex
   (contingency)

56% TSS removal
50% BCD removal
Significant floatables removal
Greater than 90% settleable
   solids removal
    23.7
 52% TSS removal
 55% BCD removal
 Significant floatables removal
 Greater than 90%  settleable
   solids removal
 80.6  (w/Hancock)
 70.2  (w/out  Hancock)
Operation and
Maintenance
 (Annual, 1985
Million)
       .49
                                       .76
                                16

-------
             A.   Description of Complete BMP Program

      The  BMP  program  concept is to maximize  in-line  storage
already available in the system conduits and conveyance of  storm
flows  to  the  WWTP.   To  actualize  this  plan,  the  existing
regulators  were  to  be modified and new "second  tier"  in-line
control  structures  were to be installed to  increase  in-system
storage.

          It  was envisioned to alter 24 regulators  with  vortex
valves  to  yield  a constant discharge  during  initial  storage
filling, with excess flows beyond available storage (for small to
moderate  storms)  diverted  to the interceptor rather  than  the
river.  In  addition,  the five modified Hancock area  regulators
(modified  as  part  of the  Hancock  Street  Detention  Facility
Implementation  in  1977)  were  to  be  replaced  with  constant
underflow  discharge  devices  (vortex flow valve  regulators)  to
increase  the  "first  flush" diversion to  the  interceptor  and
maximize  the use of the interceptor throughout the storm  event.
Furthermore,  five other  regulators of smaller size were  to  be
altered  with  weirs  to  divert all flows  to  the  interceptor.
Existing  weirs  at  all 34 regulators were  to  be  modified  to
enhance  in-system  storage and to maximize flow to  interceptor.
Fourteen  upstream structures with vortex valve  flow  regulators
were  to be constructed to yield additional in-line flow  control
for  storage  upstream of the regulator chambers.  The  resulting
changes  to  the regulator operations would achieve  the  maximum
useable  in-line storage potential of the system.

          An  increased  weir elevation of five feet  was  to  be
imposed  at  the  Weiss Street Pumping Station to  reduce  pumped
overflows  at that point and increase the flow across  the  river
crossing  and  into the East Side Interceptor.  This  improvement
would maximize West Side "first flush" passage to the WWTP.


         B.  Description of Swirl Concentrator Complexes

          Swirl concentrator facilities were proposed  at each of
the  six  major  overflow  points.   The facilities  were  to  be
tailored to the particular needs of each site.   Pumping stations
to drive the swirls were considered necesssary at each site.  New
lift  stations  were to be included for the Weiss Street  gravity
overflow  and  for  the Fraser Street  overflow.   A  battery  of
various   size   fixed  speed pumps  were  considered  for  these
stations.  The existing 100-cfs fixed speed pumps were to be used
(after  revamping/turning)  for all other stations  as  required.
New  low  capacity   (25-40  cfs) fixed speed pumps  were  to  be
included  in  all revamped stations to provide  variable  pumping
range  using  the  revamped  fixed  speed  100-cfs   pumps.   The


                               17

-------
Fourteenth  Street swirl facility was to handle combined  gravity
line  and  pump station discharge ( subject to further  hydraulic
and locational studies).

          A  swirl  degritter at the Weiss Street complex may  be
necessary if the proposed City-wide system of swirl concentrators
were  implemented  and  pending a careful  review  of  WWTP  grit
removal   capacity   under  sustained  wet  weather   high   flow
conditions.   This  degritter contingency was proposed to  ensure
that the WWTP's solids handling capacity would not be overtaxed.

Section 3.4   Description of Three Efforts to Develop
              the Demonstration Project ^ Phase 1

          Three  alternative  CSO treatment  configurations  were
investigated in detail so as to provide a suitable  demonstration
project.   It  was  anticipated that the 201 program  might  lend
partial  financial support for the project given that a  Facility
Plan had been developed and that program elements had been placed
on a priority list for funding.  Unfortunately, 201 funding never
materialized  and  final  selection of  a  demonstration  program
occurred in Phase 2.
         Alternative 1: Weiss Street Swirl Concentration
                        Demonstration Project

           Although the magnitude of the overflow at Weiss Street
greatly exceeded those at other locations,  City-owned land space
to  construct the proposed facility (see Figure 8) was  extremely
limited.  Design  of the proposed swirl concentrator facility  at
Weiss  Street  was  curtailed  due to  the  envisioned  long  and
protracted  period  required  to  acquire  the  necessary   land.
Estimated construction costs and evaluation equalled $3.1 million
(ENR=4500).


   Alternative 2: Proposed Weiss Street Demonstration Project;
                  Dunker's Floating Tank System

          In December,  1980, U.S. EPA introduced Karl Dunkers to
EDP  as he was touring the United States marketing  a new innova-
tive,  extremely cost-effective,  flow-storage technology.   Karl
Dunkers is an independent Swedish research engineer and  inventor
and  was commissioned by the National Swedish Board for Technical
Development.   In  the  mid-70's  Dunkers experimented  with  and
obtained  an  international patent for a pontoon tank  system  to
equalize  inflow  in  a two fluid media system  using  plug  flow
principles.
                               18

-------
                                                                  CITY PROPERTY LINE
120" Combined
                                         iverslon
                                         Chambe
   Regulator
                                                                          42" INTERCEPTOR
                                                   umping
                                                  Station
                                                                              RIVER CROSSING
                       Swirl
                       DegHtters
                       Proposed
                       Future
                                     :   DISIN--:-:
                                     -  FECTION----
                                     I-  CONTACT.---
                                     -CHAMBERS-.-.
                                                           .(FUTURE)-:-!
      Figures
   >^ PRIVATE ^	*<        ^Disinfection chemical
       PROPERTY                 storage building

Layout of Weiss Street combined sewer overflow treatment complex.

-------
          During the course of discussions with Dunkers,   EDP was
initiating  contract  work for plans and specifications  for  the
section 108 swirl technology demonstration project designated for
the  Weiss Street area.    At that time EDP was informed  by  the
City  of the  adverse unresolvable land problem at Weiss  Street,
effectively  precluding  this site from consideration as a  swirl
demonstration  site.   The Dunker's approach minimizes  dry  land
requirements  and  its application for the Weiss Street area  was
obvious  as a means of storing CSO with later bleedback to  WWTP.
EDP was immediately directed  to investigate this technology as a
potential demonstration project.

          In  principal,  Dunkers1  device  creates  in  a fluid,
through   a  pontooned  celled  system,   a  means  of  inputting
extraneous  fluid  (stormwater/CSO)  while  displacing  currently
stored fluid (lakewater) in a plug flow manner.   After the storm
event the reverse pattern is created.   For a small runoff event,
only  one or more of the cells are used and since the  device  is
finite,  it can be overflowed during a large event.  The relative
efficiency  in transferring flows through plug flow operation  is
determined  by the number of cells and relative  placement.

          A  conceptual plan view layout of the Dunkers1   pontoon
tank system in the (900 foot long,  100-200 foot wide,  6-10 feet
deep)  man-made  channel connecting the Weiss Street CSO  to  the
Saginaw  River is depicted in Figure 9.   The present channel was
formed  in the mid 50's when the interceptor river  crossing  was
constructed.   Low,  average high river elevations are 79.0, 81.0
and 84.0 feet,  respectively.  The channel volume up to elevation
79.0  is  estimated  to be 0.8 million cubic feet  under  present
alignment conditions (6).

          The   project  concept  would  be  as   follows.    CSO
discharging  from both the Weiss Street pumping station  and  the
gravity  trunk are to be  captured in Dunkers' system subject  to
the volumetric limitations of the channel  (as improved)  during a
given  storm  event.   Discharge   (volume) from  both  the  Weiss
gravity/pumped  discharge  would be automatically  monitored  and
total volume discharged into the pontoon system noted.  Following
the  event,  the  stored overflows would be pumped back into  the
interceptor  river  crossing  during suitable  dry  weather  flow
conditions.

          Total  estimated construction cost including  extensive
channel improvements (excluding evaluation) is about $1.6 million
(ENR=4500).   It  was estimated that the Dunker's storage  system
would  capture on the average,   about 62% of all CSO from  Weiss
Street with subsequent bleedback to high-performance WWTP.  Over-
all,  this approach was more cost effective than the earlier land
based  storage /treatment facility programmed for  this  location
and  the swirl concentrator complex proposed in the new  facility
                                20

-------
                                                                                                                                                                          SAG IN AW
                                                                                                                                                                           RIVER
3CHWINK PROPERTY
    I 34 ACRES
SCHWINK PROWflTY
   904 ACHES
LEGEND
|^^^| PROPOSED ACCESS ROAD
^"^ FENCE (TYP)
|7 — 7~7| ROCK FILL UITH
V / /I RIP RAP FACE
tj Y M AREA T0 BE CUT
IA A Al AND TRIMMED
— 	 	 POLYETHYLENE FORCE WIN
^ 	 ^V DIRECTION OF FLOW
82.2 EXISTING GRADE (TYP)
® MOTORIZED BALL VALVE
IN METER COX ENCLOSURE

WEISS ST COMBINED
SEWER OVERFLOW FACILITY
DUNKERS TANK SYSTEM
PRELIMINARY
CONTRACT NO SCALE i"= 40'
DRAWN BY PL
CHECKED BY W C P
DATE
4/1/81

DRAWING NO
1 OF 1
EOP Environmental Design & Planning, Inc.
~z=^^^r^Z Engineering. Planning A Field Services
                                                                                                                                                                             21

-------
 plan.    This   concept was proposed as a demonstration project but
 did not  proceed  due  to the level of available funding.


         Alternative  3:  Webber Street fiwitl Concentrator
                        Facility

           In raid 1981 it appeared that 201 funding support seemed
 probable  and  EDP was instructed to re-direct efforts for  place-
 ment  of the proposed swirl concentrator  facility at an  alterna-
 tive  location  within  the City.  The alternative  facility  was
 nevertheless   to be  constructed  as a  logical  and  congruent
 element   of  the overall  adopted CSO Facility  Plan.  The  Webber
 Street  Pumping  Station area  was chosen  as the new  location   to
 place  the proposed  demonstration facility.  An analysis of  this
 catchment was conducted supported by detailed  field  measurement
 programs  so   as to increase the technology scale of  the  swirl
 concentrator (80  cfs) from the scale (50  cfs) proposed in the CSO
 Facility Plan  (7).

           In 1981-1982 EDP prepared construction plans,  specifi-
 cations   and bid documents for a new treatment  complex consisting
 of   an   in-line   diversion structure controlled by  vortex  flow
 regulation devices  to direct flow to the existing pump  station,
 with lift by a new 80-cfs pumping plant,  on to  a 38 foot diameter
 swirl  concentrator.  See Figure 10.  The  cost of the facility was
 estimated to be  approximately $2.0 million (ENR=4500).

           Approximately  $.75 million was remaining from the  108
 grant  and additional  201 funding became  unavailable.  It  was
 forcasted that this  low status would remain for  the next  several
 years  and it was finally decided by U.S.  EPA to  indefinitely
 postpone  the proposed demonstration swirl concentrator project.


 Section  3.5  Phase 2. 108 Demonstration Project

           In   early  1983,  U.S.  EPA and  the International  Joint
 Commission   (IJC) ( U.S.   and  Canada)  became  interested    in
 developing  phosphorous limitations for the Great Lakes revolving
 around    a   number  of  promising  BMP   practices   controlling
 agricultural   and urban runoff  phosphorous  loadings.    Sewerage
 system  management   employing  system controls   to  inexpensively
 maximize  transient in-line storage with bleedback to WWTP's  with
 high performance treatment was identified and viewed by U.S.  EPA
 as  a promising management prospect in view of  the continuing low
 federal   funding  profile for the next several   years.    Since  a
 number  of the major sewerage systems impacting  the  Great  Lakes
 are  combined,    relatively flat and discharge to high performance
WWTPs,   the  notion of  evaluating inexpensive system storage  and
 hydraulic  optimization in Saginaw was attractive,   feasible  and


                               22

-------
                                                        1_
                                                       f-
                                                        0>
                                                        
-------
logically  extendable  to  other areas  within  the  Great  Lakes
region, if proven to work.

          On instruction in April, 1983, EDP embarked on Phase 2.
The  objective   of the Phase 2 evaluation was to  determine  the
optimum  implementation plan for the reduction of CSO impacts  to
the  Saginaw  River based on available money and the elements  of
the  overall  CSO  Facility  Plan.   Optimization  included  cost
estimation  of  each plan element followed by a series  of  model
simulations  using  various combinations of elements  within  the
total allotted project budget.

          As a first step,   additional field evaluations of flow
patterns  at various regulator chambers were  performed  allowing
further  calibration  of the simulation model.  A  limited  field
investigation  was performed including continuous water elevation
recording  at  several  regulators on each side  of  the  Saginaw
River.    This  data  was  combined  with  information  routinely
collected  by  City  personnel at the Weiss  Street  and  Hancock
Street  Pump  Stations  and at the WWTP  to  estimate  area  wide
hydraulic  conditions.  Simulations  then indicated  the  optimum
configuration  for the "Reduced BMP" implementation  plan.   This
plan  consisted of modifications to the Saginaw  sewerage  system
only  on  the West Side of the Saginaw River.  See Figure 11  for
locations controlled as part of the "Reduced BMP" plan.

          Since the entire BMP plan was not to be implemented  at
this  time,  it  was important that all elements of the  "Reduced
BMP" plan be designed and implemented such that no  modifications
will be required in the future.  Furthermore,  the concept of the
total  BMP  plan  was to control the system such  that  overflows
(except  for  extreme events) would occur only  at  major  pumped
discharge  points.  Since  it was not envisioned  to  modify  the
Emerson Street Pumping Station at this time  (for automatic "turn-
on"), the  "Reduced BMP" plan was designed such that no additional
capital    expenditure  for  pumpage  and/or  adverse  operational
problems  would occur as a result of the implementation.  It  was
for these  reasons that improvements were only programmed for  the
West Side.

          As  part of the "Reduced BMP" plan,  13 of 34,  of  the
City  of Saginaw1s combined sewer regulators were to be  modified
in accordance with the CSO Facility Plan Concept.  One of the  14
upstream   in-system type structures was  also to be  constructed.
See  Figure 12.   The Weiss Street Pumping Station weir/wet  well
operation was to be modified to increase river crossing discharge
so that more of the West Side "first flush" is transmitted to the
WWTP.
                                24

-------
NJ
Ul
                                                                r
A
                      /
                                                              r
~i
                                              .V
                                                   -Emling Hoococh SI.
                                                   Storogt/Trtotnwnt Fodlily
                                                                                                     LEGEND
                                                                                                     — -—  eirr

                                                                                                     — .— .  UMI
                                                                                                           oursioe CITY LIMITS
         r
          J
                                                                                                        • TYPCB
                                                                                                        • MODIFIED TYPE B
                                                                                                          2p*OSC0MUNEnj0W
                                                                                                          OONTMOL/STOMAee OCVCC
  4
                                                                                            _J   —J
                                                                                            O   ELEMENTS COMPLETED
                                                                                                  IN 1984
                                                                                                twirl fooKty (i«M d^rtttar)
                                                                                                Wtiti SI (wnping tMiOM
                      Figure 11   Details of Reduced BMP  Plan

-------
          CONCRETE FILLETS
                 TO 108 PIPE
CONFORM
   1/4
THEN SLOPE
          F0« /4 PIPE DIAMETER
                   I* PER FOOT
New Vortex  Valve Flow
Regulator with Vent
to
                                                                                   CAST-IN-PLACE ANCHM ASSEMLV
                                                                               SECURE FLOW REGULATOR TO SLA1
                                                                              CONCRETE FILLETS CONFORM TO 103" PIPE
                     Figure 12
                          Salt and Vermont Streets Chamber  - Plan View

-------
Section 3.6  Phase 3. J.Qg pemonstration gr o jecfc

          In April,  1983,  EDP was instructed to proceed with an
implementation program for the "Reduced BMP" Plan and to  prepare
construction  plans  and  specifications.   In  March  1984,  the
construction  contract was awarded to Gary D.  Steadman,  of  Bay
City,  Michigan.  Advanced  Fluidics,  Inc.  supplied the  vortex
valves  for the project.   The construction began in April,  1984
and was completed in September, 1984.

          The  Phase 1 EDP sewerage system simulation  model  was
used  to estimate City-wide emissions pre/post "Reduced BMP" plan
implementation. Flow measurements using automatic  equipment were
made  at  a number of representative regulators as  part  of  the
Phase  3  preproject  conditions.  After the "Reduced  BMP"  plan
project  was implemented,  flow measurements were   conducted  to
document  the  effectiveness  of the implemented  controls  on  a
representative basis. A limited post-implementation water quality
sampling    program    was  conducted  using  automatic   sampler
techniques.

          Detailed   observations   were  also  noted   by   City
maintenance  personnel  during routine post storm  inspection  of
regulator chambers to determine physical conditions.   One aspect
of  the  "reduced BMP" plan was to include low  maintenance  flow
regulating  devices to replace the existing float-operated  type.
These  existing  devices required frequent maintenance  and  were
subject to failure.  The new vortex valve flow regulating devices
performed satisfactorily and have reduced maintenance problems.

          Structural changes to regulator chambers were  intended
to  improve system storage capacities and flow hydraulics without
causing excessive surcharge or in-system  sedimentation.   Degree
of  backwatering was noted at numerous locations upstream in  the
sewerage system.  Debris accumulations in all regulator areas and
sedimentation  in  dry  weather flow channels  were  particularly
noted.   These  observations served to document the reduction  in
maintenance labor provided by "Reduced BMP" plan implementation.

          The  post  implementation documentary effectiveness  of
the  "Reduced  BMP" plan improvements in terms of  increased  wet
weather  pollutant  loadings  to  the  WWTP  was  close  to   pre
implementation predictions.   Expenditures of $.504 million (1984
ENR=4500)  under  the "Reduced BMP" plan for low  level  sewerage
system modifications (entailing a significant portion of proposed
controls  for  one-half of the City) resulted in  decreasing  the
average annual system-wide total phosphorous wet weather loadings
to  the  river by about 10%.   Annual reductions for  solids  and
organic  loadings  to the river averaged about 20%.   No  adverse
conditions resulted from the plan.
                               27

-------
          Detailed   conclusions  and  specific   recommendations
deriving  from the Phase 3 program are presented in Appendices  A
and Bf respectively.

          In sum,  the concept of inexpensive system controls  to
maximize  transient  in-line  storage  of  combined  sewage  with
bleedback   to  a  high  performance  WWTP  worked  well  and  is
recommended as a management practice.
                                28

-------
                           APPENDIX A

              108 DEMONSTRATION PROGRAM CONCLUSIONS


          EDP  has  completed a five year 3 Phased study of   CSO
pollution from the City of Saginaw,  Michigan and concludes  that
CSO  pollution  in Saginaw is controllable at  reasonable  costs.
Pertinent   conclusions  associated  with  the  BMP  program  are
detailed in the  following order:


                        PLANNING £ DESIGN

          A.  Combined Sewer System Data Reduction Analysis

                   IMPLEMENTATION £ EVALUATION

          B.  Implementation of Reduced BMP Plan
          C.  Evaluation of Implemented  Reduced BMP Plan


A. Combined Sewer System Data Reduction Analysis


                   Wastewater Treatment Plant
(1)    The  secondary WWTP had the capacity  to  handle  combined
sewage  volumes greater than generally flowing to the  plant.  An
analysis of  operating records  indicated that both hydraulic and
treatment capacity for additional loadings were available without
impairment of  overall WWTP treatment efficiency.  Increasing the
flow  of  combined sewage to the WWTP was a primary goal of  this
study.   Pollutant  loads  to  the  river  are  expected  to   be
significantly reduced by increasing flow  to the WWTP and storing
excesses  within  the system  until throughput  capacity  becomes
available.

(2)     Review of daily operating records for 1978-1979 indicated
that  the BOD removal for the WWTP averages approximately 89% for
both  wet  days and dry days.

(3)    Review of WWTP data indicate wet weather total phosphorous
removal   of 50% without AWT.   Non-soluble phosphorous  removals
are 95% but no soluble phosphorous removal is achieved.   The non
soluble fraction averages 54% of the total phosphorous.

(4)     Advanced Wastewater Treatment (AWT)  (pickling liquor  or
PeS04 addition)  is used, as required at the WWTP to meet effluent
standards.   Phosphorous  removals average 75% with AWT  and  the
                               29

-------
entire  additional level removed beyond secondary treatment rates
is attributable to a 50% reduction of soluble phosphorous.


                        Interceptor Sewer Data

(5)    The junction of the West Side Interceptor  river  crossing
and  the  East  Side Interceptor  was identified as  a  hydraulic
bottleneck.  The Weiss Street Pumping Station relieves backwater-
/surcharge  at  the crossing and together with the  Weiss  Street
gravity overflow constitute the dominant CSO in the system.

(6)    The intercepting system's major  hydraulic  bottleneck  is
the  river  crossing.   Application  of additional  head  to  the
crossing  by  raising the weir level at the  Weiss  Street   Pump
station  would   increase flows across the  river.  A  five  foot
weir  height  increase  was  estimated  to  be  optimum.


                         Regulator Data

(7)    Regulators   (earlier modifed as part of the Hancock Street
Detention Facility  improvements  (mid 1970's)) had been altered to
cause the underflow orifices to close  rapidly,  limiting  flows to
the  interceptor and thus committing the  "first flush" of a  rain
event  to in-line storage created  at the  chamber.  EDP considered
it more advisable to maintain  higher underflow discharges to  the
interceptor,  limited   only to what the  interceptor can maximally
handle. Operation in this manner will  commit the  "first flush" of
a  rain event,  generally carrying the highest  concentration  of
pollutants, to  the  interceptor, and eventually to the WWTP.

(8)     It  appeared during the EDP inspection program  that  the
mechanical  float-operated  mechanisms used to  regulate   flow  at
the  regulation chambers were  slow in  responding to rising  water
levels.   The   City reported that  the  devices   required   constant
surveillance to maintain operation.

 (9)       New   vortex  flow throttling  devices   having  no-moving
parts,   large   aperture  openings  (in  comparison to   conventional
orifices)   constructed of  durable  material  (stainless steel)  and
reported   to be nearly clog-free were  envisioned to   replace  the
existing  mechanical  float operated mechanisms  in the regulators.


                        In  System Storage JJaia

 (10)     Potential  in-line  storage  capacity  in the Saginaw  sewer
network    is   extensive.   A   total   storage  volume    (including
interceptors and  WWTP  aeration tanks)  of 3.93  million cubic  feet
                                30

-------
(29.4  million gallons) has been  estimated as available  without
threatening basement flooding.


B.  Implementation of Reduced PMP Plan

(11)      Implementation  of  the "Reduced  BMP"  plan  including
modifications of 12 of 34 combined sewer regulators, construction
of  one  upstream in-system storage structure and increasing  the
effective  head at the Weiss Street crossover was  completed  for
the construction price of $315,000.

(12)      Modification  of  regulator chambers  was  accomplished
under  controlled conditions such that no dry weather  sewage  or
wet   weather   combined   sewage  impacted  the   river   during
construction.

(13)     Vortex  valve  flow  regulators  were  constructed   and
installed  in  variable  arrangements  to  conform  to   existing
conditions  within  the  regulator  chambers.  The  devices  were
segmented  for  ease  of installation particularly  where  access
space is limited.


C.  Evaluation Q£. Implemented BMP Plan

(14)      With the exception of limited pollutant removal at  the
Hancock  Street  Facility,  all  reduction of CSO impact  to  the
Saginaw  River is attributable to increased  in-system  transient
storage  coupled with increased flow to the WWTP.   Prior to this
program,  it is estimated that on an annual basis,  37.7% of  all
wet weather related flow would be handled by the WWTP.  For  "Low
Rainfall"  events (total rain less than 0.5 inches),  53% of  the
system wide wet weather flow would be handled by the WWTP.

(15)    Implementation of the "Reduced BMP" plan is estimated  to
have  increased  the percentage of total annual wet weather  flow
directed  to the WWTP by 14.6% (from a previous "as is" level  of
37.7%).  For "Low Rainfall" events,  this incremental increase in
flow  directed to the WWTP would be 19%.   Implementation of  the
remaining  elements  of  the complete BMP plan could  produce  an
overall  incremental  increase of 30% (increasing the  total  wet
weather flow treated at the WWTP to 67.7%).   For "Low  Rainfall"
events,  this incremental increase in flow directed to WWTP would
be 34.6%.

(16)      Implementation  of the "Reduced BMP" plan is  estimated
to have incrementally  reduced (beyond "as is" levels)  suspended
solids loadings to the Saginaw River by 16%, BOD by 20% and total
phosphorous  by  8.5%.   During periods of AWT  (pickling  liquor
addition) at the WWTP,  total phosphorous removals will  increase
                                31

-------
12.6% above pre-implementation levels.

(17)     On a weight basis, the "Reduced BMP" plan implementation
is   estimated  to  have  reduced  wet  weather  suspended  solid
pollutant loads to the river by 1.4 million pounds per year,  BOD
by  0.47  million pounds per year and total phosphorous  by  3000
pounds per year.   Wet weather related total phosphorous loadings
are  estimated  to  be  reduced by 3000 to  4000  Ibs.  per  year
depending on application of AWT.

(18)      Incremental TSS and BOD removals of total  wet  weather
loadings  to river attributable to implementation of the complete
BMP program (when completed) are estimated to equal about 29% and
30%,  respectively.   Total phosphorous reduction with  secondary
treatment  is estimated to equal 16.7% and with AWT  would  equal
25% above pre BMP conditions. Mass removals due to implementation
of  the  complete BMP plan  (when completed) are estimated as  2.5
million  pounds  of SS,  0.68 million pounds of BOD and  7000  to
10,000  pounds  of total phosphorous  (latter  estimate  when  AWT
used).

(19)       WWTP TSS and BOD removal levels noted during the  post
construction  evaluation period (late 1984) have not  diminished,
confirming earlier Phase 1 and Phase 2 projections.

(20)       It  has been determined that the modification  of  the
Weiss  Street  Station  spillover weir level  has  increased  the
crossover  rate  by about 20 cfs under all  conditions.

(20)     With the exception of a few minor reported incidences of
large  stick  debris  cloggage  and  grease  blockage  of   device
handling  small  flows  (0.2 cfs),  the flow and  solids  handling
performance  of  the  new vortex valve  flow  throttling  devices
replacing  the  mechanical float-operated controllers within  the
regulation chambers was satisfactory.   No adverse flow backup or
sedimentation  problems  were  reported.   On  one  occasion  the
devices were visually observed to pass "first flush" and  scoured
solids  on  draindown.   Limited  flow  calibration  measurements
indicated   that   the   devices  generally   operated   as   per
manufacturer's specifications.

(21)      The performance of the new in-line control  chamber  at
Salt  &  Vermont Streets which generated at  maximum  capacity   a
transient  storage volume of 175,000 cubic feet  ($0.57/cubic foot
storage) was satisfactory.   The new vortex valve flow throttling
device  which  controlled   the wet weather  discharge  from this
facility  as  well as permitting passage of  normal  dry  weather
sewage worked extremely well.  No blockages, sediment buildup nor
adverse backups were reported.
                                32

-------
                           APPENDIX B

                108 DEMONSTRATION RECOMMENDATIONS


          The  conclusions  stated in Appendix A clearly indicate
the effective use of elements of the BMP plan in reducing CSO  to
the  Saginaw River.   To date,  the entire BMP plan has not  been
scheduled for completion as the the funding for implementation of
complete  facility plan elements is not available.   In addition,
the  1984  investigation  of the  system  hydraulics  during  the
construction and post evaluation phases indicated areas of system
operation  where  additional  review  and  "fine-tuning"  may  be
necessary  in  the  future due to hydraulic  changes  induced  by
implemented   elements   of   the   BMP   plan.

          The following recommendations are presented in order of
importance:

1)         The "Reduced  BMP" plan included modification of  only
12  of  34 regulator chambers.    All other  regulation  chambers
should  be updated to include new vortex flow regulating  devices
as necessary,  and appurtenances designed to maximize storage and
minimize bypass to the river.

2)         One of 14 proposed upstream in-line  storage  chambers
was completed.   Facilities for the remaining locations should be
designed and constructed.   The recommended order of priority for
implementation of these locations is as follows:

                   In-line Storage Priority List

                   1.  River & Cambrey Streets
                   2.  Birch & Harris Streets
                   3.  Gratiot & Michigan Avenue
                   4.  Cass & Woodbridge Streets
                   5.  Hamilton & Williams Streets
                   6.  Union Avenue  & Delaware Street
                   7.  Jackson & Mason Streets
                   8.  MacKinaw Street & Michigan Avenue
                   9.  Troy & Boxwood Streets
                  10.  17th & Perkins Streets
                  11.  14th & Norman Streets
                  12.  Hayes Street  & Michigan Avenue
                  13.  Weiss & Delaware Streets

          The  in-line  storage  facility at  Weiss  Street   and
Delaware Street should be completed as part of the CSO  abatement
program work at the Weiss Street Pump Station complex.
                               33

-------
3)          Existing gate opening and pump "turn-on" sequencing at
the  Hancock Street Pump Station should be reviewed to  ascertain
whether  the  operation  is  optimal.   The  existing  monitoring
equipment   at  the  Hancock  Street  Pump  Station   should   be
upgraded,  if  necessary,  for the purpose of monitoring  station
operation in compliance with optimization recommendations.

4)         The pump initialization equipment at the Weiss  Street
Pump  Station  should  be reviewed to  optimize  turn-on/shut-off
elevations  and   to  ascertain  whether  supplemental  operating
controls are necessary due to the weir modification performed  as
part of "Reduced BMP" plan.

5)         The operations of the Hancock Street Facility and  the
Weiss  Street Pump Station should be reviewed to ensure that  the
Hancock Street Station operates prior to the Weiss Street Station
during  a  storm  event.    During  areawide  storms,   detention
storage/treatment currently available at Hancock Street will thus
be utilized prior to untreated bypass at Weiss Street.

6)         The  CSO  control facility for the Weiss  Street  area
should be implemented as overflows at this location are still the
dominant  source  of wet weather pollutant load  to  the  Saginaw
River.

7)        Under extremely high rate conditions,  wet weather flow
pumped to the WWTP grit chamber is split with partial overflow to
the   WWTP bypass.  Overflow commences at a total rate less  than
the existing WWPT flow-through capacity.  Possible replacement of
the  WWTP  overflow bypass weirs with other equipment  may  allow
initial storm flow containing "first flush" materials to pass  to
the  aeration basins for storage.   Later cleaner flows would  be
bypassed,  if necessary due to full basin conditions.

8)      Currently  potential pump cavitation  conditions  prevent
maintaining WWTP wet well levels at the initial design elevation.
Although  the  City WWTP personnel maintain maximum  wet  weather
throughput   whenever  possible  to  the  WWTP,   the  elevations
currently  maintained,  reduce  the  hydraulic  capacity  of  the
interceptor  system  during  major  events  causing  overflow  at
upstream  pump stations.   Hydraulic conditions of influent  pump
intakes at the WWTP wet well should be investigated to  determine
if baffles,  spoilers or intake vanes could reduce cavitation and
allow  lower  operating  levels,  and result in  lesser  upstream
overflow magnitudes.
                               34

-------
                      REFERENCES
Metcalf & Eddy,  Inc.,  "Report to City of Saginaw, Michigan
on Preliminary Design of the Hancock Street Combined  Sewage
Overflow Storage and Treatment Facility," March 16, 1973.

Lager J. et al, Urban Stormwa^ter Management and Technology;
Update and User's Gjiidfir  EPA-600/8-77-14. September, 1977.

Pisano,  W., Connick, D. and Aronson, G., "Swirl and Helical
Bend  Regulator/Concentrator  for Storm and  Combined  Sewer
Overflow Control," October 1984, EDP EPA-600/S2-84-151.

Pisano,  Rhodes and Aronson,  "Preliminary Engineering Study
for the Control and Treatment of Combined Sewer Overflows to
the Saginaw River", June, 1980, EDP.

Pisano,  Rhodes and Aronson,  "Facility Plan for the Control
and  Treatment  of Combined Sewer Overflows to  the  Saginaw
River",  November, 1980, EDP.

Environmental  Design  &  Planning,   "Design  Development
Document:  Weiss  Street  Combined  Sewer  Overflow  Storage
Facility", March, 1981.

Environmental   Design  &   Planning,   Inc.,   Design   and
Development  Document Webber Street Combined Sewer  Overflow
Treatment Facilities, June, 1981.
                          35

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
                                                           3. RECIPIENT'S ACCESSION-NO.
4. TITLE AND SUBTITLE
  In-System  Storage Controls For Reduction
 of Combined  Sewer Overflow
 Saginaw, Michigan
                                                          6. REPORT DATE
                                                           September 1985
                                                          6. PERFORMING ORGANIZATION CODE

                                                           5GL
7. AUTHOR(S)
 William C.  Pisano, P.E., Daniel J.
 Connick and Gerald L. Aronson
                                                           8. PERFORMING ORGANIZATION REPORT NO.
                                                           10. PROGRAM ELEMENT NO.
0. PERFORMING ORGANIZATION NAME AND ADDRESS
 Department  of  Public Utilities
 City of  Saginaw
 Saginaw, Michigan
                                                          11. CONTRACY/GRANT NO.

                                                           ROD5359
12. SPONSORING AGENCY NAME AND ADDRESS
 U.S. Environmental  Protection Agency
 Great Lakes  National  Program Office
 536 South Clark  Street, Room 958
 Chicago,  Illinois  60605
                                                          13. TYPE OF REPORT AND PERIOD COVERED
                                                           Combined Sewer-1979-1985
                                                          14. SPONSORING AGENCY CODE
                                                           Great Lakes National  Program
                                                           Office-USEPA, Region  V
IB, SUPPLEMENTARY NOTES
 Ralph 6. Christensen
 Project Officer
16. ABSTRACT

 This report  overviews the results of  a  recently completed five-year  combined sewer
 overflow  (CSO)  control program in Saginaw,  Michigan (10,000 acres,  Pop. 85,000)
 funded by City  of Saginaw/U.S. EPA  108  Great Lakes National Program.   The
 implemented  control  program entailed  modification of 13 combined  sewer regulation
 chamber to maximize  transient system  storage of wet weather combined  sewerage for
 later bleedback to a well-operated  Wastewater Treatment Plant  (WWTP)  having
 phosphorous  removal  and ample treatment  capacity.  These improvements, "the reduced
 Best Management Practices (BMP) plan",  represent a partial completion of the
 first of two phases  of the City's CSO Facility Plan.  The objective  of Phase I
 was to maximize WWTP processsing of wet  weather combined sewage generated using
 inexpensive  transient system storage  (less  than $l/cu.ft.) so  as  to  minimize the
 extent, scale and cost of satellite CSO  treatment facilities (Phase  II).  The
 swirl concentrator technology was recommended to treat residual overflows remaining
 after Phase  I improvements.  Six major  facilities were recommended  and adopted as
 part of the  CSO Facility Plan.  In-system storage is controlled with  vortex
 valve regulators.
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.lDENTIFIERS/OPEN ENDED TERMS
                                                                       c.  COSATI Field/Group
 CSO Pollution    Suspended solids
 Stormwater
 Phosphorus loadings
 Swirl concentrator
 Combined sewer
 Total phosphorus
18. DISTRIBUTION STATEMENT
                                i 5
                                              19. SECURITY CLASS (ThisReport)
                                                                         21. HO. Of PAGES
to public through  the National Information
Service, (NTIS), Springfield, VA  22161
                                              20. SECURITY CLASS (Thispage)
                                                                         22. PRICE
EPA Form 2220-1 (9-73)
                                                        * U.S. GOVERNMKNT PRINTING OFFICE: 1985-557-295/631

-------