Do not weed. This document
should be retained in the EPA
Region 5 Library Collection.

-------
A NATIONAL PERMITS STRATEGY FOR IMPLEMENTATION OF
    THE RESOURCE CONSERVATION AND RECOVERY ACT
      Permits and State Programs Division
             Office of Solid Waste
      U.S. Environmental Protection Agency
                  August 1984

-------
                             PREFACE








      This  document was prepared  by the Permits Branch  in an effort



 to  improve both the timeliness and the quality of the  permitting of



 hazardous  waste facilities.  The National Permits Strategy reflects



 the high priority given by the Environmental Protection Agency to



 the issuance of permits under the authority of the Resource



 Conservation and Recovery Act (RCRA).



      The National Permits Strategy is organized  into four sections



 for easy review and understanding.  Part I establishes the need for



 this  strategy, and outlines  the problems and issues to which this



 strategy is responding.  Part II summarizes the  key elements of this



 strategy.  Part III outlines four components of  this strategy that



 are designed to accelerate and improve the quality of  RCRA permit



 issuance.  Finally, Part IV outlines a series of management



 initiatives that are to ensure implementation of this  strategy.



     The National Permits Strategy was reviewed  by EPA Regions and



 the States, by EPA Headquarters staff, and by several  public interest



 and trade associations.  Comments were analyzed  and incorporated



 in this document as appropriate.



     Critical elements of this strategy were outlined  both in the



 FY 1985 Agency Operating Guidance and the recently issued FY 1985



RCRA Implementation Plan.   This strategy will be implemented through



the FY 1985 grant work programs,  and will be fully operational by



the end of  the first quarter of FY 1985.

-------
                         TABLE OF CONTENTS
                                                             PAGE
I.   A NATIONAL STRATEGY IS NEEDED TO ENSURE AN
     EFFICIENT, HIGH QUALITY PERMIT PROCESS.                   1

     A. Four Problems Are Addressed By the National
        Permits Strategy.                                      1

     B* The Issuance of Permits is Central to the
        RCRA Program.                                          2

     C. A National Permits Strategy Will Guide
        Regional and State Permitting Activities.              3

     D. EPA Headquarters Activities Support
        Implementation of the National Permits Strategy.       3

     E. The National Permits Strategy; Permitting
        Interim Status Facilities.                             4

II.  KEY ELEMENTS OF THE STRATEGY: AN OVERVIEW.                5

III.  FOUR ELEMENTS OF THE STRATEGY ACCELERATE AND
     IMPROVE PERMITS AND ESTABLISH PRIORITIES.                 6

     A. Accelerated Requests for Permit Applications
        Will Yield Immediate Benefits.                         6

        1.  Priority Attention on Requesting Applications
            from Land Disposal and Incineration Facilities.    7
        2.  A Limited Number of Exceptions May Be Necessary.   9

     B. Priority Permit Program Activities Include Closure
        Plan Approvals.                                       10

     C. Processing and Permitting Land Disposal
        Applications Continues.                               11

     D. Coordinated Compliance Inspections and Permit
        Writing Can Improve Applications.                     11

        1.  Management of Coordinated Site Visits.            14
        2,  Exceptions to Coordinated Site Visits.            15

     D. Earlier and Expanded Public Involvement Activities
        for Selected Facilities.                              15

        1.  Environmentally Significant Facilities are
            Targeted for Public Involvement.                  16
        2.  Meaningful Public Involvement Requires
            Careful Planning.                                 17

-------
                   TABLE OF CONTENTS CONT'D.

                                                             PAGE

IV.  A MANAGEMENT STRATEGY ENSURES IMPLEMENTATION OF
     THE NATIONAL PERMITS STRATEGY.                           19

     A.  The Grant Work Program Implements the National
        Permits Strategy in States.                           19

     B.  State Authorization; Transition Planning Is           21
        Necessary.

        1.   Need for Transition Plans.                         21
        2.   Technical Assistance is Available.                 22

     C.  Resources;  Those Identified Must Be Used.             22

     D.  Regional and State Strategies Provide a Long
        Term Planning Framework.                              23

     E.  Evaluation  of Strategy Implemetationt Mid-course
        Corrections Are  Possible.                              24

-------
I.   A NATIONAL STRATEGY IS NEEDED TO ENSURE  AN  EFFICIENT,  HIGH  QUALITY
    PERMIT PROCESS.


         The purpose of this strategy is to  put in place  an approach

    to RCRA permitting that will achieve maximum environmental  benefits

    in an expeditious manner.   The ultimate  goal of the RCRA Permit

    Program is to make final determinations  on  approximately 1700

    interim status land disposal and incineration facilities by the

    end of Fiscal Year 1988, and to conclude permitting interim

    status storage facilities  in Fiscal Year 1989 (see Attachment A).

    The National Permits Strategy explicitly recognizes,  however, that

    achieving early closure of certain facilities is of sufficient

    benefit such that delays in final permit determinations may be

    acceptable.

         Strategies are outlined to improve  the quality of the  data

    on which permits are issued.  Priorities are outlined that

    emphasize permit actions likely to result in the greatest environ-

    mental improvement.


    A. Four Problems are Addressed by the National Permits Strategy.

         Issuing high quality  land disposal  and incineration permits

    is critical  to the effectiveness of the  RCRA program.  Our  careful

    evaluation of the RCRA permitting process suggests a  number of

    areas in which this process as it is implemented is deficient:

         0  State and Regional EPA offices have not dedicated the

            resources that would allow them  to meet commitments for

            permit issuance.  Resources initially allocated for
                                  -I-

-------
        permit  issuance are diverted to other hazardous waste



        management needs and, in some instances, non-hazardous



        waste needs.




      0  Those facilities that potentially cause the most serious



        environmental problems do not always receive priority



        attention.




      0  Part B permit applications are seriously deficient.




        Extensive additional data gathering is necessary long




        after the permit application has been submitted.



      0  Public involvement is often too formalized and too late in




        the permit writing process to be as effective as it could




        be in improving the permit or in assuring the public.




        Public involvement can significantly delay the permit if




        it does not begin until after the draft permit is written.






B.   The Issuance of Permits is Central to the RCRA Program.




     The permit program is the hub of the variety of hazardous



waste management activities that are conducted under the Resource



Conservation and Recovery Act (RCRA).  A key objective of RCRA is



to ensure that all facilities that manage hazardous waste  (through



land disposal, incineration, treatment and storage) do so  in a




manner that protects public health and the environment.  RCRA per-




mits are the means for implementing the environmentally protective




permit standards in Part 264.  Other activities of the RCRA program




(e.g., inspections, enforcement) facilitate the permit process.




Progress toward issuance of environmentally sound permits  is, there-



fore, a central concern of the RCRA program and a high Agency priority






                                -2-

-------
C.   A National Permits Strategy Will Guide Regional and State
     Permitting Activities.

     The policies articulated  in the National Permits Strategy

will be implemented by EPA Regions and States.  These policies

will drive Regional EPA workload priorities and resource

expenditures in support of the permitting program.  In addition,

these policies will provide a  framework for State activities related

to RCRA permitting.  In this regard, the National Permits Strategy

will be used by EPA in negotiating grant work programs and in

evaluating State activities.


D.   EPA Headquarters Activities Support Implementation of the
     National Permits Strategy.

     Although the National Permits Strategy directs Regional and

State permit programs, EPA Headquarters will undertake a variety of

initiatives designed to support these programs.   Headquarters ini-

tiatives during the remainder of FY 1984,  and throughout FY 1985

will include:

     0   Preparation of documents to clarify implementation of

        specific sections  of the National  Permits Strategy and to

        resolve major policy questions  (e.g., public participation,

        closure/post-closure).

     0   Evaluation of  the  availability,  use,  and distribution of

        permit  processing  guidance.

     0   Development  of  a permit writers  clearinghouse for

        the distribution of  model  permits  and related permit

        documents.
                              -3-

-------
     0  Increased permit writer and applicant training.

     0  Direct permit writing support through Permit Assistance

        Teams (PATs) and technical contractors.

     0  Preparation of educational materials to  support  public

        involvement in the RCRA permit issuance  process.


E.   The National Permits Strategy;  Permitting  Interim Status
     Facilities.

     This document focuses on the current universe of existing

facilities with interim status (as defined by §3005 of RCRA).

Although legislative reauthorization is not reflected in this

strategy, the timetable for permitting set forth here is consistent

with permitting deadlines that are expressed within the pending

RCRA reauthorization bills.  The permitting schedules, ending in

FY 1988 for land disposal facilities and incinerators and in FY

1989 for storage facilities, illustrate that the Agency, like

Congress, considers timely permitting to be of paramount importance

to the success of the RCRA regulatory program as a whole.
                             -4-

-------
II.  KEY ELEMENTS OF THE  STRATEGY;  AN  OVERVIEW.



         The National  Permits  Strategy  sets  in  place  an  action  plan




    that will improve  the quality,  timing, and  management  of  the  permit



    program by:




         °  Accelerating requests  for permit applications  from  interim



            status facilities.   Priority attention  will  be addressed




            to requesting Part B applications from  land  disposal  and




            incineration facilities.  This activity will result in:




            — Immediately directing  the attention  of owners  and




               operators on efforts to  comply with  permit  requirements.



            — Closing interim status facilites that  do  not intend




               to manage hazardous waste under  a RCRA permit; and



            -- Improving our knowledge  of facility  compliance with




               interim status  standards.




         0  Establishing priorities for Final Determination Actions.



            RCRA/CERCLA  sites,  new treatment, and closure  plans are




            given new  priority.




         0  Coordinating compliance inspections and permitting  activities



            to ensure  better quality  applications.




         0  Expanding  public involvement activities for  environmentally



            significant  facilities.  Such activities  will  be encouraged




            to begin as  soon as the permit application is requested.




         0  Implementing a comprehensive management approach.  Grant




            work programs, Regional and State strategies,  dedicated




            resources, performance based grants, and  program evaluation




            are important components  of the  management approach.






                                   -5-

-------
III.  FOUR ELEMENTS OF THE STRATEGY ACCELERATE  AND IMPROVE  PERMITS  AND
     ESTABLISH PRIORITIES.


     A.    Accelerated Requests  for Permit  Applications  Will  Yield
          Immediate Benefits.

          Acceleration of permit application requests  is emphasized

     because of the environmentally beneficial actions  that  such

     acceleration yields.  These actions  include:

          0   Precipitation  of decisions to close  facilities  that will

             have difficulty complying with Part  264 regulations or  that

             do not intend  to upgrade to meet  permit standards;

          0   Application  of Part 264 ground-water protection

             standards through  post-closure permits to  regulated units

             at land disposal facilities which choose  to close; and

          0   Stimulation  of applicant decisions to begin improvements

             necessary to meet  final permit standards.

          The emphasis on accelerated application requests will

     cause a temporary slowing  down of permit  issuance.  Resources

     that  might otherwise be used  for the  processing of permits will  be

     used  to request permit applications and to process closure requests.

     The benefits resulting from the National  Permits  Strategy are the

     closure of facilities  that will not meet  RCRA standards for operating

     facilities,  and the  issuance  of high  quality permits  to facilities

     that  meet federal standards.
                                   -6-

-------
 1.   Priority  Attention  on  Requesting  Applications  From  Land
     Disposal  and  Incineration  Facilities.


      The  National  Permits  Strategy  places  a  high priority on

 requesting  permit  applications  from land disposal  and incineration

 facilities.   As such, permit applications  for all  outstanding  land

 disposal  and  incineration  facilities  will  be requested  before  the

 end  of  Fiscal Year 1985 (see Attachment "A"  for a  more  detailed

 schedule).  The general emphasis upon facilities with land disposal

 units or  incinerators is due primarily to  their higher  potential

 for  environmental  and public health damage through surface and

 ground-water  contamination and  air  pollution.  Generally, storage

 applications  will  be requested  only if they meet the criteria

 described below.   Permit application  requests for  storage facilities

 should  generally resume  in 1986 and 1987 as permit issuance for

 land disposal  and  incinerators  nears  completion.   EPA's recently

 proposed class permit regulation will be in place  by that time and

 will alleviate a large  part of  the  workload associated  with storage

 permits.

     Permit program managers will also need to establish priorities

within  the land disposal, storage,  and incineration categories.

 In addition, there may  be some environmentally significant storage

 facilities whose applications should be requested.  For this reason,

 the priorities for actions called for in the National Permits

Strategy should be based upon facility-specific application of

the following criteria:

-------
     0   Facility  is  a  recipient  of wastes  from a CERCLA site.



     0   Facility  has caused  environmental  damage, violated



        environmental  standards  or disregarded RCRA  regulations



        (i.e.,  has not yet  installed  ground-water monitoring wells),



        as  evidenced by designation as  a  "Significant  Noncomplier"



        or  high priority violator for enforcement action.



     0   Facility  is  suspected source  of ground-water or surface



        water contamination  (e.g., ground-water quality



        assessment has identified presence of hazardous waste



        constituents).



     0   Facility  poses significant environmental  risk,  determined



        on  the basis of:



        —  Proximity to population centers and/or  aquifers  and



           surface waters;



        --  Facility  size;



        --  Amount,  nature and complexity  of waste  handled by facility



           and



        —  Age of facility.





     If a given facility receives  CERCLA  waste,  or is  a known source



of environmental  damage, it should  always receive highest priority.



Facilities  that are  suspected sources of  ground or surface-water



contamination, or pose significant  risks   (based on factors listed



above)  will generally  receive next  priority.  In addition, any one



of the optional factors listed below may  cause  the Region or State
                                -8-

-------
to give a facility highest priority,  if that facility is also a

potential source of ground-water contamination and/or possesses a

significant environmental risk:


     0  Degree of public concern about the facility;

     0  Anticipated financial insolvency or inability to properly

        close and conduct post-closure monitoring and maintenance;

     0  Effect upon competition of permitting a facility or group

        of facilities (e.g., applications for facilities that

        compete with one another in the marketplace should be re-

        quested and processed at the  same time so that there is

        no competitive advantage to a particular facility); and

     0  Number of hazardous waste processes to be covered by the

        permit (a site with a large number of complex processes

        may pose greater risk of spills and other environmental

        damage).


2. A Limited Number of Exceptions to Accelerated Permit Application
   Requests May Be Necessary.


     The structure of certain State programs may impede the

implementation of the National Permits Strategy.  For example,

seventeen States have regulatory "clocks" or requirements that at

least parts of the permit process occur within a fixed period

after the application is filed.  These "clocks" generally start to

run when an interim status facility's Part B application is

complete.  If, in addition, there are a large number of applications

-------
to be requested in relation to available resources, the State may

request an exemption from requesting applications  from all land

disposal and incineration facilities by the close of Fiscal Year

1985.  In no case, however, will such an exemption be extended

beyond the close of Fiscal Year 1986.  Finally, some States will

have already requested all of their land disposal and incineration

applications.  In these States, priorities for additional permit

application requests will be assessed in accordance with the

criteria described in the previous section.


B.   Priority Permit Program Activities Include Closure Plan
     Approvals.

     The National Permits Strategy assigns high priority to the

processing of closure plans for land disposal facilities.  The

following permit program activities for final determinations

are listed in their order of importance; these priorities should

generally be followed in distributing Regional and State permit

resources and in determining commitments:

     0  Emergency Permits;

     0  Facilities receiving wastes from CERCLA sites;

     0  New facility applications for treatment alternatives to

        land disposal;

     0  Closure plan approval;

     0  Existing backlog of partially processed permit applications,

        with emphasis upon those for land  disposal and incineration;

     0  Newly requested land disposal, incineration, and environ-

        mentally significant storage permits;

     0  All remaining permits.


                                -10-

-------
 C.   Processing and  Permitting  Land  Disposal  Applications  Continues.

      To date,  applications  have  been  requested  from  close to  half

 of  the land disposal  facilities  operating  under interim status.

 The remainder  of  the  applications for these  facilities will be

 requested  during  Fiscal  Year 1985  (with  some extensions possible to

 fiscal year 1986).  During  this  period,  processing of backlogged

 applications as well  as  new applications will continue with highest

 priority going toward making final  determinations for those land

 disposal facilities that  receive waste from  CERCLA sites  or

 request closure plan  approval, and  toward  obtaining  the ground-water

 monitoring  information that will be necessary to write final  permits.


 D.    Coordinated  Compliance Inspections And  Permit Writing Can
      Improve Applications.

      Some of the  greatest delays in permit processing come from

 incomplete  Part B applications.  In some cases, the  inadequacies of

 the application are due to  a lack of  understanding by the applicant

 of what is  required.  In other cases, lack of understanding is

 combined with  a poor  compliance  record and a  poor data base on such

 critical areas as ground-water quality.  A linchpin  of the National

 Permit Strategy is a  coordinated enforcement/technical assistance

process designed to improve the  quality of the  Part  B application,

 bring the facility into compliance with Part  265, and address the

facility's  attention  toward compliance with Part 264.

     One of the principal Part B deficiencies is the lack of  adequate

ground-water data to satisfy §270.14(c).   In many instances,  this

inadequacy  is related to the failure of facilities to conduct required
                              -11-

-------
ground-water monitoring during interim status.   In  other cases,  data




which has been developed under interim status  is not  adequate  for



issuing a permit.   In both cases,  facilities have failed to produce




information on aquifer characteristics, existing ground-water  contam-




ination, and other aspects of ground-water protection which EPA needs



in order to write permits.




     Joint site visits by enforcement personnel and permit writers




will be required to improve the technical quality of  the permit



application.  Within 30-90 days of the permit application request,




facilities should receive a joint site visit by enforcement per-




sonnel and the assigned permit writer.  The purpose of this visit




is twofold: to bring interim status facilities into compliance




with interim status standards; and to provide technical and process




assistance to the applicant who must complete a Part B application.




     The joint inspection/permit site visit should be announced  in




the Part B application request letter.  Facilities should be ad-



vised that the permit writer will be available after the  inspection



to discuss the application process and the  information required  for



a complete Part B application.  During the  course of the  site visit,




permit writers should  focus the applicant's attention to  aspects  of



the application that will take the most time and that have  been




found lacking in other Part B submittals.




     If  a violation of the interim status  standards  is  identified




at the time of the joint  inspection/permit  site  visit,  appropriate




enforcement action should be  taken.  Enforcement actions  should
                                -12-

-------
strive to achieve compliance with interim status standards as soon



as possible and no later than the time the Part B application is



due.  If lack of compliance by a facility at the time the appli-



cation is due results in an incomplete application,  a compliance



order (with appropriate penalties) should be issued  consistent



with the Agency's September 9, 1983 late and incomplete Part B



enforcement policy.  The exact nature of the appropriate enforcement



action will depend upon whether previous enforcement actions have



been taken.  In all cases, enforcement action should be carefully



coordinated with permit writers to ensure that information required



for the Part B is developed in a timely manner.



     During the coordinated inspection/site visit, the inspector



and permit writer should work together to conduct a  full compliance



evaluation and permitting inspection including:



     0  An interim status compliance evaluation.  For facilities



        with ground-water monitoring, this means either a compliance



        evaluation inspection or a comprehensive ground-water



        monitoring evaluation, as defined in the RCRA Implementation



        Plan.



     0  A confirmation of the Part A data.



     0  Collection of interim status plans for a thorough desk



        audit following the inspection/site visit.



     0  An assessment of the amount and type of data necessary



        to meet the information requirements of Part 270.14(c).



     The coordinated visit should result in clear guidance to



the facility owner/operator on the type and level of detail of



information needed in the Part B application.





                              -13-

-------
 1.  Management  of  Coordinated  Site Visits.




      Regions and  States are required  to make adjustments to both




 their permit application  request and  inspection schedules to ensure




 the  maximum availability  of resources necessary to  implement this




 policy.   In order to ensure that adequate resources are available




 to  implement this  policy, permit application requests should be




 spread throughout  the year.   Regions  and States must, in particular,



 avoid making all  permit application requests at the end of the



 fiscal year.




      Phase I authorized States are responsible for  conducting inspec-



 tions, but not for permit issuance.   These States should coordinate




 Interim Status inspections with the EPA Regional Offices' request for




 a Part B application.  Accordingly, State grant agreements should



 require that:




      0  Interim status inspections for land disposal and incineration




        facilities (and those storage facilities identified as prob-



        lem facilities requiring immediate attention) be conducted



        within 30-90 days of  the Part B request;



      0  EPA permit writers visit the  facility at the time of this



        inspection; and




      0  Thorough desk reviews of Interim Status plans and documents




        be conducted and review comments shared with EPA permit



        writers.




     Phase II authorized States and States with final authorization




are responsible for inspections, permit issuance, and the coordinatior



of the two.  In these States,  grant agreements should reflect the




implementation of this policy of early, coordinated facility visits.






                                -14-

-------
 2.   Exceptions  to  Coordinated  Site Visits

      When  a  complete  interim status  inspection has been conducted

 recently at  a  facility,  or when  pending  interim status enforcement

 actions dictate  an inspection  schedule different  from the policy

 outlined here,  the permit writer may, after discussion with  the

 inspector  and  review  of  the inspection reports, conduct the  site

 visit alone.   In all  cases, this visit should occur no later than

 90 days after  the  Part B application request.


 D.    Earlier and Expanded Public Involvement Activities For
      Selected Facilities.

      The ultimate  objective of public involvement is to improve the

 quality of environmental decision-making by ensuring that all

 relevant issues  are addressed  as soon as possible.  Effective

 public involvement must  take place early enough in the decision-

 making process to  ensure that  concerns made by the public can be

 addressed  in the draft permit, and that public involvement is a

 positive,  not disruptive, force.  In order for public involvement to

 be effective and to meet the ultimate objective of improving the

 quality of the permit, the public must be well informed as to the

 scope of decisions addressed by  the permitting agency, the technical

 issues involved, and  the views of all parties to  the decision-

making process.

     The public may believe that the opportunity  for their involve-

ment at the time of the public hearing is too late in the process.

Data has been gathered, the draft permit is written, and preliminary

decisions have been made.  If  the public has not been actively
                                -15-

-------
involved before this time,  they may not feel  prepared  to present

well thought-out concerns that are within the purview  of the

permitting agency.

     Finally, the major concerns of the public are often addressed

to a variety of issues (e.g.,  siting,  transportation)  that are not

within the purview or jurisdiction of  the permitting agency.  These

same issues are, however, important public concerns.  Controversy

surrounding these issues may impede progress  in issuing final

permits.  Involvement of both the applicant and other  responsible

agencies (e.g., siting boards, land use commissions) in public

involvement activities may help clarify and resolve those issues

that affect the permit but cannot be directly addressed by the

RCRA permit process.


1.  Environmentally Significant Facilities are Targeted for
    Public Involvement.


     Not all kinds of facilities will require the same  level of

public involvement.  Determining the appropriate level  of public

involvement for a particular facility requires thoughtful planning.

     EPA Regions and authorized States will plan the appropriate

level and type of public involvement for each environmentally  signif-

icant land disposal and  incineration facility for which an  application

will be or has been requested.

     In identifying these environmentally  significant  facilities,  the

Region and the State will consider  criteria  on pages 7-9  of  this

document.  In addition,  the possible contribution  to be made by
                                -16-

-------
                         I





the public in improving the quality of the permit should be



considered.



     Public involvement plans for those environmentally significant



facilities whose applications have already been requested should



take into account the stage of the facility in the permit application



process and the level of public interest addressed to date.  Public



involvement planning for these facilities should be conducted in



stages over the course of the year, to ensure even distribution



of this workload.





2.  Meaningful Public Involvement Requires Careful Planning.






      For each of the environmentally significant facilities



identified, each Region or authorized State will develop an



expanded public involvement plan.  Each expanded public involvement



plan will include a field assessment of community interests and



concerns and appropriate public involvement techniques.  The



field assessment may take place at the  time of the coordinated



inspector/permit writer visit.  Expanded public  involvement



plans should be designed with the  following in mind:



     0  The plan should be tailored to  the distinctive  and  individual



        characteristics of the site and  its adjoining  community.



     0  Issues and interests that  are outside  the scope of  the  RCRA



        permit process but that affect  the permit should be  identified,



     0  The plan should address ways  to  involve  decision-makers and



        the applicant  in public  involvement activities  outside



        the scope of the permit  (e.g. local siting boards).





                                -17-

-------
0  In most cases,  small scale,  informal,  communications




   techniques should be used to facilitate community involve-



   ment .




0  The plan should include,  where appropriate,  measures  to




   actively reach  out to the public to engage their interest,




   and to provide  the back-up educational material that  support




   informed public involvement.




0  Some of the expanded public  involvement activities should




   take place before the Part B application is  submitted.



0  The remainder of the expanded activities should take  place




   between the time of permit application and completion of




   the draft permit.
                           -18-

-------
IV.  A MANAGEMENT STRATEGY ENSURES  IMPLEMENTATION  OF  THE  NATIONAL
    PERMITS STRATEGY.
       Implementing the National  Permits  Strategy  requires  a  manage-

  ment framework  that  will  provide  for  clear  objectives,  and  continuing

  evaluation and  adjustment.   The major elements of  this  management

  framework  are:

       0   Use of  the grant  work program to  implement the  Strategy

          in FY 1985;

       0   Regional  and State  strategies that  demonstrate  the  manner

          in which  the National Permits Strategy will  be  implemented

          over a  three to five year time  frame;

       0   Better  coordination  with  States to  ensure  that  the  transfer

          of authorization  for RCRA program operation  to  the  States

          or from States whose programs revert to  EPA  does  not disrupt

          the schedules  called for  in the Strategy;

       0   Procedures to  ensure that  resources identified  for  permit-

          ting are  used  in  the permit program; and

       0   Mid-course evaluation of  the  strategy.


 A.    The Grant  Work  Program  Implements the  National  Permits Strategy
       In  States.*

       The grant  work  program  contains  the quarterly and  annual State

 commitments  to  implement  the National Permits Strategy.   The Regions

 will  negotiate  commitments with States, based on targets  given by

 Headquarters and an  analysis of the capability of  States  to achieve

 targets.   Negotiated commitments should be  realistic and  achievable.


 *Work program commitments outlined here are also found  in the RCRA
  Implementation Plan.


                               -19-

-------
The grant work program should include:




     0  Quarterly Commitments,




        -  To request a specific number of  permit applications.




           For permit processing milestones (including public



           notices and final determinations)  consistent with the




           schedule found in Table II,  Attachment A.



     0  A commitment to conduct coordinated inspection and permit




        writer visits within 90 days of the permit application




        request.




     0  A commitment to develop public participation plans for




        environmentally significant facilities.




     0  A commitment by the State to complete a multi-year permit




        strategy for submittal to the EPA Regional office before




        the end of the first quarter of FY 1985.  Any deviations




        from the policies in this National Permit Strategy




        should be outlined in the document, including:



        -  different criteria used to define high priority



           facilities for permit processing;




           unique State pricing factors that affect the adequacy



           of resources for achieving the goals of the National




           Permits Strategy;




     0  Specific actions for orderly transfer of  the permit



        program upon State authorization or upon  program reversion,




     Performance-based grants will be used to ensure that State




programs support the achievement of permit commitments  (see  the



RCRA Implementation Plan for FY 1985).






                                -20-

-------
B.    State Authorization:  Transition Planning is Necessary.






1.   Need for Transition Plans.



     There is a significant potential for delay in permit issuance



as States achieve authorization and as the responsibility for issu-



ance of permits is transferred from the Regions to the States.



To ensure that the transfer of permit processing takes place in



an orderly manner that minimizes disruption to the permit



issuance process, the EPA Regional Offices must plan the manner



in which the transfer of the permit program to the States should



proceed.  To the degree allowable by Federal and State law, the



Regions and States should develop plans to coordinate and not



duplicate permitting activities.  These transition plans should be



described in the Memorandum of Agreement and implemented through



the grant work program (see Program Implementation Guidance 82-5



for further guidance in this area).  At a minimum, such plans



should include:





      0  Agreement by the State, if allowed by State



         authorities, to request Part B applications at



         the same time EPA Regional offices are making such



         requests;



      0  Agreement by the State to coordinate processing of such



         applications with EPA, to the degree allowed by existing



         State authorities;



      0  Agreement by the State that the permit applications will



         be requested beginning immediately after State Authoriza-



         tion if existing State authorities do not allow the State






                                -21-

-------
         to request and begin processing applications concurrently



         with the EPA Region;




      0  Agreement by the State that it will coordinate its efforts



         with EPA to build upon the work already accomplished by




         the Regional staff.






2.  Technical Assistance is Available.




     A key element of the orderly transfer of the permitting process



to the States will be a period of technical assistance provided by




the Regional Office permit writers, contractors, and Headquarters



Permit Assistance Teams.  The level of  this assistance will be



determined during the State Capability  Assessment prior to final




authorization.   At the request of a State, EPA permit writers may




work with State permit writers to conduct site visits, to review




the permit applications, and to assist  in the writing of permits.




     The anticipated level of requests  from the States for tech-




nical assistance by Regional permit writers must be outlined in



Regional and State strategies.  These documents should spell out



both the anticipated level of resources and the length of time that




these resources will be necessary.






C.   Resources;  Those Identified Must  be Used.




     The annual RCRA Implementation Plan suggests that 50 to 60




percent of RCRA grant funds  (after State program development) should




be devoted to permitting.  In some cases, there has been a diversion




of these funds to other activities.






                               -22-

-------
      The  implementation  of  the National Permits Strategy  is one of

 the  highest  priorities of the Agency.  The work program developed

 as part of  the  annual State grant process must be designed to ensure

 implementation  of  the key components of this strategy.  Resource

 levels associated  with commitments must be clearly  identified and

 demonstrate  substantial  adherence to the schedules  and objectives

 set  forth in this  document.

      EPA Regional  Offices will monitor progress toward goals, ensure

 that  resources  are appropriately directed toward priority permit

 activities,  and  identify needs for technical assistance.  To

 ensure that  any  problems encountered in achieving the objectives

 and  schedules established by the Strategy are revealed in a timely

 manner, State grant work program progress will be reviewed by the

 EPA Regions  on  a monthly basis.

 D.    Regional and  State Strategies Provide a Long Term Planning
      Framework.

      During  the  first quarter of FY 1985, EPA Regions and authorized

 States will  prepare multi-year Strategies to demonstrate how the

 national schedule, priorities, and policies will be implemented

 in each Region and State.   The basis upon which these strategies

will  be developed are the annual and quarterly commitments made

 through the  grant work programs (or in the case where the Region

 is operating the program, the Regional commitments).  The multi-year

strategies will establish the manner in which the State and Regional

permitting programs will achieve the long term objectives embodied

in the National Permits Strategy.   These multi-year strategies


                              -23-

-------
will address a three to five year planning framework and will

describe:

     0 Scheduled milestones for final determinations for permit

       issuance and closures that will lead to achievement of the

       objectives of the National Permits Strategy.

     0 Realistic commitments that will lead to achieving the above

       schedule.

     0 Any necessary staff and resource development plans that

       can ensure the Region or State's ability to meet the overall

       timetable of the National Permits Strategy.

     0 Deviations from the objectives of the National Permits

       Strategy, including deviations from the final determinations

       schedule outlined in Table II, Attachment A.

     0 Agreements between the EPA Region and the State concerning

       technical assistance support that will be provided by the

       Region to the State.

     These multi-year strategies will be prepared by every State

that is authorized or expects to be authorized before the end  of

FY  1985, and by EPA Regions for all other  States.   Regions

should submit individual strategies for their respective  States

to  the Office of Solid Waste by December  31,  1984.


E.   Evaluation of Strategy Implementation;   Mid-Course Corrections
     Are Possible.

     The National Permits Strategy  is an  ambitious  effort to speed

up  the progress toward environmental  protection  that  is promised  by

the final permitting of hazardous waste  facilities.   In recogni-

tion, however,  that progress may not  be  as smooth or  as rapid  as


                                 -24-

-------
desired, careful evaluation of achievements is an integral part




of the National Permits Strategy.



     In March of 1985, the Office of Solid Waste will conduct a




preliminary examination of progress made by the Regions and the




States in achieving the objectives of this strategy.   This




examination will address, to the extent data is available, the




following elements:




     0  How many facility closures have occurred as a result




        of the accelerated permit application requests and



        examples of environmental benefits realized from these



        closures;




     0  How many withdrawals of protective filers have occurred;




     0  Whether coordinated inspections have improved the quality




        of Part B applications;




     0  The nature and kind of public participation plans that




        have been written as a result of the strategy.  To the




        degree that plans have been implemented, the evaluation




        will also try to assess the impact of that implementation.



     0  Progress made and projected to be made on requesting



        permit applications from remaining land disposal and



        incineration facilities in interim status;




     0  The nature of special exceptions requested by the Regions



        and the States;




     0  The impact of State authorization on the implementation of




        the Strategy;






                               -25-

-------
     0  To the extent commitments are not being met, resources




        being devoted to the implementation of the Strategy by the



        Regions and the States; and




     0  Identification of special technical assistance needs that



        should be supplied by EPA Regions, Headquarters, or




        contractors to enhance the State program.




     0  Impacts of the National Permits Strategy on other facilities




        whose permits had been previously called in.




     0  Effects on the permit program and the National Permits




        Strategy of RCRA reauthorization and regulatory changes.




     The results of the preliminary evaluation will be considered




prior to making the final decision on an appropriate national




strategy for requesting permit applications from the remaining



interim status facilities.




     An additional evaluation of progress and problems with imple-



menting the National Permits Strategy will be carried out in the



Fall of 1985.  This more comprehensive qualitative evaluation




will address the above issues as well as:



     0  The impact of the accelerated application requests




        on permit issuance, especially for land disposal and



        incineration facilities;




     0  The nature and impact of public involvement activities




        on the permits program; and




     0  Additional progress toward improving Part B applications




        through the joint scheduling of enforcement inspections




        and permit writing  visits.






                              -26-

-------
                   ATTACHMENT A:   STATUS  AND  SCHEDULES
                                  Table  I
                    STATUS OF FINAL RCRA  PERMIT ISSUANCE
Type of   No. of      Applications  Withdrawals/    Applications     Permits
Facility  Facilities  Requested       Closures        Received       Issued
          (estimated) (% total      (% applications               (% applications
                      facilities)     requested)                     received)
Land
Disposal
Incin-
erator
Storage
1500
230
3950
38%
79%
51%
22%
33%
50%
252
118
876
2%
8%
21%
L.D.
Inc.
St.
L.D.
Inc.
St.
               82
              26%
              20%
               4%
               5%
20%
29%
25%
 2%
 9%
13%
                                  Table  II

                      PROJECTED SCHEDULE OF ACTIVITIES
                       RCRA NATIONAL PERMITS  STRATEGY
Requests for Applications

  84    85_   .   86^      81_

       40%
        9%       -       -
               25%     25%

  Final Determinations
40%
36%
 5%
 5%
32%
18%
                          14%
                          16%
               35%
               27%
               15%
30%
12%
25%
                                    83
                                    89
14%

18%
                                                       2%

-------