NIB FBW-201845
    TECHNICAL REPORT

DESIGN AND EVALUATION OF
       TAILINGS DAMS
             August 1994
       U.S. Environmental Protection Agency
           Office of Solid Waste
           Special Waste Branch
            401 M Street, SW
           Washington. DC 20460

-------
                                           Design and Evaluation of Tailings Dams
         DISCLAIMER AND ACKNOWLEDGEMENTS
This document was prepared by the U.S. Environmental Protection
Agency (EPA).  The mention of company or product names is not to
be considered an endorsement by the U.S. Government or the EPA.

Sections of this document rely heavily on Steven G. Vick's Planning,
Design, and Analysis of Tailings Dams (BiTech Publishers Ltd. 1990).
This is particularly true of certain concepts and organizational
emphases, as well as many of the tables and figures. In some cases,
this document presents a digest of Vick's overall approach to tailings
dam planning and design. Permission to use Planning, Design, and
Analysis of Tailings Dams as a major source was provided by Mr.
Vick, who is not responsible for any errors of omission or
interpretation in the present document.

-------
                                                              Design and Evaluation of Tailings Dams
                                        TABLE OF CONTENTS
         1.    INTRODUCTION  	   1

         2.    OVERVIEW OF TAILINGS DISPOSAL	  4

              2.1 Methods for Tailings Disposal 	  5
              2.2 Types of Impoundments  	  6
                 2.2.1    Valley Impoundments  	  8
                 2.2.2    Ring-Dike Impoundments	   13
                 2.2.3    In-Pit Impoundments	   14
                 2.2.4    Specially Dug Pit Impoundment Design	   15

         3.    TAILINGS IMPOUNDMENT DESIGN	   16

              3.1 Basic Design Concepts	   16
              3.2 Design Variables	   18
                 3.2.1    Tailings-Specific Factors	   18
                 3.2.2    Site-Specific Factors	   19

         4.    EMBANKMENT CONSTRUCTION, STABILITY, AND FAILURE  	   24
j
%              4.1 Embankment Construction	   24
1              4.2 Construction Methods  	   25
                 4.2.1    Construction Using Tailings Material  	   25
'                 4.2.2    Upstream Method	   26
^                 4.2.3    Downstream Method	   28
^                4.2.4    Centerline Method  	   30
                 4.2.5    Embankments Constructed Using Alternative Materials  	   31
-v             4.3 Tailings Deposition	   32
 '                4.3.1    Single Point Discharge	   32
t^                4.3.2    Spigotting	   33
                 4.3.3    Cycloning	   33
              4.4 Stability Analysis  	   35
                 4.4.1    Flow Net Analysis	   36
              4.5 Failure Modes  	   37
                 4.5.1    Rotational Sliding	   38
                 4.5.2    Foundation Failure	   38
                 4.5.3    Overtopping  	   39
                 4.5.4    Erosion	   39
                 4.5.5    Piping	   39
                 4.5.6    Liquefaction	   39
              4.6 Performance Monitoring	   40

         5.    WATER CONTROL AND MANAGEMENT 	   4)

              5.1 Surface Water  	     41
                 5.1.1    Surface Water Evaluation	     43
                 5.1.2    Surface Water Controls  	     45
              5.2 Tailings Seepage	     4*
                 5.2.1    Seepage Flow (Direction and Quantity)  	     4"*
         	.     u s  Pnwirnnmental Protection Agency

                                                         Region 5 Library (PL-12J)
                                                   "     77 West Jackson Boulevard, 12th
                                                         Chicago, IL 60604-3590

-------
                                                      Design and Evaluation of Tailings Dams
         5.2.2    Seepage Quality	   47
         5.2.3    Seepage Control	   48
     5.3 Tailings Water Treatment  	   52

6.   CASE STUDY:  STILLWATER MINING COMPANY TAILINGS IMPOUNDMENT .  .   53

     6.1 Site Evaluation, Field Exploration and Laboratory Tests	   54
         6.1.1    Site Evaluation  	   54
         6.1.2    Field Exploration	   54
         6.1.3    Laboratory Tests  	   55
     6.2 Office Evaluations	   56
         6.2.1    Hydrology Evaluation	   56
     6.3 Tailings Impoundment Design  	   58

7.   REFERENCES  	   62

APPENDIX A    COMMENTS ON THE DRAFT "DESIGN AND EVALUATION OF
                 TAILINGS  DAMS" AND EPA RESPONSES	   66
                                   LIST OF TABLES

                                                                                  Page

Table 1.    Comparison of Embankment Types	   27
Table 2.    Stillwater Mining Company Calculated Design Floods	   57
                                  LIST OF FIGURES

                                                                                  Page

Figure 1.    Water-Retention Type Dam for Tailings Disposal	  7
Figure 2.    Embankment Types: (a) Upstream, (b) Centerline, (c) Downstream or Water
            Retention Type	  8
Figure 3.    Single (a) and Multiple (b) Cross-Valley Impoundments	   10
Figure 4.    Single (a) and Multiple (b) Side-Hill Impoundments  	   11
Figure 5.    Single (a) and Multiple (b) Valley-Bottom Impoundments	   11
Figure 6.    Single (a) and Segmented (b) Ring-Dike Impoundment Configurations	   13
Figure 7.    Phreatic Surface Through a Tailings Impoundment  	   17
Figure 8.    Upstream Tailings Embankment Construction  	   28
Figure 9.    Downstream Embankment Construction	   29
Figure 10.   Centerline Embankment Construction  	   31
Figure 11.   Examples of Tailings Embankment Flow Nets	   38
Figure 12.   Stillwater Mining Company: Liner, Sump, and Instrumentation Details	   59
Figure 13.   Stillwater Mining Company: Tailings Impoundment Stage I Sections  	   60
                                           in

-------
                                                           Design and Evaluation of Tailings Dams
                       DESIGN AND EVALUATION OF TAILINGS DAMS

1.     INTRODUCTION

In order to obtain the metals and other minerals needed for industrial processes, fertilizers, homes,
cars, and other consumer products, large quantities of rock are mined, crushed, pulverized, and
processed to recover metal and other mineral values.  A fine grind is often necessary to release metals
and minerals, so the mining industry produces enormous quantities of fine rock particles, in sizes
ranging from sand-sized down to as low as a few microns. These fine-grained wastes are known as
"tailings."

Until recent decades, the majority of mines were small underground operations with correspondingly
modest requirements for tailings disposal.  Since that time, due to increasing demand, it has become
economical to mine large lower-grade deposits by utilizing advances made by mining equipment
manufacturers and developments in mining and milling technology.  This has greatly increased the
amount of tailings  and other wastes generated by individual mining projects and by the mining
industry as a whole.

There are approximately 1,000 active metal mines in  the United States (Randol, 1993) Many of these
have at least one tailings impoundment and often several impoundments  grouped together in cells.
EPA estimates that there may be several thousand tailings impoundments associated with active non-
coal mining, and tens of thousands of inactive or abandoned impoundments.

By far the larger proportion of ore mined in most industry sectors ultimately becomes tailings that
must be disposed of. In the gold industry, for example, only a few hundredths of an ounce of gold
may be produced for every ton of dry tailings generated.  Similarly, the copper industry and others
typically mine relatively low-grade ores that contain less than a few percent of metal values; the
residue becomes tailings. Thus, tailings disposal is a significant part of the overall mining and
milling operation at most hardrock mining projects.  There are several methods used for tailings
disposal.   These include disposal of dry or thickened  tailings in impoundments or free-standing piles,
backfilling underground mine workings and open-pits, subaqueous disposal, and the most common
method, the disposal of tailings slurry in impoundments.  Modern tailings impoundments are
engineered structures for permanently disposing of the fine-grained waste from mining and milling
operations.  At some projects, tailings embankments reach several hundred feet in height and the
impoundments cover several square miles.

Historically, tailings were disposed of where convenient and most cost-effective, often in flowing
water or directly into drainages.  As  local concerns arose about sedimentation in downstream
watercourses, water use, and other issues, mining operations began impounding tailings behind

-------
                                                            Design and Evaluation of Tailings Dams
earthen dams, which were often constructed of tailings and other waste materials.  The impoundments
served the dual purpose of containing the tailings and, particularly in the arid west, allowing the re-
use of scarce water.

More recently, concerns have been raised about the stability and environmental performance of
tailings dams and impoundments.  Stability concerns are raised in part by the use of tailings material
in tailings dams/embankments;  to mitigate these  concerns, such embankments often rely on a certain
amount of controlled seepage to enhance stability, which in turn affects environmental performance.
Ritcey (1989) has speculated that the need for sound impoundments in the uranium industry
"probably" accounts for much of the recent attention paid to  impoundment design in other types of
facilities.  Perhaps triggered by the initial attention to uranium impoundments, the increasing concern
for environmental performance has led to better engineering design of tailings dams in other mining
industry sectors, for both stability  and environmental performance. For instance, experience gained
with leach pad liners is being transferred to  linings for tailings ponds, and the use of synthetic lining
materials is growing (although use of liners  is  still far from being the industry norm).  In addition,
the use of cyanide and other toxic  reagents in mill processes has raised special concerns for some
tailings and is leading to increased-treatment prior to disposal as well as increased attention to
containment.  Finally,  continuing concerns over  acid mine drainage is resulting hi a growing body of
research and emerging concepts of long-term control or mitigation.

Inactive tailings impoundments also are receiving more attention due to the long-term effects of
windblown dispersal, ground water contamination, and acid drainage.  In many cases, the costs of
remediation can be considerable, exceeding the costs of original design and operation of the tailings
impoundment.

While this report discusses general features of tailings dams  and impoundments, actual designs for
tailings disposal are highly site-specific.  Design depends on the quantity and the individual
characteristics of the tailings produced by the mining and milling  operation, as well as the climatic,
topographic, geologic, hydrogeologic and geotechnical characteristics of the disposal site,  and  on
regulatory requirements related to dam safety and to environmental performance. What may work for
one type of tailings may not work for another type, and may not work for the same tailings at
different sites. Hence each situation requires its own design process. The estimated quantity of
tailings to be disposed of is particularly important given the evolving nature of most mining projects.
Tailings quantity estimates are based on estimated reserves that change continuously as mine
development progresses.  Accordingly, the final size and design of tailings impoundments can differ
substantially from initial projections. This presents major challenges to Federal land managers and
State permit writers, who are faced with reviewing and overseeing tailings impoundment planning,
design, and performance, and to the general public, who may ultimately pay for miscalculations
resulting in environmental damages.

-------
                                                            Design and Evaluation of Tailings Dams
The purpose of this report is to provide an introduction for Federal land managers, permit writers,
and the general public to the subject of tailings dams and impoundments, particularly with regard to
their engineering features and their ability to mitigate or minimize adverse effects to the environment.
The report is based on the current literature on tailings impoundment engineering. While broad in
scope, the report is necessarily limited in depth:  a comprehensive guide to the design and evaluation
of tailings impoundments would incorporate most of the  materials in a number of examinations of
tailings dam engineering and environmental performance, including those  in texts by Vick (1990),
Ritcey (1989), and CANMET (1977), among others.

It should also be noted that tailings dam engineering is continually evolving.  The relatively recent
emphasis on environmental performance is leading to many changes in the field, many of which are
as yet not fully tested.  Vick (1990) may be the most recent and most comprehensive examination of
the topics covered by this report.  Consequently, certain sections of this report rely heavily on Vick's
approach.

The next section of this  report provides an overview of the various methods used to dispose of mine
tailings and the types of impoundments that are used.  Section 3 describes the basic concepts used in
the design of impoundments, including a number of site-specific variables of concern.  Section 4
discusses tailings embankment and stability, while Section  S briefly discusses water management in
tailings impoundments.  A case study on a lined tailings  impoundment is presented in Section 6.
Finally, Section 7 lists all references cited in the text.

-------
                                                           Design and Evaluation of Tailings Dams
2.     OVERVIEW OF TAILINGS DISPOSAL

The ultimate purpose of a tailings impoundment is to contain fine-grained tailings, often with a
secondary or co-purpose of conserving water for use in the mine and mill. This has to be
accomplished in a cost-effective manner that provides for long-term stability of the embankment
structure and the impounded tailings and the long-term protection of the environment.  In the process
of designing any tailings embankment and impoundment, these three interests, cost, stability, and
environmental performance, must be balanced,  with situation-specific conditions establishing the
balance at each stage of the process.

Impoundment of slurry tailings is the most common method of disposal and are the main focus of this
report. Impoundments are favored because, among other things, they are "economically  attractive
and relatively easy to operate" (Environment Canada 1987). Tailings impoundments can be and are
designed to perform a number of functions, including treatment functions. These include
(Environment Canada 1987):

       •  Removal of suspended solids by sedimentation
                                *'
                               *,
       •  Precipitation of heavy metals as hydroxides

       •  Permanent containment of settled tailings

       •  Equalization of wastewater quality

       •  Stabilization of some oxidizable constituents (e.g., thiosalts, cyanides, flotation reagents)

       •  Storage and stabilization of process recycle water

       •  Incidental flow balancing of storm water flows.

There'are, however,  a number of disadvantages to tailings impoundments requiring attention in
design, including (Environment Canada 1987):

       •  Difficulty hi achieving good flow  distribution

       •  Difficulty in segregating drainage from uncontaminated areas

       •  Difficulty hi reclamation, particularly with acid-generating tailings,  because of the large
          surface  area and materials characteristics

       •  Inconsistent treatment performance due to seasonal variations in bio-oxidation efficiency

-------
                                                             Design and Evaluation of Tailings Dams
         •  Costly and difficult collection and treatment of seepage through impoundment structures

         •  Potentially serious wind dispersion of fine materials unless the surface is stabilized by
            revegetation, chemical binders, or rock cover.

 2.1     Methods for Tailings Disposal

 Because mine tailings produced by the mill are usually hi slurry form, disposal of slurry tailings in
 impoundments made of local materials is the most common and economical method of disposal.
 There are four main types of slurry impoundment layouts; valley impoundments, ring dikes, in-pit
 impoundments, and specially-dug pits (Ritcey 1989).  These impoundment configurations are
 explained hi more detail below, with major emphasis on valley impoundments, as they are the most
 common.  Before describing impoundments, several other methods of tailings disposed are briefly
 described below.

 In some cases, tailings are dewatered (thickened to 60 percent pulp density or more) or dried (to a
 moisture content of 25 percent or below) prior to disposal. The efficiency and applicability of using
 thickened or dry tailings depends on the ore grind and concentrations of gypsum and clay as well as
 the availability of alternative metnbds.  Except under special circumstances, these methods may  be
 prohibitively expensive due to additional equipment and energy costs. However, the advantages
 include minimizing  seepage  volumes and land needed for an impoundment, and simultaneous tailings
 deposition and reclamation.  (Vick 1990)

 Slurry tailings are sometimes disposed in underground mines as backfill to provide ground or wall
 support. This decreases the above-ground surface disturbance and can stabilize mined-out areas. For
 stability reasons, underground backfilling requires tailings that have a high permeability, low
 compressibility,  and the ability to rapidly dewater (i.e., a large sand fraction).  As a result, only the
 sand fraction of  whole tailings is generally used as backfill.  Whole tailings may be cycloned to
 separate out the  coarse sand fraction for backfilling, leaving only the slimes to be disposed hi an
 impoundment. To increase structural competence, cement may be added to the sand fraction before
 backfilling (Environment Canada 1987).

 Open-pit backfilling is also practiced, where tailings are deposited into abandoned pits or portions of
 active pits.  The Pinto Valley tailings reprocessing operation, located hi Arizona, uses this method to
. dispose of copper tailings. In active pits, embankments may be necessary to keep the tailings from
 the active area.  However, since seepage from the tailings can adversely affect the stability of the pit
 walls or embankments, it is  unusual to see disposal hi active pits. Williams (1979), for  example,
 discusses a failure due to pore water pressure hi the floor of a pit hi Australia.  Ritcey (1989) notes
 that the hydrogeological parameters affecting the migration of seepage and contaminants  are poorly
 understood, so tailings with  toxic contaminants or reactive tailings may be poor candidates for this
 type of impoundment.  The U.S. Bureau of Mines points out that other limitations for using active

-------
                                                           Design and Evaluation of Tailings Dams
open pits for tailings disposal are loss of the pit areas for future resources, and subsequent mine
operating and design restrictions to which mine operators would be subjected.

Subaqueous disposal in a deep lake or ocean is also a possible disposal method.  Underwater disposal
may prevent the oxidation of sulfide minerals  in tailings, thus inhibiting acid generation.  Subaqueous
disposal has recently been practiced by eight mines in Canada, with three still active as of 1990
(Environment Canada 1992). Subaqueous disposal is used in areas with high precipitation, steep
terrain, or high seismicity or, in Canada, where its use predated current regulations.  This method is
also limited to coarse tailings that can settle quickly.  CANMET (Canadian Centre for Mineral and
Energy Technology) completed a bench-scale  16-year simulation of deep-lake disposal using Ottawa
River water (Ritcey and Silver 1987). They found that the tailings had little effect on pH when using
ores with a low sulfide content.  Ripley, et al. (1978), found that  the tailings can cover large areas on
the ocean or lake floor and cause turbidity problems if the disposal practice is not designed correctly.
There is little data on the long-term effect of subaqueous disposal (Environment Canada 1987),
although it is being studied in Canada and peer reviewed by CANMET (CANMET 1993).

A variation on subaqueous disposal in the ocean or lakes would be permanent immersion of tailings in
                               t,
a pit or impoundment.  This could present many of the same advantages of underwater disposal (i.e.,
reduced oxidation of sulfide minerals) but also would require long-term attention to ensure constant
water levels and possibly monitoring for potential ground water impacts.

2.2    Types of Impoundments

There are two basic types of structures used to retain tailings in impoundments, the raised
embankment and the retention dam.  Because  raised embankments are much more common than
retention dams, they are emphasized  in this report.  Either type of structure, raised embankments or
retention dams, can be used to form different  types or configurations of tailings impoundments.  The
four main types of impoundments include the  Ring-Dike, In-Pit, Specially Dug Pit, and variations of
the Valley design.  The design choice is primarily dependent upon natural topography, site conditions,
and economic factors.  Most tailings  dams in  operation today are a form of the Valley design.
Because costs are often directly related to the  amount of fill material used in the dam or embankment
(i.e., its size), major savings can be realized by minimizing the size of the dam and by maximizing
the use of local materials, particularly the tailings themselves.

Retention dams are constructed at full height at the beginning of the disposal whereas raised
embankments are constructed in phases as the need for additional disposal capacity arises. Raised
embankments begin with a starter dike with more height added to the embankment as the volume of
tailings increases in the impoundment.

-------
                                                           Design and Evaluation of Tailings Dams
Tailings retention dams (Figure 1) are similar to water retention dams in regard to soil properties,
surface water and ground water controls, and stability considerations. They are suitable for any type
of tailings and deposition method.
                                                    Impervious core
                                                       Filter
                                                         Drainage zone
                  Figure 1,  Water-Retention Type Dam for Tailings Disposal

(Source: Vick 1990)

Raised embankments can be constructed using upstream, downstream, or centerline methods, which
are explained in more detail in a later section (see Figure 2).  Each of the structures in Figure 2, for
instance, is constructed in four successive lifts, with constructing material and fill capacity increasing
incrementally with each successive lift. They have a lower initial capital cost than retention dams
because fill material and placement costs are phased over the life of the impoundment.  The choices
available for construction material are increased because of the smaller quantities needed at any one
time. For example, retention dams generally use natural soil whereas raised embankments  can use
natural soil, tailings, and waste rock in any combination.  (Vick 1990)

Finally, the phased nature of raised embankments makes it possible to attempt to address problems
that may arise during the life of a tailings impoundment.  For example, at the Rain facility  in Nevada,
unplanned seepage under and through the base of the tailings embankment made design changes
necessary.  The fact that this was a raised embankment made it possible to attempt engineered
solutions to the problem as the dam was enlarged and raised during later phases of construction, and
this could be accomplished without taking the impoundment out of service and without moving
enormous quantities of fill material or impounded tailings.

-------
                                                           Design and Evaluation of Tailings Dams
                                          T
                                          i
                                              (j)
                                      «!"«,- H,
                                              (c)
        Figure 2. Embankment Types:  (a) Upstream, (b) Centeiiine, (c) Downstream or
                                     Water Retention Type
(Source:  Vick 1990)
2.2.1  Valley Impoundments

Other things being equal, it is economically advantageous to use natural depressions to contain
tailings.  Among other advantages are reduced dam size, since the sides of the valley or other
depression serve to contain tailings. In addition, tailings in valleys or other natural depressions
present less relief for air dispersion of tailings material.  As a result, valley impoundments (and
variations) are the most commonly used.  Valley-type impoundments can be constructed singly, in
which the tailings are contained behind a single dam or embankment; or in multiple form, in which
case a series of embankments contain the tailings in connected "stair-step" impoundments.

There are several variations of valley-type impoundments.  The Cross-Valley design is frequently
used because it can be applied to almost any topographical depression in either single or multiple
form. Laid out similarly to a conventional water-storage dam, the dam is constructed connecting two
valley walls,  confining the tailings in the natural  valley topography.  This configuration requires the
least fill material  and consequently is favored for economic reasons.  The impoundment is best located
near the head of the drainage basin to minimize flood inflows.  Side hill diversion ditches may be

-------
                                                            Design and Evaluation of Tailings Dams
used to reduce normal runon if topography allows, but large flood runoff may be handled by dam
storage capacity, spillways, or separate water-control dams, located upstream of the impoundment.
Figure 3 shows single and multiple cross-valley impoundment configurations.

Other types of valley impoundments may be employed when there is an excessively large drainage
catchment area and/or there is a lack of necessary valley topography.  Two variations are the side-hill
impoundment and the valley-bottom impoundment.  The side-hill layout consists of a three-sided dam
constructed against a hillside (Figure 4).  This design is optimal for slopes of less than  10% grade.
Construction on steeper slopes requires much more fill volume to achieve sufficient storage volume
(especially when using the downstream method of construction).

If the drainage catchment area is too large for a cross-valley dam and the slope of the terrain is too
steep for a side-hill layout, then a combination of these two designs, the valley-bottom impoundment,
may be considered (Figure 5).  Valley-bottom impoundments are often laid out in multiple form as
the valley floor rises, in order to achieve greater storage volume.  Because the upstream catchment
area is relatively large, it is often,  or usually, necessary to convey upstream flows around (and/or
under) valley-bottom impoundments.
                               «,

The valley dam configurations are  often the optimum choice for economic reasons.  This is because
the valley walls form one or more  sides, so that the dam length is reduced, minimizing construction
costs.  However, decreased construction costs and low average depth of tailings in the embankment
may be offset by increased environmental mitigation and increased costs of shut-down and
reclamation.

The valley dam design is particularly sensitive to overtopping by flood waters, erosion near the
intersection of die dam and the valley hillside, and liquefaction due to higher volumes of surface
water inflow from drainages within the natural catchment basin and  from high precipitation
runon/runoff. As is  described in more detail later, the stability of a valley dam depends largely on
the level of hydrostatic pressure within fill material and the embankment.   An unusual,  one-time  rise
in the hydrostatic pressure above design levels may be sufficient to trigger failure.  The control of
inflows across, around, or under the impoundment is important to retaining structural stability and to
controlling environmental impacts.  Providing adequate internal drainage can help guard against
liquefaction, and improve the permeability and consolidation of the tailings, thereby improving the
stability of the structure.

Because a shorter embankment is required in this configuration, it is more feasible to consider
impervious cores and internal drams as a means of controlling the phreatic surface and promoting
stability of the embankment.  Surface water controls may also be necessary. Diversion channels may
not always be an option due to the difficulty of construction along steep valley sides. However.
closed conduits may  be an alternative diversion method. Another alternative surface water control n

-------
                                                       Design and Evaluation of Tailings Dams
                                             (a)
               Figure 3. Single (a) and Multiple (b) Cross-Valley Impoundments




(Source:  Vick 1990)
                                            10

-------
                                                         Design and Evaluation of Tailings Dams
                 Figure 4. Single (a) and Multiple (b) Side-Hill Impoundments



(Source:  Vick 1990)
              Figure 5. Single (a) and Multiple (b) Valley-Bottom Impoundments



(Source:  Vick 1990)
                                            11

-------
                                                            Design and Evaluation of Tailings Dams
the valley layout is to construct a smaller water-retaining dam upstream of the tailings dam to collect
the water to divert it around the tailings or use it in the mill. A water-related factor that also must be
considered, particularly in valley impoundments, is the presence of shallow alluvial ground water.
Ground water can infiltrate the tailings, thus raising the level of saturation within the tailings; this can
be seasonal, in response to seasonal high surface water flows that interconnect with the alluvium
upgradient of the impoundment (or under the impoundment itself).

It should be noted that any design that calls for diverting or  otherwise controlling water flows during
the active life of the impoundment has to consider later periods as well. The water balance may be
more favorable after tailings slurry water is no longer being added to the impoundment/and the dam
stability may be less of a concern. However, if there are toxic  contaminants in the  tailings, or if the
tailings are reactive, the design must account for environmental performance following surface
stabilization and reclamation.

The stability of the tailings impoundment is also dependent on (or at least related to) foundation
characteristics, such as shear strength, compressibility, and permeability. Depending on soil
characteristics, the valley layout can be adapted to account for high permeability materials in the
design through the use of liners and/or adequate internal  drainage. Soil characteristics often can be
improved through soil compaction. In addition, the method of tailings deposition and construction
have an increased impact on the valley impoundment layout.  The deposition of tailings affects
consolidation, permeability, strength and, subsequently, the stability of the embankment material. All
these factors are discussed in later sections.

In some cases,  liners or zones of low permeability may be appropriate means of controlling seepage
to enhance stability or environmental performance.  The upstream face of tailings dams/embankments
(i.e., the side that contacts the tailings), for example,  is frequently designed to provide a layer of low
permeability or to be  impermeable. The effect is to lower the phreatic surface through the
embankment.  This is usually accomplished with the slimes fraction of tailings and/or with synthetic
materials.

Lining the  entire impoundment area is more problematic, both because of the expense and because
irregularities in valley side walls and floors make it difficult to ensure consistent liner integrity.
Liners or layers of low permeability may be necessary, however, to impede  flows to and from
underlying ground water.  More common than impermeable synthetic or clay liners is the practice of
compacting native soil, including any available local clays, to reduce permeability to an acceptable
level; dewatered or dried-in-place slimes may also be used hi some cases. Should  a liner or low-
permeability layer be  necessary, it must be designed to account for impoundment loadings, differential
settlement, toxic or corrosive seepage, and weathering effects.  If impoundments will  desaturate after
reclamation, for example, clay or slimes can crack and provide a pathway for ground water to enter
the tailings or for contaminated seepage to enter ground water.  Similarly, layers of clay or slimes
                                               12

-------
                                                            Design and Evaluation of Tailings Dams
that are prepared in anticipation of late impoundment expansion can develop cracks if they are
allowed to dry before being covered with tailings.

2.2.2   Ring-Dike Impoundments

Where natural topographic depressions are not available, the Ring-Dike configuration may be
appropriate (Figure 6).  Instead of one large embankment (as in the valley design), embankments (or
dikes) are required on all sides to contain the tailings. Construction can be similar to valley dams,
with tailings,  waste rock, and/or other native materials typically used in later phases of construction.
Because of the length of the dike/dam, more materials are necessary for this configuration, and
material for the initial surrounding dikes is typically excavated from the impoundment area.
                                                                         (b)
         Figure 6.  Single (a) and Segmented (b) Ring-Dike Impoundment Configurations

(Source: Vick 1990)

According to Ritcey (1989), most recent dike dams have been built using downstream or centerline
methods rather than the upstream method (see below for descriptions of the various types of
construction); Ritcey cites Green (1980) as reporting that long-term stability of upstream dikes is not
certain.

Embankments are required on all sides, so this method utilizes a large amount of embankment fill  in
relation to the storage volume.  This layout can be arranged in single or  segmented form. The
                                               13

-------
                                                             Design and Evaluation of Tailings Dams
regular geometry typically used with this configuration makes it amenable to the installation of
various kinds of liners. (Vick 1990)

If the terrain is flat and thus suitable for ring-dikes, this configuration allows maximum flexibility in
actually selecting a site.  Since the dikes are relatively low in height, the design is often simpler than
a high valley dam design.  Containment can be achieved by using an impervious core in the dikes
and/or the use of a liner below the impoundment.

Unlike valley impoundments,  which are located hi a natural catchment area, the ring-dike design
enables better maintenance of water control.  The quantity of pond water is limited to that transported
with the tailings and any precipitation falling directly onto the impoundment. There is no runoff
other than from outer slopes.  Since surface runoff and flood impacts are reduced, a smaller pond
area and/or less elaborate water control measures are required. A trade-off can be made with a high
tailings depth that reduces surface area and results in less  seepage.  There are also drawbacks to this
design, including the relatively large volumes of material  necessary for construction, and  its effect on
cost.  The increased length of the embankment  walls also  may increase the possibility of failure
(Robertson 1984, cited in Ritcey J1989). Other disadvantages of the ring dike system are that the
impoundment rises above the surrounding terrain,  creating an aesthetic problem in some  locations,
and there  can be considerable wind erosion of the tailings. In many areas, also, there is  no flat
terrain suitable for ring-dike designs.

Although  each situation needs to be evaluated on its own merits, the ring dike system has the potential
for better  control of seepage than that found in  most valley dam locations.  If warranted by the
characteristics of a particular tailings, almost total containment and collection of effluent can be
achieved using  a suitable combination of low permeability cores, liners, and drainage system.  Since
seepage control is often a pressing environmental concern with tailings impoundments, the ring dike
system can have an important advantage over most other layouts.

2.2.3  In-Pit Impoundments

This method is much less common than the valley and ring-dike impoundments.  It consists of
disposing  tailings material into a  previously mined pit.  The design initially eliminates the need for
dike construction.

Since the  tailings are protected by pit walls, wind  dispersion is minimized.  Good drainage can be
incorporated into the design.  Many of the failure  modes common to tailings embankments (e.g.,
piping, liquefaction) do not apply to this design.  The lack of dam walls reduces the possibility of
slope failure, but the stability of the pit slopes do  have to be checked.

Unless the purpose is to isolate sulfide tailings  underneath water, the water table should be below the
tailings disposed  in the pit.  This may require backfilling with mine rock or overburden.  If
                                                14

-------
                                                            Design and Evaluation of Tailings Dams
backfilling underneath the tailings is necessary, and/or if the surrounding rock is not sufficiently
impermeable, a liner may be required. Ritcey (1989) notes that the hydrogeological parameters
affecting the migration of seepage and contaminants are poorly understood, so tailings with toxic
contaminants or reactive tailings may  be poor candidates for this type of impoundment.

When mining hi an active pit is proceeding laterally, the mined-out portion of the pit may be suitable
for tailings disposal.  In such cases, dikes would be constructed to impound the tailings in the mined-
out area.  This embankment could then be raised in a phased approach (Ritcey 1989).

2.2.4  Specially Dug Pit  Impoundment Design

This design is fairly unusual and involves the excavation of a pit specifically for the purpose of
tailings disposal.  The impoundment consists of four or more cells with impermeable liners and
surrounded by an abovegrade dam.  Material removed from  the pit is used in construction of the dam.
This dug pit/dam design has some of the same advantages  as the ring-dike design, including site
independence and uniform shape. Site independence benefits the design, since less effort and cost are
needed to counteract topographic obstacles, soil conditions, climatic conditions, and construction
obstacles. The uniform layout, shape, and flat terrain prevents surface runoff from entering the
impoundment and decreases the requirements  for flood control measures.
                                               15

-------
                                                           Design and Evaluation of Tailings Dams
3.     TAILINGS IMPOUNDMENT DESIGN

The actual design of a tailings dam and impoundment occurs only after the site has been selected.
However, the site selection and design are best considered to be a dynamic process. A number of
design principles should affect the site selection process as well as the determination of the
embankment type and the impoundment configuration.  This section first describes some of these
fundamental design principles as well as major design variables and site-specific factors that influence
ultimate design.  As noted previously, the major considerations in the design of a tailings dam and
impoundment are stability, cost, and environmental performance.

3.1    Basic Design Concepts

In general, tailings impoundments (and the embankments that confine them)  are designed using
information on tailings characteristics, available construction materials, site specific factors  (such as
topography, geology, hydrology and seismicity) and costs, with dynamic interplay between  these
factors influencing the location (or siting) and  actual design of the impoundment.  Because water is a
major component in any tailings impoundment system, principles of hydrology (applied to flow of
water through and around the tailings embankment) dictate many of the rules of tailings impoundment
design.  Indeed, because impoundment and dam stability are in large part a function of the water
level, these principles are of fundamental concern in the design of any tailings impoundment.

One of the basic principles used in the design of impoundments and then* embankments is the
maintenance of the phreatic surface within the  embankment.  The phreatic surface is the level of
saturation in the impoundment and embankment (the surface along which pressure in the fluid equals
atmospheric pressure (CANMET 1977)); in natural systems it is often called the water table.  The
phreatic surface exerts a large degree of control over the stability of the embankment, under both
static and seismic loading conditions (Vick 1990). The major design precept is that the phreatic
surface should not emerge from the embankment and should be as low as possible near the
embankment face (Vick 1990).  This basically  maintains a pore pressure  at the face of the
embankment lower than atmospheric pressure plus the weight of the embankment  particles and
maintains the face of the dam.  Thus any factors that might affect the phreatic surface in the
embankment may also affect stability of the embankment.  The primary method of maintaining a low
phreatic surface near the embankment face is to increase the relative permeability  (or hydraulic
conductivity, since water is the fluid) of the  embankment in the direction of flow.  (See Figure 7.)

Creating a relative increase in permeability downstream can be accomplished in one of two  ways, or a
combination of the two: by incorporating lower permeability zones in the upstream areas of the
embankment (typically by constructing embankments with low permeability  cores) and by using
higher permeability zones downstream (typically using internal drainage  zones).  The selection of
which technique to use is often based on the availability of materials, such as clays for cores and or
clean sands for drains.  The use of cores and drainage zones to maintain embankment stability ire
                                              16

-------
                                                            Design and Evaluation of Tailings Dams
                                                     Phreatic surface
                                                                              *, >*2>*3

                                               "i
                  Figure 7.  Phreatic Surface Through a Tailings Impoundment

(Source: CANMET 1977)

further discussed in a later section.  It should be kept in mind, however, that major changes in
phreatic surface require permeability differences in adjacent zones to be two or more orders of
magnitude (Vick 1990).

The low permeability layer generally controls the  overall flow rate through the impoundment.  This
allows higher permeability layers located downstream of the low permeability layer to drain and avoid
increased pore pressure.  The rulg-on increasing permeability  in the direction of flow only applies in
areas near the embankment face; if a low permeability core in the center of the embankment is used
and permeability increases downstream toward the face, permeability of the material on the upstream
side of the embankment may have little effect on the phreatic  surface downstream of the low
permeability core (Vick 1990).

In most embankments, materials in the various zones are also arranged to meet filter requirements,
which are designed to prevent migration of tailings and finer materials into coarser zones.  Otherwise
voids will be produced that can form a pathway through the dam along which water can escape.  As
seepage rates accelerate along the pathway, erosion of the dam material occurs leading to failure of
the dam. Such failures are referred to as piping failures, because of the natural "pipe" that is formed
through the embankment.  Piping failures can be avoided by the proper application of various filter
rules that have been established in the design of water-retention dams. (Vick 1990)

Factors that affect the phreatic surface in the embankment affect its stability.  These factors include
the depositional characteristics of the tailings (permeability, compressibility, grading, pulp density,
etc.) and site-specific features such as foundation characteristics and the hydrology and hydrogeology
of the impoundment area and its upstream catchment area. Changes in the phreatic surface in a waste
embankment will change  the pore water pressures and consequently the resistance of the dam
materials to sliding.  Changes to the phreatic surface can be caused by: malfunction of drainage
systems, freezing of surface layers on the downstream slope of the dam, changes in construction
method (including the characteristics of the placed material), and changes in the elevation of the pond.
The level of the water table also may be altered by changes in the permeability of the underlying
                                               17

-------
                                                            Design and Evaluation of Tailings Dams
foundation material; sometimes these are caused by strains induced by mining subsidence (Vick
1990).

In addition to maintaining the phreatic surface for stability purposes, dam design now includes factors
related to environmental impacts associated with tailings seepage. By the use of liners, drains, and
pumpback systems, tailings seepage may be controlled.  These techniques are discussed in more  detail
in a later section of this report.  The design should also address the future reclamation of the site.

3.2    Design Variables

3.2.1  Tailings-Specific Factors

Tailings composition, pulp density, grading, and other characteristics are used in the design of tailings
impoundments  in three basic ways: tailings analysis to assess the potential use of tailings sands in
constructing the embankment, analysis of tailings to be placed in the impoundment to determine  their
potential impact on structural stability and seepage characteristics, and mineralogical analysis to
determine the potential chemical aspects of seepage or other discharges from the impoundment.  In
addition to the  physical characteristics, the method  of deposition of tailings into the impoundment
plays a role in  the "engineering characteristics." (Vick 1990)

Tailings sands  are often used as an inexpensive source of material for embankment construction; by
removing the sands for embankment construction the volume of tailings to be disposed of is reduced.
Depending on the gradation (grain size distribution) of die tailings,  a cyclone may be used to separate
sufficient amounts of coarse sand from the whole tailings to construct the embankment, leaving a
higher percentage of slimes to be deposited behind  the embankment. Cycloned sands can have both
high effective strength and high permeability,  the two major characteristics necessary for downstream
embankment material.  In addition, cycloning results in the  deposit  of the less permeable slimes
behind the embankment, possibly reducing impoundment seepage.

With regard to their general physical properties, tailings are considered to be soils, subject to
traditional soil  mechanics patterns of behavior.  Index properties (gradation, specific gravity, and
plasticity) are determined by relatively simple tests that can be performed on tailings produced in
bench testing of the mill process.  These index tests are a guide to the engineering properties of the
tailings.   Caution is required, however, since  tailings differ in subtle ways from soils having similar
index properties (Vick 1990).

Tailings properties that impact design, stability and drainage of the impoundment include in-place and
relative density, permeability, plasticity, compressibility, consolidation, shear strengths,  and stress
parameters (Vick 1990).  In-place density is an important factor in  determining the size of
impoundment required for a specific operation while  relative density influences dynamic strength
behavior.  In-place density refers to die mass/unit volume of an undisturbed sample of material  where
                                                18

-------
                                                             Design and Evaluation of Tailings Dams
the sample volume is much greater than the average particle size. Gradation is a factor of in-place
density, with well graded materials typically having a higher density (CANMET 1977). Permeability
(or hydraulic conductivity) of tailings in-place in the tailings impoundment varies in both horizontal
and vertical directions due to the layered way most tailings are deposited.  Plasticity refers in a
general way to the amount of clay present.  More specifically, the Plasticity Index  is the range of
moisture content over which a soil is plastic;  numerically, it is the difference between the  Liquid
Limit and the Plastic Limit of the soil.   Tailings with  a high Plasticity Index are finer-grained and
have low permeability and drainage characteristics, while tailings with a low (or zero) Plasticity Index
are more coarse and have high permeability drainage properties. Consolidation and compressibility
are related to particle size (sands vs. slimes) and density or void ratio.  These  are a measure of the
change in overall volume the tailings may experience over time with dewatering and/or added load.
Tailing sands and slimes, for example,  are more compressible than otherwise similar soils. Shear
strengths and stress parameters of tailings are functions that affect stability and are impacted by pore
pressure.  The interaction of all of these factors is complex and affects the phreatic surface in
impoundment  and embankment.  For more information, see Vick 1990; and CANMET  1977.

In addition to tailings characteristics that affect stability and seepage quantity, tailings can  be analyzed
to determine seepage water quality.  Besides process chemicals (e.g., cyanide) that may be present,
metal mine tailings may contain an array of minerals originally present in the host  rock that can
contaminate tailings seepage.  Contaminants including arsenic, copper, lead, manganese, selenium and
other metals.  Tailings also can have significant levels of radioactivity.

Tailings and effluent may be acidic or caustic, and in some cases are neutral but later become acidic.
The oxidation of sulphides, particularly pyrite (FeS) and pyrrhotite (Fe,.xS:  Fe6S7 to FeuS12) can
result in the generation of acid drainage.  In the presence of free oxygen, the pyrite oxidizes to
produce acidic conditions.  The chemical reaction is the combination of metal sulfide and water to
produce a metal hydroxide and sulfuric acid.  In addition to chemical oxidation,  a bacterium
(thiobacillus ferrooxidans) causes bacterial oxidation which may become the dominant process  in the
later stages of acid production.  The acidification of tailings ponds can occur in tailings that were
initially alkaline; as water levels drop within the tailings impoundment, they introduce  air  into the
void spaces and the subsequent oxidation produces acids. Analysis of the ore and tailings  prior to
disposal is useful in anticipating water quality problems and the need to adjust seepage flows.  Water
management and the associated fate and transport of contaminants is addressed in a later section.

3.2.2  Site-Specific Factors

Site-specific factors play a major role in the design of an impoundment.  Siting considerations
include: (1) physical considerations such as volume of tailings and area required by the dam, (2)
financial considerations such as the amount and  cost of fill material, water controls, and tailings
depositional methods, and (3) environmental requirements such as flood control, ground water and
surface water contamination, and wildlife habitats.
                                                19

-------
                                                            Design and Evaluation of Tailings Dams
The process of selecting the most favorable site typically is a screening process wherein less suitable
sites are successively removed from further consideration.  The screening criteria include cost, design
constraints, and environmental conditions/performance; the importance of each of the criteria may
vary depending on the operation and the site being screened.  In selecting an appropriate site, the
constraints are  imposed mainly by the mill location, topography, hydrology, geology,  and
hydrogeology (Vick 1990).  Consideration of all potential factors and full investigation of the potential
site can alleviate design problems once a site has been selected. Because design factors also influence
site selection, a dynamic  iterative process of site selection can result in the most favorable outcome.

Mill Location

Tailings are generally transported from the mill in slurry form, typically with a solids content from 15
to 55 percent by weight.  This requires an extensive piping system for the tailings, as  well as for
pumping reclaim water back to the mill.  Vick (1990) quotes an average cost of about $500,000/mile
for these systems.  Consequently, sites close to the mill are favored on a cost basis over those further
away.  Initial site screening usually considers sites within about five miles of the mill; this distance
may be expanded later if no suitable  sites are found.  Ideally, sites are located downhill from the mill
to allow gravity flow of the tailings to the impoundment and to minimize slurry pumping costs;
however, pipelines with steep gradients are avoided where possible.  Sites having small elevation rises
from mill to impoundment may not be ruled out.

Topography

In addition to distance and elevation, natural topography is one of the main considerations for the
given impoundment volume required. The aim is to achieve maximum storage capacity with the least
amount of embankment fill.  Natural valleys and other topographical depressions are usually
investigated first. As a rule of thumb, embankment heights are kept below 200 feet.  High
embankments (greater  than 400 ft) often pose design and construction problems that could be avoided
by better siting. (Vick 1990) Topography is also an important factor in the site's hydrology.

Hydrology

Surface water hydrology factors generally favor water diversion around the impoundment and the
minimization of water inflows into the impoundment (unless one of the objectives is to collect water
for the mill operation). In general, these flows are minimized both for normal and flood conditions.
If possible, this is achieved by locating the impoundment as close as possible to the head of the
drainage basin  to minimize the costs of constructing  surface water diversion structures. In order to
avoid excessive water  handling requirements, the total catchment area should be less than 5 to 10
times the impoundment surface area (Vick 1990).  Even then, there must be provisions for controlling
runon and runoff after the impoundment  is "closed."
                                               20

-------
                                                             Design and Evaluation of Tailings Dams
Because location, topography, and hydrologic considerations and constraints are relatively easily
evaluated, they assume great importance in the screening process. As site investigations proceed (and
more costly investigations are necessary), it may be appropriate to re-examine some sites that are
eliminated from further consideration early in the process.

Geology and Ground Water

Once the site screening criteria of mill location, topography, and hydrology have been applied, the
number of siting options usually has been considerably reduced.  Geologic considerations then assume
a critical role.  In particular, site geology affects the foundation of the embankment, seepage rates,
and the availability of borrow materials for embankment construction.  Soft foundations,  for example,
may limit the allowable rate of embankment build-up in order to allow for adequate pore pressure
dissipation.  Sloping foundations and the presence of weak layers in the foundation will need to be
investigated since they may contribute to slope failure of the embankment.

Although geologic details are critical to siting and design, they often play a secondary role in actual
siting decisions.  This is because there are usually a limited number of sites available at this stage (the
rest having been eliminated by consideration of mill location, topography and hydrology).  In
addition, the lack of detailed information often precludes  any meaningful  comparisons of alternative
sites. The tendency is to try to engineer around any geologic problems.  If, following  the site
investigation, a "fatal" geologic problem is discovered, the site will have to be abandoned at that
time. The search will then continue for one or more suitable sites.

Ground water conditions are usually related to the geology, and also affect siting conditions.  A high
water table limits the amount of dry borrow material available for construction, and shortens the
distance for seepage to enter the ground water system. In addition, shallow ground water can
infiltrate tailings and increase the amount of water  in the  impoundment.

Initially, various observations and assessments can assess broad geologic factors, including the
availability of construction materials, special construction problems with  respect to nearby structures,
drainage conditions at the site, and apparent ground stability of the site (such as slumping, evidence
of weak planes within the rock, faulting, etc.).  The type of vegetation present can indicate subsoil
characteristics.  Test pits and trenches may  be dug and test holes may be drilled to obtain soil and/or
rock samples.  In situ permeability tests also may be run in holes drilled  at the site  of the proposed
tailings impoundment area.

A proposed site will undergo a geotechnical site investigation.  The investigation will assess site
geology, including the depth, thickness, continuity, and composition of the strata; site  hydrogeology;
geotechnical properties of soil and rock affecting design;  and availability of suitable construction
materials for building dams, dikes, drains, and impervious  liners.
                                                21

-------
                                                            Design and Evaluation of Tailings Dams
Geotechnical testing on soils is generally undertaken to determine water content, grain-size
distribution, Atterberg limits (moisture content in soil as measured in the boundary stages of four
states of soil: liquid, plastic, semi-solid, and solid), consolidation, shear, permeability, and ion
exchange capacity (of clays considered for liners).  For rocks it is usually necessary to know the shear
strength along weak layers, and the permeability and strength of the various strata.

These tests are usually performed in combination with in situ tests such as standard penetration, static
cone, vane shear, and pressure meter, in order to obtain useful data on field properties. While
estimates of soil permeability may be determined in the laboratory, these values need to be confirmed
through field testing, which may include borehole in situ methods, and large scale pumping methods.
In addition, ground water measurements, including piezometric pressures in the underlying soil/sand
rocks, and water sampling are usually undertaken to establish baseline conditions prior to construction
of the impoundment.

Foundations

The foundation area beneath the embankment is assessed using the geotechnical and other methods
noted above.  Weak material benc*ath the slope, such as buried slopes once exposed to weathering,
snow covered surfaces over which additional material has been deposited, layers of fine material
included in a coarse material embankment,  and foundation strata of low shear strength, can cause
rotational  sliding.  If a deposit of clay is extensively fissured, water penetrating into the fissures can
seriously weaken the deposit due to the dependency of the shear strength on the softened material
strength adjacent to the fissures. Compression or consolidation of the foundation can cause
appreciable settling of the overlying material, sometimes causing cracks in tailings embankments (or
zones of embankments) that can lead to seepage or piping.

The permeability of the foundation significantly affects the stability of an embankment.  When an
embankment  is constructed on a foundation of saturated impervious clay, for example, the loading of
the embankment will create excess pore water pressure in the foundation material.  Because the
immediate loading is taken by the water phase in the foundation material, there is no increase in shear
strength and the rapid increase in loading can precipitate embankment failures extending through the
foundation.  If the foundation  material beneath the tailings dam is pervious, excessive seepage can
lead to piping Mure.  All of these foundation factors are taken into account during design.

Seismicity

The design of tailings impoundments usually has to consider potential seismic activity at the site.
This requires the selection of a design earthquake for the site in question. A method commonly used
to determine the effects of the design earthquake on a particular site is to assume that the earthquake
occurs on the closest known possibly active fault.  The fault is selected on die basis of the geological
studies previously conducted in the area. Attenuation tables are then used to estimate the magnitude
                                               22

-------
                                                              Design and Evaluation of Tailings Dams
of the earthquake forces reaching the site as a result of the design earthquake occurring on the
selected fault.
                                                 23

-------
                                                           Design and Evaluation of Tailings Dams
4.     EMBANKMENT CONSTRUCTION, STABILITY, AND FAILURE
               i
4.1    Embankment Construction

Tailings embankment design investigations, described above,  lead to the selection and refinement of a
starter dam that will serve as the starting point for embankment construction.  The starter dam design
specifies the internal and external geometry of the structure, and should include specifications for
drainage, seepage control, and in some cases liner systems required to maintain embankment stability
and control releases to the environment.  It is important to emphasize that final embankment design
may differ substantially from initial expectations. If embankment construction continues throughout
the active life of the impoundment, experience gained from ongoing monitoring and analysis allow for
changes and improvements in the design to better meet project goals.

In general, if the starter dam design includes liners and/or drainage systems, such systems must be
developed prior to or concurrently with initial dam construction, as well as with each successive raise
of the embankment. Environmental considerations may create a need for liners since tailings may
have a potential to leach toxic or undesirable constituents to underlying strata; similarly, it is desirable
to limit the flow of shallow ground water into the tailings.  Liners may be composed of compacted
native soils, compacted tailings slimes, imported or local clays, synthetic materials, gunite, etc.  For
economic reasons, compaction of native soils or tailings slimes are the preferred methods of reducing
the permeability of impoundment bases where these methods  will meet objectives.  Further, as a
practical matter, some impoundment designs, such as cross-valley impoundments, may not be
amenable to any other type of liner; with very large surface areas and uneven  terrain, the use of
synthetic liners or other imported materials is generally prohibitively expensive for this type of
impoundment, even if it is technically feasible.

Drainage systems may be required for structural reasons.  As discussed above, a primary concern
accompanying the use of tailings for embankment construction is the control of pore water pressure
within and beneath the embankment.  Excessive pore pressure within the embankment may lead to
exceedence of the sheer strength of the fill material,  resulting in local or general slope failure.
Additionally, high pore pressures within or beneath the embankment face may result in uncontrolled
seepage at the dam face leading to piping failure (discussed below). Similarly, seepage through weak
permeable layers of the foundation may result in piping or exceedence of soil  shear strength, causing
foundation subsidence and compromising  the stability of the overlying embankment.  These and  other
threats to embankment stability may be partially reduced through seepage control. Generally
speaking, seepage control may be affected through the establishment of zones  of differing
permeability up-stream of, beneath, and within the embankment, either through drainage systems or
low permeability layers or cores, or both.

The primary function of drainage systems is the dissipation of pore pressure across the embankment.
Drainage systems allow the control of the phreatic surface by providing low-pressure conduits for
                                              24

-------
                                                           Design and Evaluation of Tailings Dams
seepage.  A number of methods are available to accomplish this goal.  In particular, chimney drains
and blanket drains, each composed of materials of permeability at least two orders of magnitude
greater than that of the embankment fill itself (Vick 1990), may be installed within and beneath the
embankment to allow dissipation of pore pressure.  Chimney drains are'vertical curtains of high
permeability material, while blanket drains are horizontal layers of high permeability material.
Variations of each may be used depending on design requirements.  The location of such drainage
zones depends on the method of construction of the embankment, discussed below.

Critical to the performance of drainage systems is the prevention of clogging; this  can occur, for
instance, when tailings fines infiltrate the drainage  zone.  Filters or filter zones may be employed to
help prevent clogging and hence maintain differences in permeability across zones. Filter zones may
be constructed of graded sands or synthetic filter fabrics (Vick 1990).

The foregoing discussion underscores an important concept common to tailings impoundments in
general:  seepage through tailings embankments is  essentially unavoidable and often necessary.  Since
the purpose of the tailings embankment is to impound tailings slurry (and allow for reclamation of
mill process water), and since tailings sands used for construction of the embankment are never
impermeable, hydraulic head across the embankment  will never be zero.  Some water will migrate
through and/or under the embankment.

4.2    Construction Methods ,_

A variety of construction methods and materials are used in the construction of tailings embankments.
In general, mines choose materials and methods to provide the required stability at the lowest cost. If
the tailings dam is near the mine, the use of waste rock can significantly lower the cost of materials,
while also reducing the need for waste rock disposal areas. If borrow materials are to be used, they
can be obtained from the impoundment area and increase impoundment capacity.   The materials also
should meet permeability, compressibility and shear strength requirements.  They  also must be
chemically stable, so potentially acid-generating waste rock is not suitable for embankment
construction, particular in drainage systems.  The most frequently used material in embankment
construction is tailings.

4.2.1  Construction Using Tailings Material

The use of tailings material  is generally the most economical construction method. As discussed
previously, some of the disadvantages of using tailings as dam-building material include:  high
susceptibility to internal piping, highly credible surfaces, and high susceptibility of the fine tailings to
frost action.  Also,  loose and saturated tailings are subject to liquefaction under earthquake shocks.
During construction of the tailings dam, the two major ways to improve these qualities are use of
coarse fractions of tailings and  compaction.  Generally, the sand fractions, after being separated from
the slimes, may be easy to compact using vibratory compactors. By compacting this coarse fraction
                                               25

-------
                                                            Design and Evaluation of Tailings Dams
of the tailings, the end result is a dense mass of strong material that has greatly increased resistance to
liquefaction.  Tailings separation most commonly occurs by spigotting or cycloning.  The three
methods of construction using tailings are upstream, downstream and centerline.  A comparison of
these methods is presented in Table 1.

4.2.2   Upstream Method

Upstream construction, the oldest and most economical method, begins with a starter dam constructed
at the downstream toe (Figure 8). The starter dam should be capable of passing seepage water and
the downstream portion should be resistant to piping.  The tailings are discharged peripherally from
the crest of the starter dam using spigots or cyclones.  This deposition develops a dike and wide
beach area composed of coarse material.  The beach becomes the foundation of the next dike. In
some applications, the dikes  are mechanically placed and the discharge is used to build the beach only
(in addition, slimes may be  used to coat the  upstream face of the dike to reduce permeability).
These dikes can be built with borrow fill, or  beach sand tailings can be excavated from the beach and
placed by either dragline or bulldozer.  Either way, some type of mechanical compaction of the dike
is typically conducted before the next stage of the dam is constructed.
                                «,

The single most important criteria for the application of the upstream construction method is that the
tailings beach must form a competent foundation for the support of the next dike. Vick (1990) states
that as a general rule, the discharge should contain no less than 40 to 60 percent sand. This can
preclude the use of the upstream method for  those mill tailings that contain very low percentages of
sand.  Other references state that the  determining  factor for upstream versus downstream construction
is grain-size distribution of the tailings.  In addition to grain size tests, Brawner, et al, (1973)
suggested that, "If a tractor cannot be operated on the first 100 to 200 feet of beach,  the grind is too
fine for upstream construction methods."

In addition to tailings gradation, several other factors can limit the  applicability of this method.
These factors include phreatic surface control, water storage capacity, seismic liquefaction
susceptibility and the rate of dam raising.  Upstream embankment construction offers few structural
measures for control of the phreatic surface within the embankment.  Vick (1990) identified four
important factors influencing the phreatic surface  location:  permeability of the foundation relative to
the tailings, the degree of grain-size segregation and lateral permeability variation within the deposit.
and the location of ponded water relative to the embankment crest.  Only tile pond location can be
controlled through operational practices.  The other factors must be planned for in the construction
design phase.  Both proper decanting and spigotting procedures can be used to control the distance
between the pond's edge and the embankment crest. Although the pond's location can be controlled
to some extent during operation, a tailings pond that is expected to receive high rates of water
accumulation (due to climatic and topographic conditions) should be constructed using a method other
than upstream construction. Any change in  environmental or operating conditions (heavy rainfall.
blockage of seepage outlets, rise in water levels of the pond, etc.) resulting in a rise of the phrenic
                                                26

-------
                                     Table 1. Comparison of Embankment Types
E*b«nfcme«
Type
Water retention
Upstream
Downstream
CcMritac
Mill Tailings
Requirement*
Suitable for any
type of tailing!
At least 60% sand
in whole tailings.
Low pulp density
for grain-size
segregation.
Suitable for any
type of tailings
Sands or low-
plasuciiy slunes
Discharge
Requirement*
Any discharge
procedure suitable
Peripheral discharge,
well-controlled beach
necessary
Varies according to
design detail
Peripheral discharge
of at least nominal
beach necessary
Water-Storage
Suitability
Good
Not suitable for
significant water
storage
Good
Not recommended
for permanent
storage.
Temporary flood
storage can be
designed.
Seiank
Resistance
Good
Poor in high
seismic areas
Good
Acceptable
Raising Rate
Restrictions
Entire
embankment
constructed
initially
Less than 15-
30 ft/yr most
desirable.
Over. 50 ft/yr
can be
hazardous
None
Height
restrictions for
individuals
raises may
apply
Embankment
Fill
Requirements
Natural soil
borrow
Native soil, sand
tailings, waste
rock
Sand tailings,
waste rock,
native soils
Sand tailings,
waste rock,
native soil
Relative
Embankment Cost
High
Low
High
Moderate
Use of Low
Permeability
Cores
Possible
Not possible
Possible
(inclined cone)
Possible (General
cone)
(Source: Vick 1990)
I
&

§.
fti

I
                                                                                                                      o

-------
                                                            Design and Evaluation of Tailings Dams
                                   •Equipotentiol lint
                                               surface(Upper flow line)
                                               Flow line
                                                          Note: Seepage •merging on down-
                                                             ttreoni face of embankment causes
                                                             sloughing and  may  lead to piping
                                                             and internal erosion.
                    Figure 8.  Upstream Tailings Embankment Construction

(Source: Vick 1990)

line and complete saturation of the outer sand shell could quickly lead to failure by piping or sliding.
An outer rockfUl shell may mitigate failure potential from piping or sliding.

Tailings embankments constructed using the upstream method generally tave a low relative density
with a high water saturation. This combination can result in liquefaction of the tailings embankment
in the event of seismic activity.  In addition, vibration of sufficient intensity and magnitude caused by
blasting, trains, heavy trucks, etc., may cause liquefaction.  The shear strength can be reduced to near
zero such that the fluidized slimes easily burst through the remaining thin, unsaturated sand-dike shell
and the  dam collapses and flows. This can occur at very low heights and slope angles. Therefore,
upstream construction is not appropriate in areas with a potential for high seismic activity.

The rate of embankment raises is limited by the build-up of excess pore pressures within the deposit.
This build-up of pore pressures can lead to a shear failure, which may result in breaching of the dam
and the  release of contained tailings (Brawner 1973).   The height at which potential failures are
triggered depends on the strength of the tailings within the zone of shearing, the downstream slope of
the dam, and the location of the  phreatic line.

Horizontal  drainage zones may be installed during starter dike construction to help maintain low pore
pressure within the embankment. Vick (1990) states  that a blanket drain extending well upstream of
the starter dike may  be effective in lowering the phreatic surface in the initial and subsequent
embankment rises.  He notes, however, that special effort must taken to ensure against blockage of
blanket  drains when used in upstream embankments.

4.2.3   Downstream Method

The design requirements for the downstream method  of construction are similar to conventional water
storage  dams. As in upstream construction, downstream construction also begins with a starter dam
constructed of compacted borrow materials, however, this starter dam may be constructed of pervious
sands and gravels or with predominately silts and clays to minimize seepage through the dam
                                               28

-------
                                                             Design and Evaluation of Tailings Dams
(Figure 9).  If low permeability materials are used in the starter dike,  internal drains will need to be
incorporated in the design.  The downstream method is so. named because subsequent stages of dike
construction are supported on top of the downstream slope of the previous section, shifting the
centerline of the top of the dam downstream as the dam stages are progressively raised.
                                                      Spigotted      Tailings -   	   Starter dike
           L                                          tailings v    discharge line^V       /
            X            „	beach    \	>4      /
           ."..».i.'..'..-.•.•....i.-.v...-^.!.'.!^.-..!.•.•..•::.•.'••.:.:.'.•.•.•:.•.•.•.• ::;-v.r: :vy :'::--.':^^    ^t^

                                               (a)
                                                                                      Perimeter
                                                                                      dike
                                               k)
                                              (c/)
                       Figure 9.  Downstream Embankment Construction
(Source: Vick 1990)
A variety of tailings deposition^ techniques can be used in conjunction with the downstream
construction method, but peripheral spigotting of tailings is very common.  Coarse tailings can be
spread in thin layers utilizing on-darn cycloning, or they can be hauled from a central cycloned
stockpile, then spread and compacted. If the volume of coarse tailings is not sufficient to construct
the dam, local borrow materials may be incorporated for part of the structure.  If coarse rock is used.
due to its porosity, a filter or impervious  upstream membrane is required to prevent piping of the
tailings through the rock.  If spigotting is controlled to create a wide tailings beach and the
                                               29

-------
                                                            Design and Evaluation of Tattings Dams
embankment has been made of permeable tailings, the phreatic surface may be controlled without the
need for internal impervious zones or drains. However, Brawner, et al. (1973) recommend that if the
dam will be constructed in a potential earthquake zone and/or its height is to exceed 50 ft,  the
downstream extensions must be compacted to a higher relative density than is typical to minimize the
risk of liquefaction.

The downstream construction method allows for the incorporation of drains and impervious cores to
control the phreatic surface. Brawner, et al. (1973) recommended the placement of a pervious sand
underdrain layer or alternative drainage system prior to each downstream extension.  Several other
drain designs can also be incorporated into the design.  For example, an inclined chimney  drain near
the upstream face of the dike,  and connected to a blanket drain at the diktss base, may be installed
with each successive raise of the embankment. (Vick 1990) Drainage controls help to control the
phreatic surface and minimize the chance for build-up of pore water pressures which reduce shear
strength.  Due to the ability to incorporate drains into the design, this method of construction is well-
suited to conditions where large volumes of water may be stored along with the tailings solids.

The downstream method of construction provides a degree of stability not  found in upstream
                               *,
construction due to the ability and ease of compaction, the incorporation of phreatic surface control
measures and the fact that the dam raises are not structurally dependent upon the tailings deposits for
foundation strength. A major disadvantage of this  method is the large volume of fill material required
to raise the dam.  The increased volume of fill  required  can dramatically increase the cost  of this
method of construction if the tailings from the mill cannot provide a sufficient volume of sand.
Embankments constructed with downstream raises  also cover a relatively large area,  which can be a
major disadvantage if available space is limited.

4.2.4   Centerline Method

Centerline construction is similar to both the upstream and downstream construction methods in that
the embankment begins with a starter dam and tailings are spigotted off the crest of the dam to form a
beach.  The centerline of the embankment is maintained as fill and progressive raises are placed on
both the beach and downstream face (Figure 10). The tailings placed on the downstream slope should
be compacted to prevent shear failure. The centerline method of construction provides some of the
advantages over the other two methods while mitigating some of the disadvantages.

As in the downstream method, drainage zones can be incorporated into the construction.  A wide
beach is not mandatory and this method is amenable for use with tailings that contain a relatively low
percentage of sand.  Since less sand is required, the dam raises may be added faster than in the
upstream or downstream methods.  Coarse gradation of the tailings is necessary if rapid drainage is
required to provide support for construction equipment.
                                               30

-------
                                                            Design and Evaluation of Tailings Dams
         .Ponded water
Impervious zone
                                                         J
                                                            Starter dike
                                                                      .  .
                                                                     drain
                                               (tf)
          ••..•.:•••.•.•.••••.•!••:.••.,•:'•.• .-.•.-. :;.•.•  '..'•.'•>j^^

                                              (c)
                                              (d)
                        Figure 10.  Centerline Embankment Construction
(Source: Vick 1990)
Although this embankment type is not amenable to permanent storage of large volumes of water,
short term storage of water due to heavy precipitation events or mill shutdown will not adversely
affect the stability of the dam.

If the embankment has been properly compacted and good internal drainage is provided, this
embankment type is  resistant to seismic activity.  Even in the event that the slimes placed against the
upstream slope liquefy, the central and downstream portions of the dam may remain stable due to
their good compaction and drainage characteristics.

4.2.5  Embankments Constructed Using Alternative Materials

Although the three embankment construction methods discussed above are typically built with large
volumes  of coarse tailings, portions of the dams (particularly the starter dam) may incorporate a
variety of borrow fill materials.  For example, waste rock and overburden excavated during open-pit
                                               31

-------
                                                            Design and Evaluation of Tailings Dams
stripping can be used to construct embankments.  However, waste removed from the mine may not
keep pace with the demand to raise the dam crest.  Also, waste rock that may potentially be acid-
forming is not suitable for embankment (or drainage) construction.

In general, where natural materials  are used exclusively for dam construction, standard earth dam
(water retention) design may be followed. A water retention dam constructed with native materials
should contain internal zoning such as an impervious core, drainage zone!!, and appropriate filters.
These designs are best suited when large volumes of water are planned to be stored with the tailings.
Design changes  are required to account for the higher unit weight of saturated tailings.  In addition,
since water retention dams are designed to limit the drainage through the core, placement of spigotted
slimes on the upstream face usually produce a moderately impervious upstream seal.

4.3    Tailings Deposition

Generally, tailings slurry is  transported through pipelines from the mill to the tailings impoundment
for deposition.   Once the tailings reach the impoundment, a variety of options may be employed to
deposit the tailings.  In determining which method is best suited for a particular operation, tailings
engineers (generally civil engineers specializing in the disposal of mine tailings) study the
characteristics of the tailings materials, the deposition cycle, and the climate.  They will also consider
the impoundment layout and the embankment design.  In the discussion thiit follows, it is assumed
that the embankment is not of the water-retention type, and that the tailing* will be used to provide
most of the material for construction of the embankment.

Three general methods of tailings deposition are typically recognized:  single point discharge,
spigotting, and cycloning. There are variations on all these methods and die methods may be used in
combination to meet the design criteria set by the tailings engineers.

4.3.1   Single Point Discharge

Single point discharge is the technique of discharging  tailings from the open end of a tailings pipeline.
This method is often employed at impoundments that discharge tailings sluiTy upstream of the pond
and dam (i.e., not from the  crest of the dam).  This technique is not appropriate when the pond
(and/or the fine fraction of the tailings) must be kept well away from the embankment.  Single point
discharge can also be used to discharge slurry into the dam, but this requires that the discharge point
be periodically moved to another section of the dam to prevent unequal raising of the dam sections.
Further,  the low surface area to volume ratio afforded by single point discharge makes this method
attractive in extremely cold  environments, where freezing of smaller discharge streams may occur
(Lighthall 1989).
                                               32

-------
                                                             Design and Evaluation of Tailings Dams
4.3.2  Spigotting

Spigotting is the technique of discharging tailings through small pipes (spigots) that originate from
multiple points at regular intervals along a tailings header line (Lighthall 1989).  The method is used
to achieve a more or less uniform flow of tailings, which in theory, will create uniform beaches.
However, the location of the discharge points may require rotation to create these uniform beaches.
Spiggotting  forms a gently sloping beach where the coarsest fraction settles near the point of
discharge and the fine fraction (slimes) is deposited progressively farther away from the discharge
points.  As a result of this variable gradation, the density, shear strength, and permeability of the
settled solids decrease with increasing distance from the discharge point.  As discussed above,  these
distributional characteristic could be very favorable in reducing the phreatic surface before and across
the embankment. However,  observations of actual particle size, permeability, and shear strength
distribution  with distance from the point of discharge suggest that  the smooth ideal gradation
theoretically achievable may  be rarely achieved in practice (Vick 1990, Lighthall 1989).
Nevertheless, consideration of the header tailings velocity, the solids concentration in the header and
spigot lines, and the point of discharge (among other factors) may allow the development of beaches
which provide structural stability to the main embankment while also creating a long seepage path
(providing consequent dissipation-of pore pressure) from the pond to the embankment  (Lighthall
1989).

4.3.3  Cycloning

Tailings sands (the  coarse fraction of the tailings) may be used to construct tailings dams  during active
deposition.  Mining companies typically view cost savings as the major advantage of using the coarse
fraction in this manner.  Since the sand is produced from the material to be deposited  (the tailings),
any costs related to acquiring borrow fill for the construction of embankments is eliminated or
significantly reduced.  This practice also reduces the overall volume of tailings to be deposited in the
impoundment, since at least part of the coarse fraction has been used in the dam construction.  The
method used to separate the fines from the coarse fraction in the total tailings slurry is cycloning.

Cyclones are simple mechanical devices used to separate coarse and fine particles from a slurry
through centrifugal  action. As the slurry, moving under pressure, enters the cyclone,  the fine
particles and most of the water rise to the top outlet.  The coarse particles spiral downward through a
conical section and  exit the bottom.  The separated fine fraction is referred to as  overflow and the
sand fraction is known as the underflow.  It is the underflow that is used to construct the tailings
embankments, while the overflow is discharged through a separate slimes pipeline to the
impoundment itself. The underflow and overflow should be monitored regularly to measure pulp
densities, gradation, and cyclone  inlet pressures. Adjustments of the cyclones are routinely required
to maintain pulp density and grain size objectives.
                                               33

-------
                                                            Design and Evaluation of Tailings Dams
Certain criteria should be considered when evaluating whether cycloning can be an effective tool in
the construction of a tailings embankment.  The cycloned sands should have a permeability that is
sufficiently higher than the slimes deposited in the impoundment such that the phreatic surface can be
adequately controlled in the dam. The sands should also allow quick drainage upon discharge to ease
handling and spreading of the sands. The volume of the cycloned sand recovered from the whole
tailings must be great enough to allow for dam raises as needed to mainuiin adequate volume  in the
impoundment for slimes.  If the volume of cycloned sand falls short of the amount needed for dam
raises, costs could increase as borrow materials are required to maintain .adequate impoundment
volume.  Tailings that contain less than 60 percent particles passing the number 200 sieve are
generally considered to contain  acceptable sand quality for use in cycloning.  Two-stage cycloning,
employing two cyclones in series, is often used to produce a sand fraction that contains less fines than
single-stage cycloning.

Two basic methods  of cycloning are hi common use for tailings dam construction: central cycloning
(or stationary cycloning) and on-darn cycloning.  A third method, hydraulic cell cycloning, is a more
sophisticated application that is  less  commonly used.  The central cycloning method establishes a
single permanent or semi-permanent high capacity cyclone at a strategic location,  often on a dam
                               a,
abutment higher in elevation than the projected dam crest. The cyclone underflow creates a tailings
sand stockpile for use in embankment construction while die overflow from the cyclone  is discharged
to the center  of the  impoundment. Earth-moving equipment moves  the tailings sand from the
stockpile to the embankment where  they dump and compact it.  The mechanical placement and
compaction results in sands with a high relative density. Therefore, the method is well suited for use
in areas susceptible  to seismic activity.

The on-darn cycloning system consists of several cyclone units set up on towers, skids, trucks,
scaffolds or suspended from cranes  established along the dam crest.  The number of cyclones is
determined by the size of the cyclones and the mill throughput.  The underflow sand from the
cyclones is deposited on the embankment face while the overflow is discharged to the impoundment.
The high pulp density underflow (typically 70 to 75 percent solids)  results in the deposition of steep-
sided sand piles at a slope of 3:1 to  4:1 (horizontal to vertical) on the slops of the embankment that is
under construction.   The cyclones are moved  as the sand cones raise the height of the embankment.
Normally the grade of sand placed by the cyclones does not vary with distance from the discharge
point.  However, this may differ between sites: Lighthall, et al.  (1989) rqported  that if high  pulp
density underflows  are used, tailings operators may sometimes lower the pulp density of the
underflow to wash out the cones rather than move the cyclones too  frequently.  This practice could
result in not meeting the grain size  objective for the face of the embankment.

The on-darn cycloning system is cost-effective since the sands are placed in their  final resting place
hydraulically and no mechanical action is necessary.  One disadvantage of '.his method is that the
nonmechanical placement results in  lower relative densities, ranging generally from 30 to 68  percent
                                               34

-------
                                                             Design and Evaluation of Tailings Dams
as reported in Lighthall, et al. (1989).  Although relative densities between 45 and 50 percent can
normally be achieved, relative densities below 30 percent are not uncommon. These low relative
densities may eliminate this method of deposition from use in areas of high seismic activity.

The hydraulic cell method deposits diluted cyclone underflow (i.e., sands) into bermed  cells on a
tailings embankment.  The tailings are cycloned at  a central cyclone and the water is added to the
underflow to ease pipeline transport to the cells on the embankment.  The solids in the  cells are then
allowed to settle before the excess water is decanted from the end of the cell  opposite the point of
discharge. Some mines use wide-track bulldozers to compact the sands in the cells during deposition.
Lighthall,  et al. (1989) and Mittal and Hardy  (1977) report that relative densities hi excess of 60
percent can be achieved with the hydraulic cell method and mechanical compaction.  Without
mechanical compaction, Lighthall,  et al. (1989) and Mittal and Morgenstern (1977) report that
relative densities of tailings  in excess of 50 percent can be achieved.

A major advantage of the hydraulic cell method is the achievement of high relative densities using
direct hydraulic deposition (and possibly mechanical compaction). The method  presents limitations
for use on narrow embankments since a relatively wide, flat embankment area is required for cell
                               *,
construction.  Furthermore,  fines should be limited to 5 to 10 percent in the cyclone underflow to
achieve highly permeable sands that allow quick drainage of water in the cell.  This limitation of the
fines component in the underflow may result in reductions in total overall sand recovery and, hence,
the reduction in sand available for dam construction.

4.4     Stability Analysis

From initial trial embankment design to final  site closure, the stability of the tailings embankment
remains an important consideration. The primary objective of the impoundment engineer is to
develop a reliable waste containment structure at the lowest possible cost.  Choices regarding
materials, slope angles, drainage control,  raising rates, etc., all affect the cost as well as the stability
of the structure.  Therefore, stability analysis  is performed to optimize the structure with respect to
cost and other objectives while maintaining reliability.

Slope stability analysis begins with an estimation of the reliability of the trial  embankment.
Typically,  the embankment designer proposes the internal and external geometry of the trial
embankment and then calculates the safety factor of the design.  Using detailed information on the
physical properties  of the fill material and estimates of the volume of tailings  and  water to be
contained in the impoundment, the phreatic surface is predicted.  The designer then examines a wide
range of failure modes (discussed below) to calculate the estimated stresses expressed at hypothetical
failure surfaces.  The safety factor for each failure  mode is then calculated by dividing the estimated
resistance of the embankment to stress along the failure surface by the stress load  expressed at the
failure surface.  With this process the designer can look at changes in design parameters and the
                                               35

-------
                                                           Design and Evaluation of Tailings Dams
resulting influence of the safety factor to arrive at the least-cost option consistent with safety
objectives (Inyang 1993).

Once impoundment construction has begun, the quality of information available for slope stability
analysis improves.  The above process may be repeated for each raise of the embankment, replacing
estimates of phreatic surface levels and the physical properties of fill materials with measured values
collected in the field (Mittal and Morgenstern 1974).  Based on additional safety factor calculations,
embankment design may be changed significantly before the structure is completed.

There are numerous methods for performing slope stability analysis. However, a more detailed
discussion of these methods is  beyond the scope of this paper.  Vick (1990) and CANMET (1977),
among others, provide much more detailed discussions. The following is a,brief discussion of flow
nets, used to determine seepage flow characteristics within an embankment.

4.4.1  Flow Net Analysis

In conducting stability analysis, flow nets can be used to estimate seepage direction and volume and
pore pressure at points within the'embankment (CANMET 1977).  A flow net is a graphical solution
of Darcy's law to show steady flow through porous media and is often ustd to show ground water
flow. The variables include flow characteristics (either in terms of flow or head), information on the
boundaries of the area to be modeled, and information on the hydraulic conductivity  within the area.
Boundary conditions are the characteristics of flow at the  edges of the system being modelled1.

In a flow net, a grid is formed by the intersection of flow lines (the path tliat an individual particle of
water flows through a region) and equipotential lines  (representing contours of head) (Freeze and
Cherry 1979).  According to Vick (1990), for most types of embankments, flow nets provide
conservative estimates of pore pressures within the embankment, with static pore pressure at a point
being roughly equal to its depth below the phreatic surface.

In working with seepage and pore pressures, understanding  of some basic definitions in terms of
hydraulic conductivity or permeability are necessary. Homogeneous meanss that hydraulic
conductivity (K) (or the coefficient of permeability) in the material (natural soil or the embankment) is
independent of position. Isotropic means that hydraulic conductivity is independent  of direction at the
point of measurement.  If hydraulic conductivity is dependent on position then the media is
heterogenous.  If hydraulic conductivity of a media is dependent on direction at the point of
measurement then the media is anisotropic.
    'Boundary conditions for a homogeneous isotropic media may be zero flow  (an  imperroeabk
 boundary),  constant  flow (constant  head boundary) or  a  water table (where  head approximate*
 atmospheric pressure).
                                               36

-------
                                                            Design and Evaluation of Tailings Dams
 In generating a flow net, certain assumptions are made to solve the equation, including that the flow
 is steady state rather .than transient (Freeze and Cherry 1979). For this reason, the use of flow nets to
 determine exact volumes of seepage may not be accurate due to the often transient and unsaturated
 flow conditions  at most tailings impoundments (Vick 1990).

 In homogeneous isotropic systems, (systems where hydraulic conductivity is the same throughout the
 media in terms of location and direction) flow lines and equipotential lines intersect at right angles,
 providing the graphical solution to Darcy's  Law.

 If the media  is homogeneous and anisotropic, the cross section (prior to the addition of flow lines) can
 be converted to  an isotropic system by a ratio of the vertical and horizontal conductivities2; the
 construction  the flow lines is then conducted perpendicular to the equipotential lines, as with true
 isotropic systems.  After the flow net is constructed, it can be transformed back into the original
 anisotropic system. (Freeze and Cherry 1979, CANMET 1977) For heterogeneous flow systems, a
 flow net can  be  constructed by sketching the different layers of hydraulic conductivity and by
 refracting flow and equipotential lines as they cross from one layer to another3.  Also, the same
 volume that exits one layer must enter the next layer. Typically, layers'with higher hydraulic
 conductivity  have relatively horizontal flow lines compared to layers of lower hydraulic conductivity
 with relatively vertical  flow lines.  (Freeze and Cherry 1979, CANMET 1977)

 Flow nets are generally effective for downstream and centerline dams,  which generally mimic
 homogeneous systems.   See Figure 11 for examples of typical flow nets for embankments  under
 various conditions. Due to complex permeability variations (complex heterogeneity) and boundary
 conditions, flow nets are not always realistic for upstream embankments.  Finite-element and other
 analysis can be used (Vick 1990). For additional information on the construction and use of flow nets,
 see CANMET 1977, Vick 1990, and Freeze and Cherry 1979.

 4.5    Failure Modes

 As noted above, calculation of the safety factor for a tailings embankment requires an analysis of the
potential failure  surfaces of the embankment.  There are a number of common failure modes to which
 embankments may be vulnerable. These include slope failure from rotational slide, overtopping,
 foundation failure, erosion, piping, and liquefaction.  Each failure mode may result in partial or
 complete embankment failure.
    Convert by the square root of the hydraulic conductivity in the vertical direction by the hydraulic
conductivity in the horizontal direction.
    3The tangent law is used; See Freeze and Cherry 1979.
                                              37

-------
                                                           Design and Evaluation of Tailings Dams
Decant
pond v.
>

Spigotted
tail ings be achN.
'. ... •.•••:..-. . ...-.
Tailings
discharge line
N

^

Starter dike
Internal
>^"""" drain
                                              (a)
                                              (b)
                                               (c\
                                               (d)
                   Figure 11.  Examples of Tailings Embankment Flow Nets

(Source:  CANMET 1977)

4.5.1  Rotational Sliding

Rotational sliding, so named because the failure surface appears as a segment of a horizontal cylinder,
may result in slope failures ranging from local sloughing of tailings at random areas along the face of
an embankment to massive  circular arc slides extending over the entire structure.  In general, for a
stable slope, the shear strength resisting movement along a potential failure surface exceeds the shear
stress tending to induce movement. Instability occurs when the shear stress on the failure surface
equals the shear strength (Vick 1990).  Specifically,  causes of rotational failure may include changes
in the water table, changes  in the permeability of the foundation materials,  disturbances to the
embankment caused by vibration or impact loading,  settlement of the foundation materials, etc
(CANMET 1977).

4.5.2  Foundation Failure

Foundation failures  are not uncommon among earthfill structures.  Where a weak layer of soil or rock
exists at shallow depth in the foundation below the structure, movement along a failure plane will
                                              38

-------
                                                           Design and Evaluation of Tailings Dams
occur if the earthfill loading produces stresses in excess of the shear strength of the soil in the weak
layer (CANMET 1977).

4.5.3  Overtopping

One of the most common causes of failure is overtopping by flood waters.  Overtopping typically
results when the volume of run-on entering an impoundment, from improper diversion of surface
water flows or excessive stormwater flow, exceeds the capacity of the impoundment.  Because tailings
embankments are constructed of highly erodible materials, the friction caused by  rapid flow over an
unprotected embankment crest may quickly erode a gully in the fill material, allowing sustained
release to occur.  Additionally, a rapid  increase in pore pressure associated with large stormwater
inflow may result in the liquefaction of unconsolidated impounded sands and slimes.  Sustained high
flow over the crest of an embankment can thus result in a major failure of the overall impoundment
within minutes (CANMET  1977).

4.5.4  Erosion

In areas of heavy rainfall, some form of protection against erosion is usually required.  Tailings
embankments may be  susceptible to erosion failure in two major areas, embankment abutments and
the embankment face.  Erosion along the contact line between the embankment and the abutment may
result from stormwater flow that concentrates there  (CANMET 1977).  Typically, this type of failure
is preventable with proper stormwater diversion methods and so results from faulty design or
maintenance.  Erosion of embankment faces may result from rupture in tailings lines  installed on the
embankment crest. Again,  maintenance (and alternate  siting of tailings lines) may prevent this type of
failure.

4.5.5  Piping

Piping refers to subsurface erosion along a seepage pathway within or beneath an embankment which
results in the formation of a low-pressure conduit allowing concentrated flow.  Piping may result
from seepage exiting the face  of an embankment with sufficient velocity to erode the embankment
face.  The resulting void space promotes progressive erosion extending upstream toward the source of
the seepage. In the worst case, the seepage may result in the creation of a direct channel from the
tailings pond to the dam face (CANMET 1977). Excessive piping may result in local or general
failure of the embankment or  the embankment foundation.

4.5.6  Liquefaction

Liquefaction is one of the most common failure modes of cross-valley dams. Because tailings
deposits typically comprise  unconsolidated, saturated deposits of similarly-sized grams,  they are
susceptible to temporary suspension in water (Vick  1990).  Liquified tailings may behave like a
viscous fluid, such that they may pass through narrow  openings and flow considerable distances
                                              39

-------
                                                             Design and Evaluation of Tailings Dams
(CANMET 1977).  Accordingly, even small dam failures may result in substantial releases of
impounded materials if those materials become suspended.

Factors affecting liquefaction potential include:

        •  Soil type - Uniform grain size materials, mostly in the fine sand sizes (the typical gradation
           of a tailings material), are the most susceptible to liquefaction.

        • Relative density or compactness - For a given material, the moire compact or dense it is the
          more resistant it will be to liquefaction.

        • Initial confining pressure at the time subjected to dynamic stress - This offers an
          opportunity in certain areas to prevent liquefaction by applying overloads to  loose deposits.

        • Intensity and duration of the ground shaking - Liquefaction may occur due to an intensive
          earthquake, or due to prolonged earth movement.

        • Location of the  water table - A high water able is detrimental.  Consequently, a tailings
          deposit constructed on a pervious foundation or a dam with a ptireatic line kept low by
          providing adequate internal drainage features may have a greatly reduced potential for
          liquefaction.  (Vick 1977)

By incorporating drainage facilities, maintaining a low pond surface, and compacting the fill materials
during construction, the density, saturation, and confining pressures can be controlled to reduce the
likelihood of liquefaction.  If the tailings embankment is constructed of fin; sands, compaction of
these sands will increase their density and reduce their susceptibility to liquefaction. Compaction to
obtain  relative densities of 60%  or greater  provides reasonable protection (CANMET 1977).
Therefore, provided embankment materials possess a relative density of 60% or greater, or provided
the phreatic surface is  maintained at a position well below the embankment surface, the embankment
can have a  sufficient factor of safety against liquefaction failure.  Design calculations generally are
needed to verify this for each individual dam.

4.6     Performance Monitoring

Routine monitoring and preventive maintenance are crucial in order to assure good performance of
tailings impoundments.  Monitoring can consist of visual observation of the: tailings embankment,
monitoring of piezometers  and other instrumentation.  Preventive maintenance, based on the early
observation of potential "trouble spots," can maintain the stability of the  structure, control seepage,
and contain costs.  Distress signals such as cracking, wet spots on the downstream face, and critical
settlement, all indicate deficiencies in the structure, but without proper instiumentation  it may be
difficult to accurately interpret the extent of the problem. Piezometers, pressure gages, and
inclinometers can be used to show developing trends in the  behavior of the deposited materials.  The
observations made from these instruments, combined with disposal operation logs which show dates
                                               40

-------
                                                            Design and Evaluation of Tailings Dams
 and locations of deposition, meteorological conditions, etc., can help analyze the situation.  (Vick
 1990)

 Instrumentation should be installed in the embankment or its foundation to monitor changes which
 may be critical to stability,  and in order to help predict unstable conditions. Instruments can be
 installed to measure pore water pressures, seepage flows, embankment movements, and total
 pressures.

 Pore water pressure in soils may be measured with piezometers.  The Casagrande piezometer, a
 simple and effective piezometer, has a porous ceramic stone element and is designed to measure
 pressure changes with a minimum lag time. It is installed in a hole drilled into the embankment or its
 foundation, and water levels are measured by a probe lowered down the hole.  Similar types can be
 installed using porous plastic, porous bronze, perforated steel casing, or steel casing and well points.
 Hydraulic and electrical piezometers are also  available and can be installed at various levels in an
 embankment.  These piezometers are generally more complicated to operate, and their reliability over
 long periods requires  great care  in fabrication and installation. When encountered, seepage flow
 emerging downstream from the embankment, can be collected and directed to a weir for flow
                               t,
 measurements.  Records of seepage flow will indicate when significant changes occur and permit an
 evaluation of potential problems  from piping.

 Simple methods for measuring embankment movements can be utilized.  Markers can be installed on
 the surface aligned in a straight line-of-sight to permit rapid detection of horizontal movement during
 periodic surveys. Successive measurements between two pegs spaced either side of a crack will
 indicate any widening and acceleration in separation rate. A more advanced device for measuring
 horizontal movement  is the slope-indicator. For this device, telescoping cylindrical casing is installed
 in the embankment during construction.  The sensing element is lowered down grooves inside the
 casing and measures the slope of the casing in two directions at right angles. From the measured
 slopes, the horizontal  movements occurring over the length of the casing can be calculated. Surface
 settling can be measured through the use of leveling or temporary benchmarks.

 The frequency of monitoring will depend on previous observations and the critical nature of the
 parameters.  In most instances, frequent observations during and immediately after completing
 construction phase is important.  When records indicate that conditions  are relatively stable, frequency
 of observations can be extended.  In some instances, measurements may be needed only after the
occurrence of unusual conditions such as heavy surface runoff, peak floods, or seismic activity.

The characteristics of the tailings and the construction method may change substantially over the years
taken to construct the  dam.  These changes can alter the conditions governing the stability  of the
embankment.  Changes may take place in crest levels, water levels, embankment slopes, cross-section
geometry, seepage conditions, and material characteristics.  A continuous program of inspection and
                                              41

-------
                                                            Design and Evaluation of Tailings Dams
maintenance is necessary from the beginning of deposition throughout the life of the dam.  Through
careful monitoring, areas of concern may be noted and quickly repaired, thereby preventing failure.
In addition to monitoring the stability of the dam, the performance of liners and drainage systems can
be evaluated. Monitoring wells are useful in monitoring seepage.
                                               42

-------
                                                          Design and Evaluation of Tailings Dams
5.     WATER CONTROL AND MANAGEMENT

As discussed throughout this paper, the ultimate purpose of a tailings impoundment is to contain
tailings in a cost-effective manner that provides for long-term stability of the impoundment and long-
term protection of the environment.  Water control and management are perhaps the most critical
components of tailings impoundment designs and operation. The failure modes discussed previously
are all related to water in the impoundment and/or the embankment. Similarly, the environmental
impacts of tailings and impoundments are related to water control and management, either directly, as
in the cases of ground or surface water contamination, or indirectly, as in the case of airborne
transport of dry tailings.  Water has been discussed  in the previous section in terms of stability; in
this section, it is discussed in terms of environmental performance. Most recently, environmental
issues have come to the forefront of tailings impoundment design, with special concerns over the
quality of effluent and seepage from tailings impoundments, both to ground water and surface water.
This concern has lead to both an increase in treatment of especially toxic tailings effluent prior to
discharge and more effort toward total containment of the tailings water within the impoundment.
The latter effort (i.e., containment) is a challenge  that has not been overcome: according to Vick
(1990), some  methods of seepage control are more effective than others; however, "'Zero discharge,'
even with the use of impoundmeHf liners, remains an elusive goal."

5.1    Surface Water

Control of surface water is one of the major factors  involved in design and operation of a tailings
impoundment.  A mass balance approach to water management can be used, with variables
categorized into outflows and inflows. Outflows from a tailings impoundment include overflows,
evaporation, recycle and re-use, and seepage.   Overflows are dependent on the dam's storage capacity
and the runoff volume of a storm event in the basin. Evaporation rates are a function of the climate
and the surface area of the freewater pond and saturated tailings.  Recycling and re-use volumes
depend on the operation's capacities and needs. Seepage can exit the dam as ground  water or seepage
through or under the embankment.  This section describes the surface components of water flow into
and out of the impoundment.  Subsurface flows are  described in a later section.  Both surface and
subsurface components interact in a dynamic fashion and must be considered together in any analysis.

5.1.1  Surface Water Evaluation

Estimation of surface water inflows and outflows using a mass  balance approach includes both natural
and man-made components.  Variables include precipitation (including storm events), evaporation,
run-on (including flood events), the liquid component of the tailings as it is discharged  to the
impoundment, water returned to the impoundment from any downstream seepage return systems,
evaporation, infiltration, decanting and recycling tailings water, and any direct discharge (overflow).
Ferguson et al.  (1985) also include discharge to the  free water pond resulting from tailings
consolidation.
                                              43

-------
                                                           Design and Evaluation of Tailings Dams
Precipitation data, topographic maps, streamflow measurements, and snow-depth data are used during
impoundment design to prepare hydrographs and frequency, curves for use in estimating volumes of
precipitation and runon anticipated.  Hydrographs, used for ultimate flood designs, determine changes
in inflow rates and maximum flow rates.  They illustrate stream discharge versus time for storms of
various intensities and durations.  Hydrographs are composed of interflow, surface water runoff, and
baseflow (flow attributed to shallow ground water).  Factors affecting hydrograph shape  and height
are rainfall intensity, distribution and duration; basin size, shape and drainage pattern (e.g. dendritic
or trellis); and vegetation patterns.

Peak inflow rates are affected by rainfall intensity and are indicated on a hydrograph as the  crest.
Rainfall intensity is indicated by the slope of the rising limb.  The direct iiinoff area is the area  under
the hydrograph minus the baseflow. The baseflow  is indicated at the point where the hydrograph
changes slope (inflection points).

Frequency curves,  used  for return-period flood designs, allow the designer to determine  discharge
rates of a design storm.  Snowpack depth is incorporated into dam design:; in areas with large
snowfalls or fast snowmelts.  Avalanche frequencies in the area are considered in the design as
appropriate. Rules of thumb are that freshly-fallen snow has a water content of 10 percent while
spring and compacted snow have a water content of 30 percent by volume. The importance of
containing seasonal rapid snowmelt is worth emphasizing. The Bureau of Mines states that lack of
sufficient snowmelt capacity is believed to be one of the major factors responsible for the Summitville
leach pad failure, and tailing ponds are similarly vulnerable.

Modelling and analysis can be used estimate the volumes of naturally occurring inflows  and outflows,
such as precipitation and evaporation. Methods for estimating some of the major naturally  occurring
inflows and outflows are summarized below; additional inflows and outflows, which have an element
of human control,  are described in the water controls section.

Storm Events

Runoff volumes  can be calculated through precipitation, discharge, and vegetative data of the area.
Precipitation data from wet and dry years are used to provide minimum,  average, and maximum
runoff volumes for determining storage capacity  and control structures for the dam.  Calculations
generally include a time continuum because the dam surface area will incraise and the drainage area
will decrease as  more tailings are deposited into the impoundment. Hydrographs and several
computer models,  such  as HEC (Army Corps of Engineers Hydrologic Engineering Center) and
SWMM  (Storm  Water Management Model), are available for calculating ruaoff volumes. (Huber
1993)

Large volumes of  rainfall and snowmelt in a short period of time can result in erosion of access
roads, dike damage, contamination of surface water, and catastrophic failure  of a tailings dam.  A
                                               44

-------
                                                            Design and Evaluation of Tailings Dams
 dam design includes plans to contain or mitigate runon volumes and rates associated with a flood.
 The type of flood used in a design depends on impoundment size, dam height, and the consequences
 associated with death, economics, and environmental damage.  Designs provide protection from a
 return-period flood (e.g. 100-year) or an ultimate flood (defined as the maximum volume of runoff
 from a single event). A flood design involves the determination of rates and volumes associated with
 inflows and outflows in a dam as a function of time. Because tailings impoundments are intended for
 permanent disposal (i.e., over 10 or  100 years, the most common return intervals used), it may be
 appropriate to consider much longer return intervals (and/or extended care).

 Infiltration

 Infiltration rates are generally low because of the small particle size and low permeabilities  in the
 tailings.  Infiltration rates are a function of a soil's moisture content, capillary pressure, unsaturated
 hydraulic conductivity, and the distance below the surface.  There is no runoff or ponding when the
 infiltration rate is less than the saturated hydraulic conductivity.  Runoff or ponding occurs  when the
 infiltration rate is larger than the infiltration capacity and the saturated hydraulic conductivity.
                                *
 Evaporation                    *•

 Evaporation is  a function of wind velocity, atmospheric pressure, temperature, and areal extent of
 surface water.  In general, it is proportional to the surface area of the free-water pond.
 Impoundments  in arid areas are designed to conserve and recycle water for mining processes during
 the mine's active life.  Evaporation data for certain areas are available from NOAA.  Pan evaporation
 tests can be used to determine evaporation rates if the site is not located in a basin monitored by
 NOAA.  In essence, the pan evaporation test monitors daily water loss in a Class A pan (four feet in
 diameter and ten inches deep) which is mounted one foot above the ground.  A pan coefficient (0.64
 to 0.81) is used to adjust pan evaporation rates because they will be higher than normal lake
 evaporation rates.  When the evaporation rates for a basin are known, the designer can determine if
 surface area dimensions will provide the required evaporation rates. Because net evaporation,  like
precipitation, is not constant from year to year, it may be beneficial to reduce the calculated
evaporation rate by a safety factor to account for annual variability.

5.1.2  Surface Water Controls

Each site requires a slightly different network of surface water controls because of differences  in
topography, climate, hydrology, geohydrology, etc. Most controls are a combination of storm event,
flood event, seepage control, recycling, and dewatering processes.  Methods for control can be first
used in the design phase by siting the impoundment as far up-valley as possible.  One step in
minimizing the volume of water in and seeping from the impoundment can be accomplished by
minimizing runon from outside sources through diversion of existing streams and run-on. This will in
turn reduce size requirements for the impoundment.  The storage capacity of a dam affects the size of
                                               45

-------
                                                            Design and Evaluation of Tailings Dams
runoff control structures, applicability of some control structures, embankment size, and safety factors
of a design.  In turn, it is affected by the velocity, volume,, and frequency of runoff in the basin.  In
general, the inflow plus the storage available in the dam has to equal the outflow from the dam.  The
maximum storage occurs when the inflow equals the outflow.

In some cases, storm flows are managed by increasing the freeboard in the impoundment during
design; however, this results in additional water in the impoundment available for seepage. Using
freeboard may be economical in semi-arid areas where flooding occurs infrequently and the mine
requires a large amount of water for processing streams.

The principal methods for controlling runon are catch basins and check dams, and diversion ditches
(channels and pipes).  Catch basins stop surface water from entering the railings impoundment area
but generally require some method of by-passing the tailings impoundment such as decant systems or
diversion ditches.  Catch basins may be expensive because of labor and fill material but can be cost-
effective for small runoff volumes. Treatment of the water may not be mscessary because the water
never enters the tailings impoundment itself.  Water rights claims and environmental effects are
important aspects of this alternative because the frequency and volume of water releases from the
                              t,
catch basin will affect downstream areas.

Decant systems are generally used in conjunction with other forms of surface water control. Major
costs associated with the decant systems are pumping, maintenance, and treatment costs.  It may be
difficult,  in areas with large surface water runoff volumes, to provide enough wells for removal of the
runoff hi a timely manner.

Diversion channels (open and closed) can be used for most dam  designs, especially valley-bonom dam
designs.  Closed channels (pipes) are usually used under cross-valley dams; because the dams
generally do  not permit  a side  channel for diversion.  Water treatment is not an issue  with diversion
channels if they begin diverting the runoff above the dam. However, the long-term viability of
diversion channels must be considered in design.

Spillways generally are designed as temporary structures because they will change (i.e., be moved or
increase hi length) as raised embankments increase in height.  They are constructed of an impervious
material able to withstand rapid flow velocities.  The spillway also is designed to contain and control
hydraulic jumps that occur at the bottom of the spillway.  In addition, a spillway design has to
consider and plan for water treatment if the surface water runoff passes through the tailings dam.

5.2    Tailings Seepage

As discussed previously, flow  nets and other analytical methods can be used to calculate seepage
volumes.  A less conservative  method for estimating seepage is use of a nuiss balance approach.
                                               46

-------
                                                            Design and Evaluation of Tailings Dams
assessing each of the potential inflows and outflows to determine overall water movement (Ferguson,
et al. (1985).

5.2.1  Seepage Flow (Direction and Quantity)

Seepage is the movement of water (contaminated and uncontaminated) through and around the dam
and impoundment.  Primary factors affecting the volume of seepage present in a system are depth to
the ground water table and infiltration capacities of the unsaturated zone and tailings.  The quantities
and water quality of the seepage affect the types of controls that are incorporated in the dam design.
(Vick 1990)

Historically, controlled seepage through embankments has been encouraged to lower the phreatic
surface and increase stability.  Evaluation of the volume and direction of seepage is conducted using
hydraulic principles similar to those used in embankment design.  The same variables that are used
during the design phase to  predict the phreatic surface can be used to estimate the volume of seepage
flow. Similarly, variables, such as permeability of the embankment and foundation, that might affect
the phreatic surface also affect seepage rates and volumes.  However, more exact and extensive data
may be required than for calculation of pure pressures for analysis. Flow characteristics of tailings
impoundments, their foundations, and underlying soil can be viewed as an  inter-related system, with
both saturated and unsaturated components.

Seepage evaluation can require information on: (1) components from geologic, hydrologic, and
hydrogeologic studies, and (2) physical and chemical characterizations of surface water inflows,
seepage, and tailings.  Geologic  factors affecting seepage are fractured rock, clay lenses, and uplifted
geologic formations with large differences in permeability.  Hydrologic data is affected by rainfall
intensity, soil type, and surface conditions.  This data can be used to calculate infiltration rates.
Hydrogeologic studies  can  determine:  (1) the critical path and degree of anisotropy of the ground
water, (2) the boundary conditions for ground water flow evaluations, (3) the moisture content,
permeability, and porosity  of the tailings and underlying soil, (4) the thickness of the unsaturated zone
and capillary fringe, and (5) the  storage capacity, hydraulic conductivity, and transmissivity of the
tailings and underlying aquifer.  Flow nets and more complex models of seepage flow can be
prepared.  A mass balanced approach can also be used and is presented by Ferguson et al. (1985).
For additional information  on the determination of seepage volumes and direction, see Vick (1990),
CANMET (1977), and Ritcey (1989).

5.2.2  Seepage Quality

The chemical composition  of tailings seepage is important in determining potential environmental
impacts.  Factors include waste characteristics such as mineralogy of the host rock and milling
methods used to produce the tailings, and the interaction of the tailings seepage with the liner (if any)
and the subsurface. (Vick 1990)
                                               47

-------
                                                            Design and Evaluation of Tailings Dams
Contaminant mobility can be increased by physical mining processes such as milling (a small grind
results in increased surface area for leaching).  Most mining companies manipulate pH and use
chelating agents to extract minerals from the ore.  These same processes can be applied to the fate
and transport of contaminants in tailings. While many heavy metals are hydrophobic with strong
adsorption tendencies for soil, the chemical reagents used in mining processes may be present in the
tailings material.  They are able to desorb the metals, making them mobile in leachate or surface
waters.

Contaminated water may be formed from downward migration of impoundment constituents or
ground water movement through tailings.  Most contaminant transport in ground water systems is
from the advection (fluid movement and mixing) of contaminants.  Factors affecting the rate of
advection include ground water/leachate velocity, chelation, pH, and partition coefficient values.  The
geochemistry of the aquifer, physicochemical properties of the tailings and seepage will determine the
buffering capacity of the soil, types of chemical reactions (precipitation or neutralization) and the rate
of adsorption and ion exchange.

A related problem is the production of acid by oxidation of thiosalts, which is a problem for some
metal mines hi eastern Canada.  The bacterial culprit is thiobacillus thiooxidans. Thiosalts may be
removed from the mill effluent by biological treatments (Guo and Jank 1980, quoted by Vick 1990).

According to Vick (1990), neutralization, oxidation/reduction, precipitation adsorption, ion exchange,
and biological reactions play a major role in the chemical composition of tailings seepage. These are
many of the same reactions used hi milling operations to free the desired mineral.  Seepage quality
can be modeled using complex geochemical methods.  Vick (1990) and Ritcey (1989), among others,
describe the methods in some detail.

5.2.3  Seepage Control

There are two basic options for controlling contaminated water hi  impoundments:  keeping it in the
impoundment or capturing it after it exits the impoundment.  Seepage controls are typically evaluated
in the early phases of impoundment design.  The objectives are to maintain embankment stability,
decrease water losses, and maintain water-quality at the site. Options for seepage control include
installation of liners beneath the entire impoundment (to contain water and to exclude ground water),
constructing drains for seepage collection, constructing seepage collection sind pumpback (or
treatment) systems, sometimes in conjunction with low permeability barriere, construction of low
permeability embankments  and embankment barriers (i.e., cores and liners), dewatering of tailings
prior to deposition, and decreasing hydraulic head by locating the  free-water pond away from the
embankment.  Some of these techniques are described in more detail below.
                                               48

-------
                                                            Design and Evaluation of Tailings Dams
Liners

Liners have not been^incorporated into tailings impoundment designs until the last decade or two.
Even now, due to their high cost, mining companies tend to avoid the use of liners under an
impoundment.  Although liners may be used to seal the upstream face of a tailings dam, most tailings
impoundments  in use today do not contain a lining system.  The two major types of liners used to
control flow through tailings dams are synthetic materials, which are very expensive, and constructed
liners made of local clays or other readily available materials. Slimes are also sometimes used as low
permeability barriers.

Areal coverage needed for the impoundments is a major cost consideration, especially for cross-valley
dams.  Thicknesses vary depending on the liner type but  most thicknesses can be decreased if they are
overlain with a drainage system to collect fluids, which reduces the hydraulic head (and stress) on the
liner.  An underdrain or vents may be necessary to remove sub-grade vapors that might otherwise lift
the liner and to prevent ground water infiltration into the tailings.  Liners have to be resistant to
constituents in the tailings and seepage (such as acids or caustic substances), weathering if exposed to
ultraviolet radiation, deformation from loading stresses, and seismicity.
                               *,
Clays and synthetic liners can be combined to form double and triple liners.  To prevent large
settlements, clay and synthetic liners are  not placed over  loose or easily compressed material.
Designs usually incorporate covers to mitigate the effects of sunlight, wave, and wind exposure on
clay and synthetic liners, and drying on clay liners.  The effects  of frost action and drying are
incorporated as needed into a liner design, especially for  dams with sloped bottoms.  Leakage can
occur through synthetic liners because of shrinkage, faulty seam  construction, stress loading,  exposure
to ultraviolet radiation, or improper planning and construction of the sub-grade.  Short-term
maintenance plans are generally implemented, because  many problems often occur within the first six
months of operation.

Clay Liners

Clay can be an  inexpensive option for liners, especially in areas  with a natural abundance of this
material. Clay  liners vary in thickness at least two feet, provide permeability of 10"6 cm/sec or less.
and undergo physical-property tests such as permeability, Atterberg limits, moisture content,
compaction, shear, and compression.  The Standard Proctor compaction test, the most commonly used
test, compacts the soil by a drop hammer in a standard mold.  (The soil is compacted in three even
lifts, using 25 blows per lift from a 10-lb hammer dropping  freely through 18 inches.) From the
compaction curve, the water content vs. dry unit weight,  and the optimum moisture content can be
determined. The optimum moisture content produces the maximum dry unit weight for the materal
The primary factors affecting compaction characteristics are  soil  type and compaction energy.
                                               49

-------
                                                            Design and Evaluation of Tailings Dams
The density of a clay liner depends on its mineralogy and the method and degree of compaction.
Clay can be compacted to a prescribed moisture content and density to provide a permeability of 10"6
to 10'7 cm/sec or lower.  Grain-size distribution curves may be used to determine the amount of fine-
grained material in the clay.  In general, a high-plasticity clay will be more desirable than a low-
plasticity clay because of its lower permeability, but construction and the climate of the site may have
an effect on the decision.  Chemical tests are undertaken on the clay material to determine if it is
resistant to the seepage produced by the tailings dam. Clay liners may be supplemented with other
liners (e.g., synthetic) to further reduce potential seepage.

Clay liners can fail when their permeability increases considerably above the design value.  According
to Van Zyl, et al. (1988), the three major causes of failure  are differential settlement of the
foundation,  causing localized cracking of the clay liner;  drying of the clay liner (desiccation), leading
to the development of microcracks (that can occur in areas  lined with clay too long in advance of the
time when wet tailings will cover the  liner or if the tailings dry after deposition);  and alteration of the
liner permeability, due to geochemical reactions between the liner and leach solution.

Synthetic Liners
                               t,
Synthetic liners are a relatively new development in the control of seepage in tailings impoundments.
Of the rigid liners, concrete (rarely used) and gunite may be susceptible to acid and/or sulfate attack,
and asphaltic concrete may have questionable weathering and sun-aging ctiaracteristics  (Kays 1977).
Sprayed membranes  have demonstrated installation problems which may  need to be resolved before
being considered as a possible option. Synthetic rubber membranes (butyl rubber, EPDM) may be
too costly for tailings impoundments (Vick 1990). Vick provides a discussion on some of the specific
characteristics of these materials, their design, and effectiveness.  These thermoplastic  membranes are
the most common liners considered for tailings impoundments.

Estimates of seepage through a liner can be made using Darcy's Law.  Non-rigid liners are often
grouped into a category called geomembranes.  Geomembranes are often used in conjunction with
clay liners to form a double or triple  liner combination.  Seepage losses through geomembranes are
estimated on the basis of flow through a hole in the  geomembrane.  Most synthetic liners are resistant
to acids, bases, and salts present in tailing dam seepage. Permeabilities for the liners are generally
10'' to 10'w cm/sec with average thicknesses  of 40 to 60 mils (CMA 1991). As noted elsewhere, both
the cost and technical feasibility are major factors in selecting synthetic liners, given the  large size
and uneven terrain usually encountered.

Slimes
                                                                 •
Tailings slimes are easy and inexpensive to install as low permeability layers to slow but not stop
seepage.  To be cost-effective, the  slimes must constitute a majority  of the whole mill tailings and the
coarse and fine sands must be cycloned out of the slimes.  In addition, there should be a system in
                                               50

-------
                                                            Design and Evaluation of Tailings Dams
place to guarantee even distribution of the slimes in the tailings pond (using rear, forward, and side
spigots).  Slimes are often used to line the upstream face of tailings dams (or lifts).  Although slimes
may offer a low-cost alternative to other materials, they have several disadvantages that are discussed
in Vick (1990) and Ritcey (1989). In addition, it is difficult to determine long-term permeabilities of
the slimes.

Embankment Barriers

Embankment barriers are installed below the impoundment and include cutoff trenches, slurry walls,
and grout curtains. An impervious layer of fill is generally required between them and the tailings.
Barriers are installed underneath the upstream portion of a downstream embankment and the central
portion of centerline embankments; they are not compatible with upstream embankments.  A good
water-quality monitoring program is needed when using embankment barriers to ensure that they are
completely effective in intercepting flows and also that seepage is not moving downward and
contaminating the ground water.

Cutoff trenches, usually 5 to 20 feet in depth,  are the most widely used type of embankment barrier
for tailings dams,  especially in areas with large volumes of natural clays.  Dewatering may be
necessary during the installation of cutoff trenches when they are installed below the ground water
table.

Slurry walls are narrow trenches that are best suited to sites with a level topography and containing
saturated or fine-grained soils.  They are not compatible with fractured bedrock systems.  The slurry
walls are installed by excavating a trench to a zone of low permeability material and filling the trench
with a soil/bentonite slurry which is then allowed to set to a consistency of clay.  Depths average 40
feet and permeabilities obtained can be as low as 10~7 cm/sec.

Grout curtains use cement, silicate materials, or acrylic resins as a barrier to seepage movement.
They are limited to sites with coarse-grained material (medium sands to gravel or fractured rock with
continuous open joints) and can extend to depths of more than 100 feet. Permeabilities obtained can
be as low as 10~8 cm/sec.  However, leaks can occur through  curtain joints or by subsequent corrosion
of the curtain. (Vick 1990)

Rather than simply intercepting and containing seepage flows, barriers may have gravel (or other
pervious material, appropriately filtered) drains immediately upgradient to allow seepage to be
removed or directed to embankment underdrains. Barriers and seepage collection systems also may
be used downgradient of embankments to prevent further environmental releases.
                                               51

-------
                                                            Design and Evaluation of Tailings Dams
Pumpback Systems

Pumpback systems consist of seepage ponds and/or seepage collection wells installed downgradient of
the impoundment that are outfitted with pumps that send seepage back to the impoundment or for use
as process water.  Current practices include the use of toe ponds or seepage ponds to collect seepage.
In some cases, underdrains or toe drains are designed to flow into the seepage pond. In other cases,
however,  these systems are installed after construction of the impoundment as a remedial action to
collect unanticipated seepage.  These units may be used in conjunction with slurry walls, cutoff
trenches or grout curtains to minimize downgradient seepage.  Depending on effluent quality,  the
operation of the pumpback system may  continue indefinitely.

5.3    Tailings Water Treatment

Tailings ponds can be effective in clarifying water prior to discharge. Many factors influence the
effectiveness of the pond to provide sufficient retention time to permit the very fine fractions to settle
before reaching the point of effluent discharge or time for unstable contaminants to degrade.  Factors
affecting settling time are the size of grind, the tendency to slime (particularly with clay type
minerals), pH of the water, wave action, depth of the water, and distance between the tailings
discharge and the effluent discharge.  Although settling  velocities of various types and grain sizes of
solids can be determined both theoretically and experimentally, many factors influence effectiveness
of the decant pool as a treatment device.

The grind required to liberate the valuable mineral is usually under the #200 sieve. Particles in the
range of 50 /im with a settling rate of 0.05 in/sec (0.12 cm/sec) can be affected by grind action but
will settle in a reasonable time.  Particles of 2 /*m or less can cause a turbidity problem.  Such
particles have settling rates of less than 0.01 in/sec (0.025  cm/sec) in still water and, under conditions
prevalent in most tailings ponds, require several days to settle due to the turbulence caused by wave
action.

Observations of existing ponds has led to general rules for clarification.  ITie pool should provide 10
to 25 acres of pond area for each 1,000 tons of tailings  solids transported each day and should
provide 5 days retention time.  An average of  15 acres per 1,000 tons is usually considered adequate
(CANMET 1977).
                                                52

-------
                                                            Design and Evaluation of Tailings Dams
6.      CASE STUDY:  STILLWATER MINING COMPANY TAILINGS IMPOUNDMENT

The following case study is presented as an example of the design elements required in constructing a
lined tailings impoundment.  The Agency did not evaluate facility-wide water balance changes before
and after liner installation.  Further, the Agency did not perform a cost analysis of the Stillwater liner
installation project. The decision to use a synthetic liner beneath the tailings impoundment at the
Stillwater Mine was based on site-specific factors.  While this application was technically feasible for
the Stillwater Mine, that may not be the case for other operations.

In the early 1980s, Stillwater Mining Company was planning for the development of a platinum and
palladium mine approximately 77 miles southwest of Billings, Montana. The State of Montana
Regulations require a mine to submit an application for hard rock mining and to obtain a permit for
hard rock mining before construction of the mine and mine facilities may begin (exploration activities
may continue during the permitting process).

The design for engineering report for the Stillwater tailings impoundment was submitted to the
Montana Department of State Lands in February  1987.  Its purpose was to present comprehensive
information on all the activities that had been conducted at the site in relation to the design of the
future tailings impoundment  and to present the design to accommodate the engineering criteria
developed as a result of the site evaluation, the tailings characteristics,  the environmental regulations
and future operations.  The report included a scope of work that indicated the various tasks that had
been completed in the conduct of the study. These tasks were listed as follows:

        •  Prepare design basis memoranda of the project design criteria,

        •  Supervise soil drilling, test pit excavations, and field density testing.

        •  Prepare and administer laboratory test programs for soils and tailings.

        •  Perform static and pseudo-static stability analyses and  estimate the seismically-induced
          deformations of the dam due to the Maximum Credible Earthquake event.

        •  Perform hydrological studies to determine design flood runoff to the impoundment and
          water profile curves on adjacent natural waterways resulting from designated flood events.

        •  Perform reclamation studies to design a tailings drainage system.

        •  Select appropriate impoundment liner materials.

        •  Estimate construction material quantities and prepare construction sequencing curves
          showing required  embankment crest elevation and tailings elevation versus time.

        •  Prepare inspection,  maintenance, and contingency plans.

        •  Prepare design drawings of the initial, final, and  reclaimed impoundment stages.
                                              53

-------
                                                            Design and Evaluation of Tailings Dam:
        •  Prepare an engineering report.

        •  Prepare plans and technical specifications sufficient for construction permitting.

6.1     Site Evaluation, Field Exploration and Laboratory Tests

6.1.1   Site Evaluation

The consultants responsible for all aspects of the tailings impoundment d<;sign performed their first
reconnaissance of the site in August 1983.  The purpose of this visit was to observe the foundation of
the proposed tailings disposal area, determine if evidence of potential landslides and faulting existed at
the site or in the vicinity of the site and to search for materials that could be used in the construction
of the impoundment.  The results of this reconnaissance, and previously collected information from a
past drilling effort, indicated that the foundation beneath the proposed site was composed of pervious
materials, gravels and boulders in a silty sand matrix.  Prominent unweathered granite outcrops were
noted as abutments to the tailings impoundment dam. Landslide materials were noted above the
tailings impoundment area but were determined to be stable based on the natural slope and the lack of
evidence of instability (ground cracking and leaning trees). Faulting and shearing were noted in the
granite outcrops immediately west of the proposed impoundment, the geologist conducting the
reconnaissance indicated that the fault was not active and will not have the potential for cracking of
the tailings pond  lining.

6.1.2   Field Exploration

A seismic refraction survey conducted in the impoundment area in 1983 determined the depth of
bedrock to range from 31 to 226 feet below ground surface in a trough-shiiped valley.

Test pits excavated up to 22 feet below ground surface in  1983 and 198S explored ground conditions
in the pond and dam foundation areas. In-place field density tests were conducted in 14 of the pits,
nine in the location of the proposed dam foundation. The upper one to two feet of the  test pits
consisted of brown silty and sandy soils and below this  soil horizon the miterial in the  pit was largely
composed of sand, gravel, cobbles and boulders with only 2 to 17 percent silty fines.  Building rubble
(left from a previous mining venture), abandoned pipelines and other non-native materials were
uncovered during the excavation of the pits. The average dry density of the soil in the bottom of the
pits was determined to be 130 pounds per cubic foot. The results of the seismic refraction surveys
indicated that soil densities increased below the bottom  of the test pits.

Eight monitoring wells drilled in the impoundment area between 1979 and 1983 provided baseline
ground water information and foundation conditions.  The ground water surface ranged from 40 to
100 feet below the ground surface, but bedrock in the western portion of die proposed  impoundment
was found to form a ground water boundary and wells located west of this area were dry.   Five soil
borings ranging from 54 to 74 feet deep were drilled into  the foundation area.  Standard Penetration
                                               54

-------
                                                            Design and Evaluation of Tailings Dams
 Test (ASTM D-1586) was used during the drilling, but the results were used only to qualitatively
 evaluate the density of the sands and gravels.  Representative soil samples removed during the drilling
 were sent for laboratory evaluation.

 6.1.3   Laboratory Tests

 Laboratory tests of the borrow materials to be used in the proposed embankment and the foundation
 soils included grain size analyses (both sieve and hydrometer), Atterberg  limits, natural moisture
 contents and specific gravity.  Atterberg limits tests indicated that the fines display little to no
 plasticity.  Natural moisture content was determined to range between 1 and 7 percent.  Triaxial
 compression tests were also performed on borrow materials to be used in embankment design.  The
 resulting strength parameters were used in preliminary stability analyses.  Consolidated-undrained
 triaxial compression tests with pore pressure measurements were performed on recompacted samples
 of embankment borrow materials and foundation materials.

 In the triaxial compression tests, foundation soil samples recompacted to the average foundation dry
 density determined in the field (130 pcf) were determined to have an effective angle  of internal
 friction of 35 degrees and an effective cohesion of zero.

 Laboratory compaction test results showed that the maximum dry density of the impoundment sands
 and gravels (embankment materials) range from 148 pcf to 159 pcf with optimum moisture contents
 ranging from 5 to  8 percent.  The high density  of the materials is attributed to their  high specific
 gravity (3.0 to 3.2).

 In the triaxial compression tests, the impoundment soil samples were compacted to 95 percent of the
 maximum dry density determined by ASTM D-698 (140 per).  The effective angle of internal friction
 was determined to be between 39 and 41 degrees with an effective cohesion of zero.

 Laboratory tests were also undertaken for tailings produced from a pilot grind on the mine site ore.
 Only fines were tested (cyclone overflow) since coarse tailings were to be deposited  underground.
 Gradation, Atterberg limits and specific gravity were determined for the sample as well as
 sedimentation tests to  determine the settled tailings density. Consolidation tests were conducted to
 estimate the variation of tailings density with depth and time-rate settlement characteristics.

 Mine waste rock was also proposed for use in the construction of the dam embankments, however, no
 results of field or laboratory testing were presented in the engineering report.  Results of visual
observations  noted that the rock was moderately well graded from fine rock dust to 24 niches,  with
the greatest proportion of materials in the 3 to 6 inch range. The rock was described as moderately
hard with angular sharp edges.  Debris (pipes, wood, plastic tarps and wire mesh) was noted mixed in
with the waste rock.
                                               55

-------
                                                         Design and Evaluation of Tailings Dams
6.2    Office Evaluations

The hydrology evaluations and stability analyses required for tailings dam design can be accomplished
using results of the field and laboratory tests as well as maps and published data and information.

6.2.1  Hydrology Evaluation

The Still water River flows approximately south to north just east of the tailings impoundment site. A
small tributary of the Stillwater River, Mountain View Creek, lies just south of the tailings
impoundment. The toe dike was designed to be located 200 to 300 feet west of the Stillwater River
and 50 feet north of Mountain View Creek.

The watersheds for both the Stillwater and Mountain View Creeks were estimated as well as the
tailings impoundment and tailings impoundment catchment areas. These  were presented in the
engineering report as follows:
Watershed
Tailings Impoundment
Catchment
Final Tailings Impoundment
Mountain View Creek
Stillwater River above
Mountain View Creek
Confluence
Drainage Area
*' 68 acres
35 acres
1 .48 square miles
191 square miles
Average Basin Elevation
550(1 feet

7300 feet
9000 feet
Flow records from the gaging station nearest the mine site with a long pen.od of record (located 25
miles downstream of the site) shows that the maximum recorded flow was 12,000 cfs.  The drainage
area at this location is 975 square miles.

The flood storage volumes for the impoundment were determined to size the impoundment to prevent
overtopping.  The design flood for the impoundment is based on size and downstream hazard
potential classifications as found in the U.S. Army Corps of Engineers "Recommended Guidelines for
Safety  Inspection of Dams".  Guidelines recommend that the design flood for this impoundment
should range from one-half the probable maximum flood (PMF) to the full PMF.  The one-half PMF
was chosen as the design flood for the impoundment at intermediate height* and the full PMF was
chosen for the impoundment at stages which exceed a height of 100 feet.

The PMF and one-half PMF estimates were determined for the Tailings Imi>oundment Catchment
Area, the Mountain View Creek Watershed and the Stillwater River Watershed above the confluence
with Mountain View Creek.  The Army Corp of Engineers' Hydrologic Engineering Center (HEO
                                              56

-------
                                                         Design and Evaluation of Tailings Dams
computer programs, used to determine flood hydrographs (HEC-1) and water surface profiles (HEC-
2), were employed in the estimation effort.

Other basic data for use in the PMF study were pulled from a number of sources.  The probable
maximum precipitation (PMP) for Six-hour local and 72-hour general storms were developed from the
"Hydrometeorological Report No. 55, Probable Maximum Precipitation Estimates - United States,
Between the Continental  Divide and the 103rd Meridian".  The PMP for 72-hour storms assumed
unlimited snowpack available for snowmelt since the maximized storms occur primarily from the end
of May through June (spring melt season).  Snowmelt estimates were based on the Army Corp of
Engineers' "Runoff from Snowmelt"  since actual data on local snowpack and snowmelt were not
available.  Temperatures and windspeeds during the PMP were calculated following the procedures in
the "hydrometeorologic Report No. 43, Probable Maximum Precipitation, Northwest States". Unit
hydrographs, infiltration and retention losses were developed from the Soil Conservation Service
procedures.

The results of the HEC-1 computer program determined the following results of the design floods, as
shown in Table 2.
                Table 2. Stillwater Mining Company Calculated Design Floods
Design Storm
PMF (72-hr. PMP plus
snowmelt) volume
1/2 PMF (72-hr. PMP plus
snowmelt) volume
PMF (6-hr, local storm PMP)
peak discharge
1/2 PMF (6-hr, local storm PMP)
peak discharge
PMF (72-hr. PMP plus
snowmelt) volume
1/2 PMF (72-hr. PMP plus
snowmelt) volume
Tailings
Impoundment
312 acre-feet
156 acre-feet




Mountain
View Creek


ll,230cfs
5,615 cfs
8,241 cfs
4,121 cfs
Stillwater River
above Confluence
•with Mountain
Vfew Creek




329,980 cfs
164,990 cfs
Stillwater River
below Confluence
with Mountain
View Creek




330,828 cfs
165,414 cfs
The HEC-2 water surface profiles computer program was used to determine the estimated maximum
water surface elevations and flow velocities for the PMF and 1/2 PMF peak discharges at the stretch
of the Stillwater River opposite the tailings impoundment.  The river sections (cross sections and
longitudinal sections) were assumed to be stable, with no scour or bank sloughing. This is of a
                                             57

-------
                                                           Design and Evaluation of Tailings Dams
conservative assumption since scour is likely to occur during a flood of PMF magnitude and the scour
would widen and deepen the channel.  The computed surface water elevations resulting from the PMF
on the Stillwater River were shown to locally exceed the design toe dike by 15 feet, however, this left
5 feet to the top of the toe dike.  The 1/2 PMF exceeded the bottom elevation of the toe dike by
about 4  feet and the distance left to the top of the toe dike was 16 feet.  The toe dike is beyond the
limits of the computed 100-year and 500-year flood plains.

Velocity calculations indicated that erosion would occur under PMF and 1/2 PMF conditions on both
the Stillwater River and  the Mountain View Creek.  The 1/2 PMF storm was not considered to be of
sufficient extent to cause total failure of the dam. The PMF storm was considered to create sufficient
erosion  to cause total failure of the dam.

6.3     Tailings Impoundment Design

At the Stillwater Mine, whole tailings were to be separated by cycloning into the coarse and fine
fractions; coarse fractions were to be deposited underground and fine fractions were to be placed  in
the lined tailings impoundment.
                               *.
The engineering plans for the tailings impoundment indicate that whole tailings on occasion may be
deposited in the tailings  impoundment. A total tailings production rate of 500 dry tons per day during
the first 4 years (approximately  half that to be disposed in the impoundment as fine tailings) were
estimated for tailings design. From year 5 forward a total tailings production rate of 1000 dry
tons/day (approximately half that to be disposed in the impoundment  as fine tailings) were estimated
for tailings design.  Tailings production was estimated to occur 330 days per year, 24 hours a day.
The tailings were assumed to have a solids content of 30 percent and the fine fraction was assumed to
have a solids content of 18 percent.

The tailings impoundment design, a side hill modification, calls for the embankment to be raised in
four stages throughout the life of the mine.  This layout and the final dam crest elevation were based
on the preliminary studies and a mine life of 20 years.  The maximum height of the dam  will be  130
feet and the crest width was designed to be 20 feet to accommodate vehicle, traffic and a  tailings
slurry pipeline.  The upstream slopes of the dam were designed at 1.6:1 and the downstream slopes at
2:1 as determined through static and dynamic stability analyses.  Figure 12 presents the layout of the
first stage of the impoundment.  Figure  13 presents the cross-sections of the first stage embankment.

Impoundment excavation will occurs in stages one and two to provide construction materials for  the
embankment and to increase the storage capacity of the impoundment.  Each new stage of the
embankment will be added in the downstream direction.

The embankment stage and estimated stage life statistics are listed below as based on a 1987 startup
date.
                                               58

-------
                                                                                               I
                                                                                                3
Figure 12. Stillwater Mining Company:  Liner, Sump, and Instrumentation Details

-------
                                                                      TALMAS MPOUNOMO"
                                                                           STAGE I
                                                                           SECTIONS
STU.WKTER MININC COMMNY
                                                                                                     I

                                                                                                     i
                                                                                                     Ri

Figure 13.  Stillwater Mining Company: Tailings Impoundment Stage I Sections

-------
                                                           Design and Evaluation of Tailings Dams
Stage
Number
1
2
3
4
Dam Crest Elevation
5045
5077
5096
5102
A • ir n nt
Approximate Year Dam Stage
Construction Completed
1986
1991
2001
2006
Approximate Year
Stage Filled
1992
2002
2007
2009
The impoundment was designed to store the design flood volume.  The design freeboard (3 feet while
containing the design flood volume) was determined from the flood storage volume and operational
considerations.

The impoundment was to be monitored for settlement using survey monuments located along the dam
crest.  Piezometers were to be installed in the dam foundation to monitor for seepage.

The design calls for the installation of a synthetic liner to minimize the migration of effluent from the
impoundment to ground water.  The installation of the liner was planned in stages to coincide with the
embankment raises.  Installation was planned in stages to coincide with the embankment raises. The
initial installation would cover the bottom of the impoundment and up the side slopes and
embankment.  As additional materials  were added to raise the embankment, increasing capacity of the
impoundment, new liner would be  spliced onto the top of the old liner in an encircling method. This
plan not only reduces cost but also prevents potential damage to portions of the liner that would have
been exposed for many years.  Information on the consideration of any alternative designs  was not
obtained.  The liner was selected based on economy, chemical resistance, resistance to weather,
constructability and strength and durability. Hypalon and HDPE liners were being tested at the time
of the engineering report.  Based on initial tests (simulations of the tailings pond environment), it
appeared as though the HDPE liner experienced no changes to its material properties while the
Hypalon liner was experiencing some changes in material properties.  Installation procedures for the
liner required the removal of all objects (rocks, clods, debris, sharp objects, etc) that could potentially
damage the liner.  As-built figures  have not been obtained.

In order to complete  evaluation of the  effectiveness of lining the tailings impoundment, additional
information is needed.  However, this  tailings impoundment example shows that the mining industry
is investigating options for lining tailings  impoundments and that in some cases,  liners may be a
feasible alternative. This impoundment design has been approved by the State of Montana and the
impoundment is currently operating as planned, providing an example showing that lining  of
 **
impoundments can be a feasible option to minimize seepage and environmental impact.
                                              61

-------
                                                         Design and Evaluation of Tailings Dams
7.     REFERENCES

Bedient, P.B. and W.C. Huber.  1989.  Hydrology and Floodplain Analysis.  Addison-Wesley:
     Menlo Park, 650 pages.

Bishop, A.W.  1955. "The Use of the Slip Circle in the Stability Analysis of Slopes." Geotechnique,
     Vol. 5, No. 1,  pp. 7-17.

Bishop, A.W.  1971. "The Influence of Progressive Failure on the Choice of the Method of Stability
     Analysis."  Geotechnique, Vol. 21, No. 2, pp. 168-172.

Brawner, C.O. and D.B. Campbell. 1973.  "The Tailings Structure and its Characteristics - A Soil's
     Engineer's Viewpoint."  In:  Tailings Disposal Today, Proceedings of the First International
     Tailings Symposium, Tucson, Arizona, October 31, November 1, 2 and 3, 1977. C.L. Aplin
     and G.O. Arsall Jr. (Editors).

California Mining Association.  1991.  Mine Waste Management. Sacramento,  CA.

Canadian Centre for Mineral and Energy Technology (CANMET). 1977.  Pit Slope Manual.  Chapter
     9: Waste Embankments.

Canadian Centre for Mineral and'Energy Technology (CANMET), Mine Environment Neutral
     Drainage (MEND) Program.  1993 (March 9). 1992 Annual Report.  CANMET, Toronto.

Canadian Geotechnical Society. 1989.  "Geotechnical Aspects of Tailings Disposal and Acid Mine
     Drainage."  Proceedings of a conference held May 26,  1989, Vancouver, British Columbia.

Charles River Associates. 1985.  "Estimated Cost  to the U.S. Mining Industry for Management of
     Hazardous Solid Waste."   CRA Report to the U.S.  Environmental Protection Agency #730.

U.S. Army Corps of Engineers. 1974.  "National Dam Safety Program, Proposed Guidelines for
     Safety Inspection of Dams." Federal  Register Vol. 39, No. 168 (Aug. 28), p. 31331-31346.

Das, B.M.  1990. Principles of Geotechnical Engineering, Second Edition. PWS-Kent Publishing
     Corp., Boston, Massachusetts. '

Dougherty, E.R. 1990.  Probability and Statistics for the Engineering, Computing,  and Physical
     Sciences. Prentice Hall:  New Jersey, 800 pages.

Doyle, P.M. (ed.).   1990.  "Mining and Mineral Processing Wastes: Proceedings of the Western
     Regional Symposium on Mining and Mineral  Processing Wastes, Berkeley, CA,  May 30 - June
     1, 1990."  Society for Mining, Metallurgy, and Exploration, Inc.  Littleton, Colorado.

Environment Canada; Mining, Mineral and Metallurgical Processes Division.  1987 (December).
     Mine and Mill  Wastewater Treatment.  Report EPS 2/MM/3. Minister of Supply and Services
     Canada Catalog No. En49-7/2-3E, ISBN 0-662-15788-5.
                                             62

-------
                                                         Design and Evaluation of Tailings Dams
Environment Canada; Mining, Mineral and Metallurgical Processes Division.  1992 (December).
    Environment Protection Series: Status Report on Water Pollution Control in the Canadian
    Mining Industry (1990 and 1991).  Report EPS l/MM/4.  Minister of Supply  and Services
    Canada Catalog No. En 49-7/2-3E, ISBN 0-662-20062-4.

Environmental Protection Agency, Huber, W.C. 1993.  "Information on the EPA Storm Water
    Management Model (SWMM) Version 4.2."  U.S. EPA, College Station Road, Athens, GA.

Fetter, C.W.  1980.  AppliedHydrogeology.  Columbus: Charles E. Merrill Publishing Co., 487
    pages.

Ferguson, K.A., I.P.G. Hutchinsom, and R.L. Schiffman.  "Water Balance Approaches to Prediction
    of Seepage from Mine Tailings Impoundments." In: Seepage and Leakage from Dams and
    Impoundments.   1985.

Gilbert, R.O., 1987, Statistical Methods for Environmental Pollution Monitoring. Van Nostrand
    Reinhold: New York, 320 pages.

Giroud, J.P. and  R.K. Frobel.  1983.  "Geomembrane Products."  Geotechnical  Fabrics Report, Fall,
    pp. 38^2, {cited in Van Zyl, Hutchison, Kiel, 1988}.

Hawley, J.R.  1974.  "The Use, Characteristics and Toxicity of Mine/Mill Reagents hi the Province
    of Ontario."  Ontario Ministry of the Environment, Toronto.

International Engineering Company. 1986.  "Stillwater Tailings Impoundment Engineering Report."
    Prepared for:  Stillwater Mining Corporation, February 1986.

Inyang, H.  1993. Personal Communication with Chris Long, SAIC, August  1993, concerning safety
    factors.

Kealy, C.D. and  R. Busch. Undated.  "Evaluation of Mine Tailings Disposal."

Klohn, E.J.  1981a.   "Geotechnical Investigations for Siting Tailings Dams - Design  and Construction
    of Tailings Dams." Proceedings of a Seminar November 6-7, 1980, Golden, Colorado.

Klohn, E.J.  1981b.   "The Development of Correct Tailings Dam Design and Construction Methods-
    Design and  Construction of Tailings Dams."  Proceedings of a Seminar November 6-7, 1980,
    Golden, Colorado.

Lighthall, P.C.  1987.  "Innovative Tailings Disposal in Canada."  International Journal of Surface
    Mining 1.

Lighthall, P.C., B.D. Watts and S. Rice.  1989.  "Deposition Methods for Construction of Hydraulic
     Fill Tailings Dams." In:  Geotechnical Aspects of Tailings Disposal and Acid Mine Drainage.
     The Vancouver Geotechnical  Society, Vancouver, British Columbia, May 26, 1989.

McWhorter, D. and J. Nelson.  1979.  "Unsaturated Flow Beneath Tailings Impoundments,"
    Journ. Geotech. Div., ASCE, Vol. 105, #GT11, p. 1317-1334.
                                             63

-------
                                                          Design and Evaluation of Tailings Dams
Mittal, H.K. and R. Hardy.  1977.  "Geotechnical Aspects of a Tar Sand Tailings Dike."  ASCE
     Conference on Geotechnical Practice for Disposal of Solid Waste Materials.

Mittal, H.K. and N.R. Morgenstern. 1977.  "Design and Performance of Tailings Dams." ASCE
     Conference on Geotechnical Practice for Disposal of Solid Waste Materials.

Mittal, H.K. and N.R. Morgenstern. 1975.  "Parameters for the Design, of Tailings Dams."
     Canadian GeotechnicalJournal, Vol. 13, p. 277-293.

Mittal, H.K. and N.R. Morgenstern. 1976.  "Seepage Control in Tailings Dams." Canadian
     GeotechnicalJournal, Vol. 12, pp. 235-261.

Parsons, M.L.  1981.  "Groundwater Aspects of Tailings Impoundments, Design and Construction of
     Tailings Dams."  Proceedings of a Seminar November 6-7,  1980, Golden, Colorado.

Randol International Ltd.  1985. Water Management and Treatment for Mining and Metallurgical
     Operations.  Randol International Ltd., Golden, CO.

Ritcey, G.M. 1989. Tailings Management:  Problems and Solutions in the Mining Industry.
     Elsevier Science Publishers, B.U.  Amsterdam, The Netherlands.

Ritcey, G.M. and M. Silver.  1987. Deep Water Disposal of Pyritic Tailings - A Simulation.
     Unpublished data from CANMET.

Robinsky, E. 1979.  "Tailings Disposal by the Thickened Discharge Method for Improved Economy
     and Environmental Control."  Proceedings, 2nd Int. Tailing Symp., Argall, G. (ed.), Miller
     Freeman, San Francisco, pp. 75-95.

Ross-Brown, D.M.  1979.  "Final Pit Limit Slopes - Analytical Design."  Open Pit Mine Planning
     and Design. American Society of Mining Engineers.

Schabel, P. and H. Seed.  1973. "Accelerations in Rock for Earthquakes in the Western United
     States." Bull.  Seis. Soc. of Am., Vol. 63, No. 2, pp. 501-516.

U.S. Dept. of Agriculture, Soil Conservation Science. 1964. SCS Engineering Handbook, Section 4:
     Hydrology.

Smith, E.S. 1972.  "Tailings Disposal - Failures and Lessons."  Tailing Disposal Today, Proceedings
     of the First International Tailing Symposium, Tucson, Arizona.
                                                                          «
Soderberg, Roy L.  1977.  "Design Guide for Metal and Nonmetal Tailings Disposal." Information
     Circular No. 8755. United States Department of the Interior, Bureau of Mines.  1977.

Swaisgood, J.R., and G.C. Toland. 1972.  "The Control of Water in Tailings Structures."  Tailings
     Disposal Today, Proceedings of the First International Tailing Symposium, Tucson, Arizona.

United States Department of the Interior, Bureau of Mines.  1992.   "RCRA Regulation Impact on
     Alaska Mineral Development—Tailings Management."  Prepared by Steffen, Robertson, and
     Kirsten, Inc., Denver, Colorado, May 1992.
                                             64

-------
                                                          Design and Evaluation of Tailings Dams
van Zyl, D.J.A., I.P.G. Hutchison, and J.E. Kiel.  1988. Introduction to Evaluation, Design and
     Operation of Precious Metal Heap Leaching Projects.  Society of Mining Engineers, Inc.,
     Littleton, Colorado.

Vick, S.G.  1990.  Planning, Design and Analysis of Tailings Dams.  BiTech Publishers Ltd.

Volpe, R.  and W.E. Kelly. 1985.  Seepage and Leakage from Dams and Impoundments. American
     Society of Civil Engineers.

Williams,  M.  1979.  "Tailing Dam Failure Case History."  Proceedings, 2nd Int. Tailing Symp.,
     Argall, G. (ed.), Miller Freeman, San Francisco, pp. 428-433.
                                             65

-------
                                         Design and Evaluation of Tailings Dams
                           APPENDIX A

COMMENTS ON THE DRAFT "DESIGN AND EVALUATION OF TAILINGS DAMS"
                       AND EPA RESPONSES
                               66

-------
                                                          Design and Evaluation of Tailings Dams
               Comments on the Draft "Design and Evaluation of Tiiilings Dams"
                                     and EPA Responses


A draft of "Design and Evaluation of Tailings Dams" was provided for review and comment to the
following organizations: U.S.  Department of the Interior (DOI) Bureau of Mines, DOI Office of
Surface Mining, DOI Bureau of Land Management,  ASARCO Inc., and Barrick Resources (USA),
Inc.  Comments received from these organizations included technical and editorial changes and
suggestions, many of which have been incorporated  into the current draft of this document.  Technical
comments were reviewed and included into the text where appropriate.  Editorial changes were
incorporated, often with minor language changes for expository purposes.

EPA believes that all the comments received have served to improve the documents clarity and
accuracy.  EPA would like to thank all the agencies, companies, and individuals for their time and
effort spent reviewing and preparing comments.

The following paragraphs address specific comments of a technical nature.

1.     Comment:  A limited number of references were relied upon in preparing this draft document.

       Response:  EPA reviewed additional materials that are now referenced in the  revised
       document.

2.     Comment:  The variable nature of estimates  of tailings quantities to be generated over the life
       of a project should be stressed. Additionally, changes in reserves  over the life of a mining
       project is a fundamental characteristic of mining operations and is  often misunderstood by
       some regulators.

       Response:  EPA agrees that the evolving nature of mining projects has significant implications
       for tailings impoundment design and operation.   Language underscoring the importance of this
       characteristic was therefore added to the introductory paragraphs of Section 2 of the
       document.

3.     Comment:  The stability and environmental performance of tailings impoundments are often
       interrelated.  Further, the long-term costs of a disposal system are related to both stability and
       environmental integrity.  Therefore,  stable and environmentally  acceptable designs will be
       cost effective.

       Response:  EPA agrees that careful attention to  stability and environmental performance can
       reduce long-term costs, and that performance and cost control are thus often complimentary
       considerations.  However, design and environmental performance must meet  applicable
       Federal and State regulations.

4.     Comment:  Upstream embankment with subaerial deposition should be added to Table 1:
       Comparison of Embankment Types.  Subaerial deposition can alleviate many of the stability
       concerns associated with upstream and other embankment types  relaiive to similar systems
       employing other depositional methods.

       Response:  EPA acknowledges the potential  benefits of subaerial deposition in reducing
       stability concerns in upstream embankment impoundments.  However, Table  1  is a table of
                                              67

-------
                                                           Design and Evaluation of Tailings Dams
       embankment types , not depositional methods.  Further, EPA points out that subaerial and
       subaqueous deposition may be employed with any of the embankment types given suitable
       conditions.

5.     Comment:  More information is needed in the section on pumpback systems emphasizing
       widespread use and the dearth of affordable and reliable alternative systems.

       Response:  EPA agrees that pumpback systems are often used to collect and move
       impoundment seepage.  Note that EPA located very little information on pumpback systems
       per se.  Rather, the majority of sources found focus on drainage and diversion systems with
       little attention devoted to the design and operation of the collection and retention systems
       accompanying the seepage control systems.

6.     Comment:  The Stillwater Case Study needs to be prefaced by a discussion of the unique
       characteristics of the site which may make Stillwater's experience not generally applicable to
       other mines, particularly  the small impoundment size and the perviousness of the underlying
       alluvium. Figures referred to in the text were not provided in the draft, nor does the text
       clearly explain the methods with which the liner was installed after initial impoundment
       construction.

       Response:  EPA has provided figures detailing the layout of the Stillwater impoundment in
       this revision. Additionally, EPA has included language describing the steps followed in
       impoundment liner installation. Finally, EPA feels that elements of the Stillwater project are
       potentially applicable to other • -<   iss notwithstanding some of the characteristics peculiar to
       Stillwater.
                                                            U.S. Environmental Protection Agency
                                                            Region 5, Library (PL-12J)
                                                            77 West Jackson Boulevard, 12th Flopr
                                                            Chicago, IL  60604-3590
                                              68

-------