July 1988                        EPA-700/8-88-042
Hazardous Waste GrouncH/Vater
Task Force
Evaluation of
Dover Air Force Base
Dover, Delaware
AEPA
UNITED STATES ENVRONMENTAL PROTECTION AGENCY

-------
                              JULY 18, 1988




          UPDATE OF THE HAZARDOUS WASTE GROUND-WATER TASK  FORCE



                    EVALUATION OF DOVER AIR FORCE BASE



                             DOVER, DELAWARE






     The United States Environmental Protection Agency's Hazardous Waste



Ground Water Task Force (Task Force) conducted an evaluation of  the



ground water monitoring program at the Dover Air Force Base (DAFB) located




in Dover, Delaware.  The field inspection was conducted during the       ..



period from December 8 to 12, 1986.  DAFB is one of 58 facilities evaluated



by the Task Force.  The purpose of the Task Force evaluations was to




determine the adequacy of a facility's ground water monitoring program




in regard to the applicable State and Federal requirements.  The Task



Force effort came about in light of recent concerns as to whether operators




of hazardous waste treatment, storage and disposal facilities were comply-



ing with State and ifederal ground water monitoring regulations.



     The evaluation of the DAFB focused on determining (1) if the facility



was in compliance with applicable regulatory requirements and policy,



and (2) if hazardous waste constituents were present in the ground water.



The inspection revealed that DAFB was not fully complying with applicable



interim status ground water monitoring requirements and that ground water



samples from on-site wells contained hazardous waste constituents.  This



update provides information on ground water related activities conducted




by DAFB, EPA, and the Delaware Department of Natural Resources and Environ-



mental Control (DNREC) since the Task Force Inspection.

-------
                                   -2-






     Based upon preliminary findings of the Task Foroe, EPA issued a



letter to CNREC on June 23, 1987, outlining major deficiencies in the



ground water monitoring program for the closed surface impoundments




known as the IW Basins.  The letter included a detailed listing of areas



of non-compliance with RCRA interim status ground water monitoring require-



ments (40 CFR Sutpart F Section 265).



    Using this letter as supporting evidence, DNREC issued a Notice of




Violation/Notice of Deficiency (NOV/NOD) to DAFB on .August 6, 1987.  The



NOV cited specific violations of applicable sections of 40 CFR 265 Interim




Status Regulations, sane of which related to ground water monitoring



activities.  The NOD was issued based upon the determination that the



Post-Closure Permit Application for the IW basins submitted on August 25,




1986 was incomplete.  The application was deficient in that it



failed to meet permit application requirements in Sections 122.14,122.17



and 264 Subparts F and K of the DNREC Hazardous Waste Regulations.




     As of November 1987, DAFB had tailed to comply with the MOV/NOD.



According to 7 Delaware Code section 6309(a)(l), the Secretary has the



authority to issue an order requiring compliance with State Hazardous



Waste Regulations within a specified time period if violations extend



beyond the thirtieth day after the Secretary's notification.  This



authority was exercised by the issuance of a Secretary's Order (87/HW/03)



on November 19,  1987.



     The order requires DAFB to  correct deficiencies  in the Post Closure



Permit Application, by upgrading  the ground water monitoring program




for the IW basins  consistant with 40 CFR 264 Subparts  F and G and



developing plans for long  term care and maintanence of  the final cap,

-------
                                   -3-
monitoring wells etc.  The conpliancB schedule is spread out over a 20




month period with intervening reporting deadlines.  At the end of this



timeframe, submission of a final report is required.



     In 1983, DAFB began environmental studies under the Installation




Restoration Program  (IRP).  The IRP was originally developed by the



Department of Defense (DOD) to identify and evaluate past disposal sites



on DOD property and  to eliminate hazards to public heath and the




environment in a responsible manner.  The IRP consists of four phases,



Phase I, Initial Assessment/Records Search, Phase II, Confirmation/




quantification (Site Investigations) Phase III, Technology Base Develop-




ment (Development of Technologies for the Assessment of Environmental



Impacts) and Phase IV, Operations/Remedial Actions  (Selection and




Implementation of Remedial alternatives).



     At present, Phases IV and II of the IRP are  being conducted simulta-




neously.  Under Phase IV, four (4) Solid Waste Management Units (SWUs)



are being investigated including the IW Basins and under Phase II, thirteen




(13) ShMUs are being evaluated.  DNREC is tracking  only those parts of



Phase IV which have  been  incorporated into the Secretary's Order.  An



integral component is the installation of numerous monitoring wells



facility wide, a number of which are to be located  in the general vicinity



of disposal sites evaluated by the Task -Force.



     Agreement was reached between DAFB and DNREC regarding  the scope of



work for Phase IV of the  IRP prior to issuance of the order.  To expedite



resolution of violations, the scope of work was modified to  incorporate



as many of the order requirements as possible which were not originally



included.  To the greatest extent possible, the reporting requirements

-------
                                   -4-






of the order correspond to that of the IRP study plans.  At this time,



CAFB is considered to be in compliance with the terms of the Secretary's



Order and are meeting all reporting requirements.

-------
  EPA HAZARDOUS WASTE GROUND-WATER TASK

INVESTIGATION  OF  THE DOVER AIR FORCE  BASE
          tJ.S.  Environmental Protection Ag«noy
          Regi'itx 3,  Library  (5PL-16)
          230 ,'•',  IVarborn  Street, Room 1*70
          Chicago,  IL   60604

-------
                                    CONTENTS
EXECUTIVE SUMMARY

INTRODUCTION 	        1

SUMMARY OF FINDINGS AND CONCLUSIONS 	        6

  GROUND-WATER MONITORING DURING INTERIM STATUS 	        6

     Ground-water Sampling and Analysis Plan 	        6
     Sampling and Analysis Procedures 	        7
     Monitoring Well Network 	        8
     Assessment Program Outline and Plan 	        9

  TASK FORCE SAMPLING AND MONITORING DATA EVALUATION 	        9

TECHNICAL REPORT

INVESTIGATION METHODS 	       14

  RECORD/DOCUMENTS REVIEW 	       14
  PART B PERMIT APPLICATION EVALUATION 	       14
  FACILITY INSPECTION 	       17
  LABORATORY EVALUATION 	       17
  SAMPLE COLLECTION AND ANALYSIS 	       18

FACILITY DESCRIPTION 	       26

  DAFB ORGANIZATION AND MISSION	       26
  HAZARDOUS WASTE ACTIVITIES 	       26
  SOLID WASTE MANAGEMENT UNITS 	       29

SITE GEOLOGY/HYDROGEOLOGY 	       48

  TOPOGRAPHY/SURFACE DRAINAGE 	       48
  SITE GEOLOGY/HYDROGEOLOGY 	       48

     Hydrogelogic Units	       55
     Ground-water Flow at DAFB 	       57
     Ground-water Flow at Individual Sites 	       57
     Site T-l	       57
     Site D-10 	       57
     Sites D-4, D-5 	       60

GROUND-WATER MONITORING DURING INTERIM STATUS 	       63

  REGULATORY REQUIREMENTS 	       64
  GROUND-WATER SAMPLING AND ANALYSIS PLAN 	       65
  MONITORING WELLS 	       66

     Well Construction 	       67
     Well Locations 	       70

 DAFB SAMPLING PROCEDURES 	       70

-------
                             V CONTENTS (cont.)
     Water Level Measurements 	       70
     Purgi ng 	       71
     Sample Collection 	       72
     Shipping and Chain-of-Custody	       73

  GROUND-WATER QUALITY ASSESSMENT PROGRAM OUTLINE AND PLAN 	       73

      Assessment Outline 	       73
      Assessment Plan	       74

EVALUATION OF MONITORING DATA FOR INDICATIONS OF WASTE RELEASE 	       75
APPENDICES

A     BORING LOGS FOR DAFB WELLS
B     ENVIRONMENTAL SAMPLING DATA SHEET
C     ANALYTICAL TECHNIQUES AND RESULTS FOR TASK FORCE SAMPLES
D     REFERENCES
FIGURES

1     Site Location Map 	       2
2     Location of Wells Sampled by Task Force 	       10
3     IW Basins Composite Sampling Locations 	       22
4     North Drainage Ditch 	       28
5-9   Solid Waste Management Units 	       31
10    Site Topographic Map	       49
11    Installation Drainage 	       50
12    Generalized Geologic Sections 	       52
13    Boring Log of USGS Test Well 	       54
14    Site Water Table Elevations 	       58
15    Site T-l 	       59
16    Site D-10 	       61
17    Sites D-4, D-5 	       62
TABLES

1     Selected Organic Data From Task Force Samples 	       12
2     Task Force Measurements 	       19
3     Decontamination Procedures 	       20
4     Purging and Sampling Data	       23
5     Order of Sample Collection,  Bottle Type, and Preservation List ..       25
6     State and Federal Counterpart Interim Status Regulations 	       65
7     Ground-water Monitoring Well Construction Details 	       69
8     Summary of Waste Components 	       76

-------
                                  INTRODUCTION


     Concerns have been raised about whether hazardous waste treatment, storage

and disposal facilities (TSDFs) are complying with the ground-water monitoring

requirements promulgated under the Resource Conservation and Recovery Act (RCRA)*.

In question is the ability of existing or proposed ground-water monitoring

systems to detect contaminant releases from waste management units.  To evaluate

these systems and determine the current compliance status, the Administrator of

the Environmental Protection Agency (EPA) established a Hazardous Waste Ground-

Water Task Force (Task Force).  The Task Force comprises personnel from the EPA

Office of Solid Waste and Emergency Response, Office of Enforcement and Compli-

ance Monitoring. National Enforcement Investigations Center (NEIC), Regional

Offices and State regulatory agencies.  The Task Force is conducting indepth,

onsite investigations of TSDFs with the following objectives:


   o Determine compliance with interim status ground-water monitoring require-
     ments of 40 CFR Part 265, as promulgated under RCRA or the State equivalent
     (where the State has received RCRA authorization).

   o Evaluate the ground-water monitoring program described in the RCRA Part B
     permit application, submitted by the facility, for compliance with 40 CFR
     Section 270.14(c), or the State equivalent.

   o Determine if the ground-water at the facility contains hazardous waste or
     const!tuents.


     The Dover Air Force Base (DAFB) is located in Kent County, Delaware approxi-

mately 3.5 miles southeast of the center of the city of Dover, Delaware (Figure

1).  The onsite Task Force inspection was conducted from December 8 through 12,

1986 and was coordinated by the EPA Region III personnel.
   * Regulations promulgated under RCRA address TSDF operations, including
ground-water monitoring to ensure immediate detection of any hazardous waste
or constituents released to the environment.

-------
I 'Z--y£Zl--~f&x--  • t T>A I   V/iV
I wttiil.^'A:^
        f^y^M
f"/^^'v>:i^.'-":'.5;-r-."-!tf-'~-~^'.,(<^ -.X  -1 c
^g§^|^^;>^/
               dYW NOIXVDOT 31IS
                   T 3W1DL3

-------
                                      -3-






     The DAFB treated liquid hazardous wastes resulting from aircraft maintenance




and operation in two adjacent, regulated units (surface impoundments) which are




subject to RCRA ground-water monitoring requirements.  Closure of these units was




completed in August 1986 under a State of Delaware approved closure plan.  The




approved closure plan called for the removal of all free liquids and sludge from




the surface impoundments and excavation of underlying soil to a depth of six (6)




inches.  A post closure permit application has been submitted by the DAFB and




was evaluated by the Task Force for compliance with 40 CFR Part 270.14(c).






     During the inspection, members of the Task Force evaluated compliance with




the interim status ground-water requirements of 40 CFR Part 265 and the Delaware




equivalent regulations (Del. Reg. Section 265).  The adequacy of the ground-water




sampling and analysis plan, monitoring well construction and location, analysis




of samples taken from the interim status monitoring wells and the Part B Post




Closure permit application were evaluated.  Additionally, three Solid Waste




Management units (SWMUs) were investigated.  The evaluation involved review of




State, Federal, and facility records;  facility and analytical laboratory in-




spections; and collection and analysis of samples from the ground-water monitoring




wells around the two adjacent, regulated units and three SWMUs onsite and an




oil/water separator.






     Industrial operations at DAFB consist primarily of aircraft and vehicle




maintenance and repair activities.  These and other support operations generate




hazardous material, including waste fuels, oils,  solvents, and paints at several




industrial shops on site.






     In 1963, a spill  containment system was constructed and began accepting

-------
wastewater from the engine build-up shops.  The spill containment system con-




sisted of two concrete lined oil/water separators and two unlined, earthen




settling lagoons (also known as the Industrial Waste (IW) basins).  Wastes




entered the oil/water separators where lighter than water constituents were




skimmed from the surface and sent to underground tanks.  The remaining wastes




would then enter the TW basins.  Settling occurred in the IW basins prior to




discharge to the North Ditch.  .In 1968, plating shop wastewaters were also




routed to the IW basins.






     In 1969, discharge from the IW basins to the North Ditch was terminated.




From 1969 to 1975, IW basins' effluent was routed to a sanitary treatment fa-




cility on base.  Since 1975, effluent has been discharged to a regional sani-




tary treatment facility (the Kent County sewer system).  In July  1985, the IW




basins were bypassed and closure, under a State approved closure plan, was




completed in August 1986.






     Final authorization for the State's hazardous waste program was delegated




to the Delaware Department of Natural Resources and Environmental Control (DNREC)




on June 22, 1984.  On November  19, 1980, the DAFB submitted a RCRA Part A Permit




Application for a treatment system.  This Part A listed two units; a tank (T01)




and a surface impoundment (the  IW basins).  In 1983, the DNREC deleted the sur-




face impoundment from the Part A stating that this unit was exempt from RCRA




regulation under the definition of a wastewater treatment unit.   In February




1984, the DNREC reversed this decision stating that the impoundment (IW basins)




was subject to RCRA regulation and a RCRA closure plan was required.  Therefore,




since February 1984, the IW basins have been considered to a surface impoundment




and a regulated unit subject to the DNREC interim status ground-water monitoring




requirements.

-------
                                      -5-






     Three ground-water monitoring wells (101,102,103) were installed near the




IW basins in 1982.  Samples taken from these wells in 1982 showed elevated




levels of several volatile organic compounds including 1,1,1-trichloroethane,




trichloroethylene, and tetrachloroethylene.






     In November 1984, three additional monitoring wells (Olj ,02j ,04j) were




installed in the vicinity of the IW basins.   These three wells,  in addition to




the wells installed in 1982, comprised the ground-water monitoring system for




regulated unit.  Sampling performed in 1984, 1985, and 1986 has  shown elevated




levels of organic compounds in the ground-water in several of  the wells surround-




ing the IW basins.  Specifically in 1986, ground-water samples from these wells




ranged from 0.49 ppb to 1500 ppb for tetrachloroethylene,  0.14 ppb to 240 ppb




for trichloroethylene and non-detectable to 7700 ppb for 1,1,1-trich]oroethane.

-------
                                      -6-






                      SUMMARY OF FINDINGS AND CONCLUSIONS






     The findings and conclusions presented  reflect conditions  existing at the




facility in December 1986.  Actions taken by the State,  EPA Region III and DAFB




subsequent to December are summarized in the accompanying update.






GROUND-WATER MONITORING DURING INTERIM STATUS




     Task Force personnel investigated the interim status ground-water monitoring




program at DAFB for the period between February 1984,  when the  State made the




determination that the surface impoundment was RCRA regulated,  and December 1986.






     The Task Force evaluated the ground-water monitoring program implemented in




1984 and determined it to be inadequate.  For example, records  submitted by DAFB




indicate that, whereas DAFB conducted and continues to conduct  a ground-water




sampling and analysis program for the surface impoundment, this program does not




compl y with the requirements of RCRA.  These records indicate that initial back-




ground concentrations for the parameters specified in the Delaware Regulations




Governing Hazardous Waste (Del. Regs.) 265.92(b) were never established as re-




quired by Del. Regs. 265.92(c)(1).  DAFB has not monitored for  all parameters




specified in Del. Regs.  265.92(b).  For example, analyses were  not available




for Barium, Fluoride, Nitrate, Lindane, Methoxychlor, Toxaphene, 2,4-D, 2,4,5-TP




Silvex, Radium, Gross alpha, Gross beta, Selenium, Endrin, Turbidity, Fecal




coliform, Chloride, Manganese, Sodium, Sulfate, Specific conductance, TOC, and




TOH.  Replicate measurements were not obtained for the indicator parameters




during the first year of sampling.  An initial background arithematic mean was




never calculated and no  statistical comparison has been made to determine




whether a statistically  significant increase over initial background has occurred,

-------
                                      -7-






Other program components,  including the ground-water sampling and analysis




plan and procedures,  monitoring well network and  the assessment  program outline




and plan did not comply with DNREC requirements.






Ground-Water Sampling and  Analysis Plan




     A ground-water sampling and analysis plan was developed by  DAFB on April  19,




1985.  This plan was updated on October 1,  1986.   The Task Force evaluated  the




October 1986 ground-water  sampling and analysis plan.






     Although the 1986 plan updates and improves  the original plan developed




in April 1985, it is still inadequate and does not completely comply with the




Del. Regs. Part 265.92.  The plan does not adequately detail the procedures




followed for sample collection, shipment, analytical procedures  or chain-of-




custody.  For example, the plan did not specify the order in which samples




should be taken (most volatile to least volatile); adequately describe the




chain of custody program utilized in the field and the lab, or provide an




explanation of the routine collection and analysis of quality assurance/quality




control blanks.






Sampling and Analysis Procedures




     DAFB personnel conducting the interim status sampling for the facility




did follow the sampling and analysis procedures submitted in the October 1986




plan.  However, since the plan had some deficiencies, some procedures were  also




deficient.  Conductivity,  pH and dissolved oxygen were measured in the onsite




laboratory in accordance with the sampling and analysis plan, however conduc-




tivity and pH measurements should have been taken in the field.   Because of




this, the holding time for pH was exceeded.  The plan does not include the

-------
 collection  of  equipment,  trip or field blanks or duplicate samples.  Sampling




 personnel did  not collect any of these QC samples.






     Preservation techniques specified in the plan were not correctly followed.




 The plan requires preservation of phenols by cooling the sample to 4° C and




 then adding sulfuric acid (H2S04) to the sample until a pH of 2 or less is




 attained.   In  the onsite  laboratory, samples to be analyzed for phenols were




 preserved with H2S04 without first cooling.  (Typical groundwater temperatures




 measured in the field ranged from 6°.C to 16° C).







     Task Force personnel inspected the USAF Occupational and Environmental




 Health Laboratory (OEHL) at Brooks Air Force Base, San Antonio, Texas, the




 laboratory which conducts the analyses on ground-water samples for DAFB.




 Several deficiencies were found at the OEHL.  The laboratory does not digest




 samples prior  to analysis.  Total metals for flame analysis should be digested




 according to method 3010 of "Test Methods For Solid Waste", SW-846.  All metals




 data generated for the well monitoring should be considered highly questionable,




 Additionally, pesticides were analyzed using a method which is an adaptation of




 EPA methods without adequate documentation of equivalency.  Further, for each




 analysis, a specific frequency for spiked samples, duplicate samples and QC




 checks was not established, documented or implemented.






 Monitoring Well Network




     Boring logs and well construction details for the ground-water monitoring




wells installed in 1982 (101,102,103) were inadequate and incomplete.  Con-




 struction procedures for ground-water monitoring wells installed in 1984




 (Olj,02j,04j) were not in conformance with the interim status performance




 standards (Del. Regs. Part 265).  One well (02j) lacked a gravel pack.

-------
                                      -9-






The length of the screened interval in monitoring wells Olj,  02j and 04j  was




the entire thickness of the uppermost aquifer (ranging from 15.5 feet to  34




feet).  Excessive screened length dilutes ground-water samples,  making sampling




of discrete portions of the aquifer difficult and making the  adequacy of  the




monitoring system to detect contamination migration questionnable.  The casing




material for these wells was polyvinylchloride (PVC).  Construction records




indicated that the wells were grouted with portland cement, rather than a mix-




ture of bentonite and cement.  Additionally,  concrete aprons  were not install-




ed around each well to prevent surface runoff from entering the  well column.






     From the information presently available, the wells appear  to be adequately




areally distributed to detect releases from the regulated unit.   However, as




previously stated, the excessive length of the screened interval makes the




adequacy of the monitoring system in detecting contamination questionable.






     Based on studies conducted by DAFB consultants in June 1986, ground-water




flow direction is apparently influenced by a ground-water divide running the




length of Atlantic Avenue (Figure 2).  Ground-water north of  this divide  appar-




ently flows to the northeast and ground-water south of the divide apparently




flows southeast.  The existence of the divide has not extensively been proven




and ground-water elevations taken prior to October 1986 lacked the accuracy to




provide adequate ground-water contours.






     Finally, it appears that the upgradient, background monitoring well  (Olj)




is being impacted by mounding conditions caused by the regulated unit and is




therefore does not represent true background conditions at the facility.






Assessment Program Outline and Plan




     The RCRA regulations (40 CFR Part 265.93) required submittal of an outline




for a ground-water quality assessment program by November 8,  1981.  However, the

-------
                                     >-10-






DNREC made the determination February 1984 that the surface impoundments were




subject to the RCRA regulations.  Therefore, the regulations became effective




at this date.







     During the Task Force inspection,  no record of an outline for a ground^water




quality assessment program was found.






TASK FORCE SAMPLING AND MONITORING DATA EVALUATION




     During the inspection, Task Force personnel collected samples from 18 ground-




water monitoring wells and an oil/water separator (Figure 2).  Of the ground-water




monitoring wells sampled, 6 wells monitored 3 separate Solid Waste Management




Units (SWMUs), Units D-4, D-5, and D-10.  All three SWMUs investigated were land-




fills used during the 1950's and 1960's.  These SWMUs were chosen by the Task




Force due to historical information that suggested the possibility of releases




from each unit.  The well samples were collected to determine whether the ground-




water contained hazardous waste or hazardous waste constituents.  The oil/water




separator was sampled because it may have received and stored RCRA hazardous




wastes and is a potential contaminant source.  Monitoring data from the Task




Force samples were evaluated with previous DAFB data.






     Standard procedure for purging wells includes using an organic vapor ana-




lyzer (OVA) to sample air in the wellhead and the breathing zone to determine




whether organics are present.  Three wells at unit D-4, we^lls 11,  12, and 13




showed elevated levels of organics in the wellhead (8-11 ppm, 20-50 ppm and




10-100 ppm, respectively).  Background levels were detected in the breathing




zone.  In addition, ground-water in well  13 contained a non-aqueous gasoline-like




phase approximately 0.2 inches thick.  A  sample of this phase was  taken.  During




the purging and sampling of this well, cartridge respirators were worn by sam-




pling personnel as a safety precaution.

-------
                                -11-

                            FIGURE 2
  LEGEND
— — —— USAF Proptny Line
*"*" -— Drainage Channel
.——-  Unimproved <*oad
 •101-103 Monitoring Wells. Aug 1982
 •Olj-OSj: 10-77  USAF Monitoring Wellt, Nov. 1984
   I	7
   I             /

drJ    *•
h
       Appromimat* Sc*(« (Fe«tl
           LOCATION OF WELLS SAMPLED BY THE  TASK FORCE

-------
                                   -12- -•


     Task. Force and DAFB sampling data show the presence of high  concentrations

(greater than  1000 micrograms per liter (ug/1)) of  trichloroethylene,  trans-1,2-

dichloroethylene, and  1,1,1-triehloroethane in two  of  the  eighteen wells  sampled

by the Task Force (01j and  103).  Nine other wells  (06j, 07j,  09j,  101,  102,  10,

11, 13, 21) also detected  various organic compounds  in the groundwater,  but  at

lower concentrations.  Wells 01j, 101, 102 and 103  are located near  the  IW

basins.  Wells 06j, 07j and 09j are located near unit  D-10.  Wells  10,  11, 13,

and 21 are located near units D-4 and D-5.


     Data from the Task Force samples show low levels  of  Inorganic  contaminants

in the ground-water.   For  example, the highest concentrations  of  chromium found

were 258 ug/1  (well 08j) and 187 ug/1"(well 02j).


     Table 1 presents  selected organic data for several  monitoring wells.  This

data shows that the supposed background well for the IW basins (01j)  is  not

yielding ground-water  samples representative of background conditions.


                                    TABLE  1

                 SELECTED  ORGANIC DATA FROM TASK FORCE SAMPLES

                                   IW Basins           Unit D-4      Unit D-10
Parameter *                      Olj       103             l_\_              07j

perchloroethylene                190        ND**           550              ND
trichloroethylene               2400        110             660              71
1, 1-di chl oroethane               ND        160              ND              33
1,1-dichloroethylene             ND        140              ND              ND
trans-1,2-dichloroethylene      ND       2300             260              17
1,1,1-tri eh] oroethane            ND       2400              ND              ND

*  Concentrations in ug/1.

** ND - not detected.

-------
                                      -14-


                             INVESTIGATION METHODS


The Task Force investigation of the DAFB facility comprised:

   o Reviewing and evaluating records and documents from EPA Region III, DNREC,
     and DAFB.

   o Conducting an onsite facility inspection December 8 through December 12,
     1986.

   o Evaluating the offsite analytical laboratory.

   o Sampling and analyzing data from ground-water monitoring wells and the
     oil/water separator.


RECORDS/DOCUMENTS REVIEW

     Records and documents from EPA Region III and the DNREC office were reviewed

prior to and during the onsite inspection to obtain informati.on on facility op-

erations,  construction details of waste management units and the ground-water

monitoring program.  Onsite facility records were reviewed to verify information

in Government files and supplement Government information where necessary.  Se-

lected documents requiring further evaluation were copied by the Task Force du-

ring the inspection.


     Specific documents and records that were reviewed included the ground-water

water sampling and analysis plan; analytical results from past ground-water

sampling;  monitoring well construction data and logs; site geologic reports;

site operations plans; facility permits; waste management unit design and op-

eration reports; and operating records showing the general types, quantities,

and locations of process waste sources at the facility.


PART B PERMIT APPLICATION EVALUATION - GROUND-WATER MONITORING

     The ground-water monitoring section of the Part B post-closure permit ap-

plication for the IW Basins dated August 25, 1986, has been reviewed for com-

pleteness.  The review consists of a comparison of information requirements

-------
                                      -15-


under 40 C.F.R. 270.14(c) and Del. Regs. 122.14(c).


     For easy reference, information requirements are listed in the left hand

column of the chart by regulatory citation followed by an indication as to

whether the requirement has been met in the right hand column.  Any further

explanation is provided below the response.
Information Request
Is Requirement Satisfied (yes/no)
270.14(c)(l)/Del. Regs. 122.14(c)(l)
A summary of the ground-wa.ter
monitoring data obtained during
the interim status period.

270.14(c)(2)/Del. Regs. 122.14(c)(2)
Identification of the uppermost
aquifer and aquifers hydrauli cally
interconnected beneath the facility
property including ground-water flow
direction and rate and the basis  for
such  identification.

270.14(c)(3)/Del. Regs.  122.14(c)(3)
On  a  topographic  map... a  delineation
of  the waste management area,  the
property boundary,  the proposed point
of  compliance, the  proposed  location
of  ground-water  monitoring wells  and
to  the extent possible, information
required under (c)(2).

270.14(c)(4)/Del. Regs.  122.14(c)(4)
A description of  any plume of  contami-
nation that has  entered the  ground-
water from a regulated unit  at  the
time  the application was submitted
that:

  (i) Delineates  the extent  of  the
       plume on the  topographic map.

  (ii) Identifies the  concentration
       of  each Appendix  III  constituent
       throughout the  plume  or identifies
       the maximum  concentration  of  each
       Appendix  VIII  constituent  in  the
       plume.
   Not included in the application,
   however, monitoring data is
   available in the IRP stuidy reports,
   No specific discussion included in
   application; however, IRP studies
   include hydrogeologic information.
   No.
   No.
   No.
   No.

-------
                                      -16-
270.14(c)(5)/Del. Regs. 122.14(c)(5)
Detailed plans and engineering report
describing the proposed ground-water
monitoring program to be implemented
to meet the requirements of 264.97.

270.14(c)(6)/Del. Regs. 122.14(c)(6)
If the presence of hazardous
constituents has not been detected
in the ground-water at the time of
the permit application, the owner/
operator must submit sufficient
information, supporting data and
analysis to establish a detection
monitoring program.

270.14(c)(7)/Del. Regs. 122.14(c)(7)
If the presence of hazardous constituents
has been detected in the ground-water at
the point of compliance at the time of
the permit application, the owner/operator
must submit sufficient information, support-
ing data and analyses to establish a compliance
monitoring program which meets the requirements
of 264.99.  The owner/operator must also
submit an engineering feasibility plan for a
corrective action program necessary to meet
the requirements of 264.100.

   (i)  A description of wastes previously
        handled at the facility.

   (ii) A characterization of  the
        contaminated ground-water,
        including the concentration of
        hazardous constituents.

   (iii) A list of hazardous constituents
         for which compliance monitoring
         will be undertaken...

   (iv) Proposed concentration limits for
        each hazardous constituent.

    (v) Detailed plans and engineering report
        decribing the proposed ground-water
        monitoring system.

   (vi) A description of proposed sampling and
        analysis and statistical comparison
        procedures to be utilized in evaluating
        ground-water monitoring data.
No specific plan submitted
with the permit application.
 N/A - Hazardous constituents
 have been detected in the
 ground-water.
  No.
  None presented with
  permit application.
  No.
  No
  No,
  No.
the

-------
                                      -17-
                                                    None submitted with
                                                    the permit application,
                                                    however, the IRP contains
                                                    various study initiatives,
                                                    and remediation studies.
270.14(c)(8)/Del. Regs.  122.14(c)(8)
If hazardous constituents have been
measured in the ground-water which
exceed the concentration limits
under 264.94 Table 1 or if ground-water
at the time of permit application at
the waste management boundary indicates
the presence of hazardous constituents
fro the facility in ground-water over
background concentrations, the owner/
operator must submit sufficient
information, supporting data and
analyses to establish a corrective
action program which meets the require-
ments of 264.99
FACILITY INSPECTION

     An onsite facility inspection was conducted to identify waste sources,

waste transport, waste management units (past and present), pollution control

practices, surface drainage routes and to verify the location of groundwater

monitoring, recovery, and other wells.  Base representatives and contractors

provided information"on and explained:  (1) facility operations (past and pre-

sent); (2) site hydrogeology; (3) the ground-water monitoring system, and; (4)

the ground-water sampling and analysis plan.


LABORATORY EVALUATION

     The USAF Occupational and Environmental Health Laboratory (OEHL) at Brooks

Air Force Base, San Antonio, Texas analyzes all ground-water samples for DAFB

and was evaluated regarding their ability to produce quality data for the re-

quired analysis.  Analytical equipment and methods, quality assurance procedures

and records were examined for adequacy.  Laboratory records were inspected for

completeness, accuracy and compliance with State and Federal, requirements.  The

sample handling, analysis and document control procedures followed were discussed

with laboratory personnel.

-------
                                      -18-
SAMPLE COLLECTION AND ANALYSIS

     The sampling portion of the investigation involved two activities:

(1) measuring water levels in the  18 monitoring wells to be studied and

(2) sampling the wells and one active oil/water separator.  Water level

measurements were taken in an attempt to determine the direction of ground-

water flow, as well as calculations of purge volumes (Table 2).


     The monitoring wells for the Solid Waste Management units (SWMU's)

investigated by the Task Force were constructed as follows: Unit D-4,

monitoring wells 10 through 13 in October 1984; Unit D-5, monitoring wells

21, 22 and 23, October 1984; Unit D-5, monitoring wells 05j through 09j in

November 1984.  The wells were sampled to determine if and to what extent

the ground-water contains hazardous waste or constituents.  The oil/water

separator was 'sampled to determine whether hazardous wastes were being

stored in this unit.


     Splits of all samples including duplicate volatile organic samples

were provided to DAFB.  EPA Region III did not request spHt samples.


Sample Collection Procedures

     1.  DAFB personnel unlocked the well head.

     2.  EPA contractor monitored open wellhead for chemical vapor,
         using the Photovac Tip®, 'and radiation.

     3.  EPA contractor measured depth to ground water using an oil/water
         sonic Interface Probe® (Oil Recovery Systems, 100 feet model).

     4.  EPA contractor lowered the Interface Probe through the water
         column until total depth was reached.

     5.  EPA contractor retrieved the Interface Probe from the well bore
         and decontaminated the cable and probe using procedures outlined
         in Table 3.

-------
                                                    -19-
                                                   Table 2

                                           December 1986 Task Force
                                             Measurements (feet)
Site
Number
Tl
Tl
Tl
Tl
Tl
Tl
D4
D4
DA
D4
D5
D5
D5
D10
D10
D10
D10
D10
Well
Number
04j
oij
101
02j
102
103
10
11
12
13
21
22
23
05j
06j
07j
08j
09j
Surveyed Elevations (ft)
Top of Well Casing 1
25.40
21.39
25.01
27.56
24.51
24.62
22.38
21.76
21.81
22.97
18.03
20.19
21.39
20.07
17.40
12.57
14.20
16.35
Total Well
Depth (ft)
47.06
40.10
18.97
35.04
18.93
18.94
57.98
57.05
57.15
64.90
62.05
62.06
58.10
60.64
55.12
54.02
53.09
54.23
Depth to
Water 2
15.48
11.97
14.24
17.60
13.90
13.95
13.92
13.42
13.40
14.44
11.80
11.80
12.93
13.85
12.78
8.36
10.39
11.72
Elevation of
Water (MSL)
*
*
*
*
*
*
*
7.55
*
*
5.64
8
8
5.80
*
3.68
*
3.92
1
2

* _
All measurements are reported from the top of outer casing
All measurements are reported from the top of inner casing

Elevation of water referenced to mean sea level (MSL) not possible
since difference between inner and outer casing elevation not
measured.

-------
                                      -20-

                                    TABLE 3

                           Decontamination Procedures


Equipment*                                     Decontamination Method

Interface probe                                Cleaned  after  each  use with
                                               a pesticide grade hexane wipe,
                                               followed by a  rinse with distilled
                                               water and wiped dry.


* Teflon bailers were pre-cleaned before the inspections;  none were  reused
during the inspection, therefore, none had to be decontaminated.  Photavac Tip
and Interface Probe are registered trademarks and will  appear hereafter without®.


     6.  Task Force personnel calculated water-column volume  using height of
         water column and well casing radius.

     7.  When the Task Force was ready to sample the well, the EPA contractor
         purged three water-column volumes using Teflon bailers.  Table A indi-
         cates the method of purging each well.  Purge  water  was discharged
         directly into the oil/water separator and a pump station  near the oil/
         water separator.**  This pump station discharges water to the the fa-
         cility's wastewater treatment plant. (NOTE:  Sampling of  the  oil/water
         separator described below took place prior to  discharge of  the purge
         water into the oil/water separator).

     8.  EPA contractor collected an equipment blank for DAFB.  Equipment
         blanks were collected only for monitoring well samples.

     9.  EPA contractor collected a sample aliquot and  made field  measurements
         for pH, turbidity and conductivity.

    10.  EPA contractor filled sample containers using  both the methods and
         order specified in Tables 4 and 5.  Split samples were collected by
         filling one-third of each bottle for the Task Force  and facility
         bottles, respectively.  This process was repeated until each bottle
         was filled.  (The oil/water separator was sampled by immersing the
         sample bottles below the water and allowing the bottles to fill to
         the required level).

    11.  Samples were placed on ice in an insulated cooler.

    12.  EPA contract personnel took the sample to a staging area where total-
         metals, TOG, phenols, cyanide and nitrate/ammonia samples were preserved
         (Table 5).

-------
                                      -21-

     When the oil/water separator was sampled, steps 9,10,11. and  12 were  fol-
lowed in their respective order.  A 600 ml beaker was used to collect  5-500  ml
samples at each of the locations specified in Figure 4.  The 40  total  samples
were composited and samples to be-analyzed were collected from this  20 liter
composi te.


   ** Permission was granted by DAFB for the disposal of purge water in this
manner.  This was also approved by the DNREC and the Task Force.

-------
                                                  -22-
                                               FJgure 3

                           APPROXIMATE  SAMPLING LOCATIONS FOR THE COMPOSITE
                               SAMPLES  TAKEN AT THE OIL/WATER SEPARATOR
                                       122'
        Q>
15'
           !.5'
                                0
e
                                                                                                 24'
                                                             e - Scimple location

-------
23
101
102
103
                                               -23-

                                             Table 4

                                    Purging and Sampling Data
           Purging
         Unit   Date
                                                      Sampling
                                   Purge
                Time
         T-l   12/08/86   1525-1610



         D-5   12/08/86   1300-1350

         T-l   12/10/86   0845-0910

         D-5   12/09/86   0920-1000
Volume Method/
(Gal.) Remarks
15 Well recovered
as soon as i t
was purged .
25
14
26 Well recovered
Date
12/08/86
12/08/86
12/10/86
12/09/86
Method/
Time Remarks
1610-1640
1355-1616
0917-0940
1005-1056
NA
NA
NA
NA
D-5  12/09/86   1250-1329   22
as soon as i t
was purged. Rust
colored water.

Well recovered
as soon as it
was purged .
12/09/86   1250-1329
                                                                                        NA
10
T-l
T-l
D-10
T-l
D-10
T-l
D-10
D-10
D-4
12/09/86
12/09/86
12/09/86
12/09/86
12/10/86
12/10/86
12/10/86
12/10/86
12/10/86
1432-1445
0840-0900
1558-1627
1325-1335
1355-1425
1000-1005
1100-1130
0930-1000
1355-1430
2.5
8.5
21
2.5
22.5
3
22
24
22
12/09/86
12/09/86 .
12/09/86
12/09/86
12/09/86
Well recovered 12/10/86
as soon as i t
was purged .
Well cap missing.
Well recovered 12/10/86
as soon as it
was purged.
12/10/86
12/10/86
1505-1530
0912-0943
1630-1656
1338-1405
1435-1450
1010-1055
1140-1200
1010-1030
1443-1500
NA
NA
NA
NA
NA
Duplicate
sample
collected
Field bla
prepared .
Matrix
spike
NA
NA

-------
                                              -24-
                                      Table 4 (continued)
Well
Number

 12
        Purging
 Unit
 D-4
 Date
Time
12/10/86    NA
Purge
Volume
(Gal.)

 21
 09j
D-10
12/10/86  1545-1610  20.5
 13     D-4
        12/11/86  1125-1200   24
 11     D-4
        12/11/86  0845-0915
 Oil/water
 Separator
          NA
             NA
             NA
                                                           Sampling
 Method/
 Remarks

Ova detected
organics at
20-50 ppm in
wellhead casing;
background levels
in breathing zone.

Well recovered
soon as purged.
Rust colored
water.
Date
Time
                                    12/10/86  1615-1645
                            Ova detected
                            organics 10-100ppm
                            in wellhead casing.
                            Non-aqueous phase
                            approximately 0.2
                            inches thick on top
                            of water. Oily sheen
                            on water throughout
                            purge.
                                    12/11/86  1230-1255
                      21.5  Ova detected
                            organics 8-llppm
                            in wellhead casing.
                            Background levels
                            in breathing zone.
                                    12/11/86  0925-1009
           NA
                    12/08/86    1422-?
Method/
Remarks
                                    12/10/86  1605-1630   NA
                                                 NA
                                                 Cartridge
                                                 respirators
                                                 worn during
                                                 sampling as
                                                 a precautic
                                                 Sample of
                                                 immiscible
                                                 layer taken
                                                 NA
                     Compos!te
                     sample
                     taken. 8
                     locations,
                     5 samples
                     500 ml per
                     location

-------
                                      -25-

                                    Ta.ble 5
                           ORDER OF SAMPLE COLLECTION
                       BOTTLE TYPE AND PRESERVATIVE LIST
Parameter
Volatile organic analysis (VOA)
Purge and trap
Purgeable organic carbon (POC)
Purgeable organic halogens (POX)
Extractable organics
Pesticide/Herbicide
Di oxin
Total Metals
Dissolved Metals
Total organic carbon (TOC)
Total organic halogens (TOX)
Phenols
Cyanide
Ammonia
Sulf ate/chloride/ni trate
Bottle

2
1
1
4
2
2
1
1
1
1
1
1
1
1

40-ml
40- ml
40-ml
1-qt.
1-qt.
1-qt.
1-qt.
1-qt.
4-oz.
1-qt.
1-qt.
1-qt.
1-qt.
1-qt.
Preservative

VOA vials
VOA vials
VOA vials
amber glass
amber glass
amber glass
plastic HN03
plastic HN03
glass H2S04
amber glass
amber glass CuSO^ + E-^PO^
plastic NaOH
plastic H2S04
plastic
*A11  samples were stored on ice after collection and during transport to the
 analytical laboratories.

-------
                                      -26-
                              FACILITY DESCRIPTION







     Task Force personnel  obtained  information on past  and  present  industrial




and waste treatment operations to identify potential sources  of  hazardous waste




releases.  The information is identified  in this  section.







DAFB ORGANIZATION AND MISSION




     DAFB is the home of the 436th  Military Aircraft Wing equipped  with C-5




Galaxies which provide strategic airlift  capability.  The primary mission of




the Wing is to provide immediate airlift  of troops,  cargo and military equip-




ment and to participate in airland  or airdrop operations.







     In December 1941, activities began at Dover  Army Airfield and  continued




until the airfield was deactivated  in September 1946.  During this  period, the




Base supported patrol and training operations and served <3S a site  for the de-




velopment of air-launched rockets.   From 1946 to  July 1950, the  Air National




Guard conducted training exercises  at the airfield.   In July 1950,  the DAFB was




activated and in 1952, the Base mission was changed  from air and land defense




to cargo operations.







HAZARDOUS WASTE ACTIVITIES




     Hazardous wastes resulting from aircraft maintenance and operation have




been generated, stored and disposed of onsite since   1941.  Wastes include fuels,




oils, solvents, paints and paint thinners and are generated from general  mainte-




nance,  paint stripping, painting and engine  parts cleaning and degreasing.




Industrial wastewaters are also generated by engine  shops,  aircraft wash  racks




and engine  plating shops.







     Prior  to  1963, waste oils, fuels, solvents,  and paint were disposed  of in

-------
                                      -27-






in landfills and pits located onsite or taken to fire training areas  and burned




during the fire training exercises.  Wastewaters were generated primarily by the




engine build-up shop, aircraft wash racks,  and plating shops.  Wastewaters con-




tained paint and rust removers, methylene chloride, caustic soda, muriatic acid,




sodium cyanide and nitric acid, and were discharged to a storm drainage ditch,




the North Ditch (Unit DD-1, Figure 4), that drained to a tributary of the




Little River.






     In 1963, a spill containment system was constructed to capture spilled




solvents, paints, and other Wastewaters generated primarily by the engine build-




up shop.  This system included two (2) concrete lined oil/water separators, two




(2) unlined, earthen Industrial Wastewater (IW) basins approximately 0.5 acres




in size, and a 15,000 gallon underground storage tank.  Wastewaters passed




through the oil/water separator, with floatable oil, and solvents removed for




storage in the underground tank and then to the earthen IW basins prior to dis-




charge to the North Ditch.  Other industrial wastewaters, however, were still




discharged directly to the North Ditch.  In 1968, the IW basins began accepting




plating shop wastewaters.






     Discharge from the IW basins to the North Ditch was terminated in  1969.




From 1969 to  1975, effluent from the IW basins was routed to an onsite waste-




water treatment facility.  From 1975 to the present, effluent from the  IW basins




has been discharged to the Kent County Regional Wastewater Treatment System.






     In July  1985, waste discharge was rerouted and the IW basins were bypassed.




Closure of these units was completed in August 1986 under a State of Delaware




approved closure plan (plan approved March 29, 1985).  The approved closure plan

-------
                                      -28-






called for Che removal of all free liquids and sludge from the IW basins and




excavation of underlying soil to a depth of six (6) inches.  On August 25,  1986,




the DAFB submitted to the State a Part B RCRA permit application for post closure




care of the IW basins.  This application is currently under State review.

-------
                                   -29-
                             FIGURE 4

                    NORTH DRAINAGE DITCH (UNIT DD-1)
                                                  r
LEGEND

___ USAF Property Lin«
_ " _ Drainage Channel
              Con«m«ww»
        Ph..« II Sit.

-------
                                      -30-
         **          ~


     Studies conducted by EPA's FIT contractor in August  1982  indicated  contami-


nation of ground-water and soil onsite.   Subsequently,  in October 1982,  Roy F.


Weston Designers and Engineers were tasked by DAFB to investigate ground-water


contamination at the IW basins.  Under this investigation, three ground-water


monitoring wells (101,102,103) were installed.  Samples taken from these wells


showed elevated levels of several volatile organic carbons (VOCs) including


1,1,1-trichloroethane, tetrachloroethylene, and trichloroethylene.




     As a result of these findings, the DAFB began a Base wide investigation


under the Installation Restoration Program (IRP).  The IRP is the framework


whereby Department of Defense  (DOD) facilities conduct CERCLA-mandated activites,


The IRP was designed to identify and evaluate hazardous waste disposal sites at


DOD facilities, to control the migration of hazardous substances and  to limit


the hazards to human health and the environment.  The IRP consists of four


phases:  Phase I, Initial Assessment/Records Search; Phase II, Confirmation/


Quantification; Phase III, Technology Base Development; Phase IV, Operations/


Remedial Actions.  Phase I was completed in October  1983 and included record


searches, personnel interviews, and site inspections.  Phase II, Stage  1 of  the


IRP was completed in June 1986.  This phase included further site study and


sampling.   Results of sampling and analysis showed elevated levels of VOCs and


metals in the ground-water.   Further study is being  undertaken under  Phase II,


Stage 2 and Phase IV, including hydrogeologi c studies.




SOLID WASTE MANAGEMENT UNITS  (SWMUs)


     DAFB identified fifty-five  (55) solid waste management units (SWMUs) and


eight (8) areas onsite which  were  not necessarily  SWMUs,  but from which


releases  had  occurred, in a September  1986 Phase  II  IRP  study (Figures  5-9).

-------
These units are listed below.
                                      -31-
       Unit Name/Number
DAFB Classification
1).
2).
3).
4-15).
16).
17).
18).
19).
20).
21).
22).
23).
24).
25).
26).
27).
28).
29).
30).
31).
32).
33).
34).
35).

36).

37).


Fire Training Area No. 1
Fire Training Area No. 2
Fire Training Area No. 3
Landfills No. 1-12
IW Basi ns
Hospital Incinerator
Fleet Services Incinerator
Old Waste Treatment Plant
Hazardous Waste Storage Yard
Underground Waste Liquid Storage Tank
Whiskey Tank
Entomology Shop (Building 921)
Heavy Maintenance Waste Oil Tank
Auto Hobby Shop Waste Oil Tank
North Ditch
Sludge Spreading Area
Acid Neutralization (Building 711)
Acid Neutralization (Building 615)
Acid Neutralization (Building 635)
Drum Accumulation (Building 719)
Drum Accumulation (Building 721)
•Drum Accumulation (Building 615)
Defense Reutilizati on Materials Office
Base Gas Station Waste Oil Tank
(Building 517)
Collection Pit for Wash Racks
(Building 583)
Industrial Waste Collection System Drain
a. Open Wash Rack
b. Corrosion Control Wash Rack
FT-1
FT -2
FT-3
D-l to D-12
T-l
T-2
T-3
T-4
S-l
S-2
S-3
S-4
S-5
S-6
DD-1







DRMO





Facility 66223

            (Building 582)
         c. Aircraft Wash Rack
            (Building 706)
         d. Engine Shop (Building 725)
         e. Engine Shop (Building 719)
         f. Paint and Fiberglas Shop
            (Building 721)
         g. Aircraft Maintenance Shop
            (Building 724)
         h. Battery Shop (Building 635)
         i. Refueling Vehicle Maintenance
            (Building 636)
         j. Lift Stations (Buildings 583,719,724,635)

-------
                      -32-

                  FIGURE 5

           SOLID WASTE MANAGEMENT UNITS
syv.
    DOVER AFB
TREATMENT
 FACILITIES
                 HOSPITAL INCINERATOR
                          \
                                SOURCE: DOVER AFB IHSTAILATIOM DOCUMENTS

-------
11  ****^~}

-------
                                  -34-


                              FIGURE 7

                        SOLID WASTE MANAGEMENT UNITS
                                           ^HAZARDOUS WASTE
                                              STORAGE YARD
                                                BLDQ. 1306
                                                BLDG. 1305
                                                       X
                            AUTO HOBBY TANK'
          8-3   V
        ! WHISKEY
        JP-4 TANK
                                                     DOVER AFB
                                             STORAGE SITES
 ENTOMOLOGY
    SHOP  ^
             /
SOURCE: DOVER AFB INSTALLATION DOCUMENTS

-------
                                    -35-
                                FIGURE 8
                           SOLID WASTE MANAGEMENT UNITS
            SD-1
     SLUDGE DISPOSAL AREA

V' N/\^

/  X.   ""V   ,D-4
X   ;'^N.   LIQUID WASTED ~
  N  (7  XX DISPOSAL SITE _J   f
   X./^X ^xx /^ fr^fjh      ^
                     )-5 /// \
                  -.SANITARY LANDFILL
                                                         DOVER AFB
                                                DISPOSAL  SITES
                                                           D-7
                                                         LANDFILL
    D-8
DISPOSAL SITE
                                                           D-12
                                                  CONSTRUCTION RUBBLE DUMP
                  " SANITARY LANDFILL
                             «>
                      ,„..«,.
                                N\  \ 0-10
                                SANITARY LANDFILL
     SANITARY LANDFILL
                                               SOURCE: DOVER AFB INSTALLATION DOCUMENTS

-------
                                       -36-


                                   FIGURE 9


                            SOLID WASTE MANAGEMENT UNITS
                                         '~~~
                                                JP-4 PIPELINE LEAK
                          METERING PIT SPILL
                                      SP-3v.
                                     PIPELINE LEAK*
        SP-5 & 8P-8   \
       JP-4 TANK SPILLS
      DOVER AFB
SPILL SITES
TANK OVERFLOW
•ounce: DOVER Art INSTALLATION DOCUMENTS

-------
                                      -37-
38-55)  Oil/Water Separators

    38).   Building 583 Collection Pit for Wash Racks
    39).   Building 635 Battery Shop
    40).   Building 636 Regueling Vehicle Maintenance
    41).   Building 725 Jet Engine Inspection
    42).   Primary Separators at IW Basins (could be a regulated unit)
    43).   Building 613 Jet Engine Test Cell
    44).   Building 711 Battery Shop
    45).   Building 945 C-5 Fuel Cell Dock
    46).   Building 715 Nose  Dock
    47).   Building 794 High  Reach Truck Storage, etc.
    48).   North Storage Tank Farm (4 Separators)
    49).   South Storage Tank Farm (3 Separators)
    50).   Fuel Oil Storage Tank Farm (4 Separators)
    51).   Building 124 Auto  Hobby Shop
    52).   FT-3
    53).   Building 914 Storage of pesticides, fertililizers,
          salts, snow removal equipment
    54).   Whiskey Tank
    55).   Building 918

Other Releases:

     1).   JP-4 tank valve spill                             SP-1
     2).   Diesel fuel tank spill                            SP-2
     3).   JP-4 pipeline leak                                SP-3
     4).   JP-4 pipeline leak                                SP-4
     5).   JP-4 spills (North Storage Tank Form)             SP-5,6,8
     6).   Metering Pit spill
     7).   XYZ Site fuel spill                               SP-7
     8).   Motor Pool Gas Station spill                      XYZ
          (Building 637)                                    SP-9


     Below is a more complete description of these units.  All conclusions

presented in these descriptions were those reached by the DAFB as a result of

the IRP studies.


1.   Fire Training Area No.l (FT-1)

     This unit covered an area of approximately 50 feet by 900 feet located on

the golf  course, east of the drainage ditch which bisects the course NE-SW.

Operations at the site began in 1951 and consisted of spreading at least  1000

gallons of waste fuels and liquids on a water saturated area, igniting the

material, and using protein foams to extinguish the flames as a training

-------
                                      -38-
exercise.  Exercises were reportedly conducted twice a week through the area's




period of operation, at several areas within the 50 foot by 900 foot area (exact




location undertermined).  These operations terminated in either 1959 or 1962.




FT-1 was addressed in the IRP Phase II, Stage 1 study and conclusions stated




that the unit has not affected environmental quality, however ground-water




samples showed anomalous TOC and TOX valves.






2.   Fire Training Area No.2 (FT-2)




     This unit was small pit (60 feet by 40 feet) near Building 702.  The IRP




Phase II Stage 1 report stated that fire training activities probably did not




take place at this location.  This conclusion was based on interviews conducted




with DAFB personnel prior to the start of IRP field activities.  The site was,




therefore, excluded from an IRP monitoring program.






3.   Fire Training Area No. (FT-3)




     This unit is located in the northeast section of the DAFB, east of the




N/S runway and west of Sites D-A and D-5.  It has served as the Base fire




training area since 1962.  The original site was located slightly northeast of




the existing site and has been described as a pit used to dispose of oils,




paints, and other liquid industrial wastes.  In the  1960's and early 1970's




training exercise using at least 1000 gallons of contaminated waste oi] and




fuel were conducted at the site twice per week.  Drums of waste oil and fuel




were reportedly delivered to the site and stored until used.  Current training




exercises at the existing area are conducted four times per year and use approxi-




mately 200 to 700 gallons of JP-4 jet fuel.  Unconsumed fuel, foam and water




are drained to an oil/water separator.  It is a DAFB conclusion, based on IRP




studies, that FT-3 may have caused an increase in TOC levels in the ground-water.

-------
                                      -39-
4.   Landfill No. 1 (D-l)




     This unit was a three acre fill approximately 6 feet deep used during the




early 1950's through the late 1960's, and now overlain by several feet of soil




and grass cover.  D-l was located in the eastern portion of the Base.  It is




DAFB's opinion that there has not been any evidence of a release from this unit




to date.






5.   Landfill No.2 (D-2)




     This unit is a 3 to A acre fill approximately 8 feet deep, used since the




early 1960's, located near the eastern boundary of the Base.  The landfill is




currently used for the disposal of construction debris and rubble.  The eastern




edge of unit is a level area which consists of concrete and debris.  It is DAFB's




opinion that there has been no evidence of a release from this unit to date.







6.   Landfill No.3 (D-3)




     This unit was a trench approximately 35 feet wide,  100 foot long and 6




feet deep.  It is located in the eastern portion of the facility, southeast of




unit D-2 and is now covered with grass.  The unit was reportedly used for only




about 6 weeks during the  1960's.  It is DAFB's opinion  that there has not been




any evidence of a release from this unit to date.






7.   Landfill No.4 (D-4)




     This unit was a liquid waste disposal site operated in the  late  1950's in




the northeast portion of  the base,  east of unit FT-3.   The  landfill was a single




trench, approximately  15  feet wide,  100 feet long  and  10 feet  deep.  The  IRP




Phase II, Stage  1 study  stated that  the entire area of  sites  D-4, D-5. and'  SD-1




demonstrated evidence of waste disposal activity  (disturbed ground, subsidence,




dead vegetation).  Releases  to have  been detected  by  the IRP  by  elevated  levels




of VOC  and  oil  and grease in the ground^water.

-------
                                      -40-






8.   Landfill No. 5 (D-5)




     This unit was an area fill operated during the 1960's of reportedly less




than 0.5 acres and 8 feet deep, located east of unit D-5.  Releases to the




ground-water may have occurred from this unit or nearby D-A.  Elevated levels of




VOC's and metals have been detected in the ground-water according to the IRP.






9.   Landfill No. 6 (D-6)




     This unit was reportedly a 1 acre trench fill approximately 6 feet deep,




operated during the 1960's located in the southern portion of the facility,




along the eastern boundary.  It is DAFB's opinion that there has been no evidence




of a release from this unit a date.






10.  Landfill No.7 (D-7)




     This unit is a 7 acre trench fill operated during the 1960's excavated to




a depth of approximately 32 feet.  It is located in the southern portion of the




of the facility, along the eastern boundary.  It is DAFB's opinion that there has




been no evidence of a release from this unit to date.






11.  Landfill No.8(D-8)




     This unit was a trench fill 35 feet by 300 feet and 10 feet deep operated




in the early 1970's and located in the northwest portion of the facility.  It




is DAFB's opinion that there has been no evidence of a release from this unit




to date.






12.  Landfill No.9 (D-9)




     This unit was a 7 to 8 acre area fill operated during the early  1950's




excavated to a depth of approximately 8 feet.  It is located along the western




portion of the golf course along the drainage ditch.  It is DAFB's opinion that




there has been no evidence of a release from this unit to date.

-------
                                      -41-
13.  Landfill No. 10 (D-10)




     This unit included four trench fills that occupied a total  area of 3 acres




(40 feet by 600 feet each), excavated to a depth of approximately 15 feet.  The




landfill is located on the eastern edge of the golf course and was operated




during the 1950's.  Releases to the ground-water have been detected, primarily




trichloroethylene, TOC, TOX, and metals.






14.  Landfill No. 11 (D-ll)




     This unit was a 2 acre area fill, excavated to a depth of approximately 8




feet.  It was located in the western portion of the facility, near base housing




and -just outside the 100 year flood limit.  It is DAFB's opinion that there has




been no evidence of a release from this unit to date.






15.  Landfill No. 12 (D-12)
     This unit was reportedly a 4 acre area fill used in the 1960's located in




the southern portion of the facility.  It is DAFB's opinion that there has been




no evidence of a release from this unit to date.






16.  IW Basins (T-l)




     This unit covers approximately  19,200 square feet and historically received




waste liquids (after passage through an oil/water separator) from the Industrial




Waste Collection System.  The unit began operation in 1963 and was closed under




a RCRA closure plan in  1986.  Releases to groundwater have been detected.






17.  Hospital Incinerator (T-2)




     This unit is an oil-fired incinerator used for burning of pathogenic wastes




and hospital trash.  It is located in the central portion of the facility.  The




incinerator began operation in 1921, was replaced in 1983 and is presently active




It is DAFB's opinion that there has  been no evidence of a release from this unit




to date.

-------
                                      -42-






 18.  Fleet  Services Incinerator (T-3)




     This unit is an oil-fired incinerator, located in the center of the facility.




 This unit became active in  1972, and remains active.  It-is DAFB's opinion that




 there has been no evidence  of a release from this unit to date.






 19.  Old Waste Treatment Plant (T-4)




     This unit was a plant  operational from 1943 to 1975, used for treatment of




 sanitary wastes and a located along the southwest boundary of the facility.  It




 is DAFB's opinion that there has been no evidence of a release from this unit




 to date.






 20.  Hazardous/Waste Storage Yard (S-l)




     This active unit is located at Building 1305 and 1306 in the southeastern




 section of the base and consists of the two buildings separated by an outdoor




 storage/yard.  Releases, primarily VOC's and metals, have been detected the




 ground-water.







 21 .  Underground Waste Liquid Storage Tank (S-2)




     This unit was a 15,000 gallon underground waste liquid storage tank which,




 prior to its removal in 1986, received the oils from the IW basins oil/water




 separator.  When full, the  liquids were removed from the tank by a contractor.




The unit has been replaced by an above-ground  tank adjacent to the old unit.




It is DAFB's opinion that there has been no evidence of a release from this




unit to date.






22.  Whiskey Tank (S-3)




     This active unit is an underground storage tank located in the northwestern




portion of the facility.  The tank holds oils  collected by an oil/water separator.




 It is DAFB's opinion that there has been no evidence of a release from this unit.

-------
                                      -43-


23.  Entomology Shop, Building 921 (S-4)

     The active unit is a building used for storage of pesticides.   Empty drums

are also cleaned in this building.  It is located at the western boundary of the

base.  It is DAFB's opinion that there has been no evidence of a release from

this unit.


24.  Heavy Maintenance Waste Oil Tank, Building 780/781 (S-5)

     This active unit is an 1000 gallon underground waste oil tank for small

quantities of waste oil generated by heavy maintenance in Building 780 and 781.

It is located between the two buildings.  The oil is disposed of by contractor.

It is DAFB's opinion that there has been no evidence of a release from this

unit to date.


25.  Auto Hobby Shop Waste Oil Tank, Building 124 (S-6)

     This active unit is an underground waste oil storage tank outside of the

Auto Hobby Shop.  The oil is disposed of by a contractor.  It is DAFB's opinion

that there has been no evidence of a release from this unit  to date.


26.  North Drainage Ditch (DD-1)

     This unit was located in the northern portion of  the base and extends for

approximately 3000 feet.  The ditch was approximately  40 feet wide and  15 feet

deep.  Weeds, tall grasses, and small trees grow along the bottom of the ditch.

The unit was operational during the 1950's and  1960's  and ceased use in  1969.

There is a high potential for a release from this unit due to the nature of
                                                                             «
activities conducted.


27.  Sludge Spreading Area (SD-1)

     A rectangular area, located in the northeast portion of  the base, where

-------
                                      -44-






sludge from the Old Waste Treatment Plant  (unit  T-4)  was land applied.   The




area was operated from 1943-1975.  It is DAFB's  opinion that  there  has  been no




evidence of a release,  but the unit has a  high release potential  due  to activi-




ties conducted.






28.  Acid Neutralization, Building 711




     This active unit is a battery shop in which batteries are recharged.   For




old batteries, the acid is neutralized and sent  to the sanitary sewage  system




the battery is discarded.  It is DAFB's opinion  that  there has not  been any




evidence of a release from this unit to date.






29.  Acid Neutralization, Building 615




     This active unit is a battery shop in which batteries are recharged.   For




old batteries, the acid is neutralized and sent  to the sanitary sewage  system




and the battery is discarded.  It is DAFB's  opinion that there has  been no




evidence of a release from this unit to date.






30.  Acid Neutralization, Building 635




     This active unit is a battery shop in which batteries are recharged.   For




old batteries, the acid is neutralized and sent  to the sanitary sewage  system




and the battery is discarded.  It is DAFB's  opinion that there has  been no




evidence of a release from this unit to date.






31.  Drum Accumulation, Building 719




     This unit is a drum accumulation site for waste  liquids  generated  in




Building 719.  Th drums are labeled for proper usage  and, when full,  removed to




the Defense Reutilization Materials Office (DRMO).  It is DAFB's opinion that




there has been no evidence of a release from this unit to date.

-------
                                      -45-






32.  Drum Accumulation,  Building 721




     This active unit is a drum accumlation site for methylethyl ketone,  toluene




and PD-680 product used in Building 721.  Spent fluids are also located in the




same area for accumulation prior to removal to DRMO.  It is DAFB's opinion that




there has been no evidence of a release from this unit to date.






33.  Drum Accumulation,  Building 615




     This active unit is a drum accumulation site for waste oils generated in




the Power Production Shop (Building 615) prior to their removal to DRMO.   It




is DAFB's opinion that there has been no evidence of a release from this  unit




to date.






34.  Defense Reutilization Materials Office (DRMO)




     This active unit is a collection point for waste liquid drums and any




saleable refuse.  It is located near the center of the base.  It is DAFB's




opinion that there has been no evidence of a release from this unit to date.






35.  Base Gas Station Waste Oil Tank, Building 517




     This active unit is a small above-ground waste oil storage tank locatd at




the Base Gas Station.  It is DAFB's opinion that there has been no evidence of




a release from this unit to date.






36.  Collection Pit for Wash Racks, Building 583




     This active unit is a building containing an oil/water separator which




receives drainage from the aircraft wash racks.  It includes a screen to  retain




paint chips which the influent passes through prior to treatment in to treatment




in the oil/water separator.  The paint chips are drummed in the building.  When




the drums are full, they are removed to the DRMO.  The building is located in

-------
                                      -46-


the central portion of the facility* near the wash racks.  It is DAFB's opinion

that there has been no evidence of a release from this unit to date.


37.  Industrial Waste Collection System Drain

     This active unit, in operation since 1963, is a concrete drain system

which collects industrial waste runoff from operations in many of the industrial

shops.  (The oil/water separators which are a part of the system are discussed

separately).  The system leads eventually to the IW Basins oil/water separator.

Components of the system are listed as follows:

       a). Open Wash Racks (Facility 66223)
       b). Corrosion Control Wash Rack (Building 582)
       c). Aircraft Wash Rack (Building 706)
       d). Engine Shop (Building 725)
       e). Engine Shop (Building 719)
       f). Paint and Fiberglass Shop (Building 721)
       g). Battery Shop (Building 635).
       h). Refueling Vehicle Maintenance (Building 636).
       i). Lift Stations (Building 583, 719, 724, 635).

     It is DAFB's opinion that there has been no evidence of a release from

these units to date.


38-55 Oil/Water Separators

     These active units are oil/water separators which drain to one of three

drainage systems:  industrial waste collecltion, storm drainage, or sanitary

sewage.  Due to their similarity, they will be listed together.  Date in paren-

thesis are dates units began operations.  Their locations are listed as follows:

       38. Building 583, Collection Pit for Wash Racks (1959)
       39. Building 635, Battery Shop (1956)
       40. Building 636, Refueling Vehicle Maintenance (1964)
       41. Building 725, Jet Engine Inspection (1971)
       42. Primary Separators at IW Basins  (1963)
       43. Building 613, Jet Engine Test Cell (1971)
       44. Building 711, Battery Shop (2971)
       45. Building 945, C-5 Fuel Cell Dock (1970)
       46. Building 715, Nose Dock  (1975)

-------
                                      -47-
       47. Building 794, High Reach Truck Storage, etc (1975)
       48. North Storage Tank Farm (4 Separators) (1956,1957,1960,1960)
       49. South Storage Tank Farm (3 Separators) (1953,1955,1955).
       50. Fuel Oil Storage Tank Farm (4 Separators) (1955,1955,1955,1975).
       51. Building 124, Auto Hobby Shop (1962)
       52. FT-3 (1978)
       53. Building 914, Storage of Pesticides, Fertilizers. Salts, Snow Removal
           Equipment (1959).
       54. Whiskey Tank (approximately 6-10 years old)
       55. Building 918 (1959)


     It is DAFB's opinion that there has been no evidence of a release from

any of these units to date.


Other Releases
1.   JP-4 Tank Valve Failure (SP-1)

     On October 21, 1982, approximately 3,800 gallon of JP-4 jet fuel was

spilled.  JP-4 flowed into a drainage ditch.  JP-4 was pumped out of the ditch

and the ditch and ramp were cleaned up with absorbent pads.  These pads were

drummed and disposed.


2.   Diesel Fuel Tank Spill (SP-2)

     On January 11, 1980, between 350 and 400 gallons of diesel fuels spilled

from an outside tank near Building 615.  A valve split allowing fuel to leak

onto the ground and flow into a drainage ditch.  The oil was contained and

pumped out of the ditch.  The ditch was then cleaned with absorbent pads.


3.   JP-4 Pipeline Leak (SP-3)

     In 1978, a leak was found in the JP-4 fuel pipeline near facility 534.

An unknown amount of JP-4 leaked into the surrounding soil.  The line was

repaired and the spilled JP-4 was contained and removed using absorbent pads.


4.   JP-4 Pipeline Leak (SP-4)

     In 1975, near Building 1310, a leak in a JP-4 fuel pipeline was found.

-------
                                      -48-
Th e duration and amount of the leakage was unkown.  The leak was repaired;




however, the extent of cleanup practices is not known.  The site was monitored




as a part of the IRP Phase II Stage 1 study.  Three well points around the area




were sampled for TOC and oil and grease (pol,po2,po3).  Oil and grease levels




were below background in the three samples; TOC levels detected in well points




p02 (4.9 ppm) and po3 (32 ppm) exceeded background for the Columbia aquifer




(3.2 ppm).






5.   JP-4 Tank Spills (SP-5, SP-6, SP-8)




     In 1975, a valve failed on JP-4 fuel tank 733 (North Storage Tank Farm).




The quantity of fuel spilled was not known; however,  the soil was contained by




the bermed area surrounding the tank. The fuel was pumped out of the bermed




area and reclaimed by filtration.






     In 1970, Tank 733 was overfilled with JP-4 jet fuel.  Approximately 30,000




gallons spilled into the bermed area.  The fuel was recovered and reclaimed.






     In 1979, an 18,000 gallon spill occurred at Tank 733.  The JP-4 fuel was




confined by the bermed area and was recovered.






6.   Metering Pit Spill (SP-7)




     In March of 1978, approximately 700 gallons of JP-4 fuel pumped from a




metering pit near Building 534.  The fuel was accidentally pumped over a paved




area.   The fuel was cleaned up with absorbents.






7.   XYZ Site Fuel Spill (SP-8)




     DAFB personnel reported that rainwater in manholes in the area of Build-




ing 950 contained what appeared to be a layer of fuel.  Ground-water samples

-------
                                      -49-






were collected in 1986 from four well points and two sediment samples were




collected from two manholes.  It was determined that the ground-water and sedi




ments contained levels of oil and grease and TOC above background levels.






8.   Motor Pool Gas Station Spill (SP-9)




     In October 1984, a fuel leak at the DAFB motor pool was discovered.  The




leak was repaired.  Ground-water samples from several DNREC wells located




downgradient of the spill showed elevated levels of TOC.

-------
           v          •;.               -50-







                           SITE GEOLOGY/HYDROGEOLOGY







TOPOGRAPHY/SURFACE DRAINAGE




     The Dover Air Force Base (DAFB) is located on a broad level plain approxi-




mately 1 mile west of the Delaware Bay and 3.5 miles southeast of the city of




Dover, Kent County, Delaware.  The base is situated within the Atlantic Coastal




Plain Physiographic Province known regionally as the Delraarva Peninsula distin-




guished by broad sandy plains of low relief dissected by meandering streams and




rivers.  Surface elevations vary from approximately + 10 feet MSL along the




Saint Jones River southeast of the base to about +30 feet MSL along the bases




western border (Figure  10).







     The higher elevations along the southeast-northwest trending runway parallel




what is considered a drainage divide.  Surface waters flow away  from the divide




to the northeast and southwest.  Storm water and nonprocess waters are discharged




to several surface water diversion ditches (Figure  11) North  of  the divide, sur-




face waters flow northeast through Pipe Elm Branch  and Morgan Branch to the




Little River and south  of the divide, to the Saint  Jones River.  Both the Little




and  Saint Jones Rivers discharge in the Delaware Bay.







SITE GEOLOGY/HYDROGEOLOGY




     Published reports  from a number of sources including the Delaware Geologic




Survey and United States Geologic  Survey are readily available which address




geologic/hydrogeologic  conditions  particular to the Atlantic  Coastal Plain  in




Delaware.   With respect  to the base, however,  hydrogeologic  information is  some-




what limited.  Specific  information has been developed  by various  DAFB  consultants




as part of  the Installation  Restoration Program  (IRP).

-------

-------
                                    -52-
                             FIGURE
                     INSTALLATION DRAINAGE
                                               r
LEGEND

   	USAF Property Lin«
       Drainage Direction
                                            J
              To  Moroan Branch
/s
                                                                   To PIP«
                                                                   El.n Branch

-------
                                        -53-
The information to follow was derived primarily from the Phase I and II




IRP reports, selected references and discussions with Base personnel unless




otherwise indicated.




     DAFB is located in the Atlantic Coastal Plain Province.  The coastal




plain is described as a wide expanse of sedimentary deposits consisting




of sand, gravel, clay, shale, limestone, chalk and marl dipping to the




southeast.  The western boundry of the province is termed the Fall Line




which denotes the contact between areas underlain by crystalline rocks




(Piedmont Province) and unconsolidated deposits.  Crystalline rocks are




at or near the surface at the Fall Line but are found at increasing depths




progressing in a south easterly direction.  Successively younger formations




outcrop closer to the coast due to the slight southeasterly dip




(Figure 12).




     The underlying geology exhibits a layer cake stratigraphic sequence




common to the Coastal Plain.  The base is underlain by alternating




deposits of Pleistocene and Miocene sands and clays of the Columbia and




Chesapeake groups, respectively.   The sands serve as aquifers and the clays




confining units.  The generalized stratigraphic sequence from the surface




downward includes the Columbia Formation (Pleistocene), the Kirkwood (Miocene)




Formation followed by the Frederica, Cheswold and Piney Point aquifers (with




intervening confining units) at successively greater depths.  The Columbia




Formation consists of medium to coarse sand with thin discontinuous lenses of




of silty clay and gravel.  The sand exhibits a color range from reddish brown




through shades of yellow and grey depending upon the amount of iron present.

-------
                                                -54-


                                          FIGURE 12
                               GENERALIZED GEOLOGICAL  SECTION
                                                                                      GEOLOGIC
                                                                                      COLUMN
    *Mi*** '    CKSKC1.0 OOVtH  •OOOJiOt	ft'.'OW
• SO'
TOO-



710.



•00-



MO-



XX3
          -omiDnrM. VUut
0  I 5 • i MlLtS
 I 1 I I I I
0 2 « « *


 vCKTICAL  OMOCHITIOM <
                              \V -  i-Xx^
                                v%\ \x-1"'
                                 ^>ix\  N
%^
 v«x
  '<
                                      T0 'W4
                                                                              •1NCT  |-^«0
                                                                              •01 NT  !
                                                                              •01
                                                                            FOWWAnON
           >
                  4*4 «.>•• or MCTIO*
                                                  .XPU4NATION
                                                  --- — 4PMOIIMATC  OOWXO* LIMIT
                                                        rmCT ro
-------
                                      -55-






     Below the Columbia and depths ranging from 33 feet to 63 feet below ground




surface is the Kirkwood Formation (Miocene) described as a silty clay with




stringers of fine grained sand.  This formation is considered the uppermost con-




fining unit.  During the initial Phase II drilling program, the formation was




found to consist of firm, dense, dark grey, silty clay with traces of fine sand




and silt laminations.  Information regarding the thickness of the Kirkwood For-




mation or the lithology of Frederica aquifer is unavailable since monitoring




wells did not fully penetrate  these units.  However, drilling records for  U.S.G.S.




test well No. JE 32-4  located  on  DAFB property indicates  the thickness  of  both




the Kirkwood  Formation and Frederica aquifer is approximately  20  feet (Figure  13).






     Underlying  the Kirkwood and  Frederica, in descending  order,  are the  Cheswold




and Piney Point  aquifers each  separated  by confining units ranging in composition




from clay clayey sand  or sandy silt.  The  Cheswold  consists  of  fine  to  coarse




sand and shells.  Aquifer  thickness  ranges from zero  to more than 150 feet and  is




approximately 50 to  75 feet thick in  the Dover area.   The  dip  of  the aquifer  is




reported to  be  about  11  feet/per  mile (.21%) between  Symrna  and  Dover.   Separating




the Cheswold  and Piney Point aquifers is a thick  silty sand  layer which serves  as




a  confining unit.  The Piney Point consists of green  fine  to medium  glauconitic




sands.   The  aquifer  achieves a maximum  thickness  of 251  feet.   Thickness decrease




to zero  both updip and downdip and to the northeast and  southwest along strike




giving the  aquifer a  lenticular shape.

-------
                                         -56-




                                 FIGURE  13
GROUND

SURFACE

ELEVATION.

23.7 FEET.

MSL
     LOG OF USGS  TEST WELL



     DEPTH BELOW

     QROUNO SURFACE
          COLUMBIA AQUIFER


   ~~ 4*  KIRKWOOO FORMATION

IZ2Z SB  FREDERICA AQUIFER
                            CONFININO UNIT
                     — 175
                           CHESWOLO AQUIFER
                     — 247
                           CONFINING UNIT
                     — 334
                            P1NCY POINT AQUIFER
                     — 569
                            RANCOCA4 GROUP
                    I— 737
                            MONMONTH GROUP
                     1—942
                            MATAWAN GROUP
                     I— 1275
                            MAQOTHY FORMATION
                     I— 1375
                            RARITAN FORMATION
•o

m
                                                     m

                                                     m
                                £

                                5
                                o
                                m
                                z
                                m
                                                  m
                                                  O
                                                  m

                                 m

                                 O
                                 O
                                                  m
                                                     LEGEND
                                 •a
                                 •«
                                 m
                                 a

                                 o
                                 a
                                 m
                                 •H
                                 >
                                 O
                                 m
                                 O

                                 (•
        SAND OR SAND AND GRAVEL






        SB.TCV5CLAY





        SILTY. CLAYEY SANO,

        SANOY SIUT OR SANOY CUAY
                     I— 1422

-------
                                      -57-






HYDROGEOLOGIC UNITS




     A complete hydrogeologic assessment of DAFB is currently being conducted




under Phase II (Stage IV) of the IRP.  The following describes hydrogeologic




conditions at the base as interpreted from site characterization work performed




by DAFB contractors under the IRP to date.






     Two sets of monitoring wells have been constructed at the base.  The 100




series wells in 1982 and the initial set of Phase II IRP wells in 1984.  Both




sets of wells, were installed in the Columbia aquifer with one distinct dif-




ference: the 100 series wells terminate at depth of 20 feet below ground surface




while the IRP wells terminate at the contact between the Columbia aquifer and the




Kirkwood Formations at depths ranging from 33 to 64 feet below ground surface.




Since existing monitoring wells penetrate only the upper few feet of the Kirk-




wood Formation, hydraulic/lithologic characteristics of deeper aquifers, are




unclear, other than what information was attained from the literature search.






     The major water bearing zone encountered during monitoring well installa-




tion was within the surficial Columbia Formation identified and monitored as the




uppermost aquifer.  Depth to water ranges from 6 to 15 feet below ground surface




under water table (unconfined conditions).  The saturated thickness of the Co-




lumbia, based upon depth to water measurements taken from fully penetrating




wells (IRP series) ranges from 17.50 feet near site T-l (IW basins) to 50.50




feet near sites D-4 and D-5.  On average, the saturated thickness under the




four sites investigated is 40.17 feet.  All reports indicate the Columbia For-




mation is laterally continuous underneath the base, although its variability in




thickness suggests an undulating contact between it and the Kirkwood Formation.

-------
                                      -58-






     Although no direct testing of aquifer characteristics has been performed at




the base, a definitive study of the Columbia aquifer conducted by Johnston (1973)




indicates the aquifer, if generally, a medium to coarse sand and that local changes




in its lithology and saturated thickness greatly effect aquifer transmissivity.




Average transrai ssivity and hydraulic conductivity values of 7,000 feet 2/
-------
                                      -59-
GROUND-WATER FLOW AT DAFB




     A potentiometric surface map for the Columbia aquifer (Figure 14) based on




measurements taken on January 9,  1985 from monitoring wells, was developed by IRP




consultants.  The map exhibits, a ground-water divide oriented NW-SE paralleling




Atlantic Avenue, from which ground-water flows to the northeast towards Morgan or




Pipe Elm Branch and southwest towards the Saint Jones River.  To confirm the




existence of this flow divide, further site evaluation is required.







GROUND-WATER FLOW AT INDIVIDUAL SITES




     Potentiometric surface maps for each site under investigation have been de-




veloped based upon water levels measured in monitoring wells.  One map was con-




structed for sites D-4 and D-5 given their close proximity.  Each site is ad-




dressed separately and maps are presented on Figures 15,  16, and 17.  (In devel-




oping contour maps, water table elevations were converted to MSL based upon sur-




veyed top of outer casing elevations and average values for the distance between




Inner and outer casing for the five wells from which such measurements were




taken).







Site T-l
     The configuration of the water table in the vicinity of the IW basins sug-




gests possible mounding conditions due to enhanced recharge.  This effect re-




sults in a reversal in the hydraulic gradient evidenced by a secondary component




of flow to the northeast.  This deviates from the predicted flow path to the




southeast towards the Saint Jones River (Figure  15).  The hydraulic gradient is




estimated at .20% and a ground-water flow velocity of .90 feet/day was calculated




(SAIC 1986).

-------
                                         -60-

                                 FIGURE  14

                         WATER  TABLE ELEVATION
                LEGEND
                                       r
                                                                        7
USAF Property Line
Drainage Channel
Phase II Site
Monitoring Well
	8 —
Groundwater Contour Line
Estimated Groundwater
Contour Line
Estimated Groundwater
Divide
  •
j
                                               n
       Approximate Scale (Feet)

-------
                                                            -61-
                                                        FIGURE  15
                                                IW BASINS  (UNIT  T-l)
LEGEND
O
CD
         USAF Property Line
         Phase II Site
         Groundwatar Monitoring Well. Nov. 1984
         Groundwatar Monitoring Well. Aug. 1982
         Surface Water Monitoring Site
         Sediment Monitoring Site
         DNREC Monitoring Well
         Off -Bate Contaminated Well
                                                                            Approximate Scale (Feet)

-------
                                                            -62-
                                                      FIGURE  16
                                                UNIT D-10
— -•— USAF Property Line
        Drainage Channel
        phase II Site
        Groundwater Monitoring Well
        Surface Water Monitoring Site
  O    Off Base Contaminated Well
                                                                       Green House
                                                                          Well
Approximate Scale (Feet)
          iP
          400

-------
            -63-

       FIGURE 17

UNITS D-4 AND D-5
                    	    Horeeppnd Jtoa
                    •"—
                                                           Approximate Scale (Feet)

                                                                    400
LEGEND
	USAF Property Line
——...—/- Drainage Channel
~ — —~ Unimproved Road
   Wg| Phase II Site
   •   Groundwatar Monitoring Well
   A   Surface Water Monitoring Site
   •   Soil/Sediment Monitoring Site

-------
                                      -64-






Site D-10




     Ground-Water flow across the site is in a south-westerly direction towards




the Saint Jones River.  This agrees with similar maps developed by the IRP con-




tractors.  The hydraulic gradient is .18% indicative of an essentially flat




water table.  Ground-Water flow beneach this site is estimated to be on the




order of 1.0 feet/day.  (SAIC 1986)






Sites D-4 and D-5




     Ground-Water flow underneath the sites is in a west-northwesterly di-




rection towards a wetlands area along Pipe Elm Branch.  This is in general




agreement with the configuration projected by the IRP contractors.  The




hydraulic gradient is approximately .32% with a calculated ground-water flow




rate of approximately 1.4 feet/day.  (SAIC 1986)

-------
                                      -65-
                 GROUND-WATER MONITORING DURING INTERIM STATUS






     Ground-Water monitoring at the DAFB facility has been conducted entirely




under State regulations.  The State of Delaware was authorized by the U.S. EPA




to carry out a hazardous waste program equivalent to the RCRA Federal program




of regulation codified in 40 C.F.R. 124, Part 260-270.  Delaware obtained




Final Authorization on June 22, 1984.  RCRA treatment, storage, and disposal




(TSD) facilities in Delaware are thus subject to the Delaware Regulations




Governing Hazardous Waste (Del. Regs.) in lieu of the Federal regulations,




excepting statutory authorities of the RCRA amendments.






     In February 1984, the State made the determination that the IW basins




were RCRA regulated units.  In November 1984, three ground-water monitoring




wells (Olj ,02j,04j) were installed.  These three wells, together with the




wells installed near the IW Basins in 1982 (101,102,103) were used to study the




ground-water in the vicinity of the IW Basins.






     Records submitted by DAFB indicate that, whereas DAFB conducts a ground-




-water sampling and analysis program for the IW Basins, this program does not




comply with the requirements of RCRA.  For example, available sampling records




indicate that initial background concentrations for the parameters specified




in Del. Regs. 265.92(b) were never established as required by Del. Regs.




265.92(c)( 1).  DAFB has not monitored for all parameters specified in Del.




Regs. 265.92(b).  For example, analyses were not available for Barium, Fluoride,




Nitrate, Lindane, Methoxychlor, Toxaphene, 2,4-D, 2,4,5,-TP Silvex, Radium,




Gross alpha, Gross beta. Selenium, Endrin, Turbidity, Fecal coliform, Chloride,




Manganese, Sodium, Sulfate, Specific conductance, TOG and TOH.  Replicate

-------
                                      -66-
measurements were not obtained for the indicator parameters during the  first




year of sampling.  An initial background  arithmetic mean was never calculated,




and no statistical comparison has been made to determine whether a statistically




significant increase over initial background has occurred.






     The upgradient, background well also appears to have  been impacted by the




unit.  Analytical results from the Task Force show levels  of VOC's in the up-




gradient well higher than those found in several of the downgradient wells.




Ground-water flow patterns (Figure 10) also indicated that  mounding from the  unit




is occurring near the upgradient well.  Because of this, no actual background




well for the unit exists.  Therefore the present ground-water monitoring system




is incapable of determining the impact on the quality of the ground-water in  the




uppermost aquifer underlying the facility as required under Del. Regs.  265.90.






     The following is an evaluation of the monitoring program between February




1984 and December 1986, when the Task Force investigation  was conducted. This




section addresses:




        o  Regulatory requirements




        o  Ground-water sampling and analysis plan




        o  Monitoring wells




        o  Sample collection and handling procedures




        o  Ground-Water Quality Assessment Program Outline and Plan







REGULATORY REQUIREMENTS




     The Delaware requirements for ground-water monitoring during interim




status are contained in Section  265 of Delaware Regulations Governing Hazardous




Waste  (Del. Regs).  Table 6 shows the Del. Regs, and the corresponding Federal




regulations for ground-water monitoring under interim status.

-------
                                      -67-


                                    TABLE 6

            STATE AND FEDERAL COUNTERPART INTERIM STATUS REGULATIONS

                        Delaware Regulations               RCRA Regulation
                             Section                        40 C.F.R Part
Subpart Title	

Applicability                  265.90                         265.90

Ground-water Monitoring        265.91                         265.91
  System

Sampling and Analysis          265.92                         265.92

Preparation, Evaluation        265.93                         265.93
   and Response

Reporting and Recordkeeping    265.94                         265.94


GROUND-WATER SAMPLING AND ANALYSIS PLAN

     The regulations require an owner/operator to develop and follow a sampling

analysis plan which includes procedures and techniques for:  (1) sample collec-

tion, (2) sample preservation and shipment, (3) analytical procedures and (4)

chain-of-custody control.  The Task Force evaluated the ground-water sampling

and analysis plan developed by DAFB in October 1986 and found it to be inadequate,

(DAFB had developed a sampling and analysis plan in April  1985, however the

October  1986 superceded this plan).


     In general, the plan discusses basic equipment and procedures that should

be used during sampling and analysis, however more detailed information is

needed.  The plan does not indicate whether the sampling equipment is dedicated

to individual wells.  Although the plan addresses making field measurements for

temperature, specific conductivity and pH, procedures for making these field

measurements or for calibrating instruments are not are not included.  The plan

also does not address a method for verifying that samples have been preserved

to the appropriate pH.

-------
                                       -68-
     The  plan does not address the locations (units,wells) to be sampled, the




 frequency of sampling, the order of sampling (most volatile to least volatile)




 or  the analyses  to be performed.  Most importantly, the plan fails to include




 the collection of quality assurance and quality control samples (trip and




 equipment blanks), nor does the plan discuss such QA/QC procedures to be followed




 by the lab  (matrix spikes, duplicates).  These types of samples must be taken




 to be able  to determine whether (1) samples are being cross contaminated in the




 field through improper sampling techniques, (2) samples are being cross contami-




 nated by  the lab, (3) the laboratory analysis is accurate and precise and (4)




 the results are  representative of existing conditions onsite.







     In summary, the plan needs to be revised to address the deficiencies cited




 above.  Revisions are needed to ensure consistent sampling methods and collection




 of representiye  samples.






 MONITORING WELLS




     It is unclear, from the information available to the Task Force, whether




 DAFB ever initiated a RCRA ground-water monitoring program in accordance with




 Del. Regs. 265.  A monitoring network consisting of three wells (101,102,103)




was constructed  around the IW basins in March 1982.  At that time, the IW basins




were not considered by the State to be RCRA regulated units.  Monitoring con-




 ducted as part of the study showed elevated levels of several volatile organic




 compounds in the ground-water.  Prior to construction and sampling, Well 101




was considered the hydraulically upgradient, background well, but the 1982




 sampling results showed elevated levels of organic compounds in the ground-water




 at this location.

-------
                                      -69-


     In November 1984, three additional wells (Olj ,02j ,04j), were installed near

the IW basins.

          Upgradient                        Olj
          Downgradient                      02j
                                            04 j
                                            101 (Original upgradient)
                                            102
                                            103

     Ground-water monitoring was conducted in 1984,   1985, and  1986.  Results

continued to show elevated levels of several volatile organic  compounds.  In

addition, studies conducted by SAIC Consultants for  DAFB in June 1986 indicated

that ground-water from well Olj contained elevated levels of VOC's.  SAIC con-

cluded that the well was being impacted by either the IW basins or a possible

nearby SWMU.


Well construction

     Wells  101,  102 and 103 were constructed on March 9,1982 with a mud rotary

rig.  Records of well installation were maintained by Delmarva Drilling; copies

of these records are in Appendix A.  Well Olj was constructed  on October 31,  1984

using a water rotary rig;  well 02j was constructed on November 14, 1984 using a

a hollow stem auger and well 04j was constructed on  November 9, 1984 using a

water rotary rig.  Records of well installation were maintained by JRB Associates

(now SAIC) and are also included in Appendix A.


         Well borings for well 101, 102 and 103 were drilled through a clay  to

fine sandy clay to the top of a fine to coarse brown sand.  Complete well con-

struction details were not available for wells 101,  102 and 103.  Borings for wells

Olj, 02j and 04j were drilled to the top of a dark clay zone,  directly beneath

the brown, medium to fine sands.  These borings were advanced  one to four feet

into the clay and stopped.

-------
                                      -70-







     Wells 101, 102, and 103 were completed using a 2 inch diameter PVC casing




and PVC well screens approximately 6 feet in length.  All wells were gravel




packed from 10 to 18 feet and grouted using bentonite clay from 2 to 10 feet.




Additional construction details for these wells were not available to the Task.




Force.






     Wells 01j, 02j, and 04j were completed using a 2 inch diameter PVC casing




and PVC screens ranging in length from 15 1/2 feet to 34 feet.  The annular




space around the screened interval was filled using 4Q sand as a filter material




for wells Olj and 04j,  but for well 02j  the formation was allowed to cave in




around the well casing.  The regulations (40 CFR Part 265.91(c), Del. Regs. Part




265.91(c)) require that the annular space be sealed with a suitable material




(e.g., cement grout  or bentonite slurry) to prevent contamination of samples and




the ground-water.  Additionally, no filter material was used.  Bentonite was




used as a sealing material for all three wells and a mixture of #1 Portland ce-




ment and bentonite was used for grouting.  A protective steel casing with a




locking cap was cemented to the surface for the three wells.  Following construc-




tion, these wells were developed using compressed air.  A summary of well con-




struction details are contained in Figure 7.






     Complete construction details were not available for wells 101, 102, and




103.  State regulation (Del. Regs. 265.91(c)) requires all monitoring wells to




be cased in a manner that maintains the integrity of the monitoring well bore-




hole.  The PVC casing at several monitoring wells was very loose.  Concrete




aprons around the base of the wells, which are supposed to drain surface water




away, were not in place at the wells surrounding the IW Basins.  Erosion of




surface soils was observed around several of the steel well casings.  Screen




lengths for wells Olj, 02j, and 04j were excessively long and do not allow for




sampling of discrete parts of the aquifer.

-------
                                                         -71-
                                                       Table 7
 Well
 Number

 01J
 02J
 04J
 05J
 06 J
 07J
 08J
 09J
  10
  11
  12
  13
  21
  22
  23
  101
  102
  103
 Estimated
 Location
200
500
400
800
20
20
40
20
20
30
40
30
20
20
20
ft
ft
ft
ft
ft
ft
ft
ft
ft
ft
ft
ft
ft
ft
ft
NE
W
S
NE
SE
SW
SW
NW
WSW
N
NE
E
N
NE
SE
T-l
T-l
D-10
D-10
D-10
D-10
D-10
D-10
D-4
D-4
D-4
D-4
D-5
D-5
D-5
10 ft NE  T-l
10 ft SE  T-l
10 ft SW  T-l

Date (1984)
Constructed
10/31
11/14
11/9
11/13
11/2
11/1
11/7
11/2
10/25
10/26
10/29
10/26
10/29
10/30
10/30
(1982)
3/9
3/9
3/9
MONITORING
Drilling
Method 1,2
Rotary
Auger
Rotary
Auger
Rotary
Auger
Rotary
Auger
Auger
Rotary
Auger
Auger
Rotary
Rotary
Auger

Rotary
Rotary
Rotary
WELL CONSTRUCTION SUMMAR'
Depth of
Well Casing
38.0
33.5
44.8
58.5
53.0
52.0
51.0
52.0
56.0
55.0
55.0
61.5
60.0
60.0
57.0

17.0
17.0
17.0
Screened
Interval
9-38
18-33.5
10.8-44.8
13-58.5
8-53
8-52
10-51
10-52
10-56
11-55
11-55
11.5-61.
10-60
10-60
10-57

11-17
11-17
11-17
Casing    Lithology Screened
Diameter   	Interval	

  2       brown fine-medium sand
  2       brown medium-course sand
  2       brown fine-medium sand
  2       grey/brown fine-coarse sand
  2       grey/brown fine-coarse sand
  2       brown/yellow fine-coarse sand
  2       brown/yellow fine-coarse sand
  2       brown/yellow fine-coarse sand
  2       grey/brown sand gravel  sand
  2       brown/yellow fine-coarse sand
  2       brown/yellow fine-coarse sand
  2       brown/grey sand
  2       grey medium-coarse sand
  2       grey fine-coarse sand
  2       brown fine-medium sand
  2       brown fine coarse sand
  2       fine-coarse sand
  2       fine-coarse sand
1.   Wells were constructed in 1984  using  either  hollow  stem  auger  or  rotary  (water) methods,

2.   Wells were constructed in 1982  using  mud  rotary methods.

-------
                                     - -72-







     The PVC casing meterial  was not tested for inertness to the  constituents




found in the ground-water.   PVC degrades and may adsorb or leach  materials




into the ground-water in the  presence of ketones, esters and aromatic hydrocar-




bons.  Ground-water samples may not be representative of the true conditions




in the aquifer if the well  casing degrades.







Well locations
     Information available to the Task Force indicates that all  hydraulically




downgradient wells appear to be adequately areal]y distributed to detect a




release in the horizontal direction.  Releases have been detected in wells




Olj, 02j,  and 04j; however, the excessive screen lengths of these wells causes




dilution of samples so that an accurate measure of the concentration and direc-




tion of contaminants in the ground-water is not possible.






     Well  101 had originally been designated as the upgradient well; however,




it was located to close to the waste management boundary and appears to have




been impacted by the unit.  Well Olj was designed to be the new upgradient




well; however, this too has been impacted and cannot provide samples representa-




tive of background ground-water quality.






DAFB SAMPLING PROCEDURES




     Personnel from DAFB collect samples for periodic ground^water monitoring.




DAFB demonstrated their sampling procedures on December 8,  1986, at well Olj.







Water Level Measurements
     To determine the volume of water in the well casing for calculating purge




volumes, water level measurements are taken at each well. A weighted measuring




tape, that sounds the water surface, is used to make water level measurements




and  to measure total depth of the well.  The tape is lowered into the well and




creates a sound when the weight hits the water surface.

-------
                                      -73-






At this point, the measurement on the tape at the top of the inner PVC casing




is recorded.  The tape is marked in foot increments.  The total depth of the




well is then measured by allowing the weighted end of the tape to rest on the




bottom of the well.  The depth to water is subtracted from the total depth of




the well to determine the length of the water column and volume of water in the




well.  As the tape is retrieved from the well, it is decontaminated with a




phosphate-free lab soap/tap water mixture and rinsed with distilled water.  The




tape is then dried using paper towels.






     Using this method for water level measurement is not acceptable as the use




of a sound measuring tape requires some interpretation of where the water level




is located.  The tape must be lowered in a manner that causes an impact on the




water surface sufficient enough to make a sound.  This can be influenced by the




ability of the sampling personnel to stop lowering the tape at this moment.  The




precision and accuracy of the water level measurements is questionable.






Purging




     The sampling and analysis plan requires that the wells are purged of three




water column volumes prior to sampling.   The water column height in the casing




is determined by first calculating the height of the standing water in the




casing by subtracting the depth-to-water measurement from the total well depth.




The volume of water in the casing is then calculated by multliplying the water




column height by a gallon-per-foot-of-casing conversion factor.  This volume is




then multiplied by 3 (for 3 water column volumes) to give the total purge




volume required.






     A bottom-loading, teflon bailer with a capacity of approximately 1 liter




is used to purge each well.  This bailer is decontaminated prior to purging

-------
                                      -74-







using a phospate-free detergent,  diluted to 10% concentration with tap water,




and then is rinsed using distilled water.  All rinse water is collected in 5




gallon buckets and hand carried to the industrial sewer or oil/water separator




where it is discharged.  The bailer is lowered into the well using a cotton




rope.  This cotton rope is discarded after purging is completed.






     DAFB personnel wait approximately 15 minutes, as required by the sampling




and analysis plan, after purging before sampling occurred.  This  15 minute time




period allows the wells to fully recovery.  During the demonstration, none of




the wells could be purged to dryness and all wells completely recovered




instantaneously.






Sample Collection




     After well recovery, each well is sampled using a  1 liter bailer.  For the




demonstration, separate bailers were used to purge and sample; however, normal




procedure is to sample with the same bailer that was used to purge the wells.




The bailer is lowered into the well using a cotton rope.  This rope is discarded




after sampling for the well was completed.






     DAFB sample wells  in order of the least contaminated well to the  most con-




taminated well.   Samples are collected in order of most volatile to least vola-




tile.  For example,  the order of sampling was observed  to be volatile  organics,




phenols, and metals.






     All samples  are taken  to the  onsite  laboratory where dissolved oxygen, pH,




and specific conductance analyses  are  performed.   All  instruments are  calibrated




prior  to use.   Samples  to be analyzed  for metals  are preserved using  HN03 an(*




then are placed  in a refrigerator  to  cool.  Samples  to  be analyzed  for phenols

-------
                                      -75-
were preserved by adding 2 ml of I^SO^.  The pH of the sample is then tested to

determine whether the pH is less than 2.0.  If not, more i^SO^ is added and the

sample is cooled in a refrigerator.


     Upon completion of sampling of a well, the bailer was cleaned with the

detergent mixture and rinsed twice with distilled water.


     The Environmental Sampling Data sheet (Appendix B) was filled out by DAFB

personnel.  All samples are shipped to Brooks AFB for analysis.


     The sample collection methods appear to be adequate, however no quality

assurance/quality control samples were taken.  These include duplicate well

samples, trip blanks and field equipment blanks.  These types of samples must

be taken to ensure that samples are not cross contaminated in the field and

that laboratory analyses are accurate and precise.


     Some recommendations to improve sampling methods include:

1)  Using dedicated bailers for each well.
2)  Using teflon located steel wire rather than cotton rope to lower bailers.
3)  Ensuring that bailers are lowered into the well columns in a manner that
    doesn't cause agitation.
4)  Using on Interface probe to detect water levels elevations.


Shipping and Chain of Custody

     Chain-of-custody forms are filled out prior to submission of samples to

the offsite laboratory.  Samples are packed in coolers with frozen gel blocks

and shipped within 48 hours to Brooks AFB, San Antonio, Texas.  Samples are

logged in at the OEHL at Brooks AFB and custody forms are signed over at that

ti me.

-------
                                      -76-
GROUND-WATER QUALITY ASSESSMENT PROGRAM OUTLINE AND PLAN


Ground-water Quality Assessment Program Outline

     State regulations (Del. Regs.  265.93)  require  a facility to prepare  an out-

line of a ground-water quality assessment  program effective  November  18,  1981.

Since the IW Basins became RCRA regulated  units in  February  1984,  this  section

of the regulations became effective at that time.  The outline must describe a

more comprehensive ground-water program than the one for detection monitoring

under interim status and be capable of determining:

     1.  Whether hazardous waste or hazardous waste constituents have entered
         the ground-water.

    2.   The rate and extent of migration  of hazardous waste or hazardous
         waste constituents in the ground-water.

    3.   The concentrations of hazardous waste or hazardous  waste constituents
         in the ground-water.


     During the Task Force investigation,  no record of the assessment outline

was found .


Ground-Water Quality Assessment Program Plan

     State regulations (Del. Regs. 265.93(d)) require an assessment plan to be

submitted, based on the assessment outline, which specifies:  (1) the number,

location, size, and depth of wells; (2) sampling and analytical methods for those

hazardous wastes or hazardous waste constituents in the facility; (3) evaluation

procedures, including any use of previously gathered ground-water quality infor-

mation; and (4) a schedule of implementation.


     During the Task Force investigation,  no records of an assessment program

plan were found.

-------
                                      -77-
         EVALUATION OF MONITORING DATA FOR INDICATIONS OF WASTE RELEASE






     This section presents an analysis of the Task Force monitoring data regard-




ing indications of apparent leakage from waste management units.  Analytical




results from and methods used on samples collected by Task Force personnel are




presented in Appendix C.






     Analytical data evaluated in the usability and evaluation reports were




evaluated as being quantitative, semi-quantitative. qualitative, suspect, or




unusable.  Only quantitative and semi-quantitative data were used to determine




releases.  Volatile organic analysis (VOA) data are quantitative; all other




organic data, except phenol, naphthalene, and BHC are deficient to some degree.




Quantitative inorganic data include Chloride, Aluminum, Arsenic, Barium, Beryl-




lium, Cadmium, Chromium, Copper, Iron, Lead,  Magnesium, Manganese, Mercury,




Potassium, Sodium, Vanadium, and Zinc.






     Task Force data indicate the presence of volatile organic compounds at




high concentrations (greater than 1000 ug/1)  in two of the eighteen wells




sampled (Olj and 103).  Nine other wells (06,07,09,101,102,10,11,13,21) also




detected various organic compounds, but at lower concentrations.  Well 103




had the highest concentrations of organic compounds followed by wells Olj,




11, 13, 7, and 101.  Table 8 shows all wells  sampled by the Task Force and the




levels of organic compounds found.






Unit T-l




     Monitoring well Olj is the upgradient,  background well for the closed IW




basins.  Concentrations of perchloroethylene  and trichloroethylene were detected




in well Olj  at higher levels than any other well for unit T-l, with the exception

-------
                                      -78-






of well 103.  This suggests that well  Olj  is being impacted by the unit and is




not capable of yielding sample representative of  background conditions.  The




inorganic data from the Task Force samples indicates a release from the closed




IW basins.  This release appears to be directed toward the southwest from unit




T-l; however, it does not appear to have migrated as far as wells 02j and OAj .






Unit D-A




     The results of chemical analyses  indicate that a release from unit D-4




has occurred.  Monitoring well 11, located at the west corner of the unit,




contained elevated levels of perchloroethylene, trichloroethylene, and




trans-1,2-dichloroethylene.  The release appears to be directed toward the




southwest (from unit D-4).






Unit D-5




     Sample results from the wells in the vicinity of unit D-5 did not




detect the  presence of volatile organics in the ground-water.  Inorganic data




was inconclusive.






Unit D-10




     Wells  in the vicinity of unit D-10 showed elevated levels of VOAs in




the ground-water.  The highest concentrations were found in well 7.  The




pattern of  contaminants indicates  that waste migration is primarily  to the




southwest,  towards the St. Jones River.







Oil/Water Separator




     Although requested by the Task Force, organic constituents  (volatile




organics, base/neutral acid extractable organics,  pesticides, and herbicides)




were not  analyzed by the laboratory, so conclusions regarding the concentrations

-------
                                      -79-


of these types of constituents in the liquid in the oil/water separator cannot

be made.


     Inorganic analyses showed that the liquids in the oil/water separator

were not EP Toxic.  These results are summarized below:


                         Oil/Water Separator
                         Sampling Results            EP Toxicity Level
                         (Concentration in           (Concentration in
Constituent              mi Hi grams/liter)           milligrams/liter)

Arsenic (Ar)              Not detected                      5.0

Barium (Ba)                 0.031                         100.0

Cadmium (Cd)                0.066                           1.0

Chromium (Cr)               0.072                           5.0

Lead (Pb)                   0. 167                           5.0

Mercury (Hg)                0.115                           0.2



     Dioxins and dibenzofurans were not detected in the liquids in the

oil/water separator.

-------
                  D) ASSOCIATES
        A Company at Sci*nc» Appticitioris. /ne.
        3400 WestparK Drive. McLean. Virginia 22102
                                                               WELL CONSTRUCTION  SUMMARY
           Project:     Dover AFB
Owner:   U.S.  Air Force
                                 Well
J '
-1
j
 J




0 ""
f

_, /
-
-!•!•.
10 "



?n -





30 '

40 -



50 -








.••."T '••
$. '-''
V.'.V.
,v.*.v.
• * • • •
<%2
V/WI
• I •• I
^v^
•„:•;.•
•* • •
••• ••
• • •• •
• •• ••
•• • •
••• ••
• • •• «
• •• ••
•• ! •
••• ••
• • •• '
• •«•
• • j .
':••••:
•••.••
.. ; .,
•':•••*:
>•».••
.. ; .,
••• ••
• I •• I
• • • *
.. j .,
••• ••
• I •• 5
• • * «4
••" ••
• ** I
• • J >l
*•• *«
I •• I
.*. .«
• • * • •
••*..••
•:.•:•:,
*:••••;
• •« ••
• • T • «
&:>
•• ™ • •
:•*..*•
.*.".•.
• • * ••
*•*.„••
•
•
••1














^•^""^^











•
•
•••









•
$%
• • • • •
•.v.v.
V.V.*.
•.v.v.
^
;.•;..'
•V;.:.
•• i ••
tt.*:
«• • •»
«• •.»
'••:•••
•• • ••
•..*.•.
*• * ••
:/;.:.
• • T • •
* • •
:*.. ••.
•«-•"«
•*.J.4*.
:••:•
••• •
•• * ••
:>;:••:
>• ; ..
:*••*:'•
••• •
»• ; ..
s>:s:-
••*•••
I •• J •
••• •
sy*
.•*•.•
J, •• I •
• « • • ,
• ; ••
•• •••
j •• j •
••• •
:•••:•'
••':•••'
m
•
••i






Drilling Sunmary:
local Depch: 38' Drillers: Calvin Wallace
Borehole Diamecer(s): 6" Delmarva Drilling
Failing 1250
RiB Type: Hydraulic Rotarv
Elevacion: Land Surface: 19.44' Bic(s): Drag
Top of Casing: 21.39' Drilling Fluid Type: Water
Supervisory Geologist: Richard Eades Amount Use:
Log Book No. 4 pp. 93-105 Water Level: 10.9' 11/14/84

Well Design:
Casing: Material: pvc Screen: Material: PVC
Diameter: 2" ID 2 3/8"OD Diameter: 2"
Length: 11' ~"~ Slot: 0.010; S/i.nch
Filter: Material: 4Q Sand Setting: 9'-38'
Setting: 7'-38' Seals: Type: Bentonite
Grouc: Type:yH Portland Cement /BenSett ing: 5'-7'
Setting: LS-5.0' Surface Casing: steel/PVC
Other: Protective steel casing cemented in to land surface



Tiae Log: Started Completed
Drilling: 10/31/84 1020 hrs 10/31/84 1200 hrs
Installation: 10/31/84 1300 hrs 10/31/84 1500 hrs
Water Level Reading: 11/14/84 1510 hrs
Development •'

Well Development:
Method/Equipment: Air Blown Minimum 4 hours, pumped at
10 gpm minimum 4 hours and until clear.


1

-------
             ASSOCIATES
A Company of Scifnct Applications. Ine
8400 Westoark Drive. McLean. Virginia 22102
   Project:    Dover AFB
   DRILLING LOG
Owner:  U.S.  Air Force    Well No.
 MW-01i
                                     Location:   Industrial
                                        Waste Basins
                                     Reference
                                     Poinc:  Land Surface
                                     Reference
                                     Poinc
                                     Elevacion:  19.44
                          Field Book No. :

                              By:    Rick Eades
                                                               Driller:    Calvin Wallace
                          Rig Type:_

                          local
                          Depch:	
                                                                           Failing 1205
                                                                           Hydraulic Rnf-arv
38'
             Sice Sketch
                                             Dace   Tine
                          Drilling Scarced;10/31/84  1020hr
                          Drilling Compleced:10/31/84 1200
                          Wacer Level: 10-9' 11/14/84 1510

0




*l




5 -









10

***.
1
NM»
1
•









-

-








S
u
!











.*.?••?.••'.'•
:•'••.••>'.'*;.•.








*J
30%




Gray 3ilt, very dense, well compacted.

Light brown fine sand, trace clav


SI: 5-7' BLS RE. i 2'
1.2' - Light gray (SYR 7/1) fine to medium sand
some silt, some clay, trace pebbles, thin
orange laminations near bottom of sample.
•






                                                                                Page 1 of  4

-------
             ASSOCIATES
A Company of Scitnct Applications. Inc.
3400 Wastpark Onv«. McLean. Virginia 22102
                                           DRILLING LOG
                                                                          MU-01i
                                                                                J
i n










15 -









-U








?s
I










•
'

-






.
.
.
,
.


,


a

fvffi?
•fcVS*/:







&££
SfcV*
*••••*•







c.-.v.'/vy;."
i&'&T








91
.2 I
I?
SS#2



C




SS*3









SS#4




C





8
7
8
10
13






8
15
16
20






11
14
10
15






DESCRIPTION
SI: 10-12' BLS RE: 1.3'
1.3" - Light gray (SYR 7/1) coarse to medium sand.
some fine sand, trace silt, trace clav, trace
pebbles.
Brown, coarse sand and pebbles, some medium sand, trace silt.




SI: 15-17' BLS RE: 1.1'
1.1' - Dark orange brown (10YR 5/6) fine to medium
sand, some silt, trace clay, trace pebbles.







SI: 20-22' BLS RE: 1.1'
1.1* - Dark orange brown (10YR 5/6) medium sand,
some fine sand, trace clay, trace pebbles.



sand, some pebbles.




                                                                                    Page 2 of 4

-------
              ASSOCIATES
A Company of Sciunct Applications. Inc.
3400 Westoark Drive. McLean. Virginia 22102
DRILLING LOG
                                                                           MW-Olj
25









30 -












35









40 .
9
.C
*
£
•
•















»















1
'.. *_J *,*
.•:••;•• .•;..-.


—







:'. :••':.'.•:•.'
-•S-.'-Vf-'rf1
*-.— 1VY7
•°i'°/-''x«.'







•*£•»£•'
*•*;»*:*
J!UK="-4;-








- 5
u J
u 3
1?
SS#5



—

c


SS#6







C




SS#7




C

c



^^,
^^
j
2
13
14
8
13






11

17

91

26






28
24
23
24






DESCRIPTION
SI: 25-27' BLS RE: 1.1'
1.1' - Medium orange brown (10YR 6/8) fine to medium
sand, some silt, trace clay, thin black laminations
in interval.

*
Brown, coarse to medium sand, trace silt.


SI: 30-32' BLS RE: 1.7'


,.,...


trace silt, trace clay.

Light brown medium to fine sand, some silt, trace clay.




SI: 35-37' BLS RE: 1.3'
1.3' - Medium to dark reddish brown (10YR 5/6) coarse to
medium sand, some fine sand, some pebbles, trace
silt.

Reddish brown, coarse to medium sand.
•
Reddish brown sand with some dark gray clay.
Driller indicated that top of the clay layer was contacted at
approximately 38' BLS.

                                                                                    Page  3  of  4

-------
           ^ASSOCIATES
  A Company at Seimnct Application*. Inc.
  3400 Wttstoark Drtve, McLean. Virginia 22102
                                            DRILLING LOG
                                            DRILLING LOG
                                                                            1 LlfV ™" \J L J
 40
45 --

                                                     DESCRIPTION
                             SI: 40-42'  BLS
BF .  7 n '
                               2.0'  -  Dark gray (5Y 4/1)  CJAV,  allty,
                                              fin«»lv
                                                                                    Page  4 of  4

-------
              A S S 0 CI ATE S
A Company of Sc:»nc» Applications. Inc.
3400 WestoarK Drive, McLean, Virginia 22102
                                                           WELL CONSTRUCTION  SUMMARY
   Project:     Dover AF3
Owner:   U.S.  Air Force
                                                                                    Well



o1-





10'-




20' -






30' -



An' '



-







i « i ^~
:W«
•»- x V.
•:•:•:•:•:
• • • • •
• • • • •
• • • • •
• * • » i
• • • • •
.v.*.v
.V.'.V
• • • • «
• * • • 1
• • • • •
^

••:':.'•;':'
•'.'•'.'• i'.'1'
•'•.'•'Z'"**'
•.:.•:•••••:•

•: •!.••.'• \

•'.vX*\v!
.••••'••.'•

•.•.;•>:•.
•••.•.-.•?••


11
ipl

































•













>' -r.
l-,^>
• • • • •
*•*•*•*•%'
'.V.'.V
• * • • •
• • • • • i
• • • • • i
.V.V.',
.V.'.V.
• * * • • 1
• • • • •
m

i^i^
8P
"" * !^V.«".
••":::».*{:>•
.•;• v .•:•-
•V '•",*«**•*"•*
.*•*.".*••• ••
'.•"*. •.*«;-*•"
"• ^"*- *'i '••



•'.''.'. - •' '••'
'•'''*•'.<' \'S.
:'iv:*>>%B':
•









Drilling Sunrnary:
local Depch: 33.5' Drillers: Gary Truver
Borehole Diamecer(s): 6" Walton Corporation
RiR Type: CME Auger
Elevation: Land Surface: 25.56' Bit(s): Hollow Stem auger
Top of Casing: 27.56' Drilling Fluid Tvpe : None
Supervisory Geologise: Richard Eades Amount Use:
Log Book No. 5 pp. 61-67 Water Level: 18' 11/14/84


Well Design:
Casing: Material: Schedule 40 PVC Screen: Material: Schedule 40 PVC
Diameter: 2" JD 2 3/8"OD Diameter: 2"
Length: 10' Slot: 0.010; 5 slots/inch
Filter: Material: None Setting: 18-33.5'
]
Setting: Seals: Type: Rentoiice

Grout: Type:^l Portland Cement /BenSett ing: 9.5'-11.5'
Setting: LS-9.5' Surface Casing: Steel/PVC
Other: Formation cavprf info 11 S,1 providing natural sand oack from
11-5 - 3J.5 Protective steel casino rpmpnfpH inrn

1 an<4 Qtirfacc


Time Log: Started Completed
Drilling: 11/14/84 0900 hrs 11/14/84 1030 hrs
Installation: 11/14/84 1030 hrs 11/14/84 1139 hrs
Water Level Reading: 11/14/84 1030 hrs
Development •' '

Well Development:
Method/Equipment: Air Blown for 8 hours, bailed
because of slow recovery.




-------
         	8) ASSOCIATES
         A Company of Scwtc* Applications. Inc.
         8400 Westpark Drive, McLean, Virginia 22102
            Project:    Dover AFB
              DRILLING LOG
          Owner:  U.S.  Air  Force     Well No.;
                 MW-02j
J
                      Sice Sketch
                                             Locacion:  Industrial
                                                Waste Basins
                                                Site  T-l
          Reference
          Point;  Land  Surface
          Reference
          Point
          Elevation:
                                    Field Book No.:  5   pp 61-67

                                    Log  By:     R-irU  Farfoc	

                                    Driller:    Gary  Truver	
Rig Type:_
Total
Depth:	
                                                                                  CME Aueer
33.5'
                   Date   Tine

Drilling Started:11/14/84 Q900hi
Drilling Completed:ll/14/84 103(
Water Level:  18'  11/14/84 103(
                                 Legend
                                 SI:  Sampling Interval
                                 RE:  Recovery
                                 SS:  Solit Spoon
                                 C:   Cuttings
                          DESCRIPTION
          Gradat ion
          Trace 1-127.
          Little  12-207.
          Some  20-307.
          Add "Y" >307.
                     SS#1
       5  --
                     SS#2
       10
                            10
                                   Medium to light brovm, silt, some clay, trace  sand,  trace
                                   pebbles.
                                   SI:  4-6'  BLS
                                          RE:  1.5'
                                     0.7'  - Brown (10YR 5/6) clay, some silt.
                                     0.4'  - Yellowish brown (10YR 6/6) sand, some  silt,  trace  clay.
                                     0.4'  - Yellowish brovm (10YR 6/8) clay, trace  silt.
                                   Silt,  some clay, some sand.
SI: 9-11' BLS
      RE:  2.0'
                                     0.6'  - Yellowish brown (10YR 6/8) clay, some silt.
  1.4' - Clay, trace silt grading downward  in  color  from
                                                                                        Page  1  of  3

-------
                ASSOCIATES
  A Company of 5ci»nc» Applications. Inc.
  8400 Westoark Drive. McLean, Virginia 22102
DRILLING LOG
                                                                               MW-02j cont.
^
I
1
•






'
:
.




»

-



•


•
•
•
.
•
•
•
•

3

jfi£19






HUffil
m^i
IHHDH








.•.*,••'• •.'•"•
&£&
iiiiijiiil
::;'•• :'.•'>•':
u^-iW
*%%#£






«^
#$#
1 |
— j
V J
ll
|SS#2


C



SS#3





C

C

SS#4







C


C
SS#5


"^
j
2
12
15






3
6
9
11







1
1


3






5
6
DESCRIPTION
light gray (SYR 7/1) to brown (10YR 5/6).


Clay, trace silt, brown to grayish brown.



SI: 14-16' BLS RE: 2.0'
0.2' - Brown (10YR 5/6) sand, some clay.
1.8' - Clay, color variable from gray (SYR 7/1) to
yellowish brown ( 10YR 6/8) with black streaks.


Hit gravel layer, approximately 0.5' thick.

Sand, some clay, wet.

SI: 19-21' BLS RE: 2.0'

2.0' - Light yellowish brown ( 10YR 7/8) fine sand,
some silt, trace clay, wet.




Gravel, approximately 0.5' thick.


Gravel, approximately 0.5' thick.
SI: 24-26' BLS RE : 1 . 5 '
1.5' - Medium to dark yellowish brown (10YR 5/8)
coarse to medium sand, some pebbles, trace
 10
15
20  --
25
                                                                                       Page  2 of 3

-------
              ASSOCIATES
A Company of Scitftc* Applications. Inc.
3400 Wastpark Drive. McLean, Virginia 22102
                                              DRILLING  LOG
                                                                               MW-02-J  cont,
4^
1
•»*
•
•














-
•

'
.
'

• j
•
•





3
»%?«



"^



<>»#::$
£&!£?
£•*?&•
•*







m
•
•
•








is
:«i
I*
SS#5






SS*6










SS#7






SS#8





1
j
5
5
7






6
6
7

11






3
3
4
4



2
3



DESCRIPTION
fine sand.






SI: 29-31' BLS RE: 1.3'
1.3' - Dark yellowish brown (7. SYR 5/8) coarse to
medium sand, trace fine sand, trace pebbles.







Driller indicated top of clay layer contacted at 33' BLS.
SI: 34-36' BLS RE: 2.0'
2.0' - Medium to dark gray (5Y 4/1) clay,
silty, dense, finely laminated.




SI: 37.5-38.5' BLS RE: 1.0'
1.0' - Dark gray (5Y 4/1) «H^y rlay.




 25
30  -.
35  --
40
                                                                                      Page  3 of 3  '

-------
              ASSOCIATES
A Company of Scitnca Applications. Inc.

WOO WestparK Drive. McLean. Virginia 22102
                                                        WELL CONSTRUCTION SUMMARY
   Project:
Dover AFB
Owner:   U.S. Air Force
                                                                Well No.:
                                                                                          MV.' -04j




0-






10'-







20






30 -












50'-








I
_L
m
V.'.vl
•.v.v.
.•.v.v
-'•Y-'TL
s x /" >
Y//
/ S S
-•":'•»":
•* '*••*'
•*».•'
•* • •


•* **••*'
• • * •
*.*.*.*«•
• •

* . *• t

• * • • *
• •
*.«.**.•

f*".:/1
.**.•/
. • . . •

..«*..

. ...


.* •*..*•

•* •*..*•
•
1
















^M^BHM^

























H^^HM«M^HI
Ifligi
»^ra
Ig^gPf










i1
^ &
£v$


^
///t
''•'':'••'
••**•• .
'*.•.* *.
•«**.*.
'* *.**.
.*.•••.*.*


**•"•" *•

* • B • * i
• * « * •
.vr-
• • * * •
' * * • *
'. • • ..




*"*•*.*

":"••*:

1 • * * *
• * •• *


m





Drilling Suamary:
Tocal Oepch: 44-8' BLS Drillers: Calvin Wallace
Borehole Diamecer(s) : 6V Delmarva Drilling
Failing 125U Hydraulic
Rig Type: notary
Elevacion: Land Surface: 23-2' Bic(s): Dra8
Top of Casing:. "• 4' Drilling Fluid Type :Water/Bentonite
Supervisory Geologist: A"dris Lapins Amount Use:

Log BOOK riO. J pp. lo ^° water Level: 12.76 BLS l/"/o5


Well Design: ,
Casing: Macerial: PVC Screen: Macerial: PVC

Diameter: 2" ID 2 1/4"OD Diameter: 2"

Length: 13' Slot: 0.010; 5/inch
n i r *f H*r **••* •* \ • 40 sand ?•>• i- v «r, • 10.8 - 44 . 8 ' BLS

Setting: 8.8-44.8' BLS Seals: Type: Bentonite Pellets
Grout: Type:#l Portland Cement/BenSetcing: 5.25-8.8' BLS

,,, *»cy^'^l /ntr^t
Setting: 3-5.25 BLS Surface Casing: Steel/Pvc
Other: Protective steel casing cemented in to land surface.




Tiae Log: Started Completed





Drilling- 11/9/84 0845 hrs. 11/9/84 1250 hrs.
Installation: 11/9/84 1300 hrs. 11/9/84 1442 hrs.
Water Level Reading: 1/9/85 12.76' BLS
i Development •

Well Development:
Method/Equipment: Air blown for 8 hours, pumped at
10 gpm for minimum 2 hours and
until clear.




-------
         _B) ASSOCIATES
A CompfitY of Scwnc* AppHcttJon*. Inc.
8400 Wntpark Drive, McLean, Virginia 22102
   Project:    Dover AFB
   DRILLING  LOG
Ovner:  U.S.  Air  Force    Hell No.
MW -04j
Location:
                                                               Field  Book No.:   3  pp 16-28

                                        IW Basins .  Site  T-l    Log  By;   Andris  Lanins _

                                                               Driller;  Calvin  Wallace
                                     Reference
                                     Point;  Land Surface
                                     Reference
                                     Point
                                     Elevation;    23.2'
              Site Sketch
                                    Failing 1250 Hydraul
                          Rig Type; Rotary	
                          Total
                          Depth:	44.8' BLS	

                                             Date   Time

                          Drilling Started:ll/9/84 0845H

                          Drilling Completed:ll/9/84  125
                          Water Level:  12.76'  BLS   1/9/J





















in

*•»
1
'W
1
•

>-
•
•





-
•
-
-

•
-


•

s
3
I


• •• i •
•••••<
••!••!
••••••



$«&&
&££&



gfe
im
wsS'nri








H
V J
ll


C



C


SS*1










^^
8
•










12
21
22
35






Legend Gradation
SI: Sampling Interval Trace 1-127.
RE: Recovery Little 12-207.
SS: Split Spoon DESCRIPTION Some 20-307.
C, Cuttings Add "Y" >307.


Heavy gravel (crushed stone) from large crushed stone
pile located @ 15' away.


Grayish brown medium sand, some silt and gravel.


SI: 5-7' BLS RE: l.l1
1.1" - Light gray to white (5Y 8/2 - 7/2) clayey very fine
sand, some silt; dense; firm, dry; brown to yellow
mottling at top. ,







                                                                                 Page  1  of *•

-------
         _Q) ASSOCIATES
A CompfflY of Science Application*. Inc.
3400 Wvstparfc Oriv«, McLean, Virgin^ 22102
DRILLING LOG
                           MW- OAj cent.
i n




















20 -











^
i
•^




















*•

.
,
.

,
,
,

:

$
*£?*&
iiwSi;
'r££»&
\£ttf>&.
feW-A:
&S3&

._





•'•' • ''£' ': ':.
£N*








•;&&
''•&Z&.'
• •'.;•.*• ..• '









M
w ^
H
SS#2



—




SS#3









SS#4












>^
i
i
2
14
11
14
20






13
15
40
44






5
7
8
10








DESCRIPTION
SI: 10-12' BLS RE: 1.5'
0.4' - Brownish yellow ( 10YR 6/6) coarse sand, some silt,
trace light gravel; poorly sorted; moist.
1.1' - White (5Y 8/2) silty very fine sand, trace clay and
light gravel; loose; wet.




SI: 15-17' BLS RE: 1.15'
0.75' - White (2.5Y 8/2) medium to coarse sand, trace clay
and light gravel; poorly sorted; firm; wet.
0.4' - Yellow (2.5Y 8/6) fine to coarse sand, some silt,
trace clay and light gravel; w«t.





SI: 20-22' BLS RE: 1.1'
1.1' - Brownish yellow ( 10YR 6/8) fine to medium sand,
some silt, trace clay and light gravel; light gravel
laminations every several inches; loose; wet.










-------
         ^ASSOCIATES
A Company of SCMne* AppMctttoa*. lac.
8400 W««p*rtc Oriv«. McLwn. Virginia 22102
DRILLING LOG
                                                                   MW-
                                                                           cent.
25





n
1













-


1


ll
SS#5








SS#6









SS*7












1
13
43
18
43






11 12
12 22
14 23
20 25






21
18
21
26








DESCRIPTION
SI: 25-27' BLS RE: 0.8'
0.35" - Pale yellow (2.5Y 8/4) fine to medium sand some
silt, trace light gravel; poorly sorted; loose; wet.
0.45' - Strong brown (7. SYR 5/8) fine to medium sand, some
silt, trace light gravel; few rounded quartz pebbles
at bottom; poorly sorted; wet.



SI: 30-32 BLS' RE: None
Two attempts for sample yielded no recovery. Much
heavy gravel accumulated in bottom of bore hole. Drilling
mud thickened and hole flushed to bring up gravel.






SI: 35-37' BLS RE: 0.7'
0.7' - Strong brown (7. SYR 5/8) fine sand, some silt; wet.



•







                                                                               Page	of	

-------
           SU ASSOCIATES
  A Company at Scttncu Applicmaons. Inc.
  8400 Wntpark Drive, McLean, Virginia 22102
                                           DRILLING LOG
                                                                      MW-041 cont
1










.
•


•
•




.
.
.
,
,
,
,
,
,
;
*

$
•-rv:iv'



- —





mi
I&9
aBH
391
^S^B
H

|iOi|
aflBEa
9HH
H
S^^^^al












J!
SS#8



-




SS#9






SS#10















£
22
20
26
36






17
17
20
25



16
21
50
54











DESCRIPTION
SI: 40-42' BLS RE: 0.4'
0.4' - Same as above







SI: 45-47' BLS RE: 1.3'
0.5' - Same as above
0.8' - Yellowish red (SYR 5/8) silty clay, .trace very fine
sand and silt laminations throughout; few black to
dark brown laminations; firm; dense. Ironed stained
Kirkwood Fra.

SI: 48-50' BLS RE: 2.0'
2.0' - Very dark gray (2.5* 3/0) silty, clay, trace very
fine sand; light gray very fine sand and silt
laminations throughout; firm; dense.












 40
45 -•
 50  --

-------
                        Press Hard - Write Clearly - Use Ball-Point Pen er Typewriter - Press Hard
Mail To:
Water Supply Section
Division of Environmental Control
Tatnall  Building  P.O. Box 1401
Dover. Delaware 19901
PLEASE PRINT
                                            STATE OF DELAWARE
                                  DEPARTMENT OF NATURAL RESOURCES
                                     AND ENVIRONMENTAL CONTROL
                                APPLICATION FOR A PERMIT TO DRILL A WELL
                                  To be completed by a licensed water well driller)
APPLICATION MUST BE
SUBMITTED AND PERMIT
RECEIVED BEFORE ORILLIN
IS STARTED.
Humor- .CfoV^V Ar* PV)KC_€_ P»T}C,<»
Talaphon* Niirnhju- 47$ "£^5^ Plf, ^/.'"tyMPJ-
Uailing ArMriM.- Bl t^O Ciflfl Hlfl C £ *J /fl^EY
xWir Dovev j"W. 1^901
County > Zip
WELL INFORMATION (circle one)
Purpose: Test Weil e^
DMcrlh* Ott^e- JMfljfl i;fc-«ir
Is this a replacement well? yet ^&)
«•**«« tee r*puu*nMnt: _ 	 	 	
Date ahandoMd MM!! It, to t* f+fU^ „„.,.„ 	 „
Ma*
Mat AM AnnllfAtlan ha^n m^f^ ffM- >n Aiw-nw^rl a^MBna
disposal system? yea  r>
ApproximAt* lat^l d^ith et *^U-': J.fa,._^. .....ff,
MJIKI* al ^uil^r- P | ft 1 ft t CJC^* nP


Citing MitariAl: , _ , , PVC
r-ll / r~
&frMn M^lcri*!: 	 rY^
Tentative Screen Sening: between _LSL and Jja.H.
E»llmAtMi length af &frMn __ 	 _.<£l.. _ M
Will the well be gravel packed? (JSy no
TVp*al grout: Ci.S.^ 	 FP*"i; ^O ff ffl ^» ««
CWtirvd rap^<-l»Y al »K^ u^ll- — • _ gpm
Maximum daily UM- 	 — and

1 hereby affirm the Information 1 have furnished
is accurate and correct
jA Q| /W^Wi" ^Appiican^( circle )

Oat* af Application: 1 Man "2. 8 ruy 8 2.
E«tlm«tad Qato af Cjjn0ri>^*lo«; 1 "" —> O — ^2,
rviii«*-De.)yr)-av^xa Hvi 1 («Ma 	


LUCATIOM MAP)
VVL-'V'
A\ ^
/^ ^^
'O-olOS
Vv>c*.^ ^




•
X - s^ «. -•

1 y .
* T
i
L^O'3^13 Ertstns y-— y
y .... C *^

y jf /I
' ^ >< i -^d "' i i ^f i^_^^B_"-^r.AO |^ *
i
Site Plan (Include suitable olot oian if available)











0




?

s
f


^
{ [M
•f
£

_

                               For Official Use Only. ~ Oe Net Write »e»ew Tfcto UM.
                                s governing
                                  /    /
                                itio  83
                                 '    '
Pursuant to provisions of 7 Delaware Code, Chapter 40. permission Is hereby granted to construct and use a well as des-
cribed above. All current regulations governing well construction and water resource use must be followed. The following
conditions must be observed: (       1^1             )
This permit expires:___^__

A completion report must be filed with the Division of Environmental
Control within twenty-one (21) days after completion of this well.
Failure to do so may result In license suspension.
 DOCUMCNTMO.
                                                                              Permit Number:
                                                                              Report filed	

-------
                    RITURN TO:
                                    U'AUR SUPPLY BRANCH
                                    Blue Hen Hall  Office
                                         Box 1401
                                    Dover, Delaware 19901
                                    WELL COMPLETION REPORT
                                                                      DOCUMENT 4G-08/78/C
                                                              ITT-i  I  I  »
1.  Pemlt Number;
   Owner of well:
                       \ 3 \
                                            11. Gravel  pack: Type
                                                                              feet
                                                                                r^r3)2*
                                             12.  Static Water Level:  Date	 ,	
                                                    I a   Ft.(Below, Above) Ground Surface
2.  Use of water: Domes tlcQpubllcQ
   IndustrUlQ AgMcultunlQ IrHgatlonQ
   Comnerclalrj Other
3.  Method of  Drilling:  JetQ DugQ
   DrivenQRotary :  MudQfRev.Q AlrQ
   Other
4.  Test WellQObservatlonQ'ProductlonQ
5. Total  Well  Depth:     O     feet

   Dite Completed
                    Month   Day  Year
6. If this 1s a replacement well, how wai
   previous well  abandoned?
7. Casing Material:  SteelQ PVCQ^oncreteQ
 0 1 ame te r
                 1 n .   F row
                                to   ) (  feet
   Screen Material: SteelQ PVCQ^oncreteQ

          OliiBettr     Q	Inches

          Setting fro»     (|   to
 ). Grout Type:  CementQBentonHe

   Other

   F row
                               feet
                                            13.
                                                 Puraplng Water  Level:    \'l_Ft. below grade
                                                 after    i      hourt) at            9P»
                                             14.
                                                 Well Head Completion:
                                                 Type:  Pitless Adapter (J Other
                                                            Inches above grade
                                             IS. Type of Permanent Pump Installed:
                                                 Pump Manuf.   Ala
                                                 Rated capacity _^	
                                                 Punp Intake setting
                                                                          "FtTbeTow -jrad'e
                                             16.  The completed well  1s
                                                  «.  at least 5'  fro« any overhang
                                                  b.  at least 50'  from any  septic tank
                                                  c.  at least 10'  from town srjer line.
                                                  d.  at least 100' from the ntirest
                                                      edge of any tllefleld	
                                                       (1f well 1s cased less than SO')
                                                  e.  at least 50*  from the  edg«  of any
                                                      tilefteld if casing (not Including
                                                      screen) is more than  bO1 in depth
                                                                                        W
                                              17.
                                              18.
The nearest neighbors  (circle one)
septic tank tile field,  cesspool. or
privy Is         \*ro* completed we 11.

Is completed *ell located as  shown on
application form?	•
                                                   if  no, describe location ci«aru;.«.
0.  Nun-grout Backfill of Well Annul us

   T>pe    11/A   from        to      feet
                                               Company Name
                                               Signature of Water Well Contractor
                                                                                        O.te

                                                                                            4

-------
DRILLERS LOG
Too soil
Fine sand day
Finp fo pnarsp "sanrt

t
* -- *•*




-



THICKNESS OF
STRATUN '
0
1
8
v


-







DEPTH TO BOTTOM
OF STRATUH
1
8
1^







i

•


-------
                        Prtst Hard • Write Clearly - UM Ball-Point Pen or Typewriter • Press Hard
Mail To:
Water Supply Section
Division of Environmental Control
Tatnall Building  P.O. Box 1401
Dover. Delaware 19901
PLEASE PRINT
                                            STATE OF DELAWARE
                                  DEPARTMENT OF NATURAL RESOURCES
                                      AND ENVIRONMENTAL CONTROL
                                APPLICATION FOR A PERMIT TO DRILL A WELL
                                  To be completed by a licensed water well driller)
   APPLICATION MUST BE
   SUBMITTED AND PERMIT
   RECEIVED BEFORE DRILL!
   IS STARTED.
             JAN 2 8
 Owner
                        ar <.£,
 Telephone Number  L7X-LABt
                      C,OO
 Mailing Address:
 Kent     Dover- -D
County
                                         Zip
                                               Date of Application:.
Mon
                                               Estimated Date of Construction:.
        Dey.
- 3o~<92
                                                                                                as.
                                               Pump Installer:
  K\rt Llr««iM NO.

    —.License No.
                                                                                               Lifl
       WELL INFORMATION (circle one)
Purpose: Test Well (Permanent WeljjOptlon to convert
Use:  Domestic • Public • commercial
      Industrial • Agriculture
      Describe Other:
is this a replacement well?
Reason for replacement: _
                                                                     LOCATION MAPS
Date abandoned well is to be sealed:
How	
Has an application been made for an approved sewage
disposal system?  yes ^^
Permit Number: ____^___«______________
                                                Road Map
      PROPOSED WELL CONSTRUCTION
Method of drilling:
Approximate total depth of
Name of aquifer: pl^'| «CtL/-ifM*
                                          .n.
Casing diameter (s) I	1	j
inner to outer (In.)   I  *""  I—""  I
                        PVCL
            (In.)
Casing Material:
Screen Material:
Tentative Screen Setting:  between
Estimated length of screen:
Will the well be gravel packed? (yes> no
Type of grout: C)^   From: jSLtt. to J&— ft.
                               ~        .gpm
                                         .gpd
Desirtd capacity of the well:
Maximum daily use:
 I  hereby affirm the information I have furnished
 is accurate and correct
                                  esentatlve
                                                        Site Plan  (Include suitable plot plan If available)
                               Far Official Use Only. - Do Net Write Below Tteis Urn.

 Pursuant to provisions of 7 Deleware Code. Chapter eO. permission Is hereby granted to construct and use a well as des
 crlbed above. All  current regulations governing well construction and water resource use must be followed. The foilowin
 conditions must be observed:  (        I   i             )
 This permit expires:	//^^/flS?
                                                       SIGNED:
 A completion report must be filed with the Division of Environmental
 Control within twenty-one (21) days after completion of this well.
 Failure to do so mey result In license suspension.
                                                                             Permit Number:
                                                                             Report
  OOCUMCNT NO 4
-------
              PLfASE RITURN TO:
                                     UATCR  SUPPLY BRANCH
                                     Blue Hen Hall Office
                                         Box 1401
                                     Dover. Delaware 1990}

                                                      V
                                    HELL COMPLETION REPORT
                                                                      DOCUMENT  40-OS/78/0
1. Permit Number:
   Owner of well:
                                              11. Grtvel  pack: Typ«
                                                 Fro«          to
                                                                               feet
                                              12.  Static *«ttr Level:  Date	5 -.-lrJ3 2.
                                                   ) ^   Ft. (Below. Above) Ground Surface
2.  Use of water:  DomestlcQpubllcQ
   IndustrlalQAflHculturalQ  Irrigation Q
   Commercial Either
                                              13.
                                                  Puling Water Level:  I/\   Ft. below grade
                                                  »r**»     i/.    twiuntv«t     ^  •   am
3.  Method of Drilling:  JetQ  DugQ
   OrlvenQRotary : HudQ^Rev.Q A1rQ
   Other
                                              14.  Well  Head Completion:
                                                  Typt:  P1tle$$  AdapUrQ^ Other  _
                                                         04. Inches abovt  grade —
4.  Test UellDObservatlonQ^roductlonn
S.  Total  Well  Depth:

   Data Completed
                               f e«t
                    Month  Day  Year
                                              IS. Type of Permanent Pump Installed:

                                                  Pvmp Manuf	Qj£i	'- - -
                                                  Rated capacity    -	T	.
                                                  Pump Intake setting  -       >t.  belo»< -jrade
                                              16.   The completed well  1s
6. If this Is a replacement well, how was
   previous well
 7. Casing Material: SteelQ PVCQConcreteQ

   Diameter  3  1n.  Froa   Q to  || feet
                                                   «.   at least 5'  from «n>  overhang
                                                   b.   at least 50'  from any septic  tank
                                                   c.   at least 10'  from town srjer  line.
                                                   d.   at least 100' from the neirest
                                                       edge of any tllefleld. ..  .
                                                        (1f well Is cased less ihan  SO1)
                                                   e   at least 50' from the edg« of any
                                                       tilefleld If casing- (not Including
                                                       screen)  is more than 50'  in depth
                                                                                           U
                                               17.
                                                   The nearest neighbors (circle one)
                                                   septic tank tile field, cesspool, or
                                                   privy is          fro* completed well.
!.  Screen Material:

           Diameter	^	Inches

           Setting fro»     | |   to  |Q feet



 9.  Grout Type:   Cement Q Ben tonlte  ClayQ

    Other	

                                feet
                                                                                      on
                                                    if  no,  describe  location
 10. Nun-grout Backfill  of Well Annul us

     T>pe   n Id   f rom   ~   to — •
                                                Company
                                                Signature  of Hater Well  Contractor
                                                                                          .te

-------
-X
DRILLERS LOG
Top soil
Fine sand clay
Fine to coarse brown sand


.








•

,
M

-

THICKNESS OF
STRATUM
0
1
9
s











•





DEPTH TO BOTTO*
OF STRATUM
1
9
18













•





-------
                       Press Hard • Write Clearly - Use Ball-Point Pen or Typewriter. Press Hard    JAN 2 8
Mail To:
Water Supply Section
Division of Environmental Control
Tatnall  Building  P.O. Box 1401
Dover, Delaware 19901
PLEASE PRINT
                                           STATE OF DELAWARE
                                  DEPARTMENT OF NATURAL RESOURCES
                                     AND ENVIRONMENTAL CONTROL
                               APPLICATION FOR A PERMIT TO DRILL A WELL
                                 To be completed by a licensed water well driller)
                                                                            APPLICATION MUST BE
                                                                            SUBMITTED AND PERMIT
                                                                            RECEIVED BEFORE DRILLII
                                                                            IS STARTED.
Owner
                 Air E"ov18-(/2)5/
Mailing Address:
                       D
County
                                        Zip
                                              Date of Application: _ L _ Mon._2L§_ Day
                                              Estimated Date of Construction;
                                                                                  ° "
                                              Pump Installer:
                                                                                LIM«>«*
       WELL INFORMATION (Circle one)
Purpose: Test Well (permanent Weft) Option to convert
Use:  Domestic • Public -Commercial
     industrial • Agriculture
     Describe Other:
Is this a replacement well?
Reason for replacement: _
                                                                   LOCATION MAPS
Date abandoned well is to be sealed:
Has an application been made for an approved sewage
disposal system?  yes -(no)
Permit Number:                           _
                                               Road Map
      PROPOSED WELL CONSTRUCTION
                          vj
Method of drilling:
Approximate total depth pf well:
Name of aquifer:  P| e.i&t±Qf.e.vi».
                                          -ft.
                                                 \
                                                                        •» d,  rr loo -
Casing diameter (s) t~^—j—37T
inner to outer (in.)   1.   .1      1
                       PVC
            (in.)
Casing Material:
Screen Material:        	
Tentative Screen Setting: between JLQ_ and JLSLtt.
Estimated length of screen:         fa        ft.
Will the well be gravel packed?
Type of grout: C|^.«f   From
                               no
Desired capacity of
Maximum daily use:
                                           ft.
                                         gpm
                                          gpd
  i hereby affirm the Information I have furnished
  is accurate and correct
                                                            •i      "v    *•• 'i
                                                            r^u-Ho,
                               epresentative
                                                       Site Plan (Include sultaM* ptot plan If available)
                                Per Official Use Only. - Oe Nat Write talaw TMs UM.

  Pursuant to provisions of 7 Delaware Code. Chapter 40. permission Is hereby granted to construct and use a well as des-
 cribed above. All current regulations governing well construction and water resource use must be followed. The following
  conditions must be observed: (      /     /              )
 ' This permit expires:            y^fl/fl ^	
                                                       SIGNED:
  A completion report must be filed with the Division of Environmental
  Control within twenty-one (21 ) days after completion of this well.
  Failure to do so may result In license suspension.
                                                                            Permit Number:
                                                                            Report filed	
                                                                                                   *
  DOCUMENT MO

-------
              PITA5E  RirURN TO:
                                    U'AT[R SUPPLY  BRANCH
                                    Blue Hen Hall Office
                                         Box 1401
                                    Dover, Delaware  19901
                                    HELL COMPLETION REPORT
                                                                      DOCUMENT 4G-08/78/<
                                                                            mcro:
1.  Permit Number:  S
   Owner of well:
                                             11. Gravel   pack: Typt
                                                 from         to
                                                                             feet
                                             12. Static Hater Level:
                                                         Ft. (Be low. Above) Ground Surface
2. Use of water:  DomestlcQpubllcQ
   Jndustrlain Agriculture 1Q IrrlgatlonQ
   Coninerd airj Other
3. Method of Drilling:  JetQ DugQ
   OrlvenQ Rotary: MudQUev.Q AlrQ
   Other
4. Test WellQObservatlonQ^roductlonQ
5.  Total Well Depth:

        Completed
                         | <")   feet

                                 ?£)
                    Month  Day  Year
 6.  If this Is a replacement well,  how was
    previous well abandoned?
                     til*
	      	      /      ,         •
 7. Casing Material: SteelQ P VC0 Cone ret eQ

   Diameter  c3_Jn.  Frooi  fo  to  ( /  feet
8.  Screen Material: SteelQ PVCQConcreteQ

           DUmeUr              Inches
           Setting froa    \ |    to \ r\  feet
 9.  f»rout  Type:  CementQ Bentonlte

    Other        .
                               feet
                                             13.  Pumping Water Level:
                                                 after    fa   hou Other  ^
                                                            Inches above  grade       Tj~tT~
                                             15.  Type of Permanent Pump Installed:
Pump Manuf.	
Rated capacity..
Pump Intake  setting
                                                                            7t.
                                                                                      -jrade
                                             16.  The completed well  1s
                                                  «.   at least 5' from an> overhang
                                                  b.   at least 50' from any septic  tank
                                                  c.   at least 10* from town $i-.pe    MA*  From       to      f*«»t

                                              Signature of Water Well  Contractor
                                                                                       D,te

-------
J
DRILLERS LOG
Top soil
Clay
Fine to coarse sand |


^ _. A

t








.
4
»

THICKNESS OF
STRATUM
0
1
3
/ *


\





•






DEPTH TO BOTTOM
OF STRATUM
1
3
18








•




'... , .



-------
                 ENVIRONMENTAL S/   /•LING  DATA
                           (TRACE ORGANICS)
                                                                              rwm n»i»   /
                                                                              OEHCUSEOH./
  ' L sr thtsspjce for mechanical iitiprtnti
                                                                         SAMPLING SITE
                                                                           IDENTIFIER
                                                                            IAFR 19- 7
                                                                             BASE WHERE SAMPLE COLLECTED
                                                                            SAMPLING SITE DESCRIPTION
   DATE COLLECTION BEGAN
            n')\ntUDl
                               TIME COLLECTION BEGAN
                               124 hour clock/
                                         COLLECTION METHOD

                                           Q GRAB      Q COMPOSITE
        MAIL
     REPORTS
        TO
     u in le II
     ( itan^cdi
                   ORIGINAL
                    COPY 2
   SAMPLE COLLECTED BY f\jnir. < ,rade Af-'SC,
                                                                            SIGNATURE
                                                                                                                        AUTOVON
REASON FOR
SUBMISSION
A-ACCIDENT/INCIDENT
R-RO UTI NE, 'PERIODIC
                                                                   C-COMPLAINT
                                                                   N-NPDES
F-FOLLOWUP/CLEANUP
O-OTHBR_/JpfclM /  	
         BASE SAMPLE NUMBER
           1
                                                                                       O€HL PIO
                                              ANALYSES REQUESTED 'check appropriate blocks/
  \OL-\riLl HALO( ARHOVS t\OHi       IOH60)
                                                  rnchlorotluoromettuni:
                                                                                       3448H
                                                                                             MISf  LL \M 01 S
   n
                           PRI •> GROl P  1
                                                      \ m\  f blonde
                                                                                      39T5
         t.le Haio.arron S.r^en
                                    |ool46Ul'H
                                                                                                                   PRI s (,ROIP ri
     H rom od K bin ronie thane
                                                                                                    \\lene
                                                                                                                                    HI "10
     Hronv TT.I. tlun.'
                                                   Kiii \l o\ll  1 li \M s i  HM,
                                                                                      < |i)H6D)
     '  arbon I etrai.nlorHje
                                                                        'RI  S (,ROl 1' I 1
                                                                                                                                  i2 1 UMiH
                                         ?4 3'
                                                       r'u omcthane Potential      1 Il'il465\l I
     ( hloroetlune
                                         343 1
                                                   Total I nhalomethan
                                                   S2')>)(t
     1-t hloroetln vm\l ether
                                         345"6
      hloruii.r
                                                    VOUriLJ  AKONI \ IK S (VOAi     ilOH50i
     ( hloromethane
                                         '4418
                                                         n
                                                                        I'Rl S f.RfJl P Tl
     UihromoLhloromethane
                                         32  05
                                                   Volatile Uomatic Vreen       1001461P-X
     1  2 ilk hlorohen/ene
                                         '45^
                                                      llen/ene
                                                                                    34ll3i
                                                                                                MIM'  I L \M 01 S
     1  4 ,iKh!ori>hen/ene
                                         345' 1
                                                                                                                   PKI S (iROL P T4
     l)khlor(i>i:tluoronie thane
                                                                                                    P( 1) ^
     1   1 ili.hloroethane
                                         34496
                                                        4-d:.nMro'"enz'.-n-.'
                                                                                                    Phtlulatc 1  ^crs Screen
                                                                                                                               1000069PH
                                                                                      343"!
     1   1 •Jkhi'jroethene
                                        345 il
                                                                                      34H10
                                                                                                                                    3-1292
     lrans-1, 2 Jichloroethene
                                        34546
                                                                                                    lJi-n-iuit\ i phthalate
                                                                                                                                 39110
      , 2-dii.hloropropane
                                      34541
                                                                                                       1 phthalate
                                                                                                                                 34336
     tis-1  3-cikhloropropene
                                        34"04
                                                                                                 Dinv  i>l phthalate
                                                                                                                                 343-i
     trans- 1  3-dichlornpropene
                                        34M9
                                                                                                       tyl ih'Malati:
     \1eth\lene C blonde
      . 1  2  2-tetrachloroethane
      etra^hloroethvlene
     1  1  1 -trkhloroethane
                                         '4^ 16
     1  1  2-mchloroethane
                                         '45  1
     Trii.hloroelhxlene
                                        39 I Hi)
REMARKS
AF   «Tjy.1  2752B AF FORMS 2752A AND AF 2752B. FEB 85. REPLACE AF FORM 2752. JAN 31, WHICH WILL BE USED

-------
  prc
  Planning Research Corporation              303 East Wacner Dr>\e
                                          Su.te 500
                                          C"C3qc IL 50601
                                          3' 2-928-0300
April 10, 1987
Mr. Anthony Montrone
Hazardous Waste Ground-Water Task Force (WH-562A)
U.S. EPA
401 M Street, S.W., Room S-6301
Washington, D.C.  20460

Dear Mr. Montrone:

     PRC Environmental Management, Inc., is pleased to submit for your review the
final memorandum for QA/QC support of the Work Assignment No. 548, entitled
"Evaluation of Quality Control Attendant to the Analysis of Samples from the Dover
Air Force Base, Delaware."

     If you have any questions regarding this submittal, please feel free to contact
us.

Sincerely,

PRC Environmental Management, Inc.
Daniel T. Chow

Enclosure

cc:   Nancy Deck (letter only)
     Bruce Bakaysa (letter only)
     Barbara Elkus (w/1 copy of report)
     Rich Steimle (w/1  copy of report)
     Paul  Friedman (w/1 copy  of report)
     KenPartymiller (w/1 copy of report)
                  «  ^—ii •  j —  -1	
     Pat Krantz (w/1 copy of report)
     Gareth Person (w/1 copy of report)
     Chuck Hoover (w/1 copy of report)

-------
pro
Planning Research Corporation
303 East 'A/acker C
Sole 5CQ
C'.cago i|_ 60601
3-2-938-0300
ve
          EVALUATION OF QUALITY CONTROL ATTENDANT
             TO THE ANALYSIS OF SAMPLES FROM THE
                 DOVER AIR FORCE  BASE, DELAWARE
                        FINAL MEMORANDUM

                            Prepared for

             U.S. ENVIRONMENTAL PROTECTION AGENCY
                  Office of Waste Programs Enforcement
                        Washington, D.C.  20460
                  Work Assignment No.
                  EPA Region
                  Site No.
                  Date Prepared
                  Contract No.
                  PRC No.
                  Prepared By
                 Telephone No.
                 EPA Primary Contact
                 Telephone No.
      548
      Headquarters
      N/A
      April 10, 1987
      68-01-7037
      015-54824-03
      PRC Environmental
      Management,  Inc.
      (Ken Partymiller)
      (713) 292-7568
      Anthony Montrone/
      Barbara Elkus
      (202) 382-7912
                                                     yFiw$$f! ;\:» •:-.
                                                   f*{*»-*''• *' '"*
                                       ENFORCEMENT
                                       CONFIDENTIAL

-------
MEMORANDUM
DATE:    April  16, 1987
SUBJECT: Evaluation of Quality Control Attendant to the Analysis of Samples
          from the Dover Air Force Base, Delaware Facility
FROM:    Ken Partymiller, Chemist
          PRC Environmental Management
THRU:    Paul H. Friedman, Chemist*
          Studies and Methods Branch  (WH-562B)
TO:       HWGWTF:  Tony Montrone*
          Gareth Pearson (EPA 8231)*
          Richard Steimle, HWGWTF*
          Pat Krantz, Region HI
          Joe Kotlinski, Region III
     This memo summarizes the evaluation of the quality control data generated by
the Hazardous Waste Ground-Water Task Force (HWGWTF) contract analytical
laboratories (1).  This evaluation and subsequent conclusions pertain to the data
from the Dover Air Force Base, Delaware sampling effort by the Hazardous Waste
Ground-Water Task Force.

     The objective of this evaluation is to give users of the analytical data a more
precise understanding of the limitations of the data as  well as their appropriate use.
A second objective is to identify weaknesses in the data generation process for
correction.  This correction may act on future analyses at this or other sites.

     The evaluation was carried out on information provided in the accompanying
quality control reports (2-5) which contain raw data, statistically transformed data,
and graphically transformed data.
*  HWGWTF Data Evaluation Committee Member

-------
     The evaluation process consisted of three steps. Step one consisted of
generation of a package which presents the results of quality control
procedures, including the generation of data quality indicators, synopses of
statistical indicators, and the results of technical qualifier inspections. A  report on
the results of the performance evaluation standards analyzed by the laboratory was
also generated.  Step two was an independent examination of the quality control
package and the performance evaluation sample results by members of the Data
Evaluation Committee.  This was followed by a meeting (teleconference) of the Data
Evaluation Committee to discuss the foregoing data and data presentations.  These
discussions were to come to  a consensus, if possible, concerning the appropriate use
of the data within the context of the HWGWTF objectives. The discussions were
also to detect and discuss specific or general inadequacies of the data and to
determine if these are correctable or inherent in the analytical process.
Preface

     The data user should review the pertinent materials contained in the
accompanying reports (2-5).  Questions generated in the interpretation of these data
relative to sampling and analysis should be referred to Rich Steimle of the
Hazardous Waste Ground-Water Task Force.

I.    Site Overview

     The Dover Air Force Base is located near Dover, Delaware.  It has been in
existence for over 30 years.  The hazardous waste disposal units at  the facility are
now closed.  Their previous  locations are surrounded by monitoring wells.  The units
were primarily for the disposal of organic solvents  used for the dcgreasing of
aircraft engine parts. From the previous history of  the site, the presence of
volatile organics in the  ground water is a  possibility.

     The geology of the site is mainly sandy material containing some clay.
Migration of contaminants would, therefore,  be expected to be rapid. The water
table in the area is near the ground surface.  One of the wells yielded a sample
with a distinct organic  layer.  Results for this sample were not available.

     Twenty-five field samples  including a field blank (MQA914/Q1514), an
equipment blank (MQO888/QO888), a trip blank (MQO887/QO887), and two pairs of
duplicate samples (well 11, samples MQA920/Q1520  and MQA921/Q1521  and well 103,
samples MQA910/Q1510 and MQA911/Q1511) were collected at this facility.  Sample
MQA903/Q1503 was specified by the sampling team as a medium concentration  matrix
ground-water sample and was analyzed only  for inorganics and
dioxins/dibenzofurans.   Sample  Q1S22 was an organic liquid which was not analyzed
in time to be  included in this report.  Samples were not split with Region III.

-------
II.   Evaluation of Quality Control Data and Analytical Data

1.0   Metals

1.1   Performance Evaluation Standards

     Metal analyte performance evaluation standards were not evaluated in
conjunction with the samples collected from this facility.

1.2   Metals QC Evaluation

     Total metal spike recoveries were analyzed for  twenty-three metals spiked into
two (of three possible) low concentration matrix samples (MQA900, 912, and 913)
and one medium concentration matrix sample (MQA903).  Twenty-one metal average
spike recoveries from the low concentration matrix samples were within the data
quality objectives (DQOs) for this Program. The tin  average spike recovery  was
outside DQO with a value of 130 percent. The aluminum  spike recovery was not
calculated because the sample concentration of this metal  was greater than four
times the  concentration of the spike.  Various  individual metal spike recoveries from
the low concentration matrix samples were also outside  DQO. These are listed in
Tables 3-la and 3-2a of Reference 2 as  well as in the following Sections.  A listing
of which  samples were spiked for each analyte is also available in Table 3-2a of
Reference 2.

     Twenty of twenty-three metal spike recoveries  from  the medium concentration
spiked samples were within Program DQOs. Only  one medium concentration matrix
sample was spiked for each metal. The aluminum  and cadmium spike recoveries
were outside DQO with recoveries of 182 and  28 percent,  respectively. The  lead
spike recovery was not calculated because the  sample concentration of this metal
was  greater than four times the concentration  of the spike. A listing of which
samples were spiked for each analyte is available in  Table 3-2b of Reference 2.

     The  calculable average relative percent differences (RPDs) for all metallic
analytes in the low concentration matrix samples were within Program DQOs. The
calculable RPDs for all metallic analytes in the medium concentration matrix samples
were within the DQOs with the exceptions of chromium and aluminum. RPDs were
not calculated for about one-half of the metal analytes  because the  concentrations
of many of the metals in the field samples used for  the RPD determination  were
less than  the CRDL and thus were not required, or in some cases, not possible to
be calculated.

     Required analyses were performed on all  metals samples submitted to the
laboratory.

     No metals contamination was reported in  the laboratory blanks. Tin
contamination was found in field and trip blanks  at concentrations of 80  and 54
ug/L (the tin CRDL equals 50 ug/L).

-------
1.3   Furnace Metals

     The quality control for the graphite furnace metals (antimony, arsenic,
cadmium, lead, selenium, and thallium) was generally acceptable.

     One of two cadmium (sample MQA913) and both lead (samples MQA900 and 913)
spike recoveries from the low concentration matrix samples were outside DQO with
values of 130, 56, and 134 percent. The cadmium spike recovery from the medium
concentration matrix spike sample was also outside DQO with, a recovery of 28
percent.

     The correlation coefficient for the method of standard addition (MSA) analysis
of lead in samples MQA903, 920, and 921 was below DQO. All positive lead results
should be considered qualitative.

     All antimony, arsenic, selenium, and  thallium, and cadmium (with an exception)
results should be considered quantitative.  All negative lead results (samples
MQ0887, MQO888, MQA900, and MQA914) should also  be considered quantitative.
All positive lead results should  be considered qualitative.  Due to poor recovery, the
cadmium result for sample MQA920 should not be used. The  usability of all graphite
furnace analytes is summarized in Section 4.0 at  the end of this Report.

1.4  ICP Metals

     Tin contamination was found in the  field blank (MQA914) and trip blank
(MQO887) at concentrations of  80 and 54 ug/L, respectively.  The CRDL for tin is
50 ug/L. Due to this contamination, tin results for samples MQA904 through 909,
911 through 913, and 915 through 921 should be  considered unusable. The remaining
tin results should be considered quantitative.

     The low level (twice CRDL) linear range check for chromium, cobalt, nickel,
silver, tin,  vanadium, and zinc  exhibited poor recoveries on various analysis dates
(see Section B3 of Reference 3  for a detailed listing).  The low  level linear range
check is an analysis of a solution with elemental concentrations near the detection
limit.  The range check analysis shows the accuracy which can be expected by the
method for results near the detection limits. The accuracy reported for these
metals is not unexpected.  Low  level linear range check results for chromium and
silver for all samples except MQA903 had variable recoveries and thus a bias, if
any, was impossible to determine.  Cobalt, nickel, tin, vanadium, and zinc  low level
results for all samples except MQA903 should be considered to be biased low by
approximately 20 to 30  percent. Nickel, vanadium, and zinc low level results for
sample MQA903 should be considered to be biased high by approximately  20 percent.
Results for sample MQA903 showed no recovery  of chromium and  thus the negative
chromium  results for this sample are not reliable and should  not be used.

     Individual matrix spike recoveries were outside DQO for tin  in low
concentration matrix sample MQA900 with 142 percent recovery and for aluminum in
medium concentration matrix sample MQA903 with 183 percent recovery.  The tin
results were judged to have no  impact on  the data quality as  it represented only
one of two matrix spikes. The  aluminum  results for sample MQA903 should be
considered to be qualitative due to the high aluminum recovery from the matrix
spike.

-------
     Laboratory duplicate results for aluminum and chromium in medium
concentration matrix sample MQA903 were outside DQO with RPDs of 71 and 34
percent.  These results caused the medium concentration matrix aluminum results to
be considered qualitative and the chromium results to be considered semi-
quantitative.

     All barium, beryllium, calcium, cobalt, copper, iron, magnesium, manganese,
nickel, potassium, silver, sodium, vanadium, and zinc results should be considered
quantitative. Aluminum, chromium, and tin results, all with exceptions, should also
be considered quantitative. Chromium results for sample MQA903 should be
considered semi-quantitative.  Aluminum results for sample MQA903 should be
considered qualitative.  Tin results for samples MQA904 through 909, MQA911
through 913, and MQA915 through 921 should not be used due to the above
mentioned blank contamination. The usability of all total and dissolved  ICP  metal
analytes is summarized  in Section 4.1 at the end of this Report.

1.5  Mercury

     All mercury results should be considered quantitative.

2.0  Inorganic and Indicator Analvtes

2.1  Performance Evaluation  Standard

     Inorganic and indicator analytc performance evaluation standards were  not
evaluated in conjunction with the samples collected from this facility.

2.2  Inorganic and Indicator Analvte OC Evaluation

     The average spike recoveries of all of the inorganic and indicator analytes,
except for chloride in the low concentration matrix were within the accuracy DQOs
(accuracy DQOs have not been established for bromide, fluoride*, and nitrite  nitrogen
matrix spikes).  The chloride average spike recovery was 110.5 percent in the low
concentration  matrix sample.  The bromide, fluoride, and nitrite nitrogen average
spike recoveries were 112.5, 107, and 107 percent in the low concentration matrix
samples and 100, 110, and 100 percent  in the medium concentration matrix sample.

     Average  RPDs for all inorganic and indicator  analytes were within  Program
DQOs.  The RPDs were not calculated if either one or both of the duplicate  values
were less than the CRDL.  Precision DQOs have not been established for bromide,
fluoride, and nitrite nitrogen.

     Requested analyses were performed on all samples for the inorganic and
indicator analytes.

     No laboratory blank contamination was reported for any inorganic  or indicator
analyte. The field blank contained 40 ug/L of TOX contamination (CRDL equals 5
ug/L).

-------
2.3   Inorganic and Indicator Analvte Data

     All results for cyanide, bromide, chloride, fluoride, sulfate, total phenols, TOC,
and POX should be considered quantitative with an acceptable probability of false
negatives.

     The holding times for the nitrate and nitrite  nitrogen analyses ranged from 9
to 10 days from receipt of samples which is longer than the recommended 48 hour
holding time for unpreserved samples.  All nitrate  and nitrite nitrogen results should
be considered semi-quantitative.

     The matrix spike recovery for chloride from  one of two low concentration
matrix spike samples was above the DQO recovery range 90 to 110 percent with  a
value of 114 percent.  This was not judged to have a significant impact on the
quality  of the data and all chloride results should  be considered quantitative.

     Calibration verification standards for POC were not analyzed.  A high and a
low concentration  POC spike solution was run during the analytical batch but the
"true" value of the spike was not provided by the laboratory.  EPA needs to supply
the inorganic laboratory with a POC calibration verification solution.  Until then,
the instrument calibration can not be assessed.  Also, although these spike solutions
were used as calibration verification standards, they were not run at the beginning,
at the end, and at  an interval of every ten samples analyzed during the analytical
batch, as required.  POC holding times ranged from 28 to 30 days. Although the
EMSL/Las Vegas data  reviewers recommend a seven day holding time, the  laboratory
has been instructed by the EPA Sample Management Office that a 14 day holding
time is acceptable.  The POC results should be considered qualitative.

     The field blank contained TOX contamination at a level of  40 ug/L which is
greater  than  the TOX CRDL of 5 ug/L. As a HWGWTF convention, all TOX results
greater  that ten times the highest field blank concentration or less than the
detection limit should  be considered quantitative.  All TOX results greater than  five
but less than ten times the highest concentration of sampling blank  contamination
are considered  qualitative and all other TOX results arc considered unusable.  The
TOX results  for samples MQA900 through 902, 904 through 908, 912, and 915
through 919 should not be used. All other TOX results should be considered
qualitative.

      The POX holding times ranged from 6 to 12 days. Although  the EMSL/Las
Vegas data reviewers recommend a seven day holding time, the laboratory has been
instructed by the EPA Sample Management Office that a 14 day holding time is
acceptable.  The POX  results should be considered quantitative.

-------
3.0   Organics and Pesticides

3.1   Performance Evaluation Standard

     Organic performance evaluation standards were not evaluated in conjunction
with the samples  collected from this facility.

3.2   Organic OC Evaluation

     All matrix spike average recoveries were within established Program DQOs for
accuracy. Individual matrix spike recoveries which  were outside the accuracy DQO
will be discussed  in the appropriate Sections below.  All surrogate spike average
recoveries were within DQOs for accuracy.  Individual surrogate spike recoveries
which were outside the accuracy DQO will be discussed in the appropriate Sections
below.

     All matrix spike/matrix spike duplicate average RPDs, with the exceptions of
those for chlorobenzene and lindane (gamma-BHC), were within Program DQOs for
precision.  Individual matrix spike RPDs which were outside the precision DQO will
be discussed in the appropriate Sections below. All average surrogate spike RPDs,
with the exception of that for 2,4,6-tribromophcnol, were within DQOs for  precision. -
No surrogate standard was used for  the herbicide analysis.

     All organic  analyses were performed as requested.

     Laboratory  blank contamination was reported for organics and  is discussed in
Reference  4 as well as the appropriate Sections below.

     Detection limits for the organic fractions are summarized in Reference 4 as
well as  the  appropriate Sections below.

3.3  Volatiles

     Quality control data indicate that volatile organics were determined acceptably.
The chromatograms appear  acceptable.  Initial  and continuing calibrations,  tunings
and mass calibrations, matrix spikes and matrix spike duplicates, surrogate  spikes,
and holding times were acceptable.  Laboratory blank contamination was reported.

     Laboratory  (method) blanks MB1, MB2, MB3, and MB4 contained methylene
chloride contamination.  This common laboratory contaminant was present at levels
(4 to 5 ug/L) in the vicinity of the methylene chloride CRDL (5  ug/L).  All positive
methylene  chloride results (samples Q1500,  1501,  1502, 1504, 1505, 1506,  1507, 1508,
1509, 1510, 1511, 1512,  1513, 1515, 1516, 1517,  1518,  1519, 1520, and 1521) should
not be used due to this laboratory blank contamination.

     The organic analytical laboratory is not using the contract specified primary
ions to  quantitate results for many of the HSL compounds.  This has no  affect on
the results.  The  laboratory has been made aware of this discrepancy and is
correcting  it for  future analyses.

     The volatiles data are acceptable.  Estimated method detection limits were
CRDL for  all samples except Q1509 (100 times CRDL), Q1510 (20 times  CRDL), Q1511
(20 times CRDL), Q1520 (10 times CRDL), and Q1521 (10 times CRDL).  Dilution of
these samples was required  due to high concentrations of organics. The  volatile

-------
compound results should be considered quantitative with the above mentioned
exceptions for methylcnc chloride. False negatives for the samples (Q1509, 1510,
and 1511) should be considered a possibility due to large sample dilutions.  The
probability of false negative results for all other compounds is acceptable.

3.4   Semivolatiles

     Initial  and continuing calibrations, tuning and mass calibrations, holding times,
and chromatograms were acceptable for the semivolatiles.  Some  problems were
encountered with blanks, matrix spikes and matrix spike duplicates, and surrogate
spike  recoveries.

     Due to a dilution factor of 2.0, the estimated detection limits for the
semivolatiles were approximately twice  the CRDL.

     The matrix spike recovery of 4-nitrophcnol from sample Q1512MS and 2,4-
dinitrotoluene from sample Q1506MSD were above DQO ranges of 10 to 80 percent
and 24 to 96 percent with values of 87 and 99 percent, respectively. The RPD for
pentachlorophenol in  the matrix spike duplicate analyses for sample Q1512 was above
the DQO limit.

     The phenol-D5, 2-fluorophenol, and 2,4,6-tribromophenol surrogate spike
recoveries from samples Q1504 and 1504RE (rccxtraction and-reanalysis) and the 2-
fluorophcnol recoveries from samples Q1512,  and  1519 were below their respective
DQO  ranges. The tcrphcnyl-D14 surrogate spike recovery from sample Q1506MSD
(matrix spike duplicate) and the phenol-D5 recoveries from samples QO888, Q1500,
1505,  and 1507 were above their respective DQO ranges.  The acid fraction results
for samples  Q1504 and 1504RE should  be considered suspect due to this poor acid
surrogate recovery. There was no  impact on the rest of the data.

     Two of the semivolatile method (instrument) blanks, MB1 and MB2, contained
bis(2-ethylhcxyl)phthalate contamination at concentrations of 7 and 3 ug/L. This
caused no impact on the data.

     The organic analytical laboratory is not using the contract  specified  primary
ions to quantitate results for many of the HSL compounds.  This has no affect on
the results.  The laboratory has been made  aware of this discrepancy and is
correcting it for future analyses.

     The semivolatile data are acceptable and the  results should be considered
quantitative for all samples with the exception of the acid fraction (phenols) results
for sample Q1504 and the reextraction and reanalysis of this sample.  The
probability of false negatives for all samples, with the exception of the acid
fraction  results for sample Q1504, is acceptable. Acid fraction results for sample
Q1504 should be considered unreliable.

3.5    Pesticides

     The initial calibrations, blanks, surrogate spikes, holding times, and
chromatography for pesticides were acceptable. Continuing calibration and matrix
spike  and matrix spike duplicate problems  were encountered.

-------
     The matrix spike/matrix spike duplicate RPDs for lindane (gamma-BHC) and
4,4'-DDT in sample Q1512 were above DQO limits. Lindane was detected in samples
Q1504, 1509, and  1517 but due to this poor matrix spike, these results should be
considered  semi-quantitative. There were also precision problems with the kepone
calibration factor but no kepone was found in any samples and the laboratory has
agreed to correct  the problem so this is considered inconsequential.

     The organic analytical laboratory did not follow the proper sequence of
pesticide calibrations. This was  not judged to affect data quality.

     The pesticides results  should be considered quantitative  with the exception of
the lindane (gamma-BHC) results for samples  Q1504,  1509, and 1517 which should be
considered  semi-quantitative.

3.6  Herbicides

     Initial and continuing calibrations, blanks, and  matrix spike/matrix spike
duplicates were acceptable  for the herbicide analyses. Several shortcomings with
the herbicide chromatography were noted. No surrogate standard was used for the
herbicides.

     The herbicides for which the laboratory analyzed include only 2,4-D, 2,4,5-T,
2,4,5-TP, chlorobcnzilatc, phorate, disulfoton, parathion, and famphur.

     It was felt by the EMSL/Las Vegas data reviewers that the laboratory used an
inappropriate pair of columns to quantify and confirm the chloro-herbicides analysis.

     The laboratory should have used a two column  confirmation method to analyze
the organophosphorus herbicides.

     The herbicide results  should be considered suspect due to the lack of herbicide
surrogates  and confirmation column analyses.

3.7  Dioxins and Dibenzofurans

     Dioxin and  dibenzofuran spike recovery from the blank spiked sample ranged
from 91 to 97 percent which is  considered to  be acceptable accuracy.  No precision
(RPD) information was  available as no dioxins were  detected in the duplicate
samples.  No contamination was found in the laboratory (method) blanks.  Octa-
chlorodibenzodioxin was found at low concentration  in samples Q1503 and 1506 but
was not reported  by the laboratory.

     The laboratory was not able to meet the DQO resolution criteria for two
initial and three routine calibrations for the two carbon-13 labeled TCDD isomers on
several dates.  Also, the  recovery of the internal standards  were outside DQO for
the carbon-13 labeled TCDD isomer for sample Q1500 and for the carbon-13 labeled
isomer of OCDD  for the method blank and for sample Q1500DUP (duplicate).
Dioxin/dibenzofuran negative results  for sample Q1500 should,  therefore, be
considered  qualitative.

-------
     The dioxin and dibenzofuran results should be considered to be quantitative
with exceptions.  The internal standard recovery for samples Q1500 and Q1500DUP
was low, therefore, results for this sample should be considered qualitative.
Octachlorodibenzodioxin and octachlorodibenzofuran results for all samples should be
considered qualitative due to lack of calibration linearity and sensitivity verification.

III.  Data Usability Summary

4.0  Graphite Furnace Metals
Quantitative:

results
Qualitative:
Unusable:

4.1  1CP Metals

Quantitative:
Semi-quantitative:
Qualitative:
Unusable:
4.2 Mercury

Quantitative:
all antimony, arsenic, selenium, and thallium results;
cadmium results with an exception; all negative lead

all positive lead results
cadmium results for sample MQA920
all barium, beryllium, calcium, cobalt, copper, iron,
magnesium, manganese, nickel, potassium, silver, sodium,
vanadium, and zinc results; aluminum, chromium, and tin
results with exceptions;
chromium results for sample MQA903
aluminum results for sample MQA903
tin results for samples MQA904 through 909, 911 through
913,  and 915 through 921
all mercury results
4.3 Inorganic and Indicator Analvtes
Quantitative:

Semi-quantitative:
Qualitative:
Unusable:
4.4 Oreanics

Quantitative:

Semi-quantitative:

Unreliable:

Unusable:
all cyanide, bromide, chloride, fluoride, sulfate, total
phenols, TOC,and POX results
all nitrate and nitrite nitrogen results
all POC results; TOX results with exceptions
TOX results for samples MQA900 through 902, 904 through
908, 912, and 915  through 919
volatile, semivolatile, and pesticide results, all with
exceptions
lindane (a pesticide) results for samples Q1504, 1509, and
1517
semivolatile acid fraction results for sample Q1504; all
herbicide results
all positive methylene chloride (a volatile)  results
                                        10

-------
4.5   Dioxins and Dibenzofurans

Quantitative:       all dioxin and dibenzofuran results with exceptions
Qualitative:         all results for sample Q1500/1500DUP; all octa-CDD and
                   octa-CDF results

IV.  References

1.    Organic Analyses:   EMSI
                        2421 West Hillcrest Drive
                        Newbury Park, CA  91320
                        (805) 388-5700

     Inorganic and Indicator Analyses:
                        Centec Laboratories
                        P.O. Box 956
                        2160 Industrial Drive
                        Salem, VA  24153
                        (703) 387-3995

     Dioxin/Dibenzofuran Analyses:
                        CompuChcm Laboratories, Inc.
                        P.O. Box 12652
                        3308 Chapel Hill/Nelson Highway
                        Research Triangle Park, NC 27709
                        (919) 549-8263


2.    Draft Quality Control Data Evaluation Report (Assessment of the Usability of
the Data Generated) for site 47, Dover Air Force Base, Delaware,  3/18/1987,
Prepared by Lockheed Engineering and Management Services Company, Inc., for the
US EPA Hazardous Waste Ground-Water Task Force.

3. Draft Inorganic Data Usability Audit  Report, for the Dover Air Force  Base,
Delaware facility, Prepared by Laboratory  Performance Monitoring Group, Lockheed
Engineering and Management Services Co.,  Las  Vegas, Nevada, for US EPA,
EMSL/Las Vegas, 3/18/1987.

4. Draft Organic Data Usability Audit Report,  for the Dover Air  Force Base,
Delaware facility, Prepared by Laboratory  Performance Monitoring Group, Lockheed
Engineering and Management Services Co., Las  Vegas, Nevada, for US EPA,
EMSL/Las Vegas, 3/18/1987.

5. Draft Dioxin/Dibenzofuran Usability Audit  Report, for  the Dover Air Force Base,
Delaware facility, Prepared by Laboratory  Performance Monitoring Group, Lockheed
Engineering and Management Services Co., Las  Vegas, Nevada, for US EPA,
EMSL/Las Vegas, 3/17/1987.
                                      11

-------
V. Addressees

Anthony Montrone
Hazardous Waste Ground-Water Task Force, OSWER (WH-562A)
US Environmental Protection Agency
401 M Street S.W.
Washington, DC  20460

Gareth Pearson
Quality Assurance Division
US EPA Environmental Monitoring Systems Laboratory - Las Vegas
P.O. Box 1198
Las Vegas, Nevada  89114

Richard Steimle
Hazardous Waste Ground-Water Task Force, OSWER (WH-562A)
US Environmental Protection Agency
401 M Street S.W.
Washington, DC  20460

Joe Kotlinski
US Environmental Protection Agency
841 Chestnut Street
Philadelphia, PA 19107

Pat Krantz
US Environmental Protection Agency
839 Bestgate Road
Annapolis, MD  21401

Paul  Friedman
Characterization and Assessment Division, OSW (WH-562B)
US Environmental Protection Agency
401 M Street S.W.
Washington, DC  20460

Chuck  Hoover
Laboratory Performance Monitoring Group
Lockheed Engineering and Management Services Company
P.O. Box 15027
Las Vegas, Nevada  89114
                                     12

-------