United States
Environmental Protection
Agency
Office of Water
Piogram Operations (WH-547)
Washington DC 20460
430/9-83-006
July 1382
Water
Management
of Environmental Protection
Agency Project
by Local Grantee

-------
EPA-430/9-83-006
   July 1982
                      Management  of Environmental

                      Protection  Agency  Project

                      by  Local Grantee
                          Final Report
                        Prepared by

                     Department of Civil Engineering
                     University of California
                     Berkeley, California  94720

                           For

                     Municipal Construction Division  (WH-547)
                     Office of Water Programs Operations
                     U.S. Environmental Protection Agency
                     Washington, D.C.  20460

-------
Although the research described in this report has been funded wholly or



in part by the United States Environmental Protection Agency through



grant T-901266-01, to the University of California, it has not been



subjected to the Agency's required policy review and therfore does not



reflect the views of the Agency and no offical endorsement should be



inferred.

-------
                         AKNOWLEDGEMENTS


This report resulted from the cumulative efforts of a large number of
individuals and organizations. Many grantees, consultants, state
and federal personnel contributed time, data from projects,
ideas, and lessons learned through experience.

As we developed our tentative recommendations we received
extraordinarily valuable guidance and  input from an informal
steering committee, consisting of Messrs. Harold Gold, Esq.,
Donald Barrie, Woodward Wilson, and Professors Robert Carr, John
Melin and Boyd Paulson. These gentlemen shaped this study  in  its
earliest, most critical stage by directing us away from
impractical or unrealistic alternatives, and by their astute
insights on good management practices.

The report was written by the Project  Investigator, Associate
Professor Weston T. Hester,  Department of Civil Engineering,  with
the assistance of graduate students from the Department of Civil
Engineering,  School of Law,  and School of Business
Administration, University of California, Berkeley.

As a graduate student in the Schools of Law and Business
Administration, respectively,   Mr. Jim Graves, Esq., developed
the questionnaire used for this study  and also helped formulate
the conclusions cited in this report.  Ms. Laurie Peterson, a
graduate student from the School of Law, researched many of the
topics considered here. Mr.  Hal Chapel, a specialist in data
management and analysis,  directed the  gathering and analysis  of
the large amounts of data referred to  herein.

Mr. Harold Cahill, former Director of  the Environmental
Protection Agency Construction Grants  Program, encouraged  and
guided us in the study of grantee management practices.

Mr. David Welch, Contract Officer, and Mr. Walter Brodtman,
Western Regional Manager for EPA, patiently answered our
inquiries about EPA policies and guided us to other persons who
could provide specialized help.

Finally, we owe a large measure of gratitude to the grantees  and
consultants who anonymously contributed to this study through
their input of project data, ideas, and insights.

-------
                        EXECUTIVE SUMMARY


For many local government agencies the planning, design,
construction and operation of a wastewater treatment system
represents the most difficult public works program ever
attempted. Although some agencies have prior experience managing
complex and costly projects, many others lack the sophistication
needed to complete projects on time and within budget.

The purpose of this report is to identify contemporary grantee
Project Management techniques, critically analyze those
techniques which are weak or ineffective, identify techniques
which will improve grantee operations, and establish the basic
costs for grantee Project Management services.

The Construction Grants Program has undergone many changes
since its inception, and the program will continue to evolve in
response to the needs and available funding. But, every grantee,
consultant and grantor agency representative we contacted
believes there are specific reasons why the program is less
effective than it could be. We believe the following are some of
the most important:

     1. Grantees receiving support from one or more state and
        federal agencies are frequently ill-prepared to
        coordinate the different parties involved and their
        overlapping or contradictory requirements;

     2. Many consultants aggressively pursue the opportunity to
        plan, design and manage the construction of a project for
        a grantee, but at the same time explicitly disavow any
        responsibility to assist the grantee with cost or
        schedule control.

        Fearful of the liability associated with maintaining
        cost and schedule controls, some consultants use the NSPE
        Owner Designer Agreement [NSPE Document 1910-2] which
        states in part that:

            [The designer] shall not be responsible for the
            means, methods techniques, sequences or procedures of
            construction selected by the contractor(s) ... he
            shall not be responsible for the failure of the
            Contractors to perform the work in accordance with
            the Contract Documents.

     3. When grantees are negotiating for the provision of
        certain management-control services, including cost and
        schedule control, they frequently underrate their value,
        and may reduce or eliminate them in order to cut costs.

-------
One of our highest priorities in this report was  to help  put
these problems into a helpful perspective and to  present
specific, workable approaches to their resolution.

Regardless of the problems any one grantee  is facing, and  the
source of these problems, there are at least three basic  facts
common to all grantees. First, the grantee  bears  full
responsibility for the proper use of grant  funds  and effective
functioning of the wastewater system. Secondly, EPA funding is
limited and if changes in the project are to be grant-eligibile
EPA must approve them as the project progresses.  Finally,  even
relatively small projects involve complex financial and
contractual arrangements between contractors, consultants,
sources of finance and the grantee.

Based on our site-visits to grantees, responses we have
received to a detailed questionnaire distributed  to grantees, and
input from consultant, EPA and state personnel, we have
identified four "measures of grantee success" on  a particular
project:
                   ON A SUCCESSFUL PROJECT  ...

     1.  The design work was completed less  than 30 days late;

     2.  The construction phase was completed within the original
        schedule;

     3.  The actual cost of construction was less  than 5% higher
        than the contractor's original bid  amount; and

     4.  There were no construction contractor claims or when the
        claims were resolved the grantee received the bulk of the
        award.

Many supporters and critics of the EPA Program argue that larger
grantees are more "successful" than the smaller grantees, and
that EPA should take a more active role in  assisting grantees
with the management of grant funds. We agree that larger grantees
are more likely to be successful,  but do NOT believe that it is
necessary for EPA to provide greater direct assistance to any
grantee group.

We believe that a small number of proven management techniques
can be used by grantees of any size to significantly improve
their current operation and to LOWER their  current costs. These
techniques were deliberately selected to accomodate the de facto
realities confronting the grantee and to reduce project delays,
cost overruns and the likelihood of designer and  contractor
disputes. Summarizing:

                    A SUCCESSFUL GRANTEE ...

 I. Carefully considers the qualifications  and background of
     prospective designers.
                               ii

-------
        1.1.  Prior  to selecting a project designer,  consider each
             candidate's Errors and Ommissions insurance limits,
             record of delays and cost overrruns on previous
             projects, and any current claims or disputes with
             clients or others.

 II.  Closely  monitors the schedule and projected costs of the
      work during design and construction.

        II.2. Respond immediately to any problems which are
        revealed during the 50? design review;

        II.3. Possess a detailed schedule for all planning
        and design  activities;

        II.4. Review the schedule for the project design monthly
        or more frequently;

        II.5. Require progress reports on the project's design
        monthly or  more frequently, AND reports on the estimated
        cost  of the project on a regular basis;

        II.6. Enforce the design schedule by notice to the
        designer, and threaten to or actually withhold payment
        if the work does fall behind schedule;

        II.7. Possess a detailed schedule ( e.g., bar chart, CPM,
        etc.) for all construction activities;

        II.8. Conduct a review of the construction schedule monthly
        or more frequently;

        II.9. Verify the progress of the work with respect to the
        schedule monthly or more frequently;

        11.10. Update the construction schedule with each review;
        and

        11.11. Enforce the construction schedule by notice to the
        contractor, threatening or actually witholding payments
        if the construction work falls behind schedule.

 III. Resolves any  difficulties which may arise during design
       and construction as soon as possible.

        III.12. During construction, immediately resolve all change
        orders and disputes with the contractor

Relative to grantees using four or fewer of the recommended
techniques,  those using any nine to twelve of them experience:

       1. a 145 day reduction in construction delays;


                               iii

-------
       2. a 50% reduction  in  construction  cost  overruns;
       3. an 85% reduction  in  successful construction  contractor
           claims against  the  grantee; and

       4. a LOWER total cost  for administering  the work.

Despite the fact these recommendations appear to be  a
classical prescription for  good management, we  find  that
relatively few grantees actually implement them. The most widely
cited reason for not doing  so  is the apparent cost.  Some grantees
argue that close control of project costs and particularly
schedules is expensive, frequently unnecessary  and that professional
consultants cannot or will  not perform these services. Many
grantees also argue that deferring resolution of some  problems
may permit more fact finding,  reduce project costs and increase
the likelihood of grant eligibility. We strongly disagree.

We have found that grantees that work with qualified staff or
consultant personnel to actively develop and maintain  cost and
schedule controls,  and to solve problems as soon as  they arise,
have LOWER construction costs, costs for force  account and
consultant services, and fewer claims than grantees  that do  not
perform them. Although these techniques are costly,  by using them
the grantee's net costs are lowered through more efficient
project administration, fewer  construction contractor  claims, and
shorter construction times.

Relating these management techniques to the realities  of limited
EPA funding and the need to manage complex contractual
arrangements, professional  design and management consultants will
need to assume greater responsibility for the preparation,
receipt and evaluation of project cost estimates and schedules.
And, all of the participants in the project, including the
grantor and grantee, will need to develop a greater  appreciation
for the importance of timely decisions.

We emphasize the fact that  additional assistance from
EPA, the delegated State, or other grantor agencies will NOT
necessarily enable the grantee to more successfully manage its
projects.  Rather,  we recommend that small,  medium and
large size grantees consider using contract clauses which have
been proven effective on previous projects, and adopt specific
management techniques that will enable them to  complete their
projects in less time and for less money.

In conclusion,  the grantee  is fully responsible for the proper
use of all funds,  must seek concurrence of EPA  on major decisions
if grant-eligibility is to be assured,  and needs to pay
particular attention to the formulation and administration of its
contracts with others. Fortunately,  however,  there are some
relatively straightforward management techniques the grantee can
use to effectively  meet its needs.  And,  the implication of these
techniques is that there will be more work for  consultants and

                               iv

-------
better administered contracts for the contractor, but in turn
these groups will also need to assume greater responsibility for
cost and schedule control of their work and its effective
administration.

-------
                          TABLE OF CONTENTS

Introduction 	   1

Chapter 1   :  Recommendations  	   4

     1.0   Measures of Grantee Success 	   4

     2.0   Recommended Management Techniques   	   5

     2.1.   Consider the Prospective Designer's
           Previous Experience   	   5


     2.2   Require Updated Schedules ..... 	   6

     2.3   Immediate Resolution of Problems  	   8

     3.0   Cost of Recommended Services	   8

     4.0   Conclusions 	   9

Chapter 2   :  Contemporary Approaches to Project Management     10

     1.0   Introduction	10

     2.0   Alternate Approaches to Project Management  ....  11

     2.1   The Traditional Approach	11

     2.2   Turnkey Project Management  	  13

     2.3   Construction Management 	  14

     2.4   Special Consultants   	  17

     3.0   Summary	18

     4.0   References  	  .....  20

Chapter 3   :   Professional Liability   	  22

     1 .0   Introduction	22

     2.0   Establishing Liability  	  23

     3.0   Liability According to the Contract   	  24

     3.1   Immediate Resolution of Design Problems and Changes
           or Disputes during Construction 	  24

     3.2   Schedule Control During Design  	  25

     3.3   Schedule Control During Construction  	  27

-------
     4.0  Conclusion	30
Chapter 4  :   The Contemporary Grantee 	  .....  31
     1.0  Introduction   	31
     2.0  Grantee Characteristics:  A Function of Population   32
     2.1  Small  Grantees	32
     2.2  Mid-sized Grantees 	  33
     2.3  Large  Grantees   	34
     2.4  Generalizations Pertinent to all Grantees  ....  34
     3.0  Twelve Specific Techniques for Effective Management 35
     3.1  Overall Effectiveness of the Techniques  	  36
     3.2  Overall Effectiveness of Techniques Used During
          Design and Construction  	  37
     3.3  Use of Techniques and Construction Administration
          Costs	38
     3.4  Use of Techniques and Construction Administration
          Costs  by Project Cost	39
     3.5  Use of Techniques and.Cost of Outside Construction
          Management Services by Project Cost  	  40
     3.6  Use of Techniques and Cost of Outside Construction
          Management Services by Grantee Population  ....  41
     3.7  Use of Techniques and Total Construction Management
          Costs  by Grantee Population	41
     3.8  Use of the Techniques and Cost of Grantee Force
          Account Services for Construction Management
          by Grantee Population  	  42
     3.9  Use of Techniques and Cost of Grantee Force Account
          Services for Construction Management by Project
          Cost	43
    3.10  Analysis of the Specific Tactics	44
    3.11  Qualifications of Design Consultants 	  44
    3.12  Development and Enforcement of a Master Schedule
          for the Design Phase	44
    3.13  Review of the Design Schedule on a Monthly or More
          Frequent Basis   	  45

-------
    3.14  Identification and Correction of Serious Problems at
          the 50% Design Review	45

    3.15  Development and Enforcement of a Master Schedule for
          the Construction Phase 	  46

    3.16  Review of the Construction Schedule on a Monthly or
          More Frequent Basis	47

    3.17  Updating of the Construction Schedule to Reflect the
          Current Progress of the Work   	47

    3.18  Resolution of Contract Changes or Disputes With the
          Contractor as soon as They Occur	48

    4.0   Conclusion   	48

Appendix	51

    1.  Development of the Questionnaire   	51

    2.  Question Format and Structure  	  52

-------
                          LIST OF TABLES
Table no.      Title                                  Page
  1             Delay in Completing the Design
               Phase and the Number of Techniques
               Used	   37

  2             Number of Techniques Used During
               Design and the Likelihood of Claims
               in the Design Phase	37

  3             Number of Techniques and Delays in
               Completing Construction  	 37

  4             Number of Techniques Used and Con-
               struction Cost Overruns as a Percentage
               of the Original Contractor's Bid .... 37

  5             Number of Techniques Used and the
               Likelihood that the Grantee Will Lose
               a Claim from the Construction Phase   .   37

  6             Number of Techniques Used and the Total
               Cost of Administering Construction as
               a Percentage of the Cost of Construction 38

  7             Number of Techniques Used and the Total
               Cost of Administering Construction as a
               Percentage of the Cost of Construction   38

  8             Number of Techniques Used and Cost of
               Grantee Force Account Construction Manage-
               ment Services as a Percentage of the
               Cost of Construction	39

  9             Number of Techniques Used and Total Cost
               of Administering Construction as a Percentage
               of the Cost of Construction	39

 10             Number of Techniques Used and Cost of
               Outside Firms Used to Manage Construction
               as a Percentage of the Cost of
               Construction  	  40

 11             Number of Techniques Used and Cost
               of Outside Construction Management
               Services by Grantee Population ....   41

 12             Number of Techniques Used and Total
               Cost of Administering Construction
               as a Percentage of the Cost of

-------
              Construction
13            Number of Techniques Used and Cost
              of Grantee Force Account Construction
              Management Services as a Percentage
              of the Cost of Construction .....     43

14            Number of Techniques Used and Cost
              of Grantee Force Account Construction
              Management Services as a Percentage
              of the Cost of Construction .....     43

15            Number of Prequalification Criteria
              Used and Cost Overruns as a Percentage
              of the Contractor's Original Bid  .  .     44

16            Frequency of Design Schedule Review
              and Delay in Completing Design Work  .     45

17            Outcome of 50% Design Review and
              Construction Cost Overruns as a
              Percentage of Construction Cost ...     46

18            Use and Enforcement of a Master
              Construction Schedule and Delay in
              Completing Construction  ......      46

19            Frequency of Construction Schedule
              Reviews and Delays in Completing
              Construction  ...........       47

20            Frequency of Construction Schedule
              Reviews and Percentage of Projects
              Completed on Time  .........      47

21            Updating of Construction Schedule
              Versus Cost Overruns as a Percentage
              of the Cost of Construction .....     48

-------
                         INTRODUCTION

The Environmental Protection Agency assigns complete responsibility
for the planning, design, and construction of wastewater
facilities to the local grantee.  The management of these
projects from plannning through construction, i.e., Project
Management, is an immense challenge for even the largest and most
sophisticated grantees.  And, each grantee's relative success
depends on a number of factors, from political support for the
facility to the availability of qualified grantee and consultant
personnel.

The purpose of this report is to identify contemporary grantee
Project Management techniques, critically analyze those
techniques which are weak or ineffective, identify techniques
which will improve grantee operations, and establish the basic
costs for grantee Project Management services.

To develop an accurate picture of grantee management practices we
reviewed the available literature on grants programs and Project
Management techniques, conducted a survey of representative
grantees, and had numerous discussions with EPA consultant and
grantee representatives.  Perhaps surprisingly, despite their
diversity, all of these sources yielded the same basic
conclusions.  Summarizing, some of the most cost-effective and
efficient management techniques the grantee may exercise are
selection of qualified consultants, development and maintenance
of schedules for the design and construction work, and prompt
resolution of problems and disputes.

Despite the fact that careful selection of consultants, close
schedule control and a prompt response to problems appears like a
classical prescription for good management, relatively few of the
grantees we met actually perform these functions. In particular,
few grantees actively monitor project schedules or work to
resolve disputes as soon as they arise. The most widely cited
reason for not doing so is the apparent cost.  Grantees argue
that close control of project schedules is costly, frequently
unnecessary and that deferring resolution of some problems may
permit more fact finding, reduce costs, and increase the
likelihood of grant eligibility.  We have reached the opposite
conclusion.

We have found that grantees who work with qualified consultants
to actively develop and maintain comprehensive schedules during
design and construction, and who resolve disputes promptly, have
LOWER construction costs, costs for force account and consultant
services, and fewer claims than grantees who do not perform these
services.  Although these techniques are costly, by using them
the grantee's net costs are lowered because of more efficient
project administration, fewer construction contractor claims, and
shorter construction schedules.

If the number of grantees involved in audit disputes, alleged
mismanagement and construction contractor claims continues to

-------
increase, we will probably witness a call from many public and
private organizations for greater EPA management assistance to
local grantees.  No doubt, one argument which will become
fashionable is that since EPA provided a large amount of the
money originally spent by the grantee, EPA should share in the
burden of managing the project and disputes resulting from the
work.  And, there will also be renewed calls for grantee use of
"advanced" management techniques such as turnkey construction,
construction management,  etc.

In Chapter 2, Contemporary Approaches fco Project Management, we
show that any one of the  approaches the grantee may use to manage
his project has specific limitations, but also that public and
private owners are increasingly recognizing that the overall
approach used, e.g., construction management versus greater EPA
involvement, is much less important than the management services
performed by the grantee.

A topic of growing concern to grantor and grantee agencies is the
legal obligation of the grantee's professional consultants to
compensate the grantee for damages.  For example, when higher
costs, operations breakdowns and schedule delays occur on a
particular project,  an increasing number of grantees are turning
to their professional consultants to share in the associated
costs.  In large part because there are few precedent setting
cases where the consultant was held liable for mismanagement,
there are few specific guidelines for evaluating the Project
Management consultant's liability.  But, referring to established
legal principles and those cases we do have, in Chapter 3,
Professional Liability, we show that consultants are increasingly
and deliberately disclaiming responsibility for management
functions.  And, we also review those circumstances where
liability can be assigned to consultants.

To identify the management techniques which "successful" grantees
found most helpful,  and those which were counterproductive, we
met personally with the senior officials of over twenty grantee
agencies and their consultants.  We inquired about the overall
grantee organizational structure,  grantee policies for selecting
and using consultants, particular management problems grantees
were experiencing and the administrative costs normally incurred.

Supplementing the personal visits, we also surveyed a number of
grantees to identify elements of their Project Management effort,
and we analyzed the data  collected.  In Chapter 4, The
Contemporary Grantee, we  reviewed two composite pictures of the
Construction Grants Program grantees based upon this data.
First, a picture is developed of the grantees according to the
population served and, second, with respect to the management
techniques that they use.

As a "conclusion" to this report,  we developed a series of
specific recommendations which grantees may implement to
improve the effectiveness of their grant management effort.  In
developing our recommendations we emphasize specific techniques

-------
with established records of cost effectiveness, and which would
not require changes in the EPA regulations.  In conclusion, we
believe that if grantees adopt the recommended management
practices, the costs and time associated with their projects will
be significantly decreased.  Our recommendations are presented in
Chapter 1, Recommendations.

-------
                            CHAPTER 1


                         RECOMMENDATIONS

1.   Measures of Grantee Success;

    Two of our most important objectives in this work were to
    identify specific Project Management methods which would
    improve the efficiency of grant funded operations, i.e., make
    the grantee more "successful," and to establish the costs of
    both the contemporary and proposed management methods.

    As we studied various management techniques and their
    associated results,  we adopted four measures of a "successful"
    grant funded project:

     1.1  The design work was. completed less than 30. davs
          late.

          Timely completion of the design may  permit the grantee
          to schedule construction bids for a  time when lower
          bids are more likely,  allow  the grantee to estimate
          more accurately final  costs  and effective operations
          dates for the completed facility.

          The design work was completed less than 30 days late on
          approximately three-fourths  of the projects we
          investigated.

      1.2 Tke cons true tlpu phase  Has. completed on schedule.
          Completion of construction early or  "on schedule," i.e.
          within the time originally specified in the grantee-
          contractor contract,  permits grantees to minimize
          consultant and force-account costs associated with the
          construction phase,  and allows the grantee to meet its
          own commitments for system operation.

          Approximately one-fourth of  the projects we
          investigated were completed  within the time originally
          agreed upon.

      1.3 Ulg actual cost p£ construction was  less than 51
           higher than, the contractor1 s original bid.

          Changes in the original construction contract to
          accomodate changes in  the original work or other
          conditions are virtually inevitable  during
          construction.   The most common "changes" are grantee
          recognition of differing site conditions,  but may
          include clarification  of the contract documents, small
          additions to the work  and approval of substitutes  to
          items specified.

-------
          Most changes result in an increased cost of
          construction, and a 5% increase in total costs is
          considered typical.  The actual cost of construction
          was less than 5% higher than the contractor's original
          bid for approximately three-fourths of the projects we
          investigated.

      1.4 Jhere were, no construction contractor claims for a
          particular project pr claims ibli did pcfiur resulted
          iD £h_e_ grantee reselling tfce bulk pjl th_e_ award.

          Construction contractor claims, i.e., unresolved
          disputes between the grantee and construction
          contractor, are increasingly common and due not only to
          grantee actions but also to increasingly competitive
          bidding for projects, and a greater contractor "claims
          consciousness."

          However, there is much that the grantee can do to
          minimize the likelihood of claims, their consequent
          costs (as in item 1.3 above) and to increase the
          probability of receiving the bulk of the award if the
          dispute does go to arbitration or litigation.

          For approximately 80% of the projects investigated
          there were no claims or the grantee received the bulk
          of the award.


2.   Recommended Management Techniques

          Based on our meetings with numerous grantees, a review
          of the literature and data developed through a survey
          of grantees, we have established three basic management
          techniques which significantly increase a grantee's
          likelihood of "success1" as defined by the above 4
          criteria: (1) carefully consider the qualifications and
          background of prospective project designers; (2)
          closely monitor the schedule of the work during design
          and construction; and (3) resolve any difficulties
          which may arise during design and construction as soon
          as possible.

      2.1 Consider tfce. prospective designer's previous
          experience.

          In addition to evaluating a prospective designer's
          technical ability and experience with a particular type of
          project, we believe that the grantee should consider
          the limits on his Errors and Omissions (E/0) insurance,
          his prior record of delays and cost over-runs on
          similar projects, and any current claims or disputes
          that he may have with clients or contractors.  We
          consider that a grantee used this technique

-------
    successfully if he considered any two of these
    criteria.

    Although we recommend that grantees consider a
    prospective consultant's E/0 limits, prior "track
    record" and relationships with others, we also
    recognize that this information is generally not
    released by consultants for fear of its being
    misconstrued or abused by competitors.  We also
    recognize that the consultant's E/0 insurance coverage,
    even though high, can be consumed by a small number of
    prior disputes which will then leave the grantee
    without compensation.  But, these problems
    notwithstanding,  if the grantee can assure the
    consultant that the data provided will remain
    confidential and will not be considered seriously, we
    believe most consultants will comply with the grantee's
    request.

    The professional consultant's response to inquiries
    about his background in these areas is not necessarily
    indicative of what the grantee will experience with the
    same personnel on his project, but using this
    information the grantee may be able to make more
    informed selection between consultants.  And, making an
    informed selection is particularly important since
    beyond his voluntary contribution it will be extremely
    difficult for the grantee to compel the project
    designer or construction manager to make a financial
    contribution towards correcting an improperly operating
    plant or resolving a construction contractor claim.

    Contemporary procedures for holding the professional
    legally liable are rigorous, and pursuing the recover
    of cost through legal maneuvers is time consuming and
    costly.  Therefore,  it is to the grantee's advantage to
    select consultants with an established record of timely
    completion and workable relationships with all of the
    parties involved.

2.2 Schedules

    There are at least four basic elements to the effective
    use of project schedules: (a) possession of a Master
    schedule depicting the major events, duration and
    inter-relationships for the duration of the work; (b) a
    periodic review and/or verification of the schedule
    whereby the actual progress of the work is compared with
    that projected; (c)  the preparation of progress reports
    and/or an updated schedule through which the grantee,
    designer and/or contractor jointly agree on the work
    done to date and the projected effect on subsequent
    operations; and (d)  the possession of appropriate
    enforcement mechanisms.

-------
The possession and use of a meaningful schedule for the
planning, design and construction phases is valuable for
several reasons.  First,  the exercise of constructing a
meaningful schedule for the work disciplines the
persons preparing it to plan the work, and consider
those items which may disrupt it.  Secondly, once
prepared and agreed upon by the grantee, the schedule
can serve as an excellent basis for discussing and
recording the effect of changes in the work, and
disruptive influences on the overall schedule.

For the purposes of our Recommendations we have
represented the schedule of the project's design and
construction work by nine separate management
techniques:

  1.  The grantee's possession of a detailed schedule
      of the work for the design phase;

  2.  Design schedule reviews monthly or more often;

  3.  Design progress reports monthly or more often;

  4.  Enforcement of the design schedule by notice to
      the designer, or threatened or actual withholding of
      payments  if work falls behind schedule;

  5.  The grantee's possession of a detailed
      construction schedule;

  6.  Construction schedule reviews monthly or more
      often;

  7.  Verification of the schedule and work-in-progress
      monthly or more often;

  8.  Updating  of the construction schedule with each
      review;

  9.  Enforcement  of  the  construction  schedule  by
      notice  to  the contractor or the  threatened  or
      actual  with-holding of payment   if   construction
      falls behind schedule.

 There are numerous methods for representing project
schedules, and  any one or combination may be used.  The
critical value  of this step is to be able to understand
and respond to  developments in each phase or part of
the project, and schedules are particularly valuable
for this purpose.

We  emphasize that adoption of advance schedule
techniques, such as CPM networks, is not in itself a
guarantee of good project schedule controls, but rather
the most important consideration to exercise when

-------
          selecting and specifying scheduling techniques is  that
          the  schedule as developed be accepted,  understood and
          used by all the persons associated with the project.
          For example, design phase activities may be
          meaningfully represented by bar charts, comparisons of
          projected versus expended man-hours for particular
          tasks,  or other simple measures.  Similarly, many
          simple construction operations may be represented by
          Gantt bar charts,  line-of-balance diagrams, etc.

      2.3 Immediate resolution of problems.

          Many of the problems which arise during the design or
          construction work are complex and require a cooperative
          effort between the grantee, consultants and contractor
          to reach an equitable solution.  However,  in part
          because these problems are so complex and a workable
          approach to them is not always apparent, many of the
          grantees with which we have met defer the resolution of
          problems until a more "convenient" time, usually at the
          end of the respective design or construction phase.

          Unfortunately, however,  in many cases this deferral may
          be accompanied by  a loss of productivity,  misplacement
          or destruction of  the pertinent records, further
          deterioration of the grantee-consultant relationship,
          or other problems.   In conclusion, then, we recommend
          that as a minimum  the grantee identify and immediately
          resolve serious problems revealed at the routine 50%
          design review; work for immediate resolution of
          contract changes or disputes with the contractor.

3.  Cost of Recommended Services

    In our discussions with  grantees, consultants and EPA
    personnel,  virtually all  associated increased force account
    and consultant costs with the previously recommended
    management techniques.

    In fact,  the grantee using force account or outside
    consultants for the recommended techniques reported lower
    administration costs than grantees who did not.   For example,
    working with  our sample  of grantees,  those using up to four
    techniques spent approximately 5% of the construction cost on
    all administrative services,  whereas those performing nine to
    twelve services spent approximately 4.4? of the  construction
    cost on administrative services (more detailed summaries of
    these statistics are presented later in this report).
    Virtually all of the data we have compiled supports the
    conclusion that use of the recommended services  costs no more
    than contemporary grantee management techniques,  and will
    probably  result in lower  administrative costs, regardless of
    grantee or project size  or type.

    The fact that use of the  recommend services may  result in

-------
    lower  administrative  costs for the grantee is also
    intuitively  clear.   First,  for example,  the explicit purpose
    of the scheduling procedures recommended is to facilitate
    earlier completion of the work,  with consequently lower
    administrative costs.   And,  in fact,  grantees using these
    techniques do complete the work sooner with both lower
    administrative and contractor costs.

    Second,  careful consideration of the designer's previous
    experience and prompt resolution of all problems and disputes
    before the design progresses or is completed may minimize
    potential  design-related problems, and facilitate maintenance
    of workable  relationships.

    Summarizing  some of the discussion presented later in this
    report,  the  effect of using the recommended techniques on
    project costs and delays may be summarized as follows:
                      Total                         Average
                      Administrative     Average    Cost of
    Number of          Costs as a         Delay in   Construction
    Recommended        Percentage of      Completion Over Contractor's
    Techniques Used   Construction Costs (davs)     Original 3J.d
        0-4               5.0%             243          5.4%

        5-8               4.6?             197          4.3?

        9-12              4.4?              97          2.7?

4.   Conclusion

    We have considered recommending greater EPA assistance to
    individual grantees,  more (and less) grantee commitment of
    grant funds for management services, and numerous other
    techniques to enhance the ability of individual grantees to
    manage properly their projects.  But, based on all of the
    information available to us the most effective management
    techniques the grantee can use are those outlined above, and
    are readily available through professional consultants for
    those grantees who do not already have the capability to
    provide them.  And, futhermore, use of these recommended
    services is not expected to result in higher administrative
    cost,  and requires little assistance from EPA or other
    agencies to implement.

-------
                          Chapter 2

        CONTEMPORARY APPROACHES 10 PROJECT MANAGEMENT

Introduction
For many grantees the planning, design and construction of a
wastewater system represents the most difficult work ever
attempted.  Although some have prior experience with complex
and costly projects, many others lack the technical and
managerial sophistication to complete the project on time and
within budget.

If the number of grantees involved in audit disputes, alleged
mismanagement and construction contractor claims continues to
increase,  we will probably witness a call from many public
and private organizations for greater EPA management
assistance to local grantees.  One argument which may become
fashionable is that since EPA provided a large amount of the
money originally spent by the grantee, EPA should share in
the burden of disputes resulting from the work.  And, there
will also be renewed calls for grantee use of "advanced"
management techniques such as turnkey construction,
construction management, etc.

As the authors of this report,  we believe the number of
grantees involved in disputes will increase rapidly in the
next few years,  but we also believe that additional EPA
involvement in the grantee's own project management effort,
or the adoption of a turnkey or construction management
approach will not necessarily result in better managed
projects with fewer disputes.

In this chapter, we explicitly show that any one of the
overall approaches the grantee may use to manage its project
has specific limitations, but also that public and private
owners are increasingly recognizing that the overall approach
used, e.g., construction management versus use of the
original project designer, is much less important than the
management services performed by the grantee.

Broadly, the technical services which must be performed to
complete a wastewater facility include evaluation of
alternate systems, facility planning and design, preparation
of contract documents and monitoring of the construction
work.  Professional management services performed to direct
and monitor the work include development of long-term cost
and schedule goals,  monitoring of the project-specific costs
and schedules, and assistance with resolution of disputes.
In conclusion, we encourage the grantee to emphasize
performance of these services and not necessarily adopt any
one of the standard management approaches.
                           10

-------
    A number of terms have been used to describe the management
    systems grantees use to plan, implement and control their
    work.  Program Management (1) refers to the grantee's
    management of the entire wastewater system, Project
    Management (2) refers to the management of all work related
    to a specific facility, and Construction Management (3) to
    management of the construction phase operations on one or
    more projects.  In this chapter we review the development of
    the principle management approaches used in Project
    Management and the respective advantages and limitations.

2.0 Alternate Approaches to Project Management

    Until recently, many grantees implicitly assumed that with
    their use of a standard Owner-Professional Consultant
    contract agreement that the consultant would take charge of
    the project from beginning to end; that is, he would act as a
    Project Manager and perform all of the necessary technical
    and management functions.  (4, 5)  However, a large number of
    new priorities and requirements are reshaping this
    traditional Owner-Consultant relationship, and many grantees
    may need to revise their expectations.

    Alternate approaches to Project Management began to develop
    during the Second World War when owners became increasingly
    concerned with achieving the lowest cost of construction in
    the shortest period of time.  In the late 1940's and early
    1950's, Turnkey contracts, where a single contractor provides
    design and construction services, was a popular approach.  (6)
    In principle, with the turnkey contract approach the
    consultant provides all of the necessary planning, design and
    construction services necessary to provide a facility with
    the desired performance.

    In the late 1960's and early 1970's, the use of a
    Construction Management firm in lieu of the original designer
    during construction became popular among owners in their
    attempt to reduce costs and construction time by more
    carefully controlling project schedules and cost.  (1, 8)
    And, more recently, as owners and contractors have become
    disillusioned with the Construction Management approach, more
    effort has been placed on hiring specialized consultants to
    perform particular functions and to supplement the original
    project designers. (9)

2.1 The Traditional Approach

    The classic approach to grant funded work is for the grantee
    to act as Program and Project Manager with substantial
    assistance from private, professional consultants.  Typically
    the grantee will develop and maintain a master schedule and
    budget for completing the entire system, but contract with
    professional consultants for planning, design and certain
    construction services.  Thus, the grantee retains nominal


                               11

-------
control over the direction and progress of the work, but does
not commit its personnel resources to a short term project.

Historically, the professional architectural and engineering
societies representing consultants have encouraged owners to
rely on private consultants and to use this "traditional"
approach.  For example, at one time the standard Owner-
Architect agreements defined the Architect's duties quite
broadly from preparation of preliminary studies to
supervision of the work.  (4)  And, according to the
commentary accompanying a National Society of Professional
Engineers (NSPE) Owner-Project Manager agreement,  the Project
Manager "takes charge" of the project:

     "... the Project Manager ... in effect,  takes
     charge of the Project from beginning to end in order to
     provide special expertise and relieve the Owner of
     duties and responsibilities which the Owner is neither
     qualified to undertake nor for which he will have a
     continuing need."  (5)

Proponents of this traditional approach argue that use of a
single professional consulting firm representing the grantee
from planning through construction simplifies the grantee's
own management responsibilities and is cost-efficient.  The
grantee can establish and interact with a single contact
throughout the project's life and thus need not take an
active part in the Project Management.  Also,  if the original
professional design consultant is involved during the
construction phase,  questions about the work may be resolved
quickly and directly.

The advantages notwithstanding,  use of this approach has been
declining recently.   Some consultants, fearful of assuming
unwanted liability for activities beyond their control, are
explicitly disavowing any responsibility for cost or
schedules, and also limit their responsibility for inspection
of the work.  (10)  And, in a related development, since few
consultants have personnel familiar with advanced management
techniques such as cost and schedule control,  they are
drawing a sharper distinction between the technical and
management services provided and are excluding those they are
not prepared to offer.  The net result is that in order to
satisfy their own management needs grantees are either
expanding their own staff or contracting for specialized
management services from other consultants.  (11)

In conclusion,  for many years the traditional arrangement
between the grantee and consultant resulted in the consultant
providing the full range of planning, design and construction
oversight services necessary for Project Management.  More
recently, however, professional consultants have narrowed the
range of services offered grantees and are explicitly
excluding responsibility for project costs, schedule, project
inspection and certain other functions.  And,  whereas in the
                           12

-------
    past grantees had given only limited attention to development
    and maintenance of detailed cost, schedule and inspection
    records, they are now developing these in detail in order to
    minimize audit related and construction contractor disputes.

2.2 Turnkey Project Management

    During the Second World War and early post-war industrial
    development, owners explored a number of different techniques
    to speed planning, design and construction processes.  Owners
    were concerned with controlling costs and efficient use of
    their own staff, but there was also an overriding emphasis on
    completion of the facility as soon as possible.  The Turnkey
    approach, where the owner contracts with a single contractor
    to provide a complete facility ready for operation, was
    particularly popular during this period.  (6)  Variations and
    other names applied to it include "single-source, design-
    construct responsibility" and the "design-construct"
    approach.  (12)                             " 	*
    The fact that the contractor may overlap planning, design and
    construction operations and the responsibility for the
    facility performance can be clearly focused are widely cited
    as the principle advantages of this approach.  It has been
    considered for wastewater facilities, and its advocates argue
    owners (i.e., grantees) will be able to save time, reduce
    escalating costs and focus responsibility for operational
    problems on one single firm.  (12)

    The apparent advantages notwithstanding, the complex dynamics
    of simultaneous design and construction may result in
    unexpected costs for the owner.  Abnormal weather, site
    conditions, unexpected problems with regulatory agencies and
    other unforeseen events over the several year life of a
    typical project can make it extremely difficult to plan and
    forecast time and costs associated with the future work, and
    the consultant will want to be reimbursed for these
    unexpected problems.  (7, 8)

    For unsophisticated owners, or those expecting to use the
    Turnkey approach to minimize their responsibilities, the
    problems associated with the assumption of liability and
    guarantees of performance by the consultant may pose the most
    serious obstacles.  In effect, the grantee may want an
    explicit guarantee the facility will meet established
    performance standards for water quality, cost of operation,
    etc., and for the consultant to assume responsibility for
    meeting these standards.  In fact, however, consultants
    cannot afford the open-ended costs such unilateral guarantees
    impose, and insurance which may support performance
    warrantees is usually quite costly and limited in coverage. (6)

    In summary, the Turnkey method is appealing because it focuses
    responsibility on a single contractor and the overall time


                               13

-------
    required to complete a facility may be shortened because design
    and construction can proceed simultaneously.  But,  in actual
    practice this method will be used even less frequently in the
    future due to the fact owners have not been able to adequately
    control and predict costs,  and Turnkey consultants are sharply
    restricting their assumption of liability for the facility's
    performance.


2.3 Construction  Management

    The 1950's and early 1960's was an exciting period for
    owners, contractors and consultants associated with complex
    capital projects.  The magnitude and number of industrial,
    commercial and defense related projects started after the
    Second World  War continued to grow rapidly, the impact of
    private financing and inflated costs was considerably
    greater than  it had been earlier,  and new tools for control
    and management of these projects were being developed.  (6)
    As owners placed even greater emphasis on timely completion
    of their projects,  attention was also focused on scheduling
    tools and techniques.  Project personnel tracked estimated
    and actual milestone dates and some developed elaborate Gantt
    "bar charts"  for use in project control and planning.

    But, the most important advances in project scheduling could
    be attributed to the development of the so-called Critical
    Path Method "CPM" network scheduling techniques by Hayward
    and Robinson  at DuPont, and PERT for the Navy during the late
    1950's.  (13, 14)  With the subsequent development and
    application of these networking techniques, project personnel
    were able to  "track" thousands of separate activities and
    evaluate the  impact of different events on the overall
    project schedule.  During the 1960's, academic scholars and
    practitioners in the field further developed and refined the
    use of CPM, PERT and related techniques.  And, a number of
    consulting organizations were formed to offer scheduling
    services,  and computer-based "scheduling packages" were
    developed for use by several government agencies. (14)

    As the scope  and magnitude of industrial public works
    projects continued to expand, besides employing detailed
    project schedules,  owners also attempted to minimize the
    problems associated with the use of the traditional,  lump-sum
    construction  contracts.  Some public owners began "packaging"
    their construction contracts so as to start foundation
    construction, for example,  while the balance of design was
    completed, and also adopted construction contract clauses
    which would minimize disputes and ease the burden of project
    administration during construction.  (10)

    Late in the 1960's, the federal General Services
    Administration (GSA) recognized the potential advantages
    associated with these advanced scheduling techniques and
    multiple bid  packages, and promoted their use with greater


                               14

-------
fanfare as "Construction Management."  (15)  Specifically,
GSA defined Construction Management (CM) as:

    ... a prime contractor (professional services) who will
    work with PBS (federal Public Building Service) and the
    architect to formulate the project budget, furnish the
    architect with information on construction technology and
    market conditions to insure their building design stays
    within budget, manage the procurement effort, supervise
    the construction of the building and provide, if desired,
    a wide range of other services . . . (15)


In summary, with the GSA approach the CM provides cost and
schedule input to the project designer during the planning
and design phases, assists the owner with development and
award of multiple construction contracts to start
construction while the final design is completed, and then
assists the owner (e.g., GSA) with all management functions
during the construction phase.  (15)  Unfortunately, GSA was
not able to capitalize on CM as much as expected, apparently
due to the CM's limited authority to enforce schedule and
coordination requirements (7), and stopped using CM in 1980.
(16)

However, as GSA's use of CM was declining, some grantees and
delegated states became increasingly interested in a slightly
different approach.  In 1977, the state of California issued
its Managing Construction of Claim Water Grant Projects (11)
recommendations on the use of CM and actively encouraged
grantees to employ a CM other than the original designer to
administer the work, exercise cost and schedule control and
perform other duties during the construction phase.  In 1981,
the state of Washington Department of Ecology issued its own
guidelines.  (17)

With the approach promoted by California, Washington and
others, (8) the CM assists the grantee with development of an
overall management plan, development and maintenance of a
comprehensive cost and schedule control system, and
administration of the work.  (18)  But, in contrast to GSA,
the CM does not help award "phased" of fast-track
construction contracts.

Although inconclusive, a small amount of data gathered by the
state of California since issuance of its 1977 guidelines
tentatively indicates that active use of a CM would result in
shorter completion times, fewer change orders reduced
increases in construction costs,  but slightly higher
administrative costs.  Similar conclusions, but without
supporting quantitative data, have been widely reported by
others for conventional commercial and public construction
projects.  But,  despite active encouragement, relatively few
grantees have used CMs and most have apparently chosen to
continue use of the original project designer in a limited
                           15

-------
role during construction.

No doubt, there are many reasons why the concept of CM has
not "caught on" despite its apparent advantages, but we
believe that the principal obstacles are the lack of
conclusive quantitative evidence that its use is cost-
effective, an apparent shortage of persons capable of and
willing to assume active responsibility for cost and schedule
control activities, and uncertainty about the liability of
the CM for its own and others actions.  (6, 10, 19)

Most people (and even delegated state agencies disbursing
funds), and particularly cash-short grantees,  are not
motivated to use a "new" service such as CM unless there are
known cost-effective benefits.  Interestingly,  despite the
widespread publicity and the use CM has enjoyed for over a
decade, extraordinarily little quantitative data capable of
winning the support of a skeptical agency Board of Directors
or delegated-state contract review staff has been developed.
In fact,  all the grantees we have met and who are using CM
services strongly assert that it is cost-effective, but also
admit they lack objective data supporting their contentions.

Perhaps the most cost-effective CM service is active cost and
schedule control.  By using detailed schedule and cost
projections when planning the work, and through maintenance
of comprehensive records as it takes place, the grantee will
be able to anticipate his financial needs and have a time-
record to use in discussion with the contractor and designer.
But,  until relatively recently few consulting engineers (or
contractors) were familiar with advanced scheduling
techniques,  including CPM networks, and thus placed little
emphasis on their development and maintenance.   This limited
use notwithstanding, the number of persons using scheduling
techniques is growing rapidly and the use of an appropriate
scheduling technique by the contractor, professional
consultant,  or both, will probably become commonplace within
the next few years.  (14)

Advanced scheduling techniques are now included in
contemporary undergraduate civil engineering curricula,
contractors and consultants are finding them an invaluable
tool for presenting and resolving construction contract
claims, and many large civil engineering firms are developing
specialists trained in cost and schedule administration as an
essential element of their effort to manage large,  multi-
billion dollar projects.

Finally,  the whole issue of professional liability has had a
dramatic effect on the evolution of CM services.  Since the
mid 1960's,  consulting engineers have become increasingly
fearful of assuming responsibility for the construction
contractor's work and associated liability.  So, for example,
many consultants actively monitoring the construction have
carefully avoided responsibility for safety-related programs
                           16

-------
    and defects in the completed work (obvious sources of
    potential liability),  but also for tracking the contractor's
    sequence and schedule  of work activities.   In effect, fearful
    of the assessment of unwanted liability some consultants
    offering construction  monitoring or oversight services also
    explicitly exclude certain services which  would be
    particularly valuable  to the grantee.  (20)

    Because of the whole issue of CM liability it is still
    undergoing a rapid evolution; it is impossible to predict
    precisely what effect  it will have on the  CM services
    offered.  However, at  least for the next few years if a
    grantee wants certain  allegedly "high-risk" services from a
    consultant, including  schedule control, then these should be
    explicitly stated in the grantee-CM contract.

    To summarize, the term Construction Manager or CM typically
    represents the professional consultant providing specialized
    services encompassing  development of a management plan,
    active cost and scheduling control, assistance with the
    development of the contract documents and  the negotiation of
    changes during construction.  And, most of these services are
    performed during the construction phase.  Although widely
    publicized and recognized as "valuable", few public owners
    are actively using CM, perhaps due to the  uncertainty of
    benefits.  But, as the benefits associated with good cost and
    schedule administration and other CM services become more
    widely recognized, successful grantees document the "true-
    cost" of these services and the people able to provide these
    services increase in number, we foresee that grantee use of
    CM or similar approaches will expand rapidly.

2.3 Special Consultants

    Independently of any state or federal promotion of CM or
    related services, in the late 1970's and early 1980's, many
    grantees began to realize that strong cost and schedule
    control and vigorous contract administration could result in
    substantial benefits ranging from fewer contractor claims to
    lower administrative costs.  In fact, most of the grantees we
    contacted began placing heavy emphasis on these services
    after battling complex construction contractor claims and
    seeking additional contract time from grantor agencies.  In
    both of these situations the grantees found excellent project
    records and comprehensive cost and schedule projections were
    essential for defense of their position.  (21)

    Also, the net result of the recent grantee interest in
    advanced management techniques has not been the standard use
    of CM, per se, but another type of special consultant.
    Whereas with the CM approach as it was traditionally promoted
    the CM would perform all of the construction inspection,
    contract administration and scheduling functions and the
    project designer's role would be limited to submittal review
    and some interpretation of the contract documents, with the


                               17

-------
    "special consultant" approach the original project designer
    continues to assist the grantee with the development and
    award of construction contract packages, inspection of the
    work, submittal review and design interpretations; but, the
    usually separate,  independent special consultant's role is
    limited to cost and schedule administration, negotiation of
    change orders and maintenance of project records.

    With this approach the grantee retains the original designer
    as an active participant during the construction, but is also
    able to supplement the designer's special expertise and
    project familiarity with independent personnel specifically
    contracted to provide cost and schedule control,
    documentation services and change order administration.
    Advantages of this approach include the grantee's ability to
    employ a separate organization with particular strengths in
    facility design and management,  respectively.  Conflicts of
    interest which may occur if the original designer oversees
    implementation of his own design during the construction
    phase are minimized,  and the special consultant is explicitly
    agreeing to provide particular services which designers have
    more recently explicitly excluded.

    The principal disadvantages associated with the use of special
    consultants are that they will increase the grantee's own
    administrative effort due to the employment of additional
    consultant personnel and costs for  consultant services.
    Also, unlike those providing traditional planning and design
    services,  consultants providing management services such as
    cost and schedule control may not be able to obtain
    professional liability insurance.  These potential
    disadvantages notwithstanding, we anticipate a rapidly
    expanding acceptance of this approach to Project  Management.

    In summary,  grantees are increasingly using special
    consultants to fulfill their own limited need for specific
    services during the construction phase.   With this approach
    the original designer continues to  provide inspection,
    submittal  review and other design related services during
    construction, but independently operating Special Consultants
    provide basic management services including cost  and schedule
    control,  contract administration and documentation.

3.0 Summary

    Originally,  grantees and owners of  private projects assumed
    that their professional consultants performing planning and
    designing services would also provide all of the  necessary
    management services to take charge  of their project from
    planning through construction.  In  turn,  professional
    consultants supported this assumption by suggesting standard
    form contracts using phrases implying a broad range of
    services,  and the consultants offered many of the services
    these owners anticipated needing.  But,  as public and private
    owners became more concerned with shortening the  time required


                               18

-------
to go from planning through to facility start-up,  a number of
new approaches to Project Management were developed,  including
Turnkey and Construction Management (CM).  Also, as
professional consultants became increasingly concerned with the
liability accompanying management services, some deliberately
excluded these from their contracts with the grantees.

Shortly after the Second World War in a deliberate attempt to
shorten the overall planning,  design and construction process
and to focus responsibility for plant performance, some owners
used the Turnkey approach to Project Management.  In effect,
the single professional consultant assumed responsibility for
the planning, design and construction of the facility to meet
established performance standards.  But, due to consultant
imposed limits on the amount of liability they would assume and
the fact that this approach allowed less owner-consultant
control over project costs and schedules, this approach has
been used much less frequently in recent years.

In the 1960's and early 1970's, CM and related services were
widely promoted for public and private projects.  CMs were
employed to develop and award multiple contract packages for
phased, fast-track construction and to maintain comprehensive
cost and schedule records.  But the CM concept, per se, was not
as widely adopted as its promoters hoped, and today few
grantees use the CM approach as it was originally defined.

In contemporary practice, a relatively new and promising
approach to Project Management is for the grantee to continue
to use the original designer for many of the design related
functions during construction, but to employ an independent
special consultant for specific management services, including
cost and schedule control during the planning, design and
construction phases.
                           19

-------
 1.  Wong,  Alan K. ,  "Program Management: Intent, Tools, Practice,"
       Engineering and Construction Projects, ASCE, New York, 1982.


 2.  Scarola,  John A.  and Clyde B. Tatum, "Definition of Project
       Management, "  Engineering and Construction Projects,  ASCE,
       New York, 1982.


 3.  Muller,  Frank,  "Definition of Construction Management,"
       Engineer and  Construction Projects,  ASCE, New York,  1982.


 4.  American Institute of Architects, "Standard Form of Agreement
       Between Owner and Architect," AIA Form A-102, Washington,
       D.C.,  1948.


 5.  National Society  of Professional Engineers, "Standard Form of
       Agreement Between Owner and Project Manager for Professional
       Services," NSPE No. 1910-15, Washington, D.C., 1977.


 6.  Barrie,  D.S., Directions in Managing Construction, John Wiley,
       New York, 1981 .


 7.       ,  Use c-f New Construction Method on Federal Projects a_t
       Three  Agencies  Can Be Improved, Report of the Comptroller
       General of the  United States,  General Accounting Office,
       October, 1977.


 8.       ,  Construction Management Problems Have Delayed Completion
       OL the New Plutonium Facilities at Rocky Flats,  Report of the
       Comptroller General of the United States, General Accounting
       Office,  June, 1978.


 9.  Cushman,  Robert F. ,  and William J.  Palmer, Businessman' s Guide
          Construction, Dow Jones Books, Princeton, N.J., 1980.
10.   Sneed,  William R. ,  "The Construction Manager's Liability,"
       Construction Litigation,  Practicing Law Institute,  New York
       City, 1981,  pp.  317-380.


11.   California State Water Resources Control Board, Managing
       Construction of Clean Water Grant Pro.iects,  Clean Water


                               20

-------
       Grant Guidelines issued by the Division of Water Quality,
       California SWRCB, November 19, 1977.
12.  Godwin, Richard P., and William A. Sandberg, Study of Single :
       Responsibility Concepts for Water Pollution Control
       Projects, Bechtel, Inc., April, 1974.


13.  Webster, Francis M., "Tools for Managing Projects," Project
       Management Quarterly, Vol. XIII, No. 2, June, 1982,
       pp. 46-58.


14.  O'Brien, James J.,  "Evolution of Integrated Project Control
       Systems," Engineering and Construction Projects, ASCE,
       New York, 1982,  pp. 183-197.


15.  General Services Administration Public Building Service, The
       GSA System for Construction Management, reprinted October,
       1977.


16.  PBS/GSA order No.  ADM/P545039B, October 20, 1980.


17.  Hester, Weston T.,  et al, Construction Management and
       Construction Contractor Claims, State of Washington
       Department of Ecology, 1981.


18.  National Research Council, Management of Urban Construction
       Programs, Committee on Management of Urban Construction
       Progam, Building Research Advisory Board, Commission on
       Sociotechnical Systems, Washington, D.C., 1980.


19.  American Society of Civil Engineers, Construction Division,
       Construction Risks and Liability Sharing, 1979.


20.  Kornblut, Arthur T., and John L. Sullivan, "The Liability of
       Architects and Engineers to Third Party for Economic Loss,"
       Practicing Law Institute, New York City, 1981, pp. 235-260.


21.  Cochrane, Luther,  Construction Claims: Representing the
       Construction Owner, Practicing Law Institute, New York,
       1982.
                               21

-------
                             Chapter 3


                      Professional Liability
1.   Introduction
    Many grantees contract with professional consultants to provide
    the technical and management services needed to plan and design
    their projects,  and monitor construction.   In addition to the
    necessary technical services,  the facility designer may also
    provide the basic Project Management services needed,  or these
    may be procured  from separate  consultants.  The "professional
    liability" of these consultants is in effect synonymous with
    their responsibility to the grantee or others for damages
    suffered due to  their negligence or breach of contract.

    According to common legal practice, to establish professional
    liability the grantee must show that the professional  has a
    legal duty to the grantee; that by breach  of contract  or
    negligence he failed to meet an established standard for its
    performance; and that the grantee was harmed by,  but was not
    the cause of the loss.

    If, for example,  an error is found in the  original design of a
    machinery component, the grantee and designer typically
    negotiate the distribution of  liability based upon the terms of
    the grantee-designer contract  agreement.  As a practical
    matter,  some minor errors and  omissions in the original design
    are considered inevitable, and designers frequently correct the
    design,  if not the work itself, at their own expense.   And,
    designers purchase errors and  omissions insurance to protect
    themselves from  the infrequent large losses attributable to
    design deficiencies.

    Whereas the consultant's responsibility for facility design and
    performance may  be clearly outlined in the contract documents,
    the same contracts are frequently vague about the consultant's
    responsibilities for management functions.  And,  since errors
    and omissions insurance is usually unavailable for management
    functions, many  consultants hesitate to even appear responsible
    for them.

    In this chapter  the case-law precedents and contract provisions
    relating to liability of the professional  consultant for
    management services are discussed in detail.  In conclusion, it
    is shown that although the grantee and professional consultant
    may share an active relationship on a particular project, and


                               22

-------
    the grantee may rely heavily on the professional's performance
    of specific functions, most professionals incur relatively
    little liability for the performance of management services.
2.0  Establishing Liability

    Based upon the literature study and survey compiled as part of
    this report, we have established that the grantee may
    pratically reduce cost overruns, delays and risks of litigation
    by exercising basic management services, including maintenance
    of schedule controls during the design phase; schedule control
    during construction; and immediate resolution of problems
    during design and construction.

    In principle, to establish liability of the consultant for
    these management services the grantee must show that the
    consultant had a duty to perform them, that they were not
    performed according to the contract or were otherwise done
    negligently, and that consequently the grantee suffered losses.
    Unfortunately, in practice there is no industry consensus on
    the identity and level of management services a "reasonable"
    Project Manager would ordinarily perform, most grantee-
    consultant contracts exclude many of these and other services,
    and it is extremely difficult to isolate the specific harm
    attributable to the consultant's actions versus those of the
    grantee or contractor.  And, consequently, there is
    extraordinarily little case law to provide guidance for those
    seeking to assess the liability of a consultant Project
    Manager.  There are only two separate instances in which the CM
    has been held liable for his duties as caretaker of the project
    schedule and/or negotiator of project change orders.

    In Green Plumbing and Heating Co.^ Inc. v. Turner Construction
    Co., 500 F. Supp 910 (E.D. Michigan 1980), the Mechanical
    Contractor (Green) contracted with the owner to construct a
    portion of a hospital, and Turner contracted with the owner to
    act as construction manager (CM).  Subsequently, the mechanical
    subcontractor claimed the CM interfered with its contract with
    the owner, and that the CM was negligent in performing its
    scheduling and coordinating duties.  The charge of the CM's
    negligence was later blocked, and the mechanical subcontractor
    was permitted to pursue the charge of tortius interference by
    the CM.  Unfortunately, only a limited discussion accompanied
    this case and its outcome is not instructive.

    The consolidated case of Edwin J. pobson^ Jr. Inc. v. Rutgers
    State Univ.f 157 N.J. Super. 357, 384 A. 2d 1121 (1978), and
    subsequent Broadway Maintenance Corp. v. Rutgers University,
    447 A. 2d 906 (S. Ct. N.J. 1982) contains a more elaborate, but
    direct statement on the CM's liability.

    In this case the CM had agreed explicitly "... to enforce
    the combined schedule ..." constructed by an outside CM


                               23

-------
    consultant and jointly approved by the other prime contractors
    on the job.  Based on the CM's responsibility to enforce the
    schedule and coordinate the multiple contracts,  the court held
    that it was responsible to the delayed contractors for their
    damages.
    One lesson which we may draw from the Dobson case is that if
    the Construction or Project Manager explicitly agrees to
    utilize the project schedule to coordinate the contractor's
    work,  then he may become liable for damages resulting from the
    delay.


3.0 Liability According to the Contract

    The owner-consultant agreement is a logical starting point when
    evaluating the consultant's liability for management services.
    As in the Dobson case previously cited,  the Project Manager can
    be held responsible for those services he explicitly agrees to
    perform.

    Many professional societies and contractor associations have
    developed standard owner-consultant contract agreements,  and
    although seldom used in their entirety,  they contain many
    contract clauses which are widely adopted.  Perhaps the most
    widely known standard form agreements are those  issued by the
    American Institute of Architects (AIA)  and the National Society
    of Professional Engineers (NSPE).  For the purposes of this
    discussion we will focus on the following:

         AIA Document B-141  (1977)  ,  an owner-designer agreement;
         AIA Document B-801  (1980)  ,  an owner-construction manager
                                     agreement;
         AIA Document A-201  (1976)  ,  an owner-contractor agreement;
         NSPE Document 1910-2 (197*0  ,  an owner-designer agreement;
         NSPE Document 2802 (1974)  ,  an owner-designer and
                                     contractor agreement.

    Each of these agreements contains some reference to the
    management services grantees need most,  i.e.,  prompt resolution
    of change orders and close schedule coordination,  but these
    references are seldom detailed.  In the  following discussion we
    compare the treatment of these  different management services in
    the respective contract forms.

3.1 Immediate Resolution of Design Problems  and Changes or Disputes
     During Construction

    One of the key management services a Project Manager can
    provide is to help the grantee promptly  review and resolve
    change orders and disputes.   Prompt resolution reduces the
    uncertainty inherent in any unresolved matter,  and enables the
    grantee and contractor to plan their work more effectively.

    None of the standard form contracts explicitly require the
    consultant to seek immediate resolution  of design problems,


                               24

-------
    changes or disputes during construction,  perhaps due to the
    fact that many design or construction problems require
    substantial investigation before they can be resolved.  Unusual
    delays or lack of diligence by the designer or construction
    manager,  however, may be handled according to doctrines of
    professional liability.

3.2 Schedule Control During Design

    In earlier sections of this report, it was established that
    design schedule control is improved by the use of the following
    four techniques:

        1.  the owner's possession of a detailed design schedule;
        2.  monthly or more frequent schedule reviews,
        3.  monthly or more frequent design progress reports, and
        4.  enforcement procedures permitting the owner to withhold
            payment if design work is behind schedule.

    The above contracts, however, do not include provisions for
    effective use of these techniques.

    AIA Document B-141, an owner-designer agreement, provides the
    owner a design schedule only if he requests one.  The provision
    states that:

         The Architect shall perform Basic and Additional
         services as expeditiously as is consistent with
         professional skill and care and the orderly progress
         of the Work.  Upon request of the Owner, the Architect
         shall submit for  the Owner's approval, a schedule for
         the performance of the Architect's services which shall
         be adjusted as required as the Project proceeds, and shall
         include allowances for periods of time required for the
         Owner's review and approval of submissions and for
         approvals for authorities having jurisdiction over the
         Project.  This schedule, when approved by the Owner, shall
         not, except for reasonable cause, be exceeded by the
         Architect.  (AIA  Document B-414 s 1.8)

    Recalling the four elements recommended for design schedule
    control, this contract provides a schedule (if requested by the
    owner), but no monthly reviews, progress reports or enforcement
    procedures.
                               25

-------
"SPE Document 1910-2, an owner-designer agreement, provides
only a suggested date of completion:

     (the designer) would expect to start our services
     promptly after receipt of your acceptance of this
     proposal and to complete our services within 	
     months,  (letter agreement incorporated by reference in
     NSPE 1910-2)

This agreement specifies a suggested date of completion, but
provides no interim schedule control.   It requires none of
the four elements recommended for effective design schedule
control.

NSPE Document 2802, an owner-designer and contractor
agreement,  contains a scheduling provision to cover design
and construction.  Its scheduling provision appears to
provide only the scheduled date of start and completion:

     The work to be performed under this contract shall be
     commenced as of the 	 day following the execution
     of this contract and shall be completed within such time
     schedule as shall be mutually agreed to by the Owner and
     Engineer-Contractor.  (NSPE Document 2802, Article 4)

This design and construction scheduling provision provides no
interim schedule control.  The specification of start and
completion dates is insufficient to permit adequate
assessment of the progress of the work.  Like NSPE Document
1910-2, this agreement provides none of the four elements
needed for design schedule control.

AIA Document B-801,  an owner-construction manager agreement,
contains one provision that could be interpreted as requiring
a design schedule.   It states that the construction manager
shall maintain a project schedule that integrates and
coordinates the designer's services with construction
schedules.   Under this agreement,  which contains specific
construction scheduling provisions described in detail in
later sections,  the construction manager is to:

     Provide for the Architect's and Owner's review and
     acceptance,  and periodically update,  a Project Schedule
     that coordinates and integrates the Construction
     Manager's services,  the Architect's services and the
     Owner's responsibilities with anticipated construction
     schedules.   (AIA Document B-801  1.13)

The provision states that the schedule shall coordinate the
parties'  responsibilities with reference to "anticipated
construction schedules" (emphasis added).   This wording may
imply that the construction manager  is to schedule portions
of design work that are concurrent with construction that is
to begin shortly.
                           26

-------
    If this clause were to be applied to the design phase, it
    would provide a schedule for design services, apparently
    including specification of some design milestones.  However,
    it provides no monthly review (although "periodic" updating
    is required), no monthly progress reports,  and no schedule
    enforcement procedures.

3.3 Schedule Control During Construction

    To control effectively the project schedule during
    construction, we believe that the grantee should:

         1.  possess a project construction schedule;
         2.  conduct monthly or more frequent schedule reviews;
         3.  verify the schedule and work in progress monthly or
             more often;
         4.  update the schedule with each review; and
         5.  have enforcement procedures permitting the
             withholding of payment if work falls behind  schedule.

    The current versions of the owner-designer agreements
    explicitly limit the designer's role in enforcing elements  of
    the owner-contractor agreement.  The designer denies
    responsibility for the construction contractor's failure to
    perform in accordance with the contract documents, which
    normally include the schedule agreed upon by the owner and
    contractor.

    The owner-designer agreements provided by the AIA and NSPE
    have similar provisions limiting the designer's
    responsibility for the acts or omissions of the contractor.
    The AIA owner-designer agreement states:

         The Architect shall not have control or charge of, and
         shall not be responsible for construction means,
         methods, techniques, sequences, or procedures, ... or
         the acts or submissions of the Contractor,
         subcontractors, or any other persons performing  any of
         the Work, or for the failure of any of them to carry out
         the work in accordance with the contract documents.
         (AIA Document B-141, s 1.5.5)

    Under the AIA agreement, the owner may contract for
    additional services during construction, which binds  the
    designer to:

         .  . . providing coordination of the work performed by
         separate contractors and the Owner's own forces.
         (AIA Document B-141, s 1.6.2)

    The NSPE owner-designer agreement states:

         (the designer) shall not be responsible for the  means,
         methods, techniques, sequences or procedures of


                               27

-------
     construction selected by the Contractor(s) ... He
     shall not be responsible for the failure of Contractors
     to perform the construction work in accordance with the
     Contract Documents.
     (NSPE Document 1910-2 s 1.6.2)

The NSPE design contract lacks an analagous provision for
coordination of contractors and the owner, but does offer as
an additional service:

     . . . services resulting from the involvement of more
     than one prime contractor for construction of the
     project.  (NSPE Document 1910-2 s 2.1)

It is unclear what services are contemplated under this
clause.  The current versions of the owner-contractor
agreements lack the elements necessary for adequate schedule
control during construction.   In the following section, we
will inspect the construction scheduling provisions of AIA
Document A-201.  As we have seen in the earlier discussion of
the NSPE owner-designer and contractor agreements,  the NSPE
agreement provides only the start and completion dates for
the entire project.

The AIA owner-contractor agreement contains a scheduling
clause which requires a schedule for the construction work:

     The Contractor,  immediately after being awarded the
     Contract,  shall prepare and submit for the Owner's and
     Architect's information an estimated progress schedule
     for the Work.  The progress schedule shall be related to
     the entire project to the extent required by the
     Contract Documents, and shall provide for the
     expeditious and practical execution of the Work.
     (AIA Document A-210 s 4.10)

The terms of this contract provide for an "estimated"
progress schedule, but little else.  There is no requirement
of schedule reviews,  updates,  or for the verification of the
schedule and the work in progress.  In addition,  there is no
schedule enforcement procedure available to the owner if the
work falls behind schedule.

The construction scheduling provisions of the owner-
construction manager agreements are more complete than those
contained in the contracts we have already reviewed, but they
do not specify  all the elements necessary for effective
schedule control.

The AIA owner-construction manager agreement contains
construction scheduling provisions that provide a
construction schedule,  updating to reflect progress, and
recommendations for enforcing the owner's contracts with
other parties.   The construction manager is to:
                           28

-------
     Provide for the Architect's and Owner's review and
     acceptance, and periodically update a Project Schedule
     that coordinates and integrates the Construction
     Manager's services, the Architect's services and the
     Owner's responsibilities with anticipated construction
     schedules.
     (AIA Document B-801 s 1.1.3)

     Develop a Project Construction Schedule providing for
     all major elements such as phasing of construction and
     times of commencement and completion required of each
     separate Contractor.  Provide the Project Construction
     Schedule for each set of Bidding Documents.
     (AIA Document B-801 s 1.1.5.3)

     Consistent with the Project Construction Schedule issued
     with the Bidding Documents,  and utilizing the
     Contractor's Construction Schedules provided by the separate
     Contractors, update the Project Construction Schedule
     incorporating the activities of Contractors on the
     Project, including the activity sequences and durations,
     allocation of labor and materials, processing of Shop
     Drawings, Product Data and Samples, and delivery of
     products requiring long lead time procurement.  Include
     the Owner's occupancy requirements showing portions of
     the Project having occupancy priority.  Update and
     reissue the Project Construction Schedule to show
     current conditions and revisions required by actual
     experience.
     (AIA Document B-801 s 1.2.2.2)

     Schedule and conduct pre-construction, construction and
     progress meetings to discuss such matters as procedures,
     progress, problems and scheduling.  Prepare and promptly
     distribute minutes.
     (AIA Document B-801 s 1.2.2.1)

     Endeavor to achieve satisfactory performance from each of
     the Contractors.  Recommend courses of action to the
     Owner when requirements of a Contract are not being
     fulfilled and the non-performing party will not take
     satisfactory corrective action.
     (AIA Document B-801 s 1.2.2.3)

Under this construction management agreement, the owner is
provided a schedule for construction, including the phasing of
construction activities and the start and completion dates for
separate contractor's work.  The owner also is provided
schedule reviews, although their frequency is not described.
There is no verification of the schedule and the work in
progress, but the contract does provide for scheduling
updating "as required".  Finally, the construction manager is
to recommend courses of action to the owner when construction
contracts are not being fulfilled.  These recommendations
would be forthcoming if the contractor was not performing


                           29

-------
    according to the schedule due to causes for which he is
    legally responsible.

    In conclusion,  the standard form contracts for design,
    construction and construction management do not provide the
    owner with the  recommended procedures for schedule monitoring,
    maintenance and enforcement.   The principal deficiencies of
    the contracts are lack of  monthly schedule reviews and
    updates,  inadequate schedule enforcement procedures, and lack
    of verification.

4.   Conclusion

    Grantees  who employ Project Managers to provide management
    services  are naturally concerned with their ability to hold
    the consultant  liable for damages associated with his breach
    of contract or  negligent performance of specific management
    services.

    According to common legal practice,  to establish professional
    liability  the grantee must show that the professional had a
    legal duty to the grantee; that by breach of contract or
    negligence he failed to meet an established standard for its
    performance; and that the grantee was harmed,  but was not also
    the cause  of the loss.

    We have shown that there is almost no case-law precedent for
    holding a  Construction or Project Manager liable for
    negligence in the performance of particular management
    services.   In one case where a detailed ruling was made,
    however,  the CM was held liable for  those services he had
    explicitly agreed to provide in his  contract with the owner.

    The fact  notwithstanding that some consultants have been held
    liable for management services, we do not expect a large
    number of  similar cases or decisions in the future.  In a
    systematic review of contemporary, standard-owner consultant
    contracts  forms we have shown here that most standard
    contracts  are written in a way that  minimizes the consultant's
    liability  for particular management  services.   And, we note
    that these standard contract forms,  and similar contract
    clauses,  are widely used in contemporary practice.

    Finally,  we note that if the grantee wants to establish
    Project Manager responsibility for particular management
    services,  and be able to hold the consultant liable for the
    consequences of negligence or non-performance,  the grantee
    should explicitly specify the services to be provided in the
    grantee-consultant contract.
                               30

-------
                            CHAPTER 4


                    THE CONTEMPORARY GRANTEE

1.   Introduction
    Federal and state agencies providing financial assistance to
    local grantees are naturally concerned that grant funds are
    managed properly and their original goals fulfilled.
    Although supporting statistical evidence is seldom cited,
    some observers of grant programs express concern that
    midsized and smaller grantees are sometimes mismanaging grant
    funds and receiving insufficient management assistance from
    the grantor agencies.

    Previously, many agencies constructing capital-intensive
    grant funded projects  were represented by experienced, if not
    large,  sophisticated organizations with a detailed
    institutional knowledge of the workings and vagaries of
    design and construction processes.  The state highway
    departments, for example, had developed large, comprehensive
    design and construction organizations.  With the EPA grant
    program, a different type of grantee is becoming more common,
    and specifically we observe that few have personnel
    experienced with the design and construction processes, and
    many have difficulty meeting their established objectives.

    To help us establish those management characteristics which
    "successful" grantees  found most helpful, and those which
    were less helpful or were counterproductive, we met
    personally with the senior officials of over twenty grantee
    agencies and many additional consultants to discuss their
    experiences.  We inquired about the overall grantee
    organizational structures, grantee policies for selecting and
    using consultants,  particular management problems grantees
    were experiencing and  the administrative costs normally
    incurred.

    For grantees who were  considered nominally successful by EPA,
    neighboring agencies or their peers, the management
    techniques cited as most important were the use of qualified
    personnel to perform and to oversee the work, and maintenance
    of close control over  the design and construction work
    through detailed periodic reports and a prompt response to
    any problems which developed.

    Conversely, virtually  all of the grantees experiencing
    problems reported that the difficulties they had encountered
    could be attributed to insufficient preparation for the work,
    weak or nonexistent cost and schedule controls for design and
    construction,  and the  inability to act decisively on changes,
    questions about the design,  etc.  And, these conclusions and
    other observations made during these visits were corroborated
    by the results of our  subsequent survey.
                               31

-------
    In this chapter we review two composite pictures of the
    Construction Grants Program grantees; first, a picture is
    developed of the grantees according to the populations served
    and, second with respect to the management techniques they
    used.

    First,  we categorized grantees according to populations
    served, i.e., large,  mid-sized and small,  and then developed
    a composite image of each grantee category based upon the
    data developed through our field visits and survey.  In
    conclusion, we observed that smaller grantees are usually
    managed with substantial assistance from outside consultants
    and are frequently less successful in minimizing cost over-
    runs and delays in project schedules.  Conversely, larger
    grantees usually managed their work with outside consultants
    or by force account,  and regardless of the personnel employed
    (consultant versus force account), these grantees are usually
    significantly more successful in minimizing overruns and
    delays.

    Second, based on input provided by grantees and their
    consultants, published literature, and our survey, we have
    identified 12 management techniques grantees can use to
    reduce project delays, cost overruns and the likelihood of
    claims from designers or construction contractors.
    Summarizing, these techniques may be simplified to three
    basic concepts: 1) maintain close schedule control over the
    project throughout its life; 2) identify and respond to
    potential difficulties in a timely manner  both during design
    and construction; and 3) carefully scrutinize the
    qualifications of all prospective professional consultants.
    In conclusion, the available evidence demonstrates that if
    these management techniques are used, the  cost overruns,
    delays in project completion and construction contractor
    claims are minimized, and the grantees will actually expend
    fewer funds on force account and consulting services than
    those grantees who do not.

    Many of our initial conclusions about what constitutes good
    and bad grantee Project Management practices were based upon
    discussions with EPA, grantee and consultant personnel.  But,
    the consistency and responses from these persons
    notwithstanding, we believe that the most  persuasive evidence
    supporting the merits of particular management practices is
    contained in the survey data.  The survey  data corroborated
    our observations from a large number of discussions, but most
    importantly provided specific,  quantifiable measures of the
    value (or limitations) associated with particular management
    services.  Because of its particular value we will emphasize
    the survey data in the attached discussion.

2.  Grantee Characteristics; A Function of Population

2.1 Small grantees
                               32

-------
    For the purposes of this study, small grantees are defined as
    those serving populations less than 10,000 people.
    Approximately one-half of the grantees considered for this
    study are small.

    Small grantees are typically cities, with approximately 1/4
    constructing secondary facilities, while the others are
    constructing primary, tertiary, conveyance systems,
    sludge-handling systems, or pump systems.

    Based both on our questionnaire and visits with numerous
    small grantees, we observed that they usually employ the
    original designers to manage the entire project from planning
    through construction, and that few hire a special consultant
    or manage their own projects.

    The overwhelming majority of small grantees reported projects
    valued at less than $5,000,000.00 and had construction cost
    overruns due to change orders or claims of less than 5%, but
    a few had cost overruns greater than 10?

    The total project duration ranged from less than two years to
    over six years; however, a majority of these projects had a
    duration of four-to-six years.  Half of the grantees reported
    construction time overruns of less than six months; however,
    one-fourth had time overruns greater than six months.

    The small grantee typically administered fewer than 25 change
    orders on the specified project, and spent less than 2% of
    the project costs on administrative force account work.

2.2 Mid-sized grantees

    Mid-sized grantees are defined as those agencies which serve
    a population greater than 10,000 but less than 500,000.
    Nearly half of the grantees interviewed were mid-sized
    grantees, and are typically cities; however, some are county
    or special districts.  The most common type of projects are
    up-grading of existing plants and conveyance systems, and
    these grantees were the least involved in the construction
    of tertiary plants.

    About a third of the middle grantees managed their own
    projects, a third hired special consultants as construction
    managers, and the remaining third engaged the designer to do
    the construction management.

    Half the middle grantees' projects were valued in excess of
    $5,000,000.  A third of the grantees had construction over-
    runs in excess of six months; however, the vast majority of
    middle grantees had cost overruns of less than 5% of project
    costs.

    The middle grantee typically spent less than 2% of the
    project cost on administrative force accounts; however, the


                               33

-------
    percentage of project costs expended for administrative force
    account increased noticeably, on the average, as the grantee
    size increased.

    As with small grantees, the mid-sized grantees reported
    administering fewer than 25 change orders for their specified
    projects.

    Almost half of these grantees had project durations between
    four and six years, while nearly a third lasted over six
    years.

2.3 Large grantees

    For the purposes of this study, large grantees are defined as
    those agencies serving a population greater than 500,000
    people.  Seventeen of the large grantees responded to our
    questionnaire.

    The large grantees are typically a special district
    emphasizing the construction of an up-graded treatment
    facility or a new conveyance system.  Fewer large grantees
    construct either secondary or sludge-handling systems.

    The large grantees typically managed the construction
    themselves, while a few hired the designer to do the
    construction management work.  A vast majority of these
    grantees managed a project valued in excess of $5 million.
    Of the 17 responding large grantees, three had projects
    valued in excess of $50 million.

    A vast majority of large grantees reported construction cost
    overruns less than 5%,  while no large grantees reported
    overruns in excess of 10% of the project costs.   Half of
    these large grantees reported time overruns of less than six
    months, and a third reported overruns in excess of six
    months.

    The large grantees typically reported a higher percentage
    costs expended on administrative force account than did small
    or middle grantees.  Seven of the seventeen grantees spent
    over 6%, and the remaining were evenly divided between the
    two-to-six percent bracket and the less-than-2J  bracket.

    Half of the grantees processed fewer than 25 change orders,
    and most of those remaining administered between 25 and 50
    change orders.

    Large grantee projects typically lasted longer than small or
    middle grantee projects.   These projects usually last in
    excess of six years.

2.4 Qeneralizations pertinent to all grantees

    Comparatively, the larger the population served  by the


                               34

-------
    grantee agency, the larger the dollar value of the projects
    and the percentage of administrative costs.  Also, as the
    number of people served increases, the type of agency shifts
    from the city agency to county agencies to special district.

    The grantee population also has an effect on the type of
    facility involved.  Smaller grantees constructed more
    secondary systems and upgraded existing plants.  As the
    grantee population increases,  cost overruns decrease;
    however, time overruns lightly increase.

3.0 Twelve gpecific Techniques for Effective Management

    As we discussed alternate approaches to Project Management
    with different grantees and consultants, it became
    increasingly clear that no single approach to the project's
    organization or skillful use of consultants would result in a
    well managed project for all grantees.  For example, some
    grantees were able to do extremely well with their own force
    account staff, while with others the use of their own staff
    was an apparent hindrance to effective Project Management.

    Based on our discussions with participants in the
    Construction Grants Program, our review of the literature on
    Project Management and the results of our survey, we were able
    to identify a series of specific management services which
    grantees would find productive and efficient.  We emphasize
    that these services, or any combination of them, can be
    utilized effectively for any size of grantee, project, or
    organizational structure.  Thus, even grantees with well
    established programs may be able to readily adopt and
    implement them.

    In the following section we present the specific Management
    techniques and document the relative costs and benefits
    associated with their implementation.

    With respect to the planning and design phase of the work,
    the grantee should:

      1)  Consider the prospective designer's:  a) Errors and
          Omissions insurance;  b) record of delays and cost
          overruns on previous projects; and  c) any current
          claims or dispute with clients or others.

          For the purposes of our work, we assume a grantee was
          using this technique if he considered any two of the
          above criteria;

      2)  Respond immediately to serious problems revealed during
          the 50% design review;

      3)  Possess a detailed schedule for all planning and design
          activities;
                               35

-------
      4)  Review a schedule of the project design monthly or more
          frequently;

      5)  Require  progress  reports on the project  design  and
          planning monthly or more frequently; and

      6)  Enforce the design schedule by notice to the  designer,
          and  threaten or actually withhold payment if the  work
          does fall behind schedule.

    During  the construction phase,  a similar set of  management
    techniques are used.  In particular, the grantee should:

      7)  Immediately resolve all change orders or disputes with
          the contractor;

      8)  Possess a detailed schedule of all construction
          activities;

      9)  Conduct a review of the construction schedules  monthly
          or more frequently;

     10)  Verify the progress of the work with respect to the
          schedule monthly or more frequently;

     11)  Update the construction schedule with each review; and

     12)  Enforce the construction schedule by notice to the
          contractor,  threatening or actually withholding payment
          if the construction work falls behind schedule.

    Through our investigations we have found that all grantees,
    regardless of population served or type of facility planned
    and constructed,  can use these techniques to minimize
    unexpected cost increases and delays in the projects
    completion.  Furthermore,  we note that for grantees using
    these techniques the actual force account and administrative
    costs are equal to or lower than those for grantees not using
    them.

    We have analyzed the data developed through our questionnaire
    and established specific conclusions with respect to these
    management techniques previously  mentioned,  and these
    conclusions are summarized in the following sections.

3.1  Overall Effectiveness g£ the Techniques

     The tables presented in this section show the combined
     effect of the techniques.   Some  tables present data
     applicable to the design phase only,  in which six techniques
     could be used.   Others present overall project results,
     which combine the six techniques used during design with the
     six applicable to construction.

     The tables below show the effect of techniques used during


                               36

-------
     the  design  phase.   Use  of the techniques  was  associated with
     a  time  saving of about  50 days,  and a  possible reduction in
     the  likelihood of claims.

       Table 1   Delay in Completing the Design Phase
                and the Number of Techniques Used
       Number of
      Techniques Used
     (only 6  techniques
     apply to design work)
                     Average Delay in
                      Completion of
                      Design Work
         02
         34
         56
techniques
   11
70
50
17
days
 it
Sample
Size

92 grantees
73    "
51    "
       Table 2:   Number of Techniques Used During Design and the
                 Likelihood of Claims in the Design Phase
                 (only 6_ techniques apply to design work)
         Number of
     Techniques Used
        0-2
        3-4
        5-6
                 %of Grantees
               Reporting Claims
                  8*
                  4%
                  6%
          Sample Size
          100 grantees
           74    "
           49    "
3.2  Overall Effectiveness of Techniques Used During Design and
     Construction

     The three tables below show that use of the twelve management
     techniques was associated with:
       a.  a 145-day reduction in construction delays
       b.  a 50% reduction in construction cost overruns
       c.  an 85% reduction in successful construction claims
           against the grantee.

       Table 3:  Number of Techniques and Delays in Completing
                 Construction (based on the originally scheduled
                 completion date)
       Number of
    Techniques Used
        0-4
        5-8
        9-12
                   Average Delay in
               Completing Construction
                       243 days
                       197  "
                        97
                Sample Size
                 26 grantees
                120    »
                 92    "
                               37

-------
       Table 4:  Number £f Techniques Used and Construction
                 Cost Overruns as a. Percentage of the Original
                 Contractor' s Bid

       Number of               Average Construction
     Techniques Used               Cost Overrun      Sample Size
        0-4                         5.456              25 grantees
        5-8                         4.3%             118    "
        9-12                        2.7%              93    "


       Table 5:  Number of Techniques Used and the Likelihood
                 that the Grantee Will Lose a Claim from the
                 Construction Phase ______ _

       Number of           Likelihood that Grantee Will
     Techniques Used         Lose Construction Claim  Sample Size
        0-1                          45%               22 grantees
        5-8                          20%              106     »
        9-12                          6%               90     "


3.3  Use. QL Techniques aM Construction Administration Costs
     The three tables below show that the direct costs of
     administering construction were not increased by the use of
     these techniques.   In general, the total cost of
     administering construction, the cost outside construction
     management services,  and the grantee's own force account
     services were lower when more of these techniques were used.


       Table 6: Number of Techniques Used and the Total Cost
                of Administering Construction as a. Percentage
                £f the Cost of Construction
                              Administrative Costs
       Number of              As a Percentage of
     Techniques Used          Construction Costs    Sample Size
          0-4                         5.0%           28 grantees
          5-8                         4.6%          109     »
          9-12                        4.4%           88     «
       Table 7:   Number of Techniques Used and the Total
                 Cost of Administering Construction aj> a.
                 Percentage of the Cost of Construction

                              Construction
                         Management Services as a
         Number  of          Percentage of
      Techniques           Construction Cost         Sample Size
          0-4                    5.8%                23 grantees
          5-8                    4.5%                93     »
          9-12                    4.8%                66     »
                               38

-------
       Table 8:   Number of Techniques Used and Cost Q£ Grantee
                 force Account Construction Management ftervices
                 as a. Percentage of the Cost oL Construction

                             Force Account Costs
        Number of            as a Percentage of
      Techniques Used        Construction Cost    Sample Size
         0-4                       1.6$            28 grantees
         5-8                       1.4$           110    "
         9-12                      1.3$            89    "


3.4  Use Q£_ Techniques and Construction Administration Costs,
     by Project Cost

     The following tables show the number of techniques used and
     the total cost of administering construction.  In general,
     the use of these techniques did not increase total
     administrative cost, regardless of project cost.  The
     results for larger projects should be interpreted with
     caution due to the small sample size.

       Table 9:  Number of Techniques Used and Total Cost Q£_
                 Administering Construction as a. Percentage
                 of the Cost of Construction

         1. Projects with Total Cost of Less than $5 Million
       Number of
       Techniques      Administrative Cost      Sample Size
         0-4                  5.3$                   20
         5-8                  4.6$                   74
         9-12                 4.6$                   52

         2. Projects Costing from $5 Million to $15 Million
       Number of
       Techniques      Administrative Cost       Sample Size
         0-4                  5.2$*                   6
         5-8                  5.0$                   18
         9-12                 5.3$                   20
     •These figures should be interpreted with caution due to  the
      small sample size.
         3. Projects Costing From $15 Million to $50 Million
       Number of
       Techniques      Administrative Cost       Sample Size
         0-4                 1.5$*                     1
         5-8                 5.7$                     11
         9-12                3.7$                     11
                               39

-------
         4. Projects Costing $50 Million or More
       Number of
       Techniques      Administrative Cost       Sample Size
         0-4                 1.5%*                     1
         5-8                 3.9*                      5
         9-12                4.5*                      4


3.5  Use fl£ the Techniques and Cost ££ Outside Construction
     Management Services, by Project Cost

     The following tables show the number of techniques used  and
     the cost of outside firms used to manage construction.
     The tables have been broken down according to the cost of
     the project.  In general,  the increased use of these
     techniques did not require the grantee to pay more for
     outside construction management services, regardless of
     project cost.  Some of the figures should be interpreted
     with caution due to the small sample size.

       Table 10:  Number of Techniques Used and Cost Q£ Outside
                  Firms Used to Manage Construction, as a.
                  Percentage cJl the Cost of Construction

         1. For Projects Costing $5 Million or Less
       Number of      Cost of Outside Construction
       Techniques        Management Services        Sample Size
         0-4                      5.9*                   15
         5-8                      4.8*                   64
         9-12                     4.7*                   45


         2. For Projects Costing $5 Million to $15 Million
       Number of      Cost of Outside Construction
       Techniques        Management Services         Sample Size
         0-4                      6.0**                   7
         5-8                      3.5*                   24
         9-12                     5.2*                   16

         3. For Projects Costing $15 Million to $50 Million
       Number of      Cost of Outside Construction
       Techniques        Management Services         Sample SIze
         0-4                      3.0**                   1
         5-8                      4.5**                   5
         9-12                     4.9**                   5

     *These figures should be interpreted with caution due to the
      small sample size.

3.6  Use fi£ the Techniques and Cost of Outside Construction
     Management Services, by Grantee Population

     The following tables show the number of techniques used and
     the cost of outside firms  used to manage construction.  The
     tables have been broken down according to the grantee


                               40

-------
     population.   In general,  the costs of outside construction
     management firms were lower when more of these techniques
     were used, regardless of grantee population.   Some of the
     figures should be interpreted with caution due to the small
     sample size.

       Table 11:   Number of Techniques Used and Cost of Outside
                  Firms Used fro Manage Construction as a.
                  Percentage of the Cost of Construction

       Grantee  Population

         1.  Less  than 10,000 People
       Number of
       Techniques
         0-4
         5-8
         9-12
Cost of Outside Construction
   Management Services
            6.0%
            4.5%
            4.7%
Sample Size
  12
  45
  33
         2.  10,000 to 500,000 People
       Number of
       Techniques
         0-4
         5-8
         9-12
Cost of Outside Construction
   Management Services
            6.1%
            4.4%
            5.2%
Sample
  10
  47
  24
Size
         3.  500,000 People or More
       Number of
       Techniques
         0-4
         5-8
         9-12
Cost of Outside Construction
   Management Services

            2.1%*
            2.8%*
Sample
   0
   5
   8
Size
3.7  Use pf Techniques and Total Construction Management Costs.
     by Grantee Population

     The following tables show the number of techniques used and
     the total cost of administering the construction phase.  The
     tables have been broken down according to the grantees'
     population.  In general, the grantees with populations of
     less than 10,000 people reported lower total administrative
     costs when more techniques were used.  Grantees with

     *  This figure should be interpreted with caution due to the
        small sample size.
     populations of over 10,000 people reported slightly higher
     total administrative costs when more techniques were used.
                               41

-------
       Table 12:  Number of Techniques Used and Total Cost
                  Administering Construction as a. Percentage
                  of the Cost of Construction

       Grantee Population:

         1.  Less than 10,000 People
       Number of
       Techniques
         0-4
         5-8
         9-12
       Total
Administrative Costs
         6.2%
         4.7?
         4.9?
Sample Size
   15
   50
   38
         2.  10,000 to 500,000 People
       Number of
       Techniques
         0-4
         5-8
         9-12
       Total
Administrative
         3.7%
         4.7?
         4.6?
Sample
   15
   47
   28
Size
         3.  500,000 or More People
       Number of
       Techniques
       0-4
       5-8
       9-12
       Total
 Administrative

         3.0?*
         4.5?
 Sample Size
    0
    6
   11
3.8  Use oL the Techniques and Cost of Grantee Force Account
     Services for Construction Management, by Grantee Population

     The following tables show the number of techniques used and
     the cost of grantee force account services during
     construction.  The tables are broken down according to
     grantee population.  In general,  these tables show that
     grantee force account costs remain stable or decline with
     the use of additional techniques, regardless of grantee
     population.  Some of these figures should be interpreted
     with caution due to the small sample size.
     *This  figure should be interpreted with caution due to
      small sample size.
                                    the
                               42

-------
       Table 13:   Number of Techniques Used and Cost jp£ Grantee
                  Force Account Construction Management Service,
                  as a Percentage of the Cost of Construction

       Grantee Population:

         1.   Less than 10,000 People
       Number of
       Techniq ues
         0-4
         5-8
         9-12
Force Account Costs
          .8%
         1.1%
          .9%
         2.   10,000 to 500,000 People
       Number of
       Techniques
         0-4
         5-8
         9-12
Force Account Co;
         2.1%
         1.4%
         1.6%
         3.  500,000 or More People
       Number of
       Techniques
         0-4
         5-8
         9-12
Force Account Costs

         1.9%*
         1.8%
Sample Size
   13
   46
   39
Sample Size
   12
   49
   31
Sample Size
    0
    6
   11
3.9  yse of Techniques and Cost of Grantee Force Account Services
     for Construction Management^ bv Project Cost

     The following tables show the number of techniques used and
     the cost of grantee force account services during
     construction.  "Force account" services refer to those
     provided by the grantees' own in-house personnel.  These
     tables are broken down according to the costs of the
     project.  In general, force account costs decreased when
     additional techniques were used.  Some of these figures
     should be interpreted with caution due to the small sample
     size.
     *This figure should be interpreted with caution due to the
      small sample size.
                               43

-------
       Table 14:  Number fif Techniques Used and Cost o£ Grantee
                  Force Account Construction Management Services,
                  a_s a. Percentage of the Cost of Construction

       By Cost of Project:

         1.  Less than $5 Million
       Number of
       Techniques
       0-4
       5-8
       9-12
Force Account Costs
       1.7*
       1.4?
       1.1?
         2.  $5 Million to $15 Million
       Number of
       Techniques
         0-4
         5-8
         9-12
Force Account Costs
       2.0%*
       1.0?
       1.656
         3.  $15 Million to $50 Million
       Number of
       Techniques
         0-4
         5-8
         9-12
Force Account Costs
        .5%*
       1.6?
       1.3?
         4.  $50 Million or More
       Number of
       Techniques
         0-4
         5-8
         9-12
Force
Account
  .5?*
 1.6?*
 2.9?*
Costs
                   Sample Size
                      18
                      69
                      55
                   Sample
                       7
                      22
                      20
                  Size
                   Sample
                       1
                      11
                      10
                  Size
Sample Size
    1
    5
    4
3.10 Analysis of the Specific Tactics

      The individual effects of some of the techniques are shown
      below.  Many of the techniques required the concurrent use
      of another technique (i.e.,  a schedule review cannot be
      conducted if no schedule is used), thus there are fewer
      individual analyses than techniques.

3.11  Qualifications of Design Consultants

      The capabilities of the design consultant have a direct
      effect on the grantee's costs and schedule for at least two
      reasons.   First,  a lesser-qualified designer may require a
     *This  figure should be interpreted with caution due to
      small sample size.
                                  the
                               44

-------
      longer time and higher costs to complete the design work
      satisfactorily.  Second,  construction costs and time may be
      increased by construction contractor difficulty with
      incomplete or erroneous contract documents, inadequate
      contract administration,  or an ineffective grantee/designer
      relationship.

      The survey data indicate that the grantee should consider
      the previous record of prospective designers, including:

        a.  cost or time overruns on previous projects
        b.  errors and omissions insurance availability
        c.  pending litigation or other disputes with other
            owners who have hired the designer.

          Table 15:  Dumber of. Prequalification Criteria Used and
                     Cost Overruns as a Percentage fi£ the
                     Contractor's Original Bid

          Number of Criteria Considered     Average Cost Overrun
                    0-1                             4.0?
                      2                             3.3$
                      3                             2.5?

3.12  Development and Enforcement of a. Master Schedule for the
      Design Phase

      The development of a master schedule for the design phase
      allows the designer to plan more effectively his
      activities.  In addition, the formal development of the
      schedule may alert the designer and other parties to
      potential difficulties.

      As the design work progresses, the designer and grantee can
      use the schedule to remind them of activities scheduled for
      the near future.  If work is progressing slower than
      anticipated, the owner will be in a much better position to
      alter his own time-table to reflect the probable completion
      date.

      The survey data did not reveal that the use of a design
      schedule had any effect on the completion of the design
      phase.  However, grantees that did not have a design
      schedule or did not enforce it incurred an average delay
      during construction of 80 days longer thah grantees that
      had a design schedule and enforced it.  Enforcement
      consisted of notifying the designer that work was behind
      schedule, and if necessary, threatening to withhold payment
      or actually withholding payment.

3.13  Review of the Design Schedule on a. Monthly or More Frequent
      Basis

      Schedule review allows the grantee and designer to assess
      the progress of the design work, and to take timely action


                               45

-------
      to correct or minimize delays.  The schedule review is an
      important aspect of effective management because delays and
      unexpected difficulties are frequently encountered on
      construction projects.  If they are not noted by the
      grantee, their effects may be costly.

      Grantees that reviewed schedules and work in progress during
      the design phase monthly or more often reported that design
      work was at least 6 months late on 9? of the projects.
      Grantees that did not use this technique reported that the
      design work was at least 6 months late on 20% of the
      projects.

        Table 16:  Frequency of Design Schedule Review and
                   Delay In Completing Design Work

        Frequency of Design        Percent of Grantees Reporting
         Schedule Review             at least & months Delay
        Monthly or more often                  9?
        Quarterly or not at all               20%


3 • 14  Identification ajid Correction of Serious Problems at the
      50% Design Review

      The 50? design review is an analysis of progress at the
      midpoint of the design phase.  During this review,  the
      grantee and designer consider the implications of the
      design as it takes shape.   This review may consider the
      operations and maintenance costs,the availability of
      equipment or materials specified,  and the results of
      geotechnical investigations of the proposed site.  Although
      few grantees reported that serious problems were revealed
      by the 50% review,  but not subsequently corrected,  11?
      reported that problems were not revealed by the review, but
      later became apparent.

       Table 17:  Outcome o£ 50? Design Review and Construction
                  Cost Overruns as Percentage of Construction
                  Cost
                                              Average
          Outcome of 50?  Design Review      Cost Overrun
          No serious problems were re-
          revealed, or if revealed were
          corrected immediately                   3.9?

          Serious problems were not
          revealed, or if revealed
          were not corrected                      4.1?

3.15  Development and Enforcement of a Master Schedule for the
      Construction Phase

      The use of a master schedule in construction allows the
      grantee, designer,  and contractor to communicate and to


                               46

-------
plan their respective activities.   In contrast to the
design phase,  in which the grantee and the designer may be
the only active parties,  construction adds the contractor
and subcontractors.  Delays are costly due to the
amount of equipment and labor at the site, which must be
paid for whether working or not, and the grantees'  indirect
costs due to inability to use the structure.

Construction delays are a fertile source of disputes and
claims.  The use of a construction schedule can reduce
delay by coordinating the work of the parties and,  if
claims are filed, may be used as evidence to support or
defend against them.

The construction schedule should include the timing and
duration of major work activities.  It should also describe
the procurement and delivery dates of long lead time items,
and the inspection dates of major equipment and systems.
If there are subcontractors, it should show the interfaces
between their work and the work of the prime or other
contractors.

Grantees that reported that they used and enforced a master
schedule during construction completed projects an average
of 79 days earlier than those that did not. The enforcement
procedures consisted of giving notice to the contractor
that work was behind schedule, or the threatened or actual
withholding of payment.

  Table 18: Use and Enforcement g£ a. Master Construction
            Schedule and Delay in Completing Construction

  Grantee's Use of Construction           Average Delay
          Schedule                        in Completion

  Did not use and enforce schedule            219 days
  Used and enforced schedule                  140 days

-------
3.16  Review of  the Construction Schedule  
-------
      The amount by which the cost of construction exceeded the
      contractor's original bid was strongly correlated with the
      extent of delay in finishing the project.  On an average,
      grantees incurred an additional 1% rise in construction
      costs per 150 days' delay.

3.18  Resolution o_£ Contract Changes fir. Disputes With The
      Contractor As. Soon As They Occur

      Most significant construction projects require minor
      changes in the work originally planned.  These may be the
      result of slight design changes, the grantee's request to
      add or delete features, or ambiguous or incorrect design
      documents.  Changes may also be required if the site
      conditions differ materially from those represented in the
      construction contract, or if unusually bad weather or other
      occurrence delays the work.  These changes in the scope,
      time, or cost of the work are formally recognized by change
      orders which amend the original construction contract.
      Changes are a significant cause of cost overruns, delay,
      and claims.

      Successful resolution of changes or disputes requires the
      agreement of the grantee and contractor on the scope, cost
      and time extension (if any) for the change.

      Grantees that resolved change orders or disputes with the
      contractor immediately reported contractor claims on 8% of
      the projects.  Grantees that deferred  their resolution
      until the end of the project, or resolved them
      periodically reported contractor claims on 48/& of the projects,

      In addition, immediate resolution of changes or disputes
      with the contractor was associated with lower change order
      costs.  Grantees that resolved them immediately had change
      order costs averaging 2.6% of the cost of construction.
      Owners that deferred resolution incurred change order costs
      averaging 4.1/5 of the cost of construction.
                                                     %
      The survey data indicate that prompt resolution of changes
      or disputes with the contractor reduced the likelihood of
      claims and the extent of cost overruns resulting from
      construction.

  4.  Conclusion
      We have considered recommending greater EPA assistance to
      individual grantees, more (and less) grantee commitment of
      grant funds for management services, and numerous other
      techniques to enhance the ability of the individual
      grantees to manage properly their projects.  But, based on
      all of the information available to us the most effective
      management techniques the grantee can  use are those
      outlined above, and are readily available through
      professional consultants for those grantees who do not
      already have the capability to provide them.  And,


                               49

-------
furthermore,  use of these recommended services is not
expected to result in higher administrative cost, and
requires little assistance from EPA or other agencies to
implement.
                         50

-------
                                   APPENDIX

1.   Development of Opestionnaire

    One of the most effective means of establishing major patterns
    and trends in grantee management practices is to survey a random-
    ly selected sample of contemporary grantees.  Surveys conducted
    with written questions can be directed to a much larger sample of
    grantees than it would be feasible to visit personally, and the
    data gathered can be analyzed statistically to isolate particular
    developments.

    Working with a number of grantees, consultants and California and
    federal EPA officials between December 1980 and April 1981, we
    developed and trial tested a 105 question questionnaire.
    Representatives from the University of California Survey Research
    Center provided some technical guidance to us in the development
    of the questionnaire format and the questions themselves.

    In developing the questionnaire, we focused on seven topical
    areas, including:

      a.  objective project results, including the number and types
          of claims encountered during design and construction, and
          increased construction costs;

      b.  characteristics of the grantee agency (e.g., special
          districts, county, city, etc.,);

      c.  characteristics of the specified project, including costs
          and type;

      d.  description of the role of other agencies involved in the
          project, including the federal EPA, delegated state
          authorities and the Army Corps of Engineers on behalf of
          the federal EPA;

      e.  the roles of the project designers, construction managers
          and other consultants during design and construction;

      f.  management techniques utilized by the grantee, including
          considerations used when selecting consultants, project
          managers, the cost of the administrative techniques used,
          scheduling practices and change-order management;
          and

      g. costs associated with the cost of the project.

    Prior to adoption of the final questionnaire and format, rough
    drafts were submitted to grantees, consultants and
    representative EPA officials.

2.   Question Format

    To facilitate development of meaningful responses from the


                              51

-------
    grantees,  we developed three basic types of questions: (1)
    multiple choice;   (2)  a format permitting the grantee to check
    all options which apply; and  (3) a fill-in-the-blank format.

    Multiple choice questions were used where all appropriate
    responses were mutually exclusive.  Where multiple responses to
    the same question may  have been appropriate, and no answer
    precluded any other response,  the grantee was encouraged to check
    each answer that applied.  Finally, to provide the grantee with
    adequate flexibility in responding, in a limited number of cases
    the grantee was asked  to specify particular costs or percentages
    associated with his work.

3.  Sampling Techniques

    EPA provided us with a computer-tape listing of approximately
    17,000 active grants in the construction phase (Step 3) in the
    United States and its  territorial possessions.  For the purposes
    of our survey, we limited our sample to approximately 1,000
    grantees who had been  shown at least 80? complete with the
    construction phase (Step ).  No grantee received more than one
    questionnaire, although some grantees had multiple grants.

    Each grantee was asked to respond to the questionnaire with
    respect to a specific  grant pro.iect.  In the cover letter
    accompanying the questionnaire, the grantee was asked to respond
    to the questionnaire using the best of the available information,
    and assured that all responses would be kept confidential.

    254 out of the 971 grantees actually contacted responded by
    completing and returning the questionnaire in an enclosed, self-
    addressed, stamped envelope addressed to the principal
    investigator at the University of California.  Approximately 20
    surveys were returned  incomplete or were otherwise unusable.
                              52

-------
     Questions about the project a_s a. whole 1 apd about Step

 1.   A.   Please indicate below the total estimated cost of all Step 1,
         2 and 3 work — including any costs that are grant eligible.

                        Less than $5,000,000 ....... 65.2%
                        $5,000,000 - $14,999,999 ..... 21.6
                        $15,000,000 - $49,999,999  ....  9.2
                        $50,000,000 or more  .......  4.0

     B.   What is the estimated cost of construction,  i.e., contractor
         bid price plus anticipated contingencies?
                                        *
 2.   Which of the following best describes the grantee agency?

                        City ............... 68.3?
                        County or unincorporated area . . .  9.6
                        Sanitation district  ....... 21.3

 3.   What is the approximate population served by this grantee?  If
     grantee was a county or unincorporated area, your answer should be
     for the total population of the county.

                        Less than 5,000 people ...... 36.1%
                        5,000 - 9,999  .......... 13.7
                        10,000 - 24,999  ......... 27.0
                        100,000 - 499,999  ........ 14.6
                        500,000 or more  .........  7.3

 4.   Who conducted the Plan of Study required by the EPA?

                        The grantee  ...........  7.4%
                        An engineer hired by the grantee  . 92.1

 5.   How many firms or persons submitted proposals that were seriously
     considered before someone  (either the grantee or someone else)
     was selected to do the facility plan?

                        One firm or person ........ 59.5%
                        2 firms or persons ........  8.0
                        3 firms or persons ........ 14.3
                        4 or more firms or persons .... 16,9

 6.   How many proposals were, considered for the Step 2 negotiations?

                        1 to 3 .............. 91.5 %
                        4 to 6 ..............  7.2
                        7 to 10  .............  —
                      '  More than 10 ............ 4

Questions 7 and 8 assume that there may be several Step 3 grants,
including the specified one, originating from previous Step 1 and 2
grants.


                               53

-------
 7.  Please estimate the respective grant amounts and actual  costs  for
     the specified project.

                                   Grant              Actual  cost
                                   Amount             to  grantee

     Construction contract         $	          $	    *
     Administration                $	          $	    *
     A & E                         $	          $	    *
     Inspection                    $	          $	    *
     Contingency                   $	          $	    *
     All "force account"           $	          $	    *
      (i.e., provided by the
      grantee) work included
      in the above

 8.  As a percentage of the construction cost ( contractor bid  price
     plus contingencies), please estimate the costs for Step  1  and  2
     assignable to the specified project.

                        Step 1 :	%   *
                        Step 2:	%   *

 9.  As a percentage of the construction cost, please estimate  the
     cost of administering the Step 3 phase.  Please include
     inspection costs,  schedule maintenance, grant administration and
     cost accounting, but exclude engineering design or technical
     review services.

                     Less than 3% of construction cost .  . .  .33.6?
                     3 to 5.9%	31 .0
                     6 to 8.9%	21.7
                     9 % of construction cost or more  .  . .  .12.8

10.  Which of the following issues were discussed at the  pre-grant
     conferenceCs) with EPA or any other funding agency?  (Please
     check all that apply.)

     Scheduling and timetables for work in progress 	 40.9%
     Timetables for required EPA or other agency reviews
       and approvals	40.2
     There was no pre-grant conference	44.9

Below are some issues on which EPA, the delegated state,  or the Army
Corps of Engineers may or may not have provided guidance.
For each issue, please check one box depending upon how much  guidance
was needed and how much was received.   These questions pertain  to Step
1,2 and 3 work.
                               54

-------
11.   How would you rate EPA (or other agency,  such as delegated state
     or Army Corps of Engineers)  guidance when planning the schedule
     dates for major design and construction activities?

     No guidance was received and none was needed	34.3$
     No guidance was received,  but some was needed	10.7
     Some guidance was received,  but more was needed 	  18.2
     Some guidance was received and that was sufficient. .  .  .  35.5

12.   How would you rate EPA (or other) guidance on developing  contract
     packages (i.e., the scope"of work" for each contract)  based on
     the type of work to be performed, the dollar magnitude of  the
     contract package, or the number of contract packages to  be
     awarded at or near the same  time?

     No guidance was received and none was needed	42.3%
     No guidance was received,  but some was needed	12.6
     Some guidance was received,  but more was needed  ....   15.0
     Some guidance was received and that was sufficient . . .   29-3

13.   How would you rate EPA (or other) guidance on cost accounting
     systems and project control  systems?

     No guidance was received and none was needed	    28.3%
     No guidance was received,  but some was needed	    23.5
     Some guidance was received,  but more was needed  ....    22.7
     Some guidance was received and that was sufficient . . .    25.5

14.   How would you rate EPA (or other) guidance on the type of
     facility — the appropriateness of the system design,  its
     capacity, and the operation and maintenance costs?

     No guidance was received and none was needed	    33.3%
     No guidance was received but some was needed ......    14.3
     Some guidance was received,  but more was needed	    15.0
     Some guidance was received and that was sufficient . . .    37.4

15.   How would you rate EPA (or other) guidance on methods to
     minimize disputes with contractors?

     No guidance was received,  and none was needed	46.3%
     No guidance was received,  .but some was needed	26.6
     Some guidance was received,  but more was needed 	    9.8
     Some guidance was received and that was sufficient. .  .  .   16.4

16.   Which grantor agency was the grantee's principal contact  during
     each step of the project?  Please check one box for each  Step.

                              Step 1         Step 2_
     EPA	37.6%          35.8%
     The delegated state .  .  .  62.0           63.3
     Army Corps of Engineers  .   —              .9
                               55

-------
17.  What type of facility was recommended by the Plan of Study?
     (please check all that apply.)

     Upgrading or expansion of an existing facility	39.4%
     Secondary wastewater treatment	39.4
     Tertiary wastewater treatment	19.7
     Conveyance systems	42.1
     Sludge handling   	25.2
     Pump systems	31.5

18.  How long was the grantee in Step 1?

     Less than 6 months	9.3%
     At least 6 months, less than a year	18.9
     At least a year, less than 2 years	30.8
     At least 2 years	39.2

In Questions 19-21,  please estimate any costs of delay (not
additional requirements) caused by funding agencies (other than the
grantee).  Please indicate the cost of any delay as a percentage of
the cost of that Step.

1 9.  Cost p_£ Step 1 delays:

     There were no delays due to funding agencies	32.6?
     There were delays, but they cost less than 1? of Step 1 .19.9
     1% to 9.9% of Step 1 costs    	16.3
     10% to 24.9%	17.2
     25% to 49.9%	6.3
     50% or more	5.9


20.  Cost of Step 2  delays:

     There were no delays due to funding agencies	34.2%
     There were delays, but they cost less than 1%
          of the cost of Step 2	18.7
     1% to 9.9% of Step 2 costs	20.9
     10% to 24.9%	18.7
     25% to 49.9%	3.6
     50% or more	4.0

21 .  Cost of Step 3. delays:

     There were no delays due to funding agencies ...... 41 .7%
     There were delays, but they cost less than 1%
           of the cost of Step 3	17.0
     1% to 9.9% of Step 3 costs	21.7
     10% to 24.9%   	11-7
     25% to 49.9%	4-3
     50% or more	3.5
                               56

-------
22.  How many grantee personnel were assigned at more than half-time
     (20 hours per week) for management and administration of the
     project in Step 1?

     0 to 3	95.7?
     4 to 7	   3.9%
     8 to 12  	
     13 to 24 	
     25 to 49 	
     50 or more	   	

23.  How many grantee personnel were assigned at more than half-time
     for management and administration in Step 2?

     0 to 3	94.8%
     4 to 7	   4-3
     8 to —	4

24.  How many grantee personnel were assigned at more than half-time
     for management and administration in Step 3?

     0 to 3	85.5%
     4 to 7	12.0
     8 to 12	4
     13 to 24	4
     25 to 49	     .8
     50 or more	   	

25.  Did a change in the grantee's personnel or policies during
     Step 1 cause any problems with the project?

     There was no change in the grantee's personnel
         or policies	76.7%
     There was a change in the grantee's personnel
         or policies, but it caused no problems with Step 1 . . 14.7
     There was a change in the grantee's personnel or
         policies, and it did cause problems with Step 1  ...  8.2

26.  Did the Step 1 proposals suggest any innovative or
     alternative technology?

     Yes	25.6%
     No	73.9

Questions About Step 2.
                               57

-------
27.  How long was the interim period between the funding agencies'
     acceptance of the Facilities Plan and the grantee's filing of
     grant application for Step 2?

     No interim period; Step 2 grant application was filed
        before Step 1 was completed	43.8?
     Less than 30 days	15.4
     30 to 89 days	11.1
     90 to 179 days	   8.2
     At least 6 months, less than a year	   7.7
     At least 1 year	13.0

28.  Who supervised the project designer in Step 2?
     (Please check all boxes that apply.)

     Local government officials directly 	 63.8?
     Another consultant  	  3.5
     The project designer himself  	 56.7
     Another government agency 	 15.7

29.  Who reviewed the project designer's progress?  (Please
     check all boxes that apply.)

     Local government officials directly	76.4%
     Engineer or designer himself  	 53.9
     Another government agency 	 21.3

30.  Who reviewed or approved the design (either interim or final)
     before submittal to a regulatory agency?

     Local government officials directly 	 78.3%
     Another consultant  	  3.5
     Engineer or designer himself  	 53.9
     Another government agency 	 19.7

31.  Who (other than funding agencies)  reviewed the design for
     operability and maintenance expenses and techniques?
     (Please check all that apply.)

     Local government officials directly 	 67.7%
     Another consultant 	 4.7
     Engineer or designer himself	59.4
     Another government agency	21.3

32.  Which of the following issues did the grantee initiate and
     seriously consider during final review of the Step 2 design
     proposal?  (Please check all that apply.)

     Use of innovative or alternative technology 	 18.5%
     Long-term maintenance costs   	 58.3
     Long-term operation and personnel costs for
          the finished project	64.6
     Ability of the grantee to operate the facility
          with available personnel	63.0
                               58

-------
33   What type of cash flow problems did the grantee experience during
     Step 2?  (Please check all that apply.)

     There were no cash flow problems during Step 2  ....   53.1?
     Difficulty in getting EPA approval of amendments to
        the Step 2 design contract caused shortages  ....    9.1
     EPA delays in releasing funds to the grantee
        caused shortages	•  • •  •   2f'°
     Other problems caused shortages (Please specify.)  . .  .    4.7
     Cash flow problems were anticipated and action taken
       in time to avert them	16.1

34.  Was the same or a different engineer or designer used
     on Step 1 and Step 2?

     Different designers were used on Steps 1 and 2 	  9.7%
     The Step 1 designer did part but not all of the
         Step 2 design	o^'4
     Step 1 designer did all of the Step 2 design   	85.7

35.  Which, if any, of the following prequalification criteria
     were considered in selecting a project designer (in addition
     to the required (40 CFR 35-937.3) prequalification procedures)?
     (Please check all that apply.)

     Cost or time overruns on previous projects	21.3%
     Errors and omissions insurance availability   	  11.0
     Pending litigation or other contract disputes with
         other grantees or owners   	10.2
     None of the above criteria was considered	67.7

36.  How did the person or organization verify the project
     designer's progress in Step 2?

     Verification of the project designer's work was done at
       Step 2 closeout only	13-5%
     The project designer certified the progress   	  47.6
     Inspection of the project designer's documents 	  38.4

37.  During Step 2, how often did the project designer
     submit progress reports?

     Every week	   6.5%
     Every other week	   3-9
     Monthly   	58.7
     Quarterly	   8.3
     Other (please specify)	10.9
     There were no progress reports submitted
     by the project designer in Step 2 .  11.7
                               59

-------
38.  Which of the following best describes what happened in the
     10% design review?

     Serious problems were revealed and corrected 	   4.7?
     Serious problems were revealed at this stage,  but
        not corrected at this stage   	1.9
     Serious problems which later became apparent were not
        revealed at this stage	11.3
     No serious problems were revealed at this stage,
        nor did they appear later	82.2

39.  Which of the following best describes what happened in the
     50% design review?

     Serious problems were revealed and corrected 	   6.5%
     Serious problems were revealed at this stage,  but
        were not corrected at this stage	1.4
     Serious problems which later became apparent were not
        revealed at this stage	12.6
     No serious problems were revealed at this stage,  nor
        did they appear later   	79.5

40.  Were any consultants employed in Step 2 to do value engineering?

     Yes, but they did not improve design or reduce construction
        costs significantly ( i.e., at least 10?)	3.4?
     Yes, and they did improve design or reduce construction
        costs significantly   	2.1
     No, none employed for this purpose	94.1

41.  During Step 2, what tasks were performed by consultants
     under contract to the grantee (other than the original project
     designers)?  (Please check all that apply.)

     No consultants were used in Step 2 except the
        original designer's staff 	  57.5?
     Value engineering	5.5
     Grant administration to assist in meeting EPA
        and other agency requirements   	  18.5
     Scheduling or cost control	9.8
     Geotechnical services  	  26.4
     Special construction services including management
        plans and constructability	7.1
     Surveying services   	  29-1

42.  Did the project designer submit a detailed master schedule
     for Step 2 work?

     Yes	45.7?
     No	54.3
                               60

-------
43.   Which of the following sis the master schedule for Step 2
     include?  (Please check all that apply.)

     The project designer did not maintain a schedule
         for Step 2	22.8%
     Detailed estimated cost for each activity	27.2
     Detailed presentation of timetables   	   36.6
     Application dates for permits necessary
         for construction	29.9
     Outside agency approvals  	   29.9
     None of the above	17-3

44.   How often was Step 2 work formally reviewed to insure that
     it followed the schedule?

     Every week	6.7%
     Every other week   	4.9
     Monthly	38.8
     Quarterly	6.7
     The Step schedule was not formally
         reviewed	42.4

45.   How was compliance with the schedule enforced?
     (Please check all that apply.)

     The Step 2 work never fell behind schedule	40.2?
     Notification to the project designer of his failure
         to comply with the schedule was needed to insure
         compliance	6.3
     A threat to withhold payment was made and  was
         sufficient to insure compliance  	   6.3
     Payment was withheld to force compliance	3.1
     The grantee had to change or terminate the project
         designer   	3.5
     The grantee had to change or terminate the
         project designer   	   1.6
     There was no systematic enforcement of the
         Step 2 schedule	42.9

46.   How close to the schedule time was Step 2  completed?

     Step 2 was completed on time	64.8%
     Completed less than 30 days late	    8.2
     Completed 30 to 89 days late	10.0
     Completed 90 to 179 days late	    4.1
     Completed at least 6 months but less than  1 year late    5.5
     Completed at least 1 year late	    5.9
                               61

-------
47.  Who paid the additional design cost associated with
     any delay in completing Step 2?

     Step 2 was completed on time   	64.8?
     The project designer bore the entire additional cost . 17.8
     The grantee bore the entire additional cost	7.5
     Both shared the costs	3.3
     EPA or other funding agency reimbursed the grantee
         for the additional costs	5.6

48.  Were there any disputes arising from Step 2 that led to
     litigation or arbitration?

     Yes, there was litigation or arbitration 	   1.7%
     There was a Step 2 dispute,  but it was settled prior
        to litigation or arbitration  	   6.4
     There was no dispute that threatened arbitration
        or litigation	91.5

49.  How much did the award or final settlement cost the grantee
     or other funding agency?

     There was no litigation or settlement entered arising
        from Step 2 work	93.2%
     Less than 2% of the cost of Step 2 work	   3.2
     2 to 4.9/5 of the cost of Step 2	    .5
     5 to 9.9% of Step 2	5
     10% or more of the cost of Step 2	   1.8

Questions About Step 3.

In the following questions,  the term "Construction Manager" represents
the private, professional firm with primary: responsibilities for grant
and construction contract administration.

50.  What role has the Step 2 designer's organization had
     in Step 3?  (Please check all that apply.)

     The Step 2 designer was not involved in Step 3  ....  3.1%
     The Step 2 designer is acting as the Construction
         Manager   	52.4
     The Step 2 designer provided technical review (i.e.,
         review of contractor's submittals, shop drawings,
         etc. ) in Step 3    	73.6
     The Step 2 designer provided construction engineering
         (e.g., resident engineer, field inspection, quality
         assurance)	.71.7
     The Step 2 designer provided contract administration
         (e.g., change orders, time extensions, compliance
         with specifications, resolution of claims,  schedule
         updating, progress payment computation) 	 75.6
                               62

-------
51   Assuming that persons outside the grantee organization were
     employed,  estimate how much the firm or person supervising
     or managing the Step 3 work will be paid as a percentage
     of the total construction cost.

     Less than 1% of the total construction cost 	   15.2?
     1  to 1.9%   	    ,j?'£
     2  to 3.9%   	    Jj'9
     4  to 5.9%   	    |5'°
     6  to 8.9%   	    ]|'°
     9% or more	    13-5
     The grantee supervised or managed construction
         with no outside help	    13.5

52.   What are the grantee's estimated costs for force account
     services used for managing construction in Step 3 (in-
     cluding scheduling, cost accounting, and grant administration)
     as a percentage of the cost of Step 3?

     Less than 1% of the cost of Step 3	    66.1%
     1  to 1.9%   	    1->-°
     2  to 3.9%   	    1°'°
     4  to 5.9%   	     J-°
     6  to 8.9%   	     I'l
     9% or more	      *^

53.   How long after the Step 3 approval to award was the Notice to
     Proceed given?

     Less than 3 months after the Step 3 approval to award.  75.0%
     At least 3 but less than 6 months later	15.0
     At least 6 months but less than a year later	   5.0
     At least a year but less than 18 months later	   3.3
     At least 18 months later   	   1.2

54.   Who prepared the bid documents for Step 3?  (Please
     check all that apply.)

     Grantee	   14.6%
     Designer	   94.5
     Another consultant ...    1.6

55.   Who reviewed the bid documents?  (Check all that apply.)

     EPA	   77.6%
     Grantee	   85.8
     State agency	   83.1
     Another consultant,other
      than the Construction
      Manager or designer . .    2.0
     Construction Manager . .   28.3
     There was no review of
      the bid documents ...     .8
                               63

-------
56.  Was any special scrutiny given to conspicuously low bidders in
     Step 3?

     Yes	34.5?
     No	65.5

57.  Was there a bid protest in Step 3?

     Yes	14.9%
     No	84.6

58.  What did the Step 3 bid protest in Step 3 involve?  (Please check
     all that apply.)

     There was no bid protest in Step 3	70.5%
     Restrictive specifications 	  .  .   3.9
     Irregularities in bid forms submitted  	   8.3
     Minority business enterprise (MBE) requirements.  .    .8

59.  Was the Step 3 contract awarded to the bidder with the lowest
     original price?

     Yes	   92.2?
     No (i.e.,  the lowest bidder was judged nonresponsive
         or not responsible)	    7.4

60.  How many bids were received for Step 3?

     1  bid	2.5?
     2  bids	3.8
     3  or 4 bids	23.7
     5  or more bids	69.5

61.  How did the engineer's estimated construction cost compare
     to the accepted bid?

     The estimate was less than 85% of the accepted bid  .  .  .  12.8%
     The estimate was 85 - 89,9% of the accepted bid 	  12.8
     The estimate was 90 - 99.9% of the accepted bid 	  29.8
     The estimate was 100 - 109.9% of the accepted bid ....  22.1
     The estimate was 110 - 114.9% of the accepted bid ....  10.2
     The estimate was a t least 11% of the accepted bid  .  .  .  11.9

62.  Which of the following did the "master schedule"  prepared
     by the construction contractor (i.e., times and sequences for the
     principal construction activities) include?  (Please check all
     that apply.)

     The "critical path," even if not represented by a CPM
          network	21 .3%
     Project total cost for completion of each major activity. 44.1
     Timetables for EPA and other agency reviews and approvals 20.1
     Estimated schedules and durations for the major
          activities	 .74.0
                               64

-------
63   Who reviewed the contractor's schedule when first submitted to
     ensure that it was realistic and workable?  (Please check all
     that apply.)

     There was no review of the contractor's schedule
           for this purpose	4.7%
     Construction Manager 	 50.8
     Local government officials or grantee employee 	 44.5
     Resident engineer 	 51.6
     The Step 3 contractor did not submit a schedule 	  3.1

64.  What do the grantee specifications require the contractor
     to provide on the schedule for Step 3? (Please check all that
     apply.)

     Major work activities	69-7$
     Durations of major activities 	 63.4
     Estimated costs for each activity 	 47.2
     Critical completion dates   	 39.4
     Bar charts	41 .7
     "Critical Path" networks  	 12.2
     Line-of-balance schedule charts 	  4.3

65.  How willing is the construction contractor to submit schedules?

     Very willing	32.6%
     Moderately willing (i.e., needed to be requested) .... 54.7
     Unwilling, but did submit a schedule	10.2
     Completely unwilling and did not submit a schedule  ...  1.7

66.  How frequently are schedule reviews during Step 3?

     Weekly or more often	14.2?
     Every other week	5.4
     Monthly   	56.8
     Quarterly   	7.1
     There are no formal schedule reviews for Step 3 	 15.9

67.  Is the schedule updated with each review to reflect the current
     progress of Step 3 work?

     Yes   	62. U
     No    	37.1

68.  How frequently does the grantee verify construction progress?

     Weekly or more often	29.8$
     Every other week	3.3
     Monthly	58.3
     Quarterly	4.1
     At completion of the project	3-7
                               65

-------
69.  Who verifies the schedule and work in progress during Step 3?
     (Please check all that apply.)

     Grantee employees or other government officials   .... 63.0?
     Another consultant independent of contractor  	 17.3
     Construction Manager independent of contractor  	 55.5

70.  Who reviews the schedule and work in progress-during Step 3?
     (Please check all that apply.)

     Grantee employees or other government officials 	 68.9%
     Another consultant independent of contractor  	 16.5
     Construction Manager independent of contract 	 53.5

71.  What happens when construction work falls behind schedule
     during Step 3?

     There are no occasions when construction falls behind
           schedule	20.7?
     Notifying the construction contractor that the work
           is behind schedule is sufficient to insure
           compliance	37.9
     A threat to withhold payment or resort to liquidated
           damages provision is needed to insure compliance
           with schedule .	20.7
     Payment is withheld to insure compliance  	 10.3
     The schedule for Step 3 is not enforced	3.9
     Existing EPA regulations for retention do not permit
           adequate grantee schedule enforcement 	  5.6

72.  How many change orders are estimated for Step 3?

     Less than 25	86.7?
     25 to 49	6.7
     50 to 99	5.0
     100 to 199	1.2
     200 to 499	4
     500 or more	   	

73.  What is the total estimated value of all change orders as a
     percentage of the cost of Step 3?

     Less than 2? of the Step 3 cost   	44.3?
     2 to 4.9?	30.8
     5 to 9.9?	13.9
     10 to 14.9?	   3.4
     15? or more	   4.2
     Change orders resulted in a net reduction of Step 3 cost.   3.0
                               66

-------
74   What are the principal causes of change orders during Step 3?
     (Please check all that apply.)

     Clarification of contract documents 	  24.4%
     Changed condition  	  TV*S
     Substantial design changes or additional work  	  41.7
     Substitutions 	  on'i
     Changes required as a result of shop drawing review ...  20.1

75.  Please estimate the proportion of all change orders during Step 3
     that are initiated by the project designer, by the construction
     contractor and by the construction manager.  (Check one box for
     each column.)

                               Project    Construction     Construction
                               Designer    Contractor        Manager
     Initiated at least 50%
      of the change orders       42.2%         33-5%            44.1%
     Initiated 25-49.9% of
      the change orders          15.5          18.2             17.1
     Initiated 10-24.9% of
      change orders               9-7          16.7              o.2
     Initiated less than 10%
      of the change orders       19.4          16.7             12.4
     Did not initiate any
      change orders              12.6          14.8             17-6

76.  How many outside firms, if any, were seriously considered
     for Construction Management in Step 3?

     None; the grantee provided the necessary services ....  28.6%
     None; the project designer acted as Construction Manager.  62.2
     One firm was considered   	   4.1
     2 or 3 firms were considered	   3-7
     4 or more firms were considered	   1.2

77.  In hiring a Construction Manager for Step 3 construction,
     what particular skills possessed by the firm were considered most
     valuable to the grantee?  (Please check all that apply.)

     No Construction Manager was hired for Step 3	48.8%
     Scheduling experiences  	  15.4
     Project design expertise  	  36.2
     Geotechnical services   	   4.7
     Grant administration skills 	  28.3
     Ability to resolve or prevent disputes between grantee
        and contractors	23.2
     Inspection and technical review of contractor submittals.  30.7
                               67

-------
78.  Who was most active in managing and monitoring the activities for
     Step 3?

     The grantee	24.1?
     Construction Manager 	 32.8
     The project designer from Step 2	42.7
     Some other consultant (neither the project designer no
         construction manager	4

79.  Which of the following issues did the grantee and EPA discuss
     in the pre-construction conference?  (Please check all that
     apply.)

     There was no pre-construction conference between EPA
         and the grantee	39.0%
     Cost control and scheduling techniques   	 31.1
     Change order policies  	 41.3
     Eligibility or allowability of costs   	 34.6
     Grantee's inspection responsibility  	 38.6
     Management types or techniques   	 12.2
     The grantee's responsibility fro grant management  .... 39.8

80.  Compared to the contractor's original schedule,  what is the
     actual or estimated construction time?

     Construction is expected to be,  or has been,  completed
        on schedule (or earlier than schedule)	25.6%
     Construction is expected to be,  or has been,  completed
        within 90 days after the original completion date . .   .25.2
     Construction is expected to take,  or has taken,  90 to
        179 days longer than scheduled	19-3
     180 to 269 days longer than scheduled	11.3
     270 to 364 days longer than scheduled	5.5
     At least a year, but less than 2 years,  longer than
        scheduled	6.7
     At least 2 years longer than scheduled	6.3

81.  How did the actual construction costs compare with the original
     construction contractor's bid?

     Actual construction costs were lower than the original
        bid   	20.8%
     Actual construction costs were less than 3% higher than
        the original bid	41.1
     3 to 4.9% higher   	14.4  ,
     5 to 9-9% higher	16.1
     10 to 14.9% higher	3.4
     15 to 24.9% higher	2.1
     25% or higher	2.1
                               68

-------
82   Thinking first only of those Step 3 cost increases that were
     ruled grant--ineligible,  please indicate what percentage were paid
     by the A&E firm,  by the construction manager, grantee, and
     by the construction contractor.  (Please check one box for each
     column.)
  Of those Step 3 cost
  increases ruled grant-
  ^.nelieible:

  Paid more than 50%
     of them
  Paid 25 - 49-9%
  Paid less than 25%
  Paid none of them
                              A&E
                             Firm
                         1.1%
                         1.7
                        10.9
                        86.3
                                Construction
                               Manager
  .7%
 1.3
 4.0
94.0
             Grantee
78.2%
 2.8
 3.3
15.6
        Constructio
       Contractor
 1.8%
 1.8
13.9
82.4
83.
And now thinkng only of those Step 3 increases that were ruled
grant-eligible, please indicate what percentage were paid by the
person or organization indicated.  Again, please check one box
for each column.
                              Construction
                               Manager
     Of those Step 3 cost-
     increases ruled grant-
     eligible :

     Paid more than 50% of them    .7%
     Paid 25-49.9%                	
     Paid less than 25%          93.4
                                        Grantee
                   EPA
                 or Other
                Funding Agency
                                             22.9%
                                             31 .8
                                             11.9
                       84.5%
                        4.2
                        8.5
84.  Thinking of all claims between the construction contractor and
     the grantee resulting from construction disputes, who received
     (or will receive) the bulk of the award?

     There were no claims as a result of construction  	 75.2%
     The contractor received the bulk of the award   	16.2
     The grantee received the bulk of the award	7.7

85.  Were performance bonds used to complete construction in Step 3?

     Yes	33.2%
     No   	66.4
                               69

-------
86.  Who reviewed the project during Steps 2 and 3 to insure easy
     operation of the finished facility?  (Please check all that
     apply.)

     Treatment process expert  	  12.2%
     Architect or project designer  	   74.0
     Grantee or local government officials 	  70.1
     There was no review for this purpose	   5.9

87.  Did the State or any other governmental agency under the
     Intergovernmental Personnel Act (IPA) lend any personnel to
     assist in any step of the project?  (Please check all that
     apply.)

     No, no personnel were lent to us	88.2?
     Yes,  during Step 1   	   2.8
     Yes,  during Step 2	   4.3
     Yes,  during Step 3	   5.5

88.  Who contributed to funds (not counting loans) for the project?
     (Please give percentages which each contributed.)

     EPA	* %
     State	*
     Grantee 	  *
     Industrial Contribution ...  *
     Other   	*

     Total = 100?

89.  How much time was required (or is now forecasted) for the entire
     project to go from the start of Step 1 until the end of Step 3?

                                    *    months
90.  How long was the grantee on the priority list before receiving
     the Step 1  grant?

     Less than 6 months	26.7%
     At least 6  months, less than a year .... 18.8
     At least 1  year, less than 3 years  .  .  .  .37.6
     At least 3  years	16.8

91.  Is the project now in full operation?

     Yes	82.0%
     No   	17.6
     *No statistical analysis has yet been conducted,
                               70

-------
oe
or by the delegated state, but later disapproved?   (If  so,  please
indicate the cost.)
                            71

-------