United States   .
            Environmental Protection
            Agency
              Office Of Water
              (WH-595)
EPA430/W-90-013
September 1990
-EPA
Assessment Of The
Biolac Technology
                                            Printed on Recycled Paper

-------
United States Environmental Protection Agency
    Office of Municipal Pollution Control
     ASSESSMENT OF THE BIOLACR TECHNOLOGY
           Contract No. 68-C8-0023
               September  1990

-------
                         ACKNOWLEDGEMENT








   The report was  prepared by Hydroqual, Inc.  in  fulfillment of



Contract 68-C8-0023.  It was prepared by O.  Karl Scheible, Dennis



E. Scannell and Eugene J.  Donovan, Jr.  of Hydroqual,  Inc.  Irene



Horner and Wendy Bell, OMPC,  Washington,  D.C.  were Environmental



Protection Agency Project  Officers.   The assistance  provided by



the plant operators and  owners,  as summarized  in  the report, is



acknowledged with  appreciation.   The cooperation  and assistance



provided  by  Mr.  Charles  R.  Morgan   of  Parkson Corporation  was



helpful and appreciated.
                              NOTICE
   This  document  has  been  reviewed  in  accordance  with  U.S.



Environmental   Protection  Agency   policy   and   approved   for



publication.  Mention  of  trade names or commercial products does



not constitute endorsement or recommendation for use.

-------
                                    CONTENTS

Section                                                                      Page

         FIGURES	        iii

         TABLES	         iv

   1     INTRODUCTION	       1-  1
         SCOPE OF WORK 	       1 -  2

   2     SUMMARY AND CONCLUSIONS  	       2 -  1

   3     RECOMMENDATIONS	       3-  1

   A     DESCRIPTION OF THE BIOLAC  SYSTEM  	       4-  1
         INTRODUCTION 	       4-  1
         SYSTEM CONFIGURATIONS  	       4-  2
              Biolac-R System 	       4-  2
              Biolac-L System 	       4-  5
              Wave Oxidation Modification  	       4-  5
         OTHER APPLICATIONS OF  BIOLAC  FLOATING AERATION CHAINS  	       4-5
         UNIT OPERATIONS  	       4-  7
              Aeration System 	       4-  7
                   Aeration Chains  and Diffuser Assemblies  	       4-7
                   Blowers  and  Air  Manifold  	       4-10
              Clarification and Solids Removal  	       4-10
                   Integral Clarifier  	       4-11
                   Biolac-L Settling Basin  	       4-11
         STATUS OF THE BIOLAC SYSTEM 	       4-13
              Municipal Biolac  Treatment Systems  	       4-13
              Unit Operations Associated with the Biolac System  	       4-18

   5     ASSESSMENT OF THE  BIOLAC SYSTEM 	       5 -  l
         PROCESS  DESIGN CONSIDERATIONS 	       5-  1
         BIOLAC SYSTEM TREATMENT PERFORMANCE  	       5 -  6
         EQUIPMENT 	       5.  8
              Aeration System 	       5-  g
              Sludge/Solids Removal  Systems  	       5-13
              Polishing Basins  	       5-17
         BIOLAC COSTS  	' '       5.17

   6      SITE  OBSERVATIONS  	       6-  1
         INTRODUCTION  	'	       g.  l
         LIVINGSTON MANOR WWTP, ROCKLAND, NEW YORK   	'...'.'.'.'.'.'.'.'.'.       6-1
              Livingston Manor  STP  Photograph Descriptions  	       6-3

-------
BAY WWTP   	       6 -  3
     Bay WWTP Photograph Descriptions 	       6-4
PIGGOT WWTP, PIGGOT, ARKANSAS 	       6-  5
     Piggot WWTP Photograph Descriptions 	       6-  6
BLYTHEVILLE WEST, NORTH AND SOUTH WWTPS,  BLYTHEVILLE,
ARKANSAS   	       6-7
     Blythville WWTPS Photograph Descriptions (North, South
     and West Plants)	       6-  8

REFERENCES 	       6 -  9

APPENDIX A - DESCRIPTION OF BIOLAC TREATMENT SYSTEMS

APPENDIX B - PERFORMANCE DATA SUMMARY TABLES FOR SELECTED
             BIOLAC PLANTS
                              ii

-------
                                    FIGURES

Figure                                                                       Page

   1     TYPICAL BIOLAC-R FLOW DIAGRAM	       4- 3

   2     WAVE OXIDATION MODIFICATION OF THE BIOLAC-R SYSTEM	       4-6

   3     BIOLAC AERATION CHAIN DETAIL	       4- 8

   4     SCHEMATIC INTEGRAL BIOLAC-R SYSTEM CLARIFIER	       4-12

   5     BIOLAC TREATMENT SYSTEM - U.S.  INSTALLATIONS (MUNICIPAL
         WWTP'S ONLY)	       4-14

   6     BIOLAC-R PLANT DESIGN - AERATION BASIN LOADING	       5-3

   7     BIOLAC-R PLANT DESIGN - DIFFUSERS/AIR FLOW	       5-5

   8     OPERATING BIOLAC-R PLANTS POWER USAGE	       5-7

   9     INTEGRAL CLARIFIER RAKE MOTOR AND CONTROL SWITCHES	       5-14

  10     LIVINGSTON MANOR PHOTOS A AND B	       6-4

  11     LIVINGSTON MANOR PHOTOS C AND D	       6- 5

  12     BAY, ARKANSAS PHOTOS A AND B	       6- 7

  13     BAY, ARKANSAS PHOTOS C AND D	       6- 8

  14     BAY, ARKANSAS PHOTO E	       6- 9

  15     BAY, ARKANSAS PHOTO F	       6-10

  16     PIGGOTT,  ARKANSAS PHOTOS A AND B	       6-13

  17     PIGGOTT,  ARKANSAS PHOTOS C AND D	       6-14

  18     BLYTHEVILLE, ARKANSAS PHOTOS  A AND B	       6-17

  19     BLYTHEVILLE, ARKANSAS PHOTOS  C AND D	       6-18

  20     BLYTHEVILLE, ARKANSAS PHOTOS  E AND F	       6-19

  21     BLYTHEVILLE, ARKANSAS PHOTO G	       6-20
                                      iii

-------
                                    TABLES

Table                                                                       Page

  1      SUMMARY LISTING OF MUNICIPAL WASTEWATER PLANTS WITH BIOLAC	      4-15

  2      SUMMARY OF UNIT OPERATIONS  WITH BIOLAC  SYSTEMS (MUNICIPAL
         BIOLAC PLANTS	      4-19

  3      MANUFACTURER'S  RECOMMENDED  DESIGN CRITERIA FOR BIOLAC R
         SYSTEMS IN COMPARISON TO CONVENTIONAL EXTENDED AERATION
         SYSTEMS	      5.  2

  4      SUMMARY OF AVERAGE PERFORMANCE DATA FROM SEVERAL BIOLAC
         SYSTEMS	      5.  9

  5      PROBLEMS IDENTIFIED AT VARIOUS BIOLAC PLANTS	      5-10

  6      BIOLAC SYSTEM CONSTRUCTION  COSTS	      5-18
                                      iv

-------
                                  SECTION 1
                                 INTRODUCTION

    The Environmental Protection Agency (EPA)  has supported the application of
new technologies  to  municipal  wastewater treatment in order  to encourage the
development of better  and more efficient treatment technologies.   This often
involves support of the full scale application of a technology on a widespread
scale without the benefit of long term field demonstration and evaluation, with
acceptance of the potential risk of  O&M and/or process problems due to the lack
of experience.

    The  Office  of Municipal   Pollution Control  (OMPC)  evaluates  specific
technologies to determine performance capabilities and to identify weaknesses,
limitations in terms of  use,  maintenance shortcomings and cost effectiveness.
Where an evaluation addresses a technology with which  there have been problems,
they need  to  be  defined  in order to correct  them or to  clearly indicate the
limitation  of a  technology for further  consideration  and  support.   Where
technologies  are  successful  and show beneficial  applications,  the  EPA  is
interested in providing current information to encourage their use.

    This report  addresses the  BiolacR Wastewater Treatment  System.    Biolac,
which stands for  BIOLogical Aeration Chains  is  a registered  trademark of the
Parkson Corporation, Fort Lauderdale, Florida manufacturers of the system.  It
utilizes oscillating,  diffused air  aeration  chains in extended  aeration and
aerated lagoon treatment processes.

    The first  full scale installation in the United  States  was at Fincastle,
Virginia  in 1986.   Little information has  been  available  regarding system
operation and  experience,  except  for an assessment report(l)  prepared  for the
EPA in  1986 that  relied  primarily on the manufacturer's  literature.   With the
startup of  several plants since   then,  an  evaluation of  the system was
recommended in order to  investigate  any problems  that may have been identified
with  the process,  and  to determine  if the  technology was  appropriate for
application to municipal wastewater  treatment.

-------
                                                                      Page 1-2
 SCOPE OF WORK

    The  overall  objective of this  evaluation  was  to determine the  status  of
 Biolac  systems  within the  United  States  with regard  to  equipment
 configurations,  process  design and  performance,  operation and  maintenance
 experiences, equipment  and process  related  problems,  and problem resolutions.
 Based  on  this  evaluation,   the  USEPA  would  assess  if the  technology  is
 appropriate  for  continued application to  municipal  wastewater treatment  and
 would define system limitations, if  any,  that may need to be addressed with new
 systems.

    The  scope  of work  relied on  the  collection of existing data  and contact
 with operating plants.    Information was received  from  the EPA,  the  Regional
 offices,  the manufacturer  and treatment  plant operators through  telephone
 interviews  and  several site visits.    Data  regarding  the  Biolac  equipment,
 treatment system design parameters,  and operating conditions were compiled,  and
 problems  that  were  identified with  the operation,  maintenance and process
 performance of the systems were  defined.  Modifications  that  have  been made  to
 the equipment in existing systems or are planned for  new plants were  reviewed
 with the plant operators  and  the  manufacturer, particularly as  they  relate  to
 reported problems.

    This  report describes the Biolac treatment system and presents information
 on the present  status of installations.   The current  approach to  the  design  of
 the treatment system  and an evaluation of the equipment and associated problems
are included, as  well as plant performance and cost information.

-------
                                                                      Page 2-1
                                  SECTION 2
                           SUMMARY AND CONCLUSIONS

    The Biolac Treatment System uses the process technology of either extended
aeration or  flow-through  lagoons for the  treatment of wastewaters.   The key
component is  the  aeration device, which  is assembled as  a floating aeration
chain.  A series of diffuser assemblies are suspended from a "chain" of  floats
stretched across the basin surface.  Located near the basin bottom, the  rising
air bubbles  from  the  diffusers cause the  aeration  chains  to oscillate  across
the surface.  These moving fine bubble diffusers provide sufficient oxygen and
keep  the mixed liquor  solids  in suspension.   The  Biolac-R  configuration
incorporates  an  integral  clarifier  and  sludge return  and the  Biolac-L is  a
simple flow-through lagoon and polishing basin.

    The Biolac  System was developed  in  Europe during the  mid  1970s with the
manufacturer reporting over 200  installations  worldwide.   By late 1989,  there
were greater than 50  Biolac systems operating or in the design/construct stage
in the United States.   Forty-five of these are municipal facilities, of which
32  are Biolac-R  and  10  are  Biolac-L configurations  (the  other three are
modified systems).   Most operating plants  are the  R configuration  (19  of  27
operating plants).  These also have longer  operating histories,  with the first
facility going on-line in 1986.

    Operating experience is limited because the technology  is  relatively new  to
the United  States  and most plants have only  recently  come on-line.   The long
term  reliability  of  system  components  and  performance  could  not  be  fully
evaluated within the context of this report.

    The  systems are  sized conservatively relative to conventional  extended
aeration and flow-through lagoons.  Loadings  to the Biolac-R  extended  aeration
system are  typically  7  to 8 Ibs BOD/d-1,000 ft^,  with an F/M ratio of  0.03  to
0.1 Ibs BOD/lb MLVSS;  the hydraulic residence  time is typically  24 to 48 hours.

-------
                                                                       Page 2-2

 The flow-through Biolac-L lagoon systems are designed for a hydraulic residence
 time of 6 to 20 days.

     Greater than half  the plants  have design  flows  between 0.5 and  2.0 mgd.
 Only two plants have a design flow greater than 2 mgd (both are 4.0 mgd).  The
 remaining are less than  0.5  mgd design capacity.  Most plants  are located in
 the South,  with 14  of  the 27  operating  in Arkansas and Alabama.

     Operating plants  are  consistently meeting  permit requirements.    Of 13
 plants  for which performance data  were available, average  effluent BOD ranged
 between 5.1 and  20.8  mg/L. ,  representing  removals of  91  to 98 percent.   The
 TSS effluent levels ranged between 6.7 and 34.8 mg/L,  with  removals  of 86 to 96
 percent.  Most plants were accomplishing full nitrification.

     A  major claimed advantage  of  the systems, low cost  operation  due  to  low
 power  requirements  for  mixing, appears  to be  realized based  on  an  average
 reported horsepower for  aeration  of  45  HP/million gallons  of basin  volume.
 This is  significantly  less  than  required by  conventional  fixed aeration
 systems.  Whereby aeration horsepower in extended aeration  systems is  generally
 set by  mixing  requirements for fixed aeration  systems,  the Biolac  aeration
 system  sizing is set by  oxygen requirements,  resulting in  significantly less
 power input  than conventional systems.

     Problems  that have been  encountered with  the Biolac  system have  related
 primarily  to  equipment  materials,   installation and  maintenance.   Various
 problems  which  centered on  materials of construction  and hardware  design
 resulted  in corrosion  failures, excessive wear,   and  clarifier return  sludge
 clogging problems.   These appear to  have been adequately addressed and  solved
 by replacement,  repair, and/or redesign.

    The  fine bubble diffusers have  operated well.  Where  problems have been
noted,   these were limited  and  generally  due  to  improper  installation  (clamp
materials and adequate  fastening),  and clogging/failure  of  the diffuser  sheath.
Proper,  routine  flexing of the diffusers appears to be an essential  maintenance
 task to assure the performance and  life of  the  diffusers.

-------
                                                                       Page  2-3

    Total  capital  construction costs,  based  on  data  (received  from  the
manufacturer)  for  13 plants  averaged  approximately  $1.30/gpd design  capacity
with  a range  of  $0.84 to  $2.11/gpd  for plants  greater  than 0.5  mgd.   This
excluded the cost of land.

    Overall, the Biolac system,  installed in the  Biolac  R  and  L configurations,
is  a  reliable, effective wastewater  treatment  process.   The  aeration chain
system and  integral clarifiers  are  cost effective  because  of  low power  and
operation and maintenance requirements,  and are appropriate to the  application
of extended aeration process technology.

-------
                                                                      Page 3-1
                                  SECTION 3
                               RECOMMENDATIONS

    The Biolac Wastewater Treatment system should be considered a viable, cost
effective,  alternative  extended aeration  or flow-through  lagoon  process for
application to municipal wastewaters.

    Application of  the  Biolac technology  should  incorporate several elements
that  affect its  performance  and O&M  requirements.   These include effective
screening of coarse solids, routine flexing  of the diffusers, skimming devices
in the integral clarifier (although the need for this may be influenced by the
size  of the  plant  and  the  acceptable level  of  operator  attention),  use of
corrosion resistant materials  (coal  tar epoxy painted steel  or stainless steel)
for  appropriate  metallic parts  that contact  the water,  sludge  withdrawal
systems  to minimize  the potential for  clogging  (addressing  air  lift pipe
sizing,  suction  line  hole sizes  and spacing),  and  effective  design  of the
blower systems for noise control  and air filtration.

    Continued  evaluation of O&M  requirements  and experience  is  recommended.
Current experience is limited because most plants are only  recently  installed.
Attention should  be paid to  the  long-term operation and the demonstrated unit
life of  the Wyss  diffusers in the  Biolac  treatment  system applications.   The
overall operation and maintenance costs for  the system, and winter operational
reliability should be  assessed as  experience  is  gained with  the systems.

    An  evaluation of  one  modified  Biolac  system,  the wave   oxidation
modification for biological  nutrient removal, is recommended.  The apparent low
power requirements for the system suggests that it may be a viable alternative
nitrogen removal system.   Particular attention  should be paid to system control
and process stability.

-------
                                                                      Page  4-1
                                  SECTION 4
                       DESCRIPTION OF THE BIOLAC SYSTEM
INTRODUCTION

    Biolac stands for Biological Aeration Chain systems.  Manufactured by  the
Parkson Corporation of Fort Lauderdale, Florida, the system utilizes  a moving
fine bubble aeration device and earthen basin construction,  in the application
of low loaded extended aeration  and aerated lagoon process technologies.   There
are more than 200 systems  reported in operation, primarily in the United States
and Europe.

    The basic Biolac process layout consists of a basin or lagoon equipped with
floating aeration chains.  A  polishing basin following the aeration  basin is
optional,  but is generally recommended by Parkson when designing a new facility
and assuming land is available.  This may reduce operator requirements and will
provide  greater  process  stability,  particularly  in  cases  where  stringent
effluent limits are imposed.   The polishing basin may be aerated,  unaerated or
split into aerated  and unaerated zones.  The  process goal  is  direct discharge
of  clarified  effluent of secondary quality or  better.   Nitrification can be
accomplished  and  a process option  is  available  for  nitrification-
denitrification.

    The innovative aspects of  the Biolac system lie in the approach to aeration
and mixing.   The key component is the  floating aeration chain.   This  is  a
series  of diffuser assemblies that are  suspended from  a  "chain"  of  floats
stretched across  the basin surface.   The  chains  oscillate  across  the  basin
surface, propelled  by the rising bubbles  from  the diffusers;  this  moves  the
diffusers  through  the  liquid, thereby  mixing  and aerating  the  wastewater
simultaneously.   When the chain moves to  full  tension in one  direction,  the
diffuser assemblies swing slightly and cause the chain  to move in the opposite
direction,  repeating the  oscillation  cycle.    The  chains  typically  move
laterally  8  to  30 feet  (for  activated  sludge  applications) under normal

-------
                                                                       Page 4-2

 operating  conditions,  mixing the  volume  of water  in the  traversed path and
 maintaining the mixed liquor solids in suspension.  In cases where less mixing
 is  required  (e.g.  flow-through  lagoons)  the chain spacing will be wider, with
 greater lateral movement.

    The reported  advantages  of the system  lie primarily  in  the lower energy
 requirement,  when compared  to conventional  extended  aeration  systems,  to
 maintain mixing.   Additionally,  the systems are  relatively  stable due to low
 organic loadings  and long hydraulic  retention times.   Long  solids retention
 times  in the  extended  aeration  system will  require smaller quantities of well
 digested  sludge  to  be  handled,  simplifying  this part of  the plant.   Low
 maintenance  is  also  suggested  for  the blowers, diffuser assemblies,  and
 integral clarifier components.

    This section presents a  description of  the system configurations,  and the
 elements of the unit operations that comprise the system.  A discussion of the
 status of Biolac  facilities  in  the  United States is presented,  addressing the
 types and size of facilities  currently in  operation.

 SYSTEM CONFIGURATIONS

    Alternate configurations of the Biolac  system are applied,  dependent upon
 the site requirements.   The  Biolac-R  system is an extended aeration/activated
 sludge  process,  and  the Biolac-L  system  configuration is an  aerated flow-
 through lagoon system.   A  third configuration  that has very  recently been
developed is  known as  the  Wave Oxidation  Modification;  it operates  under a
modified  aeration pattern  to achieve  anoxic  zones  for  denitrification.
Floating aeration chains  have also been installed  in existing lagoon  systems as
a retrofit,  replacing existing fixed aeration equipment.

Biolac-R System

    Figure  1  illustrates the  typical  Biolac-R  arrangement.   It  is an  extended
aeration activated sludge process,  generally designed more conservatively than

-------
           Influent
                                    WAS
(Optional)
                                                   1
                                                   Sludge
                                                    Pond
                                                  Polishing
                                                    Basin  (Optional)
    Flow
  Ifeaaurin
   Device
                                                      1
                                                                  Effluent
                                             Aerated   Unaerated
                   FIGURE 1.  TYPICAL BIOLAC-R FLOW DIAGRAM.

-------
                                                                      Page 4-4

a conventional extended aeration system.  Preliminary and primary treatment are
not components of the  system,  although, as will  be  discussed later,  effective
screening can contribute to successful operation and  lower  maintenance  of the
Biolac  system,  as  with any  secondary  treatment  plant.    It  is  generally
recommended by the manufacturer.

    Lagoon/basin depths range  from 8  to  20  feet.  Depths on  the  lower  end of
the range  are generally designed  in cases where  deep basin  construction is
impractical for hydraulic, geologic, or cost reasons.  Depths on the higher end
of  the  range  are typically used,  since oxygen transfer efficiency by  fine
bubble aeration is greater with the increased diffuser submergence.  Basin side
slopes are  engineered  based  upon  soils and construction  considerations.   For
the Biolac-R basin,  in which high mixed liquor solids are maintained, sidewall
slopes  in the  order  of  1.5  to  1  (horizontal  to vertical) are optimum to
minimize the required mixing  energy.

    Clarification and sludge  return are provided to maintain appropriate mixed
liquor solids levels.   Integral clarifiers are  used in most systems, although
existing external clarifiers  may be used with older systems where lagoons were
retrofitted with  the  Biolac  aeration  systems.   A  waste  sludge pond  is  also
provided  with the  Biolac-R  system;   this  is generally  small because  of the
limited sludge  production  in  these low  loaded  systems.   Digesters,  or other
sludge  conditioning  processes, would generally  not be needed  due  to the
stability of the waste sludge.

    A polishing  basin  is optional,  but would  be  located  after  the aeration
basin.   Although not  required,  it  is  recommended  by  the  manufacturer for
additional stability  affecting  effluent  polishing and  additional  solids
settling.    This is  particularly the  case when  there  is  little operator
attention,  restrictive  effluent  standards,  and/or  high  hydraulic variability
that may influence the  integral clarifier performance.  The polishing basin is
usually divided by a floating  curtain wall,  with aeration in  the first  section
and quiescent settling in the second  section.

-------
                                                                      Page  4-5
Biolac-L System
    The Biolac-L system  operates as  an aerated  flow-through  lagoon.    Its
configuration  is  as  shown on  Figure  1,  except  that it  does  not have
clarification and sludge  return,  and a waste sludge   pond is not needed.   A
polishing basin is required for the Biolac-L,  with  two to four days HRT (based
on average flow)  and storage  capacity for sludge.  As with the Biolac-R system,
the polishing basin can be divided into aerated and unaerated sections.

Wave Oxidation Modification

    The  Wave  Oxidation Modification  is  a  combined  carbon  oxidation,
nitrification-denitrification process.  The process  employs  a Biolac-R system
operated at  low  (0.5 mg/L or less)  dissolved oxygen  levels  (0.5 mg/L or less
through the  entire  basin) and automatic control of  each aeration chain's air
flow.  Air is throttled  back to  progressively  alternating groups of aeration
chains.    This  sets up  a situation in which  several oxic and anoxic  zones
alternate  in the aeration basin  as illustrated  on Figure  2.  After a period of
time  (approximately  15 minutes), the air flow is redistributed and the low air
flow  chains  receive  high air flow, maintaining  the mixing requirement for the
mixed  liquor solids.  A  dynamic moving  "wave"  of  alternating oxic and anoxic
zones  is formed.

    The Wave Oxidation Modification has been employed in more than a half dozen
wastewater treatment facilities in Europe.   There is  one plant  operating in the
United States,  located in Decatur,  Arkansas.   It  handles a combined  domestic
and poultry  waste high in organic nitrogen.   The plant has been operating since
mid 1989 and has reported good performance.

OTHER APPLICATIONS OF BIOLAC FLOATING AERATION CHAINS

    The  Biolac  floating aeration  chains  have  also  been used  outside the
application  of a specifically designed R or L system, primarily in retrofitting
existing  aeration  systems.   In Ellsworth, Kansas,  for example,  floating  chains

-------
   Influent
                                TIME:  t  =  0 minutes



      Ianoxici  oxic  lanoxic! oxic  Ianoxici
                                               Effluent
 c
Influent
                     HAS
TIME:  t -  15  minutes
                             \
                                                    WAS

                                             Effluent
      1  oxic  Ianoxici oxic  ianoxici oxic   1
FIGURE 2.  WAVE OXIDATION MODIFICATION OF THE BIOLAC-R SYSTEM.

-------
                                                                       Page 4-7

have  been used  in  an aeration  basin prior to  stabilization pond  treatment.
Aeration  chains have also  been retrofitted  to  an existing  aerated  lagoon
treatment facility in Excelsior  Springs, Missouri, where the  aerated lagoon  is
followed by an overland flow treatment system.   The Biolac  aeration chains have
been in operation in a previously existing plant at Durant,  Oklahoma for  over a
year and  a  half;  the aeration chains replaced the fixed aeration  equipment  in
the first one-third  section of  two basins  operated  in parallel.   A polishing
basin with aeration chains was also added to the system.  These  changes allowed
this plant  to  meet  discharge permit limits.  Several Biolac  equipped aeration
basins  are  currently being planned  to  provide nitrification  of  a  trickling
filter plant effluent at the 55 mgd wastewater  plant  in Witchita, Kansas.

UNIT OPERATIONS

    The major  components  of the Biolac systems are  the aeration equipment and
the clarification/solids handling elements.  The  following  discussions present
a description of these unit operations.

Aeration System

    The aeration system consists of the floating aeration chains  and diffuser
assemblies and the blowers and air piping manifold.

    Aeration Chains and Diffuser Assemblies

    The heart of the Biolac  system  is  the  floating aeration chain  assembly.   A
schematic of this assembly  is  shown on Figure 3.   A  restraining chain connects
the end floats  of  the aeration chain with a hook to an anchor  post  mounted  on
the basin bank.  Tension  adjustment is made by  simply  increasing or decreasing
the length of chain between  the  last  float  and  the anchor  post.  Flexible hose
connects the air header to the air pipe of the  float  assemblies.  The hose  is a
multi-layered construction with  inner  and outer layers made of  PVC,  with fiber
reinforcement  for strength.   The  outer  layer is  also  impregnated with
plasticizers and U.V. inhibitors.

-------
           Float Assembly
Flexible Hose
                          Down Coming
                           Flexible
                           Air  Hose
                          WyssDiffusers
                          Counterweight

                                7///X
                                              PVC
                                              Diffuser Assembly
                                                                       Concrete  skirt/apron—J
                     FIGURE  3.   BIOLAC  AERATION CHAIN DETAIL.

-------
                                                                      Page 4-9

    The float  assembly consists of  the float, air  pipe,  two  downcoming air
tubes  and a  fine bubble  diffuser/counterweight  assembly.    The float  is  a
polyethylene shell  filled  with closed-cell polyurethane foam.    The  float is
designed  to  remain  buoyant,  even in  the  event that the entire chain becomes
filled with  water.    The  float shell  material contains inhibitors  to resist
ultraviolet deterioration.

    The air  pipe  runs through the  center and  extends out  of  the ends of each
float.    Hose  connection points  are located  at  both  ends  of  the  float for
joining the air pipe to the downcoming air  tubes.   The air  pipe  and connections
for  new   systems  are  made  of  polyethylene  and fastened with stainless  steel
clamps.

    The  downcoming air pipes are  connected  to  the  diffuser/counterweight
assembly;  clearance  between the basin  bottom and the  diffuser centerline is
typically one foot.   The diffuser/counterweight assembly is constructed of PVC,
and  supports either two,  four or six  diffusers.   The counterweight keeps the
assembly  submerged when the diffusers are charged with air.

    WyssR Flex-A-TubeR diffusers (manufactured by  Parkson)  are used,  consisting
of  a plastic frame,  diffuser sheath,  retainer pad, backflow check valve and
stainless  steel  fastening  hardware.   The  diffuser  sheath  is  composed of
modified  PVC soft plastic  material.   When  air is  introduced to  the  diffuser,
the  flexible  sheath  expands  and  thousands  of   tiny  aperatures  open,   each
releasing a  jet  of  fine bubbles.   When air flow to  the  diffuser is  disrupted,
the  liquid  head  collapses  the sheath and  closes  the apertures,  preventing
fouling   from  backflow of  solids.    When  air flow  to the  diffusers is re-
established,  any  solids,  slime or carbonate build-up  on the surface are
displaced by the  flexing action of the sheath.

     The  EPA has  studied(2)  the WyssR  diffusers   and classified them  as fine
bubble diffusers.  However,  the  manufacturer notes that  the  air bubbles can
approach medium  size  when the diffusers are fully  charged  with  air.   The
operating range for each diffuser is from  1 to 5  scfm with a typical operating

-------
                                                                      Page 4-10

air flow of 3 scfm.  Parkson estimates a diffuser life expectancy of five years
under normal conditions with  recommended maintenance.  Maintenance  consists  of
weekly  to  bi-weekly  diffuser  flexing,  a procedure by which the  aeration chain
air flow is shut  off,  the  air remaining  in  the  chain  is  bled  off (by opening a
ball relief valve on the air header),  and the chain is then recharged with air.

    Blowers and Air Manifold

    Positive displacement rotary type  blowers,  designed for continuous service,
are generally  supplied.    For  larger  systems,  multistage  centrifugal  machines
may be  economical and are considered.   In  most  designs,  three blowers,  each
capable of handling 50 percent of the air requirement, are provided;  thus,  two
blowers will be in service at capacity,  with one on standby.   The  blowers  are
fitted  with  an inlet  filter  and silencer,  a  discharge  silencer,  a  pressure
relief  valve,  a  discharge check valve,  an isolation butterfly valve and  a
discharge pressure gauge.

    Connection between blower discharge and  the aeration chains  is  through  the
air piping manifold.   The  pipe is normally  laid adjacent to the  basin,  running
perpendicular  to the  aeration  chains.   A header pipe  off  the  manifold  is
located  at the  point of  connection  to each  aeration chain.    Each  header
contains a butterfly  valve to  isolate  each aeration chain on the air  piping
manifold for maintenance  and  a pressure relief valve for depressurization  of
the aeration chains.   Each header pipe is supported by a concrete thrust block
and a flexible  hose is used for header to float  connections.

Clarification and Solids Removal

    The Biolac-R and  Biolac-L  systems  provide for  solids/liquid separation.   An
integral  clarifier  is typically  incorporated with  the R  system,  while  a
quiescent zone  is  provided in  the polishing  basin  of the  L  system.

-------
                                                                     Page 4-11

    Integral Clarifier

    The integral  clarifier  section  is  defined by  two  concrete walls,  and a
floating  partition  wall  which  separates the  clarification  zone from the
aeration zone.   Figure 4 presents  a cross-sectional view of the clarifier.  The
rear wall of the  aeration basin serves  as  the back wall,  and the two parallel
concrete walls extend  out  into the basin.   The  floating  partition wall which
separates the aeration  basin  and  the clarification zone,  is  fixed across the
open end between the  two sidewalls.

    The partition wall  is  fixed  to the sidewalls to  permit  flow to enter the
clarifier only under  the length of the partition, minimizing short-  circuiting.
A  flocculating rake,  which moves  along the  length  of  the  clarifier  sludge
trough,  is  provided  for sludge  concentration  and distribution.    Sludge  is
withdrawn by an  air  lift  pump.    Overflow  weirs  are provided for effluent
discharge to the  polishing  basin.  The weir  design loading  rate is typically
less than 10,000 gpd/lineal  foot of weir length at average flow.

    The air lift  sludge  removal system  consists  of  an air blower (or air  from
the main aeration blowers is used), air piping,  sludge suction piping,  gravity
flow sludge  trough,  and an RAS/WAS sludge control  valve  or  gate.   A positive
displacement blower  supplies  the  required  air to lift  sludge from the  hopper
bottom to a concrete  gravity flow  sludge trough into a sludge  flow control box.
The suction pipe,  typically made  from PVC,  has holes spaced appropriately along
its length  for removal  of  the  sludge.   Two gravity flow  pipes from the  sludge
control box convey the settled sludge to either  the sludge pond  or  back to the
head  of the  plant  to  be  mixed  with  the plant  influent.    An electrically
activated and time controlled sludge gate directs sludge flow  to  either  the RAS
or WAS pipe.

    Biolac-L Settling Basin

    A  minimum of one  day  detention  time in the unaerated section  of  the
polishing basin is typically provided.   The volatile solids (about  one-half the

-------
  Waste
Activated
  Sludge
     Effluent
  Return  Activoted  Sludge

S
                       Rear Wall of
                       Aeration Basin
                                                     Floating Partition Wall
                                                     for Aeration Basin/Clarification
                                                     Zont Separation

                                                  Flocculation Rake Mechanism for
                                                  Sludge Distribution and Concentration
                                                     Clarifier  Influent
                                                           Sludgt Hopper


                                                          Sludge Suction Pipe- PVC pipe located along the length
                                                                             of the Clarifier Hopper Bottom
                        FIGURE 4.   SCHEMATIC  INTEGRAL BIOLAC-R SYSTEM CLARIFIER.

-------
                                                                     Page 4-13

total  solids)  settling in  the  basin are further  degraded by about 40  to 60
percent under  anaerobic conditions  that  develop  in the settled sludge zone at
the bottom of  the basin.  The polishing basin is sized to provide up to one to
two decades  of sludge  storage within this zone.   At  the time when it becomes
necessary  to  remove the  sludge, one  of various  methods  can be  selected to
remove sludge, including a floating  dredge,  dewatering and bulldozing, etc.

STATUS OF THE BIOLAC SYSTEM

    The Biolac  Treatment  System was developed in  Europe  in the mid-1970s; by
1985,  there  were  approximately  100  installations throughout Europe and around
the world.  The Biolac  system was first introduced  to  the United States in 1985
with a pilot  test at the Miami  Conservancy District located in Franklin, Ohio.
The first full-scale floating aeration chain system was started in January 1986
for the  treatment of  a dairy waste; approximately one  month later the first
Biolac domestic wastewater  treatment  plant  was  put into  service at Fincastle,
Virginia.   These  two  installations,  as  well  as  many other  early  U.S.
installations, were retrofits of existing plants.

    Recent Parkson information^) lists approximately 200 Biolac installations
operating in the  U.S., Europe  and  other parts  of the world.  There  were 59
domestic and industrial U.S.  installations  either  on-line, under construction
or in  the  design  phase as  of September  1989.   Recently  (March 1990), Parkson
has reported selling an additional 12 systems for domestic applications and two
for industrial clients.  The 59  installations are  spread among 20 states, with
most  located  in  the  eastern half  of the  U.S.    Figure  5  locates  the U.S.
municipal installations.

Municipal Biolac Treatment Systems

    A listing of municipal plants is presented in Appendix A.  A description of
the system and a discussion of  the operations and  performance of each plant is
included.    This  list  is  based  on  information  compiled from  telephone
interviews,   site  visits,  or  discussions  with the  manufacturer.   Table  1

-------
• Plants On Line
A Plants In Design
  Or Construction Phase
    FIGURE 5.  BIOLAC TREATMENT SYSTEM - U.S. INSTALLATIONS  (MUNICIPAL WWTP'S ONLY)

-------
TABLE 1.  SUMMARY LISTING OF MUNICIPAL
    WASTEWATER  PLANTS WITH BIOLAC

Plant
Alabama (10)
Ardmore
Berry
Camden, North
Cedar Bluff
Clayton
Columbiana
Hanceville
New Brockton
Oxford
Stevenson
Arkansas (7)
Bay
Blytheville, North
Blytheville, West
Blytheville, South
Decatur
Maynard
Piggott
Colorado (2)
Colorado Springs
Monument
Georgia (1)
Quitman
Indiana (4)
Ferdinand
Remington
Rensselaer
Cambridge City
Kansas (3)
Ellsworth
Wellsville
Witchita
Kentucky (3)
Edmonton
Greenville
Morgantown
Minnesota (2)
LeSueur
Wells
Design Flow
(mgd)

0.35
0.15
0.22
0.30
0.40
0.75
0.57
0.18
1.0
0.75

0.15
0.80
1.50
1.40
1.35
0.06
0.60

0.9
1.3

1.3

0.47
0.28
1.2
0.8

0.5
0.18
54.4

0.51
0.75
0.50

0.9
0.55
Plant
Type

R
R
R
R
R
R
R
R
R
R

R
R
R
R
W
R
R

L
L

L

R
R
R
R

L*
L
**

R
R
R

R
L

Status

D/C
0
0
0
0
0
0
0
D/C
0

0
0
0
0
0
D/C
0

0
D/C

D/C

D/C
D/C
D/C
D/C

0
D/C
D/C

0
0
0

D/C
D/C

Startup

March 1990
August 1989
August 1990
April 1990
May 1990
April 1989
March 1989
Summer 1987
June 1990
Summer 1987

March 1989
April 1989
April 1989
April 1989
Summer 1989
February 1990
April 1989

March 1989
July 1990

January 1990

Spring 1990
Spring 1990
Summer 1990
Summer 1990

April 1988
Spring 1990
Summer 1990

April 1989
April 1988
Summer 1988

May 1990
November 1989

-------
                 TABLE 1.  SUMMARY LISTING OF MUNICIPAL
                      WASTEWATER PLANTS WITH  BIOLAC
                               (Continued)

Plant
Missouri (2)
St. Louis
Excelsior Springs
New York (2)
Livingston Manor
Rock Hill
Ohio (4)
Coalton
Miami Conservancy
Frazeysburg
Lowell
Design Flow
(mgd)

4.0
2.4

0.8
0.22

0.046
4.0
0.18
0.054
Plant
Type

L
+

R
R

R
R
R
R

Status

D/C
0

0
D/C

D/C
0
D/C
0

Startup

November 1989
1985

1986
Fall 1990

Fall 1990
October 1989
Fall 1990
January 1989
Oklahoma (1)
   Durant

Oregon (1)
   Canby

Virginia (3)
   Chase City
   Fincastle
   Winchester
                           1.7


                           1.15
                           0.6
                           0.08
                           0.28
R
L
L
D/C
 0
 0
                   April  1988
                       1986
Fall 1990
   1986
   1988
    Biolac-R
    Biolac-L
    Biolac-R - Wave Oxidation Modification
    Stabilization Ponds
    Nitrification of Trickling Filter
+   Pre-aeration
0   Operating
D/C Design Construct
R
L
W
*
**

-------
                                                                      Page 4-17

presents  a  summary listing  of municipal  Biolac  wastewater plants,  current
through December 1989.  A total of 45 plants are listed,  of which  42  are R or L
configurations.  The  first  of the three other plants (Decatur, Arkansas) is a
Biolac-R plant with the Wave Oxidation Modification  for  nitrogen  removal.  The
second  (Excelsior  Springs, Missouri),  uses  the Biolac  aeration chains for
preaeration  prior  to  an overland flow wastewater treatment system.   The third
(Witchita, Kansas), will use the aeration chains for second stage  nitrification
of a trickling filter effluent.

    Of  the  42  Biolac  plants,  10  are  L configurations,  and 32 use  the  R
arrangement.  Only  5  of the Biolac L systems are currently in operation, with
the earliest startup  in April 1988;  the remaining are in  the  design/construct
stage.  Thirteen of the  32  R  plants  are  in  the  design/construct stage.  Of the
19 operating plants, most have been brought  on-line in the  past two years, with
the earliest startup in 1986 (Livingston Manor).

    Most  plants are  relatively  small,  based  on the design flow.    This is
summarized as follows for the  42  (operating and in  the design/construct phase)
Biolac R and Biolac L plants.
Design Flow
(mgd)
< 0.1
0.1 - 0.5
0.5 - 1.0
1.0 - 2.0
2.0 - 5.0
Number
Biolac R
3
11
12
5
1
of Plants
Biolac L
1
2
3
3
1
As shown,  greater  than 50 percent of either R  (53  percent)  or L  (60 percent)
plants have design  capacities  within the range  of 0.5 to  2  mgd.   Only one  of
each has a design  flow greater than 2 mgd  (both  are  4.0 mgd).  The remaining
are less than 0.5 mgd design capacity.

    Geographically,  most  plants  are  located  in  the south  and  midwest,
distributed among  14  states.   Alabama and  Arkansas have  17  of  the 45 listed
plants, all of which are Biolac-R configurations.  Of the  27  operating plants,

-------
                                                                       Page  4-18

 14  are in  Arkansas  and Alabama.   Six  of the  remaining 12  are  located  in
 moderate  climate states  (Kentucky,  Oklahoma and  Virginia).    Six  plants are
 operational in winter climate conditions  (Colorado, Kansas, Missouri, New  York
 and  Ohio),  and  only three  (Livingston  Manor,  New York;  Excelsior Springs,
 Missouri;  and  Ellsworth,  Kansas)  have  experienced  more  than  one  winter
 operation.   Thus severe  winter  operating experience  is limited at this time.

 Unit Operations  Associated with  the Biolac System

     A review of  the  plant descriptions  listed in Appendix A indicates the range
 of unit operations  included in  the process trains  of Biolac treatment plants.
 Parkson recommends  influent screening, which  is  normally  included  as  part of
 the  Biolac  System scope.   Grit removal  systems are optional and can be included
 if a large  quantity  of grit is  anticipated.  Both unit operations are shown in
 the  "typical"  system flow schemes  (see  Figure 1).

     A summary  of  unit operations associated with the Biolac system is presented
 in Table 2  (based on municipal plants  only).  Four  plants  have  no preliminary
 treatment, while  thirty-eight plants provide some  form of pretreatment;

           Bar Rack  Only                              2  piants
           Bar Rack/Screening/Grit Removal            1  plant
           Bar Rack/Comminution/Grit Removal          2  plants
           Bar Rack/Comminution/Grit Removal          1  plant
              and Primary Clarification
           Screening Only                             15  piants
           Screening/Comminution                      5  plants
           Screening/Grit Removal                     4  plants
           Screening/Primary Clarifiers               2  plants
           Comminution/Grit Removal                   1  plant
           Grit Removal                               1  plant
Twenty-seven  of  the  plants  have screening,  eleven  of which  are  traveling
screens.   Nine  plants  practice  some  type of comminution/grinding.  Ten  plants

-------
                                                           TABLE 2.  SUMMARY OF UNIT OPERATIONS WITH BIOLAC SYSTEMS
                                                                           (MUNICIPAL BIOLAC PLANTS)



Plant
Ardmore, AL
Berry, AL
Camden, AL
Cedar Bluff, AL
Clayton, AL
Columbians, AL
Hancevllle, AL
New Brockton, AL<1>
Oxford, AL
Stevenson, AL
Bay, AR
Blythevllle, AR-N
Blytheville, AR-W
Blytheville, AR-S
Maynard, AR
Piggott, AR
Colorado Springs, CO
Monument , CO
Quitman, GA
Ferdinand, IN
Remington, IN
Rensselear, IN
Cambridge, IN
Ellsworth, KS
Wellsvllle. KS
Edmonton, KY<2>
Greenville, KY
Morgantown, KY
LeSuer, MN
Hells, MN
St. Louis, MO
Fretreatment

Bar Bar Traveling Static Grit Primary
Type Rack Screen Screen Screen Grinders Chamber Clarlfier None
R X
R X
R X
R X
R X
R X X
R X
R X
R X X X
R X
R X
R XX
R XX
R XX
R X
R X
L X
L X X
L X
R XX
R X X
R X
R X
L X X
L X
R X X
R XX
R X
R X X
L X
L X
Post-Treatment
Clarification

Integral External None Aerated
X X
X
X X
X
X X
X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
X
X
X
X X
Pollshin*
Aerated/
Non-Aerated Non-Aerated

X

X


X

X
X
X
X
X
X
X
X
X

X
X



X
X








Mono







X









X


X
X
X



X
X
X
X

Livingston Manor, NY  R
Rock Hill,  NY*       R

Coalton, OH           R
Miami, OH             R
Frazeysburg, OH*      R
Lowell, OH            R

-------
                                                           TABLE 2.  SUMMARY OF UNIT OPERATIONS WITH BIOLAC SYSTEMS
                                                                           (MUNICIPAL  BIOLAC  PLANTS)
                                                                                  (Continued)



Plant
Durant, OK
Canby, OR*
Chase City, VA*
Fincastle, VA*
Winchester, VA


Bar Bar Traveling
Type Rack Screen Screen
L X
R
R
L
L X
Pretreatment Post-Treatment
_ 	 Clarification Polishing
Static Grit Primary Aerated/
Screen Grinders Chamber Clarifier None Integral External None Aerated Non-Aerated Non-Aerated
XXX XX


X
X X









d'Wetland treatment follows aeration basin.
         discharge to aquaculture pond.

-------
                                                                      Page 4-21

have grit removal, with  two  primary  clarification  plants  (these  were retrofits
of existing plants).

    None  of the  ten L  systems  have  separate  mechanical clarif iers.   Two  R
plants  have external  clarification;  the remaining  have  integral  clarifiers.
Nine Biolac-R plants do not have polishing lagoons.   Of those  that  do,  six use
fully  aerated basins,  while  the  remaining  polishing basins  are   split  into
aerated and non-aerated sections.  When  the polishing basin  is used, the trend
is  to  have this  aerated/non-aerated configuration with  new Biolac-R  systems
(with integral clarifiers), unless they  are to be  followed by  a  land treatment
process (wetlands, overland flow,  etc.).

-------
                                                                      Page 5-1
                                  SECTION 5
                       ASSESSMENT OF THE BIOLAC SYSTEM

    This  section presents  an evaluation  of  the Biolac  wastewater treatment
system.    The  discussion  focuses  on the process  design considerations  for the
system based on in-field  observations;  performance data for selected plants; an
assessment of  the  system components and related Operation  and Maintenance (0
and M);  and the costs associated  with  the installation  of  the system.

    Note that the system is relatively new; earlier discussions indicated  that
the majority  of facilities have  come on-line in  only the last  one  to three
years.  As  such, there is limited  experience, particularly with  respect  to 0
and  M and  hardware  reliability  aspects   that  are  influenced  by long-term
operations.    This  also applies  to  operating costs, which  were not estimated
within the  context  of this  report.   The  principal focus is  on  the Biolac-R
configuration since this system  is  most common and is typically  the preferred
system for new installations.

PROCESS DESIGN CONSIDERATIONS

    As discussed earlier, the approach to sizing  the extended  aeration or flow-
through lagoon  system is  somewhat  conservative  when compared  to  conventional
systems.  Table  3  compares the design parameters generally found  for extended
aeration systems and the  Biolac-R process.

    The aeration basin for the  Biolac-R system is  sized to  yield an  average
Hydraulic Retention  Time  (HRT)  of  24  to 48 hours  and a  Solids Retention  Time
(SRT)  of 30  to 70  days.    These  are greater  than  conventional design,  in
particular  with regard to  the SRT.   Food to microorganisms  ratios are  low,
ranging  between 0.03  and  0.1,  somewhat lower  than  typically  used.   The
volumetric BOD loading is 6 to 18 Ibs BODs/d- 1,000 ft3,  with a typical  loading
of 7  to  8 Ibs BOD/d- 1,000 ft3.   Figure 6  presents  actual  design loading data

-------
  TABLE 3.  MANUFACTURER'S RECOMMENDED DESIGN CRITERIA
   FOR BIOLAC-R SYSTEM IN COMPARISON TO CONVENTIONAL
                EXTENDED AERATION SYSTEMS
                             Extended(fl)
	Parameter	     Aeration        Biolac-R(k)

Hydraulic Residence          18 to 36        24 to 48
  Time (HRT), hours

Solids Retention Time        20 to 30        30 to 70
  (SRT),  days

F/M, (Ibs BOD5/d-lb MLVSS    0.05 to 0.15    0.03 to 0.1

Volumetric Loading           10 to 25        6 to 18
  (Ibs BOD5/d - 1,000 ft3

MLSS (mg/L)                  3,000 to 6,000  1,500 to 5,000

Basin Mixing                 80 to 150(c)    12 to 15(d)
   (HP/MG of Basin Volume)
(a)Reference 3
Reference 4
(c)Mechanical aeration
(d)Manufacturers data for mixing only

-------
n
4.5



  4 -



3.5 -



  3 -



2.5 -



  2 -



1.6 -



  I -



0.5 J



  0
                                                     D
                                                                               o
                                                                DESIGN LOAD
                                                                975 #BOD/MG
                              I                  2
                                            (Thou* and*)
                              BOD LOAD (THOUSAND POUNDS /DAY)
-r

 3
                   FIGURE 6.  BIOLAC-R PLANT DESIGN - AERATION BASIN LOADING.

-------
                                                                        Page 5-4
  for  25 Biolac-R plants; the mean design loading was 975 Ibs BOD/d-MG equivalent
  to 7.3 Ibs BOD/d - 1,000 ft3.  The polishing basin of the R system is typically
  sized for an HRT of 12 to 24 hours.

     Design sizing  for the flow-through  lagoon  system (Biolac-L)  is  typically
 based on  hydraulic  residence time.  An  HRT of 6  to  20  days is used,  whereas
 conventional design sizing would use a  3  to 10  day HRT.   The  Biolac-L polishing
 basin is typically designed to provide an equivalent loading of 0.5  to  1.8  Ibs
 BOD/d -  1,000  ft3,  which  generally results in an average HRT of one  to  two
 days, and greater than 10  years  capacity  for sludge.

     The Biolac  aeration system  sizing  is based  on the  assumption that full
 nitrification will be  accomplished.   The  manufacturer recommends 1.5  Ibs oxygen
 per  pound of  BOD5  removed  and  4.6 Ibs  of oxygen  per  pound of available
 nitrogen.   The  rated  transfer  capacity for  the Wyss  diffusers  under standard
 conditions,  in  clean water  is between 4 and  5 Ibs 02/hp-hr.

    At the  typical  design  loading,  the  air  required  to satisfy  oxygen
 requirements  is  higher  than that  required for mixing.  Thus the aeration system
 can be  turned  down  during nightime,  weekends,  and/or  the  initial  years  of
 operation  at  lower  loadings,  while  still maintaining mixing.  This provides a
 large  degree  of flexibility and  energy savings  with this  type  of  system when
 compared to conventional fixed aeration equipment.

    The  total number  of diffusers  is determined by dividing the  required air
 flow  by  the normal design  air flow  per  diffuser.   This  is  typically 2  to 4
 scfm/diffuser for  the  Wyss units.   The number  of aeration chains,  floats per
 chain, diffusers/float  are then  determined for the  specific application.   A
 typical aeration chain spacing of 8 to 30  feet for Biolac-R plants and up to 30
 to  50 feet  for Biolac-L  plants  is used,  above  an  unsloped  basin bottom.
 Parkson recommends keeping all diffusers at the  same elevation for the simplest
 installation and operation.   Figure 7 presents  a summary of  the  actual  number
of  diffusers  used for  the  design  of 25  Biolac-R  plants.    The  mean was  385
diffusers per million gallons basin volume.  This  is equivalent  to  an air  flow
of 1,350 scfm/MG at  3.5 scfm per  diffuser.

-------
4.B
I
n
o
P
3.8 -
  3 -
2.8 -
  2 -
1.8 -
  1 -
0.8 -
                O
             0.2
                        D
DIFFUSERS
385 /MG
AIR FLOW
1350 scfm/MG
@ 3.5 scfm/DIFFUSER
                                                                               D
0.4       0.6       0.6
              (Thousand*)
      NUMBER OF DIFFUSERS
         1.2
                                                                                 1.4
            FIGURE 7.  BIOLAC-R PLANT DESIGN - DIFFUSERS/AIR FLOW.

-------
                                                                      Page 5-6
    The  minimal requirement  for mixing and  effective solids  suspension is
approximately 3  to  4  scfm/1,000  ft^  of basin volume using the Biolac aeration
chains.   This  is  equivalent  to approximately  12  to  15  HP/million gallons.
Figure 8 presents data showing actual operating HP at 25 Biolac-R plants.  The
mean was approximately 45 HP/MG;  note that these  plants were typically at 50 to
70  percent of  their  design  loading.   This  still compares  favorably  with
conventional fixed aeration systems which require up to  100 HP/MG basin volume.
Thus, whereby aeration HP in extended air systems  is  generally  set by mixing
requirements for fixed aeration  systems, the  Biolac aeration  system sizing is
typically  set  by oxygen  requirements,  resulting in significantly  less power
input than required for conventional  systems.

    For  the  R  system,  an integral  clarifier  is normally provided to effect
solids  settling, and an  optional  aerated/unaerated  polishing basin  can be
provided.   The  polishing basin  is  not considered a  requirement  to achieve
secondary  effluent limits,  but  can  provide  additional polishing  for solids
removal.   Clarifier  design  rise rates  (overflow)  range  between 200  and 800
gpd/ft2, with  400  gpd/ft2 being  used most  often.   For the  L system, solids
settling  is  accomplished  in  the quiescent  settling  zone established  in the
unaerated section of  the polishing basin.    The  design is typically  for a 24
hour  detention  time  in  this  zone.    This  is common  for the  aerated lagoon
process.

BIOLAC SYSTEM TREATMENT PERFORMANCE

    Most Biolac plants have been operating a  relatively short time  and as yet
have not reached design  flows  or loads.  Additionally, many  plants are small
and permit sampling requirement  are  not extensive,  thus minimal data has been
collected.   The response to a  request for  data  was  good;  approximately 75
percent  of  the  domestic  plants  on-line  responded  with information.   In many
instances,  however,  the data were  limited,  often representing  monthly or
twice/month sampling.   Additionally,  several plants  do  not monitor the
influent, and  the  24  domestic plants  that  were  on-line, only 9 were on-line
longer than one year.

-------
s
2
*
a
I
4.5


 4 -


a.5-


 8-


2.5-


 2-


U-


 1-


0.5-
                  B
                                                POWER USAGE
                                                45 HP/MG
              -i—i—\—i—i—i—i—i—i—i—i—i—i—i—i—i—r-
               20    40    60    ft)    100    120    140    ISO    IftO

                                OPDUTINGHP
                                                              200
       FIGURE 8.  OPERATING BIOLAC-R PLANTS-POWER USAGE.

-------
                                                                       Page  5-8
     Performance  data  summaries for 13 plants are presented in Appendix B.  All
 but one (Fincastle,  Virginia)  are  R  plants.   In all cases, and  in  discussions
 with other Biolac plants,  the  facilities  were in  full  compliance  with  their
 permit  requirements.   Table 4 summarizes  these  data,  presenting the averages
 for the different performance periods  at  each plant.    Note  that the initial
 months  of  start-up  data  were excluded  from these  averages.   The  average
 effluent  BOD  ranges  from 5.1 to  20.8 mg/L;  the  average removal  (for  those
 plants  for which influent  data  were available)  ranged  between  91.1  and 97.9
 percent.

     The average  effluent  TSS  concentrations  ranged  between 6.7 and 34.8  mg/L;
 the average removal ranged between 86.3 and 95.7 percent.  Ammonia levels were
 typically  less than  7 mg/L in  the effluent,  except for higher  levels  in the
 Bay, Arkansas  and two Blytheville,  Arkansas plants.  It is  suggested that  these
 were influenced  by  high incoming  ammonia  concentrations  due  to  farm
 fertilization  and high infiltration into the  sewer collection system.

 EQUIPMENT

     Since the  initial installations in 1985,  design  and materials modifications
 have been  made on a  continuing  basis,  reflecting operating experience  at an
 increasing number of plants.   Problems that were identified related to hardware
 components and  materials of  construction,  ineffective maintenance,  and
 inefficiencies in operation.  The following discussions  summarize the problems
 noted by the operators and present  how they have or are being addressed.

    Table 5 summarizes the types of problems encountered by the various plants
 that were  interviewed  and/or  visited.   Plants that reported  the problems are
 also shown, if possible.   Finally,  resolution of the problem,  if there is one,
 is also discussed.

Aeration System

    The floating chain  system  is assembled  in the  field.   Problems  were
 reported primarily by early Biolac plants,  and related to the  diffusers,

-------
                                       TABLE *.  SUMMARY OF AVERAGE PERFORMANCE DATA FROM SEVERAL BIOLAC SYSTEMS
Plant
Name
Morgantown HWTP
Morgantown , KY
Greenville WHIP
Greenville, KY
Hew Brockton WHIP
New Brockton, AL
Edmonton, WWTP
Edmonton, KY
Fincastle WWTP
Fincastle, VA
Lowell WWTP
Lowell, OH
Hanceville WWTP
Hancevilla, AL
Livlnston Manor HWTP
Rock land, NY
Blythville Heat WWTP
Blytheville, AR
Blrthevlll* North WWTP
Blytheville, AR
Blytheville South WWTP
Blytheville. AR
Bay WWTP
Bay, AR
Plggot WWTP
Flggot, AR
Influent Effluent I
Period of Flow BOD BOD BOD Loading
Performance Type (MOD) X Design (mg/1) (ma/1) Removal (Ibs BOD/dayJ
4/89 to 9/89 R 0.29 58.0 243 12.7 92.3 575
5/88 to 8/89 R 0.40 55.3 178 6.2 96.5 528
6/89 to 8/89 R 0.05 27.8 233 8.7 95.5 111.5
7/89 to 11/89 R 0.2 39.2 203 11.6 91.1 185
9/88 to 8/89 L 0.05 62.5 218 18.6 91.2 86.9
7/89 to 9/89 R 0.11 20*. 186 13.3 91.8 167.0
6/89 to 9/89 R 0.5 87.8 134 9.7 92.0 514.0
6/86 to 8/89 R 0.5 62.5 260 5.1 97.9 1,062.0
7/89 to 10/89 R 0.39 26.0 ND 7.6
4/89 to 10/89 R 0.39 48.8 ND 13.8
4/89 to 10/89 R 0.60 42.8 ND 15.1
6/89 to 9/89 R 0.27 180. ND 10.4
6/89 to 9/89 R 0.35 58.0 ND 20.8
Influent Effluent X Effluen'
TSS TSS TSS NH3-N
(mjt/1) (nut/1) Removal (mg/1)
188 11.7 95.7 0.1
213 12.4 94.7 0.5
257 10.7 94.4 1.9
266 18.4 89.5 3.2
190 21.5 89.7 ND
172.0 26.0 86.3 6.7
97.8 9.0 92.0 0.8
217.0 8.7 95.3 1.9
ND 14.9 - 2.2
ND 26.3 - 26.0
ND 18.1 - 30.9
ND 6.7 - 11.3
ND 34.8 - ND
ND:  No data provided

-------
                                       TABLE 5.   PROBLEMS IDENTIFIED AT VARIOUS BIOLAC PLANTS
                   Problem
 Hardware/Materials Related

   Wear on chain restraining cables
     and rake cable
                                                     Plants Reporting Problem
 Excelsior Springs; Livingston Manor;
   Ellsworth;  Morgantown
   Corrosion of hardware pieces                 Livingston Manor;  Durant;  Excelsior
     (bolts, clamps,  cable,  connecting pieces)     Springs;  New Brockton
   Loosening of diffusers,  other parts
 Livingston Manor;  New Brockton
                                                                                                          Comments
 Chain material changed to stainless
   steel or chrome plated steel;  replacement

 Materials changed from galvanized to
   stainless steel;  replacement
 Diffuser/Aeration System

   Diffusers blowing off frame

   Diffusers clogging


   Reduced  diffuser life

   Excessive blower noise


   Blower Filters
 Livingston Manor;  Morgantown             Installation;  replace  clips

 Livingston Manor;  Durant                 Loosening  diffusers; improve  clip,  increase
                                            flexing  maintenance

 Livingston Manor;  Morgantown;  Ellsworth   Installation;  improves  flexing maintenance

 Blythville;  Bay; Columbians
                                               Blythville
                                          Install  in  separate buildings;  improve
                                            silencer  design

                                          Excessive dust; Install screens; frequent
                                            replacement
Clarifiers

  Rake motor


  Rake limit switches and float overtravel
Ranceville; Hew Brockton; Decatur
                                               Berry; Hanceville; Edmonton;
                                                 Morgantown; Lowell
Undersizing  and problems  relating to float
  over  travel; replace

Modify/replace switch with  Improved design
Sludge Withdrawal

  Air lift pump clogging
Lowell; Greenville; Bay
                                                                                        Improve  solids removal (screening)  upstream;
                                                                                          increase maintenance of lift line;  improve
                                                                                          suction line design; increase opening sice
Process Related

  Excessive debris/clogging and
    floating sludge

  Air distribution
Lowell; Greenville; Bay; Morgantown
                                               Excelsior Spring;  Morgantown;
                                                 Livingston Manor
Improve prescreening; sludge suction line;
  rake cable and limit switches

Relocate aeration chains; increase density  of
  diffusers; Increase maintenance (flexing);
  move aeration chain away from clarifier
  curtain
  Excessive Oil/Grease in Clarifier
Berry; Columbiana; Hanceville;  Piggot    Vacuum surface;  install skimmers

-------
                                                                      Page  5-11
diffuser/counterweight  assembly  and air distribution.   These  centered on  the
corrosion  of  floats  and  anchoring  cables.   The  floats  were  initially
manufactured with integral galvanized air pipe and eye bolts on the end floats
for cable connections.  These problems have been corrected by utilizing an  all
polyethylene float construction.

    The limited number  of plants which reported float corrosion problems also
commented on  corrosion problems  with  the  anchoring  cables.   Originally,  the
aeration chain was 304  stainless  steel, 3/32 inch diameter, wire cable, with  6
to 8 feet of link chain at the end to allow for tension adjustment.  The cables
had  shown  excessive  wear  in  the  area  where the  cable  dipped  into  the
wastewater.   The restraining chain has since been changed to an all link  chain
design of  3/16  inch  diameter  plated steel.   Surface rusting  of  the  new
restraining  chain still  occurs,  however,  although  this does not  effect  the
structural integrity of the restraining chain.   The manufacturer is considering
a  change  to all stainless steel.   The Livingston Manor WWTP  has  had success
using nylon rope for restraining  the floating aeration chains.  The nylon rope
is lightweight  and has  the ability to stretch,  therefore  it  stays  out of  the
wastewater.   The rope remains dry and ice-free  in winter.

    There were relatively few diffuser problems, and overall, there was a high
degree of  satisfaction with  the Wyss  diffusers.   Problems  included  diffuser
sheaths blowing off  their frames and shorter  than expected  diffuser  life.    A
diffuser can come off entirely; more often it would become unseated at one  end
due to clamp  failure,  when  either  the clamp  was  improperly installed and/or
tightened or  the  clamp  corroded.   Both conditions  have been resolved.    The
clamp material must be  stainless steel (which is the  manufacturer's standard)
and should  be  tightened  thoroughly during  installation.   If the  clamp is
allowed  too much  freedom of  movement it  can slip  as  a result  of  diffuser
flexing,  causing the  diffuser to  unseat.

    Shortened diffuser  life  has  been reported by a  few  plants.   The cause is
not immediately apparent at each, but it can be due to several factors.  If  the
clamps are not properly tightened, sludge can enter the  diffuser and be forced

-------
                                                                      Page 5-12
 into the aeration aperture,  causing the sheath to clog.  A diffuser will  also
 gradually lose  its effectiveness  if the apertures  remain  enlarged  for  extended
 periods  of time  to  the  point where they can  not  return  to their normal  size
 when uncharged.   This is due  to  overcharging  the  diffusers  (i.e. operating
 above  recommended air flow  range)  and can result  in uneven air  distribution
 across  the diffuser.  The  large bubbles that  result  from the enlarged holes
 reduce  overall  aeration  transfer efficiency.    If the diffuser  holes become
 enlarged from  extended stretching of  the  diffuser  sheaths,  an additional
 problem  can occur.  When the system is not charged with air the normally closed
 apertures  can  remain open  and wastewater/sludge can enter the diffuser by  the
 pressure  exerted  from the liquid head.

     The  manufacturer  suggests  that  a  diffuser life  of  five  years  can be
 expected under  normal conditions.   The  key  to  achieving  this  is  regular
 diffuser flexing,  as  described  in the  operations manual provided  for  the
 aeration chain  system.   This  involves shutting the air off  in a chain,
 depressurizing  the  diffusers  by  bleeding the  air and causing the  diffusers to
 collapse.  The  air is  then turned back on,  expanding the  diffuser sheaths.  A
 one  week frequency is recommended  for  flexing.   A review of operating plant
 data indicates that the procedure varied,  with  only a third following a routine
 schedule.

    An equally  important  point  is that the  diffusers  not be  overcharged.
 Normal operating  air  flow  is between one and  five  scfm/diffuser.   Increasing
 the  air  supply pressure and  operating  above   the  upper boundary  continuously
will  likely result in  enlarged apertures,  if not  torn  diffuser sheathes.
 Pressure  settings  and  relief valves on the air  system  can help  minimize this
 type of problem.

    Two  plants  reported  air  distribution  problems unrelated to  faulty
diffusers.  They have been  noted  near  the  clarifier and  also along  the  diffuser
chains themselves.  Solutions have  included utilizing side chain floats in  the
basin corners and locating air headers at both ends of the aeration chains.  A
six  inch  diameter aeration  chain option has  recently been developed.   This

-------
                                                                     Page 5-13
enables a  greater volume  of air  to  be delivered  at  a lower  pressure loss,
reducing the potential for uneven air  distribution to the individual chains.

    Few problems were reported concerning  the  blowers.   Excessive noise was a
primary complaint.  The manufacturer has addressed this by providing silencers
with  improved  noise attenuation.   Several plants  do  not house  their blower
equipment within  fully  enclosed  structures to  contain the noise.   Plants in
Piggot and Bay, Arkansas housed the blowers in  structures which had one  or more
open sides.   The plants  are located in areas where the  surrounding land  is flat
and largely  unwooded;  thus  the  noise  is  not readily  contained  by  either the
structure,  or absorbed by hills and/or forested land.

    Another problem was  identified with  regard   to  the  silencers,  and
difficulties in keeping the silencer filters clean.  The problem was especially
difficult for  plants  located in  farming regions.   Bugs,  dust and other debris
from planting  and harvesting  operations (large quantities of cotton fiber were
observed in  Arkansas)  clog the  silencer  air  filters  quickly.    At  the
Blythville,  Arkansas plants  (North, South  and West) the silencer housings were
fitted with fine screens around their  peripheries, resulting  in greatly  reduced
maintenance needs for the silencer filters.

Sludge/Solids Removal Systems

    Several  problems were noted  with the  clarification and  sludge  removal
systems  in  the Biolac  R  plants.   A  number  of problems  with  the clarifiers
centered on  the mechanical operation of the rake  drive  motor,  limit  switches
and the air  lift  sludge pumping  system.  The L systems provided  sludge  storage
times of 10 to 20 years in the polishing basin;  with only  3 plants in  operation
for less than 4 years, problems have not been encountered.

    Figure 9 illustrates the limit switch/drive cable  assembly for the integral
clarifiers.   A two  limit  switch assembly  which  allows the motor to  slow  down
before starting off in  the opposite direction  is shown.  The flocculating  rake
mechanism,  used for sludge distribution and concentrations,  is suspended from  a

-------
                                                              Poke Motor
                                                              Drive
    Torgct  ( 1 eoch top £ bottom coble)
Motor Control Switches
  FIGURE 9.   INTEGRAL  CLARIFIER RAKE MOTOR AND CONTROL  SWITCHES.

-------
                                                                     Page 5-15
 float  similar  to  the  floats  used to  support  the diffuser/counterweight
 assembly.   The  rake float is attached to a drive cable which  is pulled back and
 forth across  the clarifier by the rake drive motor.   Directional control of the
 motor is accomplished through  the use of a limit switch which is tripped by a
 target attached to the drive cable.

     Plant  operators have reported difficulties  due to the improper engagement
 of the target and the switch.    When  this  occurs,  the rake  is not stopped nor
 sent back  in the opposite direction, and  the rake  float eventually runs into
 the  limit  switch and  drive unit,  sometimes resulting  in the destruction of the
 floats.   A redesigned  limit  switch with modified upper and  lower  cable trip
 arms eliminates improper switch engagements;  an  evaluation of  their use was not
 possible.    Plant  operators  had  reported successfully modifying the  old
 switches;  one added a  PVC collar to increase the  target size,  while  another
 modified the  trigger arm by simply bending the trigger wire.

     Another clarifier system  problem was identified with the performance of the
 air  lift  sludge pumping system.   This centered on clogging of the  piping,
 resulting   in a reduced sludge return rate  and  a solids buildup  in  the
 clarifier, with subsequent  downtime  for unclogging  the  system.    Several
 contributing factors  were  identified  including the  lack  of  effective
 pretreatment screening at the head of the plant,  lack  of maintenance of the air
 lift  system,  and the air lift suction line design.   The Biolac system does not
 include primary clarification as a standard unit operation.   Without this,  the
 plant must  rely on  the  effectiveness  of its pretreatment  operation  for  large,
 potentially clogging solids removal.

    Communition  is  not  recommended  because  of the tendency for  comminuted
materials  to  mat  together  in  the  aeration  basin, resulting  in clogging
problems.   Nine of the plants  use  some form of  comminution.    Screening  is
recommended  as  a  necessary pretreatment  for  most  domestic  applications.
Screening can be accomplished by either  racks  or screens.  The size  and amount
of coarse  solids removed by each varies greatly.  A  simple bar  or  travelling
screen can retain particles four  times  smaller than  the  typical bar  rack with

-------
                                                                       Page 5-16
 one  inch  clear openings.   Generally, a  review of  the  plants indicated  that
 those plants  without or with minimal  screening encountered difficulties  with
 clogging.

     While  there is no recommended approach to sludge suction line maintenance,
 one  operator  reported a program that involved  flushing the  line  monthly  to
 remove any debris  that may  have  accumulated.

     The  manufacturer has been investigating  suction line design modifications
 for improved sludge  removal.  The utilization  of tapered suction line, and/or
 varying  hole size  and spacing has been  studied to equalize velocities along the
 length of  the sludge hopper.  Increasing  the hole  size (1.5 inch is standard)
 would reduce clogging and with improved hole spacing would minimize dead spots
 where sludge can  accumulate,  gasify and float.   A pipe is now included  that
 extends  from one  end of the suction  line to the  surface,  providing cleanout
 capability.

     The  fraying of the rake drive cables and floating  sludge  are  two problems
 that can occur as  a  result of a  malfunctioning  limit switch or a  clogged air-
 lift sludge  system.    The  rake  drive cable  material has  been changed  from
 stainless   steel  to  plastic  impregnated  galvanized  steel to reduce  cable
 fraying.

     Floating  sludge   in the  clarifier  may be attributed  to inadequate  sludge
 removal  or air leaking into the  clarifier  from the aeration chain  closest to
 the  integral  clarifier.   Breakdown of  the flocculating rake or sludge  removal
 operation  will  allow  sludge to  remain in the clarifier for  an  extended period
 of time,  resulting in gasification and subsequent floating sludge.   Sludge will
 also float to the  surface if air  from  the  aeration  basin  enters the  clarifier.
 This  is  prevented  by locating  the  last aeration  chain a sufficient  distance
 from the clarifier curtain wall and  limiting the chain  oscillation range.   Air
 flow to this chain may also be  throttled back.

    Operators  have reported the need to  manually  skim  floating  sludge  and
greases in the integral clarifiers.  The manufacturer is  currently designing  a

-------
                                                                     Page  5-17
mechanical skimmer and incorporating scum baffles  for  most  new Biolac  systems.
Better platform access across the clarifier is also being provided.

    Rake drive motor  troubles  resulted  from  undersized motors or the lack  of
delay timers.   Larger motors  have  replaced undersized units  and delay  timers
have been installed on the  rake drive motor which allows the motor to slow down
before changing its direction of rotation, and reduces the strain on the  motor.

Polishing Basins

    The polishing basin provides  additional BOD  and TSS removal,  and acts as a
backup  for  additional  solids removal when high hydraulic variability  is
encountered,   reducing the  efficiency  of  the  integral  clarifiers.    Plant
operators have  reported  significant  algae growth in the basins, resulting  in
large swings in polishing basin dissolved  oxygen, poor basin appearance,  excess
effluent suspended  solids  and  reduced performance  of the  disinfection
operation.  One plant reduced  the  algal discharge  by   submerging the effluent
intake pipe two  to three feet below the water surface.  In response  to these
concerns, the  hydraulic  retention  time  in the polishing basins  has also been
reduced from 36 to 48 hours to 12 to 24 hours so that proper operation will  be
maintained,  even at lower than  designed  flow rates.

    System staging has recently been utilized by Parkson, in which  two or more
smaller  sized  aeration basins  are  installed, as  opposed to  one large  basin.
This can be beneficial in  cases  in which the  initial  flow  or  loading will not
approach design capacity for some  time.   The  second basin  can be by-passed or
operated at a low aeration rate,  thus reducing the  operating costs.

BIOLAC COSTS

    Data received  from the manufacturer on total capital construction cost for
several Biolac plants  are  presented on  Table  6.   Cost of land, which can vary
considerably  and   is  a  key  consideration  in selecting  the  aerated
lagoon/extended aeration  treatment technology,  is not included.   Equipment

-------
TABLE 6.  BIOLAC SYSTEM CONSTRUCTION COSTS
Proiect
Stevenson, AL
Blytheville , AR
(3 Plants 1.5,
Greenville, KY
Columbiana, AL
Camden, AL
Hanceville, AL
Oxford, AL
Camden , AL
LeSeur, MN
Goodwater , AL
Cedar Bluff, AL
Bid Date
September 1986
November 1987
1.4, 0.8 mgd)
July 1987
November 1987
June 1988
February 1988
July 1988
July 1989
October 1989
November 1989
December 1988
Design
Flow (gpdl
750,000
3,700,000
740,000
750,000
220,000
570,000
2,000,000
540,000
900,000
150,000
500,000
Design
BOD (mg/L1)
400
250
350
200
225
175
225
225
440
200
220
Contract Price
$680,000
3,048,000
977,000
1,100,000
355,000
1,019,000
2,193,000
799,000
1,900,000
640,000
695,000
$/gpd
0.90
0.84
1.32
1.46
1.61
1.78
1.10
1.48
2.11
4.25
1.39

-------
                                                                     Page 5-19
costs, including the Biolac aeration chains,  integral clarifier and air blowers
and piping  are  approximately 20 percent of  the  total  cost  for plants greater
than  0.5  mgd,  and up  to 30 percent or  more for smaller plants.   An average
estimated capital cost for plants greater than  0.5 mgd  is in the range of $1 to
$1.5 per gallon per day of design flow  for a  typical municipal wastewater.  The
smaller  plants  have  a somewhat higher  cost rate,  as do plants  with  higher
concentrations  of BOD  (due  to industrial wastes).   Reported  costs  are
contractors  bid  prices  to  build the  complete  plant  and  also include
pretreatment facilities, pump  stations,  sewers,  roads  and buildings which are
variable with specific projects.

    Operating expenses include labor, power and maintenance supplies, and will
vary  with prevailing  rates  in  the plant location.   As  discussed earlier,
aeration power can be  controlled through the operation of  the blowers;  since
basin  mixing is  achieved  at  power levels  generally  less  than  required for
adequate oxygenation,  basin dissolved  oxygen levels  can be used  as a control
parameter, and power  usage kept to a minimum.  Operation of these plants is not
highly labor intensive.  Depending upon plant size and  monitoring requirements,
it was  reported that  only one  to  two  full  time  or  part-time personnel are
typically  required  for  operation and maintenance.    At  this  time,  there  is
minimal data available  on actual operating costs and  estimates have not been
made within the  context of this report.

-------
                                                                       Page 6-1
                                   SECTION 6
                               SITE OBSERVATIONS

 INTRODUCTION

     Six plants were visited to observe operations.   The Livingston Manor WWTP,
 located in Rockland, New York was visited  September  25,  1989,  and five plants
 located in the northeast corner  of  Arkansas were visited November  15  and 16,
 1989.   These site visits provided the opportunity to  inspect both old  and new
 equipment,  in retrofit  and non-retrofit  plants.   The  following  discussion
 summarizes observations  made at  the  plants, and includes photos appropriate to
 this  assessment.    Note  that plant performance data  for each  facility  may be
 found  in Appendix B.

 LIVINGSTON MANOR WWTP, ROCKLAND, NEW YORK

    The  Livingston  Manor WWTP serves  a rural  community  located approximately
 100 miles  northwest  of New York City.  The plant treats an influent flow of 0.5
 mgd.   One-third of  the  total flow is  a pretreated poultry processing waste and
 the remaining  two-thirds  is  municipal waste.   It  was  among the  first plants in
 the United States to employ the Biolac system.

    The  influent flow passes through a comminutor or a set of bar racks.   After
 screening,  grit  is removed prior to  biological treatment.   The  biological
 treatment  of the  waste  is accomplished in two aeration basins  in  series.   The
 basins  are  lined  earthen  pits  and  are  followed by  two  40-foot circular
 clarifiers which  provide clarification prior  to  discharge.   Lime addition is
 provided at  the head  of the  plant  to  maintain  the  alkalinity  level   in  the
 biological processes.

    The  plant  was  retrofitted  with the Biolac  floating  aeration  chains  in
November  1986.   The plant  had  previously  used coarse  bubble  static tube

-------
                                                                      Page 6-2
   •i
aerators since  upgrading  to an  activated sludge plant  in 1977.   The static
tubes  were  replaced  because of  hardware  failures which had  necessitated
rebuilding the  aeration system  in  1981,   and  finally  replacing  it  with the
Biolac system in 1986.  The retrofit was completed in approximately one month,
while the plant continued  to operate  as  a  secondary treatment facility.

    The  plant staff  consists of  the  superintendent,  two assistants  and an
administrative secretary,  responsible for  both the water  and sewer  departments.
Process  monitoring  is performed  daily.    Other  0 &  M  includes routine blower
maintenance/cycling and visual inspection  of  the  aeration basins.

    The  retrofit of  Livingston  Manor WWTP  proved  beneficial.   All  effluent
characteristics showed modest improvements while  60 percent less  horsepower was
needed.  More complete  nitrification was  achieved after  the retrofit.   Studies
were conducted by Parkson, which confirmed that  the  system, at 6000 mg/L  mixed
liquor suspended solids was completely mixed, at  an air  flow of 3 to 4 scfm per
1,000 cu ft.  of basin volume.  This  is  roughly one-fifth to one-eighth the air
required with fixed diffused air  systems to achieve adequate mixing.   Operation
at  the  high  MLSS  level  causes  some floating  sludge  in  the  aeration basin,
although this has apparently not  caused  process  related  problems.

    At  the  time of the site visit some  of  the  original  Biolac  equipment was
being  replaced.   These  included deteriorated restraining  cables  and  badly
corroded galvanized  air  pipes  and  eye  bolts.   Loose  and  corroded clamps
(stainless steel clamps had not  been supplied) were  responsible  for improperly
functioning  diffuser  sheathes, many  of  which were filled with  sludge.  Some  of
the  restraining  cables had  been replaced  by  nylon rope,  which appeared  to
function adequately.   The  nylon  rope's  ability  to stretch  kept it from dipping
down into the wastewater during  the chain's oscillation.  Despite the equipment
problems the system  has performed well,  as  evidenced by  the  performance data
presented  in Appendix  B.    Removals  have  averaged 87.9  percent  for  BODs, 94.5
percent  for  TSS, 91.9 percent for TKN, and 84.5 percent for NH3-N.

-------
                                                                      Page 6-3

Livingston Manor STP/Photograph Description

    Refer to Figures 10 and 11:

A.  Lined earthen basin equipped with Biolac floating aeration chains.  Middle
    aeration chain which  is  suspected  to have  diffuser problems due to uneven
    air distribution,  as  evidenced by  the large areas  of bubbling around the
    2nd and 9th floats.

B.  Two diffuser assemblies with loose  air clamps.   Clamp in the middle of the
    picture was missing its screw while  clamp in the upper left hand corner was
    severely corroded.

C.  A  diffuser  which was sliced open  lengthwise  revealed  a  significant
    accumulation of sludge within the diffuser.

D.  Picture  illustrates  the  benefit   of the  nylon  anchoring  line.   Nylon
    (foreground) stays out of water;  therefore,  does not accumulate debris.

BAY WWTP,  Bay Arkansas

    The Bay  WWTP serves  the  rural community  of Bay,  Arkansas,  receiving 100
percent domestic waste flow.    This is  a new Biolac-R  type plant.  Although the
design average  flow  is 0.15  mgd,  the actual  flow since start-up has been 0.27
MGD.   The  plant was installed adjacent to the  original plant  and was put on-
line in March  1989  after  about a  one year construction period.   The original
plant was an unaerated flow-through lagoon, which now  serves as the new plant's
sludge storage pond.

    At the head  of the plant,  influent  screening is  provided by a pair of bar
racks with 0.5  inch  openings.  After screening, the  influent  is brought into
the  aeration  basin  via   two influent pipes  to affect better inlet  flow
distribution.  The waste  is  then treated biologically in a 0.3 million gallon
aeration basin equipped with  Biolac  floating aeration chains.   The solids are
settled in an integral clarifier.   The  clarified effluent  is treated further  in
a polishing basin,  with a  detention time of one  day at the average design flow.

-------
FIGURE 10.  LIVINGSTON MANOR PHOTOS A AND B.

-------
FIGURE 11.  LIVINGSTON MANOR PHOTOS C AND D.

-------
                                                                       Page 6-6

 The  basin is  divided  roughly  in half by  a  floating  curtain.   The  first section
 of the  basin  is  aerated  while the  second section  is unaerated.  After  effluent
 polishing,  the waste  is  disinfected by chlorination.  The plant staff  consists
 of the  plant  superintendent and one assistant,  while three  other town employees
 are  made  available to the plant as needed.

     The original plant  interview  revealed  few problems,  and  all of  them  had
 been resolved satisfactorily.   Problems with  the  rake drive motor had  been
 resolved  by the  installation  of  an additional limit switch,  which  acts as  a
 delay,  allowing  the  motor to slow down prior  to  changing  its  direction  of
 rotation.   The plant  also  had floats containing galvanized air pipe. There  was
 no visible  evidence of corrosion,  although the plant was on-line for  only  six
 months.   The  restraining chains showed signs of slight surface corrosion.   Due
 to economic  considerations,  the  blower assembly was not contained within  a
 fully enclosed structure  nor was  a spare  purchased.

     Plant  maintenance   consists of  regular blower maintenance   as  per
 specifications;  bar  rack  cleaning twice  daily;  daily  floatable skimming  of
 basins  and  clarifiers;   routine diffuser flexing;  (rake) and  air lift  sludge
 system  cleaning  using the  town sewer  cleaning  truck approximately every three
 weeks.    Daily process  monitoring includes  dissolved  oxygen,   pH,  chlorine
 residual  and clarifier  sludge  level.   August and  September,  1989  effluent
 results show the  plant to be performing very well  (see Appendix B).

 Bay WWTP Photograph Descriptions

    Refer to Figures 12,  13, 14 and 15:

A.  Influent to effluent  view of  the Biolac System.  Aeration basin foreground,
    integral clarifier in back of the  aeration  basin and  the polishing  basin in
    the background.

B.  Closeup of the anchoring system and header  assembly.  Chain length  controls
    the aeration chain  tension and subsequently  the aeration chains  lateral
    range of motion.   Air header  assembly includes a butterfly  valve  (large

-------

FIGURE 12.  BAY, ARKANSAS PHOTOS A AND B

-------
FIGURE 13.  BAY, ARKANSAS PHOTOS C AND D

-------
                                                    -It*
FIGURE 14.  BAY, ARKANSAS  PHOTO E

-------
FIGURE 15.  BAY, ARKANSAS PHOTO F

-------
                                                                      Page 6-11

handle)  for  air flow  control and  an  air  bleed valve  (smaller handle)  for
unchaining the aeration chain.

C.  Side  view of the  integral clarifier consisting  of  2 concrete  sidewalls,
    concrete  backwall  (basin  backwall)  and  a floating curtain on  the influent
    side.  Also note the corner float which is typical of the later designs.

D.  Picture looking  across  the integral clarifier:   baffle  wall on  the  left;
    float and drive  cable supporting the flocculating  rake  in the middle  and
    the effluent weir on the right.

E.  Picture of the airlift sludge system consisting of:   air  compressor (middle
    foreground) ;  air  lift sludge  pipe  (vertical pipe just  to the left of  the
    rake  drive motor);  gravity flow sludge  line  (pipe  running back  along  the
    concrete walkway) and the sludge control  box.

F.  Picture  looking  across  the  length of  the  floating curtain  wall in  the
    polishing basin.

PIGGOT WWTP, PIGGOT,  ARKANSAS

    The Piggot WWTP in Piggot, Arkansas  was  designed to handle an average  daily
flow of 0.6 mgd.   The influent is  100 percent domestic wastewater,  and the flow
to the plant  is  currently about 0.35 mgd.   The plant was put  on-line in  April
1989 after about six  months  of plant construction.  An unaerated  flow through
lagoon was  previously used for treatment  of the  town's  wastewater;   this  now
serves as a storage lagoon for storm flow.

    At the head of the plant,  screening  is provided by an Aquaguard^M  traveling
screen,  manufactured  by  Parkson.    The influent   flow  is then  measured  by  a
Parshall  flume  prior  to biological  treatment.    Biological  treatment  is
accomplished  in  a  0.95  million  gallon aeration  basin, followed  by solids
clarification in two  integral  clarifiers.   Clarified effluent then flows  into
the polishing basin,  with subsequent disinfection by by ultra-violet  light.

-------
                                                                     Page 6-12

    The plant supervisor/operator performs  essentially all plant operations and
maintenance.   One helper is available about one-third of  the  month to assist
with  plant  chores,  and  an additional town employee  is provided  to  perform
weekend systems checks.  A visual inspection of all systems is performed daily.
The screening device  is  cleaned automatically and  the  screenings  are disposed
of as  needed.   The clarifiers  are skimmed  daily  of floatables  and blowers are
checked  twice  per  week.   The  UV system  is  cleaned weekly  while other
miscellaneous maintenance  (i.e.  spraying down  equipment) is  performed  as
needed.   Diffuser flexing has been  performed  on a  weekly basis.   Process
monitoring is performed  three  times per week and  includes  basin MLSS and SVI,
effluent TSS, basin  and  effluent pH.   Basin and effluent  dissolved oxygen is
measured daily.

    The plant has had problems  maintaining  the mixed liquor suspended solids at
the  recommended  operating level.    The  plant  effluent  is  meeting  permit
requirements.  Effluent  concentrations are at or  a bit  above  20  mg/1  for BOD
and TSS  (See Appendix B),  which will  likely  improve  results with increased
MLSS.   A  rake  drive cable  had frayed  but was  replaced with  a  plastic
impregnated  cable.   Blower equipment  is  protected by  a  roofed three  sided
structure made of corrugated aluminum panels.  It offers weather protection but
does  little for  noise  reduction.   Otherwise  the  plant has  experienced few
problems.

Piggot WWTP/Photograph Descriptions
    Refer to Figures 16 and 17:

A.  Blower setup consisting of  3  to 20 HP blowers, two of which  are on full-
    time.  Blowers  are housed  in a lightweight aluminum structure with one open
    side which provides some noise reduction.

B.  Flocculating rake drive control system  equipped with  dual limit switches.
    First  switch slows  down  the  motor  while the  second reverses  the motor
    collation and returns it to  correct operating speed.

-------
                                                          ^^^H
                                                           m
FIGURE 16.  PIGGOTT, ARKANSAS  PHOTOS A AND B

-------


FIGURE 17.  PIGGOTT, ARKANSAS PHOTOS C AND D

-------
                                                                      Page  6-15

C.  Effluent trough equipped with scum baffles.

D.  Effluent weir  from polishing basin.   Discharges  to the U.V.  disinfection
    channe1.

BLYTHEV1LLE WEST, NORTH AND SOUTH WWTPS, BLYTHEVILLE,  ARKANSAS

    The City of Blytheville, with a population of 25,000, is one of  the  larger
cities in Mississippi  County, Arkansas.  It  is located  approximately  185 miles
northeast of Little Rock and 70 miles  north of Memphis,  Tennessee.  Blytheville
is  primarily  a  farming  community,   growing cotton  and winter  wheat.    The
majority  of the  wastewater  flow is  domestic.    The  Blytheville plants are
identical in design, differing in size  only.  The North  plant  is the  smallest,
and  is  designed to handle  an average  flow  of  0.8 mgd.  The  South plant  is
designed for  1.4 mgd  and  the  West plant  for 1.5  mgd.    Each  plant was built
adjacent  to  former  unaerated  flow-through lagoons.    Although  the City's
original goal was to build one large plant  to handle all the  flow,  this concept
was dismissed because of the major sewer system re-routing and  renovation which
would be required.   The plants were started in April 1989.

    Each plant provides  influent  screening using  an  Aquaguard^M  traveling
screen.  Grinder pumps are used for volume  reduction of  the  screenings prior  to
disposal.    The wastewater is biologically  treated in  the aeration  basins which
incorporate solids settling  in  integral  clarifiers.    Clarified  effluent  is
treated  further in polishing  basins  which have  both  aerated and  unaerated
sections.   The effluent is disinfected using  an ultra-violet  light  system.

    The combined  staff for the  three plants consists  of the  superintendent,
maintenance supervisor, a plant  operations supervisor,  three operators and  an
administrative assistant.

    Visual  inspections of all  equipment is  performed daily.   The clarifiers and
weirs  are   sprayed  down weekly and  the  aeration  basins  and clarifiers are
skimmed as  needed.   Blower inlet and noise  filters are cleaned  weekly.  The two

-------
                                                                      Page 6-16

 larger  plants are sampled  for  permit  requirements three times  per week while
 the  other  plant is  sampled for  permit requirements  three  times  per month.
 Additionally, process monitoring is performed daily.

    The  South plant has  had trouble maintaining  the desired  operating mixed
 liquor  suspended solids  level due to a  significant underloading at the plant.
 A  two  sided  cinder block  enclosure has been  installed around the  air  lift
 sludge  blower to minimize the noise.  The West plant  developed a crack in the
 concrete sludge  trough due  to soil  settlement.  The three plants had installed
 screening around all noise filter housings to minimize silencer maintenance due
 to debris  accumulation.    The three plants  experienced high  effluent ammonia
 levels  during the start  up  spring  months which may  have been  caused by  farm
 fertilization operations  and/or limited nitrification development.   All these
 plants  were performing well, in  subsequent months through  October 1989,   as
 shown in the  data in Appendix B.

 Blytheville WWTPS Photograph Descriptions (North.  South and  West Plants)

    Refer to  Figures 18,   19, 20 and 21:

A.  Blower silencers.  Screens were installed to reduce filter clogging.  Metal
    mesh filters are used; these are brushed and washed regularly (North).

B.  Integral  clarifier.  Note the curtain and rake drive cable (North).

C.  Effluent  trough and rake drive enclosure (installed by plant) (North).

D.  Last aeration chain in basin;  closest to 3 integral clarifiers  (West).

E.  One of  three integral clarifiers at  the  West  plant.  Steel angle bracing
    was installed to minimize lateral movement of the long effluent trough.

F.  Aeration chain.   Localized boiling indicated diffuser problem (West).

G.  Structure used for air lift pump blower noise control at the South Plant.

-------
FIGURE 18.  BLYTHEVILLE, ARKANSAS PHOTOS A AND B

-------

-------
FIGURE 20.  BLYTHEVILLE, ARKANSAS PHOTOS E AND F

-------
FIGURE 21.  BLYTHEVILLE, ARKANSAS PHOTO G

-------
                                                                      Page 7-1

                                  SECTION 7
                                 REFERENCES

1. Biological Wastes  Treatment Using the Biolac System, A Technical Note.   U.S.
     Environmental Protection Agency Office of Municipal Pollution Control, EPA
     625/8-85-010.  Environmental Resources Management, Inc., West Chester, PA,
     1986.

2.  Fine  Pore  (Fine  Bubble)  Aeration  Systems.  Summary  Report.    U.S.
     Environmental Protection Agency,  Water Engineering  Research Laboratory,
     EPA/625/8-85/010,  Cincinnati, OH  45268, October 1985.

3. Personal Communication,  Charles Morgan, Parkson Corporation

4. Metcalf and Eddy,  Inc.,  Wastewater Engineering. 1979.

5. Design Brochure,  Parkson Corporation.

-------
     APPENDIX A

DESCRIPTION OF BIOLAC
 TREATMENT SYSTEMS

-------
                                                       TABLE A-l.  DESCRIPTION OF BIOLACR TREATMENT SYSTEMS
     Facility Kama
        Location
    	Contact
                                       Size
      Design
 Ardmore MWTP
 Ardmore, Alabama
 Bill Brakefield
 Engineer
 (615) 824-7980
 Berry WHTP
 Berry, Alabama
 Mike Swindle
 (Superintendent)
 (205) 669-4786
 Camden North HWTP
 Caroden,  Alabama
 G.E.  Jones - Engineer
 Jones Engineering
 (205) 872-7618
Cedar Bluff MWTP
Cedar Bluff, Alabama
Keith Davis - engineer
Lad Environmental
(205) 845-5315
Clayton WWTP
Clayton, Alabama
Bob Carter
Engineer
(205) 222-9431
 Flow   BOD
 (mud)  (»/day)

 0.35   730
                      Current
Flow    BOD
(nwd)   (»/day)
                                                                   Process Train
                                      Bar rack
                                      Biolac R
                                      Chlorlnation
 0.15   275
                  0.04
                          30
                                     Aquaguard  traveling  screen
                                     Biolac R
                                     Chlorination/dechlorination
                                     Post  aeration  (Cascade)
0.22    413
                                     Bar screen
                                     Biolac R
                                     UV disinfection
0.30
       550
                                     Aquaguard traveling screen
                                     Biolac R
                                     Chlorination/dechlorination
0.40   512
                                     Static screen
                                     Biolac R
                                     disinfection
                                                  Biolac  Description

                                                  -  Aeration  Basin  Volume, 0.70 MG
                                                  -  7  chains;  8  floats/chain;
                                                              4  diffusers/float
                                                  -  Integral  clarifier
                                                  -  Polishing  basin
                                                    Aerated zones
                                                  -  2  chains;  3  floats/chain;
                                                              2  diffusers/float
                                                  -  Blowers: 3-15 hp (1 standby)

                                                  -  Aeration basin  Volume, 0.264 MG
                                                  -  5  Chains;  5  floats/chain;
                                                              4  diffusers/float
                                                  -  Integral clarifier
                                                  -  Polishing  basin
                                                    Aerated and  nonaerated zones
                                                  -  1  chain; 4 floats/chain
                                                            2 diffusers/float
                                                  -  Blowers: 3-7.5  hp (1 on fulltitne)

                                                  -  Aeration basin  volume, 0.33 MG
                                                  -  6  chains;  6  floats/chain;
                                                              4  diffusers/float
                                                  -  Integral Clarifier
                                                  -  Polishing basin
                                                   Aerated and nonaerated cones
                                                  -  2  chains; 4  floats/chain;
                                                             2 diffusers/float
                                                  - Blowers: 2-7.5 hp (no standby)

                                                  - Aeration basin volume 0.53MG
                                                  -  7 chains;  8 floats/chain;
                                                             4 diffusers/float
                                                 - Integral clarifier
                                                 - Polishing basins
                                                   aerated and nonaerated zones
                                                 - 2 chains;  4 floats/chain;
                                                             2 diffusers/float
                                                 - Blowers:  3-15 hp (1  standby)

                                                 - Aeration basin volume,  0.45 MG
                                                 - 6 chains;  8 floats/chain;
                                                             4 diffusers/float
                                                 - Integral clarlfiers
                                                 - Polishing  basin
                                                   Aerated zones
                                                 - 1 chain;  5 floats/chain;
                                                           2 diffusers/float
                                                                                                                                         Conments/Problems
 Plant not yet on line
Plant on line August 1989.
Good system, expect even
better effluent when MLSS gets
to design MLSS(2500 mg/L).
Rake drive cable frayed (re-
placed), float destroyed from
rake overtravel no longer a
problem now.  Skim grease/oil
once/week.

Plant not yet on line
Plant not yet on line
Plant not yet on line

-------
                                                       TABLE A-l.   DESCRIPTION OF BIOLAC1* TREATMENT SYSTEMS
                                                                           (Continued)
    Facility Name
       Location
   	Contact
                                       Size
     PeaInn
                     Current
Columblana WWTP
Columbiana, Alabama
James Palmer
(Operator)
(205) 669-76*5
HancevlUe WWTP
Rancevllle, Alabama
Bill Hicks
(Operator)
(205) 352-6177
Flow   BOD       Flow    BOD
(mgd)  (»/day)   (mud)   (f/dav)
                                                                   Process  Train
0.75   1,251
0.5
        - Bar acraen
        - grit chamber
        - Biolac R
0.57   632
                 0.25
                         365
Hew Brockton WWTP
New Brockton, Alabama
James Harrison
(Superintendent)
(205) 894-5550
                        0.176  300
                                          0.05
                                                  98
Oxford HWTP
Oxford, Alabama
Ronald Windham
Engineer
(205) 271-3200
                        1.00   1,877
                                   - Schrlber screen
                                   - Biolac R
                                   - UV disinfection
                                   - Post aeration (Cascade)
                                     Bar Rack
                                     Biolac R
                                     Nutrient removal
                                     2 ponds with aquatic
                                     plants
                                     Post aeration
                                     (effluent flume)
                                    Manual bar  rack
                                    Aquaguard traveling  screen
                                    Grit  removal
                                    Biolac R
                                    Chiorlnation/dechiorlnatlon
                                    Post  aeration  (cascade)
                                                                                            Biolae Description

                                                                                            - Aeratln basin
                                                                                            - 6 chains;  8 floats/chain;
                                                                                                        2 dlffusers/float
                                                                                            - Integral clarifier
                                                                                            - Polishing basin
                                                                                              aerated zones
                                                                                            - 3 chains;  * floats/chain;
                                                                                                        2 dlffusers/float
                                                                                            - Blowers: 3-20 hp (1 standby)

                                                                                            - Aeration basin
                                                                                            - 7 chains;  10 floats/chain
                                                                                                        * diffusers/float
                                                                                            - Integral clarifier
                                                                                            - Polishing volume
                                                                                              aerated and nonaerated cones
                                                                                            - 2 chains;  * floats/chain;
                                                                                                        2 dlffusers/float
                                                                                            - Blowers: 3-16 hp (1 on full time)
                                                 - Aeratin basin volume, 0.2 MG
                                                 - 5 chains; 5 floats/chain;
                                                             2 dlffusers/float
                                                 - Integral clarifier
                                                 -  Blowers: 3 to 5 -  5 hp
                                                   Aeration basin volume, 1.5 MG
                                                   11 chains; 13 floats/chain;
                                                              6 diffusers/float
                                                   Integral clarlfar
                                                   Polishing basin
                                                   aerated and non aerated zones
                                                   3 chains; 8 floats/chain;
                                                             2 dlffusers/float
                                                   Blowers: 2-60 hp (1 standby)
                                                                                                                                        Comments/Problems
                                                                                                         Plant on line December 1989.
                                                                                                         Needed silencers  for blowers,
                                                                                                         system running well,  skim oil/
                                                                                                         grease every other day main-
                                                                                                         tenance free otherwise.
On line March 1989.  Very
pleased w/ system esp. compared
to mech. aerators which oper-
ator previously used.  Rake
motor burned out (water dara.-
due to  improper seal Installa-
tion).  Rake  overtraveled,
operator  bent  trigger forward
rake  fine  now.  Rake floats
hang up  on  other  hardware at
HWL.   Skim  oil/grease every 2
ks

Plant on line summer 1987. Very
dissatisfied originally due to
equipment problems. Clarifier rake
motor was under sized (would kick
out often in warm weather).
Floating curtain cable and
eyebolts rotted out.  Dlffuser
clamps needed to be tightened.
Auto valves on waste pump not
working, must be switched manually.
Meeting designed effluent BOD and
NH3 but monitoring reports show
lower limits that are not always
met.

Plant not yet on Una

-------
                                                       TABLE A-l.   DESCRIPTION OF BIOLACR TREATMENT SYSTEMS
                                                                            (Continued)
     Facility Name
        Location
         Contact

 Stevenson WWTP
 Stevenson,  Alabama
 J.M.  Garner
 (Operator)
 (205) 437-2490
Bay WWTP
Bay, Arkansas
Crawford Holmes
(Superintendent)
(501)  781-3386
(City  Hall  #)
Blythevllle  North WHTP
Blythevllle,  Arkansas
Jimmy Gee
(Superintendent)
(501) 763-4961
                                       Site
     Design
                     Current
Flow   BOD       Flow    BOD
(mud)  (»/day)   (mtd)   (»/day)
     Process Train
0.75   2,502
                 0.15
0.15   313
                 0.1
                         175
0.80   1,134
                 0.39
Blythevllle West WWTP
BLytheville, Arkansas
Jinnry Gee
(Superintendent)
(501) 763-4961
Blythevllle South WHTP
Blytheville, Arkansas
Jinny Gee
(Superintendent)
(501) 763-4961
1.50   3,253
                                          0.77
1.40   3,562
Aquaguard traveling  screen
Biolac R
                                     Bar screen
                                     Biolac R
                                     Chlorination
Aquaguard traveling screen
Grinders
Biolac R
UV disinfection
Aquaguard traveling screen
Grinders
Biolac R
UV disinfection
Aquaguard traveling screen
Grinders
Biolac R
l/V disinfection
Biolac Description

- Aeration basin
- 12 chains;  10 floats/chain;
              4 dlffusers/float
- Integral Clarifier
- Polishing basin
aerated and nonaerated zones
- 3 chains; 4 floats/chain;
            2 dlffusers/float
- Blowers: 3-40 hp (1 standby)

- Aerated basin
- 6 chains; 5 floats/chain;
            4 dlffusers/float
- Polishing basin
  aerated and nonaerated
- 2 chains; 3 floats/chain;
            2 diffusars/float
- Blowers: 2-7.5 hp / 5 cfra

- Aeratin basin volume, 1.09 MG
- 8 chains; 13 floats/screen;
            4 dlffusers/float
- Integral clarifer
- Polishing basin
  aerated and nonaerated zones
- 2 chains; 6 floats/chain;
            2 diffusers/float
- Blowers: 3-25 hp (1 standby)
  Aerated Basin Volume.  3.12 MG
  11 chains;  24 floats/chain;
             4 diffusers/float
  Integral clarlfiers
  Polishing basin
  aerated and nonaerated zones
  2 chains; 13 floats/chain;
           2 diffusers/float
  Blowers: 3-60 hp (1 standby)

  Aeration basin volume, 3.12 MG
  11 chains;  24 floats/chain;
             4 diffusers/float
  Integral clarifier
  Polishing basin
  Aerated and nonaerated zones
  2 chains; 13 floats/chain;
           2 diffusers/float
  Blowers: 3-60 hp (1 standby)
                                                                                                                Comments/Problems
                                                                                                         Experiencing problems  unre-
                                                                                                         lated to Biolac  system.  A
                                                                                                         Industry has left the  area re-
                                                                                                         sulting in greatly reduced
                                                                                                         flow & BOD loading.  This makes
                                                                                                         supporting design MLSS levels
                                                                                                         Impossible.
                                                                    Plant on line March 1989.   Good
                                                                    system, lowmaint., flex dlffuser
                                                                    every 2 weeks, clean air lift
                                                                    sludge pump w/ sewer cleaning
                                                                    equip, every 3-4 weeks, no
                                                                    clogging problems.
Plant on line April 1989.   Happy
w/system. Problems keeping blower
filters clean during summer,
planting and harvesting seasons.
Reduced substantially by screening
off Intake access pts.  Still
clean once/week.  Plant very  well
maintained.  Some high BOD, TSS &
NH3 numbers during initial months
after startup.

Plant on line April 1989.   Con-
crete sludge trough cracked soil
settlement.  Some high TSS & NB3
numbers during Initial months
after startup.
Plant on line April 1989.  Trouble
maintaining MLSS.

-------
                                                       TABLE A-l.   DESCRIPTION OF BIOLACR TREATMENT SYSTEMS
                                                                           (Continued)
                                       Size
    Facility Ran
       Location
   	Contact
     Desinn
                                              Currant
Decatur WWTP
Decatur, Arkansas
Rick McClean
(Superintendent)
(501) 752-3769
Flow   BOD       Flow
(mad)  (»/day)   (mud)
1.35   5,630
                                          1.1
BOD
(»/day)

5500
Process Train
Maynard WWTP
Maynard, Arkansas
Paul Mitchell
(Operator)
(501) 6*7-2701
Piggot WWTP
Piggot, Arkansas
Bradley Schaffler
(Superintendent)
(501) 598-2946
                        0.06    110
0.60   1,000
                                          0.3
                                                  450
Paint Brush Hills WWTP
Colorado Springs, CO
Kevin Smith
(Operator)
(719) 473-8600
Tri-Lakes WWTP
Monument, Colorado
0.90   1,350
1.30   2,168
            Bar screen
            Primary Clarlfier
            Blolac R
            Sand filters
            Post aeration
            (surface aerators)
            Dechlorination
                                     Bar screen
                                     Biolac R
                                     Chlorlnatlon
            Aquaguard traveling screen
            Biolac R
            UV disinfection
            Bar screen
            Biolac L
            Bar screen
            Grit removal
            Biolac R
            Chlorination/dechlorinatlon
                         Biolac Description

                         - Aeration basin
                         - 15 chains;  25 floats/chain;
                                      6 diffusers/float
                         - Integral clarifier
                         - Polishing basin
                         aerated and nonaerated zones
                         - 3 chains; 12 floats/chain;
                                     4 diffusers/float
                         - Blowers: 4-50 hp (3 standby)
                                                                                                                Comments/Problems
                           Aerated basin volume,0.104  MG
                           3 chains;  3 floats/chain;
                                     4 diffusers/float
                           Polishing  basin
                           Aerated and nonaerated zones
                           1 chain; 2 floats/chain;
                                   4 diffusers/float
                           Blowers: 2-5 hp (no standby)

                           Aeration basin volume,  0.952 MG
                           6 chains;  13 floats/chain;
                                     4 diffusers/float
                           plus 1 float at each corner at
                           effluent end with 4 diffusers/float
                           Integral clarifier
                           Polishing  basin
                           aerated and nonaerated zones
                           2 chains;  8 floats/chain;
                                     2 diffusers/float
                           Blowers: 3-20 hp (1 standby and 1
                                             runs 25X  of time)

                           Aeration basin
                           5 chains;  IS floats/chain;
                                      4 diffusers/float
                           No clarifier
                           Polishing  lagoon
                           aerated and nonaerated zones
                           2 chains;  13 floats/chain;
                                     4 diffusers/float
                           Blowers: 2-30 hp

                           2 Aeration basins at 2.1 MG each
                           11 chains/basin;  15 floats/chain;
                                            4 diffusers/float
                           External clarifier
                           No polishing basin
                           Blowers: 2-125 and 1-75 hp
Meeting all eff. limits.
Wave oxidation plant.   Took
some time to achieve denltri-
fication.  Replaced 3 of 4
rake drive motors.   751 of
float assemblies were defective
(FVC const, came unglued). 40Z
of dlff will be replcd.(expo-
sure to severe weather & hand-
ling may be cause).  Add lime
to maintain pB.

Plant not yet on line.
Plant on line April, 1989.
Had trouble getting up to
operating MLSS, some high BOD
& TSS #'s as a result.  Rake
drive cable needed replacement.
Low maintenance, flex diffusers
occasionally & skim oil/grease
daily.
Plant on line March, 1989.
Plant waa built to serve a
growing community but currently
only serves a high school & 4
houses.  Adequate evaluation
can not be made yet.
                                                                                                                                 Plant not yet on line.

-------
                                                       TABLE A-l.   DESCRIPTION OF BIOLACR TREATMENT SYSTEMS
                                                                            (Continued)
     Facility Nan*
        Location
    	Contact
                                       Size
     Deslnn
 Quitman WHIP
 Quitman,  Georgia
Flow   BOD
(nutd)  (*/day)

1.30   1,952
                     Current
Flow
(nutd)
BOD
(*/day)
Ferdinand WWTP          0.47   698
Ferdinand,  Indiana
Rusty Groeschen
(Operator)
(812) 367-2617
Remington WWTP           0.28   271
Remington,  Indiana
Marvin Sutter
(Operator)
(219) 261-2389
Renssalaer WWTP          1.20    1,942
Rensaelaer,  Indiana
Lawrence Swartz
(Operator)
(219) 866-5530
Western Wayne STF        0.80    1,341
Cambridge City, Indiana
Dan Bine
(Operator)
(317) 478-3788
Ellsworth WWTP
Ellsworth, Kansas
John Kerschner
(Supt.- Water & Sewer)
(913) 472-3941
0.50   1,250
                                          0.28
                                                 550
                                                                   Process  Train
                  - Biolac L
                  - Disinfection
                                   - Grinders
                                   - Grit removal
                                   - Biolac R
                                   - Chlorination/dechlorination
                                   - Post aeration
                                   - Bar screen
                                   - Grinders
                                   - Biolac R
                                   - Chlorination/dachlorination
                                   - Aerated grit chamber
                                   - Biolac R
                                   - Chlorination/dechlorination
                                   - Post aeration
                                   (Wyss diffusers)
                                   - Bar screen
                                   - Biolac R
                                   - Disinfection
                  - Bar  screen
                  - Grit chamber
                  - Biolac L
                  - Stablization pond
                                          Biolac Description

                                          - Aeration basin
                                          - 11 chains;  31 floats,
                                            17 floats,  14 floats,
                                            and 10 floats/chain in each
                                          of 4 cells; 4 diffusers/float
                                          - No clarifler
                                          - Polishing lagoon
                                            nonaerated zone
                                          - Blowers: 3-30 hp (1 standby)

                                          - Aeration basin volume,  0.672  MG
                                          - 7 chains; 9 floats/chain;
                                                      4 diffusers/float
                                          - Integral clarifier
                                          - Polishing basin
                                            aerated and nonaerated zones
                                          - 2 chains; 7 floats/chain;
                                                      2 diffusers/float
                                          - Blowers: 3-20 hp (1 standby)

                                          - Aeration basin volume,  0.45 MG
                                          - 5 chains; 6 floats/chain;
                                                      4 dlffusers/float
                                          - Integral clarifier
                                          - No polishing basin
                                          - Blowers:3-40 hp (1 standby)

                                          - 2 Aeration basins at 0.95  MG  each
                                          - 8 chains/basin;  10 floats/chain;
                                                            4 diffusers/float
                                          - Integral clarifier
                                          - No polishing basin
                                          - Blowers: 3-50 hp (1 standby)

                                          - Aeration basin volume  1.3  MG
                                          - 10 chains;  12 floats/chain;
                                                       4 diffusers/float
                                          - No polishing basin
                                          - Blowers: 3-20 hp

                                          - Aeration basin
                                          - 10 chains;  10 floats/chain;
                                                       4 diffusers/float
                                          - No clarifier
                                          - No polishing pond
                                            (effluent not continuous,
                                            mostly used for irrigation)
                                          - Blowers: 3-20 hp
                                                                                                                                        Comments/Problems
                                                                                                         Plant not yet on line.
                                                                                       Plant not yet on line.
                                                                                       Plant not yet on line.
                                                                                       Plant not yet on line.
                                                                                       Start up spring/summer 1990.
                                                                                       Plant not yet on line.
On line April, 1988.   Biolac
is used to supplement stabili-
zation ponds.   Very happy w/
system.  Changed check valves
on blowers(water check valves
were installed originally in-
stead of air check valves).
0 & M -only routine blower
malnt.  Some freezing in winter
resulting in some restriction
of chain/float movement.

-------
                                                       TABLE A-l.  DESCRIPTION OF BIOLACR TREATMENT SYSTEMS
                                                                            (Continued)
Size
Facility Hame
Location
Contact
Wells vi lie WWTP
Desinn
Flow
(mgd)
0.18
BOD
(»/day)
300
Current
Flow
(mud)
*
BOD
(t/day) Process Train Biolac Description
* - Biolac L -2 Aeration basins
Comments/Problems
Plant not yet on line.
Wellsville,  Kansas
Wichita WWTP
Wichita, Kansas
James Tush
(Superintendent)
(316) 522-9307
Edmonton WWTP
Edmonton, Kentucky
Halcom England
(Operator)
(502) 432-4844
34.4    18,148
                         0.51   851
                                          0.2
                                                  310
Greenville WWTP
Greenville, Kentucky
Roy McDonald
(Operator)
(502) 338-5260
0.75   2,160
                                          0.57
1,110
Morgantown WWTP
Morgantown, Kentucky
Randall Gaskey
(Operator)
(502) 526-5949
0.50   1,043
                                          0.28
                                                  350
            Primary clarifiers
            Trickling filters
            Biolac L
            (for nitrification)
            Chlorlnatlon
            Post aeration
                                     Bar screen and/or
                                     conralnutor
                                     Biolac R
                                     aquaculture pond
                                     chlorlnatlon
                                     Post aeration
Aqua-guard traveling screen
Bar screen
Biolac R
Chlorination
            Aquaguard traveling screen
            Biolac R
            Chlorination
2 chains/basin; 12 floats/chain;
                2 diffusers/float
Ho clarifier
Polishing basin
aerated and nonaerated zones
2 chains; 12 floats/chain;
          2 diffusers/float
Blowers: 2-20 hp (no standby)

6 Aeration basins,
volume 2.26 MG each
25 chains/basin; 16 floats/chain;
                 4 diffusers/float
External clarifier
Ho polishing pond
Blowers: 9-300 hp (3 standby)

Aeratln basin volume, 0.89 MG
10 chains; 10 floats/chain;
           2 diffusers/float
Integral clarifier
Polishing basin
aerated zone
2 chains; 1st chain - 5 floats/
chain. 2nd chain 3 floats/chain;
                 2 diffusers/float
Blowers: 3-20 hp (2 standby)

Aeration basin volume 1.37 MG
10 chains; 11 floats/chain;
           4 diffusers/float
Integral clarifier
No polishing basin
Blowers: 3-40 hp (2 standby)
                                Aeration basin
                                10 chains; 8 floats/chain;
                                           2 diffusers/float
                                Integral clarifier
                                No polishing basin
                                Blowers: 3-25 hp (1 standby,
                                1-30 min. on / 30 min. off)
                                                                                                         Plant not yet on line.
                                                                                                         Startup - March 1990
                                                                                On line April,  1989.   Signif-
                                                                                icant hydraulic design problems.
                                                                                Rake limit switch problems  &
                                                                                drive cable frayed.   Cable  was
                                                                                replaced w/new design.  Ho  prob-
                                                                                lems w/alr lift sludge pump
                                                                                but running continuously.   Per-
                                                                                formance can not be  evaluated
                                                                                due to hydraulics problems.
Plant on line April 1988.
Very good performance.  Air lift
sludge system doesn't perform as
claimed.  Floating sludge causes
solids to settle out in chlorine
out in chlorine contact chamber
(happens more frequently in rainy
weather ).   Solids washout at
high flows (rsin).  Rake cable
needed replacement.

On line March, 1989.  Getting
good removals.  Some dead spots
in basin (problem corrected by
blower operation described at
floats due to limit switch
Destroyed two rake
problems.  Operator Installed
a PVC collar which has prevented
rake overtravel.  Floating sludge
in clarifier when rake and/or
air lift sludge pump are down.

-------
                                                       TABLE A-l.  DESCRIPTION OF BIOLACR TREATMENT SYSTEMS
                                                                            (Continued)
     Facility Name
        Location
    	Contact
                                       Site
      Design
                     Current
 LeSueur WWTP
 LaSuaur, Minnesota
 Brad Bjarka
 (Project Engineer)
 (507) 625-4171

 Walla WWTP
 Walls, Minnesota
 Brad Bjarka
 (Project Engineer)
 (507) 625-4171
 Baumgartner WWTP
 St.  Loula MSD
 St.  Louis,  Missouri
 PRC  Engineering
 (314)  832-0400
Excelsior  Springs WWTP
Excelsior  Springs,  MO
Rex Brinker
Dir. of Utilities
(816)  637-1415
 Flow   BOD       Flow    BOD
 (mgd)   (»/day)   (nmd)   (f/day)

 0.90   3,314     *       *
 0.55    1,147
                                                                   Process Train
4.00   4,670
2.40   3,980
                 1.3
        2100
Livingston Manor WWTP
Livingston Manor,  NY
Bob Walco
(Superintendent)
(914) 439-4910
0.80   1,668
0.51    1,170
Rock Hill WWTP
Rock Hill, New York
                         0.22    367
                                     Mech. bar screen
                                     Grit removal
                                     Biolac R
                  - Biolac R
                                     Aerated lagoon
                                     Biolac L
                                     Chlorination
                    Pre-aeration using Biolac
                    Discharge to overland
                    flow area (April - Oct.)
                    or further treatment
                    in facultative lagoons.
pH adjustment
Bar rack comninuter
grit chamber
Biolac R
                                   No information available
                              Biolac Description

                              - Aeration basin volume 3.2 MG
                              - 12 chains; 27 floats/chain;
                                1480 diffusers total
                              - No polishing basin
                              - Blowers: 4-60 hp (1 standby)

                              - 2 Aeration basins volume 1.75 MG
                                per basin
                              - 8 chains; 10 floats/chain;
                                          4 diffusers/float
                              - No clarifier
                              - No polishing basin
                              - No information available on blowers

                              - Aeration basin
                              - 10 chains; 30 floats/chain
                                           4 diffusers/float
                              - No clarifiar
                              - Polishing basin
                                aerated zone
                              - 9 chains; 35 floats/chain;
                                          4 diffusers/float
                              - No information available on blowers

                              - Pre-aeration basin
                              - 12 chains; 10 floats/chain;
                                           4 diffusers/chain
                              - No clariflers
                              - No polishing basin
                              - Blowers: 3-800 cfm (1 standby)
                                                                     2 Aeration basins at 1.05 MS each
                                                                     7 chains;  12 floats/chain;
                                                                               4 diffusars/float
                                                                     2 External clarifier
                                                                     No polishing basin
                                                                     Blowers:  3-40 hp (1 standby)
                                                                   No information available
                                                                                                                                         Comments/Problems
                                                                                        Plant not yet on line.
                                                                                                         Plant not yet on line.
                                                                                        Plant not yet on line.
Biolac has been used for pre-
aeration here for over 4 years.
During original startup problems
getting chains moving was exp-
erienced (due to poor air dis-
tribution).  A 1 in 5 year storm
resulted in chain & anchor prob-
lems w/4 of the 12 air lines.
No problems w/new chain & anchor
system.  Low maintenance.

Retrofit. Plant on line 1986. One
of original  biolac U.S. Installa-
tions.   More than share of prob-
lems.   Rotted  Cables,  aye bolts
and end caps on floats and
dlffuaar clamps.  Have had quite
a bit of  success using nylon rope
or  anchorlina  especially because
rope stays out  of  MLSS.  Despite
cosmetic/equipment problems, plant
gets excellent  removal  of  BOD  &
TSS, generally 951 removal.  TKN  &
NH3 generally 90Z removal.

Plant not yet on line.

-------
                                                       TABLE A-l.   DESCRIPTION OF BIOLAC>* TREATMENT SYSTEMS
                                                                            (Continued)

Facility Name
Location
Contact
Coalton WWTP
Coalton, Ohio
Rackoff Engineers
(614) 464-3575
Size
Desixn Current
Flow BOD Flow BOD
(mgd) (*/day) (mgdj (*/day)
0.046 61 * *
q





Process Train
- Bar screen
- Blolac R
- Chlorination




Biolac Description
- Aeration basin
- 2 chains; 3 floats/chain;
4 dlffusers/float
- Integral clarifier



Comments/Problems
Plant not yet on line.



Franklin WWTP
Miami Conservancy Dist.
Nick Brookhart
(Wastewater  Engineer)
1(800)  *51-*932
4.00   18,000    4.5
                                                  29275
Frazeysburg WWTP
Frazeysburg, Ohio
Mona Miller
(City Clerk)
(614) 828-2564

Lowell WWTP
Lowell, Ohio
Paul Kullsek
(Operator)
(614) 896-3086
                         0.18   390
0.054  70
                 0.11
                         141
                  - Bar screen
                  - Primary clarifier
                  - Blolac R
                  - Chlorlnation/dechlorination
                                                            Ho  information available
                                   - Bar racks
                                   - Grinder pumps
                                   - Grit chamber
                                   - Blolac R
                                   - UV disinfection
Durant WWTP
Durant, Oklahoma
C.O. Reese
(Superintendent)
(405) 920-0364
1.70   2,400
2.10    3,173
- Bar rack
- Banninutor
- Biolac R
- Cascade post aeration
                                - Polishing basin
                                   Aerated zone
                                - 1 chain; 2 floats/chain;
                                           2 diffusers/float
                                - Blowers: 3-2 hp (1 standby)

                                - Aeration basin volume 9 MG
                                - 34 chains; 26 floats/chain;
                                             6 diffusers/float
                                - 2 external clariflers
                                - No polishing basin
                                - Blowers: 3-300 hp/6000 cfm
                                  blowers (1 standby)

                                No information available
Aeration basin
2 chains; 3 floats/chain;
          4 dlffusers/float
Integral clarifier
Polishing basin
aerated and nonaerated zones
1 chain; 3 floats/chain;
         4 diffusars/float
Blowers: 3-3 hp
(designed to have 2 running,
3 needed)

Aeration basin volume 5.3 MS
1st lagoon - 8 chains; 20 floats/
      chain; 2 dlffusers/float;
2nd lagoon - 4 different chains;
             19 floats/chain,
             17 floats/chain,
             15 floats/chain,
             13 floats/chain;
all with 2 diffusers/float.
Polishing basin area 11 acres.
aerated zone
15 chains; 30 floats/chain;
           2 diffusers/float
Blowers: 8-75 hp - 5 for lagoon
                                    Retrofit-
                                    Plant on line October 1989.
                                                                                                         Plant not yet on line.
                                                                                        Plant on line Jan.,  1989.   Plant
                                                                                        underdeslgned hydraullcally.
                                                                                        Problems w/llmit switches  on
                                                                                        rake system, operator fixed
                                                                                        problem himself.  Air lift sludge
                                                                                        pumps clog w/ fine particles.
                                                                                        Cracked elbow on one float
                                                                                        assembly delivered.   Solids
                                                                                        settling in polishing basin.
                                                                                        Generally reliable performance.
Partial retrofit ft added polishing
in April 1988 to help meet permit.
Operator doesn't  think they would
be meeting permit now without
Blolac.  Slime accumulation on
sleeves.  Metal air line fati-
gue 3 or 4 holes developed.  Need
to reduce effluent toxiclty.
Ciarlfiers overloaded.

-------
                                                      TABLE A-l.  DESCRIPTIOH OF BIOLAC1* TREATMENT SYSTEMS
                                                                           (Continued)
                                      Slat*
    Facility Hame
       Location
   	Contact
     Peatun
City of Canby WWTP
Canby, Oregon
Steve Hanson
(Superintendent)
(503) 266-4021
Ext. 248

Chase City WWTP
Chase City, Virginia
Flow   BOD
(mud)  (»/day)

1.15   2,160
                                             Current
Flow    BOD
(nmd)

0.76    1,270
0.60   1,201
Fincastle HWTP          0.08    150
Flncaatle, Virginia
Wayne Heikel
(Director)
(703) 473-3065
Lakeside HWTP           0.275  459
Winchester, Virginia
Hank Sliwinski
(Supt.- Several Plants)
(703) 722-2402
(Parkins Hill Plant *)
                                         0.04
                                                 67
     Process Train
Bar screen
Grit removal
Primary clariflers
Blolac R
External clarlfiers
Chlorlnation

Grit chamber
Biolac R
Sand filter
UV disinfection and
reaeration
                                     Bar screen
                                     Blolac L
                                     Chlorinatlon
                                     Post aeration
                                     Bar screen
                                     Biolac L
                                     Disinfection
Blolac Description

- Aeration basin
- 8 chains; 4 floats/chain;
            4 diffusers/blower
- External clarifier
- No polishing basin
- Blowers: 1-50 hp, 1-30 hp, 2-20 hp
                                                                           Comments/Problems
Plant on line in 1886.
Control air in basin to produce
anoxic zone to achieve  nitrification
denitrification. Older  generation
equipment - corrosion problems.
  2 aeration basins at .765 M3 each   Plant not yet on line.
  7 chains; 7 floats;
            4 diffusers/float
  External clarifier
  aerated and nonaerated zones
  3 chains; 3 floats/chain;
            4 diffusers/float
  Blowers: 4-25 hp (1 standby)
                                Aeration basin
                                2 chains; 7 floats/chain;
                                          2 diffusers/float
                                External clarifier
                                Polishing basin
                                aerated and nonaerated zones
                                2 chains; 8 floats/chain;
                                          2 diffusers/float
                                Blowers: 2-10 hp (1 standby)

                                Aerated basin volume 2.23 MG
                                4 chains; 14 floats/chain;
                                          2 diffusers/float
                                No clarifier
                                Polishing basin
                                3 chains; 8 floats/chain;
                                          2 diffusers/float
                                Blowers: 3-10 hp (1 standby)
                                      Plant on line September 1986.
                                      Good performance.  Corrosion  of
                                      metal hardware.  Basin froze  to
                                      within a 3 foot diameter around
                                      floats for as long as 1 week
                                      with no decrease in treatment.
                                      Hot able to contact operator.
                                      Equipment on line in 1988.

-------
             APPENDIX B

PERFORMANCE DATA SUMMARY TABLES FOR
       SELECTED BIOLAC PLANTS

-------
                                      TABLE B-l.   PERFORMANCE DATA SUMMARY
                                  CITY OF MORGANTOWN, KENTUCKY - BIOLAC R PLANT


Month
January 1989
February 1989
March 1989
April 1989
May 1989
June 1989
July 1989
August 1989
September 1989
Mean:
Mean: April to
September
Design
X of Design

Flow
(MGD)
.322
.388
.425
.345
.247
.278
.285
.270
.316
0.320

1989 0.290
0.5
58X
Influent
BOD
(me/L)
95.
136.
61.5
138.
194.
106.
151.5
608.
258.
194.2

242.7
_
-
Effluent
BOD
(mz/L)
59.1
57.5
31.4
19.3
10.5
21.3
11.9
6.9
6.4
24.9

12.7
_
-
X
BOD
Removal
37.8
57.7
48.9
86.
94.6
84.7
92.1
98.9
97.5
77.6

92.3
_
-

Loading
Ibs BOD/d
255.
440.
218.
397.
399.
246.
360.
1369.
680.
484.9

575.2
1045
55X
Influent
TSS
(mc/L)
150.
120.
100.
184.
222.
168.
86.
77.
392.
166.6

188.2

.
Effluent
TSS
(me/L)
29.
16.5
6.4
7.2
20.
14.
24.
<0.4
4.4
13.5

11.7

.
X
TSS
Removal
80.6
86.3
93.6
96.1
91.
91.7
97.2
99.5
98.9
170.5

95.7

_

NH3-N
(mp/'L)
^\ lllf^f JLtJ^
7.7
7.6
5.4
<0.01
<0.01

0.1

0.3
2.4

0.1

_
Startup January 1989 to March 1989
Sampling Program:  1 sample per month

-------
                                        TABLE B-2.  PERFORMANCE DATA SUMMARY
                                   CITY OF  GREENVILLE, KENTUCKY - BIOLAC-R PLANT


Month
May 1988
June 1988
July 1988
August 1988
September 1988
October 1988
November 1988
December 1988
January 1989
February 1989
March 1989
April 1989
May 1989
June 1989
July 1989
August 1989
Mean:
Design
X Design

Flow
(MGD)
.580
.260
.360
.270
.280
.270
.480
.490
.680
.530
.740
.580
.290
.350
.330
.336
0.4
0.73
55X
Influent
BOD
(me./L)
198.
405.
225.
170.
320.
278.
140.
150.
125.
123.
129.
105.
85.
85.
123.
184.
177.8


Effluent
BOD
(mg/L}
23.
20.
10.
2.
4.
4.
4.
3.
2.
6.
5.
6.
2.6
2.6
2.6
2.0
6.2


X
BOD
Removal
88.4
95.1
95.6
98.8
98.75
98.6
97.1
98.0
98.4
95.1
96.1
94.3
96.4
96.4
97.9
98.
96.5



Loading
Ibs BOD/d
97.
878.
675.
382.
747.
626.
560.
613.
709.
543.
796.
508.
206
248.
338.
515.
527.6
1293
41X
Influent
TSS
(rag/D
166.
625.
180.
142.
174.
202.
162.
300.
137.
157.
122.
370.
182.
80.
250.
156.
212.8


Effluent
TSS
(me/L)
25.
81.
22.
6.
2.
4.
3.
7.
7.
12.
8.
7.
6.2
5.6
1.2
2.0
12.4


X
TSS
Removal
85.
87.0
87.8
95.8
98.9
98.0
98.2
97.7
94.9
92.4
93.4
98.1
96.6
93.0
99.5
98.7
94.7



NH3-N
(mg/L)
.30
.60
.40
.75
.70
.54
.46
.45
.20
.20
.30
.25
2.9
.20
.35
.15
0.5



MLSS
(mg/L)

1856.


1736.
1278.
1392.
2019.
2178.
3532.
3700.
3400.
3704.
2648.


2494.8


Sampling program:  1 day per month

-------
                                        TABLE B-3.  PERFORMANCE DATA SUMMARY
                                   CITY OF NEW BROCKTON, ALABAMA - BIOLAC-R PLANT

Flow
Month WGD)
February 1988
March 1988
April 1988
April 1988
May 1988
June 1988
July 1988
July 1988
July 1988
July 1988
August 1988
August 1988
September 1988
September 1988
September 1988
September 1988
September 1988
October 1988
December 1988
February 1989
Mean:
June 1989 0.05
July 1989 0.06
August 1989 0.05
Mean: June to 0.053
August 1989
Design 0.175
X Design 30X
Influent
BOD
(me/L)
182.
280.
184.
173.
70.
283.
250.
290.
250.
190.
450.
234.
600.
270.
108.
225.
79.
113.
218.
175.
231.2
167
368
194
243



Effluent
BOD
fme/L)
19.
9.
6.
4.
18.
19.
7.
6.
3.
5.
8.
6.
8.
2.
7.
21.
15.
20.
2.
6.
9.6
3
3
2
2.7



Z
BOD
Removal
89.6
96.8
96.7
97.7
97.4
93.3
97.3
98.0
98.8
97.4
98.23
97.44
98.7
99.
93.5
90.7
81.0
82.3
99.1
96.6
95.0
98.2
99.2
98.9
98.8



Influent
Loading TSS
Ibs BOD/d (me/L)
105.
300.
218.
218.
47.
234.
201.
258.
300.
118.
505.
248.
658.
380.
185.
329.
163.
200.
222.
145.
251.7
69.6 153
184.1 547
80.9 176
111.5 292.0



Effluent
TSS
(me/L)
11.
22.
11.
11.
10.
17.
15.
12.
6.
3.
8.
6.
13.
6.
16.
20.
17.
18.
1.
14.
11.9
4
2
2
2.7



X
TSS
Removal
89.6
92.7
94.9
94.9
78.8
92.7
92.5
95.4
980.
97.5
98.4
97.6
98.02
98.4
91.35
93.9
89.6
91.0
99.6
90.4
93.8
97.4
99.6
98.9
98.6




NH3-N
(mg/L)
.7
.9
1.3

4.5
.8
.8
1.6
2.2
2.2
1.6
2.2
2.2
2.4
2.4



1.4
2.8
1.9
2.4
4.0
0.2
2.2



Sampling program monthly

-------
                                          TABLE B-4.  PERFORMANCE DATA SUMMARY
                                       CITY OF  EDMONTON, KENTUCKY  - BIOLAC-R PLANT

Month
May 1989
June 1989
July 1989
August 1989
September 1989
October 1989
November 1989
Mean:
Mean: September

Flow
(MGD)
ND
ND
ND
ND
ND
ND
ND

0.2(D
Influent
BOD
fme/L)
100.
80.
110.
291.
396.
114.
102.
170.4
202.6
Effluent
BOD
31.
33.
18.
3.
12.
14.
11.
17.4
11.6
X
BOD
Removal
69.
58.75
83.6
99.0
95.9
87.7
89.2
83.3
9.1

Loading
Ibs BOD/d
ND
ND
ND
ND
ND
ND
ND

185(D
Influent
TSS
(me/L)
106.
26.
64.
513.
453.
102.
197.
208.7
265.8
Effluent
TSS
(me/L)
26.
22.
4.
11.
29.
29.
19.
20.0
18.4
X
TSS
Removal
75.5
15.4
93.75
97.9
93.6
71.6
90.36
76.9
89.5

NH3-N
(mg/L)
<1.00
<1.00
<1.00
7.50
<1.00
5.30
<1.00
2.5
3.2
 to November 1989

Design               0.51
XDesign               39X

Startup April to
  June 1989

Sampling program 1 day per month

(l)From operator
850
22X

-------
                               TABLE B-5.   PERFORMANCE DATA  SUMMARY
                           CITY OF FINCASTLE,  VIRGINIA -  BIOLAC-L  PLANT


Month
September 1988
October 1988
November 1988
December 1988
January 1989
February 1989
March 1989
April 1989
May 1989
June 1989
July 1989
August 1989
Mean:

Flow
(MGD)
•ks__««JU
.044
.048
.050
.042
.049
.048
.052
.049
.069
.036
.057
.031
0.048
Influent
BOD
(me/L)
230.
200.
239.
215.
227.5
222.
229.6
217.
181.6
189.
235.
229.
217.9
Effluent
BOD
fme/L)
15.21
14.25
12.93
14.1
19.05
21.96
29.40
29.34
26.96
14.9
10.31
14.63
18.6
X
BOD
Removal
93.4
92.9
94.6
93.4
91.6
90.1
87.2
86.5
83.5
92.12
95.6
93.63
91.2

Loading
Ibs BOD/d
84.4
80.1
99.7
75.3
93.
89.
99.6
89.2
104.5
56.7
111.7
59.4
86.9
Influent
TSS
fme/L)
217.6
222.1
250.4
246.
242.5
255.
252.8
205.8
152.
155.5
131.
155.0
207
Effluent
TSS
(me/L)
8.
13.1
11.
14.5
27.63
49.87
45.2
21.3
29.4
15.5
7.25
14.8
21.5
X
TSS
Removal
96.3
94.1
95.6
94.1
88.6
80.45
82.1
89.7
80.7
90.03
94.5
90.5
89.7
Design
X Design
  0.075
64X
Sampling program one day per month

-------
                                        TABLE B-6.   PERFORMANCE DATA SUMMARY
                                        CITY OF LOWELL, OHIO  - BIOLAC-R PLANT


Month
July 1989
August 1989
September 1989
Mean:
Design
X Design

Flow
(MGD)
0.120
0.122
0.092
0.111
0.18
62X
Influent
BOD
fme/L)
168
130
260
185.9


Effluent
BOD
frae/L)
29.0
7.5
3.5
13.3


X
BOD
Removal
82.6
94.2
98.6
91.8



Loading
Ibs BOD/d
167.7
132.3
199.5
166.5


Influent
TSS
fme/L)
214.5
93.3
208.5
172.1


Effluent
TSS
(me/L)
57.0
8.0
12.5
25,8


X
TSS
Removal
73.4
91.4
94.0
86.3



NH3-N
fmg/L)
17
3
0
6.7



MLSS
(mg/L)
763
3517
5412
3230


Sampling program weekly

-------
     TABLE B-7.  PERFORMANCE DATA SUMMARY
CITY OF HANCEVILLE,  KENTUCKY - BIOLAC-R PLANT


Month
March 1989
April 1989
May 1989
June 1989
July 1989
August 1989
September 1989
Mean:
Mean: June to
September
Design
X Design

Flow
(MGD)
0.500
0.605
0.497
0.666
0.728
0.274
0.300
0.5
0.5
1989
0.57
88X
Influent
BOD
(me/L)
59.2
54.0
39.9
137.0
90.8
113.0
194.0
98.3
133.7



Effluent
BOD
(me/L)
12.4
9.8
12.8
15.8
10.5
7.5
5.1
10.6
9.7



X
BOD
Removal
79.0
81.9
67.9
88.5
88.4
93.4
98.0
85.3
92.0




Loading
Ibs BOD/d
247
272
165
761
551
258
485
391.
514.

832
62X
Influent
TSS
(me/L)
76
64
44
119
51
79
142
482.0
97.8



Effluent
TSS
(me/L)
6.5
11.0
7.0
9.0
2.7
7.3
17.0
8.6
9.0



X
TSS
Removal
91.4
82.8
84.0
92.4
94.8
90.7
90.0
89.4
92.




NH3-N
(me/L)
21.
2.1
15.7
1.0
1.0
1.0
0.1
3.3
0.8




-------
TABLE B-8.  LIVINGSTON MANOR,  NEW YORK

Date
June 1986
June 1986
June 1986
July 1986
July 1986
July 1986
July 1986
June 1987
June 1987
June 1987
July 1987
July 1987
July 1987
June 1988
June 1988
June 1988
July 1988
July 1988
July 1988
January 1989
January 1989
February 1989
February 1989
March 1989
March 1989
April 1989
April 1989
May 1989
May 1989
June 1989
June 1989
July 1989
July 1989
August 1989
August 1989
Average


Flow
0.530
0.616
0.5*0
0.611
0.569
0.548
0.621
0.677
0.661
0.692
0.638
0.801
0.725
0.526
0.488
0.451
0.489
0.452
0.748
0.480
0.248
0.222
0.606
0.515
0.491
0.578
0.334
0.921
0.365
0.404
0.624
0.593
0.507
0.277
0.488
0.544
±0.150
Influent
BOD
210.
268.
376.
241.
211.
168.
199.
141.
184.
243.
208.
254.
180.
261.
375.
320.
275.
284.
227.
305.
492.
330.
175.
227.
254.
311.
148.
166.
222.
359.
250.
254.
384.
228.
385.
260.
±79.6
Effluent
BOD
9.3
5.6
16.0
16.5
14.3
8.8
21.0
3.1
3.0
2.7
0.3
1.0
1.2
1.
1.
2.
2.
3.
2.
2.
4.
2.
6.
1.
3.
2.
4.
4.
4.
4.
5.
6.
11.
2.
4.
51.
±5.0
X Removal
BOD
95.6
97.9
95.7
93.1
93.2
94.8
89.4
97.8
98.3
98.9
99.8
99.6
99.3
99.6
99.7
99.3
99.3
98.9
99.1
98.3
99.2
99.4
96.6
99.6
98.8
99.4
97.3
97.6
98.2
98.9
98.0
97.6
97.1
99.1
99.0
97.9
±2.3
Loading
lb» BOD/Day
928.
1,377.
1,693.
1,228.
1,001.
768.
1,031.
796.
1,014.
1,402.
1,007.
1,697.
1,088.
1,145.
1,526.
1,204.
1,122.
1,071.
1,416.
1,221.
1,018.
611.
884.
975.
1,040.
1,499.
412.
1,275.
676.
1,210.
1,301.
1,256.
1,624.
527.
1,567.
1,132
±320.
Influent
TSS
187.
246.
650.
236.
106.
302.
84.
184.
160.
604.
240.
140.
140.
96.
164.
204.
184.
104.
206.
146.
300.
798.
58.
194.
128.
224.
192.
78.
100.
166.
120.
152.
364.
172.
178.
217.
±161.
Effluent
TSS
18.5
9.5
21.
17.
4.5
24.
8.
5.8
6.0
10.8
35.
4.
17.
2.
1.
2.
3.
2.
5.
1.
10.
5.
4.
9.
8.
1.
9.
3.
7.
5.
14.
10.
10.
3.
8.
8.7
±7.4
X TSS
Removal
90.1
96.0
96.7
92.8
95.8
92.1
90.5
96.8
96.3
98.2
85.4
97.1
87.9
97.9
99.3
99.0
98.4
98.1
97.6
99.3
96.7
99.4
93.1
95.4
93.8
99.6
95.3
96.2
93.0
97.0
88.3
93.4
97.3
98.3
95.5
95.4
±3.6
Influent
TKN
_
-
-
-
-
-
-
38.9
52.7
44.0
43.1
52.1
45.4
53.2
42.6
41.2
45.9
43.4
50.4
59.4
66.1
63.3
21.6
61.6
46.8
38.6
29.12
21.84
36.4
47.6
42.84
31.08
57.68
40.04
52.08
45.3
±11.3
Effluent
TKN
_
-
-
-
-
-
-
1.12
5.3
1.7
1.7
3.8
0.7
2.5
2.5
0.4
0.6
0.3
0.8
4.5
7.3
0.56
1.7
1.4
2.0
1.4
0.84
10.64
5.04
1.12
9.52
5.88
16.8
0.84
1.96
3.3
±3.8
X TNK
Removal
_
-
-
-
-
-
-
97.1
89.9
96.1
96.1
92.7
98.5
95.3
94.1
99.0
98.7
99.3
98.4
92.4
89.0
99.1
92.2
97.7
95.7
96.4
97.1
51.3
86.2
97.6
77.7
81.1
70.9
97.9
96.2
91.9
±10.6
Influent
HH3-N
„
-
-
-
-
-
-
12.6
17.6
14.3
13.2
14.8
13.2
20.1
16.2
37.7
33.6
13.4
29.7
4.5
17.6
12.9
11.7
12.3
11.2
10.6
14.8
14.56
22.12
13.1
13.44
13.8
11.48
16.43
17.5
16.2
±7.0
Effluent
NH3-N
„
-
-
-
-
-
-
0.1
2.5
0.1
0.1
0.1
0.1
1.1
0.8
0.3
0.3
0.1
0.6
3.7
5.3
0.1
0.28
0.3
0.28
0.84
0.28
1.68
3.92
1.12
8.96
4.48
14.48
0.28
0.89
1.9
±3.2
X NH3-N
Removal
_
-
-
-
-
-
-
99.2
85.8
99.3
99.2
99.3
99.4
94.5
95.1
99.2
99.1
99.3
98.
17.8
69.9
99.2
97.6
97.6
97.5
92.1
98.1
88.5
82.3
91.5
33.3
67.5
-26.1
98.3
94.9
84.5
±29.4

-------
 TABLE B-9.   PERFORMANCE DATA SUMMARY
  CITY OF BLYTHEVILLE,  ARKANSAS  WEST
            BIOLAC-R PLANT
Effluent

Month
April 1989
May 1989
June 1989
July 1989
August 1989
September 1989
October 1989
Mean:
Mean: June to
October 1989
Design:
Z of Design:
Startup April 1989 to
Flow
(MGD)
0.920
0.832
0.740
0.814
0.556
0.649
0.848
0.766
0.717

1.50
48
June 1989
BOD
(mg/L")
12.3
10.2
13.4
8.1
4.6
9.9
7.9
9.5
7.6

_


TSS
(mg/L)
43.5
12.8
14.2
5.5
36.0
10.4
7.8
18.6
14.9

_


NH3-N
(mg/L^
47.8
31.8
50.0
6.8
1.4
0.2
0.4
19.8
2.2

_


TABLE B-10.  PERFORMANCE DATA SUMMARY
 CITY OF BLYTHEVILLE, ARKANSAS NORTH
            BIOLAC-R  PLANT
Effluent

Month
April 1989
May 1989
June 1989
July 1989
August 1989
September 1989
October 1989
Mean:
Mean: August to
October 1989
Design
X of Design
Flow
(MOD)
0.462
0.338
0.345
0.403
0.474
0.263
0.446
0.39

0.39
0.8
49
BOD
(me/L)
4.1
7.1
12.8
21.5
11.9
5.9
23.6
13.8

13.8


TSS
fmg/L)
4.0
5.3
53.0
22.0
13.0
12.5
14.6
26.3

13.3


NH3-N
(mg/L)
39.2
4.3
51.0
85.2
1.2
0.7
0.5
26.0

1.0



-------
          TABLE B-ll.  PERFORMANCE DATA SUMMARY
       CITY OF BLYTHEVILLE,  ARKANSAS - SOUTH PLANT
                     BIOLAC-R PLANT
Effluent

Month
April 1989
May 1989
June 1989
July 1989
August 1989
September 1989
October 1989
Mean:
Design:
X Design:
Flow
(MGD)
0.676
0.620
0.673
0.645
0.519
0.543
0.538
0.602
1.40
43X
BOD
(mg/L)
6.9
12.4
16.5
25.2
33.8
11.0
0.2
15.1


TSS
(mg/L)
13.0
18.7
9.5
19.5
38.2
9.6
18.5
18.1


NH3-N
(mg/L)
38.7
7.9
70.4
95.3
3.3
0.2
0.4
30.9


          TABLE B-12.  PERFORMANCE DATA SUMMARY
           CITY OF BAY, ARKANSAS - SOUTH PLANT
                      BIOLAC R PLANT
Effluent

Month
May 1988
December 1988
January 1989
February 1989
March 1989*
April 1989
May 1989
June 1989
July 1989
August 1989
September 1989
Mean: June to
September 1989
Design:
X Design
Flow
(MGD)
0.120
0.275
0.136
0.211
0.067
0.049
0.055
0.118
0.287
0.557
0.100
0.266

0.15
177X
BOD
(mg/L)
20.4
36.3
39.1
33.7
30.0
21.7
14.9
24.9
10.1
3.7
2.7
10.4



TSS
frng/L)
34.0
93.0
87.1
75.0
41.4
24.8
28.3
12.4
11.2
2.0
1.2
6.7



NH3-N
(ing/D

2.0
5.0
4.5
18.9
26.0
19.3
22.4
21.5
1.1
0.2
11.3



Sampling program two grab samples per month
*Biolac system on line; startup March 1989 to May 1989

-------
TABLE B-13.  PERFORMANCE DATA SUMMARY
       CITY OF  PIGGOTT, ARIZONA
           BIOLAC R PLANT


Month
June 1989
July 1989
August 1989
September 1989
Mean:
Design:
X Design:

Flow
(MGD)
0.561
0.194
0.382
0.249
0.35
0.60
58X

BOD
fmg/L)
19
17
28
19
20.8


Effluent
TSS

-------