December 1986                   EPA-330/2-86-012
       Hazardous  Waste Ground-Water
       Task Force
       Evaluation of
       B. H. S., Inc.
       Wright City,  Missouri
                           US Environmental Protection Agtnc*
                           Region 5, Library (PL-12J)
                           77 West Jackson Boulevard, l«tn fmr
                           Chicago, IL 60604-3590
&EPA
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

-------
U3SZ.
         UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
"<. PSO^-'                        December 11,  1986

                  UPDATE OF THE HAZARDOUS WASTE GROUND-WATER
                  TASK FORCE EVALUATION OF THE B.H.S.,  INC.,
                       WRIGHT CITr', MISSOURI, FACILITY

     The United  States  Environmental  Protection  Agency's  Hazardous  Waste
Ground-Water Task Force  (Task  Force)  conducted an evaluation of the  ground-
water monitoring program  at  the  B.H.S.,  Inc. (B.H.S.), hazardous waste dis-
posal facility.  The onsite  field  inspection was  conducted during the period
February 19  through  February 26,  1986.   The Task  Force  was accompanied by
Missouri Department of Natural Resources (MDNR) and EPA Region VII personnel.
B.H.S. is  one  of 58 facilities  that  are being evaluated by  the Task Force.
The B.H.S.  facility  is  located  approximately 50  miles  west  of  St. Louis,
Missouri, near the town of Wright City.

     The purpose of  the  Task Force evaluation was to  determine the  adequacy
of the B.H.S.  ground-water monitoring system in regard to State and  Federal
ground-water monitoring  requirements.   Specifically,  the  objectives  of  the
evaluation at B.H.S.  were to:

        Determine compliance  with the State equivalent  of  40  CFR  Part  265
        interim status ground-water monitoring requirements.

        Evaluate the ground-water monitoring program described in the  facility's
        RCRA Part B permit application for  compliance with the State equivalent
        of 40 CFR Part 270.14(c)  requirements.

        Determine if  hazardous waste  constituents  have  entered the  ground-
        water at the facility.

        Provide information to assist the Regional  Administrator in determining
        if the facility meets EPA requirements for waste management facilities
        receiving waste from Federal Superfund response actions.

-------
     The facility  was  closed at  the  time of  the  inspection and, therefore,
little activity  has  taken place  since the  field  work  was  completed.   The
faciltiy has met with  MDNR once on July  3,  1986 to discuss closure, ground-
water monitoring ana Part  B  issues.  EPA  Region  VII met  with the facility on
December 8, 1986 to  preliminarily  identify the deficiencies at the facility,
ana the alternatives for correcting  those  deficiencies.  EPA and MDNR corrments
on the Part B application  for Area 2 have been formulated and will be sent to
the facility in December 1986.

     Analytical data from  the Task Force  sampling  effort  have qualitatively
indentified the presence of  methylene  chloride and i ,2-dichloroethane in the
ground water at the facility.  A majority of the wells sampled were installed
just prior to the investigation and were sampled for the first time with this
effort.  The presence  of these compounds  will be  confirmed  with additional
sampling by both the  facility,  during  routine  quarterly  events,  and  EPA.

     The Task  Force investigation  identified several  deficiencies  in  the
geologic and hydrolo^ic  site  characterization,  and in the ground-water moni-
toring system.  These include lack of  identification of the uppermost aquifer,
lack of a  true upgradient well  to  characterize the  background ground-water
quality, failure to  define the hydraulic  characteristics  of  Units  A  and B.
failure to  determine the  nature  and  extent  of the  sand  lenses  present in
Unit A, and failure to assess the vertical head distribution within and between
Hydro log ic Units A and  B.   EPA,  in consultation with  MDNR, will  initiate an
appropriate action that  will  correct  these deficiencies  and will ensure full
implementation of the Task Force recommendations.

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
HAZARDOUS WASTE GROUND-WATER TASK FORCE
EPA-330/2-86-012
GROUND-WATER MONITORING EVALUATION
B.H.S. ,  INC.
Wright City, Missouri
December 1986
Alan E.  Peckham
Project Coordinator
National Enforcement Investigations Center

-------
                                 CONTENTS


EXECUTIVE SUMMARY

INTRODUCTION 	     1

SUMMARY OF FINDINGS AND CONCLUSIONS  	    10

  GROUND-WATER MONITORING PROGRAM DURING INTERIM STATUS  	    11

    Site Hydrogeology	    12
    Ground-Water Sampling and Analysis Plan  	    13
    Closure/Post Closure Plans 	    13

  GROUND-WATER MONITORING PROGRAM PROPOSED FOR THE RCRA PERMIT ....    13
  TASK FORCE SAMPLING AND MONITORING DATA ANALYSIS 	    14
  COMPLIANCE WITH CERCLA/SUPERFUND OFFSITE POLICY  	    14


TECHNICAL REPORT

INSPECTION METHODS 	    15

  RECORDS/DOCUMENTS REVIEW AND EVALUATION  	    15
  FACILITY INSPECTION  	    15
  GROUND-WATER AND LEACHATE SAMPLING AND ANALYSIS  	    16
  LABORATORY INSPECTION  	    16

WASTE MANAGEMENT UNITS AND OPERATION 	    17

  WASTE MANAGEMENT UNITS 	    17

    RCRA-Regulated Landfills 	    19
    Nonregulated Landfills 	    20
    Surface Impoundments 	    21

  FACILITY OPERATION 	    22

    Waste Acceptance	    23
    Waste Handling	    24
    Inspection Procedures  	    25
    Leachate and Surface Runoff Handling 	    25

SITE HYDROGEOLOGY	    26

  HYDROGEOLOGIC UNITS  	    26
  GROUND-WATER FLOW	    26

    Hydrologic Unit A	    29
    Hydrologic Unit B	    29
    Ground-Water Flow Summary  	    30

-------
                             CONTENTS (cont.)


GROUND-WATER MONITORING PROGRAM DURING INTERIM STATUS  	     34

  REGULATORY REQUIREMENTS  	     34

    SWDAOP 721901  	     35
    40 CFR Part 265 Subpart F	     35
    HWFP TSD 122282001	     35
    10 CSR 25-7.011(10)	     37

  GROUND-WATER SAMPLING AND ANALYSIS PLAN  	     38

    December 31, 1981 SAPS	     38
    November 15, 1983 SAPS	     38
    April 16, 1984 SAPS	     38
    February 14, 1986 SAPS	     39

  MONITORING WELLS 	     39

    System 1	     40
    System 2	     41
    System 3	     41
    Other Wells	     42
    Interceptor Trenches 	     42
    Well Construction	     42
    System 1	     43
    System 2	     46
    System 3	     47
    Other Wells	     48
    Well Locations	     53
    Interceptor Trenches 	     53

  SAMPLE COLLECTION AND HANDLING PROCEDURES  	     54

  WAIVER OF GROUND-WATER MONITORING REQUIREMENTS DEMONSTRATION ....     54

  GROUND-WATER ASSESSMENT PROGRAM AND OUTLINE  	     55

GROUND-WATER MONITORING PROGRAM PROPOSED FOR RCRA PERMIT 	     58

  DEFINITION OF WASTE MANAGEMENT AREAS 	     58
  POINT OF COMPLIANCE	     58
  DETECTION MONITORING PROGRAM 	     60
  COMPLIANCE MONITORING PROGRAM  	     61
  CORRECTIVE ACTION PLAN 	     63

TASK FORCE SAMPLE COLLECTION AND HANDLING PROCEDURES 	     64

MONITORING DATA ANALYSIS FOR INDICATIONS OF WASTE RELEASE  	     74

REFERENCES

-------
                             CONTENTS (cont.)
APPENDICES
A    ANALYTICAL TECHNIQUES AND RESULTS FOR TASK FORCE SAMPLES
B    CONSTRUCTION DRAWINGS
C    POTENTIOMETRIC SURFACE MAPS
D    GROUND-WATER MONITORING SYSTEMS
FIGURES

1    Location Map	      3
2    Hazardous Waste Management Units and Locations  	      4
3    Area 1 Disposal Units	      6
4    Locations of RCRA-Regulated Units in Area 1 	      7
5    Typical Well Construction Systems 1 and 2   	     45
6    Typical Well Construction System 3 and GMW Wells  	     50
7    Designation of Waste Management Areas 	     59
8    Location of Task Force Sample Stations with Facility
       Units Shown   	     66
TABLES

1    Status of Waste Disposal Units, Area 1  	     18
2    Hazardous Waste Landfilled in Trench 21 	     19
3    Classification of Hydrologic Units  	     27
4    Additional Sampling and Monitoring Requirements
       Imposed by MDNR	     36
5    Ground-Water Sampling and Monitoring Requirements Imposed by
       EPA and MDNR	     37
6    Summary of Well Information, System 1 Nominal 3-Inch Diameter
       PVC Pipe with Glued Joints	     44
7    Summary of Well Information System 2, Nominal 4-Inch Diameter
       Schedule 40 PVC Threaded Flush Joint Pipe 	     47
8    Summary of Well Information System 3 and GMW Wells Nominal
       2-Inch Diameter No.  316 Stainless Steel, Treaded,
       Flush-Jointed Pipe	     49
9    Summary of Well Information, Wells P17 Through P22 and P-A
       Through P-D Nominal  3-Inch Diameter PVC Pipe with
       Glued Joints	     51
10   Summary of Well Information Nominal \ and 1^-Inch Diameter
       PVC Pipe with Glued Joints	     52
11   Phase I Ground-Water Assessment Plan Parameters 	     56
12   Wells for Monthly Water Level Measurements  	     61
13   Parameters for Compliance Monitoring Program  	     62
14   Sample Collection Data	     65
15   Order of Sample Collection Bottle Type and
       Preservative List	     67
16   Chemical Vapor and Radiation Detections at Sample Stations
       Wellheads	     70
17   Purging Data	     71

-------
EXECUTIVE SUMMARY

-------
                               INTRODUCTION

     Concerns  have  been raised about whether  hazardous  waste treatment,
storage and disposal facilities (TSDFs)  are complying with the ground-water
monitoring  requirements  promulgated under the  Resource  Conservation and
Recovery Act  (RCRA).*   In  question is the ability of existing or proposed
ground-water monitoring  systems  to detect contaminant releases from waste
management units.   To evalaute these systems  and determine the current com-
pliance status, the  Administrator  of  the Environmental  Protection Agency
(EPA) established a Hazardous Waste Ground-Water Task Force (Task Force) to
evaluate compliance  at  TSDFs and  address the  cause(s)  of noncompliance.
The Task Force  comprises personnel from the  EPA Office of Solid Waste and
Emergency Response  (OSWER),  the National  Enforcement  Investigations  Center
(NEIC), Office of Enforcement and Compliance  Monitoring (OECM), EPA Regional
Offices and State regulatory agencies.   The Task Force is conducting in-depth
onsite investigations of TSDFs with the  following objectives:

          Determine compliance with interim status ground-water monitoring
          requirements of 40  CFR Part 265 as promulgated  under RCRA  or  the
          State equivalent (where the  State has received RCRA authorization)

          Evaluate  the  ground-water monitoring program  described  in the
          facility's RCRA Part B permit application for  compliance with  40
          CFR Part  270.14(c)  or  the state equivalent (where the State has
          received RCRA  authorization)

          Determine if the ground  water at the  facility  contains hazardous
          waste constituents

          Provide information which can  aid in  determining whether  the TSDF
          can receive waste  from  response actions  conducted pursuant to the
     Regulations promulgated under RCRA address hazardous waste management
     facility operations,  including ground-water monitoring,  to ensure that
     hazardous waste  constituents  are not  released  to the environment.

-------
          Comprehensive Environmental  Response,  Compensation  and  Liability
          Act (CERCLA, Public Law 91-510)*

     To  address  these objectives, this  Task  Force evaluation determined
whether:

          The facility  has  developed and is following an adequate ground-
          water sampling and analysis plan

          Designated  RCRA and/or  State-required  monitoring wells  are  prop-
          erly located and constructed

          Required analyses  have  been properly conducted on  samples  from
          the designated RCRA monitoring wells

          The ground-water  quality assessment  program  outline  (or plan,  as
          appropriate) is adequate.

     The B.H.S.  Incorporated, Wright City, Missouri facility (B.H.S.) onsite
inspection was conducted from February 19 through 26, 1986.   The  inspection
was coordinated by personnel from NEIC.  In general, the evaluation involved
a review of State, Federal  and facility records;  a facility inspection; and
ground-water and landfill  leachate sampling and analysis.

     The B.H.S.  facility is  located approximately 50 miles west of St. Louis,
Missouri [Figure 1],   The site covers approximately 158 acres.   The facility
has interim  status (EPA ID  Number MOD068521228)  for  a  landfill  (58.9-acre-
feet) and treatment in surface impoundments (123  gallons per day).

     Hazardous waste  related  activities  at the site consist of closure of
the Area 1  landfill  and  storage/treatment of landfill  leachate by surface
impoundments [Figure  2],  A  new  landfill and tank and drum storage opera-
tion is proposed for tne site in the February 1986 RCRA Part B application.
     EPA policy, stated  in  the May 6,  1985 memorandum from Jack NcGraw on
     "Procedures for Planning  and  Implementing Offsite Response", requires
     that TSDFs receiving CERCLA  wastes be in compliance with applicable
     RCRA ground-water monitoring requirements.

-------
Figure  1
Location Map.
BHS, Inc.,  Wright
                                City, Missouri.
     0
Scale:L
1000 2000 3000
  I     I     I	
«CCO 5000
	1.	1 feel

-------
 PROPOSED HAZARDOUS
 WASTE DISPOSAL AREA
FIGURE 2. HAZARDOUS WASTE MANAGEMENT UNITS AND LOCATIONS

-------
     Disposal operations  began  in 1971 when a  sanitary  landfill  was put
into use.   Little  information is available about its construction, opera-
tion or the waste placed  in it.   This disposal  area, designated as the San-
itary Landfill [Figure 2], ceased operation in early 1977.

     In June 1977, operations began in Area 1.   The disposal area eventually
covered approximately 12  acres containing 33 drilled cell* and trench areas
[Figure 3].  Of these, six trenches (IN, 2N, 6N, UN, 12N, and 21) [Figure 4]
and  the  Progessive Trench  Area  (PTA-highlighted  in  Figure 3) were  in
existence  on  November  19,  1980 and qualified for  interim  status.   The RCRA
regulated portion of Area 1 covers approximately 2 acres.

     The proximity of RCRA regulated and pre-RCRA trenches and drilled cells
requires that all of Area 1 be treated as a single hazardous waste management
unit for ground-water monitoring purposes; however, because of this, ground-
water monitoring will  be  unable to identify releases from a specific trench
or drilled cell  regardless of when it was placed into or removed from service.

     The Missouri  Department  of  Natural Resources  (MDNR)  has  issued two
permits to  regulate Area  1 operations.   The first, a solid waste disposal
area operating permit, was  issued  in May  1977.  On  December 22, 1982, this
was replaced  by  a  hazardous waste permit  based on  the Missouri Hazardous
Waste Management Law  and  associated  regulations.   The latter  permit will
expire December 22, 1987.   Missouri was given Phase I authorization to admin-
ister the  State  ground-water  monitoring  regulations  [10 CSR 25-7.011(10)],
in lieu of the Federal ones, in November 1983 and received final authoriza-
tion to administer all of RCRA,  except for the  1984 amendments, in December
1985.

     A Part B RCRA  permit application was  submitted August 3,  1983.   It
consisted mainly of the  December 13,  1981 permit application  to the MDNR.
The application was reviewed  by  EPA Region VII and  the MDNR.   EPA  issued a
     Drilled cells were  reported  by B.H.S.  to be unlined,  3-foot-diameter
     auger holes in which drums of waste were stacked and then covered with
     locally available clayey soil.

-------
LU
K
 Z
 3

 C
 Uj
 H
  O
  ui
  oe

  <
  oe
  u
  OE
  U.
  O
  !fl
  Z
  O
   U
   C
   ce
   3
   o

-------
comment  letter October  3,  1983,  in  which  additional  information and
correction of deficiencies was requested.  In response, B.H.S. submitted an
amended  Part  B  application  on November 15,  1983.  EPA determined that the
amended  Part  B  application was also  incomplete  and contained  deficiencies.
On March  12,  1984,  EPA issued a  Letter  of Warning to B.H.S.  requesting
additional information and correction of deficiencies.  B.H.S. submitted an
amended  Part  B  application  to EPA on April  16, 1984.   On August 21, 1985,
EPA  issued an Administrative  Order to B.H.S.  The order stated B.H.S.  had
failed to submit a complete application and  proposed that B.H.S.  pay a pen-
alty of  $7,150.   Attached to  the order was  a letter listing the deficien-
cies and  comments concerning  the  Part B  application.   On October 18, 1985,
EPA  and  B.H.S.  signed  a Consent Agreement in which the Company agreed to
pay a $5,400 penalty and submit a complete application no later than Febru-
ary 14, 1986.   The revised Part B was submitted on February 14, 1986 and is
currently under review.

     The  initial  Part  B and the two  revisions covered  primarily the expan-
sion of  Area  1.   The February 1986 submittal was  essentially  a new  Part B.
It described a proposed new landfill  (Area 2),  a leachate treatment system,
tanks that would replace the current surface impoundments and a ground-water
monitoring system.

     B.H.S.  was  not  accepting waste for disposal  during  the inspection.
Area 1 was undergoing  closure  under  interim status and no  landfill units
were in operation.

     The surficial soil at the site is weathered loess, a wind-blown deposit
of glacial origin.  This  is underlain by a weathered/oxidized  glacial till
and is known as Hydrologic Unit A.   Beneath  this unit is an unoxidized gla-
cial  till and some residual soil  known as  Hydrologic  Unit B.   For purposes
of RCRA-required ground-water  monitoring, the saturated portion of Hydrologic
Unit A and the interface between  Hydrologic  Units A and B are considered by
B.H.S.  to be the uppermost aquifer.

-------
     Beneath the  glacial  deposits  are  a series  of  bedrock formations
consisting of shales,  limestones  and  sandstone.   The St.  Peter Sandstone,
ranging in depth  between  350 and 500  feet below land surface at the site,
is the principal  regional  water supply aquifer.

-------
                                                                        10
                    SUMMARY OF FINDINGS AND CONCLUSIONS

     The findings and conclusions presented below reflect conditions existing
at the  facility  during  the February 1986 investigation.  Actions taken by
the State,  EPA Region VII  and  B.H.S.  subsequent  to  February  are  summarized
in the accompanying update.

     Task  Force  personnel  evaluated  the  ground-water monitoring program
followed at  the  B.H.S.  facility for  the  period  November 1981, when the
applicable  provisions  of the  RCRA  regulations became effective, through
February 1986.   This  evaluation  revealed that the  interim status ground-
water monitoring  program  for  Area  1,  although modified  since  1981, still
needs further refinements.   New  wells have been  placed around the site as
part of  an  expanded  site ground-water monitoring program.  The Task Force
effort included the first sampling of some of these new wells.

     B.H.S. is not in compliance with 10 CSR 25.7.011(10) [40 CFR Part 265.91]
or 10 CSR 25.7.011(2)(E)(20) [Part 270.14(c)] because proper well placement
cannot be determined with confidence based on currently available hydrogeo-
logical   site  characterization.   Apparent  ground-water mounding within the
site complicates  locating an upgradient or background well to provide  back-
ground ground-water quality data for  Area 1.  Further,  B.H.S.  has proposed
the entire  perimeter of Area 1 as the point of compliance because all  areas
adjacent to Area  1 are depicted by their consultants as being hydraulicaliy
downgradient.   More recent  (April,  May and June 1986)  data  submitted  to
MDNR show  a different water table configuration  than  depicted  earlier, but
some ground-water mounding is still  apparent and  a large vertically  downward
hydraulic head differential between the upper and lower  glacial  till units
is still  evident.  The uncertainty concerning the hydrogeologic interpreta-
tion brings into  question  the ability of the present wells  to adequately
determine the impact  of  Area  1 or Area 2 on the  ground water.   Because of
the site conditions,  including apparent ground-water mounding and depres-
sions,  and apparent differential vertical hydraulic  head  distribution, the
ground-water flow patterns are not sufficiently defined to design an adequate
ground-water monitoring system.  Upgradient wells may not be truly upgradient

-------
                                                                        11
and  downgradient  wells may  not be  located  or  completed in appropriate
locations and zones to intercept ground-water contaminant plume(s).

     Inadequate interpretation  of  the hydrogeologic features of  the  site
and deficiencies in the ground-water monitoring system would adversely impact
the ability of Area 2 to accept CERCLA wastes, if it is constructed.

     The following  is  a  more detailed summary  of the  inspection  findings
and conclusions.

GROUND-WATER MONITORING PROGRAM DURING INTERIM STATUS

     A 19-well system was initially installed in late 1976 to early 1977 to
meet State  ground-water monitoring  requirements.  B.H.S.  designated six  of
these wells  for Area  1 RCRA  ground-water monitoring  purposes; however,  the
19-well  system  was  considered inadequate  to meet ground-water  monitoring
requirements for the following reasons.  Many downgradient wells never pro-
duced water or only produced  intermittently.   The upgradient and downgradient
wells were  placed  in  different water-bearing zones, precluding meaningful
ground-water quality comparisons.

     A  second  well  system,  consisting of four wells,  was  installed  in
November 1982 to meet Federal and State ground-water monitoring requirements;
however, the  designated  downgradient wells were spaced  too  far apart to
intersect potential  contamination  plumes  from  Area  1.   In  addition,  the
designated upgradient well  was too close to Area 1 and may be influenced by
potential  releases from the landfill.

     Additional wells were  installed in  1984 as part of the second system
to correct  the  above  problems.   A new upgradient well  and  an additional
downgradient well were constructed.   The  previously designated upgradient
well  was then redesignated as being downgradient of Area 1.

     Due to  changes in the well networks,  no  statistical  analysis  was done
against background  data until  1985.   At that  time,  significant  statistical

-------
                                                                        12
differences  were  found  in  a number  of  the  wells for various  required
parameters.  B.H.S.  is  in the assessment phase  which was  to  begin  in May
1986.

     The present  Area  1 upgradient well  is located within the boundary of
the  proposed  landfill  (Area 2).   If  the new  Area 2 landfill  is issued a
RCRA permit  and  is  constructed,  this well  will  be  destroyed.   Background
data will need to be collected for any new upgradient well.

     Three interceptor  trenches  [Figure  2]  on the east and south sides of
Area 1 may have  the  capability to  intercept shallow  plumes of contaminated
ground water moving  in  an easterly  or southeasterly  direction toward down-
gradient monitoring  wells.   These  trenches  may  be  included in  the  Area  1
ground-water monitoring  plan  if  they are determined to be usable based on
their  design,  construction, ground-water yielding  capability  and  their
position in the ground-water flow system.

Site Hydrogeology

     The hydrogeological  investigations  of  the  site, conducted  by  B.H.S.
consultants,  have not adequately defined the limits of the uppermost aquifer.
The poor quality and confusing interpretations of such information precludes
accurately determining ground-water flow direction(s) to design an adequate
ground-water monitoring system.

     Based on  an  existing potentiometric map  of  Hydrologic Unit B,  four  of
the  five RCRA-designated  downgradient wells may,  in  fact,  be  upgradient  of
Area 1.  The presently designated upgradient well and the other downgradient
well may be the only downgradient wells  monitoring Area 1.

     The shallow water-bearing strata are interpreted by B.H.S.  consultants
to consist of two zones and each is indicated as having ground-water mounds
and  depressions which  make  flow  generalization across the site difficult.
Onsite ponds,  which  are  not  regulated by RCRA  and which  have  been drained,
have further altered  flow  patterns.   It is also difficult to identify an
onsite location  for upgradient  wells due  to  the apparent mounds  and
depressions.

-------
                                                                        13
Ground-Water Sampling and Analysis Plan

     Four documents, issued at different times, have been prepared to describe
ground-water sampling and analysis activities at the site.  The first three
documents were inadequate because they only summarized the Federal and State
monitoring requirements  and  did  not describe activities  needed to comply
with the requirements.

     The fourth document primarily describes proposed monitoring activities
at Area 2 and  is  also  inadequate as a sampling and  analysis  plan for the
site.

Closure/Post-Closure Plans

     Closure and  post-closure  monitoring plans were submitted in 1985 and
were under joint  review  by EPA and MDNR at the time of  the  inspection.

GROUND-WATER MONITORING PROGRAM PROPOSED FOR THE RCRA PERMIT

     The February  1986 Part B  submittal  contains a ground-water monitoring
program for  the   entire  site;  however,   the program  does  not adequately
describe which wells will be sampled to accomplish specific tasks.

     The proposed  point  of compliance  for Area 2 is  inadequate.   It was
based on a simulated  potentiometric map which  used  estimated values for
hydrogeologic parameters  rather than in-situ physical measurements of hydrau-
lic conductivity  and hydraulic head distribution.   Monitoring system and
point of compliance evaluations must be based on actual  physical  measurements
rather than  estimated values.

     Because  the  hydrogeologic interpretations for the site are not  adequate,
the proposed  monitoring system may not comply with RCRA ground-water monitor-
ing requirements.    The proposed  program  can only be effectively evaluated
after a thorough  hydrogeclogic characterization of the site  is completed.

-------
                                                                        14
     Construction information for some of the wells included in the proposed
program  is  inadequate.   Because of this, the usefulness of these wells in
meeting permitting program requirements is questionable.

TASK FORCE SAMPLING AND MONITORING DATA ANALYSIS

     During  the  inspection,  Task Force  personnel  collected samples from
nine ground-water monitoring  wells,  two leachate collection sumps and two
interceptor  trench  systems.   The sampling and analysis were conducted to
determine if the ground water contains hazardous waste constituents or other
contamination indicators.  The  monitoring wells were  prepared  for  sampling
by B.H.S. and Task Force and contractor personnel.   All samples were collected
by the Task Force contractor (VERSAR, Inc.) except for leachate samples and
samples  from  Interceptor Trench 3 which  were  collected  by  B.H.S. personnel
for the Task Force.

     The analytical  results did not indicate widespread ground-water contam-
ination; however, the majority  of the trenches and all of the drilled cells
in Area 1 are not lined and do  not have leachate collection systems.  Thus,
the potential for leakage from  these disposal  units exists.  In addition to
common naturally occurring cations and  anions, selenium was  found  in wells
B-11A and B-15  at  164 ug/L and  280 ug/L, respectively.  Organic chemical
constituent analyses indicate the presence of 1,2-dichloroethane and acetone
in well  GM-1.  Methylene chloride may also be present  in this  well.  These
findings should  be  further  investigated for confirmation  and  evaluation.

COMPLIANCE WITH CERCLA/SUPERFUND OFFSITE POLICY

     The EPA  offsite  policy  requires  that any TSDF used for land disposal
of waste from CERCLA response actions must be in compliance with the applic-
able technical requirements  of  RCRA.   Interim status facilities must have
an adequate  ground-water monitoring program to assess whether  the  facility
has had  a significant  impact on ground-water  quality.  The  B.H.S.  facility
has not  fully complied with the technical ground-water monitoring  require-
ments for waste management facilities.

-------
TECHNICAL REPORT

-------
                                                                        15
                            INSPECTION METHODS

     The Task Force evaluation of B.H.S.  consisted of:

          Review and  evaluation  of  records and documents  from  EPA Region
          VII, MDNR and B.H.S.

          A facility  inspection  conducted  February 19 through February 26,
          1986

          Sampling and subsequent analysis and data evaluation for selected
          site ground-water  monitoring and  leachate  collection  systems

RECORDS/DOCUMENTS REVIEW AND EVALUATION

     Records and documents  from  EPA Region VII and the MDNR offices were
reviewed before  the  inspection.   B.H.S.  records were reviewed  to verify
information currently in Government files and to supplement Government infor-
mation where  necessary.   Selected  documents  requiring in-depth evaluation
were copied and  subsequently  reviewed.   Records review included evaluation
of facility operations, construction  of waste management  units  and ground-
water monitoring activities.

     Specific documents and records included the ground-water sampling and
analysis plan, the outline  of a ground-water quality assessment  program,
monitoring  well  construction  data  and logs, site  geologic reports,  site
operations plans,  facility permits, unit design and operation reports, and
operating records showing the general  types and quantities of wastes  disposed
of at the facility and their locations.

FACILITY INSPECTION

     The facility inspection,  conducted in February 1986,  included identifi-
cation of waste  management  units,  identification and asssessment of  waste

-------
                                                                        16
management operations  and pollution  control practices, and  verification of
the location of  ground-water  monitoring wells and the leachate collection
systems.

     Company  representatives  were interviewed  to identify  records  and
documents of interest,  answer questions about the documents,  and explain
(1) facility operations (past and present), (2) site hydrogeology,  (3) ground-
water monitoring  system rationale and  (4) the  ground-water sampling and
analysis plan.

GROUND-WATER AND LEACHATE SAMPLING AND ANALYSIS

      During the  inspection,  the  Task Force collected samples from B.H.S.
ground-water monitoring wells and landfill leachate collection system sumps.
Samples  were taken from two  interceptor trench systems in order to  character-
ize ground-water  quality  in  the zone at  the  base of the trenches.   Most
samples  were collected by an EPA contractor,  Versar,  Inc., Springfield,
Virginia,  and sent to  EPA contractor  laboratories  for analysis.  Splits of
all samples were  offered to B.H.S.,  but the facility declined.  Region VII
and MDNR also declined the offer of sample splits.  NEIC received and analyzed
two split samples.  Data from sample  analyses  were reviewed to further eval-
uate the B.H.S. ground-water  monitoring program and  identify  possible con-
taminants in the ground water.  Analytical results from the samples collected
for the  Task Force are presented in Appendix A.

LABORATORY INSPECTION

     No  B.H.S.  or contractor laboratory facilities were evaluated.   Arrange-
ments with laboratories  which had provided analytical services to B.H.S.
prior to the Task Force inspection had been discontinued.   B.H.S.  had not
sampled  any of the new ground-water monitoring wells prior to the inspection
and, while new contract laboratories  had been  selected,  there was no analyt-
ical data to evaluate.   The  onsite laboratory  had been dismantled when Area 1
reached  capacity in May 1985.

-------
                                                                        17
                   WASTE MANAGEMENT UNITS AND OPERATION

WASTE MANAGEMENT UNITS

     This  section  describes  the  design,  construction,  operation and
management of  waste  disposal  units and waste  handling  and  disposal prac-
tices at  B.H.S.   The discussion presented here  provides  a  framework  for
assessing waste  disposal  unit integrity,  explains the types and placement
of wastes  disposed  of at B.H.S. and  serves  as  a reference to  assist  in
evaluating the potential  for  ground-water contamination in the event that
leakage occurs.

     B.H.S. has operated a number of landfill units and surface impoundments
at the facility [Figure 2].   The landfill  units can be broken down into two
areas:   the Sanitary  Landfill  and  Area 1.  The Sanitary Landfill, located
just south of Area 1, began operation in 1971 and ceased operation in 1977.

     Drawings of the facility in the February 1986 revised Part B submittal
treat Area 1 and  the Sanitary Landfill as one  unit  designated "Previous
Disposal  Area".

     Area 1,  which began operation  in 1977 and ceased operation in May 1985,
comprises approximately 33 trench and drilled cell areas [Figure 3].   It is
currently undergoing closure.   A number of the disposal  units in Area  1 are
not regulated by RCRA [Table 1].

     The  facility's Part B application proposes that a landfill be built on
the western edge of  the property [Figure 2].  This  application is still
under review  by the MDNR. and EPA Region VII.

-------
                                                           18
                   Table 1

       STATUS OF WASTE DISPOSAL  UNITS
                   AREA 1
Facil ity
Designation
Number
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
IN
2N
6N
UN
12N
Drilled cells
Trench eel 1 s
(0-2 through
0-4)
Flammable
drilled eel Is
Alkaline drilled
cells
Alkaline trench
cells
(B-2 through
B-6)
Acid cells
PTA*
Opened
07/77
07/77
07/78
09/77
02/78
08/77
02/79
06/79
06/79
07/79
08/79
10/79
11/79
12/79
01/80
04/80
04/80
04/80
05/80
06/80
09/80
10/80
03/81
11/80
12/80
12/80
03/78


11/79

03/78

04/78



11/79
04/78
01/82
Date Last
Waste Accepted
09/78
09/77
06/79
07/78
10/80
08/78
03/79
06/79
07/79
08/79
09/79
11/79
01/80
12/79
04/80
07/80
06/80
06/80
05/80
09/80
12/80
03/81
12/81
03/81
06/81
06/81
06/80


08/80

06/80

06/80



06/80
06/80
05/85
RCRA
Regulated
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
No


No

No

No



No
No
Yes
Progressive Trench A.^ea

-------
                                                                        19
RCRA-Regulated Landfills

     Of the 33 trench and drilled cell units in Area 1, trenches 21, IN, 2N,
6N, UN and 12N and the PTA received hazardous waste on or after November 19,
1980 [Figure 4].

     Trench 21 was  described  in the B.H.S. Area 1 closure plans as not in
operation after  November  1980;  however,  a  review of waste  disposal  records
for the  unit revealed  that hazardous waste  disposal  occurred  through
December 5, 1980  [Table 2].   Therefore,  the trench was an active unit and
is subject  to regulation  under  RCRA.   The  PTA  and  "N"  trenches  are  clearly
identified as regulated by RCRA.

                                  Table 2
                 HAZARDOUS WASTE LANDFILLED IN TRENCH 21
                       ON OR AFTER NOVEMBER 19, 1980
Waste
Received
11/19/80
11/24/80
11/19/80

11/24/80

11/26/80
11/21/80
11/19/80

12/05/80
Generator
Litton Systems, Inc.
Mobay Chemical
Monsanto Company

Mountain View
Fabricating
Ramsey Corporation
Rival Manufacturing Co.
United Petroleum
Service
Loxcreen Company
Waste
Description
Wastewater sludge
Waste sulfur
Arsenic gallium
trash
Wastewater sludge

Sludge
Wastewater sludge
Zinc sulfate sludge

Wastewater sludge
Quantity*
54 drums
34 drums

24 drums

12 drums
14 cubic yards
8 cubic yards

56 drums
15 cubic yards
*    All drums are 55 gallons

     The trenches were dug on demand, dependent upon the types and amounts
of waste received at the site.   In Appendix B, Figures B-l through B-6 pro-
vide construction details of the RCRA-regulated trenches.
     Operation of the  PTA  began in January  1982  and  ceased in May 1985.
The section was excavated and five separate cells were consecutively filled
as waste was  received.   A  common  leachate collection system services the
PTA.

-------
                                                                        20
     Leachate collection and removal systems were installed in the "N" trench
system and  the  PTA.   Each of the "N" trenches has a separate system while
the PTA has a common system serving all five cells.

     Leachate collection and removal systems for the "N" trenches were con-
structed from a  common  design.   A  4-foot  trench was dug below the bottom
grade of the disposal trench and 1  foot of sand was  laid as a base.   A 4-inch
polyvinyl chloride (PVC) perforated pipe, enveloped in a filter fabric, was
placed on  the sand.  Sand, to a  depth  of  2-feet, was backfilled around and
over the pipe; 1-foot layers, each  of  crushed  rock  and  soil,  completed the
system.   The trenches slope to a sand-filled  sump dug to a  depth  of  2  feet
below the  collection trench.   A  6-inch PVC pipe acts as an annulus  for a
4-inch PVC collection pipe.   Rock and sand were backfilled around the 6-inch
pipe to  a  height above  the anticipated waste levels.   Figures B-l through
B-6, in Appendix B, contain the construction drawings for each "N" disposal
trench and indicate the  location of each leachate collection system.

     The leachate  collection  system for the PTA consists  of  two  lateral
collection  trenches,  oriented approximately east-west, which  drain  to a
north-south trench, which  has  a  collection sump.   The  laterals also  have
collection sumps,  but are  used  instead as observation  sumps  [Appendix B,
Figures B-7 and  B-8].

     The laterals  are 2 feet deep below the trench  bottom grade and  3  feet
wide.   The  trench  sides  and  bottom are lined  with  a  filter fabric  which
envelopes a layer  of crushed  stone.  The  laterals  slope approximately 2%
toward similarly constructed collection trenches.

Nonregulated Landfills

     The remainder of the  B.H.S.  used landfill capacity consists of the
sanitary landfill  and Area  1  trenches  and drilled cells which were  filled
before November  19, 1980.   The latter group consists of trenches  1 through 20.
two organic drilled cell areas,  a flammable drilled cell area, an alkaline

-------
                                                                        21
drilled cell area, trench cells 02 through 04 (04 consists of eight separate
trenches),  special waste  trenches,  an alkaline trench, an acid trench and
an organics trench.

     No construction information is available for the sanitary landfill and
only generic types of waste are known to have been disposed of in this unit
(e.g., sanitary, industrial and municipal wastes).  The landfill has a clay-
soil  cap  and vegetative cover.  Portions  of the sides have  experienced
erosion problems  as  evidenced by runoff gullies  exposing fill  material.
These have  been  observed  by MDNR personnel  in  the past and were observed
during the Task Force site reconnaissance on February 4, 1986.

     The trenches  in  Area  1  were dug with a backhoe to a general depth of
27 feet.  The  MDNR required B.H.S.  to inspect the excavations for pockets
of sand and  gravel.   As they were found, B.H.S. was required to remove as
much of the pockets as possible.   Usually the trench was widened or deepened
to excavate as much of the sand as possible.   The trench was then backfilled
with local  clayey  soil  to  the approximate original dimensions.   Waste was
then placed  in  the trench  and the unit  covered with soil from the site.

     The drilled cells  were  constructed by  a 3-foct-diameter auger to an
approximate depth of 27 feet.   Drums were vertically stacked to a height  of
seven drums per cell.   The remaining volume was  backfilled and covered with
soil from the site.  In each drilled cell area,  the number of cells drilled
was dependent on the amount of waste to be disposed of.

Surface Impoundments

     Three surface impoundments  (SI-1,  SI-2  and  SI-4) are currently opera-
tional  on  the site [Figure 2].  These  are to be  replaced  by tanks,  as
described in the Part B application.   A fourth impoundment,  SI-3T,  has been
drained and  is  not in  use.  The  numbering  system  of  these impoundments has
changed through the years,  which has caused some confusion in following the
history of each unit.

-------
                                                                        22
     Two of  the  impoundments were constructed in 1977 and were identified
as Lagoons 1 and 2.  They were used for the storage of water used for truck
washing and water removed from the active trenches at that time.  Both were
renovated in 1983 with the installation of a clay liner and a leachate col-
lection system.  The  capacity of these lagoons  (50,000  gallons each) was
not altered.   The units were renumbered.  Lagoon 1 became SI-2 and Lagoon 2
became SI-1.   Both now store leachate from the PTA and "N" trenches.

     Surface impoundment  SI-3  was built in 1981  originally as  a  disposal
trench, but  was  never used.   A  section was dammed off  and  acted as an
impoundment which  held surface runoff  from  Area  1.   In 1983,  it was  pumped
out and spray  irrigated,  then SI-4 was built  over  much  of the old area.
The remainder of the old excavation was backfilled with soil.

     In 1983,  surface  impoundment SI-3T was built  to  act as  a temporary
storage unit while SI-3 was  being rebuilt.  Impoundment  SI-3T is  not  lined
nor does it  have a leachate  collection  system.   It  is  still present  onsite
but is drained and inactive.

     SI-4 has a 3-foot compacted clay liner and a leachate collection system.
The capacity is approximately  150,000  gallons.   B.H.S. considers  this as a
replacement for SI-3.

     The  leachate  collection  system  for  each  surface  impoundment was
installed beneath the clay liner and consisted of a minimum l^-foot-deep by
10-foot-wide trench in which a 3-inch layer of sand was placed.   The trench
was sloped 0.5%.   A 4-inch perforated PVC pipe was wrapped in filter fabric
and placed on  the  sand  base.  The remainder of  the trench was  backfilled
with sand.   The  perforated  PVC pipe was connected  to  a  4-inch PVC riser
used to remove collected  leachate [Appendix B,  Figures B-8 and B-9].

FACILITY OPERATION

     Since the site has  not received waste since May 1985, no waste accept-
ance activities could be  observed  during the inspection.   In many cases, a

-------
                                                                        23
single load of one type of waste was disposed in a single trench or drilled
cell.  The following sections discuss past operation practices.

Waste Acceptance

     The MDNR  issues approvals  for  wastes  to  be  accepted  at  a  TSDF.   These
approvals are based on a review of composition, characteristics and hazards
for  each  waste material.   The  TSDF  (in  this  case B.H.S.) submitted  the
requests for  review  and  notified the generator of the approval or denial.
Each waste type was assigned a  sequence code by the MDNR which they used to
track the waste.   In  this  case, each waste received at the B.H.S.  site is
designated as BHSXXX.

     A laboratory  for  analysis  of incoming wastes  was  in  use onsite during
the  active period  of Area  1.  Due to the  landfill  being shutdown,  the  lab-
oratory has been dismantled  and the  equipment  has  been mothballed.  If  the
proposed landfill  (Area  2) is  opened,  the laboratory will be reactivated.

     B.H.S.  relied  heavily  on  customer  waste characterization data  for
approval  submissions to  the  MDNR.   Once a waste was approved by the State
for  disposal,  B.H.S. again relied heavily on the customers to notify them
if characteristics of a waste had changed.

     Once a waste material  had  reached the facility, B.H.S.  mainly performed
a physical,  visual  and  odor examination.   More extensive analysis was  usually
done once a month  for  a given  waste stream.  The  waste analysis plan was
not  very detailed  and  lacked  a  written basis or  schedule  when  sampling  and
analysis  of incoming waste loads would be done.   As an example, the plan
states "B.H.S.  shall  sample a random movement of hazardous wastes.  .  ." but
does not fully identify the procedures  to follow in order to determine what
is sampled, when and  how often.  The text  refers  to monthly sampling of
high volume generators but does  not  identify the  sampling frequency of  low
volume generators.

-------
                                                                        24
     The waste analysis plan  indicates only that the first  shipment of each
waste stream was tested for free  liquids.  There was no procedure to ensure
later shipments were similar  to the  first one.  If the waste was identified
as having greater than 70% moisture  content,  the waste was  tested daily for
percent volatiles.

     As B.H.S.  did  not conduct their own analysis of waste as part of the
approval process, they relied on  the generator  not  only  to  submit  true  and
valid data for approval purposes  but also to  alert B.H.S. to any waste changes.
B.H.S.'s waste  analysis was  not designed to  identify changes  in  waste  from
the original  submittal,  but  to identify  if  the waste  could be  handled  at
the site.   In order  to identify changes  in waste  from  the original  submis-
sion,  B.H.S.  stated  that  they would  review  analyses for  large  generators
(those  disposing  on  a weekly  basis), yearly, moderate generators  (those
disposing on a monthly basis), e*/ery 2 years, and other generators when pro-
duction methods would  alter  physical characteristics.   These time  frames
were inadequate when based on  the minimal analysis B.H.S. performed.

     B.H.S.  identified  the  following waste streams which we^e  not  to be
handled at the facility.

     1.    Ignitable wastes
     2.    Reactive wastes
     3.    Volatile waste  having a vapor  pressure  of greater than 78 milli-
          meters of mercury at 25° C.
     4.    Bulk liquids  and  sludges with more than  75% liquid by weight,
          having free flowing  liquid, which were free flowing themselves or
          contained more than  5%  by weight organic liquid

Waste  Handling

     After the waste material was  checked at  the facility's front gate, the
waste  was directed to  either  a storage  location or  the designated disposal
unit.   Drilled cells were drilled literally  on  demand.   Trenches took more

-------
                                                                        25
time to  construct  since  they  had  to  be excavated and the  later ones had to
have a leachate collection system installed.   In some cases, a single  waste
was placed in a trench.

Inspection Procedures

     No  formal  record of inspections conducted by B.H.S.  prior to January
1984 is  available.   From November 1980 through December 1983, the visitor
sign-in  log  served as the record  of  inspection  results.   Few  problems were
recorded during this  period  as most activities consisted of pumping water
from open trenches to the impoundments.

     On  January 23,  1984, an  inspection  log was initiated  and maintained
along with inspection results.   Daily inspections were performed for the
following items:   surface impoundments,  emergency  equipment,  storage  and
unloading areas, site fencing,  landfill  surface-water diversion  berms and
proper soil  cover on disposal  areas.

Leachate and Surface Runoff  Handling

     Throughout the operating life of Area 1, surface runoff and  water found
in open  trenches was  collected  and sprayed on  the cover of  closed sections
of Area  1.   In  all  cases,  the liquid was analyzed by B.H.S. and  found not
to meet hazardous waste  characteristic criteria [10 CSR 25.4.010(2)  through
(5) - 40  CFR Part  261 Subpart C].  Nonetheless, much of this  liquid was a
hazardous waste since it did come in contact with landfilled hazardous waste.

-------
                                                                        26
                             SITE HYDROGEOLOGY

HYDROGEOLOGIC UNITS

     The facility  is  situated  in an area characterized by wind-blown soil
and glacial deposits which overlie bedrock formations consisting of shales,
limestones and  sandstones.   The  wind-blown or loessial deposits comprise
the uppermost  layer  which consists  of clayey silt to very silty clay that
becomes sandy  near  the  base.   This  deposit  includes  the  tillable  soil  in
the area and ranges in thickness up  to 20 feet.

     The loessial soil is underlain  by a layer of oxidized glacial  till, an
interface  zone  and a  layer of  unoxidized glacial  till.  The  loess  and oxi-
dized till have  been  designated  the "A" hydrologic  unit and  the unoxidized
till and  residual  soils  have  been  designated  the "B" hydrologic  unit
[Table 3].   These units  make  up  the uppermost water-bearing zone for RCRA
ground-water monitoring  purposes.   The  "A" unit consists of sandy clay to
sandy,  silty clay and the "B"  unit  consists  of silty  clay near  the  top  but
is primarily a sandy, silty clay.

     A series of limestone and shale bedrock formations underlies the site.
Underlying the limestones and shales,  at a depth of 350 to 500 feet, is the
St.  Peter  Sandstone which serves as a major  regional  water supply  aquifer.
Other water-bearing strata occur at  greater depths.   Table 3 shows the  hydro-
logic  units  identified  at  the  site  and  their  designation  by B.H.S.
consultants.

GROUND-WATER FLOW

     Two flow regimes are present for  the area,  one for the bedrock and one
for the overlying glacial deposits.   The flow direction in the bedrock  forma-
tions,  including the St.  Peter Sandstone,  is to  the northeast.   Flow direc-
tion in the  overlying  glacial  deposits is generally believed to be to the
south and  southwest  but  locali?ed  ground-water  mounds and depressions  at
the site and the difficulty  in interpreting subsurface information, makes

-------
                                                                        27
it difficult  to  determine specific ground-water flow directions and rates
within portions of the site.   Additional information and revised interpreta-
tions are  needed  to  clearly  define the hydrogeological characteristics of
the  site  including local  ground-water  flow  patterns  and potential pathways
of pollutant migration.
                                  Table 3
                    CLASSIFICATION OF HYDROLOGIC UNITS
Geol
Name
Loess
Oxidized
Unoxidized till
Residual soil
Sulfur Springs
Snyder Creek
Cal laway
Kimmswick
Decorah
Plattin
Joachim
St. Peter
Powell-Cotter
Jefferson City
Roubi doux

ogic Unit
Lithology
Silt
Clay
Clay
Clay
Shale
Shale
Limestone
Limestone
Shale
Limestone
Limestone
Sandstone
Limestone
Dolomite
Sandstone/
1 imestone

Thickness
0-20
0-60
40-190
0-20
0-20
0-20

55-60
20
75-95
75
110-125
325-345
130-165

150+
Hydrologi
Approx. Depth

0-60

80-250






350-500
450-600

900-1200


c Unit
Designation
A
A
B
B
C
C
C
c
c
c
c
D
P
E

F
     Hydrogeologic work by  Woodward  Clyde Consultants (WCC), Kansas City,
Missouri, B.H.S.'s consultants,  identifies a  number of ground-water mounds
and depressions at the site.  The  ground-water  flow regime  at the  site has
not been clearly  defined  and no true upgradient  location  for  Area 1 has
been clearly  identified.  Although recent  (April, May and June  1986) water
level  data  submitted  to  MDNR show a different  water  table  configuration
than WCC, the problem of designating an upgradient or background well  loca-
tion for Area 1 has not been resolved.   Additional hydrological  investigation
should reveal whether an acceptable background location or locations car  be

-------
                                                                        28
identified  in  an area  which  is  hydrologically separated from,  although
perhaps not upgradient of, Area I.

     Because of  the  lack  of clear  definition  of the  ground-water gradients
at B.H.S.,  it  is  not  presently clear  where  and at what  interval(s)  a  truly
representative upgradient/background  well  or  wells  could be constructed.
The three  interceptor trenches  along  the east side  and a portion of the
south side of Area 1 may be considered for monitoring along this portion of
the proposed point of compliance  for  this  area.  Consideration  should also
be given  to installing additional interceptor trench  systems  around the
remainder of Area 1 as wells may not provide a feasible means of monitoring
ground-water quality  in  the  low  permeability terrain which  characterizes
this  site.  The  uncertainties caused  by  the difficulty  of defining  ground-
water gradients in this area shed further doubt on the feasibility of clearly
establishing acceptable upgradient or  background and downgradient locations
to monitor this site effectively with  wells.

     Two ponds on  the site,  which were  not  regulated  by RCRA since they
held  stormwater runoff, were drained in October 1985 and were considered by
B.H.S.  consultants to have contributed to ground-water mounding.  With their
removal, the associated  mound  should  disappear over time and result  in a
different ground-water  flow pattern.   WCC  was of the  opinion  that  newly
installed wells used to measure ground-water elevations may not have reached
hydraulic equilibrium.  This  further  leads to the conclusion that ground-
water gradients,  as  now measured, will  change over  time.   Also, if new
interceptor trenches  are excavated and if existing interceptor trenches  are
pumped  to  maintain lower  hydraulic  head,   these  activities  will affect
ground-water flow patterns.

     The following is  a  discussion of each of the ground-water hydrologic
units that make up the uppermost aquifer at the site.

-------
                                                                        29
Hydrologic Unit A

     This unit is showing both downward and horizontal hydraulic gradients.
Based on  calculations  by WCC, the downward flow is greater than the hori-
zontal  flow.   Three  ground-water mounds have been  tentatively  identified
and depicted  as  being:   (1)  around  the  present  impoundments  and stretching
to the west and northwest toward the drained ponds, (2) in Area 1 along its
eastern  border,  and (3)  an  area near the northwest  corner  of  the site
[Appendix C, Figure C-l].

Hydrologic Unit B

     This unit contains  sand lenses  located  from place  to  place.   WCC  does
not feel the lenses are continuous or interconnected.   This opinion has not
been supported by  adequate  field testing.   Ground-water  flow in the unit
appears to  radiate  from  the  mounds  but  probably has a net  southeasterly to
southwesterly direction  across  the  site.   Three ground-water mounds and a
depression have been tentatively identified.   The mounds are shown as being
at the approximate location of Unit A's first mentioned mound,  at the north-
west corner of the site, and along the east boundary  of the proposed landfil"
The depression appears to be located in the vicinity  of Interceptor Trench 3
along Area 1's eastern boundary [Appendix C,  Figure C-2].

     Much of  the  water  level data for Hydrologic Unit B was obtained from
the well  series  which  was installed for permit monitoring purposes.   Many
of these  have  not  been fully developed according to  WCC.   These wells  may
also not  show hydraulic  stability  because of  the  intermittant purging
required  for  development.   A true picture of  the  ground-water  gradients
was,  therefore,  not  obtainable  at the time of the  inspection.   Additional
hydrologic site  characterization  is  needed to clearly define both  vertical
and horizontal flow patterns including hydraulic head  distribution  and  per-
meability characteristics of  the  site.   More recent  (April, May and June
1986)  water level data  submitted  to  MDNR show a different  water table  con-
figuration than depicted  b>  WCC  in  the February 1986 Part B application;
however, some ground-water  higns  within the  site are  still apparent and a

-------
                                                                        30
large  vertically  downward hydraulic head  differential  is  still evident.
These  need  to  be  evaluated with respect  to  their influence on potential
pathways for contaminant migration.

Ground-Water Flow Summary

     Ground-water flow  from mounded  areas  within  an  aquifer  would  normally
be expected  to  form radial flow patterns.   If  this  is truly the case at
B.H.S., as depicted for Hydrologic Unit A by WCC, an upgradient location is
not available within the site; however, a suitable location(s) for determin-
ing background ground-water quality may be an acceptable alternative depending
on the  results  of  further hydrogeological investigation.    Further,  the
potentiometric surface maps presented by WCC in the February 14, 1986 Part B
application show decreasing hydraulic head between Hydrologic Units A and B
which provides a strong potential for vertically downward flow [Appendix C,
Figures C-l and C-2].   Therefore, if leakage from old disposal areas occurs,
it may  be  expected  to move downward and  would  not be  detectable by wells
constructed in Hydrologic  Units  A  and B  adjacent  to the disposal  areas.
The potentiometric surface map for Hydrologic Unit A indicates a ground-water
mound in approximately  the same  area as  a ground-water  depression  in the
underlying Hydrologic Unit B.   If this hydraulic head differential  is real,
it provides the potential for downward movement of ground water and supports
the possibility that  contaminants  leaking into ground water in this  area
could move  downward  to  some  unknown depth before moving laterally.   Thus,
they may escape detection  in  monitoring wells or  trenches  located adjacent
to past waste disposal areas.

     The simulated  potentiometric  surface  map "A" Unit [Appendix C, Figure
C-3] shows potentiometric contours  as much as 20 feet above the ground sur-
face.    None of the  piezometric surface maps generated by this model,  with
estimated or assigned values  for this site, are acceptable.

     B.H.S.'s hydrogeologic investigation  reports  were prepared by their
consultants, D.E.  Klockow  and  Associates  (Klockow) and Woodward Clyde Con-
sultants (WCC).    Review  of reports prepared by these  consultants reveals

-------
                                                                        31
that a number of deficiencies remain.  The Task Force came to the following
conclusions and recommendations as a result of the review of these reports.

     1.    B.H.S. has  failed  to  fully characterize the hydrogeology of the
          site, particularly with respect to:

          a.    The nature, extent  and  permeability characteristics of the
               fracture network in Hydrologic Unit A

          b.    The permeability characteristics of Hydrologic Unit B regarding
               its integrity as an aquitard

          c.    Evaluation of the broken,  jointed  and  solutioned bedrock  in
               Hydrologic Unit C and its relationship to the overlying strata
               which may constitute pathways for contaminants to escape the
               site undetected

          d.    The nature and extent of sand lenses or stringers which have
               been observed within the glacial till layers which constitute
               Hydrologic Units  A and B

          e.    Assessment of vertical  hydraulic  head distribution beneath
               the site to the  depth of the first aquiclude, aquifuge or
               zone where horizontal ground-water flow dominates  vertical
               flow components

     2.    B.H.S.  has failed  to define the limits and hydrogeologic character-
          istics of the uppermost aquifer.

     3.    B.H.S.  has  failed  to  comply with the terms  of the  EPA August 21,
          1985 Compliance Order requiring deficiencies in the site character-
          ization  and ground-water  monitoring  system to  be corrected.

     The  failure to fully characterize  the site hydrogeology and define the
limits of the  uppermost  aquifer,  as required,  will result in the  facility

-------
                                                                        •39
                                                                        Ji.
being unable to  fully comply with  Part B  requirements  found  in 40 CFR Part
270.14(c).

     Information addressing the above deficiencies must be provided before
an adequate ground-water  monitoring  system can be designed and evaluated.

     It is the  consensus  of the Task Force that B.H.S. should be required
to provide:

     1.    Adequate characterization of the hydrogeology of the site;  including
          at  a  minimum:

               Definition of the nature,  extent and permeability character-
               istics of the fracture network in Hydrologic Unit A utilizing
               both laboratory and field  testing methods.

               Definition of the permeability characteristics of Hydrologic
               Unit B regarding its  integrity as an aquiclude using both
               laboratory and  field testing methods.

               Evaluation of the broken,   jointed and solutioned bedrock in
               Hydrologic Unit C and  its  relationship to the  overlying  strata
               with respect to the potential  pathways for  contaminant migra-
               tion using cores and in-situ field testing  methods.

               Definition of the nature and extent of sand lenses or  stringers
               within the glacial   till layers,  whether they  are intercon-
               nected,  are isolated pockets or sinuous  sand stringers crossing
               portions  of the site or extending offsite.

               Definition of the vertical  hydraulic head distribution beneath
               the site  to the depth  of the first aquiclude thoroughly  enough
               to show  the three-dimensional  characteristics  of the ground-
               water flow system.

-------
                                                                   33
2.    Provide additional  data  and  interpretive information needed to
     fully characterize  the site  hydrogeology  in  sufficient  detail to
     provide a basis for an integrated ground-water monitoring system.

3.    As a result of the site characterization studies, define the limits
     of the uppermost aquifer.

4.    Present a modified ground-water monitoring system.

-------
                                                                        34
            GROUND-WATER MONITORING PROGRAM UNDER INTERIM STATUS

     Ground-water monitoring at the B.H.S. facility has been conducted under
the requirements  of  Federal  and State interim  status  regulations  and  two
State hazardous/solid waste  permits.   Prior to November 19, 1981, a State
permit defined monitoring requirements and a well system.   A number of wells
in this system were specified as RCRA ground-water monitoring wells.   After
November 19, 1981, the  Federal  and State regulations  and  a State permit
defined monitoring requirements.  B.H.S.  requested a waiver from RCRA ground-
water monitoring requirements but it was denied by EPA Region VII.

     The following is an evaluation of the monitoring program between November
1981,  when  the  ground-water  monitoring provisions of the RCRA regulations
became effective, and February  1986, when the Task  Force investigation was
conducted.

REGULATORY  REQUIREMENTS

     Ground-water monitoring  at the facility has been  regulated by both
Federal  and  State requirements.   Federal requirements  (40  CFR  Part 265,
Subpart F)  were  in effect  from November 1981 through  November  1983.   Tne
State ground-water monitoring regulations [10 CSR 25-7.011(10)] took effect
in lieu of  the  Federal  regulations in November  1983  when  the State was
granted Phase 1 interim authorization.

     Two State  permits  have  also outlined ground-water monitoring at  the
site.   These are Solid Waste Disposal  Area Operating Permit (SWDAOP) 721901
issued on  May  25, 1977  and  Hazardous Waste Facility  Permit  (HWFP)  T
-------
                                                                        25
SWDAOP 721901

     The MDNR  issued  this  permit on May 25,  1977.   It  required  quarterly
monitoring for total organic carbon (TOC),  pH, heavy metals and conductivity.
The following  were  also to be analyzed initially:  lead, chromium, copper
zinc,  cadmium,  nickel,  fluoride,  iron and manganese.  Monitoring began in
August 1977  and  two quarters  of  sampling were  completed  in  that  year.  The
permit required the installation and monitoring of 17 wells and the monitor-
ing of two existing wells (System 1).

     On January 1, 1978, the MDNR imposed additional parameter and sampling
requirements.  These  are  outlined  in  Table 4  along  with  their frequency.
Sampling under  this permit  overlapped with  the interim  status  requirements
which  follow.

40 CFR Part 265, Subpart F

     Monitoring  under  the  Federal  requirements  began in November 1981.
These  are  outlined  in Table 5 along with their frequency.  Six wells from
System 1 were  designated  to serve  as RCRA  monitoring wells.   In  December
1983,  System 1 was  replaced for RCRA ground-water  monitoring  purposes by
wells  required by the following State permit (HWFP TSD 122282001).

HWFP TSD 122282001

     The MDNR  issued  this  permit on December  22,  1982.   It  referenced  sam-
pling  and analytical requirements found in 10  CSR 25-7.011(10)(c), the State
hazardous waste  regulations  which  were  identical to  40  CFR Part  265.  It
also required  the  installation of  four wells  (System 2)  and  three inter-
ceptor trenches as ground-water monitoring points and indicated five  surface
water  sampling points.

-------
                                                       36
                 Table 4
   ADDITIONAL SAMPLING AND MONITORING
      REQUIREMENTS IMPOSED BY MDNR
Parameter
PH
Redox potential
Specific conductivity
TOC
Chemical oxygen demand (COD)
Hardness (total as CaC03)
Chloride
Iron
All of the above
Biochemical oxygen demand (BOD)
Suspended solids
Total dissolved solids
Turbidity
Extractable oil
Fecal coliform bacteria
Alkalinity
Phenol s
Nitrate as nitrogen
Sulfates
Fluorides
Cyanides
Heavy metals2
Gas chromatograph scan for
chlorinated hydrocarbons and
pesticides
Arsenic
PCBs (specifically)
Frequency
Quarterly1
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1
Yearly on July 1


Yearly on July 1
Quarterly
Annually
Quarterly is defined as the following periods.
1st quarter:
3rd quarter:

4th quarter:
              January 1-March 31
              Report due April 1
2nd quarter:  April 1-June 30
              Report due July 1
              July 1-September 30
              Report due October 1
              October 1-December 31
              Report due January 1

Heavy metals include:

Arsenic                Copper
Barium                 Lead
Cadmium                Manganese
Hexavalent chromium    Mercury
Total chromium         Nickel
                                    Selenium
                                    Silver
                                    Zinc
The total of each is to be reported.

-------
                                                                        37
                                  Table 5
             GROUND-WATER SAMPLING AND MONITORING REQUIREMENTS
                          IMPOSED BY EPA AND MDNR
Parameter
Chloride
Iron
Manganese
Phenols
Sodium
Sulfate
pH
Specific conductivitv
TOC
Total organic halide
(TOX)
Arsenic
Bari urn
Cadmium
Chromi urn
Fluoride
Lead
Mercury
Nitrate (as nitrogen)
Selenium
Si 1 ver
Endri n
Lindane
Methoxychlor
Toxaphene
2,4-D
2,4,5-TP, silvex
Radium
Gross alpha
Gross beta
Col iform bacteria
Frequency
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly

Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
for
for
for
for
for
for
for
for
for
for

for
for
for
for
for
for
for
for
for
for
for
for
for
for
for
for
for
for
for
for
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi

fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
fi
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst

rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
rst
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,

year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
year,
annually thereafter
annually thereafter
annually thereafter
annually thereafter
annually thereafter
annually thereafter
semiannual
semiannual
semiannual
semiannual

semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
semiannual
iy
iy
iy
iy

iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
iy
thereafter
thereafter
thereafter
thereafter

thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
thereafter
10 CSR 25-7.011(10)
     In November  1983,  the  State of Missouri was granted Phase 1 interim
authorization.   At that time, State regulations became enforceable in lieu
of Federal ones.   The  State ground-water monitoring regulations are  iden-
tical  to 40 CFR Part 265.   The ground-water monitoring well  system consisted
of the four wells identified above, which was later modified by the  addition
of two we!Is.

-------
                                                                        38
GROUND-WATER SAMPLING AND ANALYSIS PLAN

     Three ground-water sampling and analysis plan summaries (SAPS) and one
ground-water sampling  and  analysis  plan (SAP) can be  identified  as being
prepared  in  response  to  RCRA  requirements.   These  are  (1)  a  SAPS  which was
part of a December 31, 1981 permit application to the MDNR; (2) a SAPS found
in the  November  15,  1983 revised  Part  B;  (3)  a SAPS  found  in the  April 16,
1984 revised Part B and (4) a SAP contained in the February 14, 1986 Part B.

December 31, 1981 SAPS

     A  SAPS  was  prepared as part  of  a  December 31, 1981 permit application
to the  MDNR.   The SAP  could be  characterized  best  as an outline from which
a more  extensive, detailed  plan should have been prepared.  Based on this
SAPS, it  appears  B.H.S.  personnel monitored  according to  interpretations
site personnel  made of  Federal  and State  regulations and State  permit
requirements.

     Those requirements outlined in the State permits were followed closely
as all  parameters were monitored.   On November  20,  1981 monitoring began
for Federal  requirements, but only indicators of contamination were analyzed.

November 15, 1983 SAPS

     This SAPS was basically a two-page summary of the  interim status ground-
water monitoring  requirements.   Monitoring  parameters  were listed but pH
was missing  from the  indicators  of  contamination  list.   No sampling or
analytical techniques or methods were described.   No  procedures were listed
for any  sampling  or  monitoring  activity.   The SAPS  referred to new wells
(System 2) which were to be sampled to develop background data.

April  16, 1984 SAPS

     This SAPS was also basically a  summary  of interim status ground-water
monitoring requirements.  It  contained no more  information on monitoring

-------
                                                                        39
activities at the site than the previous SAPS.  Initial background data was
included with the revised Part B yet the SAPS still described parameters to
be monitored for the first year.

February 14, 1986 SAP

     The SAP was presented in the February 14, 1986 Part B.  It was prepared
to meet the requirements of 10 CSR 25.7.011(10)(2) [40 CFR Part 264.98] and
does differentiate  somewhat  between  the RCRA  requirements  for the  proposed
landfill and  some  of the post-closure  monitoring  requirements  of  Area  1.

     The plan,  as  written,  is not clear whether interim status monitoring
will be conducted  at Area 1.  The Part  B  implies  the  plan  will  be  used  for
interim status purposes but does not specifically state this.

MONITORING WELLS

     B.H.S. has  designated two well  systems at  various  times as their  RCRA
ground-water monitoring  system.   A  well  system  of  16  piezometer wells
(P wells)   and  a deep  downgradient  well were  installed to comply with
SWDAOP 721901.   These were monitored along with two existing wells.  Six of
these wells were  designated  for  the initial  RCRA  ground-water  monitoring
system.

     The second  system  (GM  wells)  initially consisted  of  four  wells with
two wells  added  at  a later date.  This system  replaced the  one above  for
RCRA monitoring purposes.

     A third system  (B wells) was installed primarily to supplement the GM
wells for  use in Area 2's RCRA permit monitoring program.   Certain of these
wells were sampled by the Task Force.  They were picked because their loca-
tions may  intercept  contamination  plumes which originate in Area 1.   Por-
tions of the well  system may  be  used to supplement or replace the  GM wells
in a post-closure perrit ::sued for Area 1.   Certain of the B wells and two
GMW wells,  described in System 2 belovv,  are to be sampled during ground-Water
assessment work at the site.

-------
                                                                        40
     In addition  to  the  well  systems  placed  or  designated  for  RCRA  interim
status monitoring requirements, other wells had been installed and are listed
under  the  proposed  RCRA  permit monitoring scheme for Area 2.  These wells
will be discussed and described in this section under "Other Wells".

     This  section will  include a discussion  of the interceptor trenches
placed on  the  east  and south sides of Area 1.  These trenches are located
between Area 1  and  the designated downgradient wells  GM-3 through  GM-5.
They,  therefore,  may have the potential  to  intercept  contaminant plumes
which  may  not  reach  the  monitoring wells.  These  trenches  have  become  for-
gotten members  of the  ground-water monitoring plan  for  the site  and  should
be included as  monitoring points.

     The following  is  a  discussion of  the wells used for RCRA  ground-water
monitoring under Federal  and State requirements.

System 1

     The P wells and a companion downgradient well were installed in response
to SWDAOP 721901.   Sixteen P wells were installed along with one identified
in the permit  to  be located in the southeast corner of Area 1.  This well
has been identified by B.H.S.  consultants as  both MW and DMW (hereafter MW).

     Two existing water  supply wells were also  designated  b> the permit  to
be part of  the  system.   These were the Zykan Well  and  the Old/Wash/Truck
Wash Well  (hereafter the  Truck Wash Well).

     This first well system [Appendix D, Figure D~l] was sampled to  monitor
ground water for the State from August 1977 through June 1983.

     B.H.S. designated six wells from this system to be their RCRA monitor-
ing system  for  Area  1.   The upgradient ones  were the Zykan and Truck Wash
Wells which are completed  in  the  deep  sandstone aquifer rather  than  in the
shallow aquifer immediately underlying waste  disposal  units.   The downgra-
dient ones were wells  P5,  P8, P10 and  MW.   These were sampled  for  RCRA
monitoring purposes from  November 1981 through December 1982.

-------
                                                                        41
System 2

     The entire  first  system  was  deemed  inadequate  by  the  MDNR  for  reasons
discussed in the Well Construction section which follows.  The four GM wells
replaced System  1  in November 1982 (GM-1 through GM-4).  These wells were
initially installed to meet the requirements of HWFP TSD 122282001.

     Well GM-1 was  designated as  upgradient  and wells  GM-2 through  GM-4  as
downgradient.  Sampling  and  monitoring of these wells [Appendix D,  Figure
D-2] for RCRA  began in December 1983 and continued through December 1985.

     The GM wells continued to be monitored for RCRA when the MDNR  received
Phase I  authorization.   EPA  Region VII required two wells be added to the
GM  series.   Well GM-5  was  added  in  May 1984  and  GM-1R in July 1984
[Appendix D, Figure  D-2].  Well GM-1R  was designated as  an upgradient well
since well  GM-1 was considered to be downgradient because it was influenced
by the regulated units.   Well GM-5 was designated as a downgradient well.

     Two additional  wells were required  to be  installed  by the  MDNR, GMw-1
and GMW-4,  in  December 1985.   They were  not  part  of the RCRA system but
were used by the MDNR to evaluate the GM wells.  They are used in the ground-
water assessment program for the  site.

System 3

     The B  wells were  installed [Appendix D,  Figure  D-3] to  supplement the
GM wells for Area 2's RCRA permit ground-water monitoring plan.   Certain of
these wells  were  sampled by  the  Task  Force  because  it was felt  they were
located in areas that would intercept contaminant plumes coming from Area 1
or possibly provide new background ground-water quality data.

     These wells should  also  be  considered among others to  supplement or
replace the  GM wells in  Area  1's post-closure  permit.  Many  of  these wells
would,  therefore,  act  as  dual purpose  ground-water  monitoring points.

-------
                                                                        42
Other Wells

     In December  1978,  six additional  P wells were  installed  (wells  P-17
through P-22)  to  meet State sampling and  monitoring  requirements.  These
wells are located to the east, south and north of Area 1 and were considered
to be downgradient [Appendix D, Figure D-4].

     During the period  July  through  October  1981, a  series  of  K wells were
installed.  These were  12  clusters of piezometers placed at various loca-
tions throughout  the  site  to monitor water  levels to  establish hydrogeo-
logic gradients [Appendix D, Figure D-5].

     In October 1985, four additional piezometers were installed to monitor
hydrogeologic  conditions.  These  are wells P-A,  P-B,  P-C and  P-D  and are
located to the west of Area 1 [Appendix D, Figure 6].

Interceptor Trenches

     Three trenches were installed to comply with the requirements of State
Permit HWFP TSD 122282001.   They were designed to intercept flow from Hydro-
logic Units A and B.

     The trenches are pumped once or twice a year and are not on a set mon-
itoring schedule.   The sumps for each trench (trenches 1 and 2 share a common
sump) were designated by the State permit as monitoring points.   Minimal
information is available on monitoring results.

Well  Construction

     The following is a discussion of the known construction  details for
each well  system installed by B.H.S.

-------
System 1

     This system  comprises  the P wells, well  MW,  the Zykan Well and the
Truck Wash Well.   The  P  wells  and well  MW  were installed  from  late  1976  to
early 1977.   The  P wells are all completed 35  feet below  surface elevation
(BSE) and well  MW is 128 feet  BSE.   Few construction  details are available
for well MW  although  a  boring log does exist.   The well was probably con-
structed in  the  same  manner and from  the  same materials  as the P wells.

     Well MW  was  initially  bored to 174 feet  BSE, 6  inches into limestone
bedrock.   A  gravel  layer was  found at 87  to 97 feet  BSE.   It subsequently
caved in, filling the  bottom  of the hole.   The bottom of well  MW's casing
sits on  top  of  the gravel.   The water  quality of samples taken from the
well were, in all  likelihood,  related  to the quality  of water  found  in the
caved-in section of the  boring.

     The P wells  were  constructed by drilling  an  8-inch boring  and  placing
a 3-inch PVC  pipe within it.  All wells were 35 feet  deep and have a 25-foot
screened interval.  Sand was placed as a filter within the boring/well pipe
annulus  to just  above  the top screen.   A  bentonite plug was placed on top
of  the sand  filter and  local  soil  was used to fill in the remaining space
to the surface.   Table  6 provides a summary of the depth,  screened interval
and screened  hydrogeologic  units of the P  wells  and  well MW.    Figure 5
provides the  typical construction  of the  P wells  and,  probably,  well MW.

-------
                                                                        44
                                Table 6
                     SUMMARY OF WELL INFORMATION,
                               SYSTEM 1
                   NOMINAL 3-INCH-DIAMETER PVC PIPE
                           WITH GLUED JOINTS
Well
Number
P-l
P-2
P-3
P-4
P-5
P-6
P-7
P-8
P-9
P-10
P-ll
P-12
P-13
P-14
P-15
P-16
MW
Surface
El evation
(ft. msl)
804,
790,
778,
770.
765.
764,
759.
758.
755.
761.
777.
586.
794.
798.
804.
808.
735.
,9
,5
,3
.0
.9
,3
9
4
7
2
1
.7
.9
5
4
4
5
Screened
Zone
(ft. msl)
795-770
780-755
768-743
760-735
756-731
754-729
750-725
748-723
746-721
751-726
767-742
777-752
785-760
786-761
794-769
798-773
Unknown
Screened
Hydrologic
Unit(s)
A
A
A
A,
A,
A,
A,
A,
A,
A,
A
A
A
A,
A
A
A,



B
B
B
B
B
B
B



B


B
     Many  of  the  P wells never  produced  water  or produced water  inter-
mittently.   Later  hydrogeologic  site  investigators concluded fine-grained
material may  have  plugged  the screens, causing  dry  or  mud conditions in
these welIs.
     The Zykan Well  was  constructed in 1970  to  act  as  a water  supply  for
the site.   It  is  approximately 404 feet  BSE  and draws  water  from  the  St.
Peter Sandstone formation.   The Truck Wash Well also serves as a water supply
well for the site.   There is no available data of its construction or depth.
It  supposedly  also draws water  from the St. Peter Sandstone formation.  No
other information is  known for either well.

-------
                                                                        45
 REMOVABLE
 PVC  CAf

 BENTONITE SEAL
    SELECTED
  GRADED SAND
                              3 In. PVC SCHEDULE  40  PLASTIC PIPE
 .023 In. WIDE  SLOTS^  -
I lo. DIAMETER HOLE     3
    PVC CAP
     FIGURE 5

TYPICAL WELL  CONSTRUCTION
      SYSTEMS  *1  AND  »2
                                          (REVISED FROM RE1TZ  4 JENS, INC.

-------
                                                                        46
     The  system  P wells were deemed  to  be inadequate for the  following
reasons:
     I.
     2.
Fine-grained material  was believed to  have  plugged screens of
certain wells.    This  caused  dry or mud conditions within wells,
making them  unusable  for monitoring purposes.  It was therefore
concluded that certain or all P wells were improperly constructed.

The two upgradient wells were not screened in the same water-bearing
zone as the downgradient ones.   No water quality comparison could
be made between  the  up and downgradient wells because different
water-bearing zones were being monitored.
System 2
     This  system  comprises the GM  wells  (GM-1 through GM-5 and  GM-1R).
Wells GM-1 through GM-4 were installed in November 1982 as replacements for
the System 1 wells.   All were drilled in the same manner as the P wells and
well MW,  although  the  System 2 wells have  4-inch PVC casings.  Sand was
used as  a filter  pack  material in  the  annulus from the bottom to 8 to 9
feet above the  screened interval.   The remaining annular space was filled
with a cement-bentonite grout to surface elevation.

     Wells GM-5 and GM-1R were constructed in May 1984 and July 1984, respec-
tively,  in the  same  manner as the  other  GM wells.   Table 7 provides the
depth,   screened  interval  and screened hydrogeologic  unit  for  each well.
The typical construction  of  these  wells would follow that of Figure 5 but
with a different casing size and depth.

-------
                                                                        47
                                  Table 7
                        SUMMARY OF WELL INFORMATION
                                 SYSTEM 2*
                          NOMINAL 4-INCH-DIAMETER
                              SCHEDULE 40 PVC
                         THREADED FLUSH JOINT PIPE

Well
Number
GM1
GM2
GM3
GM4
GM5
GM1R
Surface
Elevation
(ft. msl)
796.3
812.3
772.8
758.0
777.6
765.3
Screened
Zone
(ft. msl)
700.8-670.3
665.0-636.5
675.8-647.0
682.3-653.0
686.4-631.4
728.0-705.0
                         All  wells  are  screened  in
                         Zone B.
     The system was  deemed  by EPA to have an insufficient number of wells
in order to constitute effective detection monitoring and compliance monitor-
ing programs.  Further  wells  were needed in order to adequately  serve as
points of compliance.

System 3

     This system comprises  the  27 B wells.   Two  wells,  GMW-1 and GMW-4,
were also drilled along with the B wells in  order to monitor the performance
of wells GM-1 and GM-4, as required by the MDNR.   These two wells are not a
pa^t of System 3.

     All of the above wells  were drilled from October through December 1985.
They were started with  a  6-inch boring  in which a 2-inch No.  316  stainless
steel  casing was placed.  The wells are screened in hydrogeologic units  A
and B.  The  B  wells  have 10-foot  screens and  the GMW wells have 20-foot
screens.

-------
                                                                        48
     Two exceptions  are  wells  B18A  and  B19  which  are  constructed  of  2-inch
PVC pipe with  5-foot screens.   These act as  piezometers to monitor sand
lenses in the oxidizec zone (hydrologic unit A).

     Sand was packed between the boring and casing from the bottom to 2 feet
above the  screen.   A 2-foot bentonite plug was placed on top of the sand,
followed by cement-bentonite grout to the surface.  A steel protective cas-
ing was  placed  over the well   and a  concrete  pad poured around the well.

     Table 8 provides  information  on all B and GMW wells.   Figure 6 shows
the typical contruction of the B and GMW wells.

Other Wells

     Wells P-17  through  P-22  and P-A through P-D have 3-inch PVC casings.
They were installed soon after the initial P wells.   It is unknown how they
were constructed,  but  it  is inferred construction procedures  followed  that
of the initial  P welIs.

     Wells P-17,  P-18,  P-20 and P-22 are 50  feet deep and have  40-foot
screens.   Wells  P-19  and  P-21 were drilled 111 feet and 120 feet, respec-
tively,  and  have  40-foot  screens.   Sand filled the space between the bore
hole and casing  just above  the screens.   It is  unknown  if  a bentonite  plug
was used to  seal  off the  space above the  sand  and it  is  assumed local  soil
was used to fill the remainder of the annular space.

     Little construction information is available for wells P-A through P-D
other than their  size, depth and screened interval, which  is  approximately
12 feet.

     Table 9  provides the known construction information for the above wells.

-------
                                                                                           49
                                       i ac e 3
NCM
piezometer*
we' 1 NuiflDer
B-1A
B-2
B-3A
B-4
B-5
B-6A
B-7
B-3A
B-9
B-iCA
B-11A
B-12A
B-12B
B-13
B-14A
B-15
B-16
B-17A
B-17C
B-13
B-13A*
B-19A
B-198*
B-20
B-21A
B-22A
B-23A
GMV- 1
GMV.-4
iS^L 2-INCH-MAME'E^
g or Mor
Well L:
2538N,
2623N,
0502N,
2351N,
2143N,
1900N,
1889N,
1861V
2171N,
2395N,
1378N,
2380N,
2392N,
2160N,
1890N,
1506N,
1320N,
1C46V
1C 3 IN,
3"5N,
877N,
S"6N,
S82N,
1300N,
1574N,
1035N,
195~V
•ts^-g
Dcat1 on'
995E
125 :E
1521E
IbDUt
1812E
139 7 E
1609E
1428E
1 0 5 3 E
959E
1155E
562E
675E
625E
625E
^c
625E
630E
525E
750E
752E
1025E
ir_5r.E
1425E
142EE
142 5 E
1150E
2C9BE
VE-. :N-ORMA*:ON SYSTEM 3 AND GMW WELLS
NO 516 STAINLESS STEEL, THREADED, FiLiSH-JCINTEj 5:;E
E 1 8 v a t " o r.
tne grcuic
Surface
1 ft "nsi ;
308
"91
' / L.
76"
760
"51
""3
790
799
304
793
307
SO7
800
792
7°"
^ ~ -,
76i
759
748
748
745
746
"69
778
750
794.
"61
9
2
3
3
Q
3
~
3
7
^
a
;
7
2
a
5
4
4
0
5
6
-4
5
0
5
3
0
Top of
3i ser
311
793
774
768
753
763
782
792
301
806
793
809
810
802
793
791.
776
762
762
750
749
746.
748
771
779
752
738 .
795
762
48
22
88
94
57
23
09
27
54
24
95
34
55
75
2
69
81
39
84
23
66
"9
52
46
56
56
S 3
96
61
of Hole
Bottom (.msl )
60
49
38.
38.
28
35
56
59
55
57
57
116
65
PI
56.
55
54
79
47
43
29
36
2?
54
49
41
124
104
75/748
/744
16/734.
847728
17/732
7726.
/722.
7731.
34/743.
/747
7736
5/692
41/742.
/739
75/735
,'732
5 7721
7681
7712
82 '704
33/718.
33/710.
5 ''"' 2 ^
7 7 IS!
33/728
"/709"
^P 71 c
,'670
7657
15
72
54
53
9
9
7
46
7
1
H
.39
,7
45
8
. 1
4
4
.37
, 77
.57
9
6
6 7
5
42
3

Wate- L
January
Cry
754
760.
763
736
747
762.
761
748
"54
754
Dry
748.
743
758
"56
752
6S3
741
~i "• 9
733
733.
733
751
752
734
687
.eve1
'" i986

1
K
9
3
s
0
o
6
Q

7
9
3
7
. 1
i
I
q
3
0
7
c
'
7
-
5
Piezometers constructed r'roc scneauie 4C P

-------
                                                                           50
          STEEL PROTECTIVE CASINO
          WITH LOCKING MECHANISM
      81< STAINLESS STEEL THREADED
  FLUSH  COUPLED 2 In. ID WELL  CASIN<
    UPPER  10 Ft. OF ANNULUS FILLED
 IIT H  EXPANDING NEAT CEMENT GROUT'
  ANNULUS FILLED  WITH NEAT CEMENT
    GROUT, 10* BENTONITE ADDED
               UNSATURATED ZONE  \
                SATURATED ZONE
    DESIGNED FILTER PACK AROUND
    WELL SCREEN TO HEIGHT fi Ft.
     ABOVE SCREEN

O X IDIZED GL ACIAL PR I F T

 UNOXIDIZED GLACIAL DRIPT
                                              VENTED  CAP
                                             DRAIN HOLE
     4 In. X 8 Ft. CONCRETE PAD
(ANNULUS SEALED WITH CERTIFIED
(COARSE GRIT SODIUM BENTONITE TO A
* THICKNESS OF ? 2  Ft.
  816-STAINLESS STEEL  2 In.  ID
  WELL SCREEN 10  Ft. IN LENGTH

  WITH DESIGNED SLOT SIZE



 -8 In. • 10 In. DENSE
  PHASE SAMPLING CAP
  PLUG ON  BOTTOM OF  WELL SCREEN-

                                 NOMINAL 6 I or.
                                 FIGURE 6

                         TYPICAL WELL  CONSTRUCTION
                          SYSTEM »3  AND GMW WELLS
                    (Rcviied for Wood ward-Clyde Consultants)

-------
                                  Table 9
                        SUMMARY OF WELL INFORMATION
                 WELLS P17 THROUGH P22 AND P-A THROUGH P-D
                     NOMINAL 3-INCH-DIAMETER PVC PIPE
                             WITH GLUED JOINTS
Well
Number
P17
P18
P19
P20
P21
P22
PA
PB
PC
PD
Surface
Elevation
(ft. msl)
800.
748.
755.
764.
791.
779.
793.
793.
796.
796.
2
5
5
6
2
8
5*
5*
0*
0*
Screened
Zone
(ft. msl)
790-750
738-698
765-725
755-715
781.741
770-730
742-754
714-726
716-728
745-757
Screened
Hydro! ogic
Units
A,
B
A,
A,
A
A,
A,
B
B
A,
B

B
B

B
B


B
              *    Approximate

     The K  series  of  wells  are  clusters  of ^-inch  and  1^-inch wells.   Each
cluster was  placed  to monitor water  levels in one  or more  of the  following
zones:   at  the  oxidized/unoxidized interface,  at a depth of approximately
50 feet below  waste disposal  and at depths below the 50-foot level to the
bedrock.  It is  unknown which size corresponds to  which  specific  well  in  a
cluster.  The holes were bored by 6-inch and  3^-inch hollow-stem augers and
4-inch solid core continuous flight augers.   Screened intervals  ranged from
10 to 20 feet depending upon the depth of the zone to be monitored.  Screen
size was 0.5 millimeter.

     The annular space  between  the screened  interval  and  the total depth
was filled  with  sand.   The remainder of the annular space  above  the  sand
was filled with a cement/bentom'te grout.

     Table 10 provides the available construction details for each cluster.

-------
             Table 10

    SUMMARY OF WELL INFORMATION
NOMINAL VINCH AND 1VINCH-DIAMETER
    PVC PIPE WITH GLUED JOINTS
                                                   52

Well
Number
K-1-ox*
K-l-80'*
K-l-sa*
K-l-br*
K-2-ox
K-2-80'
K-2-sa
K-2-br
K-3-ox
K-3-801
K-3-1101*
K-3-br
K-4-ox
K-4-801
K-4-1201
K-4-br
K-4-brr*
K-5-ox
K-5-801
K-5-sa
K-5-br
K-6-ox
K-6-si*
K-6-br
K-7-ox
K-7-si
K-7-br
K-8-ox
K-8-si
K-8-br
K-9-801
K-9-sa
K-9-br
K-10-801
K-10-br
K-ll-ox
K-ll-sa
K-ll-br
K-12-br
* Note:
ox -
80 =
sa =
si =
110 -
br =
brr =
Surface
El evation
(ft. msl)
780.6
780.3
781.8
781.8
796.6
797.9
797.0
797.0
777.4
776.5
778.8
778.8
791.7
791.5
792.2
792.2
791.9
773.1
771.4
772. 1
772.1
746.3
745.5
745.9
770.6
769 7
770.1
793.9
791.9
792.8
736.35
736.5
736.5
732.9
732.5
759.2
759. 6
759.2
768.1

Screened
Zone
(ft. msl)
721.6-731.6
725 -705
672 -662
606 -604
739.6-741.6
741 -721
677 -667
606.4-604.4
713 -703
718 -698
688 -658
580 -578
748 -738
734 -714
672 -662
672 -662
582 -557
734.6-724.6
715 -695
677 -667
605 -603
735.3-727.3
644 -624
573 -568
737.3-727.3
772 -762
581.4-576.4
745.7-735.7
713 -693
605 -600
678 -658
625 -615
580 -575
657 -652
674 -654
724 -714
701 -691
663 -643
557 -555

Screened
Hvdrologic
'Um't(s)
A, B
B
B
B
A, B
B
B
B
A
B
B
B
A, B
B
B
B
B
A, B
B
B
B
A, B
B
B
A, B
B
B
A, B
B
B
B
B
B
B
B
A, B
B
B
B

oxidized unoxidized zone surface
SO feet in depth
completed in sand
completed in silty
110 feet in depth
bit refusal

layer
layer







bit refusal replacement

-------
                                                                        53
Well  Locations

      Appendix  D,  Figures  D-l through D-6,  indicates the locations of each
well  system,  the  interceptor trenches and  the  other  well  networks.   The
proposed  RCRA  permit  system encompasses nearly all wells installed at the
site.

Interceptor Trenches

      Few  as-built construction details are  available for the trenches.  All
trenches  were to be excavated at least 2 feet below the interface zone between
Hydrologic Units A and B.   A sand-filled lens was constructed that extended
2  feet  into  Hydrologic  Unit  B  and  the  remainder in  Hydrologic  Unit A.   For
trench 1, this sand-filled portion was 8 feet in total depth.  For trenches
2  and  3,  it  ranged from 18 to 20 feet in total depth.  All   lenses were at
least 2 feet in width.

     On the  north  side  of trench 1 is a sand-filled lens that acts as the
collection zone.   A clay cutoff wall was constructed to prevent flow beyond
the lens.   The clay was extended above and  beyond the lens to the north and
the remainder  of  the  excavation backfilled with previously  excavated soil
[Appendix B,  Figure B-10].

     Trenches 2 and  3 had a clay  cutoff on top of  the sand  lens  with the
remainder of  the  excavation  backfilled  with  previously  excavated soil
[Appendix B,  Figure B-10].

     Observation sumps  were  placed a short  distance  from  the monitoring
sump.   It is  not clear if the trenches are  sloped to either  sump.   Therefore,
it may not be possible to fully evacuate the trenches when they are pumped.

     All monitoring sumps were sand-filled, fabric-lined and 20 feet square.
They  extended  at  least  4  feet below the interceptor trench.   A 6-inch PVC
pipe  extended  into the  sump  and  is  used   to  drain accumulated water.-
Trenches 1 and 2 share a common sump [Appendix B,  Figure B-ll].

-------
                                                                        54
     The  observation  sump  was  of a  similar construction  but only 5  feet  to
a side [Appendix B, Figure B-ll].

SAMPLE COLLECTION AND HANDLING PROCEDURES

     The Task Force did not observe sample collection and handling by B.H.S.
during the  inspection because  B.H.S.  had  yet  to  initiate  sampling  of  the
new monitoring  well  system.   B.H.S. did assist in  purging some wells in
order for the Task Force to take samples.  The B.H.S. and Task Force purging
procedures are discussed together with the Task Force sampling procedure in
the section entitled  "Task Force Sample Collection and Handling  Procedures".

WAIVER OF GROUND-WATER MONITORING REQUIREMENTS DEMONSTRATION

     A request  for waiver of  the  interim  status  ground-water monitoring
requirements was submitted  to  EPA  Region  VII  by  B.H.S.  in January 1982.
During review of the  request,  it was established that downgradient wells
P-5, P-8  and P-10  were  not properly constructed (precipitation  and  surface
runoff may  penetrate  the  wells and fine sediment particles entering the
screens may have plugged  the wells) and the wells may not  be screened in
the uppermost water-bearing  zone.   It was  also established  that  the upgra-
dient wells and well  MW were  not  in the same  water-bearing zone as the  P
wells.    During  the waiver request review period,   the  GM wells were
constructed.

     The  waiver was denied on  September 3, 1983.   EPA Region VII required
the installation of a new upgradient well   (GM-1R) and a new  downgradient
well (GM-5).   These   wells  became  part of  the GM well  system and were
installed in 1984.

     A Letter of Warning,  dated March 6, 1984,  was issued by EPA Region VII
requiring the two  above wells  be installed.   In a March 22,  1984 letter,
B.H.S.  acknowledged they would  comply and the wells  were  installed.

-------
                                                                        55
GROUND-WATER ASSESSMENT PROGRAM AND OUTLINE

     Sampling and  monitoring  under RCRA began with  the  System  1 wells  in
November 1981.   The  program continued through September  1982 to build  an
initial background data  base.   The installation of the System 2 wells,  in
essence, made the  data collected from System  1  useless  in attempting to
determine compliance with ground-water monitoring requirements.

     Sampling and  monitoring  under RCRA began at  the  System 2  wells in
December 1983.   Required parameters not analyzed  for  were radium,  gross
alpha, gross beta and coliform bacteria.   Magnesium was reported instead of
manganese and all  metals were reported as dissolved.  Monthly sampling  to
establish an  initial  background  data base at  these  wells was  conducted.
When well GM-1  was considered by the MDNR and EPA Region VII to not truly
represent background,  well  GM-1R was  installed and  initial background data
base  sampling  began  in  September  1984 and continued  through May  1985.

     In September  1985,  the first  statistical analysis  was  done  for all
downgradient  GM  wells  (GM-1 through  GM-5)  compared to well  GM-1R.   The
analysis showed the following statistical  differences:   well  GM-1,  decrease
in pH; well GM-2,  increase  in TOC;  well GM-3,  increase in specific  conduc-
tivity; well  GM-4, increase in TOC  and TOX; and well GM-5, decrease  in  pH.

     A Ground-water  Assessment Plan  (GWAP) was submitted  to  EPA Region  VII
and MDNR on February 11,  1986.   Its  intent was to  sample  and monitor wells
B-l through B-ll, GMW-1 and GMW-4 to ascertain ground-water quality  effects.
The GWAP was  reviewed  and subsequently amended and  approved on April 16,
1986.

     The plan calls  for  three study  phases.   Phase  I is  to consist  of sam-
pling and analysis of  certain B and  the two  GMW wells for the  parameters
listed in Table  11.   If  contamination is  found,  Phase  II will  begin.   The
following parameters will  be  analyzed to  identify  a contamination  plume:
arsenic,  barium, cadmium,  chromium,  lead, mercury  and  silver.   Analysis of
vapors in the soil  above the ground water will be used as an indicator  of
contamination in the  ground water.

-------
                                                                            56
                                  Table 11

               PHASE I GROUND-WATER ASSESSMENT PLAN PARAMETERS
Indicator Parameter

pH

Ground-Water Quality Parameters

Total phenols

E.P.  Metals

Arsenic
Barium
Cadmium
Chromi urn
Lead
Mercury
Selenium
Si 1ver

Volatile Organic Priority Pollutants
Acrolein
Acrylonitrile
Benzene
Bromoform
Carbon tetrachloride
Chlorobenzene
Dibromochloromethane
Chloroethane
2-Chloroethylvinyl ether

Acid Extractables

Naphthalene
Isophorone

Mi seel 1aneous

Maleic acid
                           Chloroform
                           Bromodichloromethane
                           1,1-Dichloroethane
                           1,2-Dichloroethane
                           1,2-Dichloropropane
                           cis 1,2-Oichloropropene
                           Ethylbenzene
                           Methyl  bromide
                           Methyl  chloride
Methylene chloride
1,1,2,2-Tetrachloroethane
Tetrachloroethene
Toluene
Trans-1,2-diChloroethane
1,1,1-Trichloroethane
1,1,2-Trichloroethane
Trichloroethene
Vinyl chloride

-------
                                                                        57
     The  plan,  as written,  reveals that  only the previously mentioned
parameters will  be  analyzed in Phase II.  This may not be the true intent
of the  Phase  II  work.   Vapors  above  the soil  are  to  be monitored and  the
previously mentioned parameters have extremely low vapor pressures resulting
in extremely  low vapor concentrations.   Only  the  organic  constituents  of
Table 11  will  give  off vapors  in sufficient quantities so that an attempt
can be made to measure them.

     An approximate extent of the plume will be defined and additional bor-
ings and  piezometers  will  be installed to confirm the shape of the plume.
An analytical  model  will  be used to determine the flow rate and  direction
of the plume movement.

     If no contamination is found during Phase I, Phase III will  be entered.
This portion  of  the  plan is designed to evaluate whether the GM  well  con-
struction method  caused  the  statistical  differences.   If this  is  the case,
new wells will be constructed and 4 months of sampling will act as background.
The fifth month  of  sampling will represent  the  first  semiannual  analysis
and statistical analyses will be initiated.  All other sampling will  follow
a semiannual  schedule.

     Phase I  work of the GWAP was instituted on May 1, 1986.

-------
                                                                        58
         GROUND-WATER MONITORING PROGRAM PROPOSED FOR RCRA PERMIT

     In its  February  1986  Part  B application,  B.H.S.  has  proposed a series
of programs, parameters  and well locations to  be  included  in a  RCRA permit
for Area  2.  The  application  also briefly describes a program for Area 1.
The following  is  a  discussion of these  proposals.   The  RCRA permit will
describe  these  items  in  greater detail.   The sanitary landfill  is omitted
from any of the monitoring programs.

DEFINITION OF WASTE MANAGEMENT AREAS

     B.H.S. has divided the facility into two Waste Management Areas (WMAs)
[Figure 7].  WMA1  includes Area 1 and surface impoundments SI-1, SI-2 and
SI-4.   WMA2 includes Area 2 and the storage and treatment areas.  A Compli-
ance Monitoring Plan for the areas has been proposed by B.H.S.  and a proposed
Detection Monitoring  Plan  and Corrective Action Plan were provided in the
Part B application.   Selected  B series wells will serve as compliance points.

     The  site  hydrogeology  has  been divided into  two water-bearing zones
(Hydrologic Units A  and  B) for monitoring purposes.  The oxidized glacial
till has  been  designated Hydrologic Unit A.  The  unoxidized  till and below
to  the  first  bedrock  unit has  been designated  Hydrologic  Unit B.   All
B-series  wells  designated  as  points of  compliance are  screened in both
units.

POINT OF COMPLIANCE

     B.H.S. has designated  a  network  of B wells along the proposed points
of compliance for each WMA.  Some of these wells are proposed and are identi-
fied by "(P)"  in  the following list.   Appendix  D,  Figure  D-7,  identifies
the location of  the  wells  for each WMA.   Wells  designated fcr  WMA1 are:
B-1A,  B-2,  B-3A,  B-4,  B-5, B-6A,  B-7,  B-8A, B-34(P), B-35(P) and B-36(P).
Wells designated for WMA2 are: B-9, B-10A,  B-11A, B-12A,  B-12B,  B-13,  B-14A,
B-15,  B-16A  or B,  B-17C, B-18,  B-19A, B-20, B-21A,  B-22A, B-23, B-31(P),
B-32(P), B-33(P), B-34(P),  B-35(P)  and B-36(P).

-------
                                                                          59
ASTE MANAGEMENT AREA 1
 PROPOSED HAZARDOUS
 WASTE DISPOSAL AREA
        FIGURE 7. DESIGNATION OF WASTE MANAGEMENT AREAS

-------
                                                                        60
     For  WMA2,  the point of  compliance  is  the southern boundary of  the
proposed  landfill  [Appendix  D,  Figure D-7].  The sufficiency of the point
of compliance  proposed  for WMA2  cannot  be determined  until  a  more thorough
hydrogeologic  site  characterization  is  provided  and a  presentation  is  made
to illustrate  the  effects of design, construction and operating practices
on the ground-water flow patterns.

DETECTION MONITORING PROGRAM

     Both WMAs are to be monitored under the program.   Ground-water quality
background data will be developed and subsequent monitoring results will be
compared  to  it.   Statistical  analysis of monitoring data,  similar to that
done under interim status, will  be conducted.

     As proposed  in the  Part  B,  semiannual  monitoring  and  sampling will be
conducted at all B, GM and GMW wells for the following parameters:

          Arsenic
          Lead
          Chromium, total
          2,4-Dichlorophenoxy acetic acid (2,4,-D)
          Phenol

     WMA1 monitoring  and sampling points will consist  of  all  previously
monitored B  wells  and wells   GM-1 through GM-5,  GM-1R,  GMW-1 and GMW-4.
WMA2 monitoring  and sampling  points  will consist of all previously moni-
tored B we!Is.

     Wells identified in  Table  12 are to be  monitored  monthly  for water
level.   This is being  done to determine the  impact of  Area  2 on  ground-water
flow directions.  To  best  realize this goal, wells should be selected  to
represent discrete  interconnected intervals  and potentiometric maps should
be prepared to depict  lines of equal  change  in head over time.

-------
                                                                        61
     Parameters chosen for analysis should relate to wastes placed in Area 1,
wastes anticipated to be placed in Area 2 or constituents known to occur in
leachate from Area 1.

                                  Table 12
                              WELLS FOR MONTHLY
                          WATER LEVEL MEASUREMENTS
B-1A
B-2
B-3A
B-4
B-5
B-6A
B-7
B-8A
B-9
B-10A
B-ll
B-12A
B-12B
B-13
B-14A
B-15
B-16
B-17A
B-17C
B-18
Truck
Wash
Well
B-18A
B-19A
B-19B
B-20B
B-21A
B-22B
B-23A
B-30 (P)
B-31 (P)
B-32 (P)
B-33 (P)
B-34 (P)
B-35 (P)
B-36 (P)
GM-1
GM-1R
GMW-1
GM-2
GM-3
GM-4



GMW-4
GM-5
K2-OX
K2-80
K2-SA
KS-BR
K3-OX
K3-110
K3-BR
K4-OX
K4-80
K4-120
K4-BR
K4-BRR
K5-OX
K5-80
K5-SA
K5-BR
K6-OX
K6-SI



KC-BR
K7-OX
K7-SI
K7-BR
K9-SA
K9-BR
K10-80
K10-BR
Kll-OX
Kll-SA
Kll-BR
K12-BR
P-18
P-20
P-21
P-22
PA
PB
PC
PD



COMPLIANCE MONITORING PROGRAM

     This program will  be  initiated if the  statistical analysis from the
detection monitoring program shows significantly elevated levels of monitored
parameters.   A plan will be prepared that will characterize the contaminated
ground water  based  on  40 CFR 261,  Appendix  VIII.   Table  13 outlines the
minimum list of parameters  proposed to be monitored.   Others will  be chosen
based on the waste accepted for disposal.

     B.H.S.  will  propose action  levels  for  each  hazardous constituent
detected, based on  background  concentrations.   All wells  that are  part  of

-------
                                                                        62
the detection monitoring program will be monitored at this time.  Quarterly
monitoring will be  performed  and a  statistical  analysis  conducted  on  the
generated data.
                                  Table 13
                PARAMETERS FOR COMPLIANCE MONITORING PROGRAM
Parameter
pH
Specific conductance
Total organic carbon (TOC)
Total organic halide (TOX)
Cyanide, total
Chloride
Phenol
Sulfate
Dissolved arsenic
Dissolved barium
Dissolved chromium
Dissolved cadmium
Dissolved lead
Dissolved mercury
Dissolved silver
Dissolved selenium
2,4-D
2,4,5-TP silvex
Toxaphene
Analytical
Methods
EPA 150.1*
EPA 120.1*
EPA 415.1*
EPA 450.1*
EPA 335.2*
Method 407B**
EPA 625*
Method 426C**
EPA 206.2*
EPA 208.1*
EPA 218.2*
EPA 213.2*
EPA 239.2*
EPA 245.1*
EPA 272.2*
EPA 270.2*
Method 509B**
Method 509B**
Method 509A**
Detection
Limit for
Monitoring
1000 ug/£
10 ug/£
1.0 mg/£
1.0 mg/£
1.0 mg/£
50 (jg/£
1. 0 mg/£
50 ug/£
10 ug/£
50 M9/£
2.0 ug/£
50 ug/£
10 ug/£
100 ug/£
10.0 ug/£
5.0 (jg/£
              Methods for Chemical Analysis  of Water and Wastes,
              EPA 600 4-79-020,  March 1979,  U.S.  Environmental Pro-
              tection Agency,  Washington,  D.C.
              Standard Methods  for the Examination  of  Water and
              Waste Water,  15th Edition,  1980,  American Public
              Health Association,  Washington, D.C.

-------
                                                                        63
CORRECTIVE ACTION PLAN

     This program will  be  initiated if hazardous constituents measured in
the ground water exceed the limits found in Table I of 10 CSR 27.7.011(10).
B.H.S.  has left open the course of action it would take to prevent the con-
tamination and  indicates  that  the  problem will  be  studied  and actions
developed at that time.   The  ground-water monitoring  system will also  be
evaluated to determine the adequacy for contamination delineation.

-------
                                                                        64
           TASK FORCE SAMPLE COLLECTION AND HANDLING PROCEDURES

     Samples  were  collected from  the B.H.S.   facility  for analysis  to
determine if the ground water contains hazardous waste constituents or other
indicators of contamination.  This section describes the sampling procedures
followed during the site inspection.

     Thirteen stations  were sampled  comprising nine monitoring wells, two
interceptor  trench  sumps and  two  leachate collection  sumps  [Table 14,
Figure 8].  The wells were  selected to provide areal coverage, both upgrad-
ient and  downgradient of Area  1.   The interceptor  trenches  receive  shallow
ground-water discharge.   Two leachate samples were also collected to deter-
mine leachate chemical  characteristics and provide  a basis  for determining
constituents which may  leach into and contaminate the ground water.

     B.H.S.  personnel made  all  water-level  measurements in the wells  and
interceptor trench sumps and sometimes assisted in the purging of wells and
sumps.   An  EPA  contactor  did most of  the well purging  and  all but  one  of
the water sample collections.   The one exception was interceptor  trench 3,
where the sump well  casing extends 13 feet above the ground.  B.H.S. person-
nel drew the sample while standing on a raised lift of a Caterpilla10 tractor
while EPA contractor personnel  stood  below and assisted.  B.H.S.  also  drew
all samples  from  the  two leachate collection  sumps while  EPA contractor
personnel stood upwind.   Task Force personnel  observed all  purging and sam-
pling procedures throughout the inspection.

     A complete set of samples  was collected from each sample station to be
analyzed by  EPA contract  laboratories.   A complete sample set is shown in
Table 15, which lists the sample parameters with respective containers and
preservatives in the order in which they  were collected.  Replicate samples
of volatile  organic samples  and split  samples  for  all other parameters for
each sampling station were  offered to B.H.S.   but  were  declined.   Sample
sets from well B-8A and  PTA leachate  sump were provided to NEIC for quality
assurance/quality  control  purposes.

-------
                                                                                       65
Samc'e Static"
                                SAMPLE  CGLLEC'IOS  DATA
                               ing  '.Ties
                                       End
We
GM-1


GM-5

GMW-1



3-7
                 15-9    32, 24 'S6    1129    02/26 '86


                 1215    02  21/S6    1224    02 '21/36

                 i:i7    C2, 25/36    0919    02/26/86
                0907   02 '25,36   0937   02/26/86

                0900   02 20 36   0954   02''20/86
3-15            0916


B-20            1441   C2''20"36    1511    02/20/86


B-23A           1011   02'25,86    1036    02/25/86

Interceptor Treneges

Commc- sump     1236   02/20-36    1247    02''20/86
to interceptor
trencnes 1 i 2

Intercepto^     1114   02/21/86    1128    02''21/86
trencf. 3 Sump

Leac^ate

Oommcr sumo to  1304   02 24/86    1323    02/24/86

t~e''cn 3rea

--encn 2N       1331   02 24-85    13-10    02 24/86
sump
Sample clear; submersible pump,
tripiicate

Sample clear, submersible pump

Sample slightly turbid, ^nooer-
aole Well  wizard supstituted
witn Teflon bai1er

Sample clear, Teflon bailer,
NEIC split

Sample clear, Teflon bai"Ier

Sample sligtify turbid, Teflon
bailer

Sample sligntly turbid, Teflon
bailer

Samp]e sligntly turbid, Teflon
bailer

Sample clear, Teflon bailer
                                                       Sample  clear  witn  slight  sulfur
                                                       oacr;  suDmersib1e  pump
                                                       Sample  clear,  submersible  pump,
                                                       collectea  bv  B  »  S
                                                      Sample bro*n- sh-g-^en
                                                      ibie pump, NEIO  spl't, collected
                                                      by B H.S.

                                                      Sample cha^coa' -cc '• c»-ed, sub-
                                                      me'-siDle pump, co'lected by
                                                      B H.S.
*    February 2i-2~,  1936 i»as a weekena and no sampling  toon place

-------
                                                                                                      66
                                                                 rctptor Trine h • 3 S um[
                                                               INTERCEPTOR
                                                                TRENCH »2
               PROPOSED  HAZARDOUS

               WASTE DISPOSAL AREA
                                                         1      W ^
                                                        ^   ^ ^i   Common  Sump TO ,--""
                                                        ^ ™ "~   A.  lni«rc«pior Tr«n<;h *•
                                      »B-23A
                                                                              $!-Surf«c*  1 • p o u n d in « o i
FIGURE 8.   LOCATION OF TASK  FORCE SAMPLE  STATIONS WITH FACILITY UNITS SHOWN

-------
                                                                        67
                                   Table 15
                          ORDER OF SAMPLE COLLECTION,
                       BOTTLE TYPE AND PRESERVATIVE LIST
         Parameter
   Container
Preservative*
Volatile organic analysis (VOA)
  Purge and trap
  Direct inject
Purgeable organic carbon (POC)
Purgeable organic halogens (POX)
Extractable organics
Pesticide/herbicide
Dioxi n
Total metals
Dissolved metals
Total organic carbon (TOC)
Total organic halogens (TOX)
Phenols
Cyanide
Nitrate/ammonia
Sulfate/chloride
Radionuclides (NEK only)
2 60-mA VOA vials
2 60-m.e VOA vials
2 60-m£ VOA vials
2 60-m£ VOA vials
4 1-qt. amber glass
2 1-qt. amber glass
2 1-qt. amber glass
1 1-qt. plastic
1 1-qt. plastic
1 4-oz. glass
1-qt.  amber glass
1-qt.  amber glass
1-qt.  plastic
1-qt.  plastic
1-qt.  plastic
4 1-qt. amber glass
 HN03 - pH <2
 HN03 - pH <2
 H2S04

 CuS04 + H3P04
 NaOH - pH >12
 H2S04
*    All samples cooled to 4° C.

     All sample containers and preservatives were provided by an EPA contract
laboratory.   All sampling equipment was provided by the EPA sampling contrac-
tor.   Ground-water samples were collected from each well using the following
protocol:

          B.H.S. personnel  or their  contractor  determined the depth to
          ground water.

          B.H.S. calculated  the  height and volume of the water column and
          amount to be purged.

          The EPA  sampling contractor  and/or  B.H.S. purged the amount cal-
          culated (less if the well was purged to dryness).

-------
                                                                        68
          The EPA contractor monitored the open wellhead for chemical vapors
          and radiation (before and after purging).

          The EPA contractor collected a sample aliquot and conducted field
          measurements for  water  temperature,  pH,  specific  conductance and
          turbidity.

          The EPA contractor filled VOA vials and then filled the remaining
          sample containers in the order shown in Table 15.

          The EPA contractor placed the sample container in ice immediately
          after col lection.

     The  reference  point from which  the  depth-to-water  measurements are
made at B.H.S. is at the top of the well casing.   B.H.S.  personnel and their
contractor used a Water Level Indicator (Model 6000 by Slope Indicator Co.)
to make their measurements.  The Water Level Indicator probe was improperly
rinsed with deiom'zed water between use in successive wells.  Consequently,
the wells were exposed to  potential outside  or intercontamination.   B.H.S.
was able  to  make  repeatable water level measurements  to within  .01  foot.

     The  volume of  the  water column  in a well can  be  calculated  by  first
subtracting the depth to water measurement from the total depth of the well
(from construction  records)  to obtain the height of the  water column.  The
volume can then be calculated using the following formula:

          V = nr2h

where:     V = water column volume
          TT = 3.1416
          r = inside radius of well casing
          h = height of water column

-------
                                                                        69
     For  the  purpose  of the Task  Force  sampling,  the amount purged from
each well was equivalent to three water column volumes except as noted below.
During the  inspection,  B.H.S.  made  all  calculations  which  were  verified  as
correct by Task Force personnel.

     Dedicated equipment  is  set up at B.H.S. for the purging and sampling
of wells.   Of the  11  wells  chosen  for  this  investigation,  six are equipped
with Teflon  bailers  (B-7, B-8A,  B-11A,  B-15,  B-20, B-23A),  one  with  a Well
Wizard®  pump  (GMW-1) and four  with  submersible  pumps (GM-1, GM-5,  both
interceptor trench  sumps).   The Well  Wizard  at  GMW-1 was  not functioning
and, therefore, was  replaced by  a  Teflon  bailer  on a stainless  steel cable
provided by the EPA contractor.

     Before and after purging,  the EPA contractor monitored each open well-
head for chemical  vapors and radiation.  Chemical vapors were measured with
one  of  three  instruments:   (1)  Century  Systems  Portable  Organic  Vapor
Analyzer Model OVA-128;  (2)  HNU Model  Pl-101 Photoionization Analyzer or
(3)  Photovac,  Inc.  TIP  (Total  lonizable Present).    Radiation measurements
were made with a Ludlum Measurements,  Inc. Model  3.   Measurements are shown
in Table  16.   At  stations where measurements exceeded background levels,
sampling personnel  wore Level C protection.   Otherwise,  Task Force  personnel
wore Level D protection during sampling .

     From the wells with bailers, water was  manually evacuated and  discharged
into 55-gallon  drums  at each wellhead.   Responsibility  for disposal  was
left to  B.H.S.  The  submersible pumps  in wells  and  interceptor trenches
require electrical  power  sources, which were  provided by a  B.H.S. electric
generator.  Electrical  connections  were  made by B.H.S.  personnel.   Again,
responsibility for  disposal  of the purged water was left  to B.H.S.   In
accordance with B.H.S.  standard  operating procedures, the  water was dis-
charged  directly onto the  ground.   Table 17 lists  the  purge times  and
volumes purged from each station.
     Well Wizard is a registered trademark; appears hereafter without the §.

-------
                                                                        70
                                 Table 16
                  CHEMICAL VAPOR AND RADIATION DETECTIONS
                        AT SAMPLE STATION WELLHEADS
Sample Station
GM-1
GM-5
GMW-1
B-7
B-8A
B-11A
B-15
B-20
B-23A
Common sump to
interceptor
trenches 1 & 2
Interceptor
trench 3
Common sump to
progressive
trench area
Trench 2N sump
Chemical Vapor
Level (ppm)/
Meter Used
BackgroundVTIP
Background/TIP
Background/TIP
Background/OVA
5/TIP
80/TIP
Background/TIP
Background/TIP
Background/HNU
Background/TIP
Background/TIP

20/HNU
20/HNU
Radiation
Level
(mr/hr)
Background**
Background
Background
Background
Background
Background
Background
Background
Background
Background
Background

Background
Background
              *   Chemical vapor background  level  is 3 ppm.
             **   Radiation background  level is 0.1 mr,hr.

     In some cases,  the  intended (calculated) purge volume  could  not be
evacuated in a  single attempt due to dewatering of  the well.   Purging con-
tinued after a  time  allowing  the well  to recharge.   If the well failed to
produce the calculated purge volume after three or four purge attempts,  the
total  volume purged was  noted  and sampling commenced after recharge.   Stand-
ard B.H.S.  purging procedure  for the interceptor trenches is to allow the

-------
                                                                                             71
                                          Table  17

                                        PURGING  DATA
Sample Station
                          Purging Times*
                  End
Approximate
  Volume
  Purged
 (gal Ions)
          Remarks
GM-5

GMW-I




B-7

B-8A


B-11A


B-15


B-20


B-23A
Interceptor
trench 3
                  1628  02/20/86   1019  02/24/86
1350  02/20/86  1113  02/21/86
                                     32
1204  02/21/86  1212  02/21/86       83

1450  02/21/86  1116  02/24/86        9




1355  02/19/86  1451  02/19/86       19

1611  02/21/86  1000  02/24/86       13*5


1320 02/19/86   1626  02/19/86       10


1535  02/20/86  1104  02/24/86       16*5


1500  02/19/86  1054  02/20/86       15*5


1503  02/21/86  0944  02/24/86        8*5
Common sump to    1205  02/20/86  1235  02/20/86      480
1nterceptor
trencnes 1 & 2
   218
               Wei1 dewatered, purgec Dy
               B.H S.

               Purged by B.H.S.

               Well dewatered; purged by
               B.H.S. ,  EPA Task Force
               personnel and EPA
               contractor

               Purged by EPA contractor

               We1! dewatered, purged by
               EPA contractor

               Well dewatered; purged by
               E?A contractor

               Well dewatered; purged by
               EPA contractor

               Well dewatered; purged by
               EPA contractor

               Well dewatered; purged by
               EPA contractor

               °urged by B.H.S.
Purged by B.H.S.
*    February 22-23,  1966 was a weekend and no purging or sampling took place.

-------
                                                                        72
pump to  run for 30 minutes before sampling.  The Task Force followed this
same procedure.   The  leachate  systems  were not purged before  sampling.

     After  purging,  a  sample  aliquot was collected for field measurements
(water temperature, specific conductance, pH and turbidity) which were made
at  the  EPA  contractor's staging area (a garage unit near SI-2).  Volatile
organic  analysis  (VOA) vials were  the  first sample  containers  filled,  fol-
lowed by  the  order listed  in Table 15.   The VOA vials were  filled  directly
from the  bailer or an  intermediary glass beaker if a submersible pump was
used.  All  other  sample containers were sequentially filled directly from
the bailer  or pump hose.

     B.H.S.  personnel  conducted the sampling at  the  leachate collection
systems (trench 2N ana the progressive trench area) and interceptor trench 3,
with the assistance of EPA contractor personnel.  Difficulty with access to
interceptor trench  3 caused a  safety problem in sampling  from  the  13-foot-
high outer  well casing while standing  atop  the  raised platform  of  a Cater-
pillar tractor.

     At some stations,  as in the case of purging, the ground-water recharge
was slow and the well dewatered while sampling.   Rather than collecting the
entire sample set  in a single  attempt,  all  the  sample parameters were col-
lected in as many  as four attempts over  a period of 3 days, as  in  the case
with GM-1.  While the collection of a sample set may have been discontinuous,
the collection  of  each parameter was completed in one attempt.   Moreover,
for the assurance of having enough ground water to obtain a complete sample
set, some parameter containers were only partially filled.   (VOA  vials,
however,  were always completely filled,  as required for proper analysis.)
The sample containers of those  parameters requiring more than one container
(extractable organics,  pesticides/herbicides, dioxin and  radionuclides)  or
of  each  parameter  of a split sample contained equal volumes.  For  example,
instead of  filling  three of the  four bottles for extractable organics com-
pletely while  filling the fourth only partially, all four bottles were filled
with an equal,  though reduced  volume.

-------
                                                                        73
     After  sampling  was  completed at each well,  EPA  contractor  personnel
took the samples to  the staging area where a turbidity measurement was taken
and the  aliquot  for  dissolved metals analysis was filtered.  In addition,
samples  for  analysis for  metals,  total organic  carbon,  phenols, cyanide,
nitrate  and ammonia  were preserved  as  indicated in Table  15.   Leachate
samples were not preserved.

     At  the  end  of each day  of  sampling,  the  EPA sampling  contractor pack-
aged and  shipped the samples  to the  EPA contract laboratories and the NEIC
laboratory,  as appropriate.   Samples were shipped according to applicable
Department  of  Transportation  regulations  (40 CFR Parts 171-177).  Aqueous
samples  from monitoring wells and  interceptor trench  sumps  were  considered
"environmental"  and  those  from  leachate  collection system sumps were con-
sidered  "hazardous"  for shipping purposes.   The EPA  sampling contractor
also prepared  a  set  of field blanks  for  each analytical parameter (e.g.,
VOAs,  organics, metals, etc.) each day.   Field blanks were used to determine
whether  contamination  was introduced from  the sample  collection  activities
or sampling environment.

     One set each  of trip blanks and equipment blanks was prepared by the
EPA sampling contractor during  the  investigation and  shipped  to the  EPA
contract laboratory.   Trip blanks were used to determine whether contamina-
tion was introduced  from the sample containers during transport to and stor-
age at  the  B.H.S.  facility,  and equipment  blanks were  used  to determine if
contamination was  introduced  from the bailer used at  GMW-1.   All  blanks
were prepared  at the staging area using  distilled,  deionized  water  of  a
known  high purity.

     Additional  QA/QC  samples submitted  by the EPA sampling contractor  to
the EPA  contract laboratories were the performance evaluation (PE) samples
and triplicate samples.  The  PE samples were  initially prepared  by the EPA
Environmental Monitoring and Support Laboratory in Cincinnati and were used
to evaluate the accuracy of analyses performed by the contract laboratories.
Triplicate  samples of  each analytical parameter  taken  at GM-1 were used to
evaluate the precision of  the analytical  methods employed by the contract
laboratories.

-------
                                                                        74
         MONITORING DATA ANALYSIS FOR INDICATIONS OF WASTE RELEASE

     Tabulation, evaluation and interpretation of analytical data for samples
collected during the inspection and analyzed by EPA contractor laboratories
are  discussed  in detail  in  Appendix  A.   Inorganic chemical constituent
analyses of these samples indicate the presence of common, naturally occur-
ring cations and  anions.   In addition, selenium was  found  in wells  B-11A
and B-15 at 164 ug/L and 280 ug/L, respectively.   Because of the newness of
some of  the  ground-water monitoring wells in  the  system being  evaluated
(B-11A and B-15), it is not appropriate to attempt to undertake a statistical
comparison of upgradient and downgradient ground-water quality.   This compar-
ison should  be  made as  soon  as  1  year  of  quarterly  sampling  and analytical
results are available from the new system of wells.   Evaluation of the organic
chemical constituent analyses  indicate the  presence of 1,2-dichloroethane
and acetone  in  well GM-1.  Purgeable organic  halide (POX) results indicate
that methylene  chloride  may  also be present  in this  well.   The source of
these organic constituents  in  samples  should  be determined  and the  first
year of  quarterly sampling and  analysis of the new  ground-water monitoring
system wells should be  completed  to confirm whether or not  ground water at
the  facility  contains  hazardous waste constituents resulting  from  waste
disposal activities.

     Trenches IN, 2N,  6N,  UN,  12N and the  PTA  have  leachate collection
systems.  All other disposal  trenches  and drilled cells at Area  1 are unlined
and have the potential  for leakage.

     Due to  the  incomplete  hydrogeologic  characterization of the site and
the questions regarding  ground-water  flow direction,  the wells  may  not be
properly placed or constructed to intercept  leakage.

-------
                                REFERENCES

1.    D.E. Klockow  and  Associates,  December 31, 1981,  "Engineering  Design
     Manual,  Harzardous Waste Management Facility Permit Application Amend-
     ments and Revisions",  prepared for B.H.S., Inc. (included as part of
     the August 1983 Part B Application)

2.    D.E. Klockow and Associates, August 3, 1983,  "Part B RCRA Application",
     prepared for B.H.S.,  Inc.

3.    D.E. Klockow  and Associates, April  1984,  "Geotechnical Investigation,
     Soil Geology and Hydrogeology", prepared for B.H.S., Inc.

4.    Reitz and Jens,  Inc.,  April  1980, Bob's Home Service, Inc., Special
     Waste Disposal Facility", Wright City, Missouri, prepared for Bob's Home
     Service, Inc.

5.    Reitz and Jens, Inc.,  July  1980,  "Bob's Home Service, Inc., Hazardous
     Waste Disposal Facility", prepared for Bob's  Home Service, Inc.

6.    Woodward-Clyde Consultants,  March 15, 1985, "Evaluation of 1984 Ground-
     Water Monitoring Data", prepared for B.H.S.,  Inc.

7.    Woodward-Clyde Consultants,  February 14,   1986,  "Part B  RCRA Permit
     Application",,  prepared for B.H.S., Inc.

-------
                           APPENDICES

A    ANALTYICAL TECHNIQUES AND RESULTS FOR TASK FORCE SAMPLES
B    CONSTRUCTION DRAWINGS
C    POTENTIOMETRIC SURFACE MAPS
D    GROUND-WATER MONITORING SYSTEMS

-------
                       APPENDIX A
ANALTYICAL TECHNIQUES AND RESULTS FOR TASK FORCE SAMPLES

-------
                                                                         A-l
                                Appendix A
         ANALTYICAL TECHNIQUES AND RESULTS FOR TASK FORCE SAMPLES
                                B.H.S. INC.
                           Wright City, Missouri

     The following discusses analytical techniques, methods and results for
water and  leachate  samples  collected  by  the  Task  Force  at  the  B.H.S.,  Inc.
facility,  Wright  City,  Missouri.   Water sample analyses  and  results are
discussed  in  the  first  section;  the second section addresses the leachate
analyses and results.

     Field measurements  on  water  samples,  including specific conductance,
pH and  turbidity,  were  made by the EPA sampling contractor at the time of
sampling.  No field measurements were made for the leachate samples.   Labo-
ratory  analysis results  were obtained  from two  EPA contractor  laboratories
(CL) participating in the Contract Laboratory Program (CLP).  One CL analyzed
the samples  for organic  compounds while the other analyzed for metals and
other parameters.

     Standard quality  control  measures  were  taken  including:   (1)  the
analysis of  field  and  laboratory  blanks to allow  distinction  of  possible
contamination due  to sample handling,  (2) the analysis of laboratory spiked
samples and performance evaluation samples and comparison of the CL results
with NEIC  split sample  results to estimate accuracy, and (3) the analysis
of laboratory duplicates  and field triplicates  to  estimate  precision.  The
performance evaluation (PE) samples were samples of known analyte concentra-
tions prepared by  the EPA Environmental Monitoring Systems Laboratory, Cin-
cinnnati, Ohio.   Split samples  from well B-7 and leachate from the Progres-
sive Trench Area (PTA) were also analyzed by NEIC.

     Table A-l provides  a summary, by parameter, of the analytical techniques
used and the  reference  methods for the  sample  analyses.   The  CLP  results
are reported  in the data  tables and the  split sample  results are  discussed
where applicable in establishing the reliability of the CLP results.

-------
A-2
WATER SAMPLE ANALYSIS RESULTS

Specific Organic Analysis Results

     Acetone and  1,2-dichloroethane  were quantified in samples  from  well
GM-1.  This  well  was  sampled  as  the  field  triplicate and  all  three  samples
were reported  to  contain between 7.6 pg/L  and  8  pg/L  1,2-dichloroethane.
The three samples were found to contain acetone at concentrations of 46 pg/L,
46 pg/L  and  39 pg/L after  laboratory blank contamination  correction.  An
acetone  laboratory blank level of 10 pg/L has been subtracted from the above
acetone  concentrations.   Purgeable  organic halide (POX)  results  indicate
the presence of about 22 pg/L halogen which is substantially more than that
contributed  by  the  1,2-dichloroethane.   Methylene  chloride was detected  in
the samples; however, three field blanks were also found to contain methyl -
ene chloride.  The methylene chloride concentration cannot be reliably quan-
tified because  the  field blank concentrations were 1.1 pg/L, 1.2 pg/L and
5 pg/L while the sample concentrations were about 10 pg/L.  The POX results
indicate, however,  that  methylene  chloride may be  present  in the ground
water at well GM-1 and warrants further investigation.

     None of the  organic compounds determined  were  detected above blank
levels  in  the  other monitoring well  samples,  interceptor trench 1 and 2
sump and interceptor trench 3 sump;  however,  acid extractable compounds
should be considered  to  have  not been  determined  for  all samples except
those for wells  GM-1  and GMW-1.   The acid  surrogate  compound recoveries
were below the  lower CLP limit even after re-extraction.  Table A-2 contains
the limits of quantisation for the analyses for the volatile, semi volatile,
pesticide, PCB, herbicide and dioxin organic compounds.

     Analysis  of  the PE  sample  for  pesticides, herbicides,   dioxins  and
dibenzofurans was apparently  performed  very poorly.  An investigation has
established  that  shipping  and handling  of  the  PE  samples for only these
specific organic constituents was the major contributing factor.   The appro-
priate PE samples were  net analyzed for the particular class of compounds
for which  the  samples were intended.   Thus,  poor performance on the  PE
samples  is not  reflective of the data quality of the other sample analyses.

-------
                                                                         A-3
     NEIC did  not  receive  the dioxin and dibenzofuran data.  According to
the PRC  QA/QC  data  review,  no  dioxin  target  compounds were  found  in  any of
the samples.  Dioxin spike recoveries ranged from 95% to 170%.  The Lockheed
QA/QC data review stated that there was contamination at a level of approx-
imately  10  ng/L  within  10  scans of 2,3,7,8-TCDF in the samples from wells
GM-1 and GM-5.

     Control measures for the  other analyses  indicate that  sample  analysis
results  are  reliable  with  the exception of the acid extractable compounds
results  discussed above.  Further, NEIC split sample results for the sample
from well B-7  agree with the  CL  results  in that  neither detected  any vola-
tile,   semivolatile,  pesticide or  PCB compounds  above blank  contaminant
levels.

Metals Analysis Results

     The dissolved  and  total  metals  results for the water samples  are
reported in Tables A-3 and A-4.

     Caution must  be  exercised in associating any  significance to trace
element  concentrations  determined  by  the  Inductively Coupled  Argon Plasma-
Optical  Emission  Spectroscopy  (ICAP-OES) analysis.   The CL  did not  make
background corrections for the ICAP-OES analyses.  This  may result in posi-
tive biases  for trace elements when large concentrations of aluminum, cal-
cium,  iron or magnesium  are  present in the samples.   Further,  the CL ICAP-OES
analysis for many of the trace elements may be biased low due to the negative
drift  allowed for the calibration blanks.  The negative  bias was as much as
307 ug/L for aluminum,  164  ug/L for  antimony, 4 ug/L for cadmium, 16 u/L
for chromium,  15  ug/L for  cobalt, 34 ug/L for copper,  18 ug/L for nickel,
22 ug/L  for  silver,  66  ug/L for tin,  13 ug/L for vanadium and 12 ug/L  for
zinc.   The  negative blank values arise from letting the intercepts of  the
calibration  curves  drift.   More  frequent calibration was  needed.   Any
detected concentration for these elements could be biased low by the values
1isted above.

-------
A-4
     The CL  reported  925 (jg/L total lead in the sample from well GMW-1 as
determined  by  ICAP-OES.   Examination of the  raw  data found that the  CL
obtained this  value  from the analysis of a 1 to 5 dilution of the sample.
The diluted  sample  value was 185 ug/L.  The  calibration  blank values  for
lead ranged from -96 ug/L to 25 ug/L and calculation of the detection limit
from these  blank  values  gives a detection  limit  of  200 ug/L.    Thus the
diluted sample  value  is  unreliable, as  it  is  below  the detection limit.
The CL  did  analyze  the undiluted sample and obtained a value of 603 ug/L.
The lead analytical  line is severly interfered on by an adjacent aluminum
spectral line;  however,  the CL made  no  interference correction for the
apparent lead  due to  the aluminum interference.  Thus,  the  lead  concentra-
tion that should have been reported would be 393 ug/L.  The sample was  found
to contain  131,000 ug/L  aluminum  which according to the CL would cause an
apparent lead  concentration  of 210  ug/L.  Interference  corrections of  such
magnitude,   relative to the  sample  concentration,  are not  highly accurate
and the 393  ug/L  value should not  be  considered  accurate.   The CL did a
screening analysis of this sample using furnace Atomic Absorption Spectros-
copy (AAS)  but did not quantitate the concentration appropriately.   The AAS
analysis for lead is not  interfered on by aluminum and indicated the concen-
tration to  be greater than 200 ug/L.

     The dissolved elemental concentrations  determined by ICAP-OES for  many
of the  samples  are  biased  high.   Mismatching of the calibration standards
acid matrix  to  the dissolved preserved sample acid matrix was the cause of
the bias.    In  comparison of the CL results for the  well  B-7 samples,  the
dissolved concentrations  for manganese,  potassium and sodium are about 50%
higher than  the total  concentrations while  calcium and  magnesium dissolved
concentrations are about  15% higher than the total  concentrations.   In  com-
parison to  NEIC  split sample results for well B-7,  the CL  dissolved con-
centrations  for  calcium, magnesium, manganese, potassium  and  sodium are
about  30% higher  than NEIC  split sample results.  Further,  the  CL total
concentrations are from  10% to  20% lower than NEIC  total concentrations.

     For barium and zinc the dissolved concentrations  are  at times  about
twice  the total concentrations.  These dissolved barium concentrations are
in part higher  than the  total concentrations  because  of mismatching  of the

-------
                                                                         A-5
acid matrix.   For  barium,  the digestion used  for  the total  analysis may
have caused barium sulfate to precipitate.   Zinc contamination due to field
sample handling  of  the  dissolved  samples has  been  identified  for  past Task
Force projects  and  is  the suspected cause of much of the bias evident for
the dissolved zinc results.

     Dissolved and total silver spike recoveries were biased low.   The sample
analysis results for silver are, however, reported because the spike levels
may have exceeded  the  solubility allowed by the chloride concentration of
the spiked samples.   The detection limit for silver has been increased based
on the average spike recovery.  Copper spike recoveries were also quite low
indicating that values are unreliable and may be biased low.   Aluminum dup-
licate analyses showed wiae variability which probably indicates the presence
of suspended solids.

     The detection limits for the ICAP-OES analyses were recalculated based
on the variability  observed  for the calibration and  field blanks between
several  analytical  runs.   The  recalculated  detection  limits increased over
those reported  by the  CL.   As part of the detection limit recalculations,
the average negative blank value was added to the detection limit calculated
from the blank variability.  The sample results are reported using the recal-
culated detection limits.

     The CL reported  results  for arsenic,  lead, selenium and  thallium did
not account for furnace Atomic Absorption Spectroscopy (AAS) matrix effects.
These effects were  corrected  for by use of the known addition recoveries.
Further,  detection limits were recalculated based on the variability in  the
calibration curves, on  the variability in the  signal  response and on the
known addition recoveries.

     The CL reported  total  lead concentrations of 69  ug/L, 109  ug/L and
110 ug/L for the  field  triplicate samples  for  well GM-1.  Examination of
the raw data indicates that the lead analyses for these samples are in error.
The CL analyzed  the  samples  at various dilutions  with  concentrations  of
69 ug/L,  83 ug/L  and  110 ug/L being obtained for one of the samples.   THS

-------
A-6
discordance of the dilution values suggests the presence of an interference
in the analysis and that the results are unreliable.

     Fairly high selenium concentrations were reported by the CL for two of
the wells.  The  samples  from wells B-11A  and  B-15  were  reported  to  contain
164 fjg/L and 230 ug/L total selenium, respectively.  The dissolved selenium
concentrations for  these well  samples were  also  high.   Because the  CL  used
deuterium arc background correction for the furnace AAS analysis, such con-
centrations are  often  considered suspect because  of  the  inability  of  the
correction  system  to  compensate for  high nonatomic  background due  to  the
presence of high  salt  concentrations.   However, the  salt  compositions of
these two samples are not substantially different  than those of some of the
other samples where  selenium  was not detected  or  detected at much lower
concentrations.   For example,  the sample from well  B-20 was found to contain
greater concentrations  of  sulfate  and generally greater concentrations of
the major cations, yet selenium was not detected in this sample.   This sug-
gests that  the  background  correcting capability of the instrument may not
have been exceeded.  Although NEIC did not receive samples from wells  B-11A
and B-15, NEIC did  find  15  (jg/L total selenium  in  the sample  from well  B-7
while the CL  reported  17 jjg/L  total  selenium.   NEIC  determined selenium by
hydride generation coupled to ICAP-OES.   This close agreement between  labor-
atories using different analytical  techniques suggests the CL selenium con-
centrations are reliable.   It is possible that the well  B-11A and B-15 samples
contain unique components that cause  interference  and confirmational analyses
are warranted before placing  much  significance on the CL selenium results
for these two  well samples.

     High iron concentrations  cause  a negative  bias  in  deuterium arc back-
ground corrected furnace AAS analysis for selenium.  Thus, when significant
iron was found in  a sample, the  selenium  results may  be unreliable.  Simi-
larly, high aluminum concentrations  cause a positive  bias  in  deuteriuir  arc
backgrounded furnace AAS analysis  for arsenic.   Thus the  arsenic results
for samples containing  high aluminum  may be unreliable.

-------
                                                                         A-7
     The mercury analysis detection limits ranged from 0.4 ug/L to 1.8 ug/L
depending on the volume of the sample analyzed.  The detection limit calcu-
lated  from  the  variability  in the calibration  curve  and  blank values was
0.036 ug which  for  100 ml of digested  sample  would give a detection of
0.36 ug/L instead of the 0.2 ug/L reported by the CL.   There are two indica-
tions that the laboratory had contamination problems.   The initial analysis
of one  of  the  dissolved mercury  field  blanks  found a concentration of 2
ug/L while a subsequent analysis of the same blank found less than 0.2 ug/L.
For dissolved mercury, the CL reported values of less than 0.2 ug/L for two
of three field  triplicate samples  from  well  GM-1 and  reported 0.7  ug/L  for
the third sample.   The total mercury values for the field triplicate samples
were reported as less than 0.2 ug/L.

General Analysis Results

     The field  measurements for  conductance,  pH and  turbidity  and the
results of  other  analytical  testing  for the water samples are reported in
Table A-5.

     All control measures  indicate  that the ammonia,  cyanide, nitrate and
sulfate results should be reliable.

     The PE sample result and comparison with the NEIC split sample for well
B-7 indicate that the CL chloride values are biased low.   The PE sample had
a true value of 22.1 mg/L with an acceptance range of 19.6 mg/L to 25 mg/L.
The CL  reported a  value of 15 mg/L  for the PE sample.   NEIC obtained  a
chloride value of 14 mg/L for well B-7 while the CL reported 10 mg/L.   Other
control measure results were acceptable.

     Examination of  the  raw data reveals that the CL analyzed four spiked
samples for  phenol;  however, only  two  spike  recoveries  were reported.

     Aliquots of  the samples from  wells B-7  and B-20,  the Interceptor
Trenches 1  and 2 Sump  ana  a field blank were  spiked.  Recoveries  of 100%
were reported for both well  B-7  and the field blank spiked samples.  Calcu-
lation of the recovery for tne Trench spiked sample  gives a recovery of 52%

-------
A-8
and  the  well  B-20 spike recovery was  10%.   Further,  the CL analyzed the
well  B-7  spiked  sample twice and when  the  recoveries  are  calculated from
the  raw  data,  recoveries  of 50% and  74% are obtained.   It  is  not  known  how
the  CL  calculated a  100%  recovery  for  the well  B-7  spiked  sample.   Another
indication  that  the  phenol  results are  dubious  is  that the  CL  analyzed  the
sample  from well  B-11A in  duplicate  and obtained  concentrations of  10 ug/L
and  109 (jg/L.  This set of  duplicate data was not, however, reported on the
CLP  duplicate  analysis reporting sheet.  Further, the CL reported a value
for  the  PE  sample that was  unacceptable with a 39% positive  bias.   These
data  indicate  the phenol  results may be unreliable.   The  detection  limit
was  recalculated  based on  the  variability  in the  blank  over  the  analysis
run  and  in  the calibration curve and a value of 33 ug/L instead of  the CL
reported limit of 10 ug/L was obtained.

     Control measures  generally indicate the nonpurgeable  organic  carbon
(NPOC) and  the purgeable  organic carbon (POC)  results should be reliable;
however, the  laboratory  blanks  for these parameters were  often  high and
varied widely.   NPOC blank  values  ranged from 0.13 mg/L  to  2.12 mg/L.   The
NPOC detection limit calculated from the variability in the blank values is
2.2  mg/L.   Many  of the sample NPOC values are close to the  detection limit
and, thus,  should not  be considered highly  accurate.   The POC blanks ranged
from  about  1.7 mg/L  to 4.3 mg/L.  These blank  values  are  quite high and
would affect  the  accuracy  of the calibration standards prepared with this
water.  That  is,  a  signal   response calibrated  as being due to 10 mg/L POC
would actually be due  to  the presence of 14 mg/L POC.   Such a calibration
would cause a  sample concentration to be under  estimated.   Another possible
error is that sample concentrations obtained from dilutions using this water
would result in over estimating the sample   concentrations.   Because of these
possible sources of error,  the  POC results  may  be unreliable and,  thus,  are
not  reported.

     All control  measures  indicate that  the purgeable  organic  halide (POX)
results are reliable.   A detection limit of 8 ug/L instead  of the CL reported
limit of 5  ug/L  was  calculated from the variability in  the blank values.
POX was detected  in all three field triplicate  samples  from well  GM-1.   The

-------
                                                                         A-9
reported  POX  values were  16 ug/L, 23  ug/L  and 26 (jg/L.  As  discussed
previously, 1,2-dichloroethane and possibly methylene chloride were detected
in the samples from GM-1.

     Although most  control  measures  indicate  that  the total  organic halide
(TOX)  results should  be reliable, the  TOX values  may be  biased  low.  The
lack of  correlation  between the  POX values and TOX values for the samples
from GM-1  suggests  the  TOX values are  biased low.   Further,  as  discussed
below  in  the  leachate  sample analysis  section, TOX  values are definitely
biased low.  Calculation of the detection limit based on the variability in
the blank  values  results in a detection  limit  of  12 ug/L instead of CL
reported limit of 5 ug/L.

LEACHATE SAMPLE ANALYSIS RESULTS

Specific Organic Analysis Results

     Table A-6 reports the organic constituent analysis  results for the two
leachate samples.   Large amounts  of volatile  and semivolatile  organic com-
pounds were detected in both leachate samples.

     In consideration of  the different dilutions analyzed, thus different
detection limits, fairly good agreement was obtained between the split sample
analyses performed by NEIC and the reported CL values for the PTA leachate.
NEK analyzed a  1 to 10  dilution  for the  volatiles while  the  CL  analyzed a
1 to 100  dilution.   The concentrations for the detected  volatile organic
compounds differed very  little  from  NEIC results.   The  CL  reported  that
1,1-dichloroethane was  present  but  below the Limit of Quantitation (LOQ).
NEIC found 400 ug/L 1,1-dichloroethane with an LOQ of about 60 ug/L.   Further,
NEIC detected  the presence  of  1,2-dichloroethane,  trichloroethene  and
tetrachloroethene, although  the  concentrations  were  below the LOQs.   NEIC
also found 500 ug/L xylene, 8,000 ug/L 2-propanol,  3,000 ug/L 2-butanol  and
the presence of 4-methyl-2-pentanol  that were not determinea or not detected
by the CL.

-------
A-10
     Similarly, the  CL  analyzed a more diluted extract for semivolatiles.
Benzoic acid and phenol were the major semivolatiles found.  The CL D5-phenol
surrogate recovery was only 12% and the CL reported the phenol concentration
in the sample as 2,000 ug/L.  NEIC obtained a 40% recovery for the D5-phenol
surrogate recovery  and  found  8,000 ug/L phenol in the sample.  Correction
of the CL  phenol  concentration for the  recovery  would indicate that the
sample actually contained  about 17,000 ug/L phenol while  correction  of  the
NEIC value  would  indicate  that  about  20,000 ug/L  phenol was present.  NEIC
also detected  700 ug/L  2-methylphenol,  220 ug/L 2-nitrophenol, 90  ug/L
4-methylphenol   and  30 ug/L 2,4-dimethylphenol.   The  colorimetric  phenol
analysis  found  41,000  ug/L total  phenol  which  indicates  the  presence of
other phenolic  compounds that were  not quantified or determined by the  gas
chromatography-mass spectroscopy analysis.

Metals Analysis Results

     The  total  metals results  for  the  leachate samples are  reported in
Table A-7.    Depending  on  the  suspended  matter composition,  the  values
reported  for certain elements  may not represent "total" concentrations.   If
the suspended matter is siliceous then values for aluminum, calcium,  magne-
sium, potassium and  sodium are  not  "total" because the  silicate matrix  was
not dissolved.   The heavy metal  results would approximate "total"  concentra-
tions because  they  are  usually  absorbed and are not incorporated  into the
silicate  matrix.

     NEIC split sample ICAP-OES results for the PTA leachate sample analysis
agree fairly well  with  the  CL results.   For  example,  the CL  reported
6,370,000 ug/L  potassium and 2,240,000 ug/L sodium while NEIC found 6,900,000
ug/L potassium  and 2,030,000 ug/L sodium.  The  CL reported 717  ug/L  nickel
and NEIC  found  707 ug/L.

     The  CL  encountered  difficulties  in analyzing  the PTA leachate  for
arsenic,  lead  and selenium.  Apparently, the high dissolved solids content
of the sample  caused  background correction problems for  the  furnace AAS
analyses.   NEIC found 27 ug/L  arsenic and less  than 7 ug/L selenium for the

-------
                                                                         A-ll
PTA split sample.  Hydride generation coupled to ICAP-OES was used by NEIC.
Less than 7 (jg/L lead was found by NEIC using Zeeman Effect background cor-
rected L'vov platform furnace AAS.

     The CL  raw  data for the arsenic  analyses  are confusing in that  it
appears that  there may  have  been  a mixup  between the two  leachate  samples.
For the analysis run, the PTA sample was given a run number of 42 while the
other  leachate  had  a run number  of  41.   The analysis  of sample 42 found
15.4 ug/L and  the  analysis  of a 20 pg/L arsenic spike to sample 42 gave a
concentration  of 76.7 ug/L which  is  a  spike  recovery of 307%.   A number of
different dilutions  of  sample 42  were analyzed and concentrations ranging
from 94 ug/L to 250 ug/L were obtained.  Sample 42 was then analyzed by the
methods of  standard  addition  and  125 ug/L  was  found; however, the  125 (jg/L
value  was  reported  for  the  Trench 2N leachate and the  PTA arsenic was
reported as  less than  150 ug/L.   Analyses of sample 41,  which was the
Trench 2N leachate, indicate the presence of about 140 ug/L arsenic, although
analysis by  the  methods  of  standard addition was  not  performed.   Since,
the CL results are confusing and interference was apparent, no arsenic data
is reported in the data  table.

General Analysis Results

     Table A-8 reports the results of other testing for the leachate samples.

     The calculated  POX  from  the  specific  volatile organic  results  for the
PTA leachate and the  measured POX are  in  good agreement.   It is obvious,
however,  that the TOX is biased substantially low.

     The anion data are  in general agreement with NEIC split sample results.
NEIC did, however, detect  25 ug/L cyanide while the CL reported less than
10 ug/L.   Only  3 mg/L ammonia  was  found  by NEIC  while the CL  reported
30 mg/L.

-------
A-12
                           O  O
                           (_><-»
                           u^  1/1  -
                           O  C
                           OJ  QJ  OJ  C -*->•*-  Ov
                           CL  CL E  Q.  u  o  ex
                          u^ t/l  fC <*n  Q.1  Q. i^n
                               i   3  i    3  J
                                     -
                           CL CL CL  CL  c- CL CL


                           cn cn cr  en  CD cn ^r
                           o  o  c  o   o  c  c

                           <-0  TD  n3  fC   fD  T:  T3
                           E  E  E  E   E  E  E
                           O  O  O  O   O  C  O
                              CD CO CD C3
                                         C      C
                                         o  c  c
                                      <-  OJ  -4-  Q.
                                     -_J      QJ
                                      <-  a.1  E  a.
                                      re  C  —-  C
                                      i-  T)  C  13
                           CL—      O  O  QJ  O
                   I   -4->  ID  C
                          C "-
                          T3
                             -u
                   It  j_»  OJ  U
                   It  1—  C* QJ
 LJ  u  OJ  u
        JZ
 GJ  QJ  *-»  a,
 C  C  QJ  C
 QJ  QJ  f—  Q;
r—  P—  >-,•—
                                      OJ  CJ •»-  QJ
                                     2:  2: o z:
                                      tb  O
                                     -—  il.
                                      O  —  —  ifl  c
                                      >  <~J  ^  C  C



                                      E  "S "C  C c
                                      0.  0-  C.  -
                                     i.~,  n_ -T- .":

T2 "O
O C
jr -£Z

CL a-
2: s:

CL. CL
_j 	 i
CJ CJ






>~,

o"
LJ >-
k/* CL
O O
i- c,'
-4— l/>
CJ C
a, k.
d-t-1
co w
a.
C CL
o ty->
r—
•4-J C
CL O
c. —
C -*-*
o~ CL
.c; i-
< c
y-
i_, _d
— -. "
t, ,c

_
L. «
CL i/1
H 

_4_)
(_;
ZJ
C
~










rc
t _
c


£
**~
c
o
—
_j_
t/1

cr
—


TT

{_}
«*






^
C
c.
p
a.
. —
UJ


CL
JC
^_>
c:
f
o
CXJ


-c
o
JZ

CL
21















QJ
CT>
T:

i_
22

QJ
C
C
_4_J
VI
*-J
T:
CL
.c
_S

•
LJ
F—
L.
_. .
a-'
E
C
!L_
^_>
c^
,_
i_J



























CL
tr
Q
^
LO
-*-J
C
GJ
E
a.
^
'V
^C CL
CL LJ
I~ C
•c
T^ -4-J
p — (_
CL —

! 	 C
~
CJ
LJ
^- QJ
• U
o c
J-) QJ
— < i-
cu
^C! ^*-
O OJ
-C i-
*J
QJ O
2: -z.


































>i CJ
k. r-
-*-1 W
Cj -t j
E QJ
O E
— o
-4-J r—
C CL>
G- _C
O QJ
CL ^.



























CL 0
C C
0 0
;r z^i










>^
j_j
t—
-o

^
^_
— Z5
C_ i —
00
o • — •
0 -C
"T
CO O
1 (NJ
KT O
^, CT-
0
o -o
we 0
.C
ec -4J
CL OJ
uj Z












>^
5_
-w >^
CJ t.
E *J
O Cb
*~ E
ZJ 0
C t—
CJ Z3
Q C
1- LJ
0 0
i— W_
s: <-•

» ^2
-c
a.
•*- TT
w" QJ
ZJ •*->
£} i/l
E z:
O JZ;
o E
o
QJ LJ

ID C
T3 0
CH-C
Z3 fe
CL CJ















C
O
-4_>
CL
t/i t-
S- 0
OJ V>

QJ ro
E
iTJ C
i_ o
ro QJ -C
CL C i-
o T:
CJ Z CJ
c
rO
CZ^1
t-
o

^
v-
t—
t^J
2.
Q_
Ul
1
C
c
^ X X
CD CD
CL >—
a
QJ r-.
C LO
a> —>
i- *r
CL
u- -O
QJ O
U £
-i~i
o a-'
z r:




•o
OJ
1_
t3
t.
«*- "C
C QJ
«— i i-
13
QJ k.
> H—
^ C
Ui •— •
C.
a, QJ
CL >
oo •(— •
i— oO
TT k
1 OJ
C CL
O 0^
—r -f—
-o

•c c
CJ 0
-»-* z
on
=5 •
_a QJ
e -u
O ro
t_i ^*-

QJ ZJ
i — CL
ZJ >
CL ZD















(b
C
Z)


•a
c


>-,

^
Q^ ~*D
c •-
O LJ
2: 
c
ro
-i-J
T3
-t-J C
C U
ro QJ
-u a.
fO Z3
C 1-0
i-
Qj >^—
a. c
Z3
1/1 C
O
U— r—
C -^
tJ
^ I-
U -U
-M "—
CL t—
E
c c
— o
-4-J *^*
C -M
QJ -O
-t-> -4->
0 r-
CL CL
•i—
QJ CJ
> QJ
•i— i_
-«-» CL
CJ
Qj CJ

QJ i-
UO Z3
U
§ CJ
— S














CL' Q-
i i
"c "S
y t/i

t/J t/'
OJ QJ
•4— > -"— '

f— f—
Z3 Z3
0 LJ
,,— .~-
•*-> -tJ

T; *u
CL CL











OJ
rc t3
— —
C t-
0 0
ff^
-C
cC CJ
-0 J2
o oo
CD ^0
C\J O
CT^ CT>

T3 "O
o o
J= -C
— -*-J
QJ QJ
Z 2:





-4— ' -i-J
C C
ro ^
^-J -*— '
(TS fT3
C C
k. t.
Q,1 QJ
CL CL
ZJ Z3
i/t (/I

4— 4-
O O

>, >-
i- t^

Qj Qj
E _S

I- T3
o —
r- £
O ^
CJ D
1 —
CJ
+J CJ
fC •*-»
i*- ro
i — •*-
Z3 ^~
t/1 Z3
l/>
QJ
c e
•r- rj
U -r-
S !a
cc cc














Q, QJ
. i
QJ QJ
on vi

(/) ^i
QJ CJ
-4-> -+-J

r— r—
ZJ ZS
*J CJ
— —
-t-1 -t-J

^ fZ
CL CL.












C,1 CJ
J-J -4-J

i- H-
•4-J r—
i- Z)
Z (-0
CJ
Cxj
TD CD
O CX
XI «3-

CJ -C
21 c
^z
CL -M
_j a;
CJ "SL
>-,
s_
4J
QJ
E
•f—
c.
O
^~
0
CJ
t
0
•4-J
Z3
CC
>.,
t. QJ
j-> C
-,
t. Q-
0 N-
1 	 -*-1
C C
LJ *O
O
CJ C
c <-
C E
•— «t
O 1
rsi ^T
03
U QJ
^•o
CL •—
C
CJ *O
c >^
1— t_'
"O ->~
-r- W_
>^ QJ
a. u.











c
c

c -»->
O tJ
"^ •-
r— -t-J

.,— •»—
•*-> "^
l/>

-o QJ

i — fO
ro E
ZJ C
c: -^-j
T3 Zl
T: -> f"
cj CL
t
i
H
1
1
1
1
1
1
I
1
t
1
1
1
I
1
1
1
1
1
1



1
1
1
]
1
1
t

I
]
I
1
1
t
1
I
1
t
1
1
t
t
t
I
1
(
1
1

1
I

1
I
1

1
t


1





1


t 0"
i TD
O
.c
C
E
CC

,__.

*

t)
t_
CD
! O
i i_

i

c

rc
i-
O
JC
_j

+_i
^,
1 ro
1 L.

C.
C
i CJ

1 •— •
1 13


















































O

CD
1
cn
7"
•3-
0
O
1

CL
LU
sC ^

CC i-"
1 T3
zs n
- c
0- T3
CL

v^ CL
T3 -k-1
"C
-r— >+_
•— O
C
OO 1/1
>^-
CT1 o"
C >>


tJ C
zj «r

rc r—
> TO
l^~' —
s- E
C CL
**- XI
LJ
1^*1
~c o
-C •*-
^_'
CL -n
21 "c^
O
-*_• ^^
^ —
QJ QJ
t- 2:

^— . . — -
.0 LJ

-------
                                                                          A-13
                 Table A-2

LIMITS  OF  QUANTITATION FOR ORGANIC COMPOUNDS
                B H S. , INC.
            Wright City, Missouri
Limit of Limit of Limit of
Quantitatior Quantitation Quanti tatic"
(pg/'L) (pg/L) (.pg/L)
vc'atile Compounds (Purge
firomomet.hane
Chloromethane
Bromodich'oromethane
Dibromochloromethane
Bromof orm
Chi orof orm
Carbon tetracnloride
Carson ai sul f iae
CMoroetnane
1, 1-Oich'oroethene
1, -Dich'oroetnare
1, , l-Tri chioroethane
1, ,2-T'ichloroethane
1, ,2,2-Tetracnioroethane
1, -C'Chloroethane
trans- 1.2-Oicnloroethene
Trichloroethene
Tet'achloroethene
Methylene cn'oriae
Vinyl chlonde
1,2-Qichloroprcpare
cis-1.3-Cic*'cropropene
trans- 1. 3-D icnl oropropene
Be~zere
Ch'oro&erzene
Et^> lbenzene
To~ ,,ene
>V e-es
Acetone
2-3utanor,e
2-iexanore
4-Methv 1 -C'Dentanone
2~ Ch 1 c roetny 1 vinyl etrer
Styrene
\pinyl acetate
^'"Ot.C^S G 6 "^ v GG
i. t " j * D^'Qr[\Q'"3~c^ ic^CDrop'S
l,*,I,2-Tet,racn1orGeinane
"" - r • r-T-f-rnfpt *• a fi p
1,3 j~ ' ricM^oi~GprcpanG
1 , H ~ Q i c h or*o~t"bdX.snfi
"r- ch'orof luorome thane
Ac^olem
Acwj "or- tn le
h
Vo^fle Compounds (DAI)

MC^y loii t^l "e
i ^"^^OXSHB

M f y ' 3 i C 0 HC 1
b~ ^ ' cysn'Cs
Isoo-tyl alcohol
Metnacryloni tri le
Acr^" P' r

-• > - ' y . -



& ' *"3D )
1C
10
5
5
5
5
5
5
-, ^
iU
5
5
5
5
5
5
5
5
5
10
1'j
5
5
5
5
5
5
5
5
10
10
1.0
10
10
5
1 J
50
e 20
20
C,
5
20
5
50
50


r [-,
SO
ICO

5 0
1 no
1 - U
ICO
25
"inn
iO U
50




Semi -Vol at- 1 e Compounds
Am 1 1 ne
4-Chloroam 1 me
2-Ni troani 1 i i«
3-Ni troahi ! i ne
4-Ni troani 1 i ne
Benz'di ne
3,3' -D'cnloroDenz'dme
Benzyl alcohol
Benzy' crlor'de
,2-Cichlorobenze~e
J-Dic^^robenzeie
,4-0^"' loroDerze-e
,2 ,4-Trich'oropenzene
,2,4,5-Tet-achlorobenzene
,2,3.4-Tetrachlorobenzene
'entacnio-ooenjene
hexachiorobenzene
pentachlororitrobenzene
Nitrobenzene
2 .4-Oi ni trotol uene
2 ,5-Di ni trotoluene
N-Ni t re sod1 methyl ami ne
N-Nitrcsoaichenylammes
N-Nitrosoai-ropvlamme
P1s(2-Chloroethyl ) ether
4-Cn loropheny' pneny" ether
4-3romcpheny i phenyl ethe'
bi s(,2-Ch loroi sopropy i ) ether
Pi s(2-Chloroethoxy ) methane
hexacnloroethane
HexachloroDutadiene
Hexachlorocyclopentad'ene
b-s(2-Ethylnexyl) pntnalate
Butyl benzyl ohtha'ate
oi-n-Butylphthalate
di-n-Octy'^ntnalate
Ciethylpnthalate
C 'methy Iphthalate
Acenapn*hene
Acenaphthy lene
Anthracene
Benzo(.a)anth-acene
Benzo(c)f 1 ucranthene and/or
5e-zo(k)flLC'ahthene
BenzcvQ.h , i Jperylene
Benzo(a)pyrene
Cn'-vsene
C'berzo(a,h)anthracehe
n. £g-; J« jran
F" ^cranthene
Inflenc\1.2,3-c,d)pyrene
i 5 u 0 . ^ - . 6
N3~,Ktnaiene
2-Ch loronaphtPa1eie
2-Methvlnaohthaiehe
P^era"tnrene
Pyene
5-Si tro-c-toTu'd'.-e

20
20
100
100
100
100
40
20
x r\
•*u
20
20
20
20
40
40
40
20
40
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
1 f
20
20
20

20
20
20
20
20
20
20
20
20
20
20
20
~Tl
i.U
20
40
Semi-Volatile Compounds (cont
N- nitrosodi ethyl ami ne
Acetopnenone
N-mtrosodipipendine
Safrole
1,4-Napthoaumone
2 ,3,4,6-Tetrachiorophenol
2-Napthylamme
Pyndme
Pentachloroethene
1.3,5-tnmtrobenzehe
Ethylmethacrylate
o-Toluiaine hydrochlonde
2,6-Dichlorophenol
p-Dimethylaminoazobenzene
1,2,3-Trichlorobenzene
1,3,5-Trichlorobenzene
1,2,3,5-Tetrachlorobenzene
Ethyl-methanesulfonate
alpha, alpha-
Dime thy Iphenethyl ami ne
Methapyrilene
7.12-Dimethylbenzanthracene
Benzal chloride
Zih-opnos
4-Aminobiphehyl
Tetraetnyldithiopyro-
phosphate
3,3'-Oimethylbenzidihe
Pronantide
Chloro&*nzi late
o-?hehylenediamine
m-Pheny lenediami ne
p-Phehy'enediamine
Isosafro le
N-Nit'osopyrro1idine
A^aim te
Dial late
D^methoxyDeni'dine
Be nzctrich! Gride
N' trosinethyl ethyl ami he
N-Nitroso-di-N-butylamine
Cydophospham^de
^exachloroprcpene
= henacetm
Resorcmol
Dimethoate
4,4(Methylene-bis
(2-chlcroam 1 me)
Oa-aioehyde
Methyl methare sulfonate
N-mtrosomorBnolme
1-Naphthylamme
1.2-Dipnehyihydrazme
Benzoic acid
Phenol
2-Chloropheno1
2,4-Oich!orophenol
2.4,5-Trichlorophenol and/or
2,4,6-Trich'crcpnenol
}
20
40
40
40
40
40
40
40
40
40
•+ _i
40
40
40
40
40
40
40

40
40
40
40
40
40

40
40
4C
40
40
* ^
"U
40
40
40
40
** J
4C
£ ^
160
40
160
40
4C
40
40

40
40
40
40
40
ICO
20
20
in

100

-------
 A-14
                                            TaDle A-2  (cort.)
Quart'tat';
Se"n-vclati le Compounds \:ont )
Pentachloropheno i 100
4-Chloro-3-methylphenoi 20
2-Methy iphenol 20
4-Hethylphenol 20
2,4-Dimethylphenol 20
4,5-Dim tro-2-meth> Ipne^ol IOC
2-Nitropnenol 20
4-Ni tropneno1 100
2 ,4-Din' trocnenol 100
















;n
Pest-cides 'PCEs
Aidrin
a^ha-BHC
beta-BHC
ga^ma-BHC
aelta-BHC
Chiordane
4.4'-DDO
4. 4 '-DOE
4.4' -OCT
Oie'dr-n
Enacsdifar I
Ercosu! 'an I!
Enaosulfan sol'ate
Encnr
Meptac"' or
H 6 [j t. 3 C I"! ' Or GJDOX 1 G6
f Ox ^D^ff np
Hetnoxj,:hlor
Endr1 1 k,e tone
PCB-1016
PCS- 1221
PC3-1232
PCB-1242
POB-124S
PCB-1254
prg-^_26C
Kepone
Limi t of
Quanti tafo
(M9/D

0 05
0 05
0 05
0 05
0 05
0 5
0 1
0 1
0 1
0 1
0 05
0 1
0 1
0 i
C 1
0 05
^i ^ C
d UD
1
0. 5
CT
1
0 5
0 5
0 5
0 5
0 5
1
1
0 1
n
herDic-des
QicamDa
Dalapon
MCPP
MCPA
Dichloroprop
2,4-Oichlorophehoxy
acetic acid
2,4,5-T
2,4-08
Oinoseo

Oioxms 4 3 ibenzo*urans
TCDO (Tet-a)
PeCDO (Penta)
HxCDD (Hexa)
HpCDO (lepta)
OCOD (Octa)
TCDF (Tetra)
PcCDF (Penta)
HxCDF (hexa)
HpCDF (Hepta)
CCDFF (Octa)





Limit o *
Quanti tation
(ug/L)

i
2
100
100
2

4
1
4
J.

(nq, u

5
6
4
44
i
3
3
17
13





easjrec as rip.T
irect aqueous i.-.;ec

-------
                                                                                                                                                               A-15
                                        o o o —
                                                                                                                         C*i O
                                                                                                                         "-> CO  <
                                                                                                                                   x
                                                                                                                                   o
t-  C
 QJ i—  '

21  S-
O O     r^
O «3"  v  >sC
                                                                                                         O ^ 1-D O
                                                                                                         a* —' <"*•} o
                                                                                              o
                                                                                             * co f
OJ
> OJ
                                       o  o cr ^H
                                                                                                        O -- ^
                                                                                                        O —'
                              > •—

                              O 
                                                          o o
                                                                                                                                                C r-
                                                                                                                                                c. •*-
                                                                                                                                                > £2
                                                                                                                                             CL
                                                                                                            QJ  cn ^o     •—  c
                                                                                                                                             C CJ  OJ
                                                                                                                                             d,' •— •+->
                                                                                                                                             U Q.
                                                                                                                                             c E  OJ
                                                                                                                                             O 1C  QJ
                                                                                                                                             CJ UO OO

-------
 A-16
                                                                               o
                                                                               CC
                               o o
                               o Ch
                                                                                                                    <"•"!  O
                                                                                                                        GO
                                                              — c -••>
                                                                 o
 a
cr  1/1
    aj c
 i/i  i— Z
••-  CL

O O O CTs
•Sf u r« — -* LO
u" (""";
*• v
CC v


^ — 0 CT>
— o *r
v o
V •
LO
S

U~> O O CC CD O CXi "•--
rn cc ex O r^ ^o
^C CD CC v
V V r. • •. V
r-~. CT> \o
CXI

0 ~>  O i-f l-^
O — ' CC f~~> r-
C ^-^
•> v v
*r v
•-*
    o   •

 ro  •— U
•4-J  C C
 C  O !—
•—' O U">
r- o m
                                                                              c o cr
                                                                              CO O cx>
                                                                                            O  CO
                                                                                            O  =0
                                                                 us o  a"1 cr
                                                                 —• co  n- -

-------
                                                                                                                                                                   A-17
                                         O G CC  O
                                                                            ^ o~> o
                                                                             ro o <
O O CNj 1£>
or-    o
*—• c-j v m
                                                                                                            CD —« "I O    i—•CQCT'"'
                               > OJ
                              i— ZJ
                                         O O C2  CD
                                                                                                                  mo     —• cc
                              p—  a,
                               T3  3

                               C  13
O CC     '~0
C —  v
                    —' <~O  O    •—<
 iT3 ••—  U
-^  C  C
 00  —
T:  2-
 c jc
 •C -^
                                                                                                                    ] O     •—" CC  f~> CS.
                                                                                                                     CO
                                                                                                                     CO
                                                                                                                                                    »-  T3
                                                                                                                                                    CT —
                                                                                                                            —• o  -n
                                                                                                                            -H co  -^ •
                               QJ  T3
                                                                          LT CD  ^ ^O     c: ^
                                                                                                                                                •f     O
                                                                                                                                                    CO
                                                                                                                                                •c  i^  c

-------
A-18
                                                                                   O  O C
                                                                                   O  CO
                                                                                   O  I—
                                                              C r^ ^ O
                                                              CO —* rr o
                                                                                                     « v v   *
    0.0
 w  E ^
•—  re
C O (

uO .~)

V V
                                                                                                            o    •—' OO  <
    C  t-
   *J ^
    ex
 ra  u  u
•«->  a,  c
 O 4_> .—,
h-  C

T3    CO
                                                                     ) O O i
                                                                       CO O
                                                                                   o
                                                                                   o
                                                              O CO ^
                                                              CO
                                                              CC V
                                                                                                                                     13 TJ
                                                                                                                                        -C
                                                                                                                                     C -~
                                       j ju     o c  cn-i-
                                       . o-    n 2: z z
                                                                                                      o> CD f
                                                                                                      on <:

-------
                                                                                                                                             A-19
 OJ
cc
ro fO
C uO •
   C •*->
   O> -C
0, QJ LO
e -c  •
a, 4- 2:


r—
(—-









r-~







0
^






r— .
UD









CO
<*&







•0
^c










w


cr















^
:^L


^
CO ^ p" <-n


C-w


ro

CNJ
. - CJ c_; O

i/1 > — — i — i — i
c z --. — - -—
^: cr> en cr>
E 3 3 E
3



OJ
(_
C >•>
IB — - — -
4_j •»— - — . j_)
<_) T3 U • — '
3 -r— - — -
~a -C 'o
C i- X >*. O
C 3 00 C-



r-n ro
cz: CD






*-,
•u", m

LT- C
C\j v o
T
OJ




^T r^i
^~) O
fNJ V ^f
CsJ
CsJ



n-j C^
LT^ O
<^r rvj
C3
CM






ro T
LT< O
v u~) vO

 	 ' Z! LO



CD


V





.
0
»"—

V





o
1— 1

v




0
1-^

v







O
I—I

v





O
^-1

v








	 1

cr>
3









OJ
T3
-r-
C

>^
t^)
11
II
11
II
m )1

1
V 11
II
(
tl
M
1
* II
O> 1
m i
M
i
M
11
i
i
1
~i i
ro 1
1
V I
II

11
II
i~> fl
P1*! !
II
V II



11
II

II
OJ II
*-. 11
1 — 1 II
II
11

tl
11
II
r-i 11
m n
!l
V ||
M



tl
M
1
t
_J 1
-v. 11
c- (i
Z! 1
1
1
||


1
- — - II
(_) 11
•— ' II
!
i — 1
0 1
C H
CJ II
f_ \
Q_ 11























































i
fSi
>^

rQ
C
fO


C
c

'J~>
fC
3
^_
OJ

dj
E
«c
t.
'C
0-

, — .
• 13






























C
O
• t—
-4— '
n*
t-
4-1
c
QJ
CJ
C
Q
(_>


C
>
en

c
-c

U1
t/1
QJ


1/1
fO


C
C


rt3
U
*j
C
GJ
C
o
(_)

QJ
r—
c.
E
t3
t^o

^-~
^D






















l/i
QJ
ra


i-
QJ
"S
E
t)
l_
^
Q.

**-
O

>-i

•»-
Z^
^2
«T3
• ^~
f—
U

OJ
-*-J
V-
0

c

•^
t/>
tn
3
^,
^>
— •


CU
JZ


W
M_

.^
X
CD
^j

QJ
GJ
t^l

-— .
U

-------
       A-20
—'     —  E   -
13      ^  T3  :>-,
 QJ      C       ItJ  C -*->
 C      i-  Q, ^Z
 o      QJ  ^  cn
           C
           m   »
                                                                                   LO     O
                                                                                v  r^i  v  ex
                                                                                          O
                                                    C^ ^
                                                    O CO
                                                cc o ^
                                                    o *
                                                    o
                                                              (_J  (_J     CJ
                                                               cri en     en
                                                               =5 3     E
                                                                                   C71 E CT
                                                                                   E     E
                                                                                                 OJ
                                                                                                -O —
                                                                                                 r-  O
                                                                                                                •  QJ  C
                                                                                                               -o —  o
                                                                                                               QJ    •—
                                                                                                                   I  3
                                                                                                                      U
                                                                                                                   C  VI
                                                                                                                   O  —
 ^  a.'  '_
 ^C  U  C
    C 
-------
                                                                                                                                                                             A-21
.a

o  o
                                           ooozoooooo
                                                                                                                                VI  C
                                                                                                                                c  o
                                                                                                                                o —
                                                                                                                         O"
                                                                                                                         O
                                                                                                                                "~ -o
                                                                                                                                -t-j
                                                                                                                                c  t/>
 i/>  g    •
 >i fO  >-,
i—'  i/"J -^
 T3      —
 C  GJ LJ
CT  -4-J
    H3 -t-»
*J  .C -C.
                                    O O O O    00
                                   oo
                                   m csj
                                                                                                    X X  X X
                                                                                                    o o  o o
                                                                                                    O CX,  LD O
                                                                                     3

                                                                                     c
                                                                                     o
                                                                                                                                •r-  -, O  I  -T—  T3
                                                                                                  " r-  E  */l  I-
                                                                                                  r  O  OJ  QJ  OJ
                                                                                                  : :^ to Q. nr
                                                                                                                                —  o
                                                                                                                                3 -*-1
                                                                                                                                E
                                                                                     ^ -C  '-- ^D
                                                                                     rO  OJ      -O
                                                                                     3 *-  S- t-
                                                                                         u  O
                                                                                     T3  OJ  -*-J  C
                                                                                     C *-  O -f-
                                                                                     3  a,'  
                                                                                     o  o  o •«-

-------
      A-22
                                                                                           O -G sO O
                                                                                           O    rn O
                                                                                           o       o
     *J    O
     •—    2:
QJ    «r  u :


TO    •— _)
                                                               i-i"1  O O
                                                               f*^  CC O
                                                                    o
                                                                       —>    c o cc i
o o
^-< co
                                                                                                                           •— O>
                                                                                                                              4_>
                                                                                                                           VI ?O
                                                                                                                           C  0,
                                                                                                                           O  E
                                                                             en c  cr —
                                                                                                                           tL  O
                                                                                                                           f—  ^
                                                                                                                           O. -^J
                                                                                                                           E  c

-------
OJ

.c
                                    c o
                                    n c
                                    O I--
o   con
CO   —< O  II
                                            CT
                                            £
                                                      TO TO    r-
                                    X X
                                    O O
                                    C_ t—
                                           ^_s    O O S- '*-
                                                                                                                                 A-2:

-------
     APPENDIX B
CONSTRUCTION DRAWINGS

-------
                                                      E-l
44
       744.4
           fik
           s
                  741-5     739.7
                         LCS
                           738.0
                  741.0    738.2
50
                                    50
                                   25
                              SUMP

    LCS-Leachate Collection System
               FIGURE  B-l
              TRENCH 1-N
         (REVISED FROM B.H.S. INC.)

-------
70'








s
C
e
c*



«•
' '
>







>
>
i

r
*
0.









i
S,
C



•Ml
».

''







*.
0
C
I


^
1
J
<^\ '
R
A
M
P
LCS
J
|
T


*3*' S^
x ** *^
*J ' . 
-------
                                                         B-3
   W
         LCS
tfl
     o
     M
VI
vj
                     55'
                            VI
                            sO
                                   R

                                   M
                                   P
        LCS-Leachate Collection System
                FIGURE B-3
               TRENCH 6-N
          (REVISED FROM B.H.S.,

-------
                                                            B-4
LCS-Leachate Collection System
                 FIGURE B-4







                TRENCH 11-N




        (REVISED FROM REITZ *TENS. INC.)

-------
LCS-Leachate Collection  System
             FIGURE B-5




            TRENCH  12-N






    (REVISED FROM REITZ  ft JENS. INC.)

-------
B-6

-------

-------
£
                   -—	1
         ''41—^—^---)—!—•- m
          i-—i	,L_ ,
                                                                     IT




—
''\ , ' : -*
- — ' ~ > ^
V. ^
_ \. i "
- —
t - I


IX))** | •••••• 1 ^TDEKIockow 8 Associates 314
OJ rS 1 1 •••• 1 ^ Consulting Geotechnicai Engineers 443-6084
^ tPI •• ••• • X.592I Wogon Trail Road.Rt 14, Columbia, Missouri 65202
", '{jiHS; loc^odu^trial Waste Management Facility
ft fit 1, Bofeil6-F, Wright City, Missouri 63390
t-;>^
- '1^-lN
/t" "•• • .







j
1
1
'
i EACHATE -SYSTEM DETAILS ' '— ""










M
;;l
! I
i i












*
$
«












i • ; i ;
! ' < : : '
i . ; '


1 1
1 1
i '
i !
; ; ,
r' J !
•


;
,





f c - -


f
^ r-.
->
'r. o
O3
p
oo
] , ' ' : ' ' ' i ' , ' if'_
''• , '' • ' ' ' i M
1 j ; • ' : ; ' ; ' i i i >'i

•iii
" i i ; ; ' 1;

-------
                   r
,9   1
!C
D E Klockow a Associates                     3i4
Consulting Geotectir.,cal Engineers         443-6084j
5921  Wa-oi Trail Road, Rt ;4,Columbia Missouri 65202'    ,-V^1

-------
FIGURE  B-10
  «8

  M
  u    i-
  5    3
  K    —
  IX
  o
  H-
  a.
  LU
  O
  X
  -J
  H-
Z
0
CJ
  -    Z
  *    *•.
  Z    ^
       z
       o

-------
                                          FIGURE B-ll
O
                   z
                   <
                                            z
                                            <
t-
z

-------
        APPENDIX C
POTENTIOMETRIC SURFACE MAPS

-------
          APPENDIX D
GROUND-WATER MONITORING SYSTEMS

-------
                                                                                 D-l
PROPOSED HAZARDOUS
WASTE DISPOSAL  AREA
                                            W«lli

-------
                                                                                         D-2
PROPOSED HAZARDOUS
WASTE DISPOSAL AREA
                         Flgur* D-2.  Sy»ttra  '2 W«lli

-------
                                                                                                         D-3
                                                         INTERCEPTOR |\
                                                         TRENCH •!
                PROPOSED HAZARDOUS

                WASTE DISPOSAL AREA
I                      B-1A«,
i                     0
j°"-    #      L	'
i
       B-l J •
      B-14 A*
                                                             LEGEND:

                                                             • B  ..II. IRCRA)

                                                             • GMW ».IU loo*-RCRA)

                                                             o Pr«pet*4  w.ll.          Sell.
                                         Figure D-3.  Sy»t«m  *3 W«llt

-------
                                                                                       D-4
PROPOSED HAZARDOUS
WASTE DISPOSAL AREA
                      Flgur« D-4. W«IU P-17 through  P-22

-------
PROPOSED HAZARDOUS
WASTE DISPOSAL AREA
                            Figure D-t.  K-icri
-------
                                                                                     D-6
                                  \\
                                   . x INTERCEPTOR
                                   '-•T'TRENCH »3
PROPOSED HAZARDOUS

WASTE DISPOSAL AREA
                      Fi3urt D-6. W.IU PA through PD

-------