xvEPA
              United States
              Environmental Protection
              ?.gency '
               Office of Emergency and
               Remedial Response
               Washington DC 20460
 Office of Research and
' Development
* Hazai Jous Waste Engineering
 Research Laboratory
 Cincinnati OH 45268
              Technology Transfer
                              EPA/625/6-85/006
Handbook
              Remedial Action at
              Waste Disposal Sites

              (Revised)

-------
                                             EPA/625/6-85/006
                    HANDBOOK
REMEDIAL ACTION AT WASTE DISPOSAL  SITES  (REVISED)
                  OCTOBER 1985
 HAZARDOUS WASTE ENGINEERING RESEARCH LABORATORY
       OFFICE OF RESEARCH AND DEVELOPMENT
      U.S. ENVIRONMENTAL PROTECTION AGENCY
             CINCINNATI, OHIO  45268
    OFFICE OF EMERGENCY AND REMEDIAL  RESPONSE
  OFFICE OF SOLID WASTE AND EMERGENCY RESPONSE
      U.S. ENVIRONMENTAL PROTECTION AGENCY
             WASHINGTON, D.C.  20460
                             U.S. Environmental Protection Agency
                             Reg'on V, Library
                             230 South Dearborn Street
                             Chicago,  Illinois  60604           .,..

-------
                         NOTICE
The information in this document has been funded, wholly
or in part, by the United States Environmental Protection
Agency under Contract No. 68-03-3113 to SAIC.  It has been
subject to the Agency's peer and administrative review and
has been approved for publication as an EPA document.
Mention of trade names or commercial products does not
constitute endorsement or recommendation for use.
                           ii

-------
                                   ABSTRACT
     This handbook is intended for use as a basic reference tool on remedial
action.  It will assist governmental and industrial officials and technical
persons in understanding remedial technologies; selecting potentially appli-
cable technologies for a given waste site, and planning for remedial action.

     The handbook begins with an overview of the remedial investigation/
feasibility study (RI/FS) process as outlined in the National Contingency Plan
(NCP).

     The remaining sections of the document describe remedial technologies.
The technologies are organized according to the type of site problem they are
intended to remedy (e.g., surface water controls, groundwater controls).
Emphasis is placed on those technologies which have been demonstrated for
hazardous waste sites.  However, less detailed information is also included on
emerging technologies.  Established technologies are generally described in
terms of the following factors:

     •  General description

     •  Applications and limitations
     •  Design considerations

     •  Construction/implementation considerations
     •  Operation, maintenance, and monitoring
     •  Technology selection/evaluation
     •  Costs.

     The section on applications and limitations describes waste and site
conditions which favor or limit use of each technology.

     Major design, construction, and operational considerations are described
in subsequent sections.  The information is intended to provide a basic
understanding of the technologies, and a framework for planning and developing
remedial action alternatives.  More detailed guidance manuals and design
manuals on these subjects are referenced extensively throughout the document.

     The section on technology selection/evaluation provides an overview of
each technology or related group of technologies in terms of their known
technical feasibility (e.g., reliability, effectiveness, ease of implementa-
tion) and any significant environmental, public health, or institutional
effects associated with them.

     Finally, unit cost data, expressed mainly in 1984 or 1985 dollars, are
included for each technology.  Cost data from hypothetical sites or actual
case histories has also been included where it is appropriate.
                                      111

-------
                               TABLE OF CONTENTS
                                                                         Page

ABSTRACT	iii
LIST OF FIGURES	xii
LIST OF TABLES	xx
ACKNOWLEDGMENTS	xxv

1.  INTRODUCTION	    1-1

    1.1  Background and Objectives	    1-1
    1.2  Organization of the Handbook	    1-2

2.  REMEDIAL ACTION SELECTION PROCESS	    2-1

    2.1  Remedial Investigation/Feasibility Study Process	    2-1
    2.2  Remedial Action Selection Process (Feasibility Study) ....    2-3

         2.2.1  Proposed Response Action Identification	    2-3
         2.2.2  Technology Screening 	    2-3
         2.2.3  Development of Remedial Action Alternatives	    2-8
         2.2.4  Screening and Detailed Evaluation of
                  Remedial Action Alternatives 	    2-8
         2.2.5  Remedial Alternative Selection 	    2-13

3.  SURFACE WATER CONTROLS 	    3-1

    3.1  Capping	    3-2

         3.1,1  General Description	    3-2
         3.1.2  Applications/Limitations 	    3-4
         3.1.3  Design Consideration 	    3-5
         3.1.4  Construction/Implementation Considerations 	    3-9
         3.1.5  Operation, Maintenance, and Monitoring 	    3-10
         3.1.6  Technology Selection/Evaluation	    3-11
         3.1.7  Costs	    3-11

    3.2  Floating Covers	    3-13

         3.2.1  General Description	    3-13
         3.2.2  Applications/Limitations 	    3-13
         3.2.3  Design Considerations	    3-13
         3.2.4  Construction/Implementation Considerations 	    3-16
         3.2.5  Operation, Maintenance and Monitoring	    3-18
         3.2.6  Technology Selection/Evaluation	    3-18
         3.2.7  Costs	    3-19
    3.3  Grading	    3-19

-------
                         TABLE OF CONTENTS (Continued)
         3.3.1  General  Description	    3-19
         3.3.2  Applications/Limitations 	    3-19
         3.3.3  Design Considerations	    3-20
         3.3.4  Construction Considerations	    3-21
         3.3.5  Operation,  Maintenance and Monitoring	    3-23
         3.3.6  Technology  Selection/Evaluation	    3-24
         3.3.7  Costs	    3-24

    3.4  Revegetation	    3-26

         3.4.1  General  Description	    3-26
         3.4.2  Applications/Limitations 	    3-26
         3.4.3  Design Considerations	    3-28
         3.4.4  Construction/Implementation Considerations 	    3-29
         3.4.5  Operation,  Maintenance,  and Monitoring 	    3-32
         3.4.6  Technology  Selection/Evaluation	    3-32
         3.4.7  Costs	    3-32

    3.5  Surface Water Diversion and Collection	    3-32

         3.5.1  Dikes  and Berms	    3-36
         3.5.2  Channels and Waterways	    3-40
         3.5.3  Terraces and Benches	    3-52
         3.5.4  Chutes and  Downpipes	    3-57
         3.5.5  Seepage Basins and Ditches 	    3-63
         3.5.6  Sedimentation Basins/Ponds 	    3-67
         3.5.7  Levees and  Floodwalls	    3-74
         3.5.8  Selection/Evaluation Criteria	    3-79
         3.5.9  Costs	    3-80

4.  AIR POLLUTION CONTROLS	    4-1

    4.1  Control of Gaseous Emissions to the Atmosphere	    4-1

         4.1.1  Covers	    4-1
         4.1.2  Active Interior Gas Collection Recovery/System ....    4-4

    4.2  Fugitive Dusts	    4-4

         4.2.1  Dust Suppressant	    4-4
         4.2.2  Wind Fences/Screens	    4-6

    4.3  Water Spraying and Other .Commonly Used Techniques 	    4-7

5.  GROUNDWATER CONTROLS 	    5-1

    5.1  Groundwater Pumping	.'  .    5-1
                                      VI

-------
                         TABLE OF CONTENTS (Continued)
                                                                         Page
         5.1.1  Description	    5-1
         5.1.2  Applications/Limitations 	    5-2
         5.1.3  Design	    5-5
         5.1.4  Installation of Wells	    5-32
         5.1.5  Maintenance and Performance Monitoring 	    5-38
         5.1.6  Technology Selection/Evaluation	    5-39
         5.1.7  Costs of Well Systems	    5-40

    5.2  Subsurface Drains 	    5-45

         5.2.1  Description	    5-45
         5.2.2  Applications/Limitations 	    5-47
         5.2.3  Design	    5-48
         5.2.4  Construction	    5-67
         5.2.5  Performance Monitoring  	    5-72
         5.2.6  Technology Selection/Evaluation	    5-73
         5.2.7  Costs	    5-73
    5.3  Subsurface Barriers 	   5-83

         5.3.1  Slurry Walls	   5-83
         5.3.2  Grouting                                                 5-97
         5.3.3  Sheet Piling	   5-109
         5.3.4  Bottom Sealing	   5-112

6.   GAS CONTROL	   6-1

    6.1  Passive Perimeter Gas Control Systems 	   6-2

         6.1.1  General Description	   6-2
         6.1.2  Applications/Limitations 	   6-4
         6.1.3  Design Considerations	   6-4
         6.1.4  Construction/Implementation Considerations 	   6-8
         6.1.5  Operation, Maintenance,  and Monitoring 	   6-8
         6.1.6  Technology Selection/Evaluation	   6-9
         6.1.7  Costs	   6-11

    6.2  Active Perimiter Gas Control Systems	   6-11

         6.2.1  General Description	   6-11
         6.2.2  Applications/Limitations 	   6-15
         6.2.3  Design Considerations	   6-15
         6.2.4  Construction/Implementation Considerations 	   6-21
         6.2.5  Operation, Maintenance,  and Monitoring 	   6-23
         6.2.6  Technology Selection/Evaluation	   6-23
         6.2.7  Costs	   6-24
                                      VII

-------
                         TABLE OF CONTENTS (Continued)
    6.3  Active Interior Gas Collection/Recovery Systems 	   6-26

         6.3.1  General Description	   6-26
         6.3.2  Applications/Limitations 	   6-28
         6.3.3  Design Considerations	   6-28
         6.3.4  Construction/Implementation Considerations 	   6-30
         6.3.5  Operation, Maintenance, and Monitoring 	   6-30
         6.3.6  Technology Selection/Evaluation	   6-30
         6.3.7  Costs	   6-31

7.   ON-SITE AND OFF-SITE DISPOSAL OF WASTES AND SOIL	   7-1

    7.1  Excavation and Removal	   7-1

         7.1.1  General Description	   7-1
         7.1.2  Applications/Limitations	   7-1
         7.1.3  Excavation Equipment 	   7-2
         7.1.4  Implementation of Excavation and
                  Removal Activities 	   7-17

    7.2  Off-Site Disposal 	   7-24

         7.2.1  General Description	   7-24
         7.2.2  Applications/Limitations 	   7-24
         7.2.3  Implementation	   7-25
         7.2.4  Selection/Evaluation Considerations	   7-29

    7.3  On-Site Land Disposal	   7-30

         7.3.1  General Description	   7-30
         7.3.2  Applications/Limitations 	   7-30
         7.3.3  Landfill System Design, Construction,
                  and Implementation	   7-30
         7.3.4  On-Site Landfill Operation, Monitoring,
                  and Maintenance	   7-34
         7.3.5  Technology Selection/Evaluation	   7-37
         7.3.6  Costs                                                    7-38

8.   REMOVAL AND CONTAINMENT OF CONTAMINATED SEDIMENTS	   8-1

    8.1  Sediment Removal	   8-1

         8.1.1  Mechanical Dredging	   8-2
         8.1.2  Hydraulic Dredging 	   8-7
         8.1.3  Pneumatic Dredging 	   8-17
         8.1.4  Implementation of Dredging Operations	   8-20
                                     Vlll

-------
                         TABLE OF CONTENTS (Continued)
         8.1.5  Technology Selection/Evaluation	   8-31
         8.1.6  Cost	   8-36

    8.2  Dredge Material Management	   8-43

    8.3  In-Situ Control and Containment Measures	   8-47

         8.3.1  Retaining Dikes and Berms	   8-48
         8.3.2  Cover Methods	   8-49
         8.3.3  Surface Sealing	   8-53
         8.3.4  In-Situ Grouting 	   8-56

9.   IN-SITU TREATMENT	   9-1

    9.1  Bioreclamation	   9-2

         9.1.1  General Description	   9-2
         9.1.2  Applications and Limitations 	   9-3
         9.1.3  Design Considerations	   9-15
         9.1.4  Operation and Maintenance	   9-31
         9.1.5  Technology Selection/Evaluation	   9-34
         9.1.6  Costs	   9-35

    9.2  Chemical Treatment	   9-36

         9.2.1  General Description	   9-36
         9.2.2  Applications/Limitations 	   9-38
         9.2.3  Soil Flushing	   9-45
         9.2.4  Immobilization	   9-50
         9.2.5  Detoxification	   9-52
         9.2.6  Technology Selection/Evaluation	   9-58
         9.2.7  Costs	   9-59

    9.3  Physical In-Situ Methods	   9-61

         9.3.1  General Description	   9-61

10. DIRECT WASTE TREATMENT 	   10-1

    10.1 Aqueous Waste Treatment 	   10-1

         10.1.1   Activated Carbon Treatment 	   10-3
         10.1.2   Biological Treatment 	   10-10
         10.1.3   Filtration 	   10-19
         10.1.4   Precipitation/Flocculation 	   10-22
         10.1.5   Sedimentation Technology 	   10-32
         10.1.6   Ion Exchange and Sorptive Resins 	   10-36
                                      IX

-------
                         TABLE  OF CONTENTS  (Continued)
                                                                        Page

         10.1.7    Reverse Osmosis	   10-40
         10.1.8    Neutralization  	   10-45
         10.1.9    Gravity Separation  	   10-47
         10.1.10   Air  Stripping	   10-48
         10.1.11   Oxidation	   10-52
         10.1.12   Chemical Reduction  	   10-55

    10.2  Solids Treatment	   10-57

         10.2.1    Solids  Separation	   10-57
         10.2.2    Dewatering  	 •  10-76

    10.3  Solidification/Stabilization	   10-105

         10.3.1    Cement-Based  Solidification	   10-106
         10.3.2    Silicate-Based  Process  	   10-107
         10.3.3    Sorbents  	   10-110
         10.3.4    Thermoplastic Solidification  	   10-112
         10.3.5    Surface Microencapsulation  	   10-114
         10.3.6    Vitrification	   10-115
         10.3.7    Technology  Selection/Evaluation	   10-116

    10.4  Gaseous  Waste Treatment  	   10-118

         10.4.1    Flaring	   10-118
         10.4.2    Adsorption	   10-121
         10.4.3    Technology  Selection/Evaluation	   10-122

    10.5  Thermal  Destruction  of Hazardous  Wastes  	   10-123

         10.5.1    Liquid  Injection  	   10-125
         10.5.2    Rotary  Kiln	   10-126
         10.5.3    Multiple  Hearth	   10-128
         10.5.4    Fluidized Bed	   10-129
         10.5.5    At-Sea  Incineration,  Mobile Incineration  and
                    Co incineration	   10-131
         10.5.6    Advanced  Incineration Technologies  	   10-131
         10.5.7    Environmental Controls 	   10-137
         10.5.8    Overall Operation and Design  Considerations	   10-138
         10.5.9    Costs	   10-138

11.  CONTAMINATED  WATER SUPPLIES AND WATER AND SEWER LINES	   11-1

    11.1  Replacement of Contaminated Central  Water Supplies	   11-2

    11.2  Point-of-Use Water Supplies 	   11-3

-------
                         TABLE OF CONTENTS (Continued)
    11.3 Treatment of Contaminated Central Water Supplies	   11-4

    11.4 Point-of-Use Water Treatment.  ...  	   11-5

         11.4.1   General Description	   11-5
         11.4.2   Applications/Limitations  	   11-6
         11.4.3   Design Considerations	   11-7
         11.4.4   Construction/Implementation Considerations  	   11-7
         11.4.5   Operation, Maintenance, and Monitoring 	   11-7
         11.4.6   Technology Selection/Evaluation	   11-8
         11.4.7   Costs	   11-8

    11.5 Replacement of Water and Sewer Lines	   11-9

         11.5.1   General Description	   11-9
         11.5.2   Applications/Limitations                               11-9
         11.5.3   Design Considerations	   11-10
         11.5.4   Construction/Implementation Considerations  	   11-13
         11.5.5   Operation, Maintenance, and Monitoring 	   11-14
         11.5.6   Technology Selection/Evaluation	   11-14
         11.5.7   Costs	   11-14

    11.6 Inspection and Cleaning of Water and Sewer Lines	   11-14

         11.6.1   General Description	   11-14
         11.6.2   Applications/Limitations  	   11-16
         11.6.3   Design Considerations	   11-16
         11.6.4   Construction/Implementation Considerations  	   11-16
         11.6.5   Operation, Maintenance, and Monitoring	11-20
         11.6.6   Technology Selection/Evaluation 	  11-20
         11.6.7   Costs 	  11-21

    11.7 Rehabilitation of Water and Sewer Lines	11-21

         11.7.1   General Description 	  11-21
         11.7.2   Applications/Limitations	11-22
         11.7.3   Design Considerations 	  11-23
         11.7.4   Construction/Implementation Considerations	11-23
         11.7.5   Operation, Maintenance, and Monitoring	11-29
         11.7.6   Technology Selection/Evaluation 	  11-29
         11.7.7   Costs 	  11-29

APPENDIX A.  Index	A-l
APPENDIX B.  Copyright Notice 	  B-l
                                      XI

-------
                                LIST OF FIGURES


FIGURES                                                                  PAGE

2-1   RI/FS Process	   2-2

2-2   Matrix of General Remedial Technology Categories for
      Specific Site Problems 	   2-4

2-3   Identification of Data Needs for Various Remedial
      Technologies 	   2-5

3-1   Multimedia Cap	   3-6

3-2   Schematic Plan for Cross-Section of a Floating Cover
      Incorporating the Patented Burke Design	   3-14

3-3   Schematic Plan and Cross-Section of a Floating Cover
      Incorporating the Patented Burke Design	   3-15

3-4   Schematic Plan and Cross-Section of a Patented Globe
      Floating Cover and Gas Collection System Design	   3-17

3-5   Grading Vehicles and Accessories 	   3-22

3-6   Gas Migration Controls	   3-30

3-7   Temporary Interceptor Dike	   3-37

3-8   Temporary Diversion Dike	   3-39

3-9   Typical Drainage Ditch at Base of Disposal Site	   3-42

3-10  General Design Features of Diversions	   3-43

3-11  Grassed Waterways	   3-45

3-12  Grassed Waterways with Stone Centers 	   3-46

3-13  Standard Design  for Drainage Ditches 	   3-47

3-14  Effect of Drainage Ditch on Velocity 	   3-48

3-15  Bench Terraces	   3-53

3-16  Typical Drainage Bench 	   3-54

3-17  Slope Reduction Measures  	   3-55

3-18  Paved Chute  (or Flume)	   3-58

3-19  Rigid Downpipe	   3-59

                                      xii

-------
                          LIST OF FIGURES (Continued)


3-20   Flexible Downpipe	3-60

3-21   Seepage Basin; Large Volume, Deep Depth to Groundwater 	  3-65

3-22   Seepage Basin; Shallow Depth to Groundwater	3-65

3-23   Seepage Ditch	3-66

3-24   Seepage Ditch with Increased Seepage Efficiency	3-66

3-25   Typical Design of a Sediment Basin Embankment	3-68

3-26   Particle Size Distribution Graph 	  3-70

3-27   Modification of Conventional Sedimentation Pond
       to Reduce Suspended Solids  	  3-72

3-28   Typical Levee at Base of Disposal Site	3-76

3-29   Perimeter Flood Protection Structure 	  3-76

3-30   Some Typical Floodwall Sections	3-77

3-31   Levee Configurations  	  3-78

5-1    Containment Using Extraction Wells 	  5-3

5-2    Extraction and Injection Well Patterns for Plume Removal ....  5-4

5-3    Plume Diversion Using Injection Wells	5-6

5-4    Formation of Cone of Depression for a Pumped Well	5-9

5-5    Unconfined Aquifer Flow	5-10

5-6    Confined Aquifer Flow	5-11

5-7    Plots of H-h Versus r for Unconfined and Confined
       Aquifers	5-13

5-8    Comparison of Radial Flow to a Fully Penetrating Well
       with Flow to Partially Penetrating Well	5-14

5-9    Composite Drawdown in a Confined Aquifer	5-15

5-10   Recharge and Discharge Wells in Confined Aquifer 	  5-16

5-11   Method of Images for Determining Resultant
       Cone of Depression	5-18
                                     Xlll

-------
                          LIST OF FIGURES (Continued)


5-12   Distance Drawdown Diagrams for A) Varying Pumping Rating
       and B) Varying Pumping Times	5-21

5-13   Components of Typical Deep Well	5-24

5-14   Performance Curve	5-27

5-15   Components of One-Pipe and Two-Pipe Ejector Wells	5-29

5-16   Driven Wellpoint (a), Jetted Wellpoint (b), and
       Drilled Wellpoint  	  5-31

5-17   Subsurface Drainage System Components	5-46

5-18   The Use of a One Sided Subsurface Drain for Reducing Flow
       from Uticontaminated Sources	5-49

5-19   The Use of Subsurface Drainage to Lower Groundwater Levels        5-50

5-20   The Use of Subsurface Drainage in a Completely Encapsulated Site  5-51

5-21   The Affect of Relief and Interceptor Drains in Altering the
       Configuration of the Water Table  	  5-52

5-22   Subsurface Drain with a Lift Station	5-53

5-23   Symbols for the Glover and Donnan Equation for Calculating
       the Downgradient Influence of an  Interceptor Drain 	  5-55

5-24   Flow to a Drain Resting on a Low  Permeability Barrier	5-57

5-25   Basic Injection Well	5-58

5-26   Capacity Chart for N = 0.015	5-63

5-27   Typical Manhole Design for a Closed Drain	5-65

5-28   Typical Design of an Automatic Drainage Pumping Plant	5-66

5-29   Examples of Slurry Wall Placement Options	5-85

5-30   Typical Slurry Wall Construction  Site	5-90

5-31   Cross-Section of Slurry Trench, Showing Excavation and
       Backfilling Operations 	  5-91

5-32   Composition of Cement-Bentonite Slurries 	  5-95
                                      xiv

-------
                          LIST OF FIGURES (Continued)


5-33   Applicability of Different Classes of Grouts Based on
       Soil Grain Size	5-98

5-34   Semicircular Grout Curtain Around Waste Site 	   5-106

5-35   Vibrating Beam  Grout Injection  	   5-108

5-36   Some Steel Piling Shapes and Interlocks	5-110

6-1    Pathways of Gas Migration	6-3

6-2    Passive Gas Control Using a Permeable Trench 	   6-5

6-3    Passive Gas Control Synethtic Membrane  	   6-6

6-4    Typical Gas Monitoring Probe 	   6-10

6-5    Active Gas Extraction	6-16

6-6    Gas Extraction  Well	6-17

6-7    Typical Blower  Treatment Facility	6-20

6-8    Gas Col lection/Recovery System	6-29

7-1    Typical Backhoe	7-3

7-2    Hoe Digging Ranges	7-5

7-3    A Dragline	7-7

7-4    Site Operational Layout	7-18

7-5    Picillo Hazardous Waste Site Layout (Western Trench) 	   7-19

7-6    Schematic Diagram of Two Double Liner Designs for Landfills.  .  .   7-31

8-1    Clamshell Dredge 	   8-3

8-2    Open and Closed Positions of the Watertight Bucket	    8-3

8-3    Dragline Bucket on Track-Mounted Crane  	   8-5

8-4    Bucket Ladder	8-7

8-5    Plain Suction Dredge 	   8-8

8-6    Cutterhead Dredge	8-10
                                      xv

-------
                          LIST OF FIGURES (Continued)


8-7    Dustpan Dredge	8-12

8-8    Hopper Dredge	8-12

8-9    Portable Hydraulic Dredge	8-14

8-10   Diver-Operated Hand-Held Dredges 	  8-16

8-11   Pneuma Dredge	8-19

8-12   Streamflow Diversion for Sediment Excavation Using Two
       Cofferedams and Diversion Channel	8-23

8-13   Streamflow Diversion for Sediment Excavation Using
       Single Cofferdam 	  8-24

8-14   Construction of a Typical Silt Curtain Section 	  8-29

8-15   Typical Silt Curtain Development Configurations	8-30

8-16   Overview of Dredged Material Management	8-44

8-17   Submerged Diffuser System, Including the Diffuser and
       Discharge Barge	8-53

8-18   Fixation by Deep Chemical Mixing	8-57

9-1    Typical Groundwater Temperatures (ฐF) at 100 Ft. Depth
       in the United States	9-10

9-2    Configuration of Static Mixer	9-18

9-3    Possible Configuration of In-Situ Aeration Well Bank  	  9-20

9-4    Simplified View of Groundwater Bioreclamation	9-26

9-5    Plan View of Extraction/Injection System Used at
       an Air Force Site	9-28

9-6    Configuration of Reinjection  Trenches	9-29

9-7    Installation of a Permeable Treatment Bed	9-57

9-8    Economic Overview of Ground Freezing for a
       Hypothetical Site	9-64

10-1   Two-Vessel Granular Carbon Adsorption System  	  10-4

10-2   Typical Filtration Bed	10-19
                                      xvi

-------
                          LIST OF FIGURES (Continued)


10-3   Cost of Effluent Filtration	10-22

10-4   Representative Configuration Employing Precipitation,
       Flocculation ,  and Sedimentation	10-24

10-5   Solubility of Metal Hydroxides and Sulfides	10-25

10-6   40 GPM Sulfex Plant for Combined Removal of
         Cr+6, Zn, Cu, Cd, Ni and Fe	10-28

10-7   Polymer Addition Costs 	  10-32

10-8   Representative Types of Sedimentation	  10-33

10-9   Cost of Chemical Clarification with Alum	10-35

10-10  Pertinent Features of Ion Exchange Systems 	  10-38

10-11  Membrane Module Configurations 	  10-43

10-12  Air Stripping  Equipment Configurations 	  10-49

10-13  Typical Vibrating Screen 	  10-60

10-14  Wedge Bar Screen	10-62

10-15  Hydraulic Classifer	10-64

10-16  Spiral Classifer 	  10-67

10-17  Typical Cyclone	10-69

10-18  Conceptual Diagram of a Dredged Materiaal Containment Area .  .  .  10-73

10-19  Circular Clarifer	10-74

10-20  High Rate Gravity Settler/Thickener	10-76

10-21  Gravity Thickener	10-78

10-22  Gravity Thickening Construction Costs, 1975	10-79

10-23  Schematic of Typical Solid Bowl Decanter Centrifuge	10-83

10-24  General Schematic of Imperforate Basket Centrifuge 	  10-84

10-25  Schematic of a Disc Nozzle Centrifuge	10-85

10-26  Construction Cost for Basket Centrifuge	10-88
                                     xvn

-------
                          LIST OF FIGURES (Continued)
10-27  Basket Centrifuges - Building Energy, Process Energy
         and Maintenance Material Requirements	10-89

10-28  Basket Centrifuges - Labor and Total Annual Operation
         and Maintenance Cost	10-89

10-29  High G Solid Bowl Centrifuges - Labor and Total Annual
         Operation and Maintenance Cost	  10-90

10-30  High G Solid Bowl Centrifuges - Building Energy Process
         Energy and Maintenance Material Requirements 	  10-92

10-31  High G Solid Bowl Centrifuges - Labor and Total Annual
         Operation and Maintenance Cost	10-92

10-32  The Three Basic Stages of a Belt Press	10-93

10-33  Rotary Vacuum Filter  	  10-94

10-34  Filter Press (illustrative Cross-Sectional View of One
         Rectangular Chamber) 	  10-95

10-35  Construction Cost for Diaphragm Filter Press 	  10-98

10-36  Diaphragm Filter Press - Labor and Total Annual Operation
         and Maintenance Cost	10-99

10-37  Diaphragm Filter Press - Building Energy, Process Energy and
         Maintenance Material Requirements	10-99

10-38  Belt Filter Press - Labor and Total Annual Operation
         and Maintenance Cost 	  10-100

10-39  Belt Filter Press - Labor and Total Annual Operation
         and Maintenance Cost 	  10-102

10-40  Belt Filter Press - Building Energy, Process Energy
         Maintenance Material Requirements	10-102

10-41  Construction Cost for Vacuum filters  	  10-103

10-42  Vacuum Filters - Labor and Total Annual Operation and
       Maintenance Cost  	  10-103

10-43  Vacuum Filters - Building Energy, Process Energy and
       Maintenance Material  Requirements	  10-104

10-44  Purchase Costs of Elevated Flares	10-119
                                     XVlll

-------
                          LIST OF FIGURES (Continued)


10-45  Natural Gas Requirements for Elevated Flares  	  10-120

10-46  Liquid Injection Incineration System 	  10-125

10-47  Typical Rotary Kiln Furnace	10-127

10-48  Multiple Hearth Incinerator	10-128

10-49  Fluidized Bed Incineration 	  10-130

10-50  Molten Salt Destruction Simplified Flow Schematic	10-132

10-51  Flowsheet of Wet Air Oxidation	10-134

10-52  Plasma Reaction Vessel Schematic 	  10-134

10-53  Circulating Bed Combuster	10-136

10-54  Cross-section of a Typical High-Temperature Fluid
       Wall Reactor 	  10-136

10-55  General Estimates of Costs for Three Prevalent Types
       of Incinerators	10-139

11-1   Power Rodding Machine	11-19

11-2   Schematic of Bucket Machine Cleaning 	  11-20

11-3   Sewer Sliplining Methods 	  11-24

11-4   Typical Arrangement for Applying Chemical Grout to
       Small Diameter Pipe	11-26

11-5   Typical Arrangement for Sealing Large Diameter Pipe
       with Grouting Rings	11-26

11-6   Inversion Lining Installation Procedure	11-28
                                      xix

-------
                                LIST OF TABLES


TABLES                                                                    PAGE


1-1    Guidance Documents and Manuals Related to Remedial
       Actions at Uncontrolled Waste Sites                               1-4

2-1    Waste Characteristics That May Affect Remedial Technology
       Selection                                                         2-7

3-1    Summary of Surface Water Controls                                 3-3

3-2    1985 Unit Costs Associated with Capping Disposal Sites            3-12

3-3    Cover Material Handling Characteristics of Landfill Equipment     3-23

3-4    1985 Unit Costs Associated with Grading Covered Disposal Sites    3-25

3-5    Important Characteristics of Grasses and Legumes                  3-27

3-6    1985 Unit Costs Associated with Revegetation of Covered           3-33
       Disposal Sites

3-7    Typical Design Criteria for Swales, Channels and Waterways        3-41

3-8    Value of Manning's n for Various Channel Surface Materials        3-50

3-9    Permissible Design Velocities for Stabilized Channels             3-51
       and Waterways

3-10   Bottom Widths and Maximum Drainage Areas for Temporary Chutes     3-61

3-11   Design Storage Capacity Requirements for Sedimentation Basins     3-73

3-12   Normal Duration of Surface Water Diversions and Collection        3-80
       Measures

3-13   1985 Unit Costs Associated with Surfac'e Water Diversion and       3-82
       Collection Structures

4-1    Cost and Coverage for Several Sizes of Polypropylene Spheres      4-3

4-2    Commercially Available Dust Suppressant Costs, and
       Recommended Application Rates                                     4-5

5-1    Criteria for Well Selection                                       5-7

5-2    Radius of Influence Equations                                     5-20

5-3    Methods of Well Installation                                      5-33
                                      xx

-------
                          LIST OF TABLES (Continued)


5-4    1984 Costs for Selected Pumps and Accessories                     5-42

5-5    1985 Costs for Wellscreens and Wellpoints                         5-43

5-6    1985 Drilling Costs for Unconsolidated Materials and              5-44
       Installing 2- to 4- Inch Diameter Wells

5-7    Summary of Seven Recovery System Cost Scenarios ($1985)           5-46

5-8    Drain Grades for Selected Critical Velocities                     5-61

5-9    Approximate Hourly Production in Cubic Yards for Ladder and       5-68
       Wheel Trenchers Operating at 100 Percent Efficiency

5-10   1985 Unit Cost for Trench Excavation and Associated Activities    5-75

5-11   1985 Costs for Pipe Installation                                  5-79

5-12   1985 Installed Costs for Manholes                                 5-81

5-13   Capital Costs ($1985) for Interceptor Drain Installation -        5-82
       Site A

5-14   Soil Bentonite Permeability Increases Due to Leaching with        5-88
       Various Pollutants

5-15   Relation of Slurry Cut-off Wall Costs Per Square Foot as a        5-93
       Function of Medium and Depth

5-16   Typical Composition of Cement Bentonite Slurries                  5-96

5-17   Approximate Costs of Common Grouts                                5-104

6-1    1985 Unit Costs for Components of Passive Landfill Gas
       Control Systems                                                   6-14

6-2    Materials and Equipment for Active Landfill Gas Control
       Systems                                                           6-22

6-3    1985 Unit Costs for Components of Active Landfill Gas             6-25
       Control and Collection Systems

7-1    Maximum Reach and Depth for Various Sized Hoes                    7-4

7-2    Typical Dragline Excavator Dimension                              7-18

7-3    Excavation/Removal Equipment Capabilities and Limitations         7-22

7-4    Potential Analytical Requirements for Disposal                    7-28
                                      xxi

-------
                          LIST OF TABLES (Continued)


7-5    Summary of Adverse Site Conditions Affecting Liner Performance    7-33

7-6    Characteristics, Advantages, and Disadvantages of Selected        7-35
       Synthetic Liners

8-1    Comparison of Dredge Equipment to Selection Criteria              8-32

8-2    Comparison of Dredge Equipment to Applicability to
       Waste Site Conditions                                             8-35

8-3    Unit Costs for Mechanical Dredging/Excavation                     8-37

8-4    1985 Hydraulic Dredge Unit Costs                                  8-41

8-5    Cost Estimate Waukegan Harbor Slip Dredge -
       Dewater in Lagoon - Fix - Dispose                                 8-46

8-6    Order of Magnitude Cost Estimate (1983) for Dredged
       Material Handling Waukegan Harbor                                 8-60

9-1    BOD../COD Ratios for Various Organic Compounds                     9-4

9-2    Summary of Organic Groups Subject to Biodegradation               9-5

9-3    Problem Concentrations of Selected Chemicals                      9-11

9-4    Site Reclamation Using Biodegradation, Indigenous
       Microorganisms                                                    9-12

9-5    Examples of Biological Renovation at Contaminated Sites           9-16

9-6    Oxygen Supply Alternatives                                        9-17

9-7    Composition of Basal Salts                                        9-24

9-8    Basal Salts Medium Used by CDS, Inc.                              9-24

9-9    Recommended Parameters to Monitor                                 9-32

9-10   Chemical Costs                                                    9-37

9-11   Summary of Project Costs - Biocraft Laboratories, Waldwick, NJ    9'-38

9-12   Estimated Costs for Hypothetical Bioreclatnations Using Hydrogen   9-39
       Peroxide as an Oxygen  Source

9-13   Summary of In-Situ Chemical Treatment Methods for Organics        9-41

9-14   Summary of In-Situ Treatment Methods for Inorganics               9-43
                                     xxn

-------
                          LIST OF TABLES (Continued)


9-15   Site and Soil Characteristics Identified as Important in         9-44
       In-Situ Treatment

9-16   Surfactant Characteristics                                       9-48

9-17   Waste Chemical Classes Ability to React with Hydrogen Peroxide   9-54

9-18   Unit Costs for Installation of a Permeable Treatment Bed         9-60

9-19   Cost Estimates for Five In-Situ Vitrification Large-Scale
       Configuration                                                    9-63

10-1   Factors Affecting Equilibrium Adsorbability                      10-5

10-2   Carbon Influent and Effluent                                     10-6

10-3   Summary of Applications/Limitations for Biological
       Treatment Process                                                10-9

10-4   Concentration of Pollutants that Make Prebiological
       or Primary Treatments Desirable                                  10-13

10-5   Results of Pilot Scale Testing of a Reverse Osmosis Unit         10-14

10-6   General Cost Data for Various Sizes of Activated
       Carbon Contact Units                                             10-16

10-7   General Cost Data for Various Sizes of Activated
       Sludge Treatment Units                                           10-18

10-8   General Cost Data for Various Sizes of Neutralization,
       Precipitation, and Filtration Units                              10-23

10-9   Capital Costs for Sulfex Heavy Metal Precipitation System        10-29

10-10  Comparison of Chemical Costs of Hydroxide and
       Sulfide Precipitation Processes                                  10-30

10-11  General Cost Data for Various Sizes of Exchange Units            10-39

10-12  Results of Pilot Scale Testing of a Reverse Osmosis Unit         10-41

10-13  General Cost Data for Various Sizes of Reverse
       Osmosis Units                                                    10-45

10-14  Air Stripping Cost Estimates                                     10-53

10-15  Appropriate Particle Sizes for Various Soil Categories           10-58
                                     xxi 11

-------
                          LIST OF TABLES (Continued)


10-16  1985 Capital and Operating Costs for Portable Filter Press       10-105

10-17  Summary Comparison of Relative 1985 Cost of
       Stabilization/Solidification Alternatives                        10-112

10-18  Incineration Technologies                                        10-124

10-19  Estimated Capital Cost for a Rotary Kiln                         10-141

10-20  Estimation of Annual Operation and Maintenance
       Cost for a Rotary Kiln                                           10-142

10-21  Conceptual Level Capital Cost Estimates for a Liquid
       Injection System                                                 10-143

10-22  Conceptual Level Operations and Maintenance Cost
       Estimates for a Liquid Injection System                          10-143

10-23  Estimated Annual O&M Costs and Credits for a
       Liquid Injection Incinerator                                     10-142

10-24  Estimated Raw Material/Utility Requirements                      10-144

11-1   Applications and Limitations of Commonly Used Point-of-Use       11-6
       Treatment Units

11-2   1985 Costs for Point-of-Use Water Treatment Systems              11-8

11-3   1985 Costs for Replacement of Water and Sewer Lines              11-15
                                     xxiv

-------
                           ACKNOWLEDGMENTS
This document was prepared by SAIC for EPA's Office of Research and
Development in partial fulfillment of contract No. 68-03-3113, Task 7.
Clarence demons, Chief of the Environmental Assessment Staff, Center for
Environmental Research Information (CERl) was the EPA Project Officer.
Kathleen Wagner was the Task Manager for SAIC.  Other major contributors
include Kevin Boyer, Roger Claff, Mark Evans, Susan Henry, Virginia
Hodge, Shahid Mahmud, Douglas Sarno, Ellen Scopino, and Philip Spooner of
SAIC.  The direction and valuable contributions of Donald Banning,
Hazardous Waste Engineering Research Laboratory, and Paul Rogoshewski,
consultant are greatly appreciated.  Preparation of this handbook was
aided greatly by the constructive contributions of the following
reviewers:

   Douglas Ammon, USEPA, HWERL
   John Barich, USEPA, Region 10
   Robert Clemens, USEPA, OWPE
   John Gilbert, USEPA, ERT
   David Huber, USEPA, OSWER
   Donald Banning, USEPA, HWERL
   Henry R. Thacker, USEPA, ORD
   David Armentrout and M. Pat Esposito, PPEI Associate Inc.
   Stanley Carlock, US Army Corps of Engineers
   Janet Matey, Chemical Manufacturers Association
   Dale Montgomery, US Army Toxic And Hazardous Materials Agency
   Dr. Robert Pojasek, Charles T. Main, Inc.
   Richard Stanford, Clean Sites, Inc.
                                 xxv

-------
                                  SECTION  1.0

                                 INTRODUCTION
1.1  Background and Objectives


     The Comprehensive Environmental Response, Compensation,  and Liability Act
of 1980 (CERCLA) provides the U.S. Environmental Protection Agency  (EPA) with
the authority and responsibility to establish procedures  for  evaluating  re-
sponse actions, determining their appropriateness  for specific uncontrolled
waste sites, and implementing cost-effective responses.   The  plan for  enacting
these provisions appears in the (proposed) revised National Contingency  Plan
(NCP) issued in the Federal Register on February 12, 1985.  In order to  carry
out this mandate, the USEPA, Office of Research and Development (USEPA/ORD) is
involved in extensive research, development, and documentation of existing and
emerging remedial technologies.

     The first guidance document to be published by this  office on  remedial
technologies was the Handbook of Remedial Action at Waste Disposal  Sites, pub-
lished in 1982.  This document has been recognized nationwide as a  central
reference tool for understanding and planning remedial  actions.  Since 1980,
when research for the Handbook was actually completed,  there  have been numer-
ous advances in the state-of-the-art of remedial actions.  Remedial actions
have been initiated at hundreds of federally- and  industrially-financed
cleanups and these actions are providing considerable insight into  their de-
sign, reliability, effectiveness, and cost.  In addition, the EPA and  private
industry are sponsoring a great deal of research to advance the state-of-the-
art of remedial actions.  Further, the EPA has prepared numerous detailed
guidance documents which can be used in the planning and  preliminary design of
specific remedial action technologies.

     Not only have there been important technology advances over the past five
years, but there have also been significant developments  in formalizing  the
remedial action selection process.  The NCP requires that a detailed remedial
investigation (RI) and feasibility study (FS) be carried  out  for all feder-
ally-funded remedial actions in order to ensure selection of  cost-effective
remedial alternatives.  The EPA has developed detailed guidance on  carrying
out the various steps of the RI/FS process.

     In light of these recent advances in the state-of-the-art of remedial
responses, it became necessary to revise and update the Handbook so that it
may continue to be used effectively as a central reference on remedial tech-
nologies.  This document is the revised version of the original Handbook and
provides current data on remedial technologies and their  costs.

                                     1-1

-------
     The Handbook is intended to familiarize  federal,  state,  and  local  offi-
cials and private industry with the range of  remedial  technologies;  their
applications and limitations; major design and construction  considerations;
and approximate costs.  It provides sufficient information on remedial  tech-
nologies to enable the user to select potentially applicable  technologies  for
a given site, and understand what is involved in designing and  implementing
these technologies.  It also enables the user to make  an easy transition to
more detailed guidance documents and design manuals; reference  is made  to
these documents throughout the Handbook.


1.2  Organization of the Handbook


     The Handbook is organized in two parts:  Section  2 provides  an  overview
of the RI/FS process, and Sections 3 through  11 provide specific  information
on the remedial technologies.

     The remedial technologies included in the Handbook are  grouped  into one
of nine categories largely depending upon the type of  site problem they are
intended to remedy.  These categories include:

     •  Surface Water Controls (Section 3)
     •  Air Pollution Controls (Section 4)

     •  Groundwater Controls (Section 5)
     •  Gas Migration Controls (Section 6)

     •  On-Site and Off-Site Disposal of Wastes and Soil (7)
     •  Contaminated Sediment (Section 8)

     •  In-Situ Treatment Measures (Section 9)
     •  Direct Waste Treatment (Section 10)

     •  Contaminated Water and Water and Sewer Liners  (Section  11)

     Emphasis is placed on those technologies which are demonstrated for haz-
ardous waste site applications.  Many emerging technologies  are also included
but in less detail.

     The discussion of each established technology or  group  of  similar  tech-
nologies is organized as  follows:

     •  General description
     •  Applications/limitations

     •  Design considerations
     •  Construction/implementation considerations

     •  Operation, maintenance and monitoring
                                      1-2

-------
     •  Technology selection/evaluation

     •  Unit costs

     The general description provides  a basic  overview  of  the  technology  and
its intended use.  Applications and  limitations  describe mainly  those  waste-
and site-specific characteristics  that favor,  preclude, or limit  use of the
technology.  For example, presence of high permeability soils  favors in-situ
treatment whereas low permeability soils  limit use  of these  technologies.
This section also addresses the status of the  technology (e.g., well devel-
oped, emerging).  The information  in this section is particularly useful  in
screening out those technologies that  are not  applicable for a specific site.

     The sections on design; construction and  implementation;  and operation,
maintenance, and monitoring are intended  to provide a basic  understanding of
the technology, the equipment and materials involved, and  the  major consider-
ations in implementing, operating  and maintaining the system.  While these
sections provide a framework for planning and  developing remedial action  al-
ternatives, they are not intended  for use in detailed design.  The information
should not be substituted for the detailed guidance and design manuals
referenced throughout the document nor for the services of a qualified design
engineer.  Table 1-1 lists the major guidance  documents which  complement  the
data presented in this handbook.

     The section on technology selection/evaluation provides A summary of the
technical suitability of the technology based  on established performance,
reliability, implementability, and safety.  It also makes  mention of any  envi-
ronmental, public health, or institutional concerns which  may  be  particularly
noteworthy.

     The final section on each technology or group  of technologies presents
unit cost data and costs for actual or hypothetic remedial actions.  The  unit
cost data has been expressed in 1984 or 1985 dollars.
                                     1-3

-------
                           TABLE 1-1.

 GUIDANCE  DOCUMENTS AND MANUALS  RELATED TO REMEDIAL ACTIONS
                  AT UNCONTROLLED WASTE SITES


Leachate Plume Management, in press.   (USEPA,  1985)

Slurry Trench Construction for Pollution Migration Control,
EPA-540/2-84-001. (Spooner,  P. et al.,  1984)

Covers for Uncontrolled Hazardous Waste Sites, EPA-540/2-85/002.   (U.S.
Army Engineer Waterways Experiment  Station,  1985)

Evaluating Cover Systems for Solid  and  Hazardous  Waste,  SW-867C,
NTIS-PB81-166340 (Lutton, R.J.,  1982)

Guide to Disposal of Chemically Stabilized and Solidified  Waste,  SW-872,
NTIS-PB81-181505.  (U.S. Army Engineer  Waterways  Experiment  Station,
1982)

Evaluation of Systems to Accelerate the Stabilization of Waste Piles  and
Deposits, in press.   (USEPA, 1985)

Review of In-Place Treatment Techniques for Contaminated Surface Soils,
EPA-540/2-84-003a.  (USEPA,  1984)

Compatibility of Grouts with Hazardous  Waste,  EPA 600/2-84-015.
(Spooner, P. et al., 1984.)

Case Studies - Remedial Response at Hazardous  Waste  Sites,
EPA-540/2-84-002a and 002b.   (USEPA,  1984)

Drum Handling Practices at Hazardous  Waste Sites, in press.   (USEPA,
1985)

Fugitive Dust Control at Hazardous Waste Sites,  in press.   (USEPA, 1985)

Guidance Manual on Overtopping Controls for Hazardous Waste  Impoundments,
in press.  (USEPA, 1985)

Guidance on Remedial Investigations Under CERCLA, EPA-540/G-85-002
(USEPA, 1985)

Guidance on Feasibility Studies Under CERCLA,  EPA-540/G-85/003 (USEPA,
1985)

Modeling Remedial Responses at Uncontrolled Hazardous Waste  Sites,
EPA-540/2-85-001.  (USEPA, 1985)

Technical Handbook for Stabilization/Solidification of Hazardous Waste,
in production.   (U.S. Army Engineer Waterways  Experiment Station, 1985)

Hazardous Waste Processing Technology,  Ann Arbor Science Publishers,
Inc., Ann Arbor, MI

The  Remedial Action Costing Procedures Manual, in press. (USEPA, 1985).


                                1-4

-------
                                   SECTION 2

                        REMEDIAL ACTION SELECTION PROCESS



2.1  Remedial Investigation/Feasibility Study Process


     Section 105 of the Comprehensive Environmental Response, Compensation,
and Liability Act (CERCLA) requires that the EPA establish procedures to
ensure that the Hazardous Substance Response Trust Fund (commonly known as
Superfund) be used as effectively as possible in responding to releases of
hazardous substances in the environment.  In accordance with Section 105 of
CERCLA, the EPA has established a process for discovering releases, evaluating
remedies, determining the appropriate extent of response, and ensuring that
remedies selected are cost-effective.  This process is commonly referred to as
the remedial investigation/feasibility study (RI/FS) process, and is outlined
in Section F of the revised National Contingency Plan (NCP).  The EPA has
developed detailed guidance on the RI/FS process in the form of two separate
guidance documents:  Guidance on Remedial Investigations under CERCLA (USEPA,
1985a), and Guidance on Feasibility Studies under CERCLA (USEPA, 1985b).

     For every site that is targeted for remedial response action under
Section 104 of CERCLA, the NCP requires that a detailed RI/FS be conducted.
The RI emphasizes data collection and site characterization.  Its purpose is
to define the nature and extent of contamination at a site to the extent
necessary to evaluate, select, and design a cost-effective remedial action.
The FS emphasizes data analysis and decision making; it uses the data from the
RI to develop response objectives and alternative remedial responses.  These
alternatives are then evaluated in terms of their engineering feasibility,
public health protection, environmental impacts, and costs.

     The remedial investigation and feasibility study are interdependent
processes and are generally performed concurrently rather than sequentially.
Figure 2-1 presents a flow chart of the RI/FS process, illustrating the major
steps and the interdependence and concurrence of tasks in the RI and the FS.
The numbers identifying the tasks (boxes) in the flow chart are keyed to the
tasks in the model statements of work for the RI and FS, and are tabulated
under the flow chart.  The interactive nature of the RI/FS process is due to
the integration of data collected during the RI and the data analysis
activities performed during the FS.
                                     2-1

-------
                                  II
                                  sฐ
                                  ฃ ฃ
                             SS ฐ ง5 i
                             -l-tl1
                             •o < 3 i 1 H
                                                I  I  I
  V)
 . w
                                                 S
                                                 tn  S
                                                 *  *
2S2
                     ui ฃ
o S
h
ปง
                                              •5

                                              I
cb

2 -
                                                              i  i
             s>
                                    2-2

-------
2.2  Remedial Action Selection Process (Feasibility Study)


     Since a primary purpose of this Handbook is to assist the user in
conducting the feasibility study, this section discusses the FS process steps
outlined in Figure 2-1 in more detail.


     2.2.1  Proposed Response Action Identification


     The first step in the FS is to identify existing site problems using
preliminary RI data (site background data, previous studies, initial RI
investigation activities) and to determine the categories of remedial
technologies (e.g., surface water controls, air pollution controls) that are
most applicable.  Figure 2-2 presents a matrix of remedial technology
categories matched with specific site problems.  This categorization of
remedial technologies corresponds to the categorization found in Sections 3
through 11 of this Handbook.  As illustrated in the matrix, more than one
technology category may be applicable at a given site.


     2.2.2  Technology Screening


     The next step in the FS process is to identify and screen potentially
applicable remedial technologies from the general remedial technology
categories selected.  Technologies are screened to eliminate those that may
prove difficult to implement, rely on unproven technologies, or may not
achieve the remedial objectives (established early in the RI/FS process)
within a reasonable time period.  This screening process focuses on
eliminating those technologies which have severe limitations for a given set
of waste- and site-specific conditions.  The screening step may also eliminate
technologies based on inherent technology limitations.  Site, waste, and
technology characteristics which are used to screen inapplicable remedial
technologies are described in more detail below:

     •  Site Characteristics.  Site data should be reviewed to identify
        conditions that may limit or promote the use of certain remedial
        technologies.   Such information is generally gathered during the RI.
        Figure 2-3 provides a comprehensive list of site characterization data
        which is necessary for screening and detailed evaluation of remedial
        technologies.   Technologies whose use is clearly precluded by site
        characteristics should be eliminated from further consideration.  For
        example, the presence of very low permeability soils would generally
        preclude the use of in-situ methods since it would be impossible to
        ensure complete mixing of treatment reagents with waste components.
        Similarly, the presence of contaminated sediments at depths below
        65 feet would  preclude the use of certain types of dredges.
                                     2-3

-------
                     FIGURE  2-2
MATRIX OF GENERAL REMEDIAL TECHNOLOGY CATEGORIES FOR
                SPECIFIC SITE PROBLEMS
Remedial Technology Categories












Site Problem
Volatilization of chemicals
into air
Hazardous particulates released
to atmosphere
Dust generation by heavy construction
or other site activities
Contaminated site run-off
Erosion of surface due to wind
or water
Surface seepage of leachate
Flood hazard or contact of surface
water body with wastes
Leachate migrating vertically or
horizontally
High water table which may result in
ground water contamination or interfere
with other remedial technologies
Precipitation infiltrating into site to
form leachate
Evidence of methane or toxic gases
migrating laterally underground
On-site waste materials in non-disposed
form: drums, lagooned waste, wastepiles
Contaminated surface water, ground water
or other aqueous or liquid waste
Contaminated soils
Toxic and/or hazardous gases which have
been collected
Contaminated stream banks and
sediments
Drinking water distribution system
contamination
Contaminated sewer lines





ซ
0

O _
i_ P)
8 c
5 .2
^ o
CD ซ
|ซ
ปซ






*
*

•
.






.




















ซ]
S
o
O v
c c
o _o
D O
= ซ
ฃ"
ซ 0)
.

.

.





























ซ
S
i
0)
CO
1
c

11
S I

ฃ 01
0 01
3ซ












.

.


.




















"5
c
O
c ป
0 E
1 -2



W CU



















.













1

* R
"O O
itj
|ซ
ffl CD
Sr
— 0
•5 a
c -a
TO C

Is





















.

.

•


.




•D
E
(0
"(5
1-
il
E *-
'•5 a
01 ffi
w w
Is
.E E

||
o o
u o




























.











1-
S"
J 0
t o

oi yi
* 01
E U)












.








.

.

•












c
o
E
ฃ o
81
5 tS

ป S
5*





















.

.

•
.

.




^_
O
0)
•o
c 	
1.1
" 0
2^
^ $
ffl "ฎ
c ฃ
c o
1ฐ
E ป
0 .=
U -I






























.

•
                         2-4

-------
             FIGURE 2-3.
    IDENTIFICATION OF DATA NEEDS
FOR VARIOUS REMEDIAL TECHNOLOGIES









REQUIRED DATA ITEMS
GENERAL SITE CONDITIONS
Accessibility
Topography
Native Vegetation
WASTE CHARACTERISTICS
Physical State
Chemical Composition
Disposal/Burial Practices
Physical/Chemical Properties
SITE GEOLOGY
Seismic History
Depth to Bedrock
Bedrock Type
Bedrock Profile
Structural Configuration
Structural Strength
Bedrock Permeability/Porosity
SOIL CHARACTERISTICS
Profiles to Bedrock
Type /Texture
Permeability/Porosity
Engineering Properties
Soil Chemistry
Erosion Potential
Contaminant Profiles
Moisture Content
GROUNDWATER CHARACTERISTICS
Natural Groundweter Chemistry
Seasonal Potentiometric Surfaces
Aquifer Profile
Aquifer Characteristics
Groundwater Velocity and Direction of Flow
Groundwater Recharge and Discharge Areas
Contaminant Profiles
Supply Well Characteristics
SURFACE WATER
Proximity of Nearest Surface Waters
Presence of Leachate Seeps
Floodplain or Coastal Storm Surge Boundaries
Stream Profiles
Surface Water Use
Drainage Area/Runoff
Local Surface Water Quality
Stream Flow Characteristics
CLIMATOLOGY
Evapotranspiration Parameters
Wind Spaed and Direction
Temperature Parameters
Precipitation
Local Air Quality
Regional Air Quality
AIR
POLLUTION
CONTROLS





o>
c
'1
<3

•
•
•

•
•
•
•

•
•



•












•






















ซ
i
I

1
s
o
o
1
0

•
•
•

•
*)
•
•










•
•

•
•
•
*


•























SURFACE WATER
CONTROLS





O>
C
'5.
&
u

•
•
•

•
•
•
•

•
*
•


•












•







•
•
•









•







?
=5
a
5

•
•
•

•
•
•


•
•
•


•


•
*
•
•

•
•



•



















•





c
o
S
f
I

•
•
•

•
•
•
•









•
•
•

*>
•
•
•


•








•
•






*>
•
•
•


1
"o
o
^
c
01
c
•- 1
O CO

•
•
•

•
*
•
•

•




•


•
•
•
•

•
•
*


•
















•


•



LEACHATE AND GROUND-
WATER CONTROLS





O)
c
1
<3

•
•
•

•
•
•
•

•
•



•












•







•
•
•






•
•

•



9
to
DO
ฃ
ฃ
c
1
s

*
•
•

•
•
•
•

•
•
•
*>
•
•
•

•
•
•
•
•
•
•
•

•
•
•
•
•
•
•
•

•
•
•

*


•




•



c
'S.
3
a.
0
5
TS
I
CD

•



•
*
•
•


•
•
•
•

•

•

•



•


•
•
•
*)
•
•
•
•

•
•
•

•


•




•



c
o
1
o
u
a
u
!.
II
W a

•



•
•
•
f)

•
*
•
•
•

•

•
•
•



•
•

•
•
•
•
•
•
•
•

•
•
•

•


•




•


                2-5

-------
FIGURE 2-3. (CONTINUED)













REQUIRED DATA ITEMS
GENERAL SITE CONDITIONS
Accessibility
Topography
Native Vegetation
WASTE CHARACTERISTICS
Physical State
Chemical Composition
Disposal/Burial Practices
Physical/Chemical Properties
SITE GEOLOGY
Seismic History
Depth to Bedrock
Bedrock Type
Bedrock Profile
Structural Configuration
Structural Strength
Bedrock Permeability/
Porosity
SOIL CHARACTERISTICS
Profiles to Bedrock
Type/Texture
Permeability/Porosity
Engineering Properties
Soil Chemistry
Erosion Potential
Contaminant Profiles
Moisture Content
GROUNDWATER
CHARACTERISTICS
Natural Groundwater
Chemistry
Seasonal Potentiometric
Surfaces
Aquifer Profile
Aquifer Characteristics
Groundwater Velocity and
Direction of Flow
Groundwater Recharge and
Discharge Areas
Contaminant Profiles
Supply Well Characteristics
SURFACE WATER
Proximity of Nearest
Surface Waters
Presence of Leachate Seeps
Floodplain or Coastal Storm
Surge Boundaries
Stream Profiles
Surface Water Use
Drainage Area/Runoff
Local Surface Water Quality
Stream Flow Characteristics
CLIMATOLOGY
Evapotranspiration
Parameters
Wind Speed and Direction
Temperature Parameters
Precipitation
Local Air Quality
Regional Air Quality
GAS
MIGRATION
CONTROLS






o>
'a
a.
3


•
•
•

•
•
•
•

•
•



•



•
•
•
•
•
•
•
•





•











•

•


•




•
•
•
•


D
O
1
O
.c
1

If
i 3
= o
5*
E



•


•
•
•
•










•
•
•

•

•
'





•











•

•


•




•
•
•
•
•





I

E
ฃ


O
0


•
•


•
•
•
*

•
•



•



•
•
•

•

•
•





•











•

•


•




•
•
•
•


WASTE
EXCAVATION AND
REMOVAL
c
o
1
UJ
0)
I-
45 5
5 o
•o E
i K
•— V
0 C
a> a


•
•
•

•
•
•



•







•
•
•
•
•
•
•
•





•





•
•



•
•

•


•





•
•
•
•

CONTAMINATED
SEDIMENT REMOVAL
AND CONTAINMENT






-
0
E
a>
cc


•



•
•
•
•











•
•
•
•

•


















•

•
•
•
•
•
•




•

•




11
c o
10
Is
s|
c -g



•



•
•
•
•










•
•
•

•
•
•


















•

•
•
•
•
•
•




•




IN-SITU
TREATMENT



c
I
i

3

C


•
•
•

•
•
•
•


•
•
•
•

•


•
•
•
•
•

•
•



•

•
•
•

•

•
•
•


•
•

•

•
•
•



•
•
•
•
•

          2-6

-------
        Waste Characteristics.  Identification of waste characteristics that
        limit the effectiveness or feasibility of the remedial technologies is
        an important part of the screening process.  Table 2-1 presents waste
        characteristics that may influence the feasibility and effectiveness
        of remedial technologies.  Techndlogies clearly limited by these waste
        characteristics should be eliminated from consideration.  Waste
        characteristics particularly affect the feasibility of in-situ
        methods, direct treatment methods, and land disposal (on- or
        off-site).

        Technology Limitations.  During the screening process, the level of
        technology development, performance record, and inherent construction,
        operation, and maintenance problems should be identified for each
        technology considered.  Technologies that are unreliable, perform
        poorly, or are not fully demonstrated may be eliminated in the
        screening process.  For example, certain grouting methods and in-situ
        methods have not been developed to a point where they can be imple-
        mented in the field without extensive research.
                                   TABLE 2-1
                      WASTE CHARACTERISTICS THAT MAY AFFECT
                         REMEDIAL TECHNOLOGY SELECTION
Quantity/concentration                 Infectiousness
Chemical composition                   Solubility
Acute toxicity                         Volatility
Persistence                            Density
Biodegradability                       Partition coefficient
Radioactivity                          Compatibility with other chemicals
Ignitability                           Treatability
Reactivity/corrosivity
     For each remedial technology or group of technologies described in
Sections 3 through 11 of this Handbook, a discussion of applications and
limitations has been included to assist the user in screening inappropriate
technologies.

     During the screening process, the user should rely on a comprehensive
list of technologies classified by their remedial category to assure that all
viable technologies are being considered.  This list should be periodically
updated to incorporate newly developed or developing technologies.
                                     2-7

-------
     2.2.3  Development of Remedial Action Alternatives


     Technologies which have passed the initial screening process can then be
combined to form overall remedial action alternatives.  These alternatives
represent a workable number of options that each appear to adequately address
all site problems.  Each alternative may consist of an individual technology
or a combination of technologies.  An example of an alternative for a ground-
water contamination problem for which removal and leachate/groundwater con-
trols are applicable may include the following:  partial removal of contami-
nated soil ("hot spots")/disposal of soil in a permitted landfill/360" slurry
wall/groundwater pumping system/leachate treatment using activated carbon/cap.

     Additional guidance on developing remedial action alternatives and
specific formulative criteria that must be met can be found in Guidance on
Feasibility Studies Under CERCLA (USEPA, 1985b).


     2.2.4  Screening and Detailed Evaluation of Remedial Action Alternatives


     Once a list of remedial action alternatives has been developed to deal
with all site problems, these alternatives undergo screening to eliminate
those which are an order of magnitude more costly than other alternatives
and/or provide inadequate public health protection or have adverse environ-
mental impacts which preclude their use.  Only alternatives that satisfy the
remedial response objectives and contribute substantially to the protection of
public health, welfare, and the environment should be considered further.

     Those alternatives remaining after the screening are then subject to
detailed evaluation.  The objective of this detailed analysis is to provide a
level of evaluation to support the selection of the most cost-effective
alternative as required by the NCP.  The NCP specifies that the EPA select the
lowest cost alternative which effectively mitigates and minimizes damages and
provides adequate protection of public health, welfare, and the environment.
In order to meet  this goal, each alternative is analyzed in terms of  the
following factors:

          •  Technical considerations

          •  Environmental concerns

          •  Public health concerns

          •  Institutional concerns

          •  Costs.
                                      2-8

-------
          2.2.4.1  Technical Considerations
     Technical suitability of an alternative is evaluated in terms of
performance, reliability, implementability, time, and safety.
               a.  Performance
     Two aspects of remedial actions determine their desirability on the basis
of performance:  effectiveness and useful life.

     Effectiveness is evaluated in terms of the ability to perform intended
functions, such as containment, diversion, removal, destruction, or treatment.
The effectiveness of alternatives should be determined either through design
specifications or by performance evaluation.

     It should be established which environmental and public health standards
and criteria are applicable at the site and the proposed alternatives should
be evaluated according to those standards.  Any specific waste or site
characteristics which could potentially impede effectiveness should be
considered.  The evaluation should also consider the effectiveness of
combinations of technologies.

     Useful life is defined as the length of time the level of effectiveness
can be maintained.  Most remedial technologies, with the exception of
destruction, deteriorate with time.  Often, deterioration can be slowed
through proper system operation and maintenance, but the technology eventually
may require replacement.  Each alternative should be evaluated in terms of the
projected service lives of its component technologies.  Resource availability
in the future life of the technology, as well as appropriateness of the tech-
nologies, must be considered in estimating the useful life of the project.


               b.  Reliability


     Two aspects of remedial technologies that provide information about
reliability are their operation and maintenance requirements and their
demonstrated reliability at similar sites.

     Operation and maintenance requirements include the frequency and
complexity of necessary operation and maintenance.  Technologies requiring,
frequent or complex operation and maintenance activities should be regarded as
less reliable than technologies requiring little or straightforward operation
and maintenance.  The availability of labor and materials to meet these
requirements should also be considered.

     Demonstrated and expected reliability is a way of measuring the risk and
effect of failure.  The engineer should evaluate whether the technologies
                                     2-9

-------
have been used effectively at similar sites; whether the combination of
technologies have been used together effectively; whether  failure of any  one
technology has an immediate impact on receptors; and whether  the alternative
has the flexibility to deal with uncontrollable changes at  the  site.


               c.  Implementability


     Another important aspect of remedial alternatives is  implementability,
which can be described as the relative ease of installation (constructability)
and the time required to achieve a given level of response.

     Constructability is determined by conditions both internal and external
to the site conditions and include such items as location  of  underground
utilities, depth to water table, heterogeneity of subsurface materials, and
location of the site (i.e., remote location vs. a congested,  urban area).  The
engineer should evaluate what measures can be taken to facilitate construction
under these conditions.  External factors which affect implementation  include
the need for special permits or agreements, equipment availability, and the
location of suitable off-site treatment or disposal facilities.

     Time has two components that should be addressed:  (1) the time it takes
to implement a remedy, and (2) the time it takes to actually  see beneficial
results.  Beneficial results are defined as the reduction  of  contaminants  to
some acceptable, pre-established level.
               d. Safety


     Each remedial alternative should be evaluated with  regard  to  safety.
This evaluation should include threats to the  safety of  nearby  communities  and
environments as well as those to workers during  implementation.  Factors  to
consider are fire, explosion, and exposure  to  hazardous  substances.


          2.2.4.2  Institutional Concerns


     The effects of Federal, State, and  local  standards  and  other  institu-
tional considerations on the implementation and  operational  timing of each
alternative should be determined.  In general, it  is expected that regulatory
programs under the Resource Conservation and Recovery  Act  (RCRA),  the Safe
Drinking Water Act (SDWA), the Federal Water Pollution Control  Act (Clean
Water Act or CWA), and the Toxic Substances Control Act  (TSCA)  will have  the
broadest applications to remedial action alternatives.
                                     2-10

-------
          2.2.4.3  Public Health Concerns


     All remedial sites should also undergo a public health evaluation,
although the form and extent of the assessment will depend on the situation.
Steps which may be included in the public health evaluation are:

          •  Baseline site evaluation - Preliminary evaluation and
             classification that all sites must undergo, i.e., current
             site conditions.

          •  Exposure assessment - Analysis of the extent and duration of
             human exposure to site contaminants in the absence of remedial
             action.

          •  Standards analysis - Comparison of projected environmental
             concentrations to appropriate ambient standards or criteria.

          •  Evaluation of alternatives - Analysis and comparison of each
             alternative in terms of its ability to remove or mitigate
             exposures of concern.


          2.2.4.^j!t Environmental Concerns


     The environmental assessment of the proposed alternatives is intended to
determine any adverse impacts of these alternatives, methods for mitigating
these impacts, and cost of mitigation.  The environmental assessment will
generally consider the following for each alternative:  (1) effects on
environmentally sensitive areas; (2) exceedance of environmental standards;
(3) short- and long-term effects, both beneficial and adverse; (4) irreversi-
ble commitments of resources; and (5) mitigative measures and their costs.
The environmental assessment should also analyze the environmental impacts in
the absence of remedial investigation.
          2.2.4.5  Costs
     The detailed analysis of costs should include estimated capital and
operation and maintenance costs.  It should also include a present worth
analysis and a sensitivity analysis which assesses the effects that variations
in specific assumptions associated with design, construction, and operation
can have on the estimated costs of an alternative.  The Remedial Action
Costing Procedures Manual (USEPA, 1985c) provides detailed procedures for
developing costs.
                                     2-11

-------
     Direct capital costs include equipment,  labor and materials necessary for
installation or construction of remedial  actions.   This includes costs for the
following (USEPA,  1985C):

     •  Construction Costs
        -  Equipment

           Labor

        -  Materials

     •  Equipment  Costs
           Installed

           Purchased
     •  Land and Site Development

           Equipment
        -  Labor

           Materials
     •  Building and Services

        -  Equipment
                                                            * '^
        -  Labor

        -  Materials
     •  Population Relocation Costs.

     Indirect Capital Costs consist of engineering costs and contingency
allowances.

     Engineering expenses, include administration and supervision, design and
development, monitoring and testing, and project and cost engineering.
Typically, engineering expenses are in the range of 7 to 15 percent of total
direct capital costs.  However, certain sites will require additional
resources for legal fees, obtaining licenses and permits, and start-up and
shake-down of equipment (USEPA, 1985C).

     Contingency allowances are added to total capital costs to account for
unforseen circumstances such as adverse weather conditions, and inadequate
site characterization which would result in increased captial costs.
Contingency allowances typically range from 15 to 25 percent of total capital
costs (USEPA, 1985C) .

     Operation and maintenance (O&M) costs are those post-construction/
installation costs necessary to ensure continued effectiveness of a remedial
action.  The following cost components are included (USEPA, 1985C):

     •  Operating Labor - wages, salaries, training, overhead, and fringe
        benefits associated with the labor needed for post-construction
        operations.


                                     2-12

-------
     •  Maintenance Materials and Labor - labor, parts, and other materials
        required to perform routine maintenance of  facilities  and equipment.

     •  Auxiliary Materials and Energy - such items as chemicals and
        electricity needed for plant operations, water and sewer service,  and
        fuel costs.

     •  Purchased Services - such items as sampling costs, laboratory  fees,
        and other professional services.

     •  Disposal - transportation and disposal of any waste materials,  such  as
        treatment plant residues, generated during  the course  of a remedial
        action.

     •  Administrative costs - administration of remedial action operation and
        maintenance not included under other categories such as labor
        overhead.

     •  Insurance, Taxes and License - liability and sudden and accidental
        insurance; real estate taxes on purchased land or right-of-way  (for
        private-lead actions); licensing fees for certain technologies; and
        permit renewal and reporting costs.

     •  Maintenance reserve and contingency costs - annual payments into
        escrow funds to cover anticipated replacement or rebuilding of
        equipment and any large unanticipated O&M costs, respectively  (for
        private  lease actions).

     •  Other Costs - Includes all other items which do not fit into any of
        the above categories.
     2.2.5  Remedial Alternative Selection
     Each of the alternatives is summarized relative to each of the criteria
described in Section 2.2.4.  This summary is generally in the form of  tables
which allow the alternatives to be compared easily so decisiormakers can
select the most appropriate alternative.
                                     2-13

-------
                                  REFERENCES
USEPA.  1985a.  Guidance on Remedial Investigations under CERCLA.  Hazardous
Waste Engineering Research Laboratory, Cincinnati, OH and Office of Emergency
and Remedial Response, Washington, DC.

USEPA.  1985b.  Guidance on Feasibility Studies Under CERCLA.  Hazardous Waste
Engineering Research Laboratory, Cincinnati, OH and Office of Emergency and
Remedial Response, Washington, DC.

USEPA.  1985c.  The Remedial Action Costing Procedures Manual.  Hazardous
Waste Engineering Research Laboratory, Cincinnati, OH and Office of Emergency
and Remedial Response, Washington, DC.
                                     2-14

-------
                                   SECTION 3

                            SURFACE WATER CONTROLS
     Surface water controls include a wide range of containment, diversion,
and collection methods which are designed to minimize contamination of surface
waters, prevent surface water infiltration, and prevent off-site transport of
surface waters which have been contaminated.

     Surface water control technologies are designed to perform one of six
basic functions (Ehrenfelder and Bass, 1983).

     •  Prevention of Run-on/Interception of Run-off:  These technologies are
        used to divert or intercept surface water.  Technologies which are
        designed to prevent or reduce run-on include:  dikes, diversion chan-
        nels, floodwalls, terraces, grading, and revegetation.  Temporary
        diversion dikes, diversion channels, and terraces are diversion mea-
        sures constructed upslope of a site to direct run-on from off site to
        a collection system or away from the site.  Terraces are used in comb-
        ination with dikes or ditches to channel water stopped by the terraces
        away from the site.

     •  Prevention of Infiltration:  The primary method for preventing infil-
        tration of on-site surface water is capping.  Grading also helps to
        minimize infiltration by maximizing the amount of water which will run
        off without causing significant erosion.  Revegetation can either
        promote or minimize infiltration.

     •  Control of Erosion:  Surface water control technologies reduce erosion
        by reducing slope length, slope steepness, or improving soil manage-
        ment.  Innterception dikes, diversion channels, and terraces can be
        used to reduce slope length.  Slope steepness is controlled by proper
        grading.

     •  Collection and Transfer of Water:  Collection and transfer technol-
        ogies serve to collect water which has been diverted away from the
        site or prevented from infiltrating, and discharge or transfer the
        collected water to storage or treatment.  Chutes (or flumes) and down-
        pipes are designed to transfer water away from diversion structures
        such as dikes or terraces to stabilized channels or outlets.  Water-
        ways can be used to intercept or divert water as well as collect and
        transfer water diverted elsewhere.  These waterways form the base of
        the surface water collection system.  They collect water from
        diversion structures, chutes, downpipes and ditches and channel it
        either to treatment or discharge.

                                     3-1

-------
     •  Storage and Discharge of Water:  Water storage and discharge tech-
        nologies include seepage basins and ditches, sedimentation basins, and
        storage ponds.  Their function will depend on the level of contamina-
        tion of the water they receive.  Seepage basins and ditches are used
        to discharge uncontaminated or treated water downgradient of the  site.
        Sedimentation basins are used to control suspended solid particles in
        surface water flow.

     •  Protection from Flooding:  Flood control dikes (or embankments) and
        floodwalls are flood protection measures constructed as perimeter
        structures surrounding a waste site to isolate the site from flood-
        waters.  Embankments in areas subject to river flooding are called
        levees.  They are more expensive than run-off dikes or terraces and
        will usually be used only in areas where flooding is likely to be a
        problem.  Floodwalls, which are more expensive than levees, can be
        used at sites with insufficient land area to construct a levee.
        Lagoon covers are synthetic liners which are placed atop of impound-
        ment to prevent overtopping.

The most effective strategy for managing surface flow frequently includes a
combination of several of these water control technologies.  Table 3-1
summarizes the major surface water controls discussed in this section  and
indicates their primary function.
3.1  Capping


     3.1.1  General Description


     Capping is a process used to cover buried waste materials to prevent
their contact with the land surface and groundwater.  The designs of modern
caps usually conform to the performance standards in 40 CFR  264.310, which
addresses RCRA landfill closure requirements.  These standards include minimum
liquid migration through the wastes, low cover maintenance requirements,
efficient site drainage, high resistance to damage by settling or subsidence,
and a permeability lower than or equal to the underlying liner system or
natural soils.  These performance standards may not always be appropriate,
particularly in instances where the cap is intended to be temporary, where
there is very low precipitation, and when the capped waste is not leached by
infiltrating rainwater.

     There are a variety of cap designs and capping materials available.  Most
cap designs are multi-layered to conform with the above-mentioned design  stan-
dards, however, single-layered designs are also used for special purposes.
The selection of capping materials and a cap design is influenced by specific
factors such as local availability and costs of cover materials, desired
functions of cover materials, the nature of the wastes being covered, local
climate and hydrogeology, and projected future use of the site in question.
                                     3-2

-------


























CO
,J
o
en
H
2!
O
O
CtJ
U
. H
-H <
1 IS
fi
W 0
j rf*4
1— 1 ^4
ซ to
< ai
H D
co
to
O

>*
PC
^3
Jg
S
^
en


















































c
o
•r*
4J
U
C
3
In
>,
hi
CO
e
• H
hi
CL.





























hi
0)
4J
S
01
60
hi
CO
ฃ
U
CO
Q
c
O 60
•~* C
O E *O
0) O O
u hi O
O M-* ^4
b fc.
0-
hi
01
I4_l
U 00
u e hi
v a iv
-4 hi U
•-< H co
33
T3
C
CO




C
11 o
U -r4
3 to
T> O
01 hi
tt U





C
hi O
O CU -rt
N U
u -H CO
c e hi
01 -H 4J
> S —
hi W UJ
ix e
M
U-l
hi ซ-l
O 4J O
O. |
•u 01 C
C U 3
01 hi OS
^ ft) "*••.
01 u B
hi 6 O
P* w 1
B
5

X
60
O
t-t
0
je
u
0)
H








X X







X X









X X









XXX X X X












XX X









XXX
X XX



00
ECO
B oo B
hi C n T! T> --J 01 O T) 09
0) O (O E to C to eo X "^ C — i
> "< COSTCO -O 11 CO o " CO T)—l
O jj T! CO 0) C O. 00 u CO C CO
U COCCOjtOOJCO.rf .H J-l to CO >
60 bo " co ^i u u j: awOBeoo -o
B C C U 01 CU UU CO C 60 01 -H T) 0>O
•"< O -rf 60 09 B4J ซ)B 0)5 ซJT) BปB OIO
O- O T) 01 01 B CO hiOl UQ OuB -'-I CO o 0)i-l
a 60 eg > j: ซ)2 upa 3 o 01 co -o oa PL, > ti.
ojcohioi-Hja oi .coi cutj
UtJUOiOU H O CO CO _J
3-3

-------
     3.1.2  Applications/Limitations


     Capping is necessary whenever contaminated materials are to be buried or
left in place at a site.  In general, capping is performed when extensive
subsurface contamination at a site precludes excavation and removal of wastes
because of potential hazards and/or unrealistic costs.

     Capping is often performed together with the groundwater extraction or
containment technologies described in Section 5 to prevent, or significantly
reduce further plume development; thus reducing the time needed to complete
groundwater cleanup operations.  In addition, groundwater monitoring wells are
often used in conjunction with caps to detect any unexpected migration of the
capped wastes.  A gas collection system should always be incorporated into a
cap when wastes may generate gases (see Section 6).  Capping is also associ-
ated with surface water control technologies such as ditches, dikes and berms
because these structures are often designed to accept rainwater drainage from
the cap.  Two other surface water control technologies, grading and revegeta-
tion, are incorporated into multi-layered caps.

     The main disadvantages of capping are the need for long-term maintenance
and uncertain design life.  Any caps will need to be periodically inspected
for settlement, ponding of liquids, erosion, and naturally occurring invasion
by deep-rooted vegetation.  In addition, the groundwater monitoring wells,
often associated with^caps, need to be periodically sampled and maintained.
However, these long-term maintenance requirements usually are considerably
more economical than excavation and removal of the wastes.

     The design life of a cap is uncertain because of the uncertain life of
synthetic liner materials (if one is used in the cap), the uncertain amounts
of annual rainfall which will infiltrate natural and admixed liner materials,
and the uncertain rate of waste migration which would result from any infil-
trating rainwater.  This uncertainty may necessitate the strategic placement
of monitoring wells at a site to detect any waste migration, thus signaling
the need to replace the cap.  Caps generally have a minimum design life of
20 years when a synthetic liner is the only liquid barrier.  This period may
extend to over one hundred years when a synthetic liner is supported by a
low-permeability base; the underlying wastes are unsaturated; there is great
distance between the waste and the groundwater table; and proper maintenance
procedures are observed.  Rigid barriers such as concrete and bituminous mem-
branes are vulnerable to cracking and chemical deterioration, but the cracks
can be exposed, cleaned, and repaired (sealed with tar) with relative ease.
Concrete covers may have a design life of about 50 years, except when applied
to chemically severe or physically unstable landfill environments (Lutton,
Regan, and Jones, 1979).

     Another disadvantage to capping is the high cost of proper soil and
drainage materials in certain areas of the country.  However, these high costs
would seldom result in selection of the excavation and removal alternative on
the basis of economics.  The most probable reason for selecting against
capping at a site with extensive subsurface contamination would be an
unacceptable risk to a source of drinking water where even groundwater

                                     3-4

-------
monitoring would not offer  enough  assurance  that  severe  contamination would
not occur.   Such a  situation,  for  example, may  involve  an extremely leachable
and highly toxic contaminant.
     3.1.3  Design  Consideration


     The primary purpose  of  a  cap  is  to minimize  contact  between infiltrating
rainwater and the emplaced wastes.  There  are  two basic designs:   multilayered
and single-layered.  Of these,  the multi-layered  caps  are the  most common and
are required by the RCRA  land  disposal regulations of  40  CFR,  Subparts  K
through N.  However, a  single-layered  cap  may  be  acceptable  when a site is
being  temporarily covered; in  an area  where  evapotranspiration far exceeds
rainfall and there  is little or no groundwater; or when there  is absolute
assurance that the  integrity of such  a cap will be continually maintained.  It
should be noted that a  gas collection  system should always be  included  in the
design of a cover when  there is any indication that the underlying wastes may
generate gas.  The  design considerations of  the multi-layered  and single-
layered caps are discussed separately  below.


          3.1.3.1   Multi-layered Caps


     The design of  multi-layered caps  generally conforms  to  EPA's guidance
under RCRA which recommends  a  three-layered  system consisting  of an upper
vegetative layer, underlain  by a drainage  layer over  a low permeability layer
(USEPA, 1982).  Figure  3-1 provides an example of a multi-layered cap.   The
vegetative layer in Figure 3-1  is  served by  the topsoil layer; the drainage
layer  is composed of sand; and  the low permeability layer is formed by  the
combined synthetic  and  soil  liner  system.  The cap functions by diverting
infiltrating liquids from the  vegetative layer through the drainage layer and
away from the underlying  waste  materials.

     The low permeability layer of the multi-layered  cap  can be composed of
natural soils, admixed  soils,  a synthetic  liner,  or any combination of  these
materials.  However, a  synthetic liner overlying  at least 2  feet  of low perme-
ability natural soil or soil admix is  recommended because the  synthetic liner
allows virtually no liquid penetration for a minimum of 20 years,  while the
soil layer provides assurance  of continued protection  even if  the synthetic
liner fails.

  _7 Standard design practices  specify permeabilities  of  less  than or equal to
10   cm/sec for the soil  liner  (Cope et al., 1984).  This specification would
require a natural soil  in the  CL/CH range  of the  Unified  Soil  Classification
System (USCS) (not  less than 50 percent by weight  passing a  No.  200 sieve);
however, blending of different  on-site soil  types  can  broaden  the grain size
distribution of a soil and minimizes its infiltration  capacity.   Well-graded
soils are less permeable  than  those with a small  range of grain sizes,  and
mixing of local coarse and fine-grained soils  is  a cost-effective method of
creating stronger and less porous cover soil (Lutton,  Regan, and  Jones,  1979).

                                     3-5

-------
     FIGURE 3-1.

   MULTIMEDIA CAP
               2% minimum slope


        *   *   JL   *      H  ซ   *
               W7
YAW//   VKNW    WAv>0
      TOPSOIL
                 -FILTER FABRIC
'.'••;'.•.'.;':'-'.  : -. • •  :'' SAND '•


:20 'MIL SYNTHETIC
               '•_'.: y_-  •/'.'•: '.'.'.


                 - • :  \ '.  . j . ' / . •'. • •.
       WASTE
        3-6

-------
When sufficient fine grained soils are not available  to  achieve  the  desired
permeability, clay material can be brought in.  Bentonite,  a  natural clay with
high swelling properties, is often transported  to a site  and  mixed with
on-site soil and water to produce the low permeability  layer  of  the  cap.
Blending can often be accomplished in place using a blade or  harrow  to turn
and mix the soil to suitable depths (Lutton, Regan, and  Jones, 1979).

     Chemical stabilizers and cements can be added to relatively small amounts
of on-site soils to create stronger and  less permeable  surface sealants.
Portland cement or bitumen (emulsified asphalt  or tar)  is suitable  for mixing
with sandy soils to stabilize and waterproof them.  Site-specific mixing,
spreading, and compacting procedures are required.  For  a soil-cement, approx-
imately 8 percent (by weight) dry cement is blended into  the  soil with a
rotary hoe or tiller as water is added.  Intermittent sprinkling over several
days may be required before compaction and solidification are achieved
(Lutton, Regan, and Jones, 1979).

     Soils may also be treated with lime, fly ash, bottom ash, and  furnace
slag, however, these materials should be tested for hazardous metals and
organics prior to use.  These materials  contribute pozzolanic (cementing)
properties to the resulting mixture, optimize the grain  size  distribution,  and
reduce shrink/swell behavior.  Lime applied as  2 to 8 percent (by weight)
calcium oxide or hydroxide is suitable for cementing  clayey soils.   Sands and
gravels are more suitable for combined lime-fly ash treatment than  are finer-
grained soils (Lutton, Regan, and Jones, 1979).  Rotary  tiller mixing followed
by water addition and compaction is the  general application sequence for  these
mixtures.  If a synthetic liner is present, liner life may  be prolonged by
lime addition to supporting soil (Fields and Lindsay, 1975).  Other  soil
additives include chemical dispersants and swell reducers.  Soluble  salts such
as sodium chloride, tetrasodium pyrophosphate,  and sodium polyphosphate are
added primarily to fine-grained soils with clay minerals  to deflocculate  the
soils, increase their density, reduce permeability, and  facilitate  compaction.
Additives are more effective with montmorillonite clay  than with kaolinite  or
illite.

     Flexible synthetic membranes are made of polyvinyl  chloride (PVC), chlor-
inated polyethylene (CPE), ethylene propylene rubber, butyl rubber,  Hypalonฎ
and neoprene (synthetic rubbers), and elasticized polyolefin.  Synthetic
liners are generally more expensive and  labor-intensive  sealing  materials that
require special field installation methods.  Thin sheets  are  available in
sections of variable width and the sheets are overlain and  spliced  in the
field (according to manufacturer's specifications).   Special  adhesives and
sealants are used to ensure liner integrity.  The chemical  resistance of  a  cap
synthetic liner is not usually critical.  However, the potential  for organic
and/or corrosive vapors should be carefully evaluated before  dismissing the
resistance factor.  The thickness and flexibility of  a cap  synthetic liner  are
crucial and should be carefully researched during the material selection
process.  Cope et al. (1984) and Matrecon, Inc. (1983) describe  several
important considerations for selecting synthetic liners.  The slope  of the  low
permeability layer should be between 3 and 5 percent  to  prevent  erosion (if
the upper synthetic layer fails) and pooling of rainwater.  The  underlying
base of this layer should consist of fine to medium grade fill which will

                                     3-7

-------
support the weight of the entire cap and not  abrade  the  liner.   If  a  clay or
similarly fine grained soil liner is to be used, the underlying  base  must be
sufficiently fine to preclude piping of the liner.   Piping  occurs when
sections of an overlying fine-grained soil layer erode and  fall  into  an  under-
lying coarser grained soil layer (Matrecon, Inc.,  1983).  Piping may  be  pre-
vented by placement of a suitably fine-meshed  filter fabric between the  two
layers.

     The drainage layer of the multi-layered  cap is  placed  directly above the
low permeability layer.  The permeability of  the drainage layer  should be
sufficiently high that it minimizes contact of  infiltrating rainwater with the
low permeability layer (Lutton, 1982).  Current designs  generally specify a
material with greater than or equal to 10   cm/sec permeability  (Cope et al.,
1984).  This layer can be composed of a sand  in the  SW or SP  range  of USCS
(less than 5 percent passing through a number  100  sieve) or a coarser mate-
rial.  The thickness of the drainage layer depends on the amount of settling
expected and the maximum volume of water that  could  enter it.  The  vegetative
layer of the multi-layer cap is placed above  the drainage layer, usually with
a layer of filter fabric in between to prevent  piping.   The vegetative layer
usually exceeds 2 feet in thickness, but may be greater  depending on  the frost
depth, the maximum depth of root penetration,  and  the rate  of anticipated soil
loss.  The frost depth must not be allowed to  reach  the  low permeability layer
because freezing and thawing cycles could greatly  increase  its permeability.
The selection of a vegetative cover should include consideration of root pene-
tration, erosion potential, and competitive advantage over  other plant species
in the area.  These factors can be determined by consulting with local botany
professors.  Erosion potential of the soil, however  can  occur even  when  the
vegetative cover has good soil retaining capabilities.   Therefore,  it is
recommended that the soil in the vegetative layer  have an erosion rate of less
than 2 tons per acre, per year, using the U.S.  Department of  Agriculture
Universal Soil Loss Equation (USLE).  This equation  is written:

               A = RxKxLxSxCxP

Where:                        A = average spoil loss in  tons/acre for time
                                  period used  for  R

          quantitative:       R = rainfall and  run-off erosivity index
                              K = soil erodibility factor
                              L = slope length  factor
                              S = slope steepness  factor

          qualitative:        C = cover/management factor
                              P = supporting  practices factor

Directions for determining variables are given  in  Lutton, Regan, and  Jones
(1979) pp. 127-133,  For information regarding  soil  sampling  and testing, for
local data on soils and climate, or for any form of  technical assistance
regarding selection of cover materials, regional and county Soil Conservation
Services (SCS) offices should be consulted.
                                      3-8

-------
          3.1.3.2  Single-Layered  Caps


     Single-layered caps  can be  constructed  of  any  of  the  low permeability
materials mentioned above.  However, natural  soil and  admixes  are  not  recom-
mended because they are disrupted  by freeze/thaw cycles  and  exposure  to  drying
causes them to shrink and crack  (Matrecon, Inc., 1983).  The most  effective
single layer caps are composed of  concrete and  or bituminous  asphalt.  The
thickness of these liners is dependent on the amount of  anticipated  settlement
and the local weather conditions.   Periodic  application  of special surface
treatments for asphalt and concrete liners can  greatly improve their  life  and
effectiveness.  It should be noted that  single  layered caps  will not  usually
be acceptable unless there are extreme circumstances.  For example,  an asphalt
cap that can be inspected on a frequent  basis may be acceptable.   Similarly,  a
temporary cap constructed of clay  or natural  soil may  be used,  depending on
the length of time before a final  remedial response is completed.  Another
potential opportunity to use a single-layered cap may  arise  in an  area where
evapotranspiration greatly exceeds precipitation and/or  there  is a great
distance between the waste and the nearest source of usable  groundwater.   In
these cases it may be acceptable to use  an extremely low permeability  soil or
admix buried by natural soils beneath the frost  penetration  depth.   The  over-
lying soils would also protect the cap from  drying  and cracking.


     3.1.4  Construction/Implementation  Considerations


     This section discusses construction considerations  for  multi-layered
caps.  Construction considerations for single-layered  caps vary depending  on
the cap materials used (e.g., concrete,  asphalt, clay),  therefore, appropriate
construction guidance should be  acquired according  to  the  cap  material being
considered.  The EPA document entitled Lining of Waste Impoundment and
Disposal Facilities (Matrecon, Inc., 1983) contains referencesfor construct-
ing caps out of several different  materials.

     The first layer of a multi-layered  cap  is  the  foundation  layer.   It
should be composed of soil materials that are structurally capable of  support-
ing the weight of the cap.  Tests  that may be used  in  evaluating this  layer
include unconfined compressive strength  tests (ASTM D2166),  triaxial compres-
sion tests (D2850), direct shear tests (ASTM D-3080), and grain size  analyses
(ASTM D421, D422, and D1140). The  foundation material  should be spread over
the wastes in 6-inch lifts and compacted to  its maximum  achievable density
(ASTM D698 and D1557).  The structural stability tests mentioned above should
be run on each lift in sufficient  number to assure uniformity.  The  final
shape of this layer should be the  same as the final design shape.  If  the
foundation layer is also intended  to be  the bedding layer  for  the  overlying
low permeability layer, it should  meet grain  size specifications contained in
Evaluating Cover Systems for Solid and Hazardous Waste (Lutton, 1982).
Otherwise, an appropriately sized  filter fabric  should be  used  between the
foundation and low permeability  layers.
                                     3-9

-------
     The low permeability layer should be placed in 6-inch lifts  and
compacted with a bulldozer, a sheepsfoot roller, or other heavy equipment  to
over 90 percent of its dry density at its optimum water content as  determined
by ASTM D1557 or another suitable test method  (Ehrenfelder and Bass,  1983).
Permeability should be measured at the completion of each lift at a rate of at
least 2 tests per acre.  Compaction can be accomplished with  a bulldozer or a
sheepsfoot roller.  Permeability and density tests will determine the minimum
weight of the compaction equipment and the number of passes needed.   The
selection of materials for the low permeability layer should  consider all  of
the structural stability tests mentioned above and the Atterberg  limits tests
(ASTM D423, D424, D427, and D2217) (USEPA, 1983).  These limits should be  as
wide as possible to prevent future increases in permeability  due  to drying or
wetting of the cap.  The thickness of the low  permeability zone should be  at
least 2 feet, but should be increased if a lot of settling is expected in  the
underlying wastes.

     A synthetic liner should be placed and seamed according  to manufacturers
specifications.  This liner should be at least 20 mils thick  and  the material
and seams should be tested for peel adhesion (ASTM D413, Method 1 and D1876)
and shear strength (ASTM D816, Method B, modified and D882, Method  A modified)
(Cope et al., 1984).  Additional tests on the  liner should be conducted as
recommended by the liner installation company.

     The drainage layer should have a permeability of 10   cm/sec or  greater
(USEPA, 1982).  This layer should be placed in 6-inch lifts and should be  at
least 1 foot thick.  A thicker liner should be used if more than  a  few inches
of settling or subsidence is expected in the underlying waste.  If  it is
placed directly over the synthetic liner, the  drainage layer  material must be
free of sharp objects that might puncture the  liner.  Sand classified as SP by
the USCS would fulfill the liner bedding requirements.

     Filter  fabric should be placed above the  drainage layer  to prevent
clogging from the overlying vegetative layer.  This material  is generally
rolled in overlapping strips over the drainage layer in accordance  with
manufacturers specifications.  The pore size of this layer should be  large
enough to allow proper drainage, but small enough to prevent  soil migration
into the drainage layer.

     The vegetative layer should be at least 2 feet thick to  accomodate
expected root penetration, and it should be spread evenly and not overly
compacted.  The thickness of this layer should be greater than the  deepest
zone of frost penetration found in the area (USEPA, 1982).  The vegetation
should be a non-woody plant, preferably a grass, with almost  no maintenance
requirements once it is established.
     3.1.5  Operation, Maintenance, and Monitoring


     A final cap should be inspected on a regular basis  for  signs  of  erosion,
settlement, or subsidence.  It  is recommended  that  inspections  be  conducted
frequently in the first 6 months because problems are most likely  to  appear

                                     3-10

-------
during this period (Lutton, 1982).  Maintenance of  the  final  cap  should  be
limited to periodic mowing of the vegetation layer  to prevent invasion by
deep-rooted vegetation and burrowing animals.  Any  signs  of unexpected
settling or subsidence should be addressed  immediately  by removing  the
overburden to inspect and repair the affected areas.


     3.1.6  Technology Selection/Evaluation


     Capping is a reliable technology  for sealing off contamination from the
aboveground environment and significantly reducing  underground migration of
wastes.  Caps can be constructed over virtually any site,  and can be  completed
relatively quickly if the ground is not  frozen or saturated.   Most  of the soil
materials for capping are readily available in most areas of  the  country, and
the synthetic materials are widely manufactured and distributed.  The equip-
ment used for implementing this technology  is mostly standard road  construc-
tion equipment, however some specialized testing equipment must be  supplied by
the liner installer or a soil testing company.

     The performance of a properly installed, multi-layered cap is  generally
excellent for the first 20 years of service.  However,  after  this time period,
the integrity of the synthetic liner becomes uncertain  and should be  inves-
tigated regularly.  Unforseen settling invasions by burrowing animals and
deep-rooted plants also contribute to  the need for  periodic monitoring and
maintenance of the cap.  In addition,  the groundwater monitoring  wells,  often
associated with caps, need to be sampled periodically and maintained. How-
ever, these long-term maintenance requirements are  usually considerably  more
economical than the alternative to a cap, which is  excavation and removal of
the wastes.
     3.1.7  Costs
     The cost of a cap depends on the type and amount  of materials  selected,
the thickness of each layer, and the area of the country.  General material
and installation costs for caps larger than 400,000  square feet  are  presented
in Table 3-2.  In a recent RCRA Part B Permit Application for  a  4-acre
hazardous waste landfill the estimated installed cost  of a multi-layered  cap
was $5.45/ft  (SAIC, 1985).  The design for this cap included  3  feet  of  top
soil overlying a 1-foot sand layer overlying 1 foot  of compacted clay
overlying a 30-mil HDPE liner overlying 2 feet of compacted  clay.  Filter
fabric was specified between the topsoil and sand drainage layer to  prevent
clogging.  Quality control testing of each layer of  the cap  were included in
the installation cost estimates.
                                     3-11

-------
                                  TABLE 3-2.
            1985 UNIT COSTS ASSOCIATED WITH CAPPING DISPOSAL SITES*
     Element
Cost
Cleaning and Grubbing
Excavation
Earthfill
berms and levees
soil liners
Backfill
Soil Import
drainage sand
drainage rock (rounded)
Soil placement
Vegetation, mulch, and hydroseed
Geotextile Fabrics
Bentonite Admix (2-9 lbs/yd3)**
Membrane Liners
Nonreinforced
30 mil PVC
30 mil CPE
30 mil Butyl/EDPM
30 mil Neoprene
100 mil HOPE
Reinforced
36 mil Hypalon (CSPER)
60 mil Hypalon (CSPER)
36 mil Hypalon
Installation, excluding earthwork
$l,100/acre
$1.60/yd3

$2.10/yd3
$3.10/yd:5
$3.10/yd3

$10.50/yd3
$10.50/yd
$1.00/yd3
$l,100/acre
$1.00 - $3.10/yd2
$0.20 - $1.10/ft2

o
$0.25 - $0.35/ftฃ
$0.35 - $0.45/ft2
$0.45 - $0.55/ft2
$0.70 - $0.80/ft
$1.10 - $1.60/ft

$0.50 - $0.60/ft2
$0.80 - $1.00/ft
$0.50 - $0.60/ft
$0.60 - $1.20/ft2

 *Based on costs for a 400,000 ft  area presented in Cope et al.,  1984, as
  updated by construction, labor, and material cost indices in Engineering
  News-Record 1983 and 1985.
**Includes mixing and placing.

  PVC = polyvinyl chloride
  CPE = chlorinated polyethylene
  EDPM = ethylene-propylene-diene-monomer
  CSPER = chlorosulfonated polyethylene (reinforced)
                                     3-12

-------
3.2  Floating Covers


     3.2.1  General Description


     Floating covers consist of a  synthetic  lining  placed  in  one piece over an
impoundment, with proper anchoring at  the  edges,  and with  floats to  prevent
the lining from submerging.  This  technology is used mainly to  cover drinking
water supply reservoirs, but it can be used  temporarily  to  prevent overtopping
of a waste lagoon prior to  final closure.


     3.2.2  Applications/Limitations


     Floating covers cannot be considered  as a  final remedial action at a
site, but they can be more  cost effective  than  pumpdown  and treatment to
prevent overtopping of lagoon wastes.  Covers are especially  advantageous when
a year or more will elapse  before  final  closure of  the lagoon.   Floating
covers shold not be considered on  lagoons  with  weak berms  or  those located in
areas that cannot support the weight of  heavy construction  equipment.   Also,
available cover materials may not  always be  compatable with the lagoon wastes.


     3.2.3  Design Considerations


     There are two basic floating  cover  designs.  One design  is based
primarily on a rainwater collection sump which  forms around the .perimeter of
the cover during rain events (Dial, Habegger, and Kays,  1979).   Rainwater is
directed toward this sump by various configurations of foam floats that are
inserted and sealed into special pockets in  the cover.   The most common float
configuration consists of one large center float  with smaller laterial floats
attached perpendicularly at about  36-foot  centers (Figure  3-2).   After the
sump at the perimeter of the cover fills with water, it  is  drained either by
random pumping with a portable pump, or  by installing a  flexible perforated
hose in the area of the fold that  is formed  by  the  collected  water (Kays,
W.B. Globe Linings, Inc., Long Beach, CA, personal  communication,  1984).

     The other design consists of channels in the middle of the cover created
by strings of segmented sand-filled tubes which are held at a constant depth
by floats on either side of the channel  (Burke  et al., 1976).   The sand-filled
tubes are connected in parallel to flexible  perforated collection tubes above
and to the cover underneath.  Rainwater, after  striking  the cover, drains
through openings in the floats which line  the collection channels, and is
pumped off the cover through the collection  tubes (Figure  3-3).   The
dimensions for each component of the system  are determined  through a few
simple equations that are based on the dimensions of the area to be  covered
(Brown, S., Burke Rubber Co., San Jose,  CA,  personal communication,  1983).
                                     3-13

-------
                          FIGURE 3-2.
SCHEMATIC PLAN AND CROSS-SECTION OF A FLOATING COVER
        INCORPORATING THE PATENTED BURKE DESIGN
                    r
                    L
                                                             Creases m Cover
                                                             Material Formed by
                                                             Rainwater in Sump
                                                            . Perimeter Sump
                            Floatation
                             Devices
 Direction
of Drainage
                               3-14

-------
                               FIGURE 3-3.
         SCHEMATIC PLAN AND CROSS-SECTION OF A FLOATING
         COVER INCORPORATING THE PATENTED BURKE DESIGN
   AMntof
    COM*
  A tt9C niH^Hf
Omnig* ArtM
          Plotting
           Covw
          MlttnK
                                              4-— FtaiMt Collection HOM
                                                  Scnd-FillM Wปighi
                                 3-15

-------
     The synthetic lining material  for  constructing  a floating  cover usually
consists of 36-mil or 45-mil thick, reinforced Hypalonฎ,  chlorinated
polyethylene (CPE), or XR-5.  Ethylene-propylene-diene-monomer  (EPDM)  and
butyl rubber are not often used because of  their  tendancy toward  cracking and
their low field seaming quality.  The chemical resistance of  various lining
materials is determined on a case-by-case basis through  immersion testing (see
Section 3.2.4).

     If gases are expected to be  a  problem  at a waste lagoon, a gas  collection
system can be included in the cover design.  The  gas  collection system con-
sists of several air chambers formed at various points along  the  cover
floatation system (Figure 3-4).   Each chamber is  covered  by the floating cover
material and is equiped with openings which allow gases  to flow up into the
chamber from a triangular-shaped  space  formed between the cover,  the covered
liquid, and the side of the float.  The upper end of  the  air  chamber is
connected to a short standpipe and  then to  a manifold pipe to allow pumping
and collection of gases (Kays, 1976).


     3.2.4  Construction/Implementation Considerations


     Sections of cover materials  are shipped to the  site  on large wooden
pallets.  All pockets for insertion of  floatation devices are generally made
at the fabrication plant prior to shipment.  Once at  the  site,  each  pallet is
placed as near as possible to where that  section  of  cover will  be seamed into
place.  Cover materials are accordian-folded along their  length and  width for
easy deployment.  If the area to  be covered is 20,000 square  feet or less, and
Hypalonฎ is being used, only one  section  of cover is  required (Shuey,  R. ,
Palco Linings, Inc., South Plainfield, NJ,  personal  communication, 1983).

     Installation techniques vary depending on whether the area to be  covered
is full of liquid or empty.  An empty reservoir is easier to  cover because the
cover can be seamed together as it  lies on  the bottom of  the  reservoir.

     To cover a reservoir which is  not  empty, pallets of  cover  material are
prepared according to the estimated surface area  of  the bottom  of the
reservoir (Shuey, R., Palco Linings, Inc.,  South  Plainfield,  NJ,  personal
communication, 1984).  For large  reservoirs, the  first row of pallets  are
placed at intervals along the edge  of the reservoir  so that they can be easily
seamed end-to-end.  Next, cables  are attached along  the  leading edges  of the
joined cover segments so that the cover section can  be dragged  across  the
liquid.  Before dragging the entire cover section into the reservoir,  a new
set of pallets are unloaded, and  the next cover sections  are  unfolded  and
seamed onto the first.  This process continues until  all  the  cover sections
are in place.  Floats are inserted  into their pre-formed  pockets  which are
then seamed shut (Kays, W.B., Globe Linings, Inc., Long  Beach,  CA, personal
communication, 1983; Shuey, R., Palco Linings, Inc.,  South Plainfield, NJ,
personal communication, 1984).

     Anchoring for cover systems  on reservoirs  follows two basic patterns.  In
one anchoring method, a concrete  curb is  poured around the reservoir.   The

                                     3-16

-------
                               FIGURE 3-4.
             SCHEMATIC PLAN AND CROSS-SECTION OF A PATENTED
         GLOBE FLOATING COVER AND GAS COLLECTION SYSTEM DESIGN
                        :~/L:==
                                                           Pump
                                                       Flexible Gas
                                                      Collection Hose

                                                      Perimeter Sump
                                                      . Floats
_ Floating
 Cover
                                                     •Berm
Floating Cover
   i
                                        Flexible Gas
                                        Collection
                                 3-17

-------
curb has 1/2-inch diameter bolts on 12-inch centers which are fitted  into
pre-cut, reinforced holes in the cover fabric and then through holes  in metal
battens (Kays, 1977).  These battens are bolted down to produce a continuous
seal around the perimeter of the cover.  The other, less expensive, method  for
anchoring a cover begins by digging a 12-inch wide by 18-inch deep trench
around the reservoir (Shuey, R., Palco Linings, Inc., South Plainfield, NJ,
personal communication, 1984).  Next, about 40 inches of the liner are placed
into the trench so that it conforms with the sides and bottom.  The trench  is
then backfilled and compacted with heavy equipment.  On large reservoirs,
these anchor systems should be augmented with a mechanism to counteract the
effects of strong winds.  One such method is achieved by stringing cables from
the cover to the bottom of the reservoir at regular intervals (Dial,  Habegger,
and Kays, 1979).  In this design, the stress from wind is shared between the
perimeter anchor and the bottom anchor.

     The selection of floating cover material is usually based on immersion
tests performed by the cover installation company.  The actual tests  vary
depending upon the installation company, however, some standard synthetic
liner tests are described in USEPA (1983) and in Cope et al. (1984).


     3.2.5  Operation, Maintenance and Monitoring
     Floating covers should be inspected periodically  for wearing, dis-
coloration, tearing, and rainwater accumulation.  Some covers must be manually
pumped off after rain events; others have automatic pumping  systems which need
to be inspected.  Any signs of tearing or other weaknesses should be repaired
immediately upon detection.

     Accumulation of snow and ice on floating covers is not  a problem, and
attempted removal of these materials could actually damage the cover.  Stones,
sticks, leaves, and other debris, however, should not  be allowed to
accumulate.
     3.2.6  Technology Selection/Evaluation


     Floating covers should be considered whenever there  is a need  to  tempo-
rarily prevent overtopping in a waste lagoon prior to  final closure.   Although
floating covers have not been used on many waste lagoons,  there  is  strong
evidence of their potential performance  from successful applications at
hundreds of potable drinking water reservoirs.  One cover, placed over a
reservoir in Fort Saint John, British Columbia, withstood the  forces of  4  feet
of ice and -40ฐ F temperatures for 2 months (Kays, W.B.,  Globe Linings,  Inc.,
Long Beach, CA, personal communication,  1984).  Two other covers in Mobile,
Alabama have been unaffected by winds up to 150 raph (Sahol, J.R., Globe
Linings, Inc., Houston, TX, personal communication, 1983).
                                     3-18

-------
     3.2.7  Costs


     The installed costs of  floating  covers  generally range  from $2.50 to
$3.50/square foot installed  (Kays, W.B., Globe Linings,  Inc.,  Long  Beach,  CA,
personal communication, 1984).  This  cost  range  is  based on  a  liner material
cost of about $0.70/square foot for 36-mil reinforced Hypalonฎ or CPE.   If a
more chemically resistent material were required, material costs could reach
$1.50/square foot.  Additional costs  of up to $2.00/sqaure foot could  be
incurred if removal of vegetation were required  or  if difficult engineering or
site access problems were present at  the proposed site.   The incorporation of
a gas collection system into the floating  cover  will  increase  the installed
price by appoximately $1.00/square foot (Kays, W.B.,  Globe Linings,  Inc.,  Long
Beach, CA, personal communication, 1984).


3.3  Grading


     3.3.1  General Description


     Grading is the general  term for  techniques  used  to  reshape the  surface of
covered landfills in order to manage  surface water  infiltration and  run-off
while controlling erosion.   The spreading  and compaction steps used  in grading
are techniques practiced routinely at sanitary landfills.  The equipment and
methods used in grading are  essentially the  same for  all landfill surfaces,
but applications of grading  technology will vary by site.  Grading  is  often
performed in conjunction with surface sealing practices  and  revegetation as
part of an integrated landfill closure plan.


     3.3.2  Applications/Limitations


     Regrading is a relatively inexpensive remedial action component when
suitable cover materials are available on-site or close  to the disposal  site.

     The techniques and equipment used in grading operations are well  estab-
lished and are widely used in all forms of land  development.   It is  usually
possible to find contractors and equipment locally, thus expediating the work
and avoiding extra expenses.

     Surface grading serves  several functions:

     •  Reduces ponding which minimizes infiltration  and reduces subsequent
        differential settling

     •  Reduces runoff velocities to  reduce  soil erosion

     •  Roughens and loosens soils in preparation for  revegetation
                                     3-19

-------
     •  Can be a factor in reducing or eliminating leaching of wastes.

     There may, however, be certain disadvantages associated with  grading  the
surface of a given site.  Large quantities of a difficult  to obtain  cover  soil
may be required to modify existing slopes.   Suitable  sources of  cover material
may be located at great distances from the disposal site,  increasing hauling
costs.  Also, periodic regrading and  future  site maintenance may be  necessary
to eliminate depressions formed through differential  settlement  and
compaction, or to repair slopes that  have slumped or  become badly  eroded
(Tolman et al., 1978).
     3.3.3  Design Considerations
     Grading techniques modify the natural topography and run-off  characteris-
tics of waste sites to control infiltration and erosion.  This  is  accomplished
by establishing continuous surface grades to ensure that runoff water does not
pond.  The choice of specific grading techniques  for a given waste disposal
site will depend on desired site-specific functions of a graded surface.  A
graded surface may reduce or enhance infiltration and detain or promote
run-off.

     Erosion control may be considered a complicating variable  in  the design
and performance of a grading scheme.  The design  of graded  slopes  at waste
disposal sites should balance infiltration and run-off control  against
possible decreases in slope stability and increases in erosion.  The design  of
specific slope configurations, the choice of cover soil type, the  degree  of
compaction, and the types of grading equipment used will all depend on local
topography, climate, future land use of the site, and drainage  methods.

     Improperly graded slopes may deform or fail, opening cracks,  exposing
wastes, and allowing lateral seepage of leachate.  Soils used to cover graded
slopes should be selected on the basis of shear strength and erodibility
(Lutton, Regan, and Jones, 1979).  Soils high in  silt and fine  sand and low  in
clay and organic matter are generally most erodible (USEPA, 1976).  Also, the
longer and steeper the slope is, and the sparser  the vegetation cover, the
more susceptible it is to erosive forces.

     Manipulation of slope length and gradient is the most  common  grading
technique used to reduce infiltration and promote surface water runoff.   A
slope of at least 5 percent, but not greater than approximately 18 percent,  is
recommended as sufficient to promote runoff and decrease infiltration without
risking excessive erosion (Lutton, 1978).  More specifically, the  center  of
the disposal site should be the highest elevation, with top surface slopes
graded 6 to 12 percent and side slopes no steeper than 18 percent.  This
grading will enhance run-off and minimize infiltration and most soils will
remain stable on such slopes (Tolman et al., 1978).  For equal  surface areas
of land, doubling the slope length will increase  soil losses by 1.5 times
(USEPA, 1976).  Therefore, where off-site transport of contaminated soil  due
to water erosion is a major consideration, the length of graded slopes should
                                     3-20

-------
be minimized.  Minimization of slope length can be accomplished by terracing,
as discussed in Section 3.5.3.

     Grading is often accompanied by other water handling measures such as
sumps and sewers, as well as treatment systems for runoff from an uncontrolled
site.
     3.3.4  Construction Considerations
     It is important that grades be maintained as accurately as possible.
Reverse grades should not be permitted.  Also, to provide a firm subgrade and
prevent seal failure, existing cover material should be compacted to a Proctor
density of 70 to 90 percent of maximum (Tolman et al., 1978).  This can be
achieved through repeated passes of leveling equipment over the area in
several different directions.

     All states and localities publish guidelines and regulations for perfor-
mance of any grading work.  These publications should be consulted before a
grading system is designed.

     Grading methods used to roughen and loosen soils in preparation for
revegetation can be classified as scarification, tracking, and contour
furrowing.  These methods actually detain run-off and promote infiltration in
order to establish vegetation. '

     Scarification can be accomplished by harrowing along the ground contour
or by dragging the bucket teeth of a front-end loader over the ground.
Specially equipped crawler tractors can also perform scarification.  Tracking
is performed on steep slopes where movement along the contour is not feasible.
A cleated crawler tractor is run up and down the slope, leaving shallow
grooves that run parallel to the contour.  Contour terracing or furrowing is
used on long slopes in conjunction with other roughening techniques to disrupt
and slow surface runoff.  This effect is accomplished by running a bulldozer
parallel to the contour.  Dirt is allowed to dribble off the blade end,
creating small depressions that interrupt downslope surface water flow (USEPA,
1976).

     The equipment types used to construct graded slopes consist of both
standard and specialized landfill vehicles.  Excavation, hauling, spreading,
and compaction of cover materials are the major elements of a complete grading
operation.  Landfill grading vehicles include scrapers, crawler dozers and
loaders, rubber-tired dozers and loaders, and landfill compactors (Figure
3-5).  Table 3-3 summarizes the cover material handling capabilities of these
equipment types.

     Crawler tractors (dozers and loaders) are excellent landfill grading
machines (Brunner and Keller, 1972).  Dozers are fitted with U-shaped landfill
blades for pushing and spreading; loaders can be fitted with landfill blades
and multipurpose buckets for excavation and spreading.
                                     3-21

-------
                                 FIGURE 3-5.
                 GRADING VEHICLES AND ACCESSORIES
   Standard Landfill Equipment
Specialized Equipment
                        Crawler Tractor
                           Rubber-tired
                               Tractor
    Dozer Blade  VV^    Landfill Blade

Front-end Accessories
                                                                            Scraper
                                                             Steel-wheel Compactor
                                  3-22

-------
                                  TABLE  3-3.
        COVER MATERIAL HANDLING CHARACTERISTICS  OF  LANDFILL  EQUIPMENT
                                               1
                                              Rating^
Equipment
Excavating     Spreading     Compacting     Hauling
Crawler dozer
Crawler loader
Rubber-tired dozer
Rubber-tired loader
Landfill compactor
Scraper
E
E
F
F
P
G
E
G
G
G
G
E
G
G
G
G
E
NA
NA
NA
NA
NA
NA
E

1
 Assuming easily workable soil and cover material and haul distance  1,000  ft,
 >
 "Rating key:  E, excellent; G, good; F, fair; P, poor; NA, not  applicable.
 Source:  Brunner and Keller, 1972
     Rubber-tired dozers and loaders are generally  faster  and more  agile  than
crawler machines; however, they do not excavate as  well.   Rubber-tired dozers
are used infrequently at landfill sites, because they do not grade  as well  as
crawler dozers on the irregular and spongy surface  provided by  compacted
refuse (Brunner and Keller, 1972).

     Specialized landfill vehicles include compactors and  scrapers.  Steel-
wheeled landfill compactors are excellent machines  for  spreading  and com-
pacting on flat to moderate slopes.  Scrapers are effective in  excavating,
hauling, and spreading cover materials over relatively  long distances (Brunner
and Keller, 1972).
     3.3.5  Operation, Maintenance, and Monitoring
     As all fill material has the tendency to settle, periodic monitoring  of
the site is necessary.  Smoothing operations may be required  for  several years
as settling occurs.

     All seeps and ponds should be expediantly corrected.  Repeated
occurrences may indicate failure of the site cover and should be  promptly
investigated.

     It is important upon completion of grading to establish  a vegetation
cover as quickly as possible (revegetation is discussed in Section 3.4).   This
cover is essential to help prevent drying and erosion.

                                     3-23

-------
     3.3.6  Technology Selection/Evaluation


     Surface grading of covered disposal sites, when  properly  designed  and
constructed to suit individual sites, can be an economical method of  con-
trolling infiltration, diverting run-off, and minimizing  erosion.   A  properly
sealed and graded surface will aid in the reduction of  subsurface leachate
formation by minimizing infiltration and promoting erosion-free  drainage of
surface run-off.  Grading can also be used to prepare a cover  soil  capable of
supporting beneficial plant species.

     Estimated total costs for grading reported in the  cost  compendium  (USEPA,
1985) (and updated to 1985 dollars) ranged from a low of  $4150/acre to
$16,814/acre.  The lowest grading cost estimate reflected the  cost  of on-site
hauling, spreading and compacting of a one-foot thick soil layer and  a  6-inch
sand layer.  This estimate assumes the use of on-site soil.  The highest
estimate reported in the cost compendium also involved  the use of on-site soil
but included excavation and grading costs for on-site soil.  Additional costs
(30 percent) were included in these estimates to cover  overhead  and a
contingency allowance.

     1985 Operating and Maintenance costs for a graded  area  have been
estimated to include the following (USEPA, 1985):

     Item                                             Cost

Annual inspection                                 $518/year

Mowing/revegetation                               $622/year

Erosion control and drainage maintenance          $207/year

Repairs resulting from shrink/swell               $207/year
  or freeze/thaw forces

     Grading is considered essential to the continued performance and reli-
ability of a cap.  The performance and reliability of a graded surface  depends
upon effective revegetation.  Grading is easy to implement and can  generally
be performed by local contractors.  Grading rarely poses  safety  hazards to
field personnel when performned on a properly capped  site.   However,  when
grading is performed to improve site drainage at an uncontrolled site,  it may
pose a risk to worker safety where drums and explosives are  buried  near the
surface.
     3.3.7  Costs
     Unit costs associated with grading equipment and methods  are  presented  in
Table 3-4.  Costs associated with heavy equipment maintenance  (fuel,  repairs,
etc.) are not addressed.  Costs of excavation, hauling,  spreading  and  compac-
tion will vary depending on equipment type and size, type of cover material

                                     3-24

-------
                                  TABLE 3-4.
        1985 UNIT COSTS ASSOCIATED WITH GRADING COVERED DISPOSAL SITES
     Description
Unit Cost
Source
     Topsoil (sandy loam) from borrow
     pits, excavation, haulng, spread-
     ing,  and grading (within 25 miles);
     labor, materials, and equipment

     On-site excavation, hauling,
     spreading,  and compaction of
     earth (1,000-5,000 ft haul);
     labor and equipment only

     Sandy loam topsoil; material
     only

     Excavate, haul 2 miles, spread
     and compact loam, sand, or
     loose gravel (with front-end
     loader); labor,  material, and
     equipment

     Grading, site excavation, and
     fill  (no compaction);
     75 hp dozer, 300 ft haul
     300 hp dozer, 300 ft haul

     Field density compaction
     testing of  soils
$15/yd-
$2.02-3.86/yd"
$2.25/yd:
$6.65-6.72/yd-
$2.34/yd

$104/day
 McMahon,  1984
2Godfrey,  1984
                                     3-25

-------
being graded, haul distance, support labor required, and unforeseen construc-
tion difficulties.

     These costs are representative of average contractor bid  prices  for
performance of the work, and therefore include charges  for overhead and
profit.  All costs are reported in 1985 dollars.
3.4  Revegetation


     3.4.1  General Description


     The establishment of a vegetative cover is a cost-effective method  to
stabilize the surface of hazardous waste disposal sites, especially when
preceded by capping and grading.  Revegetation decreases erosion by wind and
water and contributes to the development of a naturally fertile and stable
surface environment.  Also, the technique can be used to upgrade the
appearance of disposal sites that are being considered for various re-use
options.  Short-term vegetative stabilization (i.e., on a semi-annual  or
seasonal basis) can also be used as a remedial technique for disposal  sites.

     A systematic revegetation plan will include:  (1) selection of suitable
plant species, (2) seedbed preparation, (3) seeding/planting,  (4) mulching
and/or chemical stabilization, and (5) fertilization and maintenance.


     3.4.2  Applications/Limitations


     Revegetation may be part of a long-term site reclamation  project, or it
may be used on a temporary or seasonal basis to stabilize intermediate cover
surfaces at waste disposal sites.  Revegetation may not be feasible at
disposal sites with high cover soil concentrations of phytotoxic chemicals,
unless these sites are properly sealed and vented and then recovered with
suitable topsoil.

     Grasses such as fescue and lovegrass provide a quick and  lasting  ground
cover, with dense root systems that anchor soil and enhance  infiltration.
Legumes (lespedeza, vetch, clover, etc.) store nitrogen in their roots,
enhancing soil fertility and assisting the growth of grasses.  They are  also.
readily established on steep slopes.  Shrubs such as bristly locust and  autumn
olive also provide a dense surface cover, and certain species  are quite
tolerant of acidic soils and other possible disposal site stresses.  Trees  are
generally planted in the later stages of site reclamation, after grasses and
legumes have established a stable ground cover.  They help provide long-term
protective cover and build up a stable, fertile layer of decaying leaves and
branches.  A well mixed cover of grasses, shrubs, and trees  will ultimately
restore both economic and aesthetic value to a reclaimed site, providing
suitable habitat for populations of both humans and wildlife.  Table 3-5
summarizes the suitability of various grasses and legumes for  revegetation

                                     3-26

-------
                                 TABLE 3-5.
      IMPORTANT CHARACTERISTICS OF GRASSES AND LEGUMES
   Characteristic
                     Decree
                                            Common Examples
  Texture          Fine           Kentucky bluegrass, bentgrass, red fescue

                   Coarse         Smooth bromegrass, reed canarygrass,
                                  timothy

  Grovth height     Short          Kentucky bluegrass, buffalograss,  red fescue

                   Medium         Redtop, perennial rye grass

                   Tall           Smooth bromegrass, timothy, switchgrass

  Grovth habit     Bunch          Timothy, big  bluestem, sand dropseed,
                                  perennial  ryegrass

                   Sod former     Quackgrass,  smooth bromegrass, Kentucky
                                  bluegrass,  switch* grass

  Reproduction     Seed           Red and alsike clover, sand dropseed, rye,
                                  perennial  ryegrass, field bromegrass

                   Vegetative     Prairie cordgrass, some bentgrasses

                   Seed and       White clover, crovnvetch, quackgrass,
                   vegetative     Kentucky bluegrass, smooth bromegrass

  Annual           Summer         Rabbit clover, oats, soybeans, corn,
                                  sorghum

                   Winter         Rye, hairy vetch, field bromegrass

  Perennials       Short-lived    Timothy, perennial ryegrass, red and
                                  white clover
                   Long-lived     Birdsfoot  trefoil, crovnvetch, Kentucky
                                  bluegrass,  smooth bromegrass

  Maintenance      Difficult      Tall fescue,  reed canarygrass, timothy,
                                  alfalfa

                   Moderate       Kentucky bluegrass, smooth bromegrass

                   Easy           Crovnvetch, vhite clover, birdsfoot
                                  trefoil, big bluestem

                                  Sand dropseed, crabgrass, foxtail, vhite
                                  clover

                   Strong         Timothy, Kentucky bluegrass

  Deep rooted      Weak           Many weeds

                   Strong         Big bluestem, svitchgrass, alfalfa, reed
                                  canarygrass

  Moisture         Dry            Sheep fescue, sand dropseed, smooth
                                  bromegrass
                   Moderate       Crested vheatgrass, red clover

                   Wet            Reed canarygrass, bentgrass

  Temperature      Hot            Lehman lovegrass, fourving saltbush,
                                  ryegrass

                   Moderate       Orchard grass, Kentucky bluegrass, vhite
                                  clover

                   Cold           Alfalfa, hairy vetch, smooth bromegrass,
                                  slender vheatgrass
Shallow rooted    Weak
 * Variety,  specific characteristic,  subcharacteristic, or
  favored condition.
Source: Lutton, 1982

-------
purposes.  Native species of trees and shrubs, particularly those with a
shallow root system, should generally be specified.

     The selection of suitable plant species, the use of appropriate mulches
and stabilizers, the application of required doses of lime and  fertilizers,
and optimum timing in seeding will help ensure the establishment of an effec-
tive vegetative cover.  However, unforeseen difficulties may compromise the
effectiveness of revegetation.  Clays or synthetic barriers below supporting
topsoil in poorly drained areas may cause swamping of cover soil and sub-
sequent anaerobic conditons.  A cover soil which is too thin may dry exces-
sively in arid seasons and irrigation may be necessary.  Improperly vented
gases and soluble phytotoxic waste components may kill or damage vegetation.
The roots of shrubs or trees may penetrate the waste cover and  cause leaks of
water infiltration and gas exfiltration.  Also, periodic maintenance of
revegetated areas—liming, fertilizing, mowing, replanting, or  regrading
eroded slopes—will add to the costs associated with this remedial technique.


     3.4.3  Design Considerations


     Long-term vegetative stabilization generally involves the  planting of
grasses, legumes, and shrubs.  The establishment of short-term, seasonal
vegetative cover is limited principally to species of grasses.  The selection
of suitable plant species for a given disposal site depends on  several site-
specific variables.  These variables include cover soil characteristics (grain
size, organic content, nutrient and pH levels, and water content), local
climate, and site hydrology (slope steepness and drainage characteristics).
Individual species must be chosen on the basis of their tolerance to such
site-specific stresses as soil acidity and erodibility and elevated levels of
landfill gases or phytotoxic waste components (e.g., heavy metals, salts) in
cover soil.  Other important considerations include the species compatibility
with other plants selected to be grown on the site, resistance  to insect
damage and diseases, and suitability for future land use (USEPA, 1976).

     Long-term vegetative stabilization and site reclamation require the
proper planting of compatible mixes of grasses, legumes, shrubs, and trees.
Short-term revegetation efforts generally require the use of low-cost, quick-
growing perennial and self-seeding annual species, usually grasses (USEPA,
1976).  In areas where a quick vegetative cover is essential to preventing
erosion and pollutant transport, the use of an approved sod could prove
beneficial.

     A study of vegetative growth in landfill environs (Gilman  et al., 1979)
ranked the relative tolerance of selected tree species to high  cover soil
concentrations of carbon dioxide and methane, a typical landfill condition
that causes the displacement of oxygen from the root zones of growing plants.
The tree species included (in order of decreasing tolerance): Black Gum,
Norway Spruce, Gingko, Black Pine, Bayberry, Mixed Poplar, White Pine, Pin
Oak, Japanese Yew, American Basswood, American Sycamore, Red Maple, Sweet Gum,
Green Ash, and Honey Locust.  The same study found that mounds  of topsoil
underlain by clay gas-barriers, or trenches underlain with polyethylene

                                     3-28

-------
sheeting and vented with perforated PVC vent  pipes  (Figure  3-6),  effectively
prevented the migration of  landfill gases  (products  of  anaerobic  decompo-
sition) into the root  zone  of  trees.  A further  discussion  on gas migration
control can be  found in Section  6.  The Gilman study also concluded  that  woody
plant species are more likely  to survive on  a completed fill  if  planted  when
small, generally less  than  three feet tall  (Gilman  et al.,  1979).

     Loamy topsoils—those  with  nearly equal  percentages  of clay, silt,  and
sand-sized grains—are generally best suited  for revegetation establishment.
They are easily seeded and  allow easy root penetration.   Sandy soils may be
productive when blended or  mulched with organic  matter  (Lutton,  Regan,  and
Jones, 1979).

     Mulches or chemical stabilizers may be  applied  to  seeded soils  to  aid in
the establishment of vegetative  cover.  Organic  mulches such  as  straw, hay,
wood chips, sawdust, dry bark, bagasse (unprocessed  sugar cane fibers),
excelsior (fine wood shavings),  and manure protect bare seedbed  slopes  from
erosion prior to germination.  Also, thin blankets of burlap,  fiberglass,  and
excelsior can be stapled down  or  applied with asphalt tacks to form  protective
mulch mats for  germinating  seedbeds.

     Mulches conserve  soil  moisture, dissipate raindrop energy, moderate  soil
temperatures, prevent crusting,  increase infiltraton, and generally  control
wind and water  erosion.  Stabilizers reduce  soil water  loss and  enhance  plant
growth by temporarily  stabilizing seeded soils against  wind and water erosion.
They can also be used  to stabilize graded  soils  in the  off  season until  spring
seeding.  Stabilizers are used extensively in arid regions  to  help dry,
permeable soils retain soil moisture (USEPA,  1976).

     Petroleum-based products  such as asphalt and resins are  often suitable
and are frequently used as  mulching materials.   However, some of  these
materials are toxic and selection should be made only after careful  evauation.
Specially formulated emulsions of asphalt under  various trade  names  have  been
used throughout the world to prevent erosion, reduce evaporation,  promote  seed
germination, and warm the soil to advance the seeding date.   The  film clings
to but does not deeply penetrate  the soil.  It is not readily  destroyed by
wind and rain and remains effective from 4 to 10 weeks.  Application rates of
1000 to 1200 gallons/acre are  usually required to control erosion.   Asphalt
mulches cost about twice the applied cost of  a straw mulch  (Lutton,  1982).

     In field tests comparing  the effectiveness  of these chemical additives  in
controlling erodibility of  several regional soil  types  in Virginia,  none  of
the stabilizers tested were determined to be as  cost-effective as conventional
mulches of straw and asphalt-emulsions (Lutton,  Regan,  and Jones,  1979).


     3.4.4  Construction/Implementation Considerations


     The optimum time for seeding depends on local climatic considerations and
the individual species adaptations.   For most perennial species in most local-
ities,  early fall seeding is recommended.   Annuals are  usually best  seeded in

                                     3-29

-------
                                FIGURE 3-6.
                        GAS MIGRATION CONTROLS
                  Cross-Section End View of Gas Barrier Trench

                                                           1'Topsoil

                                                           1' Subsoil
                                                           Plastic Sheet
                                                            PVC Perforated
                                                            Vent Pipes
                     Cross-Section End View of Soil Mound
Source: Gilman et al., 1979
                                    3-30

-------
spring and early summer, although they can be  planted  for  quick vegetation
whenever soil is damp and warm  (Lutton, Regan,  and Jones,  1979).   In  mild
climates (e.g., southeastern United States) the growth of  both  summer and
winter grasses will extend the  range of evapotranspiration and  erosion
resistance for cover soils (Lutton, Regan, and  Jones,  1979).

     Seedbed preparation is necessary to ensure rapid  germination  and growth
of the planted species.  Applications of lime will help neutralize highly
acidic topsoils.  Similarly, fertilizers should be added for  cover soils  low
in essential plant nutrients.   Optimum soil application rates or lime and
fertilizers should be determined from site-specific  soil tests.  Where
required, lime should be worked to 6-inch depths  into  the  soil  by  discing  or
harrowing (USEPA, 1976).  For dense, impervious topsoils,  loosening by tillage
is recommended.  Grading methods for loosening  and roughening large areas  of
soils are discussed in Section  3.2.1.

     Seeding should be performed as soon as possible after final grading  and
seedbed preparation (USEPA, 1976).  The most common  and efficient  method of
seeding large areas of graded slopes is with hydroseeders.  Seed,  fertilizer,
mulch, and lime can be sprayed  from hydroseeders  onto  steep outslopes and
other areas of difficult access.  Rear-mounted  blowers can be attached to  lime
trucks to spread seed and fertilizers over such areas, also.  Grass or grain
drills may be used to apply seed on gently rolling or  level,  stone-free
terrain.  Hand planting, a time-consuming and costly project, may  be  required
for trees and shrubs (USEPA, 1976).

     Planting is often performed in stages so  that complete revegetation may
take several years.  When planting large trees, it is  important  to know the
depth and locations of protective caps and barriers  so that they are  not
accidentally damaged.

     Mulches are usually applied after seeding  and fertilization,  although
certain mulch materials (e.g., wood fibers) may be applied  as hydroseeder
slurries mixed with seed, fertilizer, and lime  (USEPA, 1976).   Mulch  applica-
tion rates will vary depending on local climate,  soil characteristics,  and
slope steepness.

     Loose straw and hay mulches are the most common and most cost-effective
temporary soil stabilizer/mulching materials available (USEPA,  1976).   These
mulches are best applied using  a mulch blower,  at rates from 1/2 to 4 tons per
acre.   Straw/hay mulches can be anchored to the soil by asphalt, chemical
binders, or jute netting (USEPA, 1976).

     Total 1985 cost estimates  for revegetation range from $1259/acre to
$8300/acre based on cost data presented in the  cost compendium  (USEPA,  1985).
Cost for revegetation vary widely depending upon  the site  conditions.   The
lowest cost estimate was based on a hypothetical  site which required
hydroseeding (lime, fertilizer, field seed) only.  The highest  cost estimate
was for a proposed restoration of a secondary growth, temperate, deciduous
forest, requiring heavy lining to neutralize the highly acidic  soils.
                                     3-31

-------
     1985 Opertion and Maintenance  costs  for  a  revegetated  area  have  been
estimated to range from $58/acre/year  to  $1314/acre/year.


     3.4.5  Operation, Maintenance,  and Monitoring


     Periodic reliming and  fertilization  may  be  necessary to  maintain optimum
yearly growth on seeded plots.  Soils  with  poor  buffering capacity may require
frequent liming to achieve  suitable  pH levels;  these  are generally soils  high
in organic matter or clay content.   Annual  fertilization of nitrogen,
phosphorus, or potassium deficient  soils  will also  aid  reclamation efforts.
Fertilizer application rates will vary with the  nutrient content  and  pH level
of the seeded cover soil.   Periodic  mowing  and  the  judicious  use  of selective
herbicides will help control undesirable  weed and brush species.   Grass
sodding and remulching or planting new shrubs and trees is  recommended for
sparsely covered, erosion-prone areas  (Lutton, Regan, and Jones,  1979).

     All vegetation should  be monitored for sickness  and death as  these
occurrences may be indicative of contamination  in ground or surface waters.


     3.4.6  Technology Selection/Evaluation


     A well-designed and properly implemented revegetation  plan—whether  for
long-term reclamation or short-term  remedial  action—will effectively reduce
erosion and stabilize the surface of a covered disposal site, thereby
improving the effectiveness and reliability of  the  cap.  A multi-layered
capping system and properly graded slopes,  in combination with suitable
vegetative cover, will eventually isolate buried wastes from  surface
hydrologic input.

     Although vegetative cover requires frequent maintenance, it  actually
prevents more costly maintenance which would  result from erosion by surface
soils.  Revegetation is also essential to the integrity and performance of
dikes, waterways, and sedimentation  basins.


     3.4.7  Costs


     Unit costs associated  with revegetation  of  covered disposal  sites are
reported in Table 3-6.  All costs are  reported  in 1985 dollars and include
contractors overhead and profit.
3.5  Surface Water Diversion and Collection


     This section discusses the various  surface water  diversion  and  collection
methods in terms of their applications and limitations  and design  and

                                     3-32

-------
                                  TABLE 3-6.
    1985 UNIT COSTS ASSOCIATED WITH REVEGETATION OF COVERED DISPOSAL  SITES
         Description
Unit Costs
                                                            1
Source
Hydraulic spreading (hydroseeding),
  lime, fertilizer, and seed

Mulching, hay

Loam topsoil

Loam topsoil, remove and stockpile
  on-site using 200 hp dozer 6 ft deep
     200 ft haul
     500 ft haul

Hauling loam on-site (2 miles)

Spreading loam, 2-6 inches deep
     slopes
     level areas

Plant bed preparation (unspecified),
  18 inches deep, by machine

Hydraulic seeding and fertilization
  of large areas with wood fiber mulch

Mulch, hand spread 2 inches deep, wood
  chips

  Liming
    level areas
    slopes
$849.57/acre


$309.09/acre

$6.50/yd3
$1.16/yd,
$4.44/ydJ

$3.84/yd3
$1.04 - $3.12/yd^
$0.77 - $2.27/yd

$5.40/yd2
$0.41/yd"
$1.23/yd'
$87.96/acre
$570.82/acre
   2

   2
   3
   3
   2
   2
                                                            (continued)
                                     3-33

-------
                            TABLE 3-6.  (continued)
         Description
                        Unit Costs
                     Source
Fertilizing (no insecticides)
     level areas
     slopes

Seeding
     level areas
     slopes

Jute mesh, stapled (erosion control)

Sodding, in East, 1 inch deep
     level areas
     slopes

Maintenance:
  Grass mowing
     slopes
     level areas
  Re fertilization
  Weeding/pruning shrubs

On-Site Planting
                        $448.01/acre
                        $641.33/acre
                        $656.78/acre
                        $850.11/acre

                        $  0.85/yd2
                                2

                        $3.28/yd2
                        $90.71/acre
                        $37.86/acre
                        $242.04/acre
                        $l,943.87/acre
                        2
                        2
                        2
                        2
                        2
                        2
                        2
                        2
  Trees
     evergreens
     Black Pines
     Yews
     Junipers
30-36 inches
36-42 inches
42-48 inches
4-5 ft
5-6 ft
2.5-3 ft
2-2.5ft
4-5 ft
$112.19 ea.
$114.25 ea.
$160.31 ea.
$202.49 ea.
$258.20 ea.
$27 ea.
$37 ea.
$49 ea.
2
2
2
2
2
3
3
3
                                                            (continued)
                                     3-34

-------
                            TABLE 3-6.  (continued)
         Description
Unit Costs
Source
Shade trees




Birch
Oak
(balled and burlapped)
6-8 ft
8-10 ft
1.5 - 2.5 inch diameter
2.5 - 4.0 inch diameter
6-8 ft
8-10 ft

$76.65 ea.
$108.02 ea.
$276.31 ea.
$451.09 ea.
$96 ea.
$490 ea.

2
2
2
2
3
3
Shrubs (balled and burlapped)
                    2-3 ft
                    3-4 ft
                    4-5 ft
Honeysuckle shrub   3-4 ft
$55.57 ea.
$87.40 ea.
$106.20 ea.
$18.15 ea.
   2
   2
   2
   3
                                                           (continued)
 All costs include materials and installation (labor and equipment), unless
 otherwise indicated.  Note different units (acre, square yard, cubic yard,
 each).

ZMcMahon, 1984.

3Godfrey, 1984.
                                     3-35

-------
construction considerations.  Costs of these systems and  factors affecting
selection and evaluation are discussed in Sections 3.5.9  and 3.5.8,
respectively.
     3.5.1  Dikes and Berms
          3.5.1.1  General Description
     Dikes and berms are well-compacted earthen ridges or  ledges  constructed
immediately upslope from or along the perimeter of disturbed  areas  (e.g.,
disposal sites).  These structures are generally designed  to  provide  short-
term protection of critical areas by intercepting storm run-off and diverting
the flow to natural or manmade drainage ways, to stabilized outlets,  or  to
sediment traps.  The two terms, dikes and berms, are generally used inter-
changeably; however, dikes may also have applications as flood containment
levees (Section 3.5.7).
          3.5.1.2  Applications/Limitations
     Dikes and berms may be used to prevent excessive erosion of newly  con-
structed slopes until more permanent drainage  structures are installed  or
until the slope is stabilized with vegetation  (USEPA, 1976).  They  are  widely
used to provide temporary isolation of wastes  until  they can be removed or
effectively contained.  They have particularly widespread use during  excava-
tion and removal operations where it is necessary to isolate drums  or
contaminated soils which have been temporarily staged on-site.  The dikes not
only prevent runoff, but can also prevent mixing of  incompatible wastes.
These temporary structures are designed to handle relatively small  amounts of
runoff; they are not recommended for drainage  areas  larger than 5 acres
(Virginia SWCC, 1980).  Diversion of storm run-off will decrease the  amount of
water available to infiltrate the soil cover,  thereby reducing the  amount of
leachate production.

     Dikes and berms are temporary structures which  are usually used  for no
more than one year.  Though construction costs are not usually high,  the
ultimate removal of the structures entails additional costs.
          3.5.1.3  Design Considerations


     Specific design and construction criteria  for berms and dikes will  depend
upon desired site-specific functions of the  structures.  Run-off  control dikes
are generally classified into two groups:

     •  Interceptor dikes (Figure 3-7) which are built with 0  (zero)  percent
        grade and are designed only to reduce slope  length

                                     3-36

-------
                        FIGURE 3-7.
              TEMPORARY INTERCEPTOR DIKE
    2:1 or Flatter Slopes

                    CROSS SECTION
                                          Disturbed Right-of-Way
                                    min
            R.O.W
        Side  Slopes
         2; I or Flatter
                              Upslope Toe
                                  Outlet Onto Stabilized Area
                      PLAN  VIEW
Source: Virginia SWCC, 1974
                          3-37

-------
     •  Diversion dikes (Figure 3-8) which are built with a grade sufficient
        to drain and are designed to intercept and divert surface flow as well
        as to reduce slope length.

     Dikes and berms ideally are constructed of erosion-resistant, low perme-
ability, clayey soils.   Compacted sands and gravel, however, may be suitable
for interceptor dikes and berms.  The general design life of these structures
is on the order of one  year maximum; seeding and mulching or chemical
stabilization of dikes  and berms may extend their life expectancy.  Stone
stabilization with gravel or stone rip-rap immediately upslope of diversion
dikes will also extend  performance life.

     A detailed design  is not usually required before constructing interceptor
and diversion dikes/berms.  The following design criteria are commonly used:

     •  Drainage area:   5 acres maximum

     •  Top width:  2 feet minimum

     •  Height (compacted):  18 inch minimum

     •  Side slopes:  2:1 or flatter

     •  Grade:  Dependent upon topography, but must have positive drainage to
                the outlet; for interceptor dikes/berms, 1.0 to 1.5 percent.

     •  Spacing (interceptor only):
        Distance between dikes                 150 ft      200 ft        300 ft
        Maximum slope of area above dike       >10%        5-10%         <5%


          3.5.1.4  Construction/Implementation Considerations


     Dikes and berms are constructed by well-established techniques, and very
often the required excavation and grading equipment is already available at
the disposal site.  The required earth fill is often available on-site as
well.

     Structures of this type are often constructed in several lifts with each
lift being tested for adequate compaction.  The following considerations are
essential for the construction of a proper dike:

     •  All earthen dikes should be machine compacted.

     •  All diversion dikes must have positive grade to an outlet.

     •  Diverted run-off should outlet directly onto stabilized areas, level
        spreader, grassed channel, or chute/downpipe.

     •  Periodic  inspection and maintenance should be provided.


                                     3-38

-------
                                   FIGURE 3-8.
                         TEMPORARY DIVERSION DIKE
                 18" min
Cut or fill slope
                                                                          Flow
                                                                   Stone stabilization,
                                                                   if required
                                                2:1 slope or flatter
                                  Existing ground
                                  Cross-section
Positive drainage. (Grade
sufficient to drain.)

A A

A A

A A

A A

A A
f •
Vf

Vf

Y y
V
Vf

Y^
.
\
                                               Cut or fill slope
   Source: USEPA, 1976
                                   Plan view
                                      3-39

-------
     •  Diversion dikes must be seeded and mulched immediately after
        construction.
          3.5.1.5  Operation, Maintenance, and Monitoring


     Adequate maintenance of dikes and berms is essential.  Periodic  inspec-
tions and maintenance are required to ensure structural integrity and prevent
upslope deposition of sediments.  When operating improperly, dikes and berms
will actually act to increase seepage.  It is generally not a good practice to
utilize dikes or berms for a period of time exceeding one year.


          3.5.1.6  Costs


     The costs of installing and maintaining dikes and berms will vary with
the site conditions, depending on:  number and size of structures required,
local availability of suitable soil and equipment, local climate and  site
hydrology (intensity and volume of storm run-off to be diverted), amount of
maintenance required, design life of the structures, amount and type  of
stabilization required (seeding, mulching, chemical soil additives),  and
unforeseen construction difficulties.

     Unit costs associated with dike/berm construction and maintenance are
presented in Table 3-13 at the end of this chapter.


     3.5.2  Channels and Waterways


          3.5.2.1  General Description


     Channels are excavated ditches that are generally wide and shallow with
trapezoidal, triangular, or parabolic cross sections.  Diversion channels are
used primarily to intercept run-off or reduce slope length.  They may or may
not be stabilized.  Channels stabilized with vegetation or stone rip-rap
(waterways) are used to collect and transfer diverted water off site  or to
on-site storage or treatment (Ehrenfelder and Bass, 1983).


          3.5.2.2  Applications/Limitations


     Applications and limitations of channels and waterways differ depending
upon their specific design.  Table 3-7 summarizes the applications of specific
types of channels and waterways with respect to drainage area and maximum
permissible velocity.  Earthen channels can be used on the perimeter  of a
disposal site to divert runoff from entering the area of waste disposal.
                                     3-40

-------












CO
>•
1
w
1
Q

f^(

a


eu
E ^ ^i ^"*
3 ••* 4J CJ
g en -F- oi
•F- CO 0 CO
X — O ~->
OJ E — 4->
S C OJ ซ-
CD i> —
Pu




*
60
co eo
C 01
•Fป F-
CO <
F*
O

>:
60
O

O
C
ฃ
O
Oi
H


u-
o<
ฃl
eo
u
en
01 Cu
tJ E

en 4-1
cu
> Oi

4J .ฃ
•F- CO
T3 F.
•O 01
CO 73
F-- W
•F- C
O O
en o
F. -•
0 O
L4-<
ซ -a
CO 01
u en
U 3



CN
>*
..
CO
v.
O
a
E
O1






E
4-1 •'"
t- C
— E




CM






C
!ป
ฃ "1
ฑj Oi
F.
en u
en ctj
cu
J u>



CO

CD
C C
CU C
s: ctj
4-> C.
.. u
CO
W














1
1







1
1

>,
,.
CO
F.
0
a
E
eu
H





01
en a.
3 .F-
•F- a
•o
CO 14*
.. o




o





c
0

01 4J
N CO
•F- 4-1
en -F*
E
O •-
Z r-i

en
F-,
01
C
c
eo
j:
u
CL
ฃ
O

3
0
(4*
1)
en
CO
J3

t-
O

ง
4-1
4^
O
J3
4)
C
O
xj
CO
n
TJ
0
CO



(N
4-1
C
Qj
C
et)

Cb
CX,

^-s
4* -""* 4J t—<
^4-1 (J 14* CO
•- -O
ro F- \o *F-
O O
O J3 D N
4-1 CO 4-1 dJ
F. a.
•^ CO U^ CO
• a. • F.
o ^ o 4-




\n





c
o

01 4-1
N CO
•F" 4.1
en -F-
E
O •"
Z r-


en
>s
CO
3
I*
T3 01
O/ 4-1
-a eo
•a 3
o
CO














I
I









CN
4-1
C
01
c
CO
g
01
p*



g
3
E
4~ -F-
u- c

— E





vO





c:
0

01 4-1
N CO
•F- 4*
cn -F-
E
O "•
Z F-


en
^
CO
3
u
01
01 4J
C CO
0 3
4J
CO
















































o
CO
d*


en
F-
OJ
OJ
c

60
C
W
CO
o
CO



0;
o
F.
3
o
CO
3-41

-------
Figure 3-9 is a cross section of a typical  earthen channel.   They are usually
temporary, since they are inadequately  stabilized  to  resist  erosion.

     A diversion is a modification of an  earthen  channel.   A diversion is a
shallow channel excavated along the contour  of  graded slopes and having a
supporting earthen ridge (dike or berm) constructed along  the downhill edge of
the channel.  Essentially, a diversion  is a  combination  of a ditch and a dike
(USEPA, 1976).  Figure 3-10 illustrates a diversion.

     Swales placed along the perimeter  of the  site are used  to keep off-site
runoff from entering the site and to carry  surface runoff  from landfills.
They are distinguished from earthen channels by side  slopes  which are less
steep and have vegetative cover for erosion  control.

     Half-round pipe can be used in a manner similar  to  earthen channels.  It
can be constructed by cutting corrugated metal  pipe (CMP)  or can be purchased
in an asbestos impregnated asphalt called sectional slope  drains.  Channels
are constructed from half-round pipe which  is  placed  below grade.  Half-round
pipe channels are easier to install and have lower maintenance costs than
                                  FIGURE 3-9.
              TYPICAL DRAINAGE DITCH AT BASE OF DISPOSAL SITE
              •Final cover
                                              Gran lint (or • ration
                                              protection
Q% mm 1
T^tiL
?'mln. \,uJ
I.?

$^

                                      3-42

-------
                                      FIGURE 3-10.
                     GENERAL DESIGN FEATURES OF DIVERSIONS

                                                 width
                                 Trapezoidal cross-section

                                Parabolic cross-section
Source: USEPA, 1976
                                       3-43

-------
earthen channels.  In addition, infiltration  into  the  site  is minimized.   Like
earthen channels, half-round channels may be  constructed on  the  perimeter  of  a
waste site and moved as needed to protect other  portions of  the  waste  site.
They can also be used successfully to carry storm  water run-off  over a  filled
area where it is not practical to carry the run-off  around  the  fill.

     Sodded waterways (Figure 3-11) are used  primarily  in situations where the
flow quantities and velocities are significant and a full growth of grass  is
required to prevent erosion.  Typically, five acres  is often considered  to be
a large enough area to warrant sod.  The maximum allowable velocities  for
sodded waterways are dependent on the type of grass.

     Where the tributary drainage area is relatively small and  the quantity of
run-off and velocity of flow is low, grass-seeded  waterways  can  be effectively
used.

     Stone waterways provide added protection against erosion.   If the water-
way is intended to carry large quantities of  run-off  and/or  the  flow
velocities are excessive, the stone may be grouted in place.  A stone  channel
is a permanent means of diverting off-site drainage  around the  disposal  site
and carrying surface run-off from landfills.  Figure  3-12 illustrates  a
grassed waterway with a stone center.
           3.5.2.3  Design Considerations


     Channels, swales, and waterways are generally of V-shaped,  trapezoidal,
or parabolic cross-section design.  The specific design will be  dependent  on
local drainage patterns, soil permeability, annual precipitation,  area  land
use, and other pertinent characteristics of the contributing watershed.  Table
3-7 gives some general guidelines for depth and maximum side slopes  for
various channel and waterway designs.  Figure 3-13 shows a  standard  design for
an earthen channel.

     Channels and waterways should be designed to accommodate  flows  resulting
from rainfall events (storms) of 10- or 25-year frequency.  More importantly,
they should be designed and constructed to intercept and convey  such flows at
nonerosive velocities.

     Figure 3-14 depicts the effect of drainage channel shape  on relative
velocity of conveyed flows.  In general, the wider and shallower the channel
cross-section, the less the velocity of contained flow, and, therefore,  the
less the potential for erosion of drainageway side slopes.  Where  local
conditions dictate the necessity of building narrower and deeper channels, or
where slopes are steep and flow velocities are excessive, the  channel will
require stabilization through either seeding and mulching or the use of  stone
rip-rap to line channel bottoms and break up flow.

     Design of channel and waterways is generally based on  the Manning  formula
for steady uniform flow in open channel.
                                     3-44

-------
                                  FIGURE 3-11.
                            GRASSED WATERWAYS

                              Trapezoidal cross-section
                                   Parabolic cross-section
Source: USEPA, 1976
                                     3-45

-------
                          FIGURE 3-12.
        GRASSED WATERWAYS WITH STONE CENTERS
                             '""" — ** -^r "* *• —3C _jฃI'>t>. "V^^^L—~
                       Trapezoidal cross-section

                       Parabolic cross-section
Source: USEPA, 1976
                              3-46

-------
                                   FIGURE 3-13.
                  STANDARD DESIGN FOR DRAINAGE DITCHES
                                       2:1 or flatter
1
1' min.
r


7' min.
level


                                                                 Existing ground
                                    Cross-section
• Ck..*l
                                   t% ฐr $teeper< *Pซndซ'1t 0" topography
 Outlet as required.
 See item 6 below.
                                      Plan view
     Source: USEPA, 1976
             Figure  3-13.   Standard  Design  for  Drainage Ditches
                                        3-47

-------
                       FIGURE 3-14.
        EFFECT OF DRAINAGE DITCH ON VELOCITY
                               18.0'
     1.00'
V=1.00*
                               10.0'
         1.87'
                               15.0'
                            21.0'
   *V=REI_ATIVE VELOCITY
Source: Lutton, Regan, and Bass, 1983
                               10.5'
                               7.0'
                           3-48

-------
     The Manning  formula  is  considered  when  designing  for  steady uniform flow
in open channels  (Ehrenfelder  and Bass,  1983):

          v=CmR2/3 s 1/2
and for an open  channel  of cross-sectional  area,  A:
where :

           Q = design capacity  (m  /sec)

           R = hydraulic radius  (area  divided  by  wetted  perimeter)  (m)
                                                      2
           A = cross-sectional  area of the channel  (m )

           S = channel  slope  (m/m)

          C  = dimensionless  constant  (1.0 for metric units)
           m
                                               1/3
           n = Manning  roughness factor  (sec/m   ).   Values of n  for various
               materials are  given in  Table 3-8.

Permissible flow velocities for  channels  lined with vegetation are  given  in
Table 3-9.
     Channel spacing  (when used  for  interception or  slope  length  reduction)
depends on the slope  of the area above  the channel (USEPA,  1976):

          Slope                    Distance Between  Channels

          >10%                           30m  (100 ft)
          5-10%                          60m  (200 ft)
           <5%                           90m  (300 ft)


          3.5.2.4  Construction/Implementation Considerations


     The construction of channels and waterways does not generally  present any
complications as simple and well-established  construction  techniques  are
generally used.  Where there is extensive gullying,  considerable  earthwork
will be required.  Compaction of fills  should be performed  as needed  to
prevent unequal settling.   All trees, bushes, stumps, and  obstructions should
be cleared to prevent improper functioning of the channel.  If  local  fill is
used, it must meet design standards and be free of contamination.
                                     3-49

-------
                                  TABLE 3-8.
          VALUE OF MANNING'S n FOR VARIOUS CHANNEL SURFACE MATERIALS
               Material                           Suggested



          Planed Wood                              0.012

          Unplaned wood                            0.013

          Finished concrete                        0.012

          Unfinished concrete                      0.014

          Cast iron                                0.015

          Brick                                    0.016

          Riveted steel                            0.018

          Corrugated metal                         0.022

          Rubble                                   0.025

          Earth                                    0.025

          Earth with stones or weeds               0.035

          Gravel                                   0.029

          Vegetation                                 .04
a
 The Manning forumla is an empirical formula.  The dimensions of  Cm and  n are
 therefore somewhat arbitrary.  In metric units.?CM =  1.0  and n  is  in. ,,
 (s)/(Mi/')).  In English units, Cm - 1.486 (ft1/Z)/(s) and n is  in  ft1/o.   The
 numerical values for n, however, do not change.

 In situations with R>3m, roughness factor should be increased by 10 to  15%.

CFrom TRD 8.

Source:  Streeter and Wylie, 1975
                                     3-50

-------
                                  TABLE 3-9.
      PERMISSIBLE DESIGN VELOCITIES FOR STABILIZED  CHANNELS  AND WATERWAYS

Vegetative
Cover
Bermuda grass

Reed canary grass,
Tall fescue, or
Kentucky bluegrass
Grass-legume mix
Channe 1 gr ad e ( % )
0-5
5-10
>10
0-5
5-10
>10
0-5
5-10
Maximum design velocity
(ft/sec)
6
5
4
5
4
3
4
3
Red fescue, or                       0-5                         2.5
  Redtop (sericea lespedeza)

Annuals; Small grain                 0-5                         2.5
  (rye, oats, barley); Ryegrass


Source:  USEPA, 1976


          3.5.2.5  Operation, Maintenance, and Monitoring


     Failure of channels and waterways may result from insufficient capacity,
excessive velocity, or inadequate vegetative cover.  The first of these  two
are largely a matter of inadequate design.  Grassed waterways must be period-
ically mowed to prevent excessive retardation of flow and  subsequent ponding
of water.  Also, periodic resodding, remulching, and fertilizing may be
required to maintain vegetated channels.  Sediment accumulation often results
in failure of channels and waterways.  Control of vegetation to prevent matted
growth and high allowable design velocities will reduce sediment accumulation.
Stone channels have the advantage of requiring minimal maintenance.

     It may be necessary to install temporary straw-bale check dams, staked
down at 50- to 100-foot intervals, across channels and waterways in order  to
prevent gully erosion and to allow vegetative establishment (Tourbier and
Westmacott, 1974).  The installation and ultimate removal  of these, check dams
will add to the costs associated with diversions and waterways.
                                     3-51

-------
          3.5.2.6  Costs
     As with all surface water diversion structures, costs  for ditches, diver-
sions, and waterways will be highly variable because of site-specific differ-
ences in fill materials and equipment availability, design  capacity  and life
expectancy of the structure, etc.  Unit costs associated with the construction
and maintenance of these structures are presented at the end of  this chapter
in Table 3-13.
     3.5.3  Terraces and Benches


          3.5.3.1  General Description
     Terraces and benches are embankments constructed along  the  contour  of
very long or very steep slopes to intercept and divert flow  and  to  control
erosion by reducing slope length.  These structures are classified  as bench
terraces or drainage benches.  Bench terraces are used primarily to reduce
land slope while drainage benches on broadbased terraces  act  to  remove or
retain water on sloping land.


          3.5.3.2  Applications/Limitations


     Benches and terraces may be used to break up steeply graded slopes  of
covered disposal sites into less erodible segments.  Upslope  of  disposal
sites, they act to slow and divert storm run-off around the  site, thereby
minimizing erosion.  Downslope of landfill areas, they act to  intercept  and
divert sediment-laden run-off to traps or basins.  Hence, they may  function  to
hydrologically isolate sites where remedial actions have  not  yet been
completed, to control erosion of cover materials on sites which  have been
capped, or to collect contaminated sediments eroded from  disposal areas. For
disposal sites undergoing final grading (after capping and prior to revege-
tation), construction of benches or terraces may be included  as  part of  the
integrated site closure plan.


          3.5.3.3  Design Considerations


     Although benches and terraces are slope reduction devices,  they are
generally constructed with reverse fall or natural fall (see  Figure 3-15).
Figure 3-16 presents the design for a typical drainage bench  located on  the
slope of a covered landfill.  This particular bench is designed  with a natural
fall.  It is intended for long-term erosion protection as the  associated
V-shaped channel is asphalt concrete-lined.  Diversions and  ditches included
in bench/terrace construction may be seeded and mulched,  sodded, stabilized


                                     3-52

-------
                             FIGURE 3-15.
                          BENCH TERRACES
                            With Reverse Fall
 Swale or Ditch
        f/'
                                Swale or Ditch
                                    \
                            With Natural Fall
                   Ditch
                                                     Ditch
Adapted from: Tourbier and Westmacott, 1974
                                 3-53

-------
with rip-rap or soil additives, or  stabilized by  any combination of these
methods.  Lining the channels with  concrete  or  grouted  rip-rap is a more
costly alternative.

     The design of a terrace system involves the  proper spacing and location
of terraces and the design of a channel  with adequate capacity.

     The spacing between benches  and  terraces will depend on slope steepness,
soil type, and slope length.  In  general,  the longer and steeper the slope and
the more erodible the cover  soil, the less the  distance between drainage
benches should be.  This will maximize  the erosion reduction afforded by
constructed benches.  For slopes  greater than 10  percent in steepness, the
maximum distance between drainage benches  should  be approximately 100 feet,
i.e., a bench every 10 feet of rise in  elevation  (USEPA, 1976).  When the
slope is greater than 20 percent, it  has been recommended that benches be
placed every 20 feet of rise in elevation  (USEPA,  1976).  An exact solution to
terrace spacing can be found in Schwab  et  al. (1981).

     Benches should be of sufficient  width and  height to withstand a 24-hour,
25-year storm (USEPA, 1976).

     The terrace channel acts as  a  temporary storage reservoir subjected to
unequal rates of inflow and outflow.   For  graded  terraces the Manning velocity
equation given in Section 3.5.2 is  suitable  for design.  A roughness
coefficient of 0.04 is usually selected  for  tilled soil and design is based on
this condition because overtopping  would cause  the worst damage.  The maximum
                                 FIGURE 3-16.
                           TYPICAL DRAINAGE BENCH
                                                     Final Soil Cover
       3" Min. Asphaltic Concrete Liner
                     !>
                                      3-54

-------
design velocity will vary with  the  erosiveness  of  the  soil  but  should rarely
exceed 0.6 m/sec  for soil devoid  of vegetation.  The  channel  depth should
permit a freeboard of about 20  percent of  the  total depth after allowing for
settlement of the ridge  (Schwab et  al.,  1981).

     Bench terraces do not necessarily have  to  be  designed  with diversions or
ditches to intercept flow.  Reverse benches  and slope  benches (Figure 3-17)
may be constructed during final site grading on well-stabilized slopes (e.g.,
vegetated) to enhance erosion control by reducing  slope  length  and steepness.
At sites where an effective cap (e.g., clay  or  synthetic  liner) has  been
constructed, or for sites located in arid  regions, these  nondrainage benches
                                  FIGURE 3-17.
                          SLOPE REDUCTION MEASURES
              Source: USEPA, 1976
                                     3-55

-------
will function to slow sheet run-off and allow greater  infiltration  rates,
which will aid in the estabishment of a suitable vegetative  cover.   For most
disposal sites in wet climates, however, where  leachate generation  and cover
erosion are major problems, benches and terraces should be designed  in
association with drainage channels that intercept and  transport heavy, concen-
trated surface flows safely off-site.


          3.5.3.4  Construction/Implementation  Considerations


     Benches and terraces are constructed with  a variety of  commonly used
excavation equipment including bulldozers,  scrapers, and graders.   As with
other earthen erosion control structures, they  are  constructed using well-
established techniques and with local fill  material.   Benches and  terraces
must be sufficiently compacted and stabilized with  appropriate cover (grasses,
mulches, sod) to accommodate local topography.


          3.5.3.5  Operation, Maintenance,  and  Monitoring


     Benches and terraces should be inspected frequently during the  first  year
of operation and during or after major storms to ensure proper functioning and
structural integrity.  Terrace ridges may settle up to 25 percent  depending
upon construction techniques.  If bench slopes  become  badly  eroded  or if  their
surfaces become susceptible to ponding from differential settling  then
regrading and sodding may be necessary.

     If improperly designed or constructed,  bench terraces will not  perform
efficiently and may entail excessive maintenance and repair  costs.   It is
important that these structures be stabilized with  vegetation as soon as
possible after grading and compaction, or they  may  become badly eroded and
require future resodding or chemical stabilization.  Benches and terraces  also
require periodic inspections, especially after  major rainfall events.


3.5.3.6  Costs
     The costs of bench and terrace construction will  depend  on  the  amount of
fill required, the local availability of  fill materials  and grading  eqiupment,
the size and type of diversion channels to be installed,  and  the local  costs
of seeding, mulching, and other  stabilizing materials.   The frequency and
extent of required maintenance will add to these costs.

     Unit costs  for these construction and maintenance activities are
presented in Table 3-13 at the end of this chapter.
                                      3-56

-------
     3.5.4  Chutes and Downpipes


          3.5.4.1  General Description
     Chutes and downpipes are  structures  used  to  carry concentrated  flows  of
surface run-off from one level  to a  lower  level without  erosive  damage.  They
generally extend downslope  from earthen embankments  (dikes  or  berms)  and
convey water to stabilized  outlets located at  the base of terraced slopes.

     Chutes (or flumes) are open channels, normally  lined with bituminous
concrete, portland cement concrete,  grouted rip-rap,  or  similar  non-erodible
material.

     Downpipes (downdrains; pipe slope drains) are temporary structures con-
structed of rigid piping (such  as corrugated metal)  or flexible  tubing of
heavy-duty fabric.  They are installed with standard  prefabricated entrance
sections and are designed to handle  flow  from  drainage areas of  5 acres or
less.
          3.5.4.2  Applications/Limitations


     Chutes and downpipes often represent key elements  in  combined  surface
control systems.  They are especially effective  in preventing  erosion  on  long,
steep slopes, and can be used to channel storm run-off  to  sediment  traps,
drainage basins, or stabilized waterways for off-site transport.  However,
they provide only temporary erosion control while slopes are stabilized with
vegetative growth.  Chutes are limited to heads  of about 18 feet  or less
(Schwab et al., 1981).  Also downpipes are limited to drainage  areas five
acres in size.
          3.5.4.3  Design Considerations


     Chutes and downpipes are temporary structures that do not require  formal
design.  General design criteria are presented.in Figures 3-18 (paved chute),
3-19 (rigid downpipe), and 3-20 (flexible downpipes).

     Chutes are designed to handle flows based on two basic size groups.
Paved chutes of size group A have the following three qualifications:

     •  Height (H) of dike at entrance =1.5 feet minimum

     •  Depth (D) of chute down the slope = 8 inches minimum

     •  Length (L) of inlet/outlet sections = 5 feet minimum
                                     3-57

-------
                                       FIGURE 3-18.
                               PAVED CHUTE (OR FLUME)
         •L —*L- Top of earth dik
         —ป|/yU—     top ฐ* lin'
Dimen-
sion
^min
dmin
'•min
Size Group
A
1.5'
8"
5'
B
2.0'
10"
6'
                                     Slope varies, not
                                     steeper than 1.5:1
                                     & not flatter than
                                          20:1
       Undisturbed soil or
       compacted fill
                                                                ifSfls?^y i .5' *8
                                                                ll^H—Vf
                                                                —J U— 6" \ |
                                                                    '         >
                Profile
L
 2'
T
L
 2'
T
                                       Place 3" layer of sand
                                for drainage under outlet as show
                                for full width of structure
                                                                       Riprap is 9" layer of
                                                                       6" min. rook or rubble


— z. — ป•

< — Min slope
1/4" per ft
t
o
1

o5ซo
                                                                       &. ** —   __  *f
                                                                                      7'
                                                                           *  i i
                                                                           o  T  a:
                                                                              o.
                                                                              2
                                                                          6' min.
                                                                                      7'
                                                                 Toe of slope
                                       Plan view
                                                                       2 1/2" min.

                                                                  Section B-B.
Source: USEPA, 1976
                                             3-58

-------
                                          FIGURE 3-19.
                                       RIGID DOWNPIPE
                               $$%>ป
Discharge into a               ^/^W^f^,
stabilized watercourse,      ^^'"''^''^r^M^-^
sediment trapping device, dj^&t0MMw*^ ^
                        i*.y .':*s*<.iT"v.'./-.v.'.;fllllllllli™ >..
or onto stabilized
                 •       • ' t *  .. , * • t   ff '',^PC^\\HF/> * ' f^ m *J f *. -^* • *™ . •*• i'ltft
            ':..       -^^vu^.>-6^^.^,^^^S^
                                                                        Cutaway used
                                                                        to show inlet
                                                                              Earth dike
            Length as necessary to go
            thru dike
                       2:1
                           Profile
 4' min.
 @ less than 1% slope
                                                    ซ=ฃ>+12"
                                               Standard flared
                                               entrance section
                                                                                      o
                                                                                   O~0~o
                                                                          ."•"'. C * i-.0., " i ฐ
                                                                          ||l1|'i- '; •• c"c_"^(
                                                                          .'.. *
                                                                  •i,; ]v r\ " -,  ซ>   Ve  ••• '


                                                                  'll'ii ฐ r i ฐ c "r  ฐ


                                                              "oiJ^LlD^
                                                                                            ปi. ,'j
                                                                                            ' ...I
                                                                                  c' I:-1;"
                                                          Riprap shall consist of 6"
                                                          diameter stone placed as shown.
                                                          Depth of apron shall  equal the pipe
                                                          diameter and riprap shall be a min-
                                                          imum of 12" in thickness.

                                                                  Riprap apron plan
Source: USEPA, 1976
                                              3-59

-------
                                           FIGURE 3-20.
                                      FLEXIBLE DOWNPIPE
   Discharge into a
   stabilized watercourse,
   sediment trapping device,
   or onto a stabilized area.
                                                                  NOTE: Size designation is:
                                                                          PSD-Pipe Diam. (ex., PSD-
                                                                          18=Pipe Slope Drain with
                                                                          18" diameter pipe)
                                       •??•  -y •:• • ••••''?'.' '•• ••'$•'••• 's'-'--^''-^-?*
-------
Similarly, chutes of size group B meet the following criteria:
     •  H = 2 feet minimum
     •  D = 10 inches minimum
     •  L = 6 feet minimum.
Table 3-10 below presents the bottom width and maximum drainage area for
designed chutes of the two size groups.
                                  TABLE 3-10.
         BOTTOM WIDTHS AND MAXIMUM DRAINAGE AREAS FOR TEMPORARY CHUTES

Size
group
A-2
A-4
A-6
A-8
A-10
Bottom
width, D
(ft)
2
4
6
8
10
Max imum
drainage
area (acres)
5
8
11
14
18
Size
group
B-4
B-6
B-8
B-10
B-12
Bottom
width, D
(ft)
4
6
8
10
12
Max imum
drainage
area (acres)
14
20
25
31
36

 Source:  USEPA, 1976.
     If 75 percent or more of the drainage area has good vegetative cover
(established grasses and/or shrubs) throughout the design life of the chute,
the drainage areas listed in Table 3-9 may be increased by 50 percent.  If
75 percent or more of the drained area has a mulch cover throughout the
structure's life, the areas may be increased by 25 percent (USEPA, 1976).

     For downpipes (Figures 3-19 and 3-20), the maximum drainage area is
determined from the diameter of the piping, as'follows (USEPA, 1976):
Pipe/Tubing Diameter, D (Inches)
               12
               18
               21
               24
               30
Maximum Drainage Area (Acres)

            0.5
            1.5
            2.5
            3.5
            5.0
                                     3-61

-------
          3.5.4.4  Construction/Implementation Considerations
     Construction methods for chutes and downpipes are  inexpensive  and  quick.
No special materials or equipment are required.  Temporary downpipes may be
constructed by joining half-round sections of bituminous  fiber  or concrete
pipe.  These structures may be quickly constructed for  emergency situations
when downslope ditches or waterways overflow during  severe storms and  threaten
to erode the base of disposal fill areas.

     General construction criteria for both rigid and flexible  downdrains
include the following:

     •  The inlet pipe shall have a slope of 3 percent  or greater.

     •  For the rigid downpipe, corrugated metal pipe with watertight
        connecting bands shall be used.

     •  For the flexible downpipe, the inlet pipe shall be corrugated metal;
        the flexible tubing shall be the same diameter  as the  inlet pipe,
        securely fastened to the inlet with metal strapping  or  watertight
        connecting collars.

     •  A rip-rap apron shall be provided at the outlet;  this  shall consist  of
        6-inch diameter stone placed as shown in the  figures.

     •  The soil around and under the inlet pipe and  entrance  sections  shall
        be hand-tamped in 4-inch lifts to the top of  the  earth  dike.

     Paved chute construction considerations include  the  following  (USEPA,
1976):

     •  The structure shall be placed on undisturbed  soil or well compacted
        fill.

     •  The lining shall be placed by beginning at the  lower end and
        proceeding upslope; the lining shall be well  compacted,  free of voids,
        and reasonably smooth.

     •  The cut-off walls at the entrance and at the  end  of  the asphalted
        discharge aprons shall be continuous with the lining.

     •  An energy dissipator (rip-rap bed) shall be  used  to  prevent erosion  at
        the outlet.
          3.5.4.5  Operation, Maintenance,  and Monitoring


     Periodic  inspections  and maintenance  are necessary  to  ensure  proper
performance of chutes  and  downpipes.   Downpipes  should be  inspected after each
                                      3-62

-------
storm.  These structures are  intended  for  temporary  use  and  should  be  removed
when no longer needed.


          3.5.4.6  Costs


     Costs of chute and downpipe construction  and maintenance  will  vary,
depending on the size (length, width,  depth) of  the  structure  and the  type  of
liner and pipe material used  (corrugated metal,  flexible drainpipe,  bituminous
fiber, PVC).  Unit costs associated with these temporary structures  are
presented at the end of the chapter in Table 3-13.


     3.5.5  Seepage Basins and Ditches


          3.5.5.1  General Description


     Seepage or recharge basins and ditches are  used to  discharge water
collected from surface water diversions, groundwater pumping or  leachate
treatment to groundwater.  They may also be used in  in-situ  treatment  to  force
treatment reagents into the subsurface.


          3.5.5.2  Applications/Limitations
     Seepage basins and ditches are most effective  in highly  permeable  soils
so that recharge can be performed.  They are not  applicable at  sites  where
collected run-off or groundwater is contaminated.  Many basins  and ditches  are
used in areas with shallow groundwater tables.  Very deep basins or trenches
can be hazardous.

     Seepage ditches distribute water over a larger area than achievable  with
basins.  They can be used for all soil where permeability exceeds about
0.9 inches per day.


          3.5.5,3  Design Considerations


     The major factors to consider in the design  of seepage basins and  ditches
include (Healey and Laak, 1974):

     •  Amount of waste to be discharged

     •  Permeability of the surrounding soil

     •  Highest elevation of the water table

     •  Depth to impermeable stratum.


                                     3-63

-------
     There is considerable flexibility in the design of seepage basins and
ditches.  Figures 3-21 through 3-24 illustrate possible design variations.

     A seepage basin (Figure 3-21) typically consists of the actual basin, a
sediment trap, a by-pass for excess flow, and an emergency overflow.  A
considerable amount of recharge occurs through the sidewalls of the basin, and
it is preferable that these be constructed of pervious material.  Gabions are
frequently used to make sidewalls.  An alternative design for a seepage basin
is shown in Figure 3-22.  This is not designed for an intensive recharge as
the previously discussed system, and is usually used where the aquifer is
shallow.

     Seepage ditches illustrated in Figures 3-23 and 3-24 are generally used
in parallel.  Run-off is disposed of by a system of drains set in ditches of
gravel.  Depth and spacing of drains depends on soil permeability.  A minimum
depth of 48 inches is generally recommended, and ditches are rarely less than
10 feet apart.  The ditches are backfilled with gravel, on which the distri-
bution line is laid.  Sediment is removed prior to discharging run-off into
the seepage ditches by use of a sediment trap and distribution box.  The effi-
ciency of the seepage area can be increased by interconnecting two trenches by
a continuous 12-inch gravel bed, as shown in Figure 3-24 (Tourbier and
Westmacott, 1974).


          3.5.5.4  Construction/Implementation Considerations


     Seepage basins and ditches are constructed with well-established tech-
niques and procedures.  Much of the equipment and material necessary will be
found on-site.  Such things as piping and gravel may need to be specially
ordered.

     Dense turf on the side slopes of these basins will prevent erosion and
sloughing and will also allow a high infiltration rate.  Prevention of scour
by the inlet is an important consideration since it can significantly reduce
maintenance requirements.  This can be accomplished by a "hydraulic jump" or
an impact stilling basin before water flows into the recharge basin.  Perco-
lation can be improved by construction of gravel-filled trenches along the
basin floor, as shown in Figure 3-21 (Toubier and Westmacott, 1974).


          3.5.5.5  Operation, Maintenance, and Monitoring


     Seepage systems can perform reliably only if they are well-maintained.
Seepage basins and ditches are extremely susceptible to clogging by solids and
biological growth and need to be periodically monitored and cleaned if
necessary.
                                     3-64

-------
                                   FIGURE 3-21.
          SEEPAGE BASIN; LARGE VOLUME, DEEP DEPTH TO GROUNDWATER
             Sediment
               trap
                                           Seepage basin   Overflow
                             Bypass
                                   FIGURE 3-22.
                SEEPAGE BASIN; SHALLOW DEPTH TO GROUNDWATER
                Seepage
                  basin
                                                        Dense turf
Gravel filled
  trench
Source: Tourbier and Westmacott, 1974
                                      3-65

-------
                            FIGURE 3-23.
                           SEEPAGE DITCH
                         10' (min.)
                                                           48" min.
                                             18" (max.)
                             FIGURE 3-24.
         SEEPAGE DITCH WITH INCREASED SEEPAGE EFFICIENCY
                                                              2" hay
                                                              or straw
                                                          Tile,
                                                       perforated
                                                        bitumen
                                                        fiber or
                                                       p.v.c. pipe
      18" max.
                         1 10' min.
Source: Tourbier and Westmacott, 1974
                                3-66

-------
          3.5.5.6   Costs
     The costs of  seepage  structures  are  highly variable depending on type,
depth,  length, necessary materials, and construction technique.   Unit costs
for excavated structures and  associated material are tabulated in Table 3-13.
     3.5.6   Sedimentation  Basins/Ponds


          3.5.6.1   General  Description


     Sedimentation  basins  are  used  to control  suspended solids entrained in
surface  flows.  A sedimentation basin is  constructed  by placing an earthen dam
across a waterway or natural depression,  or  by excavation,  or by a combination
of both.  The purpose of installing  a sedimentation basin is to impede surface
run-off  carrying solids, thus  allowing  sufficient  time for the particulate
matter to settle,


          3.5.6.2   Applications/Limitations
     Sedimentation basins  are  usually  the  final  step  in control  of diverted,
uncontaminated,  surface  run-off,  prior to  discharge.   They are especially
useful in areas  where  there  exists a high  silt or  sand content in the surface
run-off.  They are an  essential part of any  good  surface flow control system.


          3.5.6.3  Design  Considerations


     The removal of suspended  solids from  waterways is based  on  the concept of
gravitational settling of  the  suspended material.

     A typical design  for  a  sedimentation  basin  embankment is illustrated in
Figure 3-25.  The major  components include a principal and emergency spillway,
an anti-vortex device  and  the  basin.

     The principal spillway  consists of a  vertical  pipe or riser jointed to a
horizontal pipe  (barrel) that  extends  through the  dike and outlets beyond the
water impoundment.  The  riser  is  topped by the anti-vortex device and trash
rack which improve the flow  of water into  the spillway and prevent floating
debris from being carried  out  of  the basin.   The  riser should be watertight
and, except for  the dewatering opening at  the top,  should  not have any holes,
leaks, or perforations.  The riser base should be  attached to a  watertight
connection and have sufficient weight  to prevent  flotation of the riser.

     The water discharged  from the sediment  basin  through  the principal spill-
wAy should be conveyed in  an erosion-free  manner  to an existing  stable stream.

                                     3-67

-------
                                   FIGURE 3-25.
                TYPICAL DESIGN OF A SEDIMENT BASIN EMBANKMENT
Anti-vortex Device

    Water Surface (design)
                                               Emergency Spillway Crest
                              Anti-seep Collars

                                      Pipe Conduit or Barrel
                               EMBANKMENT


Thus, at the discharge  end  of  the  spillway pipe,  an impact basin, rip-rap,
excavated plunge pools,  and revetment  should be constructed as protective
measures against scour.

     Emergency spillways  are also  suggested in the design of a sediment basin.
They are provided to convey large  flows  safely past an earth embankment, and
they are usually open channels excavated in earth, rock, or reinforcement
concrete.

     The size of a  sedimentation basin is determined from characteristics of
flow such as the particle size distribution for suspended solids, the inflow
concentration, and  the  volumetric  flow rate.  To  calculate the area of the
sedimentation basin pond  required  for  effective removal of suspended solids,
the following data  on the flow characteristics are needed:

     •  The inflow  concentration of  suspended solids.

     •  The desired effluent concentration of suspended solids.  The desired
        effluent concentration is  usually regulated by local and/or Federal
        government  authorities.

     •  The particle size distribution for suspended solids.

     •  The water flow  rate (Q)  to the pond.  For a pond receiving direct
        run-off, the run-off volume  over a certain period of time must be
        determined.  As an  example,  EPA has chosen the 10-year, 24-hour
        precipitation event as a design criteria for the overflow rate
        determination.
                                      3-68

-------
     The steps in calculating the required area of the  sedimentation basin  are
as follows:

     (1)  Calculate the removal efficiency of the pond  by using  the  following
          formula:


                                             106/(C1 -1)
                 R (% solids removed) = 1 -  —7	 x  100
                                             iob/(c2 -i)


          Where:
                 GI = solids concentration in influent  (mg/1)
                 €„ = solids concentration in effluent  (mg/1)

     (2)  Determine the smallest size of particle that must be removed  to
          achieve the required removal efficiency.  The size of  the removed
          particle can be graphically obtained from a particle size distri-
          bution  for the suspended solid in the influent to the  pond.
          Figure  3-26 shows a typical "particle size distribution" graph.

     (3)  Once the particle size is chosen, the settling velocity associated
          with the selected particle size can then be calculated using  Stoke1s
          law:
          where:
                   V  = settling velocity (cm/sec)            _
                    g = gravitational acceleration (981 cm/sec )
                      = kinematic viscosity of the fluid (cm/sec )
                    s = the specific gravity of the particle
                    D = diameter of the particle (cm), assumed to be a sphere

     (4)   With the obtained water flow rate to the pond and the settling
          velocity, surface area of the pond can then be calculated as
          follows:
                                         V
                                          s

          where:
                   A = required area of the pond (m )
                   Q = the volumetric flow rate thorugh the pond
                       (overflow rate) (m /sec)
                  V  = the critical settling velocity (m/sec)
                   O

     (5)   The  final step is to multiple the required area of the pond by a
          safety  factor of 1.2 to account for non-ideal settling:

                           A ,.      = 1.2 A    .   ,
                            adjusted        required

                                     3-69

-------
    0.
    <
    tc
    o

    z
    g


to  ^
N  00
m  g

iu  I-
tc  w
    (0

    UJ

    o


    cc
ฃ ซ

ฃ 9ฐ
c ซ•>
                                                                                                   S
                                                                                                   o
                                                                                    .8

                                                                                                    8



                                                                                                    S
aa
                                   s
                                                                                   s
                                                       3-70

-------
     The efficiency of sedimentation ponds varies considerably as a function
of the overflow rate.  Sedimentation ponds perform poorly during periods of
heavy rains and cannot be expected to remove the fine-grained suspended solids
(Rogoshewski, 1978).  If the sedimentation pond is expected to remove sedi-
ments that may have been contaminated by waste materials, consideration should
be given to improving removal efficiencies by modifying basin or outlet
design.  One such modification to the outlet structure is shown in Figure
3-27.  It is essentially a dual media sand filter surrounding the riser pipe.
Other possible design modifications include the use of baffles, extra wide
inflow or outflow weirs, energy dissipators, and siphon drawdown riser pipes
(Rogoshewski, 1978).  Alternatively, a two-pond system could be considered
that should significantly increase removal efficiencies.

     The quantity of material to be stored is also an important consideration
in the construction of the sedimentation basin.  The required storage capacity
can be calculated by multiplying the total area disturbed by a constant sedi-
ment yield rate.  Table 3-11 shows the storage requirements for some States.
In many States, there is a requirement to clean the sedimentation basin when
the sediment accumulation reaches a specified limit imposed by the State.  As
an example, in West Virginia, the law requires cleaning of the sedimentation
pond when the level of accumulation is 60 percent of the design capacity.


          3.5.6.4  Construction/Implementation Considerations


     Prior to the construction the areas under the embankment and any
structural works shall be cleared, grubbed, and stripped of topsoil to remove
trees, vegetation, roots, or other objectionable material.

     Fill material for the embankment should be clean mineral soil, free of
roots, woody vegetation, oversized stones, rocks, or other objectionable
material.  Areas on which fill is to be placed should be scarified prior to
placement of fill.  The fill material should contain sufficient moisture so
that it can be formed by hand into a ball without crumbling to facilitate
proper compaction.  Compaction shall be obtained by routing the hauling
equipment over the fill so that the entire surface of the fill is traversed by
at least one wheel or tread track of the equipment, or by using a compactor.

     The riser of the principal spillway should be securely attached to the
barrel by a watertight connection and the barrel and riser should be placed on
a firm compacted soil foundation.  The base of the riser should be firmly
anchored to prevent floating.  Previous materials such as sand, gravel, or
crushed stone should not be used as backfill around the barrel.  Fill material
(minumum of 2 feet) is placed around the pipe in thin layers and compacted by
hand at least to the same density as the embankment before crossing it with
construction equipment.

     Design elevations, widths, entrance and exit channel slopes are critical
to the successful operation of the spillway and should be adhered to closely
during construction.
                                     3-71

-------
  2
  z
  o
  lo
  o w

  wQ
  "' m

S3 i Q
N < 2
co 2 uj
uj O 0-
cc p w

O m w
E > UJ
  Z O
  O O
  O O
  gp
  O
  O
                              3-72

-------
                                  TABLE 3-11.
         DESIGN STORAGE CAPACITY REQUIREMENTS FOR SEDIMENTATION BASINS
          State                                    Requirement
     Maryland                                0.5 inches/acre drained
                                             0.2 inches/acre drained

     Kentucky                                0.2 acre-ft/acre disturbed

     West Virginia                           0.125 acre-ft/acre disturbed
                                               (60 percent )

     Pennsylvania                            V = (AIC) + (AIC/3)
                                             V = volume (ft )
                                             A = area drained
                                             I = rainfall/24 hours
                                             C = run-off constant
 To be cleaned when storage capacity drops below 0.2 inches/acre drained.
2
 To be cleaned when sediment accumulation approaches 60 percent design
 capacity.

Source:  USEPA, 1976
     The embankment and emergency spillway of the sediment basin should be
stabilized promptly with temporary vegetation (Virginia SWCC, 1980).


          3.5.6.5  Operation, Maintenance, and Monitoring


     The embankment of the basin should be checked regularly to ensure that it
is structurally sound and has not been damaged by erosion or construction
equipment.  The emergency spillway should also be checked regularly to ensure
that its lining is well established and erosion-resistant.  The basin should
be checked after each runoff-producing rainfall for sediment cleanout.
                                     3-73

-------
          3.5.6.6  Costs
     The costs for sedimentation basins vary with size, location, and  con-
struction method.  Table 3-13 at the end of this chapter lists costs for
equipment, materials, and construction needed for installation of sedimen-
tation basins.
     3.5.7  Levees and Floodwalls


          3.5.7.1  General Description


     Levees are earthen embankments that function as  flood protection  struc-
tures in areas subject to inundation from tidal flow  or riverine  flooding.
Levees create a barrier to confine floodwaters to a floodway and  to  protect
structures behind the barrier.  Floodwalls perform much the same  function  as
levees, but are constructed of concrete.

     For hazardous waste sites, levees and floodwalls help to control  major
losses of waste and cover material and prevent massive leachate producton  and
subsequent contamination from riverine or tidal flooding.


          3.5.7.2  Applications/Limitations
     Flood containment levees are most suitable  for  installation  in  flood
fringe areas or areas subject to storm tide flooding, but not  for  areas
directly within open floodways (Tourbier and Westmacott, 1974).

     Flood containment levees may be constructed as  perimeter  embankments
surrounding disposal sites located in floodplain fringe areas, or  they may be
installed at the base of landfills along slope faces that are  subject to
periodic inundation.  Levees serve to protect land disposal  sites  from  flood-
waters, which may erode cover materials and transport waste materials off-
site, or which may add water to waste materials  and  thus increase  hazardous
leachate production.

     Because of the relatively long, flat  side slopes of levees,  an  embankment
of any considerable height requires a very large base width.   For  locations
with limited space and fill material, or excessive real estate costs, the use
of concrete floodwalls is preferred as an  alternative to levee construction.
                                     3-74

-------
          3.5.7.3  Design  Considerations


     To provide  adequate flood  protection,  levees  should  be constructed to a
height capable of containing  a  design  flood  of  100-year magnitude.   Levees
designed  to protect  disposal  areas  from maximum flood levels of lesser magni-
tude/greater  frequency  (e.g., 50-year  flood) may not  provide sufficient flood
protection, particularly for  sites  known  to  contain  large quantities of
hazardous wastes.  Elevation  of  100-year  base  flood  crests can be  determined
from floodplain  analyses typically  performed by state or  local flood control
agencies.

     Figure 3-28 presents  design features of a  typical levee constructed at
the toe of a  landfill slope.  This  design is appropriate  for new or  uncom-
pleted disposal  sites;  filled wastes may  eventually  be placed on the inboard
slope of  the  levee.  Where  levee construction  is impractical due to  lack of
soil or limited  space,  perimeter protection  of  vulnerable landfill  slopes may
be afforded by the design  shown  in  Figure 3-29.  A minimum top width of
10 feet is recommended  for  most  levees; this will  permit  easy access for
construction  and maintenance  equipment (Linsley and  Franzini,  1979).

     Floodwalls  are  designed  to  withstand the hydrostatic pressure  exerted by
water at  the  design  flood  level.  They are  subject to flood loading  on one
side only; consequently, they need  to be  well  founded (Tourbier and
Westmacott, 1974).   Figure  3-30  presents  typical floodwall sections.   Like
levees, floodwalls may  require  subsurface cut-offs and interior drainage
structures to handle excessive  seepage or backwater  flow.


3.5.7.4   Construction/Implementation Considerations


     Levees are generally  constructed of  compacted impervious  fill.   Special
drainage  structures  are often required to drain the  area  behind the  embank-
ment.   Ideal  construction of  levees is with erosion-resistant,  low perme-
ability soils, preferably  clay.  Most levees are homogeneous embankments; but
if impermeable fill  is  lacking,  or  if seepage through and below the  levee is a
problem,  then construction  of a  compacted impervious  core or sheet-pile
cut-off extending below the levee to bedrock (or other impervious  stratum) may
be necessary.  Figure 3-31  depicts  these  two special  cases.   Excess  seepage
through the levees should be  collected with gravel-filled trenches or tile
drains along  the interior of  the  levee.   After  draining to sumps,  the seepage
can be pumped out over  the  levee.   Levee  bank slopes,  especially those con-
structed  of less desirable  soils  (silt, sands),  should be protected  against
erosion by sodding,  planting of  shrubs and trees,  or  use  of stone  rip-rap
(Linsley  and  Franzini,  1979).

     Fill material used in  levee  construction should  be compacted  in layers,
with the  least pervious layer along the river side of the levee.  Because the
use of levees will reduce  floodplain storage capacity,  fill material  should  be
dredged from  borrow  pits within  the floodplain  to  provide alternate  storage
volume for floodwaters.  This measure will help control rising floodpeaks and

                                     3-75

-------
                                     FIGURE 3-28.
                    TYPICAL LEVEE AT BASE OF DISPOSAL SITE
             Elevation: Minimum 2'
             Above 100 Year Flood
                       4
                   II
                                                                                  Fill
^^r
Compacted Impervious
Soil Levee

i ' \
' 1 t
| | l—_ v Min. Stripping
j f 1 Imoervious Groundwatar Cutoff Trench
! | May Be Required in Certain Soils
                                     FIGURE 3-29.
                    PERIMETER FLOOD  PROTECTION STRUCTURE
                                                                       Final Soil Cover-
Existing Grade
                                  Compacted Impervious Soil
                             Elevation: Minimum 2'
                             Above 100 Year Flood
                                                                      Verify Existing V Thick
                                                                      Clay Cover Soil (Typ.)
                               — V Key Into Impervious Soil
                                         3-76

-------
                                         FIGURE 3-30.
                          SOME TYPICAL FLOODWALL SECTIONS
Simple cantilever and sheet pile
                                        Adequate foundation
Gravity
                                                                              Earth
                                                                                fill
  Cellular
           Slab and buttress
   Buttress
T-canti lever
       Source: Linsley and Franzini, 1979
                                             3-77

-------
                                    FIGURE 3-31.
                              LEVEE CONFIGURATIONS
                              Levee with Impervious Core
            3:1  Max
                                    Compacted
                                    Impervious
                                        Fill
3:1 Max
                                   c:Vป ป*'-"<*ป%•  Rock or Impervious Stratum ;^V-
                              Levee with Cut-Off and Drain
     Filter Drain
                                      Compacted Impervious Fill
 LOW PERMEABILITY
   Blanket
                                              Sheet Pile Cut Off
•• * •ป._ป• TTT^T:—' 	ซ'ป'.ป i——•—* - ' < ซ4.>ปซ  * t  •<
\\  Impervious Stratum  '-\\l\'**-/."**" iv;V*::-:*ป"•
Source: Tourbier and Westmacott, 1974
                                       3-78

-------
prevent an  increase  in depth  of  downstream  flood  stage  (Tourbier  and Westmacott,  1974)

     Storm  run-off from  precipitation  falling  on  the  drainage  area behind the
levee may cause backwater  flooding.  To handle  such  interior drainage,  upslope
interceptor ditches, diversions, or grassed waterways can  be used  to channel
run-off to  downslope holding  basins (for  subsequent  pumping) or to off-site
streams for natural  gravity discharge.  Another method  to  handle backwater
flow is the installation of pressure conduits  (with  upslope intake works)  that
discharge beneath the levee.  These conduits should  be  equipped with tidal
gates or backwater valves  to  prevent back-flow and regulate discharge.

          3.5.7.5  Operation, Maintenance,  and Monitoring


     Levees are normally constructed for  long-term flood protection but  they
require periodic inspection and maintenance to assure proper functioning.   It
is especially important that  levees be inspected  during and after  storm
activity.


          3.5.7.6  Costs


     Costs  associated with constructing and maintaining levees will depend on
site-specific design variables, availability of suitable embankment soil,  and
the local frequency  and magnitude of flooding.  If backwater flooding or  seep-
age is a problem, then special structures must be included in  the  construction
plan.  Regular annual inspection for evidence  of  bank caving,  bank sloughing,
erosion, and foundation settlement will also increase associated costs.   Unit
costs relating to levee construction and maintenance  are included  in Table
3-13 at the end of this chapter.


     3.5.8  Selection/Evaluation Criteria


     The surface water diversion and containment methods described in this
section include a variety of  well-established methods.  Many of these methods
are intended for short-term use as indicated in Table 3-12, and are neither
effective nor reliable for use as long-term remedial measures.  All of  the
diversion and containment methods described require  frequent inspection,
maintenance, and performance  checks to ensure  continuous reliability.  Weekly
or even daily inspection may  be required for temporary measures, particularly
during periods of heavy rainfall.  Permanent measures require  somewhat  less
frequent inspections.  Operation and maintenance  requirements  for  these
measures are relatively simple (e.g., mowing grasses, removing sediments).
However, failure of  such surface control measures as floodwalls can be costly.

     Proper design is critical to the effectiveness and reliability of
diversion and collection methods.  This often requires  the use of  several
                                     3-79

-------
                                  TABLE 3-12.
      NORMAL DURATION OF SURFACE WATER DIVERSION AND COLLECTION MEASURES
      Technology                      Duration of Normal Use



Dikes and Berras                       Temporary
Channels (earthen and CMP)            Temporary
Waterways                             Permanent
Terraces and Benches                  Temporary and Permanent
Chutes                                Permanent
Downpipes                             Temporary
Seepage Ditches and Basins            Temporary
Sedimentation Basins                  Temporary
Levees                                Temporary
Floodwalls                            Permanent
control measures in an integrated system.  Though detailed design work  is
often not necessary for these systems, qualified engineering  and proper
construction practices are imperative in implementing effective controls.

     All of the methods described in this  section can be  easily and  rapidly
implemented in the field using readily available equipment and materials and
local contractors.  It is important to ensure  that only proper materials and
qualified, experienced contractors are used.   Improperly  installed systems  can
be detrimental to the integrity of a waste site.  Construction seldom poses
significant risk to worker health and safety.

     The beneficial results from surface water controls are almost immediately
evident and for this reason they are frequently implemented as emergency
measures to contain and control run-off.
     3.5.9  Costs
     The costs of excavation, hauling, Backfill,  grading  (spreading,  compac-
tion), vegetative stabilization, and maintenance  are  common  to  almost all
surface flow control  techniques.  Other  costs  associated  with surface water
                                     3-80

-------
diversion/collection structures include those  for ditch linings, rip-rap  slope
protection, soil testing, corrugated metal pipe, sheet piling, backflow
valves, and sumps.  Table 3-13 summarizes these unit costs and the  structure
construction they apply to.

     All cost estimates should be determined on a site-specific basis, con-
sidering the specific structures to be installed, all associated earthwork,
and any special appurtenances that may be required.  A general methodology for
estimating costs for construction of surface water diversion/collection struc-
tures will contain the following elements:

     •  Determine source of required earth fill (on-site vs. off-site) and
        hauling distances

     •  Determine amount of fill required (cubic yards)

     •  Determine type and quantity of other materials required (cubic yards
        of pipe, square feet of rip-rap, etc.)

     •  Determine costs of installation or placement of these materials using
        unit costs

     •  Determine costs of required stabilization for earthen structures
        (levees, berms, etc.) based on area in square yards to be stabilized;
        revegetation, rip-rap, or gravel stabilization

     •  Determine required maintenance or repair costs for a given  time period
        based on reasonable assumptions; for example:  assuming the diversion
        requires rebuilding (new fill and compaction) two times/year after
        major storms, then costs will be....

     •  Add all calculated costs for total estimated construction and main-
        tenance expenditures.

Costs are derived simply by multiplying unit costs (shown in Table 3-13) by
required quantities of the material or service.  These costs will give gross
estimates only; they are to be used as general guides for the decisionmaker in
evaluating alternative remedial action strategies.
                                     3-81

-------
                                  TABLE 3-13.
                 1985 UNIT COSTS ASSOCIATED WITH SURFACE WATER
                      DIVERSION AND COLLECTION STRUCTURES
     Description
Applicable,
Structures
    Cost
Source of
Cost Data
Excavation, hauling,
  grading (spreading
  and compaction)

Trench excavation
•  Loam, sand, and loose
   gravel
     1-6 ft deep, 1/2:1 sides
     6-10 ft deep

•  Compacted gravel and
   till
     1-6 ft deep, 1/2:1 sides
     6-10 ft deep

Building embankments;
  spreading, shaping,
  compacting

•  Material delivered by
     scraper
•  Material delivered by
     back dump

Placement of ditch
  liner pipe, 1/3 section

     15 in. radius

     18 in. radius

     24 in. radius
    All
D/B; D/D/W; BT;
L; DT/B
    See Table 3-3
    All
D/D/W; drainage
benches; C/D
                 $0.84
                 $0.84
                 $0.84
                 $0.84
      - $1.00/yd;
      - $0.99/yd~
      - $1.18/yd;
      - $1.06/yd~
$0.42 - $0.83/yd~
                f
$0.89 - $1.31/yd'




$15/ft

$20/ft

$30/ft
    2
    2
    2
    2
                                        2

                                        2
                                         2

                                         2

                                         2
                                                            (continued)
                                     3-82

-------
TABLE 3-13.  (continued)
Description
Catch basin sump,
3 ft x 4 ft x 1.5 ft
Corroguated galvanized
steel underdrain pipe,
asphalt-coated ,
perforated;
12 in. diameter, 16 gauge
18 in. diameter, 16 gauge
Corrugated galvanized
metal pipe, with paved invert
18 in. diameter, 14 gauge
36 in. diameter, 12 gauge
48 in. diameter, 12 gauge
Steel sheet piling;
15 ft deep, 22 Ib/ft^
20 ft deep, 27 lb/ft,
25 ft deep, 38 Ib/ft
Backflow preventer;
gate valves, auto-
matic operation,
flanged, 10" diameter
Floating baffles
Sump pumps, 10 ft head,
automatic
Bronze
Cast Iron

Applicable. Source of
Structures Cost Cost Data
L; DT/B $217.77 each
DT/B
$21/ft
$30/ft
C/C; SB
$34.12/ft
$86.83/ ft
$65.12/ฃt
L (seepage
control)
$10.65/ft*
$12.35/ft,
$15.70/ftZ
L (drainage $9,250 each
control)
SB $15 - $50/ft
L (backwater
drainage)
$25 - $505 each
$145 - $295 each
(continued)
2

2
2

2
2
2

3
3
3
3
4
3
3

          3-83

-------
                           TABLE 3-13.  (continued)

Description
Applicable
Structures Cost
Source of
Cost Data
Revegetation, mulch-
  ing , maintenance

Loose gravel, excava-
  vation, loading,
  hauling 5 miles,
  spreading and compacting

Stone rip-rap; dumped
  from trucks, machine-
  placed
Soil testing;
  liquid and plastic
   limits
  hydrometer analysis
   specific gravity
  moisture content
  permeability
  Proctor compaction
   shear tests
     triaxial
     direct shear

Temporary Diversion
  Dike

Temporary sediment
  construction, drainage
  area:
    1-25 acres
    50-75 acres
    75-100 acres
    100-125 acres
D/B; D/D/W; BT;
L

All (slope pro-
tection; drain-
age)
     See Table 3-4
All (slope
protection;
channel & outlet
stabilization)

All (preconstruc-
tion evaluation)
$8 - $8.50/yd~

$21/yd3
D/B
$30/test

$50/test
$7.15/test
$65/test
$110 - $120/test

$150 - $280/test
$95 - $260/test

$1.31 - $2.62/
  linear foot
                 $394 - $2,082
                 $3,942 - $6,470
                 $6,470 - $8,340
                 $8,340 - $10,913
2

3
                                        3
                                        3
                                        3
                                        3

                                        3
                                        3
                       5
                       5
                       5
                       5
                                                           (continued)
                                     3-84

-------
                           TABLE 3-13.  (continued)
     Description
Applicable.
Structures
    Cost
Source of
Cost Data
Sediment removal from
  basins
SB
$3.95 - $9.10/yd~
Paved flume, installed
Level spreader con-
struction
C/D; SB
D/B; D/D/W;
BT; C/D
$26.30 - $39.92/yd
$3.23 - $6.47/
linear foot
5
5

 Key:  D/B, dikes and berms; D/D/W, ditches, diversions, and waterways;
       BT, bench terraces; C/D, chutes and downpipes; L, levees;
       DT/B, drainage trenches and basins; SB, sediment basins.

2McMahon, 1984

3Godfrey, 1984

4
 Klikas, C., Environetics, Inc., Bridgeview, IL, personal communication, 1985.

 Virginia SWCC, 1980.  Updated to 1985 dollars using Engineering News-Record
 Construction Index.
                                     3-85

-------
                                  REFERENCES
Brunner, D. and D. Keller.  1972.  Sanitary Landfill Design  and Operation.
SW-65.  USEPA, Washington, DC.  Office of Solid Waste.

Burke, N.R., D.W. Kutnewsky, V.C. Price, and D.H. Gerber.  1976.   Reservoir
Cover and Canalizing Means.  U.S. Patent 3,991,900.

Cope, F.W., G. Karpinski, and R. L. Steiner.   1984.  Use of  Liners  for
Containment at Hazardous Waste Landfills.  Pollution Engineering.   Vol.  XVI
No. 3.  pp. 22-32.

Dial, H.S., H.L. Habegger, and W.B. Kays.  1979.  Floating Cover  for  a  Liquid
Storage Reservoir.  U.S. Patent 30,146.

Ehrenfelder, J. and J. Bass.  1983.  Handbook  for Evaluating Remedial Action
Technology Plans.  EPA-600/2-83-076.  A.D. Little.  Prepared for:   USEPA,
Municipal Environmental Research Laboratory, Cincinnati, OH.

Engineering News-Record.  1983.  ENR Market Trends.  Vol. 210, No.  6.   p.  104.

Engineering News-Record.  1985.  ENR Market Trends.  Vol. 214, No.  6.   p.  51.

Federal Register.  1979.  Hazardous Waste:  Proposed Guidelines and
Regulations and Proposal on Identification and Listing.  Vol.  43,  No. 243.
p. 59011.  December 19.

Fields, T., Jr., and A.W. Lindsey.  1975.  Landfill Disposal of Hazardous
Wastes:  A Review of Literature and Known Approaches.  EPA/530/SW-165.   USEPA,
Office of Solid Waste Management Programs, Washington, DC.

Giltnan, E., F. Flower, I. Leone, and J.  Arthur.   1979.  Vegetation Growth  in
Landfill Environs in Municipal Solid Waste.  In:  Land Disposal Proceedings  of
the Fifth Annual Research Symposium.  EPA-600/9-79-023a.  Municipal
Environmental Research Laboratory, Cincinnati, OH.

Godfrey, R. (ed.) 1984.  1985 Building Construction Cost Data.  Robert  Snow
Means Company, Inc., Kingston, MA.

Healey, K.A. and R. Laak.   1974.  Site Evaluation and Design of Seepage
Fields.  Journal of the Environmental Engineering Division,  ASCE.  October.

Kays, W.B.  1976.  Gas Venting for Floating Covers.  U.S. Patent  3,980,199.

Kays, W.B.  1977.  Roof System Controls  Pollution in Reservoirs.   Water and
Sewage Works.  November.

Linsley, R. and J. Franzini.   1979.  Water Resources Engineering  3rd  ed.
McGraw-Hill Book Company, New York, NY.
                                      3-86

-------
                            REFERENCES (continued)
Lutton, R.  1978.  Selection of Cover  for  Solid Waste  in  Land  Disposal  of
Hazardous Wastes.  In:  Proceedings of the Fourth Annual  Research  Symposium.
EPA-600/9-78-016.  Municipal Environmental Research  Laboratory,  Cincinnati,
OH.

Lutton, R. , G. Regan, and L. Jones.   1979.   Design and Construction of  Covers
for Solid Waste Landfills.  EPA-600/12-79-165.  USEPA  Municipal  Environmental
Research Laboratory, Cincinnati, OH.

Lutton, R.  1982.  Evaluating Cover Systems  for Solid  and Hazardous Waste.
SW-867.  U.S. Army Engineers Waterways Experiment Station.  Prepared for:
USEPA, Municipal Environmental Research Laboratory,  Cincinnati, OH.

McMahon, L.  1984.  1985 Dodge Guide to Public Works and  Heavy Construction
Costs.  McGraw-Hill Information Systems, New York, NY.

Matrecon, Inc.  1983.  Lining of Waste Impoundments  and Disposal Facilities.
SW-870.  Prepared for:  USEPA, Municipal Environmental  Research  Laboratory,
Cincinnati, OH.

Molz, F., S. Van Fleet, and V. Browning.   1974.  Transpiration Drying of
Sanitary Landfills.  Groundwater.  Vol 12, No. 6. pp.  394-398.

Nawrocki, M.  1976.  Removal and Separation  of Spilled  Hazardous Materials
from Impoundment Bottoms.  EPA-600/2-76-245. USEPA,  Cincinnati,  OH.

Rogoshewski, P.  1978.  Construction Source  Sediment Control.  JRB.  USEPA,
Office of Research and Development, Washington, DC.

SAIC.  1985.  Review of a Part B Permit Application  for a confidential  client.
SAIC, McLean, VA.

Schwab, G.O., R.K. Frevert, T.W. Edminster,  and K.K. Barnes.   1981.  Soil and
Water Conservation Engineering.  John Wiley  and Sons,  New York,  NY.

Streeter, V.L. and Wylie, B.  1975.  Fluid Mechanics (6th ed.).  McGraw-Hill
Book Co., N.Y.

Tolman, A., A. Ballestero, W. Beck, and G. Emrich.   1978.  Guidance Manual for
Minimizing Pollution from Waste Disposal Sites.  EPA-600/2-78-142.   USEPA,
Cincinnati, OH.

Tourbier, J. and R. Westmacott.  1974.  Water Resources Protection Measures  in
Land Development—A handbook.  Water Resources Center, University  of Delaware,
Newark, DE.

USEPA.  1976.  Erosion and Sediment Control.  Surface  Mining in  the Eastern
U.S. Vol. 1:  Planning; Vol. 2:  Design.  EPA-625/3-76-006.  Washington,  DC.
                                     3-87

-------
                            REFERENCES (continued)
USEPA.  1985.  Compendium of Costs of Remedial Technologies at Hazardous Waste
Sites.  Prepared for:  Hazardous Waste Engineering Research Laboratory,
Cincinnati, OH, and Office of Solid Waste and Emergency Response, Washington,
DC.

USEPA.  1982.  RCRA Guidance Document for Landfill Design-Liner  Systems  and
Final Cover. Draft.  Office of Solid Waste, Land Disposal Division,
Washington, DC.

Virginia Soil and Water Conservation Commission.  1980.  Virginia Erosion  and
Sediment Control Handbook:  Standards, Criteria and Guidelines.  Richmond, VA.

Wilson, D.G.  (ed.) 1977.  Handbook of Solid Waste Management.   New  York:  Van
Nostrand Reinhold Company, New York, NY.
                                      3-88

-------
                                   SECTION 4

                            AIR POLLUTION CONTROLS


     Air pollution problems at uncontrolled waste sites  are  the  result  of
gaseous emissions and fugitive dusts.

     Gases may be emitted by the vaporization of liquids, venting  of  entrained
gases or by chemical and biological reactions with solid and liquid waste
material.  Volatile organics may be released slowly but  continuously  from
surface impoundments or landfills.

     Fugitive emissions are particulates that are lifted from the  ground by
means of one or more of the following processes:

     •  Wind erosion of exposed waste materials or cover soil

     •  Re-entrainment of particulate matter by vehicular traffic  on  haul
        roads and exposed surfaces

     •  Excavation of waste materials during remedial action.


4.1  Control of Gaseous Emissions to the Atmosphere


     Methods for controlling the release of gaseous emissions to the
atmosphere include covers for control of volatile emissions from impoundments
and active gas collection systems for collection and control of gases
generated in landfills.


     4.1.1  Covers


          4.1.1.1  General Description
     Covers involve the placement of a barrier at the water-air interface to
reduce gaseous emissions.  Lagoon covers, floating immiscible liquids and
floating spheres can all be used for this purpose.

     Floating lagoon covers consist of a synthetic lining placed in one piece
over an impoundment with proper anchoring at the edges and floats to prevent


                                     4-1

-------
the lining from submerging.  Floating lagoon covers have been described fully
in Section 3.2.

     Floating immiscible liquids include a variety of water insoluble
substances, particularly long chain aliphatic alcohols, which form a monolayer
on the surface of an impoundment, and thereby inhibit the volatilization of
water soluble compounds (Vogel, 1985).  Compounds that can be used for this
purpose include:  buryl alcohol, hexadecanol and polydimethylsiloxane (Vogel,
1985; Valsaraj et al., 1985).

     A third type of cover material involves the use of floating polypropylene
spheres which arrange themselves into a closely packed configuration and
thereby reduce emissions of volatile compounds by reducing the exposed surface
area.
          4.1.1.2  Appliations/Limitations


     The various cover materials described above provide temporary methods for
reducing volatile emissions from surface impoundments.

     Floating lagoon covers function as both a surface water control mechanism
as well as a mechanism for controlling gaseous emissions; they prevent
overtopping of the impoundment while retarding volatilization of hazardous
compounds.  Performance of floating lagoon covers is only minimally affected
by wind.  They are suitable to situations where more than a year will elapse
before final closure of the lagoon.  They are not suitable for lagoons with
weak berms or for lagoons located in areas that cannot support heavy con-
struction equipment.  A variety of cover materials are available and the
materials should be selected based on chemical resistance (see Section 3.2).

     Floating polyethylene spheres are capable of reducing volatile emissions
by up to 90 percent.  Polyethylene spheres are compatible with a broad range
of compounds including inorganic acids and bases and most aromatic and
aliphatic organic compounds (Vogel, 1985).

     Floating immiscible liquids are suitable for controlling emissions of
water soluble organics only (Vogel, 1985).  Their effectiveness is dependent
on the formation of a continuous monolayer on the impoundment surface.
The control efficiency for a surface impoundment containing a floating layer
of organics is poor since this prevents formation of the monolayer.  Wave
action also destroys monolayer effectivenes (Vogel, 1985).  Effectiveness is
temporary, and the maximum desirable interval between applications is
estimated to be one to two weeks (Vogel, 1985).
                                     4-2

-------
          4.1.1.3  Technology Selection/Evaluation


     Floating covers should be considered whenever there is a need for
temporary control of volatile emissions from a surface impoundment.  The
available technologies range from use of low cost, floating immiscible liquids
which can be easily emplaced on a surface impoundment for immediate, short-
term emissions control to floating lagoon covers which are considerably more
costly and difficult to install, but result in more reliable and long-term
emissions control.


          4.1.1.4  Cost


     Costs for floating lagoon covers are addressed in Section 3.2.

     Floating spheres are priced according to their diameter. Table 4- shows
approximate 1985 costs for various diameter spheres and the approximate number
of spheres needed per square foot of coverage.
                Table 4-1.  Cost and Coverage for Several Sizes
                            of Polypropylene Spheres

Sphere diameter
(mm)
20
38
45
145
Bulk
Price
$24/1000
$117/800
$46.50/500
$75/50
Number „ required
per ft coverage
230-280
75-85
45-55
4-5
Cost of coverage
$ per ft
5.52-6.72
10.97-12.41
4.19-5.12
6.00-7.50

Source:  Capricorn Chemical Corp., Secaucus, N.J., personal communication,
         July 1985.


     The cost of surfactant layers depends upon the particular surfactant used
and the required thickness of the monolayer.  For example, only 2 x 10   Ib of
hexadecanol would be required to form a suitable monolayer for control of
highly water soluble compounds.  The chemical cost of the monolayer would be
approximately 0.03 cents per square foot per application.
                                     4-3

-------
     4.1.2  Active Interior Gas Collection/Recovery System


          4.1.2.1  General Description


     An active interior gas collection system alters the pressure gradients
and paths of gas migration by mechanical means.  This type of system is
described in detail in Section 6.3.  It typically consists of four components:
gas extraction wells, gas collection headers, vacuum blowers or compressors
and a treatment system.  The centrifugal blowers create a vacuum through the
collection headers and wells to the wastes and the ground surrounding the
wells.  A pressure gradient is thereby established, inducing flow from the
landfill (which is normally under positive pressure) to the blower, creating a
negative, or vacuum pressure.  Subsurface gases flow in the direction of
decreasing pressure gradient (through the wells, the header, and the blower)
and are disposed of by treatment (SCS, 1980).


          4.1.2.2  Applications/Limitations


     Active interior gas collection/recovery systems are used to collect gases
from beneath a landfill surface before they are vented to the atmosphere.
They can be installed at virtually any site where it is possible to drill or
excavate through the landfilled material to the required depth.  Limiting
factors could include the presence of free-standing leachate (i.e., satur-
ation) or impenetrable materials within the landfill.


4.2  Fugitive Dusts


     Commonly used measures for controlling fugitive dusts from inactive waste
piles and active cleanup sites include use of chemical dust suppressants, wind
screens, water spraying and other dust control measures commonly used during
construction.  Each is described below.


     4.2.1  Dust Suppressant


          4.2.1.1  General Description
     Dust suppressants include a wide range of natural and synthetic waste
materials which strengthen bonds between soil particles and hold this
strengthened condition for an appreciable period of time.  A wide variety of
resins, bitumenous materials and polymers are marketed as dust suppressants.
Table 4-2 lists a variety of commerically available formulations along with
                                     4-4

-------
          Table 4-2.  Commercially Available Dust Suppressant Costs,
                       and Recommended Application Rates


Material

cost/acre,
Name

Soil Seal
AMSCO-RES 4281

Supac 8 NP
Flambinder
Genaqua
Curasol
M166 & M167

Coherex CRF
Sherman Process
(no grass seed)
Sherman Process
(with grass seed)
Terra Track I
(1985 $)

1450
2350

4840
62
484
273
891

847
800

800

68
Formulation

Latex acrylic copolymer
Carboxylated styrene-
butadiene copolymer
Nonwoven geotextile
Lignosulfonate
Vinyl acetate resin
Synthetic resin
Latex

Petroleum resin
Straw mulch with
emulsified asphalt
Straw mulch with
emulsified asphalt
Vegetable gum
Applica-
tion con-
centration*

3%
20%

8 oz/yd
17%
10%
3%
7%(MI66) +
0.2%(MI67)
25%
NA

NA

0.3%

Application
rate
i
1.0 gal/yd~
0.6 gal/yd

12-ft foils
0.5 gal/yd2
0.2 gal/yd^
0.3 gal/yd.
0.5 gal/yd
2
0.5 gal/yd
NA

NA
2
1.4 gal/yd

NA = not applicable.
*Percent compound in aqueous solution, unless otherwise indicated.
Source:  Rosbury and James, 1985.
                                     4-5

-------
their approximate costs and application rates which were used to test product
effectiveness.

     Chemical dust supressants are most commonly applied with water wagons
equipped with two to five nozzles that shoot a flat spray behind the vehicle.
The flow-control system is often crude and difficult to regulate, and it is
not usually tied to vehicle speed.  A calibrated spray bar is more suitable
for application of chemical dust suppressants.  Sophisticated systems exist
which allow the operator to specify an application rate and the truck will
automatically regulate the speed and spray rate.  Some bitumens must be
applied with an asphalt distributor because the material must be heated before
application (USEPA, 1985).


          4.2.1.2  Applications/Limitations


     Dust suppressants are used primarily to temporarily bind soil particles
and reduce fugitive dust emissions from inactive waste piles.  Effectiveness
of a dust suppressant is dependent upon maintaining the soil-chemical crust.
Emerging weeds and any type of disturbance from traffic will break this crust.
Preemergent weed control may be used before applying dust suppressant.  If
undisturbed, dust suppressants can be expected to be 100 percent effective for
a period of 1 to 4 weeks using the concentrations shown in Table 4-2,
depending upon the formulation.  Control efficiencies decline thereafter
(Rosbury and James, 1985).  Dust suppressants may also be used to control dust
from active work areas (e.g., haul roads), although they are less effective
for this application and require frequent reapplication.


          4.2.1.3  Technology Selection/Evaluation


     Use of dust suppressant provides an effective means for temporary control
of fugitive dust emissions. They are reliable as a short-term control measure
but must be periodically reapplied to provide long-term fugitive dust control.
Application is straightforward and can be accomplished quickly.  The dust
suppressants are simply sprayed on the area of concern.  There is the
potential for secondary impacts (soil and groundwater contamination) from the
use of certain chemical dust suppressants which contain toxic substances.
          4.2.1.4  Costs
     Table 4-2 summarizes the costs of various dust suppressants.  Costs for
chemical dust suppressants range from $68/acre for a natural vegetable gum to
$2,350/acre for carboxylated styrene-butadiene copolymer.  Use of nonwoven
geotextile is considerably more costly than chemical dust suppressants.
Application of this material for dust control can be expected to cost
$4,840/acre.
                                     4-6

-------
     4.2.2  Wind Fences/Screens


          4.2.2.1  General Description


     A wind fence is a porous screen which takes up or deflects a sufficient
amount of wind so that the wind velocity is lowered below the threshold
required for initiation of soil movement. Wind screens are typically 4 to 10
feet high and are composed of polyester or other high strength material.


          4.2.2.2  Applications/Limitations


     Wind screens are used to reduce wind velocity and control fugitive dusts.
 Tests conducted by EPA on the efficiency of wind screens in controlling dust
from fly ash stockpiles indicated that they were about 60 percent efficient in
controlling inhalable particulates (less than 15 microns) at wind speeds of
about 10 to 13 mph (with gusts of 18 to 19 mph).  Control efficiencies for
total suspended particulates were about 75 percent. (Larson, undated).
In another study conducted by PEDCo and reported in USEPA (1985), results
showed no consistent benefits from windscreen for particles in the less than
10-micrometer respirable size range although larger size particles could be
controlled.  Maximum reduction of wind velocity can be expected for a distance
of 1 to 5 fence heights downstream.


          4.2.2.3  Technology Selection/Evaluation


     Wind fences offer a low cost method of reducing fugitive dust emissions.
The fences can be easily transported and set-up for application in various
work areas.  However they are, at best, only partially effective in
controlling inhalable particulates.


          4.2.2.4  Costs
     The installed cost of a polyester wind screen is approximately $13 per
linear foot for a screen six feet high and ranges from $2.00 to 2.50 per
square foot of screen for other heights (Vogel, 1985).
                                     4-7

-------
4.3  Water Spraying and Other Commonly Used Techniques
     There are a number of other control measures for fugitive emissions which
are simple and easy to implement, and do not warrant a detailed discussion.

     The most commonly used method for control of dust emissions is to spray
water on the exposed surface areas.  This method is mainly used to reduce
fugitive dusts along active travel paths, excavation areas and from truck
boxes loaded with soils.  Active travel areas dry quickly and water must be
reapplied frequently (about every 2 hours) to maintain effectiveness (Rosbury
and James, 1985).  Water is applied to the unpaved road surface with a water
wagon, or spray bar.  The quantity will vary with the road surface material,
sunlight, humidity and traffic level (USEPA, 1985).

     Spraying of soils in a truck box can be accomplished by installing a
frame which supports a line of spray nozzels on either side of the length of
the truck.  Contaminated soils can then be sprayed as they are loaded on the
truck and as they are being dumped.  Water spraying is more effective for
large grain-size particles although some control of small particle sizes can
be expected.  Addition of surfactant to the water can be used to increase
control efficiencies and reduce water usage (Rosbury and James, 1985).

     The effectiveness of chemical dust supressants and water spraying along
unpaved roads can be improved by compaction and addition of roadway aggregate.
A road surface will not compact unless the range of particle sizes in the
aggregate is in the correct proportion.  Table 4-3 shows the proper size
gradation for an unpaved road.


          Table 4-3.  Proper Size Gradation for Unpaved Road Surface
                Sieve Size        % Passing            Soil Type
1
3/4
3/8
No.
No.
No.
No.
in.
in.
in.
4
10
40
200
100 ~)
85-100 V-
65-100 1
55-85 J
40-70 "1
25-45 J
10-25

Gravel


Sand
Clay, silt

Source:  USEPA, 1985
                                     4-8

-------
     With too much gravel, relatively  little dust will  occur  (until  tires
grind the gravel down to silt  size particles) but the aggregate will  be  pushed
to the side of the road.  Any  applied  dust  suppressant  will simply pass
through the top surface and provide  little  control.  With  too much sand,  the
bearing capacity will be poor, and any dust suppressant that  attempts to  form
a crust will not work because  of rutting  (USEPA, 1985).

     Reentrained dust from paved roads is controlled by removing dirt from  the
road surface by sweeping, vacuuming  or flushing.  Unfortunately, all  these
methods remove coarse particles more successfully than  fine particles (USEPA,
1985).

     Fugitive dust emissions from excavation activities can be reduced by
maintaining a favorable slope  and orientation on the waste pile.  The slope of
the pile in the prevailing wind direction should be less than 10 degrees  to
minimize emissions.  Measured  wind velocities will accelerate significantly up
slopes greater than 10 degrees, and  the zone of maximum particle entrainment
is at the top of the pile.  If the length of a pile is  perpendicular  to  the
prevailing wind direction, emissions can be reduced about 60  percent  from a
pile with the length parallel  to the wind direction (Vogel, 1985).

     Dust emissions from waste piles can be substantially  reduced by  covering
the pile.  A synthetic cover can be  placed  over the piles  and secured with
tension cables.  An auger feed system  can also be installed to emplace and
remove wastes from the pile.   The installed cost for such a structure ranges
from about $4 to $6 per square foot  of pile surface area (Vogel, 1985).
                                     4-9

-------
                                  References
Larson, A.G.  Undated.  Evaluation of Preliminary Field Test Results on Wind
Screen Dust Control Efficiency.  TRC Environmental Consultants, Englewood CO.
EPA Contract No. 68-02-3115.

Rosbury, K.D. and S.C. James.  1985.  Control of Fugitive Dust Emissions at
Hazardous Waste Cleanup Sites.  In:  Proceedings of the Eleventh Annual
Research Symposium on Land Disposal of Hazardous wastes.  EPA/600/9-85/013.
USEPA, Office of Research and Development, Cincinnati, Ohio.  April 29-May 1,
1985.  pp. 80-87.

SCS Engineers.  1980.  Draft Manual for Closing and Upgrading Open Dumps.
Prepared for:  USEPA, Office of Solid Waste, Washington, D.C.

Valsaraj, K.T., C. Springer, T. Ngvyen, and L.J. Thibdeaux.  1985.
Investigations of Floating Immiscible Liquids to Control Volatile Organic
Chemical (VOC) Emissions from Surface Impoundments.  Land Disposal of
Hazardous Waste Proceedings of the Eleventh Annual Reserach Symposium,
Cincinnati, Ohio.  pp. 145-152.

USEPA.  1985.  Handbook:  Dust Control at Hazardous Waste Sites.  Prepared by
K. Rosbury, PEI Associates, Inc., Golden, CO.for Hazardous Waste Engineering
Research Laboratory, Cincinnati, OH.

Vogel, G.A.  1985.  Air Emissions Contnrol at Hazardous Waste Management
Facilities.  Journal of Air Pollution Control Associations. 'Vol. 35,
No. 5, May.  pp. 550-566.
                                     4-10

-------
                                    SECTION  5

                             GROUNDWATER  CONTROLS
     Control of groundwater  contamination  involves  one  of  four  options:   (1)
containment of a plume;  (2)  removal of a plume  after measures have  been  taken
to halt the source of contamination;  (3) diversion  of groundwater to  prevent
clean groundwater from  flowing  through a source of  contamination or to prevent
contaminated groundwater  from contacting a drinking water  supply; or  (4)  pre-
vention of leachate  formation by  lowering  the water table  beneath a source  of
contamination.  Remedial  technologies for  controlling groundwater contam-
ination problems are generally  placed in one of four categories:  (1) ground-
water pumping, involving  extraction of water from or injection  of water  into
wells to capture a plume  or  alter the direction of groundwater  movement;
(2) subsurface drains,  consisting of gravity collection  systems designed  to
intercept groundwater;  (3) low  permeability barriers, consisting of a vertical
wall of low permeability materials constructed  underground  to divert  ground-
water flow or minimize  leachate generation and  plume movement;  or (4) in-situ
treatment methods to biologically or chemically remove  or  attenuate
contaminants in the  subsurface.  These technologies can  be  used singularly  or
in combination to control groundwater contamination.

     Pumping, subsurface  drains, and barriers are addressed  in  this section;
in-situ methods are  discussed in Section 9.  Detailed information on many of
these technologies can  be found in Leachate Plume Management (USEPA,  1985).
Detailed information on barrier walls can  also  be found  in  Slurry Trench
Construction for Pollution Migration Control (Spooner et al~1984a")  and
Compatibility of Grouts with Hazardous Wastes (Spooner,  et  al., 1984b) .


5.1  Groundwater Pumping


     5.1.1  Description


     Groundwater pumping  techniques involve the active manipulation and
management of groundwater in order to contain or remove  a plume or  to adjust
groundwater levels in order to  prevent formation of a plume.  Types of wells
used in management of contaminated groundwater  include wellpoints,  suction
wells, ejector wells, and deep wells.  The selection of  the appropriate well
type depends upon the depth of  contamination and the hydrologic and geologic
characteristics of the  aquifer.
                                     5-1

-------
     5.1.2  Applications/Limitations


     Well systems are very versatile and can be used  to  contain,  remove,
divert, or prevent development of plumes under a variety of  site  conditions.

     Pumping is most effective at sites where underlying aquifers have high
intergranular hydraulic conductivity.  It has been used  with some effective-
ness at sites with moderate hydraulic conductivities  and where  pollutant
movement is occuring along fractured or jointed bedrock.   In fractured
bedrock, the fracture patterns must be traced in detail  to ensure proper  well
placement.

     Where plume containment or removal is  the objective,  either  extraction
wells or a combination of extraction and injection wells can be used.   Figure
5-1 depicts the use of a line of extraction wells to  halt  the advance  of  the
leading edge of a contaminant plume and thereby prevent  contamination  of  a
drinking water supply.  Use of extraction wells alone is best suited  to
situations where contaminants are miscible  and move readily  with  water; where
the hydraulic gradient is steep and hydraulic conductivity high;  and where
quick removal is not necessary.  Extraction wells are frequently  used  in
combination with slurry walls to prevent groundwater  from  overtopping  the wall
and to minimize contact of the leachate with the wall in order  to prevent wall
degradation.  Slurry walls also reduce the  amount of  contaminated water that
requires removal, so that costs and pumping time are  reduced.

     A combination of extraction and injection wells  is  frequently used in
containment or removal where the hydraulic  gradient is relatively flat and
hydraulic conductivites are only moderate.  The  function of  the injection well
is  to direct contaminants to the extraction wells.  This method has been  used
with some success for plumes which  are not  miscible with water.  Figure 5-2
illustrates an extraction/injection well system  for removal. One problem with
such an arrangement of wells is that, dead  spots  (i.e., areas where water
movement is very slow or nonexistent) can  occur when  these configurations are
used.  The size of the dead spot is directly related  to  the  amount of  overlap
between adjacent radii of influence; the greater  the  overlaps the smaller the
dead spots will be.  Another problem is that injection wells can  suffer from
many operational problems, including air locks and  the need  for frequent  main-
tenance and well rehabilitation.

     Extraction or injection wells  can also be used to adjust groundwater
levels, although this application  is not widely  used. In  this  approach,  plume
development can be controlled at sites where the water table intercepts
disposed wastes by lowering the water  table with  extraction  wells.  In order
for this pumping technique to be effective, infiltration into the waste pile
must be eliminated and liquid wastes must  be completely  removed.   If these
conditions are not met, the potential  exists  for  development of a plume of
contaminants.  The major drawback  to using  well  systems  for  lowering water
tables  is the continued costs associated with maintenance  of the  system.
                                      5-2

-------
                         FIGURE 5-1.
        CONTAINMENT USING EXTRACTION WELLS

                Figure 5-1a. Cross-Sectional View
                     Figure 5-1b.  Plan View
                           Extraction Wells
                            with Radius of
                             Influences
                                                    Domestic
                                                      Well
Source: USEPA, 1985
                               5-3

-------
                               FIGURE 5-2.
            EXTRACTION AND INJECTION WELL PATTERNS
                         FOR PLUME REMOVAL
  a.
                                GW Flow
                                                         Extraction Well

                                                         Injection Well

                                                         Plume Boundary

                                                         Radius of Influence
  b.
                                  GW Flow
Source: USEPA, 1985
                                  5-4

-------
     Groundwater barriers can be created using injection wells to change both
the direction of a plume and the speed of plume migration.  Figure 5-3 shows
an example of plume diversion using a line of injection wells to protect
domestic water sources.  By creating an area with a higher hydraulic head, the
plume can be forced to change direction.  This technique may be desirable when
short-term diversions are needed or when diversion will provide the plume with
sufficient time to naturally degrade so that containment and removal is not
required.

     Each of the well types used in groundwater pumping have their own
specific applications and limitations as well.  Table 5-1 summarizes the site
conditions for which each of these well types are most applicable.  Section
5.1.3.3 describes the components of these well types.

     Wellpoint systems are effective in almost any hydraulic situation.  They
are best suited for shallow aquifers where extraction is not needed below more
than about 22 feet.  Beyond this depth, suction lifting (the standard pumping
technique for wellpoints) is ineffective.  Suction wells operate in a similar
fashion to wellpoints and are also depth limited.  The only advantage of suc-
tion wells over wellpoints is that they have higher capacities.  For extrac-
tion depths greater than 20 feet, deep wells and ejector wells are used.  Deep
well systems are better suited to homogeneous aquifers with high hydraulic
conductivities and where large volumes of water may be pumped.  Ejector wells
perform better than deep wells in heterogeneous aquifers with low hydraulic
conductivities.  A problem with ejector systems is that they are inefficient
and are sensitive to constituents in the groundwater which may cause chemical
precipitates and well clogging (Powers, 1981).
     5.1.3  Design


     There are a number of considerations which go into the design of a well
system.  In this section, design considerations are divided into the following
major areas:  theory of flow towards a well; design of well systems; and
design and selection of well components (e.g., screens, casing, and pumps).
Well theory differs for confined and unconfined aquifers.  A confined aquifer
is a permeable zone between two aquicludes, which are confining beds of clay,
silt, or other impermeable materials.  Depending on the elevation of the water
source, and the permeability and rate of flow in the aquifer, the pressure in
a confined aquifer can rise to considerable heights.  The pressure will vary
considerably depending upon the rate of replenishment, the rate of discharge
and other factors.  But the quantity of water stored in the aquifer changes
only slightly.  In an unconfined aquifer, there is no upper confining bed.
The water table falls with changing flow conditions in the aquifer.  The
amount of water stored in the aquifer changes radically with water table
movements (Powers, 1981).
                                     5-5

-------
                                     FIGURE 5-3.
                    PLUME DIVERSION USING INJECTION WELLS
                    Injection Wells
                                                   Future Plume
                                                    Movement
                                                        \
                                               Domestic Wells
Source: USEPA,1985a
                                         5-6

-------















z
o
UI
UJ
w
as
go:
H ฃ
^
ฃ
E
u



















yi


i
QL
3
u


<_
o

.8
UJ
irt
i
ง
vป
•*•*
e
I
^
*















Wป
U
4-1
i
s.
t U
3 O
3 o
a. e-

0 0
*rf ซ••
^ ^ (_
i*. <3 u.






•e t. •o


I. •O I.
ง 1 ง
a. o ฃ


222
333


wป i/l 41 41
•<- C ซJ •ป
ฃ 3 |> 01 ~
•o >t <-> T) — —
*> 41 O C •• —
U X 3 <9 — O
3 ซ -0 U UI


o u c 9 ซ
W *- iซ • H-
O U VI W
U — 1/1 —
ง*4
2!
•ป — 1. — CM
6ป *A "O U 4t Wf
|, - I" . ? -
ฃ • • U •
X 91 ฃ 01 41 91
01 % • 91 • ** •
— -j ~ s •ป a —
'S, * * *



!*•

0
CM
A
t. -o a.
Ill
u
u.
O
0 M
*J A

I 1 f
ฃ
g
V
J
8 1 1
o. cS 3?
1*.
s
V
1
22''*
335







41
91

241
91
U C.
41 <ป
y
41 4
4WI L. —
2 41 ^
1 i ^
"• " 5
" * f





4J

0
A






0

ฃ
e
i
0


O

1
2 I

1
i
s 1
1
CM
1











U
a,

o
IfeB
o
C •— • >ป
51 g
Ii i
X UJ



































M
OT
^
i
ฃ
3
O
w
5-7

-------
          5.1.3.1  Theory of Flow Towards a Well


     Figure 5-4 illustrates the flow of water towards a well.  When pumping  is
started, the water level in the vicinity of the pump is lowered.  The greatest
amount of lowering or drawdown is at the well.  Drawdown  is  less  at greater
distances from the well and at some distance away aquifer lowering is non-
existent. The force or pressure that drives the water towards the well  is the
head represented by the difference between the water level inside the well and
the water level at any place outside the well (H-h/L).  The  velocity of the
groundwater increases as it approaches the well.  According  to Darcy's  law,
with increasing velocity, the hydraulic gradient increases as flow converges
towards the well.  As a result, the lowered water surface develops a con-
tinually steeper slope towards the well and this is referred to as the  cone  of
depression.  The distance from the center of the well to  the limit of the cone
of depression is called the radius of influence (R ).  The radius of influence
increases with increased hydraulic conductivity and is typically  larger for  a
confined aquifer than it is for an unconfined aquifer.

     The shape and size of the cone of depression is dependent upon pumping
rate, pumping period (i.e., cycles), slope of the original water  table,
hydraulic barriers, aquifer characteristics, and recharge rates.  Two aquifer
characteristics that are important in determining the hydraulic characteris-
tics of the water-bearing formation and thereby the cone's configuration are
transmissivity (T) and the coefficient of storage (S).  Transmissivity
indicates how much water will move through a formation and storage (stora-
tivity) indicates how much of the water can be removed by pumping.  The
coefficients of storage and transmissivity are important  in  being able  to make
the following predictions:  (Johnson Division, UOP, Inc., 1975):

     •  Specific capacity of wells with differing diameters
     •  Drawdown of an aquifer at varying distances from  the well
     •  Drawdowns with varying pumping rates and times.

Transmissivity and storativity are typically determined during  a  pump  test.

     A number of well formulas have been developed to describe both equi-
librium (steady state) and nonequilibrium flow conditions.   This  section
presents equilibrium well formulas in order to illustrate the relationship
between various  factors  (permeability, drawdown, radius of  influence,  etc.)
and provide a simple means for estimating the radius of influence or drawdown
when other  factors are known.  The equations presented below assume  ideal
aquifer conditions (e.g., uniform permeability, laminar flow, and constant
aquifer saturation and thickness).  However, such assumptions do  not  severely
limit the use.of these formula for approximating flow to  a well.  They  do  not
account for the effect of hydrologic boundary conditions  or  partially  pene-
trating wells on flow.   These  flow conditions will be discussed  later  in this
section.
                                      5-8

-------
                                    FIGURE 5-4.
                       FORMATION OF CONE OF DEPRESSION
                               FOR A PUMPED WELL
                                                    Cone of Depression
Source: USEPA, 1985
                                         5-9

-------
     Theim and Forchheimer  independently derived equations for equilibrium
(steady state) radial  flow  to  wells  under confined and unconfined aquifer
conditions, as described  in Johnson  Divison,  UOP,  Inc. (1975).  Both equations
assume recharge at the edge of the cone so that the cone dimensions remain
constant as long as pumping rates remain constant.
     The basic  formula  for  an  unconfined aquifer (shown in Figure 5-5)  is:

               H2 - hw2 = (Q/7Tk)  In  (RQ/rw)                               (5-1)

     where:

               H = saturated thickness  of the aquifer (ft)

               h  = height  of  water  at  the well (ft) measured from the  bottom
                \f
                    of  the  aquifer

               Q = pumping  rate  (ft  /day)

               K = hydraulic conductivity (ft/day)

               R  = radius  of  influence of the cone of depression (ft)

                    radius  of  the well  (ft).
                w
                                   FIGURE 5-5.
                           UNCONFINED AQUIFER FLOW
                                          Q = Constant
                   n -H
                                  = (Q/nK) In
               Source: Davis and DeWiest, 1966
                                      5-10

-------
     Equations for  well pumping a confined aquifer  (Figure 5-6)  are simpler
than those for an unconfined  aquifer.  Drawdown (H-h)  at any  point r from the
well in  a confined  aquifer  can be obtained by:
     H-h = (Q/27TT)  In (R/rw)
                                                     (5-5)
                                FIGURE 5-6.
                         CONFINED AQUIFER FLOW
                                       Q * Constant
               Confined
                Aquifer
                       Bedrock
        -ป4  *- 2r
            \

H-h = (Q/27TT) 1n (Ro/rw)
                                               r *
                                                          Depression
                                                        1   Cone
           Source: Davis and DeWiest, 1966
                                        5-11

-------
     Plots of H-h versus r on semilogarithmic paper can be developed  for  both
unconfined and confined conditions so that predictions of R  and wetted screen
length can be made.  Figure 5-7 shows two such plots.

     Nonequilibrium well formulas have an advantage over equilibrium  well
formulas in that they take into account the effects of varying  rates  of
pumping on well yield and they can be used to predict drawdown  at a specified
distance from a well at any time after pumping has started.  Nonequilibrium
well formula are presented in Johnson Division, UOP, Inc. (1975) and  USEPA,
(1985).

     Neither the equilibrium nor nonequilibrium well formula account  for  the
effect of pumping from a well which only partly penetrates an aquifer, cumu-
lative drawdown from a number of wells, or hydrogeologic boundary conditions.
Each is discussed briefly below.  Specific formulas which account for these
effects can be found in Todd (1980), USEPA, (1985), and Johnson Division,  UOP,
Inc. (1975).
               a.  Partial Penetration
      When a well does not fully penetrate an aquifer, the water  close  to  the
well must move along curved lines to feach the well.  In doing  so,  the  water
must take paths that are longer than strictly radial  flow lines (see  Figure
5-8).  The result of the longer flow paths is that drawdown  is  greater  for a
well with partial penetration and, for a given drawdown, the yield  of a well
partially penetrating the aquifer is less than that of well which fully
penetrates the aquifer.  Evaluation of the effects of partial penetration  can
be complicated.  However, the effect of partial penetration  is  negligible  on
the flow pattern and drawdown beyond a radial distance larger than  0.5  to  2
times the saturated thickness, depending upon penetration (Todd,  1980).

     A major problem associated with the use of partially penetrating wells
for the containment of plumes is that contaminants can flow  under the well if
the well does not fully penetrate the aquifer and pumping is not  sufficient.
Partially penetrating wells may be most useful in collecting floating
contaminants.
               b.  Cumulative Drawdown
     In designing  a well  system  for  containment  or  removal  of contaminated
groundwater,  it  is frequently necessary  to  use  several wells  which are  spaced
such that their  cones of  depression  overlap and  no  flow  occurs between  the
wells.  It should  be noted that  overlapping the  cones of depression may not be
sufficient to capture the plume  in aquifers with high natural flow velocities
(Keely and Tsang,  1983).
                                      5-12

-------
                             FIGURE 5-7.
             PLOTS OF H-h VERSUS r FOR UNCONFINED
                     AND CONFINED AQUIFERS
        10001
        2000
        3000
1 ill
X
1 III

1 III
1
s~
X
X
X
X Use Boreli ^
Correction
i iii
r(ft)
ซ
s



i-li is

1 III

-
-


                                             r =  1.5H
      Figure 5-6a.  Equilibrium plot for a water table aquifer. Q =  500 gpm.
      R0 = 1000 ft. K = 300 gpd/ft.2 H  = 100 ft.  rw  = 0.5 ft.
   2
 I  3.
a: 4.
ง5
| 6.
ฃ7
   8
   9.
  10.
i   i  i
                    10
                    100
1000
0,000
     Figure 5-6b. Equilibrium plot for a confined aquifer. Q = 500 gpm.
            K = 500 gpd/ft.2 m = 100 ft. R0 = 2000ft. rw = 0.5 ft.
 Source: Powers, 1981
                                5-13

-------
                              FIGURE 5-8.
     COMPARISON OF RADIAL FLOW TO A FULLY PENETRATING
        WELL WITH  FLOW TO PARTIALLY PENETRATING WELL
           Figure 5-8a. A Radial Flow to a Fully Penetrating Well,
                         Steady State Conditions
                                    Drowdown   ^ -* *
                                     cone
                 Figure 5-8b. Penetrating 50% of Aquifer
     Static Piezometric Surface
      /  //  7  //_/  /  7  /  / /  /  7  /  //////////
            Lower Confining Bed
                           • - — - Flow Lines
                           	Equipotential Lines
Source: Bureau of Reclamation, 1977
                                 5-14

-------
     For confined aquifers  with several wells tapping  the  same  system,  the
composite pumping cone  can  be calculated by summing  the  individual  drawdowns
caused by each well  (Figure 5-9).   This can be accomplished by  graphical
superposition (i.e.,  adding the drawdown curves, H-h,  for  each  well)  or by
calculations using either equilibrium (equation 5-5) or  nonequilibrium  equa-
tions.  Theoretically,  the  method  of cumulative drawdown cannot be  applied to
unconfined aquifers  because transmissivity changes with  drawdown.

     Composite drawdowns  for unconfined aquifers under equilibrium  conditions
can be calculated from:
H2-h2 = (Q1ln(RQ/r1)/  K)
                                                                      K)  (5-6)
             FIGURE 5-9.  COMPOSITE DRAWDOWN IN A CONFINED AQUIFER
                                                       Original
                                                       Watertable
         — — Drawdown due to Q2  — - — Drawdown due to Q,
                                                    Total Drawdown
         Source: Freeze and Cherry, 1979
                                      5-15

-------
               c.  Extraction/Injection Well Combinations
     As described in Section 5.1.2, a combination of extraction  and  injection
wells is frequently used in plume management.  Injection well  theory is
identical to extraction well theory except that cones of depression  and  draw-
downs are inverted to above the water table or piezometric  surface  (cone of
impression) (Figure 5-10).
               d.  Hydrogeologic Boundary Effects
     Typically, wells are not located in aquifers  that have  infinite  areal
extent, therefore, drawdown cones extend until they intercept  a  recharge
boundary or a barrier boundary.  Recharge boundaries  (e.g.,  streams)  are  areas
where aquifers are replenished with water and barrier boundaries (e.g., imper-
meable zones) are where aquifers terminate.  Total drawdown  and  the rate  of
drawdown are less than theoretical predictions where  recharge  boundaries  are
present and are greater when barrier boundaries are present.

     In order to predict head drawdown for the boundary conditions, the
methods of images can be used.  With this approach, the real bounded  system  is
                                  FIGURE 5-10.
             RECHARGE AND DISCHARGE WELLS  IN CONFINED AQUIFER

".I


s
^ s
ป H
K

IH^WWWIWWW)
V
\x
*** -s
I X
I
I N
I x^
..ซ" paw. ฃ
; •r v
! 4 |
3 .gUyy !•
,7-j

~* is--—-
K
1 !
,„.;„„*

                    Source: Davis and DeWiest, 1966
                                      5-16

-------
replaced for purposes of analysis by an imaginary system of  infinite  areal
extent (Figure 5-11).

     In this system, there are two wells pumping:  the real  well on the  left
and an image well on the right.  The image well pumps at a rate "Q" equal to
the real well and is located at an equal distance "a" from the boundary.  If
the two component drawdowns in the infinite system are summed it becomes clear
that this pumping geometry creates an imaginary impermeable  boundary  (i.e., a
boundary across which there is no flow) in the infinite system at the exact
position of the real impermeable boundary in  the bounded system.
          5.1.3.2  Well Design


     Well system design includes a determination of the number of wells
needed, the patterns and spacing of the wells, the design of the individual
wells, the pumping cycles and rates needed, and the method of handling
discharges.  The following sections provide some general guidelines  for well
system design.

     Prior to designing the well system, a complete hydrogeologic under-
standing of the site must be established.  A potentiometric surface map (i.e.,
a map depicting contours of equal head) and a geologic cross-section of the
site should be developed.  Coefficients of transmissivity (T) and storage  (S),
discharge (Q), and drawdowns (H-h ) should be determined using pump  tests.
                                 w


               a.  Equilibrium vs. Nonequilibrium Pumping


     A choice has to be made whether equilibirum or nonequilibrium pumping is
to be used at the site because this affects the extent of the radii of
influence.  Equilibrium pumping will probably be used in most plume management
systems, but nonequilibrium pumping does have advantages in some cases.
Equilibrium pumping has the advantage of allowing greater well spacing,
thereby reducing the number of wells.  It is also easier to design than
nonequilibirum pumping and may result in lower O&M costs.  Nonequilibrium
pumping may be a better alternative for aquifers with low hydraulic conduc-
tivity, for nonmiscible plumes, and for sites with groundwater barriers or
scant recharge.


               b.  Radius of Influence
     Determining the radius of influence for a well in a given aquifer  is
critical in remedial action design because it can be used for determining well
spacing, pumping rates, pumping cycles, and screen lengths.  The radius of
influence of a well increases as pumping continues until equilibrium
conditions are reached (i.e., when aquifer recharge equals the pumping  rate or
the discharge rate).

                                     5-17

-------
2
O
(/)
V)
LU
cc
0.
LL
O
LU
2
O
U
       <5
       m
cc —

II

  111

  b
  Q
  CC
  O
  LL

  LU


  1
  LL
  O
  Q
  O

  LU
       &
       ฃ
       a
                                ^ff#?.?!ปj
                                                               3
                               5-18

-------
     The most  accurate method  for  estimating  the  radius  of  influence is  by
pumping test analysis.  Pumping  tests  can  identify  recharge boundaries,
barrier boundaries,  and slow storage release  conditions.  The  pumping test
should be performed  until equilibrium  conditions  are  reached.   Typical  test
durations for  a  confined  aquifer are about  24 hours while they may be several
days for an unconfined aquifer.  Once  equilibrium conditions have  been
reached, the radius  of influence for equilibrium  or nonequilibriutn conditions
can be estimated using the equations in  Table 5-2.

     For an exact  solution of  the  radius of influence under nonequilibrium
conditions, a  distance drawdown  diagram  can be  constructed  using pump test
data.  Distance  drawdown  diagrams  are  plotted on  semilogarithmic paper  with
distance being plotted on the  logarithmic  scale.  Two such  diagrams are  shown
in Figure 5-12.  The  radius  of influence can  be obtained  from  the  intercept  of
the plots with the distance  axis at zero drawdown.  For  cases  where pumping
rates are variable but all other parameters are held  constant,  (5-12a)  the
radius of influence  obtained is  almost identical.   When  pumping times are
varied (5-12b),  the  radius of  influence  is  changed  such  that as pumping  time
increases, the radius of  influence increases.   This relationship holds  true
until equilibrium  is  reached after which the  radius of influence does not
increase with  continued pumping.

     When pumping  test data  are  lacking  or  incomplete, rough approximations  of
the radius of  influence can  be obtained  using equations  presented  in Table
5-2 and the values of transmissivity or  hydraulic conductivity, pumping  times,
and coefficient  of storage.  Coefficients of  storage  values typically range
from 0.01 to 0.35  for water  table  aquifers  and  from 0.00001 to  0.001 for
confined aquifers.   Typical values are 0.2  for  water  table  aquifers and  0.001
for confined aquifers.  Because  these  estimates are approximate and do not
take recharge  into account,  it is  advisable that  the  value  of  R be adjusted
downward so that there will be a greater overlap  of the cones  or depression
and therefore a  lower probability  that contaminants escape  between  the wells.


               c.  Well Spacing


     Determination of the proper spacing of wells to  completely capture  a
groundwater plume is probably  the most important  item in system design.  Field
practitioners have long had a  standing "rule  of thumb" for  estimating well
spacing:  adjacent cones of depression  should  overlap  (i.e.,  radii of influence
should overlap).  This method  is reasonably accurate  for aquifers  that have
low natural flow velocities but  will not be valid for  aquifers  with high
natural flow velocities.  For  these latter  cases  (and  preferably for all
cases), velocity distribution  plots should  be developed to  determine  well
spacing and ensure capture of  the plume  (Kelly  and  Tsang, 1983).

     Velocity distribution plots for determining well  spacing are discussed  in
USEPA,  (1985) and Kelly and Tsang  (1983).   The  use  of  these  plots  is  based on
a determination of the "stagnation point,"  i.e., the distance downgradient
from the  well at which the pull  of water towards  the  well by pumping  is
exactly countered by the natural flow velocity  of water away from

                                     5-19

-------
                                TABLE 5-2.
                   RADIUS OF INFLUENCE EQUATIONS
     Pumping
     Condition
Water Table  Aquifer
   (Unconfined)
Confined Aquifer
Equilibrium
   - Exact    lnftn ซ K(H -8  )?{458Q)) + Inr
                            lnRn -(T(H-hJ/229Q)  + Inr
Non-equil ibrium
   - Exact

Approximate
  Drawdown  vs.  log distance plots or Theis Method

    Ro * rw *  (Tt/4790S)ฐ*5

    Ro ' 3(H-hw)(0.47K)ฐ'5
     RQ * Radius of  influence (ft)
     K  ป Hydraulic  conductivity (gpd/ft )
     H  * Total head (ft)
     h  * Head  in well (f)
     0  = Pumping rate (gpm)
     r  ป Well  radius (ft)
     T  * Transmissivity (gpd/ft)
     t  • Time  (mln)
     S  ป Storage coefficient (dimensionless)

 Source: USEPA, 1985
                                   5-20

-------
                                     FIGURE 5-12.
   DISTANCE DRAWDOWN DIAGRAMS FOR A) VARYING PUMPING RATING
                        AND  B) VARYING PUMPING TIMES
                                       Figure 12a.
       c  12
          20
          24
               AS =  5.3 ft.
         12


         16


        20


        24
                                                                      T = 300 min.
                                                              Drawdown = 18.8 ft.
                                                        Q = 400 gpm
             1      235      10      20   30    50    100    200  300   500

                                    Distance from Pumped Well, in Feet

                                      Figure 12b.
                      Drawdown in Observation
                      Well "A" after 300 min.
                                                               Drawdown in Observatoin
                                                               Well "A" after 1000 min.
Curves Constructed for Q = 200 gpm
           1       235      10      20  30    50     100     200   300   500
                                  Distance from Pumped Well, in Feet
Source: Johnson Division, UOP Inc., 1975
                                         5-21

-------
the well.  The stagnation point is directly related to the pumping rate of  the
well (i.e., the higher the pumping rate, the further downgradient the
stagnation point) and inversely related to the natural flow velocity (i.e.,
the greater the natural flow velocity, the closer the stagnation point is to
the well).  Only for the extremely rare case of zero natural flow are the
areal boundaries of the capture zone identical to the calculated cone of
depression.  This means that even though the cones of depression of two
pumping wells intersect, they may not be completely capturing  the plume unless
their capture zones intersect.  This finding has significant ramifications  for
well system design for plume removal (Keely and Tsang, 1983).


               d.  Pumping Rates


     For a confined aquifer, capacity and therefore pumping rate is directly
proportional to the drawdown [Q/(H-h)] as long as the aquifer  is not
unwatered.  Increasing the pumping rate will not affect the radius of
influence but will affect the amount of time pumping is necessary.  Therefore,
pumping rates can be selected to suit the situation.  In  situations where the
contaminated plume floats, drawdowns and pumping rates will probably be small.
Large drawdowns and high pumping rates are desirable where contaminants are
dispersed throughout the aquifer, quick removal is desired, and natural
groundwater flow rates are large.

     For an unconfined aquifer it has been found that maximum  efficiency  for
well operation occurs at about 67 percent of the maximum  drawdown; pumping
rates should be adjusted accordingly.  This is because part of the formation
within the cone of depression is actually unwatered during pumping and the
specific yield decreases with increased drawdown.  Optimum operating condi-
tions are achieved when the product of specific yield and capacity are
greatest and this occurs at about 67 percent of maximum drawdown.


               e.  System Integration


     Once the well spacing, pumping rate, and drawdown have been determined,
the system can be designed as a unit.  At this point, a decision must be made
on the pattern and type (i.e., injection or extraction) of wells to be
installed.  Numerous patterns of extraction wells or injection wells or both
are available.  The choice is typically based on whether  the design is for
containment or removal, the time available for recovery,  and the amount of
dewatering that is allowable.  Patterns that combine extraction and injection
wells allow for more rapid contaminant removal without greatly affecting
groundwater levels.  These patterns are also advantageous because the treated
water extracted can be reinjected.

     After a well pattern is chosen, the number of wells  needed to control  the
plume must be determined.  This is based on the estimated well spacing and  the
drawdown required.  In spacing wells for plume control, it is  necessary to
                                     5-22

-------
have the well's capture zones intersect each other  so  that  contaminants  will
not flow between wells and escape as described previously.

     The number of wells needed can be determined by plotting  the  chosen
pattern of wells with their required spacing on  the potentiometric  surface map
of the site.  After this is done, the drawdowns  within  the  radii of influence
should be plotted and cumulative drawdowns determined.  This will  result in a
new potentiometric surface map of the site that  can be  used to  identify  dead
spots where contaminants can escape.


          5.1.3.3  Design and Selection of Well  Components
     As mentioned previously, there are four types of wells used  in ground-
water pumping:  deep wells, ejector wells, wellpoints, and suction wells.
This section briefly describes the major components of these well types.
               a.  Deep Wells


     The major components of a deep well are  illustrated  in Figure  5-13 and
include:  casing, screen, filter pack and seal, and pump.

     Casing—Casing size (diameter) is chosen to satisfy  two requirements.
The casing must be large enough to accommodate the pump with enough clearance
for effective operation and to ensure proper  hydraulic efficiency of  the well
at the intake section (Johnson Division, UOP, Inc., 1975).

     The controlling factor is usually the size of the pump selected  for the
desired capacity and head.  A good rule of thumb is that  the casing size
should be two standard pipe sizes larger than the nominal diameter  of the  pump
or pump bowl, and not less than one size larger.

     Screen—The function of the screen is to stabilize the hole, keep
particles out of the well, and facilitate flow into and within the well
(Bureau of Reclamation, 1977).

     The major variables which need to be considered in selecting screens
include:

     •  Screen type - Several types are available including punched,  stamped,
        louvered, wire-wound perforated pipe, and continuous-slot wire-wound
        screens.

     •  Material - Screens are made in a variety of metals, metal alloys,  or
        plastics.  Tendency towards corrosion and encrustation are two major
        factors affecting materials selection.  Corrosion of the screen causes
        enlargement of openings,  which could permit excessive sand entrance
        and premature pump wear.   If corrosion is severe, collapse could
        occur.  Encrustation is caused by mineral deposits on the screen

                                     5-23

-------
                                 FIGURE 5-13.
                  COMPONENTS OF TYPICAL DEEP WELL
                                               Throttle Valve
                                        Check
                       Pressure Gauge     Valve
  Control Panel
           Discharge Column
                    Pump
                     Motor
                 Filter Pack
Source: Adapted from Powers, 1981
                                                  Cement Grout or Bentonite Seal
                                                       Detail of Air Line for
                                                       Measuring Operating
                                                       Level
                                      5-24

-------
        surface which tend to plug  the openings  of  the  screen and  formation.
        Strength to resist column load and collapse  should  also  be considered
        in materials selection.  Column  load  results from the screen support-
        ing the weight of the casing.  These  forces  can be  considerable  in
        deep wells.  Collapse pressure results  from  earth pressure and caving
        materials squeezing the screen.

     •  Screen length - The optimum length of a  screen  is based  on the type
        and thickness of the aquifer, the available  drawdown,  and  the
        stratification of the aquifer.   Criteria for determining well screen
        length can be found in Johnson Division,  UOP, Inc.  (1975)  and USEPA
        (1985).

     •  Total open area and slot size -  A well screen must  have  a  total  area
        of openings such that the entrance velocity  does  not  exceed some
        critical value which will result in excessive friction losses in the
        screen openings.  Also the  slot  size  must be such that it  allows fine
        grained materials to enter  the well and  be removed  during  development
        but allow coarser material  to be retained outside forming  a permeable
        envelope around the well.   Procedures for determining the  required
        open area and slot size can be found  in  Powers  (1981)  and  USEPA
        (1985).

     Gravel Pack—Most wells used for remedial action will  probably be
drilled, which normally requires that the area around the well screen be
filled with a filter or gravel.  This filter  performs several important
functions (Powers, 1981):

     •  Fills the annular space preventing the uncontrolled collapse of  the
        formation against the screen

     •  Retains a sufficient percentage  of fines  thus preventing them from
        being pumped continuously

     •  Passes some amount of fines  and  mud cake  that have built up on the
        sides of the hole

     •  Transmits water freely from the  aquifer  to the  screen during pumping.

     To perform these functions, the filter should be a very  uniform material
so that it has a high permeability  and can be placed without  segregation.   The
filter should be as coarse as possible without continuously passing fines
(Powers, 1981).  Various formulas for relating gravel pack  grain size grada-
tions to aquifer grain size gradations have been developed.   Procedures  can be
found in Powers (1981) and USEPA (1985).

     Pumps—The turbine submersible  pump and  the vertical line shaft pump  are
generally used for deep wells.  Submersible pumps have  the  advantage of  being
relatively slender for their capa'city allowing their use  in small  diameter
wells.  Commercially available pumps can be obtained with capacities greater
than 100 gallons per minute and with motors of several  hundred horsepower.


                                     5-25

-------
     Vertical lineshaft pumps are similar  to  submersible  pumps  except  that  the
motor is located on the surface rather than being attached directly  to  the
pump.  This type of pump is used for extracting high volumes of groundwater
and is available in sizes ranging from a few  horsepower to over  a  thousand
horsepower.  The cost of a lineshaft pump  is  typically greater  than  for a
submersible pump of similar horsepower size.

     Before selecting a pump for any installation,  it is  necessary that
accurate information be available with regard to total capacity, operating
conditions (e.g., pumping cycle, peak load, future  needs), and  total head.
The total dynamic head (h ) of a pump represents the total vertical  lift of
water from the well.

     Total dynamic head (h ) can be calculated using the  equation:

          h  = h  + hr + h                                               (5-7)
           t    e    f    v

where:

          h  = total vertical lift, from the  pumping level in  the  well  to  the
               water discharge point (ft)

          h, = total frictional losses in  pipes and fittings expressed  as  head
           f   (ft)

          h  = velocity head required to produce the desired flow  (ft).

     Total vertical lift (h ) is the sum of the vertical  distance  from  the
                           g
pumping level in the well to the outlet and the hydrostatic pressure head  at
the discharge outlet.  Frictional losses in pipes and fittings  are calculated
using tabulated values found in Johnson Division, UOP, Inc. (1975) and  USEPA
(1985).  Velocity head (h ) is determined  using the formula h   = 0.155V ,
where V is the velocity or flow (ft/sec) and  the coefficient 0.155 has  units
of sec /ft.  Usually, h  is very small and is only  taken  into  account where
very high discharges are expected at very  low lift  and discharge head,  or
where velocity of flow is very high.

     Once the total dynamic head is obtained  and the capacity  is determined, a
pump and motor can be chosen using performance curves available from manu-
facturers.  These curves typically plot capacity versus total  head and  percent
efficiency of the system.  An example of performance curves for 325  gallon  per
minute pumps is given in Figure 5-14.


               b.  Ejector Wells


     Ejector wells have certain advantages over wellpoints and deep  wells
because they are not typically depth limited  as wellpoints are and they are
less expensive than deep wells when close  spacing  is required.   The  biggest
drawback to the use of ejector wells is that  they are very inefficient
(typically less than 15 percent efficiency).  Ejector wells can be used

                                     5-26

-------
                             FIGURE 5-14.
                      PERFORMANCE CURVE
                                    Most Efficient
                                   Operating Range
    700
    600
    500
    400
.ฃ
1   300
    200
    100
                  100        200        300
                           Gallons per Minute
400
500
  Source: Flint and Walling Inc.
                                 5-27

-------
independently of each other or arranged so that they utilize a common pumping
system.

     The typical components of a two-pipe and a single-pipe ejector well
system are illustrated in Figure 5-15.  The lift principle for the two-pipe
model is (Powers, 1981):

     •  High pressure supply water (Q1 ) moves down the supply pipe through
        ports in the ejector body to the tapered nozzle where the pressure
        head is converted to water velocity

     •  Supply water exits the nozzle at less than atmospheric pressure
        creating a vacuum in the suction chamber

     •  Groundwater (Q_) is drawn into the chamber through the foot valve
        because of the pressure differential

     •  Supply water and groundwater (Q1 + Qซ) are mixed in the suction
        chamber

     •  The mixed water enters the venturi where the velocity decreases
        because of divergence resulting in increased pressure

     •  The increase in pressure develops sufficient head to return the
        combined flow to the surface.

     The lift principle for the single-pipe model, illustrated in Figure 5-15,
is similar except that the supply water under pressure (Q, ) flows downward
between the well casing and the inner ejector return pipe, and a packer
assembly separates the supply water from the groundwater so that different
pressures are developed (Powers, 1981).

     Single-pipe ejector wells are most commonly used because they require
less piping and yields are greater for smaller diameter casings.

     Ejector pumps consist of a water tank and a pump with the required valves
and piping.  Each well can have its own pump or one pump can be used by a
number of wells.  Water from the storage tank is pumped under pressure through
a header pipe that supplies the ejector wells.  Return flow, a mixture of
supply water and groundwater, recharges the tank through the header system.
Excess water in the tank is discharged to a treatment system.

     The proper ejector pump and ejectors (i.e., nozzle and venturi) can be
selected using manufacturer's data or through calculations.  The procedures
for calculating the size of an ejector are to calculate head ratios, estimate
the capacity ratios, and calculate the diameters of the nozzle and the
venturi.  The procedure is fairly complex and is described in detail by Powers
(1981).

     Materials for risers, swings, headers, tanks, screens, and pumps should
be selected to minimize corrosion and encrustation.  Selection criteria are
                                     5-28

-------
                                 FIGURE 5-15.
    COMPONENTS OF ONE-PIPE AND TWO-PIPE EJECTOR WELLS
                Overflow
                                                                     Strainer
  Return Header
                       IV* in. (32-mm) Riser
                       with Turned Couplings
                                                                  1>4 in.
                                                                  (37mm)
                                                                  Supply Line
                                                                  (0,)
                                                                   Ejector
                                                                   Body
                                                                   Foot
                                                                   Valve
          Typical Single-Pipe
          Ejector Installed
          in a 2-in. (50-mm)
          Wellpoint
Typical Two-Pipe
Ejector Installed in
a 6-in. (150-mm)
Well
Source: Powers, 1981
                                     5-29

-------
the same as for deep well systems.  However, ejectors must also be  protected
to maintain well performance.  Ejectors used in corrosive environments  can be
made of plastic to eliminate the problem.  Ejector sensitivity to clogging
should be a primary consideration in selection.


               c.  We 11points
     Wellpoint systems consist of a group of closely  spaced wells  connected  to
a header pipe and pumped by a suction pump.  Wellpoints  are best suited  for
groundwater extraction in stratified soils where  total  lift or drawdown  will
not exceed 22 feet.  The advantages to using wellpoints  are that the  system
design is flexible and the wellpoints are relatively  inexpensive even when
closely spaced.

     A suction (vacuum) pump is  typically used  in wellpoint systems  to lift
water.  Suction pumps (either oil sealed or water sealed)  accomplish  lift by
developing a negative pressure head at the pump intake  rather than by applying
force to the water source as in  ejector pump systems.   The maximum lift
attainable by suction pump is about 22 feet.

     Wellpoints are specially made well screens that  are typically 1.5 to
3.5 inches in diameter and are capable of yields  up to  35  gallons  per minute.
Large wellpoints (up to 8 inches in diameter) generally  called suction wells,
are also available.  They have capacities greater than  35  gallons  per minute.
Figure 5-16 shows the basic types of wellpoints.  Wellpoint screens  can  be
made of heavy wire mesh, continuous wire, slotted plastic, or perforated
plates.  As with deep wells, the materials selected should minimize  the
potential for corrrosion and encrustation.

     Because wellpoints are typically installed in oversized boreholes,  filter
sands are placed around the wellpoint to fill the annular  space.   The filter
sands increase the effective diameter of the wellpoint,  decrease the  entrance
velocities of water, prevent clogging of the screen with fines,  and  provide
for vertical drainage from overlying layers (Powers,  1981).

     The depth at which wellpoints are set is dependent  upon the hydrogeology
of the site.  Although drawdown  is limited to approximately 22 feet  below  land
surface, wellpoints can be set at almost any depth depending on  the  situation.
Where contaminants float at the  top of the aquifer, wellpoints can be set  at
shallow depths.  Where contaminants sink or mix with  the groundwater, the
wellpoints can be set deeper.  The only criterion for wellpoint  depth is to
avoid dewatering below the screen.  If this occurs, air enters the system  and
reduces the vacuum and therefore the drawdown.   During  normal operation  of  the
system, dewatering below the top of a wellscreen can  sometimes occur.  The
problem can be minimized in the  field by adjusting the  valves that control
individual wells.
                                      5-30

-------
5
    o
    Q.
    O
    LLJ
    QC

    O

    O

    Z
I


UJ


O
UJ


UJ
   I-


   5
   a.

   _i
   UJ


   Z
   Q


                                   111/1   >\\\ -'jV','.',.   N
                                   1,1 < !  ,,| I,ซj,,. f ,^  >  JMW.
                                                                                                           03

                                                                                                           in
                                                                                                              Q-
                                                                                                              o
                                                                                                          .2
                                                                                                          .2


                                                                                                          5



                                                                                                           ง
                                                   5-31

-------
     5.1.4  Installation of Wells


     Well installation typically consists of four steps:

     •  Opening the borehole by dislodging and removing earth materials

     •  Installing a casing which may or may not be installed simultaneously
        with opening the borehole

     •  Completing the well by installing screens, filters, pumps, and grout

     •  Developing the well which consists of dislodging and removing fines
        that have built up on the well screen, the filter, and  the walls of
        the aquifer during the previous steps.

Each of these steps is described briefly in this section.


          5.1.4.1  Opening the Borehole


     Methods for opening boreholes are selected based on well depth  and
subsurface geologic and hydrologic characteristics.  Shallow wells ซ100
feet) are augered, driven, or jetted.  For deep wells (MOO feet), rotary
drilling, jetting, and cable-tooling are generally used.  Table 5-3  briefly
describes the applications of these methods to various geologic and  hydrologic
conditions.  Screens and casings may be installed simultaneously with the
opening of the borehole or after the borehole has been completed, depending
upon the technique used to open the borehole.  Casing and screen installation
methods are also summarized in Table 5-3.


               a.  Hand Augering


     Hand augers are available in several shapes and sizes, all operating  with
cutting blades at the bottom that bore into the ground with a rotary motion.
When the blades are full of loose earth, the auger is removed from the hole
and emptied; the operation is repeated until the desired hole depth  is reached
(Todd, 1980).


               b.  Driven Wells
     A driven well consists of a series of connected  lengths of  pipe  driven  by
repeated impacts into the ground to below the water table.  Water  enters  the
well through a drive (or sand) point at the  lower  end of  the well.  This
consists of a screened cylindrical section protected  during driving by a  steel
cone at the bottom.  Driving can be done with a maul  sledge, drop  hammer,  or
air hammer (Todd,  1980).

                                     5-32

-------








2
O
_i
(0
ซ? 2
UJ J
_l UJ
m>
^jfc
^ t
O

<- 01
oi e
1 *
k C
01 ซ
5
ซ
e S: e 01
i I
8 3




te r>


si
01
U • ite
Kb. O
01 01
ii 1
JE v tx in
^^1 si
JSi -S
ฃ 5 J ฃ2
Si 3

in
•ฃ
I


1 1


5
ฃ
w
in 01 01
0= I*S&
lu -isซ
ss i -ss
'I Sl|
=e| -t"ป

JT* ฐ 3

ป o "5 o
ฃ.2 S^
Ii ฃ1
& *
$ S




00 **O


tfl
fc.
M ** •>
|C |?2
1* ฃ"S
•i -i:
jnx m in ฃ
!l !ll
•W 4> *4ป 41 S
(/) vS


t 4.
1. i
t>
>ปZ —
2l S
ฃ #

I
^
ฃ

U
a e
in •—
— 0)
ii
I jn
*
OI
i
*
e
in




OB



„
<•• •ป
*ซ 2
ซ•- e



o>
c

"*^
S

J
^
j^

L.
01
ป ป
ซ e
Ss
3 •*•
ii
2

^ *i
:i -:
Ii ||
& =
S 8




dc ซo



01 01
01 01
u tn L. M
11 8i
we we
3 5
L
01 I
in i **
€ Jltl
I StZ

-I 'l?
i ซ "











•>
1
in
P

8




09



f
ti
Ii
ซf O



1
lป
•)
•W C
II
4?t




5-33

-------










NTINUED).
O
O
s!
3j*
P CO

z

u.
O
CO
0
0
X
HI

^—














s
it
*
Casiny/Screen







I

*
o

!






i
i












I
i
1
t

^^
• *•*
.— c



X ซ
5s
K ^

|
9
~
U
3

|
ซ
*


—
2










Driven as
hole opened


o
S



CM


a
s
|
—
7 VI
***
ฃป
1
tt
I'

e •
w O

41
'"-TS


11*
croi
>. e
ซ--
—"sH
a. >T>
>i
U 41
51
K
ol


i


i







^
X
i
^_
Convent iona
Hydraulic
91
B
SI
s




3.
U  ana o — <• a
41 vi— i .e ป
i a > -o ซ u
O >i C
w >i k <•• •ซ 41 •••
,ซ) O O 3 X 11
ป fB4^*ซ94lป
•a -a 9101 41
we ซ c — *o ซ *o
w4iซ<4i bj: ซฃ
^ o X o -o u >vi
41 <9
•a 41 -Q 41 e *j -o -a -H
41 — 4) — 4I*. 41 41 VI i
wo wo >, X, >> >\
ill i
ฃ
"5 *~
* ป - i "2.
S i? u I =5-
" ซ i ซ — t ••
s a|| 1 !t
<_ <.ฃ -2 c — g
•^ ซnป O * **
ซ < U OI/>

1
2
lซ
u




























i
2
UJ

-------
               c.  Rotary Bucket Augering

     The bucket auger consists of a cylindrical  steel  bucket  with  a  cutting
edge projecting from a slot in the bottom.  The  bucket  is  filled by  rotating
it in the hole by a drive shaft of adjustable  length.   When full,  the  auger  is
hoisted to the surface and the excavated materials are  removed  through hinged
openings on the side or bottom of the bucket.  Reamers,  attached to  the  top  of
the bucket, can enlarge holes to diameters exceeding the auger  size  (Todd,
1980).
               d.  Spiral Augers


     There are two types of spiral augers:  Solid-stem  and hollow-stem
continuous flight augers.

     Solid-stem augers consist of auger flights welded  to a  solid  core.
Drilling is accomplished by rotation of the augers which convey  soil  samples
to the surface.

     A hollow-stem auger consists of flights welded to  a hollow  core  which  has
a 1-1/2- to 6-1/4-inch inside diameter.  The drilling technique  is the same as
for the solid-stem augers except that  the core facilitates downhole sampling
and well installation.
               e.  Jetting Methods


     Jetted wells-are constructed by the cutting action of a downward-directed
stream of water.  The high velocity stream washes the earth away, while  the
casing, which is lowered into the deepening hole, conducts the water  and
cuttings up and out of the well.

     Jetting methods for installing small diameter, shallow wells include  the
following:

     •  Self-jetting, permanent drop tube—The entire wellpoint is jetted  down
        and remains in place.  The permanent drop tube eliminates the need for
        temporary jetting pipes.  Riser tubes are used to extend the  length of
        the well as jetting proceeds and act as casings.

     •  Self-jetting, separate drop tube—Same as the self-jetting, permanent
        drop tube method except that the drop tube is removed after jetting is
        completed.

     •  Separate, temporary jetting pipe—A capped pipe with cutting  teeth at
        the bottom is jetted down by water forced through openings in the  cap.
        If soil becomes difficult to remove, the pipe is rotated back and
        forth to aid the jetting process.   Once the well is pushed to the
                                     5-35

-------
        final depth, the wellpoint and riser are placed in the jetting pipe
        and the jetting pipe is removed.

     •  Separate, permanent jetting pipes—Similar to the separate, temporary
        method except that the wellpoint with screen is packed into the
        jetting pipe, the pipe is lifted to expose the screen, and the jetting
        pipe then becomes the riser casing.


               f.  Rotary Drilling


     Rotary drilling methods involve the use of a rotating bit and a viscous
fluid or air to transport the cuttings.  Four rotary drilling methods are
commonly used (Luhdorff and Scalmanini, 1982; Johnson Division, UOP, Inc.,
1975):

     •  Conventional Hydraulic (direct circulation)—This practice employs a
        drilling fluid which is circulated down a rotating drill pipe through
        the drill bit.  The fluid returns up the annulus of the borehole,
        removing the drill cuttings.  The mixture goes to a settling pit, and
        the fluid is again recirculated through the fluid system by a pump.
        Hole stability is accomplished by the hydrostatic pressure of the
        drilling fluid.

     •  Reverse Hydraulic (reverse circulation)—In this procedure, the  flow
        of the drilling fluid is reversed, allowing the circulation of fluid
        from the bit up the rotating drill pipe to a settling pit.  This
        permits holes of larger diameters to be constructed.  The  integrity of
        the borehole is achieved by hydrostatic fluid pressures created  by
        maintaining the hole full of water during drilling operations.   The
        procedure is generally cheaper, and reduces the need  for specialized
        drilling mud control and development time required for normal mud
        rotary well construction.  However, there is the potential  for loose,
        permeable soils to cave in.

     •  Air Rotary—This method uses compressed air as the drilling fluid
        instead of water or drilling mud.  A high, uphole velocity of air is
        used to remove cuttings from the borehole.  This method is good  for
        consolidated rock drilling and will allow faster penetration and
        longer bit  life as long as water infiltration into the hole is small.

     •  Air Rotary with Pneumatic Hammer—Drilling equipment  capable of  using
        either air or drilling mud as  the fluid is modified to include tophead
        drive, casing hammer operations.  Such a rig provides the  ability to
        alter the method of construction to meet varying hole conditions
        encountered in the well.  The  use of a casing hammer  allows casing  to
        be installed through difficult drilling formations such as unconsol-
        idated surface deposits and then returns to either air or mud circula-
        tion drilling for hole completion.
                                      5-36

-------
               g.  Cable Tool


     The cable tool or percussion drilling method  involves  the  raising  and
lowering of a string of drilling tools suspended on a drilling  line  in  the
well bore, followed by bailing the drilled cuttings from  the hole.   Generally,
the well bore is kept open by the installation of  a casing  string  as  the
drilling operation proceeds to the completion depth.  Cable tooling  is  much
slower than rotary drilling methods.

     Conventional cable-tool equipment consists of a bit, a stem  for  length
and weight, jars to loosen stuck stem and bits, and a rope  socket  which
connects the entire string to the drill cable.

     The California stove pipe is a modification of the conventional  cable
tool.  It has the same basic operating principle as the conventional  cable
tool.  However hydraulic jacks are used to force the casing downward  rather
than driving the casing by the impact of tools; a  mud scow  is used as both a
drill bit and a bailer, and a thin pipe within a pipe is  used as  casing as
opposed to standard line pipe (Johnson Division, UOP, Inc., 1975).


          5.1.4.2  Well Completion


     Once the borehole has been opened, installation of a screen  filter pack
and grout is necessary to complete the well  prior  to well development.  The
method of completion is different for gravel pack  and natural wells.
               a.  Filter Pack Wells
     The method typically used  to complete  a well with  an  artificial  filter is
the double-casing method.  In this method,  a string of  outside  casing,
corresponding to the size of the outside diameter of  the filter pack  (i.e.,
the borehole), is installed as  the hole is  drilled or after  it  is  completely
opened.  A second string of casing containing  the well  screen is  then centered
within the outer casing.  The selected filter  material  is  then  placed between
the inner and outer casings and the outer casing is pulled back.   The outer
casing may be removed completely or left in place above the  level  of  the
screen.

     The top of the annular space above the filter is sealed with  grout  (e.g.,
cement, clay) as is the space between the outer casing  and the  aquifer.   The
top of the inner casing is sealed with a lead  slip packer.   Pumps  are then
installed into the inner casing and the well is developed.

     Jetted wellpoints are completed in a manner similar to  drilled wells.   In
this case, filter sands are packed around the  wellpoint and  grout  is  installed
from the top of the filter to the surface.  The grout prevents  surface water
                                     5-37

-------
infiltration into the well and minimizes the chances of air entering  the
we11point.
               b.  Naturally Developed Wells


     In consolidated formations, where the material  surrounding  the well  is
stable, groundwater can enter directly into an uncased well.  For  these
naturally developed wells, grouting and sealing are  done  prior to  installing
the screen.  If a temporary outside casing has been  installed during  drilling,
the casing must be removed while the grout is still  fluid.  This allows  for a
good seal between the borehole walls and  the grout.  Once  the grout has  set,
the plug can be drilled out and the well  screen installed.

     Numerous methods are available for installing well screens  depending on
the type of well screen used, the drilling equipment, the  geologic material,
and the presence of grout.  Once the well screen  is  installed, the pump  can be
placed within the casing.  Well development can then take  place  to ensure
adequate yield.
          5.1.4.3  Well Development


     Well development  is the process where  fine  soil materials  are  removed
from in and around the screen, allowing water  to  flow  freely.   This  process  is
accomplished through one or several methods  of surging water  or air  through
the well screen and into or out of the surrounding material.  The well
development process:

     •  Removes materials  that have built up in  the openings  of the  screen
        during the well drilling  and installation processes

     •  Removes fines  from the sides of the  borehole that  resulted  from the
        drilling procedure, e.g., drilling mud

     •  Increases the  hydraulic conductivity of  adjacent  geologic materials
        and the filter pack by removing fine materials

     •  Stabilizes the fine materials  that  remain in the  vicinity of the well
        and retards their  movement into the  well.

The benefits of well development  are increased yields, reduced  pumping  of
fines which can damage pumps, and decreased  corrosion  and  encrustation.


     5.1.5  Maintenance and Performance Monitoring


     Pumps, casing, and screens must be maintained  to  ensure  a  constant
reliable flow of water from the well.  Proper  well  maintenance  is especially

                                     5-38

-------
important in plume management because the loss of a well could result  in
contaminant escape.  The causes of well yield  loss and  failure are:
encrustation, corrosion, and pump failure which is typically caused by sand
intrusion, wear on mechanical parts, or electrical failure.

     Prior to beginning any well maintenance, a preliminary evaluation must
be conducted to identify whether or not the problem can be corrected.   Opera-
tional records will determine the normal operating conditions of the well  and
aid in evaluating the problem.  Removing the pumps and  checking the casing and
screens may be necessary.  This can also be accomplished by downhole video
equipment.

     General maintenance procedures that can be used  for encrustation,
corrosion, and related pump problems include:  chemical treatment of casings,
screens,  and pumps; mechanical and electrical maintenance of pumps and well
developments.  Chemical treatment involves the use of acids, biocides,  and
phosphates to dissolve deposits.  Acids are used to dissolve inorganic
substances which have formed (e.g., calcium, magnesium, and iron deposits).
Phosphates act as dispersing agents to help break up  clays, colloids,  and  some
metal deposits.

     The  performance of a pumping system should be monitored using observation
wells that are sampled periodically for contaminants.  The location of these
wells can be determined from the potentiometric surface maps.  Observation
wells should be located to monitor deadspots and areas where cones of
depression overlap.


     5.1.6  Technology Selection/Evaluation


     Groundwater pumping systems are the most versatile and flexible of the
groundwater control technologies.  As mentioned previously they can be used to
contain, remove, or divert a plume under a wide variety of geologic and
hydrogeologic conditions (confined and unconfined aquifer; consolidated and
unconsolidated materials to any depth; and homogeneous and heterogeneous
aquifers).  When used together with a barrier wall and a cap, complete  hydro-
logic isolation of a site can be achieved.   Groundwater pumping systems,
however, perform poorly in low transmissivity aquifers.

     Operational flexibility is high since pumping rates can be modified to
adjust to changes in flow rate.  System performance is generally good  provided
the wells are properly designed and maintained.  Deadspots and areas where
cones of depression overlap should be continuously monitored to ensure
effectiveness.   The reliability of pumping systems can be adversely affected
by mechanical and electrical failure of pump which can result in loss  of
contaminants.  However,  repairs and replacement of parts can be done quickly
and easily.

     Well systems are generally safer to install than drains and barrier walls
since there  is  no need for trench excavation.   Installation is relatively  easy


                                     5-39

-------
and quick.  Contractors qualified to drill and install wells are readily
available.

     One of the biggest drawbacks with pumping systems is  that operation  and
maintenance costs are high, especially when used as a long term remedial
action.
     5.1.7  Costs of Well Systems


     Costs of well systems for plume management can vary greatly  from  site  to
site.  Some of the factors that determine these costs are the geology,  the
characteristics of the contaminated and naturally occurring  groundwater,  the
extent of contamination, the periods and duration of pumping, local wage
rates, the availability of supplies and equipment, and  the electrical  power
required.  Costs associated with a well system can be categorized  as mobil-
ization costs, installation and removal costs, and operation and maintenance
costs.

     Mobilization costs include all costs incurred in obtaining equipment and
having it available at the site.  Some of the items included in mobilization
costs are (Powers, 1981):

     •  Installation equipment including drilling rigs, jetting equipment,  and
        well development equipment

     •  Pumping equipment including pumps, contacts, hoses,  and cables

     •  Standby equipment including generators, switches, pipes,  and cables

     •  Equipment rental, repair, delivery, and handling costs

     •  Utility installation

     •  Enclosures for storing equipment

     •  Engineering and geotechnical services including the  design of  the
        system, submittal preparation, field testing, and on-site  supervision
        during installation

     •  Waste, water, and soil treatment including transport, treatment,  and
        disposal

     •  Decontamination of drill rigs and tools

     •  Health and safety precautions

     •  Lodging and per diem for drilling personnel.
                                      5-40

-------
     Installation and removal costs include the costs  for crews  and  equipment
necessary to install the well system at the site.  These costs should  also
include allowances for setup, cleanup, foul weather, and other miscellaneous
delays that typically occur.  These costs are extremely dependent on the  con-
ditions under which the well or system must be installed.  Costs are generally
obtained for drilling on a per foot or time and material basis.  Some  reasons
for variations in well drilling and installation costs are:

     •  Well diameter

     •  Well depth

     •  Well components including well screens, casing, well pumps,  motors,
        controls, discharge columns, well heads, fittings, collector pipes,
        and power lines

     •  Drilling specifications (e.g., double cased versus single cased)

     •  Geologic material being drilled

     •  Health and safety requirements

     •  Sampling requirements

     •  Site access.

     Because of the above listed variables, the cost of well installation can
vary considerably from site to s.ite.  To accurately estimate costs associated
with the installation of a well system, as much information as is available
should be obtained and evaluated prior to system design.

     Operation and maintenance costs are typically high for pumping  systems.
In some cases, these costs can be greater than the initial installation and
mobilization costs.

     Removal costs will probably be incurred at all sites at some point when
pumping is no longer required.  Removal costs can be offset somewhat by the
salvage value of the removed equipment.  However, decontamination of the
equipment may be more costly than the salvage value.

     The above list of cost related items is not all inclusive;  some sites
will require additional items.  If  long-term operations are expected,
operation and maintenance and removal costs should include escalation factors.
Tables 5-4 through 5-6 give some typical costs that may be incurred  for th,e
items mentioned above.  These costs are presented as ranges and  variation can
be expected depending on the complexity of well specification and system
designs. Before costs can be accurately determined, detailed information  is
required.
                                     5-41

-------
                                   TABLE 5-4
                 1984 COSTS FOR SELECTED PUMPS AND ACCESSORIES
                         (STANDARD PUMPS AND JACUZZI)
Pump/Accessory
      Description
Cost Range
Je t Pump
  - shallow well

  - deep well

  - jets and valves

  - seals
  - foot valves
  - air volume controls
Submersible Pumps
  - 4-inch pump

  - control boxes
  - magnetic starters
  - check valves
  - well seals
Vacuum Pumps
  - diesel motors

  - electric motors
pumping depths: 25 ft
horsepowers: 1/3 to 1-1/2 hp
capacities: 60 to 27000 gph
pumping depths: 320 ft
horsepowers: 1/3 to 2 hp
capacities: 60 to 1000 gph
single pipe jets
double pipe jets
single or double pipe
pumping depths: 900 ft
horsepowers: 1/3 to 3 hp
capacities: 50 to 2000 gph
800-7000 gpm (48,000-
  420,000 gph)
800-7000 gpm (48,000-
  420,000 gph)
$200-500

$250-650

$40-100
$30-75
$15-40
$10-50
$10-30

$425-1500

$75-150
$160-250
$15-420
$20-120

$13,000-50,000

$9,000-35,000
Source:  USEPA,  1985
                                     5-42

-------
                           TABLE 5-5
          1985 COSTS FOR WELLSCREENS AND WELLPOINTS
    (Johnson Division, UPO, Inc., and Gator Plastics Inc.)
     Type
   Description
Costs
Drive Wellpoints
Wellscreens
Jetting Screens
  (fittings)
stainless steel,             $34-43/ft
1-1/4 to 2-inch
diameter

low carbon steel,            $16-30/ft
1-1/4 to 2-inch
diameter

PVC plastic,                 $5-6/ft
1-1/4 to 2-inch
diameter

stainless steel,             $33-540/ft
1-1/4 to 36-inch
diameter

low carbon steel,            $18-157/ft
1-1/4 to 36-inch
diameter

PVC plastic,                 $10-60/ft
1-1/4 to 12-inch
diameter

cast iron or mild steel,     $30-270/ft
2 to 12-inch
diameter
                             5-43

-------
                                   TABLE 5-6                          .
       1985 DRILLING COSTS FOR UNCONSOLIDATED MATERIALS AND INSTALLING
                          2- TO 4-INCH DIAMETER WELLS
Drilling Method
                    Average Production
                       Rates  (ft/hr)
                                                Range of
                                             Drilling Costs
Conventional Hydraulic
  Rotary

Reverse Circulation
  Hydraulic Roters

Air Rotary

Auger (Hollow Stem)

Bucket Auger

Cable Tool

Hole Puncher (Jetting)'
            7
Self Jetting

Mobilization
                            40-50


                            40-50


                            50-60

                            20-40

                            40-50

                             3-5
                                               $25-40/ft


                                               $35-45/ft


                                               $17-25/ft

                                               $ll-22/ft

                                               $10-20/ft

                                               $15-17/ft

                                               $40/ft

                                               $22/ft

                                               $500-600/rig
 Includes drilling, well material, and installation costs.

 "Includes rental of all necessary equipment, e.g., well points, pumps,  and
 headers.
Source:
(1)


(2)


(3)
Bias, S.  Empire Soils Investigations, Inc., Groton, NY.  Personal
communication, October-November 1984.

Baker, P.  P.C. Exploration, Inc., Roseville, CA.  Personal
communication, October-November 1984.

Craddock, D.F.  Stang Drilling & Exploration, Rancho Cordova, CA.
Written communication, May 15, 1981.
                                      5-44

-------
     The  complexity of developing  costs for groundwater  pumping systems  led
Geraghty  and  Miller, Inc. to develop a method for estimating total capital and
operating costs for deep wells based on the use of existing hydraulic models
(Lundy  and  Mahan,  1982).  They have  applied the model  to a number of scenarios
and the resulting  cost estimates provide considerable  insight  into how aquifer
characteristics affect cost and how  the cost of well system components
compares  to total  capital costs.

     Table  5-7  summarizes seven recovery system cost scenarios to which  the
cost methodology was applied.  For these scenarios, the  plumes were assumed to
be moving in  unidirectional flow fields and to have the  following dimensions:

     •  250 to  2500 feet wide

     •  500 to  5000 feet long

     •  25  to 250  feet deep.

     A high transmissivity (100,000  gal./day/ft.) is assigned  to four low-flux
scenarios.  A low  transmissivity (5000  gal./day/ft.) is  assigned to three high
flux scenarios.
   TABLE 5-7. SUMMARY OF SEVEN RECOVERY SYSTEMS COST SCENARIOS ($1985)*




AQUIFER AND PLUME CHARACTERISTICS
DESIGN PARAMETERS
Low Flux, High Transmissivity (100.000 gal/day/ft.)
(plume width x length x depth, ftl
-1260 x 600 x 25) 2 wells. 2gpm
-1250 x 500 x 2501 2 weHs; 2gpm
-12500x5000x25) 2 weds; 20gpm
-12600 x 6000 x 250) 2 wans, 20gpm
High Flux. Low Transmissivity 16000 gal/day/ft.l
-1250 ป 500 > 25) 4weซs,40gpm
-1250 x 500 x 2601 4 wells; 40gpm
-12500x5000x2501 4 weds; 400gpm




DELINEATION


83
166
220
441

83
166
441




DESIGN IK)


28-110
28110
28-110
28-110

28-110
28-110
28-110

ฃ

M
WELLS/DRAIN


165
55
16.5
66

33
121
143
tu
ff
1
3
3
SURFACE INFF


39
39
165
166

39
39
186

i
o

TREATMENT F,


33
33
44
44

55
55
121

4
O

M
WELLS/DRAIN


166
22
165
22

166
22
SO

I
&
n
TREATMENT II


5.6
55
5.6
65

16.5
165
66




MONITORING I


11
11
11
11

11
11
11




TOTAL K


198-281
320-402
474-667
744-827

237-320
408-490
900-981




TOTAL O&M


33
39
33
39

44
SO
116
 •Cost m thousands of dollars;
  Costs were updated to 1986 costs using the
  engmnnng Una fteco/t) Construction Con Indices tor 1W2 and 1966

 Source Modified from Lundy end Mahan, 1982
                                      5-45

-------
     As table 5-7 illustrates, the total capital costs range from $198,540 to
$981,670 or $982 to $3,970/ft.  O&M costs range from $33,090 to 115,815/year.
These costs probably represent the low end of costs encountered in the  field
because of the more complex hydrogeological conditions frequently encountered.
A large percentage of total capital costs are spent on plume delineation and
well design.  Plume delineation or remedial investigation costs vary  from
26 percent of the total capital costs for a small plume wtih contamination
depth of about 25 feet to 59 percent of total costs for a large plume with
contaminatin to considerable depths.  Well design costs range from only about
3 percent up to 39 percent.  The capital costs for the well system components
ranges from about 6 percent to 30 percent and O&M costs account for 37  to
57 percent of the total O&M costs.  Although well system costs are relatively
small, the discharge from the wells influences infrastructures and treatment
costs.  In a few of the scenarios presented, these two cost elements  are
significant and account for up to 44 percent of the capital cost and  48 per-
cent of the O&M costs.
5.2  Subsurface Drains
     5.2.1  Description
     Subsurface drains include any type of buried conduit used to convey and
collect aqueous discharges by gravity flow.  Subsurface drains essentially
function like an infinite line of extraction wells.  They create a continuous
zone of influence in which groundwater within this zone flows towards the
drain.  Subsurface drainage components are illustrated in Figure 5-17.

                              FIGURE 5-17.
               SUBSURFACE DRAINAGE SYSTEM COMPONENTS
                                     5-46

-------
The major  components of  a  subsurface  drainage  system are:

     •  Drain  pipe or gravel  bed—for conveying  flow to a  storage tank or wet
        well.  Pipe drains  are  used most  frequently at  hazardous waste sites.
        Gravel bed or french  drains and  tile drains are used to a more limited
        extent.

     •  Envelope—for conveying flow  from the  aquifer to the drain pipe or bed

     •  Filter—for preventing  fine particles  from  clogging  the system, if
        necessary

     •  Backfill—to bring  the  drain  to  grade  and prevent  ponding

     •  Manholes or wet  wells—to collect flow and  pump the  discharge to a
        treatment plant.
     5.2.2  Applications/Limitations


     Since drains essentially  function  like  an  infinite  line  of  extraction
wells, they can perform many of the same  functions  as wells.   They  can  be  used
to contain or remove a plume,  or to lower  the groundwater  table  to  prevent
contact of water with the waste material.  The  decision  to  use drains or
pumping is generally based on  a cost-effectiveness  analysis.

     For shallow contamination problems, drains can be more cost-effective
than pumping, particularly in  strata with  low or variable hydraulic con-
ductivity.  Under these conditions, it would be difficult to  design and it
would be cost-prohibitive to operate a  pumping  system to maintain a continuous
hydraulic boundary.  Subsurface drains may also be  preferred  over pumping
where groundwater removal is required over a period of several years, because
the operation and maintenance  costs associated with pumping are  substantially
higher.

     One of the biggest drawbacks to the use of subsurface  drains is that  they
are generally limited to shallow depths.   Although  it is. technically feasible
to excavate a trench to almost any depth,  the costs of shoring,  dewatering,
and hard rock excavation can make drains cost-prohibitive at  depths of  less
than 40 feet.  However, in stable low permeability  soils where little or no
rock excavation is required, drains may be cost-effective to  depths of  100
feet.

     The most widespread use of subsurface drains at hazardous waste sites is
to intercept a plume hydraulically downgradient from its source  (Figure
5-18a).  Frequently, these interceptor drains,  as they are  commonly called,
are used together with a barrier wall (Figure 5-18b).  There  are two primary
reasons for the interceptor drain/barrier  wall  combination.   In  the case where
                                     5-47

-------
                                       FIGURE 5-18.
      THE USE OF A ONE SIDED SUBSURFACE DRAIN FOR  REDUCING FLOW
                         FROM UNCONTAMINATED SOURCES
                                                                       Conventional
                                                                      Subsurface Dram
                                                                                   Original
                                                                                 Water Table
                                                                             Clean
                                                                             Water
                                                                           Recharging
                                                                          from Stream
Low Permeability
            a. The conventional subsurface drain
              receives recharges from the stream
              as well as the leachate plume,
              resulting in larger collection and
              treatment.
                                                                   Subsurface Drain with
                                                                   Clay or Plastic Barrier

                                                                            Original Water
                                                                                Table
        Low Permeability
             b. One-sided drainage reduces flow
               to drain.
Source: USEPA, 1985
                                            5-48

-------
a subsurface drain  is  to be placed just  upgradient  of  a  stream,  the drainge
system would reverse the flow direction  of  the  stream  and  cause  a prohib-
itively large volume of clear water  to be collected.   The  addition of a
barrier wall would  prevent  infiltration  of  clean  water from the  stream thereby
reducing treatment  costs.

     In another application, where the primary  remedial  action involves
installation of a downgradient barrier wall  to  contain wastes,  an interceptor
drain can be installed just upgradient of the wall  to  prevent  overtopping and
to minimize contact with wastes which may degrade  the  wall.

     Subsurface drains can  also be placed around  the circumference of a waste
site in order to lower the  groundwater table (Figure 5-19)  or  to  contain a
plume.  A circumferential subsurface drain may  be  part of  a total containment
system which consists of a  barrier wall  and  a cap  in addition  to  the
subsurface drain (Figure 5-20).

     In addition to depth, other limitations to the use  of  subsurface drains
include the presence of viscous or reactive  chemicals  which  could clog drains
and envelope material.  Conditions which favor  the  formation of  iron manganese
or calcium carbonate deposits may also limit the use of  drains.

     For hazardous waste site applications,  pipe drains  are  most  frequently
used.  French or gravel drains can be used where the amount  of water to be
drained is small and flow velocities are low.   If used to handle  high volumes
or rapid flows, these drains are likely to fail due to excessive  siltation,
particularly in fine grained soils.  Tile drains have  not been widely used in
hazardous waste site applications.


     5.2.3  Design


     The major elements to consider  in designing a  subsurface drainage system
include:

     •  Location and spacing of drains to achieve desired head levels
     •  Hydraulic design of the conduit including pipe diameter and  gradient
     •  Properties and design of the envelope and filter materials
     •  Design of a pumping station.

Each of these design elements is discussed in this  section.


          5.2.3.1  Location and Spacing of Drains


     For the purposes of designing subsurface drainage systems, drains  have
been divided into two categories based on their function:   interceptor  and
                                     5-49

-------
                                         FIGURE 5-19.
       THE USE OF SUBSURFACE DRAINAGE TO LOWER GROUIMDWATER  LEVELS
                                                                                    Map View


                                                                       -Waste Disposal Site


                                                                       • Subsurface Dram
                                                                        Collected Groundwater
                                                                         Pumped to Receiving
                                                                              Stream
                                                                                    Cross Section

                                                                         Waste Disposal Site
                                                                                Original Water Table
                                          Lowered Groundwater Table
                                             Under Disposal Site
Source: USEPA, 1985
                                             5-50

-------
                                  FIGURE 5-20.
      THE USE OF SUBSURFACE DRAINAGE IN A COMPLETELY ENCAPSULATED SITE
                  Backfill
                                           Clay Cap
                                                                 Barrier Wall
                                                              Subsurface Drain
        Source: USEPA, 1985
relief drains.  Interceptor drains  are  installed  perpendicular to groundwater
flow and are used  to  intercept  groundwater  from an upgradient source.  Relief
drains are installed  parallel  to  the  direction of flow or around the perimeter
of a site where the water  table is  realtively flat.   Relief drains are used
primarily to lower the water  table  beneath  a site.   Figure 5-21 shows the
effect of interceptor and  relief  drains  in  altering  the configuration of the
water table.
               a.  Locating  Interceptor Drains
     Determining  the  required  location for an interceptor drain is more often
based exclusively on  the  use of  field  data than on theoretical design.
Remedial investigation data are  used  to develop potentiometric surface maps,
hydraulic conductivity data, plume boundary limits, and geologic cross-
sections.  With this  data in hand,  the design engineer can pinpoint and stake
the design drain  line.  Additional  borings are then taken along this line and
the alignment shifted if  needed  to obtain proper interception.

     To  function  properly, an  interceptor drain should be installed perpen-
dicular  to groundwater flow direction.   In stratified soils having greatly
different hydraulic conductivities, the drain should be installed resting on a
layer of low hydraulic conductivity.   If the trench is cut through an imper-
vious stratum, there  is danger that a  significant percentage of the leachate
moving laterally  will bridge over  the  drain and continue downgradient.
Similarly, if soil layers or pockets with high hydraulic conductivity underly
the drain, the leachate may flow beneath the drain.

                                     5-51

-------
 z

 o
 •z
 E
 LU
 b
 <

 zy


 \l
 < cc
 CC LU
LU O u.

งEO

gi5


 P
 < 3
 LL CD
  u.
  LL
  LU

  X
E il
il S O _
'ซ? „ซ>
ฃ i)
nS

Iff
^O S
•2 ง a
3 .2 ^i
2 o i
"ง.-ฃ 5
X uJ Q

II II II
v a
_ -0 -1




V
.c
o
tn *:
= -S
A 5
•a Q 0
g S 5 ป
•ง IS 3
S o ซ 5!
as CD S
1/5 3x: |
If II
Ql Q =
II " "

'_il Q







CO
2

ป
C/)
o
w
3
o
C/J
                         5-52

-------
     The problem  of  underflow beneath the drain  has  been solved at waste sites
using various  approaches.   Underflow can be minimized  by placing impermeable
liner material  at the  base of the trench before  laying a thick (1 to 3 foot)
gravel bedding.   Where pockets of highly permeable soils are found (e.g.,
scour channel  in  an  alluvial area), it is possible to  construct a manhole at
the lowest point  of  the permeable soil and to  install  a small lift station and
force main to  carry  the leachate from this low area  back up to the adjacent
gravity flow section of the drainage system (see Figure 5-22).  A third
solution is to  install a barrier wall downgradient of  the drain and key it in
to a low permeability  layer.

     In order  to  decide where to position a drain, the design engineer will
need a reasonably good estimate of the upgradient  and  downgradient influence
of the drain.   In general, the shape of the drawdown curve upgradient of the
site is independent  of hydraulic conductivity  but  is a function of head.
Therefore, the  influence of the drain extends  for  a  distance which is greater
the more gradual  the water table gradient.  Theoretical determination of the
                                 FIGURE 5-22.
                   SUBSURFACE DRAIN WITH A LIFT STATION
  MAIN LIFT STATION MANHOLE
         AND PUMP
                                               SUPPLEMENTARY MANHOLE
                                                   AND LIFT PUMP
                                CLEAN GRAVEL
                                2^uLซUJCEUE3S
                                fS^SSSSJ^^SSS^SSS
                                GRAVITY DRAIN PIPE
                                 GRAY TILL
                                                               SCOUR CHANNEL
                    I (VIEW LOOKING TOWARD SITE)
Source: Giddings, 1982
                                      5-53

-------
upgradient influence can be expressed by the following equation developed by
Glover and Donnan (1959) and described by Van Hoorn and Van der Molen  (1974):
          D  = 1.33 m I                                                   (5-8)
           u         s
where:
          D  = Effective distance of drawdown upgradient (ft)

          m  = Saturated thickness of the water bearing strata not affected
               by drainage (ft)

          I  = hydraulic gradient (dimensionless).

The depth to which the water table is lowered downgradient of the  interceptor
is proportional to the depth of the drain.  Theoretically, a true  interceptor
drain lowers the water table downgradient to a depth equal to the  depth of the
drain.  The distance downgradient to which the drain is effective  in lowering
the water table is infinite provided recharge is not occurring.  This  is never
the case since infiltration from precipitation always recharges the
groundwater.

     In some cases, it is not necessary to know the downgradient influence of
the drain.  It may be adequate to cut-off the upgradient source of the plume
and allow contaminated groundwater downgradient to continue on its course.
This will depend on the size of the plume and the use of groundwater
downgradient.

     The theoretical determination of the downgradient influence can be
obtained from the following equation (Figure 5-23):

          Dd = (Kl/q) (dg - hd - D2)                                     (5-9)

where:

          D, =  downgradient influence (ft)

          K  =  hydraulic conductivity (ft/day)
          I  =  hydraulic gradient (dimensionless)

          q  =  drainage coefficient (ft/day)
          d  =  depth of drain (ft)

          h  =  desired depth of drawdown (ft)
          D  =  distance from ground surface to water table prior  to drainage
                at the distance D  downgradient from the drain (ft)
                                 a
     In the equation given above, D, and D- are interdependent variables.  In
obtaining the solution to the equation, the value of D  is estimated,  then a
                                     5-54

-------
                                 FIGURE 5-23.
     SYMBOLS FOR THE GLOVER AND DONNAN EQUATION FOR CALCULATING THE
              DOWNGRADIENT INFLUENCE OF AN INTERCEPTOR DRAIN
                                      Original Water Table
                                                      Water Table
                                                     After Drainage
   Source: USEPA, 1985
trial computation  is made.   If  the  actual  value of D_ at distance D  is
appreciably different,  a  second calculation is necessary.  Where I is uniform
throughout the  area, D  can  be  considered  equal to D. (i.e., the distance from
the ground surface  to the water table  measured at the drain).  If a second
interceptor is  needed to  lower  the  water  table to the desired depth, it would
be located D, feet  downgradient from  the  first.
               b.  Depth  and  Spacing  of  Parallel  Drains
     This section presents  basic  equilibrium equations for estimating the
spacing of drains under  two conditions:   drains  resting on an impermeable
layer and drains above an impermeable  layer.   These equations assume that
steady state conditions  exist,  recharge  distribution and leachate generation
over the area between the drains  is  uniform,  and the soil is homogeneous.
Since real world situations rarely meet  these criteria, results obtained using
these equations should be considered approximate and a conservative design
approach should be taken to ensure that  the  desired head levels are
maintained.  Numerous computer  models  are available for obtaining more exact
solutions to drain spacing  problems.

     Drains on an "Impermeable" Barrier—Drains  are often used where the depth
to a low permeability barrier is  relatively  shallow and the  drains can be laid
just above the barrier.  In developing and using drain spacing formulas for
this case, an underlying soil layer  is considered to be "impermeable" if the
                                     5-55

-------
hydraulic conductivity is less than one-tenth that of the above soil layer
(Wesseling, 1973).

     Flow to drains resting on a low permeability layer is illustrated  in
Figure 5-24.  This flow can be represented by an equation developed by  Donnan
(1946) and described by Wesseling (1973):

          L = [(8KDH + 4KH2)/q]ฐ'5                                       (5-10)

where:

          L = drain spacing (ft)

          K = hydraulic conductivity of the drained material  (ft/day)

          D = distance between the water level in the drain line and the
              impermeable barrier (ft)

          H = water table height above the drain levels at the midpoint
              between two drains (ft)

          q = leachate generation rate (ft/day).

     For a pipe drain resting on an impermeable barrier, the  parameter  D
approximately equals the radius of the pipe and hence is very small in
comparison to H (the water table height above the drain).  This allows
equation 5-10 to be simplified to:

     L =  [(4KH2)/q]ฐ-5                                                   (5-11)

     As Figure 5-24 illustrates, when two parallel drains are installed, each
exerts an influence (L or the drain spacing), which in theory will  intersect
with each other midway between the drain lines.  The influence (L)  is the
distance  from the drain to a point where the drawdown can be  considered
insignificant and is commonly referred to as the zone of influence.

     Drain spacing (L) and hydraulic head level (H) in the equations are
interdependent design variables which are a function of the leachate
generation rate (q) and hydraulic conductivity (K) of the drained material.
Assuming  constant leachate generation and hydraulic conductivity, the closer
two drains are spaced the more their drawdown curves will overlap and the
lower the hydraulic head levels between the drains will be.

     Successful application of a subsurface drainage system under these condi-
tions requires that the drains can be placed close enough together  to inter-
cept the  entire plume or to lower the groundwater table to the level required
to prevent contact of the water with the waste material.  However,  a minimum
drain spacing may be imposed by the boundaries of the waste because excavation
through the waste material qan be extremely hazardous.
                                     5-56

-------

   DC
   UJ

   CC
   cc
   CO
   <
   UJ
   5
   cc
   UJ
   Q.


sl
lA-1
UJ ^
cc -^

ง0
  UJ
  cc
  cc
  Q
                                I-


                              5-57

-------
     Drains Above  a Low Permeability Barrier—In many instances,  it may  not  be
possible to install drains  to  the depth of a low permeability barrier  because
the cost of installing drains  to  this level is prohibitively high or because
the plume does not extend  to  the  depth of the barrier.  In these  instances
flow is not adequately described  using equations 5-10 and 5-11.

     Figure 5-25 illustrates  the  flow to a drain not resting on a low
permeability layer.   The  flow lines are not parallel and horizontal  as shown
in Figure 5-24, rather, they  converge towards the drains.  The convergence,  or
radial flow as it  is  commonly called, causes a more than proportional  loss  of
hydraulic head because the  flow velocity in the vicinity of the drains is
larger than elsewhere in  the  flow region.  The effect is that the elevation of
the water table and the drain spacing would be larger than would  be  predicted
using equation 5-10.

     Hooghoudt (1940) as  described by Wesseling (1973) developed  a modified
drain spacing formula which accounts for radial flow and head loss.  His
method accounts for head  loss by  using an equivalent depth, d, to replace  D in
equation 5-10.  The equation  can  be used to describe the conditions  shown  in
Figure 5-25, that  is, flow to drains which are installed at the interface  of a
two layered soils  with hydraulic  conductivities of K. and K . For this
condition, the equation can be written as:
     L =  [(8K2dH  +  4K1H

where the new  terms are  defined as:

      d = equivalent depth (ft)
     K. = hydraulic conductivity of the layer above the drain  (ft/day)
     K  = hydraulic conductivity of the layer below the drain  (ft/day).


                                FIGURE 5-25.
        FLOW TO DRAIN NOT RESTING ON A LOW PERMEABILITY BARRIER
                                                                          (5-12)
                                            Water Table
__ _^a^j&ป _ —
r"
K2 C
^
; 	 1 	 	
d
'..L 	
	 L 	
••• •"" — " —*Q^*
^/^
•^ Flow
1
	 1-
1
1
- "- -"- .T J
— - •*— ^~~ -^ ^"^
\. Horizontal
\^-\ Flow
\ *
: 	 .rv — ^" — -r IT" — -Ti:
Low Permeability
Layer
         Adapted from Van Schilfgaard, 1974.
         Drainage for Agriculture, Agronomy
         Monograph No. 17. Pages 245-270.
                                      5-58

-------
     In equation 5-12 both drain spacing L and equivalent depth d  are
unknowns.  The value of d is typically calculated  from a specified value  for
L, so that equation 5-12 cannot be solved explicitly  in terms of L.  The  use
of this equation as a drain spacing  formula  involves  either  a trial  and error
procedure of selecting d and L until both sides of the equation are  equal or
the use of nomographs which have been developed specifically for equivalent
depth and drain spacing (see Wesseling, 1973).

     For saturated thicknesses (D) greater than 32.8  feet,  the equivalent
depth can be calculated from drain spacing using  the  following equation
(USEPA, 1985):

     d = 0.57(L) + 0.845                                                (5-13)

     Again, it should be noted that  the Hooghoudt  equation,  though widely used
in drain spacing, is only accurate when the  level  of  the drain corresponds
with the interface between the two soil levels.  When drains are being placed
so that the interface lies either above or below  the  drains, drain spacing may
not be accurately predicted by this  formula.   Computer models or  equations
developed by Ernst (1962) and described by Wesseling  (1973)  could  be used for
a more accurate prediction of drain  spacing.


          5.2.3.2  Pipe Diameter and Gradient


     Pipe diameter and gradient are  the design parameters used to  ensure  that
water which arrives at the drainline can be  conveyed  without a build up of
pressure.  The formula used for hydraulic design of pipes is based on the
Manning formula for pipes which is:

     Q = ARฐ'67 I ฐ'5/N                                                 (5-14)

where:
                          2
     A = drainage area (ft )

     Q = design discharge (ft /sec)

     R = hydraulic radius (ft) equal to the  wetted cross-sectional area A_
         divided by the wetted perimeter (1/4  the  diameter  for full  flowing
         pipes)

     I = hydraulic gradient

     N = roughness coefficient.

Each of these factors is described further below.
                                     5-59

-------
               a.  Hydraulic Gradient and Roughness Coefficient
     In designing subsurface drainage systems, a gradient is chosen which is
great enough to result in a flow velocity that prevents siltation (>1.4 feet
per second) but will not cause turbulence (critical velocity) (SCS, 1973).
Velocities of less than 1.4 feet per second are acceptable if filter fabrics
are used to prevent filtration.  Critical velocities for various soil types
are summarized below (SCS, 1973):


                Soil Types              Velocity (ft/sec)

          Sand and Sandy Loam                   3.5
          Silt and Silt Loam                    5.0
          Silty Clay Loam                       6.0
          Clay and Clay Loam                    7.0
          Course Sand and Gravel                9.0
     Table 5-8 gives the gradients for different sizes of drains which result
in the critical velocity for drains with a roughness coefficient of 0.011,
0.013, and 0.015.  The roughness coefficient is a function of the hydraulic
resistance of the drain material.  It should be obtained from the pipe
manufacturer prior to hydraulic design.  Commonly used drainage pipes include
perforated PVC and flexible corrugated PVC (favored for their low cost and
chemical resistance); steel (rugged, more costly, subject to corrosion);
aluminum (light weight, easy to handle, subject to some forms of corrosion);
and vitrified clay.


               b.  Design Discharge


     Design discharge, Q, is equal to the sum of the individual discharges
which impinge upon the drain.  Estimates of the total discharge can be
obtained using the water balance method.  This method provides an estimate of
the amount of percolation that will recharge the water table between the lines
of the drain.  Once the percolation rate has been calculated, discharge can be
obtained by multiplying the percolation route by the drainage area:

     Q = q x A                                                          (5-15)

where:

                                3
        Q = design discharge (ft /sec)

        q = leachate generation rate (ft/sec)
                             2
        A = drainage area (ft ).
                                     5-60

-------
                                   TABLE 5-8

                 DRAIN GRADES FOR SELECTED CRITICAL VELOCITIES


Drain Size
(Inches) 1.4
Velocity

3.5 5.0
(ft/sec)

6.0 7.0


9.0
                           Grade—feet per 100 feet



                        For drains with "N" = 0.011(a)

4
5
6
8
10
12


4
5
6
8
10
12

Clay Tile, Concrete
0.28
0.21
0.17
0.11
0.08
0.07

Clay Tile, Concrete
0.41
0.31
0.24
0.17
0.12
0.09

Tile, and
1.8
1.3
1.0
0.7
0.5
0.4
For drains
Tile, and
2.5
1.9
1.5
1.0
0.8
0.6
For drains
Concrete
3.6
2.7
2.1
1.4
1.1
0.8
with "N"
Concrete
5.2
3.9
3.1
2.1
1.6
1.2
with "N"
Corrugated Plastic
4
5
6
8
10
12
0.53
0.40
0.32
0.21
0.16
0.13
3.3
2.5
2.0
1.3
1.0
0.8
6.8
5.1
4.0
2.7
2.0
1.6
Pipe (with
5.1
3.9
3.1
2.1
1.5
1.2
= 0.013
Pipe (with
7.5
5.6
4.4
3.0
2.2
1.8
= 0.015
Pipe
9.8
7.3
5.8
3.9
2.9
2.3
good alignment)
7.0
5.3
4.1
2.8
2.1
1.6

fair alignment)
10.2
7.7
6.0
4.1
3.0
2.4


13.3
9.9
7.9
5.3
4.0
3.1

11.5
8.7
6.9
4.6
3.5
2.7


16.8
12.7
10.0
6.8
5.0
3.9


21.9
16.6
13.2
8.8
6.6
5.1

(a)
   "N" is the roughness coefficient and must be obtained from pipe

   manufacturer.



Source:  SCS, 1973



                                     5-61

-------
               c.  Pipe Diameter


     The diameter of the drain pipe  is a  function  of  design  discharge,
hydraulic gradient, and the roughness coefficient.  With  this  information,  the
appropriate drain diameter can be determined based  on the Manning velocity
equation (5-14) or from nomographs prepared using  the Manning  formula.   Figure
5-26 is a nomograph for estimating pipe diameter for  pipe with an N value of
0.015.  A pipe diameter one size larger than that  determined to be necessary
is generally recommended.


          5.2.3.3  Filters and Envelopes


     The primary function of a filter is  to prevent soil  particles  from
entering and clogging the drain.  Filters  should always be used where  soils
have a high percentage of fines.

     The function of an envelope is  to improve water  flow and  reduce  flow
velocity into the drains by providing a material that is more  permeable than
the surrounding soil.  Envelopes may also  be used  to  provide suitable  bedding
for a drain and to stabilize the soil material on  which the  drain is being
placed.  Envelopes are required for most  applications.

     Although filters and envelopes have distinctly different  functions, well
graded sands and gravels can be used to meet the requirements  of both  a filter
and an envelope.

     Geotextiles are also widely used as  filters.   They are  generally  made  of
polypropylene, polyethylene, polyester, or polyvinyl  chloride.  Filter fabric
should be selected based on its compatibility with the leachate.

     The general procedure for designing  a gravel  filter  is  to:   (1) make a
mechanical analysis of both the soil and  the proposed envelope material;
(2) compare the two particle distribution  curves;  and (3) decide by  some set
of criteria whether the envelope is  satisfactory.   SCS (1973)  and others
developed various criteria which set size  limits for  a filter  material based
on the size of the base material.  A filter is considered satisfactory if it
allows some of the fine soil particles to  pass through so as not  to  plug the
filter but retains larger particles  which  would deposit in the drain.

     For synthetic materials the suitability of a  filter  can be determind from
the ratio of particle size distribution to the pore size  of  the fabric.

     The first requirement of sand and gravel envelopes is that the  envelope
have a hydraulic conductivity higher than  that of  the base material.   SCS
(1973) generally recommends that all of the envelope  material  should  pass the
1.5-inch sieve, 90 percent should pass the 0.75-inch  sieve,  and not  more than
10 percent should pass the No. 60 sieve (0.01-inch).   This minimum  limitation
is the same for filter materials, however, the gradation  of  the envelope is
not important since it is not designed to  act as a filter (SCS, 1973).

                                     5-62

-------
                             FIGURE 5-26.
                     CAPACITY CHART FOR N = 0.015
               Drain Capacity Chart —  N = 0.015
                Drain Diameter
                 (Flowing Full)
                   N  = 0.015
   O  00000
                               d   o'  o'ooooo
                  Hydraulic Gradient (Feet per Foot)
                                                                 c
                                                                 o
                                                                 o
                                                                 0)
                                                                 (A
                                                                 0)
                                                                 a
                                                                 0)
                                                                 u.
                                                                 o
                                                                 !n
                                                                 3
                                                                 O
                                                                 u
                                                                 n
                                                                 a.
                                                                 a
                                                                 O
Source: Soil Conservation Service, 1973
                                5-63

-------
     A minimum thickness of four inches is reconmended for a gravel envelope
(Bureau of Reclamation, 1978).
          5.2.3.4  Design of Manholes


     Manholes are used in subsurface drainage systems to serve as junction
boxes between drains; silt and sand traps; observation wells; and access
points for pipe location, inspection, and maintenance.  Manholes should be
located at junction points, changes in alignment or grade, and other
designated points.  There are no set criteria for manhole spacing.

     A manhole should extend from 12 to 24 inches above the ground surface  for
ease of location.  The base of the manhole should be a minimum of 18 inches
below the lowest pipe to provide a trap for sediments.  Manholes are typically
designed to have a drop in elevation between the inlet and outlet pipes to
compensate for head losses in the manhole (Bureau of Reclamation, 1978).  A
typical manhole design is shown in Figure 5-27.
          5.2.3.5  Design of the Sump and Pumping System
     Contaminated groundwater is collected by gravity flow in a drainage  sump
from which it is pumped to treatment (Figure 5-28).  The major steps in
designing the sump and pumping system include (Bureau of Reclamation,  1978):

     •  Determine the maximum inflow (Q ) to the sump:  Maximum inflow is
        based on total discharge (Q).   An extra 20 percent allowance  is
        usually made for flows in excess of design discharge.

     •  Determine the amount of storage required:  The cycling operation  of
        the pump determines the amount of storage required.  Maximum storage
        occurs when the inflow rate is one half of the discharge of the pump.
        Therefore, storage volume (S ) is equal to one half the cycling time
        (6 for a 12 minute cycle pump) times Q •
                                                        o
     •  Determine the pumping rate:  Pumping rate Q  (ft /min) is determined
        from the following expression:
where :
               (S  + Q t )/t                                             (5-16)
                 v   xp p   p
                               3
          Q  = pumping rate  (ft /min)
           m                     2
          S  = storage volume ( f t )
           V                     3   .
          Qp = maximum inflow (ft /min)

          t  = running time  of the pump  (min) .
                                     5-64

-------
                                 FIGURE  5-27.
        TYPICAL MANHOLE DESIGN FOR A CLOSED DRAIN
                                             Handles
      Note: Use chain or other locking
            device between handles.

                PLAN
                                       *4 Bars @ it"
                                        o.c. both ways in
                                        center of cover

                                         Handle-*4 bar
                                                            COVER
All joints
 to be
 grouted-
 Flow\^
                                          -12 Mm
                                           24"MO it
Ground surface*
                                                      T*F?
-36"Mm. for dram Dipt up
 to and including if diameter
 Manholes receiving three
 or more large size pipe and
 all boxes receiving larger
 than le'pipe should have
 a dimension of 4t".

'Standard precast unrein-
 forced concrete pipe.

          *4  Barsฎit"
           o.c. both ways
           center of base
                            ** bors
                                     4-A
                                     J  ?
                                    ^^
                                                                          *
                                                                           *l
                                                                          |
                                                                          ~r
                                                                             \
   Break lower section of manhole in the
    field so that rough circular opening is
    formed to receive pipe. After sections are
    fitted in place, grout carefully
    to bring pipe to grade and place grovel
    packing  around pipe as directed.

        VERTICAL  SECTION

Source: Bureau of Reclamation,  1978
                                               Loops, if used, should be placed J
                                                close to inside of manhole —^

                                                             BASE
               -Concrete base, precast or
                 cost in place, square or
                 round.
                                       5-65

-------
                           FIGURE 5-28.
   TYPICAL DESIGN OF AN AUTOMATIC DRAINAGE PUMPING PLANT
                  - Meter
                                       Door
                                        Start Collar
                                        Float Switch
                                        Ground Surface, El. 1306.0
      Pump Supports
       Start Level
      Pipe Collector

             E
         El. 1296.0 -
      Stop Level
          Concrete Base

     Source: Bureau of Reclamation, 1978
    Pipe Collector
Plug
Round Sump
Stilling Chamber
Determine the start,  stop,  and discharge  levels:  In general, the
maximum water level  for  starting the pump should be at  about the top
of the  pipe drain discharging to the sump.   The minimum elevation
should  be about 2 to  4  feet above the base  of the sump.

Determine the size of the  sump:  The volume required for storage plus
the criteria that the minimum water level should be 2 to 4 feet above
the bottom of the sump  determines the size  of the sump.

Select  the pump:  As  described in Section 5.1, selecting a pump for a
particular application  requires that the  total head capacity be
determined.  Manufacturers' performance curves can then be used to
determine pump efficiency  and necessary horsepower.  Centrifugal or
diaphragm pumps are generally used.
                               5-66

-------
      5.2.4  Construction
     The major activities associated with construction  of  subsurface  drains
are  trench excavation,  trench  stabilization,  and  installation of  the  drains
and  filter and envelope materials.
          5.2.4.1  Trench Excavation  and Associated Activities

               a.  Trench Excavation

     Trench excavation  is one of  the  most  critical elements  in  determining  the
cost-effectiveness of drains.  The need for extensive rock fragmentation may
result in exclusion of  drains as  a cost-effective remedial action.
     Trench excavation is usually accomplished using either  trenching machines
or backhoes.  Cranes, clamshells, and draglines  are also used  for deep
excavation.

     Trenchers or ditchers are designed to provide continuous  excavation  in
soil and we 11-fragmented or weathered rock.  They consist of a series of
buckets mounted on a wheel (bucket-wheel  type) or a chain sprocket  and  ladder
(bucket-ladder type).  In continuous trenching,  the wheel or ladder  is  lowered
as the revolving buckets excavate the trench to  the appropriate depth.  The
trench assembly may be mounted on wheels  or on semi-crawler or full-crawler
frames.  The trencher moves forward simultaneously as  the trench is  excavated,
resulting in a trench of neat lines and grades.  The bucket wheel types are
generally used to dig shallow trenches for agricultural drainage.  The maximum
depth for a large wheel trencher is about 8.5 feet (Church, 1981).   Bucket-
ladder type trenchers can excavate trenches up to 27 feet deep and about 6
feet wide, although 4 feet is the maximum economical width (Church,  1981).
Different sizes of bucket-wheel-type trenchers are available for various
depths and widths.  Buckets may be changed to fit the  type of  soil being
excavated.

     The factors that influence the rate  of trenching  include:  (1)  soil
moisture;  (2) soil characteristics such as hardness, stickiness, stones;
and (3) depth and width of trench.

     Generally, continuous trenching in suitable materials is  much  faster than
trenching via backhoe.  Hourly production rates  for wheel and  ladder trenches
operating at 100 percent efficiency is given in  Table  5-9.  Actual efficien-
cies may range from 20 to 90 percent depending upon the above  mentioned
factors (Church, 1981).

     Trenchers can be equipped with back-end modifications to  provide shoring,
install a geotextile envelope, lay tile or flexible piping, blind the piping,
and backfill with gravel or excavated soil.
                                     5-67

-------
                                   TABLE 5-9

          APPROXIMATE HOURLY PRODUCTION IN CUBIC YARDS FOR LADDER AND
              WHEEL TRENCHERS OPERATING AT 100 PERCENT EFFICIENCY
        Rock-earth formation
Engine hoursepower of trencher

    50    100    150    200
Alluvium, sand-gravels, lightly cemented
Weathered rock-earth:
• Maximum weathering
• Minimum weathering
210
180
120
60
420
360
240
120
630
540
360
180
840
720
480
240

Source:  Church, 1981

backhoes can excavate earth and fragmented rock up to one-half of the bucket
diameter to depths of up to 70 to 90 feet.

     The crane and clamshell can be used  for deeper excavation or when access
excludes the use of the backhoe.  Use of  draglines is generally limited to
removal of loose rock and earth.  Operation and production rates for backhoes,
cranes, and clamshells are described in Section 7.1.

     Excavation of a trench through material containing numerous large
boulders or hard rock layers results in considerable construction delays and
substantially increases the cost of construction.  Typically, these materials
must be fractured to facilitate their removal.

     The most commonly used method for fragmenting rock in hazardous waste
site work involves the use of rotary or percussion drills; backhoe-mounted
pneumatically driven impact tools (Hobgoblin); and tractor-mounted mechanical
rippers.  The Hobgoblin has a low production rate of about six cubic yards  per
hour (Richardson Engineering Services, 1980).  Mechanical rippers have con-
siderably higher production rates than the other methods, but they are limited
to depths of 6 feet or less and are not suitable for highly consolidated rock.
The depth limitation can be overcome to some extent if the ripper can enter
the trench to rip lower lifts, but this becomes uneconomical  since the trench
width clearance increases the volume of material to be excavated.  Blasting,
though commonly used in the construction  industry for rock fragmentation, is
not recommended for hazardous waste site  work.
                                     5-68

-------
               b.  Grade Control
     Proper grade control in a  subsurface drain  ensures  against  ponding of
water and provides for a nonsilting velocity  in  the drainage  pipe.   Proper
grade control can be accomplished using either automatic  laser or visual
grade-control systems.  Laser systems are adaptable to a  wide range  of  earth-
moving equipment including trenchers and backhoes.

     In visual grade control, grade stakes of equal length  are driven to the
design subgrade at selected points along the  trench line.   A  line drawn
through the top of the grade stakes would be  parallel to  the  design  grade of
the trench.  Targets are driven next to the grade  stakes  and  are adjusted to a
fixed distance above the elevation of the grade  stakes.   The  selection  of this
distance depends on the depth of the trench and  the line  of sight between the
machine operator and a reference sighting rod on the machine.  When  the
trenching machine is cutting on grade, the target  will align  with the
reference sighting rod.

     Accuracy of plus or minus  0.1 foot is easily  obtainable  with the target
method, although it depends upon the machine  operator's  skill and alertness.
If the depth of the trench is also checked with  respect  to  the design grade  at
each target point, the target grade control method can attain an accuracy
within plus or minus 0.02 foot  of the design  grade (Taylor  and Willardson,
1971).
               c.  Dewatering


     Proper installation of drains  (i.e., maintenance  of  grade,  placement  and
alignment of pipes) generally  requires dewatering  to  achieve  a dry environ-
ment.  Three basic options are available  for  dewatering:   open pumping,  pre-
drainage using wellpoints or well systems,  and  groundwater cutoff.   These
techniques may be used separately or  in combination.   Open pumping involves
construction of a sump hole or pit  at  the  lowest point of the excavation so
that water can flow towards and collect in  the  pit.   A centrifugal submersible
pump or a diaphragm pump can then be  used  to  pump  the  accumulated  water  from
the sump holes.  Any contaminated water is  subsequently treated.   Open pumping
is applicable only to shallow  trench  excavations with  stable  soils of low
hydraulic conductivity where groundwater  seepage into  the excavation is
minimal (Powers, 1981).  It is often  used  together with predrainage where
wells or wellpoints have reduced seepage  to a manageable  volume.

     Wellpoints and deep wells can  be  used  to lower  the water table near a
trench excavation.  Wellpoints are  one of  the most widely used and most
versatile dewatering technologies.  The use of  wellpoints and deep wells and
their associated costs are discussed  in Section 5.1.

     Groundwater cut-off barriers such as  steel sheet  piling, concrete,  or a
bentonite slurry may also be used together  with wells  and wellpoints to  reduce


                                      5-69

-------
the size of the predrainage system required.  These methods  are  described  in
Section 5.3.
               d.  Wall Stabilization Methods
     Trench excavations generally require the use of wall  stabilization
methods to prevent cave-ins during  installation of drain  pipes.  With  shallow
trenches in stable soils, the need  for shoring can be  eliminated by cutting
the trench with sloped walls so that a stable angle  is attained  (usually a 1.5
[horizontal] to 1 [vertical] slope).

     Shoring, which involves supporting  the  trench wall with  wood  or steel
structures, is the most commonly used method of wall stabilization.  Shoring
methods for supporting shallow trenches  involve the  use of slipshields
(constructed on-site by welding I-beams  between two  parallel  pieces of sheet
steel) and adjustable aluminum bracing.

     For trenches which are deeper  than  about 10 feet, steel  sheet piling or
steel H-piles with horizontal wooden beams between them can be driven  and
braced to support the trench walls.
          5.2.4.2  Drain Installation
     Once trench excavation is completed, the components of  the  subsurface
drain can be installed.  This process includes  laying  the pipes,  filter,  and
envelope material; backfilling; and installation of auxiliary  components.


               a.  Laying the Pipes


     All subsurface drains must be laid on a stable bed with the  desired
grade.  Trenches that have inadvertently been overexcavated  should be  refilled
with dry soil and brought to grade with envelope material.   Well-graded gravel
is then laid in an even layer several inches thick to  provide  bedding  for the
pipes.  Flexible piping must be installed in a  way that ensures  firm  support
for its entire circumference.  This may be accomplished by shaping a  semi-
circular groove in the trench bottom so that the gravel fill forms a  cradle
for the pipe.

     Pipe installation begins at  the lowest trench elevation and  proceeds
upgrade.  When bell and spigot type pipes are used, the bell end  should always
be upgrade.  During installation, the water level in  the trench  should not
exceed 50 percent of the pipe diameter above the invert of the pipe.   Water
may be removed by allowing it to  flow through previously installed tubing
(Bureau of Reclamation, 1978).  Alternatively,  the trench floor  could  deliber-
ately be overexcavated and backfilled with a larger size stabilizing  gravel.
The envelope material can then be laid on top of the  stabilized  floor.

                                     5-70

-------
     To take advantage of the characteristics of  flexible  tubing,  equipment
capable of automatic pipe installation  should be  used.   Trenching  machines  can
be modified to include a hopper  for bedding/envelope material  with chutes  to
deliver the material; a rack for  a roll  of  tubing and/or filter  fabric  which
is designed and located to minimize stretching; and a conveyor for automatic
backfill (SCS, 1973).

     Rigid pipes cannot be installed  automatically and  long  lengths of  pipe
are either hand carried or lowered by crane into  the trench.

     When extending drainage systems  under  roadways, structures,  root zones,
or areas not requiring drainage,  unperforated pipe should  be  specified.


               b.  Placement of  Envelope and Filters


     Gravel envelopes are installed around  the  pipe drain  to  increase flow
into the drain and reduce the build up  of sediments in  the drain  line.   They
may be placed by hand, backhoe,  or by a  hopper  cart or  truck.   In  continuous
trencher drain installation machines, gravel filling may be ongoing along  with
other operations.

     Filter fabrics are sometimes installed around the  gravel  envelope  to
prevent fines from clogging the  envelope and drain pipe.   When constructing  a
drain using a fabric filter wrapping, the fabric  is installed  first,  followed
by the bedding, the pipe, and the envelope  in that order.  The fabric filter
is then wrapped around the top of the envelope  prior to backfilling with soil.
A schematic of an installed pipe drain with filter fabric  is  shown in Figure
5-17.  Fabric filters can be installed manually or by machine.


               c.  Backfilling
     After the gravel envelope has been  installed,  the  trench must  be  back-
filled to the original grade.  Prior  to  backfilling,  the drain  should  be
inspected for proper elevation below  ground  surface;  proper  grade and  align-
ment; broken pipe; and thickness of the  gravel envelope.  The inspector should
ensure that pipe drains and manholes  are free of deposits of mud, sand and
gravel, or other foreign matter, and  are in  good working condition.  Unstable
soils may preclude all but spot checks before backfilling.

     Almost any type of excavation equipment can be used to  backfill trenches
including backhoes, bulldozers, scrapers, and combination backhoe-front-end
loader.  During backfilling, care should be  taken to  ensure  that the drain  is
not disturbed either vertically or horizontally.  About 1 foot  of fill should
be carefully placed over the envelope before starting the general backfill
operation (Bureau of Reclamation, 1978).
                                     5-71

-------
     Geotextile fabric may be used on the top of the envelope to prevent
siltation of the envelope from the backfill materials.  In order to prevent
settling of the backfill after construction, periodic compaction of soil  lifts
is also required.   This may be accomplished using air tamping or a vibrating
or sheepsfoot compactor.


     5.2.5  Performance Monitoring


     After installation of the subsurface drain is complete, the drain should
be tested for obstructions.   For a small drainage system, this can be done
visually by shining a high powered flashlight through a drain from one manhole
and observing the beam in another.  TV camera inspections may be used for
large diameter drains.  Mechanical methods can be used both to remove obstruc-
tions or to test for obstructions.  Flexible polyurethane foam plugs are
available which expand to wipe or scrape the pipe when water or air pressure
is applied.  They are also available with a rope through the center so they
can be pulled through the drain pipe (Knapp, Inc., 1982).

     Manholes and silt traps should be checked frequently for the first year
or two of operation for sediment build up.  Less frequent inspection is
required as the system ages.

     Piezometers may be installed in the various parts of the drainage system
to identify operational problems with the filter, envelope, pipe, or other
components of the system.  Piezometers can measure the loss of head through a
medium, and, thus, can identify obstructions to flow, such as a clogged
envelope or filter.

     Monitoring wells can also be installed downgradient of the drainage  sys-
tem.  Detection of contaminants would indicate a malfunction or failure of the
system.

     Malfunction of subsurface drains can be attributed to chemical clogging,
clogging due to biological slimes, or a variety of physical mechanisms.
Problems caused by the above conditions are usually apparent at the surface
above the drain.  Inspection of the area will reveal soft or ponded surface
conditions, areas of subsidence, and areas of accelerated vegetative growth.

     Chemical clogging of pipes and envelope materials can occur by a number
of mechanisms.  Calcium carbonate precipitates and iron and manganese deposits
can build up around collector pipes or can cause cementation of the envelope
material.  Factors contributing to calcium carbonate precipitation include
bicarbonate alkalinity, calcium hardness, pH, and changes in pressure or
partial pressure of carbon dioxide.  Formation of iron and manganese deposits
depend upon redox potential, iron and manganese concentrations, total sul-
fides, presence of iron reducing bacteria, pH, and the presence of materials
which form soluble (e.g, Cl , CN ) or insoluble (phenols, hutnic acids) iron
complexes.  Presence of viscous wastes can also clog drain envelope materials.
                                     5-72

-------
     Physical mechanisms which result in drain malfunction  include  formation
of sinkholes or blowouts due to pipe breakage, root penetration, high pressure
within the drains, and hydraulic removal of fines (scouring).  Excessive
scouring can result from improper design of envelope material or from exces-
sive velocity.  A certain amount of scour is to be expected.  If manholes are
not cleaned out periodically, sediments can build up to the point of clogging
the drains.

     Clogged drain pipes can be corrected using high pressure water jetting
equipment, mechanical scrapers or brushes, or flexible foam plugs, as
described previously.  Flexible foam plugs are coated with  plastic material in
a spiral or criss-cross design which imparts added scouring power to the plug.
The plastic can be impregnated with silicon carbonate or steel bristles to
remove scale or deposits (Knapp, Inc., 1982).  In some cases, chemicals may be
needed to remove difficult deposits.

     Where there is a structural problem, such as drain breakage or improper
drain spacing causing a sinkhole, the drain must be dug up  and the condition
corrected.  Malfunctioning perforated pipe drains located near root systems
should be dug up and replaced with non-perforated pipe.


     5.2.6  Technology Selection/Evaluation


     Evaluation of the suitability of subsurface drains as  a remedial tech-
nology is generally made by comparing the cost-effectiveness of this alterna-
tive with pumping.  Relative to pumping, subsurface drains  can be difficult
and costly to install particularly where extensive hard rock excavation and
dewatering is required.  They are also time consuming to install and may not
be an appropriate alternative where immediate remediation is required.  Safety
of field workers is also more of a concern with subsurface drains because of
the need for extensive trench excavation.

     However, there are several advantages of drains relative to pumping.
They are generally more cost-effective than pumping in areas with low
hydraulic conductivity particularly where pumping would be required for an
extended period of time.  They are easier to operate since water is collected
by gravity flow.  They are also more reliable from the standpoint that there
are no electrical components which can fail.  However, when drains  fail due to
clogging, breaks in the pipes, or sinkhole formation, they can be costly and
time consuming to rehabilitate.


     5.2.7  Costs
     Costs for installation and .operation of subsurface drains can be divided
into four categories:  installation costs, materials costs, engineering
supervision, and operation and maintenance.
                                     5-73

-------
     Installation costs depend primarily on  the  depth  of  excavation,  stability
of soils, extent of rock  fragmentation required,  and groundwater  flow rates.
The principal materials costs include pipes, gravel, manholes,  and  pumps  and
other accessories for the drainage sump.  Materials and installation  unit
costs have been combined  and are summarized  in Tables  5-10  through  5-12.

     Engineering and supervision involves such activities as  staking  the  drain
line, checking for grade  control and alignment;  and checking  pipe specifica-
tion and pipe quality, etc.  For the installation of subsurface drains  in
conventional agricultural and water conservation applications,  engineering and
supervision costs are usually about 5 to 10  percent of the  total  (Schwab  et
al., 1981).  However, these costs can be expected to be substantially higher
for hazardous waste site  applications and will vary considerably  depending
upon the geologic and hydrogeologic conditions.

     Capital costs associated with installation  of  subsurface drains  are
typically much higher than those associated  with pumping  systems.   This is
particularly true where substantial rock excavation is required and deep
drains requiring extensive shoring are needed.   These  factors may result  in
exclusion of drains as a  cost-effective remedial action.  However,  operation
and maintenance costs associated with drains are generally  lower  than with
pumping, provided the system is properly designed and maintained.   Lower
operation and maintenance costs become significant  particularly where plume
removal or containment is needed over a long period of time.

     Total capital costs  for drainage systems, as with other  remedial
technologies, can vary widely depending upon site conditions.   Two  scenarios
are briefly described below to illustrate how widely capital  costs  may range.

     At one particular hazardous waste site  (Site A) a 261  foot long
interceptor drain was installed to a depth of 12 to 17 feet.   The leachate
discharged into a 4 foot-wide, 20 foot deep  sump which pumped the leachate at
a rate of 18 to 20 gpm to a treatment system (USEPA, 1984)  (USEPA,  1985).

     Construction of the  drainage system involved excavation  to a 4 to 6  foot
wide trench which was supported with steel sheet piling during construction.
The trench was lined with filter fabric, 6 inches of gravel and a 12  inch
perforated concrete asbestos drain pipe.  Additional filter fabric  supported
by screening was then wrapped around the pipe prior to backfilling.   The  total
cost of the drainage system was $269,721 or  $65  to  86/square  foot,  (USEPA,
1984) (USEPA, 1985).

     Table 5-13 shows how the total capital  costs were distributed.

     A second case history involved installation of a  shallow (3  foot deep)
interceptor trench at the A.W. Mauthe site in Appleton, Wisconsin (USEPA
1984).

     The drainage system  was approximately 750 feet long  and  consisted of
4 inch PVC pH drainage pipe which was laid in a  gravel filled trench.  Four
foot diameter concrete sumps were installed  at two  collection points  and  the
sumps were connected by about 25 feet of PVC pipe so that water collected in

                                     5-74

-------



w
w
H
H
M
^
M
e>
<
Q
g
5
ft*
C/3

^3
pft f5
•3 ^
H W
8
g
M
PN
FH

^j
ฃ


H
O
a
ง

00
*-l






































































Ol
u
3
O
4J
CO
O
O

4J
C
0











0]
C
o
•H
4J

0
CO
2
**ซ


















8

M








i— 1 i— <


co cfl
*O *d
^^ ป-^,
in o
CO in

•CO- -CO-










OI
-o
•H
01
T3 C
•H in
a i
\o
c rH
•rt
1 -
Ol
* 01
O.T3
Ol
Ol 4_l
T) M-l

4J 00
K-4
iri ^-i
Ol
- to

O T)
4-1 (0
CO r-l
CO
U 1-i
X 01
M f
U
X C
U 0)
C l-i
ซ H
H

















e
CO
0
1-1
•0
e
CO
w

a
B
co
t3
jc"
u
4)

4ป)

(U
•H


<*-!
*



•H
i-H
CO
•o

JS.
X
w
o
pC
A!
U
CO
ซ



CM CM CM CM

CO CO CO CO
•O TJ T3 T3
*^ป ^^ *^ ~^
O i-l ON O
CM 1-1 vO -*
CM CM 1-1 r-l
•co- co- to- co-


co co co
*O "O t3
co r*i pt^ pt^
•0 nJ iJ iJ
^< ^5 to \O
nJ CT* i— 1 CO
i— 1 i— I
o •-
oi a. o.
• x 01 0> Ol
O, tJ Ol Ol
Ol *^ *O
Ol 4->
*O ^4~l 1 * 4>J
UH UH
4J -*
M-l <-l CO O
i— 1 CM
CM ซ
^ U X X
>-, U -H -H
4J CO U U
•H O. CO co
o co a a
CO U CO CO
a. u u
cซo
U 'U'"l CO
>,T3 T3
CO ^ป ^

XCM m m
r-l i— 1 CM CO



















r-l r-l

CO CO
•O t3
^_ **^.
O CO
O ON
CO r-l
co- co-










f. l-i

•no

^
\f\
co in
\o
ซ<
ฃ x
U -H
CO U
a co
CO CX
U CO
u
fO
>, -o
>,

t-~ ui
* -1









at
C
•H
r-l
60
CO
M
O



r-< r-l

CO CO
•a 13
>, >,
^^ **^
CO CO
OO CM
-* CO
co- co-










l-i l-i
^^
CO CO
^J ^J
^ป ^\

o m
CM CO
x X
•H -H
U U
CO CO
a a
CO CO
u u
CO CO
•o -d
^ป ^\

m o
0 rH








^
iH
Ol
Jฃ
CO
ง
iH
U

                                            •o
                                            0>
                                            C
                                            o
                                            u
                                   co r^
                                   CO- 
                                                     01
                                                     o>
                                                     CO
                                                     01


                                                    •H
                                                    iH


                                                     H
5-75

-------
•O
CD
4-1
a
o
O
cu
U
>J
o


4J
in
o
o

4J
•H
C
o











CO
e
0
•H
4J
a
3
CO
CO
 4-1 4-1
IH IH IH
*•••• **^ "^
m o O
r-l CO t~ป
• • •
r— oo r*.










CM CM CM
.. 4-1 4.1 4J
cu MH IH IH
60-^ --^ — .
CO ฃ1 A 43
> r-l r-l r-l
r~4
CO CM 00 OO
tO CM CO CO

•rj . . .
c e c c
to o o o
i-l 4-1 4J 4J
i—4 m to to
s > > >
&* tO tO (tt
U O U
CO X X X
01 01 CU 01
•w
3 4-1 4J 4-1
r-l IH IH IH
O
e m in o
T( rH CM -ป
C
O
•H
] t
CO 60
N <*N C
*H *^ -*H
rH CU rH
1-13 1-1
ja c a
CO 1H
4J 4J 4J
CO C 01
O 01
rH ^tj ฃ.




rH i— 4


CM CM
4-1 4-1

•*s^ -^
O in
oo r-
• ซ
in V4O


CO
j_i
cu
U

a
CO

•e
c
CO

M
CO
cu
U
to ••
l-i 01
ฃ> 60
co c e
• > 0 0
01 tO 4J 4->
r-l CO CO CO
CO > >
3 *"O (d CO
C U U
M to x x
01 01 01
3 r-l 4-1 4J
r-l 3 IH IH
0 a
C -3- O
•H rH CM


60
c
•H
^4
O

CO
c
cu

o
0




-H rH rH CO
co co co co
MH  0) 0)
4-1 CO O CU OI 01 01
* C rH
O to CM in in r~
CO N > CM CO -ป in
CU iH O
rH H B O O O O
•H O 01 4-1 4-> 4-1 4-1
ax b
1 in co \o co
V rH CM CO in








60
CO B
0) iH
rH IJ
•H 0)
a 4J
1 CO
V 9



rH rH rH rH


4-1
 01 V
oo a a a a
•P^ tr^ ff^ *r^
T3 a a. a a.
B
CO T3 *O *O "O
01 01 CU 01
C 4-1 4-1 4J 4-1
O CO to to CO
•H 60 60 60 60
4J3333
CO H I-l h I-l
CO O O O O
o o o o o
X
iH iH iH -H
CO 1 1 1 1
cu CM m oo -*
•O rH rH rH CM
rH X J= J= J=
O 4-1 4J 4J 4-1
C iH iH iH -H
•H 9 9 9 9







OI
rH
S

a
e
3
w
                                                                                    T)
                                                                                    CU
                                                                                    3
                                                                                    B
                                      5-76

-------




















x-\

fll
2
a
•H

O
CJ
\.^s



o

•
1
to
3
9
^2
™

























OJ
o

rj
0
CO




^J
CO
o
U
4_t
•H
B










0)
B
O
•H
4J
O.

ง
CO
CO

















e
CU
4J
M



























B
O
•H
CJ
3
CO

M-l
O
4-1
01
•O CU
0) M-l
•a
B O
O CM

4-1 CO
CO 01
•a
CO i-l
rJ CJ
x: B
•H
00

60 01
B >->
•H X:
B oo
Cb



60
B
•H
o.
4-*~v B
T3 3
CD CX
60 3
C C 00
•H -H C
V-( 4J -H
0) C C
-U O OJ

(U
o



^N ,*"•* X~\ ^S
^H t— 1 f-4 i— 4
s-*' '*-' ^-^ N-*





>, l>, >ป tS
cfl tfl cO flj
•O -O T3 TJ
LO O ^O O
to o^ in co
CO CO CO *^


01
CO
o
rE
CU
00

CO
CJ
CO
•H
T>

M-l
o a ex

4J a. o. 3 3
cu B B & o.
^
c a. a 4-1 4-1
cd co co B B
•H -H CU CU
CU 73 -O CJ CJ
CO
0 B B B B
.C i-l -H fH ปH
1 1 1 1
CM -* CO \O






















^~\ /"N /^s
i-l i-l r-l
^-^ V-X N^




j: x j=
CJ CJ CJ
CO co CO
CU 01 01
o m o
O CM CO
CM co  O^

•> n n *
OJ O. CX CL
N .C _C .C
B
O -* CM CM
l-i^ — -^ ^-
PO r-l r-l r-l
CO
60
3
•H
l_t
B
cu
o

CU CX
rH S
•C 3
*H CX

l-l CX
oi B
XI CO
3
CO



y-N ^*v ^*N
rH i-l rH
*^x ^-^ \— '




r* r; fl
O O O
03 tO CO
01 W 11
•^ in o
ON O CM
r-l CM






,.
B
0
•H
CO
r-l -O -O TJ
r-l CO CO CO
CO CU 01 01
4J JB f X
co
C 4J 4J 4-1
C
0

•H a a a
J3 X X
4-1
OJ -tf CO CM
CJ rH r-l r-l






















^*s ^*s ^^ /™v
r-l r-l r-l r-l
s-' ^-^ ^^ ^-^



CJ
X! X! *B CO
CJ 0 O CU
CO m co
oi 01 cu m
m O 0 r-l
O O in •*
CO *a* ^^ r— 1
 to-
oi
00
** Vj
r-l CO
O X
r-l CJ
4-1 V>
6 -H
o •ซ
CJ
B
iH -H
cu i
> CM
CU
r-| .ts
B

C< *H
CO JJ T3 T3

l-l rH CO CO CU OJ
cu r-i o> cu f. x;
j-i co xi x:
l-l 4-1 4-1 4J
CO CO 4J 4-1 M-l MH
U B M-l M-l
0) t-i O O
O O CM CM
B JJ CM CM
OS • •>
Va o •* ** G G
•H x! E e a a
4J CX CX 60 60
4-1 i-l 60 60
co 9 O O
CO O O CM VO
O I—I \C r-l r-4




CX
e
3
a

o
oo
CO
V4

CX
CO
•H
0


^

01
3
6
•H
( 1
B
o
CJ
























































5-77

-------
                   01
                   y


                   o
                   CO
                   CO
                   o
                  o
                                                    o
                                                    sf
•H
4-1
a
o
o
 I

a

H
                                      CO
                                      O
                                      O
                   10

                   o
                   CO
                   CO
                              CO
                              o
                              u
                              c
                              o
                              •H
                              4-1
                              U
                              01
                              co

                              0>
                              01
                              CO
                              60
                              01
                                      60
                                      C
                                      cu
                                      01

                                     CO

                                      01
                                      01
                                     CO
                                     CO
                                     <4-l
                                     14-1
                                     o
                                     4-1
                                     3
                                     o
                   CU
                   4J
                                      01      O
                              4J     4-1      M
                              C      Cd      4-1
                              •H      ป      C
                              O     T3      O
                              a      c     u

                              tH      O      0)
                              41      V4     -O
                              ป     O      cd


                                            O
                                                    O
                                                    CJ
                                                     01
                                                     CO
                                                     cd
                                                     e
                                                     o
                                                                cd   .o    cd

                                                               GO   oo   GO
 x   >,   C
 o>    01    o
 !-.    P   .C
MH    4-1    C[J
•o    -o   as

o    o   g
                                                                   es
                        5-78

-------
                                  TABLE 5-11
                     1985 UNIT COSTS FOR PIPE INSTALLATION
            Item
   Assumptions
Filter and Envelope

  Filter fabric


  Gravel envelope




Backfill

  Dozer backfill, no
    compaction

  Dozer backfill, air
    tamped
   Unit Cost
Polypropylene,
  laid in trench

Crushed bank run,
  screened
  0.75-0.50-in; in
  trench
Up to 300 foot haul,
  900 yd /day

Up to 300 foot haul,
  235 yd /day
$5.45/yd'
    Source
Drain Pipe
PVC perforated
underdrain





Corrugated steel or
aluminum, perforated,
asphalt coated
Porous wall concrete
underdrain, extra
strength
Vitrified clay, extra
heavy duty strength,
premium joints


10 foot length,
S.D.R. 35:
4 inch
6 inch
8 inch
10 inch
12 inch
6 inch, 18 ga
8 inch, 16 ga
10 inch, 16 ga
6 inch
8 inch
10 inch
4 inch
5 inch
6 inch
8 inch



$2,162/ft
$3.64/ft
$4.56/ft
$6.80/ft
$8.40/ft
$4.63/ft
$6.20/ft
$8.00/ft
$4.14/ft
$5.80/ft
$8.75/ft
$4.46/ft
$5.35/ft
$6.35/ft
$8.50/ft



(2)
(2)
(2)
(2)
(2)
(1)
(1)
(1)
(1)
(1)
(1)
(2)
(2)
(2)
(2)
$1.14-1.49/yd      (2)
$9.20-10.55/yd     (1)
     (1)


     (1)

(continued)
                                     5-79

-------
                           TABLE 5-11.  (continued)
            Item                Assumptions             Unit Cost      Source
Backfill
  (continued)

   impacted bt
    vibrating roller           700 yd~7day

   >mpacted backfill,        6 to 12 inch 1
    sheepsfoot roller          650 yd /day
                                                              o
Compacted backfill,        6 to 12 ^nch lifts,        $1.54/yd        (1)


                                                              o
Compacted backfill,        6 to 12 inch lifts,        $1.67/yd        (1)
Sources:  (1) Godfrey, 1984a; (2) Godfrey, 1984b.
                                      5-80

-------
                                  TABLE 5-12
                       1985 INSTALLED COSTS FOR MANHOLES
          Item
                    Cost
     Concrete slab,  cast in place,
       8" thick
     Pre-cast concrete riser pipe,
       4 ft inside diameter
       6 ft inside diameter
     Slab tops,  precast,  8-in thick
6-ft deep
8-ft deep
12-ft deep
16-ft deep
20-ft deep
6-ft deep
8-ft deep
12-ft deep
16-ft deep
20-ft deep

6-ft deep
8-ft deep
12-ft deep
16-ft deep
20-ft deep

4-ft diameter
5-ft diameter
6-ft diameter
$890
$1,275
$1,915
$2,555
$3,195
$570
$775
$1,175
$1,575
$1,975

$1,250
$1,675
$2,535
$3,395
$4,255

$175
$195
$270
     Frames and covers,
       watertight
24-in diameter     $345
32-in diameter     $430
Source:   Godfrey,  1984a
                                     5-81

-------
TABLE 5-13.  CAPITAL COSTS ($1985) FOR INTERCEPTOR DRAIN  INSTALLATION  -  SITE  A
Materials

•  550 feet of 12 inch perforated asbestos                       $3,806
   cement drainage pipe, (only about 261  feet
   were actually used)

•  147 feet of 2 inch carbon steel pipe                           1,549
   for carrying leachate to treatment system

•  2 submersible pumps and accessories                            1,041
           2
•  2,700 ft  vinyl-coated wire screen                               702

•  338 yd2 filter fabric                                            277

•  Other materials costs not given                                4,342
                                           Subtotal              11,717

Labor/Equipment

Labor, equipment rental  including                              $257,342
excavation equipment and sheet piling
and gravel fill

Company in-house labor                                              651

                                           TOTAL                269,721


Source:  Adapted from USEPA,  1984


one sump could be pumped to  the  other.   The  total  capital  cost for the  drain-
age system was about $15,400  (updated  to 1985  costs  using  ENR Construction
Cost Indeces for 1982 and  1985).  However, this cost estimate also includes
cost for a 300 foot long surface water diversion drainpipe.   Therefore,  the
unit cost for the subsurface  drain was less  than $6.86/ft   (USEPA, 1984).

     These two case histories  show an  order  of magnitude difference in  the
unit cost for subsurface drainage systems.   Probably the most significant
factor contributing to  these  cost differences  is the depth of the  drain.   In
the case of Site A the  trench  was excavated  to a depth  of  12  to 17 feet  and
shoring was required to  support  the  trench wall.   In the case of the Mauthe
site the subsurface drainage  system  was  only 3 feet  deep and  trench excavation
was greatly simplified.


                                     5-82

-------
5.3  Subsurface Barriers
     The term subsurface barriers refers  to  a variety  of methods  whereby low
permeability cut-off walls or diversions  are installed below  ground  to  con-
tain, capture, or redirect groundwater  flow  in  the vicinity of  a  site.   The
most commonly used subsurface barriers  are slurry walls, particularly soil-
bentonite slurry walls.  Less common are  cement-bentonite  or  concrete (dia-
phragm) slurry walls, grouted barriers, and  sheet piling cut-offs.   Grouting
may also be used to create horizontal barriers  for sealing the  bottom of
contaminating sites.  These types of subsurface barriers are  discussed  in the
following sections.
     5.3.1  Slurry Walls


     Slurry walls are the most common  subsurface barriers  because  they  are  a
relatively inexpensive means of vastly reducing groundwater  flow  in  uncon-
solidated earth materials.  The term slurry wall can  be  applied to a variety
of barriers all having one thing  in common:   they  are all  constructed in  a
vertical trench that is excavated under  a  slurry.   This  slurry, usually a
mixture of bentonite and water, acts essentially like a  drilling  fluid.   It
hydraulically shores the trench to prevent collapse,  and,  at  the  same time,
forms a filter cake on the trench walls  to prevent  high  fluid  losses into the
surrounding ground.  Slurry wall  types are differentiated  by  the materials
used to backill the slurry trench.  Most commonly,  an engineered  soil mixture
is blended with the bentonite slurry and placed in  the trench  to  form a soil-
bentonite (SB) slurry wall.  In some cases, the trench is  excavated  under a
slurry of portland cement, bentonite,  and water, and  this  mixture  is left in
the trench to harden into a cement-bentonite  (CB)  slurry wall.  In the  rare
case where great strength is required  of a subsurface barrier, pre-cast or
cast-in- place concrete panels are constructed in  the trench  to form a
diaphragm wall.  These types of slurry walls,  including  hybrids of the  three,
are discussed below.
          5.3.1.1  Soil-Bentonite  Slurry Walls


     Soil-bentonite slurry walls are backfilled with  soil materials mixed  with
a bentonite and water slurry.  Of  the  three major  types  of  slurry  walls,  soil-
bentonite walls offer the lowest installation costs,  the widest  range  of
chemical compatibilities, and the  lowest permeabilities.  At  the same  time,
soil-bentonite walls have the highest  compressibility  (least  strength),
require a large work area, and, because the slurry and backfill  can  flow,  are
applicable only to sites that can  be graded to nearly  level  (Spooner et al.,
1984a).  The following sections present details on applicability,  design,
construction, monitoring, evaluation,  and costs for soil-bentonite slurry
walls.
                                     5-83

-------
               a.  Applications and Limitations


     One of the first steps in considering a soil-bentonite slurry wall  for  a
given site is to review the configuration options available and determine
which best meets the goals of the remedial action.  In  the vertical perspec-
tive, slurry walls may be "keyed-in" or hanging, as shown in Figure 5-29.
Keyed-in slurry walls are constructed in a trench that  has been excavated  into
a low permeability confining layer such as a clay deposit or competent bed-
rock.  This layer will form the bottom of the contained site,  and a good key-
in is essential to adequate containment.  Hanging slurry walls, however, are
not tied to a confining layer but extend down several feet into the water
table to act as a barrier to floating contaminants (such as oils and  fuels)  or
migrating gases.  The use of hanging slurry walls in waste site remediation  is
relatively rare, and most installations are of  the keyed-in variety.

     In the horizontal perspective, slurry walls can be placed  (relative to
the direction of groundwater flow) upgradient,  downgradient, or completely
surrounding the waste site.  The various horizontal placement  options  are
shown in Figure 5-29.

     Circumferential installations are by far the most  common  and offer
several advantages.  This placement vastly reduces the  amount  of uncontami-
nated groundwater entering the site from upgradient, thus reducing the volume
of leachate generated.  Also, provided there are no compatibility problems
between the site wastes and the wall materials  (discussed later), the  amount
of leachate leaving the downgradient side of the site will be  greatly  reduced.
Moreover, when  this configuration is used in conjunction with  an infiltration
barrier and a leachate collection system (or other means of reducing  the
hydraulic head  on the interior of the wall), the hydraulic gradient can  be
maintained in an inward direction, thus preventing leachate escape.

     Upgradient placement of a slurry wall refers to one installed on  the
groundwater source side of the wastes.  Although no documented  cases  of
upgradient installatons were found, this placement could be used to divert
clean groundwater around a site in high gradient situations.   This method  will
not halt the generation of leachate but could slow its  generation by
stagnating groundwater behind the wall.

     Downgradient placement refers to installation of a slurry wall on the
side of a waste site toward which groundwater is flowing.  Although not
common, this placement can be employed  as a hanging wall to contain and
capture floating contaminants and methane.  Because there is direct leachate/
wall contact with this configuration, extensive compatibility  testing is
essential.

     Another major concern in the application of soil-bentonite walls to site
remediation is  the compatibility of the backfill mixture with  site con-
taminants.  Evidence indicates that soil-bentonite backfills are not  able  to
withstand attack by  strong acids and bases, strong salt solutions, and some
organic chemicals  (D'Appolonia,  1980b) .  The  issue of chemical incompatibility
is discussed further under "Design Considerations."

                                     5-84

-------
                                            FIGURE 5-29.
                     EXAMPLES OF SLURRY WALL PLACEMENT OPTIONS
                 Keyed-ln Slurry Wall
                                                                       Hanging Slurry Walt
                              Cut-away Cross-section of Circumferential Wall Placement
Cut-away Cross-section of Downgradient Placement
   Cut-away Cross-section of
Upgradient Placement with Drain
 Source: Spooner et al., 1984a
                                                5-85

-------
     A number of factors can limit the application of soil-bentonite to a
particular site.  Most limitations can be overcome by increased engineering,
but the associated cost increase may make some other alternative, such as
groundwater pumping, a more suitable remedial measure.

     One factor that can limit the use of a soil-bentonite wall is  the site
topography.  Because both the excavation slurry and the backfill will flow
under stress, the trench line must be within a few degrees of  level.  In most
cases, it is possible to grade the trench line level prior to  construction,
but this is an added expense.

     Cement-bentonite slurry walls are an alternative for steeply sloping
sites and are discussed in Section 5.3.1.2.

     If a keyed-in slurry wall is considered, the depth to,  and nature of,  the
confining layer becomes a concern.  The layer must be of sufficiently low
permeability to significantly retard downward migration at the design head
levels.  It must also have sufficient thickness to allow for excavation of  an
adequate key-in (2 to 3 feet).  The depth to the confining layer will also
determine the type of excavation equipment used and the completed wall costs.
Most slurry wall contractors have available modified hydraulic backhoes
capable of excavation to depths of seventy feet or more.  Below this level,
more expensive specality equipment such as clamshell grabs are required, and
costs increase dramatically.

     Another limiting factor is the amount of work area required for soil-
bentonite backfill mixing.  Ideally, there will be sufficient  work  area beside
the trench to mix and place the backfill.  If such room is available, a
central backfill mixing area can be established, and the backfill hauled to
the active trench portion.

     Another limiting factor in the use of soil-bentonite slurry walls for
pollution migration control is the lack of long-term performance data.  Soil-
bentonite walls have been used for decades for groundwater control  in conjunc-
tion with large dam projects and there is ample evidence of  their success in
this application.  However, the ability of these walls to withstand long-term
permeation by many contaminants is in question.  Most contaminant/  backfill
compatibility questions have been answered by laboratory permeation tests and
not by long-term field studies.  The issue of containment/backfill  compati-
bility is discussed further under "Design Considerations."


               b.  Design Considerations
     A host of factors must be considered  in  the  design  of  a  slurry  wall.   The
design must be based on a detailed, design-phase  investigation  characterizing
subsurface conditions and materials as well as waste  disposition  and nature.
The issue of waste/wall compatibility should  be addressed early in  the  design
by permeability testing of the proposed backfill  mixture with actual site
leachate or groundwater.  The design-phase investigation results  can then  be


                                     5-86

-------
used to decide on the optimum configuration and  to  select  any  ancillary
measures needed to enhance the performance of  the wall.  These considerations
are discussed further below.  These and other  design considerations  are
covered in great detail in Slurry Trench Construction  for  Pollution  Migration
Control (Spooner et al., 1984a).

     For most slurry walls installed  to control  comtaminated groundwater,  the
most important design consideration will be the  permeability of  the  completed
wall.  The soil-bentonite wall's permeability  is dependent on  the  backfill
mixture.  The lowest permeability is  obtainable  from backfills having  20  to
40 percent fine soil material (passing a number  200 sieve)  and preferably
plastic fines (D'Appolonia, 1980b).   Although  plastic  fines are  essential  to
achieving low permeability, there is  evidence  to show  that long-term wall
performance in a contaminated environment will be more certain if  the  backfill
is composed of clays with a low activity index (defined  as the plasticity
index divided by the percent by weight finer than two microns) (Alcar,
Oliveri, and Field, 1984).

     If a backfill mixture contains clays with a high  activity index,  the
initial low permeability of the wall  could more  easily be  increased  by
physico-chemical reactions brought about by contaminants.   This  sort of
problem can be avoided by proper backfill selection and  testing.

     A number of chemical compounds can have a detrimental effect  on soil-
bentonite slurry walls.  Table 5-14 shows how  some  chemicals can effect
backfill permeability.  More recent information  indicates  that organic  fluids
can cause dessication and cracking in soil-bentonite backfill  mixtures, and
result in permeability increases of several orders  of magnitude.   However,
these same data indicate that these organics,  at or near their solubility
limits in aqueous solution, caused no appreciable increases in permeability
(Evans, Fang, and Kugelman, 1985).  Nonetheless, landfill  and  lagoon leachates
are often complex mixtures of chemicals and no pollution control slurry wall
should be installed without thorough  compatibility  testing.

     After it is determined that a backfill mixture compatible with  site
wastes can be designed, an assessment can be made on wall  configuration.   In
most pollution migration control applications, the wall  will be  keyed  into a
low permeability confining layer beneath the site,  and completely  surround the
site.  Only in special applications are hanging  walls  and  partial  walls used.

     The design of a slurry wall for  source control at a site  must always
consider how the wall fits into the overall remedial response.  Rarely, if
ever, are slurry walls (or other subsurface barriers)  the  only action  taken in
site remediation.  At a minimum, surface infiltration barriers (caps)  are
installed to prevent filling of the site interior and overtopping  of the wall.
In some installations, extraction wells or drains are used to  maintain  lower
groundwater levels inside the wall than outside.  This prevents  the  site  from
filling and possibly floating the cover material off, and  also keeps ground-
water flowing towards the interior, thus permeating the  wall with  groundwater
rather than leachate.  Although such  an installation would be  more expensive
and would require a leachate treatment system, long-term performance of the
wall would be greatly enhanced.

                                      5-87

-------
                                    TABLE 5-14
                     SOIL BENTONITE PERMEABILTIY INCREASES
                   DUE TO LEACHING WITH VARIOUS POLLUTANTS
          Pollutant                                      Backfill
          Ca+  or Mg"*"*" @ 1,000 ppra                          N
          Ca++ or Mg"*"*" @ 10,000 ppm                         M
          NH NO  @ 10,000 ppm                               M
          Acid (PH>1)                                       N
          Strong acid (pHll)                               M/H*
          HC1 (1%)                                          N
          H2S04 (1%)                                        N
          HC1 (5%)                                          M/H*
          NaOH (1%)                                         M
          CaOH (1%)                                         M
          NaOH (5%)                                         M/H*
          Benzene                                           N
          Phenol solution                                   N
          Sea water                                         N/M
          Brine (SG=1.2)                                    M
          Acid mine drainage (FeSO, ,  pH~3)                 N
          Lignin (in Ca   solution)                         N
          Organic residues  from pesticide
            manufacture                                     N
          Alcohol                                           M/H
N - No significant effect;  permeability increase by about a  factor  of  2  or
    less at steady state.
M - Moderate effect;  permeability increase by factor of 2 to  5  at  steady
    state.
H - Permeability  increase by  factor of 5 to 10.
* - Significant dissolution likely.
+ - Silty or clayey  sand, 30  to  40% fines.
Sources: D'Appolonia, 1980s; D'Appolonia and Ryan, 1979

                                       5-88

-------
                   Construction Considerations
     Construction of a soil-bentonite slurry wall  is  relatively  straight-
forward. The equipment used is dependent on the depth  and  length of  the  wall.
For walls up to 80 feet deep, a backhoe or modified backhoe  is used  for
excavation.  Deeper installations require the use  of  a mechanical  or hydraulic
clamshell or, in rare cases, a dragline.  Small volume wall  installations  may
allow the use of batch slurry and backfill mixing  systems, while large jobs
would require flash slurry mixers and a large backfill mixing area.   Figure
5-30 illustrates a typical slurry wall construction site.

     Regardless of the equipment used, the slurry  is  introduced  just after the
trench is opened and before the water table is reached.  The primary function
of the slurry is to act as hydraulic shoring to prevent  trench collapse.
There is also evidence to indicate that the filter cake  formed on  the trench
walls by the slurry, contributes to the low permeability of  the  completed
wall.

     After a sufficient length of wall is excavated to the design  depth, back-
filling can begin.  This is usually begun by using a  clamshell to  lower  mixed
backfill to the trench bottom until the sloped backfill  extends  to the sur-
face.  Thereafter, the backfill can be pushed into the trench with a bulldozer
or poured from trucks using a trough, and allowed  to  flow  (not fall) down  the
sloped backfill.  This procedure, with backfill mixing alongside the trench,
is shown in Figure 5-31.

     Proper quality control during wall installation  is  essential.  The  most
important factors are checks of trench continuity  and  backfill mixing and
placement.  For backhoe-excavated trenches, the continuity of the  trench is
relatively easy to verify.  Inspection of the excavated  material indicates
when and where the confining layer is encountered, and observation of the
motion of the backhoe arm confirms lateral continuity.   With clamshell
excavators, confirmation of lateral continuity may be  more complicated.

     Backfill mixing and placement are carefully controlled during construc-
tion.  The soil which makes up the majority of the backfill  is placed in the
mixing area (either a central area or alongside the trench)  and  slurry is
added.  The mixture is bladed and tracked by a bulldozer until it  is of
relatively uniform consistency and of the proper density.  The backfill  must
be fluid enough to flow freely into the trench, but not  so fluid that it:
(1) fails to easily displace the slurry; (2) forms a  slope so gentle that  it
extends into the active excavation area; or (3) a  great  length of  trench must
be kept open.

     For circumferential installation, a portion of the  backfill is
re-excavated when the circle is complete.  The wall is then  allowed  to con-
solidate for up to several weeks.  Dessication and consolidation cracks  often
form in the top few feet during this time.  These  are  often  excavated and  a
compacted earth cap placed along the wall to prevent  further dessication or
cracking.  Where vehicular traffic must cross a wall,  traffic caps of
                                     5-89

-------
                                           FIGURE 5-30.
                        TYPICAL SLURRY WALL CONSTRUCTION SITE
                                            Bentonite
                                             Storage
                              Backfill Mixing
                                  Area
                                     Trench
                                     Spoils
                                                                     Backhoe
                                         77/777///777/>
                         Backfilled
                          Trench
                           Backfill
                         Placement
                           Area
Area of Active
  Excavation
Proposed Line
of Excavation
                                                                        \
                                                                     Slurry
                                                                    Storage
                                                                     Pond
                                                                           Slurry
                                                                           Pumps
                                                          Slurry
                                                        Preparation
                                                        Equipment
                                           Bentonite
                                            Storage
                                                                         ooo
                                                             Water Tanks
Access
 Road
Source: Spooner et al., 1984a
                                                5-90

-------
                                   FIGURE
              CROSS-SECTION OF SLURRY TRENCH
                          AND BACKFILLING
5-31.
     SHOWING EXCAVATION
 OPERATIONS
               "A- Emplacad />:
                   Backfill

              Source: Spooner et al., 1984a

aggregate  and/or  geotextiles  are often constructed.
traffic caps  are  tied  into  the site surface cap.
             Dessication caps and
               d.  Operation,  Maintenance,  and Monitoring
     As passive measures,  slurry walls require no operation and little main-
tenance.  Maintenance of  the  dessication cap atop the wall is the only
requirement  that  is  specific  to  the wall itself.  Maintenance of ancillary
measures such as  caps and  leachate  collection systems is important to the wall
as part of the entire remedy.  Monitoring of slurry walls usually involves
monitoring groundwater  levels  inside and outside the wall to ensure that
design head  levels are  not exceeded.  Groundwater quality monitoring can be
used to determine the effectiveness of the entire remedial effort.
                                      5-91

-------
               e.  Technology Selection/Evaluaton
     Soil-bentonite slurry walls are a relatively inexpensive and effective
means of controlling groundwater flow.  They have been in use for decades
controlling seepage through, under, and around large dams.   In uncontaminated
environments, they have been shown to have  long-term effectiveness  and  require
little or no maintenance.  Although they are installed by specialty con-
tractors, they are relatively easy to construct and are effective in con-
trolling groundwater immediately, provided  head differentials across the wall
are within design tolerances.  In contaminated environments, however, their
effectiveness over the long-term is very dependent on the types of  contami-
nants and their concentrations.  Consequently, design of such installations
should always consider methods and measures of minimizing direct contact of
high strength leachates with the wall.  The integrity of any slurry wall
placed directly through wastes or kept in constant contact with high strength
leachates must be questioned, and where questioned, verified by monitoring.

     The major safety concerns for slurry wall installations arise  from the
excavation of contaminated materials.  These can cause disposal problems,
increase air emissions from the site, and greatly slow the pace of  construc-
tion by requiring increased levels of worker protection (i.e., supplied air).
This is another reason that excavations through deposited wastes should be
avoided whenever possible.
               f.  Costs
     Costs  for  slurry walls  and other  subsurface  barriers  are  usually
expressed in costs per unit  area of wall  (dollars per  square  foot).   Thus,
total  costs are determined by  the depth and  the  length.  Width is  determined
by  the  excavation equipment  being used.   Table  5-15  shows  average  costs  for
soil-bentonite  and cement-bentonite slurry walls, and  illustrates  the effects
of  both the depth and ease of  excavation  on  costs.   Operation  and
maintenance costs are negligible.  These  costs  have  been updated using
Engineering News Record  cost indices  for  1979 and 1984.


          5.3.1.2  Cement-Bentonite Slurry Walls


     Cement-bentonite slurry walls share  many characteristics  with soil-
bentonite slurry walls,  but  are also  different  in some respects.   The
principal difference between the two  is the  backfill,  and  this produces
differences in  applications, compatibilities, and costs.   To  avoid duplication
of  previous sections, this discussion will highlight the  factors  that
distinguish cement-bentonite walls from soil-bentonite walls.

     Cement-bentonite walls  are generally excavated  using  a slurry of Portland
cement, bentonite, and water.  This slurry  is  left in  the  trench  and allowed
to  set up to  form the completed barrier.  For extremely deep  installations, a

                                      5-92

-------
                                  TABLE 5-15
             RELATION OF SLURRY CUT-OFF WALL COSTS  PER  SQUARE  FOOT
                       AS A FUNCTION OF MEDIUM AND  DEPTH


Slurry Trench
Prices
in 1984 Dollars



Medium
Soft to Medium Soil
N _< 40
Hard Soil
N 40 - 200
Occasional Boulders
Soft to Medium Rock,
Sandstone, Shale,
N > 200
Boulder Strata
Hard Rock
Granite, Gneiss,
Schist*
Soil-Bentonite
($/ftZ)
Depth Depth
< 30 30-75
Feet Feet

3-6 6-11

6-10 7-14
6-11 7-11


9-17 14-28
21-35 21-35


_>__ ___
Backfill
Depth
75-120
Feet

11-14

14-28
11-35


28-69
69-111


___.
Unreinforced Slurry Wall
Prices
in 1984
Cement-Ben tonite
($/fO
Depth
< 60
Feet

21-28

35-42
28-42


69-83
42-55


132-194
Depth
60-150
Feet

28-42

42-55
42-55


83-118
85-132


194-243
Dollars
Backfill
Depth
> 150
Feet

42-104

55-132
55-118


118-243
132-292


243-326

Notes:
N is standard penetration value in number of blows of  the hammer  per  foot, of
      penetration (ASTM D1586-67)

*Nprmal Penetration Only:
      For standard reinforcement add $ll/ft .
      For construction in urban environment add 25% to 50% of price.
      Does not include cost of working in a contaminated environment.
Updated from:  Ressi di Cervia, 1980
                                     5-93

-------
normal bentonite slurry is used for excavation, then replaced by cement-
bentonite.
               a.  Applications and Limitations


     Cetnent-bentonite walls offer the same configuration options as soil-
bentonite walls.  They are more versatile than soil-bentonite walls in  two
ways.  First, because the slurry sets up into a semi-rigid solid, this  type of
wall can accommodate variations in topography by allowing one section to set
while continuing the next section at a higher or lower elevation.  Second,
because the excavation slurry is commonly the backfill too, this type of wall
is better suited to restricted areas where there is no room to mix soil-
bentonite backfill.  Also, cement-bentonite is stronger than soil-bentonite
and so is used where the wall must have less elasticity, such as adjacent to
buildings or roads.

     Cement-bentonite slurry walls are limited in their use by their higher
costs, somewhat higher permeability, and their narrower range of chemical
compatibilities.  As Table 5-16 illustrates, cement-bentonite walls average
over 30 percent higher in cost than soil-bentonite,walls.  The permeability of
a cement-bentonite wall is normally around 1 x 10   cm/sec,_while a well
designed soil-bentonite wall is capable of achieving 1 x 10   cm/sec (Spooner
et al., 1984a).  Cement-bentonite backfills are also more susceptible to
chemical attack than most soil-bentonite mixtures.  Cement-bentonite is
susceptible to attack by sulfates, strong acids and bases (pH ^4 and X7), and
other highly ionic substances.  A more complete discussion of compatibilities
and compatibility testing is contained in Compatibility of Grouts with
Hazardous Wastes (Spooner et al., 1984b).


               b.  Design and Construction Considerations


     The design and construction of a cement-bentonite slurry wall is very
similar to that of a soil-bentonite wall.  Table 5-16 shows typical composi-
tions of cement-bentonite slurries.  Accelerators, retardants, and various
other additives may be used but are not common practice.  Figure 5-32
illustrates the composition of cement-bentonite slurries.

     Construction of a cement-bentonite wall is nearly identical as for a
soil-bentonite wall.  Although backfill mixing is eliminated, along with the
large area requirement, greater care must be taken in slurry mixing because
the mixture is more sensitive to small changes in composition.  Cement-
bentonite walls are also usually finished with dessication caps to prevent
harmful cracking.
                                     5-94

-------
                                FIGURE 5-32.
               COMPOSITION OF CEMEIMT-BENTONITE SLURRIES
Non-Setting
Slurries
       Semi
       Fluids
    Percent.
    Cement
 Cut-Off
 Slurries
Bleeding
Slurries
Percent
Bentonite
      Source: Jefferis, 1981
                                             • Percent Water
                                   5-95

-------
                                  TABLE 5-16
               TYPICAL COMPOSITIONS OF CEMENT BENTONITE SLURRIES
                    Constituent                     Percentage in Slurry


     Bentonite                                               4-7

     Water                                                  68-88

     Cement
       without replacements                                  8-25
       when blast furnace slag added, minimums               1-3
       when fly ash added, minimums                          2-7

     Blast furnace slag, maximums', if used                   7-22

     Fly ash, maximums, if used                              6-18


Adapted from:  Jefferis, 1981.


               c.  Operation, Maintenance, and Monitoring
     As with soil-bentonite walls, there is no operation required.  Main-
tenance and monitoring are usually directed toward ancillary measures,  and  not
toward the slurry wall itself.  Monitoring water levels and groundwater
quality is important, however, in evaluating the success of the wall  as  part
of the remedial effort.
               d.  Technology Selection/Evaluation


     Like soil-bentonite slurry walls, cement-bentonite walls  can be  an  effec-
tive, relatively inexpensive means of controlling groundwater  flow.   Most  of
the site constraints that affect the selection of a  soil-bentonite wall  also
apply to cement-bentonite walls.  Because cement-bentonite walls are  more
expensive, they are generally used where:   (1) there  is no room to mix and
place soil-bentonite backfill, (2) increased  strength is  required, or
(3) extreme topography make it impractical  to grade  a site level.

     As with any barrier installation, thorough  compatibility  testing is a
must.  Cement-bentonite mixtures are somewhat more susceptible to chemical
attack than most soil-bentonites, and should  not be  placed directly through
wastes or left unprotected from  attack by high-strength leachates.


                                     5-96

-------
               e.  Costs
     Average costs for cement-bentonite slurry walls and  the  effect  of  depth
and digging ease on costs are shown in Table 5-15.  They  are  more  expensive
than soil-bentonite walls due mainly to the cost of Portland  cement.  It
should be noted that these costs do not reflect work in a hazardous
environment.
          5.3.1.3  Diaphragm Walls
     Diaphragm walls are barriers composed of reinforced  concerete  panels
(diaphragms), which are emplaced by slurry trenching  techniques.  They may  be
cast-in-place or pre-cast, and are capable of supporting  great  loads.  This
degree of strength is seldom if ever called  for at a  hazardous  waste site and
their use is extremely rare.  Because diaphragm walls are constructed  in
slurry-filled trenches, it is possible to include them in cement-bentonite  or
soil-bentonite walls for short sections, such as road or  rail crossings, that
require their greater strength.  Provided the joints  between  the  cast  panels
are made correctly, diaphragm walls can be expected to have permeabilities
comparable to cement-bentonite walls.  The same compatibility concerns that
apply to cement-bentonite, apply to diaphragm walls.

     Because diaphragm walls are a specialty item, and rarely used  in pollu-
tion migration situations, they are not discussed in  detail here.   As  shown in
Table 5-15, diaphragm walls cost approximately $ll/square foot  more than
cement-bentonite walls.
     5.3.2  Grouting


     Grouting refers to a process whereby one of a variety  of  fluids  is
injected into a rock or soil mass where  it  is set in  place  to  reduce  water
flow and strengthen the formation.  Because of costs, grouted  barriers are
seldom used for containing groundwater flow in unconsolidated  materials  around
hazardous waste sites.  Slurry walls are less costly  and have  lower perme-
ability than grouted barriers.  Consequently, for waste site remediation,
grouting is best suited for sealing voids in rock.  Even in cases where  rock
voids are transmitting large water volumes, a grout can be  formulated to set
before it is washed out of the formation.  The various types of  grouts avail-
able are discussed below followed by discussions of the various  ways  grouts
may be employed.  Figure 5-33 illustrates the range of grout applicability
based on grain size.

     Cement has probably been used longer than any other type  of material  for
grouting applications (Bowen, 1981).  Cement grouts utilize hydraulic cement
which sets, hardens, and does not disintegrate in water (Kirk-Othmer, 1979).
Because of their large particle size, cement grouts are more suitable for rock
than for soil applications (Bowen, 1981).  However, the addition of clay or

                                     5-97

-------




,





{2
D
0
GC

LL
O
(A N
(A (A
(A z
111 HI —
tc ceo
3 UJ (A
= 50
u. O
ฐ (A

|2
CO

(J
Zj
a.
Q.





























10
D
O




























	








W
E
J2
u




























	 1










,c
0)
oc


























•MW^







^•^•^




Silicates


































i
i
i





0)

o
Q)
m
i.
JS
a








••••MM











J














I
0)
O



























^^MBM




Emulsions
i









MBMซJ •














O
O







O



2
*-*
__
i
0)
5 w
c
2
a









0







8
*






5
f
C,
k
C
4-
(7








•o
(0
C/5










1
2
O





i
]
j
<
c.



kk
i

5





a>
if




Medium
^•^H
0)
!2
CO
o
O



a>
c
iZ


2
S
o


S
5
a
3
J





























1
c
1
o
ca
E

CD
a
CO
TD

5-98

-------
chemical polymers can improve  the  range of  usage.   Cement  grouts  have  been
used for both soil consolidation and water  cut-off  applications,  but  their use
is primarily restricted to more open soils.   Typically,  cement  grouts  cannot
be used in fine-grained soils  with cracks  less  than 0.1  millimeter  wide
(Bowen, 1981).

     Clays have been widely used as grouts,  either  alone or  in  formulations
because they are inexpensive (Guertin  and McTigue,  1982).  Only certain  types
of clay minerals possess the physical  and  chemical  characteristics  favorable
for use in grouting.  These characteristics  include the  ability to  swell  in
the presence of water and to form  a gel structure at low solution concentra-
tions.  These properties are possessed most markedly by  the montmorillonites.
Other types of clay minerals,  such as  kaolinite and illite, can be  used  as
fillers in grout formulations, such as clay-cement  mixtures  (Greenwood and
Raffle, 1963).

     Bentonite grouts (high in calcium montmorillonite)  can be  used alone as
void,sealers in coarse sands with  a permeability of more than 10  ft/day
(10   cm/sec).  Bentonite-chemical grouts  can be used on medium to  fine
sands with a permeability between  10   ft/day  (10   cm/sec) and  1  ft/day
(10   cm/sec).  Both of these  grout types  can also  be utilized  to seal
small rock fissures (Guertin and McTigue,  1982).  Because  of their  low gel
strengths, bentonite grouts are not able to  support structures  and  therefore
can only be used as void sealers (Tallard  and Caron,  1977b).

     Alkali silicates are the  largest and most  widely used type of  chemical
grouts.  Sodium, potassium, and lithium silicates are available,  with  sodium
silicates being used more frequently.  Chemical  grouts (i.e., silicates  and
organic polymers) constitute less  than 5 percent by volume of the grouts  used
in the United States, although they represent almost  50  percent of  the grouts
used in Europe (Kirk-Othmer, 1979).  In addition to their  use as  a  grout,
sodium silicates may be used as additives  to  other  grouts, such as  Portland
cement, to improve strength and durability.

     Silicate grouts are used  for  both soil consolidation  and void  sealing
applications.  These grouts are suitable for-sub surface  applications in soils
with a permeability less than  10 ft/day (10   cm/sec).   Silicate  grouts are
not suitable for open fissures or  highly permeable  materials because of
syneresis (water expulsion) unless they are preceded  by  cement  grouting
(Karol, 1982a; Sommerer and Kitchens, 1980).  Furthermore, tests  conducted by
the U.S.  Army Waterways Experiment Station  found silicate  grouts  to be
ineffective in waterproofing fine-grained soils  (Hurley  and Thornburn, 1971).

     Organic polymer grouts represent only a  small  fraction of  the  grouts  in
use.   These grouts consist of  organic materials  (monomers) that polymerize and
crosslink to form an insoluble gel.  The organic polymer grouts include:

     •  Acrylamide grouts

     •  Phenolic grouts

     •  Urethane grouts


                                     5-99

-------
     •  Urea-formaldehyde grouts
     •  Epoxy grouts

     •  Polyester grouts.

     Acrylamide grouts have been in use for about 30 years,  and were  the  first
of the organic chemical polymer grouts to be developed.  Acrylamide grouts
have the largest use among the organic polymer grouts  and  are  the  second  most
widely used chemical grouts (after silicates) (Karol,  1982a).  They may be
used alone or in combination with other grouts such as  silicates,  bitumens,
clay, or cement (Tallard and Caron, 1977a).  Acrylic and polyacrylamide grouts
are typically used in ground surface treatment, ground  treatment for  oil  well
drilling, and subsurface applications (e.g., waterproof concrete structures).
Acrylate grouts are more commonly used for ground surface  treatment than  for
soil injection where acrylamide grouts are more frequently used.   Acrylamide
applications include structural support and seepage control  for mines,  soil
consolidation for foundations of structures and dams,  and  water control and
soil consolidation for tunnels, wells, and mines (Tallard  and  Caron,  1977a).
Specific applications include grout curtains, loose sand stabilization,
artesian flow shut-off, and water seepage control in jointed and fissured rock
(Office of the Chief of Engineers, 1973).  Based on AM-9 applications,
acrylamide grouts may be used in a variety of soil materials such  as  fine
gravel; coarse, medium, or fine sand; coarse silt; and  some  clays  (Herndon  and
Lenahan, 1976).

     Urethane grouts are the second most commonly used  type  of organic  polymer
grout (Jacques, 1981).  Urethane grouts were developed  in  Germany  for consoli-
dation applications and are now used in Europe, South  Africa,  Australia,  and
Japan (Sommerer and Kitchens, 1980).  These grouts are  used  for water and soil
applications and can penetrate finely fissured material.

     The use of phenolic resin grouts in underground and foundation construc-
tion began in the 1960s (Kirk-Othmer, 1979; Tallard and Caron, 1977a).  These
grouts may be used in fine soils and sands for a variety of  water  control and
ground treatment applications.  However, phenolic grouts are not widely used
alone but are typically used in conjunction with other  grouts  (Tallard  and
Caron, 1977a).

     Urea-formaldehyde resins are frequently referred  to as  aminoplasts.   The
idea for the use of these resins as grouts came from their use as  glue  in the
oil industry (Tallard and Caron, 1977a).  Although urea-formaldehyde  grouts
have been available since the 1960s, they have found limited usage (Karol,
1982b; Sommerer and Kitchens, 1980).  These grouts can set-up  only in an  acid
environment, therefore, they cannot be used in basic formations.

     Epoxy grouts and other glue-like grouts have been in  use  since  1960.
These grouts have had limited use in soil grouting primarily because  of their
high cost (Tallard and Caron, 1977a).  Most of the applications reported  in
the literature involve the use of epoxy resins in mortars  and  for  sealing
cracks.  Epoxy resins can adhere to and seal submerged  concrete, steel, or
wood surfaces, and are useful in water applications (Engineering News-Record,


                                     5-100

-------
1965).  They have been used  for grouting  cracked  concrete  for  structural
repairs and grouting fractured rock  to  improve  its  strength  (Office of the
Chief of Engineers, 1973).

     Polyester grouts have been in use  since  the  1960s.  They  have been used
in a variety of construction applications,  principally  to  treat  cracks in
buildings and structures  (Tallard and Caron,  1977a).  These  grouts have also
been used in mines as well as to stabilize  and  strengthen  porous and fissured
rock (Tallard and Caron,  1977a; Office  of the Chief of  Engineers,  1973).
Polyester grouts have been used infrequently  to treat sand (Tallard and Caron,
1977a).

     The compatibility of these grouts  with hazardous wastes and leachates has
not been studied in great detail, and only  general  incompatibilities are
known.  One recent study  indicates the  response of  several grouts  to various
organic chemicals is unpredictable and  often  drastic (Bodocsi,  1985).   In any
case where grouting is considered a  remedial  option, thorough  compatibility
testing must be performed.

     The component parts of  some grouts,  such as  acrilimides and urea-
formaldehydes, are toxic.  Unless the setting reactions  are  carefully con-
trolled, there is a liklihood that unreacted, toxic compounds  will be released
into the ground.  A thourough characterization of the waste  and  grout
chemistry, as well as the site geochemistry,  is required.


          5.3.2.1  Rock Grouting


     One of the greatest potential uses for grouting in  hazardous  waste site
remediation is for sealing fractures, fissures, solution cavities,  or other
voids in rock.  Nonetheless, rock grouting  at waste sites  is uncommon and no
actual applications were  found in the literature.


               a.  Applications and  Limitations


     Rock grouting may be applied to a waste  site to control the flow of
groundwater entering a site.  In theory,  grouting could  also control leachate
flow in rock, yet in many cases contaminants  interfere with  grout  setting
reactions and/or reduce grout durability.   In many  cases,  the  waste/grout
interaction and compatibility cannot be predicted and extensive  testing is
required.  These issues are discussed in  detail in  Compatibility of Grouts
with Hazardous Wastes (Spooner et al.,  1984b).
                                     5-101

-------
               b.  Design and Construction  Considerations


     As with other types of barrier construction,  the  ultimate  success  of  a
grouting project depends on thorough  site characterization.   The  ability to
seal water bearing voids or zones  is  dependent  on  being  able  to locate  them.
In many remedial grouting operations, only  a  small portion of the rock  mass
will transport water and must be sealed.  Consequently,  the exploratory
investigation must be very thorough.  Detailed  geologic  mapping of the  site,
aided by remote sensing techniques and extensive rock  coring, is  required.
Even with extensive investigation, the complexity  of groundwater  flow in
fractured and fissured bedrock can make a grouting project impossible to plan
completely in advance.

     Based on background and exploratory data,  the location for a pattern  of
primary injection holes is chosen  and injection at one or more  zones  is
identified.  The first few primary holes are  then  drilled and pressure  washed
with water and air (Millet and Engelhardt,  1982).   This  step  removes  drill
cuttings and other debris from the hole to  allow better  grout penetration.
Each hole is then pressure tested, often using  a non-setting  fluid of the  same
viscosity as the grout to be used.  These tests are used to determine the
initial grout mixture and are often conducted using the  grout plant and other
equipment to be used for the actual grouting  (Millet and Engelhardt,  1982  and
Karol, 1982a).

     Each zone within each primary hole is  then injected with the grout
mixture until a predetermined amount  is pumped  (grout  take),  or a pre-
determined flow rate at maximum allowable pressure is  reached.  Maximum
allowable pressure is typically around 1 pound  per square inch  (psi)  per foot
of overburden (Millet and Engelhardt, 1982).  Data from  the drilling  and
injection of the first primary holes  is analyzed,  and  if necessary, the grout
mixture or injection pressure modified before completing the  remaining  primary
holes.  Following completion of the primary hole grouting, the  program  is
again analyzed, necessary changes made, and a pattern  of more closely spaced
secondary holes drilled and injected.

     The analysis and evaluation of the completed  grouting becomes, in
essence, another pressure test.  Close quality  control during drilling  and
grouting identifies areas that require tertiary hole grouting to  complete
sealing.  Such areas are identified by faster than expected drilling  rates and
higher than expected grout takes (Millet and  Engelhardt, 1982).  For  a
successful grouting program, each  hole series (i.e., primary, secondary) will
have lower grout takes than the previous one.   Many projects  will require  that
proof holes be drilled and injected.  A very  low grout take on  tertiary or
proof holes indicates that most voids are grout filled and the  grouting
program was successful.
                                      5-102

-------
                c.   Operation,  Maintenance,  and Monitoring


      As  with  other  subsurface  barriers,  operation and maintenance requirements
 are  negligible.  Monitoring  programs,  consisting of hydrologic measurements
 and  water  quality assessments, are  used  to  evaluate the effectiveness of the
 completed  barrier.


                d.   Technology  Selection/Evaluation


      Rock  grouting  is very much a  specialty operation.   It  is performed by a
 limited  number  of contractors, and  each  such program is highly site-specific.
 Because  this  technique has rarely,  if  ever,  been applied to controlling highly
 contaminated  groundwater, an assessment  of  performance  and  reliability is not
 possible.  Each  instance where rock grouting is feasible for site remediation
 must  be  evaluated on a case-by-case basis.


               e.   Costs
     Each rock grouting job  is highly  site  specific,  and  valid  costs  vary
widely.  Example costs for some common grouts  are  shown in  Table  5-17.   These
have been updated using the  Engineering News-Record cost  indices  for  1979 and
1985.  As shown, individual  grout costs can vary widely.  Grout costs for a
completed job show much less variation.  This  is because  the  cheaper,
particulate grouts are used  to seal  large voids, thus  using more  grout,  while
the more expensive chemical  grouts are commonly used  to seal  small  voids. As
an example of costs for rock grouting, assume  that a  1,000  foot long  barrier,
6 feet thick, and 30 feet deep is to be placed in  rock with 20  percent  void
space.  A double row of injection holes, 6  feet on center,  will be  used (333
holes), and 40 percent sodium silicate grout will  be  injected.  Approximate
costs are given in Table 5-18.


          5.3.2.2  Grout Curtains
     Grout curtains are subsurface barriers created  in unconsolidated
materials by pressure injection.  The various methods of  forming  a  grout
curtain are described below under design and construction considerations.

     Grout barriers can be many times more costly  as slurry walls and  are
generally incapable of attaining truly  low permeabilities in  unconsolidated
materials.  A recent field test study of two chemical grouts  revealed
signficant problems in forming a continuous grout  barrier due to  non-
coalescence of grout pods in adjacent holes and grout shrinkage.  This  study
concludes that conventional injection grouting is  incapable of forming  a
                                     5-103

-------
                                  TABLE 5-17.
                      APPROXIMATE COSTS OF COMMON GROUTS
             Grout  Type
       Approximate Cost
($/gallon) of Solution (1985)
          Portland  cement
          Bentonite
          Silicate  - 20%
                   - 30%
                   - 40%
          Epoxy
          Acrylamide
          Urea formaldehyde
             1.33
             1.76
             1.76
             2.95
             3.86
            42.15
             9.34
             8.00
          Adapted from Spooner et al.,  1984b.
                                  TABLE 5-18.
             APPROXIMATE COSTS ($ 1985) FOR GROUND BARRIER IN ROCK

Unit Operation
Injection hole
drilling
Grout Pipe
Grout Injection
Grout - 40%

Approximate
Unit Cost
$14. 16 per foot
9990 feet
$8.49 per foot
9990 feet
$5.66 per cubic yard
1333 cubic yards
$3.86 per gallon
sodium silicate
35,991 gallons

Approximate Cost
$141,440
$84,869
$7,549
$139,039
Total Cost*
$391,097
Source:  Updated from USEPA, 1982 using ENR
         Construction Cost Index

*Does not include site investigation and characterization

                                      5-104

-------
reliable barrier in medium sands (May et  al.,  1985).   Therefore,  they  are
rarely used when groundwater control in unconsolidated materials  is  desired.
               a.  Applications and Limitations


     Grout curtains, like other barriers, can be  applied  to  a site  in various
configurations.  Circumferential placement offers  the most complete  contain-
ment but requires that grouting take place in contaminated groundwater
downgradient of the source.  As discussed under rock grouting,  this  could
easily cause problems with grout set and durability.  As  with other  tech-
niques, this requires extensive compatibility testing during the  feasibility
study.  Another limitation of curtain grouting  is  the problem of  gaps left  in
the curtain due to nonpenetration of the grout.   Only a few  small gaps in an
otherwise low permeability curtain can  increase its overall  permeability
significantly.


               b.  Design and Construction Considerations


     The design of a grout curtain must be based  on a thorough  site  charac-
terization.  Analysis of site characterization data, including  boring logs,
pump or injection test results, and other data, are used  to  determine if a
site is groutable and which grout is most suitable based  on  viscosity,
compatibility, and ultimate permeability.  This is a very involved process  and
should be conducted by an experienced engineer.

     Construction of a grout barrier is accomplished by pressure  injecting  the
grouting material through a pipe into the strata  to be waterproofed.   The
injection points are usually arranged in a triple  line of primary and
secondary grout holes.  A predetermined quantity  of grout is  pumped  into the
primary holes.  After the grout in the  primary holes has  had  time to  gel,  the
secondary holes are injected.  The secondary grout holes  are  intended to fill
in any gaps left by the primary grout injection (Hayward Baker, 1980).   The
primary holes are typically spaced at 20- to 40-foot intervals  (Guertin  and
McTigue, 1982).  Figure 5-34 illustrates a grout curtain.

     There are several basic techniques that are  utilized to  form the grout
wall.  These include (Hayward Baker, 1980; Guertin and McTigue, 1982):

     •  Stage-up method
     •  Stage-down method
     •  Grout port method
     •  Vibrating beam method.

     In the stage-up method, the borehole is drilled to the  full  depth of the
wall prior to grout injection.  The drill is withdrawn one "stage,"  leaving
                                     5-105

-------
                            FIGURE 5-34
           SEMICIRCULAR GROUT CURTAIN AROUND WASTE SITE
    Semicircular
   Grout Curtain
                        Secondary
                       Grout Tubes
                                Primary
                              Grout Tubes

Source: Spooner et al., 1984b
                              5-106

-------
 several  feet  of  borehole exposed.   Grout is then injected into this length of
 open  borehole until  the  desired  volume has been injected.  When injection is
 complete  the  drill  is  withdrawn  further and the next stage is injected
 (Hayward  Baker,  1980).

      Stage-down  grouting differs from stage-up grouting in that the injections
 are made  from the  top  down.   Thus,  the borehole is drilled through the first
 zone  that  is  to  be  grouted,  the  drill is withdrawn, and the grout injected.
 Upon  completion  of  the injection,  the borehole is redrilled through the
 grouted  layer into  the next  zone to be grouted and the process is repeated
 (Guertin  and  McTigue,  1982).

      The  grout port  method utilizes a slotted injection pipe that has been
 sealed into the  borehole with a  brittle Portland cement and clay mortar
 jacket.   Rubber  sleeves  cover the  outside of each slit (or port) permitting
 grout to  flow only out of the pipe.   The injection process begins by isolating
 the grout  port in  the  zone to be injected using a double packer.  A brief
 pulse of  high pressure water  is  injected into the port to rupture the mortar
 jacket.   Grout is  pumped between the double packers, passes through the ports
 in the pipe,  under  the rubber sleeve,  and out through the cracked mortar
 jacket into the  soil (Guertin and  McTigue, 1982).

      The vibrating beam  method is  not an injection technique as described
 above, but instead  is  a  way of placing grout so as to generate a wall.  In
 this method,  an  I-beam is vibrated  into the soil to the desired depth and then
 raised at  a controlled rate.   As the beam is raised, grout is pumped through a
 set of nozzles mounted in the beam's base filling the newly formed cavity.
 When  the  cavity  is completely filled,  the beam is moved less than one beam
 width along the  wall,  leaving a  suitable overlap to ensure continuity (Harr,
 Diamond,  and  Schmednecht, undated).   This method is illustrated in Figure
 5-35.
                 c.  Operation, Maintenance,  and  Monitoring
     Grout curtains, while  requiring  no  operation  and  little or no main-
tenance may require more monitoring than other  barriers.   This  is because if
even a very small gap  is left  in  the  barrier, it can enlarge quite rapidly by
piping or tunneling if there  is a sufficient hydraulic gradient across the
wall.
                 d.  Technology Selection/Evaluation
     Grout curtains are a specialty technology  seldom  applied  to  hazardous
waste sites.  (This is excepting the vibrating  beam wall  with  bitumen grout,
which has seen some application in recent years.)  As  such,  no detailed
assessment of the performance or reliability of this technology is  possible.
                                     5-107

-------
                          FIGURE 5-35.
              VIBRATING BEAM GROUT INJECTION
Source: Soletanche (undated)
                              5-108

-------
                 e.  Costs
     As with rock grouting, each  curtain  grouting  job  is  highly site specific
Each site requires differing degrees of investigation  and characterization.
The grout injection program must  be tailored  to  its  characteristics.  The
costs given for rock grouting  (Section 5.3.2.1)  can  serve as  an example of
curtain grouting.  Example grout  costs are  shown in  Table 5-17.
     5.3.3  Sheet Piling


     In addition to slurry wall and grouted•cut-offs,  sheet  piling  can be used
to form a groundwater barrier.  Sheet piles  can be made  of wood,  pre-cast
concrete, or steel.  Wood is an ineffective  water barrier, however,  and
concrete is used primarily where great  strength is required.   Steel  is the
most effective in terms of groundwater  cut-off and cost,  and  so  is  discussed
here .

           5.3.3.1  Applications and Limitations


     Steel sheet piling can be employed as a groundwater  barrier much  like the
others discussed in this chapter.  Because of costs and  unpredictable  wall
integrity, however, it is seldom used except for temporary dewatering  for
other construction, or as erosion protection where some  other  barrier,  such as
a slurry wall, intersects flowing surface water.

     One of the largest drawbacks of sheet piling, or  any other barrier
technology requiring pile driving, is the problem caused  by rocky soils.
Damage to or deflection of the piles is likely to render  any  such wall
ineffective as a groundwater barrier.


           5.3.3.2  Design and Construction  Considerations


     The primary design parameters for  any barrier are permeability  and
dimensions.  Dimensional requirements are based on site  characteristics and
are straightforward.  Depth limitations are  governed by  the soil material at
the site.  Design factors for ultimate  permeability of the cut-off  are more
complicated and must assume some factor to account for leakage through the
interlocking joints.

     Typical shapes for steel sheet piling are shown in  Figure 5-36.

     For construction of a sheet piling cut-off, the pilings  are  assembled at
their edge interlocks before they are driven into the  ground.  This  is to
ensure that earth materials and added pressures will not  prevent a good lock
                                     5-109

-------
                                   FIGURE 5-36.
                  SOME STEEL PILING SHAPES AND INTERLOCKS
 Straight Web Type
 Arch Web Type
 Deep Arch
 Web Type
 Z-Type
 Y-Fitting
Source: Ueguhardt et al., 1962
T-Fitting
                                      5-110

-------
between piles.   The  piles  are  then driven a few feet at a time over the entire
length of  the wall.   This  process  is  repeated  until  the piles are all driven
to the desired depth.

     The sheet piling  is  forced  into  place by  a drop hammer or a vibratory
hammer.  Heavy equipment  is  desirable  for fast driving and to prevent damage
to the piles.  Lightweight equipment  can  distort the top edge of the pile and
slow the driving (ARMCO,  Inc., Baltimore,  MD,  personal communication, 1980).
Often, a cap block or  driving  head is  placed on the  top edge to prevent the
driving equipment from damaging  the piles.

     When  first  placed in  the  ground,  sheet piling cut-offs are quite
permeable.  The  edge  interlocks, which are necessarily loose to facilitate
placement, allow water easy  passage.   With time, however, fine soil particles
are washed into  the  seams  and  water cut-off is effected.   The time required
for this sealing to  take  place depends on the  rate of groundwater flow and the
texture of the soil  involved.  In  very coarse, sandy soils, the wall may never
seal.  In  such cases,  it  is  possible  to grout  the piling seams, but this is a
costly procedure.

           5.3.3.3  Operation, Maintenance,  and Monitoring


     Steel sheet  piling cut-offs require  little maintenance.   In corrosive
soils, galvanized or  polymer-coated piles  can  prolong the service life of
cut-off, as will  cathodic  protection,  but  these are  preconstruction measures.
Monitoring of sheet piling cut-offs parallels  that for other barriers, and
involves monitoring head  levels  and groundwater quality on either side of the
barrier to determine  if it is  functioning  as designed.


           5.3.3.4  Technology Selection/Evaluation


     The performance  life  of a sheet piling wall can be between 7 and 40
years, depending  on the condition  of the  soil  in which the wall is installed.
Sheet piling walls have been installed  in  various  types of soils ranging from
well-drained sand to impervious clay,  with soil  resistivities  ranging from
300 ohm/cm to 50,000 ohm/cm, and with  soil pH  ranging from 2.3 to 8.6.
Inspections of these  installed walls did  not reveal  any significant deteriora-
tion of the structure  due  to soil  corrosion (USEPA,  1978).   Additional protec-
tion of the sheet piling wall  against  corrosion can  be  achieved by using
hot-dip galvanized or  polymer-coated sheet.  Cathodic protection has also been
suggested for submerged piling (USEPA,  1978).

     Steel sheet  piles should  not  be considered  for  use in very rocky soils.
Even if enough force can be exerted to  push the  piles around  or through
cobbles and boulders,  the  damage to the piles  would  be  likely to render the
wall ineffective.
                                     5-111

-------
           5.3.3.5  Costs
     Costs for installed steel sheet piling will vary with  depth,  total
length, type of pile (coated or uncoated), and  relative  ease  of  installation,
Average costs range from approximately $6.50 per square  foot  up  to approxi-
mately $16.00 per square foot (Godfrey, 1984a and McMahon,  1984a).
     5.3.4  Bottom Sealing


     Bottom sealing refers to techniques used  to  place  a  horizontal  barrier
beneath an existing site to act as a floor  and  prevent  downward migration of
contaminants.  Most of these techniques involve variations  of  grouting  or
other construction support techniques, and  no  documented  application to a
hazardous waste site was found in the  literature.
           5.3.4.1  Grouting


     Emplacement of a bottom  seal by grouting  involves  drilling  through the
site, or directional drilling  from the  site  perimeter,  and  injecting  grout  to
form a horizontal or curved barrier.  One  such technique, jet  grouting,
involves drilling a pattern of holes across  the  site  to the  intended  barrier
depth.  A special jet nozzle  is lowered  and  a  high  pressure  stream of air and
water erodes the soil.  By turning the  nozzle  through a complete rotation,  a
flat, circular cavity is  formed.  The cavity is  then  grouted with intersecting
grouted masses forming the barrier.  The directional  drilling  method  is very
similar to curtain grouting except that  it  is  performed in  slanted rather than
vertical boreholes.

     Because these techniques  are developmental,  no detailed analysis of
applications, limitations, design, or construction  considerations is  possible.
No cost data, other than  the material costs  shown in  Table  5-15, are
available.
           5.3.4.2  Block  Displacement


     Block displacement  is  an  experimental  technique  for isolating and raising
a contaminated block of  earth.  By  this  technique,  a  perimeter barrier is
constructed by slurry  trenching or  grouting.   Grout is  then injected into
specially notched holes  bored  through  the  site.   Continued  grout or slurry
pumping causes displacement  of the  block of earth isolated  by the perimeter
barrier and forms a bottom  seal beneath  the block.

     This technique has  been laboratory  tested and  field demonstrated at a
nonhazardous  site (Brunsing  and Henderson,  1984).  It has yet to be attempted
                                      5-112

-------
at an actual hazardous waste  site  and  the  technique is still being refined,
As such, no detailed analysis  for  its  use  in  waste  site remediation is
possible, and no cost data are available.
                                     5-113

-------
                                  REFERENCES
Alcar, Y.B., I. Oliver!, and S.D. Field.  1984.  Organic Fluid Effects on  the
Structural Stability of Compacted Kaolinite. In:  Land Disposal of Hazardous
Wastes.  Proceedings of the Tenth Annual Research Symposium, EPA-600/9-84-007.

Bodocsi, A.  1985.  Permeability of Grouts Subjected to Hazardous Leachates.
In:  Proceedings of a National Conference on Hazardous Wastes and Environ-
mental Emergencies.  May 14-16,  1985, Cincinnati, OH.

Bowen, R.  1981.  Grouting in Engineering Practice.  2nd ed.  John Wiley &
Sons, New York, NY.

Brunsing, T.P. and R.B. Henderson.  1984.  A Laboratory Technique for
Assessing the In Situ Constructability of a Bottom Barrier  for Waste Isola-
tion.  In:  Proceedings of the Fifth National Conference on Management of
Uncontrolled Hazardous Waste Sites.  Hazardous Materials Control Research
Institute, Silver Spring, MD.

Bureau of Reclamation.  1977.  Groundwater Manual:  A Water Resources
Technical Publicaton.  U.S. Department of the Interior, Washington, DC.

Bureau of Reclamation.  1978.  Drainage Manual.  Bureau of  Reclamation,
Denver, CO.

Church, H.K.  1981.  Excavation Handbook.  McGraw-Hill Book Company, New York,
NY.

Davis, S.N. and R.J.M. DeWiest.  1966.  Hydrogeology.  John Wiley & Sons,
Inc., New York, NY.

D'Appolonia, D.J.  1980a.  Slurry Trench Cut-Off Walls for  Hazardous Waste
Isolation.  Engineered Construction International, Inc., Pittsburgh, PA.

D'Appolonia, D.J.  1980b.  Soil-Bentonite Slurry Trench Cutoffs.  Journal  of
the Geotechnical Engineering Division, ASCE.  Vol. 106, No. 4.  pp. 399-417.

D'Appolonia, D.J. and C.R. Ryan.  1979.  Soil-Bentonite Slurry Trench  Cut-off
Walls.  Engineered Construction  International, Inc. Presented at the
Geotechnical Exhibitionn and Technical Conference, Chicago, II.  March 26,
1979.

Engineering News-Record.   1965.  Epoxy Seals Leaking Salt Mine Shaft,  p.  119.
November 18.

Evans, J.C., Fang, H., and Kugelman,  I.J.  Organic Fluid Effects on the
Permeability of Soil-Bentonite Slurry Walls.  In:  Proceedings of a National
Conference on Hazardous Wastes and Environmental Emergencies.  May 14-16,
1985, Cincinnati, OH.
                                     5-114

-------
Flint & Walling,  Inc.   1980.   Putting Water  to  Work  Since  1866.   Technical
Information Brochure.   Flint & Walling,  Inc., Kendallville,  IN.

Freeze, R.A. and  J.A. Cherry.  1979.  Groundwater.   Prentice Hall,  Englewood
Cliffs, NJ.

Giddings, T.   1982.  The Utilization of  a  Groundwater  Dam  for Leachate
Containment at a  Landfill  Site.   In:  Aquifer Restoration  and Groundwater
Rehabilitation.   2nd National  Symposium  on Aquifer Restoration and  Groundwater
Monitoring.  May  26-28, 1982.  Columbus, OH.  pp. 23-29.

Godfrey, R.S.  (ed.)  1984a.  Means  Building  Construction Cost Data  1985.   39th
ed. Robert Snow Means Company, Inc., Kingston,  MA.

Godfrey, R.S.  (ed.)  1984b.  Means  Site  Work Cost Data 1985.   4th ed.   Robert
Snow Means Co. Inc., Kingston, MA.

Greenwood, D.A. and J.F. Raffle.   1963.  Formulation and Application  of Grouts
Containing Clay.  In:   Grouts  and Drilling Muds  in Engineering Practices.
Butterworths,  London.   pp. 127-130.

Guertin, J.D.  and W.H.  McTigue.   1982.   Volume  1.  Groundwater Control Systems
for Urban Tunneling.  FHWA/RD-81/073.  Goldberg, Zonio & Associates,  Inc.
Prepared for:  U.S. Department of Transportation, Federal  Highway
Administration.  Washington, DC.

Harr, M.E., S. Diamond, and F. Schmednecht.  (No Date.)  Vibrated-Beam Placed
Thin Slurry Walls for Construction  Dewatering, Water Connservation, Industrial
Waste Ponding, and Other Applications.   M.E. Harr Enterprises,  Inc.   (West
Lafayette, IN); Sidney  Diamond and  Associates,  Inc.  (West  Lafayette,  IN);  and
Slurry Systems, Inc. (Gary, IN).

Hayward Baker  Company,  EarthTech Research  Corporation,  and ENSCO,  Inc.   1980.
Chemical Soil  Grouting.  Improved Design and Control.   Draft.   Federal  Highway
Administration, Fairbank Research Station, McLean, VA.

Herndon, J. and T. Lenahan.  1976.  Grouting Soils.  Volume  2.  Design and
Operation Manual.  FHWA-RD-76-27.   Halliburton  Services.   Prepared  for USDOT,
Federal Highway Administration, Washington,  DC.

Hurley, C.H. and T.H. Thornburn.  1971.  Sodium Silicate Stabilization of
Soils - A Review of the Literature.  UILU-ENG-71-2007.  University of
Illinois, Urbana, IL.

Jacques, W.B.   1981.  Stopping Water with  Chemical Grout.  Civil  Engineering.
December.

Jefferis, S.A.  1981.   Bentonite-Cement  Slurries for Hydraulic  Cut-Offs.   In:
Proceedings of the Tenth International Conference on Soil  Mechanics and
Foundation Engineering, Stockholm,  Sweden.   June 15-19, 1981.  A.A. Balekma,
Rotterdam,   pp. 435-440.
                                     5-115

-------
Johnson Division, UOP, Inc.  1975.  Groundwater and Wells.  A Reference Book
for the Water-Well Industry.  Johnson Division, UOP, Inc.,  St. Paul, MN.

Johnson Division, UOP, Inc.  1984.  Johnson Screens by UOP.  Johnson Division,
UOP, Inc., St. Paul, MN.

Karol, R.H.  1982a.  Chemical Grouts and Their Properties.  In:  Proceedings
of the Conference on Grouting in Geotechnical Engineering,  American Society of
Civil Engineers, NY.

Karol, R.H.  1982b.  Seepage Control with Chemical Grout.   In:  Proceedings of
the Conference on Grouting in Geotechnical Engineering, American Society of
Civil Engineers, NY.

Keely, J.F. and C.F Tsang.   1983.  Velocity Plots and Capture Zones of Pumping
Centers for Ground-Water Investigations.  Ground Water.  Vol. 21, No. 6.   pp.
701-714.

Kirk-Othmer Encyclopedia of  Chemical Technology.  1979.  Vol. 5. 3rd ed.
John Wiley & Sons, New York, NY.

Knapp, Inc.  1982.  Polly-Pig.  B5/82/5M.  Technical Bulletin.  Knapp,  Inc.,
Houston, TX.

Lohman, S.W.  1972.  Ground-Water Hydraulics.  Geological  Survey Professional
Paper 708.  U.S. Geological  Survey, Reston, VA.  70 pp.

Luhdorff, E.E. and J.C. Scalmanini.  1982.  Selection of Drilling Methods,
Well Design, and Sampling Equipment for Wells to Monitor Organics.  In:
Aquifer Restoration and Groundwater Rehabilitation.  Proceedings of 2nd
National Symposium on Aquifer Restoration and Groundwater  Monitoring.  May
26-28, 1982.  Columbus, OH.  pp. 359-365.

Lundy, D.A. and Mahan, J.S.  1982.  Conceptual designs and cost sensitivities
of  fluid recovery systems  for containment of plumes of contaminated
groundwater.  In:  National  Conference on Management of Uncontrolled Hazardous
Waste Sites.  November 29-December 1, 1982, Washington, D.C.  pp.  136-140.

May, J.H., Larson, R.J., Malone, P.G., and Boa, V.A. Jr.   Evaluation of
Chemical Grout Injection Techniques for Hazardous Waste Containment.  In:
Eleventh Annual Research Symposium on Land Disposal of Hazardous Wastes.
EPA-600/9-85-013.  April 29-May 1, 1985.  Cincinnati, OH.

McMahon, L.A.  1984a.  1985  Dodge Guide to Public Works and Heavy Construction
Costs.  Annual Edition No.  17.  McGraw-Hill Information Systems Company,
Princeton, NJ.

McMahon, L.A.  1984b.   1985  Dodge Manual  for Building Construction  Pricing and
Scheduling.  Annual Edition  No. 20.  McGraw-Hill Information  Systems Company.
Princeton, NJ.
                                      5-116

-------
Millet, R. A. and R.L. Engelhardt.  1982.  Matrix Evaluation of  Structural
Grouting of Rock.  In:  Proceedings of the Conference on Grouting  in
Geotechnical Engineering, ASCE, New York, 1982.

Minning, R.C.  1982.  Monitoring Well Design and Installation.   In:  Aquifer
Restoration and Groundwater Rehabilitation.  Proceedings of 2nd  National
Symposium on Aquifer Restoration and Groundwater Monitoring.  May  26-28,  1982,
Columbus, OH.  pp. 194-197.

Office of the Chief of Engineers.  1973.  Engineering Design.  Chemical
Grouting.  EM 1110-2-3504.  Department of the Army, Washington,  DC.

Powers, J.P.  1981.  Construction Dewatering.  A Guide  to Theory and Practice.
John Wiley and Sons, New York, NY.

Ressi di Uervia, A.L.  1980.  Economic Considerations in Slurry  Wall
Applications.  From:  Slurry Walls for Underground Transportation  Facilities.
Proceedings U.S. Department of Transportation, Federal  Highway Administration,
1979.

Richardson Engineering Services.  1980.  Process Plant  Construction Estimating
Standards.  Volume 1:  Sitework, Piling, and Concrete.  Richardson Engineering
Services, Solana Beach, CA.

Schwab, G.O., R.K. Frevert, T.W. Edminster, and K.K. Barnes.  Soil and Water
Conservation Engineering.  John Wiley & Sons, New York, NY.

Soil Conservation Service  (SCS).  1973.  Drainage of Agricultural  Land.   Water
Information Center, Syosset, NY.

Soletanche.  (No Date.)  Soils Grouting.  Technical Bulletin.  Paris.

Sonroerer, S. and J.F. Kitchens.  1980.  Engineering and Development Support of
General Decon Technology for the DARCOM Installation Restoration Program.
Task 1 Literature Review on Groundwater Containment and Diversion  Barriers.
Draft. Atlantic Research Corporation.  Prepared for:  U.S. Army  Hazardous
Materials Agency, Aberdeen Proving Ground, MD.

Spooner, P., R. Wetzel, C. Spooner, C. Furman, E. Tokarski, G. Hunt, V. Hodge,
and T. Robinson.  1984a.   Slurry Trench Construction for Pollution Migration
Control.  EPA-540/2-84-001.  JRB Associates.  Prepared  for:  USEPA, Municipal
Environmental Research Laboratory, Cincinnati, OH.

Spooner, P., G. Hunt, V. Hodge, and P. Wagner.  1984b.  Compatibility of
Grouts with Hazardous Wastes.  EPA-600/2-84-015.  JRB Associates.  Prepared
for:  USEPA, Municipal Environmental Research Laboratory, Cincinnati, OH.

Tallard, G.R. and C. Caron.  1977.  Chemical Grounts for Soils.  Vol. I.
Available Materials.  FHWA-RD-77-50.  Soletanche and Rodio, Inc.   Prepared
for:  United States Department of Transportation, Federal Highway
Administration, Offices of Research and Development, Washington, DC.
                                     5-117

-------
Tallard, G.R. and C. Caron.  1977b.  Chemical Grouts for Soils.  Vol. II
Engineering Evaluation of Available Materials.  FHWA-RD-77-51.   Soletanche and
Rodio, Inc.  Prepared for:  United States Department of Transportation,
Federal Highway Administration, Offices of Research and Development,
Washington, DC.

Taylor, W.R. and L.S. Willardson.  1971.  Target Grade Control for Trenching
Machines.  National Drainage Symposium Proceedings, December 6-7, 1971.
Chicago, IL.  American Society of Agricultural Engineers, St. Joseph, MI.

Todd, O.K.  Groundwater Hydrology.  1980.  2nd ed.  John Wiley & Sons, Inc.,
New York, NY.

Ueguhardt, L.C. et al.  1962.  Civil Engineering Handbook.  McGraw-Hill Book
Company, New York, NY.

USEPA, 1985.  Leachate Plume Management.  SAIC/JRB.  Prepared for:  USEPA,
Office of Research and Development, Cincinnati, OH.

USEPA, 1984.  Case Studies:  Remedial Response at Hazardous Waste Sites.
EPA-540/2-84-002b.  USEPA, Office of Emergency and Remedial Response,
Washington D.C. and USEPA, Office of Research and Development, Cincinnati, OH.

USEPA.  1978.  Guidance Manual for Minimizing Pollution from Waste Disposal
Sites.  EPA 600/2-78-142.  USEPA, Office of Research and Development,
Cincinnati, OH.

Van Hoorn, J.W. and W.R. Van der Molen.  1974.  Drainage of Sloping Lands.
In:  Drainnage Principles and Applications, Volume IV, Design and Management
of Drainage Systems.  Publication 16.  International Institute of Land
Reclamation Improvement, Wageningen, the Netherlands.  pp. 329-339.

Van Schlifgaarde, J.  1974.  Drainage for Agriculture.  Agronomy 17, American
Society of Agronomy, Madison, WI.

Wesseling, J.  1973.  Theories of Field Drainage and Watershed Runoff:
Subsurface Flow into Drains.  In:  Drainage Principles and Applications,
International Institute for Land Reclamation and Improvement, Wageningen, the
Netherlands.
                                     5-118

-------
                                   SECTION  6

                                  GAS CONTROL
     The disposal of solid and hazardous waste by  landfilling  employs
engineering principles and construction methods  to  confine waste  to  the
smallest area practical, compact  the waste  into  the lowest volume possible,
and cover the waste with layers of  soil to  limit exposure of the  materials  to
the environment.  This method inadvertently creates conditions in which  gases
are produced, vented to the atmosphere, and migrate laterally  through  soil,
utilities, and other pathways to  outlying areas.   Serious accidents  resulting
in injury, loss of life, and extensive property  damage can occur  where land-
fill conditions favor gas migration (Emcon, 1981).   Degradation of air quality
has resulted from the venting of  gases to the atmosphere.

     Organic matter within landfills is transformed into a variety of  simpler
organic materials and byproduct gases by the action of microorganisms  that  are
abundant in refuse.  The major components of landfill-generated gas  are  carbon
dioxide and methane; however, lesser amounts of  oxygen, nitrogen,  and hydrogen
sulfide are frequently produced.  The refuse experiences first aerobic
(oxygen-abundant), then anaerobic (oxygen-deficient) conditions,  and the gas
composition varies through the transition (Emcon,  1981).

     The period of gas generation from a landfill may range from  a few years
to hundreds of years.  The active gas production life is dependent on  site-
specific conditions.  The rate of gas production is  dependent  on  the levels of
oxygen present, refuse moisture content, environmental pH, temperature,  and
refuse composition.  Gas production is stimulated by a high percentage of
biodegradable materials such as food and garden wastes, paper,  textiles, and
wood, and can be inhibited by the presence  of waste  materials  that are toxic
to the gas-producing microorganisms.  The major  component of landfill-
generated gas is methane, which is odorless, colorless, lighter than air, and
combustible.  The high combustibility of methane makes it a potential hazard
in landfill environments.  In concentrations between 5 and 15  percent by
volume in air, methane is flammable at atmospheric  pressure and ordinary
temperatures (Emcon, 1981).

     Gases may be formed in landfills by microbiological degradation of
organic matter and/or by volatilization of  organic  liquids.  Organic gases can
also be present in landfill gas by volatilization of volatile  organic  liquids
(solvents, fuels, etc.) within the landfill or by biological decomposition of
mixtures of organic matter and organic liquids.  Landfilled organic  liquids
can inadvertently be present in domestic refuse, be  illegally  deposited  in
                                     6-1

-------
sanitary landfills, or be placed free-flowing or in containers in industrial
and hazardous waste landfills.

     The relative ease with which landfill gas is capable of migrating through
soil, often to significant distances, exacerbates the hazards of explosion and
exposure.  Movement of the gas will occur in sand, silt, or clay soils as long
as there are connected voids.  However, the rate of movement decreases as pore
size decreases; therefore, movement will be greatest through highly permeable
sand or gravel and least in clay soils.  Utility and drainage corridors often
provide pathways for methane migration (Kmcon, 1981).

     In addition to methane-related accidents, migrating gas may result in
other adverse effects such as damage to vegetation (depending on plant
sensitivity to carbon dioxide and methane, oxygen depletion, and elevated
temperatures), nuisance of malodors (carbon dioxide and methane have no odor;
malodors may result from volatile organic gases of decomposition or,
occasionally, hydrogen sulfide) (Emcon, 1981), and acute and chronic health
effects resulting from exposure to toxic gases.

     The gases originating within landfills vent to the atmosphere by vertical
migration and/or lateral migration.  The majority of the gas produced by a
landfill normally vents through the cover material.  However, if this vertical
path is sealed by frost, rain-saturated cover soil, pavement, or "capping"
with a clay or synthetic liner, there is a greater tendency toward lateral
migration.  In general, a landfill constructed in a sand-gravel environment
experiences greater lateral movement of gases than one in a clay environment.
These concepts are shown in Figure 6-1.  Since gas migration and venting can
result in significant hazard, special control systems have been developed to
alleviate these problems (Emcon, 1981).  The following three categories of gas
control systems are described in this chapter:
        Passive perimeter gas control systems
        Active perimeter gas control systems
        Active interior gas collection/recovery systems
6.1  Passive Perimeter Gas Control Systems


     6.1.1  General Description


     Subsurface migration of  landfill-generated gases beyond  the  landfill
property line (or other appropriate limit) may be prevented through  the  use  of
passive gas control systems,  i.e., systems that control  gas movement  by
altering the paths of  flow without the use of mechanical  components.   Passive
systems may be further categorized as high-permeability  or  low-permeability
systems.

     High-permeability systems entail the  installation of highly  permeable
(relative  to the surrounding  soil) trenches  or wells between  the  landfill and

                                     6-2

-------
                   FIGURE 6-1.  PATHWAYS OF GAS MIGRATION
                          EXTENSIVE LATERAL MIGRATION
 CLAY OR SYNTHETIC CAP
.(LOW PERMEABILITY)
                                           CLAY SOIL, FROZEN OR SATURATED SOIL,
                                           OR PAVEMENT (LOW PERMEABILITY)
                                                                     SAND AND GRAVEL SOIL
                                                                     (HIGH PERMEABILITY)
                               EXTENSIVE VERTICAL
                                                     SAND AND GRAVEL CAP
                                                     (HIGH PERMEABILITY)
 \
       V//////////////////////////////777//X


\ \\\ VK\\\\\ X  X^JN XCLAY SOIL
                             CLAY OR SYNTHETIC LINER \____ (LOW PERMEABILITY)
                             (LOW PERMEABILITY)
  Source: Emcon, 1981
                                        6-3

-------
the area to be protected as shown in Figure 6-2.  Since  the permeable material
offers conditions more conducive to gas  flow than the  surrounding  soil,  paths
of flow to points of controlled release  are established.  High-permeability
systems generally take the form of trenches or wells excavated outside of  the
landfill limit and backfilled with a highly permeable medium such  as a coarse
crushed stone.  As well spacing decreases, the design  and function of well
vents approaches that of trench vents (SCS, 1980).

     Low-permeability systems, as shown  in Figure 6-3, effectively block gas
flow into areas of concern by the use of barriers (such  as synthetic membranes
or natural clays) between the landfill and the area to be protected.  With
low-permeability systems, gases are not  collected and  therefore cannot be
conveyed to a point of controlled release or treatment.  The purpose of  the
system is to prevent or reduce gas migration into areas  that are to be
protected.  These two concepts (high- and low-permeability) of passive gas
control are often combined in the same system to provide controlled venting of
gases and blockage of available paths for gas migration  (SCS, 1980).

     Low-permeability passive control systems also attempt to check gas  migra-
tion by altering the paths of convective flow, but also  prevent or impede
diffuse flow by blocking available paths.  By placing  a  relatively impermeable
material in paths of gas flow, the pressure gradient across the barrier  is
"flattened" due to the high resistance.  Gases will preferentially flow  along
paths of steeper pressure gradients in order to vent to  the atmosphere.  These
new paths will be either through the ground surface between the barrier  and
the landfill or through the landfill surface.  Diffuse gas flow through  the
barrier is minimal since diffuse flow also requires paths for gas  movement.  A
barrier would effectively block the paths and contain  diffuse flow (SCS,
1980).
     6.1.2  Applications/Limitations


     Passive gas control systems can be used  at virtually  any  site  where  there
is capability to trench or drill an excavation to  at  least  the  same depth as
the landfill.  Limiting factors could  include the  presence  of  a perched water
table or rock strata.  Passive vents should generally be expected to be less
effective in areas of high rainfall or prolonged freezing  temperatures.


     6.1.3  Design Considerations
     A schematic diagram of a high-permeability  trench  is  shown  in  Figure
6-2.  The width of the trench is dictated by  the  characteristics  of available
excavation equipment, the slope stability of  the  soil being  excavated,  and  the
depth of the trench.  Minimum trench widths of 3  feet are  often  specified  in
order to ensure an open trench over the  full  depth.  The depth of the  trench
is dictated by local site conditions.  In general, the  trench should extend
from the ground surface to a relatively  impermeable  stratum  of unfractured


                                     6-4

-------
                            FIGURE 6-2.
         PASSIVE GAS CONTROL USING A PERMEABLE TRENCH
                            PLAN VIEW
                         PERMEABLE
                         VENT TRENCH
                                             AREA TO BE
                                             PROTECTED
                                             DRAINAGE SWALE
                                             AROUND LANDFILL
                                    PAVED DRAINAGE      MONITORING PROBE
                                    CROSSING IF REQUIRED (SPACE @ 100' ฑ O.C.)
                           \
                           SECTION A-A
              4" PVC, VENT PIPE
              (SPACE @ 50'ฑO.C.)
  4" PVC PERFORATED COLLECTOR**
          (CONTINUOUS)
    DRAINAGE
    SWALE
                                                       MONITORING
                                                         PROBE
                      NATURAL
                      GROUND
                             DEPTH }
                             VARIES
            GROUNDWATER TABLE. BEDROCK
        ETC
NATURAL GROUND
        AREA TO
           BE
       PROTECTED
                                                GRAVEL
                                               OR STONE
                                              C/4" MIN. SIZE)
                                    3 +
                                              * FOR APPLICATIONS WHERE
                                               VENTING OF GASES TO
                                               ATMOSPHERE IS ACCEPTABLE.
Source: SCS, 1980
      ** COLLECTOR CAN BE USED TO
        CONVEY GASES TO A TREAT-
        MENT SYSTEM.
                               6-5

-------
                       FIGURE 6-3.
       PASSIVE GAS CONTROL SYNTHETIC MEMBRANE
 PLAN VIEW
                                           SYNTHETIC
                                           MEMBRANE
                                             AREA TO BE
                                             PROTECTED
                                                MONITORING PROBE
                                                (SPACE @ 100'ฑ O.C.
Source: SCS, 1980
                        SECTION A-A
             MONITORING
                PROBE
                            DEPTH
                            VARIES
                     GROUNDWATER
                  TABLE, BEDROCK, ETC
                                          SYNTHETIC
                                         'MEMBRANE
                                              J
       AREA TO BE
NATURAL
GROUND
                                           TRENCH
                                           BACKFILL
        PROTECTED
                                       ANY CONVENIENT WIDTH
                           6-6

-------
bedrock or clay or to the lowest groundwater table  level.   In some applica-
tions, the trench need not be as deep, so  long as it extends to  a  sufficient
depth to intercept all possible avenues of gas migration.   This  depth  is  a
function of the landfill depth and the geology in the vicinity of  the  landfill
(SCS, 1980).  The logistics of excavating open trenches  (i.e., bracing or
sloping trench walls) can constrain the use of passive venting trenches to
relatively shallow depths of 30 feet and less.

     Crushed stone or river gravel is normally used as the  permeable-medium
trench backfill.  Stone sizes greater than 1/4-inch are  recommended; fine
material should not be used.  As shown in Figure 6-2, horizontal perforated
pipe and vertical solid-wall riser pipes are often used  to  ensure  that paths
of gas flow to the atmosphere remain open in the event that the  top of the
trench becomes blocked by ice, snow, vegetation, etc.  The  ground  surface
should be graded to drain away from the trench to prevent the washing  of  soil
into the voids of the stone.  If drainage swales must cross the  trench, they
should be installed using enclosed conduits or paved channels.

     Low-permeability systems would normally be installed in a trench  situated
and excavated in a manner similar to that used in installing a passive vent
trench.  The width and depth requirements would essentially be the same.
However, in lieu of the highly permeable stone backfill, low-permeability
material would be placed.  Synthetic membranes are normally used as barriers
in this application (SCS, 1980).

     The synthetic membrane is normally draped over the  wall of  the trench
furthest from the landfill.  A schematic diagram of a synthetic membrane
barrier is shown in Figure 6-3.  The membrane must be continuous in order to
be effective and many splices may be required, depending upon the  depth and
length of the trench.  The membrane should completely over  the wall of the
trench and the end is often temporarily laid on the ground  surface at  the top
of the trench to hold it in place.  It is necessary that extreme caution  be
taken during the installation to prevent tearing or puncturing of  the
membrane.  This would include "dressing" the trench wall to remove protruding
objects such as roots or jagged rock fragments.  Once the membrane has been
placed and secured at ground level, the trench is carefully backfilled with
any material that would not puncture the membrane or settle appreciably after
being placed.  Native soil, sand, or rounded gravel is often used  for  this
purpose.  Once the entire trench has been backfilled, excess membrane  above
the ground surface may be trimmed (SCS, 1980).

     Soil-bentonite slurry cut-off walls have been used  as  gas migration  con-
trol barriers.  The saturated soil-bentonite slurry backfill serves the same
function as the compacted clay or membrane barrier.  However, the  effective-
ness of slurry walls as barriers depends on the slurry remaining saturated, a
condition that is assured at depths below the groundwater table.   Special
provisions, such as the application of water, may be required to assure
continuous saturation of the slurry and thus its effectiveness as  a barrier.
Information pertaining to the effectiveness of slurry walls over a range  of
applications is limited; this technique is not conventional and  is not widely
recognized for gas migration control.  Information pertaining to slurry walls
for groundwater control and protection is provided in Section 5-3.

                                     6-7

-------
     High-permeability and low-permeability passive control concepts are often
combined into a single passive gas control system.  A synthetic membrane is
installed along the trench wall as described above under low-permeability
systems.  From that point, the trench is backfilled as described under
high-permeability systems, except that care must be taken to avert damaging
the membrane.  Such a system relies upon the high-permeability material to
control both convective and diffuse flow.  Since a relatively "steep" pressure
gradient (gravel) is followed immediately by a material extremely resistant to
gas flow (membrane), landfill gases are further encouraged to flow through the
gravel and vent piping to the atmosphere.  In addition, the combination of the
two concepts provides a degree of redundancy, affording protection in the
event that one portion of the system is inadequately designed or improperly
installed (SCS, 1980).


     6.1.4  Construction/Implementation Considerations


     Trenches excavated for passive gas control systems are normally cut with
backhoes, although other conventional trenching equipment allowing for
adequate depth and width could be used.  Rounded gravel or crushed stone,
washed of fines, should be used for venting trench backfill material, and only
rounded gravel should be used as a permeable medium in conjunction with a
synthetic membrane liner to avert tearing or puncturing the membrane.
Virtually any pipe material may be used for perforated and riser pipe,
although 3- or 4-inch PVC pipe is customarily used.  Polyvinyl chloride (PVC),
polyethylene (PE), chlorinated polyethylene (CPE), Hypalonฎ, and other
materials have been utilized for impermeable synthetic membranes.  A minimum
thickness of 20 mils is recommended.  Lap joints are cemented or heatwelded
and may be made at the factory or in the field (SCS, 1980).

     During trench excavation for passive systems, care should be taken to
ensure that workers are not overcome by venting gases or exposed to explosion
hazards.  Open flames and smoking should be prohibited in the work area.
Regular monitoring of methane, oxygen, hydrogen sulfide, and other gases of
concern should be conducted.  Depending on soil characteristics and trench
depth, sloping of trench walls may be required to avoid instability; alter-
natively, shoring and bracing can be used to support trench walls.  This does
not adversely affect the installation, although additional backfill material
is required as a result.  During the installation of synthetic membrane
barriers, extreme care must be taken to ensure that lap joints are properly
sealed and that tears and punctures are averted in the process of placing the
membrane and backfilling the trench (SCS, 1980).


     6.1.5  Operation, Maintenance, and Monitoring


     Passive gas control systems, by definition, alter the paths of gas flow
without the use of mechanical components.  As such, the systems are essen-
tially self-operating.  Vent pipes, drainage patterns, and general conditions


                                     6-8

-------
in the vicinity of the systems should be occasionally (e.g., monthly)
inspected to identify the need for repairs or other maintenance.

     Monitoring the effectiveness of passive gas control  systems normally
consists of periodic sampling of subsurface gases  from  probes  installed  in  the
area being protected.  Conceptual probe locations  are shown  in Figures 6-2  and
6-3 and a typical probe design is shown in Figure  6-4.

     Installation of a gas monitoring probe requires drilling  a hole  in  the
soil to a depth over which monitoring is desired.  The  probe pipe  is
perforated except for the upper several feet.  The probe  is  installed  in the
drilled hole, and the hole is backfilled with permeable material (sand or pea
gravel) to a height above the perforations.  The remainder of  the  hole is
backfilled with soil to act as a seal against the  intrusion  of air.   Seals  are
sometimes used to keep soil from entering the permeable material.  A  gas
sample can then be withdrawn from the probe at the surface (Emcon, 1981).

     A thin-walled PVC (polyvinyl chloride) pipe is commonly used  for  the
probe casing.  To obtain a representative gas sample, the probe must  be  purged
to ensure that gas from the soil is being withdrawn.  Since methane is lighter
than air and carbon dioxide is heavier, some stratification  of the gas is
frequently observed in the probe (Emcon, 1981).

     Gas samples can be collected in bottles for laboratory  analysis; however,
readings taken with portable meters or organic vapor analyzers are more
commmon.  Generally, the presence of methane or other combustible  gas  or fume
can be detected with devices that provide scales of measure  in "percent  com-
bustible by volume" and/or "percent of LEL" (lower explosive limit).   These
devices are commonly used by fire departments, natural gas and sewer
utilities, and the mining and refining industry.   Organic vapor analyzers and
gas chromatographs provide further identification  and quantification  of
mixtures of gases.

     The effectiveness of gas control can also be monitored  by automatic
detectors that sense the presence of combustible and/or toxic gases and  sound
alarms or trigger other responses.  The detectors  are placed in utility
vaults, living and working areas, ventilation systems, and subsurface  soils.
The detectors are sensitive to changes in temperature and humidity, and
require regular calibration and periodic replacement.

     The presence of combustible and/or toxic gases at a monitoring point is
an indication that the gas migration control system is not affording  the
protection that is intended and the flaw in the system  should  be identified
and corrected.
     6.1.6  Technology Selection/Evaluation


     Subsurface pressure is a driving force that causes landfill gas  to  flow
from the landfill to the atmosphere.  High-permeability systems attempt  to
check gas migration by altering the paths of convective (pressure) flow.  In

                                     6-9

-------
                           FIGURE 6-4.
                TYPICAL GAS MONITORING PROBE
                                            PROTECTIVE COVER
NATURAL GROUND ^


-r^_
&











>
4
*
1
4


CO
4
1
I
',.
V
f
i



/
/>

,,1,
*
i
•vV
* - *.
• ••
S\
'** ป*
V*.
";•*•ป
•.*•'."
::v-
* **?*••"
***•*• **
>:^-:
'* •.*
•*•*!*
•••v
Vf
4" r
/
-J.
/
^^

7
T
ซ/;',v
< ';.".
'. * •*
1 V-
- '. '•
' : .•. •.
•V*- *
• I*''
' .
'.':'•''.
&2
'.'•*"• *
• •"•••
••'. * * •
• •**
< •-'.••-'.
• . ••
' V'.v
T-X
i/llN.
	 	 CAP WITH Fl FXIRI F TIIRIT

^A'w
A
ry
	 COMPACTED SOIL BACKFILL
.._ .W-W PVC PIPF




%'-1'/ป" PERFORATED PVC PIPE
^ ^
^NATURAL GROUND v
'*
$
	 WASHED PEA GRAVEL
s
y,
5

Source: EMCON, 1980
                              6-10

-------
providing a highly permeable path for gas flow, the pressure gradient is
"steepened" (by reducing the length of the path of flow to the atmosphere).
Gases tend to flow in the direction of the steepest pressure gradient, often
referred to as the "path of least resistance."  Passive vents, however, do
little to control diffuse gas flow.  Gases moving under diffuse flow tend  to
move randomly in all directions from the point of generation or release.
Although the potential for gas migration is usually much lower under diffuse
flow than under convective flow, many passive vents have been ineffective  or
limited in effectiveness by diffuse gas flow passing through the permeable
medium and continuing migration beyond the vent.

     High-permeability gas control systems have functioned adequately in many
applications; however, there appear to be no clear patterns which dictate
success or failure of the systems (SCS, 1980).  While passive vents may
perform effectively at some sites, the method cannot be considered to be
reliable for landfill gas migration control because of the inability of vents
to control diffuse flow.  Numerous passive well venting systems have been
converted to active systems (see Section 6.2) because of poor or unreliable
performance.  Low-permeability systems block diffuse flow and are highly
reliable when properly designed and installed.  Combined low- and high-
permeability systems offer the highest level of effectivenesss and reliability
of passive gas control.  Since passive systems require virtually no operation
and maintenance, their performance and reliability are not limited by manual
upkeep or continuous operation of mechanical components.

     Passive gas control systems can be implemented with relatively conven-
tional construction equipment, labor, and materials.  Handling and placement
of synthetic liners requires specialized equipment and labor.  Slope stability
of soils being excavated is an important consideration.  Laying back of trench
walls requires additional excavation and working area, and placement of
shoring or bracing in the trench requires additional labor and materials.
Workers should not enter excavated areas without adequate respiratory and
other appropriate protection and rescue provisions.  No flames or smoking
should be allowed in the vicinity of open excavations.

     Passive control systems require relatively little time to implement.  A
single crew can complete up to several hundred feet of perimeter per day.  Gas
control is affected as soon as the vent is complete, although a short time may
be required for gas that has already migrated to dissipate.


     6.1.7  Costs
     Because the gas control systems described herein are "passive"  in
concept, virtually no operating or maintenance costs should be incurred.   It
is recommended, however, that periodic visual inspections be made  in  the  area
of the system to determine whether local activities may have interfered with
the system's effectiveness.  Also, subsurface gas should be periodically
monitored in the area being protected to ensure that the systems are
performing their intended functions.
                                     6-11

-------
     Costs associated with treatment of collected gases will also  contribute
to the total cost of gas control.  Treatment of gaseous waste  streams  is
addressed in Section 10.2.

     The following is an example of an estimate of  the costs of  a  passive
perimeter gas migration control system:

Scenario:

     •  Closed landfill containing primarily domestic refuse,  free liquid
        organic wastes are mixed with solid waste.

     •  Average landfill depth is 40 feet.

     •  Landfill perimeter is 2,300 feet.

     •  Continuous low-permeability clay exists at  depths of 25  feet and below
        and underlies the bottom of the landfill.

Required:

     •  Estimate the capital and O&M costs of a passive combined  low-
        permeability and high-permeability perimeter gas migration control
        system.

Assumptions:

     •  Barrier trench should extend 30 feet below  the ground  surface.

     •  By off-setting the trench from the edge of  landfill, the  length of  the
        trench will be 2,500 feet.

     •  The width of the trench will be 3 feet.

     •  Collector piping will be installed over the full length  of the trench.

     •  Vent pipes will be 10 feet long and will be spaced  at  50  feet.

     •  The trench will be lined with a synthetic membrand  and backfilled with
        washed gravel.

     •  Gases will be vented to the atmosphere.

     •  Monitoring probes will be spaced at 100 feet and will be  30 feet deep.

     •  Probes will be monitored quarterly with a portable  meter.

Estimates of Quantities:
                                                                   3
     •  Trench excavation and backfill:  30' x 2,500' x 3'  -r 27  ft /yd =
        8,333 cubic yards


                                     6-12

-------
     •  Horizontal piping:  2,500 linear feet

     •  Vertical piping:  2,500' -r 50' x 10' = 500 vertical  feet

     •  Synthetic membrane:  2,500' x 30' = 75,000 sq. ft.

     •  Monitoring probes:  2,500' 4- 100' x 30' = 750 vertical  feet

     •  Monitoring:  2,500' •=- 100" x 4 visits/year = 100 visits/year
       Item

Trench excavation
Dispose of exca-
  vated material
Gravel backfill
Horizontal piping
Verticalpiping
Synthetic membrane
Monitoring probes

Total Capital Costs
       Item

Monitoring with
  portable meter

Total Annual
  O&M Costs
                          Estimate of Capital Costs:
                                      Unit Cost
Quantity
8,333 yd3
8,333 yd3
8,333 ydJ
2,500 l.f.
500 v.f.
75,000 sq. ft.
750 v.f.
Estimate of

Quantity
Low
$ 2
$ 2
#1
$ 4
$ 4
$ 2
$10
Annual
Unit
Low
High
$ 4
$ 4
$18
$ 6
$ 6
$ 4
$15
O&M Costs:
Cost
High
100 visits
$10
$15
                                        Item Cost
Low
$ 16,666
$ 16,666
$ 99,996
$ 10,000
$ 2,000
$150,000
$ 7,500
High
$ 33,332
$ 33,332
$149,994
$ 15,000
$ 3,000
$300,000
$ 11,250
                                    $302,828    $545,908
                                    	Item Cost
                                    Low          High
$  1,000    $  1,500
                                    $  1,000    $  1,500
     Since the lengths, depths, and widths of passive system trenches vary,
the unit cost per linear foot of landfill border will be totally site-
specific.  The capital costs in Table 6-1 are given in units that can be
readily determined for a given site, with some judgment on the part of the
estimator.
                                     6-13

-------
                                  TABLE 6-1.
    1985 UNIT COSTS FOR COMPONENTS OF PASSIVE LANDFILL GAS CONTROL SYSTEMS

Item
Trench excavation by backhoe
Dispose of excavated material
on site
Crushed stone or gravel
backfill, in place
Bank sand backfill, in place
Horizontal and vertical piping
Synthetic membrane, in place
Monitoring with portable meter
Monitoring probe (drilling, pipe,
fittings, backfill, etc.), in
place
Unit
yd3
yd3

yd3
yd3
Linear ft
'ft2
Each visit
Vertical ft
Cost Per Unit
$2-4
$2-4

$12-18
$6-9
$4-6
$2-4
$10-15
$10-15

Source:  SCS, 1980; SCS, 1985; Godfrey, 1984.
6.2  Active Perimeter Gas Control Systems


     6.2.1  General Description


     Off-site landfill gas migration can also be controlled through the use
of "active" control systems that alter pressure gradients and paths of gas
movement by mechanical means.  These systems normally consist of three or
four major components (SCS, 1980):

     •  Gas extraction wells
     •  Gas collection headers
     •  Vacuum blowers or compressors
                                     6-14

-------
     •  Gas treatment or utilization systems.

     A schematic diagram of an active system is shown in Figure 6-5.
Centrifugal blowers create vacuum through the collection headers and wells to
the wastes and ground surrounding the wells.  A pressure gradient is thereby
established, inducing flow from the landfill (which is normally under positive
pressure) to the blower (creating a negative, or vacuum, pressure).  Sub-
surface gases flow in the direction of decreasing pressure gradient (through
the wells, the header, and the blower) and are released directly to the
atmosphere, treated and released to the atmosphere, or recovered for use as
fuel (SCS, 1980).  Treatment of gaseous waste streams is addressed in Section
10.2.
     6.2.2  Applications/Limitations


     Active perimeter gas control systems can be used at virtually any site
where there is capability to drill an excavation through landfilled material
to the required depth.  Limiting factors could include the presence of
free-standing leachate (i.e., saturation) or impenetrable materials within the
landfill.  Active systems are not sensitive to the freezing or saturation of
surface or cover soils.
     6.2.3  Design Considerations


     Gas extraction wells may be installed either in refuse fill or  in soil
outside of the limit of fill.  The wells in the schematic diagram in Figure
6-5 are shown in the refuse  fill.  Wells normally consist of a drilled
excavation 12 to 36 inches in diameter which is backfilled with one-inch or
larger crushed stone and 2-  to 6-inch piping, which is perforated in the area
where gas is to be collected and solid in the upper portions.  A schematic
detail of a gas extraction well is shown in Figure 6-6.  Solid-wall  pipe is
used and a concrete or clay  seal is provided in the upper portion of the well
to minimize infiltration of  atmospheric air into the system.  A valve is
provided on the lateral connection of each well to allow regulation of flow
and balancing of systems consisting of multiple wells.  A monitoring port is
provided for measuring velocity, pressure, and gas composition.  Wells are
normally drilled to the depth of the seasonally low groundwater table or to
the base of the landfill, whichever is the lesser depth.  However, geologic
conditions and/or landfill characteristics may warrant deeper installations.

     Well spacing is a critical factor in the design of the system and
requires considerable judgment on the part of the designer.  Spacings on the
order of 100 feet are commonly used, however, the appropriate spacing for a
given site will depend upon  the depth of the landfill, the magnitude of the
vacuum applied to the well,  and the rate of gas withdrawal (SCS, 1980).  Where
extraction wells are installed within landfilled material, additional
considerations are the type  of waste (solid, sludge; domestic, industrial;
organic, inorganic), the moisture content of the waste, and the degree of

                                     6-15

-------
                         FIGURE 6-5.
                   ACTIVE GAS EXTRACTION
               PLAN VIEW
                                             BLOWER/BURNER
                                                 FACILITY
                                                      AREA TO BE
                                                      PROTECTED
         GAS
         EXTRACTION
         WELL
GAS COLLECTION
    HEADER
                         SECTION A-A
                                                           PROBE
                                                  (SPACE @ 100'ฑ)
          GAS EXTRACTION WELL
        CONTROL VALVE.
 GAS COLLECTION
     HEADER
        \
GROUNDWATER
BASE OF LANDFILL
                              ' Mt
                              '.NATURAL
                               GROUND^


                             DEPTH
                             VARIES
               MONITORING
                 PROBE
Source: SCS, 1980
                           6-16

-------
                                        FIGURE 6-6.
                                 GAS EXTRACTION WELL
                                         VALVE BOX AND COVER
GAS
COLLECTION
HEADER
          1" PVC MONITORING
          PORT W/CAP
                                             BENTONITE OR
                                             CONCRETE
                                       4" PVC PERFORATED PIPE
Source: SCS, 1980
                                           6-17

-------
compaction of the waste.  Where wells are installed in soil outside of the
landfill, the grain size distribution, moisture content, stratigraphy, and
permeability of the soil should be considered.

     In order to determine appropriate values for design criteria, gas extrac-
tion tests should be performed on one or more test wells while monitoring the
change in pressure gradient radially from the wells.  Parameters that should
be monitored during the tests are:

     •  Gas extraction flow rates

     •  Subsurface negative (vacuum) pressures at various depths and distances
        from the well(s)

     •  Negative pressures within the well.

     The data should be collected under several flow conditions.  Based on the
data, several combinations of flow rates, vacuum pressure applied at the well,
and effective "radius of influence" of the wells can be established.  The
radius of influence is the distance from the gas extraction well beyond which
gases are not induced to flow toward the well and is usually the distance
corresponding to a "cut-off" (close to zero) vacuum pressure.  In design, the
zones of influence of adjacent wells are slightly "overlapped" to establish
the well spacing.  The most cost-effective combination of flow rate, vacuum
pressure, and well spacing is selected for the system design.  This will
depend on cost, whether gas recovery and use are anticipated, and optimization
of gas quality and quantity (SCS, 1980).

     With the basic design criteria having been determined as described above,
appropriate well locations may be established to suit the configuration of the
landfill perimeter.  The header  system is then laid out to convey vacuum  from
a blower (or compressor) to the wells, and thus induce the flow of extracted
gas from the wells to the blower/burner facility.  The configuration of the
header system also depends on the perimeter configuration, and the header pipe
size(s) is determined through standard flow/pressure calculations (SCS, 1980).
Header pipes are sized on the basis of flow rate and permissible pressure loss
in the header line.  Flow equations analogous to those used  for design of air
and water distribution systems can be used to correlate pressure loss with gas
flow rate, pipe length, and pipe material.  Using a commonly employed pipe-
friction-equation, pressure loss is a function of a friction factor, pipe
length, the mean gas velocity, and pipe diameter.  The friction factor is a
function of the relative roughness of the pipe.  Methods of  solution for  the
flow of gas in air conditioning  and heating networks are in  common usage, and
standard texts should be consulted for details (Emcon, 1980).

     The first step in designing a gas collection header is  to estimate gas
flow rates from the individual extraction wells.  Since preliminary flow  rate
estimates may be inaccurate, a factor of safety should be used to adjust  the
flow rate upward (Emcon, 1980).  Cumulative gas flow rates along the header
line are estimated by summing the individual well flow rates "upstream" from
the point under consideration.
                                     6-18

-------
     Once the flow distribution has been estimated for a proposed header
layout, segments of the header pipe can be sized to keep pressure losses
within limits of available motor/blower units.  Alternative header layouts can
be proposed, each requiring different lengths of various sizes of pipe.  Since
the installation cost per foot is less for smaller pipe sizes than it is for
larger sizes, there is a cost trade-off between length and pipe diameter
(Emcon, 1980).

     Header system piping may be buried, installed on the ground surface, or
elevated above the ground.  Factors that influence this decision are climate,
aesthetics, interfering land uses, potential vandalism, and cost (SCS, 1980).

     Extracted landfill gas usually has a high moisture content and, as a
result, the collection of condensate water in the system components must be
considered in the design.  Materials that resist chemical attack should be
used in collection systems because condensate can be highly corrosive.
Condensate water may be effectively drained from the header system by sloping
the piping in the direction of flow, when possible, and considering the "drag"
of the gas flow against the draining condensate when sloping the piping
against the direction of gas flow.  Overflow devices (such as traps) should be
installed at low points in the header to dispose of condensate and avert
blockages of gas flow (SCS, 1980).

     The most common practice for handling condensate water is to return it to
the landfill as it is collected.  However, condensate is potentially a
"hazardous" waste under Federal (RCRA) and some state regulations, regardless
of whether the site of condensate generation is a hazardous waste or a non-
hazardous waste landfill.  Condensate that is ignitable, corrosive, reactive,
or EP toxic (per RCRA) is considered to be a hazardous waste and cannot be
returned to nonhazardous waste or closed hazardous waste landfills.  The
acceptability of returning condensate to the landfill must be considered on a
case-by-case basis.  Alternative practices are pretreatment followed by
discharge to sewerage systems and removal of condensate from the site for
disposal elsewhere, or use as a fuel extender (Paul, 1985).

     The extracted gas flows through the header system to the blower/treatment
facility.  This facility normally consists of a vacuum blower, regulating
valves, safety devices, and a waste gas burner (if required).  A schematic
diagram of a typical blower/treatment facility employing a flare is shown in
Figure 6-7.  The flame arresters and backpressure relief valves are safety
devices that are intended to prevent injury and damage to equipment in the
event of a "flareback" in the system.  The butterfly valves are for regulating
flow and preventing passive gas flow when the system is not in service.  Gas
treatment or destruction is necessary for odor control or to prevent the
discharge of hazardous gas or vapors to the atmosphere.  However, if such
emissions are not of concern, direct venting through a vent stack to the
atmosphere may be acceptable (SCS, 1980).  Treatment of gaseous wastes is
addressed in Section 10-2.

     Extracted landfill gas is occasionally recovered for use as a high or low
btu fuel.  Systems designed solely for gas migration control seldom produce
gases of sufficient quality to warrant recovery.  However, installation of

                                     6-19

-------
                                          FIGURE 6-7.
                           TYPICAL BLOWER/TREATMENT FACILITY
                                                                   VENT STACK
                                                                   (ALTERNATE).
                                                             WASTE GAS.
                                                               BURNER
                                                              OR OTHER
                                                           GAS TREATMENT
     FLAME ARRESTOR
                               BUTTERFLY VALVE
              MONITORING
                 PORT
                W/CAP
BACK-PRESSURE
 RELIEF VALVE.
             ^~^v
           r\
        •GAS COLLECTION HEADER
         FROM EXTRACTION WELLS
Source: SCS, 1980
                                             6-20

-------
combined landfill gas control/recovery systems at  larger  sites  can  be  feasible
where there are nearby potential users of the gas.  The combined  system  is
similar in concept to a gas migration control system.  The major  differences
are that wells would be installed in the interior  of  the  landfill,  and the
design and operating criteria for optimizing gas quality  and  quantity  and
minimizing air infiltration become critical.  The  proximity to  the  landfill of
a user of the gas may limit the  feasibility of methane recovery.  Technical
and economic analyses and control, and recovery systems design should be
performed by professionals experienced in the field (SCS,  1980).

     Active gas control systems  consist of several components,  all  of  which
require different materials and  installation techniques.   Table 6-2 summarizes
the requirements for the major system components.  Specific material selection
is the discretion of the designer; however, the materials  listed  are those
that experience has proven to perform satisfactorily.  The need for corrosion
resistance and flexibility (in anticipation of landfill settlement) are  of
particular importance in selecting materials and designing system components
(SCS, 1980).


     6.2.4  Construction/Implementation Considerations
     In general, all gas extraction wells should be constructed before  any
header pipe is installed.  This is recommended because wells are often
relocated in the field during construction for a variety of reasons, and
realignment of header configurations considering the  final well locations may
be desirable.  Blower/burner facility construction may normally begin at any
time, since its location is dictated by factors of accessibility.  Associated
header alignments may be adjusted to accommodate the  facility  (SCS, 1980).

     The presence of large obstacles in landfills can cause refusal during
well drilling, therefore, high-torque drill rigs should be employed.  The
presence of explosive, ignitable, pressurized, or shock-sensitive materials in
the landfill could cause injury to workers and damage to equipment during
drilling and trench excavation.  Materials that are excavated may be hazardous
and should be treated as such.  As many landfills are known to contain
materials that were prohibited by permit, excavation of landfill materials
must be conducted with caution and an appreciation of potential consequences.

     Care should also be exercised during system installation  to keep flame
sources away from open excavations and connected piping.  Workmen should not
be allowed to work in deep trenches unless the atmosphere is regularly  checked
for oxygen, methane, hydrogen sulfide, and other compounds of concern.  Piping
and other components should be checked for leaks before the system is put into
service to prevent infiltration of air into the system.  All construction and
personal protective equipment must be decontaminated before use.
                                     6-21

-------
                                  TABLE 6-2.
        MATERIALS AND EQUIPMENT FOR ACTIVE LANDFILL GAS CONTROL SYSTEMS
    Item
            Materials
        Installation
Well drilling


Well piping



Well backfill


Header piping
Valves
Vacuum blower
Safety devices
Vent stacks
2 to 6in.   PVC, schedule 40
  to 80, perforated and solid
  wall

1 in. washed crushed stone or
  river gravel

3 in. or greater (depending on
  flow/pressure requirements);
  PVC, polyethylene, or fiber-
  glass (resistant to
  chemical attack)

Compatible with pipe size;
  gate, ball, or butterfly type;
  PVC or other reistant material

Material or coating to resist
  chemical attack; size varies
  with flow/pressure requirements

Specific items manufactured for
  use at refineries, sewage
  digestors, etc.

Any corrosion-resistant pipe of
  adequate size and strength,
  may require support
Gas treatment   Note 2
Auger, caisson, or bucket
  drill rig

Crane for deep wells,
  backhoe for  shallow wells
Place slowly by hand
Conventional trench exca-
  vating equipment,
  specialized jointing
  equipment for some pipe
  materials

Note 1
Note 1
Note 1
Note 1
                                   Note 2
Notes:
1  - No  special  equipment  required
2  - Addressed in  Section  10.2
Source:   SCS, 1980
                                      6-22

-------
     6.2.5  Operation, Maintenance, and Monitoring


     Active gas control systems require testing and adjustment  throughout
their lives of operation.  Initial start-up testing is required  to ensure  that
all components are functioning as intended.  Throttling of  individual well
valves and blower control valves is required to "balance" the system.
Mechanical components require regular service such as lubrication and part
replacement.  In addition, subsurface gas probes in the area being afforded
protection should be monitored at least annually after system start-up  to
ensure that gas migration is being controlled (SCS, 1980).

     Differential settlement of the landfill material beneath header pipes can
cause pipe movements resulting in adverse slopes, accumulation of condensate
in low spots, and partial or complete blockage of gas flow.  Proper pipe
slopes and condensate drains can minimize this problem.  A  regular program of
periodic inspection and maintenance should be established to identify pipe
breakage, condensate blockage, or other header system failure (Emcon, 1980).

     Monitoring of the effectiveness of active gas control  systems is
conducted in the same manner as described in Section 6.1 for passive systems.
Additional monitoring should be conducted during periods of system shutdown or
operating problems.  The interior of the blower/treatment facility should  also
be monitored, as leaks in the system can cause combustible  gas  to accumulate
to dangerous concentrations.


     6.2.6  Technology Selection/Evaluation


     Active perimeter gas control systems are well-established  as the most
effective method of gas migration control, as subsurface gases  are induced to
flow to points of collection and cannot migrate beyond properly  designed and
operated systems.  Because their performance is dependent on mechanical and
electrical components, active systems can be less reliable, although possibly
more effective, than passive systems.  Blower capacity or extraction wells can
readily be added to existing active systems to improve performance.  Shutdown
and other nonperformance alarms can be provided with active systems to  iden-
tify the need for emergency maintenance and thus increase their  reliability.
All active systems require regular operation and maintenance associated with
mechanical systems (motors, bearings, belts, etc.).

     Active systems can be implemented with relatively conventional equipment,
labor, and materials.  Some mechanical equipment may require delivery periods
of several months.  Well drilling is affected with caisson, auger, and  bucket
rigs, and a few systems employing high torque capacity are  needed to excavate
through large obstacles that are present in landfills.  Pipe-laying is  similar
to utility pipeline construction.

     Worker safety is an important consideration where waste materials  are
being excavated.  Personal protective gear must be used and provisions must be
                                     6-23

-------
made for removing excavated waste materials and for decontaminating equipment
No flames or smoking should be allowed in the vicinity of open excavations.

     Active gas control systems require relatively little time to implement.
Several wells can be completed by a single crew in a day (equivalent  to
several hundred feet of perimeter per day), and collection piping and
mechanical components can be installed concurrently.  Gas control can be
affected upon completion and start-up, and immediate results (as measured in
monitoring probes) are realized.
     6.2.7  Costs
     The capital costs of active landfill gas control systems vary greatly,
depending on the size and depth of the landfill, the nature of the waste, and
the selected design criteria.  Table 6-3 shows unit costs  for typical  active
system components.  The large range of unit costs is due to the variable
nature of the system, depending upon the characteristics of the landfill  in
question.  Unit costs for deep extraction wells will be greater than  for
shallower wells, due to the need for more specialized equipment.  Likewise,
large-diameter header pipe is more costly than smaller pipe due to higher
material and labor costs.  Blower/treatment facilities may vary in scale  from
a small blower with a vent stack to multiple, high volume blowers; multiple
and/or high volume burners; and automatic timers, valves,  switches, and
recorders (SCS, 1980).

     Annual operating and maintenance costs also vary with the size of the
system.  For example, a blower driven by a 5-horsepower motor operating
continuously will consume about $2,000 to $3,000 worth of  electricity  at
5 cents/kilowatt-hour.  Other electrical costs for lighting or automatic
controls are nominal in comparison.  The cost of replacement parts should also
be small, since there are few mechanical components in the system.  Small
material costs can be expected for tools, lubrication, replacement of  belts,
fuses, etc.  Manpower costs, assuming an average of two or three man-days per
month on a contract basis, should be on the order of $5,000 annually;  the
costs will vary with the scale and sophistication of the system.  Other annual
costs that may be considered are insurance, security, interest, and
administration or overhead (SCS, 1980).

     Costs associated with treatment of collected gases will also contribute
to the total cost of gas control.  Treatment of gaseous waste streams  is
addressed in Section 10.2.
                                     6-24

-------
                                  TABLE 6-3.
               1985 UNIT COSTS FOR COMPONENTS OF ACTIVE LANDFILL
                      GAS CONTROL AND COLLECTION SYSTEMS
               Item
    Unit
Cost Per Unit
Gas extraction well (drilling,
  stone, piping, etc.), in place

Well connection lateral (10 ft.
  piping, valve, excavation fittings,
  etc . ) , in place

Gas collection header (piping
  excavation, fittings, etc.),
  in place

Blower  facility (blower(s),
  safety devices, valves,
  foundation, piping, fencing
  electrical components, and
  service connection), in place

Monitoring probe (drilling,
  pipe, fittings, backfill,
  etc.) , in place

Operation and maintenance

Monitoring with portable meter
Vertical ft,
Each
Linear ft.
Lump sum
Vertical ft



Year

Each visit
   $50-75


$1,000-1,500



   $20-100



$50,000-100,000
   $10-15



 $5,000-20,000

   $10-15
Source:  Flood, F. SCS Engineers, Reston, VA, personal communication,
         March 1985.
                                     6-25

-------
6.3  Active Interior Gas Collection/Recovery Systems


     6.3.1  General Description
     Gases generated at landfill sites and vented to the atmosphere frequently
contain malodorous and/or toxic compounds.  Malodors are most commonly
associated with trace concentrations of natural organic and sulfurous gases.
Toxic compounds may be present as a result of volatilization of man-made
organic compounds that are part of the landfilled waste material.

     The following is an example of an estimate of the costs of any active
perimeter gas migration control system:

Scenario:

     •  Closed landfill containing primarily domestic refuse; free liquid
        organic wastes are mixed with solid waste.

     •  Average landfill depth is 40 feet.

     •  Landfill perimeter is 2,300 feet.

     •  Continuous low-permeability clay exists at depths of 25 feet and
        underlies the bottom of the landfill.

Required:

     Estimate the capital and O&M costs of an active perimeter gas migration
control system.

Assumptions:

     •  Extraction wells will be installed in landfilled material and will  be
        30 feet deep.

     •  The  line of wells will be inset  from the  edge of the landfill and will
        be 2,100 feet  long (parallel with and inside of the landfill edge).

     •  Wells will be  spaced at 50 feet.

     •  Monitoring probes will be spaced  at  100 feet, will be 30 feet deep,
        and  will be along a line 2,500 feet  long  (parallel with  and  inside  of
        the  landfill edge).

     •  Probes will be monitored quarterly with a portable meter.

Estimates of Quantities:

     •  Gas  extraction well:  2,100' -r 100'  x 30' =  630 vertical  feet


                                     6-26

-------
     •  Well connection lateral:  2,100' 4- 100' = 21 laterals

     •  Gas collection header:  2,100 linear feet

     •  Blower facility:  1 facility

     •  Monitoring probes:  2,500" * 100' x 30' = 750 vertical feet

     •  Monitoring:  2,500' -5- 100" x 4 visits/year = 100 visits/year

Estimate of Capital Costs:
                                        Unit Cost
     Item
Quantity
   Low
                                      Item Cost
Gas extraction well   630 v.f.
Well connection
  lateral
Gas collection
  header
              $    50

21 laterals   $ 1,000

2,100 l.f.    $    40
Blower facility
Monitoring probes

Total Capital Costs
1 facility
750 v.f.
  avg.*
$50,000
$    10
High       Low      High

$    75   $31,500   $ 47,250

$ 1,000   $21,000   $ 31,500

$    60  $ 84,000   $126,000
  avg.*
$75,000  $ 50,000   $ 75,000
$    15  $  7,500     11,250
                        Estimate of Annual O&M Costs:
                                        Unit Cost
                                   $194,000   $291,000
                                      Item Cost
     Item

Operation and
  maintenance
Monitoring with
  portable meter

Total annual
  O&M Costs
Quantity
   Low
High
Low
High
1 lump sum    $ 5,000**   $10,000** $  5,000  $ 10,000

100 visits    $    10     $    15   $ 1,000    $ 1,500
                                    $ 6,000   $ 11,500
**Control system is comparatively small; O&M costs on low end of range in
  Table 6-3.
     Gases generated in landfills will ultimately vent to the atmosphere,
either vertically through the cover material, laterally through surrounding
soil outside of the landfill limit and then vertically through paths of low
resistance to flow, or through perimeter (active or passive) control systems.
Gases that vent from landfills are generally not detected and presumably do
not significantly degrade local air quality because of dilution in the
atmosphere.  However, emissions from some landfills do measurably degrade air
quality, and experience with landfill-generated methane recovery and
utilization systems has shown that landfill gas collection generally affords
                                     6-27

-------
a net improvement in local air quality.  Installation of several  landfill  gas
collection systems has been justified, at least in part, by a recognized need
to reduce emissions from the landfills (Johns Hopkins University,  1980).

     Where the venting of landfill gas poses a health or environmental
problem, systems designed specifically for the collection of gases beneath
the landfill surface (before venting occurs) can be  installed.  Such  systems
are similar to perimeter active control systems in their basic  concept  of
operation; however, gas extraction wells and corresponding collection headers
are placed over the entire landfill surface as shown in Figure  6-8.   Interior
gas collection/recovery systems are intended to capture as much as possible
to prevent hazardous gases from being emitted to the atmosphere.   Collected
gases are conveyed to a central point for treatment or destruction (see
Section 10.2) or for processing and recovery.  Over 50 systems  that recover
landfilled-generated methane for a variety of beneficial uses are  in
operation or are under development in the United States, Europe,  and  Canada
(Waste Age, 1984).  Emcon (1980, 1981) provides additional information
specific to recovery and utilization of landfill-generated methane gas.


     6.3.2  Applications/Limitations


     Active interior gas collection/recovery systems are applicable to  land-
fill sites where gaseous emissions through the surface are to be  controlled.
This method can be used to supplement landfill capping (see Section 3.1) and
to prevent resulting lateral gas migration.  They can be used at virtually
any site where it is possible to drill or excavate through landfilled
material to the required depth.  Limiting factors could include the presence
of free-standing leachate (i.e., saturation) or impenetrable materials  within
the landfill.
     6.3.3  Design Considerations


     The design of landfill gas  collection  systems  requires  consideration of
the same basic criteria  as described under  active gas  control  systems  (see
Section 6.2).  Major variations  are described  herein.

     The depths of gas extraction wells  used  for gas  collection generally do
not need to extend to the bottom of the  landfill; typical  depths range from
50 to 90 percent of the  landfill depth at the  well  location.   In addition,
the presence of free-standing  liquid waste  or  leachate within  the landfill
can limit the practical  depth  of well  installation.

     Well spacing is determined  in a manner similar to that  described  in
Section 6.2.  Spacing of extraction wells is  generally greater because
greater interior depths  allow  higher applied  vacuum levels and larger  "radii
of influence".  Well spacings  of 200 feet are  common  for gas collection. The
well system is laid out  to cover the landfill  surface  in configurations that
allow complete coverage  with the minimum number of  wells,  ideally in an

                                     6-28

-------
                                 FIGURE 6-8.

                     GAS COLLECTION/RECOVERY SYSTEM
                                            TREATMENT/

                                          PROCESSING

                                            FACILITY
                                            Si*
                                                  LANDFILL LIMIT
  REFUSE FILL
Source: Emcon, 1981
                                    6-29

-------
equilateral triangular pattern.  The geometry of the landfill surface
generally precludes the ideal well layout, requiring compromises and
approximations (Emcon, 1980).

     The design of the gas collection header system is more complex for
collection systems because of the network of branches required to reach all
extraction wells.  However, the same basic procedure of flow/pressure
calculations is followed.
     6.3.4  Construction/Implementation Considerations
     The considerations discussed in Section 6.2 for the construction and
implementation of active perimeter gas control systems installed within
landfilled material also apply to active interior gas collection/recovery
systems.


     6.3.5  Operation, Maintenance, and Monitoring


     Active interior gas collection/recovery systems require essentially the
same operation and maintenance as active perimeter gas control systems.  The
major difference is a matter of scale; collection/recovery systems generally
have more wells, piping, associated gas flow, and condensate water.  The
relative complexity of the piping network requires frequent measurements to
balance gas flow and pressure among the extraction wells.

     Monitoring the effectiveness of interior gas collection/recovery systems
differs substantially from monitoring perimeter systems because the problems
relieved by the systems differ.  Measurement of air contaminants, upwind,
directly above, and downwind of the site is ,required to determine the
effectiveness of such systems.  Air quality monitoring is not addressed
herein.
     6.3.6  Technology Selection/Evaluation


     Active interior gas collection captures gases before they can vent  from
a landfill and thus is the only method of limiting gaseous emissions  from
landfills.  The technology has been shown to improve local air quality (where
the gas is subsequently treated or recovered), regardless of whether  air
quality was the primary concern.  Because the method relies on mechanical
components, however, shutdown alarms and regular maintenance and monitoring
should be provided to affect maximum system reliability.  Blower capacity or
extraction wells can readily be added to existing active systems to improve
performance.  All active systems require regular operation and maintenance
associated with mechanical systems (motors, bearings, belts, etc.).
                                     6-30

-------
     Active systems can be implemented with relatively conventional
equipment, labor, and materials.  Some mechanical equipment may require
delivery periods of several months.  Well drilling is accomplished with
caisson, auger, and bucket rigs, and a few systems employing high torque
capacity are needed to excavate through large obstacles present in landfills,
Pipe laying is similar to utility pipeline construction.

     Worker safety is an important consideration where waste materials are
being excavated.  Personal protective gear must be used and provisions must
be made for removing excavated waste materials and for decontaminating
equipment. No flames or smoking should be allowed in the vicinity of open
excavations.
     6.3.7  Costs
     Unit costs of active interior landfill gas collection systems are
comparable to those of active control systems (see Table 6-3).  Overall costs
are generally higher for collection systems because of the larger number and
depth of wells and larger diameter and length of header pipe needed to
collect gas from the entire landfill, rather than only along the perimeter.

     Costs associated with treatment of collected gases will also contribute
to the total cost of gas control.  Treatment of gaseous waste streams is
addressed in Section 10.2.

     Costs of active interior landfill gas collection systems are estimated
in a manner similar to costs of active perimeter gas migration control
systems.  For the example scenario presented in Section 6.2.7, the number of
wells would be estimated in accordance with the assumed spacing; (e.g.,
200-foot triangular pattern, one well per acre, etc.), and the length of
header pipe would be estimated accordingly.  A larger and more costly blower
facility would be required to handle higher rates of gas flow.  Also, if gas
migration control were not part of the performance requirement, monitoring
probes would not be installed.
                                     6-31

-------
                                  REFERENCES
Eracon Associates.  1980.  Methane Generation and Recovery from Landfills.   Ann
Arbor Science Publishers, Inc.  Ann Arbor, MI.

Emcon Associates and Gas Recovery Systems, Inc.  1981.   Landfill Gas - An
Analysis of Options.  Emcon Associates, San Jose, CA.

Godfrey, R.S.  1984.  Means Site Work Cost Data 1985.   Robert Snow Means
Company, Inc., Kingston, MA.

Paul, M. P.  1985.   Things You Might Not Know About Landfill Gas Condensate
Disposal.  Waste Age.  Vol. 16, No. 2.  pp. 64, 66.

SCS Engineers.  1980.  Draft Manual for Closing and Upgrading Open Dumps
(unpublished).  Prepared for:  USEPA, Office of Solid Waste, Washington, DC.

The Johns Hopkins University Applied Physics Laboratory.  Revised April 1980.
Landfill Methane Utilization Technology Workbook.  Publication No. CPE-7909.
115 pp.

Waste Age.  November 1984.  Preliminary Landfill Gas Update,  p. 120.
                                     6-32

-------
                                    SECTION  7

               ON-SITE AND OFF-SITE DISPOSAL  OF WASTES  AND  SOIL
     This section discusses excavation  and  removal  and  on-site  and  off-site
land disposal of hazardous wastes  and contaminated  soil.   Excavation,  removal,
and hauling of wastes and soil  at  hazardous waste sites are  generally
accomplished with conventional  heavy construction equipment.  This  equipment
is also commonly used for construction  of land  disposal facilities.  Section
7.1 discusses the equipment used for excavating, lifting,  loading,  hauling,
dumping, and grading on-site  soil  and waste material.   Section  7.2  provides a
brief overview of off-site waste disposal.  Section 7.3 gives general  guidance
for the design and construction of on-site  disposal and storage facilities to
comply with RCRA standards.


7.1  Excavation and Removal
     This section describes conventional equipment  and  the methods  applicable
for excavation and removal of contaminated soils, sludges, and  liquids.


     7.1.1  General Description
     As noted in Section 7.1.3, the major types of excavation  and  removal  are
casting and loading excavation and hauling excavation  (including the use of
pumping systems).  The equipment described in this section may be  used  for
constructing an on-site disposal facility as well as for excavation and
removal of contaminated materials.  A more detailed description of excavation
equipment can be found in Church (1981).


     7.1.2  Applications/Limitations


     Excavation and removal followed by land disposal  or treatment are  per-
formed extensively in hazardous waste site remediation.  There are no absolute
limitations on the types of waste which can be excavated and removed.
However, worker health and safety weighs heavily in the decision to excavate
explosive, reactive, or highly toxic waste material.   Other factors which  are
considered include the mobility of the wastes, the feasibility of  on-site


                                     7-1

-------
containment or in-situ treatment, and the cost of disposing the waste or
rendering it non-hazardous once it has been excavated.  A  frequent practice  at
hazardous waste sites is to excavate and remove contaminant "hot spots" and  to
use other remedial measures for less contaminated soils.

     Excavation and removal is applicable to almost all site conditions,
although it may become cost-prohibitive at great depths or in complex
hydrogeologic environments.

     Each of the equipment types discussed in Section 7.1.3 have specific
applications and limitations which must be carefully evaluated.


     7.1.3  Excavation Equipment


          7.1.3.1  Loading and Casting Excavation


     Loading and casting can be accomplished by a wide variety of conventional
equipment ranging in size from a 220 cubic yard dragline down to the 1/4 cubic
yard backhoe (Church, 1981).  These basic types of excavation machinery fall
into the following general categories:

     •  Backhoes

     •  Cranes and attachments (draglines and clamshells)

     •  Dozers and loaders.

It should be noted that these are not the only excavators  used for loading and
casting.  Other types of loading and casting equipment include trenchers, belt
loaders, and wheel bucket excavators (Church, 1981).  This equipment is not
discussed in this section because it has very limited use  in excavation at a
hazardous waste site.
               a.  Backhoes
     The backhoe unit is a boom or dipper  stick with a hoe dipper  attached
to the outer end.  Figure 7-1 illustrates  the components of  the backhoe.  The
unit is generally a crawler-mounted, hydraulically operated  vehicle with
various sized-toothed buckets ("dippers")  attached to the boom, and dipper-arm
assemblies of varying lengths.  Backhoes are generally used  for trenching and
subsurface excavation where it is expedient to keep the excavator  at  the
original ground level (Church, 1981).  However, where it is  necessary for the
backhoe to excavate beyond the maximum depth of the boom and dipper assembly,
a "working bench" can be excavated for the backhoe next to the trench so that
the vehicle can excavate to the desired depth.  The backhoe  unit can  also be
adapted with various attachments such as grapples for drum excavation work.
                                     7-2

-------
 Ill
 _l
 o
 x
 *


 I
0.
w
oc

D

(9
                                                                                           Q.

                                                                                           UJ
                                                 7-3

-------
     The digging dimensions of a backhoe are  shown  in  Figure  7-2.   The maximum
reach and depth for various sized hoes  is  shown  in  Table  7-1.  As  shown  in
this figure, the largest backhoe will dig  to  a maximum depth  of  about 30 feet.
Deeper digging depths (up to 80 feet) can  also be achieved by using backhoes
with extended dipper sticks, modified engines, and  counterweight  frames.

     Smaller backhoes with rubber tires are useful  for fast excavation on
stable working surfaces.  One frequently used smaller  backhoe is  a wheel-
mounted combination backhoe and front-end  loader.   This vehicle  can excavate,
lift, load, haul, and dump soil and waste  materials (including both crushed
and undamaged drums).  Its operation, however, is generally restricted to
relatively flat and stable working surfaces.

     Theoretical Production Rate—The hourly production in cubic yards bank
measurement (cy bra)per 50 minute working  hour for  a backhoe  and dragline can
be expressed by the equation (Church, 1981):


             P = — x BF x BC
                 CT

     where:   P = hourly production (cy bm)
             CT = cycle time (rain)
             BF = bucket factor
             BC = bucket capacity.

     The cycle time varies according to length of hoist and angle  of swing
return.   For a backhoe having a hoist length of  10  feet and swing  angles  of 30
and 180 degrees, the cycle times are 0.37  and 0.52 minutes, respectively.
Similarly,  a backhoe with a hoist of 60 feet and swing angles of 30 and  180
degrees has cycle times of 1.20 and 1.35 minutes respectively (Church, 1981).

                                  TABLE 7-1.
                MAXIMUM REACH AND DEPTH FOR VARIOUS SIZED HOES
                        (MAXIMUM DIGGING ANGLE OF 45ฐ)
                               Maximum reach       Maximum depth
            Hoe size              of boom          of excavation
             (yd3)                 (ft)                 (ft)
              1                     35                   22
              1-1/2                 42                   25
              2                     49                   30
              3-1/2                 70                   45
           Source:  USEPA, 1978

                                     7-4

-------
                            FIGURE 7-2.
                      HOE DIGGING RANGES
FIGURE 7-1  Source: Stubbs, 1959
                               7-5

-------
The bucket factor varies according to the nature of rock-earth.  For calcula-
tion purposes, an average bucket factor of 0.66 will be assumed (Church,    _
1981).  An estimate for the hourly production of a backhoe having a 1-1/2 yd
bucket and a 40 foot hoist with a 180 degree swing angle can thus be shown to
be:

             _.   50 cy bm    n ,,   , c   ,3
             p =	1	  x 0.66 x 1.5 yd
                 1.02 min

               = 49 cy bm/hr.              V -

     Costs—The total 1985 unit cost for a backhoe including labor, equipment,
and overhead.and profit varies from $1.64 to $2.44 for bucket capacities of
3.5 and-1 yd , respectively (Godfrey, 1984).  The daily output index is
1200 yd  and 360 yd , respectively.  This means that the total daily cost for
backhoe utilizing a 3.5 yd  bucket is approximately $1970.
               b.  Cranes and Attachments
     The crane equipped with a clamshell or orange-peel bucket is rarely used
for loading or casting excavation in the sense of high production.  Its uses
are in subaqueous excavation and in the rehandling of materials.  For
instance, cable-operated cranes fitted with the clamshell buckets, drum
grapples, magnets, hoists, slings, and lifters are ideal for large-scale drum
excavation, lifting, and staging at sites with unrestricted working space.

     Cranes can also be adapted for use as dragline excavators for deeper
excavations over large areas.  A dragline excavator is a crane unit with a
drag bucket connected by cable to the boom.  A dragline is illustrated in
Figure 7-3.  The bucket is filled by scraping it along the top layer of soil
toward the machine by a drag cable.  The dragline can operate below and beyond
the end of the boom.

     Maximum digging depth of a dragline is approximately equal to half the
length of the boom, while digging reach is slightly greater than.the length of
the boom (USEPA, 1978).  Drag buckets can vary in size from 1 yd  to 20 yd  ,
with boom lengths ranging from 30 to 240 feet (Church, 1981).  Various working
dimensions of draglines for various bucket sizes are shown in Table 7-2.

     Draglines are very suitable for excavating large land areas with loosely
compacted soil.  Excavation with draglines of landfill sites containing
explosive materials or very toxic chemicals is unsafe.

     Theoretical Production Rate—The hourly production rate for a dragline
excavator is calculated in the same way as for the backhoe.  The production
rate based on a 50 minute working hour can range from 160 cy bm (for bucket
capacity of 1 yd  , swing-return angle of 30 degrees, and a hoist of 10 feet)
to 510 cy bm (for hoist length of 200 ft, swing-return angle of 180 degrees
                                     7-6

-------
                      FIGURE 7-3.
                     A DRAGLINE
Source: EPA, 1978
                         7-7

-------
                                   TABLE 7-2

                     TYPICAL DRAGLINE EXCAVATOR DIMENSION
                                           Bucket size in cubic yards  (CY)
Item
Dumping radius, ft
Dumping height , ft
Maximum digging depth, ft
Digging reach, ft
Boom length, ft
Bucket length, ft
3/4
30
17
12
40
35<
11.5
1
35
17
16
45
40
14.67
1-1/4
36
17
19
46
40
11.83
1-3/4
45
25
24
57
50
13.08
2
53
28
30
68
60
14

Note that these values apply to operation of the excavator with  its boom  at  a
 40ฐ angle to the horizon.

Source:  EPA, 1978
and a bucket capacity of 20 yd ),  The hourly production rates obtained  assume
that the ground is average weathered rock-earth (Church, 1981).
     Costs—The total 1985 cost for labor and equipment (including overhead
and profit) for a. dragline with a 3/4 yd  bucket capacity was $3.00/yd   at a
production rate of 35 cubic yards per hour.  Cost for a dragline with a  bucket
capacity_of 3 yd  with a production rate of 112 cubic yards per hour is
$l-46/yd  (Godfrey, 1984).  The output index for the 3 yd  bucket is 900
yd /day, leading to a total cost of $1300/day.
               c.  Dozers and Loaders
     Dozers and loaders are generally equipped with a hydraulically controlled
(versus mechanical cable hoist) blade and bucket lift and can be either
crawler- or rubber-tire-mounted.  Crawler machines are equipped with  self-
laying steel tracks of variable cleat design and width, which provide good
ground contact and excellent flotation and traction capabilities.  For this
reason, crawlers are ideally suited for excavating over rough, unstable
surfaces.  In marshy or swampy areas where mobility is limited, extra wide
tracks are recommended to improve traction.
                                     7-8

-------
     Dozers and  loaders  are  also  available  with  large  rubber-tired  wheels that
are  faster and more mobile than crawler machines  on  level  terrain.   Their
ability to maneuver on rough, muddy,  and  sloping  terrain,  however,  depends
somewhat on the  type of  tires.  For example,  tires with  a  wide  base and  low
air  pressure provide good flotation and traction  (Church,  1981).

     Crawler dozers equipped with blades  of various  sizes  and  shapes (straight
to U-shaped) have tremendous earth-moving power  and  are  excellent graders.  In
drum excavation  work, these  dozers can remove miscellaneous  fill or soil
overburden, or they can  push earth and undamaged  or  empty  drums from unstable
surface areas to more accessible  areas for  lifting and loading  operations.
The dozers are usually used  in combination  with other  excavation equipment
such as backhoes.

     Front-end loaders are tractors equipped  with buckets  for digging,
lifting, hauling, and dumping materials.  Both crawler-mounted  and  rubber-
tired front-end  loaders  are widely used in  hauling and staging  undamaged
drums.  Because  lifting  and  loading drums onto front-end loaders usually
requires manual  assistance,  their use should  be limited  to structurally  sound
drums .

     The crawler loader  is an excellent excavator that can carry materials as
far as 300 feet  (Brunner and Keller,  1972).   Front-end buckets  vary in
capacity and design.  Medium-sized crawler  loaders typically have maximum
bucket capacities of 5 to 6 cubic yards.  Wheel-mounted bucket  loaders,  for
high-production  operations on stable  surfaces such as  paved  areas,  have  bucket
capacities up to 20 cubic yards.

     Theoretical Production Rate—The hourly  production  rate can be calculated
in the same manner as the backhoe and the dragline.  A medium sized crawler
loader having a  bucket capacity of 5  cubic  yards, with an  average cycle  time
of 50 minutes for a working hour, and a bucket factor of 0.66,  would have a
production rate  of 330 cubic yards bank measurement  per  hour.

     Cost—A wheel mounted bucket loader  having a bucket capacity of 5 cubic
yards has a total 1985 unit cost  of $0.84/yd  (Godfrey,  1984).  The daily
output would be  1,480 cubic yards, and, therefore, the total costs  for labor,
equipment, and overhead  and profit would  be $1240/day.


          7.1.3.2  Hauling Excavation


     Hauling excavation  is used for on-site and off-site transport  of wastes.
The hauling equipment discussed in this subsection includes  scrapers  and
haulers.  Dredges are also used for hauling excavation and are  discussed in
Section 8.   Dozers and loaders discussed  in the previous section can  also be
used for hauling.
                                     7-9

-------
               a.  Scrapers
     Wheel-mounted scrapers are generally used  in excavation work  to remove
and haul surface cover material at large disposal sites.  However, they  are
not suitable where drums are buried near the  surface.  They are  also useful  in
respreading and compacting cover soils.

     Scrapers are available as both self-propelled,  self-loading vehicles, and
as models that are push-loaded by crawler tractors.  Soft- to medium-density
cover soils and fill favor the self-loading scraper; medium to hard rock and
earth favor the use of the push-loaded machine.  The hauling capacities  of
scrapers range from 2 to 40 cubic yards.  These earth moving machines  can haul
cover material economically over relatively long distances—more than
1,000 feet for self-propelled scrapers (Church, 1981).

     Costs—Total 1985 unit costs including labor, equipment, overhead and
profit vary from $2.11/cubic yard to $3.98/cubic yard for self-propelled
scrapers (15 yd  capacity, 1/4 dozer, 1500 foot haul) and towed  scrapers
(10 yd  capacity, 1/4 push dozer, 5000 foot haull, respectively  (Godfrey,
1984).  The corresponding daily output is 800 yd  and 440 yd , respectively,
leading to total daily costs of $1670/day and $1750/day.
               b.  Haulers
     A variety of haul trucks are available for transporting excavated
materials and waste drums, both off-the-road and on-the-road.  Haulers are
large, rubber-tired vehicles available as single-trailer, 2- or 3-axle
vehicles, and as double-trailer, multiple-axle haulers.  Their rated haul
capacities range from 1 to 100 tons, and they are available as bottom-dump,
rear-dump, and side-dump vehicles.  Small, 1 to 2 ton haul trucks are used
most commonly in drum transport operations.

     At hazardous waste disposal  sites, haul trucks are most useful  for
hauling excavated soils and drums (damaged or undamaged) to off-site secure
landfills or selected drum reburial sites.  Soil can be loaded onto haulers
using backhoes, draglines, shovels, and loaders.  Drums can be loaded onto and
removed from haulers using backhoes, cranes, and forklift trucks, usually with
manual assistance from field workers.  Barrel grapplers, however, can usually
perform this task without manual  assistance.

     Costs—Total 1985 unit costs for dump trucks vary according  to  capacity
of truck and the distance of hauling, which decreases the daily output.  For
instance, the costs for a 6 yd  dump truck, hauling 1/4 mile round trip, has a
daily output of 240 yd  and a total unit cost of $1.787 yd .  The  same truck
hauling 4 mile round trip has a daily output of 85 yd  and a total unit  cost
of $5.05/yd  .  A 12 yd  dump truck hauling 1/4 mile has a daily output of  356
yd  and a total unit cost of $1.38/yd  .  The same truck hauling 20 mile  round
trip has a daily output of 32 yd  and a total unit cost of $15.40 yd
(Godfrey, 1984).

                                     7-10

-------
          7.1.3.3  Pumps


               a.  General Description


     Pumping is required in order to remove liquids and sludges  from ponds,
waste lagoons, and surface impoundments.  Liquid wastes pumped from these
sites must be managed so as to prevent degradation of the surrounding
environment.  The liquid wastes may be pumped to a treatment system or a tank
truck for transport off-site to a commercially operated treatment facility.
The following section discusses types of pumps available, factors affecting
selection, and costs of temporary pumping systems to be used for remedial
action.

     Pump Types—Pump types may be divided into two major categories:
(l) dynamic, in which energy is continuously added to increase the fluid
velocity; and (2) displacement, in which energy is added periodically
(Karassik et al., 1976).  Dynamic pumps may be further subdivided into several
varieties of centrifuge pumps while displacement pumps can be subdivided into
reciprocating and displacement or rotary pumps.

     Centrifugal Pumps—Dynamic centrifugal pumps have a wide range of
capacities; flow rates range from 2 or 3 gpm up to 10,000 gpm (Perry and
Chilton, 1973).  The primary advantages are low initial cost and a simple
design, which in turn means low maintenance and easy repair.  These pumps are
best suited for pumping large volumes against small heads (Cole-Partner, 1982).
They can handle liquid with large amounts of solids.  Centrifugal pumps are
limited in that they are not self-priming, and therefore liquid must be added
to the pump in order to start up the pumping action (i.e., they  cannot pump
dry).

     Some pumps are coated with special engineering plastics such as PVC, PVDF
(Kyner) or polypropylene to handle corrosives, caustics, dyes, brines,
halogenated materials slurries, and other wet substances.  These plastics are
compatible with most chemicals.

     Criteria for selecting centrifugal pumps include waste composition,
chemical compatabilities, service and operating conditions such  as flow rate
and discharge head, temperature range, and power requirements, and nature of
the solids such as abrasiveness and viscosity.

     Reciprocating Pumps—Diaphram, bellow and piston pumps are  subcategories
of reciprocating pumps.  Reciprocating pumps displace a precise volume of
liquid with each movement of an inlet suction and outlet discharge cycle.
Reciprocating pumps have the advantage of being able to deliver  fluids against
high pressures and operate with high efficiencies over a wide range of
operating conditions.  The capability of achieving high pressures at low
velocities is important when pumping abrasive slurries or other high viscosity
fluids.
                                     7-11

-------
     Diaphram pumps pulse a flexible membrane to displace the liquid with each
stroke.  The pump is usually driven by an outside source which may be at a
constant or variable speed and it may be driven mechanically or hydraulically.
These pumps can be used for product pressures up to 150 psi.

     Applications of diaphram pumps are more numerous than centrifugal pumps.
Because they have no seals, they can handle fluid mixtures with a higher
percentage of solids, such as mud, silt and sludge.  The leakfree nature of
this pump frequently causes it to be selected to prevent cross-contamination
when the fluid to be pumped is abrasive or corrosive (Perry and Chilton, 1973,
Karassik, 1976).

     Bellow pumps operate by moving a bellow back and forth to displace the
liquid.  These pumps can be used to produce pressures of up to 50 psi.
Applications of bellow pumps are more restricted than diaphram pumps, but
because these pumps have no seals and special nonclogging valves are available
for them, abrasive or particulate mixtures can be pumped (Perry and Chilton,
1973).

     Piston pumps use a reciprocating plunger to draw in and force out fluids.
 These pumps are used where pressures of 600 to 10,000 psi are needed.

     Piston pumps are not recommended for use with abrasive fluids because
these pumps require a packing seal to prevent leaks.  Since in some piston
pumps, the piston and cylinder are open to the fluid being pumped, they are
not recommended for use with corrosive chemicals.  Piston pumps have the
desirable characteristic of maintaining high volumetric efficiency at any
desired flow rate (Karassik et al., 1976).  Volumetric efficiency is the ratio
of liquid actually pumped to that which theoretically should be moved, based
on piston displacement (Perry and Chilton, 1973).

     Reciprocating pumps have the advantages of being able to pump sludges.
Additionally, total costs including initial, power, and maintenance are lower
than comparable pumps.  Another advantage is that when compared to centrifugal
and displacement pumps, the reciprocating pumps have been determined to be the
least sensitive to changes in capacity when the discharge pressure varies.
One reason for this is because leakage past the plunger seals and check valves
is comparatively small.  Another reason to use reciprocating pumps is the ease
with which the capacity can be accurately adjusted with the aid of a metering
device (Henshaw, 1981).

     Disadvantages of reciprocating pumps include pulsating flow.  This may
cause a problem when the fluid to be pumped needs to be steadily entrained.
Pulse dampeners are on the market to reduce this pulsation by 90 percent.  For
most applications initial and maintenance costs will be greater than
centrifugal pumps, but total costs will be less, as described previously.
Most problems with reciprocating pumps can be avoided by selecting pumps
appropriate for the particular job (Perry and Chilton, 1973; Karassik, 1976).
                                     7-12

-------
     Selection considerations for choosing a reciprocating pump are:  intake
and discharge pressures, metering capabilities, properties of the liquid to be
pumped (abrasive, corrosive, pH, etc.), temperature, type of flow, power,
maintenance, amount of cleaning needed, and cost.

     Displacement Pumps—The third type of pumps are the positive displacement
pumps, which consist of gear, flexible impeller and flying vane pumps.  These
types of pumps move a fixed volume of liquid from the inlet to the outlet by
the pass of gear teeth or impeller blades.

     Gear pumps consist of two meshed spur gears in a circular housing.  As
gears mesh and rotate, the fluid is forced out of the spaces between the
teeth. Gear pumps produce a virtually pulseless, low shear flow, even against
moderately high heads; and they require no check valves.  These pump can be
used to produce pressures up to 100 psi.

     Because of the close running of gears, gear pumps are not suitable for
abrasive substances.  Applications do include a wide range of fluids,
including some corrosive chemicals.

     Flexible impeller pumps are versatile and efficient.  A flexible, vaned
membrane, usually made of rubber, rotates in an eccentric housing to draw the
liquid in and force it out.  The volumes of the spaces change! as the impeller
rotates.  Different grades of impellers are compatible with fluids with
pressures up to 30 psi.  Flexible impeller pumps cannot handle abrasives but
will pump various liquids.  Flexible impeller pumps combine general features
of gear and centrifugal pumps.  They are almost as efficient, require no check
valves and are self priming.

     Flying vane pumps use movable vanes in place of flexible impellers.
Flying vane pumps also combine the general features of gear and centrifugal
pumps.  They are almost as efficient, are self priming and require no check
valves.  These pumps have low maintenance costs.

     Positive displacement pumps are designed with close tolerances between
the pump house and the impellers so the liquid being pumped cannot leak back
around the impeller.  For this reason, these pumps can develop pressure
differences of up to 100 psi in gear pumps and slightly less for other
displacment pumps. This close tolerance utilizes the liquid being pumped to
self prime the pump and lubricate the impellers, so this type of pump should
not be run dry.

     Applications of displacement pumps are varied.  Generally, these pumps
are not to be used with abrasives.

     Selection considerations for choosing a displacement pump are:  required
flow, intake pressure, exit pressure, properties of the liquid, temperature,
power intake, maintenance requirements, cost, and ease of cleaning.
                                     7-13

-------
     Immersion Pumps—Immersion pumps are designed so that  the inlet port is
immersed in liquid but the motor and electrical components  remain dry.   This
type of pump is virtually maintenance free and for the most part no metal
contacts the pumped liquid so corrosives can be pumped.  Parts of this  pump
can be constructed of materials suitable to the liquid being pumped so  that
they are applicable for use with hard to handle chemicals such as sulfuric
acid, sodium hydroxide and ferric chloride.  These pumps are self priming and
can pump liquids of temperatures up to 260ฐ.

     Submersible Pumps—Submersible pumps operate only when totally submersed
in the fluid which is being pumped.  They contain liquid-proof electrical
connections and use a motor which is cooled by the liquid.   These pumps are
economical and energy efficient.  Applications include industrial process
wastewater, flood water and most clean or dirty waters.  Some submersible
pumps are built to pump mildly corrosive solutions and kerosene based
solutions.  Certain types of submersible pumps can work in  as little as 3/16
inches of liquid and some can pump semi-solids of appreciable size.  Costs for
submersible pumps are moderate and-depend on pumping needs.

     Selection considerations for submersible pumps include required flow,
properties of the liquid, power capabilities, temperature,  ease of cleaning
and maintenance, and costs.
               b.  Pump Selection


     In selecting a pump, care must be taken to ensure reliable operation and
control.  Pump selection generally depends on the pumping capacity required
and the materials to be pumped.  The experience of pump manufacturers is often
valuable in selecting the proper size and type of pump and motor.

     When dealing with hazardous wastes, the task of pump selection is
complicated by the presence of chemicals that could corrode or dissolve pump
parts.  Corrosive liquids having a low pH or a high chloride ion content can
rapidly destroy most metal pumps.  Wetted parts should be plastic, rubber, or
ceramic, or, if made of iron, should be alloyed with silicon and/or chromium
(Beck, 1984).  It is extremely important to check the chemical compatibiliy of
seals with the fluid being pumped.

     The presence of abrasive liquids also influences pump selection.
Internal passages must have adequate dimensions or abrasive particles will
damage parts that they rub against.  Close internal clearances between
stationary and moving parts is undesirable.  Rubber and ceramic parts resist
abrasive wear better than metal parts (Perry and Chilton, 1973).  Many manu-
facturers make abrasion-resistant models, and the pump should be selected
after a detailed assessment of the waste to be pumped has been made.
                                     7-14

-------
     The pump is not the only critical component in a properly designed
pumping system.   Other factors, such as pipe sizes and configurations,
fittings, type of hose used, and nature of the substance being pumped can
determine to a large degree the efficiency of a pumping system.
               c.  Costs


     This section presents 1985 cost data for rental of a centrifugal pumping
system. These data are best estimates and individual vendors should be
contacted for specific costs.   Operating costs are determined by the size of
the pump (i.e., horsepower) and the number of hours of operation.

     Power costs for a pump are determined using the following equations:

                              bho
     (1)  Power consumption
                              Em
            bhp = brake horsepower
            E  = efficiency
             m
     (2)  Power cost = —ฃ (0.7457 kw/hp) (cost/kWh)  (operating hours)
                       E
                        m

            kWh = kilowatt-hour
            hp = horsepower

     Power costs for 10, 50,  and 100 bhp pumps are $932,  $4600, and $9320,
respectively.  These costs are based on an 80 percent operating efficiency,
1000 hours of operation, and  an electricity cost of $0.10/kilowatt-hour
(Peters and Timmerhaus, 1980).  Operating costs are determined by the size  of
the pump (i.e., horsepower) and the number of hours of operation.  Hourly
operation costs are estimated to range from $0.42/hour to $1.63/hr for
centrifugal pumps having capacities of 400 gpm to 90,000  gmp (Godfrey,  1984).
The total rental costs vary according to daily, weekly, and monthly rates.
The costs vary from $16/day to $135/month for a pump having 400 gpm capacity
(Godfrey, 1984).  It should be noted that these are approximate costs,  and
final costing would require more detailed analysis.


          7.1.3.4.  Industrial Vacuum Loaders


     Industrial vacuum loaders such as the "Supersucker"  (Super Products,
undated) and the "Vactor" (Peabody-Myers, undated) can be used in large-scale
cleanup operations to remove  soil or pools of liquid waste.  Using industrial
loaders for soil removal is safer and more efficient than using hand tools.
The Supersucker and the Vactor are vehicle-mounted, high-strength vacuums that
can carry solids, liquids, metal and plastic scraps,  and  almost any other
                                     7-15

-------
material that can fit through a 7 inch hose.  They are equipped with a boom
and up to 500 feet of hose that allow them to convey materials from otherwise
inaccessible areas.  They are available in capacities ranging from 1,250 to
6,000 gallons.  Their mobility and large capacity eliminate the need to
transfer wastes to other vehicles before hauling for disposal or treatment.
Vacuum loaders can operate in either a solids or liquids handling mode.
Changing modes can be done quickly with an exterior adjustment and without
emptying the load.  This allows the Vactor or Supersucker to convey both soils
and pools of liquid waste without dumping the load.

     Portable skid-mounted vacuum units are also available.  These can be
airlifted, dragged by bulldozer, or even hauled on the back of a pickup truck
to otherwise inaccessible areas.  These units are generally available in
capacities ranging from 1,900 to 5,700 liters (500-1,500 gallons), although
units that can handle up to 11,400 liters (3,000 gallons) are manufactured.
Skid-mounted units with vapor recovery systems are also available.

     A number of factors should be considered prior to contracting for the
services of a vacuum truck.  Because of the large capacity of the vacuum
cylinder, vacuum trucks are generally not well suited to sites with fewer than
30 drums to be consolidated.  For a small site, it is generally more
cost-effective to overpack the drums or to use a vacuum skid-mounted unit.
This is due to high transportation costs and cost of handling wastewater
generated from decontaminating the truck.

     The cost of decontamination can be substantially reduced by a number of
good management practices.  The vacuum truck, or skid-mounted unit should be
dedicated as much as possible to handling a certain type of waste so that
decontamination is not required between each load.  The units should also be
sized for the job so that excessive decontamination water is not generated as
a result of choosing an oversized vacuum cylinder.

     Another important factor to consider in selecting vacuum trucks or skid-
mounted units is the compatibility of wastes with materials of construction.
Vacuum cylinders can be purchased in carbon steel, stainless steel, aluminum,
and nickel.  They can also be treated with a variety of coatings including
epoxy, fiberglass, and neoprene rubber.  In addition to selecting vacuum
trucks with compatible liners, compatibility problems can be minimized by
allowing wastes to react in a "reaction tank" or "compatibility chamber" where
the heat of reaction can be released before pumping the wastes into the vacuum
truck.

     Costs—According to a representative of Peabody-Myers, a truck having a
capacity of 3,000 gallons and production rate of 1,000 gallons/minute has a
rental cost of $100/hr.  This figure includes all costs except initial trans-
portation to the job site (Peabody-Myers, personal communication, 1985).
                                     7-16

-------
     7.1.4  Planning of Excavation  and  Removal  Activities


     There  are  a  number of  activities which are performed prior to and as part
of excavation and  removal activities.    These  include:   design and
construction of site operating  areas; implementation of controls to minimize
environmental releases and  protect  worker  safety;  and equipment selection and
mobilization.   Each is discussed  briefly below.


          7.1.4.1  Operational  Layout


     Proper layout of the work  area (including  support  facilities) is critical
to safe and cost-effective  excavation and  removal.   Figure 7-4 illustrates
structures, buildings, and  operating areas for  an  example site.  "Hot,"
"transition," and  "clean zones" should  be  established using air monitoring
data and available information  on waste locations.   The location of these
zones should govern where activities are carried out.   For example, any
staging or  on-site treatment  of wastes  would be conducted in the contaminated
zone; personnel decontamination would be carried out in the transition zone;
and administrative and emergency  medical care would  be  carried out in the
clean zone.

     Distinct operating areas should be provided for staging,  treating,
storage and transport of wastes,  and equipment  decontamination.   Figure 7-5
shows the operating areas for a waste site containing drums,  contaminated
soils, and  lab  packs.  Each area  should be designed  such that  there is
adequate room to maneuver equipment  and to provide for  emergency evacuation.
A careful evaluation is needed  to determine the minimum safe  distance between
different operating areas.  Within  each operating  area,  provisions must be
made to segregate  reactive, corrosive,  explosive,  flammable,  and incompatible
wastes.  Wastes which are explosive  or  radioactive should be  staged or stored
in isolated areas  until arrangements can be made for their safe detonation or
off-site disposal. For each operating area, necessary measures must be taken
to minimize environmental releases,  prevent incompatible waste reactions,  and
contain contaminants which  are  released.   These measures are  described in the
fo1lowing sub sect ions.


          7.1.4,2  Environmental  Controls
     The nature and extent of preventive and mitigative measures  required  for
controlling environmental releases during excavation and removal  are  site
specific, although there are a number of general procedures  that  apply  to  all
sites.  Operating areas for staging and treating drummed wastes and contam-
inated soils should be graded to prevent puddling;  lined with  polyethylene or
clay; and bermed or diked.  (This design will provide only minimal secondary
containment and will not be acceptable at many sites.)  Where  temporary
impoundments must be used to store liquids, it may  be acceptable  to provide
                                     7-17

-------
                                   FIGURE 7-4.
                        SITE OPERATIONAL  LAYOUT
                                                                       Induitritf
                                                                       Buildinf
  Outar
Protactna
Protactna T. 9tmtH
 Clothing     ******
 aap. GMT       *'••
      \    I    _ _.
                                                       Sampta  -
                                                      Praparation
                                                                       IndwtriaJ

                                                                     #m*tfKซWm[*
                                                                        Building ..
                                 Parvonal
                             Decontamination I
                            Station IPOS No. 1l|
                                    Equqtmantl
                                      Shad  I
                          Drum
                         Stating
                          Area
                       Obtarvation
                          Towปr
                       Air Srmpling
                          Station
              OHieWWarchouaa
                  Buildinf
                                     Traffic
                                    Direction
                                     (Truehf
                                     Only)
               nObaarvation
               y   Tซ
                       Raiaxation/
                      Standby Tant

                       Air Supply
                      Tuba Traiiar
                                                 Clothing
                                                  Chang*
                                                  T radar
          Contractor
        Command Pott
        QToitat
                                                 Equipment Shad
                                                 Command
                                                    Pott
                                                  Vahicta
                                                  Parking
Source:  Buecker and Bradford, 1982
(Manuscripts originally printed in Proceedings
of the National Conf. on Management of
Uncontrolled Hazardous Waste Sites, 1982.
Available from Hazardous Materials Control
Research Institute, 9300 Columbia  Blvd.,
Silver Spring, MD 20910)
                                         7-18

-------
                                     FIGURE 7-5.
           PICILLO HAZARDOUS WASTE SITE LAYOUT (WESTERN TRENCH)
Source: Perkins Jordan, Inc., 1982
                                        FUNCTION
                                        SOLIDS STORAGE/MIXING
                                •       STAGING/SAMPLING
                               10       DRUM CRUSH. RESERVE
                                        STORAGE
                               11       LAB PACK STORAGE
                               12       LAB PACK DEMOLITION
                             '3.1*       ACIO.PCB DRUM STORAGE
                               15       CONTAMINATED SUL
                             ia       LIQUID SAMPLE/STAGE/BULK
                                                                          TO WHEEL
                                                                          WASH
                                                                          EQUIPMENT
                                                                          PARKING
                                       7-19

-------
a thick clay liner and to excavate the contaminated  soils  after  use of  the
impoundment is completed.  Long storage periods or poor  site  conditions (e.g.,
wastes in the water table or permeable unsaturated zone) may  necessitate  the
use of a synthetic liner system.  The equipment decontamination  area  should
be a hard surface area that will retain wash water by perimeter  curbing and
collect these liquids by means of a central trough and perimeter sump.

     In addition to the above-mentioned preventive measures,  a number of  other
measures may be taken to mitigate and minimize releases.   Such measures
include:

     •  Covering contaminated soils which have been  excavated to prevent
        leaching of contaminants and fugitive dusts

     •  Using sorbents, pumps, or other equipment throughout  the operation to
        clean up spills promptly

     •  Maintaining drums, overpacks, or other types of  containers at
        strategic locations in work areas and on access  roads to be used  for
        prompt cleanup of spills

     •  Constructing surface water diversions around the site to control
        run-on and run-off

     •  Constructing a holding pond downslope of the site  to  contain
        contaminated run-off

     •  Avoiding uncontrolled mixing of incompatible wastes

     •  Promptly overpacking or transferring the contents  of  any drum that is
        leaking or may soon leak; promptly resealing drums following  sampling

     •  Using sand, foams, etc. to suppress small fires  before they spread

     •  Avoiding storage of explosives or reactive wastes  in  the vicinity of
        buildings or in confined areas

     •  Covering wastes that are known to be water reactive.


          7.1.4.3  Health and Safety of Field Personnel


     The USEPA and the Occupational Safety and Health Administration  (OSHA)
have published guidelines on health and safety procedures  applicable  to the
cleanup of uncontrolled hazardous waste sites.  These guidelines should be
considered at all remedial action sites; however, they will not  be covered in
                                      7-20

-------
this report.  A partial list of  field health  and  safety documents  are
presented below:

     •  USEPA, Interim Standard  Operating Safety  Procedures,  September  1982

     •  NIOSH, A Recommended Standard for Occupational Exposure  to Hot
        Environments, HSM No. 72-10269

     •  OSHA, Code of Federal Regulations, Title  29, Section  1910.134

     •  American Industrial Hygiene Association,  Respiratory  Protection, A
        Manual and Guideline, AIHA, 1980

     •  American National Standards Institute, Inc., Practices for Respiratory
        Protection, ANSI Z-88.2-1980, New York, 1983, p. 3-5

     •  Federal Emergency Management Agency,  Planning Guide and  Checklist for
        Hazardous Materials Contingency Plans, FEMA-10, July  1981.


          7.1.4.4  Equipment Selection/Mobilization


     The choice of equipment for excavation/removal activities is based
largely on inherent capabilities and limitations  of the equipment.  These
factors were discussed in Section 7.1.3 and summarized in Table  7-3.  Other
factors affecting equipment selection include:

     •  Equipment efficiency under site-specific  conditions
     •  Equipment dispatching time (transport and setup)

     •  Contractor performance record with equipment
     •  Equipment idle time

     •  Equipment versatility
     •  Equipment modifications  to increase efficiency and safety

     •  Equipment capability for remote waste handling.


     7.1.5  Excavation/Removal Procedures

     Regardless of the types of equipment used for excavation and handling,
certain standard operating procedures and safety  practices should be followed.
                                     7-21

-------










CO
23
O
M
H
H

a
M
H-!

p
CO
W
1— 1
M
M
"
Pj
CJ

H








o-
W
1

^
Q
S
W i

0
H
^
ฃ*J
CJ
X
w
















to
91
00


C
to
TS
to
1-4
Q
to
B
O
4J
ฃ
s
-j
to
%
oo u
c •*
"3 ฃ
to to
X CL
W
U
14-1
O
CO
fl3 iH
> 3
85
c
0
4J *O
10 91
> i-
n b
U 3
K tO

•o
01 E
01 3
•H O
U b
eg <:

OH
c
o
-< 01
10 4J
> o.
vs 9;
U O
X
CO

C b
o at
u to
>
U 91
X >




9J
B.

H


C
a>
B
a
1

•o
u 10 3

"s o -H u
•H -H X 91
ฃ S* "
U > O
a E • o
01 O 0) ซ•••
ts o a>
o o
00 ฃ ฃ 4J
E U Ji
•H -H O T3
00 J ซ 11
an x> u
T) a1 *~t B
91 10  B
at to -o to at
01 9J U O
G.TJ CO K ฃ
co B 3 at jf
(0 tJ
C 1) tW flj
•H >, ,5 ai .0
x: ฃ
0) W *J O (8
•H e oป x x
e > -u u
J -H ff ป CO
















X











X






X



09
b ^
91 to


O 9J

ฃ
•O U
C 10

09 10
b
9) T>
10 E

b O
O E
ป- E X
tO b
4J U 91
O • O
3 ป • -J
JO C 4J tO
•H O
u a a ••
as a. >,
3 e u
tO t3 O -<
U *-ซ
21 bS
nog
•3 cฐ3-o
O -H -H 0>
•H CX ซM 4J
***#•*
^ 1- 0 6
Q BO A ~*
















X











X






X



1 *

U i-l
to P-I

4J X
(D CD
e

C i-H tO
^ C
CO 
•o a- to
01 b u
5 a S


X














































CO

at
rH
i
M-<
O
(Q

ง0)
-o
V -H
ki -H
0
b W
o
•83?
w
-H ฃ
0) •<-<
$•0 c
3 2
U 7 C
2 2 S








X


































B
V
4-1
CO


60
C

a
I

01
60


w
0
"4-1
X

Ifj
9) O
4J 10
u b
ฃ |
91
1 91
n to
CJ B


X





X







X


















K



0)
e
3
3
u
a


p4

b
4-t
a
•o
c
7-22

-------
     As soils are being excavated on-site,  air monitoring should be conducted
to determine unsafe levels of various hazardous constituents.   Numerous
portable direct reading instruments are available for this purpose.  These
include:

     •  Combustible gas detectors for measuring the lower explosive limit
        (lowest concentration of flammable  gas that will explode, ignite or
        burn when there is an ignition source)

     •  Oxygen meters for measuring percent oxygen

     •  Photoionization detectors, flame ionization detectors,  infrared
        analyzers and detector tubes for measuring gases and vapors

     •  Radiation meters, including alpha/beta/gamma survey meters, gamma
        radiation meters and dosimeters for detecting radiation

     Where drums are present, a visual inspection should be made of the drum
to determine whether it is empty, intact, leaking, or potentially dangerous;
as evidenced by bulking, buckling, corrosion, and other deformations.

     Drum identification and inventory should begin before excavation.
Information such as location, date of removal, drum identification number,
overpack status, and any other identification marks should be recorded  on the
drum inventory forms.

     If there is an indication that the drums contain explosive or shock-
sensitive materials, they should be handled remotely, or at a minimum,  with
vehicles equipped with plexiglas safety shields.

     If a drum is critically overpressurized, it should be isolated with a
barricade or steel demolition net until the pressure can be relieved remotely.
A tarpaulin may also be used to cover the drum, provided the cloth is
positioned remotely using long poles or rods.  However, it must be cautioned
that the mere weight of the tarpaulin or change in position of the drum could
cause rupture.  Slow venting using a bung wrench and plastic cover over the
drum has worked for less critical situations; however, this should only be
attempted by experienced personnel and extreme caution should be exercised.

     Soils and drums containing ionizing levels of radiation should be  handled
on a site-specific basis.  Generally, when such wastes are identified (via
radiation meters), they are immediately drummed or overpacked using remotely
operated equipment and moved to a separate  staging area.  However, depending
on the level of radiation, special shielding devices may be required to
protect field personnel.  The Safety Officer should be consulted if
radioactive materials are encountered.

     Any drum that is leaking, badly corroded, or deformed should be
overpacked or should have its contents transferred to a new or reconditioned
drum.  In some instances, it may be possible to transfer the drum contents to
a "compatibility" chamber or vacuum truck.   These procedures,  however,  are
                                     7-23

-------
usually used for bulking after wastes have been identified rather than at this
stage, since lack of knowledge about waste types could result in incompatible
waste reactions.

     If gas cylinders are encountered, they should be moved promptly to an
area where the temperature can be controlled, particularly if they are
subjected to temperature extremes or direct sunlight.  Gas cylinders should
not be rolled, dragged, or slid, even for short distances.  Care should be
taken not to drop the cylinders or allow them to violently strike another
cylinder or drum (Matheson Gas Products, undated).

     As contaminated soils are excavated from the disposal area, they should
be transferred to box trucks or to a temporary storage area, preferably a
diked or bermed area lined with plastic or low permeability clay.  A layer of
absorbent material should be placed on the bottom of the temporary storage
area.  Frequently, gas analyzers are used to determine the approximate level
of contamination of soils.  Soils can then be segregated based on contaminant
levels.  Pools of liquid wastes should be promptly removed using pumps or
solvent materials.
7.2  Off-Site Disposal


     7.2.1  General Description


     This section describes the major factors that must be considered in
selection of an off-site disposal facility and preparing wastes for off-site
transport.  Off-site disposal, as described in this section, includes land-
filling and incineration.  Off-site waste treatment is described in Section
10.


     7.2.2  Applications/Limitations


     Determining the feasibility of off-site disposal requires knowledge of
RCRA regulations (40 CFR Parts 261-265) and other regulations developed by
State Governments.  RCRA manifest requirements, under 40 CFR Parts 262 and
263, must be complied with for all wastes that are shipped off-site.  In
addition, the waste generator (or other responsible party, when the generator
is unknown) must comply with RCRA manifest requirements under 40 CFR Parts 262
and 263, and the generator should comply with applicable hazardous waste
generator requirements under 40 CFR Part 262.  In addition, the generator
should ensure that the facility selected to receive the wastes is in
compliance with all applicable Federal and State environment and public health
statutes.  Under 40 CFR 264.12, RCRA storage, and disposal facilities are
required to notify the generator, in writing, that they are capable of
managing the wastes.  The generator must keep a copy of this written
notification on file as part of the operating record.
                                     7-24

-------
          7.2.2.1  Off-Site Landfilling


     Landfilling of hazardous materials is becoming increasingly difficult and
more expensive due to steadily growing regulatory control of this technology.
Therefore, wastes that are amenable to treatment or incineration should be
segregated from wastes for which no treatment alternative is known.
Landfilling should usually be regarded as the least attractive alternative at
a site cleanup action.

     Landfilling costs are approximately $240/ton for highly toxic wastes
(e.g., high levels of chlorinated hydrocarbons), $120/ton for ignitable
materials (40 CFR, Part 264.312 must be complied with), $85/ton for most
industrial sludges, and $40 to $50/ton for municipal treatment sludges.
          7.2.2.2  Incineration


     Among the most important factors which a treatment facility considers in
determining the suitability of wastes for incineration include:  btu content
of the waste, viscosity, water content, halogen content and ash content.  Many
incineration facilities' permit conditions specify a minimum acceptable btu
content.  The minimum acceptable btu is generally not less than about 5000
btu/lb since at this heating value the incineration process can often be self
sustaining and require no auxiliary fuel.  High water content in a waste tends
to reduce the heating value and therefore many facilities will specify a
maximum allowable water content.  Certain incinerators are not equipped to
handle highly viscous or solid wastes, and this may be yet another criteria
which they use to accept or reject a waste load.

     EPA regulations (under RCRA) for hazardous waste incineration require
that particulate emissions be no more than 180 mg/Nm  and that hydrogen
chloride removal efficiency from the exhaust gas be no less than 99 percent.
Trial burns are conducted prior to issuance of a permit to determine the
maximum ash and chlorine content which a waste can handle in order to meet
these requirements.  Thus, the facility is likely to have maximum limits for
halogen content and ash.  Incineration of PCB's and low-level radioactive
wastes requires special permits and there are only a limited number of
facilities permitted to handle these wastes.


     7.2.3  Implementation


          7.2.3.1  Preparation of Wastes for Off-Site Treatment/Disposal


     Where drums or multiple impoundments are present it is often most
cost-effective to consolidate their contents in a tank truck.  Compatibility
testing should be performed prior to bulking wastes for off-site transport to


                                     7-25

-------
ensure that consolidation will not result in incompatible waste reactions or
in large volumes of waste which are unacceptable for off-site disposal.
Compatibility testing refers to simple, rapid, and cost-effective testing
procedures that are used to segregate wastes into broad categories.  By
identifying broad waste categories, compatible waste types can be safely
bulked on-site without risk of fire, explosion, or release of toxic gases,  and
disposal options can be determined without an exhaustive analysis of each
waste type .

     Compatibility testing protocols have been developed by a number of
cleanup contractors and generators.  Often, however, the procedures must be
tailored to meet the testing requirements of prospective treatment/disposal
facilities.  The Chemical Manufacturers Assocation (CMA, 1982) has developed  a
compatibility testing protocol which has been used at a number of sites.
Based on the CMA protocol, wastes can be segregated into the following broad
waste categories:

     •  Liquids

           Radioactive
        -  Peroxides and oxidizing agents
           Reducing agents
        -  Water-reactive compounds

     •  Water insolubles

           Low halogen, low PCB
        -  Mixed halogen, high PCB
        -  High halogen, low PCB

     •  Ac id s

        -  Strong (pH <2)
        -  Weak (pH 7-12), with or without cyanides or sulfides

     •  Bases

           Strong (pH >12), with and without cyanides or sulfides
        -  Weak (pH 7-12), with and without cyanides or sulfides

     •  So 1 id s

           Radioactive
        -  Nonradioactive.

     Testing to determine gross halogen content is sometimes eliminated if  all
insoluble wastes are to be incinerated at a facility capable of handling
chlorinated organics.  However, testing for PCBs is required regardless of  the
need for testing other halogenated compounds.
                                     7-26

-------
     The CMA protocol also requires  that  small  samples  of  wastes  that  are
intended to be bulked are mixed together.  Visual observations  are  then made
for precipitation, temperature changes, or phase separation.

     There are some differences between the CMA compatibility protocol and  the
protocol used by some cleanup contractors.  One commonly used procedure  is  to
conduct flammability and ignitability tests on  a drum-by-drum or  waste-by-
waste basis for both liquid and solid drums.  CMA, on the  other hand,  recom-
mends that these tests be performed  on composite samples before bulking, since
these tests require more costly and  time-consuining analysis  (torch  test  and
closed cup flame test).  Another common practice is to  conduct  further testing
on samples from drums containing solids.  These tests may  include water
reactivity, water solubility, pH, and the presence of oxidizers.  In general,
the decision to perform these analyses on each  waste rather  than  on a
composite sample (prior to bulking)  is made based on the number of  drums and
the types of wastes known to be present on site.

     Hatayama et al. (1980a, 1980b)  have  also provided  guidance on  waste
incompatibilities that can be useful during the waste consolidation process.
These researchers have developed a hazardous waste compatibility  protocol that
allows the user to evaluate potential adverse reactions for binary  combina-
tions of hazardous wastes.  Binary waste  combinations are  evaluated in terms
of the following adverse reactions:  heat generation from  a chemical reaction,
fire, toxic gas generation, flammable gas generation, explosion,  and violent
polymerization of toxic substance.

     A detailed waste analysis is generally required before a waste is
accepted by a treatment/disposal facility.  Table 7-4 specifies the types of
analyses which are typically required before a waste can be considered for
off-site disposal at a particular facility.  However, requirements vary
considerably depending upon the facility  permits, state regulations, physical
state of the wastes, and the final disposal option which is selected.

     On-site pretreatment of wastes may be required in  order to make them
acceptable for off-site transport or to meet the requirements of  an incin-
eration or disposal facility.  For incineration or land disposal  facilities,
pretreatment will likely be limited  to the following:

     •  Acid-base neutralization (land disposal and incineration)

     •  Metal precipitation/solidification (land disposal)

     •  Hypochlorite oxidation of cyanide and sulfide (land disposal and
        incineration)

     •  Flash point reduction (land disposal)

     •  Removal of free liquids by addition of soils, lime, fly ash, polymers,
        or other materials which remove free water (land disposal).
                                     7-27

-------
                                  TABLE 7-4.
                POTENTIAL ANALYTICAL REQUIREMENTS FOR DISPOSAL
PHYSICAL STATE

     Physical state at 70ฐF
     Number of layers
     Free liquids (percent by volume)
     pH
     Specific gravity
     Flash point
     Viscosity
WASTE COMPOSITION

     EP Toxic Metals (Arsenic, Barium, Cadmium, Chromium, Lead, Mercury,
       Selenium, Silver)
     EP Toxic Pesticides (Endrin, Lindane, Methoxychlor Toxophene, 2,4-D,
       2,4,5-TP)

     Hydrocarbon Composition (must account for 100 percent)

     Organochlorine

     Sulfur

     Cyanide

     PCB content


HAZARDOUS CHARACTERISTICS

     Reactive (pyrophoric or shock sensitive)
     Explosive
     Water reactive
     Radioactive
     Ignitable
                                     7-28

-------
          7.2.3.2  Transportation


     The transportation  of hazardous  wastes  is  regulated  by the Department of
Transportation, the Environmental Protection Agency,  the  States,  and,  in some
instances, by local ordinances  and  codes.  In addition, more stringent federal
regulations also govern  the  transportation and  disposal of highly toxic and
hazardous materials such as  PCBs  and  radioactive  wastes.   Applicable
Department of Transportation regulations  include:

     •  Department of Transportation  49 CFR, Parts  172-179

     •  Department of Transportation  49 CFR, Part  1387  (46 FR 30974,  47073)

     •  Department of Transportation  DOT-E 8876.

     The USEPA regulations under  RCRA (40 CFR Parts  262 and 263)  adopt DOT
regulations pertaining to labelling,  placarding,  packaging, and spill
reporting.  These regulations also  impose certain additional requirements for
compliance with the manifest system and recordkeeping.

     Vehicles for off-site transport  of hazardous  wastes  must be  DOT approved
and must display the proper  DOT placard.  Liquid  wastes must be hauled in
tanker trucks that meet  certain requirements and  specifications for  the waste
types.  Contaminated soils are  hauled  in box trailers and drums in box
trailers or flat bed trucks.  The trucks  should be  lined  with plastic  and/or
absorbent materials.

     Before a vehicle is allowed  to leave the site,  it  should be  rinsed or
scrubbed to remove contaminants.  Both bulk liquid  containers and box  trailers
should be checked for proper placarding, cleanliness,  tractor-to-trailer
hitch, and excess waste  levels.   Bulk  liquid containers should also  be checked
for proper venting, closed valve  positions,. and secured hatches.   Box  trailers
should be checked to ensure  correct liner installation, secured cover
tarpaulin, and locked lift gate.


     7.2.4  Selection/Evaluation  Considerations
     Excavation and removal can almost totally eliminate  the  contamination  at
a site and the need for long-term monitoring.  Once excavation  is begun,  the
time to achieve beneficial results can be short relative  to such alternatives
as in-situ treatment, subsurface drains, and, in some  instances, pumping.
Excavation   and removal can be used in combination with  almost any  other
remedial technologies.

     The biggest drawbacks with excavation, removal, and  off-site disposal  are
associated with worker safety, short term impacts, cost,  and  institutional
aspects.  Where highly hazardous or toxic materials are present, excavation
can pose a substantial risk to worker safety.  Short term impacts such as
fugitive dust emissions, toxic gases, and contaminated run-off  are frequently
a major concern, although mitigative measures can be taken.   Costs associated

                                     7-29

-------
with off-site disposal are high and frequently result in exclusion of  complete
excavation and removal as a cost-effective alternative.  The  location  of  a
RCRA approved landfill or incinerator also has a substantial  impact on costs.

7.3  On-site Land Disposal


     7.3.1  General Description


     This section describes on-site disposal of wastes by landfilling.  It
involves the design and construction of new landfills which comply substan-
tially with RCRA landfill facility standards under 40 CFR Part 264.  It should
be noted that EPA guidance for CERCLA responses requires most on-site  disposal
actions "to attain or exceed applicable and relevant standards of [all]
Federal public health and environmental laws, unless specific circumstances"
dictate otherwise (FR_ 29:5862-5932, 1985).  However, permitting requirements
under the laws are usually not required for fund-financed or  enforcement
actions under CERCLA (FR 29:5862-5932, 1985).


     7.3.2  Application/Limitations


     The RCRA requirements under 40 CFR Part 264 and all associated guidance
are concerned with the proper location, design, construction, operation,  and
maintenance of hazardous waste management facilities.  These  requirements
preclude landfilling in areas of seismic instability, in a 100-year flood-
plain, and where the integrity of the liner system would be adversely
affected.  These requirements also preclude landfilling of liquids and several
types of highly mobile and/or highly toxic wastes.  In addition to complying
with these requirements, the evaluation of an on-site landfill program must
address potential risks posed by the depth to groundwater at  the site  and the
degree of naturally available groundwater protection if the liner system
should fail.  Other factors entering this evaluation include  costs for
monitoring the groundwater, collecting any accumulated leachate, and for
implementing further corrective action if the groundwater has been contam-
inated by a leak from the new landfill.  Furthermore, it may  be technically
infeasible to develop a groundwater monitoring program at sites where  the
groundwater has already been contaminated.


     7.3.3  Landfill System Design, Construction, and Implementation


     This section describes the design of a landfill with a double liner
system and two leachate detection, collection, and removal systems according
to applicable RCRA requirements.  Figure 7-6 shows a diagram  which illustrates
the two double liner designs described in EPA guidance.  One  of these  designs
involves two synthetic liners and at least 5 feet of clay; the other involves
one synthetic liner and a clay layer that will not be penetrated by waste
leachate for at least 30 years, even if the synthetic liner fails (USEPA,
1984).
                                     7-30

-------
               in
               o
* m 2^2
0 ฃ
I W
1

>•
0 .
u 0
E fe ฐ
1

>- UJ
CO 1 W 1-


J
Q. ^
5 2
L
Ll •
^
1- UJ
CO DC
^_ •—• 	
3 <


_l frt
A ^ 2
. ? g 0
I 	
u *
> to
H "i Q
W DC 2
big & i a
-" ฃ S < i ? < 3
!T S_
^ k- -
•ป 1 	
U- C " *- '
Q fecog to
z L
^" _
^ X,
u — |-
H 2 <•
^ u

*, 5
J *=- -
C
J

5 1 ฃ
u
_
•~ _
Ll h
J C.
J u
_ "j
J 2
u :*:
3 88dR g o -j y
oc ^^8^s ui 8 ^
2 lฃzฃ f, 
OT Q
ii i <
u
j b
J O uj U
!|S|ง ||S |
S IS^SS 2^^^
cc ฃฃyฃd ฃ^^^
Ul
Z
a)-1
^J
iu m
tt D
ll
II
0
u.
O
2
<
CC
3
Q
O
5
LJJ
T
0
V)



\










0






O






O





i










o






0






o





^

^


^^*

^^
^^
^^^

^*

^

,_
Z
I

***


*^

**•
**


**•

O
CO
LU
Q












^
1




O
O


o
o
o
o
o
0


o
o
o
o



1

CM
Z
I
o
o


o
o
o
o
o
o


o
o
o
0
1
^-
^--x

^-"
^
^*

^
^**
^**^
^*
^,
^
^~
o
CO
LU
Q













7-31

-------
          7.3.3.1  Overall Liner System Design Standards


     Specific RCRA requirements pertaining to hazardous waste  landfill  liner
systems include the following (Cope et al., 1984):

     •  Liner materials must be compatible with the waste material being
        disposed and must be able to withstand any physical forces such as
        hydrostatic pressure, adverse climatic changes, and other physical
        stresses, such as the stresses of installation and the heavy equipment
        used to move and compact wastes.

     •  Liners must be placed on a stable foundation designed  to prevent
        failure due to settlement, compression, uplifting, or  warping likely
        to be caused by unexpected changes in pressure gradients above, below,
        or adjacent to the liner material.

     •  All liners must be installed to ensure that the waste  or leachate
        cannot come into contact with the surrounding soils.

     •  The liner system must be monitored and inspected during construction
        and installation, and inspected for uniformity, damage, and imper-
        fections following installation.  Soil-based and admixed liners and
        covers must be inspected for imperfections including lenses, cracks,
        channels, root holes, or other structural nonuniformities that may
        cause an increase in the permeability of the liner or  cover.

     Evaluation of the site's geological and hydrological conditions is
critical to developing a well engineered hazardous waste landfill.  Table 7-5
summarizes the major adverse site conditions which can result  in liner
failure.  Preventive measures must be taken to prevent liner failure under
these conditions.
          7.3.3.2  Primary Leachate Collection and Removal System


     RCRA requirements mandate that leachate collection and removal  systems
be placed immediately above the primary liner in all new hazardous waste
landfills.  Such systems must be capable of maintaining a leachate depth of  1
foot or less above the liner and withstanding clogging, chemical attack, and
forces exerted by wastes, equipment, or soil cover.

     EPA guidance documents recommend that the leachate collection system
consist of a drainage layer at least 1 foot thick, with a hydraulic  conduc-
tivity >_ 1 x 10   cm/sec, and a minimum slope of 2 percent.  When_installed
over a secondary clay liner with hydraulic conductivity of 1 x  10    cm/sec,
such a system provides the four-order-of-magnitude difference in permeability
known to significantly increase drainage efficiency (Cope et al., 1984).   The
drainage layer should be covered by a filter (graded sand layer or geotex-
tiles) to prevent infiltration of fines from the waste and subsequent  clogging
of the drainage layer.

                                     7-32

-------
                          TABLE 7-5.
SUMMARY OF ADVERSE SITE CONDITIONS AFFECTING LINER PERFORMANCE
   Unfavorable Condition
Potential Liner Problem
•  Geotechnical/Hydrogeologic

   Moderate to active seismic
   area

   Settlement or subsidence
   High groundwater table


   Voids

   Sinkholes

   Subsurface gas


   High permeability soils

   Climatic

   Frozen ground/ice

   Wind

   Sunlight
   High humidity
Levee instability; liner
failure

Cracks in clay or tears in
synthetic liners

Lifting or rupturing of
liner

Cracking of liner

Liner failure

Lifting of liner prior to
backfilling

Piping of subgrade
Cracking, tearing

Lifting and tearing liner

Dehydration of clay liner
(permitting cracks to develop)

Destruction of some synthetic
liners (caused by ultraviolet
rad iation)

Poor seam adhesion caused by
absorption of moisture by
the solvents
Source:   Cope et al.,  1984
                             7-33

-------
     Leachate collection pipe networks should consist of  slotted  or  perforated
drain pipe bedded and backfilled with a gravel envelope.  Layouts  should
include base liner slopes >^ 2 percent and pipe grades >^ 0.005.  Pipe  spacing
should be determined for the unit (see Section 5.2).  All pipes should  be
joined and, where appropriate, bonded (Cope et al.,  1984).   Sumps  or  basins
should be installed at low points on the base of  the fill to  collect  leachate
discharging from the collection network.  A riser  pipe  extending  from the  sump
to the ground surface enables leachate removal.


          7.3.3.3  Primary Synthetic Liner


     A variety of synthetic and natural materials  are available for  use as
liners.  While soil liners are suitable for use as  secondary  liners,  synthetic
membranes are the primary mechanisms for long term  containment.   Table  7-6
summarizes the major characteristics, advantages,  and disadvantages  of  various
liner materials.

     A critical first step in designing a liner system  for  a  hazardous  waste
landfill is an evaluation of the physical and chemical  composition of the
wastes to be contained within the facility.  Since  the  primary purpose  of  a.
liner is to prevent liquids from leaving a hazardous waste  facility,  the
physical integrity of the liner and its chemical  compatibility with  the waste
constituents must be ensured.  A test method accepted by  the  USEPA for
evaluating waste synthetic liner compatibility is  presented  in Appendix B  of
RCRA guidance document Landfill Design-Liner Systems and Final Cover.   The
method basically involves exposing a liner sample  to the waste or  leachate
encountered at the facility and, after exposure,  the sample  is tested for
strength and weight loss.  Significant deterioration in these properties  is
considered evidence of incompatibility unless otherwise demonstrated  (Cope et
al., 1984).

     Once a synthetic liner is selected (based on  the criteria described
earlier), the major focus of the design activities  is on  preparing a  firm  and
smooth base for the membrane by compacting, scraping, and rolling  the base.
The major concerns during the installation of a synthetic membrane liner  are
providing protective soil layers above and below  the liner  and proper seaming
of the liner.  This requires that manufacturers'  installation procedures  and
practices be followed for the specific type of membrane proposed.  Each type
of membrane liner also requires specific seaming  provisions  to ensure an
effective bond.  Since adverse weather conditions  (e.g.,  extreme  heat or  cold,
precipitation, winds) can affect adequate bonding  of the  liner field  seams,
installation should be avoided during these periods, unless  protective
measures are used (Cope et al., 1984).

     During placement of the liner and before wastes are  placed in the  land-
fill, tests of seam strength and bonding effectiveness  should be  conducted.
In addition, random samples of seams should be cut  from the  liner and
subjected to on-site and laboratory testing.  Liner placement, seaming, and
testing are covered in detail in the USEPA technical document Lining of Waste
Impoundments and Disposal Facilities, SW-870 (Cope  et al.,  1984).

                                     7-34

-------
                                                      TABLE 7-6.
                       CHARACTERISTICS, ADVANTAGES, AND  DISADVANTAGES OF
                                          SELECTED  SYNTHETIC LINERS
 Liner Material
                      Characteristics
                             Range of Costs   Advantages
                                             Disadvantages
 Butyl rubber
 Chlorinated
 polyethylene
 Chlorosulfonated
 polyethylene
 Epichlorohydnn
 rubbers
 Ethylene propylene
 rubber
 Neoprene
 Polyvmyl chloride
 Thermoplastic
 elastomers
 High Density
 Polyethylene
Copolymer of isobutylene
with small amounts of
isoprene
Produced by chemical
reaction between
chlonne and high
density polyethylene
Family of polymers pre-
pared by reacting poly-
ethylene with chlorine
and sulfur dioxide

Saturated high molecular
weight, aliphatic poly-
ethers with chloromethyl
side chains
Family of terpolymers of
ethylene. propylene, and
nonconjugated hydro- •
carbon
Synthetic rubber based
on chloroprene
Produced in roll form in
vanous widths and
thicknesses: polymeriza-
tion of vinyl chloride
monomer
Relatively new class of
polymeric materials
ranging from highly
polar to nonpolar

Blow or sheet extended
P.E.
                                                         M
      M
      M
M to H (based
on thickness)
Low gas and water vapor
permeability, thermal
stability; only slightly
affected by oxygenated
solvents and other polar
liquids
Good tensile strength
and elongation strength;
resistant to many inor-
ganics
Good resistance to
ozone, heat, acids, and
alkalis; easy to seam
Good tensile and tear
strength: thermal sta-
bility; low rate of gas
and vapor permeability,
weathering; resistant to
hydrocarbons, solvents,
fuels, and oils
Resistant to dilute con-
centrations of acids.
alkalis, silicates,
phosphates and bone;
tolerates extreme tem-
peratures; flexible at
low temperatures; excel-
lent resistance to
weather and ultraviolet
exposure
Resistant to oils,
weathenng, ozone and
ultraviolet radiation;
resistant to puncture,
abrasion, and mechanical
damage
Good resistance to inor-
ganics, good tensile.
elongation, puncture,
and abrasion resistant
properties; wide ranges
of physical properties.
easy to seam
Excellent oil, fuel, and
water resistance with
high tensile strength
and excellent resistance
to weathenng and ozone
Good resistance to oils
and chemicals; resistant
to weathering; available
in 20 to 150 mils thick-
nesses: resistance to
high temperature
                                             Highly swollen by hydro-
                                             carbon solvents and
                                             petroleum oils; diffi-
                                             cult to seam and repair
Will swell in presence
of aromatic hydrocarbons
and oils; high elonga-
tion, poor memory
Tensile strength
increases on aging; good
tensile strength when
supported; poor resis-
tance to oil
Difficult to field seam
or repair
                                             Not recommended for
                                             petroleum solvents or
                                             halogenated solents;
                                             difficult to seam or
                                             repair; low seam
                                             strength
                                             Difficult to seam or
                                             repair
                                             Attacked by many organ-
                                             ics, including hydro-
                                             carbons, solvents and
                                             oils; not recommended
                                             for exposure to weath-
                                             enng and ultraviolet
                                             light conditions
                                             None reported
Thicker sheets require
more field seams, sub-
ject to stress cracking;
subject to puncture at
lower thicknesses. Poor
tear propagation
 1. Adapted from Technologies and Management Strategies for Hazardous Waste Control, Office of Technology Assessment, Congress of
   the U.S.,  1983. Modified in consultation with industry experts.
 2. Cost ranges: L = $1-4/yd*. M = $4-8'ydz, H = $8-12yd* (installed costs).
 3. All ratings are based on properly compounded materials designed for that specific application

Source Cope et al ,  1984
                                               7-35

-------
          7.3.3.4  Secondary Leachate Collection
     The secondary leachate collection  system  is  located  between  the  two
liners and is generally used to detect  and remove  any  liquid which  could
migrate into the space separating the liners.   ~Lt  is designed  similarly to  the
primary leachate collection and removal system in  which liquid  is collected in
a porous medium and subsequently removed by gravity using a  network of
perforated pipes.
          7.3.3.5  Secondary Liner System


     The secondary liner should have an "adequate  thickness  to  avoid  failure
throughout the post-closure monitoring period,  and be  chemically  resistant  to
the waste and leachate managed at the landfill"  (USEPA,  1984).  Soil  liners
may be constructed of native clay materials exhibiting  a remolded  permeability
of 1 <_ x 10   cm/sec and obtained either on-site,  from  selected borrow areas,
or from off-site sources.  Proper installation  of  a  soil liner  is  needed  to
maintain this specified minimum permeability (Cope et  al., 1984).  To  ensure
adequate compaction, soil materials should be spread  in loose  lifts no more
than 6 inches deep, wetted or dried to 2 percent or more above  optimum mois-
ture content, and compacted with a sheepsfoot-type roller to the  specified
relative compaction.  Specified values must be  based  upon the  tested  rela-
tionships between moisture content, relative compaction, and permeability.
Furthermore, installation of a clay liner should not  be attempted  under
adverse weather conditions such as heavy precipitation  or freezing
temperatures (Cope et al., 1984).


     7.3.4  On-site Landfill Operation, Monitoring,  and Maintenance


          7.3.4.1  Operation and Maintenance


     The operating life of an on-site landfill  should be minimized to avoid
unnecessary generation of leachate caused by rainfall  into an open cell.
Sometimes it is more efficient to construct several  landfill cells in sequence
rather than to construct one large cell which will remain open  for a  long time
period.  This determination is made by calculating and  comparing  the  marginal
costs of extra leachate treatment with the marginal  costs of extra liner
materials.  During the operating life of an on-site  landfill, every effort
should be made to prevent run-on of rainwater into the  landfill and to prevent
hazardous liquid disposal.  All liquids should  be  solidified prior to land-
filling and the sorbent materials used should be resistant to later releases
of liquids through biodegradation or pressure of overlying wastes. All
materials placed into an on-site landfill should be  compacted as much as
possible using heavy equipment such as a sheepsfoot  roller or a specially
designed compactor vehicle.  This practice will minimize settling  after
                                     7-36

-------
 closure,  and  thus will  protect  the  integrity of the final cap (see Section
 3.1).  All  equipment  and  operators  and other workers at the landfill should be
 thoroughly  trained  in the handling  of all  wastes to be placed in the landfill.
 These  persons  should  also be  trained  in the proper operation of heavy
 equipment,  emergency  response,  and  the proper use of their safety equipment.
 During the  operating  life and post-closure period of the landfill, regular
 inspections should  be conducted to  check the integrity of the storm water
 controls, leachate  collection/detetion sumps, and ground-water monitoring
 wells.  Any broken  equipment  should be repaired or replaced immediately,  and
 any  leachate  in  the collection  or detection sumps should be removed
 immediately.   Maintenance procedures  at a  landfill are identical to those
 presented for  capping (Section  3.1.3.5).
           7.3.4.2   Groundwater  Monitoring


     RCRA  requires  all  owners and  operators  of  land  disposal  facilities to
establish  a groundwater monitoring program (Subpart  F,  Part  264).   The
groundwater monitoring  program  must  be  capable  of  determining the  facility's
impact on  the  quality of  groundwater in the  uppermost  aquifer underlying the
facility.  In  some  cases  it may be appropriate  to  monitor other hydrogeologic
limits in  addition  to,  or in lieu  of, the uppermost  aquifer,  depending on
specific conditions.

     The minimum requirements for  any groundwater  monitoring  system involve at
least one  upgradient well which is capable of yielding representative back-
ground samples and  at least three  downgradient  wells whose location and depth
ensure immediate detection of any  statistically significant  amounts of hazard-
ous wastes or  constituents in the  upper aquifer.   Where these minimum require-
ments do not allow  the  owner or operator to  meet the overall  performance
objectives, he must determine where  and how  many additional wells  are needed.
Once established, groundwater monitoring programs  must  continue for an average
of 30 years depending on  site-specific  conditions.   During this period,
groundwater samples are generally  taken semiannually and  analyzed  for indica-
tor parameters which are  developed on a site-specific  basis.   Concentrations
of indicator parameters from samples collected  at  the  downgradient  wells are
individually compared to  average background  concentrations established from
the upgradient well(s).


     7.3.5  Technology  Selection/Evaluation


     On-site landfilling  is an  expensive  technology  which should only be
considered when:  (1) there is  so  much  waste to be disposed  that the total
cost of off-site waste management  at  an acceptable site  is comparable;
(2) simple capping of the  site  will  not  provide adequate  protection of human
health and the environment; and (3)  on-site  conditions will allow the con-
struction of a landfill that will  protect  human health  and the  environment.
Since it is rare that all  three of the  above conditions  are met at  a site,  the
on-site landfill option is not  frequently  used.

                                     7-37

-------
     7.3.6  Costs
     The costs of constructing an on-site landfill depends on the size of the
facility, the design features of each layer of the liner system, and site-
specific engineering factors.  However, general material and installation
costs for the various components of a landfill are presented in Table 3-1 and
Table 5-10.  Excavation costs are presented in Section 7.1.3.  The costs for
monitoring well construction, sampling, and sample analyses can vary by orders
of magnitude because of the number of factors involved.  These factors include
well depth, diameter, type of drill rig, type of substrate, types of wastes in
the landfill, number of indicator parameters, level of indicator parameters,
number of wells, levels of existing groundwater contamination, and area of the
country.  Therefore, the costs for groundwater monitoring programs cannot be
estimated until a groundwater investigation has been conducted and a plan has
been developed.
                                      7-38

-------
                                   REFERENCES
Beck, E.G.   1984.  A  Special  Feature  Report:   Specifier's  Guide to Pump
Selection.   Pollution Engineering.  Vol.  XVI,  No.  7.   pp.  45-52.

Brunner, D.R.  and D.J.  Keller.   1972.   Sanitary Landfill  Design and Operation.
SW-65ts.  USEPA, Washington,  DC,  101-72.

Buecker, D.A.  and M.L.  Bradford.   1982.   Safety and  Air Monitoring Consider-
ations  at the  Cleanup of  a  Hazardous  Waste  Site.   Proceedings of the National
Conference on  Management  of Uncontrolled  Hazardous Waste  Sites, November
29-December  1.  Hazardous Materials Control  Research Institute, Silver Spring,
MD.

Chemical Manufacturers  Association  (CMA).   1982.   Hazardous  Waste Site
Management Plan.  Chemical  Manufacturers  Association,  Washington,  DC.

Church, H.K.   1981.   Excavation  Handbook.  McGraw  Hill Book  Company,  New York,
NY.

Cope, F., G. Karpinski, J.  Pacey,  and L.  Stein.  1984.  Use  of liners  for
containment  of hazardous  waste landfills.  Pollution Engineering.
Vol. 16, No. 3.

Cole-Parmer  Instrument  Co.  1982-83.  Pump Applications Guide.   Chicago,  IL.

Godfrey, R.S.  1984.  Means Site Work Cost Data  1985.  4th ed.   Robert S.
Means Company, Inc.,  Kingston, MA.

Hatayama, H.K., E.R.  deVera,  B.P.  Simmons, R.D.  Stephens,  and D.L.  Storm.
Hazardous Waste Compatibility.   Proceedings of  tlie Sixth Annual Research
Symposium on Disposal of  Hazardous Waste.  EPA  600/9-80-010.   USEPA,
Cincinnati,  OH.

Hatayama, H.K., et al.  1980b.   A Method  for Determining  the Compatibility of
Hazardous Wastes.  EPA  600/2-80-076.  USEPA, Office  of Research and
Development.   Cincinnati, OH.

Henshaw, T.L.  1981.  Reciprocating Pumps.  Chemical Engineering.   Vol 88,
No. 19.  pp. 105-123.

Karassik, I.J., W.C.  Krtuzsch, W.H. Frazer, and J.P. Messina.   1976.   Pump
Handbook.  McGraw-Hill Book Company, New York, NY.

Muller, B.W., A.R.  Broad, and J. Leo.   1982.  Picillo  Farm,  Coventry,  Rhode
Island:  A Superfund & State Fund. Cleanup Case History.  Proceedings of the
National Conference on Management of Uncontrolled  Hazardous  Waste  Sites,
November 29-December  1.    Hazardous Materials Control Research Institute,
Silver Spring, MD.
                                     7-39

-------
Peabody-Myers, Inc.  Undated.  VACTOR 2045.  Product Literature.
Streator, IL.

Perkins Jordan, Inc.  Evaluation of Remedial Action on the Picillo Property,
Coventry, Rhode Island.  Prepared for:  Rhode Island Department of Environ-
mental Management, Providence, RI.

Peters, M.S. and K.D. Timmerhaus.  1980.  Plant Design and Economics  for
Chemical Engineers.  3rd ed.  McGraw-Hill Book Company, New York, NY.

Perry, R.H. and C.H. Chilton.  1973.  Chemical Engineer's Handbook.   5th ed.
McGraw-Hill Book Company, New York, NY.

Skinner, J.H.  1984.  Memorandum.  Draft Technical Guidance for Implementation
of the Double Liner System Requirements of the RCRA Amendments.  USEPA, Office
of Solid Waste, Washington, DC.  December 20, 1984.

Stubbs, F.W.  1959.  Handbook of Heavy Construction.  1st ed. McGraw-Hill Book
Company, New York, NY.

Super Products.  Undated.  Supersucker.  Product Literature.

USEPA.  1978.  Milwaukee, WI.  Liners for Sanitary Landfills and Chemical and
Hazardous Waste Disposal Sites.  Cincinnati, OH.  PB 293335.

USEPA.  1985.  Draft Guidance on Implementation of the Minimum Technological
Requirements of the Hazardous and Solid Waste Amendments of 1984.  Office of
Solid Waste, Land Disposal Division, Washington, DC.
                                      7-40

-------
                                    SECTION  8

               REMOVAL AND CONTAINMENT OF CONTAMINATED  SEDIMENTS
     Contamination of the bottom  sediments of  streams,  ponds,  lakes,  harbors,
estuaries, and other water bodies may occur via  several different  pathways.
Contaminated soil may be eroded from the  surface of hazardous  waste disposal
sites by natural runoff and be deposited  in nearby watercourses or sediment
basins constructed downslope of the site.  Existing sediments  along stream
bottoms may absorb chemical pollutants that have been washed into  the water
course from disposal areas within the drainage basin.   Similarly,  contaminated
groundwater may drain to surface water courses and the  transported pollutants
may settle into or chemically bind with the bottom sediments.  Another  source
of sediment contamination results from spills of hazardous chemicals  which are
denser than water, sink to the bottom, and mix with and coat the sediments.

     Remedial techniques for contaminated sediments generally  involve sediment
removal and subsequent treatment  and disposal.   During  the removal of
contaminated sediments, it is important to minimize the threat of  further
environmental harm through resuspension of contaminants.  Various  techniques
have been developed to control this problem.  Another aspect of the removal
process involves measures for temporary diversion of water flow.   Measures
such as containment and in-situ treatment offer an alternative to  removing the
sediment.  However, these measures are not well demonstrated.
8.1  Sediment Removal
     The process of removing bottom sediments from a water body  is commonly
known as dredging.  This process has been used for many years to widen or
deepen harbors and navigable waters.  In recent years, dredging has been
employed in the removal of sediments that have been contaminated by hazardous
substances.

     Sections 8.1.1 through 8.1.3 describe the equipment used in the removal
of contaminated sediments including mechanical, hydraulic, and pneumatic
dredging.  Section 8.1.4 addresses design and implementation considerations
including information on predredging operations, dredge vessel control, and
turbidity control.  Dredging equipment is summarized in Section 8.1.5 in terms
of technical feasibility and impacts.  Costs of dredging are addressed in
Section 8.1.6.  Treatment of contaminated sediments generated during dredging
operations is addressed in Sections 10.2 and 8.2.
                                     8-1

-------
     8.1.1  Mechanical Dredging


     Mechanical dredging involves the use of excavation equipment such as
backhoes, draglines, clamshells, and bucket ladder dredges.  Draglines and
clamshells used for dredging are usually vessel-mounted, but can also be
track-mounted and land-based.

     The main advantage of mechanical dredging is removal of sediments at
nearly in-situ densities, therefore maximizing solids content and minimizing
the scale of facilities required for dredged material transport, treatment,
and disposal.  On the other hand, because mechanical dredging removes bottom
sediment through direct application of mechanical force to dislodge the
material, sediment resuspension (and therefore turbidity) is often high.
Also, mechanical dredging is relatively ineffective in the removal of free or
unabsorbed liquid contaminants.  Additionally, mechanical dredging has a
characteristically low production rate.

     Mechanical dredging generally has application in streams and rivers that
are relatively shallow and whose flow velocities are relatively low.  It is
also used for removing contaminated sediments deposited on dry river banks or
in floodplains.
          8.1.1.1  Clamshell Dredge
     Clamshell (or grab) dredges are crane-operated devices.  Most  are
equipped with one crane, but multiple crane configurations are not  uncommon.
The crane  is normally mounted on a  flat-bottomed barge or pontoon,  but may
also be crawler-mounted.  Figure 8-1 illustrates a clamshell dredge.

     Production rates for clamshell dredges are relatively low,  typically in
the range  of twenty to thirty cycles per hour.  This varies with depth and
working media.  The working depth of the clamshell is limited, theoretically,
only by the length of the cable.  In practice, most clamshell dredges operate
at depths  of up to 100 feet.  Clamshell buckets range in capacity  from 1 to
12 cubic yards.  These dredges excavate a heaped bucket of material, part of
which  is washed away by drag forces during hoisting.  Once the bucket clears
the water  surface, additional losses may occur through rapid drainage of
entrapped  water and slumping of the material heaped above the rim  (Hand,
1978).  Loss of material is also influenced by the fit and condition of the
bucket, the hoisting speed, and the properties of  the sediment.  Even under
ideal  conditions, substantial losses of loose and  fine sediment will usually
occur.  To reduce the probability of fines and loose material escaping from
the bucket during the hoisting operation, the Port and Harbor Institute of
Japan  has  designed and fabricated a bucket that is completely closed and
sealed by  flexible gaskets, so that the dredged material is better  contained
within the bucket. This design is illustrated in Figure 8-2.  A  direct
comparison of a standard open clamshell bucket with a watertight clamshell
bucket indicates that watertight buckets generate  30 to 70 percent  less
resuspension in the water column than open buckets (Barnard, 1978).  This

                                     8-2

-------
                                 FIGURE 8-1.
                             CLAMSHELL DREDGE
Source: Hand et al., 1978
                                  FIGURE 8-2.
         OPEN AND CLOSED POSITIONS OF THE WATERTIGHT BUCKET
                                     ฉ COVER


                                     (D COVER
                                        RUBBER  PACKING
                                        ROD
                                        SHCLL
Sourer Barnard. 1978
                                     8-3

-------
design has not been used in the United States, but similar modifications have
been tested here.

     A major criticism of the watertight clamshell is that the gaskets would
not stand up to continuous use in a full-scale dredging operation, limiting
its use to soft material and trash-free areas.  In addition, compatibility
problems may occur in certain chemical spill situations.  Current design
concepts include the use of an interlocking tongue-and-groove edge to overcome
the sealing problems (Barnard, 1978 and Raymond, 1983).


               a.  Applications/Limitations
     Clamshell dredges are adaptable to either land-based or barge-mounted
operation.  They are capable of excavating materials at nearly in-situ
densities, and of excavating almost any type of material except the most
cohesive consolidated sediment and solid rock.  Clamshell dredges are easily
controlled and maneuvered in small and very confined areas, and are capable of
deep-water excavation.  Availability of clamshell dredges is relatively good
in the United States.  Clamshell dredges are the subject of research and
development to improve production efficiency, accuracy, and control, and to
reduce adverse environmental effects.

     One of the greatest problems with clamshell dredges is that they generate
a great deal of sediment resuspension and therefore turbidity.  In addition,
production rate is low.  These dredges are inefficient in terms of losing
material from the bucket during the hoisting operation.  Clamshell dredges
require separate disposal vessels and equipment for operation.  Operation is
limited to use in shallow streams and rivers with low  flow velocity.  High
energy costs are associated with clamshell dredges, and maintenance costs are
also high because of the clamshell's complex machinery (Hand, 1978).


          8.1.1.2  Dragline Dredge


     A dragline dredge is very similar to a clamshell  dredge.  The dragline is
a crane-operated device that is normally mounted on a  flat-bottomed barge or
pontoon.  Like the clamshell dredge, it can also be crawler-mounted.  The
dragline may be used to excavate almost any type of material, just as the
clamshell.

     The primary difference between the dragline and the clamshell is in the
control cable arrangement.  The dragline bucket is loaded by being pulled by a
drag cable through the material being excavated and toward the crane.  By this
arrangement, the dragline offers a longer reach than the clamshell (Merritt,
1976).  The dragline is illustrated in Figure 8-3.  To accommodate the control
cable arrangement, the bucket of the dragline is somewhat different than the
clamshell.
                                     8-4

-------
                                FIGURE 8-3.
                DRAGLINE BUCKET ON TRACK-MOUNTED CRANE
                            HOIST CABLE


                         BOOM
                                              DRAG
                                              CABLE
                                                 BUCKET
                                        Source: Merrin, 1976
               a.  Applications/Limitations
     Because the dragline employs the  same basic  equipment  as  the  clamshell
dredge, its applications and limitations are very similar to those of  the
clamshell.  There are, however, some slight differences.

     Draglines are adaptable to either  land-based or barge-mounted operation,
They are capable of excavating material at nearly in-situ densities  and  are
easily controlled and maneuvered in small and confined areas,  although
somewhat less than the clamshell.  Draglines are  capable of shallow  water
excavation.  Their availability in the  United States is relatively good.

     Major limitations of draglines are that they cause a great deal of
turbidity and sediment resuspension and their production rate  is low.  Like
the clamshell, they are inefficient in  terms of losing material from the
bucket during the hoisting operation and they require separate disposal
vessels and equipment for operation.  They are limited to use  in shallow
streams and rivers with low flow velocity, and are considered  ineffective
against a free or unadsorbed liquid contaminant (Merritt et al., 1976).
          8.1.1.3  Backhoes
     Backhoes are normally used for trenching and for other  subsurface
excavation where it is expedient to keep the excavator at original ground
level.  Backhoes are mechanically or hydraulically operated  in  a drag and
hoist maneuver.  They are usually crawler-mounted, although  they can be
barge-mounted.  The lateral and vertical reach of a backhoe  is  limited by  the
                                     8-5

-------
length of the boom.  Conventional backhoes are capable of digging to a depth
of about 40 feet.  Extended backhoes ate also available and can dig to depth
of up to 80 feet.

     Because of the limited lateral and vertical reach of backhoes, they are
not often used for the removal of contaminated sediments.  However, avail-
ability of backhoes is excellent.  They are also capable of excavating almost
any type of material, and are easily controlled and maneuvered in small and
confined areas.  On the other hand, backhoes share the limitations of other
mechanical dredging terchniques, such as low production rate and requirements
for separate disposal vessels and equipment.

     Backhoes and other conventional excavating equipment are discussed in
greater detail in Chapter 7.
          8.1.1.4  Bucket Ladder Dredge


     The dredging action of the bucket ladder dredge (Figure 8-4) is provided
by an inclined submersible ladder which supports a continuous chain of buckets
that rotate around pivots at each end of the ladder.  As the buckets rotate
around the bottom of the ladder, they scoop up the sediment which is then
transported up the ladder and dumped into a storage area as the buckets round
the top pivot.  Most bucket dredges are mounted on pontoons and are not self-
propelled.  Only four of these dredges are known to be operating in the United
States (Hand et al., 1978).
               a.  Applications/Limitations
     Bucket ladder dredges are most commonly used  in mining operations  such  as
sand and gravel production.  Production rates are  generally higher  than for
other types of mechanical dredges, and they can handle many different kinds  of
material.  Bucket ladder dredges can also  load barges.  This  is  an  important
factor in cases where dredged material must be transpsorted over  long
distances to a disposal site.  Bucket volumes range from 2.8  to  36  cubic feet.
The average dredging depth of the bucket ladder is 60 feet but some  can go as
deep as 100 feet (Hand et al., 1978).

     The major limitations of the bucket dredge is the high degree  of
turbidity generated by the mechanical agitation of sediments  and  bucket
leakage.  Bucket ladder dredges require a  great deal of support  equipment (for
boats and barges), and require a complicated configuration of mooring lines.
The relative unavailability  in the United  States make bucket  dredges unlikely
candidates for dredging of hazardous materials (Hand et al.,  1978).
                                      8-6

-------
                                   FIGURE 8-4.
                                BUCKET LADDER
     Source: Hand et al., 1978
     8.1.2  Hydraulic Dredging
     Hydraulic dredges remove and transport  sediment  in  liquid  slurry form.
Slurries of 10 to 20 percent solids by wet weight  are common  in standard
hydraulic dredging operations.  The slurries may be pumped  many thousands  of
feet through floating or pontoon-supported pipeline to a  dredged material
treatment/storage area.  Hydraulic dredges are usually barge-mounted  and carry
diesel- or electric-powered centrifugal pumps with discharge  pipes  ranging in
size from 6 to 48 inches in diameter.  Unlike mechanical  dredges,  they can be
used in waters with appreciable flow velocity.

     The suction end of a hydraulic dredge is mounted on  a  moveable ladder
which may be lowered or raised to a specified dredging depth.   Often,  the
suction end of the dredge is fitted with a cutterhead to  assist in  cutting.

     The major disadvantage of hydraulic dredges is a large flow rate  asso-
ciated with pumping at low solids concentrations,  resulting in  the  need for
large areas of land to serve as settling/dewatering areas for dredged
material.  Recently, emphasis in research has been in the development  of
hydraulic dredges which are capable of removing sediments at  near  in-situ
solids concentrations, minimizing the water  content of the  pumped  slurry,  and
thereby lowering the land requirements for sediment dewatering.  Another area
of emphasis in dredge design is in the development of cutterheads which offer
low turbidity generation characteristics through the use  of shrouds and other
auxiliary features.  Hydraulic dredges include plain suction, cutterhead,
dustpan, and hopper.
                                     8-7

-------
          8.1.2.1  Plain Suction Dredge
     The plain suction dredge is the simplest of all hydraulic dredges.   It
relies solely on the suction generated by the centrifugal pump to dislodge,
capture, and transport the excavated slurry.  The dredge head is attached to
the end of a ladder and its position is controlled vertically and horizontally
by the movement of cables attached to the ladder.  Figure 8-5 illustrates a
plain suction dredge.  During normal operations, material with solids contents
of 10 to 15 percent by weight are drawn from the bottom up through  the  suction
line and discharged into a scow or through a pipeline to a nearby disposal
site.  The production rate of suction dredges depends upon the pump size,  pump
horsepower, and type of material being dredged.  During normal working
conditions, dredging is performed at 1,000 to 10,000 cubic yards per hour,
depending on the discharge velocity and pipe diameter (Hand et al.,  1978).

     Plain suction dredges are normally pulled along a straight line fixed by
a cable-and-winch arrangement anchored on land or on the bottom of  the  water-
course.  The dredge vessel moves along the line of the cable, and the cable  is
repositioned to establish a new line as dredging progresses.  They  have no
capability for lateral manipulation beyond the positioning and movement of the
dredge vessel.  Vertical control of sediment removal is maintained  by raising
and lowering the suction pipe and dredge head supporting ladder using a cable-
and-winch arrangement (Hand et al., 1978).
                                 FIGURE 8-5.
                            PLAIN SUCTION DREDGE
                                                                       LWK
                                                                 Source: Hand, 1978
                                      8-8

-------
               a.  Applications/Limitations


     Plain suction dredges are effective  in  the  removal  of  relatively  free
flowing sediments such as sands, gravels, and unconsolidated material,  and  can
operate without difficulty in deep waters.   The  most  advantageous  features  of
the plain suction dredge are its high production rate  and its  ability  to
discharge directly to disposal areas, thus eliminating the  need  for  extra
equipment.

     Plain suction dredges are ineffective against hard  and cohesive materials
such as clays and native bottom sediments, as they employ no mechanical
dislodging devices.  Although plain suction  dredges are  capable  of dredging
large volumes of material, this material  is  80 to 90  percent water.  This
demands extensive dewatering and consolidation of the material prior to
disposal.  Plain suction dredges should not  be operated  in  rough waters.
Additionally, the anchoring cables and pipelines often cause obstructions to
river traffic.  The suction line is subject  to blockage  or  damage by under-
water debris.  There are about two dozen  plain suction dredges operating in
the United States (Hand et al., 1978).
          8.1.2.2  Cutterhead Dredge


     The cutterhead  is probably the most efficient  and versatile  dredge  of
all.  Its configuration is similar to  the plain  suction  dredge, except that  it
is equipped with a rotating cutter apparatus  surrounding the  intake  end  of  the
suction pipe.  This device, known as the cutterhead, rotates  to dislodge
sediment and allows  transport of sediment by  suction to  the suction  pipe.
Slurries of 10 to 20 percent solids by weight are typically achieved,
depending upon the material being dredged (Hand  et  al.,  1978).  Figure 8-6
illustrates a cutterhead dredge.

     Cutterhead dredges move in a pattern different from other hydraulic
dredges by alternately anchoring on one of two spuds.  The anchored  spud  is
used as a pivot and  the vessel is drawn along an anchored cable,  thus swinging
the cutterhead in a short horizontal arc about the  spud.  Repeated swinging of
the cutterhead arcs while alternating anchored spuds results  in partially
overlapping cuts which form a wide effective cut through the  area being
dredged (Hand et al., 1978).


               a.  Applications/Limitations


     The cutterhead's efficiency and versatility are the features that place
it among the most popular dredges in the world.  Cutterhead dredges  are  the
workhorses of the U.S. dredging fleet with close to 300  in use nationwide
(Hand et al., 1978).
                                     8-9

-------
                                  FIGURE 8-6.
                             CUTTERHEAD DREDGE
                                                        "A" FRAME
                                                                     CUTTEMHEAO

                                                                  Source: Hand, 1978
     The cutterhead can efficiently dig and  pump  all  types  of  alluvial
materials or compacted deposits such as clay or hardpan.  The  larger and more
powerful machines are used to dredge rock-like  formations such as  coral and
the softer type of basalt and limestone without blasting.   The cutterhead is
capable of constructing level bottoms  and  finishing  slopes  efficiently.

     A properly designed cutterhead will cut and  guide  the  bottom  material
toward the suction efficiently, although the cutting  action and the turbulence
associated with the rotation of the cutterhead  resuspend  a  portion of the
bottom material.  The ability of  the dredge's suction to  pick  up bottom
material determines the amount of cut  material  that  remains on the bottom or
is resuspended (Raymond, 1983).

     Little experimental work on  cutterhead  resuspension  has been  done.  Field
studies have revealed that suspended solids  concentrations  are highly variable
within 10 feet of the cutter, but may  be as  high  as  a few tens of  grams per
liter.  These concentrations decrease  exponentially with  depth from the cutter
to the water surface.  Near-bottom suspended solids  concentrations may be
elevated to levels of a few hundred milligrams  per liter  at distances of
1,000 feet from the cutter (Raymond, 1983).
           8.1.2.3   Dustpan  Dredge
     The  dustpan  dredge is  a hydraulic suction dredge which features a widely
 flared  dredging head  along  which are mounted high-pressure water jets.  These
 jets loosen  and agitate the sediments which are then captured in the dustpan
                                      8-10

-------
head as the dredge itself is winched forward into the excavation.  Dredge
material slurries with solids contents of 10 to 20 percent by weight  are
common with dustpan dredges (Raymond, 1983).  A dustpan dredge  is  illustrated
in Figure 8-7.


               a.  Applications/Limitations
     The dustpan dredge works best in free-flowing granular material.  The
high pressure jetting action may improve efficiency slightly by  loosening
cohesive deposits.  Production rates for dustpan dredges are high, about the
same as for plain suction dredges (Raymond, 1983).

     Considerable resuspension of fine-grained sediments may result  from the
jetting action of the dustpan dredge (Hand et al., 1978).  The Norfolk
District of the Corps of Engineers conducted a demonstration project  in 1982
using a modified dustpan head (without water jets) to dredge the fine-grained
sediments of the James River in Virginia.  It was hoped that the dustpan head,
using suction only, could excavate thin layers of the contaminated clay
sediment with less resuspension than a cutterhead.  The dustpan  head, however,
experienced repeated clogging and produced at least as much resuspension as a
cutterhead operating in the same material (Raymond, 1983).  Availability of
the dustpan dredge is limited; there are about one dozen duspan  dredges in the
United States.  All of them are owned by the U.S. Corps of Engineers  and are
used primarily for channel maintenance in interior waterways.
          8.1.2.4  Hopper Dredges


     Hopper dredges (Figure 8-8) differ from other hydraulic dredges  primarily
in the type of vessel used and the methods of attachment and operation of  the
dredge head.  Hopper dredge vessels are normally  large, self-propelled,  sea-
going vessels, rather than barges.  They are positioned and moved by  the
propeller/rudder navigating- equipment of the host vessel.

     The suction pipes are hinged on either side of the vessel and extend
downward toward the stern of the vessel.  The dredge heads, attached  at  the
end of the suction pipes, drag along the bed of the area being dredged as  the
vessel moves forward; the head is sometimes called a "trailing" head  for this
reason.  Dredging is accomplished by the vessel making progressive passes  over
the project area.  Dredged material is transported up the suction pipe and is
discharged for storage into the hopper of the vessel.  Coarse-grained material
settles to the bottom of the hopper and water and fine-grained sediment  is
normally allowed to overflow the hopper into the water course.  (Overflow
would usually be unacceptable in the removal of contaminated sediments.)   Once
fully loaded, the vessel moves to an unloading area where emptying of the
hopper is accomplished by opening bottom doors or by pumping the contents  to a
treatment on disposal area.  There are 15 ocean-going, trailing suction hopper
dredges operated by the Corps of Engineers as well as several privately-owned
vessels (Barnard, 1978, and Raymond, 1983).

                                     8-11

-------
    FIGURE 8-7.
DUSTPAN DREDGE
                                      "A" FRAME:
                                       Source: Hand, 1978
     FIGURE 8-8.
  HOPPER DREDGE
          DRAG
                         PUMPS
                                      Source1 Hand. 1978
       8-12

-------
               a.  Applications/Limitations


     Hopper dredges are intended for maintenance dredging  for deep, rough-
water shipping channels, and are normally most efficient in excavating  loose,
uncohesive materials.  They can reach sediment up to 62 feet deep  and,  when
fully loaded, draft in the range of 13 to 24 feet.  Therefore, hopper dredges
are limited to dredging of deep harbors and off-shore water courses.  A hopper
dredge is capable of operating in rough, open waters; in relatively high
currents; in and around marine shipping traffic; and in adverse weather
conditions (Hand et al., 1978).

     Field data confirm that the suspended solids levels generated by a hopper
dredge operation are primarily caused by hopper overflow in the near-surface
water and draghead resuspension in near-bottom water.  Suspended solids
concentrations may be as high as several tens of grams per liter near the
discharge port and as high as a few grams per liter near the draghead.
Suspended sediment levels in the near-surface plume may exceed background
levels even at distances in excess of 3,600 feet (Barnard, 1978 and Raymond,
1983).
          8.1.2.5  Portable Hydraulic Dredges


     Portable hydraulic dredges are defined as dredge vessels which can be
moved easily from one job site to the next over existing roadways without
major dismantling.  The U.S. Army Corps of Engineers Waterways Experiment
Station has prepared a "Survey of Portable Hydraulic Dredges" (Clark,  1983),
which is a compilation and assessment of models of portable dredges available
in the United States.  Conventional cutterheads, horizontal cutters, bucket
wheel, chain cutters, vertical cutters, and dustpans are available on  portable
dredges, and have dredging depth capabilities ranging from 10 to 50 feet.
Among the manufacturers of portable dredges are:  Mud Cat; Vaughn-Maitlen
Industries (VMI); Ellicott Machine Corporation International; Eagle Iron
Works; W&S Development, Inc.; American  Marine & Machinery Company, Inc.,
(AMMCO); Quality Industries, Inc.; Dredge Masters International (DMl); Delta
Dredge and Pump Corporation; Mini Dredge, Ltd.; General Conveyors Limited
(GENFLO); Kenner Marine and Machinery, Inc.; and Waterless Dredging Company.

     An example of the most commonly used portable dredge, a Mud Cat,  is shown
in Figure 8-9.   It is available in several models with depth capabilities up
to 15 feet.

     The Mud Cat is pontoon-mounted and features a horizontally mounted,
auger-like cutting device that feeds the sediment to the suction intake of a
diesel-driven centrifugal pump.  The auger is mounted along the base of a
bulldozer-type blade.  The whole arrangement with suction pipe attached is
controlled by a hydraulic boom.  The dredge is moved along on an anchored
cable during each traverse of the excavation, and the dredge material  is
discharged ashore through a float-supported pipeline.  The width of the cut is
approximately 8 feet, and applications to date have included dredging  of small

                                     8-13

-------
                                    FIGURE 8-9.
                           PORTABLE HYDRAULIC DREDGE
            • DISCHARGE
               LINE
                                                                    ANCHOR UNE
Source: Hand et al., 1978
 reservoirs and streams.  There are several hundred Mud  Cat  dredges  owned and
 available for lease from the National Car Rental Agency.

      Vaughn Company, Inc., and Mud Cat have developed the Vaughn  Lagoon
 Pumper, a highly portable electric pumping unit mounted  on  a  platform between
 two polyethylene floats.  The unit was proved an efficient,  inexpensive means
 of removing settled solids from industrial and organic  ponds  with less
 dilution and lower waste hauling and disposing costs. (Mud  Cat,  1983).  The
 unit is 7-1/2 feet wide, 18 to 24 feet long, and weighs  4,500 pounds.   It
 features a chopper pump that is capable of dredging  sludges,  weeds, peat,
 silt, and organic material.  Like the Mud Cat, the Lagoon Pumper  is driven by
 a winch-and-cable arrangement and can be equipped  for either  on-board
 operation or on-shore remote control (Vaughn Co.,  Inc.,  1985).
                a.  Applications/Limitations
      Portable dredges are particularly  applicable  to  contaminated sediment
 remediation projects in relatively isolated  (in  terms of navigation)  water
 bodies such as lakes and inland rivers.  Portable  dredges also  character-
 istically have low depths of vessel draft  (less  than  5 feet  and many  less than
 2 feet), allowing them to be used in  shallow-water applications (Vaughn Co.,
 Inc., 1985).

      A series of tests on the Mud Cat sponsored  by EPA in the 1970s,  showed
 that resuspension of the sediment was low  and  the  resuspension  plume  imparted
 to the surrounding water during dredging was confined to within 20 feet of the
                                       8-14

-------
dredge  (Hittman,  1974).  The Mud  Cat was  also  found  to  be  very efficient  in
removing simulated hazardous material  (powder,  fine  glass  beads}  filings,  and
coal),  removing 99.3  percent from the  sediments of a test  pond (Hittman,
1976).

     The Vaughn Lagoon Pumper  can operate  in 1.5  feet of water and  can remove
materials to depths of 11  feet.   Pumping  capacity is up to 100 gallons per
minute  and 150 feet of discharge  head  (Mud  Cat, 1983).  The scale of the
Lagoon  Pumper offers  a compromise between  hand-held,  abovewater vacuum dredges
and the conventional  portable  hydraulic dredges.

     The primary  limitations of portable dredges  is  their  size.   Small size
restricts portable dredges to  low production rates,  which  limit them to
small-scale operations.


          8.1.2.6  Hand-Held Hydraulic Dredges


     A variety of hand-held dredges have been adapted from equipment designed
for other applications.  Hand-held dredges  remove a  mixture of sediment and
water in a slurry.  They may be used either abovewater  or  underwater.

     Underwater hand-held  dredges are  normally operated by divers.   The
equipment employed can range from a hose-and-collector  arrangement  to  skid-
mounted, high-production machines used for mineral recovery and maintenance at
off-shore platforms.  Abovewater,  hand-held dredges  are normally  used  by
operators wading  into shallow  waterways or  from small water craft.   Cleanup of
PCB-contaminated  sediments in  the  South Branch of the Shiawassee  River in
Michigan was accomplished  largely by vacuum dredging with  hand-held  hoses
controlled by wading operators.   Vacuum trucks were  used as the source of
vacuum  and for temporary storage  and transport of dredged  slurry.   Vacuum
hoses extended from the shore-based trucks to the areas being  dredged.  Also,
a relatively simple vacuum unit employing diaphragm  sludge pumps  was used  by
the EPA Region X  Inland Regional  Response Team to remove PCB-contaminated
sediments from the Duwamish Waterway in Washington (Willmann,  Blazevich and
Snyder, 1976).

     Dredging equipment has also  been  specially designed for operation by
divers although it has not been used in hazardous waste site remediation.
Alluvial Mining and Shaft  Sinking  Co., Ltd., a British  dredging engineering
and manufacturing firm, manufactures diver-operated  airlift dredges  and a
vibrating hydraulic "clay spade"  for removing cohesive  sediments  which are
both shown in Figure 8-10  (Hand et al., 1978).


               a.  Applications/Limitations
     The major applications of hand-held hydraulic dredges is for small-volume
projects in relatively calm waters where precision dredging is important.
Hand-held dredges can be quickly designed and assembled from off-the-shelf
equipment (Hand et al., 1978).
                                     8-15

-------
                                           FIGURE 8-10.
                            DIVER-OPERATED HAND-HELD DREDGES
            AIRLIFT DREDGE
WATER JETTING LINE
                          DISCHARGE HOSE
                            AIR HOSE
                           NEGATIVE PRESSURE
                           RELIEF VALVE
                          ^- CONTROL HANDLES

                          	 RISER TUBE

                          AIR SUPPLY LINE
   JETTING NOZZLE	HZ..,
                        REMOVABLE SUCTION FOOT
                                                               CLAY SPADE DREDGE
                                                    SUPPORT LINE
                                                    TO AIR BAG
                                                                                       SUCTION PIPE
                                                                             VIBRATOR UNIT
                                                                             Source: Alluvial Mining, 1984
                                              8-16

-------
     Abovewater units are limited  to  shallow  or dewatered  water  bodies.
Resuspension of contaminted sediments  is aggravated by wading  operators  or
divers disturbing bottom sediments  (Hand et al.,  1978).


          8.1.2.7  Waterless Dredge


     The Waterless dredge, developed  by Waterless  Dredge Company,  was  designed
for removal of sludges  from lagoons at a minimum water content.   Special
components of the dredge include a  shrouded "roll-over" cutterhead and a
submerged dredge pump.  The cutterhead is open  and fills with  sediment (or
sludge).  The sediment  displaces water in the cutterhead and blocks entry of
water into the dredge pump inlet,  and  only sediment is pumped.   At the limit
of the swing to the left, when the bow of the dredge  begins  to swing to  the
right, the cutterhead rolls down and  over 180 degrees so that  the  face of the
cutterhead is open to receive sediment and repeat  the process.  The dredge
reaches depths up to 16 feet, and  the Waterless Dredge Company claims  that
pumped slurry contains  less than 10 percent excess water,  by volume (World
Dredging and Marine Construction,  1980).


               a.  Application/Limitation


     The Waterless Dredge was used  to  remove  lead-contaminated sediments from
the Mill River in Connecticut.  Resuspension  and  resettling of contaminated
sediment was apparently of sufficient magnitude to warrant a second dredging
of recontaminated areas (York Wastewater Consultants, 1983).


     8.1.3  Pneumatic Dredging


     Pneumatic dredges  are treated as  a distinct  category  from hydraulic
dredges only because of their novelty  in this country.  Originally developed
in Italy under the trade name Pneuma,  these systems feature a  pump that
operates on compressed  air and hydrostatic pressure   to draw sediments to the
collection head and through the transport piping.  Otherwise,  they are no
different than hydraulic dredges.  There are  several different so-called
pneumatic dredges, including the airlift, the pneuma, and  the  oozer.
Pneumatic dredges can be operated in  shallow  or deep water with  no theoretical
maximum depth, and can  be relatively  easily dismantled and transported by
truck or air.  Pneumatic dredges may be able  to yield denser slurries  than
conventional hydraulic  dredges with lower levels of turbidity  and  resuspension
of solids (Hand et al., 1978).

     One of the major limitations of  the pneumatic dredges is  that they  are
capable of only modest  production rates (up to  390 cubic yards/hour).  Another
problem is that cables  and pipelines  present  temporary obstructions in
navigable water channels.   Pneumatic  systems  are not in widespread use in the
United States, and may  not be as readily available as other types.

                                     8-17

-------
          8.1.3.1  Airlift
     Airlift dredges use compressed air to dislodge and  transport  sediments.
Compressed air is introduced into the bottom of an open vertical pipe, usually
controlled and supported by a barge-mounted crane.  As the air  is  released,  it
expands and rises, creating upward currents which carry both water and sedi-
ment up the pipe.  The applied air pressure must be sufficient  to  overcome  the
hydrostatic pressure at operating depths.  Higher air pressures and  flow  rates
result in higher transport capacity.  Air can also be introduced through  a
special transport head which can be vibrated or rotated  to further dislodge
more cohesive sediments.  Slurries of 1:3 solid/liquid ratio can typically  be
achieved with airlift dredges (d'Angremond, 1978).

     Airlift dredges are crane-supported and can be mounted on  barges, and
sea-going vessels, as well as dockside.  Lateral control  is achieved by
swinging the boom of the crane in a manner similar to mechanical dredging.
Vertical control is achieved by raising and lowering the  open end  of the
vertical transport pipe and by varying the pressure of the air  released  at  the
end of the pipe  (Hand et al., 1978).


               a.  Applications/Limitations


     The primary advantage of the airlift dredge is that  it provides
continuous transport of material, thus maximizing production rate.   The
primary limitation is that sufficient depth must be available in order to
build up enough  air pressure for operation.  The minimum dredging  depth  for
economical operation is about 20 to 30 feet (Hand et al.,  1978).


          8.1.3.2  Pneuma Dredge


     The Pneuma  dredge (Figure 8-11) consists of a pump  which is lowered  by a
crane into the sediments being dredged.  The pump is driven by  compressed air
and operates by  positive displacement.  The body of the  pump contains three
cylindrical vessels, each with an intake opening on the  bottom  and an air port
and a discharge  outlet on top.  The air ports can be opened to  the atmosphere
through air hoses and valves.  The three cylinders operate in parallel,  each
one-third cycle  ahead and behind the other two  cylinders,  and controlled  by an
air distributor  located on the control vessel (Richardson, 1982).

     Pneuma dredges are normally suspended from a crane  cable and  pulled  ahead
into the sediments being dredged by a second cable.  The dredge head is
essentially fixed relative to the vessel so that lateral  manipulation of  the
dredge is limited to the positioning and movement of the  vessel.
                                      8-18

-------
                                FIGURE 8-11.
                              PNEUMA DREDGE
                                                              Source: Hand. 1978
               a.  Applications/Limitations
     Though Pneuma dredges are most applicable to  loosely  consolidated
sediments, the intake openings can be fitted with  shovel attachments  to  aid  in
penetration of sediments.  Extremely deep applications  are possible,  limited
by vertical and lateral controllability and air pressure requirements.   They
are capable of delivering a slurry of high solids  content  with minimal
turbidity generation.  Tests showed that the pneuma pump was  able  to  dredge  at
almost in-situ density in a loosely compacted, silty clay  typical  of  many
estuarine sediments while generating a low level of turbidity (Richardson,
1982).  Though not small, Pneuma dredges are relatively easily dismantled and
transported by truck or air.  The operation of the Pneuma  is  partially
dependent upon hydrostatic pressure, and this may  limit its effectiveness in
shallow water (Richardson, 1982).  Another limitation is that Pneuma  dredges
have limited availability in the United States.

     As a pure pumping device, the Pneuma pump has a very  low power efficiency
compared with a conventional centrifugal pump.  Efficiencies  in pumping  sand
or silty clay are less than 20 percent and often less than 10 percent
(Richardson, 1982).
                                     8-19

-------
     Pneuma dredges are also only capable of modest production rates (up  to
390 cubic yards per hour), and the cables and pipelines present temporary
obstructions in navigable water channels (Richardson, 1982).


          8.1.3.3  Oozer Dredge


     The Oozer dredge, developed in Japan, consists of a pump similar  in
concept to the Pneuma.  It uses negative (vacuum) pressure in the  filling
chambers and atmospheric pressure when dredging in the shallow waterways.  The
pump is usually mounted at the end of a ladder.  The pump body consists of two
cylinders to which a vaccum is applied to increase the differential pressure
and flow between the sediment and the cylinders.  Sediment thickness detec-
tors, underwater television cameras, and a turbidimeter are attached near the
suction mouth for monitoring.  Suspended oil can be collected by an attached
hood, and cutters can be attached for dislodging hard soils (Barnard,  1978 and
Toyo Construction, Co., Ltd., undated).

     Oozer dredges are normally pulled along a  straight line fixed by  a cable-
and-winch arrangement anchored on land or on the bottom of the watercourse.
The dredge vessel moves along the line of the cable, and the cable is
repositioned to establish a new line as dredging progresses.


               a.  Applications/Limitations
     The Oozer dredge is capable of operating at depths up to 60  feet.   Toyo
Construction Co., Ltd., of Tokyo claims slurries of 30 to 70 percent  solids
content can be achieved without significantly increasing turbidity or  causing
resuspension (Barnard, 1978 and Toyo Construction Co., Ltd., undated).

     Moderate production rates and obstruction of waterway traffic are
limiting factors for Oozer dredges.  In addition, they have no capability  of
lateral manipulation beyond the positioning and movement of the dredge vessel.
Vertical control of sediment removal is maintained by raising and lowering the
suction pipe and dredge head supporting ladder using a cable-and-winch
arrangement.  The availability of Oozer dredges is limited in the United
States.
     8.1.4  Implementation of Dredging Operations


     This section describes predredging activities, dredge vessel control,  and
turbidity control.
                                     8-20

-------
          8.1.4.1  Predredging Operations


     Predredging operations  consist  of  a variety  of  tasks  that  are  conducted
prior to and  in preparation  for  the  actual dredging  project.  Predredging
operations may include  site  surveys,  site operation  plans,  equipment  mobil-
ization and demobilization,  stream diversion,  cofferdam  construction,  weed
harvesting, and bottom  snagging.


               a.  Stream Diversion
     In some contaminated sediment areas, complete hydraulic  isolation  of
sediments may be desirable so that dewatering  followed by dry excavation may
be implemented, or so that hydraulic dredging  may be  conducted  in  a  contained
environment.  To accomplish stream diversion,  all or  part of the flow is
diverted by cutting off a section of the stream, diverting  flow to a pipe  or
excavated channel, and allowing the flow to re-enter  the stream channel at a
point further downstream.  Stream diversion may be accomplished by placement
of cofferdams (described in the next section), and may be temporary  or
permanent.  Generally, permanent diversion is  practical only for very small
streams.

     The Environmental Emergency Response Unit, EPA,  Edison, NJ, has developed
a mobile stream diversion unit for such operations.   The unit consists of
submersible pumps, booster pumps, generators,  a crane, and  an aluminum
irrigation pipe with ancillary fittings.  The  system  is capable of pumping
5600 gallons per minute over a distance of 1000 feet  over level terrain.
Additional capacity is available with supplemental piping and pumps.


               b.  Cofferdams
     Cofferdams can be built around a contaminated area in a waterbody to
isolate that area from stream flow.  The area can then be dredged, dewatered,
and excavated, or capped with low permeability material.  Cofferdams are most
easily constructed for flow containment of shallow ports, streams, and rivers,
or waters with low flow velocities.  Where flow velocity exceeds 2 feet per
second, cofferdam construction is not recommended because of the difficulty of
driving sheet piling under these conditions.  Cofferdam construction is fea-
sible for some relatively wide and deep rivers (up to about 10 feet), pro-
viding that the velocity of flow is not excessive.

     Cofferdams may be constructed of many materials, such as soil, sheet
piling, earth-filled sheet pile cells, and sand bags (for short duration
structures).  Sheet pile cofferdams are generally constructed of black steel
sheeting from 5 to 12 gauge in thickness, and from 4 to 40 feet in length.
                                     8-21

-------
     For additional corrosion protection, galvanized or aluminized coatings
are available.  Cofferdams may be either single walled or cellular, earth-
filled sections.  Single wall cofferdams may be strengthened by an earth  fill
on both sides.  They are most suited to shallow waters.  For depths greater
than 5 feet, cellular cofferdams (circular sheet pile cells filled with earth)
are recommended (Linsley and Franzini, 1979).

     Sheet pile cofferdams may be installed in pairs across streams to tempo-
rarily isolate areas of contaminated sediment deposition, and allow access for
dewatering and excavation.  This operation may be required for streams or
riverbeds in which contaminated sediments have been deposited completely
across the channel cross-section.  Such construction requires that the entire
streamflow be temporarily diverted through the excavation of a bypass channel,
and installation of corrogated metal piping of sufficient diameter to handle
stream flow.  Such an arrangement is illustrated in Figure 8-12.  Alter-
natively, a single curved or rectangular cofferdam may be constructed to
isolate an area along one bank of a stream or river.  This method only
partially restricts natural flow and does not necessitate construction of a
temporary diversion (bypass) channel to convey entire flow around the area of
excavation.  The single cofferdam design is illustrated in Figure 8-13.

     For small narrow streams, sheet piling may be driven by hand with light
equipment such as a hand maul or a light pneumatic hammer.  For wider, deeper
streams where longer sheeting is required and access may be difficult, heavy
driving equipment such as a drop hammer or a pneumatic or steam pile driver is
necessary.  Preassembled (interlocked) sections of sheeting are positioned and
driven with the use of a crane for wide, deep rivers.  The crane may be
operated from a barge.  A preconstruction geologic site investigation may be
necessary to ensure that bedrock or impervious strata will not interfere with
the pile-driving operation.

     The length of sheet piling required for cofferdam construction depends on
the stream depth, velocity of flow, and nature of the soil into which the
sheeting is driven.  In general, the ratio of exposed length of sheeting  to
driven length (unexposed, anchored into soil) should be about 1:1, with 1 to
3 feet of freeboard above the water surface.  For example, to construct a
cofferdam on a 5-foot deep river requires sheeting approximately 12 feet  long:
 5 feet driven, 5 feet exposed to flow, and 2 feet freeboard.  A greater
length may be required if a layer of soft, muddy, or unconsolidated sediments
overlies the stable soil stratum into which the sheeting must be driven.

     For excavation of contaminated sediments deposited along only one side of
the channel, a single curved or jointed cofferdam can be installed to isolate
the construction area from streamflow.  Such an installation will partially
restrict natural flow, creating an increased water level and higher velocity
of flow within the restricted area of the channel.  To prevent bank overflow
and excessive erosion resulting from this restricted flow, it is recommended
that a sheet pile containment wall be driven along the opposite bank in the
area of restricted flow.  Both the cofferdam and sheet pile reinforcement wall
                                     8-22

-------
                         FIGURE 8-12.
   STREAM FLOW DIVERSION FOR SEDIMENT EXCAVATION USING
          TWO COFFERDAMS AND DIVERSION CHANNEL
              Temporary sheet-pile;
              remove after pipeline construction
                                        s ROW
                                         ฃ
                            Zฃฃฑฃฃ Upstream cofferdam ฃฑjbc
Diversion
channel;
excavate, place
corrugated metal
pipe or similar
conduit
Sediment
dewatering
and excavatio
                                  Downstream cofferdam
          Temporary
          sheet-pile
         Riprap for
         outlet protection
                            8-23

-------
   i
   cc
   UJ
   UL
   U.
   o
   u

   a
   o
   Z
   55
   o
   z
   CO
   3

   Z
   o
UJ

DC
u. •ฃ

   O
   UJ
   CO

   cc
   o
   u.


   o

   CO
   cc
   UJ
   5

   I
   UJ
   oc
                                                      O5  J
                                                         l
                                                                                              
-------
 can be  pulled when  sediment  excavation  has  been  completed,  and  re-installed
 further downstream  if  additional  sediment removal  is  required.

     Areas enclosed by cofferdams may require  dewatering  if infiltration leaks
 occur through joints in  sections  of  sheet piling,  or  if excessive  precip-
 itation occurs during  excavation  activities.   Dewatering  can be accomplished
 with single-stage centrifugal  pumps, which  are available  in sizes  that  can
 pump up to 5,000 gallons  per minute  (Richardson  Engineering Services,  1980).
 Natural drainage and evaporative  drying may be sufficient to dewater  small
 areas, but this may require  too much time.  Streambed sediments isolated by
 cofferdams must be  sufficiently dewatered before excavation of  the
 contaminated sediments can be  performed efficiently.
                c.   Snagging


     Snagging  involves  the removal  of  stumps,  logs,  rubbish,  rock debris,  and
any other objects that might obstruct  or damage  dredging equipment.   Snagging
operations are  usually  carried out  with a  crane  and  clamshell  or  orange-peel
grapple.  The  crane may be barge- or crawler-mounted, depending on the  access-
ibility to the  dredge area.  In  some cases,  infestations of aquatic  weeds  may
obstruct dredging and cause delays  because of  reduced cutterhead  mobility  and
dredge pump clogging.  Mud Cat has  developed an  aquatic weed  harvester  which
can be used to  remove aquatic weeds that would obstruct the dredging.   Remote
sensing and diver survey operations may be required  as a prerequisite to
locate submerged objects for snagging.

     Diver assistance has been required in many  snagging operations  to  secure
the grapple to  debris in deep water.   Also, many activities relating to damage
assessment, containment/cleanup  activities,  environmental  assessment, and
research studies require that divers enter contaminated environments.
Experiences in  these environments have often resulted in injuries (primarily
chemical burns) to divers and/or surface support personnel.   Little  infor-
mation is available on  the effects  of  low  level  or chronic exposure  to  these
chemicals (McLellan, 1982).


          8.1.4.2  Dredge Vessel Control


     Precision  control is needed to ensure accurate  and efficient  removal  of
sediments and minimization of resuspension and transport of contaminants.
Types of controls discussed in this section  are  dredge vessel  positioning,
monitoring, and control of dredge cut.
                                     8-25

-------
     The positioning of floating dredge vessels can be considered as gross
control over the lateral extent of sediment removal.  Positioning and movement
of the dredge is generally accomplished using one or more of the following
methods:
     •  Spud anchoring

     •  Cable-and-winch movement

     •  Self propulsion (e.g., propellers)
     •  Towing.


     Lateral and vertical control of the dredging of submerged sediment  is
necessary to ensure that sediment, within identified limits of contamination,
is removed, and to minimize over-dredging and resultant costs associated with
handling, treatment, and/or disposal of excess material.  Precision in
dredging is largely dependent upon:  (1) the extent to which the dredging
equipment can be manipulated (control), and (2) the extent to which the  dredge
operator is aware of the actual cut achieved (monitoring).  The necessary
precision required for a given sediment removal situation depends upon the
types of contaminants, the lateral and vertical extent of contamination, and
the presence of obstacles such as boulders or marine structures.  The degree
of precision obtainable varies with the dredge equipment.  Table 8-1, at the
end of this section, summarizes the precision attainable  for various types  of
dredges.


     Operators of dredging equipment must receive "feedback" information in
some form in order to judge whether the intended extent of sediment removal
has been achieved.  Visual observations may suffice in some shallow water
situations.

     However, in many applications, the use of electronic monitoring and
control equipment can better provide the operator with information and
operating flexibility that is needed in removing contaminated sediments.

     Various instruments are capable of providing control or information
aiding manual control for the following functions:


     •  Dredge vessel location and orientation

     •  Dredge head location and  depth

     •  Depth of cut

     •  Locations of obstacles
     •  Slope dredging.
                                      8-26

-------
     A variety of vessel location-determining systems are  available  and  in  use
in dredging applications.  Most use radio signals or laser beams  to  determine
the vessel's position by triangulation from two or more on-shore  reference
points, although a laser system which requires only one on-shore  station is
available (Wentzell, 1983).  With the assistance of a minicomputer,  one  system
is capable of determining the coordinates of the vessel's  position,  within
3 feet, in one second (O'Donnell, 1980).  Course deviation meters, which
indicate the magnitude and direction of the vessel's deviation  from  a  pre-
determined course, are also in use.  Another system displays  the  vessel's
lateral orientation relative to the heading of a predetermined  course, and  the
distance remaining to the end of a predetermined track to  be  dredged (Jepsky,
1981).

     The depth of the dredge head when it is attached to a ladder (cutterhead
or dustpan, for example) is determined through the use of  an  inclinometer.
Mini-computer survey programs are available which provide  predredging  and
postdredging profiles and computations of area and volume  dredged, with
sounding signals used as direct input.

     Precision dredging can be facilitated by marking limits  of dredging and
obstacles with buoys or buoyed lines.  Land-based lasers have been used  to
mark lateral locations of submerged and buried pipelines.  Laser  beams are  not
subject to damage by vessels, are not obstacles to vessel mobility,  and  are
more readily seen at night and during periods of fog (World Dredging,  1983).


          8.1.4.3  Sediment Turbidity Control
     Removal of contaminated sediments in open water often generates  turbidity
caused by resuspension of fine-grained particles.  Control of  turbidity can be
accomplished through modification to dredging equipment and  the use of curtain
barriers.  In addition, there are certain procedures that all  sediment
dredging operations may follow to minimize stream bed agitation and control
turbidity.  Low turbidity dredging equipment is discussed in previous
sections; barriers are discussed in this section.

     When dredging in areas of strong currents and natural turbulence, the
dredging operation should proceed upstream, into the current,  because any
turbidity generated must pass around and under the dredge.   This will increase
the tendency of any suspended material to flocculate and settle.  Downstream
dredging will allow turbid water to spread ahead of the dredge vessel
uninterrupted (Huston, 1976).  The effect of controlling turbidity through
upstream dredging is greatest when operating in shallow flows.

     Another consideration for turbidity reduction is the timing of dredging
operations.  If dredging is to be done for contaminated sediments in  aqueous
environments, projects should be scheduled for periods of low  flow and dry,
calm weather whenever possible.  Natural stream turbidity and  current
turbulence will be minimal at such times and will not contribute to dredge-
generated turbidity.
                                     8-27

-------
     When preparing dredging contracts for contaminated sediment removal where
turbidity control is essential, contract provisions should specify the use of
special low-turbidity dredge vessels or auxiliary equipment and techniques
designed to minimize turbidity generation (Huston, 1976).  The bidder should
be made to specify minimum sediment removal volumes and maximum allowable
turbidity levels in the downstream environment to ensure an effective dredging
operation.
               Silt Curtains—Silt curtains are  low permeability  floating
barriers that extend vertically from the surface of the water  to  a  specified
depth and are used to control near surface turbidity  in the vicinity  of  small
dredging and capping operations.  A silt curtain must be designed to  meet
specific site conditions including water depth and changes in  water depth  due
to tides, type of bottom sediment, and current velocity.

     Silt curtains are best suited to use in quiescent waters  and in  con-
junction with dredges that do not demand frequent curtain movement.   Under
these conditions, turbidity levels outside a curtain may be reduced by 80  to
90 percent (JBF, 1978).

     Silt curtains are not recommended for use in open oceans,  in currents
that exceed 1 knot, in areas frequently exposed  to high tides  and large  waves,
or around hopper or cutterhead dredges where frequent curtain  movement is
necessary.  Tides and wave actions cause the curtain  to flair,  thereby
reducing its effective depth.  In areas characterized by tidal  currents, the
use of this method may actually result in higher turbidity levels outside  the
curtain than inside because of the sweeping motion of the curtain,  which may
cause resuspension (JBF, 1978).

     The components of a silt curtain are illustrated in Figure 8-14.  The
flexible skirt is generally constructed from polyester reinforced PVC or nylon
reinforced PVC.  Skirts made of KEVLAR/polyester blend are also available
(Slickbar, Inc., 1983).  The skirt is maintained by a ballast  chain along  the
bottom.  A tension cable is usually built into the upper part  of  the  curtain
to absorb stress imposed by currents.  End connectors are available to allow
two sections of curtain to be attached or disengaged  easily.   Anchored lines
are used to hold the curtain in the deployed configuration (JBF,  1978).

     There are four basic configurations used in deploying silt curtains.
These are illustrated in Figure 8-15.  The maze  configuration  is  generally not
recommended because of the potential for direct  flow  between the  separate
curtain sections.  The in-stream, U-shaped configuration is generally accept-
able on a river where the current does not reverse.   The U-shaped config-
uration is also suitable for operations along shores  and river banks.  This
configuration was effectively used to contain resuspended sediments during the
dredging of lead-contaminated sediments from the Mill River in Connecticut
(York Wastewater Consultants, 1983).  The circular or elliptical  configuration
is used in open waters and in tidal situations with reversing  tides (JBF,
1978).
                                      8-28

-------
                  FIGURE 8-14.
CONSTRUCTION OF A TYPICAL SILT CURTAIN SECTION
Design
Extra Flotation to Waterline \
r — Compensate for Weight \
\ of End Connector \

Tension
Cable -

1

\
V
1 1 M
'i '
v A-A
Source: JBF, 1978
                     8-29

-------
                                      FIGURE 8-15.
               TYPICAL SILT CURTAIN DEVELOPMENT CONFIGURATIONS
               ,ฃ.. Maze (Not Recommended)
                                                          Legend:
                                                       O  Mooring Buoy
                                                       J-  Anchor
                                                       •X-  Single Anchor
                                                          or Piling
                    Curtain Movement Due   \
                    to Reversing Currents  —**
                                             C"
                                                     U-Shaped
                                                 Anchored On-Shore
                                                               Estuary
                                         "D"
                 Circular or Elliptical
Source: Barnard, 1978
                                          8-30

-------
     JBF Scientific Corporation (1978) performed a detailed  evaluation  of  silt
curtain effectiveness and concluded that effectiveness  is related  to  four
factors:
     •  Hydrodynamic conditions at the site

     •  Quantity and type of material in suspension
     •  Characteristics, construction, and conditions of  the  curtain

     •  Methods of mooring.


     This JBF study should be consulted for a detailed discussion of  the
factors affecting performance and deployment of silt curtains.


     8.1.5  Technology Selection/Evaluation


     Although dredging and subsequent management of contaminated sediments  is
costly, in some cases it is the only viable alternative for handling  contam-
inated sediments with the exception of the "no action" alternative.   In some
situations (calm, open waters or streams with low  flow),  in-situ methods may
be used (Section 8.3).  However, the long-term reliability and effectiveness
of these measures is not yet known.  Because of the limited number  of
alternatives for handling contaminated sediments,  the decision is frequently
not whether to dredge but how to dredge.

     Factors affecting the implementability, effectiveness, and reliability of
a dredging operation depend largely on the inherent capabilities and  limita-
tions of the dredging equipment.  These are summarized in Tables 8-1  and 8-2.

     The time required to implement dredging will  depend  primarily  upon the
availability of the dredge and the location from which it must be transported.
Also important to the implementation schedule are  the weather conditions (for
rivers and streams, dredging should take place during periods of low  flow to
minimize downstream transport of contaminants) and the time it takes  to obtain
the necessary permits (State permits and permits required under Section 404 of
the Clean Water Act and Section 10 of the Rivers and Harbor Act).

     The effectiveness of the dredging operation depends  upon the precision
obtainable with the dredge, types of dredge vessel controls used and  the
operators capabilities.  Inaccuracies in dredge cut positioning and depth
control, sediment sloughing, and difficulties with obstructions and debris
will cause the dredging project to be less than 100 percent efficient.
Recovery of contaminated sediment during normal operations using conventional
(hydraulic and mechanical) dredges has been estimated to  be as low  as 65 per-
cent..  On the other hand implementation of double  pass dredging to  remove the
remaining contaminated sediments generally yields  a substantial amount of
uncontaminated sediment which must subsequently be treated.  Preplanned
                                     8-31

-------












<
OA
w
H
M
Pi
O


Z
O
M
E-i
ง
U
M

8



55
Ed



j— i

?V
u

u
Q
u
OS
Q
F*
O

2
O
to
M
03
eS
33
8

.
i— ซ
1
oo
3
<;



















































Of
00
•o
V
o

0
8.
X










































o
ฑJ
i

a*
c
o*















Cl

,— t
ซD

•o

33


















ซ-ซ
(8
U
C
ffl
.c
y
0*
ฃ





















u.
O)
N
ฃ

(0
i
0-
ฃ

.'-> zz — — JD-.S.
u-I
s^

1^ 4A *A
s^ N^ 00 r^
U X vฃ> (O . i-\ /^
(otปTj ClVm T^ป 2
 •**
" o
o ^
m CO

^^ ^^ (^ w
ซ ^ CM *-^ ^ • ^ป
OXte CM>^ en o ofiao


.
en

/•^ ^^
CN CM *~*
*3 ^* O fi O *-*
OX fc[ S T %l ฐ ป ป
cofj1^ en*.* csi^^cs  S
. . >c o i o b ^
i
S

o o —

^^
u. x -~ ^ ^o ^

A u *^ fk> CM i ec
... oo -~ o —
 — ^.
0 — Jl 4J C
— u B 0 u- -s O

CO .-o*rfซ""U^*J *-*

— B B^^JIU— -p e >,
a. Wbk ^Efi OBA O O w ^o
Q.UB -~53 OU U"ซs,*^*— CO
* l-r ? j.s.5 ง.r: •• rs •- t
^^^, 30v t- (C 3 4* > 1-
H < Q D- OCHOฃ
-------
                        TABLE  8-1.   (continued)
Footnotes

(1)  See Table 4-3, p. 54, Hand et al., 1978

(2)  See Table 4-2, p. 51, Hand et al., 1978

(3)  See Table 4-4, p. 59, Hand et al., 1978

(4)  Determined by draft of vessel; if not vessel-mounted,  there is no
     limiting minimum depth.

(5)  See Table 1, p. 12 (Clark, 1983)

(6)  Limited only by availability of support equipment (e.g.,  cables,  winches,
     etc.)

(7)  See Tables 4-8 through 4-11, pp. 76-79, Hand et al.,  1978

(8)  See Table 4-6, p. 69, Hand et al., 1978


Volume

A - Small scale, less than 1,000 cubic yards.  (See Footnote 7.)

B - Medium scale, 1,000 to 200,000 cubic yards.  (See Footnote 7.)

C - Large scale, greater than 200,000 cubic yards.   (See Footnote 7.)


Setting

D - Narrow and/or very shallow (less than 5 feet) streams.

E - Shallow (less than 20 feet) streams and rivers,  navigable  by small
    vessels.

F - Inland lakes and ponds.

G - Inland navigable channels and lake and coastal  harbors.

H - Great lakes and coastal harbors.


Auxiliary Facilities

I - Dump trucks
                                                                   (Continued)
                                    8-33

-------
                        TABLE  8.1.   (continued)
Auxiliary Facilities (continued)
J - Barges
K - Transport Piping
L - Settling Impoundments
M - Crane

Availability
Q - All or most owned by U.S. Army Corps of Engineers.
R - Bases in most major harbors and commercial waterways^
S - Based in some coastal and great lakes harbors.
T - Widely available in general earthwork applications.
U - Widely available from contractors and vendors.
V - Limited availability through United States distributors.
W - Not generally available in United States.
X - Generally available on inland commercial waterways.
Y - Can be fabricated.
Z - Very few operating in United States.

Transportability
1 - Dredge can be moved over existing roads "as-is" or with slight
    modification. (See Footnote 5.)
2 - Dredge can be moved over existing roads after disassembling to 3 or fewer
    pieces. (See Footnote 5.)
3 - Dredge can be moved over existing roads after disassembling to more than 3
    pieces. (See Footnote 5.)
4 - Dredge head can be removed over existing roads "as-is" or with slight
    modification and mounted on conventional vessel or crane.
5 - Transport restricted to navigation channels (greater than 5 foot depth)
    due to draft.
6 - Transport restricted to deep (greater than 12 feet) navigation channels
    due to draft.
                                      8-34

-------






Z
O

H
M
n
z
0
o
W
H
10

U
H

•ฃ
8
b"l

M
M
O
^_J


04

N
a
IB

4J
ฃ


MH
"iJ
k,

(U

A
JJ
U
ฃ
U
a.

S

1
CL
n
5

•O
(0
0)
X
U
0)
3

8
U
3
tn

c
a
r-t
-
* 4) 4) o
CD V ซ >> >S >-. X)
•D
ft)
ft) .r- ^

ป ซC?ป^ c ฃ ฃ




at x
*O fi a> u
i o m o o o a> o
m w v Z c c >, xi




CM V f
SCO W
^ 0 0 0 01 0
— nv& C C >, JD

1 CQ CO CD U
CM Br*> O a) O a) o
~a>vZ X C X.C
C
U
 ป **
t *^- d O O tV 4> O
lA CfiV Z C ^> >%^


•o

•U
r-. g g CO (6 4J
i 5 m o —• at a> o


i

.^. TJ
14- 01

ซ0 M *S a u
I -f  o

•o
0)
— w -0
"a • H • ^
B  o o
a Bv>ซr- >>c ซ

•D
01
V4 AJ *O

to ป e n r^
g en ol •" 0) O O
• B v >• -< >>c B

•c
l-< W -0
..* -H -H
a o B ป "
ง*n 0) •* at o o
\/ ;H — 5< B •>
ซ
ฃ C •"-
— U B 0) 3
*J >H V S CT •-<
*. o) a i •- .H a
•~j as t, o G v o -J >
fO o 0) 4J 0) O
JJO 0)0) B CJCO bOUB
<0 ff IB tt-toCr^fi^Bd
V.OI 9BOIB OEซซ
OO O V- O — O O 4) TI
- ง .2 I 'S 2 r Jl S a ป S -
01 bU* B  .0-0 D — CDO
a -o ซ- .H u9 bo> w — ok. ucfl
a c ซ K o>k oiu 0.1-1 ซ ja •"
a) •*ป. n o.4j AIM vo 54) 3>"
> s H s oca ox o 
-------
overlaps and dredgecuts controlled with modern  electronic  locating  equipment
are recommended to maximize efficiencies.

     Short-term impacts from dredging  are  a  primary  concern.   Resuspension and
downstream transport of sediment can be minimized using  low turbidity  dredges,
by dredging during low flow, and through the use of  turbidity  controls.   In
addition, a monitoring plan should be  implemented which  requires  immediate
cessation of dredging when resuspension or downstream  transport exceeds  a
certain level.

     Acceptance of a proposed dredging operation cannot  be evaluated
separately from the dredged materials handling  (see  Sections 10.2 and  8.2).
Dredges which result in high slurry densities will facilitate  good  dredge
materials management.
     8.1.6  Cost


     Unit cost associated with representative hydraulic  and mechanical
dredging techniques are described  in Tables  8-3  and  8-4.   Capital  purchase
cost and operating cost are given  for  some dredge vessels  and  accessories,
although it is recognized that dredging will most likely be performed by
specialty contractors whose rates maybe highly variable  from site  to  site.

     Cost considerations, that are not  included in Tables 8-3 and 8-4  are  the
following:


     •  Crane rental to launch and retrieve  portable dredge vessels

     •  Freight and handling costs for shipping  dredge equipment

     •  Transportation of equipment from  site to site

     •  Insurance (hull coverage and reliability) for purchased vessels

     •  Storage and/or warehouse costs
     •  Sales tax.


Unit costs for conventional excavation equipment are included  in Section  7.1,

     It should be noted that the costs associated with a dredging  operation
may be a small part of the total costs of a  contaminated sediments cleanup.
Dewatering, treatment and disposal costs  can be  a large  percentage of total
capital costs.  Sections 10.2 and 8.2  should be  consulted  for  technical and
cost information associated with dredged materials handling.
                                      8-36

-------
en
oo
PQ

cu
u
V.
3
o
o>











1 1
CO
o
CJ

4J
C
ป





















C
o

4J
(X
v>
0
CO
a

















^-*






10
CO
o
u
."
ง

O r-
O CO
oo *j
. o
CM 4-1

O
1 4-1
in TJ
r- TJ
—. eg

\o













C
o
• r*
4_l
CO
N
•i-1

•H
JO
o
ง
TJ
•g
eg

ง
*fซ
4-1 /-N
CO .-•
N CO
•H 4-)
I— O
•H 4-1
jQ
ง2
11 TJ
SOT!
TJ <
1) ^
1-1
o



,_H












CO
•a

^H^
O


00
1

O
o

vO




O.


TJ
CU
V.
o

CO

o

*-*
11 U
X 1>
n u-

O
^** o
u o
1-1 — 1
o
si


eg
u ซ
TJ TJ
CU
TJ a.
v e
4J 3
C TJ
3
O ^
8 U
i a
cu a
Ml O
1- X
CO
PQ






























TJ
1)
TJ
eg
o
r—t
1
cj
3
1.


L.
o

TJ
D
t-4
•H
a ••
i ^^
X TJ
4-1 1)
V. TJ
CO 3
11 —
U
J.5
TJ r-i
0) 3
8 eg
X

g'fc
• r*
4-1 CO
eg X
> u
co 3
u l-

o
I—* *>ปX
S
CO



t— * ^-1



















m en
^^
*ป••. ***ป
33

CM —








>-
X


x"^- O
^
<•> X O

01 ^4 i— ^
4J O ^
C
3 in TJ
O-3-1-
B-' eg
1 >>
V. TJ
cu u o
•-I ซ ••*
eg 3
1- o o
0 •*
v-x XI CM
3 —
U CJ —
O
X ~* en
_xj
u I I
CO
XI ^ ^>
U 4J
O .^1 —
•* 0 O
r- eg eg
3 a. a
eg eg eg
woo
>> 1 1

























e





















TJ
11
4.J
C
3



CU
V
J

cu
o
_g
fi(ซ
eg
Xt

o

"3
eg
1-

S3




t-H



















n c
•D
ซ*^,
St

s,
4J
*r-
U
CO
a
CO
u






P-4 ,n ^-1



















o cn m
^ ฃฃ

o en en
en oo CM

CO ^" f*}










X^ y-V

•G JT! *"^
^*^ '^*ซ ^
^ ^ Xซ
O O *^s
0 0 S
en CN
•^ -^ m
m
^ *o v.^
^ v^
eg eg TJ
^ >, i-
CO
o o >%
•H .pri
n XI U
3 3 •"
U U XI
3
-* CM O
en — i —

1 1 1
^ ^* ^t

•l-i r— 1 •!-! •**
CJ 1-1 O O
eg ซ eg eg
o- x a a
eg to eg eg
u Q u u
a
1 —II
U




1— ^ I—I





*t

— in

X Ss
cu u
t? (5
X X
eg eg

4-* 4-1
CO ซ
O O
O U
en en
TJ TJ CU 11
^ X CO CO
^ eg eg
O vo OJ cu
in sj u k.
• • CJ CJ
en — C C










^^

X V-

SH **"•.
U SM
0ฐ
en CM
*~S IM4

TJ ^-^
1-
cg TJ ] >
>ป k. C
a cu
.S ^ i.
•ง -S S -3
o xi •" cr
3 *~i D
CM O •• 60
-•~ • C eg ^
— en O i- D
— TJ X
t 1 4J 4J
CO U O
:* >, > o
4J 4-t eg ^
.~ .^ o r- o
1) CJ U X i—
c eg eg cir cu cu
— o. a. x O
r* eg eg u co x:
DO U O V 8 X
eg 380
hl| r-4 CO
O v. u pa
O



,^

















in
en

in
1
oo
O

sj-
•CO




E
eg
T5
cu
14-
lw
o
CJ

u in
0 —
00 4J
C CJ
— 3

U CU
CU TJ
X
CO -
TJ
C C
•*• Q
CO
C
O k.
•~ 0
CO —
> •!-
eg 0
U CO
X
cu u
14*
i- O

l|

i ""
0 '

•o
cu
3
C

1 .
C
o
o





























x
o


TJ
TJ
CO
A
>v
CO
i—i
U

14*
14-
CO
o

J-1
o
CO
^

eg
U

o
14-
1





















































L.
3
o
X
8.

CO
TJ
V.
CO

u

x
3
u
g

V.
X

B
                                      8-37

-------
































TJ
o;
3
C
• r-*
u i
ซ
O
u
V 	 •


.
en

00

W
PQ
^^
H


































01
CJ
I.
3
O
VI



















4J
to
o
CJ

c
s






















c
o
4J
o.

IA
CJ
CO
OJ
f*]































































01
o
_f^
f^
u
CO
&

U-t
0

c
o
•H
JJ
(0
N

r_4
•r*
jf)
o
1
•o

ซ^j
c
to
c
o
CO
N
>l^
ฃ
•8
X






I-. —
























f f.
o u
10 CO
Qj QJ
o o
•d" I-.
*-* CM
cy> •





















TJ
1.
•o to
V. X
CO
X cj

CJ Xi
•" 3
X> o
3
U CM
•x^
-* —
— 1
en -ซ
01 X X
C 4J 4J
•- O CJ
00 CO CO
a ex a
h to co
•O CJ O
V> 1 1
0



X~N
T3
• • ป -o o. o. o
T3 CO 3 CM m
"u ซ— ป CM r^ oo r^
•o co cj ^ CM en co
v- o c -^ ป_-
to i— i ซt- x: "
X 4J C C >-
*o u a. T; OT) o-D'>-
O* OO> O)')-4 o>*^ 0) CO
•"— ' CT3 004J 004J 00
xi ^ i acocococov
3- 1- > > > > > O
ucx^oi <-> a *-> co i-i
•*• o)4joiio OOICQ uoica ฃ•
CM^. OJCOCJCO XCJCO XtJCO CO
r-*4-l 4->?CO OJCO OICO 0)
CO I—" "O t— ' t3 1~J *U 4-1
-•o cxcxc o. o. c a o- c co
OOC ซCU CO OJ CO 01 CO
C 3 00 01 C cue OIC
•r* O C "O •'•" "O "O •-- T3 "O •ป" "O S-
r-* V. *f- 0> OJ OJ OJ
coeu •^otj^r. Q^^. OM..- .—
Xli-i CXOOJ3 OOJ3 OOI3 *-
•- u.r'cx u- — a 14.^.0, -o
A 8 4J 1 1 1
4JI umil Oil ir\li 01
V- •* Ol — CM CM !->
to x: —
W w d.
^- to
.- 01
0 4J
to CO
.,.
01 CJ
f. 0
4-> CO
CO
0 <
4J
c to
t- •
o o
s.
CJ ซ
C to
CO Ol
- CX
•O CO
01 4J
to vi
X OJ
01 CJ
C CO
3 14.
\*x V*
3
ฃ. CO

oo i.
C 01
OJ 4-1
.-• CO
p
OJ OJ
> x;
•r- 4J
^.
•O OJ
0 0
4-1 XI
a
00
,c *"
'w CO
01 O
01 Xt
f. 01
to 01
u
*4. V4.
o
U.
Xi O
4-1
00 4J
C OJ
Ol OJ


t3 m
01
to O •
O 4J ^
ex o
4J X — en
O Ol OS
0 X —
(4. 14. 4J
o —
oi S c
w oi o o
CO 4J "- ซ •*-
3 3 4J — 4J
u- q to .. co
CO .*- U ^* tj
6 —
1- Ol 4-i q
01 U ฃ 3 3
CX 01 u o E
CX XI E
to " CQ o
•U CO r-< CJ
q 3 eo 01
3 O ^*> XI •""*
O t— i Oi co
ex xi c -a c
01 i— O
II II 00 3 co
O I-
t- 3E c x; o;
tO Pu HH CO CX
CX PQ ^.
8-38

-------








y—v
T>
0)
C
•r-ป
4-J
C
0
U
\^
•
CO
1
00

w
hJ
ff.
PH
ซfl
H

























cu
u
^
3
0
V)




4J
CO
a
c













c
o
• ^
4-1
CX
• r*
t-
O
CO
(S




























c
0

CO
>
CO
u
X
01
DO
B
1
u
B
•IM
4J
O
B
^
cu
a
ex

i— i ••
CO x*v
4J ซ— <
01 —
B —
14*
•0 J"!
4J CO
CO JQ
00
3 13
1- B
1- a
O
CJ





4J
O
o
•*- 4J 4J 4J 4rf
O O O 0
u o o o o
CO 14- M- 14- M-
11
E h V. b >-
• F" CO CO CO co
_ cu oi 01 K
B E E E
in •ซ-• -r- •** >iซ
C^ s* O CM 1-1
— tN -* in co
 •  v>














01 01 01 eu u
00 00 00 OO OO
33333
co co cd co co
oo oo oo oo oo
- I.
J< ^ Jt A!
CO 4) 41 41 QJ
T3 41 41 41 41
^ "k •ป ik ^
•^ iป ? ? 3
~~- -V ^. ^^.
— 00 .ป O O
CN ^- VO CO <ป•
CN
ซ- ซ•ซ• to-




co
Jt
%
tซ
4J

ง
}M
U*

"8
o.
ง
T3

I

CO E 3=
O •* IX)
h ••< eg U
4> 4J CO ฃ S S
1-4 01 *^ CM u O
.ซ 4J ^ o s as
M-. O co - JE *"
x^ ^ 00 tC m o
ex 3 o co — CT>
ex x-i E
CO 4J *H *n M ป• M
V- 11 h 1 X & JC
1 •— 4-1 CM O O O
CX 4-ป E """^ BEE
•" 3 41 •— •!- T< -r<
1-1 o o I i i i
•— CM CO vD
41 1-
E O CX
O ซ-> g
u 5
co ix
•o
D
3

4J
E
O
o
•^^
•s "3 o i; B 'S
E E E B E E
4* 1) A) 4) ii (U
)- |_ ป- ^ 1- 1-
ji JC ^i >! ^ A:
 a)
a; 'ป'*'>•>
? 3 ? 3 ? ?
O f*- u^ u^ O O
u^ \O 00 ^- in o
^ ^ ^>
 ซ- 
^ f ฃ CN o so in
•^ o o t— i co in i— i
co B c

o; r r j: & & j~
B 
f 1-1
4J CO
00
n

ฃC
CUX
u a,
x u
3-39

-------
 C

 O

 o
en
 I
oo


a
01
u
3


















u
to
o
JJ
c




















c
0


a.

u
a
2













CM CM














^ ^ x-v^ ^> 0)
CQ (0 Q CQ (0 *^
U W 4J W JH> S
c c c c e
 <1J 0) "U
a
 CS CS C*4 •— '
Q) 
U 0.

CO >;
C ^
O
n -
^ CO
8. Z
CO
S CO
1-
- CO
n oo
o co
t S5
o
- co
CO C
V. O
O •-
•U JJ
co co
U G
•- V.
U CD

CO C
&* *~*

U CO
 01 ซ
U4 C JJ
•o a. to
O "^ S


-M CM PI


CO
01
u
o
CO
                    8-40

-------
                                         TABLE 8-4.
                            1985  HYDRAULIC  DREDGE UNIT  COSTS
                 Item
                                                         Unit  Cost
                                                                                 Source
Vaughn Lagoon Pumper with 75 hp motor,
  complete  platform assembly including winch

Mud Cat  Dredge Models SP-810, with 10-foot
  boom and  submerged pump;  less accessories

Mud Cat  Dredge Model SP-815, with 15-foot
  boom and  submerged pump;  less accessories
$20,000  -  50,000


     $84,500


     894,900
OPTIONAL EQUIPMENT (FACTORY-INSTALLED)
Air conditioned cab
Auger wheels (for use in lined ponds)
Auger cage assembly (extra protection for
lined ponds)
Anodes (for salt water application)
ACCESSORY EQUIPMENT PACKAGES
Discharge pipe package, 1,500 feet of
6-inch polyethylene pipe
Discharge pipe package, 1,500 feet of
8-inch polyethylene pipe
Harnessing hardware
Service boat and motor

$ 1
$
$
$

S21
$25
S 4
$ 3

,900
950
950
550

,486
,9.09
,466
,301

2
2
2
2

2
2
2
2
                                                                          (continued)
                                             8-41

-------
                                  TABLE 8-4.    (continued)
                  Item
                                                           Unit Cost
                                                                                    Source
EXTRA DISCHARGE PIPE AND CONNECTORS

Carrier pipe,  6-inch x 19  feet, male and female
  couplings,  including gasket,  float bands and
  links not  included

6-inch ring  band lock

Carrier pipe,  8-inch x 19  feet, male and female
  couplings,  including gasket,  float bands and
  links not  included

8-inch ring  band lock
$149



$  8.35

$189



$  8.61
BOOSTER PUMP AND EQUIPMENT
Booster pump, skid-mounted, including connector $30,100
fitting kit
Booster pump, skid-mounted, including connector $30,100
fitting kit
OPERATING COSTS
Fuel $1.20/gal x 5 gal/hr $ 6/hr
Lubricants:
Engine 0.10/gal hr $ 1.20/hr
Hydraulics 0.07 gal/hr
Grease 0.06 Ib/hr
Repairs/parts $ 1.50/hr
Two operators and fringe benefits $20/hr

2
2

2
2
2
2
Other cost considerations not  included:  crane rental to launch and retrieve Mud Cat Dredge,
transportation of equipment  from site  to site, administrative and sale costs, storage and/or
warehouse costs, service vehicle cost, per diem, sales, tax, interest on capital.

Source:   1. Vaughn Co.,  Inc.,  Montesano, WA, personal communication, 1985
         2. Sherman,  L., Mud Cat Division of National Car Rental System, Inc., Fort Lee,  NJ,
            personal  communication,  1985
                                                8-42

-------
8.2  Dredge Material Management


     Contaminated dredge spoil management includes methods for dewatering,
transporting, treating, and disposing of contaminated sediments after
dredging.  The most technically and economically effective strategy to handle
contaminated sediments removed from a given dredge site will depend on many
site-specific variables, which include the following:


     o  Method of dredging used

     o  Method of spoil transport - pipeline vs. truck or hopper barge

     o  Physical nature of removed spoil - consistency (solids/water content)
        and grain size distribution

     o  Volume of dredge material

     o  Nature and quantity of contamination - physical and chemical charac-
        teristics of contaminants and hazard/toxicity level of contamination

     o  Proximity of acceptable treatment, storage, or disposal facilities

     o  Available land area for construction of dewatering and treatment
        facilities.
     There are several well-established techniques for the management of
uncontaminated dredge spoil.  Techniques for managing contaminated dredge
spoil, however, are influenced by the hazardous nature of the spoil material.
Special consideration must be given to handling these sediments in a safe,
efficient manner.

     Figure 8-16 summarizes the major activities that are undertaken in order
to manage dredged materials.  Many of the activities apply to hazardous waste
contaminated soils and sludges as well as sediments, and they are discussed in
detail in other sections of this Handbook; Figure 8-16 also refers the reader
to the appropriate sections.

     Costs presented in Tables 8-3 and 8-4 do not include the cost of dredge
material management (see Sections 10.2 and 8.2).  These costs, which may
include dewatering, solids and aqueous waste treatment and transport to a
disposal site may far exceed the costs associated with the actual dredging
operation.  This point is illustrated by cost estimates which have been
developed for dredging and sequent handling of contaminated sediments from
Waukegan Harbor, Illinois.

     The Feasibility Study for Waukegan Harbor examined a broad range of
alternatives for handling PCB contaminated sediments (Ch M-Hill and Ecology
and Environment, 1983).  The costs estimates (order of magnitude) for one such
alternative (not a recommended alternative) involving dredging 10,900 cubic

                                     8-43

-------
                               FIGURE 8-16.
            OVERVIEW OF DREDGED MATERIAL MANAGEMENT
                                  REMOVED
                                CONTAMINATED
                                  SEDIMENT
                                   SOLIDS
                                 SEPARATIONS
                                 (SECTION 10.2)
                COARSE
               GRAINED
                          DB/VATERING
                        TO
                     DISPOSAL
                                        FINE-GRAINED
                                         SEDIMENTS
                                   SOLIDS
                                 DEWATERING
                                 (SECTION 10.2)
    AQUEOUS
   TREATMENT
  (SECTION 10.1)

SOLIDIFICATION/
 STABILIZATION
 (SECTION 10.3)
TREATMENT
STREAM DISCHARGE
    OR POTW
  TO DISPOSAL
                                                         TO DISPOSAL
                                    8-44

-------
yards of  sediments  from  a  harbor  slip  and  dewatering and treating the
contaminated  sediment  are  summarized  in  Table  8-5.   Total present worth cost
(expressed  in  1985  dollars)  for  the  alternative  is  $11,137,380 or $1024/cubic
yards.  The elements of  the  remedial  action are  briefly described below.

     A  sediment dispersal  control  device,  consisting of a double silt curtain
or  sheet  piling, would be  installed  across the mouth of the harbor slip.
10,900,000 cubic yards of  sediments with greater than 50 ppm PCBs would be
removed with  a hydraulic dredge  (cutterhead pipeline suction depth dredge) and
the sediment  slurry pumped through a  pipeline  to the initial solids dewatering
lagoon  (described below).  Because the hydraulic dredge cannot penetrate  the
area of deep  contaminated  sand and silt  near the OMC outfall,  a clamshell
dredge would be used to  remove this material.

     This deep dredging  would be  performed inside a single sheet pile
cofferdam.  The solids would be  loaded onto trucks  and transported to an
initial solids dewatering  lagoon.  The water level  inside the  cofferdam would
be kept lower  than outside to cause water  flow toward the contained area.  The
removed water  would be routed to a water treatment  plant  for suspended solids
and PCB removal (to 1 ppb  PCBs),  then  discharged to the harbor or to a
sanitary  sewer.

     Solids would be dewatered in  a clay-lined dewatering lagoon constructed
on OMC property.  Volatilization would be  controlled by covering the filled
lagoon surface with organic  sludge.  The supernatant would be  continuously
decanted  and routed to a 1,500-gpm water treatment  plant  to remove suspended
solids and dissolved PCBs  down to  1 ppb  before being discharged.   After
dredging  activities are  completed, rainwater and leachate water would be
treated by the 1,500-gpm water treatment plant for  the duration of the
dewatering process.

     Solids would be removed from  the  lagoon by  dragline  about 2 months after
dredging  activities are  completed, loaded  into trucks,  and transported to a
batch treatment plant.

     The  solids would be fixed at  the  batch plant by adding portland cement,
Locksorb, or another fixing  agent  to hydrate the excess water.   The mix would
then be transported to curing cells (described below).   The fixed solids  would
cure until they were non-flowable.  This is expected to take about 1 day.   The
fixed solids would be removed from the curing  cells by front end loaders  for
transportation by truck  to an approved disposal  site.

     Initial Solid Dewatering—A 24,000  cubic  yard  lagoon would be required to
dewater sediments from the slip.    The  capacity of the  lagoon is  based on
2 feet of freeboard and 8  feet of  storage.   The  lagoon would have a clay  liner
system consisting of the following:

     •  A 6-inch-thick, compacted  soil-cement  layer

                                                                            —8
     •  A 1-ft-thick,  compacted clay liner  with  a permeability  less  than  10
        centimeters per second
                                     8-45

-------
               TABLE  8-5.   COST ESTIMATE  WAUKEGAN HARBOR SLIP
                    DREDGE-DEWATER  IN  LAGOON-FIX-DISPOSE


Description

Mobilization
Health and Safety Requirements
General Site Preparation
Sediment Dispersal Control
Dredging
Localized Cofferdam and
Dewatering
Dredging of Deep Sand
and Silt
Initial Solids Dewatering —
Lagoon
Water Treatment Plant and
Water Disposal
Solids Removal
Fixation
Transportation and Disposal
Engineering, Legal, and
Administration
Subtotal
Total
1985(1)
Capital
Costs

$ 622,200
342,210
300,730
62,220
62,220

409,430
20,740
1,628,090

1,306,620
62,220
1,638,460
734,270
1,223,660
2,519,910
$10,929,980
1985(1)
Present
Worth of
O&M Costs
$ 0
0
0
0
0

62,220
0
10,370

62,220
0
0
0
20,740
51,850
$207,400
1985(1)
Present
Worth

$ 622,200
342,210
300,730
62,220
62,220

466,650
20,740
1,638,460

1,368,840
62,220
1,638,460
734,270
1,244,400
2,571,760
$11,137,380

(1)
   (Costs were updated to $1985 using ENR construction cost indices for 1983
   and 1985).
Source:  CH-M-Hill and Ecology and Environment, 1983.
                                       8-46

-------
     •  A  1-ft-thick  sand  or  gravel  layer  with  pipe  underdrains to collect any
        PCB-contaminated water  that may  penetrate  the  clay liner
                                                                           _Q
     •  A  1-ft-thick  compacted  clay  liner  with  a permeability less than 10
        centimeters per second  for additional protection  against percolation
        of PCB-contaminated water.

     Curing Cells—Three 1,400-cubic  yard  curing cells would be required to
cure the fixed solids  from the  batch  plant.  The capacity of the curing cells
is based on 1 foot of  freeboard and 4  feet  of storage.  The earth-lined cells
would have the same clay liner  system  as described for  the lagoons.   In
addition,  the curing  cells would have  2-ft-thick,  5-ft-high concrete  walls to
divide the earth-lined area into three compartments.

     Temporary Storage Requirements—Dredged solids  would require temporary
storage in a lagoon for dewatering.  Dewatering  is expected to  take 2 months
after dredging activities  are completed.   When  the solids are removed from
temporary  storage, they would be fixed and  would require  an additional day of
temporary  storage for  curing.   After  curing, they  would be disposed of in a
licensed chemical waste landfill.

     Water Treatment—Slurry water from  dredging activities would be  treated
before being discharged to remove PCB  down  to 1  ppb  or  less.

     Water treatment would consist of:

     •  Coagulation/sedimentation to  coagulate  and settle fine  sediments

     •  Sand filtration to remove suspended solids
     •  Carbon filtration  to remove  soluble PCBs

     •  A  clearwell to monitor  PCB levels  before the water is discharged

The water  treatment system would be a  "package  plant,"  of factory-constructed
modules, with a capacity of 1,500 gpm.


8.3  In-Situ Control and Containment Measures

     In responding to a situation where  bottom  sediments  are  contaminated with
hazardous  substances,  it is sometimes  technically  infeasible  or economically
unreasonable to remove all of the contaminated material from  its location in
the watercourse.  If removal is determined  to be an  unacceptable singular
remedial response, in-situ control and containment measures  are often con-
sidered.  These measures are intended  to reduce  dispersion and  leaching of a
hazardous  substance to other areas in  the water  body.   They may be temporary
or permanent response measures.

     The use of in-situ methods for permanent containment  of  hazardous waste
contaminated sediments is neither widely practiced nor well-demonstrated and
consequently these methods will not be discussed in  detail.   Laboratory and
pilot scale testing is likely to be required before  these  methods  can be

                                     8-47

-------
implemented at a particular site.  Permanent containment methods may  include
use of caps, dikes or in-situ grouting.  Temporary containment usually
involves the use of dikes or berms, although capping materials can be used  on
a temporary basis as well.


     8.3.1  Retaining Dikes and Berms


          8.3.1.1  General Description
     Retaining dikes and berms include earthen embankments, earth-filled
cellular and double sheet pile walls, water inflated dams and other materials
which can be used to minimize transport of contaminated sediments.


          8.3.1.2  Applications/Limitations


     Retaining dikes or dams can be constructed perpendicular to the direction
of stream flow, or downstream of a dredging operation in order to prevent
suspended particulate matter from flowing downstream.  This type of dike
creates the effect of a holding pond or reservoir, which prevents flow down-
stream and also promotes the settling of fine particles.  The damming creates
deeper areas where water velocity is slower and allows more time for small
particles to settle.  Retaining dikes used for this application are limited to
streams with low flow.  A water inflated dam constructed from reinforced
urethane can also be used for this purpose.

     Retaining dikes can also be constructed parallel to a river or stream
bank to isolate contaminated deposits from the deeper river channel.  When
stabilized with vegetation, capping or some other method, these dikes can
provide permanent containment.


          8.3.1.3  Implementation Considerations


     Earthen dikes can be constructed quickly and easily using readily
available earth moving equipment such as bulldozers, front-end loaders or
mechanical dredging equipment.

     Water-inflated dams are constructed by securing the ends to steel piles
or deadmen on shore and weighting the bottom of the sediments under the dam to
provide a tight seal.

     Construction of dams using sheet piling is described in Section 8.1.4.1.
                                     8-48

-------
     8.3.2  Cover Methods
          8.3.2.1  General Description


     A wide variety of materials  can be  used  to  cover  contaminated  sediments
in order to minimize  leaching of  contaminants  and  prevent  erosive transport  of
contaminated sediments.  Cover materials include  inert materials  such as  silt,
clay or sand and active materials or additives which react with contaminants
to neutralize or otherwise decrease inherent  toxicity.   Potentially applicable
active cover materials include:   limestone and greensand for  neutralization;
oyster shells or gypsum for metals precipitation;  ferric sulfate  for  both
precipitation and base neutralization; and alum  for base neutralization
(Hand, 1978).

          8.3.2.2  Applications/Limitations


     Cover materials have application for temporary or permanent containment
for hazardous waste constituents.  Their use  is  generally  limited to  protected
open waters where bottom currents and flow velocity are  generally not
sufficient to erode the cap.  Some of the active materials can be applied
together with inert cover material to treat and  contain  the sediments.

     The active covering strategy differs from the inactive covering  strategy
because each waste constituent must be evaluated on a case-by-case  basis,
whereas the performance of the inert materials is  not as strongly affected by
the waste constituents.

     A major limitation with the use of  these methods is that their feasi-
bility and effectiveness has not been demonstrated for treatment/containment
of hazardous waste contaminated sediments.  Covering methods  have been applied
to contaminated sediments in Stamford-New Haven Harbor,  Connecticut,  (Morton,
1980) and the Port of Rotterdam in the Netherlands (Van  Leeuwan, Kleinbloesem
and H.J. Groenewegan, 1983), but long-term reliability of  these actions is not
yet known.


          8.2.2.3  Design Considerations


     The behavior of inert cover materials depends largely on the particle
size and cohesiveness of the cover materials, and  the dynamics of bottom  flow.
In determining the most appropriate material (sand, clay or silt) to use  for
capping, three factors need to be considered:
     •  Susceptibility to scour and resuspension - The susceptibility of cover
        material to scouring depends on:  particle size, shape, and size
        distribution; dynamics of flow; shape of the bottom surface; angle of
        repone of the particles; and degree of cohesiveness of the cover

                                     8-49

-------
        material.  Generally, the most important of these parameters  are  the
        cohesiveness of the cover material and the roughness factor associated
        with clumps of cohesive sediments.  Water currents  sufficient  to  erode
        or scour cohesive sediments are generally greater than those  for
        noncohesive sediments of approximately the same grain size.

        The rate and extent of scour depends upon cohesive  strength rather
        than on the properties of individual particles.  Thus sand will be
        more subject to erosion than silt or clay.  However, if there  are
        clumps of cohesive material in the cover shear stress generated by
        bottom currents acting on these rough surfaces will tend to cause
        erosion (Hand, 1978; Morton, 1980).
     •  Ability to withstand leaching - The ability of cover material to
        withstand leaching is believed to be directly related to permeability.
        The coarser and more permeabie the material the more prone  it is to
        leaching.  Therefore clays will exhibit much slower rates of leaching
        than sand.

     •  Effects on benthic organisms - The ability of benthic organisms to
        recolonize a capped area without significant bioaccumulation depends
        on:  the type of cover material; the similarity to natural  surrounding
        sediments; thickness of cover; and the potential for leaching.  Also,
        the cap must be sufficiently thick to prevent burrowing.


     With active cover materials, the criteria for selection are different.
If active cover materials are to be used successfully, they must remain in
place long enough to react with and treat the contaminants.  Limestone and
gypsum are pozzolanic in nature and tend to form a thick, cement-like cover
that is resistant to erosion.  Ferric sulfate, alum, and alumina are very
fine-grained and can be expected to behave like clays.  Greensand and oyster
shells will probably scour most easily, and it may be necessary to mix these
materials with a more stable inert cover material (Hand et al., 1978).


          8.3.2.4  Implementation


     The method of emplacing active or inert cover materials is important to
the overall effectiveness of the cover system.  For this reason, the method
should be selected carefully.  There are basically three methods for emplacing
cover materials, as follows:
     •  Point dumping
     •  Pumpdown methods

     •  Submerged difuser systems.



                                     8-50

-------
               a.  Point Dumping

     Point dumping of cover material from barges, scows, or hopper dredges is
a relatively straightforward and rapid approach to conducting a capping
operation.  However, use of barges, scows, and hopper dredges for point
dumping results in a high degree of turbidity and dispersion relative to other
capping methods, particularly where low moisture, fine-grained silts and
clays are used for capping.  Also, a deep draft precludes the use of these
methods in shallow waters.

     Most modern barges are the "clamshell" type, in which dumping is accom-
plished by hydraulically opening the entire hull in a clamshell-like motion.
Most scows are divided into several compartments (usually six) with each
compartment having one pair of bottom opening doors.  The scowman can thereby
empty the compartments selectively.  Dump scows and barges have little or no
navigational equipment aboard; the basic power and navigational capabilities
reside with the tugboat (Johanson et al., 1976).

     Barges and scows have capacities ranging from 2000 to 4000 cubic yards
and a loaded draft ranging from 7 to 20 feet.  Draft limitations preclude the
use of barges and scows in shallow water.  Seven to 8 feet of water beyond the
loaded draft is required for point dumping (Johanson, 1976).

     The hopper dredge is similar to a scow insofar as it is divided into
separate hoppers and point dumping is accomplished by gravity-dumping through
hydraulically operated gates in the bottom of the hoppers.  Unlike barges and
scows, however, the hopper dredge is self-propelled and the navigational
controls are located on the vessel.  No anchors or mooring system is required,
and the operation is very efficient.  Hopper dredges can operate in rough open
waters, with relatively strong currents; a sea-going hopper dredge can be
expected to hold a clearly defined position for 1 to 2 hours in currents of up
to 4 knots (Johanson, 1976).
               b.  Pumpdown Methods


     Pumpdown of the cover material from barges, scows, or hopper dredges
would create substantially less turbidity and/or resuspension of contaminated
sediments than point dump methods, provided that the discharge pipe is
situated close to the bottom.

     Conventional pumpdown barges pump the capping material from a scow,
barge, or land-based storage area down a discharge pipe whose termination is
set close to the bottom.  For use in a capping operation, the pumpdown barge
would be moored or spudded into place and scows or barges containing the cover
material would be tied along side.  Equipment on the unloading barge would
then be swung over the hopper of the scow and the load hydraulically pumped
out.

     As with point-dumping methods using barges and scows, the pumpdown
method is limited to use in relatively calm waters and is not applicable in

                                     8-51

-------
shallow waters due to the depth of water that is drawn by the vessel.  The
loaded draft of barges typically ranges from 7 to 20 feet (Johanson,  1976).

     A hopper dredge pumpdown system would be more applicable than a  pumpdown
barge in unprotected waters where conditions might restrict the use of
barge-mounted systems.  The use of the hopper dredge allows for increased
efficiency and more control over the capping operations.  However, avail-
ability and draft restrict the use of the hopper dredge pumpdown system
(Johanson, 1976).

     Use of a hopper dredge in a pumpdown capacity would require modification
of the existing equipment to provide a pumpdown (rather than pumpup)
capability through the dragartn (See description of hopper dredge in Section
8.1).  The maximum effective depth for the pumpdown option would be 36 to
60 feet, depending on the length of the dragarm.  This method could be used  in
deeper waters, although the effectiveness would greatly decrease.  Since the
draghead will nominally be about 10 feet wide, precise navigation would be
difficult, especially if full cover is required (Johanson, 1976).  Neverthe-
less, sophisticated navigation control systems are available that permit
precision navigation.  A hopper dredge modified for pumpdown was used together
with a diffuser head for a capping operation in the Port of Rotterdam (Van
Leeuwan, 1983).

     The two pumpdown methods described above present a clear advantage over
point dumping, insofar as turbidity and resuspension of contaminated  bottom
sediment is largely reduced with these methods.  The methods are, however,
considerably slower, and in the case of barge mounted and hopper dredge pump-
down systems, require very exacting navigational controls and monitoring to
ensure complete coverage (Johanson, 1976).


               c.  Submerged Diffuser System


     The submerged diffuser system is one of the most effective methods for
controlling the placement of cover material.  The advantages of this  system
include increased control over the location of cover, decreased scouring of
the bottom area, and less turbidity in the area.

     The primary purpose of the diffuser head is to reduce the velocity and
turbulence associated with the discharged cover material.  This is accom-
plished by routing the flow through a vertically oriented axial diffuser.  The
diffuser head, illustrated in Figure 8-17, operates on the principle  that
radial divergence of the flow will slow the discharge velocity to acceptable
levels.  By varying the height of the discharge above the bottom as well as
the discharge velocity, impact velocity and thickness of cover can be
controlled (Barnard, 1978 and Hand et al., 1978).

     A hydraulic barge/pipeline system would be used with the diffuser to
provide both the support and the capability for lowering the diffuser to
within 3 feet of the bottom at the beginning of the disposal operation.  The
diffuser discharge would be raised or lowered to the desired level by a

                                     8-52

-------
o
z
o
w
   u

   O
W O

a: <2

ซ ฐ
= o
u. Z
ฃ <
Q cc

a w
S (0
rs


S

ui
CC

3

(9
                                                                                                    CO

                                                                                                    CD
                                                                                                    8
                                                                                                    CO
                                                   8-53

-------
derrick on the barge, as shown in Figure 8-17.  The  submerged  diffuser  can be
used to depths of about 100 feet under favorable conditions.   Flow  character-
istics after leaving the diffuser will depend on the type of cover  material,
currents, pipe size, flow rate, and the height of the diffuser above  the
bottom (Barnard, 1978 and Hand et al., 1978).


     8.3.3  Surface Sealing


          8.3.3.1  General Description


     Cement, quicklime, or other grouting materials can be applied  to the
surface of or mixed with bottom sediments to create a seal which minimizes
leaching and erosive transport of contaminated sediments.

     Grouts may be applied to the surface of bottom  sediments  using a number
of approaches.  These methods can generally be divided into two categories:
those which involve storm diversion and those which do not.

     There are essentially two approaches to sealing or stabilizing bottom
sediments following stream diversion.  The first is  to pneumatically  apply a
layer of concrete (shotcrete) or grout to form a surface seal.  The 01 in
Chemical Group pneumatically applied a 3-inch layer of concrete to  the  bed of
the North Fork of the Holston River in Virginia after the bulk of the mercury-
contaminated sediments had been removed (Brown, 1982).

     The second method is to mix concrete, quicklime, or a grout with the
contaminated sediments in order to stabilize the sediments.  The stabilizing
agent is applied to the surface and mixed with the contaminated sediments
using rubber-tire or crawler-type rotor or trencher mixing equipment. The
Japanese have developed a soft ground crawler vehicle (the Soil Limer)  that is
designed to crawl freely on soft ground and stabilize the ground by
continuously and uniformly mixing the soft soil with slaked lime or cement-
based solidification agents.  The Soil Limer is equipped with  a pair  of
caterpillar tracks that consist of a pair of pontoons wound with light-metal
caterpillar bands by means of special rings.  Contact pressure is light and
the developer claims that it can float.  The mixing  unit is suspended between
two pontoons.  Both trencher and rotor types are available.  The depth  of
mixing can be adjusted with a hydraulic cylinder; mixing to depths  of 6.5  feet
is possible.  The tracks can then be elevated and the vehicle  can be  used  for
compaction.  The machine can be disassembled into three parts  for trans-
portation (Yamanouchi, 1978; Nissan Hodo, Co. Ltd., undated).

     Following completion of the sealing or stabilizing operation,  the
sediment bottom can be restored to its natural grade and sediment composition
in an effort to restore the habitat for benthic organisms.
                                     8-54

-------
     Concrete  and  quicklime  have  been used  in a number of cases to stabilize
contaminated sediment by  these methods.   The  Japanese  have used the Soil Limer
in numerous cases, but  no information is  available on  leaching of soil stabil-
ized using this method.

     Grouts and sealants  can conceivably  be  applied to cover or cap atop
contaminated sediments  or spilled material without diverting stream flow.

     Methods that  have  been  used  for  applying concrete underwater include:
concrete pumps and grouting  preplaced aggregate.   The  diffuser head could also
be used for this purpose.

     Mobile concrete pumps,  which may be  barge  mounted or used on shore, are
widely used for placing concrete  underwater.   The  mobile  unit  has a variable
radius boom and may be  used  economically  at  either large  or small sites.

     Grouting of preplaced aggregate  is a method which may be  used in flowing
streams.  A coarse aggregate or combination  of  several types of aggregate are
preplaced in forms.  Grout made of  cement, sand, and water can then be forced
through pipes to fill the voids in  the aggregate (Portland Cement Association,
1979).

     The U.S. Army Engineers Waterways Experiment  Station proposed the use  of
a modified diffuser head  for use  in applying  cement cover on the bottom. A
diffuser device which would  lay the grout down  in  even bands would be most
useful.  The diffuser head could  conceivably  be used to apply  concrete,
bentonite, silicic or other  grout types (Hand,  1978).


          8.3.3.2  Applications/Limitations


     Surface sealing methods which  involve the  use of  stream diversion are
limited to shallow waters with a  low  flow velocity,  where diversion can be
accomplished cost-effectively.  The major advantage of this method is that  it
is unlikely to stir up  the sediments  and  create downstream contamination.
Stream diversion also simplifies  the  application of grouts or  sealant
materials.

     Sealing methods which do not employ  diversion are applicable to deep open
water, where bottom currents are  not  sufficient to erode  the cap.   These
methods will provide less resuspension of bottom sediments than in-situ
injection methods  (Section 8.3.4).  Also  sealing methods  such  as concrete
pumps can potentially be  used in  confined areas not  accessible to barge-
mounted injection  systems.   However,  the  grout  or  sealant  may  impact the water
column during application, application methods  would be slow,  and it may be
difficult to obtain complete coverage.

     Use of the diffuser  head for surface sealing  requires further
investigation.  Placement of the  diffuser would be difficult,  though it  could
be checked by remote television or  perhaps by divers,  depending on water
clarity and on the material  being covered.  A hydraulic crane  or other rigid

                                      8-55

-------
positioning system might be used to provide accurate placement and control of
the diffuser head.  The diffuser head could conceivably be used to apply
concrete, bentonite, silicic, or other grout types.  Application rates using
the diffuser head are expected to be slow.


     8.3.4  In-Situ Grouting


          8.3.4.1  General Description


     The stabilization of contaminated sediments can be achieved through the
injection of grouting materials into sediments.  Chemical injection using
clay-cement or quicklime has been used widely, particularly by the Japanese,
for stabilizing bottom sediments prior to the construction of port and harbor
structures.  A commonly used Japanese method for grouting with clay-cement is
the Deep Cement Mixing Method.  The system shown in Figure 8-18 consists of a
number of injection pipes mounted on a barge; the injection pipes are
connected to mixing pipes that enter the sediments.  Similar equipment is
available for deep mixing with quicklime.  The process is completed by
lowering the operating-mixing apparatus (mixing blades are located within the
individual shafts) to the required depth and injecting a cement or lime-based
slurry into the sediments.  The mixing blades are then reversed and the shafts
are removed and relocated (Takenaka Doboku, Co. Ltd., undated).

     A number of other types of grout injection and mixing apparatus are
available.  Continuous mixing apparatus are available and eliminate the need
to continuously raise, relocate and lower the mixing apparatus.


          8.3.4.2  Applications/Limitations


     Theoretically, in-situ grouting methods could be used to stabilize
sediments to depths of about 80 to 130 feet below sea bottom (Takenaka Doboku,
Co. Ltd., undated).  However, the feasibility and reliability of these methods
for contaminated sediments has not been demonstrated.  The use of in-situ
methods is restricted by barge orientation, which limits offshore activity to
calm waters and periods of good weather.  Injection may result in considerable
resuspension of sediments.


     8.3.5  Technology Selection/Evaluation


     In-situ methods have potential use as an interim or emergency measure
until dredging can be undertaken or as a primary remedial action where it is
determined to be more cost-effective than removal. The biggest advantages to
the use of in-situ methods are that they are generally much less costly than
dredging, eliminate the need for dredged material management, and minimize


                                     8-56

-------
              FIGURE8-18. FIXATION BY DEEP CHEMICAL MIXING METHOD
                                                Cementing Agent Injector
                                                      Source: Hand. 1978
resuspension of contaminated sediments.  Many  in-situ  methods  also have the
advantage that they can be implemented quickly  and  beneficial  results will be
almost immediate.

     In-situ methods for containing hazardous wastes  are  a relatively new
technology, and the long-term effectiveness  and reliability of these methods
are not well known.  EPA, State Officials, and  responsible parties interested
in implementing in-situ methods will need  to conduct  a detailed site inves-
tigation and laboratory- or pilot-scale  studies to  determine the suitability
of a particular site for in-situ containment.   Given  the  existing state-of-
the-art, this will result in considerable  costs and project delays.  For
example, contaminated sediment boundaries  and bottom  currents  must be
carefully mapped prior to undertaking capping.   Studies may be required to
determine the leachability of contaminants through  the capping material.
Up-to-date performance data on such sites  as Rotterdam Harbor, Netherlands;
Stamford-New Haven Harbor, Connecticut;  and Holston River,  Virginia, where
in-situ methods have been undertaken should be  obtained.   Data from these
sites should be evaluated to determine the susceptibility of the caps and
covers to leaching, effects on benthic organisms, and  the relevance of these
data to the proposed project.
                                     8-57

-------
                                  REFERENCES
Alluvial Mining and Shaft Sinking Co., Ltd.  1984.  Equipment and Services
Brochure.  Basildon, England.

Barnard, W.D.  1978.  Prediction and Control of Dredged Material Dispersion
Around Dredging and Open-Water Pipeline Disposal Operations.  T.R. DS-78-13,
U.S. Army Engineers Waterways Experiment Station, Vicksburg, MS.

Bokuniewicz, H.  1981.  Burial of Dredged Sediment Under the Sea Floor:  Can
you do it?  In:  Proceedings of the 14th Annual Dredging Seminar.
TAMU-SG-83-103.  Texas A&M University, November 12-13.

Brown, J.C., Olin Chemical Group.  1982.  Letter to M. Ferguson, Virginia
State Water Control Board.  Subject:  Plans and Specifications - River Bottom
Excavation Project, Saltville, VA.

CH M Hill and Ecology and Environment, Inc.  1983.  Source Control Feasibility
Study: OMC Hazardous Waste Site, Waukegan, Illinois,  EPA Contract No.
68-01-6692.  REM/FIT Zone II.  USEPA, Washington, DC. 1983.

Church, H.  1981.  Excavation Handbook.  McGraw-Hill Book Company, New York,
NY.

Clark, G.  1983.  Survey of Portable Hydraulic Dredges.  T.R. HL-83-4.  U.S.
Army Engineers Waterways Experiment Station, Vicksburg, MS.

d'Angremond, K. et al.   1978.  Assessment of Certain European Dredging
Practices and Dredged Material Containment and Reclamation Methods.  T.R.
D-78-58.  U.S. Army Engineers Waterways Experiment Station, Vicksburg, MS.

Godfrey, R. (ed.)  1984.  Building Construction Cost Data.  Robert Snow Means
Co., Inc., Kingston, ME.

Hand, T., A. Ford, P. Malone, D. Thompson, and R. Mercer.   1978.  A
Feasibility Study of Response Technologies for Discharges of Hazardous
Chemicals That Sink. U.S. Army Engineer Waterways Experiment Station,
Vicksburg, MS.

Huston,  J.  1976.  Techniques for Reducing Turbidity Associated with Present
Dredging Procedures and  Operations.  C.R. D-76-4.  U.S. Army Engineers
Waterways Experiment  Station, Vicksburg, MS.

JBF Scientific Corporation.  1978.  An Analysis of the Functional Capabilities
and Performance of Silt  Curtains.  T.R. D-78-39.  Office, Chief of Engineers,
U.S. Army.  Washington,  DC.  182 pp.

Jepsky,  J.   1981.  New Radar System Provides Accurate Dredge Positioning.
World Dredging and Marine Construction.  August,  p. 24.
                                      8-58

-------
                            REFERENCES (continued)
Johanson, E.E., S.P. Bowen, and G. Henry.   1976.   State-of-the-Art  Survey and
Evaluation of Open-Water Placement Methods.  D-76-3.  U.S. Army Waterways
Experiment Station, Vicksburg, MS.

Linsley, R. and J. Franzini.   1979.  Water-Resources Engineering.   3rd  ed.
McGraw-Hill Book Company, New  York, NY.

McLellan, S. et al.  1982.  Evaluation of the Use  of Divers  and/or  Remotely
Operated Vehicles  in Chemically Contaminated Waters.  JRB Associates.
Prepared for:  USEPA, Edison,  NJ.

Meritt, F.  1976.  Standard Handbook for Civil Engineers.  McGraw-Hill  Book
Co., New York, NY.

Morton, R.W.  1980,  Capping Procedures as  an Alternative Technique to  Isolate
Contaminated Dredge Material in the Marine  Environment.  DAMOS Contribution
No. 11.  New England Division, U.S. Army Corps of  Engineers.

Mud Cat Division, National Car Rental.  1983.  Aquatic Weed  Harvester.
Undated brochure.

Nawrocki, M.  1976.  Removal and Separation of Spilled Hazardous Materials
from Impoundment Bottoms.  EPA-600/2/76-245.  Contract No. 68-03-0304.
Hittman Associates, Inc.  Prepared for:  USEPA,  Industrial Environmental
Research Laboratory.  Cincinnati, OH.

Nipak.  1980.  Sewer Rehabilitation with Nipak Polyethylene  Pipe.   Appeared in
February 15, 1980 Advertisement.

Nissan, Hodo Co., Ltd.  Undated.  Soil-Lime-Product Literature.  Tokyo, Japan.

O'Donnell, W.  1980.  Advancements in Electronic Positioning and Volume
Computation for the Hydrographic Survey and Dredging Industries.  World
Dredging and Marine Construction.  March.   p. 19.

Palermo, M.R., R.L. Montgomery, and M.E. Poindexter.  1978.   Guidelines for
Designing, Operating, and Managing Dredged  Material Containment Areas.
Dredged Material Research Program.  Technical Report DS-78-10.  Prepared  for:
Office, Chief of Engineers, U.S. Army, Washington, DC.

Portland Cement Association.   1979.  Design and  control of concrete mixtures.
12th Edition.  Skokie, IL.  139 pp.

Raymond, G.  1983.  Techniques to Reduce the Sediment Resuspension  Caused by
Dredging.   In:  Proceedings of the 16th Texas A&M  Dredging Seminar,  College
Station, TX.

Richardson Engineering Services, Inc.  1980.  Process Plant  Construction
Estimating Standards.  Vol. 1.   Solana Beach, CA.

                                     8-59

-------
                            REFERENCES (continued)
Richardson, T. et al.  1982.  Pumping Performance  and Turbidity  Generation  of
Model 600/100 Pneuma Pump.  T.R. HL-82-8.  U.S. Army Engineers Waterways
Experiment Station, Vicksburg, MS.

Sato.  1976.  Dredging Techniques Applied to Environmental Problems.   World
Dredging.  November,  p. 32.

Slickbar Co.  1983.  World Leader in Oil Spill Control.   Southport,  CT.

Takenaka Dobuku Co. Ltd., Takenaka Komuten Co., Ltd., and Toyo Construction
Co., Ltd.  Undated.  Chemical Mixing Method.  Product Literature.  Japan.

Tao Harbor Works.  Undated.  Tao Leaflet 78-N-610.

Toyo Construction Co., Ltd.  Undated brochure.  Tokyo, Japan.

USEPA.  1980.  Environmental Emergency Reponse Unit Capability.  Edison, NJ.
26 pp.

Van Leeuwan, W.C.H. Kleinbloesem, and H.J. Groenewegan.   1983.   A Policy Plan
for the Disposal of Dredged Material from the Port of Rotterdam, and  a Special
Way of Dredging and Disposing of Heavily Polluted  Silt in Rotterdam.   In:
World Dredging Congress, Singapore, April 19-22.   pp. 499-525.

Vaughn Co. Inc. 1985.

Wentzell, H.  1983.  Polarfix.  A New Concept in High Accuracy Position
Fixing.  World Dredging and Marine Construction.  May 1983.  p.  9.

Willmann, J.C. J. Blazevich, and H.J. Snyder.  1976.  PCB Spill  in the
Duwamish-Seattle, WA.  In:  Conference on Control  of Hazardous Materials
Spills.  April 25-28,
New Orleans, LA.  p. 351.

World Dredging and Marine Construction.  April 1983.  Lasers Assist  in
Precision Underwater Excavation,  p. 26.

Yamanouchi, T., K. Gotah, K. Yasuhara, and N. Yonemura.   1978.   A New
Technique of Lime Stabilization of Soft Clay.  In:  Symposium on Soil
Reinforcing and Stabilizing Techniques, Sydney, Australia, p. 531.

York Wastewater Consultants.  1983.  Characterization, Definition, Evaluation,
and Removal of Mill River Bottom Sediments at Mill River, Mill Pond  and
Vicinity, Stanford, CT.
                                     8-60

-------
                                   SECTION 9

                               IN-SITU TREATMENT
     One alternative to waste excavation and removal and conventional  pump  and
treat methods is to treat the wastes in-situ.   In-situ treatment  entails the
use of chemical or biological agents or physical manipulations which degrade,
remove, or immobilize contaminants; methods for delivering solutions to  the
subsurface; and methods for controlling the spread of contaminants and treat-
ment reagents beyond the treatment zone.  In-situ treatment processes  are
generally divided into three categories:  biological, chemical, and physical.
In-situ biodegradation, commonly referred to as bioreclamation, is based on
the concept of stimulating microflora to decompose the contaminants of
concern.  In-situ chemical treatment involves the injection of a specific
chemical or chemicals into the subsurface in order to degrade, immobilize,  or
flush of the contaminants.  Physical methods involve physical manipulation  of
the soil using heat, freezing or other means.  In many instances a combination
of in-situ and above-ground treatment will achieve the most cost-effective
treatment at an uncontrolled waste site.

     In-situ treatment technologies are not as developed as other  currently
available technologies for restoring contaminated aquifers.  However,  there
are some in-situ treatment technologies that have demonstrated success in
actual site remediations.  In addition, most of the methods are based  on
standard waste treatment technologies and are conceptually applicable  as
in-situ treatment methods.  Applicability of in-situ methods must generally be
determined on a site-specific basis using laboratory- and pilot-scale  testing.

     The following is a summary of promising in-situ treatment technologies.
For a more thorough description of the technologies and the factors involved
in the selection of an appropriate in-situ treatment approach, the reader is
referred to the literature, particularly Review of In-Place Treatment  for
Contaminated Surface Soils (USEPA, 1984a) and Evaluation of Systems to
Accelerate Stabilization of Waste Piles or Deposits (USEPA, 1985).
                                     9-1

-------
9.1  Bioreclamation
     9.1.1  General Description
     Bioreclamation is a technique for treating zones of contamination by
microbial degradation.  The basic concept involves altering environmental
conditions to enhance microbial catabolism or cometabolism of organic contam-
inants, resulting in the breakdown and detoxification of those contaminants.
The technology has been developed rapidly over recent years, and bioreclama-
tion appears to be one of the most promising of the in-situ treatment tech-
niques .

     Considerable research conducted over the past several decades has con-
firmed that microorganisms are capable of breaking down many of those organic
compounds considered to be environmental and health hazards at spill sites and
uncontrolled hazardous waste sites; laboratory, pilot, and field studies have
demonstrated that it is feasible to use this capability of microorganisms in-
situ to reclaim contaminated soils and groundwater.

     Microbial metabolic activity can be classified into three main
categories:  aerobic respiration, in which oxygen is required as a terminal
electron acceptor; anaerobic respiration, in which sulfate or nitrate serves
as a terminal electron acceptor; and fermentation, in which the microorganism
rids itself of excess electrons by exuding reduced organic compounds.

     The bioreclamation method that has been most developed and is most
feasible for in-situ treatment is one which relies on aerobic (oxygen-
requiring) microbial processes.  This method involves optimizing environmental
conditions by providing an oxygen source and nutrients which are delivered to
the subsurface through an injection well or infiltration system to enhance
microbial activity.  Indigenous microorganisms can generally be relied upon to
degrade a wide range of compounds given proper nutrients and sufficient
oxygen.  Specially adapted or genetically manipulated microorganisms are also
available and may be added to the treatment zone.

     Anaerobic microorganisms are also capable of degrading certain organic
contaminants.  Methanogenic consortiums, groups of anaerobes that function
under very reducing conditions, are able to degrade halogenated aliphatics
(e.g., PCE, TCE) while aerobic organisms cannot.  The potential for anaerobic
degradation has been demonstrated in numerous laboratory studies and in
industrial waste treatment processes that use anaerobic digesters or anaerobic
waste lagoons as part of the treatment process.  Using anaerobic degradation
as an in-situ reclamation approach is theoretically feasible.
                                      9-2

-------
     9.1.2  Applications and Limitations


     The feasibility of bioreclamation as an in-situ treatment  technique  is
dictated by waste and site characteristics.  More specifically,  those  factors
which determine the applicability of a bioreclamation approach  are:

     •  Biodegradability of the organic contaminants
     •  Environmental factors which affect microbial activity

     •  Site hydrogeology.

     Bioreclamation can be expected to reduce the concentration of only those
organic compounds which are amenable to biological degradation.  These are
compounds that are either substrates for microbial growth and metabolism  (the
organism uses the compound as a carbon and energy source), or are cometabol-
ically broken down as the microorganism uses another primary substrate as its
carbon and energy source•

     An extensive review of research on the relative biodegradabilities of
environmental pollutants can be found in Evaluation of Systems  to Accelerate
Stabilization of Waste Piles (USEPA, 1985).  Relative aerobic biodegradability
of compounds can also be estimated using laboratory data associated with
oxygen requirements for decomposition [i.e., 5-day and 21-day biological
oxygen demand (BOD-, BOD-,), chemical oxygen demand (COD), and  the ultimate
oxygen demand (UOD).J  Table 9-1 presents relative biodegradabilities  by
adapted sludge cultures of various substances in terms of a BODc/COD ratio.  A
higher BOD /COD ratio represents a higher relative biodegradability.   Chemical
Property Estimation Methods (Lyman, Reehl, and Rosenblatt, 1982) provides
additional information on methods of estimating biodegradability.

     Table 9-2 summarizes organic groups subject to microbial metabolism by
aerobic respiration, anaerobic respiration, and fermentation.   "Oxidation"
indicates that the compound is used as a primary substrate, and  "co-oxidation"
indicates that the compound is cometabolized.  These tables and estimation
methods provide only a general indication of degradability of compounds.  In
most instances, treatability studies will be required to determine degrad-
ability of specific waste components.

     For most compounds, the most rapid and complete degradation occurs
aerobically.  There are some compounds, most notably the lower  molecular
weight halogenated hydrocarbons, which will only degrade anaerobically.
[However, recent research conducted at the USEPA Robert S. Kerr Laboratory has
discovered degradation of TCE in the presence of oxygen and methane gas
(Wilson, 1984)].

     It can be generalized that for the degradation of petroleum hydrocarbons,
aromatics, halogenated aromatics,. polyaromatic hydrocarbons, phenols,
halophenols, biphenyls,  organophosphates, and most pesticides and herbicides,
aerobic bioreclamation techniques are most suitable.  For the degradation of
halogenated lower molecular weight hydrocarbons, such as unsaturated alkyl


                                     9-3

-------
                       TABLE 9-1.
BOD5/COD RATIOS FOR VARIOUS ORGANIC COMPOUNDS
Compound
Relatively Undegradable
Butane
Butylene
Carbon tetrachlonde
Chloroform
1,4-Dioxane
Ethane
Heptane
Hexane
Isobutane
Isobutylene
Liquefied natural gas
Liquefied petroleum gas
Methane
Methyl bromide
Methyl chloride
Monochlorodifluorome thane
Nitrobenzene
Propane
Propylene
Propyiene oxide
Tetrachloroethylene
Tetrahydronaphthalene
1 Pentene
Ethylene dicMonde
1 Octene
Morpholme
Ethylenediammetetracetic acid
Triethanolamme
o-Xylene
m-Xylene
Ethylbenzene
Moderately Degradable
Ethyl ether
Sodium alkylbenzenesulfonates
Monoisopropanolamme
Gas oil (cracked)
Gasolines (various)
Relatively DvgradaU* Icont'd.)
Furfural
2 Ethyl 3-propylacrotein
Methylethylpyndme
Vinyl acetate
Diethytene glycol
monomethyl ether
Naphthalene (molten)
Dibutyl phthalate
Hexanol
Soybean oil
Paraformaldehyde
n-Propyl alcohol
Methyl methacrylate
Acrylic acid
Sodium alkyl sulfates
Triethyhne glycol
Acetic acid
Acetic anhydride
Ethylenediamin*
Formaldehyde solution
Ethyl acetate
Octanol
Gorbitol
Benzene
n-Butyl alcohol
Propionaldehyde
n-Butyrslbehyde
Ratio

-0
-0
-0
-0
-0
-0
-0
-0
-0
-0
~0
-0
~0
~0
~0
-0
~0
-0
-0
-0
-0
-0
< 0.0X12
0.002
> 0.003
ซi 0.004
0005
<0.006
< 0.008
0.32
<0.35
0.3S
<0.36
0.37
<0.38
<0.39
0.42-0.74
<0.43
<0.43
Compound
Moderately Degradable (cont'd.)
Mineral spirits
Cyclohexanol
Acrylonitnle
Nonanol
Undecanol
Methylethylpyndme
1 Hexene
Methyl isobutyl ketone
Diethanolamme
Formic acid
Styrene
Heptanol
tec-Butyl acetate
n-Butyl acetate
Methyl alcohol
Acetomtnle
Ethylene glycol
Ethylene glycol monoethyl ether
Sodium cyanide
Linear alcohols 112-15 carbons)
Allyl alcohol
Dcxlecanol
Relatively Oegradable
Valeraldehyde
n-Decyl alcohol
p-Xylene
Urea
Toluene
Potassium cyanide
Isopropyl acetate
Amy) acetate
Chlorobenzene
Jet fuels (various)
Kerosene
Range oil
Glycerine
Adiponitrile
Relatively DegradaMe (cont'd.)
Ethyleneimme
Monoethanolamme
Pyndme
Dimethyllormamide
Dextrose solution
Corn syrup
Maleic anhydride
Propionic acid
Acetone
Aniline
Isopropy! alcohol
n-Amyl alcohol
Isoamyl alcohol
Crejols
Crotonaldehyde
Phthalic anhydride
Benzaldehyde
iMbutyl alcohol
2,4-Oichlorophenol
Tallow
Phenol
Benzoic acid
Carbolic acid
Methyl ethyl ketone
Benzoyl chloride
Hydrazine
Oxalic acid
Ratio

-0.02
0.03
0031
> 0.033
<0.04
0.04-0.75
< 0.044
<0044
< 0.049
005
>006
<0.07
0.070.23
0 07-0.24
0.07-0.73
0.079
0.081
<0.09
<0.09
>0.09
0.091
0.097

<0.10
>0.10
<011
0.11
<0.12
0.12
<0.13
0.130.34
0.15
-0.15
-0.15
-015
ฃ0.16
0.17

046
0.46
0 46-0.58
0.48
0.50
-050
>0.51
0.52
0.55
0.56
0.56
057
0.57
0.57-0 68
<0.58
0.58
0.62
0.63
0.78
-0.80
0.81
0.84
0.84
0.88
0.94
to
1.1
 Source: Lyman, Reehl and Rosenblatt, 1982
                           9-4

-------















ง
M
H
2
a
o
M
O
0
M
ซ

8

B
• w
cs >->
1 PQ
o> p
W
i-4 
rV\ f\
PQ PM
•< P
H 0
M
O

U
M
1
ซ
0
Cl_l
ง
><
^ฃ
y
M
co















































































c
0
Jปป
CO
•0

'x
o
1
o
CJ


c
o
XJ
C5
T3
• 1ซ
X
O
c
o
• *•
XJ
eg
4^
C
01
E
 •ซ-••-
01 -o t-> x
C •- it) O
a) — K a
^ cd u to
1-1 S >-i ai
, ซ c co ca
O> i-- ^i W O TJ V.
C C >s i— i i-" ซ••- 4)
•i-C8r-i- < -a x u
 o
T3 4-1 O CO -i- 4)
U'OOICt) CO 0) !-< CO 4J
ฃOliJV.ซi— T3X 01 <0
bOf^snOXxincai-icai-i
•^•ot.ui-x^:O4J)-''-o)w
eg C 3CDOI OOi^'QOIUCf
u v. cocoji-it-i cagco-r- & ฃ
wซcnsw<ซCo-<[dZ<3(X



/-N
•o
01
3
C
• ^*
4-1
c
o
u
s^




















+




















09
0)
C
• H
0
S
CO
o
1.
•M
• ^
f.
9-5

-------





















/— s
•o
0ป
D
C
4-1
C
o
0
^x

CN
1
ON
a
PQ
<•
ฃ


























C
.2
*
•o

X
0
1
o
u

c
0
• f-
4-t
CO
T3
X
o
c
o
• I—
4-1
CO
^J
c
0)
B
^
0)
fa

u

,0
0
C Oi
O CO
•~ s
•*-• **4
CO
u
Q.
CO u
41 •!-
OS XI
0
V.
3













U CO
4J T3
CO C
V. 3
4-1 0
CO O.
xi g
3 0
to cj



+ +









+ + +






+









•f +







+ + +



CO
o
•r* CO
4-1 U
CO •>-
E 4-ป
O TO
i- e
< 0
CO 1-
CU T> <
C 01
CO 4J f)
X CO CU
i-l C 4J
•< , C <0
HODS


,^
•o
+ + u
3
C
•r-
4^
c
O
o


+ * +






+ +









+ + + +







+ + + + + +


CO
•O •—
C ซ C
3 C -r.
O O co
a— jz
S ^ ^J ^ป
co O o x
•u o c cu o
0 C 3 -u ^
•- 3 O fa -r- -TJ
4-1 O 1- CO >,
co a. 4-1 vซ 33 co
งB "" 
-------
•o
 0)
 3
 C
 O
 o
CM
 I
w


H
                        4-J
                        CO

                        •O
                        O

                        o
                        c
                        o
                         X
                        o
                         c
                         o
CO


tu
                         
-------
halides like PCE and TCE, and saturated alkyl halides like 1,1,1-trichloro-
ethane and trihalomethane, anaerobic degradation under very reducing condi-
tions appears to be the most feasible approach in terms of our current under-
standing of microbial degradative capability.  However, aerobic degradation in
the presence of methane gas appears promising for some low molecular-weight
halogenated hydrocarbons.

     The availability of the compound to the organism will also dictate its
biodegradability.  Compounds with greater aqueous solubilities are generally
more available to degradative enzymes.  For example, cis-l,2-dichloroethylene
is preferentially degraded relative to trans-1,2- dichloroethylene.  The most
likely explanation for this is because "cis" is more polar than "trans" and is
therefore more water soluble (Parsons et al., 1982).  The use of surfactants
can increase the solubility and therefore the degradability of compounds
(Ellis and Payne, 1984).

     Environmental factors which affect microbial activity and population size
will determine the rate and extent of biodegradation.  Hydrogeology will
affect not only microbial activity, but also the feasibility of in-situ
treatment.  These factors include:

     •  Appropriate levels of organic and inorganic nutrients trace elements

     •  Oxygen concentration

     •  Redox potential

     •  pH

     •  Degree of water saturation

     •  Hydraulic conductivity of the soil

     •  Osmotic potential (including total dissolved solids)

     •  Temperature

     •  Competition, including the presence of toxins and growth inhibitors

     •  Predators

     •  Types and concentrations of contaminants.

     Microorganisms, like all living organisms, require specific inorganic
nutrients (e.g., nitrogen, phosphate-phosphorus, trace metals), and a carbon
and energy source to survive.  Many organic contaminants provide the carbon
and energy and thus serve as primary substrates.  If the organic compound
which is the target of the bioreclamation is only degraded cometabolically, a
primary substrate must be available.  Aerobes need oxygen, nitrate respirers
need nitrate, and sulfate respirers need sulfate.  Various anaerobic
populations require specific reducing conditions.  Optimum microbial activity


                                     9-8

-------
for bioreclamation purposes occurs within  a  pH  range  of  6.0  to  8.0,  with
slightly alkaline conditions being more  favorable.

     The temperature range for optimal organism growth in  aerobic  biological
wastewater treatment processes has been  found to range from  20ฐ to 37ฐC
(68ฐ to 99ฐF).  According to the  "Q-10"  rule, for every  10ฐC decrease  in
temperature in a specific system, enzyme activity is  halved.  Figure 9-1
illustrates typical groundwater temperatures throughout  the  United States.
Although microbial populations in colder waters  are adapted  to  lower temper-
atures, biodegradation rates can be  expected to  be much  slower  than at higher
temperatures.  It may not be feasible to attempt a bioreclamation  approach  in
the extreme north.

     Concentrations of inorganic and/or  organic  contaminants  could be  so high
as to be toxic to the microbial populations.  Table 9-3  lists concentrations
at which certain compounds have been found to be toxic in  industrial waste
treatment.  Microorganisms present in the  subsurface  may be  more tolerant to
high concentrations of these compounds.  This determination  must be  made on a
case-by-case basis.  Conversely, a situation may prevail in  which  the  contami-
nant concentrations are so low (<0.1 mg/1) that  the assimilative processes  of
the microorganisms are sometimes not stimulated,  thus adaptation to  the
particular substrate will not occur  and  the  substrate will not  be  degraded
(SCS Engineers, 1979).  It is also possible  that even if the  contaminant is
present in acceptable concentrations, if there  is another  "preferred"  carbon
source available, the microorganisms will  catabolize  it  preferentially.

     It is feasible to manipulate some of  these  factors  in-situ to optimize
environmental conditions.  Nutrients and oxygen  (or NO-^ ) can  be  added to  the
subsurface.  It may be feasible in some  cases to enhance reducing  conditions,
thereby lowering the redox potential.  The pH can be  adjusted with the
addition of dilute acids or bases.   Water  could  be pumped  into  an  arid zone.
Bioreclamation could be preceded by  other  treatments  which could reduce  toxic
concentrations to a tolerable level.  Even raising the temperature of  a
contaminated zone by pumping in heated water or  recirculating groundwater
through a surface heating unit may be feasible under  conditions of low ground-
water flow.  This was done at a bioreclamation site in West  Germany  to
increase the groundwater temperature 10ฐC  (See Table  9-4)  (Stief,  1984).

     There are some factors that cannot  be corrected, such as the  presence  of
predators, competition between microbial populations, or the salinity  of
groundwater.  This points to one of  the  advantages of relying on indigenous
microorganisms rather than added microorganisms  to degrade wastes.   Although
the added specialized microorganisms may have a  superior degradation
capability as developed in the laboratory or enriched in a surface biological
reactor, they may not be able to survive subsurface conditions  (e.g.,
salinity, light intensity, temperature,  type of  predators).  However,  through
countless generations of evolution, natural  populations  have developed which
are ideally suited for survival and  proliferation in  that environment.   This
is particularly true of uncontrolled hazardous waste  sites where micro-
organisms have been exposed to the wastes for years or even decades.   However,
use of specialized microorganisms can be expected to  have the greatest
                                     9-9

-------
                                    FIGURE 9-1.
TYPICAL GROUNDWATER TEMPERATURES (ฐF) AT 100 FT. DEPTH IN THE UNITED STATES
               47
 52ฐ
     62ฐ
         67ฐ 72ฐ
                             67ฐ
                           Source: Johnson Division, UOP Inc., 1975
                                      9-10

-------
                                  TABLE 9-3.
                 PROBLEM CONCENTRATIONS OF SELECTED CHEMICALS
Chemical
      Problem Concentration  (mg/1)
                                       Substrate
                                                 (1)
                      Non-Substrate
                                    (2)
n-Butanol
sec-Butanol
t-Butanol
Allyl alcohol
2-E thy1-1-hexano1
Formaldehyde
Crotonaldehyde
Acrolein

Acetone
Methyl isobutyl ketone
Isophorone

Diethylamine
Ethylenediamine
Acrylonitrile
2-Methyl-5-ethylpyridine
N,N-dimethy1aniline
phenol

Ethyl benzene
Ethyl acrylate

Sodium acrylate
Dodecane
Dextrose
Ethyl acetate
Ethylene glycol
Diethylene glycol
Tetraline
Karosene
Cobalt chloride
>1000

500-1000

200
>1000
>1000
MOOO
>1000
MOOO
MOOO

MOOO
600-1000
MOOO
MOOO
MOOO
MOOO

MOOO
MOOO
MOOO
MOOO
MOOO

50-100
50-100
MOOO
MOOO
300-1000
100-300
100
100

300-1000
300-600

>500

MOOO

>900
MOOO

>500
MOOO
(l)Substrate limiting reprsents the condition in which the subject compound  is
   the sole carbon and energy source.
(2)Non-substrate limiting represents the condition in which other carbon and
   energy sources are present.
Source:  SCS Engineers, 1979
                                       9-11

-------






























^
1
er
W
iJ
53
H


















































K>
8
i_^

<;
CD
g
O
05
o
M

CO
D
O
BE
u



M
•V
Z
O
H
<
s
2
CD
ง
O
M
PQ
CD
Z





w
o

H
3
O
w
Pd


p


w















V
u
e
01
V
UJ
01
K








n
C

j









C
i
CO
4)
H







U
•H
m jj
H
Cft ki
4J
4-1 U
09 tO
3 €





C
CO
• H


c
8




C
o
• H
LJ
to
u







C vC
O r-
• H f-
E
tq *
•-) C
O
C 3
0 EC
1,,
tQ E
OS to
k,
01 ...
ซH C
3 4)
o- E
C 4)
• H kt
U
UH ki
i— 1 4J
M-J
II
*0 w
to c
n o
M E
ฃ2

C

3

TJ
5.
o
ki
4)
>
O
0)
^
ro
X
ฃ




ki

U 10
CD
ป C
•S"
3 C
ฃ-3
(Q
1.5
"!
O O





^
•ft
p.
09
4)
C
• H

O
to
U



P-
k> (N
4) r-.
i-i OS
r















i
o
w
r- TJ
*
0 to
kl ki
U-i bo
•C TJ
0>
4J 10
.5 k!
4-* kl
IB fl)
CJ ฃ


n

i-i
•* ฃป•
OJ 0
OC 60 f<
ki e ซ*•*
CO -H
ft- (J kl
W30)
TJ *-•
H 6 ro
C
3
•O . O
OJ n k,
M i~* 6l>
OJ f-ซ
.5 ft 1!
41 42 •-*
TJ M O
.S|g








P
3.
tO
0>
4J
>fl
O






















oc





^
to

0)
1
o
i,
to

w
01
4-1 _4
U O 1
0) C
0> ฃ
4J •- 0)
u 0 >
3 to 4)
TJ ki fH
5 60
ki O 01
O. ki "-<
0) (0
kl *0 ft.
TJ 0
O C U
z 01 0

c
•H I eo


43 O 4) •
W TJ ft ft
TJ Ot O
oi jj oo be fj
ป e f- e •> CO Pu TJ
s . .. g
SSI ซ ฃ
U 41 kl *H bO
D E i* •"•*
kl 4J > OJ -O
ซ -H > 01
to ki oi jr -<
(J 4J TJ 60 O
ฃ>H -H ฃ 0
V U U o

>,
1
to
k> to
0)
4J ซ

|.S
gง
kl -H
60 4J
to
TJ B
C -H M
CO ฃ 0)
ซ u-i
HI'I
en u to





-H

a
to

C

O
o
•-}
z

01

> r-

.fi
X

t*
OC



"

to
4J
f
bC
3
e

S
w
u
3
s-g
4) t-
4i 0)
C 0)
O k-
U-I
Oi O
Z c
(0
kl J=
€ f. u
CO (0 TJ

1
C
.H 1 4=
•i-t 4J U

TJ T) Ot >2
> e .2 '^ B
o oj y a 41
r-t >rt >-i O- kl
i-i k< U 3 4J
O 4J 4) ซ0
•"1 " M ง
>, kt *H -H
kl 41 < 4J
Ot • 4J tJ
S4-1 ซ 4)
C ft • ซ-i
S g *S fJ .S
a o w *w n
y 4J 60 E ซ
ฃ-H -f( ฃ O -H
ffl 4J 4J 43 T)




kl
41
4J 0
0 kl
3 C 41
7T ;7.T!
3 (! 0= 3
o o M er
ki 'i-i *^ ซ
60 *J JC
tO 0)
i f-i 4)
^J^-S E
S SS tt





_^
to
0)
1-1
0)
B

i
to

g

4>
00
C CN
to oo
ki OS
s"






$
a-
TJ •—
c
w -
•f-< U
ki U
41 CO
> M
CD N
ฃ ro

ง1
TJ
^ ง
0 0
TJ 4J kl
OJ OC
3 i c
TJ O -i-1
0) T)
k> CO
fri (0
B ~Mf^
O B
•H k.
AJ O O
4J *•**
COM
01 4J p
U
B O -H
O O •

f
• H


.a ^
. c
|| ..
O W *
f-t 0) •!•!
O 4-1 ffl
X ซ O
ki u O
01 -H ki
gbO u
0 ซrซ
s-s B
"S ง
O 0 0)
ฃS!1
& to .1-1

kl
>1
CO
ki i-l
0)
4J 10
to
3 C
TJ -H f-
O O 4J
k> .fl
0 CO
TJ B 'H
f M
•"H C ^
woo




g g
0 .H
3 ซH


0) -
C 4t i-l
.2 "S ^
X kl 4J
jS O V
r u TJ
to
•iS

4-1 jฃ
W-l u

ki 3 oo
O TJ OS
3S-

















CO
01
i

ki
OJ
• I
kl kl
0) oo
4J O
ซ kl

u
C 60
4! C
E -H
4J U
0> T> 01
ki 0 U
3 TJ
u C
• H . 3
n to O
C <-< 60
•f< 0)
, *1
iJS

-H U C
0)
01 ซ9 4) f-
H 3 5 ซW























4>
O

ro










fs]
OC


ki
- to


Zl
41
4>
•3,3<
6C 00
tD B O"



4^
i-H
ro
o-
kl
4>
u
60 T)
E 4>
•_2 "
B TJ
k< ki
o a




01
u
0
*4J
3 6
co 01
J=
O *->
4J
•sg
B 8
1ฐ^

4-* 3 kl
TJ 01 -H
ฃ ฃ o)
O 4J kl


kl
0)
ki U-l
4) -H

0 cr
ป B a
•O 'H
1 ง5"
I..H 01
Ms s
TJ B ki
S'S^?
10 >,
o o 0
en u ซ



4>
TJ
•i-l
C
0

U

i ซ
4) *J
*0 3
ki TJ
4J O
* a

c
* (0
0) E
jc C
3 4)

n oo
i-l 4J OS
kl 00 —1
0 01









00
o*
K
U-i
Oi

to

C 0
bC
to 4)
U U i
e ki
ki (0

• H
C0 4-)
f 0
4J J
c ^-
O -H
slS

c
•H


0) 4J
f5 ซ ฃ
O 4J TJ
X B
ki to
g4-ป C
e 49
U 01
a> e c
W -H
o w 2
|.H S

x
*f*

kl -H
4) J3
4J 0 ra
0 0)
ft e e
TJ ซn C
o o
ki *ft 42
0 >H
TJ C 42
S1,;
f-i *J TJ
-H C C
o o 0



60
1 E
O -fซ
P TJ
•0 3

B J3 O

O.s--
•H 4J tO
4J 0 E
0 or o
ง.?•ฃ
< 0 0

t-f E
0 0
f 1
E 4)


E 4J
0 tO
ki OJ
(* *

























4<
ki

OJ O k<
3 ^ |
• E 4*
0 05 U 4J
ฃ 3 f- ซ
H U^ U-I O
E o
TJ -0 • O
IM 01 ฃ B fH
0 -fC T3

11 ฃ g .5











ki
0)
3
cr
to




s ป
4) E 01
k> 41 E



* . 5
S E 0"
0) oi C
N 3
.fl ^ 0








9-12

-------
























^
T)

g
C
• H
C
O
O
1
er
S
3
H

1
t
\



























i
01
u
ฃ
ฃ
*









ซ
4J
C
E
5











Treatment





K>
01 *->
*j ป
•H •ซ-<
W t-i
0)
ft) *J
09 9


6


e
to
c


c
5



,

c
0
'^1
ซJ
U





sf t
u

II
.-. o
ce "5
& c
.8 c
1- t- O
4S =
S,
o
c

.2
4J
S


0)
^"
S3
1- i—
ฃ i
i
c
^ T5
* S
•o o
oi e a. *j
5 01 o
5 S a c
IFH kl O *H
O -C ซ —
U 9-s |
PC C C
x a; -H
h bC
oi • Kซe •
g*J K * M
C O T 0)
U 01 *t) *J
(U E ซ ซ ซ
i- ZJ (C ป
ซ (0
^- OI 0) *J -C
ซ ^ T e o)
•H K -H 0
n 3 O b ?>
ซ-S 8.1 ฃ
^
?
h 2
10
Te
0 0
60 *••
ซ

* *i ฃ
^-t *j .*•<
•^ C 3
0 O (T
Wi y a


U

0)
.S
O
03
S



z

*

o> •*
60 CO
c a*
0} — '
O


c
o
>• tr
k OC
e o
*".
" t-
f- o;
ฃ ง
** 5
o> 5-

0)
u
c
I
u
0
cc
*j a

JI
to 'i-(
ฃ u

•g
. H

'S S.^
e *o
(Q j ^,
treatment pi
s and hydros
added to rec
ter.
ซ|
-1
•-i 0
! 'H h
Z > M
x
1 _C •"
*B ' M-2
3 C J2
ฃO cd
• H tl
1 "g I |
* fi a
r-l *J O
.H C ,M
SO
u - t-<
aT ซ Si*^
i *J *J  e o>
n u M> ซ ^
V
u
o
ฃ

•M X
< H

X "CO
^-l 4ป ffi
^- ซ ^H
ฃ (S
9-13

-------
application at spill sites where the exposure time has not been long enough
for a substantial adapted indigenous population to evolve.

     Significant and active microbial populations have been found in the
subsurface.  Many types of bacteria have been isolated from subsurface soils
and groundwater, and a considerable amount of research has recently been
conducted to enumerate and characterize subsurface populations (e.g., Hirsch
and Rades-Rohkohl, 1983; White et al., 1983; Ghiorse and Balkwill, 1983;
Wilson et al., 1983; Ehrlich et al., 1983, Ventullo and Larson, 1983; and
Harvey, Smith, and George, 1984).

     Research confirms that substantial adapted populations do exist in
contaminated zones and that bacterial numbers are elevated in contaminated
zones relative to uncontaminated zones, i.e., the organic contaminants are
being metabolized, leading to an increase in bacterial biomass.  For example,
in one study, significant bacterial populations were found in groundwater
contaminated with gasoline, fuel oil, and other petroleum products (Litchfield
and Clark, 1973).  Groundwater containing less than 10 ppm of these hydro-
carbons generally had populations of less than 10  organisms/ml, whereas
groundwater,with greater than 10 ppm hydrocarbons contained populations on  the
order of 10  organisms/ml.  An investigation of a hazardous waste site
contaminated with high concentrations of jet fuel hydrocarbons, industrial
solvents, and heavy metals revealed bacterial numbers on the order of 10
cells/wet gram sample in core samples taken from the upper unsaturated zone
and the saturated zone (Wetzel, Henry, and Spooner, 1985).  A biodegradation
study conducted with subsurface soil and groundwater from this site revealed
that both aerobic and anaerobic populations were present that were capable of
degrading the organic contaminants.

     Even if substantial, active microbial populations are present, the wastes
are biodegradable, and there are parameters that can be altered to optimize
biodegradation in-situ, bioreclamation will not be feasible if the hydro-
geology of the site is not suitable.  The hydraulic conductivity must be great
enough and the residence time short enough so that added substances, oxygen,
and nutrients for example, are not  "used up" before reaching the distal
portions of the treatment zone.  Sandy and other highly permeable sites will
be far easier to treat than sites containing clayey soils.

     There is also the possibility  that added substances may react with the
soil components.  Oxidizing the subsurface could result in the precipitation
of iron and manganese oxides and hydroxides.  If this is extensive, the
delivery system and possibly even the aquifer could become clogged.  The
in-situ bioreclamation of a site near Granger, Indiana developed problems with
precipitation and clogging of the aquifer (see Table 9-4).  Addition of
phosphates could result in the precipitation of calcium and iron phosphates.
If calcium concentrations are high, the added phosphate can be tied up by the
calcium, and would therefore not be available to the microorganisms•

     Heavy metals, bound in the soil matrix, could be mobilized into  the
groundwater.  In reduced conditions, especially when there is ample organic
carbon available, metals are likely to be bound in the soil as organic/metal


                                     9-14

-------
chelates and as sulfides.  When oxidized, the metal cations  could  coprecipi-
tate with ferric hydroxide and/or precipitate in  calcium/phosphate complexes.
If iron and phosphate precipitation does not occur to a  significant  extent,
the soluble metallic cations will remain in the aqueous  phase.   The  soils may
also plug as a result of excess biological growth.


     9.1.3  Design Considerations


     Biological treatment at contaminated sites encompasses  both in-situ
treatment approaches and treatment approaches involving  groundwater  withdrawal
and treatment in biological reactors on the surface.  This section addresses
in-situ treatment and the combined use of in-situ and aboveground  treatment.
          9.1.3.1  Aerobic Bioreclamation
     The first site remediation to treat hydrocarbon contamination in-situ was
conducted by Raymond, Jamison, and coworkers at Suntech in the early  1970s.
The first treatment approaches involved stimulating the indigenous microflora
through the delivery of nutrients and air to the subsurface.  Considerable
developments have been made since the early 1970s, and many different treat-
ment approaches have been used successfully to enhance biodegradation in
contaminated zones.  The indigenous microflora have been used in some site
cleanups to degrade wastes.  Specialized microorganisms, either adapted
strains or genetically altered strains, have been used at other site remedi-
ations.  Air was used in the earlier site remediations to provide oxygen.
Hydrogen peroxide or possibly ozone now appear to be feasible alternatives to
air or pure oxygen as a oxygen source.  The earlier applications involved
gasoline spills (Raymond, Jamison, and Hudson, 1976).  Biological degradation
is now being tested at a hazardous waste disposal site which contains a com-
plex range of organics (Wetzel, Henry, and Spooner, 1985).  Table 9-4 lists
site reclamations that have involved stimulating the indigenous microflora.
Table 9-5 lists site reclamations in which specialized microorganisms were
used.
               a.  Oxygen Supply


     Oxygen can be provided to the subsurface through the use of air, pure
oxygen, hydrogen peroxide, or possibly ozone.  Table 9-6 summarizes the
advantages and disadvantages of the oxygen supply alternatives.

     Air can be added to extracted groundwater before reinjection, or it can
be injected directly into the aquifer.  The first method, in-line aeration,
involves adding air into the pipeline and mixing it with a static mixer, for
example (Figure 9-2).  This can provide a maximum of approximately 10 mg/1 0_.
                                     9-15

-------








(A
UJ
H
(0
O
UJ
H


i
grf
O
u
^
z
• o

Ok ^*
id*

00 2
< UJ
i- oc
3!
o
5
S
o
CQ
U.
O
V)
UJ
Q.
5
ซ^
X
UJ



B
0
"i tป
73 b
•H 4J B
ffl C Q.
V 11 Q,
as u
e
0
u


e
B 9> 'go
ซj 5 x
4) H Q
b N^


a
u
o u
•3*
1*4
A




CO
u

(0
•H
0) 41 U
*•* fat 4)
03 -H 4J
(0 CA u
3 <0
Ui
•C
u

6
O
V
ซ|
b
B&
ซ a

|



e
v ซ E
ซ 5 ซ
> "
o
u

I-*
B
5
"
00
0)
u






ฃ


00
1
S

X
u
1

-•a
1-1 t>
ซM U

a B
0) -H
B
b a)
ซ0 W 00
u c
Jf 0 *•
B U O
2 ซt
1 2 -Sa
O 90 ^ w
kซ V
3 S "-5
ag b O C
PC M 4J ซrt



r>4






1
in

-H
B
0)
"
09
09
11






oo
CM


•ฃ> i-l
4 6
ฃ 8
1 |
1 1
i i
l-l H4
03 •


09

O O
0 B

B
O ^
2 "S "S
•2 ฃ j=
u. O. w
oi a
V 11
y M)
O i-( O
ui in w

^
2
a) ซ^
3 " S
5

?2
B ง
H
B e
O b
ซ u e
N 00 ฃ
u rt b
< in H

•H
B
9)
ฃ
44
tg
a
11






CM


ao
i
in
w
I
i
•Q




B
01
u
00-1
B O
b B
U ซ3
O <•>
U •
1-4 00
i-l b b
a. u ซ
in ซ 14-1



|
CM
•*



1)
II
*o S
b w
w ag
ฃa

rH
B
0)
4J
09
a

P^





O





u
PHENOBA



b
tl
4J
II
1
งง
00 W
•O B
B x
* s
II



ง
•t



rH
b
w
•rt
%
rH
K
hi
i

F*
B
a)
"
09
09
U






CM
CM





U
PHENOBA




41


-------
  1/3

  W
VD

 I
3 1
H 5
  Z
  w
  c




















CO
01
OC
to
4J
c

•^
T)
It
CO
•fH
P
















CO
4)
00
CO
4J
C
CB
<•
•o
O
JC
3i
e
0
CO
u
•fH
f-H
ex
Ct







41
u
e
IB
4^
CO
Xi
3
CO
41
O
CO
IH
4J

IH
O
UH

4J
a
41
O
X
4)

f-H
CO
CJ
• fH
4j
CJ
to
|j
a

4J
o
2


•









f-H
to

3
CO

CO
f-H
f-H
41



•






UH
O

X
f-H
ex
a
3
CO
4-1
C
CO
4-)
CO
e
o
f
•



U
r-^
a;
3
•4-1
ซ^H
CO
1
~


























































41

Xl
• fH
CO
CO
&

c
01
or

x
0


































1
E
ง
U
C P
4-> O O
ex u o
c
CJ UH fH
X 0 ^
01 OO
co E
fH fH
CO Ol IP
CJ > CN
.H O!
4J ,-H V
CJ
to ป c
IH O O
CLfH -H
4.J
4J IH CB
o o e



•



*>,
fH >1
X) 4-1
to -H e
W fH 0
41 -fH .,H
*fj Xi J-J
•H 3 CO
CO f-H IH
e o 41
O CO to
CJ
CNCO
CO C 41
41 O
•V IH -Q
> f d
O OC CO
VH *rH f
{L x: 4->
•






41
C
• rH
r-H
1
C
M
• fH

01 C
f 4)
U 00
• r^ ^i
^ jfcฃ
c o
w
1 0>
C P
4) 3
OO CM
rV,
X IH
O O
















41
^
• *4
CO
c
41
a
x
41

X
|H
41



•






UH
0

jV,
,_<
a
ex
3
CO
4-1
C

4J
CO
c
O
O
•



CO
t— t
SI
3
4J
•fH
CO
1
C
fH





















4J
3
0

3
O

t*i

O
4J

4-1
CJ
01
• f)
r*
3
CO

CO
fH
fH
41



•









41
r-H
f*>
•fH
CO
CO
o
a

e
01
00

x
o




































>^ "
fH r-H
*U "H
•H O
O- co
CO
fl X
4-1
CO "H
01 &
CO
0 4J
a o
งCB
4-1
0 C
01 O
•0 CJ

CNC
C 0
CNO-
SC 3


•











4J
CO
O
u
01
4J
to
IH
41
•o
ฃ

ซ






41
C
• rH
fH
1
r-H
1)
TJ
X
O
IH
4>
CM

C
41

O
IH
13
X
s





4-1
3
O

Ol

Xi
f"!
3
Xl

>s,
CO
E

c
01
OC

x
0

*^
c
to







,c

• H
^

M
C
• <-(
X
-1-(
e
41
4J
CO
E
•H
4-1
C
M
•































X
fH
In
4)
a-
o
IH
a

CO
CO
4)
fH
C
3

>>
r-H -f)
4) 0)
b N
3 -fi
4J fH
CO 'H
e x>
41 CO
IH 4J
D- CO



O i-H CN
•u — O Xi
ec 4-1
i -o e -< 1*
W 4) ^. O
IH -H O 00 CO IH
4j fH o E fH oc
c a^< ^ o
 -fi
cj 3 in S xi
C co o>
O O co o. >,
CJ 41 CO 01 41 >
fi XI UH -o 41 to
41 CN IH ปH ^ Ol
4J c t= 3 :> x:
to co co O O
3 IH CJ X> fl 4J UH
T3 41 3 O. O
C 4J CO CO CO
3 to c CN a. 01
O 41 O 41 C r- 1 O)
IH IH -H jC CN 01 p
OC U 4J jj gs EC UH
•





























01

• H
CO
e
41
0.
x
41

CO
• rH

c
o
• rH
4J
CO
IH
41
c

00


-------
                                        FIGURE 9-2
                            CONFIGURATION OF STATIC MIXER
                  Air
   Flow
Source: USEPA, 1985
                                           9-18

-------
This concentration is  sufficient  only  for  degradation  of  about  5 mg/1
hydrocarbons, and would therefore  provide  an  inadequate oxygen  supply.   A
pressurized line can increase oxygen concentrations  as can the  use of pure
oxygen.

     The equilibrium oxygen  concentration  in  water  increases  with increased
air pressure according to Henry's  Law  (Sawyer and McCarty,  1967):

where:    CL =  PIL

          CT = concentration of oxygen in  liquid  (mg/1)
           Lt

             = volume  fraction (0.21 for 0 in air)

          P  = air pressure  (atm)

          H,  = Henry's Law Constant for oxygen.

     The value of Henry's Law Constant  is  43.8 mg/1-atmosphere  at 68ฐF  (20ฐC).
 Pressure increases with groundwater depth at the rate of 0.0294 atmospheres
per foot.

     The use of in-situ aeration wells  (Figure 9-3)  is a  more suitable  method
for injecting air into contaminated leachate  plumes.   A bank  of aeration wells
can be installed to provide  a zone of  continuous aeration through which the
contaminated groundwater would flow.   Oxygen  saturation conditions can  be
maintained for degrading organics  during the  residence time of  groundwater
flow through the aerated zone.  The required  time for  aeration  can be derived
from bench-scale studies.  Residence time  (t  ) through the  aerated zone can be
calculated from Darcy's equation  (Freeze and  Cherry, 1979) using groundwater
elevations (i.e., head) and  hydraulic  conductivity  as  follows:
          t  = (L )2/K(h1-h2)
           L     cl      •*-  *•*
where:
          t  = residence time (sec)

          K  = hydraulic conductivity (ft/sec)

          L  = length of aerated zone (ft)
           3
          h  = groundwater elevation at beginning of aerated zone  (ft)

          ho = groundwater elevation at end of aerated zone (ft).

     In the design of an in-situ aeration well zone system, the  zone must  be
wide enough to allow the total plume to pass through.  The flow  of air must be
sufficient to give a substantial radius of aeration while small  enough to  not
cause an air barrier to the flow of groundwater-
                                     9-19

-------
                                           Figure 9-3
               POSSIBLE CONFIGURATION OF IN SITU AERATION WELL BANK
      Plane View
                                                                     Zone of Aeration
         Surface Contours.
                                                                        Direction of Groundwater Flow
Cross-sectional
View
A

c
1

^m<7
Y^M>
, ••••••
• 0 0
••*:
oO%
000
\
C


v: :
e o
* ft 0 0
• V . .
0 0 0


r o-o/.
0 '"'••.'
ซ ฐ o o
0 0 ฐ


.x'.'t
ป 9 • ฐ •
ซ • • ซ ,'
• o •ป!
0 • .
[/ x^


• o ป o
XX
• 0 ซ ^*
^•':i
^^^ Air Injection Wells
x^c^cg/y/^Cvj^'
^Aerated Zone
/^^ V
• 0
'•'. :
0 *
•
b
Source: USEPA, 1986
                                            9-20

-------
     Various methods can be used to inject air or pure oxygen.  Air has been
sparged into wells using diffusers.  For example, Raymond et al.  (1975),
sparged air into wells using diffusers attached to paint sprayer  type
compressors which could deliver approximately 2.5 cubic feet per  minute.  They
were fitted with steel end plates and fittings to accommodate a polyethylene
air line and a nylon rope and were suspended into the wells.

     A blower can also be used to provide the flow rate and pressure for
aeration.  At the groundwater bioreclamation project in Waldwick, NJ,
5 pounds per square inch pressure is maintained in nine 10-foot aeration
wells, each with an air flow of 5 cubic feet per minute (Groundwater
Decontamination Systems, Inc., 1983).

     Microdispersion of air in water using colloidal gas aprons (CGA) creates
bubbles 25 to 50 micrometers in diameter.  This is a newly developed method
which holds great promise as a means of introducing oxygen to the subsurface
(Michelsen, Wallis, and Sebba, 1984).  With selected surfactants, dispersions
of CGA's can be generated containing 65 percent air by volume.

     Oxygenation systems, either in-line or in-situ can also be installed in
order to supply oxygen to the bioreclamation process.  Their advantage over
conventional aeration is that higher oxygen solubilities and hence, more
efficient oxygen transfer to the microorganisms can be attained.  Solubilities
of oxygen in various liquids are four to five times higher under  pure oxygen
systems than with conventional aeration.  Therefore, in-line injection of pure
oxygen will provide sufficient dissolved oxygen to degrade 20 to  30 mg/1 of
organic material, assuming 50 percent cell conversion.  The higher oxygen
solubilities may provide some flexibility in the design of cell banks,
especially at greater pressures, since the oxygen may not be used up
immediately, as with aeration.

     Hydrogen peroxide (^02) as an oxygen source has been used successfully
at the cleanup of several spill sites (Brubaker, G.R. FMC Aquifer Remediation
Systems, Princeton, NJ, personal communication, 1985).  Advantages of hydrogen
peroxide include:

     •  Greater oxygen concentrations can be delivered to the subsurface.
        100 mg/1 HO  provides 50 mg/1 0 .

     •  Less equipment is required to oxygenate the subsurface.  Hydrogen
        peroxide can be added in-line along with the nutrient solution.
        Aeration wells are not necessary.

     •  Hydrogen peroxide keeps the well free of heavy biogrowth.  Microbial
        growth and subsequent clogging is sometimes a problem in  air injection
        systems (Yaniga, Smith, and Raymond, 1984).

Hydrogen peroxide is cytotoxic, but research has demonstrated that it can be
added to acclimated cultures at up to 1,000 ppm without toxic effects (Texas
Research Institute, 1982).  The remediation at Granger, Indiana,  involved
adding an initial concentration of 100 ppm, and increasing it to  500 ppm over


                                     9-21

-------
the course of the treatment (API, Washington, DC, personal communication,
1985).

     Hydrogen peroxide decomposes to oxygen and water (H-0    0  + HO).  In
the subsurface, hydrogen peroxide decomposition is catalyzed by chemical and
biological factors.  There has been some concern that decomposition could
occur so rapidly that oxygen would bubble out near the site of injection and
no oxygen would be made available to the distal portions of the treatment
zone.  Research has shown that high concentrations of phosphates (10 mg/1) can
stabilize peroxide for prolonged periods of time in the presence of ferric
chloride, an aggressive catalyst (Texas Research Institute, 1982).  However,
there are problems associated with adding such high phosphate concentrations
to the subsurface, such as precipitation.  One company claims to have
developed specially stabilized hydrogen peroxide products for aquifer
remediation-  However, process performance information on these products is
not available.

     Ozone is used for disinfection and chemical oxidation of organics in
water and wastewater treatment.  In commercially available ozone-from-air
generators, ozone is produced at a concentration of one to two percent in air
(Nezgod, W.  PCI Ozone Corporation, West Caldwell, NJ, personal communication,
1983).  In bioreclamation, this ozone-in-air mixture could be contacted with
pumped leachate using in-line injection and static mixing or using a bubble
contact tank.  A dosage of 1 to 3 mg/1 of ozone can be used to attain chemical
oxidation (Nezgod, W.  PCI Ozone Corporation, West Caldwell, NJ, personal
communication, 1983).  However, German research on ozone pretreatment of
contaminated drinking waters indicates that the maximum ozone dosage should
not be greater than 1 mg/1 of ozone per mg/1 total organic carbon; higher
concentrations may cause deleterious effects to microorganisms (Rice, R.G.
Rip G. Rice, Inc., Ashton, MD, personal communication, 1983).  At many sites,
this may limit the use of ozone as a pretreatment method to oxidize refractory
organics, making them more amenable to biological oxidation.

     A petroleum products spill in Karlsruhle, Germany, was cleaned up in-situ
using ozone as an oxygen source for biological degradation (Nagel et alซ, 1982
in Lee and Ward, 1984).  The groundwater was pumped out, treated with ozone,
and recirculated.  Approximately one gram of ozone per gram of dissolved
organic carbon was added to the groundwater and was allowed a contact time of
four minutes in the aboveground reactor.  This increased the oxygen content to
9 mg/1 with a residual of 0.1 to 0.2 gram of ozone per cubic meter in the
treated water.
               b.  Nutrients
     Nitrogen and phosphate are the nutrients most frequently  present  in
limiting concentrations in soils.  Other nutrients required  for microbial
metabolism include potassium, magnesium, calcium, sulfur,  sodium, manganese,
iron, and trace metals.  Many of these nutrients may already be present in  the
aquifer in sufficient quantities and need not be supplemented.


                                     9-22

-------
     The optimum nutrient mix can be determined by  laboratory  growth  studies
and from geochemical evaluations of the site.  Caution must  be exercised  in
evaluating microbial needs based on soil  and groundwater  chemical  analysis.
Chemical analysis does not necessarily indicate what  is available  to  the
microorganisms.  In some cases generalizations can  be made,  e.g.,  if  calcium
is present at 200 mg/1 (a very high concentration), it is likely that calcium
supplementation is unnecessary.

     The form of nutrients may or may not  be critical in  terms of  microbial
requirements, depending on the site.  Studies have  shown  that  forms of
nitrogen and phosphate were not critical  for microorganisms  (Jamison, Raymond,
and Hudson, 1976).  However, it has been  recommended  than an ammonia-nitrogen
source is preferable to a nitrate-nitrogen source because ammonia-nitrogen is
more easily assimilated by microorganisms  (FMC, 1985).  Nitrate is also a
pollutant limited to 10 mg/1 in drinking water.

     The site geochemistry may be a critical factor in determining the form of
nutrients, as well as the added concentrations.  For  example,  use  of
diammonium phosphate could result in excessive precipitation (Jamison,
Raymond, and Hudson, 1976) and nutrient solution containing  sodium could  cause
dispersion of the clays, thereby reducing  permeability (Anderson,  D.,  K.W.
Brown, and Associates, Inc., College Station, TX, personal communication,
1985).  Where calcium is high, it is likely to lead to the precipitation  of
added phosphate, rendering it unavailable  to microbial metabolism. If a  site
is likely to encounter problems with precipitation, iron  and manganese
addition may not be desirable. If the total dissolved solids content  in the
water is extremely high, it may be desirable to add as little  extra salts  as
possible.

     The compositions of some basal salts media are given in Tables 9-7 and
9-8.  Only phosphate and nitrogen had to be added to  a site  in Ambler, PA.
Bulk quantities of ammonium sulfate [ (NH^^SO, )], disodium phosphate
(Na-HPO,), and monosodium phosphate (NaH.PO.) were mixed  in  a  2,200 gallon
tanE truck and added to the groundwater In the form of a  30  percent concen-
trate in water which was metered into the  injection wells (Raymond, Jamison,
and Hudson, 1976).  Phosphate concentrations in injection wells varied from
200 to 5,800 mg/1 throughout the site cleanup.  Phosphate concentrations
in all wells were determined weekly and injection rates were adjusted
accordingly.

     CDS, Inc. used the basal salt medium  listed in Table 9-8  in the  combined
surface/in-situ treatment system at the Biocraft site (Jhaveri and Mazzacca,
1984).  The nutrient solution used at the  Granger, Indiana,  site was  composed
of ammonium nitrate and disodium phosphate (FMC, 1985).

     An organic carbon source, such as citrate or glucose, could be added  if
the compound of interest is only degraded  cometabolically and  a primary carbon
source is required.  Such additions could  also be made when  low levels of
contaminants are present and are not sufficient to sustain an  active  microbial
population.  Citrate, or another chelate such as EDTA, could be added to hold
metals in solution if water is alkaline, a condition  under which metals may


                                     9-23

-------
                    TABLE 9-7
        COMPOSITION OF BASAL SALTS MEDIUM

Salt Type
KH2P04
Na2HP04
(NH4)N03
MgS04.7H20
Na,CO,
ฃ• J
CaCl2.2H20
MnS04.H20
FeS04.7H20
Concentration (mg/1)
400
600
10
200
100
10
20
5

Source:  Jamison, Raymond, and Hudson, 1976
                    TABLE 9-8
       BASAL SALT MEDIUM USED BY CDS INC.

Salt
NH,C1
4
KH2P04
K2HP04
MgS04
Na2C03
CaCl2
MnSO,
4
FeSOA
4
Concentration (mg/1)
500

270
410
1.4
9
0.9
1.8

0.45


Groundwater Decontamination Systems, Inc., 1983
                      9-24

-------
precipitate.  Citrate, however, will be preferentially degraded relative to
other organics, and could slow the degradation of contaminants.  Addition
of low concentrations of a source of araino acids, such as peptone or yeast
extract, could promote biodegradation.  However, high concentrations of these
compounds could inhibit degradation of contaminants because of preferential
degradation.
               c.  Design of Delivery and Recovery Systems
     One of the major factors determining success of an in-situ treatment
system is to ensure that the injection and recovery systems are designed to
accomplish the following:

     •  Provide adequate contact between treatment agents and contaminated
        soil or groundwater

     •  Provide hydrologic control of treatment agents and contaminants to
        prevent their migration beyond the treatment area

     •  Provide for complete recovery of spent treatment solutions and/or
        contaminants where necessary.

     A number of design alternatives are available for delivering nutrients
and oxygen to the subsurface and for collecting and containing the ground-
water.  These methods can generally be categorized as gravity flow or forced
methods.  Most of the systems that have been used for bioreclamation have
involved the use of subsurface drains (gravity system), injection wells and
extraction wells.  Subsurface drains and extraction wells are described in
detail in Sections 5.2 and 5.1, respectively.  Some examples of delivery and
recovery systems are described below.

     Figure 9-4 illustrates a hypothetical configuration in which groundwater
is extracted downgradient of the zone of contamination and reinjected
upgradient.  In-situ aeration supplies oxygen directly to the contaminated
plume while nutrients and oxygen are added in-line by way of mixing tanks.
Treated water is infiltrated through contaminated soil in order to flush
contaminants from the soil.  Extraction and injection wells can be used to
treat contaminants to almost any depth in both the saturated and unsaturated
zone.  However their use becomes cost-prohibitive in very low permeability
soils because of the need to space the wells very close together to ensure
complete delivery or recovery.  Subsurface drains can be used under conditions
of moderately low permeability although delivery and recovery of chemicals
will be slow.  They are generally limited to depths of 40 feet or less because
of the cost associated with excavation (shoring, dewatering, hard rock
excavation) of the trench.  Surface gravity delivery systems (e.g., spray
irrigation, flooding, ditches) which involve application of treatment
solutions directly to the surface, as illustrated by "surface flushing" in
Figure 9-4, are most effective for treating shallow contaminated zones located
                                     9-25

-------
                               FIGURE 9-4
    SIMPLIFIED VIEW OF GROUNDWATER  BIORECLAMATION
                                   Subsurface Aeration Wells
Inaction Well
                                                           Extraction Well
                                                    Direction of Flow
       Simplified View of
       Bioreclamation of
       Soil and Groundwater
               Aeration Zone

Direction of Groundwater Flow
                                                                     Extraction Well
                                    9-26

-------
in  the unsaturated  zone.   They  can  also  be  used  to  treat  contaminants in the
saturated zone, provided  the  following conditions are  met:

     •  The soil above  the saturated  zone  (through  which  treatment  solutions
        percolate)  is sufficiently  permeable  to  allow  percolation of  treatment
        solutions to the  groundwater  within a reasonable  length of  time

     •  Groundwater flow  rates  must be sufficient to ensure  complete  mixing of
        the treatment solutions with  the groundwater.

     The feasibility and  effectiveness of these  methods is affected by
topography and climate.

     Figure 9-5 shows the design of a groundwater injection/recovery  system
which is currently  being  used for bioreclamation at an Air Force site.
(SAIC/JRB, 1985).   The  system,  which  is  designed to operate  in moderately low
permeability soils, consists  of nine  pumping  wells  and four  injection wells.
Groundwater is pumped at  an even rate from  the pumping wells to a central flow
equalization (surge tank).  Flow is metered from this  tank into a length of
pipe into which measured  amounts of nutrients and hydrogen peroxide are added.
The treated water then  flows  to a distribution box  to  be  distributed  at an
even rate to each of the  four injection  wells.   Overflow  from the equalization
tank will flow into an  on-site  storage tank.

     The injection/recovery system was designed  using  a two-dimensional,
geohydrologic non-steady  flow model which simulated the flow of groundwater at
the site in response to an injection/recovery pumping  system.

     Important criteria used  for the  design of the  injection/recovery system
include the following:

     •  The groundwater injection rate will be the  same as the rate determined
        during the  field  testing program

     •  All injected groundwater and  associated  elements  are to be  kept within
        the site boundary to  prevent  the transport  of  contaminants  to adjacent
        areas (this implies that there may  be some  net groundwater  pumpage at
        the site)

     •  The distance between  the injection-pumping wells  should be  such that
        approximately six injection-pumping cycles can be completed within a
        6-month period.

     Figure 9-6 illustrates an  injection trench  used in the  treatment of  the
Biocraft site (Jhaveri and Mazzacca,  1983).   The trench was  10 feet deep  by
4 feet wide by 100 feet long.   The trench had a  15 mil plastic liner  installed
on the bottom, back, ends, and  top such  that  reinjected water  only  flowed out
of the front (downgradient) face of the  trench.  About 40 feet of slotted
steel pipe was installed  horizontally in the  trench to carry reinjected water
into the trench system.   As water flowed into the injection  trench, the water
was forced to exit only from  the front face.  Backflow is minimized by this
                                     9-27

-------
FIGURE 9-5. PLAN VIEW OF EXTRACTION/INJECTION SYSTEM
               USED AT AIM AIR FORCE SITE
                                             KEY:
                                                Pumping Wells

                                            j)  Injection Wells
                                            	'   Untreated Groundwater Lines

                                             — ~   Treated Groundwater Lines
                            9-28

-------
(0
UJ

o

UJ
cc
UJ
cc
u.
O
2
O

ง
DC
3
O
EZ
2
O
U
ui
OC
3
O
1
(0

I
                                                                                                  o
                                                                                                 C/3
                                                                                                  1
                                                         9-29

-------
design feature.  Barriers can also be used behind the trench and extended  to  a
point where backflow is further minimized.  In extreme cases, total control
over backflow and plume containment can be obtained by installing a
circumferential wall barrier.

     Optimum extraction and injection flow rates will many times be pre-
determined by aquifer yield limits or hydraulic design for plume containment.
The factors affecting aquifer flow rates are described in Section 5.1.

     Aquifer flow rates should be sufficiently high so that the aquifer is
flushed several times over the period of operation.  Thus, if the cleanup
occurs over a three year period, flow rates between injection and extraction
wells should be such that a residence time of one-half year dr less occurs
between the well pairs.  This corresponds to six or more flushes.  Several
recycles would cause flushing of soils containing organics, preventing the
clogging caused by microorganism buildup because of increased flow rate; more
even distribution of nutrients and organic concentration within the plume; and
better and more controlled degradation.  Flow rates and recycle should not be
high enough to cause excessive pumping costs, loss of hydraulic containment
efficiency because of turbulent conditions, corrosion, excessive manganese
deposition, flooding, or well blow out.  The operating period will depend  on
the biodegradation rate of the contaminants in the plume and the amount of
recycle.  If the period of operation is excessively long, for example more
than five years, the operating costs of bioreclamation may outweigh the
capital costs of another remedial alternative.


          9.1.3.2  Anaerobic Bioreclamation
     Anaerobic treatment is generally not as promising for site remediation  as
aerobic treatment.  Anaerobic processes are slower, fewer compounds can  be
degraded, and the logistics of rendering a site anaerobic have not been
developed to date.

     Anaerobic metabolism includes:  (1) anaerobic respiration, in which
nitrate or sulfate may be used by nitrate or sulfate reducers as a terminal
electron acceptor, and (2) interactive fermentative/methanogenic processes,
which are carried out by what is referred to as a methanogenic consortium.

     If it were possible to provide proper reducing conditions, degradation  by
methanogenic processes would be promising.  A considerable body of research
indicates that methanogenic consortiums are active in the subsurface  and are
capable of degrading certain organics (Ehrlich et al., 1982; Parsons  et  al.,
1982; and Suflita and Gibson, 1984).  Most notably, methanogenic consortiums
are able to degrade TCE, PCE, and other lower molecular weight halogenated
organics which generally cannot be degraded by aerobic or other respiratory
processes. Reductive dehalogenation appears to be the primary mechanism
involved in degradation.  Methanogenic consortiums are also able to degrade
various aromatics, halogenated aromatics, and some pesticides.  Degradation  of
                                      9-30

-------
petroleum hydrocarbons, straight-chain and branched alkanes  and  alkenes,  is
not possible under methanogenic conditions.

     Methanogenic_activity requires a very low  redox  potential,  -250  mv  or
less.  No 0ซ, NO. , or SO,   can be present or  the redox potential will  not  be
low enough.  Currently, there are no demonstrated methods  for  rendering  a site
anaerobic.  When the contamination is shallow,  there  is an aquitard below the
zone of contamination, and the flow of groundwater can be  contained,  it  might
be possible to induce reducing conditions by  flooding the  site,  as one would a
rice paddy.  Another possible method or rendering the site anaerobic  would be
to add excessive amounts of easily biodegradable organics  so that the oxygen
would be depleted.  One other promising possibility might  be to  circulate
groundwater to the surface through anaerobic  digesters or  anaerobic lagoons.
These methods may require long retention times  because of  slow degradation
rates under anaerobic conditions.  There have been no reports  of pilot or
field studies using anaerobic degradation under methanogenic conditions.

     Nitrate respiration may be a feasible approach to decontaminating an
aquifer.  Denitrification (the reduction of NO  to NH or  N  )  has been
demonstrated to occur in contaminated aquifers.  Nitrate respiration  was  used
successfully in the treatment of an aquifer contaminated with  aromatic and
aliphatic hydrocarbons (see Table 9-4) (Stief,  1984).  Nitrate can be added
in-line along with other nutrients and intimate mixing with  groundwater  can
occur.  The cost is moderate; all that is required is the  nutrient feed  system
and an in-line mixer.

     Nitrate, however, is a pollutant, limited  to 10  ppm in  drinking  water.
Consequently, it may be more difficult to obtain permits for use of nitrate  at
a site than for oxygen or hydrogen peroxide.  Additionally,  degradation  rates
under aerobic conditions are more rapid and a broader range  of compounds  can
be degraded.  There is no reason why nitrate  respiration would be a better
treatment approach given the amount of success  that has been demonstrated with
aerobic treatment approaches to date.


     9.1.4  Operation and Maintenance


     Operation and maintenance of a bioreclamation process involve aspects of
the hydraulic system as well as the biological  system.  The  hydraulic aspects
relate to pumps, extraction and injection wells, and  injection trenches;  these
are discussed in Sections 5.1 and 5.2.

     Monitoring a number of parameters is necessary to determine process
performance.  Monitoring of groundwater can be  performed at  the  injection and
extraction wells, as well as at monitoring wells.  Monitoring  wells should be
placed on-site to monitor process performance and off-site to  monitor for
pollutant migration as well as to provide background  information on changes  in
subsurface conditions due to seasonal fluctuation.  Table  9-9  lists parameters
which should be monitored, and suggests methods which can  be used to  monitor
these parameters.


                                     9-31

-------
                                  TABLE 9-9.
                       RECOMMENDED PARAMETERS TO MONITOR
Parameter
Location     Media
of Analysis
                    Analytical Method
Total Organic
Carbon (TOC)

Priority pollutant
analysis or analysis
of specific organics

Microbiology-
cell enumerations
laboratory   groundwater
laboratory
laboratory
                      field
Temperature
conductivity
dissolved oxygen (DO)
PH
Alkalinity
Acidity, M&P
Chloride
Hardness (total
NH--N
NO^-N
PO,, all forms
SOT
TDS (total dissolved
     solids)

Heavy metals
(if present)
field
soil and
groundwater
soil and
groundwater
             groundwater
groundwater
field
groundwater
field
laboratory
groundwater
soil and
groundwater
                    TOC analyzer
Direct counts.  Plate
counts on groundwater
media or enriched
media.

Plate counts with
portable water test
kits (e.g. Soil Test
Inc., Evanston, IL).

In-situ water quality
monitoring instrument
or prepackaged
chemicals, field test
kits.

Prepackaged chemicals/
field test kits; water
analyzer photometer
(Soil Test. Inc.,
Evanston, IL; Lamotte
Chemical, Chestertown,
MD).
Prepackaged chemicals/
test kits;
                                                       GC/MS; AAS.
                                                                  (2)
                                                                   (continued)
                                     9-32

-------
                            TABLE 9-9.   (continued)
Parameter             Location     Media               Analytical Method
                      of Analysis
Hydrogen peroxide     field        groundwater         Prepackaged chemicals
    2)                                                 for ^2ฐ2' test  striPs
                                                       available.  Titanium
                                                       sulfate titration  and
                                                       spectrophotometer
                                                       analysis for H^C^  for
                                                       greater accuracy.


   GC/MS = gas chromatography/mess spectrometry
(2)
v 'AAS = Atomic absorption spectrometry
     In a biological system, pH should be maintained in a range between 6 and
8 and concentrations of both nutrients and organics should be kept as uniform
as possible to protect against shock loading.  Dissolved oxygen should be
maintained above the critical concentration for the promotion of aerobic
activity, which ranges from 0.2 to 2.0 mg/1, with the most common being
0.5 mg/1 (Hammer, 1975).

     Clogging of the aquifer, injection wells or trenches, or extraction wells
by microbiological sludge is a possibility.  CDS Inc. installed two wells in
each of their injection trenches in case flushing was ever required to remove
sludge.  After 1-1/2 years of operation, clogging had not occurred (Ground-
water Decontamination Systems Inc., 1983).  However, problems with biofouling
and plugging of sparging points was encountered during a spill cleanup con-
ducted by Groundwater Technology (Yaniga, Smith, and Raymond, 1984).  This
interfered with oxygen transfer and necessitated frequent mechanical cleaning.
When hydrogen peroxide was substituted for air sparging in order to deliver
increased quantities of oxygen to the aquifer, one added benefit was that the
hydrogen peroxide kept the wells free of heavy biogrowth.

     The permeability of the aquifer could be reduced due to precipitation, as
discussed in Section 9.2.2.  Other factors, such as dispersion of clays, could
reduce aquifer permeability.  When calcium concentrations are high in the
soil, phosphates can be rapidly attenuated due to precipitation with calcium,
becoming unavailable for microbial metabolism.  Nutrient formulations should
be devised with the help of experienced geochemists which will minimize
problems with precipitation and dispersion of clays.  One company claims to
                                     9-33

-------
have developed special soil preconditioners and nutrient formulations which
reduce these problems and maximize nutrient mobility and solubility; however,
no process performance data are available on these products.

     Maintenance of the bacterial population at their optimal levels is also
important, especially for selective mutant organisms which tend to be more
sensitive than naturally occurring species.  A continuous incubation facility
operating at higher temperatures and under more controlled conditions could be
used to maintain the microbial population.  The high biomass-containing stream
formed from such a facility could then be reinjected via wells or trenches so
as to reinoculate the subsurface continuously with microorganisms.

     Aeration wells may be particularly susceptible to operational problems.
If injected gas fluidizes the material around it, soil substrata shifts can
occur which may cause a well blowout (free passage of air to the surface).
The cone of influence in a blown out well will be greatly reduced, therefore
requiring the installation of a new well.  The best method to prevent blowouts
is to keep gas velocities below those necessary to cause fluidization, or to
place wells deep enough so that overburden pressure prevents excessive fluidi-
zation, or both (Sullivan, Chemineer Kinecs, Dayton, OH, personal communica-
tion, 1983).  Suntech stated that a number of aeration wells became inopera-
tive because of blowout during their groundwater cleanup in 1972 and had to be
replaced (Raymond, Jamison, and Hudson, 1976).  This suggests that aeration
well blowout could become a commonly encountered problem if attention is not
paid to the design criteria.


     9.1.5  Technology Selection/Evaluation


     Aerobic bioreclamation has been demonstrated to be effective in degrading
organics at more than 30 spill sites.  Although it has not yet been demon-
strated at hazardous waste sites, it can be expected to be effective and
reliable provided the organics are amenable to aerobic degradation and the
hydraulic conductivity of the aquifer is sufficiently high.  There are sub-
stantial research data to suggest that microorganisms found at uncontrolled
hazardous waste sites are well-acclimated to the wastes.  Effectiveness and
reliability could be adversely affected by factors, such as precipitation,
which could reduce the permeability of an aquifer.

     Relative to conventional pump and treat methods, bioreclamation may be
more effective since it is capable of degrading organics sorbed to soils.
Sorbed organics are not removed using conventional pump and treat methods.

     The nature of the delivery systems can effect the reliability of the
bioreclamation approach.  Pumping systems are prone to mechanical and
electrical failure.  However, repairs can be made relatively quickly.
Subsurface drains are less prone to failure since there are no electrical
components.  Where mechanical failures do occur, repairs can be both costly
and time consuming.
                                     9-34

-------
     Implementation of a remedial action involving bioreclamation will  take
longer than excavation and removal of contaminated soils.  Depending upon  the
site, it could also take longer than a conventional pump and  treat  approach.
The advantage of in-situ bioreclamation over a pump and treat  approach  is  that
in-situ biodegradation treats contaminated subsurface soils,  thereby removing
the source of groundwater contamination.

     The increased time required for in-situ bioreclamation is  dependent
primarily upon the degradation rates, which are in turn dependent upon  oxygen
availability.  The form in which oxygen is delivered to the subsurface  and the
aquifer permeability are the critical factors in this respect.  As  discussed
previously, far more oxygen can be delivered to the subsurface  in the form of
hydrogen peroxide•

     Other aspects of implementation are similar to implementation  of conven-
tional pumping or subsurface drain systems with a few exceptions.   Depending
upon the hydraulic conductivity, drains or wells must generally be  spaced
closer together to ensure nutrient and oxygen availability at all portions of
the zone being treated.  The lower the flow rate of the nutrient/oxygen-
enriched water and the more rapidly nutrients and oxygen are  attenuated, the
closer the injection wells or drains must be spaced.  Well/drain spacing will
also be dictated by the need, if any, to contain the contaminated plume or
treatment solution.

     There are few additional safety hazards associated with  in-situ
bioreclamation aside from those hazards normally associated with being  on  a
hazardous waste site or a drill site.  Since wastes are treated in  the  ground,
the danger of exposure to contaminants is minimal during a bioreclamation
operation relative to excavation and removal.

     A nutrient/oxygen or nutrient/hydrogen peroxide solution does  not
represent an environmental threat.  Most of the nutrients will  be utilized and
attenuated by microbial activity.  If the form of the nutrient  is carefully
selected (e.g. ammonia-nitrogen rather than nitrate-nitrogen),  the  remaining
nutrients will not present an environmental threat.  The hydrogen peroxide
will rapidly decompose in the subsurface to oxygen and water.

     The only treatment reagent which could pose a hazard, if used,  is  the
concentrated hydrogen peroxide solution prior to mixing with groundwater.
Worker protection for operations involving hydrogen peroxide outside of a
closed container or pipe should include the use of chemically resistant
gloves, an apron, and a face shield.  Safety training in the use of  hydrogen
peroxide should be provided by qualified personnel.


     9.1.6  Costs
     Costs for biological in-situ treatment are determined by the nature of
the site geology and geohydrology, the extent of contamination, the kinds
and concentrations of contaminants, and the amount of groundwater and soil


                                     9-35

-------
requiring treatment.  There is no easy formula for predicting costs.  Costs
provided for actual site cleanups indicate that biological treatment can be
far more economical as an alternative to, or in conjunction with, excavation
and removal or conventional pump and treat methods.

     In-situ treatment costs include costs for well construction and pumping.
These are provided in Sections 5.1 and 5.2.  Unit costs for chemicals,
nutrients, and hydrogen peroxide are provided in Table 9-10.  Cost data for an
actual and hypothetical site cleanups involving in-situ treatment are
presented below.

     Total capital and research and development costs for cleanup of the
Biocraft site (Table 9-11) were $926,158 including $446,280 which were spent
on process development (R&D).  Project costs also included the hydrogeological
study, and design and operation of the groundwater injection and collection
system, and biostimulation plant.  Total operating costs, based on treating
13,680 gallons/ day, were approximately $226/day, or $0.0165/gal.  The total
cost including amortization based on projected costs is $0.0358/gal over a
three year period. Prior to the biological treatment program, contaminated
water had been removed at a rate of 10,000 gal/month.  The average disposal
cost had been $0.35/gal (Jhaveri and Mazzacca, 1984).  The cost of biological
treatment of an equal number of gallons is an order of magnitude less than
that for disposal.  The Biocraft site employed surface biological reactors as
well as enhancing in-situ treatment by reinfiltrating oxygen and nutrient
treated groundwater.  Costs for in-situ treatment alone would have been less
because process plant design and equipment would not be included in an in-situ
approach.  (See Table 9-11).

     Table 9-12 presents the estimated site cleanup costs for hypothetical
sites involving the use of hydrogen peroxide as an oxygen source for the
enhancement of in-situ biodegradation (FMC, 1985).  The cleanup of 300 gallons
of gasoline from a sand gravel aquifer over a period of 6 to 9 months is
between $70,000 and $120,000 (Site A).  Cleanup of 3,000 gallons of diesel
fuel from a fractured bedrock formation is estimated to require 9 to 12 months
and $160,000 to $250,000.  The cost estimate for degrading 10,000 gallons of
jet fuel from a fine gravel formation is estimated to cost $400,000 to
$600,000 and take 14 to 18 months.
9.2  Chemical Treatment
     9.2.1  General Description
     Generally, organic and inorganic contaminants can be immobilized,
mobilized for extraction, or detoxified.  Technologies placed in the category
"immobilization" include precipitation, chelation, and polymerization.  The
category encompassing methods for mobilizing contaminants for extraction  is
termed "soil flushing."  Flushing agents include surfactants, dilute acids and
                                     9-36

-------
                                  TABLE 9-10.
                                CHEMICAL COSTS
Category
Chemical
Cost/Unit
Acids
Hydrochloric acid, 20ฐ Baume tanks
Nitric acid 36ฐto 42ฐ Baume tanks
Sulfuric acid
  virgin, 100%
  smelter, 100%
$55-105/ton
$195/ton

$61-95.9/ton
$48-65/ton
Bases

Chelating agents


Fertilizers
(Microbial nutrients)
Caustic soda, liquid 50%, low iron  $255-285/ton
Liming material



Oxidizing agents


Reducing agents

Precipitating agents
Ammonium chloride
Citric acid

Ammonia, anhydrous, fertilizer
Ammonium chloride
Ammonium sulfate
Sodium monophosphate
Sodium diphosphate
Phosphoric acid
  75%, commercial grade
  52-54% a.p.a., agricultural
    grade
Potassium muriate, 60 to 62%,
  minimum
Potassium chloride
Potassium-magnesium sulfate

Agricultural limestone (dolomite)
Lime
Hydrated lime

Hydrogen peroxide, 35%
Potassium permanganate
$18/100lbs
$0.81-$1.19/lb

$140-$215/ton
$18/100 Ibs
$73-79/ton
$55.75/100 Ibs
$54.50/100 Ibs

$27.5/100 Ibs

$3.10/unit-tona

$0.82-0.92/unit-ton
$105/ton
$59/ton

3.50-34/tonb
$30.75-45/ton
$32.5-34.5/ton

$0.24/lb
$1.03-1.06/lb
Caustic soda, liquid 50%, low iron  $255-285/ton
Ferrous sulfate
  heptahydrate
  monohydrate
                                                           130/ton
                                                           160/ton
                                                                   (continued)
                                     9-37

-------
                            TABLE 9-10. (continued)
Category               Chemical                            Cost/Unit
Surfactant                                                             c
  Anionic              Witconate 605A                      0.65-0.85/lbc
                       Witconate P-1020BV                  0.70-0.88/lb
                       (calcium sulfonates)                           c
  Nonionic             Adsee 799                           0.75-0.87/b
Source:  Schnell, 1985, unless otherwise noted.

a.  unit-ton:  1 percent of 2,000 pounds of the basic constituent or other
    standard of the material.  The percentage figure of the basic constituent
    multiplied by the unit-ton price gives the price of 2,000 pounds of the
    material.
b.  Source:  USEPA, 1984a.
c.  Source:  Witco Chemical Corp., Houston, TX, personal communication, 1985:
    cost varies depending on quantity purchased (drum, truckload, or bulk).


bases, and water.  Detoxification techniques include oxidation, reduction,
neutralization, and hydrolysis.

     These categories do not define the limits of each technology.  For
example, a treatment method that immobilizes a contaminant may also serve to
detoxify it; a flushing solution that mobilizes one contaminant may
precipitate, detoxify, or increase the toxicity of another.

     Tables 9-13 and 9-14 provide a summary of those in-situ chemical
treatment methods for organics and inorganics, respectively, that are most
promising or have been most widely discussed in the literature.  The compounds
amenable to treatment, the treatment reagents, and the process are summarized.


     9.2.2  Applications/Limitations
     The feasibility of an in-situ treatment approach  is dictated  by  site
geology and hydrology, soil characteristics, and waste characteristics.  Since
the application of many chemical in-situ treatment techniques  to hazardous
waste disposal site reclamation is conceptual or in the developmental stage,
there is little hard data available on the specific site characteristics
that may limit the applicability of each method.  A list of  site and  soil
                                      9-38

-------
   o

   I

   I
   CO
   UJ
   oc

   i
   oc
   o
   m
is-
  CO
  o
  o
  LU
  oc
  Q.

  u.

  O


  DC
  D

  CO
Ctf
E
"3 h.
C C
— • u.
k. k


44
0*.
~
U
M
_C
•^

O
IM
3
—
•o
c
&
a
X
u

(C
4J
Ci
<.

























.^
m
a
H







CO —
r- eO
O c*
1 |
Mt> CC
r*. r*.
ON O^





1 1
1 t










C
CC CC
•C- CM
vC
r-i <•
r*. <•
w •








c
c

4J

C ^
= s
U ฃ
•o C
E
o u
** e
i 1
h &
C. 0
1 *•*
x a>
73 >
3 0
ฃ ฐ
a
^-< T
U U
— c
CC ^
c a.
ป•*
c w
i 0!
ec 3
c c
u .c
"O 1
X C
z N*
< ae

CO
ff*
)
0
30
o**





1
1








J~+
>-* r>
n c u"i
>T ^ r*
CM *ป •
-3- ^ CM
GO ^0 —
•— v> w
ซ> x^- s^




rH
Q
4J
O
01
u
cn
x
K
e
c

u
01
••"1
c
•H
•*^
C
o
^H
u
U
o> e
^ c
I—I ^B
O *>
u c ~
Q 00 C

CJ 31 X
s ^ฃ
*D
C x-^ — ^
3 -H CM
C
U
o
u


X
a*






i










r^.
CM
CM
CM


i-*
t
o


c

tj
u
k-

V.
c
c
u

•g
a
c
c;
ซ
G
a

u
C
c
C.
ฃ
C
iJ


i
w
K
O
•^4
ae
Q


oc x> oc
o> ป a>






I ill
I in










ง!/•* (M
f- f~
-j or cc
oc m oe
*n r^ OC
 w





c
c

r:
r:

cr
c
t—
ซ
s
c
u
c
ซ
c —
ft
C *J y
ec o ซ
*- 3 •—
cn w. ฃ
O -^
a 5"S
M C C
C U
ง n
ซ - -^
ea ? 3
5 i w
^^ ^^ ^^
-. CM n













1
1










00
>rt

vO
ซM
Cf^

















_J
2
ฃ

o
•4
•ae

z
<
-ป
1-
^









w
41
w
 Oป
^^ ^^ ^^


in
•a ^
j; c
a = o
j< 0 rj
•^ c. -e
•ซ -~ o)
O> -*l H
":ซ .
-ฐ :




^•v
ซ. >> X
S" " n >>
JS rs ^ป -H ซ
^ -C >1^ —
-. N g-?; <
0 ซ -a eป> o
*T ! — - • ^
. >ff -*l eป •
r^ ™ oo *r\ ^
^ ^^ ^ r* *~
ซ• •— s^ vt <"•

M
^.
X >•
r ซ5
•0 "3
^^
3) <^
W 50
3 -*
3 S
ป r"1

5 ซ ซ
•~. 4 ~ **
a c x .,
J< 3 f "
^v n *J ^"
z ^ a. -2
•ซ ei ."
O vo CM o r-
*-* CM r*. ซ
V
41 i
0 ซ
c
T X ซ
C u ซ
91 •— "2
w u 01 '
c .; u ซ
•p 7, i; . g ซ
r — one =
u o u f a
H0 1 ' U ~~* "*
— t U Ul = "•
s — — *•
^ 5 -Ci ฃ
AJ vH
It x-\ "* "•*
w- -• rg 
C -^
•

fH
(B
w
O
u
ac
>ซ
o
X
(^
•D
>ซป
^4

ON
rซ*
r-.
ซ
i— i
u-ป


m
c
o
^^

rj
00

O
GO
*>
*n

i

T3
0)
q
o
4J
o
u
5
.
rj
AJ
Q
H

                                              9-39

-------
                                  TABLE 9-12.
               ESTIMATED COSTS FOR HYPOTHETICAL BIORECLAMATIONS
                  USING HYDROGEN PEROXIDE AS AN OXYGEN SOURCE
                   Site A
Site B
Site C
Contaminant
Formation
Flow Rate
Project Time
Estimated Costs
300 gallons
gasoline
Sand/gravel
50 gpm
6-9 months
$70-120M(1)
2,000 gallons
diesel fuel
Fractured bed rock
10 gpm
18-24 months
$200-300M(1)
10,000 gallons
jet fuel
Coarse gravel
100 gpm
18-24 months
$500-700M(1^

(1)M=1000
Source: FMC, 1985






characteristics considered important in evaluating the treatment  applicability
is provided in Table 9-15 (Sims and Wagner, 1983).

     Most of the treatment approaches discussed in this section involve  the
delivery of a fluid to the subsurface.  Therefore, the same factors that  limit
the use of injection/extraction wells, drains, or surface gravity application
systems such as flooding and spray irrigation for bioreclamation  will  limit
the applicability of most in-situ chemical treatment approaches.   Minimal
permeability requirements must be met if the treatment solution is to  be
delivered successfully to the contaminated zone.  Sandy soils  are far  more
amenable to in-situ treatment than clayey soils.  Further, the contaminated
groundwater must be contained within the treatment zone.  Measures must  be
taken to ensure that treatment reagents do not migrate and, of themselves,
become contaminants.  Care must be taken during the extraction process not to
increase the burden of contaminated water by drawing uncontaminated water  into
the treatment zone from the aquifer or from hydraulically connected surface
waters.

     Potential chemical reactions of the treatment reagents with  the  soils and
wastes must be considered.  Most hazardous waste  disposal sites contain  a mix
of contaminants.  A treatment approach that may neutralize one contaminant may
render another more toxic or mobile; for example, chemical oxidation  will
                                      9-40

-------























tr
U
z
0
pe*
O

a;
O
u.

C/3
C
c
a:
E-
U
r

E*"1
fe
b^
y
C
<:
U
ex:
f-
M
s
E
O


H
i-< 1
C/i I

Z
t— i

U.
o
b
1
D
t/3




































CO
en
OJ

0
o.

1





en

e
OJ
or
to
OJ


4j
c
Ol
E
I ฃ
CO
OJ

ฃ




1
1



4J
c
OJ
E
4-1
CO
OJ
H
O
•"
OJ
JO
CO
C
OJ
1









-o
o


OJ
1 3ฃ

CO
OJ OJ
l-i Ut p T?
co o 3 o;
4-t 4->
en P x ^J tj
— OJ •<•* QJ QJ
• *H 4-1 E *-* •"•*
O CO tC t— <
y5 3 t •— • "•< o
to i- u
fl f* f 1 .i-l
Oj 4J *H 3 en
4-1 '"* ฃ 1— • ••*
CO 3 OJ QJ
e j= c
•H TJ 0 OJ O
g OJ .C • —
4J O tU 3
C O 4j "O -<
o •— i to c o
C.5 U-* 3 *^ tn

v




















u
OJ

CO
3



X
Of

j=
s-x

en
T) >-^
e 3
3 0
at*

E 3
O o
O r->
(J .
— ^
>H -F4
td
o jo
h 3
TJ i—1
3: en
ac
e
00 -C
C en
•H 3
j: —
tn M-<
3
— P
[x. OJ
4J

~ *
O
C/l 1





























u-ซ
o

en
C
o

u
3
f—i
O
ซ

en
3
O
OJ
3
cr
•<:




3
O
ป™*
\^f

en
T5
C
3


c
o
u
JD
a
o
u
TJ
3=



r*
AJ
.^
3

P
OJ

CO


1
- u
e x o
0 4J
.^ ซ^ c
4-J — . O
3 •-< •-
ซ— ' jD en
O 3 •— '
Oj en — 3
u o E

u
en C u-i u-<
i^ ซ|H Q O
C
CO T3 C C •
C OJ O O C
•- • N tn •- O
e .^ eo ^ —
c 'ja E re
o o x o oj
o e js u-i u

w














en
xj
C
CO
Jj
o
CO
U-ซ
^,
3
tn









^v
3
O


•ฃ•
00

^
X
—
.-H
3
^u
o
en


en
4J
d
CO

U
cd

u
3
en








U-i
C

OJ
J_l
CO

u>

c
0
.—
u
•2
o
c

-





ซk
01

• 1^
l-<
o

f~
o
c
a
>v
jr

•>
OJ
e
o
N
c







TJ
OJ

3

.*H
4-t
in
J2
3
tc
^
CO
g
1)
N
C
ฃ






c
o

u
CO
."2

kJ
<5


TJ
11 •
en tn
CO C
O! O
lu Ui
U 4-1
C 0
•P4 O1
^^
en cu
.,H
U-I
tn O
TJ
C en
3 en
ฃ^
E

0 JO







OJ
TJ

^
O
ki
tu
a

e
01
60
O

TJ

x:

^j
o











en
^^
O
c
OJ
a
TJ
en OJ
OJ 4-1
C CO
01 0) C
N — OJ
C O 60
01 C O
jS 0) —
ฃฃ
















en
._ 03
•c
X C
ฑ*t 3
•- o



re o o
^
en t-i

C TJ
CB 01 TJ

._ ซj tn
B •** CO
C 4J U
O 41 C
O TJ '^

9






























TJ
C
CO

c
OJ
00
o
Ij
) 1
en •-
o d
4-1 U
CO •-<
i t
U X
CO O
o
O 1-
u en OJ
4J SC 4J
Z^S

















QJ
,_4
X3
CC
c
1?



(U

Q
E

QJ
*O
PC
OJ
u<
CO







































en
*o
c
3
51
ง
u
OJ
00
X
X
o



























r-l
CO
tj
ซซ"ซ
00

1— 1
o
*
o





































tn
01
c
o
4_)
QJ

TJ
C
to
tn
0)
TJ
X
ฃ.
OJ
TJ




























>
c
O
.^
4-1
re
TJ
2
0)






































to
OJ
TJ
• ซH
^4
^_,
3
tn
TJ
•s
en
41
TJ
U-l
^
5















                              3
                              C

                              'Z  i

                              ง  i
                                 I I
                                 I I
                                 I I
9-41

-------

































<*-s
•o
41
3
C
•H
C
o
u
N^X
(*<
<-H
1


Id
-1

*3
H














t





































I

tn
in
u
u
o
ll


tn
LJ
C

Of
re
01


ฑj
c
n
E
re
u
t-i











c
u
E

re
ID
u
g_i

O
4J

O>

r>
re
e
-l '
>•* Q)
41 o — < tn c:

•p- TS a j: ai
jr >, o a sc .c
a x vi c -c w
O u U — t C
i> ij o o *-> re u-i
-1 o 01 -1 o •
0 — C 3 0! O-
3lj4JOtnoo*-'3
CO) ฃ> 41 ซ C O
•u c ^ ^ > 1) t-1
n-* re re re re E oc
OS U -— 11 41
C ซ — ' U OC
j^ -o ซ3urec
u . .0 ^- •->
re bc^-~ ec I- TS a >
u • c • o c tn re
< ^ .2 2, "a J '-a -




u
O

01
E
.ซ
,_ซ

X
u
>H4
9

u sc
" 0
re re
3 Z




n
tn c
T3 O
e .-.
3 X
S. re
o re
u E ^
tn c H
tn 41 - o
3 -a e a
0 •ซ 0
u. o .-i .
O •ซ x tn
jr *j j_i u
D. in re 4)
tn to •-< V BC !•< • ts
tn P re P 01 >-^
w < o o o ^


T)
41
N
^
in re
•-4 4J
i to re
>, 0
•-^ i
O 0)
u in
•c re
^•\ ปo
ac -_
•c
c
I ^

งre • "^^
U UJ C
0 .-. -H
g 01 >^— '
re cv tn u '•*
& j_t ซ^- O
U~4 y ••* ^^ tfi
O —

C 41 O O "*
O OC E
• -i Wi 0) -O
tซ tu ^ tn c
L, ^ a. 01 3
0) •- 0 O
> tO 4J 3O.
C —i T3 E
O 0 3 DO
O iJ E ai u

, ,

e
o

^j
re
^
• ^
^j
U
ID

,j
in
^
re

re
o









•o
c
re in
U 4)
ง4J
T3 U
re e • - .-

0 E 0 Z

re *^ ฃ 4) *-H
41 U C C
. jj 01 O
u re ~^ ui ^^
.-i e >^ a. x
u 1) C O >-
re oc--* tn o
j: >, > .-i re

• rt O 1 1 I




c
0
'^
re
N
• •4
U
41
1,
,__ซ
O
0.



1
1

1



1








1











1
1
1










1 1
1
1
1

1 i
t

1

i
1








f


1


i
1
1

1



1
1
1



1



9-42

-------



W
O
H
5
CJ3
y
P-I
i
u^
Pi
o
fn

en
p
o
3d
H
a
4
ATMENT t
-i W
i Pd
0> H
M to
J H
CO M
< W
H 1
>Z
M
b
O

s



c/:













to
to

3C
01
•— 1 r-t
.n 01 to
3 .C 4J
^ 4J CD
0 01 E
CO 4J OO
c to c 01
•rt 4J .H JC
— 0 4J
U-l O. 3
O ••< T3 Uj
U O> O
C 0) Ll
O Ll ^
•- a >, 4j
4-1 .40 • —
to ,-1 01 ~i
e to LI .H
C 4J en .0
O 01 JC O
e- E " E






e
3
O oi
-i e u
ซ 5 10
0 •* JS
u a. LI
Ll ^-4 01 CO 0)
O to 4J Q N
ty a as j= •-
B T3 C a -<
3 -H - O h — I
•H ป4-l 0) .O 01 4J
TJ *- g Li (X Ll
O 3 .— to 3 tu
CO to ,J o CO M-l












to tn to
^-* •— i i— i
to to to
4J 4J 4J
0) 01 Ol
e B e
>> >. ^
ง•> *>
CO CO
cy CD n)
ff ffi ;ฃ
C
O *^.
•H (I)  to -H ca
^ -o d X J2
•^ •* o o a.
a u-i ja ^ ซ
•-< ^ u *n o
0 3 cfl >^ ^
0) co cj 43 a
Ui
CU | | ,
i— o)
>i CO M "H T3 U
Jf-o " c 01 o 01
<=_!> .-01J3>, c
*— ^c OJ 4-1 4-1 Ll i— 1 LiO
N$ "< "Jtooj: oi—i
•-30) .n ^J^^tnoooi4_i4j
^JOJS to 0101 --Xlt03
•— ^^4^ 4j.ซx:j2>^j3 S^-i
43-J oitnocj^ c o
30"" H | _.
>0)u 4j T3~Li.-ia>o)aj
^^E^J to^jCi-ioio— ix:4-i
O Ltco PtOO)Cฃto-^ico3
>0)4jc C4->aoi4j j33-j
c .c x o o o) oi oo'- o o -H •-
1—4JO1'— Ct-EIStOiaiiJEy^^


^<
•ฃ• H
0 C
*" 3 U
O Ol
01 01 o
C u
O 01 c .^
•—0) 01 •-
4-1 CO 00 
to to
Ol 01
* sc
00 10
C Ol
•— to
X 10 CO
ป J3 01
3 	 . 4-1
.-i co a,
PปH T3 r-l

".,5 •=
•H tO 0
ซ 1 1
•0 >"
u C O
.- to
c c
01 - O
01 o •- 01
Vw — 1 4J CO
to c to 01
01 4J C
4-1 to •— to
c LI a. oo
oj to .ซ e
— * o to
tซ 4-1 01 g
> e L, i
•- oi a. c
t- ^ 0
4J to C Ll •
> — — 01
01 to | t)
0) 4J ซ u C
N C 4J •- 3
•- 01 — i C O
-o a. 3 tv a
•- CO CO p
X O 0) Li O
C 4J Ll CO U

ni
4J

CT3
6C
c^
E
u
0)
CL
to
to
to
ij
o
&-












c
OJ
ซ
Vj
CO

4J
c
CD
•— t
cO
>
•H
ฃ



c
o
• —
4-i
o
•o
'<ง
^ 1
^> 1
i ^ iJ
1
L< 01
o tn
0 0
4-1 4^ 1
1
1— 1 1— 1 1
6> >
Li O)
CJ CC
W 01
0> 01
3 3
t) T3
0) 0)
a: pd






OJ 0>
4-i U
CO co
U-i U-i
1— t 1— 1
3 3
tn M ;
w ซ
3 3
0 o
^ u
1-1 i-l
0) 01
C-t- tin











O QJ
1-1 ^-<
f 0)
u to


c c
 >
CO to
X X
0) (U :
re 3:



c
o
• 1-1
4J
u
3
t)
(U
cd
9-43

-------
                                  TABLE 9-15.
  SITE AND SOIL CHARACTERISTICS IDENTIFIED AS IMPORTANT IN IN-SITU TREATMENT
Characteristics


Site location/topography

Slope of site-degree and aspect

Soil, type and extent

Soil profile properties
   depth
   boundary characteristics
   texture*
   amount and type of coarse fragments
   structure*
   color
   degree of mottling
   presence of carbonates
   bulk density*
   cation exchange capacity*
   clay content
   type of clay
   pH*
   Eh*
   surface area*
   organic matter content*
   nutrient status*
   microbial activity*

Hydraulic properties and conditions
   depth to impermeable layer or bedrock
   depth to groundwater*, including seasonal variations
   infiltration rates*
   permeability* (under saturated and a range of unsaturated  conditions)
   water holding capacity*
   soil water characteristic curve
   field capacity/permanent wilting point
   flooding frequency
   run-off potential*
   aeration status*

                                                                    (continued)
                                     9-44

-------
                           TABLE 9-15.  (continued)
Characteristics
Clitnatological factors
   temperature*
   wind velocity and direction
*  Factors that may be managed to enhance soil treatment

Source:  Sims and Wagner, 1983

(Manuscripts originally printed in the Proceedings of the National Conference
on Management of Uncontrolled Hazardous Waste Sites.  1983.  Available  from
Hazardous Materials Control Research Institute, 9300 Columbia Blvd., Silver
Spring, MD  20910).


destroy or reduce the toxicity of many toxic organics, but chromium III,  if
present, will oxidize to the more toxic and mobile chromium VI state.   The
permeability of soils may be reduced by the treatment approach.  In soils high
in iron and manganese, for example, oxidizing the subsurface could result in
the precipitation of iron and manganese oxides and hydroxides, which could
clog the delivery system and the aquifer.


     9.2.3  Soil Flushing


     Organic and inorganic contaminants can be washed from contaminated soils
by means of an extraction process termed "soil flushing," "solvent flushing,"
"ground leaching," or "solution mining."  Water or an aqueous solution  is
injected into the area of contamination, and the contaminated elutriate is
pumped to the surface for removal, recirculation, or on-site treatment  and
reinjection.   During elutriation,  sorbed contaminants are mobilized into
solution by reason of solubility,  formation of an emulsion, or by chemical
reaction with the flushing solution.

     Solutions with the greatest potential for use in soil flushing fall into
the following classes:

     •  Water

     •  Acids-bases

     •  Complexing and chelating agents
                                     9-45

-------
     •  Surfactants

     •  Certain reducing agents.

     Water can be used to flush water-soluble or water-mobile organics and
inorganics.  Hydrophilic organics are readily solubilized in water.  Organics
amenable to water flushing can be identified according to their soil/water
partition coefficient, or estimated using the octanol/water coefficient.
Octanol-water partition coefficients are available for a large number of
compounds in:  Substituent Constants for Correlation Analysis in Chemistry and
Biology (Hansch and Leo, 1979).Chemical Property Estimation Methods (Lyinan,
Reehl and Rosenblatt, 1982) provides various methods for estimating the
octanol-water partition coefficient using readily available physical and
chemical data.  Organics considered soluble in the environmental sense are
ones with a partition coefficient (K) of approximately less than 1000 (log K =
3).  High solubility organics, such as lower molecular weight alcohols,
phenols, and carboxylic acids, and other organics with a coefficient less than
10 (log K _
-------
     Another possibility for mobilizing metals which are strongly adsorbed to
manganese and iron oxides in soils is to reduce the metal oxides which results
in release of the heavy metal into solution.  Chelating agents or acids can
then be used to keep the metals in solution.  Treatment agents which may be
suitable for this purpose include hydroxylamine together with an acid, or
sodium dithionite/citrate.

     Surfactants can be used to improve the solvent property of the recharge
water, emulsify nonsoluble organics, and enhance the removal of hydrophobic
organics sorbed onto soil particles.  Surfactants improve the effectiveness of
contaminant removal by improving both the detergency of aqueous solutions and
the efficiency by which organics may be transported by aqueous solutions
(USEPA, 1985).  Surfactant washing is among the most promising of the in-situ
chemical treatment methods.

     Numerous environmentally safe and relatively inexpensive surfactants are
commercially available.  Use of surfactants to date has been restricted to
laboratory research.  Most of the research has been performed by the petroleum
industry for tertiary oil recovery (Barakat et al., 1983; Cash et al., 1977;
Doe, Wade, and Schechter, 1977; and Wilson and Brandner, 1977).  Aqueous
surfactants have also been proposed for gasoline cleanup.  In a study
performed by the Texas Research Institute (1979) for the American Petroleum
Institute, a mixture of an anionic and nonionic surfactants result in con-
taminant recovery of up to 40 percent.  In a laboratory study conducted by
Ellis and Payne (1983), crude oil recovery was increased from less than
1 percent to 86 percent, and PCB recovery was increased from less than
1 percent to 68 percent when soil columns were flushed with an aqueous
surfactant solution.

     Characteristics of surfactants and their environmental and chemical
properties are listed in Table 9-16 (USEPA, 1985).  This table can be used to
aid in the preliminary selection of a surfactant.  However, laboratory testing
of the surfactant should be performed to verify surfactant properties.

     An economically feasible soil flushing method may involve the recycling
of elutriate through the contaminated material, with make-up solvent being
added to the system while a fraction of the elutriate stream is routed to a
portable wastewater treatment system.  The appropriate types of wastewater
treatment operations will depend on waste stream characteristics, and a
discussion of their applications can be found in Section 10.1.

     The advantages of the soil flushing process are that, if the waste is
amenable to this technique and distribution, collection, and treatment costs
are relatively low, solution mining can present an economical alternative to
the excavation and treatment of the wastes.
                                     9-47

-------


























(A
O
P
ฃ
ฃ
UJ
.&
Sl
UJ J
m O
rf i—

1
JRFACTAN
V)























X
4M>
4-1
I













>>
~
A
5




ฃ
^

O VI
W 01
a. vi
Ol T3
ti
01
5










1
4-ป
^""






OJ

c —
— c
,2 A
ซ. ฃ
1 1

U) UJ



,
T
•fl
t
i

Wl
4-"
X CT>
U *
c
O? 9
F .2
9) 4->
• •



VI

(O
VI (^1
4-1
ป~ L.
* 01
•O UJ
5 2
U *
1 Carboxyl
1 Sulfuric
— 1 CVI
I
i
01
c
c —
o ซ
re >- <

* •- T3

•o * -o
O 4-> —
•ป- <-n u
O ซ O
4-1 U 4J
งV C VI
ฃ ซ >.
4J (_> 4J —

K X ซZ

VI
u


CTI


U


ฃ
c
Ol

31
•

c
01 S_
4J
Ol 13

ซ- 01 c 
=| :i
o c -a •—
s- o 63
• •

u

ฃ;
ฃ VI
O. u
t's
- I ^
1 T, ซ
*A 0> ^
01 ^ u
u *^ e <
I. UJ i. (J
4s 1 i
I/I u *- 1^-
0< I. —
ฃ ซl 3
a. &. 1/1













01
1
on
T3
5





u
O)
4-t
 ••-
ป^
35
•

1^
4^>
s
5"

Emulsifying
•







VI
o>
c
i
c
ฃ
2
0
_J
I-*
o
1
s































k.
o
4-1
A
JC
c
Corrosion li
•






S
c
"o
OL

1
Q
tvi








O
*J VI
c"^
o —
••- 1.
w OV
0.4.1
a*
ace Ad
caeous

on on











oป
1
5
u
O)
TJ
3
•










ฃ

,
%
c
a)
Or
m






>,
*-ป


i
U">
u
'i
6

I



Ol

i




o>

X

O)

•

l/l
4->
c
V
ฃ

I
1
•



^


5 Z
•$ -gง
ซ•* 4-1 0)
ป
>>0l ป..* vi
ฃ C ฃ J Ol
"o ฃ "o J= 5
flL U i^ ft i . i
ซr ซ
u
1
i




,
•o
•9
u
S1
1

CQ
o
4~*
1
4-1
VI C
""• O
VI -~
01 4->
ac "5
VI
C
O
4U
ซ3

3
O
U.

Ol

1
o
V)
c
1-
0)
i






Detergents
•

ซ-*

CTI O
ซ o
h. U

i-
***ฃ vi
ฃ O Ol
X *'>>
8,58
oSS
a. o LU
CM









U
X
o

I
X

O)
ac




















1/1
•w
C
Wetting Age
Oispersents
• •
wi
m

o.
X u

i ป 1
•0*0 -p
41 u aJ
W X 4-*
* ^- fl
ฃ* e
— D —
>• e x
ฃ 5 ฃ
) Polyoxyel
oxypropy
) Polyoxyel
m ป










•o vi
* VI
>,
^ ^-
5ฐ
**
o z
4->
-S
!d =
•o *O
II






















O
W
*J
c
o
u
X
0
u.
•

w
•0 s
U 0)


(J 
-------
                                                O>     0) l/ป
                                               —    ae 4i
                                                        U
                                                      O 19
                                                      ง
                                                tf
                                               C    3
                                                      L.  CTI
                                                      O  1-
                                          01
                                          •o

                                          I
O
UJ
                                           0)

                                           L.
                                           TJ
O
o

cd

en
UJ

00
O en
I- Oi
O. vi
   =9
13
0)f3
4J C
5    a.
^    c
                                                UJ
                                                (/J
0)
a
3
O
CO
                                           •^     vt
                                           VI     C
                                           C     01
                          U 0)
                          10 a
                                                          9-49

-------
     9.2.4  Immobilization
     Immobilization methods are designed to render contaminants insoluble and
prevent leaching of the contaminants from the soil matrix and their movement
from the area of contamination.  Little is currently known about the
effectiveness and reliability of immobilization techniques (Truett, Holberger,
and Banning, 1982).

     Immobilization methods which are currently being investigated include:
precipitation, chelation, and polymerization.

     Precipitation is the most promising method for immobilizing dissolved
metals such as lead, cadmium, zinc, and iron.  Some forms of arsenic,
chromium, mercury, and some organic fatty acids can also be treated by
precipitation (Huibregtse and Kastman, 1979).  All of the divalent metal
cations can be precipitated using sulfide, phosphate, hydroxide, or carbonate.
However, the solubility product and the stability of the metal complexes vary.
Because of the low solubility product of sulfides and the stability of the
metal sulfide over a broad pH range, sulfide precipitation looks most promis-
ing.  The remaining anions decrease in effectiveness in the following order:
phosphate > hydroxide > carbonate.  Metal carbonates and hydroxides are stable
only over a narrow pH range and the optimum pH range varies for different
metals.  Precipitation of the metal as the metal phosphate may require very
high concentration of orthophosphate since calcium and other naturally
occurring soil cations present in high concentrations will precipitate first.

     Sodium sulfate used in conjunction with sodium hydroxide has  shown wide-
spread applicability for precipitatiion of metals.  Precipitation  takes place
at a neutral or slightly alkaline pH.  Resolubilization of sulfides is low.
Addition of sodium hydroxide minimizes the formation of hydrogen sulfide gas
by assuring an alkaline pH.  Experiments with sulfide precipitation of zinc
indicate that a high residual of unreacted sulfide may remain in solution.

     As with other in-situ 'techniques, precipitation is most applicable to
sites with sand or coarse silt strata.  Disadvantages include the  injection of
a potential groundwater pollutant; the potential for formation of  toxic gases
(in the case of sulfide treatment); the potential for clogging soil pore
space; and the possibility of precipitate resolubilization.

     The use of chelating agents may also be a very effective means of
immobilizing metals although considerable research is needed in this area.
Depending upon the specific chelating agent, stable metal chelates may be
highly mobile (as described in Section 9.2.3) or may be strongly sorbed to the
soil.  Tetran is an example of a chelating agent which is strongly sorbed to
clay in soils (USEPA, 1984a).

     A third method for immobilizing metals applies specifically to chromium
and selenium.  These metals can be present in the highly mobile, hexavalent
state but can be reduced to less mobile Cr (III) and Se (IV) by addition of
ferrous sulfate.  Arsenic exists in soils as either arsenate, As (V), or as
                                     9-50

-------
arsenite, As  (ill),  the more  toxic and  soluble  form.  Arsenic  can  be  effec-
tively immobilized by oxidizing As (ill)  to As  (IV) and  treating the  As  (IV)
with  ferrous  sulfate to form  highly  insoluble Fe-AsO,.

     Polymerization  involves  injection  of a catalyst  into  a  groundwater  plume
to cause polymerization of an organic monomer (e.g.,  styrene,  vinyl chloride,
isoprene, methyl methacrylate, and acrylonitrile).  The  polymerization
reaction transforms  the once  fluid substance into a gel-like,  non-mobile mass.
In-situ polymerization is a technique most suited for groundwater  cleanup
following land  spills or underground leaks of pure monomer.  Applications  for
uncontrolled  hazardous waste  sites are  very limited.  Major  disadvantages
include very  limited application and difficulty of initiating  sufficient
contact of  the  catalyst with  the dispersed monomer (Huibregtse and Kastman,
1979).  In-situ  polymerization was successfully performed  to remedy an
acrylate monomer leak, in which 4,200 gallons of acrylate  monomer  leaked from
a corroded  underground pipeline into a  glacial  sand and  gravel layer.  Soil
borings indicated  that as much as 90 percent of the monomer  had been
polymerized by  injection of a catalyst, activator, and wetting agent
(Williams,  1982).

      In-situ  treatment of a leachate plume using precipitation or  polymer-
ization techniques probably has limited application.  Problems associated with
these techniques include:

     •  Need  for numerous, closely-spaced injection wells  even in  coarse-
        grained  deposits because the action of  precipitation or polymerization
        will  lower hydraulic  conductivities near injection wells reducing
        treatment  effectiveness

     •  Contaminants are not  removed from the aquifer or some  chemical
        reactions  can be reversed allowing contaminants  to again migrate with
        groundwater  flow

     •  Injection  of a potential groundwater pollutant or  the  formation of
        toxic byproducts.

Therefore, prior to the application of  an in-situ precipitation or polymeriza-
tion technique at  a hazardous waste site, thorough laboratory- and pilot-scale
testing should be  conducted to determine deleterious effects and assure
complete precipitation or polymerization of the chemical compounds.

     Solidification methods used for chemical soil consolidation can also
immobilize contaminants.   Solidification and stabilization techniques are
assessed in terms of their applicability for in-situ treatment of  landfilled
wastes in Guide to the Disposal of Chemically Stabilized and Solidified Wastes
(USEPA,  1982).  The assessment concluded that most work with these techniques
has not involved in-situ treatment;  most are not applicable to hazardous waste
sites, and most of the techniques involve a thorough mixing of the solidifying
agent and the waste (Truett,  Holberger, and Banning,  1982).  Injection of
silicate gel may be feasible   to immobilize subsurface contaminants, but may
negatively impact groundwater quality (Truett,  Holberger,  and  Sanning, 1982).
                                     9-51

-------
     9.2.5  Detoxification
     In-situ treatment techniques discussed in this section are those which
serve to destroy, degrade, or otherwise reduce the toxicity of contaminants
and include neutralization, hydrolysis, oxidation/reduction, enzymatic
degradation, and permeable treatment beds.  These methods are applicable to
specific chemical contaminants, therefore, use of these in-situ techniques at
waste sites will be limited.

     Neutralization involves injecting dilute acids or bases into the ground-
water to adjust the pH.  This pH adjustment can serve as pretreatment prior to
in-situ biodegradation, oxidation, or reduction to optimize the pH range.  It
can be used to neutralize acidic or basic plumes that need no other treatment,
or to neutralize groundwater following another treatment.  It can also be used
during oxidation, reduction, or precipitation to prevent the formation of
toxic gases including hydrogen sulfide and hydrogen cyanide.

     The pH adjustment can also be used to increase the hydrolysis rate of
certain organics.  Hydrolysis involves the displacement of a group on an
organic moiety with a hydroxyl group from water, according to the displacement
reaction:

                  RX + H20 -ป ROH + HX

in which R is the organic moiety and X is the leaving group.  Of the param-
eters which affect the rate of hydrolysis (temperature, solvent composition,
catalysis, and pH), pH adjustment has the greatest potential.  The rate of
hydrolysis can be increased up to one order of magnitude for a change of one
standard unit in pH (USEPA, 1985).  Classes of compounds with potential for
in-situ degradation by hydrolysis include:

     •  Esters

     •  Amides

     •  Carbamates

     •  Phosphoric and phosphonic acid esters

     •  Pesticides.

Because a hydrolysis product may be more toxic than the present compound, the
pathways for reactions must be determined to ensure toxic products are not
produced.  USEPA (1985) has a more thorough discussion of this technology.

     Many of the environmental, health, and safety considerations that apply
to solution mining also apply here.  In contrast to solution mining, in-situ
neutralization/detoxification techniques do not inherently incorporate
collection systems.  However, a collection system should be incorporated as a
fail safe measure, to prevent migration of the treatment reagents and any
contaminants which are not successfully treated.
                                     9-52

-------
     Oxidation and reduction reactions serve to alter the oxidation state of a
compound through loss or gain of electrons, respectively.  Such reactions can
detoxify, precipitate, or solubilize metals, and decompose, detoxify, or
solubilize organics.  Oxidation may render organics more amenable to bio-
logical degradation.  As with many of these chemical treatment technologies,
oxidation/reduction techniques are standard wastewater treatment approaches,
but their application as in-situ treatment technologies is largely conceptual.

     Oxidation of inorganics in soils, is for all practical purposes limited
to oxidation of arsenic and possibly some lead compounds.  The in-situ
oxidation of arsenic compounds with potassium permanganate (KMnO,) has been
used to successfully reduce the arsenic concentrations in groundwater in the
vicinity of a zinc ore smelter near Cologne, Germany (Stief,  1984).  64,000
lb- of KMnO, were injected into 17 wells and piezometer wells resulting in an
average decrease in arsenic groundwater concentrations from 13.6 mg/1 to 0.06
mg/1 from 1975 to 1977.  In 1979, however, an increase indicated that the
mixing of groundwater and KMnO, had not been thorough.

     Of the numerous oxidizing agents available, three have been considered
potentially useful in the in-situ detoxification of organics groundwater and
soils contaminated with organics:  hydrogen peroxide, ozone, and hypochlorites
(USEPA, 1985).  Each can react with a broad range of organics and could
potentially oxidize a number of different organic contaminants in a hazardous
waste site-  Selection of the appropriate oxidizing agent is dependent in part
upon the substance or substances to be detoxified, but also upon the feasi-
bility of delivery and environmental safety.  Although there are some
compounds that will not react with hydrogen peroxide but will react with ozone
or hypochlorite, hydrogen peroxide appears to be the most feasible for in-situ
treatment.

     Ozone gas is a very strong oxdizing agent that is very unstable and
extremely reactive.  It cannot be shipped or stored; therefore it must be
generated on-site prior to application.  Ozone rapidly decomposes and its
half-life in groundwater is only 18 minutes (USEPA, 1985).  Ozone is used in
the treatment of drinking water, municipal wastewater, and industrial waste,
but has never been used in the treatment of contaminated soils or groundwater.
Ozone oxidation with ultraviolet irradiation successfully reduced concentra-
tions of benzene, phenols, and trichloroethylene in lake water (Glaze et al.,
1980).

     Hypochlorite, generally available as potassium, calcium, or sodium hypo-
chlorite (bleach) is also used in the treatment of drinking water, municipal
wastewater, and industrial waste.  Hypochlorites have never been used in the
treatment of contaminated groundwater or soils.  Tolman et al. (1978) has
described the conceptual design and in-situ detoxification of cyanide with
sodium hypochlorite.  The reaction of many organics with hypochlorite results
in the formation of chlorinated organics which can be as or more toxic than
the original contaminant.  The formation of lower molecular weight chlorinated
organics (e.g., trihalomethanes) in drinking water from hypochlorite treatment
for disinfection purposes has become a major concern of the drinking water
industry.


                                     9-53

-------
     Hydrogen peroxide (H,^)-), a moderate strength chemical oxidant, is used
routinely in municipal wastewater treatment to control various factors of
biological treatment, and is also used in industrial waste treatment to
detoxify cyanide and various organic pollutants.  Table 9-17, developed by
USEPA (1985), indicates chemical compound classes that may be degraded using
hydrogen peroxide.

     Hydrogen peroxide is commercially available in aqueous solutions of
several concentrations and is miscible in water at all concentrations.  It has
been delivered successfully in dilute solutions to the subsurface as an oxygen
source in a bioreclamation project (Raymond, Jamison, and Hudson, 1984) (see
Section 9.1).  One supplier has developed a line of hydrogen peroxide
solutions specifically designed for reclamation purposes (FMC, 1985).

     Chemical reduction is the process by which the oxidation state of a
compound is reduced.  Reducing agents are election donors, with reduction
accomplished by the addition of elections to the atom.

     Chemical reduction does not appears as promising as oxidation for the
treatment or organics.  Although reseaches have demonstrated reductive
dehalogenation of a variety of chlorinated organics and reduction of
unsaturate aromatics and aliphatics in laboratory studies using catalyzed
metal powders the treatment reagents are costly and the effectiveness of
chemical reduction in soils has not been demonstrated.

     Chemical reduction does, however, appear promising for treatment of
chromium and selenium in soils.  The in-situ reduction of hexavalent to
divalent chromium has been accomplished in Arizona well water using minute
quantities of reducing agent.  (Srivastava and Haji-Djafari, 1983).

     There are a number of disadvantages with the use of oxidizing and
reducing agents which limit their use at hazardous waste sites.  The treatment
compounds are non-specific and this may result in degradation of non-targeted
compounds.  There is the potential, particularly with oxidation, for the
formation of more toxic or more mobile degradation products.  Also, the
introduction of these chemicals into the groundwater system may create a
pollution problem in itself.  As with soil flushing, uncertainty exists with
respect to obtaining adequate contact with the contaminants in the plume.

     Enzymatic degradation of organics with cell-free enzymes holds potential
as a possible in-situ treatment technique.  Purified enzyme extracts,
harvested from microbial cells, are commonly used in industry to catalyze a
variety of reactions, including the degradation of carbohydrates and proteins.
A bacterial enzyme preparation has been used to detoxify organophosphate waste
from containers (Munnecke, 1980).  Parathion hydrolase has been tested under
field conditions in the degradation of the pesticide diazinon (Paulson et al.,
1984).  The studies indicate that parathion hydrolase can be used to effec-
tively reduce rapidly large concentrations of diazinon in soil.  The enzyme is
readily soluble in water, is reasonably stable at summer temperatures, and can
be easily handled in the field.  The pH or organic content of the soil does
not appear to affect the enzyme's effectiveness.  It appears from the study
                                     9-54

-------











UJ
O
X
o
CC
UJ
OL

z
111
o
o
cc
o
^*
z
^M
X


i

ฃ3

ฃ cc

o* ^^
iii S*^
-1 ["
00 >•
25

03

CO
UJ
CO
CO
o
s
i
UJ

u
UJ
I



























VI
c
i
o















=

c
1

Q
aE
VI









•o
c
u

u
i
JC
VI
Ol
•o
X
0
Ol
e
0
VI
•o
3
ง
ฐ
Ol
*->
u
3
<9
I/I
C
3

Ol
•.- VI
u e

Ol >>
C X
ซ o

"n >,
•a i
Ol >,
•*-ป •—

3
4j "^j
vi "9


X



X







I/I
c
fc.
ซ5
*
•O VI
5- 1
U i—
•Z 3
5 -
& >>
< <
























VI 4->
>1 VI
*^ ^*l

4-> 'Q
3 1o
U
CS1
+ Ol
Ol 1.
U. -f-
3
Ol O-
t- Ol
•i- L.
3
O" >.
0) ซ
<_ e


X X










I/I
•s
X
ut
•Q
c
VI VI
c. i/i 01
Ol Ol C VI
j: -o o -o
W .^ ซJ H-
uj x 01 u
o ^ ซ*
V a-
Ol UJ • U
U VI "-
ig VI . Ol r-
e *- vi -e >>
VI Ol Of- >> X
<. 5iฃ o ฃ o
Ol O O U Ol ^
ฃ •— U XT3 <-
UJ X S3 < 
I/I VI


IQ > >> 7



X XX










Ol
C VI
01 -a
i/i Ol O
ฃ -g*|
•p* X 01 O
N O 4J
a vi <*- 3 u
>l -1-  VI •
*^ *^ o
• 3 VI 3 U
vi  ซ 4ป ^- 4J C
VI M ^— ^ O i™ tf* ^ ^ C C V
4) !• ซrป ftl O C O *"•" '^ O ttf 9
T3 * C. C 4ll.O<*-ซ*-NO
••-4^4-ซ>*- o a *j — — i— cซ—









































X X





1
fc.
u
o
•0
x1 vi
•o
i/i u e i/i i/i
•S Sii— '^ s s S
C tป O C (J 4J ^L
O >> O> C I- O
O.X *J O 01 3 ปf— u o u jC
^- U < t- — — &
ง>| 1 *— i^ ^- VI
^ป c u u u O
o •o -a i- t. t c
i. Ol 01 01 Ol ซ ซ
+-I VI VI *J ** ** O>


































1

••
^
01
!
o
3
&

















9-55

-------
that parathion hydrolase could be used effectively to clean up diazinon
spills, but more research is required to determine how to obtain optimal field
efficacy of the enzyme.

     Permeable treatment beds are essentially excavated trenches placed
perpendicular to groundwater flow and filled with an appropriate material to
treat the plume as it flows through the material (see Figure 9-7).  Some of
the materials that may be used in the treatment bed are limestone, crushed
shell, activated carbon, glauconitic green sands, and synthetic ion exchange
resins.  Permeable treatment beds have the potential to reduce the quantities
of contaminants present in leachate plumes.  The system is applicable to
relatively shallow groundwater tables containing a plume.  To date, the
application of permeable treatment beds at hazardous waste sites has not been
performed.  However, bench- and pilot-scale testing has provided preliminary
quantification of treatment bed effectiveness.  Potentially numerous problems
exist in using a permeable treatment bed.  These include saturation of bed
material, plugging of bed with precipitates, and short life of treatment
materials.  Therefore, permeable treatment should probably be considered as a
temporary remedial action rather than a permanent one.

     A limestone or crushed shell bed can be used to neutralize acidic ground-
water and retain certain metals such as cadmium, iron, and chromium.  The
effectiveness of limestone as a barrier depends primarily on the pH and volume
of the solution passing through the limestone (Artiola and Fuller, 1979).  The
nature of the heavy metal is also an important factor.  A laboratory study
demonstrated that limestone was more effective at retaining chromium III than
for chromium VI and other metals (Artiola and Fuller, 1979).

     Fuller and other researchers (USEPA, 1978) have discussed the use of
crushed limestone as an effective, low cost landfill liner to aid in attenu-
ating the migration of certain heavy metals from solid waste leachates.
According to the authors, dolomitic limestone (containing significant amounts
of magnesium carbonate) is less effective in removing ions than purer
limestone containing little magnesium carbonate.  Therefore, in the design of
a limestone treatment bed, limestone with high calcium content is recommended
to remove heavy metals and to neutralize contaminated groundwater.

     In regard to designing vertical permeable treatment beds, the particle
size of the limestone used should be selected dependent on the type of soil in
which groundwater flows (i.e., which controls flow rates) and the level of
contamination.  In general, a mixture of gravel-size and sand-size limestone
should be used to minimize settling through dissolution.  Where excessive
channelling through the bed by rapid groundwater movement is expected or where
improved contact time between the contaminated groundwater and the treatment
bed is required, a higher percentage of sand-size particles is more
appropriate.

     A variation on the use of limestone permeable treatment beds to neutral-
ize plumes is the use of limestone or crushed shell layered over a waste site
to indefinitely stabilize the disposed waste.  This approach will be used to
                                     9-56

-------
                FIGURE 9-7
INSTALLATION OF A PERMEABLE TREATMENT BED
                             Permeable Treatment Bed
                 9-57

-------
reduce solubility of metal hydroxides by maintaining highly alkaline
conditions in the waste (Francis, 1984).

     Activated carbon as a possible treatment bed material has the capability
of removing nonpolar organic compounds from contaminated plumes, but is not
practical for the removal of heavy metals.  Activated carbon will not remove
polar organics.  However, the high cost of activated carbon, the potential for
desorption of adsorbed compounds, and the likelihood of a short bed-life in
the presence of high waste concentrations make the use of activated carbon
beds cost-prohibitive under most circumstances.

     Glauconitic greensands have potential for the removal of heavy metals.
Bench-scale studies with leachate indicate that the highest removal effi-
ciencies are for copper, mercury, nickel, arsenic, and cadmium and that effi-
ciencies increase with contact time (Spoljaric, N. Delaware Geological Survey,
Newark, DE, personal communication, 1980).  With contact time in the field
being on the order of days, metal removal efficiencies may be extremely high.
Experiments indicate that the greensands may also have a high capacity for
heavy metal cation retention, even when flushed with solutions of highly
alkaline or acidic pH (Spoljaric, N. Delaware Geological Survey, Newark, DE,
personal communication, 1980).  An in-situ experiment in England (Ross, 1980)
demonstrated promising retention capabilities.  Glauconitic greensands appear
promising; however, more research is required to determine their sorptive
capacity and capability for treating higher concentrations of heavy metals.

     Advantages of glauconitic treatment beds, based on studies to date,
include good permeability, abundance in the Atlantic Coastal Plain (i.e., New
Jersey, Delaware, and Maryland), effectiveness in removal and retention of
many heavy metals, and good retention time characteristics for efficient
treatment.  Among the disadvantages of using glauconitic treatment beds are
unknown saturation characteristics and potential for plugging over time,
potential reduction in pH, limited to areas of natural occurrence such as the
mid-Atlantic region, and possibility of land purchase requirements as
glauconite is not commercially mined•


     9.2.6  Technology Selection/Evaluation


     This section described a wide range of chemical and in-situ treatment
methods, therefore, generalizations regarding the feasibility and effective-
ness of these methods are not possible.  However, all of these methods are
developmental or conceptual and none have been fully demonstrated for
hazardous waste site remediation.

     Of all the methods described, soil flushing methods involving the use of
water surfactants appear to be most feasible and cost-effective for organics.
They .can use relatively cheap, innocuous treatment reagents, can be used to
treat a broad range of waste constituents, and do not result in toxic degrada-
tion products.
                                      9-58

-------
     The most feasible methods for treating inorganics in-situ  include  soil
flushing with dilute acids, chelating agents or other treatment agents  which
will mibolize the metals.  Precipitation of the metals as  sulfides  or
phosphates, and the use of permeable treatment beds have potential  application
although there are potentially serious drawbacks with each of these methods.
For example, permeable treatment beds are prone to clogging, and sulfide
precipitation can clog soils and reduce permeability.

     Mention of these potential drawbacks should not preclude consideration of
in-situ methods.  However, laboratory- and possibly pilot-scale testing is
likely to be required in each case, resulting in delays in implementing the
remedial action.

     As with biological treatment methods, chemical treatment methods used to
deliver and recover treatment reagents also affect the reliability  of these
methods.  Reliability of pumping and subsurface drainage systems have been
described previously.

     Again, worker safety considerations are the same as those  related  to
in-situ biological treatment methods involving a potentially hazardous
chemical reagent.  The same precautions required when working with  hydrogen
peroxide (Section 9.1.6) are required when working with acids,  bases,
surfactants, and other potentially hazardous reagents.
     9.2.7  Costs
     Costs for the chemical in-situ treatment approaches discussed in this
section are difficult to estimate since these methods have largely not been
demonstrated at hazardous waste sites and no actual cost data are available.
In-situ treatment costs are variable, but could be less than excavation and
removal methods and/or pump and treat methods.  As with removal, in-situ
approaches are conducted on a one-time basis, so there are generally no
long-term operation and maintenance costs.

     Costs for the chemical treatment approaches involving the delivery of a
reagent to the subsurface (soil flushing, various immobilization techniques,
neutralization, hydrolysis, oxidation, reduction, and enzymatic degradation)
will depend on the amount of material to be treated, the amount of chemical
reagent required, the costs for the delivery system (injection wells or
infiltration galleries), the chemical and feed system, and fees for probing,
excavation, and drilling.  Costs for laboratory- and pilot-scale studies
should also be considered when performing such a treatment approach.  Soil
flushing, which involves bringing contaminated water to the surface for
treatment, would require a wastewater treatment system.  Costs for the drains
and pumping are presented in Sections 5.1 and 5.2, respectively.  Table 9-10
provides unit costs for chemicals.

     1985 unit costs for the installation of a permeable treatment bed are
shown in Table 9-18.  Total closure costs for stabilizing approximately 8,000


                                     9-59

-------
                                  TABLE 9-18.
           UNIT COSTS FOR INSTALLATION OF A PERMEABLE TREATMENT BED
   Item
     Assumptions
    Costs
Trench excavation
Spreading
Well-point dewatering
Sheet piling
Walers, connections,
  struts

Liner
Limestone
20 ft deep, 4 ft wide,
by backhoe

Spread by dozer to grade
trench and cover

500 ft header 8" diameter,
for one month

20 feet deep; pull
and salvage

2/3 salvage
30 mil PVC
30 mil CPE

Mixed "gravel size" and
"sand size"

Installation
(Backfill trench,
100 foot haul)
$1.40 cubic yard
$l/cubic yard
$115/linear foot
$7.70/square foot
$165/ton
$0.25-0.35/square foot
$0.35-0.45/square foot

$30-45/ton3
                                                       $3.70/cubic yard
-Godfrey, 1984; Costs are total, including contractor overhead and profit.
-Godfrey, 1984; Materials only.
fSchnell, 1985.
 Cope, Karpinski, and Steiner, 1984.
                                     9-60

-------
cubic yards of sludge contaminated with nickel hydroxide by covering the site
with a I inch layer of calcium carbonate are estimated at $100,000 to
$200,000, compared with $900,000 to $1 million estimated for excavation and
removal (Francis, 1984).


9.3  Physical In-Situ Methods


     9.3.1  General Description
     A number of methods are currently being developed which involve physical
manipulation of the subsurface in order to immobilize or detoxify waste
constituents.  These technologies, which include in-situ heating, vitrifica-
tion and ground-freezing, are in the early stages of development and detailed
information is not available.

     In-situ heating has been proposed as a method to destroy or remove
organic contaminants in the subsurface through thermal decomposition, vapori-
zation, and distillation.  Methods recommended for in-situ heating are steam
injection (Hoogendorn, 1984) and radio frequency heating (Dev, Bridges, and
Sresty, 1984).

     The radio frequency heating process has been under development since the
1970s.  Field experiments have been conducted for the recovery of hydro-
carbons.  The method involves laying a row of horizontal conductors on the
surface of a landfill and exciting them with an RF generator through a
matching network.  The decontamination is accomplished in a temperature range
of 300ฐ to 400ฐC, assisted with steam, and requires a residence time of about
two weeks.  A gas or vapor recovery system is required on the surface.  Exca-
vation, mining, drilling, or boring is not required.  Field tests found that
leakage radiation levels did not exceed the recommended ANSI Standard C-95.
Preliminary design and cost estimates for a mobile RF in-situ decontamination
process (see Section 9.2.5) indicate that the method is 2 to 4 times cheaper
than excavation and incineration (Dev, Bridges, and Sresty, 1984).  This
method appears very promising for certain situations involving contamination
with organics, although more research is necessary to verify the effectiveness
in-situ.

     Artificial ground freezing involves the installation of freezing loops in
the ground and a self-contained refrigeration system that pumps coolant around
the freezing loop (Sullivan, Lynch and Iskandar, 1984).  Although never used
in an actual waste containment operation, the technology is being used
increasingly as a construction method in civil engineering projects.
Artificial ground freezing is done not on the waste itself, which may have a
freezing point much lower than that of the soil systems, but on the soil
surrounding the hazardous waste.  It renders the soil practically impermeable,
but is useful only as a temporary treatment approach because of the thermal
maintenance expense (Sullivan, Lynch, and Iskandar, 1984).
                                     9-61

-------
     In-situ vitrification is a technology being developed for the stabiliza-
tion of transuranic contaminated wastes, and is conceivably applicable to
other hazardous wastes (Fitzpatrick et al., 1984).  Several laboratory-scale
and pilot-scale tests have been conducted, and a large-scale testing system is
currently being fabricated.  The technology is based upon electric melter
technology, and the principle of operation is joule heating, which occurs when
an electrical current is passed through a molten mass.  Contaminated soil is
converted into durable glass, and wastes are pyrolyzed or crystallized.  Off-
gases released during the melting process are trapped in an off-gas hood.  The
depth of the waste is a significant limiting factor in the application of this
technology:  1 to 1.5 meters of uncontaminated overburden lowers release
fractions considerably (Fitzpatrick et al., 1984).

     Cost estimates for five in-situ vitrification large-scale configurations
are provided in Table 9-19 (Fitzpatrick et al., 1984, citing Oma et al.).
These cost comparisons are based on vitrifying to a depth of 15 feet.  Of
these costs, approximately 30 to 46 percent is for power, 10 to 13 percent is
for equipment, 36 to 45 percent is for labor, and 5 to 10 percent is for
electrodes (Banning, 1984).  Soil moisture can increase operating costs by
increasing requirements because the water in the soil must be evaporated.
Estimates for treating a humid site in the eastern United States is near
$85/cubic foot (1982 dollars) (Sanning, 1984).

     The cost of a hypothetical hazardous waste site decontaminated by radio
frequency heating was estimated for a 1 acre landfill area with contamination
extending to 20 feet (Dev, Bridges, and Sresty, 1984).  Volatile matter in the
landfill was assumed to range from 5 to 20 percent by weight, with 10 percent
of the total volatile matter being organic.  Total capital costs for a
purchase power option was estimated at approximately $17 million.  The capital
costs increase to $27.5 million if the power is generated on-site.  Capital
costs for equipment for excavation and incineration were estimated at
$832,000.  The total costs of decontamination (including operating costs but
not capital costs) was estimated to be between $4.6 and $5.7 million for radio
frequency heating (purchased power plant).  Total treatment costs for
incineration (excluding capital costs) were estimated at between $9 and $25.2
million (Dev, Bridges, and Sresty, 1984).

     Figure 9-8 provides estimated costs for ground freezing plotted as a
function of freezing rod space for a hypothetical site.  The site requires a
1,000 foot frozen wall which is 3 feet thick and is placed down to depth of
bedrock (40 feet).  The site is assumed to be located in coarse quartz sand,
150 miles from the drilling and refrigeration contractors.  From Figure 9-5,
one can see that as the drill space becomes tighter, the fuel costs, equipment
rentals, and time for wall completion are reduced.  A tight drill space yields
small frozen soil column radii and permits use of less expensive refrigeration
equipment.  The drawback of close drill spacing is the expense associated with
the drilling operation.  The linear footage of piping, a drive shoe for each
well drilled, and the labor charge per vertical foot drilled overwhelm all
other economic parameters.  Analysis of costs for this hypothetical site
illustrated that ground/freezing is only applicable as a short-term remedial
measure (Sullivan, Lynch, and Iskandar, 1984).


                                     9-62

-------
                                  TABLE 9-19.
 1982 COST ESTIMATES FOR FIVE IN-SITU VITRIFICATION LARGE-SCALE CONFIGURATIONS



Number
1
2

3

4
5


Site
Hanford
Hanford

Hanford

Generic
Generic


Power
Local
Local

Local

Local
Portable


Heat Loss
High
Average

Average

Average
Average

Manpower
Level
Average
Average

Above
Average
Average
Average
Total Cost
of Soil
Vitrified
$187/m3
$161/m3
3
$183/m

$180/m3
$224/m3
Total Cost
of Soil
Vitrified
$5.30/ft2
$4.60/ft2
2
$5.20/ft

$5.10/ft2
$6.30/ft2

Source:  Fitzpatrick et al., 1984
                                     9-63

-------
                          FIGURE  9-8
         ECONOMIC OVERVIEW OF GROUND FREEZING FOR
                      A HYPOTHETICAL SITE
    500 _.


    400 -


8  sooj
5

I  200 J


    100 L
                      FROZEN WALL 1000 X 3 X 40 FT
             SOLID   - OVERALL COST
             _._._   - DRILL EXPENSE
             	   - FUEL COSTS
             	   - EQUIPMENT RENTAL
             	- DAYS
                                                      -50
                                                        30D
                                                          A
                                                          Y
                                                          S
                       4         6         8

                         DRILL SPACING (FT)
                                                 10
Source: Sullivan, Lynch, and Iskandar, 1984
                              9-64

-------
                                  REFERENCES
Artiola, J., and W.H. Fuller.  1979.  Effects of Crushed Limestone Barriers on
Chromium Attenuation in Soils.  Journal of Environmental Quality.  Vol. 9, No.
4.  pp. 503-510.

Barakat, Y., L.N. Fortney, R.S. Schechter, W.H. Wade, and S.H. Yiv.   1983.
Criteria for Structuring Surfactants to Maximize Solubilization of Oil  and
Water.  J. Colloid Interface Sciences.  Vol. 92, No. 2.
                                                                  pp. 561-574.

Cash, L., J.L. Cayias, G. Fournier, D. Macallister, T. Schares, R.S.
Schechter, and W.H. Wade. 1977.  The Application of Low Interfacial Tension
Scaling Rules to Binary Hydrocarbon Mixtures.  J. Colloid Interface Science.
Vol. 59, No. 1.  pp. 39-44.

Considine, D. (ed.)  1974.  Chemical and process technology encyclopedia.
McGraw-Hill Book Company, New York, NY.
Cope, F.W., G. Karpinski, and R.L. Steiner.  1984.  Use of Liners for
Containment at Hazardous Waste Landfills.  Pollution Engineering.  Vol.
No. 3.  pp. 22-32.
                                                     16,
DeRenzo, D. (ed.)
Industrial Wastes.
1978.   Unit Operations for Treatment of Hazardous
 Noyes Data Corporation,  Park Ridge, NJ.
Dev, H., J.E. Bridges, and G.C. Sresty.  1984.  Decontamination of Hazardous
Waste Substances from Spills and Uncontrolled Waste Sites by Radio Frequency
in Situ Heating.  In:  1984 Hazardous Material Spills Conference Proceedings,
Government Institutes, Inc., Rockville, MD.

Doe, P.H., W.H. Wade, and R.S. Schechter.  1977.  Alkyl Benzene Sulfonates  for
Producing Low Interfacial Tensions Between Hydrocarbons and Water.  J. Colloid
and Interface Science.  Vol. 59, No. 3.
                                                                  pp.  525-531.

Ehrlich G.G., E.M.  Godsy, D.F. Goerlitz, and M.F. Hult.  1983.  Microbial
Ecology of a Creosote-Contaminated Aquifer at St. Louis Park, Minnesota.   In:
Developments in Industrial Microbiology, Volume 24.  John D. Lucas Printing
Co., Baltimore, MD.

Ellis, W.D. and J.R. Payne.  1983.  Chemical Countermeasures for In Situ
Treatment of Hazardous Material Releases.  USEPA, Edison, NJ.

Ellis, W.D. and J.R. Payne.  1984.  The Development of Chemical
Countermeasures for Hazardous Contaminated Soil.  In:  1984 Hazardous
Materials Spills Conference Proceedings, Government Institutes, Inc.,
Rockville, MD.
                                      9-65

-------
                            REFERENCES (continued)
FMC.  1985.  An Introduction to FMC's Enhanced Bioreclamation.  FMS Aquifer
Remediation Systems, Princeton, NJ.

Fitzpatrick, V.F., J.L. Vcelt, K.H. Ource, and C.L. Timmerman.  1984.   In  Situ
Vitrification-A Potential Remedial Action for Hazardous Wastes.  In: 1984
Hazardous Material Spills Conference Proceedings, Government Institutes, Inc.,
Rockville, MD.

Francis, G.Z.  1984.  Landfilled Wastes Treated in Place.  Pollution
Engineering, September,  pp. 37-39.

Freeze, R.A. and J.A. Cherry.  1979.  Groundwater.  Prentice-Hall  Inc.,
Englewood Cliffs, NJ.

Ghiorse, W.C. and D.L. Balkwill.   1983.  Enumeration  and Morphological
Characterization of Bacteria Indigenous to Subsurface Environments.  In:
Developments in Industrial Microbiology.  Vol. 24.  John D. Lucas  Printing
Co., Baltimore, MD.pp. 213-224.

Glaze, W.H., G.R. Peyton, F.Y. Huang, J.L. Burlson, and P.C. Jones.  1980.
Oxidation of Water Supply Refractory Species by Ozone with Ultraviolet
Radiation.  EPA, 600/2-80-110.  USEPA, Cincinnati, OH.

Godfrey, R. (ed.)  1984.  Building Construction Cost  Data.  Robert  Show Means
Company, Inc., Kingston, MA.

Groundwater Decontamination Systems, Inc.  1982.  Report 1.  Experiments  from
September  15 to November 5.  Waldwick, NJ.

Hammer, M.J.  1975.  Water and Wastewater Technology.  John Wiley  and  Sons,
Inc., New York, NY.

Hansch, C.  and A.J. Leo.  1979.  Substituent Constants for Correlation
Analysis in Chemistry and Biology.  John Wiley and Sons, New York.
                                                                        339 pp.

Harvey, R.W., R.L. Smith, and L. George.  1984.  Microbial Distribution and
Heterotrophic Uptake in Contaminated Groundwater, Cape Cod, Massachusetts.
U.S. Geological Survey, Menlo Park, CA.

Hirsch, P., and E. Rades-Rohkhol.   1983.  Microbial Diversity  in a Groundwater
Aquifer in  Northern Germany.  In:  Developments in Industrial  Microbiology.
Vol. 24.   John D. Lucas Printing Co., Baltimore, MD.
                                                                   pp.  183-199.

Hoogendorn, D.  1984.  Review of the Development of Remedial Action Techniques
for  Soil Contamination  in the Netherlands.   In:   1984 Hazardous Material
Spills  Conference Proceedings, Government Institutes, Inc., Rockville,  MD.


                                     9-66

-------
                            REFERENCES  (continued)
Huibregtse, K.R. , and K.H. Kastraan.   1979.   Development  of  a  System  to  Protect
Groundwater Threatened by Hazardous Spills on Land.   USEPA, Industrial
Environmental Research Laboratory, Edison, NJ.

Huibregtse, K.R., J.P. LaFornara, and K.H. Kastman.  1978.   In  Situ
Detoxification of Hazardous Materials Spills in  Soil.  In:  Proceedings of
1978 National Conference on Control of Hazardous Material Spills, April 1-13.
Information Transfer, Inc., Rockville, MD.

Jamison, V.W., R.L. Raymond, and J.O. Hudson.  1976.  Biodegradation of
High-Octane Gasoline.  Proceedings of the Third  International  Biodegradation
Symposium, Applied Science Publishers.

Jhayeri, V. and A.J. Mazzacca.  1983.  Bio-Reclamation of Ground  and
Groundwater by the CDS Process.  Groundwater Decontamination  Systems, Inc.,
Waldwick, NJ.

Jhaveri, V. and A.J. Mazzacca.  1984.  Biodegradation-A  Remedy for
Decontamination of Ground and Groundwater.   In:  Groundwater  Treatment  and
Leachate Control Seminar Proceedings, September  25-26, 1984,  Atlanta, GA.
Chemical Manufacturer's Association, Washington, DC.

Johnson Division, UOP Inc.  1975.  Groundwater and Wells.   A  Reference  Book
for the Water-Well Industry.  St. Paul, MN.

JRB Associates/SAIC.  1985.  Field Demonstration Plan for In-Situ Treatment of
Contaminated Groundwater and Soils, Kelly AFB, TX.   Prepared  for:  USEPA
Hazardous Waste Engineering Research Laboratory, Cincinnati,  OH and  US  Air
Force Engineering and Services Laboratory, Tyndall AFB,  IL.

Kufs, C., P. Rogeshewski, E. Repa, and N. Barkley.   1982.   Alternatives to
Groundwater Pumping for Controlling Hazardous Waste  Leachates.  In:
Management of Uncontrolled Hazardous Waste Sites, Hazardous Materials Control
Research Institute, Silver Spring, MD.  pp.  146-149.

Lee, M.D. and C.H. Ward.  1984.  Reclamation of  Contaminated  Aquifers,
Biological Techniques.  In:  1984 Hazardous  Material  Spills Conference
Proceedings, Government Institutes, Inc., Rockville,  MD.

Litchfield, J.H. and L.C. Clark.  1973.  Bacterial Activity in Groundwaters
Containing Petroleum Products.  Publication  No.  4211.  Americal Petroleum
Institute, Washington, DC.

Lyman, Reehl, and Rosenblatt.  1982.  Handbook of Chemical  Property  Estimation
Methods.  McGraw-Hill Book Company, New York, NY.

Metcalf and Eddy, Inc.  1972. Wastewater Engineering:  Collection, Treatment,
and Disposal.  McGraw-Hill Book Company, New York, NY.
                                     9-67

-------
                            REFERENCES (continued)


Michelsen, D.L., D.A. Wallis, and F. Sebba.   1984.  The Use of a
Microdispersion of Air in Water for In Situ Treatment of Hazardous Organics.
In:  1984 Hazardous Material Spills Conference Proceedings, Government
Institutes, Inc., Rockville, MD.

Minugh, E.M., J.J. Patry, D.A. Keech, and W.R. Leek.  1983.  A Case History:
Cleanup of a Subsurface Leak of Refined Product.  Proceedings of the 1983 Oil
Spill Conference, American Petroleum Institute, Washington, DC.

Munneke, D.M.  1980.  Enzymatic Detoxification of Waste Organophosphate
Pesticides. J. Agric. Food Chem.  Vol. 28, pp. 105-111.

Parsons, F., G. Lage, R. Rice, M. Astraskis,  and R. Nassar.  1982.  Behavior
and Fate of Hazardous Organic Chemicals in Contaminated Groundwater.  For the
Florida Department of Environmental Regulation, Tallahassee, FL.

Paulson, D.L. Jr., R. Honeycutt, H. Lebanon,  and V. Seim.   1984.  Degradation
of High Concentrations of Diazinon in Soil by Parathion Hydrolose.  In:  1984
Hazardous Material Spills Conference Proceedings, Government Institutes, Inc.,
Rockville, MD.

Raymond, R.L., V.W. Jamison, J.O. Hudson, and R.E. Mitchell.   1978.  Field
Application of Subsurface Biodegradation of Gasoline in a  Sand Formation.
Project No. 307-77.  American Petroleum Institute, Washington, DC.

Raymond, R.L., V.W. Jamison, and J.O. Hudson.  1976.  Beneficial Stimulation
of Bacterial Activity in Groundwaters Containing Petroleum Products.  American
Institute of Chemical Engineers Symposium Series.  Vol. 73, No. 166. pp.
390-404.

Rogoshewski, P.J. and D.D. Carstea.  1980.  An Evaluataion of Lime
Precipitation as a Means of Treating Boiler Tube Cleaning  Wastes.  EPA
600-7-80-052.  Hittman Associates.  Prepared  for:  USEPA,  Research Triangle
Park, NC.

Ross, C.A.M.  1980.  Experimental Assessment  of Pollutant  Migration in  the
Unsaturated Zone of the Lower Greensand.  Q.J. Eng. Geol.   London.    Vol. 13.
 pp. 177-187.

Banning, D.E.  1984.  In Situ Treatment.   Project A. USEPA, Cincinnati, OH.

Sawyer, C.N. and P.O. McCarty.  1967.  Chemistry for Sanitary Engineers.  2nd
Ed.  McGraw-Hill Book Company, New York, N.Y.

Schnell, 1985.  Chemical Marketing Reporter.  March 4, 1985.  Schnell
Publishing Company, Inc., New York, NY.
                                     9-68

-------
                            REFERENCES (continued)


SCS Engineers.  1979.  Selected Biodegradation Techniques  for Treatment  and/or
Ultimate Disposal of Organic Materials.  EPA-600/2-79-006.  USEPA, Cincinnati,
OH.

Sims, R.C. and K. Wagner.   1983.   In Situ Treatment Techniques Applicable  to
Large Quantities of Hazardous Waste Contaminated Soils.  In:  Management of
Uncontrolled Hazardous Waste Sites Conference.  Hazardous  Materials  Control
Research Institute, Silver  Spring, MD.

Sojka, S.A.  1984.  Prospects for Genetic Engineering  in Pollution Control:
the Hyde Park Landfill Site.  In:  Groundwater Treatment and Leachate Control
Seminar Proceedings, Atlanta, GA.  Chemical Manufacturer's Association,
Washington, DC.

Srivastava, V.K. and S. Haji-Djafari.  1983.  In Situ  Detoxification of
Hazardous Waste.  In:  1983 Management of Uncontrolled Hazardous Waste Sites
Conference.  Hazardous Materials Control Research Institute, Silver  Spring,
MD.

Stief, K.  1984.  Remedial Action  for Groundwater Protection Case Studies
within the Federal Republic of Germany.  In:  1984 Hazardous Material Spills
Conference Proceedings, Government Institutes, Inc., Rockville, MD.

Sullivan, J.M. D.R. Lynch,  and I.K. Iskandar.  1984.   The  Economics  of Ground
Freezing for Management of Uncontrolled Hazardous Waste Sites.  In:  1984
Hazardous Material Spills Conference Proceedings, Government Institutes, Inc.,
Rockville, MD.

Suflita, J.M. and S.A. Gibson.   1984.  Biodegradation  of Haloaromatic
Substrates in a Shallow Anoxic Groundwater Aquifer.  Preprint submitted  to
Proceedings of the 2nd International Conference on Groundwater Quality.

Texas Research Institute.   1982.  Enhancing Microbial  Degradation of
Underground Gasoline by Increasing Available Oxygen.   Americal Petroleum
Institute, Washington, DC.

Texas Research Institute.   1979.   Underground Movement of  Gasoline on
Groundwater and Enhanced Recovery by Surfactants.  American Petroleum
Institute, Washington, DC.

Tolman, A., A. Ballestes, W. Beck, and G. Enrich.  1978.   Guidance Manual  for
Minimizing Pollution from Waste Disposal Sites.  EPA-600/2-78-142.   USEPA,
Cincinnati, OH.
                                     9-69

-------
                            REFERENCES (continued)
Truett, J.B., R.L. Holberger, and D.E. Banning.   1982.  In Situ Treatment  of
Uncontrolled Hazardous Waste Sites.  In:  Management of Uncontrolled Hazardous
Waste Sites Hazardous Materials Control Research  Institute, Silver  Spring, MD.

USEPA.  1985.  Evaluation of Systems to Accelerate Stabilization of Waste
Piles or Deposits.  EPA Contract No. 68-03-3113,  Office of Research and
Development, Cincinnati, OH.

USEPA.  1984a.  Review of In-Place Treatment Techniques for Contaminated
Surface Soils.  EPA-540/2-84-003a.  Office of Research and Development,
Cincinnati, OH.

USEPA.  1984b.  Case Studies 1-23:  Remedial Response at Hazardous Waste
Sites.  EPA-540/2-84-002b.  Office of Research  and Development, Cincinnati,
OH.

USEPA.  1982.  Guide to the Disposal of Chemically Stabilized  and Solidified
Wastes.  SW-872.  Office of Solid Waste and Emergency Response, Washington,
DC.

USEPA.  1978.  Proceedings of the Fourth Annual Research Symposium Held  at San
Antonio, Texas, March 6-8.  EPA-600/9-78-016.  Washington, DC.  pp. 282-298.

Ventullo, R.M. and R.J. Larson.   1983.  Neterotrophic Activity and
Biodegradation Potential of Microbial Communities in Groundwater.   Presented
at the Fourth Annual Meeting of the Society of  Environmental Toxicology  and
Chemistry, Arlington, VA.

Wetzel, R.S., S.M. Henry, and P.A. Spooner.  1985.  In Situ Treatment  of
Contaminated Groundwater and Soils.  Kelly Air  Force Base, Texas.   In:
Eleventh Annual Research Symposium on Land Disposal, Remedial  Action,
Incineration, and Treatment of Hazardous Waste.   USEPA, Cincinnati, OH.

White, D.C., G.A. Smith, M.J. Gehron, J.H. Parker, R.H. Findlay, R.F.  Martz,
and H.L. Fredrickson.  1983.  In:  Developments in Industrial  Microbiology
Vol.  24.  John D. Lucas Printing  Co., Baltimore,  MD.

Williams, E.G.  1982.  Contaminant Containment  by In Situ Polymerization.  In:
Proceedings of the Second National Symposium on Aquifer Restoration and  Ground
Water Monitoring.  National Water Well Association, Worthington, OH.   pp.
38-44.

Wilson, P.M. and  C.F. Braudner.   1977.  Aqueous Surfactant Solutions Which
Exhibit Ultra-Low Tensions at the Oil-Water Interface.  J. Colloid  Interface
Science.  Vol. 60, No. 3.  pp. 473-479.
                                     9-70

-------
                            REFERENCES (continued)
Wilson, J.T., J.F. McNabb, B.H. Wilson, and M.J. Noonan.   1983.
Biotransformaton of Selected Organic Pollutants in Groundwater.  In:
Developments in Industrial Microbiology.  Vol. 24. John D. Lucas Printing Co.,
Baltimore, MD.

Wilson, J.T.  1984.  Presented at the Fifth Annual Meeting of  the  Society of
Environmental Toxicology and Chemistry, November 4-7, 1984, Arlington, VA.

Yaniga, P.M., W. Smith and R.L. Raymond.  1984.  Biodegradation of Organic
Compounds.  Enhanced Techniques for Diffusion of Oxygen in the Groundwater
System.   In:  Groundwater Treatment and Leachate Control Seminar Proceedings,
Atlanta, GA.  Chemical Manufacturer's Association, Washington, DC.
                                     9-71

-------
                                  SECTION  10

                            DIRECT WASTE TREATMENT
     This section describes direct waste treatment methods  applicable  for
treating aqueous, gaseous, and solid waste streams produced  at hazardous waste
sites.  Many of the treatment methods described  in this  section  are widely
used in industrial waste treatment applications  and  information  on their
design and construction is well described in the literature  cited throughout
the section.  As a result detailed information pertaining to design and
construction has not been included.  Instead, this section emphasizes
applications and limitations of these methods for hazardous  waste treatment.
Section 10.1 describes aqueous waste treatment methods.  Section 10.2
describes methods for solid waste treatment including solids separation and
dewatering methods.  Section 10.3 addresses solidification and stabilization
technologies applicable for liquid and solid wastes.  Commonly used methods
for treating gaseous emissions (with the exception of incineration) are
addressed in Section 10.4  Incineration and other thermal treatment methods
are addressed separately in Section 10.5 since these methods apply to  liquid,
solid, and gaseous wastes.
10.1  Aqueous Waste Treatment


     Aqueous waste streams resulting from the clean up of hazardous waste
sites vary widely with respect to volume, level, and type of contaminants and
level of solids.  The major sources of aqueous wastes include:

     •  Leachate plumes which have been pumped to the surface or collected via
        subsurface drains

     •  Contaminated water generated during dredging operations

     •  Contaminated run-off collected in impoundments or basins

     •  Contaminated water generated from equipment cleanup

     •  Aqueous waste generated from sediment or sludge dewatering

     •  Highly concentrated wastewater streams generated from certain aqueous
        waste treatment processes (e.g., backwash from filtration, concentrate
        from reverse osmosis).
                                     10-1

-------
     Because these waste streams are so diverse in volume, type, and concen-
tration of contaminants, a wide variety of treatment processes will have
application to hazardous waste site cleanup.  This section addresses those
processes which are considered most applicable for hazardous waste site
remediation.  Rarely will any one unit treatment process be sufficient for
aqueous waste treatment.  Therefore, the discussions which follow include
information on unit treatment processes which are frequently used in combina-
tion and any pretreatment requirements which are a prerequisite to effective
use of each treatment process.  The unit treatment processes considered in
this section include:

     •  Activated carbon
     •  Activated sludge
     •  Filtration

     •  Precipitation/flocculation
     •  Sedimentation

     •  Ion exchange
     •  Reverse osmosis

     •  Neutralization
     •  Gravity separation

     •  Air stripping
     •  Chemical oxidation

     •  Chemical reduction.

     Aqueous waste treatment at hazardous waste sites can be accomplished
using one of four general approaches:

     •  On-site treatment using mobile treatment system
     •  On-site construction and operation of treatment systems
     •  Pretreatment followed by discharge to a POTW

     •  Hauling of waste to an off-site treatment facility.

     Mobile treatment systems and systems constructed on-site have broadest
applicability.  Wastewaters discharged to POTWs often require extensive
pretreatment in order for the facility to meet its NPDES permit conditions.
Other factors which determine the feasibility of POTW discharge include
whether the facility has the hydraulic capacity to handle the waste, whether
accepting the waste will result in additional monitoring requirements or
process changes, and the potential for opposition in the community.

     Hauling wastes off-site  for treatment  is limited to all but very small
wastewater volumes.
                                      10-2

-------
     10.1.1  Activated Carbon Treatment
          10.1.1.1  General Description


     The process of adsorption onto activated carbon  involves  contacting  a
waste stream with the carbon, usually by flow through a series of packed  bed
reactors.  The activated carbon selectively adsorbs hazardous  constituents by
a surface attraction phenomenon in which organic molecules are attracted  to
the internal pores of the carbon granules.

     Adsorption depends on the strength of the molecular attraction between
adsorbent and adsorbate, molecular weight, type and characteristic of
adsorbent, electrokinetic charge, pH, and surface area.

     Once the micropore surfaces are saturated with organics,  the carbon  is
"spent" and must either be replaced with virgin carbon or removed, thermally
regenerated, and replaced.  The time to reach "breakthrough" or exhaustion is
the single most critical operating parameter.  Carbon longevity balanced
against influent concentration governs operating economics.

     Most hazardous waste treatment applications involve the use of adsorption
units which contain granular activated carbon (GAG) and operate in a downflow
series mode such as that shown in Figure 10-1 (Brunotts et al., 1983).

     The downflow fixed bed series mode has been found to be generally most
cost-effective and produces the lowest effluent concentrations relative to
other carbon adsorber configurations (e.g., downflow  in parallel, moving  bed,
upflow-expanded).   The units may be connected in parallel to provide increased
hydraulic capacity.


          10.1.1.2  Applications/Limitations


     Activated carbon is a well developed technology which is widely used in
the treatment of hazardous waste streams.  It is especially well suited for
removal of mixed organics from aqueous wastes.  Table 10-1 provides an
indication of the treatability of organics commonly found in groundwater.

     Table 10-2 delineates various factors which influence the applicability
of activated carbon treatment for any given waste (Nalco Chemical Co., 1979).
As carbon adsorption is essentially an electrical interaction phenomenon, the
polarity of the waste compounds will largely determine the effectiveness  of
the adsorption process.  Highly polar molecules cannot be effectively removed
by carbon adsorption.  Another factor to consider in determining the likely
effectiveness of carbon adsorption is aqueous solubility.  The more hydro-
phobic (insoluble) a molecule is, the more readily the compound is adsorbed.
Low solubility humic and fulvic acids which may be present in the groundwater
can sorb to the activated carbon more readily than most waste contaminants and
result in rapid carbon exhaustion.

                                     10-3

-------
                                   FIGURE 10-1.
               TWO-VESSEL GRANULAR CARBON ADSORPTION SYSTEM
            FEED WATER
    REGENERATED/MAKEUP
      ACTIVATED CARBON
         BACKWASH EFFLUENT
          BACK WASH FEED
                         ADSORBER I
                                             ADSORBER 2
REGENERATED/MAKEUP
ACTIVATED CARBON
                                                       BACK WASH EFFLUENT
                                                         BACK WASH FEED
                                                   TREATED EFFLUENT
                         SPENT CAHBON
      VALVE CLOSED

      VALVE OPEN
        Source: USEPA, 1973a
     In addition,  some metals and  inorganic species have  shown excellent to
good adsorption potential, including  antimony, arsenic, bismuth,  chromium,
tin, silver, mercury, cobalt, zirconium,  chlorine, bromine,  and iodine.

     Carbon  adsorption is frequently  used following biological treatment
and/or granular media filtration  in order to reduce the organic and suspended
solids load  on the carbon columns, or to remove refractory organics which
cannot be  biodegraded.  Air  stripping may also be  applied prior to carbon
adsorption in  order to remove a portion of the volatile contaminants, thereby
reducing  the organic load to the  column.  These pretreatment steps all
minimize  carbon regeneration costs.

     The  highest concentration of  solute in the influent  stream that has been
treated on a continuous basis is  10,000 ppm total  organic carbon (TOC), and  a
1 percent  solution is currently considered as the  upper limit (De Renzo,
                                       10-4

-------
                                  TABLE 10-1.

                  FACTORS AFFECTING EQUILIBRIUM ABSORBABILITY
     Compound Adsorbability Favored by:
          Increasing carbon chain length
          Increasing aromaticity
          Decreasing polarity
          Decreasing branching
          Decreasing solubility
          Decreasing degree of dissociation
     Functionality
          Relative adsorbability:  acids > aldehydes > esters > ketones >
          alcohols > glycols when number of carbon atoms is <4
     pH Effects
          Undissociated species are mo're easily adsorbed                    ,
          - low pH favors adsorption of acids (e.g., volatile acids, phenol)
          - high pH favors adsorption of bases (e.g., amines)
          Other compounds:  adsorption can be favored by higher pH
          - Postulated general effect:
                     Partial neutralization of surface acidity reduces
                     hydrogen-bonding of surface groups eliminating steric
                     blockage of micropores
     Temperature
          Increased temperatures can increase rate of adsorption due to
            viscosity and diffusivity effects
          Exothermic adsorption reactions are favored by decreasing
            temperatures, usually a minor effect on equilibrium level
 When the rate is controlled by intraparticle transport, decreasing molecular
 size would result in faster rate, all else being equal.

 This often is the most significant pH effect, so adsorption generally is
 increased with decreasing pH;
Source:  Conway and Ross, 1980.
                                      10-5

-------
                                  TABLE 10-2.

                          CARBON INFLUENT AND EFFLUENT
Organic Compounds
in Groundwater
 Number of
Occurrences
  Influent*
Concentration
    Range
   Carbon
  Effluent*
Concentration
  Achieved
Carbon tetrachloride                 4
Chloroform                           5
DDD                                  1
DDE                                  1
DDT                                  1
CIS-l,2-dichloroethylene             8
Dichloropentadiene                   1
Disopropyl ether                     2
Tertiary methyl-butylether           1
Diisopropyl methyl phosphonate       1
1,3-dichloropropene                  1
Dichlorethyl ether                   1
Dichloroisopropylether               1
Benzene                              2
Acetone                              1
Ethyl acrylate                       1
Trichlorotrifloroethane              1
Methylene chloride                   2
Phenol                               2
Orthochlorophenol                    1
Tetrachloroethylene                 10
Trichloroethylene                   15
1,1,1-trichloroethane                6
Vinylidiene chloride                 2
Toluene                              1
Xylene                               3
             130 ug/1-10 mg/1
             20 ug/1-3.4 mg/1
                       1 ug/1
                       1 ug/1
                      4 ug/11
                5 ug/1-4 mg/1
                     450 ug/1
                   20-34 ug/1
                      33 ug/1
                   1,250 ug/1
                      10 ug/1
                     1.1 mg/1
                     0.8 mg/1
                  0.4-11 mg/1
                  10-100 ug/1
                     200 mg/1
                       6 mg/1
                    1-21 mg/1
                      63 mg/1
                     100 mg/1
               5 ug/1-70 mg/1
                 5 ug-16 mg/1
              60 ug/1-25 mg/1
                5 ug/1-4 mg/1
                     5-7 mg/1
                  0.2-10 mg/1
                    <0
                    <0
     .05
     .05
     .05
     ug/1
     ug/1
      g/1
     ug/1
     ug/1
  <1 ug/1
 <10 ug/1
  <1 ug/1
<5.0 ug/1
 <50 ug/1
  <1 ug/1
  <1 ug/1
  <1 ug/1
  <1 ug/1
 <10 mg/1
  <1 mg/1
 <10 ug/1
<100 ug/1
  <1 ug/1
  <1 mg/1
     ug/1
     ug/1
     ug/1
     ug/1
     ug/1
     ug/1
*Analyses conducted by Calgon Carbon Corporation conformed to published U.S.
 EPA protocol methods.  Tests in the field were conducted using available
 analytical methods.

Source:  O'Brien and Fisher, 1983
                                    10-6

-------
1978).  Pretreatment is required  for  oil  and  grease  and  suspended solids.
Concentrations of oil and grease  in the  influent  should  be  limited to 10 ppm.
Suspended solids should be  less than  50  ppm for upflow systems,  while downflow
systems can handle much higher solids  loadings.


          10.1.1.3  Design  Considerations


     The phenomenon of adsorption is  extremely complex and  not mathematically
predictable.  To accurately predict performance,  longevity  and operating
economics, field pilot plant studies  are  necessary.

     In order to conduct an initial estimate  of carbon column  sizing,  the
following data need to be established  during  pilot plant  testing:

     •  Hydraulic retention time  (hours)
     •  Flow (gallons/minute)
     •  Hyraulic capacity of the  carbon  (gallons  waste/pound carbon)
     •  Collected volume of treated waste  at  breakthrough (gallons)
     •  Carbon density (pounds carbon/cubic foot).

     In the above data list, the  term  "breakthrough"  refers to the moment  when
the concentration of solute being treated  first starts to rise in the carbon
unit effluent.  The term "exhaustion"  refers  to the moment  when  the
concentration of solute being treated  is  the  same in  both effluent and
influent.
          10.1.1.4  Technology Selection/Evaluation


     Activated carbon is an effective and reliable means of  removing  low
solubility organics.  It is suitable for treating a  wide range  of  organics
over a broad concentration range.  It is not particularly  sensitive to  changes
in concentrations or flow rate and, unlike biological  treatment,  is not
adversely affected by toxics.  However, it is quite  sensitive to  suspended
solids and oil and grease concentrations.

     Activated carbon is easily implemented into more  complex treatment sys-
tems.  The process is well suited to mobile treatment  systems as well as to
on-site construction.  Space requirements are small, start-up and  shut-down
are rapid, and there are numerous contractors who are  experienced  in  operating
mobile units.

     The EPA's Mobile Physical/Chemical Treatment System includes  three carbon
columns that can be operated either in series or in  parallel and are  designed
for a hydraulic loading of 200 gpm with a 27 minute  contact  time.  This
contact time has been found to be adequate for many  hazardous waste streams.


                                     10-7

-------
However,  longer contact  times  can be  provided by  reducing  the  hydraulic flow
rate (Ghassemi, Yu, and  Quinlivan,  1981).

     Use  of several carbon  adsorption columns at  a  site  can  provide  con-
siderable flexibility.   Various  columns  can  be  arranged  in series  to increase
service life between regeneration of  the  lead bed or  in  parallel  for maximum
hydraulic capacity.  The piping  arrangement  would allow  for  one  or more beds
to be regenerated while  the other columns  remain  in  service.

     The  most obvious maintenance consideration associated with  activated
carbon treatment is the  regeneration  of  spent carbon  for reuse.  Regeneration
must be performed for each  column at  the  conclusion  of its bed-life  so  the
spent carbon may be restored as  close as  possible to  its original  condition
for reuse; otherwise, the carbon must  be  disposed of.  Other operation  and
maintenance requirements of activated  carbon technology  are minimal  if
appropriate automatic controls have been  installed.

     It is recommended that the  thermal destruction  properties of  waste
chemicals be determined  prior  to selection of activated  carbon treatment
technology, since any chemicals  sorbed to  activated  carbon must eventually  be
destroyed in a carbon regeneration  furnace.  Therefore,  of crucial importance
to the selection of activated  carbon  treatment  is whether  the  sorbed waste
material  can be effectively destroyed  in  the regeneration  furnace; otherwise,
upon introduction to the  furnace, they will  become  air pollutants.

     The  biggest limitation of the  activated carbon  process  is the high
capital and operating cost.  As  described  previously, the  operating  costs can
be substantially reduced by pretreatment  of  the waste using  biological
treatment or air stripping.
          10.1.1.5  Costs
     The cost of activated carbon units depends  on  the  size  of  the  contact
unit which is influenced by the concentrations of the target  and  non-target
organic compounds  in the waste stream  and  the desired level  of  target
compounds in the effluent.  Table 10-3 presents  construction, operation and
maintenance  costs  for cylindrical pressurized,  downflow steel  contactors
based on a nominal  detention time of 17.5 minutes and a carbon  loading  rate  of
5gpm/ft .  The construction costs include housing,  concrete  foundation, and
all the necessary  pipes, valves, and nozzles for operating the  unit  plus the
initial change of  carbon.  The operation and maintenance cost  include  the
electricity and assume carbon replacement once a year.   However,  systems for
unloading spent carbon and loading fresh carbon  are not included.

     There are a number of manufacturers such as Calgon Carbon  Corporation who
market mobile activated carbon treatement  systems.   For example,  Calgon Carbon
Corporation has a  trailer-mounted carbon adsorption treatment unit  that can  be
shipped to a treatment location within 24 to 48  hours.   The  system  can  be
configured wih either single or multiple pre-piped  adsorber vessels.   It can
handle flow of up  to 200 gpm.  The following describes  costs  associated with a

                                     10-8

-------
                                  Table 10-3
    GENERAL COST DATA FOR VARIOUS SIZES OF ACTIVATED CARBON CONTACT UNITS
 Capacity (gpra)     Column        Column    Housing  Construction        O&M
                Diameter (ft)  Length (ft) Area (ft )   Costs*    Costs  ($/yr)*
1.7
17
70
175
350
0.67
2
4
6.5
9
5
5
5
5
5
60
150
300
375
450
12,320
23,776
42,425
64,000
93,822
1,690
2,315
4,800
8,110
12,540

*Updated from 1979 to 1984 dollars using third quarter Marshall and Swift
 Equipment Index.

Source:  Adapted from Hansen, Gumerman, and Gulp, 1979.
                                      10-9

-------
mobile system consisting of two 10-foot diameter,  10-foot high,  skid mounted
vessels capable of handling up to 200 gpm (Calgon  Corp, undated):

     Delivery, supervision of installation             $25,000
     and startup, tests to conduct re-
     activation of carbon, dismantling and
     removal of system (including freight to
     and from the site)

     Delivery and removal of one truck-               $15,200
     load of carbon (2,000 Ibs)

     (Two truckloads required for a
     two-vessel system) - Rental fee (per month)      $5,000/month

     Calgon Carbon Corporation will take spent carbon back  for reactivation.
Otherwise, disposal costs for spent carbon must be added.
     10.1.2  Biological Treatment


          10.1.2.1  General Description


     The function of biological treatment is to remove organic matter  from  the
waste stream through microbial degradation.  The most prevalent  form of
biological treatment is aerobic, i.e., in the presence of oxygen.   A number of
biological treatment processes exist which may be  applicable  to  treatment of
aqueous wastes from hazardous waste sites, including conventional  activated
sludge, various modifications of the activated sludge process  including  pure
oxygen activated sludge, extended aeration, and contact  stabilization,  and
fixed film systems which include rotating biologial discs,  and trickling
filters.

     In the conventional activated sludge process, aqueous  waste flows  into an
aeration basin where it is aerated for several hours.  During  this time, a
suspended active microbial population (maintained  by recycling sludge)
aerobically degrades organic matter in the stream  along  with  producing  new
cells.  A simplified equation for this process is  shown  below:

          Organics + 02       >      CO- + H~0 + new cells

The new cells produced during aeration form a sludge which  is  settled  out  in a
clarifier.  A portion of the settled sludge is recycled  to  the aeration  basin
to maintain the microbial population while the remaining sludge  is wasted,
i.e., it undergoes volume reduction and disposal.  Clarified  water flows to
disposal or further processing.
                                      10-10

-------
     In the pure oxygen activated  sludge  process,  oxygen  or  oxygen-enriched
air is used instead of air to  increase  the  transfer  of  oxygen.   Extended
aeration involves longer detention times  than  conventional activated  sludge
and relies on a higher population  of microorganisms  to  degrade wastes.
Contact stabilization involves only short contact  of  the  aqueous wastes and
suspended microbial solids, with subsequent  settling  of sludge and  treatment
of the sludge to remove sorbed organics.  Fixed  film  systems  involve  contact
of the aqueous waste stream with microorganisms  attached  to  some inert medium
such as rock or specially designed plastic material.  The original  trickling
filter consisted of a bed of rocks over which  the  contaminated water  was
sprayed.  The microbes forming a slime  layer on  the  rocks, would metabolize
the organics, while oxygen was provided as  air moved  countercurrent from  the
water flow (Canter and Knox, 1985).

     Biological towers are a modification of the trickling filter.  The medium
(e.g., of polyvinyl chloride (PVC), polyethylene,  polystyrene, or redwood) is
stacked into towers which typically reach 16 to  20 ft.  The  contaminated  water
is sprayed across the top and, as  it moves downward,  air  is  pulled upward
through the tower.  A slime layer  of microorganisms  forms on  the media and
removes the organic contaminants as the water  flows over  the  slime layer.

     A rotating biological contactor (RBC) consists of  a  series of rotating
discs, connected by a shaft, set in a basin or trough.  The contaminated  water
passes through the basin where the microorganisms, attached  to the discs,
metabolize the organics present in  the water.  Approximately  40% of the disc's
surface area is submerged.  This allows the slime  layer to alternately come in
contact with the contaminated water and the air where oxygen  is provided  to
the microorganisms (Canter and Knox, 1985).


          10.1.2.2  Applications/Limitations


     There is considerable flexibility  in biological  treatment because of the
variety of available processes and  adaptability of the microorganisms them-
selves.  Many organic chemicals are considered biodegradable, although the
relative ease of biodegradation varies widely.  Several generalizations can be
made with regard to the ease of treatability of organics  by aerobic biological
treatment:

     •  Unsubstituted nonaromatics or cyclic hydrocarbons are preferred over
        unsubstituted aromatics

     •  Materials with unsaturated bonds such as alkenes  are  preferred over
        materials with saturated bonds

     •  Soluble organics are usually more readily  degraded than insoluble
        materials.   Biological treatment is more efficient in removing
        dissolved or colloidal materials,  which are more  readily attacked by
        enzymes.   This is not the case, however, for  fixed film treatment
        systems which preferentially treat suspended matter
                                     10-11

-------
     •  The presence of functional groups affects biodegradability.  Alcohols,
        aldehydes, acids, esters, amides, and amino acids are more degradable
        than corresponding alkanes, olefins, ketones, dicarboxylic acids,
        nitriles, and chloroalkanes

     •  Halogen-substituted compounds are the most refractory to
        biodegradation; chlorinated alphatics are generally more refractory
        than the corresponding aromatics, although the number of halogens and
        their position is also significant in determining degradation.

     •  Nitro-substituted compounds are also difficult to degrade  although
        they are generally less refractory than the halogen-substituted
        compounds.

     Although there are a number of compounds which are considered to be
relatively resistant to biological treatment, it is recommended in practice
that the treatability of waste be determined through laboratory Biological
Oxygen Demand (BOD ) tests on a case-by-case basis.  Section 9.1 provides
further discussion of the degradability of organics.

     Despite the fact that industrial type wastes may be refractory to bio-
logical treatment, microorganisms can be acclimated to degrade many compounds
that are initially refractory.  Similarly, while heavy metals are  inhibitory
to biological treatment, the biomass can also be acclimated, within limits, to
tolerate elevated concentrations of metals.

     In terms of the variety of biological treatment processes available,
Table 10-4 presents the applications and limitations of each.  The completely
mixed activated sludge process is the most widely used for treatment of
aqueous wastes with relatively high organic loads.  However, the high purity
oxygen system has advantages for hazardous waste site remediation.

     In addition, a number of other parameters may influence the performance
of the biological treatment system, such as concentration of suspended solids,
oil and grease, organic load variations, and temperature.  Table 10-5 lists
parameters that may limit system performance, limiting concentrations, and the
type of pretreatment steps required prior to biological treatment.


          10.1.2.3  Design Considerations


     Design of the activated sludge or  fixed-film systems for a particular
application can be achieved best by first representing the system  as a
mathematical model, and then determining the necessary coefficients by running
laboratory or pilot tests.
                                     10-12

-------
                                  TABLE 10-4.

      SUMMARY OF APPLICATIONS/LIMITATIONS FOR BIOLOGICAL TREATMENT PROCESS
PROCESS
APPLICATIONS/LIMITATIONS
Conventional
Completely-mixed
Conventional

Extended Aeration
Contact Stabilization

Pure Oxygen



Trickling Filters



Rotating Biological Disc
Applicable to low strength wastes; subject to
shock loads

Resistant to shock loads
Requires low organic load and long detention
times; low volume of sludge; available as package
plant

Not suitable for soluble BOD

Suitable for high strength wastes;
low sludge volume;
reduced aeration tank volume

More effective for removal of colloidal and
suspended BOD; used primarily as a roughing
filter

Can handle large flow variations and high organic
shock loads; modular construction provides
flexibility to meet increases or decreased
treatment needs.
                                     10-13

-------
                                 TABLE   10-5

        CONCENTRATION OF  POLLUTANTS THAT MAKE  PREBIOLOGICAL
                     OR PRIMARY TREATMENTS DESIRABLE
Pollutant or
System Condition
Limiting
Concentration
                                                     Kind  of Pretreatment
Suspended solids


Oil or grease


Toxic ions

  Pb
  Cr

pH

Alkalinity



Acidity

Organic load variation

Sulfides


Phenols


Ammonia



Dissolved salts

Temperature
                            >50-125 mg/1
                            flotation, lagooning

                            >35-50 mg/1
                            ฃ0.1 mg/1
                            <1 mg/1
                            P mg/1
                            <_ 10 mg/1

                            <6, >9

                            0.5 Ib alkalinity
                            as CaCO /Ib BOD
                            removed

                            Free mineral acidity
                            MOO mg/1


                            >70-300 mg/1


                            >1.6 g/1



                            >10-16 g/1

                            13-38'C in reactor
                        Sedimentation,
                        Skimming tank or
                        separator

                        precipitation or ion
                        exchange
                        Neutralization

                        Neutralization for
                        excessive alkalinity
                        Neutralization

                        Equalization

                        Precipitation or
                        stripping with recovery

                        Extraction, adsorption,
                        internal dilution

                        Dilution, ion exchange,
                        pH adjustment and
                        stripping

                        Dilution, ion exchange

                        Cooling, steam addition
Source:   Conway  and Ross, 1980
                                    10-14

-------
     The  following models have been  found  to  be  reliable  for  designing
biological treatment  systems  for waste  streams containing priority pollutants
(Cantor and Knox, 1985).

     Activated Sludge:

                    FS./X
               V =
                   U    S. - 1C
                    max   i    B
                   S. - S
                    i     e
     Biological Tower and Rotating Biological  Contactor:
                    FS.
                      i
                    U    S.
                     max  i  - K,,
                                B
                    S. - S
                     i    e
                                           •j
where     V  = volume of aeration tank ( f t )
          F  = flow rate (ft /day)
          X  = mixed liquor volatile solids (mg/1)
          S. = influent BOD, COD, TOC, or  specific organics  (mg/1)
          S1 = effluent BOD, COD, TOC, or  specific organics  (mg/1)
U    and  K  = biokinetic constants (day   )
          A  = surface area of biological  tower or rotating  biological
               contactor ( f t )
     The biokinetic constants are determined by conducting  laboratory  or  pilot
plant studies.  After the biokinetic constants are determined,  the  required
volume of aeration tank or the required surface area  for  a  biological  tower  or
rotating biological contactor can be determined for any flow  rate,  influent
concentration of BOD, COD, TOC, or specific organic,  and  a  required effluent
concentration of BOD, COD, TOC, or specific organic.


          10.1.2.4  Technology Selection/Evaluation


     Biological treatment has not been as widely used  in  hazardous  waste  site
remediation as activated carbon, filtration and precipitation/flocculation.
However, the process is well established for treating  a wide  variety of
organic contaminants.  Kincannon and Stove as reported by Canter  and Knox
(1985) have demonstrated the effectiveness of activated sludge  for  treating
priority pollutants.  The results shown in Table 10-6  indicate  that activated
sludge was effective for all groups of contaminants tested  except for
halogenated hydrocarbons.
                                     10-15

-------
                                  TABLE 10-6.

                     REMOVAL MECHANISMS OF TOXIC ORGANICS
          Compound
                                         Percept Treatment Achieved
Stripping
Sorption
Biological
Nitrogen Compounds
     Acrylonitrile
Phenols
     Phenol
     2,4-DNP
     2,4-DCP
     PGP
Aromatics
     1,2-DCB
     1,3-DCB
     Nitrobenzene
     Benzene
     Toluene
     Ethylbenzene
Halogenated Hydrocarbons
     Methylene Chloride
     1,2-DCE
     1,1,1-TCE
     1,1,2,2,-TCE
     1,2DCP
     TCE
     Chloroform
     Carbon Tetrachloride
Oxygenated Compounds
     Acroleiln
Polynuclear Aromatics
     Phenanthrene
     Napthalene
Phthalates
     Bis(2-Ethylhexyl)
Other
     Ehtyl Acetate
   21.7
    2.0
    5.1
    5.2

    8.0
   99.5
  100.0
   93.5
   99.9
   65.1
   19.0
   33.0
    1.0
                  0.58
   0.02
   0.19

  91.7
   0.50
   0.83
   1.19
   1.38
                                99.9
                                99.9
                                99.
                                95,
   97.3

   78.2

   97.8
   97.9
   94.9
   94.6
   33.8
   78.8
   64.9

   99.9

   98.2
   98.6

   76.9

   98.8
Source:  Canter and Knox, 1985 as cited by Kincannon and Stover, undated,
                                     10-16

-------
     Although biological  treatment  can  effectively  treat  a  wide  range  of
organics, it has several  drawbacks  for  hazardous waste  site applications.   The
reliability of the process can be adversely  affected by "shock"  loads  of
toxics.  Start-up time can be slow  if the  organisms need  to be  acclimated  to
the wastes and the detention time can be long  for complex wastes.   However,
the existence of cultures which have been  previously adapted to  hazardous
wastes can dramatically decrease start-up  and  detention time.

     There are a number of cleanup  contractors who  have used biological  treat-
ment as part of a mobile  treatment  system.   The high purity oxygen  treatment
process is well suited for mobile treatment  applications  because the high
oxygen efficiency enables use of smaller reactors,  shorter  detention time,  and
reduced power consumptions relative to  other activated  sludge processes.  A
hazard associated with the high purity  oxygen  process is  that the presence  of
low flash-point compounds can present a potential fire  hazard.   However, the
system is equipped with hydrocarbon analyzers  and control systems that
deactivate the system when dangerously  high  concentrations  of volatiles  are
detected (Ghassemi, Yu, and Quinlivan,  1981).  Loss of  volatile  organics from
other biological treatment processes can also  pose  some localized air
pollution and a health hazard to field  personnel.

     Rotating biological  contactors also have  advantages  for hazardous waste
site treatment.  The units are compact, and  they can handle large flow
variations and high organic shock loads, and they do not  require use of
aeration equipment.

     Sludge produced in biological waste treatment  may  be a hazardous  waste
itself due to the sorption and concentration of toxic and hazardous  compounds
contained in the wastewater.  If the sludge  is hazardous, it must be disposed
in a RCRA-approved manner.  If the  sludge  is not hazardous,  disposal should
conform with State sludge disposal guidelines.
     10.1.2.5  Costs
     Costs for various sizes of activated sludge units  are  presented  in  Table
10-7.  The costs for these units assume a detention time of 3 hours,  and use
of aeration basins, air supply equipment, piping, and a blower building.
Clarifier and recycle pumps are not included.  The basins are sized to the  50
percent recycle flow.  The influent biological oxygen demand (BOD) is assumed
to be no greater than 130 ppm and the effluent BOD is assumed to .be 40 ppm.

     The operation and maintenance costs assume that the hydraulic head  loss
through the aeration tank is negligible.  Sludge wasting and pumping  energy
are not included.

     Union Carbide manufactures a high purity oxygen activated sludge system
(UNOX) suitable for mobile system applications.  The mobile UNOX systems have
a hydraulic capacity of 5 to 40 gpm, are contained within 40 foot van
trailers, and include an external clarifier.  The oxygen required is  also


                                     10-17

-------
                                  TABLE 10-7.

   GENERAL COST DATA FOR VARIOUS SIZES OF ACTIVATED SLUDGE TREATMENT UNITS

Capacity (gpm)

70
140
350
694
Construction
Costs ($)*
78,500
85,600
107,000
160,000
O&M Costs ($/year)*

4,300
6,400
10,000
15,700
*Updated from 1978 to 1984 dollars using third quarter Marshall and Swift
Equipment Index.

Source:  Adapted from USEPA, 1980.
supplied by Union Carbide.  The customer is expected to provide installation
labor, operating manpower, analytical support, and utilities.  A typical
installation requires three to four days (Ghassemi, Yu, and Quinlivan,  1981).

     The mobile UNOX system can be either rented or purchased from the  Union
Carbide Corporation.  The estimated rental costs are as follows:
        $6,540 for the checkout and refurbishment of equipment to make  it
        operational

        $550/day for on-site service including engineering consultation on
        program planning and execution

        $9/day rental of equipment

        Transportation charges to get the equipment  from  the manufacturer to
        the site of operation and back again.
The purchase price for the UNOX mobile unit is between $260,000 and $330,000
(Ghassemi, Yu, and Quinlivan, 1981, updated using 1984 third quarter Marshall
Swift Index).
                                     10-18

-------
      10.1.3   Filtration
           10.1.3.1  General Description
     Filtration is a physical process  whereby suspended  solids  are removed
from solution by forcing the fluid  through a porous medium.   Granular media
filtration  is typically used for  treating aqueous waste  streams.   The filter
media consists of a bed of granular  particles (typically  sand or  sand with
anthracite  or coal) (Figure 10-2).   The  bed is contained  within a basin and is
supported by an underdrain system which  allows the filtered  liquid to be drawn
off while retaining the filter media in  place.  As water  laden  with suspended
solids passes through the bed of  filter  medium, the particles become trapped
on top of and within the bed.  This  either reduces the filtration rate at a
constant pressure or increases the  amount of pressure needed  to force the
water through the filter.  In order  to prevent plugging,  the  filter is
                                  FIGURE 10-2.
                             TYPICAL FILTRATION BED
                BACKWASH
                DRAIN
                                 HIGH HEAD
                                                       RAW FEED
BACKWASH
TROUGH r—
                                                   SINGLE OR
                                                   MULTIPLE LAYER
                                                   FILTER MEDIUM
                                                         BACKWASH
                                 UNDER DRAIN
                                                          EFFLUENT
               Source: Ghassemi, Yu, and Quinlivan, 1981
                                       10-19

-------
backflushed at high velocity  to dislodge  the  particles.   The  backwash  water
contains high concentrations  of solids  and  requires  further treatment
(De Renzo, 1978).


          10.1.3.2  Applications/Limitations


     Filters find economic application  in handling streams containing  less
than 100 to 200 mg/liter  suspended  solids,  depending  on  the required effluent
level.  Increased suspended solids  loading  will  reduce run lengths, and
require excessively frequent  backwash   (De  Renzo, 1978).  The suspended  solids
concentration of the  filtered liquid depends  a great  deal on  particle  size
distribution, but typically,  granular media filters  are  capable  of  producing  a
filtered liquid with  a  suspended  solids concentration as  low  as  1 to 10  mg/1.
Large flow variations will deleteriously  affect  effluent  quality.

     Often, granular media filters  are  preceded  by sedimentation to reduce  the
suspended solids load on  the  filter (De Renzo, 1978).  Granular  media
filtration is also frequently installed ahead of biological or activated
carbon treatment units  to reduce  the suspended solids load and in the  case  of
activated carbon to minimize  plugging of  the  carbon  columns (De  Renzo, 1978).

     The granular media filtration  process  is only marginally effective  in
treating colloidal size particles.  In  many cases, these  particles  can be made
larger by flocculation  although this will generally  reduce run lengths.  In
cases where it is not possible to flocculate  such particles (as  in  the case of
many oil/water emulsions), more advanced  techniques  such  as ultrafiltration
may be appropriate (De Renzo, 1978).


          10.1.3.3  Design Considerations


     The composition  and  sizing of  the  filtration bed is  an important  design
consideration.  Beds  of 4 feet or less  composed  of 0.5 mm sand and  0.9 mm
anthracite are frequently used.  However  deep-bed filters are also  available.
It is recommended that  pilot  plant  studies  be conducted  to determine optimum
size and combination of filter material.

     A filter bed can function properly only  if  the  backwashing  system
effectively cleans the material from the  filter.  Methods which  can be used
for backwashing include water backwash  only,  water backwash with auxiliary
surface water wash, water wash proceeded  by air  scour, and simultaneous  air
and water wash.

     The duration of  the backwash is about  20 min per cycle.   Backwash water,
which amounts to 1 to 5 percent of  the  total  flow, can be routed to a  primary
clarifier often via a storage vessel to allow flow equalization. Several
filters are used in parallel  to allow continuous processing during
backwashing; the backwash cycle usually is  automated.  Other  processes must be
sized to handle this  recycle  flow.

                                     10-20

-------
           10.1.3.4  Technology/Selection  Evaluation


     Filtration  is a reliable  and  effective means  of  removing  low levels of
solids from wastes provided  the  solids  content  does not vary greatly and the
filter is  backwashed at appropriate  intervals.

     Filtration  equipment  is relatively simple,  readily available in a wide
range of sizes,  and easy to  operate  and control.   Filtration is  also easily
integrated with  other treatment  steps.

     Because of  its small  space  requirements  and relatively simple  operation,
filtration is well suited  to mobile  treatment systems  as  well  as  on-site
construction.  There is extensive  experience  with  the  operation  of
granular-media filters at  hazardous  waste  sites.

     The EPA physical/chemical treatment  system which  has been in operation
for more than 9  years incorporates 3 "dual" media  (sand-anthracite)  filters
connected  in parallel in its treatment  train.   The filters are designed for a
maximum hydraulic loading  of 7 gpm/ft   or  67  gpm (Ghassemi, Yu,  and  Quinlivan,
1981).  There are also a number  of manufacturers of package plant systems
suitable for being trailer mounted and  a number of cleanup contractors who
operate mobile treatment systems which  include  granular media  filters as a
part of the treatment process.

     The most obvious maintenance  consideration with granular  media  filtration
is handling of the backwash.   The backwash will generally contain high
concentrations of contaminants and require subsequent  treatment.


           10.1.3.5  Costs
     Figure 10-3 shows construction and operating  costs  for  filtration
assuming a filtration rate of 5 gpm/ft .  A minimimum of 4 filters  are  assumed
to provide flexibility of operation.  Capital costs  include  filter  structures,
backwash and surface wash systems, media and polymer feeding.  Costs of
effluent filtering and pumping are not included.   Power  costs  are based on
each filter backwashing once per  12 hours (Gulp, Wesner  and  Gulp, 1978).

     The construction costs assume a filtration rate of  2 gpm/square foot and
76 in filter media (silica sand and anthracite coal mixture) depths inside  two
open-topped cylindrical steel tanks.  The construction costs also include
chemical feed systems (alum, soda ash, polymer, and chlorine), pumps,
pre-filter contact basin, a backwash storage basin, building,  and all
necessary piping.  The operation  and maintenance costs include all building
utilities, process utilities, routine maintenance  costs, and replacement of
filter media lost through normal backwash operations (Hansen, Gumerman,  and
Gulp, 1979).  The operation and maintenance costs  do not include treatment
chemicals because usage rates of  these chemicals would vary  considerably
                                     10-21

-------
                 FIGURE 10-3. COST OF EFFLUENT FILTRATION*
       0
       o
5,000
4,000
3,000
2,000
1,000
500
400
300
200
100













— 	 "

	














	


• -~













^x
^


, "












^f




^^




















































-











,





^











<

















/


s
^s
*^











X


,x
^












/



















.














s


-













/



-













'



'












>




**



























o
01
T3
I
,00 |
X
50 9.
40
20
in
                                                                Capital Costs  	
                                                                O&M Costs   	
                             5  6 7 8 9 10
                                              30 40 50
                               Plant Capacity, MOD
          •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
           (multiply value shown on this figure by 1.908)
          Source: Gulp, Wesner & Gulp, 1978
depending on  the wastestream characteristics.   Unit costs for treatment
chemicals are  presented  in Section 9.2.   Costs for various sizes of  package
neutralization,  precipitation, and filtration  plants are presented in  Table
10-8.
      10.1.4   Precipitation/Flocculation
           10.1.4.1  General Description


     Precipitation is a physiochemical  process whereby some  or  all of a
substance  in solution is transformed  into a solid phase.   It  is based on
alteration of the chemical equilibrium  relationships affecting  the solubility
of  inorganic species.  Removal of metals as hydroxides or  sulfides is the most
common  precipitation application  in  wastewater treatment.  Generally, lime or
sodium  sulfide is added to the wastewater in a rapid mixing  tank along with
flocculating agents (described below).   The wastewater flows  to a flocculation
chamber in which adequate mixing  and  retention time is provided for
agglomeration of precipitate  particles.  Agglomerated particles are separated
from the liquid phase by settling  in a  sedimentation chamber,  and/or by other
                                       10-22

-------
                                  TABLE  10-8.

            GENERAL COST DATA FOR VARIOUS  SIZES OF NEUTRALIZATION,
                     PRECIPITATION, AND  FILTRATION UNITS
Plant Capacity (gpm)            Construction               Operation  and
                                Cost ($)*                Maintenance  ($/year)*
4
8
40
80
140
225
280
560
78,770
89,610
126,520
179,300
253,610
293,670
396,960
619,940
20,730
21,390
26,550
47,960
56,700
57,560
61,860
92,000

*Updated from 1979 to 1984 dollars using third quarter Marshall and Swift
Index.

Source:  Adapted from Hansen, Gumerman, and Gulp, 1979.

physical processes such as filtration.  Figure 10-4 illustrates a typical
configuration for precipitation flocculation and sedimentation.

     Although precipitation of metals is governed by the solubility product of
ionic species, in actual practice, effluent concentrations equal to the
solubility product are rarely achieved.  Usually, the amount of lime added is
about three times the stoichiometric amount that would be added to reduce
solubility due to the common ion effect.  Figure 10-5 gives solubilities of
various metal hydroxides and sulfides at various pH levels.   The metal
sulfides have significantly lower solubility than their hydroxide counterparts
and more complete precipitation is achieved.  Metal sulfides are also  stable
over a broad pH range.  Many metal hydroxides, on the other hand, are  stable
only over a narrow pH range; metals reach a minimum solubility at a specific
pH, but further addition of lime causes the metal to become soluble again.
Therefore,  dosages of lime need to be accurately controlled.  This may be
particularly challenging when working with aqueous wastes from waste disposal
sites where wide variations in flow rates and quantities of metals are to be
expected.  The stabilities of metal carbonates are also quite dependent on pH.
                                     10-23

-------
                                    FIGURE 10-4.
    REPRESENTATIVE CONFIGURATION EMPLOYING PRECIPITATION, FLOCCULATION,
                               AND SEDIMENTATION
              PRECIPITATION
                                 FLOCCULATtON
   PRECIPITATING CHEMICALS—,

 FLOCCULATING AGENTS
 INLET LIQUID STREAM-
      AFTER THE ADDITION OF PRECIPITATING   BY SLOW AND GENTLE MIXING THE
      CHEMICALS THE PRECIPITATION REACTION  PRECIPITATED PARTICLES. AIDED BY
      COMMENCES TO FORM VERY SMALL PAR-   THE FLOCCULATING AGENTS, COLLIDE,
      TICLES CALLED PRECIPITATION NUCLEI.    AGGLOMERATE. AND GROW INTO LARGER
      THE FLOCCULATING AGENTS ALLOW THESE  SETTLEABLE PARTICLES
      PARTICLES TO AGGLOMERATE
-ป•
RA
1
•~.irx_n
(
/

c
c
IP
J
^
ki
c
c
LP
j
^
HQ
P i

r>ID MIX TANK FLOCCULATION CHAMBER
   SEDIMENTATION
                                                                          OUTLET LIQUID
                                                                            STREAM
     SEDIMENTATION BASIN
THE SETTLEABLE PARTICLES PRODUCED
BY THE FLOCCULATION STEP ARE SETTLED,
COLLECTED AND PERIODICALLY REMOVED
     Source: De Renzo, 1978
      Flocculation  is used to  describe the  process by which small, unsettleable
particles suspended  in a liquid  medium are  made to agglomerate into  larger,
more  settleable  particles.  The  mechanisms  by which flocculation occurs
involve surface  chemistry and  particle change phenomena.   In simple  terms,
these various phenomena can be grouped into two sequential mechanisms  (Kiang
and Metry, 1982):

      •  chemically induced destabilization  of the requisite surface-related
         forces,  thus allowing  particles to  stick together  when they  touch and

      •  chemical bridging and  physical enmeshment between  the now nonrepelling
         particles,  allowing for  the formation of large  particles.

      Flocculation  involves three basic steps:

      •  addition of  flocculating agent to  the waste stream

      •  rapid mixing to disperse the flocculating agent

      •  slow and gently mixing to allow for contact between small particles.

      Typically, chemicals used to cause flocculation include alum, lime,
various iron salts  (ferric chloride, ferrous sulfate) and  organic flocculating
agents, often referred to as "polyelectrolytes."  These materials generally
consist of long-chain, water-soluble polymers such as polyacrylamides.   They
are used either  in  conjunction with the inorganic flocculants,  such  as  alum,
or as the primary  flocculating agent.   A polyelectrole may be termed cationic,
anionic or ampholytic depending  upon the type of ionizable groups; or nonionic
                                        10-24

-------
                               FIGURE 10-5.

           SOLUBILITY OF METAL HYDROXIDES AND SULFIDES
o>
S
•o
Q
"6

•I
       10ฐ
      10-2
      10'
       ,-6
      10"8 '
     10'10 '
         0    1    2    3    4    5    6   7    8    9    10   11   12   13   14

                                        pH


 Source: Ghassemi, Yu, and Quinlivan, 1981
                                  10-25

-------
if it contains no ionizable groups.  The  range of physical/chemical
characteristics (e.g., density, viscosity,  toxicity  and molecular  weight)  of
the several thousand available polymers is  extremely broad.

     The inorganic flocculants, such as alum, lime or  iron  salts,  make  use of
precipitation reactions.  Alum (hydrated  aluminum sulfate)  is  typically added
to aqueous waste streams as a solution.   Upon mixing,  the slightly higher  pH
of the water causes the alum to hydrolyze and form fluffy,  gelatinous
precipitates of aluminum hydroxide.  These  precipitates, partially due  to
their large surface area, enmesh small particles and thereby create  larger
particles.  Lime and iron salts also have a tendency to form large fluffy
precipitates or "floe" particles.  Many precipitation  reactions, such as the
precipitation of metals from solution by  the addition  of sulfide ions,  do  not
readily form floe particles, but rather precipitate  as very fine and
relatively stable colloidal particles.  In  such cases, flocculating  agents
such as alum and/or polyelectrolytes must be added to  cause flocculation of
the metal sulfide precipitates (Canter and  Knox, 1985).

     Once suspended particles have been flocculated  into larger particles,
they usually can be removed from the liquid by sedimentation,  provided  that a
sufficient density difference exists between the suspended matter  and the
liquid.


          10.1.4.2  Applications/Limitat ions


     Precipitation is applicable to the removal of most metals  from  wastewater
including zinc, cadmium, chromium, copper,  fluoride, lead, manganese, and
mercury.  Also, certain anionic species can be removed by precipitation, such
as phosphate, sulfate, and  fluoride.

     Precipitation is useful for most aqueous hazardous waste  aqueous streams.
However, limitations may be imposed by certain physical or  chemical  character-
istics.  In some cases, organic compounds may form organometallic  complexes
with metals, which could inhibit precipitation.  Cyanide and other ions in the
wastewater may also complex with metals, making treatment by precipitation
less efficient.

     Flocculation is applicable to any aqueous waste stream where  particles
must be agglomerated into larger more settleable particles  prior to
sedimentation or other types of treatment.  There is no concentration limit
for precipitation or flocculation.  Highly  viscous waste streams will inhibit
settling of solids.

     In addition to being used to treat waste streams, precipitation can also
be used as an in-situ process to treat aqueous wastes  in surface impoundments.
In an in-situ application,  lime and flocculants are  added directly to the
lagoon, and mixing, flocculation, and sedimentation  are allowed to occur
within the lagoon.  In some cases, wind and pumping  action  can provide  the
energy for mixing.


                                     10-26

-------
          10.1.4.3  Design  Considerations


     Selection of the most  suitable  precipitate  or  flocculant  and  their
optimum dosages  is determined  through  laboratory jar  test  studies.   In
addition to determining  the appropriate  chemicals and optimum  chemical
dosages, other important parameters  which  need  to be  determined  as  part of the
overall design include (Canter  and Knox,  1985):

     •  most suitable chemical  addition  system
     •  optimum  pH requirement
     •  rapid mix requirements
     •  sludge production

     •  sludge flocculation, settling  and  dewatering  characteristics.
          10.1,4.4  Technology Selection/Evaluation


     Precipitation and flocculation are well established  technologies  and  the
operating parameters are well defined.  The processes  requires  only  chemical
pumps, metering devices, and mixing and settling  tanks.   The  equipment  is
readily available and easy to operate.  Precipitation  and  flocculation  can be
easily integrated into more complex treatment  systems.

     The performance and reliability of precipitation  and  flocculation  depends
greatly on the variability of the composition  of  the waste being  treated.
Chemical addition must be determined using laboratory  tests and must be
adjusted with compositional changes of the waste  being treated  or poor
performance will result.

     Precipitation is nonselective in that compounds other than those  targeted
may be removed.  Both precipitation and flocculation are  nondestructive and
generates a large volume of sludge which must  be  disposed.

     Precipitation and flocculation poses minimal  safety  and  health  hazards to
field workers.  The entire system is operated  at  near  ambient conditions,
eliminating the danger of high pressure/high temperature  operation with other
systems.  While the chemicals employed are often  skin  irritants,  they  can
easily be handled in a safe manner.


               10.1.4.5  Costs
     Table 10-9 shows a breakdown of costs for the 40 gpm  sulfex heavy metal
removal system illustrated in Figure 10-6.

                                     10-27

-------
•o
c
(D
o
 *

N
o
u.
O
UJ
cc
o
ui
z
m

o
o
oc
o
X
LU
U.



M



0.

O
I
UJ
oc
3
C9
c
g
1
                                                                                                       3
                                                                                                       O
                                                                                                      cn
                                                     10-28

-------
                   TABLE  10-9.  1985  CAPITAL COSTS* FOR SULFEX
                         HEAVY  METAL PRECIPITATION SYSTEM
          Selling Price

          Equipment                                                  Price

1.  Precipitator with  clear well,  centrifuge
    for dewatering,chemical feeds  and
    agitators, and engineering  drawings                            $68,768

2.  Filter with transfer  pump and  engineering
    drawings                                                         7,623

3.  Neutralization systsem including agitators,
    chemical  feeds, pH controls, sump  pump,  and
    engineering drawings                                            86,126

    Total selling price                                           $162,517

    Installation Cost  (estimated by
    outside contractor)                                            $66,657

                                            TOTAL                 $229,174
*Costs were updated to $1985 using the  1983  and  1985  ENR  Construction  Cost
 Index.

Source:  Metal Finisher's Foundation, 1977

                                                                          2
     The precipitator is sized to operate at  a surface  rate  of  1.6 gpm/ft  and
the filter at a surface rate of 3.2 gpm/ft  .  Chemical  costs  for  the Sulfex
process and a hydroxide precipitation process are  shown in Table  10-10.   These
costs were estimated for treament of an  influent containing 4 mg/1 Cu,  Cd,
Cr  , Ni, and Zn at pH 6.0.

     Figure 10-7 shows capital and operating  costs  for  a  flocculation  system
including chemical storage, chemical feeding  and rapid  mix.   A  polymer  dosage
of 1 mg/1 at 0.25 percent solution is assumed.  Construction  costs also
include piping and building to house the feeding equipment and  bag storage.

     Construction costs include:  Piping and building to  house  the feeding
equipment and bag storage.  1 Mgal/d plant size and smaller use manual  feed
procedures.  2 systems of tanks and feeders  are included.  10 Mgal/d plant
size includes cost of feeders and mixing tanks, one day tank  and  2 solution
feeders.  100 Mgal/d plant size includes costs for  4  feeders  and mixing tanks,
2 holding tanks and 10 solution feeders.  The rapid mix tank  is concrete,

                                     10-29

-------
                 TABLE 10-10.  COMPARISON OF CHEMICAL COSTS* OF
                  HYDROXIDE AND SULFIDE PRECIPITATION PROCESSES
               (1) Hydroxide Process
        Eff. Qyal.
Chemical
Dosage
Cost
Cu
Cd
Cr
Ni
Zn
Cu
Cd
Cr
Ni
Zn

(mg/1)
pH 7.5 pH
0.1 <0.
3.8 <0.
<0.5 <0.
2.3 <0.
1.3 <0.
(2)
Eff. Qual.
(mg/1)
pH 8.5
0.01
0.1
<0.05
0.05
0.01

10
1 CA(OH)2
1 Polymer
1 2 4
1
Sulfex Process
Chemical
71% NaHS
FeSO. . 7H_0
Polymer
Ca(OH)2

lb/1000 gal.
pH 7.5 pH 10
0.33 0.92
0.03 0.03
0.61

Dosage
lb/1000 gal.
pH 8.5
0.09
0.77
0.03
1.13

(if/1000 gal.
i/lb pH 7.5 pH 10
3.16 1.05 2.99
105.4 3.16 4.22
8.8 - 5.45

Total 4.21 12.66
Cost
/1000 gal.
.lb pH 8,5
19.77 1.76
3.95 2.99
105.4 3.16
3.16 3.51
Total 11.42

*Costs were updated to $1985 using the 1977 and 1985 ENR Construction Cost
 Index.

Source:   Metal Finisher's Foundation, 1977
                                     10-30

-------
              FIGURE 10-7. POLYMER ADDITION  COSTS*
IO
s ot
Millions of Dot
o
o
OJOOI


























































f.





:• CONSTRUCTION COST:














1
'' -r*'
mH























J-f
L^it
II


h , i1"





_^ J




ฑ:=j
nH
**








II . 	 ._

T ' 	 '


n| : !












(


1










^ '




-4-





















                  0.1
                  - 3
                               10            10
                             WMMwlt* Flow. Mgซl/d
                                                        100
                OOOI
                  01
                               10           10
                             Wastew*Mr Flow. Mgal/d
                                                         OOOl
                                                         Jooooi
•Costs can be updated to $1966 using ENR Construction Cost Indices for 1902 and 1986
 (multiply value shown on this figure by 1.303)
    Source: USEPA, 1982a
                                  10-31

-------
equipped with stainless steel mixer and handrails.   0.1 Mgal/d  plant  size:   no
separate building is required.  Manual operation of  feeder, mix tank  solution
feeder and holding tank.


     10.1.5  Sedimentation Technology


          10.1.5.1  General Description


     Sedimentation is a process that relies upon gravity  to remove  suspended
solids in an aqueous waste stream.  The fundamentals of a  sedimentation
process includes (Kiang and Metry, 1982):

     •  A basin or container of sufficient size to maintain the liquid to be
        treated in a relatively quiescent state for  a  specified period of time

     •  A means of directing the liquid to be  treated  into the  above  basin  in
        a manner conducive to settling

     •  A means of physically removing the settled particles  from the liquid
        (or liquid from the settled particles).

     Sedimentation can be carried out as either a batch or continuous process
in lined impoundments, conventional settling basins, clarifiers, and  high rate
gravity settlers.  Modified aboveground swimming pools have been used many
times for sedimentation in temporary, short-term treatment systems  at
hazardous waste sites.  Figure 10-8 illustrates three  different design
configurations for sedimentation.  In sedimentation  ponds  the liquid  is merely
decanted as the particles accumulate on the bottom of  the  pond. Backhoes,
draglines, or siphons are used periodically to remove  settled solids.

     Sedimentation basins and clarifiers usually employ a  built-in  solids
collection and removal devices such as a sludge scrapper and  draw-off
mechanism.  Sedimentation basins are general rectaggular,  usually employ a
belt-like collection mechanism, and are mainly used  for removal of  truly
settleable particles from liquid.

     Clarifiers are usually circular and are used in applications involving
precipitation and flocculation as well as sedimentation.  Many  clarifiers are
equipped with separate zones for chemical mixing and precipitation,
floculation, and sedimentation (Kiang and Metry, 1982).


          10.1.5.2  Applications/Limitations


     Sedimentation is commonly applied to aqueous wastes with high  suspended
solid loadings.  This may include surface run-off, collected  leachate or
landfill toe seepage, dredge slurries, and effluents from biological  treatment
and precipitation/flocculation.  Sedimentation is also required as  a

                                     10-32

-------
                                      FIGURE 10-8.
                  REPRESENTATIVE TYPES OF SEDIMENTATION
  Setting Pond

        Inlet Liquid
                                                                    Overflow Discharge Weir
                                                                    Accumulated Settled Particles
                                                              Periodically Removed by Machinical Shovel
  Sedimentation Basin

          Inlet Zone
  Inlet Liquid
Settled Particles Collected
and Periodically Removed
                                     Baffles to Maintain
                                   "Quiescent Conditions
                                                                       Outlet Zone
                                                                           Outlet Liquid
Belt-Type Solids Collection Mechanism
  Circular Clarifier
                                                     Circular Baffle

Inlet Zone "
— \
TTTTX;
^<^>-,.


—^
'
\ .
ซ•
/ !
/ — L_
s
/ Liquid
/ Flow
-'TTTT-
, ,. , -^-*^***
Annular Overflow V
Outlet Liquid
— Settling Partic
          Settling Zone,
          Revolving Collection
              Mechanism
                          Settled Particles T        Collected and Periodically Removed
                                          i Sludge Drawoff
Source: De Renzo, 1978
                                          10-33

-------
pretreatment step for many chemical processes, including carbon adsorption,
ion exchange, stripping, reverse osmosis and  filtration.

     This technology is applicable to the removal of suspended solids heavier
than water.  Suspended oil droplets or oil-soaked particles may not  settle out
and may have to be removed by some other means.  Some sedimentation  units are
fitted with skimmers to remove oil and grease that  float to the water surface.
However, these would not be effective in removing emulsified oils.


          10.1.5.3  Design Consideration


     Sedimentation is frequently considered in terms of ideal setting.   The
ideal setting theory results in the following equation for surface loading or
overflow rate .

                                    V  -2
     where:  V  = setting velocity
             Q  = flow through the basin
             A = surface area of the basin

Sedimentation basin loadings (Q/A) are often expressed in terms of  gallons  per
day per square foot.  Thus under ideal settling conditions, sedimentation is
independent of basin depth and detention time, and depends only on  the  flow
rate, basin surface area and properties of the particle.

     However sedimentation does not perform according to ideal settling
conditions since settling is affected by such conditions as turbulence,  and
bottom scour.  Therefore removal of particles is dependent on basin depth,  and
detention time as well as flow rate surface area and particle size.   The
performance of a sedimentation basin on a suspension of discrete  particles  can
be calculated, but  it is not possible to calculate sedimentation  basin
performance for a suspension of flocculating particles, such as a wastewater,
because settling velocities change continually.  Laboratory settling tests,
however, may be performed to predict sedimentation basin performance.


             10.1.5.4  Technology Selection/Evaluation


     Sedimentation  provides a reliable means to remove suspended  matter from  a
waste stream, provided the suspended matter is settleable and the treatment
process including the use of flocclants/coagulants has been appropriately
designed from laboratory settling tests.  Most clarifiers are capable of
removing 90 to 99 percent of the suspended solids.
                                      10-34

-------
      Sedimentation employs  readily available  equipment and  is  relatively easy
to operate.   The process  is  versatile in that  it  can be applied  to almost any
liquid waste stream containing suspended solids.   It can also  be easily inte-
grated into  a more complex  treatment system as  a  pre- or post-treatment
method.   Sedimentation  is nonselective and nondestructive,  resulting in a
large volume of potentially  contaminated sludge that may require further
treatment  and disposal.
              10.1.5.5  Costs
     The  cost  of a system which includes chemical  clarification,  rapid mixing,
flocculation with alum and  polymer and sedimentation is shown  in  Figure 10-9.
The cost  estimate assumed alum and polymer dosages of 200 mg/1  and 1 mg/1
respectively,  and a flow rate  to the clarifier  of  800 gpd/ft  .  The costs of
chemical  sludge proceessing  and disposal are  not  included in the  capital
costs. O&M  costs include cost  of chemical purchase (Gulp, Wesner  and Gulp,
1978).

            FIGURE 10-9. COST OF CHEMICAL CLARIFICATION WITH ALUM*
          O
          o
          .1
          Q.
          (3
             5,000
             4,000

             3,000


             2,000
             1,000
              500
              400

              300


              200
              100
                                                                100
  O
50

40
30


20
ฐ<*
                            3  4 5 6789 10
                                              20   30 40 50
                                                              100
                                                                10
              Capital Costs
              0&M Costs
                                   Plant Capacity, MGD
           •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
           (multiply value shown on this figure by 1.908)
           Source: Gulp, Wesner Ct Gulp, 1978
                                       10-35

-------
     10.1.6  Ion Exchange and Sorptive Resins


             10.1.6.1  General Description


     Ion exchange is a process whereby the  toxic  ions  are  removed  from  the
aqueous phase by being exchanged with relatively  harmless  ions  held  by  the  ion
exchange material.  Modern ion exchange resins  are  primarily  synthetic  organic
materials containing ionic functional groups to which  exchangeable ions are
attached.  These synthetic resins are structurally  stable  (that  is,  can
tolerate a range of temperature and pH conditions), exhibit a high exchange
capacity, and can be tailored to show selectivity towards  specific ions.
Exchangers with negatively-charged sites are cation exchangers  because  they
take up positively charged ions.  Anion exchangers have positively charged
sites and, consequently, take up negative ions.   The exchange reaction  is
reversible and concentration dependent, and it  is possible to regenerate the
exchange resins for reuse.  Sorptive (macroporous)  resins  are also available
for removal of organics and the removal mechanism is one of sorption rather
than ion exchange (Ghassemi, Yu, and Quinlivan, 1981).


             10.1.6.2  Applications/Limitat ions


     Ion exchange is used to remove a broad range of ionic species from water
including:

     •  All metallic elements when present  as soluble  species,  either anionic
        or cationic

     •  Inorganic anions such as halides, sulfates, nitrates, cyanides, etc.

     •  Organic acids such as carboxylics,  sulfonics,  and  some  phenols, at  a
        pH sufficiently alkaline to give the ions

     •  Organic amines when the solution acidity  is sufficiently acid to form
        the corresponding acid salt (De Renzo,  1978).

Sorptive resins can remove a wide range of  polar  and non-polar  organics.

     A practical upper concentration limit  for  ion exchange is  about 2,500  to
4,000 mg/1.  A higher concentration results in  rapid exhaustion of the  resin
and inordinately high regeneration costs.   Suspended solids in  the feed stream
should be less than 50 mg/1 to prevent plugging the resins, and waste streams
must be free of oxidants (De Renzo, 1978).
                                     10-36

-------
          10.1.6.3  Design Considerations


     Specific ion exchange and sorptive resins systems must be designed on a
case-by-case basis.  It is useful to note that although there are three major
operating models (fixed bed cocurrent, fixed bed countercurrent, and
continuous countercurrent), fixed bed countercurrent systems are most widely
used.  Figure 10-10 illustrates the fixed bed countercurrent and continuous
countercurrent systems.  The continuous countercurrent system is suitable for
high flows.  Complete removal of cations and anions ("demineralization") can
be accomplished by using the hydrogen form of a cation exchange resin and the
hydroxide form of an anion exchange resin.  For removal of organics as well as
inorganics, a combination adsorptive/demineralization system, can be used.  In
this system, lead beds would carry sorptive resins which would act as organic
scavengers, and the end beds would contain anion and cation exchange resins.
By carrying different types of adsorptive resins (e.g., polar and non-polar),
a broad spectrum of organics could be removed (Ghassemi, Yu, and Quinlivan,
1981).
          10.1.6.4  Technology Selection/Evaluation


     Ion exchange is a well established technology for removal of heavy metals
and hazardous anions from dilute solutions.  Ion exchange can be expected to
perform well for these applications when fed wastes of variable composition,
provided the system's effluent is continually monitored to determine when
resin bed exhaustion has occurred.  However, as mentioned previously, the
reliability of ion exchange is markedly affected by the presence of suspended
solids.  Use of sorptive resins is relatively new and reliability under
various conditions is not as well known.

     Ion exchange systems are commercially available from a number of vendors.
The units are relatively compact and are not energy intensive. Start-up or
shut-down can be accomplished easily and quickly (Ghassemi, Yu, and Quinlivan,
1981).  These features allow for convenient use of ion exchange and sorptive
resin systems in mobile treatment systems.

     Although exchange columns can be operated manually or automatically,
manual operation is better suited for hazardous waste site applications
because of the diversity of wastes encountered; with manual operation, the
operator can decide when to stop the service cycle and begin the backwash
cycle.  However, this requires use of a skilled operator familiar with the
process (Ghassemi, Yu, and Quinlivan, 1981).

     Use of several exchange columns at a site can provide considerable
flexibility.  As described previously, various resin types can be used to
remove anions, cations, and organics.  Various columns can be arranged in
series to increase service-life between regeneratation of the lead bed or in
parallel for maximum hydraulic capacity.  The piping arrangement would allow
for one or more beds to be taken out for regeneration while the remaining
columns would remain in service. (Ghassemi, Yu, Quinlivan, 1981).

                                     10-37

-------
                                  FIGURE 10-10.
  PERTINENT FEATURES  OF  ION EXCHANGE  SYSTEMS
  Types
                       Counlercurrenl Fixed Bed
                                    HtOtNtHAllON
                                                           Continuous Counlercuirenl
                                                        HtGfNEFUTIOI
Description
of Process
Indications
(or Use
Advantages
Disadvantages
Regeneralion Hows opposite in direction
to Influent Backwash (in regeneration)
does not occur on ovary cycle to pre-
serve resin stage heights Resin bed is
locked in place during regeneration

Handles high loads at moderate Ihrupul
or low loads at high thruput (GPM x TDS
or GPM x PPM removal = 40,000  or
more) Where effluent quality must be
relatively constant, regeneration cost Is
relatively critical, disposal  of  single
batch waste volume no problem
                  Moderate capital cost Can be operated
                  with  periodic  attention   Moderate
                  regeneration cost  Lesser  volume of
                  waste due to less frequent backwash
                  Consistent effluent quality
                  Increased conlrols and instrumentation,
                  higher cost  Requires mechanism lo lock
                  resin bed Large single batches of waste
                  disposal  Moderate water consmption
                  thru dilution and waste Requires sub-
                  stantial llooi space
Multi-stage counlercurrent movement of
resin in closed loop providing simul-
taneous treatment, regeneration, back-
wash and rinse Operation is onty Inter-
rupted for momentary resin pulse

Highloads  with high thrupuls  (GPM x
TDS 01 GPM x PPM removal  = 40,000 or
more) Where constant effluent quality Is
essential, regeneration  costs  critical,
total waste volume requires small, con-
centrated stream  lo be controllable
Where loss of product thru dilution and
waste must be  mimmi/ed Where avail-
able floor space is limited

Lowest regeneration cost Lowest resin
Inventory Consistent effluent  quality
Highest  Ihrupul to  floor space  Large
capacity units  factory  preassernblud
Concentrated low volume waste stream
Can handle strong chemical solutions
and slurry  Fully automatic opeiation

Requires automatic conlrols and inslru
mentation,  highei capital cost  Moie
headroom required
Source: Chemical Seperations Corporation
                                       10-38

-------
     Consideration must be given  to disposal of  contaminated  ion exchange
regeneration solution.  In addition to  proper  disposal,  another  important
operational consideration is the  selection of  regeneration  chemicals.   Caution
must be exercised in making this  selection to  ensure  the compatibility of the
regenerating chemical with the waste being treated.   For example,  the  use of
nitric acid to regenerate an ion  exchange column containing ammonium ions
results in the formation of ammonium nitrate,  a  potentially explosive
compound.

          10.1.6.5  Costs
     Costs for various sizes of ion exchange units  are  presented  in  Table
10-11. The construction costs assume fabricated  steel contact vessels  with
baked phenolic linings, a resin depth of 6 feet, housing  for the  columns, and
all piping and backwash facilities.

     Operation and maintenance costs include electricity  for backwashing
(after 150 bed volumes have been treated) and periodic  repair and  replacement
costs.  Costs for regenerant chemicals are not included because they vary
depending on the types and concentrations of target chemicals to  be  removed
from the wastewater.
                                 TABLE 10-11.

            GENERAL COST DATA FOR VARIOUS SIZES OF EXCHANGE UNITS
Plant Ccpacity (gpm)            Construction               Operation  and
                                Cost ($)*                Maintenance  Costs
                                                             ($/year)*
50
195
305
438
597
84,105
116,200
134,770
154,000
180,270
14,530
21,260
24,280
27,590
31,531
*Updated from 1979 to 1984 dollars using third quarter Marshall and Swift
 Index.

Source:   Adapted from Hansen, Gumerman, and Gulp, 1979.
                                     10-39

-------
     10.1.7  Reverse Osmosis
          10.1.7.1  General Description
     Osmosis is the spontaneous  flow of solvent  (e.g., water)  from  a  dilute
solution through a semipermeable membrane (impurities or  solute  permeates  at  a
much slower rate) to a more concentrated solution.  Reverse  osmosis is  the
application of sufficient pressure to the concentrated solution  to  overcome
the osmotic pressure and force the net flow of water through the membrane
toward the dilute phase.  This allows the concentration of solute (impurities)
to be built up in a circulating  system on one side of the membrane  while
relatively pure water is transported through the membrane.   Ions and  small
molecules in true solution can be separated from water by this technique.

     The basic components of a reverse osmosis unit are the  membrane, a
membrane support structure, a containing vessel, and a high  pressure  pump.
The membrane and membrane support structure are  the most  critical elements.


          10.1.7.2  Applications/Limitations


     Reverse osmosis (RO) is used to reduce the  concentrations of dissolved
solids, both organic and inorganic.  In treatment of hazardous waste
contaminated streams, use of reverse osmosis would be primarily  limited to
polishing low flow streams containing highly toxic contaminants.  In  general,
good removal can be expected for high molecular weight organics  and charged
anions and cations.  Multivalent ions are treated more effectively  than are
univalent ions.  Recent advances in membrane technology have made it  possible
to remove such low moelcular weight organics as  alcohols, ketones,  amines, and
aldehydes (Gooding, 1985).  Table 10-12 shows removal results  obtained  during
testing of a mobile RO unit using two favorable membrane  materials  (Whittaker,
1984).

     RO Units are subject to chemical attack, fouling, and plugging.
Pretreatment requirements can be extensive.  Wastewater must be  pretreated to
remove oxidizing materials such  as iron and maganese salts,  to filter out
particulates, adjust pH to a range of 4.0 to 7.5, and to  remove  oil,  grease,
and other film forms (De Renzo,  1978).  The growth of slimy  biomass on  the
membrane surface or the presence of organic macromolecules may also foul the
membrane.  This organic fouling  can be minimized by prechlorination,  addition
of biocides and/or pretreatment  with activated carbon (Ghassemi, Yu,  and
Quinlivan, 1981).


          10.1.7.3  Design Considerations

     The most critical design consideration applicable to reverse osmosis
technology is the design of the  semipermeable membrane.   In  addition  to
                                     10-40

-------
                                 TABLE  10-12.




            RESULTS OF PILOT  SCALE TESTING  OF A  REVERSE  OSMOSIS  UNIT

Percent removed in permeate
Chemical
Dichloromethane
Acetone
1 , 1-Dichloroethene
Tetrahydro f uran
Diethyl ether
Chloroform
1 , 2-Dichlorethane
1,1,1-Trichloro-
ethane
Trichloroethene
Benzene
Bromoform
Hexane
Feed
Concentration
(ppb)
406
110
34
17,890
210
270X
99
659

241
539
121
^
Percent
Concentrated
in Concentrate
203
355
795
467
439
567
415
651

346
491
633
704
Polyether-
polysul phone
membrane
58
84
99
98
97
98
92
99.8

99
99
99.1
99.8
Polyester/
amide poly-
sul phone
membrane
52
76
95
89
89
92
85
97

92
99
98
97

1.   no standard available; concentration estimated.




Source:   Whittaker, 1984
                                     10-41

-------
allowing the achievement of the required degree of separation at an economic
flux level under ideal conditions, the membrane must be incorporated in an
operating system which satisfies- these practical requirements (Conway and
Ross, 1980):

     o  Minimum concentration polarization, ie., ratio of impurity
        concentration at the membrane surface to that in the bulk stream

     o  High packing density, i.e., membrane surface area per unit volume of
        the pressure module

     o  Ability to handle any particulate impurities (by proliferation if
        necessary)

     o  Adequate support for the membrane and other physical features such as
        effectiveness of seals, ease of membrane replacement, and ease of
        cleanning.

     Membranes are usually fabricated in flat sheets or tubular forms and are
assembled into modules.  The most common materials used are cellulose acetate
and other polymers such as polyamides and polyether-polysulphone.  There are
three basic module designs: tubular, hollow fiber, and spiral wound.  These
are illustrated in Figure 10-11.  Each type of membrane module has its own
advantages and limitations.  The tubular module provides the largest flow
channel and allows for turbulent fluid flow regime; thus, it is least
susceptible to plugging caused by suspended solids and has the highest flux.
However, because of its small area/volume ratio the total product recovered
per module is small.  The cost of a tubular module is approximately five times
that for the other modules for an equivalent rate of water recovery, and the
total space requirement is about three to five times that for the spiral wound
system (Ghassemi, Yu and Quinlivan, 1981).

     A hollow fiber membrane is constructed of polyamide polymers and
cellulose triacetate by Dupont and Dow, respectively.  The polyamide membrane
permits a wider operating pH range than cellulose acetate, which is commonly
used for the construction of spiral wound and tubular membranes.  The flow
channel and the flux are about an order of magnitude lower than thee other
configurations.  This small flux, however, is compensated for by the large
surface area/volume ratio, with the total product water per module being close
to that obtainable with spiral wound modules.  However, because of the small
size of the channels (about 0.004 in.) and the laminar fluid flow regime
within the channels, this module is susceptible to plugging and may require
extensive pretreatment to protect the membrane (Ghassemi, Yu and Quinlivan,
1981).

     The spiral wound module consists of an envelope of flat sheet membranes
rolled around a permeate collector tube.  This configuration provides for a
higher flux and greater resistance to fouling than the hollow fiber modules;
it is also  less expensive and occupies less space than a tubular module
(Ghassemi, Yu and Quinlivan, 1981).
                                     10-42

-------
                FIGURE 10-11. MEMBRANE MODULE CONFIGURATIONS
                              A. TUBULAR MEMBRANE
                     CASING
                     MEMBRANE
                                                    WATER
                                                    FLOW
                            b.  SPIRAL-WOUND MODULE
               ROLL TO
               ASSEMBLE
                                       FEED FLOW
                         V
                        PERMEATE FLOW
                        (AFTER PASSAGE
                        THROUGH MEMBRANE
      FEED SIDE
      SPACER
       X
PERMEATE OUT
PERMEATE SIDE BACKING
MATERIAL WITH MEMBRANE ON
EACH SIDE AND GLUED AROUND  \
EDGES AND TO CENTER TUBE
                             c. HOLLOW-FIBER MODULE
                  CONCENTRATE
                  OUTLET
                              FLOW
                             SCREEN
                                                OPEN END
                                                OF FIBERS
 EPOXY
TUBE SHEET
                                                               POROUS
                                                              BACK-UP DISC
                                                                     SNAP RING
       "O" RING
        SEAL
             END PLATE
                                                                     PERMEATE
                         FIBER
                                  SHELL
                                          POROUS FEED
                                          DISTRIBUTOR
                                             TUBE
                                                    "O" RING  END PLATE
                                                      SEAL
Source: Ghassemi, Yu ft Quinlivan, 1981
                                       10-43

-------
          10.1.7.4  Technology Selection/Evaluation


     Reverse osmosis is an effective treatment technology for removal of
dissolved solids presuming appropriate pretreatment has been performed  for
suspended solids removal, pH adjustments, and removal of oxidizers, oil,  and
grease.  Because the process is so susceptible to fouling and plugging,
on-line monitors may be required to monitor pH, suspended solids, etc.  on a
continuous basis.  Reverse osmosis has not been widely used for treatment of
hazardous wastes.

     Reverse osmosis will not reliably treat wastes with a high organic
content, as the membrane may dissolve in the waste.  Lower levels of organic
compounds may also be detrimental to the unit's reliability, as biological
growth may form on a membrane fed an influent containing biodegradable
organics.

     The fact that RO units can be operated in series or in parallel provides
some flexibility in dealing with increased flow rates or concentration  of
dissolved species.

     Memtek Corporation of Ontario, Canada has developed a mobile reverse
osmosis unit for Environment Canada.  The unit, which is capable of handling
low flows of about 10 gpm is currently being tested for various types of
spills (Whittaker, 1984).

     The volume of the reject generated by reverse osmosis is about 10  to
25 percent of the feed volume.  Provisions must be made to treat this
potentially hazardous waste.
          10.1.7.5  Costs
     Costs for various sizes of reverse osmosis units are presented  in Table
10-13.  The construction costs include housing, tanks, piping, membranes,  flow
meters, cartridge filters, acid and polyphosphate  feed equipment,  and cleanup
equipment.  These costs are based on influent total dissolved solids concen-
trations of less than 10,000 ppm.

     The operation and maintenance costs include electricity for  the high
pressure feed pumps (450 psi operating pressure), building utilities, routine
periodic repair, routine cleaning, and membrane replacement every 3 years.
Operation and maintenance costs do not include costs for pretreatment
chemicals due to extreme usage rate variability between plants.
                                     10-44

-------
                                  TABLE 10-13.

          GENERAL COST DATA FOR VARIOUS SIZES OF REVERSE OSMOSIS UNITS

Plant Capacity (gpra)
1.74
7
70
700
Construction
Costs ($)*
17,070
33,280
171,820
1,014,600
O&M Costs
($/year)
7,580
12,070
40,829
249,930

*Updated  from  1979  to  1984  dollars  using third quarter Marshall and Swift
  Index.

Source:   Adapted  from  dansen,  Gumertnan,  and  Gulp,  1979.
     The RO unit  being  tested by  Environment  Canada can handle flow up to
 11,000 gpd and  costs  approximately $60,000.   Membranes vary considerably in
 cost.  The Toray  and  DSI membranes discussed  in Table 10-12,  for example, cost
 $360 and $915,  respectively (Whittaker  et  al.,  1985).


     10.1.8  Neutralization
           10.1.8.1  General  Description


     Neutralization consists  of  adding acid  or  base to a waste in order to
adjust its pH.  The most  common  system for neutralizing acidic or basic waste
streams utilizes a multiple  compartmental basin usually constructed of
concrete.  This basin  is  lined with  acid brick  or  coated with a material
resistant  to the expected  environment.

     In order to reduce the  required  volume  of  the neutralization basin,
mixers are installed in each  compartment to  provide more intimate contact
between the waste and  neutralizing reagents,  thus  speeding up reaction time.
Stainless  steel plates mounted on the floor  of  the pit and directly below the
mixers will reduce corrosion  damage  to the structure.   Basin inlets are
baffled to provide for flow distribution, while effluent baffles can help to
prevent foam from being carried  over  into the receiving stream (Conway and
Ross, 1980).
                                      10-45

-------
     In some cases, neutralization may be accomplished  in a discharge  sewer.


          10.1.8.2  Application/Limitation


     Neutralization can be applied to any wastestream or wastewater requiring
pH control.  It is commonly used prior to biological treatment,  since  bacteria
are sensitive to rapid pH changes and values outside a  pH range  of 6 to 9.
Similarly, aquatic ecosystems are pH sensitive, therefore neutralization  of
wastewater is required prior to discharge to a receiving water body.   In  the
case where hazardous wastes are hazardous because of corrosivity, neutraliza-
tion may be required prior to acceptance for disposal.  It is also used as a
pretreatment for several chemical treatment technologies, including carbon
adsorption, ion exchange, air stripping, wet air oxidation, and  chemical
oxidation/reduction processes.  A pH adjustment is also dictated in several
other situations, including protection of construction materials, breaking of
emulsions, insolubilization of certain organic materials, and control  of
chemical reaction rates (e.g., chlorination) (Conway and Ross, 1980).


          10.1.8.3  Design Considerations


     The choice of an acidic reagent for neutralization of an alkaline
wastewater is generally between sulfuric acid and hydrochloric acid.   Sulfuric
acid is usually used due to its lower cost.  Hydrochloric acid has the
advantage of soluble reaction end products.

     The selection of a caustic reagent is usually between sodium hydroxide
and various limes; ammonium hydroxide is occasionally used.  The factors  to be
considered in choosing the most suitable reagent include:  purchase cost,
neutralization capacity, reaction rate, storage and  feeding requirement,  and
neutralization products.

     Although sodium hydroxide costs much more than  the other materials,  it is
frequently used due to uniformity, ease of storage and  feeding,  rapid  reaction
rate, and soluble end products.  The lime materials  have the advantage of
relatively low cost.  This low material cost is at least partially offset by
increased capital and operating costs for the rather complex feeding and
reaction system required (Conway and Ross, 1980).

     While the rate of reaction between the completely  ionized sodium
hydroxide and a strong acid waste is virtually instantaneous, the reactions of
lime bases require considerable time for completion.  Reaction time can be
minimized by several approaches:  a relatively high  end point pH level,
efficient mixing, and slurry feeding as opposed to dry  feeding (Conway and
Ross, 1980).
                                     10-46

-------
          10.1.8.4  Technology Selection/Evaluation


     Neutralization is a relatively simple unit treatment process which can be
performed using readily available equipment.  Only storage and reaction tanks
with accessory agitators and delivery systems are required.  Because of the
corrosivity of the wastes and treatment reagents, appropriate  materials of
construction are needed to provide a reasonable service-life for equipment.
The process is reliable provided pH monitoring units are used.  The feed of
the neutralization agent may be regulated automatically by the pH monitoring
unit thereby ensuring effective neutralization and minizing worker contact
with corrosive neutralizing agents.

     Neutralization of hazardous wastes has the potential of producing air
emissions.  Acidification of streams containing certain salts, such as
sulfide, will produce toxic gases.  Feed tanks should be totally enclosed to
prevent escape of acid fumes.  Adequate mixing should be provided to disperse
the heat of reaction if wastes being treated are concentrated.  The process
should be controlled from a remote location if possible.
          10.1.8.5  Costs

     Capital costs for a neutralization system include costs for chemical
storage, chemical feeding and mixing.  These costs can be approximated using
Figure 10-7.

     10.1.9  Gravity Separation


          10.1.9.1  General Description


     Gravity separation is a purely physical phenomenon in which the oil is
permitted to separate from water in a conical tank.


          10.1.9.2  Applications/Limitations

     Gravity separators are primarily used to treat two-phased aqueous wastes.
A typical application would be separation of free gasoline or fuel oil from a
fuel contaminated aquifer.  Gravity separation has also been used to separate
PCS oils from contaminated groundwater.  For efficient separation, the
nonaqueous phase should have a significantly different specific gravity than
water and should be present as a nonemulsified substance.  Emulsion between
water and oil is common, and an emulsion breaking chemical must frequently be
added to the waste for efficient treatment.
                                     10-47

-------
          10.1.9.3  Design Considerations


     Gravity separators can take many shapes and arrangements, depending in
part on the characteristics of the waste.  The modern trend is to keep
separator design small and simple to reduce costs.  Typical design configura-
tions include:   horizontal cylindrical decanters, vertical cylindrical
decanters, and cone-bottomed settlers.

     Baffles are frequently installed to provide additional surface area,
which promotes oil droplet coalescence.  The cone-bottomed design is
particularly useful if heavy solids are to be settled out of the waste while
oil separation is proceeding.


          10.1.9.4  Technology Selection/Evaluation


     Gravity separation offers a straightforward, effective means of phase
separation provided the oil and water phases separate adequately within the
residence time of the tank.  Simple, readily available equipment can be used
and operational requirements are minimal.  If emulsion-breaking chemicals must
be added to promote oil-water separation, laboratory tests should be period-
ically conducted to ensure adequate dosing.

     Consideration must also be given to the disposal of the extracted waste
constituents collected.  For gravity separation processes, this material
consists of immiscible oil siphoned from the separator.


     10.1.10  Air Stripping


          10.1.10.1  General Description


     Air stripping is a mass transfer process in which volatile contaminants
in water or soil are transferred to gas.

     As shown in Figure 10-12, there are four basic equipment configurations
used to air strip liquids.

     Air stripping is frequently accomplished in a packed tower equipped with
an air blower.  The packed tower works on the principle of countercurrent
flow.  The water stream flows down through the packing while the air flows
upward, and is exhausted through the top.  Volatile, soluble components have
an affinity for the gas phase and tend to leave the aqueous stream for the gas
phase.  In the cross-flow  tower, water flows down through the packing as in
the countercurrent packed  column, however, the air is pulled across the water
flow path by a fan.  The coke tray aerator is a simple, low-maintenance
process requiring no blower.  The water being treated is allowed to trickle


                                     10-48

-------
              FIGURE 10-12. AIR STRIPPING EQUIPMENT CONFIGURATIONS
                   PACKED COLUMN
                INFLUENT-
                             DISTRIBUTOR
                                        INFLUENT
                           DIFFUSED AIR BASIN

                              AIR SUPPLY

                             :rฃF
            SUPPORT
             PLATE
          br— INCOMING
        ,,. ^   *'"
  EFFLUENT!

COKE TRAY AERATOR
              RAW WATER
                INUTT-0
      DDDD
      noon
•SPLASH
APRONS
                                 •OUTLBT
                                                              •EFFLUENT
                                             CROSS-FLOW TOWER
                                                    AIR,OUTLET
                                         INLET
                                                       COLLECTION
                                                         BASIN
Source: Canter and Knox, 1985
 through several  layers  of  trays.   This produces a large  surface  area for gas
 transfer.  Diffused  aeration stripping and induced draft  stripping  use
 aeration basins  similar to standard wastewater treatment  aeration basins.
 Water flows through  the basin from top to bottom or from  one  side to another
 with the air dispersed  through diffusers at the bottom of the  basin.  The
 air-to-water ratio is significantly lower than in either  the  packed column or
 the cross-flow tower (Canter and  Knox, 1985).
           10.1.10.2  Applications/Limitations
      Air stripping  is used  to  remove volatile organics from  aqueous  waste-
 streams.  Generally components  with Henry's Law constants of greater than
 0.003 can be effectively  removed  by air stripping (Conway and  Ross,  1980).
 This includes such  components  as  1,1,1-trichloroethane, trichloroethylene,
 chlorobenzene, vinyl chloride,  and  dichloroethylene.  The feed  stream must be
 low in suspended solids and may require pH adjustment of hydrogen  sulfide,
 phenol, ammonia, and other  organic  acids or bases to reduce  solubility and
 improve transfer to the gas phase.   Stripping is often only  partially
 effective and must be followed  by another process such as biological treatment
 or carbon adsorption. Combined  use  of  air stripping and activated  carbon can
 be an effective way of removing contaminants from groundwater.   The  air
 stripper removes the more volatile  compounds not removed by  activated carbon
                                       10-49

-------
and reduces the organic load on the carbon, thus reducing  the  frequency  (and
expense) of carbon regeneration.

     The countercurrent packed tower has been the most widely  used  equipment
configuration for air stripping at hazardous waste sites.  The reason  for  this
are (Canter and Knox, 1985):

     (1)  It provides the most liquid interfacial area.

     (2)  High air-to-water volume ratios are possible due to  low air  pressure
          drop through the tower.

     (3)  Emission of stripped organics to the atmosphere  may  be environ-
          mentally unacceptable; however, a countercurrent tower is relatively
          small and can be readily connected to vapor recovery equipment.


     The major disadvantage of the packed column is the high energy cost.


          10.1.10.3  Design Considerations
     The design of a packed tower air stripper generally  involves a deter-
mination of the cross-sectional area of the column and  the height of  the
column packing.  The cross-sectional area of the column is determined  from
physical properties of the air flowing through the column, the  characteristics
of the packing and the air-to-water flow ratio.

     A key factor is the establishment of an acceptable air velocity.   A
general rule of thumb used for establishing the air velocity  is  that  an
acceptable air velocity is 60% of the air velocity at flooding.  Flooding is
the condition in which the air velocity is so high that it holds up the water
in the column to the point where the water becomes the  continuous phase rather
than the air.  If the air-to-water ratio is held constant, the  air velocity
determines the flooding condition.  For a selected air-to-water  ratio,  the
cross-sectional area is determined by dividing the air  flow rate by the air
velocity.  The selection of the design air-to-water ratio must  be based upon
experience or pilot-scale treatability studies.  Treatability studies  are
particularly important for developing design information  for  contaminated
ground water (Canter and Knox, 1985).
                                      10-50

-------
     The height of column packing may be determined by the following equation
(Canter and Knox, 1985):
          In
                            -(1-A) + A
where
                KLaC(l-A)(l-X)M

           Z = height of packing, ft.
           L = water velocity, Ib-mole/hr/ft
          X~ = influent concentration of pollutant in ground water, mole
               fraction
           .
               effluent concentration of pollution in ground water, mole
               fraction
         K a = mass transfer coefficient, gal./hr.
           C = molar density of water = 3.47 Ib-mole/ft
           H = Henry's law constant, mole fraction in air per mole fraction in
               water
           G = air velocity, Ib-mole/hr/f t
           A = L/HG
      (l-X)M = the average of one minus the equilibrium water concentration
               through the column
          Y, = influent concentration of pollutant in air, mole fraction

In most cases, the following assumption can be made :

(1) Y. = 0, there should be no pollutants in the influent air.

(2) (l-X)M = 1, the influent concentrations should be too small when converted
to mole fraction to shift this term significantly from 1.0.
The packing column height can then be determined by the simplified equation:

                 ^2_   (1-A) + A | L
          In  I   X
     Z = 	——	
                  TO, a C(l-A)
                            "]
     The mass transfer coefficient, Ka, is determined from pilot-scale
treatability studies, and is a function of type of compound being removed,
air-to-water ratio, groundwater temperature, type of packing and tower
geometry (Canter and Knox, 1985).

     Calgon Carbon Corporation maintains a computer modelling system which
determines the appropriate tower diameters, parking heights, air/water ratios
and tower packing for a particular aplication (Calgon Carbon Corp. 1983).
This system facilitates rapid mobilization of the packed tower equipment to a
site.
                                     10-51

-------
          10.1.10.4  Technology Selection/Evaluation


     In recent years, air  stripping has gained  increasing  use  for  the
effective removal of volatile organics from aqueous wastestreams.   It  has  been
used most cost-effectively  for treatment of low concentrations  of  volatiles or
as a pretreatment step prior to activated carbon.  Calgon  manufacturers  a
treatment system which combines air stripping and  activated  carbon.

     The equipment for air  stripping  is relatively simple, start-up  and
shut-down can be accomplished quickly, and the  modular  design  of packed  towers
makes air stripping well suited for hazardous waste site applications.

     An important factor in the consideration of whether to  utilize  air
stripping technology for the removal  of volatile contaminants  is the air
pollution implications of  air stripping.  The gas  stream generated during
treatment may require collection and  subsequent treatment  or incineration.


          10.1.10.5  Costs
     Packed tower air strippers have higher  removal  efficiencies  than induced-
draft systems, which are similar to diffused  aeration  systems.  However,  the
induced-draft system is lower  in capital  cost  and  requires  less energy to
operate than a packed-tower system.  Table  10-14 describes  the  installed  cost
of an induced-draft stripper manufactured and  marketed  by the Calgon Carbon
Corporation.  As shown in Table 10-14, the  installed cost of an induced-draft
stripper, capable of treating  700 gpm  and removing 75 percent of  the TCE
contamination, is about 31 percent  ($19,000 vs.  $61,300) of the cost of a
packed-tower capable of removing 95 percent  of the TCE.  Assuming that a  well
pump with a minimum discharge  head of  25  pisig is  required  to feed both units,
the packed-tower also uses an  additional  $5,100 per  year in electrical energy
for operation of the blower.

     In a typical treatment system, re-pumping of  the  treated water would be
required.  Adding the cost of  a sump,  flow  control,  and a pump, the overall
project cost for the induced-draft  system would be about one-half the cost of
the packed tower system (Calgon Carbon Corp.,  undated).


     10.1.11  Oxidation
           10.1.11.1  General Description


     Reduction-oxidation  (redox)  reactions  are  those  in which the oxidation-
 state of  at  least one  reactant  is  raised  while  that of  another is lowered.   In
                                      10-52

-------
                  TABLE 10-14.  AIR STRIPPING COST ESTIMATES
                 (Basis:  700 gpm; 1000 micrograms/liter TCE)

Induced-Draft
Stripper
(75% Removal)
Air Stripping Equipment
Stripper Assembly & Installation
Equipment Sub-total
Recharge Pump; Assembly and Controls
Found at ion/ Sump
Equipment Freight
Project Management
Project Contingency
Total
$15,000
4,000
$19,000
$16,000
18,000
2,000
10,000
7,000
$72,000
9
Packed-Tower
5-ft Diameter
(95% Removal)
$42,300
19,000
$61,300
$16,000
23,700
5,000
20,000
20,000
$146,000

Saigon Model No. 909B (8'0" x 9'1" x 9' 0").
2
 Tower is made of fiberglass reinforced plastic and contains 15 ft.  of 2-in.
 diameter polypropylene pall ring packing.
3
 Cost includes tower, packing, packing support, detnister, 4,000 cfm fan with
 10 hp motor, damper, piping valves, and ductwork.
4
 Sump 5"  x 5" x 8'  below grade concrete.

Source:  O'Brien and Stenzel, undated.
                                     10-53

-------
chemical oxidation, the oxidation state of the treated compound(s) is raised.
For example in the conversion of cyanide to cyanate under alkaline conditions
using permanganate, the oxidation state of the cyanide ion is raised as it
combines with an atom of oxygen to form cyanate.  This reaction can be
expressed as follows:

     2 NaCN + 2KMnO,  + KOH    2 K MNO,  + NaCNO + H_0

     Common commercially available oxidants include potassium permanganate,
hydrogen peroxide, calcium or sodium hypochlorite and chlorine gas.


          10.1.11.2  Applications/Limitations


     Chemical oxidation is used primarily for detoxification of cyanide and
for treatment of dilute waste streams containing oxidizable organics.  Among
the organics for which oxidative treatment has been reported are:  aldehyde,
mercaptans, phenols, benzidine, unsaturated acids and certain pesticides
(Kiang and Metry, 1982).

     Chemical oxidation can be an effective way of pretreating wastes prior to
biological treatment; compounds which are refractory to biological treatment
can be partially oxidized making them more amenable to biological oxidation.

     One of the major limitations with chemical oxidation is that the
oxidation reactions frequently are not complete (reactions do not precede to
C0_ and HLO) .  Incomplete oxidation may be due to oxidant concentration, pH,
oxidation potential of the oxidant, or formation of a stable intermediate
(Kiang and Metry, 1982).  The danger of incomplete oxidation is that more
toxic oxidation products could be formed.  Chemical oxidation is not well
suited to high-strength, complex waste streams.  The most powerful oxidants
are relatively non-selective and any oxidizable organics in the waste stream
will be treated. For highly concentrated waste streams this will result in the
need to add large concentrations of oxidizing agents in order to treat target
compounds.  Some oxidant such as potassium permanganate can be decomposed in
the presence of high concentrations of alcohols and organic solvents (Kiang
and Metry, 1982).


          10.1.11.3  Design Considerations


     Equipment requirements for chemical oxidation are simple and include
contact vessels with agitators to provide suitable contact of the oxidant with
the waste, storage vessels and chemical metering equipment.  Some
instrumentation is required to determine pH and the degree of completion of
the oxidation reaction.  Some oxidizing reagents react violently in the
presence of significant quantities of readily oxidizable materials.  Therefore
reagents must be added in small quantities to avoid momentary excesses.
                                     10-54

-------
          10.1.11.4  Technology Selection/Evaluation


     Oxidation reactions can be carried out using simple, readily available
equipment; only storage vessels, metering equipment, and contact vessels with
agitators are required.  However, implementation is complicated because every
oxidation/reduction reaction system must be designed for the specific
application.  Laboratory- and/or pilot-scale testing are essential to
determine the appropriate chemical feed rates and reactor retention times in
accordance with reaction kinetics.  Oxidation and reduction has not been
widely used in treating hazardous wastestreams.

     A major consideration in electing to utilize oxidation technology is that
the treatment chemicals are invariably hazardous, and great care must be taken
in their handling.  In particular, the handling of many oxidizing agents is
potentially hazardous and suppliers'  instructions should be carefully
followed.

     In some cases, undesirable byproducts may be formed as a result of
oxidation.  For example, addition of chlorine can result in formation of
bio-resistant end products which can be odorous and more toxic than the
original compound.  The possibility of this undesirable side reaction needs to
be considered when using chlorine for oxidation of wastewaters (Conway and
Ross, 1980).
          10.1.11.5  Costs
     Capital costs for chemical oxidation include costs for chemical storage,
chemical feeding and chemical mixing.  These costs can be approximated using
Figure 10-7.  Chemical costs are listed in Table 9-10.
     10.1.12  Chemical Reduction


          10.1.12.1  General Description


     Chemical reduction involves addition of a reducing agent which lowers the
oxidation of a substance in order to reduce toxicity or solubility or to
transform it to a form which can be more easily handled.  For example, in the
reduction of hexavalent chromium (Cr(Vl)) to trivalent chromium (Cr(lll))
using sulfur dioxide the oxidation state of Cr changes from 6+ to 3+ (Cr is
reduced) and the oxidization state of S increases from 2+ to 3+ (S is
oxidized).  The decrease in the positive valence or increase in the negative
valence with reduction takes place simultaneously with oxidation in chemically
equivalent ratios (Kiang and Metry, 1982).
                                     10-55

-------
                          + 3S02 + 3H20    Cr


     Commonly used reducing agents include sulfite salts (e.g. sodium
bisulfite, sodium metabisulfite, sodium hydrosulfite) sulfur dioxide and the
base metals (iron, aluminum and zinc).


          10.1.12.2  Applications/Limitations


     Chemical reduction is used primarily for reduction of hexavalent
chromium, mercury and lead.  There are currently no practical applications
involving reduction of organic compounds.


          10.1.12.3  Design Considerations


     Very simple equipment is required for chemical reduction.  This includes
storage vessels for the reducing agents and perhaps for the wastes, meterring
equipment for both streams, and contact vessels with agitators to provide
suitable contact of reducing agent and waste.  Some instrumentation is
required to determine the concentration and pH of the waste and the degree of
completion of the reduction reaction.  The reduction process may be monitored
by an oxidation-reduction potential (ORP) electrode (Kiang and Metry, 1982).


          10.1.12.4  Technology Selection/Evaluation


     Chemical reduction is well demonstrated for the treatment of lead,
mercury and chromium.  However, for complex waste streams containing other
potentially reducible compounds, laboratory and pilot scale tests will be
required to determine appropriate chemical feed rates and reactor retention
times.

     Chemical reduction can be carried out using simple, readily available
equipment and reagents.  Capital and operating costs are low and the process
is easy to implement.


          10.1.12.4  Costs
     Capital costs for chemical reduction include costs for chemical storage,
chemical  feeding, and chemical mixing.  These costs can be approximately using
Figure 10-7.
                                     10-56

-------
10.2  Solids Treatment


     10.2.1  Solids Separation


     This section describes equipment and methods used to separate solids from
slurries, and/or to classify contaminated soils or slurries according to grain
size.  The objective of separating solids from slurries is to attain two
distinct waste streams:  a liquid waste stream that can be subsequently
treated for removal of dissolved and fine suspended contaminants; and a
concentrated slurry of solids and minimal liquid that can be dewatered and
treated.

     Classification of particles according to grain size may be undertaken for
one of two reasons.  The first reason is that more efficient use can be made
of equipment and land area by taking advantage of the differences in settling
velocity of different sized particles.  For example, where only limited land
space is available, settling basins may be used to remove sand and gravel with
a high settling velocity and then high rate gravity settlers could be used to
remove fine-grained particles.

     There is recent evidence to suggest that classification by grain size is
important in managing hazardous waste contaminated soils and sediments because
of the apparent tendency of contaminants to adsorb preferentially onto
fine-grained materials such as clay and organic matter.  The separation of
solids by grain size and level of contamination could prove to be extremely
beneficial to the overall management (treatment, transport, and disposal) of
contaminated soil material.  Whereas relatively non-contaminated soils and
sediments may be disposed of in ordinary sanitary landfills or discharged back
into the stream, the highly contaminated solids must be disposed in a hazard-
ous waste landfill, incinerated or treated to render them non-hazardous.

     The most appropriate solids separation method for a given site depends
upon several factors,  including the following:

     •  Volume of contaminanted solids

     •  Composition of soils or sediments, including gradation, percent clays,
        and percent total solids

     •  Types of dredging or excavation equipment used, which determines the
        feed rate to solids separation and,  in the case of slurries,  the
        percent solids

     •  Site location and surroundings.   The available land area and ultimate
        or present land use may limit the type of system that can be  utilized.

     Solids separation methods addressed in this section include:   sieves and
screens,  hydraulic and spiral classifiers, cyclones,  settling basins  and
clarifiers.
                                     10-57

-------
     Many of the methods presented in this section are discussed in terms of
their ability to treat soils slurries or sediments containing particle within
a specific size range.  Table 10-15 summarizes the particle sizes which
correspond to various soil types.
          10.2.1.1  Screens and Sieves
     Sieves or screens consist of bars, woven wire or perforated plate
surfaces which retain particles of a desired size range while allowing smaller
particles and the carrying liquid to pass through the openings in the
screening surface.  Several types of screens and sieves have application for
solids separation at hazardous waste sites.
               a.  Grizzlies

     General Description—Grizzlies consist of parallel bars which are
frame-mounted on an angle to promote materials flow and separation.  Hoppers
are provided beneath the grizzly to collect removed material.  Bar spacing is
generally 1 to 5 inches apart depending upon the desired separation.  Both


     TABLE 10-15.  APPROPRIATE PARTICLE SIZES FOR VARIOUS SOIL CATEGORIES
     USCS Classification                U.S. Standard Sieve Size
     Gravel
          Coarse                        >3/4 in.
          Fine                          No. 4 - 3/4 in.
     Sand
          Coarse                        No. 10 - No. 4
          Medium                        No. 40 - No. 10
          Fine                          No. 200 -No. 40
     USCS Classification                Particle Size (u)

     Silt                               10 - 74
     Coarse Clay                        1.0 - 10
     Fine Clay                          <1.0
                                     10-58

-------
 fixed and vibrating grizzlies are available.  Grizzlies generally have a
 maximum width of 6 to 9 feet and a length of 12 to 18 feet (Mallory and
 Nawrocki, 1974).

     Applications/Limitations—Grizzlies are used primarily for scalping,
 i.e., removing a small amount of oversized material from a stream which is
 predominantly fines.  They are generally limited to separating materials which
 are 2 inches in diameter or coarser.  Another major function of the grizzly  is
 to reduce velocity of a slurry for subsequent processing operations (Mallory
 and Nawrocki, 1974).

     Technology Selection/Evaluation—Grizzlies offer a reliable method for
 removing coarse-grained material from slurries.  By doing so, they
 significantly improve the reliability and performance of subsequent solids
 separation methods and also reduce maintenance costs by minimizing the amount
 of abrasive material which reaches the screen, cyclone, etc.  Grizzlies
 contain no moving parts and are tough and abrasion resistant.  Therefore
 maintenance requirements are minimal.  Space requirements are also minimal and
 they can be installed in almost any area.  They can easily be arranged in
 series or parallel to accommodate very high flows or achieve classification  of
 coarse materials.
               a.  Moving Screens

     General Description—Screening of fine particles  from dry materials is
 frequently accomplished using moving  screens.  Types of moving screens
 include:

     •  vibrating screens

     •  revolving screens
     •  gyratory screens

     Vibrating screens are more widely used than other screen types,
 particularly for fine particle separation, because of  their larger capacity
 per unit of screen area and their higher efficiency (Perry and Chilton, 1973).
 Only the vibrating screen will be described in this section.

     Vibrating screens consist of a plane screening surface, usually stretched
 tautly and set into a rectangular frame having sufficient sidewalls to confine
 the material flow.  Figure 10-13 illustrates a typical vibrating screen.  They
may be composed of one, two or three  screening decks.  This allows for
 progressively finer separation and lower space requirements.  Screens are
 usually inclined at a slope of approximately 20ฐ from horizontal, although
 horizontal screens are also available.  Vibration is produced by circular
motion in a vertical plane.  By vibration, the bed of material tends to
 develop a fluid state.  Larger particles remain on top of the bed while
 smaller particles sift through the voids and find their way to the bottom.
Once the fine particles have sifted through the bed of material,  the vibrating
 action increases the probability that the small particles will pass through


                                      10-59

-------
                  FIGURE 10-13. TYPICAL VIBRATING SCREEN
           Screening Surface
             Discharge End
                                                             Feed End
Source: Allis-Chalmers Corp., undated.
                                         10-60

-------
the  screen.  An  inclined  screen  allows  the  material  to cascade down the screen
surface,  increasing  the probability  that  small  particles will pass through
(Allis Chalmers, undated).

     Vibrating screens typically range  in size  from  about 3 to 10 feet wide
and  6 to  30  feet long.  Solids handling capacity ranges from 300 to 950 tph.

     Applications/Limitat ions—The  function of  vibrating screens is to
separate  particles by grain  size.   The  oversized particles are substantially
dewatered during the separation.  Typically,  vibrating screens are used to
separate materials in the  size range  of 1/8 inch up  to 6 inches.  However,
high speed vibrating screens are  also available for  separating finer particles
in the size  range of 4 to  325 mesh  (Chilton and Perry, 1973;  Mallory and
Nawrocki, 1974).  Although separation efficiencies are high with the vibrating
screen,  some fine particles  are  invariably  carried over with the coarse
particles.   Conventional vibrating  screens  are  best  suited for handling dry
materials.  Wet  or sticky  materials  tend  to blind the  screen.   Larger openings
can be used where blinding is a  problem,  but  this reduces the efficiency of
the  size  separation.  Vibrating  screens with  heated  decks are also available
to reduce moisture content,  although  they are not cost-effective for waste
streams with a high moisture content.   Because  of these limitations, the
conventional vibrating screens are  not  well suited for handling dredge
slurries.  Where the moisture content of  the  material  is high resulting in
blinding  wet screening with  sprays  can  be used.  Water is generally sprayed at
3 to 6 gpm per ton at a minimum  of  20 psi to  discourge blinding (Allis
Chalmers, undated).

     The  presence of abrasive material  in the feed may result in the need for
frequent  screen  replacement.  Therefore,  wastes should be carefully
prescreened using a  grizzly  or wedge-bar  screen.

     Relative to other types of moving  screens, vibrating screens generally
are  the most efficient, have lowest  space requirements and lowest maintenance
costs.  Vibrating screens  are the most  efficient of  the moving screens for
separating solids according  to grain  size.   However, their reliability is
adversely affected by the  fact that wet or  sticky materials tend to blind the
screen.   A water spray applied to a vibrating screen can significantly reduce
blinding.  The effectiveness of vibrating screens should be determined on a
case-by-case basis.

     The  presence of abrasive material  can  result in the need for frequent
screen replacement thereby increasing maintenance costs.

     Vibrating screens are relatively compact.   They can be installed in areas
where space is limited and are well suited  for  use in  mobile  treatment
systems.
     Cost—Costs for vibrating screens vary with  the  size  and  capacity  of the
screens,  The capital cost for a 10-ft. long, 5-ft. wide,  5-ft.  high  screen
with a capacity of 200 TPH is about $25,000.  Operation  and maintenance costs
                                     10-61

-------
for vibrating  screens  are relatively low compared  to  other  types of moving
screens (Allis  Chalmers,  undated;  Derrick Manufacturing  Corp.,  undated).


                c.   Stationary or fixed screens


     Stationary or  fixed  screens differ from moving  screens in  that they
posess no moving parts.   A continuous curved surface  and the  velocity of the
slurry across  the  surface provide  a centrifugal  force which holds the slurry
against the  screens  and  allows for separation.   One  type of fixed screen which
has potential  application for solids separation  at hazardous  waste sites is
the wedge-bar  screen or  bend-sieve.  A typical wedge-bar screen is illustrated
in Figure 10-14.  The  hydrosieve,  a modified wedge-bar  screen which uses water
pressure to  encourage  solids separation is also  used.

     General Description—The wedge-bar screen is  similar in  design to a
grizzly insofar as  it  consists of  parallel bars  which are frame-mounted on a
curved deck.   However, in the case of the wedged bar  screen,  bar spacing is
very close to  effect fine particle separation.   As the material enters the
feed inlet,  a  series of  baffles in the feed box  spread  the  material so that
the slurry is  evenly fed  over the  width of the curved screen  deck.  The slurry


                       FIGURE 10-14. WEDGE BAR SCREEN

                              Self-Adjusting Feed Baffle	
             Screen Retainer
                                                            Screen
                                                            Surface
                            _.      ^.  ,           Undersize Discharge
                            Oversize Discharge
             Source: Dorr-Oliver, 1983

                                      10-62

-------
flows through the  feed  inlet  at  the  top  of  the  feed  box and  flows  tangentially
down the surface of the  screen.  The  continuous curved  surface  together  with
the velocity across the  surface  provides  a  centrifugal  force which holds the
slurry against the screen  surface.  As the  slurry  strikes  the sharp edge of
the wedge bar, small particles are sliced off and  directed downward through
the slots along with most  of  the liquid.  Dewatered,  oversized  material  slides
on top of the screen surface  and is discharged.  The slicing action of the
wedge bars sizes the undersize particles  at  a smaller dimension than the slots
themselves and helps to  minimize blinding.   For example,  for a  slot width of 1
mm, the thickness of the slurry  layer being  shaved off  is  about 1/4 mm.   This
1/4 mm thick cut can transport particles  of  up to  1/2 mm  in  size;  plus 1/2 mm
solids pass over the screen (Hoffman-Muntner Corporation., 1978; Dorr-Oliver,
1980; Dorr-Oliver, 1983).

     Wedge-bar screens  normally  come  in  sizes of 2 to 6 feet wide, with
capacities of 30 to 200  gpm/ft .

     The hydrosieve or  pressure  screen is a  modification  of  the conventional
wedge-bar screen in which  the pressure of a  water  spray encourages more
efficient separation.   The water pressure helps to remove  fines that are
adhering to coarse grain sized materials  and breaks  up  clumps of material
which tend to clog the  screen.   Hydrosieves  with capacities  of  up  to 1500 gpm
are available.

     Application/Limitation—Wedge-bar screens and hydrosieves  are used  to
separate particles in slurry by  grain size.  The wedge-bar screen  is generally
less efficient in separating  solids  than  the vibrating  screen;  the oversized
material typically carries a  considerable amount of  fines.   The hydrosieve
minimizes this problem  by  employing a pressure spray which washes  the fines
from the coarser material.  Wedge bar screens may  be used  ahead of vibrating
screens.  This provides  a  higher solids  separation efficiency than the
vibrating screen alone  (Allis Chalmers, undated).

     Technology Selection/Evaluation—The wedge-bar  screen offers  a very low
cost method for separating solids according  to grain size.   However, the
effectiveness of the separation  methods  is not as  good  as  that  achieved  using
vibrating screens or cyclones.   Nevertheless, use  of a  water spray with  a
wedge-bar screen (hydrosieve) can significantly improve separation efficiency
by removing fines which  are sorbed to sands  and gravel.  The wedge-bar screen
contains no moving parts and  is  extremely easy to  operate  and maintain.   It is
also more resistant to  abrasion  than  the vibrating screen.   It  is  compact and
requires a minimal amount  of  space.

          10.2.1.2  Hydraulic Classifiers


               a.  General Description
     Hydraulic classifiers are commonly used to  separate  sand  and  gravel  from
slurries and classify them according to grain  size.  A  typical hydraulic
classifier is shown in Figure 10-15.  These units  consist  of elevated

                                     10-63

-------
DC
Ul
CO
CO
o
u
DC
Q
>


in

6

m
DC
D
O
                                                                                         I
                                                                                         c
                                                                                         o
               I
                                                                                         3
                                                                                         O
                                                                                         to
                                             10-64

-------
 rectangular  tanks with v-shaped  bottoms  to  collect  the material.   Discharge
 valves which are located  along the  bottom of  the  tank are  activated  by motor-
 driven vanes that sense the  level of  solids as  they accumulate.   The principal
 of  operation is simple.   The slurry is  introduced into  the feed end  of the
 tank.  As  the slurry  flows to the opposite  end, solids  settle out according  to
 particle size as a  result of differences in settling velocity.  Coarse
 materials  settle out  first near  the feed end  and  materials are progressively
 finer along  the length of the tank.   Manually adjusted  splitter gates below
 the discharge valves  can  be  used to selectively direct materials  of  specific
 grain sizes  to subsequent handling  and  treatment  (Eagle, 1981; Mallory and
 Nawrocki,  1974).  Classifying tanks are generally available  in sizes ranging
 from 8 to  12 feet wide and 20 to 48 feet long (Mallory  and Nawrocki, 1974).
 Solids handling capabilities are generally  limited  to 250  to 350  tph (Mallory
 and Nawrocki,  1974; Eagle Iron Works, 1981).


               b.   Applications/Limitations
     Hydraulic classifiers are used  to remove  sand  and gravel  size  particles
 from slurries and  to classify the removed materials according  to grain  size.
 Materials are recovered  from the classifier  at  about  30 percent moisture
 content (Written communication, 1984 Eagle Iron Works, Des Moines,  Iowa).
 They are capable of removing and classifying materials within  the size  range
 of 3/8 inch down to about 150 to 200 mesh (105  to 74 microns)  (Mallory  and
 Nawrocki, 1974; Eagle Iron Works, 1981).  The  upper limitation of 3/8 inch  is
 handled by prescreen- ing the wastes to remove  all  large materials.  Other
 solids separation  techniques are required to classify the fine-grained
materials ซ200 mesh).  Another limitation is  that  some fines  will  be removed
 with the sand and  gravel fraction.  This limitation is frequently overcome  by
 directing the solids to a spiral classifier  where they are washed to remove
 the fine-grained materials (see Section 10.2.1.3).  Hydraulic  classifers have
 a relatively low solids handling capacity and  are not well suited for handling
 large volumes of flow or high-solids concentrations.  A single average  sized
 tank with dimensions of 36 feet by 10 feet,  for example, can handle 5300 gpm
 when separating material down to 100 mesh and  only  1400 gpm when separating
material down to 200 mesh (Eagle Iron Works, 1981).

     Because of the inability of hydraulic classifiers to handle large  volumes
 of flow, a combination of solids separation methods may be advisable to reduce
 the number of hydraulic classifiers needed for  a large solids  handling
operation.  One possibility for reducing the number of classifers needed would
be to use these units to separate only those particles larger  than  105
microns.  Cyclones, hydrocyclones, or hydrosieves (see Sections 10.2.1.4 and
 10.2.1.1) could then be used to remove the fine sand fraction  (Mallory  and
Nawrocki, 1974).


               c.  Technology Selection/Evaluation

     Hydraulic classifers offer an effective method for operating and
classifying particles ranging in size from fine gravel to fine sands.   Some

                                     10-65

-------
fines are inadvertently  removed with  the  sand  and  gravel,  and the effective-
ness of the separation can be  improved by washing  the  collected  solids in a
spiral classifier to remove  the fines.

     Hydraulic classifier tanks are generally  designed and sized to be truck
mounted for mobile system applications.   Start-up  and  shut-down  can be
accomplished quickly.  Maintenance requirements  are  fairly simple.

     Use of hydraulic classifiers can be  easily  integrated with  other solids
separation methods and this  is advisable  where large flows are involved or
where classification of  fine-grained  materials (clays, silts) is required.
               d .  Co s t s

     Costs for hydraulic classifiers vary with  size  and  capacity of the
classifier.  For a size range of 24 to 49 feet  long,  8 to  12  feet  wide, and 8
feet deep; and a feed rate of 200 to 350 TPH, the  initial  cost  ranges from
$30,000 to $76,000 (Eagle Iron Works, 1981; Mallory  and  Nawroki,  1974).
          10.2.1.3  Spiral Classifier
               a.  General Description
     The spiral classifier consists  of  one  or  two  long,  rotating screws,
mounted on an incline within a rectangularly shaped  tub.   It  is  used  primarily
to wash adhering clay and silt from  sand  and gravel  fractions.   Figure 10-16
shows a typical configuration of a spiral classifier.

     The screw conveys settled solids from  a hydraulic  classifier (Section
10.2.1.2) up an incline to be discharged  through an  opening  at  the top of the
tub.  Fines and materials of low specific gravity  are  separated  from  sand and
gravel through agitation and the abrading and  washing  action  of  the screw, and
are removed along with the wastewater overflow at  the  bottom  of  the tub.   The
tumbling and rolling action caused by the continuous screw grinds particles
against each other and removes the deleterious material  coating  the sand
particles.  This tumbling action also aids  in  dewatering materials by breaking
the moisture film on the sand particles.  As the moisture  is  relieved of
surface tension, it is free to drain from the  material  (Eagle Iron Works,
1982).  The sands which are finally  discharged are substantially dewatered.

     In general, the greater the length of  the tub the  higher the degree  of
dewatering and the greater the screw diameter  the  larger the  capacity of  the
spiral classifier (Eagle Iron Works, 1982).  Classifiers are  available which
are capable of handling up to 950 tph.
                                      10-66

-------
DC
UI
V)
W
u
(B

6
                                           10-67

-------
               b.  Applications/Limitations


     Spiral classifiers are used primarily to wash, dewater,  and  classify
sands and gravels up to 3/8 inch in diameter.  They are not a  singularly
viable solids separation technology, but they are effective when  used  together
with the hydraulic classifier.  Spiral classifiers have a  large capacity and
are completely portable.


               c.  Technology Selection/Evaluation


     Spiral classifiers improve the efficiency of solids separation  achieved
with the hydraulic classifier by removing fine grained materials  attached  to
coarser particles.

     Spiral classifers are generally designed to be trailer mounted  for use  in
mobile treatment systems.  Start-up and shut-down can be accomplished  quickly
and maintenance requirements are simple.
               d.  Costs

     Costs for spiral classifiers vary with  size  and  configuration.   For a
size range of 22 to 34  feet long, 8 to 19  feet wide,  and  8  to  12  feet high the
initial cost of a spiral classifier ranges from $14,000 to  $77,000 for a
single-screw-type; and  from $37,000 to $150,000 for a double-screw-type.
Operational and maintenance costs vary with  the type  of power  utilized;  it can
be electricity, gas, or diesel  fuel (Eagle Iron Works, 1982; Mallory  and
Nawroki, 1974).


          10.2.1.4  Cyclones and Hydrocyclone


               a.  General Description


     Cyclones and hydrocyclones are separators in which solids that are
heavier than water are  separated by centrifugal force.  The major components
of a hydrocyclone are shown in  Figure 10-17.  A hydrocyclone consists of a
cylindrical/conical shell with  a tangential  inlet for feed, an outlet for the
overflow of slurry, and an outlet for the  underflow of concentrated solids.
Cyclones and hydrocyclones contain no moving parts.   The  slurry is fed to the
unit with sufficient velocity to create  a  "vortex" action that forces the
slurry into a spiral and, as the rapidly rotating liquid  spins about  the axis
of the cone, it is forced to spiral inward and then out through a centrally
located overflow outlet.  Smaller-sized  particles remain  suspended in the
liquid and are discharged through the overflow.   Larger and heavier particles
of solids are forced outward against the wall of  the  cone by centrifugal force


                                     10-68

-------
                FIGURE 10-17. TYPICAL CYCLONE
Feed
                                               Overflow
                                             Air Core
                                               Vortex  Finder
                            Underflow
 Source: Krebs Engineers, undated
                              10-69

-------
within the vortex.  The solids spiral around the wall of the cyclone and exit
through the apex at the bottom of the cone (Dorr-Oliver, 1984).

     Cyclones are available in an extremely wide range of sizes.  The smallest
units handle flows of only a few gallons per minute, while the largest units
can handle between 2000 and 7000 gpm, depending upon slurry composition
(Dorr-Oliver, 1984; Krebs Engineers, undated).  However, cyclones do not
scale-up as many other equipment types do.  In general, the larger the cyclone
diameter and inlet, the coarser the separation and the greater the cyclone
capacity.  The smaller the diameter and inlet, the finer the separation and
the lower the hydraulic capacity.  In order to remove small particles from
large volume slurries, it is necessary to use multiple, small-diameter
cyclones connected in parallel.  Banks of multiple cyclones, manufactured as a
single unit with a single feed pipe, are commercially available.

     Cyclones can also be connected in series or in various staging arrange-
ments to accomplish different objectives.  For example, a high degree of
particle size separation can be achieved by employing a bank of cyclones in
series with decreasing cyclone size and particle size removal in the direction
of flow.  It is also possible to achieve a higher underflow concentration and
a more clarified overflow by staging the cyclones.  The first stage of
cyclones could be used to classify the solids according to the desiged grain
size.  The second stage overflow cyclone could serve as a clarifier and the
underflow cyclone could serve as the concentrator.  However, the maximum
underflow concentration achievable with cyclones is about 60 percent, since
some liquid is necessary for solids discharge (Dorr-Oliver, undated).

     It should be noted that cyclones are available which can handle some
variation in flow rate and particle size by interchanging certain parts of the
cyclone.  For example, it is possible to add or delete sections to the cone,
or to change the size of the vortex finder.


               b.  Applications/Limitations


     Cyclones are available for separating or classifying solids over a broad
particle size range, from 2000 microns down to 10 microns.  However, in
hazardous waste site applications they would be used primarily to remove
smaller size particles from slurries and in situations where a sharp
separation by particle size is needed.  They are particularly applicable to
situations where space is limited.

     Cyclones are generally not effective for slurries with a solids
concentration greater than 30 percent, for highly viscous slurries, or for
separation of particle sizes with a specific gravity of less than about 2.5 to
3.2 (Krebs Engineers, undated).  Slurries with a high clay content exhibit
high pseudoplasticity or high viscosity and cannot be effectively removed
using cyclones or hydrocyclones (Oklahoma State University, 1973).
                                     10-70

-------
     Cyclones are highly vulnerable to clogging by oversized particles, and a
high degree of prescreening (or use of progressively smaller cyclones in
series) may be needed to avert clogging.


               c.  Technology Selection/Evaluation


     Cyclones offer an effective means of separating and classifying solids
over a broad range of particle size, provided the solids concentration is not
too high and the slurry is not too viscous.  Cyclones are flexible insofar as
they can easily be arranged in parallel to accomplish fine size separation, or
in various series or staging arrangements to improve classification of the
overflow or concentration of the underflow.  They can also be easily
integrated with other solids separation methods.  However, each individual
cyclone is capable of handling only very limited variations in flow rate and
particle size.

     The capital and operating costs of cyclones are relatively low.  They are
simple to operate and easy to maintain since they contain no moving parts.
Liners require periodic replacement but this can be done easily.

     Cyclone assemblies take up less space than most solids separation
equipment and are well-suited for tight locations.  Because of their
compactness and simplicity of operation, cyclones are also well-suited for
inclusion in mobile treatment systems.
               d .  Co s t s

     The cost of cyclones varies widely according to the size and the number
of cyclones placed in series.  The feed rate can vary from a few gallons per
minutes up to several thousand gallons per minute, and the size of each
cyclone can vary from 1/2 inch to 30 inches in diameter.  Initial costs for
cyclones can be as low as $5,000 and indefinately high, depending on the
configuration (Hoffman Muntnor Corp., 1978; Krebs Engineers, undated).


     10.2.1.5  Settling Basin

     A settling basin, as described in this section, is an impoundment, basin,
clarifier, or other container that provides conditions conducive to allowing
suspended particles to settle from a liquid by gravity or sedimentation.  The
slurry is introduced into the basin and settling of solids occurs as the
slurry slowly flows across the length of the basin.  Flow out of the opposite
end of the basin is reduced in its solids content.

     The size of an impoundment basin or clarifier is ideally determined by
dividing the critical settling velocity by the overflow rate.  The critical
settling velocity is a function of the diameter, and specific gravity of the
smallest particle size requiring removal and the viscosity of the water.
                                     10-71

-------
However, ideal settling conditions are never achieved and  the actual design  of
the required surface area must make allowance for turbulence, short
circuiting, and scour velocity.  Detailed procedures for sizing  sedimentation
basins can be found in most wastewater engineering handbooks.

     Settled solids accumulate on the bottom of settling basins  where  they are
temporarily stored.  As the volume of accumulated solids increases, the
effective size of the basin decreases, reducing the basin's effectiveness or
efficiency.  Accumulated solids must be periodically or continuously removed
in order for the basin to perform as intended.

     Commonly used types of settling basins are described  below:

               a.  Impoundment Basin

     General Description — An impoundment basin  is an earthen  impoundment or
diked area that is lined in a manner that is appropriate for protecting
underlying groundwater.  An adjustable weir is provided to control  overflow
rate.  A typical impoundment basin is illustrated in Figure 10-18.

     Multiple basins, or bulkheads that separate  a single  basin  into
compartments can be used in parallel to allow continuous sediment/water
separation while accumulated solids are being removed from individual  basins.
Multiple basins can also be connected in  series in order to separate solids
according to grain size.  Each basin would be designed to  retain sediments of
increasingly smaller grain size.

     Applications/Limitat ions — Impoundment basins are used to  remove
particles in the size range of gravel down to fine silt (10 to  20 microns with
flocculants) (Mallory and Nawrocki, 1974).  They  are also  used  to provide
temporary storage of dredged material and to classify sediment  particles
according to grain size.

     Impoundment basins are particularly  well-suited for large-scale dredging
operations, provided there is adequate land space available for  their
construction.  They are not suitable for  congested areas,  or for areas where
adequate measures cannot be taken to protect groundwater supplies (e.g., high
groundwater table).

     A major limitation with the use of impoundment basins is that  unlike
clarifiers, they have no mechanism for solids collection.   Therefore,
mechanical dredges (e.g., clamshells, backhoes) are typically used  to  remove
the  settled solids.  This greatly increases the operational costs associated
with use of impoundment.
               b.   Conventional  Clarifers

     General Description  — Conventional clarifers  are  rectangular or circular
 settling basins which  are typically  equipped  with built-in solids collection
 and  removal mechanisms.
                                      10-72

-------
                              FIGURE 10-18.
 CONCEPTUAL DIAGRAM OF A DREDGED MATERIAL CONTAINMENT AREA
                      MOUNDED COARSE-GRAINED
                      DREDGED MATERIAL
                                DEAD ZONE
                             AREA FOR SEDIMENTATION
                                        .DEAD ZONE
                                    PLAN
        PONDING DEPTH.


    FOR^DlMEf'jfAfioN"
                                                         FREEBOARD
                                   FOR HNE-GRANED
                               DREDGED MATERIAL STORAGE
COARSE-GRAINED
DREDGED MATERIAL
 CLAY LINER SYSTEM
                                                             EFFLUENT
                                                             TO TREATMENT
                             CROSS SECTION
Source: Adapted from Palermo et al., 1978
                                10-73

-------
     Typically, in a rectangular clarifier  a  flow with relatively high
suspended solids is introduced at one end of  the  clarifier,  solids settle
along the length of flow, and a flow with relatively  low suspended solids
leaves the clarifiers through trough-type overflow weirs.   In  most rectangular
clarifiers flights extending the width of the  tank move the  settled sludge
toward the inlet end of the tank.  Some designs move  the sludge toward the
effluent end of the tank, corresponding to  the direction of  flow of the
density current.

     Circular clarifiers are of two general types.  With the center feed type,
the waste is fed into a center well and the effluent  is pulled off at the weir
along the outside.  With a peripheral feed  tank,  the  effluent  is pulled off at
the tank center.

     Figure 10-19 illustrates a center feed type  clarifier.  The circular
clarifer can be designed for center sludge withdrawal or vacuum withdrawal
over the entire tank bottom.
                        FIGURE 10-19. CIRCULAR CLARIFIER
                      Walkway truss
                                                      Skimmer

                                                     ,	\
                                             Influent pipe
                                                               Side water
                                                               depth
         Source: Dorr-Oliver, 1976

     Many clarifiers are equipped with  separate  zones for chemical mixing and
precipitation, flocculation  and  settling.


     Applications/Limitations  — Clarifiers  are  able to remove particles down
to 10 to 20 microns (Mallory and Nawrocki,  1974)  in diameter,with the use of
flocculants.  They can  also  be used  to  produce a  thickened sludge with a
solids concentration of about  4  to 12 percent (Metcalf and Eddy, 1979) and to
separate solids by grain size.   This would  be accomplished by connecting
clarifiers in series and providing a retention time sufficient to removal
materials of a certain  grain size.

     Clarifiers are best suited  to small-  to moderate-scale cleanup operations
or to large-scale operations where impoundment basins will not adequately
                                      10-74

-------
protect groundwater supplies.  Clarifiers can be barge mounted for solids
separation during dredging operations.

     Circular clarifiers are generally more efficient in solids removal.
However, rectangular tanks are more suitable for barge-mounting and where
construction space is limited.  In addition a series of rectangular tanks is
cheaper to construct due to the shared wall concept.

               c.  High Rate Clarifier

     General Description — High rate clarifiers use multiple "stacked"
plates, tubes, or trays to increase the effective settling surface area of the
clarifier and decrease the actual surface area needed to effect settling.
Figure 10-20 illustrates a high rate clarifier.  High rate clarifiers allow a
higher flow rate per unit of actual surface area (loading rate) than do
conventional clarifiers, thus the name "high rate" clarifiers.  The trays,
plates, or tubes also induce optimum hydraulic characteristics for sedimen-
tation by guiding the flow, reducing short circuiting and promoting better
velocity distribution.

     High rate clarifiers are able to handle between 2 to 10 times the loading
rate of conventional clarifiers and therefore require limited land use (Jones,
Williams and Moore, 1978).  Package units capable of handling 1,000 to
2,000 gpm are available and are easily transportable by truck or barge.

     Applications/Limitations — High rate clarifiers are best suited to
small- to moderate-scale cleanup operations, or to large-scale operations
where construction of earthen impoundments will not adequately protect
groundwater.  High rate clarifiers are particularly applicable to cleanup
operations where land space is limited and where barge mounting of clarifiers
is required.

     High rate clarifiers are not suitable for removal of particles larger
than 0.1 inch or less than 10 microns.  Use of high rate gravity settlers has
not been demonstrated for applications in solid/water separation and they are
generally used in applications with lower solids concentrations (Mallory and
Nawrocki, 1974).  There is the possibility that cohesive sediments or soils
may clog the channels, tubes, or plates (Jones, Williams and Moore, 1978).

               d.  Technology Selection/Evaluation

     Sedimentation employing impoundment basins and conventional clarifiers is
a well established technology for removing particles ranging in size from
gravel down to fine silt.  However, proper flocculation is essential to ensure
removal of silt-sized paticles.  Sedimentation methods have not been widely
employed for classifying solids according to particle-size.  They can be
expected to be less effective in classifying solids than other methods
described in this section (e.g., classifier, cyclones, and screens).

     Impoundment basins have a high capital and operating cost.  For this
reason their use is generally limited to large-scale cleanup operations.
                                     10-75

-------
                     FIGURE 10-20. HIGH RATE GRAVITY SETTLER
 FLOW DISTRIBUTION ORIFICES
OVERFLOW BOX
                                         DISCHARGE FLUMES


                                                  /FEED BOX
                                                                   FLOCCULATION TANK
                                    SLUDGE HOPPER
                                     (REMOVABLE)
       Source: Parkson Corp., 1984
                                              10-76

-------
Impoundment basins also pose the greatest potential for secondary impacts of
all solids separation methods; contaminants may leach into groundwater if the
liner system is not properly designed and the large surface area of the
impoundment can result in volatilization of contaminants and localized air
pollution problems.

     Impoundment basins require a long set-up time and the need to obtain
construction permits can further delay the start-up of the cleanup operation.
Conventional clarifiers and high-rate clarifiers eliminate some of the
problems associated with impoundment basins.  Operating costs are
substantially less because clarifiers have a build-in solids collection
system.  Clarifiers also pose no threat to groundwater contamination.
However, capital costs associated with the use of clarifiers can also be quite
high for a large-scale cleanup operation.

     Both types of clarifiers can be barge mounted in areas of limited space.
High-rate clarifiers with their relatively small space requirements, may be
the only suitable sedimentation method in congested areas.  Clarifiers and
impoundment basins are easy to operate and maintain.

     10.2.2  Dewatering


     Dewatering is a physical unit operation used to reduce the moisture
content of slurries or sludges in order to facilitate handling and prepare the
materials for final treatment or disposal.  Devices which can be used to
dewater slurries or sludges include gravity thickeners, centrifuges, filters,
and dewatering lagoons.  Selection of the most appropriate method depends on
such factors as the volume of the slurry, solids content of the waste stream,
land space availability and the degree of dewatering required prior to
treatment or disposal.

     Although several of the dewatering methods are extremely effective in
removing water, the solids are often not sufficiently dry to meet requirements
for final disposal, and require further treatment to fixate or solidify the
wastes (Section 10.3).  The contaminated water generated during dewatering
generally contains hazardous constituents as well as several hundred to
several thousand mg/1 suspended solids,  and will require additional treatment
(Section 10.1).
          10.2.2.1  Gravity Thickening


               a.  General Description
     Gravity thickening is generally accomplished in a circular tank, similar
in design to a conventional clarifier.   The slurry enters the thickener
through a center feedwell designed to dissipate the velocity and stabilize the
density currents of the incoming stream (Figure 10-21).  The feed sludge is
                                     10-77

-------
allowed to thicken and compact by  gravity settling.   A sludge blanket is
maintained on the bottom  to help concentrate  the sludge.   The clarified liquid
overflows the tank and the underflow  solids  are raked to  the center of the
tank and withdrawn by gravity discharge  or pumping.   Flocculants are often
added to the feed stream  to enhance agglomeration of the  solids and promote
quicker or more effective settling  (Metcalf  and Eddy, 1979;  Dorr-Oliver,
1981).  Tanks are usually constructed of concrete or steel.

     Gravity thickener size and specifications  depend on  the following
factors:  maximum flow, type of wastes,  pH, volume of solids/day, percent
solids, specific gravity, maximum  particle size, and percent solids required
in the underflow.
               b.  Applications/Limitations
     Gravity thickeners  are  used  to  concentrate slurries and are capable of
achieving a solids concentration  of  approximately 2 to 15 percent (USEPA,
1979).  They generally produce  the  thinnest and least concentrated sludge of
all the dewatering methods described in this section.  The intent in using a
gravity thickener is usually to reduce  the hydraulic load of a slurry that is
to be fed to a more efficient dewatering method,  such as filtration or centri-
fugation.  They also provide a  high  sludge storage capacity.  Conventional
gravity thickeners require large  land areas for operation and therefore are
                       FIGURE 10-21. GRAVITY THICKENER
                                             Coitrteiy Link Btll
                                             SCRAPER BLADES
                                       2 UNDERFLOW
                               ELEVATION
     Source: Gulp, Wesner, and Gulp, 1978
                                      10-78

-------
not applicable where space is restricted.   However, high-rate  gravity
thickeners  designed to provide up  to  15  times the throughput of  a  conventional
thickener are  available and can reduce  land requirements considerably
(Dorr-Oliver,  1981).
                c.   Technology Selection/Evaluation
     Gravity  thickening provides a simple,  low maintenance method  for
concentrating  slurries, thereby reducing  the hydraulic load to  subsequent
dewatering  processes.   They are suitable  for operations where a high degree of
operator  supervision cannot be provided.   Because of the requirements  for a
large surface  area,  localized air pollution and odors may be significant.


                d.   Costs

     Equipment  costs for gravity thickeners are illustrated in Figure  10-22.
Costs are based on  the use of a circular  reinforced concrete basin  and related
drive and motor.

          FIGURE 10-22. GRAVITY THICKENING CONSTRUCTION COSTS, 1975*
                 i
                 o
                 s
                          2  S 4 S6789     ^  34 S 6 T tซ    I  it ปซTซt
                                   100           1,000
                                    Area, ft2

           •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
           (multiply value shown on this figure by 1.908)
           Source: Gulp, Wesner, and Culp, 1978
                                      10-79

-------
          10.2.2.2  Dewatering Lagoons


               a.  General Description


     Dewatering lagoons use a gravity or vacuum assisted underdrainage system
to remove water.  The base of the lagoon is lined with clay plus a synthetic
liner or other appropriate liner material to prevent migration of contaminants
into the underlying soils and groundwater.   At a minimum, the liner consists
of a low permeability clay layer which is several feet thick.  When the lagoon
is no longer in use, the clay liner is excavated and properly disposed of.   In
some instances this design may not be adequate to protect groundwater
supplies.  A combination clay/synthetic liner and a secondary leachate
collection system are required in some instances.

     The underdrainage system can be designed and operated using one of the
following approaches:

     •  Gravity underdrainage - This system consists of a filler material
        (well-graded sand or filter fabric) underlain by a porous free-
        draining gravel layer.  Perforated drainage pipe is embedded in the
        gravel.  The drainage pipe network is designed with flow gradients
        leading towards a central collection point or sump.  Information on
        the hydraulic design of a gravity drainage system can be found in
        Section 5.2.

     •  Vacuum pumping - Vacuum pumping systems can use either pumped wells or
        wellpoints.  Pumped wells with large vacuum pumps may be installed
        directly in the waste material.  Wellpoints may be used, provided they
        are installed to the depth of an underlying sand filter.  Installation
        of wellpoints directly in the sludge, contaminated sediments^ or soils
        is not cost-effective, because it is necessary to space the wellpoints
        very close together in order to dewater low permeability material
        (Haliburton, 1978).  Information on the design of wells and wellpoints
        can be found in Section 5.1.

     •  Vacuum assisted drying beds - Vacuum assisted drying beds use a porous
        media filter plate set above an aggregate filled support plenum which
        drains to a sump.  A relatively small vacuum pump is connected to
        drain a vacuum from the sump.  The vacuum is activated when the volume
        of the slurry has been reduced by half due to gravity drainage.  The
        vacuum holds until the solids crack, allowing air through the bed
        (USEPA, 1982).

     •  Electroosmosis - This technique involves a process in which a direct
        current electrical potential is set-up in the soil by means of
        electrodes.  This electric potential induces the flow of water in the
        pores of the fine-grained sediment or sludge towards the negative
        pole, or cathode.  A line of wells or wellpoints can be installed to
        intercept and remove the water (Mallory and Nawrocki, 1974).


                                     10-80

-------
               b.  Applications/Limitations


     Dewatering lagoons are best suited to large-scale dewatering operations
where the volume of sludge or sediment would require an inordinately large
number of mechanical dewatering units (e.g., filters or centrifuges).  Lagoons
are one of  the more effective dewatering methods.  A gravity dewatering system
is capable  of achieving 99 percent solids removal and a dewatered cake of 35
to 40 percent solids after 10 to 15 days (based on municipal sludges)
(DeRenzo, 1978; USEPA, 1982).  Vacuum assisted systems may be capable of
achieving a dry cake in a shorter retention time.

     The major limitations on the use of dewatering lagoons is that they
require large land areas and long set-up times.  Because of their large
surface area they may not be well suited to areas with heavy rainfall or to
areas where long periods of freezing would prevent dewatering.

     Each of the types of dewatering lagoons described in this section has its
own specific applications and limitations.

     Gravity drainage systems have the lowest operating costs.  However,
dewatering  is achieved at a relatively slow rate and this may result in the
need for more land area than required with the other methods.  Gravity
drainage systems are also more prone to clogging, particularly if the system
is not carefully designed.

     Vacuum pumping or vacuum assisted dewatering beds are capable of
dewatering  at a much more rapid rate than gravity systems.  Vacuum assisted
dewatering  beds reportedly increase the rate of dewatering by about 50 percent
(with a negative pressure of 8 psi or less) (Haliburton,  1978).   However,  they
require a higher degree of maintenance and are considerably more costly to
operate than gravity systems.

     Electroosmosis is a very costly technique which would be limited to
dewatering  of very fine grained (2 to 10 microns), very hazardous and
difficult to dewater solids.
          c.  Technology Selection/Evaluation


     Dewatering lagoons provide an effective means of dewatering solids.  They
are also versatile in that they can provide storage capacity for solids prior
to disposal.  Of all the dewatering technologies they require the largest time
to implement and have the greatest potential for secondary impacts due to
localized air pollution and groundwater contamination.  Operating costs are
higher than other dewatering technologies because of the need to remove the
solids with mechanical dredging equipment.
                                     10-81

-------
          10.2.2.3  Centrifuges


               a.  General Description


     Centrifugal dewatering is a process which uses the force developed by
fast rotation of a cylindrical drum or bowl to separate solids and liquids by
density differences under the influence of centrifugal force.  Dewatering is
usually accomplished using solid bowl or basket centrifuges.  Disc centrifuges
are also available and are mainly used for clarification and thickening.
Figures 10-23 through 10-25 illustrate the three types of centrifuges.

     The operation of the solid-bowl centrifuge is a continuous process.  The
unit consists of a long bowl, normally mounted horizontally and tapered at one
end.  Sludge is introduced into the unit continously and the solids concen-
trate on the periphery.  A helical scroll within the bowl, spinning at a
slightly different speed, moves the accumulated sludge towards the tapered end
where additional solids concentration occurs prior to discharging the solids
(USEPA, 1982a and USEPA, 1979).

     In the basket centrifuge, flow enters the machine at the bottom and is
directed toward the outer wall of the basket.  Cake continually builds up
within the basket until the centrate, which overflows a weir at the top of
this unit, begins to increase in solids.  At that point, feed to the unit is
shut off, the machine decelerates, and a skimmer enters the bowl to remove the
liquid layer remaining in the unit.  A knife is then moved into the bowl to
cut out the cake which falls out the open bottom of the machine.  The unit is
a batch device with alternate charging of feed sludge and discharging of
dewatered cake (USEPA, 1982a and USEPA, 1978).

     In the disc centrifuge, the incoming stream is distributed between a
multitude of narrow channels formed by stacked conical discs.  Suspended
particles have only a short distance to settle, so that small and low density
particles are readily collected and discharged continuously through fairly
small orifices in the bowl wall.  The clarification capability and throughput
range are high, but sludge concentration is limited by the necessity of
discharging through orifices of 0.05 inches to 0.1 inches in diameter.
Therefore, it is generally considered a thickener rather than a dewatering
device (USEPA, 1978) .


               b.  Applications/Limitations


     Centrifuges can be used to concentrate or dewater soils and sediments
ranging in size from fine gravel down to silt.  Effectiveness of
centrifugation depends upon the particle sizes and shapes, and the solids
concentration among other factors.  Data from the dewatering of municipal
sludges (where extensive information is available), indicate that solids
concentrations ranging from about 15 to 40 percent are achievable with the
                                     10-82

-------
                           FIGURE 10-23.
    SCHEMATIC OF TYPICAL SOLID BOWL DECANTER CENTRIFUGE
                                                                   FEED
                                            COVER
 ."•'•." OEWATERE0
.' '•'.'.    SOLIDS
Source: USEPA, 1979
                                10-83

-------
                     FIGURE 10-24.
  GENERAL SCHEMATIC OF IMPERFORATE BASKET CENTRIFUGE
                       FEED
           POLYMER
SKIMMINGS
                                                    KNIFE
               CAKE
                          CAKE
                         10-84

-------
                         FIGURE 10-25.
             SCHEMATIC OF A DISC NOZZLE CENTRIFUGE
                FEED
           EFFLUENT
           DISCHARGE
 FEED
 EFFLUENT
DISCHARGE
CONCENTRATING
CHAMBER
SLUDGE
DISCHARGE
                                                    ROTOR
                                                     BOWL
                                                    ROTOR
                                                   NOZZLES
               SLUDGE
            DISCHARGE
                       RECYCLE FLOW
   Source: USEPA, 1979
                           10-85

-------
solid bowl centrifuge.  For the basket centrifuges the cake solids
concentration typically ranges from about 9 to 25 percent.  Solids capture
typically ranges from about 85 to 97 percent with chemical conditioning, both
for the solid bowl centrifuge and the basket centrifuge.  Disc centrifuges can
concentrate a 1 percent sludge to a 6 percent solids (USEPA, 1978; USEPA
1982a).

     Centrifuges are capable of removing particles as small as 1 micron in
diameter.  However, removal efficiencies are reduced dramatically for
particles smaller than 10 microns (Krizek, Fitzpatrick and Atmatzidis, 1976).

     Although the basket centrifuge does not acheive as dry a cake as does the
solid bowl centrifuge, it has the advantage of being able to handle hard to
dewater sludges and is not significantly affected by grit.  It has the highest
capital cost but lowest operation and maintenance cost of the three centrifuge
types (USEPA, 1979 and USEPA, 1982b) .  A major limitation is that it must be
operated on a batch basis.

     The solid bowl centrifuge is very flexible in that it can handle higher
than design loadings, such as temporary increases in hydraulic loading or
solids concentrations; however, the cake solids content may be reduced.
Higher feed rates make the solid bowl centrifuge better suited for large-scale
dewatering operations.  Maintenance and pretreatment requirements are more
extensive than for the basket centrifuge.  The scroll of the solid bowl
centrifuge is very susceptable to abrasion.  This results in the need to
degrit the effluent (USEPA, 1979 and USEPA, 1982a).

     The disc centrifuge has more limited application at hazardous waste sites
than the other types of centrifuges.  Although it can yield a highly clarified
centrate even without the use of chemicals, the percent solids concentration
is low, maintenance requirements are relatively high, and pretreatment
requirements (grit and fibrous material removal) are extensive.


               c.  Technology Selection/Evaluation


     Centrifugation offers a simple, clean and reliable method for dewatering
sludges and other solids.  They are less effective than filtration methods and
dewatering lagoons, but more effective than gravity thickeners.  Centrifuges
are compact and are well suited to use in mobile treatment systems.

     Although reliable for their intended function,  centrifuges generated a
centrate and a sludge which require further treatment prior to disposal.
Suspended solids levels from centrifugation may be as high as several thousand
parts per million.

     Since centrifugation relies on the settling of particles according to
density, the process tends to classify the solids, settling the heavier
particles first.  Dewatering processes which rely on filtration achieve a more
even distribution of solid capture.  It is possible  for a buildup of fines to
                                     10-86

-------
occur in the effluent from centrifugation, particularly if the centrifuge is
operating improperly due to inadequate solids conditioning or due to a mal-
function (USEPA, 1982a).  Since most organic and inorganic waste constituents
tend to sorb to fine clay and silt particles, this may result in unacceptable
levels of contaminants in the overflow.

     Advantages of centrifuges for thickening and dewatering methods include
relatively limited space requirements and fast start-up and shut-down.  They
also generate little or no air emissions since the process is essentially
enclosed.
               d.  Costs
     This section presents construction and O&M costs for basket and solid
bowl centrifuges.  It should be recognized that the curve for construction
cost is not capital cost.  The curve does not include costs for special site
work, general contractor overhead and profit, engineering, land, legal,
fiscal, and administrative work and interest during construction.  These cost
items are all more directly related to the total cost of a project rather than
the cost of any one of the individual unit processes.  These costs are
therefore most appropriately added following cost summation of the individual
unit processes, if more than one unit process is required.  Typically, these
costs add 35 to 45 percent, depending on project size and complexity, to the
actual construction costs which are shown in the curves (USEDA, 1982a).

     Construction costs include housing for the centrifuges. Housing costs may
not be applicable for hazardous waste sites because of the short time period
the unit will be on-site.

     No costs were available for mobile treatment units involving use of
centrifuges.

     Basket Centrifuge — Figure 10-26 shows construction costs for single and
multiple basket centrifuges with capacities ranging from 4,000 to 700,000 gpd.
Centrifuge costs are for automatic machines operating on a preprogrammed
cycle, an approach which requires only minimal operator attention.

     In addition to the basic machines, the costs include equipment for
polymer preparation, storage, and application.  If other conditioning
chemicals are used, the costs would have to be adjusted accordingly.  The
costs do not include sludge and centrate pumping, sludge conveying, and sludge
storage.  It was assumed that centrifuges are located in two story concrete
block buildings with bottom discharge to trucks or storage bins.  Housing
requirements were developed from equipment manufacturers'  recommended layouts
(USEPA, 1982a).

     Figures 10-27 and 10-28 present O&M costs for basket centrifuges.
Electrical energy requirements were computed from connected and operating
                                     10-87

-------
       FIGURE 10-26. CONSTRUCTION COST FOR BASKET CENTRIFUGES *
i
9

2
1 0.000.
1
•
4
ซ *
i *
i
ซ 1 .000.
1 J
3 1
X 4
<* 3
Z
too.
s
7
•
5
4
3
I





000






000




ooo



































































M • ซ

















illSLE
INIT



I-!!- "























L— *























>













































ฃ
/



















WLTIPL
(UNITS
. , .^r_.--.
s~
'











































S






















x









9 ซ '






















• •
                                 10.000
                                TOTAL tUCHINC CAMCtTY -ป<
                                    1 00.000
                              TOTAL HACHINC CArAC
                                             1 .000,000
           •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
            (multiply value shown on this figure by 1.193)
           Source: USEPA 1982a

horsepower information  provided by equipment manufacturers.   Basket centrifuge
operating horsepower, computed on the basis of  a  complete cycle involving
machine acceleration, sludge feeding, skimming, decelerating, and sludge
plowing, averages  40 to 60  percent of the connected  horsepower.  Electrical
power for polymer  preparation and feeding is included,  but energy for sludge
pumps, centrate pumping and sludge conveying equipment  is not included.

     Maintenance  costs  were obtained from equipment  manufacturers and from
operating installations and represent an industrywide average of annual
expenditures  for maintenance, replacement parts,  lubrication, and other
consumable items  associated with basket centrifuge operation.  Maintenance
material costs  do  not include the cost of polymers.

     Labor requirements for O&M assume 24 hours per  day of operation, with
occasional downtime for maintenance as required.   The major portion of the
operating labor is devoted  to machine start-up  and adjustment, polymer
preparation,  and  required maintenance (USEPA,  1982a) .
                                       10-88

-------
  FIGURE 10-27. BASKET CENTRIFUGES-BUILDING ENERGY, PROCESS ENERGY
                 AND MAINTENANCE  MATERIAL REQUIREMENTS*
                     1  •
                       1000
                       :
                                                 BUILDING
                                                 ENERCY,
                               0.000
                                  s •ritiocoo 2 S 4 9 t re

                                     FCCD sujooe FLOW RATE -utt
                                                   I.OOO.C
                                         100.000       I .OOO.OOO

                                   FEED SLUOflE FLOW HATE -Hurt/Mr
FIGURE 10-28. BASKET CENTRIFUGES-LABOR AND TOTAL ANNUAL OPERATION

              AND MAINTENANCE COST*

00
K
ซ
- 5
)
J
:ป
f
?
B
5
4
0 IOJ
.*
t
3
4
S
i
)OC
s
Si
ฅ *
'!'
- J Z
- 100











00




3



















































„. - -*





_ p* •
















	 •





:: i









,— •





^eL













'


















s
ฃ
7





NTT








TO
C(
	 7
/
s
,'





LABOB
/





000 i 4 MftlOOOO 214 ปซ7i OOOOOt







TAl
ST
-7








/










/
/







f?










.
/T






ฃ '









-------
      It  should  be recognized that operation and maintenance costs will vary
widely depending  on sludge dewatering characteristics  and  specific operating
conditions  related to the installation, and appropriate  adjustment should be
made  if  conditions vary significantly from those  stated  above (USEPA, 1982a).

      Solid  Bowl Centrifuge (High G)—Construction costs  for solid bowl
centrifuges  are shown in Figure 10-29.  Machine throughput is significantly
affected by  the polymer dosage, and therefore the construction cost for a
given feed  rate varies with the polymer dose.  In this figure, single machines
were  assumed  to be used for feed rates up to 500  gpm,  with multiple units
being usedfor higher feed rates.  All machines are equipped with automatically
controlled  eddy current backdrive and have sintered  tungsten carbide conveyor
tips.  Polymer  storage preparation, and feed equipment is  included in the
costs, but  costs  for sludge feed pumping and centrate  pumping are not included
(USEPA,  1982a).
   FIGURE 10-29. CONSTRUCTION COST FOR A HIGH G SOLID BOWL CENTRIFUGES*
1
9
4
3
2
10.000
t
9
4
3
2
I.OOO
2
9
4
3
2
100
1
9
4
9
2





,000




000




^<
000



















.-"


















•*



















r;<





0 1 3 4 91















4

	
j^
ป'' "^^
• •



























j













Ib/ton polymer^yr

>
r
\^








[—









^








/









• 100 2 S 4 9 * f
-Y













/I











™—




n P










!
1

'
lolY"1*
I


















*"*"








1 IOOO 2 3*9 ซTtt IO.OOO
                                      10         100
                                   MUMHC CAHCITr - MOT/W
         •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
          (multiply value shown on this figure by 1.193)
         Source: USEPA, 1982a
                                      10-90

-------
     Operation and Maintenance Cost for solid bowl centrifuges are shown in
Figure 10-30 and 10-31.  Process energy was calculated from information
supplied by a manufacturer of high G centrifuges and assumes use of an eddy
current backdrive.  Energy requirements could be reduced between 5 to 20
percent if the backdrive is not utilized.  Included in the process energy
requirements are the main drive motor, the eddy current backdrive, and equip-
ment required for polymer preparation and feed.  Energy required for feed
sludge pumping and handling of the dewatered sludge is not included.

     Maintenance material requirements include replacement of the conveyor
tips every 30,000 hours of operation, as well as replacement of other
necessary components of the centrifuge and the electrical controls.

     Operation and maintenance labor requirements are based on 24 hours per
day of continuous operation.  Most operational labor is devoted to polymer
preparation and machine start-up and adjustment.  Occasional maintenance is
required for lubrication, with more extensive maintenance required
approximately every 30,000 hours for replacement of the sintered tungsten
carbide conveyor tips.

     The cost curves presented do not include the cost of polymer.  The
polymer dosage is highly dependent on the characteristics of the sludge being
dewatered, and polymer dosage will also have a great influence on the
throughput of the centrifuge.


          10.2.2.4  Filtration


               a.  General Description


     Filtration is a physical process whereby particles suspended in a fluid
are separated from it by forcing the fluid through a porous medium.  Three
types of filtration are commonly used for dewatering:  belt press filtration,
vacuum filtration, and pressure filtration.

     Belt filter presses employ single or double moving belts to continuously
dewater sludges.   As Figure 10-32 illustrates,  the belt press filtration
process includes three stages:  chemical conditioning of the feed, gravity
drainage to a nonfluid consistency and dewatering.  A flocculant is added
prior to feeding the slurry to the belt press.   In the next step, free water
drains from the conditioned sludge.   The sludge then enters a two-belt contact
zone, where a second upper belt is gently set on the forming sludge cake.  The
belts with the captured cake between them pass  through rollers of generally
decreasing diameter.  This stage subjects the sludge to continuously
increasing pressures and shear forces.   Progressively more and more water is
expelled throughout the roller section to the end where the cake is dis-
charged.   A scraper blade is often employed  for each belt at the discharge
point to remove the cake from the belts (USEPA,  1982).
                                     10-91

-------
FIGURE 10-30. HIGH G SOLID BOWL CENTRIFUGES-BUILDING ENERGY, PROCESS ENERGY AND
             MAINTENANCE MATERIAL REQUIREMENTS*
10
I
•
3
4
3
Z
\
\
t
5
4
3
Z
!
&
4
3
Z
•
i!
ป •
2 3
ง *
\
.000.0
: 1
•
3
4
I
000,00
?
•
*
ซ
- jl t
OQ.OQfi
: M
a *
- J 4
' i'
10.000
• !
1- •
ป
4
3
Z
1000
00



0




y
X
'




^
0









r~






x^







/
/
^"'"






*







,

...- —




L-rl*
., ^^






/








X






/
/
















• -7* PROCESS -
• !ป*• ENEROT -
t '











X^BUILOH




M.
           FIGURE 10-31. HIGH G SOLID BOWL CENTRIFUGES-LABOR AND TOTAL
                        ANNUAL OPERATION AND MAINTENANCE COST*
.ooc
!
9
:
•
100
1
4
:
10.
i
•
s
4
3
2
l,(
1
•
ft
4
3
Z
1
.OOO
ป
S
- 4
S
Z
000
: <
9
4
t
OOO
\
•
4
3
I
oo
>'V
r * *
Fr.
a
0













SB!



0













=











^




ae =



34 C







I








.-•^











— *







^








^







s








" *



ป t 00 > ป ซ •

S
,/T
•'








	 •"






OTป











L











cos-









LABOR












• •1000 1 > ซ



1













Tซซ
                                          HID U.UOM FLOW KATI - H>
                                         PEEP SLUOQE FLOW RATE - Htm/m.
     •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
      (multiply value shown on this figure by 1.193)
     Source: USEPA 1982a
                                           10-92

-------
             FIGURE 10-32.   THE THREE BASIC STAGES OF A BELT PRESS
 CHEMICAL
CONDITIONAL
  STAGE
       POLYELECTROLITE
         SOLUTION
GRAVITY
DRAINAGE
 STAGE
                                              COMPRESSION
                                              DEWATERING
                                                 STAGE
SLUDGE•
    CONDITIONED
    SLUDGE
                                                         WASH WATER
 Source: USEPA, 1979
      A vacuum filter consists of a horizontal  cylindrical  drum which rotates
 partially submerged in a vat of sludge (Figure 10-33).   The drum is covered
 with a continuous belt of fabric or wire mesh.   A vacuum is applied to the
 inside of the drum by means of a connection within  a central trunion.   The
 vacuum causes liquid in the vat to be forced  through the filter medium leaving
 wet  solids adhering to the outer surface.  As  the drum  continues to rotate, it
 passes from the cake forming zone to a drying  zone,  and finally to a cake
 discharge zone where the sludge cake is removed  from the media (Metealf and
 Eddy,  1979;  USEPA, 1982).

      Pressure filtration is used to describe  a category of filters in which
 rigid  individual filtration chambers are operated in parallel  under relatively
 high pressure.  The filter press (Figure 10-34),  the most  common represen-
 tative of the group consists of vertical plates  that are held  rigidly in a
 frame  and are pressed together by a large screw  jack or hydraulic cylinder as
 shown  in  Figure 10-34.   The liquid to be filtered enters the cavity formed by
 the  frame.   Pressed against this hollow frame  are perforated metal plates
 covered with fabric filter medium.  The plate  operates  on  a cycle which
 includes  filling, pressing, cake removal, media  washing, and press closing
 (USEPA, 1982a and USEPA,  1979).   As the liquid flows through the filter
                                      10-93

-------
                      FIGURE 10-33.
                ROTARY VACUUM FILTER
            CLOTH CAULKING
                    STRIPS -
    AUTOMATIC VALVE
DRUM



 FILTRATE PIPING


   CAKE SCRAPER
                                          SLURRY AGITATOR

                                         VAT
        AIR BLOW-BACK LINE
                             SLURRY FEED
Source: USEPA, 1979
                          10-94

-------
                                              FIGURE 10-34.
FILTER  PRESS (ILLUSTRATIVE CROSS-SECTIONAL VIEW OF ONE RECTANGULAR CHAMBER)
                 Perforated Backing Plate
              Fabric Filter Medium
                                                                           Inlet Liquid to be
                                                                                Filtered
                                                                       Fabric Filter Medium
            Solid Rectangular
               End Plate
                                                                      Entrapped Solids
                                                                   \
                                                                       Plates and Frames are Pressed
                                                                      Together During Filtration Cycle
                                                                      Rectangular Metal Plate
                        Filtered Liquid Outlet
                                                              Rectangular Frame
              When the cavity formed between plates A and C is filled with solids, the plates are separated.
              The solids are than removed and the medium is washed clean.
              The plates are than pressed together and filtration resumed.
              Source: De Renzo, 1978
                                                    10-95

-------
medium, solids are entrapped and buildup within the cavity until the cavity is
full.  The slurry is dewatered until no filtrate is produced.  The press is
then opened, the dewatered slurry is removed, the plates are cleaned, and the
cycle is repeated (De Renzo, 1978).  In certain applications, the filter media
is precoated with diatotnaceous earth, fly ash, or other filter aids to improve
performance.

     Diaphragm filters are specially designed filter presses.  Instead of the
conventional plate and frame unit in which constant pumping pressure is used
to force the filtrate through the cloth, diaphragm filters combine an initial
pumping followed by a squeezing cycle that can reduce the cost and process
time.
               b.  Applications/Limitations


     Filtration can be used to dewater solids over a wide range of solids
concentrations and particle sizes.  Effectiveness for a particular application
depends on the type of filter, the particle size distribution, and the solids
concentrations.  For dewatering of municipal sludges where considerable
performance data is available, typical ranges for solids content and solids
removal or capture are as follows (USEPA, 1979; USEPA, 1982; Metcalf and Eddy,
1979):

                             SolidsContent (%)    Solids Capture(%)

Belt Press Filtration        15 to 45              85 to 95

Vacuum Rotary Filtration     15 to 35 or 40        88 to 95

Pressure Filter              30 to 50              98

     Manufacturers' data is also available on the performance of filtration
methods in dewatering coal slurries.  This data indicates that belt press and
filter press filtration are capable of producing a filter cake of up to 70 to
80 percent solids.  Also, tests conducted by Rexnord, Inc. demonstrated that
high density dredged materials can be dewatered to a cake solids concentration
of 70 percent using belt press filtration (Erickson and Hurst, 1983).

     Although the filter press achieves a dry filter cake and has the greatest
capacity for solids capture, there are a number of other factors which enter
into the decision to use a particular method of filtration.

     Filter presses generally require larger quantities of conditioning
chemicals than the other filtration methods.  They also have the highest
capital and operating cost and require the largest amount of space.
Replacement of filter media on a filter press is both expensive and time
consuming (USEPA, 1982a).
                                     10-96

-------
     Vacuum filtration is the most energy intensive of  the three methods and
the least effective in dewatering.  Another limitation  on the use of vacuum
filtration is that the incoming feed must have a solids content of at least
3 percent in order to achieve adequate cake formation (USEPA, 1982a).  A big
advantage to vacuum filtration is that because dewatering is accomplished by a
vacuum rather than by mechanical means, the hydraulic throughput is higher
than for the other filter types.  Vacuum filtration has an advantage over belt
press filtration in that it is easier to maintain and can operate effectively
even without optimum chemical conditioning.

     Recent advances in belt press filtration has made  this method nearly as
effective as pressure filtration.  The belt press filter also has the
advantage of being the least energy intensive of the filtration methods.  The
major limitation on the use of this method is that the  process is very
sensitive to incoming feed characteristics and chemical conditioning.  How-
ever, these limitations can be overcome to a certain extent; most belt presses
can be equipped with sensing devices which can be set to automatically shut
off feed flow in the case of underconditioning.  The feed characteristics can
be optimized by carefully prescreening the slurry to remove large objects and
fibrous material which can deteriorate the belt quickly (USEPA, 1982a).


               c.  Technology Selection/Evaluation


     Filtration appears to offer the most effective method for dewatering
slurries.  The processes are generally reliable, provided the slurries have
been properly prescreened and conditioned.   Filtration equipment, particularly
belt press and vacuum filtration, is well suited for inclusion in mobile
treatment systems.  Mobile systems are available from several manufacturers.
However, the maintenance requirements associated with filtration are
significant.  The filter cloth or belts must be periodically replaced and the
filter media periodically washed to remove contaminated solids.

     Despite their effectiveness in dewatering sludges, both the filtrate and
the dewatered sludge are likely to require further treatment prior to
disposal.  The water generated from washing of the filter media will also
require treatment.
               d.  Costs


     This section presents construction and O&M costs for diaphragm,
belt-press and vacuum filters.  It should be recognized that the curve for
construction cost is not capital cost.  The curve does not include costs for
special site work, general contractor overhead and profit, engineering, land,
legal, fiscal, and administrative work and interest during construction.
These cost items are all more directly related to the total cost of a project
rather than the cost of any one of the individual unit processes.  These costs
are therefore most appropriately added following cost summation of the


                                     10-97

-------
individual unit  processes,  if more than one unit  process  is required.
Typically, these costs  add  35 to 45 percent, depending  on project size and
complexity, to the  actual construction costs which  are  shown in the curves
(USEPA 1982a).

     Diaphragm filter press—Construction costs for diaphragm filter presses
ranging in size  from 1,200  to 15,505 ft  are shown  in Figure 10-35.  The
largest machine  manufactured is about 6,000 ft  ,  and multiple presses are
required for  larger press areas.  Construction  costs include the diaphragm
press, feed pump, pumps for the diaphragm and cloth washing, vacuum pumps an
air compressor and  receiver, lime and ferric chloride storage and feed
facilities and all  electrical and controls necessary for  complete automatic
operations.   Housing costs  are also included (USEPA, 1982a),

     Operation and  maintenance costs shown in Figures 10-36 and 10-37 were
developed for a  4 percent  feed of anaerobically digested  sludge, chemically
conditioned with 5  percent  ferric chloride and  a  20 percent lime.  Press
loading was 1.0  Ib/sq  ft/hr, without chemicals, and cake  discharge was taken
at 35 percent.   Press operation time was 19 hours per day, with the remaining
time dedicated to press cleanup and maintenance.


        FIGURE 10-35. CONSTRUCTION COST FOR DIAPHRAGM  FILTER PRESS*
ซ
5
4
3
2
oo.ooo
<
ft
s
4
3
2
I 0.000
1
J
c
5
4
3
2
..000
I
e
5
4
3
2
too.






000






000




000


















































— t—
i

1

















300
< 00


















i







1


1











^




i







i i


U-i--

V
V
'

r 	 1 — r-
|





! ' ' i
1
i ,
y
>\

























.f
<; 	 _]
















1









i i !'
i f











i





1










!







1

i





j
j











t

i





i





i





tป
                               TOtปL FILTER PRESS AREA-ft2
                                 I 00         I 000

                                TOTAL flLTER PRESS AREA-m*
          •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1986
          (multiply value shown on this figure by 1.193)
          Source: USEPA, 1982a
                                       10-98

-------
     FIGURE 10-36.  DIAPHRAGM FILTER PRESS-LABOR AND TOTAL ANNUAL
                   OPERATION AND MAINTENANCE COST*
1
•
s
J
.0010
1
5
I
IQOJM
9
•
*
3
9
2
10X0
1
5
4
S
1
f ป
r 6
1
00
E f
k- ซ
t :
• s
i ,
o 1001
?
ซ
K 9


o itxo
^ !
>- e
"*'
-I5
• 5 *
1000











300



00















































I :
































^


—










X




**














/








-\- -









. *





'








TOTAL
.X
y'
/
<





LAB









CO









OR









>T














ta




















bOOD
                                   100

                                  TOTAL I
 FIGURE 10-37. DIAPHRAGM FILTER PRESS-BUILDING ENERGY, PROCESS ENERGY
              AND MAINTENANCE MATERIAL REQUIREMENTS*
ซ
4
5
J
.
6
S
2
.OOO.OOI
T
5
3
2
100,00
3
4
3
Z
10,000
1
6
s
2
10.00
1
5
3
2
1,00
r?
* 4
z z
0 100
I
10,


— :



0,000





0,000



000



000




























































00 Z 3 4 9 0 7














X



_/














/

'

s






1
T
1






X

y ^

2 	



,.'006 1 1 — 1










PR
EN
/
IIJ/IMJ
ซ
x
'MAI
r M














'Ct

pit


4TE
ปTE




— ; ~'tn



1
— t-*-t-h

i , ' 1
ss

e

-q
Trt

i
1
MA
Rl




' "10.000' '
NCE
,u



i
*10
0 1 00 ' 000
n]

It
1





p

L
o.ooo
•Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
 (multiply value shown on this figure by 1.193)
 Source: USEPA, 1982a
                                    10-99

-------
     Process energy  requirements are for the sludge  feed  pump,  the air pump
for inflating the  diaphragm,  and a vacuum pump  for removal  of liquid sludge
remaining in the  internal  piping prior to opening  the  press.   Energy is also
required to open  and close the press, for cloth washing,  and  for conditioning
chemical preparation and feed.  Building energy requirements  are based on 84
kwh/sq ft/yr.

     Maintenance  material  costs consist principally  (over 90  percent) of
replacement of diaphragms  and filter cloths.  Other  costs are for
miscellaneous equipment parts and for miscellaneous  electrical components.

     Labor required  is  for both operation and maintenance,  with the majority
of the labor devoted to operational requirements.  Labor  requirements are
based on operational experience of the manufacturer  (USEPA, 1982a).

     Belt Press Filters—Construction costs  are  for  belt  filter press
dewatering systems that include the belt press  unit, wash water pump,
conditioning tank, feed pump, polymer storage tank and pump,  belt conveyor,
and electrical control  panel.  Machines are  generally  sized using metric
dimensions and are rated on the basis of sludge  flow in gpm/m of belt width.
For mixtures of digested primary and secondary  sludges, a value of 50 gpm/m
belt width is a typical loading recommendation,  and  was used in the cost
development.  Higher loadings are possible  in some cases  if the sludge can be
easily dewatered  (USEPA, 1982a) .

     Estimated construction costs are presented in Figure 10-38 as a  function
of total  installed machine capacity.

           FIGURE 10-38. CONSTRUCTION COST OF A BELT FILTER  PRESS
                          <ง  '

                                       -J-
                             Total Installed Machine Capacity-gpm
                              KO^0too
                             Total Installed Machine Capacity-liters/sec
            •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
             (multiply value shown on this figure by 1.193)
            Source: USEPA, 1982a
                                       10-100

-------
     Figures 10-39 and 10-40 present operation and maintenance costs  for  the
belt filter press.  Process energy requirements were developed from the total
connected horsepower for the belt drive unit, belt wash water pump,
conditioning tank, feed pump, polymer pump and tanks, belt conveyor,  and
electrical control panel.  A belt filter  loading of 50 gpm/m of machine width
was used in selecting unit sizes and determining power requirements.
Twenty-two hours of continuous operation  with 2 hour of downtime  for  routine
maintenance was assumed in calculating process energy requirements (USEPA,
1982a).

     Labor and maintenance requirements were estimated from information
provided by equipment manufacturers, as well as information from  plants
operating belt filter presses.  The maintenance material requirments  assume
the replacement of a set of belts every 6 months in continuous service.

     As operation and maintenance costs vary widely depending on  the  nature
and solids concentration of the sludge being processed, and adjustments to
these O&M requirements may have to be made on a case-by-case basis.
Conditioning chemical costs are not included in the total annual  O&M  cost
curve (USEPA, 1982a).

          Vacuum Filters—Costs for vacuum filter installations are presented
in Figure 10-41.  The costs include the vacuum filter, conditioning tank,
vacuum and filtrate pump assemblies, vacuum receiver, a short belt conveyor
for the dewatered sludge, feed sludge piping, lime and ferric chloride storage
and feed facilities, electrical controls, and necessary housing for the entire
assembly (USEPA, 1982a).

     Operation and Maintenance cost are shown in Figures 10-42 and 10-43.
Electrical energy curves are presented for bothprocess and building energy.
Process energy is for vacuum filer drumdrive, cake discharge roller, vacuum
and filtrate pumps, tank agitators,  and the dewatered sludge belt conveyor.
Process energy requirements were calculated for a sludge solids loading of
17 Ib dry 1.7 Ib/sq ft/hr.   Building sizes are based on conceptual layouts for
various total filter areas, and energy requirements are based on 34 kwh/sq
ft/yr of building/year (USEPA 1982a).

     Labor and maintenance material  requirements are based on opeating
experience at operating dewatering facilities.  Labor requirements are based
on 24 hour per day operation, and will have to be adjusted if filters are
operated for only one or two shifts  per day.   Maintenance material costs are
for periodic repair and replacement  of equipment.   Costs are not  inlcuded for
purchase of the lime or ferric chloride utilized for conditioning, since
chemcial requirements are highly variable from sludgeto sludge, and are not
generally a function of vacuum filter surface area (USEPA, 1982a).

     Table 10-16 shows capital and operating costs for a portable filter press
used for dewartering 20,000 gal/yr of 2 percent solids sludge.
                                     10-101

-------
               FIGURE 10-39. BELT FILTER PRESS-LABOR AND TOTAL ANNUAL
                            OPERATION AND MAINTENANCE COST*
I
ซ
s
4
3
2
1.000,
i
<
s
4
5
1
IOCUX
t
•
T
t
9
3
I
tOyCC
!
3
I
3
6
S
9
Z
000
I
t
t
4
3
!
0 IOOI
$
t
9
4
1
2
D IOC
tS:
fi;
IQOO








000



00



0













































• '*




-."









.^
,'





,.^









^_





X















,/


1 —
























/














/
/TOT




LAB
/











KL




3R











0!
















T









                                           ft SLUDOt FLOW BATE ~Wซ
                                        FEED SLUOOt FLOW R*Tt -iltiri/ปc.
FIGURE 10-40. BELT FILTER PRESS-BUILDING ENERGY, PROCESS ENERGY AND MAINTENANCE
              MATERIAL REQUIREMENTS*
1
*
3
4
1
"
OOJX
t
5
4
i
r
•
i
4
s
too
J
ft
4
t
t

9
2
S \tVป
3
3
I
ป IฃC
.$
• N •
' * *
• 5 4
r
D lOOy
*
%
4
3
w




xbooo



WXO





000



OOD






















































--.











/





."/











/

















f






















	 ~*
ฃ
7
,''









1
/



/


,*
**^
8UILD
EMCB









MAI
1



PR
E>




MU
GT









Hilt,
*1EB



1CSSE















1 c
- t














                                         FCCO tLUOQC FLOW MATE -
                                          o aLtwec FLOW MTC
               •Costs can be updated to $19% using ENR Construction Cost Indices for 1982 and 1985
                (multiply value shown on this figure by 1.193)
               Source: USEPA,1982a
                                          10-102

-------
         FIGURE 10-41. CONSTRUCTION COST FOR VACUUM FILTERS*
I
t
3
4
1
I
IO.OOC
i
•
s
4
1
I
l.OOO,
T {
s s
i ;
i .
ซ tOO.
ป
9
4
1
2


!

.000




1
OOO




000



o






INQ
UN












-H-t







LE
r













[ '
Tl
~ T



-'J






-~n 	 • — • — *—







L 	 MU

LTI
(Nil

^














..-^-[ J -H 	 i 	 . — , — J— — J









PL
S
-X*








'•
-









1
1




1






i

'

'
/
; i




'••











































< lOOOO
                                 TOTAL. FILTER *MCA -fซ
                                 ror*;. FILTM AREA -ป 2
                                                        1000
FIGURE 10-42. VACUUM FILTERS-LABOR AND TOTAL ANNUAL OPERATION
              AND MAINTENANCE COST*

7 -
K 3- S
i 3- J
S I- 2
* ICCUKB IQQyC
; f ?
i *r *
1 * '
tf- t
loon iw
Jt ;;
•t- < •
•r • •
5rj'
.i-i.
a • ป
4 4
> 3
t • *
i 100






00


—•—
300


























.


***





*'*







j {



_^

,

; ^

f..:f .._ ,-





Ix1

x^
^
















^




^







j













-_J





_^ ;
^ TOT4L C

. — J


LABOfl






















OST ' ! "















. i . ,i . 4
i i 1

1 f
1
t








'




j

                                 TOTAL Ft-Ttll *ซ* -ft *
                                              Tic-
Tioo
                                 TOTAL nLTCM AftCA -
       "Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
        (multiply value shown on this figure by 1.193)
       Source: USEPA,1982a

                                       10-103

-------
            FIGURE 10-43. VACUUM FILTERS-BUILDING ENERGY, PROCESS ENERGY
                      AND MAINTENANCE MATERIAL REQUIREMENTS
I
s
4


5
S
t
:ซi
ft

-
IOO





F— =









100 	 '





10















x'




















X""











^






y
/
,.'
,,. 	 '

















H^



**









^r









r"e''







TOTAL *Xn* AซA -1

" :^iis
P UA1





x
'
' ENEซ


/
• ' AuiLN
ENEN







ซ

FN
tH







8T



M(J
QV








Jt E
























...















— '
7*5 	 ft" 	 i4o '*ฐฐ
TOtAL riLTflt Aซ* -•*
             •Costs can be updated to $1985 using ENR Construction Cost Indices for 1982 and 1985
             (multiply value shown on this figure by 1.193)
             Source: USEPA, 1982a
10.3  Solidification/Stabilization
     Solidification  and  stabilization are terms which  are  used to describe
treatment systems which  accomplish one or more of  the  following objectives
(USEPA, 1982b):

     •  Improve waste  handling or other physical characteristics of the waste

     •  Decrease the surface  area across which transfer  or loss of contained
        pollutants can occur

     •  Limit  the solubility  or toxicity of hazardous  waste constituents.

     Solidification  is used to describe processes  where  these  results are
obtained primarily, but  not exclusively, by production of  a monolithic block
of waste with  high structural integrity.  The contaminants do  not necessarily
interact chemically with the  solidification reagents,  but  are  mechanically
                                      10-104

-------
   TABLE 10-16.   1985 CAPITAL AND OPERATING COSTS FOR PORTABLE FILTER PRESS*
The recurring annual costs for dewatering are as follows:
     Total labor time to transport, hook-up, operate and
     wash the press = 40 hrs/month.
     Filter cloth cost
     Disposal cost
                                          TOTAL
-  $ 5,990/yr
=  $ 1,040/yr
=  $ 6.032/yr
   $13,062/yr
The capital cost required is as follows:
     24" SPERRY HHC (or equal filter press (delivered)
         * polypropylene construction
         * 40" W x 102" L x 62" H
         * 4,000 Ibs. (dry)
   $15,600
     Trailer and mounting (including a sludge collection
     pan)                                                  =  $ 2,080
     Trailer mounted filtrate return pump                  =  $ 2,080
     Miscellaneous hoses and filterings                    =  $ 1 ,040
                                           TOTAL              $20,800
*Costs updated to $1985 using 1983 and 1985 ENR construction cost indices.
Source:  Moore, Gardner and Assoc., Inc. 1983
                                     10-105

-------
     locked within the solidified matrix.  Contaminant loss is minimized by
reducing the surface area.  Stabilization methods usually involve the addition
of materials which limit the solubility or mobility of waste constituents even
though the physical handling characteristics of the waste may not be improved
(USEPA, 1982b; Cullinane and Jones, 1985).  Methods involving combinations of
solidification and stabilization techniques are often used.

     Solidification/stabilization methods can be categorized as follows:

     •  Cement solidification
     •  Silicate-based processes
     •  Sorbent materials
     •  Thermoplastic techniques
     •  Surface encapsulation

     •  Organic polymer processes

     •  Vitrification.

     Detailed discussions of solidification/stabilization methods can be found
in Guide to the Disposal of Chemically Stabilized and Solidified Waste and
Technical Handbook for Solidification/Stabilization of Hazardous Waste
(Cullinane and Jones, 1985).

     These documents should be consulted for detailed information on these
processes.  However, it should be noted that the state-of-the-art of
solidification/stabilization methods is advancing rapidly.  Many manufacturers
are marketing processes which involve the use of various combinations of
alkaline earth materials (e.g., lime, cement kiln dust, silicaceous materials,
cement) often together with organic polymers and proprietary chemicals.

     10.3.1  Cement-Based Solidification


          10.3.1.1  General Description


     This method involves mixing the wastes directly with Portland cement, a
very common construction material.  The waste is incorporated into the rigid
matrix of the hardened concrete.  Most solidification is done with Type I
Portland cement, but Types II and V can be used for sulfate or sulfite wastes.
This method physically or chemically solidifies the wastes, depending upon
waste characteristics (USEPA, 1982b).  The end product may be a standing
monolithic solid or may have a crumbly, soil-like consistency, depending upon
the amount of cement added.
                                     10-106

-------
          10.3.1.2  Applications/Limitations


     Most hazardous wastes slurried in water can be mixed directly with cement
and the suspended solids will be incorporated into the rigid matrix.  Although
cement can physically incorporate a broad range of waste types, most wastes
will not be chemially bound and are subject to leaching.

     Cement solidification is most suitable for immobilizing metals because at
the pH of the cement mixture, most multivalent cations are converted into
insoluble hydroxides or carbonates.  However, metal hydroxides and carbonates
are insoluble only over a narrow pH range and are subject to solubilization
and leaching in the presence of even midly acidic leaching solutions (e.g.,
rain).  Portland cement alone is also not effective in immobilizing organics.

     The end product of cement solidification will not be acceptable for
disposal without secondary containment regardless of whether the wastes are
organic or inorganic in nature.  Another major disadvantage is that cement-
based solidification results in wastes that are twice the weight and volume of
the original material thereby increasing transportation and disposal costs
(USEPA, 1982b).  Because of these limitations, Portland cement is generally
used only as setting agent in other solidification processes particularly
silicate-based processes described in Section 10.3.2.

     Another problem with cement solidification is that certain wastes can
cause problems with the set, cure, and permanence of the cement waste solid
unless the wastes are pretreated.  Some of these incompatible wastes are
(USEPA, 1982b):

     •  Sodium salts of arsenate, borate, phosphate, iodate, and sulfide

     •  Salts of magnesium, tin, zinc, copper, and lead
     •  Organic matter
     •  Some silts and clays
     •  Coal or lignite.

     Major advantages to the use of cement include its low cost, and the use
of readily available mixing equipment.


          10.3.1.3  Implementation Considerations


     Since cement is primarily used as a setting agent in other solidification
processes, Sections (10.3.2 and 10.3.5) should be consulted for information
related to implementation.
                                     10-107

-------
          10.3.1.4  Costs
     Cement costs range from $60 to $90 per ton at the mill.  However, capital
expenditure and transportation will vary widely depending on the site and the
waste (see Section 10.3.2).  Cost information for specific wastes should be
obtained from vendors.  Vendors include:  Atcor Washington, Inc., Park Mall,
Peeksville, New York; and Chemfix, Inc., Kenner, Louisiana.
     10.3.2  Silicate-Based Processes


          10.3.2.1  General Description


     Silicate based processes refer to a very broad range of solidification/
stabilization methods which use a siliceous material together with lime,
cement, gypsum, and other suitable setting agents.  Extensive research is
currently underway on the use of siliceous compounds in solidification.  Many
of the available processes use proprietary additivies and claim to stabilize a
broad range of compounds from divalent metals to organic solvents.  The basic
reaction is between the silicate material and polyvalent metal ions.  The
silicate material which is added in the waste may be fly-ash, blast furnace
slag or other readily available pozzolanic materials.  Soluble silicates such
as sodium silicate or potassium silicate are also used.  The polyvalent metal
ions which act as initiators of silicate precipitation and/or gelation come
either from the waste solution, an added setting agent, or both. The setting
agent should have low solubility, and a large reserve capacity of metallic
ions so that it controls the reaction rate.  Portland cement and lime are most
commonly used because of their good availability.  However, gypsum, calcium
carbonate, and other compounds containing aluminum, iron, magnesium, etc. are
also suitable setting agents.  The solid which is formed in these processes
varies from a moist, clay-like material to a hard-dry solid similar in
appearance to concrete (Granlund and Hayes, undated).

     Some of the additives used in silicate based processes include (Cullinane
and Jones, 1985):

     •  Selected clays to absorb liquid and bind specific anions or cations

     •  Emulsifiers and surfactants which allow the incorporation of
        immiscible organic liquids

     •  Proprietary absorbents that selectively bind specific wastes.  These
        materials may include carbon, zeolite materials and cellulosic
        sorbents.
                                     10-108

-------
      There are a number of  silicate-based  processes which  are currently
 available or  in the  research  stages.  Manufacturers'  claim differ  signif-
 icantly  in terms of  the capabilities of  these  processes  for stabilizing
 different waste constituents.

      The Chemfix process  uses  soluble silicates with  cement as  the setting
 agent.   Research data  shows that  the process can  stabilize sludges containing
 high  concentrations  of heavy metals even under very acidic conditions
 (Spencer, Reifsnyder,  and Falcone, 1982).

      The Envirosafe  I  process  uses fly ash  as  the  source of silicates  and lime
 as  the alkaline earth  material.   This method has been shown to  stabilize oil
 bearing  sludge (49%  oil and grease) and  neutralize inorganic metal sludge.
 Success  was demonstrated by use of compressive strength  tests (using ASTM
 methods) and  leaching  tests (Smith and Zenobia, 1982).

      The DCM  cement  shale silicate process  is  a proprietary process formulated
 by  Delaware Custom Material,  Inc., State College, PA.  It  involves use of
 cement,  an emulsifier  for oily wastes, and  sodium  silicate.  Testing by
 Brookhaven National  Laboratories  showed  that the process could  stabilize oily
 wastes with up to a  30 percent volumetric  loading  (Clark,  Colombo,  and
 Neilson, 1982).  Manufacturers claim that  the  process can  be used  to solidify
 wastes containing acids,  organic  solvents  and  oils (Hayes  and Granlund,
 undated).

      PQ  Corporation  of Lafayette  Hill, Pennsylvania,  has done extensive
 research on the use  of silicates.  Their research describes successful
 stabilization of a mixed heavy metal/organic sludge;  a waste containing high
 levels of organics and petroleum  by-products;  and a waste  containing organic
 solvents using modifications of the process which involves the  use of  sodium
 silicates (Spencer,  Reifsnyder, and Falcone, 1982).


          10.3.2.2   Applications/Limitations
     There is considerable research data to suggest that silicates used
together with lime, cement or other setting agents can stabilize a wide range
of materials including metals, waste oil and solvents.  However, the
feasibility of using silicates for any application must be determined on a
site-specific basis particularly in view of the large number of additives and
different sources of silicates which may be used.  Soluble silicates such as
sodium and potassium silicate are generally more effective than fly ash, blast
furnace slag, etc.

     There is some data to suggest that lime-fly ash materials are less
durable and stable to leaching that cement fly ash materials (Cullinane and
Jones, 1985).

     Common problems with lime-fly ash and cement-fly ash materials relate to
interference in cementitious reactions that prevent bonding of materials.
                                     10-109

-------
Materials such as sodium borate, calcium sulfate, potassium dichromate and
carbohydrates can interfere with the formation of bonds between calcium
silicate and aluminum hydrates.  Oil and grease can also interfere with
bonding by coating waste particles (Cullinane and Jones, 1985).  However
several types of oily sludges have been stabilized with silicate based
processes.

     One of the major limitations with silicate based processes is that a
large amount of water which is not chemically bound will remain in the solid
after solidification.  In open air, the liquid will leach until it comes to
some equilibrium moisture content with the surrounding soil.  Because of this
water loss, the solidified product is likely to require secondary containment.

     Silicate-based processes can employ a wide range of materials, from those
which are cheap and readily available to highly specialized and costly
additives.

     The services of a qualified firm are generally needed to determine the
most appropriate formulation for a specific waste type.


          10.3.2.3  Implementation Considerations


     Commercial cement mixing and handling equipment can generally be used for
silicate-based processes.  Equipment requirements include chemical storage
hoppers, weight or volume-based chemical feed equipment, mixing equipment and
waste handling equipment.  Ribbon blenders and single and double shaft mixers
can be used for mixing.  A number of mobile, trailer mounted systems are
available.

     Silicate-based solidification can also be accomplished on a batch basis
in drums.  Equipment requirements include on-site chemical storage system,
chemical batching system, mixing system, and drum handling system.  One
company has developed a solidification kit for processing wastes in a drum.
The kit consists of a drum containing a disposable mixer blade with the shaft
held by bearings welded to the inside of the lid and the bottom of the drum.
The upper end of the shaft is accessible through a bung in the lid for turning
with an external motor.  The cement can be added to the drum before it is
capped.  The liquid waste and silicate are added through bungs in the lid.  An
air driven motor is clamped to the drum lid to turn the mixer (Granlund and
Hayes, undated).

     Solidification can also be accomplished in-situ using a lagoon or mixing
pit.  This would involve the use of common construction machinery such as a
backhor or pull shovel to mix the waste and reagents.  However, the ability of
in-situ solidification to prevent leaching of contaminants would need to be
demonstrated on a case-by-case basis.
                                     10-110

-------
           10.3.2.4  Costs
     Table 10-17 provides estimated costs for silicate cement solidification
using three different mixing methods:  in-drum mixing, in-situ mixing and a
mobile cement mixing system.  In all cases it was assumed that 500,000 gallons
(2,850 tons) of wastes were solidified with 30 percent portland cement and 2
percent sodium silicate.  On-site disposal was assumed.  These costs are
intended mainly to show the relative cost of various mixing methods and the
proportion of total cost for reagents, equipment and labor.  It should be
emphasized that actual costs are highly waste-and site-specific and that
specific site and/or waste characteristics could change these cost estimates
by several fold.

     In-drum mixing is by far the most expensive alternative and requires the
greatest amount of labor and production time.  Because of the high cost,
in-drum mixing is limited to sites have highly toxic or incompatible wastes in
drums (Cullinane and Jones, 1985).

     The cost of in~situ mixing and mobile treatment are much more comparable.
All are quite sensitive to reagent cost since it typically makes up from 40 to
65% of the total cost.  The in-situ technique is the fastest and most
economical of the bulk methods because the wastes typically only have to be
handled once, or not at all if they are to be left in-place.  Labor and
equipment each make up less than 5% of the total treatment cost.  However,
in-situ mixing is the least reliable because of difficulties in accurate
reagent measurement and in getting uniform and/or complete mixing of wastes
and treatment reagents.  Mobile mixing plants, although giving excellent
mixing results and reasonably good production rates, require that both the
treated and untreated product be handled, thereby increasing the costs above
those for in-situ treatment (Cullinane and Jones, 1985).


     10.3.3  Sorbents
          10.3.3.1  General Description


     Sorbents include a variety of natural and synthetic solid materials which
are used to eliminate free liquid and improve the handling characteristics of
wastes.  Commonly used natural sorbent materials include flyash, kiln dust,
vermiculite, and bentonite.  Synthetic sorbent materials include activated
carbon which sorbs dissolved organics, Hazorb (product of Dow Chemical) which
sorbs water and organics and Locksorb (product of Radecca Corp.) which is
reportedly effective for all emulsions (Cullinane and Jones, 1985).
                                     10-111

-------
       TABLE 10-17. SUMMARY COMPARISON OF RELATIVE 1985 COST
                   OF STABILIZATION/SOLIDIFICATION ALTERNATIVES1
Parameter
In-drum
In-situ"
                                                       Plant Mixing
Pumpable
Unpumpable
Metering and
mixing efficiency
Processing days
required
Good
374
Fair
4
Excellent
10
Excellent
14
Cost/ton
Reagent
Labor and per diem
Equipment rental
Used drums
@ $11 /drum
Mobilization-
demobilization

Cost of treatment
process
Profit and
overhead (30%)
TOTAL COST/ TON


$ 24.46
(9%)*
61.09
(23%)
44.43
(17%)
57.69
(21%)
18.76
(7%)

$206.38
61.91
(23%)
$248.29


$21.27
(63%)
1.41
(4%)
1.43
(4%)
-
1.64
(5%)

$25.75
6.73
(23%)
$33.48


$21.27
(53%)
3.97
(10%)
4.07
(10%)
-
1.48
(4%)

$30,79
9.29
(23%)
$40.03


$21.27
(42%)
7.19
(14%)
7.82
(16%)
-
2.34
(5%)

$38.62
11.59
(23%)
$50.21

*% of total cost/ton  for  that alternative.
 Costs updated from 1983  costs using  1985 ENR  Index.
2
 Assumed 49 gallons of untreated waste  per  drum  and  an  average  processing rate
 of 4.5 drums per hour.
 Assumed wastes would be  mixed by backhoe with a lagoon and  left  there.
 Remedial Action is located  200 miles from  its nearest  equipment.
4                                 .                        3
 Assumed pumpable sludge  had a~daily  throughput  of  250  yd and  the unputnpable
 sludge a throughput  of 180  yd /day.   Remedial Action  is assumed  to be located
 200 miles from the nearest  equipment.

Source: Cullinane and Jones, 1985
                                  10-112

-------
           10.3.3.2  Applications/Lira itations


      Sorbents are widely used to remove free  liquid and  improve waste
handling.  Some sorbents have been used to limit the escape of volatile
organic compounds.  They may also be useful in waste containment when  they
modify the chemical environment and maintain  the pH and  redox potential  to
limit the  solubility of wastes (Cullinane and Jones, 1985).  Although  sorbents
prevent drainage of free water, they do not necessarily  prevent leaching of
waste constituents and secondary containment  is generally required.


           10.3.3.3  Implementation Considerations


      The quantity of sorbent material necessary for removing free  liquid
varies widely depending on the nature of the  liquid phase, the solids  content
of  the wate, the moisture level in the sorbent, and the  availability of  any
chemical reactions that take up liquids during reaction.  It is generally
necessary  to determine the quantity of sorbent needed on a case-specific
basis .

     Equipment requirements for addition and mixing of sorbents are simple.
Any of the mixing methods described in Section 10.3.2.3  can be used.


      10.3.4  Thermoplastic Solidification


           10.3.4.1  General Description


     Thermoplastic solidification involves sealing wastes in a matrix  such as
asphalt bitumen, paraffin, or polyethylene.  The waste is dried, heated, and
dispensed through a heated plastic matrix.  The mixture  is then cooled to
form a rigid but deformable solid.  Bitumen solidification is the most widely
used of the thermoplastic techniques.


          10.3.4.2  Applications/Limitation


     Thermoplastic solidification involving the use of an asphalt binder is
most suitable for heavy metal or electroplating wastes.  Relative to the
cement solidification, the increase in volume is significantly less and the
rate of leaching significantly lower.   Also, thermoplastics are little
affected by either water or microbial attack.
                                     10-113

-------
     There are a number of waste types which are incompatible with thermo-
plastic solidification.  Oxidizers such as perchlorates or nitrates can react
with many of the solidification materials to cause an explosion.  Some
solvents and greases can cause asphalt materials to soften and never become
rigid.  Xylene and toluene diffuse quite rapidly through asphalt.  Salts that
partially dehydrate at elevated temperatures can be a problem.  Sodium sulfate
hydrate, for example, will loose some water during asphalt incorpoation and if
the waste asphalt mix containing the partially dehydrated salt is soaked in
water, the mass will swell and crack due to rehydration.  This can be avoided
by eliminating easily dehydrated salts or coating the outside of the waste/
asphalt mass with pure asphalt.  Chelating and complelxing agents (cyanides
and ammonium) can cause problems with containment of heavy metals (Cullinane
and Jones, 1985) .

     High equipment and energy costs are principal disadvantages of therm-
oplastic solidification.  Another problem is that the plasticity of the
matrix-waste mixture generally require that containers be provided for
transportation and disposal of materials which greatly increases the cost.

     Certain wastes, such as tetraborates, and iron and aluminum salts can
cause premature  solidification and plug up the mixing machinery (USEPA,
1982b).
          10.3.4.3  Implementation Considerations


     Thermoplastic solidification requires specialty equipment and highly
trained operators to heat and mix the wastes and solidifier.  The common range
of operating temperatures is 130ฐ to 230ฐC.  The energy intensity of the
operation is increased by the requirement that the wastes be thoroughly dried
before solidification.


          10.3.4.4  Costs
     Cost data for thermoplastic solidification outside of the nuclear indus-
try is not readily available.  Wernen and Pfleudern Corporation has developed
an asphalt binder based process called the Volume Reduction and Solidification
System; solidification costs for non-radioactive materials are estimated at
$20 to $70 per ton.  This cost includes secondary containment but not final
transport and disposal (Doyle, 1980).
                                     10-114

-------
     10.3.5  Surface Microencapsulation


          10.3.5.1  General Description


     Surface encapsulation describes those methods which physically micro-
encapsulate wastes by sealing them in an organic binder or resin.

     Surface encapsulation can be accomplished using a variety of approaches.
Three methods which have been the subject of considerable research are
described briefly below:

     One process developed by Environmental Protection Polymers involves the
use of 1,2-polybutadiene and polyethylene (PE) to produce a microencapsulated
waste block onto which a high density polyethylene (HOPE) jacked is fused.
The 1,2-polybutadiene is mixed with particulated waste which yields, after
solvent evaporation, free flowing dry resin-coated particulates.  The
resulting polymers are resistent to oxidative and hydrolytic degradation and
to permeation by water.  The next step involves formation of a block of the
polybutadiene/waste mixture.  Powdered, high density PE is grafted chemically
onto the polymer backbone to provide a final matrix with ductile qualities.
Various combinations of the two resins (polybutadiene and PE) permit tailoring
of the matrix's mechanical properties without reduction of system stability
when exposed to severe chemical stress.  In the final step, a 1/4 inch thick
HDPE jacket is mechanically and chemically locked to the surface of the micro-
encapsulated waste (Lubowitz and Wiles, 1981).

     Another encapsulation method developed by Environmental Protection
Polymers involves a much simpler approach.  Contaminated soils or sludges are
loaded into a high density polyethylene overpack.  A portable welding
apparatus developed by Environmental Protection Polymers is then used to spin
weld a lid onto the container thereby forming a seam free encapsulate.

     A third surface encapsulation method involves use of an organic binder to
seal a cement-solidified mass.  United States Gypsum Company manufacturers a
product called Envirostone Cement which is a special blend of high-grade
polymer modified-gypsum cement.  Emulsifiers and ion exchange resins may be
added along with the gypsum cement which hydrates to form a freestanding mass.
A proprietary organic binder is used to seal the solified mass (United States
Gypsum Co., 1982).  The process can be used to stabilize both organic and
inorganc wastes.  It has been shown to effectively immobilize waste oil
present at concentration as high as 36 volume percent (Clark, Colombo, and
Neilson, 1982).   The volume of waste is smaller than that obtained with cement
solidification alone.
          10.3.5.2  Applications/Limitations

     The major advantage of encapsulation processes so far as research shows
is that the waste material is completely isolated from leaching solutions.
                                     10-115

-------
These methods can be used for both organic and inorganic waste constituents.
However, each of the available encapsulation processes are quite unique and
the feasibility must be determined on a case-specific basis.

     Other advantages associated with hazardous waste encapsulation include
(USEPA, 1982b):

     •  The cubic and cylindrical encapsulates allow for efficient space
        utilization during transport, storage, and disposal

     •  The hazard of accidental spills during transport is eliminated

     •  Materials used for encapsulation are commercially available, very
        stable chemically, nonbiodegradable, mechanically tough, and flexible

     •  Encapsulated waste materials can withstand the mechanical and chemical
        stresses of a wide range of disposal schemes (landfill, disposal in
        salt formations, ocean disposal).

     The major disadvantages associated with encapsulation techniques include:

     •  Binding resins required for agglomeration/encapsulation (high density
        polyethylene; polybutadiene) are relatively expensive

     •  The processes are energy intensive and relatively costly

     •  Skilled labor is required to operate molding and fusing equipment.
          10.3.5.3  Costs


     Environmental Protection Polymers has estimated that the cost of the
polybutadiene/HDPE microencapsulation method will be approximately $90/ton.
Encapsulation in the seam-free HDPE overpack is approximately $50 to $70 for a
80 gallon drum load (Lubowitz, H., Environmental Protection Polymers, personal
communication October 13 and 14, 1983).


     10.3.6  Vitrification


          10.3.6.1  General Description
     Vitrification of wastes involves combining the wastes with molten glass
at a temperature of 1,350ฐC or greater.  However, the encapsulation might be
done at temperatures significantly below 1,350ฐC (a simple glass polymer such
as boric acid can be poured at 850ฐC).  This melt is then cooled into a
stable, noncrystalline solid (USEPA., 1982b) .
                                     10-116

-------
           10.3.6.2  Applications/Lira itations


     This  process is quite costly and so has been restricted to radioactive or
very highly  toxic wastes.  To be considered for vitrification, the wastes
should be  either stable or totally destroyed at the process temperature.

     Of all  the common solidification methods, vitrification offers  the
greatest degree of containment.  Most resultant solids have an extremely low
leach rate.   Some glasses, such as borate-based glasses, have high leach rates
and exhibit  some water solubility.  The high energy demand and requirements
for specialized equipment and trained personnel greatly limit the use of this
method.
           10.3.6.3  Implementation Considerations
     Classification of wastes is an extremely energy intensive operation and
requires sophisticated machinery and high trained personnel.
          10.3.6.4  Cost


     No cost information was available for glassification.


     10.3.7  Technology Selection/Evaluation


     Evaluation of the technical feasibility and effectiveness of
stabilization/solidification methods must be determined on a case-by-case
basis.  Commercial firms specializing in these processes should be consulted
whenever solidification/stabilization is being considered.  Samples of the
solidified product will need to be subjected to extensive leaching tests
unless a reliable, effective means of secondary containment is to be used.  It
should be noted that secondary containment is recommended with most of the
previously described methods (except microencapsulation and glassification for
some waste types).  Similarly, where the end product is intended to be a
monolithic block, samples must be subjected to compressive strength tests.

     Solidification/stabilization methods run the gamut from those which use
simple, safe, readily available equipment (cement and most silicate-based
processes) to those which require highly sophisticated, costly, and
specialized equipment (e.g., glassification and thermoplastic techniques).
Use of these high technology processes should be limited to wastes which
cannot be treated cost-effectively using any other methods.   Regardless of the
simplicity of some of the equipment, professionals trained in these processes
should be consulted since formulations including proprietary additives are
very waste specific.
                                     10-117

-------
10.4  Gaseous Waste Treatment
     Gaseous wastes may be present at hazardous waste sites as a result of
bulk gas disposal in containers, volatilization of organic liquids,  byproducts
of waste decomposition, or byproducts of treatment or other on-site  processes.
Once captured and collected, gaseous wastes can be treated thermally to render
contaminants less hazardous or treated physically or chemically to remove and
concentrate contaminants.  The following three categories of gaseous waste
treatment are described in this section:

     •  Incineration

     •  Flaring
     •  Adsorption.


     10.4.1  Flaring


          10.4.1.1  General Description


     Combustion is a chemical reaction that thermally oxidizes a substance
into products that generally include ash, gases, water vapor, and heat.
Flaring is a special category of combustion where wastes are exposed to an
open flame and no special features are employed to control temperatures or
time of combustion.  Supplementary fuels may be needed to sustain continuous
combustion.


          10.4.1.2  Applications/Limitations


     Flares are commonly used in the oil and gas industry to dispose of waste
gases and fumes at refineries; at sewage treatment plants to dispose of
digestor gas; and at sanitary landfills to dispose of landfill gas.   Although
flares provide sufficient destruction of contaminants for conventional
applications, destruction removal efficiencies (DREs) required by current
environmental regulations for thermal destruction of hazardous wastes are
generally too stringent to be met by flaring.  Exceptions may be gaseous waste
streams consisting of relatively simple hydrocarbons (emissions from fuel
tanks, landfill methane gas, etc.).

     Supplemental fuel is required to sustain a flame with gases of  low
heating value.  Gases with heating values as low as the low hundreds of Btu's
per cubic foot can sustain a flame (natural gas has a heating value  of approx-
imatley 1,000 Btu's per cubic foot).

     Flame sensors, pilot flames, automatic sparkers, and alarms are often
used to sense loss of flame, attempt reignition, and alert operators to system
                                     10-118

-------
performance problems.  Shields  can  be  placed around floors to serve as
windbreaks for containing  and preventing "blowing out" of the flame.

     The flow rate dictates  the diameter and height of the flare and  the
number of flares to be employed.  The  flare must be designed such that the
flame is largely contained within the  body of the flare for safety reasons  and
to allow adequate mixing of  gas and air.  The oxygen content of the gas
influences the air/gas ratio that is sought in the combustion area of the
flare.
          10.4.1.3  Costs

     Purchase costs of  flares  depend primarily on the waste-gas  flowrate,  and
secondarily on design and  elevation.  Costs in dollars for flowrates between
1,000 and 100,000 Ib/h  are given in Figure 10-44.  Costs include ladders,
platforms, knockout drums  with seals,  and stacks high enough to  ensure
grade-level radiation no greater than 1,500 Btu/(h)(ft ).  Costs described in
Figure 10-44 refers to  self-supporting type elevated flares (approximately 40
feet high).  Costs for  elevated flares supported by guyed wires  (nominally 100
feet tall) range from 30 percent higher (than the self-supporting type)  at
250,000-lb/h flowrates,  to 80  percent higher at 2,500-lb/h flowrates.

     Operating costs for flares are high because of the substantial quantity
of natural gas and steam (in the smokeless type) consumed.  If the waste-gas
must be driven, fan power  costs for overcoming pressure drops may also be
                FIGURE 10-44. PURCHASE COSTS OF ELEVATED FLARES
                     10*
                     103
                       103          104           105
                                  Waste-gas flowrate, Ib/h
                               (high Btu-ethylene)
                               (low Btu-60 Btu/ft3)
                   Source: Vatavuk  and Neveril, 1983
                                     10-119

-------
high.  This  pressure drop depends on the size of the flare, knockout  drum,
puiping  and  stack height, with the maximum allowable pressure drop being
approximately  60  in.  HO.

     Elevated  flares require supplemental fuel, (in addition to gas for pilots
and purging) when a  low-Btu gas is being burned.  The supplemental fuel
(natural  gas)  required  is plotted against waste-gas flowrate in Figure 10-45.
This graph is  based  on  an 880-h/yr operating factor, for gas flowrates in the
range of  1,000 to 250,000 Ib/h.

     Steam consumption  for smokeless flares (or others requiring steam
injection) can be  estimated at  0.6 Ib/lb of waste-gas.
          10.4.1.4  Technology  Selection/Evaluation
     Flaring systems, by virtue of  their  relative lack of controllability, are
generally considered to perform inconsistently.    They are relatively simple
to both fabricate and install.  Conventional  steel plate, pipe, and welding
are employed in fabrication.

     When properly designed and operated,  flares  pose no unusual safety
impacts to operators or others.  The  presence  of  a visible flame is sometimes
considered by the public to be a nuisance.

       FIGURE 10-45. NATURAL GAS REQUIREMENTS FOR ELEVATED FLARES
            S
              10*
               1Q3
                                             'Elevated
                1Q2          103          10*          106
                               Natural gas, million Btu/yr

            Source: Vatavuk and Neveril, 1983
                                     10-120

-------
     Properly designed flaring systems operate automatically.  The most basic
design of flaring requires tnonical ignition.  Pilot flames, sensors, and
igniters may require regular maintenance.  Monitoring of air quality local  to
the flame is advisable to ensure that adequate treatment is being afforded.
     10.4.2  Adsorption


          10.4.2.1  General Description
     Adsorption is the adherence of one substance to the surface of another by
physical and chemical processes.  Treatment of wastestreams by adsorption is
essentially a process of transferring and concentrating contaminants (the
adsorbate) from one medium (liquid or gas) to another (the adsorbent).  The
most commonly used adsorbent is activated carbon; generally, the granular form
(GAG) is used to treat gaseous wastes.  Other adsorbents are specially
manufactured resins.

     Activated carbon is a highly porous material.  Adsorption takes place on
the walls of the pores because of an imbalance of forces on the atoms of the
walls.  The adsorption of molecules onto the wall surfaces serves to balance
the forces (Calgon Corp., undated).  Adsorption onto resins occurs in a
similar fashion.

     Adsorption gas treatment systems consist of containerized beds of
adsorbent.  Large and highly permeable void spaces between relatively large
GAG particles or pellets (nominal size of several millimeters) allow the
contaminated medium to flow through the bed, contacting the particles and
allowing adsorption to take place.  The treated medium leaves the bed with
reduced concentrations of adsorbate until the adsorbent has reached capacity.
Once adsorbents have reached capacity, little or no further adsorption occurs
and some contaminants can be released back into the medium (desorption) and
actually increase contaminant concentrations.

     Adsorbents at capacity can be disposed of in appropriate landfills,
incinerated, or can be regenerated, driving off the adsorbate and allowing
reuse of the adsorbent for treatment.  GAG is regenerated by heating in a
reduced-pressure atmosphere (Calgon Corp, undated).   Resins are regenerated by
washing with appropriate solvents (Kiang and Metry,  1982).   The adsorbate can
be recovered and reused (solvents, for example)  from the regeneration process.

     Multiple bed vessels are often required to allow adequate contact time
and/or to optimize the frequency of adsorbent changeover or regeneration.
Partial or total redundant capacity is often provided by extra bed vessels to
allow continuous operation during changeover or regeneration.
                                     10-121

-------
          10.4.2.3  Applications/Limitations


     Carbon adsorption is generally accepted for use in controlling volatile
hydrocarbons; organic-related emissions; certain sulfur-related emissions such
as hydrogen-sulfide; mercury; vinyl chloride; most halogenatd organics; and
radioactive materials such as iodine, krypton, and xenon.  Carbon adsorption
can also control oxides of sulfur and nitrogen and carbon monoxide (Calgon
Corp., undated).

     Resins are capable of removing most organic contaminants from water and
are also applicable to removal of organics from gaseous streams.  However,
resins are not widely used for gaseous waste treatment.

     Adsorption is widely used in industry for air pollution and odor control,
often in association with solvent recovery and reuse systems.  Generally, GAG
acts as an accumulator of organic contaminants until the bed is saturated.
Hot gases are passed through the bed to desorb the organics which are
condensed and recovered or are incinerated (Calgon Corp., undated).

     Monitoring of gas flowrate and influent and discharge adsorbate concen-
trations are needed to determine changeover/regeneration schedules.  Automatic
monitors and microprocessors may be warranted for highly complex and variable
systems.  Alarms and/or shut-down controls may also be warranted for complex
systems or in sensitive or populated areas.


     10.4.3  Technology Selection/Evaluation


     Adsorption techniques are well-established for removal of organic
compounds and some inorganic compounds  from gaseous streams.  Adsorption is
highly reliable provided that adsorbate and adsorbent are properly matched,
sufficient contact time is allowed, and the adsorbent is regenerated or
replaced before saturation (and desorption) is reached.  Many adsorption
systems are prepackaged and can be quickly installed and placed into operation
by contractors, suppliers, or manufacturers.  Specially designed systems
employ off-the-shelf towers, blowers, and other equipment, and require
additional installation time.

     Operation of properly designed adsorption gas treatment systems is
essentially as automatic as the gas delivery system although manual or special
automatic adjustments may be warranted  for highly variable flows or adsorbate
concentrations.  Changeover or regeneration of the adsorbent bed must be
conductd on a predetermined basis to ensure continuous effective treatment.
                                     10-122

-------
10.5  Thermal Destruction of Hazardous Wastes


     Thermal destruction is a treatment method which uses high temperature
oxidation under controlled conditions to degrade a substance into products
that generally include C0~, H-0 vapor, SO-, NO , HCl gases and ash.  The
hazardous products of the thermal destruction/incineration such as partic-
ulates, SO,,, NO ,  HCl, and products of incomplete combustion require air
pollution control  equipment to prevent release of undesirable species into the
atmosphere.  Thermal destruction methods can be used to destroy organic
contaminants in liquid, gaseous and solid waste streams.

     The most common incineration technologies applicable to hazardous wastes
include:

     •  Liquid injection

     •  Rotary kiln
     •  Fluidized  bed

     •  Multiple hearth

     The operating principles and general applications of these methods are
summarized in Table 10-18.  Mobile incinerators, at sea incinerators and
coincineration commonly employ these technologies.

     Emerging technologies for the thermal destruction of wastes include
(Monsanto Research Corp.; 1981, Keitz and Lee, 1983; Lee, 1983; State of
California, 1981):

     •  Molten salt

     •  Wet air oxidation
     •  Plasma arch torch

     •  Circulating bed
     •  High temperature fluid wall
     •  Pyrolysis
     •  Supercritical water

     •  Advanced electric reactor
     •  Vertical tube reactor.
                                     10-123

-------


















Ill

5
g

o
z
u
LU




O
LH
*4
3
en tr
0
U Vi
D O
t/3 via



U.
e
O
O
O
1
0
o
in
—


H
12
• 1*4
"o
4>
~* eo
j> <0
•^ DO
09 kl
3 O
•Q
B "
6 u
o — <
x o-
•"Z r-4




a x
e: O
u

ii ki
ki U
3 kl
.0

CO 00 kl
•* c n
'" "2
DuC
AJ eo *i^
tfi u *-ซ
CO O X
3 k, o







^H
'jS

>,
a
o
OS











T3
C
o
y
01
o>

|M4

o
4J
^ซt
0



Cfa
o


o
CO
1
o
o

^^




eo
D "O
'ฃ 8.
ki E
3 3
-H a.
J 9

^
4J
-J
ki C
TJ O -H
01
N U 13
E 'ซ =
O ki
u 11 3
CO ki J3
3
oi oo 13 e
U 01 c O
a u a -^
U 01
eo a E C
H ttj V
to oo V 01
CO -rt 4-1 3
3 J3 oo co


C
"-^ O
kl •-<
01 4J
us u
ง01
•^
6 M

D T3
"oil's
e tr
en J







to
u
•3



,ซt
eo
u
01

0)
to
0
4-*

a



Ob
e
O
o
00
1
G
O

ซ— i


TJ
01

<0
3
e
a
^
00
CO
TJ D
CO to
CO
to 3
01
00 13
T3 —4
-* O
tn a>


CO
f. X 11
oo -4 e
3 01 00 O
o .a e u
b •-<
ฃ O to c
4J 4J CO O
ai -t
t! to ki iJ
C 0) u to
11 4J C 3
U ซ0 "< Jb
to k, g
v oc e o
"^ -F4 U
r- )
CO ttj *Q kl
1> U 3J 1)
*J U C *J
0) > kl W
<0 01 3 O
3 to .0 JS



•5
u
a

pg
D
^.j
a
•^
•^
f






CO
01
iJ
01 3
OI C
CO "4
to 6
00

V4 CO
O 13 to

3 -4
to tr —
T3 "4 O
C — to
O
O TJ ki
oi e o
en to u-i



Pb4
0
o
o
vO
1
o
0

~*


to
u
09 —
O -i
00 01
- 0]
to 14 -a
•o o >•*

3 U O
O" to 01
— ' 3 TJ
C U
U to to
•••4 ki en
e oo D
to u
OC TJ O
ki c u
O 
O ^ 4J H
u 01 CO ki
C 4J 0) kl 00
—i to s it e
01 U-l .*4
is a ป u
o> • e 3
4J " O O
3 10 •-. D *-i 
-------
      10.5.1   Liquid  Injection
           10.5.1.1   General Description
     A liquid  incineration system consists of a single or double refractory-
lined  combustion  chamber and a series of atomizing nozzles.  Two chamber
systems are  more  common.  The primary chamber is usually a burner where
combustible  liquid  and gaseous wastes are introduced.  Noncombustible liquid
and  gaseous  wastes  are introduced downstream of the burner in the secondary
chamber.   A  schematic  diagram of a two-stage system is shown in Figure 10-46.
Single chamber incinerators are used for systems handling only combustible
wases  (Kiang and  Metry,  1982).
                                FIGURE 10-46.
                  LIQUID INJECTION INCINERATION SYSTEM
                                                       FLUE GAS
                                     FEED
                                STEAM WATER
                WATER

        LIQUID WASTE
             FUEL
              AIR
                                                             SALT
                                                             SOLUTION
     Source: Kiang and Metry, 1982
     The most popular  liquid  injection  incinerators are horizontally and
vertically fired units.  A  liquid  waste has  to be converted into a gas before
combustion.  The liquid  is  atomized  passing  through the burner nozzles while
entering the combustor.  This  is necessary to ensure complete evaporation and
oxidation.  If viscosity precludes atomization,  mixing and heating or other
means should be applied  prior  to atomization to reduce waste viscosity.

     The operating temperatures vary from 1300 to 3,000ฐF, with the most
common temperature being about  1600ฐF.   Residence times vary from less than
0.5 seconds to 2 seconds (Lee, Keitz, and Vogel,  1982; State of California,

                                      10-125

-------
1981). The process usually requires 20 to 60% excess air to ensure complete
combustion.
          10.5.1.2  Application Limitations

     Liquid injection can be used to destroy virtually any pumpable waste or
gas.  These units have been used in the destruction of PCBs,  solvents, still
and reactor bottoms, polymer wastes, and pesticides (State of California,
1981).  Unlikely candidates for destruction include heavy metal wastes and
other wastes high in inorganics.  It does not have a need for a continuous ash
removal system other than for pollution control (Monsanto Research Corp.,
1981).

     Liquid incinerators have no moving parts and require the least
maintenance of all types of incinerators.  The major limitations of liquid
injection are its ability to incinerate only wastes which can be atomized in
the burner nozzle and the burner's susceptibility to clogging.  It also needs
a supplemental fuel.

     Liquid injection incinerators are highly sensitive to waste composition
and flow changes.  Therefore, storage and mixing tanks are necessary to ensure
a reasonably steady and homogenous waste flow (Kiang and Metry, 1982).


     10.5.2  Rotary Kiln


          10.5.2.1  General Description


     Rotary kilns are capable of handling a wide variety of solid and liquid
wastes.

     Rotary kiln incinerators are cylindrical, refractory-lined shells.  They
are fueled by natural gas, oil, or pulverized coal.  Most of the heating of
the waste is due to heat transfer with the combustion product gases and the
walls of the kiln.  The basic type of rotary kiln incinerator, illustrated in
Figure 10-47, consists of the kiln and an afterburner (Kiang and Metry, 1982).

     Wastes are injected into the kiln at the higher end and are passed
through the combusion zone as the kiln rotates.  The rotation creates
turbulence and improves combustion.  Rotary kilns often employ afterburners to
ensure complete combustion.  Most rotary kilns are equipped with wet scrubber
emission controls.

     The residence time and temperature depend upon combustion characteristics
of the waste.  Residence times can range from a few seconds to an hour or more
for bulk solids.  Combustion temperature range from 1500 to 3000ฐF.
                                     10-126

-------
          10.5.2.2  Application/Limitations
     Rotary kilns  are  capable of burning waste in any physical  form.   They can
incinerate solids  and  liquids independently or in combination and  can accept
waste feed without  any preparation (Monsanto, 1981).  Hazardous wastes which
have been treated  in rotary kilns include PCBs, tars, obsolete munitions,
polyvinyl chloride  wastes,  and bottoms from solvent reclamation operations
(State of California,  1981).
              FIGURE 10-47. ROTARY KILN INCINERATOR SCHEMATIC
                             OXIDATION
                             CHAMBER
                                               FLUE GAS
                                               SCRUBBER
         WASTE
         STORAGE
         HOPPER
                                                               ฉ
                                                                  STACK
L VA/ yy i



ASH /
REMOVAL
MECHANISM
Jป
ฉ

1 1

T ฉ
LIQUID



                                                HOLDING
                                                TANK
                                 LEGEND:
                                  1. INFLUENT WASTE
                                  2. COMBUSTION AIR
                                  3. FLUE GAS
                                  4. RESIDUALS
                                  5. SCRUBBER WATER
                                  6. FUEL


          Source: Ghassami, Yu, and Quinlivan, 1981



     Because of  their  ability to handle waste in any physical  forms,  and their

high incineration efficiency,  rotary kilns are the preferred method  for

treating mixed hazardous  solid residues (Lee, Keitz, and Vogel, 1982).


     The limitations of  rotary kilns include susceptibility to thermal shock,

the necessity for very careful maintenance,  need for additional air  due  to

leakage, high particulate loadings,  relatively low thermal efficiency, and a

high capital cost for  installation  (Monsanto Research Corp., 1981).
                                      10-127

-------
     10.5.3    Multiple Hearth
          10.5.3.1  General  Description
     A multiple hearth  incinerator  consists of a refractory lined steel  shell,
a rotating central shaft, a  series  of  solid flat hearths, a series of rabble
arms with teeth for each hearth,  an air  blower, waste feeding and ash removal
systems, and fuel burners mounted on the walls (Monsanto Research Corp.,
1981).  Figure 10-48  illustrates  the components of the.multiple hearth.   It
can also be equipped with an afterburner, liquid waste burners and side  ports
for tar injection.  Temperature in  the burning zone ranges from 1400 to  18008F
and residence time may  be very long.
          10.5.3.2  Applications/Limitations
     The multiple hearth  incinerator  can be used for the disposal of all  forms
of combustible industrial waste materials,  including sludges, tars, solids,
liquid and gases.  The  incinerator  is best  suited for hazardous sludge
destruction.  Solid waste often requires pretreatment such as shredding and
                  FIGURE 10-48. MULTIPLE HEARTH INCINCERATOR
                                AIR
                                                FLUE GAS
                WASH
                                                           WATER
                    All
 I IHCIHIRATOR
 |            ASH
ASB
                                                 SLURJtt
                             BLOW*
                Source: Kiang and Metry, 1982
                                      10-128

-------
sorting.  It can treat the same wastes as the rotary kiln provided  that
pretreatment of solid waste is applied.  The principal advantages of multiple
hearth incineration include high residence time for sludge and low  volatile
materials; ability to handle a variety of sludges; ability to evaporate  large
amounts of water; high fuel efficiency and the utilization of a variety  of
fuels.  The greatest disadvantages of the technology include susceptibility to
thermal shock; inability to handle wastes containing ash, which fuses  into
large rock-like structures, and wastes requiring very high temperatures.  Also
control of the firing of supplemental fuels is difficult.  The multiple  hearth
incinerator has high maintenance and operating costs (Monsanto Research  Corp.,
1981; State of California, 1981).  The operating cost may be reduced by
utilizing liquid or gaseous combustible wastes as secondary fuel (Monsanto
Research Corp., 1981).
     10.5.4  Fluidized Bed


          10.5.4.1  General Description


     The fluidized bed incinerator illustrated in Figure 10-49 consists of a
cylindircal vertical refractory lined vessel containing a bed of inert
granular material, usually sand on a perforated metal plate.  Combustion air
is introduced through a plenum at the bottom of the incinerator and rises
vertically fluidizing the bed and maintaining turbulent mixing of bed
particles.  Waste material is injected into the bed and combustion occurs
within the bubbling bed.  Heat is transferred from the bed into the injected
wastes.  Auxiliary fuel is usually injected into the bed.  Bed temperatures
vary from 1400 to 1600ฐF.  Since the mass of the heated, turbulent bed is much
greater than the mass of the waste, heat is rapidly transferred to the waste
materials; a residence time of a few seconds for gases and a few minutes for
liquids is sufficient for combustion (State of California, 1981).

     The residence time is long enough to allow the solid materials to become
small and light enough to be carried off as particulates.  Suspended fine
particulates are usually separated in a cyclone when exhaust gases pass
through air pollution control devices before being released into the
atmosphere.


          10.5.4.2  Applications/Limitations


     Fluidized bed incinerators are a relatively new design, presently being
applied for liquid, solid and gaseous combustible wastes.  The most typical
wastes treated in fluidized beds include slurries and sludges.  Some wastes
require pretreatment prior to entering the reactor.  The pretreatment may
involve drying, shredding and sorting.  The fluidized bed handles the same
waste that can be treated in the rotary kiln (Monsanto Research Corp., 1981).
                                     10-129

-------
                      FIGURE 10-49. FLUIDIZED BED INCINERATOR
                                                   FLUE
                                                   GAS
                    ASH
                        J • y/ป< X'^f :•" v," ^."?~ฃst) f.
                      s^^nH'HrfiiiftfiimHiMi
                                                 FUEL




                                             BURNER

                                                 MAKE-UP SAND
                                                      WASTE
                                                     . AIR
                    Source: Kiang and Metry, 1982
     Fluidized beds  are  typically used for the disposal of municipal waste-
water treatment plant  sludges,  oil refinery waste, and pulp and paper mill
waste.  There is only  limited data on the use of fluidized bed for hazardous
waste incineration.  The technology has been used for pharmaceutical wastes,
phenolic wastes, and methyl methacrylate (State of California, 1981).

     It is particularly  well  suited for incineration of high-moisture wastes,
sludges and wastes containing large quantities of ash.  Because of the  low bed
temperature, the exhaust gases  usually contain low nitrogen oxides (Kiang and
Metry, 1982).

     The advantages  of the  fluidized bed incinerator include simple design,
minimal NO  formation, long  life of the incinerator, high efficiency,
sitnplicityxof operation, and  relatively low capital and maintenance costs.   It
also has the ability to  trap  some gases in the bed, reducing the need for and
the cost of an emission  control system.  The disadvantages include difficulty
in removing residual materials  from the bed, a relatively low throughput
capacity, the difficulty in  handling residues and ash from the bed and  the
                                      10-130

-------
relatively high operating costs (State of California, 1981; Monsanto Research
Corp., 1981).


     10.5.5  At-Sea Incineration, Mobile Incineration, and Coincineration


     At-sea incineration usually utilizes a liquid injection unit mounted on a
ship, to destroy hazardous waste far away from populated areas and shipping
lanes.  No acid gas pollutant removal system is applied.  The wastes treated
include toxic organochloride compounds, herbicides, and Agent Orange.  The
basic advantage of at-sea incinertaion is the distance from populated areas
and the high efficiency of combustion.  The disadvantages are problems with
monitoring an at-sea process, the danger of spills and the need to operate
on-shore auxiliary facilities.

     Mobile incineration has not been widely used yet but the demand for the
application of this technique grows with future bans on the landfill disposal
of certain wastes.  Existing mobile systems include liquid injection and
rotary kiln incinerators equipped with secondary combustion chambers and
environmental controls.  These mobile incinerators are capable of handling a
variety of wastes including PCBs, carbon tetrachloride, other hazardous wastes
and soils.  The primary advantage of the mobile incinerator is its ability to
treat on-site and thus eliminate the need for off-site transport of waste.
There is currently only limited experience with mobile incinerators.  Mobile
incinerators must meet all applicable state requirements which typically
include air emission permits.

     Coincineration is a process of using combustible wastes as supplemental
fuels in fossil fuel boilers or any type of incinerator (State of California,
1981; Monsanto Research Corp., 1981).  As a result of Coincineration, the
energy value of the waste is used to produce steam and the original form of
the waste is destroyed through combustion.  This incineration technique can be
implemented in any boiler where the parameters of combustion and feed make it
feasible.  The principal advantages of Coincineration include low capital
cost, and no need for the transport of on-site generated wastes.  Dis-
advantages include the possibility of damaging the boiler by some harmful
waste and the difficulty in obtaining high efficiency of combustion.


     10.5.6  Advanced Incineration Technologies


          10.5.6.1  Molten Salt
     The molten salt incinerator can be used for destruction of hazardous
liquids and solids.  In this method (illustrated in Figure 10-50) wastes
undergo catalytic destruction when they contact hot molten salt maintained at
a temperature between 1382 and 1832ฐF (Ross, 1984; Solsberg, Parent, and Ross,
1985).  Hot gases rise through the molten salt bath, pass through a secondary


                                     10-131

-------
         FIGURE 10-50. MOLTEN SALT INCINERATOR
         MOLTEN SALT COMBUSTOR SCHEMATIC
             LIQUID OR SOLID WASTE   x ATOMIZING
                              AIR
                 OFF
             DOWNCOMER
             METAL
             CONTAINMENT
             VESSEL
                                        SUPPORT
                                        STRUCTURE
INSULATED
ENCLOSURE
               SIMPLIFIED FLOW SCHEMATIC
               MOLTEN SALT DESTRUCTION
                                   SALT DISPOSAL
Source: Rockwell International, 1980
                         10-132

-------
reaction zone, and through an off-gas clean-up system before discharging to
the atmosphere (Kiang and Metry, 1982).  Supplemental fuel may be required
when wastes are not sufficiently combustible to maintain temperatures.

     Liquid, free-flowing powders, sludges, and shredded solid wastes can be
fed directly into the incinerator.  The technology has been demonstrated to be
highly effective for chlorinated hydrocarbons including PCB, chlorinated
solvents, and malathion (Kiang and Metry, 1982).  However, the process appears
to be sensitive to materials containing high ash content or high chlorine
content which must ultimately be removed in the purge system (Ross, 1984).


          10.5.6.2  Wet Air Oxidation
     Wet air oxidation involves aqueous phase oxidation of dissolved or
suspended organic substances at elevated temperatures and pressures.  The
temperature of the process is relatively low, 350-650ฐF, and the pressure
varies between 300-3000 PSI.  Figure 10-51 shows a simplified scheme of the
wet air oxidation process.

     The waste is pumped into the system by the high pressure pump and mixed
with air from the air compressor.  The mixture passes through a heat
exchanger, and then into the reactor where oxygen in the air reacts with
organic matter in the waste.  The oxidation is accompanied by a temperature
rise.  The gas and liquid phases are separated after the reactor, and the
liquid passes through the heat exchanger, heating the incoming material.  The
gas and liquid streams are discharged from the system through control valves.
The degree of oxidation is primarily a function of reaction temperature and
residence time.

     WAO is used primarily to treat concentrated waste streams containing
organic and oxidizable inorganic wastes.  It is generally selected for
treating or pretreating a waste stream which has a high COD/BOD,, ratio and is
not readily amenable to biological treatment.  It is also selected where it is
determined to be more cost-effective than incineration.  Waste streams for
which WAO is particularly applicable include concentrated streams containing
pesticides, herbicides or other complex organics which are not readily
biodegradable.


          10.5.6.3  Plasma Arc Torch
     Plasma arc torch may be used to destory either liquid or solid wastes by
pyrolyzing them into combustible gases in contact with a gas which has been
energized to its plasma state by an electrical discharge (see Figure 10-52).
The plasma gas temperature is about 90,000ฐF.  Wastes are atomized, ionized
                                     10-133

-------
                                  FIGURE 10-51.
                       FLOWSHEET OF WET AIR OXIDATION











WASTK.


STORAGE
TANK
l*^


\

/
****


GAS
SEPARATOR |
*"— T
^_
S-
?
" /S


*'• OXIDIZED
i^i x^ UTฐ ?
AIR r~\ ฃ?\ 4 T
COMPRESSOR!^ 1 V HF 1

•t
o~
PUMP
^^T ^"^ *— IV-J
1 r














REACTOR




h-J

HEAT EXCHANGER
Source: Pradt, 1976
                                 FIGURE 10-52.
                     PLASMA REACTION VESSEL SCHEMATIC
                                                  r-
                    Source: Lee, Keitz and Vogel, 1982
                                          10-134

-------
and destroyed in contact with the plasma.  The advantages of this method are
possibilities of using the exiting gas as a fuel (after removal of halogens
and other contaminants in a scrubber), the lack of hazardous interim
combustion products, high efficiency  and the ability to be portable.  Costs
are not presently available (State of California, 1981).

          10.5.6.4  Circulating Bed Combustion (CBC)


     Circulating bed combustion is an outgrowth of conventional fluidized bed
incineration.  However, the fluid bed operates with higher velocities than
conventional fluid beds and it recirculates the fluidized material within the
system returning it back to the feed  section (Ross, 1984).  Figure 10-53
illustrates a CBC.

     The CBC is suitable for burning  solid, liquid, sludge or gaseous waste
streams.  The advantages of this incinerator are similar to those of a
conventional fluidized bed system with lower susceptibility to corrosion of
the boiler, a less complicated scrubbing system, close temperature control and
dry solid waste recovery.


          10.5.6.5  High Temperature Fluid Wall (HTFW)


     The high temperature fluid wall process quickly reduces organic wastes to
their elemental state in a very high temperature process (about 4000ฐF) (Keitz
and Vogel, 1982).  The process is carried out in a patented reactor which
consists of a tubular core of refractor material capable of emitting radiant
energy supplied by large electrodes in the jacket of the vessel.  During the
process, an inert gas is injected to coat the wall of the reactor and prevent
destruction from high temperatures.  A cross-section of a typical high-
temperature fluid wall reactor is shown in Figure 10-54.  HTFW has been used
to treat PCB contaminated earth and other wastes.  It ensures high destruction
efficiency, eliminates the formation of intermediate pyrolysis products but
requires some preparation of the feed material and it also incurs high energy
costs.
          10.5.6.6.  Pyrolysis


     Pyrolysis is the thermal conversion of organic material into solid,
liquid and gaseous components.  Pyrolysis takes place in an oxygen-deficient
atmosphere at temperatures from 900ฐ to 1600ฐF.  The volatile organics
generated in the process are burned in a second stage fume incinerator at
temperatures of 1800 to 3000ฐF.  The two-stage process minimizes the volatil-
ization of inorganic components and ensures that inorganic.s, including heavy
metals, form an insoluble solid char residue.  The technology may be used for
the destruction of materials containing carbon, hydrogen and oxygen.
Pyrolysis can not handle wastes with nitrogen, sulfur, sodium contents.
                                     10-135

-------
          FIGURE 10-53. CIRCULATING BED COMBUSTOR
                                       PROCESS STEAM
                                         FOR HEATING
SUPERHEATED
   STEAM
  COMBUSTOR
  WASTES, FUEL
      AND
    ADDITIVES
      FEED
                                               QEN
                                                    t—  ELEC-
                                                      TRICITY
feri
J/%T I
HOT
CY-
LONEJ
••'•'/
...7





ป
^^

1


X
EVAPORATIVE &
-"SECTION


*H2O





1 — |



DUST
COLLECTOR
                                                     EXHAUST
                                                       GAS
  AIR-KPO)))))))))))!
  Source: Ross, 1984
                             INERT
                             DUST^

                               TURNS LOW GRADE FUEL INTO POWER
FIGURE 10-54. CROSS-SECTION OF A TYPICAL HIGH-TEMPERATURE
                     FLUID-WALL REACTOR [E]
     Source: Lee, Keitz and Vogel, 1982
                               10-136

-------
          10.5.6.7  Supercritical Water, Advanced Electric and Vertical Tube
                    Reactors
     These incineration methods are basically in the developmental stage and
even though they seem to be very promising further testing is required before
these processes can be commercialized.  The supercritical water process
involves thermal destruction of organics in waste water based on the ability
of many organic compounds to dissolve in super critical water.  The process
can probably be applied to dilute organic wastewaters (5 to 10 percent by
weight) (Ross, 1984).

     The vertical tube reactor is a very unique system for the destruction of
organic wastes in a deep well with the appropriate temperature and pressure.
The advanced electric reactor is also a unique design to treat organic sub-
stances such as PCBs and others.  The process is based on a high temperature
fluidized bed reactor (Ross, 1984).
     10.5.7  Environmental Controls


          10.5.7.1  Air Pollution Controls


     Sources of air pollutants in hazardous waste incinerators include
products of incomplete combustion of organic constituents and conversion of
certain inorganic constituents resulting in gaseous or particulate
contaminants.

     Wet scrubbers are air pollution control devices that use a scrubbing
fluid to wash contaminants from a gas.  Both gaseous pollutants and
particulates may be removed, although particulates may be more
cost-effectively removed using other equipment in some cases (Peacy, 1984).

     Electrostatic precipitation is a process by which particles suspended in
a gas are electrically charged and separated from the gas stream on collecting
plates.  Both dry and wet electrostatic precipitators are available.  Dry
electrostatic precipitators have high efficiency for removal of particulates.
The wet electrostatic precipitator can theoretically remove organic fumes as
well as fine particulates (Peacy, 1984; Kiang and Metry, 1982).

     After burners are basically simple combustion chambers used to burn gases
being emitted from the incinerators.

     Fabric filters or baghouses are air pollution control devices, consisting
of a series of larger tubular bags which remove particulates from gases.
Baghouse filters can be 99 percent effective in the removal of particulates,
provided they are kept clean.

     Gaseous pollutants can be removed from flue gases using one of three
devices:  spray towers, packed-bed towers or plate towers.  All are mass

                                     10-137

-------
transfer devices for gas absorption.  Spray towers have lower removal
efficiencies than that of packed and plate towers and are seldom used for gas
removal (Kiang and Metry, 1982).


          10.5.7.2  Heat Recovery
     There are a variety of methods for recovering waste heat through various
types of heat exchangers.  The most commonly used device is the waste heat
boiler.  Each type of boiler has its own operating characteristics and can be
used to develop steam or hot water.

     Another device for energy recovery is the turbine generator.  It is more
costly than the heat exchangers but has more versatility in terms of product
usage (Peacey, 1984).
          10.5.7.3  Water Pollution Control


     When water scrubbers are used in an incineration system, the acid
scrubber water must be neutralized prior to discharge.


     10.5.8  Overall Operation and Design Considerations


     The overall design of a hazardous waste incinerator requires the
evaluation of many factors including:

     •  Transportation and unloading

     •  Waste segregation

     •  Toxicity, flammability and explosiveness of wastes

     •  Storage

     •  Monitoring
     •  Emissions control

     •  Residue handling and disposal
     •  Other environmental factors.


     10.5.9  Costs
     It is very difficult to calculate the cost of incineration because of the
high degree of complexity of the problem.  The basic factors involved are:

     •  The limited industrial experience with incineration of bulk quantities
        of wastes

                                     10-138

-------
     •  The differences  in  type  of  waste,  operation and design of an
        incinerator

     •  The difficulty in estimating  all  capital,  operating and maintenance
        costs.

The capital cost  is comprised  basically of the cost of purchased equipment and
installation.  The first is  a  firm  cost and the second can vary depending on
the geographic location, the assembly of  control devices, topography and the
availability of utilities.   It consists of the costs of labor and material for
foundations, structural  supports, handling and erection, electrical insula-
tion, construction, permitting and  test burn protocol, etc.  The purchased
equipment costs are comprised  of the  costs of auxiliary equipment, instru-
mentation and control devices  (Monsanto Research Corp., 1981).  Annual
operating and maintenance costs  consist of the cost of labor; material,
including fuel oil and chemicals; residual ash and  waste water disposal;
taxes; insurance; overhead;  etc.  These costs also  include depreciation over
the life of the facility and depend on  the depreciation method and interest
rate of the loan.  Estimated annual operation and maintenance costs vary
depending on size and characteristics of  the waste  stream, size and mechanical
complexity of the incinerator  and how it  is used.   Maintenance costs usually
run about 5% of the depreciable  capital cost.
          10.5.9.1  Examples of  Cost  Estimates
     Figure 10-55 depicts approximate  capital  costs  for  three basic types of
incinerators as a function of  thermal  input.   To obtain  the real cost of the
installed facility the numbers  from  the  figure should be multiplied by 1.5.
The costs of multiple hearth and  liquid  injection incinerators are similar for
the heat input ranging from 5  to  10  MBtu.   The rotary kiln is three times as
           FIGURE 10-55. GENERAL ESTIMATES OF COSTS FOR THREE
                       PREVALENT TYPES OF INCINERATORS
                      3.0

                      2.1
                    I-
                      0.6
                      0.2
                                    Rotary-kiln -a
                                          Heปrtn-
?
                                         Liquid-injection
                            4  6  8 10    20   40  60 S0100
                                HIM Input, million Btu/h
                   Source: Vogel and Martin, 1983
                                     10-139

-------
expensive for the same heat input (Vogel and Martin, 1983).  The operating and
maintenance costs add several hundred thousand dollars to the capital costs
(Vogel and Martin, 1984).

     The estimation of capital costs of an exemplary rotary kiln incinerator
is given in Table 10-19.   The annual operation and maintenance cost for the
same incinerator are listed in Table 10-20.

     Estimated capital and O&M costs for a liquid injection incinerator are
shown in Table 10-21 and 10-22, respectively.  Table 10-23 shows another
estimate of O&M costs for a liquid injection incinerator based on the raw
material requirements shown in Table 10-24.  These costs were derived using a
cost estimation model (McCormick, 1983) and are considerably higher than costs
shown in Table 10-22.
                                      10-140

-------
            TABLE 10-19.  ESTIMATED CAPITAL COST FOR A ROTARY KILN
                 Item                                           1985 Cost $*


Combustion chambers:
  Refractory                                                   $  214,840
  Shell                                                           207,575
  Burners                                                          83,030

Water-storage system (two 10,000-gal tanks)                       122,470

Waste-feed system (screw feeder)                                   10,379

Ash-handling system                                                62,272

Energy-recovery boiler                                            200,984

Air-pollution control system (quench chamber,
  scrubber and absorber)                                          425,530

Blower, 304 stainless steel                                       126.620

Stack (carbon steel, 90 ft at $90/ft)                               8,406

Breeching (refractory-lined, 30 ft. at $300/ft)                     9,341

Total equipment cost                                           Si,571,447

Installation (50% of total equipment cost)                        786,254

Startup (10% of total equipment cost)                             157,238

Spare parts (8% of total equipment cost)                          125,790

Engineering (7% of total equipment cost)                          110,118

Instrumentation (20% of total equipment cost)                     314,580


Total capital cost                                             $3,065,467


 Adapted from Vogel and Martin, 1984.

*Costs updated from 1983 to 1985 dollars using ENR Construction Index.
                                     10-141

-------
       TABLE 10-20.  ESTIMATION OF ANNUAL OPERATION AND MAINTENANCE COST
                               FOR A ROTARY KILN
                 Item                                       1985 Cost $/yr*


Personnel (1 supervisor, 2 operators,
  4 yard-crew workers, 1 secretary)                         $  151,322

Electricity (473 hp) (7,200 h/yr)                              130,772

Water (3.1 x 108 gal/yr)                                       257,393

Auxiliary fuel
  Startup (10) (8 h) (10 x 10  Btu/h)                            4,670
  Operating (4.8 x 10  Btu/h)
  (7,200 h/yr)                                                 430,407

Chemicals (2.25 x 106 Ib lime/yr)                               39,128

Effluent disposal:
  Scrubber liquid (3.1 x 10  gal/yr)                           386,089
  Ash (2.88 x 10  Ib/yr)                                        14,945

Laboratory                                                      62,272

Maintenance (10% of total equipment cost)                      157,238

Refractory replacement (8-yr life)                              26,984

Direct operating cost                                        1,661,220

Value of recovered steam                                     1,245,450

Net operating cost                                             415,770
 Adapted from Vogel and Martin, 1984.

*Costs updated from 1983 to 1985 dollars using ENR Construction Index.
                                     10-142

-------
             TABLE  10-21.  CONCEPTUAL LEVEL CAPITAL COST ESTIMATES
                         FOR A LIQUID INJECTION SYSTEM
               Components                                      Cost

Site Acquisition and Development                            $  500,000
Tanks                                                          150,000
Pumps, Piping, and Compressors                                   35,000
REceiving Station and Compressor Enclosure                       70,000
Control Room, Auxiliaries, and Laboratory                      150,000
Liquid Injection Incinerator                                   175,000
Scrubbing System                                               175,000
Total Installed Cost:                                        1,255,000
  Construction, Overhead, and Fee                              125,000
  Contingency                                                  125,000
  Permitting                                                   100,000
  Start-up and Spare Parts Inventory                             25,000
Total Project Cost:                                         $1,630,000
        TABLE 10-22.  CONCEPTUAL LEVEL OPERATIONS AND MAINTENANCE COST
                    ESTIMATES FOR A LIQUID INJECTION SYSTEM
               Components                                      Cost

Labor and Supervision (2 shifts/day)                          $100,000
Fuel, Electric Power, Water and
  Chemicals and Caustic Soda)                                   75,000
Ash and Wastewater Disposal (assuming use of
  existing wastewater treatment plant)                           5,000
Waste Analysis                                                  30,000
Insurance, Taxes, and Overhead                                  50,000
Maintenance                                                     40,000
Depreciation                                                    75,000
Total Annual O&M Cost:                                        $375,000
 Maintenance costs are difficult to predict due to numerous and complex
 factors.  Conceptual level estimates for a liquid injection system are
 typically five percent of depreciable capital costs, or, as in this case,
 approximately $40,000/yr.
2
 Annualized capital costs depend on how the system is depreciated and the
 interest rate if a loan is taken out instead of taking from cash flow.
 Assuming a 10 year straight-line depreciation, annualized capital cost
 estimates are approximately $75,000/yr.  Given the current tax codes, such
 costs must take into account investment tax and energy recovery credits, as
 well as other corporate income tax adjustments.

Source:  Star, 1985
                                     10-143

-------
             TABLE 10-23.  ESTIMATED ANNUAL O&M COSTS AND CREDITS
                      FOR A LIQUID INJECTION INCINERATOR
                                                  1985
        Item                                   Annual Cost
Natural gas                                     $ 36,326
No. 2 fuel oil                                     1,245
Power                                             72,665
Water                                             12,450
Caustic soda solution (50 wt %)                  118,490
Liquid nitrogen                                    5,397
Sewer                                             60,197
Labor                                            166,060
Maintenance                                       77,841
Depreciation                                     155,681
Insurance/taxes                                   62,272
   Total                                        $768,624

Source:  McCormick, 1983.
Costs updated to $1985 using 1983 and 1985 ENR Construction Cost Indices,
                                     10-144

-------
           TABLE 10-24.  ESTIMATED RAW MATERIAL/UTILITY REQUIREMENTS
      Item
Normal Rate
Total Annual Quantity
Fuel
  Natural gas for flame
   stabilization
  No. 2 fuel oil for startup
1000 scfh
 100 gal/startup
    7 M ff
 1400 gal
Power
Id fan
Compressor
Blower
Pumps
Agitators
Total
Water
Caustic soda solution
(50 wt %)
Liquid nitrogen
Sewer use

95 hp
70 hp
35 hp
20 hp
nil
220 hp
110 gpm
230 Ib/hr

38 ft3/hr
110 gpm

-
-
-
-
-
1.15 Gwh
48 M gal
1.6 M Ib

270 M ft3
45 M gal

Source:  McCormick, 1983
                                     10-145

-------
                                  REFERENCES
Allis Chalmers.  Undated.  Selection of Vibrating Screens.   General Screen
Information, Item 3.  Milwaukee, WI.

Azad, H.S. (ed.)  1976.  Industrial Wastewater Management Handbook.  McGraw-
Hill Book Company, NY.

Brunotts, V.A., L.R. Emerson, E.N.  Rebis, and A.J.  Roy.   1983.   Cost Effective
Treatment of Priority Pollutants Compounds with Granular Activated Carbon.
Management of Uncontrolled Hazardous Waste Sites.  Proceedings, Hazardous
Materials Control Research Institute, Silver Spring, MD.  pp. 209-216.

Calgon Carbon Corporation.  1983.  Interphase Groundwater Treatment System.
23-156a.  Pittsburgh, PA.

Calgon Corporation.  Undated.  Air  Purification with Granular Activated
Carbon.  Brochure 23-55.

Carter, L.W. and R.C. Knox.  1985.   Groundwater Pollution Control.  Lewis
Publishers Inc.  Chelsea, MI.  526  pp.

Chemical Separations Corp.  Undated.  Ion Exchange Systems.  Oak Ridge, TN.

Clark, D.E., P. Colombo, and R.M. Neilson, Jr.  1982.  Solidification of Oils
and Organic Liquids.  BNL-5162.  Prepared for:  Brookhaven National
Laboratory.  U.S. Department of Energy.  25 pp.

Conway, R.A. and R.D. Ross.  1980.   Handbook of Industrial Waste Disposal.
Van Nostrand Reinhold Co., NY.

Cullinane, M.J. and L.W. Jones.  1985.  Technical Handbook for
Stabilization/Solidification of Hazardous Waste.  Prepared for:  USEPA
Hazardous Waste Engineering Research Laboratory, Cincinnati, OH.

Gulp, R.L., Wesnar and G.L. Gulp.  1978.  Handbook of Advanced Wastewater
Pretreatment.  Van Nostrand Reinhold  Environmental Engineering Series, New
York, N.Y.

De Renzo, D. (ed.)  1978.  Unit Operation for Treatment of Hazardous Wastes.
Noyes Data Corporation, Park Ridge, NJ.

Derrick Manufacturing Corporation.   Undated.  Principles of High Speed
Screening and Screen Machine Design.  Buffalo, N.Y.  3 pp.

Dorr-Oliver, Incorporated.  1984.  The Dorrclone Hydrocyclone.  Bulletin DC-2.
Stamford.  CT.

Dorr-Oliver, Incorporated.  1983.  DSM Screens for the Process Industries.
Bulletin No. DSM-1.  Stamford.  CT.
                                     10-146

-------
                            REFERENCES (continued)
Dorr-Oliver.  1980.  Fine screening for mineral processing - Rappafine DSM
Screen.  Bulletin DSM6.  Stanford.  CT.

Dorr-Oliver, Incorporated.  1976.  Dorr-Oliver Clarifiers for Municipal and
Industrial Wastewater Treatment.  Bulletin No. 6192-1.  Stamford, CT.

Doyle, R.D.  1980.  Volume Reduction and Detoxification of Hazardous Wastes by
Encapsulation in an Asphalt Binder.  35th Industrial Waste Conference.  Purdue
University.  Anne Arbor Science Inc., Lafayette, IN.  pp. 761-767.

Eagle Iron Works.  1982.  Eagle Fine and Coarse Material Washers.  General
Catalog, Section C.  Des Moines.  IOWA.

Eagle Iron Works.  1981.  Eagle Water Scalping and Coarse Material Washers.
General Catalog, Section B.  Des Moines.  IOWA.

Erickson, P.R. and J. Hurst.  1983.  Mechanical Dewatering of Dredged
Slurries.  Ninth Meeting, U.S.-Japan Conference on Management of Bottom
Sediments Containing Toxic Substances.   Jacksonville, FL, October 17-18.

Ghassemi, M., K. Yu, and S. Quinlivan.   1981.  Feasibility of Commercialized
Water Treatment Techniques for Concentrated Waste Spills.  Prepared for:
USEPA, Municipal Research Laboratory, Cincinnati, OH.

Gooding, C.H.  1985.  Reverse Osmosis and Ultrafiltration.  Chemical
Engineering, January 5, 1985.  pp. 56-62.

Granlund, R.W. and J.F. Hayes.  Undated.  Solidification of Low-Level
Radioactive Liquid Waste Using a Cement-Silicate Process.  Delaware Custom
Material Inc., State College, PA.

Haliburton, T.A.  1978.  Guidelines for Dewatering/Densifying Confined Dredged
Material.  Technical Report DS-78-11.  Prepared for:  Office, Chief of
Engineers, U.S. Army, Washington, DC.

Hansen, S.P., R. Gumerman, and R. Gulp.  1979.  Estimating Water Treatment
Costs.  Volume 3:  Cost Curves Applicable to 2500 gpd to 1 mgd Treatment
Plants.  EPA-600/2-79-162c.  USEPA, Municipal Environmental Research
Laboratory, Cincinnati, OH.

Hoffman Muntner Corporation.  1978.  An Engineering/Economic Analysis of Coal
Preparation Plant Operation and Costs.   Preparation for US Department of
Energy and US Environmenatl Protection Agency.  Washington, D.C.  PB-285-251.

Jones, R.H., R.R. Williams and T.K. Moore.  1978.  Development and Application
of Design and Operation Procedures for Coagulation of Dredged Material Slurry
and Containment Area Effluent.  Prepared for:  Office, Chief of Engineers,
U.S. Army.  Technical Reprot D-78-54.
                                     10-147

-------
                            REFERENCES (continued)
Keitz, E.L. and C.C. Lee.   1983.   A profile of Existing Hazardous Waste
Incineration Facilities.   In Proceedings of the Ninth Annual  Research
Symposium Incineration and Treatment of Hazardous Wastes,  EPA 600/9-83-003.
US Environmental Protection Agency,  Industrial Environmental  Research
Laboratory, Cincinnati, OH.

Kiang, Y. and A.R. Metry.   1982.   Hazardous Waste Processing  Technology.   Ann
Arbor Science Publishers,  Inc., Ann Arbor,  MI.

Krebs Engineers.  Undated.  Krebs Cyclones  for the Mining  Industry.   Krebs
Bulletin No. 21-130.  Menlo Park, CA.

Krebs Engineers.  Undated.  Krebs Water Only Cyclones.  Menlo Park,  CA.

Krizek, R.J., J.A. Fitzpatrick and O.K. Atmatzidis.  1976.  Investigation of
Effluent Filtering Systems for Dredged Material Containment Facilities.
Prepared for:  Office, Chief of Engineers,  U.S. Army, Washington, DC.  Report
D-76-8.

Lee, C.C.  1983.  A comparison of innovative technology for thermal
destruction of hazardous waste.  In:  Proceedings of 1st Annual Hazardous
Materials Management Conference,  Philadelphia, PA.  July 12-14.

Lee, C.C., E.L. Keitz and G.A. Vogel.  1982.  Hazardous Waste Incineration:
Current/Future Profile.  In:  Proceedings of the National  Conference on
Management of Uncontrolled Hazardous Waste  Sites.  Nov. 29-Dec. 1, Washington,
D.C.

Lee, M.D. and C.H. Ward.  1984.  Reclamation of Contaminated  Aquifers:
Biological Techniques.  1984 Hazardous Material Spills Conferences
Proceedings, Government Institutes,  Inc., Rockville, MD.

Lubowitz, H.R. and C.C. Wiles.  1981.  Management of Hazardous Waste by
Clinque Encapsulation Process.  In:   Land Disposal of Hazardous Waste.
Proceedings of the Seventh Annual Research Symposium.  EPA-600/9-81-002b.
USEPA, Municipal Environmental Research Laboratory, Cincinnati, OH.
pp. 91-102.

Mallory, C. and M. Nawrocki.  1974.   Containment Area Facility Concepts for
Dredged Material Separation, Drying, and Rehandling.  Contract report D-74-6.
Hittraan Associates, Inc. Prepared for:  U.S. Army Engineer Waterways
Experiment Station.  Vicksburg, MS.

Metal Finishers' Foundation.  1977.   Treatment of Metal Finishing Waste by
Sulfide Precipitation.  PB-267-284.   Prepared for Industrial Environmental
Research Lab, Cincinnati, OH.

Metcalf and Eddy, Inc.  1979.  Wastewater Engineering Treatment Disposal.
McGraw-Hill, Inc., N.Y.

                                     10-148

-------
                            REFERENCES (continued)
Monsanto Research Corporation.  1981.  Engineering Handbook In Hazardous Waste
Incineration.  NTIS-PB81-248163.

Moore, Gardner and Associates.  1983.  Final Activity Report Shipyards
Investigation Pearl Harbor Navy Shipyard, Pearl Harbor, Hawaii.  Prepared for
Department of the Navy, Naval Facilities Engineering Command.

Nalco Chemical Co.  1979.  Nalco Water Handbook.  McGraw-Hill, Company,
New York, NY.  p. 12-1.

O'Brien, R.P. and J.L. Fisher.  Undated.  There is an Answer to Groundwater
Contamination.  Reprinted from:  Water/Engineering and Management.

O'Brien, R.P. and M.H. Stenzel.  1984.  Combining Granular Activated Carbon
and Air Stripping.  Reprinted from Public Works, December 1984.

Oklahoma State University.  1973.   Feasibility Study of Hydrocyclone Systems
For Dredge Operations.  AD-766-212, Prepared for:  Army Engineer Waterways
Experiment Station.

Parkson Corporation.  1984.   Lamella Gravity Settler/Thickener.  Bulletin
LT-103.  Fort Lauderdale, FL.

Peacy, J.  1984.  A Special  Roundup Feature Report on Incineration.  Pollution
Engineering.  Vol. 16, No. 16.  April 1984.

Perry, R.H. and C.H. Chilton.  1973.  Chemical Engineers Handbook.  McGraw
Hill Book Company, New York, NY.

Pradt, L.A.  1976 (updated 1972).   Developments in Wet Air Oxidation.
Reprinted from:  Chemical Engineering Progress.  Vol. 68, No. 12.
pp. 72-77.

Rockwell International.  1980.  Molten Salt Destruction of Hazardous Wastes.
Pub. 523-L-18-1.  Canoga Park, CA.

Ross, R.D.  1984.  Hazardous Waste Incineration:  More Attractive Now Than
Ever Before.  Hazardous Materials and Waste Management.  Vol. 2, No. 5.

Shuckrow, A.J., A.P. Pajak,  and C.J. Touhill.  1980.  Management of Hazardous
Waste Leachate.  SW-871.  Prepared for:  USEPA, Municipal Environmental
Research Laboratory, Cincinnati, OH.

Smith, C.L. and K.E. Zenobia.  1982.  Pozzolanic Microencapsulation for
Environmental Quality Assurance.  In:  37th Industrial Waste Conference.
Purdue University.  Ann Arbor Science, MI.  pp. 397-403.
                                     10-149

-------
                            REFERENCES (continued)
Solsberg, L.B., R.D.  Parent,  and S.L.  Ross,  1985.   A Survey of Chemical  Spill
Countermeasures.  Prepared for Environmental Emergencies Technical Division,
Environmental Protection Service, Ottawa,  Canida.   January, 1985.

Spencer, R.W., R.H.  Reifsnyder, and J.C.  Falcone.   1982.   Applications of
Soluble Silicates and Derivative Materials.   Management of Uncontrolled
Hazardous Waste Sites Proceedings, Hazardous Materials Control Research
Institute, Silver Spring, MD.  pp. 237-243.

Star, A.M.  1985.  Cost estimating for hazardous waste incineration.
Pollution Engineering.  Vol.  17, No. 4.

State of California,  Governors' Office of Appropriate Technology.   1981.
Alterantives to the Land Disposal of Hazardous Wastes.  An Assessment for
California.

United States Gypsum Company.  1982.  Environstone Gypsum Cement:   A Major
Breakthrough in Radwaste Binder Technology.   TAC-225/USG/6-82.  Chicago,  IL.

USEPA.  1973.  Process Design Manual for Activated Carbon Adsorption.  EPA
625/l-71-002a.

USEPA.  1978.  Sludge Handling and Conditioning.  EPA 430/9-78-002.
Washington, DC.

USEPA.  1979.  Process Design Manual:   Sludge Treatment and Disposal.  EPA
625/1-79-011.  Municipal Environmental Research Laboratory, Cincinnati,  OH.

USEPA.  1980.  Innovative and Alternative Technology Assessment Manual.   EPA
430/9-78-009.  Office of Water Program Operations, Washington, DC and
Municipal Environmental Research Laboratory, Cincinnati, OH.

USEPA.  1982a.  Design Manual:  Dewatering Municipal Wastewater Sludges.
EPA-625/1-82-014.  Municipal Environmental Research Laboratory, Cincinnati,
OH.

USEPA.  1982b.  Guide to Disposal of Chemically Stabilized and Solidified
Waste.  SW-872.  Office of Solid Waste and Emergency Response, Washington, DC.

Van Note, R.H. et al.  1975.   A Guide to the Selection of Cost-Effective
Wastewater Treatment Systems.  EPA-430/9-75-002.  USEPA, Washington, DC.

Vatavuk, W.M.  and R.B. Neveril.  1983.  Cost of Flares.  Chemical Engineering,
Vol. 90, No. 4.

Vogel, G.A. and E.J.  Martin.    1984.  Example of Incineration Cost Estimation.
Chemical Engineering.  Vol. 91, No. 3.
                                     10-150

-------
                            REFERENCES (Continued)
Vogel, G.A., E.J. Martin.  1983.  Equipment Sizes and Integrated Facility
Costs.  Chemical Engineering Vol. 90, No. 18.

Water Purification Associates.  1975.  Innovative Technologies for Water
Pollution Abatement.  NTIS PB-247-390.

Weber, W.J.  1972.  Physiochemical Processes for Water Quality Control.
Wiley-Interscience, New York, NY.

Whittaker, H.  1984.  Development of a Mobile  Reverse Osmosis Unit for Spill
Clean Up.  Hazardous Material Spills Conference, April 9-12.  Government
Institutes, Inc., Rockville, MD.

Whittaker, H., C.I. Adams, S.A. Salo, and A. Morgan.  1985.   Reverse Osmosis
at the Gloucester Landfill.  In:  Proceedings  of the Technical Seminar on
Chemical Spills, Environment Canada, Ottawa, Canada,  pp.  191-207.
                                     10-151

-------
                                  SECTION  11

             CONTAMINATED WATER SUPPLIES AND WATER AND SEWER LINES
     Hazardous substances can enter public water  systems  through  a wide
variety of pathways, contaminating the components of  the  systems  as well  as
the water.  Once contaminated, water systems can  serve  as  secondary sources  of
contamination, and the systems' users can be exposed  to hazardous substances
over long periods of time.

     Sanitary and storm sewers can become contaminated  by infiltration of
leachate or contaminated groundwater through cracks,  ruptures,  or poorly
sealed joints in piping and by direct discharges  into the lines.  Potable
water supply mains can become contaminated by contact with contaminated water
that may inadvertantly flow through them, or by infiltration  of leachate  or
contaminated groundwater.  However, water mains are less  susceptible  to the
infiltration of contaminants, since they are generally  full-flowing,  pres-
surized systems.  The public health consequences of the contamination of
municipal mains carrying potable water supplies to commercial  and residential
consumers are potentially much greater than the consequences  of the contami-
nated sewage flowing to a treatment plant or of surface runoff  draining to
surface waters.

     This Section presents methods for providing water  supplies of acceptable
quality with the minimum disruption of service; the methods are as follows:

     •  Water supply replacement:
        -  New central water supply
           Point-of-use water supplies
     •  Water Treatment:

           Central water treatment
           Point-of-use water treatment

     •  Alteration of water and sewer pipelines:
           Replacement

           Inspection and leak detection
        -  Cleaning

           Repairing and lining.
                                      11-1

-------
11.1  Replacement of Contaminated Central Water Supplies


     Replacement of central water supplies, or sources of water  that  serve
many users through central distribution systems, generally  involves one  or
more of the following approaches:

     •  Purchase of water from another supply
     •  Provision of a new surface water intake(s)

     •  Provision of a new groundwater well(s).

     The contaminated water supply may be abandoned or may  be blended with  the
new supply to achieve acceptable water quality by dilution.  Combinations of
the approaches may be employed either concurrently (multiple replacement
supplies) or consecutively (emergency water purchased  from  a neighboring
supply unit, followed by new wells or intakes.)

     Purchase of treated water from another supply requires a cross-
connection^) between the systems.  Many neighboring public water  departments,
authorities, and companies maintain networks of interconnections that allow
ready flow and meeting between systems for emergencies such as  droughts,
fires, line breakage, or malfunction of treatment  facilities.   Where  cross-
connections do not exist, water  transmission  lines can be  installed.   The
information provided in Section  11.5 generally applies to new water pipelines.
Numerous references are available that guide  the design  and installation of
water transmission and distribution systems,  including Fair (1971) and
American Society of Civil Engineers (ASCE, 1975).

     Provision of new surface water intake may be  feasible  where a groundwater
source is to be replaced or where a replacement surface  water  intake  would
hydraulically isolate the water  supply system  from contaminated  surface  water
(e.g., intake upstream of the source of contamination).

     Surface water is drawn from rivers, lakes, and reservoirs  through
relatively simple submerged intake pipes, or  through fairly elaborate
towerlike structures that rise above the water surface.   Important in the
design and operation of intakes  is that the water  they draw be  as  clean,
palatable, and safe as the source of supply can provide.  River intakes  are
constructed well upstream from points of discharge of  sewage  and industrial
wastes.  Optional location should take advantage of deep water,  a  stable
bottom and favorable water quality, all with  proper reference  to protection
against  floods, debris, ice, and river traffic.  Small streams  may be dammed
up  by diversion or intake dams to keep intake  pipes submerged  and  preclude
hydraulically wasteful air entrainment.  Lake  intakes  are  sited with  due
reference to sources of pollution, prevailing  winds, surface  and subsurface
currents, and shipping lanes.  Shifting the depth of draft  makes it possible
to  collect clean bottom water when the wind is offshore,  and,  conversely,
clean surface water when the wind is onshore.  Reservoir intakes, resemble  lake
intakes  but generally lie closer to shore  in  the deepest part  of the
reservoir.  They are often incorporated into  the impounding structure itself
(Fair, 1971).

                                     11-2

-------
     The feasibility of providing new  surface water  intakes  is  dependent  on
numerous case-specific requirements  and conditions,  summarized  as  follows:

     •  Proximity of the point of intake  to  the water  supply system

     •  Peak demand flow versus historic  and predicted  low  flow in the  water
        body

     •  Downstream environmental, recreational, and  commercial  effects  of
        reduced flow

     •  Quality of the surface water and  corresponding  treatment requirements.

     Provision of new groundwater wells is often  feasible where  the  extent of
aquifer contamination is relatively  confined and  would  not  be expected  to be
drawn to the area of influence of the  new wells,  or  where other  (usually
deeper) aquifers can be tapped as a  replacement water  supply.   The information
provided in Section 5.1 generally applies to the  design  and  construction  of
new groundwater wells.


11.2  Point-of-Use Water Supplies


     Central water supplies that are contaminated  at the source  or in trans-
mission through pipelines can be replaced permanently  or temporarily with an
independent supply at each point of  usage.   Such  supplies could  include one or
a combination of the following:

     •  Bottled and bulk water

     •  Point-of-use wells
     •  Collection of rain water.

     The use of bottled and bulk water is common  for temporary  or  semi-
temporary water supplies on an emergency  basis until more permanent  water
supply arrangements can be made.  Bottled water is widely available  in  small
quantities from common retail outlets  (grocery and drug  stores)  and  in  large
quantities from commercial distributors.  Larger  bottles (e.g.,  five-gallon
"water cooler" bottles) require dispensers in order  to  be conveniently  used.
Their full weight (approximately 50  pounds) may present  handling and
change-over problems for some users.

     Bulk water can be provided in portable  tanks  (trailers  or  tank  trucks) by
commercial, clean water contractors  and by public  emergency  service  organiza-
tions (e.g., Army National Guard).   Tanks normally used  for  other  purposes,
such as milk tank trucks, have also  been  used.  The  tanks are typically made
available to homeowners at temporary,  centrally located  distribution points,
where small containers can be filled for  home use.   Whole tanks  can  be  made
available to commercial and institutional establishments.
                                     11-3

-------
     Point-of-use wells, or individual wells for each user establishment, may
be feasible as a permanent alternative to a contaminated central supply,
provided that the available groundwater is and can be expected  to remain
non-contaminated.  The information provided in Section 5.1 generally applies
to development of new groundwater wells.

     Rainwater is rarely the immediate source of municipal water supplies, but
could serve as a replacement to a contaminated water supply.  The use of rain-
water is generally confined to farms and towns in semiarid regions devoid of
satisfactory groundwater or surface water supplies.  For individual users,
rainwater running off the roof is led through gutters and downspouts to a
cistern situated on or below the ground.  Cistern storage converts the
intermittent rainfall into a continuous supply.  For municipal  service, roof
water may be combined with water collected from sheds or catches on the
surface of ground that is naturally impervious or rendered so by grouting,
cementing, paving, or similar means (Fair, 1971).

     The gross yield of rainwater supplies is proportional to the receiving or
drainage area and the amount of precipitation.  Because of the  relatively
small catchment area available, roof drainage cannot be expected to yield an
abundant supply of water, and a close analysis of storm rainfalls and seasonal
variations in precipitation must be made if catchment areas, standby tanks,
filters, and cisterns are to be proportioned and developed properly (Fair,
1971).
11.3  Treatment of Contaminated Central Water Supplies


     Central water supplies that are contaminated at  the  source  can be  treated
to acceptable quality at central treatment  systems.   For  some  supplies,  such
as in small communities that pump groundwater directly to distribution  systems
without treatment, central treatment may require installation  of new  facili-
ties.  For other supplies, such as in  large communities that already  treat
surface water before distribution, upgrading of existing  treatment with the
installation of polishing units may be necessary (Morrison,  1981).

     Available water treatment methods include physical,  chemical, and
biological technologies, and combinations of these methods may be used  for
removal of some contaminants.

     Many of the technologies described in  Section  10-1,  for treatment  of
aqueous wastes also apply to treatment of contaminated water supplies.   In
general, however, those technologies that are normally associated with
"polishing" (i.e., removal of low concentrations of contaminants), such as
activated carbon, ion exchange, and reverse osmosis,  are  most  applicable to
treatment for public water supplies.
                                      11-4

-------
11.4  Point-of-Use Water Treatment


     11.4.1  General Description


     Central water supplies that are contaminated at  the  source  or  in
transmission can be treated to acceptable quality at  the  point of use  (POU)
with a variety of commercially available systems.  Most applications of  POU
treatment units are for aesthetic purposes (taste, odor,  and color), although
their use is increasing for removal of organic contaminants from drinking
water (Anderson, 1984a).

     POU units are generally used in one of the  following  situations in
residential applications:

     •  Line-bypass, where separate faucets are  provided  for treated and
        non-treated water; treated water is generally used for drinking,
        cooking, etc.

     •  Faucet-mounted, where all water passing  through the faucet  is  treated.

     •  Whole-house, where all water entering the house is treated.

Line-bypass systems afford a compromise, providing only for treatment  of water
to be consumed, thereby minimizing treatment demands  and  costs.

     POU treatment processes include the following (Anderson, 1984a; Perry,
1981):

     •  Activated carbon

     •  Activated alumina

     •  Reverse osmosis

     •  Ion exchange

     •  Distillation

     •  Ozonation
     •  Ultraviolet irradiation.

Of these processes, activated carbon is the most widely used and accepted
process.  Reverse osmosis and ion exchange are also widely available for
applications where more stringent water quality  requirements apply  (hospitals,
laboratories, etc.).  Section 10.1 should be consulted for the applications
and limitations of these methods.
                                     11-5

-------
     11.4.2  Applications/Limitations
     POU units are designed to remove a wide variety of contaminants from
water.  Manufacturers' claims vary, and numerous studies have been conducted
to test the effectiveness of various units (Anderson, 1984a and b; Perry,
1981; Taylor, 1978).

     Table 11-1 summarizes the general applications and limitations of the
commonly used types of POU units.  A major limitation common to all POU units
is their reliance on the user (or service contracted by the user). If the
units are not properly installed, operated, and maintained, the desired treat-
ment may not be affected, or the accumulated contaminants may be  released from
the treatment unit after the treatment material is exhausted.  (Taylor, 1978).
                                  TABLE 11-1.
  APPLICATIONS AND LIMITATIONS OF COMMONLY USED POINT-OF-USE TREATMENT UNITS
       Process
   Applications
         Limitations
Activated carbon
Organics, hydro-
carbons, chlorine,
trihalomethanes (THM)
some pesticides
Reverse osmosis
Fluoride, total dis-  <
solved solids, sodium,
sulfate, salts, metals
 Ion  exchange
Dissolved minerals,
metals, most inorganics
Potential for excess growth of
bacteria (Taylor, 1978)

Short-lived effectiveness for
some contaminants (chlorine,
THM, pesticides) (Taylor, 1978)

Potential desorption (release
of contaminants) following
exhaustion of carbon (Taylor,
1978)

High-pressure required to
affect filtration

Low flow rate capacity requires
storage tank and/or multiple
systems in parallel
                                      11-6

-------
     11.4.3  Design Considerations


     The primary design considerations for POU units are 1) selection of  the
appropriate units for the contaminant(s) of concern, 2) selection of the
appropriate hydraulic capacity for the application, and 3) provision of
appropriate criteria and schedules for maintaining  the units.  This informa-
tion is generally available from the manufacturer or supplier.

     Manufacturers' and suppliers' performance information should be confirmed
by laboratory or trial tests under any of the following circumstances:

     •  Information has not been confirmed by a reputable organization or
        laboratory (National Sanitation Foundation  (NSF), 1981)

     •  Disparate contaminants are present

     •  Concentrations of contaminants vary widely  over time

     t  Contaminants and concentrations pose a high risk to human health

     •  Large numbers of units are to be employed.


     11.4.4  Construction/Implementation Considerations


     Installation procedures are provided by the manufacturer of each POU
unit.  Installation should be made by a licensed plumber and/or approval of
the installation should be given by a local plumbing inspector.  This is
particularly important for whole-house units and by-pass units to ensure  that
backflow and inappropriate cross-connections are averted.


     11.4.5  Operation, Maintenance, and Monitoring


     Once installed, POU units operate relatively passively and require little
or no attention.  Proper maintenance and monitoring, however, are essential to
the effectiveness and safety of the units.  Maintenance generally consists of
changing the cartridges on a regular schedule.  However, few units give any
detectable indication of having reached capacity.  Conservative change-over
schedules are recommended to help ensure that the units continuously serve
their intended purpose.  Alternatively, frequent monitoring of the quality of
the treated water could be conducted by sampling and analysis to identify the
need for cartridge changes. Many full-service water treatment companies
provide installation and maintenance services.
                                     11-7

-------
     11.4.6  Technology Selection/Evaluation
     The selection of the appropriate POU unit is based  largely on  the
contaminants to be removed.  The applicability of the commonly used type of
POU units is provided in Table 11-1.  Reliability of performance  should be a
major consideration in evaluating POU units relative to  other water supply or
treatment technologies, as their reliance on the user or user-contracted
services for installation and maintenance does not necessarily ensure a
continuously safe water supply.
     11.4.7  Costs
     Typical initial equipment, installation, and monthly maintenance  costs
for POU treatment devices are shown in Table  11-2.  Maintenance  costs  include
changing of treatment cartridges on schedules consistent with  the units'
capacities and residential rates of water consumption.
             1985
               TABLE 11-2.
COSTS FOR POINT-OF-USE WATER TREATMENT SYSTEMS
        Type of System
          Initial Costs
Maintenance Cost
Activated carbon

Activated alumina

Reverse osmosis

Deionization

Combined activated carbon
          $300-400/unit

          $200-400/unit

          $550/unit

          $700/unit

          $700-800/unit
   $2-3/month

   $1-4/month

   $7-11/month

   $4-6/month

   $8-12/month
Source:  Anderson,  1984b; Consumers Union  1984;  Ingram,  R.,  Culligan  Water
Conditioning of Greater Washington, Vienna,  VA,  personal communication,  March
1985.
                                      11-8

-------
11.5  Replacement of Water and Sewer Lines


     11.5.1  General Description


     Replacement of water and sewer pipelines that are contaminated by contact
with hazardous substances is seldom more cost-effective than rehabilitation,
but may often be the only practical alternative.  Replacement  involves exca-
vation of trenches, laying of new lines with noncontaminated pipe materials,
laying new connections and/or tying in connections, and associated backfilling
and surface restoration.  Contaminated pipelines may either be abandoned
in-place or removed in the course of trench excavation.  Construction of water
and sewer lines is common in land development projects and the associated
methods, materials, and equipment are well-established.


     11.5.2  Applications/Limitations


     Pipeline replacement is applicable to virtually all cases of pipeline
contamination.  Excavation and replacement of defective sewer pipe segments is
normally undertaken when the structural integrity of the pipe has deteriorated
severely; for example, when pieces of pipe are missing, pipe is crushed or
collapsed, or the pipe has large cracks—especially longitudinal cracks, and
alternative rehabilitative techniques are not feasible.  In addition, pipeline
replacement is often required when the pipe is significantly misaligned (Water
Pollution Control Federation (WPCF), 1983).  Factors that would limit the
feasibility of pipeline replacement are:

     •  Disruption of service and interim provisions
     •  Accessibility of pipeline and connections
     •  Interference of other utilities
     •  Disruption of vehicular traffic
     •  Depth of excavation
     •  Soil and groundwater
     •  Costs.

     The primary disadvantage of pipeline replacement is the high cost.
Analyses to determine the cost-effectiveness of pipe replacement must include
all costs associated with the replacement.  These costs typically include
pavement removal and replacement; excavation; possible substitution of select
backfill to replace poor quality existing material; dewatering and shoring,
pipe materials and couplings, and traffic control.  Potential cost increases
resulting from interference with other underground utilities and narrow
casements or limited space for construction must also be considered.  In
addition, consideration must be given to the need for temporary flow rerouting
                                     11-9

-------
to maintain service.  Depending on the service  life assumed  for other  reha-
bilitation methods, the possible higher capital costs may be somewhat  offset
by the longer service life a new line provides  (WPCF, 1983).


     11.5.3  Design Considerations


     In general, new pipeline systems will mimic the systems that  they replace
(size, material, grade, location, capacity, etc.).  The considerations  that
govern the design of new systems will apply, but not control.  Logistics  and
the presence of fixed constraints will dictate  how  the replacement  system is
designed.  However, the need for replacement may provide an  "opportunity" to
upgrade the systems in terms of capacity, improved materials and methods,
location, and/or direction of flow, and some consideration would be given to
criteria for the design of new systems (WPCF, 1983).

     The design of water distribution and sanitary  sewer systems is addressed
in numerous manuals and guidebooks, including ASCE  (1975 and 1976).   Informa-
tion that is needed as input to the design includes:

     •  Population drawing from or contributing to  the system

     •  Per capita water demand or sewage discharge

     •  Commercial, industrial, and institutional demand or  discharge

     •  Minimum and peak daily demand or discharge

     •  Fire-fighting requirements

     •  Soil, groundwater, near-surface and geologic conditions

     •  Topography and grades

     •  Locations of potentially interfering features (utilities,  buildings,
        etc.) .

     ASCE (1976) recommends  that estimates of sewage flow be based on  con-
sideration of the  following:

     •  The design period during which the predicted maximum flow  will not be
        exceeded,,  usually 25 to 50 years in the future.

     •  Domestic sewage contributions based on  future population and future
        per-capita water consumption.  If a more  satisfactory  parameter than
        water consumption is available,  that parameter should  be used.

     •  In some  instances, maximum  flow  rates may  be determined  almost
        entirely by extraneous  flows,  the  source  of which may  be  foundation,
        basement,  roof, or areaway  drains,  storm  runoff  entering  through
        manhole covers, or infiltration.

                                      11-10

-------
     •  Commercial area contributions are sometimes assumed to be adequately
        provided for in the peak allowance for per capita sewage flows in
        small communities

     •  Industrial waste flows should include the estimated employee contri-
        bution, estimated or gauged allowances per acre for industry as a
        whole, and estimated or actual flow rates from plants with process
        wastes that may be permitted to enter the sanitary sewer

     •  Institutional wastes are usually domestic in nature although some
        industrial wastes may be generated by manufacturing at prisons,
        schools, hospitals, etc.

     •  Air-conditioning and industrial cooling waters, if permitted to enter
        sewers, may amount to 1.5 to 2.0 gpm per ton of nonwater-conserving
        cooling units

     •  Infiltration may occur through defective pipe, pipe joints, and
        structures.  Design allowances should be larger (under some circum-
        stances, very much larger) than those stipulated in construction
        specifications for which acceptance tests are made very soon after
        construction.

     The relative emphasis given to each of the foregoing factors varies among
engineers.  Some have set up single values of peak design flow rates for the
various contributory items listed above.  It is recommended, however, that
maximum and minimum peak flows used for design purposes be developed step by
step, giving appropriate consideration to each factor which may influence
design.  (ASCE, 1976).

     If a sewer is to transport stormwater or wastewater from one location to
another, it must be constructed sufficiently deep (below the ground surface)
to receive these flows from basic or service connections.  It should be
resistant to both corrosion and erosion and its structural strength must be
sufficient to carry backfill, impact, and live loads satisfactorily.  The size
and slope, or gradient, of a sewer must be adequate for the flow to be carried
and be sufficient to avoid deposition of solids.  The type of  sewer joint
must be selected to meet the conditions of use as well as those of the ground.
Economy of maintenance, safety to personnel and the public, and public
convenience during its life and during construction also must be considered
(ASCE, 1976).

     The pipe material used for sanitary and storm sewers can influence other
design decisions and should, therefore, be selected early in the design
process.

     Factors that should be considered in the selection of materials for both
water and sewer construction are (ASCE, 1976):

     •  Flow characteristics-friction coefficient

     •  Life expectancy and use experience

                                     11-11

-------
     •  Resistance to scour
     •  Resistance to acids, alkalis, gases, solvents, etc. (sewers only)
     •  Ease of handling and installation
     •  Physical strength
     •  Type of joint - watertightness and eas-e of assembly
     •  Availability and ease of installation of fittings and connections
     •  Availability in sizes required
     •  Cost of materials,  handling, and installation.

     No single material will meet all conditions that may be encountered in
sewer design.  Selections should be made for the particular application and
different materials may be selected for parts of a single project (ASCE,
1976).
     New materials are continuously being offered for use in sewer construc-
tion.  Some of the more commonly used materials are (ASCE, 1976):
     •  Asbestos cement
     •  Brick masonry
     •  Vitrified clay
     •  Concrete
        -  Precast
           Reinforced precast
           Cast-in-place
     •  Iron
        -  Cast iron
           Ductile iron
     •  Fabricated steel
           Corrugated
           Plain
     •  Organic synthetic materials
           Solid-wall plastic (polyvinyl chloride (PVC), polyethylene,
           acrylonitrile-butadiene-styrene (ABS), fiberglass reinforced
           plastic)
           Truss pipe
           Corrugated polyethylene.
                                     11-12

-------
     Estimates of flow and system pressure in water distribution systems are
based on the following (Fair, 1971):

     •  Domestic, industrial, and other normal uses, determined in a manner
        similar to estimating sewage flow

     •  Standby requirements for fire-fighting as required by local codes
        and/or the American Insurance Association

     •  Estimates of system leaking

     •  Calculation of in-transit frictional pressure losses.

     A variety of pipe materials are also available for water systems; among
the most common are (ASCE, 1975):

     •  Iron

           Ductile iron

        -  Cast iron

     •  Concrete

     •  Asbestos - cement

     •  Steel

     •  Organic synthetic materials:

        -  Polyvinyl chloride (PVC)

        -  Polyethylene (PE)

           Acrylonitrile - butadiene - styrene (ABS).


     11.5.4  Construction/Implementation Considerations


     A variety of conventional and nonconventional methods are available for
constructing water and sewer lines.  The most common method is open-trench
excavation, which often requires lateral bracing of trench walls in deep cuts
and/or non-cohesive soils.  This method of sewer construction is described in
ASCE, (1976).  Other methods of construction include:

     •  Augering, or boring, where the pipe is pushed through the soil and the
        soil ahead of the pipe is removed by an auger that is advanced with
        the pipe

     •  Jacking, where the pipe is pushed through the soil and the soil ahead
        of the pipe is removed by laborers working from inside the pipe

     •  Tunneling by various means.
                                     11-13

-------
     11.5.5  Operation, Maintenance, and Monitoring


     Replacement water and sewer lines require no operations, maintenance,  or
monitoring beyond that required for other newly constructed lines.  For water
lines, this includes flushing, leak detection and repair, and hydrant  testing
to ensure that fire-fighting requirements are met (Fair, 1971).  For sewer
lines, this includes occasional flushing and cleaning  (see Section  11.6),
removal of blockages, ensuring adequate ventilation, and leak detection and
repair.


     11.5.6  Technology Selection/Evaluation


     Factors that generally favor the selection of  line replacement over  other
technologies are the complete removal of contaminants  from the  system  and the
provision of new systems with associated functional  lines.  Major drawbacks of
replacement are disruption of surface activities and costs.  Performance  and
reliability of replacement systems are the maximum  obtainable;  i.e., new
systems are the basis of comparison for evaluating  other pipeline alteration
technologies.


      11.5.7  Costs
     Typical costs  for  replacement  of water  and  sewer  lines  ae  provided  in
Table  11-3.
 11.6   Inspection  and Cleaning of Water  and  Sewer Lines


      11.6.1  General Description


      Available  techniques  for inspecting  and  cleaning  sewer  lines  are
 generally applicable to water lines.  However,  the water  lines  are normally
 smaller  in diameter than sewer  lines, and size  is often a limiting factor in
 the applicability of inspection and  cleaning  technologies.   Inspection
 techniques include smoke testing, dye-water flooding,  first-hand visual
 observation, and  closed-circuit television  visual observation.

      Inspection is generally conducted  to identify one or more  of  the
 following conditions:

      •  Points  of groundwater leakage
      •  Structural defects  in need of repair
                                      11-14

-------
                                  TABLE  11-3.
              1985 COSTS FOR REPLACEMENT OF WATER AND  SEWER  LINES
     Item
Unit
Cost Per Unit
Sewer pipe, material and
installation, in-place:
     8-inch diameter
     18-inch diameter
     36-inch diameter

Water pipe, material and
installation, in-place:
     2-inch diameter
     4-inch diameter
     12-inch diameter

Pipe bedding material

Trench excavation,
backfill, and
compaction:

     Water lines
     Sewer lines
Linear foot
Linear foot
Cubic yard
Linear foot
Cubic yard
                    $6-10
                    $13-31
                    $33-120
$3-7
$5-11
$16-27

$14-25
$1-3
$6-10
     Source:  Godfrey, 1984


     •  Points of connection

     •  Areas in need of cleaning.

     Inspection of pipelines for  leaks or infiltration points may be  part  of  a
regular sewer or water line maintenance program.  Methods to detect and  locate
pipeline breaches include the use of dyes and other tracer chemicals, patented
audiophone leak detectors, smoke  testing, and installation of pressure gages
along a given length of pipe to monitor changes in hydraulic gradient (Linsley
and Franzini, 1979).  The interiors of small diameter sewers and large
diameter water lines are commonly inspected by pulling skid-mounted minia-
turized closed-circuit television cameras through the line.  The entire
inspection can be recorded on videotape for future reference.
                                     11-15

-------
     Cleaning of water and sewer line removes deposits  and debris  from  the
pipelines and is conducted for one or more of the  following reasons:

     •  Improve flow conditions and capacity

     •  Allow visual inspections
     •  Provide clean surfaces for placement of repair  materials.

     Available sewer-cleaning techniques include mechanical scouring, hydrau-
lic scouring and flushing, bucket dredging, suction cleaning with  pumps or
vacuum, chemical absorption, or a combination of these  methods.  Access to
sewer lines for interior cleaning and repair is most commonly afforded  by
manholes.  Basin inlets and service connections provide additional points of
access.  Service and fire hydrant connections allow access to municipal water
lines.
     11.6.2  Applications/Limitations


     Pipeline inspection  is applicable to  all visually  observable  cases  of
pipeline contamination or leakage of contaminated water.  The methods  are
well-developed and accepted.  Small-diameter pipelines  (less than  6  inches)
cannot be inspected by closed-circuit television, and pipelines  less than  48
inches in diameter cannot readily be inspected  first-hand by workmen.
Television inspection offers the advantages of worker safety and a permanent
videotape record of the inspection.  It  is common practice  to clean  pipelines
before inspection to ensure visibility of  defects and free  access  of workmen
and/or equipment.


     11.6.3  Design Considerations


     Design of inspection and cleaning operations for water and  sewer  lines
consists primarily of planning  for  the logistics of  implementation.  Sections
of pipeline to be inspected and/or  cleaned are  selected based on evidence  of
the presence of contamination or contaminated seepage;  sections may  be added
or deleted in process, depending on interim findings.   Critical  points of
operation such as access manholes,  base  of operation, and material storage are
selected.  Methods of managing  disruption  of service (water or sewer)  and
surface activities such as traffic  are also planned.  Affected parties are
notified in advance of the planned  work.


     11.6.4  Construction/Implementation Considerations


     Smoke bombs or canisters are used to  generate  the  smoke required  for
smoke testing of pipelines.  The smoke should be nontoxic,  odorless, and non-
staining.  Air blowers are used to  force the smoke  into the pipes.  Smoke
                                      11-16

-------
coming out of the ground, catch basins, pipes, and other sources during  the
test is noted and recorded by observers and photographs are  taken  for  perman-
ent documentation of the results. Sand bags and/or plugs can be used to  block
the sewer sections to prevent the smoke from escaping  through  the  manholes and
adjacent sewer pipes (WPCF, 1983).

     Dye-water flooding is used to simulate rainfall and thus  identify points
of runoff-related infiltration and sources.  Equipment needed  for  dye-water
testing is limited to that required to carry the water to  the  testing  site and
to block the sewer sections to be tested.  A fire hose is  all  that is  needed
to deliver the water to the testing site.  When the water  source is not  close
by, water tankers are required to deliver the water.   Sand bags or sewer pipe
plugs are normally used to block the sewer sections.  Fluorescent  dyes are
usually employed for high visibility (WPCF, 1983).

     The following is a general procedure for dye testing  for  possible
infiltration from a storm sewer to a sanitary sewer; similar procedures  are
used for evaluating other sources:

     •  Plug both ends of the storm drain section to be tested with sand bags
        or other materials.  Block all the overflow and bypass points  in the
        sewer section.  Provide bypassing of flow, if necessary.

     •  Fill the storm drain section with water from fire hydrants or  other
        nearby water sources.  Add dye to the water.

     •  Monitor the downstream manhole of the sanitary sewer system for
        evidence of dyed water.

     •  Measure the flows in the manhole before and during the dye-water
        testing. As an alternative, the flows can be simultaneously measured
        at both the upstream and downstream manholes during  the test.

     •  Record the location of storm drains and sanitary sewer lines being
        tested; the time and duration of tests; the manholes and the flow
        rates where the flows are monitored; the observed presence, concentra-
        tions and travel time of the dyed water into the flow monitoring
        manholes; and the soil characteristics (WPCF,  1983).

     First-hand visual observation of conditions is possible in large  diameter
sewers that permit workmen to enter.  Physical proximity to  the pipeline
interior enables workman to observe structural conditions, condition of
joints, location and nature of deposits and debris, and locations  of points of
infiltration.  Worker safety is an important consideration under such
conditions (WPCF, 1983).

     Television inspection is accomplished by using closed circuit systems
specifically designed for sewer inspection.  There are several configurations
                                     11-17

-------
of closed-circuit systems for sewer inspections, each of which have in common
the following (WPCF, 1983):

     •  Power for operation generated on-site

     •  Power control

     •  Transport winches

     •  Video (color, if possible) and lighting control

     •  Recording and documentation

     •  Radio communication

     Television inspection provides a video screen picture of pipeline being
inspected to an operator in a nearby van.  The operator controls the speed of
movement along the pipeline and records details of conditions observed.  Most
systems also provide for videotape recording of the inspection for future
reference.

     Pipeline cleaning is necessary for efficient collection system operation
and for exposing pipe materials for television inspection.  All collected
sediment and debris should be removed from the line and disposed of at an
approved site.  Care should be taken during the cleaning to minimize transport
of deposits into downstream lines.  As extensive outline of sewer cleaning
methods can be found in WPCF (1982).  The procedures for the most common
methods are briefly described below.

     Mechanical scouring techniques include the use of power rodding machines
("snakes"), which pull or push scrapers, augers, and brushes through the
obstructed line (Figure 11-1).  "Pigs," bullet-shaped plastic balls lined with
scouring strips, are hydraulically propelled at high velocity through water
and sewer mains to scrape the interior pipe surface.

     Hydraulic scouring is achieved by running high-pressure hoses into sewer
lines through manholes and flushing out sections of the sewer.  This technique
is often used after mechanical scouring devices have cleared the line of solid
debris or loosened sediments and sludges that coat the inner surface of the
pipe.

     A bucket machine can be used to dredge grit or contaminated soil from a
sewer line (Figure 11-2).  Power winches are set up over adjacent manholes
with cable  connections to both ends of a collection bucket.  The bucket is
then pulled through the sewer until loaded with debris.  The same technique
can be used to pull "sewer balls" or "porcupine scrapers" through obstructed
pipes (Hammer, 1975).  Bucket dredging is also useful for collecting samples
of contaminated sediments, groundwater, or leachate that may have infiltrated
the lines.

     Suction devices such as pumps or vacuum trucks also may be used to clean
sewer lines of liquids and debris.  Again, manholes and fire hydrants provide
easy access for the setup and operation of such equipment.
                                     11-18

-------
                   FIGURE 11-1.
           POWER RODOING MACHINE
Clecninq tool
               Source: Hammer, 1975
                    11-19

-------
                                 FIGURE 11-2.
                   SCHEMATIC OF BUCKET MACHINE CLEANING
                        Power winch with
                         loading chute
      Truck for hauling
        •way debris
                         Roller
Bucket
                                  Source: Hammer, 1975

     Another method  of  sewer  pipeline cleaning is the use of hydrophilic
polymer foams and gels  that absorb  and physically bind liquid pollutants  in  a
solid elastromeric matrix  (Johnson, J.,  Chemical Research Division,  3m Com-
pany, personal communication,  March 1980).   These polymers are special
chemical grouts that  can either  be  applied  internally to pipelines or injected
through breaks in the line  from  the exterior.   Once the absorbent grout has
set (solidified), the solid grout/pollutant matrix can be hydraulically
flushed from the line.  The applications of any of these hydrophilic grouts,
whose formulations are  often  proprietary, are still in the developmental  and
testing stages.
     11.6.5  Operation, Maintenance,  and Monitoring
     Inspection and  cleaning  of  water and sewer lines are essentially oper-
ating and maintenance  activities.   Montoring for effectiveness of cleaning  may
be warranted upon  completion  and periodically thereafter to ensure ongoing
absence of contaminants  from  the pipeline.
     11.6.6  Technology  Selection/Evaluation
     Inspection  and  cleaning  of water and sewer lines is established  and
accepted technology  for  conventional applications.  Removal of hazardous
contaminants  from  pipelines may be afforded by conventional methods where
                                      11-20

-------
contaminants are associated with deposits or debris  such  as  sludge,  slime,  or
sediments.  Contaminants that are sorbed onto the pipe material may  not be  as
readily removed.  Information concerning the effectiveness of  conventional
methods in such cases is not available.
     11.6.7  Costs


     Inspection and cleaning of water lines can be accomplished by  a variety
of methods, and costs vary accordingly.  Television inspection and  light high-
pressure water cleaning (the minimum required in preparation  for  repairing  or
lining pipelines) typically costs $100 to $150 per hour, or $0.40 to $0.60  per
linear foot for a rate of progress of 2,000 feet per eight-hour day and $0.80
to $1.20 per linear foot at a rate of 1,000 feet per day.  (D'Angelo, T., Pipe
Maintenance Services, Inc., Exton, PA, personal communication, April 1985).
Costs for other inspection and cleaning methods are highly variable and
dependent on the type of pipeline and nature of the material  being  removed.

11.7  Rehabilitation of Water and Sewer Lines


     11.7.1  General Description


     Water and sewer lines that are in contact with contaminated  substances or
allow infiltration of contaminated water can be lined or sealed in-place with
chemically inert material in order to isolate the water being transmitted from
the contaminants. Available methods include the following:

     •  Insertion of a new pipe inside of existing pipe (sliplining)

     •  In-place forming of new pipe inside of existing pipe

     •  Point repairs of leaks and other defects.

     Sliplining involves sliding a flexible liner pipe of slightly  smaller
diameter into an existing circular pipeline and then reconnecting the service
connections to the new liner.  Polyethylene is the most common material used
for sliplining pipelines (WPCF, 1983).

     A patented system called "inversion lining" uses a flexible  lining
material that is thermally hardened.  Access to the pipeline  can  be made
through manholes or excavations.  After the lining system has been  installed
and cured, a special cutting device is used with a closed-circuit TV camera to
reopen service connections.  The system is available only through licensed
contractors (WPCF, 1983).

     Because inversion lining can be accomplished relatively  quickly and
without excavation, this method is particularly well-suited for repairing
pipelines located under existing structures or large trees.   It also is
particularly useful for repairing pipelines located under busy streets or


                                     11-21

-------
highways where traffic disruption must be minimized.  Because the liner
expands to fit the existing pipe geometry, this method is applicable  to  all
pipeline shapes.  The cured resin material is reportedly corrosion-resistant.
Inversion lining also affords minor structural reinforcement.  Inversion
lining may be used for misaligned pipelines or in pipelines with bends where
realignment or additional access is not required (WPCF, 1983).

     Inversion lining using water to cure the resins is generally used in
pipelines with diameters less than 57 inches and manhole-to-manhole segments
less than 1000 feet long.  Larger diameter pipelines (to 108 inches)  have been
lined by inversion techniques using air (WPCF, 1983).

     Inversion lining is relatively new in the U.S. and its cost-competitive-
ness has not yet been fully established (WPCF, 1983).  It is a patented  system
available only through a limited number of licensed contractors.

     Chemical grouting is commonly used for sealing leaking joints in
structurally sound sewer pipes.  Small holes and radial cracks can also  be
sealed by chemical grouting (WPCF, 1983).

     Chemical grouts are synthetic materials that are applied as low-viscosity
liquids and cure as flexible, form-fitting solids.  Commonly used chemical
grouts are acrylamide gel, acrylate polymer, and polyurethane gel (WPCF,
1983).
     11.7.2  Applications/Limitations


     Repairing and lining of water and sewer  lines  applies  to  lines  that  are
1) contaminated as a result of ongoing contact with contaminated  substances,
or 2) allowing the infiltration of contaminated water.  The application of
materials to the interior of the pipe should  resolve either or both  problems
if the materials are properly selected.  The  materials  used have  low suscepti-
bility to chemical degradation and have relatively  low  permeability  to water,
and would be expected to effectively isolate  sewage and water  flows  from
contaminated pipelines and seepage.  However, the repair  and lining  materials
and techniques were not developed for control of hazardous  contaminants and
there is no information available that addresses their  effectiveness under
these special circumstances.  Factors that  could adversely  affect the
performance and reliability of repairs and  lining are:  1)  incompatability of
repair materials and contaminants, and 2) permeability  of repair  materials
with respect to contaminants.

     Sliplining is used to rehabilitate extensively cracked pipelines,
especially lines in unstable soil conditions.  It is also used to rehabilitate
pipe installed in a corrosive environment and in areas  where sewer pipes  have
massive destructive root intrusion problems (WPCF,  1983).   The flexible liner
pipes have the advantage of being able to accoraodate a  normal  amount of future
settlement or, moderate horizontal or vertical deflection.
                                      11-22

-------
     If the existing pipeline joints are offset, service lateral taps are
protruding, or if the diameter of the pipeline has been significantly reduced
in some other manner, the liner pipe diameter may need to be much smaller than
the diameter of the existing pipeline.  Such conditions can limit the utility
of this method (WPCF, 1983).

     Premanufacturered sliplining pipe cannot be used in pipe that is signifi-
cantly "out of round," since its cross section must pass through that of the
existing pipe.  New pipe formed in-place cannot be used where the existing
pipe has low structural integrity, unless reinforcing is added in the forming
(generally limited to larger diameters where workmen can enter).

     Point repairs can be used where problems are confined to joints  or to
relatively few short sections of pipe.

     Chemical grouting is generally used to seal open pipeline joints and
cracks.  It does not improve the strength of a pipeline, and should not be
used when pipe is severely cracked, crushed, or badly broken.  Chemical
grouts, once applied, may dehydrate and shrink if the surrounding moisture is
reduced significantly.  Some joints and cracks may be difficult to seal
chemically using gel grouts when large voids exist outside the pipe joint and
extremely large quantites of grout may be required to seal the joint (WPCF,
1983).

     Inspection and cleaning of pipelines is generally necessary in prepara-
tion for rehabilitation.  These methods are addressed in Section 11.6.
     11.7.3  Design Considerations


     Design of water and sewer line rehabilitation consists primarily of
planning for the logistics of implementation.  Sections of pipeline to be
rehabilitated are identified based on television or other inspections.
Critical points of operation such as access manholes, base of operation, and
material storage are selected.  Methods of managing disruption of service
(water or sewer) and of surface activities such as traffic are also planned.
Affected parties are notified in advance of the planned work.


     11.7.4  Construction/Implementation Considerations


     Typical sliplining materials include high-density polyethylene (HOPE) and
fiberglass-reinforced pipe (FRP).

     Before installing a liner pipe, the existing pipeline should be inspected
by closed circuit TV to identify all obstructions such as displaced joints,
crushed pipe, and protruding service laterals to locate service connections.
The existing pipe is thoroughly cleaned immediately before sliplining begins
(WPCF. 1983).
                                     11-23

-------
     HDPE  sliplining is pulled  through existing  pipelines by a  cable that is
fed through the section to be  lined.  The cable  and pipe are advanced by a
winch and  pully assembly (see Figure 11-3).  An  approach trench is  excavated
at the  insertion end of the  existing pipe section to allow a gradual transi-
tion from  the ground surface, where sections of  HDPE pipe are heat  fused to
form a  continuous pipe to an opened section of pipe.  Several thousand feet of
water or sewer line can be sliplined in a single set-up of such an  operation
(Waste  Engineering and Management, 1983).  FRP can be sliplined in  a manner
similar to that used for HDPE,  although a combination of pushing and pulling
of the  pipe can be employed  (see Figure 11-3)  (A.O. Smith-Inland, undated).

     Wastewater flow in existing sewers may not  need to be interrupted during
insertion  of a sliplining as low flows may continue through the annular space
between the two pipes.  Alternatively, it may  be necessary to temporarily plug
the upstream lines and pump  the flow around the  section being lined using
above-ground piping (WPCF, 1983).  The annulus between the old  and  new
pipelines  is sometimes filled with grout where structural failure of the old
pipe could concentrate loads and cause problems  with the HDPE pipelines.

     In-place forming of new pipe inside of existing pipe is accomplished with
portland cement grout and mortar, chemical grouts, and synthetic resins.
                                    FIGURE 11-3.
                            SEWER SLIPLINING METHODS
           .WINCH ASSEMBLY
           VREMOTE MANHOLE
           OR ACCESS PIT
                                RAMP FOR TWO-WAY.
                                  INSERTION
                              .CABLE ATTACHED
                              TO SUIOE CONE
 MIN. OP
 12 X LINER  MIN. OP
 DIAMETER  2.5 XD
                                                                  LINER
                                                                  PIPE
       PIPE SUPPORT-
         ROLLER
                                    "PULL" METHOD
            .WINCH AS3AMBLY
                                           MINIMUM OP STANDARD PIPE LENGTH
                                           JOINING MACHINE
                                                       PUSH PLATE-
                         ' \CABLE PASSING THROUGH
              ' EXISTING PIPE   ALINING PIPE ANCHORED
            V REMOTE MANHOLE   T0 PUSH PUATE
            OR ACCESS PIT              „   _
                                    "PUSH" METHOD
       ^•LINER PIPE
•PIPE SUPPORTED ROLLER
                                   Source: WPCF, 1983
                                        11-24

-------
     Chemical grouts can be used to seal fractures and leaking joints to
waterproof points of infiltration/exfiltration.  Grout materials used for this
application include acrylamide, acrylate, urethane and polyurethane.

     The chemicals necessary to form acrylamide or acrylate gels are usually
mixed in tanks and pumped through separate hoses to the pipeline joint to be
sealed.  The water and catalyst solution initiates the chemical reaction when
mixed with the acrylamide solution.  Additives can be included in either
solution to help control shrinkage, reaction or "gel" time, and other
variables (WPCF, 1983).

     The two solutions are pumped through separate hoses to the point to be
sealed.  The solutions are mixed as they are injected into the leaking
opening, initiating the chemical reaction.  This reaction changes the two
solutions into a gel.  The gel time can be controlled from just a few seconds
to several minutes.  The grouts or gels stabilize soil around joints or cracks
by filling the voids (WPCF, 1983).

     Urethane grout materials form either an elastomeric gel, much  like the
acrylamide and acrylate gels, or a rubber-like foam.  Water is the  catalyst
for the urethane gel material.  Urethane gel seals pipeline joints  by forming
a collar within the pipe joint as well as by consolidating soils and filling
voids outside the joint (WPCF, 1983).

     Urethane gel is applied in essentially the same manner as the  acrylamide
and acrylate gels.

     Polyurethane foam differs from the gel grouts in that the foam is used to
form an in-place pipeline gasket and does not fill voids or stabilize the soil
outside of the pipe joint (WPCF, 1983).

     Small and medium diameter pipes can be grouted using a hollow  metal
cylinder with inflatable rubber sleeves on each end of a center band, called a
"packer."  An inflated packer can be used both to test and chemically seal a
pipeline joint.  A van is used as the operation and control center  for a TV
monitor, pumps, air compressors, and the feed system equipment.  A  closed-
circuit TV camera allows positioning of the packer at pipeline joints and
cracks for sealing.  The packer and the TV camera are pulled along  with a
cable from manhole to manhole, and the process is viewed on the TV  monitoring
screen in the van (see Figure 11-4)  (WPCF, 1983).

     The amount of grout needed to seal a defect depends upon the size of the
leak.  The gels usually are pumped until the grout solidifies; the  back
pressure will then indicate to the operator that the leak has been  sucessfully
sealed.  The rubber sleeves are deflated and moved to the next joint for
sealing (WPCF, 1983).

     For grouting large-diameter pipes, pressure grouting or manual placement
of oakum soaked with grout may be used.  Pressure grouting is accomplished
using pipe grouting rings or predrilled injection holes (Figure 11-5).
                                     11-25

-------
                                       FIGURE 11-4.
TYPICAL ARRANGEMENT FOR APPLYING CHEMICAL GROUT TO SMALL DIAMETER PIPE
                                          CHEMICAL, CATALYST, AND
                                       •'AIR PRESSURE FEED LINES: ALSO
                                       POWER SOURCE FOR TV CAMERA
                                                           WINCH
                                -MANHOLE ASSEMBLY
                                     ROLLER
                                     Source: WPCF, 1983
                                       FIGURE 11-5.
TYPICAL ARRANGEMENT FOR SEALING LARGE  DIAMETER PIPE WITH  GROUTING RINGS
                 CHEMICAL, CATALYST
                 AND AIR PRESSURE
                 FEED LINES
                                                 CONTROL
                                                 PANEL    -HAND-HELD  PROBE
                                                                   SEALING
                                                                   RIN6
                                      Source: WPCF, 1983
                                          11-26

-------
     Grouting using sealing rings requires the use of a small control panel,
chemical and water pumps, and various other accessories depending on the type
of sealing grout being used.  A worker must enter the line, manually place the
ring over the joint, and inflate the ring to isolate the joint.  Sealing grout
is pumped into the small void between the pipe wall and the face of the ring
through a hand-held probe.  As the pressure in the void increases, the grout
solution is forced into the joint and surrounding soil.  The catalyst solution
is injected and the grout cures, sealing the joint from infiltration  (WPCF,
1983).

     Linings and coatings can be used to protect pipelines from internal
corrosion.  Most linings, however, are integrated into the pipe when it is
made (WPCF, 1983).

     Reinforced shotcrete (gunite) is a mixture of fine aggegate, cement, and
water applied by air pressure using a cement ejector.  Compared to cement
mortar linings, gunite is denser and has a higher ultimate compressive
strength.  It also improves a pipeline's structural integrity.  Gunite adheres
well to other concrete and brick sewers and is more corrosion-resistant than
normal concrete.  It can be trowled to a finish to improve a pipeline's
hydraulic characteristics (WPCF, 1983).

     Gunite is well-suited for extremely deteriorated large sewers where
persons and equipment can work without restriction.  Long lengths of sewers
may be effectively renewed with little excavation and minimal traffic
disruption.

     Gunite can be applied under low wastewater flows; however, totally
dewatering the pipeline is more effective.  Welded wire mat or small diameter
rod reinforcing is used for structural gunite applications (WPCF, 1983).

     In-place forming with synthetic resins (inversion lining) can be
accomplished without excavation in most cases.  The reconstruction is done
through existing pipe access points, requiring only limited disruption of
surface conditions and activities.  A four-step installation process, shown in
Figure 11-6, can normally be accomplished in a matter of days  (Utz, 1983).  A
fiberfelt tube impregnated with a liquid resin is fed into an inversion
standpipe which has been erected on site.  The felt tube has an impermeable
coating on the outside which eases handling and provides a water barrier for
the inversion process  (insituform, undated).  The end of the tube is pulled
through the inversion standpipe, turned inside out and clamped to the stand-
pipe such that a leak-proof seal is established.  As more water is added to
maintain the weight of the column, additional tubing is fed into the stand-
pipe, and the impregnated tube snakes its way forward through the pipe being
rehabilitated (WPCF, 1983).

     The weight of the water presses the coated felt at the nose, inverts it,
and then presses the resin-impregnated side against the insides of the
existing pipe, leaving the smooth coated side as the new interior surface of
the rehabilitated pipe.   After the inverted tube reaches the next manhole or
other access point, the water is heated to cure the resin, forming an
impermeable new pipe within the old pipe.  The ends are cut off, the head of

                                     11-27

-------
                  FIGURE 11-6.
INVERSION LINING INSTALLATION PROCEDURE
                               INVERSION     ^

                  LINER ATTACHED  \TUBE    MATERIAL
                   TO HEADE-     V
                     PIPE
        2 VPIPE TO
        ^     BE LINED
                       STEP I
                       STEP 2
          HOT WATER(OR AIR)
          CIRCULATION HOSE
                       STEP S
  LINED PIPELINE RETURNED TO SERVICE AFTER THE CURED
  LINER HAS BEEN TRIMMED, THE INSTALLATION EQUIPMENT
  HAS BEEN REMOVED, AND ANY SERVICE CONNECTIONS HAVE
  BEEN  REOPENED

                       STEP 4
                 Source: WPCF, 1983
                      11-28

-------
water is released, and the operation is complete.  Service connections are
reinstated in non-man-entry pipes by means of remotely controlled cutting
device (insituform, undated).
     11.7.5  Operation, Maintenance, and Monitoring
     If properly implemented, lined, and repaired, water and sewer lines
should require no operation or maintenance beyond that required for other
lines.  Periodic monitoring for contaminants of concerns in water or sewage
should be conducted to determine whether leaking or other failure of the
measures  has occurred.
     11.7.6  Technology Selection/Evaluation


     Repairing and lining offer the advantage of eliminating contaminants
without the need for disruption of surface activities.  However, the presence
of contaminants in close proximity to water or sewage may be cause for ongoing
concern.  Because these technologies were not specifically developed for con-
trol of hazardous substances, their performance and reliability under such
special circumstances is neither certain nor can be fully evaluated with
available information.  Coordination of material selection with manufacturers
may be useful in determining material compatability.  Also, laboratory
bench-scale and/or field pilot-scale tests may be warranted to ensure that
effective, long-term isolation of contaminants can be affected.


     11.7.7  Costs
     Costs of sliplining water and sewer lines vary with the diameter and
depth of the pipeline.  Costs for relatively small diameter (less than
15-inch) HDPE sliplining projects range from $20 to $30 per linear foot
(D'Angelo, T., Pipe Maintenance Services, Inc, Exton, PA, personal
communication, April 1985; Metcalf, K. Norfolk, VA, personal communication,
April 1985).  Larger diameter sliplining projects are seldom undertaken and
must be costed on a project-specific basis.

     Inversion lining costs are normally given on a per-linear-foot basis for
initial television inspection, cleaning, by-pass pumping, and post-construc-
tion television inspection combined.  The following are representative unit
costs for typical inversion lining of sewer lines.

          Diameter (inches)            Cost (Linear Foot)

                 8                     $45-50
                10                     $47-52
                12                     $49-54
                                     11-29

-------
Reconnection of laterals typically costs $100 to $250 each, depending on
logistics and the number of laterals in a given project.  (Tice, M.,
Insituform East, Inc. Landover, MD, Personal communication, April 1985.)


     Grout repairs to sewer pipelines are generally accomplished by pumping
grout into a joint until soil voids are filled, as determined by back-
pressure.  A wide range of grout volumes can be pumped into a joint, and sewer
grouting work is typically conducted on a per-hour basis for manpower and
equipment ($100 to $150 per hour) and on a per-gallon basis for grout ($5 to
$10 per gallon  for chemical grout).
                                      11-30

-------
                                  REFERENCES
American Society of Civil Engineers (ASCE).  Pipeline  Design  for Water  and
Wastewater 1975. New York, NY.   127 pp.

American Society of Civil Engineers (ASCE).  1976.  Design  and Construction  of
Sanitary and Storm Sewers.  Manual of Practice no.  37.  New York,  NY.   331 pp.

Anderson, M., R.A. Cottier and G.E. Bellen.  1984a.  Point-of-Use  Treatment
Technology to Control Organic and Inorganic Contaminants, Part I.
Water Technology.  September 1984.  pp. 36-41.

Anderson, M., R.A. Cottier and G.E. Bellen.  1984b.  Point-of-Use  Treatment
Technology to Control Organic and Inorganic Contaminants,
Part II.  Water Technology.  October 1984.  pp. 41-45.

A.O. Smith-Inland, Inc.  undated.  1 1/3 Miles of  Red  Threadฎ Inserted  as
Water main Under Portland Harbor, Pipefacts File 120,  Little  Rock,  AR.   2 pp.

Association Francaise de Travaux en Souterrain (AFTES).   1975.  Recommenda-
tions for the Use of Grouting in Underground Construction,  trans,  by G.W.
Clough.

Comsumers Union of United States, Inc.  1984.  1985  Buyers Guide Issue.
Mount Vernon, NY.  pp. 82-85.

Fair, G.M. et al. 1971.  Elements of Water Supply  and  Wastewater Disposal.
John Wiley and Sons, Inc., New York, NY.  752 pp.

Godfrey, R.S.  1984.  1985 Means Building Construction Cost Data,  43rd  Annual
Edition.  Robert Snow Means Co. Inc., Kingston, MA.

Insituform of North America, Inc.  undated.  Design Guide for Pipeline
Reconstruction.  Memphis, TN. 6 pp.

Linsley, R. and J. Franzini.  1979.  Water Resources Engineering.   3rd  Ed.
McGraw-Hill Book Company, New York, NY.

Morrison, 1981.  If Your City's Well Water has Chemical Pollutants, Then What?
Civil Engineering.  Vol. 51, No. 9.  pp. 65-67.

Perry,  D. L. et al.  1981.  Development of Basic Data and Knowledge Regarding
Organic Removal Capabilities of Commercially Available Home Water  Treatment
Units Utilizing Activated Carbon, Phase 3/Final Report.  EPA  Contract No.
68-01-4766.  Gulf South Research Institute.  Prepared  for:  Criteria and
Standards Divison, Office of Drinking Water, U.S. Environmental Protection
Agency.  October 23, 1981.  74 pp.
                                     11-31

-------
                            REFERENCES (continued)
National Sanitation Foundation (NSF) Drinking Water Treatment Units, Health
Effects.  Standard Number 53.  Ann Arbor, MI.  11 pp. and appendices.

Taylor, R. H., M. J. Allen and E. E. Geldreich.   1978.  Testing of Home Use
Carbon Filters.  Presented at AWWA Water Quality  Technology Conference.
Louisville, KY.  December 4, 1978.  9 pp.

Utz, John H.  1983.  Solving a Difficult Sewer Rehabilitation Problem.  Public
Works.  March 1983.  pp. 59-60.

Water/Engineering and Management.  1983.  Sliplining Water Mains Overcomes
Leakage.  February, 1983.  pp. 14-15.

Water Pollution Control Federation (WPCF).   1983.  Existing Sewer Evaluation
and Rehabilitation.  Manual of Practice FD-6.  Washington, D.C.  106 pp.

Water Pollution Control Federation (WPCF) 1982.   Operation and Maintenance of
Wastewater Collection Systems.  Manual of Practice No. 7. Washington, D.C.
                                      11-32

-------
                                  APPENDIX A

                                     INDEX
 Accessibility
      in Data Needs 2-5

 Acids
      in compatibility testing 7-26
      and  biodegradation 9-5

 Acrylamides
      as grout 5-98, 5-99, 5-100,
      5-101

 Activated carbon 10-3, 10-49, 11-5,
      10-121

 Activated sludge 10-10

 Adsorption 10-121

 Aeration  10-11

 Aerobic 6-1, 9-2, 9-3, 9-5, 9-15,
     9-34, 10-10

 Air pollution controls 4-1 to 4-0,
     10-137

 Air quality
     in climatology, data needs 2-5
     in specific site problems 2-4

 Air stripping 10-48

 Alcohols
     and  biodegradation 9-5
     and  toxicity to microbes 9-11

 Aldehydes
     and  biodegradation 9-5
     and  toxicity to microbes 9-11

Aliphatic alcohols
     as floating immiscible liquids 4-2

Alkanes
     and biodegradation 9-5
Alkyl halides
     and biodegradation, 9-3, 9-5

Amides
     and biodegradation 9-5
Amines
     and biodegradation 9-5
     and toxicity to microbes

Anaerobic 6-1, 9-2, 9-3, 9-5, 9-28

Anganochlorine
     in waste analysis 7-28

Aquifer
     artesian 5-14
     confined 5-5, 5-8, 5-11, 5-19
     data needs 2-5
     heterogeneous 5-5, 5-7
     homogeneous 5-5
     unconfined (water table) 5-5,
     5-8, 5-10, 5-15, 5-19

Aromatics
     and biodegradation 9-3, 9-5

Asphalt
     as a dust suppressant 4-5
     as mulch for revegetation 3-29

Augers
     hand 5-32, 5-33
     rotary bucket 5-33, 5-35, 5-44
     spiral 5-33, 5-35, 5-44

Backfilling
     and subsurface drains 5-71
     and slurry walls 5-89

Backhoes 7-2 to 7-6, 7-22, 8-2, 8-5,
     8-32, 8-35

Barriers
     and pumping 5-39
     and subsurface drains 5-47 to
     5-49, 5-51, 5-53
                                     A-l

-------
                            APPENDIX A (Continued)
     low permeability 5-1, 5-55 to
     5-59
     concrete 3-4
     bituminous membranes 3-4
     subsurface 5-83 to 5-113
Bases
     in compatability testing 7-26
     in pretreatment 7-27

Basket centrifuges 10-82

Bedrock
     in site geology data needs 2-5
     fractured or jointed 5-2

Belt filter presses 10-91

Benches 3-3, 3-52 to 3-56

Bentonite 3-7
     and slurry walls 5-83, 5-93
     5-96
     for wells 5-25

Berms 3-3, 3-12, 3-36 to 3-40, 8-48

Biological towers 10-11

Biological treatment 10-10

Bioreclamation 9-1 to 9-39

Biphenyls
     and biodegradation 9-3, 9-5

Bitumen 3-7

Block displacement 5-112

BOD/COD ratio 9-3, 9-4

Bottom ash
     and soil treatment 3-7

Bottom sealing 5-112, 5-113

Bucket factor 7-6

Bucket ladder dredge 8-2, 8-6, 8-7
Butyl alcohol
     as floating immiscible liquid 4-2

Butyl rubber
     and synthetic membranes 3-7,
     3-12, 3-16, 7-35
Capping
     general 3-1, 3-2 to 3-12, 6-28
     multi-layered 3-5 to 3-8, 3-9
     single-layered 3-5, 3-9

Carbon dioxide 6-1

Carboxylated styrene-butadiene copol-
     omer as dust suppressant 4-5

Casing
     for wells 5-23, 5-31, 5-33, 5-37

Cercla 1-1, 2-1

Cement
     Portland 3-7, 5-83, 5-92

Cement-based solidification 10-106

Centrifuges 10-82

Channels 3-1, 3-3, 3-40 to 3-52

Chelation
     and chemical treatment 9-36,
     9-43, 9-45, 9-46

Chemical Composition
     in waste characteristics,
     data needs 2-5
     in technology selection 2-7

Chemical stabilizers 3-7

Chemical treatment 9-39 to 9-61

Chlorinated Polyethene
     and synthetic membranes 3-7,
     3-12, 3-16

Chromium
     as alloy 7-14
                                     A-2

-------
                            APPENDIX A (Continued)
Chutes 3-1, 3-3, 3-57 to 3-63

Circulating Bed Combustion 10-135

Clamshells 7-6, 7-22, 8-2 to 8-4,
     8-32, 8-35

Clarifiers 10-72

Clean Water Act
     in remedial action alternatives
     2-10

Climatology
     in data needs 2-5

Cofferdams 8-21 to 8-25

Coke tray aerator 10-49

Compatibility testing 7-25 to 7-27

Cone of depression 5-8, 5-9, 5-12,
     5-18

Cone of impression 5-18

Contour furrowing 3-21

Costs
     of activated carbon units 10-8
     of activated sludge 10-17
     of active gas control 6-25 to
     6-27, 6-31
     of airstripping 10-52
     of benches and terraces 3-56,
     3-82
     of bioreclamation 9-35 to 9-39
     of capping 3-11, 3-12
     of cement-based solidification
     10-108
     of centrifuges 10-87
     of channels and waterways 3-52,
     3-82
     of chemical clarification 10-35
     of chutes and downpipes 3-57,
     3-82
     of cyclones 10-71
     of dikes and berms 3-40, 3-82
of dredging 8-36 to 8-42, 8-46
of dust suppressants 4-5, 5-6
of excavation equipment 7-6,
7-8, 7-9, 7-10
of filtration 10-97
of floating covers 3-19
of grading 3-24 to 3-26
of ground freezing 9-64
of grouting 5-103, 5-104, 5-109
of heavy metal precipitation
10-29
of hydraulic classifiers 10-66
of hydroxide and sulfide
precipitation 10-30
of incineration 10-141
of in-situ treatment 9-35, 9-59
of in-situ vitrification 9-62
of ion exchange 10-39
of levees and floodwalls 3-79,
3-82
of liners 7-35
of microencapsulation 10-116
of neutralization 10-47
of off-site disposal 7-25
of on-site disposal 7-38
of oxidation 10-55
of passive gas control 6-12
to 6-14
of permeable treatment 9-60
of polymer addition 10-31
of polypropylene spheres 4-3
of pumping 7-15
of reduction 10-56
of remedial action
alternatives 2-11 to 2-13
of revegetation 3-31 to 3-35
of reverse osmosis 10-44
of sedimentation basins/ponds
3-74, 3-82
of sediment treatment 8-46
of seepage basins and ditches
3-67, 3-82
of sewer line cleaning and
inspection 11-21
of sewer line rehabilitation 11-29
of sewer line replacement 11-14
of sheet piling 5-112
of silicate cement solidification
10-111
                                     A-3

-------
     of slurry walls 5-92, 5-93, 5-97
     of spiral classifiers 10-68
     of subsurface drains 5-73 to 5-82
     of surface water controls 3-80 to
     3-85
     of surfactant layers 4-3
     of thermoplastic solidification
     10-114
     of vacuum loaders 7-16
     of well systems 5-40 to 5-46
     of wind screens 4—7

Covers
     synthetic 4-8
     and sediments 8-49 to 8-54

Cranes 7-2, 7-6 to 7-8, 7-22

Cross-flow tower 10-49

Cutterhead Dredge
     and hydraulic dredging 8-9,
     8-32, 8-35

Cyanides
     in compatibility testing 7-26
     in pretreatment 7-27
     in waste analysis 7-28

Cyclones 10-68

Darcy's Law 5-8, 9-19

Data needs
     in site-specific
     characteristics 2-5

Dessication Caps 5-94

Detoxification 9-52

Dewatering
     in subsurface drain
     installation 5-69, 5-75

Dewatering lagoons 10-80

Diaphragm Walls 5-97
APPENDIX A (Continued)

             Diaphragm filters 10-96

             Diffused air basin 10-49
             Dikes 3-1, 3-3, 3-36 to 3-40,
                  8-48

             Disposal
                  of wastes 7-1 to 7-40
                  off-site 7-24 to 7-30
                  on-site 7-30 to 7-38

             Distillation 11-5

             Ditches 3-1, 3-2, 3-3, 3-63 to 3-67

             Diversion channels 3-1

             Diversion (channel) 3-42, 3-43

             Diversion Dikes 3-38, 3-39, 3-40

             DOT
                  and transportation of
                  wastes 7-29

             Downpipes 3-1, 3-3, 3-57 to
                  3-63

             Dozers 7-2, 7-8, 7-9, 7-22

             Dragline 7-2, 7-6, 7-7, 7-8,
                  7-22, 8-2, 8-4, 8-5,
                  8-32, 8-35

             Drains
                  interceptor 5-51 to
                  5-55, 5-82
                  relief (parrallel) 5-51,
                  5-55 to 5-59
                  subsurface 5-1, 5-46 to
                  5-82, 9-25
                  installation 5-70 to 5-72

             Drawdown 5-8, 5-9, 5-12, 5-15,
                  5-17, 5-21, 5-22, 5-25,
                  5-30
                  in plots 5-19, 5-20, 5-21
                                     A-4

-------
                            APPENDIX A (Continued)
Dredging
     mechanical 8-2 to 8-6, 8-32,
     80-35
     hydraulic 8-7 to 8-17,
     8-32, 8-35
     pneumatic 8-17 to 8-20,
     8-32, 8-35

Drilling
     rotary 5-32, 5-3A, 5-36, 5-44
     cable tool 5-34, 5-44

Drums
     and transportation of
     wastes 7-29

Dust suppressant 4-4 to 4-6

Dustpan dredge
     and hydraulic dredging
     8-10, 8-32, 8-35

Electroosmosis 10-80

Embankments 3-2

Encapsulation 10-115

Envelope
     and subsurface drains
     5-47, 5-62, 5-64, 5-71
     and leachate collection 7-34

EP Toxicity
     in waste analysis 7-28

Epichlorohydrin rubbers
     and synthetic membranes 7-35

Epoxides
     and biodegradation 9-5

Epoxy
     as grout 5-100

Erosion
     control of 3-1, 3-3, 3-7,
     3-8, 3-19. 3-20, 3-24, 3-36,
     3-52, 3-57
Esters
     and biodegradation 9-5

Ethylene propylene rubber
     and synthetic membranes
     3-7, 3-12, 3-16

Evapotranspiration 3-5, 3-9
     in climatology, data needs
     2-5

Excavation
     general 7-1 to 7-24
     equipment 7-2 to 7-16

Feasibility study (FS) 1-1, 2-2,
     2-3

Fermentation 9-3, 9-5

Filters
     and subsurface drains
     5-62, 5-71

Filter pack
     for wells 5-24, 5-25, 5-30,
     5-31, 5-37

Filtration 10-19, 10-91

Flaring 10-118

Flammability
     in compatibility testing 7-27

Flash point
     in waste analysis 7-28

Floating covers 3-13 to 3-19

Flocculation 10-22

Flooding
     protection from 3-2, 3-3,
     3-74 to 3-79

Floodplain
     in surface water,
     data needs 2-5
                                     A-5

-------
                            APPENDIX A (Continued)
     in disposal requirements
     7-30

Floodwalls 3-1, 3-2, 3-3,
     3-74 to 3-79

Flood control dikes 3-2

Flow
     equilibrium (steady state)
     5-8, 5-10
     non-equilibrium 5-8
     laminar 5-8
     and velocity distribution
     plots 5-19

Fluidized bed incinerator
     10-129

Flumes 3-1, 3-57

Flyash
     and soil treatment 3-7
     and slurry walls 5-96

Fugitive dusts/emissions
     4-1, 4-4 to 4-8, 7-20

Furnace slag
     and soil treatment 3-7
     and slurry walls 5-96

Gabions 3-64

Gas
     collection system 3-5,
     3-16, 3-17, 4-4, 6-14
     to 6-25
     migration 2-4, 3-30, 4-4,
     3-30, 6-2
     emissions 4-1 to 4-4, 6-28
     controls 6-1 to 6-32
     organic 6-1
     detectors 6-9, 7-23
     passive perimeter controls
     6-21 to 6-14
     active perimeter controls
     6-14 to 6-24
     extraction wells 6-14 to
     6-25
     collection headers 6-14
     to 6-25
     treatment or utilization
     6-14 to 6-25
     active interior controls
     6-26 to 6-31
     cylinders 7-24

Gaseous waste treatment 10-118
Geology
     in data needs 2-5

Geotextiles
     as capping 3-12
     as dust suppressant 4-5
     and subsurface drains
     5-62, 5-72

Classification 10-116

Glycols
     and biodegradation 9-5

Grade control
     in subsurface drains 5-69

Grading 3-1, 3-3, 3-19 to 3-26

Grapples 7-6

Gravel pack (see filter pack)

Gravity collection systems  5-1

Gravity separation 10-47

Gravity thickening 10-77

Gravity underdrainage  10-80

Grizzlies  10-58

Ground freezing  9-61

Ground leaching
     (see  soil flushing 9-45)
                                     A-6

-------
Groundwater
     in data needs 2-5

Groundwater
     monitoring 7-37
     temperatures 9-9

Groundwater
     extraction 3-4
     containment 3-4

Groundwater
     controls 5-1 to 5-118
     diversion 5-1
     pumping 5-1 to 5-46

Groundwater
     barriers 5-5

Groundwater quality
     in specific site
     problems 2-4
APPENDIX A (Continued)

             Heat recovery 10-138

             Henry's law 9-19

             Herbicides
                  and biodegradation
                  9-3, 9-5

             Heterogeneous aquifers 5-5

             High temperature fluid wall
                  10-135

             Hoists 7-6

             Homogeneous aquifiers 5-5

             Hopper dredges
                  and hydraulic dredging
                  8-11, 8-32, 8-35
Grouting
     and subsurface barriers
     5-97 to 5-109
     cement 5-97
     clays 5-98, 5-99
     bentonite 5-98, 5-99
     silicates 5-98, 5-99
     organic ploymers 5-98, 5-99
     curtains 5-103 to 5-109
     port method 5-105, 5-107
     and bottom sealing 5-112
     and sediments 8-55, 8-56

Grouting
     for wells 5-24, 5-37, 5-38

Gyratory screens 10-59

Halogens
     in compatibility testing
     7-26

Haulers 7-9, 7-10, 7-22

Head 5-8, 5-9, 5-20, 5-26,
     5-27, 5-28, 5-56
             Hydraulic barriers (boundary
                  conditions) 5-8, 5-16,
                  5-17, 5-18, 5-19, 5-20

             Hydraulic classifiers 10-63

             Hydraulic conductivity 5-2,
                  5-8, 5-10, 5-51
                  in well selection 5-5, 5-7,
                  5-19, 5-38, 5-58, 5-73

             Hydraulic gradient 5-2, 5-8,
                  5-59, 5-60

             Hydrocarbons
                  and biodegradation 9-3, 9-5

             Hydrocyclones 10-68

             Hydrogen sulfide 6-1, 6-8, 9-50

             Hydrogen peroxide
                  and bioreclamation
                  9-15, 9-17

             Hydrolysis 9-40, 9-42, 9-52

             Hydrosieve 10-63
                                     A-7

-------
                            APPENDIX A (Continued)
Hydroxy compounds
     and biodegradation 9-5

Hypalon
     and synthetic membranes
     3-7, 3-12, 3-16, 3-19, 6-8

Immobilization 9-47

Impoundment basin 10-72

Incineration 7-25

Infiltration
     prevention of 3-1, 3-3, 3-8,
     3-20, 3-26, 3-44, 5-2
     through capping 3-4, 3-5

In-situ heating 9-61

Interceptor dike 3-36, 3-37, 3-38

Inversion lining 11-22

Ion exchange 10-36, 11-5

Jetting
     and well installation 5-33,
     5-35, 5-36, 5-44

Ke tones
     and biodegradation 9-5
     and toxicity to microbes 9-11

Lagoon
     covers 3-2, 3-3

Landfills 7-25, 7-30 to 7-38

Latex
     as dust suppressant 4-5

Leachate
     in specific site
     problems 2-4

Leachate
     prevention 5-1
     control 5-101
Leachate
      collection 7-32, 7-33,  7-36

Levees  3-2,  3-3,  3-12,
      3-74  to 3-79,  7-33

Lifters 7-6

Lignosulfonate
      as dust suppressant  4-5

Lime
      and soil treatment 3-7

Liners
      natural 3-4  to 3-6,  3-12,
      7-20, 7-30 to  7-32,  7-33,  7-36
      synthetic 3-4, 3-5,  3-6, 3-7,
      3-10, 3-11,  3-12, 3-13, 3-16,
      4-1,  7-30 to 7-32, 7-33,
      7-34, 7-35
      admixed 3-4, 3-5, 3-6,  3-12,
      7-32, 7-33

-Liquid  injection  10-123

Liquid  migration
      requirements 3-2

Loaders 7-2, 7-8, 7-9,
      7-15, 7-16,  7-22

Magnets 7-6

Manholes
      and subsurface drains
      5-62, 5-65,  5-81

Manning formula 3-44, 3-49,  3-50

Methane 6-1, 6-8

Methanogenic processes
      and bioreclamation 9-2,
      9-30, 9-37

Microencapsulation  10-115

Mobile  incineration 10-131
                                     A-8

-------
                               APPENDIX A (Continued)

   Molten salt  incineration  10-131

   Monitoring wells  3-4, 3-11,  5-72
   National contingency plan (NCP)
       1-1, 2-1, 2-8

   Native vegetation
       in data needs 2-5

  Neoprene
       and synthetic membranes
       3-7, 3-12, 7-35

  Neutralization 9-52, 10-45

  NIOSH 7-21

  Nitrate
       and  anaerobic  bioreclamation
       9-30, 9-31

  Nutrients
       and  bioreclamation 9-22
       to 9-23

  Nitrites
      and biodegradation 9-5

 Nitro compounds
      and biodegradation 9-5,
      9-32

 Nitrogen 6-1,  9-22

 Octanol-water  partition
      coefficients  9-46

 Organophosphates
      and biodegradation 9-3,
      9-5

 OSHA  7-21

Osmosis 10-40

Oxidation 9-3,  9-5, 9-38,
     9-41,  9-42, 9-53, 9-54
 Oxidizing agents
      in compatibility testing
      7-26
 Oxygen 6-1, 6-8, 7-23, 9-15
      and requirements for
      bioreclamation 9-3, 9-15
      to 9-22

 Packed tower 10-48

 Packer 5-28, 5-37

 PCS
      and incineration 7-25
      in compatibility testing
      7-26
      in waste analysis 7-28
      and sediment treatment
      8-45
 PCE
      and  biodegradation  9-2,  9-30
 Permeability 5-8,  5-25
     of  slurry walls  5-87,
     5-88,  5-94
     of  grouts 5-99
     and gas control  systems
     6-4, 6-7

 Permeable treatment bed
     9-56

 Peroxides
     in  compatibility testing
     7-26

 Pesticides
     and biodegradation 9-2,
     9-30

 PH
     in waste analysis 7-28
     in bioreclamation
     monitoring 9-9, 9-32

Phenolic grouts 5-99, 5-100
                                     A-9

-------
                            APPENDIX A (ContinuedO
Phenols
     and biodegradation 9-3,
     9-5

Phosphates
     and bioreclamation
     9-8, 9-22, 9-32

Phytotoxic 3-26, 3-28

Piezometric surface 5-14

Piezometers 5-72

Pipes
     and subsurface drains
     5-47, 5-59 to 5-62, 5-70,
     5-71, 5-79
     and leachate collection
     systems 7-34

Piping
     and liners 3-8, 7-3

Plasma Arc Torch 10-133

Plume
     containment 5-1, 5-2,
     5-16, 5-19, 5-47, 5-54
     prevention 3-4
     removal 5-1, 5-2, 5-47
     diversion 5-5, 5-6
     non miscible 5-17
     floating contaminants
     5-12
     delineation 5-46

Point dumping
     and sediment covers
     8-50, 8-51

Polydimethyl siloxane
     as floating immiscible
     liquid 4-2

Polyester
     and silt curtains 8-28
     and filters 5-62
     as grout 5-100, 5-101
                                     A-10
Polyethylene
     and synthetic membranes
     3-7, 6-8, 7-17, 7-35
     and filters 5-62

Polyhydrldes
     and biodegradation 9-5

Polymerization
     and chemical treatment
     9-36, 9-42, 9-51

Polyolefin
     and synthetic membranes 3-7

Polypropylene
     as filters 5-62
     and synthetic membranes 7-35
     spheres 4-2, 4-3
     as pump coating 7-11

Polyvinyl chloride (see PVC)

Ponds 3-2, 3-3, 3-67 to 3-74

Potentiometric surface
     map 5-17, 5-23, 5-51

Precipitation 9-47, 9-51, 10-22
     in climatology,
     data needs 2-5, 3-9

Precipitation
     and chemical treatment
     9-36, 9-43, 9-50

Pretreatment
     of wastes 7-27

Proctor Density 3-21

Production rates
     backhoes 7-4, 7-6, 8-6
     cranes and attachments 7-6, 7-8
     dozers and loaders 7-9

Production rates
     clamshells 8-2
     draglines 8-5
     pneumatic dredges 8-17

-------
                            APPENDIX A (Continued)
Public health
     in screening remedial
     action alternatives
     2-8, 2-11

Pumps
     submersible 5-25, 5-42, 7-14
     vertical lineshaft 5-26
     performance curves 5-27
     ejector (jet) 5-28, 5-42
     suction (vacuum) 5-5,
     5-30, 5-42
     centrifugal 7-11
     reciprocating 7-11 to 7-13
     diaphram 7-11, 7-12
     bellow 7-11, 7-12
     piston 7-11, 7-12
     positive displacement
     7-13
     gear 7-13
     flexible impeller 7-13
     flying vane 7-13
     immersion 7-14

Pumpdown
     and sedmiment covers
     8-50, 8-51, 8-52

Pump Test 5-8, 5-19

Pumping
     equilibrium vs non-
     equilibrium 5-17, 5-20

Pumping
     rates 5-22
     and groundwater controls
     5-1 to 5-46

PVC (Polyvinylchloride)
     and synthetic membranes
     3-7, 3-12, 6-8, 7-35
     dand filters 5-62
     and silt curtains 8-28
     as pump coating 7-11
PVDF
     as pump coating 7-11
 Pyrolysis  10-135

 Radioactivity
     meters  7-23
     in  compatibility
     testing 7-26
     in  waste analysis
     7-28

 Radius of  influence
     of  a  well 5-2,  5-8,  5-9,
     5-10, 5-12, 5-17,  5-19, 5-20

 Rainfall
     in  climatology,
     data  needs 2-5
     events  (storms) 3-44

 RCRA
     and disposal regulations 3-5
     and capping design 3-5
     and off-site disposal 7-24
     and incineration 7-25
     and transporatation 7-29
     and on-site disposal 7-30, 7-37
     and landfill liner systems 7-32
     and leachate collection systems
     7-32
     and ground water monitoring 7-37
     in remedial action alternatives
     2-10
     landfill  closure requirements
     3-2

 Reactors 10-137

 Reamers 5-35

 Recharge
     in groundwater characteristics,
     data needs 2-5

 Recharge
     rates 5-8

Reduction
     and chemical treatment
     9-38,  9-43, 9-54,  10-55
                                     A-ll

-------
 Remedial  Investigation
      (RI)  1-1

 Remedial  technology
      catagories 2-4
      data  needs 2-5, 2-6

 Removal 7-1 to 7-24

 Resins 10-36
      as grout 5-98
      as dust suppressant 4-5
      as mulch for revegation 3-29

 Revegetation 3-1, 3-3, 3-19, 3-26
      to 3-32
 Reverse osmosis 10-40, 11-5

 Revolving  screens 10-59

 RI/FS 1-1, 2-1, 2-2

 Rock grouting 5-101 to 5-103

 Rotating biological contacter
     10-11

 Rotary kiln 10-126

 Roughness coefficient 5-60

 Runoff
     prevention of 3-1,  3-3, 3-36
     interception of 3-1, 3-3, 3-52
     diversion of 3-36,  3-40, 3-42,
     3-52, 3-57,  3-79

 Safe Drinking Water Act
     (SDWA)
     in remedial  action
     alternatives 2-10

Safety
     in remedial  action
     alernatives  2-10
     field personnel 7-20
APPENDIX A (Continued)

             Salts
Salts
     and soil treatment 3-7
                  and bioreclamation
                  9-23, 9-24

             Scarification 3-21

             Scrapers 7-10, 7-22

             Screens 4-6, 4-7, 5-37

             Screen
                  for wells 5-23 to 5-25,
                  5-31, 5-33, 5-38, 5-43

             Screens and sieves 10-58
                  grizzlies 10-58
                  vibrating 10-59
                  gyratory 10-59
                  revolving 10-59
                  fixed 10-62

             Sediments
                  removal 8-1 to 8-42, 8-44
                  treatment 8-43 to 8-57
                  in-situ control 8-47 to 8-57
                  covers 8-49 to 8-54
                  surface sealing 8-54 to 8-56
                  in-situ grouting 8-56

             Sediments, contaminated
                  in specific site
                  problems 2-4
                  removal and
                  containment of
                  8-1 to 8-60

             Sediment trap 3-64, 3-65

             Sedimentation 10-23, 10-32

             Sedimentation basins 3-2,
                  3-3,  3-67 to  3-74, 10-32

             Seepage basins 3-2, 3-3,  3-63
                  to 3-67

             Seismic history
                  in site geology,
                  data  needs  2-5
                                     A-12

-------
                            APPENDIX A (Continued)
Settling basin 10-71

Sewer lines, contaminated
     in specific site
     problems 2-4

Sewer lines 11-1
     replacement 11-9
     inspection and
     cleaning 11-14
     rehabilitation 11-21

Sheet piling 5-109 to 5-112

Silicate based solidification 10-108
Silicon
     as alloy 7-14

Silt curtains 8-28 to 8-31

Site-specific characteristics
     in technology screening 2-3
     in geology 2-5
     in ground water 2-5
     in surface water 2-5
     in climatology 2-5
     in in-situ treatment
     9-44

Slings 7-6

Sliplining 11-22

Slurry Walls 5-2, 5-83 to
     5-97
     soil-bentonite 5-83 to
     5-92
     cement-bentonite 5-92
     to 5-97
     as gas migration
     barriers 6-7
Soils
     in data needs 2-5
     treatment for liners 3-7
     tests 3-9
     characteristics for
     revegetation 3-28
Soils, contaminated
     in specific site
     problems 2-4

Soil flushing
     and chemical treatment
     9-36, 9-41, 9-43, 9-45 to 9-46

Soil water partition
     coefficient 9-46

Solid bowl solidifications 10-108

Solidification 9-51, 10-106

Solids separation 10-57

Solution mining (see soil
     flushing)

Solvent flushing (see soil
     flushing)

Sorbents 10-111

Sorptive resins 10-36, 10-122

Specific capacity 5-8

Specific gravity
     in waste analysis 7-28

Specific yield 5-22

Spiral classifier 10-66

Stabilization 9-51, 10-106

Stage-down
     and grout curtains
     5-105, 5-107

Stage-up
     and grout curtains 5-105,
     5-107

Stagnation point 5-19, 5-22
                                     A-13

-------
Storage coefficient(s)
     5-8, 5-17, 5-19, 5-20
APPENDIX A (Continued)

             Swales 3-42, 3-43, 3-44

             TCE
Submerged diffuser system
     and sediment covers 8-52,
     8-54

Subsurface barriers (see
     Barriers, subsurface)

Suction Dredge
     in hydraulic dredging
     8-8, 8-32, 8-35

Sulfates
     and bioreclamation 9-31,
     9-32

Sulfides
     in combatibility testing
     7-26
     in pretreatment 7-27

Sulfur
     in waste analysis 7-28

Sumps 5-64, 5-66, 7-34

Superfund 2-1

Surface encapsulation 10-115

Surface water
     in data needs 2-5
     controls 3-1 to 3-88
     collection and transfer
     3-1, 3-3
     storage and discharge
     3-2, 3-3
     diversion and collection
     3-32 to 3-85, 7-20, 8-21

Surface water quality
     in specific site
     problems 2-4

Surfactants 9-46 to 9-48,
     9-49
                  and biodegradation 9-2,
                  9-3, 9-30

             Technology limitations
                  in technology screening
                  2-7

             Technology screening
                  in site characteristics
                  2-3, 2-5
                  in technology limitations 2-7
                  in waste characteristics
                  2-5, 2-7
                  in remedial action
                  alternatives 2-8

             Terraces 3-1, 3-3, 3-21,
                  3-52 to 3-56

             Thermal Destruction 10-123

             Thermoplastic elastomers
                  and synthetic membranes 7-35

             Thermoplastic solidification
                  10-113

             Thiols
                  and biodegradation 9-5
             TOG
                  and bioreclamation monitoring
                  9-32
             Topography
                  in data needs 2-5

             Toxic substance control act
                  in remedial action
                  alternatives 2-10

             Tracing 3-21

             Transmissivity (T) 5-8, 5-15,
                  5-17, 5-19, 5-20, 5-39, 5-45
                                     A-14

-------
                            APPENDIX A (Continued)
Trenches
     excavation 5-67 to 5-70

Trickling filter 10-11

TSCA 2-10

Turbitity control
     and sediments removal
     8-27 to 8-31

Universal soil loss equation
     3-8

Ure a-f o rmaldehyde
     as grout 5-100, 5-101

Ur ethanes
     as grout 5-99, 5-100
Vacuum assisted drying
     beds 10-80

Vacuum loaders 7-15, 7-16, 7-22

Vacuum pumping 10-80

Vapor detectors 7-23

Vegetable gum
     as dust suppressant 4-5

Venturi
     and ejector wells 5-28

Vibrating beam
     and grout curtains
     5-105, 5-107, 5-108

Vibrating screens 10-59

Viscosity
     in waste analysis 7-28

Vitrification 10-116

Wall stabilization
     and subsurface drains
     5-70
Waste characteristics
     in technology screening
     2-5, 2-7
     in specific site
     problems 2-4

Waste migration 3-4

Waste treatment
     in-situ 9-1 to 9-70

Water Spraying 4-7

Water supply 11-1
     contamination 11-1
     replacement 11-2
     treatment 11-4

Water table 5-8, 5-15,
     5-54, 7-33
Waterways 3-1, 3-3,
     3-40 to 3-52

Wedge bar screen 10-62

Wellpoints 5-1, 5-5, 5-7,
     5-30, 5-31, 5-43, 5-69
Wells
     suction 5-1, 5-5, 5-7
     ejector 5-1, 5-5, 5-7,
     5-26 to 5-30
     deep 5-1, 5-5, 5-7,
     5-23 to 5-26, 5-69
     extraction 5-2, 5-3,
     5-4, 5-16, 5-22, 5-46,
     5-47, 9-25 to 9-28
     injection 5-2, 5-4,
     5-16, 5-22, 9-25 to 9-28
Wells
     partially penetrating
     5-8, 5-12, 5-14
     design 5-17 to 5-23
     components 5-23 to 5-31
     driven 5-32, 5-33
     completion 5-37, 5-38
     development 5-38
                                     A-15

-------
                            APPENDIX A (Continued)
     installation 5-32 to 5-38
     maintenance 5-38, 5-39

Wet air oxidation 10-133

Wind fences/screens 4-6, 4-7

XR-5 3-16
                                     A-16

-------
                                  APPENDIX B

                               COPYRIGHT  NOTICE
Figure 3-15
Figure 3-21
Figure 3-22
Figure 3-23
Figure 3-24
Figure 3-30
Figure 3-31
Table 5-1
Figure 5-5
Table 5-5
Figure 5-6
Figure 5-7
From Tourbier, J.  and R. Westmacott.   1974.   Water  Resources
Protection Measures  in Land Development—A Handbook.   Used  by
permission of Water  Resource Center,  University  of  Delaware.

From Tourbier, J.  and R. Westmacott.   1974.   Water  Resources
Protection Measures  in Land Development—A Handbook.   Used  by
permission of Water  Resource Center,  University  of  Delaware.

From Tourbier, J.  and R. Westmacott.   1974.   Water  Resources
Protection Measures  in Land Development—A Handbook.   Used  by
permission of Water  Resource Center,  University  of  Delaware.

From Tourbier, J.  and R. Westmacott.   1974.   Water  Resources
Protection Measures  in Land Development—A Handbook.   Used  by
permission of Water  Resource Center,  University  of  Delaware.

From Tourbier, J.  and R. Westmacott.   1974.   Water  Resources
Protection Measures  in Land Development—A Handbook.   Used  by
permission of Water  Resource Center,  University  of  Delaware.

From Linsley, R. and J. Franzini,  1979.  Water Resources
Engineering, 3rd Edition.  Used by permission of McGraw-Hill
Book Company.  New York, N.Y.

From Tourbier, J.  and R. Westmacott.   1974.   Water  Resources
Protection Measures  in Land Development—A Handbook.   Used  by
permission of Water  Resource Center,  University  of  Delaware.

From Powers, J.P.  1981.  Construction  Dewatering:  A  Guide
to Theory and Practice.  Used by permission of John Wiley and
Sons, Inc.  New York, NY.

From Davis, S.N.and  R.J.M. Deweist.   1966.  Hydrogelogy.
Used by permission of John Wiley and  Sons, Inc.  New York,
NY.

From Johnson Division.  UOP, Inc.  1975.  Groundwater  in
Wells:  A Reference  Book for the Water Well Industry.  Used
by permission of Johnson Division, UOP, Inc.  St. Paul, MN.

From Davis, S.N.and  R.J.M. Deweist.   1966.  Hydrogelogy.
Used by permission of John Wiley and  Sons, Inc.  New York,
NY.

From Powers, J.P.  1981.  Construction Dewatering:  A  Guide
to Theory and Practice.  Used by permission of John Wiley and
Sons, Inc.  New York, NY.
                                     B-l

-------
                            APPENDIX B (continued)
Table 5-7
Figure 5-9


Table 5-9


Figure 5-10



Figure 5-11



Figure 5-12



Figure 5-14



Figure 5-15



Table 5-16
Figure 5-16a&b
Figure 5-16c
Modified from Lundy, D.A. and J.S. Mahan.  1982.  Manuscripts
originally printed in the proceedings of the National
Conference on Management of Uncontrolled Hazardous Wastes  -
1982.  Nov. 29 - Dec. 1.  Used by permission of Hazardous
Materials Control Research Institute.  Available from
Hazardous Materials Control Research Institute, 9300 Columbia
Blvd., Silver Spring, MD  20910.

From Freeze, R.A. and J.A. Cherry.  1981.  Groundwater.  Used
by permission of Prentice-Hall, Inc.  Englewood Cliffs, NJ.

From Church, H.K.  1981.  Excavation Handbook.  Used by
permission of McGraw-Hill Book Company, New York, NY.

From Davis, S.N.and R.J.M. Deweist.  1966.  Hydrogelogy.
Used by permission of John Wiley and Sons, Inc.  New York,
NY.

From Ferris, et. al.  1982.  As cited by Lohman, S.W.   1972.
Ground Hydraulics Geological Survey Professional Paper  708.
Used by permission of US Geological Survey, Reston, VA.

From Johnson Division.  UOP, Inc.   1975.  Groundwater in
Wells:  A Reference Book for the Water Well Industry.   Used
by permission of Johnson Division, UOP, Inc.   St. Paul, MN.

From Flint and Wailing, Inc.   1980.  Putting water to work
since 1866.  Technical  Information Brochure.   Used by
permission of Flint and Walling, Inc.  Kendallville, IN.

From Powers, J.P.  1981.  Construction Dewatering:  A Guide
to Theory and Practice.  Used by permission of John Wiley  and
Sons, Inc.  New York, NY.

Adapted from Jefferis,  S.A.  1981.  Bentonite-Cement Sluries
for Hydraulic Cut-offs.  In:  Proceedings of the Tenth
International Conference on Soil Mechanics and Foundation
Engineering.  Stockholm, Sweden.  June 15-19,  1981.  Used  by
permission of S.A. Jefferis.

From Johnson Division.  UOP, Inc.   1975.  Groundwater in
Wells:  A Reference Book for the Water Well Industry.   Used
by permission of Johnson Division, UOP, Inc.   St. Paul, MN.

From Powers, J.P.  1981.  Construction Dewatering:  A Guide
to Theory and Practice.  Used by permission of John Wiley  and
Sons, Inc.  New York, NY.
                                     B-2

-------
                            APPENDIX B  (continued)
Figure 5-22      From Giddings, T.   1982.  The Utilization  of  a Groundwater
                 Dam for Leachate Containment at a Llandfill Site.   In:
                 Aquifer Restoration and Groundwater Rehabilitation.   2nd
                 National Symposium  on Aquifer Restoration  and Groundwater
                 Monitoring.  May 26-28.  Used by permission of National Water
                 Well Assoc., Worthington, OH.

Figure 5-25      Adapted from Van Schlifgaarde, J.  1974. Drainage  for
                 Agriculture, Agronomy monograph number  17, pages 245-270.
                 Used by permission  of American Society  of  Agronomy.   Madison,
                 WI.

Figure 5-32      Adapted from Jefferis, S.A.  1981.  Bentonite-Cement  Slurries
                 for Hydraulic Cut-offs.  In:  Proceedings  of  the Tenth
                 International Conference on Soil Mechanics and Foundation
                 Engineering.  Stockholm, Sweden.  June  15-19, 1981.   Used by
                 permission of S.A.  Jefferis.

Figure 5-33      Adapted from Bowen, R.  1981.  Grouting  in Engineering
                 Practice.  2nd. Ed.  Used by permission  of John Wiley and
                 Sons,  Inc.  New York, NY.

Figure 5-35      From Soletanche, undated.  Soils Grouting.  Technical
                 Bulletin.  Used by  permission of Soletanche.  Paris,  France.

Figure 5-36      From Ueguhardt, L.C. et al.  1962.  Civil  Engineering
                 Handbook.  Used by  permission of McGraw-Hill  Book  Company.
                 New York, NY.

Figure 6-1       From Emcon Associates and Gas Recovery  Systems, Inc.  1981.
                 Landfill Gas - An Analysis of Options.   Published  by
                 permission of Emcon Associates.  San Jose, CA.

Figure 6-4       From Emcon Associates.  1980.  Methane  Generation  and
                 Recovery From Landfills.  Published by  permission  of  Ann
                 Arbor Science Publishers, Inc.  Ann Arbor, MI.

Figure 6-8       From Emcon Associates and Gas Recovery  Systems, Inc.  1981.
                 Landfill Gas - An Analysis of Options.   Published  by
                 permission of Emcon Associates, San Jose,  CA.

Figure 7-1       From Stubbs, E.W.   1959.  Handbook of Heavy Construction.
                 1st Edition.  Used by permission of McGraw-Hill Book  Company.
                 New York, NY.
                                     B-3

-------
                            APPENDIX B (continued)
Figure 7-4
Table 7-5
Table 7-6
Figure 8-3
Figure 8-10
Table 9-1
Figure 9-1
Figure 9-6
Table 9-7
Table 9-8
From Buecker, D.A. and M.L. Bradford.   1982.  Page 299.
"Safety and Air Monitoring Considerations of the Cleanup of  a
Hazardous Waste Site."  Manuscripts originally printed  in
Proceedings of the National Conference  on Management of
Uncontrolled Hazardous Waste Sites - 1984.  Used by
permission of Hazardous Materials Control Research Institute.
Available from Hazardous Materials Control Research
Institute, 9300 Columbia Blvd., Silver  Spring, MD  20910.

From Cope, F., G. Karpinski, J. Pacey and L. Stein.  Use of
Liners for Containment of Hazardous Waste Landfills.
Pollution Engineering.  Vol. 16. No. 3.  Used by permission
of Pudvan Publishing Co.  Northbrook, IL.

From Cope, F., G. Karpinski, J. Pacey and L. Stein.  Use of
Liners for Containment of Hazardous Waste Landfills.
Pollution Engineering.  Vol. 16. No. 3.  Used by permission
of Pudvan Publishing Co.  Northbrook, IL.

From Merritt, F.   1976.  Standard Handbook for Civil
Engineers.  Used by permission of McGraw Hill Book Company.
New York, NY.

From Alluvial Mining and Shaft Sinking  Co., Ltd. 1984,
Equipment and Services Brochure.  Used  by permission of
Alluvial Mining and Shaft Sinking Co.,  Ltd.  Basildon,
5S14-1EA, England.

From Lyman, Reehl and Rosenblatt.  1982.  Handbook of
Chemical Property Estimation Methods.   Used by permission of
McGraw-Hill Book Company.  New York, NY.

From Johnson Division.  UOP, Inc.  1975.  Groundwater in
Wells:  A Reference Book for the Water  Well Industry.   Used
by permission of Johnson Division, UOP, Inc.  St. Paul, MN.

From Jhaveri, V. and A.J. Mazzacca.  1983.  Bio-reclamation
of Ground and Groundwater by CDS Process.  Used by permission
of Groundwater Decontamination Systems.  Waldwick, NJ.

From Jamison, V.W., R.L. Raymond and J.O. Hudson.  1976.
Biodegradation of High-Octane Gasoline.  In:  Proceedings of
the Third International Biodegradation  Symposium.  Used by
permission of Elsevier Applied Science  Publishers.  Barking,
Essex 1G11, 8JU, England.

From Groundwater Decontamination Systems, Inc.  Report  1.
Experiments from Sept.  15 to Nov. 5.  Used by permission of
Groundwater Decontamination Systems.  Waldwick, NJ.

                    B-4

-------
                             APPENDIX B (continued)
 Figure  9-8
 Table  9-15
Table 9-19
Table 10-1
Table 10-2
Figure 10-3
Figure 10-4
Table 10-5
 From Sullivan,  J.M.,  D.R.  Lynch,  and I.K.  Iskandar.   1984.
 The  Economics of  Ground  Freezing  for Management  of
 Uncontrolled Hazardous Waste  Sites.   In:   Proceedings  of the
 1984 Hazardous  Material  Spills  Conference.   Used by
 permission  of Government Institutes  Inc.   Rockville, MD.

 From Sims,  R.C. and K. Wagner.   1983.   In-situ Treatment
 Techniques  Applicable to Large  Quantities  of Hazardous Waste
 Contaminated Soils.   In:   Proceedings  of National Conference
 on Management of  Uncontrolled Hazardous Waste Sites.   October
 31 - Nov. 2.  Used by permission  of  Hazardous Materials
 Control  Research  Institute.   Available from Hazardous
 Materials Control Research Institute,  9300 Columbia Blvd.,
 Silver Spring,  MD  20910.

 From Fitzpatrick, V.F.,  J.L.  Vcelt,  K.H. Ource,  and C.L.
 Timmerman.  1984.  In Situ Vitrification - A Potential
 Remedial Action for Hazardous Wastes.   In:   Proceedings of
 the  1984 Hazardous Material Spills Conference.   Reproduced
 with  permission of Government Institutes Inc.  The entire
 publication 1984 Hazardous Material  Spills  Conference
 Proceedings is  available  from Government Institutes, Inc.,
 966 Hungerford  Drive, #24, Rockville,  MD   20850.

 From  Conway, R.A. and R.D. Ross.  1980.  Handbook of
 Industrial  Waste Disposal.  Used by  permission of Van
 Nostrand Reinhold Company.  New York,  NY.

 From  O'Brien, R.P. and J.L. Fisher,  1983.   There  is an Answer
 to Groundwater  Contamination.   Reprinted from
Water/Engineering and Management.  Used by  permission  of
 Scranton Gillette Communications, Inc.  Des  Plaines, IL.

 From  Gulp,  R.L., G.M. Wesnar  and G.L.  Gulp.   1978.  Handbook
 of Advanced Wastewater Treatment.  2nd Ed.   Used  by
 permission  of Van Nostrand Reinhold  Co. New York,  NY.

 From  DeRenzo, D. (ed).   1975.   Unit  Operations for Treatment
of Hazardous Wastes.   Used by permission of  Noyes Data
 Corporation.  Park Ridge,  NJ.

From  Conway, R.A.  and R.D. Ross.  1980.  Handbook of
 Industrial Waste Disposal.  Used by  permission of Van
Nostrand, Reinhold Company, New York, NY.
Figure 10-6
From DeRenzo, D. (ed).  1975.  Unit Operations for Treatment
of Hazardous Wastes.  Used by permission of Noyes Data
Corporation.  Park Ridge, NJ.

                    B-5

-------
                            APPENDIX B (continued)
Figure 10-9
Figure 10-10
Table 10-10
Table 10-12
Figure 10-12
Table 10-14
Figure 10-13
Figure 10-14
Figure 10-15
Figure 10-16
Figure 10-17
From Gulp, R.L., G.M. Wesnar and G.L. Gulp.  1978  Handbook
of Advanced Wastewater Treatment.  2nd Ed.  Used by
permission of Van Nostrand Reinhold Co., New York, NY.
From Chemical Separations Corp.
Ridge, TN.
Ion Exchange Systems.  Oak
Hale, F.D., C. Murphy, Jr., and R. Parrat.  1983.  Page  195.
"Spent Acid and Plating Waste Surface Impoundment Closure."
Manuscripts originally printed in the Proceedings of  the
National Conference on Management of Uncontrolled Hazardous
Waste Sites - 1984 and Hazardous Wastes and Environmental
Emergencies - 1984.  Available from Hazardous Materials
Control Research Institute, 9300 Columbia Blvd., Silver
Spring, MD  20910.

From Whittaker, H.  1984.  Development of a Mobile Reverse
Osmosis Unit for Spill Clean Up.  In:  Proceedings of the
1984 Hazardous Materials Spills Conference.  Reproduced with
permission of Government Institutes, Inc.  The entire
publication 1984 Hazardous Material Spills Conference
Proceedings is available from Government  Institutes,  Inc.,
966 Hungerford Drive, #24, Rockville, MD  20850.

From Canter, L.W. and R.C. Knox.  1985.   Groundwater
Pollution Control.  Used by permission of Lewis Publishers,
Inc.  Chelsea, MI.
From O'Brien, R.P. and M.H. Stenzel.
Calgon Corp.  Pittsburgh, PA.
     Used by permission of
From Allis-Chalmers Corp.  undated.  Model SH-Rip-Flo-
Inclined vibrating screen.  Bulletin 26B11211.  Used by
permission of Allis-Chalmers Corp.  Milwaukee, WI.

From Dorr-Oliver Inc.  1983.  DSM Screens for the Process
Industries.  Bulletin No. DSM-1.  Used by permission of
Dorr-Oliver, Inc.  Stamford, CT.

From Eagle Iron Works.   1982.   Eagle Fine and Coarse Material
Washers.  General Catalog, Section C.  Used by permission of
Eagle Iron Work.  Des Moines, IW

From Eagle Iron Works.   1982.   Eagle Fine and Coarse Material
Washers.  General Catalog, Section C.  Used by permission of
Eagle Iron Work.  Des Moines, IW

From Krebs Engineers,  undated.  Krels Water Only Cyclones.
Used by permission of Krebs Engineers.  Menlo Park, CA.
                                     B-6

-------
                            APPENDIX B  (continued)
Figure 10-19
Figure 10-20
Figure 10-21
Figure 10-22
Figure 10-34
Figure 10-44
Figure 10-45
Figure 10-46
Figure 10-48
Figure 10-49
Figure 10-50
Figure 10-51
From Dorr-Oliver Inc.   1976.  Dorr-Oliver  Clarifiers  for
Municipal and Industrial Wastewater Treatment.  Bulletin  No.
6192-1.  Used by permission of Dorr-Oliver,  Inc.   Stamford,
CT.

From Parkson Corporation,  1984.  Lamella Gravity
Settler/Thickener, Bulletin LT-103.  Used  by  permission of
Parkson Corporation.  Fort Lauderdale, FL.

From Gulp, R.L., G.M. Wesnar and G.L. Gulp.   1978  Handbook
of Advanced Wastewater  Treatment.  2nd Ed.   Used by
permission of Van Nostrand Reinhold Co., New  York, NY.

From Gulp, R.L., G.M. Wesnar and G.L. Gulp.   1978  Handbook
of Advanced Wastewater  Treatment.  2nd Ed.  Used by
permission of Van Nostrand Reinhold Co., New  York, NY.

From DeRenzo, D. (ed).  1975.  Unit Operations  for Treatment
of Hazardous Wastes.  Used by permission of Noyes Data
Corporation.  Park Ridge, NJ.

From Vatavuk, W.M. and  R.B. Neveril.  1983.   Cost of  Flares
Chemical Engineering.   Vol. 90, No. 4.  Used  by permission of
McGraw-Hill, New York,  NY.

From Vatavuk, W.M. and  R.B. Neveril.  1983.   Cost of  Flares
Chemical Engineering.   Vol. 90, No. 4.  Used  by permission of
McGraw-Hill, New York,  NY.

From Kiang, Y and A.R.  Metry.  1982.  Hazardous Waste
Processing Technology.  Used by permission of Ann Arbor
Science Publishers, Inc.  Ann Arbor, MI.

From Kiang, Y and A.R.  Metry.  1982.  Hazardous Waste
Processing Technology.  Used by permission of Ann Arbor
Science Publishers, Inc.  Ann Arbor, MI.

From Kiang, Y and A.R.  Metry.  1982.  Hazardous Waste
Processing Technology.  Used by permission of Ann Arbor
Science Publishers, Inc.  Ann Arbor, MI.

From Rockwell International.   1980.  Molten Salt Destruction
of Hazardous Wastes.  Pub. 523-K-18-1.  Used by permission of
Rockwell International.   Canoga Park, CA.

Pradt, L.A.  1972.  (updated 1976).  Developments in Wet Air
Oxidation.  Chemical Engineering Progress.  Used by
permission of American  Institute of Chemical Engineers, New
York,  NY.
                                     B-7

-------
                            APPENDIX B (continued)
Figure 10-52
Figure 10-53
Figure 10-54
Figure 10-55
Table 10-19
Table 10-20
Table 10-21
Figure 11-1
From Lee, C.C., E.L. Keitz and G.A. Vogel.   1982.  Hazardous
Waste Incineration:  Current/Future Profile.  Manuscripts
originally printed in Proceedings of the National Conference
on Management of Uncontrolled Hazardous Waste Sites -  1982.
Used by permission of Hazardous Materials Control Research
Institute.  Available from Hazardous Materials Control
Research Institute, 9300 Columbia Blvd., Silver Spring, MD
20910.

From Ross, R.D.  1984.  Hazardous Waste Incineration:  More
Attractive Now than Ever Before.  Hazardous Materials  and
Waste Management Magazine.  Vol. 2, No. 5.  Used by
permission of the Hazardous Materials & Waste Management
Assoc., Kutztown, PA.

From Lee, C.C., E.L. Keitz and G.A. Vogel.   1982.  Hazardous
Waste Incineration:  Current/Future Profile.  In:
Proceedings of the National Conference on Management of
Uncontrolled Hazardous Waste Sites.  Nov. 29 - Dec. 1, 1982.
used by permission of Hazardous Materials Control Research
Institute.  Silver Spring, MD.

From Vogel, G.A. and E.J. Martin.  1983.  Equipment Sizes and
Integrated Facility Cost.  Chemical Engineering.  Vol. 90,
No. 18.  Used by permission of McGraw-Hill,  Inc.  New  York,
NY.

Adapted from Vogel, G.A. and E.J. Martin.  Estimating
Operating Costs.  Chemical Engineering.  Vol. 91, No.  1.
Used by permission of McGraw-Hill, Inc.  New York, NY.

Adapted from Vogel, G.A. and E.J. Martin.  Estimating
Operating Costs.  Chemical Engineering.  Vol. 91, No.  1.
Used by permission of McGraw-Hill, Inc.  New York, NY.

From Star, A.  1985.  Cost Estimating for Hazardous Waste
Incineration.  Pollution Engineering.  Vol.  16, No. 7.  Used
by permission of Pudvan Publishing Co., Northbrook, IL.

From Hammer, M.J.  1975.  Water and Wastewater Technology.
Used by permission on John Wiley and Sons, Inc.  New York,
NY.
Figure 11-2
From Hammer, M.J.  1975.  Water and Wastewater Technology.
Used by permission on John Wiley and Sons, Inc.  New York,
NY.
                                     B-8

-------
                            APPENDIX B (continued)
Figure 11-3      From Water Pollution Control Federation.  1983.  Existing
                 Sewer Evaluation and Rehabilitation.  Manual of Practice
                 FD-6.  Used by permission of Water Pollution Control
                 Federation.  Washington, DC.

Figure 11-4      From Water Pollution Control Federation.  1983.  Existing
                 Sewer Evaluation and Rehabilitation.  Manual of Practice
                 FD-6.  Used by permission of Water Pollution Control
                 Federation.  Washington, DC.

Figure 11-5      From Water Pollution Control Federation.  1983.  Existing
                 Sewer Evaluation and Rehabilitation.  Manual of Practice
                 FD-6.  Used by permission of Water Pollution Control
                 Federation.  Washington, DC.

Figure 11-6      From Water Pollution Control Federation.  1983.  Existing
                 Sewer Evaluation and Rehabilitation.  Manual of Practice
                 FD-6.  Used by permission of Water Pollution Control
                 Federation.  Washington, DC.
                                     B-9
                                  ปU.S. GOVERNMENT  PRINTING OFFICE. 1986-646' I I 6/40604

-------