-------
1
^
^
o
c
in
^O
^^
i/>
ro
«-
K
O
*
II
V)
4-»
O
o
^^
4_,
u
(0
^
o
u
*-*
c
-Q
I_
o
{/)
-O c
(U O!
+J
c °
o 3
<_> -4-
V
en
CO
cu
r~t c-
i U
rt .£
OJ O
LiJ £
1 o
CO
3c i *-
u- c
C C
01
t_ fO -
(ft O -O
s. o*
O O O
DO C
* *
L.
O U. L
**- Q£ C
* 4
03
C Z =
0
it *
a. c\j h
0 CO M
^ -S± C T-
«- to
u. «
' O O ^
4) L. 4-1
y) *- (J
O t- D
03 .D "D
4» (U C
oe. u-
sO N. CO
C/l
+*
W
O
u
4_i
c
0)
Q
«-
3
cr
Oi
>s
L_
fD
>
r»
X
D
(0
T3
C
(0
(_
4^
H-
(J
t_
_Q
O)
^+-
>4-
0
fr
C\J
r^
+
o
o en
O 4J
- en
3 «- 0
3 ». 0
3 *^
C
x O (1<
a E
# -
-l CT
7 cu
*
C
u. O
£ 4-1
* U
(U
z >
E C
f^ en 4^
3 vO en cu
CO 0 -Q
- o O
0
II CU X
n en T3
-* 4-< a en
n -* en 4-4-'
3 L o CO en
J O U O O
3 .r- 54; CJ
4J 4.. o
3 o
O ' II CU
co e.
4-* "-
en TJ
c c
0
4-
c
0
^
u
0)
c
4V
C 4-»
0) C
Q CT
t- CU
o
X
c- e_
o (0 en
en
^ .^ o
en x u
4-» 3
en co X
O 0
0 T> C
c cu
c (0 aj
o c
^- e_ en -
4-* CU 4-* 4^
co 4-« en c
o o
.- 0 O
(U *4-
cn o u
c - cu e/>
^3 '^ en
+ CO T3 O
*- c o
C CU 4--
CU JZ "D O
E 4J c <1>
a. co e.
CT-4- 0 C
cu eu
^ 4-1 L.
(/) ' +
en o "D
4-* o en
en H- 4-»
O 4J O CO
0 C O
CU E U
o a «
CU "- 4-t O
i-3 cu en cu
"O CU 4J O
a
>> 4J "oj
to rj co Q o
a u
II C II II
* ^
4J CD
C 4->
O O
C_3 H*
1
O (-
o
e. *4-
co w
en
e. o
O u
*4-
en en
o a.
4-- en
O LLI
(0
4- 0)
C
4^
M- en
o -
I- X
4S CU
cu
J '5
C CO
CU -M
QL. CD
D a.
CT
cu e.
O
C u.
O
r
4-*
O en
CU 4-<
i en
C -
O X
cu
4J *
C CL
O> fl 00
-Q U-i
E t- u_
H- O C£ O
o y> c
03 -
t- C/3 0>
0 -M L.
C JT
C «- 3 3
t- 3 CO
I- O) C
0) M- C 0
a. o -
t- (- O 03
01 O u- U
_ o
' CO Q.
N- H- >* a.
u *-» >
..- < 4--
JQ O 0) M-
03 ( O
H- *-* -Q t-
0) OJ 4-*
JZ (_
-M 0» E
(/) O L.
O 3 (- O
4-» *+- H-
to OK) « ~a "D
U 4-- W CO) C
03 03 H- O C 03 ^J
{_ >r> -i |
3 » 4-» 03 tr co
O O *- CD 4-» C
*O C U .O O 0>
4-03 O
f- 4J J3
O^ 03 Q. t- O t
*" ^= E
1- t_ 4) 4-* 4-J 4-J D- O
a> ^ 3 ' c a. L.
^ **^ ' t_ >4-0> (D H-
E ^3 M- 0 0 E
o> M- t_ a. 3 ^o
(J _* 4-» - O> 0>
0) » (D Q> 0>3 C*-^
o *-* 3 E L. o" u- (- (/>
4) 4) -C O - 4-* 0)
4-* Q 4_» < i _rf 4) (/) 0)
(0 W i- - 0) 3 t-
E 0»»*-C04-iOXH- 03
4-» O 4-» D 0)
4^ 03 otconJ*^- o.
(A t_ 4-» O) D (0 JT (DC/)
4) C 03 »4~ "O 4-* LLJ
t3 4) t- H- C O) a)
L- 4) t_ *- .^ 0)0>.C
a. a» o oi '
as a) oi .Q t_ 4-< 4-< a>
4-* E in E E *- ' u M- c
(/j .^ CM .^- 3 0) - 3
O -- « ' C QC M- "O O"D
(J -^-03
H II II II II II L. L_
* & O)
l u_ u. 03 a.
1 ^ C/J O > «E ^ i n ^
1 (0 jQ U
2.3-5
-------
2.3.3 Operating Cost Procedures
Table 2.3-2 presents procedures for estimating operating costs for dry
sorbent injection alone. Operating costs for humidification are presented in
Section 3.5. The operating and maintenance labor requirements and maintenance
materials for sorbent injection are based on typical values for coal-fired
boilers. Electricity costs are based on electrical requirements to operate
the pneumatic feed systems. Lime costs are based on the amount of lime
injected. Equations for electricity and lime were taken from Reference 10.
Table 2.3-3 presents procedures for estimating operating costs for FF's.
The operating and maintenance labor requirements are based on those from
established EPA procedures, with the exception of maintenance materials.
Because maintenance material requirements for FF's can vary directly with the
size of the unit, maintenance material costs are assumed to be calculated at
five percent of the direct capital costs. This percentage is the same one
used for dry sorbent injection to estimate maintenance material costs. The
cost of bag replacement assumes a 2-year bag life, which is typical for FF's.
A gross air-to-cloth ratio of 3:1 is used.
Electricity to operate the I.D. fan is calculated using a total pressure
drop of 12.5 inches of water, 7 inches of water across the FF and 5.5 inches
for the additional ductwork and dry sorbent injection. The cost of compressed
air for the pulse jet FF's is estimated from established EPA procedures. The
costs for solids disposal are determined from the amount of solids collected
by the FF and a tipping fee of $25/ton.
All cost rates are based on December 1987 dollars. The operating labor
wage is the average from those obtained from the Department of Commerce Survey
of Current Business for private nonagricultural payrolls and EPRI's Technical
Assessment Guide. ' Electricity rates will be obtained from the Energy
Information Administration, Monthly Energy Review. Operating hours per year
can be varied to meet model plant specifications.
Indirect operating costs such as taxes, insurance, and administrative
charges are based on percentages of the capital costs. Payroll and plant
overhead are based on a percentage of the labor and material costs.
2.3-6
-------
TABLE 2.3-2. ANNUAL OPERATING COST PROCEDURES FOR
DRY SORBENT INJECTION FOR NEW MWC's11
Operating Labor:
Supervision:
Maintenance Labor:
Materials:
Electricity:
Lime:
Overhead:
Taxes, Insurance,
and Administrative
Charges:
2 manhour/shift
15% of operator labor costs
0.5 manhour/shift, 10% premium
over operating labor wage
5% of total direct costs
(52.56 * (lime feed ratea) + 251,850) *
(electricity costs) * (hours of
operation/8,760)
4.38 * (lime feed rate3) * (lime cost) *
(hours of operation/8,760)
60% of the sum of all labor costs
(operating, supervisory, and
maintenance) plus maintenance material
4% of total capital costs
References
14
18
18, 19
20, 21
22
22
23
23
aLime feed rate in Ib/hr is based on 100 percent capacity of waste processed.
2.3-7
-------
TABLE 2.3-3. ANNUAL OPERATING COST PROCEDURES
FOR FABRIC FILTERS FOR NEW MWC's
Operating Labor:
Supervision:
Maintenance Labor:
Materials:
Bag Replacement:
Electricity:
Compressed Air:
Sol id Waste:
Overhead:
Taxes, Insurance,
and Administrative
Charges:
Capital Recovery:
2 manhour/shift
15% of operator labor costs
1 manhour/shift, 10% wage rate premium
over operating labor wage
5% of direct capital costs
2
$1.35/ft for teflon coated fiberglass;
2-year 1ife
Calculated based on fan requirements
for inches of water pressure drop
across FF
2 scfm/1,000 acfm flue gas
Apply appropriate tipping fee in $/ton
(Assume $25/ton)
60% of the sum of all labor costs
(operating, supervisory, and
maintenance) plus materials
4% of total capital costs
15-year life and 10% interest rate
References
24
24
18, 24
20
25
26
27
28
23
23
29
2.3-8
-------
REFERENCES
1. Radian Corporation. Municipal Waste Combustors - Background Information
for Proposed Standards: Post-Combustion Technology Performance.
EPA-450/3-89-27C. August 1989.
2. Reference 1.
3. Letter from Sedman, C.B., EPA, to Chang, J., Acurex Corporation.
July 14, 1986. EPA guidelines for costing flue gas cleaning technology
for municipal waste combustion.
4. Reference 1.
5. Reference 1.
6. Callaspy, D.T. Dry Sorbent Emission Control Prototype Conceptual Design
and Cost Study. Presented at the First Joint Symposium on Dry S02 and
Simultaneous SCL/NO Control Technologies. November 1984.
£ /\
7. Process Plant Construction Estimating Standards. The Richardson Rapid
System. Volume 4. 1982. p. 100-45.
8. Stearns Catalytic Corporation. Economic Evaluation of Dry-Injection Flue
Gas Desulfurization Technology. Prepared for Electric Power Research
Institute. Palo Alto, CA. EPRI No. CS-4343. January 1986. Appendix A.
9. Garrett, D.E. Chemical Engineering Economics. Van Nostrand Reinhold,
New York. 1989. p. 298.
10. Radian Corporation. Industrial Boiler Furnace Sorbent Injection
Algorithm Developed. Prepared for U. S. Environmental Protection Agency.
Research Triangle Park, NC. Contract No. 68-02-3994. May 1986. p. 10.
11. U. S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies. Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987. p. 3-6.
12. Reference 10, pp. 9 and 10.
13. Electric Power Research Institute. TAG^-Technical Assessment Guide
(Volume 1: Electricity SUDD!v-1986). Palo Alto, CA. Publication No.
EPRI P-4463-SR. December 1986. p. 3-3.
14. U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A. February
1987. p. 5-42.
15. Reference 13, p. B-4.
2.3-9
-------
16. United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. June 1988. p. S-12.
17. Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. DOE/EIA-0035 (87/12).
March 1988. p. 109.
18. Reference 10, p. 12.
19. Neveril, R.B., (GARD Inc.). Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for U. S. Environmental Protection
Agency. Research Triangle Park, NC. Publication No. EPA 450/5-80-002.
December 1978. p. 3-12.
20. Reference 10, p. 11.
21. Reference 8, p. 1-9.
22. Kaplan, N. et al. Control Cost Modeling for Sensitivity and Economic
Comparison. Proceedings from the 1986 Joint Symposium on Dry S02 and
Simultaneous S0,/N0 Control Technologies, EPRI CS-4966, Volume 2.
£ A
23. Reference 14, p. 2-31.
24. Reference 10, p. 2-31.
25. Reference 14, p. 5-39 and 5-43.
26. Reference 20.
27. Reference 14, p. 5-45.
28. Reference 14, p. 2-29.
29. Reference 19, p. 3-16.
2.3-10
-------
2.4 SPRAY DRYING WITH EFFICIENT PARTICULATE CONTROL
2.4.1 Overview of Technology
Spray drying is designed to control S02 and HC1 emissions. When used in
combination with an efficient participate control system, spray drying can
also control CDD/CDF, PM, and metals emissions. In the spray drying process,
lime slurry is injected into a spray dryer (SD) vessel. The water in the
slurry evaporates to cool the flue gas, and the lime reacts with acid gases to
form salts that can be removed by a PM control device. The simultaneous
evaporation and reaction increases the moisture and particulate content in the
flue gas. The particulate exiting the SD vessel contains fly ash plus calcium
salts, water, and unreacted lime.
Spray drying is commonly used in combination with either a fabric
filter (FF) or an electrostatic precipitator (ESP) for PM control. Both
combinations have been used for MWC's in the United States, although SD/FF
systems are more common and may be more effective for CDD/CDF, PM, and metals
control. Two basic designs of FF's are available:" reverse air and
pulse jet. In a reverse air FF, flue gas flows through unsupported filter
bags, leaving the particulate on the inside of the bags. The particulate
builds up to form a particulate filter cake. Once an excessive pressure drop
across the filter cake is reached, air is blown through the filter in the
opposite direction, the filter bag collapses, and the filter cake falls off
and is collected. In a pulse jet FF, flue gas flows through supported filter
bags leaving particulate on the outside of the bags. To remove the built-up
particulate filter cake, compressed air is introduced through the inside of
the filter bag, the filter bag expands and the filter cake falls off and is
collected. The cost procedures are based on pulse jet FF systems.
2.4.2 Capital Cost Procedures
Vendor capital cost estimates for SD systems combined with either an ESP
or a FF applied to three types of MWC's (mass-burn, modular, and RDF) were
obtained for systems designed to achieve 90 percent HC1 and 70 percent S0«
removal and PM emissions of 0.01, 0.02, and 0.03 gr/dscf at 12 percent COp.1
A cost comparison of SD/FF and SD/ESP systems designed to achieve a PM
emission rate of 0.01 gr/dscf at 12 percent C02 is presented in Appendix A for
2.4-1
-------
two mass-burn facility capacity sizes (250 and 3,000 tons/day of MSW). This
comparison indicates that, at this PM control level, costs for SD/FF and
SD/ESP systems are very similar, with the annualized costs for SD/FF's being
slightly lower than for SD/ESP's. Although cost procedures presented in this
section focus on SD/FF systems, they are representative of costs for SD/ESP
systems.
Cost procedures for stand-alone SD systems (i.e., without a FF) are
presented in Section 3.6. These procedures were developed based on the SD/FF
data plus supplemental cost quotes from three SO manufacturers. These cost
procedures are intended to assist in evaluating methods to retrofit SD systems
at existing plants already equipped with efficient PM control devices.
2.4.2.1 Direct Costs. Direct costs for an SD/FF system include
purchased equipment cost for an SD, FF, induced draft (I.D.) fan, and ducting.
The SD components include a reaction vessel, atomizer, lime feed preparation
equipment, and solids handling equipment. The SD is sized based on a
stoichiometric ratio (moles of calcium per mole of both 862 and HC1 in the
flue gas entering the spray dryer) of 1.5:1. The FF cost is based on a
pulse-jet type unit operated at a net air-to-cloth ratio of 4:1 and a gross
air-to-cloth ratio of 3:1.
Costs for single SD/FF units were based on cost data provided by two
manufacturers as shown in Table 2.4-1. The data from these two manufacturers
were used to estimate installed capital costs of SD/FF systems for all furnace
2
types and are plotted as a function of flue gas flowrate in Figure 2.4-1.
The costs are approximately the same for any combustor type at the same
flowrate. There are two reasons for this. First, the cost of the FF is
assumed to be sensitive only to flue gas flowrate and is unaffected by PM
grain loading. Second, the inlet SCk and HC1 concentrations in the flue gas
were assumed to be essentially the same for all facility types. Inlet SO- and
HC1 concentrations primarily depend on the MSW composition (particularly
sulfur and chlorine contents) and MSW heating value. The values for these
three factors assumed for the three facility types result in approximately the
same S0« and HC1 concentrations.
2.4-2
-------
TABLE 2.4-1. VENDOR QUOTES FOR SPRAY DRYER/FABRIC FILTER TOTAL
CAPITAL COSTS (IN $1,000 AUGUST 1986)a
Flue gas
;e flowrates, Outlet PM emissions, qr/dscf at 12% CO,,
Vendor
C
C
G
type
MB
MB
MB
acfm
24,523
245,230
245,230
0.03
1,712
5,262
6,000
0.02
1,712
5,262
6,000
0.01
1,762
5,624
6,000
Installed capital costs reported are the purchase costs for one unit
multiplied by a 1.6 adjustment factor. Auxiliary equipment costs are not
included.
MB = mass-burn.
C0utlet grain loading from fabric filters.
tmg.017
section.2-4
2.4-3
-------
too
90
e
J
to
OulM Loading.
0.01
0.02grM«cf
Q
0.03grM«cf
Figure 2.4-1.
Capital cost estimates of an SD/FF for a model MB facility, and
RDF facility.2
2.4-4
-------
Table 2.4-2 summarizes the capital cost procedures for single SD/FF
units. These procedures are based on achieving a PM control level of
0.01 gr/dscf at 12 percent CCu. The equation was developed from
Figure 2.4-1.
From Table 2.4-2, the total direct costs can be estimated for single
units by knowing the inlet flue gas flowrate and the length of ductwork
needed. The flue gas flowrate is based on 125 percent of the design flowrate
to accommodate variations in feed waste composition and operating conditions.
To estimate the costs of multiple units, the direct costs of a single SD/FF
unit including auxiliary equipment are multiplied by the number of units.
2.4.2.2 Indirect and Other Costs. To be consistent with established EPA
methodology, the equations were adjusted to distinguish direct costs (i.e.,
purchased equipment and installation costs) from indirect capital costs (i.e.,
engineering costs, construction and field expenses, contractor fees, start-up
and performance test costs). To separate these costs, indirect costs are
assumed to be 33 percent of the direct capital costs. Contingency is assumed
to be similar to that applied to fossil-fuel fired boilers. Interest during
construction and working capital is not included for air pollution control
devices. Costs are reported in December 1987 dollars. The Chemical
Engineering Plant Cost Index for all equipment was used to escalate costs from
August 1986 dollars.
2.4.3 Operating Cost Procedures
Table 2.4-3 presents the procedure for estimating operating costs. In
general, the references in this table have been used in previous EPA cost
analyses.
The operating and maintenance labor requirements for SD/FF are based on
those used in fossil fuel industrial boiler cost analyses and assume that
operating and maintenance labor costs bases would be essentially the same for
coal-fired industrial boilers and MWC facilities. However, the maintenance
material cost for SD/FF systems applied to MWC facilities is usually lower
than the cost for systems at coal-fired boiler facilities, since uncontrolled
SCL emissions are much higher from coal-fired boilers. Because SCu
concentrations are lower at MWC facilities, less concentrated slurries can be
2.4-5
-------
TABLE 2.4-2. CAPITAL COST PROCEDURES FOR SD/FF FOR NEW MWC'S3
Total Direct Costs (December 1987 dollars)
Single SD/FF Unitb: Costs, 103 $ = 8.053 (Q)0'517
Ductworkb: Costs, 103 $ = [1.3868 * L * Q°'5]/l,000
Fanb: Costs, 103 $ = [1.8754 * Q0t96]/l,000
Multiple Units: Multiply the above costs by the number of units
Indirect Costs = 33% of total direct costs
Contingency = 20% of sum of direct and indirect costs
Total Capital Costs = Total Direct Costs + Indirect Costs + Contingency Costs
aQ = 125 percent of the actual flue gas flowrate, acfm
L = Duct length, feet
Assumes that the total installed costs are 133 percent of the direct capital
costs.
2.4-6
-------
TABLE 2.4-3. ANNUAL OPERATING COSTS PROCEDURES FOR
SPRAY DRYER/FABRIC FILTER FOR NEW MWC's3
Reference
Operating Labor: 4 manhours/shift; $12/manhour 8, 9
Supervision: 15% of operating labor costs 10
Maintenance:
Labor: 2 manhours/shift; 10% wage rate premium 9
over operating labor wage
Materials: 2% of direct capital costs 11
Bag Replacement:
2
Bags: $1.35/ft for teflon-coated fiberglass; 12
2-year life for SD/FF;
Bag replacement cost not included for SD only
Electricity: Cost Rate = $0.046/kwh
Fan: 12.5 inches of water pressure drop 13, 14
Atomizer: 6kW/l,000 Ibs/hr of slurry feed + 15kW 15
Pump: 20 feet of pumping height 16
10 psi discharge pressure
10 ft/sec velocity in pipe
Compressed Air: 2 scfm air/1,000 acfm flue gas; 17
$0.11/1,000 scfm of air
Water: Calculate water flowrate required for cooling the flue 18
gas to 300°F; water cost = $0.50/1000 gal
Lime: Based on lime feed rate calculated for a given 19
stoichiometric ratio; lime cost = $70/ton
Solid Waste: Calculate solid waste collected by the spray 20
dryer and fabric filter using PES program and
apply appropriate ash disposal fee in $/ton;
Assume $25/ton
(continued)
2.4-7
-------
TABLE 2.4-3. (Continued)
Reference
Overhead: 60% of the sum of all labor costs (operating, 21
supervisory, and maintenance) plus materials
Taxes, Insurance, and
Administrative Charges: 4% of total capital costs 21
Capital Recovery: 15-year life and 10% interest rate 22
aAll costs are in December 1987 dollars.
2.4-8
-------
used to achieve the same removal efficiency, which in turn result in less
erosion of equipment and potential for plugging. Therefore, the maintenance
23
material cost was estimated at 2 percent of the direct capital cost.
Estimating the material cost at 2 percent of the direct capital cost
corresponds to 1.25 percent of the total capital costs.
The costs of bag replacement assumes a 2-year bag life, which is a
24
typical bag-life for FF's. A gross air-to-cloth ratio of 3:1 is used.
Electricity costs include electricity consumed by the I.D. fan, atomizer, and
slurry pumps. Electricity consumed by the I.D. fan is calculated using a
pressure drop of 12.5 inches of water across the SD/FF. Atomizer electrical
25
requirements are based on the amount of slurry feed. Slurry pumping
requirements are estimated from assumed pumping height, discharge pressure,
26
and fluid velocity in pipe used in previous cost analysis. The costs for
compressed air for pulse-jet FF's are estimated from the air usage rate of 2
27
scfm/1,000 acfm of flue gas. The stoichiometric ratio (moles of calcium per
mole of SOp and HC1 in the inlet flue gas) assumed is 2.5 to achieve 90
percent SOp and 97 percent HC1 removals.
All cost rates are based on December 1987 dollars. The operating labor
wage rate used is the average from those in the Department of Commerce, Survey
of Current Business for private nonagricultural payrolls and EPRI's Technical
?8 29
Assessment Guide. ' Electricity rates are from the Energy Information
Administration, Monthly Energy Review. The freight-on-board (FOB) costs for
quick lime (calcium oxide, CaO), $45/ton bulk, are from the Chemical Marketing
Reporter; an additional cost of $25/ton is assumed for transportation, based
on a hauling rate of $0.05/ton-mile and a 500-mile hauling distance. For
estimating ash disposal costs, a tipping fee of $25/ton is used. For new
plants, the operating costs will be based on the assumption of 8,000 hours of
operation per year; however, operating costs can be calculated for any number
of operating hours.
2.4-9
-------
REFERENCES
1. U. S. Environmental Protection Agency. Municipal Waste Combustion
Study: Costs of Flue Gas Cleaning Technologies, Research Triangle
Park, NC. Publication No. EPA/530-SW-87-021e. June 1987. 121 pp.
2. Reference 1, p. 4-10.
3. Reference 1.
4. Letter from Sedman, C.B., EPA, to Chang, J., Acurex Corporation.
July 14, 1986. EPA guidelines for costing flue gas cleaning technology
for municipal waste combustion.
5. Bowen, M.L. and M.S. Jennings. (Radian Corporation.) Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Industrial Boilers. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/3-82-021. August 1982. p. 2-11.
6. Reference 4.
7. U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 2-6.
8. Memorandum from Aul, E.F., et al., Radian Corporation, to Sedman, C.B.,
EPA. May 16, 1983. 36 pp. Revised Cost Algorithms for Lime Spray
Drying and Dual Alkali FGD Systems.
9. Neveril, R.B. (CARD, Inc). Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication
No. EPA-450/5-80-002. p. 3-12.
10. Reference 7, p. 5-43.
11. Electric Power Research Institute. TAG^-Technical Assessment Guide
(Volume 1: Electricity Supply-1986). Palo Alto, CA. Publication
No. EPRI P-4463-SR. December 1986. p. 3-10.
12. Reference 7, p. 5-39 and 5-43.
13. Reference 7, p. 5-45.
14. Letter and attachment from Fiesinger, T., New York State, Energy Research
and Development Authority, to Johnston, M., EPA. January 27, 1987.
Draft report on the economics of various pollution control alternatives
for refuse-to-energy plants, p. 6-9.
15. Reference 1, p. 4-23.
2.4-10
-------
16. Dickerman, J.C. and K.L. Johnson. (Radian Corporation.) Technology
Assessment Report for Industrial Boiler Applications: Flue Gas
Desulfurization. Prepared for the U.S. Environmental Protection
Agency. Washington, DC. Publication No. EPA-600/7-79-178i.
November 1979. pp. 5-5 and 5-17.
17. Reference 7, pp. 5-46 and 5-52.
18. Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
19. Chemical Marketing Reporter. Volume 233. Number 1. January 4, 1988.
20. Reference 7, p. 2-29.
21. Reference 7, p. 2-31.
22. Reference 5, pp. 2-17 and 2-18.
23. Reference 17.
24. Reference 12.
25. Reference 1.
26. Reference 18.
27. Reference 19.
28. Reference 11, p. B-4.
29. United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. June 1988. p. S-12.
30. Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. DOE/EIA-0035 (87/12).
March 1988. p. 109.
31. Reference 21.
2.4-11
-------
2.5 COMPLIANCE MONITORING
Continuous emission monitoring (CEM) systems are used to determine
compliance with emission limits for MWC facilities. The following sections
describe monitoring systems for opacity, S02, HC1, 02, and CO^. Section 3.1
discusses the types of combustion control monitors required for good
combustion practices.
2.5.1 Overview of Technology
2.5.1.1 Continuous Opacity Monitoring . Stack opacity can be
continuously measured using emission measurement systems based on the
principle of transmissometry. Transmissometry measures the attenuation of
visible light by particulate matter in stack effluent. Light from a lamp
source is projected across the stack to a light sensor. The degree of
attenuation (opacity) reflects the amount of light adsorbed and scattered by
the particulate matter in the effluent.
The EPA regulations (Appendix B of 40 CFR Part 60) require the opacity
monitoring system to operate for a minimum of 168 hours within certain
performance specifications without unscheduled maintenance, repair, or
adjustment. The regulations set forth minimum performance criteria for the
following system parameters: calibration error (<3 percent), 24 hour zero
drift (<2 percent), 24 hour calibration drift (<2 percent), and response time
(10 seconds maximum). During or before installation, it is necessary to
calibrate, zero, and span using calibration filters and to perform all
alignments.
To validate accuracy, as required in 60.13(d), instruments automatically
perform simulated zero and span calibration checks at selectable intervals
(usually daily). It is also usually necessary to have an air purge system to
prevent accumulation of particulate from condensing on the optical surfaces.
Maintenance is typically required on an as-needed basis (usually weekly).
This involves cleaning all filters, checking the optical alignment and the air
purge system, and recalibrating the instrument.
2
2.5.1.2 Continuous SO,, Monitoring . Continuous monitoring of SO,
z i.
emissions is typically accomplished by irradiating a given volume of sample
air by ultraviolet (UV) or infrared (IR) light and measuring either the
2.5-1
-------
energy absorbed or the resulting fluorescence of the S02 molecules.
Commercially available units differ in design and method, but in general it is
necessary to: (1) collimate the light from the original source to provide a
narrow band; (2) prepare the sample for analysis; and (3) increase the
signal-to-noise ratio of the final signal via phase-sensitive detection,
second derivative spectroscopic measurement, or other techniques.
All SO- monitoring systems required under NSPS must have complete zero
and span calibration checks performed daily. If not, a weekly manual check is
recommended. About every month, it is necessary to clean, service, and
readjust the instrument. The actual maintenance schedule needed depends on
the instrument and the site of application. Instruments utilizing filters,
chillers, sample dryers, or support gases typically require more maintenance.
Continuous monitoring systems must be installed at sampling locations
where representative measurements can be made of the total emissions from the
affected facility, or can be corrected so as to be representative. The SCL
monitoring system must be capable of operating for a 168-hour minimum within
certain performance specifications without unscheduled maintenance, repairs or
adjustments. The regulations (Appendix B of 40 CFR Part 60) set forth minimum
performance criteria for the following system parameters: accuracy
(<20 percent) and 24-hour calibration drift (2.5 percent of span). The
calibration drift is determined using calibration gases (i.e., gases of known
concentrations), gas cells, or optical filters. The relative accuracy is
determined by measuring pollution concentrations with EPA reference methods
while concurrently operating the continuous monitoring system.
2.5.1.3 Continuous HC1 Monitorjng. The EPA has not published
performance specifications for HC1 monitors, but is currently evaluating the
reliability, accuracy, and reproducibility of various monitoring systems. The
outcome of this evaluation will determine which monitoring systems will serve
as the basis for any ensuing EPA performance specifications for continuous HC1
monitors.
In brief, four types of extractive monitors are being evaluated and are
available commercially. The first type is a wet chemical batch process. A
sample of the flue gas passes through an automatic bubbler system, and the
HC1-laden liquor is sprayed against a specific ion electrode. The second type
2.5-2
-------
is a nondispersive infrared (NDIR) analyzer. This instrument determines the
HC1 concentration of the sample flue gas by ratioing the peak heights of the
flue gas and reference gas. Both types of monitors are certified for CEM
applications in West Germany.
The third type uses a tape sampler. A sample of gas is exposed to a
chemically impregnated tape. The HC1 in the flue gas reacts with the
chemical on the tape leaving the tape stained. The instrument determines the
HC1 concentration by measuring the reduction in transmissivity of the tape.
The last type of monitoring system is based on continuous spectrophotometry.
A sample of flue gas is contacted with a thiocyanate reagent stream in a
column. The reagent leaving the column, which contains adsorbed HC1, is fed
to the spectrophotometer to obtain an HC1 signal. These two types are not
certified for CEM applications in West Germany.
2.5.1.4 Diluent (Op/CO,, Monitoring). Diluent monitors are an integral
part of an S02 or HC1 continuous monitoring system. Diluent concentrations
(02 or COp on a percent basis) are required to convert actual concentrations
of SOp or HC1 to concentrations at either 7 percent 02 or 12 percent CCL.
Continuous monitoring of 02 is based on the paramagnetic properties of
02 molecules and their response to nonhomogeneous magnetic fields or by oxide
cell differential voltages. Monitoring C02 is accomplished through infrared
absorption methods.
2.5.2 Compliance Monitoring Costs
Table 2.5-1 summarizes the continuous monitoring costs associated with PM
only, acid gas only, and PM and acid gas controls combined. Except for HC1
and operating costs for S02 and 02 monitors, the monitoring costs are the same
as those used by EPA in developing NSPS for both small and industrial steam
o
generation units. Costs for HC1 monitors and operating costs for a combined
8 9
S02/02 monitor are based on recent information. '
The capital costs were updated to December 1987 dollars using the
Chemical Engineering Plant Cost Index for all equipment, while the operating
costs were updated to the same time bases using the Bureau of Labor
Statistics' Producer Price Index for all industrial commodities. An automatic
data reduction system is included in all options shown in Table 2.5-1.
2.5-3
-------
TABLE 2.5-1. CONTINUOUS MONITORING
(December 1987 Dollars)
{JST SUMMARY
Pollutant
PM
Acid Gas
PM + Acid Gas
Capital
Costs
Method ($1,000)
Opacity3 61
SO, (inlet and outlet) 67
HCt (inlet and outlet) 140
02/C02 19
Data Reduction System 31
Total 256
Opacity3 61
S09 (inlet and outlet) 67
HCT (inlet and outlet) 140
00/C00 19
£' c.
Total 286
Operating
Costs .
($l,000/yr)D
8
10
74
15
4
103
8
10
74
15
107
Annual i zed
Costs
($l,000/yr)c
16
19
92
18
8
137
16
19
92
18
145
Includes costs for automatic data reduction system.
Based on 2 certifications/year and maintenance requirements of 0.5 man-hour/
day for opacity and Op/COp monitors and 1 man-hour/day for SOp and HC1
monitors.
°Annualized costs include annual operating costs and capital charges on
equipment and installation costs. Capital charges are based on a 15-year
equipment life at 10 percent interest rate.
2.5-4
-------
REFERENCES
1. Radian Corporation. Industrial Boiler NSPS Issue Papers' Issue Paper
No. 7 Compliance Monitoring Costs. Prepared for the U.S. Environmental
Protection Agency. Research Triangle Park, N.C. September 1980.
pp. A3 and A-4.
2. Reference 1. pp. A-l and A-2.
3. Letter and attachments from Rigo, H.G., Rigo and Rigo Associates,
Incorporated, to Russo, G.P., Connecticut Resources Recovery Authority.
November 18, 1986. p. 1. Draft position papers on technical questions
concerning Connecticut waste-to-energy projects.
4. Reference 3.
5. Reference 3. p. 2.
6. Reference 5.
7. Reference 1. pp. A-3 and A-4.
8. Kiser, J.V., "More on Continuous Emissions Monitoring", Waste Age,
June 1988. p. 124.
9. Memorandum from Peeler, J., Entropy Environmentalists, Inc., to Riley,
G., EPA. June 1, 1988. Review of Draft MWC Compliance Monitoring
Document.
10. Radian Corporation. Industrial Boiler SOp Cost Report. Prepared for the
U.S. Environmental Protection Agency. Research Triangle Park, N.C.
Publication No. EPA-450/3-85-011. November 1984. p. 2-23.
11. Reference 1. p. 3.
2.5-5
-------
3.0 PROCEDURES FOR EXISTING PLANTS
This section presents procedures for estimating costs for existing
municipal waste combustion (MWC) plants. Most procedures presented in this
section rely on those procedures discussed for new plants. However,
additional procedures are developed which are unique to existing plants such
as costs for combustion modifications to the combustors, flue gas cooling
using humidification, and downtime associated with either the installation of
the air pollution control device (APCD) or modifications to the combustor.
This section also provides a methodology to assess the higher costs of
installing APCD's at existing plants, compared to new plants, using retrofit
factors.
Section 3.1 presents procedures for estimating costs for operating the
existing combustor. Procedures for estimating costs of combustion
modifications are presented in Section 3.2. Section 3.3 provides the
procedure for estimating costs for flue gas temperature control using
humidification. Sections 3.4, 3.5, and 3.6 discuss estimation of costs for
particulate matter control, dry sorbent injection, and spray drying,
respectively. Section 3.7 present the methodology to determine retrofit
factors and additional site-specific costs. Downtime costs associated with
the installation of an APCD or modifications to the combustor at an existing
plant are discussed in Section 3.8.
3.1 OPERATION OF THE EXISTING COMBUSTORS
No capital costs are estimated for the combustors and other equipment
associated with the balance of plant, because these costs are sunk and are
independent of the costs for retrofitting additional APCD's. Therefore, only
the operating costs of the combustors and the balance of the plant are
considered. Operating costs procedures for new combustors and the balance of
plant are presented in Section 2.1 and are assumed to be the same for existing
plants. For existing plants, capital recovery costs are not included in the
total operating costs.
3.1-1
-------
3.2 COMBUSTOR MODIFICATIONS
3.2.1 Introduction
This section describes the methodology and assumptions used to estimate
capital and annual costs associated with combustor modifications needed to
1 2
ensure good combustion for MWC's. ' The organization of this chapter is as
follows:
Section 3.2.2 discusses the approach used to estimate capital costs
for each of the combustion modifications, including all assumptions.
An example calculation is provided for each retrofit.
Section 3.2.3 provides a methodology for estimating annual costs for
MWC plants.
The Chemical Engineering Plant Cost Indices are used to convert costs to
December 1987 dollars.
3.2.2 Capital Cost Procedures
Capital cost estimates were calculated for each retrofit component and
expressed as a direct, installed cost, unless otherwise noted. When
uninstalled equipment costs are provided, an installation factor is applied:
Direct Capital Cost (DCC) = 1.45(Equipment Cost)
The installation factor applies to delivered equipment in a solids processing
plant.
Capital costs that may vary based on unit size must be scaled using
factors. For example, the cost of a modification, C, at a unit of a given
size is scaled for a unit of different size by the following equation:
Cj = C2 (TPDj/TPDg)"
where:
C, = scaled capital cost of equipment at unit #1;
C« = capital cost of equipment at unit #2;
3.2-1
-------
TPDj = capacity (tons per day) of unit #1; and
TPD2 = capacity (tons per day) of unit #2.
The exponent n varies according to the retrofit application. It is assumed
that the volumetric heat release (Btu/ft -hr) is constant for similar
combustor types (i.e., mass-burn waterwall, RDF-fired, etc.). Therefore, for a
given design, unit firing capacity (tons per day) scales directly with furnace
volume. Consequently, a change in a given design feature will vary as the
cube root of each resulting change in dimension modifications, and the
exponent is 0.667. In the case of retrofitting a row of overfire air nozzles,
where a one-dimensional change is required (along the width of the combustor),
the exponent is 0.333. Perry's Chemical Engineers' Handbook also applies
A
typical exponents for various pieces of equipment. The exponent values
range from 0.30 to 1.00 depending on the specific equipment. As noted in
Perry's Chemical Engineer's Handbook, use of exponents to estimate costs
results in a slightly higher probable error (10 to 50 percent) than study
estimates (up to 30 percent).
Indirect capital costs (ICC) and contingencies must be applied to the
direct capital costs (DCC) estimates. Indirect capital costs, which include
general facilities and engineering and home office costs, etc., are calculated
as 30 percent of DCC:
ICC = 0.30(DCC).
A single contingency is applied to the DCC:
Contingency = 0.20(DCC).
The 20 percent contingency factor is applied in all cases except when a
retrofit is judged to be especially difficult, such as with stoker (grate)
3.2-2
-------
replacement; a contingency factor of 30 percent is used in this case. The
total plant capital cost (TPC) is calculated as follows:
TPC = DCC + ICC + Contingency.
The following subsections describe the costing methodology for specific
retrofit elements, including:
Stoker rehabilitation,
Refractory-wall furnace reconfiguration,
Fuel feeding modifications,
Underfire air modifications,
Overfire air modifications,
t Monitoring/control modifications,
Auxiliary fuel burner installation, and
Economizer installations for flue gas temperature reduction.
3.2.2.1 Stoker Rehabilitation
This modification includes demolition and replacement of existing stoker,
drives, siftings hopper, siftings conveyor, and structural steel. It is also
assumed that a new stoker is equipped with a ram feeder.
Chesner reports direct capital costs for stoker rehabilitation for
four 250-tpd units to be $4,160,000 (in December 1984 dollars) based
on quotes from two stoker equipment suppliers.
Assume single unit cost for 250-tpd unit is $1,040,000.
Apply CEP index:
12/84 - 324.3
12/87 - 332.5
Unit Cost = 1,040,000 (332.5/324.3) = $1,066,000.
Apply scaling factor and account for number of units:
DCC = 1,066,000 (TPD/250)'677(number of units).
3.2-3
-------
Example: Estimate the direct capital cost of replacing traveling
grates with new reciprocating grates in two 375-tpd units:
DCC = 1,066,000 (375/250)'677 (2) = $2,797,000.
3.2.2.2 Refractory-Wall Furnace Reconfiguration
This modification includes material and labor for reconstructing the
combustion chambers and refractory-lined flues, including structural steel and
refractory brickwork. It is assumed that new overfire air nozzles and
sampling ports are included in the new furnace design.
Chesner reports direct capital costs for furnace reconfiguration for
four 250-tpd units to be $6,072,000 (12/84 dollars).
t Assume single unit cost for a 250-tpd unit is $1,518,000.
Apply CEP index:
12/84 - 324.3
12/87 - 332.5
Unit Cost = $1,518,000(332.5/324.3) = $1,556,000.
t Apply scaling factor:
DCC = l,556,000(TPD/250)'667(number of units).
Example: Estimate the direct capital cost of reconstructing two
120-tpd refractory wall combustors:
DCC = 1,556,000(120/250)>667(2) = $1,903,000.
3.2.2.3 Fuel Feeding Modifications
Ram Feeder - This modification includes material and labor, including the
hydraulic system, for a new ram feeder, plus any necessary modifications to
the feed chute.
Nashville Thermal reports 1979 direct capital (installed) costs of
ram feedecs (one dual ram for each of two 360-tpd units) to be
$360,000.'
Assume that the unit cost is $180,000 for dual rams and $90,000 for
single ram. (Single rams can be used for grates with widths up to
8 feet.)
3.2-4
-------
t Apply CEP Index:
1979 (yearly average) - 247.6
12/87 - 332.5
DCC = 90,000(332.5/247.6} = $121,000 per ram feeder.
Example: Estimate the direct capital cost of retrofitting one ram
on each of two 120-tpd units with 8-foot wide grates:
DCC = $121,000(2) = $242,000.
RDF Metered Feeder - This modification includes installing metered
feeding modules, consisting of two hoppers, one ram feeder, and one
variable-speed drive conveyor per module.
Q
Equipment cost = $150,000 per module.
Apply installation factor to obtain direct capital cost:
DCC = $150,000(1.45) = $217,500 per module.
Example: Estimate the direct cost of retrofitting metered feeding
modules on two 300-tpd RDF-fired facilities. Assume two
distributors per unit and one module per distributor:
DCC = $217,500(2 modules/unit)(2 units) = $870,000.
3.2.2.4 Underfire Air Modifications
Segmented Underfire Air Supplies - This modification includes installing
segmented, separately controllable underfire air plenums.
Laval in estimated the direct capital cost of five new underfire air
plenums to be $153,000 Canadian (2/85) for the Quebec City
Incinerator.
Assume cost for one plenum = $153,000/5 = $30,600.
Convert to U.S. dollars:10 $Canadian = 1.35 ($U.S.)
$U.S. = 30,600/1.35 = $22,700 (2/85 dollars).
Apply CEP Index:
2/85 - 325.4
12/87 - 332.5
3.2-5
-------
(22,700)(332.5/325.4) = 23,200.
Apply scaling factor:
(Quebec City'is a 250-tpd unit.)
DCC = 23,200(TPD/250)'667(h)(number of units),
where h = number of plenums.
Example: Estimate the direct capital cost of installing a single
underfire air plenum to the drying grate section of two 120-tpd
units:
DCC = 23,200(120/25)-667(l)(2) = $28,400.
Underfire Air Preheat - This modification includes a natural gas burner
sized to provide sufficient heat input to raise combustion air temperatures
from 68°F to 300°F.
t Example: Determine the size and direct capital cost of an auxiliary
fuel burner required to preheat underfire air supplied to the drying
grate. Assume that the unit size is 250 tpd.
250 tpd(2000 Ib/ton)(day/24 hr)(hr/60 min) = 347 Ib/min MSW.
Assume that the combustor operates at 150 percent excess air and
that stoichiometric air requirements are 3.25 Ib air/lb waste.
Total air requirements are:
(347 lb/min)(3.25 Ib air/lb waste)(2.5) » 2820 Ib air/min.
Assume that 70 percent of total air is supplied as undergrate air,
and 20 percent of undergrate air is supplied to the drying grate.
(2,820 lb/min)(.70)(.20) = 395 Ib/min at 68°F.
Q - mcp T
where: Q = heat input,
m = 395 Ib/min (mass flowrate),
c = 0.24 Btu/lb F (specific heat of air at standard
P conditions), and
T = 300 - 68 = 232°F.
Q = (395 Ib/m1n)(0.24 Btu/lb°F)(232°F)(60 min/hr) = 1.32 106 Btu/hr
Use a 1.4 x 106 Btu/hr burner.
3.2-6
-------
MITRE reports capitalficosts of burners ranging from capacity of
9.2 x 10° to 1.5 x 10° Btu/hr to be $1200 per burner.
Apply CEP Index:
1981 (yearly average) - 297.0
12/87 - 332.5
1,200 (332.5/297.0) = 1340.
Apply installation factor to obtain direct capital cost:
DCC = 1,340(1.45) = $1,950 per burner.
3.2.2.5 Overfire Air Modifications
Flow modeling/thermal analysis studies are required in most cases prior
to modifying overfire air systems. Overfire air modifications made at
refractory-wall MWC's and tube and tile waterwall MWC's will usually require
only new ducting, dampers, and nozzles. New overf-'-e air rows in
membrane-wall MWC's are assumed to require installation of new waterwall tube
panels.
12
Flow Modeling/Thermal Analysis Studies - These analyses include flow
visualization studies, mixing and dispersion measurements, and flow
distribution studies on a built-to-scale physical model. In addition,
mathematical modeling is included as part of the thermal analysis.
Cold flow modeling - $75,000
Thermal analysis - $50.000
Total $125,000
Ducting and Dampers -
Ducting Capital Costs:13 C = l.l(L)(Q)0<5,
where L = Length (ft) and
Q = 125 percent of the actual flue gas flowrate (acfm).
s Example: Estimate direct capital costs of ductwork and dampers
required to supply overfire air to two rows of nozzles. Assume a
gas flowrate of 21,400 acfm. Assume that the overfire air system
3.2-7
-------
is designed to provide 40 percent of total air flow (8,560 acfm).
At standard conditions, Q = 1.25(8,560) = 10,700 acfm.
Assume ducting length requirements are 100 feet.
C = 1.1(100)(10,700)'5 = $ll,400(equipment cost).
Damper Capital Costs: Chemical Engineering. December 29, 1980
presents cost curves for rectangular dampers.
Estimate costs of a damper to install in ducting. Assume that the
damper is manually controlled and has a 1.5 ft cross-sectional
area. The damper equipment cost is $400 (in December 1977 dollars).
Apply CEP Index:
12/77 - 210.3
12/87 - 332.5
400(332.5/210.3) = $600 per damper (equipment cost).
Total equipment cost = Ducting costs + damper costs
$11,400 + 600 = $12,000.
Apply installation factor:
Total DCC = 1.45(12,000) = $17,400.
Insulation for Ducting - Capital costs for ducting insulation vary from
3.5 to 22 percent of direct capital costs for ducting. Selection of the
appropriate factor is based on flue gas temperature.
Example: Assume that ducting carries preheated air at a temperature
of 300UF and that capital costs for the ducting are $20,000.
Estimate direct capital costs of insulation.
Perry's Chemical Engineers Handbook (Table 25-51) specifies a range
of 3.5 to 6 percent of ducting costs over $17,000. Select 6 percent
as conservative number.
C = 20,000(0.06) = $1,200.
Apply installation factor:
DCC = 1.45(1,200) = $1,740.
3.2-8
-------
Membrane Wall Overfire Air Nozzle -
Laval in reports direct capital costs for one row of nozzles
installed at Quebec City Incinerator to be $40,000 (Canadian
2/85 dollars).10
t Convert to U.S. dollars:
$U.S. = $Canadian/1.35
$U.S. - 40,000/1.35 = 29,600 (2/85 dollars).
Apply CEP Index:
2/85 - 325.4
12/87 - 332.5
DCC = 29,600(332.5/325.4) = $30,200 per row.
Apply scaling factor:
(Quebec City is a 250-tpd unit.)
DCC = 30,200(TPD/250)'333(number of rows)(number of units).
Example: Estimate direct capital costs for two new overfire air
rows per unit for two 1000-tpd combustors:
DCC = 30,200(1000/250)>333(2 rows/unit)(2 units) = $192,000.
3.2.2.6 Combustion Controls and Monitors
Fully Automatic Combustion Controller - This modification includes all
hardware and software required for converting a manual combustion control
system to a fully automatic control (programmable logic controller).
17 18
Direct capital costs for one unit are $200,000. '
Additional units can be installed in control scheme using the same
hardware. Incremental capital costs are restricted to those costs
required for installation. Assume that the direct capital cost of
an automatic controller for more than one combustor is:
DCC = 200,000[1 + 0.45(N - 1)],
where N = number of combustors, and
installation factor = 45 percent of equipment costs.
DCC = 200,000 + 90,000(3 - 1) = $380,000.
3.2-9
-------
Monitors - Display readouts and data loggers are included for each
monitor. Air flow monitors are venturi flow meters with pressure transducers.
1 Q
Direct capital cost of in situ CO/CL monitors - $45,000 .
1 Q
Direct capital cost of in situ CO monitor - $22,000 .
Direct capital cost of air flow pressure monitors for underfire air
plenums and overfire air headers - $1,500 per plenum or row of
overfire air nozzles.
Oxygen Trim Control - This modification includes installation of a
control loop which adjusts underfire air flowrate and/or plenum distribution
based on feedback signals from an 0- analyzer.
Hampton, VA plant manager reports direct capital costs to be $25,000
for two 100-tpd units.
Assume that these costs are fixed, per unit costs:
DCC = $12,500/combustor.
3.2.2.7 Auxiliary Fuel Burner Installation
Gas pipeline costs:
DCC - $50,000 per 1/2 mile22.
Auxiliary gas burners - Capital costs of dual-fuel burner packages,
including blowers, igniters, safety panels, and controls, are
available for the following burner sizes. An installation factor
of 45 percent is applied to obtain direct capital costs.
Burner size (Btu/hr) Equipment Cost Direct Capital Cost
10.5 $16,000 $23,200
30.0 $25,500 $37,000
45.0 $35,000 $50,800
60.0 $42,000 $60,900
Burner equipment costs for sizes other than those provided above
should be extrapolated based on size, and the 45 percent
installation factor should then be applied.
Example: Estimate the capital cost of providing auxiliary fuel to a
facility with three 300-tpd combustors. Assume the nearest source
of gas is one mile away, and each combustor requires two burners,
each rated at 35 x 10 Btu/hr.
3.2-10
-------
DCC of pipeline = $100,000 and
Cost of one 35 x 10 Btu/hr burner = $31,400.
Apply installation factor:
DCC = 1.45(31,400) = $45,500.
Total direct capital costs for burners = $45,500 and
(2 burners/unit) (3 units) = $273,000.
Total direct capital costs = 100,000 + 273,000 = $373,000.
3.2.2.8 Carbon Monoxide Profiling
This activity includes two days labor for three men in the field plus
travel and reporting. Sampling is assumed to include (L, carbon monoxide
(CO), and temperature measurements in a 16-point array under six variable air
distribution settings. Carbon monoxide profiling is required on only one
combustor when multiple units of identical design are in place:
DCC = $10,000 (Reference 24).
3.2.2.9 Economizer for Flue Gas Temperature Control
This modification includes a separate economizer module designed to
:e flue gas temperatures
ducting and a bypass damper.
reduce flue gas temperatures from 600°F to 450°F, along with the addition of
Equipment cost = $45,000 (1986 dollars) for an economize^sized to
handle flue gases from four 75-tpd units (300-tpd total).
Apply CEP Index:
1986 - 318.4
12/87 - 332.5
45,000(332.5/318.4) = $47,000.
Apply installation factor:
DCC = $47,100(1.45) = $68,100.
Apply scaling factor:
DCC = 68,100(TPD/300)'59.
3.2-11
-------
t Example: Estimate the direct capital cost of installing one
economizer for three 50-tpd units:
DCC = 68,100(150/300)'59 = $45,200.
3.2.3 Operating Cost Procedures
Total annual costs include annual operating and maintenance (O&M) costs
and annualized capital costs. Table 3.2-1 presents a summary of inputs used
to estimate annual costs. The costs provided for each plant are incremental
O&M costs. For example, if a plant is equipped with auxiliary fuel burners at
baseline, it is assumed that the fuel is used for start-up and shutdown, and
no incremental O&M cost is applied to the plant for auxiliary fuel
consumption. Plants without auxiliary burners in place will incur additional
costs for fuel consumption. The following examples illustrate the calculation
of annualized costs associated with combustion controls.
Example: A mass-burn refractory-wall MWC'consisting of three
250-tpd combustors must add auxiliary fuel burners and operate the
burners during start-up and shutdown. The facility maintains a five
per week operating schedule. Determine the size of burners required
to provide 60 percent of rated thermal load and estimate natural gas
consumption costs.
Combustor (250 ton/day)(2000 1b/tonH4500 Btu/lb)
zs T r J ^ r -"" Jx ' - T
thermal load (24 hr/day)
= 94 x 106 Btu/hr
Assume for a refractory-wall facility that gas is fired for six
hours during start-up and two hours during shutdown. Assume that
the plant operates 50 weeks/year, and start-up/shutdown occurs
weekly.
Total gas use = (50 wk/yr)(6 + 2 hours)(56 x 106 Btu/hr)(3 units)
= 67.2 x 109 Btu/yr
3.2-12
-------
TABLE 3.2-1. O&M COST INPUTS (DECEMBER 1987 DOLLARS)
Item
Value
Direct Operating Costs
Operating Labor
Supervision
Maintenance Labor
Maintenance Materials
Natural Gi.s
Water
SteaiT;
Solid Was e Disposal
Indirect ( Derating Costs
Overhand
Taxes, Insurance, and
Administrative Charges
Capital Racovery
$12.00/hour
15 percent of operating labor
110 percent of operating labor
(assume 1 hr/shift for
maintenance of controls and
monitors)
100 percent of maintenance labor
$4.50 per 106 Btu
$0.50 per 1000 gallons
$5.30 per 1000 Ib
$25 per ton
60 percent of all labor costs
(operating, supervisory, and
maintenance) plus 60 percent
maintenance materials
4 percent of total plant capital
costs
15 year life and 10 percent
interest rate
CRF =
id + i)n
(1
- 1
where i = interest rate and
n = number of years
CRF =
.1 + fl.n"
(l.l)15 - 1
= .1315
3.2-13
-------
Using c gas cost of $4.50/106 Btu:
C = (67.2 x -Cr Bti!/yr}(4.50/106 Btu) = $302,000/yr
ExiHULLi: Determine the annual costs for a combustion retrofit at the
plant in the above example. Total plant capital costs are assumed to be
$500,OOC. including installation of CO and () monitors.
Direct Costs:
Assume ] hr/shift (3 hr/day) maintenance of monitors and
controls.
Maintenance Materials = (3 hr/day)(5 day/wk)(50 wk/yr)($13.20/hr) =
$10,000/yr,
Maintenance Materials = $10,000/yr (100% of maintenance labor)
Ges costs = $302,GQO/yr, and
Kc additional operating labor is required.
lota' Direct Annual Costs = 10,000 + 10,000 + 302,000 - "322,000.
Indirect Costs:
Overhead = G.6(maintenance labor + maintenance materials;,
Overhead = 0.6(20,000) = $12,000.
Taxes, insurance and Administrative Charges = .04(total plant
capital costs) = .04(500,000) = $20,000.
Annualized capital = .1315(500,000) = $66,000 assuming 15 year
facility life and 10 percent weighted cost of capital.
Total Indirect Annual Cost = Overhead + Taxes, Insurance, and
Administrative + Annualized Capital
= $12,000 + $20,000 + $66,000 = $98,000.
Total annual cost = Direct Cost + Indirect Cost
= $322,000 + $98,000 = $420,000/yr.
3.2-14
-------
REFERENCES
1. Radian Corporation and Energy and Environmental Research Corporation.
Municipal Waste Combustors - Background Information for Proposed
Guidelines for Existing Facilities. Prepared for U. S. Environmental
Protection Agency. Publication No. EPA-450/3-89-27e. August 1989.
2. EER. Municipal Waste Combustion Study: Combustion Control of MSW
Combustors to Minimize Emission of Trace Organics. Prepared for U. S.
Environmental Protection Agency. June 1987. Publication
No. EPA/530-SW-021C.
3. Perry, Robert H. and Don Green. Perry's Chemical Engineers' Handbook
(Sixth Edition). New York: McGraw-Hill, 1984, p. 25-70.
4. Reference 3, p. 25-69.
5. U. S. Environmental Protection Agency. EAB Control Cost Manual (Third
Edition). Research Triangle Park, NC. Publication
No. EPA-450/5-87-001A. February 1987.
6. Chesner Engineering and Black and Veatch Engineers. Energy Recovery from
Existing Municipal Incinerators. New York State Energy Research and
Development Authority (NYSERDA) Report No. 85-14. November 1984.
p. 43-85.
7. Telecon. Conversation between J. Jackson, Nashville Thermal, and
P. Schindler, EER, on April 6, 1988.
8. Telecon. Conversation between Tom Giaier, Detroit Stoker, and
P. Schindler, EER, on May 13, 1988.
9. Lavalin. National Incinerator Testing and Evaluation Program (NITEP):
Quebec Urban Community MSW Incinerator Program Planning. Part 2 Final
Report. Prepared for Environment Canada. April 1985.
10. Wall Street Journal. Foreign Exchange. February 7-27, 1985.
11. MITRE Corporation. The Estimation of Hazardous Waste Incineration Costs.
MTR-82W233. January 1983. p. 55.
12. EER in-house estimate provided by D. Moyeda.
13. U. S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies. Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987.
14. Vatavuk, W. and R. Neveril. "Part IV - Estimating the Size and Cost of
Ductwork." Chemical Engineering, December 29, 1980, p. 73.
15. Reference 1, Table 25-51, p. 25-70.
3.2-15
-------
16. Reference 5, p. 7-3.
17. Reference 5, p. 7-3.
18. Telecon. Conversation between Rob Busby, Bailey Controls, and
P. Schindler, EER, on May 17, 1988.
19. Compilation of vendor quotes obtained by S. Agrawal, EER, for EPA/OSWER.
Documented in letter to Robert Holloway, EPA/OSWER. April 8, 1987.
20. Waukee Flo-meter Price List. Waukee Engineering Company Bulletin No.
1-1274-R8. Milwaukee, WI. April 1, 1987.
21. Information provided to EPA and EER during visit to NASA/Langley Waste to
Steam Plant, Hampton, VA. July 6, 1988.
22. Telefax from Dan Hughes, Florida Gas Transmission Company, to
W.S. Lanier, EER. April 12, 1988.
23. Vendor cost quotes provided to EER by Ed Flammang, North American
Manufacturing Company, Cleveland, OH. August 11, 1988.
24. EER in-house estimate provided by Z. Frompovich.
25. Telecon. Conversation between Col. Frank Rutherford, Tuscaloosa Solid
Waste Authority and P. Schindler, EER. May 26, 1988.
3.2-16
-------
3.3 HUMIDIFICATION
3.3.1 Overview of Technology
Humidification is used to cool the flue gas entering the particulate
matter (PM) control device. Humidification can be used separately or in
combination with dry sorbent injection. The primary objective of cooling
is to reduce the temperature of the flue gas entering the PM control device
to below that at which post-combustion formation of dioxin is suspected to
occur (approximately 450°F).
The quantity of water required is a function of the temperature,
flowrate, and moisture content of the flue gas at the inlet to the
humidification chamber and the temperature reduction required.
Qw = (T.-T0) * Qs * (1-WTR/100)/940 (1)
where: Q = water required for flue gas coolirj, lb/hr;
T, = inlet flue gas temperature, F;
T = outlet flue gas temperature, °F;
Q = flue gas flowrate, scfm; and
WTR = moisture content of the inlet flue gas, volume percent.
Flue gas temperatures at the combustor exit for refractory-wall
combustors generally ranged from 1,400 to 1,600°F; for waterwall
combustors, temperatures ranged from 400 to 600°F.
For units already using quench towers for flue gas cooling (primarily
refractory-wall systems without heat recovery), the water feed rate is
increased to achieve the additional cooling. For units without an existing
flue gas cooling system, a humidification chamber is installed. The
humidification chamber diameter is sized for a flue gas velocity of
2
10 feet/second and a chamber length-to-diameter (L/D) ratio of 3 to 1. To
minimize PM fallout and impingement of wetted solids on chamber walls, no
baffles or other internals are used. Pressure nozzles are used for water
atomization.
A secondary effect of cooling the flue gas entering the PM control
device is a reduction in flue gas volume (i.e., acfm) and a corresponding
3.3-1
-------
increase in the specific collection area (SCA) thereby enhancing the PM
collection efficiency of the ESP. However, because MWC ESP's operate at
temperatures above the temperature of maximum particle resistivity (300 to
400°F for most fly ashes), decreasing flue gas temperature may in some
instances increase fly ash resistivity enough to create ESP back corona
problems and impair PM collection efficiency. Because of the current lack
of information on resistivity-temperature relationships for MWC fly ash,
this analysis assumes that humidification does not alter particulate
resistivity enough to cause ESP operating problems. As a result, the
impact of humidification on ESP performance is estimated based solely on
the change in SCA due to flue gas volume reduction.
3.3.2 Capital Cost Procedures
Capital costs are estimated for existing facilities without an
existing flue gas cooling system. Direct capital costs include the
humidification (evaporative cooling) chamber including the vessel and
supports, water spray system and controls, and duct modifications. Direct
equipment cost for the humidification chamber are based on the flue gas
3
flowrate using the following equation:
Equipment Costs ($) = 0.372 * Q + 67,980 (2)
where: Q is 125 percent of the actual inlet flue gas flowrate (acfm)
to accommodate variations in waste composition and operating
4
conditions.
The costs estimated by equation 2 are in December 1987 dollars.
Originally, the costs were in December 1977 dollars and were adjusted to
December 1987 dollars using the Chemical Engineering Plant Cost Index for
all equipment. The equipment costs are then adjusted for retrofit
difficulty based on the procedures described in Section 3.7.1.
Costs for instrumentation, taxes, freight, and installation are
estimated using indirect cost factors for venturi scrubbers. The
3.3-2
-------
resultant procedure for estimating capital cost is summarized in
Table 3.3-1.
3.3.3 Operating Cost Procedures
Table 3.3-2 presents procedures for estimating operating and
maintenance (O&M) costs for the humidification chamber. Because of the
simple design and operating requirements of the system, O&M labor and
maintenance materials are assumed to be at the low end of those presented
in Reference 6 (i.e., using the wet scrubber labor and materials
requirements). Other O&M costs include water and the electricity used by
the pumps. All costs are based on December 1987 dollars. An operating
labor wage of the $12/hr was used. This wage was the average of the labor
wages reported by both the Department of Commerce Survey of Current
Business for private nonagricultural payrolls and EPRI's
7 8
Technical Assessment Guide for utility power plants. The labor wage
reported by EPRI in January 1985 dollars was updated to December 1987
dollars using the Bureau of Labor Statistics' Producer Price Cost Index for
all industrial commodities, prior to averaging. An electricity cost of
$0.046/kWh was obtained from the Energy Information Administration
Q
Monthly Energy Review. Equipment life is assumed to be 15 years.
3.3-3
-------
TABLE 3.3-1 CAPITAL COST PROCEDURES FOR HUMIDIFICATION10'11
Equipment Costs (December 1987 dollars)
1. Humidification Chamber and Pumps:3
Cost, $ = 0.372 * Q + 67,980
2. Ductwork
Cost, $ = 0.981 * L * Q°'5
Retrofit Purchase Equipment Costs = 1.18 * Equipment Costs * Retrofit
Factor (from Section 3.7)
Installation Direct Costs = 0.56 * Purchased Cost
Indirect Costs = 0.35 * Purchased Cost
Total Capital
Costs = Purchased Equipment Costs + Installation Direct Costs +
Indirect Costs
= 1.91 * Purchased Costs
aQ = 125 percent of the actual flue gas flowrate, acfm
L = Duct length, feet.
Includes a contingency of 3 percent of the purchased costs.
3.3-4
-------
TABLE 3.3-2 OPERATING AND MAINTENANCE COSTS FOR HUMIDIFICATION
Operating Labor:
Supervision:
Maintenance Labor:
Maintenance
Materials:
Water:3
.a,b
Electricity:
Overhead:
Taxes, Insurance,
and Administrative
Charges:
Capital Recovery:
0.5 man-hours/shift; wages of $12/hr
15% of operating labor costs
0.5 man-hours/shift
10% wage premium over operating labor wages
1% of total capital investment
0.00012 * Q * (hours of operation) *
(water costs, $/1000 gal)
cost of $0.50/1000 gal
1.587 x 10"4 * Q * (hours of operation) *
(electricity costs, $/kWh)
cost of $0.046/kWh
60% of the sum of all labor costs (operating,
supervisory, and maintenance) and maintenance
materials
4% of the total capital costs
15-year life and 10% interest rate
References
6, 8
12
12
13
14
15
15
15
Q = water injection rate, Ib/hr, (from Equation 1 in Section 3.3.1).
w
'Assume 20 feet of pumping height, 100 psi discharge pressure, and
10 ft/sec velocity in pipe.
3.3-5
-------
REFERENCES
1. PEI Associates, Inc. User's Manual for the Integrated Air Pollution
Control System Cost and Performance Program (Version 2). Prepared for
the U. S. Environmental Protection Agency. Research Triangle Park,
NC. Contract No. 68-02-3995. April 1985. p. 4-16.
2. Neveril, R.S. (GARD Inc.) Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for U. S. Environmental
Protection Agency. EPA-450/5-80-002. December 1978. p. 4-40.
3. Reference 2. p. 4-41.
4. Letter from Sedman, C.B., EPA, to Chang, J. Acurex Corporation. July
14, 1986. EPA guidelines for costing flue gas cleaning technologies
for municipal waste combustor.
5. Reference 2. p. 3-11.
6. Reference 2. p. 3-14.
7. United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. Oui\2 1988. p. S-12.
8. Electric Power Research Institute. TAG - Technical Assessment Guide
(Volume 1: Electricity Supply - 1986). Palo Alto, CA. Publication
No. EPRI P-4463-SR. December 1986. p. B-4.
9. Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. DOE/EIA-0035 (87/12).
March 1988. p. 109.
10. Reference 2. p. 4-41.
11. U. S. Environmental Protection Agency. Municipal Waste Combustion
Study: Costs of Flue Gas Cleaning Technologies. Research Triangle
Park, NC. Publication No. EPA/530-SW87-021e. June 1987.
12. Reference 2. p. 3-12.
13. Reference 5. p. 4-23.
14. Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E.,
EPA. October 19, 1984. Development cost for wet control for
stationary gas turbines.
15. U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 2-31.
3.3-6
-------
3.4 PARTICULATE MATTER CONTROL RETROFIT
This section discusses three electrostatic precipitator (ESP) control
alternatives for reducing PM emissions from existing MWC facilities. These
alternatives are: installation of a new ESP (discussed in Section 3.4.1),
increasing the plate area of an existing ESP (Section 3.4.2), and rebuilding
an existing ESP to improve performance (Section 3.4.3).
3.4.1 Installation of a New ESP
The procedures for estimating ESP capital costs for new plants (described
in Section 2.2.2) are applicable to the procedures used for existing plants.
The existing plant cost procedures include site-specific retrofit factor and
scope adders used to estimate the cost of demolition, replacement, relocation
of existing equipment, new ducting, and stacks, if needed.
3.4.1.1 Capital Cost Procedures. The procedures developed for
estimating the capital costs of ESP's for new plants (described in
Section 2.2.4.1) are used to estimate the direct costs of major equipment,
including the fans and ash handling. Estimated duct lengths are required to
calculate duct costs for connecting the ESP to an existing plant. The
estimated direct costs of new equipment and ducts are then multiplied by
site-specific retrofit factors determined by the procedures described in
Section 3.7.1.
Total direct capital costs for retrofit are calculated as the sum of the
adjusted equipment costs plus any scope adders. Scope adders are additional
significant costs for items, such as chimneys or demolition, that are required
for an accurate estimate of the ESP retrofit. Determination of scope adder
costs is described in Section 3.7.2.
After the total direct capital costs have been estimated, the remainder
of the capital cost procedure (for indirect and contingencies costs) is the
same as for ESP's installed in new plants as described in Section 2.2.4.1.
3.4.1.2 Operating Cost Procedures. Operating costs for retrofit ESP's
are estimated using the same procedures as those for new plants discussed in
Section 2.2.4.2. The costs of taxes, insurance, and administrative charges
are estimated as a fraction of the total retrofit capital costs. The proposed
3.4-1
-------
procedures also allow operating hours to be varied to reflect model plant
specifications.
3.4.2 Increase in ESP Plate Area
Additional ESP plate area is installed when the existing ESP is too small
to achieve the desired PM control. Addition of plate area is accomplished by
installing a new ESP in series with the existing ESP. This approach results
in minimum facility downtime and will simplify cost estimation relative to the
addition of plate area to the existing ESP.
3.4.2.1 Capital Cost Procedures. The procedures developed for
estimating the capital costs of ESP's for new plants (described in
Section 2.2.4.1) are used to estimate the direct costs of installing
additional ESP plate area. First, the required particulate removal efficiency
is calculated based on the PM emission limit desired and the inlet PM
concentration. This removal efficiency is then used to calculate the required
specific collection area (SCA) using either equation 2 or 4 presented in
Section 2.2.4.1. Next, the SCA of the existing ESP is subtracted from the
calculated SCA to determine the additional SCA required. The additional SCA
required is used to calculate the additional plant area requirement and the
direct costs of the second ESP using equations 1 or 3 in Section 2.2.4.1. The
required duct length is estimated for each model plant based on the equipment
configuration for that plant. The estimated direct costs of the new ESP and
ducts are then multiplied by a site-specific retrofit factor determined
according to the guidelines discussed in Section 3.7.1. Appropriate scope
adders are costed based on procedures described in Section 3.7.2.
After the total direct capital costs have been estimated, the remainder
of the capital cost procedure (for indirect and contingency costs) are the
same as for ESP's installed in new plants presented in Section 2.2.4.1.
3.4.2.2 Operating Cost Procedures. Operating costs for the second ESP
are estimated using procedures for new plants discussed in Section 2.2.4.2.
Only those costs associated with the second ESP are included. Because
operating, supervision, and maintenance labor are available for the existing
ESP, it is assumed that no additional labor requirements are necessary to
operate and maintain the second ESP.
3.4-2
-------
3.4.3 ESP Rebuild
An ESP rebuild can be used with existing ESP's with PM removal
efficiencies lower than those predicted in either Figures 2.2-2 or 2.2-4 for a
new ESP with equivalent SCA. Rebuild of an ESP includes replacing worn or
damaged internal components (plates, frame, and electrodes), upgrading
controls and electrical systems for more effective energization, and flow
modeling to evaluate gas distribution. The ESP rebuild does not include
making design changes to the existing ESP, such as changes to the
plate-electrode geometry or addition of collection area.
3.4.3.1 Capital Cost Procedures. The procedures developed for
estimating the capital costs of ESP's for new plants (described in
Section 2.3.4.1) are used to estimate the direct costs of ESP rebuild. Based
on contacts with ESP vendors, a typical cost for rebuilding an existing ESP is
roughly 30 percent of the total capital cost of a new ESP of equivalent size,
i o
but can be as high as 50 percent of the new ESP cost. '
The recommended procedure for estimating the total capital costs for ESP
rebuild is to use 30 percent of the cost for a new ESP. This factor assumes
equipment costs of 42 percent of the cost of a new ESP plus installation and
indirect equipment cost multipliers of 0.33 and 0.27, respectively. These
indirect cost multipliers are lower than those used for new ESP's because:
(1) new foundations, supports, piping, insulation, and painting are not
required and (2) engineering and erection expenses are reduced relative to the
costs for a new ESP. Site-specific retrofit factors are not used since the
rebuild is performed within the existing ESP.
3.4.3.2 Operating Cost Procedures. The operating and maintenance costs
after ESP rebuild are the same as before the rebuild with the exception of
additional waste removal. The additional waste removal requirements are based
on the incremental reduction of PM achieved after the ESP is rebuilt.
3.4-3
-------
REFERENCES
1. Telecon. Lamb, Linda, Radian Corporation, with Gawrelick, Gary,
Research-Cottrell. February 13, 1988. Rebuild Costs for ESP's.
2. Telecon. Martinez, John, Radian Corporation, with Gawrelick, Gary,
Research-Cnttrell. April 11, 1988. Additional cost information on ESP
rebuilds.
3. Turner J.H. et al. Electrostatic Precipitators (draft section). In:
EAB Control Cost Manual, U. S. Environmental Protection Agency. Research
Triangle Park, NC. Publication No. EPA-450/5-87-001A. February 1987.
p. 6-56.
3.4-4
-------
3.5 DRY SORBENT INJECTION RETROFIT
3.5.1 Overview of Technology
Cost procedures are presented in Section 2.3 for the injection of dry
sorbent into the furnace or duct of a new plant. The major distinctions
between the design of sorbent injection systems for most existing facilities
versus new facilities are (1) the reuse of an existing ESP rather than a new
fabric filter for PM control, and (2) the higher capital costs to reflect the
difficulty of a site-specific retrofit. For existing facilities not equipped
with an ESP, new fabric filters can be used.
Another retrofit option for duct sorbent injection at existing facilities
is to , ,-.jcct dry sorbent following an existing spray humidification chamber.
In this j^ion, the flue gas leaving the combustor is cooled by humidification
to 350C :,..fore it enters the ESP, or to 300°F in the case of a fabric filter.
Dry sor :.-., -'i, is injected after the gas is humiinfied to minimize cake buildup
in the cruet.
3,5.2 '.aoltal Cost Procedures
Tba procedures developed for estimating the capital costs of dry sorbent
injection for new plants are used to estimate the direct capital cost of major
equipment and ductwork for retrofit installations. Because the major
equipment components of dry sorbent injection (reagent storage and handling
system) can be located in remote areas, difficulties associated with spacial
constraints (i.e., access/congestion) and underground obstructions is
generally minimal. Based on the application of dry sorbent injection to
coal-fired utility boilers, the direct capital cost for new plants is
increased by 10 percent to account for the estimated costs of modifying an
existing duct in the case of duct sorbent injection, modifying an existing
overfire air system in the case of furnace sorbent injection, or modifying an
existing humidification chamber.
The total direct capital costs for retrofit also include the cost of any
scope adders such as additional ducting or existing equipment demolition that
is required to accurately estimate dry sorbent injection retrofit costs at a
specific site. Additional ductwork can be estimated using cost equations in
Section 2.3. Scope adders are defined in Section 3.7.2. Determination of
scope adder costs is also described in Section 3.7.2.
3.5-1
-------
After the total direct capital costs have been estimated, the remainder
of the capital cost procedure for estimating indirect capital costs and
contingencies is the same as for dry sorbent injection at a new plant
presented in Section 2.3.4.1.
3.5.3 Operating Cost Procedures
Operating costs for retrofit dry sorbent injection installations are
estimated using the same procedures discussed in Section 2.3.4.2 for new
plants. Operating costs for existing plants are higher than for new plants of
equivalent sizes because the maintenance expenses are affected by access and
congestion difficulties. This increased cost is handled by calculating
maintenance materials as a percentage of the total capital investment. The
costs of taxes, insurance, and administrative charges are based on the total
retrofit capital costs.
3.5-2
-------
REFERENCE
Radian Corporation. Retrofit Costs for SO, and NO Control Options at 50
Coal-Fired Plants (Draft Report). Preparea for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Contract No. 68-02-4286.
February 1988.
3.5-3
-------
3.6 SPRAY DRYER RETROFIT
3.6.1 Overview of Technology
Spray dryers (SD) combined with fabric filters (FF) can be retrofitted at
existing plants where very high levels of CDD/CDF and acid gas control are
required. Key technology considerations include reconfiguration of the
ducting between the combustor outlet and stack, and the availability of space
for installing sorbent handling equipment, SD vessel, FF, and ash disposal
facilities.
Stand-alone SD costs were developed for this study to evaluate the costs
of retrofitting a new SD in front of an existing particulate control device.
Cost procedures presented in Sections 3.6.2 and 3.6.3 can be applied to
estimate SD retrofit costs at existing plants. In most cases, the existing
particulate control device is an ESP. For cases where it is determined that
additional plate area is required to handle the increase in fly ash loading to
the ESP caused by the SD, costing procedures presented in Sections 2.2 and
3.4.2 for modifying ESP's to add plate area should be used.
3.6.2 Capital Cost Procedures
The procedures developed for estimating the capital costs of SD/FF
systems for new plants (described in Section 2.4.4) can be used to estimate
the direct capital cost of major equipment and ducts for retrofit
installations. Required duct lengths are used to estimate the duct costs for
connecting the SD system to an existing plant. The estimated direct costs of
new equipment and ducts are then multiplied by site-specific retrofit factors
determined by the procedures in Section 3.7.1.
Capital costs for stand-alone SD systems are based on quotes obtained
from three manufacturers. " These quotes, shown in Table 3.6-1, exclude the
costs of any particulate control device. As discussed in Section 2.4, direct
capital costs were correlated with flue gas flowrates. The direct capital
cost equation in Table 3.6-2 for a single SD unit was developed from these
2
quotes. The correlation coefficient (R ) for this equation is 0.81.
Figure 3.6-1 shows the relationship of both the predicted SD direct capital
costs and the vendor costs with flue gas flowrate. The accuracy of the
3.6-1
-------
TABLE 3.6-1. VENDOR QUOTES FOR SPRAY DRYER DIRECT CAPITAL COSTS
(in 1000$ August 1988)
Vendor
A
A
A
A
A
B
B
B
B
B
C
C
C
C
C
aMB/WW
MB/RC
RDF
btpd =
Combustor
Type
MB/WW
MB/RC
RDF
MB/WW
RDF
MB/WW
MB/RC
RDF
MB/WW
RDF
MB/WW
MB/RC
RDF
MB/WW
RDF
= mass burn/waterwall
Combustor.
Size, tpd°
100
250
300
750
1,000
100
250
300
750
500
100
250
300
750
500
Flue gas
Flowrate,
acfm
24,000
49,000
82,800
210,000
393,000
24,000
49,000
82,800
210,000
196,500
24,000
49,000
41,400
210,000
196,500
Direct
Capital Costs
890
1,225
1,575
2,725
3,930
850
1,400
900
2,500
2,150
1,300
2,170
1,650
3,430
2,560
= mass burn/rotary combustor
= refuse-derived fuel
tons burned per day
3.6-2
-------
TABLE 3.6-2. CAPITAL COST PROCEDURES FOR SPRAY DRYERS'
Total Direct Costs (December 1987 dollars)
Single SD Unit only: Costs, 103 $ - 8.428 (Q)0'460 * N * RF
Ductwork5: Costs, 103 $ = [1.3868 * L * Q°'5]/l,000 * N * RF
Fan5: Costs, 103 $ = [1.8754 * Q°'96]/l,000 * N * RF
Multiple Units: Multiply the above costs by the number of units
Indirect Costs = 33% of total direct costs
Contingency = 20% of sum of direct and indirect costs
Total Capital Costs = Total Direct Costs + Indirect Costs + Contingency Costs
Q = 125 percent of the actual flue gas flowrate, acfm
L = Duct length, feet
N = Number of units
RF = Retrofit factor, dimensionless
Assumes that the total installed costs are 133 percent of the direct capital
costs.
3.6-3
-------
>
.M
»
O
u
o T?
o
«/»
0)
o
o
0)
1
I 1
*
K) KJ KJ KJ
1-8
003 *» t.
- O « < .,- a>
M 3* a- h
00 V
0> -M
i/l O
(V
5 si
O
O §
V)
0 -0
o e
UJ
i-i
l« 3
°tl
£ B
o a
S§
» o
*J V.
<« <*-
'v
s.
o
CO
-------
±30 percent. It should be noted that the costs shown in this figure are
reported in August 1988 dollars and that the flue gas flowrate is the actual
flue gas flowrate. The SD direct capital cost equation in Table 3.6-2 was
derived by de-escalating the predicted cost curve shown in Figure 3.6-1 to
December 1987 dollars using the Chemical Engineering Plant Index and by
correcting for 125 percent of the actual flue gas flowrate. Comparing the
direct capital coits for SD with those for SD/FF estimated using procedures in
Section 2.4, the SD costs are generally between 50 and 60 percent of the costs
for a SD/FF for flue gas flowrates ranging from 25,000 to 400,000 acfm. These
flue gas flowrates covor the range of flowrates from small modular units to
large RDF units. For ESP reuse, the costs of additional plate area, if any,
estimated from procedures presented in Section 3.4.2 should be included.
The required duct length is estimated for each model plant based on the
proposed air pollution control device (APCD) equipment configuration for that
plant. The estimated direct costs of new equipment and ductwork are then
multiplied by site-specific retrofit factors described in Section 3.7.1.
The total direct capital cost for retrofit is calculated as the sum of
the adjusted new equipment costs plus any scope adders. Scope adders
incorporate additional capital costs for items such as chimneys or demolition
that are required for SD retrofit. Determination of scope adder costs is
described in Section 3.7.2.
After the total direct capital cost has been estimated, the remainder of
the capital costing procedure for indirect capital costs and contingencies
is the same as for SD/FF installation at a new plant (see Section 2.4.2).
3.6.3 Operating Cost Procedures.
Operating costs for retrofit SD/FF installations are estimated using the
same procedures as for new plants in Section 2.4.3. Table 3.6-3 presents the
annual operating cost procedures for stand-alone SD's. Annual operating costs
for the SD system alone exclude costs associated with the PM control device,
such as bag replacement, compressed air, and solid waste costs. Operating
labor, supervision, and maintenance labor costs for the SD alone are half
those for a similar SD/FF system. Electricity costs for the I.D. fan are
based on 5.5 inches of water pressure drop for an SD compared with
3.6-5
-------
TABLE 3.6-3. ANNUAL OPERATING COSTS PROCEDURES FOR STAND-ALONE
SPRAY DRYERS FOR NEW MWC's3
Operating Labor:
Supervision:
Maintenance:
Labor:
Materials:
Electricity:
Fan:
2 man-hours/shift; $12/man-hour
15% of operating labor costs
1 man-hour/shift; 10% wage rate
premium over operating labor wage
2% of direct capital costs
Cost Rate = $0.046/kwh
5.5 inches of water pressure drop
Reference
4, 5
6
5
7
4, 5
Atomizer:
Pump:
Water:
L i me :
Overhead:
6kW/l,000 Ibs/hr of slurry feed + 15kW
20 feet of pumping height
10 psi discharge pressure
10 ft/sec velocity in pipe
Calculate water flowrate reguired for
cooling the flue gas to 300 F; water
cost - $0.50/1000 gal
Based on lime feed rate calculated by
assuming a stoichiometric ratio of
1.5:1; lime cost = $70/ton
60% of the sum of all labor costs
(operating, supervisory, and maintenance)
plus materials
Taxes, Insurance, and
Administrative Charges: 4% of total capital costs
Capital Recovery:
15-year life and 10% interest rate
8
9
10
11
12
12
13
All costs are in December 1987 dollars.
3.6-6
-------
12.5 inches of water pressure drop for a SD/FF. Operating costs for ESP reuse
are estimated from procedures presented in Section 3.4.2 for additional ESP
plate area.
Operating costs for existing plants are higher than for new plants of
equivalent size, since maintenance expenses will be affected by access and
congestion difficulties. This increased cost is handled by calculating
maintenance materials as a percentage of the total capital investment. The
costs of taxes, insurance, and administrative charges are based on total
retrofit capital costs. These procedures also allow operating hours to be
varied to meet model plant specifications.
3.6-7
-------
RFFERENCES
1. Letter and attachment from Weaver, E.H., Belco Pollution Control
Corporation, to Johnston, M.G., EPA. September 28, 1988. Retrofitting
of spray dryers to existing MWC's.
2. Letter and attachment from Buschmann, J.C., Flakt Incorporated, to
Johnston, M.G., EPA. October 27, 1988. Costs for spray dryers applied
to MWC's.
3. Letter and attachment from Murphy, J.L., Wheelabrator Air Pollution
Control, to Johnston, M.G., EPA. November 18, 1988. Costs for spray
dryers applied to MWC's.
4. Memorandum from Aul, E.F., et al., Radian Corporation, to Sedman, C.B.,
EPA. May 16, 1983. 36 p. Revised Cost Algorithms for Lime Spray Drying
and Dual Alkali FGD Systems.
5. Neveril, R.B. (CARD, Inc.). Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/5-80-002. December 1978. p. 3-12.
6. U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 2-6.
7. Electric Power Research Institute. TAG^-Technical Assessment Guide
(Volume 1: Electricity Supply-1986). Palo Alto, CA. Publication No.
EPRI P-4463-SR. December 1986. P. 3-10.
8. Reference 1, p. 4-23.
9. Dickerman, J.C. and K.L. Johnson. (Radian Corporation.) Technology
Assessment Report for Industrial Boiler Applications: Flue Gas
Desulfurization. Prepared for the U. S. Environmental Protection Agency.
Washington, DC. Publication No. EPA-600/7-79-178i. November 1979.
pp. 5-5 and 5-17.
10. Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
11. Chemical Marketing Reporter. Volume 233. Number 1. January 4, 1988.
12. Reference 7, p. 2-29.
3.6-8
-------
13. Bowen, M.L. and M.S. Jennings. (Radian Corporation). Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Industrial Boilers. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/3-82-021. August 1982. pp. 2-17 and 2-18.
3.6-9
-------
3.7 DETERMINATION OF RETROFIT F*^TORS AND SCOPE ADDER COSTS
The costs of air pollution control device (APCD) installation at an
existing plant are greater than at a new facility due to higher construction
costs imposed by site access and congestion, longer duct runs caused by space
limitations, and the need to demolish and relocate some existing facilities.
Procedures for estimating these costs at MWC's were adapted from procedures
developed for the Electric Power Research Institute (EPRI) for retrofitting
APCD's at existing electric generating plants. These additional costs are
divided into two types of adjustments: retrofit multipliers (discussed in
Section 3,7.1) and scope adders (discussed in Section 3.7.2).
3.7.1 Retrofit Factors
Site-specific retrofit factors can be estimated based on access and
congestion problems associated with retrofitting APCD's at existing plants.
Depending on the level of accessibility and congestion, one of four factors
(ranging from 1.02 to 1.42) is recommended based on the guidelines shown in
Table 3.7-1. The total direct costs of new APCD equipment excluding ductwork
2
are multiplied by this retrofit factor to estimate retrofit costs.
3.7.2 Scope Adders
Scope adders are site-specific costs for additional ducting, chimneys,
demolition, or any other major items that can be included in retrofit cost
estimates in addition to the main control system equipment. Estimating
procedures for some common scope adders are described here.
3.7.2.1 Ducting. Direct capital costs for ducts are estimated using the
equation described in Section 2.2 for new plants. The duct costs are then
multiplied by the retrofit factor from Section 3.7.1 to estimate the direct
capital cost of ducts for existing plants. Depending on chimney and APCD
tie-in difficulties at the model plant, the ductwork retrofit factor may be
different than that chosen for the APCD.
3.7.2.2 Stacks. The installed capital cost of stacks is estimated from
equations developed for industrial boilers. Total direct and indirect
capital cost data from one manufacturer were correlated into separate
equations for lined and unlined stacks, and for stacks larger and smaller than
3.7-1
-------
TABLE 3.7-1. SITE ACCESS AND CONGESTION FACTORS FOR
RETROFITTING APCD EQUIPMENT AT EXISTING PLANTS3
Retrofit
factor
Congestion
level
Guidelines for selecting retrofit factor
1.02
Base Case
1.08
Low
1.25
Medium
1.42
High
Interferences similar to a new plant with adequate
crew work space. Free access for cranes. Area
around combustor and stack adequate for standard
layout of equipment.
Some aboveground interferences and work space
limitations. Access for cranes limited to two
sides. Equipment cannot be laid out in standard
design. Some equipment must be elevated or
located remotely.
Limited space. Interference with existing
structures or equipment which cannot be relocated.
Special designs are necessary. Crane access
limited to one side. Majority of equipment
elevated or remotely located.
Severely limited space and access. Crowded
working conditions. Access for cranes blocked
from all sides.
Reference 4.
3.7-2
-------
5 feet in diameter (stacks larger tnan 5 feet in diameter and 100 feet tall
are normally tapered). For a lined acid-resistant stack, the equations for
direct and indirect capital cost, updated to December 1987 dollars, are:
Cost, 103 $ = [26.2 + 0.089 x (H) x (1 + 4.14 D)] for D > 5 ft and
Cost, 103 $ = [26.2 + 0.080 x (H) x (1 + 4.33 D)] for D < 5 ft
For an unlined stack, the equations are:
Cost, 103 $ - [26.2 + 0.0625 x (H) x (1 + 2.59 D)] for D > 5 ft and
Cost, 103 $ = [26.2 + 0.087 x (H) x (1 + 2.20 D)] for D < 5 ft,
where
H = stack height, ft and
D = stack diameter, ft.
To estimate the total capital costs, the direct and indirect costs are
increased by 20 percent to account for contingency.
3.7.2.3 Demolition and Replacement. Costs for demolition of existing
buildings required for installation of new APCD equipment are estimated
according to EPRI guidelines. In general, demolition cost is estimated by
multiplying the amount of material to be demolished or moved (i.e., square
feet of building space) by an appropriate cost factor in Reference 5. These
estimates are made on a plant-specific basis as needed. Costs for demolition
or replacement of existing equipment such as ductwork, fans, and ESP's are
assumed to be the same as the costs for installing the same equipment.
3.7-3
-------
REFERENCES
1. Stearns Catalytic Corporation. Retrofit FGD Cost-Estimating Guidelines.
Prepared for Electric Power Research Institute. Palo Alto, CA.
Publication No. CS-3696. October 1984.
2. Reference 1. pp. 4-1 to 4-3.
3. Bowen, M.L. and M.S. Jennings (Radian Corporation). Costs of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxides Controls on Fossil
Fuel-Fired Industrial Boilers. Prepared For the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication
No. EPA-450/3-82-021. August 1982. p. 2-11.
4. Reference 1. p. 5-4.
5. Reference 1. pp. 4-9 to 4-14.
3.7-4
-------
3.8 DOWNTIME COSTS FOR RETROFIT MODIFICATIONS
In many situations, the retrofit equipment cannot be installed during a
normally scheduled maintenance shutdown and thus will result in additional
downtime and loss of MWC revenues during retrofit. The loss of revenue is
mainly from: (1) a loss of steam and/or electrical sales and (2) a loss of
tipping fees from receiving MSW. It is assumed that the work force at the
facility would be productive during the downtime period and that the cost of
idle workers can be ignored.
To estimate the downtime costs due to loss of revenue, the length of
downtime required to install the APCD must be estimated. Table 3.8-1 presents
ranges of unit downtimes required to apply combustion control and install
various APCD's on existing MWC facilities. Once the downtime period is
estimated, Sections 3.8.1 and 3.8.2 present the procedures used to estimate
costs for the loss of steam and electrical sales and the loss of tipping fees,
respectively. Costs attributed to the loss of revenue are treated as a
one-time cost that is annualized over the useful life of the APCD.
3.8.1 Procedures to Estimate Loss of Steam and Electricity Sales
3.8.1.1 Loss of Steam Sales. To estimate the costs of loss of steam
during downtime, the amount of steam that would have been generated during the
downtime period is multiplied by a sales price for steam (typically in dollars
per 1,000 Ib of steam). A typical steam price in December 1987 dollars is
$5.50/1,000 Ib of steam. For example, the lost revenues from steam sales for
a facility normally producing 10,000 Ib/hr of steam are $1,320 per day (i.e.,
$5.50/1,000 Ibs steam times 10,000 Ibs steam/hr times 24 hours).
3.8.1.2 Loss of Electricity Sales. The cost of lost electricity sales
is estimated by multiplying the amount of lost electricity generation by the
electricity price. The electricity price is assumed to be the same as the
electrical cost rate used in this report to estimate APCD electricity costs
($0.046/kWh in December 1987 dollars). Applying this procedure, the cost of
lost electricity sales for a facility with a 1,000 kW capacity turbine is
$1,100 per day (i.e., $0.046/kWh times 1,000 kW times 24 hours).
3.8-1
-------
TABLE 3.8-1. DOWNTIME REQUIREMENTS IN MONTHS4
Combustor
downtime
(months)
Combustion Modifications 0.25-4
ESP-Rebuild 1-2
ESP-Add plate area 0.5-lb
Retrofit Spray Dryer 1
Retrofit Sorbent Injection 0.5-lb
Humidification 0.25-1
Reference 2.
If there are significant space limitations, up to an additional
6 months could be required.
3.8-2
-------
3.8.2 Procedures to Estimate Cost; from Loss of Tipping Fees
Downtime costs associated with loss of tipping fees are estimated by
multiplying an appropriate tipping fee (typically $25/ton) by the increase in
tonnage of solid waste disposal. The increase in solid waste is the
amount of feed that would have been reduced in the combustor plus the fly ash
t!r,t would have been collected by the existing PM control device, if the
combustor were operating during the downtime period. For example, if the
weight of MSW fed to a 100 tpd combustor is reduced by 75 weight percent
during combustion (including bottom ash and fly ash), the tonnage of solid
waste to be disposed would increase from 25 tpd during combustor operation up
to 100 tpd when the unit is shut down. The increase in solid waste disposal
costs is approximately $1,880, based on a $25/ton tipping fee (i.e., $25/ton
times 75 tons per day).
3.8-3
-------
PtFERENCES
1. Electric Power Research Institute. TAG-Technical Assessment Guide
(Volume 1: Electricity Supply-1986). Palo Alto, CA. EPRI
No. P-4463-SR. December 1986. p. B-4.
2. Memorandum from White, D.M. and J.T, Waddell, Radian Corporation, to
R.E. Myers, EPA/ISB. June 3, 1988. Time Requirements for Retrofit of
Particulate Matter (PM), Acid Gas, and Temperature Control Technologies
on Existing Municipal Waste Combustors (MWC's).
3.8-4
-------
APPENDIX A
COST COMPARISON BETWEEN SPRAY DRYER/FABRIC FILTER
AND SPRAY DRYER/ELECTROSTATIC PRECIPITATOR SYSTEMS
-------
COST COMPARISON BETWEEN SPRAY DRYER/FABRIC FILTERS (SD/FF)
AND SPRAY DRYER/ELECTROSTATIC PRECIPITATOR (SD/ESP) SYSTEMS
A.I INTRODUCTION
This appendix compares SD/FF and SD/ESP costs for two model mass-burn
waterwall plants (a 250-tpd plant and a 3,000-tpd plant) at a PM outlet
concentration of 0.01 gr/dscf. Costs presented in the appendix for SD/FF
systems are based on cost procedures discussed in Section 2.4. Cost
procedures presented in this appendix were used for SD/ESP. Lime
requirements are based on a stoichiometric ratio of 1.5:1 for both systems.
The objective of this comparison was to determine whether (1) the costs of
these systems differ sufficiently to warrant separate costing procedures for
each system and (2) a single procedure can be used.
A.2 COST COMPARISON BETWEEN SD/ESP'S AND SD/FF
Costs for SD/ESP's and SD/FF systems are estimated for two model
mass-burn plants. Model plant 1 is a 250-tpd plant with two combustors,
whereas model plant 3 is a 3,000-tpd plant with four combustors. These
plants were selected to cover the size range of most MWC facilities. For
both plants, the SD systems are assumed to achieve 90 percent HC1 and 70
percent S0? removal and an outlet PM emissions of 0.01 gr/dscf at 12 percent
C02- The following two sections discuss the approach taken in estimating
costs for SD/ESP applied to these model plants and the results of the cost
comparison. The costs for SD/FF systems are based on procedures presented in
Section 2.4 at a stoichiometric ratio of 1.5:1.
A.2.1 Approach Used to Estimate SD/ESP Costs
Table A-l presents purchased equipment cost data for SD/ESP's provided
by five manufacturers. The vendor quotations were based on design
specifications for model mass-burn and refuse-derived fuel (RDF) plants.
Because the costs in Table A-l contain significant scatter, the costs for
vendors A and C were used to develop the capital cost procedure for SD/ESP's
applied to mass-burn combustors. Both manufacturers are experienced in SD
technology. Furthermore, the costs reported by both were consistent and
generally were conservative compared to the other vendor's costs. Limited
A-l
-------
TABLE A-2. CAPITAL AND ANNUALIZED COSTS PROCEDURES FOR MASS BURN MWC'sa'b
Capital Costs (dollars per ton/day of MSW processed)
1. Mass burn MWC without electrical generation:
Unit Capital Costs = 50,420 (430/Size)0'39
2. Mass burn MWC with electrical generation:
n ^Q
Unit Capital Costs = 60,700 (430/Size)""33
3. Total Capital Costs = Unit Capital Cost * TPD
Annualized Costs
1. Operating and Maintenance Costs excluding waste disposal:
For mass burn refractory wall MWC,
Costs = (15.7 - 0.00115 TPD) * Total Capital Costs/100
For mass burn waterwall MWC,
Costs = (12.5 - 0.00115 TPD) * Total Capital Costs/100
2. Capital Recovery0
Costs = CRF * Total Capital Costs
3. Waste Disposal of Bottom Ash:
Costs = 1_ * IOP__WR * TPD * HRS * WDC
aCosts are estimated in December 1987 dollars.
Size = combustor MSW feed rate, tons/day
TPD = plant MSW feed rate, tons/day
HRS = hours of operation
CRF = Capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
WR = weight reduction MSW in the combustor percent
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
cApplies only to new plants. Capital recovery costs are not estimated for
retrofit applications, since the capital costs are sunk.
A-2
-------
cost daU were available from vendor E at other outlet PM emission levels to
substantiate the relative high equipment cost at 0.01 gr/dscf at 12 percent
co2.
Table A-2 presents the capital cost procedures for SD/ESP applied to
mass-burn facilities only. A cost equation was developed relating purchased
equipment costs in Table A-l at an outlet PM emission level of 0.01 gr/dscf
at 12 percent CO,, with flue gas flowrate on a logarithmic basis. The
resultant equipment cost equation updated to December 1987 dollars using the
Chemical Engineering Plant Index is given below:
Equipment Costs, 103 $ = 5.896 Q°'535
where:
Q = 125 percent of the actual flue gas flowrate, acfm.
Both installation and indirect costs are 60 percent of the equipment costs.
2
Assuming that the indirect costs are 33 percent of the direct costs, the
direct cost equation for SD/ESP system shown in Table A-2 can be derived.
Total direct cost equations for ductwork and the I.D. fan for SD/FF systems
in Section 2.4 are used directly for SD/ESP systems. To be consistent with
the SD/FF procedures in Section 2.4, costs for installation, indirect capital
costs, and contingencies for SD/ESP are based on the same percentages used in
the SD/FF procedures.
Operating costs for SD/ESP were estimated using Table A-3. These
operating costs are based on lower operating labor requirements (3 man-hours/
shift versus 4 man-hours/shift) and lower fan gas-side pressure drop
requirements (5.5 inches versus 12.5 inches) than those for SD/FF. The
gas-side pressure drop of 5.5 inches is based on a pressure drop of 5 inches
across the SD and 0.5 inches across the ESP. Electricity costs are included
for ESP energization. Additional costs are included for the SD/FF systems
for bag replacement and compressed air. The same cost rates used to estimate
SD/FF operating costs in Section 2.4 are used for estimating operating costs
for SD/ESP systems in December 1987 dollars.
A.2.2 Cost Comparison Results
Tables A-4 and A-5 present costs for both SD/ESP and SD/FF systems
applied to 250- and 3,000-tpd mass-burn plants, respectively. The capital
A-3
-------
TABLE A-2. CAPITAL COST PROCEDURES FOR SD/ESP ON NEW MASS-BURN PLANTS
Total Direct Costs (December 1987 dollars)3
Single SD/ESP Unit: Costs, 103$ = 7.087 (Q)0'535
Ductwork: Costs, 103$ = 1.387 * L * Q°'5/1000
Fan: Costs, 103$ = 1.875 * Q°'96/1000
Multiple Units: Multiply the above costs by the number of units.
Indirect Costs = 33% of total direct costs.
Contingency = 20% of sum of direct and indirect costs.
Total Capital
Investment = Total Direct Costs + Indirect Costs + Contingency Costs.
aQ = 125 percent of the actual flue gas flowrate, acfm
L = Duct length, feet
Cost procedures assume thatjthe total installed costs are 133 percent of the
total direct capital costs.
A-4
-------
TABLE A-3. ANNUAL OPERATING COSTS PROCEDURES FOR
SD/ESP ON NEW MASS-BURN PLANTS
Reference
Operating Labor: 3 man-hours/shift; $12/man-hour 3, 4
Supervision: 15% of operation labor costs 4
Maintenance:
Labor -- 2 man-hour/shift 3, 4
10% wage rate premium
over operating labor wage
Materials -- 2% of direct capital costs 3
Electricity: Electricity costs = $0.046/kwh
2
ESP Energization -- 1.5 watts/ft plate area 5
Fan -- 5.5 inches of water pressure drop 6, 7
Atomizer Auxiliary Equipment -- 8
Kw = 6kw per 1,000 Ibs/hr of slurry feed + 15kw
Pump --20 feet of pumping height 9
10 psi discharge pressure
10 ft/sec velocity in pipe
Water: Based on water flowrate required for 10
cooling flue gas to 300 F and water cost
rate of $0.50/1000 gal
Lime: Based on lime feed rate to the spray 11
dryer calculated by assuming a stoichiometric
ratio of 1.5:1. Apply appropriate lime
costs in $/ton ($70/ton)
Solid Waste: Calculate solid waste disposal rate 12
collected by the ESP and the spray
dryer and apply appropriate tipping
fee in $/ton. (Assume $25/ton)
A-5
-------
TABLE A-3. ANNUAL OPERATING COSTS PROCEDURES FOR
SD/ESP ON NEW MASS-BURN PLANTS
(Continued)
Reference
Overhead: 60% of the sum of all labor 13
costs (operating, supervisory,
and maintenance) plus materials
Taxes, Insurance, and
Administrative Charges: 4% of total 13
capital costs
Capital Recovery: 15-year life and 10% 14
interest rate
A-6
-------
TABLE A-4. COSTS FOR SD/ESP'S AND SD/FF'S FOR A 250-TPD
MASS-BURN PLANT3
Model Plant No. 1
250 tpd Mass-Burn Facility with 2 Combustors
Outlet PM Emissions = 0.01 gr/dscf
SD/FF SD/ESP
Capital Cost (1.000 $)
Total Direct 3,270 3,730
Total Indirect 1,080 1,230
Contingency 870 993
Total Capital Costs 5,220 5,960
Operating Costs (1,000$)
Direct Costs:
Operating Labor 96 72
Supervision 14 11
Maintenance Labor 53 40
Materials 65 75
Electricity 62 51
Water 1 1
Lime 50 50
Waste Disposal 81 81
Bag Replacements 15 0
Compressed Air 80
Indirect Costs:
Overhead 137 119
Taxes, Insurance. & Administration 209 238
Total Operating Costs 791 738
Annualized Costs
Capital Recovery 687 783
Total Annualized Costs 1,480 1,520
aCosts are in December 1987 dollars.
A-7
-------
TABLE A-5. COSTS FOR SD/ESP'S AND SD/FF'S FOR A 3,000-TPD
MASS-BURN PLANT3
Model Plant No. 3
3,000 tpd Mass-Burn Facility with 4 Combustors
Outlet PM emissions = 0.01 gr/dscf
SD/FF SD/ESP
Capital Cost (1.000 $)
Total Direct 17,340 20,260
Total Indirect 5,720 6,690
Contingency 4,610 5,390
Total Capital Costs 27,600 32,300
Operating Costs (1.000 $)
Direct Costs:
Operating Labor 192 144
Supervision 29 22
Maintenance Labor 106 106
Materials 347 405
Electricity 629 504
Water 12 12
Lime 594 594
Waste Disposal 975 975
Bag Replacements 184 0
Compressed Air 98 0
Indirect Costs:
Overhead 404 406
Taxes, Insurance. & Administration 1.110 1,290
Total Operating Costs 4,680 4,460
Annualized Costs
Capital Recovery 3,640 4.250
Total Annualized Costs 8,320 8,710
aCosts are in December 1987 dollars.
A-8
-------
costs for SD/ESP systems are higher than those for SD/FF systems for both
plants. This is because ESP capital costs are more sensitive to PM removal
requirements than those for FF's. At the removal efficiencies required to
achieve an outlet loading of 0.01 gr/dscf, the capital costs for a SD/ESP are
roughly 15 percent higher than for a SD/FF.
Tables A-4 and A-5 show that operating costs for SD/ESP and SD/FF
systems are essentially the same. For both plants, capital-related operating
costs are greater for an SD/ESP than for an SD/FF. The noncapital-related
costs for an SD/ESP are lower. The magnitude of these cost differences are
roughly equal, resulting in about the same operating costs for both SD
systems.
Because of lower capital costs, annualized costs for SD/FF systems are
roughly 4 percent less than SD/ESP systems for both model plants. The
results from this cost comparison, which showed the annualized costs for both
systems are similar, agreed with those presented in another cost study
prepared for the State of New York.
A-9
-------
REFERENCES
1. U. S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies, Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987. pp. 2-1 to 2-3.
2. Bowen, M.L. and M.S. Jennings (Radian Corporation). Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Industrial Boilers. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/3-82-021. August 1982. p. 2-11.
3. Memorandum from Aul, E.F. et al., Radian Corporation, to Sedman, C.B.,
EPA. May 16, 1983. 30 p. Revised Cost Algorithms for Lime Spray
Drying and Dual Alkali FGD Systems.
4. Vatavuk, W.M., and R.B. Neveril, Estimating Costs of Air Pollution
Control Systems, Part II: Factors for Estimating Capital and Operating
Costs, Chemical Engineering, November 3, 1980. pp. 157 to 162.
5. Neveril, R. B. (CARD, Inc.) Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-750/5-80-002. p. 3-18.
6. U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 6-39.
7. Letter and attachment from Fiesinger, T., New York State Energy Research
and Development Authority, to Johnston, M., EPA. January 27, 1987.
Draft report on the economics of various pollution control alternatives
for refuse-to-energy plants, p. 6-9.
8. Reference 7, p. 6-10.
9. Dickerman, J.C. and K. L. Johnson. (Radian Corporation) Technology
Assessment Report for Industrial Boiler Applications: Flue Gas
Desulfurization. Prepared for the U. S. Environmental Protection
Agency. Washington, DC. Publication No. EPA-600/7-79-178i.
November 1979. pp. 5-5 and 5-17.
10. Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
11. Chemical Marketing Reporter. Volume 233. Number 1. January 4, 1988.
12. Reference 6, p. 2-29.
A-10
-------
13. Reference 6, p. 2-31.
14. Reference 2, pp. 2-17 and 2-18.
15. Reference 7, pp. 6-1 to 6-17.
A-ll
-------
APPENDIX B
DETAILED COST EQUATIONS
-------
TABLE B-l. CAPITAL AND ANNUALIZED COST PROCEDURES FOR MODULAR MWC'sa'b
Capital Costs
1. Modular MWC without heat recovery:
Unit Capital Cost = $24,300 per ton/day of MSW processed
2. Modular MWC producing steam (without generating electricity):
Unit Capital Cost = $32,500 per ton/day of MSW processed
3. Modular MWC generating electricity:
Unit Capital Cost = $54,600 per ton/day of MSW processed
4. Total Capital Costs = Unit Capital Costs * TPD
Annualized Costs
1. Operating and Maintenance Costs excluding waste disposal:
For TPD < 150 and MRS < 6,000,
Costs = (10 - 0,23 TPD + 0.006 MRS) * Total Capital Costs/100
Otherwise,
Costs = (15.7 - 0.00115 TPD) * Total Capital Costs/100
2. Capital Recovery0:
Costs = CRF * Total Capital Costs
3. Waste Disposal of Bottom Ash:
Costs
24 *(10°100 | * TPD * HRS * WDC
aCosts are estimated in December 1987 dollars.
bTPD = plant MSW feed rate, tons/day
HRS = hours of operation
CRF = capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
WR = weight reduction of MSW in the combustor, percent
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
Applies only to new plants. Capital recovery costs are not estimated for
retrofit applications since the capital costs are sunk.
B-l
-------
TABLE B-2. CAPITAL AND ANNUALIZED COSTS PROCEDURES FOR MASS-BURN MWC's
Capital Costs (dollars per ton/day of MSW processed)
1. Mass-burn MWC without electrical generation:
Unit Capital Costs = 50,420 (430/Size)0'39
2. Mass-burn MWC with electrical generation:
Unit Capital Costs = 60,700 (430/Size)0'39
3. Total Capital Costs = Unit Capital Cost * TPD
Annual ized Costs
1. Operating and Maintenance Costs excluding waste disposal:
For mass-burn refractory wall MWC,
Costs = (15.7 - 0.00115 TPD) * Total Capital Costs/100
For mass-burn waterwall MWC,
Costs = (12.5 - 0.00115 TPD) * Total Capital Costs/100
2. Capital Recovery0
Costs = CRF * Total Capital Costs
3. Waste Disposal of Bottom Ash:
Costs = 1_
'a'b
* TPD * HRS * WDC
aCosts are estimated in December 1987 dollars.
Size = combustor MSW feed rate, tons/day
TPD = plant MSW feed rate, tons/day
HRS = hours of operation
CRF = Capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
WR = weight reduction MSW in the combustor percent
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
cApplies only to new plants. Capital recovery costs are not estimated for
retrofit applications, since the capital costs are sunk.
B-2
-------
TABLE B-3. CAPITAL AND ANNUALIZED COST PROCEDURES FOR RDF FACILITIES3'13
Capital Costs (dollars per ton/day of RDF processed)
1. Coarse RD facility:
Unit Capital Costs = 73,600 (400/Size)0'39
2. Fluff RDF facility:
Unit Capital Costs = 161,880 (315/Size)0*39
3. Total Capital Costs = Unit Capital Costs * TPD
Annualized Costs0
1. Operating and Maintenance Costs excluding waste disposal
Costs = (12.5 - 0.00115 TPD) * Total Capital Costs/100
2. Capital Recovery0:
Costs = CRF * Total Capital Costs
3. Waste Disposal of Bottom Ash:
Costs = 1
L. * /JOO - WR\
24 y 100 f
* TPD * HRS * WDC
aCosts are estimated in December 1987 dollars.
Size = combustor RDF feed rate, tons/day
TPD = plant MSW feed rate, tons/day
CRF = capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
WR = weight reduction of MSW in the combustor, percent
HRS = hours of operation
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
°Applies only to new plants. Capital recovery costs are not estimated for
retrofit applications since the capital costs are sunk.
B-3
-------
TABLE B-4. PROCEDURE FOR ESTIMATING CAPITAL COSTS FOR NEW FBC'S
(December 1987 dollars)
Total Direct and Indirect Costs:a
Costs, 103$ = 64,900 * TPD * (900/TPD)0'39
Process Contingency: 20% of total direct and indirect costs
Total Capital FBC Costs: Total direct and indirect costs + process
contingency
aTPD = plant municipal waste feed rate, tons/day.
B-4
-------
TABLE B-5. PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS FOR FBC'S
(December 1987 dollars)
Combustor and Balance of Plant (excludes coarse RDF processing area):
Operating labor (based on 10 man-years, 40 hours/week. $12/hr):
OL = 10 * 40 * 52 * 12 * (TPD/900) = 277.3 * TPD
Supervision (based on 3 man-vears/vear. 40 hours/week. 30% wage rate
premium over the operating labor wage):
SPRV = 3 * 40 * 52 * 12 * 1.3 * (TPD/900) = 108.2 * TPD
Maintenance labor (based on 3 man-vears/vear, 40 hours/week. 10% wage
rate premium over the operating labor wage):
ML = 3 * 40 * 52 * 12 * 1.1 * (TPD/900) = 91.5 * TPD
Maintenance materials: 3% of the total capital costs
Electricity (based on 3 MW power consumption, and electricity rate of
$0.046/kwh):
ELEC = 0.153 * TPD * HRS
Limestone (based on $40/ton for limestone):
LIMESTONE = 0.02 * LFEED * HRS * N
Water (based on 3% blowdown rate and $0.05/1.000 gal):
WC = 1.86 x 10"6 * STM * HRS
Waste disposal (based on tipping fee of $25/hr):
AD = 1.25 x 10"2 * N * HRS * WDR
Overhead: 60% of the sum of all labor costs (operating, supervisory,
and maintenance) plus 60% of maintenance materials costs
Continued
B-5
-------
TABLE B-5. (CONCLUDED). PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS
FOR FBC'S (December 1987 dollars)
Coarse RDF Processing Area:
Total Operating and Maintenance Costs (TOT O&M):
TOT O&M = 4.4 x 10"4 * (12.5 - 0.00115 * TPD) * TDI
Taxes, Insurance, and Administrative Charges:
4% of the total capital cost
Capital Recovery (based on 15 year life and 10% interest rate):
13.15% of the total capital cost
OL = operating labor costs, $/yr
SPRV = supervision costs, $/yr
ML = maintenance labor costs, $/yr
ELEC = electricity costs, $/yr
MRS = hours of operation per year
LIMESTONE = limestone costs, $/yr
LFEED = limestone feed rate per unit, Ib/hr
N = number of combustors
WC = water costs, $/yr
STM = plant steam production, Ib/hr
AD = waste disposal costs, $/yr
WDR = waste disposal rate per unit (bottom and fly ash collected), Ib/hr
TPD = plant municipal waste feed rate, tons/day
TDI = total direct and indirect capital costs for FBC plant, $
B-6
-------
TABLE B-6. PROCEDURES FOR ESTIMATING CAPITALISTS
FOR ELECTROSTATIC PRECIPITATORS (ESP'S)a'D
Design Equation for Mass-burn and RDF Facilities:
SCA = -189.29 In (100 - PMEFF)
101.89
Design Equation for Modular Units:
o Use above design equation for large modular units whose flue gas
flowrate (Q) is greater than or equal to 30,000 acfm
o For small modular units whose Q < 30,000
SCA = -285.7 In (100 - PMEFF)
79.6
Purchased Equipment Costs
ESP for Massburn and RDF plants and large modular plants0:
Costs, 10J $ = (305.2 + 0.00738 * TPA) * RF * N
ESP for small modular plants (Q < 30,000)c:
Costs, 10J $ = 1.08 * (96.3 + 0.015 * TPA) RF * N
ESP Rebuilds: 3
Costs, 10 $ = 0.42 * purchased equipment costs for a new ESP (RF = 1)
Ductwork: ~ n c
Costs, 10J $ = 0.7964 * N * RF * Qu<0
Fan: , n Qfi
Costs, 10J $ = 1.077 * N * RF * Qu'30
Installation Direct Costs
= 67% of purchased equipment costs for new ESP and ESP upgrades
(i.e., addition of new plate area in existing ESP)
= 33% of purchased equipment costs for ESP rebuilds only
(continued)
B-7
-------
TABLE B-6. (Continued)
Indirect Costs
54% of purchased equipment costs for mass-burn, RDF, and large modular
units with new ESP and ESP upgrades
$14,000 for small modular units with new ESP and ESP upgrades
24% of the purchased equipment costs for ESP rebuilds
Contingency
= 3% of purchased equipment costs
Total Capital Costs
= Purchased equipment costs + installation direct costs +
indirect costs + contingency costs
aCosts are estimated in December 1987 dollars.
PMEFF = particulate matter removal efficiency, percent
SCA = specific collection area, ft /I,000 acfm
Q = 125 percent of the actual flue gas flowrate per ESP unit, acfm
TPA = total plate area, ft*
RF = retrofit factor obtained from Table B-16
N = number of ESP units
L = duct length, feet
clncludes taxes and freight of eight percent of the ESP equipment costs. For
retrofit applications requiring additional plate area of the existing ESP,
TPA is the increase in the plate area.
B-8
-------
ja
fa
tfi
v.
Q.
{/*)
UJ
f^
o
Lu
t/1
f
C/>
o
C5
^f^
H <
f"
3
UJ
K
O
[1L_J
^*
<3E
iZI
^*.
{J
z
r~
4f
3£
(
oo
UJ
oe
o
u.
1 1 1
QC
i
LiJ
^J
C3
oe
fc^
CO
UJ
CO
*t
^
CO
^
£
x.
*
LA
v
II
O
1
c.
f^
N,
<\J
V^
«*-
0
CD
o
CO
3
u
0
Q
(Q
'
jj
4
JC
at
z
.g
z
*
in
f\j
CO
o
II
i
X
14
^
CU
o
ID
3
c_
O
-G
CO
D
C
4-t
ID
L.
0)
O
c
JC.
4-1
^
01
o
s
o>
t_
Q
01
CO
t.
o
CO
3
-J O
o «-
1
4-1 4-1
CO »<-
O
U 4=
CA
L. *-x
O C-
JJ 3
CO O
-C
c
OS CO
C E
4-1 in
K
c- o
01
a. c
O 0
01 TJ
J= Oi
4J CO
ID
o ^
X 0
«- 0
-Q
CO
1
u
C 01
o u
- c
CO CO
c
> 01
L. 4-1
Of C
Q
CO Z
V)
QC
z
3
LL.
jjl
o
o
X
o
in
n
u
Ul
1
UJ
<
(l
^^
3
O
o
o
H-
0
01
CO
^
4J
u
L
4-1
u
01
01
TJ
c
CO
o
3
Q
O
TJ c.
01 TJ
c/> 0)
0 c.
O 3
CA
CA
CO 01
4-1 L.
a
CO .C
u u
c
u
<-
0) >
U 4->
c
CO U
c
01 L.
C u
.^ 01
CO
X Ul
CO
oe
X
*
z
*
^
0,
«
CO
o
^~
X
o
UJ
I
2
3
*^
O
o
o
«^
o
0)
4-1
CO
L.
^
4J
U
l-
4-1
U
01
^
01
TJ
C
CO
ID
01
c_
ID
C
O
4-1
U
01
"o
o
CNi
4-1
«v
CA
4-1
CD
3
in
^~
c
0
TJ
01
CA
CO
CD
^
a
C/l
UJ
>
JQ
TJ
0>
E
u>
c
o
u
^.
4^
i^
O
i^
C.
4-1
U
0)
UJ
CA
4-1
CO
O
U
CA
^
CD
01
ID
01
U
C
ID
c
01
c
CO
H-
o
M
o
CO
_,
a.
r*
01
U
C
CO
at c
a cu
3 4-1
c
*
CD I
CO E 4
at c
3= TJ <
c <
« CO
z - c
X 4
« c-
O (
IM CA <
i (
0 >
« C. -
01 1
x a. 4
3 C
in co 4
C\J
<
«- ai j
C 4
M -
4-1 *
0 ID (
< <-
01 J
a >
o
^N \^f
C
O CA t
4^ 4-1 <
*v CO (
in o t
CM U C
ty) j
c. C
* o
0 JJ (
ID :
0)
U 4
*4- - C
I t
a ca 4
C G
14-
Q O I
Q
E
4-137
a> <
c
-C 1
TJ 4J C
01
CO 0 C
m i
O i
-o c
co :
CA C
0 .. C
a TJ -
CA CO
tw 0)
O 4= G
C. I
CO > t
< O 1-
CA
M
0
O
CO
4-1
a.
CD
O
^
CD
4-f
O
4-1
01
-C
0 4-1
^
n s-
3 o
j
- in
0 «-
^
a. «-
D
J
*
^ «^
D 0>
1 4-1
3 CO
^ £_
U 4-1
: CA
j 0)
t_
0)
3 t->
c
d*?
O
l>
U T)
J C
CD
D
: cu
J H-
ii
a
>
c_
-i CD
D 0)
_ ^
^
o in
- c
= 0
3
C TJ
01
3 CO
: co
D CO
V
u" >
J C.
: 01
D >
O
3 O
n cu
: ae
j
CO
n 4-1
D .
< Q
a CD
u
N-
CO
O
1
01
CJ
01
a
C
"~
TJ
01 O
4-f C.
CO CU
S H
4-> 0)
CO L.
0> CD
01 o
L- I/>
CO TJ
CA
4J 3
O 01
U c.
TJ
c
< ca
en
01
X TJ
L- CD
01 c_
> o>
o a.
O 3
01
C. O)
C CO
CO TJ CO
4-> 30
'i- » o
a u
0 C 4-1
o u
N«* CU
TJ c-
C CO
CO 4-1 TJ
£ c
CO O O
CO I-
O 4J 4J
a. 01 CD
CO t-
TJ a. ID
C/> 4-1
01 UJ CA
4^ C
CA L. -
a o
3 -4- TJ
c
c in co
CA CO
01 0 4J
CO U CA
CO O
01 c. U
b 5 ~
C CD C
. . cu
E
c 01 a.
CD E -C
M- 13
c. o tr
O C- CO CU
4- X C- .
»» JC CO CU
CU *A 4-1 - CA
c. -C
C X 3 UJ U
co c. ca ^ ~ c_
4-i X4-MI.4-133
» oi v a.
O X *» « Q. C C
0 ^ 00. 3 *-
v> . c/> oi c_ c- o
' CA»UJ4-iXl.O
CO 4J CO ^ OI M- £
3 CO W I- C- 1_ 40 Q. 3
C 4-i OOO3 XIO
c coca us->4-o-o>
CO O4-1C CO 4-1 C 01
U-*-O(-CACOH-4^ID O -C
X C"-O4-!4-! COC_ 4-1
c o acoooau cu oi
o jao.1 o o a> co4-> t-
co co oi ' co ca ID
01 'UJO.OIXX01COO E
4-1 O>*4- C -»- * O CO 4-1 4-1
COH-COUO-4-O- W 10
« O C to TJ 01 O
TJ COOl«4-i4-i4JCOTJCU 01
C.J3I.CUO3 4-i t__
OlE3OIOI4^J=CO CO CO
3 Q.3OCO lUCOCO 4-1
J3 OCJZEOIOIQC03 cn--
01 4-i Q.
c- M u n u n u n M n ca CD
o u
a. co u u cj
Crt t- LU UJ 4-i
UJ ID J J c. O
UJ UJ O 01
t- t/> za.3 c£-Qu
OO i a£--j
-------
3
*
O
0
r
O
UJ
Z
r
UJ
00
ce.
O
o
o
u*
f.
o
^_->
^1
^.
h-
^t
<-t
O
£»
3C>
>^^
^*
5?
*^
L^
CX)
1 1
UJ
oe
0
^~
Of
UJ
DC
O
UJ
Jj^
QJ
oc
Q.
00
CO
UJ
1
CO
^M
£
a
c
V)
Oi
E
-
>,
ro
TJ
in
«-
C
o
TJ
Oi
in
m
CO
Oi
3
-^
^
.
O
(_
4-*
C
o
CJ
3
O
_^
u-
-o
aj
01
3
0
.c
o
ra
m
S_
0
*
.c
in *
4-- 3
C/)
0 0
u
4-1 CO
c
O> OI
ED
a _j
u
L.
3
O- «
*^
c
a
ct
u ^
OI 4->
a c
(a
o
a.
« L, 4J
o> c
v a.
(0 « Q.
1- O
0 - L.
tn
M- O)
o *- 3
4-* 4^
O «^
O
10 -O IO
O"ae -4- ee -4- u.
* TJ * 0
L. C 0 «
^ ^ ^ ^^
C ^O O sO -4- >
(0 »- O t- CO
-co to o c ro
4J . , . <0 O
O (MO -CO
(A 4-1
M + C + O
Oi Oi U
ro 01 to ai o
s^ s^ rt vx ^ *^
at
o) * m * *
01 01 01
E in E o E o
30 3 «- 3 «-
^ ^ "o (M "o f\j
II II II
0) ft) Q)
D) C/) O) CO O) U
10 4^ (Jj 4^ (Q 4^
t- in t. in <- in
o o o o o o
4-> U 4-1 U 4J (J
« in in
in
<- <- t. c
o o o
U. U. U. CO
TJ
01
4)
O O O ".
i
(M
«
^N
L.
O
* 4-i
t- 3
0 XI
M E
in o
3 u
XI
E !_
O 01
u a.
<- a
01 C
a
in xi in
c ** *t
. 0)
TJ O H- O
OI ^ r*
OI UL- O 14-
M- CO 3 CO
C * «
O C
N-* U- O "-
ae of
C 4-1
O * U *
._ Oi
u c
OI » »
C NO 4-» fM
- o c «-
f> Oi CO
-> O XI «-
C L.
01 o o o in
XI Bl L.
t- II II O>
0 Oi TJ
in in o in 01
4-* w c in u_
00 L. 0
3 O 3 CJ O
TJ >4-
L.
C. L. 4-*
O O 0>
14. U. £
,^
>
flt E flt
in o
3 * u «
XI
E Z t- z
O 01
u « a.*
L. ^ u> /->
0) ro L. m
Q.O- OI O> -H
(M TJ fM £
L. O> 4-*
01 o> a> r> CT
TJ * C
Oi + + 01
Oi 0 -J
4-14- 3 U.
CO 4-* CO 4->
0) ^^ 0)
c o> r> o>
O CO C CO u-
>- (M O PU
0 O O
co 4-> o o
o o u o -j-
4^0 .0 C
u ^ c *-* o
OI
>* * TJ
C 4-> U
NJ- c co «
r\j QJ ^^ n
4-» O XI O CO
C u **
Oi «- O fM
XI V) t-
L. II II O
O 4) >
W U) O U) O>
4-> U) C tf> C
U O 1- O O
3 U 3 U O
TJ H-
o
L. L. *-
00 f
14-1^ (0
E
3
Oi
c
oo a.
.
xj
T3
o>
c
c
0
U-
K
z <^
L.
^\ o
t 1 »4-*
"X (/)
1- 3
4-1 E
u- M O
CO 3 U
1
vj O 0)
u a.
r L. CO
OI 4-<
+ Q. L.
M- O U.
33 4-* C£. Q. CC
t_
M O * C *
- a. o
i-1 Z - Z
C 4--
k o -It u -Ic
sj- 4-» /"x 1 ^^
0 u- C u.
o a> co co
^
+ C v* 0 -*
T- 3 »-
14- O 4J O
U> 01 O -^ O I
C 1
ro o o c o
N. x^ O
o + +
0 C 4J
O fM U (M
o 01
4-» (M fM I
+ 0 fM C fM |
0) \^ "~ Xj^
C « 4-1 «
CM in o> o
\^ 4-» O XI «~
C 1- .
« O" T- O fM
XI m
in i- n u
O O 01
in in tn o w
L. 4J « CM
II O U O u O
O. 3 CJ 3 O
in TJ M-
4-> C
in o L. u
00 0
CJ 4-* 14- U.
u
0)
c
0 0
1
in
B-10
-------
1
1
i
1
-o
*
^^
o
in
o"
in
CM
~
*
0
f
^
ro
II
CD
V)
O
(j
,,
4-*
O
CO
c
o
u
4J
c
0)
XI
o
^*""»
"O TJ
0* c
3 co
5 w
4-> 0>
O eu
3
o _,
~-* >4-
cu
CO
* CO
CO cu
| C-
CO g
_J O
CO *-
^C c
I o
4-*
u
CU
c
c
4-1 C
c c
CU
1 XI
tA
0
o
4.*
C
E
Q.
IT
CU
X
(_
CD
.P.
X
3
CO
Q
c
CD
l_
CU
,,_
H-
u
u
CO
H-
0
J4>
CM
N.
4^
O
o v
O 4-*
5 «- 0
3 "^ O
3 "N
-in 4--
c
» o cu
- O E
Q.
*
3
0 CU
*
C
(_ U. O
o u- u- a:
t- ex o; 4->
* *
CO
C Z 3
O
* «
Q. <\J 1-
O OO M
v-» ^ C r
«- 10
U. f
U O -
CU t- +»
) 0) II H- 1
CO 4-» CO
CU CA "- t
U- 0) C,
1- O T) C
QUO CU C.
4-1 U
0 C- 3
CO Xt T>
0) CD C
oe u.
-or-- 03
* u
CU
r c
r»* CA 4-»
CM 4J C
D -O « CU
oo O Xt
u <-
o o
> ^^ 4^ CA
O
II CU X
C. c.
n to TJ
J 4J Q W
0 ^ CA H- 4-*
3 I- O CO w
J O CJ 0 0
3 - X U
4-" 4J O
U 01 tfl +1
3 o
O II CU
CO <-
4-* -
CA TJ
C C
o -
+
c
0
4-t
u
CU
c"
C 4-.
CU C
Xt cu
O Q.
CA "~
3
x cr
I- CU
TJ
X
t. C-
O CO
0 C
I- CA "-
CO 4-> tA C
O O
' O O
CO >4-
4-> 4-» +
CA U U
c eu CA
XI - 4- O C
CU CU
\^ 4J C-
CA "~ +
CA O TJ
4J O U)
O 4J O CA
U C O
to E 0
4- E 3
U Q. c/) CA 4->
U 4J CJ
c- 3 CU V! CU
IT .C O L.
TJ CU 4-i U
a
*4- »*- V4- *
O O O CO
>H 4-> CO
o-£ X U X "~ 4-*
ro CM co Q o
ro ** tu in co H-
a (J
II C II II
'* *
>-> CO
C 4--
o o
U 1
U L.
>v. Q
t- **"
CO (A
(A
t- O
O U
4-
CA cy)
O Q-
4-> V)
U UJ
CO
- O)
c
4-f >
>- CA
O
(_ X
CU
ex. _c
< 2
C M
CU 4^
Q. ca
3 "a
IT
CU t_
O
C i
o
"-
4^
O Ul
CU 4-i
1 CA
C
X
CU
4-1
c tx
CU CO
XI LU
E t-
4- O O
U CA C
CO
I- CU
0 L.
.C
C «- 3
3
t. *~ C
CU 1- O
a. o
t- U CO
CU O CJ
4»l 4-« >^-
0
. to a.
H- >4- ^ a.
T CO
O 4J 1
._ .-a) 4->
xi o eu M-
co t. _ . o
CU CO 4->
CU 1-1 CU
4-1 CU £
CO O t_
O 31- O
4-> »4- M-
«
tA OKI tA TJ TJ
C_ 4-> 4-> C U C
CO CO H* O C CD *O
^ C >P» *r 1
' 2 - 4-t CO CA CD
O O 4J CO 4-1 C
TJ C 0 XI O «U
M- CO *- O ' '
t^ 4-. Xt
CO CA Q. Q. eu co co
O co Q. c_ o t
« D) CU CO CO
x: E
L. I QJ 4J 4J 4J O O
CU -C 3 C Q. t-
E XI C 0 0 E
cu >4- i- O. 3 TJ
CJ . 4-> eu CU
CU -COCU 013 C4-i
Q 4J 3 E <- IT to
" 4^ 3 fU t E
C C 0 ^ t- 0 -
3 CO O OX 4-4J
> U. c_ tA
TJ C tU CO TJ tu
CU 01 .c O 4J CU
CO >- CA c- .*- CU 3 t-
E 0>>4-tA4->OX»- CO
no 4-> 3 eu
4-* CD eucuco-t-a.
tA t-4-*O)3CO J= COCO
01 C CD H- TJ 4-> UJ
TJ 0) I- t- C Ol tA
Of CUOOO4-'CUC C-CU
I Qi t 4-t '* OJ 0) t
CO *^ IU CA t *4~ L- * 4-* 4-*
a. o> o cu
CA CU 0)X)t-4^4-»> Ol
4-1 EinEEv cj H-C
tA -r- IM 3 S> 3
O «- C « *- TJ OTJ
CJ CO
II II II II II II L L.
XI 01
' u. u_ CO Q.
< c/)ar>zoe: t u-3
CO XI U
B-ll
-------
2
0
o
h-
<->
UJ
^"^
^f
» *
h
Z
t . i
02
O
GO
>
a
a:
o
i
(S>
o
CJ7
«ZI
H""*
H
uu
a.
O
d£j
^^
^M
s
4^C
^j
o
^E
^^
rfjT
^^
H-
oo
1 1 j
ae
O
oo
UJ
QC
O
UJ
O
§
a.
a>
CD
UJ
_j
CD
^C
^^
CA
(/) CA
a: o
x u
« CA
2 CD
« t-
41
in 4J
CM C/) CO
co of e
O CU
to * o
II Of C
X Z CO
-I C
Z * * 41
Z 11- C
^1
41
a
CD
L.
O
^^
CT
C
to
t_
* a
0 E
K"l
E
II 41
C.
-> a
o
4)
CO
L.
*v
CM
»
4A
H-
O
41
a
CD
2
4-<
t^
.C
*^
CA
c_
3
O
C
to
E
(M
C
O
-o
CA
ID
CO
l_
0
-Q
CO
o
c
4J
CO
L.
OJ
a
o
L.
cu
u.
to
o
o
4-
4-* 41
C- 4-1
41 C
Q -
3 CO
* CO
* E
CO O O
* o »c
o
O II O
in
ai CA
O CM Z 3
« in
C _i a
t-
O v O
4-- « O
O
4> ^ 4_>
« I CO
C 0 C-
0
4J X
C L.
41 in 4J
^ CNJ 41
l- E
o in o
CO
II -C
41 u
^ CJ -
4-f UJ O
_J 4-*
*- UJ CA
o
CA
CA CO
4^ *^
CA J=
0 3
O ^£
^ >O
co %r
4^ O
Q. o
CD «/)
u
H-
4-> O
U
41 41
C. 4-*
CO
"O c-
41 >
*-» '^
0
**-
O 1-
4-*
M U
in 41
41
CA C
0
CD
"O
c. 41
41 CA
w CO
ID CO
Z ^
41 >
U 4-t
C
ID U
C
41 L.
C 0
._ tu
CO
Z UJ
O
T3
u
CO
T3
C
ID
CU
E
T3
41
L.
>
.C
L_
O
C
o
4-1
^
o
CO
>
c
o
T3
41
CA
CO
m
,,
41
E
_j
U
c
ID
C
41
C
ID CA
E 4->
CA
TJ 0
c u
CO
i
CD
L. -
o a.
IA ID
"- U
^ ^
41 CD
a 4^
3 0
l/J 4J
41
cn x:
C 4--
^
(0 O
L-
a
0 t-
U (D
U O
O
.a o
(0 >
*-*
' (D
' L.
(0 4-J
U)
>4 -p
o c
i
3 T>
CA <
4) -a
£ C
4J ID
v^. i
O 41
U
O to
\O C.
3
CA
C
T3
CO
41
-C CA
I- 41
CU X
> CO
O I-
CA
CA
O
U
CD
4-*
a
ID
u
CO
4-*
O
4-*
41
-C
,^_
O
in
fl
>(
s~O
41
CO
t_
4-1
41
C-
41
C
^
O
^
£^
cc
cu
._
CO
41
in
c
o
T3
01
IA
CD
CO
^
(_
41
0
U
41
Of
-^!
CD
4-*
.^
a
CO
CJ
CA
4-*
CA
0
O
4-*
u
41
c.
T3
C
O
4-*
CD
j
CD
4-*
CA
C
~n
C
CD
£
CA
O
U
4-1
c
L. 41
^» Q.
CA 3
I- tT
CO CA 41
' 4-*
CA 41
O O ' CA
*O U CD
.C
>v- X 0
CO 4-t L.
O. 3
T- o c- a.
C. -F- .C
c- X t. >.*-
4) c- \ 4J -Q O
^J x wo
E ^ cu E
41 «t - - 3
U CA 41 4-* CA
41 4->
0 CA CA C C 4)
4J O O 3 -C
C cn o 4->
O C 4-> C_
o o c. o cu cu
"O O 41 Q. c_ C.
41 UCA4-*^ I X CD
4-> O *J CO CO C 41 >v.
CD J3 c_ . . 4- «A cy)
E CO C 4» CD u
'- ' 3 Q. 41 4J c_ » CA
4J O 0 C CA O
CA O)*- C4l"D4-> U
CU CO*-COX)4ICA
^ 0 C I. 4) O <
flj 4J (_ ft) O ** U (0
i_ a>"-
QJ E D >> E Q-
C/J Q. 3 O (0 I '^ <0
4J O C £ S T3 0
CA
O II II II II II II II 4-*
U 0
CJ UJ 41
C/> Ul Z t-
«. J « 0£ t » 14. <« t^-
< Ozxzujc/>_j a
CO J3 U
B-12
-------
_a
v*
t&
oo
ac
UJ
i
^**
u.
^^
QC
CQ
u.
ae
o
*^
GO
CO
o
- _
z
HH
r^»
s
LU
a.
0
^
=3
21
2C
g^
CJ
<2>
^^
»
*jt
i"**
^^
CO
UJ
QC
O
LL.
CO
ac
^3
O
LtJ
^J
o
a.
O
^^
1
CO
.
L^J
J
03
r|^
1
«
«
o z
*
rO CO
O CO 3 4V
in of -i w
(M Z U. O
o
U) 0 * «
ac co
z ii z in '
i CO
* CJ * 0
1. CO 3 *~ 41
_l X 4V
41 14. CO
.. ,- g
in *-*
f> oi
4V
CO
c.
II
CJ 4V
1 4V (A
Z C 01
01 1_
1. 4V
,i
01
CJ
CO
2
c_
O
XI
CO
Q
C
4V
CO
l_
01
a: o
in
01
« -C
z
* 01
0 0
ro E
u
E
_l 01
O "-
D
41
c_
.C
CM
*»
14.
O
41
O
CO
,
4V
F
jr
CO
CO
3
O
JT
c
CD
E
CM
C
0
"Q
4*
CO
CO
CD
>_/
(_
O
-Q
CO
O
c
4V
CO
i_
41
Q
O
4V
CO
c_
01
o
CO
2
-1 O
o «-
4V 4V
CO M-
O
O -C
CO
0 L.
-O 3
CO O
JZ
c
O> CO
C E
4V *~
CO
C- C
41 o
Q.
0 XI
01
01 CO
-C CD
4V CO
^^
H-
o
tl
&^ C.
in o
T- J3
CD
1
C 01
O U
C
10 CO
C
> 41
Ol C
Q
3 CO
CO Z
- c
3
CT
41 X
O
X «-
u
CO X)
- c
CO
X
3 Ol
CO *
-a
c
a a
CO
i- -Q
4V C.
CO
.,- Ol
O CM
J3 r-'
CO
4- ro
41 -4-
-C O
4V
o
*-* 4-*
O (D
JQ t-
**- .£
0 4V
O
en -v
4V U
C/> i
O 0
CJ 4-1
-* (_
CO
4V CO
OL CO
CO V)
CJ 0
c-
4V O
U
41
1- CM
5 £
4> in
-c ro
4V
^
*4- V»
O
c
X O
XI
01
CO
t/i to
CD
CO ^
L.
01
4V 4V
10 C
Z Oi
E
01 41
CJ CJ
C CO
CO
C Q
01 41
4V CC
c
o
CO CD
Z CO
« O
41
xt CM O
i C
OH CO
T- C
a: oi
X 4-»
< C
(M
r- CO
« ^
^
II -
CD
U
UJ XI
_l 01
UJ CO
CO
41
c_
4>^J
e-
2
V^
*O
vj-
o
o
w
o
OJ
CO
>,
^
u
(_
M
u
L.
Q
!
O
a
CO
f-
o
c
in
CM
c
o
XJ
Ol
CO
CD
m
^
4^
in-
0
c_
o
Ol
J
UJ
a
E
O
U
t_
o
E
^f
(J
V)
o
o
o
T-"
»«V
^*«
^
O
M
XI
c
CO
CO
ID
41
_*
*4-
E
\4.
U
CO
o
o
o
T~-
^
L
<^
CO
o
E
H-
0
CM
C
o
x>
Oi
CO
CO
m
XV
i_
^
(^
"XI
Ol
CO
CO
41
c_
a
E
0
CJ
t^.
o
j{
o
^5
CO
3
"a
^^
o
c
CO
tt C
a 41
3 4V
c
* -
CO
M
o
o
^
CO
1*.
Q.
CO
CJ
=J
10
o
Ol
-c
CO CO 4V
co e 4v
A *4-
3= X» O O
c o
* CO
z *
X 4
« c.
o
CM CO C
1 >f (
0 >
« C.
41
x a. 4
3 <
in co 4
CM
- c
«- O> J
C 4
II
O CO
- in
0 «-
V
~ ro
3
J
v '"S
0 0)
V 4V
3 CO
V L.
U 4V
z w
v 41
L.
41
< <- c
0) 3<
a v
o
^*"» sv
c
O CO
^v CO
in o
CM O
«/» J
L. C
>4- O
o jo
co ;
41 _,
01 4
M-
f
tr co 4
c
1- «4- -F
Q O !
D
e
CO «
c
0 41 1
J= I
X> 4V
Ol
CO >4-
co o <
CO
^^ ^4?
o <
CO
CO c
0
a xi
CO CO
..- 41
a v= <
L.
-C 01
CO > I
< O h
r
o
A
1) XI
31 C
CO
D
: 4i
J H-
r~
u
>
L.
v CD
0 41
_ >l
A in
- c
E 0
3
t XJ
41
3 W
: co
o m
u >
J u
I 4)
0 >
o
3 CJ
A 41
~ Ctf
CO
A 4V
u
< Q
0 CO
o
t
CO
4V
CO
0
u
1 J
u
01
XI
c
0
4V
CO
10
CO
c
XI
c
CO
E co
4- 4V
CJ CO
CO O
u
4V .c 4V
-^ c
C J3. 01
3 E
Q.
41 4V 3
a. cr
C 01
. 41 3
CO 4V 01
C. CO I- CO
CO c_ S 41 CO
2 >4- Q- -c
O CJ o
O CO t- t_
XI -4- O 3
» 4V Q.
r*- co 4v -^
GO CO " "~ 41
O ro c M- .c
^ 3 4V
t- 01 U
L. X 3 C_ *-
OIL. V, L. 41 C-O
J3 X tft XH- O. c- J3
e ~s. >» x co E
CJ CA 41 4v t_ fA CO
41 - 4v ._. CO X E
O CO COCOCC_^^«O 41
TCO OCA O 4V«4-4v
O C O 41 CO
CJ OC_OJZ>4-COO4I 0)
Ol L.C04V.Q4V COCO CD CD
4v O4VCOCOC14-COOU1_
CO ^--1 -OIOCTO"- W
ECOC4I E CO -4v
D Q. 11 41 4V CU X CO CO
4v OCJCJC34VXICO O
CO COM- C CO 41 41 O U
41 CO*4-CO 'OH-CJCOQ.
'* O C n j_ >r_ y) co -_
41 4v ^ QJ 01 41 <^ 1. 41 '^ CO
t- CO 0) CO 4v L. CL CO 4v L. XI 4v
cac-jat-c 3uO-
4lE3»-a)in4v4iEj= CX
CO Q.3OCOCOCMU 'OCA (0
4v O C JC E n ^ CO 41 O CO U
(A
O fl II M || || tl II |} || U t-t
0 0
CJ o 3 UJ a: cx: (_
^ O 3C T X CO O U» LLJ ^1 3 Q
(D ^ U
B-13
-------
TABLE B-ll. PROCEDURES FOR ESTIMATING CAPITAL COSTS OF STANDALONE
SPRAY DRYER AND SPRAY DRYER/FABRIC FILTERS3'D
Direct Costs
SD/FF Unit0: Costs, 103 t = 8.053 * N * RF * (Q)0'517
Stand-Alone SD Unit: Costs, 103 $ = 8.428 * N * RF * (Q)°'46°
Ductwork0: Costs, 103 $ = (1.3868 * N * RF * L * Q°'5)/l,000
Fanc: Costs, 103 $ = (1.8754 * N * RF * Q0<96)/1,000
Indirect Costs = 33% of direct costs
Contingency = 20% of sum of direct and indirect costs
Total Capital Investment = Direct Costs + Indirect Costs + Contingency Costs
aAll costs are estimated in December 1987 dollars.
Q = 125% of the actual flue gas flowrate, acfm
N = number of units
RF = retrofit factor obtained from Table B-16
L = Duct length per unit, feet
r*
The total installed costs are assumed to be 133 percent of the direct capital
costs.
B-14
-------
CO
Of
GO
a
oo
Q;
1 1 1
«
Q
^
^^
^f
a.
GO
LU
O
_J
l^f
.
0
z
OC
O LU
)^M h^
CO ***
f LL.
O 0
J 1 k>~4
CB:
C5 OO
iriET *^
H« j^^
LOB Nw
(irf" ^^^
2 uj
UJ >-
Q- QC
O O
J >-
*^ ^f
^~i f^
z a-
3"
_ si
S2 *^
o z in *
z u * o in
INJ «- «
* CO CJ «- Z O
Of. < X <-
ae 3: co «- *
ro x
« « HO
10 Z ^
0>
tO * 4-1
ID
ii r»- c-
__l ^~ 4^
Z en
II cu
c-
01
17
ID
2
c.
0
J2
ID
a
c
to
Z CD
CO t-
* a: 01
3: Q
z 0
« 01
x. -c
O 4J
*
0 I-
O HI
II >
ro o
OH E
3
o i
x:
c\j
JJ
H-
0
0)
D
CO
3
c_
0
X)
ID
,
4-1
H-
,^
.C
CA
CA
3
O
-C
C
CO
**
C
O
01
CA
CD
CQ
U-
U_
X.
a
CO
i_
o
L.
o
XI
to
D
C
4J
to
01
a
0
0>
L.
Q
u
.e
IM
»
4y^
*4-
O
01
O
to
2
f^
0
CD
$j
*4-
-C
en
CA
L.
3
O
C
CO
E
r\j
C
o
^Q
Ol
CA
to
CD
O
CO
L.
O
L.
Q
ft
ID
a
c
4-t
CD
t_
01
Q
O
01
CD
01
C
ID
O
4_i
*^
,^
^
CA
^ CA
O 3
r~
4-> C
CO ID
0 E
O
C\J
£_
O C
JQ 0
to
TJ
01
o en
C ID
.- CO
to
t_
01
a u.
O u.
01 0
£ CO
*- 0
O H-
X (-
in o
* ft
ID
t*
C 01
O 0
c
CA ID
- C
> 01
U 4J
01 C
a
3 ID
CO Z
1 01
Z 4-1
c
I,
r*
0>
o
ni
2
!_
O
ID
C
C
.^
4_l
ID
t.
Ol
Q
O
01
-C
u
>
o
E
3
E
01
Q
o>
4^
10
Ol
o
ID
3
^C
o
t«
4-«
H-
.^
.C
CA
1_
3
O
C
ID
E
r-
C
O
I
CA C-
O
O CD
CA
to en
4-> 0
a a
UJ
u -
4-1 4J
U -4-
0) ^
u in
to
TJ
CO
4-> C
0 0
01 01
£ CA
4-- 10
CO
*4- *~i
O
I\J U.
U.
^
IA in
^
CD L.
O
t- H-
01
4-1 4-1
ID C
Z Ol
01 Ol
U CJ
C CD
to '
C Q
01 01
4-1 Q£
c
"- a
CD CD
z m
CJ -J- O
UJ
-i ii ru
UJ
Z CJ II
< UJ
u- _i at:
UJ -!
Z CO <
-H
2
>^
SO
O
o
4^
H-
o
Ol
CD
^
^.
4_l
^
U
L_
O
01
_*
0>
T-,
c
CO
Q
O
I_
TJ
Ol
e_
3
CA
CA
Ol
L_
Q
o
3
en
Ol
-C
u
c
in
rvi
«
C
0
T3
4-1
U
(_
4-t
U
- X-N O
3 ae
t i_
+ 30
U_ JjV
CO E
N^ 14, H-
co u
* ^ ta
O « o
o o
i
0 0 -
fv.
* X «-
^ T O
-J- O (A
o rvj
TJ
0 »- C
CD
II II
CA
CJ O CO
UJ UJ D
_J _J
UJ UJ CU
i- a. 3
< z:
rr> **-
a.
E
i^
2
L. V
if x^
x. >o
-Q -J
O
o o
o «t
o
«- o
L. 01
01 4->
D- CD
L-
2
4-*
O
C
O 1-
TJ 0
01 01
IA
CO 01
m
^ TJ
c
!_ CD
01
N 2
E
O in
< +
^
O TJ
4- 01
Ol
4_»
» ^
U (-
^- t-
(_ 3
4_i __,
U (A
41
' *+-
UJ O
4_
» ..
.c o
01 C
Ol Q
JC
Q
O)
c c
ft
E >
a.'-
0
>4- 0
0
01
4-- >
01
01 U
<4- 01
CO
O -v
C\J V
4-
c
o o
TJ
01
VI V
CO t-
m 3
*~f CA
IA
a. oi
3 O
Q.
01
1- O
O c-
M- CD
SI.
>. o
4-* CA
'* >p-
CJ TJ
L- »-
4-* CA
U Q
01
O
UJ *-
CD
O
o
o
1
^
L-
CD
0
E
+-
CJ
CA
IM
C
O
TJ
01
IA
CO
m
u.
u.
o
CO
0
L.
r
^
TJ
Ol
CA
CA
01
L.
a
E
O
c_>
(0
3;
*
Z
*
Q£
1
3
1C
in
o
"~
x
o
o
o
u
CO
cj a:
3 z
k
CD
0
O
o
o
^_
«^
o
in
0
c
CD
u_
O
0
o
to
o
o
c
~0
o
u
ID
et
01
3
u.
C
O
TJ
01
CO
ID
GO
, t
t_
CU
CO
3
*
u-
co
*
in
o
o
u
UJ
1
..
^\
01
E
CJ
3
D
L-
o
H-
c
o
4-1
0
c
o
TJ
01
CA
CD
CO
i .
01
E
i
B-15
-------
-o
O>
c
**^
o
o
*
CM
V ^
CO
UJ
CO
^
'
DC
o
3
41
CO
^
2
CM
O
X
in
CM
^-
II
o
^
c
0
4-1
in
CM
t^
O
01
u
*4»
OP
c
a
a
£
c
o
T3
1)
CO
CO
m
^/
u_
u_
^,
o
CO
L.
O
M-
_*
CO
CO
o
a
CO
_
CA
<
CO
CO
0
u
CO
CO
c.
01
I
01
u
c
CO
c
41
c
CO
E
«*-
0
0
-o
CO
3
"a
01
o
c
CO
c
01
4-1
c
CO CO
E w
"o o
c u
CO
^
CO
X 4--
o a.
tfl CO
o
8. 2
3 O
CO 4->
0>
C 4->
CO O
L_
oi M:
a -j-
o
***
CO CO
4-1 4)
co a
O t-
O 10
JZ
U CJ
0
~s >
-
CO
* L.
CO 4J
CO
*^- '
0 C
If
E
CO <
41 "O
J= C
4J CO
O 01
u
tt c
0 CO
-O t-
3
CO
c
T3
CO
01
J= CO
c- 41
C) X
> CO
O t-
ca
4-1
CO
o
o
CO
a.
CO
u
CO
4-1
o
01
4-*
o
X
in
«
ro
,.
01
10
(-
^
CO
41
f_
ii
c
X
o
iy
£
a
01
**-
'-
01
in
«»
c
o
T^
41
CO
CO
03
>
L.
0>
o
u
01
oc
_^
CO
^
CC
CJ
E
u
CO
4-*
c
3
01
a
c.
41
.
> £
**- H-
U
U CO
c_ -
n 4-»
CO -
4- C
3
0)
J= C.
4V 01
a
o
4>
01 4-1
4-1 '
CO U
3 X^
O U ^ *»
CO j; COOl
00 X ^. CO 4-. J=
O C_ ^l-H-OJ^ H-C04-'
«-X » X 4J L. L.
^x *v JZ 41 4> 41 X
t- »» -MCOOI - C^IJT^,
^ . 4V-4JCO .
OI4-> O4JCOZ3-OOOIA
UCO UCO O 4-*«4-H->4-4-'
OIO C O 01 c. CO
a o ot-o.e«4-oiciAcocooi-
^-O 4J Q-3W4-'4-«UX
CC-CA4-*-Qw CO CACOCO ^^
"~ O 4^ (0 OS C *4 10 f ^ O O O t 4A
Q ,^ f^ ^ Q) Q pj 4-" 4> O O (J
~O as C v £ coo. co-
oi '3O-4I4I4-'OI1- XXX CO
4-» OUUC3 4I4J4J4JTD4J
CO O) >^ C CO O ' "U 4-* i^1 *^ * 4) CA
£ CO H~ 10 ^ U *^* 41 10 CJ O O (A O
o c a u u i. - co u
4-* 4-*L- 01 01 01 H- L.C-C.4I
4> 1-J31-C 30IOIUUUQ.OI
01 OL3OCOCOCMO CO ' > 'OCO
U OC-CE.Q*-CO 5 41 CJ
CO LJ UJ
O UJ CJ _ 1
O 1 UJ UJ
uj i a.
' CO U 3 CXZUJZK
0 -Q Z u. u.
-C
(- -^.
>* .0
** »
* o
***. u *
vt to
03
» (0 O
** O CO
y) Q^ ,^»
o « -a
"O d)
-------
TABLE B-13. PROCEDURES FOR ESTIMATING CAPITAL COSTS FOR HUMIDIFICATION
Purchased Equipment Costs, 10 $
1. Humidification Chamber and Pumps:
Costs = (0.438 * Q + 80,220) N * RF/1,000
2. Ductwork:
Costs = (1.16 * L * Q°-5) * N * RF/1,000
Installation Direct Costs = 56% of Purchase Equipment Costs
Indirect Costs = 32% of Purchase Equipment Costs
Contingency = 3% of the Purchase Equipment Costs
Total Capital Costs = Purchased Equipment Costs +
Installation Direct Costs + Indirect Costs
= 191% of Purchase Equipment Costs
aAll costs are estimated in December 1987 dollars.
Q = 125% of the actual flue gas flowrate, acfm
L = duct length per unit, feet
N = number of units
RF = retrofit factor obtained from Table B-16
a,b
B-17
-------
-O.
»
**
o
^"T
^t
f J>
i
"^
0
t t
^£
QC
O
u_
00
I/)
O
^^
(9
jp
,
.P
c2
LU
a.
o
j
^^
^^
13
*y
^^
**t
O
J
r
^£
^p
rjT
r
t^^
LhJ
OC
O
U.
LU
oe
o
U±J
O
fly*
Q.
,
^_
^*
1
CD
LU
-J
CD
^*-
^"
cn
cn
0
u
CA
OC CO
3!
* 41
Z CO
*
ac cu
in » cj
CM 3 C
CO <0
* c
O 41
CO 4->
u a: c
1 CO
z * E
Z >4-
o
* o
of -Q
X CO
*
z c
ft 4^
CO
in L.
N- cu
Q
o o
II CU
JZ
b
CU
x^
u
JZ
*N,
«
tA
s~
o
41
a
CO
3
L.
O
CO
4^
tt-
-C
cn
cn
C-
3
O
JC
c
CO
in
o
c
o
73
41
CO
CO
CO
l_
0
£>
CD
O
c
.<
4-*
to
U
Q)
a
0
0
g
3
E
41
t_
Q
O
CO
3
O
_J
o
<^ 4-»
4^
cn -c
O CO
CJ *x
t_
l~ 3
O O
-Q -C
CO C
CC
O)
c. in
4-> O
CO
I- C
QJ G
a
0 73
41 C/I
x: co
4J CO
H-
O
*« il
in o
- -O
cc
(,
C 41
0 CJ
- C
to co
c
> 4)
C- 4-*
ft) C
Q -
3 co
CO Z
*
££
o o
i -O
o
«- CO
3
a
ro
h-I 4)
u
II C
CO
u c
LU 41
_l 4-*
LU C
4) ._
O) CD 0
U .. E 4.
CO ^
-C -C
0 3
cn -^
73 -O
^ o
CO
Q.O
tft
o
O <4-
g O
. CU
4-* 4-*
£ CO
O) L.
41
cn .c co
i-» CJ
cn o> -
0 C L.
CJ - 4-»
a. u
e cu
CO 3
4-> a cu
Q. -4-73
CO O C
CJ CO
4-*
_ CU
CO 41 O
4-» »4~ C
0 -
4-> O Q
C\J
4) Q
£ C
4J 0 C
4- 73
O 41 >
cn 4-<
X CO
«- CO O
>^ o
1
CJ CU
CA in >
« to
3
c -
CO U 41
C c-
41 L. 3
4-* 4-1 CO
C O CO
.- 4) 4)
CO L.
z LU a
b
cn
4-1
cn
o
u
CO
4-'
a
CO
CJ
CD
4-»
O
41
Si
t **
j
t *4-
73 O O
C CJ
co »e
Cl
X 4-
Vt t- '
a: o c
3C tO Cl
- e.
* >
z cu ci
a. 4.
« 3 c
CA *
cc
t- - 0
3 0) J
c *
*
in co <
I L.
0 CU ».
^ a v
0
O CO c
4-1 <
-O cn c
O i
II CJ Cl
j
CJ C- c.
3 0
co ;
u *
/N f
c
CO CO 4.
a c
H-
O O C
o
1 4
«- cn *
O 41 7
in .c £
4-* C
o
0 <
c t
0
CO >
3 O 1-
in
i
ro
i. «-
9
i
w *~J
a cu
^ 4-*
} CO
J U
11 4->
i tn
4>
cu
3 4->
c
e
r
o
0
' 73
J C
CO
D
: 4)
J -4-
U
>
< CO
0 4)
o in
_ ,»
- c
= 0
C 73
4)
3 tn
: co
0 CO
,
u >
J i-
: 41
D >
o
3 0
0 4>
: a
^
CO
A 4-*
1) -
< a
0 CO1
ej
4-1
C
41
U
c_
CU
a
cu
E
3
E
4- 0
CA u. CJ >
L. u-o cn
CO O -
- ~ - VI
-^ « CU 4-f CO
o cu t- <- o)
73 O t- 3 C
v* 3 4-> 3 CU
1^ O 4J CO 3
CO >» CO t. 1
OK *^ C- CU CU *4-
r- O CU Q. Q.
c- o Q. E C
l_ X «- E CU 4) -
4>L- ^s.L. >^ 4)4-'4->
J3>- *»JZ t- 4JC04-1
e *** **. ) to u c
41 f>» --Q CO CO 4)
o cn *L- o coo>34->
0) - 4->XZ O) O C
OCfl CA*^ i O O
4-* OCU*y> c 4I3M-CJ
C tn u 4-> ^ 3
.^O C co* -4- cn cu
U OC-C-CAt-41 4- CDC-
73 .- O 4^ X 4JO)3
4> c«cn4-'j3Ccn'^ cn 4-*cu *->
4-> o u co co o o Vt o cu < 4) tn
CO Si I ' O 4J 3
E CO C CU 4-> .* C 3 O
r- ' D Q- CU CJ X « OH-E
4-> O O 41 4-- 4-< ^
tn O)*- c i tn 4-> u u u u
4) COH-COCUO D
O C CJ O 1
CU 4J L. CU C_ 1 *- CO
c_ co eu cn 4-> c- 4-> u i C3
co L- jj c. c cu o cu c otno
CUE34JCU4J '" I I OZ
cn Q. 3 o co co 'Co i 4)
4J O C £ E 3 4) 3 w t»
cn tu
o u u u ii u ii u u .c
0 3
u
' C/> QC LU O£
' «J ac: J t i cj »*
a: OZXZ3UJ3 3
CO J3 U
B-18
-------
TABLE B-15. CONTINUOUS MONITORING COST SUMMARY'
Pollutant
compliance
options
PM only
Acid gas only
PM + acid gas
Method
Opacity5
S0? (inlet and outlet)
HCt (inlet and outlet)
o2/co2
Data Reduction System
Total
Opacity
S0? (inlet and outlet)
HCT (inlet and outlet)
00/C00
-------
TABLE B-16. SITE ACCESS AND CONGESTION FACTORS FOR RETROFITTING
APCD EQUIPMENT AT EXISTING PLANTS
Retrofit Congestion
factor level Guidelines for selecting retrofit factor
1.02 Base case Interferences similar to a new plant with adequate
crew work space. Free access for cranes. Area
around combustor and stack adequate for standard
layout of equipment.
1.08 Low Some aboveground interferences and work space
limitations. Access for cranes limited to two
sides. Equipment cannot be laid out in standard
design. Some equipment must be elevated or
located remotely.
1.25 Medium Limited space. Interference with existing
structures or equipment which cannot be relocated.
Special designs are necessary. Crane access
limited to one side. Majority of equipment
elevated or remotely located.
1.42 High Severely limited space and access. Crowded
working conditions. Access for cranes blocked
from all sides.
B-20
-------
TABLE B-17. PROCEDURE FOR ESTIMATING SCOPE ADDER CAPITAL COSTSa'b
Direct and Indirect Costs
1. New Ducting:
Costs, 103 $ = 1.844 * L * N * RF * Q°'5
2. New I.D. Fan:
Costs, 103 $ = 2.493 * N * RF * Q°'96
3. New Stacks (costs per stack):
o For a lined acid resistant stack,
Costs, 103 $ = [26.2 + 0.089 * H * (1 + 4.14 * D)] for D > 5
Costs, 103 $ = [26.2 + 0.080 * H * (1 + 4.33 * D)] for D < 5
o For a unlined stack,
Costs, 103 $ = [26.2 + 0.0625 * H * (1 + 2.59 * D)] for D > 5
Costs, 103 $ = [26.2 + 0.087 * H * (1 + 2.2 * D)] for D < 5
Contingency = 20% of the direct and indirect costs
Total Capital Costs = Direct Costs + Indirect Costs + Contingency Costs
aAll costs are estimated in December 1987 dollars.
L = duct length per unit, feet
N = number of units
RF = retrofit factor obtained from Table B-16
Q = 125% of the actual flue gas flowrate, acfm
H = stack height, feet
D = stack diameter, feet
B-21
-------
TABLE B-18. DOWNTIME COST PROCEDURE3
Capital Costsb
Loss of Tipping Fees:
Costs, $ =/ME_l*fI£D\ * WDC * HRS * (D-|y12)
Loss of Energy (Steam or Electricity):
Costs, $ = IE2 * ER * HRS * DC * (DT/12)
24
Annualized Costs (Capital Recovery)0
Costs, $ = CRF * Downtime Capital Costs
aCosts are estimated in December 1987 dollars. Apply only to retrofit
applications.
WR = weight reduction of waste in the combustor, percent
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
TPD = plant waste feed rate, tons/day
HRS = hours of operation
DT = downtime, months
ER = energy cost rate, dollars per ton ($24.84/ton for mass burn waterwall
units, $36.16/ton for RDF units, and $19.52/ton for modular and mass
burn refractory units with heat recovery)
CCRF = capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
B-22
-------
TECHNICAL REPORT DATA
(Please read Instructions on the reverse before completing]
1. REPORT NO.
EPA-450/3-89-27a
3. RECIPIENT'S ACCESSION NO
4. TITLE AND SUBTITLE
Municipal Waste Combustors - Background Information for
Proposed Standards: Cost Procedures
5. REPORT DATE
August 1989
6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
8. PERFORMING ORGANIZATION REPORT NO. ;
9. PERFORMING ORGANIZATION NAME AND ADDRESS
Office of Air Quality Planning and Standards
10. PROGRAM ELEMENT NO.
U. S. Environmental Protection Agency
Research Triangle Park, North Carolina
27711
11. CONTRACT/GRANT NO.
68-02-4378
12, SPONSORING AGENCY NAME AND ADDRESS
DAA for Air Quality Planning and Standards
Office of Air and Radiation
U.S. Environmental Protection Agency
Research Triangle Park, North Carolina 27711
13. TYPE OF REPORT AND PERIOD COVERED
Final
14. SPONSORING AGENCY CODE
200/04
15. SUPPLEMENTARY NOTES
16. ABSTRACT
Cost Procedures for the costing of new and existing municipal waste combustor
facilities and associated equipment are presented. Cost procedures are developed
for combustors, heat recovery equipment, humidification equipment, air pollution
control devices for the reduction of particulate matter and acid gas emissions, and
continuous emission monitoring equipment.
Costs in this report are divided into capital costs, operating and maintenance
costs, and annualized costs. Costs associated with retrofitting existing facilities
are also presented.
17.
KEY WORDS AND DOCUMENT ANALYSIS
DESCRIPTORS
b.IDENTIFIERS/OPEN ENDED TERMS C. COSATI Field/Group
Air Pollution
Municipal Waste Combustors
Incineration
Pollution Control
Costs
Air Pollution Control
13B
18. DISTRIBUTION STATEMENT
19 SECURITY CLASS (This Report)
Unclassified
21 NO OF PAGES
166
20 SECURITY CLASS (Tins page)
Unclassified
22 PRICE
EPA Form 2220-1 (Rev. 4-77) PREVIOUS EDITION is OBSOLETE
-------