-------
Table 15. Character of Cooling Water
(Plant B-ll(a))
Alkalinity
COD
Total solids
Total dissolved
Total suspended
Ammonia
Nitrate
Chloride
Fluoride
Aluminum, |J/g
Oil and grease,
PH
Temperature, F
Temperature , C
Intake Water
Municipal
mg/1
95
NA(C)
192
solids 190
solids 2
0.01
0.06
25
1.01
—
Ib/day --
4.5-6.5
NA
Discharge Net loading in Waste-
mg/l(a) water gram/mton(b)
Avg . Average
95
15 172
198 69
180
18 182
1.1 12.5
0.07 0.11
29 46
0.9
0.7 0.008
5 (?) 86
(7.5 mg/1)
4.5-6.5
97-112
36-44
Volume: 80,000 gal/day = 302,800 I/day.
Product: 25-33 tons/day = 23-30 mton/day.
(a) Corp of Engineers data.
(b) fConc effluent - cone intake (mg/1)] x liters/day -,n-3 i -i j- / ^
J 7 ——, \", /J^ -n x 10 J gram/mg = loading, gram/mton
Avg. amount of metal cooled, mtons/day & & E» s>
(c) NA = Not applicable.
43
-------
wet scrubbing system. Water used in the scrubbing thus gains resulting
pollutants and is the source of a waste water stream.
Waste water from A1F3 demagging gas scrubbers can normally be
recirculated because of the relative insolubility of fluorides (which
can be settled out) . Waste Water from the scrubbing of chlorine
demagging fumes, however, can be recycled only to a very limited degree.
This is because the chloride salts are highly soluble and would soon
build up to make water unusable. Thus, the discharge of this effluent
is the source of wastewater from fume scrubbing. Table 16 gives data on
present smelter practices in regard to scrubbing waste water. Of 69
plants surveyed, 46 are demagging their melts. No demagging waste water
discharges are reported from those plants using A1F3. All plants using
chlorine are discharging demagging scrubber wastewate, whether to
navigable waters, public sewage, or holding ponds.
i es . Very few smelters in the secondary industry have reliable
water-use data for their fume scrubbing systems, in one plant, D-6,
water usage measured by the project sampling team was one-third the
usage estimated by company personnel. In general, data given out by the
plants should be used with caution.
Data on the quantities of water used in scrubbing, which were most
consistent in terms of their content, are given in Table 17 . Water
usage is given in liters per kilogram of magnesium removed during the
demagging operation. Basing the water use on magnesium removal provides
a common unit for all smelters. The values in Table 17 are fairly
consistent, with the average water use being 150 liters per kilogram of
magnesium removed.
Characteristics. The character of the raw waste water generated during
the scrubbing of chlorination fumes is given in Table 18. No similarly
detailed data on this waste water was available in the secondary
aluminum industry. The data on plants C-7 and D-6 was obtained by
sending project water sampling teams to the plant sites for
representative samples. The waste water samples were then analyzed for
appropriate constituents.
At plant C-7 fumes were scrubbed in a tower followed by neturalization
and settling of the raw waste water in separate unit operations. This
arrangement permitted sampling the acidic effluent from the scrubber
before it was treated and is one example of raw fume scrubber waste
water collected by a tower. At plant D-6f the fumes were trapped under
a proprietary bell-shaped device in contact with the molten metal and
were scrubbed with water. This arrangement also permitted sampling of
raw untreated waste water from a different method of fume scrubbing.
Simultaneous scrubbing and pH adjustment is considered a treatment and
the treated waste water is characterized in Section VII.
44
-------
TABLE 16. FUME SCRUBBING WASTEWATER - GENERATION
AND DISPOSAL PRACTICES
Practice Number of Plants
• Use A1F- for demagging 14
No air pollution control 5
Dry air pollution control 7
Wet air pollution control 2
- Water recycled continuously 2
• Use Cl for demagging 28
No air pollution control 3
Dry air pollution control 1
Wet air pollution control 24
Wastewater discharged:
- with no recycling 12
- with some recycling 6
- no discharge-continuously recycled 0
- to evaporation pond 7
- with neutralization 17
- with solids removal 12
• Use both A IF., and Cl for demagging 4
No air pollution control 1
Dry air pollution control 1
Wet air pollution control 2
Wastewater discharged:
- with no recycling 1
- to evaporation pond 1
- with neutralization 2
- with settling 2
Total Number of Plants Demagging 46
45
-------
TABLE 17. QUANTITIES OF WASTEWATER GENERATED IN THE WET
SCRUBBING OF CHLORINATION FUMES
Company (code)
C-7
D-6
D-8
C-26
Wastewater Generated
I/kg of Mg
, 95.
182
190
133 <
Removed (Gal/lb)
2 (11)
(22)
(23)
!> (16)
(1) Estimated from data provided by plant on water usage
and rate of Mg removal.
46
-------
TABLE 18. CHARACTER OF WASTEWATER FROM CHLORINATION
FUME SCRUBBING (No Treatment)
C-7
(a)
D-6
(b)
Parameter
COD
Total solids
Total dissolved
solids
Total suspended
solids
Sulfate
Chloride
Cyanide
Fluoride
Aluminum
Calcium
Copper
Magnesium
Nickel
Sodium
Potassium
Zinc
Cadmium
Lead
Manganese
Chlorine residue
Oils and grease
Phenols (ppb)
PH
(a) Average of
(b) Average of
Cone. ,
mg/4
123
2910
1885
225
11
4420
<0.02
0.24
472
0.12
0.25
41.2
0.050
3.11
--
0.952
0.066
0.061
0.449
0.257
13.9
20.7
2.1
three composite
five composite
Loading, ,,
grains /KgMgv '
12.1
301
194 10
22.3
0.51
446 8
° (d)
-0.08*- ;
50.9
-0.215
0.02
3.86
0.003
-0.007
--
0.091
0.006
0.004
0.049
0.027
0.590
-0.002
— ••
samples.
samples.
(c) Loading calculated as: [cone, effluent (rag/A)
Cone. ,
mg/j£
536
,500
480
481
,671
—
0.7
6.12
990
1.31
55.8
0.74
770
206
3.58
0.30
0.24
2.34
6.24
—
1.0
- cone.
Loading,,,
grams /KgMgv
95.8
1856
83.0
84.4
1560
—
-0.324
0.615
176
0.236
9.81
0.106
32.7
37.1
0.64
0.054
0.025
0.349
0.403
™ ™
intake (mg/j6) ] x
quantity of water used (I)
quantity of Mg removed (Kg)
(d) Negative numbers indicate that the process apparently reduced the
concentration of this parameter, and are derived from the reports
of analytical results as shown above.
(e) Analytical methods from Standard Methods for the Examination of Water
and Wastewater, 13th Edition (1971).
47
-------
Table 18 gives both effluent concentrations (milligrams per liter) and
loadings (grams of pollutants per kilogram of magnesium removed). For
almost every parameter listed, the loadings vary widely. Raw waste
waters (averages of composites) gathered during chlorine demagging have
a low pH due to the hydrolysis of anyhdrous aluminum chloride and
magnesium chloride that make up the fume. The hydrolysis forms
hydrochloric acid which accounts for part of the high chloride levels
present without the associated total dissolved solids. The data at
plant c-7 suggests that the chloride in excess of that accountable from
aluminum and magnesium had to come from excess chlorine used during
demagging. A similar imbalance in operation is suggested by the data on
raw waste water for Plant D-6. Unreacted chlorine was measured as
residual chlorine in the raw waste water from plant C-7. The effect of
pH adjustment and settling on the raw waste water from plant C-7 is
described in Section VII.
When chlorine is used for demagging, most of the product is magnesium
chloride during the initial phase of the operation and only a little
aluminum chloride is formed. At the temperature of the molten alloy,
760-780°C (1UOO-1450°F), some of the magnesium chloride is included in
the off gases (which may include unreacted chlorine). As the magnesium
level is decreased, the chlorine flow is decreased but more aluminum
chloride is formed. When chlorination is done within the furnace the
fumes are usually wet scrubbed through a series of towers. When done in
the forewell, the fumes are caught in a bell contacting the molten metal
and scrubbed with a specially designed aspirator mechanism. The
scrubbing is done with and without neutralization of the scrubbing
liquid.
When aluminum fluoride is used for magnesium removal, both magnesium
fluoride and residual aluminum fluoride remain at the surface of the
melt. Both materials are solid at 780°C (1450°F) and exert vapor
pressures of less than 1 torr. They do react with water vapor to yield
hydrofluoric acid. The recovery of the fumes during demagging is done
with fume hoods over the forewell and the gases scrubbed with recycled
water through venturi-type scrubbers.
Chloride fume scrubber water (when not scrubbed with caustic solution)
has a pH of 1.5 and contains hydrolyzed metal chlorides of aluminum,
magnesium, and other volatile metal halides such as zinc, manganese,
cadmium, nickel, copper, and lead. in alkaline scrubber waters sodium,
potassium, and calcium are present with a corresponding reduction in the
amount of dissolved heavy metals and aluminum and magnesium. The pH
range is 9-11.(See Section VII.)
The water from aluminum fluoride fume scrubbing contains HF which is
neutralized with caustic. Any metal fluoride or partially hydrolyzed
fluoride particulates would be expected to react in the scrubber system
to form insoluble fluroides after pH adjustment. The supernatant should
contain fluorides of magnesium and aluminum and perhaps cryolite, all of
48
-------
which are only sparingly soluble. Most of the heavy metal fluorides
associated with the alloying metals may end up in the fumes and
subsequently in the scrubber sludge.
Fume scrubber water generation is intermittent and coincides with the
1.5-4 hour magnesium removal cycle for each heat (every 24 hours). The
water flow rate during the scrubbing ranges between 3,800-12,500 liters
(1000-3300 gallons) per hour producing about the same amount of
discharge. Of the 27 companies practicing wet scrubbing for air
pollution control, scrubbing water is discharged directly (8),
discharged with recycle (3) , discharged after recycling (2) , recycled
continuously (2) (only those using aluminum fluoride for magnesium
removal), discharged to ponds (5), and recycled and discharged to ponds
(2). Twenty of the 27 companies neutralized the scrubber water and 15
make an effort to remove solids as sludge by settling or by filtration.
Waste Water From Residue Processing
Sources. Residues used by the secondary aluminum industry are generally
composed of 10 to 30 percent aluminum, with attached aluminum oxide,
fluxing salts (mostly NaCl and KCl), dirt, and various other chlorides,
fluorides, and oxides. Separation of the metal from the nonmetals is
done by milling and screening and is done wet or dry. When done dry,
dust collection is necessary to reduce air emissions. Milling of dross
and skimmings will produce a dust that when scrubbed wet will contain in
suspension insoluble solids such as aluminum oxide, hydrated alumina,
and soluble salts from the flux cover residues such as a sodium chloride
and potassium chloride. Drosses also contain aluminum nitride which
hydrolyzes in water to yield ammonia. When slags are milled, the waste
water from dust control contains more dissolved sodium and potassium
chloride and fluoride salts from the cryolite, than from drosses or
skimmings. Some of the oxides of heavy metals are solubilized in the
slag and leachable from the dust.
With wet milling the dust problem is minimized but the operation
produces a waste water stream that is similar to the scrubber waters in
make up but more concentrated in dissolved solids contaminants. The
aluminum and alumina fines are settled rapidly and are used to assist
the settling of more-difficult-to-settle components obtained as sludges
from related waste water discharges.
Of the 23 plants recovering aluminum values from residues, 8 use wet
techniques which lead to the generation of highly saline waste waters.
Table 19 lists the general character of these 8 coded plants. Waste
water is generated by wet dust removal systems (dust generated by dry
milling of residue), the washing of residue fractions (sized), and by
wet milling the residue to liberate metallic aluminum. In every case
the waste water is passed into a settling pond before discharge.
-------
TABLE 19. RESIDUE WASTEWATER GENERATION AND DISPOSAL PRACTICE
Plant Codes
Practice D-l D-2 D-3 D-4 D-5 D-6 D-7 D-8
Wastewater generated by:
Wet dust removal system x X
Washing of residue fractions X
Wet milling of residues X X X X XX
Disposal of wastewater:
Discharge with some recycling X X
Discharge to settling pond XXXXXXXX
Chemically treat wastewater to aid settling XX XX
Discharge to navigable waters via settling pond XX X
No direct discharge streams from settling ponds XX XXX
-------
Water use for the wet milling of residues has been based on
the tonnage of aluminum recovery rather than the tonnage of residues
processed. This is because the former quantity is generally known more
accurately by the smelters than the latter.
Table 20 gives available data on the quantity of waste water generated
in the wet milling of residues in liters per metric ton of aluminum
recovered. Values for plants D-3 and D-8 are fairly close, while the
value for plant D-4 is roughly an order of magnitude higher.
Characteristics. The character of waste water generated during wet
milling of residues or residue fractions is given in Table 21. Two
plants, D-4 and D-3, had some analytical data on their waste water from
Corps of Engineers' permits. To provide better characterization of the
waste water, sampling teams were sent to plants D-6, D-8, and D-4 to
gather water samples for analysis.
It is noted from the table that waste water loadings are exceedingly
variable. For example, chloride loadings are 0.32, 326U, and 150 kg/m
ton (0.61, 6500, and 300 Ib/ton) for plants D-3, D-4, and D-8
respectively. This variability is attributed to variation in the salt
content in the residues being processed at the time samples were taken.
If the dissolved salt (chloride) content is low, drosses from primary
aluminum melt operations are being processed (e.g., plant D-3). If they
are high, then slags (and drosses or skimmings) from secondary aluminum
melting operations are being processed (e.g., plant D-4). Some residue
millers operate on a toll based on the amount of molten aluminum
recovered and process both types of residues. Therefore, there are
highs and lows in the dissolved salt content of the waste water
depending on the batch of residues being milled. Nontoll millers
process both types of residues also; low salt residues for their high
aluminum content and home slag for improved aluminum recovery within the
plant. In some cases such plants will also accept slag from secondary
smelters not equipped to process their own. The raw waste water as it
comes from the mill and screening operation contains large amounts of
insoluble solids that settle very quickly. Isolation of the raw
discharge stream to determine the amount of solids present could not be
done but it was estimated that the solids content in the waste water is
about 30 percent by weight. This would be a highly variable value and
dependent upon type of residue being processed at the time. Settling is
a very effective way to remove the insoluble solids. However, there is
variation in a plant's ability to remove suspended solids (compare
plants D-4 and D-8). Milling at plant D-8 is done with a mixed stream
containing 75 percent alkaline fume scrubber water and 25 percent fresh
water. The concentrations reported in Table 18 have been adjusted for
this variation and are reported only as the new gain in concentration
due to milling. The data suggest that milling with an alkaline stream
reduces the ammonia concentration appreciably from that resulting from
milling with unaltered intake water (0.30 mg/1 vs 350 mg/1 for D-4) and
suggests an effective way to reduce the level of this pollutant. The
51
-------
TABLE 20. QUANTITIES OF WASTEWATER GENERATED IN THE WET MILLING
OF RESIDUES PER TON OF ALUMINUM RECOVERED
Wastewater Generation
£/mton of Al recovered
Company (code) (Gal/ton)
D-3 16,690(1)
D-4 218,000
D-8 28,838
(1) From Corp of Engineers' data.
52
-------
TABLE 21. CHARACTER OF SETTLED WASTEWATER FROM RESIDUE PROCESSING
Plants
Parameter
Alkalinity
COD
Total solids
Total dissolved
solids
Total suspended
solids
Sulfate
Chloride
Cyanide
Fluoride
Ammonia
Aluminum
Calcium
Copper
Magnesium
Nickel
Sodium
Potassium
Zinc
Cadmium
Lead
Manganese
Chlorine residue
Oils and grease
Phenols (ppb)
PH
Nitrates
D-3
Loading
(Kg/mton Al)
6.47
0.97
13.51
0.121
0.319
0.129
0.33
0.002
<0.001
0
0.053
8.68
0.032
D-6
Cone .
(mg/.0
314
2,045
12,920
4,961
1,100
6,492
0.04
2.9
0.75
0.3
58.8
0.174
32.5
1.2
2,560
1,087
0.015
0.05
0.20
0.16
55.4
--
8.3
D-4(C)
Cone.
(mg/4)
586
24,264
15
47
15,465
8.7
350
16.4
23
0.070
6
0.240
11,600
6,470
0.10
0.002
0.020
0.045
--
0
--
9.09
Loading., ,.
(Kg/mtonre;
102
5,144
1.5
1.5
3,264
1.81
73
3.5
-7.4
0.008
3.9
0.009
2,528
1,407
0
0
0.004
0.002
--
0
--
D-8(d)
Cone .
(mg/jO
500
29
17,800
17,400
159
151
8,903
0.05
16.5
0.30
28
48
0.137
76
0.20
3,103
4,802
0.198
0.005
0.028
0.060
_-
0.5
0.03
9.2
Loading, ,
(Kg Anton) ^
-7.5(f)
0.17
326
324
-5.6
1.8
150
0
0.38
-0.03
-1.49
0.17
0.003
1.39
0
46.2
102
-9.1
-0.001
-0.001
0
__
0
0
(a) Calculated from U. S. Corps, of Engineers, concentration data not given.
(b) From residue milling solid waste washing, tonnage values of residue waste processed not
available - loading cannot be calculated. Water flow is 151 4pm.
(c) Data from 7 month and 9 month average and verification data from state: metals verified
composite of 18 samples collected over a period of 6 days.
(d) Represents composite of 9 samples collected over 3 days. Milling waste stream is blended
with scrubber waste stream.
(e) Loading calculated as: [cone, effluent (mg/jfc) - cone, intake (mg/jfc)] x
quantity of water used (1)
quantity of Al recovered from residue (mton)
(f) Negative values indicate that the process reduced the concentration of this parameter,
and are derived from reported analytical values.
53
-------
mixed stream is also claimed to be effective in reducing the suspended
load in the pH-adjusted fume scrubber water. The effectiveness is
attributed to the rapid settling of the coarser milling wastes which
carry down with them the hydrated alumina and magnesium hydroxide in the
treated fume scrubber water and the associated heavy metals. Fluoride
in milling waste water is due to the cryolite or aluminum fluoride
contained in the slag (flux cover). The presence of aluminates in the
alkaline milling water acts on fluoride to limit its concentration.
Fluoride content in the slag is also quite variable and depends on the
source of the residue being milled at the time. The concentrations of
fluoride found in the milling waste water are less than those attainable
by the use of lime precipitation.
54
-------
SECTION VI
SELECTION OF POLLUTANT PARAMETERS
Introduction
This section reviews the waste characterizations in Section V and
identifies in terms of chemical, physical, and biological constituents
those parameters which constitute pollutants as for the secondary
aluminum smelting subcategory. Rationale for the selection and
rejection of each of the waste water constituents considered is given.
A list of materials used in the secondary industry is presented and
considered for identifying probable constituents in the waste streams
from metal cooling, wet fume scrubbing, and wet residue milling
operations.
Identificatign_of^Pollutant Parameters
Analytical data on waste water streams generated by the secondary
aluminum industry were limited. To assess the pollutant levels it was
necessary to collect samples from the three types of waste streams
previously identified. The waste water constituents considered were
those most likely to be present in the individual waste streams based
upon an analysis of the raw materials used by the plants in the
subcategory. The raw materials used by the secondary aluminum smelters
are given in Table 22.
Consideration of the materials consumed by the secondary smelters led to
the selection of the following parameters for analysis in the waste
streams sampled:
Alkalinity Copper
COD Magnesium
Total Solids Nickel
Total Dissolved Solids Sodium
Total Suspended Solids Zinc
Sulfate Oil and Grease
Chloride Phenols
Cyanide Cadmium
Fluoride Lead
Aluminum Potassium
Calcium Manganese
55
-------
TABLE 22. MATERIALS CONSUMED BY THE SECONDARY ALUMINUM INDUSTRY
Category
Constituents
Raw Materials
Processing Materials
Water Treatment Materials
Solid Scrap: Al, Mg, Cu, Si, Ni, Zn, Fe,
Pb, Mn, Cd, Ti
Residues: Al, A1203, NaCl, KC1, Na3AlF6,
MgCl2, MgF2, A1C13, A1F3, CaCl2
C12, A1F3, N2, KC1, NaCl, CaCl2,
KJU.F,, H20, Oil and Grease
NaOH, NaC03, various flocculents
56
-------
Chlorine pH
Ammonia
Assessment of the resulting analytical data on the waste water streams
(Section V, Tables 13, 14, 15, 18, and 21) led to the selection of
constituents of pollutional significance.
Cooling Waste^Water
The analyses of cooling waste water streams for three plants are given
in Table 13, 14, and 15, Section V. Examination of the values for the
various parameters show total dissolved solids, lead, and manganese to
be net additions to the stream. Oil and grease also are found in
pollutionally significant quantities.
£U!2§_Scrubbing_Waste_ Water
Analyses of two typical waste water streams from fume scrubbing during
chlorination are given in Table 18, Section V. Examination of the
concentration values shows those listed in Table 23 to be additions to
the stream. The average pH is noted to be between 1 and 2 and is thus a
significant pollutant parameter. Total suspended solids are at a level
potentially reducible by treatment and have been selected as a pollutant
parameter.
Residue Milling Waste Water
Analyses of four residue milling waste water streams are given in Table
21, Section V. Three of these provide concentration levels. The fourth
provides only loading values. From the concentration levels it is
established that those parameters listed in Table 23 are significant
contributions to the water and are considered significant pollutants.
Total suspended solids, although typically low, can be at high levels,
as is the case for plant C-6, and are included as a pollutant parameter.
Ammonia levels and pH are identifiable as contributions from the
process, and are subject to control by currently practicable control and
treatment measures.
Rationale for Rejection of Other W^ste Water
Constituents^as Pollutant Parameters
Waste water from the three unit operations, metal cooling, demagging
fume scrubbing and residue milling were characterized in a limited way
prior to the sampling and analysis completed in this survey. The choice
57
-------
TABLE 23. POLLUTANT PARAMETERS IDENTIFIED
Raw Waste Water
Pollutant Parameters
Cooling
Fume Scrubbing
Wet Residue Milling
Total Solids
Total Susp. Solids
Total Dis. Solids
Chloride
Cyanide
Aluminum
Copper
Sodium
Zinc
Co dm i urn
Lead
Manganese
Oil and Grease
pH
COD
Total Solids
Total Dis. Solids
Total Sus. Solids
Chloride
Aluminum
Copper
PH
Alkalinity
COD
Total Solids
Total Dis. Solids
Total Sus. Solids
Sulfate
Chloride
Magnesium
Nickel
Zinc
Cadmium
Lead
Manganese
Oil and Grease
Sodium
Potassium
Fluroide
Ammonia
Aluminum
Calcium
Copper
Magnesium
Sodium
Potassium
58
-------
of possible pollutant parameters for which analysis were to be made was
based on information supplied to the Corp of Engineers for permits to
discharge under the Refuse Act Permit Program and on an understanding of
the chemistry associated with each operation waste stream. Such
reasoning produced the parameters listed previously from which
pollutionally significant parameters were to be selected. As a result,
some of these parameters were rejected as pollutants because the
constituents were not contributed to the water by the operation. The
constituents rejected on this basis are listed in Table 24 for each of
the raw waste water streams.
Selection of Pollutants for Effluent
Limitations
The control and treatment technologies discussed in Section VII describe
current practices by the industry that are used to treat some of the
selected pollutants in each type of raw waste water. From these
discussions it was concluded that current practice for the treatment of
residue milling waste water can control only the amounts of suspended
solids, pH, fluoride, heavy metals, COD, and ammonia. Dissolved solids
are not treatable by current practice of the industry or by projected
practice foreseen before 1977. Therefore, only the pollutants listed in
Table 25 have effluent limitations recommended. Effluent limitations
for total dissolved solids, sulfate, and chloride were not recommended
since treatment of the pollutants is beyond the scope of the best
practicable control technology currently available and because of cost
availability of the technology.
Current practice by the industry to treat waste water from scrubbing
fumes from chlorine demagging is to adjust the pH of the stream to
neutralize the acid and to reduce the amount of metals in solution by
precipitation as hydroxides. The soluble salts present in the raw waste
water are not treatable by current technology. Therefore, only the
pollutants listed in Table 25 have effluents limitations recommended.
Total solids, total dissolved solids, chloride, magnesium, heavy metals,
sodium, and potassium are not the subject of recommended effluent
limitations. For all but aluminum, magnesium and heavy metals,
treatment of the pollutants is beyond the scope of the best practicable
control technology currently available as defined by the Act because of
cost and availability of the technology.
The aluminum, magnesium, copper, nickel, zinc, cadmium, lead and
manganese that are present in raw fume scrubber waste water can all be
precipitated as hydroxides by adjustment of the pH of the waste water to
between 7.5-8.5. The effect of the treatment is presented in Section
VII. There is an optimum pH for precipitation of each metal that
results in its greatest removal by settling. The pH selected for this
mixture of metals is a compromise between maximum removal of aluminum as
aluminum hydroxide and maximum removal of heavy metal hydroxides with
aluminum hydroxide (and magnesium hydroxide). Therefore, it is
59
-------
TABLE 24. WASTEWATER CONSTITUENTS REJECTED
AS SIGNIFICANT WASTEWATER PARAMETERS
Raw Wastewater Stream
Constituent Rejected
Cooling Water
Fume Scrubbing
Wet Residue Milling
Alkalinity
Fluoride
Calcium
Magnesium
Nickel
Ammonia
Sulfate
Cyanide
Fluoride
Phenols
Alkalinity
Cyanide
Nickel
Zinc
Cadmium
Lead
Manganese
Oil and Grease
60
-------
TABLE 25. POLLUTANTS SUBJECT TO EFFLUENT LIMITATIONS
Treated Wastewater Stream
Pollutant Under
Effluent Limitation
Wet Milling of Residues
Fume Scrubbing
pH
Total Suspended Solids
Fluoride
Ammonia
Aluminum
Copper
COD
pH
Total Suspended Solids
Oil and Grease
COD
61
-------
concluded that with appropriate pH adjustment and settling of solids,
aluminum, magnesium, and the associated heavy metals will be removed
from solution to levels consistent with the best practicable control
technology currently available. However, there is insufficient data on
treated fume scrubber water to base effluent limitations and standards
for all the metals.
62
-------
SECTION VII
CONTROL AND TREATMENT TECHNOLOGY
Introduction
The control and treatment technology for reducing discharge of
pollutants in waste water from metal cooling, fume scrubbing, and
residue milling is discussed in this section. The discussion includes
control and treatment alternatives for each type of waste water stream
and identifies process modifications to reduce or eliminate the
discharge of water.
Waste_Water From Metal Cooling
The major pollutants in the waste water generated during the cooling of
ingot molds containing molten alloy are oils and greases and suspended
and dissolved solids. The oil and grease used to lubricate mold
conveyor systems are washed from equipment as the ingots are sprayed
from the underside with water. The water is collected in a pit which is
drained to a sump. The dissolved solids and suspended solids are
attributable to poor housekeeping in the area of the cooling pit. In
those operations where cooling water is spray-cooled before recycling,
dust is removed from the air in the vicinity of the plant. The
production of deoxidizer shot differs from ingot cooling in that the
molten metal shot contacts the water as it is quenched. During the
quench some aluminum reacts with the water to eventually form a sludge.
Typically, cooling waste water is discharged by the secondary aluminum
smelters without prior treatment. It has been found more practical by
many of the smelters to control the discharge of cooling waste water
through continuous recirculation or by adjusting water flow so that
total consumption (evaporation) takes place. Others have avoided water
usage completely through the use of air cooling.
Contrgl^Alternatiyes
The amount of waste water generated from metal cooling can be reduced by
recirculation and cooling. A waste water discharge could be eliminated
by adopting a concept of either total consumption through regulated flow
or air cooling. However, the latter two alternatives are not suited to
smelters producing deoxidizer shot.
63
-------
Recirculation. Of 58 secondary smelters canvassed which generate
cooling waste waters, 15 are recirculating the water continuously with
no discharge whatever. Seven others are recycling the cooling water but
discharge the holding tanks periodically, usually at 6-month intervals.
The reason for the discharge is to permit sludge removal from cooling
towers and pits. A flow diagram for a recirculating system is given in
Figure 4.
Discussions with smelter personnel have indicated that it is possible to
discharge the cooling water into an auxiliary holding tank, to permit
sludge removal from the main system. The water could then be returned
to the system after sludge removal.
Installation of a recirculation system involves the construction of a
cooling tower, possible enlargement of the cooling pit, an auxiliary
holding tank, associated plumbing, and necessary pumps. The size and
cost of these facilities would depend on the production capacity of the
smelter. Generally, this type of equipment has been engineered, built,
and installed by smelter personnel. Because of this it is difficult to
obtain accurate cost data. Estimates have run from $2000 to $5000 for
the spray cooling, water storage pit, pumps, and associated plumbing to
provide enough capacity for a smelter with an output of about 0.454
million kg (1 million Ib) of alloy per month.
Maintenance on the recirculation system is largely due to sludge
buildup. This involves approximately 4 man-days every 6 months. Very
seldom are any maintenance problems mentioned in connection with the
recirculatory system itself. The amount of sludge buildup appears to
vary from plant to plant. Those that do not have a sludge problem claim
to recirculate their cooling water continuously and must replenish the
water that has evaporated. They attribute the sludge buildup by others
to poor housekeeping more than removal of solids from the air. Similar
comments were made about dissolved salts; however, as their
concentration increases, the only recourse would be to discharge the
cooling water. Oil and grease accumulation would appear to be
unavoidable. However, at these higher concentrations of oil and grease,
removal by skimming is facilitated. Use of more expensive greases that
melt at higher temperatures and are less prone to erosion have been
suggested as a means of controlling this pollution problem.
tion °.f Cooling Water^ Of the 58 smelters using cooling
.
water, three have reduced the flow rates such that the water is
essentially totally evaporated by the hot ingots. As such, no waste
water is generated. Specially designed nozzles exist to give a water-
mist spray that reduces the steam-to metal interface. However, these
nozzles are inclined to get plugged with dirt and thereby present a
maintenance problem. Such approaches require longer conveyors to assure
that the ingots have cooled sufficiently to be handled.
-------
Pt3
E* «q
§ «>
•3 a
W -H
O ij
•^ o
S o
B -d o
°'S*>
g 8>
@ 5
H
en
>•
c/i
P5
W
5
SS
O
o
u
s
g
g
n
§
o
W
Pi
w
1
o
H
en
£
-------
Air_Cooling. Of the 69 secondary smelters canvassed, 13 are air cooling
their ingots and sows. Air cooling is accomplished by conveying the hot
ingots through an air tunnel fitted with entrance and exhaust blowers.
The conveyors need to be approximately twice the length of water cooling
conveyors. Maintenance is higher on the air-cooled system because of
the longer conveyor, the added heat load on the lubricants, and the
additional blower motors. In some cases a water mist is added to the
air to improve the cooling rate. The water is completely evaporated.
Treatment_Alternatives
The waste water from cooling operations requires treatment to remove the
oil and grease and suspended solids before discharge. This holds for
once-through water and for recirculated water. As in most treatment
processes, it is less difficult to treat waste water with high
concentrations of pollutants than those with low concentrations.
Therefore, treatment of recirculated water would be preferable.
Oil_and_Grease. Specialized skimming devices are available for the
removal of oil and grease pollutants from water. Grease (and oil) traps
can reduce the levels so that such specialized equipment is not
overloaded since the latter are made to operate efficiently at low
levels of oil and grease on the surface of water.
66
-------
Solids Separation. Both dissolved and suspended solids are added to the
cooling waste water. Removal of suspended solids requires settling
which is very slow at low concentrations but can be made more rapid at
high concentrations. The components of the suspended solids are
primarily aluminum hydroxide or hydrated oxide which are known to be
excellent coagulants. Recirculation of cooling water will build the
suspended solids level to concentrations great enough to effect rapid
settling between cooling operation cycles. Sludge is removed periodic-
ally, usually every 6 months. However, others have claimed no need to
remove sludge since buildup was not detected. The supernatant water is
of sufficiently good quality that it can be pumped into a holding tank
during sludge removal from the settling tank or pit and then reused.
The latter procedure appears to be more in line with a process that
evaporates water and which is constantly replenished. For example, a
settling tank or pit with about 37,850 liters (10,000 gallon) capacity
and a holding tank of comparable size would be required to supply water
for a 15 metric ton per day (17 ton) ingot casting operation. Billet
"direct chill" cooling and shot cooling require, typically, about a
3.785 million liter (1.0 million gallon) capacity system.
Sludge from the settling tank which amounts to about 757 to 7,570 liters
(200 to 2000 gallons) every 6 months is disposed of in sanitary sewers,
storm sewers, lagoons, ponds or simply dumped onto slag destined for
land disposal or reprocessing. Since the sludge is primarily hydrated
alumina, the nonwater environmental impact is considered to be
negligible. Disposal in land fills after dewatering by filtration would
be the ultimate means of sludge disposal. The filtrate would be
recycled or discharged to the sanitary sewers.
Waste Water From Fume Scrubbing
The fumes formed during chemical magnesium removal must be controlled to
reduce air emissions to acceptable levels. Wet scrubbing techniques
have been employed for this purpose and take numerous forms, some of
which are considered to be proprietary. The discharge from these wet
fume scrubbing devices contains most of the volatile metal salts
entrained in the gas flow, when chlorine is used for magnesium removal,
aluminum chloride and magnesium chloride are the principal constituents
while chlorides of the other alloying elements are also found due to
entrainment. When aluminum fluoride is used for magnesium removal the
principal volatile products may be silicon tetrafluoride and hydrogen
fluoride which is formed from the high-temperature hydrolysis of the
slightly volatile fluoride salts reacting with moisture in the air. In
both cases the air pollutants are transferred into water pollutants. In
the case of chloride fume scrubbing, the salts are mostly soluble in
water. In the case of fluoride fume scrubbing, the salts are only
slightly soluble, but the hydrolysis product, hydrogen fluoride, is very
soluble.
67
-------
Control Alternatives
Control of air emissions during magnesium removal can be done dry as
well as wet. Dry emission control techniques must contend with rather
corrosive gases for both types of magnesium removal. Anhydrous chloride
salts hydrolyze to produce hydrogen chloride gas which in turn reacts
with water vapor to form hydrochloric acid. Hydrogen fluoride and
hydrofluoric acid are formed only at high temperatures; however, once
formed, they remain in the gases being scrubbed.
Fume_Contro1. Three processes exist for reduction and/or removal of
fumes without major use of water either in the process or in fume
control. These are the Derham process, the Alcoa process, and the
Teller process.
The Derham Process. The Derham process includes equipment and
techniques for magnesium removal, with chlorine, from secondary aluminum
melts with a minimum of fume generation and without major use of water
in either the process or in fume control. The principal concept is the
entrapment of magnesium chloride, the reaction product of magnesium
removal, in a liquid flux cover, with the flux being subsequently used
in the melting operations.
The elements of the Derham process are indicated in Figure 5. The
principal components consist of a separate bath of the metal to be
treated with its special flux cover, and means to circulate the molten
metal to and from that separate bath.
The treatment bath may be integral with the smelting furnace or separate
depending on whether the particular installation is a new facility or
the equipment is being installed on existing equipment. The molten
metal circulation from the main furnace hearth to the Derham unit is
accomplished by pumping (usually with an air-driven siphon) rather than
by less direct methods such as mechanical stirring or nitrogen-gas
sparging or agitation. The molten metal brought to the treatment unit
is treated in the usual manner with gaseous chlorine to achieve
magnesium removal, resulting in the generation of molten magnesium
chloride as the reaction product. By maintaining a relatively thick
cover of molten salt on the bath in the treatment unit, the emissions of
aluminum chloride to the atmosphere usually produced by demagging are
nearly completely arrested. As the flux cover becomes saturated with
respect to magnesium chloride, it is removed and may be used as a flux
in the main melting furnace. The flux is usually cast into cakes.
After grinding it may be used as a covering flux at the charging well of
the melting furnace.
Any gaseous effluents from the treatment unit are blended with the
combustion gas effluent and released to the stack. Emission control
requirements vary, and may be satisfied by blending the gases. In
situations requiring particulate control with baghouses, the chloride
68
-------
Slag (Metal Recovery
'' or Discard)
REVERB
SCRAP CHARGE • • .... •j MEL
FUR
y ,
i
MAT T17M ___.
ERATORY
TING
NACE
1
1
-
METAL DERHAM f
£*TRrtTT ATTfiM PPtV^co ^""T
t> "*" UN
i '
FLUX CONtAiNING
MgCl2
NEW
(NaGl
IT - ^__
FLUX '
, KC1)
/"
COMBU
GA
/
PRODUCT ALLOYS
1
STION
SES
.
CHLORINATION
GASEOUS
EFFLUENTS
GASEOUS CHLORINE
•> TO STACK
OR SCRUBBER
FIGURE 5. SCHEMATIC DIAGRAM OF ELEMENTS OF THE DERHAM PROCESS
69
-------
emissions, although hygroscopic, are usually dilute enough not to inter-
fere with baghouse operation.
Associated engineering features reported for this process include the
significant reduction of fuel requirements and melting time resulting
from metal circulation. Heat transfer rates from the center hearth to
the charging well are increased so that temperature gradients are
decreased. The usual gradient was quoted as being 200°F between
charging well (1300°F) and melt (1500-1600°F). With metal circulation
this is reduced to 150°F. The increase in melt rate was quoted as at
least 20 percent.
The efficiency of chlorination is reported to be nearly stoichiometric
down to 0.1 percent magnesium in the melt. This is better than ordinary
chlorination rates which are 50-60 percent efficient at the lower range
of magnesium content. No adverse effects on product quality are
reported. One user, employing the process for degassing only (rather
than demagging), reports improved metal quality in the application of
the process in an extrusion plant.
The Derham process is generally satisfactory in terms of meeting air-
pollution restrictions. Although a back-up scrubber may be desirable
under stringent regulations and/or transient process conditions the
loading should be very low. Water use would not be completely
eliminated but recycling of water could be done more easily.
The Alcoa Process. The Aluminum Company of America is providing for
licensing a "fumeless" demagging process that claims 100 percent
efficiency in chlorine utilization for magnesium removal. It recovers
molten magnesium chloride as a product. At present it is being used in
England for captive scrap processing. The unit is installed between the
holding furnace and a casting machine and removes magnesium continuously
as the metal flows through.
The operation uses no flux salts and attains the high chlorine
efficiencies through extended gas residence times achieved by employing
gas-liquid contactors. For very dirty scrap a short period of
prechlorination in the furnace is necessary to improve fluxing. The
system has been operated on a commercial scale at an alloy flow rate of
5900 kg (13,000 Ib) per hour with a magnesium removal rate of 27 kg (52
Ib) per hour. Magnesium content was reduced from 0.5 to 0.1 percent.
Coated Baghouse (Teller) Process. Baghouses have not been effective in
the removal of fumes from demagging operations. Blinding occurs during
collection of submicron particulates. These particles enter the
interstices of the weave and create a barrier to gas flow. When
blinding occurs, the pressure drop rises rapidly and gas flow
diminishes.
70
-------
The Teller modification of baghouse operation has been described in
varying detail since the inventor considers most information proprietary
(Teller, 1972). Only one system has been installed at a secondary
aluminum smelter. Basically the system differs from a normal baghouse
in that the bags are precoated with a solid to absorb effluent gases as
well as particulates, supposedly without blinding. Upon saturation, the
coating is removed along with the collected dust by vibration. A fresh
coating is then applied. The collected particulate and spent coating
are to be disposed of in a landfill. The system is suited for
collection of emissions from operations using aluminum fluoride for
demagging. A prototype has been installed in such a facility where its
performance is being evaluated. The evaluation program is also to
establish its effectiveness for the collection of emissions from
operations using chlorine for demagging.
The proprietary system, in the case of fluoride emissions from glass
furnaces, is based on simultaneous filtration and chromatographic
absorption and baghouse recovery. The chromatographic solid is injected
into the gas duct and is then separated from the gas in a baghouse. The
solid serves as an absorbent for acid gases and as a baghouse precoat to
prevent blinding. The reactive carrier coats the bags and acts as a
filtration precoat. It breaches rather than blocks the interstices and
acts as the actual filter, using the bag surface only as a support.
This is the principle of the precoat action.
The chromatographic material consists of a monomolecular layer of
reagent on a reactive carrier. In one application, the carrier cost was
estimated to be $30 per metric ton. In the absorption of hydrogen
fluoride, it can provide one transfer unit in 0.0254 cm (0.01 inch)
depth of the chromatographic material. With a duct line injection rate
of 0.454 to 0.908 kg per 280 cu m (1 to 2 Ib per 10,000 cu ft) of gas,
80-90 percent removal of hydrogen fluoride occurred in the duct and 99
percent in the baghouse collector.
The recovered solids consisting of the original chromatographic
material, neutralized gaseous fluorides, and the particulates from the
operation can either be recycled, if the discharge is compatible with
feed material being charged to the operation, or it can be removed to a
landfill.
In order to apply the Teller process to specific secondary aluminum
operation, the nature and the variability of the emission with the types
of scrap, and/or the ratio of scrap types being charged as well as the
rate of magnesium removal must be established. To be comprehensive such
a study would require considerable expenditure.
Treatment Alternatives
71
-------
Of the 69 facilities canvassed, 46 use demagging to prepare alloys (see
Table 26). Of these, 29 employ some form of wet scrubbing to control
air emissions. Three use aluminum fluoride and 26 use chlorine for
demagging. A number of the smaller volume operations have delayed
installing wet air pollution control devices until water standards are
more clearly defined. In one case, a wet scrubber system has been
employed for smoke abatement since restrictions on fuel consumption have
ruled out the use of afterburners. No demagging was done at this plant.
Removal of fumes formed during demagging from the air by wet scrubbing
techniques transfers the pollutants to water. Disposal and treatment
prior to disposal or reuse are dictated by the method used for magnesium
removal from the molten metal. When chlorine is used, the anhydrous
salts hydrolyze during scrubbing to form acidic solutions of chloride
salts which even after neutralization preclude re-use of the water
continuously without buildup of high levels of salt concentration. When
aluminum fluoride is used, scrubbing of the fumes with water produces
fluorides in solution which, when subsequently treated, can assure the
formation of slightly soluble salts that do not increase their
concentration in water, making continuous recycle of water possible
after settling.
Discharge practices and treatment practices used on both types ot waste
water are given in Tables 27 and 28 and are described in the following
sections.
Chloride Fume-Scrubber Waste Water. The water from fume scrubbing
operations using chlorine for demagging are highly acidic due to the
hydrolysis of aluminum chloride and magnesium chloride. Four plants are
discharging directly into sanitary sewers without treatment. Three
discharge into sewers after neutralization, and four after
neutralization and solids removal by settling. Such an effluent pro-
vides at no charge a source of partially soluble aluminum and magnesium
salts which are suitable for coagulation and precipitation treatment.
Neutralization to a pH of 6.0-7.0 will precipitate most of the aluminum
and magnesium as hydroxide. Coprecipitation of heavy metal hydroxides
also occurs. The effectiveness of neutralization is diminished if too
much alkali is added since dissolution of aluminum hydroxide occurs at
about pH 9. The data presented in Table 29 indicate that this is true.
When neutralization follows the scrubbing as is shown in the flow
diagram of the treatment of chloride scrubber water in Figure 6, not all
of the aluminum is precipitated when the pH is raised to 9.0-9.2. This
could be in part due to over treatment with alkali causing dissolution
of the aluminum hydroxide. The scrubbing operation is done directly
with an alkaline solution at plant D-8 and the data suggest that
aluminum loading is high due to the high pH. The heavy metals are
decreased; however, due to the high pH, the total solids and sodium
loading is increased. Smelter personnel using pH-control
72
-------
TABLE 26. MAGNESIUM REMOVAL PRACTICE (DEMAGGING)
USED BY SECONDARY ALUMINUM INDUSTRY
Chemical
Used
Number of Smelter
Plants Using
Magnesium Removal
Number of Smelter
Plants Using Wet
Scrubbing to
Control Emission
During Demagging
Aluminum
Trifluoride
14
Chlorine
32
46
(a)
26
29
(b)
(a) Of this total, 4 use both methods for magnesium removal.
(b) Of this total, 2 use both methods for magnesium removal.
73
-------
TABLE 27. TREATMENT OF EFFLUENTS FROM FUME
SCRUBBING (DISCHARGED AS NOTED)
Number
Treatment
Effluent Control
Discharge Directly
No Recycle
With Recycle
After Recycle
Total
Discharge to:
Stream
Sanitary Sewer
Total
of Smelters Using Given Practice
Neutralize
Solids Removal Solids
Neutralize C^ AlFo Removal
2 5 1
3 -
1 1 -
3 90 1
1 4 -
3 41
4 81 0
No
Treatment
4
-
-
4
-
4
4
-------
TABLE 28. TREATMENT OF EFFLUENTS FROM FUME
SCRUBBING (NO DISCHARGE)
Number of Smelters Using Given Practice
Neutralize
Solids Removal
Treatment
Neutralize
CL
AlFo
Solids
Removal
No
Treatment
Effluent Control
Recycled Continuously
Discharge into Pond
Recycle and Discharge
to Pond
Total
2
1
75
-------
CJ
H
O
nJ
w
5;
*2
w
H
3
O
^_l
CQ
g
PC
o
en
g
C5
2
rH
i-i
H
CO
O
<2
z
o
C_|
H
O
H
W
fc!
•
CN
W
03
«3
H
•O
0)
C
E
a
b
0
M-l
O
01
^
•^
c
CO
4.
^
"c
c
MH
O
E
c
}-.
oC
to
b
c
r^
Cl
o
a>
^
0)
c
k*
00
Q
4->
3
CO
i— 1
*
vO
O
-
0
t-H
^^
t-l
-4
(U
CO
to
U
^,
1
U
4-1
C
to
I
f*^
M
HI
to
CO
U
^^
7
^j
4-
c
n
PL,
4J
C
01 fiO
B C
4J •!-)
(0 r-l
(11 4J
M 4J
H V
cn
•H
F-4 O
to Z
I—I
4J
C
(U
B
4J
(U
H
0
Z
4J
O
(4-1
a
4J
0)
z
4->
C
(11
6
4J
CO
(U
Jj
H
^
.
O ON i— 1 CO
rH 01 W
•H O -H 3 r
^(iQ4J4-J4JrHi— ICQ 3 3r-
rH O O O O 3 J2 >>t-4 rH C(
^Ot^EHfHC/lUUCi-t^lt.
OO CO>—(OO OLA
• . o . . . . j O * •
O ^D ON rH O O O 1 O O>
ON
rH
COr-tO o oo o ooor-
CM i-H 1 rH
d" rH 1 | II
1 vO
CM
O OO 00 in ON rH ^D CM
rHrHO inOOrH CMO
OOO OOOO iH,£!!E
O^SUlMCJt-JSUOPH Ou
-------
32 gpm
SCRUBBER
SYSTEM
NaOH
soln
REACTION TANK
JFloc. Ageat
MIXING TANK
SETTLING TANK
Sludge to dump
-&• SEWER
CEKTRIFUGE
FILTER
FIGURE 6.. CHLORIDE FUME SCRUBBER WASTEWATER TREATMENT (NEUTRALIZATION-SETTLING)
77
-------
instrumentation for alkali feed claim that they are unreliable and
require frequent maintenance. Under conditions of failure, over-
neutralization occurs.
The effluents from chloride scrubbers are also discharged into streams.
Four smelters neutralize and remove solids by settling before
discharging into navigable waters. Two discharge With recycling and two
discharge directly after neutralization and settling to remove solids.
Effluents are also discharged to ponds with impermeable to semipermeable
surfaces both with and without neutralization. Solids are removed
periodically after evaporation of the water. One practice is to recycle
the neutralized water through the scrubber until it is too difficult to
pump. The slurry is then discharged to the pond. Another practice is
to employ a settling tank for neutralization from which the supernatant
is discharged into the evaporation pond and part of which is recycled to
the scrubber as needed. The settling tank was drained weekly into the
pond in order to remove the sludge accumulation of 625 liters (165
gallons). The flow diagram of a facility employing an evaporation pond
in this manner is shown in Figure 7.
Aluminum Fluoride Fume-Scrubber Water. Three of the 14 smelters using
aluminum fluoride for magnesium removal use wet scrubbing for emissions
control. Two of the three recycle the water continuously and neutralize
the solution with sodium hydroxide. The other plant also neutralizes
the waste water, but since both chlorine and aluminum fluoride were used
at this plant, the effluent is discharged to a lagoon.
The continuous recycle system shown in Figure 8 scrubs the emissions
with a venturi-type scrubber followed by a packed tower and demisting
chamber. The waste water is collected in a settling tank where it is
treated with 5 percent caustic to neutralize hydrogen fluoride formed
from hydrolysis. The sodium fluoride formed reacts with particulate
aluminum fluoride carried with the emission to form insoluble cryolite.
The magnesium fluoride, which may also be carried with the air stream,
cryolite, and other insolubles are separated in settling tanks and the
alkaline supernatant is recycled to the scrubber system. The plant
personnel claim there is no water discharged except that removed with
the sludge which is discarded in landfills. The installation was
designed for operation on one furnace, but plans are to use the system
for the three remaining furnaces. Special retractable panels are being
installed to improve air flows over the forewell for emission control.
Until these improvements are made the system remains idle.
Waste Water From Residue Milling
Water is used by 6 of the 23 smelters that process residues to recover
metallic aluminum values. Depending on the nature of the residue being
78
-------
Fresh Water
SCRUBBfifi
Caustic
RECYCLING
TANK
10,000 gal
sediment
Process Wastewater
overflow 40
drain once a week
recycle
Remove 3i 55 gallon
drums of sludge each
week approx. kQ - 50^
solids after draining
150 gpm
POND
FIGURE 7. CHLORIDE FUME SCRUBBER TREATMENT (PARTIAL RECYCLE AND EVAPORATION POND DISCHARGE)
-------
w
w
Pi
H
§
H
w
H
CO
?H
CO
Pi
§
O
CO
w
w
o
h-1
Pi
o
£3
,-J
3-
1
s
\
\
\
\
\
N
s
\
s
\
oo
w
Pi
3
80
-------
milled, the amounts of dissolved solids and insoluble solids in the raw
waste water vary. When the residues are slags from secondary smelters,
the waste water is very high in dissolved salts. When the residues are
drosses or skimmings from primary or foundry sources the amount of
dissolved salts in the waste water is greatly reduced; however, the
insoluble solids fraction in the dross approaches 70 percent by volume.
At most residue milling facilities, both types of residues are handled
and both types of raw waste water are generated from the same milling
operation. Waste Water is also generated from the wet control of dust
from a dry milling operation and the production of a low-salt, high-
aluminum product from the solid waste from the dry-milling of residues.
The product is used for "hot tops" in the steel industry.
Current Practice
Waste Water generated during wet milling of residues is treated in
settling ponds in which the insoluble materials are removed. No control
of the dissolved salts is practiced by two plants discharging into
streams and one discharging into municipal sewers, but the suspended
solids are reduced to low levels by those ponds. Some dissolved salt
control by evaporation is claimed by those discharging the waste water
into lagoons. Four smelters with waste water from residue milling use
such lagoons.
In one plant, all milling residues less than 60 mesh are discharged for
treatment in settling ponds. The first stage of a four-stage pond
system is treated with a polyelectrolyte to improve settling. A fourth
settling pond with skimmers discharges the clear overflow into the
midcourse of the receiving stream. The sludge from the fourth stage is
recycled back into the first pond and is removed with the aid of the
material passing through 60 mesh. The insoluble residue is disposed of
through sales or through an industrial disposal contractor. Residues
stored outside are subject to leaching by the rain and the runoff is
directed into the plant drainage ditch and the fourth pond.
In another operation shown in Figure 9 (Plant D-8), the discharge from
the milling operation containing the insoluble materials after metallic
aluminum was removed is used to accelerate settling of alkaline scrubber
solutions from chloride fume scrubbing waste water discharged into the
same ponds. Because of the mixing occurring in the waste water circuit,
the benefits of this treatment on scrubber waste water loading could not
be determined.
Control Alternatives
The alternative to wet residue milling and resulting waste water
treatment is dry milling of the residues. Seventeen of the 23 residue
processors practice dry milling to eliminate water contamination.
81
-------
BAY WATEE 50 gpm
aECIRCULATED
150 gpm
volume varies with type
DEDSS MILL
ZOO"r~Z2a
gpn gpm
alkaliae cvertreeted.
POKES;(3)
20 gpa
DEMAft FOME
SCHU3BEE
[Pumped & Metered
BAY
VATER
30,000 gpd
SODA ASH
SLUHHT
FIGURE 9. RESIDUE MILLING AND ALKALINE CHLORIDE FUME SCRUBBER WASTEWATER TREATMENT SYSTEM
82
-------
Impact mills, grinders, and screening operations are used to remove the
metallic aluminum values from the nonmetallic values. The high levels
of dust formed in these operations are vented to baghouses. The
baghouse dust and the nonmetallic fines from the screening constitute
the solid waste from the operation. These are stored on the plant site
on the surface of the ground. Attempts are made to control the runoff
by containing dissolved salts in drainage ditches, contamination of
surface and subsurface waters are unavoidable as the solid waste
handling is practiced now. Markets for the "field leached waste" are
developing in the cement industry since the waste consists mostly of
impure aluminum oxide. The purity is claimed to be too low for use as a
substitute for bauxite ore.
Those practicing dry dross milling in areas where land for solid waste
disposal of the waste is limited, as in municipalities, are using the
services of industrial waste disposal contractors.
Treatment_Alternatives
Wet milling of primary aluminum residues and secondary aluminum slags by
a countercurrent process is claimed by certain segments of the industry
as the only way to reduce or possibly eliminate salt impregnation of
ground and runoff water from the discarded solid waste. By using a
countercurrent milling and washing approach, two advantages could be
realized. The final recovered metal would be washed with clean water
providing a low-salt feed to the reverberatory furnaces. The waste
water with the insolubles removed would be of a concentration suitable
for economical salt recovery by evaporation and crystallization. Heat
for evaporation could be supplied by the waste heat from the
reverberatory furnaces. The process would have to contend with the
ultimate disposal of the dirt, trace metals, and insolubles recovered
from the brine which should contain very low levels of soluble salts.
Such salt recovery installations are operating in England and
Switzerland and the salts recovered help pay for the operation since
they are reusable as fluxing salts in the secondary aluminum industry.
Such a system has not been put into practice in the United States,
although groundwork for research in the area appears to be developing.
83
-------
SECTION VIII
COSTS, ENERGY AND NONWATER QUALITY ASPECTS
Introduction
This section deals with the costs associated with the various treatment
strategies available to the secondary aluminum industry to reduce the
pollutant load in the water effluents. In addition, other nonwater
quality aspects are discussed. Since the entire secondary industry is
engaged in recycling scrap aluminum, it represents significant savings
in natural resources both in terms of aluminum ore (bauxite) and in the
reduced pollution and energy consumption represented by a ton of
secondary aluminum vs a ton of primary aluminum. These aspects of the
industry therefore alleviate the nonwater quality environmental impacts
identified for each method of control of waste water cited in this
section.
Because of the nature of the secondary industry, the cost data obtained
are lacking in some details. Often the equipment and operating costs
have been combined with other portions of the process. Where data were
lacking, engineering estimates were made. All costs are expressed in
terms of metric tons. Costs per ton are ten percent higher.
Basis for Cost Estimation
Capital Investment
Where possible, data on equipment costs and total capital were obtained
from the secondary aluminum processors. These capital investments were
changed to 1971 dollars by the use of the Marshal and Steven's Index
(Quarterly values of this index appear in the publication Chemical
Engineering, McGraw Hill.). In addition, where cost data were not
available, equipment costs were estimated from published data (Peters
and Timmerhaus, 1968). The total capital investment was then calculated
as this cost plus:
Installation 50% of equipment
Piping 31% of equipment
Engineering 32% of equipment
Electrical Services 15X of equipment
Contractor's Fee 5X of equipment
84
-------
Contingency 10% of equipment.
Qperating_Costs
The extent of operating cost data available from the secondary
processors was usually limited to raw materials and maintenance
costs. In order to put all operating costs on a common basis, the
following procedure was used to calculate annual operating cost
items:
Raw material cost - as reported
Maintenance - as reported or estimated as 5% of total
plant cost
Depreciation - 10% of the total capital
Interest - 8% of total capital
Tax and Insurance - 1% of the plant cost.
Waste Water From Metal_Cooling
Control Costs
There are esentially two means for effecting waste water control: (1)
recycle the cooling water using a cooling tower to remove the heat in
the water, and (2) perform the ingot cooling in air, avoiding the use of
water altogether.
In a recycle system, there will be a build-up of dissolved solids, and
some suspended solids, oils and greases, and sludge. Because of this a
blowdown is carried out about twice a year, typically amounting to 1,000
gal. In present practice this blowdown is discharged. However, it is
technically feasible to perform total evaporation on this blowdown.
It is relatively inexpensive to convert a once-through ingot cooling
line to a recirculation system. A capital cost of about $0.43/annual
ton of aluminum with an operating cost of $0.15/ton would be required.
Elements in this cost calculation include pumps, settling and slime-
settling basin and the cooling tower. The operating cost does not
include savings resulting from the lowered freshwater use. In order to
perform a total evaporation of the blowdown from the cooling tower, a
capital cost of $0.30/annual ton and operating cost of $0.05/ton would
be added to the costs for the recirculation system.
Addition of an air-cooling process necessitates longer conveyor lines
and the installation of blowers. The cost of the air- cooled ingot line
relative to the base cost of a once-through cooling system, however, is
dependent on whether the plant is to be newly constructed or if a change
85
-------
from water-cooled to air- cooled is considered. In the first case, the
smelter is faced with only the difference in initial costs between water
cooling equipment and air cooling equipment ($3.I/annual ton). However,
the smelter with an existing water-cooled line essentially is faced with
an investment for the total air-cooled line ($9.2/ton).
Operating costs for the two cases are air cooling, $2.25/ton, and water
cooling $1.09/ton. Again, no credit has been claimed for the water
saving. Another consideration is the fact that an air- cooled ingot
line would result in an additional energy consumption of about 11
kwhr/ton.
Treatment_Costs
Water from ingot cooling lines contains large amounts of oil and grease
and dissolved solids. The suspended solids content is about 250 - 500
mg/1, approximately half the concentration of the oil and grease and
dissolved solids. Treatment of this stream could be done by an "API"
separator, which would remove about 75% of the oil and grease (Patterson
and Minear, 1971) and probably about 50% of the solids. The equipment
consists essentially of a lagoon with a skimming device. This treatment
costs about $0.08/annual ton capital, and $0.07/ton operating.
Cost Benefit
A summary of the cost-benefit relationship of control and treatment
systems for waste water from metal cooling is shown in Table 30. The
data (capital cost) are plotted as Figure 10. Several points can be
noted from the data presented in Table 30. A zero discnarge of effluent
water can be achieved by two means, recycle of the cooling water and
evaporation of the blowdown from the cooling tower in an evaporator, or
the use of air to cool the ingots. It is apparent that of the two, the
recycle scheme is the most economical, requiring a capital outlay of
less than $l/annual ton. The one advantage of air cooling is that there
is no water use, whereas water cooling does result in a water
consumption of about 55 gal/ton (cooling ingot from 1,500° to 100°F).
However, the saving in the cost of water does not justify the use of air
cooling to reach a zero discharge from an economic standpoint. In
addition, the energy requirements of an air-cooled line are higher, and
the air cooling cannot be used for shot cooling.
It is concluded, therefore, that it is possible to perform the cooling
step and to achieve a zero discharge of water, either by recirculation
or by air cooling, costs involved would add about $0.15 to $1.0/ton to
the cost of the aluminum produced.
86
-------
TABLE 30. COST BENEFIT OF CONTROL AND TREATMENT
FOR WASTEWATER FROM METAL COOLING
Discharge
Oil and Dissolved Suspended Costs
grease Solids Solids Capital; Operating;
kg/ton kg/ton kg/ton $/annual ton $/ton
Once-through cooling 1.2 0.12 0.63 0 0
Recycle cooling water 0.5 0.12 0.13 0.4 0.1
Recycle cooling water 0 0 0 0.7 0.2
with evaporation
Oil Separation 0.4 0.12 0.33 0.1 0.1
Air Cooling (total) 00 0 9.2 2.3
Air Cooling (A water) 0 0 0 3.0 1.1
87
-------
CVJ
c
o
M
W
4J
c
-------
Waste Water From Fume scrubbing
Control Costs
The three processes in present use for the control of water effluent are
the Derham Process, the Alcoa Process, and the use of A1F3 as a
demagging agent.
The equipment cost of the Derham Process was obtained from the licensing
company (Andrews, 1973) as between $5,000 and $10,000 for a production
rate of 5,450 tons of aluminum/year. Addition of other capital items of
installation, piping, etc., at an average cost of $7,500 results in a
total capital requirement of $3.U/annual ton. The capital equipment
includes the molten aluminum pumps, an additional holding furnace, and
other items necessary for conversion of a standard demagging operation
to the Derham Process.
The licensing company claims that several cost savings to the secondary
smelter would result when the Derham Process is used. The major savings
claimed are:
(1) The reported chlorine usage is 3 kg/kg of magnesium removed,
in lieu of the value of 3.5 kg/kg found in conventional
demagging operations.
(2) An increase in melt rate of 20%.
The operating cost of $2.5/ton calculated for the Derham Process
includes the savings expected as a result of the two claims above.
However, because of the present uncertainty as to whether the Derham
process may meet all air pollution control standards, the costs for this
alternative have also been calculated for two possible cases of scrubber
use. If the Derham process were applied in a small treatment unit (the
recommended method) a relatively small volume of gases would need to be
scrubbed. This case was calculated on the basis of a caustic scrubber
treating 500 actual cubic feet per minute of gases at 150°C (300°F) and
gave additional increments of costs amounting to $0.55/annual metric ton
capital cost and $0.13/metric ton operating cost. If the backup
scrubber for the Derham process treated all the gases (i.e., combustion
gases and demagging fume combined), the cost of the larger scrubber
would be higher. This case is calculated on the assumption that there
are some operational factors such as lack of space or very stringent air
pollution control conditions that would lead to the use of the scrubber
on the combined gases. The conditions assumed for this case were a
caustic scrubber with capacity to treat 11,000 actual cubic feet per
minute at 650°C (1200°F) giving a capital cost of $2.23/annual metric
ton and an operating cost of $0.54/metric ton (i.e., over and above the
costs of the Derham process itself).
89
-------
The equipment cost of the Alcoa 503 process was obtained from the
licensee (Demmler, 1972). The equipment cost includes the basic
reactor, the salt-tapping vessel, and the metal-tapping vessel. The
calculated capital investment for a 17,000-ton capacity installation was
$5.9/annual ton.
The operating costs were calculated based on information provided by the
licensee. These represent a difference between the cost of the Alcoa
503 process and those of the usual fume scrubber operation. The total
operating cost was calculated to be $2.9/ton. The Alcoa 503 process is
an entirely a dry process. No water is used for fume control.
The third method of water control is by the use of a wet scrubbing
system in conjunction with A1F3 as the demagging agent. The major
advantage of this scrubbing system over a conventional chloride fume
scrubber is the ability to recirculate the water used for scrubbing.
The fluoride is precipitated with caustic in the recycle loop. It is
claimed that total recycle can be effected, which would result in zero
discharge of water. However, as the process is relatively new, rhere is
not enough operating experience to determine whether a small bleed
stream would be required. For the purposes of this report, it was
assumed that total recycle is being accomplished.
The capital cost of equipment was obtained from the equipment supplier
(Waki, 1973) and includes the cost of the scrubber, packed tower,
neutralization facilities, thickening tanks, and associated pumps. The
total capital required is about $14/annual ton of aluminum. An
operating cost of $5.t/ton has been calculated for the A1F3 process.
This cost includes the additional expense of using A1F3, rather than
chlorine, as the demagging agent.
Costs associated with another control technique for fume control process
(the "Tesisorb") have been calculated based on data from a fluoride
control installation in a glass plant (Teller, 1972). These costs were
$27.7/annual metric ton capital and $7.3/metric ton operating. Because
of the proprietary nature of the process, the elements involved in this
cost estimate have not been given. The technical feasibility of this
process applied to fume control in a demagging operation has not been
sufficiently established, although it does have the advantage of
resulting in a zero water effluent discharge from demagging fume control
operations.
Treatment Cost§
The method of treatment of scrubber water in use at the present time is
neutralization and settling. Costs for this operation are estimated at
$2.8/annual metric ton capital and $1.50/ton operating. The equipment
cost includes the neutralization facility, settling pond, and associated
-------
pumps, piping, controls, etc. The costs of caustic and polyelectrolyte
accounts for about 1/3 of the total operating cost to neutralize and
settle scrubber water.
Cost Benefit
A summary of the effluent loadings and costs for the treatment and
control models is given in Table 31. It is readily seen that the Derham
Process gives the best cost benefit. Of the other two dry processes,
the Alcoa 503 is only slightly more expensive; however, the installation
of the Tesisorb system would result in higher costs.
Waste Water From Residue Milling
Control_Costs
At the present time, the only technically feasible means of removing the
soluble constituents from the waste is evaporation. The alternative
control measure is to perform the residue milling dry.
The costs for evaporation are dependent on the amount of soluble salts
in the residue being milled. The capital cost to evaporate the water
from a low salt-content residue (dross) is $16/annual metric ton with
operating costs of $24/ton. The major equipment included in the capital
cost of evaporation is an evaporator and crystallizer. Tne heat
required for the evaporation amounts to about 70 percent of the total
operating cost in this cost, assuming a cost of $0.50/million Btu. In
the case of a residue with high salt content (slag), operating costs
would be very high (greater than $300/ton) due to the large amount of
heat necessary for evaporation. For economic feasibility in the case of
water discharged from slag wet milling, some means must be used to
increase the salt concentration in the water and lower the water use
before evaporation can be considered.
Treatment Costs
Settling treatment in practice has been found to be 99.9+ percent
effective in removing the suspended solids. Dissolved solids, however,
are not removed at all. Costs reported from one plant were $8.7/annual
ton capital, and $3.3/ton operating, corresponding costs reported from
a second plant were $15.3/annual ton and $10.9/ton. The reason for the
substantial difference in costs between the two plants is related to the
amount of water use. In the first plant, the residue is primarily
dross, with a low salt content, and consequently, a water use of only
29,000 liters/ton (7,000 gal/ton). However, in the second, the water
used for the wet milling operation is 217,000 liters/ton (52,000
91
-------
TABLE 31. COST BENEFIT OF CONTROL AND TREATMENT
FOR WASTEWATER FROM FUME SCRUBBING
Waste Loads,
grams/kg MR Removed
Process
Suspended Dissolved
Solids Solids Al Mg pH
Costs
Capital Operating
$/Annual ton* $/ton*
Once-Through 175
Scrubbing
Neutralize ^50
and Settle "*
A1F Process 0
Derham 0
Process
Derham
Process
with small
scrubber**
Derham
Process
with large
800
500
0
0
50 5
40 1.0
0 0
0 0
1.5
9.1
* Ton = metric ton = 2200 Ib.
** Insufficient data available to characterize effluents.
0
2.8
14.0
3.4
3.9
0
1.5
5.4
2.6
2.7
scrubber**
Alcoa 0
Process
Tesisorb 0
(Teller)
5.6
0 0 0 5.9
0 0 0 - 27.7
3.1
2.9
7.3
92
-------
gal/ton) because of the higher salt content of the residue (slag) which
is milled in this plant.
Cost Benefit
The data on cost benefit are presented in Table 32. It is evident from
this data that control costs to reach a zero discharge are very high.
The only economically feasible method of attaining zero discharge of
water is for new sources to install a dry milling operation in lieu of
wet milling. At this point, however, evaporation cannot be ruled out
completely because of the potential to reduce costs by countercurrent
milling and selective crystallization of saleable salts. On the other
hand, the cost to remove the suspended solids is moderate, and
represents less than half the economic burden of evaporation.
93
-------
TABLE 32. COST BENEFIT OF CONTROL AND TREATMENT
FOR WASTEWATER FROM RESIDUE MILLING
Waste Loads, kg/ton
Process
No Treatment
Settle
Suspended
Solids
720
1.0
Dissolved
Solids
present
present
Costs
Capital
NH,. $/annual ton*
35 0
35 8.7-15.3
Operating,
$/ton*
0
3.3-10.9
Settle and Evaporate,
Low Flow 0 0 0 16 24
Dry Milling 0 0 0 130
* Metric ton of aluminum produced.
94
-------
SECTION IX
BEST PRACTICABLE CONTROL TECHNOLOGY CURRENTLY
AVAILABLE—GUIDELINES AND LIMITATIONS
Introduction
The effluent limitations which must be achieved by July 1, 1977, are to
specify the degree of effluent reduction attainable through the
application of the best practicable control technology currently
available. Such control technology is based on the average of the best
existing performance by plants of various sizes, ages, and unit
processes within the industrial category. Because of the absence of
data on the characterization of waste water by this industry, the
recommended treatment technology and the corresponding effluent
limitations are based on a sampling survey of waste waters from
exemplary plant operations in this subcategory. Consideration must also
be given to:
(a) The total cost of application of technology in
relation to the effluent reduction benefits to
be achieved from such application
(b) The size and age of equipment and facilities
involved
(c) The processes employed
(d) The engineering aspects of the application of
various types of control techniques
(e) Process changes
(f) Nonwater quality environmental impact (including
energy requirements)
The best practicable control technology currently available emphasizes
treatment facilities at the end of a manufacturing process. It also
emphasizes the control technologies within the process itself when they
are considered to be normal practice within the industry. Other
technology currently available was considered for its degree of economic
and engineering reliability.
95
-------
I ndustry Category and Waste Water Streams
The secondary aluminum smelting subcategory is defined as that segment
of the aluminum industry which recovers, processes, and remelts various
types of aluminum scrap to produce metallic aluminum alloy as a product.
Although primary aluminum producers recover captive scrap generated from
their own operations, they are not included in this subcategory. The
secondary smelters buy scrap in various forms on the open market as
their raw material.
A more useful approach for the purpose of developing effluent
limitations guidelines is to deal with the waste water streams
themselves. The principal streams are (1) waste water from metal
cooling, (2) waste water from fume scrubbing, and (3) waste water from
residue milling. Each stream has an associated loading of pollutants
per pound of product or scrap processed. For example, the recommended
guidelines require a smelter generating only cooling waste water to meet
the effluent limitations established for that waste stream. A smelter
generating cooling, scrubber, and residue milling waste waters would be
required to meet the effluent limitations established for each
respective waste water stream.
Waste Water From Metal Cooling
S££lugQt_Limitations Based gn^the Application of the
Best Practicable Control Technology Currently Available
The recommended effluent limitations based on the application of the
best practicable control technology currently available is no discharge
of process waste water pollutants.
The achievement of this limitation by use of the control and treatment
technologies identified in this document leads to the complete recycle,
re-use, or consumption of all water within the process, with an
associated result of no discharge of water.
Identification_gf_Best^Practicable Control
Technology__Currently Available
The best practicable control technology currently available for metal
cooling in the secondary aluminum industry is the elimination of water
discharge through the use of the following approaches:
(1) Air cooling of ingots
(2) Total consumption of cooling water for ingot cooling
(3) Recycle or re-use of cooling water for deoxidizer-
96
-------
shot cooling or ingot, cooling
With re-use or recycle of water, the need for sludge removal and oil
removal will be dictated by plant operational procedures and the care
used in controlling contaminants caused by poor housekeeping. Dissolved
salt contamination may be reduced with improved housekeeping and
improved manufacturing procedures. Such precautions would provide for
an extended period of water reuse which approaches that of zero
discharge.
To implement the air cooling method or the total evaporation cooling
method (the air cooling method with water mist added to assist the air
cooling) requires:
(a) The addition of ingot molds to the lengthened
conveyor line
(b) The installation of blowers
(c) In the case of total evaporation cooling, the
addition of special nozzles, flow meters, and
controls to existing water lines.
To implement a recycle system for ingot cooling requires:
(a) The addition of a cooling tower, holding tanks,
and pumps to the existing water cooling facility
(b) Provisions for oil and grease removal
(c) Provisions for sludge removal, dewatering, and
disposal.
Rationale for Selecting the Best Practicable
Control Technology Currently Available
Thirty-one of the 58 plants canvassed (or 54 percent) are cooling ingots
by one of the methods given above. Existing cooling lines using once-
through water cooling could be converted to one of three alternative
methods to eliminate the discharge of water. Shot cooling will continue
to require direct water cooling and only the last option above, (c), is
available to these plants.
Age and Size of Eguipment_and Facilities. As set forth in this report,
general improvements in production concepts have encouraged
modernization of plant facilities throughout the industry. This,
coupled with similarities of waste water characteristics from metal
cooling for plants of varying size, substantiate the identification of
total recycle of cooling and/or consumptive cooling as practicable.
97
-------
Total Cost of Application^in Relation to Pollutant Reduction. Based on
the information contained in Section VIII of this report, a capital cost
of about $O.H3/annual metric ton of aluminum alloy would be required to
convert an existing once- through cooling systems to a recirculation
system. An operating cost of $0.15 per ton would be required but does
not include savings resulting from the lowered fresh water use.
Conversion to an air-cooled ingot line from a water-cooled line is
estimated to require an investment of $9.2 per ton. Operating costs
would be $1.09 per ton with no credit being claimed for water savings.
Engineering Aspects of Control Technique Application.
This level of technology is practicable because over 54 percent of the
plants in the industry are now achieving effluent reductions by these
methods. The concepts are proven, available for implementation, and may
be readily adopted by adaptation or modification of existing production
units.
. This technology is an integral part of the whole cost
saving and waste management program now being implemented within the
industry. While the application of such technology requires process
changes, they are practiced by existing plants in the industry.
Environmental lID£§£ii There are four possible
associated impacts upon major nonwater elements of the environment:
(1) An incremental addition to the thermal load of
the plant by thermal radiation from air cooling
of ingots.
(2) Added electrical energy requirements of about 11
kwhr per ton would be needed for air cooling oper-
ations.
(3) Negligible impact on air quality is anticipated
from water evaporation either from consumptive
water-mist cooling or from sludge drying.
(4) Solid waste disposal of dried sludge would be a
minor impact because of very small amounts accumu-
lated, and its nontoxic character (A12O3) . Oil
and grease collected during recycled water cooling
operations may be disposed of through responsible waste oil
disposal contractors.
Waste Water From Fume Scrubbing
Ef fluent Limitations^Based^on the Application_of^the
Best Practicable Control Technology Currently Available
98
-------
The recommended effluent limitations based on the application of the
best practicable control technology currently available are given in
Table 1 for waste water generated during magnesium removal with
chlorine. The recommended effluent limitation based on the application
of the best practicable control technology currently available is no
discharge of process waste water pollutants for waste water generated
during magnesium removal with aluminum fluoride.
JRationale^fgr Effluent Limitations Based on the Application
of the Best Practicable Control Technology Currently Available
The values given in Table 1 were derived as follows:
(1) The 30-day-average value for total suspended solids is the
average of the values given in Table 29 (namely 284 gm/kg and
66 gm/kg) for Cases I and II of Plant C-7. These two values
are considered the most representative available. It may be
noted that both these "after treatment" values are higher than
the suspended solids values in the untreated waste. The
increase in values during treatment is due to the fact that
neutralization produces fine particles of reaction products
which add to the suspended solids values.
(2) Similarly, the 30-day-average value for Oil and Grease is the
average of the two values (O.U and 3.5 grams/kg) from the same
effluent values (Plant C-7, Cases I and II) given in Table 29.
(3) The 30-day-average value for Chemical Oxygen Demand is the
average of the two values (6.1 and 6.8 grams/kg for the same
effluents (Plant C-7, Cases I and II, Table 29).
(4) The 30-day-average ranges of pH given in the limitations are
those estimated to provide the optimum conditions for
acceptable pH and co precipitation of both heavy metals, such as
copper, and amphoteric elements such as zinc and aluminum.
Practicable Control
_
Technology Currently Available
The best practicable control technology currently available for control
of the discharge of pollutants contained in fume scrubber waste water is
the following:
(1) When chlorination is used for magnesium removal,
adjustment of the scrubber effluent pH to between
7.5 and 8.5 followed by settling for solids removal.
Prior adjustment of the pH of the scrubber liquor
so that the resultant effluent from the scrubber
is at a pH of 7.5 to 8.5 followed by settling for
solids removal is equally practicable.
99
-------
(2) When aluminum fluoride is used for magnesium re-
moval, adjustment of the scrubber effluent pH to
between 7.5 and 8.5 followed by settling for solids
removal. (In practice this treatment is an integral
part of the control technology discussed in Section
X.) After neutralization and settling, the super-
natant is recycled continuously. Solid fluorides
are removed continuously.
The fume-scrubber water from the chlorine magnesium removal process,
upon pH adjustment, cannot be recycled continuously due to excessive
buildup of sodium chloride. Partial recycle of the clarified treated
effluent will reduce water consumption.
The use of neutralization and settling treatment to remove pollutants
from chloride scrubber waste water requires reaction tanks for pH
adjustment, mixing tanks for polyelectrolyte addition (if settling is
not rapid), a settling tank for solids removal, and associated pumps,
controls, and plumbing.
The implementation of continuous recycle of fluoride scrubber waste
water will require the additions of liquid storage and pumping
capabilities. A chain conveyor for continuous solids removal also would
be required.
Rationale for Selecting the Best Practicable
Control Technology Currently Available
Of the 29 plants using wet scrubbing to control air emissions 20 (or 69
percent) are practicing some form of pH adjustment. Of these 20, 15 (or
51 percent) are removing solids by settling.
The adjustment of pH to 7.5 to 8.5 and settling are effective in
removing aluminum and magnesium ions as hydroxides from chloride fume
scrubber waste water. Some removal of heavy metals as hydroxides also
occurs with the removal of the aluminum and magnesium hydroxides. At a
pH of 9.0 or greater aluminum hydroxide and other amphoteric metal
pollutants are dissolved. Therefore, to maximize the overall metal
removal, the pH generally should not exceed 8.5. (See Discussion,
section VI and Table 29, section VII.)
An adjustment of pH to 7.5 to 8.5 is effective in reducing the
solubility of fluorides by neutralizing the hydrogen fluoride in the
effluent. Acid fluoride salts are more soluble than the neutral
fluoride salts of the common pollutants in fluoride fume scrubber waste
water. The limited solubility of the neutral fluoride salts in water
provides a supernatant solution suitable for recycle in scrubber
operation.
100
-------
§iS.e of Eguipjnent and Facilities^ Those segments of the
industry that are refining aluminum alloys must remove magnesium to
attain the specifications of their customers. Therefore, regardless of
the size or age of the facility, chemical removal of magnesium is
practiced. Control of air emissions from demagging operations with wet
scrubbers also is practiced by a majority of the secondary aluminum
smelters. Control of the pH and solids content of the effluent from the
scrubber is also practiced. In such cases, investments would have to be
made for sludge disposal. In a large tonnage secondary smelter,
scrubber equipment is used continuously and requires larger treatment
facilities than a smaller tonnage plant. A small plant may require
treatment capacity for operations lasting only four hours per day. The
capital investment for treatment equipment per annual ton would be
greater for the smaller plant. However, the similarities in the fume
scrubber waste water generated in each type of magnesium removal process
(chlorine or aluminum fluoride), regardless of the size or age of the
facility, substantiate the level of pollutants that can be removed by
the pH adjustment-settling treatment.
Those plants using aluminum fluoride for magnesium removal can, by using
the same technology, eliminate the discharge of pollutants by adapting
the system to completely recycle the supernatant after settling.
Total Cost of Applicatign^in Relation^to Pollution__Reduction. Based on
the information contained in Section VIII of this part of the report, a
capital cost of about $2.75 per annual metric ton of aluminum alloy
produced would be required to install a pH adjustment-settling treatment
capability to control pollutant levels from the chloride scrubber
systems. An operating cost of $1.5 per metric ton is estimated for such
an installation. Lesser capital expenditure would be required by those
already neutralizing the scrubber effluent.
For those plants using aluminum fluoride for magnesium removal,
treatment of the scrubber waste water requires, in addition to
neutralization and settling, a means to recirculate the scrubber water
continuously and continuous solids removal. This would require an
estimated capital investment of $9.9 per annual metric ton and an
operating cost of $2.US/metric ton.
Engineering Aspects of Control_Technigue Applications. This technology
is practiced by over 51 percent of the plants in the industry to reduce
the discharge of pollutants from fume scrubbing operations. The
concepts are proven and are available for implementation. They can be
adopted to fume scrubbing effluent streams by those presently not using
them as an end-of-pipe treatment facility.
E£2£§§§_2h§LS3§§• Tne technology of pH adjustment and settling to remove
solids is an integral part of the whole waste management program already
implemented by part of the industry. All plants in the industry use the
101
-------
same or similar demagging processes which produce similar discharges.
There is no evidence that operation of any current manufacturing process
will affect the capability of a plant to implement these end-of-pipe
waste treatment technologies.
Nonwater Quality Environmental Impact. There is only one essential
impact upon major non water elements of the environment. It is the
potential effect on soil systems due to the reliance upon the land for
ultimate disposition of final solid waste from the treatment. The solid
wastes are primarily inorganic and nonleachable. The solid waste from
fluoride recovery potentially can affect ground waters adversely and
should be disposed of in an acceptable landfill to prevent the
contamination of surface or subsurface waters.
Ef fluent mLimitations_Based_Qn_rthe Application of the
gest Practicable Control Technology Current ly^Ayailable
The recommended effluent limitations based on the application of the
best practicable control technology currently available are:
(1) When chlorine is used for magnesium removal,
those presented in Table I in Section II.
(2) When aluminum fluoride is used
for magnesium removal, no discharge
of process waste water pollutants.
Guidelines for_the Application of Ef fluent^Limitatigns
Selection of Production Units^ Effluent limitations specify the
quantity of pollutants which may be discharged from a point source after
the application of the best practicable control technology currently
available. This quantity must be related to a unit of production so
that the effluent limitations can be broadly applied to various plants
in the same subcategory.
The amount of pollutant generated during the chemical removal of
magnesium from a given heat is dependent upon the amount of magnesium
originally present in the charged scrap and the final magnesium content
desired in the metal produced. Judicious selection of scrap entering
the melt will reduce this difference, the length of time required for
chemical treatment, and the amount of chemical required for reducing the
magnesium content to the desired level. These variables in turn estab-
lish the amount of material entering the scrubber water. There are
variabilities in the amount of magnesium removed for a unit weight of
chemical agent. Frequently these are dependent on the furnace operators
102
-------
techniques and/or plant practice and therefore are not suited for a
production unit. An invariant production unit suitable for
determinations of pollutant loadings is the amount of magnesium removed
relative to the amount of metal produced. This can be determined from
the percent magnesium contained in the charge before magnesium removal
and the resultant magnesium content.
The application of this guideline requires the reporting of the number
of pounds of magnesium removed based on the magnesium content of the
melt before magnesium removal, the magnesium content of the product
metal, and the net weight of the metal treated for magnesium removal.
These data are currently a part of company records. Also required are
the flow rate of the discharge water stream from the scrubber system,
and the analyses of the pollutants in that stream.
Waste Water from Residue Milling
Effluent Limitations Based on the Application^nof the
Best Practicable Control Technology Currently Available
The recommended effluent limitations based on the application of the
best practicable control technology currently available is that given in
Table 2 in Section II.
Ratignale_for Effluent Limitations Based on^the^Application
of the Best Practicable^Control Technology Currently Available
The values given in Table 2 were derived as follows:
(1) The 30-day-average value for Total Suspended Solids is that
reported for Plant D-4 in Table 21. This value is used because
it was based on verified, seven-to-nine- month averages of
sampling, and is otherwise considered a valid value on the
basis of plant operations and raw material variation.
(2) The value for fluoride is derived from data for Plant D-8 in
Table 21 and is based on 9 composite samples over a three day
period.
(3) The value for ammonia was derived by using the actual
concentration of ammonia in the effluent from a plant using
exemplary milling practice (0.3 mg/1. Plant D-8, Table 21) and
calculating the loading on the associated flow (200 gpm, or
1,090,080 liters/day) and production (37.8 metric tons per
day). This use of concentration reflects the chemistry of the
reaction during alkaline wet milling. The calculated net
loading of ammonia for Plant D-8 in Table 18 is a negative
value, that is, the discharge water from the alkaline wet
milling operation contained less ammonia than the intake water.
103
-------
The limitation value for aluminum was derived in the same
manner as the ammonia value, i.e., using the concentration of
28 mg/1 for Plant D-8 in Table 21. The same flow, and
production as in (3) were used, giving a value of 1.0 kg/metric
ton of metal recovered.
(5) The values of ammonia, aluminum, copper, and pH are
interrelated. The pH specified is to be achieved with reagents
other than ammonia. However, if an ammonia loading were not
specified, the specified pH value could be present due to a
high ammonia content. Further, ammonia and copper interact to
form chemical complexes whose presence would not necessarily be
reflected in the measurement of pH. Aluminum is specified to
prevent under or over-alkalization.
(6) The value of Chemical Oxygen Demand specified is that listed
for Plant D-3 in Table 21 (0.97 rounded to 1 kg/metric ton).
The source of COD in the effluent has not been fully
documented.
Identification of the Best Practicable
Control^TechnologY^QlJ£renfely-^y§ilgfal?
The best practicable control technology currently available for control
of the discharge of pollutants contained in waste water from residue
milling is the following:
A settling treatment of three to four stages with
partial recycle of the sludge and the clear super-
natant from the fourth stage to the mill. Adjust-
ment of the intake water pH is necessary to reduce
ammonia levels in the waste water during milling.
When milling is done without pH adjustment of the intake water, ammonia
remains in solution as a pollutant. To aid the settling of the milling
wastes, a polyelectrolyte is frequently added to reduce the level of
suspended solids. Recirculation of the sludge in the last settling pond
to the mill will reduce the overall sludge content of the final pond.
alg_fQ£_Selecting the Best Practicable
__
Control Technology Currently Available
Only 6 of the 23 plants (or 26 percent) processing residues use water
for milling. Of these, only three are discharging to navigable waters
after treatment in such ponds. The remaining three use total
impoundment.
settling is capable of reducing settleable and suspended solids to very
low levels. Dissolved salts are not removed, however.
104
-------
Evaporation and crystallization, although a viable alternative for salt
removal, is not currently practiced in the United States. The principal
reason is that the cost of salt recovery (for flux cover use) exceeds
the price of the salt, even if more concentrated salt solutions were
attainable through process changes. The alternative to discharge is
total impoundment.
Age and _Size._of Equipment and Plant. Regardless of the size and age of
the facility, the waste water generated from residue milling is similar.
All plants are practicing the same type of waste management. Loadings
do vary with techniques employed and the amount of molten metal re-
covered from the operation. Modernization of this segment of the
secondary aluminum industry has already reduced the number of smelters
processing residues for metal value recovery to 23 plants. Since 17 of
the 23 plants process the residues dry, this trend is expected to
continue. The life of the equipment in the wet mill is 2 to 3 times
longer than equipment in dry mills because of the lower energy
requirements needed for comminution.
Total Cost^in^Rela tion_to^ Pol lution_ Reduction
Based on the information contained in Section VIII of this report, a
capital cost of about $8.7 to $15.3 per annual metric ton of alloy
recovered as molten metal and an operating cost of $3.3 to $10.9 per
annual metric ton to treat residue waste water by settling is estimated.
Variations in the cost are dependent upon (1) the amount of water used
for milling and (2) the solids content of the residue.
Engineering Aspects of Control Technique Application^ This level of
technology is practiced by three of six plants which process residues by
wet methods. The concepts are proven and are reliable for
implementation.
E£2.C-§.§.§._CJ2§.!12§.§ • Only minor process changes are foreseen. The practice
of partial recirculation of the treated effluent is currently used by
two plants in the industry.
NQELwater 2Uaii£Y. Environmental Impact^ There is no added impact upon
major nonwater elements of the environment by the adaptation of settling
for removal of suspended solids. An impact on soil systems currently
exists due to the reliance upon land for the ultimate disposition of the
final solid waste from a wet residue milling operation.
Guidelines for thA^Q Effluent Limitations
Effluent limitations specify the quantity of pollutant which may be
discharged from a point source after the application of the best
practicable control technology currently available. This quantity must
be related to a unit of production so that the effluent limitations can
105
-------
be broadly applied to various plants in the same category, regardless of
their production capacity.
The amount of pollutants in the waste waters from residue milling
largely depends upon the source of the residue. Residues from primary
smelters, foundries, etc. (dross, skimmings) contain little, if any,
soluble salts and up to 40 percent recoverable metal. Residues from
secondary smelters (slags) contain high levels of soluble salts (KCl,
NaCl) and as little as 5 to 10 percent metal.
The production unit used for effluent limitations is the amount of
molten metal recovered from the residue. The information required for
the application of this guideline includes the weight of metal produced
(currently a matter of routine record), the rate of flow of the effluent
from the residue milling operation, and the concentrations of the
pollutants in that flow.
106
-------
SECTION X
BEST AVAILABLE TECHNOLOGY ECONOMICALLY
"ACHIEVABLEf GUIDELINES AND LIMITATIONS
Introduction
The effluent limitations which must be achieved by July 1, 1983, are to
specify the degree of effluent reduction attainable through the
application of the best available technology economically achievable.
This technology can be based on the very best control and treatment
technology employed by a specific point source within the industry
category or subcategory or technology that is readily transferable from
one industry process to another. A specific finding must be made as to
the availability of control measures and practices to eliminate the
discharge of pollutants, taking into account the cost of such
elimination.
Consideration must also be given to:
(a) the age of the equipment and facilities involved;
(b) the process employed;
(c) the engineering aspects of the application
of various types of control technologies;
(d) process changes;
(e) cost of achieving the effluent reduction
resulting from the technology;
(f) nonwater quality environmental impact (including energy
requirements) .
The best available technology economically achievable also assesses the
availability in all cases of in-process controls as well as the control
or additional treatment techniques employed at the end of a production
process.
A further consideration is the availability of processes and control
technology at the pilot plant, semi-works, or other levels, which have
demonstrated both technological performances and economic viability at a
level sufficient to reasonably justify investing in such facilities.
Best available technology economically achievable is the highest degree
of control technology that has been achieved or has been demonstrated to
107
-------
be capable of being designed for plant-scale operation up to and
including no discharge of pollutants. Although economic factors are
considered, the costs for this level of control are intended to be top-
of-the-line of current technology subject to limitations imposed by
economic and engineering feasibility. However, best available
technology economically achievable may be characterized by some
technical risk with respect to performance and with respect to certainty
of costs and thus may necessitate some industrially-sponsored
development work prior to its application.
Waste Water frgm_Metal_Cooling
The effluent limitations attainable by the application of the best
available technology economically achievable for cooling waste waters is
no discharge of process waste water pollutants to navigable waters as
developed in Section IX. The best available technology economically
achievable is identical to the best practicable control technology
currently available.
Waste Water from Fume Scrubbing
Identification^of^Best^Available Technology Economically Achievable
The best available technology economically achievable is the use of in-
process and end-of-process controls and treatment. to achieve no
discharge of waste water pollutants into navigable waters. This can be
done using one of the following approaches:
(1) The use of currently available processes for fumeless
chlorine magnesium removal
(2) Using a combination of AlF3^ for demagging and continuous
recycling of scrubbing water from emission and effluent
control systems
(3) Using a combination of A1F3 for demagging and a coated
baghouse system for air pollution control.
Fumelgss Chlorine Demagqing Processes.. The process developed by Derham
and the process developed by Alcoa are techniques for removing magnesium
from molten aluminum scrap with a rrinimum of fume generation through the
efficient use of chlorine. No water is used for fume control but a
back-up scrubber may be required with the Derham system.
108
-------
In the Derham Process a thick cover of fluxing salt over the molten
metal almost completely arrests fume emissions and the subsequent need
for wet scrubbing for their control. Details of this process are given
in Section VII.
The Alcoa process operates on a similar principle, using efficient
chlorination of magnesium to minimize emissions. The unit is inserted
between the casting line and the furnace and demagging with chlorine
takes place as the metal is being cast.
AlF^Magnesium_RejrtO^aJL_with_Cont^uous_Recirculation_of Scrubber __ Water.
The use of A1F3 for removing magnesium from molten aluminum scrap is
advantageous in that it permits fume scrubbing waste water to be
continuously recycled. This is because the fluoride salts are
relatively insoluble and can be settled out. The same approach for wet
scrubbing fumes from chlorine demagging for emission control is not
possible because of the dissolved solids build-up.
A1F3 Magnesium Removal Fume Control With the Coated Baghouse (Teller^
Process^ In this process fumes from A1F3 magnesium removal are
controlled by passing them through chemically-treated filters (bags)
which remove the pollutants from the exhaust. The system eliminates the
use of water for fume control.
Ra t iona le _f or _S e 1 e ct in g_ Be_s t_ Available Technology
Economically Achievable
Available for Achieving Effluent Limitation. The effluent
limitation of no discharge of process waste water pollutants from fume
scrubbing is required before July lr 1983. This allows sufficient time
for the planning, purchasing, installation, and trial operation of
equipment needed for the three control alternatives identified.
Cost 2f_ Achieving the Effluent Limitations^ The estimated cost of
achieving the effluent limitations from fume emission control will
depend on which of the three techniques given above is used. The use of
the Derham Process for magnesium removal involves an estimated capital
expenditure of $3.4 per annual metric ton of capacity and an estimated
operating cost of $2.5 per metric ton. The Alcoa Process has been
estimated to require a capital cost of $5.9/annual metric ton and an
operating cost of $2.9/metric ton (with no credit being taken for
selling the magnesium chloride) . The use of A1F3 for magnesium removal
combined with continuous recirculation of scrubber water for emission
control involves an estimated capital expenditure of $14.0 per annual
metric ton and $5.4 per metric ton operating costs, use of chemically-
treated baghouse systems (Teller System) for removal of air emission
during magnesium removal with A1F3 was similarly estimated to require a
109
-------
capital expenditure of about $27.7 per annual metric ton of capacity and
an operating cost of $7.3 per metric ton.
Aspects of_ Control Technique Application. The engineering
practicability of the Derham Process is demonstrated by its present use
in the industry. Currently, the process is under license or operating
at four plants within the U. S. and in four plants outside the U. S. In
a telephone canvass of the secondary industry several plants indicated
that they were considering using this process. Both the Derham and
Alcoa processes will require extensive research and development efforts
to meet their limited capacity (Alcoa) and to reduce their reliance on
back-up scrubbers (Derham) to meet air quality standards.
The use of A1F3 for demagging with continuous recirculation of scrubber
water is considered achievable because two large plants in the secondary
industry are using this technique for emissions and effluent control.
The use of chemically-treated baghouses (Teller System) for dry air
pollution control during A1F_3 demagging is yet unproven from an air
quality standpoint. One major plant in the secondary industry has
installed the system and is presently evaluating its effectiveness.
Process __ Changes. The application of the Derham Process or the Alcoa
Process for magnesium removal would require those plants using A1F3_ to
change to chlorine and adopt the appropriate procedures and safety
measures for its application. No major process changes are anticipated
for those already using chlorine.
The use of A1F3_ with continuous recycling of scrubber water would
require those plants presently using chlorine to change to A1F3_ for
demagging. This would not involve a major process change, as the
application of AlF^ for demagging is simpler than chlorination demagging
but twice as expensive for the removal of the same amount of magnesium.
Those plants with low-energy wet-scrubbing systems used tor chlorine
demagging would need to change over to higher energy systems for
effective scrubbing of the fumes generated with the use of AlF3_.
Although not a principal process change, the change to AlF3_ demagging
would require extensive modification of present air pollution control
equipment now used for collecting fumes from chlorine demagging in some
of the larger plants.
The chemically-treated baghouse system (Teller System) for dry air
pollution control would require those plants using chlorine for
demagging to change to AlF_3. Those already using A1F3 would have no
process change.
Nonwater Quality, Environmental impact^ The use of the Derham Process
results in no known nonwater quality environmental problems. The
residues resulting from its application may be too high in soluble salts
110
-------
for economic processing by residue milling techniques for metal recovery
and could present a solid waste disposal problem. Insufficient
information exists on the process to assess this impact.
Application of A1F3 with continuous scrubber -water recirculation will
result in a solid waste disposal problem. Fluoride salts precipitated
and settled from the scrubbing water are slightly soluble and could
possibly be leached in a landfill disposal.
Application of chemically-treated baghouse systems for dry air pollution
control also results in a solid waste as the bag coating and the
collected dust and fumes may contain fluoride salts that are slightly
soluble and leachable to ground water. Disposal of solid wastes in an
acceptable landfill is required to prevent contamination of surface or
subsurface waters.
Waste Water^from Residue Milling
Identification of Best Available^ Technology Economically Achievable
The best available technology economically achievable for waste water
from residue milling is the replacement of present wet-milling
operations by totally dry milling methods. In dry milling, the residue
is crushed and the contained salts, fracturing into small particles, are
screened out as undersized waste material. The dry operation is
extremely dusty and requires extensive air pollution controls.
Recovery of dissolved salts contained in waste streams from wet milling
by evaporation and crystallization is a potential approach to the
control or elimination of the discharge of pollutants. The salts can be
reused for flux and the condensed water can be recycled back to the
milling process. Salt recovery has not been demonstrated in the United
States but is used in Europe.
Rat ionale^for^Selecting[_the_Best Available Technology
Economical! Y_ Ac hi evable .
Time Available for Achieving Effluent Limitations. The effluent
limitation of no discharge of process waste water pollutants to be
achieved July 1, 1983, allows time for the retirement of existing wet-
milling operations by those plants using this practice.
2f Achieving the Effluent Limitations. The cost of achieving no
discharge of process waste water pollutants from the milling of residues
is estimated to be about $130.00 per annual ton of aluminum production
capacity. This is the cost of building a new plant, for the changeover
111
-------
from wet to dry milling involves a complete process change. Data are
not available for operating costs, but estimates from the secondary
industry indicate such costs to be higher than for wet processing.
The cost of recovery of salts from waste water from residue milling is
dependent on the type of residue being processed. The estimated capital
cost to evaporate the water from low-salt content residues is $16/annual
metric ton of aluminum, while operating costs are $24/metric ton. When
high salt-content residues are processed, the estimated capital costs
are $200/annual metric ton and the operating costs are $124/metric ton.
Aspects of Control Application. That dry processing of
residues for aluminum recovery is practical from an engineering
standpoint is demonstrated by the fact that, out of 23 plants processing
residues, 15 use a totally dry mill operation and generate no associated
waste water stream. Thus, the technology is well proven by actual
practice.
§.§ • Plants presently wet-milling residues will need to
completely alter their presmelter processing facilities to adopt dry-
milling practices. Crushing, screening, conveying, and dust collection
equipment will be required for the conversion.
Non water Quality Environmental Impact. Both dry milling and wet milling
of residues generates large quantities of solid wastes, ranging from 2.3
to 9 tons per ton of aluminum recovered, depending on the grade of the
residue. Generally this solid waste from dry milling contains the
highly soluble chloride salts that were washed out during wet milling.
Solids should be disposed of in an acceptable landfill to prevent
contamination of surface or subsurface waters.
Dry milling also generates large quantities of airborne dust.
Appropriate dry collection systems are normally able to control the
atmospheric emissions of the dust.
Recovery of salts by evaporation from wet milling waste water is
estimated to require additional consumption of thermal energy of 8.6 x
106 kg cal/ton for the low-salt residue waste water and 176 x 106 kg
cal/metric ton for the high-salt residue waste water (on the basis of
metric tons of aluminum recovered) .
112
-------
SECTION XI
NEW SOURCE PERFORMANCE STANDARDS
Introduction
The standards of performance which must be achieved by new sources are
to specify the degree of effluent reduction attainable through the
application of the best available demonstrated control technology,
processes, operating methods, or other alternatives. The added con-
sideration for new sources is the degree of effluent reduction
attainable through the use of improved production processes and/or
treatment techniques. The term "new source" is defined by the Act to
mean "any source, the construction of which is commenced after
publication of proposed regulations prescribing a standard of
performance".
New Source Performance Standards are based on the best in-plant and end-
of-process technology identified with additional consideration given to
techniques for reducing the discharge of pollutants by changing the
production process itself or adopting alternative processes, operating
methods, or other alternatives. The effluent standards of performance
reflect levels of control achievable through the use of improved
production processes (as well as control technology) , rather than
prescribe a particular type of process or technology which must be
employed. A further determination must be made as to whether a standard
permitting no discharge of pollutants is practicable.
Consideration must also be given to:
(a) the type of process employed and process changes
(b) operating methods
(c) batch as opposed to continuous operations
(d) use of alternative raw materials and mixes of raw materials
(e) use of dry rather than wet processes (including substitution
of recoverable solvents for water)
(f) recovery of pollutants as by-products
Waste Water from Metal Cooling
Standards^of Performance based on the Application of
the_Best_Available^Demonstrated. Control Technology
The recommended standards of performance to be achieved by new sources
is no discharge of process waste water pollutants into navigable waters
as developed in Section IX of this document.
113
-------
Identification of the Bestr Available Demons-bra ted Control
Tg-ChnQlQgy.1 -Processes A-QEggating Me thodgj or Other ^Alternatives
The Best Available Demonstrated control Technology for metal cooling
waste water is identical to the Best Practicable control Technology
Currently Available described in Section IX. The control and treatment
technologies identified in Section IX are:
(1) Air cooling of ingots
(2) Total consumption of cooling water for ingot cooling
(3) Recycle or reuse of cooling water for deoxidizer shot
cooling or ingot cooling.
Rationale for the_Select ion of the Best Avai lab le^Demonstrated
Con t r o 1 _ Tec hno 1 22y_
Thirty-one of the existing plants or 54 percent of the plants canvassed
during development of these guidelines were using the technology
identified above and described in Sections VII and XI of this document.
Thus, the technology is judged to be both available and demonstrated.
A new source has the freedom to design a technology, initially, to
achieve the standard of performance without any change in existing
equipment. The current practice of these control technologies by a
large fraction of the industry demonstrates that there are no
significant technical or economic barriers to the selection and
implementation of such technology.
The cost of application of the technologies, identified in Section VIII,
is estimated to be the same or less for new sources than for existing
plants.
Waste Water from Fume Scrubbing
Standards of Performance based on the j Application of
the Best^Available^Demonstrated Control Technology
The recommended standards of performance to be achieved by new sources
discharging to navigable waters are:
1) Identical to the effluent limitations presented in Table 1,
Section II, for those plants using chlorine for magnesium
removal
2) No discharge of process waste water pollutants for those plants
using aluminum fluoride for magnesium removal.
I^gptif ication of the Best_Available Demonstrated Control
^s^gx Operating Methods^ or Other Alternatives
114
-------
The technology previously identified in Section X as the best available
technology economically achievable for control of fumes from chlorine
demagging does not meet the criterion of "demonstrated" and may not be
capable of handling the anticipated capacities of new plants and still
permit the control of air contaminants by dry methods. Therefore, the
technology previously identified in Section IX as Best Practicable
Control Technology Currently Available is considered identical to the
Best Available Demonstrated Control Technology for waste waters from
magnesium removal processes.
Rationale fpreselectign_of_the Best Available Demonstrated^Control
Technology
The rationale for concluding that the Best Available Demonstrated
Control Technology is identical to the Best Practicable control
Technology Currently Available for waste waters from magnesium removal
processes using chlorine is as follows:
(1) Although the technology described in Section X, the Best
Available Technology Economically Achievable, indicates that
the Derham and Alcoa processes are able to control fume
emissions from chlorine demagging without the use of water,
there are some technical limitations to their adoption by new
sources. The Alcoa prototypes have been limited to inhouse use
for primary aluminum processing and have not been used by the
secondary aluminum industry in the United States. In addition,
the design may require modification to meet the casting
poundage rates presently used by most of the industry. In
effect, the system may not be applicable to new sources without
further development work.
(2) The Derham process is used by two secondary aluminum smelters
in the United States to control fumes generated during the
process of magnesium removal with chlorine. One of these
plants was not studied and the other was found to be not fully
operational. Therefore, it was concluded that insufficient
data are available to prove that the system is effective under
typical operating conditions. A supplemental wet scrubber may
be required with the Derham process to meet air emmissions
standards. This is the case for at least one plant in the
subcategory. The Derham process is considered insufficiently
demonstrated to be applied to new sources without further
technical evaluation.
Waste Water^from Pesidue Milling
Standards of Performance based on the Application of the Best
Ayailable Demonstrated Contro1 Technology
115
-------
The recommended standard of performance to be achieved by new sources is
no discharge of process waste water pollutants into navigable waters.
Identif ication_of ^the i Best Available Demonstr at ed Control Technology^
PrQcessesJ_^OBerating^MethQdsx_Qr Other Alternatives
The Best Available Demonstrated Control Technology, processes, operating
methods, or other alternatives for residue milling waste water are:
(1) Dry milling, currently in practice in existing plants in the
U.S.
(2) The evaporation of waste waters from wet milling of residues
with the associated reclamation and reuse of fluxing materials.
This technology is not currently demonstrated in any existing
plant in the U.S., but is demonstrated in Europe.
The details and costs of these technologies are presented in Section VTI
and VIII of this document.
Technology
The rationale for the selection of the best available demonstrated
control technology is as follows:
(1) A new source has the freedom to choose the most advantageous
residue-processing techniques for maximum recovery of metal and
by-products with the minimum use or discharge of water.
(2) In contrast to an existing source which may have a large
capital investment in waste treatment facilities to meet
effluent limitations by July 1, 1977, a new source has complete
freedom in the selection and design of new waste treatment
facilities.
(3) In contrast to an existing source, a new source has freedom of
choice with regard to geographic location in seeking any
economic advantage relative to power cost or land cost.
Since the technology for achieving no discharge of residue milling waste
water has been demonstrated for a facility currently being constructed,
it is considered the best available demonstrated control technology for
new sources. The possibility of a slightly higher cost in relation to
several orders of magnitude reduction in pollution and the possible
elimination of monitoring expense for no discharge of effluent warrants
the selection of this technology as the best available demonstrated
control technology for the secondary aluminum smelting subcategory.
116
-------
Time Available for Achieving Effluent Limitations., The effluent
limitation of no discharge of process waste water pollutants for best
available technology economically achievable, to be implemented July 1,
1983, allows time for the retirement of existing wet-milling operations
by those plants using this practice.
Cost of Achieving No Discharge of Process Waste Water Pollutants^ The
cost of achieving no discharge of process waste water pollutants from
the milling of residues is estimated to be about $130.00 per annual ton
of aluminum production capacity. This is essentially the cost of
building a new plant, for the changeover from wet to dry milling
involves a complete process change. Data are not available for
operating costs, but estimates from the secondary industry indicate such
costs to be higher than for wet processing.
The cost of recovery of salts from waste water from residue milling is
dependent of the type of residue being processed. The estimated capital
cost to evaporate the water from low-salt content residues is $16 per
annual ton of aluminum, while operating costs are $24/ton. When high
salt-content residues are processed, the estimated capital costs are
$200/annual ton and the operating costs are $124/annual ton.
Engineering Aspectg of _Control __ Application. That dry processing of
residues for aluminum recovery is practical from an engineering
standpoint is demonstrated by the fact that out of 23 plants processing
residuse, 15 use a totally dry mill operation and generate no associated
waste water stream. Thus, the technology is well proven by actual
practice.
Plants presently wet-milling residues will need to
completely alter their presmelter processing facilities to adopt dry-
milling practices. Crushing, screening, conveying, and dust collection
equipment will be required for the conversion.
117
-------
SECTION XII
ACKNOWLEDGEMENTS
Appreciation is expressed to the following organizations associated with
the secondary aluminum industry that provided information:
Apex Smelting Co., Des Plaines, Illinois
Diversified Materials, Inc., St. Louis, Missouri
Newark Processing Co., Newark, Ohio
Rochester Smelting and Refining Co., Rochester, N.Y.
U.S. Reduction Co., East Chicago, Indiana
Vulcan Materials Co., Metals Division, Sandusky, Ohio
Wabash Smelting and Refining Co., Wabash, Indiana
Acknowledgement is made of the cooperation of the personnel in many
plants in the secondary aluminum industry that were canvassed and who
voluntarily provided background information and wastewater management
practices. Special acknowledgement is made to those plant personnel and
company officers that cooperated in providing plant operating data and
cost data and provided facilities for sampling of their in-plant
streams. The assistance provided by the Aluminum Recycling Association
during this study is appreciated.
Special acknowledgment is made to Mr. Marshall Dick for his technical
evaluation and comments and to Ms. Chris Miller and Ms. Kay Starr for
the timely preparation of this report.
118
-------
SECTION XIII
REFERENCES
(1) Aluminum Association, "Aluminum Scrap Consumption and
Recovery", Aluminum Statistical Review, New York (July,
1969) .
(2) Andrews, C., Vice President, Aluminum Processes, Inc.,
(3) Danielson, J. A., "Air Pollution Engineering Manual",
U.S. Dept. of Health, Education, and Welfare, Cincinnati,
Ohio (1967) .
(4) Demmler, J. A., Staff Member, Technical Marketing Division,
Aluminum Corporation of America, private communication,
June 22, 1973.
(5) Francis, F. J., "Secondary Aluminum Smelter Air Pollution
Control Using a Chromatographic Coated Baghouse — A
Technically New and Economic Solution", Proceedings, 65th
Annual Meeting of the Air Pollution Control Association
(June 22, 1972) .
(6) Ginsburg, T. H. , "Scrap Utilization by Secondary Aluminum
Smelters", Proceedings of the Third Mineral Waste Utiliza-
tion Symposium, Chicago, Illinois (March 16, 1972) .
(7) Patterson, J. W. , and Minear, R. A., Waste Wgter Treatment
Technology* Report t IIEQ71-4, from Illinois Institute of
Technology to state of Illinois, Institute for Environmental
Quality, August, 1971.
(8) Peters, M. S. , and Timmerhaus, K. D., PI an tmDe s ign
Economics for Chemical Engineers, 2nd Ed. , McGraw Hill
Book Co. 7 New York, 1968.
(9) Shirley, W. C. , "Secondary Aluminum Industry Emission
Control", Rept. prepared for the Aluminum Smelting Research
Institute (1971) .
(10) Siebert, D. L., "Impact of Technology on the Commercial
Secondary Aluminum Industry", U.S. Bureau of Mines Informa-
tion Circular 8445 (1971) .
119
-------
(11) Spendlove, M. J., "A Profile of the Nonferrous Secondary
Metals Industry", Proceedings of the Second Mineral
Waste Utilization Symposium, M. A. Schwartz, Chm. (March
19, 1970) .
(12) Staff, Bureau of Mines, "Mineral Facts and Problems—
Aluminum", U. S. Bureau of Mines Bulletin 650 (1970) .
(13) Staff, "Metal Statistics—Aluminum Profile", American
Metals Market (1972) .
(1U) Staff, "Aluminum—Profile of an Industry—Part II", Metals
Week, (August 12, 1968) .
(15) Staff, "Process Effluent Water Data Development",
Aluminum Recycling Industry Survey (November 28, 1972).
(16) Stamper, J. W., "Aluminum", U. S. Bureau of Mines Mineral
Yearbook (1971).
(17) Teller, A. J., "Air Pollution Control", Chemical Engin-
eering—Deskbook Issue (May 8, 1972).
(18) Teller, A. J., "Control of Emissions from Glass Manu-
facture", Ceramic Bulletin, Vol. 51, No. 8 (1972) .
(19) Wahi, B., Environmental Research Corp., St. Paul, Minn.,
private communication, June 19, 1973.
(20) Weston, Roy F., Inc., Draft, "Pretreatment Guidelines for
Discharge of Industrial Wastes to Municipal Treatment
Works", Contract No. 68-01-0346, for the Environmental
Protection Agency (November 17, 1972) .
120
-------
SECTION XIV
GLOSSARY
Act
The Federal Water Pollution Control Act Amendments of 1972.
Alloying
The process altering the ratio of components in a metal by the addition
or removal of such components.
Borings and Turnings
Scrap aluminum from machining of castings, rods, bars, and forgings.
Captive Scrap JRunaround Scrap)
Aluminum scrap metal retained by fabricator and remelted.
COD
Chemical oxygen demand parameter used to assess water quality.
Compatible Pollutants
Those pollutants which can be adequately treated in publicly owned
sewage treatment works without harm to such works.
Demagging
Removal of magnesium from aluminum alloys by chemical reaction.
Residues generated during the processing of molten aluminum or aluminum
alloys by oxidation in air.
121
-------
Effluent
The waste water discharged from a point source to navigable waters.
Ef fluent_Limitation
A maximum amount per unit of production (or other unit) of each specific
constituent of the effluent that is subject to limitations in the
discharge from a point source.
Fluxing gaits jor Covering Flux^
Sodium chloride or a mixture of equal parts of sodium and potassium
chlorides containing varying amounts of cryolite. Used to remove and
gather contaminants at the surface of molten scrap.
Heat
A fully charged reverberatory furnace containing aluminum alloy of
desired composition.
Heel
That part of the molten aluminum alloy remaining in the furnace to
facilitate melting of scrap being charged for the preparation of
following heat.
Incompatible Pollutants
Those pollutants which would cause harm to, adversely affect the
performance of, or be inadequately treated in publicly owned sewage
treatment works.
Ingots
A mass of aluminum or aluminum alloy shaped for convenience in storage
and handling. Sizes according to weight are 15, 30, 50, and 1000
pounds.
122.
-------
Irony Aluminum
High iron content aluminum alloy recovered from old scrap containing
iron. Prepared in sweating furnace operating at temperatures
sufficiently high to melt only the aluminum.
Q 1 i pjDi nc[S _a nd_ Fo r gings
Scrap from industrial manufacturing plants such as aircraft and metal
fabricators.
Ingots of aluminum alloy weighing 15 to 50 pounds.
Point., Source
A single source of water discharge such as an individual plant.
Pretreatment
Treatment performed on waste waters from any source prior to
introduction for joint treatment in publicly owned sewage treatment
works.
Residues
Include dross, skimmings and slag recovered from alloy and aluminum
melting operations—both from primary and secondary smelters and from
foundries.
Reyerberatory Furnace (Reverb^
An open-hearth furnace used for the production of aluminum alloy from
aluminum scrap.
Skimmings
Wastes from melting operations removed from the surface of the molten
metal. Consists primarily of oxidized metal but may contain fluxing
salts.
123
-------
Fluxing salts removed from the surface of molten aluminum after charging
and mixing. Contains 5 to 10 percent solid aluminum alloy.
Solids
Aluminum scrap metal.
Sows
Ingots weighing 500 to 1000 pounds.
Standard of Performance
A maximum weight discharged per unit of production for each constituent
that is subject to limitations and applicable to new sources as opposed
to existing sources which are subject to effluent limitations.
Sweated Pigs
Ingots prepared from high iron aluminum alloy.
Aluminum recovered from bauxite
124
-------
Q
u
w
o
H
§
3
O
ro
CO
CO
4->
•H
C
0
o
•H
4-1
5
G
•H
cd
4J
43
0
H
^>
r>
x™s
CO
4-1
•H
C
0
cj
CO
•H
rH
00
c
^
^
rH
P.
•H
4-J
rH
S
&
4-1
•H
J^
O
•iH
4J
CU
&
G
O
•H
4-1
cd
•H
01
43
§
•H
CO
M
CU
>
13
O
O
C
o
. 1
•n
4-1
cd
•H
>
cu
jz
O O £H
Cd Cd p£J
4-1
•H
G
•a
s
cu
4-1 H
cu
CU 43
14H CO
CO 1 -H
CU CU -U
M M iH
O O M
cd cd PQ
00
0
rH
•H
^4 CU
\ 4J
co 3
CU G
•H -H
M a
o -^-
rH CO
cd M
CJ CU
4-1
B cu
M
00 0
O -H
rH 43
"H JD
00
y^l ^
rH-'a'
cd --
o a
00 3
in oo
in CM
in o
O 0
43
rH
^v^
a a
pq o
•o
D
£X
"x^.
4-1
C
C3 CU
4-1
rH 3
cd c
E3
CU ~v.
H CU
cu
43 MH
en
•H O
4J -H
•H 43
M •S
pq o
cu
4-1
3
C
J
CO CO
M M
CU CU
4J 4-1
CU CU
CO
CJ O M
•H TH HJ
43 43 4J
pH »H J
»j tJ *n
c
•H
^^
B a
0 0
oo
CM CM
r*"*" ^^ f^o
rH O 00
CM
4-1 4J
MH M-l
CO
MH 3 3
o o o
T3
C
0
O
in cn in
00 v0
cd
CO
M
cu
CO 4-1 M
3 CU CU
cd a 4J
M CU
oo o a
O -H O
rH 43 rH
A! O Ai
^
Tl
~a
oo 3 a
\St fj i^j
/•
>
** m ^
in oo o
o cn '~t
TJ
43 00 -H
rH S S
&
T3
-•^_
CO
o
rH
rH
cd
00
c
-35
C rH 0)
3 rH rH
O -H -H
p, B S
^^
cu
4-1
3
T~H
o
CO
•s
v-x 0)
CO 01
CU 4-J
M CU
cu B
43
P, 01
CO M
o cd
a 3
cd co
B
8
cd co
cd
tavS
/•• ^
rH
00
•H
CO
pt
o>
in CM
o &
oo o
O 0
•
o
^/
4-1
00 M-l
•H
CO 0*
CX CO
y*-^
cu
00
3
cd
00
^^
rj
o
13
•H
01
^ ^VJ
cd o)
3 01
cr MH
co
13 M
G cd
3 3
o cy
CX CO
00
o
rH
•H
4^
to
M 0
0) O
4J O
01 rH
•H
4-1 CO
C (3
cu o
O 4-1
CU O CO
M -H M
cd M cu
34-14-1
§r§ g
e
tJ
00
cn ^ 6
^J-
CN 1*""* "d"
in o r-n
<± & o
vD O O
c
•H
a-
CO 4-J >^
CO
cu /-*
43 4-1
0 M
c o
•H 43
CO
01 ^
cd co T)
3 C M
o- o cd
CO 4-1 >-,
•
01
•H
rH
ex
•H
4-1
rH
e
fl
4-1
o
C3
M
£3
o
•H
CO
M
01
g
o
rH
cd
3
4-1
o
^4
y^-s
td
s-x
125
-------