-------
40. Total administrative coats (Lin* 35): The total administrative
costs, both clerical and technical, for the monitoring program are repeated
here.
41. Total monitoring costs (Line 37 + Line 38 + Line 39 + Line 40):
The total cost for the entire closure period monitoring program is the
sum of the costs of ground-water monitoring, soil core testing, lysimeter
testing, and the administrative costs. All of these coats are reliably
known from the operating experience of the facility.
D. Fence Maintenance
For a land treatment facility consisting of SO acres of active fields,
assuming that the site is square, each side is 1475.3 feet. The perimeter
of the site is then 5903.2 feet.
1. Length of fence to be replaced: Since the land treatment facil-
ity has a prolonged closure period and possible post-closure activities,
it is necessary to maintain the security fence along the field perimeters
in good condition. We have estimated that 10Z of the fencing will be
corroded and damaged to the point of requiring replacement.
2. Unit cost of replacing fence: The security fence is a galvanized
metal 6-foot high chain link fence made of #9 wire. The installed unit
cost of replacement sections is $13.06 per linear foot.
3. Total cost of replacing fence (Line 1 x Line 2): The cost of
replacing the damaged fence sections is the product of the length of the
fence needing replacement and the unit coat of replacement, for a total
of $77,5.
E. Repair of Drainage Channels
1. Length of drainage channels: The land treatment facility's
drainage channels are an important part of the containment system. They
channel run-off water to a surface impoundment. Our estimate is chat
500 feet of these channels will have to be replaced during the closure
period.
2. Channel volume per unit length: The channels have a square
cross sectional area measuring 3 feet by 3 feet. This results in a
volume of 0.33 cu. yds. per linear foot of channel length.
9-41
-------
3. Channel excavation unit cost: The unit cost of excavating the
channels with a backhoe is $.67 per cu. yd. This work would be performed"
by a contractor and is based on contractor estimates.
4. Total channel excavation cost (Lin* 1 x Line 2 x Line 3): This
total cost is the product of the length of the drainage channels required,
the volume per unit length, and the unit excavation cost.
5. Unit cost of hand grading: The inner surface of the channels
must be shaped and prepared for seeding. This work is performed by hand
at a-unit cost of $.02 per sq. ft. This work will be performed by a
contractor and is based on contractor estimates.
6. Channel surface area: The inside surface of the new channel
is approximately 4500 sq. ft. in area. All of this area must be shaped
and prepared.
7. Total cost of hand grading (Line 5 x Line 6): The total cost
of this hand grading is the product of the unit cost and the surface
area of the channels.
8. Total replanting cost: The total cost of seeding, fertilizing
and mulching the channel surface is estimated at $50 by a contractor.
9. Total channel repair cost (Line 4 + Line 7 + Line 8): The
total cost of channel repair is the sum of the excavation cost, hand grad-
ing cost and replanting cost.
F. Management Inspection of Land Treatment Facility Operations
1. Number of technical management parson-hours required for each
inspection ' The prolonged closure period for the land treatment facility
and the recurring operations of spreading and disking necessitate an
inspection program conducted by facility management throughout the closure
period. Each one of these inspections requires 8 hours of technical manage-
ment time.
2. Inspection frequency: The inspections are conducted once per
month throughout the closure period. On each inspection, the manager
checks the progress of the facility operations: spreading, disking,
sampling, decontamination, etc.
3. Duration of closure period: To allow the hazardous waste to
decompose, the closure period must be 15 months in duration.
9-42
-------
4. local technical management person-hours required for inspections
(Line 1 x Line 2 x Line 3): The technical hours required for Che actual
inspections are the product of the number of hours for each inspection
and the total number of inspections required.
5. Person-hour coses for technical management duties: The person-
hour cost for this technical supervisory labor is $30 per hour (fully-
loaded labor rate).
6. Total technical management costs for inspections (Line 4 x Line
5): The technical cost for the inspections conducted throughout the
closure period is the product of the total inspection technical hours
and the technical labor rate.
7. Additional technical management labor required: A small amount
of additional technical time will be required for managerial tasks
associated with the inspections (such as writing reports). Approximately
8 percent to 10 percent of the inspection tine is required for this
additional work.
8. Total cost of additional technical management labor (Line 5 x
Line 7): The cost of this additional technical labor is the product of
the additional hours required and the technical labor rate.
9. Total cost of technical management labor (Line 6 + Line 8):
The total cost of all the technical labor required is the sum of the
labor directly spent on inspections and the labor related to inspections.
10. Number of clerical hours required: Clerical labor is needed to
support the periodic inspections of the land treatment facility. Only
a modest amount of clerical labor is required.
11. Person-hour costs for clerical labor: The labor race for
clerical labor at this facility is $8 per hour. (This is a fully-loaded
labor race.)
12. Total cost for clerical labor (Line 10 x Line 11): The total
cost for the needed clerical labor is the product of the clerical hours
and the clerical labor rate.
13. Total inspection cost (Line 9 + Line 12): The total cost of the
inspection program is the sum of the technical labor costs and the cleri-
cal labor costs.
9-43
-------
G. Professional Certification
1. Number of person-hours required for inspections: Approximately
one week of professional time will be required to certify the proper
closure of the land treatment facility. Most of this professional work
will be an independent professional engineer as specified by the interim
status regulations. The professional engineer will be assisted by a soil
specialist who will evaluate the soil samples taken during the closure
period.
2. Cost per person-hour: The contracted cost of these professionals
is $75 per hour based on their current quotes for these services.
3. Total costs of professional engineer's time (Line 1 x Line 2):
The total cost for these contracted professional services is the product
of the number of hours required and the quoted hourly rate.
4. Number of technical hours required for administrative duties:
The land treatment facility technical staff will need to devote 8 hours
of time to administering this certification.
5. Person-hour costs for technical administrative duties: The
fully-loaded labor rate for the technical staff is $30/hour.
6. Total administrative costs for technical labor (Line 4 x Line 5):
The technical administrative costs for the land treatment facility is the
product of the number of technical hours required and the technical labor
race.
7. Number of clerical hours required for administrative duties:
Eight hours of clerical work are required to support the administration
of che certification.
8. Person-hour costs for clerical administrative duties: The
fully-loaded labor rate for clerical workers at this facility is $8/hour.
9. Total administrative costs for clerical labor (Line 7 x Line 8):
The cotal clerical labor costs are the product of the labor rate and
the number of hours required.
10. Total administrative costs (Line 6 + Line 9): The total adminis-
trative costs are the sum of the technical labor cost and the clerical
labor cost.
11. Total certification costs (Line 3 + Line 10): The total cost
for certification is the sum of the costs of the professional engineer
-------
•ad the administrative coats.
H. Total Coat» Plus Administration and Contingencies
Items 1 through 7 give the costs of each major closure function on
each of the preceding worksheets. Line 8 is the total of Lines 1 through
7, $39,389.
7. Administration: All additional administration costs are com-
puted by multiplying the subtotal (Line 8) by 15 percent.
8. Contingencies: Allowance for contingencies is computed by
multiplying the subtotal (Line 8) by 15 percent.
9. Total cos ts of closure (Line 8 + Line 9 + Line 10): A grand
total for land treatment facility closure costs is computed by adding
together the coets from the worksheets and the allowances for additional
administration and other contingencies.
9-45
-------
LAND TREATMENT FACILITIES
WORKSHEET A - DISPOSING OF WASTE INVENTORY
Macbod of Disposal: Spreading on the Land Treatment Fields
1. Maximum inventory to be disposed
2. Rim-off water to be disposed
3. Total material to be disposed (Line 1 + Line 2)
4. Application rate (vet weight)
5. Acreage utilized
6. Number of applications in the closure period
7. Unit cost of spreading
8. Total cost of spreading (Line 5 x Line 6 x Line 7)
9. Number of disIcings required during the
closure period (excluding one disking for
decontamination)
10. Unit cost of disking (equipment cost and labor)
11. Total cost of disking (Line 5 x Line 9 x Line 10)
12. Total cost for disposing of inventory and
run-off water (Line 8 + Line 11)
5000 tons of
liquid waste
5000 tons
10,000 tons
100 tons/acre
50 acres
2
$48/acre
$4800
10
$4.80/anre
$2400
$7200
9-46
-------
LAND TREATMENT FACILITIES
WORKSHEET B - DECONTAMINATING THE FACILITY
1. Area of facility contaminated
2. Depth of material removed
3. Unit cost for removal (including machinery rental)
4. Cost of removing the contaminated soil
(Line 1 x Line 2 x Line 3)
5. Quantity of contaminated soil disposed on-cice by
landspreadlng
6. Quantity of contaminated soil disposed off-site
7. Application rate
8. Acreage utilized
9. Number of applications
10. Unit cost of spreading (equipment cost and labor)
11. Total cost for spreading the contaminated soil
on the land treatment fields (Line 8 x Line 9
x Line 10)
12. Number of diskings carried out to assist
in disposing of contaminated soil
13. Unit cost of disking (equipment cost and labor)
14. Total cost for disking the spread soil into the
land treatment soil (Line 8 x Line 12 x Line 13)
15. Total cost of disposing of the contaminated soil
(Line 4 + Line 11 + Line 14)
16. Cost of decontaminating equipment
17. Disposing of residues from equipment decon-
tamination
18. Total cost of decontaminating the facility
(Line 15 + Line 16 + Line 17)
1200 sq. yds.
.33 yds. (1 ft.)
$1.60/cu. yd.
$633.60
396 cu. yds.
(481 tons)
0
10 tons/acre
50 acres
1
$6/acre
$300
$4.80/acre
$240
$1173.60
$1000
$1000
$3173.60
9-47
-------
LAND TREATMENT FACILITIES
WORKSHEET C - MONITORING ACTIVITIES
(GROOHD-WATER AND SOIL MONITORING)
Ground-Water Monitoring
1. Number of veils monitored
2. Number of samples taken at each well (1 per cycle)
3. Total number of samples (Line 1 z Lin* 2)
4. Number of hours for collecting the sample (per sample)
5. Total number of hours for collecting the samples
(Line 3 x Line 4)
6. Number of hours for preparing and delivering sample
(per each sampling cycle of eight wells)
7. Total number of hours for preparing and delivering
sample (Line 2 x Line 6)
8. Person-hour costs for collecting and handling samples
9. Total ground-water sampling and collection costs
((Line 5 + Line 7) x Line 8)
10. Number of ground-water quality analyses
11. Number of ground-water contamination analyses
12. Unit cost of ground-water quality analysis
13. Unit cost of ground-water contamination analysis
14. Total ground-vater quality analysis costs
(Line 10 x Line 12)
13. Total ground-water contamination analysis costs
(Line 11 x Line 13)
16. Total ground-water chemical analyses costs
(Line 14 + Line 15)
Soil Monitoring
Soil Core Sampling;
17. Number of soil core samples taken during the
closure period
18. Labor hours required for each core sample
(includes movement between sampling locations)
19. Labor unit cost for collecting core sample
8 wells
3 samples
24 samples
2 hours
48 hours
3 hours
9 hours
$15/hour
$855
16 analyses
24 analyses
$77
$108
$1232
$2592
$3824
66 samples
.5 hours
$15/hour
9-48
-------
WORKSHEET C (continued)
20. Total cost"of collecting soil sample* for cha entire $495
closure period (Line 17 x Line 18 x Line 19)
21. Unit soil core sample analysis cost (10 parameters) $60
22. Total soil core sample chemical analysis cost $3960
(Line 17 x Line 21)
Lysimeter Sampling of Soil Moisture:
23. Number of lysimeter samples taken during the 20
closure period
24. Labor hours required for each lysimeter collection 1 hour
of soil moisture
25. Labor unit cost for collecting samples $15/hour
26. Total sampling cost for lysimeter collection $300
of soil moisture (Line 23 x Line 24 x Line 25)
27. Unit cost for moisture sample analysis $150
28. Total cost for moisture sample chemical analysis $3000
(Line 23 x Line 27)
Administrative Costs
29. (lumber of technical hours for administration 16 hours
30. Person-hour technical costs $30/hour
31. Total technical costs for administration $480
(Line 29 x Line 30)
32. Number of clerical hours 16 hours
33. Person-hour clerical cost $8
34. Total clerical costs (Line 32 x Line 33) $128
35. Total administrative costs (Line 31 + Line 34) $608
Maintenance Costs
36. Monitoring well maintenance (includes maintenance $750
of associated equipment)
Cost Sundries for Monitoring
37. Total cost of ground-water monitoring for the $5429
closure period (Line 9 + Line 16 + Line 36)
38. Total cost of soil core sample monitoring for $4455
the closure period (Line 20 + Line 22)
9-49
-------
WORKSHEET C (continued)
39. Total cote for soil moisture (lysineter) monitoring $3300
for the closure period (Line 26 + Line 28)
40. Total administrative costs (Line 35)
41. Total monitoring costs for the entire closure
period (Line 37 + Line 38 + Line 39 + Line 40)
.9-5C
-------
LAND TUAXMBIT FACILITIES
woucsmT o - mfd N&XHTIIUNCZ
1. Langth of fanca to ba replaced 590 faat
2. Unit coat of replacing f«nc« $13.06/llnear ft,
3. Total cogt of raplaclng fanca (Lin* 1 x Llna 2) $7705
9-51
-------
LAND TREATMENT FACILITY
WORKSHEET E - REPAIR OF DRAINAGE CHANNELS
1. Length of drainage channels requiring excavation
2. Channel volume per unit length
3. Channel excavation unit cost
4. Total channel excavation cost
(Line 1 x Line 2 x Line 3)
5. Unit cost for hand grading
6. Channel surface area to be prepared by hand
7. Total cost of hand grading (Line 5 x Line 6)
8. Total replanting cost (including seed,
fertilizer and mulch)
9. Total channel repair cost
(Line 4 + Line 7 + Line 8)
500 feet
.33 cu. yds.
per linear ft.
$.67/cu. yd.
$11.05
$.02/sq. ft.
4500 sq. ft.
$90
$50
$250.55
9-52
-------
LAND TREATMENT FACILITIES
WORKSHEET F - MANAGEMENT INSPECTION OF LAND
TREATMENT FACILITY OPERATIONS
1. Number of technical management per»on-hour»
required for each inspection of the land treatment
facility
2. Inspection frequency
3. Duration of closure period
4. Total technical management parson-hours required
for inspections during the closure period
(Line 1 x Line 2 x Line 3)
5. Person-hour costs for technical management duties
6. Total technical management costs for land treatment
facility inspections (Line 4 x Line 5)
7. Additional technical management labor required
related to the inspection program
8. Total cost of the additional technical management
labor (Line 5 x Line 7)
9. Total cost of technical management labor
(Line 6 + Line 8)
10. Number of clerical hours required
11. Person-hour costs for clerical labor
12. Total cost for clerical labor (Line 10 x Line 11)
13. Total inspection cost (Line 9 + Line 12)
8 hours
1 per month
13 months
120 hours
$30
$3600
10 hours
$300
$3900
9-53
-------
LAND TREATMENT FACILITIES
WORKSHEET G - PROFESSIONAL CERTIFICATION
1. Number of person-hours required for inspecting 40 hours
the land treatment facility and its operating records
2. Cost per person-hour $75
3. Total costs of professional engineer's time $3000
(Line 1 x Line 2)
4. Number of technical hours required for administrative 8 hours
duties
5. Person-hour costs for technical administrative duties $30
6. Total administrative costs for technical labor $240
(Line 4 x Line 5)
7. Number of clerical hours required for administrative 8 hours
duties
8. Person-hour costs for clerical administrative duties $8/hour
9. Total administrative costs for clerical labor $64
(Line 7 x Line 8)
10. Total administrative costs (Line 6 + Line 9) $304
11. Total certification cost (Line 3 + Line 10) $3304
9-54
-------
LAND TREATMENT FACILITIES
WORKSHEET H - TOTAL COSTS PLUS ADMINISTRATION
AND CONTINGENCIES
1. Cose of disposing of inventory (From Worksheet A) $ 7,200
2. Cost of decontaminating the facility (From Worksheet B) $ 3,173
3. Cost of monitoring (From Worksheet C) $13,792
4. Cost of fence maintenance (From Worksheet D) $ 7,705
5.. Cost of repairing drainage channels (From Worksheet E) $ 251
6. Cost of management inspections (From Worksheet F) $ 3,964
7. Cost of professional certification of closure $ 3,304
(From Worksheet G)
8. Total of Line 1 through Line 7 $39,389
9. Administration $ 5,908
10. Contingencies $ 5,908
11. Total costs of closure (Line 8 + Line 9 + Line 10) $51.205
9-55
-------
9.4 EXAMPLE - LANDFILLS
For illustrative purposes, a sample cost estimate has been developed
for A landfill vlch che following characteristics: the landfill has been
in operation for 10 years and covers approximately 75 acres. Sixty-five
acres have been partially closed (i.e., they have been filled with wast*,
an adequate cap and vegetative cover established and maintained). Ten
acres of the Landfill are currently in active use and have not received
final cap or cover but are largely filled. Of the 65 acres which have
received final cap and cover, it is assumed that approximately 5 acres
are in need of revegetation due to failure of original vegetation over
the life of the facility. The landfill accepts hazardous solid waste re-
ceived in trucks. Waste is received for this site in 55-gallon drums.
9-56
-------
A. Disposing of Inventory
1. Volume of waste when processed for landfill disposal: It is
estimated from the closure plan that Che most expensive closure conditions
likely to occur over the life of facility would result In 900 55-gallon drums
of waste to be disposed and no trench yet constructed for their disposal.
This situation would occur when existing trenches had been filled but not
yet capped, and waste continued to be accepted for further disposal.
Th±3 estimate should be based on the volume of the waste after conducting
the necessary processing prior to disposal. For example, if sludge is
taken in, the proper volume to be used is that of solidified sludge, not
the volume of the sludge as it enters the facility. In this case, since
waste is accepted in drums only, there is no need for further calculation.
2. Estimated volume of contaminated soil residues disposed
of through on-site landfill operations: This volume is determined from
Worksheet B.
3. Total volume of wastes to landfills on-site (Line 1 + Line 2):
In this case, the total volume to be landfilled on-site is the volume of
inventory (300 cu. yds.) plus the estimate volume of residues and con-
taminated material to be disposed of on-site from Worksheet B (600 cu.
vds.). It is possible in some cases that not all inventory could be
disposed of on-site. For example, if two wastes normally are neutralized
by combination, and there is inadequate volume of one of the wastes to
complete neutralizing the second waste at the time closure commences,
some portion of the second waste would have to be disposed of off-sice.
4. Estimated cost of constructing a trench: The cost of construct-
ing a trench adequate for 1400 cu. yds. of material of the type indicated,
including adequate liner, is estimated as $18,000, based upon past trench
construction experience at the facility.
5. Estimated cost of placing wastes in trench (excluding final
cover and vegetation) : Based on the annual volume and operating costs
of the facility (excluding profits and depreciation), it is estimated
chat the costs of placing this waste will be $6000.
9-57
-------
6. local coat of disposing of inventory (Line A + Line 5): The
cocal cost of disposing of inventory are then the sum of Lines 4 and 5.
B. Deconearningtln$ the Facility
1. Area of facility contaminated: It is assumed in the example that
at che end of facility life, approximately 1800 sq. yds. of the surface of
the facility will show sufficient contamination to justify its disposal
as hazardous was te.
2. Depth of material removed: It is assumed that removal to 1 foot
will be necessary.
3. Cost of removal: The assumed cost of removing this material
is $1.40 per cu. yd. for a total cost of $840. This does not include
the costs of disposing of the material.
4. Quantity disposed on-site: For the sample problem, it is
assumed that all 600 cu. yds. will be disposed on-site.
5. Quantity disposed at an off-site TSDF: None of the material
removed will be disposed off-site.
6. Cost to decontaminate equipment: It is assumed that $1000 will be
sufficient for decontaminating equipment.
7. Volume of waste resulting from decontaminating equipment: It
is estimated chat 25 cu. yds. of material will need to be disposed of
as a result of decontaminating equipment.
8. Unit cost of off-site disposal: Contact with other area
hazardous waste dlspcsal facilities indicates that land disposal for
these wastes would currently cost $40/cu. yd.
9. Unit cost of hauling: Hauling this small quantity of residue
20 miles Co nearest landfill will cost $10 per cu. yd. according Co
local trucking concerns.
10. Total cost of off-site disposal (Line 7 x Line 8): Total costs
of disposing residue are then $1000.
11. Total cost of hauling (Line 7 x Line 9): Total cost of hauling
is then the unit cost of hauling times the total volume of residues to
be disposed.
12. Total cose of decontaminating the facility (Line 3 + Line 6 + Line
10 + Line 11): Tocai costs are then $2850.
9-58
-------
Aa noced in ctic summary of this example, ic has beeu assumed that.
the equipment for all necessary earth work Is available on-site. As a
result, costs for placing a final cap over the fill area include only
labor, operating costs, and materials, not costs associated with rent-
ing equipment or capital recovery factors for purchased equipment.
1. Area to be capped: The example assumed that 10 acres, or 48,400
sq. yds., will remain open and require both a clay cap and topsoil.
2. Type of material used for impermeable layer: Clay is the
impermeable material specified in the closure plan.
3. Depth of impermeable layer: It is assumed that 2 ft. of clay
will provide an adequate cap.
4. Volume of material required (Line 1 x Line 3): The amount of
clay required is 32,428 yds. (48,400 x .67 yds.).
5. Source of impermeable material: It is assumed that clay is
available on-site as a result of previous excavations, at a haul distance
of 800 yds. or less.
6. Cost of impermeable material: Because the material is available
on-site, the cost is zero.
7. Depth of topsoil required: It is assumed that 2 ft. of topsoil
will be adequate to ensure that the roots from vegetation of the fill
area do not penetrate the clay cap.
8. Volume of topaoil required (Line 1 x Line 7): The amount of
topsoil required is 32,428 cu. yds.
9. Source of topsoil: Again, it is assumed that adequate topsoil
Is available on-slte from previous excavations.
10. Cost of topsoil: The cost in this case is zero, since the
material is available on-site. (If topsoil were not available on-site,
a cost estimate -would have to be developed through discussions with local
suppliers, etc.)
11. Cost per cu. yd. for hauling, spreading and compacting clay and
topsoil: In the example, it is assumed that this can be done for $1.20
per cu. yd.
12. Cost of placing impermeable portion of cap (Line 4 x Line 11):
Based on these assumptions, the costs of placing the impermeable portion
9-59
-------
of che cap would be $38,914.
13. Cose of placing topsoil (Line 8 x Line 11): Based on the assump-
tions, che costs of placing topaoil are also $38,914.
14. local coats of final cap (sum of Line* 6, 10, 12, and 13): The
total costs of the final capping operation will be $77,828. This does
not include administrative expenses or contingency planning, both of
which are calculated on Worksheet G.
D. Planting Final Vegetation
As in the above worksheets, it is assumed that all necessary equip-
ment is available on-site, but that material and labor costs will be
accrued during the closure exercise.
1. Area not yet vegetated: The area remaining open at the time
of closing is 10 acres.
2. Area already closed but requiring replanting: It is assumed
in this case that 5 acres of the closed portion of the landfill require
replanting, due to the failure of original .vegetation efforts.
3. Total area to be planted (Line 1 + Line 2): The sample
case provides for 15 acres to be planted during closure.
4. Type of vegetation to be used: In this example, it is assumed
that coarse field grass (a mixture of rye grass and Kentucky fescue)
will be employed for final vegetation.
5. Quantity of seed used per acre: According to industry suppliers,
150 Ibs. of seed should be applied per acre.
6. Celt of seed per pound: Calls to local suppliers determined that
seed is available at $.50/lb.
7. Total cost of seed (Line 3 x Line 5 x Line 6): Given the above
assumptions, the total cost of seed will be $1125.
8. Type of fertilizer to be used: Given the topsoil and climatic
conditions, 10/10/10 fertilizer is assumed to be adequate.
9. Quantity of fertilizer per acre: .25 tons is assumed to be
reasonable, given the quality of topsoil and the climatic conditions.
10. Cost of fertilizer per ton: According to local suppliers,
fertilizer is available for $200/ton.
9-60
-------
11. Total cost of fertilizer (Line 3 x Line 9 x Line 10): Given
the above assumptions, the total coat of fertilizer is $750.
12. Cost of soil preparation per acre: Preparing the soil includes
both disking and fertilizing and is aasuaad to be $100 per acre.
13. Total cost of preparing soil (Line 3 x Line 12): The total
cost of preparing soil, excluding materials such as fertilizers, is,
given the above assumptions, $1500.
14. Cost per acre of seeding (excluding cose of seed): It is
assumed for the sample facility that seeding will cost $150 per acre.
15. Total cost of seeding (excluding seed) (Line 3 x Line 14):
Given the above assumptions, the total cost of seeding for the facility is
$2250.
16. Cost per acre of mulching: The cost per acre of purchasing and
applying a hay mulch is assumed to be $120.
17. Total mulching costs (Line 3 x Line 16): Given the above assump-
tions, total mulching costs, including costs of hay, are $1800 for the
18. Total costs for vegetation (sum of Lines 7, 11, 13, 15, and 17):
The total costs for establishing vegetation are $7425.
E. ground-Water Monitoring
Assume that closure of the landfill will require a total of 90 days.
In order to determine the maximum possible ground-water monitoring costs,
the most extensive monitoring needed at closure is assumed. Assuming
that ground-water quality analyses are required annually and ground-water
contamination analyses are required semi-annually, the most expensive
case is that in which both sets of analyses are required during the 90-
day closure period.
1. Number of wells monitored: For the sample landfill, it is assumed
chat eight wells would need to be monitored.
2. Number of samples per well: One sample is taken per well for
both analyses.
3. Total number of samples (Line 1 x Line 2): Given the above
assumptions, eight samples are required.
9-61
-------
4. Number of hours required for collecting Che sample: It Is
assumed that experience has shown that 2 hours are sufficient to
gather samples from each well.
5. Total number of hours required for collecting the samples
(Line 3 x Line 4): For eight samples, 16 hours are required for collec-
ting the samples.
6. Number of hours required for preparing and delivering the
sample: It is assumed for the example that experience has shown that
this can be done in 3 hours.
7. Person-hour costs for collecting samples: Assume that the
fully-loaded costs for labor required for collecting, preparing and
delivering the sample averages $15 per hour.
8. Total sampling and collecting coats ((Line 5 + Line 6) x Line 7)
This results in total sampling and collection costs of $285.
9. Number of ground-water quality analyses: One analysis must
be made for each veil sample, for a total of eight.
10. Number of ground-water contamination analyses: One analysis
must be made for each well sample, for a total of eight.
11. Unit cost of ground-water quality analysis. It is assumed
chat the coat of an analysis for the following parameters is $77 per
sample:
Chloride $ 6/sample
Iron $12/sample
Manganese $12/sample
Phenols $25/sample
Sodium $12/sample
Sulfate $10/sample
12. Cost of ground-water contamination analysis. It Is assumed
chat an analysis for the following parameters is $108 per sample:
pH $ 4/sample
Specific Conductance $ 4/sampla
Total Organic Carbon $25/sample
Total Organic Halogen $75/sample
13. Total ground-water quality analysis costs (Line 9 x Line 11):
For eight samples at $77 per analysis, this yields a total cost of $616.
9-62
-------
14. local ground-water contamination analyst* coses (Lina 10 x
Line 12): For aight samples at $108 par analysis, this yialds a total
cost of $864.
IS. Total analysis costs (Lina 13 + Lina 14): The total analyses
costs, therefore, are $1480.
16. Number of technical hours for administration: This includes
all time necessary to administer and report the data from the analyses
and is estimated as 8 hours.
17. Person-hour technical costs: The fully-loaded cost required
for this work is assumed to be $30 per hour.
18. Total technical costs for administration (Line 16 x Line 17):
Given the above assumptions, total costs for administering the tests
are assumed to be $240.
19. Number of clerical hours: Assume for this case that 5 hours of
clerical time are required to produce Che necessary reports.
20. Per-hour clerical costs: Assume the fully-loaded costs for
clerical work are $8 per hour.
21. Total administrative costs (Line 19 x Line 20): Given the above
assumptions, the total clerical costs are $40.
22. Total administrative costs (Line 18 + Lina 21): The sum of
technical and clerical costs are then $280.
23. Monitoring equipment maintenance: It is assumed chat an average
of $150 is required for a 90-day period to ensure adequate maintenance of
monitoring equipment and walls.
24. Total monitoring costs (sum of Lines 8, 15, 22, and 23): Tocal
monitoring costs, excluding administration and contingencies, are then
$2195.
F. Fence Maintenance
For a 75-acre site, assuming that the site is square, each side of
the sice is 1807 feet in length. The perimeter of the site is then
7228 feet.
1. Length of fence to be replaced: It is expected that some
sections of che facility's security fence will have corroded and will
have co be replaced. Our estimate is chat 10Z of the perimeter fence
will have co be replaced.
9-63
-------
2. Unit cose of replacing fence: The security fence around che
facility perimeter is a galvanized metal chain link fence 6 feet high.
This fence is made of #9 wire. The unit replacement cost for this
fence is $13.06 per linear foot.
3. Total coat of replacing fence (Line 1 x Line 2): The coat of
fence replacement is the product of the length of fence needing re-
placement and the unit cost of replacement, for a total of $9442.
G. Professional Certification
1. Number of person-hours required for inspections: It is
assumed that SO hours are required for periodically inspecting all as-
pects of closure of the landfill.
2. Coat per person-hour: In this case, assume that a registered
independent profeaalonal engineer may be hired at a coat of $75 per hour.
3. Total coats of independent profesaional engineer's time (Line
1 x Line 2): This yields a total coat of $6000 for the independent
professional engineer.
4. Number of technical hours required for administrative duties:
Assume chat 8 hours are required from the owner/operator's staff for
administrative duties connected with employing an independent professional
engineer.
5. Person-hour costs for technical administrative duties: It is
assumed that the total fully-loaded costs for the owner/operator's rtaff
are $30 per hour.
6. Total administrative coats for technical labor (Line 4 x Line 5):
Given the above assumptions, the total administrative costs for technical
labor are $240.
7. Number of clerical hours required for administrative duties:
Assume that 5 hours of clerical time are required for the necessary typing
and certifications.
8. Person-hour costs for clerical administrative duties:. Fully-
loaded costs of clerical time are assumed to be $8.
9. Total administrative costs for clerical labor (Line 7 x Line 8):
Given the above assumptions, total clerical coats are $40.
9-64
-------
10. local administrative co«t« (Lin* 6 + Line 9): Sunning technical
and clerical labor, the total administrative coats are $280.
11. Total certification costs (Line 3 + Line 10): The total costs
for certification, including the engineer's fees and administrative costs,
is then $6280.
H. Total Closure Costs Including Administration and Contingencies
Lines 1.through 7 of this Worksheet simply summarize the total closure
costs, excluding administration and contingencies, from each of the prior
worksheets.
8. Total of Lines 1 through 7: The total costs for the activities
listed in Lines 1 through 7 are $130.020.
9. Administration: For administrative tasks, including taxes,
insurance, and administration and supervision not included elsewhere,
a total of 13 percent of total costs from Line 8 is used.
10. Contingencies: A general provision for contingencies of 13
percent of total costs has been included.
11. Total closure costs (Line 8 + Line 9 + Line 10): The estimated
cocal closure costs are then $169,026.
9-65
-------
LANDFILLS
WORKSHEET A - DISPOSING OF INVENTORY
1. Volume of waste when processed for disposal 800 cu. yds.
2. Estimated volume of re«idue and contaminated 600 cu. yds.
soil to be disposed through on-*ite landfill
operation
3. Total volume of waste to be landfilled on-site 1400 cu. yds.
(Line 1 + Line 2)
4. Estimated cost of constructing trench $18,000
5. Estimated cost of placing waste in $ 6,000
trench
6. Total cost of disposing of inventory $24.000
(Line 4 + Line 5)
9-66
-------
LANDFILLS
WORKSHEET B - DECONTAMINATING TEX FACILITY
1. ATM of facilicy contaminated
2. Depth of matarial removed
3. Cost of removal
4. Quantity diapoeed on-aite (see Worksheet A
to develop coat)
5. Quantity diaposed off-eite
6. Coat to decontaminate equipment
7. Volume of waate reaulting from decontaminating
equipment
8. Unit coat of off-eite diapoaal ($/cu. yd.)
9. Unit coat of hauling ($/cu. yd.)
10. Total coat of diapoaing off-site (Line 7 x Line 8)
11. Total coat of hauling (Line 7 x Line 9)
12. Total coata of decontaminating the facility
(Line 3 + Line 6 + Line 10 + Line 11)
1800 aq. yda.
.33 yd. (1 ft.)
$840
600 cu. yda.
0
$1000
25 cu. yda.
$40
$10
$1000
$250
$2850
9-67
-------
LANDFILLS
WORKSHEET C - PLACING FINAL CAP
1. Area co be capped (Include sum of all portions
of the facility remains open and any portions of
the facility opened to dispose of inventory and
wastes from the process of decontamination)
2. Type of material used for impermeable layer
48,400 sq. yds.
(10 acres)
Clay with perm-
eability of 10"7
3. Depth of material of impermeable layer
4. Volume of material to be used for impermeable
layer (Line 1 x Line 3)
5. Source of impermeable material
6. Cost of impermeable material
7. Depth of topsoil
8. Volume of topsoil (Line 1 x Line 7)
9. Source of topsoil
10. Cost of topsoil
11. Cost per cu. yd. for hauling, spreading and
compacting
12. Cost of impermeable portion of cap
(Line 4 x Line 11)
13. Cost of placing topsoil (Line 8 x Line 11)
14. Total costs (Line 6 + Line 10 + Line 12 + Line 13)
.667 yds. (2 ft.)
32,428 cu. yds.
On-site from
previous exca-
vations
0
.667 yds. (2 ft.)
32,428 cu. yds.
On-site from
previous exca-
vations
0
$1.20
$38,914
$38,914
$77.828
9-68
-------
LANDFILLS
WORKSHEET D - PLANTING FINAL VEGETATION
1. Area not yet vegetated (should be approximately
equivalent to area remaining open)
2. Area already closed but in need of son* replanting
prior to final closure
3. Total area to be planted (Line 1 + Line 2)
4. Type of vegetation to be used
5. Quantity of seed per acre
6. Cost of seed per pound
7. Total cost of seed (Line 3 x Line 5 x Line 6)
8. Type of fertilizer to be used
9. Quantity of fertilizer per acre
10. Cost of fertilizer per ton
11. Total cost of fertilizer (Line 3 x Line 9 x
Line 10)
12. Cost of soil preparation per acre
13. Total cost of preparing soil (excluding
materials) (Line 3 x Line 12)
14. Cost per acre of seeding (less materials)
15. Cost of seeding (Lin* 3 x Line 14)
16. Cost per acre of mulching
17. Total mulching costs (Lin* 3 x Line 16)
18. Total coats for vegetation
(Line 7 + Line 11 + Line 13 + Line 15 + Line 17)
10 acres
5 acres
15 acres
Coarse grass
150 Lbs.
$.50
$1125
10/10/10
.25 tons
$200
$750
$100
$1500
9-69
-------
LANDFILLS
WORKSHEET E - GROUND-WATER MONITORING
1. Number of wells monitored 8 wells
2. Number of samples per well 1 sample
3. local number of samples (Line 1 x Line 2) 8 samples
4. Number of hours required for collecting sample 2 hours
(per sample)
5. Total number of hours required for collecting samples 16 hours
(Line 3 x Line 4)
6. Number of hours required for preparing and delivering 3 hours
samples
7. Person-hour costs for collecting samples $15
8. Total sampling and collection costs $235
((Line 5 + Line 6) x Line 7)
9. Number of ground-water quality analyses 8 analyses
10. Number of ground-water contamination analyses 8 analyses
11. Unit cost of ground-water quality analysis $77
12. Cost of ground-water contamination analysis $108
13. Total ground-water quality analysis costs $616
(Line 9 x Line 11)
14. Total ground-water contamination analysis costs $864
(Line 10 x Line 12)
15. Total inalyses costs (Line 13 + Line 14) $1480
16. Number of technical hours for administration (e.g., g ,
reporting data to EPA)
17. Person-hour technical costs $30
18. Total technical coses for administration $240
(Line 16 x Line 17)
19. Number of clerical hours 5 hours
20. Person-hour clerical costs $8
21. Total clerical coses (Line 19 x Line 20) $40
22. Total administrative costs (Line 18 + Line 21) $280
9-70
-------
WORKSHEET E - continued
23. Monitoring «quipnant •aintanance
24. Total monitoring costs (Lin« 8 + Line 15 +
Line 22 + Line 23)
9-71
-------
LANDFILLS
WORKSHEET F - FENCE MAINTENANCE
1. Length of fence to be replaced
2. Unit cost of replacing fence
3. Total cost of replacing fence
(Line 1 x Line 2)
9-72
-------
LANDFILLS
WORKSHEET G - PROFESSIONAL CERTIFICATION
1. Number of person-hours required for inspections
2. Cost per person-hour
3. Total costs of independent professional engineer
certification (Line 1 x Line 2)
4. Number of technical hours required for administrative
duties
5. Person-hour costs for technical administrative duties
6. Total administrative costs for technical labor
(Line 4 x Line 5)
7. Number of clerical hours required for administrative
duties
8. Person-hour costs for clerical administrative duties
9. Total administrative costs for clerical labor
(Line 7 x Line 8)
10. Total administrative costs (Line 6 + Line 9)
11. Total certification costs (Line 3 + Line 10)
80 hrs,
$75
$6000
8 hrs.
$30
$240
5 hrs.
$8
$40
9-73
-------
LANDFILLS
WORKSHEET H - TOTAL COSTS OF CLOSURE INCLUDING
ADMINISTRATION AND CONTINGENCIES
1. Cost of disposing of inventory (From Worksheet A) $ 24,000
2. Cost of decontaminating the surface and ancillary $ 2,850
facilities (from Worksheet B)
3. Cost of placing the final cap (From Worksheet C) $ 77,828
4. Cost of planting final vegetation (From Worksheet D) $ 7,425
5. Cost of ground-water monitoring (From Worksheet E) $ 2,195
6. Cost of fence maintenance (From Worksheet F) $ 9,442
7. Cost of professional certification (From Worksheet G) $ 6,280
8. Total of Line 1 through Line 7 $130,020
9. Administration $ 19,503
10. Contingencies $ 19,503
11. Total costs of closure (Line 8 + Line 9 + Line 10) $169.026
9-74
-------
9.5
EXAMPLE - INCINERATORS
A 12-acre incinerator facility has bulk storage facilities for 120,000
gallons of slop oil, 120,000 gallons of phenolic wastewater, and 1,000,000
gallons of organic sludge. Waste is also delivered in 55-gallon drums; a
maximum of 600 drums may be stored at the facility. In addition to these
delivered wastes, the facility normally contains an Inventory of 50 drums
of non-combustible ash from the incinerator.
The incinerator is designed to operate at 16 gpm with the following
feed mixture: 4 gallons of slop oil, 4 gallons of wastewater, and 8 gallons
of sludge (a 1/1/2 ratio). The total operating horsepower of the incinerator
(including pollution control equipment in the form of a caustic scrubber
used to remove chlorinated compounds emitted from the slop oil) is 350 HP.
The following worksheets are based on this facility description.
9-75
-------
SAMPLE CLOSURE COST ESTIMATING WORKSHEETS: INCINERATORS
A. Characterizing the Waste Inventory
Worksheet A is used to describe each waste accepted at the site. For
the example, worksheets must be prepared for each of the following wastes:
slop oil, phenolic vascewater, and biological treatment sludges. For each
waste product accepted, the following information is required:
1. Describing the waste: Describing the origin and general nature
of the waste.
2. Chemical composition: Chemical composition should be expressed
in weight percents for major components and parts per million (ppm) for
trace components. This information should be readily available to the
operator from the bill of,lading for each waste shipment.
3. Physical state of the waste: This describes whether the waste is
a liquid, solid, or mixture. This information is utilized in making.estimates
of solid residues requiring disposal (Worksheet B).
4. Heat of combustion of the waste: The heat content (expressed in
BTU/lb., or BTU/gal.) of the waste products. This information is used in
determining auxiliary fuel requirements (if any) on Worksheet C.
5. Specific gravity of the waste: The specific gravity of the waste
at 60 F referenced to water at 60 F is used in the example problem.
6. Closure inventory: For the example, it has been assumed that the
operator has identified from experience that the maximum inventory he has
ever had stored on-site was a 14-day backlog. We will assume that this
inventory is comprised of the total components: 224 drums of slop oil
(12,320 gallons), 224 drums of phenolic wastewater (12,320 gallons) and
152 drums of sludges (8,360 gallons); the bulk storage tanks contain 28,000
gallons of slop oil, 28,000 gallons of phenolic wastewater, and 233,560
gallons of organic sludges. Under these conditions, the incinerator will
be able to treat its inventory through seven days of burning its optimum
feed mixture, and seven days of burning sludges alone (through the addition
of auxiliary fuels).
9-76
-------
B. Treating the Inventory
It Is assumed that the Inventory on-hand at the time of closure will
be incinerated on-site. All equipment necessary for the operation of the
incinerator is assumed to be in complete working order.
1. Time required for treating the inventory: It will require 336 hours
(322,560 gallons of waste T 960 gallons throughput per hour). If it is
further assumed that the incinerator is on-stream 90% of the time, the total
time required for treating on-site inventory is 373 hours.
2. Manpower requirements for treating the Inventory: The total number
of personnel required to operate this facility (including plant operators,
equipment operators, guards, maintenance persons, and laboratory personnel) "
is estimated as six. Therefore, total man-hour requirement for treating
the inventory is 2238 hours.
3. Cost of manpower: The average hourly wage rate of a plant operator
(including fringe benefits and labor burdens) is assumed to be $20.
4. Total costs of operating labor during inventory treatment (Line 2
x Line 3): Given the above assumptions, labor costs for this phase of
closure are $44,760.
5. Fuel requirements for treating the inventory: These represent both
the cost of utilities consumed in order to treat the waste inventory, plus
any auxiliary fuels which had to be purchased. Each of these items is
separately coated below.
6. Electricity requirements for treating the inventory: The inciner-
ator is actually in operation for 336 hours. Electricity requirements for
KW
Che example are equal to 350 HP x .746 {=• x 336 hours - 87,730 kwh.
7. Costs of electricity: Electricity is assumed to be available at
a cost of $.06/kwh.
8. Total costs of electricity (Line 6 x Line 7): Total electricity
costs for the example are $5264.
9. Auxiliary fuel requirements: During the first 168 hours of inven-
tory treatment, the incinerator will be receiving an input feed of 25Z slop
oil, 252 phenolic wastewater, and 50Z organic sludges. This feed has a
heat value of 2900 BTU/lb. and will burn autogenously. During the remaining
168 hours, the feed will be comprised entirely of sludges, with a heat
value of 700 BTU/lb.; this mixture does require auxiliary fuel inputs.
9-77
-------
10. Type of auxiliary fuel used: It la assumed chat #6 fuel oil is
used as the auxiliary fuel.
11. Quantity of fuel required: Using engineering analysis, and
assuming an average heat value of 154,000 BTU/gal. for fuel uil, total
auxiliary fuel requirements are estimated at 10,456 gallons.
12. Cost of auxiliary fuel: It is assumed that #6 fuel oil is available
to the operator at $.90 per gallon.
13. Total cost of auxiliary fuels (Line 11 x Line 12): The total
cose of auxiliary fuel inputs is $9410.
14. Total fuel coses (Line 8 + Line 13): Total fuel costs are $14,674.
15. Chemical requirements: This category includes all chemicals,
catalysts, adsorbents, and other supplies consumed during inventory treat-
ment. In the example, the only chemical required is the caustic consumed
during flue gas scrubbing of chlorine entrained in the incinerator waste
scream.
16. Type of chemicals used: It is assumed thac the caustic will be
purchased as a 50Z solution.
17. Quantity of chemicals required: There are 40,320 gallons of slop
oil in the waste inventory assumed to be present at che time of closure.
This is equivalent to 319,334 Ibs. of slop oil (40,320 x .95 specific
gravity of slop oil x 8.34 Ibs./gal. water). Since the chlorine concent
of che slop oil is assumed Co be no greater than 3 percent, Che maximum
quantity of chlorine to be scrubbed is 9,580 Ibs. (270 moles). Assuming
thac 1 mole of NaOH is required Co neutralize 1 mole of chlorine, 270 moles
x 40 Ibs. NaOH/mole - 10,800 Ibs. NaOH consumption.
18. Cose of chemicals required: Caustic is assumed to cost $.08257
dry Ib.
19. Total cost of chemicals (Line 17 x Line 18): The toeal cost of
chemicals consumed during inventory treatment is $891.
20. Disposing or creating residues generaced during inventory treatment:
The residue generated during inventory treatment is a powdery solid, inciner-
ator ash. The ash has a *pvcffic gravity of 2.5.
21. Amount of residue on-s'ite after treating the inventory: There
are 50 55-galIon drums of ash stored on-site at the point of closure (each
weighing 1150 Ibs., for a total of 57,500 Ibs.). In addition, residues
9-78
-------
are generated by processing the waste inventory. The sludges incinerated
in the example are assumed to be 10 percent solids; one-third of the solids
are assumed to be non-combustible. The slop oil and wastewaters processed
by the incinerator produce no ash. Therefore, the amount of new residue
generated - (total amount of sludge in inventory times specific gravity
of the non-combuscible portion of the materials times the portion of the
sludge chat is non-combustible), or:
241,920 x (2.5 x 8.34) x .0333 • 167,968 Ibs.
Total residue to be disposed of is equal to 167,968 Ibs. and 57,500 Ibs. -
225,468 Ibs.
22. Method of disposing of ash: It is assumed that the incinerator
ash is put into drums and transported to a secure landfill. The residue
generated during inventory treatment can be placed in 146 drums, making
the total number of drums to be disposed of 196.
23. Unit costs of disposing of residue: The costs of disposing in
a landfill are assumed to be $50/drum, according to industry specialists.
24. Total costs of disposing of residue (Line 21 z Line 23): Total
costs for the sample case are $9800.
25. Costs of hauling residue to landfill for disposal: In the example,
it is assumed that the nearest landfill that will accept the drummed
residue is 50 miles away, and that trucks with a carrying capacity of 40
drums are rented at an hourly cost of $60. At a speed of 40 mph, and
assuming four hours for loading/unloading each trip, the total hauling
costs are estimated at $1950.
26. Total cost of treating and disposing of inventory (sum of Lines
4, 14, 19, 24, and 25): Given the above assumptions, the total cost of
inventory disposal will be $72,075.
C. Decontaminating the Facility
In order to completely decontaminate the incinerator facility, the opera-
tor must see to it that all storage tanks and liquid waste feed lines are
cleaned, that wastewaters from the cleaning process are properly disposed
or treated, that all equipment structures and containers left on-site are
decontaminated, and that all contaminated soil is removed properly. These
various activities are individually cos ted below.
9-79
-------
Tank Cleaning
1. Storage tank cleaning: The total volume of storage capacity to
be cleaned is 1,240,000 gallons (120,000 gallons of slop oil storage,
120,000 gallons of phenolic vastevater storage, and 1,000,000 gallons of
organic sludge storage).
2. Mechod used: The cleaning method selected for the sample case
is steam-cleaning.
3. Unit cost of cleaning: Renting equipment, labor, and operating
costs for 1600 gal./hour of cleaning equipment are assumed to be approxi-
mately $.02/gal. of capacity cleaned, based on information from the Means
construction cost guide.
4. Total costs of storage tank cleaning (Line 1 x Line 2): Total
costs of steam-cleaning the storage facility are $24,800, given the above
assumptions.
5. Cleaning residue generation: According to closure guidelines for
waste treatment sites issued by the Texas Department of Water Resources,
the amount of contaminated vashvaters produced by steam-cleaning can be
assumed to be equal to .125 times the volume of the tank being cleaned.
6. Quantity of cleaning residue generated (Line 1 x Line 5):
155,000 gallons of contamined washwater are generated in the example.
7. Method of disposing of residue: In the sample case, residues are
assumed to be transported by tank truck to a surface impoundment for
evaporation.
8. Unit costs for disposing of residues: Based on waste disposal
industry estimates, it will cost $.05/gal. to dispose of residues in an
impoundment. •
9. Total costs for disposing of residues (Line 6 x Line 8): Total
costs of cleaning residue disposal, given these assumptions, are $7750.
10. Hauling costs for residues: In the example, hauling cose esti-
mates are based on the following assumptions - the distance between the
incinerator and the surface impoundment is 100 miles one-way, a 7000-gallon
trailer is used, the average trip speed is 40 mph, and the hourly rental
1
cost of truck and driver is $60. The cost of one round trip is $300.
11. Number of trips required: The number of trips required for the
case is 23.
9-80
-------
r.-fal Tiatt'. tug ..•«(.* r^i i*»Uii^a iiiue 10 * Line 11); In*
costs for residue disposal are estimated at $6900.
Decontaminating the Facility
13. Flush out liquid waste feed lines: The estimated cost of flush-
ing out all liquid residues from feed lines on the facility (before the
storage areas and incinerators are cleaned) 1* assumed to be roughly one-
eighth of the costs of tank cleaning, or $3000.
14. Pump out and backfill sumps: Sumps are to be decontaminated to
prevent the possibility of rain water accumulating and contaminating these
portions of the facility. The estimated costs of this activity are
$2000.
L5. Removing contaminated soils: Because of spills and other
accidental releases, certain areas of the waste disposal site such as
the dikes in areas around storage tanks may be contaminated. We have
assumed in this example problem that 2.5 percent of the area of the site
(exclusive of reservoirs, ponds, and basins) is contaminated.
Contaminated area • .025 x 12 acres x 4SAO sq. yd./acre
- 1452 sq. yds.
16. Depth of soil removal: For this example, the assumed depth of
soil removal is one foot.
17. Total amount of soil removed (Line 15 x Line 16): The total
amount of soil removed in this example is (1452 x .333), or 484 cu. yds.
IS. Unit cost of removing soil: Costs of removing soil (including
equipment rental) are estimated at $1.60/cu. yd.
19. Total cost of soil removal (Line 17 x Line 18): Given the above
assumptions, the cost of removing the contaminated soil from the inciner-
ator site is $774.
20. Costs for disposing of contaminated soils: The contaminated soil
is assumed to be disposed in a sanitary landfill. Based on current esti-
mates, the soil can be landfilled at a cost of $30/ton.
21. Total cost of disposing of soil (Line 17 x Line 20): The cost
of disposing of the contaminated soil is $14,520.
22. Hauling coses for contaminated soil: In this example, the
nearest landfill is assumed Co be 50 miles away, the truck used for hauling
9-81
-------
h«* * carrying capacity of 44,000 Iba., and la ranted ac a hourJy eo«i
of $60.
23. Numbar of trlpa required: Assuming an average speed of 40 mph,
22 crips will be required.
24. Total hauling coats for contaminated soil (Line 22 x Line 23):
Given the above assumptions, the total costs for hauling the contaminated
soil are $3300.
25. Total costs of decontaminating the facility (sum of Lines 4, 9,
12, 13, 14, 19, 21, and 24): The total costs of decontaminating the
sample incinerator are $63,044.
D. Monitoring
1. Cost of air sampling during inventory treatment: In order to
ensure that the incinerator remains in compliance vith Clean Air Act
regulations during the closure period, it wms assumed that daily sampling
cost of $25 are incurred while the incinerator is operating.
2. Number of samples required: The inventory treatment phase of
closure is estimated to take 16 days at the sample site.
3. Total coses of monitoring (Line 1 x Line 2): Given the above
assumptions, monitoring costs will be equal to $400.
E. Professional Certification
1. Number of person-hours required for inspections: Ic is assumed
that 20 hours are required for periodically inspecting all aspects of
incinerator closure.
2. Cost per person-hour: In this case, assume that a registered
independent professional engineer may be hired at a cost of $75 per hour.
3. Total costs of independent professional engineer's time (Line 1
x Line 2): This yields a total cost of $1500 for the independent profes-
sional engineer.
4. Number of technical hours required for administrative duties:
Assume that eight hours are required from the owner's or operator's staff for
administrative duties connected with employing an independent professional
engineer.
9-82
-------
5. P«r»oo-hour costs for techelnsl aevlaiatcatlve duties: It la.
assumed chat the total fully-loaded coats for the owner's or operator's staff
are $30 per hour.
6. Total administrative costs for technical labor (Line 4 x Line 5):
Given the above assumptions, the total administrative coats for technical
labor are $240.
7. Number of clerical hours required for administrative duties:
Assume that five hours of clerical tine are required for the necessary
typing and certifications.
8. Person-hour costs for clerical administrative duties: Fully-
loaded costs of clerical time are as sums d to b* $6.
9. Total administrative costs for clerical labor (Line 7 z Line 8):
•
Given the above assumptions, total clerical costs are $40.
10. Total administrative costs (Lioe 6 4- Line 9): Summing technical
and clerical labor, the administrative coats are $280.
11. Total certification costs (Line 3 + Line 10): The total costs for
certification, Including engineer's fees and administrative costs, are
$1780.
F. Total Costs Including Administration and Contingencies
Line 1 through 4: These lines simply require the transfer of the
cost information supplied in Worksheets B through E.
5. Preliminary closure cost estimate (sum of Lines 1 through 4):
For the sample facility, total worksheet costs are qual to $137,299.
6. Administration: The costs for administration, which include
insurance, taxes, and supervision and administration not included else-
where, are assumed to be 15 percent of Line 5.
7. Contingencies: A provision for contingencies of 15 percent of
Line 5 has been included.
8. Total costs of closure (Line 5 + Line 6 + Line 7): The total
costs of closure, including administration and contingencies, for the
sample incinerator are $178,489.
9-83
-------
INCINERATORS
WORKSHEET A - CHARACTERIZING THE WASTE (#2)
This worksheet should be used to describe each waste accepted at the facility.
1. Description of the waste:
Phenolic wastewater
2. Chemical composition of the waste:
1000 ppm phenols
3. Physical state of the waste:
Liquid
4. Heat of combustion of the waste:
0
•
5. Specific gravity of the waste:
1.0
6. Closure inventory:
40,320 gal.
9-84
-------
INCINERATORS
WORKSHEET A - CHARACTERIZING THE WASTE (13)
This worksheet should be used to describe each waate accepted at the facility.
1. Description of the waste:
Waste activated sludge
2. Chemical composition of the waste:
3. Physical state of the waste:
Mixture (suspension) - 10Z solids, 901 water
4. Heat of combustion of the waste:
700 BTU/lb.
5. Specific gravity of the waste:
1.06
6. Closure inventory:
241,920 gal.
9-85
-------
INCINERATORS
WORKSHZET B - HEATING THE INVENTORY
1. Time required for treating the inventory
2. Manpower requirements for treating the inventory
3. Unit cost of labor
4. Total cost of labor - treating the inventory
(Line 2 x Line 3)
5. Fuel requirements
6. Electricity requirements
7. Unit cost of electricity
3. local costs of electricity (Line 6 x Line 7)
9. Auxiliary fuel requirements
10. Type of fuel used
11. Quantity of fuel required
12. Unit cost of fuel oil
13. Total cost of auxiliary fuels
(Line 11 x Line 12)
14. Total fuel costs for treating inventory
(Line 8 + Line 13)
15. Chemical requirements
16. Type of chemicals used
17. Quantity of chemicals used
18. Unit cost of chemicals
19. Total cost of chemicals (Line 17 x Line 18)
20. Residues generated during inventory treatment
21. Amount of residue generated
22. Method of treatment
23. Unit cost of disposing of residue
24. Total costs of disposing of residue
(Line 21 x Line 23)
25. Hauling costs for disposing of residue
26. Total costs of treating and disposing of
inventory (sum of Lines 4, 14, 19, 24, and 25)
9-86
373 hours
2238 man-hours
$20/hr..
$44,760
Yes
87,730 kwh
$.06/lcwh
$5264
Yes, for input
feed B
#6 fuel oil
10,456 gal.
$.90/gal.
$9410
$14,674
Yes
Caustic, 50% solution
10,800 Ibs.
$.0825/lb.
$891
Incinerator ash
225,468 Ibs.
(196 drums)
Landfill
$50/dmm
$9800
$1950
$72.075
-------
INCINERATORS
WORKSHEET C - DECONTAMINATING THE FACILITY
1. Volume Co be cleaned
2. Method used
3. Unit costs of cleaning
4. Total costs of tank cleaning (Line 1 x Line 2)
5. Cleaning residue generation rate
6. Amount of residue generated (Line 1 x Line 5)
7. Method of disposal
8. Unit cost for disposing of residue
9. Total costs for disposing of residue
(Line 6 x Line 8)
10. Unit cost for hauling residues
11. Number of trips required
12. Total coses of hauling residues
(Line 10 x Line 11)
13. Cost of flushing liquid waste feed lines
14. Cost to pump out and backfill sumps
15. Amount of contaminated soil area
16. Depth of soil removal
17. Total amount of soil removed (Line 15 x Line 18)
13. Unit cost of removing soil
19. local cost of removing soil (Line 17 x Line 18)
20. Costs for disposing of contaminated soils
21. Total cost of disposing of soil (Line 17 x Line 20)
22. Unit costs of hauling contaminated soils
23. Number of trips required
24. Total cost of hauling soils (Line 22 x Line 23)
25. Total costs of decontamination (sum of Lines
4, 9, 12, 13, 14, 19, 21, and 24)
1,240,000 gal.
Steam-cleaning
$.02/gal. capacity
$24,800
.125 x volume of tank
155,000 gal.
Surface impoundment
$.05/gal.
$7750
$300/trip
23
$6900
$3000
$2000
1452 sq. yds.
1 ft.
$774
$1.60/cu. yd.
$774
$30/ton
$14,520
$150
22
$3300
$63.044
9-87
-------
INCINERATORS
WORKSHEET D - MONITORING
1. Cost of air sampling
2. Number of samples required
3. local costs of air monitoring (Line 1 x Line 2)
9-88
-------
INCINERATORS
WORKSHEET E - PROFESSIONAL CERTIFICATION
1. Number of person-hours required for inspecting the 20
facility
2. Coat per person-hour $75
3. Total coats of independent professional engineer $1500
certification (Line 1 x Line 2)
4. Technical hours required for administrative 8 hrs.
duties
5. Person-hour costs for technical administrative duties $30
6. Total administrative costs for technical labor $240
(Line 4 x Line 5)
7. Number of clerical hours required for administrative 5 hrs.
duties
8. Person-hour costs for clerical administrative duties $8
9. Total administrative costs for clerical labor $40
(Line 7 x Line 8)
10. Total administrative costs (Line 6 + Line 9)
11. Total certification costs (Line 3 + Line 10)
9-89
-------
UOIKSBBZT F - TOTAL COSTS OKHttWC AJJKDfXSTlATION AND CUTIPI CATION
1. Coses of treating and disposing inventory (From $ 72,975
Worksheet B)
2. Co*ts of decontaminating the facility (From $ 63,044
Worksheet C)
3. Costs of monitoring (Fro* Worksheet D) $ 400
4. Costs of professional certification (From $ 1,780
Worksheet E)
5. Estimated basic costs of closure (sum of Lines $137,299
1, 2, 3, and 4)
6. Administration $ 20,595
7. Contingencies $ 20,595
8. Total costs of closure $178,489
9-90
-------
9.6 EXAMPLE - MDLTIPLE PBOCISS FACILITY WITH TAJKS
AMD SURFACE BmtOODMHRS
A 2-ecre hazardous vast* treatment and storage facility haa storage
tanks for 60,000 gallons of vasta sol-wits and 10,000 gallons of slop
oil. Wasta is received at tha facility both from tank tracks and in
55 gallon druas; tba facility haa a mrrlmn» storaga capacity of 200
drums. Thara axa two treatment process** emdertaken at tha facility.
There is a 30,000 gallon (SO1 z 20' x 4') concrete-lined surfaca
impoundment used for tha gravity separation of oily wastes into solvent,
slop oil, and sludge phases. The normal composition of the oil wastes
accepted is 80 percent solvent, 15 percent oil, and 5 percent sludge.
There is a 30,000-gallon clay-lined surface impoundment (also 50* x 20'
x 4') for solidifying pickling liquor wastes. A storage pile holds
up to 8,000 cu. ft. of solidified pickling wastes; it is surrounded
by a clay-lined surface iapoundaent that collects drainage and run-off.
9-91
-------
SA.1PLE CLOSURE COST ESTIMATING WORKSHEETS: MULTIPLE PROCESS FACILITY
A. Characterizing th« Waste
Worksheet A is used to describe each waste accepted at the facility.
For example, separate worksheets must be prepared for each of the following
wastes: oily wastes and pickling liquor wastes (the two types of wastes
processed at the storage facility) and the three end products of the treat-
ment actions performed (waste organic solvents, slop oil, and solidified
pickling liquor wastes). For each waste product specified, the following
information is required:
1. Describing the waste: Describe the origin and general nature
of the waste.
2. Chemical composition: Chemical composition should be expressed
in weight percents for the various major components, and in parts per million
(ppm) for any trace components. This information may be readily available
to the operator from the bill of lading for each waste shipment.
3. Physical state: This describes whether the waste is a liquid,
solid, or mixture. This information is used in making estimates of solid
residues requiring disposal (Worksheet B).
4. Heat of combustion of the waste: Represents the heat content
(expressed in BTU/lb. or BTU/gal.) of the waste products. The information
is used to determine auxiliary fuel requirements if the waste is to be
disposed of through incineration.
5. Specific gravity of the waste: The specific gravity of the waste
at 60 F referenced to water at 60 F.
6. Closure inventory: The operator must identify the maximum quan-
tity of each waste that can be present at the facility in storage tanks,
drums, or surface impoundments, during any point in the facility's active
life. In the example, it is assumed that there are times in which the stor-
age capacity of this facility is completely utilized. This would therefore
represent the maximum inventory for developing the closure cost estimate.
In the sample case, the closure inventory would consist of 65,500 gallons
of waste solvents, 10,000 gallons of slop oil, 35,000 gallons of oily waste,
30,000 gallons of pickling liquor waste and 8,000 cu. ft. of solidified
pickling wastes.
9-92
-------
B. Treating Inventory
1. Waste inventory: As noted in the waste characterization section
of this example, the sample facility is assumed to have the following waste
products on-site at the time of disposal: 35,500 gallons of oily waste,
30,000 gallons of pickling liquor wastes, 65,500 gallons of recovered waste
solvent, 10,000 gallons of recovered slop oils, and 8,000 cu. ft. of solidi-
fied pickling wastes.
2. Methods of treatment or removal: These materials will be removed
of in a variety of ways, as indicated below:
a. Solvents - it is assumed that the facility can find other manu-
facturing/commercial establishments that will use the waste solvents (which
have a BTU content of 135,000 BTU/gal.) as boiler fuel.
b. Slop Oils - pumped out of storage and hauled to an Incinerator.
c. Oily Wastes - placed in surface impoundment for separation
into its component parts. Solvents and slop oils recovered from this pro-
cess are disposed of in the same manner as (a) and (b) above. Sludges left
in the basin are to be dredged, stabilized.and hauled to a landfill.
d. Pickling Liquor Wastes - solidify with cement and transfer
the resulting solid waste to a landfill.
e. Solidified Pickling Liquor Wastes - transfer to a land-
fill.
Since treatnent of inventory categories (c) and (d) will generate
additional waste products in categories (a), (b) and (e), these preliminary
processing phases will be discussed first.
Disposing of Oily Waste
3. Composition of oily wastes: It is assumed that the normal compo-
sition of the oily wastes is 80 percent solvent, 15 percent slop oil, and
5 percent sludge.
4. Amount of wastes produced after settling: Using this percentage
mix, settling out the inventory of oily wastes will produce 28,400 gallons
of solvent, 5,325 gallons of slop oil, and 1,775 gallons of sludge.
5. Sorbent requirements: It is assumed that the sludge will be mixed
with an equal volume of sorbent material, with a specific gravity of 1.8.
The specific gravity of the sludge is estimated at 1.2.
6. Cost of sorbent: It is assumed that sorbent material is available
on-site for no cost.
9-93
-------
7. Amount of residue generated: After stabilization, approximately
22 tons of residue will need to be landfilled.
8. Unit coat of disposing of residue: It is assumed that a land-
fill will charge $50/con to dispose of the stabilized residues.
9. Total costs of disposing of residue (Line 7 x Line 8): Given
these assumptions, the total cost of disposing of facility sludge resi-
dues will be $1100.
10. Costs of hauling residue: It is assumed that the nearest land-
fill is 100 miles one-way from the site. Trucks with a 44,000-Lb.
capacity can be rented at a cost of $60 per hour (including driver);
the average traveling speed of the truck is 40 mph. For one round trip,
the cost of residue hauling is $300.
11. Number of hauls required: With 22 tons of waste (line 7), only
one trip by a 44,000 Ib. capacity truck will be required.
12. Total cost of hauling residue (Line 10 x Line 11): Given
these assumptions, the total cost of hauling residue is $300.
13. Cost of disposing of oily waste (Lin* 6 + Line 9 + Line 12):
The total cost of disposing of oily waste is then the sum of sorbent
material costs, costs of disposal, and costs of hauling for a total of $1400.
Disposing of Pickling Liquor Waste
14. In order to solidify the pickling liquor wastes in the closure
inventory, the waste must be mixed with cement. It is estimated that
one sack (94 Ibs/sack) of cement will solidify 10 gallons of waste.
15. Amount of cement required: To dispose of on-site inventory,
3,000 sacks of cement (282,000 Ibs.) will be required.
16. Cost of cement: Cement is estimated to cost $2.50/sack.
17. Total cost of materials (Line 15 x Line 16): Given the above
assumptions, total material costs for solidifying the inventoried
pickling liquor waste are $7,500.
18. Total amount of residues produced: Given a specific gravity
of pickling wastes of 1.05, and the proportions of cement to waste
assumed, the total solid residues produced by inventory disposed is
272.4 tons.
9-94
-------
Liquor - 30.000 gal x 1.05 S.G. x 8.34 (vacer weight) •
262,800 Ib.
Cement • 3,000 sacks x 94 Iba/sack - 282,000 Ibs.
262,000 Ibs + 282,000 Ibs - 544,800 Ibs -
272.4 tons
19. Other on-sita rasiduas: Wasta catagory (a) represents
previously solidified pickling wastes stored on-site. It is assumed
that there is 8,000 cu. ft. of this material currently in storage, and
that the material weighs approximately 135 Ib/cu. ft (similar to a
mortar-like cement). Therefore, the total weight of this residue
would be 1,080,000 Ibs. (540 tons).
20. Total amount of pickling residue (Line 18 + Line 19): Total
solid residues from treatment of the pickling wastes are 812.4 tons.
21. Unit cost of disposing of residue: As in Line 8 above, it is
assumed that a landfill will charge $50/ton to dispose of such residues.
22. Total cost of disposing of residue (Line 20 x Line 21): Total
disposal costs are estimated to be $40,620.
23. Costs of hauling residues: The costs and method of hauling
residues are the same as Lin* 10 above.
24. Number of hauls required: Given truck capacity of 44,000 Ibs.
(22 tons), it will take 37 round trips to haul the solidified pickling
wastes.
25. Total cost of hauling residues: Given the above assumptions,
the total hauling costs will be $11,100.
26. Cost of disposing of pickling liquor waste (Line 17 + Line 22
+ Line 25): The total coat of disposing of pickling liquor waste is
then the sum of costs of materials, residue disposal and hauling, for a
total of $59,220.
27. Amount of solvent on-site: Including the solvents recovered
during the settling of inventoried oily waste, the total inventory of
waste solvents at the sample facility are 60,000 gal. (storage tank) 4-
5,500 gal. (drums) 4- 28,400 gal. (surface impoundment) - 93,900 gal.
28. Method of disposal: It is assumed that the waste solvents can
be provided to manufacturers as a boiler fuel.
9-95
-------
29. Coat of disposal: It Is •••timed Chat the users of ch« solven&a
will pay che coses of pumping and hauling the solvents co cheir facilities.
No additional credit is awarded to the owner/operator of the tank facility.
Treating Slop Oil
30. Amount of slop oil on-site: Including the alop oils recovered
during the settling of inventoried oily waate, the total Inventory of
slop oils are 10,000 gal. (storage tank) + 5,325 gal. (surface impound-
ment) - 15,325 gal.
31. Method of treatment: It is assumed chat the slop oils will he
trucked co an incinerator.
32. Cost of treatment: The estimated fee paid Co the Incinerator
for creating the wastes is $0.60/gallon.
33. Total costs of treatment (Line 30 x Line 32): Given che above
assumptions, ic will cost $9,195 to treat the slop oil inventory.
34. Costs of hauling: It is aaaumed that the nearest incinerator
is 50 miles away, that the wastes will be transported in a 7,000-gallon
capaclcy truck, ac an average speed of 40 oph. The hourly rental cost
for truck and driver is $60.
35. Number of hauls required: Given trailer capacity, it will
require three trips to haul the slop oils to the incinerators.
36. Total costs of hauling: Given the above assumptions, hauling
costs are estimated at $450.
37. Total coets of treating slop oil (Line 33 + Line 36): The total
costs of creating slop oil are then che sum of the costs of disposal and
hauling, for a total of $9,645.
38. Total coses of disposing of inventory (sum of Lines 6, 9, 12,
17, 22, 25, 29, 33, and 36): The total costs of che above activities
are estimated to be $70,265.
9-96
-------
C. Decontaminating the Facility
Tank Cleaning
1. Cleaning method: In tola example, the storage tanks are
steam cleaned.
2. Volume: In the sample case, there are 60,000 gallons of
solvent storage capacity and 10,000 gallons of oil storage capacity
to be cleaned, for a total of 70,000 gallons.
3. Unit cleaning costs: For a 2,000 gallon-per-hour steam cleaning
unit (capable of washing a 16,000-gallon area of storage capacity/hour),
costs of equipment rental, labor, and operation are equal to $.02/gallon
of capacity cleaned.
4. Total costs of steam cleaning (Line 2 x Line 3): Total cleaning
costs for the storage tanks is $1400.
5. Type and quantity of residues generated: Steam cleaning
generates residues in the form of contaminated vashvaters. The rate of
residue generation is 1 gallon of waste/8 gallons of tank volume. In
the example, total residues are 70,000 * 8, or 8750 gal.
6. Method of disposal: It Is assumed that the residues are hauled
to a surface impoundment and evaporated.
7. Cost of disposal: Impoundment disposal of washwaters is
estimated to cost $.05/gallon.
8. Total cost of disposal (Line 5 x Line 7): Costs cf disposing
of these cleaning residues will be $438.
9. Cost of hauling cleaning residues: For one round crip, che
cost of hauling residues is $600. The cleaning residues will be hauled
in a 7,000-gallon tank truck, with an average truck speed of 40 mph.
The hourly rental cost for truck and driver is $60; the nearest
available surface impoundment is assumed to be 200 miles away.
10. Number of hauls required: Given the assumption on residue
generation and truck capacity, two trips will be required, at 3600/crip.
11. Total costs of hauling: Total hauling costs are $1200.
12. Total costs: The sum of the costs of steam cleaning, disposal
and hauling yields a total of $3038.
9-97
-------
Decontaminating the
13. Cleaning method for Impoundment 1: It 1* attuned that che
concrete-lined impoundment will be sandblasted.
14. Are* of concrete impoundment to be cleaned: The aree requiring
sandblasting, based on the sample facility description, is equal to the
base area (5Q1 z 20', or 100 sq. ft.) plu« the area of che site
walls (21 x 50' x 4' + 2' x 20' x 4', or 560 *q. ft.), for a total of
1560 sq. ft.
13. Coses of sandblasting: A 6 cu. ft. capacity compressor will
be used In the sample estimate. The unit rents for a $lOO/week, and
coets $1.75/hour to operate; labor costs are estimated at $20/hour.
The unit can clean 40 sq. ft. of concrete/hour. Consequently, sand-
blasting coets are estimated at $.60/sq. ft.
16. Total costs of sandblasting (Line 14 x Line 15): Sandblasting
costs are estimated to be $936.
17. Type and quantity of residue generated: The residues will
consist of contaminated sands. It was assisted that 4000 Ibs. (2 tons)
of sand residue will be generated.
18. Unit coets of disposal: The sands will be landfilled at a
disposal cost of $50/ton.
19. Total costs of disposal (Line 17 x Line 18): Total disposal
costs will be equal to $100.
20. Cleaning method for Impoundment 2: All contaminated clays
from che clay-lined Impoundment will be removed and hauled to a landfill.
21. Area of clay impoundment to be decontaminated: Since the dimen-
sions of this Impoundment are the same as those of the concrete-lined
Impoundment discussed above, the surface area to be contaminated is the
same as that estimated in Line 14 of this worksheet, or 1560 sq. ft.
22. Amount of clay removed: It is assumed that the clay in the
pickling liquor impoundment has been contaminated to a depth of one
foot. Therefore, 1560 cu. ft. of clay, or 57.8 cu. yds., must be
removed.
9-98
-------
23. Ifctit coat of raaiiTtag clip: Clay feature T will be performed
with e backhoe. Including coats of equlpaent rental and labor, the
coata of removing the clay la eatiaatted to be $1.6C/cu. yd.
24. Total coata of removing clay (Line 22 * Line 23): Given the
above aaeueptlona, the eoata of reap*Ing the soil are $92.
23. Dispoeing of contaainated clay*: Claya will be haaled to a
landfill for diapoaal. The eoata of diayoaal are eatlaated to be
$30/cu. yd.
26. Total eoata of diapoaal (Line 22 x Line 25): The total coata
of diapoaal are $1734.
Eeaoving Soil and Miscellaneous Activitiea
27. Removing contaainated aoila: Becauae of spill* and other
accidental releaaaa, certain areaa of the waate diapoaal facility, such
aa diked-ln areaa around atorage tank* will be contaaineted. It ia
aaauaad for the aaaple facility that 2.5 percent of the total alte area
la contaainated.
Contaainated area « 2 acraa x 4840 sq. yd./acre x .025
rate of contamination - 242 aq. yd.
28. Aaount of aoil removed: The depth of aoil removal required
to remove all hasardooa contaainanta ia aaaoaed to be 1 foot. Thus,
the total aaount of soil reaoved - 242 aq. yd. x .33 yd. - 80.7 cu. yds.
29. Unit coat of removing aoil: Aa in Line 23, reaovlog soil can
be accomplished at a coat of $1.6O/cu. yd.
30. Total coat of removing aoil (Line 28 x Line 29): Total coat
of removing soil la $129.
31. Disposing of contaminated aoila; Contaminated soils are also
hauled to a landfill, where they may be diapoaed at a coat of $30/
cu. yd.
32. Total coata of diapoaal (line 28 x Line 31): Given the above
assumptions, diapoalng of aoila will coat $2421.
9-99
-------
33. Hauling cose* for decontamination traacee: The veates described
In Linea IT, 22, and 28 of thla tforkaheet will be hauled Co the landfill
in a 44,000-lb. truck. The landfill la assumed to be 100 milea away; the
hourly coat of truck and driver ia $60 and the average trip speed is
40 mph. Adequate dividera will be auppliad ao that mixed loada can be
carried.
34. Number of tripa required: If it ia assumed that a cu. yd. of
earth weighs approximately 2000 IDS., the hauling of these waste residues
will require seven trips.
35. Coats of hauling decontamination reeiduee (Line 33 x Line 34):
At $300 per round trip, total hauling coata would be $2100.
36. Flush pumps and tranafer linea: All pumps and piping used to
transfer hazardoua waate are flushed to remove contaminants. This
process ia assumed to coat $2000.
37. Decontaminate equipment: All materials handling equipment
used on-sice must be decontaminated. Thia ia aaaumed to cost $500.
38. Decontaminate containers: In the example, it is assumed that
all drums kept on-site will be crushed and buried in a landfill, at a
total coat of $1000.
39. Total costs of decontaminating facility (sum of Lines 4, 8,
11, 16, 19, 24, 26, 30, 32, 35-38): Total coata of decontaminating the
facility, baaed on the above aaaumptiona, are. estimated to be $14,070.
D. Professional Certification
1. Number of person-hours required for inspections: It is assumed
chat 16 hours are required for periodically inspecting all aspects of
closing the tanka and impoundments.
2. Coat per person-hour: In this case, assume that a registered
independent professional engineer may be hired at a cost of $75 per hour.
3. Total coats of independent professional engineer's time (Line 1
x Line 2): This yielda a total coat of $1200 for the independent pro-
fessional engineer.
9-100
-------
4. Number of c*cftnic*l hour* required fo; iUnauj.aCidCi.vii
Assume chat 8 hours are required from the owner's or operator's staff for
administrative duties connected with employing an independent professional
engineer.
5. Person-hour costs for technical administrative duties: It is
assumed that the total fully-loaded costs for the owner's or operator's
staff are $30 per hour.
6. Total administrative costs for technical labor (Line 4 x Line 5):
Given the above assumptions, the total administrative costs for technical
labor are $240.
7. Number of clerical hours required for administrative duties:
Assume that 5 hours of clerical time are required for the necessary
typing and certifications.
8. Person-hour costs for clerical administrative duties: Fully-
loaded costs of clerical time are assumed to be $8 per hour.
9. Total administrative costs for clerical labor (Line 7 x Line 8):
Given the above assumptions, total clerical costs are $40.
10. Total administrative costs (Line 6 + Line 9): Summing technical
and clerical labor, the administrative costs are $280.
11. Total certification costs (Line 3 + Line 10): The total costs
for certification, including engineer's fees and administrative costs, are
$1480.
E. Total Costs Including Administration and Contingencies
Items 1 through 3 give the costs of all activities on each of the
preceding worksheets. Line 4 is the total of Lines 1 through 3, $85,315.
5. Contingencies: A general provision for contingencies of 15
percent of Line 4 has been included.
6. Administrative and supervisory cost: For administrative casks,
including taxes, insurance, and administration and supervision not included
elsewhere, a total of 15 percent of total costs from Line 4 is used.
7. Total costs of closure (Line 4 + Line 5 + Line 6): The
total costs for closing the tanks and impoundments are estimated for
the sample case to be $111,559.
9-101
-------
MULTIPLE PROCESS FACILITY
WORKSHEET A - CHARACTERIZING THE WASTE (#1)
Description of th« waste
Organic solvent
Chemical composition
(Not given)
Physical state of the waste
Liquid
Heat of combustion of che waste
18,000 BTU/lb.(135,000 BTU/gal.)
Specific gravity of the waste
.9
Maximum Inventory of the waste
60,000 gallons bulk storage
5,500 gallons in drums
ID numbers for areas holding these wastes
Tanks T-l to T-4
9-102
-------
MULTIPLE PROCESS FACILITY
WORKSHEET A - CHARACTERIZING THE WASTE (92)
1. Description of the watte
Slop oil
2. Chemical composition
(Not given)
3. Physical state of the waste
Liquid
4. Heat of combustion of the waste
16,000 BTU/lb.(126,720 BTU/gal.)
5. Specific gravity of the waste
.95
6. Maximum inventory of the waste
10,000 gallons bulk storage
7. ID numbers for areas holding these wastes
Tank T-5
9-103
-------
MULTIPLE PROCESS FACILITY
WORKSHEET A - CHARACTERIZING THE WASTE (13)
1. Description of the waste
Oily was CM
2. Chemical composition
(Mot given)
3. Physical state of the waste
Mixture (95Z liquids, 51 sludge)
4. Heat of combustion of the waste
(Not given)
5. Specific gravity of the waste
(Not given)
Maximum inventory of the waste
30,000 gallons in holding basin
5,500 gallons in drums
7. ID numbers for areas holding these wastes
Impoundment S-l
9-104
-------
MULTIPLE PROCESS FACILITY
WORKSHEET A - CHARACTERIZING THE WASTE (#4)
Description of the waste
Pickling liquor wait*
Chemical composition
(Not given)
Physical state of the waste
Liquid
Heat of combustion of the waste
0
Specific gravity of the waste
1.05
Maximum inventory of the waste
30,000 gallons in holding basin
ID numbers for areas holding these wastes
Impoundment B-l
9-105
-------
MULTIPLE PROCESS FACILITY
WORKSHEET A - GBAEACTZBlZBiG THE WASTE (15)
1. Description of the vasts
Solidified pickling liquor wastes
2. Chemical composition
(Hot given)
3. Physical state of the waste
Solid
4. Beat of combustion of the waste
(Hot given)
5. Specific gravity of the waste
2.2
6. Mariana inventory of the waste
8,000 cu. ft. in storage pile
7. ID numbers for areaa holding these waatea
Rone
9-106
-------
MULTI7L1 PiOCBSS FACILITY
WODCSRBET 1 - TBATXHG THE UIVBfTUU
1. Vast* Inventory at time of closure
Waste solvents
Slop oil
Oily wastes
Pickling liquor wastes
Solidifed pickling wastes
2. Methods of treatment or removal
Waste solvents
Slop oil
Oily wastes
Pickling liquor wastes
Solidified pickling wastes
Disposing of Oily Waste
3. Composition of waste
80Z solvent, 15Z slop oil, SZ sludge
4. Amount of waste produced
28,400 gal. solvent, 5,325 gal. slop oil,
5. Amount of sorbent used in sludge treataent
6. Cost of aorb*nt used
a. Cost of materials
7. Amount of residue generated
8. Unit coat of disposing or removing residua
9. Total cost of disposing or removing residue
(Line 7 z Line 8)
10. Costs of hauling residua
11. Number of trips required
12. Total cost of hauling residue (Line 7 x Line 10)
13. Costs of disposing or removing oily waste
(Line 6 + Line 9 + Line 11)
65,500 gal.
10,000 gal.
35.500 gal.
30,000 gal.
8.000 cu. ft.
Reuse as boiler fuel
Incinerate
Separate; recover solvents,
incinerate slop oils, landfill
sludge*
Solidify, landfill
Landfill
1.775 gal. sludge
1:1 ratio with oils
0
0
22 tons
$50/ton
$1100
$300/trip
1
$300
$1400
9-107
-------
WORKSHEET B (continued)
Treatias or Removing Pickling Liquor Waste
14. Amount of cement required for solidification
15. Total amount of cement required
Cost of cement
Cost of materials (Line 15 x Line 16)
Amount of residues produced by treating inventory
Amount of other residues already on-site
16
17
18
19
20
Total amount of pickling residues
.(Line 18 + Line 19)
21. Unit cost of disposing or removing residue
22. Total cost of disposing or removing residue
(Line 20 x Line 21)
23. Costs of hauling residues
24. Number of trips required
25. Total costs of hauling (Line 23 x Line 24)
26. Costs of disposing or removing pickling liquor
waste (Line 17 + Line 22 + Line 25)
Removing Waste Solvent
27. Amount of waste solvent
a.
b.
28.
Amount of solvent in inventory
Amount of solvent obtained from oily
waste inventory treatment
Method of removal
29. Cost of removal
Treating Slop Oil
30. Amount of slop oil on-site
a. Amount in inventory
b. Amount generated from disposing or
treating oil waste inventory
31. Method of treatment
32. Unit cost of treatment
33. Total cost of treatment (Line 30 x Line 32)
34. Unit costs of hauling residues
1 sack/10 gal.
3000 sacks
$2.50/sack
$7,500
272.4 tons
540 tons
812.4 tons
$50/ton
$40,620
$300/trip
37
$11,100
$59,220
93,900 gal.
65,500 gal.
28,400 gal.
Recovery and reuse
as boiler fuel
15,325 gal.
10,000 gal.
5,325 gal.
Incinerate
$0.60/gal.
$9,195
$150/trip
9-108
-------
WORKSHEET B (continued)
35. NuMbar of crip* raquirad 3
36. Total coat* of haullog (Una 34 x Una 35) $450
37. Coata of craating slop oil $9,645
38. Total coata of treating invmntory ^70.265
(Sua of Llnaa 6, 9, 12, 17, 22, 25, 29,
33 *nd 36)
9-109
-------
MULTIPLE PROCESS FACILITY
WORKSHEET C - DECONTAMINATING THE FACILITY
Tank Cleaning
1. Cleaning method used
2. Capacity to be cleaned
3. Unit cleaning costs
4. Total costs of steam cleaning
(Line 2 x Line 3)
Quantity and type of residues generated
5.
6.
7.
8.
9.
10.
11.
12.
Method of disposal
Cost of disposal
Total cost of disposal
(Line 5 x Line 7)
Cost of hauling residues
Number of trips required
Total costs of hauling (Line 9 x Line 10)
Total costs of tank cleaning
Decontaminating the Impoundment
13. Cleaning method used - Surface Impound-
, ment 1
14. Area to be cleaned
15. Unit costs of sandblasting
16. Total costs of sandblasting
(Line 14 x Line 15)
17. Quantity of residues generated
18. Unit cost* of disposing of residue
19. Total coats of disposing of residue
(Line 17 x Line 18)
20. Cleaning method used - Surface Impound-
ment 2
21. Area to be cleaned
22. Amount of clay removed
23. Unit cost of removing clay
24. Total cost of removing clay
(Line 22 x Line 23)
Steam cleaning
70,000 gallons
$.02/gallon
$1,400
8,750 gallons of contaminated
washwaters
Surface impoundment
$.05/gallon
$438
$6007trip
2
$1200
$3038
Sandblasting
1560 sq. ft.
$.60/aq. ft.
$936
2 tons of contaminated sand
$50/ton
$100
Clay removal and landfill
disposal
1560 &q. ft.
57.8 cu. yds.
$1.60/cu. yd.
S92
9-110
-------
WORKSHEET C (continued)
25. Unit cose of disposing of residue (clay)
26. local coses of disposal
(Line 22 x Line 25)
Soil Removal and Miscellaneous Site Cleanup
27. Soil area contaminated
23. Amount of soil removed
29. Unit cost of removing soil
30. Total cost of removing soil
(Line 28 x Line 29)
31. Unit costs of contaminated soil
disposal
32. Total costs of dispoalng of soil
(Line 28 x Line 31)
33. Hauling costs for decontamination
wastes (including impoundment cleanup)
34. Number of trips required
35. Total costs of hauling
36. Costs of flushing pump and transfer
lines
37. Decontaminate equipment
38. Decontaminate containers
39. Total costs of decontaminating the
facility
$30/cu. yd.
$1734
2.5Z of site area
(242 sq. yd.)
80.7 cu. yd.
$1.60/cu. yd.
$129
$30/cu. yd.
$2421
$300/trip
7
$2100
$2000
$500
$1000
$14,070
9-111
-------
MULTIPLE PROCESS FACILITY
WORKSHEET D - PROFESSIONAL CERTIFICATION
1. Number of person hours required for Inspections 16 hours
2. Cost per person-hour: engineer $75
3. Total costs of independent profession*! engineer's $1200
time (Line 1 x Line 2)
4. Number of technical hours required for 8 hours
administration
5. Cost per person-hour: technical $30
6. Total administrative costs for technical $240
labor (Line 4 x Line 5)
7. Number of clerical hours required for 5 hours
administration
8. Costs per person-hour: clerical $8
9. Total administrative costs for clerical labor $40
(Line 7 x Line 8)
10. Total administrative costs (Line 6 + Line 9) $280
11. Total certification costs (Line 3 •»• Line 10) $1480
9-112
-------
MULTIPLE PROCESS FACILITY
WORKSHEET E - TOTAL COSTS INCLUDING
ADMINISTRATION AND CONTINGENCIES
1. Costs of disposing of inventory $ 70,265
(From Worksheet B)
2. Costs of decontaminating the facility (From $ 14,070
Worksheet C)
3. Costs of professional certification (From $ 1,480
Worksheet D)
4. Subtotal $ 85,815
5. Contingencies $ 12,872
6. Administration $ 12,872
7. Total closure costs $111,559
(Line 4 + Line 5 -I- Line 6)
9-113
-------
9.7 OCAMPLI - FOST-CLOSUM OOtT fS TWITES
4 large flat landfill of 200 acre* he* bean closed la accordance
with the 04 interim status regulations. This landfill consists
of rather closely spaced oarrow trenches that are protactad by clay
covers and cover vegetation. The facility soil is a soil vttich is
mostly clay in content. All of the facility is planted vlth grass to
resist erosion.
The post-closure operations at this facility have been planned to
carry out the requirements of Che interest status regulations. The ac-
tivities planned are as follows:
e periodically inspecting the facility
• coving
• routine erosion repairs
e replacing security fences (*» needed)
• fertilising
• leach*te pumping and disposal
• ground-vatar monitoring
• monitoring well replacement (as needed)
• repair of severe erosion caused by storms
• post-closure administrative services
These activities are costad in the attached annotated worksheets. All of
these activities are coated based on the assumption that the facility is
completely closed sad that no "free" assistance is available from an
active portion of the facility. This mesas that some of the supporting
facilities such as office space that are available during closure are
not automatically available during the post-closure period.
9-114
-------
SAMPLE POST-CLOSURE COST BSTD1ATTNG WORKSHEETS
A. Periodically Impacting the Facility
1. Number of technical management person-hours required for each
inspection: Each inspection at this closed hazardous waste facility
will be conducted by two people in a rented vehicle. We are of the
opinion that two people are needed to conduct the inspection of the
large closed waste disposal area (200 acres) and that an extra measure
of safety is afforded by having two inspectors. Each inspection takes
a full day of work by two technically trained managers.
2. Annual number of routine inspections: Six routine inspections
will be conducted during each year of the post-closure period. These
will be conducted on a bimonthly basis.
3. Person-hour costs for technical management labor: The fully-
loaded labor rate for this technically trained labor is $30 per hour,
4. Technical labor costs for annual routine inspections (Line 1 x
Line 2 x Line 3): The technical labor cost for these annual routine
Inspections is the product of the person-hours required for each inspec-
tion, the number of inspections planned, and the technical labor rate.
5. Annual number of engineer-supported inspections: In addition
to the routine inspections described above, two annual engineer-supported
Inspections are planned. These inspections use a team of professional
engineers and one of our technical managers. The engineer is a state-
certified professional engineer from an independent firm that is contracted
co supply professional services to the hazardous waste disposal facility.
6. Number of independent state-certified engineering hours for each
engineer-supported inspection: For each inspection, eight hours of the
engineer's time is required.
7. Number of technical management hours for each engineer-supported
Inspection: For each inspection, eight hours of technical labor is
required. This requirement is in addition to the engineering labor chat
is required.
8. Person-hour cost for a professional engineer: The quoted cost
of engineering services is $75 per hour. These services will be obtained
from an Independent engineering firm.
9-115
-------
9. Engineering labor costs for ehe engineer-supported inspections
(Line 5 x Line 6 x Line 8): The cose of che engineering labor is Che
product of che number of engineer-supported inspections, che number of
engineering hours needed for each inspection, and the person-hour cost
of engineering services.
10. Technical labor coats for Che engineer-supported inspections
(Line 3 x Line 5 x Line 7): The technical managerial labor costs for
the engineer-supported inspections is che produce of Che labor race for
technical labor, the number of inspections required, and che technical
labor hours required for each inspection.
11. Labor costs for the engineer-supported inspections (Line 9 +
Line 10): The total labor costs for the engineer-supported inspections
is the sum of the engineering labor and technical labor costs.
12. Cost of renting the truck for each inspection: A rented pick-
up truck is used for transporting the inspectors throughout the hazardous
waste disposal facility. The quoted rate for che truck is $25 per day and
$.14 per mile. In addition, the renter must supply gasoline. The mileage
for each inspection is 50 miles including the trips between che facility
and the rental agency. This results in a total cose for the truck of
$36 per day ($25 rental, $7 mileage, and $4 gasoline). The gasoline
value is estimated based on a truck mileage of 15 mpg and a gasoline
price of $1.20 per gallon.
13. Annual cost of renting the truck for inspections (Line 2 -f- Line
5 x Line 12): The total annual truck rental cost is the product of the
total numbe of inspections needed (both routine and engineer-supported)
and the daily truck rental cost.
14. Total annual inspection cost (Lin* 4 + Line 11 + Line 13): The
total cost of conducting this post-closure inspection program is the sum
of che annual total labor coses for Che routine inspections, che annual
labor coses for che engineer-supported inspections, and che annual rental
costs for the truck.
9-116
-------
B. Routine Monitoring and Maintenance Activities
Mowing Operations
1. Facility acreage: The waste diapoaal area of thia hazardous
waste facility is 200 acree. This area includes the cover of the waste
disposal trenches and land cloae to the trenchea.
2. Moving labor: The vaate diapoaal area is to be mowed periodically
to promote the growth of cover vegetation and to inhibit the growth of
large deep-rooted vegetation such as young trees. This moving is to be
carried out on a contract basis by a moving service. The quoted labor
rate for this service is $14.28 per acre moved.
3. Moving equipment: The quoted rate for the moving equipment is
$5.37 per acre moved. Thia rate includea fuel and all equipment coats.
4. Unit moving coat (Line 2 + Line 3): Adding the labor rate and
the equipment rate yielda the total contracted moving rate (unit cost) for
each acre mowed. Cheaper agricultural methoda cannot be used because of
the impact of the heavier equipment on the cover.
5. Annual frequency of moving: Moving of the waate disposal area
is required once a year during the post-closure period. This frequency
of mowing will encourage the growth of cover vegetation and will suppress
the growth of trees and other deep-rooted vegetation.
6. Annual coat of mowing (Line 1 x Line 4 x Line 5): The annual
cost of mowing is the product of the facility acreage, the unit mowing
cost, and the annual frequency of mowing.
Routine Erosion Damage Repair
7. Annual routine eroaion rate: The annual routine loss of soil
from the facility ia computed using the Universal Soil Loss Equation
(USUE) .
A • RKLSCP
A - Average soil loss, tons/acre
R - Rainfall and run-off eroslvity index
K • Soil erodibility factor
L • Slope - length factor
S - Slope - steepness factor
C - Cover/management factor (type of vegetative cover)
9-117
-------
P * Practice factor (terracing, contour plowing)
This equation computed for the sample facility's location yields an
annual soil loss of 0.12 tons per acre. With a soil density of approxi-
mately 100 Ibs. per cu. ft., 0.089 cu. yds. are lost from each acre. In
our subsequent computations, we make the very conservative assumption
that all of the lost soil will have to be replaced and reseeded.
8. Total annual routine erosive loss (Line 1 x Line 7): The total
annual routine soil loss is the product of the acreage times the annual
soil loss per acre.
9. Unit cost for land excavation of soil: Replacement soil will be
obtained on-site at the facility. Since the amount of soil required is
very small compared to the daily capacity of earth-moving machinery,
hand labor will be used to excavate the soil. The rate stated here is
a fully-loaded rate for union labor working for an independent contractor.
This unit cost is based on contractor quotes.
10. Unit cost for on-site transportation of soil: The excavated
soil is transported by truck on-site to the location where the erosion
repair is to be made. This service will be provided by an independent
contractor.
11. Unit cost for compacting the soil by hand: The unit cost of
hand compacting the new soil as a repair for erosion damage is estimated
co be the same as for hand excavation of the soil. This service will
be provided by an independent contractor.
12. Unit cost of seeding: The cost of seeding is a function of
the surface area of the new bare soil. In our estimates, we assume
that a small gully (or gullies) have formed. The ratio of surface area
to soil volume is small. This new soil is seeded with the same type of
grass as is used for the original cover vegetation.
13. Aggregate unit cost of repairing routine soil erosion damage
(Line 9 4- Line 10 + Line 11 + Lin* 12): The aggregate unit cost of
repairing the routine soil erosion is the sum of the excavation unit
cost, the on-site trucking, the hand compacting of the soil, and hand
seeding of the bare soil.
14. Total annual cost for repairing erosive damage of a routine
nature (Line 8 x Line 13): The total annual cost of such routine erosive
9-U8
-------
repairs under average rainfall condition* is the product of the amount -
of soil loec and the unit aggregate coat for erosion damage repairs.
15. Adjustment factor to account for unusually vet seasons: The
above cost (Line 14) is computed for average rainfall conditions at the
facility location. A safety factor of 2 is applied which is the equiva-
lent of increasing the rainfall and runoff erosivity index (within the
Universal Soil Loss Equation) from 150 to 300. This changes the facility's
rainfall from its actual aid-Atlantic level to the high southern levels.
This conservative assumption is required to allow for the annual variation
in routine rainfall-caused erosion.
16. Adjusted annual cost for repairing routine erosion damage (Line
14 x Line 15): The adjusted annual cost for erosion repair of a routine
nature is the product of the average annual cost and the adjustment fac-
tor.
Replacing the Fence
17. Frequency of replacing the fence: Security at the facility is
provided by a 6-ft. high chain link fence that has been established along
the entire perimeter of the facility (11,808 ft. in length). This fence
is made of galvanized #9 wire. Operating experience- at this hazardous
waste facility indicates that the fence must be replaced every 15 years.
Thus, during Che anticipated 30-year duration of the closure period, the
fence will have to be replaced once.
lc. Facility perimeter: The length of the security fence is the
lengca of the facility oerimeter (11,808 ft.).
19. Unit cost of replacing the fence: Quotes were obtained from
fencing suppliers for a new fence of equal specifications. The value
given here is a unit cost per linear foot for an installed fence.
20. Total cost of fence replacement (Line 18 x Line 19): The cost
of replacing the perimeter security fence is the product of the perimeter
footage and the unit cost of the Installed fencing.
21. Pro-rated annual cost of fence replacement: The total cost of
replacing the security fence is pro-rated to each year by dividing the
total cost (Line 20) by the number of years in the post-closure period
(30 years).
9-119
-------
Fertilizing
22. Unit cose of fertilizing: The hazardous waste disposal facility
has relatively poor soil resulting in the experienced necessity of annual
fertilizer applications until the vegetation has become established, & periodic
applications .thereafter. Type 10/6/4 fertilizer costing $0.12 per Ib. (in
50-lb. bags) is applied at a rate of 500 Ibs. pe-r acre. This corresponds
to a nitrogen application rate of 50 Ibs. per acre. The unit cost of ferti-
lization is the sume of the labor, materials and equipment costs.
Labor $69.10/acre
Materials $60.00/acre
. Equipment $ 5.00/acre
Previous experience at this facility has shown that this application
rate for fertilizer is satisfactory to maintain the vegetation.
23. Number of applications of fertilizer for the first 3 years: One
application of fertilizer is needed each year for a total of 3 applications.
24. Number of applications of fertilizer for remaining -years of post-
closure (Years 4 through 30): One application of fertilizer is needed every
5 years, or a total of 5 applications for the remainder of post-closure.
25. Total costs of fertilizing for the first 3 years of post-
closure (Line 1 x Line 22 x Line 23): The cost of fertilizing for the
first 3 years is the product of the acreage fertilized, the unit cost of
fertilization and the frequency of application during the first 3 years.
The costs of fertilizing for the first 3 years are then $80,460.
26. Total costs of fertilization for years 4 through 30 of post-
closure (Line 1 x Line 22 x Line 24): The cost of fertilizing is the
product of the acreage fertilized, the unit cost of fertilizing, and
the frequency of application during Che years 4 through 30. The costs
for fertilizing for the remainder of post-closure is then $134,100.
27. Total costs of fertilizing during post-closure (Line 25 + Line
26): The total fertilization costs are the sum of the costs for ferti-
lizing during the first 3 years and the 5 applications required during
the remainder of post-closure. The total costs f°r fertilizing for
the entire 30-year period are then $214,560.
28. Total annual costs of fertilizing (Line 27 i- 30): The
total costs for fertilizing for the 30-year period is divided by the
9-120
-------
30 years of the post-closure period to yield an annual cose of $7152.
Ground-Water Monitoring Wall Replacement
29. Unit cost for well replacement: The lowest observed depth of
the water table has been closer to the surface than SO ft. throughout the
active operation of the facility. A replacement well to a depth of
aprpoximately SO ft. will cost $425 when installed by an independent
contractor ($8.50 per vertical linear ft.). This quoted price includes
a suitable casing.
30. Number of wells needing replacement: The monitoring wells have
a relatively long useful lifetime as do residential wells. It is antici-
pated that two wells will have to be replaced during the post-closure
period.
31. Total cost of monitoring well replacement (Line 29 x Line 30):
The total post-closure period cost of well replacement is the unit cost
of each well multiplied by the number of wells required in the post-
closure period.
Leachate Pumping and Disposal
32. Frequency of removing the leachate: Leachate is removed perio-
dically from the hazardous waste facility risers by means of a vacuum truck.
Every month, the truck circulates to each riser pumping out the collected
leachate. This service is performed by an independent contractor.
33. Average total monthly leachate withdrawal: Since the facility's
cover system is quite effective in reducing infiltration, only 2000 gals.
of leachate (average value) will have to be removed each month. This
leachate is removed to an off-site disposal area.
34. Unit cost of removing the leachate to an active off-site disposal
area: The unit cost of removing the leachate includes driving the vacuum
truck to each riser at the facility and removing the leachate and deliver-
ing the truckload of leachate to the off-site disposal area. A relatively
high per-gallon removal cost is quoted because of the necessity of collec-
ting a small amount of leachate from each of the widely dispersed risers
throughout the large facility. This cost includes- transportation to the
TSDF.
9-121
-------
35. local annual cost of removing the laachate (Line 32 x Line 33 x
Line 34 x 12): The annual laachate removal cost Is the product of the
monthly leachate volume removed, the number of months in a year, and the
unit cost per gallon removed.
36. Unit cost for removing leachates to an off-site TSDF: The unit
cost for off-site disposal of the leachate material is $.05/gal. This
material is disposed of in a surface impoundment.
37. Annual costs for off-site disposal (Lin* 32 x Line 33 x Line 36
x 12): The cost of disposing of the material in the off-site surface
impoundment is the product of the amount of leachate disposed and the
unit cost for the disposal.
38. Total annual cost for removing and disposing of leachates (Line
35 + Line 37): The total cost for leachate removal and disposal is the
sum of the removal cost and the disposal cost.
Ground-Water Monitoring
39. Number of wells monitored: This hazardous waste facility has
12 ground-water monitoring wells. One well is upgradient and 11 wells
are downgradient from the disposal area.
40. Number of samples taken per well (annual): Two "cycles" of
ground-water sampling will be conducted annually. One ground-water
quality analysis and two ground-water contamination analyses are to be
carried out. One sample may be used for both the ground-water quality
and ground-water contamination analyses. Therefore, two samples are
taken from each well annually.
41. Total number of samples (annual) (Line 39 x Line 40): The total
number of ground-water samples taken annually is the product of the
number of monitoring wells and the number of samples taken annually from
each well.
42. Number of hours for collecting the sample (per sample): Each
sample requires two hours of collection time. The well must be pumped
dry and allowed to refill. Then a sample is taken. The facility ex*
perience is that approximately two hours are required for each well
sampling (including some time for moving about the fields).
9-122
-------
43. local number of hours for collecting the sample (Line 41 x
Line 42): Annually, 24 samples will have to be collected, requiring
48 hours of labor.
44. Total number of hours for preparing and delivering the sample:
The total number of hours required for packaging and delivering the
samples is six hours per year.
45. Total sample handling hours (Line 43 + Line 44): The annual
total time for collecting and delivering the ground-water samples is
54 hours.
46. Person-hour costs for handling ground-water samples: The
person-hour costs for handling the samples is based on the facility ex-
perience of $15 per hour fully-loaded.
47. Total sample handling costs (Line 45 x Line 46): The total
labor cost for handling the samples is the product of the hours required
and the unit labor costs.
48. Unit cost of ground-water quality analysis: The unit cost
of an analysis for the following parameters is $77 per analysis:
Chloride $ 6/sample
Iron $12/sample
Manganese $12/sample
Phenols $25/sample
Sodium $12/sample
Sulfate $10/sample
49. Unit cost of ground-water contamination analysis: The unit
cost of an analysis for the following parameters is $108 per analysis:
pH $ 4/sample
Specific Conductance $ 4/sample
Total Organic Carbon $25/sample
Total Organic Halogen 375/sample
50. Total cost of ground-water quality analysis (annual) (Line 39
x Line 48): The annual cost for analysis of water quality is the product
of the number of wells and the unit cost of the analysis.
51. Total cost for ground-water contamination analysis (annual)
(Line 41 x Line 49): The annual cost for analysis for ground-water
contamination is the product of the number of sample sets to be analyzed
and the unit cost of the analysis.
9-123
-------
52. Total annual ground-water monitoring coats (Line 49 + Line 50 +
Line 51): The total annual cost for ground-water analysis is the sum of
the ground-water quality analysis cost, the ground-water contamination
analysis cose, and the sample handling cost.
Routine Maintenance Summation
53-60. The annual cost for each of Che routine maintenance and
monitoring operations are added together to yield the total cost (annual).
This cost does not include administrative costs which .are computed on a
separate worksheet (Line 53 + Line 54 + Line 55 + Line 56 + Line 57 +
Line 58 + Line 59).
9-124
-------
C. Erosion Daaape Contingency Scenario
1. Percentage of vegetation removed: Some unplanned events that
will create additional demands for care will occur during the duration of
the post-closure period. This worksheet computes the additional cost
that would result from such an unplanned evenC that removes 30% of the
vegetative cover from the hazardous waste facility. After the vegetation
is removed, the soil remains bare for one month exposed to normal rainfall.
Resulting erosive damage is repaired and the bare acreage is revegetared.
The one month lapse between the damaging event and the revegetation allows
for delays in the discovery of the damage and the time required for the
revegetation steps.
2. Facility acreage: The entire facility is impacted by the event.
3. Acreage reduced co bare soil (Line 1 x Line 2): The acreage
stripped of vegetation is the product of the percentage of vegetation
removed and the total acreage of the facility.
4. Annual per acre soil loss rate (without vegetative cover): The
annual soil loss for each acre of bare soil is computed using the Univer-
sal Soil Loss Equation (USLE).
A - RKSLCP
A * Average soil loss, tons/acre
R » Rainfall and run-off erosivity index
K - Soil erodibility factor
L • Slope - length factor
S » Slope - steepness factor
C - Cover/management factor (type of vegetative cover)
P - Practice factor (terracing, contour plowing)
This equation is for erosion resulting from rainfall subsequent to the
event that removed the vegetation.
5. Monthly bare ground soil loss rate: The annual loss rate
computed in Line 4 is converted to a one month loss rate. This conver-
sion is accomplished by dividing the annual loss rate by 12.
6. Amount of soil lost before repairs are instituted: The amount
of soil lost from the bared ground is the product of the monthly loss
race per acre and che acreage of the facility that is exposed. This
product is then multiplied by two to allow for soil lost during the
9-125
-------
removal of Che vegetation. The ground is assumed to be bare for about
one month before the repairs and replanting are completed. The conversion
to volume of soil lost is carried out assuming a soil density of 100 Ibs.
per cu. ft.
7. Unit cost for excavating and loading soil: The unit cost for
excavating and loading replacement soil is computed using a 2 cu. yd.
front end loader. This operation will be performed under contract.
8. On-site haul of excavated soil to the area needing repair: The
excavated soil is transported on-aite over a 2000 ft. distance by trucks
operating under contract.
9. Filling and compacting eroded areas of the facility: The replace-
ment soil is filled and compacted into the eroded areas using a dozer
operating under contract.
10. Total unit cost for replacing soil (Line 7 + Line 8 + Line 9):
The total unit cost of replacing soil is the sum of the excavation-
loading, hauling and filling unit costs. These unit coats were obtained
from estimates made by a local contractor.
11. Cost of replacing the lost soil (Line 6 x Line 10): The total
cost for replacing the lost soil is the product of the amount of soil
lost times the unit cost for soil replacement.
12. Unit cost for seeding the bare soil: The unit cost for seeding
the bare acreage is computed from the sum of the labor, materials and
equipment costs.
Labor $69.10/acre
Materials $13.90/acre
Equipment $ 5.00/acre
The grass planted is Kentucky bluegrass available from a local supplier
at $0.32 per Ib. in 50-lb. bags. The application rate for this seed is
1 Ib. per 1000 sq. ft. (or 43.56 Ibs. per acre). This is less than one-
third of che seed application rate used for home lawns. Experience has
shown this seeding rate to be satisfactory.
13. Unit cost for fertilizing: Since the soil at this hazardous
waste facility is quite poor, fertilization is necessary. Type 10/6/4
fertilizer costing $0.12 per Ib. (in 50-lb. bags) is applied at a rate
of 500 Ibs. per acre. This corresponds to a nitrogen application rate
9-126
-------
of 50~-lbs. per acre. The unit cost of fertilization is the sum of the
labor, materials and equipment costs.
Labor $69.10/acre
Materials $60.00/acre
Equipment $ 5.00/acre
Previous experience at this facility has shown that this application
rate for fertilizer is satisfactory.
14. Unit cost for mulching with straw: Since the soil is bare, pro-
tection from erosion must be provided while the grass starts to grow.
This is achieved by using straw mulch at an application rate of 1 ton
per acre. The unit cost of mulching is the sum of the labor, materials
and equipment costs.
Labor $34.50/acre
Materials $85.00/acre
Equipment $ 5.00/acre
15. Total unit replanting cost (Line 12 + Line 13 + Line 14): The
total unit replanting cost is the sum of the seeding, fertilizing, and
mulching costs. Lime is not applied at this facility because it is not
recommended by the Agricultural Extension Service (DSDA).
16. Total replanting costs (Line 3 x Line 15): The total replanting
cost for the facility is the product of the acreage to be replanted and
the unit cost of replanting each acre.
17. Number of erosive incidents expected in the post-closure period:
It is anticipated that such highly erosive incidents will occur twice
during the post-closure period. These will be either major storms or
floods.
18. Total cost for repairing damage from erosive incidents (Line 11
+ Line 16 x Line 17): The total post-closure cost for repairing the damage
from such incidents is the sum of the repair costs for each incident
(soil and vegetation) multiplied by the number of incidents expected in
the 30-year post-closure period.
19. Total annual cost for repairs required by erosive incidents
(Line 18 r 30 years): The total cost of repairing the damage from the
two incidents is divided by the 30 years of the post-closure period to
yield the annual cost for contingency repairs.
9-127
-------
D. Initial Replanting to Establish Vegetation
1. Percentage failure of vegetation per year: It is estimated
chat in this climate, 10 percent of the vegetation will fall per year due
Co inadequate initial establishment.
2. Number of years required for full vegetation: It ia estimated
chat three years will be necessary for full establishment of vegetation
to the point replanting will no longer be necessary.
3. Facility acreage: Facility acreage is 200 acres.
4. Total acres to be replanted due to initial failure of vegetation
(Line 1 x Line 2 x Line 3): Total acres co be replanted are then 60
acres.
5. Annual per acre soil loss: The annual soil loss for each acre
of bare soil is computed using the Universal Soil Loss Equation (USLE).
A - RKLSCP
A - Average soil loss, tons/acre
R « Rainfall and run-off eroslvity index
K • Soil credibility factor
L • Slope - length factor
S • Slope - steepness factor
C • Cover/management factor (type of vegetative cover)
P « Practice factor (terracing, contour plowing)
This equation is for erosion resulting from rainfall subsequent to the
event that removed the vegetation.
6. Monthly bare ground soil loss rate: The annual loss rate com-
puted in Step 4 is converted to a one-month loss rate. This conversion
is accomplished by dividing the annual loss rate by 12.
7. Amount of soil lost before repairs are instituted (Line 4 x
Line 6): The amount of soil lost from the bared ground is the produce
of the monthly loss race per acre and the acreage of the facility that
is exposed. This product is then multiplied by cvo to allow for soil
lose during the removal of the vegetation. The ground is assumed to be
bare for about one month before the repairs and replanting are completed.
The conversion to volume of soil lost is carried out assuming a soil
density of 100 Ibs. per cu. ft.
9-128
-------
S. Unit coat for excavating and loading toil: Th« unit cost for
excavating and loading raplacaaant aoil ia computed uaing a 2 cu. yd.
front and loadar. Thia operation will ba parforaad undar contract.
9. On-eite haul of azcavatad soil to area naading repair: The
excavated soil ia transported ou-«ite over a 2000 ft. distance by trucks
operating under contract.
10. Filling and compacting eroded areas of the facility: The replace-
ment soil is filled and compacted into the eroded areas using a dozer
operating under contract.
11. Total unit coat for soil replacement (Line 8 + Line 9 + Line 10):
The total unit cost of soil replacement is the sum of the excavation-
loading, hauling and filling unit costs. These unit costs vere obtained
from estimates made by a local contractor.
12. Cost of soil replacement (Line 7 x Line 11): The total cost for
replacing the lost soil is the product of the amount of soil lost times
the unit cost for soil replacement.
13. Unit cost for seeding bare soil: The unit cost for seeding the
bare acreage is computed from the sum of the labor, materials and equip-
ment costs.
Labor $69.10/acre
Mate rials $13.90/acre
Equipment $ 5.00/acre
The grass planted is Kentucky bluegrass available from a local supplier
at SO.32 per Ib. in 50-lb. bags. The application rate for this seed is
1 Ib. per 1000 sq. ft. (or about 40 Ibs. per acre). This is less Chan one-
third of the seed application race used for home lawns. Experience has
shown this seeding rate to be satisfactory.
14. Unit cost for fertilizing: Since the soil at this hazardous
waste facility is quite poor, fertilization is necessary. Type 10/6/4
fertilizer costing $0.12 per Ib. (in 50-lb. bags) is applied at a rate
of 500 Ibs. per acre. This corresponds to a nitrogen application rate
of 50 Ibs. per acre. The unit coat of fertilizing is the sum of the
labor, materials and equipment costs.
Labor $69.10/acre
Materials $60.00/acre
9-129
-------
Equipment $ 5.00/acra
Previous experience at this facility has shown that Chi* application
race for fertilizer is satisfactory.
15. Unit cost for mulching with straw: Since the soil is bare,
protection from erosion must be provided while the grass starts to grow.
this is achieved by using straw mulch at an application rats of 1 ton
per acre. The unit cost of mulching is the SUB of the labor, materials
and equipment costs.
Labor S34.50/acre
Materials $83.00/acre
Equipment $ 5.00/acre
16. Total unit replanting cost (Line 13 + Lin* 14 + Line 15): The
total unit replanting cost is the sum of tbe seeding, fertilizing, and
mulching costs. Lime is not applied at this facility because it is not
recommended by the Agricultural Extension Service (USDA).
17. Total replanting costs (Line 4 x Liae 16): The total replanting
costs for the entire 30-year period are then $20,796.
18. Total costs for initial replanting to establish vegetation (Line
12 + Line 17): The total costs for the initial replanting to establish
vegetation are Chen $20,847.
19. Tocal annual cose (Line 18 r 30): The total cost for the initial
replanting to establish vegetation is divided by the 30 years of the post-
closure period to yield the total annual cost, for s total of $695.
E. Administrative Services
1. Number of technical hours required for administrative duties
(annual): Since the facility is closed, all of the required administration
is an extra cost that must be carefully accounted for. This facility esti-
mates that an average of three weeks of labor by a manager is required to
administer the complete set of specified post-closure activities. This
average administrative requirement includes the administration of the
occasional contingent events described in Worksheet C.
2. Person-hour cost for technical administrative duties: The labor
rate for facility technical labor is $30 per hour fully-loaded.
3. Total administrative costs for technical lai t>r (Line 1 x Line 2):
9-130
-------
Tiu total cose for administrative technical labor ti tba product of the
hours required and tha labor rata.
4. Number of clerical houra required for administrative dutiaa:
Thraa weeks of clerical vork la required to support the technical adminis-
trator.
5. Person-hour costs for clerical administrative duties: The fully-
loaded labor rate for clerical labor at the facility is $8 per hour.
6. Total administrative costs for clerical labor (Line 4 z Line 5):
The total cost for administrative clerical labor is the product of the
hours required and the labor rate.
7. Office or trailer rental: The total annual administrative cost
also includes che rental of office space during the busier times of each
post-closure year. This includes typewriter, telephone and supplies.
8. Total annual administrative costs for post-closure activities
(Line 3 + Line 6 + Line 7)i The total coet of administration is the
sum. of the costs of technical labor, clerical labor, and office rental.
P. Total Costs Tflg3.udiin Vfulfistration sfld Contingencies
Items 1 through 5 summarise the total annual costs of the post-
closure functions taken from the cost worksheets. The erosion contingency
repair cose (Line 3) uaed is the annual cost of the two major erosion
events expected in the post-closure period (30 years).
6. Total of Lines 1 through 5: The total costs of che activities
listed in Lines 1 through 5 are $40,206.
7. Contingencies: Fifteen percent of the sum of the above costs is
taken as an allowance for contingencies. This contingency allowance is
made in addition to the coats expected from the two major post-closure
erosion events.
8. Administration: An additional 10 percent of Line 6 is included
for fees, insurance and related needa.
9. Total annual costs of post-closure (Line 6 + Line 7 + Line 8):
The total sum of the annual post-closure costs is $50,258.
9-131
-------
POST-CLOSUH2
WORKSHEET A - PERIODIC FACILITY INSPECTION
1. Number of technical management person-hours 16 hours
required for each routine inspection of the
doted facility
2. Annual number of routine inspections 6
3. Person-hour coses for technical management labor $30
4. Technical labor costs for annual routine inspections $2880
(Line 1 x Line 2 x Line 3)
5. Annual number of engineer-supported inspections 2
6. Number of independent state-certified engineering 8 hours
hours for each engineer-supported inspection
7. Number of technical management hours for each 8 hours
engineer-supported inspection
8. Person-hour cost for a professional engineer $75
9. Engineering labor costs for the engineer-supported $1200
inspections (Line 5 x Line 6 x Line 8)
10. Technical labor costs for the engineer-supported $480
inspections (Line 3 x Line 5 x Line 7)
11. Labor costs for the engineer-supported Inspections $1680
(Line 9 + Line 10)
12. Truck rental cost for each inspection $36
13. Annual truck rental cost for inspections $288
(Line 2 + Line 5 x Line 12)
14. Total annual inspection cost (Line 4 + Line 11 + $4848
Line 13)
9-132
-------
WORKSHEET B - ROUTINE MONITORING AND MAINTENANCE ACTIVITIES
Mowing Operations
1. Facility acreage
2. Mowing labor (per acre)
3. Mowing equipment (per acre)
4. Unit mowing cost (Line 2 + Line 3)
5. Annual frequency of mowing
6. Annual cost of mowing (Lin* 1 x Line 4 x Line 5)
Routine Erosion Damage Repair
7. Annual routine erosion rate
3. Total annual routine erosive loss (Line 1 x Line 7)
9. Unit cost for hand excavation of soil
10. Unit cost for transporting of soil on-site
11. Unit cost for hand compacting soil (repairing
erosive damage)
12. Unit cost of seeding
13. Aggregate unit cost of repairing routine soil
erosion damage (Line 9 + Line 10 + Line 11 + Line 12)
14. Total annual cost for repairing erosive damage of
a routine nature (Line 8 x Line 13)
15. Adjustment factor to account for unusually wet seasons
16. Annual cost for repairing routine erosive damage
(Line 14 x Line 15)
Fence Replacement
17. Frequency of replacing fence
13. Facility perimeter
19. Unic cost of replacing fence
200 acres
$14.28
$5.37
$19.65
Once a year
$3930
0.12 tons
per acre
(.089 cu.
yds./acre)
17.8 cu. yds.
$21.21/cu. yd,
$2.13/cu. yd.
$21.21/cu. yd.
$l/cu. yd.
$45.55/cu. yd.
$810.79
S1621.58
Once during
post-closure
period
11,808 ft.
$13.06/linear
ft. (installed)
9-133
-------
WORKSHEET B (continued)
20. Total cost of fence replacement (Line 18 x Line 19)
21. Pro-rated annual cost of fence replacement
Fertilizing
22. Unit cost for fertilizing
23. Number of fertilizer applications for first 3 years
24. Number of fertilizer applications during remainder
of post-closure (Years 4-30)
25. Total costs of fertilizing for first 3 years
(Line 1 x Line 22 x Line 23)
26. Total costs of fertilizing for post-closure
years 4-30 (Line 1 x Line 22 x Line 24)
27. Total fertilizing costs (Line 25 + Line 26)
28. Annual cost of facility fertilization (Line 27 T 30)
Ground-water Monitoring Well Replacement
29. Unit cost for replacing well
30. Number of wells needing replacement during the
post-closure period
31. Total cost of monitoring well replacement during
the entire post-closure period (Line 29 x Line 30)
Leachate Pumping and Disposal
32. Frequency of removing the leachates
33. Average monthly total leachate withdrawal
34. Unit cost of removing the leachate to an active
off-site TSDF
35. Total annual cost of removing leachate
(Line 32 x Line 33 x Line 34 x 12)
36. Unit coat for disposing of leachate off-site (at
a surface impoundment)
37. Annual costs for disposing off-site (Line 32 x
Line 33 x Line 36. x 12)
38. Total annual costs for removing and disposing of
leachates (Line 35 + Line 37)
$154,212.48
S 5,140.41
$134.10/acre
3
5
$ 80,460
$134,100
$214,560
$ 7,152
$425/well
2
$850
Once/month
2000 gals.
$0.l8/gal.
$4320
$.05/gal.
$1200
$5520
9-134
-------
WORKSHEET B (continued)
Ground-Water Monitoring
39. Number of veils monitored 12 wells
40. Number of samples taken per well (annual) 2 samples
41. Total number of samples per well (annual) 24 samples
(Line 39 x Line 40)
42. Number of hours for collecting the samples (per 2 hours
sample)
43. Total number of hours for collecting samples 46 hours
(Line 41 z Line 42)
44. Total number of hours for preparing and delivering 6 hours
samples
45. Total sample handling hours (Line 43 + Line 44) 54 hours
46. Person-hour costs for handling ground-water samples $15
47. Total sample handling costs (Line 45 x Line 46) $810
43. Unit cost of ground-water quality analysis $77
49. Unit cost of ground-water contamination analysis $108
50. Total cost for ground-water quality analysis $924
(annual) (Line 39 x Line 48)
51. Total cose for ground-water contamination analysis $2592
(annual) (Line 41 x Line 48)
52. Total annual ground-water monitoring cost (Line 49 $4326
-t- Line 50 + Line 51)
Routine Maintenance Summation
53. Annual moving cost (Line 6) $3930
54. Annual cost for repairing routine erosive $1621.58
damage (Line 16)
55. Annual cost for replacing fence (Line 21) $5140.41
56. Annual cost for fertilizing (Line 28) $7152
57. Annual cost for replacing well (Line 21 T 30) $28
58. Annual cost for removing leachates (Line 38) $5520
59. Annual cost for ground-water monitoring (Line 52) $4326
60. Total annual cost for routine activities $27.717.99
9-135
-------
POST-CLOSURE
WORKSHEET C - EROSION DAMAGE CONTINGENCY SCENARIO
1.
2.
3.
4,
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18,
19.
Percentage of vegetation removed
Facility acreage
Acreage reduced to bare soil (Line 1 z Line 2)
Annual per acre soil loss rate (without
vegatative cover)
Monthly bare ground soil loss rate
Amount of soil lost before repairs are instituted
(Line 3 z Line 5 z 2) (The factor of 2 adjusts for
immediate soil losses)
Unit cost for excavating and loading soil (on-site
operations using a 2-cu. yd. front end loader)
On-site haul of ezcavated soil to area needing
repair
Filling and compacting the eroded areas (using
a dozer)
Total unit cost for soil replacement
(Line 7 + Line 8 + Line 9)
Cose of replacing lost soil (Line 6 z Line 10)
Unit cost for seeding the bare soil
Uait cost for fertilizing
Unit cost for mulching with straw
Total unit replanting cost (Line 12 * Line 13 + Line
Total replanting cost (Line 3 z Line 15)
Number of erosive incidents expected in the post-
closure period
Total cost for repairing damage from erosive
incidents (Line 11 + Line 16 z Line 17
Total annual cost for repairs required by erosive
incidents (Line 18 4- 30)
30Z
200 acres
60 acres
12 tons
per acre
1 ton per
acre
(.741 cu.
yds./acre)
120 tons
(89 cu. yds.)
$0.21 per
cu. yd.
$0.85 per
cu. yd.
$1.25 per
cu. yd.
$2.31 per
cu. yd.
$205.59
$88/acre
$134/acre
$124.50/acre
14) $346.50/acre
$20,790
2
$41,580
S1386
9-136
-------
POST-CLOSU1Z
WORKSHEET 0 - INITIAL REPLANTING TO ESTABLISH VEGBTATIOH
1. Percentage failure of vegetation par
2. Number of years required for full vegetation
3. Facility acreage
4. Total.acres to be replanted due to initial
failure of vegetation (Lin* 1 z Lisa 2 z Lin* 3)
.5. Annual p«r acre soil lose rate (for areas with
inadequate vegetative cov«r)
6. Monthly bare ground aoil loss rat*
7. Amount of toil lost b«fora repairs are
instituted (Line 4 x Line 6)
8. Unit cost for soil ezcavation and loading
(on-site operations using a 2-cu. yd. front end loader)
9. On-sitfe haul of excavated soil to area needing
repair
10. Filling and compacting eroded areas (using a
dozer)
11. Total unit cost for soil replacement
(Line 8 + Line 9 + Line 10)
12. Cost of soil replacement (Line 7 x Line 11)
13. Unit cost for seeding bare soil
14. Unit cost for fertilizing
15. Unit cost for mulching with straw
16. Total unit replanting cost (Line 13 •*• Line 14 + Line 15)
17. Total replanting coses (Line 4 x Line 16)
18. Total costs for initial replanting to establish
vegetation (Line 12 + Line 17)
19. Total annual cost (Line 18 r 30)
10 percent
3
200 acres
60
6 tons/acre
.5 tons
(.3706 cu.
yd./acre)
30 tons
(22 cu. yds.)
$0.21 per
cu. yd.
$0.85 per
cu. yd.
$1.25 per
cu. yd.
$2.31 per
cu. yd.
$50.82
$88/acre
$134.10/acre
$124.50/acre
$346.60/acre
$20,796
•$20,847
$695
9-137
-------
POST-CLOSURE
WORKSHEET E - ADMINISTRATIVE SERVICES
1. Number of technical hour* required for administrative 120 hours
duties (annual)
2. Person-hour cost for technical administrative duties $30
3. Total administrative costs for technical labor $3600
(Line 1 x Line 2)
4. Number of clerical hours required for administrative 120 hours
duties
5. Person-hour costs for clerical administrative duties $8
6. Total administrative costs for clerical labor $960
(Line 4 jc Line 5)
7. Office or trailer rental (includes equipment and $1000
supplies)
3. Total annual administrative costs for the post-closure $5560
activities (Line 3 + Line 6 + Line 7)
9-138
u
-------