-------
cadmium, copper, and zinc. The average of the analyses in
the six areas shows that lead exists in concentrations
from 0.3% to 2.3% by wt. Chromium, nickel, and cadmium
exist at concentration levels of less than 100 ppm by wt.
with cadmium the least. Copper and zinc are at
concentrations of a few hundred ppm by wt. These overall
levels agree with the values obtained from the screening
samples.
o Analyses for BNA showed that all areas contained
phthalates, primarily di-n-butylphthalate and
bis(2-ethylhexyl)phthalate. Total phthalate
concentrations up to 34 ppm by wt. in LAS were measured.
Phenols were also abundant, with total concentrations over
400 ppm measured in the FSA. Naphthalene also was
detected in the soil in all areas except DSA and LAN with
concentrations over 100 ppm by wt. at FSA.
Bis(2-ethylhexyl)phthalate was the primary semivolatile
detected in the screening samples.
o Volatiles were not detected in the soil samples at DSA and
LFA. The primary volatiles detected were toluene, xylene,
trichloroethene, tetrachloroethene, and ethyl benzene.
Some samples also contained 1,1,1-trichloroethane and
trans-1,2-dichloroethene. The maximum volatiles, based
upon multiple sample averaging, were measured at FSA with
up to 14 ppm by wt. trichloroethene, 6 ppm
tetrachloroethene, 26 ppm toluene, and 91 ppm xylenes.
The area with the second largest quantity of volatiles is
LAS with maximum sample values primarily in the range for
each component of 0.3-3.7 ppm by wt. Toluene was injected
into the slurry samples exiting the HAZCON unit for DSA,
LFA, and PFA, to produce an equivalent concentration in
the feed soil of approximately 125 ppm by wt.
Concentrations of the Injected toluene in the 7-day core
samples ranged from 1.3 ppm by wt. in DSA to 12 ppm in
LFA. The toluene in the 28-day core samples ranged from a
minimum at DSA of 1.3 ppm by wt. to a maximum at LFA of 24
ppm by wt.
7.2.2.2 LEACHATE ANALYSES
Results of the leachate analyses, for which data reduction
calculations are provided in Appendix D, are highlighted as
fol1ows:
o The TCLP leachates of the six feedstock soils showed very
low oil and grease. For each area, the treated soil
leachate concentrations were greater than for untreated
soil leachates, even though the untreated soil
concentrations are greater on average by a factor of 2.5.
The values were from below the detection limits (0.2 mg/1)
for DSA to 3.7 mg/1 at FSA. The leachate results for the
7- and 28-day cores appear higher than the untreated soil,
ranging from 0.6 ppm by wt. for DSA to 4.1 ppm for LAN and
84
-------
FSA at 7 days, and 1.6 to 10.4 ppm by wt. for LAS and FSA,
respectively at 28 days.
PCBs were not detected in any leachate, whether the soil
was treated or untreated.
The 7- and 28-day TCLP leachates for metals showed that
the quantity of metals in the treated soil leachates (see
Table 7.10) is well below that for untreated soils. For
the 7- day and 28- day cores leachates, except for lead,
all the metal concentration levels were near or below
detection limits. The lead concentrations were close to
detection limits, at levels of about 2-90 ug/liter except
for FSA, where the concentration ranged from 7-950 ug/1,
averaging 400 ug/1. For the untreated soils, chromium and
copper were below detection limits and cadmium and nickel
were near the detection limits. The lead concentration
ranged from 1.5 mg/1 for DSA to 52.6 mg/1 for LAS. For
zinc, the values ranged from 0.7 mg/1 for DSA to 23.0 mg/1
for FSA. The solidification process reduced the lead
concentration by a factor of ajjout 500 to 1000. TCLP data
on the 28-day cores were equivalent to the 7-day cores.
The leachate concentrations from ANS 16.1 were generally
equivalent to those of TCLP, while those of MCC-1P were
greater by a factor of 5-10. The leachate concentrations
increased with increased leaching time for both tests.
For the BNAs, very significant reductions in
concentrations were obtained between the soil and the TCLP
leachates of the untreated, 7-, and 28-day cores. The
phthalates, as a group, for all leachates were reduced to
approximately their detection limit of 0.010 mg/1. This
may be because the phthalates concentrations were very
significantly reduced from the untreated soils to the
treated soils. For the phenols, measurable quantities in
the leachates were observed. For FSA, where the soil
samples contained about 400 ppm by wt, leachate
concentrations of 3-4 mg/1 were measured. In each area,
concentrations in the untreated soil, 7-day, and 28-day
core leachates were approximately the same, even though
the concentrations in the cores were less than one-half
that in the untreated soil. The same trend existed for
naphthalene, except at lower concentrations. Table 7.11
provides a summary of the leachate concentrations.
The special leach tests, performed only on 28 day cores,
provided results that showed that the leachate
concentrations from MCC-1P were equivalent to TCLP
leachates, but greater than for ANS 16.1. For the ANS
16.1 leachates, concentration did not appear to be a
function of leaching time. However, for MCC-1P the phenol
concentrations in the extracts increased with time, but
the phthalates and naphthalene did not.
85
-------
TABLE 7.10. CONCENTRATION OF METALS IN TCLP LEACHATES
*
Metal Concentration - mg/liter
Soil Location Pb Cr Ni Cd Cu Zn
Soil
DSA
LAN
FSA
LFA
PFA
LAS
1.5
31.8
17.9
27.7
22.4
52.6
<0.008
<0.008
0.27
<0.008
<0.008
<0.008
0.02
0.07
0.11
0.06
0.05
0.07
<0.004
0.02
0.13
0.03
0.01
0.04
<0.03
<0.03
<0.3
<0.08
<0.03
0.13
0.07
1.1
23.0
6.7
1.4
4.8
7-Day Cores
DSA 0.015 <0.07 <0.15 <0.04 <0.06 <0.02
LAN <0.002 <0.07 <0.15 <0.04 <0.06 <0.02
FSA 0.07 0.02 <0.008 <0.003 <0.03 0.02
LFA 0.04 <0.07 0.15 <0.04 <0.06 0.04
PFA 0.01 <0.07 0.15 <0.04 <0.06 <0.02
LAS 0.14 <0.008 <0.008 <0.003 <0.05 0.04
28-Day Cores
DSA
LAN
FSA
LFA
PFA
LAS
0.007
0.005
0.400
0.050
0.011
0.051
<0.007
0.007
<0.070
0.009
<0.007
0.015
0.020
<0.015
<0.15
0.015
<0.015
0.025
<0.004
<0.004
<0.040
<0.004
<0.004
<0.004
0.023
0.010
<0.060
0.080
0.027
0.055
0.037
0.017
0.037
0.013
0.030
0.258
Where the symbol < is used, indicates values below detection limits of
quantity shown. The detection limits vary between metals and from
analysis to analysis.
Where 2 of 3 values were above detection limits, three values were averaged
assuming the one below detection limits is zero. If only one of three values
are above detection limits, the results are reported as below detection
Iimits.
86
-------
TABLE 7.11
BASE NEUTRAL/ACID EXTRACTABLES
IN TCLP LEACHATES
BNA
OSA
Concentration - ug/1
LAN FSA LFA PFA
LAS
Untreated Soil
phthalates ND 10 ND 10 10 NO
phenols ND 1010 2810 ND ND ND
naphthalene ND ND 50 ND ND 10
7-Dav Cores
phthalates ND 30 ND 10 20 ND
phenols 40 1310 3850 30 50 470
naphthalene 15 ND 60 10 20 ND
28-Dav Cores
phthalates ND 10 10 20 30 80
phenols ND 1440 2720 80 80 650
naphthalene ND ND 60 ND ND ND
ND - Not Detected
87
-------
o For the volatile organics, the primary compounds detected
were trichloroethene, tetrachloroethene, xylenes, ethyl
benzene, and toluene. During the Demonstration Test
operations, toluene was injected into the slurry mix zone
of the HAZCON MFU for DSA, LFA and PFA as described
earlier. For the TCLP leach tests on the untreated soils,
toluene was added to the soil at approximately the same
concentrations as measured in the 7-day cores. In the
TCLP leachates for untreated soils for DSA, LFA, and PFA,
toluene concentrations were quite high, 900-5100 ug/1.
For FSA, where the feedstock averaged 26 ppm by wt.
toluene, the soil leachate averaged 230 ug/1 toluene. The
other primary volatile organics, trichloroethene,
tetrachloroethene, ethyl benzene, and xylenes were greatly
reduced in the untreated soil leachates.
The results of the 7-day and 28-day core leachates are
similar in magnitude to the untreated soil, even though
the core concentrations are less than one half of the
untreated soil. See Table 7.12 for a comparison of the
average key volatile organic components in the TCLP
1eachates.
The results of the two special leach tests showed that the
leachate concentrations were approximately equal. They
were lower by about a factor of 2 compared to TCLP
extracts. VOC concentrations did not appear to increase
with increased leaching time intervals.
o Extraction Procedure Toxicity (EP Tox) tests were
performed on 28-day cores for metals only, for LAN and
FSA. For LAN, the leachate metals were predominantly lead
(Pb) and averaged 0.02 mg/1 for cores averaging
approximately 0.3% Pb by wt. For FSA, where the cores
contained 1.0% by wt. lead, the leachate concentrations
averaged 0.21 mg/1. These values appear to be larger for
LAN and less for FSA than the TCLP results.
7.2.2.3 WATER CHEMISTRY
An analysis of the process water, supplied by truck from the
local fire department, was performed. The water was low in
dissolved solids, 340 mg/1, and very low in suspended solids,
1 mg/1, with a pH of 8.05. The primary cations detected were
calcium, magnesium, sodium, and silicon. Two of the primary
anions detected were sulfate and chloride at concentration
levels of 35 mg/1. Details of the water chemistry analyses
are provided in Appendix B, Tables A-50 and A-51.
7.2.3 MICROSTRUCTURAL STUDIES
Analyses of the untreated soil and 28-day core samples were
performed on a microstructural scale. All analyses were
performed more than three months after soil processing. All
88
-------
TABLE 7.12. VOLATILES IN TCLP LEACHATES^
Volatile Organic
Concentrations - ug/l
DSA LAN PSA LFA
PFA
LAS
Untreated Soil
Toluene
Xylenes
Trichloroethene
Tetrachloroethene
Ethyl benzene
7 Day Cores
Toluene
Xylenes
Trichloroethene
Tetrachloroethene
Ethyl benzene
28 Day Cores
Toluene
Xylenes
Trichloroethene
Tetrachloroethene
Ethyl benzene
915
< 50
< 20
< 40
< 70
380
3.5
< 10
< 20
< 40
370
6
< 9
< 6
< 3
10
7
2.4
< 4
< 7
< 6
6
< 2
< 4
< 7
40
8
2
3
2
245
525
165
19
80
220
340
105
11
60
230
330
100
20
60
5100
< 230
< 95
< 210
< 360
210
5
< 2
< 4
< 7
370
< 6
< 9
< 6
2
1100(b)
< 180
< 76
< 160
< 290 <
350 <
20
< 5 <
< 10 <
< 20 <
670
170
< 9
< 6
< 3
10
35
8
5
7
15
15
5
10
20
50
40
8
10
4
(a) < indicates less than detection limits. Within one sampling area, the
detection limit may change between samples. For these, the highest
detection limit is shown.
(b) Two values <60 and 2200 ug/l.
89
-------
samples were studied by scanning electron microscopy (SEM),
x-ray diffraction (XRD), and optical microscopy (OM) . Energy
dispersive x-ray spectrometry (EDXRA) was also performed on
selected samples. The type of information to be obtained from
each test is:
o X-ray diffractometry - crystalline structure of the soil
and hydration products
o Energy dispersive x-ray spectrometry - elemental analysis,
i.e., calcium, aluminum
o Microscopy - characterizes crystal appearance, porosity,
fractures, and the presence of unaltered soil/waste
material
The detailed report with photographs and x-ray diffraction
patterns is included in Appendix C.
The results can be summarized as follows:
o The untreated soils consist of quartz and clay minerals,
illite, and in some cases kaolinite. The filter storage
area feed was low in quartz, as would be expected.
o The solidified samples show crystals of portlandite,
ettringite, calcium silicates, calcium aluminate, and
sometimes gypsum.
o Abundant pores of various sizes and shapes could be seen
in all core samples. Some of the pores include trapped
air bubbles. Large cracks also are seen in some of the
pores.
o Unhydrated tricalcium silicate was seen in all core
samples. In some cases dicalcium silicate was observed,
particularly for FSA.
o Several peaks in each x-ray diffraction pattern could not
be identified, as known minerals, but were seen both in
the soil and core samples. These peaks are likely to be
the organics.
o Mixing does not appear to be completely efficient.
o The cores contain unaltered brownish aggregates that were
also observed in the untreated soil.
The interpretation of the above observations is presented in
section 8.1.3.
90
-------
7.3 DATA QUALITY ASSURANCE
In Section 7 of the approved Quality Assurance Project Plan
(QAPP), it was indicated that various Quality Control (QC)
samples would be taken to control and/or assess data quality.
These are:
o QC check samples - standard samples of known analyte
concentration.
o Laboratory Blanks - deionized water taken through sample
preparation steps.
o Field blanks - clean soil samples brought to the field and
then analyzed in the laboratory to check for field
contami nati ons.
o Spiked samples - samples were spiked with either known
contaminants or surrogate standards to confirm analytical
recoveries and thus accuracy of the analyses. Duplicates
on the spiked samples were also performed.
o Duplicate samples - duplicate samples from the field were
collected and analyzed to confirm soil sample data.
To verify that correct sampling procedures were used, EPA sent
a Quality Assurance (QA) team to the field to observe Radian
Corporation's sampling procedures. In addition, QA teams went
to Radian's laboratories both in Austin, TX and Sacramento, CA
to observe and correct, if necessary, procedures being used in
the laboratory. The audits found Radian's work satisfactory.
The detailed QA/QC results reported on Radian procedures is
provided in Appendix B. Overall the QA/QC data indicated that
the measurement data are acceptable and defensible.
The purpose of the QA/QC program was to fulfill two related
purposes :
o An organized frame work for sampling and analytical
efforts.
o To control data quality within preestablished limits to
ensure that it was adequate to achieve the objectives of
the program.
The following is a brief summary of the QA analyses:
o Soil samples
Blanks--For metals, the blanks showed levels the same
as in uncontaminated soil. PCBs were not detected in
the reagent blank. Methylene chloride, toluene,
acetone, and three other VOCs were detected in the
91
-------
reagent blanks. Methylene chloride is probably a
laboratory contaminant. Only toluene of these six was
considered in the VOC analyses, and some errors in
these values may exist. Toluene was only one of five
VOCs looked at for reporting VOC data.
Spiked sample results — All the metals recoveries and
almost all the VOC and PCB recoveries were within the
acceptance range.
Duplicate sample results--Matrix spike duplicates for
metals showed excellent repeatability, with a
coefficient of variation (CV) less than 5%.
Repeatability for VOCs was also acceptable, with a CV
of 50%. The repeatability for PCBs, which had a CV
within 10%, was acceptable; 50% is the maximum
acceptable CV. The repeatabi1itity for O&G was good,
with almost all CV less than 5%, but wide variations in
sample homogeneity was observed.
Soil sample leachates
Blanks — Only acetone was detected in two samples near
the detection limits of 5 ug/1 and was probably due to
laboratory contamination. Metals and PCBs were not
detected in the blanks.
Spiked samples — Matrix spike recoveries of lead were
high; therefore, results for Pb may be biased slightly
high. The recovery of the other metals was within the
acceptable target range of 80-120% of the theoretical
value. Volatile organic matrix and surrogate spikes
were all within the acceptance criteria. For PCBs the
surrogate spike recovery of the samples was below
acceptance limits; therefore the detection limits of
these compounds (measured by Method 680) could be
slightly greater than the laboratory reported. PCBs
were not found in any leachates.
- Duplicate sampl es —Resul ts for VOC and O&G all met
acceptance criteria. Duplicates for untreated metals
samples were not performed, but duplicates for metals
in treated samples showed very low CVs.
Slurry samples (7-day cores)
Blanks —No analytes were detected in the reagent
blanks.
Spiked samples —Matrix and surrogate spike recoveries
were within the acceptance limits. Recovery of toluene
was above the acceptance limits, but impact on the
overall results should not be significant.
92
-------
Duplicate samples--Duplicate samples analyzed for VOC
by Method 8240 were within accuracy acceptance limits.
o Slurry sample leachates
Blanks — No metals or PCBs were detected. Acetone was
detected in some of the blanks, but since this is not a
field contaminant and the levels were so low, the
effect on the results is negligible.
Spike samples--Metals recoveries for the nine samples
were all acceptable. Matrix spike and surrogate spike
recoveries for five VOCs were good although a few
examples of deviation from the acceptance range were
noted. For PCBs the recoveries were low, indicating
detection limits may be higher than reported. However,
no PCBs were detected in the leachates.
Duplicates--Al1 metals and volatile organics met the
acceptance criteria on coefficient of variation.
o Core samples and core sample leachates
Blanks--Chromiurn, lead, copper, and zinc were detected
in reagent blanks. However, review of the field data
shows that the low levels of the analytes make these
values insignificant. Eight VOCs were detected in 1 or
2 of 10 laboratory reagent blanks; therefore low levels
of those compounds must be reviewed with some suspicion
since toluene, xylene, and ethyl benzene, three of the
five measurable components of VOCs, are included. PCBs
were not detected in the blank. Some phthalates were
detected, but may be laboratory contaminants.
Spiked samples — Ten spiked samples for metals were all
within acceptance limits of 80-120%. Eight spiked
samples for VOC were performed and virtually all
results were within acceptance limits. All BNA spikes
met acceptance limits.
Duplicate samples--Results for metals and VOC were very
good, within a CV of 10%.
BNA analyses — The high results for phthalates levels in
blanks and low naphthalene in the matrix spikes may
provide cause for suspicion. However, phthalates are a
common laboratory contaminant and low levels in field
samples may be an error. An interlaboratory
performance audit by Radian also left suspicions on the
phthalates results. The spiked sample results for
phenols met acceptance criteria.
From the above results for blanks, spikes, and duplicates, the
chemical analyses should be acceptable. The primary purpose
of the analyses is to observe changes and orders of magnitude
93
-------
of the values before and after the HAZCON treatment. The
deviations noted above should have an insignificant impact.
The physical tests, moisture, bulk density, and unconfined
compressive strength were performed in triplicate for each
sample collected. The other physical tests, permeability,
particles size, and pH, were performed only once on each
sample. Permeability is the most important parameter of the
tests performed once. The results showed all the treated soil
permeabilities were in the 10"° to 10"9 cm/sec range,
which is very low. Exact numerical values and differences
between samples is less important than the observed
consistency of the order of magnitude results.
The QAPP did not include any protocols for the microstructural
analyses, which were performed by Scientific Waste
Strategies. Since these results are only intended to be
qualitative and no attempt was made to quantify, the trends
reported should be valid.
94
-------
SECTION 8
DISCUSSION OF RESULTS
The analytical results summarized in Section 7.0, are
discussed and evaluated in Section 8.1. Operating procedures,
a chronology of which is presented in Section 5.2 for the
HAZCON Demonstration Test, are evaluated in Section 8.2
8.1 ANALYTICAL RESULTS
The analytical data consist of physical test results of
untreated soil, treated soil after a nominal 7-day curing
period, and essentially fully cured samples, which were
analyzed more than 28 days after treatment. The discussion of
the analytical results can be further subdivided into the
fol1owi ng:
o Physical tests
o Chemical analysis - primarily soil composition and
leachate results
o Microstructural analyses
o Overall evaluation
8.1.1 PHYSICAL TESTS
The physical tests on the soil and cores consisted of the
fol1 owing:
o Free moisture - untreated, 7-day, 28-day
o Undisturbed bulk density - untreated, 7-day, 28-day
o Particle size distribution - untreated
o Permeability - untreated, 7-day, 28-day
o Unconfined compressive strength - 7-day, 28-day
o Total organic carbon - untreated
o Oil and grease - untreated, 28-day
o pH - untreated soil
o Wet/dry weathering - 28-day
o Freeze/thaw weathering - 28-day
o Unconfined compressive strength after weathering - 28-day
8.1.1.1 BULK DENSITY
The treated soil density was about 10-20% greater on average
than the undisturbed untreated soils. The bulk density test
for all samples was performed in triplicate. In general,
except for the untreated soil in DSA, the individual area
results were in tight bands, with a bulk density greater than
1.4 mg/1 particularly for the treated soils. For FSA, the
95
-------
treated soil results were 5% lower than the untreated soil
results. Results of the microstructural analysis presented in
Section 7.2.3 indicate a very porous structure for all the 7-
and 28-day cores, which may account in part for the relatively
small bulk density increases.
The bulk density did not change between 7 and 28 days; the
change occurred entirely in the initial 7-day period. Density
decreased with higher oil and grease content, both for the
untreated and treated soils. Since the soil represents only
about 40% of the total weight of the mix of soil, cement,
water, and Chloranan, and the bulk density increase is 10-20%,
the volume of the treated soil more than doubles.
Calculations for volume increase for each plant area is
provided in Appendix D.
The laboratory-prepared solidified formulations on soils from
LAN and FSA, without the use of Chloranan, showed a lower bulk
density than the field samples, particularly for FSA. For FSA
the bulk density was reduced from 1.51 to 1.36 mg/1. Two
possible contributory causes may be the lack of Chloranan or
the higher moisture content.
8.1.1.2 FREE MOISTURE
The water addition during processing was not tightly
controlled or adjusted for moisture in the feed. The water
was adjusted by HAZCON based upon visual observation of the
slump of the concrete mix. Based upon the material balances
shown in Table 5.2, the total water added per run is the
correct order of magnitude, 40% by wt. of cement. Comparing
the untreated soil with 7-day treated soil showed an increase
in free moisture content. Comparing the 7-day material to
28-day showed that, except for DSA, the moisture content
decreased by about 10-15%. This is probably due to the
continuation of the cement hydration reactions, which would
reduce free moisture (drying at 60°C). It appears that the
hydration reactions are 60-80% complete at 7 days, with DSA
and LAS close to 100% complete.
8.1.1.3 PERMEABILITY
The permeabilities of the treated soils were very low,
primarily in the range of 10"8 to 10"9 cm/sec. This
compares to undisturbed soil permeabilities of about 10"1 to
10"z cm/sec, except LAS, which was near 10"5 cm/sec.
Calculations for the permeability reduction factors are
provided in Appendix D. The permeability for the laboratory
formulations without the use of Chloranan were a factor of 10
greater than field cores for LAN and equivalent to the field
cores for FSA. The untreated filter sludge was impermeable,
and the scheduled tests could not be performed. In general,
for stabilization/ solidification processes, 10"' cm/sec is
96
-------
considered impermeable. The design of soil barrier liners for
waste disposal sites target permeabilities of 10"' cm/sec or
less. The permeability for the two laboratory formulations on
LAN and FSA, without the use of Chloranan, provided results
that were a factor of 10 greater for LAN and equivalent for
FSA to the field cores. There were not any differences
between the nominal 7- and 28-day core sample permeabilities.
This is due to the fact that the 7-day as well as the 28-day
permeability tests were run after curing for 30+ days. The
permeability measurements were very time-consuming, and
difficulties were encountered in performing the analyses.
Therefore, they could not be performed in the time frame
originally planned. Tables A-14 and A-23 in Appendix B
provide all the permeability results and the dates on which
the tests were performed.
8.1.1.4 UNCONFINED COMPRESSIVE STRENGTH
The unconfined compressive strength test, which for each
sample was performed in triplicate, produced individual values
that ranged from about 100 psi for FSA to above 2200 psi for
DSA. Based upon the averages of the three tests, the range
was from 220 psi at FSA to 1570 psi at PFA, both at 28 days.
In general, compressive strength was markedly lower with
increased oil and grease (O&G). The average of triplicate
tests at 28 days for the two highest oil and grease areas was
about 220 psi for FSA (25.3% O&G) and 520 psi for LAN (16.5%
O&G).
Decreasing pH with increased O&G is believed to be a result of
the oil and grease concentrations and not a factor in the
unconfined compressive strengths. The soil particle size
distribution may influence core strengths, but insufficient
data exists to confirm. In addition, with the exception of
PFA, which was a litter coarser, the particle size
distributions were equivalent.
Although it was expected that the 28-day sample tests would
give higher strengths, this was not evident from the results.
The free water levels discussed above indicate that the cement
hydration reactions were still proceeding, which should have
resulted in increased strengths. It appears that LAN and PFA
did increase in strength, but that the others either decreased
or remained unchanged. An explanation for this unexpected
lack of strength increase is not available.
For the laboratory formulation tests on FSA and LAN, definite
increases in strength between 7- and 28-day cores of 30-50%
were observed. These formulations for LAN obtained 7- and
28-day core strengths comparable to the field blocks.
However, for FSA, the field blocks were many times stronger.
This seems to confirm that the Chloranan helped the
solidification process. At lower oil and grease levels, the
effect of Chloranan may be less significant.
97
-------
8.1.1.5 OIL AND GREASE
Oil and grease levels ranged from about one percent by weight
for DSA to 25% for FSA. Typically the total organic carbon
(TOC) level is about 4-5% greater than the level of O&G, which
is as expected. The values for O&G reported for the screening
samples are consistently greater than for the feedstocks used
in the Program. This probably can be explained by the method
of obtaining each feedstock for the Demonstration Test, where
a backhoe was used; some less-contaminated soil was excavated
along with the more-contaminated soils. For the screening
samples, the most contaminated area in each plant location was
targeted and only a 40 Ib sample was collected.
8.1.1.6 pH
In general, the feedstocks were acidic, except for PFA.
Values as low as a pH = 2.4 were obtained for FSA samples.
There is some trend toward lower pH values with increased oil
and grease levels. However, the original source of the
contamination would also have an impact, not just the
quantity.
8.1.1.7 PARTICLE SIZE
Particle size distributions on the untreated soils were also
measured, except for FSA, which was too sticky for the
screening analyses. Basically the soils are fine, with about
half the soil by weight finer than 200 mesh (74 micron). PFA
was somewhat coarser than the other soils.
8.1.1.8 WEATHERING
The two weathering tests, wet/dry and freeze/thaw, are twelve-
cycle tests, measuring weight loss relative to a control
specimen. The control specimen is maintained at 72°F in a
moisture chamber, when the test specimens are dried or frozen
for 24 hrs. Both samples then are inserted into water and
placed in the moisture chamber for 24 hrs. The results of
samples from each site location for the wet/dry tests indicate
that the weight loss of the test specimens is only slightly
greater than for the control. However, the loss differentials
during the freeze/thaw tests appear to be larger. All weight
losses were about one percent for both the specimens and
control s.
Unconfined compressive strengths on both the test and control
specimens were run. The results for the test samples show
that compressive strength was not lost in either the test
specimens or controls.
8.1.1.9 OTHER OBSERVATIONS
Significant variations in physical properties of the soil
98
-------
between each composite within a soil area were noted. For
example, oil and grease at LAS ranged from 6.1% to 8.6% and
for LAN from 14% to 18%. Moisture levels were also somewhat
variable at FSA, LAS, and LFA. This means that individual
grab samples within a given feedstock are even more variable.
Thus, physical test results on untreated soil based on average
feed properties may not be directly related to the 7-day and
28-day core sample results, which are based more on localized
properties of the solidified soil samples. Although it is
believed that the overall results are representative for each
plant area, individual distortions in the data do exist.
In addition, significant variations even within a sample,
split spoon or core, probably exist. Many of the leaching
tests (see Appendix D) showed a larger weight of an analyte or
organics group existed in the leachate than in the solid.
Also, consistent material balances for the lead and organic
analytes between treated and untreated soil could not be
obtained from the data. Only for total oil and grease was
there a consistency in the concentrations before and after
treatment. However, due to the large amount of data
available, definitive trends in the results exist. Therefore,
the results obtained are still valid.
The laboratory formulations were prepared without Chloranan,
similar to the method concrete is typically blended. For FSA,
the UCS test values were about one-tenth of those for samples
collected in the field. In addition, the bulk density was
lower by almost 10%. Results for the other laboratory
prepared samples were equivalent to the field prepared and
cured samples. Thus, Chloranan improved the physical
properties of a treated soil where the oil and grease levels
were high, about 25% by wt in the untreated soil.
A grab sample of the process water showed low suspended and
dissolved solids, with a pH of 8.05. This water should not
impact the process or any of the laboratory analyses.
8.1.2 CHEMICAL ANALYSES
The chemical analyses consist of the following:
o Untreated and treated soil compositions
o TCLP leachate analyses
o Special leach test analyses
A discussion of the results highlighted in Section 7.2.2
fol1ows.
8.1.2.1 SOIL COMPOSITION
The composition of the untreated soil was basically as
expected. The oil and grease values were a little low
99
-------
compared to the values anticipated based upon the screening
samples and the RI/FS prepared by NUS Corporation for EPA
Region III. This probably is due to the inclusion of
less-contaminated soil around and below the targeted soil and
to the general variability within each area. Samples having
the maximum oil and grease in each of the six plant areas were
targeted for the screening samples.
The PCB concentration levels, with averaged values up to 52
ppm at LAS, were higher than originally anticipated based upon
the RI/FS and screening samples, which were at less than 25
ppm. The two Aroclors detected were the same as measured in
the screening samples, but both were at higher concentrations.
The results for the priority pollutant metals were as
expected. Lead was the major contaminant with concentrations
up to 2.3% by wt. measured. After reviewing the soil
analyses, only the major metal contaminants were carried
forward to analyze in the 28-day cores and leachates. These
were chromium, nickel, zinc, copper, and cadmium. In general
the levels of contamination in the soil agreed with those
obtained during the screening tests.
The results for the base neutral/acid extractable (BNAs)
showed primarily phthalates, phenols, and naphthalene.
Phenols differ from other BNAs in that they have greater
solubility in water and therefore, may be more readily
Teachable. Other BNAs reported in the RI/FS but not detected
in the screening analyses, such as fluorene, pyrene, and
f1uoranthene, were only occasionally detected in these
analyses. The phenols were not checked for on the screening
samples. Phthalate concentrations in the 28-day core samples
(ND to 2.15 mg/kg) were very low compared to the untreated
soil (12.15 to 34.2 mg/kg). This may be caused by
base-catalyzed hydrolysis reactions, which is a reasonable
possibility, or possibly other reactions caused by the
Chioranan.
The volatiles in the FSA samples were considerably greater
than anticipated, averaging 150 ppm by wt. It had not been
expected to observe volatile levels above 30 ppm for any of
the plant areas. The screening test results showed LAS to
have the highest concentration of volatiles, with much less
reported for any of the other plant areas. For LFA, PFA, and
DSA, toluene was injected into the slurry mix to produce a
final concentration of 125 ppm by wt., based upon the feed
soil. The maximum value reported in the core samples was 24
ppm in 28-day cores at LFA, with values down to 1 ppm. Since
the soil is only 40% of the total core weight, this maximum
value is equivalent to 60 ppm on a soil weight basis.
Therefore, the majority of the toluene was lost. This
indicates that the toluene either vaporized off in the HAZCON
mixing screw, possibly due to poor injection or improper
100
-------
mixing, or during sample preparation in the pulverization
step, or both. However, sufficient toluene remained to
provide valuable information for leaching test analyses.
Attempts to relate VOC and BNA component concentrations before
and after solidification were not successful. There was such
variability in the grab samples that in some cases it appeared
that concentrations were greater in the cores than in the
untreated soil. However, for oil and grease, approximate
material balances could be obtained; see Tables 7.1-7.6.
8.1.2.2 TCLP LEACHATE ANALYSES
Oil and grease in the leachates from the untreated soils were
near the detection limit of 0.2 ppm by wt. in the range of
<0.2 ppm at DSA to 3.7 ppm at FSA. These results are lower
for each plant area than for the 7- and 28-day core leachates,
where the results were in the range of 1-10 ppm by wt. (mostly
2-4 ppm by wt.) . Since these values are all so close to the
detection limits for the laboratory procedure, it may not be
proper to differentiate between them. However, it is also
possible that the treatment process tended to agglomerate the
oil and grease and after crushing the solid core for
performing the leach test, some O&G globules were released
into the leachate. The leachate concentrations for the
special leach tests were less than for TCLP. Also, the oil
and grease concentrations in the treated cores are about 40%
of these of the untreated soils.
The immobilizing of the priority pollutant metals was
accomplished by the solidification. Except for lead and zinc,
virtually all the metals were reduced to their detection
limits in water. For lead the values were just above
detection limits, ranging up to 400 ug/1, which is well below
regulatory levels of about 5 ppm by wt. However, lead was the
predominant metal contaminant with measured soil
concentrations ranging from 0.3 to 2.3% by wt., so the lead
reduction was dramatic.
Except for phenols, the BNAs (semivolati1e organics) were
reduced to near their detection limits of 10 ug/1 in the
leachates of both untreated and treated soil samples. This is
a reduction of more than one thousandfold, compared to the
contaminated soil. However, the phenols were not reduced to
the same extent. For LAN and FSA, with concentrations in the
soil or cores ranging from 5-400 ppm by wt., the reduction
factor is of the order of 10-100. For FSA, TCLP leachate
concentrations of 3-4 mg/1 were observed for both treated and
untreated soils. Therefore, the HAZCON process did not appear
to reduce the Teachability of phenols. Results of the MCC-1P
and ANS 16.1 leach tests provided equivalent results. In
addition, the quantity of phenols in the leachate increased
with time.
101
-------
The volatiles in the leachates ranged from 100 to 1000
micrograms per liter (for the higher soil and core
concentrations). These are reduction factors of about 100 on
average compared to the soil. However, the concentrations in
the untreated soil, 7-, and 28-day core leachates are
approximately the same. Therefore, at least in the
concentration range investigated, up to 150 ppm by wt. (FSA),
the solidification did not appear to impact the leachate
results. The results of the special leach tests showed
leachate concentrations less than for TCLP leachates, and the
concentrations did not appear to be time-dependent.
Calculations for total VOCs, toluene, total BNAs, phenols, and
lead showed in many instances, except for lead, greater
quantities of the analyte(s) in the leachate than in the
soil. This indicates that great variability in the
concentration of these analytes may exist within a given
sample. Concentrations in the test specimens used for the
three leach tests were possibly much greater than in the
material used for determining concentration levels in the
total samples. This could also account for, in some cases,
the greater migration potential (leaching potential) of the
organic analytes in the treated soil compared to that in the
untreated soil, even though average concentrations of the
analytes in the cores are less than one-half those in the
untreated soil. However, since many leaching analyses have
been performed, the general observations for organics, that
the leachate concentrations for the treated soils are about
the same as the untreated soil, is valid.
The special leach tests, MCC-1P and ANS 16.1, were performed
on one sample set taken from 28-day cores for LAN, FSA, PFA,
and LAS. In general, for a given time frame, the results from
MCC-1P were greater than from ANS 16.1, which may be due to
MCC-1P being performed at 40°C vs. ambient conditions for
ANS 16.1.
The MCC-1P leachate concentrations for VOC and BNAs were
equivalent to TCLP extracts. For lead the values were greater
and increased with leach time. For oil and grease, the TCLP,
MCC-1P, and ANS 16.1 leachate concentrations appear equal.
A brief comparison test between EP Tox and TCLP for metals was
performed on samples from LAN and FSA. The results for EP Tox
were greater for LAN and about the same for FSA. This is
expected for basic solutions (these leachates are basic due to
the cement components).
8.1.2.3 SPECIAL LEACH TEST ANALYSES
Leach tests ANS 16.1 and MCC-1P were two procedures originally
developed for the nuclear industry for the leaching of low
level radioactive wastes, but have been applied with
modifications to hazardous wastes. These tests utilized solid
102
-------
cores simulating the solidified wastes, as compared to TCLP
and EP Tox where the solid cores are first ground to a
powder. MCC-1P simulates a relatively static groundwater
flow, with the samples in contact with one leachate for time
periods of 3, 7, 14, and 28 days at a temperature of 40°C.
ANS 16.1 simulates a moving groundwater regime with the solid
core specimen placed in a new fresh leachate, so that the
boundary concentrations of the analytes are kept below
saturation level. Samples are collected after 1, 3, 7, 14
days with the total leach time being 28 days. A diffusion
coefficient might then be calculated.
It should be noted that experience with these tests on
hazardous wastes is limited. Comparisons to the treated soil
TCLP results have been made, but the significance of the
differences is unclear. Some differences would be expected
due to the diverse ratios of solid to extract used in each
test. The nature of these two procedures, that of simulating
leaching from a solidified mass, makes it illogical to perform
these tests on untreated soils. Therefore, the results of
these tests are compared to the treated soil TCLP tests only.
It was anticipated that TCLP would be the most severe leaching
test, providing the highest contaminant concentrations in the
extracts. However, the extract concentrations for the metals
for MCC-1P were greater than for TCLP, 0.3-0.7 mg/1 versus
0.01-0.06 mg/1, and approximately equivalent for VOCs, BNAs,
and oil and grease. This indicates that at least for the
28-day cores from the HAZCON process the increased surface
area for leaching for the TCLP test is balanced by the
increased time and temperature of MCC-1P. The differences
between MCC-1P and ANS 16.1 extracts may be due to the higher
leaching temperature, 40°C versus 22°C.
Since the leaching times range from 1 to 28 days in these
tests, the effect of time was reviewed. For the organics,
time did not appear to be related to leachate concentrations
except for phenols in the MCC-1P test. Since phenols are
soluble in water, this is not unexpected. The concentration
of lead appears to increase with time for both leach tests,
although the trend for MCC-1P is less definitive.
8.1.3 MICROSTRUCTURAL STUDIES
Microstructural and microchemical analyses are proven methods
for understanding the mechanisms of structural degradation in
materials similar to those in this Demonstration Test. The
literature is replete with examples of SEN and XRD analyses of
soils, cement, soil-cement mixtures, and each of these mixed
with various inorganic and organic compounds. However, there
have been relatively few studies of the microstructure of
complex waste/soil mixtures like those resulting from
stabilization/solidification procedures. Consequently, in
103
-------
some cases interpretation of microstructural observations may
be difficult. The microstructual report is intended to be
complete in its reporting, yet conservative in its
conclusions. Many observations will become more useful as the
understanding of stabilization/solidification technologies
improve.
A discussion of the results presented in Section 7.2.3
fol1ows:
o The two predominant clays seen in the samples, illite and
kaolinite, are nonexpandable clays. Therefore, the
organic compounds in the soil will not be adsorbed within
the layers of the clay minerals. Any organics adsorbed
will be on the outside surface and therefore will be more
loosely held.
o The crystalline phases seen in the core samples,
portlandite, ettringite, calcium silicates, calcium
aluminate, and gypsum, are the principal components of
Portland cement. Portlandite and ettringite are the major
hydration phases of portland cement. Thus, the major
bonding agent is portland cement, and SEM observations
agree with this conclusion.
o An abundance of pores of all sizes and shapes were
observed in the core samples. Some of the pores were due
to trapped air bubbles. The high concentration of the
pores may be due to incomplete mixing. Crystals of
portlandite, calcium aluminate hydrate, and ettringite
grew into these pores. These crystals are thus more
easily accessible to percolating water.
o The quantities of unhydrated tricalcium silicate and
dicalcium silicate were much greater than usually observed
in hydrated portland cement with moderate water-to-cement
ratios. The water-to-cement ratio of 0.4, typical of
cement, is used in the processing operation. The high
concentration of unhydrated silicates could result from
inefficient mixing, resulting in insufficient water
transported to these grains.
o Mixing does not appear to be highly efficient. Among the
facts indicating this are: 1) the brownish aggregates do
not undergo disaggregation 2) there are significant
amounts of unhydrated Portland cement clinker in the
samples, 3) there are globules of dark colored material in
the core samples visible to the naked eye, and 4) there
are many pores, including air bubbles.
o Two factors suggest that soil components passed through
the process unchanged. They are the presence in the cores
of apparently unaltered brownish aggregates and peaks in
104
-------
the x-ray diffraction pattern for both the soil and the
cores, which could not be identified with any expected
mineral constituents of the soil.
In summary, some of the waste in the soil appears to pass
through the process unaltered, and thus, it appears that
encapsulation is a major part of the mechanism of
solidification/stabilization. In addition, the mixing
operation is not highly efficient, resulting in incomplete
hydration of the cement and high porosity.
8.2 OPERATIONS
For the 5-cu-yd test runs, HAZCON utilized four people to
operate the unit. Their functions were as follows:
o 1 man - add feed soil and water to feed hopper
o 2 men - move and watch slurry mixer, smooth surface
of blocks, and control Chloranan flow
o 1 man - at the control panel and supervise operations
In addition, EPA provided support services to excavate the
feedstock, screen it, and bring it to the HAZCON MFU. The
soil was brought to the unit in a 2 1/4 cu yd (soil level to
surface of bucket) front-end loader, which fed it very slowly
to the feed hopper at approximately the rate the MFU processed
it. Therefore, at least two support people were required full
time to provide feed to the HAZCON unit. Also a cement supply
truck with operator/driver was on hand full time. For the
25-cu-yd run, three additional people were required to operate
the cement pump and control the feed to the large pits.
Some operating difficulties were encountered in all of the
runs, causing down times on the order of one minute to two
hours. The shutdown periods related to momentary screw
pluggages due to lack of water, oversized feedstock (stones
greater than 3 inches), interruptions of Chloranan feed, or
emptying of the cement feed hopper, which required refilling
from a supply truck. For two runs, DSA and PFA, only four
blocks were prepared due to a combination of lack of daylight,
need for more feed, and operating difficulties. On two
occasions the soil feed screw jammed so badly that the MFU had
to be brought to the decontamination area for a complete clean
out. Direct addition of water by hose to the feed screw
facilitated the movement of the soil and reduced the
likelihood of jamming. This was a water feed stream that was
not measured directly by the in-line flowmeter. Only
approximate consumptions could be provided.
In generally observing the operations, the consistency of the
slurry was quite variable due to variations in water
feedrate. The consistency of the mixed product varied from a
very thin slurry to almost a dry powder. In addition, the
105
-------
variability of the slurry mix may have prevented the Chloranan
from achieving its fully claimed benefit in counteracting the
presence of organics. As indicated in Section 8.1.3, if
insufficient water is provided, components of the cement, such
as the tricalcium silicate was incompletely hydrate, as
observed in the x-ray diffraction analyses. This will result
in a weaker and less durable block, as compared to a block
from fully mixed components.
A review of the material balances shows that for the 5-cu-yd
runs, the total mass of the blocks was consistent with the
calibrated rates for cement and soil adjusting for outage
time. Material balances also indicate the following:
o The soil was only 40% of the total weight of the blocks.
o The cement-to-feed ratio was approximately 1:1.
o The Chioranan-to-feed ratio on a weight basis ranged from
0.05 to 0.09, which is less than the target value of 0.1.
The lowest value was for FSA. No apparent reduction in
physical properties were observed.
o The water-to-feed ratio was approximately 0.4 on a weight
basis, which is appropriate for concrete preparation.
o The volume of undisturbed feedstock to produce the 5 cu yd
of slurry to fill the five 1-cu-yd molds was approximately
2 cu yd. (The front-end loader held 2 1/4 cu yd, filled
level to the top of the bucket, which produced 4 to 5
blocks.) The approximate bulk density of the screened
soil after transporting to the unit was about 20-30% less
than in the undisturbed samples analyzed and reported in
Tables 7.1-7.6.
For the extended length run at LAS, approximately 22-24 cu yd
of slurry was produced to fill the three 1-cu-yd molds and the
two large excavations. The excavations were 8x16 ft and were
filled to a depth of 2-2 1/4 ft. As shown in Table 5.1,
approximately 52,300 Ibs of the total feed (soil + cement +
Chloranan + water) was used. However, based upon the bulk
density of solidified soil of 1.7 g/ml (106 lbs/ft3), for
the total weight processed only about 18 cu yd of slurry would
have been produced. Therefore, it appears that 10,000-15,000
Ib more total feed material was processed. Since the cement
and water rates are constantly measured and the soil is based
upon the initial calibration, it is quite likely that the
missing mass, compared to the HAZCON Monitoring Worksheet, is
contaminated soil. Six front-end loader loads of soil were
processed, which is approximately 13-14 cu yd. If the
screened feed soil had a bulk density of 1.2-1.3 g/ml (75-80
lb/ftj), this would indicate a total soil usage of about
30,000 Ib, which is over 10,000 Ib greater than that recorded
on the HAZCON Monitoring Worksheet, thus providing sufficient
feed to fill the pits.
Also shown on the Monitoring Worksheet, two-thirds of the
cement was used before starting the slurry flow to the second
106
-------
large pit; this value should have been only slightly more than
50%. This ratio tended to be confirmed by the fact that 130
of a total of 255 gallons of Chloranan was used only 10
minutes after the second large pit was started.
Based upon this reasoning, the overall ratio of cement-to-soil
was about 2:3 and probably even lower for the second large
pit. In addition, the Chioranan-to-soi1 feed rate is about
0.08 versus that listed in Table 5.2, 0.119, which is based
upon the HAZCON Monitoring Worksheet. It does not appear that
any loss in physical properties resulted from this apparent
reduction in cement feed. (See Appendix B, Table A-14.)
8.3 MEETING OF SITE PROGRAM OBJECTIVES
Information relating to each of the program objectives in
Section 1.2 was obtained. This information can be summarized
as follows:
o Immobilization of site contaminants — The priority
pollutant metals were very satisfactorily immobilized,
with leachate concentrations reduced to below 0.1 ug/1 for
soils containing metals up to 23,000 mg/kg. Untreated
soil extract concentrations were typically 20 to 50 mg/1.
Immobilization of organics, VOCs, BNAs, and PCBs was not
observed. TCLP leachate concentrations for organics in
untreated and treated soils were approximately equal.
This occurred even though, on average, the treated soil
composition is lower in contaminants, due to the addition
of cement, water, and Chloranan.
o Technology effectiveness as a function of oil and grease
concentrations—The soil samples taken were in the range
of 1-25% by wt. oil and grease (O&G). Higher O&G soils
tended to have more VOCs and BNAs. Greater VOCs and
phenols (BNA components) led to higher leachate
concentrations. The most direct impact of higher O&G is
reduced unconfined compressive strength. In addition,
FSA, which had the greatest O&G content, appeared to have
a slightly greater permeability than the other test
samples.
o System performance—The operational performance of the
system was erratic, with many short and long shutdowns.
The system shutdowns ranged from 1-2 minutes up to 2-3
hours. Many shutdowns occurred for each soil feedstock.
The slurry consistency was quite variable, ranging from a
powdery mix to a very thin slurry. However, for the
extended duration run, operation outages were less and the
consistency of the product slurry improved. The impact of
consistency on physical or chemical properties of the
solidified blocks was not observed.
107
-------
Long-term integrity--Measurements of long-term integrity
of the solidified masses cannot be directly performed.
However, indications of potential difficulties could be
inferred from the microstructural analyses. These
observations showed a porous structure, with incomplete
cement hydration and organic globules existing in the
solidified cores.
Remediation costs--Remediation costs were prepared based
upon using HAZCON's MFU and the operating conditions used
for the Demonstration Test. The results showed that the
cleanup cost was $205 per ton of contaminated soil under
the ground rules defined.
108
-------
SECTION 9
ECONOMICS
9.1 INTRODUCTION
A cost analysis addresses two main categories, capital costs
and operating and maintenance costs.
Capital costs include both depreciable and nondepreciable cost
elements. Depreciable costs include direct costs for site
development, capital equipment, and equipment installation as
well as indirect costs for engineering services prior to unit
construction, such as feasibility studies and consultant
costs, administrative tasks such as permitting, construction
overhead and fee, and contingencies. Nondepreciable costs
include start-up costs including operator training, trial or
test run expenses, and working capital. Operating and
maintenance costs include variable, semivariable and fixed
cost elements. Variable operating cost elements include raw
materials, utilities, and residual water disposal costs.
Semivariable costs include unit labor and maintenance costs,
and laboratory analyses. Fixed costs include depreciation,
insurance, and taxes.
The above cost element breakdown, however, is based upon a
permanently sited hazardous waste cleanup device. The HAZCON
MFU as employed at the Douglassvi11e Superfund site is a
transportable unit that will not be installed at a fixed
site. Thus, it assumes some different cost elements that will
impact on a cost analysis from the more frequently encountered
permanent installations.
In general, the cost for a transportable hazardous waste
remediation facility falls into three categories: capital
costs including all costs that can be amortized over the
service life of the unit; mobilization/demobilization costs
associated with start-up and shutdown at a given site, that
can be amortized over the duration at the site; and operating
cost to operate and maintain the system. Capital costs can be
subdivided into direct, indirect, and nondepreciable cost
elements. Mobilization/demobilization costs can be accrued as
semivariable operating and maintenance costs. Operating costs
include variable utility and raw material costs, semivariable
labor and maintenance costs, and fixed costs such as
depreciation, insurance, and taxes.
In addition, for a mobile unit, several capital cost elements
defined for the permanently sited unit should be redefined
into a different cost element category. These include the
direct costs for site development and the direct costs for
109
-------
engineering studies, which on a site-specific basis become
mobilization/demobilization costs. These factors are not
included here because of the complexity of the analysis and
planning in this area. Total site cleanup is the
responsibility of others, with the HAZCON technology used for
only part of the total remediation.
Based on the above, an overall cost element breakdown, as
illustrated in Table 9.1, can be developed.
9.2 COST ELEMENTS
A detailed discussion of each of the cost elements defined in
Table 9.1 is provided in the following subsections. Since
this cost analysis is being prepared based upon the
Demonstration Test, the cost to process each ton of
contaminated soil will be distorted to a greater value. Cost
projections for a commercial installation will be included in
the Applications Analysis Report. In addition, not every
expense that might be encountered in a site cleanup is
included. Items such as permitting and site preparation were
omitted due to their complexity to predict costs.
9.2.1 CAPITAL COSTS
9.2.1.1 DIRECT COSTS
Equipment Fabrication/Construction and/or Purchase --
The costs for the design, engineering, materials and equipment
procurement, fabrication and installation of the HAZCON MFU
(including vehicle), are included as direct costs. The costs
include all the subsystems and components installed but do not
include the costs of the vehicles for the transport of the
accessory equipment, described in Section 3.2. Waste
preparation equipment is not included as it can be assumed to
be rented or provided by the site-responsible party.
Pretreatment or posttreatment of the soil is assumed not to be
required. For the items calculated as a fraction of direct
costs, the total of the HAZCON MFU and associated tanks,
pumps, etc., is the capital cost value used.
The capital cost value of the MFU was provided by HAZCON and
is $100,000. It is assumed that the equipment has a 10 yr
life. In addition, storage bins or tanks for cement,
Chloranan, and fuel are required, as well as an air blower for
transferring cement, pumps for the liquid, and associated
piping and controls. This was assumed to be an $80,000 cost
to the project, whether the equipment was purchased new or
used or it was sold or discarded at project completion. These
factors are site specific and major variations could occur
between sites.
110
-------
9.2.1.2 INDIRECT COSTS
Administrative/Permitting --
Administrative costs associated with regulatory compliance
issues could be numerous and varied. The costs that are being
accrued under this cost element are directed to the overall
non-site-related regulatory activities in establishing federal
and state permit requirements, preparing initial permit
applications, and supporting permit application information
throughout the permit issuance process. Once the final
permits are issued, recordkeeping, inspection, survey response
to permitting agencies, and additional reporting activities
may be required. These costs include the preparation of
technical support data, sampling/analysis, and quality
assurance project plans by in-house engineering personnel,
RCRA/TSCA permit forms (if applicable); time, travel, and per
diem for consultant and in-house staff interfacing with
Federal EPA officials; and in-house administrative and
clerical staff. For the cost estimates developed in this
analysis, these factors are not included.
For this cost analysis, administration costs are taken as 10%
of direct costs (HAZCON MFU and tanks, pumps, etc.) on an
annual basis. It includes office expenses such as supplies,
telephones, reproduction equipment, and furniture, but not
salaries (included elsewhere).
Contingency --
A contingency cost, approximating 10% of the direct capital
cost on an annual basis, is allowed for unforeseen or poorly
defined cost definitions. For the HAZCON process this is a
minor factor.
9.2.1.3 NONDEPRECIABLE COSTS
Operations Procedures/Training --
In order to ensure the safe, economical, and efficient
operation of the unit, the creation of operating procedures
and a program to train operators is necessary. Costs that may
accrue include: preparation of a unit health/safety and
operating manual, development and implementation of an
operator training program, equipment decontamination
procedures, and reporting procedures. These documents must be
site-specific. They can be related to basic documents, the
preparation costs for which can be amortized over the life of
the equipment.
Ill
-------
TABLE 9.1. COST ELEMENT BREAKDOWN
CAPITAL COST
Direct
o Equipment Fabrication/Construction or Purchase
Indirect
o Administrative/Permitting
o Contingency
Nondepreciable
o Operations Procedures/Training
o Initial Start-up/Shakedown
o Working Capital
OPERATING & MAINTENANCE COSTS
Variable
o Raw Materials - Cement
o Fuel
o Power
o Water
o Chemicals - Chloranan
Semi vari able
o Labor
o Maintenance
o Equipment Rentals and Consumables
o Analytical Services
o Mobilization/Demobilization
Site Preparation/Logistics
Transportation/Setup
On-Site Checkout
Working Capital
Decontamination/Demobilization
Fixed
o Depreciation
o Insurance
o Taxes
112
-------
It was assumed that three days of training would be required
for all HAZCON personnel, site support personnel, health and
safety officer, and sampling technician. The cost includes
salaries and living expenses. These are the only costs
included in this category.
Initial Start-up/Shakedown --
After the unit is brought to a site it must be initially
started and operated to check out the mechanical and
technical integrity of the equipment and its controls. This
cost is assumed as part of site mobilization.
Working Capital --
Although the unit is a transportable system, it will require a
supply of maintenance materials attributable to a
nondepreciable capital cost. Maintenance materials account
for approximately one-half of the total maintenance cost, and
3-month inventories are usually maintained. This cost as used
in Table 9.2 is assumed as 10% of maintenance costs.
9.2.2 OPERATING & MAINTENANCE COSTS
9.2.2.1 VARIABLE COSTS
Variable operating cost elements for this unit include fuel,
power, water, chemicals, and process waste disposal. They are
defined as variable operating cost elements because they can
usually be expressed in terms of dol1ars-per-unit flow of soil
treated and as such, these costs are more or less proportional
to overall facility utilization during specific site
operations. It is also assumed for the tabulation of costs
that there are no process waste byproducts.
Fuel --
The fuel requirement for the unit includes diesel fuel to
power the vehicle part of the MFU. In addition, fuel is used
for supporting vehicles - backhoe, front-end loader, etc. It
is estimated by HAZCON that their equipment will consume 4
gph. It is assumed that the supporting equipment consumes an
additional 4 gph. The cost of diesel fuel is about $1.00/gal.
Power --
The power requirement for the unit includes the electrical
requirements for the trailers, sampling equipment, auxiliary
lighting, etc. It is assumed that the daily average power
consumption is 5 kw with the cost of electricity $0.04/kwhr.
Water --
Water use is based upon the water content of the feedstock to
113
-------
bring the cement-like final slurry to about 20% by wt. water.
In addition, some water is used for decontamination. The
total average water usage rate is 14 gpm at a cost of $0.80
per 1000 gal Ions.
Chemi cals - -
The HAZCON proprietary additive is Chloranan, which inhibits
the effects organics have on the solidification of cement. It
is utilized in a ratio to the contaminated soil of 1:10.
HAZCON indicates the delivered cost for cement is $50/ton and
Chloranan is $3.00/gal (Chloranan density is 9.0 Ibs/gal).
Decontamination Water --
If the unit is not operated 24 hours per day, the unit needs
to be cleaned with high pressure water or steam to prevent
plugging. Costs will accrue for the containment and disposal
of this waste stream. An additional 10% water consumption was
assumed.
9.2.2.2 SEMIVARIABLE COSTS
Labor --
Operating costs for personnel for the HAZCON unit is based
upon 3 shifts per day, 21 shifts per week and totals 17
people; this includes 12 process operators, 4 supervisors, and
1 overall coordinator. In addition, there are support
personnel for operating the contaminated soil moving
equipment, a site safety and health office, the project
manager, office personnel, and a part-time sampling
technician. This totals 21 people.
The labor and living expenses for the HAZCON personnel was
provided by HAZCON. These costs range form $17.50/hr to
$50/hr for salaries with overhead and $85/day for expenses.
The support personnel costs were based upon actual costs
Incurred by EPA/Env1response for the Demonstration Test.
Salaries with overhead range from $20 to $60/hr with living
expenses (except local hires) at $120/day.
Maintenance --
Maintenance materials and labor costs are extremely difficult
to estimate and cannot be predicted as functions of a few
simple waste and facility design characteristics because a
myriad of site-specific factors can dramatically affect
maintenance requirements. Annual maintenance cost will be
assumed as 10% of capital cost.
Analyses --
In order to ensure that the unit is operating efficiently and
114
-------
meeting environmental standards, a program for continuously
analyzing waste feed and treated solids is required.
Initially sample sets will be taken daily, and less often as
operation efficiency improves, approximately once per week.
based upon the expected need to perform many of the laboratory
tests described for the Demonstration Test, the cost of a
sample set is estimated to be $5000.
Mobilization/Demobilization --
As discussed in Section 9.1, the following costs will accrue
to the HAZCON unit at each specific site. The costs are site-
specific and may vary widely depending on the nature and
location of the site. They include site preparation/
logistics, transportation/set-up, construction supervision,
on-site checkout, site-specific permitting/engineering
services, working capital, and decontamination/
demobilization. Site preparation is assumed to be by others
and no costs are included. The other costs listed above are
included elsewhere. It is assumed that mobilization is three
days of salaries plus living expenses for all personnel.
Site Preparation/Logistics -- The costs associated with site
preparation/logistics include advanced planning and
management, detailed site design and development, auxiliary
and temporary equipment and facilities, water conditioning,
emergency and safety equipment, and site staff support. Soil
excavation, feedstock preparation, and feed handling costs are
also included. This may be performed by other than HAZCON,
but still comprises part of the site remediation costs. Due
to the temporary and transient nature of the setup at
Douglassvi11e, the costs incurred by EPA for the test are not
directly used because they would be misleading. Costs for
advanced planning, detailed site design and development, and
water conditioning if needed, are assumed to be part of the
site prime contractor's expenses, and are not included.
Transportation/Set-Up -- The cost of transportation and
set-up includes disassembly of the unit at its presen*
location and transport to a new location. The HAZCON unit is
integral with the vehicle automotive function. Auxiliary
process equipment is transported on separate flatbed trucks.
The costs for transporting the unit to the Douglassvi11e site
are not included.
On-site Checkout -- Once the unit has been set up, it is
necessary to shakedown the system to ensure that no damage
occurred as a result of disassembly, transport, and
reassembly. This cost is shown as initial startup and is
assumed to be 10% of direct costs calculated on an annual
basis.
115
-------
Working Capital -- Fuel inventory, Chloranan, and cement
storage facilities will exist at each site, and as such are
semivariable operating costs specific to the site-specific
mobilization/demobilization cost element breakdown. It is
assumed that all these raw material items will be fully
consumed and therefore, no additional charge to the project is
added. The storage facilities for these materials are
included as part of the direct capital costs.
Decentamination/Demobilization -- With the completion of
activities at a specific site, the unit must be decontaminated
and demobilized before being transported to its next
location. Costs that will accrue to this cost element include
field labor and supervision, decontamination equipment and
materials, utilities, security, health/safety activities, and
site staff support. The demobilization costs included are
based upon three days for all personnel.
9.3 OVERALL COST EVALUATION
A primary purpose of this economic analysis is to estimate
costs for a commercial-size remediation. It was assumed for
this analyses that part of the Douglassvi11e site would be
remediated. Due to the short-term nature of the Demonstration
Test and the fact that labor and chemical costs dominate the
remediation costs, actual costs for the test were not directly
used. However, since HAZCON used a small-scale, continuous,
commercial unit, the capacity, on-stream factor, and chemical
usage during the Demonstration Test was the starting basis for
a commercial cleanup estimate. The results of the analysis
are presented in Table 9.2.
The results of the analysis show that the cost per ton of soil
processed is $206. In comparison to the costs of a future
commercial unit, which would be larger, have an improved
on-stream factor and probably use less chemicals, the cost per
ton of soil processed is very high. The lower values can be
obtained based upon HAZCON's recommendations for reducing
chemical consumptions 25-50% for attaining an on-stream factor
of 90%, and for use of a new 2300 Ib/min batch processing unit
and might reduce these costs by 50%. This type of analysis
will be included in the Applications Analysis Report. Since a
70% on-stream factor with high chemical consumption was
actually seen at Douglassvi11e, PA, the costs for this level
of operating efficiency were calculated. It should be noted
that not all the expenses encountered in a site cleanup are
included, such as site preparation and permitting.
As can be seen from the results, 90% of the costs consist of
raw materials (cement and Chloranan) and labor.
116
-------
TABLE 9.2. ESTIMATED COST
CAPITAL COST
Pi rect
Equipment Costs, $ 100,000
Chemical Storage, $/ton 2.25
Indirect. $/ton
Administration (10% Direct Costs) 0.32
Contingency (10% Direct Costs) 0.32
Nondepreciable. $/ton
Operator Training (3 days) 0.84
Working Capital
OPERATING AND MAINTENANCE COSTS
Variable, $/ton
Cement 50.00
Chloranan 66.67
Fuel ($1.00/gal-diesel) 1.29
Electricity ($0.04/kwhr) 0.03
Water ($0.80/1000 gal) 0.08
Semivariable. $/ton
Salaries and Living Expenses 64.70
Equipment Rentals and Consumables 10.36
Analytical Services 6.50
Maintenance (10% Direct Costs) 0.32
Mobilization/Demobilization 1.66
HAZCON and Support Fixed
Site Preparations
Insurance and Taxes (10% Direct Costs) 0.32
Depreciation (10 yrs.) 0.18
TOTALS, $/ton 205.84
117
-------
TABLE 9.2. NOTES
1. The demonstrated HAZCON MFU capacity is 300 Ib/min.
2. It is assumed that 35,400 tons of soil at the
Doug!assvi11e site was processed. This value derives from
continuously operating the demonstrated unit for 6 months
at an on-stream factor of 90%. The actual on-stream
factor used was 70%.
3. Utilities Consumption Estimates
1,200 max installed KVA
Water - 14 gpm
Diesel Fuel - 8 gph
4. Chemical Consumption
Cement - 1:1 to contaminated soil
Chloranan - 1:10 to contaminated soil
5. Labor Estimate - 4 shifts per week - includes overhead
HAZCON - 1 Manager, $50/hr; 4 Shift Supervisors, $35/hr;
12 Operators, $17.50/hour; 10% OT
Support Personnel - 1 Manager, $50/hr; 4 Shift
Supervisors, $45/hr; 12 Operators,
$40/hr; 10% OT
Others - 1 SSHO, $50/hr; 1 Project Manager, $60/hr;
Laboratory Technician (part-time), $40/hr; Office
Manager, $40/hr; Secretary, $20/hr
Living Expenses (motel, food, car rentals, etc.) -
HAZCON, $85/D; Support Personnel - Managers and
Supervisors $120/D, Operator - local - no charge;
Others - $120/0
6. Rental and Consumable Supplies
Health and Safety consumables and instruments - $450/D
Office space, office supplies, portable sanitary
faci1i ti es - $50/day
Sampling Materials - $40/set
Heavy Equipment Rental - front-end loaders, backhoes,
steam cleaner, drill rig, etc. - $1000/day
7. Site preparation costs, since it would be so interrelated
with the overall planning and costs of the Prime
Contractor for the entire site, are not included.
8. The costs taken as a fraction of capital and maintenance
costs are prorated to the actual time on site.
9. Operator training assumes 3 days of training for HAZCON
operators, site preparation operators, the Health and
Safety Officer, and sample technician.
118
-------
REFERENCES
1. Remedial Investigation Report/Feasibility Study of
Alternatives, Berks Associates - Douglassvi1le Disposal
Site - Union Township, Berks County, PA., EPA Work
Assignment No. 59-3651, Contract No. 68-01-6699, June
1986. Prepared by NUS Corporation for Region III.
2. Letter Report, S. Sawyer to P. de Percin, Laboratory
Analyses of Screening Samples, July 6, 1987.
3. Demonstration Plan - HAZCON/Douglassvi11e SITE Program,
August 31, 1987, EERU Contract No. 68-32-3255. Submitted
to P. de Percin, EPA HWERL, Cincinnati, Ohio, August 31,
1987.
«U.S. GOVERNMENT PRINTING OFFICE:! 9 89 -6 its-16 3^7066
119
-------