DRAFT   GUIDANCE
         FINANCIAL ASSURANCE AND LIABILITY INSURANCE

            Requirements for Owners and Operators
of Hazardous Waste Treatment, Storage, and Disposal Facilities
              under RCRA, Subtitle C, Subpart H
            This publication (SfoM)26) was prepared
 under contract no. 68-01-5794 for the Office of Solid Waste
             U.S. ENVIRONMENTAL PROTECTION AGENCY
                          March 1981

-------
     This document (SW-926) was prepared for the Office of Solid
Waste by the International Research and Technology Corporation.
Editing and technical content were the responsibilities of the
Hazardous and Industrial Waste Division, Office of Solid Waste.

-------
                            TABLE  OF  CONTENTS


                                                                    Page

1.0  INTRODUCTION                                                     1-1

1.1  Purpose of This Guidance Document                                1-3
1.2  Applicability of Subpart H — Financial Requirements             1-3
1.3  Financial Requirements for Owners and Operators of
     Hazardous Waste Management Facilities                            1-4

     1.3.1  Assurance of Financial Responsibility for the
            Closure and Post-Closure Care of Hazardous Waste
            Management Facilities                                     1-7
     1.3.2  Liability Insurance for Claims Arising from
            Sudden and Accidental Occurrences                         1-8
     1.3.3  Liability Insurance for Claims Arising from Nonsudden
            and Accidental Occurrences                                1-8
     1.3.4  The Difference Between Financial Requirements Under
            Interim Status Standards and General Status Standards     1-9

1.4  Role and Responsibility of Involved Parties                      1-1°

     1.4.1  Owners or Operators                                       1-10
     1.4.2  Regional Administrators                                   1"H
     1.4.3  Financial and Insurance Communities                       1-12

1.5  Relationship of the Financial Regulations to Other
     Portions of the RCRA Regulations                                 1"12

     1.5.1  Relationship Between Closure and Post-Closure Plans
            and Financial Responsibility                              1-13
     1.5.2  Cost Estimates and Financial Responsibility               1-14
     1.5.3  Cost Estimates and Levels of Assurance                    1-15
     1.5.4  Effects of Permitting Process and the RCRA Permit
            Conditions on Financial Responsibility                    1-16

1.6  Effects of Compliance Procedures on Financial
     Responsibility Mechanisms                                        1-17

2.0  FINANCIAL RESPONSIBILITY MECHANISMS — CLOSURE AND
     POST-CLOSURE                                                     2-1

2.1  Trust Funds                                                      2-1
     2.1.1  What is a Trust?                                          2-1
     2.1.2  RCRA Trust Fund                                           2-2
                                   iii

-------
                TABLE OF CONTENTS  (continued)
                                                               Page
       2.1.2.1  Investment of Funds                             2-5
       2.1.2.2  Specific Investment Provisions                  2-6
       2.1.2.3  Trust Irrevocability                            2-7

2.1.3  Qualifications of the Issuing Institution                2-7
2.1.4  Initially Executing the Trust                            2-9

       2.1.4.1  Information for the Owner or Operator           2-9
       2.1.4.2  Information for the Regional
                Administrator                                   2-11
       2.1.4.3  Certification of Acknowledgement (State
                Requirement)                                    2-11

2.1.5  Care of the Trust Agreement                              2-12
2.1.6  Multiple Facilities on One Trust Fund                    2-12
2.1.7  Payments into the Trust Fund and Trust Valuation         2-12

       2.1.7.1  Payments into the Trust Fund During
                Interim Status                                  2-13
       2.1.7.2  Payments into the Trust Fund During
                General Status                                  2-14
       2.1.7.3  Payments into the Trust Fund
                 — Facility Changes from Interim to
                General Status                                  2-16
       2.1.7.4  Payments into the Trust Fund
                — Variations Allowed                           2-16
       2.1.7.5  Objections to Valuation of the Trust Fund       2-17

2.1.8  Trustee Notice of Non-Payment                            2-17
2.1.9  Release of Funds from the Trust Fund                     2-18

       2.1.9.1  Release of Funds When Value of Trust
                Fund Exceeds Cost Estimates                     2-18
       2.1.9.2  Release of Funds Due to the Provision
                of an Alternate Financial Assurance
                Mechani sms                                      2-18
       2.1.9.3  Release of Funds as Reimbursement for
                Closure or Post-Closure                         2-19
       2.1.9.4  Release of Funds Due to Release from the
                Requirement to Provide Financial Respon-
                sibility for Closure or Post-Closure            2-20
       2.1.9.5  Release of Funds After Change in Facility
                Ownership or Operation                          2-21
                               iv

-------
                     TABLE OF  CONTENTS  (continued)


                                                                  Page

     2.1.10 Changes of  Trustees                                    2-21

            2.1.10.1 Why Trustee Would Be Changed                 2-21
            2.1.10.2  How Trustee is Changed                       2-22

     2.1.11 Standby Trust Fund                                     2-22
     2.1.12 Liability of Trustee                                   2-24

2.2  Surety Bonds                                                  2-24

     2.2.1  What is a Surety Bond?                                 2-24
     2.2.2  RCRA Surety Bonds                                      2-25

            2.2.2.1  Financial Guarantee Bonds                     2-27
            2.2.2.2  Performance Bonds                             2-27

     2.2.3  Qualifications of Issuing Corporate Surety             2-28
     2.2.4  Initially Executing the Surety Bond                    2-29

            2.2.4.1  Information for the Owner or Operator         2-29
            2.2.4.2  Information for the Regional
                     Administrator                                 2~32
            2.2.4.3  EPA Care of Bond                              2~33

     2.2.5  Multiple Facilities on the Bond                        2-34
     2.2.6  Changes in  the Coverage of the Surety Bond             2-34

            2.2.6.1  Increasing the Amount of the Bond             2~3^
            2.2.6.2  Decreasing the Amount of the Bond             2~35

     2.2.7  Cancellation of the Surety Bond by the Owner
            or Operator                                            2-36

            2.2.7.1  Cancellation of the Surety Bond Due
                     to a Change in the Status of the Issuing
                     Corporate Surety                              2-36
            2.2.7.2  Cancellation of the Surety Bond Due to
                     Changes  in Facility Ownership or Operation    2-37
            2.2.7.3  Cancellation of the Surety Bond Due to
                     the Release of the Owner or Operator from
                     the Requirement to Provide Financial
                     Responsibility for Closure or Post-Closure
                     Care                                          2-37

-------
                     TABLE OF CONTENTS  (continued)


                                                                   Page

     2.2.8  Cancellation of  a Surety Bond by the Surety Bond
            Company                                                2-38
     2.2.9  Liability of the Surety Company                        2-39

2.3  Letters of Credit                                              2-41

     2.3.1  What is a Letter of  Credit?                             2-41
     2.3.2  RCRA Letters of  Credit                                 2-42
     2.3.3  Qualifications of Issuring Institution                 2-44
     2.3.4  Initially Executing  the Letter of Credit               2-44

            2.3.4.1  Information for the Owner or Operator         2-44
            2.3.4.2  Information for the Regional Administrator    2-46
            2.3.4.3  EPA Care of Letters of Credit                 2-47

     2.3.5  Multiple Facilities  on One Letter of Credit            2-47
     2.3.6  Changes in Coverage  of the Letter of Credit            2-47

            2.3.6.1  Increasing  the Coverage of the Letter
                     of Credit                                     2-48
            2.3.6.2  Decreasing  the Coverage of the Letter
                     of Credit                                     2-48

     2.3.7  Cancellation of  the  Letter of Credit by the Owner
            or Operator                                            2-49

            2.3.7.1  Cancellation of the Letter of Credit Due
                     to Changes  in the Status of the Issuing
                     Institution                                   2-49
            2.3.7.2  Cancellation of the Letter of Credit Due
                     to Changes  in Facility Ownership or
                     Operation                                     2-50
            2.3.7.3  Cancellation of the Letter of Credit Due to
                     the Release of the Owner or Operator from
                     the Requirement to Provide Financial
                     Responsibility for Closure or Post-Closure    2-50

     2.3.8  Cancellation of  the  Letter of Credit by the Issuing
            Institution                                            2-51
     2.3.9  Responsibility of the Issuing Institution              2-52

2.4  Changing Mechanisms and Combining Mechanisms                  2-52

     2.4.1  Changing Mechanisms                                     2-53
     2.4.2  Use of Multiple  Financial Mechanisms                   2-54


                                   vi

-------
                     TABLE OF  CONTENTS  (continued)
                                                                   Page
     2.4.3  One Mechanism for tore Than One Facility                2-55
     2.4.4  Single Mechanism for Closure and Post-Closure           2-58

3.0  LIABILITY INSURANCE                                            3-1

3.1  What is Liability Insurance?                                   3-1
3.2  RCRA Liability Insurance                                       3-1

     3.2.1  Hazardous Waste Facility Liability Endorsement          3-3
     3.2.2  Coverages                                               3-3

            3.2.2.1  Responsibility for Coverage                    3-4
            3.2.2.2  Extent of Coverage - Multiple Facilities on
                     One Policy                                     3-4
            3.2.2.3  Comprehensive and General Liability Coverage   3-4
            3.2.2.4  Environmental Impairment Coverage              3-5

     3.2.3  Limits of Liability                                     3-6
     3.2.4  Financial Condition of the Insured and Legal
            Defense Costs                                           3-7
     3.2.5  Deductibles in the Insurance Policy                     3-7

3.3  Qualifications of Insurers                                     3-7
3.4  Evidence of Insurance Agreements                               3-7
3.5  Sudden and Accidental, and Nonsudden and Accidental,
     Coverage on One Insurance Policy                               3-9
3.6  Variances to the Liability Requirements                        3-9

     3.6.1  Assessing Degree and Duration of Risk                   3-10

            3.6.1.1  Waste Characterization                         3-13
            3.6.1.2  Environmental Pathways                         3-14
            3.6.1.3  Population at Risk                             3-15
            3.6.1.4  Design of Containment                          3-15
            3.6.1.5  Management Procedures                          3-16

     3.6.2  Procedures for Owner or Operator to Obtain
            a Variance                                              3-17
     3.6.3  The Role of Regional Administrator in Variance
                                                                    1  1 Q
            Requests                                                J~1J3
     3.6.4  Documentation Requirements                              3-18

3.7  Cancellation of an Insurance Policy                            3-19
                                   vii

-------
                     TABLE OF CONTENTS  (concluded)


                                                                   Page

4.0  ROLE OF STATES IN RCRA                                         4-1

4.1  Applicability of State Financial Requirements                  4-1

     4.1.1  Comparing State and  Federal Financial
            Responsibility Requirements for Facilities              4-2
     4.1.2  Flexibility and Security of State-Required
            Mechanisms                                              4-4
     4.1.3  Amount of Funds Available                               4-7
     4.1.4  Evidence of the Establishment of a State-
            Required Mechanism                                      4-7

4.2  State Assumption of Financial Requirements                     4-8

GLOSSARY                  	G-l

APPENDIX                  	A-l
                                   viii

-------
                             LIST OF TABLES

                                                                    Page

Table

1-1  40 CFR Parts 264/265 Subpart H                                  1-2

1-2  Applicability Summary:  Financial Assurance and Insurance
     Requirements                                                    1-6

2-1  Trust Fund Regulations                                          2-2

2-2  Regulatory Authorities for Financial Institutions               2-8

2-3  Surety Bond Regulations                                         2-26

2-4  Letter of Credit Regulations                                    2-43

3-1  Liability Insurance Regulations                                 3-2

3-2  Outline of Risk Components                                      3-11
                                    ix

-------
1.0  INTRODUCTION




     EPA has developed two sets of standards for hazardous  waste manage-




ment facilities under the authority of Section 3004 of  the  Resource




Conservation and Recovery Act of 1976 (RCRA).  The standards  in 40 CFR




§265 apply to facilities operating with interim status,  and the




standards in 40 CFR §264 apply to facilities operating  with general




status.




     This guidance document accompanies the portions of Subpart H of




Parts 264 and 265, issued as interim final on January 12, 1981, which




contain the financial requirements standards for the owners and




operators of hazardous waste treatment, storage, and disposal facilities




(TSDF's) (see Table 1-1).  Additional guidance reflecting any future




changes will be provided when these interim final regulations become




final.




     This document does not provide guidance for those  portions of




Subpart H which relate to closure and post-closure cost  estimates




(starred on Table 1-1).  Those requirements were issued as  final regula-




tions on May 19, 1980.  Since financial assurance for facility closure




and post-closure monitoring and maintenance can only be as  adequate as




the cost estimates and the closure and post-closure plans upon which the




assurance is based, this document should be read in association with the




guidance manuals for developing closure and post-closure plans and cost




estimates.
                                  1-1

-------
                               TABLE 1-1

                    40 CFR PARTS 264/265, SUBPART H


     •   Applicability (264.140,  265.140)

     •   Definitions (264.141,  265.141)

     •   Cost Estimate for Closure  (264.142,  265.142)

     •   Financial Assurance  for  Closure (264.143,  265.143)

     •   Cost Estimate for Post-Closure  Monitoring  and  Maintenance
         (264.144, 265.144)

     •   Financial Assurance  for  Post-Closure Monitoring  and Maintenance
         (264.145, 265.145)

     •   Use of a Mechanism for Financial Assurance of  Both Closure  and
         Post-Closure Care (264.146,  265.146)

     •   Liability Requirement  (264.147, 265.147)

     •   Incapacity of Institutions Issuing Letters of  Credit,  Surety
         Bonds, or Insurance  Policies (264.148,  265.148)

     •   Applicability of State Financial Requirements  (264.149,
         265.149)

     •   State Assumption of  Responsibility  (264.150, 265.150)

     •   Wording of the Instruments (264.151, 265.151)
*Not covered in this guidance document.
                                   1-2

-------
1.1  Purpose of This Guidance Document




     The primary purpose of this guidance document  is  to assist  the




Regional Administrators in implementing the sections of  the  interim




status and general status regulations defining financial requirements




for the owners and operators of hazardous waste management facilities.




It should provide the owners and operators of these facilities with




valuable assistance in understanding their responsibilities. This




document also provides the financial and insurance  communities with




additional details on the role EPA expects them to  play  in implementing




these regulations.




1.2  Applicability of Subpart H — Financial Requirements




     The regulations make an important distinction  between the applica-




bility of the financial requirements regulations and the actual  pro-




vision of assurance of financial responsibility. While  the  regulations




apply to both the owner and the operator of a hazardous  waste management




facility, either the owner or the operator must provide  the  assurances




of financial responsibility required for the facility.




     If the owner and the operator of a facility are different parties,




it is of no concern to EPA which one provides the necessary  assurances




of financial responsibility, or if the provision of these assurances is




somehow shared or divided.  However, the Agency will consider both




parties responsible for carrying out these requirements. For a




discussion of this joint responsibility see 45 Federal Register  33169-




33170.
                                  1-3

-------
     States and the Federal government are specifically exempted from

the financial requirements.  The Agency judged that these entities would

always have adequate resources to conduct closure and post-closure

activities properly, as well as to satisfy tLfid-party damage  claims.

This exemption does not automatically extend to owners or operators

engaged as lessors, lessees, partners, joint venturers or otherwise with

a State or the Federal government.  Such owners or operators must pro-

vide necessary assurances of financial responsibility.  These  assurances

may take the form of providing evidence that a State or the Federal

government has legally assumed responsibility for the obligations of the

owner or operator (see Section 4.2 for a discussion of State assumption

of responsibility).

1.3  Financial Requirements for Owners and Operators of Hazardous
     Waste Management Facilities

     Section 3004 of RCRA authorized the Environmental Protection Agency

to promulgate such regulations establishing standard requirements for

owners and operators of hazardous waste management facilities  respecting

"qualifications as to ownership, continuity of operation,... and

financial responsibility as may be necessary or desirable."

     The Agency concluded that compliance with this statutory  mandate

necessitated regulations assuring the protection of human health and the

environment from potential adverse effects due to improper closure or

lack of post-closure care as a result of owners or operators not having

adequate financial resources.  It also necessitated regulations assuring

the ability of owners and operators to satisfy third-party damage claims

arising from the operations of hazardous waste management facilities.

                                  1-4

-------
     The regulations specify that owners and operators of hazardous

waste management facilities must demonstrate financial responsibility to

cover closure and post-closure care and the ability to satisfy third-

party claims arising from the operations of these facilities.   Four

types of requirements may apply to a given facility:

     (1)  The provision of assurance of financial responsibility
          for facility closure;

     (2)  The provision of assurance of financial responsibility
          for facility post-closure monitoring and maintenance;

     (3)  The provision of evidence of liability insurance for
          claims arising from sudden and accidental occurrences  at
          the facility; and

     (4)  The provision of evidence of liability insurance for
          claims arising from nonsudden and accidental occurrences
          at the facility.

     A discussion of the alternative financial responsibility mechanisms

available to satisfy closure and post-closure assurance is provided in

Section 2.0 of this document; a discussion of insurance mechanisms

necessary to assure the satisfaction of third-party claims is  provided

in Section 3.0.  State-required mechanisms and State assumption  of

responsibility for financial requirements are discussed in Section 4.0.

     The financial requirements which must be satisfied by owners  or

operators and the deadlines for their satisfaction can vary according to

the type of facility (e.g., treatment, storage or disposal), the annual

sales of the owner or operator, and whether the facility is operating

with interim or general status.  These differences are summarized  in

Table 1-2 and further explained in the sections which follow.
                                  1-5

-------
CM
 I
           in
           z


e
i
ince — Nons
1 Accidental
Insure
and

c
•a
3 iH
cn 4

1 C
1 41
•a
41 -H
u u
ca <
u
3 *a
c 5


|
u


hi 41
a h
ui a


rH
-I 0
4 1
Is

e
u.

i

i


41
hi
a
m
O

7 cj


to.


w
u
[2
<*4
a

41
a.

*"*

A 1
«« to en
(J hi (ft -H
ca hi u a
u -a .55

41  ^4
hi U 30
•HUM
a « os
O"*»
a: u o




•a
4)
hi

3
O"
Si

1





c
o
•H
CO
•-*
3

4t
X


O
"3 41







C


(a

H





Required
i




4t
h> e
x-35

U fl
"85*3
hi u 00
•H U 41
3 41 SC
o-m
at w o




•a
4>
hi

3

d

I




41
c
5


3

41
OC


o
41
^







41
OO
ta
o
VI

§41 C 41 C
JS O JS Q
U 4-> 1-1 iJ
a u (« hi rq
U ^H 41 -H 41 •-»
41 3 u 3 ht 3
•*« 41 (4 01 <4 01
m ec aei ai
CA cn
£ Q 4-1 O hi O
C 41 Q 41 § 4)
41 4» 01
•a > -a > *w >
01 45 3 -H U -H
— * U -H CJ -rt U
34) a oi 3 a
E* U OS Ul 3C W
41
•H
U O
<*•! 1j


3
X 00
JD 4)

•o
hi O
•H

a- M
cS Q

01
hi C

u -2
M
M O


£3

41
hi a
So
•H


3
X 90
A 41
B6
-a
41 "**
hi O
3 01
tr u


§
1 s s
cn
^ 41 V
« (rt "
-* « ^ (A
« U V
M -H 3T r-l
a. cn w tn

u a
to u
< 0

•H O


U (II
i£
C
(fa
c
(0
hi
3
ca
S Z
~4 (A
 en
5 i
hi T3
O. h>
cn N
x m
ctj -C
tj
S 5


V 41 —
hi U ^
•^ 41 V
a u M
tr cn
u Q «
OS h. 3

T)
O
a.
Ul
a
                                                                                             u 3
                                                                                             * O
                                                                                              -
                                                                                             11
                                                                                            <*\
ss
Si
                                                                                                « H
                                                                                                Id ^

                                                                                                3 •;
                                                                                             -J   OS
                                                                                             (Q   W =
                                                                                             r-   ft ^
                                                                                             3   h. •
                                                                                             ^   — -
                                                                                                
-------
     1.3.1  Assurance of Financial Responsibility for the Closure and
            Post-Closure Care of Hazardous Waste Management Facilities

     Owners or operators of TSDF's must establish financial assurance

for closure of their facilities.  In addition,  owners or operators of

disposal facilities must establish assurance for 30 years of post-

closure care.  Assurance for facilities operating with interim status

must be provided by either a trust fund, a surety bond guaranteeing

payment into a standby trust fund, a letter of  credit, a combination of

these instruments allowed by the regulations (see Section 2.4.2), a

State-required mechanism authorized by the Regional Administrator (see

Section 4.1), or a State assumption of responsibility for these require-

ments (see Section 4.2).  Owners or operators of facilities operating

with general status may also provide assurance  using a surety bond

guaranteeing performance of closure or post-closure monitoring and

maintenance.

     Owners or operators of facilities operating with interim status

must provide assurance for closure and post-closure by July 13, 1981.

Owners or operators of new facilities which will operate with general

status must provide evidence of this assurance  60 days before hazardous

waste is first received for treatment, storage  or disposal.  Surety

bonds and letters of credit need not be effective, however, until imme-

diately before hazardous waste is first received for treatment, storage

or disposal.  Owners or operators of facilities which are granted

permits and change from interim to general status will already have

their mechanisms for assurance of closure and post-closure care in place

before the change occurs.


                                  1-7

-------
     1.3.2  Liability Insurance for Claims Arising from Sudden and
            Accidental Occurrences

     An owners or operators of TSDF's must demonstrate financial respon-

sibility for claims arising from the operatic is of their facilities from

sudden and accidental occurrences that cause Injury to persons or

property.  Financial responsibility for these claims must be provided by

liability insurance, a State-required mechanism authorized by the

Regional Administrator (see Section 4.1), or a State assumption of

responsibility for these claims (see Section 4.2).  This coverage is

necessary only during the operating life of a facility.  The level of

liability coverage required is discussed in Section 3.2.3.

     Owners or operators of facilities operating with interim status

must provide evidence of this liability mechanism for claims arising

from sudden and accidental occurrences by July 13, 1981.  Owners or

operators of new facilities which will operate with general status must

provide evidence of this liability mechanism 60 days before hazardous

waste is first received. T the coverage must be effective prior to the

receipt of hazardous waste for treatment, storage, or disposal.  Owners

or operators of facilities which are granted permits and change from

interim to general status will already have their liability mechanism

for claims arising from sudden and accidental occurrences in place.

     1.3.3  Liability Insurance for Claims Arising from Nonsudden and
           Accidental Occurrences

     Owners or operators of surface impoundments, landfills, or land

treatment facilities must demonstrate financial responsibility for

claims arising from the operations of theier facilities from nonsudden
                                   1-8

-------
and accidental occurrences that cause injury to persons or property.

Financial responsibility for these claims must be provided by liability

insurance, a State-required mechanism authorized by the Regional Admin-

istrator (see Section 4.1), or a State assumption of responsibility for

these claims (see Section 4.2).  This coverage is necessary only during

the operating life of a facility.  The level of liability coverage

required is discussed in Section 3.2.3.

     This financial requirement will be phased in for owners or

operators of facilities operating with interim status and for owners or

operators of facilities which are granted permits and change from

interim to general status (see Section 3.4 for these dates).  Owners or

operators of new facilities must provide evidence of this coverage 60

days before hazardous waste is first received for treatment, storage, or

disposal.  The coverage must be effective prior to the receipt of

hazardous waste for treatment, storage, or disposal.

     1.3.4  The Difference Between Financial Requirements Under
            Interim Status Standards and General Status Standards

     There are minor differences between the financial

requirements of Parts 264 (general status standards) and 265

(interim status standards).  These differences are summarized

below.

    (1)  Deadlines for the establishment of financial mechanisms
         (see Table 1-2 and Sections 1.3.1, 1.3.2, 1.3.3 and 3.4).

    (2)  Amount of time allowed for the build-up of a trust fund
         (see Sections 2.1.7.1, 2.1.7.2 and 2.1.7.3).

    (3)  Types of surety bonds allowed to provide assurance (see
         Section 2.2.2).
                                  1-9

-------
1.4  Role and Responsibility of Involved Parties




     The promulgation of the regulations establishing financial  require-




ments for the owners and operators of hazardous  waste management




facilities is only a preliminary step in carrying out some of  the goals




of RCRA.  These goals will only be achieved if the parties involved




understand and carry out their responsibilities  as prescribed  by the




financial requirements regulations.




     1.4.1  Owners or Operators




     Owners or operators will have the primary responsibility  for




carrying out the requirements of these regulations.  They will have to




develop cost estimates based on closure and post-closure plans (see




Sections 1.5.1 and 1.5.2) and set aside assets or use a third-party




guarantee to prove that funds will be available when needed for  these




activities.  They will also have to provide a liability mechanism so




that third-party claims may be satisfied while the facility is in opera-




tion.



     Once financial and liability mechanisms are established,  owners or




operators must also adjust the mechanisms whenever necessary to  reflect




changes which occur annually (e.g., cost estimates due to inflation) or




periodically (e.g., change in extent of facility operations, sale of a




facility).  This is further explained in Sections 1.5.1, 1.5.2,  1.5.3,




1.5.4 and in the discussions in Sections of 2.0 and 3.0 of the various




financial and insurance mechanisms.
                                   1-LO

-------
     1.4.2  Regional Administrators

     There are five basic areas of responsibility for Regional Adminis-

trators in conjunction with financial requirements.

    (1)  Regional Administrators will have to evaluate each
         financial and liability mechanism provided by an owner or
         operator to ensure that it is a mechanism allowed by the
         regulations.

    (2)  Regional Administrators will have to determine that the
         financial and liability mechanisms provided are executed
         correctly (see the sections describing the various
         mechanisms).

    (3)  Regional Administrators will have to check that financial
         mechanisms provide assurance at least equal to the
         relevant cost estimates (see Section 1.5.2) unless
         assurance is provided by a trust fund (in which case the
         assurance must be at least equal to the required
         percentage of the cost estimates).

    (4)  Regional Administrators will have to judge whether
         liability mechanisms reflect the degree and duration of
         risks at individual facilities (see Section 3.6.1).

    (5)  Regional Administrators will have to evaluate requests
         from owners or operators for decreases in co\/erage of
         financial mechanisms, releases from the financial and
         liability requirements, and reimbursements for expenses
         from trust funds (see sections describing the various
         mechanisms).

     Regional Administrators should also be sure that owners or

operators rigidly adhere to deadlines (e.g., for the establishment of

mechanisms, for payment into a trust fund).  The financial and liability

mechanisms were developed to provide Regional Administrators with some

warning of threatened losses of coverage, necessary increases in

coverage, and failures to make payments into trust funds.   The Regional

Administrators must know when cancellations will take effect and whether

necessary increases in coverage have been obtained.  A chronological
                                  1-11

-------
record of all actions taken by owners or operators to comply with the

financial responsibility requirements is therefore necessary for each

facility.  Documents, correspondence, and other items related to the

financial responsibility requirements of a facility must always be dated

using a time-clock or a date stamp.

     1.4.3  Financial and Insurance Communities

     EPA expects the financial and insurance communities to follow

standard business practices when offering the financial and liability

mechanisms required by the financial requirements regulations.  The

financial and insurance communities must use the forms developed by EPA

(unless they are offering State-required mechanisms) and certify that

the wording of the mechanism is identical to the wording of the

mechanism developed by EPA.  Specific requirements for different members

of the financial and insurance communities are discussed in the sections

describing the financial and liability mechanisms.

1.5  Relationship of the Financial Regulations to Other Portions of
     the RCRA Regulations

     Owners or operators of TSDF's must have financial assurance in an

amount sufficient to cover the costs of closure and post-closure care.

The amount guaranteed by the financial mechanism chosen is based on the

closure and post-closure cost estimates, which are derived from the

closure and post-closure plans.  Guidance on developing cost estimates

and preparing closure and post-closure plans is provided in two other

EPA guidance manuals.
                                   1-12

-------
     1.5.1  Relationship between Closure end Post-Closure Plans  and
            Financial Responsibility

     The cost estimates are based on the costs of activities described

in the closure and post-closure plans.   The closure plans describe  the

procedures required to ensure that the facilities are closed in  a manner

consistent with the closure regulations.  The post-closure plans

describe procedures for monitoring and maintaining disposal facilities

for a specified period of time after the facility has been closed.   The

activities described in both closure and post-closure plans must account

for the maximum extent of operation; that is, the most extensive activi-.

ties that could be required.

     For facilities operating with interim status, closure and post-

closure plans must be prepared and be available,  subject to inspection

at the facility, by May 19, 1981.  Although all owners and operators are

not required to submit their plans, the Regional Administrators  intend

to request some owners and operators to submit their plans for

evaluation.  For facilities operating with general status, the plans

will have been evaluated as part of the permitting process.

     During both interim status and general status, owners or operators

must revise the plans during both the operating life of their facility

and during post-closure, if changes in operations or design affect  the

plans.  These changes only affect financial responsibility if they  also

affect the cost estimates and render the amount guaranteed by the finan-

cial assurance mechanism inadequate.  However, owners or operators  only

have to adjust the level of their financial assurance mechanisms during

the active life of their facilities.


                                   1-13

-------
     During interim status, owners or operators are responsible for




updating their plans when needed and for keeping updated versions of  the




plans at the facility available for EPA inspection.  For a facility




operating with general status, the plans become part of the conditions




of the permit and all plan revisions are treated as permit




modifications.




     1.5.2  Cost Estimates and Financial Responsibility




     The amount guaranteed by the financial responsibility mechanism  is




based on the cost estimates.  The effectiveness of the financial




requirements depends both on the accuracy of the cost estimates and the




fact that the amount covered by the financial instrument accurately




reflects the cost estimates.  During interim status, owners or operators




must prepare cost estimates by May 19, 1981 and have them available at




theier facilities subject to inspection, but they do not need to submit




them, unless requested by the Regional Administrator.  For facilities




operating with general status, the cost estimates will be evaluated




during the permitting process and will be part of the permit conditions.




     During interim status and general status, owners and operators must




revise the cost estimates annually to reflect the effects of




inflation.   The cost estimates must also be revised whenever changes in




plans affect the costs of closure or post-closure.  During interim




status, owners or operators must adjust their estimates every May 19




using an inflation adjuster specified in the regulations; during general




status, estimates must be adjusted on the anniversary date of the




permit.  Whenever the cost estimates are increased during the active
                                   1-14

-------
life of the facility, the amount provided by the financial assurance




mechanisms must be adjusted upward if it is no longer sufficient  to




cover the costs of closure or post-closure.  Once closure begins  (within




30 days after the date on which the owners or operators expect to




receive the final volume of wastes), however, owners or operators not




required by regulation to adjust the amount provided by the financial




mechanisms, regardless of the revisions made to the plans.




     At any time (i.e., during the life of the facility or post-




closure) , owners or operators may request that their cost estimates and




their level of financial responsibility be reduced if the amounts exceed




the current cost estimates.  For example, if owners or operators  change




their operating plans and reduces the area that is open during the life




of the facility, they may reduce their closure cost estimates and the




level of their financial responsibility.  Similarly, they may reduce




their post-closure cost estimate and the amount provided by the




financial instrument if they are granted a variance to the 30-year post-




closure care period.




     1.5.3  Cost Estimates and Levels of Assurance




     Regional Administrators may check to be sure that financial  instru-




ments are always based upon current cost estimates.  Although the most




recent plans and estimates are kept at the facilities during interim




status, Regional Administrators may request at any time that the  plans,




estimates, or both be submitted to them so that they can review them.




The Regional Administrators also may check the plans and estimates at




the facilities, where they must be available for inspection.
                                  1-15

-------
     When owners or operators receive a RCRA permit for a facility,  the


cost estimates requirements will become part of the permit conditions.


Annual adjustments to account for inflation and to reflect current costs


must be submitted to the Regional Administrators for approval,  as  part


of the conditions of a permit.  On each anniversary of the date on which


a facility was granted a permit, and at any other time that Regional


Administrators receive a request for a modification of the cost


estimate, they should compare the new cost estimate with the amount


assured by the financial instrument.


     1.5.4  Effects of the Permitting Process and the RCRA Permit
            Conditions on Financial Responsibility


     All facilities which were in operation on November 19, 1980,  and


whose owners or operators have submitted notification and Part  A of  the


permit application, are operating in interim status until a RCRA permit


is recieved.  Any time after July 13, 1981, the Regional Administrators


may require owners or operators of existing container, tank, surface


impoundment and pile facilities to submit Part B of the permit


application.  This will enable the Regional Administrators to begin


permitting these facilities.  The permitting process for incinerator


facilities may begin any time on or after July 22, 1981.  The permitting


regulations for land disposal facilities have not yet been promulgated.


     Owners or operators of new facilities (i.e., facilities not in


existence on November 19, 1980) must have a RCRA permit before  they


begin operations.  As part of the permitting process, closure and  post-


closure plans, cost estimates, and financial assurance mechanisms  will


be evaluated and revised if necessary and incorporated as part  of  the


permit conditions.
                                   1-16

-------
     The Regional Administrators will review each permit after a

specified period of time, and either reissue it for another specified

period or revoke it.  During this review, the Regional Administrators

should ensure that the amount covered by the financial mechanism is

adequate.  Once a facility has received a permit, the Regional Adminis-

trators only have to ensure that the financial mechanism is consistent

with the conditions of the regulation.

1.6  Effects of Compliance Procedures on Financial Responsibility
     Mechanisms

     It is the intent of these regulations to ensure that hazardous

waste management facilities are never without the required coverages  for

closure and post-closure.  Therefore, surety bonds and letters of credit

may not be cancelled while a compliance procedure is pending.   A compli-

ance procedure is defined broadly as "any proceedings pursuant to RCRA

or regulations issued under authority of RCRA which seeks to require

compliance or which is in the nature of an enforcement action  or an

action to cure a violation."  (40 CFR §§264.141 and 265.141)

     Every compliance order, notice of intent to terminate interim

status or to terminate a permit, or any other notice with respect to  an

enforcement action or an action to cure a violation issued by  a Regional

Administrator must reference the trust funds, surety bonds, letters of

credit, or State-required mechanisms which are providing assurance of

financial responsibility for closure or post-closure; warn that these

mechanisms may not be cancelled while the compliance proceeding is

pending; and warn that they may be subject to claims by the EPA if

violations are not corrected.  If the Regional Administrator deems the


                                  1-17

-------
owner's or operator's violation to be serious enough (e.g.,  violation of




closure requirements), the order or notice may also  indicate the




Regional Administrator's intention to have the financial institution or




surety company place the funds guaranteed by a letter of credit or




surety bond in the standby trust fund (see Section 2.1.11).




     Policy from the Agency will be forthcoming on how funds in trust




funds or standby trust funds will be expended if it  becomes  necessary




for the Agency to direct closure or post-closure care at hazardous waste




management facilities.
                                   1-18

-------
2.0  FINANCIAL RESPONSIBILITY MECHANISMS

2.1  Trust Funds

     2.1.1  What is a Trust?
     A trust is an agreement among three parties, in which one party

transfers legal title to assets (usually money) to another party,  who

manages the assets for a third party.  The party providing the assets to

create a trust is the grantor or trustor, the party with legal title is

the trustee, and the party deriving the benefits from the property is

the beneficiary.

     Trust arrangements are governed by a trust agreement or

instrument.  The instrument typically names the grantor, trustee,  and

beneficiary, and defines the objective of the trust.  It may also

specify the amount of discretion the trustee will exercise over invest-

ments or define the types of assets that may compose the trust.

     Individuals or corporations establish trusts for many different

reasons.  Some possible benefits of establishing a trust are:

    •  Professional Asset Management — Trustees may be highly
       skilled professionals with access to specialized
       information with which to make investment decisions.

    •  Security and Protection — Both the grantor and the
       beneficiary have the security of knowing that the trustee
       is legally charged with acting solely for the benefit of
       the trust.

    •  Relief from Administrative Details — Trustees can free
       both grantor and beneficiary from having to handle details
       associated with managing assets.

    •  Financial Planning — A trust can be used in planning how
       to meet future financial commitments (statutory or
       otherwise).
                                   2-1

-------
     2.1.2  RCRA Trust Fund

     Owners and operators of TSDF's  may create a  trust fund to meet

their obligation to provide financial  assurance for closure and post-

closure care.  Table 2-1  indicates the sections of the Code of Federal

Regulations (CFR) applicable to the  implementation and use of the trust

fund and the section specifying the  wording of the agreement.

                               TABLE 2-1
                         TRUST FUND REGULATIONS
 SUBJECT OF
 REGULATION
       SECTION OF REGULATION

  INTERIM STATUS          GENERAL STATUS
 Closure Trust

 Post-Closure Trust

 Trust Agreement Form
40 CFR §265.143(a)

40 CFR S265.145(a)

40 CFR §265.151(a)
40 CFR §264.143(a)

40 CFR §264.145(a)

40 CFR §264.151(a)
For the text of these regulations see 46 Federal  Register pp. 2851 et
seq. (January 12, 1981).


     In the RCRA trust agreement, the owner or operator  is  the grantor,

his bank or other financial institution is the trustee,  and EPA is the

beneficiary.

     The trust fund is designed to ensure that the owner or operator

will set aside assets over a period of time to cover  the costs of

closure or post-closure care (or both) when these activities  occur at

the facility.  For facilities with interim status, the value  of the

trust may build towards the required level of assurance  over  a period of

20 years, or over the life of the facility, whichever is shorter  (see
                                   2-2

-------
Section 2.1.7.1).  For permitted facilities with general status,  the

value of the trust may build over the life of  the permit which, in  most

cases, will be 10 years (see Section 2.1.7.2).  When a facility receives

a permit and thus changes from interim to general status, the  balance  of

the required trust amount must be paid in over the term of the permit

(see Sections 1.2.6 and 2.1.7.3).

     In addition to providing one alternative  form of financial

assurance, the trust agreement and regulations also serve another

purpose.  Owners and operators who use surety  bonds or letters of credit

as financial assurance mechanisms must also at the same time establish a

standby trust fund (see Section 2.1.11).  Any  funds drawn under those

instruments will be placed directly into the standby trust fund (see

Sections 2.2.2.1, 2.2.2.2 and 2.3.2).  Except  with regard to payments

into the fund the standby trust fund generally functions according  to

the trust agreement and regulations described  in this section.

     Each section of the RCRA trust agreement  provides for specific

features of the trust.  Those features are briefly explained here.   Most

sections of the trust agreement are also explained in greater  detail in

other indicated sections of this manual.

                     Sections of  the Trust Agreement

    •    Introduction — describes parties to  and purpose of the
         trust fund (see Sections 2.1.1 and 2.1.2)

    •    Section 1 — defines "fiduciary," "grantor," and
         "trustee" for the purposes of this trust

    •    Section 2 — provides for the identification of the
         facilities and the amounts of the closure and post-
         closure cost estimates covered by the trust agreement
                                   2-3

-------
Section 3 — establishes EPA as the beneficiary of the
trust and describes the constitution of the "fund"

Section 4 — provides for reimbursement of closure and
post-closure expenditures (see Section 2.1.9.3)

Section 5 — describes the assets which will be paid into
the fund

Section 6 — explains how the trustee will manage and
invest the assets composing the fund (see Sections
2.1.2.1 and 2.1.4.1)

Section 7 — specifically authorizes certain trustee
investments (see Section 2.1.2.2)

Section 8 — describes the powers of the trustee (see
Section 2.1.2.2)

Section 9 — provides that certain taxes and fees will be
paid by the fund and that the trustee will be reimbursed
for expenses either by the grantor (owner or operator) or
by the fund (see Section 2.1.4.1)

Section 10 — obligates the trustee to value the fund
annually and to provide the appropriate Regional Adminis-
trator with the valuation (see Section 2.1.7)

Section 11 — allows the trustee to consult with counsel

Section 12 — authorizes trustee compensation (see
Section 2.1.4.1)

Section 13 — sets forth the procedure for a change of
trustees (see Section 2.1.10.2)

Section 14 — explains how the trustee is to receive
orders from EPA or the grantor (owner or operator) and
the duty of the trustee to act in accordance with these
orders

Section 15 — obligates the trustee to notify EPA and the
grantor if a scheduled payment into the fund is not
received (see Section 2.1.8)

Section 16 — explains how the trust can be amended

Section 17 — establishes that the trust is irrevocable
and sets forth how it can be terminated (see Sections
2.1.2.3 and 2.1.10.2)
                          2-4

-------
    •    Section 18 — addresses the extent of trustee liability
         (see Section 2.1.12)

    •    Section 19 — provides that the trust will be
         administered according to the laws of a chosen State

    •    Section 20 — discusses the use of headings and grammar
         in the trust agreement

     Many of the above provisions are common to most trusts.  Two of the

most important provisions specific to the RCRA trust, concerning invest-

ment and the irrevocability of the trust, are discussed in the following

three sections of this manual.

     2.1.2.1  Investment of Funds

     The RCRA trust agreement allows the trustee discretion in investing

the trust's assets, but holds the trustee to a "prudent man" standard.

Originally stated in 1830 by the Massachusetts State Supreme Court, a

recent version of that standard has been codified in the Employee

Retirement Income Security Act of 1974 (ERISA), an act which established

provisions for management of the assets of trusts established for

pension plans.  The ERISA prudent man standard requires the fiduciary to

discharge his duties "... with the care, skill, prudence, and diligence

under the circumstances then prevailing that a prudent man acting in a

like capacity and familiar with such matters would use in the conduct of

an enterprise of a like character and with like aims...."  (29 USC

§1104).  This statutory standard is the basic investment guideline for

management of the trust assets by the trustee of the RCRA trust.

     The Agency has added three exceptions to this standard.  These

additional investment provisions are discussed in the. following section.
                                   2-5

-------
     2.1.2.2  Specific Investment Provisions

     Section 6(i) of the trust agreement specifically forbids  the

trustee to invest in:

    Securities or other obligations of the Grantor,  or any other
    owner or operator  of the facilities, or any of their
    affiliates as defined in the Investment Company  Act of 1940,
    as amended, 15 USC §80a-2.(a)...

     EPA included this provision to protect the trust corpus in the

event of the bankruptcy of any of the businesses or  affiliates of the

owner or operator.

     Securities and other obligations of the Federal government or a

State government are specifically exempted from this restriction on

investment.  EPA did not want to exclude investments in Federal and

State bonds where the  Federal government or a State  government is the

owner of the facility or the land on which a facility is situated, but

the operator is another entity and is the party responsible for meeting

the financial requirements.

     Trustees are generally obligated to keep trust  property segregated

from the trustee's own funds and from other funds.   However, in the

interest of increasing the availability of trust funds for EPA'3

purpose, the trust agreement specifically allows the trustee to depart

from this general rule.  First, he is allowed to invest in time or

demand deposits of the trustee, up to the insured amount.  Second,

Section 7 of the trust agreement expressly allows the trustee  to

transfer assets of the fund "to any common, commingled or collective

trust fund created by the trustee in which the Fund  is eligible to

participate...."  This practice is forbidden by law  except in  authorized
                                   2-6

-------
cases.  The Securities and Exchange Commission has agreed that in the




case of the RCRA trust fund such commingling of trust  assets  will be




allowable, to increase the number of trustees available.




     2.1.2.3  Trust Irrevocability




     The RCRA trust is irrevocable; it cannot be changed  or terminated




by the grantor except by the written agreement of the  trustee and the




SPA Regional Administrator, as well as the grantor.




     2.1.3  Qualifications of the Issuing Institution




     EPA has decided that the trustee named in the trust  agreement must




be a bank or other financial institution which has the authority to act




as a trustee and whose trust operations are regulated  and examined by a




Federal or State agency.




     All domestic bank trust departments and savings and  loan trust




departments are regulated and examined.  In order to determine whether




the financial institution named as trustee on a trust  agreement has the




authority to act as a trustee, the regulatory authority may be




contacted.  Table 2-2 indicates the primary regulatory authority for




each type of financial institution.




     Some American branches of foreign banks are regulated and examined




by the Federal Deposit Insurance Corporation, and that authority can




certify whether the bank in question has trust powers. Other foreign




banks with American branches should be able to provide information about




which regulatory authority oversees their operations and  can attest to




their trust powers.
                                   2-7

-------
                               TABLE  2-2

           REGULATORY AUTHORITIES FOR FINANCIAL  INSTITUTIONS
              Type of Financial
                 Institution
     Primary Regulatory
         Authority
1.  State Bank

    a. not insured by the FDIC*;
       not a member of the FRS**

    b. insured by the FDIC;
       not a member of FRS

    b. insured by the FDIC;
       a member of the FRS
2.  National Bank and some
    Washington, D.C. Banks

3.  State-chartered Savings
    and Loan
    Federally-chartered
    Savings and Loan
State Banking Authority for
 the State in question

Federal Deposit Insurance
 Corporation

Board of Governors of the
 Federal Reserve,  through
 Federal Reserve Banks
Comptroller of the Currency
State Savings and Loan Insurance
 Corporation for the State
 in question

Federal Home Loan Bank Board
 *FDIC * Federal Deposit Insurance Corporation
**FRS * Federal Reserve System
                                    2-8

-------
     Trust companies or other institutions should be able  to  provide

owners, operators or Regional Administrators  with the name of the regu-

latory authority able to attest to their trust powers.

     2.1.4  Initially Executing the Trust Fund

     2.1.4.1  Information for the Owner or Operator

     The trust agreement allowable under these regulations should be

widely available, although the owner or operator  might  have to

familiarize his chosen trustee institution with the  trust  instrument

specified in the regulations.  Trustee institutions  charge fees  for

their services.  These fees can be expected to vary  depending upon the

specific trust institution involved, the amount of the  trust  fund, the

extent to which the owner or operator uses the trust institution for

other services, and the extent of investment  activity and  trustee invol-

vement.

     This trust agreement specifies that the  trustee must  provide

services that include:

    •    Making authorized payments from the  fund (see  Section
         2.1.9.3);

    •    Investing, reinvesting, exchanging,  selling and managing
         the fund (see Section 2.1.2.1);

    •    Furnishing an annual valuation of the fund  to  the
         Regional Administrator and to the owner  or  operator  (see
         Section 2.1.7); and

    •    Notifying the Regional Administrator of  the failure  of
         the grantor to make a deposit (see Section  2.1.8).

     As discussed in Sections 2.1.2.1 and 2.1.2.2, the  trustee is

allowed a large degree of discretion in investing the fund.  The owner

or operator should discuss investment with prospective  trustees  to


                                    2-9

-------
determine how different investment strategies would affect fees.   The




general investment philosophy of the trustee (e.g., maximization  of




income, maximization of safety, etc.) is another topic which should  be




of interest to the owner or operator.  The owner or operator could also




discuss the eligibility of his trust to participate with others in a




commingled fund (see Section 2.1.2.2) as this too might have a bearing




on costs.




     The owner or operator should inquire about other expenses and fees




that would be levied against the trust such as:




    •    Income Taxes — State and Federal




    •    Brokerage Fees




    •    Legal Fees (e.g., for setting up the trust)




    •    Accounting Fees






     If an owner or operator is dissatisfied with the performance of his




chosen trustee, he may change to another eligible trustee institution




after receiving a written consent from the Regional Administrator and




the trustee (see Section 2.1.10.2).




     The owner or operator and the trustee should note especially that




when initially executing the trust agreement, they both will be held




responsible for making certain that the wording of the trust agreement




is identical to the wording of 40 CFR §265.151(a) (Interim Status) or 40




CFR §264.151(a) (General Status).  They both are also responsible for




making certain that the certification of acknowledgment accompanying the




trust agreement (see Section 2.1.4.3) conforms to state requirements on




the proper content of this acknowledgment.





                                    2-10

-------
     2.1.4.2  Information for the Regional Administrator

     All trust agreements submitted to EPA must:

    •    Be delivered to the Regional Adminstrator either in
         person or by certified mail.

    •    Be received by the Regional Administrator by the
         effective date of the interim status regulations (July
         13, 1981) for existing facilities.  For  new faciliteis
         the trust agreement must be received 60  days before the
         date on which hazardous waste is first received for
         treatment, storage, or disposal.

    •    Have wording identical to the wording specified in the
         regulations

    •    Be accompanied by a formal Certification of Acknowledge-
         ment

In addition, the initial trust fund payment (see  Section 2.1.7.1) must

be made at the time the trust is established.

     2.1.4.3  Certification of Acknowledgment (State Requirement)

     An acknowledgment is a formal declaration by persons executing an

instrument (such as a trust fund) that they affirm the obligation or

responsibility created by the instrument and that they give their affir-

mation freely.  The acknowledgment is usually given before an authorized

official, such as a notary public.

     State laws may differ concerning the form and wording of the

acknowledgment and who, if anyone, must witness the acknowledgment.

Therefore, no standard language has been provided in the regulation.

Although the owner or operator and trustee will be held responsible for

making certain that the certification of acknowledgment conforms to

State law, Regional Administrators should become  familiar with the

acknowledgments required by the States they are administering.
                                   2-11

-------
     2.1.5  Care of the Trust Agreement




     Copies of the trust agreement should be kept in a safe  location.




     2.1.6  Multiple Facilities on One Trust Fund




     An owner or operator may use one trust fund to provide  assurance  of




financial responsibility for closure, post-closure care,  or  both,  for




one or more facilities (see Section 2.4.3 and 2.4.4).




     2.1.7  Payments into the Trust Fund and Trust Valuation




     The trust fund is not required to provide assurance  of  financial




responsibility in the full amount of the cost estimate when  it  is  first




established.  During interim and general status, the amount  of  financial




assurance provided by the trust is allowed to build to the required




level over specified time periods (see Sections 2.1.7.1,  2.1.7.2 and




2.1.7.3).



     Owners and operators and Regional Administrators should remember




that in addition to deliberate adjustments in the value of the  trust




fund to reflect changes in cost estimates, the value of the  trust fund




will fluctuate depending on the investment earnings (or losses) of the




assets composing the fund.  The trustee will be responsible  for the




valuation of the trust fund (see Section 2.1.7.5 for the valuation




procedure).  The owner or operator will be responsible for the accuracy




of cost estimates.  After the owner or operator has updated  his cost




estimates and received the trustee's report of valuation, the owner or




operator will have to calculate how large the new deposit into the trust




fund will have  to  be to maintain the required amount of assurance of




financial responsibility.
                                    2-12

-------
     2.1.7.1  Payments Into the Trust Fund During Interim Status

     During interim status the procedure for determining and making

payments into the trust fund must operate as follows.   Sample

calculations are provided in the Appendix.

    •   May 19, 1981

          By this date closure and post-closure cost estimates
     must be available at the facility.

    •   July 13, 1981

          By this date the first payment must be deposited into
     the trust fund.  The amount of the  first payment  may be
     calculated using the formula:

                   ACE-CV
                     Y
     where ACE equals the adjusted closure cost estimate or the
     adjusted post-closure cost estimate or both, CV equals the
     current value of the trust fund (the value of CV would be
     zero before the first payment was made), and Y equals the
     remaining operating life of the facility or 20 years, which-
     ever is shorter.

    •    May 19, 1982

          By this date cost estimates must be adjusted using the
     inflation factor calculated in accordance with 40 CFR
     §§265.142 and 265.144.

    •    Between the end of June and the end of July 1982

          The trustee must furnish to the grantor and  the appro-
     priate EPA Regional Administrator(s) a statement  confirming
     the value of the fund.

    •    No later than August 12, 1982

          By this date the second payment must be deposited into
     the trust fund.  The amount of the  second payment may be
     calculated using the same formula as above.

     Subsequent adjustments of cost estimates for inflation must  take

place annually by May 19 over the operating life of the facility.

Subsequent statements confirming the value of the fund must be furnished

                                   2-13

-------
by the trustee to the grantor and the appropriate Regional

Administrator(s) annually between the end of June and the end of July.

Subsequent payments into the fund must be deposited annually by August

12.

     2.1.7.2  Payments Into the Trust Fund During General Status

     During general status, the procedure for determining and making

payments into the trust fund must operate as follows.  Sample calcu-

lations are provided in Appendix A.

    •    Date the facility receives  a permit

              By this date approved  cost estimates must be
         available at the facility.

    *    Each anniversary of the date on which the facility
         received a permit

              Cost estimates must be adjusted annually by this
         date using the inflation factor calculated in accordance
         with 40 CFR §§264.142 and 264.144.

    •    60 days before the date on  which hazardous waste is first
         received for treatment, storage or disposal.

              By this date the first payment must be deposited
         into the trust fund.  The amount of the first payment may
         be calculated using the formula:

                            ACE-CV
         where ACE equals the adjusted closure cost estimate
         or the adjusted post-closure cost estimate or both; CV
         equals the current value of the trust fund (the value of
         CV would be zero before this first payment was made), and
         Y equals the number of years in the term of the initial
         RCRA permit.

         End of the month coincident with or preceding the
         anniversary date of the first establishment of (and
         payment into) the fund
                                   2-14

-------
              The trustee must furnish to the grantor and the
         appropriate EPA Regional Administrator(s)  a statement
         confirming the value of the fund.

    •    No later than 30 days after the anniversary date of  the
         first payment into the trust fund

              By this date the second payment must  be deposited
         into the trust fund.  The amount of the second payment
         may be calculated using the same formula as above except
         that Y would equal the number of years remaining in  the
         initial RCRA permit.

     Subsequent adjustments of cost estimates for inflation must  take

place annually over the operating life of the facility on the anniver-

sary of the date on which the facility received a permit.  Subsequent

statements confirming the value of the fund must be furnished by  the

trustee to the grantor and the appropriate Regional Administrators )

annually at the end of the month coincident with or preceding the anni-

versary date of the first establishment of the fund.  Subsequent

payments into the fund must take place annually over the term of  the

initial RCRA permit no later than 30 days after the anniversary date of

the first establishment of the fund.

    •    After the term of the initial RCRA permit

     Subsequent adjustments of cost estimates for inflation must  take

place annually on the anniversary of the date on which the facility

receives a new permit.  These adjustments must be made annually during

the operating life of the facility.  Subsequent valuations of the fund

must take place annually at the end of the month coincident with  or

preceding the anniversary date of the first establishment of  the  fund.

Subsequent payments into the fund must take place whenever the  value of

the fund is less than the amount of the new estimate.  The difference


                                   2-15

-------
must be deposited into the fund within 60 days of  the change  in the  cost



estimate.



     2.1.7.3  Payment into the Trust Fund —•  Facility Changes from

              Interim to General Status



     When a facility with interim status is granted a permit, the



facility begins operating with general status (see Section 1.5.4) and



must comply with general status standards. If a facility has a trust



fund, there are two significant differences in procedures:  (1) annual



adjustments of cost estimates to account for  inflation will become due



on the anniversary of the date of the permit  rather than May 19, and (2)



the number of years of the pay-in period will change from the remaining



operating life of the facility or 20 years, whichever is shorter, to the



number of years in the term of the initial RCRA permit.  A. sample calcu-



lation is provided in the Appendix.



     2.1.7.4  Payments into the Trust Fund — Variations Allowed



     Owners or operators may elect to make payments into the trust fund



at an accelerated rate, or to deposit the full amount of the cost



estimates at the time the fund is established.  The owner or operator,



however, must still adjust cost estimates annually for the inflation



factor and to reflect changes in closure and  post-closure plans.  The



trustee must also still value the fund annually and provide a statement



to the grantor and appropriate EPA Regional Administrator(s) confirming



the value of the fund.  In order to determine whether a new payment  into


                                          APK—r*v
the trust fund is necessary, the formula    "•     should be
                                   2-16

-------
applied in the manner described in Sections 2.1.7.2,  2.1.7.3 and




2.1.7.4.




     2.1.7.5  Valuations of the Trust Fund




     The trustee's statement to the grantor and appropriate Regional




Administrator(s) confirming the value of the fund  should  detail  both  the




results of investment activity and the expenses levied against the fund.




According to Section 10 of the trust agreement, "securities in the Fund




will be valued at market value as of no more than  30  days prior  to the




date of the statement."  Examples of expenses that might  be levied




against the fund are given in Section 2.1.4.1.




     The owner or operator (grantor) may object to the trustee's invest-




ment activities, or to expenses levied against the fund,  in writing,




within 90 days of the date the statement is furnished to  him. Notwith-




standing any objections, the owner or operator is  obligated to make




required payments into the fund by the appointed date. The EPA




(beneficiary) may object to any of the trustee's activities at any time




with no time limitation.  If the trustee issues a  revised statement of




the fund's value to the owner or operator and the  appropriate EPA




Regional Administrator(s), the owner or operator may  apply for a refund




if the value of fund exceeds the required amount (see Section 2.1.9.1).




     2.1.8  Trustee Notice of Non-Payment




     The trustee is obligated to notify the owner  or  operator and the




appropriate EPA Regional Administrator(s), by certified mail, within  10




days following the expiration of the 30-day period after  the anniversary




of the establishment of the trust, if a required payment  has not been
                                   2-17

-------
received.  Upon receiving such notice, the Regional Administrator wil]

institute a compliance procedure if the value of the trust fund is less

than the amount required (see Section 1.6).

     2.1.9  Release of Funds from the Trust Fund

     Owners and operators may be permitted to have funds released from a

trust fund for several reasons which are described in the following five

sections of the manual.  If a Regional Administrator determines that an

owner's or operator's request for a release of funds is justified he

must authorize the trustee in writing, within 60 days of having received

the request, to release such funds.

     2.1.9.1  Release of Funds When Value of Trust Fund Exceeds Cost
              Estimates
     Regional Administrators may approve a release of funds if the

current value of the trust fund (according to the trustee's statement of

value) exceeds the total applicable cost estimates.  Such a situation

might occur if the owner or operator had made deposits higher than those

required by these regulations, inflation was lower than expected, or

investment earnings were significantly higher than expected.

     2.1.9.2  Release of Funds Due to the Provision of an Alternate
              Financial Assurance Mechanism
     The Regional Administrator may approve a release of funds from a

trust fund if the owner or operator substitutes another form of

acceptable financial assurance for closure or post-closure care (see

Sections 2.2 on RCRA Surety Bonds, 2.3 on RCRA Letters of Credit and 4.1

on State-required mechanisms).  Such release may not occur until after

the Regional Administrator has received proof that the alternative
                                    2-18

-------
financial assurance mechanism has been executed and is in force (see

Section 2.4., 1).

     2.1.9.3  Release of Funds As Reimbursement for Closure or Post-
              Closure Expenses

     After the beginning of final closure, the owner or operator may

request reimbursement for closure expenditures by submitting itemized

bills to the Regional Administrator.  Similarly, bills for post-closure

care may also be submitted for reimbursement.  Within 60 days of

receiving the bills, the Regional Administrator will instruct the

trustee to make reimbursements, if the expenditures are in accordance

with the closure or post-closure plan or are otherwise justifiable.

     The Regional Administrator will need to use his judgment in

assessing whether the expenditures are justifiable.  During closure, for

example, adverse weather conditions may create a need for unanticipated

remedial activities which were not included in the plan. Ordinarily, the

Regional Administrator will only release up to 80 percent of the closure

fund during the actual closure period.  The remaining 20 percent will be

held to ensure that some funds are available if closure is incomplete or

inadequate.  It will be returned when certification of satisfactory

closure has been received by the Regional Administrator (see Section

2.1.9.4)

     Assessing the validity of post-closure expenditures may be even

more difficult since the post-closure plan is only revised during the

operating life of the facility when it will be difficult to predict the

kinds of activities that will be needed in future years.  In addition,

the plan only has to account for routine post-closure monitoring and


                                   2-19

-------
maintenance activities and expected contingencies (e.g.,  adverse weather

conditions likely to occur over a 30-year period).   Thus,  there  probably

will not be enough money in the fund to cover the costs of extraordinary

events (e.g., liner failure, damages caused by unusually  severe  weather

conditions).

     When assessing the itemized bills, the Regional Administrator will

need to decide if any extra expenditures due to the costs  of  cleaning up

a contingency not accounted for by the plan or due  to an  accelerated

maintenance schedule, should be covered by the trust or whether  the

owner or operator should pay them himself.  If the  owner  or operator has

to cover these costs himself, the costs might place an undue  financial

burden on the owner or operator and lead him into bankruptcy. In this

case, the EPA would be left responsible for post-closure  care of the

facility.  If the Regional Administrator agrees to  reimbursement, there

is the possibility that the trust fund will run out of funds  before the

end of the post-closure period.

     2.1.9.4  Release of Funds Due to Release from the Requirement to
              Provide Financial Responsibility for  Closure or Post-
              Closure

     The Regional Administrator will notify the owner or  operator within

60 days after receiving acceptable certifications (from the owner or

operator and an independent registered professional engineer) that he is

no longer required to maintain financial assurance  for closure if the

Regional Administrator is convinced that closure has been accomplished

in accordance with the closure plan.
                                   2-20

-------
     At the end of the post-closure period the owner or operator may

request a release from the requirement to provide financial assurance

for post-closure care.  If any assets remain in a trust at the end of

the post-closure period, the Regional Administrator may authorize their

release after the trustee has levied final administrative expenses.

     2.1.9.5  Release of Funds After Change in Facility Owner or
              Operator

     If the owner or operator sells the facility for which the trust

fund provides financial assurance, the trust fund will not transfer  to

the next owner or operator.  Instead, the new owner or operator will

have to provide new financial assurance for the facility.

     The Agency will not allow a trustee to release funds from a trust

fund to an owner or operator because the ownership or operation of the

facility has been sold or transferred until the new owner or operator

meets the applicable financial responsibility requirements and is

granted interim status or a permit.

     2.1.10  Changes of Trustees

     The trustee of a trust has a legal interest in the property in  the

trust because he has control over it, can sue to protect it, and is

responsible for its preservation.  Unless the trust instrument specifi-

cally identifies an individual as trustee, however, the trust exists

independently of the trustee.  A change from one trustee to another  will

not affect the existence of the trust itself.

     2.1.10.1  Why Trustee Is Changed

     The owner or operator must change the trustee if the trustee insti-

tution fails to meet the requirements of the regulations (see Section


                                   2-21

-------
2.1.3 for qualifications of trustee institutions).   If an owner or




operator is dissatisfied with the performance  of  his  chosen  trustee,  he




may change to another eligible trustee.  Finally, the trustee  may




resign.




     2.1.10.2  How Trustee is Changed




     Upon written agreement of the owner or operator, the trustee and




the appropriate Regional Administrator(s),  the trustee may resign or  the




owner or operator may appoint a successor trustee.   If the owner or




operator cannot or does not appoint another trustee when the present




trustee wishes to resign, the present trustee  will  request a court of




competent jurisdiction to appoint a successor. The present  trustee




remains responsible,  however, until he has been replaced. The name of




the successor trustee and the date on which he takes  over administration




of the trust must be  sent to the appropriate Regional Administrator(s),




the owner or operator and the former trustee 20 days  before  the change




becomes effective.




     2.1.11  Standby  Trust Fund




     By the time a letter of credit or a surety bond is obtained, the




owner or operator is  also required to set up a standby trust fund. An




originally signed duplicate of the trust agreement  must be sent to the




appropriate Regional  Administrator with the letter  of credit or surety




bond.




     Any funds collected from a surety company or drawn from a letter of




credit must be placed directly into the accompanying standby trust fund




by the surety or institution making the payment.   Without such a deposi-
                                   2-22

-------
tory mechanism, funds payable to a Regional Administrator would have to




be deposited directly into the United States Treasury and could not  be




used specifically to pay for closure or post-closure care of a hazardous




waste management facility (see 31 U.S.C §484).




     EPA plans to seek authority from Congress  to directly receive and




disburse funds derived from financial assurance mechanisms under RCRA.




If EPA obtains that authority, owners and operators would no longer be




required to establish standby trust funds.




     A standby trust fund is essentially the same as the trust fund used




as a primary financial mechanism.  However, after a nominal payment  is




agreed upon by the owner or operator and the trustee and paid into the




fund as specified in the trust fund requirement, further payments into




the trust fund are not required until the trust fund is funded by the




owner or operator, a surety company, or an institution issuing a letter




of credit.




     The owner or operator is obligated to fund the standby trust fund




if it is accompanying a financial guarantee bond (see Section




2.2.2.1).  The owner or operator may choose to  partially fund the stand-




by trust fund in order to increase his amount of financial assurance




coverage when using a surety bond or letter of  credit (see Sections




2.2.6.1 and 2.3.6.1).




     A surety company will fund the standby trust fund when it becomes




liable for the actions of the owner or operator (see Section 2.2.9).




     An institution issuing a letter of credit  will fund the standby




trust fund when the Regional Administrator draws on the letter of credit




(see Section 2.3.9).



                                   2-23

-------
     When financial assurance mechanisms are combined to provide assur-

ance of financial responsibility (see Section 2.4.2), only one  trust

fund or standby trust fund is required.  A letter of credit or  surety

bond combined with a trust fund need not be accompanied  by a separate

standby trust fund.  If a surety bond and letter of credit are  combined,

only one accompanying standby trust need be provided.

     2.1.12  Liability of Trustee

     The trustee is responsible for errors in the administration of the

trust that are the result of not acting in good faith.  This includes

errors made through willful negligence or gross misconduct and

violations of the "prudent man" standard for investment.

2.2  Surety Bonds

     2.2.1  What is a Surety Bond?

     A surety bond is a contract of suretyship, typically involving the

assumption of liability by one party, the surety, for the obligation of

another party, the principal or obligor, to a third party, the  obligee

or beneficiary.  In a surety bond, the surety states the conditions

under which it agrees to protect the obligee against the default of the

principal.  The surety bond also contains a "penal sum"  which represents

the extent of the surety's liability in monetary terms.

     Surety bonds can be written for many different purposes:

    •    Fidelity bonds insure against losses caused by the
         dishonesty of employees.

    •    Contract bonds secure the performance of contractual
         obligations.

    •    Court bonds secure the performance of a litigant, in
         advance of a final decision by a court in order to
         protect the opposing litigant from loss.

                                    2-24

-------
    •    License and permit bonds secure that the performance of
         licensees (liquor store owners, auctioneers,  etc.) will
         be in conformity with obligations under the license or
         permit.

     2.2.2  RCRA Surety Bonds

     An owner or operator may use a Financial Guarantee Bond for Closure

and a Financial Guarantee Bond for Post-Closure to satisfy the interim

status financial responsibility requirements.  During general status an

owner or operator has the option of using both the Financial Guarantee

Bonds and the Performance Bonds to satisfy the financial responsiblity

requirements for closure and post-closure.

     In the RCRA surety bonds, the owner or operator would be the

principal and the EPA would be the obligee.  Table 2-3 shows the

location of the regulations applicable to surety bonds and the bond

forms.
     Since surety bonds guarantee the performance of statutory or con-

tractual obligations, the responsibilities or obligations of the

respective parties (surety, principal, and obligee) must be clearly

defined in the underlying contract or in the relevant  statute.  The

obligations and provisions of financial guarantee bonds are clearly

specified in the regulations; the bases for the performance bond

contract are the closure and post-closure plans.

     During interim status, the Regional Administrator will normally not

review an owner's or operator's plans until 180 days before final

closure is scheduled to begin.  The terms of the underlying contracts

for performance bonds are based on plans which could change

significantly when the plans are reviewed.  Since major changes in

performance requirements could be used as a defense against liabilities

                                   2-25

-------
                               TABLE 2-3

                        SURETY BOND REGULATIONS
      SUBJECT OF
      REGULATION
             SECTION OF REGULATION

  INTERIM STATUS        GENERAL STATUS
Closure Bond
  Financial Guarantee Bond
  Performance Bond

Post-Closure Bond
  Financial Guarantee Bond
  Performance Bond

Bond Form
  Financial Guarantee Bond
    Closure
    Post-Closure
  Performance Bond
    Closure
    Post-Closure
40 CFR §265.143(b)
        NA
40 CFR §265.145(b)
        NA
40 CFR §265.151(b)
40 CFR §265.151(c)

        NA
        NA
40 CFR §264.143(b)
40 CFR §264.143(c)
40 CFR §264.145(b)
40 CFR §264.145(c)
40 CFR §264.151(b)
40 CFR §264.151(d)

40 CFR §264.151(c)
40 CFR §264.151(e)
NA:  Not Applicable

For the text of these regulations see 46 Federal Register pp.  2851  et
seq. (January 12, 1981).


for the surety, performance bonds are not allowed during interim

status.  Performance bonds will be allowed for facilities operating with

general status, because the plan will be evaluated and approved as  a

condition of the permit.

     EPA's bonds contain a provision for an optional rider allowing the

surety company and the owner or operator to automatically adjust the

penal sum of the bond (see Section 2.2.1).  Another unique feature  of

EPA's surety bonds is that they must be accompanied by a standby trust

fund as discussed in Section 2.1.11.
                                    2-26

-------
     2.2.2.1  Financial Guarantee Bonds




     The Financial Guarantee Bond for Closure and  the Financial




Guarantee Bond for Post-Closure are designed  to  ensure that  at least  60




days before the expected date of final closure of  a facility the owner




or operator will place the amount of money guaranteed by  the bonds  in a




standby trust fund (see Section 2.1.11 for a  discussion of  the standby




trust fund).  The bonds also ensure that the  owner or operator will




place the amount of money guaranteed by the bonds  in the  standby trust




fund within 15 days after an order to begin closure has been issued by




the Regional Administrator or a court, or within 15 days  after a termin-




ation notice of the permit has been issued.  If  the owner or operator




defaults on these obligations, the surety company  will be responsible




for placing an amount equal to the penal sum  of  the bond  into the stand-




by trust fund.




     2.2.2.2  Performance Bonds




     The Performance Bonds for Closure and Post-Closure are both




designed to ensure that the owner or operator will perform  in accordance




with the closure or post—closure plans and other permit requirements.




The bonds also obligate the owner or operator to perform  final closure




or post-closure even though closure may occur sooner than expected, or




the requirements in the plans or permit (or both)  may change.  If the




owner or operator defaults, the surety must either perform  in accordance




with the plans and permit requirements or deposit  the penal sum  into  the




standby trust fund.
                                    2-27

-------
     2.2.3  Qualifications of Issuing Corporate Surety




     The Department of the Treasury decides which corporate sureties




meet necessary legal and financial requirements to write bonds  when the




United States (or one of its agencies or departments) is the obligee.




Qualified sureties are listed in the Department of the Treasury's




Circular 570 which is published annually as of July 1 in the Federal




Register.  Circular 570 can be ordered from the Department of the




Treasury at any time, but orders for over 10 copies should be submitted




prior to June 1.  Interim changes to Circular 570 are also published in




the Federal Register and issued separately as supplements.  Whenever




there is doubt as to whether a surety not listed in Circular 570 or in




supplements is qualified to write RCRA bonds, the Audit Staff of the




Department of the Treasury may be contacted at (202) 634-5010.




     The Department of the Treasury does not allow qualified sureties  to




underwrite a single risk greater than 10 percent of the paid-up capital




and surplus of the surety company.  This amount, called the underwriting




limitation, is included as Note b in Circular 570 after the name and




address of the surety.  Surety companies may exceed their underwriting




limitations as long as the risk is shared using coinsurance or




reinsurance.  When two or more sureties (i.e., cosureties) are  listed  on




a bond, the penal sum of the bond may not exceed the aggregate




underwriting limitations for all of the sureties listed.  If one surety




is listed on a bond and the penal sum of the bond exceeds the under-




writing limitation listed in Circular 570, the surety must submit a




Reinsurance Agreement in Favor of the United States to EPA with the




bond.



                                   2-28

-------
     Circular 570 (Note c) also lists the States in which surety




companies are licensed.  A surety company must be licensed in the State




where it executes a bond.




     A surety bond will no longer be considered assurance of financial




responsibility if the surety company is removed from the Department of




the Treasury's Circular 570.  The owner or operator is required to




establish another financial mechanism within 60 days of the removal of




the surety from the list.  However, if the surety has been removed from




the list due to a merger, the owner or operator must  inform the




Regional Administrator of the merger within 60 days.  A new bond need




not be executed as long as the new surety will be listed in Circular 570




and meets the other requirements already mentioned.




     The Department of the Treasury keeps track of the financial




position of sureties listed in Circular 570 and provides updated infor-




mation to federal departments and agencies.  When the Treasury staff




notices that a particular surety has a quickly deteriorating financial




position, they send a notice to federal departments and agencies to use




discretion in approving bonds issued by that particular surety.




     2.2.4  Initially Executing the Surety Bond




     2.2.4.1  Information for the Owner or Operator




     Financial guarantee bonds and performance bonds may be considered




"hazardous" (risky) by the surety industry.  This is likely to affect




the premiums charged for these bonds, the number of brokers or agents




with the authority to execute these bonds, the underwriting information




required by the surety company from the owner or operator, and the
                                   2-29

-------
amount and types of collateral security required from some owners and




operators.




     Surety companies charge the principal premiums as compensation to




the surety company for the use of its name and credit as surety.  The




Surety Association of America (SAA) will include in their rate manual a




premium rate or possibly a scale of rates based on their evaluation of




the risks and administrative burdens involved in underwriting these




bonds.  Sureties may charge different rates to their customers based on




the size of the bond penalty amount; for example, the higher the bond




penalty amount, the lower might be the percentage that the premium would




be of the bond penalty amount.




     Since few sureties have had experience with the bonding of




hazardous waste management facilities, EPA believes availability of




these bonds may be limited at first.  There may be a limited number of




brokers or agents with the authority to execute these bonds since




special expertise may be required.  Surety companies provide their




authorized brokers or agents with a power of attorney, a written




document stating that the named broker or agent is allowed to act on




behalf of the surety company.  Since power of attorney forms may contain




limitations, owners or operators should check to be sure that the broker




or agent with whom they are dealing has the authority to underwrite




these bonds.  They should make certain that bonds written on behalf of




the EPA are not excluded, that the relevant types of bonds are not




excluded (e.g. all financial guarantee or performance bonds), and that




the required penal sum of the bond is not above an agent's monetary




limit.



                                   2-30

-------
     Before an agent or broker executes a surety bond,  he will gather

underwriting information to be presented to the surety  company to  deter-

mine if the owner or operator will be able to meet the  obligations

guaranteed by the bond.  Certain factors which surety companies can be

expected to consider in their decision process are:

    •    The financial condition of the owner or operator, based
         on financial statements.

    •    The accuracy of financial statements presented to the
         surety.

    •    The inherent risks associated with the hazardous waste
         management facility .(e.g., type of facility, type of
         waste, location of facility, etc.).

    •    The expected risks and profits associated with the future
         operation of the facility.

    •    The quality of the management of the facility  as well as
         the qualifications of key personnel.

    •    The past operating experience of the facility.

     Surety companies may underwrite bonds for certain  owners and

operators who otherwise would not qualify for a bond if collateral

security is deposited with the surety company by the owner or

operator.  Surety companies are likely to prefer highly liquid forms of

collateral such as certificates of deposit or Treasury  Bills.

Collateral arrangements would be defined in a collateral agreement

between the surety company and the owner or operator.  Owners or

operators who are not required by the surety to deposit collateral

security with the surety company might elect to do so for the purpose of

receiving a premium discount.
                                   2-31

-------
     The owner or operator and the surety should note that when

executing the surety bond, they will both be held responsible for making

sure that the wording of the surety bond is identical to the wording

required by the regulations.

     2.2.4.2  Information for the Regional Administrator

     The EPA Regional Administrator must make sure that surety bonds

accepted as assurance of financial responsibility conform both to the

Treasury's regulations for bonds given to the United States and to EPA's

regulation governing bonds which are acceptable for this purpose.  Title

6 of the U.S. Code, §§6-13, authorizes the acceptance of corporate

surety companies on bonds given to the United States.  The Department of

the Treasury Circular 297 contains the Treasury regulations governing

surety companies doing business with the United States.

     All surety bonds submitted to EPA must:

    •    Be delivered to the Regional Administrator either in
         person or by certified mail.

    •    Be received by the Regional Administrator by the
         effective date of the interim status regulations (July
         13, 1981) for existing facilities.  For new facilities
         the surety bond must be received 60 days before the date
         on which hazardous waste is first received for treatment,
         storage, or disposal.

    •    Be effective by the effective date of the interim status
         regulations (July 13, 1981) for existing facilities.  It
         must be effective before the initial receipt of hazardous
         waste for facilities operating with general status.

    •    Have wording identical to the wording specified in the
         regulations.

    •    Be accompanied by an originally signed duplicate of a
         standby trust fund (see Section 2.1.11).
                                     2-32

-------
    •    Have a penal sum equal, at a minimum, to the cost
         estimates if the bond is the only mechanism providing
         assurance (see Section 2.2.5 for bonds covering more than
         one facility and Section 2.4.3 for bonds combined with
         other mechanisms to provide assurance).

     The Regional Administrator must also check that:

    •    The surety has not exceeded its underwriting limitation
         specified in Circular 570 (see Section 2.2.3).

    •    The power of attorney for the individual signing for the
         surety is sufficient (see Section 2.2.4.1).

    •    The signature for a corporate, partner or individual
         principal is sufficient.

     If the corporate principal is a division of another corporation, an

officer (or attorney in fact) of the parent corporation must sign for

the principal. The power of attorney for the attorney in fact should be

attached to the bond (se« Section 2.2.4.1 where the purpose of a power

of attorney is described).

     If the principal is a partnership, one partner can sign as long as

words indicating that he is signing for the partnership are inserted

(e.g., "For the Partnership" or "For the TSD Company").  Persons other

than partners must have a power of attorney to sign for a partner.

     If the principal is an individual he should sign as "owner" or

"operator."  Persons other than the "owner" or "operator" must have a

power of attorney to sign for an "owner or operator."

     2.2.4.3  EPA Care of Bond

     Once a bond is accepted as assurance of financial responsibility

for closure or post-closure, by the Regional Administrator, at least one

copy should be made of the bond and all attachments.  The original bond

and attachments should be kept in a fire-safe location.


                                   2-33

-------
     2.2.5  Multiple Facilities on One Bond




     An owner or operator may use one surety bond to provide assurance




of financial responsibility for more than one facility (see  Section




2.4.3).




     2.2.6  Changes in Coverage of the Surety Bond




     The penal sum of the surety bond must at least equal  the amount  of




the most recent cost estimate for the facility and activity  (i.e.




closure or post-closure) for which the bond is providing financial




assurance, except in cases where the bond is combined with another




mechanism (see Section 2.4.2).  If the adjusted cost estimate exceeds




the penal sum of the bond during the operating life of the facility,  the




owner or operator must either increase the penal sum of the  bond to an




amount equal to the new estimate or combine the bond with  another  form




of financial assurance to cover the total costs.  Regardless of  changes




in costs, a surety bond does not have to be increased once a facility




has been closed.



     If the most recent estimate decreases during the operating  life  of




the facility, the owner or operator may reduce the penal sum of  the bond




to the level of the current estimate following approval by the Regional




Administrator.




     2.2.6.1  Increasing the Amount of the Bond




     A bond that includes an optional rider allows the owner or  operator




and the surety to automatically adjust the penal sum of the  bond




upwards.  However, since the rider specifies that upward adjustments




will not be more than 20 percent of the penal sum of the bond, the
                                    2-34

-------
surety does not have to automatically agree to upwards adjustments in




excess of 20 percent.




     Owners and operators with a bond that does not include a rider




allowing an adjustment of the penal sum have several options.  They may




execute a new agreement with the surety providing for an increased penal




sum.  They may deposit the difference between the new cost estimate and




the penal sum of the bond into the standby trust fund which accompanies




a surety bond (see Section 2.1.11).  They also may obtain a letter of




credit in the amount of the difference between the new cost estimate and




the penal sum of a financial guarantee bond.




     Regardless of the option chosen, the owner or operator must




increase the amount of financial assurance to the required level within




60 days of the change in the cost estimate.  Notice of the change must




be delivered to the Regional Administrator in person or by certified




mail within 60 days after the change has been made.




     2.2.6.2  Decreasing the Amount of the Bond




     An owner or operator must apply to the Regional Administrator for




any decrease in bond coverage.  During interim status, the Regional



Administrator would likely request the closure or post-closure plans and




any other operating information about the facility necessary to decide




whether the request would be justified.  A Regional Administrator could




normally make this determination and notify the owner or operator within




60 days of the application for decreased bond coverage.  The Regional




Administrator's written approval would then be sent to the owner or




operator and the surety company.  Once the penal sum of the bond was
                                   2-35

-------
decreased by the surety, the owner or operator would have to notify the




Regional Administrator of the change by certified mail within 60 days.




     The Regional Administrator should seldom allow the amount of a




Performance Bond for Post-Closure to decrease after a facility has




ceased operation.  Future rates of inflation cannot be predicted with




any degree of accuracy.  But even assuming a constant inflation rate of




8%, and equal annual expenditures for post-closure care, the amount of a




Performance Bond for Post-Closure would be insufficient to carry out




post-closure activities until the 17th year of post-closure.




     2.2.7  Cancellation of a Surety Bond by the Owner or Operator




     An owner or operator must request permission from the Regional




Administrator to cancel a surety bond.  If the bond guarantees




facilities in more than one Region,  the owner or operator must request




the permission of all of the Regional Administrators.  Regional Adminis-




trators will give their written consent for cancellation to the owner or




operator if the owner or operator has been released from the relevant




financial responsibility requirements (see Section 2.2.7.3).  Permission




for cancellation may also be given by the Regional Administrators if the




owner or operator successfully demonstrates that he has substituted an




alternate form of assurance of financial responsibility for the bond




(see Section 2.4.1).




     2.2.7.1  Change in the Status of the Issuing Corporate Surety




     If the surety company listed on a bond is removed from Circular




570, the bond will no longer provide acceptable assurance of financial




responsibility (see Section 2.2.3).   The owner or operator must change
                                   2-36

-------
mechanisms as provided in Section 2.4.1.  Once alternate financial

assurance is obtained the original surety bond may be cancelled by the

owner or operator.

     2.2.7.2  Cancellation of the Surety Bond Due to Changes in Facility
              Ownership or Operation

     If the ownership or operation of a facility has been transferred,

the Regional Administrator may not allow the surety bond providing

assurance for that facility to be cancelled until the new owner or

operator meets the applicable financial responsibility requirements and

has been granted either interim status or a permit.

     2.2.7.3  Cancellation of the Surety Bond Due to the Release of the
              Owner or Operator from the  Requirement to Provide
              Financial Responsibility for Closure or Post-
              Closure Care

     The Regional Administrator will notify the owner or operator within

60 days after receiving acceptable certifications (from the owner or

operator and an independent registered professional engineer)  that he is

no longer required to maintain financial assurance for closure if the

Regional Administrator is convinced that closure has been accomplished

in accordance with closure plan.

     At the end of the post-closure period the owner or operator may

request a release from the requirement to provide financial assurance

for post-closure care.  The Regional Administrator may approve cancel-

lation of the surety bond at the end of the post-closure period.

     If assurance of financial responsibility is no longer necessary for

a facility guaranteed by a surety bond, the Regional Administrator will

return the original bond to the issuring surety company with a copy of

the letter to the owner or operator informing him of his release from

this requirement.
                                   2-37

-------
     2.2.8  Cancellation of a Surety Bond by the Surety Company




     Because surety companies choosing to underwrite the bonds might be




undertaking very long-term obligations, the bonds contain a provision




allowing them to be cancelled by the surety company.  The surety company




can exercise this option by sending a notice of its intention to cancel




by certified mail to the owner or operator and to the Regional Adminis-




trator.  Cancellation cannot become effective until 90 days after the




date on the Regional Administrator's signed receipt for the notice of




cancellation.  A surety can also not cancel a bond while a compliance




procedure as defined in 40 CFR §§264.141 or 265.141 is pending (see




Section 1.6).




     Regardless of whether a violation which led to a compliance order




could have any impact on the ability of the owner or operator to perform




closure or post-closure care, the surety bond will have to remain in




full force and effect.  This is essential because a violation or a




series of violations completely unrelated to closure or post-closure




care could cause the Regional Administrator either to revoke interim




status or a permit.  Closure might then be ordered for the facility,




making assurance of financial responsibility for closure or post-closure




care a necessity.  Serious violations might also result in large expen-




ditures which would force the owner or operator to close the facility




earlier than anticipated or in the worst case, actually lead to




bankruptcy.




     A compliance procedure will be automatically instituted as soon as




the Regional Administrator receives notice of the surety company's
                                   2-38

-------
intention to cancel a bond.  The owner or operator is allowed 30 days




from the notice to demonstrate to the Regional Administrator alternative




financial assurance as specified in the regulations. When the Regional




Administrator receives notice that an the alternative mechanism has been




provided, he will then notify the surety company that the bond cancel-




lation will become effective at the end of the 90-day period.




     If the owner or operator is unable to provide assurance of




financial responsibility acceptable to the Regional Administrator within




30 days, EPA will inform the surety company of its obligation to either




place the penal sum of the bond in the standby trust fund if it is a




Financial Guarantee Bond for Closure or Post-Closure, or place the penal




sum of the bond in the standby trust fund or begin performance of




closure or post-closure care if it is a Performance Bond for Closure or




Post-Closure Care.




     2.2.9  Liability of the Surety Company




     If the owner or operator fails to perform as guaranteed by the




bonds, the surety will be liable (see Sections 2.2.2.1 and 2.2.2.2).




Therefore, the Regional Administrator may direct the surety to place the




penal sum of the bond in the standby trust fund or with a performance




bond, allow the surety to perform closure or post-closure care after a




determination that the owner or operator has failed to fulfill all of




the conditions of the bond.  If the Regional Administrator allows the




surety to perform closure or post-closure, the surety will have to




perform according to the requirements of the permit, plans or other




regulations issued under the authority of RCRA.  If a surety is to
                                   2-39

-------
deposit the penal sum into a trust fund, the Regional Administrator




should notify the trustee at least two weeks in advance of  the  trans-




action, if possible.




     If the surety either fails to deposit the penal sum in a trust fund




or is not performing closure or post-closure in accordance  with the




regulation the Regional Administrator will need to issue a  claim against




the surety.  In order to make a claim against a surety company  the




Regional Office should send a "demand letter" to the surety's Federal




process agent in the federal court district where the facility  in




question is located.  A "demand letter" should be a registered  letter




explaining the demand for payment into the standby trust fund and




including a specific period of time during which the surety company is




expected to respond to the demand.




     Federal process agents, who have power of attorney to  process these




claims, are appointed by surety companies in each judicial  district




where they will undertaken suretyship.  The name and address of the




process agent for a particular surety may be obtained from  the  clerk of




the U.S district court for the district in question.  If the Regional




Administrator is informed that the appointment of a process agent for




the surety is pending or that the agent is absent from the  district, the




"demand letter" may be served upon the clerk of the court.   This should




only be done when there is no process agent for the surety  present in




the district.




     If the Regional Administrator's demand for payment of  a claim is




not settled to his satisfaction, he should send a report to the
                                   2-40

-------
Secretary of the Treasury including a copy of the subject bond,  the




basis for the claim against the company, a chronological resume  of




efforts to obtain payment, a statement of all reasons offered by the




surety for nonpayment and a statement of the agency's views on the




matter.




     The Secretary of the Treasury may revoke a. surety company's certif-




icate of authority to appear on bonds given to the United States if the




Regional Administrator's complaints are found to be justified.




     2.3  Letters of Credit




     2.3.1  What is a Letter of Credit?




     A letter of credit is an instrument by which the credit of  one




party, whose financial standing is considered more desirable than that




of a second party, is extended on behalf of the second party to a third




party.  These three parties to a letter of credit are the account party,




or customer, who is the applicant requesting the issuance of a letter of




credit; the issuer, who is the entity undertaking the obligation of the




account party; and the beneficiary, who is the party in whose favor the




credit is issued.  The issuer, on behalf of its customer, allows the




beneficiary to draw funds from the issuer upon the presentation of




papers or documents in accordance with the terms of the letter of




credit.



     The best-known type of letter of credit is the documentary letter




of credit, used principally to finance shipments of merchandise.  It




normally requires the beneficiary of the letter to present documents




generated by the shipment and underlying transaction (e.g., bills of
                                    2-41

-------
lading, invoices, insurance certificates) before obtaining payment.  It




supports the contract setting up the underlying transaction,  and is used




to ensure payment if actions required by that contract are carried out.




     Another type of letter of credit is the standby letter of credit




(also called the guaranty or special purpose letter of credit).  It




creates an obligation on the part of the issuer to the beneficiary to




pay money to the beneficiary if the account party fails to perform a




specified obligation.  The standby letter of credit is classified as




"clean" credit because shipping or commercial documents are not required




to obtain payment.




     Letters of credit may be either revocable or irrevocable




instruments.  Revocable credit operates as a payment arrangement which




can be terminated at the option of the issuer or account party without




the consent of the beneficiary.  It thus does not provide a financial




guarantee to the beneficiary.  The terms of an irrevocable letter of




credit can only be amended by the agreement of all parties to the




credit.




     2.3.2  RGRA Letters of Credit




     An owner or operator may satisfy the financial responsibility




requirement for closure and post-closure care by obtaining an




irrevocable standby letter of credit, which guarantees the availability




of sufficient funds to cover the costs of closure or post-closure or




their combined costs.  For the purposes of these regulations  the owner




or operator will be the account party, the bank or financial  institution




will be the issuer, and the EPA, through its Regional Administrators,
                                   2-42

-------
will be the beneficiary.  The letter of credit must be irrevocable for

an initial period of at least one year and must provide for automatic

extensions of the same period.  Table 2-4 shows the location of the

regulations applicable to letters of credit and the letter of credit

form.

     The letter of credit is designed to ensure that funds are available

to cover the costs of closure and post-closure.  The risk that the

account party (i.e., the owner or operator) will fail to pay the costs

of closure and post-closure is assumed by the issuer, who is responsible

up to the full amount of the credit upon presentation of the documents

specified in the terms of the credit.

                                TABLE 2-4

                      LETTER OF CREDIT REGULATIONS
SUBJECT OF
REGULATION
Closure
Letter of Credit
Post -Closure
Letter of Credit
Letter of Credit
Form
SECTION OF REGULATION
INTERIM STATUS GENERAL STATUS
40 CFR §265.143(c)
40 CFR §265.145 (c)
40 CFR §265.151 (d)
40 CFR §264.143(d)
40 CFR §264. 145(d)
40 CFR §264.151(f)
For the text of these Regulations see 46 Federal Register pp. 2851 et
seq. (January 12, 1981).
     A unique feature of EPA's letters of credit is that they must be

accompanied by a standby trust fund.  All amounts paid by the issuing

institution must be deposited into this standby trust fund.  The reason

for this requirement is discussed in Section 2.1.11.

                                   2-43

-------
     2.3.3  Qualifications of Issuing Institution




     The regulations require that the. issuing institution must be a bank




or other financial institution which has the authority to issue letters




of credit and whose letter of credit operations are regulated and




examined by a Federal or State agency.




     All domestic bank and savings and loan letter of credit departments




are regulated and examined.  The Regional Administrator can confirm that




a financial institution has the authority to issue a letter of credit by




contacting the regulatory authority.  Table 2-2 shows the regulatory




authority primarily responsible for each type of financial institution.




     Some American branches of foreign banks are regulated and examined




by the Federal Deposit Insurance Corporation (FDIC) which can certify




whether the bank in question has the authority to issue letters of




credit.  Other foreign banks with American branches should be able to




specify which regulatory authority could attest to their authority.




     A letter of credit will no longer be considered assurance of finan-




cial responsibility for the closure or post-closure care of a hazardous




waste management facility if the issuer becomes insolvent, bankrupt, or




its license or charter is suspended or revoked, or if it no longer meets




the requirements for qualified institutions.




     2.3.4  Initially Executing the Letter of Credit




     2.3.4.1  Information for the Owner or Operator




     Irrevocable standby letters of credit will be treated by banks and




other financial institutions as credit commitments.  An owner or




operator will be required to prepare and sign a credit application, as
                                   2-44

-------
required by the institution, and to sign a consent to the terms of the




agreement.  The financial institution will decide whether to assume the




credit risk on behalf of the owner or operator on the basis of the




information provided and its own credit review, which will be equivalent




to that applicable to a potential borrower in an ordinary loan.




     The terms of the agreement between the owner or operator and the




bank or other financial institution will vary according to the insti-




tution's assessment of the risk it is assuming.  The bank will therefore




look carefully at the reason for the letter of credit, the ability of




the owner or operator to perform, and the owner's or operator's credit




responsibility for the full term of the credit.




     Because letters of credit count against the legal loan limits of a




bank, even if no payout of funds occurs, certain financial institutions




may be unable or unwilling to issue them.  In such situations, a local




bank may be able to arrange for a letter of credit to be issued by one




of its larger correspondent banks (a bank which transacts business, such




as borrowing or loaning money, with another bank).




     The fee for the letter of credit may be negotiable, depending on




the business history of the parties and particularly on the collateral




required to secure the credit.  Most banks will probably require the




same types of collateral as for a direct loan.  Collateral may be




required up to a value of 100 percent of the letter of credit.  Banks




may provide letters of credit for certain owners or operators who other-




wise would not qualify, if collateral is deposited with the bank.
                                   2-45

-------
     The owner or operator and the issuer should note that they will

both be held responsible for ensuring that the wording of the letter of

credit is identical to that required by the regulations.  The form

should be certified by the issuer and placed on the letterhead of the

bank or other financial institution issuing the letter of credit.

     The contract between the owner or operator and the issuer will

normally require the owner or operator to reimburse the issuer for

amounts paid out by the issuer pursuant to the terms of the letter of

credit.

     2.3.4.2  Information for the Regional Administrator

     The Regional Administrator must ascertain that owners or operators

who use letters of credit as evidence of financial assurance have

complied with the following:

    •    The owner or operator must deliver the letter of credit
         to the Regional Administrator either in person or by
         certified mail by the effective date of the Interim
         Status regulations for existing facilities.  For new
         facilities, the letter of credit must be delivered at
         least 60 days before the date on which hazardous waste is
         first received for treatment, storage or disposal.

    •    The letter of credit must be effective by the effective
         date of the interim status regulations (July 13, 1981)
         for existing facilities.  It must be effective before the
         initial receipt of hazardous waste for facilities
         operating with general status.

    •    The wording of the letter of credit must be identical to
         the wording specified in the regulations (see Table 2-4).

    •    An originally signed duplicate of the standby trust
         agreement must be delivered to the Regional Administrator
         with the letter of credit.

    •    The face value of the letter of credit must equal at a
         minimum equal the cost estimates if the letter of credit
         is the only mechanism providing assurance (see Section
         2.3.5 for letters of credit covering more than one
         facility and 2.4.3 for letters of credit combining with
         other mechanisms).

                                   2-46

-------
     The Regional Administrator should contact the bank or other finan-




cial institution which issued the letter of credit if questions  arise




about the term of the credit.




     2.3.4.3  EPA Care of Letters of Credit




     It is highly recommended that the Regional Administrator keep the




original letter of credit in a fire-safe location.  The Regional Admin-




istrator should also set up a system of record-keeping to account for




all letters of credit in his custody.




     Because under General Status letters of credit will expire  at many




different times, such record-keeping should include a "tickler"  file for




alerting the Regional Administrator to impending expirations.




     2.3.5  Multiple Facilities on One Letter of Credit




     An owner or operator may use one letter of credit to assure funds




for multiple facilities only if they are all located in the same EPA-




Region (see Section 2.4.3).




     2.3.6  Changes in Coverage of the Letter of Credit




     The letter of credit must be issued for at least the amount of the




most recent cost estimate for the facility and the activities (i.e.,




closure or post-closure) for which the letter of credit is providing




financial assurance, unless the letter of credit is combined with




another mechanism (see Section 2.4.2).  If the adjusted cost estimate




exceeds the guaranteed credit during the operating life of the facility,




the owner or operator must either increase the credit to an amount equal




to the new estimate or combine the letter of credit with another form of
                                   2-47

-------
financial assurance to cover the total costs.  Regardless of the changes




in costs, a letter of credit does not have to be increased once a




facility has been closed.




     If the most recent estimate decreases during the operating life of




the facility, the owner or operator, following approval by the Regional




Administrator, may reduce the amount of the letter of credit to the




level of the current estimate.




     2.3.6.1  Increasing the Coverage of the Letter of Credit




     Whenever the adjusted cost estimate of closure or post-closure, or




closure and post-closure combined (whichever is be assured by the letter




of credit), increases to an amount greater than the amount of the




credit, the owner or operator must, within 60 days of the increase,




cause the amount of the credit to be increased to an amount at least




equal to the new estimate.  Such an increase would be created by an




amendment to the letter of credit.  That amendment will require the




written approval of the issuer, the owner or operator, and the Regional




Administrator.  The amendment to the letter of credit must be delivered




to the Regional Administrator either in person or by certified mail




within 60 days of the increase.  Alternatively, the owner or operator




may obtain other financial assurance to cover the increase.




     2.3.6.2  Decreasing the Coverage of the Letter of Credit




     Whenever the adjusted cost estimate decreases,   the letter of




credit may be reduced to the amount of the new estimate following




written approval by the Regional Administrator.  After receiving written




approval, the owner or operator must obtain the issuer's agreement to
                                   2-48

-------
the decrease.  The owner or operator then must notify the Regional

Administrator by certified mail or by personal delivery within 60 days

of the decrease in the amount of the letter of credit.

     The Regional Administrator should seldom allow the amount of a

letter of credit for post-closure care to decrease after a facility has

ceased operation.  Future rates of inflation cannot be predicted with

any degree of accuracy.  But, even assuming a constant inflation rate of

8 percent, and equal annual expenditures for post-closure care, the

amount of a post-closure letter of credit would be insufficient to carry

out remaining post-closure activities until the 17th year of post-

closure.

     2.3.7  Cancellation of the Letter of Credit by the Owner or
            Operator

     An owner or operator must request permission from the Regional

Administrator to cancel a letter of credit.  The Regional Administrator

will give his written consent for cancellation to the owner or operator

if the owner or operator has been released from the relevant financial

responsibility requirements (see Section 2.3.7.3).  Permission for

cancellation may also be given by the Regional Administrator if the

owner or operator successfully demonstrates that he has substituted an

alternate form of assurance of financially responsibility for the letter

of credit (see Section 2.4.1).

     2.3.7.1  Cancellation of the Letter of Credit Due to Changes in the
              Status of the Issuing Institution

     If the bank or other financial institution which issued the letter

of credit fails to meet the qualifications discussed in Section 2.3.3
                                   2-49

-------
the letter of credit will no longer provide acceptable assurance of

financial responsibility.  The owner or operator must change mechanisms

as provided in Section 2,4.1.  Once alternate financial assurance is

obtained, the original letter of credit may be cancelled by the owner or

operator.

     2.3.7.2  Cancellation of the Letter of Credit Due to Changes in
              Facility Ownership or Operation

     If the ownership or operation of a facility has been transferred

the Regional Administrator may not allow the letter of credit providing

assurance for that1 facility to be cancelled until the new owner or

operator has met the applicable financial responsibility requirements

and has been granted either interim status or a permit.

     2.3.7.3  Cancellation of the Letter of Credit Due  to the Release  of
              the Owner  or Operator from the Requirement to Provide
              Financial  Responsibility for Closure or Post-Closure Care

     The Regional Administrator will notify the owner or operator within

60 days after receiving  acceptable certifications (from the owner or

operator and an independent registered professional engineer) that he is

no longer required to maintain financial assurance for closure if the

Regional Administrator is convinced tht closure has been accomplished in

accordance with the closure plan.

     At  the end of the post-closure period, the owner or operator may

request a release from the requirement to provide financial assurance

for post-closure care.   The Regional Administrator may  approve cancel-

lation of the letter of  credit at the end of the post-closure period.
                                    2-50

-------
     2.3.8  Cancellation of the Letter of Credit by the Issuing
            Institution

     Since institutions issuing letters of credit may be undertaking

very long-term obligations, the letters of credit contain provisions

which allow the issuers to refuse to extend the letters of credit beyond

the current expiration date (letters of credit must be irrevocable for a

period of at least one year).  If the issuer decides not to extend the

letter of credit, he must notify by certified mail both the owner or

operator and the Regional Administrator of his decision at least 90 days

before the current expiration date.  The letter of credit cannot be

terminated until 90 days after the date on the Regional Administrator's

signed return receipt of the notice of expiration of the letter of

credit.

     The letter of credit also may not be terminated while a compliance

procedure as defined in 40 CFR §264.141 or §265.141 is pending.

Although the violation itself may not involve the closure and post-

closure regulations, the letter of credit will have to remain in full

force and effect.  This is essential because a violation or a series of

violations completely unrelated to closure or post-closure care could

cause the Regional Administrator either to revoke interim status or a

permit.  Closure might then be ordered for the facility, making

assurance of financial responsibility for closure or post-closure care a

necessity.  Serious violations might also result in large expenditures

which could force the owner or operator to close the facility earlier

than anticipated or in the worst case, actually lead to bankruptcy.
                                   2-51

-------
     The Regional Administrator will automatically institute a




compliance procedure as soon as he receives notice of the. issuer's




intention to terminate the letter of credit,  unless the owner or




operator has already demonstrated alternate financial assurance.  The




owner or operator is then allowed 30 days to provide the Regional Admin-




istrator with substitute assurance of financial responsibility.   If the




Regional Administrator accepts the substitute assurance of financial




responsibility, he will then return the original letter of credit to the




issuing institution for termination.




     If the owner or operator fails to provide acceptable alternative




financial assurance within 30 days, the Regional Administrator may draw




on the letter of credit.  The issuing institution must then deposit the




total amount of the letter of credit into the standby trust fund.




     2.3.9  Responsibility of the Issuing Institution for Performance




     EPA expects the issuing institution to fulfill its obligation to




place the total amount of the letter of credit in the standby trust fund




whenever the Regional Administrator presents the draft and statement as




specified in the letter of credit.  The Regional Administrator may draw




on the letter of credit under the circumstances explained in




Section 2.3.2.  If an issuing institution is to deposit the penal




sum into a trust fund, the Regional Administrator should notify




the trustee at least two weeks in advance of the transaction, if




possible.




     2.4  Changing Mechanisms and Combining Mechanisms




     In order to achieve the maximum amount of flexibility in these
                                   2-52

-------
regulations, EPA allows owners and operators to change financial




assurance mechanisms and to combine them.




2.4.1  Changing Mechanisms




     Owners or operators may change the mechanism being used to provide




assurance of financial responsibility as long as prior written approval




is received from the Regional Administrator for the Region in which the




facility is located.  If the mechanism is providing assurance for more




than one facility, and these facilities are in more than one Region,




prior written approval may be needed from all of the affected Regional




Administrators (see Section 2.4.3).  All of the affected Regional Admin-




istrators must be notified within 60 days after the change takes place.




     Before a Regional Administrator approves of the change in




mechanisms, he will have to make certain that the new mechanism complies




with all of EPA's regulations for mechanisms to be used as financial




assurance of closure or post-closure care.  The new mechanism, if




approved, must become effective before the previous mechanism runs




out.  The Regional Administrator must make sure that the essential




overlap in mechanisms is present, but should strive for the minimum



necessary amount of coverage by the two mechanisms so as to reduce the




burden to the owner or operator.  Some suggestions as to how this may be




carried out are discussed below.




     If an owner or operator wants to cancel a surety bond or letter of




credit and place the necessary amount of funds in the accompanying




standby trust fund, he must first receive the approval of the Regional




Administrator for the cancellation of the bond or the letter of
                                   2-53

-------
credit.  The owner or operator would then be expected to place the
necessary amount of funds in the standby trust fund within 30 days of
the Regional Administrator's approval.  If the money is  not deposited
within 30 days, the Regional Administrator can issue a compliance  order
(so that the bond or letter of credit may not be cancelled) because the
owner or operator could be without assurance of financial responsibility
after another 60 days. When an owner or operator changes from a surety
bond or letter of credit to a trust fund, the amount of  money deposited
into the trust fund must be equal to the amount that would have had to
be in the trust fund, if the trust had been the original financial
assurance mechanism.
     If an owner or operator changes from a trust fund to a letter of
credit or surety bond, the Regional Administrator should not direct the
trustee to release funds from the trust until the effective date of the
letter of credit or surety bond.
     If an owner or operator changes from a surety bond  to a letter of
credit (or vice versa) the effective date of the letter  of credit  should
be no more than 30 days after the Regional Administrator approved  can-
cellation of the surety bond.
     2.4.2  Use of Multiple Financial Mechanisms
     Owners or operators may use more than one financial mechanism to
meet the closure or post-closure financial responsibility requirement
for one hazardous waste management facility.  The mechanisms which may
be so combined are limited to the trust fund, financial  guarantee  bonds,
and letter of credit.  The estimated costs for more than one facility
may not be assured by more than one mechanism.
                                    2-54

-------
     Multiple financial mechanisms may prove particularly useful when a




cost estimate for a facility guaranteed by a financial guarantee bond or




letter of credit increases markedly.  The issuing surety or financial




institution may be unwilling to increase the penal sum or credit amount.




The owner or operator could make up the difference between the old and




new cost estimates (and thus remedy the deficiency of the penal sum or




credit amount) by depositing the difference in the already existing




standby trust fund (see Section 2.1.11).  Cancelling the financial




guarantee bond or letter of credit and replacing it with a new mechanism




would not be necessary.




     Whenever mechanisms are combined, the financial assurance provided




must equal the relevant cost estimate.  Even though the amount of assur-




ance provided by a trust fund may build up when a trust fund alone is




providing assurance of financial responsibility, the amount of assurance




provided when a trust fund is combined with a letter of credit,




financial guarantee bond, or both must, at a minimum, be equal to the




relevant cost estimate.




     Whenever a financial guarantee bond is combined with a letter of




credit to provide assurance for one facility, the owner or operator need




only establish one standby trust fund.  If a trust fund is combined with




a surety bond or letter of credit, a separate standby trust fund is




unnecessary.




     2.4.3  One Mechanism for More than One Facility




     Owners or operators may use one trust fund, one surety bond or one




letter of credit to provide assurance of financial responsibility for
                                   2-55

-------
closure, or for post-closure care, of more than one hazardous waste

management facility (see Sections 2.1.6, 2.2.5, and 2.3.5).   In each of

these cases, the owner or operator must make sure that the mechanism

correctly lists for all facilities Included, the EPA Identification

Number, name, address, and the amount of funds assured by the

mechanism.  While the trust fund of surety may provide assurance of

financial responsibilities for facilities in more than one Region,  the

letter of credit may only be used to assure funds for facilities in one

EPA Region.

     Whenever the list is changed by the addition or subtraction of a

facility, or by an increase or decrease in the amount of funds assured

by the mechanism, all of the appropriate Regional Administrators must be

sent corrected lists within 60 days of such changes.

     Whenever a trust fund or surety bond is used to cover facilities in

more than one Region, all of the Regional Administrators of  Regions in

which these facilities are located must normally be involved in

decisions related to:

     •   Allowing decreases in the amount of funds guaranteed by
         the mechanism, unless the decrease is due to
         reimbursements or to switching mechanisms for a facility
         or facilities in one Region (see below).

     •   Allowing the owner or operator to change to another
         financial assurance mechanism (including a State-required
         mechanism).

     •   Allowing the owner or operator to be released from  the
         requirement to provide assurance of financial responsibi-
         lity for the closure or post-closure care for a
         particular facility.
                                   2-56

-------
     Decisions involving a reduction in the amount ot  funds guaranteed




by the mechanisms (unless the decrease is due to reimbursements or to




switching mechanisms for a facility or facilities in one Region) must be




agreed upon by all the Regional Administrators who have the facilities




in their Regions to ensure that the amount of funds remaining is




sufficient to cover all the facilities.  Whenever an owner or operator




requests a reduction in the amount of funds guaranteed by the mechanism




except for reasons mentioned above, the owners or operators of all the




facilities covered by the mechanism must send their most recent cost




estimates to the Regional Administrators so that the Regional




Administrators can check the cost estimates against the amount of funds




currently guaranteed.




     Decisions involving whether to authorize reimbursements from a




trust fund for closure or post-closure care expenses for a particular




facility could be made by the Regional Administrator for the Region in




which the facility is located.  Similarly, decisions as to whether one




of the facilities on a list could switch to another financial assurance




mechanism could also be made only by the Regional Administrator for the




Region in which the facility is located.  However, the Regional Admin-




istrator in question may not reimburse a larger amount of money than is




listed as the estimate for the particular facility, nor may he approve




switching a sum larger than the estimate for all the facilities in his




region to another mechanism.
                                   2-57

-------
     2.4.4  Single Mechanism for Closure and Post-Closure



     An  owner  or operator may provide assurance  of  financial  responsi-




bility for  the closure and post-closure care of  one,  or more  than  one,




hazardous waste management facility using a trust fund or a letter of



credit.   The closure and post-closure cost estimates must be listed




separately.
                                   2-58

-------
3.0  LIABILITY INSURANCE




3.1  What is Liability Insurance?




     Insurance Is a method of reducing risk and redistributing losses.




Ordinarily one party will contract to compensate another party or




parties for losses due to particular perils.  The likelihood that losses




will be suffered is estimated; fees are collected from all participating




parties on the basis of the likelihood of losses; and all or part of




such collected funds are paid back to the participating parties who




suffer losses covered by the insurance contract.




     Liability insurance protects individuals or commercial enterprises




against the possibility that as a result of their own concession of




responsibility or a judgment by a court of law or by an adminstrative




body, they may be required to pay damages to another party for injury to




the latter's person, property or other interests.




3.2  RCRA Liability Insurance




     Owners and operators of hazardous waste management facilities may




use liability insurance to meet their obligations to provide assurance




of financial responsibility for claims arising from the operations of




these facilities.




     Table 3-1 indicates the sections of the Code of Federal Regulations




applicable to RCRA insurance requirements.
                                   3-1

-------
                               TABLE  3-1
                    LIABILITY INSURANCE REGULATIONS
 SUBJECT OF REGULATION
     SECTION OF REGULATION

 INTERIM STATUS       GENERAL STATUS
   Insurance — Sudden
     and Accidental

   Insurance — Nonsudden
     and Accidental

   Hazardous Waste Facility
     Liability Endorsement
40 CFR S265.147(a)
40 CFR §265.147(b)
40 CFR §265.151(e)
 40 CFR §264.147(a)
40 CFR §264.147(b)
40 CFR§264.151(g)
For the text of these regulations, see 46 Federal Register pp. 2851 et.
seq. (January 12, 1981).
     These regulations contain the minimum standards that must be met by

insurance policies in order for them to provide the required insurance

coverage.  These standards concern:

     •   The amendment of the policy by the Hazardous Waste
         Facility Liability Endorsement

     •   The coverages listed on the policy

     •   Limits of liability

     •   Financial condition of the insured and legal defense
         costs

     •   Deductibles in the policy

     •   Cancellation
                                   3-2

-------
     These standards are discussed below.
     3.2.1  Hazardous Waste Facility Liability Endorsement
     Unlike the mechanisms authorized to provide assurance of financial
responsibility for closure and post-closure care, the Agency has not
developed specific wording for the instruments (policies) which must be
used to provide liability assurance.
     The Agency has, however, developed specific wording for a mandatory
Hazardous Waste Facility Liability Endorsement which must be attached
and submitted with all insurance policies which are used to fulfill an
owner's or operator's obligation to provide assurance of financial
responsibility for claims.  An endorsement amends an underlying
policy.  It serves as a supplementary contract to qualify, enlarge, or
change in some other manner the obligation created in the underlying
insurance policy.  If there is a discrepancy between any of the provi-
sions of the insurance policy and the endorsement, the provisions of the
endorsement supercede the provisions of the policy.
     The first paragraph of the Hazardous Waste Facility Liability
Endorsement lists the facilities to which the endorsement will apply.
(The insurance policy might include coverages for facilities that do not
treat, store, or dispose of hazardous waste.)  It also defines some
conditions under which the insurance company will be held liable for
claims (see Sections 3.2.4 and 3,2.5) and specifies that the limits of
liability are exclusive of legal defense costs (see Section 3.2.4).
     3.2.2  Coverages
     Owners or operators of hazardous waste TSDF's are required to have
an insurance policy (or a State-required mechanism approved by the
                                   3-3

-------
Regional Administrator) providing coverage for claims from the operation




of such facility or group of facilities from sudden and accidental




occurrences that cause injury to persons or property.




     Owners or operators of surface impoundments,  landfills or land




treatment facilities are also required to maintain liability insurance




for claims arising from nonsudden and accidental occurrences.




     3.2.2.1  Responsibility for Coverage




     The owner or operator whose name appears on the RCRA permit appli-




cation or RCRA permit will be the owner or operator responsible for




providing such liability coverage.




     3.2.2.2  Extent of Coverage - Multiple Facilities on One  Policy




     Coverage is required for a hazardous waste facility or a  group of




facilities.  That is, if one owner or operator is  responsible  for




several facilities, the required coverage will serve for all such




facilities.




     Whenever more than one facility is covered by one insurance policy,




a list including the following information for each facility must be on




the policy itself or attached to the policy:  the  EPA Identification




Number, name, and address.  Whenever the list is changed by the addition




or subtraction of a facility or by an increase or  decrease in  the amount




of funds assured, all of the appropriate Regional  Administrators must be




sent corrected lists within 60 days of the change.




     3.2.2.3  Comprehensive and General Liability  Coverage




     Many owners or operators of hazardous waste management facilities




already have liability insurance.  Perhaps the most common type of




insurance covering some types of liability is Comprehensive and General




                                   3-4

-------
Liability (CGL).  This insurance would satisfy the requirements for




coverage of sudden and accidental occurrences that cause injury to




persons or property.




     CGL policies do not generally provide coverage for claims arising




from nonsudden and accidental occurrences that cause injury to persons




or property.  Owners or operators who must have an insurance policy with




coverage for nonsudden and accidental occurrences will have to have such




coverage added to an already existing policy or have a. new policy




executed providing such coverage.




     3.2.2.4  Environmental Impairment Coverage




     Some environmental impairment insurance policies include coverage




for liability claims arising from occurrences which are both nonsudden




and non-accidental.  This type of policy would provide acceptable




coverage for claims arising from nonsudden and accidental occurrences as




required by these regulations.  The coverage for claims arising from




occurences which are both nonsudden and non—accidental is somewhat




broader than that currently required to meet the regulation.  The regu-




lation does not require coverage for claims arising from occurrences




which are expected and intended, e.g., releases to the environment that




are allowed under the conditions of a permit.  The regulation does




require coverage for claims arising from occurrences which are not




expected or intended, e.g., a gradual release in excess of that allowed




under conditions of a permit.  Such a release might occur for example,




if a liner system failed.
                                   3-5

-------
     3.2.3  Limits of Liability




     Owners or operators of TSDF's are required to maintain liability




insurance for claims arising from sudden and accidental occurrences with




liability limits in the amount of at least $1 million per occurrence




with an annual, aggregate of at least $2 million during the operating




life of the favcility.




     Owners or: operators of surface impoundments, landfills or land




treatment facilities are required to maintain liability insurance for




claims arising from nonsudden and accidental occurrences with liability




limits in t:he amount of at least $3 million per occurrence with an




annual aggregate of at least $6 million during the operating life of the




facility.




     Owners or operators may combine different types of insurance




policies in order to> provide the necessary coverages up to the required




limits of liabilities.




     Excess liability insurance provides coverage above a specified




figure and up to a sipecified limit.  Such insurance could be combined




with a CGL policy to effectively raise the liability limits of specified




coverages.  An "umbrolla" contract may also serve to raise the limits of




liability on a primaicy insurance policy.  It provides broader coverage




than excess liability insurance.  For the purpose of these regulations




it could have the s'>arae effect as excess liability insurance and raise




the limits, of liability on those coverages required by these regulations




(as well as others) so that the amounts of liability covered would




satisfy these regulations.
                                    3-6

-------
     3.2.4  Financial Condition of the Insured and Legal Defense Costs




     The Hazardous Waste Facility Liability Endorsement makes it clear




that the insurer is obligated to pay claims regardless of the financial




condition, insolvency, or bankruptcy of the insured, and that the stated




amounts of mandatory coverage exclude legal defense costs.  The owner or




operator (insured) may contract separately with the insurer for these




legal defense costs or may contract for coverage in excess of mandatory




amounts as long as the amounts required by these regulations are speci-




fically set aside for claims awards.




     3.2.5  Deductibles in the Insurance Policy




     The Hazardous Waste Facility Liability Endorsement provides that no




deductible in the policy may be asserted by the insurer for claims up to




those amounts of insurance required by the regulations.  However, this




provision of the endorsement does not nullify any obligation of the




insured to the insurer, as defined in the insurance policy, with regard




to deductible amounts.




3.3  Qualifications of Insurers




     The Agency is not placing its own restrictions on which insurers




are acceptable underwriters of liability insurance required by these




regulations.




3.4  Evidence of Insurance Agreements




     Owners or operators of hazardous waste management facilities oper-




ating with interim status must provide the Regional Administrator with




evidence of insurance coverage for claims arising from sudden and acci-




dental occurrences by July 13, 1981.  The effective date for this




coverage must also be on or before July 13, 1981.



                                   3-7

-------
     Owners or operators of surface impoundments, landfills or land




treatment facilities operating with interim status must provide the




Regional Administrator with evidence of insurance coverage for claims




arising from nonsudden and accidental occurrences by January 12, 1982,




if their sales in 1980 were more than $10 million.  If sales were more




than $5 million but less than $10 million, such evidence must be




provided by January 12, 1983.  If sales were less than $5 million,  such




evidence must be provided by January 12, 1984.  The effective dates for




this coverage must be on or before the dates specified.




     For the purpose of these regulations, "sales" shall be the total




revenues or total sales, as defined by generally accepted accounting




principles, appearing on the owner's or operator's income statements for




the calendar year 1980.




     Owners or operators of new facilities operating with general status




must provide evidence of the applicable insurance coverage(s) to the




Regional Administrator at least 60 days before the date on which




hazardous waste is first received for treatment, storage or disposal.




The effective date for this coverage must be on or before the date on




which hazardous waste is first received for treatment, storage, or




disposal.




     Owners or operators who receive permits will already have sudden




and accidental coverage for existing facilities.  These owners or




operators must provide evidence of nonsudden and accidental coverage by




the same dates such evidence would have been provided had the facility




continued to operate with interim status (see above).  The dates on
                                   3-8

-------
which this coverage must become effective are the same as the dates by

which evidence must be provided.

     All owners or operators must send originally signed duplicates of

their insurance policies including the endorsement(s) to the appropriate

Regional Adtninistrator(s) by certified mail, or deliver them in

person.

     Regional Staff will check that insurance policies:

     •   Conform to regulatory requirements

     •   Are received by the correct dates

     •   Are effective by the correct dates

3.5  Sudden and Accidental and Nonsudden and Accidental Coverage on One
     Insurance Policy

     Owners or operators may use one insurance policy to provide

assurance for claims arising from sudden and accidental occurrences, and

from nonsudden and accidental occurrences arising from the operations of

the facility.  The liability limits of a policy providing for sudden and

accidental occurrences, and nonsudden and accidental occurrences for a

single facility must be in the amount of at least $4 million per occur-

rence with an annual aggregate of at least $8 million.

3.6  Variances to the Liability Requirements

     Either an owner or operator or the Regional Administrator can

initiate a proceeding to obtain a variance to the liability requirements

for a facility.

     An owner or operator may obtain a variance to the liability

requirements if he can demonstrate satisfactorily to the Regional Admin-

istrator that the levels required by the regulation are too high for the

degree and duration of risk associated with his facility.

                                   3-9

-------
     The Regional Administrator may require a variance for a facility if




he determines that the levels of liability are too low for the degree




and duration of risk at a facility.  He may make this determination at




any time.  The Regional Administrator may also require that an owner or




operator of a treatment or storage facility obtain coverage for




nonsudden and accidental occurrences if the Regional Administrator




determines that there is a significant risk to human health and the




environment from such occurrences.




     3.6.1  Assessing Degree and Duration of Risk




     The level of liability coverage consistent with the degree and




duration of risk of a particular facility will be a function of the




following five components of risk:




     (1)  Characteristics of wastes being handled or disposed;




     (2)  Environmental pathways at the facility;




     (3)  Population at risk;




     (4)  Design of the containment; and




     (5)  Management procedures.




Table 3-2 provides an outline of the risk components associated with




hazardous waste management which will affect the level of coverage




appropriate for a particular facility.




     In determining a level of coverage consistent with the degree and




duration of risk, the goal is to ensure that the level chosen guarantees




protection from the maximum probable loss associated with the




facility.  The maximum probable loss is not the worst conceivable event,




but rather the worst accident that could be reasonably expected to
                                   3-10

-------
                               TABLE  3-2
                       OUTLINE OF RISK COMPONENTS

Waste Characterization
     Volume of Waste
     Lethality
     Infectivity
     Flammability
     Radioactivity
     Carcinogenicity
     Mutagenicity
     Compatibility with other wastes
     Transformation of waste products
     Half-life

Natural Pathways
     Leachate formation
     Solubility of wastes
     Drainage and runoff
     Soil porosity
     Flood plains
     Wetlands
     Geological faults
     Unstable slopes
     Amount of precipitation
     Evaporation rate
     Storm frequency
     Prevailing winds
     Burrowing animals
     Bioaccumulation/food-chain contamination

Population Risk
     Proximity of population
     Proximity to aquifer
     Proximity to ground or surface waters
     Proximity to wildlife preserve/endangered species
     Buffer zone of facility
     Zoning status of restrictions

Design of Containment
     Disposal methods (e.g., drums, free burial)
     Site design
     Transport systems
     Holding systems
     Age of facility
     Durability of containment system
     Compatibility of containment system with wastes
                                   3-11

-------
                         TABLE  3-2  (continued)

Management Procedures
     Monitoring and leak detection system
     Disposal operations
     Regulatory compliance
     Technical Competence
     Management system
     Emergency response capabilities
                                    3-12

-------
occur.  As a result, in arriving at an estimate of the maximum probable




loss, it is necessary to consider factors relating to the possible size




of loss, such as characteristics of the waste, the environmental




pathways and the populations at risk, and also factors relating to the




probability of the event, such as containment design, management




practices, and aspects of the environmental pathways.  In some cases, a




very large maximum loss would be conceivable, but it would not represent




the maximum probable loss because of the low probability of the chain of




events that would lead to such a loss.  For example, if a facility




handles very low hazard materials and is not located near water sources




or population centers, maximum losses in the event of an accident would




be small.  If the containment designs are state-of-the-art, the proba-




bility of an accident would also be small.




     3.6.1.1  Waste Characterization




     The inherent toxicity of the waste materials generated and/or




handled by a facility and the total amount of wastes produced greatly




influence the potential maximum losses at a given facility.  Toxicity,




in this context, should be viewed broadly enough to include materials




that are hazardous because of their infectivity, flammability or radio-




activity.  Other key elements which greatly influence the degree of risk




at a site are the compatibility of the various wastes which are buried




in the same cells, the chemical characteristics of the "breakdown"




products that would be created during decomposition, and the half-lives




of the various elements involved.
                                   3-13

-------
     3.6.1.2  Environmental Pathways




     In addition to the chemical toxicity of the wastes disposed,  the




natural pathways specific to a particular site may greatly increase the




risk to human health and the environment.  The solubility of wastes will




greatly influence the likelihood of seepage from the disposal site.




Another Influence on potential exposure is the quantity of leachate that




routinely accumulates as part of normal operations.  Drainage and  runoff




patterns are determinants of transport for soluble materials and those




that can be moved by water.  The characteristics of the soil (e.g.,




porosity) also may guide seepage in specific directions and increase the




potential for liabilities.




     The environment surrounding a facility producing, handling or




storing hazardous waste will play a large role in determining both the




chances of liabilities and the extent of the damages if an accident




occurs.  Proximity of flood plains, wetlands, aquifers, geological




faults or unstable slopes all increase risk potential.  Similarly,




prevailing geohydrological conditions, including groundwater flow




patterns, groundwater quality, and seasonal zones, will affect the risk




of exposure.  Other potential significant climatic factors include the




amount of precipitation, evaporation rates, and the frequency of high




winds or other violent meteorological phenomena.




     Ecological pathways should also be considered in the risk




evaluation.  If the hazardous materials come in contact with living




organisms, bioaccumulation is possible.  Organisms contaminated by toxic




wastes may become part of the human diet, contributing to a public
                                   3-14

-------
health hazard.  Finally, burrowing animals may destroy the structural




integrity of landfills or surface empoundments.




     3.6.1.3  Population at Risk




     Important factors that must be considered in evaluating the degree




of risk involved are the proximity of present and future human




population centers and the potential for wastes to reach human




populations.  The proximity of waste disposal sites to aquifers and




ground and surface waters and the uses of these water sources will




greatly affect the potential size of liability claims if an accident




should occur.  The risks of population exposure may also be influenced




both by the size of the buffer zone established at the facility itself




and the zoning status or restrictions on the area surrounding the




facility.  Potential exposure to wildlife preserves or endangered




species may also increase subsequent liability.




     3.6.1.4  Design of Containment




     The probability of liabilities will be greatly influenced by the




design of the facility's containment.  The degree of containment will




vary depending on how the wastes are handled and disposed (e.g., how




wastes are stored, whether wastes are disposed in drums or freely




buried) and the structural barriers of the facility.  The potential for




damages will also be influenced by the structural integrity of the




facility, including the type of containment system (i.e., man-made




liners or relatively impermeable natural clay soil layers) used to




minimize leaching, the drainage and diversion structures erected, and




the piping and structural barriers provided for runoff and leachate




control.



                                   3-15

-------
     The age of the facility will also represent an important variable




affecting the degree of waste containment.  Older systems may not have




been well designed for long-term confinement of hazardous materials, or




they may have become vulnerable to breaks because of metal fatigue or




corrosion.  In addition to age, the expected lifetimes of liner




materials and burial drums and the compatibility of these materials with




the wastes may be critical factors in evaluating risk potential, espe-




cially for extremely toxic wastes with long half-lives.




     3.6.1.5  Management Procedures




     In assessing the probability of losses associated with a particular




facility, the management procedures employed by the operator must also




be critically evaluated.  This will include evaluating the reliability




of monitoring and leak detection systems, since proper use of these




mechanisms can avoid incidents associated with seepage.  In most situa-




tions, seepage is sufficiently gradual so that even if containment




fails, timely detection and adequate remedial measures may avert liabi-




lities.  Also, the normal operating procedures of the facility should be




assessed.  The likelihood of potential liability, for example, would be




much greater at a site where large quantities of wastes are routinely




accumulated for significant periods of time before disposal than at a




site where there is minimal lag time between the receipt and disposal of




wastes.
                                    3-16

-------
     This category of risk components includes many human factors.




Ideally, a facility's plan for hazardous waste management should




include:




     •    Clear assignment of responsibility




     •    Appropriate education for workers on hazard potentials




     •    Procedures for safe handling




     •    Well-defined emergency response procedures




     •    Regulatory compliance




In assessing the overall management structure of the facility, the




surveyor must consider the status of each of these aspects of operation,




not only in terms of their existence "on paper," but also in regard to




the manner in which these objectives are communicated to facility




personnel, and the observed commitment of top level management to




fulfilling these objectives.




     3.6.2  Procedures for Owner or Operator to Obtain a Variance




     If an owner or operator of a facility operating with interim status




believes that the required level of insurance for his facility is incon-




sistent with the degree and duration of risk, he may submit a variance




request to the Regional Administrator.  This request must be delivered




either in person or by certified mail.  An owner or operator of a new




facility (i.e., a facility that was not considered in operation on




November 19, 1980) may submit a variance request with Part B of the




permit application.  If an owner or operator of a facility operating




with general status wishes to request a variance, he must do so by




seeking a permit modification pursuant to the procedures under 40 CFR




§124.5.



                                   3-17

-------
     3.6.3  The Role of the Regional Administrator in Variance  Requests




     The Regional Administrator is responsible for evaluating the




validity of requests which are submitted to him.   In addition,  he may




adjust the level of coverage required at any time if he deems it neces-




sary to protect human health and the environment.




     In evaluating variance requests, the Regional Administrator may




request any technical and engineering data he finds necessary to assess




the degree and duration of risk.  The Regional Administrator will




process the requests in accordance with permit modification procedures




under 40 CFR §124.5 (for facilities operating with interim status, the




requests will be treated as permit modifications) or as part of the




permitting process under 40 CFR §122.25 for facilities applying for




general status.  In considering variance requests for facilities with




interim status, the Regional Administrator may hold a public hearing at




his own discretion or whenever he finds, based upon requests for a




public hearing, a significant degree of public interest in the possible




decision to adjust the level or type of coverage  required for a




facility.




     3.6.4  Documentation Requirements




     The owner's or operator's request for a variance should include the




level of insurance he deems appropriate for his facility as well as




sufficient documentation to support the request.   This documentation




should be technical and the engineering data should be relevant to the




risk components described in Section 3.6.1.  In cases where the Regional




Administrator initiates the variance proceedings, the owner or operator




must furnish any data requested within 60 days of his request.




                                    3-18

-------
3.7  Cancellation of an Insurance Policy




     Paragraphs 3 and 4 of the Hazardous Waste Facility Liability




Endorsement contain the conditions under which the policy and




endorsement may be cancelled.




     Paragraph 3 states that the endorsement may not be cancelled




without cancelation of the policy to which it is attached.  The




insurance company or the insured must send the Regional Administrator




notice in writing of intent to cancel the policy.  Cancellation may not




be effective for at least 60 days after the notice is received by the




Regional Administrator.  If the insurance policy and endorsement cover




facilitiss in more than one Region, originally signed copies of the




notice of intent to cancel must be sent to all of the applicable




Regional Administrators.  Cancellation of the policy and endorsement




will become effective in a particular Region only 60 days after the




Regional Administrator in that Region has received such notice.




     Paragraph 4 specifies further that cancellation of a "claims-made"




policy, that is a policy which covers claims which are made during the




term of the policy, may not be cancelled or terminated within 120 days




of any fire, explosion, or unplanned sudden or nonsudden release of




hazardous waste or hazardous waste constituents to air, soil, surface




water or ground water.
                                   3-19

-------
4.0  ROLE OF STATES IN RCRA




     Section 3006 of RCRA allows States to assume responsibility for




carrying out the requirements of Subtitle C of the Act — Hazardous




Waste Management.  States may assume this responsibility only after




authorization from EPA.




     EPA must administer hazardous waste management in States without




authorized programs, in States whose programs do not meet the minimum




requirements prescribed by RCRA, and in States waiting for EPA authori-




zation to administer their own programs.




4.1  Applicability of State Financial Requirements




     A number of States have adopted hazardous waste regulations which




require owners or operators to demonstrate financial assurance for




closure and post-closure care.  Several States also require liability




coverage.  Like the Federal regulation, many of these State regulations




require owners or operators to use specific financial mechanisms for




these purposes.




     EPA recognized that differences between State and Federal financial




responsibility requirements might result in duplication and unnecessary




costs to owners or operators.  This would not be a problem in those




States that have received interim or final authorization from EPA to




operate their own hazardous waste regulatory program, since only the




State's financial requirements would apply.  In order to avoid




duplication and unnecessary costs to owners or operators in States with




financial responsibility requirements but without interim or final EPA




authorization to run their own hazardous waste management programs,
                                   4-1

-------
owners or operators may use State-required mechanisms to meet the

Federal financial requirements if these mechanisms provide closure or

post-closure financial assurance or liability coverage equivalent to or

greater than that of the Federal mechanisms.

     A difficult but critical task for the Regional Administrator will

be to assess whether State-required mechanisms provide assurance for

closure, post-closure care, or liability coverage equivalent to or

greater than that provided by Federal mechanisms.  To evaluate whether

State-required mechanisms provide for financial responsibility that is

equivalent to or greater than that required by Federal regulations, the

Regional Administrator should examine three related areas for each

facility.

     (1)  What types of financial responsibility coverage for the
          facility are required by the State?  How does this
          compare with the Federal requirements?

     (2)  Do the financial responsibility mechanisms required by
          the State have the same degree of security and
          flexibility as the Federal mechanisms?

     (3)  Is the level of coverage required by the State
          equivalent to or greater than the level of coverage
          required by Federal regulations?

     4.1.1  Comparing State and Federal Financial Responsibility
            Requirements for Facilities

     Table 1-2 summarizes the Federal financial requirements which must

be satisfied for each type of facility.  After referring to this Table,

Regional Administrator should compare the Federal financial responsi-

bility required for the type of facility with the State financial

responsibility required for the type of facility.  For example, a land-

fill, surface impoundment or land treatment facility according to


                                    4-2

-------
Federal regulations, must provide assurance of financial responsibility




for closure, post-closure, and liability claims arising  from sudden and




nonsudden accidents.  Although a State may require a landfill,  surface




impoundment or disposal facility to meet some of these financial




requirements, it may not require that it meet all of them.




     Once the differences between Federal and State financial responsi-




bility requirements for a particular facility are established,  Regional




Staff must decide whether Federal and State financial requirements  which




sound the same are, in fact, equivalent.  Definitions of what the




financial responsibility mechanisms are supposed to ensure  are




especially important.  In particular, Regional Staff should review  the




duration of the care provided by a particular mechanism  and the




activities which are included in its coverage.  For instance, according




to the Federal regulations, the post-closure care period must continue




for at least 30 years.  Financial mechanisms providing for  post-closure




care must, by definition, provide for 30 years of care.   This care  must




consist of providing and maintaining applicable ground-water monitoring




and reporting systems, waste containment systems, and security




systems.  State mechanisms providing for a shorter term  or  not covering




all of the closure and post activities defined in Subpart G of  40 CFR




264 and 265 cannot be fully equivalent.




     State-required financial responsibility mechanisms  to  satisfy  State




regulations sometimes will not include all elements of what the Federal




requirements define as assurance for closure, post-closure  and  liability




coverage.  Because of differences in the duration of care assured by the
                                   4-3

-------
mechanism (e.g. for post-closure) or in the levels of coverage required




(especially in the case of liability), they may not fully cover these




requirements.  State-required surety bonds may only ensure closure,




partial post-closure care, and some liability coverages for sudden and




accidental occurrences.




     The Regional Administrator must establish which Federal




requirements are covered by State-required mechanisms,  or which portions




of Federal requirements are covered by the State-required mechanism




(e.g., five years of post-closure care instead of 30 years).




     4.1.2  Flexibility and Security of State-Required  Mechanisms




     The Regional Administrator must examine the actual workings of the




State financial mechanisms to determine if they are equivalent to the




Federal mechanisms with regard to flexibility and security.  The flexi-




bility of State-required financial mechanisms is important because the




State mechanisms alone may not be sufficient to meet all present and




future Federal financial responsibility requirements for the owners or




operators of hazardous waste management facilities.  The Regional Admin-




istrator must decide if any element of a State-required mechanism




precludes adding to the mechanisms, precludes payment by the mechanism,




or calls payment by the mechanism into question if additional financial




responsibility coverage is available from other sources.




     Determining if State-required mechanisms for closure and post-




closure provide the same degree of security which Federal mechanisms for




these events provide will be a particularly critical aspect of the




review process.  In order to decide if a State-required mechanism for
                                   4-4

-------
closure or post-closure provides security equivalent to the Federal

mechanisms, the Regional Administrator should ask the following

questions about the State mechanisms securing funds for closure or post-

closure.

     (1) Does the mechanism offer strong protection against the
         successful collection of third-party claims?

     (2) Are adequate qualifications required for banks or other
         financial institutions empowered to hold assets of the
         owner or operator or to guarantee his payment or
         performance?  (e.g., Which banks may hold trust funds?
         Must surety companies be state-approved?)

     (3) Which circumstances will allow the State or EPA to take
         over assets held by a bank or other financial
         institution, or to collect a third-party guarantee?

     (4) Can third-party guarantees be cancelled?  If so, will the
         owner or operator be able to replace it with his own
         funds or with another third-party guarantee (State or
         Federally required)?  Will the original guarantor honor
         the guarantee and provide the necessary funds for closure
         or post-closure if the owner or operator is unable to
         find another financial responsibility mechanism
         satisfactory to the Regional Administrator?

     (5) Could cancellation of a third-party guarantee become
         effective before the State or EPA could legally collect
         funds from the guarantor for closure or post-closure?
         Would violations by the owner or operator of State or
         Federal regulations not related to closure or post-
         closure put a third-party guarantee in jeopardy?

     The Federal mechanisms for closure and post-closure were designed

to provide a great deal of security because closure and post-closure are

events certain to occur at facilities where these procedures are

required.  EPA is convinced that despite the strict specifications it

has established for financial responsibility mechanisms for closure and

post-closure, at least one mechanism for these events should be

available to each qualified owner or operator.
                                   4-5

-------
     Federally authorized mechanisms to cover liability for damage

claims arising from sudden or nonsudden accidents do not have such

strict specifications (see Section 3.0).  There may never be a need for

an owner or operator to satisfy damage claims.  Besides, EPA is aware

that the number of insurers willing to provide coverage for nonsudden

events is somewhat limited.  If stricter requirements for liability

mechanisms had been imposed, every qualified owner or operator might not

be able to procure the necesssary coverage.  Therefore, comparing a

State-required mechanism covering liability to the Federal mechanism

should be easier than comparing the State-required mechanisms for

closure and post-closure to the Federal mechanisms.

     In comparing a State-required mechanism covering liability to the

Federal mechanisms, the Regional Administrator should ask the following

questions about the State mechanism securing funds for liability claims:

     (1) Are the types of coverages provided by the State mechanism
         equivalent to the coverages required on insurance
         policies?

     (2) Are the limits of liability provided by the State
         mechanism at least as high as the amounts required on
         insurance policies?

     (3) Will these amounts be available to claimants regardless
         of legal defense costs, the financial condition of the
         ensured and deductibles?

     (4) Will cancellation of the State mechanism not be effective
         for at least 60 days, or at least 120 days of any fire,
         explosion or unplanned sudden or nonsudden release of
         hazardous waste if the mechanism is written on a claims-
         made basis?

     If a State-required mechanism attempts to include coverage for some

aspects of closure, post-closure and liability, the mechanism will be
                                   4-6

-------
acceptable only for coverage of liability, but not closure or post-




closure, if it does not contain both the flexibility and security




elements of the Federally required mechanisms for closure and post-




closure.




     4.1.3  Amount of Funds Available




     If a State-required mechanism for closure, post-closure, or




liability coverage is found to be acceptable, Regional Staff must then




make certain that the amount of funds available from the State mechanism




is equal to the amount required by Federal regulations.  (Closure and




post-closure amounts are discussed in 1.5.2 and liability amounts are




discussed in 3.2.3).  If the amount available is less than that required




by Federal regulations, the owner or operator may add to the State




mechanism (if possible) or establish an additional Federal financial




assurance mechanism (see Section 2.0) or liability insurance (see




Section 3.0) to cover the difference.  The amount of funds available




through the State and Federal mechanisms together must equal at least




the amount required by the Subpart H Regulations.




     4.1.4  Evidence of the Establishment of a State-Required Mechanism




     Owners or operators must submit suitable evidence to Regional




Administrators, either in person or by certified mail, if they are using




State-required mechanisms to fulfill financial responsibility closure,




post-closure, or liability requirements, of the existence and terms of




that mechanism.  Examples of suitable evidence include:  a copy of a




trust agreement, surety bond, letter of credit, etc., with the State




listed as the beneficiary.  Such submittals must include or have
                                   4-7

-------
attached the following information:  the facility's EPA Identification


Number, name, address, and the amount of liability coverage or funds for


closure or post-closure care assured by the mechanism.


4.2  State Assumption of Financial Requirements


     Both the interim status and general status financial requirements


regulations allow States to assume responsibility for the owner's or


operator's compliance with closure, post-closure or liability require-


ments.  The State may assume the responsibility either:  (1) by assuming


legal responsibility for an owner's or operator's compliance with the


closure, post-closure or liability requirements of these regulations or


(2) by assuring that funds will be available from State sources to cover


these requirements.


     If a State assumes legal responsibility for part of these require-


ments (e.g., for closure and post-closure, but not for liability), the


owner or operator must provide the additional coverages as specified by
                                                                      \

these regulations.  If the amount of funds available through a State


guarantee is less than the amount required by these regulations, the


owner or operator oust obtain one of the financial assurance mechanisms


as specified in these regulations to cover the additional closure or


post-closure assurance, or additional liability insurance as specified


in these regulations to cover the additional liability assurance.


     Evidence of the State's assumption of responsibility must be


provided by the owner or operator.  This evidence must consist of a


letter from a legally-authorized official, or officials, of the State


describing the nature of the State's responsibility regarding the
                                   4-8

-------
closure, post-closure, and liability requirements covered.   If the State
is assuming legal responsibility for any of the financial requirements
of the owner or operator, the letter should include a citation from the
State law, regulation, legislative resolution or other legal authority
providing for such assumption of responsibility.  If the State is
assuring that funds will be available from State sources to cover any of
the owner's or operator's financial requirements, the letter should
specify the source of State funds and include a citation of the State
law, regulation, legislative resolution, or other legal authority
providing that State funds may be dedicated in this manner.  The letter
must include or have attached to it, the following information:  the
facility's EPA Identification Number, name, address, and the amounts of
liability coverage or funds for closure or post-closure care that are
assured by the State.  Such letters must be signed by the State
official, or officials, with the legal authority to execute the
financial guarantee and to make such commitments on behalf  of the State.
     This letter must be delivered in person or by certified mail to the
Regional Administrator.  For facilities operating with interim status,
the letter must be delivered by July 13, 1981, unless it assures only
the liability requirement for coverage of claims arising from nonsudden
and accidental occurrences.  In this case the letter must be delivered
by the date this specific coverage is due (see Section 3.4).  For
facilities operating with general status, the letter must be delivered
in person or by certified mail to the Regional Administrator at least 60
days before the date on which hazardous waste is first received for
treatment, storage or disposal.
                                   4-9

-------
                                GLOSSARY

Financial, Administrative and Legal Terms Used in This Guidance Manual
Account Party


Acknowledgment
Attorney in Fact
Beneficiary
Certificate of Acknowledgment
Coinsurance
Collateral Security
Contract of Suretyship
 Person in favor of whom a letter of
 credit is issued.

 Formal declaration before an authorized
 official, by  the person who executed
 the instrument, that it is his free act
 and deed.

 A private attorney authorized by
 another to act in his place for the
 transaction of business in general.
 This authority is conferred by an
 instument in  writing commonly called a
 "power of attorney."

 One for whose benefit a trust is
 created.

 The certificate of a notary public,
 justice of the peace, or other
 authorized officer, attached to a deed,
 mortgage, or  other instrument, setting
 forth that the parties thereto
 personally appeared before him on such
 a date and acknowledged the instrument
 to be their free and voluntary act.

 A relative division of risk among
 insurers or sureties.

 A security given in addition to the
 direct security, and subordinate to it,
 intended to guarantee its validity or
 convertibility or insure its
 performance;  so that if the direct
 security fails, the creditor may fall
 back upon the collateral security.

 Contract whereby one party engages to
 be answerable for a debt, default or
miscarriage of another and arises when
 one is liable to pay debt or discharge
 obligation, and party is entitled to
 indemnity from person who should have
 made the payment in the first instance
 before surety.
                                   G-l

-------
Damages
Grantor

Hazard


Insurance
Instrument
Issuer
Letter of Credit
Market Value
A pecuniary compensation or indemnity,
which may be recovered in the courts by
any person who has suffered loss,
detriment or injury, the unlawful act
or omission or negligence of another.

The person who creates a trust.

The risk, danger, or probability that
the event insured against may happen.

A contract whereby, for a stipulated
consideration, one party undertakes to
compensate the other for loss on a
specified subject by specified
perils.  The party agreeing to make the
compensation is usually called the
"insurer" or "underwriter;" the other,
the "insured" or "assured;" the agreed
consideration, the "premium;" the
written contract, a "policy;" the
events insured against, "risks" or
"perils;" and the subject, right or
interest to be protected, the
"insurable interest."

A written document; a formal or legal
document in writing such as a contract,
deed, will, bond or lease.

A bank or other financial institution
which by establishment of a letter of
credit obligates itself to make a
payment to the obligee for the account
of the obligor (account party).

A written instrument, addressed by one
person to another requesting the latter
to give credit to the person in whose
favor it is drawn.

Price which a seller, willing but not
compelled to sell, would take, and a
purchaser, willing but not compelled to
buy would pay.
                                   G-2

-------
Notary Public
Obligee
Penal Sum
Power of Attorney
Premium
Principal
Reinsurance
Rider
Risk
Securities
A public officer whose function it is
to administer oaths; to attest and
certify, by his hand and official seal,
certain classes of documents, in order
to give them credit and authenticity.

The person in favor of whom some
obligation is contracted.

A sum agreed upon in a bond to be
forfeited if the condition of the bond
is not fulfilled.

An instrument authorizing another to
act as one's agent or attorney.

The sum paid or agreed to be paid by an
insured to the underwriter as the
consideration for insurance or acting
as surety.

The person primarily liable, for whose
performance of his obligation a
guarantor or surety has become bound.

A contract by which an insurer (or
surety) procures a third person to
insure him against loss or liability by
reason of original insurance.  A
contract that one insurer (or surety)
makes with another to protect the
latter from a risk already assumed.

An addition paper attached to, and
forming a part of, an insurance policy
or surety bond.

In insurance law; the danger or hazard
of a loss of the property insured; the
causalty comtemplated in a contract of
insurance; the degree of hazard; a
specified contingency peril.

Evidences of obligations to pay money
or of rights to participate in earnings
and distribution of corporate, trust
and other property (e.g., stocks).
                                   G-3

-------
Surety
Surety Company
Trust Fund
Trustee
Underwriting Limitation
One bound with his principal for the
payment of a sum of money or for the
performance of some duty or promise and
who is entitled to be indemnified by
someone who ought to have paid or
performed if payment or performance be
enforced against him.

A company, usually incorporated, whose
business is to assume the
responsibility on bonds in
consideration of a fee proportioned to
the amount of security required.

A fund held by a trustee for the
specific purposes of the trust.

The person appointed, or required by
law to execute a trust.

The restriction on the amount that an
insurance company or surety can
guarantee.
                                   G-4

-------
     CO.

     I
     H
     en
      W
      H
      w
      2:
      M
      w
      Q

      W
      O
a    o
w    u
IX
      CO

      3
      H








B

tn
i *
t*













•c
BL.
t-4
I.*
« **
i-,
I

!
i
I








n
i
H -<
3 -
Q£
H


1
1
1
i
I
i
i
i




i
F-
tn -i
= a
H <
< U
H 0
in
X 8
*•* z
fli <
Id M
^ b
W 1












§
•^ O
C *•> "
CQ n o
o w»
« U «H
W «•
a at

a o n
in c. 01



41

0) II
b
3
U)
o
tH
U




o
w
i
•3
s
u
U O
9) O
So*
(•"1
Of  UM O
Z D-

1
0 a» C"
§«- c
•H 3
* •-( O
2 « i
«> c
•^4 4J
U •*•* C
• 0) CO U
1- v- E
u a ix
c. a oj
o c > o.
g ?SS
°.s c i
o "U "•
K 3 ^
iH E
«• s
>— '
1
^N
01 4J
^i C
<= i S
0^2
o . I
, 6C CO
-T C
3 — «
5J « ^_ g
• b tr, e
" OJ b 5
0 0. IS to
1 0 J c
g
S c m g
- mr; ^
0 C -i
p* *"
«• 2 ^
E
ft
^


1 /-*
^j
« e
dw 3
0 -H g
S " i
,H y
 G t~* 4J
•* tn a
• JJ b 0)
• to a I
a b tu S,
I 0) >• CO
g So =•
00 .-t'1 "
. N an m
o = i
^ -H -H
<»•*£,
i
b





0)

AJ
0, 00
•a c
§-rt
to
3
01
.a -o
c
4J 3 *
01 
3 U
S f
to 1 S-
«- u 3
oo e b u
91 tU U CJ
t&.sl
n c. 4J ^-(
~H 3
u o E
^ 0) U U
^T u c o
3 t-i t-( Uj
n u.
o
o
m a*
• k4 J-l
C 3 X
v£> CD O
ft O U
V> r-,
U 1*
a id
•33
r* 4) CO
O w O
a] «-(
<-, 3 ej
«r^ } y^.
x •DUO
<8 W 4J
0 0 «»
o *w a e
O O ft
T3 -U
O gen
m 3 co y
1-1 «
 ^-^

g
9* 4J
• to
-» o
r» O

01
I b
3
r-» to
o o
• fH
fH O *-*
01
X "O u
u n
0 u £
O tn i-!
C 3 u
• 	 CO
o -a oi
i^- to
 *-*


c
o
• tn
IN O
in u
vy
01
" S
r* to
0 0
• fH
iH O i~*
01
X 13 JJ
01 CO
CUE
O 01 -H
O 3 4J
• — 1 tO
o -o o
n to
 U £
IH e u
» e
ON JJ 00
tH CO 3

>> — ; to
re -o 3
z <


c
o
m
o
fH

4J
C
01
b
b
3
U

O
O
in

-»
fH


1
01
3
tH
CO
!>
u
e
01
b
b
3
tj




O
O
CO

ft

0)
3
fH
10
>
u
s
01
b
b
3
U





•0
B
 O
)H J->
4J n
- C 3
fH 0) b
tn e «
u
X *" 01
•H to j:
3 fcl 4J
n to
1 u-
CN to O
to oi
 oi
iH -H 3 01
01 fH 01
01 U tO u
c a) > to
3 b 3
b c *J
u-i Q D
O u b E
e b o
•a co 3 b
C b u IH
a u





0
o
m
v£>
fH


1
O
in
O
vO








O
o
in
•3-
fH

1
O
o
c*

>T










o
o
CO
fH

1
g
i-H
CM
rn
v>



















CN
00
^
tH
CM

U
U

S

<


^
4J
C
3
s
CO

u
o c
O OJ
C 6
* IX
Ov sC fl
f-H —
 o
o
1 0)
n




.*-.
c
3
O
5
w
c
a<
I
,x
m to
O\ O.
ej\ in
—t -*T3
•
01
^ u
u U
<:
o
u to
C -H
•H 3
s
4J b
C 0
§IH
>s ai
a js

T3 00
c c
o — ^
u »
11 3
CO
                                                                                                                       i—t     a    ^
                                                                                                                              o
                                                                                                                              o.

                                                                                                                             •a
                                                                                                                              3
                                                                                                                             —i
                                                                                                                             -a
                                                                                                                                    -
                                                                                                                                 O  fl  (N
                                                                                                                                    W  CO
                                                                                                                                 a)  ai  <^
                                                                                                                                 3  c. ^H
                                                                                                                                 r- »  C
                                                                                                                              (U  W  -4

                                                                                                                                 C  C  )-

                                                                                                                                 Ci  — t  O
                                                                                                                              3  U  aj  u

                                                                                                                             -»-l  IM  g  U

                                                                                                                                 3  CU  3
                                                                                                                                 u  u  u-i


                                                                                                                              QJ  0)  4J  C
                                                                       A-l

-------
       CO
       D
       H

       £
       W

       _1

       2
       U
T)    3
 (1)    M
 3    iJ
 c    q
•H    <
•u    W
 C    Q
X
M
Q



l/s.
4k
oe
c a
u. z
en C
u
H H
< en
a a
Of
c-t



a
i
u^
H-
Cfi *fc
S
oc
H





*r
ifc
§C
£
K E
i |






a
|
i»
H
(A «h
n
ae
H









en
u
z


M O
j g
i 3
i i



C
o o
o\
•9 *
V ^
>

V CM
U CM
01
M M
0)
w .a
•32
C ej
V 0
a.
a
«
u
1
1 —
U 4J
at m
§ * §
••«,* =>
iS §
« « 5
W U
3 3 1
am'
O 0
u "u




g
1
•5*
Of 03
O ON
Ot p*
M
u «*
+4
EX
»•«
at a
a> n
4)
4J
i
^i
*>
a
01 O

o"

•

G


u


01
a. ot
u c
<8 3 41
ffl 0»
n o -o
> CJ 01
— i >
(I 4J (0
u tn £
" *•£
frl5
2 * .5~
— 0» U -3
U b (0 U
t9 3 01 U
«- « «
o^a
0) •-« (A 01
u U O U
a

a
E

01
.a

n
I

4^
I
x
a
a.

§
o
^H
«>
0
1
O
o
o
o
o
4S>

X
J3

1
O
1
O
§
o
03
«v


fl
T3
C
3
«M

4J
(0
3
u
2
e
w

u-t Ji
•-I 9)
3 -C
01 O 01
o -a >
3 W -^
">««--
N U O^
X ffl 0) O*
J3 — M -4
U
O
1b ^^
J-, w
1 1
E I
g. S
^ ^ w
< « c
Su §
Ks |
- *" a
o ae a
" 2 *
n u
5 5
u
A
N
a tn
j=
iM U
-* V «
J 3
*C U
00 i-* X
25.2:
.» X
r»» 01 J3
M
h n •?
« a ai
JS S >
1 * -
0) «) 01 r*.
U 3 W GO
OJ 0 W 0*
a T3 H —

|M
O -^
"*-. u
e
w 3
1 I
01
a. M
c
•< u
2~ E
u n •»•
(CM a
m a
o —• n
-H n > 4J
••M «
AJ O U
e *«-
c
o a)
u oo
01 a) a)
w w ;-
« -H o
T; 
-a « u =1 U
3 u
no i ><
XTJ u .
« u o -• UJ
' 3- S3
2 2?£.
> » i-*
** i -5 -H 3
Si! S' £
- i 2 S.2
•^ 9 w O ***

OS
O
M
,
fN
CM
W
0)
JQ
O
4J
y
o


T3
* V
* b (
n g
CN o a
-S 5
x->- ° -s
tM T3 HI
O -^ « u
O <*> *j a
°. . S £
O -S, o
2 1 S
 %^





Fx
03
OS
-c
X
3
"6




01
* s^
N *^r
0 J w
*H § OH
X • «O AJ
•H 0) 01
O Q3 u 0)
O v> ai
O 3 w
* 1 *-. 0)
o ^ o
£ 3 °



e
0 01
n u
41 w a
w o -a
eg w
£ u 01
*« «J £
*J «*- « X
ft) e wi £
•ent of cost
the inflatio
anniversary o
ich the facll
ved a pemit
U 00 £ <*4
n Q jc a «
3 — o U
--t u q e «
•3 3 01 O W

I CM
O\
(N ON
» ^
O%
— H 0)

(• "}
Z

•sj
IQ e
e u



i
a
o c
> 0
CM
W fH
C «•
4t
U
t-
b
o


i
r^. o3
O3 O\
OS <-H
ki
U 0>
01 A
ja e
?!
if
"o °
•9
•o e
e u
u



•
01
3
f-t
(8 O
> O
OS
4j r-.
£«.
u
u
3

•Q
c
3
OJ IM Qf
J= e w
u M « -5 5
jZ n *Q M *n
<** *J 3 o> C
O U .C CJ «M 3
** u M (U Q M.
K 0 = U
O u O fi. Cl U
u 4j j; s w £
e c u u a j
2 3^ i °'-
«a«-* &°
oi a o) «*- *« « M
j= w = o a a e
W • ">4 ^01
>.. ;•§£ si
•"•« « "Jj-si
« « c o» 4 5 --
a w « JB o 4 x

^


>^s
rH
X

3
n

c
p^i
V*
O
5
-i
**i
C*4




w
(fl
3
U


01


payment into
•o
1
y>














^
c
3
u
n c
n E
- X
CM <5
>~* a

•^
01 ' S
I
1










^
3
3
i
S
OS S
03 >-
-4 a
OS CO —
«o-
-3
1 C
G
U
3J
31


IH
O

n u
x u
(C (0
~ "3
41
O X tr.
«
c n •
<3 H -U #
^ 01 C *
** > i *
i.'S 5.8
«> e « i
s « °-g>-
-i « u <
O u b IQ
U <*• 3
•S2 . E
3 •*• j; o
•*• (Q 4> >*•
                                                                                                                       5    I
                                                                                                                                    :  •  3
                                                                                                                                    .-« a
                                                                                                                                       i -o    £
                                                                                                                             M    M
                                                                                                                             M
                                                                                                                             3    •-* i
                                                                                                                            .s    -^  
-------




^

o c
u. g
Su.

HI H
< M
a i
H








a
£
H -H

5














_-

Q
S*
Z
H M
en oc

Oi E*4



PlH
M O <
3 BS H
b. co

S to J
M Id <
M U 06
§11
2 O o

CO Q)

r-t «H
41
* O
C 01
!-t W
U U
(U ^4
.a e
o u


^
g
O O)
a
D
U 0
§a •
as -H 0
<* v o
CD O •*« U -
« o a» « o
•H y s *A
4J * 01 «H 
a rsr u *j
Sm an
 u u v
0 6
41 4J u O
W 1 C « W
- « O 0)
1 « 
•a « a> j: «
< I CO J-t 1-










CR
OT
U
U
o
IM
a.
OP
c

iJ

1
91
a.
i
CO 00

^4 «~ 4

O X
C -H
3 J5


0 0

•o -c
££









§
0
CM
Vf

u
tl
3
<8



e
91

^
3



o -c
c
*J 3
C >4-*
QJ
a tn
u 3
a n


01 O
01
> u

01 rt 41
u a u
9t > 01
U 3
M I*
k. C U
O 01
SEI
O 3 M
U O «W
U

m
00
ON
f^i

•
rM

LI
n

3


0]
«
01
X

0 0
§ u
V> Q
>*4
u
" 1
11
§ c
o <
si g
ce
i
0 rt
O >H to
§ «

c c
m ^



c

i^

AJ
M
3
*J HC
o B

C U4 >•
^H CJ


= ta
1 1
ta u
B. O

U 01
•H 01
H

00

f>^


o
f-l

01
.2
c
LI
o
o


01
e
S

4J
a
01
01
a
u
91
hi
3

in <-4
•4 O 73
O 0)

• 01
O r» 3
O trt — i
o  13

C 1 •—
m



01 «
o u
•u O
at Lt
e u
0}
oi e
o
01 Lt
O ffl
U iH
U-i
u- c
O -H
4J 0)
c j:

S

01 C
3 -H
Tl 01
•a 3












u
u
o
c.
91
a

M
O
U
a
14-t
C
o
a

c
9J
4J

TJ
C
CO

X
a>
3
a
-o
3
itj




•








O

»-1

o
                                                            •3  «J
                                                         V   -  -*
                                                         4J   3  =
                                                         •Jl   U
                                                         O  .=  1 •*>
                                                         O  LI  U GO
                                                                •B ON
                                                         U  <-.  01 *4
                                                         u   O  X
                                                         O

                                                         O   (0
                                                                U  Ui
                                                                 -J  O
                                                                .2  *J
                                                         CU  »->   S  O
                                                         -i  =   S  S
                                                         Ul  01   C  **-
                                                         3  b
                                                         -^  1-   'J  *
                                                         •O  3  .=  3
                                                         «  O  4-1  -H
                                                        W >  >-  >«


                                                        1*         «
A-3

-------