United States        Office of Water and      SW 176C.12
           Environmental Protection    Waste Management      October 1979
           Agency          Washington, D.C. 20460

           Solid Waste
&EPA     European Refuse Fired
           Energy Systems

           Evaluation of Design Practices

           Volume 12

-------
                                 EPA
      and State. So Lid Woi-te Mana.gme.nt
        EUROPEAN REFUSE FIRED ENERGY  SYSTEMS

           EVALUATION OF  DESIGN PRACTICES

                 Copenhagen:  Amager
                 Denmark
    tnip tiapoit (SW-776c.72) deAUtibeA wctfe
the. 0^-tce ofa Sotid WaAta undent c.ontna.c.t  no.  6S-01-4376
and  izpfioducad 04 ^ecex.ued fitLom the. dont^actofi.
The. ^ndingA AhouJLd be. at&u.bute.d to the.  c.ontnjac.ton.
       and not  to the. fl^/cce ojj Bo Lid
         Copies  will  be available from  the
      National Technical  Information Service
             U.S.  Department of Commerce
               Springfield, VA  22161
                    Volume  12
      U.S. ENVIRONMENTAL PROTECTION AGENCY

                       1979
   i •,-  ',  ,-
      '•'(•<-•- -.,

-------
           This report was prepared by Battelle Laboratories, Columbus, Ohio,
under contract no.  68-01-4376.

           Publication does not signify that the contents necessarily reflect the
views and policies  of the U.S.  Environmental Protection Agency, nor does
mention of commercial products  constitute endorsement by the U.S.
Government.

           An environmental protection publication (SW-176C.12) in the solid waste
management series.
                               U.S. Environmental Protection Agency

-------
             TRIP REPORT
                 on



     COPENHAGEN:  AMAGER, DENMARK

           on the contract

  EVALUATION OF EUROPEAN REFUSE-FIRED
    ENERGY SYSTEM DESIGN PRACTICES

        in October 3-6, 1977

                 to

  U.S. ENVIRONMENTAL PROTECTION AGENCY


     EPA Contract No. 68-01-4376
         RFP No.  WA-76-B146

                 by

Philip R. Beltz and Richard B. Engdahl


           March 31, 1978
              BATTELLE
        Columbus Laboratories
           505 King Avenue
        Columbus, Ohio  43201

-------
                                 PREFACE

           This  trip  report  is one of a series of  15  trip  reports  on
 European waste-to-energy systems prepared for the U.S.  Environmental
 Protection Agency.   The overall objective of this investigation is to
 describe and analyze European plants in such ways that  the  essential
 factors in their successful operation can be interpreted  and  applied
 in various U.S. communities.  The plants visited  are considered from
 the standpoint  of environment, economics and technology.
           The material in this report has been carefully  reviewed by the
 European grate  or boiler manufacturers and respective American licensees.
 Nevertheless, Battelle Columbus Laboratories maintains  ultimate responsi-
 bility for the  report content.  The opinions set  forth  in this report are
 those of the Battelle staff members and are not to be considered  by EPA
 policy.
           The intent of the report is to provide  decision making  in-
 formation.  The reader is thus cautioned against  believing  that there is
 enough information to design a system.  Some proprietary  information has
 been deleted at the  request of vendors.  While the contents are detailed,
 they represent only  the tip of the iceberg of knowledge necessary to de-
 velop a reliable, economical and environmentally  beneficial system.
           The selection of particular plants to visit was made by Battelle,
 the American licensees, the European grate manufacturers, and EPA.  Pur-
 posely, the sampling is skewed to the "better" plants that are models of
 what the parties would like to develop in America.  Some  plants were selected
 because many features envolved at that plant.  Others were chosen because
 of strong American interest in co-disposal of refuse and  sewage sludge.
          The four volumes plus the trip reports  for the  15 European
 plants are available through The National Technical Information Service,
 Springfield,  Virginia  22161.   NTIS numbers  for the volumes and ordering
 information are contained in the back of this publication.  Of the 19
 volumes only the Executive Summary  and Inventory have been prepared for
wide distribution.

-------
                                    ii
                               ORGANIZATION
          The four volumes and 15 trip reports are  organized the  the
following fashion:

          VOLUME I

A  EXECUTIVE SUMMARY
B  INVENTORY OF WASTE-TO-ENERGY PLANTS
C  DESCRIPTION OF COMMUNITIES VISITED
D  SEPARABLE WASTE STREAMS
E  REFUSE COLLECTION AND TRANSFER STATIONS
F  COMPOSITION OF REFUSE
G  HEATING VALUE OF REFUSE
H  REFUSE GENERATION AND BURNING RATES PER PERSON
I  DEVELOPMENT OF VISITED SYSTEMS

          VOLUME II
J  TOTAL OPERATING SYSTEM RESULTS
K  ENERGY UTILIZATION
L  ECONOMICS AND FINANCE
M  OWNERSHIP, ORGANIZATION, PERSONNEL AND TRAINING

          VOLUME III

P  REFUSE HANDLING
Q  GRATES AND PRIMARY AIR
R  ASH HANDLING AND RECOVERY
S  FURNACE WALL
T  SECONDARY (OVERFIRE) AIR

          VOLUME IV

U  BOILERS
V  SUPPLEMENTARY CO-FIRING WITH OIL, WASTE OIL AND  SOLVENTS
W  CO-DISPOSAL OF REFUSE AND SEWAGE SLUDGE
X  AIR POLLUTION CONTROL
Y  START-UP AND SHUT-DOWN
Z  APPENDIX

-------
                            TABLE OF CONTENTS
LIST OF PERSONS CONTACTED, REFERENCED, OR CONSTRUCTION
  PARTICIPANTS 	    1

     Addresses 	    1

STATISTICAL SUMMARY	    3

OVERALL SYSTEM SCHEMATIC 	   15

COMMUNITY DESCRIPTION	   17

     Geography	   17

SOLID WASTE PRACTICES	   20

     Solid Waste Generation	   20

     Solid Waste Collection	   22

     Solid Waste Transfer	   22

     Provisions to Handle Bulky and Noncombustible Wastes	   24

     Solid Waste Disposal	   24

DEVELOPMENT OF THE SYSTEM	   28

     Recommendations for System Development in North America 	   31

PLANT ARCHITECTURE AND AESTHETIC ACCEPTABILITY 	   33

TOTAL OPERATING SYSTEM 	   37

     Maximum Rated Capacity	   37

     Forms of Operation	   40

     Operating Hours 	   41

     Problems	   43

          Old Problems	   43

          Continuing Concerns	   43

-------
                             TABLE OF CONTENTS
                                (Continued)


                                                                     Page

REFUSE-FIRED HOT WATER GENERATOR EQUIPMENT 	  .  	   44

  Waste Input	44

  Weighing Operation 	  	   46

  Waste Storage and Retrieval	48

  Furnace Hoppers, Feeders, and Swivel Gate	52

  Primary (Underfire) Air	52

  Secondary (Overfire) Air 	   56

  Boiler Room Cool Air	56

  Flue Gas Recirculation Hot Air	56

  Flue Gas Fan	58

  Fan Summary	58

  Furnace Combustion Chamber 	   60

  Burning Grate (Forward Pushing Step Grate)  	   60

  Furnace Refactory Wall 	   69

  Rotary Kiln	71

  After Burning Chamber	75

  Boiler (General) 	   76

  Convection Section 	   79

  Economizer	81

  Boiler Water Treatment 	   81

  Cofiring	•	81

ENERGY UTILIZATION EQUIPMENT 	   83

  More of Mr. Blach's Comments on Heat Exploitation	85

-------
                            TABLE OF CONTENTS
                               (Continued)

                                                                        Page

 POLLUTION  CONTROL EQUIPMENT	    89

     Air Pollution	    89

     Water Pollution	    92

 ASH HANDLING AND DISPOSAL	    93

CHIMNEY •	    93

 PERSONNEL  AND MANAGEMENT	    98

     Personnel	    98

     Management	    98

 ECONOMICS	100

     Capital Cost (Assets and Liabilities)  	  100

     Annual Costs (Expenses and Revenues)	100

     Profitableness at Exploitation of Heat	106

FINANCE	HI

REFERENCES	112

                             LIST OF TABLES

 TABLE  14-1.   Population and Refuse Consumption in the Copenhagen
                Immediate Metropolitan Area	    21

 Table  14-2.   Primary, Secondary, Flue Gas  and Recirculation
                Fan Parameters	    59

 Table  14-3.   Assets  (March 31, 1976) at Copenhagen:Amager  	  101

 Table  14-4.   Liabilities (March 31, 1976)  at Copenhagen:
                Amager	102

 Table  14-5.   Annual  Costs During 1975-1976 at Copenhagen:
                Amager	103

 Table  14-6.   Revenues During 1975-1976 at  Copenhagen:
                Amager	104

-------
                             LIST OF TABLES
                               (Continued)
Table 14-7.   Annual Costs and Revenues at Copenhagen:
                Amager	105

Table 14-8.   Operational Costs (Exclusive of Interest  and
                Depreciation) and Income by Heat Sale From
                a Plant with Three Furnaces of 12 t/h for
                Variable Net Calorific Values of Refuse and
                Degree of Incineration Capacity	107

Table 14-9.   Operational Costs (Exclusive of Interest  and
                Depreciation) and Income by Heat Sale From
                a Plant with Two Furnaces of 3 t/h for
                Variable Net Calorific Values of Refuse and
                Degree of Incineration Capacity	.108

                            LIST OF FIGURES

Figure 14-1.   Engineering Drawing of Copenhagen:Amager	    16

Figure 14-2.   Map of Copenhagen, South and East Metropolitan
                 Area Served by the Amager Plant	    18

Figure 14-3.   Copenhagen:Amager Plant Located on Canal	    19

Figure 14-4.   Transfer Station Under Construction at Amager 	    23

Figure 14-5a.  Ramp Leading to Transfer Station	    25

Figure 14-5b.  Bulky Waste Being Dropped into the Von Voll
                 Scissor Shear 	    25

Figure 14-5c.  Trailer Load from the Transfer Station Being
                 Weighed Before Transport to the Uggelose
                 Landfill	    25

Figure 14-6a.  Landfill Operations at Uggelose, Denmark	    27

Figure 14-6b.  Landfill Operations at Uggelose, Denmark.  . . 	    27

Figure 14-7.   First Volund System Built at Gentofte in 1932 and
                 Decomissioned 40 Years Later in 1972	    29

Figure 14-8.   Volund's Procedure for System Development 	    32

Figure 14-9.   Copenhagen:Amager Plant Located at Sea Level	    34

-------
                            LIST OF FIGURES
                               (Continued)

                                                                       Page

FIGURE 14-10a.  Control Room at Copenhagen :Amager	   36

Figure 14-10b.  Lobby Entrance 	   36

Figure 14-10c.  Cafeteria	   36

Figure 14-10d.  Conference Room	   36

Figure 14-11.   Maximum Rated Capacity on Volund Rotary
                  Kiln Furnaces	   38

Figure 14-12.   Total (Three Lines) Operation Hours per Month.  .....   42

Figure 14-13.   Monthly Tonnage of Industrial1, Household, and
                  Total Refuse Weighed at the Copenhagen:
                  Amager Scales	   45

Figure 14-14a.  Scale House and Two Scales 	   47

Figure 14-14b.  Plastic Card 	   47

Figure 14-14c.  Monitor in Control Room of Truck Scale 	   47

Figure 14-14d.  Digital Readout in Scale House 	   47

Figure 14-14e.  Ramp to Tipping Floor	   47

Figure 14-14f.  Tipping Floor	   47

Figure 14-14g.  Tip Arrangement Permitting Good Crane View 	  .   47

Figure 14-15a.  Tipping Door that can Close	   49

Figure 14-15b.  Crane Operator Controlling Polyp Towards Hopper. ...   49

Figure 14-16a.  Sven Polyp Grab at Copenhagen:Amager Going
                  Down for Another Load	   51

Figure 14-16b.  Schematic of Polyp 	   51

Figure 14-17.   Sloping Air Intake Filters Above the Bunker at ,
                  Copenhagen:West Only (Raised Intakes at Amager).  .  .   54

Figure 14-18.   Original and Raised Position of the Primary
                  Air Intake	   55

-------
                            LIST OF FIGURES
                              (Continued)

                                                                       Page

Figure 14-19.   Six Dilution Sidewall Secondary Overfire Air
                  Jets at Copenhagen :Amager	   57

Figure 14-20.   General Design Configurations for Volund Furnaces. .  .   61

Figure 14-21.   Furnace Design (Two-Way Gas Grate and Rotary
                  Kiln) at the Old (1934) Frederiksberg Plant,
                  Dismantled in 1970	   62

Figure 14-22.   Volund's Lengthwise Placed Section of Grate	   64

Figure 14-23.   Volund's Movable Sections Hydraulically Driven
                  by a Transverse Driving Shaft Connected to
                  the Individual Sections by Pendulum Driving
                  Bars	   65

Figure 14-24.   One of the Earliest Volund Patents 	   66

Figure 14-25.   Grate Furnace Exit Into a Rotary Kiln at One
                  of Volund's Plants	   68

Figure 14-26.   Rotary Kiln Being Repaired at Copenhagen:Amager.  ...   73

Figure 14-27.   Two Support Rings of a Volund Rotary Kiln	   74

Figure 14-28.   After Burning Chamber and Boiler at Copenhagen:
                  Amager	   77

Figure 14-29.   Amager Boiler Design 	   80

Figure 14-30.   Copenhagen: Amager's Refuse Fired Energy Plant
                  in the Foreground and the Oil (or Coal?)
                  Fired Plant in the Background	   84

Figure 14-31a.  Insulated Hot Water Pipes Leaving Boiler 	   86

Figure 14-31b.  Map of District Heating Network	   86

Figure 14-31c.  Pumps to Send Hot Water to the Power Plant
                  Which Sends the Hot Water to the District
                  Heating Network	   86

Figure 14-32.   Energy Delivery to the District Heating Network.  ...   87

Figure 14-33a.  Rubber Ash Conveyor at Copenhagen:Amager 	   94

-------
                            LIST OF FIGURES
                              (Continued)

                                                                       Page

Figure 14-33b.  Ferrous Separation From Ash at CopenhagenrAmager ...   94

Figure 14-34.   Patent for Volund's Ash Sluice and Pusher	   95

Figure 14-35.   Ash Chute and Skip Hoist at Copenhagen:Amager	   96

Figure 14-36.   Management Structure of Copenhagen:Amager	   99

-------
   LIST OF PERSONS CONTACTED. REFERENCED. OR CONSTRUCTION PARTICIPANTS
Gabriel Silva Pinto


M. Rasmussen


Evald Blach
Jorgen Hildebrandt
Per Nilsson



Thomas Rosenberg
Architect
Consulting Building Engineers
Consulting Mechanical Engineers
Project Manager, Main Plant
  Layout, Volund
Chief Engineer, Sales Activities
  Volund
Former Chief Engineer, Volund
Plant Manager, Amager Plant
Chief of Development Department
  Civil Engineer of the
  Renholdnings Selskabet
Sales Manager, International
  Incinerators, Inc., Atlanta,
  Georgia,
J. Maglebye Architectural Office
Ramboll & Hannemann
Copenhagen Gas and Electricity
  Services
                                   Addresses
Refuse Fired Hot Water Generation Plant
Amager Forbraending
Kraftverksvej
2300 Copenhagen S
Denmark
Tele:  (01) 950351

Vendor Headquarters
A/S Volund
11 Abildager
2600 Glostrup
Denmark
Tele:  02-452200
Telex:  33130 Volund Dk

Collection Organization
Renholdnings Selskabet
Since 1898
8-10-16 Kraftuaerksvej
2300 Copenhagen S
Amager Island
Denmark
Tele:  08233-5171
     American Coordinating Firm
        Mr. Gunnar Kjaer, President
        Volund USA Ltd.
        900 Jorie Boulevard
        Oak Brook, Illinois  60521
        Tele:  (312) 655-1490
        *This firm is owned by:
        1.  Volund A/S (Denmark)
        2.  Waste Management, Inc.
        3.  Jack Lyon & Assoc.
  American Sales Representative
        Mr. Ronald Heverin
        Director of Marketing
        Advanced Systems Group
        Waste Management, Inc.
        900 Jorie Boulevard
        Oak Brook, Illinois  60521
        Tele:  (312) 654-8800

-------
WEKA-VERLAG Gmbh
8901 Kissing
Augsburgerstrasse 5
Germany
F.L. Smidth & Co.
11 West 12 Street
New York City, New York

Danish Boiler Association
Dansk kedel Forening
Sankt Pedersvej 8
2900 Hellerup
Denmark
Tele:  (01)629211

-------
                             STATISTICAL SUMMARY

GENERAL
  Name of plant                                Amager Plant
  Location of plant                                Copenhagen, Denmark
  Year completed                                            1970
  Administration/Ownership         Communities of interest consist of
                                   several municipalities including
                                   parts of Copenhagen
  Area of plant                               approx. 3*1,000 m^
  Area of building                            approx. 19,000 m^
  Cost of construction, including              approx. 115,000,000 D%Kr.
    a building

Design Data
  Plant capacity
    Annually                                 220,000 - 330,000 tonnes/yr
    Daily                                             864 tonnes/24 h
  Capacity, each furnace
    Daily                                             288 tonnes/24 h
    Design hourly                                      12 tonnes/hour
    Actual hourly                                      13 tonnes/hour
   Number of furnace
    Operating                                           3
    Stand-by                                            0
    Extension potential                                 3
  Calorific value of refuse (design)
    Lowest (design)                                 1,000 kcal/kg
    Average (design)                                2,000 kcal/kg
    Highest (design)                                2,500 kcal/kg
    Calorific value of refuse (actual)              1,800 kcal/kg

-------
Composition of Refuse

    Combustibles
    Ash and inerts
    Water
  Furnace temperature
    Minimum
    Average
    Maximum
  Contents of unburnt matter in residue
Lowest
26$
42$
32$
Average
45$
26$
29$
Highest
55$
22$
23$
          800 C
          950 C
        1,000 C
         0-3$
OPERATION OF PLANT
  Cost of operation and maintenance
  Number of operators and workers
  Number of officers
  Operating hours of plant
  Working hours of operators
  Number of shifts
  Electric power consumption
  Water consumption
    City water (excluding sea water) for
      clinker cooling
  Actual continuous operating time
  Actual operating days
  Maintenance and repair of plant
    Regular or periodical overhaul and
      repair including mechanic, electric,
      and boiler systems
  D.Kr.  35/tonne of refuse
            45
            10
24 hours/day 7 days/week
 8 hours/day 5 days/week
             5
     1,000,000 KwH/month

       7,000 tonnes/month

       approx. 12 weeks
       365 days/year

        normal
REFUSE COLLECTION AND TRANSPORTATION
  Population in refuse collection region
    of the plant
  Area of refuse collection of the plant
  Amount of refuse collected, presently
  Disposal of refuse
    Incineration
        550,000-600,000

           138 km2
      1,400-1,000 tonnes/day

              50$

-------
    Dumping at sea                                         0$
    Reclamation                                            0%
    Other:/dump/ industrial refuse                        50$
  Method of transportation                             Truck
  Charge of collection                              Charged 30 D.Kr./t.

REFUSE STORING
  Weighing equipment of refuse
    Number                                              2
    Type                                            Automatic
    Capacity                                        50 tonnes
    Recording, printing, and summation              Automatic
      of weight
  Refuse silo (bunker)
    Number                                              1
    Capacity                                       10,000 m3
    Dimension
      Length                                           48 m
      Width                                            17 m
      Depth                                            13 m
    Specific weight of refuse                       0.2-0.3 tonnes/m^
    Storing capacity                         3 days max. refuse delivery
  Refuse silo door
    Type                                     Flap,  double-hinged
    Number                                             11
    Dimension
      Height                                            8.0 m
      Width                                             3.8 m
      Thickness, total                                122 mm
    Operation                                       Hydraulic
    Capacity                                        10,000 m3
  Big refuse crusher                                None

REFUSE FIRING PLANT
  Furnace
    Filling hopper

-------
    Number
    Clear opening at top
    Clear opening at bottom
    Height
    Thickness of plate
    Materials
    Volume
  Filling chute
    Number
    Clear opening
    Height
    Thickness of plate
    Volume
  Swivel gate in filling chute (damper)
    Number
    Dimension
    Thickness
    Operation
Grate I
  Width of grate
  Length of grate
  Area
  Velocity of grate
  Length of grate stroke
  Type of grate
  Materials of grate
    Grate frame
    Grate bar or plate
    Side seal
Grate II
  Width of grate
  Length of grate
  Area
  Frequency of grate
  Length of grate stroke
  Type of grate
   1  per furnace
   6  m x 6 m
   2.3 m x 1.15 m
       6 m
       8 mm
   Mid steel
      15 m3

       1
   2.3/2-7 m x 1.15 m
       8.5 m
       8 mm
      19 m3

       1
   2.58 m x 1.26 m
      10 mm
      Manual

       2.7 m
       2.5 m
       6.75 m2
   3 stroke/min.
     130 mm
Grate bar, grate plate

   Meehanite HR
   Meehanite HR
   Nicromax

       2.7 m
       2.0 m
       5.4 m2
   3 stroke/min.
      130 mm
   Grate bar

-------
  Materials of grate
    Grate frame
Grate III
  Width of grate
  Length of grate
  Area
  Velocity of grate
  Length of grate stroke
  Type of grate
  Materials of grate
    Grate frame
    Grate bar or plate
    Side seal
Grate IV
Rotary kiln
  Shape
  Diameter
    Inside of shell
    Inside of lining
  Length
  Volume
  Number of revolutions
    Range
    Normal
  Inclination
  Materials of shell
  Materials of support ring
  Materials of support roller
  Materials of thrust roller
  Number of support rings
  Number of support rollers
  Number of thrust rollers
  Number of drive support rollers
Steps between grates
  Number of steps
  Height of steps between Grate I
                Meehanite HR

                    2.7 m
                    5.0 m
                   13.5 m2
                3 stroke/min.
                  130 mm
             Grate bar, grate plate

                Meehanite HR
                Meehanite HR
                Nicromax
                None

                Cylindrical
m
                      m
                    3.1
                    8 m
                   73 m
                0-12 rph
                6-8 rph
                    3 deg.
                DIN 42.2 steel
High tensile strength steel castings
High tensile strength steel castings
High tensile strength steel castings
                    2
                    2
                    1
                    2

                    2
                    1.0 m

-------
    and Grate II
  Height of steps between Grate II
    and Grate III
Steps beetween grate and rotary kiln
  Number of steps
  Height of step
  Width of steps
Hopper under grate
  Number
  Thickness of plate
  Size of chute
Clinker chute
  Clear opening (or 100 ?)
  Height
After combustion chamber
  Volume
Hydraulic equipment for grate movement
  and rotary kiln
  Number per furnace
  Hydraulic pump
    Number per furnace
    Capacity
    Pressure
    Motor
  Oil tank
  Hydraulic cylinder
                               Grate I
            2.0 m
            1
            1.0 m
            2.7 m
            6 mm
        240 x 240 mm

        900 mm x 1 ,000 mm
        1 ,900 mm

          125 m3
        1  set/furnace

   Operating 2, standby 0
   47 lit/min. each pump
           70 kg/cm2g
           15 HP each
          600 liters

Grate II    Grate III
    Number
    Cylinder bore
    Cylinder stroke
  Hydraulic motor for rotary kiln
    Number per kiln
    Revolution
    Torque
  Speed reduction equipment
    Type
5
80 mm
130 mm
5
80 mm
130 mm
5
85 mm
130 mm
        max. 1,200 rpm
            3 kg-m

        Double worm gear

-------
     Number per kiln
     Revolution
     Torque
     Ratio of reduction
  max.  76 rph
  1,272 kg-m
     1:800
VENTILATING AND DRAFTING PLANT
 Primary air (P.D. Fan)
   Manufacturer
   Number per furnace
   Amount of air
   Static pressure
   Temperature
   Number of revolutions
   Drive type
   Motor size
 Secondary air fan (cooling air  fan)
   Number per furnace
   Amount of air
   Static pressure
   Temperature
   Number of revolutions
   Drive type
   Motor size
 Flue gas fan (I.D. Fan)
   Number per furnace
   Amount of gas
   Static pressure
   Temperature
   Number of revolutions
   Drive type
   Motor size
 Recirculation fan
   Number per furnace
   Amount of air
   Static pressure
   Temperature
  Nordisk Ventilator
      1
 45,000  Nm3/h
    230  mmAq
     30  C
  1,490  rpm
  Belt drive
     75  HP

      1
 35,000  Nm3/h
    460  mmAq
     30  C
  1,670  rpm
  Belt drive
    150  HP

      1
107,000  Nm3/h
    170  mmAq
    350  C
  1,010  rpm
  Belt drive
    220  HP

      1
 45,000  Nm3/h
    220  mmAq
    350  C

-------
                                   10
    Number of revolutions
    Drive type
    Motor size
  Cooling air fan for by-pass damper
  Steam air heater
     1,1160 rpm
     Belt drive
       150 HP
     None
     None
CHIMNEY
  Chimney
    Type
    Number
    Diameter at top
    Height
    Gas velocity at top
Concrete with steel flue
     1 per 4 furnace
         2.8 m
       150 m
     max. 27 m/sec
AUXILIARY BURNING PLANT FOR FURNACE
     Not necessary
DUST COLLECTING PLANT
  Electrostatic precipitator
    Number per furnace
    Capacity
    Gas temperature
      Operating
      Maximum
    Dust content
      Inlet
      Outlet
    Efficiency
    Pressure drop
  Multi-cyclone
   107,000 Nm3/h

       300 C
       350 C

         7.5 g/Nm3
         0.15 g/Nm3
        98*
       5-10 mm water
     None

-------
                                      11
CLINKER AND FLY ASH TRANSPORTATION PLANT
  Clinker transportation equipment under
    clinker chute
    Type                                    Submerged conveyor stainless
                                            steel laminated
    Number per furnace                                  1
    Capacity                                            M tonnes/h
    Speed                                               3 m/min
    Width                                               1.1 m
    Length of traveling                                13 m
  Ash transportation equipment under grates
    and rotary kiln
    Type                                            Vibration conveyor
    Number per furnace                                  1
    Capacity                                            0.6 tonnes/h
    Speed                                           .6 - 1.2 m/min
    Width                                           diam. 300 mm
    Length                                             1H.5 m
  Ash transportation equipment under
    boiler or gas cooler
    Type                                    Vibration conveyor (screw
                                            conveyor submerged stainless
                                            steel
    Number per furnace                                  1
    Capacity                                            0.6 tonnes/h
    Speed                                           .6 - 1.2 m/min
    Width                                           diam. 600 mm
    Length                                              6.3 m
  Fly ash transportation equipment under
    Dust collector
    Type                                            Fluidizing
    Number per furnace                                  if
    Capacity                                            0.6 tonnes/h

-------
                                  12
  Specific weight of clinker
  Storing Capacity
Clinker transport
  Number
  Type
  Length of traveling
  Width
  Speed
Disposal of clinker and fly ash
             1.0 tonnes/m3
             4 days

         1 plus 1 stand-by
    Laminated steel conveyor
            50 m
             1 m
             3 m/min.
         Landfill
Boiler
  Method of gas cooling
  Boiler
    Type
    Number per furnace
  Design pressure
  Working pressure
  Hot water temperature
  Feed water temperature
  Capacity
  Heating surface
    Radiation heating surface
    Convection heating surface
    Superheater
    Economizer (Normal steel tubes)
    Economizer (Casted steel)
    Gas air heater
  Gas temperature
    Inlet
    Outlet
         Waste heat boiler

Hot water boiler water tube
             1
            16 kg/cm2g
             6 kg/cm^g
           120 C
            75 C
         21.5 x 106 kcal/h

           330 m2
           330 m2
         None
           H55 m2
           720 m2
         None

           800 C
         280 - 320 C

-------
                                  13
Clinker transport
  Number
  Type
  Length of traveling
  Width
  Speed
Disposal of clinker and fly ash
         \  plus 1 stand-by
    Laminated steel conveyor
            50 m
             1 m
             3 m/min.
         Landfill
Boiler
  Method of gas cooling
  Boiler
    Type
    Number per furnace
  Design pressure
  Working pressure
  Hot water temperature
  Feed water temperature
  Capacity
  Heating surface
    Radiation heating surface
    Convection heating surface
    Superheater
    Economizer (Normal steel tubes)
    Economizer (Casted steel)
    Gas air heater
  Gas temperature
    Inlet
    Outlet
  Amount of gas
    Lowest calorific value
    Average calorific value
    Highest calorific value
  Boiler outlet gas temperature control
  Heat utilization
Water spray gas cooler
         Waste heat boiler

Hot water boiler water tube
             1
            16 kg/cm2g
             6 kg/cm2g
           120 C
            75 C
         21.5 x 106 kcal/h

           330 m2
           330 m2
         None
           1J55 m2
           720 m2
         None

           800 C
         280 - 320 C

          33,000 Nm3/h
          77*000 Nm3/h
          98,500 Nm3/h
         Yes, automatic
         District heating
         None

-------
                                   14
Boiler cleaning equipment
  Type                                            Shot cleaning
Soot blower                                       None

Hot water cooler
  Type                                            Air cooler
  Number                                              2
  Capacity                                          370 tonnes/h
Heat exchanged                                    18.3 x 106 kcal/h
Hot water temperature
  Inlet                                             115 C
  Outlet                                             60 C
Hot water pressure                                   10 kg/cm^g

-------
                                     15
                         OVERALL SYSTEM SCHEMATIC

         Figure  14-1  shows  the cross-sectional schematic  of the
Copenhagen: Amager plant  designed and built by Volund A/S.
                           COMMUNITY DESCRIPTION

                                  Geography

          Figure  14-2  is  a map of the Copenhagen metropolitan area.
 Copenhagen itself  is  located on the east coast of Denmark, not far from
 Sweden.
          The Amager refuse-fired steam generator is  shown at the north
 end  of Amager Island just southeast of downtown Copenhagen.  Its twin  unit
 "Vest" or "West" described in Trip Report 15.
          The terrain is rather flat,  which is typical  of eastern Denmark.
 The Amager plant  (see  Figure  14-3) is  located  right on the  canal
 separating Amager Island from the main Danish  island to Amager's north.
 Amager  Island  was originally  unimproved  swamp  land that has  been
 "poldered" with pilings, dykes, and debris fill over many centuries. Being
 at sea level did interfere with construction in two ways.  First,  numerous
 pilings had to be sunk.  Secondly,  the refuse bunker pit  had to be shallow
 and  encased in special water protective coatings.
          The population in the City of Copenhagen proper has fallen  from
 550,000,  10 years ago, to 430,000 presently.  Reasons  are typical of those
 in many large cities.  Basically young families are moving to the suburbs,
 leaving  the city for students,  government workers, retired people, and
 those wishing a  short  commute to work.  The  Amager  plant serves about
 620,000  people  in central, east, and southern Copenhagen and those
 residents of the Amager Island.

-------
16
                                                  w
                                                  e>
                                                  w
                                                  o

                                                  o
                                                  o
                                                  M

                                                  !
                                                  Q
                                                 w
                                                 w
                                                 SB

-------
                                          17
       NT-
                                * x,  *•    •  \\  •/  <  I       >••"''   '  r,   ':v
                             X '   ~\        H  ',(  fHEUERUP  «•''„>  I   ^   '/

                            - '"-    \        ^  4,)W  /'' >-''  !     <7
                                 ^       » —'—~-\^ ,'« ^O'' 3f'"    ''  /y x'^'^         ;''
                \
if'v^v-/
^',^/ A \
/,•=;
i ^-
\j
Ci
f
y.
^
S a I t h
                                                                                    Plant
West Refuse Plant
        FIGURE 14-2.   MAP OF COPENHAGEN, SOUTH AND EAST METROPOLITAN  AREA
                       SERVED BY THE AMAGER PLANT

-------
                             18
FIGURE 14-3.  COPENHAGEN:AMAGER PLANT LOCATED ON CANAL

-------
                                     19
                           SOLID WASTE PRACTICES

                           Solid Waste Generation

          The "immediate"  Copenhagen metropolitan area, as served  by the
two large  Volund plants  (Amager and West),  has  a total  population of
1,137,978  and generates 509,246 tonnes (560,171 tons) per year as  shown in
Table 14-1.
          Five  communities  sent 253,439  tonnes  (278,783 tons)  to
Copenhagen:  Amager during the 1975/1976  fiscal year. On  a  7-day  burning
basis, about 694 tonnes  (763 tons)  per day  were consumed. These figures
compare with the  rated capacity of 864  tonnes  (950 tons).
          Collections are  higher than  the national average from  offices,
stores, etc.  However, household waste  collections are lower than  normal.
Bulky  and  garden waste is  collected separately  and usually landfilled.
Only 9 percent of Copenhagen's residents have gardens.  Vegetative waste
amounts to 10 percent of the total household waste as an annual average.
          Household generation rate figures were provided as follows:

          City of Copenhagen               0.8 to 1.0 kg/person/day
          Suburbs                         1.2 to 1.5 kg/person/day
          Metropolitan Area                1.0 to 1.4 kg/person/day

          In 1975-1976, households in  the Amager district generated 351 kg
per person.   Adding commercial and  industrial refuse brings the  total to
466 kg per person. This  translates to  a combustible receivable  rate of
1.226 Kg  (2.7 pounds per day)/person day.
          The refuse composition has been changing over the years to about
these figures:

                            1964/1965         1970
Heat Value (kcal/kg)           1,600      1,800-2,000
Moisture  (percent)                35           33
Combustibles (percent)            40           45
Noncombustibles  (percent)         25           22           23

-------
                                   20
      TABLE 14-1.   POPULATION AND REFUSE CONSUMPTION IN THE  IMMEDIATE
                   COPENHAGEN METROPOLITAN AREA
Population (Inhabitants)
I/S Amager Area
I/S Vest* Area
TOTAL
Refuse Consumption (Tonnes)
I/S Amager Plant
I/S Vest Plant
TOTAL
April 1, 1974
524,955
581,333
1,106,288
1974-1975
224,449
215,224
439,673
April 1, 1975
580,556
575,996
1,156,552
1975-1976
255,488
234,230
489,718
April 1, 1976
568,343
569,635
1,137,978
1976-1977
255,807
253,439
509,246
* Vest is translated to West.

-------
                                  21

                           Solid Waste Collection

          Delivery is by local garbage  trucks.   Therefore,  there  is
little,  if any, bulky waste  burned.
          The  overall cost for collection and  disposal averages about 465
D.Kr.  ($95) per year per person throughout  Denmark.
          Waste has been  collected since  1898 by a not-for-profit society,
Renholdnings  Selskabet.  Much could be  written  regarding  this  very
successfful  organization. One  item of interest is that  each walking
collector  has a computer printout that tells him exactly how many  Danish
Kroner  he  will earn by  "traveling  17 horizontal steps, three vertical
steps, picking  up a 10 liter can ...".

          Comment:  We are unaware of any  collection system as detailed and
          filled with motivational factors  as the system at Renholdnings.
          Further information is available.

                           Solid Waste Transfer

          The  transfer activity at Amager  is unlike that  of West.  A large
transfer station is shown  under construction in  1974 in Figure  14-4.   The
area's  industrial waste  and household bulky waste is taken to  this
transfer station located on  the grounds of  the  Amager plant. Some  of the
waste is  then  transferred  to the Uggelose landfill located  37 km (23 mi)
northwest  of Amager and inland. During 1975-1976,  32,374 garbage  trucks
entered the transfer  station.  Some combustible waste  was taken to the
refuse burning plant.   About 13,723 transfer trailer loads were taken  to
the Uggelose landfill.

         Hazardous waste collected at the Amager  plant  is  later
         transported to the Federal hazardous  waste treatment center  at
         Nyborg,  Denmark.

-------
                              22
FIGURE 14-4.
TRANSFER STATION UNDER CONSTRUCTION AT AMAGER.
PHOTO TAKEN FROM WINDOW AT THE AMAGER REFUSE
BURNING PLANT.  THE STORAGE YARD OF THE
RENHOLDNINGS SELSKABET COLLECTION ORGANIZATION
IS SHOWN IN BETWEEN.

-------
                                    23
              Provisions to Handle  Bulky and Noncombustible  Wastes

          Homeowners must call the city of  residence if they  wish their
bulky waste  picked up.
          The self-contained Amager plant  itself has no  provision to
handle bulky wastes.  As  previously stated,  adjoining the  plant  is the
transfer  station. Trucks with bulky or noncombustible loads  are weighed at
the same scale as is household refuse. Referring back to the  aireal photo
in Figure  14-3,  the trucks  behind of the chimney,  up and around to the
left out of  the picture, and to the  transfer station.
          Figure  l4-5a shows the ramp leading to the completed  station. An
operator is  about to dump a load of  bulky material into a Von Roll  scissor
shear  in  Figure  14-Sb. Size reduced combustible material  is  then hauled
directly  to the  refuse  burning plant.  If  most  of  the  material is
noncombustible,  it is compacted,  weighed (see Figure l4-5c),  and  sent to
the Ugglose  landfill (30 km (19 mi)  northwest of Amager.
          The Von Roll shear can process up to 80 m3/hour (105 yd3/hour).
It operates  intermittently and has a hydraulic drive.  One  man  operates
the  crane  and  shear on the  day shift.   The  maintenance record has  been
very good.

                            Solid Waste Disposal

          The greater* Copenhagen metropolitan area is now served  by eight
refuse-fired energy plants.  All of the following are within  a 32 km (20
mi) semicircle radius of Copenhagen:
          •   Vest (West)
          •   Amager
          •   Brondby
          •   Taastrup
          •   Roskilde
          •   Albertslund
          •   Horsholm
          •   Helsinor
   *"Greater" metropolitan  area with 8 plants is  differentiated from the
    "Immediate" Copenhagen  metropolitan area having only  the Amager and West plants.

-------
                                       24
FIGURE 14-5a.   RAMP LEADING TO TRANSFER STATION
                                       FIGURE 14-5b.   BULKY WASTE BEING DROPPED
                                                      INTO THE VON ROLL
                                                      SCISSOR SHEAR
 FIGURE 14-5c.
TRAILER LOAD FROM THE TRANSFER STATION BEING WEIGHED BEFORE
TRANSPORT TO THE UGGELOSE LANDFILL

-------
                                       25
          Figures 1^-6a and l4-6b show landfill  operations at the Uggelose
site northwest  of Copenhagen.
          In previous years, composting was  practiced at two sites west of
Copenhagen.   Eventually,  there was  some talk about mercury and cadmium
content.   Perhaps too, the market for compost material was not great.  For
whatever reasons, it was  closed.   Now,  however, as is  often the  case,
composting  is  returning at a new site northwest  of Copenhagen beginning in
January, 1978.

-------
                                 26
   FIGURE 14-6a.  LANDFILL OPERATIONS AT UGGELOSE, DENMARK

FIGURE 14-6b.  LANDFILL OPERATIONS AT UGGELOSE, DENMARK:

-------
                                    27
                          DEVELOPMENT OF THE SYSTEM

         Waste-to-energy began in Copenhagen in  the early 1930's with the
1932  commissioning  of the  two 144-tonne  (158 ton)  per day Volund
grate/rotary kiln furnaces at Gentofte, each with a three-drum  boiler as
shown in Figure  14-7. The steam was used to make electricity as specified
by the city's  Electrical  Board.  This construction was  followed by two
similar Volund units at Frederiksberg in 1934.
         These two plants  served  Copenhagen well for 40  years. During
that  time,  these plants  had  reached their capacity. Therefore excess
refuse had to be landfilled both  inland and on  the sea coast.  Referring
back  to the map,  Figure  14-2, notice the large undeveloped area  in the
western part of Amager Island.  This was basically low swamp  land that has
been filled in with both demolition debris and household refuse.
         During the 1960's, when knowledge of landfill leachate damages
became better  known and when neighbors became upset over blowing  trash,
etc.,  local citizens groups on  Amager Island were effective in getting the
attention of elected officials.
         For  a  time,  it seemed  that  each  community wanted to
independently solve its solid waste disposal problems. Finally, one of the
island communities decided to  build a resource recovery plant. Others soon
followed. Eventually the City of Copenhagen joined in the development.
         Incidentally,  the  excitement  about Amager encouraged the
residents west of Copenhagen to develop a similar system now called "Vest"
or"West". Eventually, the Copenhagen Gas and Electric Company conducted a
study  that resulted in the recommendation that  two new refuse-fired hot
water  generators be built to replace Gentofte and Frederiksberg.
         Of note was  that the  competitive  approach  provided both
organizations with a quantity discount if both purchased similar units.

-------
                            28

FIGURE  14-7.  FIRST VOLUND SYSTEM BUILT AT GENTOFTE IN 1932 AND
              DECOMISSIONED 40 YEARS LATER IN 1972

-------
                                   29
The competitors at Amager were:
          •   Heenan-Froud
          •   Martin
          •   VKW
          •   Volund
          •   Von Roll
          Officials remember that VKW, Volund, and Von Roll had the  lowest
single unit prices  (i.e., nonquantity  discount).   Other excellent Volund
plants  in Denmark, the long history (40 years) of successful operations at
                                                                 •f
Gentofte and Frederiksberg, the low (maybe  not the lowest)  single plant
price,  the quantity discount, and the Volund headquarters being nearby all
contributed to the  decision favoring Volund.
          Construction  began  in 1965 with  2  year's of sea and earth
reclamation. Plant  construction began  in 1967  and was completed in 1970.
Construction  at Amager preceded work at West. Both began operation  within
2 months of each other.
          Improvements were made to both plants above what was technically
specified in the contract. Unfortunately the Amager building was not fit
to accept the improved  ash transport system as was done  at West. The
refuse input cranes and the ash discharge equipment are just  two examples
that  are discussed  later in this report.
          Copenhagen:Amager is owned by the  five communities it serves, as
are listed in  the "Organization" section  at  the end of this trip report.
Amager started operations  in February  28, 1974  with three furnaces,
each  designed to burn 12 tonne (13.2  ton) per  hour assuming 2,500 kcal/kg.
          Comment:  Many  of the more precise interviewees  refer to "xx
          tonnes  per hour assuming y,yyy  kcal/kg".   After all, the
          limiting factor is not how much refuse weight can  mechanically
          be  pushed through  the unit. Rather, the limiting  factor  is the
          heat release rate that will not unduly affect system reliability.
          Figure 14-8 shows the development of  a Volund system.

-------
                                  30
               Volund's Relation to the North American Market

          Volund A/G initiated activity in North America  Janauary 9, 19^8
with the  F.  L.  Smidth & Co.  Smidth had the "sole and exclusive rights to
make, sell and/or use the VOLUND INCINERATOR  SYSTEM  ...in  the  United
States...Canada and Mexico".
          Also in 19^8, Smidth and  The Hardaway Construction Company of
Columbus,  Georgia formed a joint  venture company called  International
Incinerators  Incorporated (III) with offices in Atlanta, Georgia.  Ill
was to "devote its best efforts to an aggressive attempt  to  obtain orders
from purchasers  ... (in North America)... for the sale or installation  of
apparatus  and equipment made in  accordance with the  VOLUND INCINERATOR
SYSTEM".
          With this charter , III  sold 13 municipal waste incinerators,  2
of which  had energy recovery.   They  also sold  3 industrial  waste
incinerators.   During this time of cooperation, III  utilized many of the
Volund A/G patents and site-specific drawings. In addition, III developed
many of their own techniques and filed patents.  Eventually many of the
early Volund A/G patents expired.   Yet Volund A/G  continued to file
patents  in America.
          With the Congress passing the Clean Air Act of 1970 and the
ensuing regulations on incinerators,  many units closed.   Few new orders
(regardless  of manufacturer) were placed after 1970.   In fact III had some
of the  very  last orders.  Nevertheless the future  looked bleak.  Ill
survived on their  replacement parts business.
          Eventually the license  agreement between F. L.  Smidth (the 50
percent owner of III) ceased effective December 31,  1975.  Smidth then
sold  its  shares  to the other  original joint  partner  The  Hardaway
Construction  Company.
          Subsequently  Volund A/G and  III (now  100 percent owned by
Hardaway)  were not able to come to agreement on a  new  license.
          Volund  A/G continued  efforts  to find  a new licensee.  Finally  a
joint venture corporation was founded and is known as  Volund  USA  (VUSA).

-------
                                     31
          An abreviated  name used orally is VUSA.   It is owned jointly by
the" following parties:
          Volund  A/G  (Glostrup, Denmark)
          Waste Management, Inc. (Oak Brook,  Illinois)
          Jack Lyon & Assoc. (Washington,  D.C.)
          Others
          30 percent
           30 percent,

          30 percent
          10 percent
          We have been  informed that  VUSA would  like potential purchases
of VOLUND INCINERATOR SYSTEMS to contact:
  Sales, Construction,  Operations

     Mr. Ronald Heverin
     Director of Marketing
     Advanced Systems  Group
     Waste Management,  Inc.
     900 Jorie Boulevard
     Oak Brook, Illinois  60521
Engineering,  Design, Start-up

    Mr.  Gunnar Kjaer
    President
    Volund  USA
    900  Jorie Boulevard
    Oak  Brook, Illinois  60521
          Frankly,  both Volund A/G and III lay claim and probably desire
recognition for  these 13 or so American plants.  All  plants are shown  in
the current inventory published separately  by  Volund A/G and III.
          Effectively,  this means that  a  community  desiring "something
that  looks  like a  Volund  grate  followed by a rotary kiln" has two
potential  vendors.   Some  would speculate  that this is an unnatural
situation that still has not settled.

          Volund has prepared a block  flow diagram  showing how they view
the developmental process for these systems (see Figure 1U-8).

-------
                                   32



Waste Problem



Wa-tc \mount Preliminary w
waste /vmouni Investigation wa^ic

Types
1
_ .^ .



1




nment




Building Prclimimrv Prnicct Mechanical
and Plant Techniques Preliminary I reject Engineering


2

Economv Approval Enviro
tconomy of Authorities tnviro


Offer



nment


Plint Turhnimip . HptTilnrl Prniprt — Mechanical
Plant lecnmque Detailed Project - Englneering


„ ., , ^ . „ . ^ . , „ ,


El-erection



3 4

iction

Erection

^ ^


>eration


Test Running




                 Preliminary Investigation    I   3   I  Turnkey Job
           2  I Preliminary Project
4  I  Machinery Delivery
FIGURE  14-8.  VOLUND'S  PROCEDURE FOR SYSTEM DEVELOPMENT

-------
                                  33

                PLANT ARCHITECTURE AND AESTHETIC ACCEPTABILITY

         Plant  architecture at  both the Amager and  West  plants  is
excellent  to outstanding.   Yet  there are important  differences between the
two plants  caused (1) by the site  location, and (2)  partly by the type  of
construction contract.
         The  Amager site  is located on "new" land  that is an extension of
Amager Island  (see Figure 14-9). Being right on the  sea, the refuse pit  is
shallow and limited to only 4 m  (13 ft) below sea level.
         The Amager plant  is situated on a land parcel  of 31,500 m2  (7
acres)  leased  from the City of  Copenhagen.  The building itself is on
8,400 m2 (1.87 acres).  The floor  space within the plant  totals 25,37*1  m2
(5.64  acres).   Finally, the cubic  content of the building is 244,805 m3
(8.6 million ft3).
         It  is  truly in a  "nonresidential" industrial  area and was thus
designed with  a functional  rectangular industrial theme. West,  by
contrast,  is  in a  residential neighborhood and  has interesting modular
building block and exterior wall themes. The landscaping effect  (and cost)
was much more at West.
         Of  note is that  since  1970,  the Copenhagen Town Hall has not
received a  single complaint from the citizens about  Amager waste disposal.
         Perhaps  another reason  for Amager's  modest but attractive
appearance  is that vendor competition for construction of  Amager was under
a traditional "fixed price" contract where most items were agreed to ahead
of time.  West,  however,  was built under  a  "cost plus fixed  fee"
arrangement. Thus,  at West, there was an increased  tendency to opt for the
"best" but  not necessarily  for the "most economical".
         Despite the identical  refuse input  requirements and similar
processing  equipment, there was more attention  to aesthetics at the  West
plant. As such, West was 25,000,000 D.Kr. ($4,800,000) more expensive.
         The building height is 25 m (83 ft).  The  stack  is very tall  at
150 m (492  ft).
         At  both plants,  everything that could produce noise is enclosed.
The tipping floor for refuse collection trucks is  fully enclosed.  The
electrostatic precipitator,  often  on plant roofs,  is enclosed.

-------
FIGURE 14-9.  COPENHAGEN:AMAGER PLANT LOCATED
              AT SEA LEVEL

-------
                                    35
             The  administration portion of the building is indistinguishable
as part of  the  total monolithic structure. The only  clue to its position
is the  semicircle parking lot  clearly seen in the previous Figure 1*1-3 •
          Figures 1^1-IOa, b,  c,  and d show four very  clean rooms where
Amager  staff work. The rooms are attractive,  well lighted, functional,  and
generally pleasant.  Comments were  made several times  during Battelle's
visits  in  Scandanavia that such  pleasant surroundings  are necessary to
attract and  keep the desired kind of employees.
          A  publication, Amager-forbraending  Interersentskab^ ^),  has
several paragraphs of interest regarding architecture.
             "The building  is constructed of reinforced concrete, with an
          exterior cladding of concrete components.  The  entire north wall
          has been designed  so  that it can be moved  if the  plant  is
          extended  and has, therefore,  been built  as a light  steel
          construction with aluminum cladding.  The  top of the silo is
          likewise covered with aluminum.  The size of the lot permits an
          extension with an  additional three furnaces to a total  of  six
          furnaces,  and the  technical assistance rooms,  pump rooms, etc.,
          as well as administration offices and  personnel rooms have been
          given the proper dimensions for this purpose."

-------
                                          36
                FIGURE 14-10a.  CONTROL ROOM AT COPENHAGENrAMAGER
FIGURE 14-10b, LOBBY
        ENTRANCE
FIGURE 14-10c. CAFETERIA
FIGURE 14-10d. CONFERENCE
               ROOM

-------
                                     37
                           TOTAL OPERATING SYSTEM

                           Maximum Rated Capacity

          Battelle's host for the Volund visit was Gabriel Silva Pinto. In
April, 1976,  he  wrote  an excellent  article  in an  internal  Volund
publication*  that discusses  basic  design of the total  operating system.
The following summarizes the article and Figure 14-11.
          For  purposes of  the vendor's guarantee  to the customer, there
must be a  clear  understanding of  the relation  between Maximum Rated
Capacity  (MRC)  and Lower  Heating  Value (LHV).  The numbers used in the
example figure are those associated with the Volund Rotary Kiln Furnaces.
          For  each furnace designed by Volund,  a  theoretical diagram,
similar to Figure  14-11, is developed.  Its purpose is to  show how  the  MRC
(tonnes/hr)  is a function of the refuse's  LHV (kcal/kg).
          As an example,  assume  that the LHV is  2,000  kcal/kg.*»
Typically,  such municipal solid waste has the following composition:

                                               Percent
          Inerts                                  25.0
          Moisture                                30.0
          Combustibles
            Carbon                                 8.6
            Cellulose                             34.8
            Plastics                               1.6
             Total Combustibles                  45.5
          TOTAL                                  100.0
   * See Reference  4.
  ** Amager was designed with expected average LHV of 2,000 kcal/kg.
     However, the actual is closer to 1,800 kcal/kg.

-------
              38
          -  uof ijsoduioo asnjsy
CO CN  rH O
     c
     00

-------
                                    39

          The refuse feeder is to be adjusted so that the refuse layer on
the grate is  1 m (3.3 ft).   This type  of refuse has an average density of 200
kg/m3 ( 336 pounds/yd3).
          More must  be  known about  the  specific system before the  MRC
answer (in tonnes/hr)  can be given. The  effective grate  area must  be
known.  The following  formula relates key variables:

      /tonnes^   Effective Grate Area (m2)  .  Grate Load /kcal   \
      \^ hour / = 	\_m2. hour /
                     Lower Heating Value /kcal\ .  1000  /kg   \
                                       ^  kg /        (^tonne /

          At  this point, some rules of thumb need  to be applied:
          •   For  hotter refuse with LHV  of 1,800  to 2,500 kcal/kg,  the
              grate load ranges from 600,000 to 650,000 kcal/m2 . hr.
          •   For  cooler refuse with LHV  under  1,800 kcal/kg, the grate
              load ranges from 450,000 to  550,000  kcal/m2  . hr.
Experience of Volund must be used to actually estimate the grate load.  But
once estimated, the capacity can be determined.  Mr. Pinto's example does
not  refer to any one system. Therefore, we have arbitrarily added capacity
figures of 10 to 14 tonnes per hour.
          An important  design consideration can  be seen  from the capacity
versus LHV curve.  It is uni-modal peaking at 1,200-1,400  kcal/kg.  As an
example,  it  is  assumed that the plant  is nominally designed to burn 12
tonnes per hour of refuse assuming it to have a 2,000 LHV.
          Perhaps  on a spring day, rain is excessive.   The moisture
percent rises from its normal 30 percent to 37  percent;  the combustibles
fall from 45 percent to 38 percent; the density increases from 200 kg/m3
to 300 kg/m3;  and the inerts remain  constant.  The air  preheater remains
unchanged and the use of any other fuel remains unchanged.
          With the conditions of  the  wet waste given,  the operator  may
increase  the feed rate, raise the feed layer thickness to 120 cm (3-9 ft),
and thus  increase the throughput from its  nominal  12 tonnes/hour up to 13
tonnes/hour.
          This,  of course, has a logical limit.  If the refuse becomes too
wet, full of  inerts,  and lacking in LHV, then less tonnes  per hour  can be
processed.  The  furnace could easily choke on even 8 tonnes/hour of soggy

-------
                                    40
rags and  house furnace ashes if autothermic  reactions are not possible.
         In the other direction,  above  a LHV of 2,000, this  particular
furnace should process slightly less refuse  per hour.
         Mr. E. Blach, Volund's former chief engineer, wrote  in  1969 an
excellent paper  outlining Volund's product offerings and  its  philosophy.
The following section presents some of the philosophy of how plants should
be operated. Several of his other sections appear later.

                             Forms of Operation

             "The  best way  of running an  incinerator plant is running it
         24 hours a day,  i.e., continuous operation. The  big  variations
         of  temperature wear in  a  furnace and the auxiliary machinery
         than a steady operation,  and corrosion and cleaning problems,
         etc.  in the boiler part also decrease by continual operation.
         With  regard  to  possibilities  of maintenance  and  repair,
         continual operation is not possible for a one-furnace plant, and
         that  is one of the reasons why  an incinerator  plant should
         usually consist of at  least  two-furnace units. Unfortunately,
         this is often not economically possible at the small plants.
             An  ideal way  of operation for plants with several  furnaces
         is obtained by always keeping a spare oven, while  the other or
         the  others run continuously. Through a convenient rotation so
         that the furnaces alternately are  taken out of operation,  there
         is  plenty of time for  inspection, maintenance,  and repair of
         each  furnace. Small damages  can thus be found  and repaired
         before  they spread and  require  big and expensive  repairs. At
         one-furnace plants, the possibilities of inspection are  smaller
         and  it can  be  tempting  to  let a long time  pass  between
         maintenance and repair  stops so that the  damages grow big and
         expensive to repair.
             With  noncontinuous operation, which in practice is a one- or
         two- shift operation, the furnace is stopped. When the operation
         is  to be discontinued  for  6  to 8 hours  the  furnace is fed with
         suitable amount of refuse proportionally to the standstill
         period.  When the furnace  is approximately full with refuse the

-------
         grate movement and combustion air as well as I.D.  fan are
         stopped. The natural  draught will  then keep a slow combustion,
         which develop sufficient heat to  keep the plant  warm all through
         so  that  it can quickly get  up to  full capacity, when it  is
         started  again. After a couple of  hours, the temperature of the
         flue gases will  be so low, that there  is  the risk  of
         condensation, and thus corrosion  in the convection part of the
         boiler.  However,  the boiler water still can be kept  at  full
         temperature,  and the boiler chute can ensure minimum 70 C return
         flow temperature.
             However,  at  stops of more than 6 to 8 hours, there must be
         taken special  measures, such as by-pass  with damper around the
         boiler and its convection  part.  This is a rather  difficult
         construction to carry out in sufficiently strong and  practical
         form because of the high temperatures.
             Furthermore, it results  in the  operational inconveniencce
         that  changing  over cannot take place  till the  flue  gas
         temperature is below  400 C,  which normally means after  3  to 4
         hours'  stop.   During weekend stoppages, the temperature of the
         boiler water cannot be maintained, and it will in this  case be
         necessary also to keep the  boiler warm by circulation of hot
         water."	perhaps by  a standby boiler.

                             Operating Hours

         The monthly operating hours for the  three-line total  are  shown
in Figure  14-12.   At the  recent average  of 1,700 hours per month, the
plant lines operated about 80 percent of the time.
         During the 1975-1976 fiscal year  (April 1 to March 31, the three
furnaces  together operated  19,663 hours or 75  percent of time available.
This equates  to an average  of 13 tonnes (14.3 tons) per hour per furnace.
This compares with a design capacity of 12 tonnes (13.2 tons) per hour per
furnace.   This  higher  refuse flow rate is  consistent with the previous
discussion  on maximum rated capacity.   Because the average  calorific  value
is 1,800  kcal/kg, more refuse can be processed.

-------
                                            42
               1000  1100
 1972
 1973
          APRIL
           MAJ
           JUNI
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
      NOVEMBER
      DECEMBER
        JANUAR
       FEBRUAR
         MARTS
1973
          APRIL

1974     JUN"!
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
      NOVEMBER
      DECEMBER
        JANUAR
       FEBRUAR
         MARTS
         APRIL
           MAJ
1974
1975
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
     NOVEMBER
     DECEMBER
        JANUAR
       FEBRUAR
         MARTS
1976     JUNI
          JULI
        AUGUST
     SEPTEMBER
      OKTOBER
     NOVEMBER
     DECEMBER
        JANUAR
      FEBRUAR
        MARTS
                          1200
                                     Hours
                                 1300    1400   1500
                                                   1600
                                                         1700
                                                               1800
                                                                      1900
                                                                            2000
                                                                                  2100  2200
                                                                                                       X
                                                                                                       H
                                                                                                       53
                                                                                                       g
                                                                                                       W
                                                                                                       53
                                                                                                       O
                                                                                                       w
                                                                                                       c^
                                                                                                       O
                                                                                                       C/l
                                                                                                       w
                                                                                                       hJ
                                                                                                       W
                                                                                                       ftj
                                                                                                       SS
                                                                                                       H
                                                                                                        H
                                                                                                        O
                                                                                                        H
                                                                                                        csi
                                                                                                        rH
                                                                                                        I
                                                                                                        W
                                                                                                        O
                                                                                                        M
                                                                                                        fa

-------
                                     43

                                   Problems

          Plant officials and Volund representatives have identified three
old and partially solved  problems as well  as  five continuing concerns.
These  are  listed here and discussed later  in the report.

Old Problems

          •   The  crane was under capacity
          •   The  grate-furnace  refractory  grossly failed due  to poor
             anchoring
          •   The  ash handling  conveyor system had excessive  wear due  to
             fines buildup

Continuing Concerns

          •   The  rotary kiln lining must  occasionally be repaired
          •   The  convection section has  dew  point corrosion  due to the
             low  temperature boiler feedwater
          •   The  economizer must be manually  cleaned every 1,500 to 2,000
             hours, thus, setting the  maintenance schedule
          •   The  electrostatic  precipitator corrodes slightly  due  to
             running  "hot" when  the  economizer is  clogged  and is not
             properly cooling the flue gases
          •   The  ash handling  system, while improved, is still causing
             problems due to "fines".

                  REFUSE-FIRED HOT WATER  GENERATOR EQUIPMENT

                                Waste  Input

          The plant receives normal household, commercial, hospital, and
light  industrial refuse (see Figure 14-13). Because of the chute size, the
maximum refuse object size is 1  m (3 ft). Aaager, in contrast to West, has
no shredder.  Instead, a transfer station adjoins the Amager plant.

-------
                                       44
                                  Tonnes/Month
           TON 2000  4000   6000
                                8000
1972
          APRIL

 Ib/O     JUNI
           JULI
         AUGUST
      SEPTEMBER
       OKTOBER
      NOVEMBER
      DECEMBER
         JANUAR
       FEBRUAR
          MARTS
          APRIL
           MAJ
1973
1974
           JULI
        AUGUST
     SEPTEMBER
      OKTOBER
     NOVEMBER
     DECEMBER
        JANUAR
      FEBRUAR
        MARTS
1974
1975
         APRIL
           MAJ
          JULI
       AUGUST
    SEPTEMBER
      OKTOBER
     NOVEMBER
     DECEMBER
       JANUAR
      FEBRUAR
        MARTS
1975
1976
         APRIL
          MAJ
          JULI
       AUGUST
    SEPTEMBER
      OKTOBER
     NOVEMBER
     DECEMBER
       JANUAR
      FE'BRUAR
        MARTS
                                      10000  12000   14000   16000   18000  20000   22000   24000 26000
                                                                                                      w
                                                                                                      3
                                                                                                       8
                                                                                                     .  G
                                                                                                    g
                                                                                                    1
                                                                                                    §
                                                                                                        w
                                                                                                    ed

                                                                                                    8   I
                                                                                                         w
                                                                                                     H   CO
                                                                                                     H   fe
                                                                                                     w
                                                                                                      i
                                                                                                      g
                  (0 u
                  •H J=
                  O 60
                  (-1 -rl
                  (U ,J
                     d ^
                     ca;
                                                               0)
                                                               to
                                                               4-1
                                                               0)
                                                               Pi
                                                                O
                                                                HI
                                                                O
                                                                                    0)
                                                                                    to
                                                                                    CO
                                                                                    4J
                                                                                    O

-------
                                 45
          Because of the extensive  vegetable farming on  Amager Island, the
plant receives much garden waste  in  the spring and summer.
          The sewage sludge  could  be dischharged directly into the pit or
in a special  built silo with the  necessary transport arrangement all  of it
in air tight execution.  The waste  oil would be stored in tanks and pumped
to special burners.
          At  the moment the  only sludge type burned in  West and Auger are
ridlings  form the course grid at  the water treatment plants.   This matter
which comes  in  containers  is infiltrated and if it had to be treated in
other way shedding would be necessary.  On the  Volund  rotary kiln  plant
direct feeding  is possible.  While these containers come every day to the
plants the amounts can not be measured in percentages of  the total waste.
          The plants at West  and  Amager were designed  to burn waste oil,
but a parallel development  on the complete  treatment  of all hazardous
chemical- and  industrial wastes gave the best solution  for the problem as
the waste oil  today  is  purified and  resold at Nyborg.   Thus  the
installations have never used the waste oil burning facilities.
          The plant was  designed for lower heating value waste between
1,000 and 2,500 kcal/kg  (1,800 and 4,500 Btu/pound) .  The average is
actually  1,800 kcal/kg (3,240 Btu/pound) which is lower than at West.
          About  400 vehicles  per day deliver waste to the pit.  Ownership
of the vehicles falls into  three categories: private,  public,  and
not-for-profit  utility collection.  In this third category, Renholdnings
Selskabet (Cleaning Holding Company) was established back in 1898. This is
the most  noteworthy collection  operation observed throughout the European
visit.  The company was formed in  response to  the series of epidemics or
plagues in the latter part of the 19th century.

                             Weighing Operation

          Arriving trucks proceed  to one of the two load cells, 50 tonne
(55 ton)  scales manufactured by Philips of Holland (see Figure  l4-l4a).
Drivers   produce their universal plastic  cards (Figure l4-l4b)  that
identify  the  vehicle owner,  etc.  This information, along with the  gross
weight,  is fed  into the computer,  where the tare weight, mailing address,
etc.  are  stored.

-------
                                         46
 FIGURE  14-14a. SCALE
 HOUSE  AND TWO SCALES
                               FIGURE 14-14c. MONITOR
                                IN CONTROL ROOM OF
                                TRUCK SCALE
                             FIGURE 14-14b. PLASTIC CARD
                    FIGURE 14-14d.  DIGITAL READOUT IN SCALE HOUSE
FIGURE 14-14e.  RAMP TO
 TIPPING FLOOR
FIGURE 14-14f.
       FLOOR
TIPPING
FIGURE 14-14g. TIP
 ARRANGEMENT PERMITTING
 GOOD CRANE VIEW

-------
                                   47
          Occasionally the plastic cards jam,  break, or become lost.   In
this event,  the  driver would have to get out of the  truck  and spend
several minutes  in the scale house filling out a  form.  The cards were
replaced on an as-needed basis. They  have changed the  system so that  every
6 months all  of the plastic cards are changed at  once.
          At  the time of the  visit in October,  1977,  a particular card
would  work  at  Amager,  West,  and the Hillerod transfer station.   An
identical  Philips system was under  consideration  for  the Roskilde Volund
plant as  well.   In theory, the system could be  used  throughout Denmark to
the advantage of all.

          Relevant  information is  displayed  (see Figure l4-l4d) on digital
 readout devices.  The single operator can  process 120  vehicles  per  hour if
 both scales  are used  simultaneously.  The  scales can be used  automatically
 at night when the  scale  house is  unmanned.  Opening the plant gate and
 weighing  the vehicles can be controlled from inside the plant at  the main
 control room  with use  of  television cameras (see Figure l4-l4c).  Truck
 entrance and  tipping activities are shown in  Figures l4-l4e,  f, and g.

                        Waste Storage  and  Retrieval

          Amager  has  a pit 48 m (158 ft) long,  17 m (56 ft)  wide,  and  13 m
 (43  ft) deep.  The capacity to the  tipping  floor door level  is 10,000 m3
 (13,462  yd3).  However,  with refuse piled  against several doors  and by
 piling refuse against  the wall to the furnace, the maximum capacity can be
 doubled  to  20,000 m3 26,924 yd3).   This converts to 3.5  days  maximum
 storage.  The specific  weight or density  is 0.2  to 0.3  tonnes/m3  (336 to
 505  pounds/yd3).
          The 11  refuse  doors are  described as double hinged flap doors
 8.0  m (26.4 ft)  high,  3.8  m (12.5  ft) wide, and 122 mm  (4.8 in) thick.
 They are  operated  hydraulically.  The  tipping  configuration was  designed

-------
                                    48

carefully to allow  for a door and  also to permit  full view of  tipped
refuse by the crane operators (see Figures l4-15a  and  b).
          The West pit  is much deeper by comparison  than Amager. The West
pit bottom is 4.0 m  (13.2 ft) above  sea level while  Amager  is 3.7  m
(12.2ft) below sea level.
          There are  two fire cannons located around  the pit at the hopper
level.  They also have four hoses that are 30 m (100  ft) long. The local
fire  department is  called for the  few fires that  cannot be controlled by
plant personnel.
          The plant  has two cranes (one active and one  often in reserve),
manufactured by Thomas  Schmidt A/S.   During the  day,  the second crane
mixes  incoming waste to a fairly uniform calorific  content.  Only at night
is this crane truly in reserve.

          Comment:  When planning the number of cranes, there are a number
          of factors  that could necessitate having a mixing crane.  Some
          are seasonal changes with low calorific  value (wet vegetation loads),
          a or high calorific material (truck loads  of tires, industrial plastics
          etc.)-  If  in  the future, industrial wastes might augment household
          waste, space should be set aside during  the  initial construction for a /
          mixing crane.

          Each  crane is rated at 10.5 tonnes  (11.5  tons). Television
cameras aimed at the  hopper assist the crane operator  in  setting  the  drop
position over the hopper.
          When both  cranes are functioning, they  can  together put up to 50
tonnes (55 tons) per  hour into hoppers.  The cranes  are equipped with  Sven
8 m^  (10.8 yd3) star grab polyp  buckets (Figure l4-l6a). Each normally
handles 2.5 tonnes  (2.75 tons) of refuse per lift. The maximum net  load is
4 tonnes (4.4 tons).
          The Amager cranes were  initially a source  of  numerous problems.
Esentially the cranes and bucket  were undersized.  The bearings  on the
polyp bucket often  failed.  The  crane hoist motor  would burn out for no
apparent reason.  Hydraulic leaks from the polyp  due to  high temperatures
on the hydraulic coil were frequent.

-------
                    49
                            .Centered Crnne
                             Control Room
                        /I

  FIGURE 14-15a.  TIPPING DOOR THAT CAN CLOSE.
                 UNOBSTRUCTED VIEW OF PIT BY
                 CRANE OPERATOR
FIGURE 14-15b. CRANE OPERATOR CONTROLLING
               POLYP TOWARDS HOPPER

-------
                              50
   FIGURE 14-16a. SVEN POLYP GRAB AT COPENHAGEN:AMAGER
                  GOING DOWN FOR ANOTHER LOAD
lifting cables
                                       open and close cable

                                       hydraulic motor
       FIGURE 14-16b.   SCHEMATIC OF POLYP

-------
                                    51

          After 2 years, most  of the problems were solved by a series of
corrective steps.  Bearings  twice  the original  size  were installed.   The
German electric motors were replaced by larger Siemensmotors.  Better seal
packing and gaskets reduced  hydraulic oil leakage.
          However, the original  design did have  beneficial features.  In
contrast  to the old Gentofte plant where cables would break every 2 weeks,
the Amager cables would last about 1 year.  The difference was for several
reasons.   First,  a strong  special German wire  cable  was  always used.
Second,  the  bucket was always hydraulic and not mechanical..  Third, the
polyp is  controlled with a hydraulic motor located  inside the bell of the
polyp  top.  There is a  sensor so that when  the polyp is more than 45
degrees from  its level position,  it switches  off and refuses to permit
further  movement that  might  snag the cables.  Fourth,  the polyp has
additional stability due to  the  four lifting strands as compared to two
strands in some less expensive system as shown in Figure  1i<-l6b.

          Based on the many  crane  problems at  Amager and the success in
curing them,  West was more  properly designed and has had fewer problems.
This revised  cable and polyp system has worked  exceptionally well and is
considered  well worth the extra money. Incidentally,  Volund was so
impressed with  the Sven polyp that Volund bought Sven in  1977.

                 Furnace Hoppers, Feeders, and Swivel Gate

          The hopper dimensions  at its top opening  are 6  m (20 ft) by 6 m
(20 ft).   Farther down, at  the  hopper bottom,  the dimensions are 2.3 m
(7.6 ft)  by 1.15 m (3.8 ft).  Its  height is 6  m (20 ft).  The walls are
made from 8 mm  (.31 in) plain carbon steel.
          Sometimes instead  of a steel hopper,  Volund will  install a
concrete  hopper.  Concrete is cheaper and quieter.
          The filling chute  has  a  slightly larger width dimension than the
 hopper:   2.3 m (7.6 ft) by  1.15 m (3.8 ft).   It too  is made of 8 mm
 (.31 in  ) steel.
          The swivel gate or damper is located in  the chute.  It is opened
when refuse  falls on it and closed  when no  refuse is above  it.    Its
function  is to  prevent burnback.

-------
                                     52
           The damper's dimensions are 2.58 m (8.5  ft) by 1.26 m (4.16 ft)
  and  is 10 mm (.39 in)  thick.  The 2.3 m dimension  gradually increases to 2.7  m
  (8.9 Ft) near the furnace entrance so that jamming is minimized.
          Volund typically  installs chutes with  only  refractory lining.
Except for flowing material,  the hopper  should always be empty.  There
should  be no  refuse  above this kind of damper  to interfere with its
closing. With proper crane operator training and performance, burnback can
be minimized.  Officials  believe that water cooled jackets, besides being
unnecessary, have more costs of operation and maintenance.

                          Primary (Underfire) Air

          The plant designers had been of the opinion that the air  intake
should be  at the hopper level for better control of odors  from the pit. As
someone  stated,  "if the primary air  is taken  from  the top of the  bunker
(higher  and  above the  crane),  you could smell the air on the  tipping
crane  control room-hopper floor".

          The intake was  thus located at the  hopper level as shown in
Figure 1*1-17.  This resulted in a very dusty floor  and atmosphere  around
the hopper.   But more  important the dust raised by the falling refuse
would  clog the vent and accumulate in the  ductwork.  The air intake was
later raised  about 3 m  (10 ft) to  the level shown in  Figure 14-18.  The
entrance  at this higher position should  (1)  better  remove smoke from any
pit fires  (2)  provide better ventilation  in the summer,  (3) be  freer  from
dust and  (4) permit a better environment.
          The  air is then pulled in and  down by the Nordisk  1490 rpm fan
which  can  pull 45,000 Nm3/hour.  The  temperature is assumed to be 30 C (86
F) in  the  summer.  The static pressure is 230 mm water.
          Primary air  is  delivered to four  hoppers under the grates:
Drying Grate  (one hopper), Ignition  Grate  (one hopper),  and the  Combustion
Grate  (two hoppers).  There is one large damper per furnace that  is set
only  once.   However,  each of the  four hoppers (plemum sections) has its
own separately  controlled damper that  can be adjusted from the  control
room.  Each  hopper's pressure reading  is  sent to the control room, but  it
is not recorded.

-------
H
co
w
5s
w
§
PQ
W
O
PQ
pe! Pi
W W
H O
W H
i*; 
-------
                                    54
  Raised Position
Original Position
           FIGURE 14-18.  ORIGINAL AND RAISED POSITION OF THE
                          PRIMARY AIR INTAKE

-------
                                      55

          There are two types of fan drives available  for designs: (1) fan
belt and (2)  direct. The  direct method is not normally used except for
large  induced draft (ID) fans just before the chimney.   In the future, the
Amager plant  capacity  can be raised (other systems  permitting) simply by
changing  the belt. Assuming that the electric motor speed does not change,
then the air  pressure  can be lowered and a higher quantity of air  can be
passed.
          Volund  usually specifies a  fan to be operated at a point
situated  in  the middle of the capacity curve e.g. lower  r.p.m. than the
maximum  allowed.   In  case more air  is  necessary,  for  speed  can be
increased.
          One other point is that  when  Volund dimensions a fan they ask
for a certain amount of air at a certain pressure.   In case  the  pressure
is  lower  than necessary more air can be transported by the fan.   These two
factors are proportionally to each other e.g. higher pressure  = less air.
          There are now very few problems with the  primary air system. The
blades are self cleaning.  Sometimes when the  hopper floor area  is hosed
down  with water, the mist would be  sucked  into  the vent.  The moisture
would mix with the dust  (from crane discharges into the hopper)  and form
deposits.  Now every 6  months, the ventilator is  opened and air is  blown
through the duct.

                         Secondary (Overfire) Air
           Volund  furnaces have three (3)  sources of secondary air that can
 be blended for proper operation.  Sometimes (1) oxygen rich refuse bunker
 air (2)  normal boiler room air or (3)  oxygen poor flue gas recirculation air
 may be needed in  varying amounts when the refuse heating content varies.

 Refuse Bunker-Oxygen  Rich Air

           Amager  can pull its cool oxygen-rich secondary air  from the refuse
 bunker.   This is  slightly different from  West where    both  primary and
 secondary air is  pulled from the boiler room.  The  Nordisk Ventilator forced-
                                                                     3
 draft 150 Hp belt-driven fan, running at  1,670 rpm,  can pull  35,000 Nm  hour.
 The temperature is assumed to be 30 C (86 F)  and the static pressure is 460
 mm water.

-------
                                  56
          The air is sent to two manifolds on each side of the  furnace and
above Grate  III. Each manifold a set of nozzles  as shown below.
                           o
                         o
                           o
                         c
                o
                   0        l£ Grate
                o
Secondary Air Nozzles
                  Figure 14-19 shows  the sidewall jets.,
Flue Gas Recirculation - Oxygen Poor Air

          Amager formerly (during only the  first year) used  recirculated
flue gas  as  secondary air. The air was drawn from the flue gas  leaving the
hot electrostatic precipitator. See the previous Figure 1U-1.
          Another Nordisk Ventilator forced draft fan, this one at  150 Hp,
was belt driven at  1,460  rpm. The  fan  is rated at 45,000  Nm3/hour and
delivered the 300 to 350 C  (572 to 662  F) hot  flue gas at 220 mm water
pressure.
          Many Volund units are built to permit use of either or to permit
blending.

Boiler Room - Oxygen Normal Air

          The  use  of  ambient  boiler  room air  at  30  C   (86 F)  or
recirculated  flue gas air, 138 to 177 C (280  to 350 F),  is  determined by
basic  furnace design and the refuse lower  heating value (LHV).  Assume that
the  furnaces were nominally designed  for refuse with  a  LHV of 2,000
kcal/kg.  If the LHV is well over  2,500  kcal/kg, air rich in  02,  might  shock
the refractory and cause the Carborundum bricks to grow  and then spall.
Therefore, if the refuse is "hot", then recirculated flue gas  air, poorer
in 02, should be used. In contrast, if the  refuse is  "cool"  or wet,  then
ambient boiler room, rich in 02, should be  used.
          Of the European vendors visited,  Volund is the only manufacturer
known to us to use recirculated flue gas.

-------
57

-------
                                       58

          The  recirculation  flue  gas  fan  has  a  damper  that  is
automatically controlled.  It  sends a larger or  smaller quantity  of the
flue  gas back to  the furnace depending  on the  furnace combustion
temperature. The dampers are adjusted so that the furnace temperature is
always 900 to 1,000 C (1652 to 1832 F).
          At Amager, where the refuse is cooler,  1,800 kcal/kg (3240 Btu/pound),
 than  at West, they now  use both refuse bunker primary air and boiler room
 secondary air.   Refractory life has improved.   The boiler room air is now put
 through the back wall where the flue gas recirculation air had been previously
 inserted.

                                Flue Gas Fan

          An  induced-draft Nordisk Ventilator  flue-gas fan is  located
between the  electrostatic precipitator and the chimney.  It  is necessarily
the strongest fan  and can pull 107,000 Nm3/hour with its 220 Hp motor. It
too is belt  driven but at a lower  speed of 1010 rpm.  It  delivers  the flue
gas at 170mm water pressure to the chimney. Flue gas  temperatures range
from  300  to  350 C (572 to 622  F).  The fan has a damper connected  with a
regulator  which holds the vacuum  in  the  furnace constant at all times.

                                Fan  Summary

          Table 14-2 presents key design parameters for the four fans:  (1)
F.D.  primary air,  (2) F.D. secondary air, (3) I.D. flue gas  recirculation,
and (4) F.D.  flue  gas recirculation.
          The plant people report that the  furnaces each with  four fans
have experienced only minor maintenance.
          Assuming  the  maximum  refuse  calorific value to be 2,500 kcal/kg
(4500 Btu/pound),  the theoretical air is 3.01 m3/kg (234 ft3/pound). After
combustion,  the  theoretical combustion  flue gas is  3.78 m3/kg (294
ft3/pound),  while the actual is 5.3 to  6.8 m3/kg  (412 to 528  ft3/pound).

-------
                                       59
CM
 I
W
_1
PQ
* -
e
o
•H
en 4-i
cfl co
O rH

cu o
3 t-i
rH -H
fa O
cu
e!
4-1
14-J
Cfl
CO rJ
cfl a
o
"0
cu cu
3 0
rH 3
fa X(
c
I—I


V) 4-i
•H 14H
i O
r?
Cfl T3
TJ CU
C 0
O V-t
CJ O
CU fa
c/>

(-4 4J
•H UH
> O
r4
cfl TJ
e co
•H CJ
1-4 r4
P-i O
fa
































rH 0
O
0
*l
i r*
U 1
-l
3
o
J2

01
E
CO Z
o ^
CO
C !M
^J -H
3 





O O O
CN m vo
CN 01 ~3"
ri
,i




o o o
r^- m rH
rH 01 O
**
rH










O O O
vD 01 r^

«,
rH







000
O1 O"l CTi
csi ~a-
n
rH







S-J
cu
4-1
Cfl
^2 ^^s
e
e ex
e ^
< — ^^ ^
0
cu en
(JO C
3 ^ O
en -H
W CU 4.)
1) H 3
VJ 3 rH
PU 4-> O
cfl >
O M CU
•H CU ptj
4-> CX
co g n
4-1 a) cfl
co H fa





en o
cu in
ts M





en o
CU CN
>. CN












en o
cu m
>1 rH









en m
cu r^
>,


















/^N
PH
5-

60
S t-i
•iH CU
> S
•H 0
1-J fa
P
(-1
4-> O
rH 4-1
cu o
M S



















•
T3
CU
en
3
)-i
cu
60
C
O
rH

o
C

en
•H
#\
T3
CU
rH
rH
CO
4-1
en
C
•H

>^
rH
rH
CO
C
•H
60
•H
V4,
O
n
C
0
•H
4-1
CO
rH
3
a
i-i
•H
0
cu
&

en
cfl
O

cu
3
rH
fa

*

-------
                                     60
                         Furnace Combustion Chamber

          The original Volund designers had two seemingly opposite design
considerations.  First, the design should ensure proper drying out of the
wet refuse.  Therefore, there is a desire to use a gas counter-flow to the
waste flow as shown in Figure H4-20a.
          On the other hand,  there should be good burnout  of putrescibles
and carbon.  Therefore, the gas flow should parallel the waste flow as in
Figurel4-20b.
          A  compromise suggested by other vendors would be to simply have
the flue gas exit centered over the grate as shown in Figure lH-20c.
          The  Volund simplified answer is to  put a wall  above  the grate
and to send  some of the  gases back toward  the  feed chute  and  the other
gases toward the ash chute as shown in Figure l4-20d.
          The more elaborate answer from Volund is to attach a rotary kiln
at the  end  of  the furnace grate as shown in Figure l4-20e.  Here some hot
gas returns  back toward  the feed chute to  help dry the incoming waste.
Also,  the other gases continue flowing with  the waste out of  the grate
area and into the rotary kiln.  The heat supports further  combustion in
the kiln to  consume almost all of the putrescibles and unburnt carbon.
          This  configuration, known as the  two-way gas grate and rotary
kiln  system,  is the design at both Amager and West.  The schematic  (see
Figure 14-21) for Frederiksberg (1931*) shows the basic configurations. To
restate, the original  two Volund plants  (Gentofte and  Frederiksberg)
successfully served Copenhagen for UO years.

                  Burning Grate (Forward Pushing Step Grate)

          Information,  for the record, regarding the Volund   grate is
distributed between the trip reports 14 and 15  (Amager and West).  Part of
this section is taken directly from a technical 1969 paper  written by Mr.
E. Blach, former Volund Chief Engineer, entitled "Plants for Incineration
of Refuse".
             "This grate  construction  is  built up  of several grate
          sections, each separated by a vertical grate transition bar. The

-------
                                    61
                      VWundM
FIGURE 14-20.  GENERAL DESIGN CONFIGURATIONS FOR VOLUND FURNACES

-------
                              62
FIGURE 14-21.
FURNACE DESIGN (TWO-WAY GAS GRATE AND ROTARY
KILN) AT THE OLD (1934) FREDERIKSBERG PLANT,
DISMANTLED IN  1970

-------
                           63
ratio of size  between the individual grate sections and grate
transitions is determined  by the composition of the refuse.
    Figure 14-22.  The individual grate  section is built up of
lengthwise-placed sections of 180 to 300 mm wide laid up with an
inclination  of 18-15°.   Every other of these sections are fixed
and every other are moveable, and each section  is  built up of a
through grate  bar, which is welded  up,  on which a number of
grate blocks  of specially alloyed  cast iron are  fitted, which
are in turn filled up with loose grate bars of cast iron.
    Figure  14-23.   The moveable sections  are  driven
hydraulically  by  a transverse driving shaft placed under the
grate,  which  is connected  to the individual sections by pendulum
driving bars.  From a neutral position, the movement in forwards
stroke is slowly raising,  forward going, and then lowering and
backwards going.  In the .backwards stroke,  the movement is
slowly lowering and  backwards  going and then raising  and
forwards going.
    Along  the side of grate sections, which are built into the
wall of the furnace, there are a number of side  sealing beams,
which  through  building in springs  give  the  grate sections a
transverse flexible assembling.
    Figure 14-24  is  a drawing included in one of Volund's first
patents.   The  first grate section acts as  a feeding  and
predrying grate and  apart from the last  part of the transition
bar, it is  covered with grate plates. Ignition  and the first
part of the  combustion take place at the first transition and on
the second grate. The  final combustion and burnout takes place
on  the third grate,  and  calcining and cooling of the clinkers
begin at the  last part of the tjiird  grate and  continue on the
subsequent clinker chute.
    The layer of  refuse  is 300 to 500 mm  (12 to 20 inches). The
moveable grate  sections  give  a lifting, moving,  and turning
movement in  the lower half of the layer  so that the combustion
air, which in a regulated  way is supplied from below, can get to
all  parts of  the layer. At the  transition  bars, there is a
supplementary turning, mixing, and air supply.

-------
64
                                                W
                                                O


                                                8


                                                §
                                                M
                                                H
                                                O
                                                w
                                                 P-I

                                                 w
                                                 w
                                                 1-5
                                                 O
                                                 CM
                                                 CM
                                                 w
                                                 &
                                                 g
                                                 H

-------
65
                                                                  w s
                                                                  in E>
                                                                  erf ,J
                                                                  w n
                                                                  > Q
                                                                  to ^
                                                                  a w
                                                                  3 H
                                                                  W 0
                                                                  > W
                                                                  M co
                                                                  »J Q
                                                                  ,J M
                                                                  < >
                                                                  U M
                                                                  M O
                                                                  hJ a
                                                                  S3 M


                                                                  K W
                                                                     o
                                                                  CO H
                                                                  Z
                                                                  O O
                                                                  M W
                                                                  H H
                                                                  u o
                                                                  w w
                                                                  W O
                                                                  .-J O
                                                                  pa,
                                                                  < H
                                                                  > PL,
                                                                  O •<
                                                                      co pa
                                                                  O  Pi D^

                                                                  >  O O
                                                                  CO

                                                                  CN1

                                                                   I
                                                                  w


                                                                  o
                                                                  I—I
                                                                  PL,

-------
                                66
Oct. 1, 1935.             A  CHRISTENSEN            2,015,842
          FURNACE WITH GRATE FOR COMBUSTION OF REFUSE OF ANY KIND
                         Filed Nov. 5. 1932
                                        INVENTOR
     FIGURE 14-24.  ONE OF THE EARLIEST VOLUND PATENTS

-------
                                     67
          Volund supplies  furnaces with either  three  or four separate
grates.   Amager has three grates per furnace.
          Each  of the furnaces has two operating hydraulic pumps.  At some
other installations, an additional hydraulic pump  is  used as a standby.
Each pump's capacity is 47  liters/minute (12.4  gallons/minute).  Each pump
has  a  15 Hp motor.   The  resultant  pressure is  70 kg/cm^  (1,160
pounds/in^).   The plant has one 600 liter (160  gallon) hydraulic oil
storage  tank.
          Each  of the first three  grates have five  hydraulic cylinders
with cylinder  bases of 80 mm  (3.15 inches)  and strokes of  130 mm
(5.1inches). The stroke frequency  is three strokes  per minute.
          Having three grates means that there are  two  steps. The height
between  Drying Grate I and Grate II is 1 m (3  feet). Between Grate II and
Final Grate III, the height  is 2 m (6 feet).
          The  final step,  from the grate system to the rotary kiln, is 1  m
(3 feet)  high.  The grate exit to the rotary kiln is shown in Figure 14-25.
          The  earlier Volund plants  (1930's)  had grates with an angle  of
23 degrees and  a conical rotary kiln based on the  refuse  composition  of
the "poor times".   In  the  beginning of 1960 the  grate  inclination was  20
degrees  and the kiln at a choice of conical or cylinder  depending on the
town and the living standard of people.
          In 1965 the rotary kiln  became cylindrical and the grates were
constructed at  15 degrees.   This is the present  situation.
          Amager plant officials estimate that the  individual grate bars
will last about 15,000 hours. Stated in another manner,  on the average 100
percent  of the  bars are replaced every 15,000 hours.  The grate bars  last
20,000 hours at West.
          Compared to  West,  the  amount  of small-sized inert  (ash)
particles is more at Amager. Perhaps Amager's increased volume of  inerts,
less grass and more home furnace  ash, contribute to Amager's shorter grate
life.
          The  ash leaving  the Amager plant is  often smaller than the West
ash because any large  clinker at  800  C (1472 F)  from the rotary kiln
falling  into a  bath of "cold" water will explode into small fragments.

-------
                  68
FIGURE 14-25.
GRATE FURNACE EXIT INTO A. ROTARY
KILN AT ONE OF VOLUND'S PLANTS

-------
                                     69

          All grate frames,  bars, and grates  are made from a material
called  "Meehanite HR." It is  ductile  but has a  minimum 350  Brinnell
hardness.  The  side seals are  made from "Nicromax". Due to the moving and
rubbing surfaces, this  can be less ductile but very hard. Occasionally
tramp metal (usually iron)  will  fall on the first grate  and break a bar.
          All three grates  have  a 2.7 m (8.9 feet)  width.  The grate  stroke
is 130  mm  (5.1  inches). Roughly 23 percent of the grate area is open for
combustion air to enter. The  length and area of the three grates  are as
follows:

                 Drying Grate 1  Burning Grate 2  Burning Grate 3
Grate Length (m)        2.5            2-°               5.0
Area (m2)               6.75            5.4              13.5

                          Furnace Refractory Wall

          Volund furnace walls are  refractory lined (and not lined with
water tube walls) inside a  steel framework.
          The six furnaces  for both Amager and  West (three each)  were
designed and built at  about  the same time.  (West later added a  fourth
unit).
          Volund originally  chose Hoganus, a  high-quality and expensive
refractory,  for  its flame wall lining. The bricks  themselves were not a
problem.  The  difficulty,  however, was that there were not enough anchors
between the iron structural framework and the bricks. In addition, the few
original  anchors were not properly welded  and broke during thermal
expansion.  Also, ash was accumulating or "slagging" on the walls.
          As a result  of  the several problems,  the furnace walls  were
rebuilt. Fortunately the warranty period was still  in effect. More anchors
were added.  The welding technique was changed.
          To cure the ash slagging problem, silicon carbide was added to
the walls  above the  grate .5  to .7 m (1.5 to 2 feet). However, where the
flame is hottest and the 02 levels the greatest,  the SiC is to be avoided
so that it  does not  oxidize. Hence, the lowest wall areas and up a little
bit in the  middle side wall are  left with Hoganus chamotte bricks exposed.

-------
                                       70
         Volund officials believe that, with proper anchoring, a
refractory  wall furnace is  less expensive and more reliable than a water
tube wall  furnace. Having  learned from the Amager experience, they  now
specify a  wall  shown below:
         Plastic Silicon Carbide,
         beginning .5 to .7m
         above grate
             Flame
          Thick Chamotte Bricks
                       Refuse Bed
                                                          Porous  Chamotte Bricks
•Moler Blocks
                                                          Steel Plate
                                                             Furnace Room
                                         225 60 150   mm
          The Moler blocks near the  outside wall are unique to Denmark.
The clay is literally quarried or carved out of the deposit in the  final
shape.   (There  is no normal mixing and blending of clays.)  The blocks are
simply fired.  The brick dimensions of 23.4 x 11.3 x  6.2  cm (9.2 x  4.4 x
2.4 inches)  weigh 1.2 kg (2.6 pounds).  This is slightly heavier than many
insulating fire  bricks but much stronger.
          Volund does not  report the furnace  volume or heat release area
since the wall enclosures are not designed for  heat transfer, as are the
walls of a water-tube wall furnace.
          The furnace roof is always arched if the  span is less than 3 m
(10 feet).  However, for wider roof sections, a steel structure is  built
with  many hangers.  Specially shaped  Chamotte bricks are then suspended
from the anchors.  Then granulated Moler particles are  spread on  top of
the steel and bricks.  Finally, rock wool is laid on top of everything.

-------
                                      71
                                Rotary Kiln

         The rotary kiln is seen in its relationship  to other key furnace
parts in a plant schematic of the now dismantled Gentofte plant (see  the
previous Figure  14-7)  that served northern Copenhagen  so  well for 40
years. The basic design (with the exception of major modifications  to  the
boiler and air pollution control equipment) remains the  same today. To
repeat, again from Mr. E. Blach's paper:
             "Pre-drying, ignition, and the first part  of  the combustion
         takes place on  the grate system ...,  but then the refuse  slides
         into the rotary kiln, where the final combustion and burning out
         takes place.
             While  in  operation the rotary kiln turns slowly  and thus
         creates a perfect overturning of the burning refuse. The
         movement  makes  the refuse travel a  very  long  way and thereby
         stay for a long time in the kiln. The  system operates with the
         so-called divided flue gas/combustion air  circulation,  e.g.  the
         primary  combustion air is divided into two  after having passed
         through the  layer of refuse on the  grates,  one part passing
         through  the rotary kiln and one part passing over the layer of
         refuse  on the grates up to the top of the furnace, from where it
         is brought back  to the  after  burning chamber through the
         previously mentioned connecting flue gas passage  coming from the
         rotary kiln.
             Besides primary  air, secondary air is added over the grate
         sections  as well  as the rotary kiln  in order  to ensure for
                                                           v
         certain  that the  flue gases are fully  burned.  By adding a
         surplus of primary and/or  secondary air a cooling  of the
         combustion can  be achieved. But this  cooling  function  can be
         achieved  better  and more  effectively by using a flue gas
         recirculation system, e.g., cooled flue gas is  brought back to
         the combustion zone, over  the grates,  and  at  the rotary  kiln.
         While in  operation, this cooling function  is done automatically
         so that  the temperature is kept at 900°- 1,000° C.

-------
                                       72

             The  rotary kiln is built  up of an outer heavy steel plate,
          which are lined  with wear resistant  fire-proof bricks  on the
          inside  laid up and built  on an  insulating layer  direct up to the
          steel  plate. The  ends  the kiln are  furnished with  special
          sliding seals and transition  sections.  The whole construction
          rests on two sets of running and guiding wheels, which  at the
          same  time act as friction pinion, activated by hydraulic motors.
          The speed of rotation can  be regulated variably between 0  and 15
          r.p.h.
             The  grate/rotary kiln design is used for capacities from 5
          t/h to about 20 t/h, but can be  built also in larger plants."
          The  carbon steel shell  (see Figure 14-26) has an inside diameter
                                                                   f-
of 4 m (13.2 feet). With the addition of refractory, the  inside diameter
is reduced to 3.4 m (11.2 feet).  Each kiln is 8 m (26.4 feet) long. Volund
will build kilns up to 10 m ( 33  feet). The volume is 73 m2
          The  kiln is sloped downward-at a 3  degree angle and revolves
upwards of 12 revolutions per hour (rph).  It however, normally revolves at
6 to 8  rph. IF the furnace operator is told by the crane operator that the
refuse is wet or if he sees a disturbance  in the kiln, he can easily lower
the kiln speed.
          The  original configuration had two  support rings,  two support
rollers, one thrust roller, and two  drive support rollers all made from
high tensile-strength steel castings (see  Figure 14-27).
          Later, officials decided that large spacing between rollers was
permitting alternatively  excessive compressive and tensile forces.  Thus
open  spaces  would develop in the  lining  depending on  where the brick
section was on its rotation.  Eventually  bricks would be either crushed or
would fall out.
          The two hydraulic motors per kiln  are  rated at  3  kg-m  (21.8
foot-pounds) and have a maximum speed of 76  revolutions per hour  or 1.27
rpm. The nominal reduction is 1:800.
          The  refractory  bricks are anchored onto the steel shell.  Moler
refractory was originally specified  to be  placed next to the steel  shell.
Then  next to  the Moler refractory, Chamotte bricks of 36-55 percent  Al2C>3
content are used to line  the inside of the  kiln. The  composition is 85
percent SiC at the inlet.

-------
73
                                               Q
                                               W
                                               06
                                               M
                                               < PS
                                               (X W
                                               w o
                                               ftj <5
                                               w
                                               CO
                                                 w
                                                  w
                                               >< 0<

                                               IS
                                               pi •<
                                               VD
                                               CM
                                                I
                                                o

-------
                     74
FIGURE 14-27.
TWO SUPPORT RINGS OF A
VOLUND ROTARY KILN

-------
                                       75

          To some extent,  because of very high temperatures,  the kiln is
self-cleaning. Slag  does  not normally  accumulate on refractory  walls.
However,  at some other  Volund plants,  slag "rings" occasionally form
within  the  kiln. This  only  occurs  if the kiln  is conical and  the
temperature is very high.   Interestingly,  this  slag ring can gradually
move down  the  length  of the kiln. It eventually disappears.
          Everytime  the furnace is stopped and cooled enough ,  the kiln is
inspected. Occasionally several rings of brick are replaced.  Finally in
1977i after 7 year's (1*2,000 hours) operation,  the kiln was completely
rebuilt  at a cost of  150,000 D.kr.  ($25,960).
          During  this major  change,  the  brick used was respecified.
Instead of the  very  porous Moler  brick, which  was  crushed  under
compressive pressures once per revolution, a harder inner  brick was used.
Some insulation quality was sacrificed but  the temperature just  outside
the kiln rose  only 2  C (3.6 F) from before.

                           After Burning Chamber

          Flue gas leaves  both the grate section in an upward direction
while flue gas also leaves the kiln and rises. Occasionally  slag will form
on  the  45°  slanting  lower surface in the mixing chamber above the rotating
kiln (see  Figure  1U-1).

                               Boiler (General)

          The  boilers at both Amager and  West  were designed  and built
under Volund patents.  The Amager units consist of a refractory walled
furnace, an  afterburning chamber and then followed by the Volund boiler
(see Figure  14-28).   Thus, Volund units are not "water wall  incinerators."
          Later Volund plants in Japan and Aalborg have Eckrohr vertical
water-tube wall boilers completely  separate and following the combustion
furnace.  The  Eckrohr (translated "corner-tube") boilers were built under
a license  from Professor Dr. Vorkauf of Berlin, W. Germany.   We later heard
that roughly 180 of these boilers have been installed on refuse-fired
energy systems.  When asked why Volund often now uses the Eckrohr boiler
instead  of the traditional Volund boiler,  the  reply evoked the Eckrohr
features - features that seemed popular in several other places  over
Europe.

-------
                        76
FIGURE 14-28.  AFTER BURNING CHAMBER AND BOILER
               AT COPENHAGEN:  AMAGER

-------
                                       77
          •   The four  corner tubes are used not only to carry downstream
              water  but  also  they  provide structural support for the  whole
              boiler,  thus reducing  construction costs.
          •   The heat transfers rate is excellent.
          •   The circulation pattern is good.
          •   It has high efficiency.
          •   It is  a natural circulation boiler.
          The market for energy  demands slightly higher  temperatures at
West than at Amager as follows:

                                  West             Amager
Energy form                   Overheated water     hot water
Water temperature leaving
  plant*                         160  - 170 C       115 - 120 C
Water temperature return-
  ing to plant*                    140 C            70 - 75 C
                                  284 F             158 F
Heat output                   21.5 goal/hour      20 goal/hour
Pressure (working)              16 kg/cm^    6 kg/cm^ - 7 kg/cm^
                              225    psi            85   psi

          The key reason for  higher temperatures at West  (and not Amager)
is that  an early  customer was  the  Copenhagen County Hospital that needed
hotter water for sterilization and  air conditioning.  So  often, we  have
observed that the  initial customers will dominantly effect long term  energy
configurations.
          The amount  of combustion  gas entering the boiler was provided
but as a function of refuse lower heating values.
 * Actual temperatures will vary from these average  temperatures
  depending on the time of year.

-------
                                        78
                           Lower Heating Value,     Amount of Gas,
                                 kcal/kg              Nm3/hour
1,000
2,000
2,500
33,000
77,000
98,500
          Lowest
          Average
          Highest
          The  combustion gas inlet temperature  to the boiler is around  800
C (1,^72  F).  The outlet combustion gas temperatures range from 280 to 350
C (536 to  662  F).
          Details of heating surface  area  are shown below with the codes
also appearing in Figure 1U-29:
                                                           Units
          First Pass Radiation Wall (R1)
          Second Pass Radiation Wall (R2)
          Third Pass Radiation Wall (R3)
            Regular Radiation Walls
          Scott Walls (S1 and S2)
            Total Radiation Walls
            Convection Section (C)
            Economizer Section (E)
              Total Heating Area

          Boiler cleaning has been an experimental matter at Amager.   They
tried  acoustic (sonic)  cleaning.  They  also tried vibrating (mechanical
rapping)  the tubes.  Now  for the convection and economizer sections,
falling  steel shot is  used  routinely.   On shutdowns; the first, second,
and third open radiation passes are manually brushed clean.
          Mr. Pinto referred several times to their corporate position of
not participating in the municipal  waste  to very high temperature  steam
systems.   They will not  sell anything  that would likely have corrosive
failures within a year or two.  As  Mr.  Pinto  stated,  "It's not  fair (to
the customer) to build a system that might fail".
          Volund later clarified its position with the  following statement.
          "The highest  temperature in any of the Volund plants is 490 C at
          Ortvikens  Papperbruk,  Sundsvall, Sweden.   The plant  which is

-------
79
                                                                   O
                                                                   M
                                                                   CO
                                                                   Pi
                                                                   W
                                                                   O
                                                                   PP
                                                                   W
                                                                   O
                                                                  O-
                                                                  I

-------
                                      80
          mainly for bark incineration is equipped with an Eckrohr boiler,
          which produces steam at 425  C,  and in a separate   overheater
          the  temperature is brought up to 490 C  - 67 ato.

          Sundsvall, Sweden - steam:    28.5  t/h  - 67 ato - 490    C
          Itabashi, Japan, - steam:      28.9  t/h  - 16 ato - 203,4  C
          Nishinomiya, Japan - steam:   14.6  t/h  - 18 ato - 208,8  C
          Kawagushi, Japan - steam:      15.8  t/h  - 16 ato - 203,4  C
          Kohnan, Japan - steam:        35.9  t/h  - 16 ato - 203,4  C
          Boras, Sweden - steam:        16.5  t/h  - 10 ato - 285    c

          If a customer wanted excellent burnout  rates, wanted  500 C
(932 F) steam, and  showed high interest in Volund;  then Volund might
submit a bid.   Volund  could propose  to raise  the  steam  temperature
to 300 C (572  F) by burning refuse.   The steam would  then be  input
to a topping off fossil fuel (likely oil)  boiler  to raise it  to the
500 C (932 F)  level demanded.

                             Convection Section

          An interesting  corrosion problem developed at Amager, but not
West,  due to  the  temperature of  the entering  feedwater.   Amager's
returning warm water is  about 70 C (158 F). The manufacturer had warned
the system owner that  this would put the metal temperature at the  entrance
to the  convection boiler  section  in  a  dangerous  "dew  point corrosion"
temperature zone.   Another cause for the dew  point corrosion was  the many
early (first 2 years)  shutdowns due  to crane  malfunction.
          Thus,  with  accepted forewarning,   the system was constructed.
Some  of the lower convection section bundles  were replaced  after 30,000
hours because  of dew point corrosion.
          Later when  the complete line was overhauled after  42,000 hours,
the entire convection system was replaced.  There are thicker tubes on
the bottom and thinner tubes on the  top.  Officials  now hope that  the
unit can go for 60,000 hours without corrosion rupture.

-------
                                     81

                                 Economizer

          The economizer  and its steel shot cleaning system both were
supplied  by Eckstrom of Stockholm, Sweden. As at West,  the Amager
economizers were  fin  tube with small spaces.  The  spaces and corners became
so  clogged with  flyash and steel shot,  that  they will have to be replaced.
Because of the clogging, the economizers  at both  Amager and  West have set
the overhaul schedule  for the whole plant. Until the  economizers are
replaced, the unit will continue to shutdown  every 1,500  to 2,200 hours.
The manufacturer's  original recommendation  of shutdown for inspection and
cleaning every 3,000  hours would have been mainly to restore efficiency.
The economizer is cleaned manually with  brushes.
          It is  likely  that  the electrostatic  precipitator corrosion
problems experienced were caused by the clogged economizer not doing its
job, i.e. lowering economizer flue  gas  exit temperature to below 300  C
(572F).
          Unfortunately,  shot cleaning was not in the  original design.
Therefore,  on retrofit, the falling shot  was  down—concurrent to the flue
gas.  In future economizer designs, both the gas flow and the steel shot
flow will be downward.

                           Boiler Water  Treatment

          The boiler feedwater is  thoroughly  treated at  the adjoining
power plant. Treatment includes deaerating, desalting and demineralizing.

                                  Cofiring

          Cofiring is not a significant practice at Amager.  However, and for
the record,  in 1931 Volund did cofire Gentofte with bark and  coal  in a 3-1/2
tonne/day unit.   In late 1977,  Volund had a proposal to a Polish city that
included cofiring of refuse and coal.
         The reader is referred back to the Waste Input Section where
there is a  discussion about original  inclusion of sewage sludge  and waste
oil.  Currently there is some  sewage  sludge coarse ridlings put  directly
into the pit for mixing with refuse.   No appreciable waste  oil is  cofired.

-------
                                       82
                          ENERGY  UTILIZATION EQUIPMENT

          Figure 14-30 shows  the  refuse burning plant in  the foreground
with  the larger conventional power plant, owned by Copenhagen Gas and
Electric, in the background.  The  refuse plant  is a base load plant.  The
conventional plant,  being the peaking plant, can adjust its operations to
ensure steady energy delivery depending on season.
          The refuse  plant's hot  water is sent to the electricity plant,
but it is not used  to  make electricity.  Rather, the hot water is combined
with the electricity plant's waste heat and together they supply  the
Amager Island district heating network.
          The Amager  refuse  plant sells its  hot  water for a lower price
than does the West  plant  for  several  reasons: (1) the water  temperature is
lower  at Amager and  hence  contains  less energy per pound; (2) the single
distribution pipe to the  power plant  is only a couple of hundred feet;  (30
Copenhagen Gas and Electric Authority (CGEA) handles the district heating
distribution, so the refuse plant has no distribution expenses, and  (H)
the refuse plant's  energy competes  with the CGEA plant's waste heat.
          Roughly 1.2  Gigacalories  (4.76 million Btus)  can be  added  to water
per tonne of refuse  burned.   At Amager, the annual average sale price  to CGEA
varies  from 55 to 60 D.kr.  per Goal ($2.40 to 2.62/million Btus).  The  formula
is somewhat unique.  If the CGEA electric power plant is working and producing
its wdn waste heat,  then  the  energy value paid to the refuse plant is  60 per-
cent of the comparable oil price for the same energy.  However, if the electric
power plant is not  in  operation,  then  the refuse plant receives 100 percent of
the comparable oil  price.   All calculations are based on heating value and  not
on volumes of water.
          Under  this  arrangement, the refuse plant sold 70 percent of its
production during 1975-1976.   The percentage has been increasing from  year
to year.
          Belysningsvaesen or Copenhagen Gas and Electric Co. was the
consultant  for Amager Incineration  and was in charge of the project as
their  experience power stations was assumed  to  be of value.
          The plan with Amager Incineration was to  sell district heating
to the communities  forming the partnership.  The  Power  Station next to
Amager Incineration has a surplus of waste heat in  much more  quantity  than

-------
                                    83
FIGURE  K-49.  COPENHAGEN:  AMAGER'S REFUSE FIRED ENERGY PLANT IN THE
               FOREGROUND AND THE OIL (OR COAL?) FIRED PLANT IN THE
               BACKGROUND

-------
                                      84
 the Incineration plant.  Thus to avoid competion and duplicate pipelines, an
 agreement  took place where Amager sells  the  heat to the Power Station.
 Nevertheless by  1982 the Amager  plant shall have installed Unit No.  A  and
all the  heat produced can be sold as a  pipeline under the  canal  to the
Copenhagen  city,  where a pipeline will  be installed in  the meantime and
 better prices  for  the sold heat  will be achieved.
         Heavy  insulated water pipes  are  shown  in Figure  l4-31a.  The
pumps  used  to send steam to the  combined  district heating system are shown
in Figure 14-31b.
         Amager produces hot  water at 115 to 120 C (239  to 248 F) at 6
kg/cm2 (85  psi).  As stated before, this  is lower quality hot water than
the superheated water at West.  Amager  sends its share  of the energy to
the power plant which then distributes it to  the district heating  system
shown in Figure 14-31C.   Of the  total energy sold, 50  percent goes
directly to  household radiators.  The other  50  percent transfers its
energy through water-to-water heat exchangers before going  to radiators..
         The total energy delivered to the district heating system is
shown in Figure 14-32. Note that the  summer  base load  is usually  8,000
Gigacalories while the winter peak load is  around 20,000  Gigacalories.
Presumably  a  few industries, hospitals, etc. provide the  base load in the
summer.
         The 1975-1976 energy sold amounted to 188,253  Gigacalories
 (746,988 million Btus) for a  revenue  off  4,877,703 D.kr . ( $8 1 2 , 950 ) .
Dividing revenue by quantity  results  in an  average sale  price of  25.91
D.kr./Gcal  (1.09/million Btus).
         Since  the hot water is "priced"  at $2.40 to 2.62 per million Btu
and the  "average revenue" over  a year's time is only $1.09 per million
Btu;  it  is  assumed that only  44  percent  of the hot water generated is  sold.
         Having monitored events at the  Nashville  (Tennessee) Thermal
Transfer Corporation (NTTC) we must point out to the reader that more
revenue  derives from district cooling than from  district heating.   We ask
the retorical  question, "Is  there a  future for district cooling for
European systems that will even the   seasonal  revenues  from  energy
production  and raise annual revenues?"

-------
                                 85
                                                 JB>
 FIGURE  14-31a.
  INSULATED HOT
  WATER PIPES
  LEAVING BOILER
  AT AMAGER
                                                   FIGURE 14-31c.  MAP OF
                                                                  DISTRICT
                                                                  HEATING
                                                                  NETWORK
                                                                  OF AMAGER
                                                                  ISLAND
FIGURE 14-31b.
PUMPS TO SEND HOT WATER TO
THE POWER PLANT WHICH SENDS
THE HOT WATER TO THE DISTRICT
HEATING NETWORK AT AMAGER

-------
                                           86
                                     Gigacalories
                2000  4000   6000   8000   10000  12000   14000   16000   18000   20000   22000  24000 26000
1972
-___      MAJ
1973      JUNI
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
     NOVEMBER
     DECEMBER
        JANUAR
       FEBRUAR
         MARTS
1974
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
      NOVEMBER
      DECEMBER
        JANUAR
       FEBRUAR
         MARTS
1974     APRIL
           MAJ
1975
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
     NOVEMBER
     DECEMBER
        JANUAR
       FEBRUAR
         MARTS
1976
           MAJ
           JULI
        AUGUST
     SEPTEMBER
       OKTOBER
     NOVEMBER
     DECEMBER
        JANUAR
       FEBRUAR
        MARTS
                                                                                              §
                                                                                              H
                                                                                              W
                                                                                              O
                                                                                              H
                                                                                              O
                                                                                              M
                                                                                              Q
                                                                                              W
                                                                                              K
                                                                                              H
                                                                                              O
                                                                                              H
                                                                                              PJ
                                                                                              w
                                                                                              w
                                                                                              Q
                                                                                              O
                                                                                              CM
                                                                                              CO
                                                                                              W
                                                                                              04
                                                                                              &
                                                                                              O

-------
                            87
      More of Mr. Blach's Comments on Heat Exploitation

    "It will always be economically profitable to  exploit the
heat from an incinerator plant, whenever possible.
    The heat  can  be  used for  district  heating,  various
industrial purposes,  drying and burning of sewer sludge or other
sludge products, and for production of electricity.
    If the heat cannot be exploited,  other arrangements must be
made to cool the  900-1000  C(1652 0 1832 P), hot  flue gas to
about maximum 350  C (662  F),  before  it is led into  the
precipitator and the chimney.
    Such a cooling of the flue  gas can  be done by adding air,
water spray, a combination of water spray and air, or by letting
the flue gas through a waste heat boiler and then cool  the water
or steam.
    Initial expenditures of  plant as well as operational costs
for the  cooling plant with air, water spray, or a  combination
are  just as high as the  costs  of  an actual  plant  for heat
exploitation with a possible supplementary air cooler.  The sale
of  heat,  therefore,  is an  actual working income,  which
contributes essentially to the operation of the plant, even with
regard  to the  extra costs  for repair  caused  by  wear and
corrosion in the convection part of the boiler part.
    Least profitable  is the  production  of electricity  as the
costs of high pressure boilers and turbines are too  high and the
efficiency too  low compared with the low price at  which the big
power stations can produce the electricity.  There is a  great
need for drying and  burning sludge, and the use  of waste heat
for the  purpose can be expected to be common in the  future. Sale
of  heat for district heating  or industrial purposes has,
therefore,  up to now been the solution which  technically and
economically has shown the best results."

-------
                                   88

                       POLLUTION CONTROL EQUIPMENT

                              Air Pollution

         Both at Amager and West, Rothemuhle  two field electrostatic
precipitators  (ESP) are the sole means of  air pollution control now  in
efffect. Plant  officials were initially hesitant about this and had
thought  of the need to add a mechanical cyclone collector after the ESP.
They wanted to make sure that the larger paper particles  would for certain
be captured. Therefore,  they mandated  that  room should be available for
adding  the cyclones later if necessary.  The space is outlined with dash
lines in the previous Figure 14-1. As discussed later, there has been  no
need to  add any cyclones.
         The  ESP  inlet gas  flow is  107,000  Nm^/hour. The flue gas
temperature is designed to be around 300 C  (662 F) with a 350 C (662  F)
maximum. Because of the  clogging economizer  section of  the boiler,  there
have been many excursions well about 350 C (572 F). As a result, there has
been some corrosion at the top and front end  of the ESP. Volund estimates
the inlet loading to be 7.5 g/Nm3.
         Each of the two fields is 8.5 m  (28 ft) high,  and 7.0 m (23  ft)
deep. Flow-model studies  were not conducted before installation. The
average  flow  velocity is  0.86 m/sec  (0.26ft/sec). The maximum is 1  m/sec
(3.3 ft/sec). Each ESP field has two  rectifiers. Volund would permit a
one-field ESP only on a  small system where  the regulations are not  as
stringent.
         Again it is helpful to quote  from  the Interersentskab brochure:
              "In  the  electrostatic filter the  speed of the  smoke  is
         reduced to approximately 1 m/s,  after which the smoke passes
         between vertically suspended, electrically earth  connected
         profiled steel sheets. The mutual distance between the sheets  is
         about 25 cm (10 inches).  Tightly  stretched between the sheets
         are  a great number of steel wires, equipped with spikes.  The
         steel wires are insulated  when hung  and are connected with  an
         80,000 volt direct current generator. When the smoke slowly
         passes this system of negatively charged steel wires, the dust
         particles carried along will be electrically charged and will

-------
                                      89

         therefore be pulled over onto the earth-connected  (grounded)
         sheets.  Thus, a continuous layer of dust will gradually  be
         formed  on the sheets and can  be shaken off by hard blows on the
         sheets.  This causes the lumps of dust  to drop into  accumulation
         funnels.   The flyash at Amager falls into a water bath and is
         transported to a rubber belt conveyor  by a screw conveyor.
             The total efficiency of the  electrostatic filter is more
         than 98 percent. During  1972,  approximately 5,000 tons  of fly
         ash was separated through Amagerforbraending's filters."
         Even though the ESP is housed  inside the normally warm
furnace/boiler room, the ESP hoppers are equipped with electric heaters.
When the  room temperature falls to 10 C (50 F),  the heaters are  turned on
to prevent possible dew-point corrosion in the ESP.
         Fly  ash  is removed from  the bottom of  the ESP hoppers
pneumatically. The pneumatic tube dumps  onto a  conveyor belt  for transport
to the ash bunker to be humidified.
         During the plant tour,  a  "gray smoke indicator" registered
                                                      o
values between 6.5 and 8.0 on the Ringleman scale.  The 0  meter  was not working.
         Upon startup, the  unit exceeded  the 150  mg/Nm3  limit for
particulates. The primary reason was that a standard ESP  (without  special
entrance vanes)  was used to clean a very highly loaded flue gas.  The
Amager estimate of 7.5 g/Nm3 compares with more  typical inlet loadings of
around 5 g/Nm3.   This 2.5 g/Nm3 difference is  attributed mostly to use of
the rotary kiln compared to a grate only  system.
         Because  of  noncompliance,   Rothemuhle   complied  with  its
guarantee.   They  then did conduct  flow model tests. Turning  and guide
vanes were  added. The tests proved so successful that they again concluded
that cyclones would not have to be added.
         The  new Danish air  pollution regulations specify limits for
particulates, HC1, and S02 (corrected to  11 percent 02  and 7  percent C0?).
Amager tests show that the unit is now well within the limits.
                                     Danish Law      Amager  Plant
     Particulates (mg/Nm3)               150              60- 90
     HC1  (mg/Nm3)                      1,500             700-900
     S02  and S03 (mg/Nm3)             1,500             200-300

-------
                                        90

          Because the HC1 and S02 gases are in compliance, no scrubber has
been needed.   A new  feature of the law is that particulate tests are  to be
made every month.  The  sampling point  is 50 m up  the  150 m chimney. The
respected Danish Boiler Testing Company is employed to perform the tests.
          One emissions analysis reported is as follows:

          Nitrogen  (N2)                                  66.40$
          Oxygen (02)                                    12.40*
          Carbon Dioxide  (C02)                           12.MO$
          Water (H20)                                     8.64$
          Hydrogen Chloride (HC1)                         0.06%
          Sulfur Dioxide  (S02)                            0.01$
          Unidentified and Measuring Errors                0.09%
            TOTAL                                        100.00%

          (Nitrogen  is normally 78  or 79 percent on a  dry gas basis (no
          H20).  But even dropping  the H20 out, the N2 is still not near
          78 percent.  This analysis  appears  in  the attractive  brochure
          Amager-forbraending Interessentskab.  The  Volund system does not
          produce much NOX  relatively  due  to  the lower combustion
          temperatures.
           Officials repeated  a  statement heard  elsewhere  in Europe
and America that,  "for each 1 percent above 96 percent efficiency,  the ESP
purchase price doubles".  This, of course, is far from accurate.  However,
it makes the clear point  that going from clean air emissions to very  clean
air emissions is very expensive.

                             Water Pollution

          Amager discharges a small amount  of waste water directly into
the canal.

-------
                                     91
                           ASH HANDLING AND DISPOSAL
           Unfortunately,  the new handling system at Amager caused
  considerable problems.  West designed differently and operates much
  better.  Basically,  Amager uses a sluice, pusher and conveyors (see
  Figure 14-33) while  West  uses a skip hoist (see Figure  14-34).
          Because of the  high  temperature on  clinkers at  furnace outlet
(rotary kiln  outlet) an ash pusher  alone cannot do the perfect job as the
necessary  air tighteners would be lost when it is not possible to  maintain
an ash column on the chute.
          If  the ashes  can  be held  in the chute  and  thus create
air-tighteners between the atmosphere and  the vacuum inside the furnace as
it is  the  case  in small furnaces  without rotary kiln,  the ash pusher alone
is the ideal  solution on servicew and economy.
          But the accumulation of ashes of 800°C will result in a condense
mass of clinker impossible to  discharge.
          To avoid  the problem  a sluice is  included in  the system
maintaining airtightness and in the same  chute  a water spray cooling is
included.
          Originally the  Amager rubber  conveyors (Figure 14-35a) let too
much water and fine ash out and into the tank  bottom. The material would
settle, build  up,  and  then interfere with  the conveying. There was
excessive  wear on rollers and nylon bearings.  Downtime for repair and
fines removal was excessive.
          To partially solve  the  problem, stainless steel apron  conveyors
were replaced by vibrating conveyors. They have  also installed air pipes
in the  bottom of the fines  tank to keep the siftings in solution so they
can be removed.
          Another major difference is that Amager uses about 3  tonnes of
water per  tonne of ash while West uses only 1 tonne of water  per tonnne of
ash.
          Ash disposal at Amager is entirely different from the  treatment
at West.  The ash is  simply  trucked  (Figure 14-35b)   to  reclaim further
portions  of Amager Island.  It  is very profitable in that 1  m^ (1 yd^) of
land reclaimed from the sea is worth 200 to 300 D.kr.  ($35 to 52). About 3
m3 (4 yd3)  volume of ash is used to reclaim a 1 m^  (1  yd^) area.

-------
92
                                                        Pi
                                                        w
                                                        a
                                                        w
                                                        u
                                                        to

                                                        K



                                                        to

                                                        0
                                                       g
                                                        i
                                                        o

-------
                      93
  V



  N
              3rt   0-
  •V


  N


  V


  V
          Y
                                                   H
                                                   W
                                                   M

  s

  \
///7Y7\
                                                   I/I

                                                   is
                                                    w
                                                    H
                                                     W
la
                                                    g

-------
                                           94
                    FIGURE 14-35a.  RUBBER ASH  CONVEYOR AT
                                    COPENHAGEN:  AMAGER

                                                                                <\ v —>
**»."„,
              FIGURE 14-35b.   FERROUS SEPARATION  FROM ASH AT
                              COPENHAGEN:  AMAGER

-------
                                    95

                                CHIMNEY

         The chimney was  constructed by a local contractor,  Ramboll
Hannemann, using  a Polish patented system for continuously pouring
concrete.  The stack  has a 2.8 m (9.2 ft) diameter.  Most of the stack  is
lined  with 280 mm  (11  inch) thick plain carbon steel.  The flue gas
velocity is 27 m (89  ft/sec).   At the top 10 m  (33 ft), there is a corten
steel that is used  to prevent  corrosion.  The stack height is 150 m (500
ft).

-------
                                     96

                         PERSONNEL AND MANAGEMENT

                                 Personnel

         Amager's personnel structure  is  based on five shifts: early
mornings, days, nights,  weekends, and replacements.   Each shift has four
key  men--the  supervisor, boiler tender,  furnace tender, and crane
operator—for a total of 20  operating men.
         Another  23 men  are  utilized in maintenance, repairs,  and
cleaning.  Two men are used at  the  scale  house and two are used on  the
tipping floor.
         The  administration personnel  number six people: the director,
operating manager, office manager,  two office  employees, and a canteen
lady.
         Realizing that the plant  runs  2U  hours  per day, 365 days  per
year, many of the above personnel are used as vacation, holiday, and sick
replacements.   Considering  this,  the total plant staff numbers 53
employees.

                                Management

         The Amager operations  are  managed  by representatives from  the
five  communes  listed in Figure 14-36.   Note  that 18 people attend  the
annual general meeting (community stockholders meeting).
         More frequent meetings are held with  the management  committee of
six representatives: a chairman, and the borgomiester from each commune.
         Finally, the day-to-day  administrative  director is the focal
point for the  communities with the plant personnel.

-------
                                       97
1975-76
COMMUNES
Drag0r kommune
Frederiksberg kommune
Hvidovre kommune
K0benhavns kommune
Tarnby kommune

REPRESENTATIVES TO THE ANNUAL COMMUNITY SHAREHOLDERS MEETING

Borgmester Alb. Svendsen
Viceborgmester Chr. Lauritz-Jensen
Landsformand Arne Ginge
Borgmester Svend Aagesen
Kommunalbestyrelsesmedlem Jens Kristensen
Kommunalbestyrelsesmedlem Alf Christensen
Borgerrepraesentant Gunnar Ulbaek
Borgmester  Lilly Helveg Petersen
Borgmester A. Wassard
Forretningsf0rer Andreas E. Hansen
Overborgmester Egon Weidekamp
Overlaerer Kit Falbe Hansen
Skoleinspekt0r Niels J0rn HougSrd
Typograf Kurt Kristensen
Havnemester Elhardt Madsen
Borgmester  Tork. Feldvoss
Generalaudit0r Jens Harp0th
Journalist Marcelino Jensen

MANAGEMENT  COMMITTEE
Borgerrepraesentant Gunnar Ulbaek (formand)
Borgmester  Lilly Helveg Petersen
Viceborgmester Chr. Lauritz-Jensen
Borgmester  Tork. Feldvoss
Borgmester  Svend Aagesen
Borgmester  Alb. Svendsen

ADMINISTRATIVE DIRECTOR
Willy Brauer (administrerende direkt0r)
     FIGURE 14-36.  MANAGEMENT STRUCTURE OF COPENHAGEN:  AMACER

-------
                                    98

                                ECONOMICS

                    Capital Cost (Assets and Liabilities)

          The  1975-1976 annual report  presents an accounting schedule of
assets  and a schedule of liabilities.  These are shown in Tables  14-3.The
refuse-fired  hot  water generating plant itself  cost 117,600,000 D.kr.
($16,650,000)  during the 1970-1972 construction  period.  The  original
capital costs were as follows:

          Ground Work and Construction           63.0 million Dkr
          Machinery                            45.0 million Dkr
          Other Costs                           9.6 million Dkr
           TOTAL                             117.6 million Dkr

Since  then, another  40  million D.kr. has been  spent on capital
improvements. Both assets  and liabillities, by  definition, equal
181,452,000 D.kr.

                      Annual Costs (Expenses and Revenues)

          Annual costs and revenues  are distributed as shown  in Table
14-5.   On the revenue side, note that the tipping fees ($6.06/t) and the
general head tax ($11.33/t) provide  most of  the revenue totaling $17.39
per ton.     Charging a tipping fee of only $6.06/ton encourages  suburbs,
private haulers and industries to contribute  waste.  If they had  to
support  the  entire  $17-39 per  ton,  many who have  freedom  of choice
regarding  disposal, might apt for landfilling at a distant site.   Having
the foreing  waste and its tipping fee will help carry some  of the fixed
expenses.  The revenue  from district  heating, originally planned to be
2,200,000 D.kr. in this year, actually turned out to be more than double
that at 4,878,000 D.kr.  By  definition of a "not-for-profit organization",
the expenses  must equal revenues.   In this  case, they are both equal to
36,305,000 D.Kr. ($6,272,460).
          Table  14-7 presents  the annual costs  and revenues per tonne for
almost 5 fiscal  years.  Note  that increased revenues from the sale of heat

-------
                                    99
         TABLE 14-3.  ASSETS (MARCH 31, 1976) AT COPENHAGEN:AMAGER
Current Assets (Cash, Stocks, Supplies)                   12,882,000 Dkr
Money on Loan to Others                                    2,431,000
Transfer Station                                           8,980,000
Landfill                                                   1,625,000
Refuse Burning Hot Water Generator*                      155,534,000
Under Surplus, 1972-1973                     4,339,000
Over Surplus, 1973-1974        1,757,000
Over Surplus, 1974-1975          489,000
Over Surplus, 1975-1976        2,093,000     4,339,000   	
  TOTAL ASSETS                                           181,452,000 Dkr
* Includes 7 years of improvements.

-------
                                 100
     TABLE 14.4.  LIABILITIES (MARCH 31, 1976) AT COPENHAGEN:AMAGER
Loan on "Refuse Fired Hot Water Generator                      101,920,000 D.kr.
Loan on Landfill                                                  108,000
Short Term Creditors                                            2,538,000
Accrual Account for Test and Development with
  Waste Treatment                                                  60,000
Accrual Account for Finalization of Building Surroundings
  and Machinery Works                                              35,000
Accrual Account for Renewal of Ash Transportation
  Plant (?)                                                     1,566,000
Accrual Account for Interest and Capital Return               321,927,000
Equity in the Refuse Burning Plant                             39,718,000
Equity in the Transfer Station                                    580,000
  TOTAL LIABILITIES                                           181,452,000 D.kr.

-------
                                    101
     TABLE 14-5.  ANNUAL COSTS DURING 1975-1976 AT COPENHAGENrAMAGER
Operational Salaries                                       5,028,000 Dkr
Other Operation Expenses                                   2,196,000
Ash Disposal Expenses                                        769,000
Transfer Station Expenses                                  4,008,000
Landfill Operation Expenses                                  853,000
Administrative Expenses, Meetings                            197,000
Administrative Salaries                                      514,000
Other Administrative Expenses                                224,000
Plant Maintenance                                          2,415,000
Government Taxes and Other Fees                            1,018,000
Interest on Loan                                           7,425,000
Depreciation on Plant                                      8,000,OOP
  TOTAL EXPENSES                                          32,647,000 Dkr
Account Set Aside to Build an Ash Transportation           1,566,000*
  Plant
Surplus Returned to Asset Account                          2,093,000
  GRAND TOTAL                                             36,305,000
  Amount set aside for changing  (1) existing ash discharge plant with
  new  (1977) ash transport plant  (2) existing rubber belts with vibrating
  conveyors (3) magnetic separation and  (4) ash treatment prior to selling.

-------
                                    102
      TABLE 14-6.   REVENUES DURING 1975-1976 AT COPENHAGEN:AMAGER
Communities' Tipping Fee at 40 Dkr/tonne  ($6.06/ton)
                                          *
Government (?) Tipping Fee at 40 Dkr/tonne
Private Haulers' Tipping Fee at 40 Dkr/tonne
                        *
Head Tax at 30 Dkr/year  ($4.55/year)
Revenue From Energy Sale to District Heating Network
Transfer Station Tipping Fee (?)
Landfill Tipping Fee
Interest Earned on Current Assets
Rent of Excess Office and Filing Space
  TOTAL REVENUES
                                       7,872,000  Dkr
                                         169,000
                                       2,423,000
                                      16,441,000
                                       4,878,000
                                       2,743,000
                                         515,000
                                       1,019,000
                                         246,000
                                      36,306,000  Dkr
  Net Disposal Fee
=  tipping fees + head tax
= $6.06  +   $4.55
   ton    person year
= $6.06/T  +  $11.33/T
= $17.39 per ton
                                            (  1 year)(l day person)  (2000 Ibs)
                                            (365 days)(  2.2 pounds)  ( 1 ton  )
           Assumes 6.00 D.Kr. per U.S. $ in 1975-76

-------
103
"o o
o
°^ .
o
vO ON
ON
rH
r--. O
ON O
1
in in
r~ m
ON CM
rH


m
r^" ^^
ON O
1 **
*xf S3"
1 — CM
ON CM
i— 1

I**** C3
O^ O
r~H ^^
1
00 \O
r-- CN
ON CM
rH


oo
p-^ O
ON O
1
CM O
p~ CM
ON CM



























Tj
CO
C
J-I
^
£Q

CO
Ol
c
pi
o
H
ON
ON
O
CM


CM
f^
ON
rH





«^j-
OO
00




sf
O
^
rH






^-
rH
CM
rH





































cn
0)
60
to

p-
!•••
ON




xO
00






CM
 00






CM 00
r~ ^f
CM 00




v£> O
CM r~
CM CM







r-. CM
rH 1^
CM CM



























rH
cO
co C
o o
ex -H
CO 4-1
•H CO
f~} ^4
4-1
)-i cn
0) -H
A! a
C -H
•H p
rH -d
O •<
in oo
CM O-
rH -3"
1— t


p^ e?N

CTN O
in -
bO

01
C
W

4-1 £
CO O
O rJ
O fe

rH CD
cd 3
•u C
O Ol
H >
a;
oi
CM
"*
00
O


00
00
ON
00





i-l
rH
vO
O
rH


r^
•*
\D
ON






ON
CM
ON
ON




















01
e
o
o
G
M

bO
C
•H
4-1
CO
VH
01
ex
0

4-1
CO
K


ON vO
m ON
vO O



ON vo
ON ON
00 O






00 OS
 4J
4-1 C
G 01
M Czi

e e
o o

fXj ['T |

Ol 01
3 3
c e
Ol 0)
r* K*
0< OJ
p3 r^\
P-.
oo
m
OS


oo
oo
.3.
oo





N^-
m
o
o
rH


r^
ON
^j.
ON






ON
i— 1
co
ON
































4-1
CO
O
u

4J
Ol
^t














CO
•H
CO
•H


rH
•H
O
4J
O

01
3
T3

4-1
CO
0)
*
i[ ]
O
0)
rH
cfl
CO
e
o
IH
CU
a
o
u
c
•H

c
•H
CU
CO
•rl
^1

}_l
tO
co

1
o
4-1
1
t-l
tO
0)


u
•rl
4J

c*
tO
J.J
P

*

-------
                                      104
have offset  increases in operating costs so that the  net  cost to the
taxpayer has remained relatively steady for 5 years.

                   Profitableness  at Exploitation of Heat

         For the final time, Mr. Blach's comments are entered  into the
American record.
         He  presents  the analytical logic one would expect supporting
"economy of  scale  theory".   We,  however,  have learned that in actual
practice there  is  little economy of scale.  Designers and  customers of
large plants tend to mitigate the potential economies by extra "bells and
whistles"  which would  not be considered in the small plant.
          This presents the economics of a 3 x 12 t/hr plant versus a 3 x
3 t/hr plant.  The  analysis uses three different Kcal/kg estimates and two
utilization rates.
             "As mentioned before, the cost of the  installation of a
         boiler for the recovery of the waste heat can  be expected to be
         of  the same  magnitude as the cost of other forms of  installation
         for the  cooling of  the flue gas. In the  same way,  the
         operational  and maintenance costs can be calculated  to  be of the
         same  magnitude  provided the boiler construction  is  executed
         correctly and  appropriately, taking into  consideration the
         special corrosive, wearing, and clogging properties  of  the flue
         gas.
             As  previously mentioned, the  income from the waste heat
         sales will be a  real operational income which can cover  a larger
         or  smaller part of the operational costs, depending  on  how large
         an  amount  of  the produced heat can be sold and  at which price.
         The following enclosed  two tables (Tables 1M-8 and 1^-9) show
         examples  of  operational  costs (exclusive of  interest and
         depreciation) and incomes resulting from heat sales  from a large
         plant with three units of 12 t/h and a smaller plant with three
         units of 3  t/h.  Figures are  calculated  for  net calorific
         values of 1,500, 2,000,  and 2,500 Kcal/kg.   Plant  utilization
         for  the  smaller  plant is  50  percent  and 75  percent,
         respectively, and for  the  larger  plant 65  percent and 80

-------
105











H
3
SB U
^_
>H h
PQ r-
Pd
pa C
O ^
u u
53
M H
U
O S3

5 W
iJ
£5
s s
rl PCj
H <
£>
CJ Pi
pa o
M pn
PH
W J=
Q ~~-

Q
Z CM
< i-l

E-i P*
C/0 O
Pi CO
W U
H U
a «:
hH £3
p2
fe p
o E

H pa
> pa
H pd
co SS
P H
iJ
0 S3
X H
pa M
**mi/ t~Z

CO H
H 53
CO 53
O iJ
c_> PM
^
SB S
0 0
M cd
EH pti
S pa
w >-j
PH ^
O CO


*
CO
1
*^
rH

HJ
5
H












































K
M
O









































60
ffi

0)
3

cd


o
•H
H-l
•H
M
0
cd
U
4J
0)
^










































n
*^»^
4J

CM
rH

^
CO

• •
^»
U
•H
CJ
cd
a.
cd
u

4J
a

rH
PH



60

~-»
cd
o
o
o
CM








60

* — .
H
cd
o


o
o
o
CM








60

•^
cd
a


o
O
in

























.•
>
4J
•H
U
td
C

C,

^
E

r-4
tt
T-
e
C
C

CJ
•H
^
O
(U
r
H
















C
O
•H
4J
td
N
•H
i— 4
•H
4-1


O

CD
01
M
60
01
O









































1

<
\
(


1
(


\
<



<



(




<



6^5
o
00





m
VO






6-S
O
00








!n







5*5
O
00







n





















^
cd
0)
^
^.
4-1

D
0
•n
«
n
-i
•o
n
n
o
•o

X
*
N

^

N
H

^

n
oooo o o
oooo oo ooo
coomco -*o ocMvo
cNTcTr-ror -^cT o\o"-*
mi— i o -* CMO cMin
CM «^ CO i— ( C"O i-H
vo r^ iH

OOOO O O
omoo oo OCMO
in en oT vo  f.
CN ^O CO


s~^ *O
)-i K ^
cd a) ij
a) cd
>^ ~> 4J a)
-^ b w >•
vO ^ tt) -^
O ' M tl
rH C 0) J< ^

4J -D " I
w" *> i ^" s
•H -H g co
o 4-1 en 4-1 , ^-» ^v

ij cdM cdMcdcdcd
3^^ rj ^ CU tt) Q)
4J Q • ^ r* ^
cdvO OlrH>-,^ — ,-HC •**• I ^~
0)4-1 CO>,McdQ^4J^
CJ Cd T5 IH • V4 *~s • CO •
•H rH 4J ^i C 0) Ci O C
o 4-* o cd • cd ci< ^^ cd o cd
C3 td CO Q)£j£3 OC Q O
•HO) 42 Cd *— ^ O N— ' rH V— ^
J2 >% Q "B vH cd
0) rH !X1V~' /-v CU 4J x-> C r-N
> «O ,O ,Q rH4JCdrHOin
•HCUcd rH'-Cd-H-'iHI
4-1 U B OI Cd -3- i-l CJ VO 4J r-~
O g 9 6 cj >fc^ !3 ci) v^ ed ^-^
CUT3COOM O M ri
14-1 O 0) CJvO • i-H CX • OI
U-lMMCOOCdOIOO-O


• ••• •• •••
i-HcNcn-* mvo r-oooN

-------
                                             106
%
X

>H
PQ U
  M
r-r-1 rTj

o S
u o
Z rJ
H 
a
CO _,r.,
S3 HIO
^J    W
U ffi Q

  SQ
-5^

c/) H
H 2! W
C/3 < W
O rJ
CJ ex.
     s
^^
a s fe
OOO
H ftf
H Fn C/2
«jj   W
W W C3

A^ ^ ^
 I

4J
•H
a
cd
o
cd
u

4J
c
ct
P""


00

cd
CJ
o
o
in
CN






00
^
^-
cfl
U
O
O
o
CN1







60
•^
cd
o
o
o
in
^































1



•I


















c
o
•H
4J
cd
Nl
•H
1
•H
4J
WH
o

0)
^t
00
01
0




























.1
>^
J
H
o
cd
a

o
>
^
cd
°

H
cd

H
E
o
c

o
•H
^J
o
j£


s
f"-





o
m




gv°
in
r^






o
u-i






in
^





b
m














o

\£> -3- m CM
CN CO CN iH
in



o o o o
CN O O O
crT w oo" *T
in


0 0 O O
oo o o o
CM r» ro -ct
viT in ON -a-*
CN CM rH 00
CO
^
cd
cu
o j
iH C

cd cd
cu cj o
>~, M CN
4J P>.
"-- >, ^H
•U rO
^ *H cd
w > 8
•H -H 3
U 4-1 CO
a u s^ -i .c cd
Q) 4-1 CO
C cd -o
•H rH 4-1
o 4-i o cd
C cd co 0)
•HO jr
J3 ^
0) rH f>~,
s ^ »O TJQ
•H 01 cd
4-1 CJ B -
0
o
u>
CN
^
m
o
0
in

o
o
-*
^3."
00
CO




">
Ai
c
cd
Q

o
CN
P^
"cd
§
CO
0)
M


cd M

CO •
4-* .**1
cd •
01 C
a

^o
f—j
01 n)
5 W
CJ VO

o
•^
CN


O
-cf
st
CM


0
in
ON


o
m
o\
i— j


o
5


o
t~»
^
iH






















s— \
*£
c
cd
o

^-N
iH
• •
-*

•
O
0

^
m
*>
iH
O
O
o
o
o
"^1
o
o
0
o
I-(
o
0
o
o
o
rH
o
o
m
rH
O
o
o
Q
o
rH
rH
T)
C
cd

4->
0)
cu
4-1
a
•H

•
CJ
vi
CO
4J
CO
O
CJ

cd
a
cd
cu
p.
O
•o
cu
4-1
cd
rH
O
rH















































/— \
^4
cd
cu
>,
"Zr
x
Q

^-^
a
•H
4J
cd

o
M
P.

0
o

in

-------
                                   107
      percent, respectively, of the nominal capacity.  As  a total sale
      of the produced heat  all  the year round cannot normally  be
      expected, there has only  been calculated the incomes driving
      from sales of 75 percent of the produced heat.
          The obtainable selling price  for  the heat—here rated to
      Dkr. 20,  -per million Real—will be  determined by  the  fact that
      it should be able  to  compete with the production price for a
      normal oil-fired plant,  i.e., among other things, it  will be
      dependent on the price  of oil.  When in competition with heat
      from  power stations,  the selling price  is  lower (Dkr.
      12,--15,--per million Kcal).*
          As shown on the tables,  the incineration capacity  (Line 1)
      and operational costs (Line  6)   are equally rated for  the
      different  calorific values.   This,  of  course,  is  an
      approximation, but  nevertheless close to the real  figures as far
      as the operational  costs are concerned, which will increase only
      little with  the  increase of the calorific value,  whereas the
      incineration  capacity  may vary with  the calorific value,
      depending on the refuse composition, so that the  capacity can
      normally be expected  to  increase  for lower calorific powers.
      This means that  the values for the operational  costs  per ton
      refuse incinerated can  be expected to be proportionately lower
      for the  refuse with the  lower calorific value  than for  the
      refuse with the high calorific value.
          As regards the  small plant, there has  been calculated with
      two-shift operation at  50 percent exploitation  and three-shift
      operation at 75 percent exploitation, and the plant  closed on
      Saturdays and Sundays.   For the larger plant,  calculations are
      based on continuous  operation all days of the year.
          It can be seen that the  operational  costs per burnt  ton of
      refuse are much cheaper for the large plant than for the  smaller
      one. The operational costs for the  small plant executed  as grate
      furnace  and with mechanical gas cleaning, and  for  the  large
      plant  executed as  grate/rotary kiln furnace with electrostatic
      precipitator, will  be almost equal per ton of plant  capacity.
      With uniformly rated  interest and depreciation conditions, the
* The selling price of  12-50 D.Kr./million Kcal is an old price used in
  1975-1976.  Prices today (1978) are 30-60 D.Kr./Gcal ($1.35-$2.70 per
million Btus).

-------
                          108

large  plant will  consequently also  have the  lower total
operational costs  per treated  ton of refuse.
    Accordingly, with  the large  plant,  a  more  effective and
secure  refuse treatment, a better gas  cleaning,  as well as a
cheaper treatment  price are  achieved."

-------
                                  109

                                FINANCE

         The financial  arrangements were straightforward.   The 5
municipalities put in money based on population.  The remainder was
borrowed at local banks.  The payoff period is variable as well as the
interest rate that has averaged about 8  percent.

-------
                                    110
                                REFERENCES
(1)     Amager-forbraending Interersentskab (Amager-refuse incinerator for
       the  public welfare).  A colorful public relations  description of the
       plant from all aspects.

(2)     I/S Amager-forbraending.  The 1975-1976  Annual Report  of  plant
       financial results.

(3)     Volund patents supplied by Volund. Dated from 1931  to  1975.

(4)     Maximum Rated Capacity (MRC) on Volund Rotary Kiln Furnaces by
       Gabriel Silva Pinto,  Project Manager. VIG (The  Volund Incinerator
       Group) News, pp 3-4.

(5)     Miscellaneous Collection Routing Data Processing Materials from P.
       Nielsen of Renholdnings Selskabet,  the  local not-for-profit
       collection society.

(6)     Data sheet about Volund,  3 pages.

(7)     Affaldsbehandling (Refuse Treatment-Volume Reduction by Different
       Treatment Methods), a  Volund publication.

(8)     Statistical Data  Sheet on the Amager Plant, 23 form pages with
       relevant data recorded.

(9)     Plants for Incineration of Refuse by Chief Engineer  (former), Cand.
       Polyt. E. Blach, A/S Volund.   An excellent 25-page technical  paper
       telling how Volund and its  competitors  build refractory,  water
       wall, and rotary kiln  furnaces for refuse  distraction and  energy
       production.
                                                             1828L
           >US SOWWWI.TWIITIWiOFf.Ce.19W -620-007/6311

-------