SOLID WASTE  AND FIBER RECOVERY  DEMON-
STRATION PLANT FOR THE  CITY OF  FRANKLIN,
OHIO:  AN INTERIM REPORT

N.  Thomas Neff

A.  M. Kinney, Incorporated
Cincinnati,  Ohio

1972
                    DISTRIBUTED BY:
                    KfiJl
                    National Technical Information Service
                    U. S. DEPARTMENT OF  COMMERCE
                    5285 Port Royal Road, Springfield Va. 22151

-------
  BIBLIOGRAPHIC DATA
  SHEET
 4. Title and Subtitle
1. Report No.
       EPA-SW-47D.I-72
                                                    2.
PB   213   646
 5. Report Date
  Solid Waste and Fiber Recovery Demonstration Plant  for the
  City of Franklin, Ohio; An Interim Report
                                                                              1972
                                               6.
 7. Author(s)
  N,  Thomas Neff
                                               8. Performing Organization Re pi
                                                 No.
 9. Performing Organization Name and Address
  A,  M.  Kinney, Inc.
  Consulting Engineers
  Cincinnati, Ohio  45219
                                               10. Project/Task/Work Unit N.
                                               11. XXKSiKac/Grant No.

                                                   G06-EC-00194
 12. Sponsoring Organization Name and Address

  U.S.  Environmental Protection Agency
  Office of Solid Waste Management Programs
  Washington, D.C.  20460
                                               13. Type of Report & Period
                                                 Covered
                                                        Interim
                                               14.
 lit. Supplementary Notes
 16. Abstracts
  The  Franklin, Ohio, resource  recovery demonstration project has elicited widespread
  interest, so this interim  report was prepared to:   (1)  present a preliminary analysis
  of the solid waste disposal and fiber recovery portions of the project; (2) provide
  preliminary data by which  others may be guided in evaluating emerging solid waste
  disposal and resource recovery technologies.  The historical development of this
  EPA-sponsored project and  a general description and evaluation of the process used
  are  included.  The preliminary plant economics presented are based on construction
  costs and the first six months of operation.  The plant began functioning in June
  1971 and is now in regular operation recovering ferrous metals and paper fibers
  which are sold to local industries.   The final report is scheduled for submittal to
  EPA  in February 1973.
 17. tCey Words and Document Analysis.  17a. Descriptors

  *Refuse  disposal, *Materials recovery,  Incinerators--refuse  disposal, Size reduction
  (comminution), Wet mills, Magnetic separators, *Reclamation—salvage, Sludge disposal
| I b Identifiers/Open-Ended Terms
(
 *Solid waste disposal, *Resource recovery,  Fluid bed incinerator,  Solid waste
 separation  technology, Liquid cyclone  separator, Paper fiber recovery system, Sewage
 sludge disposal, Franklin  (Ohio)
 17c. COSATI Field/Group
18. Availability Statement
Release to public *
t -l-
, IIL , 	
19. Security Class (This
Report)
UNCLASSIFIED
20. Security Class (This
Page
UNCLASSIFIED
21. No. of Pages
9(7
22. Price
*H
-------
                                                     EPA-SW-4'7D.I-72
        SOLID WASTE AND FIBER RECOVERY DEMONSTRATION  PLANT

                  FOR THE CITY OF  FRANKLIN, OHIO

                         An Interim Report
      This interim report (SW-4?d.i) on work performed under
Federal solid waste management demonstration grant no. G06-EC-00194
   to the City of Franklin} Ohio} was written by N. THOMAS NEFF
    A. M. Kinneyf Ino.3 Consulting Engineers3 Cincinnati, Ohio
          and isi reproduced as received from the grantee.
                                i •
                               -If-

               U.S. ENVIRONMENTAL PROTECTION AGENCY

                               1972

-------
ILLUSTRATIONS SIGNIFICANT TO TEXT MATERIAL


  HAVE  BEEN  REPRODUCED  USING A DIFFERENT
                            r
PRINTING TECHNIQUE AND MAY APPEAR  AGAIN IN


        THE BACK OF  THIS PUBLICATION

-------
This report has been reviewed by the U.S. Environmental
Protection Agency and approved for publication.  Approval
does not signify that the contents necessarily reflect
the views and policies of the U.S. Environmental Protection
Agency, nor does mention of commercial products constitute
endorsement or recommendation for use by the U.S. Government.
An environmental protection publication in the solid waste
management series (SW-47d.i).

-------
                              FOREWORD






     The Franklin, Ohio, project was funded in 1968 to demonstrate an




innovative solid waste disposal technique utilizing wet grinding and




subsequent incineration.  Later the scope of the project was expanded




to recycle portions of the solid waste stream.  The facility presently




includes the capability to separate ferrous metals and reuseable paper




fibers for recycling prior to disposing of the remaining solid wastes.




Further construction is now in progress which will also add to the




plant the capability to recover color-sorted glass and aluminum.  This




pilot plant now represents one of the first resource recovery facilities




in the country, and the project has become one of the most successful




projects ever funded by the solid waste demonstration program.




     This small system is a completely unique environmental control




complex which has been toured by visitors from many parts of the world.




The project's contributions to solid waste processing and resource




recovery technology have been immense.




     Due to the widespread interest in the project, this report has been




prepared as a preliminary effort to describe and evaluate the first seven




months of plant operation.  The U.S. Environmental Protection Agency project




managers who have followed the development of this project are:  R. Kent




Anderson, Dennis A. Huebner, Thomas C. Leslie, Ora E. Smith, and David G.




Arella.

-------
                                  CONTENTS
SECTION
    I
   II
  III
   IV
   VI
APPENDIX
                                                           PAGE
Preface 	  1
Abstract	  4
History and Development of Project	  7
Preliminary Operations Analysis 	 14
     A.  General Description of Process 	 14
     B.  Description and Evaluation of Process Streams 	 20
     C.  Operating Problems and Improvements Under Study ... 48
Preliminary Plant Economics 	 56
     A.  Construction Costs 	 56
     B.  Operating Costs 	 61
Summary and Conclusions 	 67
     A.  Summary	 67
     B.  Conclusions 	 68


Operating Cost Elements for a 150 Ton Per Day Plant 	 70
Operating Cost Elements for a 500 Ton Per Day Plant 	 77
        Preceding page blank
                                     vii

-------
ILLUSTRATIONS




Frontispiece




Figure 1.




Figure 2.




Figure 3.




Figure 4.




Figure 5.




Figure 6.




Figure 7.




Figure 8.




Figure 9.




Figure 10.




Figure 11.




Figure 12.




•figure 13.




Figure 14.




Figure 15.




Figure 16.




Figure 17.




Figure 18.




Figure 19.




Figure 20.
                                                            PAGE




Aerial View of Franklin Plant  	  iv




Environmental Control Complex Flow Diagram  	   9




Receiving Floor 	  13




Plant Layout 	  15




Hydrapulper 	  16




Magnetic Separator and Liquid Cyclone  	  18




Fluid Bed Reactor 	,	  21




Waste Load Variation	  24




Cyclone Rejects and Junk Remover Rejects  	  26




Cyclone Rejects Analysis	  28




Reuseable Paper Fiber Recovered 	 	  30




Paper Fiber Being Loaded for Shipment	  31




pH of Various Plant Waters	  33




Biochemical Oxygen Demand of Various Plant Waters  	  34




Total Suspended Solids in Various Plant Waters  	  35




Total Dissolved Solids in Various Plant Waters  	  36




Settleable Solids in Various Plant Waters  ..,	  37




Total Solids in Ash Slurry 	  38




Total Volatile Solids in Ash Slurry  	  39




Proximate Analysis of Reactor Feed 	  45




Rej ec ts to Landfill 	  49
                                      viii

-------
             SOLID WASTE AND FIBER RECOVERY DEMONSTRATION PLANT

                       FOR THE CITY OF FRANKLIN, OHIO

                              An Interim Report


                      This report was prepared for the
            City of Franklin, Ohio, under Grant No. G06-EC-00194


                             SECTION I - PREFACE


     This interim report was prepared in advance of the final demonstration

operations report because of the widespread interest that has been shown in

the Franklin, Ohio, solid waste and fiber recovery plant.  Cost data is

reported for the period of June 1 to Dec. 31, 1971, and the operational data

is for the period from May 17, 1971, to Feb. 29, 1972.

     This project has been supported by Grants No. 1-D01-UI-00194,

2-G06-EC-00194, and 3-G06-EC-00194-1S1 from the Environmental Protection

Agency, pursuant to the Solid Waste Disposal Act as amended.  The plant is now

in regular operation, and the testing and evaluation phase of the project is

in progress.  The final report is scheduled for submittal in February 1973.

     The plant demonstrates:  (1) the "Hydrasposal"* system developed by The

Black Clawson Company for the disposal of essentially unsorted municipal refuse,

in which metals and glass are separated for recycling; and (2) the "Fibreclaim"*
     *Copyrighted trademarks of The Black Clawson Company, Middletown, Ohio,

for systems for the disposal of solid wastes and for the recovery of paper

therefrom, covered by various U.S. patents.

-------
process for the recovery of recyclable paper fiber.   In addition,  raw sludge



from an adjoining sewage treatment plant will be mixed with the organic



residue from the Hydrasposal and Fibreclaim processes and burned in the fluid



bed reactor which is an integral part of the Hydrasposal system.



     The solid waste and fiber recovery plant is the first part of a total



environmental control project planned for the City of Franklin.  The sewage



treatment plant will receive and treat municipal and industrial waste water




from the Franklin region, thus replacing an obsolete municipal sewage plant



and thereby preventing the discharge of sewage pollutants into a part of the



Great Miami River.  This plant, being built by the Miami Conservancy District




with financial assistance from the Environmental Protection Agency, Office of



Hater Programs, is expected to be operational in July 1972.



     In addition to the solid waste plant, a glass recovery system is now



being designed which will take one of the reject streams from the Hydrasposal




system and extract recyclable aluminum and glass cullet.  The cullet will be



further sorted into brown, green, and clear colors.   This addition is sponsored



jointly by the Glass Container Manufacturers Institute and the Environmental



Protection Agency.



     Application has been made for Federal assistance to build an industrial



waste liquids disposal facility which would utilize the fluid bed reactor



portion of the Hydrasposal system to incinerate the collected and blended



wastes during time when the reactor is not being used to incinerate solid



waste.  This facility is expected to safely dispose of more than 10,000




gallons per day of oils and solvents, which are now being dumped on the land,

-------
into streams, or are being burned improperly.



     The intent of this report is to present a preliminary analysis of the




operation of the solid waste disposal and fiber recovery portions of the



Franklin Total Environmental Control Complex, and to provide preliminary data




by which others may be guided in evaluating emerging technology of solid waste




disposal and resource recovery.

-------
                           SECTION II - ABSTRACT


     Title;   System for total refuse disposal by fluid mechanical separation
             of solid wastes and fluid bed oxidation of combustibles, and
             reclamation of paper fibers.

     Grantee;  City of Franklin, Ohio
               35 East Fourth Street
               Franklin, Ohio  45005

     Project Director:  Bernard F. Eichholz,  City Manager

     Date Project Started;  Sep. 24, 1968

     DateProject Ends;  Feb. 28, 1973

     Objectives;  To design, construct, operate, and evaluate a demonstration

plant utilizing an innovative system for disposal of municipal solid waste and

the recovery of metals, glass, and paper fibers therefrom.   The system is

designed to receive virtually unsorted refuse and to separate it using a

fluid-mechanical process.  Reuseable paper fibers, metals,  and noncombustibles

are separated in the process, and the remaining combustible solids are mixed

with sewage sludge from an adjoining sewage treatment plant.  This residual

mixture is then burned in a fluid bed reactor.

     Procedures;  The project has been conducted in three phases—design,

construction, and operation.  The first two of these have been completed, and

initial operating data have been obtained.

     The initial two-thirds Federal grant, awarded Sep. 24, 1968, encompassed

the design of a facility to receive unsorted municipal refuse, to wet-grind it

into an aqueous slurry using a Hydrapulper, to hydrodynamically remove metals,

glass, and other noncombustibles, and to burn the organic solid residue, along

with raw sewage sludge, in a fluid bed reactor.  The City of Franklin retained

-------
A. M. Kinney, Inc., Consulting Engineers, Cincinnati, Ohio, to design the




plant, based on process design data supplied by The Black Clawson Company of




Middletown, Ohio.  The one-third matching funds for this phase were supplied




by the City from the sale of bonds.




     Before design was completed, an adjunctive process was developed by The




Black Clawson Company which would mechanically separate reclamable paper pulp




fibers from the aqueous slurry prior to its being mixed with the sewage sludge.




Further supplemental grant funds were received to add a method of magnetically




separating ferrous metals from the junk removed from the Hydrapulper.  The




one-third matching funds for the fiber reclamation portion of the plant were




reimbursed to the grantee by The Black Clawson Company.




     The second phase of the demonstration project was begun on July 24, 1970,




with the award of lump sum contracts for the construction of the solid waste




and fiber recovery plant; and for procurement of the process equipment.




Construction was essentially completed by May 17, 1971, when start-up personnel




reported to the jobsite.  The ensuing month was spent in testing, making




operating adjustments, and training personnel.  On June 14, 1971, the first




collection trucks were received, and on June 21,  1971, all municipal refuse




was routed to the new plant.  The plant has been operating on one shift per




day, five to five-and-a-half days per week since that date, processing 40 to




50 tons per day.  The plant is being operated for the City of Franklin under




a contract with Black Clawson Fibreclaim, Inc., a subsidiary of The Black




Clawson Company.  The total cost of engineering and construction to this




stage is $1,988,000.

-------
     The third phase of the project began with the initial operation of the



plant.  The City of Franklin authorized A. M.  Kinney,  Inc., to obtain physical



and fiscal data on the plant during the demonstration period and to prepare



the interim and final reports on the project.   The Federally-supported



demonstration period is for 15 months from initial operation (May 17, 1971, to



Aug. 17, 1972).  The final report on the project is required to be submitted




by Feb. 17, 1973.

-------
             SECTION III - HISTORY AND DEVELOPMENT OF PROJECT







     The Franklin project was begun in 1967, when the City realized its




landfill would be full in another 3 to 4 years.  Studies of new sites were




meeting the usual opposition from residents who did not want a landfill near




their properties.




     One of the members of the Franklin City Council was Mr. Joe Baxter, Jr.,




an engineer employed by the Shartle-Pandia Division of The Black Clawson




Company, Middletown, Ohio, manufacturers of paper mill machinery.  Mr. Baxter




conceived the idea of utilizing an array of this machinery to pulp solid waste,




automatically eject nonpulpable objects from the pulper, hydrodynamically




separate finely chopped noncombustibles, and burn the residual pulped




combustibles in a fluid bed reactor, in the same manner as sewage sludge is




burned.




     Entirely at The Black Clawson Company's expense, a pilot plant was built




in the Research and Development Laboratory of their plant at Middletown, to




prove the idea was feasible.   The Black Clawson Company retained the services




of A. M. Kinney, Inc., Consulting Engineers, to evaluate the process.   Pilot




plant tests showed that municipal solid waste could be pulped in a Hydrapulper,




that the noncombustible content of the refuse could be separated from the




organic residue, that mixing sewage sludge with the combustible remainder




increased the filterability of the sludge, and that the remainder going to




landfill constituted a 90 to  95 percent reduction in landfill volume




requirements.




     Since the Middletown pilot plant did not include a fluid bed reactor,

-------
other pilot operations were performed to determine the combustion




characteristics of the pulped organic residue.  Pilot plant tests were



performed in a Copeland reactor and a full scale test was made in the



Dorr-Oliver, Inc., sludge-burning reactor at the Ocean City, Maryland, sewage



treatment plant, both using organic rejects from the Middletown pilot plant.



     On the basis of the feasibility study, application was made, under the



Solid Haste Act of 1965, for a demonstration grant to design and build a full



scale plant in Franklin, Ohio, which would demonstrate this innovative method



at minimum cost, and at the same time would solve Franklin's solid waste



problem.




     Grant No. 1-D01-UI-0019H was received on Sep. 2<+, 1968, and the City



retained A. M. Kinney, Inc., to prepare a preliminary Design Manual to




establish design concepts and estimated construction costs.



     During this period, the Miami Conservancy District became responsible



for the water quality of the Great Miami River, and started planning a



regional sewage treatment plant for the Franklin area.  They acquired a tract:



of land adjacent to the southwest edge of the City, and offered a part of



this property to the City as the site for the solid waste plant.  The



inter-relationship of the two plants is shown in Figure 1.  Provisions were



made in the construction of the solid waste plant for the connections to the



sewage treatment plant which is now under construction.



     Also during this time, further development work was done by The Black



Clawson Company in the application of other paper mill-type equipment to the




separation of reuseable paper fiber from the aqueous slurry.  The pilot plant

-------
Figure 1.   Environmental control complex flow diagram.

-------
at Middletown was expanded to prove the feasibility of this process.   On the



basis of the pilot plant results, a supplementary grant application was made



and funds were awarded to include the Fibreclaim process in the Franklin



plant.




     The solid waste system Design Manual and the fiber recovery system Design



Manual, both prepared by A. M. Kinney, Inc., for the City of Franklin, formed




the bases for award of the construction grants No. 2-G06-EC-00194-02 and



3-G06-EC-0019f-lSl, which was made on Mar. 2, 1970.  Final design drawings



and specifications were then prepared, and lump sum bids solicited, in




accordance with the laws of the State of Ohio governing bidding for municipal



projects.



     While the solid waste and fiber recovery plant was being built,  the Glass




Container Manufacturers Institute announced that it had completed a series of




tests and trial operations using the glass-rich fraction separated from the



pulped refuse by the liquid cyclone in the Middletown pilot plant.  Using a



train of screening and classifying equipment to separate extraneous material,



the Glass Container Manufacturers Institute equipment train was capable of



recovering a stream of color-sorted cullet and an aluminum rich stream.  The



cullet was separated by the use of a Sortex optical sorter.



     The Glass Container Manufacturers Institute proposed that the City of



Franklin apply for a supplementary grant to add this equipment train to the



Franklin plant, on the condition that the Glass Container Manufacturers



Institute would reimburse the City for the matching funds.  Award of this




grant (No. 3-G06-EC-00194-03S2) was made by the Environmental Protection
                                    10

-------
Agency, Office of Solid Waste Management Programs on June 8, 1971.  Design of




this addition is now under way, and construction is expected to begin in the




summer of 1972, with completion scheduled before the end of the year.




     Construction of the solid waste plant was completed on May 17, 1971, and




the fiber recovery plant was completed on June 28, 1971.  The plant was




dedicated on Aug. 11, 1971, by Mr. Richard D. Vaughan, then Director of the




Office of Solid Waste Management Programs, Congressman Walter E. Powell of the




24th District of Ohio, and Mr. Bernard F. Eichholz, City Manager, City of




Franklin, Ohio.




     The Miami Conservancy District, in expanding its role from flood control




of the Great Miami River to that of total water management of that stream,




recognized that a major source of pollution was industrial waste liquids being




dumped in sewers, streams, and land draining to the river.  The District




commissioned a survey study of these pollutants and of possible alternative




disposal means for them.  The result of this study was a recommendation that a




regional disposal center be built at Franklin to take advantage of the




Hydrasposal system's integral fluid bed reactor.  The reactor at Franklin is




capable of incinerating many of the industrial liquid wastes, and is expected




to be used a maximum of two shifts per day, five-and-a-half days per week




through most of the 1980's.




     The City of Franklin retained A. M.  Kinney, Inc., to prepare




specifications for the design and construction of a receiving,  storage,  and




blending facility which would be added to the solid waste recyclinp-sewap.e




treatment complex.  Proposals were received by public bidding,  and a firm was
                                     11

-------
selected to build the industrial liquid disposal facility, conditional upon



receipt of Federal assistance.  Application for a Federal grant to build the



facility has been made by the City.




     Even in its present, unfinished state the Franklin Environmental Control



Complex has attracted inquiries and visitors from many parts of the world.



     Because it is a full scale commercial plant, operating in regular daily



service to the City and its environs, demonstrating a new approach to resource




recovery and solid waste disposal, visitors have come from nearly every state



of the Union, and from such foreign countries as Sweden, Australia, Italy,




Japan, and Great Britain to observe its operation.



     The future of the plant is not only a function of the completion of the




other parts of the complex, but is largely dependent upon the economic



viability of its operation.  The process lends itself to more innovation, so




that other recovery facilities may be added in the future to reduce its




operating costs.
                                     12

-------
               SECTION IV - PRELIMINARY OPERATIONS ANALYSIS






     A.  General Description of Process.  The flow of material through the




plant is shown schematically in Figure 1, and the physical arrangement of




equipment is shown in Figure 3.  As shown in these diagrams, refuse is




delivered to the plant by private contractors and individual citizens.  All




incoming refuse is weighed and recorded at the scale, except that from




passenger vehicles and small pickup trucks.  The vehicles dump their loads




onto the concrete receiving floor, from which the refuse is pushed onto the




feed conveyor by a front-end loader.




         The conveyor feeds the refuse into the Hydrapulper at a controlled




rate.  The Hydrapulper is a Black Clawson Model SW pulping machine, 12 feet




diameter, and equipped with a 300 horsepower motor.  Recycled water is mixed




with the refuse, and all pulpable and friable materials are converted into a




water slurry (with approximately 4 percent solids content) by the action of




a high speed cutting rotor in the bottom of the Hydrapulper tub.   Pieces of




metal, tin cans, and other nonpulpable and nonfriable materials are ejected




from the Hydrapulper through an opening in the side of the tub.  These




materials pass down a chute which connects the tub opening to a specially




designed bucket elevator known as the junk remover.  In this chute they




receive a preliminary washing by the water which is being recycled back into




the pulper.  The junk remover discharges the materials into a rotating drum




washer, where they are again washed with the recycled water.  They are then




conveyed under a magnetic separator where the cans and other ferrous  objects




are separated for recycling.   The nonferrous materials are collected  for

-------
                                                       w
                                                       .J
                                                                                         S
                                                                                               M
              «

              g
            « M
            hi (0
            >H O
            S 3
            Q (2


            M "* O
            < < co    o
                 CO S5 H
            O Q W O CO
            H W S M
            CO CO Ps H >J
            co co ac < M
            U W O H O
            B 05 CJ CO
                                                                                               ^
                                                                                         oa « w
                                                                                         M b p erf
                                                                                               fc H
                                                                r-i pg n
                                                                co «n co
    i  i  i

^r m vo t^
PO « co <*>
            J CJ < CO

            I   I   I   I
                                                                                                I  I
00 O\ O i-H  ro ^t *^* ^ *^
                                                            «-li-ti-li-lfHfM«MCM
-------
landfill burial.



         The slurry is extracted from the Hydrapulper through a perforated




plate located beneath the rotor in the bottom of the tub.  In addition to



paper fiber, the slurry contains almost all of the organic content of the



refuse, plus most of the glass, small pieces of metal, ceramics, and much of



the aluminum.  To remove the inorganics, the slurry is pumped to the liquid



cyclone, where the heavier materials are separated by centrifugal action.




         The heavier materials pass into a chamber in the bottom of the liquid



cyclone from which they are conveyed into hoppers for landfill disposal.  The




waste glass recovery demonstration plant, to be built later in 1972, will



interface with the solid waste plant at the discharge of the liquid cyclone




conveyor.



         After the metals and glass have been removed for recycling, the



slurry is pumped to the Fibreclaim process for extraction of paper fiber.  In



this process, the long paper-making fibers are mechanically separated from the



coarse organics, such as rubber, textiles, leather, yard waste, and high wet




strength paper, paper coatings and fillers, paper fines, and very small pieces



of glass, dirt, and sand.



         The coarse contaminants are removed in two stages of screening.  The



first stage is a Black Clawson VR Classifiner, in which the acceptable



material is passed through a screen having 1/8 inch diameter openings.  The



second stage screen is a Selectifier screen having 1/16 inch diameter openings.



         The fine glass and dirt is removed by pumping the Selectifier screen



accepts through a battery of centrifugal cleaners.  Separation of the organic
                                     17

-------
fines from the long fibers is accomplished by passing the slurry over an



inclined, slotted fine screen known as a Hydrasieve, manufactured by the Bauer



division of Combustion Engineering Company.  Long fibers are retained on the



screen, while the fines pass through the 0.020 inch slots.



         Finally, the reclaimed long fibers are dewatered in two stages.  The



first stage is a Black Clawson Hydraden£;er, which is an inclined screw




conveyor type thickener which removes most of the water.  Additional water is



removed by squeezing the partially dewatered pulp in a cone press manufactured



by the Rietz Manufacturing Company.  The pulp is delivered by screw conveyor



to a waiting truck or shipping container at HO to 50 percent moisture.




         When the Miami Conservancy District completes installation of its



area waste water treatment plant, the dewatered recovered fiber will be



rediluted with the sewage plant effluent water, and pumped directly to the




Logan-Long Company, who now buy the recovered pulp for use in making dry felt



for asphalt roofing.



         The unrecoverable organic rejects from the fiber recovery operations



are combined and pumped to a storage tank.  From the storage tank they are



returned to the Hydrasposal system.



         As the organic rejects are drawn from the storage tank at a desired



rate they are dewatered to 40 percent solids content in two stages.  An



inclined screw thickener (Hydradenser) discharges to a Rietz cone press.  The



press discharges to a screw conveyor which breaks the dewatered cake into




lumps 5/8 inch to 1-1/2 inches in size.  These are then fed through a rotary




star-feeder into a pneumatic conveyor system which delivers the material to




the fluid bed reactor.




                                     19

-------
         The fluid bed reactor is a 25 foot inside diameter vertical




cylindrical unit supplied by Dorr-Oliver, Inc.  In this unit,  room temperature



air is blown by a 500 horsepower Spencer blower into a windbox at approximately



H-l/2 psig.  The air flows upward through a perforated plate and gravel



dispersal layer into a layer of sand, which becomes fluidized by the air.



When starting up from a cold condition the fluidized bed is initially



preheated by oil burners.  After the fluidized sand reaches operating



temperature of 1300 F to 1500 F, the injection of the organic  rejects supplies



sufficient fuel to continue their combustion,  so that no auxiliary fuel is



required in normal operation.  For shutdown periods in excess  of 24 hours,



small quantities of fuel are used to maintain bed temperature,.



         The exhaust gases are cleaned of particulate matter in a venturi



scrubber, and are discharged through a gravity separator as a clean,




nonpolluting odorfree white plume.



         Sludge from the adjoining sewage treatment plant will be mixed with



the organic rejects between the Hydradenser and the cone press so that it will



be dewatered without the aid of flocculating agents in the press, and burned



in the fluid bed reactor.



     B.  Description and Evaluation of Process Streams.  The impact of the



Franklin plant on the environment can be measured only by comparison of the




inflows, which formerly were dumped or buried, with the outflows which are now



either recycled, passed on to downstream treatment facilities, or emitted into




the air.  The process flows within the Hydrasposal and Fibreclaim processes



are actually of little importance to this report.  This section of the report,
                                     20

-------
therefore, is confined to the environmental impact concept.




         1.  Solid Waste Receipts.  Between June 21, 1971, and Dec. 31, 1971,




a total of 6,299 tons of refuse were received at the plant.  Of this amount,




6,140 tons were processed through the system.




             Although no categories have been recorded, the plant operators




have estimated that 85 to 90 percent of the receipts are from residential




sources.




             The tonnage received and not processed consisted primarily of




large items which are not grindable by a Hydrapulper, such as vehicle tires,




refrigerators, water heaters, iron and wooden furniture, industrial pallets,




automotive parts, kitchen and laundry appliances, building demolition waste,




dead tree trunks, and lumber.




             Some items not originally considered as processable by a




Hydrapulper have proven to be, such as dead small animals, aluminum lawn




furniture, small appliances, television sets, and light drums.




             Incoming refuse from commercial haulers is received from packer




trucks, and open dump trucks.  Individuals and small haulers bring refuse in




pickup trucks, station wagons, rental trailers, and automobiles.  Obviously




processable loads are dumped on the receiving floor and pushed onto the feed




conveyor by means of a front-end loader.  One plant operator acts as




weighmaster, receiving clerk, cashier, and loader operator.  It is incumbent




upon this operator to scan the incoming loads and the material being pushed




onto the conveyor to extract unprocessable materials.  During early operations,




several instances occurred where ungrindable items were charged into the
                                     22

-------
Hydrapulper with resulting downtime while the object was removed, and, if



necessary, repairs were made to the Hydrapulper.  When these materials are



spotted, they are pulled out, set aside, and periodically sold as scrap to a



junk dealer.  Unsaleable items must be landfilled, but these amount to only



about 1-1/2 percent of the tonnage received.  A change in the baffle plate




has virtually eliminated Hydrapulper downtime resulting from damage by this




type of material.



             Figure 7 shows the variations in refuse received and processed




during this report period.



         2.  Junk Remover Rejects.  Of the tonnage processed, approximately




H percent is ejected by centrifugal action through the junk chute of the




Hydrapulper into the junk remover.



             The magnetizable, or ferrous, fraction averages 68 percent of the




junk remover rejects, or 7.2 percent of the total refuse received.  This



consists mostly of cans, but also contains bottle tops, spark plugs, nails,



bolts, and an infinite variety of unrecognizable pieces.  This material is



dumped into detachable truck bodies in which it is hauled several times a week



to a nearby steel company (Armco) which pays the equivalent price of No. 2



bundles (presently $13.30 per short ton) for it.



             No further recycling process is immediately contemplated for the



nonmagnetizable rejects.  These rejects average 1.45 tons per day, or 3.5



percent of the refuse tonnage received.  They are disposed of in the nearby




plant landfill.



             Typical analyses of the junk remover reject streams are as
                                     23

-------
Figure 7.  Waste load variation.

-------
follows:

             Sixty-eight percent of junk remover rejects are collected by th<;

magnetic separator.  Approximately 80 per\cenX of this fraction is all steel

cans and steel cans with aluminum tops.  The remaining 20 percent usually is

spark plugs, nuts, bolts, wire, and automobile and appliance parts.  Of the 32

percent not collected by the magnetic separator 6 to 16 percent is nonferrous

metal, 1/2 to 2 percent is ferrous metal missed by the separator, and 82 to 94

percent is miscellaneous objects such as rubber, heavy plastics, stones, and

large pieces of glass.

         3.  Liquid Cyclone Rejects.  Approximately 10.5 percent, by weight,

of the total refuse received is separated by the liquid cyclone.

           •  An average of analyses of the liquid cyclone rejects shows this

stream consists of:

             Description                          Percent (Dry Basis)

             Clear glass                                 38.4
             Green glass                                  4.9
             Amber glass                                 21.8             65.1

             Magnetic metals                              3.3
             Aluminum                                     2.3
             Other metals                                 0.8              6.4

             Large stones (greater than No. 4 mesh)                        4.6

             Loss on ignition                                              6.0

             Miscellaneous materials (plastics, rubber, etc.)             17.9

             Total                                                       100.0

             The waste glass plant now being designed will receive its input

from the liquid cyclone discharge conveyor.  At present, however, this
                                      25

-------
material, along with the nonferrous junk remover rejects and the unsaleable,




unprocessable material, is buried in the plant landfill.  The cyclone rejects




contain a higher percentage of adherent organic material than was anticipated.




The waste glass plant equipment train will include washing and screening




operations to remove this material before color sorting the glass, and will




return it to the main plant for burning.




             Figure 9 shows the trends in cyclone rejects analyses during the




report period.




         4.  Recovered Fiber.  Fiber recovery operation began during July 1971,




and continued through Aug. 28, 1971.  During this period 76.3 tons of fiber




(air dried basis) were produced, which was sold to the Logan-Long Company of




Franklin, Ohio, manufacturers of roofing products.




             On Aug. 28, 1971, fiber production for Logan-Long Company was




stopped because of operating problems on their paper machine.  Between Sep. 1




and Sep. 15, 1971, Logan-Long Company evaluated the performance of their




machine using no reclaimed fiber.  During this same period, The Black Clawson




Company and Logan-Long Company conducted laboratory investigations into the




cause of the problems.  The results of these investigations are discussed in




this report under the heading of "Operating Problems and Improvements Under




Study".




             Fiber recovery operations were resumed in September and Octouer




to produce fiber for a series of experimental papermaking tests being made by




the St. Regis Paper Company, and were again resumed in November for Logan-Long




Company after both they and The Black Clawson Company made process changes
                                      27

-------
Figure
9.  Cyclone rejects analysis.
                                 28

-------
which enabled Logan-Long to use the recycled fiber.




             The quality of recycled fiber, when processed in a paperboard




mill equipped to eliminate lipids and fines, is reported to be good.  No




analytical data on the experimental paper and board manufactured from the




recovered fiber has been reported, because it is not considered conclusive in




view of the production difficulties encountered.  The Logan-Long Company has




reported that the fiber is the equivalent of the corrugated board, old




newsprint, and mixed paper currently used by them in the production of roofing




felt.




             The commercial viability of the fiber recovery process depends




not only on the physical usefulness of the fiber, but also on the financial




return which would result from the additional capital required for this




adjunct to the Hydrasposal system.  Operating data indicates that the




oven-dried fiber yield at the Franklin plant was 5 to 7.6 percent of the




refuse tonnage as received compared to the 18 percent yield indicated by the




Middletown pilot plant operation and several experimental runs at Franklin.




Several modifications to the system are required to increase the yield.  On




The Black Clawson Company's recommendation, the City has included the funds




for yield and quality improvement modifications in a supplementary grant




application.




             The tonnage of fiber produced during the report period is shown




in Figure 10.




         5.  White Water Waste.  An estimated 50 gpm of waste water was




routinely discharged from the process water system through December 1971.
                                     29

-------
Figure 10.  Reuseable paper fiber recovered.

-------
Under design conditions, with sewage sludge dewatered and burned in the fluid

bed reactor, part of the total discharge will be the water which will convey

the sludge.  This will be done to prevent contamination of the plant process

water with untreated sewage water.

             White water is constantly withdrawn from the system to reduce the

level of total and dissolved solids in the process water.  This is replaced

with fresh water makeup.

             An average analysis of the waste water is as follows:

             pH                                   5.6
             Five day BOD                     3,148 mg/liter
             Suspended solids                 3,411 mg/liter
             Total dissolved solids           3,315 mg/liter
             Settleable solids                   83 ml/liter

             Temporarily, the waste water is piped to an aeration basin

installed by the Miami Conservancy District to serve until the sewage

treatment plant is completed.  The treated water is now discharged to ground

absorption.

             Figures 12, 13, 14, 15, and 16 show the physical and chemical

characteristics of the various plant waters.

         6.  Sewage Sludge.  Because the area waste water treatment plant

being built by the Miami Conservancy District has not been completed, no

sewage sludge has been burned to date in the process.

         7.  Ash Slurry.  Approximately 40 gpm of ash slurry is bled from the

scrubber-separator water recirculating system.  This quantity can be varied to

limit the amount of total solids in this system, but it is now run at a
                           *
constant rate because of failure of the flowmeter supplied with the scrubber.
                                     32

-------
Figure  12.  pH  of vai.'
-------
         Jit
           Mi
                                       14414411
                                       i'  11 >  m
                                                    1
    ifJ-L-

    Iff
            14
                         Iff ft
                                   w
                                            I
                                                 m
         -lit
         *
                                                                   I
                                                                   i-t
                                                       I
         trr
                                    1'  i J i'
                                    liU iii
                                    11'r t:'
                                          &
                                              •t
                                              ^T
      tfr*
                                                             1
                                     ap
                                     3f w
                                HH
                                                        I
                                                        F+H
                                                           ii
                                            m
                                         i
                                         IB
                                                 i
    ifr
                                                1
                                                      itk
   Jit
.4---II
                                                                     -t-
                                              HH
Figure 13.   Biochemical oxygen demand  of various  plant  waters.

-------
                          •|; (i.j-.,T/«Hi sonos osttsaasns TVIOJL i; -I. -
Figure m.   Total suspended  solids  in various plant waters
                                      35

-------
Figure 15.  Total dissolved solids in various plant waters.

-------
          Ujjii'j.

          SllL
         ft
          Si*
         4*i-:
                                                                nrHf
                                                          1*
                                                   -i.^Li i:,.!];:.
                                                   ipvfc.frtr
                                                   ^i^jfe
Figure 16.   her i ;•

-------
Figure 17.  Total solids in ash slurry,
                                 38

-------

   m
   n.
     I
     ffi
      «tei±
        ' T •;."
144:4- '
Figure 18.  Total
                     39

-------
             An average analysis of the ash slurry water is as follows:

             pH                                   8.5
             Total solids                     16,100 ing/liter
             Suspended solids                 13,400 mg/liter
             Dissolved solids                  2,700 mg/liter
             Settleable solids                    25 ml/liter
             Total volatile solids             1,500 mg/liter

             Figures 12, 14, 15, 16, 17, and 18 illustrate variations in the

chemical and physical properties of the ash slurry.

             Until the Miami Conservancy District sewage treatment plant is

completed, the ash slurry is being discharged to surface drainage.  When the

sewage treatment plant is operational, this slurry will be piped to the

industrial primary clarifier where it is expected to be used as a settling

agent.  (See Figure 1).

         8.  Stack Gases.  The products of combustion from the fluid bed

reactor are conveyed through a downflow venturi scrubber, then up through a

gravity separator column before being discharged to atmosphere.

             From Dec. 28, 1971, through Jan. 4, 1972, a field crew from

Environmental Sciences, Inc., of Pittsburgh, Pennsylvania, performed a series

of three tests covering simultaneous sampling of the emissions from the  fluid

bed reactor and the emissions, from the.scrubber serving the reactor.  The data

taken consisted of the collection and analysis of the particulate and gaseous

emissions in the stack gases»  Also during each test, samples of the inlet and

outlet scrubber water, and of organic rejects fed to the reactor were

collected, so that a complete material balance could be performed on the

entire system.

             The purpose of the testing program was to determine the air

-------
pollution emissions from the fluid bed reactor in order to certify to the City

of Franklin and to the State of Ohio the quantity and nature of the air

pollutants being emitted from the process.   Tests of the fluid bed reactor and

the venturi scrubber were also needed by A. M. Kinney, Inc., to prepare a

comprehensive evaluation of the treatment process.  The testing program

allowed for the determination of the emissions from the fluid bed reactor when

operating at normal operating capacity at steady state, as well as allowing

the determination of the collection efficiency of the venturi scrubber serving

the fluidized bed reactor.

             Based upon the results of the  three tests performed on the inlet

and outlet of the scrubber, the following average results were .reported by

Environmental Sciences, Inc.
             Scrubber dry solids removal efficiency
             Scrubber condensables removal efficiency
             Solid particulate loss on ignition (900 C)
                  Parameter

                  Grain loadings - grains per
                   standard dry cu ft (SDCF)  at
                   12 percent carbon dioxide

                  Grain loadings - grains per
                   SDCF - actual reading

                  Condensables - percent

                  Particulate flow - Ib/hr

                  Volumetric flow rate SDCF
                   per minute

                  Gas temperature - F

                  Water - percent
Inlet

     4.5



     2.542


     1.0

   358

16,500


  moo

     5.5
98.8 percent
23.5 percent
 3.3 percent

Outlet

  0.076
  0.043


 45.5

  6.11
190

 34.1

-------
                   Parameter                           Inlet        Outlet

                   Sulfur dioxide—parts per            45          less than 7
                    million (ppra)

                   Nitrogen oxides—ppm                143          125

                   Aldehydes                           none         none

                   Hydrocarbons                        none         none

                   Carbon monoxide                     trace        trace

                   Chlorides—Ib/hr                      4.7          0.43

              The data given above generally show that  the effluent from the

fluid bed reactor contains only a trace of combustible  material,  either as

gases or solids.  These results, coupled with an exit gas temperature of

1400 F, indicate that the reactor is efficient and operating well.   The

venturi scrubber and mist separator remove about 98 percent of the  dry and

condensable particulate.  Considering that the scrubber system operates at a

differential of only 7 inches of water, its performance is excellent.

              The analysis of the impinger water indicates undetectable amounts

of nitrates and fluorides, with most of the soluble, condensable  material

being in the form of sulfates and chlorides.  The impinger water  was very

acidic (pH—2.5).  The chemical analysis of the scrubber water indicated

large amounts of solid and dissolved particulate with high quantities of

sulfate and chlorides, and only minor contributions from other ions.  The

scrubber water was only slightly acidic (pH—6.0).

              The quality and quantity of the particulate and gases

theoretically emitted from the reactor and the measured quantities  of material

picked up by the scrubber water system did not balance  well with  the measured
                                      42

-------
concentrations of pollutants in the stack gas due to errors involved in:




(1) obtaining a representative sample of scrubber water; (2) estimating




scrubber water flows and refuse fuel consumption; (3) an accurate fuel




analysis; (H) not chemically analyzing the solid particulate collected during




the test, and (5) miscellaneous problems that could be isolated and solved




only by extensive research.




              These tests show that the emissions from the scrubber are below




the limit of 0.1 grain per standard dry cubic foot of gas flow (corrected to




12 percent carbon dioxide) set by the specifications, which were based on




Federal guideline specifications which were in effect at that time.




              However, regulations adopted by the State of Ohio, Air Pollution




Control Board, on Jan. 28, 1972, with an effective date of Feb. 15, 1972,




limit dust emissions from incinerators to 0.1 pounds of particulate per 100




pounds of combustible refuse charged, when operating at the manufacturer's




maximum rating.  At the time this report was written, it was uncertain whether




the Franklin reactor would meet this requirement, since the plant does not




function like a conventional incinerator.  The City's consulting engineers




have requested the State of Ohio to clarify whether the "combustible refuse




charged" should be measured at (1) the reactor inlet, excluding the




noncombustibles removed by the junk remover and liquid cyclone as at Franklin,




or (2) the plant receiving floor, as would be the case with a conventional




incinerator.




              It is planned by the plant operating contractor to have another




stack test made as an acceptance test of the Dorr-Oliver equipment.   These

-------
results will be included in the final report.

          9.  Organic Rejects.  Although it is not an external stream, the fuel

feed to the fluid bed reactor also is being monitored during the evaluation

period in order to gather operating data on this key part of the Hydrasposal

system.  The physical characteristics of the reactor sand bed and the ash from

the reactor fuel are also analyzed at regular intervals.

              Typical analyses of the organic rejects are as follows:

              Ultimate Analysis                        Percent

                 Moisture                               54.36
                 Carbon                                 22.90
                 Hydrogen                                2.84
                 Oxygen                                 15.18
                 Nitrogen                                0.02
                 Sulfur                                  0.07
                 Ash                                     4.63

              Proximate Analysis                       Percent

                 Moisture                               54.36
                 Volatile                               36.03
                 Ash                                     4.63
                 Fixed carbon                            4.98

                 Heating value (oven dry basis) 8,345 Btu per pound

              Figure 19 illustrates the variations in proximate analyses of the

reactor fuel.

         10.  Auxiliary Fuel.  No. 2 commercial fuel oil is  used to preheat the

bed sand in the fluid bed reactor in order to bring it up to minimum operating

temperature.  When the bed reaches this temperature, feeding the dewatered

organic rejects is begun, and, under normal operation all of the rejects burn

autogenously.  Under unusual or upset conditions, it has been necessary to
                                      44

-------
Figure 19.   Proximate .,-" ^.,,/si;:  of reactor feed.
                                   45

-------
fire supplementary fuel through oil guns located within the static bed level

to maintain minimum bed temperature.  During the period of this report a total

of 22,120 gallons of fuel oil were used, including approximately 4,600 gallons

used during a period when organic rejects were drawn off intermittently for

test purposes, thus interrupting continuous feed to the reactor.

        11.  City Water.  At the present time, city water is used as the sole

source of makeup water to the system.   When the sewage treatment plant is

completed, its effluent will be recycled for use as process water.  Process

usage of some city water may continue, as for example in the venturi scrubber

sprays and as seal water.

              Actual quantities of city water used are not recorded, because

the plant operators removed the city water meter in an attempt to solve a

problem of low water pressure at the scrubber sprays, and replaced it after

the report period.  The average water usage is calculated as follows:

              Waste water to pond (measured)           50 gpm
              Ash water to surface (measured)          40 gpm
              Water evaporated by scrubber
                (from stack analysis)                   50 gpm

              Total                                   140 gpm

              Average consumption of water per ton of refuse processed is

calculated as follows:

              Hydrapulper operating time                            783.3 hours
              Reactor and scrubber operating time                   866.8 hours
              Tons of refuse processed                            6,140
              Hydrapulper usage:
                783.3 hours at 50 gpm x 60 minutes
                  per hour                                    2,349,900 gallons
              Reactor usage:
                866.8 hours at 90 gpm x 50 minutes
                  per hour                                    4,680,700 gallons
                                                              7,030,600 gallons


                                      46

-------
               The 7,030,000 gallons consumed, divided by the 6,140 tons




processed, equals 1,145 gallons per ton of refuse.




          12.  Electric Power.  Electric power service to the plant is supplied




by The Cincinnati Gas & Electric Company, through a single 1,500 kilovolt-arnper-s




(kva) transformer and a meter serving both the Hydrosposal and Fibreclaiin




systems.  A separate temporary connection is installed to serve the floating




aerator in the temporary waste water treatment basin.  When the sewage




treatment plant is completed, it will be served by its own transformer and




meter.




               Power consumption for the report period was a total of 935,600




kilowatt-hours (kwh).  No measurement of the division between Hydrasposal and




Fibreclaim systems is available.




               The unit consumption of electric power during report period is




computed as follows:




               935,600 kwh consumed, divided by the 6,140 tons processed,




equals 153 kwh per ton of refuse.  Because this quantity includes the start-up




period it is to be considered as order-of-magnitude only.  Recent data has




indicated consumption of approximately 180 kwh per ton.




          13.  Rejects to Landfill.  The three streams which go to landfill are




summarized as follows:




               a.  Unprocessable Refuse Received.   Consists of large or heavy




ungrindable or unfriable items.  This fraction averages approximately 0.66




tons per day or 1-1/2 percent (by weight) of refuse received.




               b.  Nonferrous Junk Remover Rejects.  Consists of smaller

-------
ungrindable or unfriable materials.   This  fraction averages  approximately




1.45 tons per day, or 3.5 percent (by weight)  of the refuse  received.




               c.  Liquid Cyclone Rejects.  Consists of inorganic rejects,




3/4 in. and smaller, which have passed through the extractor plate of  the




Hydrapulper.  This stream contains 5 to 15 percent putrescible organics.




                   All of the cyclone rejects, which now go  to landfill,




average approximately 10.5 percent (by weight) of the refuse received.




                   In the latter part of 1972, this stream will be diverted to




the waste glass recovery system, where the glass and aluminum between  1/8 in.




and 3/4 in. will be recovered for recycling.  The remaining  undersize  and




oversize material, stones, plastics, and metals will continue to go to




landfill, but the putrescible organic will be  returned to the Hydrasposal




system for incineration in its fluid bed reactor.




               The total of reject streams going to landfill during the report




period average 15.5 percent of the tonnage received.  No total measurement




of volume to landfill was made, but  it is  estimated at less  than 5 percent




of the total volume received at this plant, or 8.3 percent of the volume




required for conventional landfill operation.




               Figure 20 shows the variations  in quantities  and constituents




of the material taken to the plant landfill.  Quantities are reported  by  the




plant operators on an oven-dried basis, in order to eliminate valuations  in




actual tonnage due to varying moisture contents.




      C.  Operating Problems and Improvements  Under Study.  While, the  physical




data in this report are concerned primarily with quantitative and qualitative

-------
Figure 20.  Rejects   ••

-------
analysis of external process streams, the overall effectiveness  of the




Franklin demonstration plant is dependent on its internal operation.




         The problems which have affected overall plant operation, and the




improvements which are being considered, are thus an integral part of this




analysis.




         1.  Refuse Receiving.  For economy reasons, the refuse  receiving area




was designed as an open-ended, high-walled shed.  The basis for  computation of




receiving floor space was that the entire area,  except for walking aisle space,




would be used for receipts.  This has proved impractical for operation of the




front-end loader.  As a result, when a number of trucks arrive in a short time




span, it is necessary to accumulate the: refuse on the ramp leading to the




receiving floor until the peak is worked off.  Although this has been




unsightly, and operation of the front-end loader outside during  inclement




weather is inconvenient, the plant operators feel no remedial action is




economically justifiable.




              Another operating problem was one of maggots in the apron




conveyor pit and sump, on the receiving floor, and on the operating floor.




This problem was worst during the warm weather,  but it has been  controlled by




use of insecticides.



              A continuing problem is the tire wear on the front-end loader.




The operating conditions for this machine result in the need for replacement




of the tires approximately every 6 months despite switching to solid heavy-duLy




industrial tires.




              To compensate for maintenance downtime on the front-end loader,
                                      50

-------
the plant service truck was purchased with a snowplow blade, which permits




its use in pushing refuse onto the conveyor.




          2.  Hydrasposal System.




              a.  Hydrapulper.




                  (1) It was found in initial operation that the apron conveyor




caused large quantities of dust and dirt to fall out onto equipment and




personnel below it, and that the Hydrapulper was splashing dirty water over




the floor and visitors.  Therefore, a fiber glass cover has been fitted over




the Hydrapulper and conveyor.  The cover is equipped with access doors and a




monorail for access to the pulper.  Rapid access is needed in order to remove




ungrindable materials and to work on the rotor.




                  (2) A high maintenance item is replacement of the swing




hammers on the rotor of the Hydrapulper.  At the present time, life is about




300 operating hours, or about 1,800 tons.  Hammer replacement time is




approximately one hour.  Development work continues to improve the




effectiveness and service life of the hammers.




                  (3) Retrieval of unprocessable material that inadvertently




entered the Hydrapulper, and repair of damage caused by it, caused some minor




service interruptions during early operating periods.  Changes in baffle




clearance have apparently corrected the problem.  Outages of this type have




ranged from 1/2 hour to 2 days.




                  (4) Excessive vibration of the Hydrapulper occurred during




the initial operation period.  Addition of heavy crossbracing to pulper




supporting structure has largely eliminated this problem.
                                      51

-------
             b.  Hydradensers.  The lack of consistent performance by the




solid waste plant Hydradensers (dewatering screws)  has been the  subject of




continuing developmental work.  The erratic water removal characteristics and




the need for frequent adjustment has had an adverse effect on experimental




work on the burning of organic rejects,  and on the  plant maintenance costs.




Recent design changes have corrected this situation.




             c.  Fluid Bed Reactor.




                 (1) Two problems which  have occurred during this  report




period are related to the sand bed of the reactor.




                     A gradual attrition of the sand in the fluid  bed, caused




by the mechanical agitation of the sand, has caused fine particles of silica




to be carried over into the scrubber-separator.  The result has  been a




buildup of silicon-rich scale in the separator.  This was manifested as




stones which caused some damage to the scrubber water pump before  the




operators began to inject a dispersion agent into the system. This chemical




tends to keep the scale soft and in suspension in the scrubber water.




                     The other problem related to the fluid bed  is the gradual




agglomeration of the sand and its retention of mineral ash and glass particles.




From sieve analyses and increases in fluidizing air blower horsepower




requirements it became evident that the size of the bed sand particles was




increasing.  In February 1972, it was necessary to replace the entire sand bed,




when large masses of agglomerated sand accumulated.  The operating contractor




has instituted a program of periodic replacement of a portion of the sand




bed, and has reduced the maximum operating temperature limit.
                                     52

-------
                 (2) The rotary feed valve which passes the pulped organic




rejects into the pneumatic feeder supply to the fluid bed reactor has




repeatedly plugged and constantly limited the firing rate.  This feeder was




replaced with one of a different design to overcome this problem.




             d.  Miscellaneous.  A number of relatively minor additions and




corrections were made during the start-up period, or are planned, to improve




the operation of the Hydrasposal process.  Among these have been modifications




to the junk remover to eliminate excessive water carryover, relocating access




doors in the junk remover, instrument and control modifications, improvements




to platforms at the fluid bed reactor, and improvement of forklift tractor




access doors.  In addition, it is planned to replace the present 1,500 kva




transformer with a 2,000 kva transformer in order to provide electrical power




capacity for the waste glass recovery plant and for changes in the fiber




recovery process.




             e.  Plant Design Limitations.  The requirement of minimal first




cost placed limitations on the design of the Franklin plant which have




resulted in several operating problems which cannot be economically corrected,




but which should be considered in the design of future plants.




                 In addition to the previously mentioned space problem in the




receiving area, limited space in the Hydrasposal area has resulted in a




crowded equipment arrangement, making access to some areas for maintenance and




housekeeping difficult.




                 An operating problem which is somewhat annoying is an




excessive amount of process water spillage on the operating floor in the
                                     53

-------
Hydrasposal area.  While the amount of water on the floor would possibly not




be considered excessive by contemporary paper mill standards,  it is excessive




from a housekeeping and sanitary standpoint.  Consideration should be given,




in future designs, to improving drainage in this area.




                 Another problem for which there is no  simple  solution at the




Franklin plant is the high noise level around the Hydrapulper.  Future plants




may overcome this problem, but the Franklin plant layout precludes construction




of sound-attenuating walls.  The operator's station at  Franklin is in the




control room where the sound level is below the 80 dbA  continuous occupancy




limits of the Occupational Safety and Health Act.  Occupancy of areas having




sound levels higher than 80 dbA is abnormal and for a relatively short time.




         3.  Fibreclaim System.




             a.  Fiber Quality.  As stated heretofore,  fiber recovery




production for the Logan-Long Company was stopped on Aug. 28,  1971, because of




problems experienced in using the Franklin recycled fiber on their paper




machine.  The Black Clawson Company later reported that tests  made by




Logan-Long Company with their paper machine, and tests  made by The Black




Clawson Company in their laboratory indicated the cause of the problem was the




concentration of lipids and fines which occurred when the white water system




was closed up, i.e., when a higher percentage of the total white water flow




was recirculated.  This caused an increased amount of lipids and fines to




adhere to the fiber.




                 In the papermaking operation, as at Logan-Long Company,




water is removed from the newly formed sheet by pressing it out through a

-------
series of wringers, called press rolls.  The sheet of paper is supported at




the press rolls by a very porous woolen blanket, which also serves as a medium




by which the pressed out water may be removed, i.e., the water leaves through




the pores in the blanket.  The excessive fines and lipids apparently filled up




these pores, resulting in very reduced life of the blankets.




                 The condition was corrected temporarily by employing an




excessive amount of fresh water in the fiber recovery operation, with




equivalent increased bleed-off from the system to reduce the equilibrium level




of fines and lipids in the white water, and by installation of a high pressure




shower to clean the blanket on the Logan-Long Company paper machine.




                 For a permanent correction, a supplemental grant request has




been made to install a flotation clarifier in the white water recycling system.




             b.  Fiber Yield.  Primarily due to problems associated with




scaling up from pilot plant operation to full scale commercial operation, the




yield of recovered fiber has been substantially below expectations.




                 The screening system, which selectively sorts out the




recyclable long fibers, was sized according to secondary fiber paper mill




standards.  The screens were found to be inadequate due to the much higher




quantities of plastics, leather, rubber, etc., present in the slurry.  As a




result, the fiber recovery department can operate at only about one-half the




capacity of the balance of the plant, and much fiber is lost as a result.




Several experimental runs were made at reduced overall capacity., and the




anticipated yield (20% plus, air-dried basis) was realized.




                 A supplemental request has been made to install additional




screening capacity.






                                      55

-------
                  SECTION V - PRELIMINARY PLANT ECONOMICS






     A.  Construction Costs.  The following cost data are based on the latest




contract value for the process equipment and the final contract value for the




construction contracts for the Franklin plant.   The final value given for the




mechanical contract includes $3,230 for installing additional nozzles and




temporary scaffolding to make the stack gas analysis.  The process equipment




contract is being kept open to permit process changes.




         The general construction work, including site development, grading,




foundations, structural and miscellaneous steel, building work, paving,




painting, and landscaping, was done by the Monarch Construction Company of




Cincinnati, Ohio.




         The mechanical construction, including installation of all




Owner-furnished process equipment, contractor-furnished mechanical equipment,




piping, ductwork, instrumentation heating, ventilating, and plumbing was done




by Hughes-Bechtol, Inc., of Dayton, Ohio.




         Electrical construction work, including furnishing and installing




temporary construction power and all lighting,  electrical conduit, wire,




fixtures and equipment, grounding system, electrical controls, and




instrumentation was done by The Gustav Hirsch Organization, Inc., of Columbus,




Ohio.




         Sprinkler construction work including furnishing and installing all




materials for the sprinkler system in the receiving area, was done by the




Cincinnati Sprinkler Company of Cincinnati, Ohio.




         Process equipment includes the Hydrapulper liquid cyclone, tanks,
                                     56

-------
pumps, fluid bed reactor, venturi scrubber and gravity separator, screens,




process instruments, and controls.  This was supplied by the Shartle-Pandia




Division of The Black Clawson Company of Middletown, Ohio, who also supplied




the process design information, including flow rates, pressures, consistencies,




and equipment dimensions and weights.




         The sound system for the project included furnishing of equipment




for an industrial page-party phone and speaker system.  This was done by




J. W. Thompson Company of Middletown, Ohio.  Installation was under the




electrical contract.




         Construction costs are shown in the General Cost Summary on the




following pages.
                                     57

-------
                            CITY OF FRANKLIN,  OHIO

                     SOLID WASTE AND FIBER RECOVERY PLANT

                                 COST ANALYSIS

                             GENERAL COST SUMMARY
Item
    City
Unreimbursed
                                                   Solid Waste Plant
Federal Share   City Share
               Total
Process equipment
$ 2,500.00     $  506,761.06   $ 253,380.55   $  760,141.61
Construction
 General construction
 Mechanical construction $   779.00
 Electrical construction
 Fire protection
 Sound system                 —
    Sub-total            1
    779.00
Miscellaneous equipment
Present construction and
 equipment contracts     $ 3,279.00

Engineering (as of
 Dec. 31, 1971)               —
Total
$ 3,279.00
$ 152,260.34
179,075.33
66,765.15
2,900.00
445.11
$ 76,130.16
89,537.67
33,382.57
1,450.00
222.55
$ 228,390.50
268,613.00
100,147.72
4,350.00
667.66
!?  401,445.93

    24,771.23
$ 200,722.95

   12,385.59
$  602,168.88

    37,156.82
               $  932,978.22   $ 466,489.09   $1,399,467.31
                   81,994.12
                   40,997.06
                  122,991.18
$1,014,972.34   $ 507,486.15   $1,522,458.49
                                       58

-------
	Fiber Recovery Plant	             Sewage Plant
Federal        Black Clawson                    Miami Conservancy  Combined
 Share             Share        Total            District Share    Totals
$ 126,962.67   $   63,481.33    $ 190,444.00    $    —            $  953,085.61


$  48,346.67   $   24,173.33    $  72,520.00    $  3,465.50        $  304,376.00
   65,317.99       32,659.01       97,977.00       6,973.00           374,342.00
   31,082.58       15,541.28       46,623.86         —               146,771.58
                                                                        4,350.00
      —        	—              —             —            	667.66
$ 144,747.24   ~§   72,373.62    $ 217,120.86    $ 10,438.50        $  830,507.24

    1,663.20   	831.60        2,494.80         —                39,651.62


$ 273,373.11   $  136,686.55    $ 410,059.66    $ 10,438.50        $1,823,244.47
                   41,138.55       41,138.55         —               164,129.73
$ 273,373.11   $  177,825.10    $ 451,198.21    $ 10,438.50        $1,987,374.20
                                      59

-------
         The construction cost figures shown in the following table are

estimated for a 150 ton per day plant similar to the Franklin plant but built

today without Federal assistance.  They are based on The Black Clawson Company

estimates that a complete, installed plant identical to the Franklin plant

would cost about $3,000,000.  This estimate includes building, foundations,

process equipment, reactor, auxiliary equipment, instruments, controls, and

engineering for complete functional Hydrasposal and Fibreclaim plant, but does

not include cost of land, nor does it include cost of any standby equipment.


                       PROJECTED CONSTRUCTION COSTS
150 Ton per day plant
estimated at today's costs
Hydrasposal
Fibreclaim    Total
Process equipment
Construction
General construction
Mechanical construction
Electrical construction
Sub -total
Miscellaneous equipment
Total construction and
equipment
Engineering
Total
$ 1,140

$ 340
400
150
$ 890
55

$ 2,085
165
$ 2,250
,000

,000
,000
,000
,000
,000

,000
,000
,000
$

$


$


$

$
360

120
160
70
350
5

715
35
750
,000

,000
,000
,000
,000
,000

,000
,000
,000
$

$


$


$

$
1,500

460
560
220
1,240
60

2,800
200
3,000
,000

,000
,000
,000
,000
,000

,000
,000
,000
                                     60

-------
     B.  Operating Costs.  The operating costs shown in the following table




are projected for a. hypothetical 150 ton per day plant constructed without the




2/3 Federal funding received by the Franklin plant and operating with the




efficiencies and yields predicted by The Black Clawson Company to be achieved




at Franklin by August 1973.  By that time, the plant will have been operating




for one full year burning sewage sludge and recovering design quantities of




paper fiber.




         The projected costs for a hypothetical 500 ton per day plant have




been made by A. M. Kinney, Inc., on the basis of previous studies, amended to




reflect projected Franklin unit costs.




         It was assumed such a plant would operate 24 hours per day, 7 days




per week, 52 weeks per year.  A detailed explanation of the elements of this




projection is given in Appendix A of this report.




         The rate schedule charged for solid waste receipts as of Feb. 16,




1972, is as follows:




              Loads received from trucks              $6.00 per ton




              Loads received from pickup trucks       $2.25 each




              Loads received from automobiles         $0.75 each




              Large appliances                        $2.50 each




              Tires                                   $0.25 each
                                     61

-------
OPERATING COSTS
Load Rate
50 tons /day
13,000 tons/yr
per year per ton
Hydrasposal
Operating labor
Total maintenance
Fuel oil
Power — electrical
Office supplies
Telephone, etc.
Equipment rental
Plant security
Insurance
Debt service
Operating supplies
Water cost
Gross operating cost
Credit sludge
Credit metal
Net operating cost
Fibreclaim
Operating labor
Total maintenance
Power — electrical
Telephone, etc.
Plant security
Insurance
Makeup water cost
Waste water disposal
Debt service
Operating supplies
Gross operating cost

$ 44,600
46,900
3,100
HO, 100
100
360
2,400
480
6,900
175,500
5,200
730
$326,370
- 10,000
- 12,100
$304,270

$ 17,100
8,060
14,600
180
240
2,100
410
4,450
58,500
700
$106,340

$ 3.43
3.60
0.24
3.08
0.01
0.03
0.18
0.04
0.53
13.50
0.40
0.06
$25.10
- 0.77
- 0.93
$23.40

$ 1.32
0.62
1.12
0.01
0.02
0.16
0.03
0.34
4.50
0.05
$ 8.17
Load Rate
100 tons /day
26,000 tons/yr
per year per ton

$ 89,200
84,400
3,100
57,800
100
360
4,800
480
6,900
175,500
7,800
1,460
$431,900
- 20,000
- 24,200
$387,700

$ 34,200
14,570
21,700
180
240
2,100
820
8,900
58,500
1,050
$142,260

$ 3.43
3.24
0.12
2.22
--
0.01
0.18
0.02
0.27
6.75
0.30
0.06
$16.60
- 0.77
- 0.93
$14.90

$ 1.32
0.56
0.83
0.01
0.01
0.08
0.03
0.34
2.25
0.04
$ 5.47
       62

-------
Load Rate
150 tons /day
39,000
per year
$133,800
126,600
3,100
75,000
100
360
7,200
HBO
6,900
175,500
10,400
2,190
$541,630
- 30,000
- 36,300
$475,330
$ 51,300
21,850
28,600
180
240
2,100
1,230
13,350
58,500
1,400
$178,750
tons/yr
per ton
$ 3.43
3.24
0.08
1.92
--
0.01
0.18
0.01
0.18
4.50
0.27
0.06
$13.88
- 0.77
- 0.93
$12.18
$ 1.32
0.56
0.73
—
0.01
0.05
0.03
0.34
1.50
0.04
$ 4.58
Load
500
Rate
tons /day
182,500 tons/yr
per year per ton
$ 290,000
298,000
5,000
313,000
500
1,080
70,000
960
15,300
398,000
16,000
11,000
$1,418,840
- 100,000
- 169,200
$1,149,640
$ 140,000
100,000
110,000
540
480
8,100
5,500
35,000
211,000
2,300
$ 612,920
$ 1.59
1.63
0.03
1.72
--
0.01
0.38
—
0.08
2.18
0.10
0.06
$ 7.78
- 0.55
- 0.93
$ 6.30
$ 0.77
0.55
0.60
--
--
0.04
0.03
0.19
1.15
0.01
$ 3.34
63

-------
OPERATING COSTS
Load Rate
50 tons /day
13,000 tons/yr
per year per ton
Fibreclaim gross operating
cost (see previous sheet)
Based on 15% fiber yield
Credit fiber sales
Net operating cost
fiber recovery
Net operating cost
Hydras posal
Combined Hydrasposal and
Fibreclaim net operating
cost
Tons of fiber produced
Based on 20% fiber yield
Credit fiber sales
Net operating cost
fiber recovery
Net operating cost
Hydrasposal
Combined Hydrasposal and
Fibreclaim net operating
cost
Tons of fiber produced

$

$

$

$


$


$

$

$


$


106,340

- 48,700

57,640

304,270


361,910
1,950

- 65,000

41,340

304,270


345,610
2,600

$

$

$

$


$


$

$

$


$


8.17

-3.75

4.42

23.40


27.82
—

-5.00

3.17

23.40


26.57
__
Load Rate
100 tons /day
26,000 tons/yr
per year per ton

$

$

$

$


$


$

$

$


$


142,260

- 97,400

44,860

387,700


432,560
3,900

-130,000

12,260

387,700


399,960
5,200

$

$

$

$


$


$

$

$


$


5.47

-3.75

1.72

14.90


16.62
—

-5.00

0.47

14.90


15.37
__
       64

-------
        Load Rate




        150 tons/day
      39,000 tons/yr




per year          per ton
                           Load Rate




                           500 tons/day
                         182,500 tons/yr




                    per  year        per ton
$  178.750
$  1.58
$  612,920
$  3.34
$ -116,100




$   32,650




$  171,330






$  506,980





     5,850
$ -3.75




$  0.83




$ 12.18






$ 13.01
$ -685,000




$ - 72,080




$1,119,610







$1,077,560





    27,100
$ -3.76




$ -0.12





$__6_-JL°






$  5.88
$ -195,000




$ - 16,250




$  171,330







$  158,080





     7,800
$ -5.00




$ -0.12




$ 12.18







$ 11.76
$ -911,000
$ -5.00
$ -301,080      $ -1.66




$1,119,610      $  6.30
$  818,560
                        36,500
$  1.61
                                       65

-------
         The cost data for the 500 ton per day  plant  in  the  foregoing

tabulation assumes public ownership of the plant.   If the  plant  were privately

owned the annual operating costs would be  increased as follows:

                                             Hydrasposal           Fibreclaim

         Additional cost of money            $  398,000           $211,000
         Taxes, etc. (1 percent capital)           39,000            30,000
         Total                               $  437,000           $241,000

         With 15 percent fiber yield

         Net operating cost                  $1,512,110           $163,775

         Net cost per ton                    $	8.29	$	0.90

         Combined operating cost per ton                   $9.19

         With 20 percent fiber yield

         Net operating cost                  $1,512,110           $ -65,225

         Net cost per ton                    $	8.2J	$ -	0.36

         Combined operating cost per ton                   $7.93
                                     66

-------
                   SECTION VI - SUMMARY AND CONCLUSIONS






     A.  Summary.  The Franklin, Ohio, Solid Waste and Fiber Recovery Plant,




in its first seven months of operation has successfully demonstrated its basic




premises.  On a commercial scale, essentially unsorted municipal refuse can be




successfully wet-ground in a Hydrapulper; relatively small ungrindable items




such as tin cans can be removed from the Hydrapulper slurry and separated into




ferrous and nonferrous fractions; the quantity of noncombustibles remaining in




the slurry can further be reduced by inertial separation in a liquid cyclone;




recyclable paper fiber can be successfully removed from the slurry by the




Fibreclaim process; and the nonrecoverable organic residue can be burned in a




fluid bed reactor.




         While these objectives have been obtained, and technical feasibility




established in the first seven months of operation, the corollary objectives




of determining the economic viability of the Hydrasposal and Fibreclaim




processes have not been clearly obtained.  The data on actual operating costs




during this initial period reflect not only the developmental nature of the




process, but also unforeseen start-up and training expenses, both of which




are fundamental to emerging technology.  It is to be expected that the results




of the second eight months of operation will be more conclusive than the first




seven.  When the necessary process changes are authorized, as requested, a




second year of operational evaluation could further improve the quality of




analytical results.  Whether the target costs projected by the plant operators




for August 1973 are achieved depends on many unknowns, and it is felt that the




final report will reflect some modification as experience eliminates these
                                     67

-------
unknowns.




     B.  Conclusions.




         1.  The technical successes achieved in operating this plant have




warranted the Federal support received so far, in advancing the technology




of resource recovery methods.  They have also more than warranted the




enlightened action of the City Council and City Manager in pursuing the




project.




         2.  Continued Federal support in funding process and plant




modifications is warranted because the amounts requested represent a small




fraction of the total cost of the plant, and the results which they would




obtain would not only increase the cost effectiveness of the operation, but




provide significant technological advancement of an already innovative process,




By extending the demonstration support period, the opportunity to obtain




analytical data is increased.




         3.  The impact on the environment of the Franklin plant is already




favorable, and the planned expansion of the plant will make it even more




noteworthy.




         4.  The predicted economic viability of the Franklin plant is still




under study, and will not be accurately known until approximately mid-1973.




         5.  On the basis of data obtained at Franklin, the economics of a




500 ton per day, or larger, plant are indicated to be attractive, compared to




an incinerator for which adequate air pollution controls are provided.
                                      68

-------
APPENDIX
    69

-------
         Each shift works basic 40 hours per week.  Labor figures include

50 percent markup for fringe benefits and administrative burden.

     6.  Sludge credit is based on sludge load increasing in a straight line

ratio to refuse load.

     7.  Fibreclaim power costs include clarification of recirculating

Whitewater by air flotation, and aeration of waste water to reduce B.O.D. to

acceptable levels before discharging to existing sanitary sewers.

     8.  Waste water disposal costs include sewerage charges based on

approximate rates in effect in southwestern Ohio for "normal" sewage.

     9.  Capital investment is amortized over 25 year period at 6 percent

interest rate.

     Calculations for 50 tons per day load rate are given as follows.  Similar

calculations were used to obtain costs for other load rates.

     Fifty tons per day (t/d) can be processed in one 8-hour shift.

         (50 x 2,000 x .55)/480 = 114.5 Ib/min oven dried solids to

         reactor (capacity: 132 Ib/min).

     1.  Operating labor—Hydrasposal

         Assume:  one control operator
                  one weighmaster
                  one material handler
                  two-thirds plant manager

         Plant manager:   2/3 x $12,000          = $ 8,000
         3 men at $3.48 per hour average        =  21,750
                                                  $29,750

         Fringe benefits and administrative burden = 50  percent

             1.5 x $29,750 = $44,600 per year
                                    71

-------
         Operating labor - Fibreclaiin

         One operator: $3.48 x 2,080            = $ 7,400
         One-third plant manager                =   4,000
                                                  $11,400

             1.5 x $11,400 = $17,100 per year

     2.  Maintenance.  The Black Clawson Company has projected a cost of

$3.60 per ton for Hydrasposal at Franklin.  Similarly the maintenance cost

for Fibreclaim was projected at $0.62 per ton at Franklin.

         Hydrasposal—13,000 x $3.60            = $46,900

         Fibreclaim—13,000 x $0.62             = $ 8,060

     3.  Fuel Oil Costs.  In the most recent 8-week period Franklin burned

3,395 gallons of No. 2 fuel oil to reheat reactor, or about 424 gallons per

week.  Reactor is reheated once each week after being off on week-end.

         424 x 52 = 22,000 gallons per year

         22,000 gallons x $0.14 per gallon = $3,085 per year

     4.  Power—Electrical.  Unit consumption of electrical power at

Franklin for first 28 weeks of operation is:

         935,600 kwh/6,140 tons = 153 kwh per ton of refuse

         If fiber recovery had been in full operation during that period, the

unit consumption would have been 180 kwh per ton of refuse according to the

plant operators.  Additions planned for fiber recovery will increase this

figure to 204 kwh per ton.

         The maximum demand experienced at Franklin is 1,152 kw.
                                     72

-------
         Demand charge—per month:

              20 kw @ $2.00       = $   40.00
              80 kw @ $1.90       =    152.00
             900 kw @ $1.45       =  1,330.00
             152 kw @ $1.35       =    205.00
                                    $1,727.00   Demand

         Energy charge:

             204 x 13,000 tons = 2,650,000 kwh per year

             2,650,000/12 = 221,000 kwh per month

         Per current Cincinnati Gas £ Electric rate schedule:

             1,000 kwh @ 2.5$                   = $   25.00
             5,000 kwh @ 1.45$                  =     72.50
             60 x 1,152 = 69,120 kwh @ 1.0$     =    691.20
             120 x 1,152 = 138,240  kwh @ 0.8$   =  1,109.00
             7,640 kwh @ 0.575$                 =     44.00
                                                  $1,941.70 per month

         Fuel adjustment: 221,000 kwh x .003545   $  784.00

         Demand charge                            $1,727.00

         Total electrical cost                    $4,452.70 per month

         Total annual power cost:

             $4,452.70 x 12 = $53,500

         The Black Clawson Company  suggests split 25 percent Fibreclaim,

75 percent Hydrasposal.

             $53,500 x 0.75 = $40,100   Hydrasposal

             $53,500 x 0.25 = $13,400   Fibreclaim

         See also water treatment  cost calculation.

     5.   Office Supplies.  Same as  at Franklin—say $100 per year.

     6.   Telephone.   Same as at Franklin.
             Hydrasposal—$360 per  year
             Fibreclaim--$180 per year
                                     73

-------
     7.  Equipment Rental.  Detachable truck bodies to handle ferrous metal.

Same as at Franklin—$2,400 per year.

     8.  Plant Security.  Same as at Franklin.
             Hydrasposal—$480 per year
             Fibreclaim—$240 per year

     9.  Insurance.  Franklin cost totals $6,135 for $2,000,000 investment,

or 0.3 percent.

         See construction cost estimate:

             Hydrasposal:  $2,250,000  x 0.003 = $6,750
                                            Use $6,900

             Fibreclaim:   $  750,000  x 0.003 = $2,250
                                            Use $2,100

    10.  Debt Service.  Assume money amortized at 6 percent for 25 years.

Capital recovery factor = 0.078.

             $2,250,000 x 0.078 = $175,500  Hydrasposal

             $  750,000 x 0.078 = $ 58,500  Fibreclaim

    11.  Operating Supplies.  Assume same cost per ton as at Franklin ($0.40

for Hydrasposal, $0.05 for Fibreclaim).

             $13,000 x 0.40 = $5,200    Hydrasposal

             $13,000 x 0.05 = $  650    say $700 for Fibreclaim

         It is assumed that this cost  would increase by 50 percent with each

50 ton per day load increase.

    12.  Hater Cost.  Water useage at  Franklin for 10,000 ton per year load

rate is estimated to be 90 gpm for Hydrasposal system and 50 gpm for

Fibreclaim.

-------
         Using the clarified effluent from the sewage treatment plant as

makeup process water, the cost is $0.05 per 1,000 gallons.

         Water cost for 50 ton per day load rate:

             Hydrasposal—(1.3 x 90 x 60 x 8 x 260 x .05)/1,000 = $730

             Fibreclaim— (1.3 x 50 x 60 x 8 x 260 x ,05)/1,000 = $406 say $410

    13.  Credit for Sludge Burning.  Assume sludge load equal to Franklin.

             400 tons per year (oven dried solids) @ $25 per ton = $10,000 per
             year

    14.  Credit for Metal Sales.  Recoverable metal equals about 7 percent of

refuse processed.  No. 2 bundles price about $13.27 per ton.

             .07 x 13,000 = 910 tons

             910 x $13.27 = $12,090  say $12,100

    15.  Water Treatment Costs.  At Franklin it is not required to reduce the

B.O.D. in the waste water before discharging to sewage treatment plant.

Therefore, this cost is not included in 204 kwh per ton power requirement.  In

most localities it will be necessary to reduce B.O.D. to approximately 300

parts per million (ppm).

             65 gpm @ 3,200 ppm B.O.D.

             (65 [3,200 - 300] x 60 x 8.3)/l,000,000 = 93.9 Ib B.O.D/hr

             1 horsepower hour per 2 Ib B.O.D.

             93.9/2 = 47 horsepower requirement

             47 x 0.746 = 35 kw

             35 x $1.40              = $ 49.00 demand per month
             35 x 8 x 260/12 x .0085 =   51.40 energy per month (including
             fuel adjustment)
                                       $100,40 x 12 = $1,200 per year
                                     75

-------
     Add to power costs for Fibreclaim:




         $13,400 + $1,200 = $14,600




16.  Waste Water Disposal.




         Estimated water to sewer =65 gpm




         Approximate sewerage charges—"Normal"




         Sewage—secondary treatment plant =  $0.55 per 1,000  gallons




         (65 x 60 x 8 x 260 x 0.55)/1,000 = $4,450 per year




17.  Credit—Fiber Sales.




     For 15 percent fiber yield:




         Fiber recovered = .15 x 13,000 = 1,950  tons  per year (air dry)




         1,950 tons @ $25 per ton = $48,700




     For 20 percent fiber yield:




         Fiber recovered = .20 x 13,000 = 2,600  tons  per year (air dry)




         2,600 tons at $25 per ton = $65,000  per year
                                 76

-------
             OPERATING COST ELEMENTS FOR A 500 TON PER DAY PLANT






     In computing the cost projections for an hypothetical 500 tons per day




plant, the following assumptions were made:




     1.  Total actual maintenance costs for Hydrasposal system at Franklin




equals about 14 percent per year of total electrical and mechanical capital




costs.  Minimum predicted costs are approximately 5 percent.  Therefore,




maintenance costs for the larger system have been projected at 10 percent of




estimated mechanical process equipment and electrical costs, and 5 percent of




reactor costs as a median rather than flat cost per ton.  Similarly,




Fibreclaim costs are projected at 5 percent of electrical and mechanical




costs.




     2.  Power costs were calculated on kw per ton of capacity demand charges




and kwh per ton of refuse processed energy charge using Cincinnati Gas &




Electric rate schedule.  One-fourth of total charged to Fibreclaim.




     3.  Plant is assumed to run continuously 24 hours per day, seven days




per week, 52 weeks per year.




     4.  Water costs are based on low cost water source such as at Franklin.




     5.  Operating labor includes the following personnel divided into four




shifts, each working a basic 42 hour week:




         one plant manager




         four shift supervisors




         four crane operators




         four weighmasters




         ten laborers - operator trainees




         thirteen Fibreclaim operators






                                     77

-------
         Labor figures include 50 percent markup for fringe benefits and

administrative burden.

     6.  Sludge credit is based on assumption that 500 tons per day plant

would have approximately ten times the sewage load.

     7.  Fibreclaim power costs include clarification of recirculating white

water by air flotation and aeration of waste water to reduce B.O.D. to

acceptable levels before discharging to existing sanitary sewers.

     8.  Waste water disposal costs include sewer charges based on approximate

rates in effect in southwestern Ohio for "normal" sewage.

     9.  Capital investment amortized over 25 year period at 6 percent

interest rate.

     Calculations for a 500 ton per day plant are given as follows:

     1.  Operating Labor—Hydrasposal

         Assume:  one plant manager            $ 12,000
                  four shift supervisors         40,000
                  four crane operators           36,000
                  four weighmasters              36,000
                  ten laborers                   69,500
                                               $193,500

         Assume fringe benefits and administrative burden at 50 percent.

             $193,500 x 1.5 = $290,000

         Operating labor--Fibreclaim

             3 men per shift = 12 men

             Plus 1 man extra on day shift = 13 men

             13 X $7,200 x 1.5 = $140,000
                                     78

-------
     2.  Maintenance—Hydrasposal.

         Installed capital costs:

             Process equipment:             $1,580,000
             Electrical:                       100,000
                                            $1,980,000

             Reactors:                      $2,000,000

             Process equipment and
              electrical maintenance
              estimated at 10 per cent, or  $  198,000

             Reactor maintenance
              estimated at 5 percent, or    $  100,000

                                            $  298,000 per year

         Maintenance—Fibreclaim

         Total mechanical and electrical costs estimated at $2,000,000

             .05 x 2,000,000 = $100,000

     3.  Fuel Oil.  Reactors assumed to be running continuously.  No fuel

requirement for preheating.

         Allow:  $4,000    building heating
                  1,000    reheat and support fuel
                 $5,000

     4.  Power—Electrical.

         Total energy used at Franklin first 6 months = 935,600 kwh

         Refuse processed:  6,140 tons

             935,600/6,140 =153 kwh per ton

         If fiber recovery had been operating full time The Black Clawson

Company estimates this number would be 180 kwh per ton.

         With additional screening capacity and clarifier added to fiber

recovery, energy required per ton expected to be 204 kwh per ton.
                                     79

-------
         The maximum demand experienced at  Franklin is  1,152 kw.

             500 tons per day demand =  1,152 x 500/150  =  3,840  kw

             500 tons per day energy =  204  x 182,500/12 = 3,100,000 kwh per month

         Demand charge—3,840 kw:

                20 kw @ $2.00     = $   40.00
                80 kw @ $1.90     =    152.00
               900 kw @ $1.45     =  1,330.00
             2,840 kw @ $1.35     =  3,835.00

             Total demand           $5,357.00 per month

         Energy charge—3,100,000  kwh:

             1,000 kwh @ 2.5*                     = $    25.00
             5,000 kwh @ 1.45*                    =      72.50
             60 x 3,840 s 230,500  kwh @ 1.0$      =   2,300.00
             120 x 3,840 = 461,000 kwh  @ 0.8*     =   3,690.00
             461,000 kwh @ 0.575$                  =   2,640.00
             1,942,000 kwh @ 0.5$                  =   9,710.00

             Total energy                           $18,437.50

         Fuel and tax adjustment = 3,100,000 x $0.003545  = $11,000.00

             $5,357 plus $18,437 plus $11,000 = $34,794 per month—total

             $34,794 x 12 = $417,000 per year—total

         The Black Clawson Company suggests split 25 percent Fibreclaim and

75 percent Hydrasposal.

             $417,000/4 = $104,000~Fibreclaim

                          $313,000—Hydrasposal

         See also water treatment  cost  calculation.

     5.  Office Supplies.  Say $500 per year.
                                     80

-------
     6.  Telephone.  Franklin—$360 per year—Hydrasposal
                               $180 per year—Fibreclaim

         Say 3 x $360 = $1,080 per year—Hydrasposal

         Say 3 x $180 = $540 per year—Fibreclaim

     7.  Equipment Rental or Disposal of Rejects to Landfill.

         Rejects = 20 percent of refuse received

             .2 x 182,500 a 365,000 tons per year at $2.00 per ton = $73,000

             Say $70,000

     8.  Plant Security.  Two times Franklin actual cost.

         $960 per year—Hydrasposal

         $U80 per year—Fibreclaim

     9.  Insurance.  Insurance costs at Franklin are approximately 0.3 percent

of capital costs.

             .003 x 5,no,000 = $15,300 for Hydrasposal

             .003 x 2,700,000 = $ 8,100 for Fibreclaim

    10.  Debt Service.

         Total cost Hydrasposal system, less reactor      $3,110,000

         Reactors                                          2,000,000

         Total investment                                 $5,110,000

         Assume amortization at 6 percent for 25 years

         Capital recovery factor = 0.078

             $5,110,000 x 0.078 = $398,000

         Total investment Fibreclaim =  $2,700,000

             $2,700,000 x 0.078 = $211,000
                                     81

-------
    11.  Operating Supplies.

         500/150 x $5,200 = $16,690  Say $16,000     Hydrasposal

         500/150 x $700 = $2,340     Say $2,300      Fibreclaim

    12.  Hater Cost.  See calculation for 150 tons per day plant.

         Hater cost—Hydrasposal = $0.06 per ton

             0.06 x $182,500 = $10,920  Say $11,000

         Hater cost—Fibreclaim  = $0.03 per ton

             0.03 x $182,500 = $5,460  Say $5,500

    13.  Sludge Credit.  Assumed 500 ton per day refuse load would mean

area sludge load equals 10 times 50 ton per day refuse load area.

         10 x $10,000 = $100,000

    14.  Ferrous Metal.  Recoverable ferrous metal equals about 7 percent of

refuse processed.

         0.07 x 182,500 = 12,750 tons

         12,750 tons at $13.27 per ton = $169,200

    15.  Hater Treatment Costs.  See calculation for 50 ton per day load.

         Previous studies by A. M. Kinney, Inc., indicate 130 gpm of waste

water must be discharged from 500 ton per day plant.

         130 x 60 x 8.3 x (3200 - 300)/1,000,000 = 188 Ib B.O.D. per hour
         @ 2 Ib B.O.D. per horsepower hour = 94 horsepower requirement

         94 x 0.746 = 70 kw

         70 kw x 1.40 = $98.00 demand charge

         70 x 24 x 365/12 = 51,100 kwh

         51,100 kwh @ $0.005      = $255
         51,100 kwh @ $0.003545   = $181     fuel adjustment

         $98 plus $255 plus $181 = $534 per month x 12 = $6,400 per year

                                     82

-------
         Add to power cost previously calculated

             $104,000 plus $6,400 = $110,400   Say $110,000

    16.  Waste Water Disposal.

         Estimated water flow to sewers per month:

             130 gpm x 1,440 x 30 = 5,620,000 gallons

         Based on Cincinnati, Ohio, current rate schedule:

             Minimum                                             $   90.00
             3,750,000 gallons @ $0.27 per 1,000 gallons            900.00
             1,870,000 gallons @ $0.19 per 1,000 gallons            355.00
                                                                 $1,345.00
             Average $0.24 per 1,000 gallons

         These rates are based on primary treatment only.  Secondary

treatment will be required in future at approximately double this cost.

             5,620,000 x 2 x $0.24/1,000 = $2,690 per month

             $2,690 x 12 = $32,350   say $35,000

    17.  Credit—Fiber Sales.

         For 15 percent fiber yield:

             Fiber produced = .15 x 182,500 = 27,400 air dried tons

             27,400 tons @ $25 per ton = $685,000 per year

         For 20 percent yield:

             Fiber produced = .20 x 182,500 = 36,500 air dried tons

             36,500 tons @ $25 per ton = $914,000 per year
                                                               U0766
                                     83

-------
Frontispiece - Aerial View of Franklin Plant
                       IV

-------
Figure ^.   Receiving floor.
                                 13

-------
Figure U.  Hydrapulper.

-------
 Fig. 5a —Magnetic Separator
Fig.5b— Liquid  Cyclone
Figure 5.  Magnetic separator and liquid cyclone

-------
Figure 6.  Fluid bed reactor.
                                 21

-------
Figure 8.   Cyclone rejects and junk remover rejects,

-------
Figure 11.  Paper fiber being loaded for shipment.

-------