905D76107S
UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
                      REGION 5
                      230 S DEARBORN ST
                      CHICAGO. ILLINOIS 60604
JULY 1976
ENVIRONMENTAL
IMPACT STATEMENT
                                     DRAFT
TUNNEL COMPONENT OF THE TUNNEL
AND RESERVOIR PLAN PROPOSED BY THE
METROPOLITAN SANITARY DISTRICT
OF GREATER CHICAGO
CALUMET TUNNEL SYSTEM
SUMMARY REPORT

-------

-------
                SUMMARY REPORT

                    OF THE

    DRAFT  ENVIRONMENTAL  IMPACT STATEMENT


            TUNNEL COMPONENT OF THE

           TUNNEL AND RESERVOIR PLAN

                PROPOSED  BY THE

       METROPOLITAN SANITARY DISTRICT

              OF GREATER  CHICAGO
                Prepared By  The

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                   REGION  V

               CHICAGO, ILLINOIS

                      And

       BOOZ,  ALLEN AND HAMILTON, INC.

              BETHESDA, MARYLAND



                                 APPROVED BY:
                                 GEORGE R. ALEXANDER, JR.
                                 REGIONAL ADMINISTRATOR
                                 JULY 1976
U.S.  Environmental Protection Agency
Region 5, Library (5PL-16)
2SO S. Dearborn St-eet, Room 1670
Chicago, IL  60604

-------
              ABLE   OF   CONTENTS
                    Executive Summary
                                                      Page
                                                     Number
  I. BACKGROUND INFORMATION                            -iii-

     1.1  Legal Basis for the EIS                       -iv-
     1.2  Scope of the EIS                              -iv-
     1.3  Identification of the Applicant               -iv-
     1.4  Project History                                -v-
     1.5  Objectives of TARP                           -vii-
 II. EXISTING ENVIRONMENTAL SETTING                   -viii-

     2.1  Natural Environment                         -viii-

          2.1.1  Water Resources                      -viii-
          2.1.2  Land Resources                         -xi-
          2.1.3  Atmospheric Resources                 -xii-
          2.1.4  Biological Resources                  -xii-

     2.2  Man-made Environment                        -xiii-

          2.2.1  Socioeconomic                        -xiii-
          2.2.2  Land Use                              -xiv-
          2.2.3  Sensitive Areas                        -xv-
          2.2.4  Financial Resources                    -xv-
          2.2.5  Labor Resources                       -xvi-
          2.2.6  Transportation                        -xvi-
          2.2.7  Major Projects and Programs           -xvi-


III. THE PROPOSED ACTION                              -xvii-

     3.1  Alternative Plans                           -xvii-
     3.2  Plan Selection                             -xviii-
     3.3  TARP Tunnel Systems                          -xix-
     3.4  TARP Subsystems                              -xix-
     3.5  Calumet Tunnel Segments and Branches        -xxii-
     3.6  Cost of Tunnel System and Subsystems        -xxii-
     3.7  TARP Financing                              -xxiv-
 IV.  PRINCIPAL FINDINGS CONCERNING THE EFFECTS OF
     THE PROPOSED ACTION                              -xxix-
  V.  CONCLUSIONS AND RECOMMENDATIONS                 -xxxix-

                           -ii-

-------
                 I.  BACKGROUND  INFORMATION
     This chapter first defines the  legal basis  and the scope
of the EIS and then describes .the  authority  and  program of the
applicant for EPA funding, the MSDGC.  Finally,  the history
and objectives of the Tunnel and Reservoir Plan  (TARP)  are
reviewed.  This chapter of the executive summary corresponds
to Chapter I of the-.environmental  impact statement (EIS).
1.1  LEGAL BASIS FOR THE EIS

     The U.S. Environmental Protection Agency  (EPA)  is  the
administering agency for a major Federal  environmental  pro-
gram entitled "Grants for Construction of Treatment  Works."1
This program allows the EPA Administrator to provide finan-
cial aid to any state, municipality,  intermunicipal  agency,
or interstate agency for the construction of publicly owned
water pollution control facilities.   The  program will en-
courage reduction of point sources of water pollution and
improve national water quality.

     The EPA's granting of funds for  a water pollution  con-
trol facility may require an EIS.  Each proposed water  pollu-
tion control facility is evaluated on a case-by-case basis
by the appropriate EPA regional office to determine  whether
the proposed facility is expected to  have significant en-
vironmental effects or be highly controversial.  The EPA has
prepared this EIS because it expects  the  environmental  ef-
fects of the tunnel system to be significant.

     This EIS is being issued pursuant to PL 91-90,  the
National Environmental Policy Act  (NEPA)  of 1969,  and Exe-
cutive Order 11514, "Protection and Enhancement  of Environ-
mental Quality" dated March 5, 1970.  Both NEPA  and  Execu-
tive Order 11514 require that all Federal agencies prepare
such statements in connection with their  proposals for  major
Federal actions significantly affecting the quality  of  the
human environment.
     Authorized by Title II, Section 201(g)(1), of the Federal Water
     Pollution Control Act Amendments of 1972, Public Law 92-500 (FWPCAA)
                             -111-

-------
     This EIS has been prepared in accordance with the
regulations and guidance set forth in the President's Council
on Environmental Quality (CEQ)  Guidelines dated August 1, 1973,
and the EPA's Final Regulations 40 CFR-Part 6, dated April 14,
1975.
1.2  SCOPE OF THE EIS

     The EIS addresses the cumulative effects of constructing
and operating three conveyance tunnel systems which are part
of the total Tunnel and Reservoir Plan (TARP) proposed by
MSDGC.  These three tunnel systems are:

          Mainstream (59th Street to Addison Street)
          Calumet
          Lower Des Plaines.

Where appropriate, this statement also assesses the effects
associated specifically with the Calumet Tunnel system route.
Two other statements address separately the  effects associated
with  the Mainstream Tunnel  system and  the Lower Des Plaines
Tunnel system.  The Mainstream statement has already been
developed and issued, whereas the Lower Des  Plaines statement
is currently in the development stage.  These tunnel systems
comprise what is referred to in the  statement as "TARP, Phase I."

      The subject of these statements is confined to the tun-
nel systems  and their associated  components  because EPA is  now
considering  whether to grant funds  to  construct these  tunnels
under its water pollution control authority.  Other compo-
nents of TARP, including the reservoirs, flood relief  tun-
nels, instream aeration, and wastewater treatment  plant im-
provements,  are either ineligible for  EPA funding  or are not
now under consideration for construction grants.   Therefore,
these other  components are  not considered to be part of the
proposed action under review.  The  effects of these other
components on water quality and the  likelihood of  their being
financed is  analyzed in this EIS  in  order to provide a con-
text  for evaluating the significance of the  water  quality
improvements expected from  the three tunnel  systems.


1.3   IDENTIFICATION OF THE  APPLICANT

      The Metropolitan Sanitary District of Greater Chicago
(MSDGC)  is the construction grant applicant  for the compo-
nent  of Tunnel and Reservoir Plan (TARP) addressed by this
EIS.  The MSDGC was organized in  1889  under  an act to create
sanitary districts to remove obstructions in the Des Plaines
                           -iv-

-------
and Illinois Rivers.1  Under the provisions of  the  act,  the
MSDGC is responsible for providing surface water  and  sewage
drainage within the District's boundaries, which  it does by
constructing necessary facilities, conveyance systems, and
treatment plants.  The MSDGC is authorized to treat waste-
water, either totally or partially,  from any municipality
within its designated jurisdiction,  as well as  to own and
operate all wastewater facilities located within  the  MSDGC
jurisdiction.

     The MSDGC service area is approximately 860  square miles.
Approximately 44 percent of this area, or 375 square  miles,
is served by MSDGC-owned combined-sewer systems  (see  Figure  1-1)
in which wastewater or sewage collected in local  sewer systems
is conveyed to treatment plants.  These systems serve 120
municipalities which have a total population of approximately
5.5 million.  The District owns and  operates 70.5 miles of
navigable canals, 6 wastewater treatment plants,  and  approxi-
mately 440 miles of intercepting sewers.  The three major
plants (North-Side, West-Southwest,  and Calumet)  in the MSDGC
service area have a secondary capacity of over  1,750  million
gallons per day (MGD).  The remaining plants have a combined
tertiary capacity of over 16 MGD.  A water reclamation plant,
the John F. Egan plant, is presently under construction and
will have a capacity of about 30 MGD.


 1.4   PROJECT HISTORY

      The MSDGC  initiated  its wastewater facilities  planning
 study in September 1967,  with  a  ten-year  clean-up and flood
 control program.   The  objectives  of  the program are to  solve
 the District's  flooding problem,  protect  Lake  Michigan  from
 further pollution,  and improve  the water  quality of rivers
 and streams  in  the Chicago  metropolitan area.   The  Tunnel
 and Reservoir Plan (TARP) has  evolved from  this ten-year
 program.

      Concerned  officials  from  the  State of  Illinois,  Cook
 County, the  MSDGC,  and the  city  of Chicago  reactivated  a
 Flood Control Coordinating  Committee (FCCC)  in. November 1970
 to investigate  the pollution and flooding problems  in the
 Chicago metropolitan  area.  The  Committee's  primary assign-
 ment  was to  develop a  viable plan  to minimize  the area's
      Illinois Revised Statutes, Chapter 42, Section 320, approved
      May 29, 1889.
                            - v -

-------
                                    FIGURE 1-1
                        Metropolitan Sanitary  District
                              of Greater Chicago
                                 Service Area
SERVICE AREA OF MSDGC
COMBINED-SEWER
SERVICE AREA
BOUNDARY
                     -VI-

-------
pollutant discharges and the flooding caused by overflows
of mixed sewage and wastewater.  Another priority item in
the plan was elimination of the need to release polluted
river and canal flood waters into Lake Michigan.  The Com-
mittee's plan was to address the combined-sewer area within
Cook County, covering 375 square miles.  The deliberations
and studies of the FCCC and of a technical advisory commit-
tee which they formed resulted in the selection of TARP as
less costly and more environmentally acceptable than the
other plans they evaluated.  The Committee then initiated
additional studies to develop and refine TARP.


!-5  OBJECTIVES OF TARP

     A primary objective of TARP is to improve surface water
quality within-the planning area.  TARP is designed to meet
the standards set forth in the "Water Pollution Regulations
of Illinois."1  These regulatory standards were established
for three surface water-use classifications:  (1)  General
(primary body contact), (2) Public and Food Processing
(drinking water), and (3)  Secondary Body Contact and Indigenous
Aquatic Life.  All surface waters in the State of Illinois
have been given a water-use classification by the Illinois
Pollution Control Board (IPCB) and should comply with the ap-
propriate water quality standards.  Details of these standards
are presented in Chapter II of this EIS.  Other important
objectives of TARP are to:

          Preserve the health and well-being of the population
          Prevent further pollution of Lake Michigan due to backflow
          Utilize treated waste byproducts
          Prevent flooding.

     The final TARP is a combination of several alternative
plans designed to collect urban runoff during all wet wea-
ther conditions except those storms of a magnitude equal to
the three most severe storms recorded to date by the U.S.
Weather Bureau Service.
                            - vii-

-------
             II. EXISTING ENVIRONMENTAL SETTING
     To provide a basis for assessing the impacts of a pro-
posed project, an EIS initially describes the existing natural,
social, economic, and cultural setting of the area which
may be affected by a project.  This chapter summarizes the
major findings of the EIS with respect to the natural and
man-made environments of the Chicago metropolitan area.  This
chapter is divided into two sections which correspond to
Chapters II and III of the EIS text:  Natural Environment
and Man-made Environment.
2.1  NATURAL ENVIRONMENT

     The existing natural environment of the Chicago area
summarized in this section focuses on those features rele-
vant to impact assessment of the proposed TARP project.  This
section is divided into the following categories:

          Water Resources
          Land Resources
          Atmospheric Resources.
2.1.1  Water Resources

     The surface water systems of the Chicago area consist
of a network of rivers and canals whose natural flow into
Lake Michigan is controlled by a series of locks.  These
surface water systems include the Chicago River, the Sanitary
and Ship Canal, the Calumet River system , and the Des Plaines
River system.  Lake Calumet and Lake Michigan also constitute
an important part of the area's surface water resources.

     The quality of the surface water systems is affected by
steady-state effluent discharges and by injections or dis-
charges of polluted wastewaters.  The polluted wastewater
results from overflows of combined-sewer systems during rain-
fall events of nominal size (approximately 0.1 inches or
greater).  The frequency of these rainfall events is approxi-
mately 100 times per year, and the resulting overflows are
discharged directly to the Chicago area's streams and rivers.
                            -viii-

-------
Pollutant concentrations in the  streams and rivers presently
exceed  water quality standards established  by the State of
Illinois  Pollution  Control Board.   Concentration ranges of
various pollutants  in the Chicago  area's  surface systems are
presented in Table  II-l.  Further  details on the water quality
of specific water systems are presented in  Section 2.1.1 of
the EIS.
                          Table II-l
          Summary of Pollutant Concentration Ranges
             in Chicago's Surface Water Systems
Pollutant
Dissolved oxygen (DO)


Biochemical oxygen
demand (BOD)
Ammonia (as N)

Suspended solids (SS)
Fecal colifonn

Chicago Raver —
Sanitary and
Ship Canal System
1.2 to 7.7 mg/1



5.2 to 9.2 mg/1
0.8 to 6.2 mg/1

19 to 54 mg/1
477 to 12,700
(counts/100 ml)
Calumet River
System
3.9 to 9.0 mg/1



4.1 to 7.3 mg/1
1.3 to 13 mg/1

12 to 73 mg/1
152 to 738
(counts/100 ml)
Des Flames
River System
6.0 to 10 mg/1



5.0 to 6.7 mg/1
0.3 to 1.2 mg/1

29 to 68 mg/1
411 to 8,700
(counts/100 ml)
Applicable Illinois Standards*
Secondary
Contact
5.0 mg/11
4.0 mg/1 (1978) 2
3.0 mg/1
4.0 mg/1 mm.1
2.0 mg/1 mm.
4-20 mg/14
4.0 mg/1 (winter)
2.5 mg/1 (summer)
5-25 mg/15
1000/100 ml1

General
Use
6.0 mg/1
5.0 mg/1 mm.3



4-20 mg/14
2.6 mg/13

5-25 mg/15
200/100 ml2

 *  Effluent discharge standards apply if water quality standard is not designated.

 1  North Shore Channel Standards

 2  Chicago River-Sanitary and Ship Canal System and Calumet River system.

 3  General Use Standard applicable to Des Plaines River system.

 4  4 mg/1-Kanover, Egan, and O'Hare Sewage Treatment Plants
    10 mg/l-wsw and Calumet Sewage Treatment Plant
    20 mg/1-Lemont Sewage Treatment Plant

 5  5mg/l-Hanover, Egan, and O*Hare STP
    12mg/l-WSK and Calumet STP
    25mg/l-Lemont ETP
      Serious public health  problems involving contamination
of Chicago's drinking water supply has  led to implementation
of regulatory measures to protect Lake  Michigan,  an important
drinking water  resource, from pollution.   Locks and gates have
been installed  to divert river flows  away from Lake Michigan,
allowing eventual drainage  into the Illinois River.  Lake
Michigan supplies most of the drinking  water for  the Chicago
area.   The withdrawal amount is approximately 1,600 cubic
feet per second (CFS), and  the maximum  amount that  can be
withdrawn from  Lake Michigan is 3,200 CFS.1  This withdrawal
limit,  or allotment, is presently divided into three usage
types:   domestic water supply, indirect waterway  diversion,
and  direct waterway diversion.  The diversion usages allow
improved effluent dilution  and improved navigation.
      Supreme Court Decision.
                              -ix-

-------
     In the Chicago metropolitan area, there are two main
aquifer systems:  the upper aquifer, which consists of gla-
cial drift and dolomites, and the lower aquifer, which con-
sists of dolomite and sandstone formations.  Unconsolidated
Quaternary deposits and Silurian dolomites of the upper aqui-
fer are hydraulically connected and function, in most areas,
as a single water-bearing unit.  Clayey deposits in the gla-
cial drift act as confining layers to create artesian condi-
tions in the upper aquifer.  The lower aquifer includes dolo-
mite and sandstone formations extending from the base of the
Maquoketa Group to the top of the Eau Claire shales of the
Cambrian system.  The average thickness of the upper aqui-
fer and lower aquifer is approximately 400 feet and 1,000
feet, respectively.  The sources of recharge for the ground-
water in the upper aquifer are infiltration of precipitation
and influent streams.  The lower aquifer is recharged in
parts of McHenry, Kane, and De Kalb Counties where the
Maquoketa Group outcrops, and further west where the Group
has been removed by erosion.  With respect to using the
aquifers as a water resource, studies indicate that the
lower aquifer is capable of producing about 25 Million Gal-
lons per Day (MGD) and the upper aquifer is capable of a
potential yield of 108 MGD.

     Discharges into the waterways of the Chicago area ori-
ginate from several sources, including:  wastewater treat-
ment facilities, industrial plants, and combined-sewer over-
flows.  Six wastewater treatment facilities currently dis-
charge treated water to existing waterways.  The outfalls
are located adjacent to the facilities.  Most of these faci-
lities are in compliance with the BOD and SS effluent
standards (under present permit conditions), and two smaller
plants are within the ammonia-nitrogen standard.  With re-
spect to industrial plants, wastewater is conveyed to treat-
ment plants and processed before discharging.  The industrial
waste load averages approximately 195 MGD or equivalent to a
population of 4.5 million.  Combined-sewer overflows, which occur
about 100 times per average year, inject pollutants in large
amounts into waterways at approximately 640 outfall points in the
Chicago area.   During such events,  minimum Illinois water quality
standards established for restricted-use waters are not met.

     Numerous water resource management programs have been
initiated to address the flooding and/or pollution problems
of the Chicago area.  These programs have been or are cur-
rently being conducted either regionally or locally.  A few
of these programs include:  the Section 208 Areawide Waste
Treatment Management Planning program, the Chicago-South
End of Lake Michigan study (C-SELM), the City of Chicago
                            - x-

-------
Sewer Construction program, Thornton Quarry Flood Control
project, and the Chicago Metropolitan Area River Basin Plan
(CMARBP).
2.1.2  Land Resources

     The Sanitary and Ship Canal and the Calumet-Sag Channel
have significantly altered the natural drainage patterns
which are from west to southwest in the area near Lake Michigan,
Prior to construction of the Canal and Channel, the drain-
age flow was toward Lake Michigan.  The flow is presently
toward the Chicago River and the Sanitary and Ship Canal,
which drain into the Illinois Waterway system.  The overall
low relief of the MSDGC combined-sewer system area makes it
prone to flooding caused by sewer system backups and/or over-
bank flows.  The areas with the highest overbank flooding
potential lie along the North Branch-Chicago River and in
the Calumet River system.

     The Chicago area lies on the broad, gently sloping, north-
westerly-trending Kankakee Arch.  This arch, which connects
the Wisconsin Arch to the northwest with the Cincinnati Arch
to the southwest, separates the Michigan Basin from the
Illinois Basin.  The northeast sector of the Chicago area
lies-on the northeastern side of the Kankakee Arch, while
the southwestern sector of the Chicago area lies on the
southwest flank of the Arch.  In the Chicago area, overall,
a number of gentle east-west-trending folds are superimposed
on the area's broad regional geologic structures.  Numerous
minor faults and several major faults have been mapped, in-
cluding:  the Sandwich fault near Joliet and the Des Plaines
disturbance near the community of Des Plaines.  The upper-
most 500 feet of rock layers, particularly the dolomites
and shales between the top of the Racine formation and the
base of the Brainard formation, will be relevant to the pro-
posed construction of the TARP tunnel systems.  The surface
layer (glacial deposits) has an average thickness of approxi-
mately 80 feet.  Drop shaft and construction shaft installa-
tions will be constructed within this layer.

     Based on 175-year historical earthquake records, four
major earthquakes occurred within 100 miles of Chicago with
intensities equal to or greater than MMI VIII  (Modified
Mercalli Intensity scale).  These earthquakes originated at
Fort Dearborn (Chicago)   (1804), near Rockford  (1909), near
Aurora (1912), and near Amboy (1972).  Within the MSDGC
combined-sewer service area, there are 30 faults with moder-
ate vertical displacement characteristics and 86 minor
faults with small vertical displacement characteristics.
                            -xi-

-------
2.1.3  Atmospheric Resources

     Air quality in the Chicago metropolitan area is pres-
ently monitored by the city of Chicago Department of Environ-
mental Control and the Cook County Department of Environ-
mental Control.  A total of 61 monitoring stations have been
established in Cook County; 30 of these are located within
the city limits of Chicago.  Based on the 1974 Annual Air
Quality Report published by the State of Illinois EPA, am-
bient air quality standards were frequently violated at one
or more stations.  The pollutant standards violated include:
sulfur dioxide, particulate matter, carbon monoxide, hydro-
carbons, and photochemical oxidants (measured as ozone).

     The existing outdoor noise levels in most areas of
Chicago are caused mainly  by  street traffic.  Other noise
sources include trains, aircraft, and industrial plants in
city areas, and power lawn mowers, power tools,  and other
motor-driven equipment in residential areas.  Based on a
recent EPA study, typical noise levels for the Chicago area
ranged from 36.3 dBA  (decibels-A scale)  (night)  to 106.2
dBA  (day).  The day-night level  (Ldn)  ranged from 59.0 dBA
to 71.2 dBA (overall  average).


2.1.4  Biological Resources

     Many species of wildlife reside in or migrate to the
forest preserves, parks, and other natural areas in the
Chicago region.  Over 200 species of birds have been sited
in these areas and about half of these species are the mi-
gratory and waterfowl type.  Common mammals residing in the
preserves include:  whitetail deer, eastern cottontail,
opossum, racoon, gray squirrel, red fox, and woodchuck.
Approximately 40 species of reptile and amphibian can also
be found in the Calumet area.  A comprehensive list of the
wildlife species is provided in Appendix J of the EIS.

     Aquatic life in the rivers and streams of the Calumet
watershed is currently limited to pollution-tolerant or
hardy species.  Poor water quality conditions of these
waterways have reduced the diversity and abundance of
aquatic life.   The major species of fish in the watershed
include:  central mudminnow, white sucker, carp, goldfish,
stone-roller,  creek chub, bluntnosed minnow, fathead minnow,
golden shiner, black bullhead, largemouth bass,  green sun-
fish, bluegill, pumpkinseed, sunfish (lepomis),  Johnny
darter.
                           -Xll-

-------
     The natural vegetation normally found in the natural
areas of the Calumet Tunnel project area consists of a
modified form of the beech-maple forest, in the more moist
areas, and Oak-hickory forests in the more open areas.  The
transitional flora between these two forest types include
maple-basswood and maple-basswood-red oak forest.  A recent
survey was conducted along the Little Calumet River, and a
few areas in a natural state were found.  Natural vegetation
was observed near Kennedy Avenue, Cline Avenue, Coifax Street,
and Burr Street in which the majority of species were cotton-
woods, poplars and willow with occasional oak, maple, and
mulberry.  Wetland areas along various streams are predomi-
nated by willow species, eastern cottonwood, and yellow
poplar.  Various grasses, forbs, cattails, arrowheads, and
nettles are also common.
2.2  MAN-MADE ENVIRONMENT

     The various components related to man's activities in
the Chicago area are summarized in this section.  These com-
ponents include:  Socioeconomic, Land Use, Sensitive Areas,
Financial and Labor Resources, Transportation, and Major
Projects and Programs.


2.2.1  Soc ioeconomic

     The Chicago metropolitan area has experienced growth
and change in its demographic profile similar to other major
cities in the United States.  Chicago, the third largest
standard metropolitan statistical area (SMSA) in the United
States, has experienced typical population redistribution
trends within the SMSA.   The close-in suburban jurisdic-
tions grew rapidly during the 1950's from a substantial in-
migration of population from the south and an out-migration
of people from the city of Chicago.   During the 1960's, the
counties adjacent to Cook County urbanized rapidly.  Con-
tinued redevelopment of the City, when combined with smaller
household trends, uncertainties regarding energy availability
and cost, and the increasing cost of suburban new construction,
should result in a strengthening of  the urban centers and a
lessening of the outward population  movements.  Chicago's
population is expected to stabilize  after 1980..

     Contract construction income accounts for less than
eight percent of total earnings in the Chicago region.  While
average monthly  wages  for construction employment are  high
relative to other industries in the  Chicago region, total
                            -X1Z1-

-------
earnings from contract construction have ranged from 6.5 to
7.7 percent of total earnings over the period 1950 to 1971.
The construction industry is heavily unionized, and the
current union hourly wage rate averages $11.02.   (Refer to
Table III-6 of the EIS).

     The Chicago area has traditionally sustained strong
construction activity in the public and private sectors.
Major public redevelopment projects have stimulated private
investment and development, particularly within the city of
Chicago.  Construction employment opportunities have thus
attracted and created a large construction labor force.  Con-
struction employment in the Chicago SMSA numbered 136,897
people in 1970 or approximately 4.8 percent of the total
employed.  Construction employment in the Chicago SMSA ac-
counted for 61 percent of total construction employment in
the State of Illinois.  The Chicago area construction work
force is highly flexible and can expand rapidly, given the
demand for construction services.
2.2.2  Land Use

     The predominant land use bordering the Calumet Tunnel
route can be characterized by its industrial zoning in which
large portions of land are underutilized and vacant.  There
are a few small residential areas bordering the tunnel route.
Rock taken from the tunnel will probably be disposed of at
McCook, Stearns, and Thornton quarries.  Sludge will be dis-
posed of at a number of sites or by a number of programs,
including:  the Fulton County project, NuEarth, broker sales,
Lawndale Lagoons, and other landfills.

     The land areas bordering the proposed tunnel route are
expected to remain generally the same along the main and
branch segments.  New recreational park development along
the riveredges are envisioned as a land enhancement move-
ment by the communities in the Calumet area.

     Redevelopment plans may also call for the strengthening
of various industrial areas.  Industrial uses along the
Calumet-Sag Channel are likely to continue because of the
need for low cost water transport.  Improved water quality
in the rivers and the channel plus storm water management
would enhance improvement of industrial areas.
                            -XIV-

-------
2.2.3  Sensitive Areas

     There are no known archeological  or  historically signi-
ficant sites adjacent to or within  the Calumet Tunnel route.
MSB is presently investigating areas adjacent  to planned
tunnel routes.  There are selected  sites  of  historic and
architectural interest within the vicinity of  the tunnel
route, but none within the immediate 500-foot  impact area
of the tunnel.  These sites are  listed in Chapter III of
the EIS.
2.2.4  Financial Resources

     Financial resources are currently  available  to fund the
Calumet Tunnel system.  TARP's Phase  I  tunnel  system cost
breakdown is approximately  $1.03 billion-'-  for  water pollu-
tion elements and $0.81 billion for flood  control measures.
Operation and maintenance of TARP has been estimated at
$13 million annually.  The  estimated  cost  of the  Calumet
system alone is $378.2 million, with  an annual maintenance
cost of $2.5 million.

     Analysis of the funding resources  required to finance
the Calumet Tunnel system reveals that  sufficient funds
are currently available from the Federal Government,  the
State, and the MSDGC.   (See Section 3.3.1  of the  EIS).
Additionally Federal Water  Pollution  Control funds of ap-
proximately $290.0 million will be required to meet the
implementation plan for the other conveyance tunnel systems..
In view of the sound fiscal posture of  the MSDGC,  the high
funding priority assigned TARP by the State, and  the very
conservative estimates of future Federal appropriations,
it can be reasonably assumed that future financing require-
ments can be satisfied.

     Maintenance costs  can  either be  covered  through an ad
valorem property tax, or through a user charge system based
on water consumption.   EPA  favors the latter  approach and
has awarded the MSDGC two grants to develop such  a user
charge system.
     Cost estimates based on values presented in MSDGC's "Facilities
     Planning Study—MSDGC Overview Report," Revised, January 1975.
                            -xv-

-------
 2.2.5  Labor Resources

      Labor resources are considered adequate to meet con-
 struction and implementation needs of TARP and other proj-
 ects.  The diversified labor force in the Chicago metro-
 politan area is vulnerable to economic recession because
 of the emphasis upon manufacturing and nonservice employ-
 ment.  Thus, while national unemployment was about 8.4 per-
 cent in the third quarter of 1975, Cook County had a 9.6
 percent rate, and the city of Chicago sustained a 11.2 per-
 cent rate of unemployment.  Increasing productivity rates
 and an expanding labor force should contribute to keeping
 Chicago unemployment levels higher than the national rate
 for the next few years.   Therefore, new employment oppor-
 tunities presented by TARP and other projects should not
 experience a shortage of labor resources.

      The labor force is  predominantly male, with white
 collar workers comprising 53 percent of the labor force in
 the SMSA.
2.2.6  Transportation

     Implementation of the Calumet Tunnel system will in-
volve the use of roadways and waterways.  Trucks carrying
rock and spoil material from construction sites will utilize
several surface streets and expressways in reaching the
quarry or disposal site.  The roadways range from dirt roads
to six-lane divided highways.  The Calumet Tunnel route also
is proximate to major waterways; the Calumet River, the Little
Calumet River, and the Calumet-Sag Channel.  Waterborne com-
merce is important to the Chicago economy; of the 46.2 million
tons of waterborne freight traffic handled by the Port of
Chicago, an average of 37 percent or 17.1 million tons are
moved over the inland waterways annually.


2.2.7  Major Projects and Programs

     There are no planned major projects and programs pro-
posed over the next 10 years in the vicinity of the Calumet
Tunnel route.  Possible projects and programs that could de-
velop during this period would consist mainly of transpor-
tation system improvements.  Other possible public projects
include the proposed acquisition of rights-of-way along the
northern segment of the Calumet River.  These rights-of-way
are privately owned,  and used by Commonwealth Edison and Natural
Gas Pipeline Company of America for energy transmission.  The
intent of the public acquisition would be to establish a per-
manent utility corridor to more efficiently service growing
energy demands.

                           -xvi-

-------
              III.  THE PROPOSED ACTION
     Identifying and defining a plan and its systems and
subsystems establishes the proposed action for which the en-
vironmental setting is described and the environmental im-
pacts are assessed.  The proposed action identified and de-
fined for this EIS is the Phase I conveyance tunnel systems
and their associated subsystems only.  The planned storage
reservoirs, waste treatment plant upgrading and expansion,
on-line reservoirs, and instream aeration facilities were
not included.

     The information presented in Chapter IV and V of the
EIS is summarized in this chapter and divided into seven
parts:

          Alternative Plans
          Plan Selector
          TARP Tunnel Systems
          TARP Subsystems
          Calumet Tunnel Segments and Branches
          Cost of Tunnel System and Subsystems
          TARP Financing.
3.1  ALTERNATIVE PLANS

     Many plans to resolve the Chicago area's flooding and
water pollution problems were developed during the past two
decades by concerned government agencies, local organiza-
tions, and individuals.  At first, the plans focused prima-
rily on the flood control problem, however, as water quality
conditions in the area worsened, more emphasis was placed
on controlling the water pollution.  A total of 23 plans
were formulated, and many were evaluated in detail by a
Flood Control Coordinating Committee (FCCC), consisting of
representatives from the State of Illinois, Cook County,
the MSDGC, and the city of Chicago.

     In screening the alternative plans, the FCCC established
overall flood and pollution control objectives which pro-
vided a basis for evaluating alternative plans.  A plan was
automatically rejected if it did not:
                           -xvii-

-------
          Prevent all backflows to Lake Michigan to protect
          water supply resources

          Reduce pollutant discharges caused by combined-
          sewer overflows

          Reduce flooding in the combined-sewer and down-
          stream areas.

     In the initial screening, 6 plans were eliminated and
the remaining 17 were modified to meet the objectives more
fully as well as to provide a more quantitative basis for
comparison.  The modifications were referred to as MODs,
and consisted basically of a combination of different sto-
rage capacities and waterway improvement actions.  The
resulting MODs yielded 51 alternative subsystem plans, or
subplans, to tre evaluated by the FCCC.  In the next screen-
ing phase, the FCCC defined eight principal parameters,
including capital costs (1972 dollars), estimated annual
operating and maintenance costs (1972), project benefits,
land acquisition acreage, underground easement requirements,
resident and business relocations, construction impacts,
and operation impacts.   A technical advisory committee was
organized by the FCCC to evaluate the modified alternatives
in detail using the eight parameters.  The advisory commit-
tee's interim report, "Evaluation Report of Alternative
Systems," recommended a 50,000 acre-feet (ac-ft) storage
level, which was part of the modified alternative designated
as MOD 3.  After reviewing the report, the members of the
FCCC unanimously concluded that the flood and pollution con-
trol plan should be in the form of one of the four Chicago
Underflow plans developed (four of the seventeen plans) or
a combination of these plans, along with the recommended
storage level.  The FCCC stated that, "These alternatives
are less costly and more environmentally acceptable to the
community than any of the other plans presented.  Detail
studies along the lines of these alternatives should pro-
ceed to develop the final plan layout."
3.2  PLAN SELECTION

     In August 1972, the FCCC members presented their final
recommendations in a report with seven technical appendices.
The report recommended consolidating the favorable features
of the four Underflow plans into the Tunnel and Reservoir
Plan (TARP).  TARP was developed further and refined, then
                          -XVI11-

-------
evaluated in detail with four selected alternatives and the
"no-action" alternative.  In this evaluation, 15 significant
environmental impact parameters were identified as the basis
for evaluation.  The FCCC concluded that very few negative
impacts are expected for any of the alternatives incorporat-
ing conveyance tunnels, and that adverse impacts will occur
if the "no-action" alternative is chosen.  The FCCC also con-
cluded that the construction impacts of all plans on the en-
vironment will most likely be relatively short-term and local-
ized.  Finally, the beneficial impacts of the plans will far
exceed the adverse impacts.  Within'the scope of the FCCC
analysis, TARP had the highest ranking and was selected as
the most suitable plan to solve the flood and pollution prob-
lems of the Chicago metropolitan area.

     TARP would provide the most benefits for the lowest
cost and the least adverse environmental impacts.  Field
studies and subsurface exploration programs further refined
the plan; however, they did not change the original TARP
concept.  They were conducted only to optimize overall sys-
tem effectiveness.  Presently, TARP will enable collection
of runoff water resulting from all but three of the severest
rainfall storms recorded during the past 21 years.


3.3  TARP TUNNEL SYSTEMS

     The four tunnel systems that are a part of the Tunnel
and Reservoir Plan are the Mainstream, Calumet, Lower Des
Plaines, and O'Hare systems.  Each system is a completely
independent operating unit with collection, storage, convey-
ance, and treatment capabilities.  Figure III-l shows the
present routes and layout of these systems relative to the
MSDGC combined-sewer service area, the MSDGC overall service
area, and Cook County.  Each of the TARP systems shown in
the figure consists of three component systems:  reservoirs,
conveyance tunnels, and sewage treatment plants.  A total
of three reservoirs, 120 miles of conveyance tunnels, and
four sewage treatment plants are included in the plan.

     The TARP systems have two basic features which play a
major role in solving the flood and pollution problems.
First, the combined storage capacity of the plan is almost
136,800 ac-ft of which 127,600 ac-ft of the total is reser-
voir capacity and 9,200 ac-ft is tunnel capacity.  The
planned treatment capacity of TARP will be approximately
2,240 MGD.  Second, over 640 existing overflow points
will be eliminated within the MSDGC combined-sewer service
area by the TARP systems.
                            -xix-

-------
            FIGURE III-l
     Tunnel and Reservoir Plan
     System Layout and Routes
-XX-

-------
     The proposed locations for the three reservoirs are:
McCook quarry, Thornton quarry, and an area northwest of
O'Hare International Airport.  The conveyance tunnels,
located 150 to 290 feet below ground level, will be con-
structed under existing waterways and public rights-of-way.
Of the sewage treatment plants, three of the four plants
are currently activated sludge plants with a combined
planned capacity of approximately 2,150 MGD.  The remaining
plant is the proposed O'Hare-Des Plaines plant which will
have a treatment capacity of over 70 MGD.  A water reclama-
tion plant, the John F. Egan plant, is presently under con-
struction and the capacity will be 30 MGD.
3.4  TARP SUBSYSTEMS

     The subsystems common to all TARP tunnel systems in-
clude drop shafts, collecting structures, and pumping sta-
tions.  The drop shafts range from 4 to 17 feet in diameter
and have two basic designs.  One design features a slotted
inner wall to assist in aerating the incoming water.  The
wall separates the air shaft from the water shaft and allows
air either to enter or to escape while water is flowing in
or being pumped out.  The other design features a separate
air shaft, to be installed in areas where high overflow rates
prevail.  The inside diameter of this drop shaft design
ranges from 10 to 17 feet.

     Approximately 640 collecting structures will be con-
structed to collect the overflows at established locations.
The collecting structure basically consists of a diversion
unit at the overflow point and a connecting pipe to the
drop shaft entrance chamber.  Most of the new structures
will be constructed near curbs or in low points adjacent to
major public thoroughfares.

     Pumping stations will be constructed underground at the
end of all conveyance tunnel routes and adjacent to all sto-
rage reservoirs.  These stations permit a rate of dewatering
of the tunnels and reservoirs which will allow a full tunnel
or reservoir to be emptied within two to three days.  The
stations will also be used to transport bottom sludge dredged
from reservoirs to treatment facilities.
                            -xxi-

-------
3.5  CALUMET TUNNEL SEGMENTS AND BRANCHES

     The Calumet system of TARP consists of:   one waste
treatment plant with a total capacity of approximately  220
MGD; over 37 miles of conveyance tunnel with  a storage
volume of 1,690 ac-ft; and one main storage reservoir with
a maximum capacity of 40,900 ac-ft. The component subsys-
tems associated with the Calumet system include 59  drop
shafts; over 100 collecting structures; and two pumping
stations located near the Calumet Sewage Treatment  Plant
and the intersection of the Torrence Avenue and plant-to-
Calumet city Tunnels.  The system and its component sub-
systems will be constructed in two phases.  In Phase I,
approximately 30 miles of tunnel will be constructed, and
in Phase II, the remaining 7 miles will be constructed.
The Phase II tunnel route is parallel to the  Indiana Avenue
segment of the Phase I tunnel, as shown in Figure III-l,
and it will be used as a relief tunnel.

     This EIS addresses the Phase I segments  and branches
of the Calumet system and focuses only on the conveyance
tunnel system.  The overall length of this tunnel system
is approximately 30 miles.  The subsystems associated with
it include 59 drop shafts, 5 construction shafts, 22 access
shafts, 101 collecting structures, and 2 pumping stations.
3.6  COST OF TUNNEL SYSTEM AND SUBSYSTEMS

     The MSDGC estimated cost  of a 10-foot diameter tunnel
in rock with nominal aquifer protection is $200^ per lineal
foot.  In rock with high quality aquifer protection, the
cost is $230.  Tunnel cost for soft ground construction is
$350.  Similarly, for a 35-foot diameter tunnel, the esti-
mated costs are $1,030, $1,090, and $1,680 per  lineal  foot,
respectively.

     Large rectangular tunnels adjacent to construction  shafts
will be excavated by the drill and blast method and the estimated
cost with nominal aquifer protection  is $2,090  per lineal foot
1    MSDGC, January 1975.

2    All cost figures presented in this  section are based on 1972 values.
                          -xxii-

-------
for a 30-foot square tunnel.   The  same type and size of tun-
nels with high quality aquifer protection would cost an esti-
mated $2,170 per lineal  foot.

     The tunnel costs estimated above include the following
base figures:

          Cost of muck disposal,  estimated to be $4.00 per
          solid cubic yard

          Nominal grouting  for control of infiltration
          during construction, estimated to be $0.30 per
          square foot of tunnel wall

          Access and ventilation shaft construction

          Ventilation and hoist equipment

          Grout and grout inspection equipment

          Average aquifer protection costs.

Additional grouting for  aquifer protection in unlined tun-
nel segments in the upper aquifers is estimated to cost
$1.50 per square foot of tunnel wall.  This grouting would
be provided to a depth of about one tunnel diameter beyond
the excavated tunnel limit.

     The total construction  cost for all the Phase I TARP
tunnel systems is approximately $567 million.  The estimated
total costs for the subsystems are:  $93 million for collect-
ing/connecting structures, and $38 million for pumping
stations.  These subsystem costs are based on the following:

          Collecting Structures and Connecting Lines.  The
          cost of the near-surface collection structures
          leading to the drop shafts includes the gravity
          interceptor sewers and the necessary connecting
          structures.  Table III-l lists the costs for these
          subsystems with respect to the TARP tunnel systems,
     Grouting is a procedure whereby a mixture of cement and water is
     injected under pressure into a drilled hole that intersects a
     source of seepage such as an open joint, fault, or bedding plane.
                           -xxiii-

-------
                         Table  III-l
                    Estimated  Costs For
        Collecting Structures  and Connecting Lines
Tunnel System
Mainstream
Calumet
Lower and Upper
Des Plaines
TOTALS
Estimated Cost ($ .Million)
Intercepting
Structures
8.701
1.084
1.043
10.828
Collection
System
3.648
1.088
3.489
8.225
Total
12.349
2,172
4.532
19.053
          Drop Shafts.  The estimated cost of drop  shafts
          includes all drop shaft components.  The  costs are
          related to the shaft diameter and to the  depth of
          penetration into the rock formations.  The cost of
          250-foot deep drop shafts varies from  $80,000 for
          a shaft two feet in diameter to $1,400,000 for a
          20-foot diameter shaft.

          Pumping Stations.  The estimated construction cost
          of pumping facilities includes the structure, pump-
          ing equipment, power generation for the operation
          of larger units, and discharge piping  to  the appro-
          priate treatment plant.  The estimates have been
          based on use of variable-speed, motor-driven units.
          Total capital costs for pumping vary as follows:
            Lift
           Height

          300 feet

          525 feet
Estimated Cost ($ Million)

     Pumping Capacity
 1000 cfs      100,000 cfs
    5.6

    5.7
200

300
3.7  TARP FINANCING

     Financing of the entire $3.54 billion MSDGC Flood and
Pollution Control Plan over the next 11 years is doubtful.
As illustrated in Table III-2, however, the financing re-
quirements for all conveyance tunnels could be met by a
modest increase in Federal and MSDGC funding over a period
of 11 years,  from 1976-1986.   An additional $290 million
appropriation of funds are estimated to be required to
                           -XXIV-

-------
fN
    a
    0)

    in
    >i  QJ

       +j
   •H     c
    OJ <4-l  (0
    c  o  -\
    C!     C^
    3  n

        c  o
   H  0)  U
        e  -p
    Q)  0)  C
H

 0)
H

 m
        o
    w  O

    f^4  CJ
    c<  o
    f^I  -H
    EH  4J
     I   3
     C  H
'3  O  -H
T3 2  O
 d)     o^
    (U
    CnO
    C
    -H -a
    U  C
    C  <0
    rt)
    C
    •H
           U
           o
           Q







S
















MSDTiC









in
i
M
o
"

*







<
u






S-,
e-o
SS

•H 3

V
V *>
Si!
11

>• V
32
C <0
U 

>n
*
*J -H
•n1 3


rf «

4J 4J
C U
0) 0)
p 1-
si
>> 0
c «
01 -H
ss
u<
1-0
2£

•o c
< DC
V *-
p T"
W C
u o.
.n
*J X
§;
s!
h
ii
-^ a
s|
u"c
U o.

S" a
^ !2
c «
V -I
n «
u 5
r.
*> t
n C
wu
n
>. i
-H (
£ c





o
0

o
o







o


0

0


r-



«
«



O
o


o
o


o
0

o

o
rl


0

«>
 a
> c
c c
-^





o
o

0
0





o

o


o

o


\D



0
0



0
o


0
0



o

o

o
0





o
o

^

-<
Instream j
Aeration
«



o o

O O O
0
o o
o o o
o



O 0

o o o

o
tC *H
o • •

o

CO W
J to
1 (N 1
o • o
. eg .
o 
-------
                             FOOTNOTES
1     All cost estimates are based on those presented in the MSDGC's
      Facilities Planning Study  (January 1975) and are escalated 6
      percent annually for inflation.

2     These funds represent the remainder of the FY 1975 and FY 1976
      PL 92-500 appropriation which are expected to be allocated to
      MSDGC by the State.

3     These are Federal funds, above and beyond the existing PL 92-500
      appropriation, which are expected (in the form of a new appropria-
      tion) over the period FY 1977-1982.

4     These are Federal funds above and beyond the additional $780 million
      expected over the FY 1977-1982 period.

5     These are funds, under the State's current $750 million bonding
      authorization, which are expected to be available to MSDGC to
      finance the Tunnel Plan.

6     The funds in this category represented those available by virtue
      of the unused bonding authority of the MSDGC under the current
      $380 authorization.

7     This category represents funds expected to be available under an
      additional $200 to $400 million bonding authority for which  the
      MSDGC is currently formulating plans to ask the State of Illinois.

8     There is no current COE appropriation for any MSDGC Flood and
      Pollution Control Plan elements.

9     There is no near future COE appropriation expected for any MSDGC
      Flood and Pollution Control Plan elements.

10    Includes approximately $49.6 million already obligated to the
      North Shore section of the Mainstream Tunnel Plan (Addison-
      Wilmette segment).

11    Figure doesn't include the estimated $124 million already obligated
      for the O'hare treatment plant project.

12    The total estimated cost $3030.6 million differs from the $3536.5
      million (Table 111-10 of the main body of the EIS)  because of the
      exclusion of the following projects:  sewers, solids disposal,
      O'Hare Treatment plant, and flood control (non-TARP).
                               -xxvi-

-------
finance the three  (Mainstream, Calumet, and Lower Des
Plaines) TARP tunnel systems.  The additional Federal
funds represent a modest portion  (28.3 percent) of the
conservatively estimated $780 million of new PL 92-500
money which is expected to be forthcoming to MSDGC over
the next six fiscal years.  Congress, however, has not
yet approved any additional appropriation beyond the
initial $18 billion which was authorized under PL 92-500
and totally allocated over the FY 1972-1976 period. The
$73.5 million of MSDGC funds represents an increase of
about 19 percent over the current MSDGC bonding autho-
rization.  This amount, however, represents a very modest
proportion of the additional $200-400 million bonding
authorization for which MSDGC is currently formulating
plans to ask the State of Illinois.

     If the Phase I tunnels of TARP are not implemented, there
is a very high probability that approximately 90 percent of
the currently available Federal funds assigned to the MSDGC
will be lost by both the State of Illinois and the MSDGC.
This potential loss to the MSDGC and state stems from the
fact that the Calumet treatment facility expansion project,
(which represent the next major project in terms of priority
for Federal funds) will not meet the September 30, 1977 dead-
line for Step 3 funding eligibility.  Assuming this project
did not qualify in time for existing Federal funds, it is
estimated that only approximately 10 percent of the $323.6
million could alternatively be allocated to other MSDGC or
statewide prioritized pollution control projects.

     The financing feasibility of other key elements  (non-
Phase I TARP)  of the MSDGC's Flood and Pollution Control
Plan (see Table III-2), which are closely related to the
overall goal of meeting the 1983 water quality standards,
ranges from almost certainty to near zero.  Addressing
these elements in the order of priority specified in the
MSDGC's 1975 Facilities Plan, instream aeration stands
slightly ahead of the conveyance tunnels.  The approximately
$16.7 million required for instream aeration can easily be
met from existing state and MSDGC funding sources.1 It is
very unlikely, however, that the financing will be available
to increase the treatment levels, efficiencies, and capacities
at the Calumet and West-Southwest treatment plants.  The
total required financing  ($1.02 billion) would necessitate
a significant increase above the additional levels of Federal
($780 million) and MSDGC  ($200-400 million) funds expected
to be available over the FY 1977-1986 timeframe.  The fi-
nancing feasibility of the Calumet treatment plant expansion,
however, is reasonable in view of their combined total
1    As of May 1976, funding for instream aeration has already been
     authorized.
                           -XXVil-

-------
estimated costs of $352.8 million.   The  Federal  funding
portion  ($264.6 million) could be provided  from  the additional
$780 million PL 92-500 appropriation expected over the next
six years.  The MSDGC portion  ($88.2 million)  could be
provided from the anticipated  $200-400 million additional
bonding authorization.   In terms of the West-Southwest
treatment plant expansion project  (estimated cost of $666.3
million), the financing feasibility  is very questionable in
view of the requirement for additional funds beyond the
levels  (Federal and MSDGC) expected  to be available over
the period FY 1977 to 1986.

     The operation and maintenance costs of the  TARP tunnel
systems will be financed by a  user charge system rather than
the current ad valorem tax system.   PL 92-500 requires the
development of a user charge system  and  the State of Illinois
presently has the authority to impose a  user charge.  This
system of financing the annual operations and maintenance
costs of the tunnel systems is not expected to have a sig-
nificant economic impact in the  commercial, industrial, and
household sectors.  The incremental  charge  in the MSDGC tax
rate per $100 of assessed valuation  (1975 rate was $.4005)
is estimated to be $.0541  (for operations and maintenance)
and $.0532 (for tunnel construction)  by  the year 1986.  The
tunnel construction impact will  continually decline after
1986 with the continuing growth  of the tax  base.   Details
of this financial system are provided in the EIS in Sections
3.3.1 and 9.3.
     However, to provide the $126.3 million,  the MSDGC's additional
     bonding authorization must be at least $216.5 million.
                         -xxviii-

-------
       IV.  PRINCIPAL FINDINGS CONCERNING THE EFFECTS
                  OF THE PROPOSED ACTION


     Chapters VI through IX of the EIS assess the beneficial
and adverse effects of the construction and operation of the
conveyance tunnel systems on greater Chicago's natural and
man-made environments.  This chapter presents the principal
findings of that analysis only for those effects expected
to be relatively significant.

     The most significant finding relates to the expected
improvement in water quality resulting from the operation
of the three Phase I tunnel systems.  To assess the signifi-
cance of this improvement the EIS includes the consideration
of the possible and likely cumulative effects of TARP com-
ponents which are not a part of the Phase I systems.  These
other components are the reservoirs, treatment plant im-
provements, and instream aeration.

     The principal findings of the EIS are listed as
follows:

      (1)  Effects of Operation on Water Quality

      (2)  Effects of a Significant Earthquake on Tunnel
          System

      (3)  Effects of Rock Spoil Generated During Construction

      (4)  General Effects of Construction

      (5)  Effects of Infiltration and Exfiltration

      (6)  Worker Safety During Construction

      (7)  Effects of Operation on Land Use

      (8)  Effects of Construction on Employment

      (9)  Funding Uncertainty for TARP

      (10) Effects of Flooding on Lake Michigan.
                          -XXIX-

-------
(1)   Effects of Operation on Water Quality

     THE TUNNEL WILL SIGNIFICANTLY REDUCE THE POLLUTANT
     LOAD CURRENTLY DISCHARGED TO CHICAGO'S WATERWAYS,
     HOWEVER,  THE TUNNELS ALONE WILL NOT RESULT IN ATTAIN-
     ING APPLICABLE ILLINOIS WATER QUALITY STANDARDS,
     AND, THEREFORE, WILL NOT ENABLE ADDITIONAL USES
     OF THE AFFECTED WATERWAYS.  THE ATTAINMENT OF ILLINOIS
     WATER QUALITY STANDARDS DEPENDS ON ADDITIONAL CON-
     TROL MEASURES FOR WHICH THE FUNDING PROSPECTS ARE
     NOW POOR.

     This conclusion is based on the following find-
ings:

          The  tunnels will capture approximately 90 per-
          cent of the pollutant load now discharged dur-
          ing  combined-sewer overflows and will reduce
          the  pollutant load 75 percent overall and the
          frequency of overflows from 100 to 10 times
          per  year.   1977 Illinois water quality stand-
          ards will continue to be violated during over-
          flow events because of uncontrolled injections
          of pollutants into the waterways.

          The  tunnels may not result in the attainment of
          1977 Illinois standards for ammonia over
          lengthy reaches of waterway, because high
          concentrations of this pollutant are dis-
          charged from local wastewater treatment plants.
          Although data are not presently available to
          allow a more definitive determination of effects
          on this point, the attainment of water quality
          standards in the area's major river systems
          is clearly and intimately tied to the up-
          grading and expansion of MSDGC treatment
          plants.

          With the tunnels on line,  1977 Illinois standards
          of 4 mg/1 for dissolved oxygen (DO)  will still be
          violated along approximately 50 of the 80 miles
          of the Main Channel and of the Calumet River sys-
          tems during the critical late summer months.
          Conditions along the Des Plaines River system
          have not yet been modeled by the MSDGC, but will
          be completed under the Section 208 planning
          program.
                      -xxx-

-------
         1977 Illinois standards for DO are likely to
         be met over the entire 80-mile length of the
         modeled waterways during critical summer dry
         flow conditions, assuming  implementation of
         the following pollution control  components:

              Tunnels
              Reservoirs
              Treatment plant improvements
              Instream aeration.

         The water quality impact of these various
         pollution control options  is  summarized in
         Table IV-1.

         Given current projections  of  Federal, State,
         and MSDGC financing capabilities and policies,
         the financing of the tunnels  and instream
         aeration appears secure.   The financing of the
         Calumet treatment plant expansion is probable;
         but financing the costly West-Southwest treat-
         ment plant is very doubtful.  The financing
         of the reservoirs in the near future is very
         unlikely given the absence of any Federal com-
         mitment to provide assistance.

     Additional details on water quality are provided in
Sections 2.1 and 8.1 of the EIS text and details on
financing in Section 3.3.1.
 (2)  Effects of a Significant Earthquake on Tunnel
     System

     IF A SIGNIFICANT EARTHQUAKE OCCURS IN THE CHICAGO
     AREA, THE EVENT MAY OFFSET TUNNEL ALIGNMENT AND
     CAUSE SIGNIFICANT DAMAGE TO PORTIONS OF THE TUNNEL
     SYSTEM.

     This conclusion is based on the following findings:

          The 175-year historical earthquake records
          indicate that a seismic event with a Modified
          Mercalli Intensity  (MMI) of VIII can recur
          in the Chicago area at a rate of about once per
          100 years.  Assuming the tunnel system is in opera-
          tion for 100 years, the probability of this event
          occurring at some time during this period is 100
          to 1 or 10,000 to 1 for any given year.  If an
          MMI VIII event occurs, severe alterations to tunnel
          alignment or tunnel surface may result.

                     -xxxi-

-------
co




Options

rH
O
rH
CU
C
c
(0




>H -CH







H
1
>
H

0)
rH
A
(0
EH





















4->
C
o
u

c
o
•H
4-1
3
rH
rH
O
CM

rH
fO
•H
4-)
G
0)
4J
O
CM

MH
O

4J
U
ft)
QJ
e
H




u

c
•H
to
S

O"1
c
0
rH
<

>1
4-1
•H
rH
to
3
O

r-l
0)
4->
10
3-

c
o









CO
E
5
4-1
CO
>.
CO

l_l
OJ
>
•rH
CH

4J
0)

3
rH
ro
U

'O
C
(0













ssed in Section 8.1.1 of E
Q)
M
'O
•d
rO

CO
4-1
£_)
0)
III
11 r
-i
XI

"0
Q)
4->
a,
o
FO
to

M
01

J_l
o

c
•H

C

o

CO

CO
C
O
•H
4-1
p.
O

4-1
0

CP
c
•H
CO
fO
   a,
m
4J
0
2
c
•r| C
TJ O
TO -H
in v< jj

tn rH a, IH
3 CL D OJ
rH <
IX in jj
n c E
in -H ro ro
rH 0 rH 01
0) > CU kj
C IH JJ
c 01 jj m
3 in c c
H 01 01 H

jj tn
TO 3
0) rH
M CM
EH




•U C
c tolo

3 rH rH|jJ
JJfN QJ
tn c tT* <]
rH 01 C
o' e •-< E
C JJ TJ ro
C TO TO QJ
= 0) tl "fi
Si ti cnjj
E-I a. co
D C
t— t

c
0
'**
^
(0
Ll
rH in QJ
-H <
01 0) in
l/> C 3 E
ro C rH TO
.C 3 tX Q)

JJ
in
c







M in
rH
01 01
in c
TO C
£ 3
0. E-









c
0
O -n
Z 
CL / > C
"X, jj oi
/ 01 H c
' JJ rH 0
TO TO DJ
3 3 E
O 0
U


01

C
TO
j •
U


C
TO
0
•rl
UH
•H
C
Cn
•rl
in

O
Z


01
cn
c
TO
£
U
jj
C
TO
U
-H
U-l
C
a>
•H
CO

o
Z
 CJ *J 'O
QJ D- C TO
O (DO
:: o u I-H
T5 •— 1 M
4) 0! 4J t-
u o a c c
«U TO TO
W t/1 4J
S 0 r- D T! •
O 0 -H  In QJ MH TO in
O «-J >i O C 4->
i-i 1 T3
O TO C QJ
O Q) t) a-*
O i-i >,jj nj oj
j-» in *H ,c
in ^ o -P
S >i 0) W -H
O TO CL-H > UH
-I J 0 0
14H iH tfl C tfl
(U J-* E iH IH « £
> TO -H -H TO O --<
O 3 *J M -c E -J


Xj
Q)
3
OJ
1 05
T3 3
0) 0
C rH
•H M-4

S 0)
0 >
U 0


tn
o •
£ JJ
TJ a QJ
C 01 E
•rl > -
0 TJ TJ
in IH M IH
rH a TO TO
QJ E TJ TJ
> -H C C
01 TO TO
rH 01 JJ JJ
>i in in
TO TO
•H 3 TJ to
C rl C 3
0 01 O rl
g jj >• o
J TO 01 £

in
a UH

o c •
£ JJ-H ~
Cu tn M tn
in 0 3 oi
C 6 TJ TJ
£ O
a-u JJ in
01 O -H
TJ E c a
c — oi
TO in
TJ OJ 3
TO IH E O
•rt TO 'rt rH
C TJ *" ""
0 C rl
JTO 0) 0)
JJ£ >
in JJ O




c
TO
O
-H
UH
•H
C
Cn flt
•H Cf
cn c
re
O £
Z U
TJ
i tn 01
tn 3 jj jj cn
O u TO c oi
Cu O rH 0) cn
— £ O E u
CL--H 4J TO
TJ CO > TO £
CO 01 U
TO £ in ^ in
aTJ -u -t
TO L< TJ
•rl — . TO O
C >.TJ JJ JJ
O -H C C
JX) TO 01 TO
•H JJ 3 rH
cn in TJ QJ
1 U C
t TJ cn TO -H
C 0) HJ O TJ H
TO JJ C £ C 3
JJ TO Q) 1 Cu TO *UJ
cn rH E cn jj
O JJ -H •- in TJ 3
TO -ri TO TJ in 01 0
•H > 01 QJ {/! JJ rH
C rl JJ Cn 3 TO UH
E VH TO TO O O QJ
f- TO >irH £ £ -t >





TJ
c in
TO 3

TO 0
•H £ CO
C Q*rH
0 in o
| 0 >
< a. J










c
TO
U
•H
UH
• H
C
tn 01
-H cn
CO C
TO
£•£








^
c
a
u
•H
UH
•H
C
cn 01
tn c
TO
O £
Z o
I
IH
1 01 1
0 JJ C >
TJ CD TO O rH
IH 3 U 01
TO 01 JJ
TJ rl UH U 01
C -H 0 -H rH
TO JJ XI CL
JJ C £ 0 E •
U 01 JJ rl 0 TJ
Cn 01 U 0)
in IH C C JJ
•H 01 01 < in TO
O > -H C C
CO O-H
• rt Q) . -H E
rH JJ rH >, JJ -rf
rH Ql -rt TO -H rH
M E E 3TJ 0)
co m
TJ 1 C •
IH 4J C 0 TJ
3 TO C < -H QJ
O T) OJ JJ >
•H C U — 1 OJ
01 TO M • TJ -rl
XI JJ 01 >i C rH
n a TO o oi
tn 3 a w
rH in O IH
0) -H r- oi o >.
> O JJ -H rH
01 C C" TO XI JJ
-H -H C 3 O TO
rH O HO)
O rH rH UH QJ IH
Q tH TO O TO Cn
O 1 0 C 1
rH C CO < -H
4) 10 TJ
J3 JJ Cn C JJ
in c UH • o in 01 •
in ooinu-rtcntn
rH in rH >, X IH CJ
01— ITOJJ(COQ1TO£
> O C 3 -rl rH 0
oiccnaiLiXiin jj
§rHTOO)TOO!-H>jJ
MTJCL3TOJJOin





_
TJ D TO
QJ v IH
> JJ
rH C Crl
O 0) 01 in
in cn u c
cn >, c O
•rl X O -H
Q O U JJ


1
£ in
cn 01
0) -rl -rt
OJ b, TJ JJ
3 C -H
TO >

QJ JJ • JJ
JJ 01 Cn U
TO E C TO
3 -H
cn jj 01 TJ
in TJ Q c oi
•rt IH O -H JJ
o ra xi -H jj
C TJ 0) -H
•H C -US
rH ro cn O -i
rH JJ C £ 01
M CO -n to a


01
Cn

TO

O
jj
C
TO
U
•H
UH
•rl
C
cn
•H
CO

o
2




JJ
C
TO
0
•H
UH
C
Cn Q)

cn c
ro
O £
Z U




jj
C
TO
U
H
UH

C
Cn QJ
in c
TO
O £
Z U
u in
CJ in cn >i
4J TJ C TO
TO IH O 3
3 TO -1 IH
TJ TO 01
cn c JJ
•H TO JJ TO
O JJ OJ 3
C CO E
•rl TO
rH 01 JJ 01
rH 0) O ^
M 3 C TO






tn
01 01
M in

TO
3 rl
0 QJ
rH JJ
rH TO
< 2
01
>
a

in
01
c
•H
TO
CL

in
01
a

0)
£
jj

tn
c
o
rH
ro
>,
JJ
•rt

TO
3
tT


01
JJ
TO
3

UH
0

in
c
0

JJ
TO

3
E
• H
CO

IH
QJ
jj
3
a
E
o
u
in
3
0
£
a
in
o

a
TJ
c
TO

C
OJ
tT
O
IH
JJ
•rl
C

£

'S

TJ
Q)
E
3
in
in
TO


01

41
rH


IH
TO
-H
JJ
IH
51
JJ

0
JJ

Cn
C
•H
•D
TO

Cn
a
D





















in
c
o
Jj
•H
TJ
C
o
u

3

rH
UH

rl
41

JJ
TO
0)



^
TJ


O


TJ
01
JJ
TO
3

TO

U











cn
c
o
•rt
JJ
•H
TJ
C
o
u

3
0
UH

^J
QJ
£
JJ
TO
01




TJ

UH
O

in
c
o
•rt
JJ
TO
rH
3
E
• r!
cn

rl
01
JJ
3
a
E
o
u
                                        -XXXll-

-------
          The conveyance tunnels will pass through
          several active faults prevalent in the TARP
          project area and will be sensitive to earth
          movement at these locations.  Information on
          the distribution and nature of the active
          faults is insufficient  to assess accurately
          the extent of damage which could result from
          an MMI VIIIearthquake.

     Further information on this subject may be found
in Sections 2.2.3, 2.2.4, and 8.2.2 of the EIS.
(3)   Effects of Rock Spoil Generated During Construction

     THE ROCK SPOIL MATERIAL GENERATED DURING TUNNEL
     CONSTRUCTION IS NOT EXPECTED TO BE MARKETABLE.
     THEREFORE, ENVIRONMENTAL IMPACTS ASSOCIATED WITH
     DISPOSAL OF THE ROCK SPOIL WILL DEPEND LARGELY ON
     THE AVAILABILITY OF LANDFILL DISPOSAL SITES.

     Approximately  4,563,000 cubic yards  (bulk measure)
of spoil will  be removed  from the Calumet Tunnel seg-
ments and branches.  Although this amount can be ade-
quately contained within  Thornton Quarry, the large
quantities of  spoil involved in reservoir excavation
could complicate disposal plans for tunnel spoil.  Dis-
posal of rock  spoil from  the reservoirs was addressed
briefly in Section  6.2.4  of the EIS.  A significant
portion of rock spoil generated by reservoir construc-
tion is likely to be marketable and to be stockpiled
on the quarry  site  for eventual sale by the quarry
owners.

     Major findings supporting the above conclusions
are:

          Shale and other constituents present in the
          rock excavated from the Phase I tunnels will
          limit the rock's suitability for low-grade
          commercial uses.

          Landfill disposal sites capable of accepting
          the entire volume of tunnel spoil to be gener-
          ated during TARP Phase I have not yet been
          identified by the MSDGC.
                     -xxxxii-

-------
          Thornton Quarry has enough volume to accept
          the entire quantity of spoil to be excavated
          from the Calumet Tunnel segments and branches,

          Since conventional methods will be used to
          excavate rock from Thornton Quarry for reser-
          voir construction, it is likely that a sig-
          nificant portion of the spoil will be market-
          able.  Present plans envision stockpiling the
          saleable portion on the quarry sites for
          eventual sale by the quarry owners.  Various
          stockpile configurations are being considered,
          Nonsaleable spoil can be stockpiled on-site,
          as is proposed for the Thornton Quarry site,
          or at a site located south of Lake Calumet
          and owned by the MSDGC.

     A more detailed discussion is provided in Section
6.2.4 of the EIS.
(4)  General Effects of Construction

     CONSTRUCTION OF THE TARP TUNNEL SYSTEMS WILL
     RESULT IN TEMPORARY PUBLIC ANNOYANCE AND INCON-
     VENIENCE FROM THE CUMULATIVE EFFECTS OF NOISE,
     HANDLING OF CONSTRUCTION DEBRIS, VIBRATION
     FROM BLASTING, DISRUPTION OF VEHICULAR AND
     PEDESTRIAN TRAFFIC, AND GLARE FROM THE ILLUM-
     INATION OF CONSTRUCTION AREAS AT NIGHT.  AL-
     THOUGH THE CUMULATIVE EFFECTS MAY BE NOTICE-
     ABLE,  TAKEN SINGLY, EACH EFFECT IS MINOR.

     This conclusion is supported by the following find-
ings:

          Surface construction sites are located in
          areas which are generally either vacant or
          near low-utilized industrial land.

          Noise at each construction site should be
          within levels mandated by Chicago ordinances
          and, at each surface construction site, noise
          will only occur for periods of three to nine
          months.
                      - XXXIV-

-------
           Because blasting  will  be used only to excavate
           shafts and not  the  tunnel,  itself,  blasts will
           be relatively infrequent and will continue at
           any one site for  not more than 120 days.

      Further information  on this subject may be found
 in Sections 6.3.1,  6.3.2, 7.1.1, 7.2.1, 7.4,  and 10.2.
 (5)   Effects of Infiltration and  Exfiltration

      IF THE GROUTING PROGRAM IS NOT EFFECTIVE,1
      GROUNDWATER INFILTRATION DURING CONSTRUCTION
      AND WASTEWATER EXFILTRATION  DURING TUNNEL
      OPERATION CAN BE A SIGNIFICANT PROBLEM.

      This conclusion is supported by the following
 findings:

           The inflow rate of groundwater for  the TARP
           tunnel systems is estimated to be an average
           of approximately 0.5 MGD per mile of tunnel.
           In the absence of appropriate mitigative mea-
           sures, this rate is sufficient to lower the
           piezometric or hydraulic pressure level of
           the upper aquifer.  Tunnel grouting is the
           most effective method to reduce infiltration
           and a grouting program  has been incorporated
           in TARP.  Grouting integrity, however, must
           be maintained to keep inflows below the allow-
           able limit of 500 gallons per day per inch of
           tunnel diameter per mile of tunnel.  Obser-
           vation wells will be required to monitor
           integrity throughout the operational phase
           of the tunnel.

           Exfiltration will most  likely occur when tun-
           nel pressures exceed inflow pressures during
           high storm runoff conditions.  The TARP grout-
           ing program is expected to prevent extensive
The objective of grouting is to achieve maximum penetration and a
uniform grout spread.   If grouting is ineffective, maximum infil-
tration/exfiltration flows will result.
                        -XXXV-

-------
           exfiltration of tunnel wastewaters into the
           upper aquifer.  However, if grouting integri-
           ty is not maintained during tunnel operation,
           exfiltration will be at a high enough rate to
           degrade groundwater quality of the upper
           aquifer.  Observation wells  will be neces-
           sary to determine whether exfiltration is
           occurring along the tunnel routes.

     EIS Sections 2.1.2,  6.1.2,  and 8.1.2 provide more
information on the subject of groundwater infiltration
and wastewater exfiltration.   Specifications for obser-
vation well spacing and for the monitoring program are
also presented in these sections.
 (6)   Worker Safety During Construction

 TUNNEL OR UNDERGROUND CONSTRUCTION WORKERS WILL BE
 MORE SUSCEPTIBLE TO INJURY, DISABILITY, AND FATALITY
 THAN SURFACE CONSTRUCTION WORKERS.  THE INCIDENCE OF
 INJURIES AND FATALITIES, HOWEVER, IS NOT EXPECTED TO
 BE GREATER THAN NORMAL FOR THIS TYPE OF CONSTRUCTION
 WORK.

      This conclusion is supported by the following
 findings:

           Based on recent national statistics  for all
           types of construction activities,  the Calumet
           Tunnel system construction may result in 90
           disabling injuries  and in  one permanent dis-
           ability  or fatality.   For  construction of
           the entire tunnel system,  injuries and fata-
           lities are expected to increase proportion-
           ately.

           Based on the  safety statistics of  the current
           construction  of a rapid-transit system subway
           in  Washington,  D.C.,  construction  of the en-
           tire TARP tunnel  system could result in 1,525
           injuries and  in nine  fatalities.

           Analysis of the geologic and  seismic charac-
           teristics of  the  project area indicates  that
           most of  the area  is stable and suitable  for
                     -XXXVI-

-------
          the construction of underground tunnels.
          Precautionary measures will be required to
          protect workers in segments where rockfall  and
          partings  (loosened material) may occur frequently
          and shale deterioration conditions prevail.

     Further information on this subject may be found
in Sections 6.2.2 and  7.1.2.
(7)  Effects of Operation on Land Use

     THE QUALITY OF LAND IN CERTAIN RIVERBANK SECTIONS
     ALONG THE CALUMET TUNNEL ROUTE MAY BE ENHANCED  BY
     REDUCED FLOODING CONDITIONS.

     Vacant land exists in the flood-prone areas  asso-
ciated with the Calumet Tunnel system.  The reduction
of flooding in these areas may enable development of
this under-utilized land into open space uses such as:
parks, playgrounds, sport fields, and parking areas.
(8)  Effects of Construction on Employment

     CONSTRUCTION OF THE CALUMET TUNNEL"WILL PROVIDE
     OVER $89 MILLION IN CONSTRUCTION INCOME OVER AN
     EIGHT-YEAR PERIOD AND WILL CREATE A PEAK  SUPPLY
     OF APPROXIMATELY 680 JOBS OVER A THREE-YEAR PERIOD.

     Further information may be found in Section 7.1.3.
 (9)  Funding Uncertainty  for  TARP

     THE CONVEYANCE TUNNELS CAN  BE  FINANCED BETWEEN
     1976-1987 .WITH MODEST INCREASES  IN  ANTICIPATED
     FEDERAL AND LOCAL FUNDING.  HOWEVER,  THE FUNDING
     OF THE RESERVOIR DURING  THIS TIME PERIOD IS NOT
     A PART OF THE CURRENT FINANCING  PLAN  AND COULD
     NOT BE ACCOMPLISHED  WITHOUT HAVING  A  MAJOR FINAN-
     CIAL IMPACT ON THE STATE, CITY,  OR  MSDGC.

     Additional details on this  finding  may be found
 in  Section 3.3.1 of the EIS.
                     -XXXVll-

-------
(10)  Effects of Flooding on Lake Michigan

     THE FLOODING PROBLEM EXISTING IN THE CHICAGO  AREA
     WILL NOT BE RESOLVED BY THE PHASE  I TUNNELS.   OVER-
     FLOW TO LAKE MICHIGAN WILL STILL PERSIST  IF THE
     PROPOSED RESERVOIRS ARE NOT IMPLEMENTED.
                    -xxxviii-

-------
                CONCLUSIONS AND RECOMMENDATIONS
     The following is a summary of the principle conclusions
of the Draft EIS, as well as recommended and suggested  miti-
gative measures.

     1.  Implementation of the Calumet Tunnel system will
significantly reduce the pollutant load in the Chicago  water-
ways.  These loadings will be reduced further with  the  imple-
mentation of the Mainstream and Lower Des Plaines Tunnel  systems
Water quality will be enhanced further with the upgrading  of
MSDGC's treatment facilities and the construction of the  flood
control aspects of the Tunnel and Reservoir Plan.

     2.  Significant earthquake events could adversely  affect
tunnel alignment and tunnel lining.   Smaller earth  movements
could also affect the lining and grouting of the tunnels.  It
is, therefore, essential that MSDGC's inspection and main-
tenance program be extensive enough to insure efficient
operation of the system.
                                                     •
     3.  The rock spoil excavated from the Phase I  tunnels is
not expected to be marketable.  Evaluation of various disposal
alternatives leads to the conclusion that adequate  environ-
mentally acceptable landfill sites are available to handle
the volume of rock which will be generated by the Phase I
tunnels under consideration.  We will rely on existing  local,
state, and Federal regulations to insure that disposal  takes
place in an acceptable manner.  Additionally the MSDGC  will
be required to inform USEPA of their spoil disposal program
as it is developed through discussion with the Contractor.
This will be a condition of any grant awarded to the MSDGC
for the Calumet Tunnel System.

     4.  Although an effective grouting program is  proposed,
it must be sufficiently flexible to respond to the  actual
conditions encountered during construction.  Should the
grouting not be sufficient, additional infiltration could
adversely affect the hydraulic pressure of the upper aquifer.
Additionally, under surcharged conditions, exfiltration
will occur, resulting in adverse impacts on the groundwater
quality of the upper aquifer. Observation wells to  monitor
grouting integrity during operation are necessary along
the entire tunnel alignment. If pollutants are detected
in the observation wells, additional mitigative measures
must be implemented to protect the upper aquifer, including
a groundwater recharge system. Chapter X discusses  particular
aspects of the monitoring program, which will be developed
in conjunction with the MSDGC, IEPA and USEPA. This monitoring
program will also be a grant condition.
                            xxxix

-------
     5.  Since the majority of the construction shafts and
drop shafts are in close proximity to area waterways,  runoff
from these sites could adversely affect water quality. Berms
will be constructed around stockpiles of construction  materials
and spoil materials to preclude runoff into the waterways.

     6.  It is presently proposed that water pumped from the
tunnels during construction be discharged directly to  the
waterways after a period of settling.  Since the possibility
of silt and other pollutants still exists after settling, it
is recommended that these dewatering flows be discharged to
MSDGC's intercepting system for treatment, except during
periods of combined sewer overflows.  This will be a condition
of any grant awarded for the Calumet Tunnel System.

     7.  Although no known historic, architectural,  or arch-
aeological resources will be affected by the proposed  project,
the possibility of finding archaeological resources must be
investigated by the MSDGC.  This must be accomplished  by
contacting the State Historic Preservation Officer.

     8.  Conformance with applicable regulation of the Occupa-
tional Health and Safety Administration, U.S. Department of
Labor, and the Bureau of Mines, U.S. Department of the Interior
is essential for safety of construction workers.

     9.  There exists a wide range of potential adverse impacts
which could develop during construction.  This includes blasting,
waste spillage, traffic congestion, light glare, and fugitive
dust at construction and disposal sites.  While these  effects
could be considered insignificant any measures taken to reduce
their impact would aid in public acceptability of the  project.
These suggested mitigative measures are discussed in Chapter X.
                            xxxx

-------