Storm and Combined Sewer Demonstration Projects

                  January  1970
          William A.  Rosenkranz,  Chief
Storm and Combined Sewer Pollution Control Branch
   Division of Applied Science  and Technology
       Office of Research  and Development
 Federal Water Pollution Control Administration
         U.S. Department of  the Interior
                Washington,  D.C.

-------
                             CONTENTS
SECTION

   1

   2

   3
      TITLE                         PAGE

Introduction	.. „..   1

Completed Report Abstracts	  19

Information Sheets—Active Projects..  33

  a.  1102--Combined Sewer Overflows.  33

  b.  1103--Storm Water Discharges...  9?

  c.  110U--Non-Sewered Runoff	„.. 101

  d.  1503--Control of Pollution from
            Construction	 103

Pertinent Areas.. „	 105

Urban Drainage, Research, and Develop-
ment, FWPCA	 113

-------
                             SECTION 1
                           INTRODUCTION
Program Background

A brief outline of the background relating to the authorization and
implementation of the current storm and combined sewer pollution
control program of the Federal Water Pollution Control Administration
is desirable to orient the reader to the need for research and
development activities in this difficult technical area.

In 196^ the U.S. Public Health Service studied the combined sewer
problem and published a report, "Pollutional Effects of Stormwater
and Overflows from Combined Sewer Systems - A Preliminary- Appraisal".
This report concluded that pollution stemming from combined sewer
overflows is a significant part of the total water pollution problem
and that the cost of separating sanitary sewage from stormwaters
would cost nationally about $30 billion.  The report also recommended
that alternative solutions be investigated to determine if means of
control other than sewer separation could be found for application at
lower cost.

The American Public Works Association Research Foundation conducted
a stody of combined sewer problems in 196? by contract for the Federal
Water Pollution Control Administration.  Its report,w"Problems of
Combined Sewer Facilities and Overflows - 1967", submitted to FWPCA
in December 1967 indicates that separating the Nation's combined sewers
would cost about $^-8 billion, including the necessary plumbing changes
on private property.

The report also contains several additional findings that help in
describing the type and magnitude of combined sewer problems.  Some
of the more significant are:

    1.  There are an estimated 1,329 jurisdictions in the United
        States with a population of 5^- million served in whole or
        in part by combined sewers.  The sewer systems of an estimated
        36 million persons are wholly the combined sewer type.

        The association further estimated that the use of alternative
        corrective measures could reduce the cost of control or
        treatment to $15 billion.
                                 1

-------
    2.  The area served by combined sewers in the 6hl jurisdictions
        surveyed by AFWA is 2,557,000 acres.

    3.  In the jurisdictions surveyed, the population served by
        separate sanitary sewers is approximately one-half that
        served by combined sewers - 15,^25,000 and 3*1,080,000,
        respectively.

    k.  Of the 6^1 jurisdictions surveyed, ^93 reported 9,860 combined
        sewer overflows.   Sanitary sewer pumping station overflows,
        treatment plant by-passes and other overflow sources bring
        the grand total of reported overflows to lU,212.

    5.  Jurisdictions surveyed reported the existence of 10,025
        regulators at combined sewer overflow structures.  The
        most commonly reported types were perpendicular weirs and
        others of nonmecheni^al type.  Least commonly used are
        mechanical types.

    6.  Cost of regulator maintenance varied widely, but averaged
        $52? per regulator per year.   Twenty-two percent of the
        jurisdictions interviewed reported no regular inspection of
        regulators.

    7.  Fifty-three percent of the jurisdictions reported infiltration
        problems during wet weather.

    8.  Ninety-six jurisdictions reported combined sewer overflows
        during dry weather.

        These are but a few of the survey's 29 itemized findings.
        Examination of those 29 listings can only lead to the con-
        clusion that the discharge of untreated sewage from combined
        sewers--even during dry weather--is a significant factor in
        the total pollution picture.  Improved techniques for dealing
        with the problem must be diligently sought.
The Demonstration Program

The Water Quality Act of 1965, now a part of the Federal Water
Pollution Control Act, authorized the Secretary of the Interior "...to
make grants to any State, municipality or intermunicipal or interstate
agency for the purpose of assisting in the development of any project
which will demonstrate a new or improved method of controlling the
discharge into any waters of untreated to inadequately treated sewage
or other waste from sewers which carry stormwater or both stormwater
and sewage or other wastes...".  The act authorized grants up to
50 percent of the estimated eligible cost of the project up to $1 million.

-------
The Clean Water Restoration Act of 1966, also now a part of the
Federal Water Pollution Control Act, amended the original authorization
slightly so as to remove the $1 million ceiling and authorize the
demonstration grants to be made in amounts up to 75 percent rather
than the original 50 percent of the estimated project cost.  Contracts
can also be utilized to implement worthwhile projects.  Since it is
sometimes overlooked, it should be emphasized that projects not involving
combined sewage, but planned for the purpose of controlling pollution
resulting from stormwater discharges, are eligible for participation.

During the early stages of the program, which actually was implemented
early in 1966, it became apparent that early control and treatment
methods applied to limited extent in the United States and other countries
should be among the first to be explored, with the objective of incorporating
as many new techniques and applications as might be feasible.  There are
three basic approaches that can be utilized to solve combined sewage or
stormwater pollution problems: (l) control, (2) treatment, and (3) combina-
tions of the two.

Progress to date indicates that the development of a single control or
treatment method to solve combined sewer or stormwater pollution problems
is not likely.  Instead, those methods which are found to provide whole
or partial solutions under specific circumstances will have their place
in the planning of any combined sewer or stormwater project.

The methods to be utilized must be chosen only after the specifics of the
area in question are defined.  The sewer hydraulics, topography, land
use patterns, availability of construction sites, rainfall and runoff
characteristics, location of overflow points, capabilities of the municipal
sewage treatment facilities, water quality standards for the receiving
waters, and other factors must be thoroughly evaluated.

The Underlying Problem

Combined sewers have "build-in" inefficiencies.  They are designed to
carry only specific quantities of stormwater, in addition to sewage.
Such a system, therefore, of necessity incorporates planned (and unplanned)
overflow points to relieve it of excess flows when runoff exceeds system
design.  These overflow points include trunk sewer regulators, pump
stations, siphons, relief sewers, and wastewater treatment plant bypasses.

Untreated sewage discharged from combined sewers and from overloaded,
nominally separate, sanitary sewers has proved to be a substantial
pollution source in terms of its effects on water quality in the receiving
stream—even though the percentage of total flow lost from the system by
overflow may be small.  The flow characteristics of combined sewers are
relatively poor during dry weather when sanitary wastes alone are carried;

-------
certain of these wastes remain in the system until a rainstorm purges
the system.  As a result, a large pollution load, over and above that
normally carried, is discharged from  this  type of sewer.   Thus
research and development must correct this situation if we are to
avoid frequent treatment plant bypassing.

Consideration of the history and function of sewerage systems leads to
the immediate conclusion that control and/or treatment of combined
sewer overflows or stormwater discharges are directly related to the
system's  efficiency.  Overflows would not occur if the system were
completely effective as a transport media.  Federal research and
development to resolve the storm and combined sewer problem, therefore,
has as its main thrust, the development and demonstration of techniques
and hardware which will improve system efficiency and minimize, if not
completely control, untreated discharges from the system.
Development of Ideas and Application of New Or Improved Methods

Some of the approaches that have been or could be considered as parts
of the solution to the problem are worthy of discussion.  They can be
considered under the three basic categories mentioned, the first being
control methods.

     Control related to the physical aspects of routing, diversion and
containment of either stormwater or combined sewage.   Within this broad
area are:

     Reduction and regulation of stormwater input to sewers, utilizing
short-term surface or underground storage, land treatment measures,
irrigation or percolation to groundwater, treatment and injection to
groundwater, infiltration control, elimination of illicit sewer connections,
and the use of special conveyance systems such as presure or vacuum
sewers for the purpose of separating sanitary sewage from stormwater.
Brief descriptions of one or two projects that fall within the control
category will serve to illustrate approaches now being implemented.

     The City of Chicago's Lawrence Avenue underflow sewer system now
under construction will demonstrate and evaluate the feasibility of
utilizing large-diameter tunnels for temporary storage of combined
sewage during storm periods.  About 3-1^ miles of 12-foot tunnel and
1.76 miles of 17-foot tunnel will be used.  Combined sewage will be
lifted from storage after the storm and discharged to the North Side
Treatment Works for treatment.

     The Minneapolis-St. Paul Sanitary District, Detroit, and Seattle
are installing systems for maximizing control within the sewerage systems
to eliminate as much overflow from the systems as possible.  Regulators
are being redesigned, rebuilt or replaced; overflow points monitored

-------
with data transmitted to central logging points, and remote control
of regulators installed.  Based on conditions within the critical points
of the system, positive control of overflows can be effected.  Sub-
stantial computer capability is an integral and key factor in the workability
of this approach in.large metropolitan areas.

     Treatment includes all potential methods of treating combined
sewage or stormwater.  Physical, chemical and bio'logical methods are
being evaluated as a part of the Program.  Physical treatment includes
screening and straining, filtration, sedimentation, and hydraulic solids
separation.  Chemical treatment methods might include chemical oxidation,
use of polymers to improve sedimentation rates, and new or improved
disinfection techniques or methods.

     A project being conducted by the Dow Chemical Company for the
Federal Water Pollution Control Administration is an example of chemical
treatment.  Polymers are being screened and evaluated toward improving
the effectiveness of sedimentation as a solids removal method utilizing
short detention periods.  The Dow Chemical people will also attempt to
optimize high-rate sedimentation tank design by comparison of tank
configurations and other design aspects.

     Allis Chalmers has developed a new biological treatment method
which may have promise for use with combined sewage.  The system is
termed the BIO-DISC system.  A series of disks mounted on individually
powered shafts are rotated through the waste to be treated.  Biological
growth attaches to the disks, which can be rotated from 15 to 30
revolutions per minute.  Under steady loading rates, efficiencies ex-
ceeding those of trickling filters have been obtained.  Testing the
system under the loads peculiar to combined sewers is being undertaken.

     Biological treatment methods are, of course, difficult to apply to
combined sewer overflow because of the variable waste constitutent
concentrations and the extreme variability in flows.  Biological systems
function best under conditions as close to "steady-state" as possible,
which is almost impossible to achieve during storm periods.

     Combinations of control and treatment should be discussed since no
one method is likely to provide "the answer" to combined sewer or stormwater
pollution problems.  Any combination of the methods mentioned—or others —
has the potential for solving a given pollution situation.  Some combinations
might be:  in-system or off-system storage for subsequent treatment in
specially designed facilities (physical, chemical or biological), temporary
or short-term storage of collected stormwater, followed by treatment and
utilization for groundwater recharge, and retention of minor storm flows
with pumpback to the collection system.

-------
     The Metropolitan District Commission (Boston) demonstration grant
project utilizes a facility providing a minimum sedimentation period
of 10 minutes  with an influent flow rate of 233 MGD.   Chlorinated
effluent will be discharged through a 96 inch outfall to the Charles
River.  Solids removed in the sedimentation tank will be returned to
the sewerage system for transport to the sewage treatment plant.

     Somersworth, New Hampshire is implementing a project similar in
basic concept to the Metropolitan District Commission project, but of
different design.  This project will also evaluate the use of polymers
to increase the carrying capacity of the main interceptor.  This  feature
may be of some interest as a new concept.  Prior work done by the
Western Company of Richardson, Texas under contract to FWPCA (°)  indicates
that high molecular weight polymers can increase the flow in a sewer to
as much as 2.^ times the flow without polymer addition--at a constant .,
head.  This phenomenon is being investigated further and will be  subjected
to additional evaluation at Somersworth and at Dallas, Texas.

     Mt. Clemens, Michigan is proceeding with a project which will utilize
a combination of control and treatment techniques.  Combined sewage will
be discharged into three small lakes or "lakelets".  The lakelets will
operate in series and will be aerated with surface aerators.  Effluent
from the first two ponds will pass through microstrainers.  The effluent
from the third pond will be chlorinated after microstraining and discharged
to the Clinton River.  The potential of the lakelets for recreational uses
such as boating and fishing will be explored as a part of park operation.

     Many other techniques or methods are being evaluated in active
projects.  Use of stabilization ponds, various treatment tank designs,
reduction of infiltration, improved overflow regulators, high rate
trickling filters, filtration, pressure sewer systems, sewer flushing,
dissolved air flotation, ultrasonic filtration, several screening techniques
and other technologies are being applied and evaluated.

Other Areas of Need

There are many other areas which need thorough exploration by means of
active demonstration and evaluation.  Some of these are discussed below
to illustrate the broad scope of interest involved in the program.

     INFILTRATION

     Research is also underway to  find new and improved sewer sealants
for infiltration control.  Many of the problems associated with existing
sealants, such as shrinkage upon drying, or structural weakness probably
can be overcome by using modified polymeric and other plastic materials.
Methods of application in both new construction and repair work are also
being considered.  Control of infiltration could substantially reduce dry
weather flows in many cases, thereby eliminating, or at least delaying,
the need for increased capacity.
                                  6

-------
     A definite need exists to establish guidelines for infiltration
control, including allowable volumes, types of sealants and application
methods, construction materials and procedures, etc.  Such guidelines
would serve to upgrade the quality of original construction and help
in judging the need for corrective action in existing sewers.

     Building connections to street sewers are a major source of
infiltration.  Municipal officials and firms specializing in sewer
sealing say that as much as 70-80 percent of the infiltration load
occurs in these lines.  The Federal Water Pollution Control Administration
is, therefore, seeking practicable methods, to control this.

     ILLICIT CONNECTIONS

     It is well known that illicit connections can cause serious local
overload problems.  A recent municipal u) program demonstrated that,
when a community takes the time to program the removal of illicit connec-
tions, benefits are realized in reduced storm peak flows as well as
average flows.

     Through a concerted effort, utilizing a public relations campaign,
questionnaires, individual building inspections and a good follow-up
program the Springfield, Illinois Sanitary District was able to substan-
tially reduce the number of downspounts connected to its sewers.  In
combined sewer areas the reduction in connections was 88.1 percent.  In
areas having some separate and some combined sewers, a 90-^ percent
reduction was obtained.  An 89.5 percent reduction was achieved in areas
where sanitary and storm sewers were completely separated.  The real
significance, however, was in the reduced number of public complaints.

     Before the campaign the Springfield Sanitary District received as
many as 300 complaints of basement flooding in a single day.  After the
campaign, such complaints were virtually non-existent.  No such reduction
in complaints occurred in adjacent areas under jurisdiction of the City
of Springfield.

     The effort was also successful from a cost standpoint.  The Sanitary
District has conservatively estimated that the cost of removing the roof
leaders from the sewerage system will be returned in terms of reduced
operation and maintenance costs in 16 months.   While the campaign required
a substantial effort over a two-year period, its effectiveness is evident
in improved sewerage system efficiency.

     Other communities should eliminate illicit sanitary connections to
separate storm sewers since wastes from this source seldom receive treatment.
                                  7

-------
     FRICTION REDUCERS

     Local flooding and system bottlenecks are very obvious to the
public and troublesome to routine operation and maintenance.  If lack
of capacity is the problem, several solutions other than replacement or
relief sewers may be possible.  Recent research (°) has shown that
polymeric fluid friction reducers can increase the flow capacity of
pipes at constant head as much as 2.k times.  These results, obtained
in test-stand experiments, are now being tested under actual field
conditions.  A 2^--inch, constantly surcharged sewer in Dallas, Texas
is being used for this purpose.  If proved effective, many cities will
find this increased pipe-carrying capacity useful in their overloaded
sewers.  As with other methods, the economics will have to be evaluated
for specific projects.

     OVERFLOW REGULATORS
                           /o \
     Another major problem ^ ' in combined sewer operations is in the
area of overflow regulator devices.  A first step in improving the
functional efficiency of combined sewers should involve a vigorous and
active regulator maintenance program since malfunctioning devices are
frequently sources of trouble.
                            (g)
     For example, Cincinnati^' uses telemetered monitoring to/detect
unusual or improper overflows.  A more sophisticated approach ^ ' is taken
by the Minneapolis-St. Paul Sanitary District (MSSD) in its storm and
combined sewer demonstration grant project.  A computer-assisted regulator
control system affords positive control of the overflow structures.  Based
upon rainfall and wastewater level measurements, storm flows can be diverted
to the interceptor to most efficiently use the interceptor capacity.  MSSD
uses a helicopter for surveillance of overflow points after a rainfall.

     The Cities of Detroit and Seattle also are using Federal grants to
develop computer-assisted regulator control systems.

     New types of regulators promise increased efficiency in sewer systems.
As part of its demonstration project MSSD has gone to positive control
gates and inflated rubberized-fabric dams as regulator devices.

     Research is being pursued on a new type of overflow regulator that
uses fluidic technology.  It appears from other fluidic applications that
this principle can work effectively with regulators.  Again,no moving parts
or electrical components are required.  Improved regulator and control
capability, as well as reduced operation and maintenance costs, are anticipated.
The fluidic principle has also been successfully demonstrated in the control
and regulation of irrigation flows.

-------
     SEWER FLUSHING

     Until recently the quality of combined sewer overflows has bee.n
inadequately delineated.  Current studies appear to substantiate the
results of investigations (11,12,13,1*0  conducted during the last five
to ten years.  Still not firmly determined, however, are the specific
causes of the very wide fluctuations in overflow quality.  The "first
flush" phenomenon has not been observed with any degree of regularity;
perhaps we have not determined all of the factors involved.

     This phenomenon is the very high pollution load that occurs during
the initial stages of overflow.  The pollutional concentration subsequently
decreases as the storm continues, and finally reaches a steady level.
Several variables undoubtedly contribute to the character of the "first
flush".  Solids which have settled out during dry weather flows probably
are resuspended.

     In an attempt to confirm the cause of the "first flush" phenomenon,
work under a Federal Water Pollution Control Administration research
contract is now investigating the effects of programmed sewer flushing.
The effects of sewer flushing during dry weather periods, types of equip-
ment required, and the economics of this approach are being determined.

     SURFACE ENVmONMENTAL POLLUTION

     A second source of pollution load which may influence the "first    ,  .
flush" is "surface environmental pollution". The recently completed study^  '
by the American Public Works Association reveals that a considerable solids
and biochemical oxygen demand (BOD) load is present on the streets and
adjacent land areas.  Land use, air pollution, street sweeping schedules
and efficiency, and catch basin cleaning affect the quality of the surface
runoff.

     Improved and conscientious "housekeeping" would reduce street litter
and hence the stormwater pollution load.  Street litter has been estimated
to have a pollution potential equal to one percent of the raw sewage pollution
load.

     Materials flushed off city streets to catch basins pose another serious
problem.  Preliminary investigations indicate that catch basins contain a
strong waste which is displaced in a ratio of one-half the catch basin volume
for each equal volume of added surface runoff water.  The role of the catch
basin and its relative importance as a contributor of waste loads versus the
associated maintenance problems needs further investigation.

     STORAGE FACILITIES

     Obviously, over-all sewerage system efficiency is reduced when
combined sewer overflows occur.  Some ways to increase the collection system


                                  9

-------
efficiency have been discussed.  When overflows occur, what additional
methods can be used to reduce either or both the quanity and quality of
wastes lost, to further improve system efficiency?  A primary concern
is control of the total volume.  An obvious technique, in-system (15)
storage, can be utilized by taking advantage of excess capacity in the
trunk or the interceptor sewers.

     Holding tanks are frequently considered as a means of controlling
overflows.  These are used in Europe (l6,17,l8) and have been applied
to a limited extent in the United States.  Concrete and steel tanks are
commonly used for this type of facility.  Classic examples ^9) can be
found in Michigan's McComb and ¥ayne Counties north of Detroit.  The
stormwater tanks of Columbus, Ohio, constructed in 1932, perhaps the
first in the United States, have been recently modernized.  Assisted
by an FWPCA demonstration grant,  the City will, for the first time,
comprehensively evaluate its holding tanks to determine optimum operating
procedures and facility effectiveness.

     The City of Milwaukee has under construction a similar type of
facility designed to utilize a mathematical model to determine the over-all
size and projected efficiency.  This project will include a new sludge
removal technique (resuspension by agitators), and will evaluate in
detail the facility's effects on water quality in the receiving Milwaukee
River.

     Sewerage systems are generally gravity flow, utilizing lift stations
where necessary.  New type of systems are needed.  Vacuum and pressure
type systems may prove technically and economically attractive and should
therefore be considered when seeking answers to specific sewage treatment
problems.  By reducing the amount of water used to convey the wastes and
by utilizing small transport conduits, added capacity and cost saving
in the existing system may be realized.

     TREATMENT FACILITIES

     Converse to the concept of storing and subsequently returning
wastewaters to a municipal treatment facility, is treatment at individual,
remotely located outfalls.  In considering these, it is important to
recognize that combined sewer overflows and stormwater discharges differ
in character from the sewage normally treated in sewage treatment plants.
In general, it can be assumed that dry-weather sewage flows approximate
steady-state conditions, while wet weather flows are completely random,
as evidence by the rainfall-runoff phenomenon.  Both the quality and
quantity of storm flows have extreme variations.  For example, the flows
are from 1 to 100 or more times greater than dry weather flows, and the
suspended solids content may range from 10 to 5,000 milligrams per liter
(mg/l).  Obviously any treatment facility must have special features to
handle the wide variations and unpredictables of stormwater flows.

     These same wide variations also affect storage facilities, though
here it is a matter of available space.  Economic considerations are just
as important as technical feasibility for any corrective measure since
the former is the ultimate factor in the planning and decision-making
processes.
                                  10

-------
                           (23)
     The treatment methods      under investigation include:

     1.  Microstraining
     2.  Dissolved air flotation (total and partial)
     3.  Rotating biological contactor
     h.  High rate plastic trickling filters
     5.  Ultrasonic filtration
     6.  High rate sand filtration
     7.  Cyclones
     8.  Oxidants
     9-  Chlorination and ozonization
    10.  Polymer additives
     Results to date indicate that a combination of both storage
and treatment will most likely be required in many combined sewer
systems, based upon the characteristics of the sewerage system, its
overflow location, the receiving body of water, available land, and
many other factors.

     MU1HCIPAL TREATMENT PLAITS

     Our discussion would not be complete without covering briefly
the effects of collection system efficiency on municipal wastewater
treatment plants.  With regard to problems associated with excess
storm flows, it would usually accomplish little to contain the flow
within the collection system and then bypass it at the treatment plant.
This merely moves the discharges and concentrates the effects in one
location.

     Consequently, it appears that auxiliary stormwater treatment units
will be required to maintain continuously high levels of treatment
efficiency.
     THE "PLACE" OF COMBINED SEWER AM) STORMWATER POLLUTION CONTROL
     THE TOTAL WATER POLLUTION CONTROL PICTURE

     The public is demanding that we, as a nation, preserve and protect
our environment.  Water pollution control has top priority in achieving
that end.  Nature does her part to assist man in maintaining desired
levels of water quality standards, as each body of water has a maximum
waste assimilative capacity.  For example, in the Delaware River and
Estuary, it has become necessary to assign waste load allocations to
each of the waste sources.  Based upon today's loads, the desired water
quality can be maintained by providing specified degrees of treatment.
                                  11

-------
     Even as the population grows and industry expands, the discharge
waste load must be maintained within the assimilative capacity of the
receiving waters.  As the waste loads increase, the "marginal" waste
loads or sources assume greater importance.   The combined sewer overflow
load may amount to 5 percent of the raw'load, but when you remove by
secondary treatment methods 85 percent of the raw waste load received
at the treatment plant, then the untreated combined sewer overflows
represent a load equivalent to 33 percent of the effluent load, or 25
percent of the total load discharged.  As more advanced treatment is
provided, the percent of total discharged waste load representing
untreated overflows can only increase, and we must not forget the many
other waste sources which are seldom considered in calculating the
magnitude of raw waste loadings.

     Problems associated with "marginal" pollution, such as uncontrolled
overflows, must be recognized now and planning initiated to improve
sewerage system efficiencies so as to bring wastewater flows under control.
Municipal programs with this objective cannot begin too soon because
corrective action is time-consuming.  Effort devoted to improving sewerage
systems will pay dividends in complete control of metropolitan wastewater
problems and pollution abatement.

     Research and development currently undertaken cooperatively by
Federal, State and local entities, including industry, will assist in
finding the more efficient and less costly control and treatment methods
needed to restore and maintain our water resources for maximum usefulness
to man.

     The tables and figures which follow illustrate the extent and
impact of the combined sewer overflow problem from a national standpoint.
                                  12

-------
                               REFERENCES


 (l)  Federal Water' Pollution Control Act,  as  amended by  the Federal
        Water Pollution Control Act Amendments of 1961  -  (PL&7-88), the
        Water Quality Act of 1965  - (PL89-23^),  and  the Clean Water
        Restoration Act of 1966 -  (PL89-753).

 (2)  Federal Water Pollution Control Administration.  Pertinent Areas for
        Research and Development,  Storm and Combined Sewer Pollution Control,
        July 1968.

 (3)  Federal Water Pollution Control Administration.  Storm and Combined
        Sewer Pollution Control Projects, March 1, 1968.

 (U)  Federal Water Pollution Control Administration, Division  of Engineering
        Development.  Research and Development Programs,  August 1, 1968.

 (5)  American Public Works Association -Research Foundation.   Problems of
        Combined Sewer Facilities  and Overflows  - 19&7-   Contract report for the
        Federal Water Pollution Control Administration, December 1, 1967.

 (6)  Overfield, J.K., Baxter,  J.K.,  Crawford,  H.R., Santry, I.W., Increasing
        Sewage Flow Velocity by Using Chemical Additives, July  1968, presented
        at WPCF Annual Conference,  Chicago, Illinois, September 22-27, 1968.

 (7)  Peters, Gerald L. and Troemper, A.P., Reduction of  Hydraulic Sewer
        Loadings by Downspout Removal,  Presented at  the Annual  Meeting of the
        Central States Water Pollution Control Association, St. Paul,
        Minnesota,  June 12,  1968.

 (8)  American Public Works Association-Research Foundation.  The Causes
        and Remedies of Water Pollution from Surface Drainage of Urban Areas,
        Contract Report for the Federal Water  Pollution Control Administration,
        June 28, 1968.

 (9)  Caster, A.C., Monitoring Stormwater Overflows, Journal Water Pollution
        Control Federation,  Volume 37,  No.  9,  September 1969.

(10)  Real-Time Computer Control of Urban Runoff, James J. Anderson, presented
        at ASCE Hydraulics Division Conference,  August 23, 1968.

(ll)  Burn, R.J. and Vaughn,  R.D.,  Bacteriological Comparisons  Between Combined
        and Separate Sewer Discharges in Southeastern Michigan, Journal Water
        Pollution Control Federaltion,  Vol. 38,  No.  3, March 1966.

(12)  Burn, R.J., Krawczyk, D.F.,  and Harlow,  G.L., Chemical and Physical
        Comparison  of Combined  and  Separate Sewer Discharges, Journal Water
        Pollution Control Federation, Vol.  Uo, No. 1, January 1968.
                                  13

-------
(13)  Weibel,  S.R.,  Anderson, R.J.,  and Woodward, R.L., Urban Land Runoff
        as a Factor  in Stream Pollution, Journal Water Pollution Control
        Federation,  Vol.  36, No.  7,  July 1964.

(lU)  Benzie,  W.J. and Courchaine, R.J., Discharges from Separate Storm
        Sewers and Combined Sewers,  Journal Water Pollution Control Federation,
        Vol. 38,  No. 3, March 1966.

(15)  Weller,  L.W.,  and Nelson,  M.K.,  Diversion and Treatment of Extraneous
        Flows  in Sanitary Sewers, Journal  Water Pollution  Control Federation,
        Vol. 37,  No. 3, March  1965.

(l6)  Institution of Civil Engineers,  Symposium on Storm Sewage Overflows.
        Advance papers, May 4,  1967.

(17)  Ministry of Housing and  Local  Government, Technical  Committee on Storm
        Overflows and the Disposal of  Storm Sewage -  Interim Report.  Her
        Majesty's Stationery Office, 1963.

(l8)  Cohrs, Albert.  Storm Water Tanks  in the  Combined Sewerage System in
        Berlin.  Gus and Wasserfach, Vol.  103,  No. 36, September 7, 1962.

(19)  Hubbell, George E.   Effect of  Storage and Skimming on Combined Sewage
        Overflows.   Presented  at the 39"th  Annual Conference of the Water
        Pollution Control Federation.   September 25-30, 1966.

(20)  Devenis, K.P., Charles A.  Maguire  Associates, Boston University Bridge
        Storm Water  Detention  and Chlorination  Station.  Presented at New
        England Water Pollution  Control Association,  Spring Meeting, June 11,
        1968.

(21)  Anon., Tunnels Will Store  Storm  Runoff, Engineering  News Record,
        November 30, 1967-

(22)  Pikarsky, Milton, and Keifer,  Clint, Underflow  Sewers for Chicago,
        Civil Engineering - ASCE, May  1967.

(23)  Report on Improvements to  the  Boston Main Drainage System, Camp Dresser
        and McKee,  Consulting  Engineers, September 1967.

      Rosenkranz, William A.,  Developments in Storm and Combined Sewer
        Pollution Control.  Presented  at New  England  Water Pollution Control
        Association Spring Meeting,  June 11,

-------
                  TABLE I. —ESTIMATED COST OF COMBINED SEWER SEPARATION*
STATE
Alabama
Alaska
Arizona
Arkansas
California
Colorado
Connecticut
Delaware
District of Columbia
Florida
Georgia
Hawaii
Idaho
Illinois
Indiana
Iowa
Kansas
Kentucky
Louisiana
Maine
Maryland
Massachusetts
Michigan
Minnesota
Mississippi
Missouri
Montana
Nebraska
Nevada
New Hampshire
Now Jersey
New Mexico
Now York
North Carolina
North Dakota
Ohio
Oklahoma
Oregon
Pennsylvania
Rhode Island
South Carolina
South Dakota
Tennessee
Texas
Utah
Vermont
Virginia
Washington
West Virginia
Wisconsin
Wyoming
Complnte
Separation of
Combined Sowers
(Public)
e
8,350,000
25,700,000
712,000,000
35,400,000
373,000,000
81,300,000
334,000,000
3,720,000
317,000,000
15,750,000
4,270,000,000
1,710,000,000
326,000,000
109,500,000
490,000,000
243,000,000
19,500,000
1,425,000,000
2,430,000,000
423,000,000
1,335,000
972,000,000
20,950,000
263,000,000
33,000,000
196,000,000
990,000,000
7,100,000,000
6,320,000
64,300,000
2,410,000,000
372,000,000
2,300,000,000
231,000,000
16,600,000
173,000,000
69,000,000
116,500,000
228,000,000
610,000,000
280,000,000
585,000,000
1,420,000
Plumbing Changes
to Affected
Buildings
_
3,950,000
23,300,000
547,000,000
17,000,000
146,000,000
52,600,000
119,000,000
1,490,000
191,900,000
300,000
2,420,000,000
872,400,000
188,800,000
46,000,000
264,390,000
116,500,000
4,520,000
926,330,000
1,548,500,000
189,600,000
52,000
605,000,000
7,450,000
96,700,000
6,770,000
106,450,000
753,500,000
4,366,000,000
1,360,000
17,400,000
1,532,800,000
219,000,000
1,396,500,000
204,700,000
8,240,000
111,700,000
42,800,000
28,220,000
128,400,000
478,000,000
179,080,000
408,000,000
557,000
Total
Separation
*
T 12,300,000
49,000,000
1,259,000,000
52,400,000
519,000,000
133,900,000
453,000,000
5,210,000
508,900,000
16,050,000
6,690,000,000
2,582,400,000
514,800,000
155,500,000
754,390,000
359,500,000
24,020,000
2,351,330,000
3,978,500,000
612,600,000
1,387,000
1,577,000,000
28,400,000
359,700,000
39,770,000
302,450,000
1,743,500,000
.11,466,000,000
7,680,000
81,700,000
3,942,800,000
591,000,000
3,696,500,000
435,700,000
24,840,000
284,700,000
111,800,000
144,720,000
356,400,000
1,088,000,000
459,080,000
993,000,000
1,977,000
                              $30,391,645,000       *18,378,259,000
          Note: (—) Indicates no evidence available that combined sewers are used in state.
                                                               $48,769,904,000
*From the American Public Works  Association Research Foundation Report,
"Problems of  Combined  Sewer  Facilities and Overflows -  1967".

-------
       FIG.  I.  COMPARISON OF  METHODS OF CONTROL AND/OR
       TREATMENT OF COMBINED SEWER OVERFLOWS: NUMBER OF
       JURISDICTIONS REPORTED USING, PLANNINGCONSTRUCTION
       AND BELIEVING METHODS APPLICABLE. *
       Disinfection Sedimentation In-system
                         Storage
Automated Sewer Separa
Regulator    tion
      the American Public Works Association Research Foundation Report,

"Problems of Combined Sower Facilities and Overflows - 196?".
                                  16

-------
FIG.IE. RELATIVE USE OF COMBINED SEWERS COMPARED TO
TOTAL SEWERED POPULATION^ BY STATES
                                          Ratio projected population1
                                          sewered by combined sewer
                                          to total sewered population
                                                              51-75%
                                                              Over
 (1) Source—Statistical Summary 1962 Inventory, Municipal Wastes Facilities in the United
 States
                            17

-------
          F1GJII RELATIVE COST OF COMPLETE SEWER SEPARATION
          BY STATES.*
                                               Key:
                                               Estimated State Cost
                                               0-$10,000,000

                                               to $500,000,000
                                               to $1,000,000,000 '/////////////
*Fron the American Public Works  Association Research Foundation Report,

"Problems of  Combined Sewer Facilities and Overflows - 196?".
                                   18

-------
                                       SECTION 2
                          COMPLETED PROJECT REPORT ABSTRACTS
CONTRACT OR
GRANT NO.

  lU-12-23
  lA-12-46?


  .T.14--12-27
  114-12-20


  29-IDA-2


  111 _12-314-
CONTRACTOR OR
GRANTEE	

Acoustica
Associates
  llj-12-214-     Alii s-Chalmers
  ll4—12-65     American Public
               Works Association
  114-12-19     FMC Corporation
  114--12-17     FRAM Corporation
The Franklin
Research Institute

Havens and Emerson
  lU-12-39     Hercules, Inc.
Hittman Associates
Meridian, Idaho
The Western Co.
               The Western Co.
TITLE OF FINAL REPORT

"Demonstrate Feasibility of
 the Use of Ultrasonic Fil-
 tration in Treating the
 Overflows from Combined and/or
 Storm Sewers", September 1967

"Municipal Sewage Treatment
 with a Rotating Biological
 Contactor", May 1969

"Problems of Combined Sewer
 Facilities and Overflows--
 1967", December 1967

"Phase I—Feasibility of a
 Periodic Flushing System
 for Combined Sewer Cleaning",
 August 1967
                      Strainer/Filter Treatment of
                      Combined £
                      July 1969
                                     Combined Sewer Overflows",
REPORT NO.
(If Any)
"Selected Urban Storm Water
 Runoff Abstracts", June 1969

"Feasibility of a Stabilization-
 Retention Basin in Lake Erie at
 Cleveland, Ohio", May .1968

"Crazed Resin Filtration of
 Combined Sewer Overflows",
 October 1968

"The Beneficial Use of Storm
 Water", August 1968

"Sewer Infiltration Reduction
 by Zone Pumping", June 1969

"Polymers for Sewer Flow Control",
 August 1969
                                                          WP-20-11
                                     WP-20-16
  WP-20-21
                                                          DAST-U
  DAST-9
  WP-20-22
                     "Improved Sealants for Infiltration  WP-20-18
                      Control", June 1969
                                            19

-------
CONTRACT OR    CONTRACTOR                                                REPORT NO.
GRANT NO.      OR GRANTEE           TITLE OF FINAL REPORT                (if Any)

  lU-12-14-86    Bowles Engineering   "Design of a Combined Sewer          DAST-13
               Corporation           Fluidic Regulator",  October
                                     1969

  lU-12-29     American Society of  "Combined Sewer Separation           ORD-U
               Civil Engineers       Using Pressure Sewers",  October
                                     1969
                                            20

-------
              A.  PPB 1102 - COMBINED SEWER Discharges


DEMONSTRATE FEASIBILITY OF THE USE OF ULTRASONIC FILTRATION IN
TREATING THE OVERFLOWS FROM COMBINED AND/OR STORM SEWERS

     Acoustica Associates, Incorporated
     Contract Number lU-12-23, September 1967

The feasibility of employing ultrasonic filtration for treating
overflows from combined and/or storm sewers has been demonstrated
in a three-month laboratory test program.  This new technique
involves the use of permanent-type low-head filter elements which
are mounted within canisters into which ultrasonic energy is
applied on a programmed basis.  The beneficial effect of the
ultrasonic energy is manifested in three significant ways:
(l) the total quantity of influent filtered between backwash
cycles increased by factors of from four to 18 times; (2) length
of filter runs between required backwashing was extended from
four to ten times; and (3) 'ultrasonic energy used during back-
washing can restore the filter elements to "like-new" condition
without necessitating frequent filter replacements or maintenance
work of any kind.
Reductions in BOD and suspended solids averaging between 40% and
70% were obtained in a selected number of tests with raw sewage
diluted in varying degree with water using 20 and 50 micron ele-
ments at filtration rates approximating 10 gpm/sq. ft. and at
a head loss of from 1 to U psi.  Based upon the tests conducted
with simulated "combined" sewage, it is concluded that the
ultrasonic filtration system is technically and economically
feasible for full-scale waste water treatment use.
MIMICIPAL SEWAGE TREATMENT WITH A ROTATING BIOLOGICAL CONTACTOR

     Aliis-Chalmers
     Contract Number lU-12-2^, May 1969

A Rotating Biological Contactor (RBC) was installed at the Milwaukee
Metropolitan Sewerage Commission treatment plant at Jones Island to
demonstrate the feasibility of treating municipal waste with an
RBC system.

The RBC system effectively treated domestic sewage at high loading
rates.  Ninety percent COD removal was attained at a loading of
350 to UOO pounds of COD per day per thousand cubic feet of disc
volume.  Pounds of COD removed increased with pounds of COD applied.
Efficiency of treatment improved with increased retention time.
Percent BOD removal was approximately five percent greater than
percent COD removal.  Lower disc speed resulted in a slightly
lower efficiency.  Lower strength wastes are not as efficiently
treated as higher strength wastes at the same organic loading.
Recovery from high hydraulic loading is rapid.

                                 21

-------
This report was submitted in fulfillment of Contract 1U-12-2U
Modification 2 between the Federal Water Pollution Control
Administration and Aliis-Chalmers Manufacturing Company.
PROBLEM? OF COMBINED SEWER FACILITIES AMD OVERFLOWS -- 1967

     American Public Works Association
     WP-20-11, December ±967

The effects and means of correcting combined sewer overflows and
separate storm and sanitary sewer discharges were inventoried on
a national basis in 196? and compiled in this report.   On-site
personal interviews with the public officials of approximately
900 communities in the United States collected over 250,000
pieces of data which have been analysed and grouped by State,
river basin, and population group to define the problems of com-
bined sewer facilities and overflows.  Nationwide projections
were made for major items of interest including, area and popu-
lation served by combined sewers, overflow locations,  type and
number of regulators, associated land and water uses,  estimates
of costs for sewer separation by States, alternate control and/
or treatment methods and consideration of other aspects of the
overall problem.  Findings, Conclusions and Recommendations
are presented in summary form.

This report was submitted in fulfillment of Contract Wo. 1^-12-65
between the Federal Water Pollution Control Administration and
the American Public Works Association -- Research Foundation.
PHASE I—FEASIBILITY OF A PERIODIC FLUSHING SYSTEM FOR COMBINED
SEWER CLEANING

     FMC Corporation
     Contract No. lU-12-19, August 196?

Published literature has shown that one of the causes of pollution
from stormwater overflow of combined sewers is the deposition of
pollutional solids during dry weather flow followed by pick up
of the pollutional material during storm flow when the flow must
be bypassed.  As a solution to this problem it has been proposed
that a flushing system be used to periodically cleanse the sewers
during dry weather and convey the solids to the treatment plant.

This is a final report of the work done by FMC Corporation, Central
Engineering Laboratories under a six month contract, Contract lU-12-19,
from the Federal Water Pollution Control Administration to study
the Feasibility of a Periodic Flushing System for Combined Sewer
Cleansing.
                                 22

-------
Under this Phase 1 contract a study was made of sewer flushing
practices, application requirements and hydraulic theory, an
investigation was made of sampling methods and equipment, and
flushing test equipment was designed for use in Phase II and
the cost of Phase II was estimated.

In the course of the various background studies it was confirmed
that additional detailed information is needed in order to apply
a periodic flushing system to actual combined sewers.  It was
also concluded that the existing information on sewer flushing
indicated a good possibility that a periodic flushing system
would be feasible for reducing pollution from combined sewer
stormwater overflow.

The detailed information needed to apply a sewer flushing system
must be determined by a large number of controlled experiments
of flushing effectiveness.

The design of flushing evaluation equipment for use in Phase II
has been carried to the point that cost estimates can be made for
construction of the equipment.  A description of the design and
the cost estimates are included in this report.

It is recommended that this program be continued into Phase II
in order to determine the effectiveness of flushing under various
conditions.  The work in Phase II should also include the integration
of the test results into a design procedure, the design and develop-
ment of flush station equipment and control systems, the selection
and approval of a demonstration location for Phase II, and the
preliminary design and cost estimation for the Phase III demonstration.
STRAINER/FILTER TREATMENT OF COMBINED SEWER OVERFLOWS

     Fram Corporation
     WP-20-16, July 1969

The primary objective of this feasibility study was to evaluate
the principle of a 'self-cleaning strainer, self-cleaning filter'
concept for the treatment of combined sewer overflows.  The antici-
pated goal was to design and construct a prototype system capable
of handling up to 1000 gallons per minute with a B.O.D.  reduction
near 60 percent, and with the capability of automatic operation in
remote locations.

A combined sewer overflow in Providence, Rhode Island, was sampled
and analyzed to determine the type and amount of contaminant dis-
charged into the receiving stream.  The average concentration was
determined to be nearly equal to pure domestic sewage.  It was
also determined that the analysis reported for overflows is very
dependent on the exact sampling method used.   Automatic sampling
                                23

-------
devices utilizing small diameter tubing do not take a representative
sample since the suspended solids distribution is not uniform over
the cross-sectional area of the discharging stream.  Based on over-
flow sample analysis data (samples taken manually), a synthetic
substrate solution was prepared to evaluate a forced flow self-
cleaning strainer for significant operating variables.

The strainer and filter systems were evaluated using the synthetic
substrate, primary influent to two separate municipal treatment
plants, fresh sewage solids and actual combined sewer flow.  It
was demonstrated that the strainer model produced consistent sus-
pended solids removal rates near 35 percent under highly varying
load conditions, at a flux of 25 gallons per minute per square
foot.

The diatomite study showed operational success could be achieved at
a 50 percent organic reduction rate at U gallons per minute per
square foot of area, but at a minimum estimated operating cost
of $1.50 per 1000 gallons.

This report was submitted in fulfillment of Contract lU-12-17
between the Federal Water Pollution Control Administration and
the Fram Corporation.
SELECTED URBAN STORM WATER RIMOFF ABSTRACTS

     The Franklin Research Institute
     WP-20-21, June 1969

Selected Urban Storm Water Runoff Abstracts is a compilation of
abstracts summarizing articles from a variety of technical publi-
cations, covering the subjects of urban runoff, storm water
discharge, storm sewers, and combined sewers--together constituting
"the problem of urban drainage".  Articles on more general subjects,
such as "sewerage" or "sanitary engineering", and topics not closely
related to storm water, such as "agricultural runoff", have been
excluded.

The present work represents an effort to index, expand and update
the annotated bibliography, Storm Water Runoff from Urban Areas,
issued in April 1966 by the Cincinnati Water Research Laboratory
of the Federal Water Pollution Control Administration.  Among
the 573 abstracts presented are 386 not previously included, which
summarize articles dated both earlier and later than 1966, so that
the present compilation represents as complete a bibliographic
record as possible of storm water articles, up to--and to some
extent including--1968.  The 187 abstracts from the 1966 edition
were indexed, but not otherwise edited or re-evaluated.  For
convenience, the abstracts are classed in eleven sub-topic
categories, and arranged by abstract number within each category.

-------
Since most of the papers fit into more than one category, the
cumulative subject index at the end of the volume provides the
necessary access to individual concepts by referring to each
pertinent abstract number.  Each item includes a bibliographic
citation, an abstract, and a set of indexing descriptors (subject
terms listed in the Water Resources Thesaurus, November 1966
edition) and identifiers(newly suggested subject terms).  The
most important index terms are marked by an asterisk.   The format
of abstract presentation follows the one used by the Department
of the Interior's Water Resources Scientific Information Center
for its periodical, Selected Water Resources Abstracts.

This report was submitted in fulfillment of Contract lU-12-467
between the Federal Water Pollution Control Administration and
The Franklin Research Institute.
FEASIBILITY OF A STABILIZATION-RETENTION BASIN IN LAKE ERIE AT
CLEVELAND, OHIO

     Havens and Emerson
     Contract No. 1^-12-27, May 1968

A feasibility study was conducted of a large stabilization-
retention basin to be constructed in Lake Erie at Cleveland,
Ohio.  The stabilization is viewed as a possible alternative to
separation of a combined sewer system.  The proposed basin would
treat flows from a number of large combined sewer overflows,
from several polluted streams, and effluent from a large secondary
wastewater treatment plant.  Treatment would consist of bio-
oxidation, sedimentation, stabilization and disinfection.   A
shoreline collection system is included to convey flows to the
basin.

The chemical, biological, physical and structural aspects  of
the proposed basin were studied, and the probable benefits to
water quality and the effectiveness of the basin as a treatment
device were evaluated.   Estimates of cost of the basin and
collection system were prepared, and it was concluded that the
stabilization basin would provide a higher degree of pollution
abatement than would separation of sanitary and storm sewers,
at about one-third the cost.
CRAZED RESIN FILTRATION OF COMBINED SEWER OVERFLOWS

     Hercules, Incorporated
     DAST-U, October 1968

The feasibility of developing a self-cleaning,  self-adjusting
filtering device constructed of cylindrical structure of fibers

-------
laid down in predetermined patterns by a winding process and bonded
in place by resins was investigated.  The permeability of the
structure is imparted by a mechanical cracking or carzing of the
resin.  The tube would act as a normal pipe under open channel
flow.  Surcharging or pressurization to h psig would cause the
walls to become permeable.  Filtration runs indicated a 62.%
reduction of suspended solids in the filtrate.  However, sustained
runs could not be realized.  The self-cleaning aspect was not
demonstrated.  This report was submitted in fulfillment of
Contract No. 1^-12-39 between the Federal Water Pollution Control
Administration and Hercules Incorporated.
SEWER INFILTRATION REDUCTION BY ZONE PUMPING

     Meridian, Idaho
     DAST-9, June 1969

The intent of this project was to field demonstrate the reduction
of ground water infiltration into sanitary sewers by pumped draw
down of the water table in the sewer area assuming the geology
precipitation and local irrigation practices were amenable to
rapid and wide enough zones of influence.  It was demonstrated
that the water table was lowered and the volume of flow to the
treatment plant was reduced.  Previously, wet basements were
dried.  The water table was not lowered uniformly, nor were
the characteristics of the relevant geology as uniform as
expected.  For 1^0 square blocks, 70 pump units would be required
at an average cost of $UO,000 per unit and a total power bill
of $122.50 per day.  This is not economically favorable when
compared with other corrective measures available at this location.
This report was submitted in fulfillment of Grant Wo.  29-IDA-2
from the Federal Water Pollution Control Administration to the
City of Meridian, Idaho.
POLYMERS FOR SEWER FLOW CONTROL

     The Western Company
     WP-20-22

Six water-soluble polymers were investigated to determine their
effects upon aquatic flora and fauna, flow characteristics of
wastewater, and the operation of a wastewater treatment plant.

It was found that the polymers and gels, in the magnitudes tested,
were not toxic to bacteria, algae, or fish, and did not act as  a
nutrient for algae growth.

Based upon calculations obtained from flow test data, a maximum
flow increase of 2.*+ times the flow prior to injection could be
obtained if a constant head was maintained.  Laboratory flow test
data indicated that if flow rates were held almost constant prior
to and during polymer injection, a reduction in the static head
occurred as a result of friction reduction within the fluid.

                                 26

-------
The most effective polymers in providing energy reduction were
Polyox Coagulant-701, WSR-301, and AP-30; however, AP-30 required
higher polymer concentrations to obtain equivalent flow character-
istics.

In field tests on a 2^-inch diameter line, it was found that
polymer concentrations of between 35 and 100 mg/1, decreased
frictional flow resistance sufficiently to eliminate surcharges
of more than six feet.

Based upon an economic analysis, the average annual cost of new
construction was approximately five times the cost of using polymers
during peak storm-flow periods.

This report was submitted in fulfillment of Contract lU-12-3^ between
the Federal Water Pollution Control Administration and The Western
Company.
IMPROVED SEALANTS FOR INFILTRATION CONTROL

     The Western Company
     WP-20-18, June 1969

The objective of this program was to develop new, more effective
sealants for sewer line leaks (leaking joints, cracks and large
holes).  This purpose was achieved, and all equipments and
materials investigated, tested or compared are presented, along
with test results, supporting data, conclusions and recommendations.
A wide range of candidate materials was surveyed, and weaknesses
of rejected materials were noted.  Meanwhile, specific properties
of acceptable materials were ascertained and materials having
these properties were identified.  These latter materials were
subjected to tests designed to demonstrate their effectiveness
as sealants.  Cost/effectiveness of the new sealant materials was
compared with that of present sealant materials.  It was concluded
that infiltration adversely influences sewer system operating
costs and effectiveness, and that leakage repair systems are
limited in their effectiveness.   Several sealants developed
during the program were demonstrated to be able to effect strong,
permanent repairs.  Wo significant cost increase beyond that
experience with present sealers  was indicated.  Some present
sealant application equipment can be modified for use with the
new materials, but new equipment designs are described and
recommended.  Too, long-term field tests of the materials are
recommended.
This report was submitted in fulfillment of Contract lU-1
between the Federal Water Pollution Control Administration .and
The Western Company of North America.


                                 27

-------
DESIGN OF A COMBINED SEWER FLUIDIC REGULATOR

     Bowles Engineering Corporation
     DAST-13, October 1969

The objective of this program was to demonstrate feasibility,  and
to develop a workable configuration for a combined sewer Fluidic
regulator, whose purpose is to minimize combined sewer discharge
while protecting interceptor sewers from overloading during storm
flows.  A second objective was to develop design procedures and
criteria for the general application of this concept to municipal
sewer diversion requirements, including preliminary investigations
of construction methods, costs, and maintenance requirements.   A
third objective was to establish a plan and location for an
operational demonstration of the concept with a cooperating
municipality.

All objectives were successfully met.  A generic Fluidic Regulator
configuration was evolved which diverts 0 to 75^o of the combined
sewer flow away from the interceptor as a function of water level
sensed in the interceptor sewer, or combined sewer, in either  an
analog or digital operational mode.  Application design criteria
were evolved for a range of small to medium sized municipal sewers,
in terms of a few basic parameters.  Projected installation costs
are only slightly more than for conventional diversion structures;
while the anticipated construction and maintenance requirements
are simple and minimal.

The City of Philadelphia was established as the demonstration
site, and a demonstration unit should become operational in late
1970.  Recommendations were made for experimental activity to
improve regulation linearity; expand application size limit,
and to better definitize construction methods and costs.

This report was submitted in fulfillment of Contract 1^-12-^86,
between the Federal Water Pollution Control Administration and
the Bowles Engineering Corporation.
COMBINED SEWER SEPARATION USING PRESSURE SEWERS

     American Society of Civil Engineers
     ORD-4, October 1969

This report is concerned with the separation of community waste-
waters and runoff from rainfall and snowmelt in areas presently
served by combined and intercepting sewers.  Separation is
accomplished by withdrawing the wastewater fraction of flows from
existing plumbing systems and passing it through a sequence of
added systems components as follows:  (l) a storage, grinding and
pumping building; (2) pressure tubing fished from the unit through
each existing building sewer into the existing combined sewer;
and (3) pressure piping inserted in that sewer and extending to
the existing intercepting sewers that carry the wastewaters to
treatment and disposal works.  Runoff from rainfall and snowmelt,

                                 28

-------
thus unencumbered by wastewaters, is removed from the community
through the residual passageways of the one-time combined sewer
system, which has thus become a combination of a new pressure
conduit system within an old gravity conduit system.

The feasibility of this scheme of separation, the selection of
available systems components and the development of required new
systems components are described in this report on the basis of
information drawn from 25 project reports and technical memoranda.

The feasibility of storing, grinding and pumping sewage from
individual residences has been established; and standard commi-
nuting and pumping equipment will be satisfactory for serving
larger buildings.  Acceptable types of pressure tubing are
available that can be pushed and pulled through existing building
drains and sewers.  Pressure conduits can be suspended inside
combined sewers that can be entered by workmen.  There are
combined sewer areas that can be separated most effectively by
a version of the method investigated, but generally pressure
systems will cost more than new gravity systems.  New capabilities
developed appear to be of potentially greater use for applications
other than separation, such as new construction including utility
corridors, and introduce viable alternatives for design of waste-
water sewerage.

This report was submitted in fulfillment of Contract Number lA-12-29
between the Federal Water Pollution Control Administration, and the
American Society of Civil Engineers.
                                 29

-------
                B.  PPB 1102 - STORM WATEE RUNOFF
WATER POLLUTION ASPECTS OF URBAN RUMOFF

     American Public Works Association
     WP-20-15, January 1969

A study was conducted to determine the factors in the urban environ-
ment which contribute to the pollution of 'urban storm water runoff
and to determine methods to limit this source of water pollution.
It was found that street refuse--litter--could be a significant
factor when the nature of the shock discharge of the pollution is
considered.

An evaluation was made of the efficiency of street cleaning methods
and limitations of commonly used equipment explored.

Catch basins in conjunction with street inlets to the storm water
disposal system were also determined to be a potential major source
of pollution as large quantities of septic liquid are released
during periods of storm water runoff.

Other potential sources of pollution considered included air
pollution, roof discharges, and chemicals used in the urban environ-
ment.  Surveys were made to determine national patterns, a compre-
hensive set of "typical" ordinances governing a wide sampling of
possible sources of urban storm water runoff pollution were compiled
and are included in the report.

Findings and Recommendations are included in summary form.

This report is submitted in fulfillment of Contract WA-66-23
between the Federal Water Pollution Control Administration and
the American Public Works Association.
THE BENEFICIAL USE OF STORM WATER

     Hittman Associates
     Contract No. 1^-12-20, August 1968

This report contains a discussion of the work performed in the
analysis and optimization of the system; the conceptual designs
of potable, sub-potable, and pollution control systems; the con-
ceptual design of a system for controlling pollution using a
"conventional design" approach, the results of the system evalu-
ation and plans for the demonstration of the local storage, treatment,
and reuse of storm.  The appendices to this report include the
derivations of the hydrology equations, survey reports on water
usage and the public acceptance and legal aspects of reuse,
design reports on the "conventional" and demonstration system,
detailed estim tes on the cost of the demonstration program,
and descriptive information on packaged water treatment plants.

                                 30

-------
Storm water runoff from local areas is normally considered to be
a form of waste-water.  Use of storm water from surface water supplies
normally occurs only after the runoff has undergone natural treat-
ment processes and becomes a concentrated source.   In this report,
the local utilization of storm water runoff is referred to as "reuse"
based on the normal classification as wastewater and to distinguish
the type of usage from the normal use of surface water supplies.

This final report covers the work performed by Hittman Associates,
Incorporated, in cooperation with the Rouse Company and the "new
city" of Columbia, Maryland, on the collection, storage, treatment,
and reuse of storm water as a means of pollution control and water
supply augmentation.  This work was performed for the Federal Water
Pollution Control Administration, U.S. Department of the Interior,
under Contract lU-12-20.
                                 31

-------
                              SECTION 3

                 ACTIVE PROJECT INFORMATION SHEETS

                a. 1102 Combined Sewer Discharges
GRANTEE
Minneapolis-St.
Paul Sanitary
District, 11022 FAQ

Springfield Sani-
tary District,
3-ILL-l

Metropolitan Dis-
trict Commission,
Boston, Mass.,
11023 FAT

City of Detroit,
11022 FAX

City of Milwaukee,
11023 FAU
PROJECT OFFICER

Louis Breimhurst



Ralph Christensen



Allyn Richardson




Lawrence O'Leary


Clifford Risley
Sewerage and Water   George Putnicki
Board of New Orleans,
11023 FAS
City of Chippewa
Falls, Wisconsin,
11023 FIY
Louis Breimhurst
East Chicago Sani-   Clifford Risley
tary District, Ind.,
11023 FAV
METRO, Seattle,
Wash., 11022 ELK

City of Columbus,
Ohio, 11023 FAL
William Clothier
Robert Feder
City of Shelbyville, Ralph Christensen
111., 11023 FAM

Department of Public Albert Bromberg
Works, City of New
York, 25-NY-l
City of Chicago,
111., 11022 EMD
Clifford Risley


             33
PROJECT MANAGER
Darwin Wright
Darwin Wright
George Kirkpatrick
Darwin Wright


Darwin Wright


Francis Condon



Darwin Wright



Darwin Wright



George Kirkpatrick


Francis Condon


Darwin Wright


George Kirkpatrick



Francis Condon
PAGE

 38



 39



 in
 1*3

 hh
 50


 51


 52

-------
GRANTEE
New Providence,
N.J., 11023 FAN
City of Somersworth,
N.H. , 11023 FAP
City of New York,
N.Y., 11023 FAO
City of Mount
Clemens, Mich. ,
11023 FAR
City of Cleveland,
Ohio, 11023 EZW
City of Dallas,
PROJECT OFFICER
Albert Bromberg
Edward Struzeski
Thomas Murphy
Lawrence O'Leary
George Harlow
George Putnicki
PROJECT MANAGER
Darwin Wright
Francis Condon
Francis Condon
Francis Condon
William Rosenkranz
George Kirkpatrick
PAGE
53
58
62
6h
65
66
Texas, 11023 FAW

City and County
of San Francisco,
Calif., 11023 DXC

Board of County
Commissioners,
Montgomery Co.
Ohio, 11022 DHQ
                     William Bishop
                     Eugene Harris
                      Darwin Wright
                      Francis Condon
Merrimack College,   Warren Oldaker
1102U DOK

New York State       Richard Keppler
Department of Health,
Albany, N.Y.,
11022 DQI
City of Dallas,
Texas, 11022 DZU

City of Akron,
Ohio, 11022 DXH

University of
Cincinnati,
1102U DQU
George Putnicki


 George Harlow


Robert Feder
Lehigh University,   Richard Dewling
110214- EKD
                      Francis Condon
                      George Kirkpatrick
George Kirkpatrick
Francis Condon
Darwin Wright
                      George Kirkpatrick
                         75
                         87
                                                                    90
                         91

-------
GRANTEE
                     PROJECT OFFICER
                      PROJECT MANAGER
PAGE
City of Kenosha,
Wisconsin,
11023 EKC

Tulane University,
11022 DEI

City of Rohnert
Park, Calif.,
11023 DSX
CONTRACTOR

Rand Development
Corporation,
WA 67-2

Rhodes Corporation,
114-12-11

Dow Chemical Co.,
1^-12-9

Cornell, Howland,
Hayes, and Merry-
field, 114-12-121

Allis Chalmers,
                     Clifford Risley, Jr.  Francis Condon
George Putnicki


William Bishop



         CONTRACTS

PROJECT OFFICER

Robert Feder



George Putnicki


Ralph Christensen


William Clothier



Darwin Wright
                                           Francis Condon
                                           George Kirkpatrick
Rex Chainbelt, Inc., Clifford Risley, Jr.
1U-12-UO

Underwater Storage,  George Kirkpatrick
Inc., 114-12-139
                                           PROJECT MANAGER
                                           William Rosenkranz
                                           William Rosenkranz
                                           William A. Rosenkranz
                                           Francis Condon
                                           Darwin Wright
                                           Francis Condon
                                           George Kirkpatrick
Melpar, Inc.,
1^-12-133
                     George Kirkpatrick    George Kirkpatrick
Karl R. Rohrer       George Kirkpatrick
Assoc., ll4-12-ll4-3

Glenfield & Kennedy  Allyn Richardson
Inc., 114-12-136

Aerojet-General      John Merrell, Jr.
Corp., Il4-12-l80
                                           George Kirkpatrick


                                           Darwin Wright


                                           Darwin Wright
 93



 9k


 95
PAGE

 Uo
 55


 56


 57


 59

 60

 6l


 63


 67
                                  35

-------
CONTRACTOR
                     PROJECT OFFICER
PROJECT MANAGER
                        PAGE
American Process
Equipment Corp.,
3J4-12-195

Burgess & Niple,
lU- 12-401

Henningson, Durham
and Richardson,
114-12-1402

Aerojet-General
Corp., 114-12-197

Metcalf & Eddy,
Inc., 1^-12-14-07

Roy F. Weston,
114-12-403

Hayes, Seay,
Mat tern, &
Mattern, lU-12-200

American Public
Works Assoc.,
lU-12-14-56

Black, Crow &
Eidsness,
                     Darwin Wright
                     Alfred Smith
FMC Corporation,
1^-12-14-66

Ionics Inc.,
114-12-^90

Water Resources
Engineers, Inc.,
114-12-501
                     John Merrell, Jr.


                     William Bishop


                     H. R. Thacker


                     H. R. Thacker



                     Darwin Wright



                     Asa Foster



                     George Kirkpatrick


                     Allyaa Richardson


                     Darwin Wright
Metcalf & Eddy, Inc., Darwin Wright
114-12-502

University of        Darwin Wright
Florida, lU-12-503

American Standard,   Allyn Richardson
Inc., lk-IZ
Darwin Wright
Francis Condon
                     Ralph Christensen     Darwin Wright
George Kirkpatrick


George Kirkpatrick


Darwin Wright


Darwin Wright



Darwin Wright



Francis Condon



George Kirkpatrick


Darwin Wright


Darwin Wright



Darwin Wright


Darwin Wright


Allyn Richardson
                         70



                         71


                         72


                         73


                         76



                         77



                         78



                         79


                         81


                         82



                         83
                                                                     85
                                  36

-------
CONTRACTOR           PROJECT OFFICER       PROJECT MANAGER         PAGE

American Public      Darwin Wright         Darwin Wright            86
Works Assoc.,
114-12-550

Battelle Memorial    William Clothier      Francis Condon           92
Institute,
114-12-519

Roy F. Weston,       Darwin Wright         Darwin Wright            9^
1^-12-829
                                  37

-------
 INFORMATION  SHEET~~
           RESEARCH  & DEVELOPMENT GRANT
Tki& &he.et deAc/Ltfaea b^it^ty an R 6 V Giant auaaJided undeA. Sec.  6,
fede/uuL Mate*. Pollution. Control Ac-tlCdeon Wo£e* RutoxaUon Act) .
GRANTEE: Minneapolis-St.  Paul  Sanitary District,  St.  Paul, Minnesota
TITLE OF PROJECT;  "Dispatching  System for  Control  of Combined  Sewer  Losses"


PROJECT SITE: Minneapolis-St.  Paul,   PATE AWARPEP;  May  25,  1966
             Minnesota
FEDERAL GRANT;   $870,750              TOTAL  EST.  PROJ. COST;  $1,71*1,500

PROJECT NUMBER;  11022 FAQ           PPBS MO.  1102


PESCRIPTIOM OF PROJECT;  Dispatching  system for  control  of combined sewer
 losses.   The project includes preliminary  studies  to update historic data,
 a four phase construction project consisting  of installation of  a gauging
 system,  a data logger, five river monitors, telemetering rain  gages,
 regulator modifications,  and  a  post-construction program evaluation  to
 include  special studies  by the  University  of  Minnesota.  Existing regulators
 will be  replaced with modern  power operated gates  at 18 key diversion
 locations.   A  supervisory system will be provided  to telemeter gate  positions,
 flows and levels in sewers to be controlled by  the new  regulators.   This
 information will be transmitted to a central  point where a  dispatching
 operator can observe conditions and  regulate  flow  accordingly.   Maximum
 utilization of interceptor sewer capacity  would be assured  and overflow
 to the river will  be minimized.
 INQUIRIES:  Contact tht  Storm and Combined Sewer Pollution Control Branch
                        0^-cce 0(( ReaeotcJt and Pevelopneitt
                        fedviat (totte* Pottotton Con&tot Mmvti&&ui£Lon.
                        U.S. Pepo/idnen* otf the. Intvuon.
                        633 Indiana. Ave. M.W.
                        Wa&hington, P. C. 20242

                                  38

-------
 INFORMATION  SHEET
           RESEARCH & DEVELOPMENT  GRANT
Tku> 4fieet deAc/utbea bfu.t^ty an R £ P Gtiant awarded unde* Sec. 6,
        Wa*e/i Pot&ttuw Con&iol AcxtfCdean Wate* Re^o-tatum Act).
GRANTEE;  Springfield Sanitary District
TITLE OF PROJECT: "Evaluation of a Stabilization Pond for Treatment of
                   Combined Sewer Overflows"

PROJECT SITE: Springfield,  Illinois  PATE Atl/ARPEP;  June lk,  1966

FEDERAL GRANT; $86,570               TOTAL EST. PROJ. COST;  $199,1^0

PROJECT NUMBER; 3-ILL-l              PPBS HO.    1102


PESCRIPTION OF PROJECT;  The goal of this project is to determine the
 effectiveness of a stabilization pond as an overflow treatment device
 for combined sewage.   A twelve-acre stabilization pond will  receive the
 flow by-passed at an  existing pumping station during periods of precipi-
 tation.   This pond will intercept short duration, high intensity rainfalls,
 The system will provide both temporary storage and treatment of the over-
 flow.

 Evaluation of the facility will not only include routine sampling of
 influent and effluent, but will also include  biological sampling of the
 pond and the receiving stream.
INQUIRIES:  Contact, tht  Storm and Combined  Sewer  Pollution Control Branch
                        Fede/ia£ WcvteA Pottwtton Control
                        U.S. Vqpawtmtnt o£ the. Intvuoi
                        633 Indiana. Ave. N.OI.
                                    P. C. 20242
                                39

-------
 INFORMATION  SHEET—
        RESEARCH  & DEVELOPMENT  CONTRACT
Th.it> &he.nt duc.fu.bu bui^ty an R6V Contract auXLide.d undvi Sec. 6,
Ftdvial WateA Pollution Control Ac* {Clean WateA Re t -Ttion Ac*).
CON/TRACTOR; ^^^ Development Corporation
            Cleveland, Ohio
TITLE OF PROJECT: "Rapid Flow Combustible Filter"


PROJECT SITE:   Cleveland, Ohio

FEDERAL CONTRACT;  $1^,850            PATE AK/ARPEP:  August 8,  1966

PROJECT A/UMBER:  WA 67_2               PPBS AfO; jj.02
                  11023 DPI
PESCRIPTION OF PROJECT:

This project includes the design, construction, operation and evaluation
of a rapid flow combustible filter.  This filter, which will utilize
combustible materials — primarily coal, will be installed  at a  combined
sewer overflow in Cleveland, Ohio.  Overflowing waste will  percolate  through
a basket containing a relatively shallow bed of coal before discharge.
Removal of coarser materials by mechanical filtration is the anticipated
result.  Upon exhaustion of the filter, the coal-solids mixture  will  be
incinerated.
The investigators, in addition to designing and building the unit, will
develop design criteria for future, similar installations.  Evaluation  of
the process will include not only treatment efficiency, but also information
on operating costs and procedures.  Difficulties encountered in  incinerating
the coal after use will also be investigated.
INQUIRIES:  Contact the.
                        O^ice. OfJ ReAeaJich and Ve.velopme.nt
                        ftdeAol WateA Pollution Con&iol AdminiAtxation
                        U.S.  Ve.pantmejfit ojj the.
                        633 Indiana Avenue, N.W.
                        Wa&hington,  V.  C.  20242

G.\f:

-------
 INFORMATION  SHEET~~
           RESEARCH & DEVELOPMENT  GRANT
  i& &he.et ducAibtA bfu.^ly an R S P Gnant awarded ande*. Sec.  6,
federal WateA. Pollution Control Ae£(C£ean WateA Rea-to.'uttuM Act).
GRAAfTEE; Metropolitan District Commission
         20 Somerset Street
         Boston, Massachusetts

TITLE Of PROJECT; "Boston University Bridge Storm Water Detention and
                   Chlorination Station"

PROJECT SITE:  Cambridge, Mass.       PATE AWARPEP;  September 2, 1966

FEPERAL GRANT; $1,000,000            TOTAL EST. PROJ.  COST: $U, 3*^,650

PROJECT NUMBER;  11023 FAT            PPBS MO.   1102


PESCRIPTION OF PROJECT;

A detention basin will be constructed to intercept peak flows and to
chlorinate waste water, as a means of reducing combined sewage overflows
into the Charles River.

The project includes the construction and evaluation of a combined sewer
overflow facility, designed to provide a 10-minute minimum sedimentation-
detention time with an influent of 233 MGD.  The chlorinated effluent will
flow by gravity from the detention tanks through a 96 inch outfall pipe into
the Charles River.  Sludge deposits in the detention tanks will be returned
to the sewer system to be treated at the sewage treatment plant.  All settled
materials will be flushed out of the tanks and into the sewer system after
the storm subsides.
INQUIRIES;  Contact tht Storm and Combined Sewer Pollution  Control Branch
                        0^-tce 0(J ReJ&fidi and Development
                        federal Watesi. Pollution Control
                        U.S. Pepo/Ument orf the. Intvuon.
                        633 Indiana. Ave. N.W.
                        Utukington, V. C. 20242
GWerdig  10256?
                                  in

-------
 INFORMATION  SHEET~~
           RESEARCH  & DEVELOPMENT GRANT
Tki& 4/ieet deAvUbu fa/tte££y an R 6 V GMMt auwided andm Sec.  6,
federal. Ukttvi Pollution Control Act[Clean Watvt. Rtt>to>uvUon Act) .

GRANTEE:  City of Detroit,  Board of Water Commissioners
          735 Randolph Street,  Detroit,  Michigan


TITLE OF PROJECT;  "System Monitoring and Remote Control"


PROJECT SITE;  Detroit, Michigan     PATE AtMRPEP:   September 1^,  1966

FEPERAL GRAMT:  $1,000,000           TOTAL EST. PROJ.  COST:  $2,113,000

PROJECT MUMBER:  11022 FAX           PPBS HO.
DESCRIPTION Of PROJECT:  Reduction in stream pollution caused by combined
sewer overflows by installation of modern control equipment for sewage
flows thereby maximizing the use of storage within the existing sewer
system.  The project consists of installation of new power operated ^
diversionary overflow structures and automatic control instrumentation.
The instrumentation includes devices for determination of waste water
quality, flow measurement, rainfall data, conduit liquid level sensing,
and remote operation of diversion gates.  Telemetering will be provided
to transmit and record data collected by the instruments and to provide
feed back data relative to status of the remote controlled units.  Investi-
gations will be made to observe the modifications and additions to the system,
to analyze and evaluate the data collected, and to determine the overall
effectiveness of the demonstration.
INQUIRIES:  Contact the  Storm and Combined  Sewer Pollution Control Branch
                        0^-cce of, ReAeaAc.h and Development
                        federal blaten. Pollution Control
                        U.S. PeptfUment of, the
                        633 Indiana. Aue. N.lt).
                        Washington,  D. C. 20242

 GWerdig 1286?                    k2.

-------
  INFORMATION  SHEET--
            RESEARCH  & DEVELOPMENT  GRANT
      4fiee/t deAc/u.fae6 bfu.t,{,ty an R 6 V Giant awarded urtde/L Sec.  6,
         Wa-te/i Pottwtlon Control ActlCdain WateA Reito/uUxon Act).
 GRANTEE:  City of Milwaukee, 8^1 North Broadway, Milwaukee, Wisconsin  53202
 TITLE OF PROJECT: "Humbolt Avenue Overflow Detention and Chlorination Facility"


 PROJECT SITE;  Milwaukee, Wisconsin   PATE AO/ARPEP;   October 15, 1966

 FEPERAL GRANT:  $1,1*68,589           TOTAL EST.  PROJ.  COST; $2,368,118

 PROJECT NUMBER:  11023 FAU           PPBS HO.  H°2

 PESCRIPTION OF PROJECT:   The project will demonstrate the effectiveness of
a detention tank including chlorination facilities for the treatment of
combined sewer overflows from a 570 acre urban area.  The tank influent will
be screened.  The tank will be designed to provide a minimum of 15 minutes
detention time for sedimentation and chlorination.  After an overflow the
sludge deposits and remaining wastewater will be pumped to a nearby inter-
ceptor sewer for treatment at an existing treatment plant.

Because of the complex nature of the combined sewer system, eight in-system
monitoring stations will record flows and sample the overflows.

The overflows presently discharge to the Milwaukee River, seriously impairing
most beneficial water uses.  Three river monitoring stations will record the
dissolved oxygen and temperature, and provide for the collection of river
samples to determine the effects of the proposed project on the river water
quality.

All data will be analyzed to relate the effectiveness with  operation and
costs, inclusive of benefits received.  Results will be utilized to develop
a method for optimizing the design of such  facilities and establish relation-
ships to other  approaches for achieving comparable results.
 INQUIRIES:  Contact thf. Storm and Combined  Sewer Pollution Control Branch
                                 &  Rejeo/idi and Development
                                 UlatUi Pollution Conftot
                         U.S.  Pep&ttotent orf  the.
                         633 Indiana. Ave.. A/.bl.
                         Wa&hington,  V.  C. 20242

GWerdig  12?6?                     ,

-------
 INFORMATION  SHEET--
           RESEARCH  & DEVELOPMENT GRANT
Tkit> A/ieet ducfubu b^U^ly an. R 6 V Gfutnt auxuided undM. Sec.  6,
federal Wote/t Pollution Control Act(C£ean WoteA. ReAtcvuttton Act).

GRANTEE: Sewerage and Water Board of New Orleans, New Orleans,  Louisiana
TITLE OF PROJECT: "Chlorination and Hypochlorination of Polluted Storm
                  Water Pumpage"

PROJECT SITE: New Orleans, La.       PATE AWARPEP:December 2, 1966

FEDERAL GRAMT: $1,03^,250            TOTAL EST.  PROJ.  COST;$1,^9,OOP

PROJECT MUMBER: 11023 FAS            PPBS NO.  H02


PESCRIPTION OF PROJECT:

To control bacteriological pollution in Lake Pontchartrain the project
will demonstrate the effectiveness, efficiency, and economics of
using open drainage canals as treatment facilities; the effectiveness
of chlorine and hypochlorite disinfection on intermittent high flow
discharges; and the optimization of various feeding rates, multiple
points of application, and contact time.  Facilities for disinfection
will be placed and operated in the St. Charles Canal, the London Avenue
Canal and the Orleans Avenue Canal.  A sodium hypochlorite blending
plant will be constructed and a chlorine alarm system installed.  The
project will  include the provision of appropriate instrumentation for
the generation of quantitative and qualitative data necessary for a
comprehensive evaluation.
INQUIRIES:  Conta&t tkt Storm and Combined Sewer Pollution Control Branch
                        044
-------
 INFORMATION  SHEET ~~
           RESEARCH  & DEVELOPMENT GRANT
Tki& *hztt duuUbu bftit^ly an. R 6 V G^ant auwided undvi Sec.  6,
fed vial (fate* Pollution Control AetlCteon WateA RutotuttLon Act).

GRANTEE:  City of Chippewa Falls, Wisconsin
TITLE Of PROJECT: "Utilization of a Storage Pond with Treatment for
                   Combined Sewer Overflows"

PROJECT SITE: Chippewa Falls, Wis.   PATE AO/ARPEP;  December 23, 1966

FEDERAL GRANT;$289,685               TOTAL EST.  PROJ.  COST;  $773,98U

PROJECT NUMBER; 11023 FIY            PPBS NO.    1102


PESCRIPTION OF PROJECT;

Project includes construction of a combined storm water pumping station
and storage pond, increased interceptor pumping capacity, increased
interceptor pumping conduit, and final settling tank capacity, combined
relief sewer and some separation.  It will demonstrate the control and
elimination of stormwater by passes by diverting to a storage pond for
sedimentation with subsequent discharge to the waste water treatment
works for both primary and secondary treatment with chlorination.  The
design, operation procedures, and treatment efficiency will be evaluated.
Comparison with separation of storm and sanitary sewers will also be
evaluated.
INquiRIES;  Contact the.
                        0^>cce 0(J Rejea&cfo and Pevetopneitt
                        federal Watui Pollution Contol AcfoottA-futtum
                        U.S. Pepatdneat o£ the.
                        633 Indiana Ave. N.bl.
                        Washington,  P. C. 20242
GWerdig lU68

-------
 INFORMATION  SHEET~~
           RESEARCH  & DEVELOPMENT GRANT
Tki& thevt ducrUbu bUi^ty an R 6 V Giant auxvtded undesi Sec.  6,
        titotvi PoltuuUon Contiot Act(C£eon Watvi Rutoxation Act) .
GRAA/TEE:  East Chicago Sanitary District, East  Chicago, Indiana
TITLE Of PROJECT:  "East Chicago Treatment Lagoon"


PROJECT SITE:  East Chicago, Indiana PATE Aft/ARPEP:   December 23,  1966

FEPERAL GRANT:  $1,0^,120           TOTAL EST.  PROJ.  COST; $2,179,110

PROJECT NUMBER;  11023 FAV           PPBS NO.   1102


PESCRIPTION OF PROJECT:  Project will evaluate the  effectiveness  of
treating combined sewer overflows in a very deep detention basin  having
aerobic and anaerobic levels of treatment.  The aerobic treatment is
accomplished by large oxygen transfer units suspended on surface  of basin
waters.  The prime objective of the project is to demonstrate a control
method to optimize the quality of treatment to storm water and combined
sewage mixed with industrial waste water.  This treatment will render a
more acceptable discharge to the recieving waters.   The demonstration
will assess design criteria for detention basins to provide storage and
treatment to  storm water and combined sewer overflows; design requirements
for large oxygen transfer units in relation to volumes of waste water and
quality of effluent.
INQUIRIES:  Contact the.  Storm and Combined Sewer Pollution Control Branch
                        0^-tce o£ Reifcotdt and Development
                        Fedetol Mate* Pollution Con&iol \dntin4AtAatLon
                        U.S. Pepa/idnent ofi tkt Intvuon.
                        633 Indiana. Aue. N.ttl.
                        OJcukJjigton,  V. C. 20242

 GWerdig 1286?                    1^6

-------
 INFORMATION  SHEET—
        RESEARCH  ft  DEVELOPMENT  CONTRACT
Thit> &he.et deAc.ni.bu  bfu.e.^ly an RSP Contact awwided undet Sec.  6,
Fedetod WateA  Pollution Control Ac*  {Clean Wo£et  Re. t -ition Ac*).
CONTRACTOR;  Bhodes Corporation
             Oklahoma City, Okla.
TITLE OF PROJECT:  "Use of a New Technique for Waste Treatment"


PROJECT SITE:  Fort Smith, Arkansas

FEPERAL CONTRACT;  $317,733            PATE AO/ARPEP: December 28, 1966

PROJECT NUMBER;  iU-12-11              PPBS MO.-  1102

PESCRIPTION Of PROJECT:

This project includes the design,  construction,  operation and evaluation of
a prototype high capacity treatment  facility  designed  to handle  excessive
flows received at a treatment plant  during period  of storm runoff.   The
treatment  system to be investigated  consists  of  cyclones for removal of
coarse solids followed by a high rate  dissolved  air flotation system for
removal of finer solids.  Detention  in the flotation unit will "be less
than 10 minutes.
The demonstration unit will "be designed to handle  500,QOO  gallons  daily.
A portion  of the flow at a treatment plant receiving flow from a combined
sewerage system is to "be diverted  through the facility.   For purposes of
the demonstration, "both wet and dry  weather flow -will  be treated.  Discreet
data will  be kept for storm events.
In addition to treatment efficiency  of the facility and  its components,
the investigators will determine design criteria,  operating and  maintenance
problems and costs.  Recommendations will include  suggestions for use at
remote locations.
INQUIRIES:  Contact the. Storm and Combined Sewer Pollution Control Branch
                        0f5f5-i.ce 0($ Re4eo*.cA and Pevedopment
                        TzdeAat Watvi Poilution Con&iot
                        U.S.  Ve.pasutonent OfJ the.
                        633 Indiana Avenue,  N.W.
                        Washington,  P.  C.  20242

-------
 INFORMATION SHEET ~ ~
           RESEARCH &  DEVELOPMENT  GRANT
 TkiA 4/teet deAOUbe*  b^U^ly an R 6 V Giant awarded undvi Sec. 6,
         Watui Pott&tLon Control Act (Clean Mate* Re6£04atum Act).
 GRANTEE:   Municipality of Metropolitan Seattle
           ^4-00 West Harrison Street
           Seattle, Washington  98119

 TITLE OF  PROJECT; "Duwamish River— Elliott Bay Storm Water Control System"


 PROJECT SITE; Seattle, Washington    PATE AU/ARPEP;  December 29, 1966

 FEPERAL GRAAfT;  $1,1+00,000           TOTAL  EST.  PROJ. COST;  $3,891,900

 PROJECT MUMBER;  11022 ELK           PPBS HO.  1102


 PESCRIPTION OF PROJECT;

A sewerage System Control Scheme designed to regulate and program system
flows thru the use of overflow regulators operation-programmed by use of
computers.  Flows to the waste treatment facilities will be controlled to
improve efficiency of plant operation during rainfall periods and to
provide selective controlled discharging of storm-water overflow at
different points in a manner which will minimize the effect of waste
discharges in the receiving waters.  Automatic water quality monitors will
be utilized as control devices in tirggering discharges to surface water
from the regulator stations.  Functions of the system for controlling
pollution caused by storm water overloading of treatment facilities
and sewerage system overflows will be evaluated.
 INQUIRIES;  Contact tke. Storm and Combined Sewer Pollution Control Branch
                         046-cce o^ ReAeefidi and VeveJtopntnt
                         Fedetol WoteA Pollution. Con&tot
                         U.S. Pepo/itment orf the.
                         633 IncUana Ave. N.W.
                         dla&hington, V. C. 20242
GWerdig 10256?
                                    i+8

-------
 INFORMATION  SHEET~~



           RESEARCH & DEVELOPMENT  GRANT



Tfat& 4/ieCxt dt&csu.bu btu.t£ly an R 6 V Giant auxwded undeA Sec.  6,
fedvuit Watvi PottutLon Control Ac*(C£ean WcuteA ReAtoMuUon Act).

GRANTEE:  City of Columbus, Ohio



TITLE Of PROJECT:  "Modification of Whittier Street Storm Standby
                   Tanks"

PROJECT SITE; Columbus,  Ohio          PATE AOJARPEP;  March 30, 1967

FEPERAL GRANT: $300,000             TOTAL EST. PROJ.  COST;  $1,231,519

PROJECT MUMBER;  11023 FAL            PPBS MO.  1102


PESCRIPTIOM OF PROJECT;

 This project consists of an evaluation of the pollution reduction
 effectiveness of storm overflow tanks modernized "by installation
 of automated sluice gates and other equipment.

 Physical features of the project consist of the renovation of three
 existing combined sewer overflow tanks having a capacity of 1.3 fflg
 each.  The renovation includes automatic controls for the tank influent
 sluice-gates, new travelling bridge type sludge collectors and new
 pumps.  One objective of the automation is to keep sludge levels  low
 by continuously removing it from the tanks and thereby preventing
 anaerobic decomposition and its resultant odors.  Another objective
 is to control flows at the treatment plant "by proper use of the
 automatically operated sluice gates.  The improvements in tank
 efficiencies are expected to reduce bacterial contamination of the
 receiving stream, the Scioto River.

 Evaluation will include studies of the efficiency of the tanks as
 treatment units as well as studies of the effect of the system on
 the river.
INQUIRIES;  Contact the.
                        Of^-tce 0(( ReAeotdi and Pevelopneitt
                        Fedviat Watvi ?ottwtian Control
                        U.S. Vipcwtinejit o£ the. Inte/uo*
                        633 Indiana. Avt. N.W.
                        (i/aAfung&m, P. C. 20242

 GWerdig lU68

-------
 INFORMATION  SHEET--
           RESEARCH & DEVELOPMENT  GRANT
     4/ieet ducJLibeA bfUt^ty an R 6 V Giant auwided undeA Sec. 6,
federal. Mate*. Pollution Con&iol Ac£(Cdeon WateA Re*to>uition Act).

GRAA/TEE;   City of Shelbyville,  Illinois
TITLE Of PROJECT;   "Systems Approach to Combined Sewer Storm Water
                    Overflow Pollution Abatement"

PROJECT SITE: Shelbyville, Illinois  PATE AO/ARPEP; March  30,  196?

FEPERAL GRANT:   $HO,000            TOTAL EST. PROJ. COST; $2,295,077

PROJECT DUMBER; 11023 FAM            PPBS HO.  HO2


PESCRIPTION Of PROJECT:

 A demonstration of a systems approach to pollution abatement is the goal
 of this project.  The effectiveness of treating combined sewer overflows
 from gpi^n drainage areas in three types of detention and treatment units
 will "be evaluated.  These individual units will "be coordinated into a
 total control system for the community.

 Ifaits to be installed and evaluated under the grant include:

       (l)  A storm overflow lagoon, designed  for 5-day detention
            of a 10-year storm, foSULowed by primary and secondary
            stabilization lagoons will receive flow from  95#  of the
            drainage area.
            A storm overflow lagoon designed for 600# of  dry  weather flow.
            A-primary storm holding tank for 600$ of dry  weathe r flow for
            2-hr detention and equipped with a chlorinator, coraminutor
            solids collecting facilities and a lift  station to pump
            sludge to the treatment plant.
            Contact the.
                        0^-Lc.e. o£ Re^ea/idi arid Development
                        fed.uutt Watesi Pollution Control
                        U.S. Ve-pewtment o& the. Intesuox.
                        633 Indiana Ave.. A/.Ol.
                        Washington, V. C. 20242

-------
 INFORMATION SHEET ~ >-
           RESEARCH &  DEVELOPMENT  GRANT
JkiA Akeet dt&cAJUo&t, bfu.t^Lg an R & P Giant moulded unde* Sec. 6,
        Wote/i Pollution Contto£. ActlCdeon Wote* RfcA-to/uttton Act) .
GRANTEE:  City of New York, Department of Public Works
          Municipal Building
          New York, New York  10007

TITLE OF PROJECT: "Wards Island Water Pollution Control Plant Ponsar
                   Flow Regulating Siphon"

PROJECT SITE: New York City          PATE Aft/ARPEP:  March 30, 196?

FEPERAL GRANT:  $167,250             TOTAL EST. PROJ. COST; $223,000

PROJECT NUMBER: 25-NY-l              PPBS A/0.  1102


PESCRIPTION OF PROJECT;

A unique flow regulating device, called the Ponsar Regulator,  will be
installed and evaluated in the New York Sewerage System.   The function
of the regulator is to deliver a predetermined maximum volume of combined
sewage to the interceptor sewer from the drainage area collector system,
with the objective of evening-out the hydraulic load on the sewage
treatment plant for increased operating efficiency and to  decrease the
possibility that, during high flows, inadequately treated  sewage would
"overflow" the plant and discharge directly into streams.  The function
and capabilities of the device to contribute to improved sewerage  system
flow control will be evaluated.

The regulator operates on a siphon principle wherein the flow is pro-
portional to the sum of the hydrostatic and differential pressure  heads.
The device is constructed so that the total pressure difference will
remain constant after a predetermined hydrostatic head has been reached
and surpassed.

Also, an adjacent existing conventional regulator will be  monitored for
direct comparison of performance under similar conditions.
INQUIRIES:  Contact the. Storm and Combined Sewer Pollution Control Branch
                        OtfjJ-tce 0({ ReA&ficfo and Peve£0pnen£
                        Fede/utfc WateA. Pollution Control
                        U.S. Pepat&neat o& tke.
                        633 Indiana. Ave. N.U/.
                                    P. C. 20242
GWerdig 102567                    51

-------
 INFORMATION  SHEET~
           RESEARCH  & DEVELOPMENT GRANT
     Ahe.et dt&cjubu bUt^ly an R 6 V Quint auxuided undui Sec. 6,
feduial lilatvi Pottwtion Control Act (Clean WatM. Rutoiation Act).

GRANTEE:  City of Chicago, Department of  Public Works, Chicago,  Illinois
TITLE Of PROJECT:  "The Lawrence  Avenue Underflow Sewer  System"


PROJECT SITE;  Chicago, Illinois      PATE AWARPEP;   March 30, 196?

FEPERAL GRANT:  $1,500,000           TOTAL EST.  PROJ. COST: $20,021,067

PROJECT NUMBER:  11022 EMD           PP8S NO.
PESCRIPTION Of PROJECT:  This project will evaluate the effectiveness  of
employing a deep tunnel system within a highly developed urban area to
temporarily store excess combined sewer flows for return to the sewage
treatment plant during off-peak hours.  This demonstration will reduce
the discharge of untreated combined sewage to the receiving stream and
minimize overloading the waste treatment plant.  Should this method of
control prove to be economically feasible through the use of advanced
tunneling equipment, present plans in the Chicago Metropolitan Area
envisions a vast network of deep tunnels for ultimate control of all
waters in excess of that which can be conducted by the existing drainage
systems.
INQUIRIES:  Contact tht  Storm and Combined Sewer Pollution Control Branch
                        0^-tce o£ RueafiiC.lt and Development
                        FerfeAfcfc Watt*. Pottutwn Contol
                        U.S. Pepo/Umeat orf tht
                        633 Indiana Aue. N.df.
                        Ua&kington,  V. C. 20242

-------
 INFORMATION  SHEET--
           RESEARCH &  DEVELOPMENT  GRANT
TJU4 Aheet deA&ttbeA btUt^ty an R 6 V &um£ auxvided undvi Sec. 6,
Fede/utd afctte* Pollution Contnol AcilCdean WateA. Re&t04a£um Act) .
GRAWTEE: Borough of New Providence, New Jersey
TITLE OF PROJECT:  "Utilization of High Rate Trickling Filters for
      :Treatment of Combined Sewer Overflows"

PROJECT SITE: New Providence, N.J.   PATE Aft/ARPEP; June l6, 196?

FEPERAL GRANT;  $1+7^,000             TOTAL EST. PROJ. COST; $1,187,680

PROJECT NUMBER; 11023 FAN            PPBS HO.  1102


DESCRIPTION OF PROJECT;

Two high rate trickling filters will be installed to accommodate and
treat the extremely wide range in volume of overflows which occur
during periods of rainfall.  Overflows are presently discharged
untreated to the receiving waters, causing organic and bacterial
pollution.  Adaptation of this conventional treatment method to
adverse operating conditions to achieve treatment of combined sewage
prior to discharge will be demonstrated.  One trickling filter will
be constructed with a plastic filter medium; the other, with conventional
trap rock or stone filter medium.  Following the filters, facilities
will be provided to add polyelectrolytes and other chemicals to improve
sedimentation efficiency in the final settling tank, also as a part of
this project.  Chlorination facilities will disinfect the final effluent.

The facilities will be operated so as to maintain biological growth on
the filters during dry weather periods, making the filters effective
during periods of overflow.  A monitoring program will thoroughly evaluate
the operation and effectiveness of the separate treatment units as well
as the overall effectiveness of the entire installation.  The system
operation will be varied so as to develop the most effective and economi-
cal plant operation to achieve the desired results.
INQUIRIES;  Contact tke. Storm and Combined Sewer Pollution Control Branch
                        0^-tce o£ Rejeatcfi and Pevelopnent
                        Fedetol Itlatvi Pottuutton Control
                        U.S. Pepo/ttmeitt o£ the, Intvuai
                        633 Indiana Aue. A/.U/.
                        Wcuhington, P. C. 20242

                                  53

-------
 INFORMATION  SHEET —
         RESEARCH &  DEVELOPMENT  CONTRACT
    * the.et. duc.fu.bu fattest/ an Rgp Contract awarded unde*. Sec.  6
 fzdvi&t DJateA Pollution Contact Ac* IC£ean Wtttet Re t -a£uw Ac*) '.
 CON/TRACTOR;  j^ Chemical Company
             Midland, Michigan
 TITLE OF PROJECT;  "Demonstration and Evaluation of Polymeric Additives
                   in the Treatment of Storm Water Overflow"

 PROJECT SITE;   Detroit, Michigan

 FEDERAL CONTRACT;   $700,000           PATE AWARPEP;  August 8, 1967

 PROJECT NUMBER;  1^12-9               PPBS NO;  1102
                 11023 FDB
 PESCRIPTION  OF PROJECT:

This project involves a two year study of the use of polymeric chemicals
to control pollution from combined sever overflows.  The project will be
carried out at Milk River Pump Station in suburban Detroit, Michigan.  This
installation, which serves an area of about 3700 acres, includes a  3-5 MG
detention basin.  The project will include  complete development of
hydrological information for the demonstration area.

Flocculant studies will be carried out on both laboratory and full  scale
to demonstrate the effect of the use of polymeric flocculants.  A demon-
 stration of the effectlveneas of disinfectants, both with and without
polymers, will be completed on both pilot plant and laboratory scales.
A major part of the project will be the fabrication of a model of the
 existing basin.  This model will be tested  concurrently with the full
 scale basin to validate its use for model extrapolation.  An optimized
model will be conceived, built and tested as a design for sedimentation
basins  incorporating chemical flocculation.
INQUIRIES;  Contact the.
                        0^-ic.e. o& ReAeoAch and Ve.veZopme.nt
                        Fe.deAat Wate*. Potfation Contfiot
                        U.S. Ve.paAtment ofi the. InteAioi
                        633 Indiana. Avenue, N.W.
                        Wa&hington, P. C. 20242

G.I i

-------
INFORMATION  SHEET
        RESEARCH  Ik DEVELOPMENT CONTRACT
Thi* .Ahee-t de.6cij.beA bfu.e.^ty an R6V Contract awaide.d undeA Sec. 6,
fedeAal WateA Pollution Contact Act \Ctzan WateA Re 1 *ition Act).


CONTRACTOR; Cornell, Rowland, Hayes and Merryfield, Engineers  and Planners
            1600 Western Avenue
            Corvallis, Oregon


TITLE OF PROJECT: "Primary Treatment  of Storm Water Overflow from Combined
                   Sewers by High Rate Fine Mesh Screens"

PROJECT SITE; Portland, Oregon

FEPERAi. CONTRACT; $139,331             PATE AO/ARPEP; August  1?,  196?

PROJECT NUMBER; lU-12-121              PPBS NO;   1102
	   11023  FDB             	
PESCRIPTION OF PROJECT:  This project will include  the  design,  construction,
demonstration and evaluation of  the performance  of  high rate,  fine mesh
vibrating screens for  removal of solids from combined sewage.

Various attempts have  been made  to use vibratory screens in  sewage treatment
in the past.  Grease formation and varying rates of flow were  persistent
problems.  The contractor has several innovations in screen  configuration
and combinations to be constructed and demonstrated which may  reduce these
operating difficulties.  If the  demonstration is successful, the device will
be used in normal sewage and at  some  industrial  treatment plants as well
as overflow points in  combined collection systems.

Development of such devices, which are compact and  adaptable,  are needed
for primary treatment  of excess  combined sewage  under the constraints urban
land use and low initial cost.
INQUIRIES;  Contact the. Storm and Combined  Sewer  Pollution Control Branch
                        0^-ice. OjJ ReAeaAch and Ve.veJtopme.nt
                        ffLdeAat WateA Votlution Contiot
                        U.S. Ve.pavtme.nt o$ the.
                        633 Indiana. Avenue,  N.W.
                        Wa&kington,  V. C. 20242

G.<:                               55

-------
INiXWiATION SHEET
                                                           Date to bo Rolcaccd

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT

      This Project is a Contract         ,  under Section6a(l)   	}
Federal Water Pollution Control Act (Clean Water Restoration Act).
GRANTEE OR CONTRACTOR;  Allis Chalmers
"{Name and Address)      Milwaukee, Wisconsin
PROJECT DIRECTOR;
(Name and Address)
TITLr] OF PROJECT:
Dr. Egbert K. A. Guth
Allis Chalmers
Milwaukee, Wisconsin

"Design, Construction, Operation and Evaluation of a
 Demonstration Waste Treatment Device Termed the
 'Rotating Biological Contactor' "
PROJECT SITE: Milwaukee,-  Wisconsin
Grant or
Contract
Period
From: 9/28/67
Thru: 2/28/70
Eligible
Grant
Period Costs
$ 388,526
FWPCA Gyfcnt
or Contract
Amount
$ 388,526
PROGRAM (PROJECT) NUMBER;
        1U-12-2U

DATE OFFERED:
DATE ACCEPTED (AWARDED);

        September 28,  196?
DESCRIPTION OF PROJECT;

        This project will demonstrate the applicability of a new concept of
        biological treatment to be applied within the sewage system.   The
        contractor has spent several years in developing a biological treat-
        ment method related to trickling filters and activated sludge processes;
        the method uses power driven rotating disks as the "housing media"
        for biological growths.  Laboratory results have indicated that
        greatly shortened detention periods can accomplish treatment equivalent,
        as compared to more conventional methods.  This technique offers
        the potential for biological treatment of flows of greater than
        normal magnitude, an important factor in treating combined sewer
        overflows.
INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of the Interior
                     Washington, D. C.   202^2
                                       56

-------
    ):
-------
  INFORMATION  SHEET~~
            RESEARCH  & DEVELOPMENT GRANT
 Tklt> Ahttt ducJuJbu bfu-t^lg an R 6 V Giant auxwded andvi Sec.  6,
 fedvuat W&tVL Pottution Con&iot Act (Clean WateA Rt&totation Act) .
 GRANTEE:  City of Somersworth,  New Hampshire



 TITLE OF PROJECT;  "Somersworth Combined Sewage Overflow Treatment Project"


 PROJECT SITE:  Somersworth, N.  H.     PATE AWARPEP;  December 1,  196?

 FEPERAL GRANT; $559, 080              TOTAL EST. PROJ.  COST:   $931,800

 PROJECT NUMBER;  11023 FAP            PPBS HO.  1102


 PESCRIPTION OF PROJECT;

Construction and evaluation of the applicability of  two one-million gallon
combined sewage treatment and storage tanks.  Pollution of receiving waters
caused by discharge of untreated combined sewage during wet weather periods
will be abated by providing facilities which will accomplish (a) short-term
detention chlorination and pump-back to the sewerage system and (b) variable
sedimentation times, chlorination,  long-term detention and discharge to
receiving waters.  Effects of treatment on the receiving stream and sewage
stabilization pond, technical and economic benefits  will be evaluated.
Potential benefits of polymers to increase carrying  capacity of the inter-
ceptor will be explored.
  INQUIRIES;  Contact tht Storm and Combined Sewer Pollution Control Branch
                         0^-cce 0(5 ReAeotcft and Peve£opnen£
                         Fede/ut£ WateA Pollution ConViol
                         U.S. V&pavtment orf the.
                         633 Indiana Ave. N.W.
                         OJatkington, V. C. 20242

                                   58

-------
 INFORMATION  SHEET--
        RESEARCH  & DEVELOPMENT CONTRACT
Thti Afteet ducJuibu bJu.e.£ty an RSP Contfiact auWidzd undtn Sec.  6,
        WateA Pottution Control Act IClean WattA Re^,"ratuw Ac*) .
CONTRACTOR;  Underwater  Storage,  Inc.
             1028  Connecticut  Ave.,  N.W.
             Washington, B.C.   20036


TITLE OF PROJECT:   "Pilot Demonstration Underwater  Storage  Facility for
                    Storm Water Overflow"

PROJECT SITE;  Washington, B.C.

FEPERAL CONTRACT:  $658,763             PATE AO/ARPEP:  December  ik,  196?

PROJECT NUMBER: lU-12-139              PP8S A/0;   1102
-  11022 DWF              -

DESCRIPTION OF PROJECT:

   The project  includes  the design,  construction, operation and evaluation
   and removal  of  a pilot plant underwater  facility for  temporary  storage
   of storm overflows from a combined  sewer.   Pollution  of  the  Anacostia
   River  due to such discharges will be controlled  by capturing and
   temporarily  storing the combined  sewage  in flexible underwater
   containers until the  storm  causing  overflow has  ended.

   Storage  will be completely  under  water in  two  100,000 gallon containers
   of flexible  rubberized nylor material.   These  will be anchored  to the
   bed of the Anacostia  River. The  combined  sewage will pass through an
   automatic bar screen  and grinder  and through a grit chamber  and then flow
   to the storage  containers by gravity.  Pumps of  a  non-clogging  type
   will be  used to remove the  untreated sewage from the  storage containers
   and return it to the  sewerage  system for subsequent treatment.

   The system will be treated  with water pumped from  the river  during
   periods  when there is no natural  storm water overflow.
"INQUIRIES:   Contact the. Storm and Combined  Sewer Pollution Control Branch
                                $ KueaAch  and Veuttopmuit
                                WateA  Pollution Contact
                        U.S.  Dtparubnent otf  the. IntvUox.
                        633  Indiana Avenue, N.W.
                        Wa&kington, P. C. 20242

-------
INFORMATION  SHEET ~ ~
        RESEARCH & DEVELOPMENT  CONTRACT
     4hee£ dz&cAibu b^U.e.^ly an R5P Contract asaaJuLed undeA Sec.  6,
        WateA Potdutton Contact Ac* ICCean Wa*e/i R^.-f."ration Act).
CON/TRACTOR: Melpar,  Inc.
            7700  Arlington Boulevard
            Falls Church,  Virginia
TITLE Of PROJECT: "Pilot  Plant  for Underwater Storage of Combined Sewer
                   Overflow"
PROJECT SITE;  Cambridge, Maryland

FEPERAL CON/TRACT;  $^10,386

PROJECT NUMBER: 14-12-133
	  11022 DPP
PESCRIPTION Of PROJECT:
PATE AWARPEP; December lU, 1968

PP8S WO;  1102
   Based on preliminary plans  and specifications,  the contractor will
   design,  construct,  operate  and evaluate,  and be  prepared to remove,
   a pilot  plant  underwater  facility to provide temporary storage of
   storm overflows  from a combined sewer.  Pollution of the Anacostia
   River due to such discharges  will be controlled by capturing and
   temporarily storing the combined sewage in flexible underwater con-
   tainers  until  the storm causing overflow  has ended.

   Storage  will be  completely  under water  in a single container having a
   maximum  capacity of 200,000 gallons. The bottom of the tank will be
   of vinyl coated  steel, placed in a depression excavated in Choptank
   River.  The upper half of the storage container will be of flexible
   neoprene coated  nylon material.  Two, two speed (600 - 1,000 gpm)
   pumps will be  used  to pump  the combined sewage  to storage, and to
   remove the untreated sewage from the storage container and return
   it to the sewerage  system for subsequent  treatment.

   The system will  be  tested with fresh water during periods when there
   is no natural  storm water overflow.

INQUIRIES;  Contact the.  Storm and Combined  Sewer  Pollution Control Branch
                                >tf RfcAfc&tch and Ve.vttopnG.nt
                                WateA  Pottution Control
                         U.S. Ve.pavbnejnt o^ the.
                         633 Indiana Avenue,  W.W.
                         Washington, V. C.  20242

                                  60

-------
INFORMATION  SHEET
        RESEARCH  & DEVELOPMENT CONTRACT
     t>he.tt duc.tu.bu bfUe.f,ty an RSV Contract auntJed undeA Sec. 6,
fe.de.ictl WateA PottwUon Contact Act IC£ean Wa-tet Re ( -ttion Act).
CONTRACTOR; Karl R. Rohrer Associates
            529 Grant Street
            Akron, Ohio  M+311


TITLE OF PROJECT: "Construction of a Facility to Demonstrate Offshore
                   Underwater Temporary Storage of Storm Overflow  from
                   a Combined Sewer"
PROJECT SITE:  Sandusky, Ohio

FEPERAL CONTRACT; $559,895             PATE AWARPEP; December lh,  196?

PROJECT NUMBER;  lU-12-1^3             PPBS W; 1102
                  11022 ECV
PESCRIPTION OF PROJECT: A pilot plant underwater facility will be  designed,
constructed., operated and evaluated as a method of temporarily storing  storm
overflows from a combined sewer0

Storage will be completely under water in two 100,000-gallon containers of
flexible rubber nylon material,,  These will be attached to a nearly  square
2U" pipe frame and anchored to the bed of Sandusky Bay of Lake Erie.  After
passing through a bar screen, the combined sewage will flow by gravity  to
the storage containers.  An 1,800 G-IM pump of a non-clogging type will be
used to remove the untreated sewage from the storage containers and  return
it to the sewerage system for subsequent treatment„

Provision will be made for testing the system with fresh water during periods
when there is no natural storm water overflow.
 INQUIRIES;   Contact the. Storm and Combined Sewer Pollution Control Branch
                         0^-tce  of,  RweflAdt and Ve.vttopne.nt
                         Ftideiai Wat^n.  Poliation Contiot
                         U.S.  Ve.paAtme.rA 05 tke. 1nteAi.oi
                         633  Indiana Avenue,  N.W.
                         taa&lungton,  V.  C.  20242

 C-.-/:                                61

-------
 INFORMATION  SHEET--
           RESEARCH  & DEVELOPMENT GRANT
Tkit> *httt duvU.hu bfUt^ly an R. 6 V Giant auwuiuL wndvi Sec.  6,
fedvtat lilatvi Pollution Control Ac-t(C£ean WateA RutoMtion Act].

GRANTEE:  City of Few York
TITLE OF PROJECT;  "Evaluation of Spring Creek Auxiliary Pollution Control
      'Project"

PROJECT SITE: New York City, New YorkgATE AWARPEP;  December 26, 1967

FEDERAL GRANT; $8^3,750              TOTAL EST. PROJ.  COST;  $1,126,000

PROJECT NUMBER; 11023 FAO            PPBS NO.    1102


VESCtmiOH Of PROJECT:

 Overflows from combined sewers contribute significantly to  the pollution
 of Jamaica Bay, New York City in constructing a major combined sewage
 treatment facility "Spring Creek Auxiliary Pollution  Control Project"
 specifically designed to provide sedimentation and chlorination treat-
 ment to combined sewage.  The demonstration project will establish
 pre-construction water quality conditions in  Jamaica  Bay, Spring Creek
 area, and location of all sources contributing to  pollution of the
 Bay.  Characterization of parameters that measure  the effects of combined
 sewers will be apart of the investigations.  Following construction the
 effectiveness of the combined sewage treatment facilities will be evaluated.
 It is anticipated that the Spring Creek facility will serve as a prototype
 for additional projects leading to an upgrading of the quality of Jamaica
 Bay waters.
INQUIRIES;  Contact the. Storm and Combined Sewer  Pollution Control Branch
                        O^^ce o£ ReAtcuich and VtveJtopntnt
                        Fede/utt Wotet Pottuution Con&iot
                        U.S. Vtpevubntnt o$ the.
                        635 Indiana. Ave. N.W.
                        WoAkington, V. C. 20242
GWerdig  101767

-------
INFORMATION  SHEET —
        RESEARCH K  DEVELOPMENT  CONTRACT
Thu> &hz&t ducnibu bui^iij an R6V Con&iatt am.ide.d undeA Sec. 6,
        WattA Pollution Contnol Act IC£ean Wo^e/t Re t "ition Ac-t).
CONTRACTOR;  Glenfield & Kennedy,  Inc.
             King of Prussia, Pennsylvania
TITLE OF PROJECT:  "Microstraining, Ozonization & Chlorination Pilot Tests
                    on Combined Sewer Overflows"

PROJECT SITE: Philadelphia, Pennsylvania

FEPERAL CONTRACT; $180,086             PATE AWARPEP;  December  27,  196?

PROJECT NUMBER;   1^-12-136              PP8S NO;  1102
                 11023 EVO
PESCRIPTIOM OF PROJECT:  The project will  involve  the  construction,  operation,
and evaluation of the use of microstrainers  for treating  combined  sewer  over-
flows.  Microstrainers are currently used in raw water  supply  treatment  and
for polishing sewage treatment plant effluent.   The demonstration  site will
"be on part property in the City of Philadelphia,  Pa.

The applicability of ozone to disinfect flows  will also be  evaluated.  Improved
techniques for disinfection are also desired.   Ozone  is used fairly extensively
in Europe for water supply disinfection,  but has  had  only limited  use  in this
country.

Evaluation of screening and filtration methods is a very  important facet of
the total Storm/Combined Sewer Program since such treatment has the potential
for removing large amounts of organic and inorganic solids  contained in  the
overflows.  Such solids are major pollutants during storm periods.
INQUIRIES:  Contact the. Storm and Combined Sewer  Pollution Control Branch
                                |< R&seoAch and V^itopmunt
                                Ucutzi Poiiation Cotitloi
                        U.S. Ve.r&ifrnzn£ 03 iha Inte/txoi
                        633 Indiana. Avenue,  W.W.
                                    V. C. 20242

                                 63

-------
 INFORMATION  SHEET--
           RESEARCH  & DEVELOPMENT GRANT
Tfou Ahe.et deAuUbe* bUt^ly an R 6 V Quint auxvuLed undeJi Sec.  6,
Fede/tofc Uktte/i Pot&ttuw Control Ac*(C£eon WateA. RutotuuUon Act).

GRANTEE;  City of Mt.  Clemens,  Michigan
TITLE OF PROJECT;  "A Combined Sewerage Collection and Treatment Facility"


PROJECT SITE:  Mt. Clemens, Michigan PATE Atl/ARPEP;  February 28,  1968

FEDERAL GRANT;  $631,989             TOTAL EST.  PROJ.  COST;   $918,500

PROJECT NUMBER;   11023 FAR           PPBS NO.  1102


PESCRIPTION OF PROJECT;

Overflows from combined sewers cause pollution of the Clinton River during
wet-weather periods.  The project is designed to demonstrate the feasibility
of controlling such pollution by constructing three aerated "Lakelets"  to
serve as treatment units.  The "Lakelets" will be equipped with surface
aerators and operated in series.  Effluent from the first two ponds will be
subjected to chemical treatment and microstraining, with the final effluent
from the third pond receiving similar treatment and chlorination prior  to
discharge to the Clinton River.  The project will explore the potential of
the Lakelets as recreation facilities for boating and fishing as a part of
park operation.
 INQUIRIES:  Contact the. Storm and Combined Sewer Pollution Control Branch
                        O^-tce o£ ReAeotcfi and Vevtlopntnt
                        fedvtat Mate* Pottutton Control
                        U.S. Pepafedneitt orf the. Intvuoi
                        633 Indiana Ave. H.W.
                        Uatkington, V. C. 20242

-------
 INFORMATION  SHEET--
           RESEARCH &  DEVELOPMENT  GRANT
Tfe£& Akee* du>cju.bu t^U.tf,ty on R 6 P G/um£ awarded andeA Sec. 6,
Fedetad Wa*e/i Po-ttatuw Control ActlCdotn Wo£a* RutonjtUon Act).

GRAA/TEE;   City of Cleveland
           City Ball,  601 Lakeside Avenue
           Cleveland,  Ohio  ¥m^

TITLE OF PROJECT; "A Program for Demonstrating Combined Sewer  Overflows
    Control Techniques for Water Quality Improvement and Beach Protection"

PROJECT SITE:  Cleveland, Ohio       PATE AWARPEP;   May 3, 1968

FEPERAL GRANT; $325,162              TOTAL EST. PROJ. COST; $1,030,000

PROJECT NUMBER;  11023  EZW           PPBS  MO.   H02


PESCRIPTION OF PROJECT;
The project consists of the immediate application of several control
and treatment methods designed to abate pollution from combined sewer
overflows and control of water quality at  the  Edgewater and White  City
bathing beaches on Lake Erie in the City of Cleveland.  Control and
treatment measures to be applied include:

(l)  Bypochlorination of combined sewer overflows and local streams
     contributing to pollution of beach areas,
(2)  Use of polymers to reduce overflows by increasing interceptor
     flow capacity.
(3)  Initiation of a sewer flushing program to reduce solids discharged
     from the drainage area tributary to the Edgewater overflow.
(k)  Screening of overflows and streams.
(5)  Construction of sheet piling and flexible barriers to enclose beach
     areas.
     Control of water quality within enclosed  beach areas.
     Collection of debris and coarse solids.
     Miscellaneous sewerage system improvements.
INQUIRIES;  Contact tht Storm and Combined Sewer Pollution Control Branch
                        0^-Lc.t o£ ReAeotck and Vevttopmtnt
                        feJdeAat Mate*. PotCutcon  Con&wl
                        U.S.  Pepne*t orf  the. Intvuo*.
                        633 Indiana. Ave.  N.W.
                        Washington,  P.  C.  20242

                                 65

-------
 INFORMATION SHEET
           RESEARCH &  DEVELOPMENT GRANT
           du>cJtib&>  bru.£ity an  R  £  P Gnmt ca&Lfidzd ttndVL Sec. 6,
              ?oiiu£wn Con&ioi  ActlCCcoK fc'a-tet Re^c/uxtion A
GRANTEE:   City of Dallas
           210 City Hall, Main and Harwood
           Dallas, Texas  75201

TITLE OF PROJECT:  "Stormwater Treatment Facilities"
PROJECT SITE;   Dallas, Texas         PATE AWARPEP;   May 21, 1968

              :  $1,093,360            TOTAL ESj'.JgOJ. COST;  $1,^88,732

               : H023 FAW              F6S W.  1.102
            OF  PROJECT;

The project consists of the 4^sign, construction and evaluation of a
facility to treat overflows from sewers carrying a mixture of domestic
wastewater and infiltration stormwater.  Physical features include a
diversion structure, pumping station, flocculation and sedimentation
basins, chemical feed facilities, and a pipeline for conveyance of
waste lime sludge from the municipal water treatment plant to the
overflow treatment facility.

Treatment Unit #1 will include flocculation,  sedimentation and polishing
treatment with tube-type clarifiers; Unit #2.  will include flocculation
and sedimentation; Unit #3 will include high-rate sedimentation.   Effluent
from the facility will be chlorinated.- Design flow rate will be 28 million
gallons per day.

The facility will be operated and evaluated as a demonstration project for
a period of one year following completion of construction.
                         Storm and Combined Sewer Pollution Control Branch
                                                Peve£op/ie*i£
                         U.S.
                         633 IndJuLna Aue.. W.W.
                                   , P. C. 20242
                                   66

-------
I N I'O R M A T ION  SIJ !• E T '	
        RESEARCH  K  DEVELOPMENT  CONTRACT
                            ij an ?J>V Con&iact aiWidtd undvi. Sec.  6t
Fc.dtfial Wat&i Potiut4.cn  ContAoi Act lCido.ii Wot&i Rv-tsivLLon Ac-t).
CONTRACTOR;   Aerojet-General  Corporation
              9200  East Flair  Drive
              El  Monte,  (Jalifornia  91734


TITLE OF PROJECT;   "Role of Solids in Combined Sewage Pollution"


PROJECT SITE;   San Francisco, California

FEPcRAf. Ccy/TRACT;   $92,605.00          PATE /.{(/ARPEP:  June 20, 1968

PROJECT DUMBER:  14-12-180             PPBS NO*   1102

         Q.V OF ?>RQJECT;
  The  piarpose  of  the twelve -month field investigation and evaluation  is
  directed toward determination of  the feasibility and potential
  benefits that may be obtained through the removal of solids utilizing
  in-sewer screening devices.   Sufficient data to permit a reasonable
  assessment of the anticipated removals  of floatables anid solid
  material will be obtained.   The effect  on chlorinattion requirements
  resulting from  £he solids  removals will be investigated,.  The contractor
  will evaluate the relationship between  the aesthetic water quality
  considerations  and proposed State Water Quality Standards for those
  bodies  of water receiving  combined sewer overflows.
7//OUIRIES:  Contact the.  Storm  and  Combined  Sewer  Pollution Control Branch
                        0^-tce  o^ RuWitk and Ve.ve.iopnc.nt
                        fcdeiai WatcA Voiiution Contnoi Adr/
                        U.S.  P£pO/ti!i»ni 0|J tilt
                        633  Jj-mar.a AV£;JUC,  W.W.
                        WoAWngCon, P.  C.
                                   67
G.-J:

-------
I N 1' O R M A T ION  S11 )•: K T
        RESEARCH  S  DEVELOPMENT  CONTRACT
T/;a 4/ic.ci duansibu  b.'i.ic.fciy CM  K£P Cou-t'aic.i e.iWidtd undeA Sec.
                               d  Aa-t
          -'   American Process Equipment Corporation
              2015  Lisenby Avenue
              Panama City, Florida  32401


TITLE OF PROJECT;  "Fabrication and Evaluation of an Ultresjonic Filtration
                    System for Treating Combined Sewer Overflows"

PROJECT SITE:   Panama City,  Florida

_F£PcRAf. CO/.'TIMCT;  $248,500.00          PATE AWAKPEP;   June 25, 1968

PROJECT MUBUK:   14-12-195             PPSS W;  1102
                  11023 DZF
PESCRIPTIOM OF  PROJECT;

   This fourteen month investigation will design, fabricate and demonstrate
   an ultrasonic filtration system of field size with a maximum capacity
   of 160 gpm.  The potential effectiveness of this syfetem was demon-
   strated in a three month feasibility study, in which a laboratory
   unit achieved BOD and Suspended Solids reductions of approximately
   65% for a 50 micron element treating raw sewage which had only
   been subjected to coarse bar screens and a detritor.  Ultrasonic
   energy can restore  the filter elements  to  "like  new"  condition
   without necessitating  frequent filter element replacements.   The
   testing program would  provide definitive quality and  quantity data on
   system performance, reliability and cost.  Pretreatment  requirements
   will be determined  and automatic operating procedures will be
   established.  Included as  a part of this proposal is  a one month test
   program to determine the applicability  of  the proposed "field unit"
   for removal  of  algae from  oxidation pond effluents.
            Contact, -t/ie Storm and Combined Sewer Pollution Congrol Branch
                                          /i and
                                       Pollution ContAot
                         U.S.  Vej-;a;Ujn& t'nc.
                         633 Indiana Avenue., W.W.
                                   , P. C. 20242-
                                    68
C-.V:

-------
 INFORMATION  SHEET
        RESEARCH K  DEVELOPMENT  CONTRACT
                                                            Sec.  6,
Vc.d2.nal £'.Y(/£ CA  PotCu^ian Coivfoot Ae£ lCte.au WtUeA R^-C.-iatcon Ac-t) .
CMTRACTOR;   Burgess & Niple, Limited
              Consulting Engineers
              2015 West Fifth Avenue
              Columbus, Ohio  43212

TI TIE Of  PROJECT;   "Engineering Investigation of Storm and Combined
                     Sewer Pollution at Bucyrus, Ohio"

PROJECT SITE;   Bucyrus, Ohio

FEPcRA/. CQ.TrKACT;   $136,665.00         PATE AWARPEP;   June 27,  1968

PROJECT NUMBER;   14-12-401             PPSS MO;   1102

PESCRIPT70M OF PROJECT;

   A thirteen (13) month study to investigate the combined sewer  problems
   and evaluate the benefits, economics and feasibility of collection
   and treatment of overflows in Bucyrus, Ohio.  The problems encountered
   are considered to be typical of combined sewer systnms in small  communities
   with flat terrain.  Plans will be formulated for solutions of  the
   problems pinpointed during the field investigations.  Development of  the
   corrective plans will consider several storage concepts,, physical
   and chemical treatment, partial separation of sewers where appropriate
   and possible sewage treatment plant modifications.

   Field investigations will include monitoring of principal overflow
   locations, rainfall measurements, and stream gaging.
            Contact the. Storm and Combined Sewer Pollution Control Branch
                        0^-ic.o.  OjJ  Re4e/(*c/i and Ve.ve.Lop wit
                        ftdznat WoicA PoMution Con&iot Adr.iuiut nation
                        U.S. Pc.po/ti?;»n-t o£ the.
                        633  lnd4M.ua AvtJiue,  W.W.
                                to ii,  P.  C.  20242-
                                  69
G.-/:

-------
I N FORM AT 10 N  S H E E T	
        RESEARCH  & DEVELOPMENT  CONTRACT
TkU Ah&zt duc.ni.bti,  bnlz&ly an RSD  Coii&iact  avxifide.d imde/i Sec.  6,
        I'JateA Pollution Control Ac*  !C£ean WateA  Re.>Is*.action Act).
CONTRACTOR;   Henningson, Durham & Richardson
              3555 Fornam Street
              Omaha, Nebraska  68131
TITLE Of PROJECT:   "An Engineering Investigation of Storm  and  Combined
                    Sewer Problems"

PROJECT_SITE:    Des Moines, Iowa

FEPERAL CONTRACT;  $301,200.00         PATE Aft/ARPEP;    June  28,  1968

PROJECT WI/M8ER:   14-12-402            PPBS A/0;  MOB
	     110214. FEJ           	
PESCRIPTIQM OF PROJECT:

  This fifteen month study pertains to engineering  investigations
  necessary to assess combined sewer overflow  and stormwater  discharge
  problems in Des Moines, Iowa with the development of recommended
  applicable solution.  Field investigation will be utilized  to pinpoint
  and assess existing problems.  Recommended solutions will be  selected
  from a number of alternate approaches based  on cost and expected
  effectiveness in controlling and/or treating the  discharges.  Alternate
  solutions to be included are surge or retention basins, percolation
  basins, mechanical clarification facilities, utilization  of flood
  control facilities and  existing open surface channels.   Preliminary
  estimates for sewer separation will be developed.

  The contractor will conduct a stream and  combined sewer sampling apd
  analysis program, coupled with a rainfall network for development of
  rainfall-runoff-quality relationships<,
 INQUIRIES;   Contact the. Storm and Combined Sewer Pollution  Control  Branch
                        O^-cce  0({  Re^eoAc/i and Peue/optiani
                        fade-fiat Woiet. Pollution Control
                        U.S.  Pepcw-ftrietti o£ the. InteA+on
                        633  Indiana. AveKtte,  A/.W.
                        Washington,  P.  C.  20242

 G.V:                                70

-------
1 N 1' () K iN • A TIC) N  SI i
        RESEARCH  & DEVELOPMENT  CONTRACT
              PotCc^-can C
                               ^  Act ICtcau
CC''jrK.'.Ci P.'!.'
              Aerojet-General Corporation
              Environmental Systems Division
              El Monte  California
      Or' PROJECT:   "
                     A Method for Assessing the Extent of Pollution from
                     Stormwater Runoff from an Urban Area"
                Sacramento,  California

                    $402,594.00        PATE
              ?:  PROJECT:
                                                   V:  June 29, 1968
                                                   H02
  This 15 month study will investigate the combined sewer problems in
  Sacramento, California.  Seven potential control and/or treatment
  systems will be explored to determine applicability as solutions to
  the problems defined by field investigation.   They include:  high
  rate cyclone and air flotation treatment, rapid flow combustible filter,
  pressure sewers, temporary storage, deep tunnel system, stabilization
  ponds, and sewer separation.  Preliminary plans and specifications will
  be prepared for each of the systems with a cost/effectiveness evaluation
  to measure the capability of each system to correct the pollution
  problems resulting from combined sewer overflows.  Economic and social
  impact studies will be included.

  A combined sewer overflow data collection and analysis program, including
  rainfall-runoff-quality relationships will be established at several
  locations.
INQUIRIES:
                          Storm and Combined Sewer Pollution Control Branch
                         Oj^-tce o£ Reie/tAc/i and
                         Fe.d&nat WatcA Poitution
                         U.S.  Pcp-.vi-tfi2.ni 0({ -t/ie
                         633 Indiana Avenue, W.W.
                                  n, V. C. 20142-
                                   71

-------
IN'FOR MAT ION  SHEET
        RESEARCH  K DEVELOPMENT  CONTRACT
T/ita A/tcci duvuhtt, b'LLti-itj an TtfP  COK&ULCJ. aiWidad undeA Sec. 6,
                                                  Rc-.^."t,v^o;t Ac-C).
CONTRACTOR;   Metcalf & Eddy,  Inc.  Engineers
              1029 Corporation Way
              Palo Alto, California  94303
TITLE OF PROJECT:  "Engineering Investigation of the East Bay Municipal
                    Utility District of the San Francisco Bay Area (Oakland)

PROJECT SITE:    Oakland,  California

FEPcRAL CO.'.TRACT:    $141,300.00        PATE AWARPEP:   June 29, 1968

PROJECT MMBER:   14-12-407             PPBS M0;    1102
                  11024 EQG
PESCRIPTIO.V OF ?>ROJ£CT:

   A fifteen (15) month study to conduct an engineering investigation
   of sewer infiltration problems in the East Bay Municipal Utility
   District of the San Francisco Bay Area (Oakland).  At the present
   time,  (due to infiltration) the sanitary sewage system functions
   as a combined storm-sanitary system during wet weather.  Sewage treat-
   ment plant flows rise to 5 times dry weather flow resulting in a
   great deal of by-passing.  Problem areas and causes will be delineated
   and alternative engineering solutions will be developed, including
   determination of both technical and economic feasibility.  Generalized
   cost curves will be developed for the alternates.  Applicability of
   solutions to other areas with similar problems will be considered.

   A representative data collection program will be conducted.  Approxi-
   mately twenty flow gaging stations, five sampling sites and a rain
   gage network will be utilized.
INQUIRIES:   Contact tkz. Storm and Combined Sewer Pollution Control Branch
                                            and
                                       PolLution Con&ioi
                         U.S.  Ve.pa/Ujnwt OjJ the.
                             IncU&r.a AVCJIUC, W.W.
                                  n, P. C. 20242-
                                    72

-------
INFORMATION  SHEET
        RESEARCH  & DEVELOPMENT  CONTRACT
                     b'u.e.&ty an R5P Contract awttictecf unde/t Sec.  6,
                        ContAol Ac-t
CONTRACTOR:   R. F. Weston
              Environmental  Science & Engineering  Consultants
              1426 Lewis Lane
              West Chester,  Pennsylvania   19380

TITLE OF PROJECT:  "Develop  and Demonstrate  a  Method  for  Assessing
                   the  Extent  of Pollution from  Storm Water  Runoff in
                   an Urban  Area"
l^2^L^]IL:  Washington, D.  C.

FEPERAL CONTRACT; $229,525             PATE  AWARPEP:    June  29,  1968

PROJECT NUMBER;  14-12-403             PPSS  NO;    1102
                 11024  EXF
PESCRIPTION OF PROJECT:

 Roy F. Weston will conduct  a  twelve  month study to investigate  the
 combined  sewer problems in  the District  of  Columbia.   Twenty-five square
 miles served by combined sewers would be included in the project area.
 Several alternate approaches  to solution of the overflow problem will
 be investigated, with  emphasis on chemical  flocculation  coupled with
 high-rate filtration.  The  "deep  tunnel" storage  concept will also
 be considered.

 The Contractor will gage major streams  and  major  overflows  within the
 demonstration area, in conjunction with  a overflow quality  sampling
 and analysis program at selected  locations.

 A laboratory research  program will be conducted to determine  the
 efficiency of removing flocculated solids and associated BOD  by high
 rate filtration of combined sewer overflows.  Filtration rates  of
 15 or more gallons per minute per square foot are anticipated.
INQUIRIES:  Contact the.  Storm and Combined Sewer Pollution Control Branch
                        0^4,c.
-------
   INFORMATION  SHEET	
             RESEARCH &  DEVELOPMENT  GRANT
                            ty a>: R £ V G
-------
 INFORMATION  SHEET
           RESEARCH  & DEVELOPMENT  GRANT
                               >; R $
           Board of  County Commissioners
           Montgomery County, Ohio
TITLE  OF PROJECT:   "The  Determination  of Ground Water  Infiltration
       '              and  the  Effects  of Internal Chemical  Sealing  of
                     Sanitary Sewers"
                KetterinS>  Onio       PATE  Mt\RDcQ:  August 8,  1968
 FEPcRAL  G.^H";   $96,570               TOTAL EST.  PZOJ.  COST; $137,000

 PROJECT  HLf;.:55R;  11022 DHQ            PP3S  NO.  1102

          ;.' OF
 A demonstration program is  to be  carried  out which will precisely
 identify the  cause  and degree of  infiltration  of  surface  and  ground
 water  into selected sewer sections.  After  establishing the cause
 and affects of this surcharging remedial  action will be taken
 utilizing internal  sewer sealing  with  chemicals and pressure
 grouting.   New techniques for ehcmical application will be developed
 as the work progresses.  After and during the  sealing program
 effectiveness and cost data will  be  analyzed to establish the most
 effective technique and material  with  respect  to  solution of  the
 problem and cost.
INQUIRIES:  Contact thi  Storm and Combined Sewer  Pollution Control Branch

                         ¥ed.&ia£ l>!c..t&i  PoLb^tLor. Con&iot hcLtuJUAfria^ion


                         Washington, V. C. 20242
                                  75

-------
 I N F O R M A T I O N   S H E E T
        RESEARCH &  DEVELOPMENT  CONTRACT
  ia 4/iee£ duc.nj.bo,>> bfU.q.^JLy an RS'D Contract aw>ide.d undue Sec.  6t
         ttatcA Pollution Conftat Act lC.ie.an WateA KM*nation Aci).
 CONTRACTOR:  Hayes, Seay, Mattern and Mattern
             Roanoke, Virginia
TI7LF OF  PROJECT: "Engineering Investigation  of Combined Sewer Overflow
                   Problem"

               Roanoke , Virginia

           ^£[;  $10^»19l             PATE Ati'ARPEP;   August 16,  1968

              l;  1^-12-200              PPBS MO;  1102
                 1102U  DMS
                  ?£§£I:  -A twelve  (.12) month  study to investigate
overloaded sewer problems in Roanoke, Virginia.   Storm waters enter
the sanitary sewer system causing overloading  of both the collection
system and the sewage treatment facilities.  By-passes enter the Roanoke
River and reach Smith Mountain Lake, a hydro-electric power development
which is also used extensively for water-oriented recreation.  The
overflow problems of the area will be subjected  to a detailed engineering
evaluation.  Preliminary plans with cost  estimates for remedial measures
will be prepared.
_T_MOUTR_7ES:   Contact -t/ie Storm and Combined Sewer Pollution Control Branch
~                        0^-tce otf ReAM-tc/i and Vzv&iopr.e.nt
                         fe.de.nat WatcA PotlutLon ContnoL
                         U.S.  Pc.po'Ldiis.ni of, the.
                         Wcttkington,  V.  C.  20242

                                   76

-------
 INFORMATION  SHEET
         RESEARCH  K DEVELOPMENT  CONTRACT
 Tfi-66 4/tee.t ducn^LbsJ, bfu.s.^iy an R5P Contract avxL>idc.d una'e-t Sec.  6,
 federal OteteA Po££u£ixm Contnot Act \Ciaan d'ate-i  Re.^.^atcon Act).
 CONTRACTOR; American Public Works Association
             1313 East 60th Street
             Chicago, Illinois
 TITLE OF PROJECT: "Analysis of Regulator  Facilities,  Their  Application
                    and Maintenance Practices"

 PROJECT SITE; Chicago, Illinois

 FEPERAL CONTRACT: $65,000              PATE AWARPEP;  August 30,  1968

 PROJECT NUMBER: lU- 12-^56              PPSS WO;  1102
                 11022 DMU
A seventeen month analysis of combined  sewer  overflow regulator facilities
to determine what improvements are needed  to  increase the  efficacy,  resulting
in reduced pollution.  The final report will  serve  as a community working
guide as it will establish the state of the art by  (l)  providing practical
and useful information concerning design criteria and operational and
maintenance practices, (2) stressing the application  of newly developed
or improved materials and technology presently available,  and (3) identi-
fying areas for future research and development.  The APWA Research
Foundation will finance up to 25$> of the total cost through financial
participation by public agencies such as cities and counties at the  local
level.
 INQUIRIES:  Contact the Storm and Combined Sewer Pollution  Control Branch
                         Ojf^ce 0($ Re^e^Ac/i and
                         Fecte-u-i a'otet  PoltutLoa CoiitioL
                         U.S. Pcjra-'Uttent o  the.
                                   , V. C.  20242

                                   77

-------
I N F O R M A T ION  SII E E T
        RESEARCH  &  DEVELOPMENT  CONTRACT
  ib 4fteet dzAcx+boA  b'Uc.&f.y an  RBV Con-t>Mct ai'.wtde.d undeA Sec. <5,(&2)
federal Mate*. PoitwUon Con&iat  Act ICte&n Mate* Ritejuo
-------
INFORMATION  SHEET
        RESEARCH  K DEVELOPMENT  CONTRACT
                             an R£P CoyttA.ac.-i aautderf  undeA Sec.  6,
              PoltwUc-n ContAoi Aa£ I Clean Mate*  R £.>.*•> ration Act).
CONTRACTOR.-  FMC Corporation
             Central Engineering Laboratories
             1185 Colemstn Avenue
             Santa Clara, California  95052

TITLE OF PROJECT; "Evaluation' of a Periodic Flushing  System for
                   Combined Sewer Cleaning"

               Santa Clara, California

               l: $323,600             PATE AWARPEP:  October 9,
PROJECT NUMBER: 1H-12-U66              ppBS NO;  H02
                 11022 DNO

gESCRTPriaV OF PROJECT;

  The objective of this 13-month project  is to perform Phase  II of a three-
  phase program to demonstrate  the  feasibility of  reducing pollution from
  combined sewer storm overflows by means of periodic  flushing during
  dry weather.  Included  in  the total program are  study of the theoretical
  basis for correlating flushing requirements for  various  sewer conditions,
  verification of the  hydraulic requirements for flushing  by  test, and
  installation and systematic operation of flushing equipment in a signifi-
  cant area of an actual  combined sewer system.

  The test equipment  to be built in Phase II consists  of 12"  and 18" diameter
  test sewers about 800 feet long,  supported above ground  so  the slope can
  be adjusted.  Flush tanks  will be provided at  three  points  along the
  test sewers.

  Based on extensive  tests with this facility, system  design  procedures
  and criteria for application  of sewer flushing systems will be determined.
  Flushing equipment  for  use in an  actual field  environment will be designed
  and built.
            Cottfii-t tkc. Storm and  Combined Sewer Pollution Control Branch
                                           and Ve.vs.topne.nt
                                      ?ol£uti.on Contfiot hdx\iruj>t nation
                        U.S.  r"ipci.fjjr>&it GO tkz Int&uo'c
                                  ,  P. C. 20242

                                  79

-------
 INFORMATION  SHEET~
           RESEARCH & DEVELOPMENT  GRANT
Tki& 4/ieet ducAi.ba& b^Ui^ty an R £ V Gfwjnt tmuidiLd undeA Sec. 5 ,
        WatM. Pollution Cont/iol Act(C£eon WcuteA Rutoiation Act).
GRANTEE:   Merrimack College
           Turnpike Road
           North Andover, Massachusetts  018^5

TITLE OF PROJECT: "Controlling Pollution from Combined Sewer Overflows
                   and Storm Water by Electrode Potential"

PROJECT SITE: North Andover, Mass.   PATE AWARPEP: December 22, 1^;8

FEPERAL GRA.VT; $21 . 63               TOTAL EST. PROJ. COST;  $4.5, tf <

PROJECT WAfBER; 1102^ DDK            PP8S NO.  1102


PESCRIPTIffl OF PROJECT;

To  investigate and demonstrate at the laboratory  level the feasibility
of  utilizing electrode potential measuring systems to indicate  the
strength  of  combined  sewage.  A secondary objective  of this demonstration
will  be determining the  feasibility  of  the incorpation of such  an
electrolytic circuit  in  a  control scheme to  regulate the flow  of
combined  or  other sewage by mechanical  means.
INQUIRIES;  Contact tht
                        0^ic.t o$ Re^eo^ch cud t?eve£opnent
                        Fe5e/ut£ (fate*  Po-t&ttcon  ConUiol
                        U.S. PeaA^jient  o  t'nz
                        Washington, V.  C.  20242

-------
INFORMATION SHEET -  - -
                    RESEARCH & DEVELOPMENT  CONTRACT
This sheet describes  briefly an R & D Contract awarded under Sec.  6,
Federal Water  Pollution Control Act  (Clean Water Restoration Act).
CONTRACTOR;   Ionics Incorporated
              65 Grove Street
              Watertown, Massachusetts 02172

TITLE OF PROJECT:   Feasibility of High Current Density Hypochlorite
                      Generation

PROJECT SITE;   Watertown, Mass.            DATE AWARDED;   Fgb _  ^

FEDERAL CONTRACT:   l!+_ 12-^90               TOTAL PROJ. COST:

PROJECT NUMBER; 11023 DM                 PPBS NO;
BRANCH CHIEF; William Rosenkranz, Chief    PROJECT OFFICER:  Allyn Richardson
       &  Combined  Sewer Pollution Control Br.                 Northeast Region
      L i J- -L\»/ii  \jr  JT t\\J
-------
I N F O R M A T I 0 N  S11 E E T
        RESEARCH  & DEVELOPMENT  CONTRACT
                     b.-U.e.tiy CM  RSV  CoiitM.c.£ auXL'idzd undeA Sec. 6,
        Woti>A PoiiLisUon Contnot
CPA/TRACTOR;  Water Resources Engineers, Inc.
             1900 Olympic Boulevard
             Walnut Creek, California  9^596
TITLE Or PROJECT:  TRIUMVIRATE., Storm Water Pollution Control Management
PROJECT SITE: Walnut Creek, California

FEPcRAL CONTRACT: $11^,860              PATF Afl'ARPEP; March U,  1969

PROJECT /.'q'.!S£R: 1^-12-501               PP8S .VO; 1102
          V OF PROJECT:  An eighteen  (l8) month program  to  develop  a
  comprehensive mathematical model capable  of representing  urban storm
  water runoff phenomena, both quantity and quality,  from the  onset of
  precipitation on the basin, through collection,  conveyance,  storage,
  and treatment systems, to points downstream from outfalls which are
  significantly affected by storm discharges.  The validity of the  model
  for simulating existing situations  will be demonstrated by applying
  it to several storm and combined sewer drainage  basins:   (l)  Storm
  sewers:  1 large and 1 small basin; (2) Combined sewers:  1  large and
  1 small basin.

  Development of the model is scheduled for twelve months and  demonstration
  is for a period of six (6) months.

  The Triumvirate of University of Florida,  Water  Resources Engineers,  Inc.,
  and Metcalf and Eddy, Inc. have joined together  (under the overall
  coordination of Metcalf and Eddy, Inc.) to develop  this working tool to
  assist municipalities in the management and* control for storm water
  pollution abatement.  Total project cost  is $513,650.
            Contact £/ie Storm and Combined  Sewer  Pollution Control Branch
                                         i/i and
                                       Pollution Cor^tot
                        U.S. PcjL\tt£>ia»:.£ o£ tin
                        533  iKctcaua Avenue, W.W.
                                     P.  C.  2 0242
                                  82
C-,-/:

-------
I N F O R M A T I O N  S11 E E T	
        RESEARCH  X  DEVELOPMENT  CONTRACT
T/;<'.5 -i/iee-t dc.>u.b&i>  b-U.n^ty a.;: R£P Cojo£>uie£ awxvuiec/ undent Se
                               £ Act
CONTRACTOR;  Metcalf and Eddy, Inc.
             1029 Corporation Way
             Palo Alto, California  9^303


TITLE Or PROJECT:  TRIUMVIRATE, Storm Water Pollution  Control Management


PROJECT SITE:  Palo Alto, California

FEDERAL CONTRACT;  $253,800             PATF Ah'ARPEP;  March k,  1969

PROJECT KU.'.!BER;  lU-12-502              P?BS MO;   1102
                (1102UDOC)
PESCRIFfl0,'J  OF  PROJECT:  An eighteen (18) month program  to develop a
  comprehensive mathematical model capable of representing "urban storm water
  runoff phenomena, both quantity and quality, from  the  onset of precipi-
  tation on the basin, through collection, conveyance, storage,  and treatment
  systems,  to points downstream from outfalls which  are  significantly
  affected by storm discharges.  The validity of  the model for simulating
  existing situations will be demonstrated by applying it  to several storm
  and combined sewer drainage basins:   (l) Storm  sewers: 1 large and 1
  small basin; (2) Combined sewers:  1  large and  1 small basin.

  Development of the model is scheduled for twelve months  and demonstration
  is for a period of six (6) months.

  The Triumvirate of University of Florida, Water Resources Engineers,
  Inc. and Metcalf and Eddy, Inc. have  joined together (under the overall
  coordination of Metcalf and Eddy, Inc.) to develop this  working tool
  to assist municipalities in the management and  control for storm water
  pollution abatement.  Total project cost is $513j650.
INCH/TRIES;   Contact tkt Storm and Combined  Sewer  Pollution Control Branch
                         0^-ice, 0(5 Reieaxie/t  r^icf Ve.vs.topne.tiX.
                         Fc.de.tiat U'oieA Pottution Contiot A.dnu^Utnation
                         U.S. Pef>oAxj)ietvt o^  ike. I
                         633 Ind-tano. Avenue, W.W.
                         WoA/'unf^ou, V. C. 20242
                                   83
C-//:

-------
INFORMATION  SHEET
        RESEARCH  &  DEVELOPMENT  CONTRACT
     &ke.e.t deAc.ij.bu  b'l.i.e.&ly an  R5P Contract auxt.ide.d undvi Sec. 6,
Fec/e/tnX fc'ateA Pottution  ContKot  Act {Cfean t'-'o/Cw Re.^.'iatum Aci) .
CONTRACTOR; University of Florida
            Department of Environmental Engineering
            Gainesville, Florida  32601
TITLE Of FHOJfcCT:  TRIUMVIRATE, Storm Water  Pollution Control Management
  .             Gainesville, Florida

FEPERAL CO^'RACT; $1^,990              PATE Afr'ARPEP; March 11,  1969

PROJECT M.WBER: 1^-12-503               PPRS WO;   1102
              " (11024EBJ)
gFSCR'/ KnO,V OF roOJECT :   ^ eighteen  (l8) month  program to develop a
 comprehensive matehmatical model capable of representing urban storm
 water runoff phenomena, both quantity and quality,  from the onset of
 precipitation on the basin, through collection,  conveyance, storage, and
 treatment systems, to points downstream from outfalls which are significantly
 affected by storm discharges.  The validity of the  model for simulating
 existing situations will be demonstrated by applying  it to several storm
 and combined sewer drainage basins:   (l) Storm sewers:   1 large and 1
 small basin; (2) Combined sewers:  1  large  and 1 small  basin.

 Development of the model is scheduled for twelve months and demonstration
 is for a period of six  (6) months.

 The Triumvirate of University of Florida, Water  Resources Engineers, Inc.
 and Metcalf and Eddy, Inc. have joined together  (under  the overall coordi-
 nation of Metcalf and Eddy, Inc.) to  develop this working tool to assist
 municipalities in the management and  control for storm  water pollution
 abatement.  Total project cost is $513,650.
            Contact, the.  Storm and Combined Sewer Pollution Control Branch
                        Oi^-ice o{>  Rg.5c.a-'tc/i and Vz.vtiop-;i°nt
                         fzd&iat (t'oicA  Pollution Co)i£>iot
                        U.S. VtfXVLtiMnt 0|J the. I
                         633 Indiana. Avenue, N.l'J,
                        Wa&hington, V. C.  20242

-------
 INFORMATION  SHEET
         RESEARCH  & DEVELOPMENT  CONTRACT
                           iij an RSV Cont>ia.c£ autt'tc/ed  undnt Sec.  6t
         UateA PolfaUon Control ktt \Cium Wat&i  Re.^.'i&ttott Ac*).
 CONTRACTOR; American Standard Incorporated
             P.O. Box 2003
             New Brunswick, New Jersey
 TITLE OF PROJECT;   "Develop a Suspended Solids Monitor"


 PROJKT SITE: New Brunswick, New Jersey

 FEPHRAL CONTRACT; $121,91*6             PATE Aft/ARPEP; March 28, 1969

 PROJECT MUMBER; i^-ie-l^              PPBS MO;  1102
                 1102U DZB
 DESCRIPTION OF PROJECT:

A suspended solids monitor for use in continuously measuring  suspended
solids in sewage will be developed and evaluated.  A new principal  for
such measurement, based on the measurement of light depolarization, will
be utilized.  Phase I of the project will determine feasibility of  the
technique, Phase II will accomplish design of the prototype instrument,
Phase III will involve selection and bench-scale testing of optical
components, and electronic components will be selected in Phase IV.
Phase V will consist of field standardization and calibration of  the
prototype in a sewage environment.
 lA/QUIRIES;   Contact the. Storm and Combined Sewer Pollution  Control  Branch
         ~               O^ice. o^ ReAeoAch and Ve\>e.t.opn
-------
I N FO R M AT I O N  S11 F, E T ~
        RESEARCH  K  DEVELOPMENT  CONTRACT
Thti 4/icc/t  1969

PROJECT MAI8ER:  1^-12-550              PPBS NO;   1102
                 11022 EFF
DESCRIPTION  OF PROJECT;

A 15 month study of the causes and control  of  storm and ground water
infiltration into sanitary and combined sewers  —  including investigation
of sewer design, construction, testing and  inspection,  and grouting
practices.  Specific objectives include:  (l)  catalog  the extent and
causes, (2) delineate the relative importance  of various sources,
(3) investigate present design criteria and practices,  (U) review present
construction,  testing and inspection practices  and techniques, (5) investi-
gate present infiltration detection, leak location and grouting techniques
and practices, (6) identify future research, development and demonstration
needs and (7)  prepare a "Manual of Recommended Practice".
 INQUIRIES:   Contact £hz Storm  and  Combined Sewer Pollution Control Branch
                         0^-U'ce OQ  RfcAa/W.c/1 and Vivc.topn;iotc
                         U.S. Pcpcytxi»ie>:-4  OQ the. In-tc/'u^o-t
                         533 Indiana. Averse,  A/.W.
                         WatliinQton, P. C.  20242
                                    86
 C-//:

-------
 INFORMATION GI1EET
                                                            Date to be Released

               RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT
       This Project is a Demonstration Grantunder sc.Cfu,n	
 Federal Wator Pollution Control Act (Clean Water Restoration  Act).


 GRAT-;TEE OR CONTRACTOR:  New York State Department of Health
 (Name and Address)8U Holland Avenue
 PROJECT DIRECTOR:
 (Name and Address)
Albany, New York  12208

Leo J. Hetling
(Address same as above)
 TlTLi  OF PROJECT:  "A Pressure Sewer System Demonstration"
 PROJECT SITE: Albany, New York
Grant or
Contract
Period
From: h/ 16/69
Thru: 12/70
Eligible
Grant
Period Costs
$311,800
FWPCA G. url
or Contract
Amount
$ 200,800
 PROGRAM (PROJECT) NUMBER:
         11022DQJ

 DATE_ OFFERED:
       March 2k, 1969

 DATE, ACCEPTED (AWARDED):
       April 16, 1969

 DESCRIPTION OF PROJECT:

The New York State Department of Health proposes a 21 month investigation to
install, demonstrate and evaluate a pressure sewer system which could be utilized
to separate sanitary sewage from combined sanitary sewage and storm water.  A
pilot-scale system will be designed to serve 11-12 houses in a redevelopment
area in Albany, New York,  presently served by combined sewers.  Prototype
pump-grinder units developed by the General Electric Company as a part of the
ASCE Contract (1^-12-29) would be utilized to convey sewage from the home to
the pressure sewer in the street.

Four principal objectives are incorporated in the project:  (l) monitoring,
evaluation of the prototype pump-grinder units to determine reliability and
need for modification or redesign.  (2) test durability of the units operating
singly and in concern (manifolded to common pressure sewer).  (3)  provide
proof of the field suitability of the assemblage, which should be considered
a module of a larger pressure system.  (U) provide new data which would be
invaluable in subsequent pressure system applications.

Four principal investigating entities would be involved in conducting the
project, each with assigned responsibilities:  New York State Department of Health,
New York State Pure Waters Authority, American Society of Civil Engineers and the
 INQUIRIES:   Contact Project Coordination Environmental Technology, Inc.
                      Office of Research  and Development
                      Federal Water  Pollution Control  Administration
                      U. S.  Department  of the Interior
                      Washington,  D.  C.    202^2
                                         8?

-------
INFORMATION GIIEET
                                     April 30, 1969
                                                           Date to be Released

              RESEARCH, DEVELOPMENT,  OR DEMONSTRATION PROJECT

      This Project is a Demonstration Grantunder Suction 6al    	,
JVdrral Watjr Pollution Control Act (Clean Water Restoration Act).

                        City of Dallas
GRAKIEE OR CONTRACTOR:  500  South Ervay Street
(Name and Address)      Dallas,  Texas  75201
PROJECT DIRECTOR:
(Name and Address)
A. E. Holcomb
TlTLi OF PROJECT:  "Use  of Polymers  to Reduce or Eliminate Sewer Overflow in
                    the  Bachman Creek Sewer"
PROJECT SITE:   Dallas,  Texas
Grant or
Contract
Period
From: 5/23/69
Thru: 6/23/71
Eligible
Grant
Period Costs
$ Mu,6U?
FWPCA <;• ^.'\
or Contract
Amount
$ 331,233
 PROGRAM  (PROJECT) NUMBER:
        11022DZU

 DATE OFFERED;
        April 23,  1969

 DATL ACCEPTED (AWARDED):
       May 23,  1969

 DESCRIPTION  OF PROJECT:
        The project consists  of the design,  construction and evaluation of a
        permanent polymer injection station  on the Bachman Creek Sewer in
        Dallas,  Texas.   The project will further demonstrate and evaluate a
        technique developed earlier for FWPCA by contract which utilizes
        injection of polymers into a sewer for the purpose of increasing
        the carrying capacity of the pipe.

        During periods  of wet weather the Bachman Creek sewer receives excess
        quantities of ground  or storm water  due to infiltration.  The flow
        then exceeds its carrying capacity and untreated wastes overflow in
        at least 10 locations, causing pollution of Bachman Creek.  The
        project  will seek to  eliminate or greatly reduce the number and volume
        of untreated overflows by increasing the flow capacity of the Bachman
        Creek Sewer through the addition of  polymers.  Design criteria,
        operating techniques, optimum polymer concentration and other
        pertinent data critical to the intended use will be evaluated.
 INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of tho Interior
                     Washington, D. C.   202^2
                                        88

-------
INFORMATION SHEET
                                                           Date to be Released

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT
      This Project is a Grant
                                          under Section
                                                        6al Demonstration
Federal Water Pollution Control Act(Clean Water Restoration Act).
GRAKZEE OR CONTRACTOR:  City of Akron
                        166 South High Street
                        Akron, Ohio  Ml-308
(Name  and  Address)
PROJECT DIRECTOR:  C. E. Susong
(Name and Address) City Engineer
                   166 South  High Street
                   Akron, Ohio  M+308
TTTLi OF PROJECT:  "Demonstration of Void  Space  Storage with  Treatment  and Flow
                    Regulation"
Grant or
Contract
Period
From: 5/23/69
Thru: 5/23/72
Eligible
Grant
Period Costs
$ 750,000
FWPCA >•>• '^'*
or Contract
Amount
$ 562,500
PROJECT SITE: Akron, Ohio


PROGRAM (PROJECT) NUMBER:
       11020DXH

DATE OFFERED;

       April 24,  1969
"DATE ACCEPTED (AWARDED):

       May 23, 1969
DESCRIPTION OF PROJECT:

       The project is to construct,  operate and evaluate  an underground storage/
       treatment facility for excess combined sewage.   The facility will include
       novel concepts in construction and operation.   It  will be an excavated
       hopper shaped cavity,  lined with an impermeable membrane, filled with an
       inert material covered with soil and the surface made useable.   Storage
       will be in the void space of  the fill.   The flow regulation of  influent
       will be a new and improved device, probably a fluidic regulator.  The.
       sewage will be pre-treated prior to entry to the storage facility.  Tube
       clarifiers will  be utilized to compare results  with an on-going project
       where these units are  being used for the first  time at an operational
       level on  combined sewage.
INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of tho Interior
                     Washington, D.  C.    202^2

-------
INFORMATION GREET
                                                           Date to be Released

              RESEARCH, DEVELOPMENT,  OR DEMONSTRATION PROJECT

      This Project is a Research Grant     under Section 5a2
Federal Water Pollution Control Act (Clean Water Restoration Act).
GRAKTEE OR CONTRACTOR:  University of Cincinnati
(Name and Address)Cincinnati, Ohio  ^5221
PROJECT DIRECTOR:    Herbert C. Preul, Ph.D., Dept. of Civil Engineering
(Name and Address)   University of Cincinnati, Cincinnati, Ohio  ^5221
TITL, OF PROJECT:   "Urban Runoff Characteristics"
PROJECT SITE: Cincinnati, Ohio
PROGRAM  (PROJECT) NUMBER:
Grant or
Contract
Period
From: 6/23/69
Thru: 6/23/70
Eligible
Grant
Period Costs
$ 55,690
FWPCA ';• '^\
or Contract
Amount
$ 52,905
first year)
DATE OFFERED;
       May 28, 1969

DATE ACCEPTED (AWARDED):
       June 23, 1969

DESCRIPTION OF PROJECT:
       The intent of this first year of a proposed three year research project is
       to collect, for the first time, detailed information defining the physical
       characteristics of an urban drainage area tributary to a combined sewer
       drainage system and detailed data relating to the quantity and quality of
       various sources of pollution within the combined sewer drainage area.
       Generally in the past, data have been collected only at the actual overflow
       location from a drainage area.  The collection and evaluation of data, from
       within the tributary drainage area will provide valuable insights regarding
       methods for controlling the strength and volume of combined sewer overflows.

       A comprehensive storm water management mathematical model is presently
       under development for predicting the quantity and quality of combined sewer
       overflows.  The detailed data collected will be utilized for verification
       and utilization of this model by communities needing a working tool for
       development of combined sewer overflow abatement programs.
INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of the Interior
                     Washington, D. C.   202U2
                                        90

-------
INi'OKMATION SHEET
                                                           Date to be Rolcacc.d

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT

      This Project is a Re search Grant    , under Section 5a(2)	,
Federal Water Pollution Control Act (Clean Water Restoration Act).
GRANTEE OR CONTRACTOR;  Lehigh University
(Name and Address)Bethlehem, Pennsylvania  18015
PROJECT DIRECTOR;
(Name and Address)
TITL£ OF PROJECT:
W. H. Graf, Associate Professor of Civil Engineering
Lehigh University
Bethlehem, Pennsylvania  18015

"Transport of Solid Suspension in Conduits"
PROJECT SITE:
Bethlehem, Pennsylvania
Grant or
Contract
Period
From: 7/1/69
Thru: 6/30/70
Eligible
Grant
Period Costs
$ Ul,095
(1969-70)
FWPCA Grstnt
or Contract
Amount
$ 37,000
PROGRAM (PROJECT) NUMBER;
       11024 EKD

DATE OFFEREDi
       June 12, 1969

DATE ACCEPTED (AWARDED);
       June 19, 1969

DESCRIPTION OF PROJECT:
       The objectives of this two-part project are:

       1.  To continue the investigation and determination of design
           criteria for minimum transport velocities of non-depositing
           solid-liquid mixtures in pipe lines.

       2.  To further develop a modified Venturi meter to measure mixture
           flow rate and concentration simultaneously.

       The benefits would include improved design and operation of pressure
       lines for the transport of ground sanitary sewage.  Such pressure
       lines would be used for combined sewer separation and control of
       overflows of combined sewage to streams, as developed by the
       combined sewer separation project of the American Society of Civil
       Engineers (FWPCA contract no. lU-12-29).
INQUIRIES:    Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U.  S.  Department of the Interior
                     Washington, D.  C.   202^2
                                         91

-------
INFORMATION G11EET
                                                           Date to be Released

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT

      This Project is a  Contract        ; under Sect ion 6al    	,
Federal Watjr Pollution Control Act (Clean Water Restoration Act).
GRATMEE OR CONTRACTOR:  Battelle Memorial Institute
 (Nameand Address)
PROJECT DIRECTOR:
(Name and Address)
 TITLi OF PROJECT:
     Pacific Northwest Laboratory
     P.O. BOX 999
     Richland, Washington  99352
     Allen J. Shuckrow
     Pacific Northwest Laboratory
     Battelle Memorial Institute
     Richland, Washington  99352
"Development, Demonstration and Evaluation of Physical-
 Chemical Treatment of Combined Storm-Sanitary Sewage"
 PROJECT  SITE:  Richland, Washington, and selected field sites
Grant or
Contract
Period
From: 6/23/69
Thru: 12/23/72
Eligible
Grant
Period Costs
$ 391,310
FWPCA ')"ur
-------
INFORMATION SHEET
                                                           Date to be Released

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT

      This Project is a Demonstration Gran,t under Section Sal	,
      l Wat or Pollution Control Act (Clean Water Restoration Act).
GRAT-:TEE OR CONTRACTOR:
(Name and Address)
PROJECT DIRECTOR:
(Name and Address)
City of Kenosha
100-51st Place
Kenosha, Wisconsin
Mr. 0. Fred Nelson

Rex-Chainbelt Technical Center
5101 West Beloit Road
West Milwaukee, Wisconsin  532lU
TiTLi OF PROJECT:  "Demonstration Project  of Biological Absorption of Pollutants
                    from Combined Storm Water Runoff and Sanitary Sewage"
PROJECT SITE:   Kenosha,  Wisconsin
PROGRAM  (PROJECT) NUMBER:  H023EKC
Grant or
Contract
Period
From: 9/10/69
Thru: 6/10/72
Eligible
Grant
Period Costs
$ 730,000
FWPCA '}• ur't
or Contract
Amount
$5^500
DATE OFFERED;   July 23,


DATE, ACCEPTED (AWARDED):

      September 5, 19&9

DESCRIPTION OF PROJECT:

  The project  objective is  to provide a means  for high rate biological treatment
  of combined  sewage by the utilization of viable, activated sludge,  clarification
  and disinfection.   The method will be to store sludge in a biosolids reservoir
  and maintain a contact tank and solids stabilization tank in an empty and ready
  condition at the sewage treatment plant.

  When  a rain  event  occurs  the excess combined sewage will be directed to the
  contact tank and the activated sludge proportionally introduced.   The tank
  will  be designed to have  15-30 min contact time.  From the contact tank the
  flow  will be directed to  a clarifier for solids separation.  The  effluent
  will  be disinfected and discharged to Lake Michigan with solids returned
  to the solids  stabilization tank and reused or wasted to the digesters.
INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of the Interior
                     Washington, D. C.   202^2

                                         93

-------
INrOIiMATION SHEET
                                                           Date to be Roleaced

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT

      This Project is aDempnstration Gratifr under Section 5                 ,
Federal Water Ttollution Control Act (Clean Water Restoration ActJ.
GRANTEE OR CONTRACTOR:  Tulane University
(Name and Address)New Orleans, Louisiana 70118
PROJECT DIRECTOR:
(Name and Address)
TITLr] OF PROJECT:
Dr. Frank W. Macdonald
Professor of Civil Engineering & Public Health
Tulane University

"Bedding and Infiltration Studies of Sanitary
Sewers in the Gulf Cost Area"
PROJECT SITE:
New Orleans, Louisiana
Grant or
Contract
Period
From: 9/18/69
Thru: 2/lU/Tl
Eligible
Grant
Period Costs
$ 31,385
FWPCA G.-ant
or Contract
Amount
$ 23,538
PROGRAM (PROJECT) NUMBER;
       11022 DEI

DATE OFFERED;
       August  25, 1969

DATE ACCEPTED (AWARDED);
       September 18,  1969

DESCRIPTION OF PROJECT:
       This is  a continuation  grant  for  the  fifth and final year  of a
       Demonstration  grant.  The  objectives  are to determine the  best
       type of bedding  arrangements  and  the  most suitable materials to
       be  used in laying sewer pipes in  the  Gulf Coast Area.  Investi-
       gations  will also be  conducted on the performance of manholes,
       tees and other appurtenances.  Infiltration studies  will continue
       of  three in-use  sections of sewer lines.  This final year  will be
       used in filling  voids in the  needed data, and the preparation of
       the final report which  will contain a "Manual" section of  recommended
       materials and  practices.
INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of the Interior
                     Washington, D. C.   202^2

-------
 ;•,, j; CATION SliEET
                                                           Date t.r, L-. Rc'lrar:- d

              RESEARCH, DEVELOPMENT, OR DEMONSTRATION PROJECT
                   is a Demonstration Grantunder Sectional)
Federal Water Pollution Control Act(Clean Water Restoration Act).
GRANTEE OR CONTRACTOR:  City of Rohnert Park, California
                        1+35 Southwest Boulevard
                        Rohnert Park, California  91+928
(Nameand Address)
PROJECT DIRECTOR:
(Nairn and Address)
TITLi. OF PROJECT:
PROJECT SITE:
                       John A. Voegtle,  P.E.
                       Yoder/Orlob Associates
                       1900 Olympic Boulevard
                       Walnut Creek, California   91+596
                       "Treatment of Peak Wet Weather Wastewater Flows,
                       and Rate Control  of All Wastewater Discharges
                       to Interceptor Sewers"

                       Rohnert Park, California
Grant or
Contract
Period
From: 10/10/69
Thru: 7/10/72
Eligible
Grant
Period Costs
$ 1+01,300
FWPCA 0' unt
or Contract
Amount
$299,500
PROGRAM (PROJECT) NUMBER-.
       11023 DSX

DATE OFFERED;
       September 18,  1969

DATE ACCEPTED (AWARDED):
       October 10,  1969

DESCRIPTION OF PROJECT:
       Inflow of storm water to the City of Rohnert Park sanitary sewer
       system causes  peak wet weather flow of up to 10 times the average
       dry weather  flow.  As a result, the treatment plant becomes
       ineffective  for a period of several weeks.

       A new combined sedimentation and flow equalization pond would be
       constructed  to include an unique sludge collection system for use
       during wet weather and an aerator for dry weather use only.  All
       excess wet weather overflow from this pond would be delivered to
       a storage and  chlorination pond (the existing oxidation pond), and
       would be released to the receiving stream after about two days
       detention and  chlorine contact.  Dry weather flow and solids collected
       in the equalization pond would underflow to the existing primary
       sedimentation  basin and sludge digester.  Achievement of a nearly
       constant underflow would serve to demonstrate its effect on operation
       of the existing facility, and to demonstrate the feasibility of
       designing a  less costly interceptor sewer for later transport of
       the underflow  to a Regional treatment plant.  Extension of this
       system to other plants in the area could serve to reduce the cost
       of a Regional  plant.
INQUIRIES:   Contact  Project Coordination
                     Office of Re1 search and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of the Interior
                     Washington, D. C.   20?'+2

-------
INi'OiiMATION SHEET
                                                           Date tn b« RoJcaccd

              RESEARCH, DEVELOPMENT,  OR DEMONSTRATION PROJECT

      This Project is a Contract         ,  under Section 6a(l)	,
Federal Water Pollution Control Act (Clean  Water Restoration Act).
GRANTEE OR CONTRACTOR;   Roy F. Weston
(Name and Address)
PROJECT DIRECTOR;
(Name and Address)
TITLK OF PROJECT:
Environmental Scientists and Engineers
Lewis Lane
West Chester, Pennsylvania  19380
Micheal Neijna
Roy F. Weston
Lewis Lane
West Chester, Pennsylvania  19380
"Kingman Lake Recreational Area - Phase One
Engineering Investigation"
PROJECT SITE:
Washington, D.C.
Grant or
Contract
Period
From: 12/69
Thru: ^ or 5/-J
(21 weeks)
Eligible
Grant
Period Costs
Q$ 137,750
FWPCA Grant
or Contract
.Amount
$137,750
PROGRAM (PROJECT) NUMBER;
       11023 FIX
       Contract No. 1^-12-829
DATE OFFERED:
DATE ACCEPTED (AWARDED);
       December 29, 1969

DESCRIPTION OF PROJECT:
       This 21 week, $137,750 project will be an engineering  investigation
       to develop design parameters and preliminary costs for the design
       of a combined sewer overflow treatment facility, including soils
       information necessary for construction.  Basic quality and quantity
       information on  the combined sewer overflows from the Northeast
       Boundary Trunk  sewer, Washington, D.C., will be defined.  Overflows
       from this outfall will be treated and used for recreational purposes
       in the Kingman  Lake Recreational Area.
INQUIRIES:   Contact Project Coordination
                     Office of Research and Development
                     Federal Water Pollution Control Administration
                     U. S. Department of the Interior
                     Washington, D. C.   202^2
                                         96

-------
GRANTEE

City of South
St. Paul, Minn.,
11031 DSL

City of LaSalle,
111., 11032 DTI
t>.  Storm Water Discharges

            GRANTS

  PROJECT OFFICER       PROJECT MANAGER
  Clarence Oster
George Kirkpatrick
  Clifford Risley, Jr.  Francis Condon
PAGE

 99



 100
CONTRACTOR

AVCO - Economic
Systems Corp.,
lU-12-18?
                              CONTRACTS
  PROJECT OFFICER
  George Putnicki
PROJECT MANAGER
Darwin Wright
PAGE
                                 97

-------
I N F O R M A T ION  S H E E T
        RESEARCH  & DEVELOPMENT  CONTRACT
ThU, 4/ieei ducM.bu fruity an KSV Contract auoa.nde.ct undeA Sec.  6t
      t KattiL PottwUon Control Act ICtuui WatM. Re.\*.»TatuM Act).
             AVCO-Economic Systems Corporation
             1701 K Street, N. W.
             Washington, D. C.  20006
                ;  "Develop the Relation between Land-Use Practices
                   and Influence of Pollution in Urban Storm Water"

                Tulsa, Oklahoma

               L: $11^,300.00          PATE AWARPHP;  June is, 1968
              :   W-12-187               8SWO;   "03
  AVCO proposes to develop the relationship between land-use practices
  and incidence of pollution in urban stormwater runoff.  Means of
  analyzing and evaluating the extent and degree of pollution resulting
  from urban areas of varying land-use patterns will be developed
  utilizing Tulsa, Oklahoma as the subject area.  Based on the findings
  of field investigations, a recommended program for corrective measures
  emphasizing regulatory controls of the area, such as improved urban
  planning, zoning and regulations of land-use will be developed.

  During the 18 month study, AVCO will monitor the storm water runoff
  from fifteen sampling sites.  The data will be stored in STORET and
  subsequently used in the mathematical model along with the land-use data.
  An IBM Sytem /360 will be used for the mathematical model for pollu-
  tion incidence determinations. Mathematical relationships will make
  use of a regression technique and principal component analysis.
INQUIRIES:  Con-tact -t/ie Storm and Combined Sewer Pollution Control  Branch
                               0(5 Rese/tAc/i and
                                W
-------
               INFORMATION SHEET~~
                         RESEARCH &  DEVELOPMENT GRANT
                 A A/iee£ dtf>cju.bi& bntt^ty an R S V Giant cua&Adejd undeA Sec.  6,
                      W&tvi Pollution Control Ac£(C£ean Wate&  Rea-toiotuw
              GRANTEE;  City of South St.  Paul, Minnesota
              TITLE OF PROJECT;  Demonstration Project for Temporary Detention of
                                 Storm and Combined Sewage in Natural Underground
                                 Formations
              PROJECT SITE: South St.  Paul, Minn.   PATE AWAKPEP:  July 22,  1968

              FEPERAL GRANT; $385,000              TOTAL  EST.  PROJ.  COST;  $380,000

              PROJECT ffl/HBER:  11031 DSL           PPBS NO.  11Q3


              PESCRIPTION OF PROJECT;
Natural permeable underground strata in the South St. Paul area will be used to demonstrate
their capacity for the temporary storage of both storm water and combined storm water and
sewage during periods of storm runoff.  Deposits of alluvium, or gravel, which are
approximately 100 feet in depth are to be located for this purpose by drilling in
favorable locations.

Prior to introduction of the waste waters into the ground, they must be treated by
removal of suspended solids, and will be chlorinated, if necessary, to eliminate danger
of contaminating adjacent sources of water supply.  The capacity for rapid pre-treatment
and movement of large volumes of waste water into the ground must be demonstrated if
the system is to prove feasible.

Waste water thus entering the ground during storms will be pumped out over a period of
several months.  If the quality of this water meets the required standards, it can be
returned directly to the streams.  Otherwise, it will be  transported'to the sewage
treatment plant.

Prior to introduction of waste water into  the underground formation, city water will
be used to test the direction, rate of movement, and quality of water in the ground
through use of observation wells.
               INQUIRIES;   Contact the. Storm and Combined Sewer Pollution Control Branch

                                      federal WateA Pollution Contfiot
                                      U.S. VepaAtrnznt o& the.

                                      Wtuhindtan,  V.  C. 20242

                                               99

-------
 INFORMATION GIIEET
                                                            Date to be Released
               RESEARCH, DEVELOPMENT,  OR DEMONSTRATION PROJECT

       This Project is a Grant            ,  under Sc-ctiun6al
 Fodrral Water Pollution Control Act (Clean Water Restoration Act).
 GRAKTEE OR CONTRACTOR:   The City of LaSalle, Illinois
 (Name and Address)
 PROJECT DIRECTOR:
 (Name and Address)
 TITLi OF PROJECT:
 Chamlin and Associates
 3017 Fifth Street
 Peru, Illinois  6l35^

"The Construction and Technical Evaluation of the
 Various Aspects of an Aluminum Storm Sewer System"
 PROJECT SITE:  LaSalle, Illinois
Grant or
Contract
Period
From: 6/23/69
Thru: 11/23/72
Eligible
Grant
Period Costs
Total $958,068
Eligible$^76,368
FWPCA '/• ur't
or Contract
Amount
$1+32,276
 PROGRAM  (PROJECT) NUMBER:
     11032DTI

 DATE OFFERED;
June 13, 1969

 DATE ACCEPTED (AWARDED):
June 23, 1969

 DESCRIPTION  OF PROJECT:

The City of LaSalle will demonstrate the correction of combined sewer overflow
problems by constructing a separate storm drainage system for a portion of the
city.  Engineering study indicates that this is the most economical solution
for LaSalle.  The development and demonstration aspects will be:

(a)  The installation and evaluation of performance, durability and dependability
     of various size corrugated aluminum pipe, (b) prototype development and
     evaluation of improved joint couplers, tapping saddles, catch basins and
     manholes, (c) a detailed cost analysis to" allow comparison of aluminum
     pipe with commonly used sewer material, and (d) a construction practice
     evaluation for future installation guidance.
  INQUIRIES:   Contact Project Coordination
                      Office of Research and Development
                      Federal Water Pollution Control Administration
                      U. S. Department of the Interior
                      Washington, D. C.   202^2
                                        100

-------
                    c.  IIOU Non-Sewered Runoff
                              GRANTS

GRANTEE              PROJECT OFFICER       PROJECT MANAGER         PAGE

University of        Robert Buckley        George Kirkpatrick      102
Michigan,
110^4-1 DRS
                                101

-------
  INFORMATION  SHEET
            RESEARCH &  DEVELOPMENT  GRANT
 T/u,4 Aiitvt rfodcJtt.6p.-A bvlcl^t/ an R 6 V &wjtt otwirfed (inrfe*. Sec.  6,
               Pot£n£uw Cvutkat Ac£(C£aan Wote/t Re-a-toAotion Act).
           The Regents of the University of Michigan
           Ann Arbor, Michigan


 TITLE OF PROJECT; "Rainfall-Runoff Relations on Urban (and Rural)
                    Areas"
                        1

 PROJECT SITE: Detroit, Michigan      PATE AWARPEP;

 FEERALGAfT: $18,986               TOTAL EST.  PROJ. COST;  $20,085 (1968-69)
 PROJECT K'(MBER:  iio^l DRS           PS HO.
             OF
Objectives of the project are to gain a better understanding of the factors
which control the relationship between storm rainfall, or snow melt, and
the resulting st«rm runoff, and to determine the effect of urbanization
on this runoff process.  The benefits would include prevention of flo»d
damage by means »f improved design of storm sewers and waterways, and
would provide data needed- for the improved design and operation of
facilities f»r control of pollution due to storm water and/ or combined
sewage.
 INUIRIES:  Contact the. Storm and Combined Sewer Pollution Control Branch
                                 Wcut&i Poilmtwn Contnot
                         U.S. Vt£-&itrt\2jijt o^  the.
                         633 7:-''>.^ Ave.  H.W.
                                -ion,  V.  C.  20242

                                   102

-------
          d.  1503 Control of Pollution from Construction

                              GHAUTS

GRANTEE              PROJECT OFFICER       PROJECT MANAGER         PAGE

National Association Darwin Wright         Darwin Wright
of Counties,
15030DTL
                                103

-------
  INFORMATION SHEET
            RESEARCH  & DEVELOPMENT  GRANT
      4/tc.e^: doatyuJbea  bfu.ti.fity an R 6 V Gmcjit cwwidzd undeA Sec, 6,
          at&i  Pot&tticn Control Aei{C££0.;i W&t&i tt&>£o?i&£,ion Act).
 GRAMTEE:  National Association of Counties  -  Research Foundation
           1001 Connecticut  Avenue,  N.W.
           Washington,  B.C.   20036

 TITLE OF  PROJECT:  "Community Action Guide  for  Erosion and Sedimentation
                     Control"

 PROJECT SITE:  Washington,  B.C.        PATE AOIARPEP:  February 11,  1969

                                                                $56,5^3
                :  15030DTL             ™-   15°3
 PJESCRI TTlQl{_01r PRO JegT :
The National Association of Counties-Research Foundation will develop a
"Community Action Guide for Erosion and Sedimentation Control" to impress
on local officials by providing comprehensive information on all aspects
of planning, operations, financing, staffing and management of such
programs.  Successful case studies will be reviewed and evaluated.   In
addition, the grantee will prepare a  preliminary State-of-the-Art report
on erosion and sediment at i'on control for urban and rural problems based
upon knowledge gained during interviews for the "Guide" .  Specific
Research and Development needs will be defined.
  INQUIRIES:  Contact tkt Storm and Combined Sewer Pollution Control Branch
         ~                               LC.h.axd Vtvztopnmt.
                                        PoUtuZLon Confjiol
                          U.S. Vz
                          633 Zfottona Ava. W.W.
                                   ,n, V. C. 20242

-------
               SECTION 14
        U.S. DEPARTMENT OF THE INTERIOR




FEDERAL WATER POLLUTION CONTROL ADMINISTRATION






 PERTINENT AREAS FOR RESEARCH AND DEVELOPMENT




  STORM AND COMBINED SEWER POLLUTION CONTROL
                  JULY, 1968





                   105

-------
     The problem of pollution from storm and combined sewers is one
which has only recently begun to receive proper emphasis as a signi-
ficant pollution source.  There are in the United States over 1900
communities with combined or partially combined sewerage systems
serving some 59 million people.

     The discharge of polluting wastes from storm drainage systems
and overflows from combined sewers serves as a distinct challenge to
the ingenuity of minicipal officials, consulting engineers, universities
and corporations engaged in research and development, as well as equip-
ment manufacturers.  Polluting discharges from combined storm and
sanitary sewers occur during wet-weather periods when the carrying
capacity of the sewers is exceeded due to the large amounts of storm
water entering the sewers.  The normal, or dry weather flow is prevented
from overflowing continuously by means of overflow weirs, mechanical
regulators, valves and other devices.  They permit overflows to occur
when sewer flows reach a predetermined level.

     Separation of the storm water from the sanitary sewage can be
at least a partial answer to the problem since if the systems are
completely separated the most concentrated waste load can be conveyed
to and treated at the waste treatment plant.  We have come to recognize
in recent years, however, that surface runoff also contains significant
amounts of pollutants - some cases nearly as much as sewage - so
that separation of sanitary wastes is now believed to be only a partial
solution to the total problem.

     Congress had these factors in mind when the current storm and
combined sewer pollution control demonstration grants were authorized.
Section 6 (a) (l) of the Federal Water Pollution Act authorizes "	
grants to any State, municipality, or intermunicipal or interstate
agency for the purpose of assisting in the development of any project
which will demonstrate a new or improved method of controlling the dis-
charge into any waters of untreated or inadequately treated sewage or
other wastes from sewers which carry storm water or both storm water
and sewage or other wastes 	."  The Federal Government can provide
up to 75 percent of the estimated reasonable cost of individual research,
development and demonstration projects.  The applicant must provide
assurances that local funds are or will be available to pay for the
remainder of the cost.  Application for contract support for pertinent
research and development projects will also be considered.

     The necessary application forms and more detailed information
concerning the Program can be obtained by writing to:

           Office of Research and Development
           Federal Water Pollution Control Administration
           U.S. Department of the Interior
           633 Indiana Avenue, N. W.
           Washington, D. C. 202^2
                                   106

-------
     By way of assisting those who wish to participate in the task
of controlling or abating pollution- from storm and combined sewers
the following outline of technical areas for which applications
are desired is provided:

A.  DRAINAGE AREA CONTROL

    1.  Reduce and regulate stormwater input to sanitary sewers

        a.  Diversion of surface runoff to the ground water by
            altering and controlling land use to increase infiltration
             1.  Reduction of impervious areas - increasing open spaces
             2.  Terracing and otherwise reducing land slopes through
                 landscaping
             3.  Planting grasses, trees and shrubbery
             ^.  Reducing extent and time of exposure of bare earth
                 during land development and construction

        To.  Shallow pervious basins for percolation to ground water
            or use sprinklers

        c.  Ground water disposal wells (injection & others)

        d.  Reduction of ground water infiltration to sewers
             1.  Development of better methods of determining location
                 and extent of sewer infiltration
             2.  Development of better sewer Joints, lateral connections,
                 etc.
             3.  Development of better methods of repairing existing
                 lines, making new installations and closing of abandoned
                 connections

        e.  Storage of stormwater runoff
             1.  Temporary storage of stormwater at building or immediate
                  area through use of holding tanks, seepage pits, roof-
                 tops, or backyard storage (detention) facilities.  Regu-
                 lated discharge from storage to the groundwater, a
                 watercourse, or sewer system
             2.  Stormwater collection sumps (neighborhood) with regulated
                 discharge to sewer system (includes storage facility •under
                 streets)
             3.  "Upstream" storage or other control methods to decrease
                 runoff effect on lower portions of the system
             U.  Stormwater storage in urban area surface lakes, ponds,
                 caverns, for subsequent discharge to watercourse or
                 sewer systems
             5.  Storage and operating characteristics necessary for
                 snowmelt runoff
             6.  Reuse of stored water for irrigation, street cleaning,
                 sewer flushing and other purposes
                                     107

-------
     2.   Eliminate discharge of sanitary sewage  and other wastes
         to storm sewers

          a.  Eliminate illicit connections of sanitary sewers where
              separate sewers exist

          b.  Reduce groundwater infiltration to storm sewers

          c.  Separation and collection of concentrated waste materials
              on the surface for discharge to sanitary or industrial
              waste sewers.   (Animal waste, industrial materials  and
              waste projects, sludges,  etc.)

     3.   Reduce solids in storm runoff

          a.  Soil erosion control
               1.  Highway,  street, and utility  construction methods
                   and practices changes
               2.  Use of solids retaining pond, basin, or other  type
                   unit with necessary  treatment
               3.  Grass seeding and other type  plant coverage of exposed
                   earth

          b.  Improved street cleaning  and urban "housekeeping" methods
              to prevent solids from reaching the sewers

     !+.   Pre-treatment of water entering storm sewers

          a.  Disinfection only

          b.  Primary clarification with modifications (with and
              without chlorination or other type disinfectants)

          c.  Lagoons, ponds, tanks with solids  holding capacity
              for given period

          d.  Filtration

          e.  Treatment for nutrient removals

          f.  Treatment or storage in catch basins

          g.  Other treatment methods and processes or combinations
              of the above including chemical treatment
B.  COLLECTION SYSTEM CONTROL

     1.  Improvements in gravity sewer system
                                 108

-------
             a.   Catch basin improvements including operation and
                 maintenance practices

             b.   Sewer planning and controls to regulate time of flow
                 during heavy starmwater periods,  including sewer
                 flood flow routing techniques, travel time, etc.

             c.   Improved sewer shapes and materials to improve flow
                 conditions, (lower' "n") better sewer connections and
                 manhole flow channels

             d.   Increase trunk and interceptor design capacity

             e.   Improved system design methods utilizing best hydro-
                 logical practices
2.  Special conveyance systems
             a.  Limited separation of combined sewers with express
                 sewer construction for sanitary waste

             b.  Partial separation
                  1.  Separate drains for streets,  yards,  parking lots,
                      new buildings, etc.
                  2.  Phased separation of sewer systems in all new areas
                      to be sewered and redeveloped.   While this method
                      could have significant long-range beneficial effects,
                      demonstration grants for separation of sewers are  not
                      envisioned
                  3.  Preventing stormwater flows in separate systems from
                      being discharged to combined sewers
              c.  Separation of sanitary sewage and use of separate sewer
                  inside larger sewers where available to convey sewage
                  to treatment plant

              d.  Use of vacuum conveyance systems  for sanitary sewage
                  & solid wastes
              e.  Others

3.  Reduce peak flows
              a.  Diversion of excess flow from combined sewer to external
                  facilities for storage and regulated feed back to system
                  for treatment
              b.  In-line treatment to improve flow conditions

              c.  In-line detention through use of enlarged segment of
                  sewer
              d.  In-system detention of waste and stormwater through
                  telemetering or other type signaling systems with
                  remote control on flow.
              e.  Reduction in water use through improvements in plumbing
                  fixtures
                                109

-------
       k.  Reduce infiltration and exfiltration

            a.  Development of improved methods of locating sewer
                •leaks} checking out new sewers, laterals  and house
                lines

            b.  Development of new and better methods and materials
                for making sewer repairs,  closing abandoned openings
                and construction in general

            c.  Development of methods of sealing sewers  in place,
                internally and externally,  to reduce infiltration

            d.  Improved means of implementing control of illicit
                "clearwater" connections to sewers

       5.  Systems analysis and control methods

            a.  In-line (internal) storage with telemetering and
                remote or automatic flow control

            b.  External storage in tanks,  ponds, etc. for feed back
                with automatic control system

            c.  In-system routing of stormwaters to utilize full storage
                capacity of system and subsequent treatment

            d.  Others and combinations of (a), (b), (c)   (including
                periodic dry weather flushing to move solids deposited
                in sewers, and better sewer maintenance in general)


C.  EXTRANEOUS (EXTERNAL) DISCHARGE CONTROL

       1,  Treatment of combined sewer overflow

            a.  Treatment at or near point of overflow through use
                of conventional type primary treatment units or ponds,
                tanks, lagoons with chemical treatment and chlorination.
                Other types of treatment facilities or processes.

            b.  Use of subterranean holding basins with treatment
                facilities

            c.  Expansion or additions to existing treatment plants to
                treat excess flow

            d.  Nutrient removal

            e.  Treatment with return of concentrate to interceptor for
                further treatment at sewage treatment plant
                                 110

-------
       2.  Treatment of stormwater runoff

            a.  Small drainage area plants vs. central plant utilizing
               " new or improved methods of treatment

            b.  Utilization of upstream storage to cut peaks and
                control plant input

            c.  Pre-treatment and direct ground water replacement

            d.  Irrigation by spreading, spray or other methods

            e.  Treatment and use as supplement to raw water supply

            f.  In-line treatment

            g.  Others
D.  MISCELLANEOUS
       1.  Determination of economic feasibility study of separation
           vs. combined sewer system and local vs. central treatment
           facilities for overflow and stormwater.

       2.  Development and demonstration of new or Improved accurate
           instruments for flow measurement and water quality monitoring.

       3.  Development and demonstration of improved techniques of hydro-
           logic analyses, to determine reasonable accurate rainfall -
           runoff relationships.  Compilation of sources of existing
           data and development of improved statistical methods.

       k.  Management techniques geared to optimize control and/or
           treatment through utilization of new methods.

       5.  Development of improved construction materials and methods

       6.  Development of performance criteria needed in relationship
           to stream water quality standards
     It should be noted that the above outline is not considered to be
all-inclusive, since there may be numerous completely original ideas
which could be added — some of which may be more significant than any
of those listed.  Submission of such ideas to the Federal Water Pollution
Control Administration is strongly encouraged.

     Some of the technical areas outlined are currently under evaluation
by means of either grant or contract projects, for example:   Most of the


                                  111

-------
more conventional storage techniques including the use of tanks with
pump-back to the interceptor, surface storage ponds, treatment lagoons
are underway.  More unique applications of storage principals such as
localized "upstream" storage to prevent overloading of "downstream"
sewers need further development.  The use of chlorine to disinfect
storm and combined sewer discharges is included in several projects,
therefore new disinfection techniques suitable for application to
high volume — short duration flows need exploration.  Similar
examples can be found in any of the major technical areas listed.

      The brief descriptions of existing demonstration projects will
 serve as additional examples of work being done.   Any further duplication
 of these control methods will be minimized as much as possible to permit
 activation of projects designed to explore technical areas not now being
 evaluated.  Some duplication will be in order so as to provide evaluation
 of function under a suitable variety of hydrological conditions.
                                                             GPO 881-412
                                    112

-------
                                  SECTION 5
                  URBAN DRAINAGE RESEARCH AND DEVELOPMENT
           IN THE FEDERAL WATER POLLUTION CONTROL ADMINISTRATION
Program Plan for Urban Drainage Projects in the Storm and Combined Sewer
     Pollution Control Branch, Division of Engineering Development
                       Outline of Requirements  for
                  Equipment, Data, Methods,  and Criteria
                                     113

-------
 I.  Instrumentation - Equipment for obtaining hydrologic measurements  and
     chronologic records

     A.  Measurement of individual parameters

         1.  Precipitation—rain and snow

         2.  Flow in sewers  and streams

             a.   Very low flows

             b.   Flash floods

             c.   Sand channels

         3.  Time of travel  in  sewers and streams

         k.  Fluid turbulence and dispersion

         5.  Chemical and bacterial quality, sediments,  and  bed  load

         6.  Soil moisture

         7.  Other

     B.  Time -  synchronous  measurements of parameters,  such as  synchronized
         measurement of rainfall and flow at short time  intervals  for
         rainfall-runoff analyses in small basins

     C.  Transmission of data

     D.  Adaptation of equipment to automatic  data processing, particularly
         the development of  equipment to collect rainfall records  and to
         transfer them automatically to a machine  input  media

II.  Data Collection

     A.  Compilation of existing rainfall and  flow data  of  sufficient
         geographic distribution, length of record, and  temporal and
         quantitative accuracy  for deriving useful rainfall-runoff
         relationships

     B.  Compilation of existing data on quality of flows in combined sewers
         and streams.  Include  data on quality of  low flows  and  distribution
         of quality with time and discharge during periods  of storm flow

     C.  Classification and  selection of urban areas for the collection of
         basic hydrologic data

     D.  Development of theory  for the design  of hydrologic  data networks

     E.  Implementation of pilot programs for  the  collection of  basic
         hydrologic data


                                     Ilk

-------
      F.  Nationwide inventories of existing drainage  systems.   These  may
          include complete descriptions of the  systems,  data on construction
          costs, including design and engineering,  evaluation of performance,
          flood damage experience, outstanding  deficiencies,  methods of
          financing, esthetic characteristics,  public  understanding and
          acceptance, public health hazards, recreational aspects, legislation
          and ordinances affecting the system,  and  administrative and  opera-
          tional experience.

III.  Rainfall Studies and Analyses

      A.  Determination of basin rainfall from  point gage readings

      B.  Temporal distribution of rainfall

      C.  Synthesis of rainfall data

      D.  Storm models and techniques for estimating probable maximum  floods
          in areas of limited data

 IV.  Hydrology and Hydraulics of

      A.  Surface Runoff and Combined Sewers

          1.  Rainfall-runoff relationships

              a.   Consideration of rainfall patterns in  estimating runoff
                  from rainfall

              b.   Estimation of losses from rainfall on  small watersheds

              c.   Geometry and morphology of a  stream  basin  in  relation to
                  hydrologic characteristics

              d.   Methods for estimating  peak rates of runoff and for
                  development of runoff hydrographs from small  areas

                  (l)   Parametric methods

                       (a)   Correlation analysis

                       (b)   Partial system synthesis with linear  analysis

                       (c)   General system synthesis

                       (d)   General non-linear  analysis

                  (2)   Stochastic methods

                       (a)   Markov chains

                       (b)   Monte Carlo methods

                                      115

-------
    e.  Spectral properties of rainfall-runoff relationships

    f.  Surface treatment of small watersheds  to modify runoff

    g.  Effects of frozen ground on flood runoff

    h.  Soil-moisture effects

2.  Runoff from snow melt

3.  Frequency of flows

    a.  Methods for determining the frequency  of peak flows and
        storm volumes in small streams,  combined sewers, and
        combined sewer overflows

    b.  Methods for determining the frequency  of low flows in small
        streams

U.  Flood routing

    a.  Improved methods of flood routing, including a procedure
        for reproduction of the rapidly rising stages that often
        occur during floods

    b.  Overland sheet flow--a routing problem

5.  Travel time

    a.  Use of fluorescent and radioactive tracers in measuring
        the time of travel of flows in streams and combined sewers

    b.  Use of tracers to study time of concentration of flood flows

6.  Turbulence, dispersion

    a.  Development of techniques for measuring turbulence in
        streams

    b.  Use of tracers in studying dispersion

    c.  Determination of regional patterns of  dispersion

    d.  Effect of stream inlets on main stream or  reservoir

7.  Radioactive and chemical tracers

    a.  Relating the movement of soluble tracers in streams to
        the movement of water

    b.  Determining the physical characteristics of fluorescent
        tracers in streams
                             116

-------
     c.  Effects of chemical and radioactive tracers on biota in
         streams

     d.  Determining absorption characteristics of radioactive
         tracers

     e.  Determining the effect of large-scale channel features
         on dispersion of soluble tracers in streams

 8.  Estimating the magnitude of diurnal fluctuation in stream
     flow

 9.  Effect of transported materials on the estimate of flood
     discharges

10.  Measurement of unsteady flow in streams and channels

11.  Mathematical representation of hydrographs

12.  Erosion, sedimentation

     a.  Shear distribution on stream boundaries

     b.  Eswsion and sediment yield from land surfaces by
         precipitation

     c.  Land sources of solutes and sediments

     d.  Physics of sediment transport in overland and channel flow

     e.  Sediment routing through channel and flood plains

     f.  Data on minimum transport velocities in combined sewers

     g.  Effects of manholes, junctions, inlets, bends, drops, etc.
         on the transport of solids in combined sewers

     h.  Methods for the control of erosion

13.  Improvement of flow characteristics

     a.  Use of additives such as long-chain polymers

     b.  Control of aquatic growth

     c.  Improved structural design of drains and combined sewers

     d.  Methods of sewer inspection and maintenance

     e.  Alteration of combined sewer routing to reduce downstream
         flow variability

     f.  Diversion of flood flows from urban areas through bypass channels

                            117

-------
   ik.  Water quality studies

        a.  Developing a general model for determining oxygen profiles
            in streams and estuaries

        b.  Chemical and physical processes affecting water quality

        c.  Biologic processes affecting water quality

        d.  Mechanical processes affecting water quality

B.  Surface Storage

    1.  Use of flood volume - duration - frequency analyses to determine
        flood storage requirements

    2.  Storage requirements to maintain selected flows

    3.  Evaluation of ecological and limnological characteristics of
        lakes and ponds

    U.  Optimum procedures of reservoir and pond control for reduction
        of sediment and temperatures

    5.  Effect of streamflow regulation on downstream channel losses

    6.  Effect of ponding behind a series of dams on water quality

    7.  Streamflow regulation for quality control

    8.  Study of unique storge space, such as on roof tops

C.  Ground - Water Storage

    1.  Determining the feasibility of methods of directing stormwater
        flow to underground aquifers

    2.  Investigating the feasibility of water spreading for conservation
        of water

    3.  Determining efficient techniques for recharging groundwater
        from surface runoff

    h.  Developing the mechanics of flow in unsaturated porous media

    5.  Study of surface water - groundwater interrelations

    6.  Study of sewer flow and groundwater interrelations

    7.  Investigating the retention and movement of water in fine-
        grained material

    8.  Analysis of th~ •'  ~ioal properties of porous  media that
        influence  ihu u^c   •• ^» storage, and movement of water

                                  118

-------
           9-  Study of changes occurlng in the properties of porous media
               as water moves through the media

   V.  Development of Statistical Methods

       A. Characterization of univariate hydrologic series-time series
           analysis

       B,  Statistical identification of hydrologic characteristics and
           relationships

       C.  Hydrologic systems analysis using stochastic methods—mathematical
           simulation and modeling, optimization, and decision theory

  VI.  Systems Studies

       A.  Experimental watersheds (A.G.U. definition)

       B.  Representative watersheds (A.G.U. definition)

       C.  Use of physical models

       D.  Use of mathematical models

 VII.  Organization for Urban Drainage Management

       A.  A study of the feasibility and means by which public agencies
           responsible for urban drainage in large metropolitan areas could
           coordinate their activities to attain greater efficiency and economy

           1.  Identification of items which could be included in agreements
               between existing public agencies in a region

           2.  Management patterns inherent in organizational alternatives

       B.  Preparation of a summary of State enabling legislation establishing
           drainage districts and authorities

       C.  Research to determine the proper level of organization for drainage
           management

VIII.  Economics of Urban Drainage

       A.  Economic systems analysis of the urban drainage complex

       B.  A program of research into the area of benefits and cost sharing
           between various levels of government and private land developers

       C.  Development of methods for evaluating and quantifying intangible
           >••   rits, or alternate solutions for attaining realistic cost-


                                        119

-------
         benefit analyses in urban storm drain design

     D.  A study of the comparative costs and benefits of developing multi-
         purpose impoundments to control runoff, versus the loss of land to
         flood plains when no such impoundments are provided

     E.  Compile data on cost of constructing storm drains

     F.  Record data on flood damage caused by inadequate storm drains

     G.  A critical study of the economics of research into improved
         hydrologic methods as compared with continued use of present
         practices

IX.  Planning Urban Drainage

     A.  An analysis of master plans prepared and adapted in many communities
         for drainage control with a summary of the major considerations
         which must be included in the preparation of a good master plan

     B.  Compilation and analysis of typical zoning plans as they relate
         to flood plains and drainage

     C.  Factors to be considered in the preparation of zoning plans

     D.  A study of methods used to coordinate plans and programs for storm
         drainage between the various public agencies of the metropolitan
         area

     E.  Study how planning for storm water drainage can be integrated  with
         comprehensive planning for urban areas

 X.  Financing Capital Improvement of Urban Drainage

     A.  A study of alternate methods of financing storm drainage improvements

     B.  An analysis and summary of federal aid financing programs

XI.  Legal and Regulatory Aspects of Urban Drainage

     A.  A compilation and analysis of typical drainage control ordinances
         of counties, cities, and towns including the preparation of model
         ordinances which may be applicable to the needs of various levels
         of governments and agencies

     B.  A compilation and analysis of erosion and siltation control
         ordinances including the preparation of model ordinances

     C.  Regulatory measures for pollution control

     D.  Flood insurance provisions


                                       120

-------
       E.  Legal devices for control of water and related land rights

 XII.  Ksthetics of Urban Drainage

       A.  Landscaping, park development along the drainage  system

       B.  Appropriate and attractive design of structures

       C.  Elimination of polluted open waterways

       D.  Use of drainage water for development of recreational lakes and
           ponds

XIII.  Public Support for Improved Facilities - Psychological and social
       research in methods of understanding public attitudes and gaining
       public support

 XIV.  Information Storage and Retrieval

       A.  Development of systems similar to the Storet system for handling
           various kinds of data

       B.  Development of schemes for transferring various systems to ft
           common format
                                       121
                                           * U. S. GOVERNMENT PRINTING OFFICE 1970 O - 375-920

-------