AUDIT  GUIDE

             FOR

       CONSTRUCTION

      GRANT PROGRAM
ENVIRONMENTAL PROTECTION AGENCY
      WASHINGTON, B.C. 20460
        Revised January 1978

-------
This document  is  not a  replacement for or  supplement  to  EPA
regulations, guidelines, or official EPA policy statements. It is a guide
used by the Environmental Protection Agency and its auditors to assist in
conducting interim  and final construction grant audits. As such, this
guidance is subject to be modified as EPA regulations, guidelines, and
policies change.

-------
                          TABLE OF CONTENTS
                                                                             Page
Chapter 1: Introduction                                                      1-1

1.1  Purpose of Audit Guide                                                 1-1
1.2  Program  Background                                                     1-1
1.3  Authority for Audit                                                      1-2
1.4  Audit Standards                                                         1-2
1.5  Audit Objectives                                                         1-2
1.6  Matters Requiring Immediate Attention                                   1-3
    1.6.1  Suspected  Fraud, Irregularity,
             or Collusion                                                   1-3
    1.6.2  Insufficient Data or
             Inadequate Systems                                             1-3
1.7  Quality Control                                                          l'-3
Chapter 2: Definition of Program Terms                                      2-1
Chapter 3: Preliminary Procedures                                           3-1

3.1  Developing the Audit Approach                                          3-1
3.2  Types of Audits                                                         3-1
    3.2.1  Interim Audits                                                     3-1
    3.2.2  Final  Audits                                                       3-3
3.3  Developing the Plan                                                     3-3
3.4  Major Activity Areas for  Audit Focus                                    3-7
    3.4.1  Accounting  Practices                                               3-7
    3.4.2  Procurement Practices                                              3-9
    3.4.3  Project Management Practices                                       3-12
Chapter 4: Field Audit Procedures                                           4-1

4.1  Approach to Audit of Costs                                             4-1
    4.1.1  Factors for Determining
             Allowability                                                    4-1
    4.1.2  Review of Costs                                                    4-4
4.2  General Audit Steps                                                     4-5
    4.2.1  Initial  Field Audit
             Procedures                                                     4-5
    4.2.2  Verification of Claim                                               4-6
    4.2.3  Verification of Eligibility                                            4-6
    4.2.4  Credits, Rebates,  and
             Refunds                                                        4-6
    4.2.5  Unpaid Bills                                                        4-7
4.3  Specific Areas of Audit                                                  4-7

-------
                                                                            Page
   4.3.1  Audit of the  Force Account                                        4-7
   4.3.2  Audit of Engineering
             Services                                                       4-9
   4.3.3  Audit of Construction
             Costs                                                         4-19
   4.3.4  Other Costs                                                       4-27
   4.3.5  Other Audit Matters                                               4-27
Chapter 5: Exit Conferences                                                 5-1

5.1  Audits with No  Findings                                                 5-1
5.2  Audits with Significant
       Findings                                                             5-1
5.3  Documentation                                                           5-1
Chapter 6: The Audit Report                                                6-1

6.1  Introduction                                                            6-1
6.2  Content and Format of Audit
       Report                                                              6-1
    6.2.1  Scope Paragraph                                                   6-i
    6.2.2  Opinion                                                           6-1
    6.2.3  Comments on  Compliance,
             Performance, and
             Internal Controls                                              6-1
6.3  Presenting the Findings                                                 6-2
6.4  Example  Audit Report No.  1                                            6-3
6.5  Example  Audit Report No.  2                                            6-14
Appendix  A: Survay of Grantee's
  Accounting, Procurement, and
  Property Management Systems                                            A-l
Appendix  B:  Bond Calculation  Guidance                                     B-l
Appendix  C:  Supplemental  Audit
  Procedures for Relocation Costs                                           C-l
Appendix  D: Criteria for  Eligibility  and
  Allowability of Selected Items of  Costs                                    D-l

Appendix  E: Consulting Engineer
  Subagreements-Records Subject
  to Audit                                                                 E-l
                                       11

-------
                                                                           Page
Appendix  Ft Consulting Engineer
  Subagreements--Allowable  Methods of
  Compensation                                                             F-l

Appendix  G:  Consulting Engineer
  Subagreements  Subject to 40 CFR
  35.937-5, -6, and -7                                                     G-l

Appendix  H:  Interpolation of Fee
  Percentage                                                               H-1

Appendix  I: Application of Paragraph B.5
  of Appendix D to 40 CFR 35, Subpart E                                  M

Appendix  J: EPA Division Audit Offices
  and Cognizant  Geographic Areas                                           J-l

Appendix  K:  References                                                     K-l
                                      111

-------

-------
                        CHAPTER 1:  INTRODUCTION
1.1 PURPOSE OF AUDIT GUIDE

    This guide has been prepared to assist the Environmental Protection Agency (EPA) and its
auditors in conducting interim and final audits of the construction grant program. The audit
steps in this guide are intended to provide general insight into the nature and scope of audit
contemplated. This guide is npt  intended to be  a complete manual of procedures, nor is it
intended to supplant the auditor's judgment of the work required to meet the audit objectives
outlined in this audit guide. The audit procedures contained in this guide may not cover all
circumstances or conditions encountered in auditing a particular grant, and, similarly, not all of
the audit procedures will apply to each grant audited. The  auditor must use his professional
judgment to tailor the procedures to meet conditions at the audit site so that the audit objectives
set forth in the guide may be achieved.

1.2 PROGRAM BACKGROUND

    The first Federal legislation concerning water pollution was the Rivers and Harbors Act of
1899. The Act provided that those convicted of polluting navigable waters or their tributaries
would  be  guilty of a misdemeanor and, upon conviction, would be fined between $500 and
$2,500 and imprisoned for not less than 30 days nor more than one year. Forty-nine years later,
the 1948 Federal Water Pollution Control Act was enacted. It provided grants for the planning
and design prior to construction  and loans for construction of waste-water treatment plants.
The Federal Water Pollution Control Act  of 1956  provided the basis  for  the current
construction grant program. This Act was amended in 1961,1965, 1966, 1970, 1972, 1973, and
1977. The Act, as amended, provides for Federal grants  to municipalities, intermunicipal
agencies, states, and interstate agencies for the purpose of planning, designing, and constructing
waste treatment facilities.

    The Department of Health, Education, and Welfare administered the program until 1966.
The Federal Water Pollution Control Act of  1966 transferred this  responsibility  to  the
Department  of the Interior. The  construction  grant  program  was transferred to  the
Environmental Protection Agency in 1970 (Reorganization Plan No. 3).

    After June 30,  1967, Federal participation in grants for the cost of constructing a waste
treatment facility could be increased to 40 percent if the state agreed to pay not less than 30
percent of the estimated reasonable cost of all state construction projects receiving Federal
grants. The percentage limitation could be-further increased to 50 percent if (1) the state agreed
to pay  not less than 25 percent of estimated reasonable cost of all projects for which Federal
grants  were made and  (2) enforceable water quality standards had been established for the
waters into which the project discharged. An additional Federal participation of as much as ten
percent of the approved grant was permitted if the funded  project was  in conformity  with a
metropolitan plan  for that  particular area.  Thus, it was possible for a Federal grant to be
awarded for an amount equal to 55 percent of the total estimated reasonable project cost.

    Title  II of the Federal  Water Pollution Control Act Amendments  of 1972 authorized a
Federal grant of 75 percent of the cost of construction of a treatment works. In addition, Section
206(a)  through (e) of P.L. 92-500 (codified in Subpart D of 40 CFR 35 and amended by P.L.
93-207) may  provide  for  reimbursement of public sewage treatment projects  on  which
construction was initiated after June 30,1956.
                                         1-1

-------
1.3 AUTHORITY FOR AUDIT

    The authorized representatives of the Administrator of EPA and the Comptroller General
of the United States have authority to audit the grantees' books, documents, records, and papers
(P.L. 92-500). This audit authority is extended to the subcontractors' books, documents,
records, and papers which are pertinent to the project (40 CFR 35.935-7). EPA auditors and
auditors under contract to EPA, are the Administrator's representatives.

    The EPA Office of Audit is responsible for audits of EPA grants. The Division Audit
Director (see Appendix J to this guide) may elect to have an individual audit conducted by his
staff, another Federal  agency, state or local government auditors, or an independent public
accountant. When the Division Audit Director elects  to have the audit performed by an
independent public accountant, the Director must notify the grantee or contractor as to the firm
performing the audit. The selected firm must contact the grantee or contractor to arrange for
the start of the audit.

1.4 AUDIT STANDARDS

    Audits of EPA construction grants will be made in accordance with this guide and the
"Standards for Audit of Governmental Organizations, Programs,  Activities, and Functions"
issued by the Comptroller General in August 1972. The independent public accountant will not
be required to express an opinion as to the efficiency and economy of operations or with respect
to program evaluations. He will, however, be required to perform certain audit tests related to
these aspects and to report the results of his examination.

    In performing audits of EPA grants/contracts, the auditor is expected  to  adhere to
generally  accepted auditing  standards.  In  addition, the auditor should utilize applicable
portions of the American  Institute of Certified Public Accountants' (AICPA) Industry Audit
Guides. Of particular importance is the guide "Audits of State and  Local Governmental
Units."

1.5 AUDIT OBJECTIVES

    The objectives of the audits of grants and contracts are to:

          a.    Determine whether the management controls exercised by the grantee through
its management system, accounting system, procurement system, and property control system
are adequate to provide assurance that costs claimed/incurred are reasonable, allowable, and
allocable to the sponsored project under the grant terms and conditions,  Federal Management
Circulars (FMCs), and applicable EPA regulations.

          b.    Identify any noncompliance with applicable grant provisions or EPA rules
and regulations and, based upon the review, provide recommendations for improvement.

          c.    Determine whether the costs claimed under the EPA  grant are reasonable,
allowable, and allocable to the sponsored project.
                                         1-2

-------
1.6 MATTERS REQUIRING IMMEDIATE ATTENTION

    1.6.1 Suspected Fraud, Irregularity, or Collusion

    Audits performed in accordance with this guide are not for the purpose of detecting fraud,
although audits may minimize fraud loss, discourage irregularities, and identify conditions of
gross  mismanagement.  If,  during the examination,  instances  of  possible fraud, gross
mismanagement, or other similar irregularities are noted, the auditor should:

          a.    Document the situation;

          b.    Immediately notify the Division Audit Director of the situation encountered;
and

          c.    Proceed only in accordance with instructions provided.

    1.6.2 Insufficient Data or Inadequate Systems

    The auditor is expected to use professional judgment in arriving at conclusions concerning
the sufficiency of available supporting data.  If additional  guidance is  needed as to the
acceptability of certain data, the auditor should contact the  Division Audit Director or his
designated  representative.  Where  insufficient data or inadequate systems  preclude reaching
opinions concerning the  reasonableness, allocability, and  allowability of costs  within  a
reasonable period of time, the auditor must, as a minimum:

          a.    Document tests and observations to support the auditor's opinion regarding
insufficient data or inadequate systems.

          b.    Notify the Division  Audit  Director and cease  work until instructions are
received.

1.7 QUALITY CONTROL

    EPA retains the right to review  audit workpapers to evaluate the overall quality of the
audit  performed. In  this regard, EPA  may require  that copies of the audit  workpapers be
forwarded along with the completed audit report to the responsible Division Audit Director or
his designated representative. The audit workpapers will be  returned to the auditor upon
completion of the EPA evaluation. Based on  this review, the auditor may have to return to the
job site  to perform whatever additional work is required. In this regard, the  auditor should
retain the workpapers applicable to the audit of any EPA grant or contract for three years after
completion of the assignment and submission of the required audit report.
                                         1-3

-------

-------
            CHAPTER 2:   DEFINITION  OF PROGRAM TERMS
    In conducting  a  construction grant audit, it is extremely important that  the auditor
understand certain program terms. Program terms are defined in 40 CFR 35.805 and 35.905 of
EPA's Final Construction Grant  Regulations. In  addition,  the following definitions are
presented to further assist the auditor.

    Cutoff Date--A cutoff date is established by  the EPA Regional Office. The grantee is
normally notified of the cutoff date by letter. After the cutoff date, the cost of work performed,
equipment or materials delivered or installed, or services rendered will not be allowable for
Federal participation. If no other cutoff date is established, the cutoff date will be the date of the
final inspection performed by either the state agency or EPA, whichever the Region deems the
true final inspection.

    Federal Share--The amount of the Federal grant not to exceed the smaller of the amount of
the approved grant or the actual allowable audited costs multiplied by the percentage of Federal
participation on which the grant was computed.

    Force  Account-The grantee's use of its own employees, material,  and equipment for
construction, construction-related activities, or facility repair or improvement.

    Grantee-An applicant who has  received a grant.  A grantee may be a municipality,
intermunicipality agency, state, interstate agency, District of Columbia, Puerto Rico, Virgin
Islands, Guam, American Samoa, or Trust Territory of the Pacific Islands.

    Industrial Cost Recovery-Recovery, from the industrial users, of construction costs of a
treatment works. This recovery is based on the proportionate treatment  of waste from such
users  over a period of 30 years or the life of the facility. Fifty percent of the recovered funds,
together  with  any interest earned  during the year,  is to be refunded annually to the U.S.
Treasury. Forty percent of the recovered amount is to be retained by the grantee and used only
for EPA-approved construction. The remaining ten percent may be used as the grantee wishes.

    The amendments to PX. 92-500 (P.L. 95-217, dated December 27, 1977) provide for an
18-month moratorium on the collection of industrial cost recovery payments by the grantee.

    Operation and Maintenance—The operation and maintenance of a treatment works during
its service life, following completion of the Step 3 phase.

    Project File~The EPA file which contains each grant agreement or amendment (such as
Step 1, Step 2, or Step 3) and supporting documents, correspondence with the grantee, copies of
inspection reports, and the grantee's payment requests.

    Value Engineering (VE)--A specialized cost control technique based on a systematic and
creative approach which identifies and focuses on unnecessarily high cost in a project in order
to arrive  at a cost saving without sacrificing the reliability or efficiency of the project. Value
engineering is required for all Step 2 grant applications having a projected total Step 3 grant-
eligible construction cost of $10 million or more, excluding the cost of interceptors and collector
sewers, for  all construction grant projects certified by the state on or after October 26, 1976.
(See Section 4.3.5.i of this guide.)
                                         2-1

-------

-------
                CHAPTER 3:  PRELIMINARY PROCEDURES
3.1 DEVELOPING THE AUDIT APPROACH

    The scope of each construction project is initially defined by a prospective applicant, with
final determination made by the Regional Administrator when  grant assistance is awarded
(35.930-4).

    Grants are generally obligated in three separate stages of project development (see Figure
3.1):

          a.    Step 1—facility plans and related elements;

          b.    Step 2--preparation of construction drawings and specifications; and

          c.    Step 3-fabrication and building of a treatment works.

A "Project" may consist of an entire step, a segment, or a combination of steps (35.905-24).
Construction grant projects funded under Public Law 84—660 consist of a combination of Steps
1, 2, and 3. An average sized project may require approximately two years  to plan and
construct. Very large regional projects may require 12 to 15 years.

3.2 TYPES OF AUDITS

    Two types of field audits will be discussed in this guide: interim audits and final audits.
(Preawards and defective pricing audits are integral parts of EPA Audit's workload. They are
not covered by this guide, but will be the subjects of separate guidance.)

    The overall objectives of interim  and final audits are to ensure that the grantee is in
compliance with grant requirements and to identify any areas in the  management of the
construction grant program which need improvement.

    The auditor is expected to have the skills necessary to perform the reviews required to meet
the objectives   of this guide.  If the auditor encounters situations requiring  skills  of  an
engineering technical nature, he should contact the Division Auditor Director, who will review
the situation and arrange for technical assistance.

    3.2.1 Interim Audits

    The primary purpose of the interim audit is to (1) review grantee operations during
construction to detect weaknesses in internal  controls or in the controls over contractors
responsible for  design and construction and (2)  offer recommendations for improvements.
Interim audits will be performed during the earlier part of a construction project, often shortly
after the construction  contractor has submitted a construction payment request. Accordingly,
interim audits will be primarily directed toward:

          a.    Internal accounting controls,

          b.    Procurement systems,
                                         3-1

-------
                                    Figure 3.1


          CONSTRUCTION PROJECT MILESTONES-OVERVIEW
STEP 1

  Facility Plans  and Related  Elements
  Municipality submits application
  State and EPA review application
  Facility plans  and alternatives are proposed
  Environmental and social aspects are considered
  Priorities are set by state for Step  2

STEP 2

  Preparation of Construction Drawings,  Plans,  and
  Specifications
• Municipality submits application
• State and EPA review application
• Plans and specifications are completed
• State and EPA review and approve plans  and
  specifcations
• Priorities are set by state for Step  3

STEP 3

  Fabrication, Building,  and Certification of Treatment
  Works
  Municipality submits application
  State and EPA review application
  Applicant advertises and selects low, qualified bidder
  State and EPA review and approve selected bidder
  Construction

    a) Progress  payments
    b) Request  for changes approved
    c) Interim inspections by state/EPA
    d) Interim audits by state/EPA
    e) User charge, industrial  cost recovery system
    f) Operations and maintenance manual approved
    g) Grantee  certifications
       •  Project completed
       «  Final audit,  payment
                                        3-2

-------
          c.    Design and construction controls,  and

          d.    Costs  incurred.

    3.2.2 Final Audits

    The primary purpose of the final audit is to review grantee records after completion of the
project to assure that costs claimed are reasonable, allocable, and allowable and that the grantee
has met the grant objectives. Final audits will also be concerned with controls in effect at the
time of grant performance, to provide assurance that the grant was administered efficiently and
resulted in an acceptable final product.

3.3 DEVELOPING THE PLAN

    The EPA Office of Audit will utilize the criteria presented in Figure 3.2, other relevant
reports, construction grant and audit information, and sampling techniques to select projects
for audit.

    Once the grantee has been selected, the Office of Audit will review the project files and,
after consultation with the Regional Office, assemble an audit planning package which will be
used to:

          a.    Determine whether a field audit will be performed;

          b.    Determine the scope of audit; and

          c.    Provide a basis for preparing the audit services order.

    Descriptive data needed for completing the audit estimates will be provided (Figure 3.3) to
the prospective auditor for use in developing an audit plan. Other data relevant to actual project
costs and contract information (Figure 3.4) should be obtained from the project file by the
auditor selected to perform the audit.

    When an auditor  under contract to EPA is to  perform the audit, the Division  Audit
Director will coordinate the entrance conference date with him and confirm the date by letter to
the grantee.

    There are substantial regulatory requirements with which the grantee must comply under
the P.L. 92-500 construction grants program. These requirements are primarily set forth in
Parts 30 and 35 of EPA regulations published in Title 40 CFR, but other parts are applicable
when referenced (e.g., Part 4, Implementation of the Uniform Relocation Assistance and Real
Property Acquisition Policies Act of 1970). The auditor must also review the grant documents
in order to identify the terms and conditions unique to the  audit being performed.

    In reviewing the project, the Division Audit Director will determine if there are areas
requiring special attention. The Director  will identify  areas which require detailed audit
coverage as well as areas requiring little or no coverage. In addition, the Director may decide to
expand the audit to cover certain  aspects of efficiency,  economy, or program effectiveness.
Whenever the scope of audit is expanded, the  Director will provide the necessary additional
audit guidance.
                                         3-3

-------
                             Figure 3.2

FACTORS TO  BE  CONSIDERED IN DETERMINING  AREAS OF
AUDIT EMPHASIS

    •  Size of grants/projects

    •  Existence  of unit-price contracts

    •  Type of construction contracts and subcontracts

    •  Type and materiality of engineering contracts and
       subcontracts

    •  Number and  significance of change orders

    •  Experience with prior grantee/project audits

    •  Indication of deficiencies
                                      3-4

-------
                                 Figure 3.3


    INFORMATION TO BE  PROVIDED TO PROSPECTIVE  AUDITORS
FOR USE IN DETERMINING  SCOPE,  SCHEDULE, RESOURCES,  PLANS,
         AND ESTIMATES OF AUDIT  REPORTS

    •   Grant number

    •   Grantee name,  address, and phone number

    •   Eligible  project  cost

    •   Grant amount

    •   Number and dollar value  of change orders

    •   Number, amount,  and type of construction contracts

    •   Number, amount,  and type of engineering agreements

    •   Extent of force account work (as available)

    •   Cutoff date

    •   Notification if construction is located in a flood
       hazard area requiring the  grantee to purchase flood
       insurance

    •   National Pollutant  Discharge Elimination System
       (NPDES) permit
                                   3-5

-------
                               Figure 3.4



INFORMATION TO BE OBTAINED FROM THE PROJECT FILE
      BY THE AUDITOR PERFORMING THE AUDIT

*  •  Final project inspection date

   •  Any additional engineering, construction contracts

   •  Copies  of related subcontracts (as  available)

*  •  Final inspection reports and cutoff dates
      (final audits)

   •  Copies  of EPA-approved change orders

   •  Bid tabulations,  contractor  proposals

   •  Expenditure work sheet calculations

   •  Payments made by EPA

   •  Approvals to  advertise, award contracts

   •  Other pertinent correspondence (e.g.,  management
      problem  areas)

   •  Grants information and control data sheets

   •  Inspection reports, correspondence, and memorandums

*  •  Final Project  Progress Report and Payment Request
      (PPR &  PR) or Outlay Report and Request for
      Reimbursement for Construction Program

   •  Form FWPCA-7 or Form 5700-32, Application, with
      supporting  documentation

   •  Form FWPCA-7c, State  Priority Certification and
      Project Approval

   •  Form FWPCA-8a or Form 5700-20 (Offer and
      Acceptance)

*  Normally  not  available from Regional Office project
   files for an  interim  audit.
                                   3-6

-------
    After the auditor has been selected and he has studied the project file furnished by EPA, he
must:

          a.    Note any special grant conditions which may be significant to the audit; and

          b.    Familiarize himself with the  regulations  applicable to the grant/project as
indicated in grant award documents.

3.4 MAJOR ACTIVITY AREAS FOR AUDIT FOCUS

    The general scope of audits will be established by the EPA Division Audit Director during
the definition and audit planning stages. The major activity areas to be addressed during the
audits include the grantee's:

          a.    Accounting practices,

          b.    Procurement practices, and

          c.    Project management practices.

Both  interim and final audits will include the audit of costs incurred associated with these
activities.

    3.4.1 Accounting Practices

    A primary requirement for the competent management of any project is a good accounting
system. The major areas which should be of primary concern to the auditor during his survey
(see Appendix A of this guide) are discussed below. For additional information on the criteria of
an adequate/acceptable accounting system, see the EPA publication, "Accounting Guide for
Construction Grants" (October 1977).

          a.    Accounting records

    In order to have an accounting system, there must be records of all financial transactions.
This system should document all receipt and disbursement transactions, including explanations
and identifying codes (e.g., invoice number) on a chronological basis. It should also group them
by type of account (e.g., expense, asset) and by individual account (e.g., Board of Supervisors
payroll, communications expense).

    Accounts should be set up in such a way as to identify each cost with a cost center and cost
objective in the form of a  task or subtask.  A cost center may be an organizational unit, a
function, or even an item of expense. Its purpose is to collect costs on a functional  basis. Thus,
accounts might be divided into more than one cost center (e.g., payroll expense  might be
distributed into several departments) and cost centers may have more than one account (e.g.,
the accounting department's costs might include payroll expense, supplies, and other accounts).

    An important project  management objective of accounting records is the derivation of
information regarding  actual versus  budgeted costs by  project task  and by  performing
organization. A separate cost center or series of subaccounts should be established to identify
and accumulate the costs applicable to the EPA construction grant.
                                         3-7

-------
    All  entries  in  the  chronological and account groupings should  be cross-referenced.
Further,  the groupings should be cross-referenced to the supporting documents. (See 40 CFR
30.800 and 30.805.)

          b.    Supporting documents

    Every entry in the accounting records should be supported by appropriate documentation.
This could be a document from outside the grantee's office, as in the case of an invoice, or it
could be an internally generated document, as in the case of payroll. In many cases, several
documents will support a single transaction. For instance, a purchase of materials should have a
purchase request, purchase order, and receiving report in addition to an invoice. It might also
involve requests for proposal, contracts, advisory board resolutions, progress reports, and
progress  payments.  The key is that the files  of supporting documents should contain all
information necessary to explain every transaction completely and should be cross-referenced
in such a Way that transactions can be traced from any document dealing with the transaction
back to the initiation of that transaction and forward to the entry or entries concerned with that
transaction.

          c.    Traceability

    Traceability is composed of two elements. The first is mechanical in nature.  All entries
should be traceable to supporting documents. This requires a good filing system based on
reference codes for each entry and document. In a small system, codes may not need to be as
detailed,  due to the lower volume of transactions, but in almost all systems referencing based
solely  on a  date or name  will eventually prove  cumbersome,  inefficient,  and probably
inadequate. Sequential numerical codes are usually best, not only for ease of referencing but also
for internal control.

    The second element of traceability is the logic behind the transaction. One should be able
to determine not only what was done but why it was done. It is here that written procedures
become important. Some companies and governmental units survive without them; however,
they constantly experience exceptions to the unwritten rules and loose internal control because
of employee turnover and changes in circumstances. A grantee should have or should prepare
complete procedures for handling grant funds.

          d.    Segregation of costs

    Accounting systems under Federal grants must provide for segregation of costs. In order
to permit grantees and EPA to determine in which costs the government will  participate, the
accounting system must differentiate between:

               (1)    Eligible and ineligible costs

    Each construction grant project is normally evaluated by EPA Regional Office personnel
to determine which portions of the project are eligible for Federal participation under Federal
statutes.  All  costs applicable to eligible portions of the project are considered eligible costs.
Costs applicable to the ineligible portion, conversely, are considered  ineligible and cannot be
claimed for Federal participation.

               (2)    Allowable and unallowable costs

    All  costs related to construction  grants  must be allowable under applicable Federal
regulations and the terms of the grant if EPA is to participate. Grantee costs must also be
considered allowable under FMC 74-4  and EPA regulations in 40  CFR 35.940.  Each cost
                                         3-8

-------
should be  scrutinized in  view of these requirements.  Unallowable costs should then be
segregated, thus preventing their inclusion in the grantee's claim for Federal participation.

               (3)   Direct and indirect costs

    A further distinction  must be made between direct and indirect costs. Direct costs are
those which  can  be directly  identified  to a  particular  grant. For example,  accounting or
procurement costs are commonly not identified with individual grant projects. Grantee indirect
costs  are  not allowable as charges  to  a  grant  program  unless an  indirect cost proposal
identifying indirect costs  and showing  the  proposed allocation is  prepared, audited, and
accepted by the Federal government. (See 40 CFR 30.715-2 and 40 CFR 35.940-4.)

          e.    Internal control

    Internal  control is  the  means  by which  the accounting, procurement, and  other
management systems are regulated. It serves to assure management that proper procedures are
being followed with respect to receipts and disbursements.

    Each grantee should  have controls which act to check  the functioning of the system
automatically and which ensure that all  major transactions have checks and balances on the
individuals involved.  Contractors hired  by the grantee  should be supervised not only  with
respect to their work but  also with respect to their accounting for the costs of work under
reimbursable contracts. This supervision should also be provided for as a part of the grantee's
internal control system. For example, costs of contractor efforts by task should be recorded and
should have  an audit trail which the grantee could examine in detail  if the contract  were
significant in amount.

          f.    Accounting reports

    Accounting reports are an integral part  of an accounting system and are often the least
planned aspect of the system. This applies more to internal reports than to external reports
because the form of many  external reports is prescribed. Grantees should realize that the data
which must be reported to outside sources is not always the same, as that which is required for
internal management. Like internal control, report content will vary from grantee to grantee.
The keys here are simplicity, comparability, and advance planning.

          g.    Summary

    The constant question must be: has the grantee given sufficient thought to planning the
accounting system? It should be based on analysis of needs and resources, rather than on  a
standard system copied from a book. The thing to look for is an understanding of those needs
and an analysis of how the accounting system will fulfill them.

    3.4.2 Procurement Practices

          a.    Construction contracts

    EPA  regulations (40 CFR 35.938-3) require  that each construction contract greater than
$10,000 (see 40 CFR 35.936-19 for those under $10,000) shall be either a firm-fixed-price (or
lump sum) contract, a unit price contract, or a combination of the two, awarded by means of
formal advertising to the lowest reponsive, responsible bidder. Exceptions include negotiated
change orders (see 40 CFR 35.938-5) and other construction contracts negotiated for reasons
given in 40 CFR 35.936-18.
                                         3-9

-------
               (1)   Firm fixed price (FFP)

    The FFP contract generally provides that the contractor will be paid a lump sum agreed to
in advance for the construction of the facility reflected in detailed plans and specifications. It is
not subject to adjustment by reason of contract  cost experience and, when appropriately
applied, places maximum risk upon the contractor. The grantee and the Federal government
are assured of a reasonable price  through the receipt of competitive bids under the formal
advertised procurement process. For changes in scope of work, noncompetitive change orders
to formally advertised procurements must be negotiated.

               (2)   Unit price

    The unit price contract generally provides that the contractor will be paid a fixed sum  for
each unit of work performed under the approved plans and specifications. This type of contract
is commonly used where the work represents a repetition of things, such as the laying of sewer
lines,  or where the quantity of  work may vary  substantially. Unit prices are not subject to
adjustment by reason of cost experience. As in FFP contracts, the reasonableness of the total
contract price is assured through the receipt of competitive bids  under  the formal advertised
procurement process. Where there are significant differences in unit  quantities awarded and
unit quantities constructed, the reasonableness  of unit prices must  be established through
negotiation.

          b.    Engineering contracts (Figure 3.5)

    Engineering  and consulting  services under  grants  are generally obtained  through a
negotiated procurement. This type of procurement should involve screening a number of firms
for technical  competence. Under a negotiated procurement, there are  a number of types of
contracts: firm fixed price, cost plus fixed fee (or cost reimbursable), time and material (or labor
hour), or combinations of the above. The Federal Procurement  Regulations (FPR),  Section
1-3.4, discuss in detail these forms of contracting, when they are considered applicable, and
their limitations. The following summary of each is provided.

               (1)   Firm fixed price

    The FFP contract generally provides for a firm price agreed to in advance for the services
to be  procured. It is not subject to adjustment by reason of the contract cost experience and,
when appropriately applied, places maximum risk  upon the contractor. Since the contracting
firm assumes full responsibility  for profit or loss, it has maximum incentive for effective cost
control and contract  performance. The FFP contract is suitable for use in procurements only
when definite performance requirements are available and when fair and reasonable prices can
be established at the outset. Prior to award, a negotiation process which includes either price or
cost analysis  should  take place between the firm  and  the grantee to arrive at a  reasonable
estimate of cost plus a negotiated profit. The grantee is expected to document this negotiation.

               (2)   Cost plus fixed fee (CPFF)

    The CPFF contract provides for  the payment of actual cost  plus a fixed  fee to  the
contractor. The fixed fee once negotiated does not vary with actual cost. Therefore, the CPFF
contract provides the contractor only minimum incentive for effective management control of
costs.
                                         3-10

-------
on
 eu


1

6



I
      OJ3
                             D Z

                             f, O
                             <; O


                             U

                             S
                             u
                             u
                             a
                             tt,
                             J O
                             o. O
                             8
                             6. O
                             oc
                             « o

                             "* 5
                                     I Q_ U-


                                     i • •
                                      Q- <
                                             6 ^
                                                   .C ^J



                                                   ~ TJ
                                                        I III!!!.
                                                        £X C/3 Cl. U C <, V5
                                                                     c 2 o.
                                                                  c d "

                                                               ' S-o » 1
                                                  3-11

-------
    The CPFF contract provides that the contractor receive its actual allowable labor, other
direct costs, and indirect costs, plus a fixed-fee profit. The CPFF contract is written to provide
for a total estimated cost (contract ceiling).  The firm's costs are subject to an audit during or
after completion of performance to determine that its claims included only allowable costs in
accordance with applicable regulations.

               (3)   Time and materials

    This type of contract provides for the procurement of services on the basis of direct labor
hours at specified fixed hourly rates (which include direct labor, overhead, and profit). This
type of contract does not afford the contractor with any positive incentive to control cost. It is
essential that time and materials contracts be used only where provision is made for adequate
controls, including appropriate surveillance  during performance. Because this type of contract
does not encourage effective cost control and requires almost constant surveillance, it should be
used only after determination that no  other type of contract will suitably serve. This  type of
contract shall establish a ceiling price which the contractor should not exceed.

    The time and materials contract has been used frequently by engineering and consulting
firms in the past. While it is an acceptable form of contracting, certain controls that have not
existed in the past are essential. The grantee  is responsible for obtaining cost data from the
consulting engineer for evaluation and negotiation in establishing hourly rates. This should be
documented to show that a determination of reasonableness was made. In addition, the grantee
is  responsible for maintaining surveillance over the hours charged by the contractor. The
contract must set a reasonable ceiling on the total cost of these services. A final audit will be
made to assure that the contractor has appropriate documentation to support the time charged
to the project.

    In summary, any of the above forms of engineering contracts can be acceptable. However,
the grantee is responsible for demonstrating that:

               (1)   The method selected is appropriate for the services to be performed (see
FPR 1-3.4);

               (2)   The necessary evaluation of the reasonableness of the proposed costs
was made; and

               (3)   Controls were maintained during performance.

    In reviewing systems for procurements awarded under EPA's "Subagreement Regulations
for Construction Grants," the auditor should be guided by the requirements of 40 CFR  35.936,
40 CFR 35.937, and 40 CFR 35.938.

    3.4.3 Project Management Practices

    The grantee's ultimate ability to control costs  and  construction  schedules is strongly
influenced by the project management approach applied. In addition  to establishing a clear
understanding of  contractual  relationships,  the  grantee, the engineering firm, and the
construction contractor  must maintain a  complete communication  system with effective
controls over costs and schedules and with a  rapid decision-making and feedback capability.
The basic principles of such a system of management controls are shown on Figure 3.6.
                                         3-12

-------
                                     Figure 3.6
Basic Principles of the Grantee-Engineer-Construction Contractor System

•   Proper definition of project scope; estimated cost; schedules; and responsibilities of the
    grantee, the engineer, and the construction contractor

•   Prompt revision of scope, estimated costs, and schedules after changes

•   Control of design costs and procurement of engineering services and construction

•   Control of schedule, costs, and changes during construction by monitoring:

          work schedules, material schedules, and start-up;

          material quantities purchased and used

Planning and Design Phase Cost and Schedule Control Activities

•   Inclusion of VE for Step 3 projects with eligible construction costs of $ 10 million or more
    (excludes interceptor and collector sewers)

•   Regular planning and design meetings attended by proper management membership

•   Regular reports on planning and design progress as related to prior schedules

•   Specifications, reviews, and approval for major equipment, much the same as for drawings

Controls Applied During Construction

•   A program for viewing overall time  schedule and cost  variances from budgets  and
    schedules

•   Inspections and reports of installed quantities  of materials, with  comparison between
    planned and actual construction

•   Control   of  field   progress  by   periodic  site   reviews   or  continuing  on-site
    inspection/monitoring

•   A change-order budget system  which shows  dollars, man-hours, and quantities of
    materials or equipment

•   A change-order approval system with (1) adequate formalized evaluations of the impact of
    pending changes and (2) change notification procedures for fully implementing approved
    changes
                                         3-13

-------
          a.    Planning and design phases cost and schedule control

    The control of costs and construction schedules during planning and design is of great
importance. Common activities and management control activities are shown in Figure 3.6.

          b.    Construction phase cost and schedule control

    Emphasis during the construction phase is focused on the management and monitoring of
project cost and schedule data for construction labor, material installations, and performance of
subcontractors  providing equipment and services. The grantee must ensure that adequate
inspections at the project locations are provided and that construction and equipment conform
with the approved plans and specifications. Controls exercised during this phase are shown in
Figure 3.6.
                                        3-14

-------
                 CHAPTER  4:   FIELD AUDIT PROCEDURES
    In performing the audit, the auditor must use professional judgment on a case-by-case
basis in determining the specific audit procedures to be applied. Not all of the audit procedures
outlined in this guide will apply to each audit.

    The auditor must consider the materiality of costs incurred by the grantee as related to
administrative labor and materials,  engineering services, and construction. In addition, the
management controls applied by the grantee to the overall program must be reviewed.

    The  prior sections  of this  manual outline project  management systems  and  their
relationships to the audit, including the need to focus on the specifics of the procurement,
accounting, and project management activities. This section sets forth the field audit procedures
to be used in conjunction with this guidance.

4.1 APPROACH TO AUDIT OF COSTS

    In conducting audits of EPA construction grants, the auditor will be attempting to reach a
conclusion as to the acceptability of costs. In an interim audit, the auditor will express an
opinion on costs incurred through the grantee's most current accounting period even though
these costs may not have been claimed on a reimbursement voucher to EPA. In a final audit, the
auditor will express an opinion on the  costs  reported on the final report of expenditures or
updated form. Thus, in a  final audit where the grantee has actually incurred costs in excess of
the amounts claimed or reported, the auditor may not increase the amount of the grantee's
claim. Nor should the auditor allow the grantee to offset unclaimed costs with questioned costs,
even if the net amount would not increase the grantee's claim. He should, however, disclose
through footnotes the  extent of unclaimed or unreported costs  which would normally be
considered allowable.

    4.1.1 Factors for Determining Allowability

    To be allowable under a grant program, costs must meet the following general criteria:

          a.  Be necessary and reasonable for proper and efficient administration of the grant
program,  be allocable thereto  and, except as specifically provided  herein, not be a general
expense required to carry out overall responsibilities of state or local governments;

          b.  Be authorized or not prohibited under state or local laws or regulations;

          c.  Conform to  any limitations or exclusions  set forth  in the grant document,
Federal laws, or other governing limitations as to types or amount of cost items;

          d.  Be consistent with policies, regulations, and procedures that apply uniformly to
both Federally assisted and  other activities of the unit of government of which the grantee is a
part;

          e.  Be accorded consistent  treatment through application of generally accepted
accounting principles appropriate to the circumstances;

          f.  Not be allocable to or included as a cost of any other Federally financed program
in either the current or a prior period; and
                                         4-1

-------
          g.   Be net of all applicable credits.

    Costs questioned normally fall under one or more of the following categories (see Figure
4.1):

    Ineligible  costs:  Costs which are  specifically  prohibited  by (1) Federal  statutes  or
regulations, (2) the terms of the grant,  (3) other cost  principles cited in the grant, or (4)
applicable EPA regulations or guidelines.

    Unreasonable costs: In determining the reasonableness of a given cost, consideration shall
be given to:

          a. Whether the cost is of a type generally recognized as ordinary and necessary for
the conduct of the grantee's (contractor's) business or the performance of the contract;

          b.   The restraints or requirements imposed by such factors as generally accepted
sound business practices, arm's length bargaining, Federal and  state laws and regulations, and
grant/contract terms and specifications;

          c.   The action that a  prudent  businessman would take in the circumstances,
considering his responsibilities to the owners of the business, his employees, his customers, the
government, and the public at large; and

          d.   Significant deviations from the established practices of the  grantee/contractor
which may unjustifiably increase the grant/contract costs.

    In conducting his examination, the auditor should be cognizant of the costs incurred which
indicate to him that they may be excessively high or even unwarranted. In determining whether
to question any costs as being unreasonable, the auditor should  rely on his own judgment; he is
not expected to make judgments on technical matters outside of his area of expertise.

    Unallocable costs: In reviewing the allocability of costs, the auditor will be guided by the
following criteri?:

          .a.   A  cost is allocable to a particular grant/contract to the extent of benefits
received.

          b.   Any cost allocable to a particular project or function may not be shifted to a
Federal grant/contract to overcome fund deficiencies, to avoid restrictions imposed by law or
grant/contract agreements, or for other reasons.

          c.   Where  an allocation of common costs will ultimately result in charges to a
grant/contract, an indirect cost rate proposal must be prepared to justify the equitability of the
charge.

    Undocumented costs: Costs for which detailed documentation is not available to show that
the costs claimed were incurred under the EPA grant/contract.

    Unapproved costs: Costs for which grant/contract provisions or applicable cost principles
require  awarding agency approval, but for  which  the  auditor finds no evidence of such
approval.
                                          4-2

-------
                                     Figure 4.1



Examples of Ineligible Costs

• Interest on bonds or other financing costs

• Fines and penalties resulting from violation of Federal, state, and local laws

• Personal injury compensation or damages as a direct result of construction on the project

Examples of Unreasonable Costs

• Purchase of expensive equipment needed only for a short period when a lease would have been
more economical

• Costs for which appropriate evidence is not available under a negotiated contract that the
grantee or contractor employed those controls necessary to assure that the price was reasonable

Examples of Improperly Allocated Costs

• Costs already matched to another Federal program

• Inequitable allocation of indirect costs to the contract/grant

• Costs allocated in total to the grant, which also benefited other grantee/contractor programs

Examples of Improper Documentation of Costs

• Lack of time and attendance records, invoices, etc.

• Lack of written contracts with consultants

• Lack of proper authorization to incur costs or to disburse funds

• Non-Federal contributions recorded but not documented

Examples of Costs Not Approved by EPA

• Purchase of capital equipment

• Costs incurred before or after grant/contract period, except Step 1 and 2 grants prior to July
1,1975 (40 CFR 35.925-18)
                                         4-3

-------
    Unresolved costs: During the course of an audit, the auditor should attempt to reach a
definite conclusion as to whether each item of incurred/claimed cost is allowable. There may be
instances in which the allowability of cost cannot be determined without the assistance of an
EPA engineer or other program official. In these instances, the auditor should designate these
costs in the audit report as unresolved pending the Region's approval/disapproval of actual
allowability. Examples of unresolved costs are (1) change orders of force account work not
approved by EPA and (2) costs for which an assist audit has been requested but not received as
of the audit report date.

    The auditor must perform all audit tests on unresolved  costs to determine that the costs
would  otherwise be allowable  pending resolution  of the issue resulting in the cost  being
unresolved.

    4.1.2 Review of Costs

    Under the terms of the grant, EPA's participation in a project is for a limited period. Thus,
EPA may only participate in those costs properly chargeable to that period, with the exception
of certain pregrant costs  which will be allowable (40 CFR 35.925-18). In reviewing costs, the
auditor will be examining total project costs.  For many projects, EPA is only participating in a
portion of the project. Thus, it  will be necessary for  the  auditor to  review the  grantee's
segregation of costs as to the eligible and ineligible portions of the project.

    When portions of the project are considered ineligible,  the ineligible portions should be
clearly identified by EPA in the review of plans and specifications. Bid documents commonly
distinguish between eligible and  ineligible portions of  a  construction  contract. Where the
contractor's monthly pay estimates are prepared on the same basis as the bid  documents,
distinction  between eligible and ineligible construction  costs is simplified. Further guidance
concerning the eligibility of specific items is included in Appendix D of this guide.

    EPA may only participate in the acceptable portion of eligible costs. The auditor  will
review each cost to determine whether it is acceptable as a charge to the  EPA project. During
the audit, the auditor will be testing the systems utilized  by the grantee in managing the grant.
Where items of costs are  shown to be unallowable (unreasonable, unallocable, undocumented,
unapproved, or  ineligible), the costs should be questioned.  Where the  audit tests  have not
disclosed any material deficiency with respect to items of cost,  the cost should be accepted.

    Once the auditor has evaluated eligible construction costs, he will classify the costs as
accepted or questioned.

    The auditor must review costs other than construction costs claimed  to determine whether
or not they are acceptable. He then should allocate other acceptable costs over the eligible and
ineligible portions of the project on the following basis:

                Total  Eligible Construction               Other         Other Eligible
                	Costs Accepted	       x    Acceptable  =    Accepted
                Total Construction Costs                 Costs            Costs

    For final audits, this formula should only be applied in situations where:

    a.  Other acceptable costs  incurred are associated with both eligible  and  ineligible
construction, and

    b.  Accounting records accumulating and segregating these costs are not available.
                                          4-4

-------
Examples of items exempt from this formula are (1) bond costs (on P.L. 84-660 projects),
because the bond formula takes into consideration total eligible project costs (see Appendix B of
this guide for an illustration of bond formula); and (2) special studies not related to construction
which are totally eligible. The auditor should use the above criteria to determine whether the
formula should be applied to a particular cost category.

    For interim  audits  where the eligibility ratio  is applicable,  the following qualifying
language should be incorporated in the report:

    The approved grant application estimates eligible construction costs which, when taken
    over total construction costs, result in an eligibility factor of	percent. To arrive at the
    total eligible project  costs,  a ratio based on  actual costs will be applied to all other
    acceptable costs at the time of the final audit.

Total eligible project costs will be computed as follows:

  Total  Eligible Construction   +   Other Eligible   =   Total Eligible
         Costs Accepted          Accepted Costs     Accepted Costs

    The percentage of project costs  in  which EPA is participating, through the grant
agreement, will then be applied to total eligible project  costs accepted. This will show the
Federal share earned.  The designation of a cost  as questionable by the auditor does not
necessarily mean that the cost will be disallowed. The determination as to the acceptability of
costs will be made by the EPA Regional Administrator.

4.2 GENERAL AUDIT STEPS

    4.2.1 Initial Field Audit Procedures

    In starting the audit, the auditor should:

          a.   Conduct an entrance conference with the official-in-charge upon arriving at the
audit  site. The purpose of the entrance conference is to (1)  inform the grantee of the purpose of
the audit, the general plan of audit approach, and the records to be used during the audit; and
(2) answer the grantee's questions regarding the audit. During the conference, the  auditor
should also arrange for private, adequate working space.

    The auditor  should document the entrance conference in his workpapers. He should
include the names and positions of those attending the conference and details of the matters
discussed.

          b.   Obtain background information on the grantee organization. This may be in the
form  of  charters,  bylaws,  incorporation documents, or  public relations documents  which
identify the nature of the organization's operations and key employees. In addition, the auditor
should obtain copies of the organization's financial reports  as well as access to any audit reports
issued by the organization's internal or external auditors.

          c.   Identify any additional EPA or other Federal grants or contracts awarded to the
grantee. In this regard, the auditor will obtain the grant/contract number, the amount of the
agreement, the status of the  grant/contract,  and the Federal  agency involved. The auditor
should promptly communicate this to the Division  Audit Director so  that he may decide
whether the scope of the audit will be expanded to cover these agreements.
                                         4-5

-------
          d.   Familiarize himself with the grantee's accounting, personnel, procurement, and
property management systems as they relate to grant expenditures. The auditor should initially
obtain information regarding established policies and procedures governing these activities. In
this regard, each audit should be initiated with a survey of the project utilizing, as a minimum,
the survey questionnaire contained in Appendix A of this guide. The purpose of this survey is to
identify significant weaknesses in the systems, as they apply to the EPA grant, and  to establish
the scope of the audit. The survey should include documentation and testing of the records to
validate the information  obtained and  to support decisions affecting the scope of audit.
Appendix A should be included as documentation in the workpapers for all interim audits and
any final audits where the grantee has other active EPA grants.

    4.2.2 Verification of Claim

    The auditor should reconcile the control account (that  is, total cost incurred) with the
latest/final request for reimbursement/cash outlay report and reconcile each expense item in
total to the project cost and/or disbursement ledger. The auditor should:

          a.   Determine the mathematical accuracy of the report and the ledger.

          b.   Determine whether the grantee prepared the report based on its own accounting
records or whether the report was prepared by  EPA or the grantee's consultant.  If it was
prepared by others, determine what records were used.

          c.   Analyze supporting data (e.g., contractor's  and/or  other  certification for
cumulative billing amounts submitted for the cash outlay reimbursement report).

          d.   Determine the total cash payments to the grantee under the construction grant.

          e.   Determine  the total disbursement by the grantee to date  and  compare  with
Federal payments. Any under-  or over-payment should be documented.

    4.2.3 Verification of Eligibility

    Identify from the EPA project file any portions of work under each construction contract
or engineering subagreement which have been designated ineligible for Federal participation.

    Review the grantee's  disbursement ledger to determine if project costs are segregated by
means of a special project account which (1) identifies eligible  and ineligible costs, (2) identifies
allowable and unallowable costs, and (3) contains separate accounts for each item of expense
(FMC 74-4); that is:

          a. Construction, by contract;

          b. Engineering services; and

          c. Legal and administrative services.

    4.2.4 Credits, Rebates, and Refunds

    Throughout the audit, the auditor should be alert for  evidence of  credits,  rebates, or
refunds. Such items  should be credited properly  to the construction account. As part of the
audit:
                                          4-6

-------
          a.   Examine  contractor hillings,  rioting  whether certain  items  are  marked or
indicated for deletion;

          b.   Examine cash receipt records, noting  funds received from contractors and/or
other sources (i.e., state sales tax refunded to grantees or subcontractors); and

          c.   Determine that funds  received for copies  of the phns and  specifications
(unrefunded deposits) are credited to the grant costs.

    4.2.5 Unpaid Bills

    If the grantee has any unpaid bills relating to the specific grant under audit, the following
audit steps should be taken:

          a.   Determine the reasons for the unpaid bills.

          b.   Determine whether there are sufficient funds available to pay  bills in  a timely
manner.

          c.   Assure that costs related to long-standing unpaid bills or retainages have not
been included  on the request for reimbursement or cash outlay report to EPA. If they have,
such costs should be set out in the audit report unless they represent normal accounts  payable.

4.3 SPECIFIC AREAS OF AUDIT

    4.3.1 Audit of the Force Account

    The actual construction work  is normally performed by  construction contractors under
contracts  awarded  through competitive bidding. Construction-related activities  such as
preliminary planning,  designing,  preparation  of plans  and  specifications,  and  resident
inspection  services are normally performed  by consulting engineers  under subagreements.
However, in some instances the work is performed by employees of the grantee. This is known
as "force account" work. If force account costs are claimed, such costs should consist of project
work performed by employee labor  of the  grantee or materials, equipment, and  supplies
purchased by the grantee. (Direct travel costs may be allowed.)

    Determine that:

          a.   Force account work (construction/engineering/administration) was specifically
approved by EPA as provided  in EPA regulations  40 CFR 30.645, 40 CFR 35.935-2, and 40
CFR 35.936-14.

          b.   Construction work  handled through the  force account  was not for repair,
maintenance, or operation of existing facilities.

          c.   Completed construction was appropriately approved by the grantee's engineer.

          d.   Purchases of material or supplies were based on competitive bids as required by
state or local procedures or Federal regulations. (This step may be included under the Review of
Procurement Controls.)
                                         4-7

-------
    The auditor should include in his workpapers a schedule showing force account labor
costs, and on a selective basis he should:

          a. Trace hours charged to time records;

          b. Verify payroll computations;

          c. Verify payments made from the payroll to the construction account; and

          d. Verify fringe benefit costs.

    All indirect costs claimed by the grantee must be supported by an approved indirect cost
proposal. If the auditor encounters a situation where indirect  costs are not supported by an
approved proposal, he should contact the Division Audit Director for further instructions. The
auditor should also be alert for situations where:

          a.  Persons are working in a capacity other than that for which they are getting paid
(e.g., engineer working as a draftsman).

          b.  Costs  are claimed for hours worked  on the project but  not paid  for by the
grantee, i.e., overtime hours not paid for. These costs are not an actual cost to the grantee and
therefore are not allowable.

          c.  Labor hours are charged on a departmental average hourly rate. This should not
be accepted unless there is supporting documentation to prove that it represents actual cost.

          d. Overtime hours are being charged solely to an EPA project when the employee
works on other jobs during the same period.

    The auditor should include in his workpapers a schedule of force account material, supply,
and equipment costs.   On a selective basis, he should:

          a.  Verify types and quantities of items used to issue slips or similar documentation.

          b.  Determine  that  the  amounts charged were  reasonable and  computed in
accordance with the grantee's normal costing policy.

          c.  Determine that  costs claimed do not  include nonexpendable  construction
equipment (i.e., exceed minimal cost and  life expectancy) even though such equipment may
have been purchased specifically for the project.

          d.  Determine that any write-offs of expendable items do not exceed the amounts
allowable under the cost principles contained in FMC 74-4.

          e.  Determine whether the  grantee followed  EPA guidance in disposing of or
adjusting costs for unused materials which remained after completion of construction.

    If use allowance or rental rates were used in arriving at costs charged  to the project,
determine whether these factors are in line with FMC 74-4. Review and test the method used to
accumulate hours of equipment usage. Test payments made for use of equipment  to invoices
and cancelled checks  and/or to fund transfer documents.
                                         4-8

-------
    4.3.2 Audit of Engineering Services

    In reviewing procurements of engineering services, the auditor should be aware that EPA
regulations governing these procurements  have changed with  the issuance of Program
Guidance Memorandum (PG) 53 and with the issuance of EPA's "Subagreement Regulations
for Construction Grants" (40 CFR 35.935,  35.936, and 35.937, dated December 17, 1975).
Appendix F  to this  guide  (Consulting Engineer  Subagreements—Allowable Methods of
Compensation) addresses the acceptability  of the type  of engineering contract during the
transition period of the December 17,  1975, regulations. Accordingly, the audit criteria may
change depending upon  whether the engineering contract  was awarded prior to or after the
effective date of the above regulations.

          a.   Contracting procedures

    It is the  responsibility of the grantee  in contracting for engineering  services  to take
reasonable measures to ensure that services are obtained from qualified firms at a reasonable
price.

    Grantees could prior to July 1, 1975, use their own procurement regulations which reflect
applicable state and local laws, rules, and regulations, provided that these rules and regulations
adhere to minimum standards as set forth in Attachment  O to FMC 74-7.  Effective July  1,
1975, grantee procurements of consulting engineering services must be in accordance with the
requirements  of Program Guidance Memorandum 53. Effective December 17, 1975, grantee
procurements  of consulting  engineering services  must  be in  accordance  with  (1) the
requirements  of Appendix D to EPA's "Subageement Regulations for Construction Grants"
(which superseded PG 53) and (2) 40 CFR 35.936 and 35.937.

    For  procurements awarded under 40 CFR 35.936 and 40 CFR 35.937, the auditor should
review the grantee's procurement procedures for consulting engineering services and determine
that these procedures include, where applicable, requirements for:

               (1) Public notice (40 CFR 35.937-2);
               (2) Evaluation  of qualifications (40 CFR 35.937-3);
               (3) Solicitation and evaluation of proposals (40 CFR 35.937^-);
               (4) Negotiation  (40 CFR  35.937-5);
               (5) Cost and price  considerations  (40  CFR 35.937-6
                     and 40 CFR  35.937-7);  and
               (6) Required solicitation and Subagreement provisions
                   (40 CFR 35.937-9).

    Note that 40 CFR 35.937(a) provides that the provisions of 35.937-2 (Public Notices),
35.937-3 (Evaluation of Qualifications),  and 35.937-^  (Solicitation and Evaluation  of
Proposals)  are not required, but may be  followed where  the  population of the  grantee
municipality is 25,000 or less according to the most recent U.S. census. When $10,000 or less of
services (e.g.,  for consultant or consultant subcontract services) is required, the provisions of
35.936-19 (Small Purchases) shall apply.

    For  procurements awarded prior  to the effective date of 40 CFR  35.936 and 40 CFR
35.937, the auditor should determine that the grantee has documentation to show that:

               (1) Procurements were conducted so as not to prohibit maximum open and
free competition.
                                         4-9

-------
               (2)  Contracts were made only with responsible contractors who possess the
potential ability to perform successfully  under the terms and conditions of a  proposed
procurement. Consideration should have been given to such matters as contractor integrity,
record of past performance, and financial and technical resources.

               (3)  The contract clearly defines the scope of services to be provided under
each reimbursement method included in the contract.  The contractual language should be
specific enough to identify the services provided under each phase of the contract.

    Agreements between grantees and engineering  firms covering engineering  services take a
number of forms. Usually, a single agreement covers all phases of engineering. Traditionally,
these agreements were entered into well in advance of the award of a construction grant and
represented a continuing relationship for engineering services. The reimbursement provisions
contained in such agreements varied from a single fee covering all services to separate fees for
each phase of work or combination thereof. Historically, the reimbursement for engineering
services included: (a) firm-fixed-price (lump sum) contracts, (b) time and materials (labor hour)
contracts, (c) percentage-of-construction-cost  (fee curve) contracts, and (d) actual Isbor cost
plus a stipulated multiplier for overhead and profit (cost plus a percentage of cost).

    However, for  agreements awarded  after June  30, 1975, the cost-plus-percentage-of-cost
(including salary multiplier where profit is included in the multiplier) and the percentage-of-
construction-cost   types  of  contracts  are  not  acceptable. (See  Appendix  D  to  EPA's
"Subagreement Regulations for Construction Grants," published December 17, 1975.)

    In some cases a negotiated subagreement may have been executed prior to July 1, 1975, to
cover work under more  than  one step  of a grant.  Guidaace for these situations is given in
Appendix D as referenced above.

    Note that Appendix E has been added  to this guide to provide an outline  of the types of
records subject to audit under various situations, and Appendix F has been added to provide an
analysis of types of engineering contracts allowable during the transition period.

          b.   Contracts for engineering services awarded prior to July 1, 1975

    EPA does not consider that the fee curve or multiplier method of compensation ensures a
reasonable price in the absence of an effective negotiation based on current cost data. However,
EPA does not take exception to these forms of contracting prior to July 1, 1975,  as they were in
accordance with industry practices which EPA regulations did not prohibit. The auditor's
report should disclose instances where  the fee curve or multiplier  forms of contracting were
used.  The auditor  will not be responsible for determining the reasonableness of fees awarded
under the fee curve or 1 he multiplier. However, the auditor will be responsible for evaluating the
application of the fee curve for reasonableness and consistency. The fee curve will be evaluated
in accordance with historical and advisory guidelines in general use or guidelines acceptable
locally such as the American Society of Civil Engineers  (ASCE) Manual  No. 45. Other data
relied upon or utilized by the contracting parties in negotiation of the agreement will also be
evaluated for reasonableness and consistency.

    In cases where engineering services are compensated under a multiplier, fee curve, or FFP
contract awarded prior to July  1, 1975, the  following  audit steps and paragraphs, as
appropriate,  should be  included  in the schedule and referenced  to technical service costs
incurred, claimed, accepted, and questioned.
                                         4-10

-------
    If multiplier and/or tec curve v •:• nv-i, MI'-I i::<- •'Q'l.<>yi.'ig^aragraph_shoulJLbe included
in the report

    We   noted   that   compensation   lor   engine?; ir-g   services   was  based   upon
    the	  method <>!' con!i acting.  I he use of the	   	and
    profit resulting solely therefrom have been accepted because, at the time the contractual
    arrangement was made, this  me'hod  of contracting  was  not prohibited and was  in
    accordance with accepted industry  practices. The.-   	  method  of
    contracting is now prohibited try Appendix D to Snbpart E of 40 CFR 35, dated December
    17, 1975.

    If a multiplier contract was used, the auditor should:

               (1)  Determine whcthet  t.'ic amounts hilled were based on the terms of the
agreement.

               (2)  Determine whether  the  grantee  has  performed  an  audit of  the
engineering firm's records to establish the propriety of rhe salary rates and hours billed. If not,
the auditor should arrange through the grantee to perform an audit of the engineer's records. In
instances where access to records is denied,  aU  engineering fees billed under this method of
contracting should be questioned.

    If a fee curve contract was used, the auditor should:

               (1)  Determine whethei the (Ve billed agrees with the contract terms as to the
rate used and the method of application

               (2)  Ascertain  whether the fee provided in the contract is consistent with the
ASCE or state society guidelines in effect a< 1 he lime oi'the award. If not, why?

               (3)  Ascertain  whethei  ihe ree percentage is determined in accordance with
the engineering agreement  and wheihir ;he  use of  separate contracts is justified (e.g.,
interceptor versus treatment plant). If sepaiaie  contracts  aie not justified, the additional
compensation should be questioner!


    If an FFP contract  was used jnjhe £bseiK_e_o[ an ct'feciive price  negotiation, then th^e
following paragraph should be included in (he repmr

    We noted that compensation for engineering services was based upon a firm-fixed-price
    method of contracting without the use of tin  the gi antee.
                                         4-1 i

-------
               (2)  Evaluate the reasonableness of the fixed price. In this regard, the auditor
should compare the services provided, the price charged to the services, and the price obtained
by using the fee curve as outlined in the ASCE manual,

          c.   Contracts for engineering services awarded subsequent to June 30, 1975 (under
EPA  "Subagreement Regulations for Construction Grants,"  40 CFR 35.936 and 40 CFR
35.937)

    Determine whether the grantee performed a negotiation to establish the reasonableness of
compensation. As a minimum, this should include a cost review to determine the composition
of each element of cost and the profit proposed by the consulting engineer.

    Unless available documentation  shows that  the grantee's negotiation  resulted  in  a
reasonable price, the auditor will review the reasonableness and validity of cost data submitted.
Where review of the engineer's records shows that cost data was incorrect,  unreasonable, or
unallowable under applicable cost principles (FPR 1-15.2, FPR 1-15.4),  the excessive costs
should be  questioned.  In addition,  the fee  curve  and multiplier contracts where profit is
included in the multiplier are generally considered ineligible if awarded after June 30, 1975.

    The right of access to  records in auditing charges for engineering services under
agreements awarded prior to the effective date of EPA's "Subagreement Regulations for
Construction Grants" is governed by the terms of the engineering agreement and Appendix D
to the Subagreement regulations. This guidance generally prescribes the right  of audit access to
the engineer's records. In instances where indications of fraud, gross abuse, or corrupt practices
are noted, the auditor has the right of access to all records. Refusal by a consulting engineer to
allow access to his records as provided by Appendix D will render costs incurred under such
contracts ineligible. Accordingly, all such costs will be questioned pending access to records.
See Appendix E to this  guide, Consulting  Engineer Subagreements-Records  Subject to Audit.

    Guidance for reviewing engineering costs is as follows:

          d.   Verilication of engineering costs

    Before auditing the  engineering firm's records, the auditor should determine from the
Division Audit Director whether another Federal agency has audit cognizance of the firm. If
another agency has cognizance, the Director will provide further instructions. If no other
agency has audit cognizance, the auditor should complete the applicable sections of this guide.

               (1)  Determine amount  of charges for engineering services. (This should be
detailed by services billed under the various methods of reimbursement, e.g., FFP or CPFF.)

               (2)  Based on a review  of the records, determine that claims for services
provided are applicable to the eligible portion of the construction.

               (3)  Determine whether technical service costs were incurred prior to the
EPA approval of the grant award or after the date of completion of construction. If work was
initiated before October 31, 1974, prior EPA approval was not required. However, for grants
awarded after this date the provisions of 40 CFR 35.925-18 apply.

               (4)  When evaluating the engineering services  charged  on a reimbursable
basis, determine that:

                     (a) Salaries of partners doing less than "partner's" work (e.g., drafting)
are billed at a rate commensurate with the duties performed.


                                         4-12

-------
                     (b)   Services included as a basic service under an FFP or fee curve
contract are not also billed on a reimbursable basis.

                     (c)   An offsite overhead rate was used when appropriate.

                     (d)   Partners' salaries are reasonable.

               (5)  Determine the adequacy of the engineering firm's accounting system to
account for the type of contract awarded.

               (6)  Determine that the costs of engineering services claimed by the grantee
do not include charges related to ineligible services such as site acquisition, bond preparation,
easement, rights-of-way, or claims against the government. The engineer's invoice should be in
sufficient detail to clearly define the nature of the work performed.

               (7)  Verify the mathematical accuracy of the billing for engineering services
and test grantee payments for engineering services to vouchers and cancelled checks.

          e.   Engineering services compensated under the fee curve

    Question all costs billed under this method of compensation for agreements entered into
after June 30,1975.

    For subagreements awarded prior to July 1, 1975:

               (1)  Determine whether the amount billed agrees with the contract terms as
to the rate used and the method of application.

               (2)  Ascertain  whether  the  compensation provided  in  the contract is
consistent with the ASCE or state society guidelines in effect at the time of the award, except as
provided for in steps three and four below.

               (3)  Determine whether the compensation (fee) percentage is based upon the
total of all construction contracts under a specific project (e.g., treatment  plant, interceptor
sewers). If a separate fee percentage was used for each contract, the resulting additional cost
should be  questioned. In  determining  the allowability  of costs based on a  separate fee
percentage for each contract, consider the appropriate ASCE or state society guidelines in effect
at the time  the  engineering agreement was negotiated. (See Appendix I of this guide,
Application of Paragraph B.5 of Appendix D to 40 CFR 35, Subpart E.)

               (4)  Paragraph B.5 of Appendix D of 40 CFR 35, Subpart E, provides that in
no event will allowable costs for a percentage-of-construction type contract be based on an
amount exceeding the  low bid  for  construction.  This specifically  excludes  the  cost of
construction  contract change orders  and  cost overruns from the computation basis. The
method of computing allowable  cost depends on the time between  completion  of plans/
specifications and bid opening.

                     (a)  Less than one  year: If  less  than   one  year  elapses  between
substantial completion and bid opening, paragraph B.5.a of Appendix D limits allowable cost to
the amount obtained by applying the applicable fee  curve percentage to the low bid for
construction.
                                         4-13

-------
                     (b) More than  one year:  When one  year  or more  elapses between
substantial completion of design  and bid opening,  paragraph B.S.b of Appendix D limits
allowable costs to the lowest of:

                     •  The applicable fee  curve  percentage  applied  to  the total  of the
consulting engineer's construction cost estimate provided at  substantial completion of plans
and specifications plus an escalation of up to five percent of the estimate.

                     •  The applicable fee curve  percentage applied  to the  consulting
engineer's construction cost estimate provided  at  substantial completion  of  plans  and
specifications. A consulting engineer's compensation escalation of up to $50,000 is added to the
resultant amount.

                     •  The applicable fee  curve  percentage  applied  to  the low bid for
construction.

                (5)  It is EPA policy to recognize those costs incurred by  the consulting
engineer that are not in the scope of the contract at the time of the construction contract award.
For example, a  change (ordered by the grantee/owner) which  requires specific design and
specification preparation by the consulting engineer in the scope of the construction contract
probably should be recognized as requiring a change in the consulting engineer's contract for
which  reasonable  additional  compensation is allowable. Conversely,  additional consulting
engineering fees will not be considered eligible if these fees are the result of a change order to the
construction  contract to correct  a design deficiency which  is attributed to  the consulting
engineer.

    Of course, these two examples are the extremes in the premises, and between these two
poles may arise situations requiring a subjective judgment on the part of the EPA project officer
as to the validity  of the consulting engineer's request for added  compensation. Additional
compensation for such design work should be based on actual  cost  records available for audit.

    In the absence of cost records, the auditor should determine whether the change order was
of a type which generated an increase in design effort and, therefore, an increase in design cost.
Certain change orders do not require additional design effort; for example, an increase solely in
construction  quantities does  not  increase design cost. However,  a change ordered by the
grantee/owner  for a  modification in the scope of  the construction contract does require
additional design effort. If these  additional design  costs are not supported  by actual  cost
records,  the costs should  be suspended  with  the recommendation  that  the  Regional
Administrator determine the eligibilty of these costs.

    Also, in the period between the original substantial completion (a subjective judgment on
the part of the project engineer) and the bidding of the project, EPA regulations may have been
issued  which would require  some changes  in  the  plans  and specifications  for which the
consulting  engineer  could request, and EPA  could pay, additional compensation under
Paragraph B.S.c of 40 CFR 35, Subpart E, Appendix D.

          f.  Engineering services reimbursed under firm-fixed-price contracts

                (1)  Determine that the amount billed is in accordance with the terms of the
agreement and Appendix D to EPA's "Subagreement Regulations for Construction Grants"
(Part B of Appendix D to Subpart E of 40 CFR 35) and that the  work was accepted by the
grantee.
                                         4-14

-------
               (2)  For FFP contracts awarded prior to the subagreement regulations (July
1,  1975), the auditor should evaluate the reasonableness of the fixed price. In this regard, the
auditor should compare the services provided and price charged with the services and price
obtained by using the fee curve as outlined in the ASCE manual. Amounts in excess of the
comparable fee curve percentage should be questioned.

               (3)  For FFP agreements in excess of $100,000 awarded after  June 30, 1975,
the auditor should analyze the information documenting the grantee's cost  review of the
composition of costs and perform audit steps four through eight below. (See 40 CFR 35.937-6.)

               (4)  Determine what review was performed by the grantee to determine the
reasonableness and validity of the amounts proposed (both quantity and dollar estimates).

    Where the grantee has not perfomed a review of subagreement costs or the review is
considered inadequate, the auditor should furnish the Division Audit Director with a list of all
applicable subagreements. (A review of proposed subagreement costs is considered adequate if:
(a) the  grantee's in-house engineering staff develops an independent, detailed cost estimate
which, when compared to the proposed consulting engineering cost estimate, demonstrates the
reasonableness of the proposed amount; (b) the grantee performs a verification of the proposed
costs and quantitites to the data used by the engineering firm in developing the proposal; or (c)
sufficient cost and pricing data for work similar to this project is available to provide a basis for
comparison.) The Director will decide whether an audit of the subagreement is necessary and
will advise the auditor reviewing the grant.

    If another agency will perform the audit, the Division Audit Director will initiate the
request for audit and provide a copy of the request to the auditor performing the review of the
grant. The  auditor does not have to wait for the results of audit requests from another Federal
agency; he should prepare the audit report and set aside the requested  portions. The audit
report should explain that the subagreement is being audited by another audit agency and that
the results will be transmitted as soon as received.

    If the Division  Audit Director has  determined that no  other Federal audit agency is
cognizant and that the subagreement should be audited, the auditor should make arrangements
to perform an audit of the documentation maintained by the engineering firm. In instances
where access to records necessary for the audit is denied, all engineering fees billed under this
method of compensation should be questioned pending access to records.

               (5)  The auditor should compare the fixed price negotiated under the contract
and the engineer's actual incurred costs. When  actual costs were  substantially less  than
estimated costs included in the proposal  used as a basis for  negotiation, a comparison of
estimated and actual incurred quantities (labor hours/material quantities, etc.) should be made.
(EPA regulation 40 CFR 35.937~6(c)(6) requires that the engineer account for costs in the same
manner in which he proposes costs.)

               (6) In instances where the actual  quantities (labor hours) were significantly
less than estimated quantities, the auditor should obtain an explanation for the differences from
the consulting engineer. Where the reduction in quantities was due to new and improved work
methods or efficiencies in performance, the auditor should accept the lump sum price. In other
instances, the auditor should review the data used for estimating the quantities included in the
consulting  engineer's proposal. In instances where the data used as a basis for negotiation was
not complete, current, or accurate, the auditor should question amounts claimed in excess of
costs computed using complete, current, and accurate data.
                                         4-15

-------
               (7) In instances where actual costs were significantly less than estimated costs
and where actual quantities did not vary significantly from estimated quantities, the auditor
should review the engineer's cost proposal used as a basis for negotiation.

               (8)  In reviewing the  engineer's  cost proposal, the auditor should as  a
minimum determine that costs proposed were allowable under FPR 1-15.2 and 1-15.4.

    In instances where amounts proposed do not represent current (at the time of negotiation),
valid cost or pricing data, the auditor should question any amounts claimed in excess of those
computed using current, complete, and accurate cost data.

    The auditor should determine that:

                     (a)  Salary rates proposed represented current salary data, factored for
the length of the contract.

                     (b)  Fringe benefits  represented  cost history based on  actual fringe
benefit cost incurred by the engineering firm.

                     (c)  Costs  of material and  supplies  were based  on  current  cost
information.

                     (d)   Costs  of subcontracts  were based  on  properly  documented
previous experience of similar work or bids from the prospective subcontractors.

                     (e)  Travel costs were based  on amounts regularly paid under  the
engineer's standard procedures.

                     (f)  Other direct costs were based on accurate, valid costing data.

                     (g)  Indirect  costs  were proposed  based  on  rates  computed  in
accordance with FPR 1-15.2 and 1-15.4.

          g.   Engineering services reimbursed under the multiplier form of contracting

               (1)  Question  all costs billed  under  this method  of  compensation  for
agreements entered into after June  30, 1975, unless the  agreement complies with 40 CFR
35.937-l(d) of the EPA "Subagreement Regulations for Construction Grants."

    However, for  agreements awarded under the new regulations, if under either a  CPFF or
firm-fixed-price contract the grantee desires to utilize a multiplier for interim billing purposes,
all of the following must apply:

                     (a) The multiplier and the portions of the multiplier allocable to
overhead and allocable to profit have been specifically negotiated;

                     (b) The portion  of the multiplier allocable to overhead includes only
allowable items of cost under the cost principles of FPR 1-15.2 and 1-15.4;

                     (c) The portions of the muliplier allocable to  profit and allocable to
overhead have been separately identified in the contract; and

                     (d)  The firm-fixed-price contract includes a guaranteed maximum price
for completion of the specifically  defined scope of work; the CPFF contract includes a fixed
                                         4-16

-------
dollar profit which may not be increased except in case of a contract amendment which
increases the scope of work.

    Thus, the multiplier is not an acceptable form of contracting in itself, but under a CPFF or
FFP contract it may  be used for interim billing purposes. Cost claimed under a multiplier
arrangement not meeting the above criteria should be questioned.

                (2) For agreements entered into prior to the effective date of the  new
subagreement regulations:

                     (a)   Determine whether the amounts billed were based on the terms of
the agreement.

                     (b)   Determine  whether the grantee has performed  an audit of the
engineering firm's records to establish the propriety of the salary cost billed.

                     (c)   In establishing the acceptability  of salary cost used as a base to
which the multiplier is applied, use actual salaries and wages paid. In addition, make sure that
the multiplier is applied to the labor of only bona fide employees of the engineering firm.

                     (d)   Regardless  of contract terms, the  actual costs of fringe  benefits
must be supported by the accounting records when they are claimed as a direct charge. If the
charges are not supported or if the actual cost is less than the amount claimed, the total of the
difference is unallowable for Federal participation. Where the fringe benefits are claimed as a
direct charge and also included in the multiplier, the duplicate direct charge is unallowable for
Federal participation.

                     (e)   Regardless of contract terms, question charges made to the grant
where there was no cost incurred. Labor charges and related costs for straight time or overtime
hours which are billed but for which cost has not been incurred will be unallowable for Federal
participation.

                     (f)   Regardless of contract terms, the actual cost of service  charges
must be supported  by accounting records. Service charges are defined as any supplemental
charges added to other direct cost (nonsalary) which are claimed on an actual cost basis. If the
service charges are not supported or if the actual cost is less than the amount claimed, the total
or the difference is unallowable for Federal participation. This is in accordance with the ASCE
manual, which states that the service charge is for expenses to be reimbursed by the client. (See
PG 64, dated February 5, 1976.)

    In reviewing direct costs claimed by the engineer, the auditor should determine whether
service charges are claimed on an actual cost basis or a percentage added to a direct cost item
(for example, service charge of X% added to the cost of supplies purchased or outside services).
When such claims are identified, the auditor should:

                           •  Determine the   engineer's  actual  cost of  the services as
supported by the accounting records.

                           •   Determine that  costs included  in the service  charge  are
consistently applied and are not duplicated in other accounts (e.g., overhead).

                          •   Compare the service  charge  applied to the actual cost of the
service and question any over-recovery of actual cost.
                                         4-17

-------
          h.   Engineering services reimnmsr-d nude;  s time and materials form of contracting

               (1)  Determine whcliici  tlio  giants  ha»  performed  an  audit of  the
engineering firm's records to establish the pioi/r K;! > of labor hours billed.
               (2)  For time and materials contracts ove  5100,000 awarded after June 30,
1975, perform Step 4 under FFPconira, t-    i%.'-v t-^"--}  lc /

               (3)  Determine the JtJ.-quacs •» flu; lirnA accounting system to identify and
accumulate project labor hours.

               (4)  Verify the rc-. ur.. •> . >t >\n Lib. t :,viu<,i 'aimed to the accounting records.

               (5)  Determine that the categories of labor billed are in accordance with the
contract terms and that employees are charged in the correct classification.

               (6)  In reviewing costs claimed under u lime and materials contract awarded
under 40 CFR 35.937, the auditor should compaie the iaU;s claimed to the engineer's proposal,
which details the labor rates, overhead rate, and pioht factor used as a basis for negotiation. The
auditor should determine that:

                     (a)   The labor raies  used  as  a  basis for negotiaion were based on
complete, current, and accurate cost data al the time of negotiation. The cost data used should
include actual  average  labor rates for  eategones of employees or  for specific employees
anticipated to perform the work.

                     (h)   The overhead rates used as a b.isis for negotiation were prepared in
accordance with FPR 1-15.2 and 1154 and were based on complete, current, and accurate
cost data.

               (7)  In instances where the total rate negotiated under 40 CFR 35.937 was not
based on complete, current,  and accurate cost data or was not prepared in accordance with FPR
1-15.2 and 1-15.4, the auditor should compute an acceptable rate, using current, complete, and
accurate cost data, and question amounts resulting  from rhe use of an unacceptable rate. The
auditor should determine that:

                     (a)   Salary rates proposed represented current salary data, factored for
the length of the contract.                                    *

                     (b)   Fringe benefits represented cost  history and were based on actual
fringe benefit costs incurred by the engineering firm.

                     (c)   Indirect  costs  were  proposed  based  on  rates  computed  in
accordance with FPR 1-15. 2and 1-15.4.

          i.   Engineering services reimbursed under a cost-plus-a-fixed-fee contract

               (1)  Determine whether  the grantee  has  performed  an  audit  of the
engineering firm's records to establish the propriety of costs billed.

               (2)  Where the gramee has not performed reviews of subagreement costs or
the reviews were inadequate, the auditor should furnish (he Division Audit Director with a list
of all applicable subagreements.  The Director will decide whether an audit is needed and, if one
is needed, who will perform the audit. If no audit of the subagreement is considered necessary,
                                         4-18

-------
the Division Audit Director will so advise the auditor reviewing the grant. In such cases, the
costs claimed under the subagreement will be considered allowable if costs were claimed in
accordance with subagreement provisions.

    If another agency will perform the audit, the  Division Audit Director will initiaie the
request for audit and provide a copy of the request to the auditor performing the review of the
grant. The auditor does not have to wait for the results of audit requested from another Federal
agency; he should  prepare  the audit  report and set aside the requested portions. The audit
report  should explain that the subagreement is being audited by another audit agency and tha-.
the results will be transmitted as soon as received.

    If the Division Audit  Director has determined that no other Federal audit agency is
cognizant and that  the subagreement should lie audited, the auditor should make arrangements
to perform an audit of the documentation maintained by the engineering firm.

                (3)  Determine whether other direct costs claimed are reasonable, applicable,
and allowable under the terms of the contract and the Federal cost principles contained in FPR
1-15.2 and 1-15.4.

                (4)  Review  the  firm's overhead  rate to determine that it  is  reasonable,
equitable, and in accordance with the principles set forth in FPR 1-15.2 and 1-15.4 and the
"EPA Audit Guide for Reviewing Indirect Cost Allocation Plans and Rate Proposals."

                (5)  More complete guidance as to the audit of CPFF contracts is contained
in the  "Audit Guide for EPA Contracts." The overhead rates considered allowable by the
auditor should be used in determining allowable indirect costs under the subagreement.

    4.3.3 Audit of Construction Costs

    Plant construction and equipment costs  represent a major  portion of the construction
grant program. The grantee will normally have established a procedure or engaged the design
engineer to ensure  that construction is in accordance with the specifications, plans, schedules,
and construction contract.  For grants awarded under P.L. 92-500, the basic procurement
system requirements and procedures  utilized to award the construction contract must be in
accordance with the applicable grant  regulations (40 CFR 35.936 and 40 CFR 35.938, dated
December 17, 1975).Specific criteria for procurement systems are outlined in section 3.4.2 of
this guide.

    In reviewing procurements of construction contracts, the auditor should  be aware that
EPA regulations governing these procurements  have changed with the issuance of EPA's
"Subagreement Regulations for Construction Grants." Accordingly, the audit criteria may
change depending  upon whether the construction contract was awarded prior to or afier the
effective date of the revised regulations.

          a. Audit guidance for basic construction contracts and change orders

                (1)  The  auditor  will review the  grantee procurement records  for  each
construction contract awarded in excess of $10,000 to determine whether-.

                     (a)   Construction contracts  awarded under the grant are firm fixed
price or unit price or combinations of two (40 CFR 35.938-3).

                     (b)   Adequate public notice (40 CFR 35.938-4(a)) was given.
                                        4-19

-------
                     (c)  Adequate time (40 CFR 35.938-4(b)) was given  for preparing
bids.

                     (d)  Bidding documents include (40 CFR 35.938-4(c)):

                          •  A complete statement of the work to be performed, including
necessary drawings and specifications and the required completion schedule;

                          •  The terms and conditions of the contract to be awarded;

                          •  A clear explanation of the method of bidding and the method
of evaluating bid prices; and

                          •  Responsibility requirements or criteria which will be used in
evaluating bidders.

                     (e)  The grantee provided for sealed bids and  for safeguarding bids
received until public opening (40 CFR 35.938-4(d)).

                     (f)  Contracts were awarded  to  the lowest  responsive, responsible
bidder. If not, determine what rationale exists for awarding to other than the lowest bidder  (40
CFR 35.938-4(h)).

                     (g)  Approvals were obtained from EPA prior to contract award.

                     (h)  Awarded  contracts   contain  a   provision  for  access  to
contractor/subcontractor  records,  reports,  drawings,  and accounts for the  purpose of
inspection, review, copying, and audit by EPA representatives (40 CFR 35.935-7).

                     (i)  At least two brand names followed  by the  words "or equal"  are
used in the specifications (P.L. 92-500 and 40 CFR 35.936-13(a)(l)). The use of only one brand
name is considered restrictive.

                     (j)  Items considered ineligible to EPA were identified as ineligible in
the contracts.

                     (k)   Special circumstances  or provisions pertaining to the  contract
require review; e.g., implementation of the provisions of the Uniform Relocation Assistance
and Real Property  Acquisition Policies Act  of 1970 when acquiring real property for  the
project. (Appendix C of this guide provides supplemental procedures for auditing relocation
costs.)
               (2)  Review and test the grantee's procedures for accumulating cost of change
orders.

               (3)  Determine if change  orders to the  contract(s)  pertain to eligible
construction and have been reviewed, checked  for duplication of base contract items, and
approved by EPA. If approvals from EPA have not been received, such costs are not acceptable.

               (4)  Determine whether documentation is maintained that demonstrates the
purpose, cause, necessity for the change order(s), and reasonableness of the change order price.
In this regard, determine whether costs and quantities estimated were supported  and evaluated.
Be alert for instances where support for a change order indicates that work was for a purpose
other than that described on the change order.
                                         4-20

-------
               (5)  Determine that change orders for quantity increases or decreases were
approved by the grantee as soon as it could be readily determined that a change was necessary
and/or an overrun/underrun would occur.

               (6)  Determine that credits for deletions have been included in the change
order. Credit for deletions from FFP contracts should be based on the market price at the time
of deletion. Credit for deletions from unit price contracts should be based on the bid price of the
item.

               (7)  Determine that  prior EPA  approval was obtained for changes over
$ 100,000 and changes in the scope of the project.

               (8)  Determine whether the grantee  or consulting engineer  performed an
evaluation to establish the reasonableness of the change order price (40 CFR 35.938-5). Note
that EPA regulation 40 CFR 35.938-5 does not technically apply to change orders under grants
awarded prior to  March 1, 1976. However, the requirement to assure the reasonableness of
change order costs has always existed in EPA regulations. Although 40 CFR 35.938-5 is not
applicable, the principles prescribed by this regulation are just good business practices; thus,
procedures comparable to those required by this regulation should be followed in negotiating
change order prices. Therefore, in auditing change orders under grants awarded prior to March
1,  1976, the auditor should follow the same basic  audit procedures used for auditing change
orders under grants awarded after March 1, 1976. It is important to be aware, however, that in
writing deficiencies related to these change orders, the auditor should not cite 40 CFR 35.938-5
as a specific requirement.

                     (a)   Original Bid Item. For variances in quantities of items included in
the original bid package, it is acceptable to use the original bid price. However, if the variance is
significant (15  percent)  and the dollars are material,  the grantee should be  required  to
demonstrate it has evaluated the reasonableness of using the original bid price.

                     (b)   New Items. Since the reasonableness of the price of new bid items
was not established in the basic award, the grantee should take adequate measures to assure that
new items are reasonably priced. Prices for new items should be established on the basis of an
independent estimate developed from current cost and pricing data or a detailed analysis of the
data  used to  develop  the  contractor's  price.  The responsibility  for establishing  the
reasonableness of change order prices is frequently delegated to the consulting engineering
firms. In these instances, the audit should include a review of the engineer's records, which
should contain estimates of man-hours to  be expended, quantities of material,  hours  of
equipment usage, and cost and pricing data.

               (9)  Change orders under grants awarded  after the effective date of EPA's
"Subagreement Regulations for Construction Grants"  (40 CFR 35.936 and 35.938) must be
negotiated on the basis  of current cost and pricing data furnished by  the contractor to the
grantee. For FFP or unit  price change orders awarded,  the auditor should  analyze the
information documenting the grantee's cost review of the composition of costs and perform the
following audit steps:

                     (a)   Determine what reviews were  performed by  the grantee or its
consulting engineer to ascertain the reasonableness  and validity of the amounts proposed (both
quantity and dollar estimates).

                     (b)   Where the grantee  has not performed a review of change order
costs or the reviews are considered inadequate, furnish the Division Audit Director with a list of
all change orders  under the specific contract being reviewed.  (A review of proposed change
                                         4-21

-------
order cost is considered  adequate if (!)  ihe grantee or its consulting engineer develops an
independent detailed cosi estimate which when compared to the contractor's proposed change
order cost demonstrates the reasonableness of the amount proposed or (2) the grantee performs
a verification of the proposed  costs and quantities to  the data used by the contractor in
developing the proposal.) The Director will decide whether an audit of the contractor's records
is needed. If no audit of the subcontracts is considered necessary, the Division Audit Director
will so advise the auditor -eviewing the grant. In such cases, the costs claimed under the change
order will be considered allowable if costs were claimed in accordance with FPR 1-15.2 and
FPR 1-15.4. If the Division A.udit Director has determined that an audit of the contractor's
records is necessary, the auditor  should  make arrangements to audit the documentation
maintained by the contractor.

                     (cj  Initially, compare the amounts paid under the  contract and the
contractor's actual incurred costs. Where actual costs were substantially less than estimated
costs, compare estimated and actual incurred quantities (labor hours/material quantities, etc).

                     (d)  In instances where the actual quantities (material and man-hours)
were significantly less than estimated quantities, obtain an explanation of the differences from
the contractor. Where the reduction in quantities was due to new and improved work methods
or other efficiencies, the auditor should accep! the amount negotiated for the change order. In
other instances, the auditor should review the data used for estimating the quantities included
in the contractor's proposal.  In instances where the data used as a basis for negotiation was not
complete, current, or accurate, the auditor should question amounts claimed in excess  of costs
computed using complete, current, and accurate data.

                     (e)  In instances  where  actual  costs were significantly less  than
estimated costs and where actuai quantities did not vary significantly from estimated quantities,
review the contractor's cost proposal used as a basis for negotiation.

                     (0  In instances where amounts proposed do not represent current (at
the time of negotiation), valid cost or pricing data, question any amounts claimed in excess of
those computed using current cost data.  The auditor should  also ascertain the rationale for
differences disclosed above. (See40CFR 35.938-5.)

                     (g)  In reviewing the  contractor's  cost proposal, as  a minimum
determine that:

                           •  Salary rates proposed represented current salary data factored
for the length of the contract.

                           •  Fringe  benefits represented cost history based on actual fringe
benefit cost incurred by the engineering firm.

                           •  Costs of  material and  supplies  were based on current cost
information.

                           •  Costs of  subcontracts were based on properly documented
previous experience of similar work or bids from the prospective subcontractors.

                           •  Other direct costs were based on accurate, valid costing data.

                           •  Indirect costs were proposed based on  rates computed in
accordance with FPR 1-15.2 and 1-15.4. (See 40 CFR 35.938-5(d)(4).)
                                         4-22

-------
               (10)  Determine  that all  credit  (decrease) change  orders  have  been
considered in interim or final payments to contractors.

               (11)  Determine whether the work was  completed and accepted by  the
grantee or its designated representative.

               (12)  Determine whether the engineer accepted the change order work as
complete and in accordance with the change order specifications.
                                  4
               (13)  If the auditor is  unable to assure himself that the reasonableness of the
change order was evaluated by the  grantee or the engineer, he should question the cost and
make a recommendation that the Region determine whether to participate in the cost of the
change order.

               (14)  Determine whether the contractor completed  construction within  the
time constraints provided in the contract. In instances where construction was not completed
within the time frame established by the contract, including amendments, determine whether or
not the grantee recovered liquidated damages as spectified in the construction contract. Any
additional cost—construction, engineering, legal,  or  administrative-generated because of a
contractor's lack of performance should be covered by the liquidated damages clause. Thus, any
such increase in cost is unallowable for Federal participation even if the grantee elects not to
exercise its right to recover liquidated damages.

          b. Verification of construction pay estimates

     It is the grantee's responsibility to  establish adequate controls to ensure that construction
contractors  are paid only  for  construction work performed  and materials and equipment
furnished.

     Audit tests of construction  pay  estimates  depend, to a large  degree, on  the type of
construction contract awarded, i.e., FFP, unit price, or a combination of FFP and unit price
items.

               (1) Firm-fixed-price contracts

     In practice, the responsibility  for  initially approving interim pay estimates is normally
delegated by the grantee to the  consulting engineer as an element of services  during  the
construction phase.  However, it is the grantee's responsibility to determine that the consulting
engineer exercises procedures and controls adequate to ensure that contractors are paid only for
acceptable construction performed through the cutoff date of the pay estimate. Accordingly,
the auditor should determine whether the grantee has performed a review or analysis to make
such a determination.

               (2) Unit price contracts

     Under unit price contracts, the  contractor is normally reimbursed monthly on the basis of
actual quantities furnished under each bid item. The total cost of this type of contract is flexible
to the extent that quantities are estimated and final payment will be based on actual quantities
received. The responsibility for verifying  unit quantities claimed is  normally a part of the
services provided by the consulting engineer.

     The auditor should perform adequate tests to  determine whether the grantee or  the
consulting engineer  (acting  as the grantee's representative)  exercised the necessary controls to
                                         4-23

-------
ensure that payments were made only for quantities received. Claims for quantities which
cannot be supported in the grantee's or consulting engineer's records should be questioned.

          c. Audit guidance for construction pay estimates

               (1) Firm-fixed-price contracts

    Under FFP contracts, the contractor is  normally  reimbursed monthly on the basis of
percentage of completion of work plus project inventories stored. In performing final audits, the
auditor should:

                     (a) Examine vouchers, invoices, and disbursement records to determine
that costs claimed have been paid in accordance with the original contract award and approved
change orders.

                     (b) Determine that the work required under  the contract has been
completed by the contractor and accepted by the grantee based on a final inspection by the
grantee.

    In performing interim audits, the auditor should:

                     (a) Examine vouchers, warrants, and/or cancelled checks to determine
that costs booked have been paid in accordance with approved progress pay estimates.

                     (b) Ensure that costs claimed are based on  the total value of work in
place  (completed work)  reduced  by any amounts withheld by the grantee as a retainage
(usually a percent of costs claimed  that is withheld to  guarantee  satisfactory completion of
work).

                     (c)  Determine whether the grantee or the consulting engineer initially
approved pay estimates.

                     (d)  Review the procedures actually used by the consulting engineer to
determine that the procedures limit interim payments to work completed and  accepted and
inventories stored (40 CFR 35.938-6). This should include appropriate tests of specific items
included in the pay estimate to source documents which indicate the  resident inspector's
acceptance. The source documents will include inspector's diaries, daily inspection reports, and
other correspondence.

               (2) Unit price contracts

                     (a)  Examine  vouchers,  invoices, and  disbursement  records  to
determine that costs claimed have been paid. Costs claimed should be based on the total value of
work in place (completed work) reduced by any amounts withheld  by the grantee as retainage
(usually a percent of costs claimed withheld to guarantee satisfactory completion of work).

                     (b)  Review  the  procedures  used for the  verification  of quantities
claimed under unit price contracts. The pay estimate should be prepared by the contractor and
approved by the  grantee or its representative. In no instance should  the contractor's pay
estimate be prepared by the grantee or its representative (the engineer).

                     (c)  Verify quantities  billed to  the original contract and approved
change orders.
                                         4-24

-------
                     (d)  Describe briefly in the working papers the procedures in effect and
the type of records maintained for recording units of work completed, e.g., pipe placement, piles
driven, concrete placed, rock excavation, sheeting). Are the procedures used and the records
kept in accordance with the firm's written procedures?

                     (e)  On a selective basis, determine that quantities claimed are properly
supported by documentation maintained by the contractor and/or determined by the resident
engineer. The documentation may include:

                          •    Daily inspection reports or inspector's diaries;

                          •    Calculations from excavation notes and shop drawings;

                          •    Receipts for materials delivered to the site;

                          •    Pile driving records; and

                          •    As-built drawings. (The auditor may use these to accept
quantities of pipe and manholes if he determines, by reviewing source documentation such as
field reports, that the as-builts accurately represent in-place construction.)

                     (f)  Determine that all entries  are  dated.  This  applies to summary
records, books of secondary entry, and source documents.

                     (g)  Determine that all records documenting quantities are maintained
on a current basis. Diaries and inspection reports should be maintained daily, summary sheets
weekly or monthly.

                     (h)  Review and determine the mathematical accuracy of calculations
of excavation and backfill, sheeting, concrete, asphalt, rock excavation, and other items for
which quantities are determined through mathematical computations.

                     (i)   Estimates for quantities of rock excavation, excavation below
grade, and backfill are often treated as contingencies because actual soil conditions may vary
significantly from those established in preliminary test borings. Determine that records show
that these items were actually used.

                     (j)   Source documents such as the  inspector's diary and/or daily
inspection  reports sometimes indicate  unacceptable  construction. Determine whether the
inspector has a method for summarizing construction deficiencies that is useful in obtaining
corrections. Determine that all construction recorded as unacceptable has been corrected or is
in the process of being corrected.

          d.    Quality control

    It is the grantee's responsibility to ensure that construction is performed in accordance
with  the design plans  and specifications. This  responsibility is  normally assigned to  an
engineering firm which, under contract with the grantee, provides resident inspection services.
These services generally include furnishing a professional engineer to be in overall charge of the
project construction inspection, a qualified project representative, and a resident inspector. The
inspection  of work and  materials should normally be  continuous whenever work is being
performed on the project and throughout the duration of construction.
                                         4-25

-------
    The grantee or its engineering firm should exercise controls to provide assurance that
construction was performed in accordance with the approved design plans and specifications.
The auditor should review records documenting this system of controls.

    The auditor should exercise  reasonable judgment in pursuing audit deficiencies and
indications of construction deficiencies. This  guide does not require  that  audits include
engineering evaluations of grantee or auditee operations. Should conditions be encountered
which require such evaluations, the auditor should contact the Division Audit Director, who
will review the situation and arrange for appropriate technical assistance.

          e.     Guidance for auditing quality control procedures

    In auditing controls exercised by the grantee over quality of construction, the auditor
should place maximum reliance on inspections performed by state or EPA inspectors. In this
regard, he should review inspection reports showing the results of such inspections. Where such
inspections are documented to show that  each of the areas set forth below was properly
controlled by the grantee and its engineer, further audit work may not be required. If, however,
the grantee did not properly manage the areas below, the auditor should review them. Where
inspection documentation indicates management problems, the auditor should  follow up to
determine that corrective action was taken. The auditor should proceed as follows:

                (1)   Where the grantee has delegated the  responsibility for professional
services during  construction and/or resident  inspection,  determine how  the grantee  stays
apprised  of construction progress  and problems encountered  during the constructicn. The
grantee's procedures should include review and evaluation of daily inspection reports and
engineers' work progress reports,  and observation  of  the  work performed by the resident
engineer and resident inspectors.

                (2)   Determine the grantee's or consulting engineer's minimum qualification
requirements for resident inspectors.

                (3)   Review personnel records and determine the resident inspector's actual
qualifications. Do these qualifications meet the minimum requirements (step 2 above)?

                (4)   Determine whether  the  grantee  or  consulting engineering firm has
written procedures, in the form of a "construction manual" or otherwise, which prescribe the
duties and responsibilities of the resident inspectors in performing day-to-day activities.  Were
these procedures followed?

                (5)   Determine whether there are written procedures requiring that certain
types of daily records be kept by the inspector (e.g., diaries, daily inspection reports). Were daily
inspection  reports maintained? Do such records appear to be complete in accordance with
procedures?

                (6)   Review work progress reports and other correspondence maintained by
the grantee and note any major  construction  problems identified. Determine that noted
construction deficiencies were corrected. The auditor should also determine that a punch list of
minor construction deficiencies was maintained so that corrective actions may be taken during
project cleanup.

                (7)   Review  the contract specifications  and determine  what tests  (e.g.,
concrete density tests, soil compaction, line and grade tests)  are required, who should perform
the tests, and what limits or tolerances have been established.
                                         4-26

-------
               (8)   Determine, on a selective basis from the engineer's records,  whether
tests were performed as required and whether test results were within the specified limits or
tolerances.

               (9)   Should the audit disclose construction deficiencies of a serious nature
which have not been corrected, attempt to identify the cost associated with that portion of
construction. These costs will not be considered acceptable for EPA participation until the
construction deficiencies are corrected.

     4.3.4 Other Costs

     In reviewing other costs, the auditor should determine whether the costs are allowable and
applicable to the EPA grant. Guidance concerning the allowability of specific cost items can be
found in PMC 74-4,40 CFR 35.940, FPR 1-15.2, FPR 1-15.4, and Appendix D to this guide.
The auditor should determine that:

          a.  The types of expenditures involved were contemplated in  the original budget
and the expenditures were adequately documented;

          b.  In instances where the contractor has established separate pools for such costs as
computer services,  reproduction, and communications, the  methods used to calculate and
distribute such costs are equitable;

          c.  Amounts claimed are properly supported as other direct costs, and similar costs
are not recovered through indirect costing methods;

          d.  The contractor credits to the government the applicable portion of any income,
rebate, allowance, or other credits relating to any allowable costs received by or accruing to the
contractor;

          e.  When applicable, necessary approvals have been obtained from the EPA project
officer; and

          f.  Such costs are allowable under applicable cost principles.

     The auditor should be alert for additional engineering costs or any other added costs due to
contract default. These costs are not eligible, as the grantee is compensated for these costs by the
contractor's bonding company.

     4.3.5 Other Audit Matters

          a.    Flood insurance

     Effective July 1, 1975 (or one year after a community's notification of identification as a
flood-prone community,  whichever is later), for activities  where the  total cost is $10,000 or
more per structure, EPA is  prohibited by law from making any grant for acquisition or
construction purposes  in a flood  hazard area unless the community in which the project is
located is  participating in the flood insurance program and flood insurance is purchased by the
grantee. If the audit planning package furnished by the Division Audit Director identified
construction in a flood hazard area, the auditor should determine that the grantee has  flood
insurance.
                                         4-27

-------
          b.    Property control

               (1)   Real property

    Real property should be reviewed to determine that it is (a)  for the purpose of the grant
and (b) controlled in accordance with 40 CFR 30.810-5.

               (2)   Personal property

    The auditor should review the grantee's property management system using the criteria set
forth in 40 CFR 30.810. In evaluating this system, the auditor should:

                     (a)   Determine whether the grantee  maintains property  records to
account for equipment purchased for use in the EPA grant program.

                     (b)   Review the property records  maintained and consider whether
they contain necessary information, such as:

                          •     The manufacturer's serial number or other identification
number; the acquisition date; the cost; the source of acquisition; the percentage of EPA equity;
the ultimate disposition data (including  sales price and the method used to determine fair
market value); and the location, use, and condition of the property.

                          •     A description of the property.

                     (c)   Ascertain whether the grantee takes a physical inventory of grant
equipment and  reconciles the results  with property records at least once every two years to
verify the existence, current utilization, and continued need for the property.

                     (d)   Determine whether:

                          •     Differences  between  the  property  record  balances  and
physical balances are investigated and fully documented.

                          •     Property records are adjusted as a result of the inventory.

                          •     The grantee takes action to dispose of an item of equipment
if it is no longer needed.

                          •     Periodic  inspections   and   routine  maintenance   are
performed on equipment.

                     (e)   Select from the property records a sample of equipment items
purchased for the EPA grant and physically inventory the equipment to see whether the system
is adequate in terms of (c) above.

          c.    National Pollutant Discharge Elimination System

    The auditor should review the NPDES permit (furnished by the grantee or in the audit
planning package) to determine effluent limitations and other requirements as established in the
permit.  He should determine from  grantee  records and discussions whether the permit
requirements are being met.
                                         4-28

-------
               (1)   Does the grantee have procedures for performance reporting under the
NPDES  permit requirements  and/or  state and local  requirements?  Have  they  been
implemented?

               (2)   Are required sampling, analytical, and reporting systems in operation?

               (3)   Do reports indicate that standards are complied with? Note exceptions.

          d.    User charge system (UCS)

    The auditor should determine (for grants awarded after March 1, 1973)  whether:

               (1)   The grantee has developed a UCS. If a UCS has not been developed, its
status should be documented.

               (2)   The Regional Administrator has paid more than  50 percent of the
Federal share of the Step 2 grant. If so, has the grantee submitted adequate evidence of timely
development of a UCS (40 CFR 35. 935-13(a))?

               (3)   The Regional Administrator has paid more than  80 percent of the
Federal share. If so, has the system been approved by the Regional Administrator?

          e.    Industrial cost recovery (ICR)

    The auditor should determine (for grants awarded after March 1, 1973)  whether:

               (1)   The grantee has indicated  to the Regional Administrator that it has
industrial users. If it advised the Regional Administrator that it does not have industrial users,
the auditor should be alert for information to the contrary during the audit.

               (2)   The grantee has obtained  letters from "significant"  industrial  users
agreeing to pay under the ICR system.

               (3)   Grantees requesting payment of more than 50 percent of the Step 3 grant
have made timely progress in developing an approved ICR system in accordance with the ICR
guidelines dated February 1976.

               (4)   Grantees requesting payment of more than 80 percent of the Step 3 grant
meet the criteria described in the guidelines.

               (5)   For final audits  of construction grants which have ICR systems, the
system proposed by the grantee has been approved by the Regional Administrator. The auditor
should qualify his report to the extent that he has not audited the ICR system but will at a later
date.

          f.     Operation and maintenance (O&M) manual

    No more than 50 percent of the Federal share may be paid until the grantee submits a draft
operation and maintenance manual, and no more than 90 percent may be paid until the manual
is approved by the Regional Administrator (40 CFR 35.935-12).
                                        4-29

-------
          g.    Sewer use ordinance

     No  more  than 80  percent  of the  Federal share may be  paid until  the  sewer use
ordinance(s)  has been submitted by the grantee and approved by the Regional Administrator
(40 CFR 35.935-16).

          h.    Operation of facility

     An important step of the field work will be a tour of the waste-water treatment plant. The
objective of this portion of the audit is to discuss operation  of the plant with  operating
personnel.  The auditor will be  alert for indications  that the  facility is not managed and
maintained in accordance with grant objectives.

     During this phase of the audit, the auditor should:

               (1)   Determine whether the grantee has established a permanent record file
which includes:

                     (a)   The operation and maintenance manual;

                     (b)   A complete set of as-built drawings;

                     (c)   Plans, specifications, drawings, and  manufacturers' specifications
for operation  and maintenance of each unit.

               (2)   Determine whether the grantee has employed the number of qualified
treatment plant operators indicated in its operation and maintenance manual.

                     (a)   Has  the grantee  established institutional  arrangements for
personnel training and development leading to certification?

                     (b)   Do  key  supervisory   personnel  meet  the state's  minimum
certification requirements?

                     (c)   Obtain  and review  copies of Federal,  state, and/or local agency
inspection  reports. Identify any  major deficiencies reported and determine the status  of
corrective action being taken.

                     (d)   Review the engineer's  daily inspection reports, punch lists, and
deficiency lists to  ascertain construction deficiencies which required correction.  Determine
whether the deficiencies were corrected. Request technical assistance as required.

               (3)   Determine that the plant  has a laboratory capability and that it is being
utilized.  Review effluent testing procedures for consistency with  requirements  in the O&M
manual.

               (4)   Discuss the overall operation of the plant with several levels of operating
personnel, including the plant superintendent:

                     (a)   Are there problems which impair the plant's ability to properly
                          treat sewage? If so, review the plant's:

                          •     Equipment;
                                         4-30

-------
                          •    Process design; and

                          •    Facility design.

Obtain operating peronnel's suggestions for remedial measures.

                     (b)   Do any overflows occur, or is it necessary to bypass any units?
Frequency and cause?

                     (c)   What' are the frequency and nature of contacts by regulatory
agency personnel (local, state, or Federal)?

                     (d)   Has an adequately funded preventive maintenance system been
established?

                     (e)   Is the  plant successful in meeting effluent limitations  under its
discharge permits?

                     (f)   Are any items of equipment or sections of the plant not in use?
Why? Costs of unnecessary or inoperable equipment should be questioned or suspended.

          i.    Value engineering

    VE is required for all Step 2 grants on or after October 26, 1976, having a projected Step 3
grant-eligible construction cost of $ 10 million (see page 2-1).

               (1)   As a minimum, the VE proposal should include, as per 40 CFR 35.936
and Program Requirements Memorandum (PRM) No. 75-36, a description of the:

                     (a)   Scope of VE analysis;

                     (b)   VE team and qualifications;

                     (c)   Level of VE effort;

                     (d)   VE cost estimate; and

                     (e)   VE schedule in relation to project schedule.

               (2)   VE Summary Reports-Upon completion  of  the VE  analysis,  a
preliminary report summarizing the VE findings and  a final report describing implementation
of VE recommendations must be submitted to the project officer on a time schedule  approved
by him.

               (3)   Grant Eligibility-The grant eligibility  of the VE fee is limited to the
actual  VE  analysis of the project.  The applicant may incorporate training as  part  of the
proposed VE workshop. However, the intention must  be so stated in the proposal, and all costs
associated with such training  must be computed separately. For example, the cost  for a VE
instructor, additional time and room space, etc., must be itemized and separately identified for
training.  These  additional costs for training are not grant eligible (PRM 75-36, Section VII,
Paragraph 2).
                                        4-31

-------
               (4)   The audit approach should include:

                    (a)   Discussion with the project officer on the adequacy of the VE
proposal regarding the requirements listed above.

                    (b)   Review of the  Step 2 grant application to determine that the
application includes the minimum required information set forth above.

               (5)   Audit steps should include, but are not limited to:

                    (a)   Verification that the required VE  team qualifications have been
met.

                    (b)   Determination  that a firm independent of the design firm  is
conducting the VE review. If not, determine that the VE team members had not been involved
in any part of the proposed project design  except for VE analysis. The audit report should
comment that the VE analysis was performed in-house.

                    (c)   Review of the preliminary and final VE reports.

                    (d)   Determination that the VE recommendations were implemented
to the maximum extent feasible.

               (6)   For further information and guidance, see:

                    (a)   "Federal Register," Vol. 41, No. 186 (September 23, 1976), pages
41690-41691.

                    (b)   "Value Engineering Workbook for  Construction Grant Projects,"
US Government Printing Office, MDC-29, and US Environmental Protection Agency, EPA-
430/9-76-008 (July 1976).

                    (c)   "Value Engineering in the  EPA Construction Grants Program,"
PRM No. 75-36 (January 20, 1976).
                                        4-32

-------
                     CHAPTER  5:   EXIT  CONFERENCES
    Throughout the course of the audit, the auditor is expected to discuss deficiencies disclosed
during audit, their effect, and possible corrective actions,  with responsible officials of the
audited party. The primary purpose of these disussions is to ensure that audited parties have an
opportunity to  provide additional data with respect to the problem  areas identified during
audit.

5.1 AUDITS WITH NO FINDINGS

    For audits with no findings or audits without significant findings, the auditor should notify
the Division Audit Director and then hold a preliminary exit conference with the audited party
at the site. When the audited party is a subcontractor, a separate or joint exit conference may be
held with the grantee and the subcontractor. If the audited parties desire to provide written
comments with respect to matters raised in the audit, they should be furnished a copy of the
draft report and afforded the opportunity to provide written comments. It is not necessary to
return to the job site for a formal exit conference.

5.2 AUDITS WITH SIGNIFICANT FINDINGS

    For audits with significant findings, the auditor should initially discuss the findings with
the Division Audit Director by telephone. The auditor should then hold a preliminary exit
conference with the audited party to discuss the factual information disclosed during the audit.
He should emphasize that the audit results and findings are tentative at that point, and that they
will be included in a draft report forwarded to the audited party for written comment.

    The auditor  should  prepare his  draft audit report, highlighting the costs  considered
unallowable and other deficiencies disclosed during the audit. The Division Audit Director
should be promptly furnished a preliminary copy of the draft report. If, after reviewing the draft
report, the Division Audit Director agrees that the deficiencies are significant, he will meet with
the responsible EPA program officials to brief them on the situation. In addition, he shall
require  that the  grantee  and  other  audited  parties (such  as those  performing under
subagreements) be furnished a copy of the draft audit findings and conclusions to enable review
and written comment prior to the  formal exit conference.

    After he receives written comments from the audited parties, the auditor will conduct an
exit conference with each of the responsible parties involved (i.e., the grantee and other parties
having subagreements whose operations and/or costs were audited).

5.3 DOCUMENTATION

    The auditor's workpapers shall contain the name of the auditor who conducted  the exit
conference, the names and positions of those in attendance, details of the matters discussed, and
a summary of the reactions of the audited parties.

    A synopsis of the audited parties' comments will be included in the section of the audit
report entitled  "Comments  on  Compliance, Performance, and  Internal Controls." When
written comments are of reasonable length, they will be included as an attachment to the report.
The auditor may also include any  rebuttal considered appropriate in light of the audited parties'
comments.
                                         5-1

-------

-------
                     CHAPTER  6:   THE AUDIT REPORT
6.1 INTRODUCTION

    Audits  of EPA  construction grants may result  in  findings and recommendations
concerning costs questioned or deficiencies in the administration of the grant. For effective
administration of the  construction grant program, audit reports must contain all findings,
observations, conclusions, and recommendations resulting from the audit.

6.2  CONTENT AND FORMAT OF AUDIT REPORT

    The audit report will be prepared in accordance with the following instructions and in the
formats shown in the Example Audit Reports (with  exhibits and schedules) on pages 6-3
through 6-24.

    6.2.1 Scope Paragraph

          a.    The scope paragraph will identify the grant audited and the period audited.
For final audits, the period audited will normally be from the date of grant offer to date of final
inspection or the designated cutoff date. For interim audits, the period audited will normally be
from the date of grant offer to the date audited costs were incurred or claimed.

          b.    The scope paragraph will also include a statement that the examination was
made in accordance with the EPA "Audit Guide for Construction Grant Program" and the
GAO  "Standards for Audit of  Governmental Organizations,  Programs, Activities, and
Functions." If conditions were encountered which preclude the inclusion of such a statement,
an appropriate statement will be prepared explaining the nature of conditions which required
the deviation.

    6.2.2 Opinion

    The report will contain an opinion as to the costs incurred/claimed and costs eligible under
the EPA grant. Based on the review of the reasonableness, allowability, and allocability of costs
claimed in conjunction with grant terms and conditions and applicable Federal regulations, the
auditor will classify costs as "accepted," "questioned," or "suspended"  in a separate schedule
referenced in the report.

    6.2.3 Comments on Compliance, Performance, and Internal Controls

    The report will include a separate section relating to the compliance, performance, and
internal control reviews made during the examination. The report should include a discussion
of any deficiencies identified during the course of the audit. In addition, the interim report must
contain comments as to the adequacy of the  accounting system and procurement systemTA
final audit report must contain those comments only if the grantee has other active EPA grants.
                                         6-1

-------
6.3 PRESENTING THE FINDINGS

    Audit  findings,  whether  they  relate  to  costs  questioned  or  grant administration
procedures, will be presented in sufficient written detail to ensure that report recipients may
readily:

         a.    Understand the finding;

         b.    Understand the basis for the finding; and

         c.    Grasp the significance of findings not directly related to the costs questioned.

    The discussion of an audit  finding should conclude with management  improvement
recommendations, if applicable.
                                         6-2

-------
6.4 EXAMPLE AUDIT REPORT NO. 1
Division Audit Director
Office of Audit
Environmental Protection Agency
Any City, U.S.A.

    We have  examined the statement of costs incurred/claimed* and EPA-eligible costs
(Exhibit A) for the City of Anywhere, U.S.A., under EPA Grant No. XXXX for the period
(month, day, year) to (month, day, year). Our examination was  made in accordance with
generally accepted  auditing standards and the "Standards  for  Audit  of Governmental
Organizations,  Programs, Activities,  and  Functions."  The  audit included  tests of the
accounting  records  and  other  auditing  procedures  we  considered  necessary  in the
circumstances. The Environmental Protection Agency's "Audit Guide for Construction Grant     g
Program," revised January 1978, was also used as a guide in our examination.

    As part of our examination,  we determined the allowability  of costs incurred/claimed
under  the project in accordance  with the provisions of the grant and applicable  Federal
regulations. Schedule A-l sets forth the costs which we questioned in this regard and includes
an explanation of the reasons such costs were questioned.

    In our opinion, subject to the effects on Exhibit A of EPA's ultimate resolution of the     o
questionable expenditures referred  to in the preceding paragraph, Exhibit A fairly presents the     .§
financial information in accordance with generally accepted accounting principles and financial
provisions of the grant.

    In  addition,  in  connection  with   our  examination  of  the  statement  of  costs     g
incurred/claimed and eligible EPA costs, we have reviewed the grantee's (1) system of internal
control (based on criteria established by EPA and set forth in the aforementioned EPA audit     c
guide) and (2) compliance with provisions of the grant and applicable Federal regulations. Our
report thereon appears as Exhibit B.

    This report is intended for use in connection with the grant to which it refers and should
not be used for any other purpose.
DATE                                 SIGNATURE
     *The audit report will normally address costs claimed. However, on interim audits there
may be instances where the grantee's claim is not current. In these instances, the audit report
will address cost incurred.
                                         6-3

-------
EXAMPLE AUDIT                                                  EXHIBIT A
REPORT NO.  1
                             City of Anywhere, U.S.A.
                         Secondary  Sewage Treatment  Plant
        Statement of Grantee's Costs Incurred/Claimed  and EPA-Eligible Costs
              for  the Period (Month, Day, Year) to (Month, Day, Year)

    Description*            Total Costs        Costs Claimed
                         Incurred        as EPA-Eligible

Construction Costs           $2,780,000         $731,715

Project Inspection
  Fees                       133,537          26,707
Total Costs                 $2,913,537         $758,422
Grant No. XXXX was awarded to the City of Anywhere, U.S.A., under Public Law 84-660.
The grant was awarded on (month, day, year) and provides for 55-percent Federal participation
in the construction  of a secondary sewage treatment plant and  interceptor sewers, with a
maximum Federal share of $1,100,000. At the time of completion of the audit field work
(month, year), construction was approximately 40-percent complete on two contracts. The
third construction contract under the grant had been recently awarded, but construction had
not started at (month, year).

See Schedule A-l for a statement of costs accepted and questioned during the audit.
    The cost categories listed on the Outlay Report and  Request for Reimbursement for
Construction Programs (SF 271) should conform to the Description column.
                                         6-4

-------
EXAMPLE  AUDIT
REPORT  NO. 1
                                        SCHEDULE A-l
                               City of Anywhere,  U.S.A
                          Secondary Sewage Treatment Plant
                 Statement of Cost  Incurred, Accepted, and Questioned
              for the Period (Month, Day, Year)  to (Month, Day, Year)
   Description
Construction Cost

Project Inspecton Fees

Total Costs

Determination of amount
due grantee or EPA
based on audit

  Federal share (55%) of
  accepted eligible  cost
        EPA-Eligible Costs
Incurred

$731,715

  26,707

$758,422
Accepted

$551,348

   9,787

$561,135
Questioned

  $180,367

    16,920

  $197,287
Notes

  1

  2
$417,132
$308,624*
  $108,508
  Less EPA payments made
  through (month, day, year)

Balance due Grantee
     This amount should not be construed as being the final determination of the Federal share
of accepted eligible costs. The amount may vary depending upon the resolution by EPA of
questioned costs totaling $197,287.
                                          6-5

-------
                               Notes  to Schedule A-l

Note 1  Construction Contracts
    a.  The grantee contracted for the erection of 198,422 feet of wooden fence around the
construction site of the treatment plant at a cost of $1.50 a linear foot, for a total price of
$297,633. The contractor submitted invoices totaling $325,000 for the 198,422 feet of fence
installed.  The  consulting  engineer  approved  and  the  grantee  paid  the overpayment
requested.   The overpayment was $27,367.                                                 $27,367


    b.  The grantee awarded a $550,000 construction contract for repair, maintenance, and
construction of the collection system. Upon reviewing the scope of the contract, the EPA
project engineer stated that it should not have been deemed eligible for Federal participation
because it relates to the collection system, not to necessary interceptors. Therefore, we question
the entire  contract  because  P.L.   84-660   excludes  collection  systems from Federal
participation.  The total cost incurred to date is $ 150,000                                    150,000

    c.  The grantee contracted for a protective wooden fence to be completed by September
15, 1974. The fence was not completed until September 18, 1974. This delay required another
contractor under the grant to  defer  the start of excavation  to  September 20, 1974. The
contractor incurred $3,000 in equipment rental costs during the three-day delay. Chapter VII of
the Handbook of Procedures states that increased costs resulting from lack of performance by
the construction contractor are  unallowable for participation, even if the grantee  elects not to
exercise its right to recover liquidated damages. The cost incurred during the three-day overrun
is $3,000.                                                                                  3,000
                                                       Total Costs Questioned          $180,367
Grantee's Comments

     The grantee agrees with the above questioned costs.
                                          6-6

-------
Note 2  Project Inspection Fees

     A  summary of audit recommendations follows:
    Description
Subagreement Costs*
   Personnel
   Fringe Benefits
   Overhead
   Travel
   Subcontracts

   Total Costs
   Fee

Total Subagreement Costs
   plus Fixed Fee

Force Account Costs

Total Project Inspection
   Fees
Eligible Costs
                             Incurred
$32,000
  6,000
 32,000
  2,537
 23,000

$95,537
  8,000
             Costs
$10,000
  1,886
 10,000
  2,537
 - 0 -

$24,423
  8,000
                       Questioned    Reference
$22,000
  4,114
 22,000
 - 0 -
 23,000
     *In this example audit report, engineering fees were considered to be compensated under a cost-plus-fixed-fee
contract; thus, an audit of actual cost was performed. In cases where engineering services are compensated under a
multiplier, fee curve, or FFP contract awarded prior to July 1,1975, the procedures outlined in section 4.3.2.b of this
guide should be included in this schedule and referenced to technical service costs incurred/claimed, accepted, and
questioned.

           a.    Engineering firm's records do not accurately record project cost--$22,000: The
consulting engineer was unable to support charges totaling $22,000 for project supervision and
inspection. The project was charged for the full time of the project engineer and one-half time
for another engineer whose identity we could not determine. The engineering firm's payroll
records did not identify the projects to which the inspectors were assigned, and the firm was
unable to provide the weekly time sheets which,  a  representative of the firm stated, contain
project identification. We are questioning all charges except the salary of the project engineer.

           b.    The amount questioned represents the application of the firm's fringe benefit
rate of 18.7 percent to personnel costs questioned in Note 2a above (18.7 percent x $22,000 =
$4,114).

           c.    The amount questioned represents the application of the firm's overhead rate
of 100 percent to personnel costs questioned in Note 2a above (100% x $22,000 = $22,000).

           d.    Approval of engineer subcontracts~$23,000: The consulting engineer, without
the Icnowledge or approval of the  grantee or EPA, awarded a fixed-price subcontract for the
design of the settlement basins. EPA regulations require prior approval of subcontracts and  a
determination  that  such  subcontracts  are   reasonably priced.  Further,  the  consulting
engineering firm could not demonstrate that the subcontract was awarded at a reasonable price.
Consequently, we have questioned this subcontract of $20,000 plus a 15-percent management
fee of $3,000, or $23,000.
                                            6-7

-------
          e.     The grantee incurred personnel costs of $30,000 for force account work, of
which $6,000 was claimed as EPA-eligible costs. Since the grantee's records did not identify
eligible costs, the grantee used the percentage of eligibility identified in the grant application
(20% of $30,000  — $6,000). An in-depth analysis of the force account costs revealed that
$ 13,490 was related to another project. The remaining $ 16,510 is accepted as eligible costs.

          f.     The approved grant application estimates eligible construction costs which,
when taken over total construction costs, result in an eligibility factor of 20 percent. To arrive at
the total eligible project cost, a ratio based on actual costs  will be applied to all other acceptable
costs at the time of the final audit.*

Engineering Firm's Comments

(a thru c)        The engineering firm's representative agreed that records were not available to
support all salary charges, but contended that the staff had performed sufficient work to earn
the cost claimed.

          d.     The engineering firm's representative stated that they were not aware of these
requirements. Based upon the performance of the subcontractor, they considered this to be a
reasonable price.

Grantee's Comments

     The grantee concurred with the facts in Note e.
     *See page 4—5 of this guide.
                                           6-8

-------
EXAMPLE AUDIT REPORT NO.l                                 EXHIBIT B

                           CITY OF ANYWHERE, U.S.A
                  SECONDARY SEWAGE TREATMENT PLANT
                         CONSTRUCTION GRANT XXXX

COMMENTS ON COMPLIANCE, PERFORMANCE, AND INTERNAL CONTROLS

    As a part of our examination, we reviewed and tested the grantee's system of internal
accounting controls to the extent we considered necessary to evaluate the system as required by
generally accepted auditing standards. This evaluation established a basis for reliance on the
grantee's accounting control system in determining the nature, timing, and extent of other
auditing procedures necessary for expressing an opinion on the financial reports.

    The objective of internal accounting control is to provide reasonable, but not absolute,
assurance that the (1) assets are safeguarded against loss from unauthorized use or disposition
and (2) financial records are reliable for  preparing financial statements  and maintaining
accountability for assets.  The concept of reasonable assurance recognizes that the cost of a
system  of internal  accounting  controls  should not exceed the benefits derived and also
recognizes that the evaluation of these factors necessarily requires estimates and judgments by
management.

    There are inherent limitations that  should be recognized in considering the potential
effectiveness of any system of internal accounting controls. In the performance of most control
procedures, errors can result from misunderstanding of instructions, mistakes of judgment,
carelessness, or other personal factors. Control procedures whose effectiveness depends upon
segregation of duties can  be circumvented by collusion. Similarly, control procedures can be
circumvented intentionally by management, either with respect to the execution and recording
of transactions or with respect to the  estimates and judgments required in the preparation of
financial statements. Further, projection of any evaluation of internal accounting control to
future periods is subject to the risks that the procedures may become inadequate because of
changes in conditions and that the degree of compliance with the procedures may deteriorate.

    The EPA "Audit Guide for  Construction Grant Program," revised January 1978, requires
a review and evaluation of the adequacy of the accounting system and internal controls of the
grantee to (1) safeguard its assets; (2) check the accuracy and reliability of the accounting data;
(3) promote operating efficiency; and  (4) encourage compliance with prescribed  management
policies and such additional fiscal, accounting, and administrative requirements  as EPA may
establish. We understand that EPA considers procedures conforming to the criteria in its audit
guide to be adequate for EPA purposes. Procedures that are not in conformity with the audit
guide indicate some inadequacy for EPA purposes. Based on this understanding and on our
study, we believe that the City's procedures were adequate (inadequate) for EPA purposes
except for (because of)  the conditions  described  below,  which we believe  are material
weaknesses in relation to the grant to which this report refers. In addition to such weaknesses,
other conditions  which we believe are  not in conformity  with the criteria referred to above are
described on the following pages.
                                         6-9

-------
GRANTEE'S ACCOUNTING SYSTEM (Interim Report)*

    The grantee's general accounting system is considered adequate to record and accumulate
financial information.  However, the grantee's  cost  accounting  system  is not  considered
adequate to identify and accumulate costs under the subject grant. The grantee maintains a
general accounting system controlled by a general ledger and supported by various accounting
journals. However, the grantee does not maintain cost or project accounting records to identify
EPA-eligible project costs.  The general ledger consists of one construction account which
includes the costs of all construction projects undertaken by the City. As a result, we could not
determine the amount of EPA-eligible expenditures incurred.

    EPA general  grant  conditions provide "the  grantee shall  maintain books, records,
documents, and other evidence and accounting procedures and practices sufficient to reflect (1)
the amount, receipt,  and disposition by the grantee of all assistance received for the project,
including both Federal assistance and any matching share or cost sharing, and (2) the total cost
of the project, including  all direct and indirect costs of whatever nature incurred for the
performance of the project for which the EPA grant has been awarded...."

    During the course of our audit, the accounting system deficiency was discussed with the
City Controller, who  made arrangements  for  a  public  accounting firm to  identify and
accumulate, from the City's records, costs incurred under the grant project. At the completion
of our audit, project costs incurred by the City from inception of the grant through June 30,
1975, had been identified and summarized. However, costs incurred since July 1, 1975, have not
been analyzed, and a system to provide the identification and accumulation of future grant
expenditures has not been implemented.

Recommendation

    We  recommend that EPA  require the  City  to  take immediate action to implement
accounting procedures adequate to reflect EPA-eligible  and allowable project costs.

Grantee's Comments

    The grantee concurred and indicated that necessary corrective action would be taken.

GRANTEE'S PROCUREMENT SYSTEM

    The grantee's procurement system for construction and engineering services was generally
adequate except for procedures relating to pricing change orders.

    The grantee has not established effective procedures for controlling the change orders to
assure that: (1) a review of the reasonableness of change order costs is made, (2) responsibility is
assigned  for final acceptance of the change order  work prior to approving payment  on the
change orders, and (3) responsibilities  of City  officials authorized to sign and approve the
change orders are defined. The grantee, on the recommendation of the consulting engineer,
approved three contract change orders, valued at $100,000, under contract number XXXX.
The change orders extended the construction period for nine months and provided for extensive
substitution of equipment.
     *For final audits, statements regarding the accounting systems are necessary only if the
grantee has other active EPA grants.
                                        6-10

-------
    Our review of the  consulting engineer's records  disclosed that the engineer had not
performed a cost analysis or taken other measures to assure the reasonableness of the change
order price. In addition, neither the grantee nor the consulting engineer had approved the
change order work prior  to payment for the change order. We also noted that the changes have
not been submitted to EPA for approval. We do not take a position concerning the merits of the
changes, but we believe  that  changes altering the scope of the project are subject to prior
approval before they are binding on EPA.

Recommendation

    We recommend  that  the  grantee be  required to  establish  effective procedures for
controlling change orders which will, as a minimum, provide for reasonable costs, acceptable
work, and properly defined responsibilities for City officials approving the change orders. In
addition, prior EPA approval should be obtained whenever the change orders alter the scope of
the project and/or when cost changes exceed $100,000.

Grantee's Comments

    The grantee and the engineering  firm concurred with the auditor's findings and
recommendations.

CORRECTION OF CONSTRUCTION PROBLEMS

    Our review disclosed that construction  deficiencies noted in the inspection reports were
not adequately controlled to assure correction. The current inspection system does not provide
a mechanism for assuring that deficiencies identified in the inspection process are corrected.
For example, we identified 25 construction deficiencies  (from inspectors'  diaries and daily
inspection reports) which had not been corrected at the time of completion of the audit field
work. These deficiencies were recorded over a six-month  period ending in June 1974. As of June
1975, when we discussed these deficiencies with the resident inspector and project engineer, no
action had been taken to correct the deficiencies. The project engineer indicated that some of
the deficiencies represented major structural defects.

Recommendation

    We recommend that EPA take appropriate action  to ensure that the grantee requires its
consulting  engineering firm to adequately  control  and document followup action  on all
construction problems included in the inspection reports or other records. The grantee should
ensure it is fully informed of the status of construction and operational problems identified by
the consulting  engineering  firm. We also recommend that EPA perform an inspection to
determine the seriousness of the construction deficiencies and the appropriateness of proposed
corrective action.

Engineering Firm's Comments

    Representatives of the engineering firm  indicated that they would take prompt action to
follow up on deficiencies and get the contractors to take necessary corrective action.

Grantee's Comments

    The grantee stated that it would take the necessary action to get deficiencies corrected.
                                        6-11

-------
CONFLICTING CONTRACT TERMS

    The grantee has relied on the consulting engineer to determine whether the contractors
have performed the work in accordance with the plans and specifications approved by EPA.
The contract between the grantee and consulting engineering firm is not clearly defined as to the
firm's responsibility  for inspecting the work of construction contractors and its authority to
interpret the plans and specifications. However, the contracts between the grantee and three of
its contractors contain specific language that states the consulting engineer is the grantee's
representative on all matters concerning interpretation of plans and specifications, inspections,
and obtaining rework of work not meeting those plans and specifications. Thus, the grantee
appears to rely on the consulting engineer to obtain satisfactory completion of the project when
in fact the contract does not provide that assurance.

Recommendation

    We recommend that the grantee be required to amend its consulting engineering contract
to specifically state the engineer's authority and responsibility.

Engineering Firm's Comments

    Representatives of the engineering firm stated that they see no problem with the present
wording of the contracts.

Grantee's Comments

    The grantee concurred with the audit finding and stated that the consulting engineering
contract would be appropriately amended.

ENGINEERING FIRM'S ACCOUNTING SYSTEM

    The engineering firm's accounting system is not considered adequate to identify and
accumulate costs under the subject contract. Adequate documentation is not maintained to
support all costs charged to the project. Payroll records did not identify the projects to which
inspectors were assigned. As a result, we questioned $22,000 of personnel costs charged to the
project. (See Schedule A-l, Note 2 (a).)

Recommendation

    We recommend that the engineering firm be required to maintain records which properly
document salary charged. This should include, as a minimum, weekly time sheets which are
signed  by the  employee and his supervisor  and which  identify all projects on  which the
employee is working. In addition, appropriate reconciliations should be made between labor
distribution and payroll records.

Engineering Firm's Comments

    The engineering firm stated that immediate action was being taken to correct deficiencies
in its accounting system.

Grantee's Comments

    The grantee concurred with the audit finding and recommendation.
                                        6-12

-------
ENGINEERING FIRM'S PROCUREMENT SYSTEM

    The engineering firm's procurement system is considered generally adequate to protect the
interests of the grantee and EPA with the following exception: the engineering firm awarded a
subcontract for a portion of the work under its contract with the grantee. However, in awarding
such a contract, the engineer did not perform an adequate cost or price analysis to ensure a
reasonable price for the subcontracted work.

Recommendation

    We recommend that future subcontract procurements by the engineering firm under cost-
plus-fixed-fee contracts be subjected to a cost or price analysis to assure reasonable prices.

Engineering Firm's Comments

    The engineering firm's representatives were not aware  of this requirement, but will
consider it in subcontracting for future work.

Grantee's Comments

    The grantee concurred with the audit finding and recommendation.
                                       6-13

-------
6.5  EXAMPLE AUDIT REPORT NO.2
Division Audit Director
Office of Audit
Environmental Protection Agency
Any City, U.S.A.
    We have examined the statement of costs incurred/claimed* and EPA-eligible costs
(Exhibit A) for the City of Anywhere, U.S.A., under EPA Grant No. XXXX for the period
(month, day, year) to (month, day, year). Our examination was  made in accordance with
generally  accepted  auditing standards and the "Standards  for  Audit  of Governmental
Organizations,  Programs, Activities,  and  Functions."  The  audit included  tests of the
accounting  records  and  other auditing  procedures  we considered  necessary  in the
circumstances. The Environmental Protection Agency's "Audit Guide for Construction Grant
Program," revised January 1978, was also used as a guide for our examination.

    As part  of our examination, we  determined the allowability  of costs  incurred/claimed
under  the project in accordance with the provisions of the grant and applicable Federal
regulations. Schedule A-l sets forth the costs which we questioned in this regard and includes
an explanation of the reason such costs were questioned.

    In our opinion, subject to  the effects on Exhibit A of EPA's  ultimate resolution of the
questionable expenditures referred to in the preceding paragraph, Exhibit A fairly presents the
financial information in accordance with generally accepted accounting principles and financial
provisions of the grant.

    In addition, in connection with our examination of the  statement of costs  incurred/
claimed and eligible EPA costs, we have reviewed the grantee's (1) system of internal control
(based on criteria established by EPA and set forth in the aforementioned EPA audit guide) and
(2) compliance with provisions of the grant and applicable Federal regulations. Our report
thereon appears as Exhibit B.

    This report is intended for use in connection with the grant to which it refers and should
not be used for any other purpose.
DATE                                 SIGNATURE
     *The audit report will normally address costs claimed. However, on interim audits there
may be instances where the grantee's claim is not current. In these instances, the audit report
will address costs incurred.
                                        6-14

-------
EXAMPLE  AUDIT
REPORT NO. 2
EXHIBIT A
                               City of Anywhere, U.S.A.
             Statement  of Costs Incurred/Claimed and EPA-Eligible Costs
              for the Period  (Month, Day, Year) to (Month, Day,  Year)

     Description*                       Total Costs      Costs Claimed
                                       Incurred     as EPA-Eligible

Administration                            $87,000       $ 65,000
Preliminary Expense                        200,000         70,000
Land, Structures, Rights-of-Way              127,530
Architectural Engineering Basic Fees          700,000        600,000
Other Architectural Engineering Fees          95,000         87,000
Project Inspection  Fees                     115,000        103,000
Construction and Project
  Improvement Cost                     4,150,000       3,760,000

Total Claimed                          $5,474,530      $4,685,000
Grant No. XXXX was awarded to the City of Anywhere, U.S.A., under Public Law 92-500.
The grant was awarded on (month, day, year) and provides for 75-percent Federal participation
in the construction of a secondary sewage treatment plant and interceptor sewers, with a
maximum Federal share of $13.5 million. At the time of completion of the audit field work
(month, year), construction was approximately 30-percent complete on ten contracts.

See Schedule A-l for a statement of costs accepted and questioned during the audit.
     The cost categories listed on the Outlay Report and  Request for Reimbursement for
Construction Programs (SF 271) should conform to the Description column.
                                         6-15

-------
EXAMPLE AUDIT
REPORT  NO.  2
                                           SCHEDULE  A-l
                            City  of Anywhere, U.S.A.
        Statement  of  Costs Claimed, Accepted, Suspended,  and Questioned
            for  the Period (Month, Day,  Year) to (Month, Day,  Year)
    Description
Administration
Preliminary Expense
Architectural  Engineering
      Basic  Fees
      Other
Project Inspection  Fees
Construction

Total Costs

Determination of amount
due grantee or EPA
based on audit

  Federal Share (75% of
  accepted eligible costs)
               EPA-Eligible Costs
Claimed
$65,000
70,000
600,000
87,000
103,000
3,760,000
Accepted
$47,258
70,000
570,400
76,492
31,743
3,711,700
Suspended
$63,363
40,067
Questioned
$17,742
29,600
10,508
7,894
8,233
 $4,685,000
$4,507,593
$103,430
$73.977
                                                                               Notes
$3,513,750    $3,380,695*
               $77.572
            $55.483
  Less EPA payments
  made through
   (month, day, year)

Balance due EPA
              3,750,000

              $369.305
     "This amount should not be construed as being the final determination of the Federal share
of accepted eligible costs.  The amount may vary depending upon the resolution by EPA of
questioned and suspended costs of $177,407.
                                           6-16

-------
                                Notes to Schedule A-l
Notel

    Of the total costs claimed by the grantee under the Administration cost category, we have
questioned $17,742 for the following reasons:

    (a) The  grantee claimed costs  incurred  by a city employee whose salary was totally
reimbursed with Federal funds under the Public Service Program.                              $ 1,242


    (b) The sale of plans and specifications to prospective bidders cost $100 per copy. Each
bidder then received a refund of 100 percent of the cost of one copy, but additional copies taken
by the same bidder were only refunded at 50 percent of the original cost. The results of our test
performed on one contract indicated  that where  18 bids were received, the grantee's gross
receipts totaled $23,500; $10,050 was returned to bidders, and $13,450 was credited to general
revenue. This $13,450  should  have been  used to reduce the reimbursable  costs for the
preparation of the plans and specifications.                                                  13,450


    (c) The grantee claimed costs for printing and legal fees related to the sale of bonds. Costs
associated with the approval, preparation, issuance, and sale of bonds are not eligible for grant
participation  in accordance with EPA's "Construction Grants Handbook of Procedures,"
Chapter VII (formerly Program Guidance Memorandum No. 64).                              3,050

                                                                Total  Costs Questioned $17,742

Grantee's Comments

    The grantee concurred with the above findings and has indicated that it will compute the
amount of miscellaneous revenue for each contract and offset this revenue  to the cost of the
project.

Note 2

    We noted that compensation for engineering services was based upon  the fee curve and
multiplier methods of contracting. The use of the fee curve and multiplier and profit resulting
solely  therefrom have been accepted because, at the time  the contractual  arrangement was
made, these methods of contracting were not prohibited and were in accordance with accepted
industry practice. The fee curve and multiplier methods of contracting are now prohibited by 40
CFR 35, Subpart E, Appendix D, dated December 17, 1975.

    In addition,  the grantee's claim  of $600,000 for the  design services was  computed by
applying the fee suggested by curve A of the American Society of Civil Engineers to the total
actual construction costs, including change orders and overruns on estimated quantities in the
plans and specifications for completed contracts 1 through 4. However, paragraph B.5.a  of
Appendix D to 40 CFR 35 limits EPA participation to the amount based upon the low bid for
construction. Accordingly, we computed the accepted amount based upon curve A and the low
bids of $13,100,000 for both the eligible and ineligible portions of the construction contract.
This resulted in a fee of 5.9 percent. Application of the accepted rate to the low bid for eligible
construction  work of $11,790,000 resulted in  a fee of $695,610. This fee was reduced  by the
applicable portion ($125,210) of the $139,122 credit for preliminary work and construction
phase, for an accepted cost of $570,400.


                                         6-17

-------
Grantee's Comments

    The grantee concurred with the above finding.

Engineer's Comments

    The engineer agreed with the above finding and calculations.

NoteS

    We have questioned $10,508 of other architectural engineering fees as not being eligible for
EPA  participation  per Chapter  VII  of  the  EPA  "Construction Grants  Handbook  of
Procedures" (formerly Program Guidance Memorandum No. 64).

    (a) Processing and coordinating the grant application as reported on employee time sheets.   $3,420


    (b) Cost incurred for easement preparation.                                               2 870


    (c) Al5-percent service charge was applied to all direct nonsalary costs excluding mileage.
This service charge could not be supported by the accounting records.                            4,218


                                                                Total Costs Questioned $10,508

Grantee's Comments

    The grantee agreed with the above questioned costs.

Engineer's Comments

    (a) The firm stated that the majority of the grant application costs were incurred because
the grantee requested supplemental information and analyses

    (b) No Comment.

    (c) The firm stated that the service charge was provided for in the engineering agreement
and was used to compensate  for overhead costs and risks involved in  the  use of outside
consultants.

Note 4

    Of the total costs claimed by the grantee under the Project Inspection Fees cost category,
we have suspended $63,363 and questioned $7,894 for the following reasons:
                                             Amounts
Reference
a
b
Suspended
$63,363
- 0 -
Questioned
$5,742
2,152
                            Total        $63,363        $7,894

                                        6-18

-------
    (a) The grantee  had claimed  $69,105  for  force account  work representing  resident
inspection services. The use of force account  work had not been approved by EPA. Program
Requirements Memorandum 75-15  provides for a deviation from the provisions of 40 CFR
35.935-2(a) relating to the use of force account work on construction projects. The effect of this
deviation is to allow the use offeree accounts for any Step 1,2, or 3 work for which the Regional
Administrator has given prior written approval. Although the grantee had requested approval
for the force account work in a letter dated June 8,1976, the Regional Administrator had not, at
the time of our audit, responded to the grantee's request. Of the total amount claimed  for force
account work, $63,363 is supported by the grantee's accounting records; the remaining $5,742
is unsupported. Therefore, if retroactive approval of the force account work is granted, Federal
participation should be limited to the amount of supported  costs.

    (b) Questioned costs of $2,152  are inspection fees billed on Contract No. 2 invoices  17
through 20 for services after the contract completion date (June 18, 1976). Chapter VII of the
Handbook of Procedures states that increased costs resulting from lack of performance by the
construction contractor are unallowable for  participation, even if the grantee elects not to
exercise its right to recover liquidated damages. No liquidated damages were assessed, although
the contract was not completed until September 19,1976.

Grantee's Comments

    (a)  The grantee expressed the view that all of the force  account inspection costs are
proper, and stated, "I think that we can explain these charges such that they can be determined
to be eligible."

    (b)  The grantee did not concur with our position on resident inspection costs  incurred
after the contract completion date.

Engineer's Comment

    (a)  No comment.

     (b)  The engineer stated that a request for an extension of the contract completion date
had been submitted to EPA through the State Department of Natural Resources, but approval
has not been received. The engineer also contended that inspection costs have not been and will
not be increased due to delayed construction. The engineer stated that inspection services were
not provided during the  time the contractor was not working. Therefore, inspection costs
incurred after the scheduled completion date are not added costs but costs that would have been
incurred if the project had proceeded in a normal manner.

Auditor's Comments

    We believe the construction contractor will overrun the scheduled completion date even if
a time extension is granted. There is merit to the engineer's contention that no added cost will be
incurred since he did not perform during the "down period." We believe these facts should be
documented and considered at the time of final inspection. Until that time, unless the scheduled
completion date is revised, we recommend no payment for inspection services performed after
the scheduled contract completion date.
                                        6-19

-------
NoteS

    We have questioned or suspended the following amounts of construction costs as being
ineligible for Federal participation.

          (a)  Although eligible costs for construction were not questioned, we determined
that the Region had reimbursed the grantee for the Federal share of retained construction
payments. The grantee did not record or claim the retainage. The reimbursement of the Federal
share produced a temporary overpayment to the grantee. The Region should adjust for any
overpayments. Retainage should be deducted in all future partial payments.

          (b)  The amount suspended includes the following change orders which have not
been approved by EPA.

      Change  Order 3,  Contract 1                                 $ 3,429
      Change  Order 5,  Contract 1                                   4,142
      Change  Order 1,  Contract 3                                  20,541
      Change  Order 1,  Contract 5                                  11,955

      Total                                                        $40,067

          (c) Construction costs claimed also included sales tax not paid by the grantee and
ineligible construction. The details are as follows:

        Contract             Sales Tax      Ineligible Construction
                              Not Paid

            1                    $  837
            2                      300            $2,150*
            3                      250
            4                      310            4,000*
            5                      215
            6                      171
        Total                   $2,083            $6,150

     *Represents the cost of construction declared ineligible by EPA.

Grantee's Comments

     The grantee stated that it will no longer claim construction retainage or unpaid sales tax.
Regarding the suspended change orders, the grantee stated that the change orders have been
submitted to the state agency and are awaiting approval.
                                        6-20

-------
EXAMPLE AUDIT                                                 EXHIBIT B
REPORT NO. 2
                          CITY OF ANYWHERE,  U.S.A
                  SECONDARY SEWAGE TREATMENT PLANT
                         CONSTRUCTION  GRANT XXXX

COMMENTS ON COMPLIANCE, PERFORMANCE, AND INTERNAL CONTROLS

    As a part of our examination, we reviewed and tested the grantee's system of internal
accounting controls to the extent we considered necessary to evaluate the system as required by
generally accepted auditing standards. This evaluation established a basis for reliance on the
grantee's accounting control system in determining the nature, timing, and extent of other
auditing procedures necessary for expressing an opinion on the financial reports.

    The objective of internal  accounting control is to provide  reasonable, but not absolute,
assurance that the (1) assets are safeguarded against loss from unauthorized use or disposition
and (2) financial records  are reliable for  preparing financial statements and  maintaining
accountability for assets. The  concept of reasonable assurance  recognizes that the cost of a
system of internal accounting controls  should  not  exceed the  benefits derived  and also
recognizes that the evaluation of these factors necessarily requires estimates and judgments by
management.

    There are inherent limitations that  should be recognized in considering the potential
effectiveness of any system of internal accounting controls. In the performance of most control
procedures, errors can  result from misunderstanding of instructions, mistakes of judgment,
carelessness, or other personal factors. Control procedures whose effectiveness depends upon
segregation of duties can be circumvented by  collusion. Similarly, control procedures can be
circumvented intentionally by management,  either with respect to the execution and recording
of transactions or with respect to the estimates and judgments required in the preparation of
financial statements. Further,  projection of any evaluation of internal accounting control to
future periods is subject to the risks that the procedures may become inadequate because of
changes in conditions and that the degree of compliance with the procedures may deteriorate.

    The EPA "Audit Guide for Construction Grant Program," revised January 1978, requires
a review and evaluation of the  adequacy of the accounting system and internal controls of the
grantee to (1) safeguard its assets; (2) check the accuracy and reliability of the accounting data;
(3) promote operating efficiency; and (4) encourage compliance with  prescribed management
policies and such additional fiscal, accounting, and administrative requirements as EPA may
establish. We understand that EPA considers procedures conforming to the criteria in its audit
guide to be adequate for EPA purposes. Procedures that are not in conformity with the audit
guide indicate some inadequacy for EPA purposes. Based on this understanding and on our
study, we believe that the  City's procedures were  adequate (inadequate) for EPA purposes
except  for  (because of) the conditions  described below,  which we  believe  are material
weaknesses in relation to the grant to which  this report refers. In addition to such weaknesses,
other conditions which we believe are not in conformity with the criteria referred to above are
described on the following pages.

GRANTEE'S ACCOUNTING SYSTEM

    The grantee's accounting system did  not  provide  for (1) segregation of eligible and
ineligible costs; (2) time and effort reports to support costs of construction  inspection services;

                                        6-21

-------
(3) adequate internal controls over cash receipts; (4) reconciliation between the General Ledger
Account, the Construction In Progress-Sewer Plant Account, and the Outlay Report and
Request for Reimbursement  for Construction  Programs; and  (5)  acquiring supporting
documentation of consulting engineer billings.

SEGREGATION OF COSTS

    All costs, whether eligible or ineligible for EPA participation, were accumulated in the
Construction In Progress-Sewer Plant Account. This method of accounting makes it difficult
to determine eligible project costs for EPA participation.

    Accounting systems under Federal grants must provide for segregation of costs in order to
permit grantees and EPA to determine in which  costs the government will participate.

TIME AND EFFORT REPORTS

    At the time of audit, time and effort reports were not used by the grantee to support costs
incurred for construction inspection by force account.

    EPA requires time and effort reports to support direct salary costs to the grant project.
This enables EPA to adequately identify those costs applicable to the project.

INTERNAL CONTROLS

    The grantee's internal control over cash  receipts was considered inadequate. We were
advised that the accountant is solely responsible for preparing the deposits,  recording to the
cash receipts journal and general ledger, and performing bank reconciliations of the various
funds maintained by the grantee. Adequate physical safeguards and separation of duties are
essential for proper internal control.

RECONCILIATION OF  GENERAL LEDGER  ACCOUNT  AND OUTLAY REPORT

    The costs recorded in the Construction In Progress-Sewer Plant Account did not agree
with the costs reported in the Outlay Report. Our analysis of the cash disbursements journal
showed that two engineering invoices totaling $13,125.89 and grantee travel costs for $836 were
paid out of another fund. We determined  that these  amounts were chargeable to the
construction fund. In addition, we found that a transfer of charges for $21,840.94 to the
construction fund  had been recorded twice. We were able to reconcile the Construction Fund
Account and the Outlay Report after taking these and other transactions into account.

SUPPORTING DOCUMENTATION FOR SUBAGREEMENTS

    The grantee was not requiring supporting data such as names of personnel, hours worked,
rates of pay, in-house cost tickets, travel expense reports, vendor invoices, or other applicable
support to be provided by the consulting engineer for direct costs billed to the grantee. Such
support would enable the grantee to determine if the direct costs are appropriate and valid to
the grant project.

    During the course of our audit, the grantee established a procedure for segregating eligible
and ineligible costs and began using time and  effort reports to support force account work.
Consequently,   no further recommendations on  these items  are  made  at this  time.
Recommmendations on the other items are made in the Recommendations section that follows.
                                       6-22

-------
    For the most part, costs were not questioned in this report due to inadequacies in the
grantee's accounting system.  We were able,  through other audit  techniques, to  make
determinations on costs impacted by the accounting system deficiences listed above.

Recommendations

    We recommend that EPA ensure that the grantee:

    (1)  Improve its internal controls over cash receipts by segregating the duties that are now
performed by the accountant.

    (2)  Make  the necessary  adjusting  entries  in  order  that the  Construction In
Progress-Sewer Plant Account will reconcile with the Outlay Report.

    (3)  Require the consulting engineer  to  submit supporting documentation for direct
charges billed.

Grantee's Comments

    The grantee agreed to implement the above recommendations.

GRANTEE'S PROCUREMENT SYSTEM

    We found that the grantee had not adequately solicited bids for the construction work as
required by the EPA regulations. Title 40 CFR 35.938-4(a) provides that when the estimated
cost of Step 3  construction is $10 million or more, notice for solicitation must generally be
published  in trade  journals of nationwide distribution. The estimated construction cost
exceeded $10 million for  this  grant,  but the  bids were solicited only through "The City
Bulletin."  Although the grantee did receive at least four bids for  each contract under the
project, solicitation  of bids appears to be something less than nationwide as prescribed by
regulations. In addition, we noted that the grantee failed to allow 30 days between the date of
first announcement of the call for bids and the date by which the construction bids were to be
submitted. Under 40 CFR 35.938^-(b), generally not less than 30 days' notice must be given to
assure adequate time for bid preparation.

Recommendation

    We recommend that the Region require the grantee to comply with the provisions of 40
CFR 35.938^- mentioned above.

Grantee's Comments

    The grantee stated that it was unaware of these requirements, but it will comply with these
provisions on future grants.

GRANTEE'S PROPERTY MANAGEMENT SYSTEM

    The grantee did not maintain a property management system that meets the requirements
of 40 CFR 30.810, which in essence states that property records shall be maintained accurately
and provide for: a description of the property;  manufacturer's  serial number or  other
identification numbers; acquisition date  and cost; source of the property; location, use, and
condition of the property;  and ultimate  disposition  data including sales price or the method
used to determine fair market value if the grantee compensates EPA for its share.
                                        6-23

-------
    Although only a few items of equipment have been purchased, as part of the construction
contract the grantee will receive laboratory equipment and office furniture that will require
property accountability.

Recommentation

    We recommend that EPA ensure that the grantee establishes a property  management
system, in accordance with 40 CFR 30.810, to account for equipment and property purchased
under the grant.

Grantee's Comments

    The grantee stated that it will install a property management system that meets the criteria
of 40 CFR 30.810.

Engineer's Accounting System

    The  engineering  firm's accounting  system is  considered adequate to  identify  and
accumulate costs under the subject contract.

Engineer's Procurement System

    Since there were no major procurements under the engineering subagreement, our audit of
the engineer's procurement system was limited to a cursory review. In the areas we did examine,
there were no deficiencies noted.
                                        6-24

-------
                                                              APPENDIX  A
                  SURVEY  OF GRANTEE'S ACCOUNTING,
            PROCUREMENT, AND PROPERTY MANAGEMENT
                                   SYSTEMS

INTRODUCTION

    This survey should be considered  as  a starting  point to gain a quick,  preliminary
understanding  of the auditee's  operating system. It supplements but does not replace the
normal audit review. The normal audit review must still be performed using the detailed audit
guide, a core audit program, and the auditor's judgment.

    This survey should be performed in all interim audits and all final audits except where a
final audit is performed on an auditee that has no active in-house grants. The survey is intended
to be used to analyze the grantee's accounting records and systems that pertain to the EPA
grant. It should not be applied to those systems that are not affected by the grant.

    Depending on the audit, some questions may be more relevant than others. The matter of
relevancy should be settled between the field auditor and his supervisor prior to completion of
this survey.

    Questions  that may pertain to both the grantee and the engineer are marked with a double
asterisk. Questions that are applicable to the grantee only are not coded. Questions that pertain
to the engineer only are marked by a single asterisk.

    Negative responses generally will indicate a potential problem. The degree of seriousness of
each negative answer should be discussed between the field auditor and his supervisor  before
further audit action is taken.
                                       A-l

-------
               Survey of Grantee's Management  System
                                                                                   Yes
                                                                                       No
N/A
                                                                                               W/P Ref.
ACCOUNTING SYSTEM

* *   1.  Is the accounting routine set forth in accounting manuals?

**   2.  Do we have copies of such manuals in our files?

**   3.  Does the auditee main tain:

            a. An accrual accounting system?

            b. A cash basis system?  If so, are adjustments made to properly reflect the
auditee's overhead and G&A submissions on the accrual basis?

* *   4.  Does the auditee have an internal audit staff? If so,

            a. Do they render written reports on the results of their examinations?

            b. Have we reviewed their reports?

            c. Are they directly responsible (and do they report) to an executive officer
other than the chief accounting officer?

**   5.  Are  the auditee's accounting records subjected to an independent audit at least
every two years?

**   6.  Has  the auditee established project  accounting records  to record  the costs
applicable to EPA work?

**   7.  Are all incurred costs of a project recorded on these records on a current basis?

**   8.  Does the auditee propose and accumulate costs on all projects in a consistent and
compatible manner?

* *   9.  Is appropriate documentation maintained to support direct charges of:

            a. Personnel?

            b. Consultants?

            c. Fringe benefits?

            d.  Materials, supplies, and equipment?

            e. Travel?

            f. Other costs (subcontract charges, long-distance telephone calls, etc.)?

**   10. Are costs contained in the project accounting records segregated as to their
eligibility, allowability, and allocability to the respective EPA projects?

* *   11. Are controls established to ensure that:

            a. Grantee costs  incurred and recorded prior to or  subsequent to  the
established Federal grant period are segregated and not claimed for reimbursement unless
approved?

            b.  Engineer costs  incurred and  recorded prior  to or  subsequent to  the
established contract period are segregated and not claimed for reimbursement unless
approved?
                                                  A-2

-------
               Survey of Grantee's Management  System
                                                                                  Yes
                                                                                      No
                                                                                         N/A
                                                                                              W/P Ref.
**   12. Is change order work separately identified in the respective project cost records?

**   13. Are project costs summarized and reconciled with control accounts contained in
the auditee's general ledger?

**   14. Are the project cost records used as the basis for:

            a. The grantee's financial status reports and "Request for Reimbursement"
vouchers?
            b.  The engineer's request for reimbursement?
**    15. Are  frequent comparisons  made  between expended  and budgeted costs to
provide timely indications of potential project overruns?

      16. Are approvals requested for significant deviations from amounts contained in
the grant or contractual agreement?

**    17. Is there an established policy to maintain consistent treatment and control of
direct and indirect cost distributions to avoid duplicate recoveries of cost?

**    18. Are separate cost centers established to accumulate and distribute such items as:

            a. Computer usage?

            b. Reproduction charges?

**    19. Are administrative  service charges or material handling rates based on uniform
policies and supported by the accounting records?

**   20. Has  the auditee developed indirect  cost rates  in accordance with  Federal
requirements?

*    21. Are separate offsite indirect cost rates applied to job site labor?

**   22. Are overhead expenses distributed between the various indirect cost pools in a
systematic manner?

**   23. Does the auditee post credits for rebates, returns, and allowances as a reduction
to expenditures?

Automated Data Processing (ADP)

**    1. Is the accounting system automated? (If "no," omit questions 2 through 10.)

**   2. Are the ADP aspects of the auditee's financial accounting system documented?

**   3. Are audit trails provided that permit the tracing of any transaction back to the
original source document and forward to summary records?

**   4. Are source  documents controlled  from the point  of origin to the point of
conversion to machine-readable media?

**   5. Is the access to machine-readable computer facilities and records (tapes, cards,
etc.) controlled?

**   6. Are rejected and erroneous data controlled until corrections are made?
                                                 A-3

-------
Survey of Grantee's Management System
** 7. Are positive processing controls (e.g., controls which make tests against
established criteria before processing action is taken, such as tests to determine whether
updates have been made, validity checks, limit tests, compatibility tests, field completeness
tests) programmed into the automated system?
** 8. Are provisions made for:
a. Safeguarding computer programs and data files,
b. Backup or emergency operation, and
c. Reconstruction of data files in case of catastrophe?
* * 9. Does the system provide controls over the distribution of reports?
** 10. Does the auditee's internal audit staff periodically review the ADP function with
respect to:
a. Software and hardware utilization?
b. Budgeted versus actual operating costs?
Obligations
1 . Does the system include accounting for obligations/encumbrances/commitments
(legally binding agreements)?
2. Does the system limit obligations to the amount approved for each respective
budget category?
3. Are procedures established to assure that obligations reported are supported by
appropriate purchase orders, contracts, etc.?
4. Do these procedures provide for a periodic validation of recorded obligations?
5. Are obligations entered on accounting records when the legal commitment is
made (e.g., approval and issuance of subgrant or contract)?
6. Does the system require the timely liquidation of obligations?
7. Are obligations reclassified as expenditures when the goods or services are
received or constructive receipt occurs?
Cash controls
** 1. Are details of vouchers payable or accounts payable balanced monthly with
general ledger controls?
** 2. Are bank accounts reconciled monthly by employees who do not prepare or
approve checks and who do not have access to ledgers?
** 3. Are supporting data attached to and filed with vouchers?
** 4. Are supporting data controlled and cancelled to minimize the possibility of
improper or duplicate payment?
5. Are records maintained to identify and support in-kind contributions applicable
to specific projects?
Yes
























No
























N/A
























W/P Ref.
























A-4

-------
Survey of Grantee's Management System
6. Are excess grant funds invested for interest by the auditee where permitted?
Personnel
* * 1 . Does the auditee maintain an organizational chart?
** 2. Are organizational functions and duties structured to segregate as much as
possible responsibilites such as approving financial transactions, entering transactions,
keeping control records, and maintaining custody of funds and property?
** 3. Are employee time distribution records maintained to reflect the actual time
spent on each activity, including leave?
** 4. Are the individual time distribution records prepared and certified by each
employee and approved by his supervisor?
** 5. Are labor costs distributed in accordance with the time reflected on time
distribution records?
** 6. Are such labor distribution costs periodically reconciled with the actual payroll
register?
** 7. Does the auditee have written policies for overtime payments?
** 8. Are such overtime policies acceptable under the terms of the grant and
applicable Federal regulations?
* * 9.1s unpaid overtime for exempt employees properly accounted for?
** 10. Are labor rates consistently applied (e.g., individual, category averages,
departmental averages)?
* 11. Are employees working under Federal grants/contracts paid' at rates
comparable to the rates paid employees working on other projects?
* 12. Has the auditee established reasonable and consistent labor rates to cover the
time spent by top executives?
* 13. Are formal policies in effect with respect to bonuses, retirement plans, and/or
profit sharing?
PROCUREMENT SYSTEM
** 1. Do the procurement personnel have independent and final authority over the
award and administration of purchase contracts?
** 2. Do procurement policies and procedures require requisitioners to affirm that:
a. The items/services are really needed and not otherwise available?
b. The specifications and quality requested are actually needed?
** 3. Does the formal selection process attempt to restrict the use of sole-source
contracts and promote competitive bidding to the maximum extent possible?
a. Is written justification required when noncompetitive selection is used in
lieu of formal public advertising on major procurements?
Yes
























No
























N/A
























W/P Ref.
























A-5

-------
               Survey of Grantee's  Management System
                                                                                 Yes
                                                                                     No
                                                                                        N/A
W/P Ref.
            b. Are all responsible bidders allowed a reasonable time in which to submit
their offers?

* *    4. Wherever possible, do major procurements require the use of:

            a. Source lists and catalogues?

            b. Vendor files which cover:


                  (1) Technical and financial capabilities?

                  (2) Quality and delivery experience?

**   5.  Is documentation maintained to support the costs  or prices  negotiated on all
major purchases and contracts?

**   6.  Are procedures in effect to assure that required conditions stipulated in the grant
general provisions and appropriate clauses outlined in EPA regulations are incorporated
into procurement aggreements?

**   7.  Are procedures established to ensure that the type of purchase contract utilized is
appropriate  for  the  procurement being  undertaken  and  acceptable to the Federal
government?

PROPERTY MANAGEMENT SYSTEM

     1.  Does  the auditee  maintain property  records  for all government-furnished
property and equipment which show:

            a. A description of the item?

            b. The date acquired?

            c. A property tag I.D. number or manufacturer's serial number?

            d.  The location of the property?

            e. The cost or value?

            f. The condition of the item?

            g. The percent of Federal participation?

     2. Are periodic inventories made to validate government property  information?

     3. Are differences between physical and book inventories analyzed,  and are the
resulting adjustments approved?

     4. Does the auditee follow different accounting policies with respect to major and
minor equipment expenditures?

     5. Are procedures established to assure that required EPA approval is  obtained for
purchases or any changes in use or disposition of grant/contract property?

     6. Do the procedures require that EPA receive its appropriate share of any proceeds
from disposition of the property?

     7. Has the  auditee established procedures for classifying and recording property
improvements, major repairs, and the rearrangement of machinery and equipment?
                                                 A-6

-------
                                                                APPENDIX  B

                      BOND  CALCULATION  GUIDANCE

    Bond issue costs are allowable if incurred under Public Law 84-660, but are unallowable
under Public Law 92-500.

    The primary  guidance for  eligible bond  cost for construction  grants  is included in
Construction Grant Memorandum 70-5, dated February 13,1970, which is quoted below:

    Subject: Uniform Determination of Bond Issue Costs for Construction Grants

    It has been noted that some differences exist  between Regions  in the  method of
    determining bond charges eligible for grant participation. Therefore, in order to provide
    for uniformity, the following procedures are to be followed in computing such costs.

    Bond costs eligible for Federal participation are those associated with the bond funds
    actually needed to finance the applicant's share of the eligible costs. Bond funds used in
    computing bond costs, then, will normally include the total eligible cost of the project less
    any funds from Federal and State sources. If a portion of the grantee's contribution comes
    from sources other than a bond issue, a further deduction would be necessary. In those
    cases where State grants consist of annual payments over an extended period and it is
    necessary to "issue bonds to prefinance the State grant, the eligible cost  for computing
    allowable bonding costs need not be reduced by the amount of the ultimate State grant.

    Eligible bond issue costs include those costs associated with printing, advertising, issuing,
    and other costs subsequent to the bond election.

    Federal and State grant amounts, plus any funds from other sources, will be computed on a
    percentage basis, based on the funds expended for construction of the project. If a project
    has proceeded on a reimbursable basis, bond costs based on all bonds used during the
    construction are eligible, even though reimbursement is made at a later date.

    After determining the percentage of Federal and  state grants to be considered (plus any
local funds from sources other than bonds), the eligible bond issue costs are determined by use
of the formula explained in Example 1.

    Examples 2 and 3 cover some of the problem areas  which may arise. In addition, the
following comments should clarify most of the situations encountered.

COMMENTS ON SPECIAL SITUATIONS

    1. If the bond issue is increased during the project period, all bonds issued and all related
eligible costs are used in the bond formula.

    2. If other Federal agencies participate in the eligible cost, the percentage reduction from
"K" is increased as shown in Example 1. A HUD grant is usually applicable to the ineligible
portion of the project; in such cases, this step is disregarded.

    3. Where there is an increase in the Federal grant  subsequent to the bond transaction and
the grantee is legally bound to pay  bond costs relative  to the original grant amount, no
adjustment of the K factor is required. The same applies to state participation. In essence, the K
                                         B-l

-------
factor should be based on funds available (Federal, state, and other) at the time the grantee
negotiated for the bonds.

    4. Studies for determining water or sewage rates are sometimes included in reported legal
or bonding cost and not identified. Such studies are considered general administration of the
municipality and thus not eligible for Federal grant participation.

    5. Immaterial differences in the bond cost calculation should be disregarded.
                                          B-2

-------
                        BOND  COST CALCULATIONS

EXAMPLE #1 - NORMAL  BOND CALCULATION
F  =
      KC

F  = Eligible bond issue costs to  be  calculated
S  = Total eligible project costs,  exclusive of bond issue costs--$180,029
K =  100% less percentage of Federal grants, state grants,  other
    financing, and grantee cash.  For this  example,  K=45%  (100%-(30+ 15+10)).
B  = Amount of bond issue--$192,000
C  = Total bond issue costs--$4,500
„      $180,029
r  =   	
                  -1
       $192,000
    45% x $4,500
F  _   $180,029
   ~   $192,000   .
        $2,025
F  _   $180,029
         93.81
F  -    $1,919
NOTE: In rare instances, an amount slightly greater than C, allowable bond costs, will be
obtained for F. In such cases, use C.
                                       B-3

-------
                        BOND COST CALCULATIONS

EXAMPLE #2 - APPLICATION OF GRANTEE CASH TO INELIGIBLE  COSTS


S = $81,145
C  =  $972
B  =  $60,000
F  =  Eligible bond issue costs to be calculated

Determination of Ineligible Costs

Total  Project Costs                  $82,145
Eligible Project Costs                $81,145
Ineligible Project Costs                $1,000

Source of Funds

Federal Grant                         55%
Grantee Cash                         $5,000

Determination of Percentage of Grantee Cash

$5,000 -  $1,000 (Ineligible) =  $4,000 =  cash available for eligible project costs*

                   C c
                  °f S
Computation of K

K = (100%  less 55% grant less 4.9%  grantee cash) =  40.1%

Computation of F

         S
F  =
      -5--i
      KC
                 -1
       $81,145
       $60,000
     .401 x $972

F  = $531
    * Local funding should be applied to the ineligible project costs first, and the remainder
should be used to reduce K.
                                        B-4

-------
                       BOND COST CALCULATIONS
EXAMPLE  #3 - SIGNIFICANCE  OF SOURCE OF FUNDS
Computation of S

Construction Cost
Technical Service
Administrative
Bond Cost
                            $120,220
                              13,310
                                600
                           (Omitted)
Source of Funds

Federal  Grant
Bond issue
Balance unaccounted" for*
     Amount

      $44,260
       75,000
     $119,260

       14,870
S = $134,130
S = $134,130

      Percent of
        Total

         33
         56
        Jl
        100
Computation of K

K = 100% less 33% (Federal) less  11%  (local) = 56%

Computation of C

Legal Costs
Printing Costs
Advertising Costs
                                                     C  =
                              $1,500
                                500
                                187
                              $2,187
Computation of F

      $134,130
F  =
      $ 75,000
    $2,187 x .56

F  =  $2,227
Since F is greater than C, use $2,187 as eligible bond cost.

    *The balance unaccounted for is assumed to come from local funds unless the funds were
obtained by means of a loan, in which case the percentage obtained by loan would not be
deducted from the K factor. In the example above, if the $14,870 had been obtained by loan, K
would be 100% less 33%, or 67%.
                                      B-5

-------

-------
                                                               APPENDIX  C

      SUPPLEMENTAL AUDIT PROCEDURES FOR RELOCATION COSTS

APPLICATION OF AUDIT PROCEDURES

    These audit procedures supplement the "Audit Guide for Construction Grant Program."
EPA  Division  Audit  Directors will  authorize independent public  accountants and  EPA
auditors  to  use these supplemental procedures whenever a construction  project  includes
relocation costs. The  procedures  must be followed explicitly because they  are the  audit
application of EPA regulations, 40 CFR, Part 4, that pertain to payments made to displaced
persons.

    People who are displaced or whose realty is acquired after January 1, 1971, due to an EPA-
assisted project are entitled to compensation as provided by the Uniform Relocation Assistance
and Real Property Acquisition Policies Act of 1970. Auditors shall use the following  checklist
when examining relocation costs. Applications for benefits must be filed within 18 months from
the date  the displaced person moves from the acquired real property or the date of final
payment for such property, whichever is later, unless this time period is extended by  the EPA
Administrator.

ALLOWABLE COSTS

A. Dwelling and Personal Property

     1. Transportation of people and personal property to a replacement site, not to exceed 50
miles unless justified.

    2. Packing, crating,  unpacking,  and uncrating of personal property,  and the cost of
advertising for such services.

    3. Storage  of personal property, generally up to 12 months.

    4. Insurance premiums covering loss or damage of personal property in transit or storage.

    5. Lost, stolen, and damaged property; removal,  reinstallation,  and modification of
property.

    6. Movement of personal property by the displaced person, not  to exceed the  cost of a
commercial move unless approved by the EPA Administrator.

    7. In lieu of actual reasonable moving and related expense, payments to each occupant of a
dwelling of (a) a $200 dislocation allowance and (b) a moving expense allowance not to exceed
$300  based  on  state highway department or Federal Highway Administration allowance
schedules.

    8. A replacement  housing payment not to exceed $15,000, provided the displaced owner-
occupant actually owned and occupied the dwelling not less than 180 days prior to initiation of
negotiations, and the  displaced owner-occupant purchases and  occupies a replacement
dwelling. The $15,000 allowance is the lower of (a)  $15,000 less payment for any increased
mortgages, interest costs, or incidental closing costs, (b) the difference between the acquisition
price  of the  acquired dwelling and the estimated cost of a replacement dwelling, or (c) the
difference between the acquisition price of the acquired dwelling and the actual price of the
replacement dwelling.
                                        C-l

-------
    9. A replacement housing payment not to exceed $4,000 is payable to a displaced tenant or
a displaced owner-occupant of a dwelling for less than  180 days, provided he occupied the
dwelling for not less than 90 days and is not eligible for the $15,000 replacement housing
allowance. A displaced owner-occupant is entitled  to the $4,000 payment, rather than the
$ 15,000 payment, if he elects to rent, rather than buy, a replacement dwelling.

    Computation of the $4,000 payment is as follows:

         a.  Displaced tenant.  48 times the reasonable monthly rent for  a comparable
replacement dwelling less 48 times the average month's rent paid by the displaced tenant for the
three months preceding the initiation of negotiation.

         b.  Displaced tenant by displacing agency. 48 times the reasonable monthly rent tor
a comparable replacement dwelling less 48 times the monthly economic rent, but no more than
would be received under the $ 15,000 payment provision.

         c.  Displaced homeowners. 48 times the reasonable monthly rent for a comparable
replacement dwelling less 48 times the monthly economic rent, but no more than would be
received under the $ 15,000 payment provision.

    In no event shall the rental payment, plus the monthly average rental or economic rent,
exceed the rental of the replacement dwelling.

    Monthly economic rent is either the result of an analysis of the available private rental
market, an analysis of at least three comparable replacement dwellings available on the private
market, or any method approved by the EPA Administrator.

    10. Should a tenant elect to purchase a house within one year from displacement, the
replacement housing payment shall be the down payment, plus incident settlement costs, using
a conventional loan, and shall include points or a  loan service fee. The maximum payment is
$4,000; if more than $2,000, the tenant must match the excess dollar for dollar up to the $4,000
maximum Federal payment.

    11. The rules for determining the cost of a replacement dwelling are the same as those used
to set monthly economic rent (Item 9).

    12. Land values associated with the replacement housing payment shall be determined as
follows:

         a.  A dwelling located on a tract  typical for the area-probable selling price of a
comparable replacement dwelling less the acquisition price of the acquired property.

         b.  A dwelling located on a tract larger than typical for the area-probable  selling
price of a comparable replacement dwelling  on a typical tract less the estimated value of the
dwelling on a tract typical for the area.

         c.  A dwelling located on a tract having a fair market value higher than residential
use-probable selling price of a comparable  replacement dwelling on a typical tract less  the
estimated value of the dwelling assuming it was located on a tract typical for the area.

    13. No part of a replacement housing payment may be made for any portion of a dwelling
used in connection with a business or farm.
                                         C-2

-------
     14. Each individual or family occupying a multiple dwelling is entitled to separately
calculated replacement housing payments.

     15. Displaced homeowners of a multifamily building are entitled to payment based on the
cost of a comparable one-family unit in a multifamily or single-family structure.

B.   Business or Farm

     1. Packing, unpacking, crating, and uncrating of personal property, the advertising for
such services, and storage of personal property (generally up to 12 months).

     2. Insurance premiums covering loss or damage while in transit or storage.

     3. Lost, stolen, and  damaged property;  removal, reinstallation, and modification  of
personal property.

     4. Movement of personal property by the displaced person, not  to exceed the cost of a
commercial move unless approved by the EPA Administrator.

     5. Should the cost of moving the property be disproportionate to its value, reimbursement
will be the difference between liquidated value of the property to be moved and the replacement
cost at the relocated site.  This is applicable  to junkyards, stockpiled  sand, gravel, minerals,
metals, etc.

     6. Should the cost of moving outdoor advertising displays equal or exceed their in-place
value, such displays may be acquired along with the realty, unless prohibited by state law.

     7. The expenses of searching for a replacement farm or business  (limited to $500 unless
approved by the EPA Administrator):

          a.  Travel cost.

          b.  Extra cost of meals and lodging.

          c.  Time spent in search at the displaced person's salary rate, not to exceed $10
hourly.

          d. Necessary brokers' fees to locate a replacement business or farm if approved by
the displacing agency.

     8. Actual direct loss of tangible personal  property as a result of relocation:

          a.  Business or farm operation discontinued-fair market value of personal property
for continued use at the displaced location, or estimated cost to  move same up to 50 miles,
whichever is less.

          b.  Personal property abandoned-reimbursement same as 8a above.

     The cost of removal of personal property will  not be offset against any payments due
displaced persons. The displaced person must make a bona fide effort to  sell property not
moved.

     9. A displaced person in business may  elect, in lieu of reimbursement for moving and
related expenses, a fixed amount equal to the  average annual net income of the business if that
                                         C-3

-------
business: substantially contributes to the displaced person's income and cannot be relocated
without substantial loss of income; is not part of a firm engaged in similar business having one
other location; is not being acquired by  a state or Federal agency; and  is not an outdoor
advertising business.

     10. A displaced person in farming may elect, in lieu of reimbursement for moving and
related  expenses, a fixed amount equal to the average annual  net  earnings. Should  the
acquisition be partial, payment can be made only if the remaining property  is not an economic
unit.

     11. A displaced nonprofit organization may elect,  in lieu of reimbursement for moving
and related expenses, a fixed amount equal to the average annual net income, provided (a) the
organization cannot be relocated without a substantial loss in existing  patronage and (b) the
organization  is not part  of a commercial enterprise having one other location, engaged in
similar activity, which is not in itself being displaced.
                                          C-4

-------
                                                               APPENDIX  D
   CRITERIA FOR  ELIGIBIITY AND  ALLOWABILITY OF SELECTED
                                ITEMS  OF COSTS

INDIRECT COSTS

    Indirect costs are those incurred for a common or joint purpose, benefiting more than one
project or cost objective, and not specifically identifiable to the particular  project  or cost
objective benefited. Indirect costs consist of items of a general overhead nature such as office
space, utilities, and telephone. The costs are allowable only if determined on the basis of a
negotiated indirect cost  agreement and incorporated in the grant agreement. (See 40 CFR
30.715-2.)

TRAVEL COSTS

    Grantee  travel costs-allowable  travel  costs include travel  considered necessary and
directly related to accomplishing project objectives. Travel not directly related to construction
and/or startup of the facility, including trips to professional meetings, symposia, lectures, etc.,
is not allowable as a direct charge to the project. Travel not directly related to a specific project
may, however, be recovered under an indirect cost agreement (FMC 74—4).

    Consulting engineer travel costs—allowable travel costs include travel considered necessary
and project related, including on-site travel costs. Costs of relocation of employees and their
families may be considered allowable when such travel is justified and  approved by the grantee.
The  cost of transportation between  living  quarters and the construction site  is normally
unallowable. In unusual  circumstances, where job sites are located in isolated areas and living
quarters are not available within 30 miles, travel costs between living quarters and the job site
are considered allowable  (FPR 1-15.2 and FPR 1-15.4).

BOND COSTS

    All costs  under P.L. 92-500 grants associated with the approval, preparation, issuance,
and sale  of bonds  (including bond counsel and underwriters' fees) are ineligible for grant
participation. Interest on bonds or  any other form of indebtedness is unallowable (FMC 74-4).

LIQUIDATED DAMAGES

    Monies received by grantees in the form of liquidated damages shall have no effect on the
determination of allowable costs of grant projects. However, any additional costs-construction,
engineering, legal, or administrative-generated because of a contractor's lack of performance
should be covered by the liquidated damages received. Thus, any such increase in cost as a
result of lack of performance is unallowable  for participation even if the grantee elects not to
exercise its right to recover liquidated damages.

BID BOND FORFEITURE

    All bid bond forfeitures should be treated as a reduction to project construction costs.
                                        D-l

-------
STUDIES, REPORTS, AND FEDERAL REQUIREMENTS

Rate Studies

    Such studies are eligible if required for the establishment of user charge or industrial cost
recovery systems in order to comply with 40 CFR  35.925-11  and 35.925-12. Such studies
require prior approval either in the grant agreement or an amendment thereto. Allowable costs
may include legal, CPA, and engineering fees related to the studies. (In order to avoid double
payment,  care  must be exercised to assure that such work is not incident to a general
contractual obligation.)

Financial Reports and Studies

    To the extent that such reports constitute "rate studies" for user charges and/or industrial
cost recovery procedures, the costs are allowable, provided that such studies are approved in
advance by the Regional Office and that the results of such studies are acceptable to EPA.
Financial reports which  constitute studies of, for example, the local tax base or tax structure, to
determine the financial capabilities of the applicant or the financial feasibility of the proposed
undertaking, are similarly allowable. The costs of all other financial reports and studies should
generally be  considered unallowable because such studies constitute a normal function of
government.

    In  this  regard, the  Regional Office should adhere to a strict interpretation of the term
"studies." Generally, "studies"  refers to preliminary reviews, examinations, analyses,  etc. The
interpretation must not be extended to include preparing procedures, designing implementation
schemes, drafting statutes or regulations, delineating boundaries relating to finances, issuing
bonds, adjusting tax rates,  establishing assessment districts, or  performing  other  activities
which are a normal function of government and as such are unallowable.

Establishment of Special Assessment Districts

    The "mechanics" of establishing special assessment districts developed, for example, on
the basis of rate studies, are a normal function of government, and as such their associated costs
are unallowable. Included in this restriction are legal,  administrative, and engineering costs
associated with activities such as (1) drafting and reviewing statutes/ordinances, (2) preparing
regulations, (3) delineating district boundaries, and (4) holding elections.

    This policy extends equally to the establishment of any "special districts" such as  election,
service, or rate districts (including Regional Authorities) related to the grant project.

Public Liaison Services

    Such services are generally unallowable since they constitute a type of public information
service and as such are not directly related to or necessary for the construction of the treatment
works.

Public Participation in Step  1

    EPA Regulation 40 CFR 35.917-5 states that "...the facilities planning process (Step 1)
shall be consistent with  40 CFR 105-Public Participation in Water Pollution Control...one or
more public hearings or meetings should be held within the area to obtain public advice...."
                                          D-2

-------
    In some cases, these minimum requirements can be met without expense. However, in
instances where the plan will be extensive, public interest is significant, or the chance of serious
public controversy is high, the expenses  of meeting these minimum requirements may be
increased. In such instances:

          (1)   Additional public participation efforts may also be appropriate.

          (2)   The consulting engineer may have to allocate staff time for preparing mailing
lists, fact sheets, summaries of technical reports, maps, graphics, and questionnaires for the
public meetings. Staff time may also have to be spent writing and distributing news releases,
meeting summaries,  and reports. In addition to the required meetings and hearings, other
meetings and workshops might be necessary, and the staff  might  have to appear before local
boards, civic groups, and other interested organizations.

          (3)   The municipality may set up a task force or  advisory committee to assist in the
planning process.

    The above services  are grant  eligible,  and the determination  of their remuneration is
subject to the terms and scope of the particular subagreement between the grantee and its
engineer. If additional public participation services  not covered in the basic engineering firm
contract scope are required by the grantee, state, or EPA offices, then EPA should participate
in such amended contract scope costs.

    Administrative costs of the grantee relating to participation are  reimbursed as outlined in
the grant agreement.

    Any costs (travel, per diem, etc.) of the citizen groups  or other interested parties are not
grant eligible.

Assistance with State and Federal Regulations

    The cost of assistance associated with addressing state and  Federal regulations and
procedures which  are basic to the  functions of general government (such as preparation of
applications and related documents or obtaining state construction and discharge permits) are
unallowable. Costs growing out of meeting specific Federal statutory requirements such as
public hearings  and other activities  related to the user  charge study,  facilities planning,
National Environmental  Policy Act  (NEPA), Uniform  Relocation Assistance  and Real
Property Acquisition Policies Act, etc., are allowable.

    If such costs entail assistance which is readily available through Federal or state offices,
such  as interpretation of regulations  or  explanation of grant procedures,  they  should  be
disallowed. (In order to avoid double payment, care must be exercised to assure that such work
is not incident to a general contractual obligation.)

Redesign/Replanning Costs Resulting from Changes in Federal Requirements

    In those cases in which an applicant's completed or partially  completed planning and/or
designs  are  rendered invalid or unacceptable by changes in  Federal requirements, both the
original cost plus the redesign or replanning costs  are allowable. The Regional Office must
assure itself that the planning and/or design thus invalidated was undertaken in good faith by
the applicant and was not the result of a disregard for existing Federal directives by either the
applicant or his agent.
                                          D-3

-------
Costs of Implementing the Uniform Relocation Assistance and Real Property Acquisition
Policies Act of 1970 (P.L. 91-646)

    Four basic categories of costs associated with this Act may be considered allowable:

          (1) Moving and related expenses;

          (2) Replacement housing;

          (3) Relocation assistance advisory services (entailing direct services of the grantee in
assisting the displaced person(s)); and

          (4) Acquisition of real property.

    Documented allowable costs from these categories incurred on or after July 1, 1972, will be
treated as other allowable project costs and reimbursed at the same percentage rate. In the case
of costs resulting from acquisition or displacement occurring before July 1,1972, EPA shall pay
the full amount of the first $25,000 of such costs for each displaced person. Allowable costs
should be determined in accordance with 40 CFR 4 and guidelines which will be issued
pursuant thereto. (See Appendix C of this guide for audit procedures.)

Field Surveys to Identify Cultural Resources

    Reasooable  costs  incident  to  field  surveys to  identify  historical,  architectural,
archeological, and cultural resources in the primary impact area of grant projects are allowable.
Allowable costs must be determined on a case-by-case basis and may include the cost of on-site
inspections,  review  of pertinent  documents,  photographic  reconnaissance,  services  of
archeologists or historians, etc.

    Such costs should receive  prior approval and delineation by the EPA Regional Office.
Survey costs associated solely with the examination of the National Register of Historic Places
are unallowable. EPA may participate in the cost of intensive surveys (e.g., "digging") only
when a sufficient amount of information exists to  indicate that there is  a reasonably  high
probability of discovering important cultural resources.

    See PRM 75-27, dated November 2, 1975, for additional guidance on this subject.

Industrial Planning

    Step 1 related costs of industrial planning conducted and paid for by  an industry whose
wastes will be treated in a municipal system are not allowable. (See 40 CFR 35.925-15.)

Facilities Serving Communities and Federal Facilities

    Whenever a planned treatment works will jointly serve a municipality and a  Federal
facility, that portion of construction cost allocable to the Federal facility will not be allowable
for 75-percent construction grant funding, subject to the following exceptions:

          (1)   Facility planning (Step 1) costs.

          (2)   Cost of Step 2 work if a Step 2 grant has been certified by the state for funding
to EPA prior to the December 29, 1975, issuance of Program Guidance Memorandum 62 (now
PRM 75-35).
                                          D-4

-------
          (3) Design and construction costs allocable to a Federal facility producing less than
250,000 gallons per day,  or five percent of the total design flow of waste treatment works,
whichever is less.

     That portion of the construction costs allocable to the Federal facility shall be based on all
factors which significantly influence the cost of the treatment works. Factors such as strength,
volume, and delivery flow rate characteristics will be  considered  and included to ensure a
proportional allocation of costs to the Federal facility.

     As a minimum, the portion of construction cost allocable to the Federal facility should be
based on the ratio of its total hydraulic requirements, including allowances for future needs, to
the total design flow of the treatment works. The portion (percentage) allocable to the Federal
facility must be agreed upon by the municipality and Federal agency, and approved by EPA,
prior to award of a Step 2  or Step 3 grant, whichever is applicable, for the works or any portion
thereof. See PRM 75-35 for additional detail.

FACILITIES' SITE-RELATED COSTS

Site Acquisition Versus Site Preparation Costs

     All costs associated either directly or indirectly with the acquisition of any land used for or
incidental to the construction of treatment plants, lagoons, force mains, gravity sewers, outfall
lines, appurtenant piping  and structures, and pumping stations—whether by purchase, rental,
lease, or easement-are ineligible. Similarly, all legal, realty, engineering, and grantee costs
associated with such ineligible acquisition are unallowable, as are the costs of easements, rights-
of-way, non-construction-related surveying, plat preparation, meetings, etc.

     NOTE: The cost of land used  as an integral part of the treatment process, such as spray
irrigation sites  (PRM 75-25,  dated July 18,  1975),  may  be eligible if approved and in
accordance  with   pertinent   regulations  and/or  guidelines.  Legal,  administrative,  and
engineering costs associated with the acquisition of grant-eligible land are allowable for grant
participation.

     Costs associated with the preparation of the treatment works site (including appurtenant
features) before, during, and (to the extent agreed upon in the grant agreement or amendment
thereto) after construction are generally eligible. These costs include such items as: grade and
construction-staking surveys; surveying for alignment and slope; and preparation of working
drawings  and plans dealing with site preparation, locations, grades, slopes, distances, depths,
and alignments. Also eligible are costs such as fine-grading, seeding, and protective trees and
shrubs.

     Costs related to reasonable site screening or other  aesthetic purposes are also allowable.
Criteria for participating in  aesthetics-related work include: support  expressed in NEPA-
related studies, approved  facility plans,  and necessary screening of adjacent properties  (when
the facility is in constant public view).

Certificate as to Title to Project Site

     Except in the case of grant-eligible land,  legal costs associated with certifying as  to  the
adequacy  of the grantee's  interest in the project site should be considered a normal function of
government incident to the project, and as such they are unallowable.
                                          D-5

-------
Acquisition of Privately or  Publicly Constructed Waste
Treatment Facilities

    Costs incurred by a grantee or applicant associated with the purchase, lease, or acquisition
of privately or publicly constructed and owned waste treatement facilities are not allowable.

Demolition of Existing Structures

    Demolition of existing structures constitutes an allowable cost provided that the structures
are on the facility site (including rights-of-way for the eligible sewer lines) and that construction
cannot be undertaken without such demolition. Offsite demolition is unallowable. Aesthetics-
related demolition is allowable only if it conforms to the criteria relating to the allowability of
site preparation outlined above.

    If demolition of existing structures  is required on a site not previously owned by the
grantee,  the grantee must  address  such  demolition  in  the  cost-effective  analysis  and
demonstrate to the satisfaction of the Regional Office that  in choosing the site appropriate
consideration was given to the cost of demolition.

Removal, Relocation, and/or Replacement of Utilities

    Costs associated with the removal,  relocation,  and/or replacement  of utilities  (water,
electricity, etc.) are allowable  when such  activity  is  incident to and  necessary for the
construction of the eligible facility. However, participation  in the cost  of replacing existing
utilities with utilities having a greater capacity than those originally in place can only be allowed
if mandated by local, state, or Federal codes,  ordinances, or statutes. If a mandate for greater
capacity does not exist, any additional cost must be borne by the grantee.

    The provision of new or increased  utility service  when  required for the facility  (e.g.,
construction of a new facility or increased capacity)  being constructed is an allowable cost
provided  that the grantee (utility customer) would ordinarily be required  to pay for  such
installation.

Restoration of Streets and Rights-of-Way

    The cost of restoring streets and/or rights-of-way to their original condition is an allowable
cost if the need for such restoration results directly from the construction of the eligible project.
Allowable restoration may include, for example: refilling and patching of street and roadway
surfaces (generally limited to the width of the trench), fine-grading and reseeding of off-street
rights-of-way, reasonable tree plantings, and restoration of sidewalks.

EQUIPMENT, TOOLS, PARTS, AND SUPPLIES

    In accordance with 40  CFR 30.810,  the  grantee  is required to  maintain property
accountability on all equipment, tools, parts, and supplies purchased under the project.

Mobile Equipment

    Generally,  such equipment is allowable if it is  identified by the grantee, approved in
advance  of purchase by the Regional  Office,  and directly  necessary for the operation and/or
maintenance of the overall waste-water treatment facility.  Such equipment must be necessary
for the transmission of waste water or sludge or for the maintenance of plant grounds and/or
equipment. Allowable items include but are not limited to:
                                          D-6

-------
          a.   Portable standby generators.

          b.   Large portable emergency pumps to provide "pump-around" capability in the
event of pump station failure or pipeline breaks.

          c.   Sludge tanks and trailers and other necessary transport and handling equipment
in those cases where the location of the ultimate sludge disposal site requires such equipment.
However, cars and trucks are unallowable except for specialized sludge-handling or transport
equipment.

          d.   Grounds and building maintenance apparatus. Such apparatus may include, for
example, mowers and snow removal equipment (in certain geographic areas). Regional Offices
may use such criteria as cost effectiveness,  potential  for abuse,  and frequency  of use in
considering allowability. Requests for participation  based upon less than 100-percent  use
should be agreed to only in special situations and prorated accordingly.

Office Equipment and Furnishings

     Such items as identified by the grantee and approved in advance by the Regional Office,
when installed or located at the treatment works and necessary to the administrative and/or
technical (including training and meetings) functioning of the works, may be allowable.  In
larger  facilities,  allowability  may be extended  to reasonable special-purpose rooms and
equipment related to the function of the facility. There may well be instances in which the
Regional Office  will need to exercise judgment, as in  the case of "luxurious furnishings,"
televisions, etc.

Shop Furnishings

     Reasonable  furnishings for  shop areas  such as  shelves, bins, and  workbenches  are
allowable costs.

Laboratory Equipment and Supplies

     Generally, laboratory items are allowable if identified by the grantee and approved prior to
procurement by the Regional Office as necessary to conduct tests required for plant operation.
In addition, the  cost of a reasonable inventory of chemicals and supplies necessary to start
operation of the  plant is allowable. An EPA publication,  "Estimating Laboratory Needs for
Municipal Wastewater Treatment Facilities," discusses equipment needed for various size
plants.

Safety Equipment

     Based upon the specific needs of individual  facilities, necessary  and  reasonable safety
equipment is  an allowable cost. Generally,  such equipment  should be delineated in  the
operation and maintenance manual; the approval of that  document may constitute the basis for
EPA's participaton.

NOTE: Such  equipment should meet applicable  Federal, state, local, and industry safety
regulations and standards.

Tools

     Allowable tools are only those which are specified  as special-purpose tools necessary for
                                         D-7

-------
the  repair  and   adjustment  of  specific  process  components  by  the  equipment
suppliers/manufacturers or approved by the Regional Office. All other tools are unallowable.

Replacement Parts

    Replacement parts identified and approved in advance by the Regional Office as necessary
to assure uninterrupted operation of the facility may be included as allowable costs. Allowable
replacement items are only those which constitute parts of major systems  components and
which are: (1) not immediately available and/or whose procurement involves an extended "lead
time," (2) identified as critical by the equipment supplier(s), or (3) critical but not included in
the inventory provided by the equipment supplier(s).  In those instances  where  adequate
"backup" components are built into the system, a reduction in replacement parts should be
made.

    Items  of routine  "programmed" maintenance such  as  ordinary  piping, air filters,
couplings, hoses, and bolts are unallowable. See the EPA Technical Bulletin,  "Design Criteria
for Mechanical, Electric  and Fluid  System  and Component Reliability," for additional
discussion.

Collection-System Maintenance Equipment

    EPA will participate in the cost of  collection-system maintenance when the grantee
demonstrates'that the equipment:

               (1) Is needed  frequently;

               (2) Is necessary to preclude the discharge or bypassing of raw  sewage; or

               (3) Is necessary to provide for the health, safety, and welfare of the citizens.

Such equipment must be reasonable and approved by the Regional Office.

    EPA participation in the cost of such  equipment  purchased in connection  with  a
construction grant shall be based upon a proration of the portion of the collection system in
which EPA participates to the total system. Thus, if EPA participates in 65 percent of the
grantee's total collection system, the allowable costs shall constitute 65 percent  of the cost of
such equipment purchases pursuant to the grant agreement. Generally, the proration should be
based upon the relative lengths of the new to the total system rather than cost or size.

Project Inspection

    Costs  associated with technical  inspections  of the eligible project before  and during
construction (including time extensions approved by  change order) are allowable Such costs
must be clearly documented, and to avoid double payment, the work must not be incident to a
general  contractual obligation.

Ground-Water-Monitoring Facilities

    Costs  associated with  the  construction  of  ground-water-monitoring equipment and
facilities may be considered allowable only in those cases in which, as a direct result of project
construction; the possibility of ground-water deterioration, depletion, or modification exists.
Allowability may not be extended to the operation, surveillance, and/or analyses associated
with these facilities. Such facilities require the prior approval of the Regional Office,
                                         D-8

-------
Biological "Seeding"

    Under certain conditions (climatic, geographic, nature of wastes, etc.), reasonable costs
associated with the purchase and/or transportation of biological seeding materials required for
initiating (or expediting the initiation of) the treatment process operation are allowable.

SUBAGREEMENT COSTS

    The following requirements are mandated under P.L. 84—660, P.L. 92-500, and EPA
regulations 40 CFR 30.800 and 30.805.

Service Charges

    Service charges are defined as any supplemental charges added to other direct costs
(nonsalary) which are claimed on an actual cost basis. Regardless of contract terms, the actual
cost of service charges must be supported by accounting records. If the service charges are not
supported or if the actual cost is less than the amount claimed, the total or the difference is
unallowable for Federal participation. This is in accordance with the ASCE manual, which
states that the service charge is for expenses to be reimbursed by the client.

Fringe Benefits

    Regardless of contract  terms, the actual cost of fringe benefits must  be supported by
accounting records when they are claimed as a direct charge. If the charges are not supported or
if the  actual cost is less than  the amount claimed, the total or the difference is unallowable for
Federal participation. Where the fringe benefits are claimed as a direct charge and also included
in the multiplier, the duplicate direct charge is unallowable for Federal participation.

Labor Charges and Related Costs

    Regardless of contract terms, where charges have been made to the grant and there was no
cost incurred, the charges should be questioned. Labor charges and related costs  for straight
time or overtime hours which  are billed but for which cost has not been  incurred  will be
unallowable for Federal participation. (Compensatory time will be considered in determining
actual labor costs incurred. However, compensatory time is allowable only if it is  incurred in
accordance with established company policy, if it is properly controlled and accounted for, and
if it is  used within an annual accounting period.)
                                         D-9

-------

-------
                                                                 APPENDIX E
         CONSULTING ENGINEER  SUBAGREEMENTS--RECORDS
                               SUBJECT TO AUDIT
                                  Method  of Compensation (1)

                      Percent of         Salary         Time and        Cost Plus          Firm
Type of Records       Construction Cost     Cost Plus        Materials          Fixed            Fixed
                    (ASCE Curve)      Multiplier        (Per Diem)          Fee            Price
      (2)                  (3)              (4)              (5)              (6)             (7)

Category A: Technical
and professional
project records               Yes            Yes             Yes            Yes            Yes
Category B: Financial
records of direct
costs for the
services performed            No             Yes             Yes            Yes            No
Category C: Financial
records pertaining to
profit and overhead           No              No              No             Yes            No

Notes:

          (1) An engineering subagreement may provide for more than one  method of
compensation based on the  different services provided. Records  under each  method of
compensation under a  subagreement are subject to audit individually in accordance with the
guidance provided in Appendix D to Subpart E of 40 CFR 35, paragraph A.2.d. In addition,
under agreements covering both grant-eligible and ineligible work, access to records will be
exercised to the extent necessary to allocate contract work or costs between work eligible for
Title  II construction grant assistance and work or costs  which are ineligible  (Appendix D,
paragraph A.2.c).

          (2) Where there is an indication of fraud, gross abuse, or corrupt practices, EPA will
exercise its right of access to records in all categories (Appendix D, paragraph A.2.b).

          (3) Agreements based upon a percentage of construction cost. Category B and C
records will not be audited. However, terms of the agreement, including the total amount of
compensation, will be  evaluated for fairness, reasonableness, and consistency with historical
and advisory guidelines in general use and acceptable locally (such as ASCE Manual 45 or other
analyses or data relied upon or utilized by the  contracting parties in negotiation  of the
agreement). Such evaluation shall also consider comparable contracts for which EPA grants
have been awarded (Appendix D, paragraph A.2.b(l)).

     Total allowable fees under percentage-of-construction-cost type contracts are conditioned
by the following (Appendix D,  paragraph B.5):

                     (a)  Applying the accepted fee rate to the low bid where design work
(Step 2) is essentially continuous from start of design to bid opening (Step 3) and bid opening
occurs within a year of design completion;
                                          E-l

-------
                     (b)  Where  design  work is not continuous from start of design to
bidding or one year or more elapses between substantial Step 2 completion and bid opening, the
total allowable contract costs may not exceed the lower of:

                           1. The consulting engineer's construction cost estimate provided
at the time of such substantial completion plus an escalation of this construction cost estimate
of up to five percent, but not to exceed the consulting engineer's total compensation based on
the low bid for construction; or

                           2. The consulting engineer's construction cost estimate provided
at the time of such substantial completion plus a consulting engineer's compensation escalation
not to exceed either $50,000 or the consulting engineer's total compensation based upon the low
bid for construction.

                     (c)  Where the low bid for construction would have resulted in a higher
consulting engineer's total compensation than provided in paragraph B.S.b of Appendix D, the
Regional Administrator may also consider a reasonable additional compensation for updating
the plans and specifications, revising cost estimates, or similar services.

          (4) Agreements based upon salary cost times a multiplier, including profit. Category
A and B records will be audited. Category C records will not be audited. However, terms of the
agreement, including the total amount of compensation and the multiplier, will be evaluated for
fairness, reasonableness, and consistency with historical and  advisory guidelines in general use
and acceptable locally (such as ASCE Manual 45 or other analyses  or data  relied upon or
utilized by the contracting parties in negotiation of the agreement). Such evaluation shall also
consider comparable contracts for which EPA grants gave been awarded. Items of overhead or
other indirect  costs  will only be audited to the extent necessary to assure that types of costs
found both in overhead and reimbursable direct costs, if any, are properly charged (Appendix
D, paragraph A.2.b(2)).

          (5)  Time and materials (per diem) agreements.  Category C records will  not be
audited. Category A and B records will be audited to the extent necessary to  determine that
hours claimed and classes or personnel used were properly supported.  The per  diem rates will
be evaluated in accordance  with  appropriate portions  of paragraphs A.2.b(l) and (2) of
Appendix D. (See Appendix D, paragraph A.2.b(3).)

          (6)  Cost  plus a fixed fee (profit). All direct costs and overhead and other indirect
costs claimed  will be audited to determine that they  are reasonable, allowable, and properly
supported by the consulting engineer's records. The amount  of fixed fee will not be questioned
unless the total  compensation appears unreasonable when evaluated  in  accordance with
paragraphs A.2.b(l) and (2) of Appendix D. (See Appendix D, paragraph A.2.b(4).)

          (7)  Firm-fixed-price (lump sum) contracts. Category B and C records will not be
audited.  The contract amount will not be questioned unless the total compensation appears
unreasonable when evaluated in accordance with appropriate portions of paragraphs A.2.b(l)
and (2)  of Appendix D.  (See Appendix D, paragraph A.2.b(5).)
                                         E-2

-------
                                                                APPENDIX F
       CONSULTING  ENGINEER  SUBAGREEMENTS--ALLOWABLE
                       METHODS  OF COMPENSATION
                              Method of Compensation


                     Percent of        Salary          Time and        Cost Plus          Firm
Date of Grant         Construction Cost     Cost Plus        Materials          Fixed            Fixed
Award	          (ASCE Curve)      Multiplier       (Per Diem)          Fee            Price


Prior to July 1, 1975--all
grant steps                 Yes            Yes             Yes            Yes            Yes

July 1, 1975, through
March 1, 1976
Step 1
Step 2
Step 3
After March 1, 1976
Step 1
Step I
Step 3
No (1)
No (2)
Yes (3)

No (1)
No (2)
No (4)
No (1)
No (2)
Yes (3)

No (1)
No (2)
No (4)
Yes
Yes
Yes

Yes (5)
Yes (5)
Yes (5)
Yes
Yes
Yes

Yes
Yes
Yes
Yes
Yes
Yes

Yes
Yes
Yes
Notes:

          (1)   This method of compensation is unallowable unless  "work was initiated"
before July 1, 1975 (Appendix D, paragraph B.I). The definition of "work initiated" for Step 1
is as follows (40 CFR 35.905-4):

               (a)    Prior to November 1,  1974: the execution of a  subagreement for any
element of Step 1 project work; issuance of a notice to proceed; or a work order for Step 1 work.

               (b)    Subsequent to October 31, 1974: the date of approval of a plan of study.

In addition, this  method  of compensation will not  be questioned when  remimbursed in
conjunction with a Step 3 award for work within the scope of Step 2 work "contracted for"
prior  to July 1,  1975 (Appendix D,  paragraph B.2.).  Note the  words "contracted for" as
opposed to "grant  award." In  this  context, "contracted for"  relates to  the engineering
subagreement.

          (2)   This method of compensation is unallowable unless  "work was initiated"
before July 1, 1975. The definition of "work initiated" for Step 2 is as follows:

               (a) Prior to November 1, 1974: the execution of a subagreement for plans and
specifications; issuance of a notice to proceed; or a work order for Step 2 work.

               (b) Subsequent to October 31, 1974: the date of approval of facilities plans.

    In addition, this method of compensation will not be questioned when reimbursed in
conjunction with a Step 3 award for work within the scope of Step 1 and 2 work contracted for
prior to July 1, 1975.
                                         F-l

-------
          (3) Although Appendix D is silent on Step 3 grants awarded during this period, the
Headquarters Grants Administration Division (GAD), in a memorandum to Region IX dated
August 18, 1976, provided the following guidance:

    Neither  PG  53 nor  Appendix  D  requires the renegotiation  of Step  3  engineering
    agreements, even if they are of the types prohibited under 35.937-1.

    While EPA does not require this renegotiation, there is nothing  to prevent a grantee or
    state from requiring renegotiation if it desires to do so.

          (4) Multiplier agreements are not allowable except for subagreements executed prior
to March 1,  1976, which  cover  more than one step (40 CFR 35.937-11).  However, such
agreements are subject to the requirement that the subagreements may have to be renegotiated
to either the cost-plus-fixed-fee or firm-fixed-price method of compensation prior to the grant
award  action for the next  step  (Appendix  D,  paragraph B.6).  Headquarters  GAD's
memorandum to Region IX dated August 18, 1976, provided further guidance in this regard:

    Under the provisions of 35.937-11, Appendix  D is applicable to  all existing engineering
    agreements for which grants are awarded on or after March 1, 1976. Therefore, for Step 3
    grants awarded after March 1, renegotiation of such contracts is not required (presuming
    of course that the Step 2 work was initiated before June 30,  1975).

The definition of "initiation of work" is provided in Note 2 above.

          (5) 40 CFR 35.937-1 (e) provides certain restrictions on the use of time and material
subagreements when the amount is expected to exceed $10,000.
                                         F-2

-------
                                                          APPENDIX  G
              CONSULTING ENGINEER SUBAGREEMENTS
                <=1TRTECT TO 40 CFR  35.937-5, -6. AND -7
      (NEGOTIATION AND SUBMISSION OF EPA FORM  5700-41)
                  Date of Grant Award                 Applicability

                  Prior to March 1,  1976               No

                  March 1,  1976, to  June 30, 1976      Yes (1) and  (2)

                  After June 30, 1976                  Yes (1)
Notes:
         (1)  Subagreements executed prior to March 1, 1976, which cover more than one
step may be exempted until the next step is awarded (40 CFR 35.937-11). The exemption does
not apply to Step 2 work initiated after June 30, 1975 (40 CFR 35, Subpart E, Appendix D,
paragraphs B.3 and B.6). Nor does it apply to Step 3 grants where the Step 2 work was initiated
after June 30, 1975. (See Headquarters Grants Administration Division's memorandum dated
August 18,1976.)

         (2)   For grant applications submitted between December 17, 1975, and February
28, 1976,  the subagreements are not exempted subject to Note 1 above. Grant applications
submitted prior to December  17, 1975, may be  exempted. (See  Alm/Breidenbach Class
Deviation dated May 11,1976.)
                                     G-l

-------

-------
                                                                            APPENDIX  H
                        INTERPOLATION  OF  FEE PERCENTAGE
     When construction costs, or other bases of compensation, fall between two known points on the fee curve, it is
necessary to use interpolation to arrive at the applicable fee percentage. Most engineering agreements specify the use
of straight-line interpolation between points.,In the absence of a specified method of interpolation, the use of the
straight-line method will result in a slightly higher, but insignificantly different, amount of allowable costs. An
explanation of straight-line interpolation follows:

Audit Question:   What percent design fee corresponds to construction costs of $9,750,000?

                                                           Construction Cost           Fee Percentage

    Lower Limit                                           $5,000,000                    6.42%
    Upper Limit                                           10,000,000                    6.03%

    Absolute Difference                                     $5.000.000                     .39%

    (Above data based on ASCE  1972  Curve "A" (page H-2).)

     The interpolation can be made in either of two directions (from the "bottom up" or from the "top down").
Thus, there are two ways to compute the "incremental difference" (shown below).  Both methods give the same
results. Whichever direction is chosen, the auditor must be sure that he is consistent in the approach.

    Construction Cost                           $9,750,000       Upper  Limit                           $10,000,000
    Lower Limit                                5,000,000  -or-  Construction  Cost                       9,750,000

    Incremental  Difference                       $4,750,000       Incremental  Difference                   $250,000

     The interpolation may be expressed in ratio form, for each of the two methods above, as follows:

    (Incremental Cost Difference)                   $4,750,000   =   _?	(Incremental Fee Difference)
    (Absolute Cost Difference)                     $5,000,000      .39% (Absolute Fee Difference)

    (Incremental Cost Difference)                     $250.000   =   2	 (Incremental Fee Differ   a)
    (Absolute Cost Difference)                     $5,000,000      .39% (Absolute Fee  Difference)

    Cross multiplying,  the unknown is solved as shown below:

         (1)  Incremental         = $4.750,000 x .39%     =     $18.525    = ,37%
              Fee difference            $5,000,000                $5,000,000      	


                                  6.42% - .37%  =  6.05%


NOTE:     When method (1) is used (from the "bottom up"), the  result must be deducted  from the higher fee
           percentage.


         (2)  Incremental          =  $250,000  x  .39% =     $975        .Oj%
              Fee difference            $5,000,000         $5,000,000     	
                               6.03% + .02% = 6.05%
                                                      'o
NOTE:   Using method  (2) (from the "top down"),  the  result is added to the lower fee percentage.
                                                H-l

-------
                    Figure H-l

     CURVE A, MEDIAN COMPENSATION FOR
BASIC SERVICES EXPRESSED AS A PERCENTAGE OF
     CONSTRUCTION COST FOR PROJECTS OF
       ABOVE-AVERAGE COMPLEXITY (1971)
    14
    13
    12
    11
    10
  .a  8
















































































































1
\





















\





















\
s
\









III 1 1 1 1 Hill II
Net construction % from
cost Curve A-1971
$100,000
200,000
500,000
1,000,000
5,000,000
10,000,000
50,000,000
100,000,000





>
1
\
\













\













\
'













s





11.63
10.25
8.52
7.53
6.42
6.03
5.70
5.64








•i,
^













--.













— .




1 1










^




...









• ••II




     0.01     0.05 0.1     0.5  1       5  10
               Net construction cost, in millions of dollars

   Source:   ASCE Manual No. 45.
50  100
                       H-2

-------
The total design fee  in this case would  be computed as follows:

$9,750,000 (total construction costs) x 6.05%  =  $589,875.

NOTE:     The design fee percentage would be applied to eligible construcion costs to obtain accepted design costs
            per audit.
                                                  H-3

-------

-------
                                                              APPENDIX  I
                    APPLICATION OF  PARAGRAPH  B.5
               OF APPENDIX  D TO 40 CFR 35, SUBPART E
    The following example is intended to clarify the provisions, and to provide a working
model, of the application of paragraph B.5 (determining total allowable contract costs for grant
payment where work for the design step is not essentially continuous from start of design to
bidding, or one year or more elapses between substantial completion of Step 2 design work and
bid opening for Step 3 construction).

    The provisions of Appendix D are applicable to all existing construction grants, regardless
of statutory authority or date of award. Thus, Appendix D applies to both P.L. 84—660 and
92-500 grants.

1.  COMPUTATION OF ALLOWABLE COST

    Appendix D provides that in no event will allowable costs for a percentage-of-construction
type contract be based on an amount exceeding the low bid for construction. This specifically
excludes the cost of change orders and cost overruns from the computation basis. The method
of computing allowable cost is dependent upon the time between substantial completion
(discussed in paragraph 2 below) of plans and specifications and bid opening.

    A.   Less Than One Year.  If  less  than  one  year   elapses between  substantial
    completion and bid opening, paragraph B.5.a of Appendix D limits allowable cost to the
    amount obtained by applying the applicable fee curve percentage  to the low bid  for
    construction.

    Example:

      Facts
         Substantial completion of design-May 20, 1973
         Bid opening-November 27,  1973

         Low bid                             $5,000,000
         Changes orders                        1,000,000
         Total construction cost                $6,000,000

         Fee curve  at $5,000,000 =  6.42%

          Application

         Low bid                             $5,000,000
         Fee curve  percentage                    x  .0642
         Allowable  fee                         $321,000
                                       1-1

-------
B.    More  Than One Year.  When  one year  or  more  elapses  between  substantial
completion of design and bid opening, paragraph B.5.b limits allowable costs to the lowest
of:

      (1)   The applicable fee curve percentage applied to the total of the consulting
      engineer's construction cost estimate provided at substantial completion of plans and
      specifications plus an escalation of five percent nf the estimate.

      (2)   The applicable, fee curve percentage applied  to  the  consulting engineer's
      construction  cost estimate  provided  at  substantial  completion of plans and
      specifications. A consulting engineer's compensation  escalation of up to $50,000 is
      added to the resultant amount.

      (3)   The applicable fee curve percentage applied to the low bid for construction.

Examples:

  Facts
     Substantial completion of design-June  15,  1972
     Bid opening--Nov. 27, 1973

     Engineer's estimate at substantial
       completion
     Low bid
     Total  construction cost

(1)  Engineer's estimate of construction
      Allowable escalation
      Applicable fee curve percentage
        (interpolated)
(2)  Engineer's estimate of construction
      Applicable fee curve percentage
        (interpolated)

      Engineer's  compensation escalation
(3)  Low bid
      Applicable fee curve  (from curve
        percentage)
$4,000,000

 5,000,000
 6,000,000

$4,000,000
    x 1.05
$4,200,000
   x .0664
  $278,880

$4,000,000

   x .0670
  $268,000
    50.000
  $318,000

$5,000,000

   x .0642
  $321,000
Method (1) above resulted in the lowest compensation; therefore, allowable compensation
in the example would be example (1), or $278,880.
                                     1-2

-------
2.   SUBSTANTIAL  COMPLETION

     No precise definition of "substantial completion" of design has been made within EPA.
Therefore, auditors must apply their judgment to the circumstances of each grant to ascertain
the date of substantial completion. Design is normally substantially complete when no major
additions or revisions are required to complete the plans and specifications.

     Evidence of substantial completion may consist of one or more of the following:

          a. Dates shown on plans or specifications.

          b. Transmittal of plans and specifications from the consultant to the grantee.

          c. Submission of plans and specifications to the state and EPA for review.

          d. Minutes of board meeting in which completed plans are accepted or discussed.

          e. Grant application checklists in which completion date is annotated.

          f. Engineer's billings which show percentage of completion of design.
                                        1-3

-------

-------
                                                                        APPENDIX  J
             EPA DIVISION AUDIT OFFICES AND COGNIZANT
                                 GEOGRAPHIC  AREAS
Address of Cognizant
EPA Division Audit Office

Mr. Juan Soto,  Jr.,  Director
Mid-Atlantic Audit Division
Environmental Protection Agency
Crystal Mall #2, Room 716
Washington, D.C. 20460
(703)  557-7700
Geographic Area

Pennsylvania, Delaware,
Maryland, Virginia,
West Virginia, and
Washington, D.C.
Mr. Kenneth A. Konz, Director
Eastern Audit Division
Environmental Protection Agency
90 Church Street,  Room 802
New York, New York  10007
(212) 264-5730
Maine, Connecticut, New York,
Massachusetts, Rhode Island,
Vermont,  New Hampshire,
New Jersey, Puerto Rico,
and the Virgin Islands
Mr. W.  Rogers Smith, Director
Northern Audit Division
Environmental Protection Agency
1 North Wacker  Drive
Chicago, Illinois  60606
(312) 353-2486

Mr. Truman R.  Beeler,  Director
Western Audit Division
Environmental Protection Agency
215 Fremont  Street
San Francisco, California 94105
(415) 556-1954
Mr. Leslie M. Buie, Director
Southern  Audit Division
Environmental Protection Agency
1371 Peachtree Street,  NE
Atlanta,  Georgia  30309
(404) 881-3623
Ohio, Michigan, Wisconsin,
Minnesota,  Indiana, Illinois,
Iowa, Nebraska, Missouri,
and Kansas
Colorado, Utah, Nevada,
Hawaii, Washington, Oregon,
California,  Idaho, Montana,
Wyoming,  Arizona,
North Dakota,  Alaska,
South Dakota,
Guam, American  Samoa, Trust
Territories of the Pacific
Islands, and Wake Island

Alabama,  North Carolina,
South Carolina, Florida,
Georgia,  Mississippi, Texas,
Arkansas, Tennessee,
Kentucky,  Oklahoma,
New Mexico, and Louisiana
                                             J-l

-------

-------
                                                              APPENDIX  K


                                 REFERENCES

Audit Guide for  EPA Contracts, Environmental  Protection  Agency  (Washington,  D.C.:
February 1976).

Audit Guide for Reviewing Indirect Cost Allocation Plans and Rate Proposals, Environmental
Protection Agency (Washington, D.C.: Publication pending).

Audits of State and Local Governmental Units,  American  Institute of Certified  Public
Accountants (New York: 1974).

Clean Water Act of 1977, Public Law 95-217 (December 27, 1977).

"Construction  and  Architect-Engineer  Contracts,"  Public  Contracts  and   Property
Management, Code of Federal Regulations 41, Subpart 1-15.4 (U.S. Government Printing
Office, Washington, D.C.). Also codified in the Federal Procurement Regulations, Subpart
1-15.4.

Consulting Engineering—A Guide for the Engagement of Engineering Services,  American
Society of Civil Engineers, Manual No. 45 (New York: rev. 1972).

"Contracts with Commercial  Organizations," Public Contracts and Property Mangement,
Code of  Federal  Regulations 41, Subpart  1-15.2  (U.S.  Government  Printing  Office,
Washington, D.C.). Also codified in the Federal Procurement Regulations, Subpart 1-15.2.

"Cost Principles Applicable to Grants  and Contracts with State and Local Governments,"
Federal Management Circular, FMC 74-4, General Services Administration, Office of Federal
Management Policy (July 18,  1974). Also referenced in "Project Costs," Protection of the
Environment, Code of Federal Regulations 40, Subpart F, Section 30.710(a).

Federal Water Pollution Control Act, Public Law 84-660 (July 9, 1956).

Federal Water Pollution Control Act Amendments of 1972, Public Law 92-500 (October 18,
1972).

"General  Grant  Regulations and Procedures;  State  and Local  Assistance-Interim
Regulations," Federal Register, Part III, Vol. 37, No. 112 (Environmental Protection Agency,
Washington, D.C.: June 9, 1972).

"General Grant Regulations and Procedures," Protection of the Environment,, Code of Federal
Regulations 40, Subchapter B,  Part 30 (U.S. Government Printing Office, Washington, D.C.).

"Grant  Programs-Interim  Regulations," Federal Register,  Part  II, Vol. 36, No. 229
(Environmental Protection Agency, Washington, D.C.: November 27, 1971).

Handbook of Procedures-Construction  Grants Program for Municipal Wastewater Treatment
Works, Environmental Protection Agency (Washington, D.C.: February 1976).

Standards for Audit of Governmental Organizations, Programs, Activities, and Functions, U.S.
General Accounting Office (U.S. Government Printing Office, Washington, D.C.: 1972).
                                       K-l

-------
"State and Local Assistance," Protection of the Environment, Code of Federal Regulations 40,
Subchapter B, Part 35 (U.S. Government Printing Office, Washington, D.C.).

"Uniform Administrative Requirements for Grants-in-Aid to State and Local Governments,"
Federal Management Circular, FMC 74-7, General Services Administration, Office of Federal
Management Policy (September 13, 1974).
                                         K-2

                                                  *U.S. GOVERNMENT PRINTING OFFICE :  1978 0-720-335/6103

-------