-------
As the table shows, increasing the bond maturity to 30 years
would decrease annual payments by 12%, but it would increase
the total debt service by almost $440 million C20%). With
40-year bonds, the average annual debt service would be
reduced by 20%, but total debt service would increase by
47%, or more than $920 million.
5.2.4.8 A Worst Case Analysis
The accuracy of the MFP cost estimates, the level of grant
funding ultimately obtained, and the prevailing interest
rates at the time of bond issues, all have the potential of
altering the forecast fiscal impact of the MFP. As Table
5.46 indicates, the assumptions of the Mosaic Alternative
(MMSD Recommended Plan) include: 1) a $1.66 billion program:
2) 36% grant funding: and 3} all bonds sold (to raise the
non-grant-funded portion) at 6% interest. This worst case
analysis examines the impact of three different deviations
from the assumptions upon which the Mosaic Alternative is
founded. All worst case scenarios assume district-wide financing,
5.2.4.8.1 Worst Case "A"; The sequence of expenditures
needed to implement the $1.6 billion MFP is technically
referred to as the Project Delivery Analysis (PDA). The PDA
is used to establish the annual budget for implementing the
Mosaic Alternative and as a basis for estimating project
design costs. The PDA would be modified during the design
phase as more refined cost estimates become available.
This PDA has an accuracy range of -15% to +30%. In other
words, the cost range of the MFP is $1.4 billion to $2.16
billion. The worst case "A" in Table 5.46 assumes that the
MFP would end up costing 15% more than the PDA estimate of
$1.6 billion. The total cost would, in this case, increase
by $249 million to $1.9 billion.
At the time the Draft EIS was released, the MMSD had anti-
cipated an overall grant funding level of 36%. However,
information that has since become available suggests that
36% may be an overly optimistic estimate. Therefore, the
worst case "A" assumes that the $1.9 billion would be only
25% grant funded.
Recently, interest rates on G. 0. municipal bonds have
exceeded the 6% rate assumed for the Mosaic Alternative.
Therefore, this worst case analysis assumes that the $1.42
billion of needed capital (75% of 1.9 billion) would be
raised with G.O. bonds paying 7.5% interest. This higher
interest rate assumption increases the equalized tax rate by
12%.
5-112
-------
ffl
CrH
•rl >1
•U
0) C
JJ 3
58
X 01
(fl 01
EH y
3
QJJ fO
< 3
&4 rH
§ ''"'
01
4) 0)
JJ 3
(0 01
« 01
H
JJ
01 TJ
01 C
M 0
o) pa
•u
c c
H 0
en
w
tn o>
h3 -rl JJ
*( TJ -H
Z C rH
fTj O
63 (fl
en jj rH
< C -H
M >
W ° *
0
3
^
u
(fl
M
01 3
JJ O
(0 O
E <
•rl
JJ UH
01 O
W
rH
JJ 01
tn >
0 01
U r3
1)
'O JJ
0) (0
N 1-1 E
0) -rl O
OlrH X M
(0 10 (fl UH
M 3 JJ
D tT o in
> 41 >iO O
(0 JJ o o
rH M rH (N
r~ (0 0) I
m 3 Qj in
. C O M co
•» C M 0) on
(fl Qj Q4iH
•
T3 OP
C vD
J2 >,
ifl
a a
en
S tn
S 4)
3
rH 01
rH 01
<-rl
r- •
rH O 'O
(fl . . 01
3 C rH TJ
c o m- c
C-H 3
(fl rH • E
>i o 3
IH o on 01
0 ifl o tn
M m (fl
JJ 3 +
01 O 11
DOOM
U < JJ (0
•O
01
in -a
o e
CO c
O 0
•H O
JJ 01
sac
tn en (0
01 E rH
01
T3 JJ
0) (0
N M E
41 -H o
OlrH X M
(fl [fl (0 U*
M 3 JJ
01 tT o in
> U >iO 0
(0 -POO
rH M rJ OI
O 'O U 1ft- 1
in 3 a in
. C 0 M oo
U3 C M u en
(0 Q4 04 rH
OP •
in E O
T) • o in
C r~ M •
O MH 1C
(0 01
Q Qj 01 01 O
en jj tn JJ
S 01 (0 (fl
£01 MHO
3 M 00
rH 01 X O •
rH 01 (8 C in
jj
C M
(fl 0
M
O* fc £
C o
^~* U e i^
C -H TJ IH
0 rH O)
•H i-H T3 01
rH -rl C 41
rH .Q 3 01
•rl 4H flj .
j3 r«j 41 o
"*** JJ M co
CO . C 0 .
^T rH (fl g if)
• V> M -H «•
W tT1
41 O
M • JJ JJ jJ
O 13 O fl
— DC M r-
T) n
in 3 in a ^
01
01
• (fl IO
C 0) 10
0 M •
-H O rH
rH C
rH -r(
•rl C
X) C (fl
0 J=
cn -H -U
• rH
rH rH M
U>-rl 41
E £ •
4) >iO O
Ifl 4J O O
rH M i-H (N
P» (0 1) 1
in 3 04 in
• C O M co
co c M 41 en
(0 O4 QjrH
E f
fQ OP o in
C oo n .
O 03 Vt-
X! in M
• co 0
vo T3 X JJ
ro 1) M (B
• 13 o EH P«
vt C ^
3 -
M UH C • f
0 O T3 'W*
— JJ -H 0)
C rH 13 E
OP (fl rH C O
in M -H 3 M
,_! O> X! MH IH
C
0
•rl
• O. rH
C < r-i
O 04 -H IO
•H g E y=
rH 00 rH
•H C en
J3 (0 •»
r; {/> *_i
vo JJ 1)
rH 10 >
• M O
01 1) -
Xi 4) 1) •
JJ tn c
O -rl (0 (0 O
x; E oi -ri
JJ -H M rH
01 OP JJ O rH
00 01 C -H
U n 01 -H A
tn
c
o
- -H
s a
jj g
tn 01 3
M 01 01
O (fl 01
3 U <
1)
"O JJ
1) (0
01 N M E
Ol-rl O
(fl rH X M
M (0 Ifl UH
0) 3 JJ
> tT o in
(0 41 >i O O
JJ O O
U3 rH M rH CM
co to i -H M
(fl IH o
Q 04 41 4-1
en jj oi •
S 01 (0 11 rH VO
S 11 M 01 !N CO
3 (fl • •
rH 01 X 01 0 01
rH 01 Ifl M rH rH
<; -H E-I o
C
0 E
•H 0
rH M
rH MH
•rl
XI 01
01
in T3 tn •
• 01 (fl rH
01 TJ 01 01
to- C M •
3 O 0
>*H C rH
•rl V>
•a jj
01 C CD 0
^ (fl jj jj
CM (0
3 O> M r-
m (*">
JJ X •
OP O 10 T
O C EH in-
• 04
c «c
0 B<
•rl 3
rH £ VO O •
rH IO ^T 11
•rt C • 00 01
XI (0 rH W- (fl
J3 «• 01
in JJ CM
MH < O
01 M O C
«• 0) -H
A 01 •
"JH OlJJ C C
o -H (0 o o
r"* g .,H -iH
JJ -rl rH rH
01 Of JJ rH rH
O O 01 -rl -H
U in ai A 6
01
C
0
S -rl
CJ JJ
' I1
01 11 3
M 01 01
O (0 tn
S U <
tjl
c
• H
O
c
(0
c
0)
•o
•rH
3
JJ
o
•H
M
Jj
01
•rl
Q
3
01
01
(fl
Ifl
5-113
-------
The estimated cumulative effect of the above assumptions is
a 49% increase in the Milwaukee County tax rate. That is,
while the assumptions in the Mosaic Alternative lead to an
average annual equalized tax rate of $4.37 for district-wide
financing, the assumptions outlined in the worst case "A"
lead to $6.50 per $1,000.
5.2.4.8.2 Worst Case "B"t The worst case "B" assumes that
the $1.6 billion estimate is 30% lower than what the final
cost would be Cin 3.980 dollars}. This assumption causes the
$1.66 billion to increase by $498 million to $2.16 billion.
In addition, grant funding is assumed to be 15%.
With these two assumptions, the entire $1.8 billion would
have to be raised locally. Bonding $1.8 billion at 6% would
result in an average annual tax rate of $7.35/$l,000.
However, if bond issues are assumed to average 8%, the tax
rate would increase an additional 16% to $8.57/$l,000.
In summary, the worst case "B" analysis, including a project
cost increase of 30%, 15% grant funding, and 8% interest on
MMSD bonds, would cause the Milwaukee County property tax
rate for the MFP to increase 96% over the tax rate associated
with the Mosaic Alternative, from $4.37 to $8.57/$l,000.
5.2.4.8.3 Worst Case "C": Worst case "C" assumes that the
capital cost of the MFP would be 50% higher than the estimated
$1.66 billion and that no grant funding would be available
during implementation of the program. If the $2.5 billion
would be debt financed with 20-year G.O. bonds at 9% by
Milwaukee County, the average annual equalized County tax
rate would be $12.86 per $1,000.
With implementation of the MFP, the 1985-2005 average annual
equalized Milwaukee County property tax rate would likely be
between $4.37 and $12.86 per $1,000, depending upon which of
the possible combinations of cost estimates, funding levels,
and interest rates ultimately occur.
5.2.4.9 Fiscal Impacts of CSO
The MMSD Recommended Plan assumes that all capital costs of
the MFP would be spread district-wide, and that all operation
and maintenance costs would be distributed through the User
Charge Program. Since the CSO program is part of the MFP,
all CSO-related capital and O&M costs are assumed to be
shared district-wide.
However, the costs of some MFP projects have more priority
on the Wisconsin Project Priority List than CSO abatement,
5-114
-------
and the cost of implementing the MFP would exceed the $60
million per year ceiling for federal and state grants during
most years. Therefore, grant funds would not be available
for CSO abatement. The effect on the property tax rate
produced by different CSO solutions can be predicted by
applying the percentage differences in cost among alternatives
to the tax rate. For example, given that a $1,064 billion
alternative (Mosaic), would result in a $4.37 per $1,000 tax
rate, then a $1.098 billion solution, which is a 3.2% increase,
would result in a $4.51/$1,000 tax rate Csee Table 5.47).
Assuming the continuation of the current contract formula,
costs to communities outside of Milwaukee County would also
increase, but not as much as in-County costs. The contract
formula is not as sensitive to changes in MMSD capital
expenditures as the property tax system, because the charges
to contract communities are based on a 2% depreciation of
MMSD assets in place. The contract formula distributes costs
based on a 50-year payback period as opposed to 20-year
bonds in Milwaukee County.
5.2.4.10 Individual Community Financing
On June 5th, 1980, the Milwaukee Metropolitan Sewerage
Commission approved the district-wide financing of all com-
ponents of the MFP. However in the past, all communities
in the MMSD planning area have financed their own local
sewer rehabilitation and relief, CSO abatement, and trunk
sewer connections to the Milwaukee County line. Historically,
the MMSD has financed Metropolitan Intercepting Sewer (MIS)
construction and treatment plant construction or improvement.
District-wide financing of the entire MFP has been con-
troversial. A lawsuit has been filed against the MMSD by 15
suburbs to challenge the legality of district-wide financing.
Due to the uncertain outcome of this lawsuit, the EIS provides
a parallel fiscal impact analysis that assumes the CSO
abatement, local sewer rehabilitation, and trunk sewer
connections to the Milwaukee County line are financed by the
individual communities that own, or would own, the sewers.
This financial arrangement is referred to as the Individual
Community Financing Alternative.
The following assumptions underlie this analysis. These
assumptions are used because they enable the results under
the Individual Community Financing Alternative to be compared
to the District-Wide Financing Alternative.
5-115
-------
TABLE 5.47
FISCAL IMPACTS OF CSO ALTERNATIVES
Alternative
1. Inline
2. CST/Inline
3. Modified
Total Storage
4. Complete
Separation
*Costs in thousands
Source: ESEI
Total Initial
MWPAP Capital:
Local Share*
$1 ,064 ,005
1,074,535
1,088,085
1,097,925
Average Annual Burden
Percent Annual to a $50,000
Increase Tax Rate Home in Milwaukee
Base
1%
2 . 3%
3.2%
$4.37
4. 41
4.47
4. 51
218
220
223
225
5-116
-------
1.) Each community would finance its own sewer rehabilitation
and relief with. 20-year G.O. bonds at 7% interest.
2.1 Each community joining the MMSD would finance its own
connecting trunk sewer with 20-year bonds at 7% interest.
3.) Both the City of Milwaukee and Shorewood would finance
their own costs for CSO abatement with 20-year bonds at
7% interest. CSO costs include only CSO components,
not interceptor and relief components.
4.) All program elements not identified in 1, 2, or 3 above
would be financed district-wide with 20-year G.O. bonds
issued by Milwaukee County at 6% interest. The debt
service would be recovered by the existing contract
formula and the Milwaukee County ad valorem property
tax.
5.) Grant funding would be distributed proportionally among
all program elements (e.g., CSO abatement, interceptors,
or WWTP upgrading and expansion), regardless of which
municipality assumes the financing.
Table 5.48 compares the average annual debt service of indi-
vidual community financing with district-wide financing. Table
5.49 compares average tax rates. Major differences observed be-
tween the two methods of financing are discussed below:
1.) Average annual costs to the City of Milwaukee and the
Village of Shorewood would be lower under the District-
Wide Financing Alternative. Costs of the City of Milwaukee
would decrease 30%; Shorewood's by 24%. This decrease
would occur because, with district-wide financing,
about $400 million for CSO abatement in these two
municipalities would be distributed to all planning
area communities.
2.) The average annual costs to each of the remaining MMSD
communities within Milwaukee County would increase under
the District-Wide Financing Alternative (relative to
the Individual Community Financing Alternative). This
increase would occur because these communities would
share the costs of CSO abatement in the City Milwaukee
and Shorewood.
3.) However, when all the average annual costs for Milwaukee
County communities from 1985-2005 are totaled, the sum
for the District-Wide Financing Alternative would be
less than the sum for the Individual Community Financing
Alternative. The bond interest rate for the District-
Wide Financing Alternative is assumed to be 6%, whereas
5-117
-------
TABLE 5 .48
INDIVIDUAL COMMUNITY FINANCING VS. DISTRICT-WIDE FINANCING"1
1985 - 2005 AVERAGE ANNUAL DEBT SERVICE
MILWAUKEE
COUNTY
COMMUNITIES
Bay side
Brown Deer
Cudahy
Fox Point
Franklin
Glendale
Greendale
Greenfield
Hales Corners
Milwaukee
Oak Creek
River Hills
St. Francis
Shorewood
Wauwatosa-
West Allis
West Milwaukee
Whitefish Bay
Subtotal
INDIVIDUAL
COMMUNITY™
FINANCING
$ 467
905
1,281
922
985
1,773
1,188
1,871
474
59,578
1,563
259
513
1,965
4,256
4,460
652
1,214
$ 84,326
DISTRICT-
WIDE ,
FINANCING
$ 732
1,502
1,926
1,216
1,675
3,032
2,039
3,149
786
41,694
2,685
406
786
1,495
6,721
6,216
1,075
1,880
$ 79,015
PERCENTAGE
CHANGE
FROM 1 TO 2
57%
66
50
32
70
71
72
68
66
-30
72
57
53
-24
58
39
65
55
-6%
CONTRACT COMMUNITIES
Brookf ield
Butler
Caddy Vista
Elm Grove
German town
Menomonee Falls
Mequon
Muskego
New Berlin
Thiensville
Subtotal
$ 487
113
47
230
761
989
769
574
1,223
164
$ 5,431
$ 750
181
36
341
684
1,580
1.114
583
1,646
192
$ 7,107
54%
60
-23
48
-10
60
28
2
35
17
31%
All costs in thousands.
Column 1 is derived from Table 4, Column 5.
Column 2 is derived from Table 51, Appendix X.
Source: MMSD and ESEI
5-113
-------
TABLE 5.49
INDIVIDUAL COMMUNITY FINANCING VS. DISTRICT-WIDE FINANCING:
1985 - 2005 AVERAGE ANNUAL EQUALIZED TAX RATES1
MILWAUKEE
COUNTY
COMMUNITIES
Bayside
Brown Deer
Cudahy
Fox Point
Franklin
Glendale
Greendale
Greenfield
Hales Corners
Milwaukee
Oak Creek
River Hills
St. Francis
Shorewood
Wauwatosa
West Allis
West Milwaukee
Whitefish Bay
SEWER ,
REHABILITATION
.24/$1000
.15
.42
.55
.08
.08
.05
.10
.13
.31
.07
.03
.37
.16
.26
.63
.14
.32
TRUNK
SEWER
CONNECTORS
/$1000
CONTRACT COMMUNITIES
Brookfield^
Butler
Caddy Vista
Elm Grove
Germantown
Menomonee Falls
Mequon
Muskego
New Berlin
Thiensville
.03
.05
.08
.04
.04
.04
.03
.03
.20
1.63
1.13
.30
.57
.20
.30
cso
3,4
ABATEMENT
MMSD
CHARGES
/$1000 2.50/$1000
3.42
3.08
50
50
50
50
50
50
50
50
50
50
2.50
,50
.50
,50
.50
2.50
2.50
COMMUNITY
FINANCING
ALTERNATIVE
TOTAL
2.74/$1000
2.65
2.92
3.05
2.58
2.58
2.55
2.60
2.63
6.23
2.57
2.83
2.87
5.74
2.76
3. 13
2.64
2.82
DISTRICT- WIDE
FINANCING
ALTERNATIVE
TOTAL
4.37/$1000
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
4.37
36
39
32
77
35
14
05
.98
1.04
1.24
.39
1.44
2.95
.85
2.52
1.18
1.39
1.58
1.27
1.74
.59
2.28
2.26
1.27
2.22
86
73
1.62
72
03
1All values are expressed in dollars per $1000 of equalized value.
2The tax rates for the contract communities (Brookfield through Thiensville) are based
on all taxable property within the communities (e.g., only 40% of Brookfield1s property
is Tn~the contract area). For commparison purposes only, this table assumes contract
communities would use the property tax to pay the contract charges.
3These rates are subject to change depending on the results of the ongoing Sewer System
Evaluation Survey.
These rates are based upon the Inline Storage Alternative.
Property value estimated.
Source: MMSD and ESEI
5-119
-------
the local bond issues Cfor the Community Financing
Alternative! are assumed to be 7%. As a result, the
average annual debt service Cfrom 1385-20051 with the
Individual Community Financing Alternative would be $84
million as opposed to an average $79 million annually
for the District-Wide Financing Alternative.
4.1 Average annual costs for all MMSD contract communities
Ci.e. outside Milwaukee County!, except Germantown and
Caddy Vista, would be higher with the District-Wide
Financing Alternative than with the Individual Community
Financing Alternative. The cost increase would occur
because these communities would share the cost of CSO
abatement in Milwaukee and Shorewood.
5.} The tax rates for the City of Milwaukee and Shorewood
would decrease with the District-Wide Financing Alternative
from $6.23 and $5.74, respectively, to $4.37.
6.) Except for Germantown and Caddy Vista (discussed above),
tax rates would increase for non-Milwaukee County
communities with the District-Wide Financing Alternative.
Table 5.50 compares the average annual household charges by
community for Milwaukee County communities with the District-Wide
and Individual Community Financing Alternatives. These
household costs are calculated by multiplying either the
assessed tax rate times the average assessed home value or
the equalized tax rate times the average equalized home
value. (Both methods produce the same tax payment.) The
contract communities' cost distribution methods were simulated
to determine the household costs in this table.
The greatest difference between the Individual Community
Financing Alternative and the District-Wide Financing Alternative
is the shifting of CSO abatement costs. Assuming Milwaukee
and Shorewood would finance their own CSO abatement, peak
year (.19901 tax rates would be $7.20 per $1,000 (equalized)
for the City of Milwaukee and $6.65 (equalized) for Shorewood.
These rates incorporate the proportionate funding assumption
discussed above for CSO abatement. If CSO abatement received
no grant funding, these peak tax rates would be $11.25 and
$10.40, respectively. For a more detailed comparison of
these two financing methods, the reader is referred to
Section 2.0 of the Addendum to Appendix X, Fiscal/Economic
Impacts.
5.2.4.11 Other Methods of Distributing Project Costs
As mentioned previously, there are other methods that could
be used to distribute project costs. A use-based system
5-120
-------
TABLE 5.50
INDIVIDUAL COMMUNITY FINANCING AND DISTRICT-WIDE FINANCING
COMPARED TO NET PROPERTY TAXES:
1935 - 2005 AVERAGE ANNUAL HOUSEHOLD CHARGES
MILWAUKEE
COUNTY
COMMUNITIES
COMMUNITY
FINANCING
ALTERNATIVE
Bayside $315
Brown Deer 164
Cudahy 150
Fox Point 334
Franklin 177
Glendale 194
Greendale 201
Greenfield 160
Hales Corners 178
Milwaukee 249
Oak Creek 149
River Hills 450
St. Francis 136
Shorewood 491
Wauwatosa 193
West Allis 191
West Milwaukee 133
Whitefish Bay 2 254
CONTRACT COMMUNITIES
Brookfield86
Butler 25
Caddy Vista 126
Elm Grove 92
Germantown 106
Menomonee Falls 79
Mequon 95
Muskego 104
New Berlin 79
Thiensville 99
DISTRICT-WIDE
FINANCING
ALTERNATIVE
$503
271
225
478
299
328
354
269
295
175
253
695
208
374
306
267
221
393
131
39
96
137
95
126
122
105
106
116
1981
AVERAGE
NET
PROPERTY TAX1
$2,347
1,457
1,172
2,376
1,505
1,457
1,872
1,351
1,553
1,103
1,032
3,870
1,234
2,217
1,568
1,558
1,179
2,138
1,716
1,056
N/A
2,200.,
1,382
1,443
1,853
1,132
1,360
1,517
This figure is derived from the 1981 Net Tax Rates in the
Citizens Government Research Bureau, Bulletin, March 7, 1981
and updated property values in Table 20 of Appendix X.
2
This table assumes the contract communities would use their
present methods of cost apportionment.
1980 Average Net Property Tax
N/A: Not Available.
Source: MMSD and ESEI
5-121
-------
could be implemented, by which, each community would pay
according to the percentage of the total flow they contribute
to the MMSD. Another form of cost apportionment would be
the ad valorem taxation of all property served by the sewer
system, regardless of jurisdictional boundaries. The costs
to the communities in the planning area under the use-based
or service area tax systems are compared to present distribution
methods in Table 5.51. The assumptions used to determine
these costs are listed in Table 5.52.
A use-based distribution of MFP costs would result in an
average increase of charges to contract communities of 8%
over the charges associated with the Mosaic Alternative. In
addition, the charges to some Milwaukee County communities
would increase even more dramatically: Cudahy by 45%;
Milwaukee by 20%; Oak Creek by 44%; St. Francis by 19%; and
West Milwaukee by 113%. Although these communities have
relatively low property values, they contribute large amounts
of wastewater, which accounts for their increased costs.
The costs to the 13 remaining Milwaukee County communities
would be reduced from the costs associated with the Mosaic
Alternative. This reduction would range from 16% to 66%.
These communities have relatively higher property values and
would pay more if costs are distributed by ad valorem property
taxation.
If the MFP costs are distributed by an ad valorem tax of all
property in the entire MMSD sewer service area, the costs to
suburbs outside Milwaukee County would increase an average
of 94% over the charges imposed by the current MMSD Contract
Formula. At the same time, charges to communities in Milwaukee
County would decrease an average of 8%.
5.2.4.12 The EPA Preferred Alternative
Should the U.S. Supreme Court decide that the CSO abatement
facilities need not be designed for the worst storm on
record Ca 40-year recurrence interval), the MMSD would have
to comply with the DNR Stipulation Csee Chapter 2).
The DNR Stipulation states that if Federal and/or State
financial assistance is not available, the Sewerage Commission
must spend $13 million annually in 1976 dollars C$20.3
million in 1980 dollars! between 1983 and 1996 toward the
CSO abatement project. After 1996, the Sewerage Commission
must continue to spend the 1996 dollar equivalent of $13
million in 1976 dollars. This amount would not have to
be adjusted for inflation after 1996. Because of the very
low position of the CSO project on the State priority list,
it is very likely that the CSO abatement would have to be
financed entirely with local funds.
5-122
-------
CB ^.
01 H
c •—
fB
g §
SH
dt? HH
I H I + + I CN
I I i
I++I++I I I IJ+I I I I
M-l cfl
°S
co CN H r- vo
r-i o vo PI o
r-
CN H rH
rH r-- in CM
CN vo H o
nfN'S'rHroCM
o
o
in
OQ
0)
jj
0)
U3
>-v
m
'*"••''
EH
W
13
o
M
EH
Si
O
CM
— 4
^
EH
0
o
Pa
o
W
Q
0
ffi
EH
W
S
H
«c
5*°
(?
H
EH
£*•<
m a
SH CD O X
d) rl M (D
cn «C cu EH
Cn H
G *-'
rfl
U 0
SH
dP fu
r-H
VH a)
O 4-1
0
dP £H
^
tn
ffl
U
^ 0
CN rH
-- PH
, — {
M-l (fl
O 4-J
O
* EH
•o o
CIJ O
Q "O O
CO G rH
S CD
o c
^» o fd
H 0) H
*—* PH P|
ro n d CN
iHr-liHH fNH(N POr-IOOi-lrNCN rHO VOID
ro iJ
in
in
co o
cnvoinr—icncNcoocNPicnoo
r- vo r» CN CM
cocNvocT>picnrH^ip)inot~-ocnvOPir~-cNCnvor~-cocMCTirH IOCNVOCNCMCO
co co
CN
rH ^1* P)
CN O CN
cn
PI
cn
CN r~ vo rH pi cn
in PI vO cn co CN
CO rH CN
vo cn rH
cn
in CN
i 0 0
tn
•rl
CU 4-1
ceo
•rl -rl 4-1
>i in 0 rH c
rH T3 a
i x; o cn ^
G
(T)
4-1 13 H3 g X
(fl!HSH3
0)
0)
tn tn
H -H
i
M a
v «
tn us
•rl 3 4=
tn
i-H H
O rH -rl -H
4J
3 tn tn
10 CU CU
S 3 S S
I
rH
•H
S
tn
4-)
5-123
-------
TABLE 5.52
ASSUMPTIONS FOR ALTERNATIVE FUNDING ANALYSIS
Assumptions of Mosaic Alternative (MMSD Recommended Plan)
Existing contract formula for non-Milwaukee County
Suburbs
MMSD annual debt service (after reduced by contract
communities' payments) is recovered by ad valorem
taxation of Milwaukee County property.
County equalized property valuation is assumed to rise
at a real growth rate of .4% per year.
Assumptions of Flow Based Analysis
Flows used to determine the percent of total are 1995
estimates (Base flow + I/I). The estimates are averages
between 1985 and 2005 design year flows.
Community percentages are calculated by dividing each
community's 1995 flow by the total 1995 flow.
Each community's percentage is multiplied times the
MMSD average annual (1985-2005) debt service, which -is
about $86 million.
No assumption is made on how the communities would
distribute the cost to the household level.
County boundaries are ignored.
Assumptions of Service Area Property Tax
Only the property in each community that is served by
the sewerage system is considered in the analysis.
1985-2005 average annual tax rate is $4,06 per $1000.
of equalized property value.
The tax rate is applied equally to all served property
in the sewer service area regardless of jurisdictional
boundaries.
5-124
-------
Assuming that the U.S. District Court Order is overturned,
the Preferred CSO abatement facilities would be designed for
a 2- to 5-year storm recurrence interval Cmeaning that the
system's capacity would be exceeded only once during the
average 2- to 5-year periodl.
The capital cost of this alternative would range between
$350 and $520 million. If between $350 and $520 million is
spent at the rate of $20 million per year, $203 million
would be spent fay 1932 and $284 million by 1996 (in 1980
dollars). If approximately $20 million (in 1980 dollars)
would be spent annually on the CSO project after 1996, a
total of $350 million would be spent by 1999, $467 million by
2005, and $520 million by 2008.
The fiscal impacts of the EPA Preferred Alternative are
discussed below for a district-wide as well as an individual
community financing scheme and summarized in Table 5.53.
5.2.4.12.1 District-Wide Financing: With a district-wide
financing arrangement, the MMSD would spend about $203
million on CSO abatement and about $1.1 billion on the
balance of the EPA Preferred Alternative for a total of
about $1.3 billion by 1992. Beyond 1992, the MMSD would
continue to spend $20 million a year (1980 dollars) for 7 to
15 more years until between $350 and $520 million had been
spent on the CSO project. The total cost for the EPA
Preferred Alternative would be between $1.47 and $1.64
billion.
Assuming that the $1.3 billion is expended by 1992, that
$20 million per year is spent on CSO thereafter, that the
expenditures are 36% grant funded, and that G.O. bonds are
issued at a 6% interest rate, the 1985-2005 average annual
equalized property tax rate for Milwaukee County would be about
$3.50 per $1,000 to finance the local portion.
Assuming that the $1.3 billion (and $20 million per year
after 1992) would be 0% grant funded and that interest rates
on the bonds would average 9%, the 1985-2005 average annual
equalized tax rate would be about $6.80 per $1,000.
Thus under a district-wide financed scheme, the average
annual equalized Milwaukee County tax rate (1985-2005) to
finance the EPA Preferred Alternative would range from $3.50
to $6.80 per $1,000 depending upon available grant funds and
prevailing interest rates on G.O. bonds.
5-125
-------
Ed
2 O
O K
X •
< 0
EH 0
O
< a
D m
2 to-
a
< <
tn
M
3
•8
CO
m o
r** ^*
i— I ro
H m o
•P r^ ^?
•H H ro
O|
EH i^ i^ OS
PS D W
H Q 2 ft
cu w 2
O S < C/3
On CM [V]
ft W H EH
b O <
r3 < <: EH
< ft
D Ed in Q
O< 0 W
ro Cd Ed ON
in K CN H
• i-J EH 1 f— I
in < in sC
D PS co D
Ed 2O
0)
I)
O 3
(d
•P rH
•H -H
O S
0 O
m co
• •
ro u3
•c/> -co-
rt! Ed
EH HO
CD HH
2 PS
> CO
rtj
EH
Q 03
W Ed
EH Q
<; tn en
H ffi C G
EH EH O O
co mm
Ed Ed
O
in 2 O O
0 < •
02 t3
CN H 0)
1 b U
m c
CO O rB
CTi SH g
rH -H
b
0)
CO
a
o
H
£n
ft
^1
D
CO
CO
T3 -P
(U (d 0) fd
T3 PS T3 PS
C G
34J 3 4J
PD 01 fTi W
0) 0)
4-1 M 4-1 SH
CO) CO)
(04-) (d 4J
t, (-1 tj r»
M >-« W i-«
OH OH
dP dP dP dP
VO v£ O CTi
ro
O 0 0
M i-H
0 0 O
CTi ^3* PO
•-H CN
to-
O 0
O CO CO
• • •
O CN CN
•CO-
000
co co kO
• • •
H CN f
(I)
•H
4-1
fd
O >-!
2 (1)
H 4J
U i-l
a co <;
f^ *&
z c n
H O 0)
b CQ M
T3 M
>" C • 0)
EH rd O M-i
H • OH ft c hi
H (d <
Q dP d(= O rH EH
2 vO ^ CO rd O
H ro O 03 EH
O m in
r^ r^*
CN CN
in in o
f**- r^ in
rH CN ^P
V>
o o
o m in
• • •
o m m
0 0 O
in m o
• • •
ro m r?i
•H
p
g
OJ
P
rH
in <
r0
C T3
O 0)
CQ SH
'O M
G • 0)
cd O 4-1
Q)
T3 ft
<1) C ft EH H
S 3 4J W i^ W
3 b en G P K co
tn oj CD o MH ry
tn 4-1 M £
-------
5.2.4.12.2 Individual Community Financing; If the City of
Milwaukee finances the EPA Preferred CSO alternative with
36% grant funding and issues $20.3 million worth of bonds
each year at 6% interest, the 1985-2005 average annual
equalized tax rate would be about $1.80. The balance of the
MFP would cost City of Milwaukee taxpayers another $2.80 per
$1,000 equalized, increasing the total to $4.60. The rest
of Milwaukee County would be taxed at a rate of about $2.80
per $1,000 equalized.
Assuming 0% grant funding and 9% interest on the bonds for
both the City and the County, the City of Milwaukee would be
taxed at the rate of about $9.00 per $1,000 equalized C$3.50
for CSO plus $5.50 for the balance of the EPA Preferred
Alternative}. The rest of Milwaukee County would be taxed
at about $5.50 per $1,000 equalized.
Thus, under an Individual Community Financing arrangement,
the 1985-2005 average annual equalized City of Milwaukee
property tax rate to finance the EPA Preferred Alternative
would range from $4.60 to $9.00, depending upon available
grant funding and prevailing interest rates. The costs to the
rest of Milwaukee County would range from $2.80 to $5.50 per
$1,000.
With either District-Wide or Individual Community Financing,
households in the contract communities would be charged
about one-half as much as households in Milwaukee County
suburbs (assuming the current contract formula).
5.2.5 Economic Impacts
5.2.5.1 Introduction
Any of the MFP final alternatives, except No Action, would
have both positive and negative impacts on the economy of
the Milwaukee area. The massive amount of money spent in
the Milwaukee area to implement the MFP would have positive
impacts by stimulating the economy, creating jobs, and
increasing income levels. However, negative impacts would
also occur because 64% of this money would come from the
taxation of citizens in the Milwaukee area, thus reducing
the amount of money that these taxpayers could otherwise
save or spend within or outside of the region.
Any change in the region's economy affects all aspects of
the area's economy. For example, contracting a construction
firm to build a treatment plant could cause that firm to
hire more employees in addition to purchasing the materials
needed for the job. This is called a direct effect. Also,
the firms that do business with the firms supplying the
5-127
-------
construction company would be stimulated. These many levels
of economic interactions, coupled with, the effects of the
increased consumer spending due to increased income, are
called indirect or induced effects. At the same time, a
reduction in spendable income due to increases in the tax
rate could reduce the money being spent locally, thus having
a negative indirect effect on local businesses.
The Regional Industrial Mutiplier System CRIMSl model,
developed by the United States Department of Commerce,
Bureau of Economic Analysis, was used by the MMSD to estimate
specific economic impacts of the program. The EPA, DNR,,and
EIS consultant evaluated the RIMS model and determined that
it was an acceptable method of evaluating potential economic
impacts.
The RIMS model is a method of quantitatively estimating the
total effect of a major project like the MFP on the local
economy by tracking the many levels of economic effects
it sets off. The RIMS model was used to measure how the MFP
would affect gross output Cregional economic production),
earnings (.income) , and employment in the study area. The
results of the RIMS analyses for all final alternatives were
similar, so the Mosaic Alternative is used as the basis for
the discussion in this chapter. For a detailed description
of the RIMS model and its application to this project, the
reader is referred to Appendix X, Fiscal/Economic Impacts.
Because 64% of the project costs are projected to be locally
funded, both the positive and negative impacts of the project
must be considered. The positive and negative impacts of
the Mosaic Alternative are discussed separately and then
are combined to determine the program's net impact on the
local economy.
5.2.5.2 Positive Economic Impacts
The total dollar amounts of gross output, earnings, and
employment stimulated by the direct and indirect effects of
the Mosaic Alternative are listed below.
Gross Output = $4,544,452,000
Earnings = $1,173,626,000
Employment = 55,097 man-years
Thus, although the MFP would cost $1.6 billion, it would
stimulate the local economy to increase its output by $4.5
billion. The MFP would directly and indirectly create
55,097 man-years of work increasing local earnings by $1.2
billion.
5-128
-------
5.2.5.3 Negative Economic Impacts
The negative economic impacts of the MFP are more difficult
to assess. Quantification of the negative impacts of the
project requires analysis of how consumers (the taxpayers)
would have spent the tax money used to support the MFP.
There are two extremes to measure the range of negative
economic impacts. The "least case" assumes that none of the
tax money raised to support the debt service would have been
spent within the region. Therefore, there would be no
ripple effect on the local economy from the lost consumer
income. The negative impacts of the MFP under this "least
case" assumption are shown below.
"Least Case;"
Gross Output = -$1,966,319,000
Earnings = -$ 333,584,000
Employment = -23,707 man-years
The second way that the negative impacts could be generated
is termed a "worst case", which assumes that all of the
money taken out of the private sector to support the debt
service would have been spent in the local economy. This
spending shortfall would, therefore, have repercussions
throughout the local economy. Just as the $1.6 billion
program expenditure multiplies into a total of $4.5 billion,
the $1.97 billion spent on debt service must also be represented
in its multiplied form. The $1.97 billion would ripple
through the economy by way of direct and indirect effects
and create a multiplied total of $5.5 billion. The same
procedure was carried out for earnings and employment,
listed below.
"Worst Case;"
Gross Output = -$5,525,758,000
Earnings = -$1,137,313,000
Employment = -72,197 man-years
In other words, if the negative effects of the MFP, i.e. the
local burden in terms of gross output, earnings, and employment,
are subjected to the same "multiplier," or ripple effect,
as the positive effects, the resulting "worst case" negative
effects could potentially cost $5.5 billion in gross output,
$1.1 billion in earnings, and 72,197 in man-years.
The actual negative impacts of the MFP would probably fall
somewhere between the "least case" and "worst case" scenarios.
5-129
-------
5.2.5.4 Net Impacts
To measure the net impacts to the local economy of the MFP,
the negative impacts are subtracted from the positive. Table
5.54 summarizes the net impact of the MFP, assuming the least
and worst case scenarios. The economic impact of the MFP
may be characterized as having an initial positive effect,
quickly followed by a period of negative effects in the form
of debt service payments.
5.2.5.5 Impacts of CSO Alternatives on Area Employment
The RIMS model was not used for the final CSO alternatives.
Therefore, no method exists for quantitatively assessing
and comparing the direct and indirect impacts of each final
CSO alternative on the Milwaukee area economy. However,
certain manpower requirements for CSO alternatives can be
estimated, and statements regarding the requirements of local
labor can be made.
The EIS assumes that the implementation of a CSO alternative
which utilizes the local labor and materials market would
have a greater positive impact on the area economy than an
alternative which relies to a greater extent on non-local
labor and materials. Generally, much of the sophisticated
equipment and specialized labor required for cavern and deep
tunnel construction is not available in the local area (this
specialized labor and equipment represents only a small portion
of the labor and equipment required for any alternative).
Therefore, the positive employment impacts of a sewer separation
alternative, which relies on more local labor, will probably
be greater than the positive employment impacts of a storage
alternative. The employment impacts of the Complete Sewer
Separation Alternative are compated below to those of the
MMSD Recommended CSO Alternative (Inline Storage) since they
represent two extremes in terms of employment impacts.
According to Appendix 6D of the MMSD CSO Facility Plan, complete
sewer separation would require an average of 190 construction
workers per year for ten years to complete the main line
sanitary sewer construction. In addition, a minimum average
of 150 workers per year for ten years would be required for
separating residential, commercial, and industrial buildings.
The Complete Sewer Separation Alternative would require 340
(190+150) man-years per year for ten years, for a total of
3,400 (340 x 10) man-years (a man-year is employment for
one person for one year; thus, this does not necessarily
mean 3,400 new jobs would be created).
5-130
-------
TABLE 5.54
NET ECONOMIC IMPACT ASSUMING LEAST CASE NEGATIVE
Positive - Negative = Net Impact
Gross Output
(x 1000) $4,544,452 $1,966,319 $2,578,133
Earnings
(x 1000) $1,173,626 $ 333,584 $ 840,042
Employment
(man-years) 55,097 23,707 31,390
NET ECONOMIC IMPACT ASSUMING WORST CASE NEGATIVE
Positive - Negative = Net Impact
Gross Output
(x 1000) $ 544,452 $5,525,758 -$ 981,306
Earnings
(x 1000) $1,173,626 $1,137,313 $ 36,313
Employment
(man-years) 55,097 72,192 17,100
Source: MMSD and ESEI
5-131
-------
According to Chapter 8 of the MMSD CSO Facility Plan,
the MMSD Recommended CSO Abatement Alternative would
require an average of 310 construction-related personnel
per year, for 9 years, for a total of 2,790 man-years.
The comparison would be 3,400 man-years for complete
sewer separation as opposed to 2,790 man-years for the
construction of new storm sewers and storage facilities
(MMSD Recommended Plan). However, if it is assumed that
10% of the work force for the recommended alternative
would be imported, then the comparison would be: 3,400
man-years required for complete sewer separation vs.
2,511 man-years for the MMSD Recommended CSO Alternative.
Although the Complete Sewer Separation Alternative has
the potential to employ a greater number of local construction-
related workers, the rather intense disruption to CSSA
businesses caused by the Complete Sewer Separation Alternative
could offset the positive impact of greater local employment.
It would be difficult to differentiate between the negative
economic impacts of the Inline, Complete Sewer Separation,
Modified GST/Inline, and Modified Total Storage Alternatives
for CSO and I/I abatement because the amount of local
tax dollars raised to finance construction of any of
these alternatives would be nearly equal. Table 5.55
summarizes the employment impacts of the final CSO alternatives,
5.2.5.6 Tax Climate
Historically, Milwaukee and Wisconsin have had reputations
as high tax areas. However, two important changes have
recently been made in the state tax policy: the property
tax exemption for manufacturing machinery and equipment and
the exemption of inventories and livestock. These tax
exemptions should affect the manufacturing sector because
their taxable property will be reduced substantially.
Businessmen in the manufacturing sector who were interviewed
by the MMSD indicated that the machinery and equipment
exemptions have changed their attitudes about Wisconsin's
tax climate. The inventory exemption would have similar
effects on retail and wholesale businesses.
Another factor would be the increases in property taxes that
could be deducted on federal and state income tax forms.
Due to recent State law changes, residential property taxes
can no longer be an itemized deduction on state income tax
forms. Since 1979, property taxes have been treated as a
tax credit which can be claimed by all persons filing a
Wisconsin State income tax return.
5-132
-------
TABLE 5.55
CSO ALTERNATIVES: ECONOMIC IMPACTS
Inline: The 11% complete separation and 89% partial
separation required could almost totally draw from the
local labor supply. A small amount of non-local labor
could be supplemented with local labor to satisfy the
deep tunnel, dropshaft, and cavern construction.
Complete Separation: Although this alternative involves
100% separation, it would require 440 miles of sanitary
sewers, as opposed to 460 miles of storm sewers, with the
Inline alternative. The positive economic impacts may be
slightly less than with the Inline alternative.
The local labor required for separation is nearly identical
to Inline, but there would be less local labor required
for near-surface facilities, soft-ground tunnels, screening
structures, and access shafts (the "all other" category).
If current financing practices were applied to the analysis
of the complete separation alternative, homeowners in the
CSSA could be severely burdened with additional costs.
Specifically, current MMSD practices require that homeowners
pay for the costs of connections and repairs made from the
street to the home. Under the complete separation alternative,
there could be this additional fiscal burden to CSSA home-
owners, unless the opinion of the MMSD Legal Staff is
confirmed, that the entire MMSD would pay the costs of
street-to-house connections in the CSSA.
GST/Inline: This alternative involves 120 miles of con-
struction, with 11% complete separation, 21% partial
separation, and 68% complete storage. This may have fewer
positive economic impacts than Inline, but no comparison
with complete separation is possible.
Total Storage: With no sewer separation, the local labor
needs would be more intensified in the tunnel and storage
facility construction. Positive economic impacts will be
limited to the "all other" category, yielding much less
of an economic benefit than Inline or CST/Inlirte.
5-133
-------
5.2.5.7 Business Relocation
Taxes are often an important factor when businesses choose
to locate or remain within the planning area. To study how
tax increases might affect specific industries in the Milwaukee
area, the EIS has relied on a MMSD survey of 47 firms and on
interviews by the EIS consultant with trade associations.
The businesses sampled represented each major industrial
sector throughout the region. Interviews were conducted
with senior executives of each participating firm.
The objectives of the MMSD survey were to provide infor-
mation on the project, to discuss estimates of the firms'
sewer related tax increases due to the project, and to
elicit the companies reactions to the future changes.
Few of the firms surveyed indicated that the tax increases
would put them at a competitive disadvantage to similar
companies outside'the planning area. No firm stated a
desire to move outside the planning area to avoid MFP costs.
This response may partly be explained by the large exemption
to property valuation granted to the industrial sector.
5.2.5.8 Impacts on Selected Industries
Table 5.56 compares projected 1985 sewerage costs for selected
industries with their 1979 costs. These sewerage costs
include user charges for O&M and property taxes for capital
debt service. For this comparison, the 31 major industrial
firms were grouped into three categories: heavy machinery;
breweries and dairy products; and manufacturing. For these
three categories of industries, sewerage costs would increase
by 24% on the average, with the highest increase (67%) in
the heavy machinery industry.
In all these industries, sewerage costs are now and will
continue to be only a small portion of the cost of doing
business. Table 5.57 illustrates the small percentage of
present and projected value added (.the value of a firm's
finished product less the cost of materials} attributable to
sewerage costs. Only in the chemical industry are sewerage
costs a significant portion of value added, and the percentage
of operating cost attributable to sewer costs would not
change drastically if the MFP is implemented. The effects
on other industries and households are summarized below.
5.2.5.8.1 Brewing; The project would probably not have any
adverse effect on the brewing industry because capital costs
are recovered by property taxes and not by user charges.
The brewing industry is a heavy water user, but its taxable
property values are not especially high.
5-134
-------
w
tn
2
M
J
f£
M
OS
EH
cn
Q
Z
H
rH
n
PS
o
b
Ul
EH
cn
o
U
a
o
ex
H
3
U
cn
m
00
(TV
rH
Q
2
^J
cn
p-
cn
i-H
CN — •
01 in
4J )4
tn id
O rH
CJ rH
O
oi a
0*
id o
M ao
cu an
SrH
CU
a] IM
O
in
00 01
cn *o
rH C
id
13 01
•
CU
W
(d
cu
M
O
C
dP H
dP dP dP
r- rH in
e • 0
rH VO t~
in ao cn
i-H CN rH
^,
•M
M
0)
a
o x
IH it)
CM EH
rH rH Ul
• • •
in T o
r—
CU
01
CU
IH
O
C
dp H
dP dP dP
m r- co
• • •
r- rH cn
rH
01
cn
rl M
cu id
01 JZ
D U
in 10 oo
• • •
o n o
r- cr> CN
r** n cn
* «
to-
rH CN CO
t e t
rn co in
rH
10
•P
o
EH
CN in cn
CM rH in
rH fl ff)
>,
4-1
^4
(8 rH
01
3 CU
O 0
C
o
-H
4J
a
•H
M
0
01
CU
a
x: -H
4J ^J
a < a: o
c
•rl 0 CM CM Oi
00 333
en cn O O O
4-> rH rl ^4 rl
01 C3 C3 U
o -n
u id
dP
o
•
*J>
CN
^
^1
cn
CO
en
°
dP
CN
0
00
r^
rH
VO
•
cn
o
CO
^
rH
t/>
dP
f>
•
O
rH
cn
•
*4*
CO
0
•,
CO
to-
rH
•
r-
r-
cn
^
r^.
to-
m
•
0
in
10
t/v
ao
\Q
CN
ro
«
^- C
to- o
f4 ^
J3 'H
•rH Q|
i-4 id
4J CJ
CD
•r( G S
T3 CO
rH CU O
K) 4J 3
4J 01 4J T3
O 0
4-)
OP
dP O
o o
in rH
•^ ,y
o u
o o
4J 4-1
in 01
~ •
01 0}
4J 4-1
C C
id ra
x; x!
o o
cu cu
s s
•a -a
c c
~ ~
tn eg
V4 ^-1
cu ,
U
•rl
id
£^
QI trt tri
c c c
•rl H) -rl
XI V4
O 01 3
IB CU 4J
S -rl O
rl Id
> 0) <*->
> S 3
n) cu C
CU rl Id
K 03 2
1 1 1
< a cj
CM CM CM
333
O O 0
U O U
c
rH
rH
1
r^
«
^
w
^
c
id
rH
CM
E
CU
4J
tn
>^
cn
Vl
0)
4-1
id
cu
0]
id
S
Q
Ul
;g
jgj
••
CU
O
IH
3
O
CO
5-135
-------
TABLE 5.57
SEWERAGE COSTS AS A PERCENTAGE OF VALUE ADDED
Sewerage Cost as a Percent
of Estimated 1976 Value Added
Description
Heavy Machinery
Paints and Allied Products
Primary Metals
Fabricated Metals
Machinery Except Electrical
Electric and Electronic
Equipment
Transportation Equipment
Total
Beverages and Dairy Products
Malt Beverages
Dairy Products
Total
Other Manufacturing
Food Processing Excluding
Beverages and Dairy
Products
Paperboard Products
Misc. Chemicals
Leather Tanning
Total
All Groups, Total
1979 Sewerage
Cost1
0.2%
0.2
*
0.1
0.1
*
0.1%
0.8%
0.2
0.7%
2.2%
N/A
16.2
3.2
4.0%
0.3%
Projected 1985
Sewerage Cost
0.5%
0
0
0.1
0
0
0.2%
1.1%
0.2
0.9%
2.5%
N/A
18.2
3.6
4.5%
0.4%
*Less than 0.05%
N/A - Not Available
Manufacturers'
2
Manufacturers'
Source:
and merchants'
and merchants'
stocks 50% tax exempt.
stocks 100% tax exempt,
Table 7-12
WSP: Environmental Assessment.
5-136
-------
5.2.5.8.2 Leather Tanners; The leather tanning industry
faces severe foreign competition and consequently has had
great difficulty passing price increases to its customers.
Interviews revealed that the projected increases in property
taxes would not adversely affect this industry.
5.2.5.8.3 Construction; The MFP could create a temporary
upsurge in the construction industry in Milwaukee. In 1984,
employment in construction is expected to rise to a high of
3,000 man-years. The annual average through 1990 would be
1,800 man-years. This average figure would represent an
increase of about 10% over average annual construction
employment in the Milwaukee area over the past decade.
Representatives of the U.S. Department of Labor's Office of
Construction Services, several of its branch offices, and
construction experts at the U.S. EPA all concurred that the
surge in employment created by the MFP is not a critical
issue. The construction industry tends to have employment
swings as projects are completed or new projects start up.
5.2.5.9 Impacts on Households
Household property would be the most seriously affected by
increases in property taxes. This property does not have
some of the benefits (e.g., inventory exemptions) which
lessen the burden to industries.
Milwaukee should receive some additional state property tax
credits due to the increase in property taxes associated
with the MFP, which would lower the net tax levy. Home-
owners who itemize their income tax deductions (usually in
the middle or upper income brackets) would be able to itemize
their increased property tax levy on their federal income
tax forms and claim a portion of their property taxes as an
income tax credit on their State income tax form. For
detailed information on the fiscal impacts to households,
see Appendix X, Fiscal/Economic Impacts.
5.2.5.10 Construction Impacts on Local Businesses
The construction of various components of the MFP would
reduce available parking spaces and disrupt traffic patterns
and access to some businesses. The MMSD has estimated that
the MFP construction projects would have durations lasting
from two weeks to two months per block. The disruption of
traffic and access could also disturb businesses in the
vicinity. Businesses which rely on impulse buying (e.g.,
record or book stores) would be more severely affected than
those that sell necessities. Also severely affected would
5-137
-------
be businesses that have a high business threshold (require
greater numbers of daily receipts to remain solvent}.
Retailers outside the central business district could also
be affected by MFP construction because they must rely
heavily on customers using private automobiles. The central
business district has a large customer market readily available
from retail, financial, and other businesses. Pedestrian
access would be less disrupted than vehicular traffic.
Further discussion of impacts to traffic and access can be
found in Section 5.2.12 of this volume and in the CSO Appendix.
5.2.6 Noise
5.2.6.1 No Action Alternative
The operation of wastewater treatment facilities does not
significantly affect the noise levels in the planning area.
Most of the WWTPs are located in residential areas, but
there have been no complaints that noise levels are increased
by WWTP operations. The Jones Island treatment plant is
located near residential development, but it is surrounded
by heavy industry; and thus noise from the WWTP is not
considered a hazard.
5.2.6.2 Local, Regional and Mosaic Alternatives
The Local Alternative includes the construction of six
interceptors of relief systems and three new wastewater
treatment facilities as well as the rehabilitation and
expansion of the Jones Island and South Shore treatment
plants. In addition, five public and two private WWTPs
would be upgraded or expanded. The Regional and Mosaic
Alternatives include eight interceptors and the rehabili-
tation and expansion of the Jones Island and South Shore
treatment plants. All this construction would require heavy
machinery. This equipment should have internal noise muffling
equipment. Construction noise would be temporary, although
some construction periods could be several years; the South
Shore WWTP would require three and one half years for expansion.
The MMSD has estimated that construction of sewers, dropshafts,
cavern access shafts, and near-surface conveyance and storage
facilities for the abatement of CSO and attenuation of peak
flows would result in outdoor noise levels of approximately
55 decibels CdBA) in the A-weighted scale at a distance of
57Q feet C174 m), approximately one and one-half blocks.
This 55 dBA noise level has been identified by EPA as requisite
to protect public health and welfare with an adequate margin
of safety CU.S. EPA, MCD-20, 1976). Some blasting might be
5-138
-------
required for tunnels and storage caverns. The durations of
construction activities to abate CSO are outlined in Table
5.58.
Most sewer construction would occur in streets 50 to 90 feet
C15 to 27ml from residences. Outdoor noise levels from this
construction have been estimated to be in the range of 75 to
87 dBA (CSO FP). Indoor noise levels would be less (by
approximately 15 dBA) due to the typical noise attenuation
qualities of residential buildings. Exposure to peak sewer
construction noise levels would generally be limited to a
period of one to two days per residence.
The noise associated with the construction of dropshafts,
cavern access shafts, and near-surface conveyance and storage
silos would be in the same range as those expected for sewer
construction. Noise from the construction of screening
facilities for the Modified CST/Inline and Modified Total
Storage Alternatives would be substantially higher due to
the need for pile driving operations. The distance from
residential areas to dropshafts construction sites would be
greater than 600 feet (183 m) for all but four dropshafts.
Of those four, one is located 100 feet C30 m) from residences,
two are 200 feet C61 m) from residences, and one is 300 feet
C91 m) from residences. Construction at these sensitive
sites should employ the best available noise control methods.
The duration of construction at these sites would be approximately
one year.
In general, the CSO alternatives that involve sewer con-
struction would cause the greatest noise disruption through-
out the CSSA. However, specific locations would only be
affected on a short-term basis. Conversely, facilities
requiring long duration construction at specific sites could
have major long-term noise impacts in sensitive residential
areas. Operating noise from the treatment facilities could
potentially have long-term impacts on the surrounding environment,
since most of the facilities are located near residential
land. However, these operations have not in the past disrupted
the surrounding communities.
Noise generated during operation and maintenance of any CSO
abatement component would be minimal. Most facilities would
be underground, thus preventing the transmission of operation
and maintenance noise to the human environment. Some minor
intermittent noise would be generated by maintenance vehicles
and personnel entering and leaving a particular facility.
Ventilation equipment would be operated prior to entry of
sewers, deep tunnels, and caverns. The noise produced by
ventilation equipment could be minimized by proper vent
location, baffling, and vegetative screens.
5-139
-------
TABLE 5.58
DURATION OF CSO CONSTRUCTION ACTIVITIES
Alternative Extent
Complete Sewer Entire CSSA affected by sewer construction within
Separation 50 feet to 90 feet of buildings.
15 lift stations.
Duration
10 years total, 1 to 2 weeks
per residential block.
6 months each
Inline Storage Entire CSSA affected by sewer construction within
50 feet to 90 feet of buildings.
9 miles of near surface collector sewers.
6.5 miles of shallow tunnels w/access shaft
every 1000 feet.
14 dropshafts (no screening facilities).
4 near surface storage facilities (without screening),
1 cavern access shaft.
10 years total, 1 to 2 weeks
per residential block.
1 to 2 weeks per residential
block.
2-6 months per access shaft.
1 year at each site.
3 years each site.
31! years at this site.
Modified CST/
Inline Storage
Modified CST/
Inline Storage
(cont.)
21% of CSSA affected by sewer construction within
50 feet to 90 feet of buildings.
9 miles of near surface collector sewers.
6.5 miles of shallow tunnels with access shafts
every 1000 feet.
14 dropshafts (with screening).
4 near surface storage facilities (with screening).
2 cavern access shafts.
1 to 2 weeks per residential block.
1-2 weeks per residential block.
2-6 months per access shaft.
1 year each.
3 years each.
3"i years each.
Modified Total
Storage
9 miles of near surface collector sewers.
6.5 miles of shallow tunnels with access shafts
every 1000 feet.
14 dropshafts (with screening).
4 near surface storage facilities (with screening)
2 cavern access shafts
1-2 weeks per residential block.
2-6 months per access shaft.
1 year each.
3 years each
3H years each
1 Mile = 1.609 Kilometers
1 Foot = 0.3048 Meters
Source: ESEI, 1980.
5-140
-------
Pump stations and screening facilities would present the
greatest potential for producing long-term noise impacts.
Proper acoustical treatment of the structures housing these
facilities would limit objectionable noise to the confines
of the buildings. Additional protection could be achieved
by providing buffer zones with vegetative screening around
the facilities.
5.2.7 Public Sealth
Public health concerns associated with the MFP are related
to the exposure to disease-producing organisms or toxic
substances. Potential risks to public health affected by
the MFP include the following issues:
1. Sewerage system or treatment plant discharges of disease-
producing organisms,
2. The use of chlorination for WWTP effluent disinfection,
3. Priority pollutants discharged from WWTPs,
4. Aerosal emissions from WWTPs, and
5. Groundwater quality impacts of the deep tunnel CSO
abatement system.
All of these issues are discussed below.
5.2.7.1 No Action Alternative
With the No Action Alternative, untreated or inadequately
treated sewage would continue to be discharged to surface
waters from combined sewer overflow outfalls, dry weather
and wet weather bypasses from the separate sewer systems,
overloaded wastewater treatment plants, and malfunctioning
septic systems.
Pathogens discharged in sewage can contaminate water and
infect humans and other animals through water consumption or
direct body contact. Water-borne diseases include cholera,
hepatitis-A, typhoid fever, salmomellosis, and gastroenteritis,
Fecal coliform bacteria are used as indicator organisms for
the presence of viral, bacterial, protozoan, and fungal
pathogens. The number of fecal coliform organisms in the
water is an indication of the bacteriological safety of the
water and the public health hazard associated with its use.
With the No Action Alternative, all major streams in the
planning area, the Inner Harbor, and the Outer Harbor would
continue to violate the fecal coliform standards established
5-141
-------
by the DNR and recommended in the 208 Plan. The direct
relationship between fecal coliform organisms and the actual
occurance of water-borne diseases is difficult to determine.
Nonetheless, the excessive fecal coliform levels expected
under the No Action Alternative could pose a substantial
risk to public health if these waters were consumed or used
for body-contact recreational activities. Milwaukee area
beaches would probably continue to be closed due to high
fecal coliform levels in Lake Michigan.
Wastewater effluent is now disinfected by chlorination and this
process would continue with the No Action Alternative.
Chlorination produces by-products which are carcinogens or
suspected carcinogens. With the No Action Alternative, the
concentrations of residual chlorine in the receiving waters
would be very similar to existing concentrations. Based on
the limited data available, concentrations of chlorination
by-products are currently well below the EPA proposed drinking
water criteria.
The chlorination process does, however, pose another risk to
human health due to possible accidents associated with the
storage, handling, and transportation of the chlorine gas.
Proper precautionary measures would minimize this risk.
There are numerous other substances that would be discharged
from wastewater treatment plants which, if present in high
enough concentrations, can be toxic to humans. These priority
pollutants are discussed in Section 4.3 of Appendix VII,
Water Quality. Concentrations of priority pollutants in the
Inner Harbor, Outer Harbor, near-shore Lake Michigan, and at
the Lake Michigan water supply intakes were measured in
1980. Because of the scarcity of data available, it is not
possible to quantitatively predict concentrations of these
priority pollutants in the future.
However, the existing data and EPA water quality criteria
were used to assess the impacts of discharges from the Jones
Island and South Shore WWTPs on near-shore Lake Michigan
water quality. No pollutant concentrations measured exceeded
the EPA criteria established to protect human health.
Phthalate esters, a group of organic compounds, were detected
at levels which could have chronic toxic effects on aquatic
life. However, these concentrations were less than 0.2% of
the concentrations determined to be toxic to humans.
Public concern has also been expressed about health hazards
posed by aerosol emissions from wastewater treatment plants.
Under the No Action Alternative, aerosol emissions from
treatment plants would be expected to continue at approx-
imately the existing levels. The following studies have
5-142
-------
addressed the risks to public health associated with aerosol
emissions from wastewater treatment plants:
"Health Effects of Aerosols Emitted from an Activated Sludge
Plant," EPA-60Q/1-79--OJ.9,
"Health Implications of Sewage Treatment Facilities," EPA-
600/1-78-032,
"Health Effects of a Wastewater Treatment System," EPA-
700/1-78-062,
"Assessment of Disease Rates among Sewer Workers in Copenhagen,
Denmark," EPA-600/1-78-007,
"Environmental Monitoring of a Wastewater Treatment Plant,"
EPA. In publication,
"The Evaluation of Microbiological Aerosols Associated With
the Application of Wastewater to Land: Pleasonton, CA.,"
Department of the Army, and
"Health Risk of Human Exposure to Wastewater," EPA, in
publication.
Some of the studies concluded that some wastewater treatment
plants produce aerosol emissions which contain fecal coliforms,
pathogens, enteroviruses, mercury, and other toxic sub-
stances. However, the studies did not indicate that the
wastewater treatment plants contributed to a higher incidence
of disease near the plants. Nevertheless, the presence of
these organisms and substances at higher levels than would
otherwise occur indicates an increased risk to public health.
5.2.7.2 Local, Regional and Mosaic Alternatives
All of the action alternatives would include abatement of
CSO. These alternatives would eliminate the discharge of
untreated or inadequately treated sewage to surface waters
from combined sewer overflows, dry weather and wet weather
bypassing from separated sewer systems, malfunctioning
septic systems, and overloaded wastewater treatment plants.
Thus, these alternatives would reduce the risk to public
health from the discharge of pathogens. The implementation
of these alternatives, together with implementation of the
208 Plan, would allow all streams in the planning area to
meet both the existing DNR and 208 recommended fecal coliform
standards.
Risks to public health resulting from chlorination of WWTP
5-143
-------
effluent would be less with an action alternative than with
the No Action Alternative because smaller amounts of residual
chlorine would be discharged to inland streams. If the EPA
recommendations CSection 3.13.6.1) are acted upon, dechlorination
processes would be implemented at the Jones Island and South
Shore WWTPs, further reducing inputs of chlorine to Lake
Michigan.
With any action alternative, the discharge of priority
pollutants to Lake Michigan would be similar to the No
Action Alternative. If priority pollutants are contained
within effluent discharges to inland streams, these pollutant
discharges would cease when these WWTPs are abandoned.
Aerosol emissions from the Jones Island and South Shore
WWTPs with the action alternatives would also be similar to
the No Action Alternative. Aerosol emissions would cease
from WWTPs which are abandoned. However, aersol emissions
would continue from those WWTPs that would utilize land
application of sewage effluent. The infiltration-percolation
ponds, which would not be covered, could emit some pollutants
into the atmosphere.
Public concerns have been raised about the possibility that
the proposed construction of approximately 17 miles of 20-
to 30-foot diameter tunnels beneath Milwaukee County may
pollute groundwater. This issue is addressed in detail in
an attachment to the Addendum to Appendix V, Combined Sewer
Overflow which includes a study by Converse Ward Davis
Dixon,Inc. The study concludes that that the escape of
pollutants from the tunnels into the groundwater could be
mitigated in final design. However, such mitigating measures
may not be cost-effective. The study recommends a series of
followup studies and procedures to minimize the impacts of
the tunnels. In addition, an extensive groundwater monitoring
system is recommended. If implemented, these measures
should adequately protect the groundwater resources in the
planning area.
5.2.8 Safety
5.2.8.1 No Action Alternative
Other than risks to the public health, safety is primarily a
concern during new construction activities. Because the No
Action Alternative calls for no new development, safety is
not a significant issue.
5.2.8.2 Local, Regional and Mosaic Alternatives
Any major construction project poses a potential threat to
5-144
-------
the safety of workers and the public. For the construction
necessary to implement the MFP, the MMSD requires the contractor
to adhere to laws and local ordinances governing safety
and be responsible for the construction sites. Generally, the
hazards associated with construction are temporary and they
would end when work is completed. Measures to reduce safety
hazards during construction are listed in Table 5.59.
There are also hazards associated with the operation of
treatment facilities. Workmen or the public could be exposed
to dangerous chemical or biological substances including
toxic chemicals, corrosives, dust, fumes, smoke, noise,
biological infective agents, and gases. Physical hazards
also exist, including fire, electrical shock, falls, explosions
and equipment related accidents. However, precautions are
taken at existing WWTPs to minimize these dangers, and it is
assumed that adequate precautions would be taken in the
future.
5.2.9 Traffic and Access
5.2.9.1 No Action Alternative
Because the No Action Alternative requires no construction
other than for projects now underway or projects that have
received "Findings of No Significant Impact" designations,
no major affect on transportation patterns or pedestrian
access to residential, commercial, or industrial establish-
ments is expected.
5.2.9.2 Local Alternative
Most of the construction activities required to implement
this alternative would take place in the existing public
right-of-way, mainly in streets with some use of easements
and other public lands. Construction projects of this
nature tend to disrupt traffic patterns, increase traffic
congestion in both arterial and non-arterial streets near
the construction site, decrease parking availability, and
limit accessibility to residences and local commercial
establishments. Table 5.60 summarizes the impacts of the
program elements on traffic and access.
The Local Alternative would create impacts of both short and
moderate duration. Construction activities at the Jones
Island, South Shore, South Milwaukee, Caddy Vista, Muskego
Northeast, New Berlin Southeast, Germantown, and Thiensville
WWTPs would range from minor upgrading to complete reconstruction,
It has been estimated by the MMSD that construction activities
at the Jones Island WWTP would require approximately five
years to complete. South Shore WWTP construction duration
5-145
-------
TABLE 5.59
MEASURES TO REDUCE SAFETY HAZARDS
AT CONSTRUCTION SITES
1. Confer with local utilities to obtain locations and
routes of all utility facilities that might interfere
with the chosen route. Utilities might include water,
storm and sanitary sewer, fuel, gas, steam and elec-
tricity both aerial and underground.
2. Hold traffic interference from construction activities
to a minimum. This can be done by use of warning
signs, obstruction lights and detouring.
3. Begin trenching and tunneling at lower end of route
to help protect against flooding. Keep water out
of trenches by pumping or well points.
4. Check that adequate shoring and sheeting is used at
excavations.
5. Be sure that methods and equipment used for construction
are the safest alternatives. (Example: Loads should
not be swung over workmen's head as they work in the
excavations.)
6. Sites must have a-system of security., to protect the
public from unknowingly coming onto the site. This
could be done with placement of -equipment and barriers
both during construction activities and off-hours.
5-146
-------
TABLE 5.60
CONSTRUCTION IMPACTS ON TRAFFIC AND ACCESS
FACILITY
CSO FACILITIES:
A. Complete
Separation
WORK INVOLVED
Open-cut sewer con-
struction, public and
private
15 Lift stations
SEVERITY AND
TYPE OF IMPACT
Entire CSSA affected,
Separation in most
buildings
Minimal traffic impact
Localized access im-
pact
DURATION
1 to 2 weeks per
residential block,
10 yrs. total
6 months each,
10 yr. total
B. Inline Storage
Open-cut sewer con-
struction on public
property
9 miles of near sur-
face collector sewers
Entire CSSA affected
within 50 to 90 feet
of buildings
Complete disruption
to the 9 Tiile area
1 to 2 weeks per
residential block,
10 yrs. total
1 to 2 weeks per
residential block
6.5 mi. of shallow
tunnels with access
shaft every 1000 ft.
14 dropshafts (no
screening facilities)
4 near surface stor-
age facilities (with-
out screening)
4 access shafts for
deep tunnel construc-
tion
Localized disruption
at dropshaft sites
Localized disruption,
increased truck
traffic
Localized disruption,
increased truck traffic
10 acres of complete
disruption per access
shaft
2-6 months per
access shaft
1 year at each site
3 years each site
3 1/2 years per
access shaft
C. Modified CST/Inline
Storage
Open-cut sewer con-
struction on public
property
9 mi. of near sur-
face collector sewers
6.5 mi. of shallow
tunnels with access
shaft every 1000 ft.
14 dropshafts with
screening
4 near surface storage
facilities with
screening
4 cavern access shafts
21% of CSSA affected 1 to 2 weeks per
within 50 to 90 ft. of residential block
buildings
Complete disruption
to the 9 mile area
Localized disruption
at dropshaft sites
1 to 2 weeks per
residential block
2-6 months per
access shaft
Localized disruption, 18 months at each
Increased truck traffic site
Localized disruption, 3 yrs. each site
Increased truck traffic
10 acres of complete
disruption per access
shaft
3 1/2 years per
access shaft
•D.
Modified Total
Storage
9 miles of near sur-
face collector sewers
6.5 mi. of shallow
tunnels with access
shafts every 1000 ft.
14 dropshafts with
screening
4 near surface stor-
age facilities with
screening
4 cavern acess shafts
5-147
Complete disruption to 1 to 2 weeks per
the 9 mile area residential block
Localized disruption
at access shafts
2-6 months per ac
shaft
Localized disruption, 1 year each
Increased truck traffic
Localized disruption, 3 years each
Increased truck traffic
10 acres of complete
disruption per access
shaft
3 1/2 years each
-------
TABLE 5.60 (continued)
CONSTRUCTION IMPACTS ON TRAFFIC AND ACCESS
FACILITY
INTERCEPTORS
A. Open-cut
B. Tunnel
WORK INVOLVED
Open-cut at depths
of 0 to 25 feet.
Often along right-
of-ways
Tunnels with surface
construction limited
to shaft and storage
sites
WASTEWATER TREATMENT PLANTS
A. Jones Island WWTP Upgrading and expan-
sion of facility, demo-
lition of equipment to
be replaced
Transportation of
new equipment and con-
struction waste in and
out of WWTP
Lakefill
Relocation of Jones
Street
Disposal of demolition
material and construc-
tion byproducts
Normal plant operation
B. South Shore WWTP
Upgrading and expan-
sion of facility
Lakefill
Normal Plant
Operation
5-148
SEVERITY AND
TYPE OF IMPACT
Moderate to severe
traffic disruption.
Much less disruption
if not constructed
along a right-of-way.
Minimal traffic im-
pacts, but heavier
equipment can be
expected. Minor
access problems.
Slight impact caused
by on-site work. WWTP
is in an industrial
area which is removed
from major arterials
Moderate to severe
over a short term
period, localized near
the WWTP
Could affect Outer
Harbor shipping and
boating
Port of Milwaukee
would be affected by
all work involved,
including street
location
510,000 cubic yards
would have to be dis-
posed of
This could be affected,
e.g. transportation
of pickle liquor,
chlorine and could be
a safety problem
Localized impact caused
by transportation of
new equipment into
plant. Nearby resi-
dents along major tran-
portation routes could
be impacted. Approx-
imately 33,000 cubic
yards of concrete and
36,000 cubic yards of
stone and gravel would
be hauled in (Alt.
No. 1.)
Op to 510,000 cubic
yards of net fill
would be required.
This could be a severe
impact during the
hauling period
This could be impacted Mid 1981 - mid 1984
by bringing in construc-
tion materials
DURATION
About two weeks per
city block. Two
years total.
Long duration at
shaft sites. Two
years total.
Majority of work
would occur during
1982-1983, Although
some work could
start in mid 1981
and run through 1986
1981-1986 construc-
tion period
Mid 1982 - mid 1984
1981-1986 construc-
tion period
1981-1986 construc-
tion period
1981-1986 construc-
tion period
Most construction
occurs during 1982
through 1983,
although some starts
in mid 1981 and some
ends in mid 1984
Mid 1981 - mid 1982
-------
TABLE 5.60 (continued)
CONSTRUCTION IMPACTS ON TRAFFIC AND ACCESS
SEVERITY AND
FACILITY WORK INVOLVED TYPE OF IMPACT DURATION
LOCAL TREATMENT PLANTS
(Caddy Vista, German- Upgrading and expan- Increased truck traffic 1 to 2 years each
town, Muskego, New sion of facility, demo- in and near residential
Berlin, Thiensville, lition of equipment areas.
South Milwaukee) to be replaced.
Transportation of new Noise and dust
equipment and construc-
tion waste in and out
of WWTP
5-149
-------
has been estimated to be approximately three years. The
upgrading or new construction at the other local WWTPs would
require one to two years. Heavy machinery and truck traffic
would be the primary impacts of these construction activities.
Short-term disruption would also occur along the routes
chosen to connect the Germantown, New Berlin Southeast, and
Muskego WWTPs to their proposed land application sites, as
well as to connect outlying portions of New Berlin to the
new treatment plant site. Much of the construction of these
connector sewers would be open-cut. Many routes would
follow roads with average to wide right-of-ways. Traffic
might be impaired, but detours would be unnecessary. Many
of these connection sewers would be routed through rural and
undeveloped areas and would have little impact on traffic or
access.
Also included in the Local Alternative are six interceptors
which would extend the MIS system within Milwaukee County
Csee section 3.13.2.2).. The Franklin portion of the Franklin-
Muskego Interceptor, Oak Creek North Branch, Underwood
Creek, Root River Interceptor, the Northeast Side Relief
System, and the Franklin Northeast pump station would be
constructed early in the planning period. Large portions of
these interceptors would be tunnelled, but some would also
use open-cut construction methods.
Interceptor construction would take approximately two years.
Open-cut sewers would cause moderate to severe disruptions
to traffic. Portions in the Franklin-Muskego and Oak Creek
North Branch would be routed through rural areas. Their
impacts would be similar to those for connection to land
application sites. The impacts from tunnel construction
would not be as severe because surface construction would be
limited to access shaft and storage sites. Heavier traffic
can be expected in the area due to the large amounts of soil
and concrete that must be transported for such projects.
Access problems associated with tunneling would be minor.
Impacts near access shafts would be of longer duration than
for open-cut methods.
Construction for the Northeast Side, Underwood Creek, and
Root River Interceptors would have more severe impacts
because they are routed through moderately developed areas,
which would increase the likelihood and severity of interruptions
of access to business and residential units.
5.2.9.3 Regional and Mosaic Alternatives
Traffic and access impacts tinder the Regional and Mosaic
Alternatives are similar to those identified under the Local
5-150
-------
Alternative, The Jones Island and South Shore WWTPs would
have the same construction durations and impacts identified
above. All other WWTPs in the planning area would be abandoned
under the Regional and Mosaic Alternative. Instead, connecting
sewers would be constructed to transport flows from existing
local plants to the MIS system. The methods for this construction
would be similar to those used for interceptor construction,
and thus they would have the impacts discussed for the Local
Alternative. The construction of sewers would take place
mainly in rural areas except for the South Milwaukee connector.
This sewer would be constructed in South 5th Street in a
medium residential area. This sewer would not be built
under the Mosaic Alternative because the South Milwaukee
WWTP would be upgraded and would continue to operate throughout
the planning period.
Six MIS extension interceptors are proposed under the Local
Alternative. Under both the Regional and Mosaic Alternatives,
three additional interceptors would be built: Menomonee
Falls-Germantown, Hales Corners, and the Muskego portion of
Franklin-Muskego. The construction of Menomonee Falls-
Germantown and Hales Corners Interceptors would not severely
disrupt traffic and access because both interceptors would
be constructed by tunneling methods. In addition, the
Menomonee Falls-Germantown Interceptor would be located in a
rural area. The Franklin-Muskego Interceptor portion which
would serve Muskego would be constructed by open-cut methods
along Forest Home Avenue and open fields in Franklin.
Although the construction would disrupt traffic flow on
Forest Home Avenue, it is not expected that detouring of
traffic would be necessary.
Under the MMSD Recommended Plan, the Franklin-Northeast
Interceptor would be constructed instead of upgrading the
pump stations. If constructed, the interceptor would pass
through open fields for most of its route and accordingly
would not cause major traffic or access problems.
5.2.9.4 CSO/Peak Flow Alternatives
Facilities for the abatement of CSO and the attenuation of
peak flows would be constructed under the Local, Regional
and Mosaic Alternatives. Because these facilities would be
located in areas which contain much of the major industrial
and commercial activities and most of the high density
residential areas in the planning area, the potential for
major disruption of traffic and reduction in access exists.
The disruption to traffic, mass transit, and access to
industry, commercial centers, and residential areas is
discussed in detail in section 5.12 of Appendix V, Combined
5-151
-------
Sewer Overflow. Table 5.58 outlines the duration for specific
components of the different alternatives for CSO abatement
and peak flow attenuation.
The Complete Sewer Separation Alternative would create the
most access problems because sewer construction Cmost of it
open-cut^ would take place in 92% of the combined sewer
service area (CSSA). The construction of sanitary sewers
and laterals from buildings would affect access to major
transportation corridors and affected properties and parking
availability. About 440 miles of new sanitary sewer would
be placed in street right-of-way. There are more than 500
miles of street in the CSSA. Sewer construction would
necessitate the closing of some residential streets to
through traffic for a minimum of two weeks. Residences with
alleys would continue to have direct access to their houses
during the construction period. In those areas without
alleys, inhabitants would have to park their vehicles on
nearby streets.
Traffic would be maintained in commercial areas; however,
some lanes would be closed and on-street parking would be
prohibited. The central business district would be the area
most susceptable to severe traffic impacts. Mitigative
measures, such as suspension of construction work during
peak traffic hours and the proper sequencing of work projects,
would be needed to prevent severe restrictions to traffic in
this area.
The Inline Storage Alternative would cause disruption similar
to the Complete Sewer Separation Alternative because the
same amount of area would be affected by sewer separation.
The effects would be slightly lessened because no private
property work would be required.
The Modified CST/Inline Storage System would require sewer
construction in only 24% of the combined area; 21% would
require partial separation with no private property work,
and the remaining 3% would be separated with only minor
localized modifications to the existing system. Although
some commercial areas would be affected, the bulk of the
separation activities would take place in residential areas,
minimizing short-term access problems.
The Modified Total Storage System would require only minor
modifications of the existing system to complete any planned
sewer separation. Impacts on access would be minimal.
Sewer construction would occur in small areas in discrete
corners of the service area so that only small areas would
be affected at any one time.
5-152
-------
Storage facility construction would require three to four
years of construction activity. Traffic problems would be
local and would be limited to the immediate vicinity of the
construction site (near-surface storage site or dropshaft
site). The major impact would be construction traffic.
Because construction of CSO facilities would cause congestion
in the central business district and the urban areas, public
transportation would be interrupted. The amount of disruption
to public transit would depend on the area affected by sewer
separation. Table 5.61 lists the number of bus routes
affected by various CSO alternatives. The degree of severity
is based on the number of total routes and importance of the
routes affected.
5.2.10 Archaeological and Historical Sites
5.2.10.1 No Action Alternative
The No Action Alternative would have no impact on arch-
aeological or historical sites in the planning area. No new
construction would take place, therefore, no archaeological
or historical sites would be destroyed or disturbed.
5.2.10.2 Local, Regional and Mosaic Alternatives
The planning area is rich in historic and cultural resources.
Numerous historic structures reflecting a variety of architectural
styles and a number of archaeological sites have been identified.
Any new construction in the planning area could uncover
previously unknown archaeological sites.
Cultural Field investigations along the construction corridors
of the interceptor alignments have identified historical and
archaeological sites which are listed in Table 5.62.
As was discussed in Chapter 4, Affected Environment, the
Jones Island WWTP has been determined to be eligible for
inclusion in the National Register of Historic Places. A
Memorandum of Agreement (MOA) has been prepared by the MMSD,
EPA, DNR, State Historic Preservation Officer CSHPO), and
the Advisory Council on Historic Preservation in order to
outline the specific actions necessary to avoid or mitigate
adverse impacts to the plant during rehabilitation and
expansion activities. The MOA is included in the Final EIS
as Attachment A.
Based on preliminary surveys at the Jones Island site, the
SHPO and the MMSD's consulting archaeologist have concurred
that previous dredge, fill, and construction activities may
have destroyed some significant prehistoric or historic
5-153
-------
TABLE 5.61
BUS ROUTES AFFECTED BY CSO ALTERNATIVES
Alternatives
Complete Separation
Inline Storage
Modified CST/Inline
Modified Total Storage
Routes Affected
44
44
17
1
Severity
Extreme
Extreme
Minor
Minimal
5-154
-------
TABLE 5.62
HISTORICAL AND ARCHAEOLOGICAL SITES IN INTERCEPTOR ROUTES
Interceptor Type(s)
Franklin-Muskego Archaeological Site
Underwood Creek
Root River
Oak Creek North
Franklin-Northeast
Prehistoric
Aboriginal Sites and
Historic Site
Archaeological Site
Prehistoric
Aboriginal Site
2 Archaeological
Sites
Prehistorical
Aboriginal Site
Historically
Significant
Structure
Location
Near Tess Corners
Creek in the
Construction
Corridor
Near the
Construction
Corridor
In Service Area -
Site is far from
the Construction
Corridor Area
In the
Construction
Corridor
In Service Area
In Service Area
In Service Area
Materials
Recovered
Prehistoric
and Historic
Artifacts
Aboriginal
Campsites and
Worksites
Prehistoric
Aboriginal
Occupation
Source: MMSD
5-155
-------
archaeological deposits. However, as stated in the Jones
Island: West Plant Preliminary Case Report, "it is not
possible to demonstrate that such sites do not exist in the
proposed expansion area". Controlled test excavations were,
therefore, recommended. These excavations were performed in
the summer of 1980 and recovered only a small amount of
historic material. In view of the expense and technical
problems involved, the investigating archaeologist and the
SHPO recommended that no further work be done. Additional
information may be found in Appendix II, Jones Island.
It is possible to generally discuss the impacts that could
occur in the CSSA. It is anticipated that no standing
structures would be destroyed or relocated as a result of
sewer or storage facility construction. Dropshaft facilities
would, however, be visible from some landmarks listed on the
National Register of Historic Places. Due to the uncertainty
of the impact, the SHPO should be consulted to determine the
severity of these visual impacts. New gravity storm sewers
would generally be placed under pavement at the same level
or above the existing combined sewers. Thus, they would be
located in previously disturbed material.
The proposed dropshaft sites are along the Milwaukee and
Menomonee Rivers, which are also areas of relatively dense
concentrations of archaeological sites. Construction activities
on three to five acres for each dropshaft could disturb an
unknown number of archaeological sites. Many of these
dropshaft locations are in park-like open areas which may
not have been disrupted by previous construction. Therefore,
additional field inventories should be performed and reviewed
by the SHPO prior to final design of dropshaft and storage
facilities. Additional information concerning the location
of the archaeological and historical sites in the CSSA may
be found in Appendix V, Combined Sewer Overflow .
During construction, previously unidentified property which
could be eligible for inclusion on the National Register of
Historic Places may be encountered. At that time, in accordance
with section 800.7 of the regulations for the Protection of
Historical and Cultural Properties (36 CFR Part 800}, construction
would have to cease until it could be determined by the SHPO
whether the site would be eligible for the National Register
of Historic Places. Eligible" sites must be recovered in
compliance with the current Advisory Council procedures or
else avoided altogether.
It is in the purview of the SHPO to be consulted during all
phases of the facilities plan/environmental impact statement
process. By reviewing preliminary plans for all projects,
the SHPO can determine impacts on identified historical/
5-156
-------
archaeological sites in the early stages of the project and
assist in mitigating any adverse impacts. By reviewing
final design specifications, the SHPO can assure compliance
with federal regulations when unidentified properties are
discovered during construction.
5.2.11 Recreation and Aesthetics
5.2.11.1 No Action Alternative
A decision not to take action to upgrade the sewerage system
could affect recreational opportunities in the planning
area. Increased flows to the WWTPs would increase the
frequency of sewer overflows and bypasses, adversely affecting
water quality. With a continued decline in water quality,
beaches on Lake Michigan would still have to be closed
occasionally to protect public health. Continued nutrient
loads to the Outer Harbor, Whitnall Park Pond, Big Muskego
Lake, and the near-shore portions of Lake Michigan could
increase algal growth in these surface waters thereby reducing
their general recreational and aesthetic value and that of
adjoining parks and parkways. Floating debris in these
waters as a result of sewage overflows and bypasses would
also reduce their recreational and aesthetic value.
5.2.11.2 Local, Regional and Mosaic Alternatives
With implementation of any action alternative, all bypasses
and overflows of inadequately treated sewage would end.
Therefore, Lake Michigan beaches could be closed less frequently
for sewage-related problems. Also, the abandonment of
public and private WWTPs could slightly improve the appearance
and recreational value of Big Muskego Lake and Whitnall Park
Pond.
Nutrient loads to the area surface waters would be reduced
under each alternative. Algae would continue to be present,
but would be reduced in comparison to the No Action Alternative.
The abatement of CSO would reduce the amount of debris in
the lower reaches of the Milwaukee and Kinnickinnic Rivers.
However, debris would still be visible in these rivers from
runoff and discharges outside the planning area.
With any of the action alternatives, some sewerage facilities,
such as dropshafts, would have to be constructed in parks or
residential areas. These facilities would be incompatible
with their surroundings. In order to mitigate these potential
impacts to parkland, the U.S. Department of the Interior has
recommended the following actions (Minor to McGuire, 1/12/81}:
5-157
-------
"1. Vehicular and pedestrian access should be maintained.
The potential for temporary entrances at new locations
should be discussed with local park and recreation
officials.
2. Barriers and/or buffers which minimize adverse noise
impacts from construction equipment should be provided.
3. Disruption of utilities should be avoided. For example,
the loss of water service might cause the closing of a
swimming pool. Loss of gas or electricity could cause
the closing of an entire recreational complex.
4. Vegetation in the area of construction should be protected
from damage by heavy equipment. Trunks of trees should
be protectively wrapped (2 by 4 lumber may be wired
together and wrapped around trees for protectionI. Low
branches which become damaged should be properly pruned.
Small shrubs which might be lost should be temporarily
transplanted and returned to their original location
after construction.
5. All areas should be restored to the preconstruction
condition. Areas left bare by construction should be
reseeded of sodded. All trees and shrubs lost or
damaged should be replaced with landscaping material
of at least equal size, value, and utility.
6. Soil compacted as a result of heavy machinery should be
scarified or otherwise loosened to promote healthy
plant growth.
7. All debris and surplus materials from construction
should be removed from the area as construction progresses
and not as a last minute cleanup effort. All possible
precautions should be taken to prevent soil poisoning
by spills of toxic materials such as oils, fuels, and
solvents."
There is the potential for using abandoned wastewater treatment
facilities for recreational purposes. EPA encourages
recreational use of wastewater treatment and conveyance
facilities which are being planned, designed, and constructed.
This concept of dual use has been recently emphasized to
encourage community participation in the planning of wastewater
treatment facilities and to provide an opportunity for the
fullest utilization of every public dollar spent. There are
many opportunities for dual use through the coordination and
incorporation of recreation facilities and open space in the
development of new wastewater treatment and conveyance
systems and the modification of existing systems, particularly
5-158
-------
in urban areas where land is at a premium.
The MMSD has recommended that the South Shore WWTP be expanded
by enclosing 30 acres and filling in 12 acres of Lake Michigan
to the north of the existing site. Since the expansion
would take place at lake level, it should not greatly increase
the visibility of the facility except to lakefront property
directly adjacent to the South Shore WWTP. The MMSD plans
to landscape their property thereby reducing the plant's
visibility and providing a more aesthetically pleasing view.
The MMSD is also investigating the possibility of integrating
recreational facilities into the lakefill. This issue is
discussed further in the Addendum to Appendix III, South
Shore.
5.2.12 Energy Consumption
5.2.12.1 No Action Alternative
The wastewater treatment facilities in the planning area
require energy to operate. Most of the energy they use
is purchased as fuel oil, electricity, or natural gas,
although the South Shore WWTP also produces electricity with
on-site generators fueled by methane gas, a by-product of
anaerobic digestion. The No Action Alternative would not
significantly affect energy consumption at the WWTPs because
there would be no new construction or improvements to existing
facilities. It is assumed that energy consumption would
increase at a rate proportional to increases in wastewater
flow. Table 5.63 presents the year 2005 energy consumption
of the Jones Island, South Shore, and local WWTPs, and the
MMSD conveyance system. Of the estimated 2949 billion BTU
(3,111 billion kJ) per year required by this alternative,
natural gas would supply 78%, electricity 10.6%, and digester
gas (used at the South Shore WWTP) 8.5%. The remaining 2.9%
would be supplied by fuel oil and diesel fuel.
Because of the unpredictable rises of energy prices in the
future, an energy cost sensitivity analysis has been prepared.
This analysis evaluates how the cost of operating the sewerage
facilities in the planning area would change if the cost of
one energy source doubled. The analysis was conducted for
each type of fuel used by the sewerage facilities. Increases
in the price of natural gas were found to have the most
serious consequences for the costs of operating sewerage
facilities in the planning area with the No Action Alternative,
A doubling of the price of natural gas would increase the
cost of the energy used by these sewerage facilities by
80.3%.
5-159
-------
TABLE 5.63
NO ACTION ALTERNATIVE
YEAR 2005 ENERGY USE
(Billion BTU)
Facility
Jones Island
South Shore
Local WWTPs
MMSD Conveyance
Total
Electricity
152.01
50.06
105.80
17.32
Natural
Gas
2196.68
52.88
0.0
0.0
Diesel
Fuel
0.0
0.0
6.0
0.0
Fuel
Oil
76.19
0.0
0.78
0.0
Digester
Gas
0.0
249.83
0.0
0.0
Total
2424.58
352.77
112.58
17.32
325.19
2249.56
6.0
76.97 249.83
2907.55
NO ACTION ALTERNATIVE
YEAR 2005 ENERGY COST
($ x 1000)
Facility
Jones Island
South Shore
Local WWTPs
MMSD Conveyance
Total
Electricity
501.5
165.2
349.2
57.2
Natural
Gas
4942.5
119.0
0.0
0.0
Diesel
Fuel
0.0
0.0
17.2
0.0
Fuel
Oil
214.1
0.0
2.2
0.0
Digester
Gas
0.0
0.0
0.0
0.0
Total
5658.2
284.2
368.6
57.2
1073.2
5061.5
17.2
216.3
0.0
6368.2
Electricity:
Natural Gas:
Fuel Oil:
Diesel Fuel:
Digester Gas:
1 kwh = 10,500 BTU
1 Therm = 100 ft = 100,000 BTU
1 gallon = 142,500 BTU
1 gallon = 140,000 BTU
1 Therm = 167 ft = 100,000 BTU
1 BTU =1.06 kilojoule CkJ)
5-160
-------
5.2.12.2 Local Alternative
The energy requirements of the Local Alternative would be
less than those of the No Action Alternative. The reduction
of 23.9.% to 26.4% (depending on the chosen CSO alternative)
would be due primarily to changes in the processes at the
Jones Island WWTP. The facility now uses 2196 billion BTU
of natural gas. Approximately 260 billion BTU of this
amount is lost as waste heat from the sludge drying operation.
The rehabilitation and expansion of the WWTP would eliminate
the Milorganite process as well as the wasted energy associated
with the process. In addition, anaerobic digesters would
be added for sludge processing. The methane that is a by-
product of this process would be converted to energy, significant
ly reducing the need for natural gas.
Table 5.64 compares the energy required for the Local and No
Action Alternatives. Of the estimated 2094 billion BTU
(2209 billion kJ} that would be used each year by the WWTPs
and the MIS system with the Local Alternative, electricity
would supply 58.9% and digester gas (used whenever possible
to operate treatment plants) 34.7%. The remaining 6.4% of
the energy requirement would be supplied by natural gas and
diesel fuel.
A sensitivity analysis was also performed for the Local
Alternative. For this analysis, it was assumed that the
Inline Storage Alternative would be implemented for CSO
abatement and peak wastewater flow control. Energy costs
with the Local Alternative would be most sensitive to variations
in the cost of electricity.
5.2.12.3 Regional Alternative
With the Regional Alternative, energy consumption in the
year 2005 would be reduced between 33.1% and 35.7% (depending
on the chosen CSO alternative) from the requirements with
the No Action Alternative. The reduction in energy use
would result from the elimination of Milorganite production
and the abandonment of local WWTPs. The future energy
requirements are shown in Table 5.65 Of the 1825 billion
BTU ,(1925 billion kJ} that would be used each year by the
Jones Island and South Shore WWTPs and the MIS system,
electricity would supply 53.5% and digester gas 39.5%. The
remaining 7% would be supplied by natural gas, diesel fuel,
and fuel oil.
A sensitivity analysis, assuming the implementation of the
Inline Storage Alternative was performed for the Regional
Alternative. This analysis determined that these energy
costs would be most sensitive to variations in the price of
5-161
-------
TABLE 5.64
LOCAL ALTERNATIVE
YEAR 2005 ENERGY USE (BILLION BTU)
COMPARED TO NO ACTION ALTERNATIVE
Facility
Electricity
Jones Island 735.63
South Shore 192.57
Local WWTPs 262.36
MMSD Conveyance 49.98
CSO/Peak Flow 46.90
Facilities ( !•)
Natural
Gas
0. 0
47. 50
0. 0
0. 0
0. 0
Diesel
Fuel
Fuel
Oil
29.61 0.0
49.42 0.81
0.45 0.0
0.0 0.0
0.0 0.0
Digester
Gas
Total
274.15 1039.39
447.18 737.48
4.47 267.28
0.0 49.98
0.0 46.90
Total No
Action Alt.
2424.88
352.77
112.58
17.32
0 . 0
Total
1287.44
47.50
79. 48
0. 81
725.80 2141.03
2907.55
LOCAL ALTERNATIVE
YEAR 2005 ENERGY COST
COMPARED TO NO ACTION ALTERNATIVE
($ X 100)
Facility
Electricity
Jones Island $2,427.6
South Shore 635.5
Local WWTPs 865 . 8
MMSD Conveyance 164.9
CSO/Peak Flow 154.8
Facilities
Natural
Gas
$ 0
106. 9
0
0
0
Diesel
Fuel
S 84 .
141.
1.
0
0
. 7
, 3
, 3
Fuel
Oil
$ 0
2. 3
0
0
0
Digester
Gas
$ 0
0
0
0
0
Tota
$2 , 512
886
867
164
154
1
. 3
. 0
. 1
. 9
. 8
Total No
Action
$5,658.
284.
368 .
57,
0.
Alt.
2
, 2
6
, 2
, 0
Total 4,248.6 106.9 227.3 2.3 0 4,585.1 6,368.2
Electricity: 1KWH = 10,500 BTU
Fuel Oil: 1 gallon = 142,500 BTU
Digester Gas: 1 Therm = 167 ft3 100,000 BTU
Natural Gas: 1 Therm = 100 ft3 = 100,000 BTU
Diesel Fuel: 1 gallon = 140,000 BTU
1 BTU = 1.06 kilojoule(kJ)
(1) Assumes Inline Storage as the CSO/Peak Flow Facilities Alternative.
For Comparative purposes see Table 5.63.
Source: MWPAP and ESEI
5-162
-------
TABLE 5.65
REGIONAL ALTERNATIVE
YEAR 2005 ENERGY USE (IN BILLION BTU)
COMPARED TO THE NO ACTION ALTERNATIVE
Facility
Jones Island
South Shore
Conveyance
CSO/Peak Flow
Facilities (1)
Total
Electricity
Natural
Gas
735.63 0.0
192.57 47.50
48.20 0.0
46.90 0.0
Diesel
Fuel
Fuel
Oil
29.61 0.0
49.42 0.81
0.0 0.00
0.0 0.0
Digester
Gas
274.15
447.18
0.0
0.0
Total
1039.39
737.48
48.20
46. 90
1023.30
47.50
79.03
0. 81
721.33
1871.98
Total No
Action Alt
2424.58
352.77
17.32
0 . 0
2907.55*
REGIONAL ALTERNATIVE
YEAR 2005 ENERGY COST
COMPARED TO NO ACTION ALTERNATIVE
($ X 1000)
Facility
Electricity
Jones Island $2,427.6
South Shore 635.5
Conveyance 159.1
CSO/Peak Flow 154.8
Facilities
Total
3377.0
Natural
Gas
S 0
106. 9
0
0
Diesel
Fuel
$ 84.7
141. 3
0
0
Fuel
Oil
$ 0
2. 3
0
0
Digester
Gas
5 0
0
0
0
Total
$2,512.3
886 . 0
151.9
154 . 8
Total No
Action Alt
$3,658.2
285.2
365 . 6
57.2
106.9
226 . 0
2. 3
3712 . 2
6368.2
Electricity: 1 KWH = 10,500 BTU
Natural Gas: 1 Therm = 100 ft3 = 100,000 BTU
Fuel Oil: 1 gallon = 142,500 BTU
Diesel Fuel: 1 gallon = 140,000 BTU
Digester gas: 1 Therm = 157 ft = 100,000 BTU
1 BTU = 1.06 kilojoule (kJ)
•Total includes 112.58 BTU for local plants
(1) Inline storage is assumed as the CSO/ Peak Flow Facilities Alternative.
For Comparison see Table 5.63
Source: MWPAP and ESEI
5-163
-------
electricity.
5.2.12.4 Mosaic Alternative
The Mosaic Alternative would have energy requirements very
similar to the Regional Alternative. The only difference
would be that the South Milwaukee WWTP would require 22.68
billion BTU (23.93 billion kJl for operation C82% of which
would be electricityl, compared to 3.8 billion BTU (4.0
billion kJ) for connection to the MMSD system. Table 5.66
outlines the detailed energy requirements of the Mosaic
Alternative.
The energy requirements outlined above for the Local, Regional,
and Mosaic Alternatives have all assumed implementation of
the Inline Storage Alternative. If another of the final
four CSO abatement/peak wastewater flow control alternatives
were selected, the total energy requirements of each system-
level would change. Table 5.67 shows the annual energy
requirements of each of the four alternatives and how their
energy requirements affect the total system-level requirements
of the Local, Regional,and Mosaic Alternatives.
A detailed discussion of energy requirements for the various
components of the Local, Regional, and Mosaic Alternatives
may be found in Appendix II, Jones Island; Appendix III,
South Shore; Appendix V, Combined Sewer Overflow; Appendix
VI, Local Alternatives; and Appendix VIII, Interceptor
Alignment.
5.2.13 Resource Consumption
None of the Final Alternatives would affect mineral resources
in the planning area.
5.2.13.1 No Action Alternative
Wastewater treatment plants consume the major portion of all
resources used by sewerage facilities in the planning area,
including chemicals for phosphorus control, sludge thickening,
and disinfection. The resources consumed in the conveyance
system are negligible. The resource consumption of the No
Action Alternative was calculated by adjusting exisitng
consumption fay the expected future wastewater flows. Quantities
required are detailed in Table 5.68.
5.2.13.2 Local Alterantive
Resource requirements for the operation of 8 public and 2
private treatment plants included in the Local Alternative
are detailed in Table 5.69. It is assumed that conveyance
5-164
-------
TABLE 5.66
MOSIAC ALTERNATIVE
YEAR 2005 ENERGY USE (BILLION BTU)
COMPARED TO THE NO ACTION ALTERNATIVE
Natural
Facility
Jones Island
South Shore
South Milwaukee
Conveyance
CSO/Peak Flow
Facilities
-------
TABLE 5.67
ANNUAL ENERGY REQUIREMENT
CSO/PEAK FLOW STORAGE ALTERNATIVES
Complete
Sewer Inline Modified CST/
Separation Storage Inline Storage
Electricity 4.30 4.47 9.29
(106 KWH)
Diesel Fuel ~ ~ 1350.00
(Gallon)
Equivalent Energy 45.05 46.90 97.73
(109 BTU)
Local Total 2139.18 2141.03 2191.86
Modified Total
Storage
11.30
1700.00
118.91
2213.04
(109 BTU)
Regional Total
(109 BTU)
Mosaic Total
(109 BTU)
1870.12
1888.60
1 BTU= 1.06 Kilojoule (KJ)
Source: MMSD
1871.97
1890.45
1922.80
1941.28
1943.98
1962.46
5-166
-------
TABLE 5.63
TREATMENT PLANT RESOURCE CONSUMPTION
NO ACTION - YEAR 2005
Pickle
Ferric Liquor
Polymer Chloride T/yr
T/yr T/yr
Caddy Vista
Muskego NE
Muskego NW
N.B. Regal Manors
Germantown
Thiensville
School Sisters of Notre
Dame
WEPCO
South Milwaukee
Jones Island
South Shore
TOTAL
NA
NA
NA
49
NA
49
0.8 —
00
NA
1771.5 —
1771.5 1825.0
NA
1825.0
as Fe
NA
52.0
49.2
94.7
00
NA
1825.0
1478.3
Chlorine
T/yr
NA
3.3
3.2
11.2
6.9
2.3
0.2
0.6
NA
912.5
522.8
3499.2 1463.0
T = Tons
5-167
-------
and CSO facilities would expend no significant resources.
Materials required for construction cannot be quantified
because the plans are not specific enough at this time.
Massive amounts of concrete and reinforcing steel would be
required to construct the proposed facilities.
5.2.13.3 Regional Alternative
With the Regional Alternative, the Jones Island and South
Shore WWTPs would treat all wastewater flows in the planning
area. As a result, the annual consumption of alum, ferric
chloride and polymer would be reduced. The consumption of
pickle liquor and chlorine would increase from the No Action
Alternative. Table 5.70 compares the resource consumption
of the final alternatives.
5.2.13.4 Mosaic Alternative
The Mosiac Alternative is also similar to the Local Alter-
native except that only the Jones Island, South Shore, South
Milwaukee, WEPCO, and School Sisters of Notre Dame WWTPs
would be in operation.
A comparison of resource consumption with the Local, Regional,
and Mosaic Alternatives can be found in Table 5.70.
5.2.14 Engineering Feasibility
5.2.14.1 No Action Alternative
The MMSD projected the flows that would be conveyed to each
WWTP in the planning area in the year 2005, assuming that
the growth forecasted by SEWRPC would occur. Analysis of
each public wastewater treatment facility in the planning
area was performed to determine its ability to treat these
projected wastewater flows. The WWTPs were evaluated for
hydraulic capability and ability to meet the tentative WPDES
effluent limits set by DNR.
To determine hydraulic capacity, average daily base flows
(ADBF) and maximum flows to each WWTP were reviewed. For
each WWTP, the current average hydraulic capacity of each
WWTP was compared to the ADBF projected over the planning
period. It was determined by this evaluation that only four
public treatment facilities would have the capacity to
adequately treat year 2005 projected daily flows. These are
the Jones Island, South Shore, South Milwaukee, and Caddy
Vista WWTPs.
5-168
-------
TABLE 5.68
RESOURCE CONSUMPTION YEAR 2005
Ferric Pickle Act. Fly Sulfur
Local System Alum Polymer Chloride Liquor Carbon Lime Ash Chlorine Dioxide
Level Alternative T/yr T/yr T/yr T/yr as Fe Ib/yr T/yr T/yr T/yr T/yr
Caddy Vista 1.4
Muskego NE 24.1
New Berlin SE 65,6
Germantown 30.9
Thiensville 143 0.358 5.7
Sisters of Notre
Dame _ 0.5
WEPCO 1.2
South Milwaukee 4.4 338 36,5
Jones Island 290 2400 1697 2860 9500 6700 1055 352
South Shore 510 3030 2860 700 350
Conveyance Systems
(includes MMSD
collection
system)
CSO System
TOTALS 143 800 2738 4727 572C 9500 6700 1900 702
Regional System Level
Alternative
Jones Island 290 2400 1697 2860 9500 6700 1055 352
South Shore 510 3030 2860 700 350
Conveyance Systems
(includes MMSD
collection
system)
CSO System
TOTALS 0 800 2400 4727 5720 9500 6700 1755 702
Preferred System
Level Alternative
Sisters of Notre
Dame 0.50
WEPCO 1.20
South Milwaukee 4.4 338 36.5
Jones Island 290 2400 1697 2860 9500 6700 1055 352
South Shore 510 3030 2860 700 350
Conveyance System
(includes MMSD
collection
system)
CSO System
TOTALS 0 804 2738 4727 5720 9500 6700 1793 702
5-169
-------
The analysis of ADBF of a WWTP does not reflect the over-
loading that can occur during wet weather. The second
analysis compared present and year 20.05 maximum daily flow
to each plant's peak hydraulic design capacity. This
evaluation indicated that the South Milwaukee WWTP would be
the only treatment facility in the planning area that would
be able to adequately treat year 2005 maximum daily wastewater
flows.
The DNR has set tentative effluent limits for the planning
period. The future limits are equal to, or more stringent
than current limits, and the only existing WWTPs that have
the equipment necessary to meet them are the South Shore,
Jones Island, South Milwaukee, and Thiensville WWTPs.
However, Jones Island, South Shore, and Thiensville would
have overloading problems during wet weather that would lead
to inadequate sewage treatment and effluent violations. The
South Milwaukee plant has the hydraulic capacity to treat
year 2005 maximum flows, but problems in facility operation
could result in occasional violations.
In addition, portions of the MMSD conveyance system are in
disrepair. The failures of this system greatly contribute
to the MMSD's infiltration and inflow problems. With the No
Action Alternative, these sewers would continue to deteriorate
throughout the planning period, thereby increasing the total
volume of wastewater in the system and further taxing treatment
facilities.
The eight private WWTPs that would operate under the No
Action Alternative were also evaluated. Five of the WWTPs
would not have the equipment to meet tentative future standards:
the Cleveland Heights Grade School in New Berlin, New Berlin
Memorial Hospital, the Chalet-on-the-Lake Restaurant in
Mequon, the Highway 100 Drive-in Theater, and St. Martins
Road Truck Stop in Franklin. Only three private treatment
facilities; Wisconsin Electric Power Company CWEPCO) in Oak
Creek, the School Sisters of Notre Dame in Mequon, and the
Muskego Rendering Company, are meeting their current limits.
Although the WWTP at the Muskego Rendering Company has
recently expanded its hydraulic capacity to 83,000 gallons
(314 m ) per day, the plant discharges its effluent to
absorption ponds that have a capacity of only 25,000 gallons
C95 m3) per day. The ponds are adequate for present discharge
rates, but flows to the WWTP are expected to double during
the planning period. With the No Action Alternative, the
absorption ponds would be hydraulically overloaded. Effluent
limits could also be violated due to high influent BOD.
Only the WEPCO and School Sisters of Notre Dame treatment
facilities would be able to treat future wastewater loadings
adequately to meet the stringent year 2005 effluent limits.
5-170
-------
5.2.14.2 Local Alternative
Although, the first phase of facilities planning does not
include actual design of sewerage facilities, a preliminary
evaluation was made of the technical feasibility of the
alternatives. This evaluation included an investigation of
whether the techniques included in the alternative had been
used successfully in other cities and what the consequences
of a system breakdown would be. Basically, all the alter-
natives that survived preliminary screening could be implemented
successfully. In evaluating the technical feasibility of an
alternative, several assumptions had to be made. These
assumptions are listed below.
1. All critical components would be provided with backup
equipment for use during maintenance procedures and in
the event of the component's failure.
2. All facilities would be equipped with a secondary power
supply that could be used if a power failure occurred.
3. Critical components would be equipped with protective
mechanisms that would relieve them in case flows increase
beyond peak capacity.
4. Maintenance procedures and schedules would be developed
and followed for all equipment. These procudures would
include periodic inspections of all equipment and
structures.
The Local Alternative would include the operation of the
Jones Island and South Shore WWTPs and six smaller WWTPs.
The Jones Island and South Shore WWTPs would continue to
treat the majority of the wastewater flows in the planning
area. The basic treatment processes at these WWTPs have
been proven feasible.
The other treatment plants in the planning area would be
much smaller in capacity, most less than 10 MGD (0.44 nr/sec).
These facilities would use either the activated sludge
process or land application of effluent by infiltration-
percolation. The activated sludge process has been widely
used and is a proven wastewater treatment technique. If the
facilities are properly designed and constructed, the process
could be used successfully. Because activated sludge treatment
uses biological organisms, flows should be fairly constant.
Dramatic increases or decreases in flows could destroy the
biological communities.
5-171
-------
Land application has been proposed at the Muskego Northeast,
New Berlin Southeast, and Germantown WWTPs. The infiltration-
percolation technique has been used successfully for many
years in climates similar to Wisconsin's. The sites for
these ponds should be carefully selected based on soil
quality and the depth to groundwater.
The conveyance system required by the Local Alternative
would include gravity sewers and force mains. Gravity
sewers do not require pumps for conveyance of wastewater
flows. They are the most reliable means of conveying
wastewater. If properly designed and constructed,gravity
sewers would require little maintenance and would have a
long service life. No difficult or innovative construction
techniques would be required to install gravity sewers.
Force mains would also be constructed to implement the Local
Alternative. This type of sewer requires pump stations and
pressure resistant force mains. Pump stations should be
equipped with multiple pumps for use during maintenance
procedures, for emergency back up, and for peak flow demand.
The pump stations and force mains would require more maintenance
than gravity sewers.
The Complete Sewer Separation Alternative for abatement of
CSO would require separation of building plumbing systems.
The separation could cost up to $4,000 per house, and this
cost might have to be borne by the property owner (pending a
ruling on a MMSD legal staff opinion that this cost would be
borne by MMSD). Property owners may be reluctant to spend
that amount of money. Also, the inspection of all buildings
to ensure that they are adequately separated would be difficult.
Many of the buildings in the CSSA are older structures, and
care should be taken to preserve their structural integrity.
All the other proposed CSO and peak flow storage alternatives
would require tunnelling in both deep rock formations and in
the softer, surficial glacial deposits. Deep rock deposits
are generally dolomite, a limestone-like substance. While
the dolomite is impervious, fissures in the rock structure
can convey large amounts of groundwater. Lining of tunnels
would be required but may prove unnecessary depending on the
structural quality of the bedrock. Generally, the dolomite
is a good construction medium with minimal need for structural
bracing during construction.
Soft ground tunnels would involve more risk; tunnelling
could degrade the structural quality and bearing capacities
of upper layers of the geologic strata which could lead to
the settling of buildings, the disruption of utilities,
cracking of pavement, and, in extreme cases, the collapse of
5-172
-------
buildings and streets. Extreme caution would be necessary
for this type of construction, especially in highly urban
areas.
The proposed subsurface construction would create large
volumes of spoil materials. Table 5.70 gives a comparative
approximation of the amount of spoil that would be generated
by different alternatives. Disposal of such large amounts
of material would require a well designed disposal system.
The MMSD has tentatively identified four options for spoil
disposal and utilization: MMSD use, public projects, marketing,
and disposal.
MMSD use of spoil material is limited by the court-ordered
construction schedule of the various components of the MFP.
Using spoil material for the initial lakefilling at the
Jones Island and South Shore WWTPs is not feasible because
any lakefill that might occur at these WWTPs would be
necessary prior to the major deep rock tunnel and cavern
construction that would supply most of the spoil material
generated by the MFP. However, the MMSD has identified the
additional 18 acres of lakefill which the MMSD has proposed
for possible future plant expansion as the optimum alter-
native for spoil disposal. MMSD preference for this alter-
native is largely due to the size of its fill requirement
C355,000 cubic yards), its freedom from scheduling constraints,
and the fact that both crushed dolomite and overburden could
be used. However, there is no guarantee that this additional
18 acre lakefill will be necessary or approved. Other
potential MMSD uses for the crushed dolomite include bankfill
material and a concrete aggregate. In order to use the
excavated dolomite for these purposes, it would have to be
processed by crushing and screening.
Potential public projects which could utilize MMSD spoil
material include Milwaukee Department of City Development
plans to expand the Summerfest grounds and Milwaukee County
Park Commission plans for filling lakefront areas between
Bender Park and South Shore Park. Schedules for these
projects are compatible with MMSD excavation schedules.
However, these projects are still in the planning stage.
Required funds and permits have not been obtained at this
time.
Sale of the mineral dolomite to local quarry companies would
be possible if the dolomite could not be used by the MMSD or
by public projects. After processing, the dolomite could
be used as construction aggregate, roadstone, railroad
ballast, fill, and agricultural lime. Local quarry com-
panies have expressed interest in purchasing the dolomite.
5-173
-------
TABLE 5.70
SPOIL MATERIAL GENERATED
(XlO cubic yards)
1)
Alternative
Rock
2)
Overburden
Total
Complete Sewer 1.534
Separation
Inline Storage 2.876
Modified CST/ 5.402
Inline Storage
Modified Total 5.402
Storage
6.920
7.368
3.324
4.977
8.454
10.244
8.726
10.379
1) Includes spoil material generated for CSO abatement and peak
wastewater control alternative assuming a 48% level of I/I
reduction. Should conditions arise which cause the storage
volumes to change, as outlined in Chapter 3, Section 3.9,
the volume of spoil material would change.
2) Assumes a 1.2 expansion factor from the in-situ to the
excavated state.
Note: Where excavated material meets design specifications,
it may be used as backfill material.
Source: MMSD Draft Inline Storage Facility Plan, 1981. and
ESEI, 1981.
5-174
-------
Transportation costs and the potential for oversupplying the
local market are problems with this option. Quarry operators
in Chicago have indicated during telephone conversations
with the MMSD that the sale of dolomite from the Tunnel and
Reservoir Project (TARPl has influenced quarry operations in
the Chicago area. Much of the excavated dolomite from TARP
has been bought by quarry companies, stockpiled, and filtered
into the local market slowly to help maintain a stable
market. Nevertheless, some reductions in quarry operations
have occurred.
It is possible that an oversupply of mined rock could also
reduce operations and employment in Milwaukee area quarries.
However, stockpiling and the greater than normal demand for
aggregate due to MMSD construction requirements should minimize
these impacts. A possible benefit of marketing the crushed
dolomite would be the extension of life of existing quarries.
If none of the above uses of the excavated dolomite or re-
moval overburden are possible, direct disposal would be
necessary. Chapter NR 180 of the Wisconsin Administrative
Code governs solid waste management procedures in Wisconsin.
Specifically, any disposal operations must be operated in a
"nuisance-free and aesthetic manner" and must avoid areas
within wetlands, critical habitat areas, and areas in which
operation may be detrimental to surface water or groundwater
quality. Several inactive quarries in the Milwaukee area
have been identified as possible disposal sites. Any selected
disposal site would have to be approved by the DNR.
Regardless of how the excavated spoil is ultimately used or
disposed of, it is very likely that temporary stockpiles at
worksites or central storage areas would be necessary.
These stockpiles would have to meet the requirements of
section NR 180.07, "Storage Facility Requirements."
The availability of some construction material may be severely
limited. Concrete, for example, is in short supply. In
1979, the U.S. had to import 11% of the year's demand for
concrete. The deterioration of concrete producing equipment
will offset capacities created by new construction of production
facilities. Present concrete production capacity in the
U.S. is projected to be 80 million tons C73 million metric
tonsl annually CENR - 6/19/801. Table 5.71 is a summary of
the concrete required for construction of most of the components
for CSO and peak flow storage. As can be seen, the concrete
requirements of the MFP would in some cases be in excess of
1% of the national annual concrete production.
5-175
-------
TABLE 5.71
CONCRETE REQUIREMENTS
CSO/PEAK FLOW ALTERNATIVES **
Concrete Required (1)
Alternative Cubic Yards Ton*
Complete Separation 261,538 529,615 (0.66%)
Inline Storage 402,589 815,242 (1.02%)
Modified CST/Inline 390,288 790,333 (0.99%)
Modified Total Storage 396,840 803,602 (0.71%)
1/2 yr. LOP Inline 282,442 571,946 (0.71%)
* Parenthetical numbers reflect percentage of U.S. Annual
Concrete Production Capacity.
** Reflects requirements of sewer construction, deep tunnels,
drop shafts, storage caverns, near-surface collection and
storage silos. Control structures, screening facilities,
drop shaft energy disapation chambers, connections to caverns,
and outfall work are not included.
(1) Requirements based upon the assumption of 48% removal of I/I.
Should conditions arise which cause the storage volume to
change as outlined in Chapter 3, Section 3.9, these require-
ments would change accordingly.
Source: MMSD and ESEI
5-176
-------
5.2.14.3 Regional Alternative
A preliminary analysis was also performed to evaluate the
technical feasibility of the components of the Regional
Alternative. The analysis of the technical feasibility of
the Regional Alternative used the assumptions that were
discussed for the Local Alternative: critical components
would be provided with backup equipment, all facilities
would be equipped with a secondary power supply in case of a
power failure, critical components would be equipped with
relief devices, and proper maintenance and inspection
procedures would be followed.
With the Regional Alternative, all WWTPs in the planning
area, except Jones Island and South Shore, would be abandoned.
The wastewater flows that had been treated at the abandoned
WWTPs would instead be conveyed to either the Jones Island
or South Shore facilities. Since the flows from the abandoned
WWTPs would increase flows to Jones Island and South Shore
by only 5%, the processes proposed for the Local Alternative
could successfully treat the increased capacity.
The wastewater flows from all abandoned WWTPs except Thiensville
and Caddy Vista would be diverted to new or existing intercepting
sewers. The sewers connecting the abandoned treatment
facilties to the interceptors would either be gravity sewers
or force mains. Both conveyance systems are feasible,
although force mains would require more maintenance and
backup power sources. Most interceptors would be gravity
sewers.
The wastewater flows from the Thiensville WWTP would be
conveyed to the Northwest Side Relief System. The sewers
included in this proposed system would be designed to
incorporate the flows from the Thiensville WWTP as well as
the other flows in the system's service area.
The sewage flows from the abandoned Caddy Vista WWTP would
be connected to a local sewer system in the southern part of
the City of Oak Creek. The local sewer system could adequately
handle these increased flows until late in the planning
period.
5.2.14.4 Mosaic Alternative
Because the Mosaic Alternative is so similar to the Regional
Alternative, the issues of technical feasibility are the
same. The difference between the two alternatives would be
the operation of the South Milwaukee, School Sisters of
Notre Dame, and WEPCO wastewater treatment facilities. An
5-177
-------
appraisal of these facilities (see Chapter III), indicated
that they could meet future WPDES permit standards without
bypassing. Therefore, these facilities are considered
technically feasible.
5.2.15 Legality
The planning for the MFP has been guided by a number of
legal requirements, the most significant of which are EPA
and DNR regulations, the U.S. District Court Order, and the
Dane County Court Stipulation. With the Local Alternative,
several individual communities or sanitary districts—
Thiensville, Germantown, New Berlin, Musekgo, Caddy Vista,
and South Milwaukee — would operate their own WWTPs.
Accordingly, they would not be under the requirements of the
U.S. District Court Order or the Dane County Stipulation,
although the MMSD would still have to meet those requirements.
Other legal issues affect all local system-level actions.
These are discussed below for each designated management
agency.
5.2.15.1 MMSD
With any final alternative, the MMSD would be responsible
for four components of the MFP: the operation of the Jones
Island and South Shore WWTPs, the construction of CSO and
I/I abatement facilities, the construction of expansion and
relief sewers, and the development of a solids disposal
program. The MFP evaluated a variety of alternatives to
select the final Local System-Level Alternative that would
meet both the Dane County and U.S. District Court require-
ments and all other Federal, State, and local laws.
The key requirement of the U.S. District Court Order is the
elimination of all dry and wet weather bypassing in the
MMSD. All discharges of "human fecal waste from the com-
bined sewer system must be eliminated with provision of
storage for the largest storm on record since 1940." Any
overflows caused by a storm of greater magnitude must receive
primary treatment and disinfection before discharge.
Bypassing must be eliminated at the WWTPs, and the treatment
plant effluent must meet limitations stricter than EPA and
DNR requirements.
MMSD appeals of this court order have lessened these re-
quirements. On April 26, 1979, the Federal Court of Appeals
in Chicago rejected the stringent effluent limits and substituted
the DNR secondary effluent limits. On May 1, 1980, the U.S.
Supreme Court issued a stay of the District Court and Court
of Appeals rulings pending the final ruling on the case
which will likely occur in 1981.
5-178
-------
With the stay of the U.S. District Court Order, the Dane
County Court Stipulation establishes the legal requirements
for the MFP. The Dane County Stipulation essentially sets a
schedule for actions required in order for MMSD to meet
existing EPA and DNR regulations. There are four requirements
the MFP must comply with: WPDES effluent limitations must
be met at all WWTPs; dry and wet weather overflows from the
separated sewer areas must be eliminated; a cost effective
means of abating CSO and meeting applicable water quality
standards must be determined; and a solids management program
must be developed.
The components of the action alternatives have been developed
to meet all of the requirements of both the U.S. District
Court Order (as modified by the Court of Appeals) and the
Dane County Court Stipulation. The recommended CSO Alter-
native would eliminate overflows up to the storm of record
for the District Court Order and could be modified to a
level to meet applicable water quality standards for the
Dane County Court Stipulation, if the Supreme Court rules in
favor of the MMSD. See Chapter 3, Section 3.9 for a discussion
of alternatives to meet DNR water quality standards.
Two legal issues remain. The first is the District Court
requirements for primary treatment and disinfection of any
overflows that occur from a storm greater than the storm of
record. The Inline Storage Alternative would separate
combined sewers in the public right-of-way, thus reducing
CSO volumes by 70% and limiting possible inflow from the
remainder of the CSO system. The MMSD has recommended that
screening and chlorination facilities not be built because
the possibility of overflows is remote. If this portion of
the District Court Order is upheld by the Supreme Court, the
MMSD would have to approach the District Court for a ruling
on the screening facilities.
A second question arises regarding the achievement of water
quality standards required by the Dane County Court Stipu-
lation. No MFP alternative alone would achieve these water
quality standards Csee Appendix VII, Water Quality). The
DNR must determine whether the MMSD has to undertake further
analysis of alternatives to achieve these standards or
whether the issue of water quality standards could be delayed
until completion of the planning stages of the MFP.
The remainder of the MMSD actions would meet EPA and DNR
regulations and the two court requirements. Both Jones
Island and South Shore would meet their WPDES permit ef-
fluent limits. Dry weather bypassing would be eliminated
throughout the MMSD service area. Wet weather bypassing
would be eliminated in the separated sewer area. Also, the
5-179
-------
construction of facilities would proceed under the schedule
imposed by the Courts.
Other executive orders and legislation establishing federal
policies on wetlands, floodplains, and the protection of the
cultural environment have also affected the development of
the final alternatives. These issues have been addressed in
separate sections of this Chapter.
5.2.15.2 Local Agencies
With the Local Alternative, Thiensville, Germantown, New
Berlin, Muskego, and Caddy Vista would operate local WWTPs
during the planning period. The Regional 208 Plan would
have to be amended to incorporate these five communities as
"designated management agencies" for treatment of sanitary
sewage. Currently, only the MMSD and South Milwaukee have
been so designated within the planning area.
As designated management agencies, each of the local communities
would be required to prepare a facilities plan addressing
specific issues of their proposed treatment facilities.
Specific treatment alternatives would be developed and
analyzed for cost effectiveness and possible impacts to the
natural and man-made environments, as required by EPA and
DNR regulations. The selected treatment alternative would
have to meet WPDES effluent limits and conform to all other
Federal, State, and local laws and regulations.
The treatment alternatives for the local communities analyzed
as part of the MFP have been identified only as feasible
concepts. If the concept is found to be part of the cost-
effective, environmentally sound solution to the existing
water pollution problems, it would undergo further legal
analysis as part of a specific rigorous facilities plan and
environmental assessment.
5-180
-------
ATTACHMENT A
MEMORANDUM OF AGREEMENT
JONES ISLAND WWTP - WEST PLANT
-------
Advisory
,
Council On ,
Historic P r
Preservation
1522 K Street, NW
Washington. DC 20005
33 1981
Mr. Charles H. Sutfin
Director, Water Division
Environmental Protection Agency
Region V
230 South Dearborn Street
Chicago, IL 60604
Dear Mr. Sutfin:
Enclosed is the Memorandum of Agreement reflecting the agreement to
mitigate the adverse effects of the Treatment Facilities Improvement
Project in Milwaukee, Wisconsin, on the Jones Island West Plant reached
by the consulting parties.
Please sign and date this agreement and forward it to Richard A. Erney,
Wisconsin State Historic Preservation Officer, for his dated signature.
Thereafter, it must be returned to the Council for ratification by the
Chairman. The agreement will become final 30 days after receipt by the
Chairman or earlier if ratified by the Chairman.
The ratified Memorandum of Agreement will constitute the Council's
comments in accordance with Section 800.6(c)(3) and completes your
responsibilities under Section 106 of the National Historic Preservation
Act and the Council's regulations.
Thank you for your cooperation.
Sincerely,
A* c v>^vwro..k
Jordan E. Tannenbaum
Chief, Eastern Division
of Project Review
Enclosure
-------
Advisory
Council On
Historic
Preservation
1522 K Street, NW
Washington, DC 20005
MEMORANDUM OF AGREEMENT
WHEREAS, the Environmental Protection Agency (EPA), proposes to provide
funding for the improvement of sewage treatment facilities in Milwaukee,
Wisconsin; and,
WHEREAS, EPA, in consultation with the Wisconsin State Historic Preservation
Officer (SHPO), has determined that this undertaking as proposed would have
an adverse effect upon the Jones Island West Plant, a property eligible for
the National Register of Historic Places; and,
WHEREAS, pursuant to Section 106 of the National Historic Preservation
Act of 1966 (16 U.S.C. Sec. 470f, as amended, 90 Stat. 1320), and Section
800.4(d) of the regulations of the Advisory Council on Historic Preservation
(Council), "Protection of Historic and Cultural Properties" (36 CFR Part
800), EPA has requested the comments of the Council; and,
WHEREAS, pursuant to Section 800.6 of the Council's regulations,
representatives of the Council, EPA, and the Wisconsin SHPO have consulted
and reviewed the undertaking to consider feasible and prudent alternatives
to avoid or satisfactorily mitigate the adverse effect;
NOW, THEREFORE, it is mutally agreed that implementation of the undertaking
in accordance with the following stipulations will satisfactorily mitigate
adverse effect on the above-mentioned property.
Stipulations
EPA will ensure that the following measures are carred out.
1. Prior to any demolition or alteration of the Jones Island West Plant,
EPA will record the Jones Island West Plant so that there will be a
permanent record of the history and present appearance of the Plant
and sewage treatment process. EPA, in consultation with the Wisconsin
SHPO, will first contact the National Architectural and Engineering
Record (NAER) (Lake Central Region, Federal Building, Ann Arbor,
Michigan 48107), to determine what documentation is required. All
documentation must be accepted by NAER and the Council notified of its
acceptance, prior to any demolition or alteration. EPA will also
provide copies of this documentation to the Wisconsin SHPO, Milwaukee
Metropolitan Sewerage District Archives, and the Milwaukee Historical
Society.
-------
Page 2
Memorandum of Agreement
Environmental Protection Agency
Jones Island West Plant
2. In cooperation with the Wisconsin SHPO, EPA will prepare a brochure
based on the information in the above referenced documentation. This
brochure will document the significance of the Jones Island West Plant
and will be made available to the general public.
T
3. Final plans for the proposed improvements will be developed in consultation
with the Wisconsin SHPO to ensure that, to the fullest extent possible,
portions of the Jones Island West Plant which can feasibly be retained
will be retained and reused as part of the improved facilities.
4. Plans and specifications for any rehabilitation work needed for buildings
to be retained will be developed in consultation with the Wisconsin
SHPO and will be consistent with the recommended approaches in the
Secretary of the Interior's "Standards for Rehabilitation."
5. Prior to any alteration or demolition of the Jones Island West Plant
the Wisconsin SHPO, or his designee, the Milwaukee Historical Society
will be given a reasonable opportunity to select architectural elements
from the buildings or portions of buildings that will be lost through
demolition or alteration for curation or use in other projects. EPA
will be responsible for ensuring the careful removal of these elements
and will deliver them without cost to the SHPO or the Milwaukee Historical
Society. The Wisconsin SHPO will notify the Council when all selected
architectural elements have been salvaged.
6. Within 90 days after completion of the project, EPA will notify the
National Register of any changes in the Jones Island West Plant so
that the records of this eligible property may be kept current.
7. Failure to carry out the terms of this Agreement requires that EPA
again request the Council's comments in accordance with 36 CFR Part
800. If EPA cannot carry out the terms of the Agreement, it shall not
take or sanction any action or make any irreversible commitment that
would result in an adverse effect with respect to National Register or
eligible properties covered by the Agreement or would foreclose the
Council's consideration of modifications or alternatives to the
proposed Treatment Facilities Improvement that could avoid or mitigate
the adverse effect until the commenting process has been completed.
8. If any of the signatories to this Agreement determine that the terms
of the Agreement cannot be met or believes a change is necessary, that
signatory shall immediately request the consulting parties to consider
an amendment or addendum to the Agreement. Such an amendment or
addendum shall be executed in the same manner as the original Agreement.
9. Within 90 days after carrying out the terms of the Agreement, EPA
shall provide a written report to all signatories to the Agreement on
the actions taken to fulfill the terms of the Agreement.
Executive
Advisory Council on Historic Preservation
-------
Page 3
Memorandum of Agreement
Environmental Protection Agency
Jones Island West Plant
Environmental Prota^ion Agency
(date)
Wisconsin State Historic Preservation Off:
(date)
Chairman
Advisory Council on Historic Preservation
-------
GLOSSARY
-------
GLOSSARY
Activated Sludge: Sludge floe produced in raw or settled
wastewater by the growth of zoogleal bacteria and
other organisms in the presence of dissolved oxygen
and accumulated in sufficient concentration by returning
floe previously formed.-'-
Acute Toxicity: Any toxic effect produced within a short period
of time, usually up to 24-96 hours, resulting in severe
biological harm and often death.^
Ad Valorem: A tax or duty levied in the form of percentage
of value of property.
ADBF: Average Daily Base Flow.
Aeration: The bringing about of intimate contact between air
and a liquid by one or more of the following methods:
(a) spraying the liquid in the air, (b) bubbling air
through the liquid, (c) agitating the liquid to promote
surface absorption of air.l
Aerated Lagoon: A natural or artificial wastewater treatment
pond in which mechanical or diffused-air aeration is
used to supplement the oxygen supply.-'-
Aerobic: Requiring, or not destroyed by, the presence of
free elemental oxygen.1
Algae: A class of plants, including single cell plants and
common sea weeds. ^-^
Allocation System: Section of the Dane County stipulation
requiring that the MMSD and the DNR, "establish rules
and regulations to restrict the amount of wastewater
discharged to the sewerage system of the District
each year."^
Anaerobic: Requiring, or not destroyed by, the absence
of air or free (elemental) oxygen.^
Annual Capital Expenditures: The dollar amount of bonds
assumed to be issued annually to finance MMSD
improvements.
-------
Aquifer: A porous, water-bearing geologic formation,
generally restricted to materials capable of yielding
an appreciable supply of water.
Basic Industry: Firms serving markets outside the area of
their location (exporting products).
Benthos: The plant and animal life whose habitat is the
bottom of a sea, lake or river.9
Biochemical Oxygen Demand (BOD): The quantity of oxygen
used in the biochemical oxidation of organic matter
in a specified time, at a specified temperature, and
under specified conditions. (2) A Standard test
used in assessing wastewater strength.
Biodegradable: The process of decomposing quickly as a
result of the action of microorganisms.9
BOD: Biochemical Oxygen Demand.
Bypass: Diversion of untreated wastewater from a sewage
facility into a body of water, or to the effluent
channel of a wastewater treatment facility.
CFS: Cubic Feet per Second.
Chlorination: The application of chlorine to drinking water,
sewage, or industrial waste for disinfection or
oxidation of undesirable compounds.
Chronic Toxicity: Any toxic effect which causes poisonir.g,
death or damage to an organism by prolonged exposure
which may range -from several days to weeks, months, or
years.^
Clarifiers: A unit of which the primary purpose is to
reduce the concentration of suspended matter in a
liquid. Usually applied to sedimentation tanks or basins.
Combined Sewer: A sewer intended to receive both wastewater
and storm or surface water.
Construction Grants Program: Section 208 of PI 92-500 creates
a funding program for improvements to municipal waste-
water treatment facilities.
CSO : Combined Sewer Overflow.
CSSA: Combined Sewer Service Area.
DATCP: Wisconsin Department of Agriculture, Trade and
Consumer Protection.
BCD. Milwaukee Department of City Development.
ii
-------
Debt Limit: The maximum amount of debt that a governmental
unit may incur under constitutional, statutory, or
charter requirements. The limitation is usually a
percentage of assessed valuation.
Debt Service: Principal plus interest that a bond issuer
pays the bond buyer over the maturity period of the
bond(s).
DNR. Department of Natural Resources (Wisconsin).
DOA: Department of Administration (Wisconsin).
Draw Down Effect: A lowering of groundwater levels due to
pumping.
Dry Industry: Industry that does not use or discharge large
quantities of water.
Effluent: Wastewater or other liquid, partially or completely
treated, or in its natural state, flowing out of a
reservoir, basin, treatment plant, or industrial treatment
plant, or part thereof.1
EIS: Environmental Impact Statement.
Emergent Plants: Plants anchored below water level and
growing above water level, such as a rush or cattail.
Equalized Property Value: The full market value of property
as determined by the Wisconsin Department of Revenue,
Bureau of Property Tax.
EPA: Environmental Protection Agency (U.S.).
Eutrophication: The normally slow aging process by which a
lake evolves into a bog or marsh and utimately assumes
a completely terrestrial state and disappears. During
eutrophication, the lake becomes so rich in nutritive
compounds, especially nitrogen and phosphorus, that
algae and other microscopic plant life become super-
abundant, thereby choking the lake.^
Exporting Industry: Firms serving markets outside the area
of their location (exporting products).
Facilities Plan: Section 208 of PL 92-500 provides funding
for the planning of municipal wastewater treatment.
These planning documents (such as the MWPAP) are
facilities plans.
Fauna: Animal life.
iii
-------
Fiscal Impact Analysis: An evaluation of the net public costs
or revenues resulting from actual or planned growth.2
Flow Augmentation: The increase in stream flow by artificial
means.
FNSI: Finding of No Significant Impact.
Forage Fish: Non-game fish such as the common shiner and
fathead minnow.
General Obligation Bond (G.O. Bond): Validaly issued and
legally binding evidence of indebtedness secured by
the full faith, credit and taxing powers of the
issuer.7
Glacial Drift: A general term for all types of glacial
deposits.3
Grit Chamber: A dentention chamber or an enlargement of a
sewer designed to reduce the velocity of flow of the
liquid to permit the separation of mineral from organic
solids by differential sedimentation.
Groundwater: The supply of freshwater under the earth's
surface in an aquifer or soil that forms the natural
reservoir for Man's use.
Hydraulic Head: (1) The height of a column of fluid necessary to
develop a specific pressure. (2) The pressure of water at
a given point in a pipe arising from the pressure in it.H
Hydrocarbon: Any of the class of compounds consisting
solely of carbon and hydrogen.
Hydrology: The science dealing with the properties, distribution,
and circulation of water and snow.9
I/I: Infiltration and Inflow.
Igneous Rocks: Rocks that crystallize from a melt within,
Or at the surface of the earth.^
Indirect Fiscal Impacts: The revenues and costs to a community
associated with growth inconsistent with the 208 plan.
Induced Growth: The magnitude, timing, location, and density
of residential development has been projected for a
proposed sewer service area, with and without the
proposed sewerage facility. The difference between
the two projections represents the induced growth
attributable to the proposed facility.
iv
-------
Infill Development: Locating new development in existing
urban aread, where most public services are already
available.
Infiltration: (1) The flow or movement of water through
the interstices or pores of a soil or other porous
medium. (2) The quantity of groundwater that leaks
into a pipe through joints, porous walls, or breaks.^
Inflow: Clearwater which enters a sewer system. Although
generally rainwater entering through manholes covers and
illegal drain connection, it also includes cooling water,
sump pump water and other clearwater which would normally
not need treatment.
Influent: Water, wastewater, or other liquid flowing into
a reservoir, basin, or treatment plan, or any unit
thereof.1
Inner Harbor: The Lake Michigan estuary-affected regions of
the Milwaukee, Menomonee, and Kinnickinnic Rivers.
Interceptor Sewers: Sewers used to collect the flows from
main and trunk sewers and carry them to a central
point for treatment and discharge.^
Land Application: A process of wastewater treatment by
which treated wastewater is sprayed or spread on
agricultural land.
Leapfrog Development: A development pattern whereby vacant,
developable area-s adjacent to existing urban develop-
ment are bypassed in favor of inexpensive, agricultural
tracts.
Macroinvertebrates: Those animals lacking a backbone which are
observable with the naked eye.
Mesotrophic: The condition of a water body which is characterized
by moderate nutrient concentrations and aquatic plant growth,
moderate water transparency, and eccassional-periods of
low oxygen content.
Metamorphic Rock: Any change in the composition, texture,
internal structure, etc., of a rock produced by
temperature, pressure, or migrating fluids. -*
MGD: Million Gallons per Day.
Mg/1: Milligrams per Litre.
-------
Mixing Zone: An area contiguous to a point source pollution
discharge where receiving water quality may not meet appli-
cable water quality standards.
MMSD: Milwaukee Metropolitan Sewerage District.
MWPAP: Milwaukee Water Pollution Abatement Program.
NAAQS: National Ambient Air Quality Standards.
NEPA: National Environmental Policy Act.
Nitrification: The processes by which ammonia is oxidized to
nitrite and nitrite is oxidized to nitrate.
Nitrifying Bacteria: Organisms which belong to the family Nitro-
bacteraceae and which are active in the processes of nitri-
fication.
Nonpoint Source Pollution: Pollution originating from areas other
than specific discrete sources. Nonpoint sources would in-
clude urban and rural storm water runoff, atmospheric dep-
osition, livestock wastes, construction activities, and mal-
functioning septic systems.
NPDES: National Pollution Discharge Elimination System.
Old Field Vegetation: An abandoned agricultural field which
is undergoing succession to a grass, shrub, or forest
environment.
Oligotrophic Lake: Lake or other contained water body poor
in nutrient. Characterized by low quantity of
planktonic algae, high water transparency with high
dissolved oxygen in upper layer, adequate dissolved
oxygen in deep layers, low organic deposits colored
shades of brown, and absence of hydrogen sulfide
in water and deposits. ^
O&M: Operation and Maintenance.
Organic Matter: Referring to or derived from living organisms.
In chemistry, any compound containing carbon.
Outer Harbor: The Lake Michigan area enclosed with the the Milwaukee
breakwaters.
VI
-------
Overlapping Per Capita Debt: The consideration of debt
from more than one municipal corporation. For example
the same property may be taxed to support city debt
service as well as county debt service. When the total
debt from all government bodies of a local jurisdiction
is divided by that jurisdiction's population, an
overlapping per capita debt is obtained.
Palezoic: The second era of the geologic time scale.
230-600 million years ago.3
Particulates: Finely divided solid or liquid particles in
the air or in an emission. Particulates include
dust, smoke, fumes, mist, spray and fog.9
Pathogens: Disease-carrying microorganisms such as the
typhus or polio viruses.
PCBs: Polychlorinated Biphenyls.
Per Capita Income: Total personal income received in an
area during a year divided by the area's population.
pH: The reciprocal of the logarithm of the hydrogen-ion
concentration. The concentration is the weight of
hydrogen ions, in grams, per liter of solution.
Neutral water, for example, has a pH value of 7 and
a hydrogen-ion concentration 'of lo-'.
Phytoplankton: The floating plants of a body of water, often
microscopic.
Piezometric Surface: The level to which water will rise in
a. tightly cased well. In an unconfined aquifer the water
table represents the piezometric surface.
PPL: Project Priority List.
Precambrian: The oldest, major division in the geologic
time scale; equivalent to about 90% of geologic time.^
Present Worth: Present worth analysis is a method of determining
the present value of future money receipts and disbursements
Net Present worth equals the present worth of benefits minus
the present worth of costs.
Primary Environmental Corridor: Wetlands, woodland, flood-
plain and wildlife habitat preserved from development
by the 208 Plan.
VII
-------
Primary Treatment: The first stage in wastewater treatment
in which substantially all floating and setteable
solids are mechanically removed by screening and
sedimentation.^
Pumpage: The withdrawal of water from an aquifer by wells or
other mechanical means.
Re-aeration: The absorption of oxygen into water under
conditions of oxygen deficit. ^
Real Growth Rate: The net annual growth rate of property
value after having been discounted by the inflation
rate. A genuine increase in property value holding
all other variables constant.
Residence Time: The time it would take for the full volume
of a lake to be replaced by inflowing waters.
Residual Chlorine: The chlorine that remains following
initial contact with the wastewater. Residual chlorine
includes free chlorine and chloramines.
Revenue Bonds: A bond payable from charges made for services
provided. The borrower obligates to operate the utility
system to provide sufficient net revenues to meet the
obligations of the bond issue.
RIMS: Regional Industrial Multiplier System; an input-
output model developed by the U.S. Department of
Commerce, Bureau of Economic Analysis (BEA). This
model is used by the MWPAP to estimate the net
(negative vs. positive) economic impacts of the
project.
Secondary Impact: The significance of the projected induced
growth is measured in relation to the growth outlined
in the SEWRPC Year 2000 Land Use Plan. A secondary
impact exists when the difference between the Land
Use Plan and the induced growth is meaningful.
Secondary Wastewater Treatment: The treatment of wastewater
by biological methods after primary treatment by
sedimentation. -1-
Sewer Moratorium: A halt in the construction of sewer
extensions, imposed on a community by the DNR.
SEWRPC: Southeastern Wisconsin Regional Planning Commission.
Vlll
-------
Sludge: (1) The accumulated solids separated from liquids,
such as water or wastewater, during processing, or
deposits on bottoms of streams or other bodies of
water. (2) The precipitate resulting from chemical
treatment, coagulation, or sedimentation of water or
wastewater.
SMSA: Standard Metropolitan Statistical Area.
SSES: Sewer System Evaluation Study.
Suspended Solids: Solids that either float on the surface of
or are in suspension in water, wastewater, or other
liquids, and which are largely removable by laboratory
filtering.1
TARP: (Tunnel And Reservoir Project) A combined sewer and
flood control program under construction by the Metro-
politan Sanitary District of Greater Chicago, consisting
of 131 miles of tunnelled sewer and 3 aerated storage quarries,
Total Ammonia-Nitrogen: The total concentration or amount of
nitrogen in the form of ammonia.
Total Nitrogen: The sum of the various forms of nitrogen
compounds (e.g. nitrates, nitrites, ammonia, and or-
ganic) .
Turbidity: The cloudy condition of water due to the sus-
pension of silt or finely divided organic matter.
Ultimate Biochemical Oxygen Demand (BOD ult): The measure of
the total oxygen necessary to complete biologically de-
grade all organic matter in a water sample. The analysis
procedure assumes that it is equal the BOD exerted over
a 20 day period. Ultimate BOD is approximately 1.5 times
as large as the BOD exerted over a 5 day period (6005).
Un-ionized Ammonia: Expressed as NH-j, un-ionized ammonia has one
less hydrogen ion than does the ionized ammonia, NH4+.
The un-ionized form of ammonia is toxic to fish and aquatic
life.
Urban Sprawal: The patter of low density residential
development (and accompanying low population density)
fostered by the availability of developable land which
is easily served by public utilities and highways.
-------
User Charge System: A system to distribute annual operation
and maintenance costs of sewerage facilities to the
users of the system. The MMSD's User Charge System
was put into effect on January 1, 1980.
Value Added: The wholesale price of a good minus the cost
of materials.
WAC: Wisconsin Administrative Code.
Water Quality Management Plan (208 Plan): General guide for
water quality management in Southeastern Wisconsin,
completed in 1979 by the Southeastern Wisconsin Regional
Planning Commission, prepared under Section 208 of
the Federal Water Pollution Control Act (PL 92-500) .
WEPA: Wisconsin Environmental Policy Act.
WEPCO. Wisconsin Electric Power Company.
Wet Industry: An industry that uses and discharges large
volumes of water during the manufacturing process.
The discharge is referred to as process wastewater.
Examples include brewing, leather tanning, and food
processing.
WSP: Wastewater System Plan.
WWTP: Wastewater Treatment Plant.
9
Zooplankton: Planktonic animals that supply food for fish.
x
-------
SOURCES FOR THE GLOSSARY
1. American Public Health Association, et al., ed.,
Glossary: Water and Wastewater Control Engineering
(1969)
2. Robert W. Burchell and David Listokin, The Fiscal Impact
Handbook (New Brunswick, NJ. Rutgers, 1978)
3. R. K. Paull and R. A. Paull, Geology of Wisconsin and
Upper Michigan (Kendall/Hunt Publishing Co., 1977).
4. Lennos L. Moak, Administration of Local Government Debt,
(Chicago: Municipal Finance Officers Association,
1970).
5. William Davis, The Language of Money, (Boston: Houghton-
Mifflin Co., 1970).
6. Resolution of Dane County Circuit Court, File Number
77-132-92 (2) .
7. Robert P. Hanson, ed. , Moody's Municipal and Government
Manual, Volume 1, (New York: Moodys Investor
Service, Inc., 1980).
8. SEWRPC, Planning Report 25, A Regional Land Use Plan and
a Regional Transportational Plan for Southeastern
Wisconsxn--2000, Volume I. (Waukesha, Wisconsin,
1975).
9. Gloria J. Studdard, ed., Common Environmental Terms
(Washington: U.S. EPA, 1974).
10. The American Geological Institute, Dictionary of
Geological Terms (Garden City, NY: Anchor Press/
Doubleday, 1976).
11. Daniel N. Lapedes, ed., Dictionary of Scientific and,Tech-
nical Terms, 2nd Edition (New York, NY: McGraw-Hill,
1978).
12. Wisconsin Administrative Code
13. U.S. E.P.A., Quality Criteria for Water, (Washington, D.C.
Government Printing Office).
xi
-------
BIBLIOGRAPHY
-------
BIBLIOGRAPHY
Alvord, Burdick and Howson, 1954. Report on Separation of Storm
and Sanitary Sewage in Areas Served by Combined Sewers.
Metropolitan Sewerage Commission. Milwaukee, WI.
, 1956. Report on Intercepting Sewers and Sewage
Treatment, Milwaukee Metropolitan Area. MMSD. Milwaukee,
WI.
, 1957. Special Summary of Report on Intercepting Sewers
and Sewage Distict. MMSD. Milwaukee, WI.
, 1958. Report on Design of Puetz Road Sewage Treatment
Plant and Main Intercepting Sewers. MMSD. Milwaukee, WI.
, 1970. Design Criteria and Proposed Programming, South
Shore Waste Water Treatment Plant Sewerage Commission of the
City of Milwaukee, WI.
, 1971. Report on Northeast Side Sewer Systems. Metro-
politan and City Sewerage Commission, Milwaukee, WI.
, 1972. Report on Pollution Abatement in the Lincoln
Creek Area. fiMSD. Milwaukee, WI.
, 1974a. Environmental Assessment: Northwest Branch
Main Relief Sewer System. MMSD. Milwaukee, WI.
, 1974b. Report on Sludge Disposal, South Shore Waste-
water Treatment Plant. MMSD. Milwaukee, WI.
American Geological Institute, 1976. Dictionary of Geological
Terms. Garden City, NY: Anchor Press/Doubleday.
American Public Health Association, 1969. Glossary: Water and
Wastewater Control Engineering.
American Society of Civil Engineers, 1970, Manual of Practice 9;
Design and Construction of Sanitary and Storm Sewers. New
York: ASCE.
, .1977. Manual of Practice 8; Wastewater Treatment Plant
Design. Mew York: ASCE.
-------
Aware, Inc., 1974. Process Design Techniques for Industrial
Waste Treatment. Edited by C. E. Adams, Jr. and W.W.
Eckenfelder, Jr. Nashville, TN.
Babbitt, Cleasley and Doland, 1967. Water Supply Engineering.
New York: McGraw-Hill Book Co.
Earret, G. V., and Blair, J. P., 1976. Industrial Development
Potential. School of Business Administration. University
of Wisconsin-Milwaukee.
Barton-Aschman Assoicates, Inc., 1973. Comprehensive Plan, 1973:
City of Oak Creek. Barton-Aschman Assoicates, Inc. Chicago,
IL.
Bayside, Village of, 1973. Selected Codes. Bayside, WI. .
Becker, G. C., 1976. Environmental Status of the Lake Michigan
Region. Volume 17: Inland Fishes of the Lake Michigan
Drainage Basin. Argonne National Laboratory. ANL/ES-40.
U.S. ERDA. Argonne, IL.
Beverstock, F., and Stackert, R. P., eds., 1972. Metropolitan
Milwaukee Fact Book: 1970. Milwaukee Urban Observatory.
Milwaukee, WI.
Brown Deer, City of, 1977. Zoning Code. Brown Deer. WI.
Bruhy, M. E. and Overstreet, D. F., 1977. Phase I Inventory of
The Franklin-Muskego Interceptor Route Under Task 2-1.3.2.3.
7.2. MMSD. Milwaukee, WI.
Burchell, R. W., and Listokin, D., 1978. The Fiscal Impact Hand-
book. Center for Urban Policy Research. New Brunswick, NJ.
California, State of, Office of Planning and Research, 1978.
Economic Practices Manual. Sacramento, CA.
Camp, Dresser and McKee, Inc., 1978a. Preliminary Total Solids
Management Program. f!MSD« Milwaukee, WI.
, 1978b. Total Solids Management Program. Volume I.
MMSD. Milwaukee, WI.
, 1978c. Total Solids Management Program. Volume II.
MMSD. Milwaukee, "WI.
, 1978d. Total Solids Management Program. Volume III, and IV
Apprendices A-Q. MMSD. Milwaukee, WI.
, 1978e Total Solids Management Program: Public
Involvement Report, August 1978. MMSD. Milwaukee, WI.
Kill
-------
Christensen, K., 1976. Social Impacts of Land Development.
The Urban Institute. Washington, D.C.
Citizen's Governmental Research Bureau, 1978a. 20th Annual
Municipal Budget Bulletin. Washington, D.C.
, 1978b. 27th Annual Property Tax Rate Bulletin.
Washington D.C.
, 1980a. Bulletin Volume 68, No. 3. Washington, D.C.
, 1980b. Bulletin Volume 68, No. 6. Washington, D.C.
City Planning Associates, Inc., 1961a. Development Plan,
New Berlin, Wisconsin. Part 1. City of New Berlin.
New Berlin, WI.
, 1961b. Development Plan, New Berlin, Wisconsin.
Part 2. City of New Berlin. New Berlin, WI.
Code of Federal Regulations, Title 40, Part 6. Preparation
of Environmental Impact Statements.
Part 35. Municipal Wastewater Treatment Works,
Construction Grants Program.
. Part 50. National Primary and Secondary Ambient
Air Quality Standards.
. Part 1500. Preparation of Environmental Impact
Statements.
The Commission on State-Local Relations and Financing Policy,
1977. Recommendations of the Commission on State-Local
Relations and Financing Policy, January, 1977. State of
Wisconsin. Madison, WI.
Converse Ward Davis Dixon, Inc., 1981. Report on the Evalua-
tion of the Potential for Groundwater Pollution from Storage
Tunnels in the Niagaran Formation Proposed by the Milwaukee
Metropolitan Sewerage District. Caldwell, NJ.
Cudahy, City of, 1977. Municipal Code. Cudahy, WI.
Dane County Circuit Court, 1077. Case No. 152-342. Sewerage
Commission of the City of Milwaukee and the Metropolitan
Sewerage Commission of the County of Milwaukee versus The
Wisconsin Department of Natural Resources. Madison, WI.
xiv
-------
, 1977. Resolution Adopting Rules to Implement the
Waste Load Restrictions and Apportionment Section as
Provided in the Stipulation Approved by the Circuit Court
of Dane County Relative to Case 152-342. File No. 77-132-
92 (2) . Madison, WI.
Davis, William, 1973. The Language of Money. Houghton-Mifflin
Co. Boston, MA.
Devaul, Robert, W, 1967. Trends in Groundwater Levels in Wisconsin
through 1966., WGNHS Information Circular No. 9. Madison,
WI.
EcolSciences, Inc., 1977. Handbook for Evaluation of Secondary
Environmental Impacts of Wastewater Treatment Facilities.
Vienna, VA.
, 1979. Technical Memorandum: Review of Population
Forecasts for Milwaukee Metropolitan Sewerage District
Facilities Plan. Milwaukee, WI.
Elm Grove, Village, 1973. Codes and Ordinances. Elm Grove, WI.
Engineering New Record "Cement Faces Chronic Shortages". ENR.
June 19, 1980. Vol. 204 No. 25. McGraw Hill, Inc. New
York, NY.
Erickson, Robert M., 1972. Trends in Groundwater Levels in
Wisconsin, '67-'71, WGNHS Information Circular No. 21.
Madison, WI.
Ferebee, J.L., 1932. Reports, Note and Data Pertinent to
Expansion of Existing Sewage Treatment and Sludge Disposal
Facilities. Sewerage Commission of the City of Milwaukee.
Milwaukee, WI.
Ferebee, J.D., Townsend, S.W., and Hatton, T.C., 1932. Report
Upon Proposed Extension to Existing Sewage Treatment Plan.
Sewerage Commission of the City of Milwaukee. Milwaukee, WI.
, 1933. Report Upon The Probable Future Sanitary
Requirements in the Water-Sheds of the Milwaukee, Menomonee,
Kinnickinnic and Root Rivers, and Oak and Sauk Creeks.
Fitzgerald, M., et. al., 1977. Manual for Evaluating Secondary
Impacts of Wastewater Treatment Facilities. EPA-600/5-78-
003 U.S.
xv
-------
Foley, F.C., Walton, W.C., and Drescher, W.J., 1953. Ground-
water Conditions in the Milwaukee-Waukesha Area Wisconsin,
USGS Water Supply Paper 1229. Washington, D.C
Fox Point, Village of, Wisconsin, 1974. Selected Codes.
Fox Point
Franklin Common Council, 1974. Franklin, Wisconsin Zoning
Ordinance. Franklin, WI.
Gebert, W.A., and B.D. Holmstrom, 1974. Low-flow Characteris-
tics of Wisconsin Streams at Sewage-Treatment Plants.
U.S.G.S. Water Resources Investigations. Washington, D.C.
Glendale, City of, 1973. The Glendale Zoning Ordinance.
Glendale, WI.
Great Lakes National Program, 1978. Lake Michigan Study: Some
Preliminary Findings. EPA. Washington D.C.
Green, J.H., and Hutchinson, R.D. Groundwater Pumpage and Water
Level Changes in the Milwaukee-Waukesha Area, Wisconsin,
1950-61, USGS Water Supply Paper/809-I. Washington D.C.
Greendale, Village of, 1976. Selected Codes and Standard Speci-
fications. Greendale, WI.
, 1976. Zoning District Map. Greendale, WI.
Greenfield, City of, 1977. Selected Codes. Greenfield, WI.
Hales Corners, Village of, 1978. Selected Codes. Hales Corners,
WI.
Harland, Bartholomew and Associates, 1976. Final Report on the
Comprehensive Plan. Glendale, WI.
Huddleston, T.R., and Schein, F., 1976. Economic Change and the
Urban Poor: An Analysis of Changes in the Milwaukee Low
Income Area and the SMSA. Wisconsin Planning Office.
Madison, WI.
International Joint Commission, 1977a. Menomonee River Pilot
Watershed Study. Windsor, Ontario.
, 1977b. Land Use and Land Use Practices in the Great
Lakes Basin. Windsor, Ontario.
xvi
-------
Kinney, K.S., 1978. Industrial Drain Hurting Area's Economic
Vigor. Milwaukee Journal, March 26, 1978. Milwaukee, WI.
Lathy, Jr., R.F., et. al., 1980. Treatment Plant Odors and
Neighbors: A Case Study. Journal of the Water Pollution
Control Federation, Vol. 52, No. 7. July, 1980.
Washington, D.C.
Lin, C.K., 1971. Availability of Phosphorus for Cladophera
Growth in Lake Michigan. Proc. 14th Conf. Great Lakes
Res.: 39-43.
Linsley, R.K., Kohler, M.A., and Paulhus, J.L.H., 1975.
Hydrology for Engineers. McGraw Hill, Inc., New York, NY.
McFadzean and Everly, Ltd. 1974. Design Program Report for
Community Center Park - Greendale, Wisconsin, City of
Greendale. Greendale, WI.
Meadows, G.R., and Call, S.T., 1977. Property Value Trends
and Resident Attitudes as Guides to Neighborhood
Revitalization: A Case Study of Milwaukee, Milwaukee
Urban Observatory. UWM. Milwaukee, WI.
Meinholz, T.L., Kruetzberger, w.A., Harper, M.E., and
Fay, K.J., 1979. Verification of the Water Quality Impacts
of Combined Sewer Overflow. EPA-600/2-79-155. Municipal
Environmental Research Laboratory. Cincinnati, OH.
Meinholz, T.L., Kruetzberger, W.A., Kobriger, N.P., and
Harper, M.E., 1979. Water Quality Analysis of the Milwaukee
River to Meet PRM 75-34 (PG-61) Requirements. Rexnord
Environmental Research Center. Milwaukee, WI.
Menomonee Falls, Village of, 1973. Zoning Ordinances. Menomonee
Falls, WI.
Mequon, City, of, 1976. City of Mequon Code of Ordinances.
Chapter 4: Zoning Code. Mequon, WI.
Metropolitan Milwaukee Association of Commerce, 1978. Economic
Fact Book on Metropolitan Milwaukee. MMAC. Milwaukee, WI.
Metropolitan Sanitary District of Greater Chicago, 1980. Ground-
water Monitoring Program, Mainstream Tunnel System, Addison
Street to 59th Street, Revised Report. Chicago, ILI
xvi i
-------
Milwaukee Common Council, 1977. Milwaukee Code of Ordinances.
City of Milwaukee. Milwaukee, WI.
Milwaukee County, 1979. Statistical Report of Property Valuation.
Milwaukee, WI.
Milwaukee Department of City Development, 1976. Overall Economic
Development Program. DCD. Milwaukee, WI.
, 1977a. Historical Trends: A Summary. DCD. Milwaukee,
WI.
, 1977b. Population Projections. DCD. Milwaukee, WI.
, 1977c. Toward A Comprehensive Plan. A Preservation
Policy for Milwaukee. DCD. Milwaukee, WI.
, 1978a. 1978 City of Milwaukee Housing Survey: General
Results. DCD. Milwaukee, WI.
, 1978b. Major Linkages Among Manufacturing Industries
With the Milwaukee Metropolitan Area. DCD. Milwaukee, WI.
, 1978c. Future Economic Trends: An Overview. DCD.
Milwaukee, WI.
Milwaukee Health Department, 1976. Beach, River and Harbor
Pollution Research. Milwaukee Health Department. Milwaukee,
WI.
Milwaukee Metropolitan Sewerage District, 1976. Facilities Plan.
MMSD. Milwaukee, WI.
, 1976-1980. WPDES Permit Monitoring Data. Unpublished.
, 1977a. Environmental Assessment - Hales Corners
Interceptor. MMSD. Milwaukee, WI.
xvi 11
-------
, 1977b. Environmental Assessment - Memononee Falls-
Germantown Interceptor. IMSD. Milwaukee, WI.
. 1977c. Environmental Assessment - Northeast Side
Relief Sewer System. FiMSD. Milwaukee, WI.
, 1977d. Environmental Assessment - Root River Inter-
ceptor. MMSD. Milwaukee, WI.
, 1978a. Waste Load Allocation Procedures. MMSD.
Milwaukee, WI.
, 1978b. User Charge and Industrial Cost Recovery
Program, Volume I: Final Reports, Interim Reports,
Technical Memorandum. MMSD. Milwaukee, WI.
, 1978c. User Charge and Industrial Cost Receovery
Program, "olume II: Technical Memorandum. MMSD.
I-ilwaukee, O.
, 1978d. Comprehensive Facilities Plan: T'ork Plan.
"MMSD. rilwaukee WI.
, 1978e. Unpublished Biological Sampling Data.
MWPAP. Milwaukee, WI.
, 1978f. Caddy Vista Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
, 1978g. Northridge Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
, 1978h. Oak Creek Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
, 19781. Mitchell Field Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
, 1978j. Franklin Northeast Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
, 1978k. Pilot Plant Investigations: Preliminary Phase
I Technical Report. MMSD. Milwaukee, WI
, 19781. Franklin-Muskego Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
, 1978m. r'"-otal Solids Management, Environmental
Assessment. 'USD. Milwaukee, VII.
, J979a. T, astewater System Plan, South Shore Environ-
mental Assessment Element. MMSD. Milwaukee, WI.
, 1979b. Energy Impact and Resource Recovery Analysis.
MMSD. March 1, 1979. Milwaukee, WI.
xix
-------
_, 1979c. Probability Curves from Hydrocomp Simulation.
Model. SEWRPC. Waukesha, WI.
, 1979d. Wastewater System Plan, Combined Sewer Overflow
Element. MMSD. Milwaukee, WI.
, 1979e. Combined Sewer Overflow Characterization,
Storage and Pilot Plant Treatment. MMSD. Milwaukee, WI.
, 1979f. Oak Creek Southwest Interceptor, Environmental
Inventory. MMSD. Milwaukee, WI.
_, 1979g. Infiltration/Inflow Analysis: Executive
Summary. IIMSD- Milwaukee, WI.
, 1979h. Infiltration/Inflow Analysis: Volume I, Part I:
District-Wide Analysis. MMSD. riilwaukee, WI.
, 1979i. Infiltration/Inflow Analysis: Volume II, Part II:
Community Summaries. MMSD. Milwaukee, WI.
, 1979j. Infiltration/Inflow Analysis: Volume III, Fart II
Community Summaries. MMSD. Milwaukee, WI.
, 1979k. Infiltration/Inflow Analysis: Volume IV, Part II:
Community Summaries. MMSD. Milwaukee, WI.
, 19791. Infiltration/Inflow Analysis: Volume V, Part
III: Appendices A-P. MMSD. Milwaukee, WI
_, 1979m. Infiltration/Inflow Analysis: Volume VI, Part
III: Appendices Q-,c. MMSD. Milwaukee, WI.
__, 1979n. Wastewater System Plan, Environmental Assess-
ment Bibliography. MMSD. Milwaukee, WI.
, I979o. Wastewater System Plan, Jones Island Facilities
Plan Element: Planning Report. MMSD. Milwaukee, WI.
, 1979p. Wastewater System Plan, Jones Island Facility Plan
"Element: Environmental Assessment. MMSD. Milwaukee, WI.
, 1979q. "Economics Procedures Manual" Technical Memo-
randum. 5/2-13. February 14, 1979.
, 1979r. Wastewater System Plan, South Shore Facilities
Plan Element. MMSD. Milwaukee, WI.
, 1979s. Wastewater System Plan, Muster Facilities Plan.
MMSD. Milwaukee, WI.
, 1979t. Wastewater System Plan, Environmental Assesment.
MMSD. Milwaukee, WI.
, 1980a. CSO. MMSD. Milwaukee, WI.
xx
-------
, 1980b. Environmental Assessment, Volumes 2, 2A, and
2B. MMSD. Milwaukee, WI.
, 1980c. Franklin Muskego Interceptor Facility Plan
Element. MMSD. Milwaukee, WI.
, 1980d. Franklin Northeast Interceptor Facility Plan
Element. MMSD. Milwaukee, WI.
, 1980e. Jones Island Facility Plan Element. MMSD.
Milwaukee, WI.
, 1980f. Mitchell Field South Facility Plan Element.
MMSD. Milwaukee, WI.
, 1980g. Northridge Interceptor Facility Plan Element.
MMSD. Milwaukee, WI.
, 1980h. Oak Creek Interceptor Facility Plan Element.
MMSD. Milwaukee, WI.
, 1980i. Solids Management., Facility Plan Element
Volumes 1 and 2. MMSD. Milwaukee, WI.
, 1980j. South Shore Facility Plan Element. MMSD.
Milwaukee, WI.
, 1980k. Underwood Creek Interceptor Facility Plan
Element. MMSD. Milwaukee, WI.
•, 19801. Wastewater System Plan, Volumes A, B, C, D.
MMSD. Milwaukee, WI.
, 1981a. "Inline Storage Facility Plan", Appendices 4A,
4B and 4C, Draft Document. Milwaukee, WI.
, 1981b. "Infiltration/Exfiltration Analysis, Draft Docu-
ment. Milwaukee, WI.
, 1981c. Transmission of Unpublished Data, February 13,
"Correspondence, Fred Meinholz (MMSD) to Jay Hockmuth (VJDNR) .
, 1981d. Transmission of Unpublished Data, February 18,
Correspondence Fred Meinholz (MMSD) to Jay Hockmuth (WDNR).
, 1981 e. Transmission of Unpublished Data, March 10,
"Correspondence Robert Larget (MWPAP) to Herbert Gurschke
(MMSD).
xxi
-------
, 1981f. Transmission of Unpublished Data, March 25
Correspondence, James Wilson (MWPAP) to Jim Ibach (MMSD).
, 1981g. Exhibit A, Summary of Support Documentation
For Recommended Alternatives. Unpublished.
_, 1981h. Exhibit B, Effects of Recent Planning
Outputs on the Recommended Facilities. Unpublished.
, 1981i. Exhibit C, Summary-Amendment 7 to Task
Order 3: CSO Abatement Plan to Comply with Dane County
Court Stipulation. Unpublished.
, 1981J. Exhibit D, Role of Instream Measures in the
WPAP. Unpublished.
Milwaukee Public Schools, 1978. Enrollment Analysis: 1963-1983.
Milwaukee Public Schools. Milwaukee, WI.
Moak, Lennox L., 1970. Administration of Local Government Debt.
Chicago: Municipal Finance Officers Association.
Moody's, 1980. Moody's Municipal and Government Manual, Volume I.
Robert P. Hanson, ed. New York: Moody's Investor Service,
Inc.
Muller, T., 1976a. Economic Impacts of Land Development. The
Urban Institute. Washington, D.C.
, 1976b. Fiscal Impacts of Land Development. The Urban
Institute. Washington, D.C.
Municipal Ordinance Service, Inc. 1977. Zoning Code of Brookfield,
Wisconsin. City of Brookfield, Brookfield, WI.
, 1978. Zoning Code of City of Brookfield, Wisconsin.
Brookfield, WI.
Muskego, City of, 1972. Selected Codes. Muskego, WI.
New Berlin, City of, 1978. Zoning Ordinance. New Berlin, WI.
Newman, Donald G., 1977. Engineering Economic Analysis. San
Jose, CA: Engineering Press.
Oak Creek, City of, 1977. Selected Codes. Oak Creek, WI.
O'Neel, W.G., Davis, A.L., and Van Dusew, K.W., 1975. SAM:
Wastewater Collection System Analysis Model, User's Manual.
CH2M Hill. Corvallis, OR.
xxii
-------
Ozaukee County, 1979. Statistical Report of Property Valuation.
Paul, R.K., and Paul, R.A., 1977. Geology of Wisconsin and
Upper Michigan. Dubuque, IA: Kendall/Hunt Publishing Co.
River Hills, Village of, 1975. Selected Codes and Ordinances.
River Hills, WI.
St. Francis, City of, 1964. Ordinances. St. Francis, WI.
Schaenman, P.S., 1976a. Using an Impact Measurement System to
Evaluate Land Development. The Urban Institute. Washington,
B.C.
, 1976b. Measuring Impacts of Land Development. The Urban
Institute. Washington, D.C.
Shorewood, Village of, 1977. Selected Codes. Shorewood, WI.
Slater, T.M., and Barry, J.T., 1975. Brown Deer Land Use Study.
James T. Berry, Inc; Kahler Slater & Pitzhugh Scott, Inc.
Brown Deer, WI.
Southeastern Wisconsin Regional Planning Commission, 1971.
Population of Southeastern Wisconsin: 1960 and 1970.
Waukesha, WI.
, 1972a. The Economy of Southeastern Wisconsin. Technical
Report No. 2. Waukesha, WI.
, 1972b. The population of Southeastern Wisconsin. Tech-
nical Report No. 11. Waukesha, WI.
, 1974. A Regional Sanitary Sewage Plan for Southeastern
Wisconsin. Planning Report, 16. Waukesha, WI.
, 1975a. A Regional Housing Plan for Southeastern
Wisconsin. Planning Report No. 20. Waukesha, WI.
, 1975b. A Regional Land Use Plan and A Regional Trans-
portation Plan for Southeastern Wisconsin. Volume I. Plan-
ning Report No. 25. Waukesha, WI.
, 1976. Digital Computer Model of the Sandstone Aquifer in
Southeastern Wisconsin, Technical Report No. 16. Waukesha,
WI.
xxi 11
-------
, 1977. A Regional Park and Open Space Plan for South-
eastern Wisconsin for the Year 2000. Planning Report No. 27.
Waukesha, WI.
, 1978a. A Regional Land Use Plan and Regional Trans-
portation Plan for Southeastern Wisconsin. Volume II. Plan-
.ning Report No. 25. Waukesha, WI.
, 1978 b. Printout: Housing Units by Sewer Interceptor
by Year. Waukesha, WI.
, 1978c. Printout: Land Use Data for Northeast Side
Relief System East for Years 1963 and 1970. Waukesha, WI.
, 1978d. Printout: Land Use Date for Northeast Side
Relief System East for Years 1970, 1985 and 2000.
Waukesha, WI.
, 1978e. Printout: Regional Housing Study: Land Use
Controls Inventory. Waukesha, WI.
, 1978f. Printout: Total Population for Milwaukee
Metropolitan Sewerage District by Quarter. Waukesha, WI.
, 1978g. Printout: Total Population by Sewer Interceptor
by Year. Waukesha, WI.
, 1978h. Data Pertaining to Sewer Service Area Employment
Allocations: 1972, 1985 and 2000. Waukesha, WI.
, 1978i. SEWRPC Newsletter. Volume 18, No. 13.
Waukesha, WI.
, 1978J. Village of Butler Zoning Ordinance. Waukesha,
WI.
, 1978k. Codes and Ordinances of the Village of
Germantown, WI. Chapter 17: Zoning Ordinance. Waukesha,
WI.
, 19781. Water Quality of Lakes and Streams in Southeastern
Wisconsin: 1967-1975. Technical Report No. 17. Waukesha,
WI.
, 1978m. Lake Michigan Estuary and Direct Drainage Area
subwatersheds Planning Program Prospectus. Waukesha, WI.
,1979. A Regional Water Quality Management Plan for
Southeastern Wisconsin - 2000. Vols. I, II and III.
Waukesha, WI.
, 1980. A Regional Air Quality Attainment and Maintenance
Plan for Southeastern Wisconsin: 2000. Planning Report
No. 28. Waukesha, WI.
xxiv
-------
Stevens, Thompson & Runyan, Inc., 1982. CSO Facilities Plan Out-
line for Chapter 2. MMSD. Milwaukee, WI.
_, 1978b. CSO Facilities Plan. Chapter 4. MMSD.
Milwaukee, WI.
, 1978c. CSO Facilities Plan. Volume II, Chapter 6:
Alternative Development and Analysis. MMSD. Milwaukee, WI.
, 1978d. CSO Facilities Plan. Appendix 10: Conveyance,
Storage and Treatment, and Evaluation. MMSD. Milwaukee, WI.
, 1978e. CSO Facilities Plan. General Summary of
Selected Alternative for Out-of-Basin Concept. MMSD.
Milwaukee, WI.
Studdard, Gloria J., ed., 1974. Common Environmental Terms.
USEPA. Washington D.C.
Tec-Search, Inc., 1969. Germantown, Wisconsin: Comprehensive
Plan. Tec-Search, Inc. Wilmette, IL.
Thiensville, Village of, 1974. Selected Codes. Thiensville,
WI.
Tiebout, Charles M., 1962. The Community Economic Base Study.
New York: Committee for Economic Development. New York,
N.Y.
Torrey, M.S., 1976. Environmental Status of the Lake Michigan
Region. Volume 3: Chemistry of Lake Michigan. Argonne
National Laboratory. ANL/ES-40. U.S. ERDS. Argonne, IL.
U.S. Army Corps of Engineers, 1977. Storage, Treatment, Overflow,
Runoff Model "STORM". Davis, CA.
, 1979. "Draft Plan of Study - Chicagoland Underflow Plan,
Phase I, General Design Memorandum." Chicago, IL.
U.S. Congress, Clean Air Act Amendments of 1977. P. L. 95-95,
95th Congress. Washington, D.C.
, Clean Water Act Amendments of 1977. P.L. 95-217,
95th Congress. Washington, D.C.
, Federal Water Pollution Control Act Amendments of 1972.
P7 L. 92-500, 92nd Congress. Washington, D.C.
, National Environmental Policy Act of 1969. P.L. 91-
190 as amended by P.L. 94-83. 94th Congress. Washington,
D.C.
XXV
-------
United States Court of Appeals, Seventh Circuit, Case No. 77-2246,
People of the State of Illinois, Plaintiff-Appellee, and
People of the State of Michigan, Intervening Plaintiff-Appellee,
vs. City of Milwaukee, The Sewerage Commission of the City of
Milwaukee, and the Metropolitan Sewerage Commission of the
County of Milwaukee, Defendants-Appellants. Chicago, IL.
United States District Court, Northern District of Illinois,
Eastern Division - Case No. 72-C-1253, 1977. People of The
State of Michigan vs. The City of Milwaukee, et. al. Judgment
Order. Chicago, IL.
1980. People of the State of Illinois and the People of
The State of Michigan vs. The City of Milwaukee, et.al.,
Amended Judgment Order. Chicago, IL.
U.S. Department of Commerce, Bureau of the Census, 1971. General
Population Characteristics: Wisconsin 1970 Census of Popu-
lation. Publication PCG-B51 Wis. Washington, D.C.
1972a. 1970 Census of Population Detailed Characteristics-
Wisconsin. Washington, D.C.
, 1981. 1980 Census of Population and Housing, Preliminary
Reports. Washington, D.C.
, 1972b. 1970 Metropolitan Housing Characteristics:
Milwaukee, WI. SMSA. GPO.. Washington, D.C.
, 1972c. 1970 Census of Housing. Volume I: Housing
Characteristics for States, Cities & Counties; Part 51,
Wisconsin. GPO:. Washington, D.C.
, 1974a. Wisconsin 1972 Census of Retail Trade. RC 72-A-
50. Washington D.C.
, 1974b. 1972 Census of Wholesale Trade: Area Series,
Wisconsin. Washington, D.C.
, 1975a. Wisconsin 1972 Census of Manufactueres. MC 72
(3)-50. Washington, D.C.
, 1975b. 1972 Census of Selected Service Industries:
Area Series, Wisconsin. GPO. Washington, D.C.
, 1977. Annual Housing Survey 1975: Milwaukee, WI.,
SMSA. Series H-150-75. GPO. Washington, D.C.
XXVI
-------
U.S. Department of Housing and Urban Development 1975. Analysis
of the Current Housing Market Situation - Milwaukee, Wisconsin
Second Draft. U.S. Depart of HUD. Washington, D.C.
U.S. Environmental Protection Agency, 1973. "Wastewater Treatment
and Reuse by Land Application", 2 Volumes. EPA 660/2-73-006b.
Office of Research and Development. Washington, D.C.
1975a. Handbook for Sewer System Evaluation and Rehabili-
tation. Office of Water Program Operations. EPA-430/9-75-
021. Washington, D.C.
, 1975b. Cost-Effective Comparison of Land Application
and Advance Wastewater Treatment. Office of Water Program
Operations. EPA 430/9-75-016. Washington, D.C.
, 1975c. Guidance for Preparing a Facility Plan. Office
of Water Program Operations. EPA-430/9-76-015. Washington, D.C.
, 1975d. Cost of Wastewater Treatment by Land Application
Office of Water Program Operations. EPA-430/9-75-003. Washington
, 1976a. Application of Sewerage Sludge to Cropland:
Appraisal of Potential Hazards of the Heavy Metals to Plants
and Animals. Office of Water Program Operations. EPA-430/
9-76-013. Washington D.C.
, 1976b. Direct Environmental Factors at Municipal Waste-
water Treatment Works. Office of Water Program Operations.
EPA-430/9-76-003. (MCD-20) Washington, D.C.
, 1976c. Draft EIS on the Tunnel Component of the Tunnel
and Reservoir plan proposed by the Metropolitan Sanitary
District of Greater Chicago, 59th to Addison St., Chicago,
IL.
, 1976d. Model Plan of Study. Office of Water Program
Operations. EPA-430/9-76-004. Washington, D.C.
, 1976e. Quality Criteria for Water. Office of Water
Planning and Standards. Washington, D.C.
, 1977a. Alternatives for Small Wastewater Treatment
Systems. Part 1: On-Site Disposal/Septage Treatment and
Disposal. EPA Technology Transfer. EPA-625/4-77-011. EPA.
Washington, D.C.
, 1977b. Alternatives for Small Wastewater Treatment
Systems. Part 2: Pressure Sewers/Vacuum Sewers. EPA
xxvii
-------
Technology Transfer. EPA-625/4-77-011. Washington, D.C.
, 1977c. Alternatives for Small Wastewater Treatment
Systems. Part 3: Cost/Effectiveness Analysis. EPA
Technology Transfer. EPA-625/4-77-011. Washington, D.C.
, 1977d. Process Design Manual: Wastewater Treatment
Facilities for Sewered Small Communities. EPA Technology
Transfer. EPA-625/1-77-009. Washington, D.C.
, 1977e. October, 21, Issuance To All Interested Govern-
ment Agencies, Public Groups and Citizens. EPA-Region V.
Chicago, IL.
, 1978a. Analysis of Operation and Maintenance Costs for
Municipal Wastewater Treatment Systems. EPA 430/9-77-015.
Office of Water Program Operations. Washington, D.C.
, 1978b. Construction Costs for Municipal Wastewater
Conveyance Systems: 1973-1977. Office of Water Program
Operations. EPA-430/9-77-015. Washington, D.C.
, 1978c. Construction Costs for Municipal Wastewater
Treatment Plants: 1973-1977. Office of Water Program
Operations. EPA-430/9-77-013. Washington, D.C.
, 1978d. Design Seminar Handout, Small Wastewater Treat-
ment Facilities. Washington.
1978e. "Direct Environmental Factors at Municipal
Wastewater Treatment Works - Evaluation and Control of
Site Aesthetics, Air Pollutants, Noise and Other Opera-
tion and Construction Factors." (MCD-32) EPA 43019-76-003
Washington, D.C.
_ , 1978f. "Energy Conservation in Municipal
Treatment". (MCD-32) EPA 430/9-77-011. Washington, D.C.
_ , 1978g. Innovative and Alternative Technology Assessment
Manual. (Draft) EPA-43019-78-009 . Municipal Environ-
mental Research Laboratory. Cincinnati, OH.
_ , 1978h. Process Design Manual: Municipal Sludge Land-
fills. EPA Technology Transfer. EPA-625/1-78-010 .
Washington, D.C.
_ , 1978i. Report to Congress on Control of Combined Sewer
Overflow in the United States. EPA-430/9-78-006 .
Washington, D.C.
xxviii
-------
, 1978J. Sludge Treatment and Disposal. Volume I:
Sludge Treatment. EPA-62514-78-012. Environmental Rese-
arch Information Center. Cincinnati, OH.
, 1978k. Sludge Treatment and Disposal. Volume II:
Sludge Disposal. EPA-625/4-78-012. Environmental Re-
search Information Center. Cincinnati, OH.
, 19781. March 23, Issuance to All Interested Govern-
ment Agencies, Public Groups, and Citizens. EPA - Region
V. Chicago, IL.
, 1979. STORET listing for Lake Michigan Basin.
Washington, D.C.
, 1980. Lawrence Avenue Underflow Sewer System Interim
Report, Planning and Construction. EPA 600/2-80-014, Munici-
pal Environmental Research Laboratory. Cincinnati, OH.
U.S. Geological Survey, 1972. Topographic Maps of the Milwaukee
Area, 1%'. USGS. Washington, D.C.
Washington County, Wisconsin, 1979. Statistical Report of Pro-
perty Valuation. Wisconsin Department of Revenue: Bureau
of Property Tax. Madison, WI.
Waukesha County, Wisconsin, 1979. Statistical Report of Property
Valuation. Wisconsin Department of Revenue: Bureau of Prop-
erty Tax. Madison, WI.
Wauwatosa, City of, Wisconsin, 1978. Municipal Codes. Wauwatosa,
WI.
West Allis, City of, Wisconsin, 1975. Revised Municipal Code.
West Allis, WI.
West Milwaukee, Village of, Wisconsin, 1972. General Ordinances.
West Milwaukee, WI.
Whitefish Bay, Village of, Wisconsin, 1972. General Ordinances.
West Milwaukee, WI.
Wisconsin Administrative Code. Natural Resources Chapter, (var-
ious section). Madison, WI.
XXIX
-------
Wisconsin Department of Administration, 1977. Official Population
Estimates for 1977. DOA. Madison, WI.
Wisconsin Department of Agriculture, Trade and Consumer Protection.
Farmland Preservation Act, 1978. Madison, WI.
Wisconsin Department of Industry, Labor, and Human Relations, 1978.
Employment Review: The Milwaukee Area. Wisconsin Job Service.
Milwaukee, WI.
Wisconsin Department of Natural Resources, 1968. Report on an
Investigation of the Pollution in the Milwaukee River Basin
made during 1966 and 1967. Madison, WI.
, 1969a. Reports on the Investigation of the Pollution
of the Milwaukee River, Its Tributaries, and Oak Creek made
during 1968 and 1969. Madison, WI.
, 1969b. Little Muskego Lake. Lake Use Report FX-10 WDNR.
Madison, WI.
_, 1971. Big Muskego Lake. Lake Use Report FX-3. WDNR.
Madison, WI.
, 1976. Southeastern Wisconsin River Basins: A Drainage
Basin Report. WDNR. Madison, WI.
Wisconsin Department of Revenue, 1978. Comparisons Among Major
Property Tax Relief Programs. DOR. Madison, WI.
Wisconsin Department of Revenue, 1979. Wisconsin Tax Burden Study.
Madison, WI.
Wisconsin Electric Power Company, 1974. An Environmental Study
of the Ecological Effects of the Thermal Discharges from
Point Beach, Oak Creek, and Lakeside Power Plants on Lake
Michigan. Volume 2 Limnetics, Inc. Milwaukee, WI.
Wisconsin Environmental Policy Act of 1972. 1971 Assembly Bill
975. Chapter 274. Madison, WI.
Wisconsin Statutes, 1977, various chapters (34th Edition), Madison,
WI.
Wisconsin Water Pollution Control Laws of 1978, Chapter 147:
Pollution Discharge Elimination. Madison, WI.
XXX
-------
COORDINATION
-------
Coordination:
Agencies and Individuals Receiving the Draft EIS
A. Federal
Senator William Proxmire
Senator Gaylord Nelson
Representative Toby Roth
Representative F. James Sensenbrenner
Representative Les Aspin
Representative Alvin Bahlus
Representative Robert Kastenmeier
Representative David R. Obey
Representative Henry S. Reuss
Representative Clement Zablocki
Council on Environmental Quality
Department of Housing and Urban Development
Advisory Council on Historic Preservation
Department of Health, Education, and Welfare
Department of Labor
Department of Commerce
Department of Interior
Department of Agriculture
US Fish and Wildlife Service
Department of Transportation
US Army Corps of Engineers
National Park Service
US Geological Survey
USEPA Regional Offices
B. State
Office of the Governor
Wisconsin Department of Natural Resources—Southeast District
Wisconsin Department of Administration
Wisconsin Department of Health and Social Services
Wisconsin Department of Local Affairs and Development
Wisconsin Department of Transportation
Wisconsin Department of Justice
Wisconsin Department of Industry Labor and Human Relations
Wisconsin Department of Business Development
Wisconsin Department of Revenue
Wisconsin Department of Public Instruction
Wisconsin Department of Agriculture
State Historical Society
XXXI
-------
C. Local
Southeast Wisconsin Regional Planning Commission
City of Muskego
City of West Allis
City of St. Francis
City of South Milwaukee
City of Oak Creek
City of Glendale
City of Milwaukee
City of Mequon
City of New Berlin
City of Greenfield
City of Wauwatosa
City of Franklin
City of Cudahy
City of Brookfield
Village of Hales Corners
Village of River Hills
Village of Fox Point
Village of Bayside
Village of Germantown
Village of West Milwaukee
Village of Shorewood
Village of Greendale
Village of Butler
Village of Elm Grove
Village of Whitefish Bay
Village of Brown Deer
Village of Menomonee Falls
Village of Thiensville
D. Groups and Citizens
Citizen Advisory Committee for the Draft EIS,
Cindy Roth, Coordinator
Robert R. Abrams
Janis M. Arthur
Carole Ann Earth
Jeanette Bell
Donald K. Builey
P. Ciccantelli
Thomas Crawford
James Doetze
Honorable Lynn Eley
Thomas J. Farrahy
Gerard Froh
Norman Gill
Honorable Chester Grobschmidt
xxxii
-------
James E. Grootemaat
Randolf A. Gschwind
J. E. Hackel
Honorable Francis P. Havey
Henry Kolbeck
Suzane Kraase
Charles E. Kroeger
Jan Marsh
Shirley Mueller
Helen C. Newman
Leonard Pampel
Suzanne Ratkowski
Terry Rozga
Marvin Schroeter
Gerald M. Schwartz
David Sharpe
Hall Smith
Brien Sobanski
Thomas Spellman
Dawn Marie Staccia
Gail Miller Wray
For a complete list of individuals and agencies receiving the
DEIS, contact U.S. EPA Region V, Chicago, Illinois.
XXXI11
-------
LIST OF PREPARERS
-------
List of Preparers
United States Environmental Protection Agency
Chief of EIS Section
Project Officer
Eugene Wojcik
Michael 0'Toole
Wisconsin Department of Natural Resources
MMSD Environmental Impact Coordinator
Special Assistant to MMSD Projects
Environmental Engineer-MMSD Unit Leader
Environmental Engineer-Municipal Wastewater
Section
Planning Analyst
Environmental Engineer-Wastewater EIS
Unit-Bureau of Environmental Impact
Environmental Engineer-Water Quality Manage-
ment
Environment Specialist-Water Quality Manage-
ment
Director, Bureau of Environmental Impact
Steve Ugoretz
Dorothy Harrell*
Jay Hochmuth
Charles Burney
Michael Desrosier*
William Baunann
Sharon Meier
Michael Llewelyn
Roger Fritz
Thomas Bennwitz
Roger Bannerman
H.S. Druckenmiller
ESII
Principal in Charge
Senior Project Manager
Senior Project Manager
Project Managers
Principal Authors
Editor
Engineering
Edward F. Bradley
Thomas L. Meinholz
John H. Baldwin
Kevin J. Fay
Edward J. Powelson
Robert Evangelist!
Peter R. Spinney
Melissa M. McGuire
Kevin J. Fay
Robert Evangelisti
Mark G. Madden
King K. Moy
Steven C. Schory
Reed Rodenkirch
Scott Stanke
Mary P. Kerr
*Incumbent during the preparation of the Draft EIS.
XXXIV
-------
Socioeconomics
Natural Science
Typists
Wapora, Inc.*
Project Administrator and Editor
Senior Enviornmental Engineer
Senior Water Quality Scientist
Health Scientist
Edward J. Powelson
Mark A. Vannucci
Louise M. Palagano
James W. Hock
Richard J. Fulk
David L. Haselow
David B. Kendziorski
Bruce F. Leon
Suzanne S. Skone
Sally A. Arnold
Gloria Logan
DeAnn Calhoun
E. Clark Boli
J.P, Singh
Mirza Meghji
Gerard Kelly
Sjibcontractors
Consoer, Townsend & Associates
Assistant Vice President
Associate
Engineer
Engineer
Engineer
Engineer
Converse, Ward, Davis, Dixon, Inc.
Project Manager
Staff Consultant
Senior Geologist
Chief Geologist
Raymond J. Avendt
Wen C. Huang
Peter V. Cavagnaro
Stanley A. Labunski
Shin A. Ann
Louann Bewersdorf
Peter Spinney
Issa S. Oweis
Syed A. Pasha
Charles S. Robinson
Harper - Owes
Engineer
Scientist
Scientist
Real Estate Research Corporation
Vice President
Principal Counselor
Senior Analyst
Senior Analyst
Senior Analyst
Martin Harper
Clay Patmont
Starr Dehn
Margary al Chalabi
Stephen B. Friedman
Roberta Walker
Sholom Gliksman
Valerie Kretchmer
•Original EIS consultant for CSO analysis which was incorporated
into this document
XXXV
-------
INDEX
Access (plus Traffic) - 1-21, 3-132, 4-1, 5-145
Aesthetics - see Recreation
Agricultural Land - 1-20, 1-28, 5-61
Air Quality - 1-18, 1-19, 1-21, 2-6, 3-125, 4-1, 4-21, 4-40, 5-38
Algae - 3-123, 4-15 thru 19, 5-31, 5-32, 5-36
Ammonia -
Toxicity - 1-21, 1-26, 3-114, 3-122, 3-123, 4-10, 4-12, 4-14,
5-12, 5-19, 5-24, 5-25, 5-31
Un-ionized - 1-26, 1-28, 1-31, 3-114, 4-10, 5-2, 5-3, 5-6,
5-8, 5-31, 5-32
Aquatic Biota - 3-40, 3-123, 4-1, 4-16 thru 21, 5-34
Aquifer - see Groundwater
Archaeological Resources - 3-42, 4-1, 4-81, 5-153
Big Muskego Lake - 3-121, 4-14, 4-18, 4-35, 5-7
Biochemical Oxygen Demand - 3-104, 3-121, 4-8, 4-11, 4-12, 5-2,
5-3, 5-6, 5-8, 5-12, 5-14, 5-19, 5-24, 5-25, 5-67
Bonding - 3-127, 5-90, 5-91, 5-106, 5-110
Bypasses - 1-2, 1-4, 1-5, 1-14, 4-12, 4-13, 4-14, 4-35
Caddy Vista WWTP - 1-7, 1-9, 1-20, 2-8, 3-71, 3-98, 3-102, 3-121,
4-9, 4-13, 5-2
Cadmium - see Metals
Chlorination/Chlorine - 1-30, 3-67, 3-70, 3-113, 4-10, 5-2, 5-3,
5-6, 5-8
Clean Air Act - 2-6, 3-2, 3-4
Clean Water Act of 1977 - 1-1, 1-4, 2-5, 4-35, 4-38, 4-40
Coastal Zone Management Act - 4-37
Combined Sewer Overflow (CSO, 1-2, 1-4, 2-5, 3-78, 3-122, 4-2,
4-11 thru 13, 4-51, 4-52, 5-19
XXXVI
-------
Combined Sewer Overflow (CSO)
Abatement - 1-6 thru 8, 1-11, 1-15, 1-32, 2-6, 2-7, 3-76,
3-80, 3-115, 4-35, 5-19, 5-21, 5-22
Effects of - 3-91, 4-11, 5-10
Combined Sewer Service Area (CSSA) 1-18, 2-3, 3-23, 4-12, 5-12,
5-18, 5-20
Complete Sewer Separation Alternative 1-11, 1-18, 3-87, 5-19
Construction - 1-21, 3-41, 5-70, 5-48, 5-71, 5-137
Control Options - 3-5
Source Control - 3-5
Conveyance and Storage - 3-6
End-of-Pipe - 3-7
Instream - 3-9
Copper - see Metals
Cost - 1-22, 3-97, 3-120, 3-127 thru 3-129, 5-81
CSO Abatement/Peak Flow Attenuation Alternatives - 1-13,
1-15, 1-22, 1-25, 1-28, 3-86, 5-151
EPA's Preferred Alternative - 1-32, 3-120, 5-122
System Level Alternatives - 1-22, 3-26, 3-33, 3-36, 3-44
thru 47, 3-54, 3-57, 3-59, 3-128, 3-130, 5-82, 5-102, 5-106
Cost Distribution Methods - 5-89, 5-92
Individual Community Financing - 3-129, 5-93, 5-114
District Wide Financing - 5-93, 5-125
Other Methods - 5-94, 5-120
Dane County Circuit Court Order 1-4, 1-13, 2-5, 2-6, 3-1, 3-77,
3-79, 3-80, 3-91, 3-93, 4-35, 5-81
Deep Tunnels - 1-18, 1-25, 3-124, 3-132
Deer Creek - 4-4, 4-14, 4-18
Department of Natural Resources (DNR) 1-1, 2-5, 3-37, 3-93
Disinfection - 1-30, 3-67, 3-70, 3-113, 4-10, 5-6, 5-8
Dissolved Oxygen - 4-4, 4-8, 4-9, 4-12 thru 14, 4-16 thru 18,
5-2, 5-3, 5-10, 5-12, 5-23
Draw-down Effect - 5-55
Economic Impacts - 3-131, 5-114, 5-127, 5-128
Economy 4-1, 4-54, 5-127, 5-128
xxxvii
-------
Effluent - 5-29
Characteristics - 5-30
Discharge - 5-29
Limits (Standards) - 2-4, 2-5, 2-6, 5-2, 5-29
Employment - 4-57, 4-64, 4-69, 5-130
Employment Impacts of MFP - 1-18, 3-132, 5-130
Energy - 4-83, 3-42, 3-133, 3-134, 5-159
Engineering Feasibility - 3-42, 3-134, 5-168
Environmental Corridors - 2-6
Environmental Impact Statement Requirements - 2-4, 2-7, 2-8
Environmental Protection Agency (EPA) - 1-1, 2-5, 3-37, 3-112
EPA Preferred Alternative - 1-28, 1-29, 1-30, 1-31, 1-32, 1-33,
3-112, 5-1, 5-32, 5-34, 5-122
Fecal Coliform Bacteria - 5-2, 5-6, 5-8, 5-17, 5-19
Federal Water Pollution Control Act Amendments of 1972 - 1-4, 2-4
Fiscal Impacts - 1-27, 1-28, 5-78, 5-114
Indirect Fiscal Impacts - 5-75
of CSO Abatement - Peak Flow Attenuation Alternatives - 3-86
of System-Level Alternatives - 3-127, 5-85
Floodplains - 2-5, 4-1, 4-31, 4-32, 4-39, 5-57
Fox River Basin - 4-2, 4-4, 4-14
Funding
Federal - 2-4, 2-5, 4-49, 4-50, 4-52, 5-89
State - 4-49, 4-50, 4-52, 5-89
Future Development (Secondary Growth Impacts) 1-21, 3-41, 5-70,
5-72, 5-73, 5-76, 5-77
Geology - 4-26, 4-27
Germantown WWTP - 1-7, 1-8, 3-20, 3-100, 3-123, 4-9, 5-3
Groundwater - 1-21, 1-25, 3-40, 4-1, 4-2, 4-28, 4-31, 5-45
Historical Resources - 4-37, 5-153
xxxviii
-------
Industrial Pretreatment - 1-31
Infiltration and Inflow (I/I) - 1-2, 1-4, 1-6, 1-25, 1-29, 3-5,
3-22, 2-3, 3-24
Inline Storage Alternative - 1-7, 1-11, 1-18, 3-85
Inner Harbor - 1-25, 4-2, 4-9, 5-12
Instream Measures - 3-9, 5-29
Interceptors - 1-6, 1-21, 2-6, 2-7, 2-8, 1-31, 2-8, 3-71, 4-35
Caddy Vista - 2-8
Franklin-Muskego - 1-11, 3-73, 3-74
Franklin-Northeast - 1-11, 1-31, 3-73, 3-74
Hales Corners - 1-11, 1-31, 3-74, 3-75
Menomonee Falls-Germantown - 1-11, 1-31, 3-74, 3-75
Northeast Side Relief - 1-31, 3-74, 3-76
Oak Creek (North of Ryan Road) - 1-11, 1-31, 3-73, 3-74
Oak Creek (South of Ryan Road) - 2-81
Oak Creek Southwest - 2-8
Root River - 1-11, 1-31, 3-74, 3-75
Underwood Creek - 3-74, 3-75
Ryan Creek - 2-8
Underwood Creek - 1-11, 1-31
Jones Island WWTP - 1-4, 1-9, 3-9, 3-100, 4-9, 4-10, 4-15, 4-19,
4-22
Expansion - 1-15, 2-7, 4-38, 3-43, 3-66, 3-67, 3-68, 3-70
Lakefill - 1-27, 5-32
Outfall - 1-21, 1-26, 4-16, 5-31
Treatment - 1-9, 1-32, 3-15
Kinnickinnic River - 2-2, 4-1, 4-2, 4-10, 4-11, 4-13, 4-15, 4-17
Lake Michigan - 1-20, 1-27, 2-2, 4-1, 4-9, 4-10, 4-15, 4-19, 4-20,
3-122, 5-33
Lakefill - 1-19, 1-26, 1-27, 1-30, 1-32, 5-32, 5-173
Land Application - 1-10, 1-20, 1-31, 1-33
Landfill - 1-10, 1-20, 1-31, 1-33
Land Use - 2-6, 3-41, 4-1, 4-40, 4-48
Lead (see Metals)
Legal Requirements - 2-4, 4-35, 4-51
xxxi x
-------
Legality - 4-1, 4-35 thru 4-51, 5-178
Level of Protection - 1-29, 3-112
Local System-Level Alternative (Final) - 1-9, 1-19, 3-2, 3-26,
3-33, 3-100
Master Facilities Plan (MFP) - 1-1, 1-4, 2-1, 3-1, 4-35, 4-38,
4-48, 4-64
Menomonee River - 2-2, 4-1, 4-2, 4-9, 4-10, 4-11, 4-17, 4-27,
4-83, 5-12
Metals - 1-31, 5-12, 5-14, 5-17, 5-19, 5-21, 5-22, 5-24, 5-25
Metropolitan Intercepting Sewers (MIS) - 1-2, 4-12, 4-13
Milorganite - 1-10, 1-20, 1-21
Milwaukee County Debt Limit - 3-130
Milwaukee River - 1-20, 2-2, 4-1, 4-9, 4-10, 4-11, 4-16, 4-17,
4-27, 4-83, 5-12
Mitigative Measures - 1-27, 1-31
MMSD Planning Area - 2-3, 4-1, 4-2, 4-11, 4-32, 4-33, 4-34
MMSD Recommended Plan - 1-6, 3-109, 5-1, 5-32
Modified GST/Inline Alternative - 1-13, 3-87, 5-29
Modified Total Storage Alternative - 1-13, 1-18, 1-28, 1-29, 3-91
Mosaic System-Level Alternative (Final) - 3-2, 3-106, 5-35
Muskego Northeast WWTP - 1-9, 1-10, 4-9, 3-18, 3-102, 5-3
Muskego Northwest WWTP - 1-7, 1-9, 3-19, 4-9, 4-35, 5-7
Muskego Rendering Company WWTP - 1-10
National Environmental Policy Act (NEPA) - 4-37
National Historic Preservation Act - 4-37
New Berlin WWTP - 1-7, 1-8, 4-9, 4-14
New Berlin Southeast WWTP - 4-32
Nitrogen - see Ammonia
xl
-------
No Action Alternative - 1-14, 3-98
Noise - 3-41, 4-1, 4-77, 4-78, 4-79, 4-80, 5-138
Non-point Source Pollution - 1-4, 4-4, 4-11, 4-12, 4-40
Oak Creek - 3-73, 4-2, 4-4, 4-13, 4-18
Odors - 1-19, 2-1, 3-40, 4-1, 4-22, 4-25, 4-26, 5-38, 5-43
Organic Pollutants - 5-12
Outer Harbor - 1-26, 3-122, 4-9, 4-10, 4-15, 4-19, 5-29
Outfall - see Jones Island Outfall or South Shore Outfall
Particulates - 5-43
Pathogens - 1-4, 1-14, 3-10, 3-13, 4-4, 4-9, 4-11, 4-12, 5-2, 5-31
PCE's - 4-15, 4-19
Phosphorus - 4-9, 4-13, 4-14, 4-15, 4-19, 5-32
Phytoplankton - see Algae
Planning Area - see MMSD Planning Area
Plant Nutrients - 4-8, 4-9, 4-12, 4-13, 4-14, 4-15
Point Source Pollution - 4-4
Pollutant Loads - see Water Quality
Population - 4-52, 4-53, 4-54, 4-55, 4-56
Prime Agricultural Land - 2-6, 3-40, 5-61
Property Taxes - 4-74
Average - 1-23, 1-24, 4-74, 4-75
Existing - 4-69, 4-73, 4-75
Industrial - 4-64, 4-67, 4-69
Public Health - 2-1, 2-2, 3-41, 3-132, 4-1, 4-12, 4-21, 4-29, 5-141
Recreation and Aesthetics - 3-41, 4-1, 4-24, 4-39, 4-40, 4-81, 4-82,
4-83, 5-157
Regal Manors WWTP - 1-9, 3-19, 4-14, 5-7
Regional Plan C208 Plan) - 2-3, 4-40, 4-42
xli
-------
1
Regional System Level Alternative - 1-19, 3-2, 3-36, 3-105, 5-102
Resource Conservation and Recovery Act - 4-37
Resources - 4-83, 4-84, 4-85, 5-164
River and Harbor Act of 1899 - 4-37
Root River - 1-20, 4-2, 4-4, 4-9, 4-13, 4-14, 4-17, 4-18
Safety - 5-144
School Sisters of Notre Dame WWTP - .1-10, 4-9
Scour - 1-15, 1-18
Screening of Alternatives - 3-1, 3-37, 3-82
Primary - 3-42
Secondary - 3-43
Sediment Loadings - 5-23
Quality - 1-18, 4-15
Sewers
Combined - 1-2, 2-3, 4-35, 5-152
Separated - 1-2, 1-11, 2-3, 2-4, 4-35
Sewer System Evaluation Survey (SSES) - 1-6, 1-25, 2-6, 2-7, 3-25,
4-75
Sludge - 3-70, 4-24
Soils - 4-1, 4-27, 4-29, 4-48
Solids Handling (or Management) - 1-6, 1-10, 1-19, 1-20, 1-31, 1-33,
2-6, 2-7, 3-22, 3-70, 3-114, 4-35
South Milwaukee WWTP - 1-7, 1-9, 3-19, 3-102, 4-9
South Shore WWTP - 1-9, 1-15, 1-19, 1-20, 1-27, 1-30, 2-7, 3-16,
3-68, 3-69, 3-70, 3-100, 4-9, 4-15, 4-16, 4-18, 4-19, 4-22,
4-26
Outfall - 4-16, 4-19
Suspended Solids - 4-8, 4-9, 4-12, 4-13, 4-14
xlii
-------
System Levels
Local - 1-7
Mosaic - 1-7
Regional - 1-7
Subregional - 1-7
Tess Corners Creek - 4-9, 4-13, 4-18, 4-35
Thiensville WWTP - 1-7, 1-9, 1-20, 3-21, 3-100, 4-2, 4-9, 4-12,
5-10
Threatened and Endangered Species - 2-5, 4-1, 4-20, 4-21, 4-39,
5-37
Topography - 4-1, 4-27
Toxic Substances - 3-6, 4-4, 4-10, 4-19
Traffic - see Access
Transportation - see Access
Treatment Plants - see individual names
Unionized Ammonia - see Ammonia
U.S. District Court Stipulation - 2-5, 2-6, 4-35
User Charge for distributing MMSD operation and maintenance costs
- 1-22, 4-66, 4-67, 4-69, 4-72, 4-75
Wastewater Conveyance - 1-6, 1-11, 1-21, 1-31, 1-33, 2-8, 3-71,
3-104, 3-105, 3-109, 3-111, 3-115
Wastewater Treatment - 1-1, 1-5, 1-7, 1-30, 1-32, 2-8, 2-11, 3-66,
3-68, 3-100, 3-105, 3-106, 3-112, 3-115, 4-9
Water Quality
Existing - 2-1, 2-2, 2-10, 3-120, 4-11
Objective (DNR) 1-4, 1-5, 4-5, 4-7, 4-11
Future - 1-15, 3-120, 5-2
Standards - 1-29, 2-5, 2-6, 3-91, 4-4, 4-5, 4-7, 4-12, 4-13,
4-38
Wet Industries - 4-69, 4-75
Wetlands - 2-5, 4-1, 4-33, 4-34, 4-35, 4-39, 5-59
Whitnall Park Pond - see Water Quality
xliii
-------
Wildlife Habitats - 4-1, 4-33, 5-60
Wisconsin Electric Power Company WWTP - 1-10, 4-9
Wisconsin Environmental Policy Act (WEPA) - 4-37
Wisconsin Pollution Discharge Elimination System (WPDES) - 2-5
Zinc - see Metals
Zooplankton - see Aquatic Biota
xliv
-------
U.S. Environmental Protection
Region 5, Library (5PL-16)
230 S. Dearborn Street,, Boom 1670
Chicago,. IL 60604
-------