&EPA
                                   United States
                                   Environmental Protection
                                   Agency
                                Municipal Environmental Research
                                Laboratory
                                Cincinnati OH 45268
                                   Research and Development
                                EPA-600/S2-80-178 Feb. 1981
Project  Summary
                                   The  Cost  of  Alternative
                                   Flue Gas  Desulfurization  (FGD)
                                   Sludge  Disposal  Regulations

                                   A  Technical  Cost Analysis for the
                                   Utility Industry
                                   Howard L. Rishel
                      - i ' '• •'•;vyr:r:;;; i-Yoic-cHon  Agoncy
                                                                  * ;"• ry
t
t
  To meet the sulfur dioxide emission
limits of the Clean Air  Act,  some
utilities  have  turned  to flue gas
desulfurization (FGD). Its acceptance
by the industry and the various sludge
treatment  and  disposal  options
available to the industry are described
in this report. Current Federal and
state  regulations affecting  FGD
sludge disposal are discussed and
placed in a conceptual  framework
from which regulatory scenarios are
developed.  These scenarios  were
applied  to the current  (1980) and
projected (1985) FGD capacity to
estimate what changes, if any, current
utility  operations  would need  to
achieve  compliance. Using the best
available  cost  data base  for  these
disposal alternatives, region-specific
cost estimates were developed for 10
model power plants for  each of 5
disposal  options. Applying  each
regulatory scenario, the cost impact
on the  utility industry  was then
estimated for the  50  different
situations.
  This Project  Summary was devel-
oped by  EPA's Municipal Environ-
mental Research Laboratory, Cincin-
nati. OH, to announce key findings of
                               -, .':orn Street
                               >;s  60504
the research project that is fully docu-
mented in a  separate report of the
same title (see Project Report order-
ing information at back).

Introduction
  The  Clean Air  Act  and  its
amendments   have  prompted  the
widespread implementation of wet flue
gas desulfurization (FGD)  systems by
utilities in an effort  to meet sulfur
dioxide emission limitations. This trend
has been further  enhanced  by the
current U.S. energy policy favoring the
use of native  coal reserves. The end
result  is  a   projected  substantial
increase in FGD implementation in the
United States through  1985.
  With the use of the predominant
available  FGD  technologies,  large
volumes  of  by-product sludges
requiring disposal are generated. These
sludges have been and will continue to
be disposed of to land, either to ponds as
a  slurry or to landfills as a dry material.
Ponding is currently the most common
method of FGD sludge disposal. Sludge
ponds are typically lined with in situ
soils, although synthetic and imported
natural liners  (particularly clay) have
begun to find application. Disposing of

-------
treated, or dewatered, or both types of
sludge to landfill is rapidly gaining favor
and should account  for a majority of
new sludge disposal  capacity by the
early  1 980's.  FGD  sludge landfills are
currently   used   to  dispose  of
mechanically  dewatered  sludge,
dewatered sludge mixed with dry ash,
and chemically stabilized sludge.
  The data base established thus far for
FGD sludge indicates a need to regulate
its disposal, primarily because of the
potential for ground  water  contamin-
ation   and  land  degradation  (waste
instability) resulting from the disposal of
large volumes of this material to land. To
date,  the states, typically state  solid
waste and water quality agencies  in a
site-specific permitting process,  have
regulated FGD sludge disposal.
  The  purpose of  this  project was to
review the  cost to utilities  of  various
approaches to regulating FGD sludge
disposal. These  regulatory  scenarios
are  structured to demonstrate  the
incremental   cost  of  increasingly
stringent technical requirements  and
are  not  intended  to  parallel  any
proposed  EPA  regulations  for  FGD
sludge disposal.

The Regulation of FGD Sludge
Disposal
  Current Federal laws that may affect
future  regulation   of  FGD  sludge
disposal  include  the  Resource
Conservation and Recovery Act (RCRA)
of 1976 (PL 94-580), the amendments
of  1977,  the  Marine  Protection,
Research, and Sanctuaries Act of 1 972
(PL 92-532), the Federal Water Pollu-
tion Control Act of 1972 (PL 92-500),
and the Federal Surface Mining Control
and Reclamation Act of 1977 (PL 95-
87)  The disposal  of FGD  sludge  is
specifically  addressed only in RCRA.
  The impact  of Federal FGD sludge
disposal  regulations  on  the  utility
industry  would depend on the severity
of the regulation. Recent research and
current regulatory practice indicate that
ground  water  protection   and  the
prevention   of   permanent  land
degradation are the principal environ-
mental  concerns  when  disposing  of
FGD sludge. The degree  of  protection
that is necessary will be specific to each
proposed disposal site.
  To assess the cost impact of a range of
regulatory  approaches,  a set of five
regulatory  scenarios  was  developed.
Beginning  with Scenario No  1, each
scenario represents  an increasingly
stringent regulation based on (1) added
protection  of  ground  water  and  (2)
added  sludge  stability  to improve the
potential for site reclamation, or (3) a
universal  requirement for  sludge
treatment and disposal regardless of
site-specific factors. The five regulatory
scenarios considered are as follows:

 No.  1.  Federal  Advisory--State
        Legislation and Enforcement:
        Simple  permitting, stabiliza-
        tion   not  required  and  not
        commonly used.
 No.  2.  Federal  Advisory--State
        Legislation and Enforcement:
        Site-specific  evaluation with
        stabilization sometimes
        required.
 No.  3:  General Federal Legislation--
        State  Enforcement: Physical
        stabilization required;  no
        ponding
 No.  4-  Comprehensive  Federal
        Legislation — State Enforce-
        ment upon  Approval:  Chem-
        ical  stabilization  required  in
        urban areas.
 No.  5:  Comprehensive  Federal
        Legislation and Enforcement--
        No State Involvement:  Chem-
        ical  stabilization   universally
        required; specifications  given
        for the stabilization technique.
Developments of Model Power
Plants and Associated Sludge
Disposal  Costs
  An accurate assessment of the cost
effect of each scenario on the utility
industry required knowledge of the cost
of each  disposal alternative  to each
FGD-equipped plant An approximation
of these cost effects was  developed
using  a set  of  10  model  plants,
representing three geographic regions,
four coal types,  and urban and rural
locations. For each  model plant, capital
cost, annual operating cost, and lifetime
revenue requirements were estimated
for each of  six disposal  options:

1.  Unlined ponding

2.  Clay-lined ponding

3.  Dry (dewater) and landfill

4  Dravo

5.  IUCS

6  Dry (dewater), mix,  and  landfill
  Each of the coal-fired utility genera-
ting  plants projected to be on line by
1980 and by 1985 was then assigned to
one of the 10 model plant categories to
produce an approximate industry profile
of waste generating capacity. The pro-
file was subjected to each regulatory
scenario to  estimate how each utility
would shift from its preferred disposal
option  to  its remaining least-cost dis-
posal option under the revised regula-
tory  scenario. In this manner, the cost
effect of each utility and to the industry
as a whole were  estimated  as  the
incremental  cost  of  complying  with
each successive degree of regulation.
  It  should  be emphasized that this
approach includes only plants that will
be either on line by mid-1980 or those
that  will be on line by mid-1985. Al-
though cost  impacts were estimated for
the entire remaining life span of each of
these  plants,  a  declining  operating
scenario was used  in  which  annual
generation decreases over the life span
of each plant. Thus, the plants in the
1980 group included substantially more
retrofit  situations  than those  for the
predominantly younger, 1985 group of
plants. The result of this shift in group,
composition is a substantial increase in]
total  remaining  lifetime  generation^
even  though  coal-fired  generating^
capacity is  expected to increase only
moderately between 1980 and 1985.

Utility Industry Response to
Regulatory Scenarios
  In  the absence  of additional regula-
tory  constraints (Scenario No.  1), the
utility industry  from a  post-1980  per-
spective will be committed to spending
close to $2.6 billion (1980 dollars), and
from a post-1985 perspective over  $3.1
billion (1980 dollars), for FGD sludge
disposal. Scenarios No. 2through Bare
expected to add  from  $18 to $972
million to those future revenue commit-
ments for the post-1980 estimate and
from $35 million to $2.32 billion for the
post-1985  estimate.   This  relatively
modest increase in future revenue com-
mitments is due to two factors: (1) older
plants  using high-technology retrofits
will  be 5 years older by 1985, so that
their post-1985 revenue commitments
will  be  substantially reduced; and (2)
new plants coming on line by 1985 will
have their entire useful life ahead of
them; they will  be situated on cheaper,
rural land, and will have selected the
cheaper, nonretrofit disposal options as4
part  of their  original designs.        J

-------
I
  The  post-1980 to post-1985 shift to
newer plants (combined with an abso-
lute  increase   in  future  coal-fired
generation) allows the average cost per
kilowatt hour (in terms of 1980 dollars)
to  decrease  The  result  is  that  the
average  future  (1980 dollars)  to  the
consumer for FGS  sludge disposal is
expected  to  range  from  1.017 mills
(Scenario No. 1)to1 400 mills (Scenario
No. 5) per kilowatt hour after 1980, and
from 0759  (Scenario No  1) to  1.321
(Scenario No. 5) mills per kilowatt hour
after 1985. It should be re-emphasized
that these cost estimates do not include
plants  coming on line  after 1985.

Key Conclusions
  In general, more  stringent disposal
regulation resulted in (1) lower per unit
capital requirements than those for cur-
rent disposal practices and (2) high life-
time revenue requirements as a result
of higher operating costs (labor and raw
materials in particular).
  The industry profile  for 1980 shows
that in most  cases  sludge ponding is
more prevalent in the western U.S. than
in the  eastern  U.S  because of more
favorable  site-specific conditions The
cost effect of more stringent regulatory
scenarios (particularly the  universal
stabilization  requirement)  in the West
was proportionately greater than it was
for the Midwest  or East.
                                              and remaining plant life span were not
                                              allowed to influence this choice, as they
                                              would in practice.
                                                Another topic of interest is the impor-
                                              tant interrelationship between sludge
                                              disposal  costs, electricity rate sched-
                                              ules,  subsequent changes in electricity
                                              demand, and the ultimate distribution
                                              (by customer  type)  of  FGD  sludge
                                              disposal  costs  Sludge  disposal costs
                                              may be lagged over time and have differ-
                                              ential impacts  on various classes of
                                              customers   Moreover,  demand
                                              elasticity may vary  by customer class
                                              Should EPA  choose  to regulate FGD
                                              sludge  disposal  specifically  on   a
                                              national  scale,  the above-mentioned
                                              interrelationship will  be addressed as
                                              part of the economic impact analysis.
                                                The other general area that deserves
                                              additional study is the rapid evolution of
                                              FGD  sludge  disposal  technology  in
                                              response to  the changing regulatory
                                              climate and its resulting cost impact on
                                              the utility industry  Specific areas that
could be enhanced in an update of this
study include:

 •  Second-generation  FGD  sludge
    disposal technologies

 •  Trends in FGD

 •  Updated  forecasts  of  FGD  imple-
    mentation

 •  Long-range  utility  power genera-
    tion trends

 •  Impact of RCRA and Mine  Safety
    and Health  Act (MSHA) on  FGD
    sludge management
  Consideration  of  the above-named
technical  and  institutional  changes,
combined with a more exact analysis of
disposal economics, would  provide a
solid  foundation for  the  economic
impact analysis required in conjunction
with impending  new Federal  regula-
tions for FGD sludge disposal
t
Recommendations
  Research recommendations resulting
from this study may be categorized into
two general areas. (1) incorporating the
diversity of local utility conditions into
the  analysis,  and  (2)  updating the
current data base to reflect changes in
the regulatory climate and the evolution
of FGD technologies.
  With regard to  the first area, the
conceptual nature of this study required
the use of many simplifying assump-
tions.  As  a  result,  important local  or
plant-specific  cost  factors  were not
accounted for that  could  significantly
affect the costs projected in this study
  In addition to addressing these factors
on a local rather than  a regional basis,
any  subsequent  research embracing
these  plant-by-plant variations should
also  consider  the effects  that current
sludge disposal capital investments and
remaining plant lives have on the selec-
tion of either a sludge disposal method
or a compliance strategy for sulfur oxide
control In this study, sunk capital costs
                                                 Howard L Ft/she/ is with SCS Engineers, Long Beach, CA 90807.
                                                 Donald E. Banning and Oscar W. Albrecht are the EPA Project Officers (see
                                                   be low]
                                                 The complete report, entitled "The Cost of Alternative Flue Gas Desulfurization
                                                   (FGD) Sludge Disposal Regulations," {Order No. PB 81 -118 895; Cost: $ 12.50,
                                                   subject to change) will be available only from-
                                                         National Technical Information Service
                                                         5285 Port Royal Road
                                                         Springfield, VA 22161
                                                         Telephone: 703-487-4650
                                                 The EPA Project Officers can be contacted at:
                                                         Municipal Environmental Research Laboratory
                                                         U.S. Environmental Protection Agency
                                                         Cincinnati, OH 45268

-------
                                                                                                                                                         <
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Postage and
Fees Paid
Environmental
Protection
Agency
EPA 335
Official Business
Penalty for Private Use $300
     r
                             ~i
     L
                             J
                                                                                                           U.S. GOVERNMENT PRINTING OFFICE: 1981—757-064/026

-------