-8
 United States
 Environmental Protection
 Agency
Municipal Environmental
Research Laboratory
Cincinnati OH 45268
Research and Development
EPA-600/S2-84-155 Nov. 1984
Project  Summary
 Sewage  Sludge  Versus
 Commercial  Methods  for
 Reclaiming  Strip-Mine  Soils

 Lilia A. Abron-Robinson and Leon W. Weinberger
  Two types of methods for reveget-
ating strip-mined soils were compared
with regard to cost, feasibility, and
environmental impacts:  the use of
municipal sewage sludge and commer-
cial methods.
  The in-depth investigation included
visits to strip-mined sites being reclaimed
with sewage sludge  and  a literature
review to gather data on  strip-mined
land reclaimed with commercial meth-
ods. The literature review  was neces-
sary because adequate data were not
available otherwise.
  Cost comparisons of the two reclama-
tion methods were made using only
those costs associated with renovation
after the sludge or commercial materials
were delivered to the site. This compari-
son indicated that reclamation of strip-
mined land with sewage sludge  costs
roughly the same as commercial meth-
ods.
  The study also used available data to
show that both commercial methods
and sewage sludge application could
be used successfully to reclaim  strip-
mined soils  with no adverse environ-
mental  impacts. Selection of the  re-
clamation practice should be based on
site-specific evaluations of  cost, social.
political, and aesthetic factors.
  This Project Summary was developed
by EPA's Municipal Environmental
Research Laboratory, Cincinnati, Ohio,
to announce key findings of the research
project that is fulfy documented in a
separate report of the same title (see
Project Report ordering information at
back).

Introduction
  The process for the surface mining of
coal, called strip mining, is accomplished
with either area or contour stripping. Both
practices involve the removal  of over-
burden materials to expose the coal, the
removal of the  coal, and the  replace-
ment of overburden into the excavated
pits. Strip-mining operations typically
leave  behind steeply sloping  spoil or
waste  mounds depleted of plant nutrients
and organic matter. These mounds
rarely  support vegetation and are easily
eroded, causing contamination  of near-
by water supplies and the destruction of
wildlife habitat.  These mounds prevent
rapid, productive redevelopment of strip-
mined lands.
  The  Surface Mining Control and Rec-
lamation Act of  1977 (PL-95-87) was
passed by  the Federal government in
response to citizen  concern and the
negative environmental impacts of the
waste  mounds. Section 508 of the Act
sets forth the general requirements for
reclamation plans submitted as part of
application  permits. The main objective
of reclamation is to restore the ability of
the residual spoils to support a vegetative
cover.
  Reclamation. with commercial  meth-
ods relies on products readily available
on the open market. Inorganic fertilizers
are  used in combination with lime and
topsoil to  restore the fertility of strip-
mined lands.
  Reclamation with municipal  sewage
sludge uses the  residue remaining after
the  treatment of wastewater.  Sewage
sludge contains essential plant nutrients,
organic matter, and  a high alkalinity
that can neutralize acid soils. The dis-
posal  of sewage sludge  has  been a
problem for many municipalities, and
using  it for reclamation provides a
beneficial alternative to sludge disposal.
Sewage sludge also contains various

-------
trace elements (such as  metals) that
could cause environmental problems,
depending on the quality of the sludge.
Thus environmental monitoring programs
are required by Federal and usually State
regulatory  agencies to  document en-
vironmental changes at  sludge applica-
tion sites.
  This study was undertaken to compare
the costs, feasibility, and environmental
impacts  of both  types  of  strip-mined
reclamation methods (commercial and
municipal sewage sludge). The  investi-
gation included visits to strip-mined sites
being reclaimed  with sewage sludge
and a literature review to gather data on
strip-mined land  reclaimed using com-
mercial methods. The review was neces-
sary because adequate  data  were not
available otherwise.

Reclamation Sites

Fulton  County, Illinois
  At the Fulton  County site, sewage
sludge is being applied to about 480 ha
(1,200  acres).  The  sludge disposal
operation has  continued  since 1971,
with certain fields receiving the maximum
annual sludge application of 576 metric
tons/ha. Successful  reclamation has
been achieved,  and both soil organic
levels and fertility  have increased.
Growing a corn crop each  year and
selling it to a local animal feedlot results
in a financial return.
  Extensive environmental  monitoring at
the site does not indicate any significant
adverse  impacts on surface water  or
groundwater. Although cadmium con-
centrations have  increased in the corn,
they are within  Federal limits for animal
feed.
  Costs for the Fulton County operation
are primarily influenced by transportation
and land costs.  The distance from the
sludge generation point to the disposal
site incurs transportation costs that are
nearly half of the total cost. The entire site
includes 6,100 ha (15,250 acres) located
outside the jurisdiction of the municipal
agency  producing the sewage sludge.
The land costs and  real  estate  taxes
would  not usually be incurred if a
municipality used sludge to reclaim land
in its own jurisdiction. The Fulton County
operation  has permanently solved a
sludge  disposal problem, reclaimed
strip-mined land, and been  positively
received by the public.

Ottawa, Illinois
  The State of Illinois requires that about
0.8 ha (2 acres) of a 60.7-ha (150-acre)
strip-mined site be reclaimed to demon-
strate the effectiveness of using sewage
sludge before  the remaining area  is
subsequently reclaimed. Digested lagoon
sludge was applied to the area,  and
grass was sown in late 1979. The pilot
project successfully reclaimed the site by
producing a flourishing grass cover.
  Environmental  monitoring did not
indicate any adverse impact on ground-
water or surface water.  Costs  for the
project were greatly influenced by the
sludge transportation  distance, which
represented more than 64 percent of the
total costs for reclaiming the 0.8-ha (2-
acre) site.
  The Ottawa  operation  provides  a
viable sludge disposal operation. Though
no  large volume  of sludge has  been
used to date, the project demonstrates
the  usefulness  of sludge in reclaiming
strip-mined sites.  Overall,  the  Ottawa
operation has had positive  public  reac-
tions, with  no negative reaction of any
kind. In fact, it may influence other private
concerns to enter into similar ventures.

Sites Using Commercial
Methods
  A literature review was conducted  to
gather data on strip-mined land  that
had been reclaimed using commercial
methods. The  review indicated  that
although commercial methods  can be
successful for reclamation, the vegetation
may not  survive on very acid soils if the
underlying acids migrate upward to the
root zone. On very acid spoils, the depth
of the topsoil should be increased, and
limestone should be applied before the
topsoil is added. In  all cases, periodic
fertilization and liming are needed  to
maintain a good vegetative  ground
cover.
  The data  also indicated that the water
quality of acidic  mine spoil runoff is
rapidly  upgraded after  the spoil  is
covered with topsoil.  The duration of this
improvement depends on the stability of
the  topsoil  and the growth of the plant
cover. Groundwater quality has shown a
short-term  reduction in  acidity and
sulfate concentration following  mine
spoil reclamation.

Cost Analysis
  The full report presents only cost data
for sites where the costs were actually
incurred and documented. The data
were developed using two scenarios: (1)
an  acid  strip-mined  site with relatively
steep slopes reclaimed to produce a
forage crop similar to the Ottawa opera-
tion, and (2) a neutral-pH soil withtlatter
slopes reclaimed to  support  row crop
agriculture similar to the Fulton County
operation.  Cost estimates were developed
for each scenario with a range for unit
and total costs. Earthworking generally
incurred the greatest  unit cost.
  Cost comparisons for reclaiming strip
mines using sludge and commercial
methods are difficult to make because
of the dissimilarities of the two methods
and  the differences  in the cost data
bases available.
  For purposes of comparison, costs  for
reclaiming with sludge included only
those costs associated with the operation
after the sludge was  delivered (monitor-
ing, staff, sludge application, site prepar-
ation, and  farming costs). Therefore, the
total unit costs used for comparison with
commercial  methods for the  Fulton
County and  Ottawa  operations were
$9,045/ha (S3,660/acre) and $26,8047
ha ($ 10,850/acre), respectively. The unit
costs for commercially reclaiming the
two sites ranged from $8,382/ha ($3,3957
acre) to $15,543/ha  ($6,290/acre) and
from $7,243/ha ($2,930/acre) to $13,5687
ha ($5,495/acre), respectively.  These
costs do not take into consideration the
degree  of  reclamation achieved at any
of the sites studied or described. The rate
of sludge application that would  be
required to be equivalent to commercial
methods of reclamation is not clear, so a
range of reclamation costs was calcu-
lated to achieve the various reclamation
objectives  described as follows.
  The main objective of the  Fulton
County operation was to build up organic
matter  since the soil pH  was neutral.
Costs were estimated for achieving 1, 2,
and 3 percent soil organic matter, which
corresponds to a sludge application rate
of 100, 200 and 300 metric tons/ha,
respectively. The costs ranged from
$13,546/ha ($5,485/acre) to $40,6387
ha  ($16.450/acre).  The  objective  of
reclamation  at the Ottawa site was to
neutralize  the acid  soils  and promote
grass growth. Costs were  estimated for
sludge  application rates ranging from
1,000 to 2,500 metric tons/ha, and they
ranged  from  $10,860/ha ($4,400/acre)
to $27,150/ha ($11,000/acre).
  Reclamation  costs for commercial
methods were estimated for each scenario.
Estimates were made for costs of topsoil
replacement  ranging  from 30 to 122 cm
deep. The estimates ranged from $8,3827
ha ($3,395/acre) to $29,8087 ha ($12,0707  ^
acre) for  site 1, and from $7,243/ha  I
($2,935/acre) to $27,833/ha ($ 11,2707

-------
acre) for site 2. Municipal sludge applica-
tion  for strip-mined reclamation was
shown to be roughly equal  in cost to
commercial reclamation methods. A one-
time sludge application (Ottawa) appeared
to be  less costly and more comparable to
commercial methods.

Social and Environmental
Impacts
  Selection of a  sludge management
strategy cannot be based solely on cost.
Land  reclamation  using sewage sludge
offers the municipal  agency a productive
use for a  waste product.  The public
usually reacts positively to using sludge
for reclamation, as this practice tends to
be  more aesthetically  acceptable than
a landfill or an incinerator complex.
  Residents near  the reclamation  site
may oppose the transportation of sludge
outside the jurisdiction of the sludge-
generating municipal agency. The public
may also be concerned with the potential
for environmental degradation posed by
the presence of many trace elements in
the sludge.
  Private companies  may  chose to
reclaim their strip-mined lands using
sewage sludge to improve public rela-
tions, or they may avoid it  because of
public concern.  Additionally,  these
companies are notgenerallyfamiliar with
the concept of reclamation using sewage
sludge. They may riot have the proper
equipment for applying sludge and may
also be hesitant about becoming involved
with the requirements and  red tape of
municipal agencies.

Conclusions
  The  results of the  environmental
monitoring  at the Ottawa and Fulton
County sludge reclamation sites indicate
that municipal sewage  sludge does not
adversely affect groundwater, surface
water, soil,  or crops  when properly
managed. The data from these two sites
show that the use of sewage sludge for
strip-mined  reclamation is a  highly
satisfactory procedure, since sludge
restores the neutral  pH of acid soils and
increases  the nutrient and organic
matter content. The Fulton County site is
now producing corn,  and the Ottawa
site supports a vigorous stand of grass.
  The  literature survey revealed that
commercial  methods would  not  nega-
tively affect groundwater, surface water,
soil, or crops if properly managed.  But
commercial methods may have a  short-
lived effect, since  there appears to be a
tendency  for the underlying acids to
migrate upward to the root zone even-
tually and affect the growing plants.
  Sewage sludge may thus have a more
permanent effect  on keeping a good
vegetative cover  on renovated, strip-
mined  land. This tendency may make
the sewage sludge renovation  of strip-
mined land attractive, even if it is more
costly.

Recommendations
  1.  Factors that should be considered
     when selecting  sewage sludge or
     commercial methods for reclaiming
     strip-mined lands include the owner-
     ship of the site, the availability of
     sewage sludge,  the sludge  trans-
     portation  distance,  and the pros-
     pects for short- or long-term disposal.
  2.  The cost comparison procedure will
     vary depending  on  who is  making
     the comparison—the strip-mine
     owner or  the sludge generator. An
     owner should compare the costs of
     both practices based on site-specific
     information,  whereas a  sludge
     generator should compare the cost
     of  land reclamation with  that for
     other  viable  sludge management
     options.
  3.  Insofar as  possible, cost comparisons
     for sewage sludge and commercial
     methods should be made for achiev-
     ing the same end conditions.
  4.  Many studies have been conducted
     to demonstrate that  sewage sludge
     can be used to renovate  strip-
     mined land. Thus attention should
     now  be paid  to improving opera-
     tions  (such as methods of applica-
     tion,  transportation, etc.)  and to
     defining more clearly the level of
     renovation  achieved by  various
     sludge application rates.
  The full report was submitted in partial
fulfillment of Contract No. 68-03-3018 by
PEER Consultants, Inc., Rockville, Maryland
20852, under the sponsorship of the U.S.
Environmental  Protection Agency.

-------
     LiliaA. Abron-Robinson and Leon W. Weinberger are with PEER Consultants,
       Inc., Rockville, MD 20852.
     Gerald Stern is the EPA Project Officer (see below).
     The complete report, entitled "Sewage Sludge Versus Commercial Methods for
       Reclaiming Strip-Mine Soils,"(Order No. PB 85-107 779; Cost: $13.00,
       subject to change) will be available only from:
             National Technical Information Service
             5285 Port Royal Road
             Springfield, VA22161
             Telephone: 703-487-4650
     The EPA Project Officer can be contacted at:
             Municipal Environmental Research Laboratory
             U.S. Environmental Protection Agency
             Cincinnati, OH 45268
    U S GOVERNMENT PRINTING OFFICE; 1984 — 559-016/7850
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
                                                                                          DEC 11-31  ;  :;:,;,,,Tf PERMIT NO. G-35 j-
Official Business
Penalty for Private Use $300
                                                     "'•-,. OK >c,,.
                                           AGENCY
          CHICAGO  IL  60604

-------