United States
Environmental Protection
Agency
Hazardous Waste Engineering
Research Laboratory
Cincinnati OH 45268
 Research and Development
EPA-600/S2-84-175  Dec. 1984
Project  Summary
Capital  and O&M  Cost
Relationships  for Hazardous
Waste  Incineration
Robert McCormick
  The objective of this study was to
develop relationships between capital
and  operation/maintenance (O&M)
costs for hazardous waste incineration
and the various waste-specific, design-
specific, and operational factors that
affect these costs. These cost relation-
ships have been designed so that total
capital investment, annual O&M cost.
and unit (dollars per Ib, etc.) disposal
cost estimates can be calculated for a
variety of waste compositions, different
incineration system designs and con-
figurations, and a wide range of system
operating conditions and performance
requirements.  Sequential elements of
the estimation procedure are: (1) input
data specifications, (2) design assump-
tions and engineering calculations, (3)
capital cost estimation, (4) annual O&M
cost estimation, and (5) unit disposal
cost calculation.

  The input data specifications include
physical/chemical  waste  characteris-
tics and throughput rates, generic in-
cinerator design type,  capacity, and
operating temperature, particulate and
acid gas removal requirements, energy
recovery utilization, and operating sched-
ule. When these data are specified by
the user, conceptual design, material
balance, energy balance, capital cost,
and O&M cost calculations are per-
formed in sequential fashion. The pro-
jected accuracy of this cost estimation
procedure is ±30 to 40 percent.

  This Project Summary was developed
by EPA's Hazardous Waste Engineering
Research Laboratory, Cincinnati. OH.
to announce key findings of the research
project that is fully documented in a
separate report of the same title (see
Project Report ordering information at
back).

Introduction
  The U.S. Environmental Protection
Agency (EPA) is currently performing a
Regulatory Impact Analysis (RIA) of the
RCRA performance standards for hazard-
ous waste incineration facilities. One of
the key elements of this RIA effort is the
development of representative cost data
for hazardous waste incineration, includ-
ing:

• Capital costs for  new facilities  de-
  signed  in accordance with  the  Re-
  source Conservation and Recovery Act
  (RCRA) requirements.
• Operation and  maintenance (O&M)
  costs for these facilities.
• Retrofit costs for existing facilities to
  comply with RCRA standards.

  This cost information is also needed by
the Incineration Research Branch (IRB) of
the Industrial Environmental Research
Laboratory, U.S. EPA, to complement
technical/environmental evaluations of
hazardous waste incineration  technol-
ogies, and to aid  in identifying  future
research priorities.
  The report summarized herein focuses
on capital and O&M costs of incineration.
Retrofit costs are addressed in a compan-
ion report entitled, "Retrofit Cost Relation-
ships for Hazardous Waste Incineration."
  The objective of the study was to
develop relationships between capital

-------
and  O&M  costs  for hazardous waste
incineration and the various waste-
specific, design-specific, and operational
factors that affect  these  costs. These
costs relationships were to be designed
so that total capital investment, annual
O&M cost,  and unit ($/lb., etc.) disposal
cost  estimates could be calculated for a
variety of waste compositions, different
incineration system designs, and config-
urations, and  a wide range  of system
operating conditions and performance
requirements. This degree of parametric
cost estimating capability was considered
essential for the RIA effort and for future
IRB utilization.
  Based on these objectives, a capital and
O&M cost  estimation  model has been
developed  in  computer-ready format.
Sequential elements of the model are: (1)
input data  specifications, (2) design as-
sumptions and engineering calculations,
(3) capital  cost estimation,  (4) annual
O&M cost estimation, and(5) unit disposal
cost  calculation.
  Input requirements for the model  in-
clude basic physical/chemical properties
of the wastes in question, plus a limited
number of  facility design and operating
specifications. Based on these input data
and  numerous technical assumptions in
line with current industry practice, a wide
array of engineering calculations are
performed to specify and  design  the
required hardware for the facility and to
estimate the rates at which fuel, power,
and  other  chemicals/utilities are con-
sumed.
  Based on the preliminary design speci-
fications, equipment costs are estimated
using a series of  empirical relationships
between cost and capacity, materials of
construction, or  other  relevant design
features. Estimated costs for equipment
installation  and contingencies are then
combined with the equipment  costs to
determine total capital investment.
  Variable  costs for fuel, power, etc. are
estimated  from the consumption rate
calculations previously mentioned and a
series  of regionalized  unit  cost data.
Semi-variable costs such as labor  and
maintenance,  fixed charges to capital,
and energy recovery credits (optional) are
also estimated to determine  the net
annual O&M cost. This cost is then
divided by the annual waste throughput
to arrive at the final  unit disposal cost
estimate.
  More details of the input requirements,
intermediary calculations, and outputs
are  described below.  Limitations  of the
model are also discussed
Methodology
  For input data specification purposes,
wastes are divided  into five categories:
combustible organic liquids, non-combus-
tible liquids (without support fuel), pump-
able slurries or sludges, non-pumpable
sludges or bulk solids, and containerized
solids. The following data are required for
each waste stream  or mixture of wastes
included in each of these categories: (1)
normal  or average feed rate, (2) gross
heating value,  (3) fractional  content of
carbon, hydrogen, oxygen, nitrogen, mois-
ture, ash, and chlorine, and (4) presence
of toxic, heavy metals or alkali metals in
the ash. Certain facility design and oper-
ating conditions must also be specified to
use  the model, including (1) owner/op-
erator designation, (2) generic incinerator
design (liquid injection, rotary  kiln, or
multiple chamber/ hearth type), (3) nom-
inal primary and secondary chamber
incineration temperatures, (4) minimum
excess air requirements,  (5) frequency
and duration of incinerator startups, (6)
waste heat boiler utilization and  generic
design (firetube or watertube), (7) partic-
ulate size distribution and control require-
ments, (8) acid gas (HCI) control require-
ments, (9) regular operating schedule and
annual facility utilization, and(10) region-
al location and climatical considerations.
  These input data are self-explanatory
with the exception of "owner/operator
designation."Three distinct owner/oper-
ator scenarios are  provided so that the
economic impacts of regulation  can be
evaluated across different segments of
the  hazardous  waste incineration user
industry. These three scenarios  are: (A)
commercial, institutional, or small indus-
trial firms operating <10 million Btu/hr
incinerators, (B)  large  industrial firms
operating 10 to 50 million Btu/hr facilities
for captive waste disposal, and (C) com-
mercial waste disposal, semi-private or
corporate central facilities in the 50 to
100 million Btu/hr range.
   Certain waste characteristics  and de-
sign alternatives that can impact costs
are not addressed in the study. First of all,
wastes containing significant concentra-
tions of sulfur, phosphorus, or halogens
other than chlorine are not provided for.
This limitation is imposed because few of
these types of wastes are "listed" for
RCRA purposes, and because assessment
of air pollution control costs would be
beyond the scope  of the study  if such
wastes  were  considered. Similarly, air
pollution control device (APCD) selection
is limited to venturi scrubbers for partic-
ulate contnl  and packed bed absorbers
for acid gas (HCI) removal. These limita-
tions are realistic because venture and
packed bed scrubbers are the choice of
most designers.*
  Before the input data can be used to
estimate capital and O&M costs, a num-
ber of design assumptions and engineer-
ing calculations are needed for conceptual
design  purposes and to  estimate raw
material and utility consumption rates.
The design assumptions incorporated in
the model are too numerous to address in
their entirety in this summary; however,
the major underlying assumptions are as
follows:

  1.  Either liquid injection, rotary kiln, or
     multiple chamber hearth incinerat-
     ors are  used.  Unique, exotic, or
     hybrid designs are not considered.
  2.  Bottom ash from kiln and hearth
     incinerators is  disposed off-site at
     sanitary or secure landfills, depend-
     ing on ash toxicity.
  3.  Incinerators are equipped with suf-
     ficient fuel firing capacity to reach
     the designated operating temper-
     ature prior to waste injection.
  4.  Firetube and watertube waste heat
     boilers are the only energy recovery
     devices considered. Where utilized,
     waste heat boilers are located im-
      mediately  downstream  from the
      incinerator, recovering enough heat
     to reduce combustion gas temper-
     atures to 550°F.
  5.  Waste heat boilers are followed by
      small in-line quenches to reduce
      gas temperatures to adiabatic satur-
      ation upstream from the APCDs. If
      waste  heat boilers  are  not em-
      ployed, larger quenches are used to
      achieve the same temperature re-
      duction.
  6.  Three air pollution control system
      configurations  are  considered: (a)
      venturi scrubber for particulate
      control, (b) packed bed absorber for
      HCI removal, and(c) venturi scrubb-
      er followed by HCI absorber. It is
      assumed that at least one air pollu-
      tion control device is needed. A flow
      diagram for a complete scrubbing
      and flue gas handling system is
      presented in Figure 1.
  7.   All scrubbing systems have a com-
      mon sump that receives the quench,
      venturi scrubber, and absorber ef-
 *An appendix to the report covering ionizing wet
 scrubbers is currently being written and will be
 published separately

-------
      fluents. At  least 5 percent of the
      combined effluent is discharged to
      limit solids buildup, and the remain-
      der is recycled.
  8.   Caustic soda  solution is  used in
      stoichiometric quantities  for  HCI
      scrubbing and neutralization.
  9.   All systems are assumed to be
      balanced draft, with combustion air
      blowers for the incinerators and ID
      fans downstream from the APCDs.
 10.   Reasonable on-site storage capac-
      ities and/or housing structures are
      provided for liquid and solid wastes.
 11.   The overall system  is adequately
      designed in terms of safety inter-
      locks and materials of construction
      to prevent catastrophic failure.

  These design assumptions are typical
 of good industry practice. Therefore, they
 provide a reasonable basis for cost esti-
 mation for the industry as a whole, which
 is the goal  of the RIA. However, these
 assumptions do not reflect current  prac-
 tice for all  facilities, so cost estimates
 derived from the  model  may  not be
 representative for specific facilities.
  Based on these  design assumptions
 and the input data previously described,
 engineering calculations are performed
 for conceptual design and raw material/
 utility consumption rate estimations.
 These calculations  include: (1) land and
 associated  site development require-
 ments; (2) storage tank capacities, agita-
 tion, nitrogen blanketing,  and heating
 requirements; (3) pump capacities and
 power requirements; (4) piping require-
 ments; (5)  bulk  solid waste handling
 equipment sizing and operational require-
 ments (carts, transport vehicles, convey-
 ors, and feeders); (6) atomizing air  com-
 pressor capacity and power requirements;
 (7) square  footage for buildings  and
 structures; (8) incinerator operating re-
 quirements  in terms of low-fire, supple-
 mental heating, and startup fuel; combus-
 tion air blower capacity and power; ash
 handling water and power; and exit gas
 characteristics;  (9)  waste heat boiler
 steam generation, fuel savings,  and exit
 gas temperature;  (10) quench water
 requirements, booster pump capacity and
 power requirements, and saturated exit
 gas composition;  (11) scrubbing system
 water requirements,  chemical  require-
 ments, pump power requirements, and
 blowdown rate; and (12) induction  draft
 fan capacity and power requirements.
  Freight-on-board  costs for front-end
storage and  handling equipment, incin-
erator subsystems and auxiliary equip-
 Inlet
 Gas
                               Packed
                               Bed
                               Absorber
                              Venturi
                              Scrubber
                                                                       To
                                                                  Atmosphere
                                                         ID Fan

                                                    Caustic Solution
                                                   Makeup Water
                           Blowdown
                           to Disposal
Figure 1.    Generalized flow diagram for quench/scrubber system.
ment, packaged waste heat boilers and
necessary trim, and scrubbing/flue gas
handling equipment are based on vendor
estimates. Cost versus capacity curves
are presented for each equipment item or
subsystem,  based on the design and
material-of-construction  specifications
previously determined. These cost versus
capacity curves are used  in conjunction
with the actual conceptual design calcu-
lations to estimate purchased equipment
costs for the facility in question
  Costs for equipment delivery, installa-
tion  materials and labor, engineering
design, permitting, construction expenses
and fee, and contingency are then est-
imated as percentages of the purchased
equipment cost. These factored costs,
combined with the purchased equipment
costs, constitute the  depreciable fixed
capital cost estimate for the facility.
  Total capital investment estimates in-
clude the depreciable fixed capital invest-
ment, plus allowances for land purchase,
startup, trial  burns, and working capital.
Costs for land, trial burns, and working
capital are estimated directly, based on
facility design and operating character-
istics. Startup costs are estimated as a
percentage of the direct costs for equip-
ment purchase and installation, plus
indirect and contingency costs.
  Annual O&M costs and credits  are
divided into four categories for calculation
purposes: (1) variable costs, such as fuel,
power, water, caustic soda solution for
HCI scrubbing, liquid nitrogen for tank
blanketing and residue disposal (ash and
scrubber blowdown); (2)  semi-variable
costs, such as labor, maintenance, and
waste analyses; (3) fixed costs, such as
depreciation,  insurance, and taxes; and
(4) energy recovery credits for waste heat
boiler utilization (optional). Annual vari-
able cost estimates are based on the raw
material-utility consumption rate calcula-
tions previously described, the assumed
annual  utilization percentage  for  the
facility, and regionalized unit cost data. In
this study, unit cost data are given for the
Chicago, Houston,  Los  Angeles, and
northern New Jersey metropolitan areas.
  Operating  labor cost  estimates  are
based on assumed staffing requirements
for the various categories and capacities
of hazardous waste incineration facilities,
and regionalized wage/salary rates. Six
separate staffing scenarios are provided,
with differentiation based on owner/op-
erator designation (A, B, or C) and waste
mix (liquids only or liquid and solids).
Maintenance costs are estimated as a
percentage of the depreciable fixed capita I
investment, as are the costs for deprecia-

-------
  tion, insurance, and taxes. Energy recov-
  ery credit estimates are based  on the
  calculated fuel conservation rate, annual
  utilization percentage,  and regionalized
  costs for fuel.
    The  net annual O&M costs is deter-
  mined by summing the variable, semi-
  variable, and fixed operating costs and
  subtracting any energy recovery credit.
  Dividing this net quantity by the estimated
  annual waste throughput yields the unit
  disposal cost estimate, which is the
  desired output.

  Applicability and Limitations
    The  accuracy  requirements stated at
  the  outset of  this study were ± 70
  percent. For most facilities, the budget-
  ary pricing procedures used in this study
  should provide better accuracy, i.e., ± 30
  to 40 percent. This degree of accuracy is
  considered acceptable for purposes of the
  RIA and for first-cut comparisons of the
  costs for incineration versus other waste
  disposal alternatives. However, caution
  should be exercised  if the model is
  utilized for site-specific cost  estimating
  purposes.
         R. McCormick is with the Acurex Corporation, Mountain View, CA 94039.
         B. L. Blaney is the EPA Project Officer (see below).
         The complete report, entitled "Capital and O&M Cost Relationships for Hazardous
            Waste Incineration."  (Order No. PB  85-121  119;  Cost: $19.00. subject to
            change) will be available only from:
                 National Technical Information Service
                 5285 Port Royal Road
                 Springfield, VA  22161
                 Telephone: 703-487-4650
         The EPA Project Officer  can be contacted at:
                 Hazardous Waste Engineering Research Laboratory
                 U.S. Environmental Protection Agency
                 Cincinnati, OH 45268
                                                  U S GOVERNMENT PRINTING OFFICE. 569-016/7868
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
     BULK RATE
POSTAGE & FEES PAI
        EPA
   PERMIT No. G-35
Official Business
Penalty for Private Use $300

-------