United States
 Environmental Protection
 Agency
Air and Energy Engineering
Research Laboratory
Research Triangle Park NC 27711
 Research and Development
EPA/600/S7-87/016  Sept. 1987
 Project  Summary
 Evaluation  of  Boiler Design
 Modifications  for  Enhanced
 LIMB  Application
D. E. Ryan and R. Smolensk^
  Under EPA sponsorship, a study was
conducted to evaluate the technical
and  economic impact of designing
wait-fired pulverized-coal units  to
incorporate dry sorbent sulfur control
technology (LIMB). Conventional (non-
Li MB) units were set up at three sizes
(200. 400, and 600 MW) to burn a low
sulfur (0.48%) subbituminous fuel.
LIMB units were then set up to achieve
70% SOX removal using  dry sorbent
injection.  Standard  cost estimating
procedures were used to evaluate the
cost differentials between the conven-
tional and LIMB units. These cost data
were used to establish removal cost
trends as  a function of  calcium-to-
sulfur (Ca/S) mole ratios and boiler
size. The study concluded that it is
technically  feasible to achieve 70%
sulfur removal in a unit burning low
sulfur fuel using  only  dry  sorbent
injection. The results also showed that
Ca/S ratios between 2.8 and 3.5 can
be accommodated  without  radical
alterations  to state-of-the-art  boiler
configurations.
  This Project Summary  was  devel-
oped by EPA's Air and Energy Engi-
neering Research Laboratory. Research
Triangle  Park. NC. to announce key
findings  of the research project that is
fully documented in a separate report
of the same title (see Project Report
ordering information at back).
Introduction and Summary
  The Environmental Protection Agency
is engaged  in a research  program  to
develop improved control technologies
for the emission of  sulfur and  nitrogen
oxides (SOX and NOX) from the combus-
tion of fossil fuels. These emissions are
important due to their magnitude and
apparent link to acid rain. The cause and
potential solutions of  the acid rain
problem are still being debated; however,
control of SO, and NOxfrom power plants
is a major element in all proposed control
strategies.
  The choice of control  techniques for
acid  rain will  likely include a  mix  of
technologies to achieve  the mandated
pollutant reduction  at a cost that will
minimize the impact on the nation and
on specific geographical areas. Commer-
cially available options include: coal
switching, coal cleaning, and various
types of  flue gas desulfurizatipn (FGD)
systems. In addition, analysis indicates
that  low  capital cost technology for
retrofit to existing boilers would provide
further flexibility in a control strategy
even at moderate (e.g., 50%) S02 removal
rates. One such technology is LIMB
(acronym for Limestone Injection  Multi-
stage Burner), which  is  based  qn the
injection of dry sorbents  into the boiler
for direct capture of SOa from the
combustion gases. LIMB  combines sor-
bent injection for SO« control with the
use of low-NOx burners.
  The EPA LIMB program was initiated
in  1981, although work in related areas
had been previously conducted by the
EPA and others. The  LIMB program is
structured to provide an  understanding
of  the controlling factors in the LIMB
process and to establish  a basis for the
private sector commercialization of the
technology.
  This engineering study was performed
for the E PA as  part  of the Agency's
ongoing  effort to investigate all the
potential uses of sorbent injection for the
control of SOX emissions.

-------
  This  investigation was performed to
determine the technical and cost differ-
entials within  the scope of the study
between a conventional utility boiler and
a utility boiler designed to incorporate the
LIMB process. Comparisons were made
using nominal 200, 400, and 600 MWe
units. The scope of the study considers
only the boiler shell; auxiliary equipment
(e.g., fans, precipitators, flue gas desul-
furization equipment) is not addressed.
  Both the conventional and LIMB units
were designed to fire a low sulfur (0.48%
by weight), subbituminous western coal.
The overall procedure was: (1) a conven-
tional boiler was designed for each of the
three plant sizes to be studied; (2) a LIMB
boiler was designed which gave the same
output as its conventional sister unit (the
LIMB  unit  included the  alterations
required to allow for 70% of the sulfur
introduced into  the boiler via the fuel to
be removed by sorbent injection without
additional downstream  gas processing);
and  (3) a  cost analysis was performed
to determine  the  cost differentials
between the LIMB and the conventional
units.
Conclusions
  The conceptual design work performed
to date demonstrates that it is technically
feasible to design  a LIMB unit burning
low-sulfur coal to accommodate Ca/S
ratios  between 2.8 and  3.5 without
radically altering state-of-the-art boiler
configurations. In addition, it was deter-
mined that, based on an economic
analysis utilizing "LIMBCOST" (an EPA
computer program), the limiting factors
when  optimizing with respect to the
Ca/S ratio are thermodynamic (i.e., the
lower  limit  on the Ca/S ratio was set
by  establishing the  largest  possible
residence time cavity and still have a high
enough gas temperature  entering the
convection pass to complete the required
heat transfer to surfaces downstream of
the cavity).
  The conceptual design work also
indicated  that of the two principal LIMB
design criteria (sorbent residence time to
980°C and quench  rate to 870°C),
residence time dominated unit configu-
ration  considerations. When the design
residence time is  achieved, acceptable
quench rates typically follow.

Recommendations
  The  work performed to date suggests
a need for continuing validation of some
of the cost  assumptions  used in this
study,  to reflect  actual experience  as
LIMB technology matures. The optimiza-
tion work performed as part of this study
used an AEERL in-house cost estimating
program called "LIMBCOST." This pro-
gram includes a number  of  algorithms
and  parameter  values  for:  (1) sorbent
injection system (materials  handling)
costs; (2) base unit capital costs; (3) fuel
costs; (4) sorbent costs; (5) waste dispo-
sal costs; (6) costs of other consumables;
and (7) maintenance and operating costs.
Verifying these  cost assumptions was
beyond the scope of this study. Therefore,
these study results can be  considered
initial estimates. In addition, no compar-
ison was made to determine the trade-
off  between LIMB and backend sulfur
removal.  Any true  optimization would
have to consider this issue.
  From a technical standpoint, further
investigations should consider the injec-
tion process and  verification of the
capture data provided by the EPA. These
data are expected to be generated during
the  EPA's demonstration  programs.
However, for purposes of this study, it
was assumed that: (1) the nozzles could
indeed get the sorbent  into the flue gas
stream; (2)  complete mixing was subse-
quently achieved after injection; and (3)
the expected capture data provided by the
EPA are valid.
  Planned  demonstration testing  will
provide  the data  to  validate  these
assumptions and (if necessary) appro-
priately modify the results of this study.


Objectives and Approach
  The work done in developing this report
focused on  three primary objectives:

1.  Demonstrating the  feasibility of
    designing boilers at 200, 400, and
    600 MW to  be  compatible with the
    LIMB process.

2.  Evaluating  the cost differentials
    between these LIMB  compatible
    units and boilers designed without
    the LIMB process incorporated (i.e.,
    conventional units).

3.  Establishing cost trends for these
    units as a function of both megawatt
    rating and Ca/S ratio.

  The  five-step  approach used during
this study consisted of:

1.  Establishing design criteria for the
    boilers. This included defining steam
    conditions,  fuel type,  and the  LIMB
    parameters to be used.
2.  Designing conventional boilers at (
    200, 400, and 600 MW which used
    all of the design parameters estab-
    lished in step  1,  except the LIMB
    design parameters.

3.  Designing  units with the same
    megawatt ratings used in step two,
    but this  time  incorporating LIMB
    parameters into the design.

4.  Using  standard  cost estimating
    procedures  to establish cost differ-
    entials  between the  conventional
    units and their sister LIMB units.

5.  Using these cost differentials to
    establish and evaluate cost trends as
    a function of megawatt rating and
    design Ca/S ratio.

-------
     D. E. Ryan and R. Smolensk! are with Babcock & Wilcox Co., Barberton,  OH
       44203.
     David G. Lachapelle is the EPA Project Officer (see below).
     The complete report entitled "Evaluation of Boiler Design Modifications for
       Enhanced LIMB Application." (Order No. PB 87-199 634/AS; Cost: $13.95,
       subject to change)
     will be available only from:
             National Technical Information Service
             5285 Port Royal Road
             Springfield, VA 22161
             Telephone:  703-487-4650
     The EPA Project Officer can be contacted at:
             Air and Energy Engineering Research Laboratory
             U.S. Environmental Protection Agency
             Research Triangle Park, NC 27711
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Official Business
Penalty for Private Use $300

EPA/600/S7-87/016


-------