United States
Environmental Protection
Agency
Air and Energy
Engineering Research Laboratory
Research Triangle Park NC 27711
Research and Development
 EPA/600/S7-88/020  Jan. 1989
Project Summary
Evaluations  of  Electrostatic
Precipitator  Performance at
Edgewater Unit 4  LIMB
Demonstration
John P. Gooch and James L. DuBard
  The  EPA  is  sponsoring  a
demonstration  of   Limestone
Injection Multistage  Burners (LIMB)
technology at  Ohio  Edison's
Edgewater  Station  Unit 4, which
employs a wall-fired boiler of 105
MW electric generating capacity. The
boiler  is  equipped  with  large
electrostatic precipitator (nominal
SCA 600 ft2/1000 acfm* at  528,000
acfm) of modern design that  was
retrofitted  in  1982.  This report
describes extensive laboratory- and
pilot-scale studies,  as well  as
preliminary on-site tests at Unit 4.
  This Project Summary was devel-
oped by EPA's  Air  and  Energy
Engineering Research Laboratory,
Research  Triangle  Park, NC,   to
announce  key  findings  of  the
research  project  that is  fully
documented in  a  separate report of
the same title  (see Project Report
ordering information at  back).

Introduction
  Coal-fired  utility  boilers  account for
approximately 70% of the SOX emissions
and 20% to 25% of the NOX emissions in
the U.S. These emissions are believed to
be precursors of acid  precipitation. The
coal-fired electric generating capacity
east of  the   Mississippi  River
(approximately 180,000 MW) accounts
for 16 million tons  of SOX and 4  to 5
" Readers more familiar with metric units may use
 the conversion factors listed near the end of this
 summary
 million tons of NOX discharged into the
 atmosphere annually. Only about 10% of
 the coal-fired utility boilers in the
 eastern U.S. are subject to SOX and NOX
 emission controls under the New Source
 Performance  Standards (NSPS). A
 significant reduction of SOX  and NOX
 emissions may require retrofit applica-
 tions of  emission control technology to
 the existing boiler population.
    LIMB technology is a retrofit SOX and
 NOX emission control technology  which
 may be applicable to  a significant
 number of  existing wall-fired and
 tangentially fired  boilers. LIMB  tech-
 nology involves injecting a  calcium-
 based sorbent directly into a furnace that
 is equipped  with  Iow-N0x  burners.
 Since  1986,  the development of  LIMB
 technology has focused on  furnace
 injection of  hydrated lime,  at about
 2200°F,  with  subsequent humidification
 of the combustion gas downstream  of the
 heat exchangers. The particulate matter
 suspended in the combustion gas stream
 (fly ash  and partially sulfated  sorbent)
 must  be collected  in an  existing
 electrostatic precipitator (ESP).
  Candidates among existing boilers  for
 a retrofit application of LIMB technology
 are mostly equipped with small  ESPs that
 were designed to  collect low-resistivity
 fly  ash  from  high-sulfur  coal  com-
 bustion.  These ESPs typically  have
 specific collection areas (SCA) less than
 300 ft2/1000 acfm. A retrofit application of
 LIMB technology will result in changes in
 the suspended particulate matter that

-------
present  a difficult  challenge to these
ESPs.
  The  EPA is  sponsoring  a  demon-
stration  of LIMB technology  at  Ohio
Edison's Edgewater Station Unit 4, which
employs  a wall-fired  boiler  of  105  MW
electric generating capacity. This partic-
ular unit has a large ESP (nominal SCA
600 ft2/1000 acfm  at 528,000  acfm) of
modern  design  that  was retrofitted in
1982.
  LIMB  tests, with furnace  injection of
pulverized limestone,  began  during 1984
in a 1 million Btu/hr pilot coal combustor.
The  early  tests focussed  on  calcium
utilization  and SOX removal  issues, but
some data were also obtained on the
changes in dust resistivity, mass loading,
and particle size distribution  that impact
ESP performance.  During  1985, the
emphasis  in LIMB  development shifted
to  furnace injection  of hydrated  lime.
Measurements of the changes  in dust
properties caused by  LIMB were used to
perform  preliminary  estimates of the
impact of  LIMB  on the Edgewater Unit 4
ESP, using the mathematical  model. The
data from the pilot  coal combustor were
also used  to estimate  the impact of LIMB
on small ESPs with SCAs in the range of
200  to 300 ft2/iooO  acfm.  The experi-
mental  data  and  the  results  of
mathematical  modeling  have  been
reported.
  The master plan for a demonstration of
LIMB technology included   preliminary
tests of the impact of LIMB on the  EPA
mobile pilot ESP.  The pilot ESP  was
refurbished and installed  on  a  com-
bustion  gas sidestream  from a heating
plant boiler in Oromocto, New Brunswick,
for the purpose of evaluating operating
problems  and  performance upgrading
methods prior to the  Edgewater demon-
stration  project. However,  satisfactory
boiler operation with  LIMB could not be
achieved  in  the allotted  time period
before the pilot ESP  was moved to the
Edgewater demonstration site. There-
fore, the  pilot coal combustor was the
only significant  source of data  on  LIMB
dust properties prior to  the  preliminary
LIMB trials at Edgewater Unit  4 during
September, 1987.  Following  the prelim-
inary LIMB trials, which were conducted
without humidification of the  combustion
gas stream, extensive tests of the impact
of humidification on  ESP performance
were conducted during  January  and
February  1988.  Results of  these  tests
have been reported.
Summary of Results and
Conclusions
  This  section summarizes the principal
findings related to the impact of LIMB on
ESP  performance,  both  from  the
preliminary LIMB trials at Edgewater Unit
4 and  from  tests  in the  pilot coal
combustion facility with a laboratory ESP
installed on the combustion gas stream.
The  principal  findings  cover  dust
resistivity,  electrical  and  mechanical
operation,  dust loading and particle  size
distribution, electrode dust accumulation
and cleaning, and mass emissions  and
opacity.

Dust Resistivity
Edgewater Unit 4
• During baseline  operation, the dust
  resistivity measured  in  situ at the ESP
  inlet  averaged 3x1010  ohm-cm  at
  350 °F.
• During operation with  LIMB, the dust
  resistivity was too high  to be measured
  accurately with the point-plane in situ
  resistivity probe. The measured values
  were in the range of 1x1012 to 5x1012
  ohm-cm, at 300° to 360°F, but the
  actual values  are  believed to have
  ranged as high as 1x1014 ohm-cm.

Pilot Facility
• Laboratory measurements of LIMB
  dust  resistivity  indicated values as high
  as 1x1014  ohm-cm  at the  operating
  temperatures experienced  in  the
  Edgewater Unit 4 ESP.
• Cold-side  combustion  gas  stream
  humidification was  found  to  be  an
  effective means  of  moderating LIMB
  dust  resistivity. The resistivity  values
  (measured  both in situ and  in the
  laboratory) dropped over two orders of
  magnitude  at temperatures   of
  approximately  220°F,  representing
  about  a  100°F  approach  to  the
  adiabatic saturation temperature.
• LIMB dust resistivity is expected to be
  below 1x1012 ohm-cm within a 100"F
  approach to saturation, and  below
  1x1010  ohm-cm  within  a  50°F ap-
  proach to saturation.

Electrical Operation
Edgewater Unit 4
• During  baseline  operation,  there  was
  no evidence  in the measured trans-
  former-rectifier secondary  voltage-
  current  curves of any  electrical  or
  mechanical malfunction.              J

• During operation with LIMB, there was
  severe electrical malfunction caused by
  the  high resistivity of the precipi-tated
  LIMB dust.  Electrical  degradation
  began  in  the  ESP  inlet  field and
  progressed to the fifth field within three
  to four hours of operation with  LIMB.
  Electrical degradation  resulted in  the
  immediate onset of back corona at the
  threshold voltage  for primary corona.
  There was no working voltage  range
  which   would   permit   useful
  electrification of the ESP.

Pilot Facility

• Furnace sorbent injection  caused
  severe  electrical  degradation  of  the
  laboratory  ESP. Humidification within a
  100°F  approach  to  saturation was
  necessary to  permit useful electrifica-
  tion of the  ESP.

• At a fixed  operating voltage applied to
  the   laboratory ESP,  the  operating
  current  increased  with  increasing
  humidification and closer approach to
  saturation.
Mechanical Operation
Edgewater Unit 4

• During an  internal inspection  of the
  ESP after furnace sorbent  injection,
  there  was no evidence of any  serious
  electrode  misalignments or  electrode
  cleaning difficulties. The ESP appeared
  to  be in good  mechanical  operating
  condition.  However,  problems  were
  encountered  with  the  ash removal
  system during the LIMB tests.


Dust Loading and Particle Size
Distribution
Edgewater Unit 4
• LIMB  had an adverse  impact  on the
  mass  loading  and  particle  size
  distribution of dust entering the  ESP.
  The overall mass loading increased by
  about a factor of two.

• During operation with LIMB, the  mass
  loading increased by  about a factor ol
  10 in the particle size  range  from 0.5 tc
  1.0 iim. This is the particle size range
  where ESPs are least efficient and the
  particulate  emissions contribute  mosf
  strongly to plume opacity.

-------
pilot Facility
-> Furnace injection of hydrated  lime
  resulted in changes in the suspended
  particulate  matter that were consistent
  with data from the preliminary LIMB
  trials at Edgewater Unit 4. At a typical
  Ca/S stoichiometry of  about 2,  the
  overall  mass loading  increased by  a
  factor of 2 to 3, and the fine particulate
  mass loading increased about tenfold.

Electrode Dust Accumulation
and Cleaning
Pilot Facility
• There  was  a rapid accumulation of
  dust deposits on the  laboratory ESP
  electrodes  during furnace  sorbent
  injection and combustion gas stream
  humidification.  Dust deposits  on  the
  high voltage discharge electrodes built
  up very rapidly.
• There  was no difficulty in cleaning the
  ESP  electrodes  by   mechanical
  rapping, even at  a close approach to
  adiabatic saturation.   LIMB dust was
  removed more  easily  than the fly ash
  from pulverized coal combustion.


Mass Emissions and Opacity
Edgewater Unit 4
• During  baseline  operation,  the ESP
  operated with a  clear stack. Opacity
  readings were  in the  range of 1% to
  2%.
• During  operation with LIMB, opacity
  rose rapidly to the   20%  limit  after
  electrical degradation  began in the fifth
  ESP field. Steady  state operation  of
  the  ESP with LIMB was not achieved
  during the preliminary  trials. Furnace
  sorbent  injection had to be  stopped
  after 3 to 4 hours to  avoid exceeding
  the opacity limit.
• Mathematical modeling of the ESP
  performance  during  cold-side
  humidification of the  combustion gas
  stream indicated that  the performance
  will  be satisfactory within  a   100°F
  approach to  saturation because of the
  large size of the ESP.

Pilot Facility
• There  was  no   catastrophic
  spontaneous  reentrainment from the
  laboratory   ESP  electrodes   of
  humidified   LIMB   dust,   as
  humidification was  increased  all the
  way to the point of adiabatic saturation.
• Spontaneous reentrainment of pre-
  cipitated LIMB dust occurred in large
  agglomerates which did not affect the
  measured  outlet gas opacity.  In  an
  operating ESP,  these agglom-erates
  would be quickly recollected.
• The  outlet gas opacity decreased
  (concurrently with  the  increasing
  operating  current)  with increasing
  humidification and a closer approach to
  saturation.
• The  outlet gas  opacity  decreased by
  several  percentage points  after the
  laboratory  ESP   electrodes  were
  rapped.  This performance improve-
  ment is  a result  of the improved
  electrical operating  condition obtained
  with cleaner electrodes.
Future Work
  A  long term  demonstration  of  LIMB
technology with humidification is planned
at Edgewater during the last part of CY
1988. The test plan for the demonstration
includes evaluations of the  performance
of the full scale ESP with humidification.
Pilot-scale studies are  also  planned with
the  EPA pilot  ESP   system. These
experiments  will focus on  performance
enhancements which  may  be  achieved
with  electrode  modifications  and
humidification on ESPs with  smaller SCA
values that  are more  typical of  the
potential LIMB  retrofit  candidate
population than the large ESP installed at
Edgewater.

Metric Equivalents
  Readers more familiar with metric units
may use the  following equivalents  to
convert from the nonmetric units used in
this summary:
   Nonmetric
  Multiplied
     by
Yields
metric
 Btu/hr
 cfm
 °F
 ft2
 ton
0.293
0.000472
5/9 (°F - 32)
0.0930
907.18
W
m3/s
°C
m2
kg

-------
John  P.  Gooch  and James L. DuBard are with  Southern Research  Institute,
  Birmingham, AL 35255.
The complete report entitled,  "Evaluations  of Electrostatic Precipitator  Perform-
  ance at Edgewater Unit 4 LIMB Demonstration," (Order No. PB 89-109 1771 AS;
  Cost $15.95, cost subject to change)will be available only from:
    National Technical Information Service
    5285 Port Royal Road
    Springfield, VA 22161
    Telephone:  703-487-4650
The EPA Project Officer can be contacted at:
    Air and Energy Engineering Research Laboratory
    U.S. Environmental Protection Agency
    Research Triangle Park, NC 27711
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Official Business
Penalty for Private Use $300

EPA/600/S7-88/020
                                                0000329   PS
                                                                          It   60604

-------