United States
                   Environmental Protection
                   Agency
Hazardous Waste Engineering
Research Laboratory
Cincinnati OH 45268
                   Research and Development
EPA/600/S2-86/012 Aug. 1986
v°/EPA          Project  Summary

                    Guidance  Manual  on
                    Overtopping Control
                    Techniques  for  Hazardous
                    Waste Impoundments
                    Virginia Hodge, Nick DeSalvo, Shahid Mahmud,
                    Joshua Margolis, Mark Evans, and John Meade
                     The overall objective of this project
                    was to provide guidance for selecting
                    cost-effective interim management
                    methods to control overtopping of im-
                    poundments, pits, ponds, or lagoons at
                    uncontrolled hazardous waste sites until
                    final remedial actions could be initiated.
                     Hazardous waste impoundments are
                    subject to overtopping through the col-
                    lection of  rainwater, run-on, or other
                    uncontrolled inflow. Lagoon overflows
                    are generally the result of insufficient
                    capacity due to either  insufficient free-
                    board (high level of lagoon contents) or
                    structural problems that reduce the ef-
                    fective capacity.  No matter what the
                    cause, lagoon overflows can pose sig-
                    nificant environmental and public health
                    risks through the contamination of soils,
                    ground water, and surface water,  as
                    well as the potential to spread the con-
                    tamination into areas not currently im-
                    pacted by the lagoon. Thus,  interim
                    measures may be necessary to control
                    lagoon overflows prior to identification
                    and selection of  a  final remedial
                    measure.
                     A manual has been prepared that
                    addresses both immediate control mea-
                    sures for emergencies  and longer term
                    measures  lasting  several  months  to
                    several years. The technology and cost
                    guidance presented is general in nature
                    because of the  variability of waste
                    lagoons and impoundments and the
                    unique conditions and considerations
                    that exist at each site.  Where possible,
                    factors affecting application, technology
                    selection,  and costs are identified, as
                    well as their likely impact on imple-
mentation and cost-effectiveness.
Design issues are briefly presented as
background to each option; however,
the manual is not intended to replace
the services of a qualified engineer in
designing site-specific systems.

  This Project Summary was developed
by EPA's Hazardous Waste Engineering
Research Laboratory, Cincinnati, OH, to
announce  key findings of the research
project mat Is fully documented In  a
separate report of  the same  title (see
Project Report ordering Information at
back).

Introduction
  The Comprehensive  Environmental
Response,  Compensation, and Liability
Act of 1980  (CERCLA) established  a
nationwide program for the cleanup of
uncontrolled hazardous waste sites.
Under this program, uncontrolled waste
sites  are identified and ranked, and re-
moval or remedial actions are identified,
studied, and implemented to eliminate or
reduce contamination  problems.  Interim
measures  must often be applied to pre-
vent  or reduce further environmental
contamination or threats to public health
until final actions can  be taken. The ob-
jective of this manual is to provide guid-
ance  on selecting cost-effective  interim
management methods to control over-
topping of impoundments, pits, ponds, or
lagoons at  uncontrolled hazardous waste
sites.
  Impoundments are subject to overtop-
ping through the collection of rainwater,
run-on, or other uncontrolled  inflow.

-------
Lagoon overflows are generally the result
of insufficient capacity due to either in-
sufficient freeboard (high level of lagoon
contents)  or structural problems  that
reduce the effective capacity. No matter
what the  cause,  lagoon overflows can
pose significant environmental and public
health risks through the contamination
of soils, ground water, and surface water,
as well as the potential to spread the
contamination into areas  not currently
impacted  by the  lagoon. Thus,  interim
measures may be necessary to  control
lagoon overflows prior to identification
and selection of a final response measure.
  Typical response actions to temporarily
control an overflow problem have included
reconstruction of the impoundment berm
to increase the  freeboard,  removal  of
liquid to lower the lagoon level, or both.
However,  other response methods such
as run-on diversions and covers are avail-
able, and may  often  be  more cost-
effective.
  Surface impoundments are highly vari-
able in size, structure, design, and pur-
pose.  Lagoons  have been used for
treatment, storage, or disposal of liquid,
solid, and semi-solid wastes from in-
dustrial, mining, oil and gas, and  agri-
cultural operations. They may be square,
rectangular, circular, or irregular in shape
and  may be unlined causing seepage to
underlying  soils  or  lined  to  prevent
seepage. Furthermore, lagoons may  be
built  aboveground or belowground via
natural or manmade depressions. Com-
monly, more than one surface impound-
ment may be found at a particular site
and  these multiple impoundments may
be  interconnected. These  features,  in
conjunction with site-specific character-
istics, can significantly affect the choice
of overtopping control  measures.

Manual Content
  The manual has been prepared to pro-
vide  technical  guidance to On-Scene
Coordinators (OSCs); Federal, state, and
local officials; private firms; and  field
personnel. It presents guidance for se-
lecting impoundment overtopping controls
as a temporary  solution pending  final
response  action. As such,  it addresses
both  immediate control measures for
emergencies and longer term measures
lasting several months to several years.
  The technology and cost guidance pre-
sented are general in  nature because of
the  variability  of waste  lagoons and
impoundments and the unique conditions
and considerations that exist at each site.
Where possible, factors affecting applica-
tion, technology  selection, and costs are
identified, as well as their likely impact
on  implementation and  cost-effective-
ness. Furthermore, while design issues
are briefly presented as  background to
each option, this manual is not intended
to replace the services  of a  qualified
design engineer in designing site-specific
systems.
  The  manual presents the  selection
process for overtopping control decision-
making and key factors affecting selection
decisions.  Details  are provided on
pumping and wastewater management
options; structural,  floating,  and  air-
supported cover systems; and surface
water diversion and berm reconstruction
technologies.

Selection of Overtopping Control
Measures
  The  selection of overtopping  control
measures proceeds in four steps:
1. Identification of the site problem; i.e.,
   specifically why the  lagoon overflows
   and  what site characteristics contri-
   bute to the overflow. At  the same
   time, the site situation is  assessed
   regarding the  need for immediate
   emergency measures to be applied
   prior to  identifying further interim
   control measures.
2. Preliminary selection of response op-
   tions that may be applicable based on
   the site problem. Thus, the first and
   second steps of the selection process
   are closely linked.
3. Evaluation  of the site characteristics
   affecting  the applicability of a par-
   ticular response. These characteristics
   are  defined  by the response tech-
   nologies  identified in Step 2 and are
   critical to  the  final evaluation  and
   selection of a response in Step 4.
4. Selection of a single response option
   or combination of options  that best
   controls  the  overflow problem  until
   the final remedial action is undertaken.
   This selection process is highly site-
   specific and requires consideration of
   site-related decision factors relative to
   the applicable technologies and their
   costs.

Characterization of Overtopping
Problem
  Waste  lagoon overtopping  may be
caused by insufficient lagoon capacity to
accommodate liquid inflows to the lagoon
or reduced lagoon capacity due to struc-
tural damage to the upper portion of the
lagoon  berm.  Insufficient capacity  may
be the result of  insufficient freeboard in
the  lagoon; precipitation; or run-on or
overflows/liquid feeds from a connecting
lagoon or other system. Structural damage
reducing the effective lagoon capacity
would include  erosion,  cracks, subsi-
dence, breach,  or other  penetration of
the lagoon berm in the area of the lagoon
level.
  In general, the nature of the overtopping
problem is highly site-specific and must
be evaluated in terms of the causal  and
contributing factors. For example, a crack
in the top  of  an  impoundment berm
reduces the capacity of the  lagoon  if it
penetrates from the interior berm wall to
the exterior. Where the crack or break is
sufficiently deep,  there may  be a single
event of lagoon spillage.  However, pre-
cipitation may quickly cause an overflow
to recur.
  Thus, the first step in selecting appro-
priate overtopping control measures is to
identify the problem, including both the
cause and the contributing factors. Once
the reasons for the lagoon overflow have
been defined, they can be used to identify
potential actions  to control the general
problem  until  a  final  site  action is
developed.
  If the lagoon is overflowing or overflow
is imminent, immediate control measures
are required. These control  measures
consist of constructing a temporary hold-
ing pond to contain the overflow or using
a temporary  pumping system to lower
the lagoon level. Once the urgency of the
problem has been reduced, appropriate
control measures for the interim period
prior to response should be identified and
implemented.  These measures  will
supplement or replace the stop-gap mea-
sures employed to control the immediate
problem by  identifying and  addressing
the contributing factors.

Identification of Applicable
Response Options
  Each problem has a choice of several
technologies that may be applied.  The
selection of a single response will depend
on site-specific factors. Where more than
one problem is involved,  the  response
options are expanded. Possible responses
for  overflow caused by precipitation in-
clude pumping, covering the lagoon, or
raising the berm height. If both precipita-
tion and run-on are causing lagoon over-
flow, the  response options expand to
include run-on  diversions. Furthermore,
the selected response may involve a single
response option  (e.g.,  pumping) or a
combination  of response options (e.g.,
construct diversion, pump, and cover).
  It should be noted that certain response
options  require  specific  associated

-------
responses. Pumping lagoons to remove
liquid and increase freeboard requires
management of the waste liquid. Similar-
ly, raised covers such as air-supported
and arch-supported structures  may re-
quire vapor or condensate control to pre-
vent the buildup of hazardous gases inside
the structures or release of liquids outside
the lagoon berm. The impact of these
requirements must be considered in the
selection process.

Evaluation and Selection of
Overtopping Controls
  A specific  control measure is selected
based  on  technology and  site-related
decision factors. This process involves a
simple cost-effectiveness evaluation to
decide among competing  control re-
sponses. The manual presents summary
tables for the potentially applicable tech-
nologies (e.g., pumping,  wastewater
management, lagoon cover systems, berm
reconstruction, and surface water diver-
sion systems) which include  specific,
decision-related criteria regarding  tech-
nology applicability, limitations, and costs.
  The  technology evaluation shouM
screen the options based on applicability
to the site problem (defined through the
site criteria)  as well as the potential to
reuse any permanent systems or materials
or the need to demolish structures such
as covers or diversion structures for final
site action. The reuse of a system will
impact its cost-effectiveness since the
capital investment is spread over several
applications. Alternatively,  the  removal
of a cover and its anchoring system or
the demolition of diversion structures may
impact the costs of the final remedial
action.
Other criteria included in the  technology
evaluation are:
  • Anticipated  length of time before
    remedial measures are implemented
    - Short  time intervals (less that  3
      months) would support a pumping
      system or diversion structures.
    - Long time intervals (3  to 5 years)
      would support cover systems.
  • Urgency of problem
    - Where lagoon  overflow is  immi-
      nent, pumping or construction of a
      temporary holding pond would be
      indicated.
    - Where the situation is less urgent,
      pumping may be used as an initial
      measure prior  to another control
      response or pumping  alone may
      be  implemented  as  a  cont-—'
      measure.
  • Time to implement control measures
    - Cover  systems will require  more
      time to implement than the use of
      pumps or site reconstruction.
  • Size of lagoon
    - Structural covers cannot be used
      where the smallest dimension ex-
      ceeds the greatest width available.
    - Multiple pumping stations or berm
      reconstruction may be more cost-
      effective than a floating cover  for
      large lagoons.
    - Covers may be more applicable to
      small and moderate sized lagoons
      where frequent pumping may be
      necessary.
  • Volume of liquid to be removed
    - Areas with heavy or frequent rain-
      fall would favor a  permanent
      pumping station, berm reconstruc-
      tion, diversion structures, a cover,
      or a combination of these options.
    - Areas with isolated precipitation
      events would  favor temporary
      pumping stations.
  As part of the cost-effective selection
effort, general estimates can be made for
rapid comparisons of responses and deci-
sionmaking. One method  would be to
average the costs over the length of time
that the control measure is in effect. In
such cases, the costs should include gross
estimates of maintenance, inspection, and
repair activities that would be likely within
the time period. Detailed cost guidance is
available  through  EPA  procedural
manuals.
  Both the technology and cost compari-
sons  should consider single-response
options and multiple-response options. In
some instances, a technologically complex
solution may be more cost-effective than
a technologically simpler  solution.   For
example, under certain conditions it may
be more cost-effective to install a floating
cover on a  lagoon (including an initial
pumpdown and some berm strengthen-
ing) to control  overflow resulting  from
precipitation than  to pump down  the
lagoon level several times a year while
the final response action is under study.
Of course, this decision depends on  the
expected length of time before final mea-
sures are  implemented, the technology
costs,  and  on-site  features  such  as
precipitation patterns.
  Of special importance is the evaluation
of pumping  options.  Either a temporary
pumping system can be brought in when
needed or a permanent pumping system
can be constructed. The decision would
depend on the number of times pumping
would be necessary and the relationship
of pumping to other options. However,
where frequent pumpdowns are neces-
sary (e.g., due to heavy annual rainfall), a
permanent pumping station should be
selected unless a  more cost-effective
control  option is available. Lagoon size,
volume of liquid to be pumped, frequency
of pumping,  and wastewater  manage-
ment requirements would all affect the
selection of this option.

  Wastewater management options also
involve a complex evaluation. Wastewater
management is always necessary in con-
junction with pumping. Management
options involve a number of on-site and
off-site methods to store, transport, treat,
or dispose of pumped  liquids. Liquids
could be pumped to a storage  tank on-
site  or  a tank truck may  be  used to
transport wastewater  to  an  off-site
Publicly Owned Treatment Works (POTW)
or commercially operated treatment fa-
cility. Mobile  treatment  units  may be
brought on-site to pretreat wastewater in
order to make it acceptable for  a POTW.
Wastewater  can  also  be  discharged
directly from the site to a surface water
body if it meets water quality standards.
Finally,  the  liquid  may be  discharged
directly to a POTW provided that sewer
connections are available and the com-
position of the liquid is acceptable for the
POTW. Key decision factors will involve
the  type of  pumping system  selected
(temporary or permanent),  wastewater
quantities,  wastewater  characteristics,
available facilities, etc.
  The manual discusses factors affecting
selection, installation, and costs of pump-
ing systems as well as  various waste-
water management options.

Lagoon Cover Systems
  Waste lagoons may be covered to pre-
vent precipitation accumulation that may
cause the impoundment to  overflow. A
variety of commercially  available  cover
systems have been  used  in  similar
applications.

Frame-Supported Tension
Membrane Structures
  Frame-supported  tension  membrane
structures provide an efficient and stable
building with a free span coverage of a
site.  These structures consist  of fabric
panels tensioned between specially de-
signed arches. Such structures are avail-
able  commercially  from  a  number of
manufacturers and  have been used in
exhibitions and fairs, and  in  aviation,
manufacturing, recreation, military, and
mining applications.
  Frame-supported  tension  membrane
structures are available at total  costs
ranging from $8/ft2 to $19/ft2. There are

-------
limited operational costs unless special
control systems are required. They cannot
be used if the smallest lagoon dimension
is greater than  140 feet or if the soil
conditions are inadequate to support the
load of the structure and/or  the con-
struction equipment. The site must also
be easily accessible in order to erect the
structure. The frame is susceptible  to
attack by strong acids and may require
treatment with  special  coatings in an
acidic environment.
  In general, this option is not feasible
for short-term usage at a single site. This
type of structure is reusable and can be
decontaminated; accordingly, its applica-
tion  may  be cost-effective if  reuse  at
other sites is practicable.

Prefabricated  Steel Frame
Buildings
  Prefabricated  steel frame  buildings
such as those used for warehousing may
also be used to cover lagoons. There are
many manufacturers of steel frame build-
ings and various types of structures. The
rigid frame  system is one of the more
common and most practical to use over
moderately sized lagoons.
  The total costs of a prefabricated steel
frame structure to cover a lagoon varies
from $14/ft2 to $23/ft2 depending on the
site, design  of the structure, coating re-
quired, and manufacturer. (In most cases,
a  special coating may  be required  to
increase the longevity of the structure).
The  structure can  be decontaminated,
dismantled,  and reused. This  structure
cannot be  used  if the smallest lagoon
dimension is greater than 200 feet. As
with other structures, it is necessary to
determine the stability of the soil to with-
stand the loading of the building and
construction equipment.
  In general, the  high  costs of a pre-
fabricated steel  frame  structure  make
this  control measure infeasible unless it
can be reused at other sites.

Air-Supported Structures
  Air-supported  structures have  been
used for warehouses and construction
shelters, and  for covering recreational
and sewage treatment facilities. This type
of structure is a totally free-span structure
that maintains stability in  space and
resistance to loads through  a  pressure
differential between the  interior and ex-
terior of the structure.  This method  of
support leaves the interior free of poles,
pillars, or other support devices that would
be impractical to erect over a lagoon.
  Air-supported  structures  can cover
lagoons of many configurations and sizes.
Their total costs range from $3.25/ft2 to
$10/ft2 and are thus highly competitive
with other technologies used for over-
topping control. The coated fabric used in
the  structure can  be selected  to be
compatible  with  the contents  of the
lagoon. Heating, ventilation, condensate,
and  air pollution controls can also be
designed to meet specific lagoon and site
requirements. These auxiliary systems
impose additional costs to the cover sys-
tem; however, the cover can be decon-
taminated and is reusable.
  There are several limiting factors for
the application of air-supported struc-
tures. If the smallest lagoon dimension is
greater than 550 feet, this system cannot
be used. The soil conditions may preclude
certain anchoring  systems or require the
construction of concrete anchoring bases,
which will increase the system cost.

Floating Cover Systems
  A  floating cover consists of a lining
placed in one piece over an impoundment
with proper  anchoring at the edges and
floats to prevent the lining from sub-
merging. According to industry officials,
approximately 80 to 85 percent of all
floating covers have been constructed
over potable water reservoirs. The re-
maining 15 to 20 percent have been used
at biodegradation facilities, slaughter-
houses, chemical treatment ponds, and
toxic waste lagoor
Floating covers
any other type of ci
in total cost be
$6.50/ft2. The Mr
vary according t<
lagoon; Hypalon
type of liner used.
is limited if there i
of debris on the s
submerged in the
ture the cover. Ar
floating cover is t
be reusable due to
to lagoon content!
Surface Water
Bern Improvei
Lagoons may 0'
water run-on or 1
manual discusse
maintain or increa
of the lagoon by:
• Diversion of
face run-on
ditches, diver:
• Prevention of
through the
struction of b
These control opti
5.
re less expensive than
vering system, ranging
ween $2.50/ft2 and
ng material used can
the contents of the
s the most common
Use of a floating cover
s a substantial amount
rface of the lagoon or
agoon that may punc-
other limitation of the
lat the fabric may not
swelling from exposure

Diversion and
nents
erflow due to surface
erm degradation. The
options that either
se the holding capacity

quid inflow from sur-
through the use of
ions, dikes, and berms.
waste material outflow
instruction or recon-
srms.
ns are unique relative
to other overtopping controls discussed
because they are directed at preventing
overtopping through measures applied,
external to the impoundment (i.e., on the
walls or surrounding areas).

Surface  Water Controls
  Surface water controls are improve-
ments external to the impoundment and
its immediate area that prevent liquids
from entering the impoundment or erod-
ing impoundment walls. When designed,
constructed,  and maintained  correctly,
surface water controls can extend the
useful life of the impoundment by either
preventing run-on, which fills available
lagoon capacity,  or  reducing  wall  de-
gradation, which  lessens available lagoon
capacity.  Surface water  control  tech-
niques include:
  •  Ditches, diversions, and waterways:
     small drainage ways  that intercept
     and  divert  run-on away from  an
     impoundment.
  •  Diversion and interceptor berms and
     dikes: structures  that intercept and
     divert  run-on  away  from   an
     impoundment.
  •  Terraces and benches: wide drainage
     ways that slow down run-on and
     divert it to ditches and diversions.
  •  Levees and floodwalls:  embank-
     ments used to prevent contact of
     floodwaters and tides  with  the
     impoundment.
  These options are discussed in detail in
the manual. Also included are unit costs
for construction  of ditches, diversions,
and waterways, as well as costs for other
diversion structures. In general, costs of
surface water controls are very dependent
on such items as:
  •  Extensiveness and terrain of  area
     requiring control.
  •  Number  and size  of  structures
     required.
  •  Amount  and  type   of  non-local
     materials required (e.g., cement,
     asphalt, synthetic liners, etc.).
  •  Accessibility of the site (especially
     for heavy machinery).
  •  Severity of weather patterns.
  •  Design life of control.

Impoundment Wall Construction
and Repair
  When designed, constructed, and main-
tained correctly, improvements to surface
impoundment walls can extend the useful
life of the  impoundment by either main-
taining or increasing its  capacity  until
final  response actions are implemented.
This  can  be accomplished by either  re-
pairing existing  defective  walls and/or

-------
increasing the height of berms to increase
capacity. These options, along  with as-
sociated costs, are discussed in detail in
the manual. Factors influencing the costs
are similar to those identified for surface
water controls.

Conclusion
  Presently, the most common method of
preventing  overtopping of abandoned
waste lagoons is  pumpdown/treatment
of the upper two feet of  the waste liquid.
Since this costs between $0.10/gal and
$.40/gal, this method can be expensive,
especially if it must be performed several
times prior to final cleanup of a site.
Alternative methodologies are available;
however, the final costs will depend on
many site-specific factors. These factors,
along with  details on alternative tech-
nologies  such as: pumping and waste-
water management, various lagoon cover
systems, surface water controls, and im-
poundment wall construction and repair,
are presented in the manual. The manual
will enable Federal, state,  and  local of-
ficials to select a technology or  series of
technologies  for  short-term control of
impoundments that are subject to over-
topping through collection  of rainwater,
run-on, or other uncontrolled inflow.
Virginia Hodge. Nick DeSalvo. Shahid Mahmud. Joshua Margolis, Mark Evans.
  and John Meade are with JRB Associates, McLean. VA 22102.
Anthony N.  Tafuri is the EPA Project Officer (see below).
The  complete report, entitled  "Guidance Manual on Overtopping  Control
  Techniques for Hazardous  Waste Impoundments," (Order No.  PB  86-154
  168/AS; Cost: $16.95. subject to change) will be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, v'A 22161
        Telephone: 703-487-4650
The EPA Project Officer can be contacted at:
        Releases Control Branch
        Hazardous Waste Engineering Research Laboratory—Cincinnati
        U.S. Environmental Protection Agency
        Edison, NJ 08837

-------
United States
Environmental Protection
Agency
Official Business
Penalty for Private Use $300

EPA/600/S2-86/012
Center for Environmental Research
Information
Cincinnati OH 45268
TV fl'-S-POSIAGe
                                                                      v
      0000329  PS
      U  S ENVIR  PROTECTION AGENCY
      REGION 5 LIBRARY
      230 S  DEARBORN  STREET
      CHICAGO             IL   60604

-------