United States
Environmental Protection
Agency
Water Engineering
Research Laboratory
Cincinnati OH 45268
Research and Development
 EPA/600/S2-86/053 Aug. 1986
Project  Summary
Assessment of  Assay
Methods for Evaluating
Asbestos  Abatement
Technology

Mark A. Karaffa, Robert S. Amick, Ann Crone, and Thomas J. Powers
  Two analytical methods and two sam-
pling schemes were evaluated for their ef-
fectiveness in  a project to remove air-
entrainable asbestos from Columbus East
High School in Columbus, Indiana. The
two analytical methods were phase con-
trast microscopy (PCM) and transmission
electron microscopy (TEM). The sampling
schemes included a static method and an
aggressive one using a leaf blower.
  The study results indicated that the
building abatement did meet the PCM
specifications in effect at the time, allow-
ing acceptance of the work and  reoc-
cupancy. However, the TEM results re-
vealed airborne asbestos concentrations
averaging four times outdoor levels with
peak values near 1 million asbestos struc-
tures/m3. Aggressive sampling amplified
the significance of the situation, produc-
ing average airborne asbestos concentra-
tions that were 50  times the  outdoor
levels, with peak concentrations near 1.5
million asbestos structures/m3 of air.
  As a result of this study, TEM coupled
with aggressive sampling is the currently
recommended method of choice for post-
abatement clearance.
  This Project Summary was developed
by EPA's Water Engineering Research Lab-
oratory, Cincinnati, OH, to announce key
findings of. the research project that is fully
documented in. a separate report of the
same title (see Project Report ordering in-
formation at back).

Introduction
  The Technical Assistance  Program of
the Office of Pesticides and Toxic Sub-
stances of the U.S. Environmental Pro-
tection Agency (EPA) provides guidance
and information on the identification of
asbestos-containing materials in buildings
and on the correction of potential asbestos
hazards. Four EPA Guidance Documents
contain much of the technical informa-
tion about asbestos in nonindustrial set-
tings. 1'2'3'4 These documents describe
how to establish an asbestos identification
and control program, provide background
information and direction to school of-
ficials and building owners on exposure
assessment, and develop and implement
an asbestos  abatement  program.  The
most recent asbestos guidance from EPA
not only emphasizes recent experience
and new information on asbestos control
but also introduces and discusses criteria
for developing an appropriate asbestos
control plan.
  Considerable scientific uncertainty still
surrounds the effectiveness of  specific
abatement actions in reducing the risk of
exposure to airborne asbestos. One critical
concern among those responsible for as-
bestos abatement is how  clean the con-
tractor leaves a building (or building area)
after removing the asbestos material or
after completing work that  could have dis-
turbed an asbestos-containing material
(e.g., encapsulation, enclosure, or special
maintenance operations). The two criteria
recommended  by the EPA guidance
(1983)3 that was in effect at the outset
of this study were visual inspection of the
worksite and air monitoring after comple-
tion of the project. Visual inspection
should detect incomplete  removal, dam-
age caused by abatement activity,  and
(most important) the presence of debris or
dust left by inadequate cleanup of the
work area. Air monitoring by the mem-
brane filter collection technique and phase-
contrast microscopic (PCM) analysis are
recommended to supplement the visual in-
spection  and to determine whether ele-
vated levels of airborne  fibers generated
during the removal process  have been suf-

-------
ficiently reduced. This currently recom-
mended optical microscopic technique is
one of two methods specified by the Na-
tional  Institute for Occupational Safety
and Health (NIOSH) to determine airborne
fiber concentrations;  it is used by the
Occupational Safety and Health Adminis-
tration (OSHA) to measure total airborne
fibers in occupational environments.
  The  EPA-recommended air-monitoring
methodology for determining abatement
completion (NIOSH Method No. P&CAM
239) was as follows:
  Air sampling should begin after the
  project has been completed and all
  surfaces in the  abatement site have
  been cleaned, perferably within  48
  hours after abatement work is finish-
  ed. A minimum  of three air monitors
  per worksite and at least one per room
  is recommended. Air is drawn through
  a membrane filter for about 8 hours
  at a flow rate of  approximately 2 liters
  per minute."A total air volume of ap-
  proximately 1,000 liters collected at
  the   specified flow  rate should  be
  sampled. After  the sampling, a sec-
  tion  of  the filter  is mounted on a
  microscope slide and treated to form
  a transparent, optically homogeneous
  gel. The fibers are sized and counted
  by using a phase-contrast microscope
  at 400  to 450X magnification. For
  counting purposes, a fiber is defined
  as a particle with a physical dimension
  longer  than 5  micrometers and a
  length-to-diameter ratio of 3 to 1 or
  greater.3
This method is intended to give an index
of the.airborne concentration of fibers of
specified dimensions  in an atmosphere
known or suspected to contain asbestos;
it is not designed to count fibers less than
5 \xn   long or to  differentiate  asbestos
fibers from other  fibrous particulates.

  The  most significant limitation of the
PCM method 6ompared with transmission
electron microscopy (TEM) and scanning
electron microscopy (SEM) is that PCM is
limited in  the detection of fine particles
(i.e., those with submicron diameters or
lengths less than  5 ^m) that may be toxi-
cologically significant.  For  example,  in
glove-box tests of  simulated  industrial
mechanical operations on asbestos-con-
taining products (drilling, sawing, and san-
ding),  the PCM method counted fewer
than 1 percent of the fibers counted by
TEM.5  Although conditions of this glove-
box study were obviously different from
asbestos abatement activities, some con-
cern existed about the relative merits and
capabilities  of the different analytical
methods used to determine representative
fiber concentrations. Another study esti-
mated that small asbestos  fibers (i.e.,
fibers less than 0.2 ^m wide and 5 \*m long
that are not detected by the PCM method)
were present at 50 to 100 times the con-
centration of the larger, optically visible
fibers.6

Study Objective
  The objective  of this research project
was to identify and quantify the fine frac-
tion of airborne asbestos fibers present in
building atmospheres after an asbestos
remedial activity. The project focused" on
the adequacy of EPA's previously recom-
mended PCM method of analysis and sam-
ple collection technique. The PCM method
was compared with TEM methods, and
the feasibility of an alternative aggressive
sampling technique was investigated. The
results of this study established the advan-
tages and limitations of applying PCM and
TEM analytical methods, both separately
and in  conjunction with an  aggressive
sampling technique, to the evaluation of
air quality following asbestos abatement.
  This project was conducted during the
postabatement phase of asbestos removal.
Reliable methods of air sampling and anal-
ysis permit the use of monitoring results
to be  included in evaluating the efficacy
of asbestos abatement methods and in
developing better technical guidance for
abatement contractors, building owners,
and other parties directly responsible for
remedial asbestos programs.
  Active or recently completed abatement
sites  were selected 'for  monitoring  be-
cause they provided an excellent opportu-
nity to collect real world data, and because
the monitoring tasks could be arranged
with minimum lead time and coordination.
  The conditions in a work area while the
final air samples are collected can  influ-
ence the results of a postabatement as-
sessment. After an abatement action, the
air  is  usually sampled while the area is
sealed off, before ventilation is restored,
and after at least a 24-hr settling period
following the final wet cleaning. Conse-
quently, this monitoring technique may fail
to detect residual fibers that have settled
on  horizontal surfaces during this static
condition or that  were missed  by the
cleaning.

  Residual  asbestos fibers  constitute a
potential exposure hazard because they
could  be reentrained later, when the air in
the area is agitated by personnel traffic,
air  flow  from ventilation systems, and
custodial activities. Thus for more accu-
rate characterization of postabatement fi-
ber concentrations, the work area should
experience appreciable air movement to
simulate actual use conditions during air  J
monitoring.                             *
  The introduction of air turbulence into
the work area during the collection of sta-
tionary air samples is termed "agressive
sampling." This method entails the crea-
tion of air movement by the use of blowers,
fans, brooms, or compressed air streams
to entrain any paniculate matter that may
be present. The advantages of the aggres-
sive sampling technique over the static (or
nonaggressive) sampling are that the for-
mer reflects worst-case conditions and
that the testing requires a relatively short
period. The  disadvantages are that this
technique is not readily standardized or
reproducible, nor does it reflect normal ex-
posure levels to  occupants. As with  the
static sampling method, no criteria have
been established to define an acceptable
or safe level of fibers in a nonoccupational
environment. The research on fiber con-
centration levels using the  PCM and TEM
methods is continuing so that the before-
, during-, and after-abatement criteria can
be developed within  the next 2 years.

Project Description
Site Select/on
  Air monitoring was conducted at two
selected sites from which friable asbestos
building materials had been removed: Site
1, Columbus East High School, Columbus,
Indiana; and Site 2, the U.S. EPA Environ-
mental Research Laboratory in Corvallis,
Oregon.
  This report describes only the results of
the air monitoring survey  conducted at
Site 1.  The monitoring data from Site 2
and the significance of these data are  the
subject  of a separate report. These  se-
lected sites met the  following criteria:
  • The abatement  plan  involved  the
    removal of friable, spray-applied,  as-
    bestos-containing material.
  • The contractors  carried out the work
    area preparation, removal, and decon-
    tamination in accordance with EPA-
    recommended  specifications  and
    requirements.1
  • Multiple work areas containing  ho-
    mogeneous asbestos material were
    available for monitoring.
  • The building owner and  abatement
    contractor agreed to cooperate with
    EPA and to provide access to select-
    ed  areas of the  building.
Abatement Program
  A multiphase asbestos abatement and
renovation program  was conceived and
implemented. The first abatement phase

-------
was conducted during  the summer of
1984 and included the following areas:

  Academic Building:
    Third floor - all rooms
    North and south large-group instruc-
    tional rooms (sidewall enclosures)
    Mechanical penthouses
    Stairwells and elevator shafts
    Industrial arts
    TV studio/publications
    Music rooms
    Auditorium
  Gymnasium:
    Storage rooms
    Mechanical room
    Concessions
    Restrooms

  Sources of friable, asbestos-containing
fireproofing were controlled by removing
the material or by placing it in airtight en-
closures in areas where complete removal
and replacement were not feasible. Deci-
sions regarding the most appropriate con-
trol method for each Phase  I subspace
were based on EPA-recommended assess-
ment factors for evaluating the potential
for fiber release.3
  Asbestos-containing fireproofing insula-
tion had been spray-applied to steel beams
and columns on the first, second, and third
floors and in mechanical areas. The range
of asbestos concentration for this moder-
ately friable material was 30 to 60 percent
chrysotile asbestos, based on an analysis
of 17 representative bulk samples by polar-
ized-light microscopy and dispersion stain-
ing.7 Throughout these areas, there was
a considerable  amount  of  overspray on
sections of the corrugated steel deck pan
between the treated beams. The treated
beams  were largely concealed by a  su-
spended lay-in or interlocking steel panel
ceiling,  but in some areas, the construc-
tion design rendered the fireproofed beams
visible and exposed.
  The structural beams on the lower level
had also been sprayed with friable mater-
ial, but it contained no asbestos. Many of
these beams had been enclosed by drywall
and  therefore  were not visible.  Other
beams on the lower level were concealed
above suspended ceilings, and still others
were exposed  (visible).
  Asbestos-containing  fireproofing was
also found in the gymnasium on the ceil-
ing above the mezzanine level and in the
mechanical equipment and storage rooms.
The spray-applied material on beams above
the suspended ceiling on the lower level
of the gymnasium contained mostly fi-
brous glass and no asebestos fibers.
Procedures
  The procedures followed for the removal
and enclosure of the asbestos-containing
fireproofing at Site 1 were consistent with
those described in the EPA guidance docu-
ments, and they complied with EPA and
OSHA asbestos regulations. Detailed spe-
cifications describing the scope of work,
the work  sequence, and specific perfor-
mance criteria for the abatement contrac-
tor were prepared by the project team and
distributed as part of the bid package. The
technical job specifications for the removal
and enclosure of the asbestos-containing
fireproofing  were  based on the  Guide
Specifications for the Abatement of As-
bestos Releases From Spray- or Trowel-
Applied Materials in Buildings and Other
Structures, published by the Foundation of
the Wall and Ceiling Industry.8
  An industrial hygiene technician was on-
site throughout the entire abatement pro-
ject. The field technician was  under the
direct supervision of a certified industrial
hygienist,  who made weekly inspections
of the job  site and was available for con-
sultation. The first phase of the asbestos
abatement program began on May 30 and
was completed (excluding final renovation
items) by  August 11, 1984.  The second
phase of the abatement program was com-
pleted during the summer months of 1985,
and the third phase will be completed dur-
ing the summer of 1986.

Abatement Activities
  The abatement activities were performed
in three distinct stages: preparation, re-
moval, and decontamination. Each of the
building areas included in Phase  I were
isolated as separate abatement work areas.
Some work  areas comprised multiple
rooms (e.g., the third-floor classroom area
and the music area), and some consisted
of a single room (e.g., the penthouses,
storage rooms, and the TV studio). Each
work area  was prepared by turning off the
ventilation and electrical systems; sealing
off all air ducts and openings; covering the
floors, walls, and immovable objects with
plastic sheeting; installing high-efficiency-
particulate-air-  (HEPA-) filtered exhaust
units; and  constructing worker decontam-
ination facilities. Suspended ceilings and
carpeting  were removed and disposed of
as contaminated waste, or they  were
cleaned and disposed of by conventional
means. Workers wearing full protective
equipment and approved air-purifying res-
pirators removed the fireproofing by first
wetting it with an amended water solution
and then  scraping  it off. The  asbestos-
containing debris was placed  in double
 6-mil plastic bags and disposed of at a
 local EPA-approved sanitary landfill. All
 substrate materials from which asbestos
 was removed were wire-brushed and wet-
 wiped repeatedly to remove as much of
 the fireproofing material as possible. A dry
 removal method that did not use the
 amended water solution was used in the
 TV studio room to prevent damage to the
 acoustical panels  and electronic equip-
 ment in this area.
  All stripped or potentially contaminated
 surfaces were sprayed with an approved
 asbestos  sealant to bond any residual
 fibers to the substrata The work area was
 decontaminated by removing all loose de-
 bris, removing the plastic sheeting from
 the walls and floors, and repeatedly  wet-
 wiping or mopping the walls and floors.
 When the work area had passed a thor-
 ough visual inspection and air monitoring
 showed that the fiber concentrations were
 less than 0.05 fiber/cm3 (the clearance
 level of the contractor's specifications),
 the  barriers and HEPA-filtered exhaust
 units were removed, and the area  was
 opened for occupancy by other tradesman
 responsible for various components of the
 renovation, for example, fireproofers, pain-
 ters, electricians, plasterers, and heating,
 ventilating, and  air conditioning (HVAC)
 installers.
 Monitoring Approach
  Samples for subsequent PCM and TEM
analysis were collected from two or three
representative locations within each de-
signated work area after completion of all
abatement activities but before any appli-
cation of replacement fibrous material (e.g.,
nonasbestos fireproofing). Plastic sheeting
on walls and floors had been removed, the
substrate had been sprayed with a sealant,
and HEPA-filtered exhaust units had been
removed. Air sampling was not conducted
until the abatement area had passed a rig-
orous visual inspection by the onsite in-
dustrial  hygienist and architect. In each
designated work area, first static and then
aggressive sampling techniques were used.
To summarize briefly, filter holders contain-
ing either 0.8-^m Millipore mixed-cellulose
ester filters  (PCM) or 0.4-^m Nuclepore
polycarbonate filters (TEM)  were  posi-
tioned (1.4 to 1.7 m) 4.5 to 5.5 ft above
the floor at  arbitrary locations. Battery-
powered sampling  pumps were used to
draw air through the filters. The constant-
flow pumps were calibrated to 2 to 3 L/m
and were operated for 6 to 8 hr/test, de-
pending  on  the contractor's  schedule.
Samples were collected from several in-
door work areas and at outdoor locations
during each  monitoring period.

-------
  In addition to the postabatement moni-
toring, limited preabatement monitoring
was conducted in an area of the audito-
rium to take advantage of the one oppor-
tunity available for preabatement monitor-
ing in the abatement program schedule.
Two PCM and  two TEM preabatement
samples were obtained and analyzed.
  Upon completion of each monitoring
survey, samples were submitted to the ap-
propriate  laboratory for  preparation  or
analysis. The Nuclepore filters were hand-
carried to EPA for carbon coating before
they were transported to the laboratory for
TEM analysis.

Methods of Air Sampling
and Analysis
Overview of Sampling  Strategy
  Samples designated for PCM and TEM
analysis were collected with both aggres-
sive and static methods in seven different
work areas. Samples were also collected
from the surrounding environment outside
the building. Each work area consisted of
a specific room or rooms and adjacent hall-
ways, closets, or other spaces that were
treated as a separate component of the
total abatement project. The building areas
sampled included the auditorium, gymnas-
ium, industrial arts rooms, music rooms,
projection booth, TV studio, and elevators.
These sampling locations were not select-
ed as part of a study design; selection was
dictated by the contractor's abatement se-
quence and schedule. After completion of
abatement efforts in the individual work
areas, representative PCM and TEM sam-
ples were collected. All outdoor air sam-
ples were collected in the parking lot ad-
jacent to the school building, except for
one that was collected on the roof of the
building.
  All postabatement air samples were col-
lected  while the work area was still iso-
lated (i.e., containment barriers were in
place) but after (1) the substrate had been
sprayed with a sealant,  (2) the plastic
sheeting  covering the walls and floor had
been removed,  and (3) all surfaces  had
been wet-wiped. Because of timing, limit-
ed  preabatement monitoring in one area
of the  auditorium was conducted before
any abatement activity in the auditorium.
Insofar as possible, outdoor and indoor air
sampling was conducted concurrently, but
inclement weather or equipment availabil-
ity  sometimes made this impossible.
  Whenever  possible, side-by-side sam-
ples, (one PCM and one TEM)  were col-
lected  in  each work area under static and
aggressive sampling conditions. Accessi-
bility  restrictions prevented aggressive
sampling in some areas. As each building
area became available, sampling was per-
formed in the following sequence. Sam-
ples designated for both PCM and TEM
analysis were collected under nonaggres-
sive conditions approximately 1 to 24 hr
following a satisfactory visual inspection
of the of work area by the architect and
onsite industrial hygienist, depending on
the contractor's schedule for final clean-
ing.  Immediately  afterward  or on the
following day, samples for PCM and TEM
analysis were again collected, this time
under aggressive conditions (i.e., turbulent
air movement). Placement of the sampling
equipment within each work area was the
same during both static and aggressive
sampling. The number of samples per work
area was not specified  by study design,
but efforts were made to collect at least
two of each type of sample within each
work area.

Sampling Equipment
  Samples for PCM analysis were collect-
ed on 37-mm Millipore, Type AA, mixed-
cellulose ester membrane filters (0.8-jum
pore size). The filters were preassembled
in three-stage polystyrene cassettes  by
the  manufacturer.  Samples  for TEM
analysis  were  collected  on  37-mm
Nuclepore polycarbonate membrane fil-
ters (0.4 fjm pore size). The polycarbonate
membrane filter was supported within a
three-stage  polystyrene cassette  by
means of a support pad and backup filter
(mixed-cellulose ester membrane, 5-//m
pore size). Each  sample cassette was
sealed with a cellulose shrink band to
prevent air from entering the sides of the
unit during sampling.
   Battery-operated  personal  sampling
pumps equipped with rotameters and/or
constant-flow controls were used to draw
air through the sample filters. All sampling
pumps were calibrated with a soap-film
flowmeter before and after sample collec-
tion. The rotameter setting of  each cali-
brated sampling pump was noted to pro-
vide a visual indication of proper pump
functioning, and the settings were check-
ed periodically throughout the sampling
period.

Sample Collection  and Handling
   Samples designated for both PCM and
TEM analysis were collected at a known
flow rate of approximately 2 to 3 L/min
(LPM). Sampling duration was 6 to 8 hr.
The average sample volume per filter was
 1,200 L.
   All samples were collected open-faced
(i.e., with the face cap of the cassette de-
vice removed) to expose the maximum ef-
fective surface area of the filter. During
sampling,  the  face caps were carefully
stored in clean, resealable, plastic bags.  4
The filter  cassettes were positioned at  "
breathing zone height (1.4 to 1.7 m, or 4.5
to 5.5 ft above the floor) and were sup-
ported by taping the end of the sampling
hose to the wall or clipping it to an adjust-
able tripod. The sample cassettes were
also positioned so that the membrane fil-
ters were  angled  approximately 45 de-
grees toward the floor.
  At the end of the sampling period, each
filter cassette was turned upright (i.e., the
filter plane was parallel to the floor), the
sampling pump was turned off,  the face
cap of the three-stage filter cassette was
repositioned tightly on  the cassette, the
cassette was disconnected from the sam-
pling hose, a plastic plug was inserted into
the cassette outlet, and the cassette was
placed face-up in a box for transport.  All
PCM and TEM filter samples were main-
tained in this  upright position from the
time of collection until they were carbon-
coated or analyzed by the  appropriate
laboratory.
  The PCM analysis equipment was avail-
able at the Columbus East site, and a por-
tion of the PCM samples (final clearance
samples collected under static conditions)
were analyzed onsite shortly after comple-
tion of sampling. Rapid  reporting of these
sample results was essential so that the
building areas could  be released  to the
contractor for additional nonabatement
work and renovation. The remaining PCM
filters were hand-carried to the laboratory,
where they were subsequently analyzed.
  The TEM samples were submitted to the
EPA Project Officer (or his representative)
and  hand-carried  to  EPA in  Cincinnati,
where they were carbon-coated. The TEM
samples were then either shipped by over-
night courier or hand-carried to the lab-
oratory for analysis.

Static Sampling
   Samples for PCM and TEM analysis
were collected under static conditions for
comparison with similar samples collected
under aggressive conditions. The sampling
condition was considered static when air
movement in the work area was negligible
and/or minimized to the greatest possible
extent. Under this condition,  asbestos
fibers (or any other particulate matter) will
settle out if given sufficient time. Any work
area,  no matter how contaminated, can be
totally "clean" as defined by PCM as long
as enough time is allowed to elapse before
static sampling. The probability of reen-
trainment of these asbestos fibers is much
lower under static conditions than under

-------
 conditions of typical building use (aggres-
 sive sampling conditions).  In this study,
 static sampling conditions  existed when
 the work area was sealed off, all ventila-
 tion was shut off, and personnel access
 was prohibited. These are the typical con-
 ditions under which air monitoring is con-
 ducted at a work site following asbestos
 removal  and decontamination.

 Aggressive Sampling
   Samples for  PCM and TEM analysis
 were also collected under agressive sam-
 pling conditions.  Aggressive conditions
 were created by introducing  air turbulence
 into the sampling area by intermittent use
 of  a hand-held electric blower. The air
 movement created was much greater than
 would exist under conditions of normal
 building use. Under these aggressive sam-
 pling conditions,  most asbestos fibers
 susceptible to entrainment will become
 airborne  and remain suspended for the
 duration  of the sampling period, as long
 as the use of fans or the hourly introduc-
 tion of air turbulence is continued. Thus
 an aggressive environment provided the
 best possible setting for high or "worst-
 case"  airborne asbestos fiber concentra-
 tions following abatement. Figure 1 com-
 pares  airborne  fiber concentrations for
                        PCM and TEM under static and aggressive
                        conditions.
                          The blower used in this study was a 1-hp
                        electric power blower (Figure 2). The air-
                        flow rate at the blower outlet is approx-
                        imately 8.5 m3/min (300  ft3/min). The
                        electric blower was equipped with a two-
                        piece plastic tube extension and concen-
                        trator nozzle that enabled the operator to
                        direct the airstream at objects and sur-
                        faces within the sampling  area.
                          Aggressive sampling conditions were
                        created in each of the work  areas sampled
                        by an initial blow-down of all  surfaces,
                        followed  by  hourly agitation  with  the
                        blower throughout the  duration of  the
                        sampling period. During aggressive sam-
                        pling, all containment barriers isolating the
                        work area were intact, and building air-
                        handling systems remained off. In some in-
                        stances, it was necessary for the contrac-
                        tor to remove the HEPA filtration units for
                        use in another active work area..Figure 3
                        shows the aggressive sampling procedure
                        in progress. The sequence of operations
                        is summarized below:
                          1.  A technician entered the work area,
                             positioned the sampling equipment,
                             and started the sampling  pumps.
                          2. Using a back-and-forth motion, the
                            technician directed the airstream of
     the  electric blower at all surfaces
     within  the sampling  area  (walls,
     floors,  ceilings, all structures be-
     tween walls, ceilings, and floors, and
     any other  exposed surfaces within
     the  enclosed area). The  technician
     then exited from the sampling area.
  3. After approximately 1  hr,  the techni-
     cian reentered the work area and
     repeated the blow-down of  all sur-
     faces. This procedure was then re-
     peated hourly for the duration of the
     sampling period. Unless actively en-
     gaged in  manipulating the electric
     blower, the technician did not remain
     within the enclosure.
  4. At the end of the sampling  period,
     samples were  collected, sampling
     pumps were turned off, and the sam-
     pling equipment was removed from
     the area.
  The technician used appropriate respir-
atory protection  and  decontamination
procedures.

Methods  of Analysis
Phase-Contrast Microscopy
  All PCM samples were analyzed in ac-
cordance with NIOSH Method No. P&CAM
239.9 This optical microscopic technique
is the method the OSHA uses to measure
  Aggressive
     TEM
  Aggressive
     PCM
       Static
       TEM
      Static
       PCM
Ambient TEM
Ambient PCM
I     Range	1

  25%     75%
   Percentiles

           .001                   .005      .010                  .050      .100                  .500

                                                            106Fibers/m3

Figure 1.    Comparison of airborne fiber concentrations measured by TEM and PCM under aggressive and static conditions.

                                                                                 5
                                                                                         1 00
                                                                                                  2.00

-------
total airborne fibers in occupational en-
vironments. The EPA guidance document
pertaining to asbestos in buildings recom-
mends a visual inspection followed by air
monitoring by the membrane filter collec-
tion technique and PCM analysis as one
method for evaluating satisfactory com-
pletion of asbestos abatement and decon-
tamination of the work site.3
  Airborne fiber concentrations are deter-
mined by NIOSH Method No. P&CAM 239
through microscopic  examination of the
fibers collected on a mixed-cellulose ester
membrane filter. A triangular wedge con-
stituting approximately one-eighth of the
entire surface area of the 37-mm-diameter
filter is removed from the sample cassette,
mounted on a microscope slide, and ex-
amined. The filter wedge is rendered into
an optically transparent homogeneous gel
by the  use of a slidemounting solution of
1:1  (by volume) dimethyl phthalate  and
diethyl oxalate. A microscope  equipped
with a  phase-contrast condenser is used
to size and count the  fibers at 400 to
450X  magnification. Only  those fibers
longer  than 5 pan  with a length-to-width
ratio of 3 to 1 or greater are counted.
Fibers are sized by comparing fiber length
with the diameters of the calibrated circles
of a Porton reticle. Sample analysis con-
tinues until at least 20 fibers or 100 micro-
scopic fields  have been counted. Micro-
scopic field areas generally range from
0.003  to 0.006 mm2.
Transmission Electron Microscopy
  Nuclepore filters were prepared and ana-
lyzed for asbestos content by TEM in ac-
cordance with the Methodology for the
Measurement of Airborne Asbestos  by
Electron Microscopy.™ The current TEM
methodology was developed particularly
for application to samples collected from
a volume of air in which the asbestos con-
centration is considered  a minor compo-
nent of the total particulate loading. Car-
bon coating of the samples was perform-
ed by the EPA staff. Sample  preparation
and analyses were completed by the TEM
laboratory.
  Three levels of TEM analysis are describ-
ed in the methodology. Briefly summariz-
ed, Level I TEM analysis involves examina-
tion of the particulates deposited on the
sample filter by a 100-kV TEM. Asbestos
structures (fibers, bundles, clusters, and
matrices) are counted, sized, and identi-
fied as to asbestos type (chrysotile, amphi-
bole, ambiguous, or no identity) by mor-
phology  and  by observing the selected
area electron diffraction (SAED) patterns.
The width-to-length ratio of each particle
that is  counted is recorded. Level II TEM
analysis consists of a Level I analysis plus
chemical  elemental  identification  by
energy-dispersive spectrum (EDS) analysis.
Energy-dispersive analysis is used to deter-
mine the spectrum of the X-rays generated
by an asbestos structure. X-ray elemental
analysis is used for further categorization
Figure 2.   Electric blower used for aggressive sampling.

                                    6
of the amphibole fibers, identification of
the ambiguous fibers, and confirmation or
validation of chrysotile fibers. All Nucle-
pore samples collected in this study were
analyzed by Level II TEM.

Results
Air Monitoring Results
   The results of TEM analyses of samples
collected under static and aggressive con-
ditions are  compared in Figures 4 and  5.
The measured fiber concentrations after
abatement  varied widely under both static
and aggressive sampling conditions, re-
gardless of  the analytical method used. For
example, fiber concentrations  determined
by PCM  ranged from less than 2,000  to
90,000 fibers/m3 for static  sampling and
from 2,000 to 110,000 fibers/m3 for ag-
gressive  sampling.  Similarly,  concentra-
tions  determined by  TEM  ranged from
6,000 to  583,000 fibers/m3 for static
sampling and from 14,700 to 1.27 million
fibers/m3 for aggressive sampling.

Statistical Comparisons

Statistical Method of  Analysis
   The Mann-Whitney test was used to de-
termine whether the observed differences
in analytical methods and sampling con-
ditions were statistically significant.11 Use
of the Mann-Whitney test required no prior
assumption regarding  the  nature of the
underlying  probability distribution function
of measurements  of asbestos  fiber
concentrations.

Analytical Methods
   Table  1  compares the asbestos fiber
levels  detected  by the PCM and TEM
methods of analysis under various sam-
pling conditions. PCM and  TEM concen-
trations  relate to different fiber popula-
tions, as defined by their detection limits
and by their standard protocols. Based on
the application of the Mann-Whitney test
and the assumption that the fiber/volume
concentrations are comparable,  the dif-
ference between PCM and TEM results is
statistically significant (i.e., p <0.02) for
ambient sampling and for indoor sampling
under static and aggressive  conditions.
The ratios of TEM/PCM concentrations for
static sampling were 6.5 for ambient sam-
ples and 5.2 for indoor samples. For ag-
gressive sampling, the ratio of TEM/PCM
was 9.8.

Sampling Conditions
   The difference between  the geometric
average  fiber concentrations under static
and aggressive sampling conditions (Table
 1) was  statistically  significant  (i.e.,  p

-------
Figure 3.   Aggressive sampling in progress.
Table 1.    Comparison of Asbestos Fiber Levels* Detected by PCM and JEM Analyses
          Under Various Sampling Conditions


                                           Sampling Conditions
Analytical Technique
PCM analysis, fibers/m3
TEM analysis
Asbestos fibers/m3
Asbestos structures/m3
Outdoor
(Ambient)
2,000+110?
13,000 110]
15,000
Postabatement
Static
8,000 120]
42,000 [26]
64,000
Postabatement
Aggressive
27,000 [14]
266,000 [20]
725,000
 *AH values are geometric means.
 +Below limit of reliable quantitation 1 = 21,000 fibers/m3). Detection limit = fibers/m3.
 *[ ] =  number of samples.
 <0.001) for PCM and TEM. The ratio of ag-
 gressive to static fiber concentrations was
 3.4 for PCM analyses and 6.3 for TEM
 analyses.
 Indoor Versus Ambient Samples
  Also included in Table 1 are the PCM and
 TEM analyses for samples collected in the
 ambient atmosphere. For samples analyzed
 by PCM, the geometric mean fiber concen-
 tration was 8,000  fibers/m3 for indoor
 samples compared with 2,000 fibers/m3
 for  ambient  samples—a  ratio of  4.1.
 However,  the PCM  method is  not suffi-
 ciently sensitive for effective detection of
 these ambient and indoor (static) concen-
 trations because they are below the lower
 limit of reliable quantitation by the method.
 Consequently, the observed differences
 between the two sample groups are prob-
 ably not meaningful.
  For the TEM samples collected indoors
 under  static  conditions, the  geometric
 mean asbestos fiber concentration was
 42,000 fibers/m3 compared with 13,000
 fibers/m3 for ambient samples—a ratio of
 3.2. The  observed  difference  between
 these indoor, static  TEM concentrations
 and the ambient TEM concentrations was
 statistically significant (p = 0.009). The
 ratio of indoor asbestos concentrations
 under aggressive sampling conditions to
 ambient  asbestos concentrations  was
 20.5.

TEM Data from Static and
Aggressive Sampling Conditions
  Figures  4 and 5 present data from the
TEM asbestos analysis reports. Figure 4
 is the static TEM  measurement, and
 Figure 5 is the aggressive TEM analysis.
The analysis includes:
  •  Types of asbestos fibers observed.
  •  Number of other fibrous structures.
  •  Numbers  of nonfibrous  asbestos
     particles.
  •  Diameters and lengths  of fibers ob-
     served by analyst.
  •  Total  asbestos structures per cubic
     centimeter of air.
  The structural analysis data for each
 TEM sample were entered into EPA's DEC
 POP 11/70 computer in Cincinnati  and
 transferred to the IBM 3081 at EPA's Na-
 tional Computer Center in North Carolina.
 The data  were processed  by using the
 statistical  analysis system (SAS) and plot-
 ted by use of the TELLAGRAF system.
 Length-to-width plots were made for the
 fibers.
Conclusions and Recommendations
The following conclusions resulted from
this study:

-------
 I
      1.0
                                          i   iiiiiii      i    i   iiiiir

                                              PCM Method
                                                 7400
                                                 *
                                                 o
                                                      Legend

                                                  &  Chrysolite Fiber
                                                  Q  Chrysotile Bundle
                                                  O  Chrysotile Matrix
                                                  &  Ambiguous Bundle
                                                  •if  Amphibole Fiber
                                             I
                                                   I III
                                                                 1  I  I l  I I l
         0.01
0.1                      1

  Fiber Diameter, micrometers
                                                                           10
Figure 4.   Results o1 TEM analysis under static conditions. Plot of fiber length and diameter for
           a static postabatement air sample in Room M112.  Total asbestos structures/cc of
           air = 0.067.
   The aggressive sampling  technique
   used in this problem-definition study
   revealed that air-entrainable asbestos
   remained at this site immediately after
   completion of abatement actions. The
   mean asbestos fiber concentration dur-
   ing aggressive sampling, as determin-
   ed by TEM, was about 6 times that of
   the mean asbestos fiber concentrations
   during static sampling.
          2. The  fiber concentrations  measured
             under aggressive sampling conditions
             were higher than those measured un-
             der static conditions regardless of the
             analytical method used. The ratio of ag-
             gressive to static fiber concentrations
             during PCM analyses was 3.4, whereas
             this ratio during TEM analyses was 6.3.
             The average PCM concentration during
             aggressive sampling conditions was
   0.03 fiber/cm3-less than the NIOSH-
   recommended occupational limit of 0.1
   fiber/cm3. This 8-hr time-weighted av-
   erage is frequently cited in abatement
   contractor specifications  as the final
   postabatement acceptance criterion.
3. The study results clearly demonstrate
   that under similar sampling conditions,
   TEM analysis detects more fibers than
   PCM. The ratio of TEM/PCM concen-
   trations for static sampling was 6.5 for
   ambient samples  and  5.2 for  indoor
   samples; the ratio for aggressive sam-
   pling was 9.8.
4. Concentrations of work area asbestos
   fibers that were determined by TEM
   and measured by both  aggressive and
   static sampling methods were signifi-
   cantly higher than ambient  TEM con-
   centrations. The actual environmental
   conditions that exist in a building after
   reoccupancy, reactivation of ventilation
   systems, and the return to typical  us-
   age patterns are somewhere between
   the static and aggressive  sampling
   conditions.

The following recommendations are based
on the study findings:

1. TEM should  be recommended  as  the
   analytical method of choice for mea-
   suring airborne asbestos fiber concen-
   trations for final clearance testing in at-
   mospheres of buildings that have  un-
   dergone asbestos abatement. How-
   ever,  the current  TEM protocols  are
   very time-consuming and expensive for
   routine use in large  surveys.
2. PCM analyses should be conducted as
   a preliminary check to determine whe-
   ther additional  cleaning is  necessary
   before final clearance testing by TEM.
   The PCM analyses are  relatively inex-
   pensive and can be performed quickly.
3. & criterion should be established to de-
   fine an acceptable asbestos fiber con-
   centration in  building areas after asbes-
   tos abatement, but not until a standard-
   ized TEM protocol and an aggressive
   sampling procedure have been devel-
   oped and validated. Once developed,
   these methods should be required for
   all postabatement assessments.
4. Research should continue in the areas
   of asbestos  measurement,  sampling,
   hazard assessment, and abatement
   control technology  so that asbestos
   hazards in buildings can be effectively
   reduced.  One important research ave-
   nue  should  be the development of
   quicker, less expensive methods for
   monitoring the atmosphere in buildings
   after asbestos  abatement.
                                    8

-------


10











1









1
\ 1 I I 1 I I 1 I 1 1 1 1 1
A D
A n *
- D n
A
I A n
DM D
& o fl-
A
" O
x
B D
J A OD
i 8 S*** *
i • D n
A D u nO
& B O °O
& 0 °
— $ O D O
~ O A
Q O
A
O
A
D
O
*
*
i i i i i i 1 1 1 i iiii
n i| i ii
PCM Method /
7400 /
Jj
V 7
Dv


*
*


5*







Legend
Chrysotile Fiber
Chrysotile Bundle
Chrysotile Matrix
Chrysotile Cluster
Amphibole Fiber
l\\ III
1 i i i i
/
-
—




~

-



—
-

-



—


1 1 1 1 1
          0.01
                               0.1                     1

                              Structure Diameter, micrometers
                                   10
5.  Falgout, D. Environmental Release of
   Asbestos  From Commercial Product
   Shaping. Engineering-Science, Fairfax,
   Virginia. EPA/600/S2-85/044. August
   1985.
6.  Chatfield,  E.J. Measurement of As-
   bestos Fibre Concentrations in Ambi-
   ent Atmospheres. Study No. 10, On-
   tario Research Foundation.  1983.
7.  PEDCO Environmental, Inc.  Inventory
   of Friable Asbestos-Containing Mater-
   ials in Columbus East High School with
   Recommendations for Corrective Ac-
   tion. Final Report, Volume I. January
   1984.
8.  Association of the Wall/Ceiling  Indus-
   tries International, Inc. Guide Specifi-
   cations for the Abatement of Abestos
   Release From Spray-or-Trowel-Applied
   Materials In Buildings and Other Struc-
   tures. The Foundation of the Wall and
   Ceiling  Industry,  Washington,  D.C.
   December 1981.
9.  National  Institute  for  Occupational
   Safety and Health. Asbestos Fibers in
   Air. NIOSH Method No. P&CAM 239.
   NIOSH Manual of Analytical Methods,
   Second Ed., Vol. 1. U.S. Department of
   Health, Education, and Welfare, Cincin-
   nati, Ohio. April 1977.
10. Yamate,  G., S.C. Agarwal,  and R.D.
    Gibbons. Methodology for the Mea-
    surement of Airborne Asbestos by
    Electron Microscopy (Draft). Prepared
    by NT Research Institute for the Of-
    fice of Research and Development,
    U.S. Environmental Protection Agen-
    cy, Research Triangle Park, North Car-
    olina. July 1984.
11. Mosteller, F., and R.E.K. Rourke. Sturdy
    Statistics: Nonparametrics and Order
    Statistics, Addison Wesley, Reading,
    Massachusetts, 1973.
  The full report was submitted in fulfill-
ment of Contract No. 68-03-3197 by PEI
Associates, Inc. under the sponsorship of
the U.S. Environmental Protection Agency.
 Figure 5.    Results of JEM analysis under aggressive Conditions. Plot of fiber length and
            diameter for an aggressive postabatement air sample in Room M112. Total asbestos
            structdres/cc of air = 1.112.
References

1.  U.S. Environmental Protection Agency.
   Asbestos-Containing  Materials  in
   School Buildings: A Guidance Docu-
   ment,  Part  1. Office of Toxic Sub-
   stances,  Washington,  D.C.  20460.
   March 1979.
2.  Sawyer, R.N., and D.M. Spooner. As-
   bestos-Containing Materials in School
   Buildings: A Guidance Document, Part
   2. Office of Toxic Substances,  U.S. En-
   vironmental Protection Agency, Wash-
   ington, D.C. 20460. March 1979.
3. U.S. Environmental Protection Agency.
   Guidance  for Controlling Friable As-
   bestos-Containing Materials in Build-
   ings. Office of Toxic Substances, Wash-
   ington, D.C. EPA 560/5-83-002. March
   1983.
4. U.S. Environmental Protection Agency.
   Guidance  for  Controlling Asbestos-
   Containing Materials in Buildings. EPA
   560/5-85-024. June 1985.

-------
Mark A. Karaffa, Robert S. Amick, and Ann Crone are with PEI Associates, Inc..
  Cincinnati. OH 45246-0100; the EPA author Thomas J. Powers (also the EPA
  Project Officer, see below) is with the Water Engineering Research Laboratory,
  Cincinnati, OH 45268.
The complete report, entitled "Assessment of Assay Methods for Evaluating
  Asbestos Abatement Technology,"  {Order No.  PB 86-194 446/AS; Cost:
  $11.95, subject to change) will be available only from:
       National Technical Information Service
       5285 Port Royal Road
       Springfield, MA 22161
       Telephone: 703-487-4650
The EPA Project Officer can be contacted at:
       Water Engineering Research Laboratory
       U.S. Environmental Protection Agency
       Cincinnati, OH 45268
                               10

-------

-------
  O  22
  oo   <
    co wo   en
    Otna
      30 M
o.

o
CK

o
   w
   HI
 O


 >
 o
 w
2
n
                                                                           CD  <

                                                                           3  <
                                                                           5  (
                                                                           o


                                                                           I
                                                                           5'
                                                                        Da
                                                                         il
                                                                         0) «
                                                                         - o

                                                                         O3
                                                                         I


                                                                         at
                                                                         to
                                                                         o>
                                                                         oo
                                                             cb

                                                            'a*

                                                            '-Z
                                                            
                                                            co

-------