United States
                     Environmental Protection
                     Agency
Hazardous Waste Engineering
Research Laboratory
Cincinnati OH 45268
                     Research and Development
EPA/600/S2-87/023 June 1987
&EPA           Project  Summary

                     The  Block Displacement
                     Method  Field
                     Demonstration  and
                     Specifications

                     Thomas P. Brunsing
                      The Block Displacement technique
                     has  been  developed  as  a  remedial
                     action method for isolating large tracks
                     of ground contaminated by hazardous
                     waste. The technique places a low
                     permeability barrier around and under
                     a large block of contaminated earth.
                      The Block Displacement process is
                     composed of separate bottom barrier
                     and  perimeter barrier construction
                     processes.  The  bottom  barrier con-
                     struction is accomplished by propagat-
                     ing horizontal separations from a series
                     of injection wells.  A soil-bentonite
                     slurry is pumped into these wells at low
                     pressure, opening the separation and
                     forming  a barrier. In the  process the
                     ground  is displaced upward by an
                     amount corresponding to the thickness
                     of the final barrier placed. The perime-
                     ter barrier is  constructed by one of
                     various means including slurry wall, jet
                     grouting, or drill notch and blast. The
                     perimeter barrier is constructed prior to
                     the bottom if necessary to induce a
                     favorable in-situ stress state.
                      The technique was demonstrated at
                     Whitehouse, FL where a block of earth
                     60 ft in  diameter and 25 ft deep was
                     lifted.   Horizontal  fractures  were
                     extended from seven injection holes to
                     form the bottom barrier. The block was
                     displaced upward as much as 12 in. by
                     the injection of approximately 2,000 ft3
                     of bentonite slurry.  Upward displace-
                     ment was monitored by standard sur-
                     vey techniques during the lifting pro-
                     cess.   After  displacement  was
                     completed, a topographic survey was
                     conducted  and  the quality of the
                     bottom  barrier was  assessed by core
                     drilling.
  This Project Summary was devel-
oped  by EPA's Hazardous Waste
Engineering Research Labaoratory,
Cincinnati, OH, to announce key find-
ings of the research project that is fully
documented in a separate report of the
same title (see Project Report ordering
information at back).

Introduction
  Block Displacement is a method for
vertically lifting a large  mass  of earth.
The technique produces a fixed under-
ground physical  barrier around and
beneath the earth mass. The barrier is
formed by pumping slurry, composed of
a soil bentonite and water mixture, into
a series of notched injection holes. The
resulting barrier completely isolates the
earth mass.
  The  process is illustrated in Figure  1
for isolating a chemical  waste site. In-
ground pollution is contained by inhib-
iting ground-water migration through the
contaminated zone. The barrier material
should be compatible with in situ soil and
ground-water chemistry.
  A bottom barrier is  formed  when
lenticular  separations extending  from
horizontal notches at the base of injec-
tion holes coalesce into a larger sepa-
ration beneath the ground being isolated.
  Continued pumping of slurry  under
pressure produces a large uplift force
against the bottom  of  the block and
results in  vertical displacement propor-
tional to the volume of slurry pumped.
  A perimeter barrier is constructed with
the bottom barrier either  prior to, during,
or following bottom barrier construction.
The perimeter barrier can be constructed
including  slurry wall, vibrating beam.

-------
Groundwater Level
Lowered
                                                                  Barrier
     Positive Seal Through
     Injected Bentonite
     Mixture

Figure  1.    Block displacement barrier in place.
dynamic fracturing, or jet groutingtech-
niques.  If constructed prior  to  bottom
separation, the perimeter barrier can be
used to enhance the horizontal stress
field for the purpose of maintaining the
horizontal orientation of the propagating
bottom separations. A perimeter separa-
tion would first be constructed and then
surcharged  to increase  the  horizontal
stress field in the formation. A surcharge
is additional pressure transmitted to the
fluid slurry in the perimeter separation
either by  raising the slurry  fluid  level
above ground level  or by placing a seal
in the perimeter separation and pressur-
izing the slurry below the seal.
  The Block  Displacement  method can
be  used to increase the width of  an
initially  thin  perimeter barrier such as
might be constructed by vibrating beam,
dynamic  fracturing, or jet  grouting
techniques. To increase perimeter width
by  means of the  block lift, the thin
perimeter must be constructed on a slight
angle off  vertical prior to a substantial
portion  of the lift. The slight angle  off
vertical  tapers inward toward the  block
center. Upward displacement of the block
resulting from injection along the bottom
barrier  will  then increase  the initial
thickness of the perimeter separation.
  Construction  of  the  bottom  barrier
proceeds in four phases:
                                                     Bottom Barrier
 1.  Formation of notches at the base
     of the injection holes
 2.  Initial  bottom separation  of  the
     notched holes
 3.  Propagation of the local  separa-
     tions at each injection point coa-
     lescing into a single larger bottom
     separation
 4.  Generation of a complete bottom
     barrier by controlled  vertical dis-
     placement of the earth mass using
     low pressure slurry injection into
     the horizontal separation.
Each  of these phases is carried out
through control and monitoring of slurry
pressure, slurry flow rate, total volume
injected, and slurry composition. Defor-
mation and vertical displacement of the
isolated soil  is also monitored.
  The  notching  operation (Phase 1)
requires a high-pressure rotating jet at
the base of the injection hole. The jetting
slurry  is designed to optimize  notch
erosion, to  remove cuttings, and to
minimize leak-off  into  the  soil. A
mechanical notching tool can be used in
lieu of  the  jet notching  tool,  but the
maximum notch diameter achievable will
be reduced. A large notch diameter is
desired to  reduce fracture  initiation
pressure and to reduce the tendency for
                                        propagating separations to turn upward
                                        due to unfavorable in situ stress condi-
                                        tions.
                                          The initiation  of bottom  separation
                                        (Phase 2} requires a slurry pressure, P0,
                                        at the separation defined by.

                                                     Po = prgh + AP


                                        where p,  = the average earth mass den-
                                                   sity of the soil overlaying the
                                                   notching operation

                                               g  = the gravitation constant

                                              AP  = the pressure in excess of the
                                                   overburden

                                               h  = the depth   of the bottom
                                                   separation
                                                               The pressure in excess of overburden,
                                                               AP, is a function of soil properties, notch
                                                               diameter, slurry properties and the speed
                                                               of  the  operation. The  strength of  a
                                                               material  being  fractured  is classically
                                                               measured by its fracture toughness. The
                                                               pressure  required to initiate propagation
                                                               is  the  pressure  required to  open  a
                                                               sufficiently  wide  gap  at the tip of  the
                                                               notch to allow the slurry to flow into the
                                                               separation.  The gap width is dependent
                                                               on the  gel  strength  of the slurry. The
                                                               tendency for the  slurry  to leak off into
                                                               the soil and form filter  cake  at the tip
                                                               of the notch complicates this process and
                                                               increases the  required  initiation pres-
                                                               sure.
                                                                 Separation  coalescence (Phase 3]
                                                               occurs by adding slurry volume and by
                                                               gradually increasing the gel strength and
                                                               viscosity  of the slurry. Slurry  pressure
                                                               required  to propagate  the horizontal
                                                               separation  will decrease  during this
                                                               phase due  to  the increased  area ovet
                                                               which it  is acting. The  viscosity of the
                                                               slurry serves to limit flow in one specific
                                                               direction, thereby avoiding undesirable
                                                               channeling of slurry material. The higher
                                                               viscosity increases  pressure  drop al
                                                               distances  from  the  injection holes,
                                                               reducing  the  pressure available foi
                                                               fracturing. This pressure/distance rela-
                                                               tionship  causes the separations tc
                                                               maintain  a generally circular shape in the
                                                               horizontal plane.
                                                                 Vertical displacement (Phase 4) utlizes
                                                               the maximum capacity of the pumping
                                                               equipment  to  inject a slurry with higr
                                                               solids content to form the final barrier
                                                               When the  perimeter  barrier separatior
                                                               is  constructed prior  to displacing the

-------
ground, the required injection pressure
is dependent on the overburden weight,
system geometry, shear resistance in the
perimeter and slurry pressure drop
across the bottom separation.
  The  final  thickness of the  bottom
barrier can be controlled to any dimen-
sion, from a few inches to several feet.
The desired  thickness  depends on the
isolation required by the structure or soil
mass being isolated.

Field Demonstration

Site Description
  A demonstration of the Block Displace-
ment technique was conducted at a site
adjacent to the Whitehouse Oil pits  in
Whitehouse,  FL  The Whitehouse site
was selected from a list of 114 top priority
EPA superfund sites.
  The  site was  flat and composed  of
marine sediments of silty sand in excess
of 100 ft overlaying limestone bedrock.
The silty sand appeared to be sufficiently
stratified to be compatible with  Block
Displacement. Ground-water level in the
area varies from 2 to 5 ft, and local drillers
indicated  that a thick hardpan  layer
existed  at a depth of approximately 20
ft.                          •
  Three exploratory holes were drilled
and  continuously  sampled. The soil
profile was categorized, and the standard
penetration resistance  was recorded in
all holes.  Hardpan was encountered in
all three  holes at  approximately 10-ft
depth and continued to between 20 and
25 ft underlaid by unconsolidated brown
sand. The contact between hardpan and
brown sand below was a gradual tran-
sition of interbedded layers and lenses
of the two soils.
  The transition zone between  hardpan
and underlying brown sand appeared to
be a suitable medium for inducing bottom
fracture. A block  diameter of 60 ft and
depth of 23 ft were selected based on
this geology.

Construction
  The  field operation involved  three
distinct operations:
 • An explosive blast in three adjacent
   test  holes  to  determine  perimeter
   fracture performance

 • Preparation of the block by drilling and
   slotting 32 perimeter  holes, and
   drilling and casing seven slurry injec-
   tion holes
• Fracturing both the bottom and the
   perimenter, and lifting the block.

Perimeter Test Blast
  Before commencing with  the  block
perimeter and injection hole drilling,
three test holes were drilled to a depth
of 27 ft at a 14 degree angle off vertical.
The three holes were of 6-in. diameter
and spaced at 3-ft and 6-ft intervals along
a straight line. They were drilled  in an
area apart from the proposed  test block.
This drilling was done to gain experience
in angled drilling with the mobile rig, to
experiment with hole slotting  tools, and
to use these holes to conduct an exper-
imental blast for joining the slot tips. The
hole spacing and  explosive charge load
would determine the ultimate  number of
block perimeter holes required. Twenty-
six  feet  of  50-grain/ft Prima-cord™*
explosive were placed to within 1 ft of
the top  of each hole,  and 10 ft  were
overlapped at  the bottom  to  give this
portion of each hole a 100-grain/ft load.
The cord was  capped at the  bottom  of
each hole using a special cap insertion
tool. Post-blast inspection showed that
the fractures  between the 3-ft spaced
holes clearly joined; and that the 6-ft
spaced holes had their slots extended far
enough to join but not in a straight line,
thus making verification difficult.

Injection Hole Drilling
  Seven 23-ft  deep injection holes were
to be cased with  6-in. PVC  pipe, and
hence required a larger bit for drilling.
An 8-in. bit was fabricated, and with the
exception of  encountering  occasional
tree roots, the drilling went  smoothly.
PVC pipe in 25-ft lengths was installed
i n each hole so that the last 2 ft protruded
above ground.  Each hole was also bottom
grouted using Portland cement to ensure
a reasonable casing seaJ. Two cubic feet
of grout  were placed in each hole
displacing the drilling mud.   The  PVC
casing was then pressed through the wet
grout using  the drill rig downhaul. The
cement was later drilled through to earth,
and the  casings  were  temporarily
capped.

Perimeter Hole Drilling
  The experience gained during test hole
drilling  proved  very helpful for the
perimeter hole drilling. At each of the 32
hole locations,  the drill rig was  positioned
•Mention of trade names or comercial products does
 not constitute endorsement or recommendation for
 use.
on the block perimeter and tilted to the
desired 14 degree angle by extending the
appropriate hydraulic stabilizer jack
inside the block. Subsequent measure-
ment indicated that the  off vertical
anglevaried from  12 to 14  degrees
around the block. The 6-in. drill bit was
used, and  five  to  seven  holes  were
completed each day. A fresh batch of 10
percent bentonite by weight m ud was left
in each  hole  to ensure  against hole
collapse


Perimeter Slotting
  For the perimeter slotting operation, a
pile driver was brought to the site and
two new and different slotting tools.were
fabricated. Because  of the large surface
area and general geometry of the disc
slotter, the impact force required to drive
it was so great that the pipe bent severely
before the tool  reached the bottom of the
first  hole. A second  tool with a reduced
area, diamond-shaped slotter was fab-
ricated using a single length pipe. The
thickness of the slot blades was also
reduced by half  for  this tool. Using the
modified diamond slotter, the pile driver
heads  were angled  at 14 degrees  off
vertical. The pile driver delivered 700- to
1,400-ft-lb  blows to  the  slotting tool,
typically driving the  tool 6 in./blpw.  All
32 perimeter holes were slotted in just
over 3 days.
Perimeter Fracture
  In preparation for the perimeter frac-
ture blasting, a 5-ft long, 18-in. diameter
"sona tube" (tubular heavy gauge card-
board cement form) was placed on-end
over each perimeter hole, as shown in
Figure 2. Each tube was then filled with
a very heavy barite (specific gravity of
>2.0) mud, which acted as a surcharge
to prevent mud loss during the blast, and
to force the mud in each perimeter hole
out into the separation created  by  the
blast.
  With this accomplished, the explosive
charges were loaded into each hole and
fired.  A,detectable perimeter fracture
appeared to run around almost,the entire
circumference of the block at the surface.
A piece of spring steel was used to probe
the fracture to verify hole connection.
This device confirmed that most perime-
ter  holes  did join  down to a depth of
several  feet, beyond which the  spring
steel could not penetrate the fracture.
The blast-induced  fracture  appeared
continuous.

-------
Figure 2.   Surcharged perimeter holes ready for explosive blast.
Bottom Notching and Fracture
  The  bottom  notching  technique
employed  a high-pressure,  slurry  jet
oriented horizontally and rotated at the
bottom of the  hole to erode  a pancake
shaped notch.  Initially a  2-percent
bentonite slurry  was jetted in a slurry
medium in  all seven  injection holes
yielding notches 2 ft in diameter. During
the first attempt to create a fracture, high
pressure was required  to induce slurry
flow. This  indicated the need for larger
notches. Renotching of  the holes first to
a 4-ft  diameter  and finally  to  a  6-ft
diameter was required to create  the
bottom fracture.

Block Lift
  A  mud  distribution  manifold was
fabricated  for  both fracturing and  lift
operations. A  3-in.  diameter inlet port
was connected to the outlet of the mud
pump,  and each valved 2-in.  outlet port
was  connected  to an injection hole
casing. Each  casing had a pressure
gauge installed as a means of  monitoring
injection pressure  and  as  an  aid in
detecting connections with other holes.
Although the  manifold  permitted mud
injection into any number of the seven
holes simultaneously, the pumping was
usually confined to one of three holes
at a  time. The hole selected to receive
the mud was  determined by measure-
ments of lift at certain points on the block
using the engineer's level set up outside
the block. When lift was observed at an
injection  point,  the mud  was  then
directed to a different injection hole in
an attempt to lift the entire block surface
as evenly as possible. This process was
continued until each  injection hole was
lifted between  1/32 and 1/16 in. during
mud injection.  Separation coalescence
between injection holes was observed
after  approximately 500 gal. of  slurry
were pumped  into the central injection
hole. Once lift was detected, the injection
slurry was modified by adding local soil
to add weight and reduce cost. The added
material  was  surface  excavated, silty
sand that acted as an aggregate  in the
bentonite and water matrix. After several
days  of  pumping, primarily  into the
central injection hole, some lift had been
detected nearly everywhere.

Summary of Test Results
  Displacement of the  block  was mon-
itored by recording the change in eleva-
tion of  16 fixed rods.  Elevations were
read through a surveyor's level located
50 ft outside   of the block  perimeter.
Additional survey poi nts beyond the block
boundary  were  monitored during  a
portion of the lift operation to verify that
no lift  was occurring  outside  of  the
perimeter.  Survey points 0  through  6
correspond to rods located approximately
3 ft from the injection holes. The remain-
ing nine survey points, 3p through 30p,
correspond to rods located just inside the
perimeter. These survey point numbers
correspond to the closest hole  numbered
progressively from  1 to 32 in a counter-
clockwise direction around the perime-
ter.
  A total of approximately 2,000 ft3  of
bentonite slurry was injected during the
block lift  operation. A daily tabulation of
slurry injected during the lift operation
was maintained by counting the number
of 1 -1 /2 yd3 batches of slurry mixed and
verifying this count with a daily bag count
of the bentonite used.
  Data from surface topographic surveys
and from accumulated daily lift records
were combined to  give the two profiles
of the final block position shown in Figure
3. In  total, the block was  displaced
upward in excess of 12 in. at its highest
point and tilted approximately one degree
from  horizontal.   A  crescent shaped
portion of the block outside of injection
hole No. 3 was sheared free of the lifting
block and did not move appreciably. The
entire remaining portion of the perimeter
lagged behind the inner  portion  of the
block, lifting only 3 to 6 in.
  Tap roots as large as 24 in. in diameter
were found at approximate 6-ft intervals
extending from roughly 5 ft below the
ground surface to the upper boundary of
the hardpan layer. In addition, perimeter
fractures filled  with gelled  slurry
extended down only a few feet  before
becoming  indistinguishable hairline
fractures.
  Thin-walled tube soil samples were
taken 4  weeks after stopping  slurry
pumping  to determine the integrity of the
bottom seal. Obtaining undisturbed soil
samples  of  the  soft  slurry  material
bounded  by hardpan  on top and uncon-
solidated sand beneath was difficult. In
eight attempts, three acceptable samples
were obtained.  Sample No. 8 shown in
Figure 4 indicated that a well defined
boundary of separation between injected
clay  slurry and the overlapping  native
sand had formed.

Conclusions
  The Block  Displacement demonstra-
tion  provided three  distinct technical
conclusions:
• The bottom barrier construction com-
   ponent of  the process  is viable and
   has been demonstrated.

-------
              Non-Lifting
              Section of
              Block \

       i           i 7»W
            Ground
            Water
            Elevation
      24ft
                                       -Soft-
                                   Injection Holes
                               Displaced
Block
                    12 in.
                      jn _]      L_ Bottom Slurry Barrier
                                   Section A-A'
                                                                 Perimeter
                                                        "— 3 w.
idated material. Slurry mix, pumping and
distributing equipment  demonstrated
that the slurry designs used  can be
adequately mixed and placed in the field.
Lift monitoring using standard  survey
equipment was quite adequate for deter-
mining performance and as feedback for
correcting  slurry injection during the
lifting operation.  Adequate correlation
was obtained  between  slurry injected
and ground volume displaced.
  The full report  was  submitted  in
fulfillment of Contract No. 68-03-3113,
Task 37-2 by JRB Associates under the
sponsorship of the  U.S.  Environmental
Protection Agency.
                   5 in. —J


Figure 3.   Final block displacement.
                                             in.
                                    Section B-B'
 • The drill,  slot and blast  perimeter
   barrier construction technique applied
   as part of the total isolation process
   was unsatisfactory and should not be
   considered for  Block Displacement
   application.

 • Construction materials,  equipment
   and procedures for implementing the
   Block  Displacement  process  were
   evaluated  and refined sufficiently to
   be considered for field  application
   under geologic conditions similar to
   those at the demonstration site.

  The bottom barrier construction tech-
nique, which required repeated modifi-
cation to notching and sealing  tech-
niques,  ultimately performed quite
consistently.  Drilling, notching, separa-
tion propagation, and block lift were all
adequately demonstrated. Surface dis-
placements, core samples and lift volume
versus slurry volume correlations all
support  this conclusion. Subsequent
                                        coring  data,  lift  monitoring  data  and
                                        independently derived conclusions from
                                        interpretation of ground penetrating
                                        radar records indicate at least 80 percent
                                        of the  underlying area defined by the
                                        design  perimeter was covered by bottom
                                        barrier material.
                                          The  drill, slot  and blast  perimeter
                                        separation technique did  not  produce a
                                        sufficiently smooth continuous fracture
                                        to allow the perimeter surfaces to fully
                                        override each other during the displace-
                                        ment  process.  Performance  of this
                                        perimeter  separation  technique in the
                                        more consolidated hardpan is  uncertain,
                                        as post lift perimeter mapping could not
                                        extend  down into the hardpan region.
                                        Alternate,  more  direct perimeter con-
                                        struction techniques such as slurry wall
                                        or vibrating beam construction would be
                                        more  appropriate in unconsolidated
                                        ground.
                                          Slurry jetting  in  a compressed  air
                                        stabilizing  medium proved adequate as
                                        a bottom notching method in  unconsol-

-------
                             Bentonite
                             Slurry
                             Barrier
                          Bentonite
                          Slurry
                          Barrier
Figure 4.   Test core from hole No. 8.
  Thomas P. Brunsing is with Foster-Miller, Inc., Waltham, MA 02254.
  Walter E. Grube, Jr. is the EPA Project Officer (see below).
  The complete report,  entitled "The Block  Displacement Method Field
    Demonstration and Specifications." (Order No.  PB 87-170 338/AS; Cost:
    $18.95, subject to change) will be available only from:
          National Technical Information Service
          5285 Port Royal Road
          Springfield, VA 22161
          Telephone: 703-487-4650
  The EPA Project Officer can be contacted at:
          Hazardous Waste Engineering Research Laboratory
          U.S. Environmental Protection Agency
          Cincinnati,  OH 45268

-------
United States                        Onter for Environmental Research                                          BULK RATE
Environmental Protection               Information                                                        POSTAGE & FEES P/
Agency                            Cincinnati OH 45268                                                        EPA
                                                                                                     PERMIT No G-35


Official Business
Penalty for Private Use $300


EPA/600/S2-87/023
      OC00329    PS
      U S                    ™ON  *Gf«CY

-------