United States
                    Environmental Protection
                    Agency
Hazardous Waste Engineering
Research Laboratory
Cincinnati OH 45268
                    Research and Development
EPA/600/S2-87/063 Nov. 1987
&ERA         Project Summary
                     Investigation  of Slurry Cutoff Wall
                     Design and  Construction Methods
                    for Containing  Hazardous Wastes
                    Richard M. McCandless and Andrew Bodocsi
                      Specific technical design standards
                    for soil-bentonite slurry trench cutoff
                    walls used to isolate hazardous wastes
                    have not been established. A review of
                    current  design  and construction
                    methods was performed for summariz-
                    ing current engineering practice, identi-
                    fying areas of  technical debate, and
                    initiating necessary research to promote
                    the development of rational standards.
                    The  review of  current  methods was
                    followed by laboratory studies  using
                    specialized test equipment to  study
                    model cutoff walls.
                      An instrumented slurry test column
                    was developed and used to investigate
                    the  hydraulic characteristics and im-
                    portance of bentonite  slurry  seals
                    formed on the walls of the cutoff trench
                    during  construction. Testing involved
                    the penetration of a 5% bentonite: water
                    slurry into  two different sands, the
                    formation of a different type of slurry
                    seal  in each case, and the measurement
                    of their hydraulic conductivities  based
                    upon the time-rate of flow and the
                    measurement of internal pore pressure
                    conditions.  The effectiveness of dif-
                    ferent slurry seals varied greatly de-
                    pending upon the degree of filtration of
                    hydrated bentonite particles during
                    slurry penetration into granular soils. In
                    all cases, however, the effectiveness of
                    the seals alone (ignoring the contribution
                    of the soil-bentonite backfill) was very
                    low, suggesting that they cannot be
                    relied upon to offset the effects of latent
                    defects  in the  backfill, and that the
                    current  practice of disregarding the
                    slurry seal in cutoff wall design should
                    not be changed.
  Laboratory testing also involved an
instrumented slurry wall tank capable
of accommodating 508 mm (20 inches)
diameter, 101.6 mm (4 inches) thick
model cutoff walls. The tank was used
to evaluate the effects of overburden
pressure (vertical consolidation) and
hydraulic gradient (horizontal consolida-
tion), and to evaluate the potential for
self-remediation  of hydraulic defects
("windows" through the barrier) via in
situ consolidation of the soil-bentonite
backfill. Various models were permeated
with water under varying hydraulic
gradients and vertical surcharge pres-
sures. The average equilibrium hydraulic
conductivity of the models was mea-
sured  under each set of conditions.
Results demonstrated that both over-
burden pressure and hydraulic gradient
have significant and comparable effects
on the average conductivity of the wall.
Moreover, water content, unit weight,
and vane shear strength data measured
on samples of the soil-bentonite backfill
after the test clearly indicated that ef-
fective overburden stress decreased
with increasing depth in the model,
most likely due to friction between the
backfill and sand in which the model
was constructed.
  Another model wall was intentionally
breached by two slot-like "windows"
representing small pockets of entrapped
bentonite slurry in the backfill immedi-
ately after construction. By incre-
mentally increasing surcharge pressure
it was possible to "heal" the windows
as evidenced by a return to the predeter-
mined baseline hydraulic  conductivity
of the wall. This suggests that in situ

-------
*.,
consolidation of the backfill may help
to  eliminate  some types  of as-built
hydraulic defects or micro-cracks within
the backfill  resulting from long-term
chemical degradation.
  This Protect Summary was developed
by EPA's Hazardous Waste Engineering
Research Laboratory, Cincinnati, OH, to
announce key findings of the research
project that  Is fully documented In a
separate report of the same  title (see
Project Report ordering Information at
back).

Introduction
  Slurry trench  cutoff walls were first
used in  the United States in  the early
1940's.  Since that time,  their use has
become  more widespread and now  in-
cludes application as hydraulic barriers
to control the movement of contaminated
groundwater from hazardous waste dis-
posal  sites.  Specific  technical design
standards for slurry trench  cutoff walls
(also known as soil-bentonite walls) have
not been established. Each application is
unique and requires site-specific engi-
neering  evaluation. Nevertheless,  the
current state-of-the-art involves funda-
mental concepts, performance  criteria,
and methods common to all applications.
The purpose of this project is threefold:
  • to compile  information on current
     design and construction methods
  • to identify specific research needs to
     promote the development of rational
     standards
  • to perform initial research in selected
     areas of need
  The first phase of the project involved
review of published literature  on slurry
wall technology, interviews with owners,
engineering consultants and construction
contractors, and a general  assessment of
methods and research needs. Based upon
these findings, two subsequent research
phases  emphasized laboratory  model
studies of slurry  seals formed on  the
walls of a cutoff trench during  construc-
tion and small  model cutoff  walls  in-
corporating  both  slurry  seals and a
standard soil-bentonite backfill.
  Specific  objectives of the laboratory
studies were to determine or evaluate:
  • the depth of penetration of slurry or
     filtered slurry into typical granular
     soils
  • the hydraulic conductivity of various
     types of  seals derived  from slurry
     penetration and slurry filtration dur-
     ing penetration into typical granular
     soils
  • the stability of the seals (described
     above) after initial development
  • in situ consolidation and the effect
    of surcharge loading and hydraulic
    gradient on soil-bentonite hydraulic
    conductivity
  • the feasibility of "window" closure
    within a soil-bentonite wall due to
    overburden consolidation pressures.

Current Methods
  The initial phase of this study involved
a survey of current design and construc-
tion methods which form the basis of
present slurry cutoff wall technology. The
survey involved review of published litera-
ture on  the subject,  interviews  with
selected vendors and professional practi-
tioners specializing in slurry wall applica-
tions,  and visits to three  slurry  wall
construction sites, the  report does not
attempt  to quantify the variability in
present methods  but simply documents
the range of philosophy and current prac-
tice in  the areas of Design, Specification,
Construction and QA/QC. The specific
considerations that are least standardized,
and  therefore  most variable,  in  each
subject area are summarized below:

Design        • soil-bentonite mix
                 design
               • method of hydraulic
                 conductivity testing
               • bentonite type
               • bentonite content in
                 the backfill
               • the use of
                 contaminated trench
                 spoils in the backfill

Specification   • performance type or
                 materials and
                 methods type
Construction   • backfill mixing/
                  handling techniques
               • backfill placement
                  method
               • equipment type
               • personnel - level of
                  experience

QA/QC        • verification of trench
                  depth, width and
                  continuity
               • personnel - level of
                  training/experience
               • responsibility -
                  contractor,
                  consultant or owner?
               • frequency and
                  manner of backfill
                  testing
Laboratory Investigations
Procedures

Slurry Seals

  An instrumented  slurry test  column
was developed to study various bentonite
slurry seals formed on the walls of the
cutoff trench during construction. The
system consists  of  an acrylic  column
equipped with probes to measure in situ
pore  pressure after  the formation of a
slurry seal  in different sands.  Spring-
suspended inflow (head) and outflow (tail)
permeant reservoirs were employed tc
achieve constant-head test conditions. A
schematic of the  system  is shown ir
Figure 1. Pore pressures were monitorec
during permeation to produce data on the
depth of the slurry  penetration, the
hydraulic conductivity of the overall seal
and changes in these features as a func
tion of time.
  A clean fine sand identified  herein a;
the "+200 sand" (retained on the no. 2CK
sieve) was  used to study the  surfac<
filtration (filter cake) type of slurry seal ii
the  slurry test  column.  This sand i
predominantly fine,  of roughly uniforn
size (no. 40  to no. 50 sieve size), witl
about 25 percent medium sand by weigh
A clean medium to coarse sand was use
to investigate deep filtration and rheolog
cal blockage seals. The gradation con-
prised roughly 75% medium  sand an
25% coarse sand, with all material bein
retained on the no. 40 sieve ("+40 sand"
  All tests involved slurry seals derive
from the  penetration  of  a standard
percent bentonite: water slurry (weigh
volume basis). Slurry was driven into tr
test sands under controlled pressure (se,
formation pressure) for a standard peric
of five hours. Seals formed in this manni
were then permeated by water undi
variable hydraulic pressures sometime
different than the seal formation pre;
sure. Testing comprised both  saturate
and unsaturated cases to model cone
tions below and above the groundwat
table, respectively.
  In all cases, hydraulic conductivity da
were calculated from several paramete
measured during the test.  These parar
eters included the pressure different!
between any two pore pressure probe
the physical distance between the probe
and the volume flow-rate through tl
sample (discharge per unit time).
  Figure 2 shows typical pore pressu
distributions during steady flow for t
+40  and  +200  sands under rougf
equivalent hydraulic gradients. In ea
case, the data  demonstrate  a  nea

-------
                                                      Vacuum
      Suspension
      System
      Outflow
      Permeant
      Reservoir
     Inflow
     Permeant
     Reservoir
                                                                  Slurry
                                                                 Reservoir
                                                                     Supply
Figure  1.    Schematic of the slurry test column system.
                          Baseline Distributions: +40 Sand & +200 Sand
                                                      20
                                                              24
                                                           28
Figure 2.
                         12       16
                       Column Depth (in.)
Typical baseline (no slurry seal) pore pressure distribution for fine (+200) and
medium to coarse (+40) sands used in this study.
constant rate of head loss through the
sample prior to the introduction of slurry.
After development of a  slurry seal, the
steady-state pore pressure distributions
for the +40 and +200  sands were as
shown in Figure 3a and 3b, respectively.
Data such as these were used to define
the  location, thickness,  and  hydraulic
gradient across the  seals, from which
their hydraulic  conductivities  were
computed.
                             Results

                             Slurry Seals
                              Numerous tests were performed  on
                             both  the  +40 and +200 sands  at seal
                             formation and  perme.ation  pressures
                             ranging from 9.3 kPa (1.35 psi) to 68.95
                             kPa (10.0 psi). Of these, only two tests of
                             the +40 sand and five tests of the +200
                             sand  produced  useable  data. In most
                             other tests the slurry seals were breached
by the combined effects of cracking and
erosion (piping) from beneath. The cause
is believed to be related to minor pressure
fluctuations within the system in response
to temperature changes and/or supply
pressure changes from day to night and
vice-versa. These pressure fluctuations
would cause differential expansion/con-
traction between the acrylic column and
the sand.  Such disturbance would cause
micro-cracks in the seal followed by pro-
gressive  widening  of  the  cracks via
erosion. It was possible, however, to gen-
erate comparative initial permeability data
for the seven tests described above, and
to compute the "breakthrough time" (time
for the first drop of permeant to pass
through the cutoff wall barrier) for the
two types of slurry seals.
  Figure 4 is a schematic of two typical
soil-bentonite  walls,  showing the ex-
pected zone of  slurry penetration  and
seal formation in the +40 and +200 sands.
Deep slurry penetration accompanied by
Theological blockage occurs in the +40
sand, whereas a surface filtration seal is
shown for the +200 sand. In both sche-
matics, the soil-bentonite backfill is as-
sumed to be the same, having a hydraulic
conductivity of 1.0 x  10'7 cm/sec. The
depth  of  slurry  penetration and the
hydraulic conductivity of the seal in each
case  are  based upon  results obtained
using the slurry test column.
  Assuming the same  in-service  head
differential across each barrier and steady
flow according to Darcy's law, it was
determined that the effectiveness of the
wall in the +40 sand based upon a break-
through criterion would be about three
times as much as that of a similar wall
constructed in a deposit of  +200  sand
(93.5 years vs. 31.0 years). Moreover, the
breakthrough times of the two slurry seals
alone (no  soil-bentonite  backfill) was
determined to be on the order  of two
weeks or less.


Procedures

Mode/ Cutoff Walls
  The  slurry wall tank  constructed for
this study accommodates circular cutoff
walls roughly  559  mm  (22  inches) in
height, 102 to 152  mm (4 to 6 inches)
thick, and up to 610 mm (24 inches) in
diameter.  The  tank  is of stainless steel
construction and employs a  pneumatic
bladder system to vertically confine and
consolidate the model wall during per-
meation  in  the  horizontal direction. A
schematic of the system is  shown as
Figure 5.

-------
        12
                        Post Penetration Distribution: +40 Sand
                                                               (at
        11
        /On
7

6



4

3
                              >W
                                               N
                             Top of Sample
           0
Column Depth (in.)
Post Penetration Distribution: +200 Sand (b)


Q .
#-



4-


















\
\
\
\
i







r-^j
Top of






»—«--,
Sample






*—»-^
















                                                                         4
Figure 3.
                           Column Depth (in)

   Typical initial pore pressure distributions after formation of slurry seals in the
   (a) +40 and(b) +200 sands
  The model walls were constructed
between two concentric PVC (polyvinyl
chloride) slip forms representing the walls
of a  circular cutoff trench.  The forms
were positioned in the tank and backfilled
with clean fine sand in 102 mm (4 inch)
lifts creating an  empty 102 mm (4 inch)
wide  annular space between the forms.
This  space was  then  filled with a 5%
bentoniteiwater  slurry (weight:  volume
basis) comprising  the  same bentonite
used  in the soil-bentonite mix. The soil-
bentonite  backfilling  operation varied
slightly for different models but generally
involved raising  both forms  about 102
mm (4 inches),  allowing the bentonite:
water slurry  to penetrate the sand and
form  a surface filtration slurry seal, and
then backfilling with soil-bentonite  using
a pressurized tremie pipe. This general
                                procedure was repeated until the surface
                                of the model wall was level with the
                                surface of the center core of sand (sand
                                encircling the model wall).
                                  After construction,  the model  was
                                readied for testing by  installing a com-
                                bination membrane/hydraulic cutoff over
                                its  surface  and  positioning  concentric
                                load-bearing  plates over each element of
                                the model (core sand, soil-bentonite wall,
                                outer ring of sand). This arrangement
                                allowed for differential loading and  con-
                                solidation of the soil-bentonite wall  rela-
                                tive to the adjacent sand bodies.
                                  The typical testing procedure used in
                                evaluating the  effects  of overburden
                                pressure and gradient involved saturation
                                of the sand elements of the  model, ap-
                                plication of a selected surcharge pressure,
                                consolidation of the soil-bentonite  wall
under the applied surcharge (time esti-
mated from conventional consolidation
tests performed on the backfill material),
application of the design hydraulic head
pressure at both  the top and bottom of
the saturated center core of sand (Figure
5),  and the measurement of hydraulic
head and volumetric inflow at prescribed
time intervals.
  Similar procedures were used  in  the
construction and testing of  the third
model  wall to  evaluate  the  closure of
artificial slot-like windows via surcharge
pressure.  The  slots were intended  to
model macro-defects such  as  small
pockets of entrapped  slurry remaining
after construction of the  wall. Two slots
approximately 7.9 mm (5/16 inch) wide
by  1.6 mm (1/16 inch)  high were  cut
into the third wall after preconsolidation
under  an effective overburden of 41.4
kPa (6.0 psi) as measured at the surface
of the wall. The windows were positioned
180° apart at a depth of about 127 mm (5
inches) below the top of the wall. Both
ends of each slot were covered  with a
fabric-covered  wire  mesh  to prevent
washing the core sand into the slot during
permeation. The test procedure involved
incremental increase of overburden (sur-
charge) pressure until the slots were
effectively closed as evidence by a return
to the predetermined baseline hydraulic
conductivity of the model.

Results

Model Cutoff Walls
  The testing of  model slurry walls in-
volved staged  incrementation  of over-
burden pressure and hydraulic gradient,
followed by sampling and measurement
of unit weight,  vane shear strength and
moisture content as a function of depth
in the model. Three different hydraulic
gradients (i = 21, 42,  83) were applied
under effective overburden pressures of
41.4, 82.7  and  165.5 kPa (6, 12, 24  psi)
as  measured at the surface of the wall.
Figure 6 presents a chronological sum-
mary of the final  equilibrium conduc-
tivities measured for  each set of test
conditions. Initial hydraulic conductivities
are represented by an open triangle and
final equilibrium values by an open circle.
Two incidences of hydrofracture  are in-
dicated by solid triangles.
  Except for test 2(g), the data suggest a
logical trend of decreasing equilibrium
hydraulic conductivity as a function of
either increasing surcharge pressure or
increasing hydraulic gradient. The data
do  not,  however,  reflect the correcl
magnitude of change in hydraulic con-

-------
             +40 Sand Test 7-6
       S/B Backfill
     - 40 "4-36" -f- 40"-

ks = 557 x 10~* cm/sec

          *Sb = 1 0 x W~7 cm/sec
                                           +200 Sand Test 5-7


                                      S/B Backfill
                                                                      A/7
                                                                  Surface
                                                                  Filter Cake.
                                                 0.25" [_ 35.5"[ 025"
                                           ks= 1 68 x 10  cm/sec
                                                      ksh = 1 Ox W7 cm/sec
Figure 4.    Idealized conditions after construction of cutoff walls in the +40 and +200 sands.
       Permeant Reservoir
       (typ)
     V9A
                                             '    Pore Pressure
                                             '        Probe

                                                            1
                                                               V9B
   Dram
           V1
                                                                  V2
                  — — 	 —  —   Air Pressure Line

                  	Permeant Flow Line

Figure 5.    Schematic of the slurry wall tank system
ductivity between successive tests. The
reason is that hydrofracture permanently
changed the properties of the wall, thus
artifically  offsetting groups of  data
measured after hydrofracture from other
groups of data measured before hydro-
fracture.
  After the completion  of test 2(g) re-
ported in Figure 6, the tank was opened
                                  to permit inspection of conditions and
                                  allow for sampling and  testing of  the
                                  backfill. Testing involved measurements
                                  of unit weight, vane shear strength and
                                  water content. Data for these parameters
                                  appear as a function of depth in Figure 1.
                                    After sampling and inspecting of  the
                                  model  a new wall was constructed for
                                  the window closing test. After establishing
a baseline or reference value of hydraulic
conductivity, the two slot windows were
formed at the  locations and depths pre-
viously described. Overburden pressure
was than  gradually increased causing
the apparent hydraulic conductivity of the
model to decrease until the windows had
been effectively closed as evidenced by a
return   to the  measured  baseline
conductivity.

Conclusions for Slurry Seals
  •  For  seals formed on fine sands by
     the surface filtration mechanism: 1)
     the density of a seal is proportional
     to the density of the sand in which
     the  seal  forms and proportional to
     the prevailing hydraulic head  under
     which the seal forms, 2) the hydraulic
     conductivity  of a seal is inversely
     proportional  to the  prevailing  hy-
     draulic head under  which the seal
     forms  and inversely proportional to
     the density of the sand in which the
     seal  forms, and 3) the thickness of
     the seal  is a function of formation
     time only.
  •  Based upon the unknown frequency
     of chemically induced or construc-
     tion-related "windows" in a typical
     soil-bentonite cutoff wall, it appears
    that  the current practice of design
    on the basis  of the  permeability of
    the  soil-bentonite  backfill alone
    should not be changed.

Conclusions for Model
Cutoff Walls
  •  The  average hydraulic conductivity
     of model cutoff walls was observed
     to decrease  both as  a function of
     increased overburden  pressure
     (vertical   consolidation), and  in-
     creased hydraulic pressure (horizontal
     consolidation  due  to  hydraulic
     gradient), as well as their combined
     effect.
  •  Hydrofracture,  or rupture of the
     cutoff  wall may be  induced in  the
     subsurface at locations where the
     hydraulic  driving  pressure exceeds
     the  effective vertical overburden
     pressure. Although the applied sur-
     charge pressure at the top of the
     wall  in these cases was higher than
     the hydraulic pressure, it was not
     effective  over the full depth of the
     wall  resulting in general hydrofrac-
    ture  (presumably near the base of
    the wall).
  •  Density,  water content  and  vane
    shear  strength data measured on
    samples  from a  cutoff wall  after

-------

    I
                                                                                      testing all confirm the dissipation of
                                                                                      vertical overburden pressure  with
                                                                                      increasing depth in the model.
                                                                                    • The success of the window closing
                                                                                      test suggests that the effective over-
                                                                                      burden pressure  in  the  wall  may
                                                                                      serve  to close residual slurry  win-
                                                                                      dows and may even close a multitude
                                                                                      of micro shrinkage cracks that may
                                                                                      develop in the backfill over the life of
                                                                                      the  barrier due to the  effects of
                                                                                      chemical leachates.
                                                                                    The full  report was  submitted  in ful-
                                                                                  fillment of contract number 68-03-3210,
                                                                                  07 by the University of Cincinnati under
                                                                                  sponsorship of the U.S. Environmental
                                                                                  Protection Agency.
       10
                     30        60       90       120

                                    Time [Days]
                                                          150
                                                                   180
                     V         Initial K
                     Q         Equilibrium K

                     1         Breakthrough

                     •         Ruptured Surcharge Bladder

                     Q        Projected Equilibrium K
Figure 6.    Chronology and results of hydraulic conductivity tests.

-------
Depth
(in.)
—
1
/
/
/

4 •


IK
?n

Dry Unit Weight
fib/ft3)
114 116 118











/




-K.

^'
'*•'•'
4-


X
X
'**•
*•



f-
/
/




L7*
X





*'
•



Wafer Content (%l
14 16 18 20









~\\
V
\





\
y
*•





•









Figure 7.   Results of tests on soil-bentonite backfill after completion of hydraulic conductivity
           tests.
   Richard M.  McCandless and Andrew Bodocsi  are  with the University  of
     Cincinnati. Cincinnati, OH 45221.
   Naomi P. Barkley is the EPA Project Officer (see below).
   The complete report, entitled  "Investigation of Slurry Cutoff Wall Design and
     Construction Methods for Containing Hazardous Wastes," (Order No. PB 87-
     229 688/AS; Cost: $24.95, subject to change) will be available only from:
           National Technical Information Service
           5285 Port Royal Road
           Springfield, VA22161
           Telephone: 703-487-4650
   The EPA Project Officer can be contacted at:
           Hazardous Waste Engineering Research Laboratory
           U.S. Environmental Protection Agency
           Cincinnati. OH 45268

-------
                                                                                                                  •C  W .U 1.
                                                                                                         62SOIC9 t
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
     BULK RATE
POSTAGE & FEES PA
        EPA
   PERMIT No G-35
Official Business
Penalty for Private Use $300

EPA/600/S2-87/063

-------