United States
                  Environmental Protection
                  Agency
Water Engineering
Research Laboratory
Cincinnati, OH 45268
                  Research and Development
EPA/600/S2-88/001 Sept. 1988
v°/EPA         Project  Summary
                   Survey  and Evaluation  of  Fine
                   Bubble  Dome and  Disc  Diffuser
                   Aeration Systems  in North
                   America
                   Daniel H. Houck
                     A study of 19 North American
                  municipal activated sludge plants
                  equipped with  either ceramic fine
                  bubble dome or  disc  diffuser
                  aeration systems was carried out to
                  better define  the  oxygen  transfer
                  performance  and operation and
                  maintenance (O&M) requirements of
                  these systems  and  the proper
                  approaches to their design. Two of
                  the plants were located In metro-
                  politan Toronto,  Ontario.  The re-
                  maining  17 were located in the
                  United States. The plants  were
                  selected  on the bases  of size and
                  age of the system, location, and
                  quality of available  data  from
                  installation lists  provided by the
                  principal manufacturers of dome and
                  disc  diffuser  equipment.  All treat
                  predominantly domestic  wastes,
                  though  some have  significant
                  industrial flows as well.
                     Data on process design, influent
                  and  effluent  wastewater char-
                  acteristics, aeration power and air
                  flow,  and O&M experiences were
                  requested from each plant. These
                  were  supplemented as needed by
                  on-site investigations  and Inter-
                  views of plant personnel.
                     The results of this work indicate
                  that, although the North American
                  experience  has not  been as
                  uniformly satisfactory  as that  of
                  overseas  users, ceramic fine bubble
                  aeration technology  can  be
                  successfully  implemented  here.
                  Those plants that have avoided major
 design  flaws  and are  operated
 conscientiously are performing quite
 well. Most of the problems encoun-
 tered would require little  money or
 time to  correct. Better training of
 plant operators and improved design
 practices are urgently needed.
    This  Project  Summary was
 developed by EPA's Water Engineering
 Research Laboratory. Cincinnati,  OH,
 to  announce  key findings of  the
 research project  that  is fully
 documented in a separate  report of
 trie same title (see Project Report
 ordering information at back).

 Introduction
    Interest remains  high in  the
 wastewater treatment industry in reduc-
 ing power consumption and costs of
 energy-intensive treatment  processes.
 Aeration for secondary and tertiary ac-
 tivated sludge treatment, often account-
 ing for 50% or more of total plant energy
 consumption, continues to be a primary
 focus in  the effort to reduce energy
 costs. Consequently, expanded  use of
-reportedly more efficient  aeration equip-
 ment has been experienced in North
 American  plants in recent years. It was
 decided that enough new ceramic dome
 and disc fine bubble  aeration systems
 had been installed and operated for  a
 sufficient period by late  1982 to justify
 undertaking a  domestic survey  and
 evaluation of the technology.
    The study's primary objectives were
 to assess the  oxygen transfer per-
 formance  and O&M history  of ceramic

-------
dome and disc diffused aeration systems
in  North America and  to enumerate and
discuss the  principal design  factors
affecting that performance.  To  allow
comparison with an earlier foreign study
of  U.K. and  European  ceramic dome
systems  (Houck, D.H. and A.G. Boon.
Survey and  Evaluation of Fine Bubble
Dome  Diffuser Equipment. EPA-600/2-
81-222, September  1981),  the study
approach and assessment methodology
used were quite similar to that employed
previously.

Characteristics of Aeration
Systems

Genera/
    All 19  plants  evaluated  were
equipped with either  ceramic  dome  or
disc diffusers  supplied  by one  of the
following manufacturers:
   "Envirex, Inc., Milwaukee, Wl
    Gray Engineering Group, Ltd.,
       Markham, Ontario, Canada
    Norton Company, Worcester, MA
    Sanitaire-Water  Pollution Control
       Corp.,  Milwaukee, Wl
The Gray and Norton systems featured
18-cm (7-in.) diameter dome  diffusers
of the type  studied in the earlier U.K.
survey. Envirex and  Sanitaire  manu-
facture disc diffusers.  The Sanitaire disc
diffuser is 22 cm  (8.7  in.) in effective
surface diameter; the Envirex disc  is
slightly larger. A  list  of the surveyed
plants along with background information
is  given in Table 1.

Design and Operation
    Aeration system  design  and
operating data for the 19 plants visited
are summarized in Table 2.  Thirteen  of
the  systems inspected were being
operated in the plug flow mode. Another
four  were  utilizing  the step feed
configuration, while one was using both
the plug flow and step  feed  operating
regimes in different tanks. One plant was
employing the complete mix  operating
mode.
    Several  of the plants had  aeration
tanks described  by their  designers  as
complete mix  that  were  clearly
functioning in the plug flow mode (e.g.,
Riverside). Only three  plants  - West
Bend, North Buffalo, and  Coulton - were
being  operated in multiple-pass,  plug
flow  configurations  that  resulted  in
length-to-width  (L/W)  ratios  greater
  "Mention of trade names or commercial products
  does not  constitute endorsement  or recom-
  mendation for use.
than 15. In contrast, over half of the U.K.
and  Dutch  plants evaluated  in the first
survey project had  aeration  basin  L/W
ratios of more than  15. High L/W ratios
create design problems in  attempting to
match oxygen demand with a  diffuser
layout of appropriate tapered density that
will not  yield zones  of either under or
overaeration.
    Four of the 13 plants with plug flow
basins were  designed  with  uniform
diffuser configurations; the other 9 were
designed  with  tapered  aeration. A
uniform  diffuser  density  substantially
increases  the difficulty of  accurately
matching oxygen demand with  oxygen
(air) supply in a plug flow aeration basin.
Zones of over and/or underaeration  are
virtually  impossible to avoid in  such a
situation. The problem becomes acute in
multiple-pass plug flow basins with very
long L/W ratios.
    The recommended ranges  of spe-
cific air flow rates for dome and  disc
diffusers are  0.24 to 0.94  L/sec  (0.5 to
2.0 scfm) and 0.24 to 1.42 L/sec (0.5 to
3.0 scfm),  respectively. Headless across
the  media  becomes  very  small  at
specific  air flows less than  the recom-
mended lower limits, making it difficult to
obtain uniform air distribution across the
entire diffuser surface.  Power costs
generally  become  uneconomic if  the
recommended upper  operating limits are
exceeded  for  substantial  periods
because of  decreased oxygen  transfer
efficiency and increased pressure on the
blowers. The average air flow  per diffuser
was within the recommended ranges for
13 of the 17 plants with available air flow
operating data. Four facilities were  op-
erating below  their recommended
ranges.
    Diffuser density  and  air flow rates
per diffuser  varied widely,  reflecting the
lack of  any standardized  approach for
designing  dome and disc  diffuser aera-
tion systems in North America. Minimum
power levels were generally much higher
than those found in the  U.K. plants. No
problems with solids settling in the aer-
ation tanks were reported by any of the
plants evaluated.

Process Performance
    Aeration system  process per-
formance data are presented in  Table 3
for the 19 plants surveyed. Most of the
plants were not designed for nitrification,
though it was occurring  in a number of
them because they were underloaded or
as  a result of the  mode  of operation
selected  by plant  personnel.  Several
plants  featured two-stage  activated
sludge  treatment. Most  of  the plants
were operating  well below design flows
and were producing very high  quality
effluents.
    Air flow varied from 22 to 112 m3/kc;
total 5-day biochemical oxygen demanc
(TBOD5) applied (350 to  1,800 ft3/lb) jr
the North American  plants but generally
averaged less  than that for  the U.K
plants, even where nitrification was being
practiced. In  general, the non-nitrifying
plants averaged less than  62  m3 aii
supplied/kg TBOD5  applied (1,000 ft3/lb]
unless  there  were  problems  with  the
aeration  equipment.  Nitrifying  plants
averaged much  higher with the  exception
of the Village Creek plant, where the aii
flow data may  have been questionable,
Volumetric  loadings  in  the  North
American plants were similar  to those
found  in the  United Kingdom,  but food-
to-microorganism (F/M)  loadings were
somewhat higher here, ranging  from 0.03
to 0.59  kg TBODs/day/kg mixed liquor
suspended solids (MLSS)  vs. 0.05 to 0.45
in the United Kingdom.  MLSS levels in
the North American plants were  usually
less than 3,000  mg/L.  Very little
consistency was noted in basic process
parameters among  the North  American
plants, even between similar  nitrifying or
non-nitrifying  plants.
    Several disc-equipped  plants  had
been originally  designed and  specified
for the  smaller dome diffusers. Sub-
sequently, disc units were purchased and
substituted for the domes on  a  one-to-
one basis. At  West Bend,  this resulted in
substantial overdesign of the aeration
system such that it could not be operated
efficiently  at current  loadings. Plant
operators reported that they  could  not
turn down air flow  sufficiently to reduce
the mixed liquor dissolved oxygen (DO)
level below 6  to 9 mg/L and still maintain
recommended minimum  diffuser specific
air flow rates.

Oxygen Transfer Performance

Method of  Measuring Oxygen
Transfer Performance
    Considerable development work has
been  conducted in recent  years for
measuring oxygen  transfer performance,
including  steady and non-steady state
methods and off-gas  analysis. For  this
project,  since no direct  oxygen  transfer
field measurements were made,  oxygen
transfer  performance was estimated
using  empirically derived  oxygen
consumption  values based  on  TBODs
removal  and  ammonia nitrogen (NH4-N)
oxidized. This  oxygen   mass  balance
technique was  developed by  Boon  anqj
Hoyland of the  British Water  Research

-------
Table 1. Characteristics of Surveyed Plants
Plant Location
(Plant Name)
United States
Coulton, CA
Greensboro, NC
(North Buffalo)
Howard County, MD
(Little Patuxent)
Levittown, PA
(Lower Bucks County)
Rialto, CA
Riverside, CA
West Bend, Wl
Whither, CA
(Whither Narrows)
Berlin, NH
Berlin, Wl
Fort Worth, TX
(Village Creek)
Ltitz, PA
Meriden, CT
Montpelier, VT
Houston, TX
(Park Ten Municipal
Utilities Dist.)
Ridgewood, NJ
Seymour, Wl
Canada
Toronto, Ontario
(Highland Creek)
Toronto, Ontario
(Humber-North plant)
Aeration System Description
Partially nitrifying, concentric step feed basins with sludge
reaeration, uniform diffuser layout, Gray domes
Nitrifying, 2-pass plug flow basins following ist-stage
roughing biofilters, tapered diffuser layout, Envirex discs
Nitrifying (summer), two-stage system, 2-pass step feed
1st stage basins, 1-pass plug flow 2nd-stage basins
(operated in summer only), uniform diffuser layout both
stages, Norton domes
Non-nitrifying, 1-pass plug flow basins, tapered diffuser
layout, Norton domes
Nitrifying, 1 -pass step feed basins, uniform diffuser
layout, Gray domes
Partially nitrifying, 1-pass plug flow basins, tapered
diffuser layout, Norton domes
Nitrifying, 5-pass plug flow basins following ist-stage
roughing biofilters, uniform diffuser layout, Sanitaire discs
Non-nitrifying, 1 -pass plug flow basins, tapered diffuser
layout, Sanitaire discs
Unknown nitrifying, 1-pass plug flow basins, tapered
diffuser layout, Norton domes
Partially nitrifying, 1-pass step feed basins, uniform
diffuser layout, Sanitaire discs
Partially nitrifying, i -pass plug flow basins, tapered
diffuser layout, Norton domes
Nitrifying, two-stage system, i-pass plug flow basins
both stages, tapered diffuser layout both stages, Norton
domes
Nitrifying, two-stage system, complete mix basins both
stages, uniform diffuser layout both stages, Sanitaire discs
Non-nitrifying, J-pass plug flow basins, uniform diffuser
layout, Sanitaire discs
Unknown nitrifying, 2-pass step feed basins, uniform
diffuser layout, Norton domes
Partially nitrifying, 1-pass plug flow basins, tapered
diffuser layout, Gray domes
Nitrifying, concentric plug flow basins, uniform diffuser
layout, Sanitaire discs

Nitrifying, 1 -pass plug flow basins, uniform diffuser
layout, Norton domes
Partially nitrifying, 1-pass plug flow basins, tapered
diffuser layout,Norton domes
WW Flow (mgd)'
Design
5.4
16.0
15.0
12.0
2.0
13.8
9.0
15.0
2.2
1.6
40.0
3.5
11.6
3.97
1.0
4.5
0.61

4.8
31.2
Average"
3.2
12.0
8.9
8.0
2.35
9.0
4.5
12.5
1.7
0.8
54.5
0.9
7.1
1.5
0.2
3.0
0.54

3.0
24.5
Avg. % Removal
T8ODS
96
95
97
93
94
98
98
90
94
96
95
98
95
92
U
90
98

98
94
TSS
94
95
97
90
93
98
98
90
94
98
96
98
95
95
U
90
99

96
94
         = Unknown
         1 mgd = 0.044 m3/'sec
         At time of plant visits from late-1982 to mid-1983
Centre based on the work of Eckenfelder
and  0'Conner (Biological Waste Treat-
ment. Pergammon Press, New York, NY,
1961) for use on the earlier survey. It has
an estimated  accuracy  of  ±  20% if
reliable influent,  effluent,  and  mixed
liquor concentration data are available
over a meaningful operating period along
 «ith  dependable records of  wastewater
Jow  and air  supply.  The  limits  of
accuracy become much broader if his-
torical data are questionable or unreliable
and/or if air flow control is poor.
    The oxygen mass balance technique
used in this study is  represented by the
following equation:
Oygen consumed (Ib/day)         (1 )
= R(BODS- BODe)
   where:
                      4.3 (Ns-Ne)
R  = units  of  oxygen consumed
     by  heterotrophs per unit of
     TBOD5 removed in Ib/day
     and is described  by  the
     equation:

R  = 0.75 + 0.05/(F/M)    (2)

     with an assumed maximum
     R value of 1.5

-------
  BODS = reactor  influent  TBOD5
           Ib/day
  BODe = secondary  effluent TBOD5,
           Ib/day
     Ns = reactor  influent  NhU-N,
           Ib/day
     Ne = reactor  effluent  NH4-N,
           Ib/day
    F/M = food-to-microorganism
           loading,  day1,  based  on
           MLSS under aeration
    In contrast to the U.K. experience, no
North American  plants were  equipped
with  lead-stage  anoxic  zones for
promoting nitrate reduction and oxygen
recovery using  the  denitrification pro-
cess. Consequently,  the  third term of
Boon and  Hoyland's equation,  which
accounts for the oxygen credit (chemical
oxygen  released to the mixed liquor that
lessens  the  amount  of DO  needed)
derived from denitrification,  was not
needed  in this study and is omitted from
Equation 1.
    An  adiabatic compression  equation,
with corrections  for  equipment
efficiencies, was used to estimate  blower
power consumption when  only air flow
data were  available. Compressor effi-
ciency was assumed  at 70%, coupling
efficiency at 95%,  and motor efficiency
at 92%.  Factoring in these assumptions
yields the following relationship:
Wire Power = 0.276 Q
Req'd (kW)
(3)
            P
                              .
                            — 1
    where:
       Q   = air flow, scfm
       Pa  = ambient air pressure, psi
       PI  = piping  system  headless,
             psi
       DI  = diffuser headloss, psi
       SH = static head above diffuser,
             psi
       Pi  = inlet pressure, psi
Diffuser stone headloss was assumed to
be  0.3 psi,  and total  piping  system
headloss  was assumed to  be  0.3 psi.
Ambient pressure was assumed to be
14.7 psi, and inlet pressure was taken as
14.6 psi.
Aeration Efficiency Estimates
    Oxygen  transfer  performance  is
typically expressed  in terms of aeration
efficiency, which is defined  as the mass
transfer  of oxygen  per  unit of line (or
wire)  power  input.  Mass  balance
estimates of oxygen  consumption and
either  measured or estimated  blower
power consumption, as described in  the
previous  section, were  utilized  to
calculate estimated aeration efficiency
values for each plant visited except Lititz
and Park Ten as shown in Table 4.
    A wide  variation  is evident  in  the
estimated aeration  efficiencies of  the
North American plants, ranging from 0.63
kg  O2/kWh (1.03  Ib/wire  hp-hr)  for
Humber to 2.52 kg 02/kWh (4.15 Ib/wire
hp-hr) for Ridgewood.  The average  for
the  17  plants  for  which  aeration
efficiencies could be calculated  was 1.51
kg  02/kWh  (2.49  Ib/wire hp-hr). This
compares favorably with  the  average
estimated aeration  efficiency of 1.48 kg
02/kWh  (2.43 Ib/wire  hp-hr) for the 16
plants from the  earlier survey for which
adequate information  was  available to
prepare estimates.
    Of the above  17  North  American
plants, six were  totally  nitrifying at  the
time of  the study (North Buffalo, Rialto,
West Bend,  Meriden,  Seymour,  and
Highland Creek), six more  were partially
nitrifying (Coulton, Riverside, Village
Creek, Ridgewood, Humber, and Berlin,
Wl), four were not nitrifying at  all  (Little
Patuxent, Lower  Bucks County, Whittier
Narrows, and  Montpelier),  and  no
nitrogen data were available for  one plant
(Berlin,   NH). The  estimated  average
aeration efficiency  was 1.59 kg 02/kWh
(2.62 Ib/wire hp-hr) for the six nitrifying
plants, 1.45 kg 02/kWh (2.38 Ib/wire  hp-
hr) for the six partially  nitrifying plants,
and 1.32 kg 02/kWh (2.17 Ib/wire hp-hr)
for the four non-nitrifying plants.
    The above  results suggest  that
nitrifying  systems are  more energy
efficient  than non-nitrifying systems. A
possible reason  for their better oxygen
transfer performance  is  their lower
organic  loading  rates and  longer sludge
retention times  (SRT's) contrasted with
typical non-nitrifying  systems. Longer
SRT's are generally believed to promote
higher alpha values and higher oxygen
transfer  rates in  wastewater,  thereby
resulting in  higher  system  aeration
efficiencies provided the SRT's are  not
substantially longer than  necessary to
sustain nitrification.

Operation and  Maintenance
     Maintenance observations  at the 19
plants surveyed are summarized in Table
5.  Over one-half of these  plants  had
significant  problems  with  the diffuser
systems at startup or  within the first  few
years of operation. Two plants required
complete replacement of the initially
installed equipment. Plant  operators on
the job  during initial installation reported
that installing contractors were given  little
supervision and often did not fully check
out the system after installation.
    It was observed that some  plant
operators  did not  comply  with  the
recommended minimum  air flow  rates
given in  literature provided by  all the
equipment  suppliers. Four of the plants
were operated  at  air  flows  below
recommended minimums  much of the
time.  In   one  case,  the  operator
overloaded the aeration system in lieu  of
putting a second basin on stream, greatly
exacerbating problems caused  by failure
of diffuser  hardware. Installers  at this
same plant had overtightened much  of
the system's hardware, causing extensive
dome  hold-down  bolt  failure  and  air
leakage.
    About  one-half of  the plants  were
doing  an   adequate maintenance  job.
Several, such as Berlin (NH), Montpelier,
and  Seymour, were highly aware of the
benefits of preventive maintenance and
had  set up and followed routine cleaning
and  checking schedules much like those
observed in the  United Kingdom. These
plants  reported  excellent  O&M  experi-
ences with  their diffuser systems.


Conclusions
     Unlike  the generally favorable  O&M
performance  observed overseas, the
North American plants visited were more
likely to have experienced  significant
problems with their fine bubble aeration
systems. It appeared that many  of the
same design deficiencies noted  in plants
overseas  have  been  repeated  here.
Problems  with equipment had occurred
in  about   one-half  of  the   plants
evaluated. Those  plants  that  had
experienced  significant equipment
problems tended also to exhibit relatively
poor aeration efficiencies.
     Overall, estimates of oxygen transfer
performance  for  the  North  American
plants were on a par with those estimated
previously  for the U.K. plants.  In both
surveys, however, several plants were
producing aeration efficiencies well below
the  potential  capabilities of  ceramic
diffusion technology. The  sub-standard
oxygen transfer performance of those
U.K. plants  exhibiting  below  normal
aeration efficiencies could be tied in most
cases  to   long  tank  L/W ratios,  non-
tapered diffuser configurations,  and
associated overaeration  and  wasted
energy.  On  the  other  hand,  the
contributing factors for  those North
American  plants  with below-average
aeration efficiencies appeared  to  be
linked  more closely  to wastewater char-"
acteristics  (i.e., greater contributions from

-------
Table 2. Aeration System Design and Operating Data
Aeration Basin Dimensions
Plant Name
Coulton: Unit 1
Unit II
North Buffalo
Little Patuxent
Lower Bucks
County
Rialto
Riverside
West Bend
Whittier
Narrows:
Tank 1
Tanks 2&3
Berlin (NH)
Berlin (Wl)
Village Creek:
Tanks 1,2, & 4
Utitz: Stage 1
Stage II
Meriden: Stage 1
Montpelier
Park Ten
Ridgewood
Seymour
Highland Creek
Humber
Length
(ft)"
1241174
153.5
260
185

200
100
250
113


300
300
100
80

239
114
139
100
39
92.3
116
201
115
246
Width
(ft)"
8.25
14
20
30.25

30
20
40
19.8


30
30
25
20

104
25
30
56
39
30
24
26
58
58.3
SWD
(ft)"
10
14.4
14.5
15.3

15
15
17.6
18


14.4
14.4
15
15

13.8
15
15
18
18
14.5
15
14.7
25
24
Effect. Basin
L/W
726.5*
32.9ft
26.0
12.2

6.7
10.0
6.3
28.5


10.0
10.0
4.0
4.0

2.3
4.6
4.6
5.4
1.0
6.2
4.8
7.7
2.0
4.2
Diffuser Density
(No./fP)-
0.30-0.25
0.41
0.23-0.14
0.39

0.28-0.16
0.47
0.54-0.45
0.17


0.26-0.15
0.33-0.19
0.27-0.15
0.21

0.50-0.28
0.49-0.26
0.41-0.22
0.10
0.18
0.31
026-0.14
0.12
0.54
0.56-0.28
Diffuser Taper
(%)
Uniform
Uniform
33/26/22/19
Uniform

64/36
Uniform
26/26/26/22
Uniform


39/38/23
39/38/23
45/32/23
Uniform

34/27/21/18
48/26126
48/26/26
Uniform
Uniform
Uniform
33/29/19/19
Uniform
Uniform
47/29/24
Air Flow per Unit
Volume
(cfm/1,000 ft3)?
25.6-22.1
24.9-24.5
22.7-13.2
32.1

23.3-13.3
19.3
11.1-9.3
3.5


23.3-14.2
23.0-13.4
7.2
10.4

20.5-11.3
U
U
11.9
3.6
U
10.7-6.0
5.4
7.2
30.2-15.1
Avg. Air Flow
per Diffuser
(cfm)tt
0.87
087
1.43
1.27

1.25
0.62
0.36
0.37


1.14
0.93
0.71
0.74

0.56
U
U
1 73
0.37
U
0.62
0.64
0.34
1 29
   U = Unknown
   '  1 ft = 0.305 m
   " 1 dome/ft2 =  10.76 domes/m2
   i  1 cfm/1,000 ft3 = 0.017 Um3/sec
   tt 1 cfm = 0.472 Usec
   t  Based on  six plug flow aeration sections of 174 ft each
   tt Based on  three plug flow aeration sections of 153.5 ft each
industry with lower concomitant  alpha
values), equipment failure, and a higher
incidence of diffuser sliming or fouling.
    The  principal conclusions of this
study follow:
1   Estimates   of  system  aeration
efficiency  varied  widely for  the  visited
plants  but seemed to be linked to pro-
cess configuration  and  loading  con-
ditions, wastewater characteristics, and/or
O&M problems. Plants using higher rate
processes  seemed to  have  lower
aeration efficiencies with  one exception
(Whittier Narrows) where O&M practices
were rigorous and effective. Within the
limits  of  the accuracy  of  the  mass
balance technique  employed in  this
study, the  estimated aeration efficiencies
for  the  non-nitrifying  activated sludge
systems averaged 1.32 kg Oa/kWh  (2.17
Ib/wire  hp-hr).  The  average  estimated
aeration efficiency of those plants where
complete  or a  significant  degree  of
nitrification  was  occurring was  1.52  kg
02/kWh (2.50 Ib/wire hp-hr). In  general,
it  appears  that the  lower F/M and
volumetric loadings and  longer  sludge
ages  necessary  to sustain  nitrification
result in  improved  oxygen  transfer
performance  and  reduced rates  of
diffuser fouling.
2.   Inadequate  or  inappropriate O&M
procedures were found to be a principal
contributor  to less-than-optimum  ox-
ygen  transfer performance and/or major
equipment maintenance  problems  ob-
served at some plants.
•  For the most part, operators had been
   provided  little  or  no  literature  or
   training for diffuser system operation,
   troubleshooting,  or maintenance.
   Several  of  the  plants visited had
   experienced major equipment failure,
   but the operators were not  aware of
this until it was pointed out to them. In
general, plant maintenance mechanics
did not know the correct  procedures
for checking, tightening, and  replacing
diffuser hardware, though several had
developed  effective  procedures by
trial and error.
With  only  two  exceptions,  plant
operators did not understand that fine
bubble ceramic diffusers  would
probably  require cleaning  after 6  mo
to 2 yr of operation, depending on the
rate  of diffuser  media fouling and
headless buildup. Advance provisions
for diffuser cleaning  had been made
only  at  the Village Creek  plant
(ultrasonic cleaning) and the  Seymour
plant  (acid  gas  cleaning)  and there
was  general  ignorance  of the time,
manpower    and   equipment
requirements, and costs  associated
with diffuser cleaning.

-------
Table 3. Aeration System Process Perforrr
Average TBOD5 (mg/L)
Plant Name
Coulton
North Buffalo
Little Patuxent
Lower Bucks
County
Rialto
Riverside
West Bend
Whittier Narrows
Berlin (NH)
Berlin (Wl)
Village Creek
Utitz
Meriden
Montpelier
Park Ten
Ridgewood
Seymour
Highland Creek
Humber
Raw
WW
244
200
150
220

256
160
150
325
195
485
274
177
264
128
U
140
360
145
200
Primary
Erf.
J80
720~
115
220
(est.)
185
80
62"
142
60
242
175
119
90
66
-
90
--
-
100
Final
Eff.
12
10
78ft
15

13
5
8
4
12
20
79
5ft
5/t
10
10
5
4
5
20
lance Data
Average Volumetric
Loading (Ib
TBOD5/day/l,OOOft3)«
22.7
19.9
27.7ft
40.8

60.4
8.5
5.8
38.9
7.6
76.8
58.3
10.4ft
17. en
7.5
U
27.0
10.5
10.9
29.7
Average MLSS
(mg/L)
2,500
2,300
2,800ft
2,800

6,450
2,700
600
7,053
7,750
7,400
3,500
U
3,900tt
2,000
U
2,000
5,800
2,500
4,300
Average F/M Loading (kg
TBOD5/day/kg MLSS)
0.74
0.14
0.24/t
0.23

0.15
0.05
0.75
0.59
0.07
0.79
0.27
U
0.07ft
0.72
U
0.22
0.03
0.07
0.11
Average Air Flow
ft3/lb TBOD5 applied)t
7,570
7,249
7,066ft
647

461
7,799
866
678
576
892
499
U
7S7tt
349
U
428
777
953
7,037
    U=unavailable
        11b TBOD5/day/l,000 ft3 =0.016 kg/day/m3
    t   1 fP/lb TBOD5 applied =0.062 rn^/kg
        TBOD5 of roughing biofilter effluent
    n   Based on first-stage aeration only
•  Plant operators  were not aware of the    •
   relationship  between  process
   operation and aeration efficiency. Only
   a few were  aware  of the  need to
   maintain  minimum  air  flows,  and
   several of the  underloaded  systems
   were  being   operated   below
   recommended  air  flow  rates  per
   diffuser.  None  of  the plant O&M
   manuals  inspected  provided  any
   guidance  for  diffuser  system    •
   maintenance or efficiency monitoring.
3. Poor aeration  system  performance
and/or  O&M problems  were often
attributable to design inadequacies or
errors.
   Typical design errors included lack of
   aeration taper,  poor inlet and  outlet
   design, too many or too few diffusers,
   and lack of DO monitoring equipment.
   The  excessive  aeration  tank  L/W
   ratios common to many  U.K. plants
   were not observed in this study.
   Little  attention  had been given  to
   facilitating periodic  maintenance  at
   many of  the plants  studied. In most
   cases, draining  of aeration  tanks
   required the use of  special pumping
   equipment.
•  Most of the plants were not equipped
   with the monitors necessary  to check
   aeration  system  performance.
   Specifically,  few had separate power
   meters for aeration blowers and many
   had no means of measuring air flow to
   the aeration  tanks. Provision of on-
   line DO monitors was uncommon, and
   those plants  that  had  DO  monitors
   often did not maintain them properly.
•  Several plants had been designed for
   28-cm  (7-in.)  dome  diffusers  but
   were equipped with the larger 22-cm
   (8.7-in.) disc diffusers  because the
   latter were low bid, However, design
   engineers required  that  the same
   number of  the larger diffusers  be
   installed, resulting  in oversizing of the
   aeration systems in  these plants.
   Extensive  research at  Los  Angeles
   County Sanitation Districts  has verified
   that  three   22-cm  (8.7-m.)  disc
   diffusers are equivalent to  four 18-
   cm  (7-in.) dome  diffusers  from  an
   oxygen transfer standpoint.
4. Poor quality  installation was a major
cause  of subsequent equipment
problems.  Often,  critical  hardware  was
over-  or  under-tightened,  causing
leakage and/or  breakage. Manufacturer
and/or  design engineer supervision (
most  installations  was  minimal,  an
contractors often did not follow publishe
guidelines.  In some cases, the fragility <
the plastic  hardware contributed  to th
problem. The equipment supplied  by th
major manufacturers varied in  sensitivil
to installer error. However, when correctl
installed, most of the equipment, with th
exception of some gasket materials, w£
relatively trouble  free.  Also,  substanti,
improvements in  product quality hav
been made in response to field problenr
and competitive  pressures over the la
several years. Where  problems hav
been  experienced, all  of the princip.
suppliers  have promptly  honore
equipment warranties,  even   wher
complete system replacement has bee
required.
5.  Although diffuser sliming and  foulin
were only clearly indicated at four of th
plants  visited, zones of  coarse bubblin
were  evident in several  other   plant
Coarse bubbling may  or may  not b
indicative of fouling, but it definitely has
negative impact on  oxygen  transf<
efficiency.  Based  on  these limite
observations, ceramic  diffuser   foulir
appears  to become more prevalent wi

-------
Table 4.
Aeration System Oxygen Transfer Performance Data
Plant Name
Coulton
North Buffalo
Little Patuxent
Lower Bucks County
R/a/to
Riverside
West Bend
Whittier Narrows
Berlin (NH)
Berlin (Wl)
Village Creek
Lititz
Meriden
Montpelier
Park Ten
Ridgewood
Seymour
Highland Creek
H umber

U = Unavailable
Avg. WW Avg. Air Flow* Avg. Power
Flow* (mgd)t (cfm)* Usage (kW)
3.2 5,400 149
12.0 10,420 386
8.9 5,500 154
8.0 6,600 223
2.35 1,160 50.2
9.0 7,500 203
4.5 1,400 61.1
12.5 6,966 207
1.7 340 8.3
0.8 1,000 31.4
54.8 27,720 812
0.9 U U
7.1 2,800 102
1.5 200 7.3
0.2 U U
3.0 670 19.6
0.54 800 24.3
3.0 2,400 75
24.5 14,710 730


How Power Calc. Field Aeration
Usage Derived? Data Quality (Ib O?/wire hp-hr)
ca/c. poor 1.33
meas. good 1.36
meas. fair 1 39
meas. fair 1 84
ca/c. poor 2.90
meas. fair 1.89
meas. good 1 85
ca/c. good 1.94
meas. fair 3.74
meas. good 1.91
ca/c. fair 3.97
poor
meas. fair 3.80
meas. fair 3.49
poor
meas. short 4.15
meas. fair 3.22
meas. fair 2.57
meas. good 1.03
Average: 2.49

Efficiency
(kg/kWh)
0.81
0.83
0.85
1.12
1.75
1.15
7.13
1.78
2.27
1.16
2.41
--
2.31
2.12
--
2.52
7.96
1.56
0.63
1.57

* At time of plant visits from late-1982 to mid-1983
1 1 mgd =0.044 m3/sec
t 1 cfm =0.472 /./sec
Table 5. Aeration System Maintenance Summary
Aeration System
Plant Name Year Started Up Startup Experience
Coulton
North Buffalo
L/ttle Patuxent
Lower Bucks County
Rialto
Riverside
West Bend
Whittier Narrows
Berlin (NH)
Berlin (Wl)
Village Creek
Lititz
Meriden
Montpelier
Park Ten
Ridgewood
Seymour
Highland Creek
Humber
1981 Poor, entire system replaced
1982 OK, minor problems
1980 Some breakage, leaking
1982 OK
1981 OK
1982 OK
1980 OK
1981 OK
1979 OK, some contractor error
1981 OK
1978 Poor, contractor error
1981 Poor, entire system replaced
1982 OK, some contractor error
1981 OK
1978 OK
1983 OK, vendor's rep. msta/ted
1982 OK
1968 OK, few problems
1982 OK
Aeration System Operating Experience
Excellent, no problems since replacement
General disc gasket failure in 1 yr
Poor, frequent failure of plastic parts (particularly dome
Fair, slime growth from heat treatment recycle
Excellent
Excellent
Excellent
Some slime growth, cleaned periodically with hosing or
no mechanical problems
OK, a few small leaks
Some slime growth and possible plugging



retainer bolts)




gas injection,


Poor, significant leakage and periodic failures of plastic hardware
Excellent, no problems since replacement
Excellent
Excellent
Poor, system failed due to O&M error
Some slime growth, cleaned periodically with hosing or




acid brushing
Fair, some plugging, in-situ gas cleaning system works well
Excellent, no failures in 14 yr
No way to check system, possible failure



-------
increasing process load,  particularly  at
the influent end of plug flow reactors and
the multiple feed points of step feed
reactors.  Where rapid diffuser fouling is
encountered,  a  recently-developed,
proprietary,  in-situ,  non-process  in-
terruptive  cleaning  technique using
hydrochloric acid  gas injection from  the
air side may permit aeration efficiency to
be  maintained  at  acceptable levels
between  more rigorous  process-inter-
ruptive cleaning cycles.
         6. Although the O&M peTTbrmaw,v, ^
         collected  in this project__are
         generally positive as ttibse" reported  in
         the earlier U.K. study, it should be noted
         that several  plants were  visited where
         ceramic diffusers are  performing  quite
         well and have produced  major  energy
         cost  savings.  These   plants  are
         characterized  by careful  attention  to
         correct  installation and O&M  of  their
         diffuser  systems. Where problems have
         been experienced, they could normally
         be  diagnosed   and    corrected    at
/ icdsuuaoie COST, basically,  this  stud
  verified that "fine bubble ceramic  diffusio
  technology can  work  well  in  Nort
  American  plants  and  that  improvei
  design,  installation,  and O&M practice
  are the primary ingredients  needed t
  maximize  aeration  performance  am
  potential cost savings.
      The  full  report  was submitted ii
  fulfillment  of  Purchase  Order  No
  C2667NASX by D.H. Houck  Associates
  Inc., under the  sponsorship of  the  U.S
  Environmental Protection Agency.
    Daniel H. Houck is with D. H. Houck Associates, Inc., Silver Spring, MD 20901.
    Richard C. Brenner is the EPA Project Officer (see below).
    The complete report, entitled "Survey and Evaluation of Fine Bubble Dome and
         Disc Diffuser Aeration  Systems in North America," (Order No. PB  88-
         243 886/AS; Cost: $19.95, subject to change) will be available only from:
             National Technical Information Service
             5285 Port Royal Road
             Springfield, VA 22161
             Telephone:  703-487-4650
    The EPA Project Officer can be contacted at:
             Water Engineering Research Laboratory
             U.S. Environmental Protection Agency
             Cincinnati, OH 45268
 United States
 Environmental Protection
 Agency
Center for Environmental Research
Information
Cincinnati OH 45268
                BULK RATE
          POSTAGE & FEES PAID
                   EPA
             PERMIT No. G-35
 Official Business
 Penalty for Private Use $300

 EPA/600/S2-88/001
                                  0000329   PS
                                                                  60604

-------