United States
                    Environmental Protection
                    Agency	
Risk Reduction
Engineering Laboratory
Cincinnati OH 45268
                    Research and Development
 EPA/600/S2-89/005  Jan. 1990
v°/EPA         Project Summary

                    An  Evaluation  of the
                    Secondary  Effects of
                    Air  Stripping
                    Mark D. Umphres and James H. Van Wagner
                     At  a  2.9 million  gallon  per day
                    (mgd) well contaminated with several
                    volatile  organic compounds (VOCs),
                    principally trichloroethylene (TCE), a
                    packed  tower aerator  was  pilot
                    tested,  designed, constructed, and
                    monitored during its  first  7 mo of
                    operation. Pilot testing was based on
                    gas/liquid mass transfer theory- Cal-
                    culated  mass transfer  coefficients
                    coupled with this theory were used to
                    design the full-scale aerator for TCE
                    control.  Modeling of VOC off-gas
                    dispersion was required to obtain a
                    construction  permit  in Southern
                    California. In addition to liquid-phase
                    VOCs, other parameters  including
                    bacteria, temperature,  pH, dissolved
                    oxygen,  calcium,  alkalinity,  turbidity,
                    particle counts, noise, and  air-phase
                    VOCs were monitored  to assess the
                    secondary  effects  of aeration.
                    Secondary effects refer  to the air,
                    water, and ambient quality that  might
                    be affected by tower operation for the
                    control of VOCs. Parameters such as
                    calcium carbonate deposition, corro-
                    sion, and Legionella were examined.
                    Of  the  many parameters, only cal-
                    cium deposition and standard  plate
                    count (SPC)  bacteria  required con-
                    trol. The full-scale aerator was  modi-
                    fied to improve VOC control. A capital
                    and  operation  and  maintenance
                    (O&M) cost analysis indicated packed
                    tower aeration (PTA)  to be  cost-
                    effective.
                     This Project Summary was  devel-
                    oped by EPA's Risk Reduction  Engi-
                    neering Laboratory, Cincinnati, OH, to
                    announce key findings of the research
                    project that is fully documented in a
                    separate report of the same title (see
Project Report ordering information at
back).
Introduction
  Since 1974, researchers have observed
widespread  contamination of finished
drinking water with  trace amounts of
synthetic organic  chemicals, many of
which have been linked to adverse health
effects.  Recent surveys  of groundwater
quality have discovered equally wide-
spread contamination of groundwaters
once thought to be protected. California
groundwater has  been contaminated
principally with  TCE  and  dibromo-
chloropropane.
  The  Valley  County  Water  District
(VCWD) provides groundwater to the City
of Baldwin Park and a portion of the City
of Irwindale.  The District lies in  the San
Gabriel Valley,  roughly 30 miles east of
the  City of Los Angeles. In  December
1979,  TCE  exceeding 1 mg/L  was
discovered in one of  the District's wells.
The California Department of Health
Services (CDHS), responsible for enforc-
ing drinking water standards, immediately
began an extensive monitoring program.
TCE contamination  was found throughout
the  San Gabriel  Valley;  however, the
concentrations observed elsewhere were
considerably  less than  those found in
some VCWD wells. In 1980, the CDHS
established an action level for TCE  of 5
ng/L; wells exceeding 50 ug/L TCE were
shut down.
  Granular activated  carbon (GAG)
adsorption and air stripping are the most
common  technologies  for  removing
organic  contaminants. Air stripping by
PTA is considerably less expensive  than
GAC. This  study covered the pilot testing,

-------
design,  and monitoring of  a full-scale
PTA at the VCWD Lante Well. In addition
to TCE,  the well  contained  tetrachlo-
roethylene  (PCE)  and 1,1,1-trichloro-
ethane (TCA).

Objectives
  The  viability  of  PTA has been  com-
pared  with that  of GAC  and  other
processes. Although economics and sim-
plicity  of operation and  maintenance
favor aeration, further work was needed
to identify other aspects that could  affect
its performance and  cost.  Several states
have established  policies  regarding the
emissions from tower aerators  in re-
sponse  to the  concern over air quality
and the issue of trading a  water contam-
ination  problem  for  a  potential air
pollution problem.  Some  states require
that  controls be provided regardless of
the levels of VOCs in the off-gas.  Other
states such  as California require a  study
of the  effect  of  VOC dispersion  to
determine if the level  of air  pollution is
significant and if controls are needed.
  The  primary  objectives  of this  study
were to evaluate the secondary  effects of
PTA. Secondary effects are those affect-
ing water, air, and ambient quality, and in
this  study include  PTA's  influence on
mineral scaling, corrosivity,  microbiolog-
ical  quality, noise, air  quality,  and
particulate concentration. Pilot-scale tests
were conducted  to  develop  design
criteria  for  the  full-scale  packed  tower
aerator  and to  assemble information for
an  air  pollution  control  permit.  The
aerator  was then  constructed, and  once
in operation, it was monitored to assess
secondary effects.

Pilot-Scale Testing and Full-
Scale Design

Approach
  The  design  of  the pilot-scale testing
and  the analysis of the data was based
on conventional gas/liquid mass transfer
theory.  This theory established the rela-
tionship between a number of factors that
affect  the design  and  performance of
packed tower aerators —  factors  includ-
ing the Henry's coefficients of TCE and
the other VOCs, packing depth, air load-
ing  rate,  water loading rate, air-to-water
ratio, and air pressure drop through the
packing.
   Nineteen  pilot runs  were  conducted.
Influent  and  effluent samples   were
analyzed  for VOCs, calcium, alkalinity,
total dissolved  solids,  turbidity, particle
counts,  pH,  chlorine residual,  and
temperature. Each run corresponded to a
unique set of operating conditions for
packing depth and water loading rate.
The operating conditions during the pilot
study ranged  from 1.75  to  9.75 ft  of
packing depth, 4.3  to  28  gpm/ft2 water
loading  rate,  and 29  to 160 cfm/ft2  air
loading rate.

Equipment
  The pilot-scale unit was designed for
countercurrent air and  water  flow with
forced draft air supply. It was constructed
of 11.5-in. diameter  clear Plexiglas", sup-
ported by a  plenum.  The  shell was
assembled in 2-ft sections separated  by
flow redistributors. The tower was packed
with  1-in. polypropylene Super  Intalox*
saddles. Air was  supplied by a centrifugal
blower. The blower intake was extended
15 ft from the  tower  to  reduce  recir-
culation  of  the  off-gas.  Air  flow was
adjusted  to  a predetermined pressure
drop across an orifice plate in the air flow
meter.  An  inclined-tube manometer
measured differential  pressure.  Influent
water was supplied  directly from  the well
pump discharge. Influent  water  entered
an  18-ft  standpipe that  maintained  a
constant influent pressure and water flow.
From the standpipe, flow was diverted to
a  rotameter and then  to the  packing.
Treated water flowed from the plenum to
an air break.  The height of the air break
was adjusted to keep water in the plenum
so that gasses would not be lost through
the water discharge  line.

Testing and Design
  Pump tests and pilot-scale studies took
place in November  and December 1982.
Pump  tests  indicated TCE typically
increased from near 70 to near 400 ug/L
in 6 hr and leveled off  near 500 pg/L at
24 hr.  During pilot  tests, the pump was
operated 4 hr before  testing began with
the result that influent TCE ranged from
200 to 400 ug/L.
  The  Sherwood and  Holloway corre-
lation  was  used to  determine  mass
transfer coefficients  (KLa's).  The data
analyses  discounted the  contribution of
end  effects,  i.e., volatile  losses in  the
distribution  and plenum  collection  of
water.  For each of the 19 runs, Kua's
were determined for TCE,  PCE, TCA and
for four trihalomethanes that were spiked
into the influent water. A computer model
 •Mention of trade names or commercial products
  does not  constitute endorsement or recom-
  mendation for use
(utilizing  the theory and  design crit
described in the Project Report) analy
the data for design purposes.
  As inputs  to the computer model,
ug/L influent TCE  and 3  pg/L efflt
TCE were conservatively  chosen  i
yielded  a design  of 99.4%  remo
based  on countercurrent  operation.  '
1-in. saddles used during piloting w
also chosen. The  least-cost  desi
based on a 1400 gpm (2.9 mgd) flowr,
included: 30  gpm/ft2  water  loading r;
5600  cfm air loading rate, 30:1  air
water ratio,  18-ft  packing depth, 7.
tower diameter, and an air pressure d
of 0.05 in./ft of packing. The design v
done in early 1983.
  A unique  feature of  the  design  v
elevating the packed tower  aerator 01
structural platform to allow treated we
to flow directly  to an existing,  surfa
level,  2-mil-gal  storage reservoir. Ad
tionally, the  design called  for the cai
bility to feed chlorine and  sodium he
metaphosphate  (SHMP) to the  aera
influent or effluent,  as needed, for mic
biological or stability control. The aera
incorporated  ports at its top and botti
to allow access  to  water   and
distributors and packing material.

Secondary Effects
  Pilot testing  included  an analysis
secondary effects.  The chlorine dema
was  found to be less than 0.5 mg
Turbidity and particle count data show
insignificant  change; these data su
gested that,  even  at higher air-to-wa
ratios, any entrainment of  dust would r
measurably  affect suspended solid cc
centration. Aeration raised the  pH abc
0.3 units. Calcium and alkalinity lev*
showed very little change. The calculat
Langlier  Index indicated a slight increa
as a  result  of  aeration, but suggest
only slight  calcium  carbonate  scalii
tendencies.  Influent water temperatun
were  near 64°F and dropped  less th;
1°F  with aeration.  Mean  effluent  c
temperatures were the  same as efflue
water temperatures.
  Ambient air was sampled for  VOCs
the pilot unit when it was not in operatic
TCE concentrations between 6  and (
ng/L were found, with the higher lev
attributed to nearby industrial activit
Using  Henry's  law  and the  pilot-sea
hydraulics, the  worst-case scenario
entraining these VOCs into the treat*
water  was calculated and  found to t
between 0.02  and  0.2  ug/L.  The  Ce
culated  levels  were  lower than tho:
typically found  during  pilot testing ar

-------
suggest that ambient air would have  no
detrimental  impact of full-scale  PTA
performance.

Air Quality Modeling
  The South  Coast Air Quality Manage-
ment  District (SCAQMD)  did computer
modeling of the dispersion pattern  of
expected  VOC  discharges from  the
designed  packed  tower aerator.  The
modeling produced estimates of annual
average ground-level concentrations  of
TCE within 2 mi of the Lante Well. The
model utilized projected concentrations of
the VOC off-gases and meteorological
data from  nearby airports.  Results indi-
cated that  PTA off-gases would create a
maximum  annual average  TCE  concen-
tration of 21  ng/L northeast of the well
outside  a  residential  area.  A maximum
annual average in the nearby residential
area would be 5.8 ng/L. The CDHS, in
reviewing  the results, used a 106 risk
factor of 52 ng/L for  TCE.  The  VCWD
received a permit to construct.

Full-Scale Monitoring
  Following construction  and start-up
testing,  the  packed tower  aerator was
monitored  during the 7 mo period begin-
ning in  July  1985. For  the first 3 mo,
operation was continuous and allowed  for
corrosion testing.  Normally, the  VCWD
operates the Lante Well  on an  inter-
mittent  basis to  maintain  distribution
system  pressure and  meet demand. Fol-
lowing  the  corrosion monitoring,  the
aerator was operated  intermittently, com-
ing on-line at midnight and  shutting down
near 8:30  am.  Samples were typically
collected at 7:30 am.

VOCs
  Start-up  tests began in January 1985.
During the first few  months of testing,
TCE influent concentrations occasionally
exceeded  800 iig/L-significantly above
the 500 tig/L design criteria. The reason
for this is not understood. Because of this
increase,  effluent  TCE concentrations
sometimes exceeded  the  5 \ng/L  target
level. Control  of TCE was as low  as
96.9%  removal. Several  modifications
were  made  in an  attempt  to improve
performance. After start-up,  18 ft of pack-
ing had  settled to approximately 17-1/2 ft.
Further, it  was observed that water was
not evenly distributed over a  series of
weir troughs that delivered water to the
packing. Adding 6 in. of packing material
and stainless steel wire mesh to the weir
troughs improved performance.  The air
inlet  was modified  from  one  that
delivered air offset from the center of the
aerator  to one that  directed  air more
symmetrically  across the bottom of the
tower.  This, however, did  not  improve
performance.
  During the   7-mo  monitoring  period,
TCE control ranged from 99.1% to 99.5%
removal, and effluent concentrations were
typically below 5 pg/L.  The  difference
between pilot-scale  prediction  and full-
scale performance may have been due to
axial dispersion and side-wall channeling.
The consensus of packing manufacturers
was that it is not necessary to redistribute
water with packing depths less than 20 ft.
No redistributors were built into the full-
scale tower although they were used in
the pilot-scale tower upon which  the
design  was based.  At full-scale,  redis-
tributors may  have  improved  perform-
ance.

Secondary Effects

Microbiological Quality
  During the  first 3  mo of monitoring,
chlorine was fed ahead of the aerator but
downstream of the influent sample tap.
When  prechlorinating, effluent  residuals
exceeded 0.6  mg/L,  and little difference
was  observed between  influent and
effluent SPC  when  either R2A or plate
count agar media was used. To evaluate
the potential for microbiological growth in
the aerator, prechlorination was  discon-
tinued.  In the  following  months,  effluent
plate counts were approximately 2 logs
greater than influent counts  as a result of
aeration. Effluent densities were typically
103/mL. Results from  the two media were
in reasonable agreement.
  Legionella were not found in any of the
samples. Colonies with morphology simi-
lar to Legionella were observed in pre-
sumptive  tests, however.  Subsequent
confirmation attempts using fluorescent
antibody staining  indicated that  Legion-
ella were not present.
  Similarly, coliforms were not  found in
any  of the  samples using  the most
probable number method.  All  samples
were reported  at less than 2.2 colony
forming units/100 mL.

Water Temperature
  The  influent  water temperature was
consistently in the range of 59° to 63°F.
Effluent temperatures  were  typically
within one or two degrees of influent, with
a few  exceptions  when  effluent temper-
atures  dropped 5°  to 10°F.  On these
occasions, correlation  with dry  bulb
temperature or relative humidity was  not
apparent.


Calcium Carbonate  Deposition
  The VCWD observed  calcium carbon-
ate scaling during an  earlier project
studying  spray  aeration  in  the 2-mil-gal
reservoir.  In this  project, after 3  wk  of
operation, the pump boosting water from
the reservoir  to  the  distribution  system
failed  as  a result of  scaling within  the
casing.  Additionally,  scaling was  ob-
served on the bottom 3 in. of  packing.
After SHMP was brought on line at 1
mg/L and the  pump was acid cleaned,
further scale buildup in the pump and on
the packing in subsequent weeks was  not
evident.
  Analyses of the packing  showed  no
calcium scale at the top  of the tower,  but
an increase from less than 1 mg Ca/piece
at the  bottom  at start-up  to  131   mg
Ca/piece  at  the bottom  after  3  wk.
Analyses  of dissolved calcium  showed
very  little change across  the  aerator.
Concentrations fluctuated  between  66
and 72 mg/L. Coupled with the flow-rate
data over the  3 wk  period,  it was
concluded that scaling was limited to  the
lower  3  in. packing. Analyses  of  the
packing following several weeks of add-
ing SHMP confirmed that further scaling
had not occurred.
  Influent and  effluent alkalinity were
nearly constant at 180  mg/L over time.
Aeration raised the mean dissolved oxy-
gen (DO) concentration  from 5.5  to  9.3
mg/L. The pH level was typically elevated
from 7.6  to near 7.9  as carbon  dioxide
was  stripped. Although C02 was  not
measured,  its calculated loss, based on
carbonate chemistry, was approximately
5.2 mg/L.
  The calculated Langlier Index of  the
water  influent  to  the  aerator was near
zero. With the increase of  pH during
aeration,  however, the Index was slightly
positive, suggesting the treated water had
mild scale-forming properties. This could
account for the  calcium scaling  in  the
bottom of the tower  and in the  down-
stream  pump.  Both  of these  waters
experienced the highest pH.

Corrosion
  Mild  steel and  copper corrosion rates
were evaluated  during  the first  3  mo
when  the  aerator was  in  continuous
operation.  Rates were  measured with
Rohrbach corrator probes and an  ASTM
procedure for  metal coupon weight loss.

-------
Both metal coupons and corrator probes
were  installed in corrosion test racks
located on the influent and effluent sides
of the aerator. Coupon analyses indicated
a decrease in the rates of both metals
over  time.  Copper displayed little
difference in rates between influent  and
effluent waters, whereas mild steel rates
decreased  slightly across  the  aerator.
Weekly corrator  readings indicated a
similar drop in rates for both metals over
time,  and generally,  the readings were
within 1  log agreement of rates deter-
mined by coupon weight.  The  slightly
higher mild steel  corrosion rates in  the
aerator influent may possibly be  a result
of the lower pH and lower  Langlier Index
of that water.
  The addition of SHMP after the third
week of operation appeared to have  little
effect on  the  effluent corrosion  rate  of
either material.

Particulates
  Both turbidity and particle counts in the
range  of  1p to  60ii were measured.
Despite the fact that  a residue gradually
built up at the blower inlet and at the air
inlet within the  aerator, no  significant
difference between influent and  effluent
turbidity  or  particle counts were
observed. Effluent turbidities averaged
0.29 nephelometric turbidity unit.

Air Quality
  24-hr,  continuous  air samples were
collected by a SCAQMD contractor  up-
and  downwind of the aerator. Based on
the model and ambient conditions,  the
downwind  sampler  was  located at a
distance  suspected of having the highest
concentrations of  TCE.  The  detection
level provided by the contractor was near
5.8 jig/L for TCE. A lower detection level
would have  required technologies not
routinely used by the SCAQMD. TCE was
not found in any of the samples. Because
these levels were appreciably higher than
the  21.8  ng/L  annual  average  TCE
concentration predicted  by the model
before the  construction  permit was
granted, model predictions  could not be
checked directly.

Noise
  With the aerator operating, noise levels
were near 80 decibels (dB) at the blower.
At a distance of 100 ft, however, levels
dropped to near 55 dB,  which was the
background level at that distance with the
aerator shut down. OSHA  restricts 8-hr
workplace noise to  no greater than 90 dB.

Costs
  The capital cost  of the  tower was near
$218,000.  This  included  connecting  of
the existing  reservoir and  the chlorine
and SHMP feed systems. The  amortized
capital cost  was $0.062/1000  gal.  O&M
costs,  based on  the 7-mo monitoring
period, amounted to $0.031/1000 gal.  A
comparison  of the capital cost of the
elevated  tower  versus a  wet  well and
repumping  indicated comparative  costs
within 10%.  This suggests that the total
cost of $0.093/1000 gal can  be con-
sidered representative of PTA facilities.

Conclusions
  The use of gas/liquid  mass transfer
theory together  with  pilot testing data
provided  for  the  design  of a  full-scale
PTA.  Factors such  as water distributic
over the packing, redistribution onto tt
packing, and changes in  packing  dep
can influence full-scale performance fi
control of VOCs. The secondary effec
observed during pilot testing were a goc
predictor  of  the  secondary  effed
observed during full-scale operation. Th
changes in water chemistry as a result <
aeration, such as pH,  DO, and C02, ma
affect calcium  carbonate  deposition  c
corrosion  of some  metals.  Corrosion <
mild steel and copper was insignificant i
these  studies; however,  SHMP wa
required to prevent deposition. Bacteri;
densities,  as  measured  by  SPC,  ir
creased as a  result  of  aeration,  bt
Legionella and coliform bacteria were nc
observed.  Moderate  levels of  chlorin
were  sufficient for  bacterial  contro
Aeration  had  no  significant  effect oi
waterborne particulates, water  tempera
ture, or ambient noise levels. The impac
of VOC  off-gas dispersion  and centre
must  be  considered. In this  study, m
TCE was found in air  at low part-per
billion levels  during tower operation
Modeling of PTA off-gases indicated TCf
levels  in  the low  part-per-trillion  range
which were not  significantly different thai
measured  ambient  TCE  levels. A PT>
total cost of less than $0.10/1000  gal a
2.9 mgd was demonstrated  and deeme(
cost-effective for VOC control.
  The  full  report was submitted  in  ful
fillment of Cooperative Agreement CR
809974 by James M. Montgomery Con
suiting Engineers,  Inc.,  under the spon
sorship of the U.S. Environmental Protec
tion Agency.

-------
 Mark D. Umphres is with  James  M.  Montgomery Consulting  Engineers,  Inc.,
  Pasadena, CA 91101; and James H. Van Wagner, now retired, was with the Valley
  County Water District, Baldwin Park, CA 91706.
 Richard J.  Miltner is the EPA Project Officer (see below).
 The complete report, entitled "An Evaluation of the Secondary Effects of
 Air Stripping," (Order No. PB 89-161 517I AS; Cost: $15.95, subject to change) will
 be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA 22161
        Telephone: 703-487-4650
 The EPA Project Officer can be contacted at:
        Risk Reduction Engineering Laboratory
        U.S. Environmental Protection Agency
        Cincinnati, OH 45268
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Official Business
Penalty for Private Use $300

EPA/600/S2-89/005
^^>w^^?
;          -\ °rl.--  i    «.  -» r ~l«
 ji&'.'VW    ';' j^o'ii  :" Q  3  -1 ~U
          / ) 3    i    W         (


-------