United States
Environmental Protection
Agency
Environmental Research
Laboratory
Duluth MN 55804
Research and Development
EPA-600/S3-83-061  July 1984
Project Summary
A  Simple  Transmission
Network Planning  Method:
Wisconsin  Power  Plant
Impact  Study

Farrokh Albuyeh and James J. Skiles
  This report describes a new model for
planning the expansion or modification
of transmission networks. The model is
different from traditional models which
employ mathematical optimization
techniques, in that it closely parallels
the logical steps followed in practice by
planning engineers. No claim is made
for the optimally of plans produced.
but they  will be similar to those
developed by planning engineers on the
basis of their working experience with
the system.
  The first step in analyzing a power
network is to  formulate a model  that
describes the components in the system
and how they are interconnected. A
classical network  reduction algorithm
models the system by simple equivalents.
focusing  attention  on parts of the
system that are of interest. Reliability
criteria for the network are translated
into a  series  of contingency studies
which the algorithm treats as pass-fail
tests. Sensitivity matrices simulate the
experience of  planning engineers. An
overload logic  then ranks the branches
of the network according to their
expected  effect on  the system,  and
performs a series of contingency
studies to find  the least costly changes
that will alleviate line overloads in the
network.  When no overloads remain,
the voltage correction logic checks for
deviations of the voltage from specified
limits and adjusts the bus reactive
power injections where necessary. The
program then advances to the next
planning period and repeats the entire
process.  A line  removal  subroutine
checks the usefulness of lines after
passage of a number of planning
periods and removes unnecessary lines.
  Sample planning studies indicate that
this method is applicable to practical
problems in large networks, and that it
will significantly  shorten and simplify
the planning process.
This Project Summary was developed
by EPA's  Environmental Research
Laboratory, Duluth, MN. to announce
key findings of the research project that
is fully documented in a separate report
of the same title (see Project Report
ordering information at back).

Background
  One of the most important areas to be
considered  in the planning of new or
expanded sites for generating electricity
is the accompanying modification of the
transmission network. The network must
be designed to carry electricity effectively
and economically, with a specified degree
of reliability, from the generating site to
the load centers. Constraints on the
network may limit or preclude develop-
ment of certain sites. Therefore, modifi-
cation of the transmission network must
be considered in  evaluating alternative
plans for expansion.
  This report  describes a new model,
unlike earlier models employing optimi-
zation techniques, for planning the ex-
pansion or modification of transmission
networks. It closely parallels the logical
steps followed in practice by planning
engineers. The  report contains the
following major parts:

  1.  Review of the basic concepts in
    power systems.

-------
  r
  2.   Review of load-flow studies and
      methods.
  3.   Review of methods for network
      reduction.
  4.   Review of methods for network
      planning and expansion.
  5.   Description of the proposed method
      and examples of systems studies
      based on it.
  6.   Appendices: mathematical deriva-
      tions for models, computer outputs
      for sample studies, and listings of
      programs for an AC model and a
      DC model.
  Planning expansion of the transmission
network is one of the most difficult parts
of an electrical network study. Mostofthe
problems relate to four factors:
  1.   The  large numbers of possible
      expansion alternatives.
  2.   The complexity of reliability criteria,
      which vary with the system and the
      utility company.
  3.   External cost variables, such as
      environmental  costs, that are
      difficult to quantify.
  4.   Uncertainties  in predicting  future
      power demand.
  Traditionally, plans for network expan-
sion  have been designed by the utilities'
planning engineers on the basis of their
work  experience with the system. The
system is expanded to satisfy specified
reliability criteria. Outages are simulated
on critical branches, and for  a predicted
load profile the network is expanded by a
standard procedure.
  Most  attempts to develop automatic
algorithms for planning  network expan-
sion  have treated the problem as one of
optimizing a performance index subject to
a set of equality and inequality constraints.
These techniques are difficult to evaluate
because few of them have been developed
beyond the experimental stage. Planning
engineers are  reluctant to use the
automated algorithms. Not only do plans
produced by automated methods  not
always match those developed by standard
engineering procedures, but "optimal
solutions" obtained from different models
and with different techniques differ from
each other. The method developed in this
report has been tested in several sample
cases and appears to be a practical tool
for the complex  and lengthy process of
planning expansion  of transmission
networks.

Review of Planning Models
  A typical power system is composed of
generating stations connected to load
centers  by a transmission network.
Transport of electricity can also take place
or from  other  power systems. The
transmission system generally has a
multiple loop structure with  several
multiple-interconnected voltage levels (in
contrast to the radial structure common
to distribution systems). The loop structure
permits flexibility in routing of energy on
various links and offers multiple path
combinations for contingencies.
  The  first step in  analyzing a power-
network is to formulate a model which
describes the characteristics of individual
components  in the system and how they
are interconnected. For computer appli-
cations, network matrices provide an
accurate and convenient way of repre-
senting network models.
  Load-flow  calculations are performed
during planning, operation, and control
phases of power system studies. Digital
computers have replaced  the earlier
"network  analyzers"  in  these  studies.
The load-flow problem is solved with a set
of nonlinear equations that describe the
steady state  performance of the system.
The  principal  information that  such a
solution yields is  the magnitude and
phase  angle of the voltage at each bus
and the real and reactive power flowing in
each line. The report discusses several
so-called Y-bus methods for solving load-
flow problems.
  The report also reviews four techniques
for network reduction. These techniques
simplify non-essential parts of the
network so that the planner may focus on
those  parts  of the network that are of
interest.
  Planning studies for expansion of power
systems can be divided into four steps:
forecasting loads,  planning  generation
capacity, planning transmission networks,
and planning distribution  networks.
Planning has traditionally been treated as
a problem in mathematical optimization.
The  techniques employed include heu-
ristic  methods, linear programming,
nonlinear programming, dynamic pro-
gramming, and integer programming.
The report describes the major features of
these  methods.  All of them require a
mathematical model of the system and a
statement of the problem  in terms of
mathematical optimization of a perform-
ance index or cost function. The major
differences  among present automatic
network planning techniques are in their
methods of optimization.
  None of the earlier methods has so far
led to a practical solution. This failure
may be caused by the large number of
variables that are difficult to quantify and
predict, such as costs and environmental,
political, geographical,  social, and tech-
nical constraints. The  various methods
are  nearly impossible to evaluate and
compare because few of them have been
developed beyond experimental  stages
and the demonstrations  that have  ap-
peared represent systems of very limited
size.

The Proposed Model
  The algorithm developed in this report
divides the problem into three parts:
modeling the  network, contingency
analysis, and expansion logic. In modeling
the network, a classical network reduction
algorithm  is used to model  the external
system by simple equivalents and to let
the planner focus on the areas of interest.
Two different modeling techniques  are
utilized: DC modeling and AC modeling.
In the  DC model, the network is repre-
sented  by a DC power flow  method
whereas in the  AC model the network is
modeled by a decoupled AC power flow
model.  For contingency analysis an
automatic contingency selection method
using network sensitivity  matrices is
developed. This technique  selects only
the contingencies that are critical  and
avoids  having  to simulate  all possible
contingencies.  The  expansion  logic is
composed  of an overload  logic and a
voltage correction  logic. The overload
logic uses the sensitivity  matrices to
identify the  most  economical  set of
branch  reinforcements and the voltage
correction logics determines that reactive
power  adjustments at buses to  correct
voltage level violations. The voltage
correction logic is used  in conjunction
with the AC model only.
   Before a planning  study for the trans-
mission network begins, the sites, sizes,
and dates of future additions of generating
capacity will be tentatively planned.  The
following data are needed:
   1.  Descriptions of the existing trans-
     mission system.
   2.  Forecasted load profiles for  the
     entire planning period.
   3. A list of potential rights-of-way,
     specifying their lengths, constraints,
     and the  particular transmission
     facilities they can accommodate.
   4.  Impedances, shunt capacitances,
     and capacities of  available new
     transmission facilities, together
     with data on their cost.
   5.  Operating constraints for the sys-
     tem, which are strongly influenced
      by limitations in transmission.
   6.  Legal, environmental, and political
      constraints.
   7.  Reliability criteria.

Sensitivity matrix
   The sensitivity  matrix J is an r x r full
matrix, where r is the number of branches.

-------
Each element Ju is the ratio of the branch
phase angle difference Af, to the branch
capacity
Contingency analysis
  The  expanded network must satisfy
prescribed reliability criteria. In planning
studies, these criteria are translated into
a series of contingency studies and are
treated as pass-fail tests. The network is
to be designed  to withstand any single
line outage with no cascading overloads
for the given load and generation profile.
Multiple contingency tests are made by
removing lines or generators one by one
and  proceeding  as with  the single
contingency test.
  An automatic contingency selection
method has been implemented to select
critical branches and thus reduce the
number of contingency cases studied.
  For every branch, a number is calculated
showing the relative effect that removal
of Ymax  units of susceptance  from that
branch will have on the system.
  The Effect Indices are then used to rank
branches  according to  their expected
effect on the system. The magnitudes of
the Effect  Indices indicate the expected
effect that the  removal of the largest
capacity line from the branch  may have
on the  system.  For contingency studies,
the branch with  the largest Effect Index is
outaged first. The results of the load flow
are checked  for overloads. Then, the
branch with the next largest Effect Index
is outaged. This process is repeated until
no overloads  are observed over several
successive contingency cases. Different
stopping criteria may be used. Tests on
the IEEE 14  Bus Test System and the
Wisconsin Upper  Michigan  System's
reduced network show that with the
stopping criterion of "no overloads over
four  successive  outages" the results are
identical to those  obtained  using an
exhaustive contingency checking ap-
proach.
Cost vector
  The total cost of adding capacity on a
branch  is  a function  of capital cost,
operating cost, and environmental cost.
Because many environmental (including
social and  political) costs  cannot be
quantified,  the environmental cost is
usually treated as a "go" or "no go" type
of factor. It can be assigned an arbitrarily
large value for a particular right-of-way in
order to exclude that right-of-way from
consideration by the automatic expansion
algorithm.  Methods  are needed  for
assigning  realistic  dollar  values to
environmental costs so that the model
 can treat these costs as it does conven-
 tional capital and operating costs.

 The expansion logic
   The planning logic is divided into two
 parts:
   1) The Overload Logic
   2) The Voltage torrection Logic
   The overload logic utilizes the sensitivity
 matrices to find the least costly network
 changes to alleviate line overloads. This
 is a simple approach and can be classified
 as  a  heuristic method that  treats the
 problem as a sequence of unconstrained
 minimization problems.
   There are two assumptions made:
   1)  Transmission capacity of a branch
       can be  increased by adding lines
       only.
   2)  Only specific type  of lines or
       voltage  levels that are provided to
       the  program can be used in ex-
       panding the system.
   In the  absence  of  an  input table
 containing  types of lines to  be chosen
 from,  the  line types already existing on
 rights-of-way  are  used during the  line
• selection process.

 The voltage correction logic
   The voltage correction logic is initiated
 after all line overloads are alleviated. The
 steps are as follows:
   1)  The contingency tests are carried
       out  and a  vector is  formed that
       shows the largest voltage magni-
       tude deviations from  the specified
       limits for every  bus during  the
       contingency tests.
   2)  From the  reactive  power flow
       equation, the  adjustments to the
       bus reactive powers needed to
       bring the  voltage  magnitudes
       within  the  specified limits  are
       calculated.
 Line removals
   As the network is developed through
 successive planning periods, lines added
 in earlier periods may become unneces-
 sary. Therefore, a subroutine was devel-
 oped to test the possibility of removing
 lines from the  system. A line removal
 program checks the usefulness of lines
 after passage of a number  of planning
 periods and removes unnecessary lines.
 This algorithm  may be viewed as the
 reverse of contingency analysis, in that it
 tests the results of removing branches
 having the least effect on the system.


 Planning studies
   Several sample planning studies were
 carried  out  using  network data for  a
model of the Pacific Northwest System,
the IEEE 14-Bus Test System, and a 26-
bus model of part of the Wisconsin Upper
Michigan System. These are presented in
the Appendices of the full report. Where
real data were unavailable, arbitrary
values  were assumed. In practice, the
planning engineer would have access to
the necessary data and would be able to
use the  computer  programs developed
here to solve real, practical problems.

Conclusions and
Recommendations
1.  A simple  automated method for
    network expansion has been devel-
    oped. It is especially suited for studies
    of alternative schedules for expanding
    the  generation and transmission  of
    electricity.
2.  The steps in the algorithm follow the
    logical steps carried out in practice by
    planning engineers.
3.  No claim is made for the optimality of
    the  plans produced by this method,
    but they will be similar to those
    obtained by planning engineers and
    the  automated method will shorten
    and simplify the planning process.
4.  The method has three new features:
    a.  A network  expansion technique
       which  uses sensitivity matrices
       to obtain economical  plans.
    b.  Use of the "B" matrix from the
       fast-decoupled load-flow algorithm
       in an  iterative procedure for
       adjusting bus reactive power to
       bring voltage within specified
       limits.
    c.  An automatic contingency se-
       lection procedure  that ranks
       branches  according to their
       expected effect on the system,
       thus reducing  the number  of
       contingency studies required.
5.  Of  the two models developed, the
    non-iterative DC model  is  simpler
    and faster and convergency difficult-
    ies  do not occur with  certain  ill-
    behaved networks.  The AC model is
    more realistic and more flexible. It
    uses a more accurate network model
    and it provides information on voltage
    magnitudes as well as on load flows.
6.  Interaction between the planner and
    the program is not only possible but
    necessary:
    a.  New, updated information should
       be fed into the program regularly.
       The program cannot be expected
       to give satisfactory results over
       many planning periods unless it
       "knows" everything the planning
       engineers know.

-------
     b.  A variety of generation and load
         schedules should be considered
         for the network under study.
     c.  Various ratings of network com-
         ponents should  be considered:
         for example, emergency ratings,
         normal summer, normal winter,
         etc. Ratings on other components
         such as breakers or line traps
         may also limit  the flow in  a
         branch.
     d.  The reliability criterion incorpo-
         rated in the program is a single
         contingency  criterion. The user
         might  want to examine other
         contingency cases. Generator
         outages and multiple line contin-
         gencies can also be simulated.
     e.  The program cannot introduce
         either new nodes or new rights-
         of-way into  the system. The
         planner can  represent potential
         but initially unusedrights-of-way
         as lines of high impedance, and
         potential  but initially unused
         nodes as nodes connected to the
         network by  potential  rights-of-
         way.
      f.  If  abnormal  plans  result, the
         planner should consider alterna-
         tives  such as lines  of higher
         voltage, changes in transformer
         taps,  or  additional  lines for
         voltage support.
  7. Several avenues for future research
     are apparent:
     a.  Further work on the  load-flow
         algorithm  should include trans-
         former tap changing under load.
     b.  Combining network reduction
         and network planning into one
         program would  overcome the
         need for multiple editing programs
         and  relax restrictions  on the
         system size.
          c.  The program should be modified
              to  include other techniques for
              network reduction.
          d.  Research is needed to implement
              sparse  matrix techniques in the
              planning programs.
          e.  Continued efforts are needed to
              quantify the broad range of
              environmental and social costs of
              transmission networks.
          Farrokh Albuyeh and James J. Skiles are with the University of Wisconsin,
            Madison, Wt 53706.
          Gary E. Glass is the EPA Project Officer (see below).
          The  complete report, entitled "A Simple Transmission Network Planning
            Method: Wisconsin Power Plant Impact Study," (Order No.  PB 84-199 553;
            Cost: $ 16.00. subject to change) will be available only from:
                  National Technical Information Service
                  5285 Port Royal Road
                  Springfield, VA 22161
                  Telephone: 703-487-4650
          The EPA Project Officer can be contacted at:
                  Environmental Research Laboratory
                  U.S. Environmental Protection Agency
                  6201 Congdon Blvd.
                  Duluth.MN 55804
                                             U.S. GOVERNMENT PRINTING OFFICE; 1984 — 759-015/7741
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Official Business
Penalty for Private Use $300
                              IL 60604

-------