United States
 Environmental Protection
 Agency
Air and Energy Engineering
Research Laboratory
Research Triangle Park NC 27711
Research and Development
EPA/600/S7-85/016 July 1985
Project  Summary

Economics of Retrofitting
Big  Rivers  Electric  Corporation's
Lime-Based  FGD  System  to
Organic-Acid-Enhanced
Limestone  Operations

Dennis Laslo, Norman Ostroff,  Richard Foley, and Donald G.  Schreyer
  In 1982-83, Peabody Process Sys-
tems, Inc. (PPSI) conducted pilot plant
tests at the R.D. Green Station of Big
Rivers Electric Corporation (BREC).
PPSI's final report of the pilot testing
included comparisons of the operating
costs of a lime-based full-sized
absorber, to a retrofit limestone system
enhanced with dibasic acid (DBA) or
adipic acid. The site specific changes
required for BREC to converttheir
existing lime FGD system to a lime-
stone system enhanced by DBA or
adipic acid, and the costs of making
such a change are described in this
paper. Results of this analysis indicated
that an annual cost savings of $2.6 mil-
lion could  be achieved by converting
the existing BREC lime system to an
adipic-acid-enhanced limestone sys-
tem, and an annual savings of $3.1 mil-
lion could be achieved by converting to
a DBA-enhanced system.
  This Project Summary was devel-
oped by EPA's Air and Energy Engi-
neering Research Laboratory, Research
Triangle Park, NC, to announce key
findings of the research project that is
fully documented in a separate report of
the same title (see Project Report order-
ing information at back).

Introduction
  In 1982-83, Peabody Process Systems,
Inc. (PPSI) conducted pilot plant tests at
the R.D. Green Station of Big Rivers
Electric Corporation (BREC). PPSI's final
report of the pilot testing included com-
parisons of the operating costs of a lime-
based full-sized absorber, toa retrofit
limestone system enhanced with dibasic
acid (DBA) or adipic acid. The economics
did not include the cost of new equipment
required to make the conversion. A
second project was funded by the EPA to
define the capital requirements neces-
sary for the retrofit, thereby completing
the economic comparison.
  The existing R.D. Green Station has
two 240 MW boilers that use an Ameri-
can Air Filter (AAF) flue gas desulfuriza-
tion (FGD) system employing  a spray
tower absorber and dolomitic lime as a
reagent. Dolomitic lime enhances SO2
removal efficiency by accumulating dis-
solved alkalinity (MgSO3), allowing a rel-
atively low liquid-to-gas ratio (L/G) to be
used for the system. Adipic acid and DBA
enhance the performance of limestone
scrubbing systems such that a mixture of
limestone and DBA or adipic acid may be
substituted for lime with minor changes
to an existing FGD system.
  This report addresses the site specific
changes required for BREC to convert
their existing lime FGD system to a lime-
stone  system enhanced by DBA or adipic
acid, and the costs of making such a
change. Results of this analysis, which
was based on site specific capital and raw
material costs, indicated that an annual
cost savings of $2.6 million could be

-------
achieved by converting the existing lime
system to an adipic acid enhanced lime-
stone system, and an annual savings of
$3.1 million could be achieved by con-
verting to a DBA-enhanced system.


Required Process Modifications
Prediction of Full-Scale SO2
Removal Efficiencies with
Limestone/Organic Acid
  The BREC pilot plant test results could
not be used to predict SO2 removal effi-
ciencies for the full-scale spray tower
because  wall effects reduced the spray
zone mass transfer effectiveness for the
pilot plant operations. An attempt was
made to compare the existing BREC spray
tower performance to that of the 10 MW
Shawnee spray tower. Typically, larger
diameter spray towers are more efficient
than the  10 MW Shawnee spray tower;
consequently, use of the 10 MW data for
predicting full-scale performance should
be conservative.
  However, a direct comparison of the
operation of the full-scale BREC spray
tower to  the Shawnee operations could
not be made since much of the required
process  data (Mgt+concentration, pH,
L/G, inlet S02 concentration, and tem-
perature) were not available. For this rea-
son, semi-empirical equations (devel-
oped by Bechtel for limestone scrubbing
with adipic acid) were used to estimate
full-scale liquid pumping requirements
for achieving 90 percent S02 removal as
a function of inlet S02 concentration.
  Adipic acid and liquid pumping require-
ments for the retrofit were calculated for
several inlet SO, conditions. Increased
L/G rates would be obtained by increas-
ing the rpm of the existing recycle pumps
to the capacity  of  the existing motors.
Calculation results showed that, even at
the highest sulfur coal, there is sufficient
pumping capacity for  meeting com-
pliance when 3,000 ppm of adipic acid is
used.
Basis  for  Retrofit  Equipment
Design
  The  ultimate coal analysis typical of
coal burned at BREC was used as a basis
for combustion  calculations,  which
assumed an excess air rate of 50 percent
and a coal feed rate of 277,000 Ib/hr*
which  were  consistent with operating
conditions measured in a series of test to
evaluate the performance of BREC's ESP.
Combustion calculation results were also
consistent with  measured  values and
were thus used as the basis for perform-
ing material  balance calculations  to
establish required equipment sizes.

Retrofit Equipment Required
  The existing lime system would be con-
verted by  utilizing  as  much  existing
equipment as  possible. Only a  ball mill
and organic acid feed system will  be
added. No changes to the absorption por-
tion of the system were required.
  An existing equipment list of the BREC
FGD system was prepared jointly by PPSI
and BREC. A site visit was made by PPSI
engineers to determine possible use of
existing equipment in the limestone ret-
rofit and to locate sites  for new equip-
ment  construction.
  Existing lime silos will be used to store
coarse  limestone;  however, the  lime
slakers will  not be  operated. Three  50
ton/hr* ball mills (one  spare) will  be
housed in an electrically  heated building
near the existing silos. DBA or adipic acid
storage and handling  facilities will also
be in  the ball mill area. Conveyors have
been  priced to transport  the  crushed
limestone from the storage silos to any of
the three ball mill  feeds. Supernate,
tapped from a  nearby 6 in.* line, will be
used  to slurry the  limestone,  and the
organic acid will also be added to the ball
mill. A crane was priced for new ball addi-
tion to the ball mill.
  Tanks, pumps,  and agitators for the
limestone/organic  acid  feed  system
*1 ton = 907 2 kg, 1 in = 2.54 cm..
                            were sized and priced based on  maxi-
                            mum coal feed rate and maximum sulfur
                            coal. Note that costs for an electrical sub-
                            station to provide power for the ball mills
                            were not included: BREC felt that suffi-
                            cient electrical  capacity  was  available
                            from existing equipment. If this substa-
                            tion were  included, it would raise the
                            capital costs by $52,000.

                            Process Conversion Costs
                             To provide cost comparisons of various
                            full-scale process  alternatives, a  base
                            case of BREC was calculated, using the
                            parameters of Table I. The typical operat-
                            ing load of 75 percent was obtained using
                            BREC-projected load demands  through
                            1995.
                             Potential process alternatives consid-
                            ered in this evaluation are:
                            - Limestone - with adipic acid addition.
                            - Limestone - with DBA addition.
                            Direct and indirect capital requirements
                            for new equipment are summarized in
                            Table 2.  Capital requirements are  based
                            on equipment sizing for 100 percent load
                            and maximum  sulfur. The ball mills are
                            very  conservative  since  the limestone
                            work index supplied by BREC for a typical
                            quarry was 12. Other quarries were not
                            surveyed but finding a work index of 10 or
                            lower should not be difficult.
                             Operating costs shown in Table 3 were
                            calculated  based on typical conditions,
                            since  an  unfair  advantage for  lime-
                            stone/organic acid would result at maxi-
                            mum boiler load and coal sulfur. By using
                            a fixed capital recovery factor of 20 per-
                            cent, the annualized costs of  a lime-
                            stone/organic   acid  retrofit  and  the
   Table 1.
Parameters Assumed for Base Case Calculations
BREC's Green Station Unit No. 2
Plant Load
Module Gas Flow

Inlet SO2 Concentration
Lime Stoichiometry"
Lime Consumption
SO2 Removal Required
L/G (max.)
L/G (current)

   CURRENT
Recycle, Module A
Recycle, Module B
Operation
Cake Solids
                     205 MW
                      1,525.000 Ib/hr/tower
                     or 383.000 acfm/modu/e '
                     2,550 ppm wet
                      1.02
                      12 tons/hr
                     90%
                     57
                     41
                      14,900 gpmc
                      16,500 gpm
                      7,560 hr/yr
                      42.0%
•1 lb = 0454kg.
  1ft3 = 28.3 L
  Moles Ca per mole S02 absorbed.
 C1 gal. =3.79 L.

-------
Table 2.    Cost Estimate Summary, BREC Limestone/Organic Acid Retrofit

                               (1982 Cost Basis/

                                          Direct Investment ($ 1.000s)
                            Limestone/Adipic Acid
                                                    Limestone/DBA
Description
Foundations,
Site Preparation
Buildings
Structural Steel
Tank Heater
Process Tanks
Limestone Preparation
Pumps & Drives
Machinery
Insulation
Piping & Valves
Instrumentation
Electrical
Painting
Freight
Material
50

170
94

4
2,145
18
30

105
115
173
1
25
Labor
50

77
56

2
736
4
12

65
30
108
4

Total
100

247
150

6
2,281
22
42

170
145
281
5
25
Material
50

170
94
1
24
2.125
18
30
6
105
115
173
1
25
Labor
50

77
56
1
8
126
4
12
6
65
30
108
4

Total
100

247
150
2
32
2.251
22
42
12
170
145
28 1
5
25
 Total Direct Costs
               2,930      544      3.474     2,937     547

                               Indirect Investment ($ 1,000s)
                                    existing lime system were compared. The
                                    results shown in Table 4 indicate a yearly
                                    savings of $2,642,000 for limestone with
                                    adipic acid and $3,153,000 for limestone
                                    with DBA. These results would be differ-
                                    ent for  other locations due primarily to
                                    variation in the cost differential between
                                    lime and limestone.
                          3,484
Start-up Expenses
Field Expenses
Vendor Salary
Vendor Expenses
Vendor Overhead
Contingency
Vendor Profit @ 15%
Total Indirect Costs
Total Cost


100
20
100
117

337

10
20
20

20
22

92

10
20
120
20
120
139
585
1.014
4.488


100
20
100
117

337

10
20
20

20
22

92

10
20
120
20
120
139
587
1.016
4,500
Table 3.
 Operating Cost Summary - Typical Operating Conditions3BREC Limestone/Or-
ganic Acid Retrofit

                                       (1982 Cost Basis)

                                   First Year Cost ($ 1,000s)
                                   Lime    Limestone/Adipic
                                                      Limestone/DBA
Alkali
   Lime @ $60/ton                 5,856
   Limestone @ $6.50/ton
   Additive
Utilities
   Electricity @ $0.01369/kWh         215
                                      1.222
                                        931

                                        378
                     1.222
                      418

                      378
 Total
                        6.071
2,531
                                                                     2,018
 Savings Compared to
 Lime System
                                      3,540
                    4,053
" Typical Operating Conditions:
 Firing Rate - 100 tons/hr per boiler
 3.0% sulfur coal
 Lime Stoichiometry = 1.O2 mole CaO/mole S02 removed
 Limestone Stoichiometry = 1.05 mole CaCO3/mole S02 removed

-------
    Table 4.    BREC Limestone/Organic Acid Retrofit Projected First Year Cost Differential for
              Conversion from Lime
                                     (1982 Cost Basis)

                                          Limestone/A dipic     Limestone/DBA
New Investment
Annual Charge @ 20% ($ 1.000s)
New Annual
Operating Costs ($ 1.000s)
Total
Annual Savings
SI, OOOs
mills/ kWh
898
-3.540
2.642
0.927
900
-4.053
3.153
1.106
    D. Laslo. N. Ostroff, R. Foley, andD. Schreyerare with Peabody Process Systems,
      Norwalk, CT 06851.
    J. David Mobley is the EPA Project Officer (see below).
    The complete report, entitled "Economics of Retrofitting Big Rivers Electric
      Corporation's Lime-Based FGD System to Organic-Acid-Enhanced Limestone
      Operations," (Order No. PB 85-191 146/AS; Cost: $8.50, subject to change)
      will be available only from:
            National Technical Information Service
            5285 Port Royal Road
            Springfield,  VA22161
            Telephone: 703-487-4650
    The EPA Project Officer can be contacted at:
            Air and Energy Engineering Research Laboratory
            U.S. Environmental Protection Agency
            Research Triangle Park, NC 27711
United States
Environmental Protection
Agency
                        Center for Environmental Research
                        Information
                        Cincinnati OH 45268
Official Business
Penalty for Private Use $300
EPA/600/S7-85/016
OOOC329    PS
U  S  ENVIR  PROTECTION  AGENCY
REGION  5  LIERA
2^0  $  DEARBORN
CHICAGO
                                  STREET
                                     It-

-------