United States
                     Environmental Protection
                     Agency
Water Engineering Research
Laboratory
Cincinnati OH 45268
                      Research and Development
EPA/600/S2-85/005  Mar. 1985
<>EPA           Project Summary

                      Liquid Waste  Composting
                     James C. Patterson and John R. Short
                       This research project was conducted
                     at the Chesapeake and  Ohio Canal
                     National Historical Park to examine the
                     feasibility of adapting and  using the
                     sludge composting technique to com-
                     post liquid waste collected in National
                     Parks. This study evaluated the com-
                     posting of two problematic  liquid raw
                     wastes—sanitary toilet pumpings and
                     septic tank pumpings (septage). Effec-
                     tiveness of the process was  character-
                     ized by measuring indicator organisms
                     destruction,  nutrient transformations,
                     heavy metal content, and temperature
                     and oxygen variation. Effective destruc-
                     tion of pathogenic microorganisms was
                     achieved by  temperatures in excess of
                     55° obtained  within the  composting
                     pile.
                       The system was  costly on  a unit
                     volume basis, but costs were reasonable
                     when the value of  the compost was
                     considered. The process provided thor-
                     ough waste  treatment without costly
                     equipment and specialized construction.
                       This Project Summary was developed
                     by EPA's Water Engineering Research
                     Laboratory, Cincinnati, OH, in coopera-
                     tion  with the U.S. Department of
                     Interior's  National  Park  Service, to
                     present key findings of the research
                     project that is fully documented in a
                     separate report of the same title (see
                     Project Report ordering information at
                     back).

                     Introduction
                       The National Park Service Chesapeake
                     and Ohio Canal National Historical Park
                     (C&O Canal) was faced with a serious
                     waste disposal problem in 1975. Several
                     years prior to 1975, pit  toilets were
                     replaced with sanitary tank-type or port-
                     able toilets from which raw wastes had to
                     be pumped and disposed of to municipal
                     treatment facilities. For a period of time.
waste disposal at local municipal plants
was permitted; however, without warn-
ing, the C&O Canat was refused further
disposal privileges. A thorough investiga-
tion of alternatives led to the selection of
the aerated static pile composting system.
A major question to  be addressed was
whether a liquid waste material, at that
time estimated to be greater than 95%
liquid, could be successfully composted.
It was decided in 1976 to initiate a pilot
project and evaluate the feasibility of
composting sanitary toilet waste.  As
composting efficiency was obtained, the
C&O Canal decided to investigate com-
posting of a blend  of septic tank waste
(septage) and sanitary toilet waste. This
also proved successful.

Materials and Methods
  Pile construction began with a mixture
of wood chips, sawdust,  and  previously
composted material.  This mixture was
used as a bulking  agent to absorb the
large percentage of liquid in  the waste
prior to composting. About 18 cu m(24cu
yd) of bulking agent  were  required per
3780 L (1000 gal) of  liquid waste. After
soaking, the bulking material was incor-
porated into a cone shaped compost pile
4.6 m (15 ft) in diameter and 2.7 m (9 ft)
high. Each pile  consisted  of a bottom
mattress of previously composted mate-
rial, a core of the waste-soaked bulking
material,  and an insulating blanket of
compost material. An oval of  perforated
pipe protected by wood chips was laid
between  the mattress and the bulking
material during  construction and was
connected to the intake manifold of a
blower, A damper between the pile and
the blower provided draft control.
  Monitoring and quality control at the
site were critical to accomplishing proper
composting. During the composting cycle
temperature and oxygen readings were

-------
taken daily at 48 locations within each
compost pile. The temperature was moni-
tored to ensure adequate pathogen de-
struction,  and  oxygen analyses  were
made to ensure adequate aeration.
  Weekly compost  samples were taken
from  internal pile  locations. To obtain
representative samples  without  major
disturbance of the  composting  mixture,
four access pipes were installed during
pile  construction.  These access  pipes
were capped and covered by blanketing
materials to reduce heat loss during the
sampling procedure.
  Compost piles were usually maintained
at a minimum of 55°C for 4 weeks to
ensure good breakdown of organic mate-
rials and adequate  destruction of patho-
gens. Longer periods could be maintained
if desired, and some remained for up to 7
weeks. Generally,  active  compost piles
were maintained for a standing period of
4 weeks to ensure a pathogenically safe
end product. Active  composting was
followed by a  3-  to  6-month storage
(curing) phase before using the product.
Results
  The  raw waste and  final compost
characteristics are presented in Tables 1
and 2, respectively. These data are means
of measurements from  three compost
piles for each type  of waste. The  raw
waste values  are for the liquid waste as
applied to the bulking material, and the
final compost values are for the product of
8 weeks of composting.
  Both wastes showed a wide range in
the level of measured parameters' vari-
ability of the  wastes as  generated. The
septage had  generally  lower levels for
most of the measured parameters. How-
ever,  the  heavy metal  content of the
septage was higher, probably due to the
use of  household products containing
heavy metals.
  Samples taken from the sanitary toilet
waste  composting piles  indicated  that
total coliform  and fecal coliform levels
dropped to less than 3/gram between the
second and third week of composting for
all pile locations. By the  third sampling
cycle,  and throughout  the additional
samplings, organism counts remained at
these low levels.
  The  first  compost pile  constructed
(using  only septage} did not perform as
anticipated. Temperatures were generally
lower and the oxygen percentages vari-
able. The second and third piles func-
tioned well with thicker  insulation and
longer aeration time.
Table 1.
Raw Waste Characteristics
                                        Table 2.    Final Compost Characteristics

Parameter
BOD
COD
Total Coliforms
(MPN/g)
Fecal Colilforms
(MPN/g)
Salmonella, sp
(neg. or posj
Total Solids <%)
Total Volatile
Solids (% of
Total Solids)
pH
Soluble Salts
Total Kjeldahl
Nitrogen
Total
Phosphorus
Total
Potassium
Cadmium
Copper
Lead
Nickel
Zinc
Sanitary
Toilet Waste
9.700*
33,000

830

810

neg.
2.5


53
7.7-8.2
3,300

160.000

4,500

3,300
1 5
230
31
7.3
41O\
Septage
Waste
2,900
15,000

3,700

1,600

neg.
1 7


59
5.9-6 5
280

13.000

3,000

160
1.8
520
63
12
420

Parameter
Total Coliforms
(MPN/g)
Fecal Colilforms
(MPN/g)
Total Solids (%)
Total Volatile
Solids (% of
Total Solids)
pH
Soluble Salts
Total Kjeldahl
Nitrogen
Ammonium
Total
Phosphorus
Total
Potassium
Cadmium
Copper
Lead
Nickel
Zinc
Sanitary
Toilet Compost

<3*

<3
54


42
58-74
1,600

1 1,000
880

2,900

2,700
3.0
50
73
28
220
Septage
Compost

<3

<3
51


49
63-74
880

6,900
120

2,500

2,100
2.5
91
59
26
190
"All units are ug/l unless otherwise noted.
All values are
piles
means from three compost


*AII units are mg/l unless otherwise noted.
 All values are means from three compost
 piles.
}A zinc-based disinfectant was used in these
 toilets
  Analyses of indicator organisms during
septage composting indicated that when
proper  compost temperatures were
achieved, the maximum level of total
coliforms dropped to less than 3/gram
between the second and third week of
composting for all sample locations. Fecal
coliform concentrations achieved desired
levels by the second week. As was the
case with sanitary toilet waste compos-
ting, counts for both total coliforms and
fecal coliforms did not increase when the
septage compost piles were taken down
and moved to the storage pit.
  Temperature  monitoring  showed the
lowest temperature readings  occurred
within the blanket rather than within the
active composting medium. Low temper-
atures were expected around  the lower
sections of the pile because of sloughing
of the blanket materials and concentrated
air  movement  around  the pipe.  The
highest temperatures occurred at the top
of the pile and in the central core. The
compost temperature rose  above  55°C
within the first 5 days.  When compost
                             activity proceeded normally, temperatures
                             ranged  between 64° and 75°C  for a
                             lengthy period, ensuring a high degree of
                             pathogen destruction. Temperatures in
                             excess of 55°C have been maintained at
                             the C&O Canal for 6 to 7 weeks.
                               Oxygen data showed composting pro-
                             ceeded  well when the oxygen range was
                             5% to 15%; however, the preferred range
                             was 8% to 10%.

                             Costs
                               The cost of treating the waste material
                             generated during the 1 978 project period
                             was about $0.60/gallon. Thisfigure does
                             not include  land acquisition costs or the
                             local retail  value of the final compost
                             product. When the value of the compost
                             material was subtracted  from the total
                             cost, the net cost of treating the wastes
                             was $0.20/gallon. Labor and equipment
                             rental made up  about two-thirds of the
                             total costs.

                             Conclusions
                               The   aerated  static  pile composting
                             system  provided adequate treatment for
                             septage and sanitary toilet  pumpings.
                             Within  a 3-week  period, the waste-

-------
organic mixture  became  compost,  and
after a short storage (curing) period, the
compost became a valued organic soil
amendment. The system had the follow-
ing features: (1) little capital expenditure
was required when compared with tradi-
tional mechanical systems; (2) no full-
time onsite personnel were required; (3) a
minimum of equipment was needed; (4) a
high degree of waste stabilization was
achieved with little or no release of any
effluent; (5) the user was provided with a
highly flexible and efficient waste  recy-
cling alternative that was easily adapted
to remote sites, differing waste  loading
needs, and different organic wastes; (6)
wastes could be treated as they accumu-
lated  or stored until  treatment  was
needed; (7)  the product contained low
levels of coliform organisms; and (8) the
compost contained low levels of many
micro-nutrients and  was  an  excellent
organic soil amendment, which was used
on disturbed soil areas.
  The full report was submitted in fulfill-
ment  of Interagency Agreement No. 78-
D-X0298  by the Ecological  Services
Laboratory,  National Capital  Region,
National Park Service, U.S.  Department
of the Interior in cooperation with the U.S.
Environmental Protection Agency.
James C. Patterson and John R. Short are with the National Park Service, U.S.
  Department of the Interior, Washington, DC 20242.
Robert P. G. Bowker was theEPA Project Officer (see below for present contact).
The complete report, entitled "Liquid Waste Composting," (Order No. PB 85-160
  406/AS; Cost: $11.50, subject to change) will be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA22161
        Telephone: 703-487-4650
For further information Donald S. Brown can be contacted at:
        Water Engineering Research Laboratory
        U.S. Environmental Protection Agency
        Cincinnati, OH 45268

-------
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
    BULK RATE
POSTAGE & FEES PAIt
       EPA
  PERMIT No  G-35
Official Business
Penalty for Private Use $300
        OCOC329   PS

        U  S  ENVIR PROTECTION  AGENCY
        REGION  5  LIBRARY
        230  S  DEARBORN  STREET
        CHICAGO              IL

-------