United States
                    Environmental Protection
                    Agency
Water Engineering Research
Laboratory
Cincinnati OH 45268
                     Research and Development
EPA/600/S2-85/007 Mar. 1985
c/ERA         Project Summary
                    Technology  Assessment of
                    Sequencing  Batch  Reactors
                     Robert L. Irvine
                      The innovative and alternative tech-
                     nology provisions of the Clean Water
                     Act of 1977 provide financial incentives
                     to communities using wastewater treat-
                     ment alternatives that reduce costs of
                     energy consumption over conventional
                     systems. To increase awareness  and
                     implement such alternatives, the U.S.
                     Environmental Protection Agency's
                     (EPA)  Water Engineering Research
                     Laboratory  has  initiated  a series of
                     assessments intended to evaluate both
                     the current status and capabilities of
                     these technologies. This report provides
                     an analysis of one of these technologies,
                     the Sequencing Batch Reactor (SBR).
                      The SBR is a fill and draw activated
                     sludge system. Each tank in the SBR
                     system is filled during a discrete period
                     of time and then operated in a batch
                     treatment mode. If tank volumes and
                     aeration practices are properly designed,
                     the SBR can simulate any conventional
                     continuous flow activated sludge  sys-
                     tem. In a cost and energy comparison,
                     the cost of SBR closely compared with
                     that of the oxidation ditch and  was
                     roughly 20 percent less than that for the
                     conventional activated sludge systems
                     tested. As far as energy use  is con-
                     cerned, the SBR was 13.5 percent more
                     efficient than the oxidation ditch and
                     was the equivalent of the conventional
                     activated sludge systems.
                      This Project Summary was developed
                     by EPA's Water Engineering Research
                     Laboratory. Cincinnati, OH, to announce
                     key findings of the research project that
                     is fully documented in a separate report
                     of the  same title (see Project Report
                     ordering information at back).

                     Technology Description
                      The SBR, a type of periodic process, is a
                     fill  and  draw activated sludge  system.
Each tank in the SBR system is filled, one
after the other, during a discrete period of
time and then operated in a batch treat-
ment mode. After treatment, the mixed
liquor is allowed to settle and the clarified
supernatant is drawn. The tank is then
refilled after the remaining tanks in the
SBR systems have been filled.
  If the time required for a tank to fill is
very long when compared with the time
provided for batch treatment,  the SBR
behaves like a conventional completely
mixed  activated sludge facility.  If the
opposite is true, the SBR behaves like a
nominal  plug flow system.  A properly
designed SBR can simulate any conven-
tional  continuous flow  activated sludge
system. Each  SBR tank carries out the
functions of equalization, aeration, and
sedimentation in a time sequence rather
than in the conventional space sequence
of continuous flow systems, where these
functions are  carried  out in  separate
tanks.  Because the relative tank volumes
dedicated to, say, aeration and sedimen-
tation can be redistributed easily by
adjusting the mechanism that controls
the time (and, therefore, share of the total
volume) planned for either function, the
SBR is flexible. By working in time rather
than in space, the SBR can  be either a
labor-intensive, low-energy, high-sludge-
yield system or a minimal-labor,  high-
energy, low-sludge-yield system.
  Each tank in an SBR system undergoes
one or more cycles (i.e., the time between
one filling and the next) during each day.
The cycle of a typical SBR tank is divided
into five discrete periods—FILL, REACT,
SETTLE, DRAW, and IDLE (Figure 1).
  FILL:  During FILL, either raw waste-
water (screened and degritted) or primary
effluent is added to the activated sludge
remaining in the tank from the previous
cycle.  FILL  ends either when the tank is

-------
   Percent of:
   Max     Cycle
   Volume   Time
        Influent
      25
      to
     100
25
     100
              35

                                     Purpose/Operation
                                                                   Air
                                                                  On/Off
                                         Add
                                       Substrate
                                                                    Air
                                                                  On/Cycle
                                                      Reaction
                                                        Time
     100
              20
                                   Settle
                                                                  Air
                                                                  Off
                                                       Clarify
     WO
      to
     35
15
                                   Draw
                         Effluent
                                                    Air
                                                    Off
                                                     Remove
                                                     Effluent
     35
      to
     25
                                   Idle
                                                    Air
                                                   On/Off
                                                     Waste
                                                     Sludge
Figure 1.    Typical SBR operation for a complete cycle in one tank.
full or when a maximum time for FILL is
reached. The  wastewater flow is then
diverted  to  the  next tank  in the SBR
system. Although FILL time is shown to
be 25 percent of the total cycle time, a
range of 40% to 60% would  be  more
typical for a two-tank system and, in any
event, would more or less depend on the
extent of daily variations in the hydraulic
flow rate.
  REACT:  Reactions begun during FILL
are completed during REACT. Although
the liquid level appears to remain maxi-
mum, sludge  wasting  can  take  place
during REACT as a simple means  to
control sludge age, e.g., sludge age  in
                         days would be equal to the reciprocal of
                         the fraction of the maximum liquid volume
                         wasted each day. The total cycle time
                         dedicated  to REACT  can actually vary
                         from just greater than zero to more than
                         50 percent.
                           SETTLE:  During SETTLE, solids and
                         liquids separate. The time should  be
                         between 0.5 and 1 hour so that the sludge
                         blanket remains below  the withdrawal
                         mechanism during  DRAW and does not
                         rise (because of gas formation) before
                         DRAW is completed.
                           DRAW:  During  DRAW, the treated
                         wastewater is removed.  The percent of
                         cycle time can range from 5 to more than
30. DRAW cannot be overly extended,
however, because of possible problems
with rising sludge.
  IDLE:  The IDLE period can be used to
waste sludge from the system. Otherwise
IDLE is  simply that time that  must be
waited after DRAW for the last tank in the
SBR system to be filled before the tank in
question can be refilled, thus beginning a
new cycle.
  An SBR system consists of the head-
works, one or  more tanks,  an  aeration
device, a mechanism to withdraw waste-
water, and a control system. The influent
sequences from one tank to the next and
may be  either pumped in or allowed to
flow in  by gravity. When using gravity
flow, some device such as an adjustable
weir or automatic valve must be used to
divert the flow to one tank or the other.
  Theoretically, there's no  limit  to the
size of each tank, or the number of tanks
used in the SBR system. The tank may be
an  earthen ditch, an oxidation ditch, a
rectangular  basin, or any  concrete or
metal structure.  Virtually any  aeration
system (e.g., diffused, floating,  mechan-
ical, or jet) can be used although a system
that separates mixing from aeration (e.g.,
as for the jet) and one that is not clogged
by having mixed liquor settle on it once
each cycle  would likely  be best.  The
withdrawal mechanism may be as simple
as  a pipe fixed at some predetermined
level (with the flow regulated by either an
automatic valve or a pump depending on
the hydraulic grade line of the system) or,
preferably, an adjustable or floating weir
at or just beneath the liquid surface. As
with the fixed  mounted pipe, discharge
from the weir can be regulated by an
automatic valve or a pump. Level sensors
and a timing device provide overall control
of the SBR.
  Because REACT, SETTLE, and  DRAW
take place after the  flow  has  been di-
verted, the SBR system with just one tank
would be quite unusual for a municipal
waste situation but not all that uncommon
for  day schools, amusement  parks,  or
industries that operate for 8 to 1 5 hours
each day with little or no flow generated
during the remaining hours. In a two or
more tank system, the time for REACT,
SETTLE, and DRAW in one tank must be
less than or equal to the time required to
fill the  other tanks  An SBR with three
tanks is probably the practical limit for
such systems. Although the total volume
(sum of all  tanks used) of an SBR de-
creases with the number of tanks em-
ployed, the incremental reduction is
minimal for greater than three. In addi-
tion, the complexity of operation increases

-------
as the number of tanks increases. As a
result, except under quite unusual circum-
stances, only one, two,  or three tanks
would be recommended.

Status of the
Developed Technology
  The retrofit plant in Culver, Indiana,
served as the first full-scale demonstra-
tion plant for SBR treatment of domestic
wastewater in the United States. At least
four domestic waste plants are in various
stages of design or construction: Juneau,
Alaska; Sabula, Iowa; LeClaire, Iowa; and
Poolesville, Maryland. An SBR-like facility
was started up  in July 1983 in Grundy
Center, Iowa.
  On the industrial side, Alphenrose Dairy
owns and operates a two-tank fill and
draw system in Portland, Oregon. A
single-tank SBR was reportedly used in
Ada,  Oklahoma,  to treat  wastewaters
from  a vehicle  maintenance area for a
utility company. A single-tank SBR for a
hazardous waste disposal site owned and
operated by CECOS International, Niagara
Falls, New York, began operation in June
1984, and Occidental Chemical Corpora-
tion  has designed a similar system to
treat its landfill  leachates in the Niagara
Falls area.

Process Capabilities
  The only full-scale SBR performance
data currently available is from the EPA-
funded research project completed at
Culver, Indiana.* Between May 1980 and
May  1981,  the Culver  SBR produced
average 5-day biochemical oxygen  de-
mand (BODs) and suspended solids (SS)
concentrations of less than 10 g/m3
each:
             Raw        Effluent
            Waste-   North   South
	       water'   Tank    Tank
BOD5, g/m3  160(152)  9+(147) 10*(144)
SS, g/m3    130(153)  7 (258)  9 (258)

*( ) = number of observations
'Effluent BOD5 measurements were conducted on
 prechlormation  samples Post-chlormation BOD5
 effluent averaged 5 g/m3 (143 observations)

Nitrification
  Because nitrification requires that  the
dissolved oxygen (DO) be greater than
approximately 0.5 g/m3, the aeration time
during FILL and REACT must be suffi-
ciently long and the DO  must be suffi-
ciently high to allow both the enrichment
of nitrifiers and the completion  of
am monia-mtrogen(NH4-N) oxidation. The
following data are from those 5 months of
the Culver study when nitrification was
achieved, August to Decembr 1 981 :
 Raw
Waste-   North
 water    Tank
                              South
                              Tank
NH4-N,g/m3   20(82)    11(79)   10(78)
SS, g/m3    150(94)    5  (94)   6  (94)
BOD5, g/m3  170(59)   11* (57)  10' (59)

"( ) = number of observations
'Post chlorinatron BOD5 effluent (August to December
 19811 = 7 g/m3

Denitrification
  Denitrification requires the DO to be
less than approximately 0.5 g/m3, the
presence of nitrite and/or nitrate nitrogen
(the sum of these two is reported in NOX-
N), and a carbon source for energy. A
mixing-only period of FILL with no oxygen
supplied and the organics in the waste-
water as the carbon source provides the
best  conditions for denitrification until
the oxidized nitrogen supply, left  in the
residual liquid after DRAW, is exhausted.
After all  available  NOX-N  is depleted,
however,  anaerobic reactions occur. To
prevent these conditions after achieving
denitrification, aeration during the later
part of FILL can be instituted. The follow-
ing denitrifcation data are also  from
August to December  1 981 :
              Raw
             Waste-
              water
                          Effluent
          North
          Tank
South
Tank
•Full-Scale Study of Sequencing Batch Reactors. R F.
 Irvine and L. H. Ketchum, Jr., EPA/600/2-83/020,
 NTIS No. PB83-183186, Municipal Environmental
 Research Laboratory, U.S. Environmental Protection
 Agency, Cincinnati, Ohio 45268.
 NOx-N, g/m3    20(80)* 13(81)   10(81)
 NH4-N +
  NOx-N.g/m3 22*       2.4       23

 *( ) = number of observations
 'Sum of averages of NH4-N and NO.-N


 Controlling Microorganism
Populations
  The types  of bacteria in SBR activated
sludge can be controlled by the treatment
plant  operator who can easily relax or
eliminate some of the selective pressures.
For example, the treatment plant operator
at Culver, Indiana, modified the aeration
and mixing scheme in such a way as to
encourage biological phosphorus removal
and minimize nitrification and denitrifica-
tion. During the subsequent  10-month
period, effluent phosphorus  concentra-
tions averaged less than 1 g/m3 without
addition of chemicals.
   In  every  SBR cycle,  microorganism
 selection pressures are quite severe—the
 mixed culture microorganisms are sub-
 jected to feast and famine as well as high
 and essentially zero DO conditions. Only
 a limited number of microorganisms can
 both  survive and compete in  this envi-
 ronment. In  a  conventional continuous
 flow activated sludge facility, population
 dynamics is largely influenced  by the
 unsteady state nature of the influent
 wastewater. By way  of contrast,  the
 unsteady state nature of the SBR opera-
 tion overwhelms variations in the waste-
 water and, thus, results in a more control-
 lable system.

 Process Limitations
   Two major limitations became apparent
 during the developmental stages of the
 SBR. (1) It is a noncontinuous flow system
 with no real operating counterpart in the
 United States.  This  significant  liability
 has been partially overcome with  the
 Culver demonstration. (2) SBR was per-
 ceived to have value only  in small sys-
 tems. Although a  limit  of 18,925 m3/d
 was considered reasonable for purposes
 of cost analyses in this  assessment, the
 author believes that there are no theoret-
 ical or technical reasons for any upper
 limit. System selection should be based
 on a cost-effectiveness analysis for each
 specific  application  and  the level  of
 reliability and consistency desired.
   Limitations of more concern  include
 the freezing of scum (if present) during
 winter operating conditions, the possibil-
 ity of high effluent SS of high mass loaded
 systems, and finally, the  possibility of
 developing through  improper  operation
 an organism  population that has  a large
 number of filaments.

SBR Cost and Energy

Cost Considerations
  A modular design was used to estimate
costs for SBR's operating at four different
average daily flow rates (Table 1).  A two-
tank system was used for the 379 m3/d
plant, and three-tank systems were as-
sumed for the remaining three daily flow
rates. In all  cases, size selection was
based on a 50 percent draw-off volume
and on a cycle  with  zero time in IDLE
when using a peak flow, which is  double
the average dry weather flow. A three-
tank system  was used  for the 18,925
m3/d  flow with  each tank composed of
four equal  sized modules. In  all other
cases, only one module was used for each
tank.

-------
  Energy Requirements
    Estimated energy requirements for
  aeration  and decanting for each  of the
  four SBR flow rates are:

           Energy Requirements (kWh/yr)
                      Table 1.
   Flow
   Rate
  (mVd)   Aeration
Decanting    Total
   379   33.1 x103
   1,893  12.4x10"
   3,785  24.9x10"
  18,925  12.4x106
4.1 x 103   37.2 x 103
37x10"   16.1x10"
6.6x10"   31.5x10"
3 7 x 106   16 1 x 106
  Cost and Energy Comparisons
    A cost and energy analysis comparing
  the SBR with oxidation ditch and conven-
  tional activated sludge systems for flow
  rates of 379, 1,893, 3,785, and 18,925
  mVd indicates similar costs for the SBR
  and  the oxidation  ditch, with the SBR
  being  slightly  less costly.  Costs  are
  roughly 20 percent less for the SBR than
  for the conventional  activated sludge
  systems compared. The energy analysis
  showed the SBR to be 13.5 percent more
  efficient  than the oxidation ditch  and
  equally as efficient as conventional acti-
  vated sludge. The  unique  fill and draw
  feature of the SBR permits its energy
  input to be widely varied without seriously
  impairing the effluent quality.
    The full report was submitted in fulfill-
  ment of Contract No. 68-03-3055, Roy F.
  Weston, Inc., by Robert  L. Irvine of the
  University of  Notre  Dame,  under the
  sponsorship of the  U.S. Environmental
  Protection Agency.
SBR Copt Estimates tin's 1,000) for Four A vervfye Daily Flow Rates
                                                                      Flow Rates (m3/d)
Process Unit,
Inlet control system'
Contact chamber baffle walls
Aerators
Excavation, concrete, handrail
Microprocessors
Level control/ monitor
Decant system
Subtotal (!)
. 379
$ 2
2
25
70
10
2
9
120
1.893
$ 3
, 4
50
150
10
4
16
237
3.785
$ 4
5
60
250
10
4
18
351
18.925'
$ 20
24
256
840
10
16
90
1.256
                      Noncomponent costs*
                          Subtotal (II)

                      Engineering, construction, supervision.
                        and contingencies^
                      Total installed capital
                      Annual operation and maintenance
                      Present worthy
                                                                                 30
                                                                                            59
                                                                                                      88
                                                            314
                             150
                              45
                             195
                              13
                             329
                                       296
 89
385
 24
632
                                                 439
132
571
 40
983
                    1.570
  471
2,041
  148
3,564
                       * At 25 percent of subtotal (I), cost includes piping, electrical installations, instrumentation, andsite
                       preparation.
                       \A 130 percent of subtotal (II).
                       \Present worth computed at 73/n percent interest rate and 20-year life (PWF - 10.29213). Add
                       present worth O&M costs to Total Installed Capital costs.
                          Robert L. Irvine is with the University of Notre Dame, Notre Dame, IN 46556.
                          Jon Bender is the EPA Project Officer (see below).
                          The complete report, entitled "Technology Assessment of Sequencing Batch
                          Reactors, "(Order No. PB85-167 245/AS; Cost: $11.50. subject to change) will
                          be available only from:
                                 National Technical Information Service
                                 5285 Port Royal Road
                                 Springfield. VA 22161
                                 Telephone: 703-487-4650
                          The EPA Project Officer can be contacted at:
                                 Water Engineering Research Laboratory
                                 U.S. Environmental Protection Agency
                                 Cincinnati, OH 45268
United States
Environmental Protection
Agency
                Center for Environmental Research
                Information
                Cincinnati OH 45268
                                                       BULK RATE
                                                  POSTAGE & FEES PA
                                                          EPA
                                                     PERMIT No. G-35
Official Business
Penalty for Private Use $300
         0000329   PS
         U S  ENVIR  PROTECTION  AGENCY
         REGION  5  LIBRARY
         230  S  OEARBCRN  STREET
         CHICAGO                It    €0*04

-------