United States
Environmental Protection
Agency
Robert S. Kerr Environmental
Research Laboratory
Ada, OK 74820
Research and Development
EPA/600/S2-85/016  Apr. 1985
Project  Summary
Optimization  of  Nitrogen
Removal  by  Rapid  Infiltration

E. R. Bennett, L. E. Leach, Carl G. Enfield, and David M. Walters
  The objective of this  research field
study was to evaluate the operational
methods for optimization  of nitrogen
removal in the rapid-Infiltration proc-
ess. Previous studies (1,2) at the same
site had showed a high degree of bio-
logical nitrification but essentially no
nitrogen  removal through denitrifica-
tion. A further objective of the study
was   to  evaluate  the  efficacy of
removal of other pollutlonal constitu-
ents under the operational conditions
necessary  for enhanced  nitrogen
removal.
  The rapid infiltration field site con-
sisted  of  three basins  with surface
areas of 0.36,  0.19 and  0.22 hectares
(0.87, 0.47 and 0.54 acres). The  beds
had approximately 3 meters (10 feet)
of granular  earth materials overlying
an  impermeable  shale  strata.  The
basins had underdrain pipes installed
just above the  shale base. Primary ef-
fluent from the City of Boulder waste-
water treatment plant was applied to
the basins utilizing hydraulic loading
rates  ranging  from   4.4   to 42
meters/year (IB to 140 ft./yr.). Three
types  of  loading  sequences  were
used: flood loading  every three and
one-half days, flood loading daily, and
sprinkler system loading based on soil
moisture  sensors  and   computer
analysis and control. The influent and
effluent  quality variations  were
measured over a three-year period and
the performance of  the system was
related to the operational parameters.
The  quality parameters utilized were
nitrogen (total, organic, Kjeldahl, am-
monia     and   nitrite/nitrate),
biochemical oxygen  demand,  total
organic  carbon,  suspended  solids,
total and fecal conforms, phosphorus.
and pH. Total nitrogen removals were
increased  substantially  over  the
previous studies. Under optimum con-
ditions,  sustained  removals  above
seventy-five  percent  were  achieved
with values  for individual  weeks  in
the mid eighty  percent  range.  In-
creased denitrification resulted from
maintaining saturated  soil conditions
for long periods, using low infiltration
rates and reduced hydraulic  loadings.
The  removal  of  phosphates was
shown  to be  directly related to a
critical  phosphorus mass  loading  of
3.0 Kg/Ha-d (0.3 gm/m'-d) that repre-
sented  the mineralization rate for the
soil chemistry of the field system.
Sustained  removals  greater  than
ninety-five  percent  were  achieved.
BOD and  TOC removals  were high
throughout the study  with most BOD
values above ninety percent.
  The project  report  is published  in
two volumes based on each  of the
two  loading  modes,  the  manual
loading  and the automated loading
system with computer control.

  This  Project Summary was devel-
oped by EPA's Robert S. Kerr Environ-
mental  Research Laboratory,  Ada,
OK, to announce key  findings of  the
research project that is fully docu-
mented in a separate report  of  the
same title (see Project Report order-
ing information at back).

Introduction
  The  high-rate land treatment  process
utilizing  rapid-infiltration beds  is   an
economically attractive,  low energy con-
suming  process providing a high degree
of pollutant removal for municipal waste-
waters.  When rapid-infiltration beds  are

-------
designed  with direct  discharge to  the
groundwater,  nitrogen  removal  through
soil adsorption, biological  nitrification and
denitrification  becomes one of  the  key
parameters in the design and operation of
the process.  In the earlier studies at the
same site,  it  was found that nearly com-
plete  ammonia conversion to nitrate was
accomplished  when applying either  pri-
mary  or secondary effluent but  that the
removal of nitrogen from  the wastewater
denitrification  was  relatively low, in  the
range of fifteen percent. Evaluations have
been  made  on  several  rapid-infiltration
sites  located in different  regions of the
country  and  the  results  have  been  re-
ported  in  the  literature.  In   general,
nitrogen removals in the range of thirty to
seventy percent have  been attained.
  This  research was  focused on evalua-
tion of  the operational conditions that in-
fluence conversion and  removal of  the
nitrogen forms in the treatment of primary
wastewaters.  In  addition, the treatment
efficiencies for  biochemical oxygen  de-
mand (BOD), total organic carbon (TOO,
suspended solids, coliform bacteria  and
phosphorus were evaluated under a range
of operating  conditions.
Conclusions
  Rapid-infiltration  treatment   utilizing
flood loading was shown to be capable of
removing seventy-five percent of the total
nitrogen  from  wastewater,  continuously
producing an effluent with a concentra-
tion of less than ten mg/l of N.  In addi-
tion,  under  reduced loading conditions,
effluent  total nitrogen  levels of  7 mg/l,
phosphorus of 0.5  mg/l  and BOD of 5
mg/l were attained.
  Nitrogen  removal  was  enhanced  by
creating reducing conditions in  the soil
system.   Maintaining   a   saturated  soil
moisture  condition with  long periods of
continuous  flooding  of the  basins  pro-
duced the highest nitrogen reductions. In
addition,  it was found that low infiltration
rates improved removals by increasing the
contact  time of  the water with  the soil
and by extending the periods of saturation
of the upper portion of the soil.  Lowering
the  mass loading rate  and the  hydraulic
loading  of  the  system reduced  the am-
monia leakage  from the system.
  The extent of phosphorus removal was
found to be correlated  to a distinct max-
imum mass loading of 3.0 Kg/Ha-d (0.3
gm/m2-d).  It  was  concluded that this
value  represented the  mineralization rate
for the soils employed in the study. When
loadings exceeded this  level, the  minerali-
zation reaction was not capable of regen-
erating the sites for the phosphorus ad-
sorption at a fast enough rate to maintain
a balance between the two reactions and
the treatment efficiency declined rapidly.
  BOD reductions were high for all  load-
ing conditions studied. A large portion of
the BOD was removed in  the  solids mat
produced  at the surface of the beds by
the accumulation of the solids present in
the primary effluent. BOD  removals  were
improved at lower  hydraulic loading rates.
  The rapid-infiltration  basins provided
major reductions in coliform bacterial den-
sities.  However,  the removals  were not
sufficient  to  meet  some  environmental
water quality  standards and  disinfection
processes may be a required part of the
process for discharging of  the effluent
into a stream.
  Weather-dependent  operational   prob-
lems  with the flood  loaded beds  were
minimal throughout the year. The use of
primary effluent did not create odor  prob-
lems. Operation of  the  sprinkler  loading
system  was  not  possible  when the am-
bient  air  temperature  dropped   below
freezing.
   Several  different loading rates and pat-
 terns were evaluated. The results for the
 best  conditions are  based on the four-
 weeks' result in  the maximum removals.
 Optimum  four-week  nitrogen removals
 were found  to  be seventy-seven  percent
 for the  flood loaded  beds  utilizing  the
 conditions of  daily  application of  4.67
 cm/day. Nearly the same optimum remov-
 al, seventy-six percent, was achieved with
 loading twice per week at a  rate  of 10.3
 cm/day.  In both  cases,  reducing  condi-
 tions were maintained  by  keeping  the
 beds flooded  over  for several weeks dur-
 ing  the   loading   sequence.  Nitrogen
 removals  were  somewhat less for  the
 sprinkler loaded system with  a maximum
 four-week value of sixty-five percent at  a
 loading rate of 3.84 cm/day. Phosphorus,
 BOD, and  suspended  solids removals
 were all greater when the sprinkler loading
 system was utilized.
   Several  conditions can  be defined  for
the rapid-infiltration system  studied  that
 resulted in an optimum operational range.
The optimization can be defined in terms
of  an operating range that will produce
the best combination of removals for four
constituents: BOD, phosphorus, ammonia
and nitrate. The effluent requirements for
a  rapid-infiltration  system  may  require
 removal  of some or all of  these constitu-
 ents.
   Enhanced BOD removals were found to
result   primarily   from   lowering  the
hydraulic  loading   rate  of the  system.
Phosphorus removals  were found  to be
high when the mass loading rates on the
long and  short  term were  less than the
mineralization  rate of the soil material.  In
this study the value was found to be 3.0
Kg/Ha-d (0.3 gm/m2-d). With an influent
wastewater  phosphorus  concentration of
approximately   7.5  mg/l,  the  hydraulic
loading  rate should not exceed about 4
cm/day (50 ft/yr,  1  gpd/ft2). Ammonia
leakage was also found to be reduced  at
low mass application rates. A value of 4
cm/day for the hydraulic loading rate was
also  found  to  be  advantageous for im-
proved nitrogen removal operating condi-
tions.

  While  lowering  the   loading   rates
enhanced  the  removals  of these  three
parameters, there  are two  factors  that
provide  the  lower   limit  of  hydraulic
loading that can be used for an optimum
system. One of these  is system cost, but
more importantly from the standpoint  of
performance is  that nitrate  removals  re-
quire a high enough loading rate to pro-
duce  saturated soil  conditions.  This  is
governed  by the grain size distribution  of
the soil and the infiltration rate through
the solids mat that forms at the surface of
the beds. In this research, it was  found
that it required approximately 1000 Kg/Ha
(10 mg/cm2. 0.022 Ib/ft2) of wastewater
suspended solids captured at the surface
to produce an infiltration rate low enough
for the continuous flooding of the bed
surfaces to create  reducing  conditions.
This  would  require  that the  beds  be
loaded for more than seven weeks at a
rate of 4 cm/day after each drying  period
before reducing conditions could be fully
reestablished.   It was  difficult  to  attain
these conditions during the low loading
rate phase of the flood loading studies on
bed  1 and the  sprinkler loading phase for
beds 2 and 3.  Two approaches could be
used  to improve  the system  operation.
Resting  periods,   without  scarification,
should be short to prevent drying out  of
the solids mat on the surface of the  beds.
New  designs  should  use  tighter,  more
organic soils with  high cation  exchange
capacities  in  order to reduce infiltration
rates and  enhance the  adsorption capacity
for ammonia and allow somewhat  higher
hydraulic  loading rates while maintaining
saturated  conditions. Shallow scarification
should be used only when the percolation
rate of the beds  cannot be  restored by
resting.  Compaction  of  the  soil  to a
prescribed Proctor  density could be used
after the scarification operation.

-------
Recommendations
  The nitrogen and phosphorus removal
mechanisms in land treatment systems are
dependent on the adsorption capacity of
the soil for these constituents and by the
regeneration rate  of the sorption sites by
biological   reactions  for   nitrogen   and
chemical   precipitation  reactions  for
phosphorus. Studies relating the proper-
ties of different soils with removal effec-
tiveness over  a range of  loading condi-
tions would provide a greater understand-
ing of the mechanisms of the treatment
process and  provide direction  for  the
selection  of the  land treatment location
for the design engineer.
  Nitrogen  removal  effectiveness  has
been  shown to be related to maintaining
saturated  soil  moisture  conditions  that
produced  the reducing environment.  Fur-
ther  development  of  the  operational
parameters  for   creating  optimal  soil
moisture conditions,  particularly with the
sprinkler  loading  method,  would   be
useful.
  Most rapid  infiltration  systems  have
been  designed  with the concept that the
effluent  percolates  to a  ground  water
aquifer.  The  alternate  system  utilizing
beds  designed  with underdrain pipes and
discharge to a surface stream, such as the
system used  in this research project, can
be  designed  to be  a  highly effective
means of providing advanced wastewater
treatment with a high degree of reliability
while requiring  low  energy  consumption
and  ease of  operation. The  underdrained
system concept  should be  developed fur-
ther  as a contained system for small com-
munities  or cluster home developments.

Facilities
  The rapid-infiltration system  utilized in
this field investigation was  located on the
site  of the 75th Street wastewater  treat-
ment plant in Boulder, Colorado. The 75th
Street plant  is  a  trickling filter  plant
situated  on  the  south  bank of Boulder
Creek.   Construction   of  the   rapid-
infiltration site was  accomplished  in the
spring of 1976. The site consisted of three
basins, designated one,  two, and three,
moving from south  to north.  The con-
figuration of  the beds is shown in Figure
1. The earth  materials in  the beds were
approximately three-meters  (10-ft)  deep
and  the  base material was  an  imperme-
able  shale strata. Earth berms, approx-
imately 0.8 meters (2.5 ft) high, separated
the basins, while a clay dike surrounding
                                                          Earth Berm with Clay Dike ,,
the entire basin area isolated the system
from  groundwater interference.
  The rapid-infiltration site was located in
the Piedmont section of Boulder County.
These deposits were composed  of  loose
sand,  loose  gravel,  and  clayey  sand
underlain  by  bedrock of oceanic origin.
Each  of the beds originally had approx-
imately 75 cm (2.5 feet) of finer textured
material  at  the  surface overlying coarse
sand  and gravel  in  the lower portion  of
the system. Prior to this study, 60 cm (2
ft) of the finer material was  removed from
beds  two and three so that  15 cm (0.5 ft)
of finer textured materials remained. All of
the beds had  twelve or more percent clay
and  two  and one-half percent  or  more
organic matter in the surface  layer.
  Primary  effluent  wastewater  was
pumped  through a  0.35 meter  (14 in.)
delivery pipe to  the  rapid-infiltration site.
Two  methods of bed loading  were used.
From December,  1980 to January,  1983,
the beds  were flood loaded.  During the
summer of 1982, a fixed sprinkler distribu-
tion  system  was installed  on beds  two
and three and this loading method was in-
itiated in January 1983. The system con-
sisted of a  network  of  10  cm  (4 in.)
diameter aluminum  irrigation  pipes  with
 Primary
 Clarifier
                                                            0.22 Ha. 0.54 Ac
                           Splitter Box
                         Valve
                                                                                    Surface Sprinkler System
                                                                                                                     Effluent
                                                                                                                    Sampling
                                                                                                                    Manhole
                 0.13 Ha, 0.47 Ac
                                                   Flood Loading Pipes

                                                                Bedl

                                                             0.35 Ha, 0.87 Ac
                         Trailer with
                       Sprinkler Pump
                                        18 cm dia. Underdrains

                                             O.O04 Slope
                      and Flow Controls
           N
Figure 1.    The rapid infiltration system layout.

-------
risers installed at 6.2 meter (20 ft) inter-
vals.  Rotating sprinkler nozzles were  in-
stalled at the top of the risers with  each
nozzle having a 4.4 mm (11/64 in.) orifice.
There were 13 rotating nozzles per  bed.
The spray loading system was designed to
operate at a gage pressure of 2585 mm of
Hg (50 psi). The pipeline from  the primary
clarifier to the beds was modified so that
it passed through a  trailer in  an inverted
"U"  shaped loop.  A tee was  installed in
the pipe so that the  flow  could be  di-
rected to the flood loading of the beds or
diverted to a separate pump and  valving
system  that would  allow  the sprinkler
systems to be operated.
  The primary purpose of  the sprinkler
system  was to use a  computer-operated
loading pattern  based  on  sensing  in-
struments  at   the  site to  control  the
moisture content of the soil  in order to
optimize the conditions for the nitrifying
and  denitrifying bacteria in the soil.  Each
bed  had three sets of  electrodes at 5 cm
and  30  cm  depths that  measured  soil
temperature.   Three   moisture-content
probes were also installed in each bed at
the  5 cm  depth. The temperature  and
moisture content data  were measured on
computer   command  and   sent   by
telephone to the control computer located
in  the  Robert S.  Kerr  Environmental
Research Laboratory  in Ada,  Oklahoma.
The  computer  was  programmed  to
analyze the data and  relay  a  signal  back
to the control trailer at the Boulder site if
the  spray  pumps  were to be turned  on
based on  the sensing  of  soil moisture
contents. The system was programmed to
be inoperable when  the temperature was
below -5°C  or when the  wind velocity
exceeded 56 Km/hr (35  m.p.h.). It was
also  possible  to  operate  the  sprinkler
system manually at the site.
  After the wastewater passed  through
the soil materials in the beds, it was col-
lected in an underdrain system consisting
of two perforated 18  cm (7 in) diameter
pipes running the length of each bed at a
soil depth of 2.5 to 3.2 meters  (8 to 10 ft),
just  above  the shale layer at  the  bottom
of the beds. The  line  from each of the
beds had V-notch weirs installed in the ef-
fluent sampling manhole  for flow  rate
measurements.
   For the first two years of the study, the
influent  pipe  led  directly to an  in-line,
totalizing,  propeller flow  meter  and then
to a distribution  spitter  box.  Lift  plate
gates were used to divert the  flow to bed
1, bed 2, or bed 3 during flood loading. In
the third year of the study, a section of
the  influent pipe was  removed,  reducers
were attached to each end of the remain-
ing pipe and a pipe was installed in a 'U'
shape, through  the  control  trailer and
back to the original pipe. The pipe had a
tee connection to a 7 cm (3 in) diameter
pipe which led to a shutoff  valve and the
sprinkler   pump.   The  pump discharge
branched  into  two pipes each  having  a
pressure actuated, rate of flow controller.
Each of the two  pipes exiting the control
trailer was connected to a  10 cm (4  in)
diameter aluminum irrigation pipe that led
to the west edge of  beds  2 and  3 and
continued down the center of the beds to
the east end. The ends of the irrigation
pipes  were capped  and  2  cm  (0.75  in)
diameter risers were installed at 6.2 meter
(20 ft) intervals.  Rotating sprinkler heads
at the top of the risers had  an application
radius  of  approximately 12.3 meters (40
ft).

Operation
  Two  effluent  samples,  acidified and
unacidified,  were taken at  the  outlet
streams of the individual beds in the ef-
fluent  manhole on intervals of 3,  7, 10,
24, 34, 48 and 72 hours after  loading was
initiated and effluent flows were measured
at each time. The acidified  aliquots were
used  for the  analysis of ammonia, total
Kjeldahl  nitrogen,  nitrate,   phosphorus,
and TOC. The unacidified volumes, taken
at effluent peak flow, were for pH, BOD
and suspended  solids analyses.  Special
grab  samples  of influent  and  effluent
flows were obtained  using  sterilized bot-
tles for the coliform tests and using nitric
acid  acidified  bottles  for  the  calcium,
magnesium, and  sodium series. All chem-
ical  analyses were   accomplished using
methods from Standard Methods for the
Examination  of  Water  and  Wastewater
(3), or Methods for Chemical Analysis of
Water and  Wastes (4), using blanks and
spikes for quality control.
  Nitrogen  removal   involved biological
nitrification  and  denitrification processes
and for this reason, wastewater treatment
plant  primary effluent was used as the in-
fluent  to the  process to provide an ade-
quate  carbon  source for  the biological
growth. Another  reason for  the use  of
primary effluent was  to  demonstrate that
rapid   infiltration  was  an  effective and
reliable means of achieving high removal
efficiencies  for  BOD, suspended  solids,
phosphorus and  other pollutional param-
eters  while  operating  in  a mode  intended
for optimum nitrogen removals.
  The research was conducted as a field
study using several different loading rates,
loading-resting patterns and two applica-
tion  techniques:  flood   loading   and
sprinkler loading. At times, the combina-
tion of these parameters did not result in
optimum conditions. For this reason,  the
time-concentration  curves  are presented
to  illustrate the  effect of  the  variables.
The  average   removal percentages  are
used to summarize the treatment achieved
by the rapid-infiltration process and values
for the best four-week period during  the
study are shown and give an indication of
the performance  that  could be expected
for a  system  operating continuously  at
near optimum conditions. Individual week-
ly  removal  percentages displayed  some
degree of variability, due to the changing
nature of the pollutional strength of  the
influent stream, which is typical of a field
study. For this reason, longer term  four-
week trends in removal percentages  are
more significant.
  During  the  study,  the  Boulder waste-
water treatment  plant was involved in a
major construction  project. Relocation of
the  rapid-infiltration   influent  pipe was
necessary and  this caused some down-
time  for  the  beds  which  was not a
planned part of the research. The  inactive
period for beds  2 and  3  during weeks
118-135 was caused by the construction
project.
  Three  different modes  of  wastewater
application were  used during the study.
Initially,  the beds had a target value  for
flood loaded of approximately 40 cm  (16
in.) of primary  effluent on  three and one-
half  day  intervals.   This  pattern  was
followed for the first 78  weeks of  the
study,  encompassing  the  period  from
December  of  1980  through  March   of
1982.  The  second   loading  sequence,
which involved  only  bed  1,  utilized a
lower loading  rate of approximately  5  cm
(2  in) of flooding  application  each day.
This was used from  April, 1982 through
February  of  1983.  The third mode,  the
sprinkler distribution system was ready for
use on  beds 2  and 3 after January,  1983,
and it was necessary  to  discontinue  the
research operation  of  bed  1 because  the
overflow of the sprinkler pumping system
was directed to  bed   1 and made  it  im-
possible to  maintain  a  consistent and
measured loading amount. The  sprinkler
system  operated from January through
December of 1983, although it was  inter-
rupted from March through June by  the
construction  in the treatment plant. The
average loading rates and loading patterns
are summarized in Table  1. The  loading
rate for the 3.5-day pattern averaged  123
ft/yr  based on  the weeks that loading  ac-
tually occurred. Resting of the  beds was

-------
necessary and occupied 28 percent of the
weeks of this portion of the study. The
overall average loading rate over time in-
cluding resting periods is given in Table 1 .
No intentional resting periods were util-
ized with the 1-day or sprinkler-system
patterns. Downtime periods caused by
construction in the wastewater treatment
plant were not included in the calculation
of loading rates.

Results
The average concentrations for the
rapid-infiltration bed influents and ef-
fluents, as well as removal percentages
for the total period of each loading mode,
are given in Table 2. Some of the meas-
ured chemical constituents of the waste-
water including pH, sodium, and mag-
nesium were essentially unchanged during
the rapid-infiltration process. The slight
increase in calcium probably resulted from
dissolving of calcium carbonate deposits
in the bed material.
Coliform removals were significant, but
relatively high concentrations remained in
the process effluents. The results of this
study show that the long-term use of
underdrained rapid-infiltration beds may
require disinfection of the effluent prior to
discharge into a surface receiving water.
The values shown in Table 2 include
periods of study when the variables tested
were not at optimum. In order to judge a
more optimized system performance,
Table 3 has been constructed with a sum-
mary of the removal percentages for the
important parameters shown and with the
efficiencies obtained under the best condi-
tion studied based on four continuous
weeks of operation.
The first ten weeks of the study were
not included in the selection of the best
four weeks of operation because the beds
had been rested for more than a year and
loading during this period did not repre-
sent normal operation.
The use of rapid-infiltration beds to
remove nitrogen from wastewater involves

me creation OT aerouic conoiuons ior
nitrification, and reducing conditions for
denitrification simultaneously or sequen-
tially in such a manner as to prevent
pulses of ammonia or nitrate from being
released in the effluent during any portion
of the loading and infiltration cycle.
The beds, which had been standing idle
for a year, were scarified prior to any
wastewater application. For the first ten
weeks of loading, the influent percolated
through the beds very rapidly. Infiltration
rates were high (>50 cm/d) and the bed
Table 1. Loading Depths



Operating Mode 1 23
flood (3'A day) flood (1 day) sprinkler
Loading rate, cm/d
including resting ft/yr
gal/d-ft1


Table 2. Average Constituent Concentration
Constituent Bed influent
Mode 1 (3% day)
Nitrogen
Ammonia-N 16.5 mg/l
Nitrate-N 0.27 mg/l
Organic-N 7.05 mg/l
Total-N 23.82 mg/l
T. Phosphorus-P 7.65 mg/l
BOD-5 101 mg/l
TOC 67.3 mg/l
Suspended so/ids 51.2 mg/l
Coliforms/ 100 ml
Total 58.5 x 10'
Fecal 13.4 x 10'
pH 6.85
Calcium 41.6 mg/l
Magnesium 21.5 mg/l
Sodium 56.6 mg/l

Mode 2 (1 day)
Nitrogen
Ammonia-N 13. 75 mg/l
Nitrate-N 0.36 mg/l
Organic-N 8.40 mg/l
Total-N 22.51 mg/l
T. Phosphorus-P 8,94 mg/l
BOD-5 54.5 mg/l
TOC 53.1 mg/l
Suspended solids 53.9 mg/l
Coliforms/ 100 ml
Total -
Fecal 14.3 x 10s

Mode 3 (sprinkler)
Nitrogen
Ammonia-N 17.85 mg/l
Nitrate-N 0. 13 mg/l
Organic-N 6. 76 mg/l
Total-N 24.74 mg/l
T. Phosphorus-P 7. 13 mg/l
BOD-5 80.4 mg/l
TOC 54.8 mg/l
Suspended solids 53.5 mg/l
Coliforms/ 100 ml
TV**a/
Total —
Fecal —


7.42
88.6
1.8


and Removals
Bed effluent

6.5 mg/l
1.85 mg/l
0.85 mg/l
9.20 mg/l
1.33 mg/l
8.8 mg/l
10.2 mg/l
14.7 mg/l

1.6 x 10"
0.65 x 10'
6.85
58.6 mg/l
21.5 mg/l
53.0 mg/l



3.23 mg/l
4.58 mg/l
1.06 mg/l
8.87 mg/l
0.53 mg/l
3.8 mg/l
6.7 mg/l
10.2 mg/l

—
0.93 x 10'


1.28 mg/l
10.50 mg/l
0.64 mg/l
12.42 mg/l
0.55 mg/l
2.2 mg/l
5.0 mg/l
6.0 mg/l




4.67
56
1.15



% removal

60
—
88
61
83
91
85
71

97
95
—
-41
0
6



77
—
87
61
94
93
87
81

—
94


93
91
50
92
97
91
89




3.84
46
0.95






































Table 3. Comparison of Three Loading Modes Average and Best 4-Week Results
Operating Mode 1
flood (3'A d)
% removal
avg. 4-week
Total Nitrogen 61 76
Total Phosphorus 83 87
BOD-5 91 91
TOC 85 85
Suspended solids 71 73
2
flood (1 d)
% removal
avg. 4-week
61 77
94 97
93 96
87 91
81 89
3
sprinkler


% removal
avg. 4-week
50
92
97
91
89
65
98
99.5
96
98

-------
effluents were highly nitrified but  with
less than forty percent nitrogen removal.
These results are shown as the beginning
of the time-history curves of Figure 2. The
results shown in  the figure are for bed 1
for the  first  120 weeks of flood loading
and for bed 2 with  manually controlled
sprinkler loading during weeks 109-117,
followed by an inactive period caused by
inplant construction during weeks 118-135
and  then  for  bed  2  with  computer-
controlled  loading  for  the  remaining
sprinkler loading period. The results of the
other beds were similar. The top curve on
each  graph shows the  loading rate  as a
                                          function of the week of loading. The next
                                          curve shows the infiltration  rate, and the
                                          third curve relates  the  total  nitrogen con-
                                          centration  of  the   influent  and  effluent
                                          (solid dark lines) and the ammonia nitro-
                                          gen concentration  of the influent and ef-
                                          fluent (lighter  solid lines) and the nitrate
                                          nitrogen  concentration  of  the  effluent
                                          (dashed lines). Nitrites were included in
                                          the nitrate measurements. Organic nitro-
                                          gen and  influent nitrate  nitrogen are not
                                          shown on the  curves except that they are
                                          included in the total nitrogen values. The
                                          bottom curves show the percent removal
                                          of total nitrogen.
>  20

•^  15

-------
total  nitrogen loading  of  24.5 Kg/Ha-d
(21.5  Ib/ac-d), caused an  overloading of
the system resulting  in continued increase
in  ammonia leakage  into  the effluent.
When the loading was  reduced to 17.0
meters/year  (55.8 ft./yr.)  with a  total
nitrogen  loading of  11.1  Kg/Ha-d (9.9
Ib/ac-d) beginning with week 71, the am-
monia leakage showed a steady decline.
  The removal  of  nitrate was accom-
plished by maintaining flooded-over condi-
tions  on the basins. This was done for
periods of more than  a month without
adversely affecting the total nitrogen con-
centration in the effluent. The low infiltra-
tion rates  that resulted from the formation
of solids mats on the bed surfaces  were
necessary for the denitrification reaction
to occur. The only times when  poor nitro-
gen  removals were  observed were im-
mediately  after  resting  periods  with
scarification for  the first three loading se-
quences when nitrates were released from
the system due to  the  fact that it took
several loadings to reduce the infiltration
rate  and  establish  reducing  conditions.
The operation with continuously saturated
bed surface conditions was possible due
to the field layout and the soil profile.  It
was possible for air to  enter  the lower,
coarse strata of the beds  from the  sides
and from  the underdrain system.
  The major factor  affecting the effluent
nitrogen concentration appears to be the
nitrogen mass-loading rate  with respect to
the soil  cation  exchange capacity.  The
cation  exchange   capacity  is  usually
greater for soils of higher organic content.
The cation exchange capacity for the up-
per layer of soil in the beds of this study
ranged from 15 to  24.  The  coarse  ma-
terials in  the lower  portions of the  beds
had measured values in the range of 2 to
3.  Soil  organic matter,  including  that
disked in  during scarification provides the
energy source for the denitrifying bacteria
and  this  may  be  an  important source
along with the  BOD  of the  wastewater
being treated.
   Phosphorus  removal  from  wastewater
was  evaluated  in  conjunction with the
operating  conditions needed for nitrogen
removal.  Land  treatment  of  phosphorus
involves the two sequential reactions  of
adsorption  of  the   phosphate  ion  and
precipitation of  a solid that is retained in
the soil matrix.  The precipitation usually
appears to be the rate-limiting step. When
a system  is overloaded, the  rate of pre-
 cipitation  becomes  inadequate to con-
 tinually renew the sites for the adsorption
 reaction,  and phosphorus leakage occurs
 in  the process effluent.
  Phosphorus removals in this study are
summarized in Figure 3. The lower curves
in each part of  the  figure show  that the
treatment system was severely overloaded
during  the  initial  32  weeks  of  the
research.  Long   resting  periods  in  the
following  weeks caused  the system to
completely  recover  by week 50. Lower
loading rates and more frequent resting
periods maintained  efficient phosphorus
removals for the remainder of the study.
  Three  periods  were selected from the
data array (weeks 15-19, 74-78 and 92-96)
as steady-state  condition  for the points
(squares)  in Figure  4.  A  line was  con-
structed  through the points to  illustrate
the removal capacity of  the soil in  this
research.  The  reported  results of other
researchers  have also been  shown.  The
curve  illustrates  that there  was a  very
discernible  maximum loading  rate   that
gave high removals and there was very lit-
tle tolerance for overloading. Analysis of
the phosphorus removal curves  for  each
of the beds during the period of the study
showed   that   when  the   long-term
                                     (months) or short-term (days) phosphorus
                                     loading was  greater than 0.3 g/m2-d, the
                                     removal efficiency declined  quite rapidly,
                                     and when the phosphorus loading was
                                     reduced below that level, the phosphorus
                                     removal improved. It was concluded that
                                     the value of 0.3  g/m2-d represented the
                                     mineralization rate (phosphorus precipita-
                                     tion rate) for the  soil of the beds used in
                                     this study. The other  researchers points
                                     on Figure 4  show that the  mineralization
                                     rate may have  been quite different for the
                                     various soils encountered  in the different
                                     research projects  and  that the value may
                                     become less  with  many years of operation
                                     of  a system.
                                       BOD and TOC  gave similar patterns of
                                     high  removal under all operating condi-
                                     tions for the  rapid-infiltration process. The
                                     most significant parameter affecting BOD
                                     removal was the hydraulic loading rate.
                                       The effluent suspended solids  concen-
                                     trations were higher than expected for an
                                     earth filtration  system. Suspended  solids
                                     concentrations  followed the same removal
                                     pattern as that of BOD, except that the
  ^20
  £  10
  ^   °0
  -J    0
                 3.5 Day Cycle
             1
                             Loading Rate: Bed 1

                                   1 Day Cycle
      Sprinkler
Manual  ,   Computer

   Construction
    10  20   30  40  50   60  70   80  90  100  110  120 130 140  150160
                               Week Number
                                   Phosphorus: Bed 1
0   10  20  30  40  50
                                 60   70   SO _90  100  110 120  130 140 150 160
                                     Week Number
                               Phosphorus Removal: Bed 1
                                                                (Bed 2)
2/00
Q
E 80
«
* 60
0 40
£ 20
8 0
W \ A.

\ 1
xA/^A 1
\ i /^
M
f__S^T«
\
I



I 1 1 1 1 1 1 1 1 1
\
\
\



,






, ,
— ~*\ f ^
y




i i i
fc 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160
Q.
Week Number
Figure 3.    Phosphorus analysis.

-------
influent values were  lower and  the ef-
fluent  values  were two  to  three  mg/l
greater.  Inspection  of  the  underdrain
system revealed extensive biological slime
growth, which was thought  to  be  the
source of the paniculate  matter in the ef-
fluent. For systems discharging directly to
the ground water, this would  not occur.
  One of the major considerations in the
use of rapid-infiltration beds with  primary
effluent is the potential of odors near the
site. Odors were not a problem during the
period of this  research. Most of the time
during the study, standing water,  primary
effluent, was present on the beds. Natural
surface aeration was sufficient to  prevent
septic conditions and the ponding did not
cause offensive odors.
  The highly nutriated soils in the beds
produced  voluminous  weed  growth on
the surface of the beds during  the warmer
months. Weed cutting was a necessary
part of the system maintenance program
at this site for aesthetic  reasons.  Cutting
was done about  every six weeks in  the
                                    summer, during the period when the beds
                                    were rested. Excessive  algae growth oc-
                                    curred when the  ambient air temperature
                                    was  above  33°C  (90°F)  for  extended
                                    periods of  time.   This  condition caused
                                    clogging of the solids mat on the beds ac-
                                    companied by  greatly reduced  infiltration
                                    rates.  When this condition became ex-
                                    cessive, it was  necessary to rest the beds,
                                    which tended to necessitate shorter, more
                                    frequent intervals  between resting periods
                                    of the beds in the  summer than in the
                                    winter.
                                      Cold weather conditions had  very little
                                    effect on  the operation  of   the  flood
                                    loaded  beds.  Temperatures as low  as
                                    -23°C  (-27°F)   were  encountered for
                                    short  periods of  time.  Under  the  worst
                                    conditions,  an ice  layer several  inches
                                    thick formed on  the beds but seemed to
                                    have little effect on the overall  functioning
                                    of  the system.  Problems were encoun-
                                    tered  with  the  sprinkler system  during
                                    severe winter conditions. The  system ex-
                                    perienced operating  problems  when the
    Middleville. Mi. (7)    Helen. Ga. (9)
          \WardCo.. (6)/  ^Tallahassee. Ft. fW)

          CCa
100
 I
       90
       80
       70
       60
 50
       40
       30
       20
       10
      .Caddilac. Mi. (8)
           Brook ings. SD.fl 1)
                                               FortDevens. Ma. (12)
                                     This Study
                                                                 Phoenix, Ar. (13)
             Holister. Ca.<5)
Figure 4.
          .1      .2     ,3     A      .5    .6      .7

                  Long Term Phosphorus Removed(g/m2.d)

      Phosphorus removal comparison with other studies.

                               8
                                                               .8
                                                                       .9
                                                                             1.0
ambient air temperature went below freez-
ing. Although the wastewater was warm
enough to  flow  through  the  sprinkler
nozzles in  the normal fashion,  some of
the water would wet the outside of the
sprinkler head housing. When frozen, this
water  would  prevent the sprinkler  head
from turning,  causing it to spray in the
same   position  throughout   the  loading
cycle.
  The  thin-walled aluminum  irrigation pipe
was joined with connections having neo-
preme  flap gaskets to assure that the pipe
was water  tight.  When  pressurized the
pipe would  drain at the joints when the
pump  was stopped between  loadings.
This prevented the freezing of the water
within  the pipe between loadings. This ar-
rangement  worked  satisfactorily  except
during  large snowstorms. The snow  and
ice surrounding the  pipes would  seal the
joints,  causing the pipes to  remain full of
water,  in  some instances causing  irriga-
tion pipe rupture. Spray loading  systems
must be used  with care in winter weather
and provisions made for  cold  periods
when the system cannot be operated.
References
  1. Smith, D.G., K.D.  Linstedt and E.R.
    Bennett.  Treatment of Secondary Ef-
    fluent  by   Infiltration-Percolation,
    EPA-600/2-79-174, U.S.  Environmen-
    tal  Protection  Agency,  Ada,  Okla-
    homa, 1979.  104pp.
  2. Hartman,  R.B., K.D.  Linstedt,  E.R.
    Bennett and  R.R. Carlson.  Treatment
    of Primary Effluent by Rapid Infiltra-
    tion.   EPA-60072-80-207,   U.S.   En-
    vironmental  Protection Agency, Ada,
    Oklahoma, 1980.  104pp.
  3. Standard  Methods  for the Examina-
    tion of Water and Wastewater. Four-
    teenth   and   Fifteenth  Editions,
    Academic Press,  New York. APHA,
    AWWA.WPCF, 1976-80.  1193 pp.
  4. U.S.  Environmental Protection Agen-
    cy. Methods for Chemical Analysis for
    Water and Wastes. 1979.
  5. Pound,  C.E.,  R.W.  Crites and S.C.
    Reed.  Land  Treatment:  Present
    Status,  Future Prospects.  American
    Society  of  Civil  Engineers,   Civil
    Engineering, 48, (61:98-102, 1978.
  6. Sturdevant,  C. Evaluation  of Forest
    Treatment of Wastewater in an Alpine
    Environment. M.S. Thesis, Univ.  of
    Co.,  Boulder, Colorado,  1984. 152pp.
  7. Sutherland,  J.C., J.H. Cooley, D.G.
    Neary and  D.H.  Urie.  Irrigation  of
    Trees and Crops with Sewage Stabili-
    zation Pond  Effluent  in  Southern

-------
   Michigan. Proceedings of Wastewater
   Use  in the Production of Food  and
   Fiber.  EPA-660/2-74-041. Washing-
   ton,  D.C. p295-313, 1974.
 8. Urie, D.H.  Phosphorus and Nitrate
   Levels in Groundwater as Related to
   Irrigation  of Jack  Pine with Sewage
   Effluent.  Recycling Treated Municipal
   Wastewater  and   Sludge  Through
   Forest and  Crop  Land,  Penn State
   University  Press,   University   Park,
   Pennsylvania, p176-183,  1973.
 9. Nutter, W.L.,  R.C., Shultz and G.H.
   Brister. Land Treatment of Municipal
   Wastewater on  Steep Forest Slopes
   in the Humid   Southeastern United
   States.  Proceedings  of  Symposium
   on  Land Treatment of Wastewater.
   Hanover, New Hampshire. 1978.
10. Overman, A.R. Wastewater  Irrigation
   at   Tallahassee,   Florida.  U.S.  En-
   vironmental  Protection  Agency,
   EPA-600/2-79-151. 1979.
11. Dornbush,  J.N.   Infiltration   Land
   Treatment of  Stabilization Pond  Ef-
   fluent. Technical Progress Report 3.
   South   Dakota   State   University,
   Brookings, South Dakota. 1978.
12. Satterwhite, M.B.,  B.J. Condike and
   G.L. Stewart. Treatment  of Primary
   Sewage  Effluent by Rapid Infiltration.
   U.S. Army Corps  of Engineers, Cold
   Regions   Research  and   Engineering
   Laboratory. 1976.
13. Bouwer,  H., W.J. Bauer and R.D.
   Dryden.  Land Treatment  of Waste-
   water  in Todays  Society. American
   Society  of   Civil   Engineers,
   48(11:78-81,  1978.
E. R. Bennett is with the University of Colorado. Boulder, CO 80309; the EPA
  authors L. £. Leach (also the EPA Project Officer, seebelowl. CarlG. Enfield,
  and David M. Walters, are with the Robert S. Kerr Environmental Research
  Laboratory, Ada, OK 74820.
The complete report consists of two volumes, entitled "Optimization of Nitrogen
  Removal by Rapid Infiltration"
  "Volume I. System Description and Evaluation, "(Order No. PB 85-173 938/AS;
    Cost: $13.00)
  "Volume II. Remote Computer Operating System,"* (Order No. PB 85-173
    946/AS; Cost: $26.50)
The above reports  will be available only from: (cost subject to change)
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA 22161
        Telephone: 703-487-4650
The EPA Project Officer can be contacted at:
        Robert S. Kerr Environmental Research Laboratory
        U.S.  Environmental Protection Agency
        P.O.Box 1198
        Ada, OK 74820
"Most readers would not find it necessary to purchase Volume II of this report since the environmental
 evaluation and supporting data of the computer-operated system are included in Volume I. Volume II
 contains the descriptions of the various hardware components, how they were interfaced, and computer
 software for operating the system.
                                                                              .Government Printing Office: 1985 — 559-111/10824


                                                                                  9

-------
                                                            75
                                                            ;:• to

                                                            Is
                                                            
                                                            a>
                                                            to
xuim
MO
o.    m
O    Z
*»    o
                                                                            o
                                                                            (?
                                                                            o

                                                                          0) «
                                                                          - • o

                                                                          0D
                                                                          I

                                                                          A
                                                                          U1
                                                                          to
                                                                          O)
                                                                          oo
                                                                          i)
                                                                           '
                                                                           c
                                                                           <»
                                                                           »
                                                                           O
                                                                          ! r

-------