United States
Environmental Protection
Agency
Hazardous Waste Engineering
Research Laboratory
Cincinnati OH 45268
Research and Development
EPA/600/S2-85/023 May 1985
                                                                       -/I*
Project  Summary
Optional  Cost  Models  for
Landfill  Disposal  of  Municipal
Solid  Waste
James F. Hudson and Patricia L. Deese
  Forty-five  landfills and  associated
transfer  stations,  balers,  shredders,
and  transportation  networks  were
analyzed  to  determine  costs for
building and  operating a landfill and
to identify the factors that have the
greatest impacts on those costs. The
landfills studied  ranged in size from
under 100 to more than 5000 tons per
day and were located across the con-
tinental United States.
  A primary concern of the study was
to determine whether baling or shred-
ding reduced landfill costs. Analysis
of the data indicates that any  savings
incurred  at the landfill, due to prior
baling or shredding, usually does not
compensate  for  the added  cost of
these more  sophisticated  processing
facilities for the average case. On the
other hand, baling or shredding might
be feasible in a situation where com-
ponent costs  for the entire landfilling
system are high.
  Another important finding  is that
landfilling is only a small portion of
total costs. On the average, both the
haul and the  processing components
of the  system  are  more expensive
than the  landfilling component.
  This  Project Summary was devel-
oped by  EPA's Hazardous Waste En-
gineering  Research Laboratory, Cin-
cinnati, OH, to announce key findings
of the research project that  is fully
documented in  a separate report of
the same title  (see Project  Report
ordering information at back).

Introduction
  All steps in  solid waste  management
cost money. An effective manager will try
to find the system that acceptably handles
wastes at minimum cost. But the number
of options is large, and .detailed engineer-
ing studies of every option are expensive.
Simple methods are needed to structure
the  various options and  estimate rough
costs for each step so that extravagant
options can be eliminated. The remaining
possibilities  can  then be analyzed  in
depth.
  This project was designed to determine
the  average costs of each option. Cost
data were collected and analyzed from 45
operating solid waste management facil-
ities, and  methods were developed  to
relate these findings to other  local com-
munity information. The methods make it
possible  to compare the costs  of systems
with direct haul, transfer stations,  balers,
shredders, and various landfill locations
and  characteristics.   Incinerators  and
systems  with significant resource recovery
were not included in this  study.
  Waste is generated along various col-
lection routes and hauled in the collection
trucks to a processing facility or a landfill.
If the waste is  processed,  it is then
transported in large vehicles to the land-
fill.  Three types  of  processing  were
studied—transfer, bailing,  and  shredding.
The landfilling costs depend on the types
of processing as well as the landfill design.
(depth,   number  of  lifts,  etc.). Landfill
construction costs, including liners, leach-
ate  control systems,  excavation,  and
other site-related  costs, depend on site
conditions.

Site Selection
  The original plan called for  the  collec-
tion of data from nine sites for each of
the  following five  solid waste manage-

-------
ment schemes, for a total of 45 sites:
  •  Direct haul systems
  •  Transfer stations
  •  Balers-untied
  •  Balers-tied
  •  Shredders
  To meet the  overall objectives  of the
project, a set of criteria was developed for
the selection of solid waste management
facilities  to be used in  the data base:
  •  The waste from the processing facili-
     ty had to be landfilled  (minimal fer-
     rous recovery was acceptable),
  •  Records of  the weights  of  wastes
     processed had to be available,
  •  The  facility  had   to  have  been  in
     operation for at least  1  year  before
     January 1980,  and
  •  Parties at the site had to be willing to
     participate in the study.
  The selection process consisted of con-
tacting persons knowledgeable in the field
and  evaluating results of  an extensive lit-
erature review. After a potential site was
identified, local officials were contacted to
verify site characteristics and  data avail-
ability.   Many   potential   sites   were
eliminated because of the lack of  scales.
After elimination  of all sites that did not
meet the  set  criteria  or did  not  have
records  of  the  weights  of waste proc-
essed, the final  list  of  candidate sites in-
cluded 2 tied balers, 7  untied balers, and
14 shredders.
  Because of the limited number  of ac-
ceptable  sites, a  new  selection strategy
was  devised.  First, all the balers  were
grouped  together.  Second, every  effort
was  made to include all of the acceptable
shredder  and  baler   facilities.    Finally,
transfer stations and direct haul facilities
were selected to insure a  reasonable sam-
ple  distribution of the following  param-
eters:
  •  size   (with  an  effort  to focus on
     smaller facilities
  •  ownership  (including   private  and
     public facilities), and
  •  geographical  location   (selected  to
     permit  reasonable  logistics  for field
     work).
  With this  new selection  process, the
final sample consisted of  12  balefills,  9
shredfills,  11  transfer  stations, and  13
direct  haul systems.  Of these  45  sites
selected,  18 had some form of leachate
collection, and another 16 plan leachate
facilities  in the future. Of the 18 sites with
leachate collection,  7  discharge leachate
to a  sewer, 4 recycle leachate over  the fill,
and  7  have  onsite  leachate treatment.
Over half of the sites  have some  sort of
liner.  Eighteen  sights use natural clay
liners and  five  sites use  some form  of
manmade liner.  Table 1  shows the distri-
bution of facilities by type and size.

Data Collection
  Substantial data  were  collected from
each  of the solid waste  management sys-
tems  visited. Information  fell  into three
basic categories: background,  operations,
and costs.  The data were gathered during
a series of  previsit telephone interviews, a
site  visit,  a review  of  documents,  and
followup telephone calls. A detailed inter-
view  guide was developed to insure that
the correct questions were asked and to
provide a  mechanism for organizing  the
information collected.
  Collection of  background   data  was
necessary to identify which parties actual-
ly incurred  costs  for the various com-
ponents  of the solid waste management
systems.   A special  questionnaire  was
developed   for  use  during  the previsit
telephone  interviews to  determine which
parties were responsible for  which com-
ponents.
  The hypothesis was that the main oper-
ational  factors  affecting  cost are haul,
processing,  transfer,  landfill  operations,
and  landfill construction.  For  these com-
ponents, data were collected  on the size
of the operation  based  on  weights  of
waste processed.
  Haul  operational data focused on  the
factors   that  influenced  the  resources
dedicated to hauling wastes in collection
vehicles from the final pickup point to the
discharge  point.  The resources invested
include labor time,  equipment time, and
fuel.  Data  were collected  on the percent
of the  work day  dedicated  to hauling
rather than to  collection,  the  distance of
the haul, the average tons per load, and
the crew size.
  Processing operational data were meant
to reflect  the  efficiency with which  the
facilities are used. Data were collected  on
the design capacity, the  actual wastes
processed, days lost  to down time, hours
of operation per day, and days per year.
Availability  of  storage capacity for both
processed  and  unprocessed waste  was
determined.  For shredders,  the average
particle size and the existence of  metal
separation were noted.  For balers,  the
type of facility (either tied or untied)  and
the size and weight  of the bales were
recorded.
  Transfer operational data  focused  on
the resources used in transporting proc-
essed  wastes to  the landfill face.  Data
gathered included vehicle type and capa-
city,  crew  size,  transfer distance,  and
round  trip time.
  Landfill operational  factors that  might
influence  cost  (other  than  size) included
the number  and types of waste  streams
handled, age of the facility, method used,
number and height of  lifts, amount of dai-
ly cover, and source of cover.
  Landfill construction data included type
of liner if any,  type of leachate collection
and treatment if any,  and landfill  method
used.  Another  important   factor  was
whether  the landfill   construction  was
phased with  operations or whether the fill
was constructed all at one  time.
  The cost  data collected for each com-
ponent of the  solid waste  management
system were  divided into  capital  and
operational  costs  to  assure  costs were
comparable  from  site to site. The costs
were  standardized  for labor  rates, infla-
tion,  and discounting method. Thus the
labor and capital  portions  of each cost
had to be calculated.


Conclusions and
Recommendations
  The cost  data  collected  from  the 45
case  study sites were analyzed using sta-
tistical methods.  Also developed was a
series of cost curves that illustrate the in-
fluence of various parameters on  the  cost
of different components.
  For both  haul in the collection vehicles
and haul in  the  larger  transfer vehicles, in-
creasing vehicle capacity reduced  costs. A
10-percent increase in vehicle size led to a
6- to  7-percent decrease in  costs  across
all sites.
  Baling and shredding had little effect on
the  cost of transportation  in  large ve-
hicles. As expected, shredders and balers
had  higher   capital  and  operating costs
than transfer stations which  offset other
cost-reducing factors such as size.
Table 1.    Number of Sites by Size and Type

                                       Design Capacity (metric tons/
• Type of Site
Haul
Transfer
Shredder
Baler
Total
0-100
4
1
3
8
100-300
3
1
3
3
10
300-600
2
6
2
4
14
600 +
4
3
4
2
13
Total
13
11
9
12
45

-------
  Large  processing facilities  did  not ap-
pear to be much, if any, cheaper per ton
than  small  ones.  The actual hours  of
equipment  operation  did  affect  costs,
however.
  Increases  in landfilling capacity reduced
costs  considerably.   A  200-ton-per-day
facility was  27 percent less expensive per
ton than a  50-ton-per-day facility. Baling
and shredding also helped. A balefill was
43 percent less expensive per ton than a
conventional landfill,  and an  uncovered,
shredded  waste fill was 70  percent less
expensive to run. Thus the extra process-
ing does lead to savings in landfilling, but
not enough  to offset the extra processing
cost.
  No model was  developed  for landfill
construction costs.  These  costs  varied
greatly and  were  influenced  by  a  large
number of site-specific characteristics.
  Study  results confirm  that high-tech
processing  is  expensive  and  can  be
justified only if it eliminates  considerable
landfill construction  costs  or greatly in-
creases in-place density, thus spreading
landfill costs over a  longer period. Since
the former is not likely to bring sufficient
savings,  the latter may become the key
factor in decisionmaking.
  Such analyses often require an estimate
of in-place  density  (the total  amount of
solid waste  that can  be  disposed of per
acre of landfill). Though there are many
theoretical or experimental  estimates of
densities that can be achieved through
compaction,  baling,   or  shredding,   very
few actual  operational data  exist on in-
place  densities.  None of the  45  sites in
this study (which  included  most of  the
major balers and shredders) kept  records
of in-place density. Thus the collection of
operational in-place density data through
landfill surveys could  greatly  improve the
decisionmaking  process.
James F. Hudson and Patricia L Deese are with Urban Systems Research and
  Engineering, Inc., Cambridge, MA 02138.
Oscar W. Albrecht and Douglas C. Ammon were the EPA Project Officer (see
  below).
The complete report,  entitled "Optional Cost Models for Landfill Disposal of
  Municipal Solid Waste," (Order No. PB 85-176 808/AS; Cost $ 13.00, subject
  to change) will be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA 22161
        Telephone: 703-487-4650
For further information, Douglas C. Ammon, can be contacted at:
        Hazardous Waste Engineering Research Laboratory
        U.S. Environmental Protection Agency
        Cincinnati, OH 45268
                                    ft U.S. GOVERNMENT PRINTING OFFICE: 1965-55M16/27048

-------
United States
Environmental Protection
Agency
Official Business
Penalty for Private Use $300
Center for Environmental Research
Information
Cincinnati OH 45268
         OCOC329   PS

         U S  EMVIR  PROTECTION  AGENCY
         REGION  5 LIIRARY
         230  S DEARBORN STREET
         CHICAGO              IL

-------