;\1,
                    Unitsd. States
                    Environmental Protection
                    Agency
Water Engineering Research
Laboratory
Cincinnati OH 45268
                    Research and Development
EPA/600/S2-85/033  June 1985
&ER&         Project  Summary


                    Review  of  Current RBC
                    Performance and  Design
                    Procedures

                                      U s  Environmental Protection Agency
                                      Region V, Library
                                      23C South  Dttrborn Strew
                                      Chicago, Winds  606W   ..;.^
                      This study investigates the perform-
                    ance and operating histories of rotating
                    biological contactors (RBC's) used for
                    secondary wastewater treatment. Site
                    visits and contacts with plant operators
                    were undertaken  to provide data for
                    design engineers  concerned  with im-
                    proving these systems.
                      Plants surveyed complied better with
                    effluent requirements than with BOD
                    removal standards. Unacceptable per-
                    formance was traced to organic over-
                    loading or underloading. Equipment per-
                    formance is the most severe limitation
                    currently  facing RBC systems, with
                    component failures prevalent in equip-
                    ment from all suppliers.  Cumulative
                    RBC performance in terms of BOD
                    removal fell below the manufacturers'
                    design  recommendations. Dissolved
                    oxygen limiting conditions were the
                    most significant  RBC  performance
                    problem. Costs of operating RBC units
                    were less than those for activated sludge
                    systems and more than those for trick-
                    ling filters.
                      This Project Summary was developed
                    by EPA's Water Engineering Research
                    Laboratory, Cincinnati. OH, to announce
                    key findings of the research project that
                    is fully documented in a separate report
                    of the same title  fsee Project Report
                    ordering information at back).

                    Introduction
                      Over the past two decades, rotating
                    biological contactor(RBC)technology has
                    become a viable alternative for secondary
                    wastewater treatment. As of 1979, ap-
                    proximately 263 municipal facilities in
                    the United States were using RBC's. The
                    rapid emergence  of RBC  systems as
                    viable secondary  treatment processes
has increased the need to review their
performance history and provide back-
ground for the design engineer concerned
with improving the design, operation, and
reliability of these systems. This investi-
gation was designed to fulfill this need in
part by evaluating the performance and
operating history of RBC facilities that
treat municipal wastewater and approach
design flow conditions.
  The investigation included site visits to
six plants for a review  of process per-
formance and to 14 plants for power
measurements. In addition, process per-
formance data were  collected from  16
plants, contacts were made with opera-
tors of eight additional plants with organic
overloading problems, and operators of
24  plants were contacted to review
maintenance requirements.

Process Performance
  A survey of 16 RBC facilities with an
average influent BOD concentration of
124  mg/L  revealed  that these plants
have greater success in complying with
effluent concentration criteria (maximum
30  mg/L) than they have with BOD
removal standards (85 percent minimum).
Average monthly BOD removal for  the
plants surveyed was 82  percent  and
varied from  75 to 90 percent for  one
standard deviation from the mean. The
average monthly effluent concentration
was 18 mg/L, with one standard deviation
from the mean producing a range of 12 to
28 mg/L. Unacceptable performance was
traced to either organic overload or
underload conditions.
  Organically overloaded systems refer
to facilities in which the influent  and
reactor organic concentrations result in
dissolved oxygen limitations in the initial

-------
stages of the RBC system  and reduced
organic removals. In some facilities, the
first stage may be organically overloaded,
but subsequent  stages are capable of
increasing their respective organic remov-
al rates in response to the higher organic
concentration of the influent. The result
is that final effluent concentration is still
acceptable. In instances where subse-
quent  stages  are not  available,  final
effluent quality does not meet secondary
treatment requirements.

Equipment Performance
  A review of RBC units manufactured in
the United States revealed that they are
similar in  size, shape, and materials of
construction and that component failures
were found  in equipment from all sup-
pliers.  From  a survey of equipment fail-
ures at 17 operating RBC plants, it was
concluded that shaft failures have the
most serious impact on operations and
generally result from overloading. How-
ever, the survey revealed that radial arms
have the highest rate of equipment failure
(30 percent) of the five  main RBC  com-
ponents (shafts,  bearings,  radial  arms,
media, and  drive system). Equipment
performance was judged to be the most
severe limitation currently facing RBC
systems. As a result of this poor operating
history, it was concluded that design
engineers should require an RBC equip-
ment  warranty sufficient to protect the
owner against equipment failure.

Design Procedures
  Most municipal wastewater RBC sys-
tems  are  currently designed  using
manufacturer-derived empirical design
relationships that are based on observed
municipal wastewater treatment perform-
ance. For the range of conditions observed
at the 16 RBC plants described above,
cumulative RBC performance in terms of
percent BOD removal fell  below the
manufacturers' design recommendation.
  Dissolved  oxygen limiting conditions
were observed to be the most significant
problem associated with RBC  perform-
ance. Only one  manufacturer currently
recommends design modifications that
account for dissolved oxygen limitations.
This design criterion is defined in terms of
a limiting value for pounds of BOD per day
per 1,000 ft2. A  review of 23 operating
RBC  facilities revealed that nuisance
organism  growths associated with dis-
solved oxygen limiting  conditions were
reported for  facilities experiencing a first-
stage organic loading greater than 6.4 Ib
of BOD per day per 1,000 ft2.
  Organic overload should be avoided in
RBC design by limiting total BOD loading
per stage to 6.4 Ib per day per 1,000 ft2.
Organic loading should take into account
intermittent sidestream loadings, septage
loadings, and average hourly peak load-
ings as well as the average daily loadings.
  RBC designers should make more use
of RBC kinetics, reactor  design,  and
system characteristics so that they may
incorporate alternative equipment layout,
flexibility, and quality control in the design
and selection of RBC equipment, particu-
larly when  using  empirical  methods.
Additionally, greater flexibility to improve
RBC process control options is required.
Because no single design approach has
been completely acceptable for predicting
RBC performance, the  RBC designer
should supplement existing methods with
field visits to similar  facilities to define
operating problems and design deficien-
cies.


Operation and Maintenance
Requirements
  Costs associated with  operating RBC
units averaged less than those reported
for  activated  sludge  systems  but more
than those reported for trickling filters.
Labor  costs to operate and maintain RBC
units (including  inspection, lubrication,
and housekeeping) represent 60 percent
of the total RBC operation and mainte-
nance costs.  Actual  RBC maintenance
averaged 2.9  hr per week, or 2.7 percent
of the  total plant requirements.

Power Requirements
  A review of RBC manufacturers' power
studies  together with the results of a
WESTON field power  measurement pro-
gram  resulted in the following conclu-
sions  regarding  mechanically driven
units:

  1.  The power consumed by a mechan-
     ically driven  RBC  unit is directly
     related  to the surface area  of the
     unit (linear relationship).
  2.  The power consumed by a mechan-
     ically driven  RBC  unit  has  been
     reported to be  proportional  to the
     rotational speed to the third power.
  3.  Initial RBC stages of mechanically
     driven RBC units with thick biolog-
     ical growths consume more power
     than do later stages with thinner
     growths.
  4.  Power consumption reported during
      manufacturers'  clean media tests is
     significantly lower than power con-
     sumption  measured  under field
     conditions.
  5.  Power consumption by standard-
     density media shafts (100,000 ft2)
     and  high-density media shafts
     (150,000 ft2) driven by mechanical
     drives at rotational  speeds  of ap-
     proximately 1.6 rpm was observed
     in the field to be approximately 2.3
     and 3.4 kW per shaft, respectively.
  6.  Air-drive units with combined stan-
     dard high-density media rotating at
     1.2 rpm averaged approximately 3.6
     kW per 100,000 ft2 of surface area
     (for a combined standard and high-
     density unit).

  The full report was  submitted in fulfill-
ment of Contract No. 68-03-2775 and No.
68-03-3019 by Roy F.  Weston, Inc., under
the sponsorship of the U.S. Environmental
Protection Agency.

-------
     This Project Summary was prepared by staff of Roy F. Weston, Inc., West Chester,
       PA 19380.
     Jon H. Bander is the EPA Project Officer (see below).
     The complete report, entitled "Review of Current RBC Performance and Design
       Procedures,' (OrderNo. PB85-180545/AS; Cost: $19.00, subject to change)
       will be available only from:
             National Technical Information Service
             5285 Port Royal Road
             Springfield, VA22161
             Telephone:  703-487-4650
     The EPA contact person, Francis L Evans III, may be reached at:
             Water Engineering Research Laboratory
             U.S. Environmental Protection Agency
             Cincinnati, OH 45268
                                         U.S. GOVERNMENT PRINTING OFFICE: 1985-559-016/27095
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Official Business
Penalty for Private Use $300
                                         OCQC329
                                                                       K  AGENCY

-------