United States
Environmental Protection
Agency
Water Engineering
Research Laboratory
Cincinnati OH 45268
Research and Development
EPA/600/S2-85/040 Sept. 1985
Project Summary
The  Loves  Creek Anaerobic,
Upflow (ANFLOW)  Pilot  Plant:
Performance Summary
 Michael T.  Harris, Terrence L. Donaldson, Richard K. Genung, Angel L
 Rivera, and Charles W. Hancher
  The performance of an anerobic, up-
flow (ANFLOW) fixed-film bioreactor
was studied on a near-commercial
scale in Knoxville, Tennessee, with a
190-m3/day facility from August 1981 to
October 1983.
  During treatment of low-strength
municipal wastewater before primary
sedimentation, the effluent met the
EPA secondary  treatment discharge
limits of 30 mg/L for TSS and BOD the
vast majority of the time, with only an
occasional increase to the 30- to 40-
mg/L range for perhaps 1 to 2 days.
Loading rates were -0.25 kg/m3-day of
TSS and BOD each, and the  hydraulic
retention time was 9 to 10 hours. This
performance was maintained in ambi-
ent cold weather tests (~12°C water
temperature), though the rate of solids
accumulation in the bioreactor was
higher in cold weather because of de-
creased biological activity, which nor-
mally converts solids to off-gas.
  The primary mechanism for remov-
ing TSS and BOD appears to be bio-
physical filtration. Approximately 20%
of the influent carbon was converted to
methane, and 30% remained  in the
bioreactor as sludge. The balance of the
carbon was  converted  to CO2 or re-
mained in the liquid effluent as TSS and
BOD/COD. More than half of the
methane was dissolved  in the effluent
water; this methane could potentially
be recovered along with the methane in
the off-gas.
  Dry solids accumulated in the biore-
actor at the  rate of -150 kg/3800 m3
(3800 m3 = 1 million gal) of wastewater
treated, which represents a 75% to 80%
reduction in solids production com-
pared with primary sedimentation and
activated sludge or trickling filtration.
The rate was slightly higher in cold
weather and somewhat lower in warm
weather. A simple material balance
model was shown to predict the sludge
accumulation using measurable influ-
ent and effluent parameters.
  Gas production increased at higher
loading rates  with higher strength
wastewater. Solids accumulation also
increased, probably as a partial result of
the solids content of the feed, which
was formulated by mixing primary clar-
ifier underflow with the raw waste-
water.  Performance of the ANFLOW
process under these conditions was
ambiguous, however, because the
bioreactor was heavily loaded with ac-
cumulated solids when this test was
run.
  After ~2 years of operation, the pilot
plant was decommissioned and the site
was returned to the City of Knoxville, as
required by contractual agreements.
  This Project Summary was devel-
oped by ERA'S Water Engineering Re-
search Laboratory, Cincinnati, OH, to
announce key findings of the research
project that is  fully documented in a
separate report of the same title (see
Project Report ordering information at
back).

Introduction
  Recent development of the upflow
anaerobic filter, the upflow anaerobic
sludge blanket, and the attached film
expanded bed, along with a better un-
derstanding of the microbiology of
anaerobic  processes  have suggested
the feasibility of anaerobic  bioactivity
for treating low-strength wastewater at
temperatures <20°C. The fixed-film pro-

-------
cesses are especially attractive because
the bacteria are retained on the packing
material and are  not washed off in the
effluent. Thus  mean cell  residence
times on the order of 100 days can be
obtained. Also, the fixed-film systems
have been postulated to be less suscep-
tible to toxic materials because films ex-
posed to these  materials may slough
off, leaving lower levels of film viable
for continued wastewater treatment.
  The development of anaerobic filter
technology for treating municipal
wastewater has been pursued by Oak
Ridge National Laboratory (ORNL) since
1976. The ANFLOW (ANaerobic up-
FLOW) process has been operated suc-
cessfully at the laboratory on a
19-m3/day and a 190-m3/day (5,000- to
50,000-gal/day) scale. Performance over
this range has been consistent and pre-
dictable; no scale-up problems have
been encountered. A commercial AN-
FLOW unit of the latter size could handle
the municipal wastewater produced by
250 to 500 persons. Larger  systems
could be constructed using this basic
model.

Facility Description
  The ANFLOW pilot plant was located
at the Loves Creek Wastewater Treat-
ment Plant in Knoxville, Tennessee. The
pilot plant was  designed to process
-190 m3day (50,000 gal/day) of munici-
pal wastewater after pretreatment (bar
screening and grit settling) but before
primary clarification.
  The ANFLOW  bioreactor was basi-
cally a cone-bottomed,  mild-steel tank
constructed to American Petroleum In-
stitute (API) 620 Code  Specifications.
The tank was 4.9 m (16 ft) in diameter
and 5.4 m (18 ft) high with a 3-m-(10-ft-)
high packed section, the internal sur-
faces were coated with Amercoat* coal-
tar epoxy paint.  The entire system was
mounted on truck scales to provide a
continuous readout of its weight.
  The 3-m section above the cone was
packed  with 3-in. polypropylene Pall
rings  manufactured by Glitsch, Inc.,
which were floated into place randomly.
This material is relatively inexpensive,
gives a high void fraction in the bioreac-
tor, has an acceptably high packing sur-
face area, and has an open structure to
facilitate intermittent backwashing of
solids from the  bioreactor. Sampling
ports were located at several axial and
'Mention of trade names or commercial products
 does not constitute endorsement or recommenda-
 tion for use.
radial positions in the bioreactor. The
gas headspace above the normal liquid
volume was ~7.5 m3. The off-gas was
monitored and safely vented through
the roof. The incoming wastewater
could be preheated to ~25°C in a verti-
cal, double-pipe heat exchanger. Liquid
effluent was recycled to the  inlet of the
Loves Creek Plant.
  The ANFLOW bioreactor was inocu-
lated with  sewage sludge  in  August
1981. Operation during the start-up pe-
riod (through  September 1982) is de-
scribed elsewhere.  (A. L. Rivera, T. L.
Donaldson, R.  K. Genung, M. T. Harris,
and C. W.  Hancher,  The Loves Creek
Anaerobic,  Upflow  (ANFLOW) Pilot
Plant: Design and Start-Up, ORNL/TM-
8828, Union Carbide Corp. Nuclear Div.,
Oak Ridge Nat I. Lab., April  1984). This
report describes the performance of the
system under ambient  temperatures
during the 1982-83 winter and under in-
creased loading rates during the sum-
mer of 1983.

Performance Summary
  During treatment of low-strength mu-
nicipal wastewater before primary sedi-
mentation (when TSS and  BOD were
typically  100 mg/L each), the  effluent
met the EPA secondary treatment dis-
charge limits of 30 mg/L for TSS and
BOD the vast majority of the time, with
only an occasional increase to the 30- to
40-mg/L range for a brief period of time
(perhaps 1 to 2 days). Loading rates
were -0.25 kg/m3«day of TSS and BOD
each, and the  hydraulic retention time
was 9 to 10 hours.
  The bioreactor was operated at ambi-
ent temperatures from October 1, 1982,
to March 16, 1983. Then the feed pre-
heater was turned  on to simulate the
spring and summer  warm-up period.
After that followed high-strength waste-
water study in which primary  clarifier
underflow was added to the wastewater
feed.
  The performance throughout this pe-
riod is summarized  in Table 1 for the
various operating conditions during the
period from October 1982 to September
1983. In general, the good  removal of
TSS and  BOD achieved during  the
start-up period was maintained in ambi-
ent cold weather tests (~12°C water tem-
perature), although the rate of solids ac-
cumulation in the bioreactor was higher
in cold weather because of decreased
biological activity, which normally con-
verts solids to off-gas. These solids
were partially digested later during the
warm weather operation.
  The primary removal mechanism for
TSS and BOD appeared to be biophysi-
cal filtration. Approximately 20% of the
influent carbon was converted to
methane, and 30% remained in the
bioreactor as sludge. The balance of the
carbon was converted to C02 or re-
mained in the liquid effluent as TSS and
BOD/COD. More than half of the meth-
ane was dissolved in the effluent water;
this methane could potentially be recov-
ered along with the methane in the off-
gas.
  Gas production increased  at higher
loading  rates during the high-strength
wastewater study. Solids accumulation
also increased, probably as a partial re-
sult of the high  solids content of the
wastewater formulated by mixing pri-
mary clarifier underflow with the raw
wastewater. In terms of effluent water
quality,  performance of the  ANFLOW
process under these conditions is am-
biguous  because the bioreactor was
heavily loaded with accumulated solids
when this test was run.
  Analyses for total phosphates, ortho-
phosphates, TKN, NH3-N, sulfates, sul-
fides, and volatile acids were done on
influent and effluent samples periodi-
cally. The average total concentrations
of phosphates and orthophosphates
were 2.5 and 2.0 mg/L (three samples),
respectively, in the influent, and 3.0 and
2.0 mg/L (four samples), respectively,  in
the effluent. Respective averages for in-
fluent and effluent total nitrogen were
7.8  and 9.0  mg of N/L (three samples
each), and for NH3-N, they were 7.0 and
7.8 mg/L (four samples each). These re-
sults suggest that <15% of the TKN was
organic nitrogen.
  Daily influent and effluent sulfate con-
centrations averaged 37 and 26 mg/L,
respectively (four samples). Sulfide
concentrations were 0 and 6 mg/L for
the influent and effluent streams. These
data correspond with  a sulfate reduc-
tion and  sulfide production rate of -1
kg/day (or 0.013 kg/m3-day as  sulfide.
The concentration of sulfide in the liquid
effluent was well below toxic levels
(e.g., >100 mg/L) that have been known
to inhibit methanogenesis.
  Liquid samples were obtained period-
ically at 0,4, and 8 ft from the bottom  of
the packed section. Removal of TSS and
total COD/BOD was greater in the lower
portion of the packed section, whereas
removal of soluble COD/BOD was ap-
proximately uniform  throughout the
packed section.

  During the cold weather period, the   m

-------
Table 1.   Operation and Performance Summary for the 190-m3/day ANFLOW Pilot Plant*

                                                             Raw Wastewater
                                                               Plus Primary
                                                                 Clarifier
                                                       -       Underflow,
                                 Cold       Temperature        Temperature
                               Weather     Control to >20°C    Control to >20°C
                                  Raw Wastewater
Operating or Performance
      Parameter
Temperature of feed, °C            12-18            20-25               22

Period of operation, days             137              213               61

Hydraulic loading rate,                10.0              7.3              7.3
  m3/m2-day

TSS loading rate, kg/m3-day           0.15             0.12             0.73

BOD loading rate, kg/m3-day           0.13        0.23* (0.14)*             0.40

COD loading rate, kg/m3-day           0.35             0.30              1.2

TSS removal efficiency, %              80              80               78

BOD removal efficiency, %             63           69f(50>*               70

COD removal efficiency, %             50           57'(45)*               71

Methane yield coefficient,              50              160              110
  L CH4/kg COD removed

Volumetric CH4 production rate,          9              24               94
  L CH4/m3 reactor-day

Concentration of CH4 in               3-9            63-76            60-80
  off-gas, %

Sludge production rate,               170         200*1120)*              575
  kg dry solids/3800 m3 of
  wastewater treated

"All average values were derived from monthly averages.

1Values observed during the start-up period.

* Values observed during the increasing-temperature period.

influent and effluent concentrations of
volatile acids were <1 mg/L. These data,
along with the fact that very little off-gas
was produced during this  period,  indi-
cated a substantial decrease in anaero-
bic bioactivity in the ANFLOW column
during the cold weather period. How-
ever, effluent remained good because
removal of TSS and BOD continued  by
biophysical filtration.
                                                  rate of VSS   rate of VSS
                                                + production — destruction
                                                  (kg/d)        (kg/d)

                                                  rate of inert   rate of inert
                                                + solids in   - solids out
                                                  (kg/d)        (kg/d).
Sludge Accumulation
  The amount of sludge in the bioreac-
tor was estimated independently using
a material balance model and the mea-
sured change in weight of the ANFLOW
column. The mass balance equation fol-
lows:
 Rate of TSS
accumulation
   (kg/d)
           rate of VSS   rate of VSS
           in (kg/d)    - out (kg/d)
The quantities on the right side of the
equation can be expressed in terms of
measurable or otherwise known param-
eters.
  The accumulation of dry solids in the
bioreactor is plotted in Figure 1. Accord-
ing to the model, -850 kg of dry solids
(or 170 kg  solids/3800 m3 wastewater
treated) accumulated in the column dur-
ing the cold weather period (days 483
through 588). The data in Figure 1 also
show the solids accumulation esti-
mated  by  the  measured change in
bioreactor weight. To convert bioreac-
tor weight to the mass of solids in the
 reactor, it was assumed that the total
 volume occupied by the liquid  and
 solids was constant, and that the densi-
 ties of the water, volatile solids, and dry
 inert solid had constant values of 1.0,
 1.0, and 2.5 g/mL, respectively. The data
 in  Figure 1 show excellent agreement
 between the model and the experimen-
 tal data over the entire operating period
 of -750 days.
   Discharge of solids was carried out
 several times late in the project. Simple
 draining of the  bioreactor removes
 some solids, but not as much as is prob-
 ably desired. Techniques need to be de-
 veloped to improve the solids discharge
 procedures. Solids can be dislodged
 from the packing very easily by a gentle
 stream of water from a  hose. Approxi-
 mately 5500 kg of dry  solids was re-
 moved from the bioreactor when the pi-
 lot plant was decommissioned, which is
 in  reasonable agreement  with  the
 —6800 kg indicated in Figure 1.

 Residence Time Distribution
 Tests
  Residence time distribution tests
 were conducted before inoculation and
 after  —5000 kg of dry solids had accu-
 mulated in the bioreactor. An inert fluo-
 rescein dye was used. The flow patterns
 before inoculation were adequately de-
 scribed by three unequal-volume tanks
 in series  with volume ratios of 1:3:6.
 The latter flow patterns could be de-
 scribed by two equal-volume tanks in
 series. However, a substantial reduction
 occurred  in the mean residence time;
 approximately one-sixth of the total re-
 actor volume was used, while the other
 five-sixths were occupied by solids
 and/or stagnant dead-volume zones.

 Metal Test Coupons
  Type 316 stainless steel metal test
 coupons were evenly coated with seven
 types of paint and placed in the top of
 the ANFLOW column at the gas-liquid
 interface for exposure to both the liquid
 and gas phases. The Amercoat 395/395
 paint sample showed no signs of peel-
 ing and no indication of reactivity with
 the corrosive  atmosphere  after -800
 days. The Sikagard 62-gray also
 showed high resistance to the corrosive
 atmosphere. Other paints showed sig-
 nificant deterioration. Overall, the gas
 phase was more reactive to the paints
than the liquid phase.

 Energy Conservation
  ANFLOW is an energy-conserving
technology. Earlier studies have indi-

-------
     10.000
      8,000
      6,000
      4,000
      2,000
                             T
                                         T
                       •   Bioreactor Weight

                      —  Material Balance Model
          I
                 I
                       I
                             I
\
I
Figure 1 .
          0          200         400          600

                              Time After Inoculation (days)

           A ccumulation of solids in the A NFL O W bioreactor.
                                                           800
                                                                      100O
cated that at the 3800-m3/day (1-mgd)
scale, a treatment plant using the AN-
FLOW process would need only 60% of
the energy required for a plant  using
activated sludge to treat weak waste-
waters, or it would need only 30% of the
energy required to treat strong waste-
waters. When  only the biotreatment
step is  considered, ANFLOW is pro-
jected to need less than 10% of the en-
ergy  required by  activated  sludge.
Methane recovery  is  not included in
these comparisons, but recovery of
methane and conversion to electricity at
40% efficiency are projected to provide
more than sufficient energy to operate
the ANFLOW-based treatment plant.
  The full report was submitted in fulfill-
ment of Interagency Agreement EPA
No.AD-89-F-2-A173 by the Oak  Ridge
National Laboratory under the sponsor-
ship of the U.S. Environmental Protec-
tion Agency. The work described  in this
report was also supported in part  by the
U.S. Department of Energy.
                                                                        U. S. GOVERNMENT PRINTING OFFICE;1985/559-l 11/20707

-------

-------
   Michael T. Harris, TerrenceL Donaldson, RichardK. Genung, AngelL Rivera, and
     Charles W. Hancher are with Oak Ridge National Laboratory, Oak Ridge, TN
     37831.
   Ronald F. Lewi's is the EPA Project Officer (see below).
   The complete report, entitled "The Loves Creek Anaerobic, Upflow (ANFLOW)
     Pilot Plant: Performance Summary," (Order No. DE 85-010 578; Cost $ 11.95,
     subject to change) will be available only from:
          National Technical Information Service
          5285 Port Royal Road
          Springfield, VA 22161
          Telephone: 703-487-4650
   The EPA Project Officer can be contacted at:
          Water Engineering Research Laboratory
          U.S. Environmental Protection Agency
          Cincinnati.  OH 45268
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
     BULK RATE
POSTAGE & FEES PAID
        EPA
  PERMIT No. G-35
Official Business
Penalty for Private Use $300
EPA/600/S2-85/040
                                     tCU  W  TILLcY
                                     RtGION V   EPA
                                     LJSPARI2N
                                     230  S  OcAS^CRN   ST
                                     CHICAGO
                                                                    A 060*

-------