United States
                     Environmental Protection
                     Agency
Air and Energy Engineering
Research Laboratory
Research Triangle Park NC 27711
                     Research and Development
EPA/600/S2-85/060 July 1985
&ER&          Project Summary

                     Alternative  Processes for
                     Treatment of  Sinter  Plant
                     Wastewater

                     Cinthia L. Rudasill, Karl Brantner, and Stephen A. Hall
                       With the promulgation of Best Avail-
                     able Technology Economically Achiev-
                     able  (BAT)  Effluent Guidelines and
                     Standards for Iron and Steel Manufac-
                     turing, a  greater degree of treatment
                     than the clarification process normally
                     used to achieve best practicable tech-
                     nology (BPT) standards may be required
                     for sintering plant blowdown. This study
                     evaluated the  effectiveness  of two
                     treatment alternatives in achieving the
                     BAT  standards: (1) direct filtration,
                     using a dual media filter; and (2) hydrox-
                     ide precipitation with lime, followed by
                     dual  media  filtration. Evaluation of a
                     third alternative, alkaline chlorination,
                     was attempted; but, due to nonrepre-
                     sentative test conditions, the effort was
                     abandoned.
                       The treatment processes were tested,
                     using two EPA-owned mobile pilot plant
                     trailers: one contained a clarifier, used
                     to simulate preclarification; and the
                     other contained the hydroxide precipi-
                     tation clarifier, chemical  tanks,  dual
                     media filter, and associated equipment.
                       The limited data generated during the
                     study indicate  that either treatment
                     alternative tested would  produce an
                     effluent that would meet the  promul-
                     gated BAT standards. Direct filtration is
                     less expensive and requires less main-
                     tenance and operator attention than the
                     hydroxide precipitation/filtration alter-
                     native.
                       This Project Summary was developed
                     by EPA's Air and Energy Engineering
                     Research Laboratory, Research Triangle
                     Park, NC to announce key findings of
                     the research project that is fully docu-
                     mented in a separate report of the same
title (see Project Report ordering in-
formation at back).

Introduction
  Under the  Effluent Guidelines and
Standards for the Iron and Steel Manu-
facturing Point Source Category promul-
gated  May 27, 1982, Best Available
Technology (BAT) effluent limitations for
the Sintering  subcategory are based on
applying a higher degree of treatment
than BPT clarification alone. Pilot plant
studies were conducted to evaluate two
treatment alternatives for removal  of
selected pollutants for which BAT limita-
tions had been proposed.

   NOTE: This study was conducted
   before the May 27, 1982, pro-
   mulgation of the BAT  Effluent
   Limitations for the Iron and Steel
   Manufacturing  Point  Source
   Category. The basis  for the
   selection of pollutant parameters
   for evaluation of the alternative
   treatment systems investigated
   in this study was the proposed
   guidelines made public in
   December 1980. This report has
   been  updated to indicate the
   promulgated guidelines.

The treatment alternatives piloted were:
(1) direct filtration,  employing a dual
media pressure  filter; and (2) hydroxide
precipitation with lime, followed by dual
media filtration. A third alternative, alka-
line chlorination, was attempted; but, due
to an  intermittent production schedule
during  this test  phase,  representative
samples were not collected. The waste-

-------
water tested was blowdown  from the
venturi scrubber and cyclonic mist elim-
inator wet air pollution control system.
Wastewater analyses quantified suspend-
ed solids, fluoride, cyanide, phenols, oil
and grease, and various heavy metals and
priority pollutants.
  The  major  objective of the  testing
program was to develop a data  base from
which the alternative treatment systems
could be evaluated both individually and
comparatively. The data base was gener-
ated through laboratory  analyses  of
regularly  collected  samples and moni-
tored operating  conditions during pilot
plant operation.  To  assess the perfor-
mance  of  each  process, the  data was
analyzed for removal of selected pollu-
tants. Capital  and operating costs were
developed to  assess  the economics  of
each process application.  An  overall
comparative evaluation was then made,
based on both performance and econom-
ics.


Summary

Testing Program Description
  Trailer-mounted pilot  facilities  were
used to test two treatment alternatives
for sinter plant blowdown:  (1) direct
filtration, using a dual media filter; and(2)
hydroxide precipitation with lime, follow-
ed by dual media filtration. The pilot plant
consisted  of  two existing EPA-owned
trailers, part of  the Mobile Wastewater
Treatment System (MWWTS) designed to
provide treatment for a nominal through-
put of 5 gpm.* Trailer No. 1 contained the
chemical treatment system and filtration
equipment. Trailer No.  2  contained a
clarif ier for preclarification, required since
the influent to the pilot plant was tapped
from the sintering blowdown line prior to
treatment with other waste waters in an
existing on-site clarifier.
  Flow trains for the direct filtration and
hydroxide precipitation followed by filtra-
tion treatment alternatives are shown in
Figure 1. Filtration is common  to both
alternative BAT treatment models that
were tested in  the pilot study. Direct
filtration  of sintering  blowdown was
evaluated for removal of suspended solids
and other pollutants (e.g., metals, which
may  be  in  particulate—nonsoluble—
form).  In  the  hydroxide  precipitation
alternative, filtration of clarified  effluent
is a polishing step for removing the metal
hydroxides that are  not  removed  by
clarification.
  The filter media consisted of 12 in. of
sand, with a particle size in the range of
0.4 to 0.8 mm, and 24 in. of anthracite,
with a particle size of 1.0 to 1.5 mm. The
hydraulic loading rate to the filter  was
kept at approximately 5 gpm/ft2 during
the tests.
  Precipitation of  heavy metals as hy-
droxides through the addition of lime is a
well-established  technology. Lime is
added to raise the pH to a level found to be
the most suitable for optimum precipita-
tion of the metal hydroxides which are of
concern. The metal hydroxide precipitates
form a floe which can entrain particulates,
including other metallic forms, and thus
enhance their removal. In  addition to
removing metals, hydroxide precipitation
with lime can also remove fluoride by
providing a source of calcium for precipi-
tation of calcium fluoride.
  Although hydroxide  precipitation is
relatively simple,  it has several limita-
tions. Its effectiveness in removing heavy
metals is a function of the solubility of the
metal hydroxides  which, in turn,  is a
function of pH and water quality.  Thus
removal of heavy metals is limited to the
solubility of the metal hydroxides in the
particular wastewater matrix under con-
sideration.  Based on  bench scale data
and previous experience with  hydroxide
precipitation of heavy metals, the  pilot
tests were run at an operating pH of 10. A
slurry of hydrated  lime—Ca(OH)2—was
applied to the  wastewater in a rapid mix
 /.  Direct Filtration
        tank to maintain a pH of 10. The waste-
        water then flowed by gravity to a floccu-
        lator/clarif ier for f locculation and settli ng.
           Eight-hour composite samples of  raw
        wastewater (pilot plant influent), clarifier
        effluent (during the hydroxide precipita-
        tion testing  phase), and final (filtered)
        effluent were collected automatically and
        analyzed  for selected pollutant param-
        eters.
           The analytical work performed for  this
        study incorporated quality control anal-
        yses,  including  method  and  reagent
        blanks, field replicates, laboratory repli-
        cates, standards and spikes. The quality
        control data was  monitored daily.  All
        samples received by the laboratory were
        logged in and processed immediately
        upon receipt to ensure that holding times
        were not exceeded.
           The selected pollutant parameters for
        the  sinter plant  pilot  testing  included
        suspended solids, pH, fluoride, cyanide,
        phenols, oil and grease, and certain heavy
        metals and  priority pollutants. These
        parameters (shown in Table 1)were used
        to develop a data base for evaluating the
        alternative treatment processes.


        Plant Site
           Pilot testing was conducted at  the
        Armco Steel Corporation, Middletown,
        Ohio, Works. The sinter  plant converts
        iron-bearing waste  fines into blast  fur-
        nace  feed  materials. During  the  pilot
        plant test period, the feed to the sinter
                    Raw
                 Wastewater
2.  Hydroxide Precipitation With Lime
      Dual
-M  Media
      Filter
                                                   Treated
                                                  Effluent
                                                               Dual  \ Treated
                                                               Media
                                                               Filter  J Effluent
(*) Readers more familiar with metric units may use
  the conversion factors at the back of this Summary.
         Chemical Addition
                              Flocculation and Clarification

Figure 1.    Pilot plant process flow trains.
                                                             Filtration

-------
Table 1.    Pollutant Parameters Selected
           for Pilot Testing of Sinter Plant
           Slowdown
  Phenols (4 AAP)
  Fluoride
  Suspended Solids
  Oil and Grease

  pH
  Fluoranthene
  Phenol
  Chrysene
  Pyrene
Cadmium
Chromium
Copper
Cyanide
Lead
Nickel
Silver
Zinc
plant consisted of approximately 70 per-
cent BOF slag, 15 percent taconite fines,
12 percent blast furnace scrubber sludge,
and 3 percent coke fines.
  Waste gases from the sinter plant are
cleaned by a venturi scrubber and cyclonic
mist eliminator. Slowdown, taken directly
from  the bottom  of  the mist eliminator
tank  at a rate of 325 gpm, comprises
about 15 percent of the mist eliminator
flow.  The balance of the flow is recircu-
lated  back to the scrubber.
  Results and Evaluation—Summaries of
the direct filtration  data and hydroxide
precipitation/filtration data are given  in
Tables 2 and 3, respectively. To ensure
representative values, unusually high  or
low values have  been dropped from the
averages and  ranges in  these tables.
Priority pollutants that were detected are
given in Table 4.
  The promulgated BAT and BPT limita-
tions are given in Table 5.
  The two processes were compared with
respect to effectiveness in removal of the
selected pollutant parameters. Direct
filtration was effective in removing all of
the selected pollutant parameters found
to be present in the sinter plant blowdown
in significant quantities. The degree of
chromium and zinc removal varied with
varying levels of soluble chromium and
zinc in the influent. Cyanide, present in
very low levels,  was not affected. All of
the BAT and BPT  Effluent Limitations
were met by the direct filtration effluent.
Filter operation  is simple and easily
controlled,  requiring  minimal  operator
attention. No sludge is produced.  The
backwash solids loadthat is intermittently
generated could be recycled to the head
of most existing BPT treatment systems
without any additional treatment.
  Hydroxide  precipitation  followed by
filtration was effective in removing all of
the selected pollutant parameters found
to be present in significant quantities,
except phenols. The degree of chromium
removal varied with the level of soluble
influent chromium. Cyanide, present in
very low levels,  was not affected. All of
the BAT and BPT  Effluent Limitations
were met by the hydroxide precipitation
and direct filtration effluents. Operation
is straightforward and could be automati-
cally  controlled with  a high  level of
reliability. Operations manpower would
be mainly for lime slurry batching, system
monitoring,  and  routine  maintenance.
The waste sludge which is produced can
be treated and disposed of along with BPT
sludge  at  most  plants by  employing
existing BPT facilities.
  Both  treatment  processes  performed
well; however, neither performed signif-
icantly better than the other. Hydroxide
precipitation achieved slightly  lower
residuals for most parameters than direct
filtration. Direct filtration produced a high
quality effluent at a significantly lower
cost and less operational considerations
and, therefore, best achieved the goals of
BAT.
  Because heavy  metals in  the sinter
plant  blowdown were predominantly in
particulate form,  direct filtration was
effective in removing them. If significant
quantities of soluble metals had been
present, its effectiveness  would have
been  considerably less. Therefore, this
evaluation  is based on the sinter plant
blowdown that was treated during the
study.
                                                       Economic Analysis
                                                         Estimated capital costs and operating
                                                       costs for the direct filtration and hydroxide
                                                       precipitation with filtration processes are
                                                       given in Table 6. Construction costs were
                                                       developed  for  treatment facilities  de-
7able 2.    Direct Filtration Data Summary
Parameter
Suspended
Solids
pH
Fluoride
Phenol
Cyanide
Oil & Grease
Total Cadmium
Total
Chromium
Total Copper
Total Lead
Total Nickel
Total Silver
Total Zinc
Preclarifier Influent (ppm)
Mean Range
1644
7.9
109
0.23
0.07
158
0.017
0.362
0.150
0.490
0.140
0.0130
13
120-5210
7.3-8.6
15-250
0.04-0.60
0.047-0.094
28-310
86
38
—
77
'Except for the Preclarifier, for which fewer samples were taken, the number of samples may vary due to unusually high or low data values which were
 dropped from the averages and ranges. Six oil and grease samples were taken at each sampling point.

-------
Table 3.    Hydroxide Precipitation Data Summary
         Preclarifier Influent (pprnj Number of   Pilot Influent (ppm)   Dumber of Clarifier ^fluent (ppm)  Number of   Filter Effluent (ppm)   Number of
Parameter
Suspended
Solids
PH
Fluoride
Phenol
Cyanide
OH&
Grease
Total
Cadmium
Total
Chromium
Total
Copper
Total
Lead
Total
Nickel
Total
Silver
Total
Zinc
Mean
143
7.9
193
0.32
0.03
191

-------
  In developing the cost estimates,  an
effort was made to provide a realistic and
representative estimate for implementing
the BAT treatment alternatives. However,
site-specific costs will influence actual
costs for any facility. In addition to these
site-specific costs, a few other costs have
not been included.  Construction cost
estimates do not include:
     Land acquisition/space allocation
     Ancillary facilities
     Retrofitting/process equipment
     adaptation
     Equipment replacement
  1.
  2.
  3.

  4.
  5.   Backup  facilities, except  those
      normally  engineered into waste-
      water treatment design
  6.   Utility and yard services
  7.   Start-up costs
  8.   Indirect costs (interest during con-
      struction, insurance).


Conclusions

Study Conclusions
  Results of the pilot studies for treating
sinter plant blowdown indicate that both
direct filtration  and hydroxide precipita-
tion followed by filtration are effective in
removing the selected BAT pollutants to
the levels indicated in the effluent guide-
lines and limitations.
  Direct filtration  significantly  reduced
suspended solids, oil and grease, and
heavy metals levels. A slight reduction in
phenols levels was observed. None of the
pollutant parameters for which effluent
limitations have been  promulgated ex-
ceeded these limitations.
  Hydroxide precipitation  followed  by
filtration also produced an effluent that
met all limitations.
  Influent  cyanide concentrations and,
consequently,  effluent concentrations
met both the maximum and average BAT
limitations, throughout the study.  As
expected, the data showed that neither
process removed cyanide.
  Since the pH of the influent wastewater
was  fairly high and good  removal  of
metals,  suspended solids,  and fluoride
was  observed  in  the preclarifier,  the
benefits of raising the pH further by lime
addition were marginal. Optimizing the
clarification step  in BPT,  by a  lower
overflow rate and polymer addition, may
be able  to achieve an  effluent quality
comparable to  that achieved by  direct
filtration.
  Both  treatment trains appear to be
capable of providing the degree of treat-
ment required  to  meet effluent limita-
tions. Direct filtration, however, is con-
siderably less  expensive and  requires
less operator attention and maintenance
than hydroxide precipitation followed by
filtration.


Study Constraints and
Limitations
  The  primary  objective of the testing
program was to develop data for alterna-
tive treatment systems as applied to sinter
plant wastewater. Although the treatment
processes that were  evaluated in  this
study have  been  previously tested or
applied for the treatment of metal plating
wastewaters and other iron and steel
wastewaters, no data existed for their
application to the  treatment of  sinter
plant wastewater. The EPA reqgestedthe
development of 12  data points for each
treatment alternative, to be accomplished
by 8-hour composite sampling during 24-
hour per day pilot plant operation. This
approach was taken primarily because of
time constraints. It is important that the
results of the testing program be viewed
in the proper perspective, with due con-
sideration of the limitations attendant to
both the duration  and the  method of
testing.
  Direct Filtration and Hydroxide Precipi-
tation—The data for the two treatment
                                        Table 5.    Promulgated BA T and BPT Effluent Limitations

                                                                  •	Average	
                                                                                Effluent
                                                               Concentration     Limitation
                                                                Basis (ppm)   (kg/'kkg product)
                                                            Maximum
                                                                    Effluent
                                                   Concentration    Limitation
                                                    Basis (ppm)   (kg/kkg product)
Discharge (gal/ ton)
Total Suspended Solids
Oil and Grease
Ammonia (Nj*
Total Cyanide
Phenols
TRC*
Lead
Zinc
pH
75
90
20
20
2.0
0.20
—
0.50
0.55

0.0250
0.00501
0.00501
0.000501
0.0000501
—
0.000125
0.000150

275
50
50
4.0
0.35
0.90
1.5
1.5

0.0751
0.0150
0.0150
0.0010
O.O001
0.00025
0.000375
0.000450
Within the range of 6.0 to 9.0
                                        'Ammonia (N) and Chlorine Residual ITRC) limitations were developed for the alkaline chlorination
                                         alternative only.
                                        Table 6.    Summary of Annual Capital and Operating Costs'
Item
Construction Costs
Engineering and Construction Management. 2O%
Contingency, 15% of Construction and Engineering
Total Capital Cost
Amortized Capital Cost (10 yr at 18%)
Annual Operating Costs
Labor
Chemicals
Power
Maintenance (Materials and Labor)
Total
Total Annual Cost
$/1,OOOgal. treated
Hydroxide
Precipitation
571.5OO
1 14.300
85.700
771,500
171,700

70.000
19,000
6,100
7.700
102.800
274,500
$2.51
Direct
Filtration
362,900
72.600
54.400
489,900
109,000

70.000
0
2.000
4.900
76,900
185,900
$1.70
                                        "Based on third quarter of 1981.

-------
alternatives  evaluated  were generated
under  controlled operating conditions
over 4 days of operation. The test results,
therefore, reflect a very limited range of
influent conditions and pilot plant oper-
ating parameters. Long-term changes in
the raw wastewater composition, tem-
perature, and pH, and variations in treat-
ment plant operation, may produce results
that are  different from those observed
during the test period.
  Bench tests were conducted with  the
objective  of pre-establishing  certain
operating conditions, primarily chemical
dosage and pH. However, most pilot plant
operating  parameters were selected on
the basis of experience to give a practi-
cable  and/or reasonably conservative
system, within the constraints  of  the
existing pilot equipment. Process optimi-
zation was not attempted during the pilot
plant operation.
  Comparison of effluent quality achieved
by each treatment alternative with  the
BAT limitations was based on average
and maximum values for twelve  8-hour
composite samples of effluent, and  not
30-day average and maximum values of
24-hour composites, as would be required
for permit compliance.
  In summary, the pilot plant test results
indicate the  range of effluent concentra-
tions achievable by the processes tested
with the raw wastewater  characteristics
that existed at Armco Steel's sinter plant
during the pilot testing  period. The aver-
age and maximum effluent concentra-
tions do not necessarily represent  the
levels  that  can be routinely  achieved
industry-wide by a full sized system.
  Alkaline Chlorination—A\ka\\r\e chlo-
rination followed by filtration was  at-
tempted on the Armco Steel sinter plant
blowdown. The effort was terminated due
to numerous problems and malfunctions
relating to the sinter plant operation.
  A field  crew was on-site to run  the
alkaline chlorination testing in April 1981.
During  this  time,  Armco  experienced
many,  sudden plant shutdowns. These
unexpected  shutdowns  caused  many
operating problems at the pilot plant. In
addition, due to a strike by ore handlers,
Armco changed from the high lime sinter
burden that  is normally used (and which
had been used throughout the study) to a
high iron burden not normally used by the
plant. As a  result,  representative data
was not collected for the alkaline chlorin-
ation  treatment  train. The scheduled
move of the pilot trailer to the next test
site  prohibited further testing  at  the
Armco sinter plant to generate the desired
data.
Recommendations
  Based on limited data from this study,
optimized BPT clarification to minimize
overflow rates plus polymer  addition
followed by filtration is identified as being
most advantageous for the treatment of
sinter plant blowdown. This incorporates
advantages of both processes—the rela-
tively low cost of direct filtration and the
flocculation and additional settling pro-
vided by  the hydroxide  precipitation
process. It was apparent from the data
that the additional metals removal pro-
vided by the hydroxide precipitation was
due to a reduction in the net residual
suspended solids  concentration rather
than the increase in pH since the concen-
trations of soluble metals were virtually
unchanged.  Additional  testing  of this
treatment scheme would provide a more
conclusive data base.
  The constraints of short-term piloting
should be recognized. The pilot plant data
base  was limited  to the  wastewater
quality encountered at the time of the
testing and the process operating condi-
tions  employed. It was  not possible  to
develop data for a broad  range of waste-
water quality or  to optimize  process
operation in  the short  period  of pilot
testing. Therefore, augmenting the exist-
ing pilot plant data base with longer term
pilot studies designed to optimize treat-
ment processes and evaluate a reason-
able range of variables (or even full-scale
testing) would be beneficial.
  Confirming the data base on a sinter
plant with  an  acid  burden  and  acid
blowdown would also be beneficial. Many
sinter plants have a blowdown with a pH
that may be as  low as 2.0.  In such  a
system, the makeup of dissolved metals
would be completely different.

Conversion Factors
  Although EPA policy is to use metric
units in its documents, certain  nonmetric
units are used  in this  Summary  for
convenience. Readers  more familiar with
the metric system may use the following
factors to convert to that system.
Nonmetric
ft2
gal.
in.
ton
Times
0.0929
3.785
2.54
907.18
Equals
Metric
m2
I
cm
kg
   C. L. Rudasill, K. Brant ner, andS. A. Hall are with Met calf & Eddy, Inc., Boston, MA
     02114.
   John S. Ruppersberger is the EPA Project Officer (see below).
   The complete report, entitled "A It er native Processes for Treatment of Sinter Plant
     Wastewater," (Order No. PB 85-211 258/AS; Cost: $10.00. subject to change)
     will be available only from:
           National Technical Information Service
           5285 Port Royal Road
           Springfield, VA 22161
           Telephone: 703-487-4650
   The EPA Project Officer can be contacted at:
           Air and Energy Engineering Research Laboratory
           U.S. Environmental Protection Agency
           Research Triangle Park, NC 27711
                                                                            U. S. GOVERNMENT PRINTING OFFICE:1985/559-l 11/20605

-------
United States                     Center for Environmental Research
Environmental Protection             Information
Agency                          Cincinnati OH 45268
Official Business
Penalty for Private Use $300
     EPA/600/S2-85/060
                                   OCCC32?    PS

                                   U  S  ENVTR  PROTECTION  a^ENC
                                   REGION  5  LI8RABY
                                   210  S DE4PBORN  STREET
                                   CHICAGO              IL   60*04

-------