United States
                  Environmental Protection
                  Agency
Water Engineering
Research Laboratory
Cincinnati OH 45268
                  Research and Development
EPA/600/S2-85/075 Aug. 1985
c/EPA         Project  Summary

                  Centralized Treatment  of
                  Metal  Finishing  Wastes
                  at  a  Cleveland  Resource
                  Recovery  Park:
                  Part  I:  Design  and  Costs
                  Part  II:  Financing
                  Part  III:  Site  Investigation
                  E. H. Comfort, P. Crampton, G. H. Cushnie, D. S. Harrison,
                  J. Kresky, C. G. Roberts, and R. D. Smith
                    This report, in three parts, describes
                  the characteristics of the Cleveland,
                  OH, area electroplating operations and
                  an approach and design for a central-
                  ized facility to treat cyanide and heavy
                  metal wastes generated by this indus-
                  try. This facility is termed the Resource
                  Recovery Park (RRP).
                    Part I examines the technical feasibil-
                  ity of the concept, assessing the wastes
                  of a number of platers in considerable
                  detail and designing the treatment and
                  recovery processes to be applied to
                  those wastes. Part II presents the re-
                  sults of a marketing study intended to
                  determine the incentives for individual
                  plating shops to participate in  the sys-
                  tem. Part II also details the proposed
                  management and financing plan  pro-
                  jecting an attractive rate of return to
                  investors. Part III describes an investi-
                  gation of a particular site and the ac-
                  companying design and costs.
                    This Project Summary was devel-
                  oped by EPA's Water Engineering Re-
                  search Laboratory, Cincinnati, OH, to
                  announce key findings of the research
                  project that is fully documented  in a
                  separate report of the same title  (see
                  Project Report ordering information at
                  back).
Introduction

  In 1982, when this study was made,
the metal finishing industry in greater
Cleveland was composed of approxi-
mately 100 plants (76 within city limits),
the vast majority of which were small
electroplating job shops. These shops
discharged an average of 18,500 gal/day
of rinsewater that contained dilute con-
centrations of cyanide and various
heavy metals used* in the electroplating
process. EPA's pretreatment standards
require that the discharge of these pol-
lutants were to have been reduced by
April 27, 1984. In addition to the rinse-
water, electroplating shops generate
spent process solutions. Although the
volumes of these solutions are rela-
tively small  (typically 300 gal/wk), the
concentration of heavy metals is quite
significant, often exceeding 1,000 mg/L.
EPA has listed  spent solutions from
electroplating operations as RCRA haz-
ardous wastes.
  The typical solution for compliance
with electroplating pretreatment regula-
tions is to install conventional physical/
chemical treatment consisting of
cyanide oxidation, hexavalent chromi-
um reduction, metals precipitation, and

-------
sludge dewatering. The  conventional
system produces a sludge that is classi-
fied by EPA as hazardous and that re-
quires disposal in an approved landfill.
  The EPA estimated capital and annual
operating waste treatment costs for an
average job shop complying with EPA
regulations in 1984 are  $87,400 and
$22,400,  respectively. This exceeds the
monetary capabilities of many electro-
plating shops; in  fact, EPA estimates
that 20 percent of job shops will be
forced to close. Industry  estimates on
job shop closures will be  much higher.
  With compliance, the disposal of
treatment sludges is also a  financial
burden for many platers because of the
high cost of disposal and a lack of ap-
proved landfills. Sludges often must be
transported more than  100  miles to
landfills where the charge for disposal
may exceed $0.50 per gallon.
  In 1977, EPA's Office of  Research and
Development  (ORD), anticipating the
potential impact to industry  resulting
from compliance with wastewater and
solid waste  regulations, began investi-
gating alternatives to on-site waste
treatment. The most promising alterna-
tive discovered to  date  is centralized
treatment. The primary assets of this
approach are economy of scale and im-
proved waste  management. When re-
source recovery is included in the cen-
tral  treatment system,  not only are
operating costs reduced by the value of
the recovered materials, but the volume
of waste treatment residuals is de-
creased,  thereby reducing the need for
hazardous waste disposal capacity. No
other alternatives were considered at-
tractive at this time.
  Earlier  studies have established the
economic feasibility of the Centralized
Waste Treatment  (CWT)  concept, its
successful application in  the Ruhr Val-
ley in Germany, and its potential use in
five, widely differing municipalities.
  The focus of this three-part report is
on  defining the  components of the
planned RRP. The results of the analysis
and design are presented, and a discus-
sion of the benefits of the proposed RRP
for the Cleveland metropolitan area and
the participating electroplaters is devel-
oped.

Design  and  Costs

  In January  1981, the present CWT
project was  initiated to develop a cen-
tral treatment facility design. To gather
data for the design, engineering  visits
were made to  30 of the major electro-
plating shops in the area. Estimates
were then made of the waste volumes
and characteristics  each shop  would
contribute to the RRP, after application
of in-plant concentrating techniques.
  A study to characterize the Cleveland
electroplating industry and to  deter-
mine the local impact of environmental
regulations determined that all  of the
shops would be required to meet the
federal pretreatment standards and that
the local publicly owned treatment
works plans to enforce its own pretreat-
ment standards. It was found that for
shops discharging 10,000 gpd or more,
the federal standards are the controlling
limits. For shops discharging less than
10,000 gpd, however, the federal limits
regulate the discharge of only cyanide,
lead, and cadmium.  For these  shops,
the local standards  will be  used  for
other metal parameters such as nickel,
chromium, copper, and zinc.
  The RRP  treatment process design is
a conventional  system with ion ex-
change regeneration  capabilities. Metal
and cyanide recovery were not included
in the initial design because of technical
and economic considerations. A sche-
matic of the RRP operations as they may
eventually develop is given in Figure 1.
  The capital and operating costs  for
the 76-plant design were  determined.
The total  RRP investment cost  is
$1,560,000. An additional $1,240,000
would be required to purchase  ion  ex-
change modules. It was assumed that
these modules would be owned by the
RRP system and leased to the  plating
shops. Therefore, the total capital re-
quired  by the 87-plant-capacity  RRP is
$2,800,000. The operating costs for this
capacity  design were calculated to be
$705,000. The resulting waste treatment
fee for the  RRP is $0.085 per gallon of
waste received or per gallon of  ion ex-.
change  regeneration solution—the
amount needed to regenerate receiving
modules.

Financing
  Part II presents the results of market-
ing, financial, and economic analyses of
the proposed RRP. The incentives  for
participation, the proposed manage-
ment structure, the planned sources of
financing, and pro forma operating re-
sults are  described.
  The great majority of electroplating
shops in Cleveland would find  it eco-
nomical to participate. All but the four to
six largest shops can pretreat their
wastes cheaper by joining the RRP than
they could by installing in-plant treat-
ment. Financing by a combination  of
private equity capital  and commercial
debentures is proposed, with owner-
ship in the hands of a private corpora-
tion. The  return on investment to the
providers  of the equity is shown to  be
very attractive. Proposed fees are calcu-
lated based on a criteria of complete
capital recovery in 10 years at a cost of
funds of 20 percent in addition to a
profit of 10 percent of total annual costs
(including capital recovery).  On this
basis, operating results are projected
for 10 years showing that revenues are
sufficient to achieve investment goals.
Although  the proposed facility would
have the  potential of providing addi-
tional economic benefit through recov-
ery of resources and cogeneratfon  of
electricity and process heat, that benefit
is not included in  the analysis pre-
sented.

Site Location
  Part III of this report presents the re-
sults of an analysis of a specific site as a
potential location for the RRP. The anal-
ysis covers engineering and  cost
aspects as well as ownership, manage-
ment, marketing, and financing  con-
cerns.
  The potential site has a number of sig-
nificant advantages that would increase
the likelihood of a successful RRP oper-
ation. The location and size of the site
and  the availability of existing struc-
tures are primary assets.
  The market evaluation for the specific
site indicates that for 54 of the 76 Cleve-
land electroplating  shops the facility
could provide a  savings when com-
pared with on-site treatment. The pro-
posed facility will have the potential  of
providing  additional economic benefit
through recovery of resources and co-
generation of electricity and  process
heat.
  A combination of a loan secured from
the program established by Ohio's Sen-
ate Bill 313 and the private placement of
stock appears to be the preferred
method of obtaining capital. The return
on investment to the  providers of the
equity is shown to be approximately
13.1  percent.

Conclusions
  For most industrial cities, major sav-
ings in  total pollution  control  costs
could be obtained if a centralized facility
is established to treat the concentrated
wastes of  a number of manufacturers.
This concept has been in practice in the

-------
      3
Administrative
Office

Analytical
Laboratory
                   Area for
                  Treatment
                  Chemical
                  Receiving
             Q)  Truck  Q
             O
                Roofed Waste
                Receiving Area
                                                                                        Area Secured by Fencing
                                                                 Recovered
                                                                  Material
                                                                  to Market
                                        Discharge    Solids Hauled
                                          to City     to Disposal Site
                                          Sewer
 Figure 1.    Central processing facility.
 Ruhr Valley of Germany for over  10
 years, with almost complete success.
 The facilities have been funded both pri-
 vately and by municipalities (using their
 credit and capital). In all cases, they are
 fully supported by fees charged to those
 sending wastes to the facility; yet fees
 represent major savings to the partici-
 pating industries over building individ-
 ual facilities.
  The concept of centralized waste
treatment offers relief for only one  of
the problems facing  most platers. The
problems  of replacing outdated equip-
ment, obtaining cheaper energy, and in-
corporating  cost-saving  automation re-
main. The Cleveland RRP would not
only  provide waste treatment for all
local  users and those within a practical
shipping range, but would offer the fol-
lowing additional features:
  • Facilities for recovering compo-
    nents of wastes, where  economi-
    cally feasible
  • Sites for relocating and moderniz-
    ing facilities where the current loca-
    tion is limited
  • Low cost  steam  and electricity
    through a central boiler-cogeneration
    facility
  • Centralized  laboratory facilities
  • Distributed  computing services
  • A pool of credit for qualifying partic-
    ipants
  • Centralized  shipping services
  Private financing of the proposed RRP
is  shown to be a viable and  attractive
venture. The steps being taken in Cleve-
land to achieve this goal should serve as
a model  for other U.S. industrial com-
munities.
  The full report was submitted in fulfill-
ment of Contract No.  78-03-2907 by
CENTEC Corporation under the spon-
sorship of the U. S. Environmental Pro-
tection Agency.

-------
       E. H. Comfort, P. Crampton, G. H. Cushnie, D. S. Harrison, J. Kresky, C. G. Roberts,
         andR. D. Smith are with Centec Corporation. Reston, VA 22090-5281.
       Alfred B. Craig, Jr. was the EPA Project Officer (see below).
       The complete report, entitled "Centralized Treatment of Metal Finishing Wastes at
         a Cleveland Resource Recovery Park: Part I. Design and Costs, Part/1. Financing,
         Part III.  Site Investigation," (Order No. PB 85-217 651 /AS; Cost: $23.50,
         subject to change) will be available only from:
               National Technical Information Service
               5285 Port Royal Road
               Springfield, VA 22161
               Telephone: 703-487-4650
       The EPA Project Officer can be contacted at:
               Water Engineering Research Laboratory
               U.S. Environmental Protection Agency
               Cincinnati, OH 45268
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
     BULK RATE
POSTAGE & FEES PAID
        EPA
   PERMIT No. G-35
Official Business
Penalty for Private Use $300

EPA/600/S2-85/075

-------