United States
                    Environmental Protection
                    Agency
Water Engineering Research
Laboratory
Cincinnati OH 45268
_
"x
                    Research and Development
EPA/600/S2-85/131  Jan. 1986
SERA         Project  Summary

                    Demonstration of  Service
                    Lateral Testing and
                    Rehabilitation Techniques
                    C. H. Steketee
                      New equipment and techniques were
                    used to repair service lateral piping in
                    two sanitary sewer basins in Salem,
                    Oregon. The  object was to reduce
                    infiltration and inflow (I/I) significantly.
                    The project included identifying, testing,
                    inspecting,  and  repairing the faulty
                    piping.
                      The importance of repairing service
                    laterals was well demonstrated. If these
                    are faulty, particularly near the sewer
                    main, repairing mains and manholes
                    will do little to reduce peak  l/l's. No
                    single repair method was  best for all
                    service lateral installations.
                      This Project Summary was developed
                    by EPA's Water Engineering Research
                    Laboratory,  Cincinnati. OH. to an-
                    nounce key findings of the research
                    project that is fully documented in a
                    separate report of the same  title (see
                    Project Report ordering information at
                    back).

                    Introduction
                      Studies were conducted  from  1981
                    through  mid-1984  to determine  how
                    municipal sanitary sewers in Salem,
                    Oregon,  could be repaired to reduce
                    infiltration and inflow (I/I). For many
                    years, Salem's sewer system has col-
                    lected large  amounts of I/I during wet
                    weather. These wet weather  flows in-
                    termittently exceed the hydraulic capac-
                    ities of the sewage collection and treat-
                    ment  systems, causing raw sewage
                    bypasses into storm drainage systems,
                    receiving streams, and occasionally onto
                    city streets. Previous city efforts to correct
                    these situations generally have not re-
                    sulted in large demonstrable I/I reduc-
                    tions.
  In late 1981, the city decided to repair
the sewers in two small sewer basins and
to measure the results carefully. Flows
from the basins were monitored during
the wet weather months before, during,
and after repair work was done.  Two
sewer basins with large volumes of I/I
were selected—the Skyline and the
Missouri basins. Both drain to manholes
where flows can be readily measured.
The Skyline basin was chosen because
most sewers there are constructed of
rubber-ring-jointed concrete pipe similar
to much Salem piping built since 1960.
The Missouri basin was chosen because
sewers there are built of concrete-mortar-
jointed pipe similar to most sewer piping
installed in Salem from 1940 to 1960.
  For both basins, the project included
identifying, testing,  inspecting, and re-
pairing faulty service lateral piping. These
efforts required the use of new equipment
and the development of new techniques.
  Annual precipitation in Salem averages
40 in., 70 percent of which falls between
November 1 and April 1. The topography
of both sewer basins is low to moderately
sloping. Red  clay-loam soils of low per-
meability predominate. Winter rains
result in groundwater levels near the
ground surface. Since the percolation of
precipitation  into the deep soil strata is
slow, most mid-winter precipitation runs
off.
  Both sewer repair projects were under-
taken as cooperative ventures of the City
of Salem, Westech Engineering, Inc., and
Gelco Grouting Service. The City of Salem
crews performed mainline TV inspections,
smoke stesting, mainline grouting work,
and manhole repair work. Westech Engi-
neering, Inc., organized and guided both

-------
projects, collected data, and prepared the
reports. Gelco crews tested, inspected,
and repaired service lateral piping.

The Skyline Basin
Sewer Repairs
  The  Skyline basin is  a 67-unit sub-
division served by 2,584 ft of rubber-ring-
jointed concrete pipe installed between
1964 and 1966, and 745 ft of PVC pipe
constructed in the late 1970's. Almost all
concrete sewer pipe had  been previously
tested  and chemically grouted by city
grouting crews; yet peak I/I flows meas-
ured 560,000 gpd  during  a storm  in
January 1982 at 3:00 a.m.,  when very
little domestic sewage was contributed.
When  the sewers  were eventually re-
paired, they still contributed 411,000 gpd.
  Various investigations of pipe condi-
tions were made. During  the fall of 1 981,
flow monitoring and recording equipment
was installed in the downstream man-
hole, and  it has  been  maintained there
during the wet  weather months ever
since. All sewer mains were TV-inspect-
ed, and each main joint  was air tested.
Only 1 5 faulty main joints were discover-
ed. The sewers were smoke  tested, but
only one service lateral leak was found.
Flows were measured at each manhole at
night between 12:01  and 6:00 a.m. during
storm periods to determine the amount of
I/I contributed by each section of sewer
main. I/I contributed by leaking manholes
was also measured.  The I/I  entering
mams  and manholes  was found  to be
small.  Most service laterals were con-
structed  of  4-in.,  rubber-ring-jointed,
concrete pipe.
  Property owner  permission  was ob-
tained to install service lateral cleanouts
adjacent to each house where leaking
service laterals had been identified. Ex-
cavations were made by hand, and ABS
plastic service cleanouts were installed.
Next, plugs were inserted through the
cleanouts, and a mainline packer normally
used  for  mainline  grouting  work was
centered over each service tee so that
each service  lateral could be air-tested.
Of the 31 tested, 28 failed. Hydrostatic
water  tests  were  performed  on each
lateral at the same time. In  all but one
case, the hydrostatic test and the air test
results were identical.
  Next, the 28 faulty service laterals were
TV-inspected by rodding a 1.5-in.-diam-
eter TV camera down the service piping
from  the recently  installed  cleanouts.
These  inspections revealed service piping
that was generally in  good structural
condition. Few visible leaks  or broken
pipes were discovered. These inspections
raised suspicions that many service lat-
erals were leaking at their connections to
the sewer main. Thus the downstream
3-or 4-ft section of each faulty service
lateral was isolated and air tested. Nine-
teen leaked. Because those faults were
immediately adjacent to the main, they
were considered to be major I/I contrib-
utors.
  Repairs were subsequently made to the
Skyline sewer system. Leaking manholes
and joints in sewer mains were sealed by
chemical grouting. Faulty service laterals
were  repaired with  a  variety of tech-
niques, most of which involved chemical
grouting. A new innovation, developed by
Westech/Gelco and nicknamed "the
snake," was used to repair most faulty
service laterals. This equipment consisted
of a flexible rubber cylinder that had a
pneumatically operated apparatus to pro-
pel the unitthrough service lateral piping.
The equipment was used to systematically
isolate 7-ft sections of service  lateral
pipe, to perform air tests on the isolated
piping, and to seal  leaks using chemical
grouting.
  After the initial repairs were completed,
peak I/I  volumes of  150,000 gpd were
measured—a 63-percent reduction from
the original 411,000 gpd. In two sections
of sewer main, only mains and manholes
were repaired, not  service laterals. This
step was taken to see how repairing
adjacent sewers affected the I/I collected
by these two sewer  sections. Although
overall flows were greatly reduced, the I/I
collected by these two sewers increased
by 208  percent  in  one section and de-
creased  by  43  percent in the other.
Eventually, most of the remaining faults
were repaired. Peak I/I flows from the
repaired basin were reduced by approxi-
mately 92 percent.
  Because initially the mains and man-
holes were relatively watertight in the
Skyline basin, more  than 90  percent of
the peak I/I flow was attributed to the
service laterals. TV inspections of sewer
mains during  high  groundwater condi-
tions revealed most faulty service laterals.
The most significant service lateral faults
were those immediately adjacent to the
main,  where  sheared tees or  leaking
joints probably resulted from inadequate
compaction of bedding materials beneath
the service tee and service piping. During
high groundwater  conditions, some  of
these faults contributed more than 50
gpm I/I.
  The cost of repairs to the Skyline sewer
basin totaled about $70,000, not includ-
ing the  cost of flow monitoring, investi-
gations for  scientific purposes,  report
writing, and other similar tasks. Numer-
ous  difficulties  were  encountered  in
testing, inspecting, and repairing service
lateral piping, but most  of these have
since been overcome.

The Missouri  Basin Sewer
Repairs
  In the Missouri basin, 220 homes are
served by 13,345 ft of concrete-mortar-
jointed  sewer mains installed in 1955
and  1956. Although investigations into
the condition of the Missouri basin sewers
began in the fall  of 1981, repairs to this
sewer system did not begin until 1983.
The  results of the work done  in the
Skyline basin had come to the attention of
the U.S. Environmental Protection Agency
(EPA) officials, who were interested  in
further developing and evaluating tech-
niques and equipment for locating, test-
ing,  inspecting,   and  repairing  faulty
service laterals.  EPA  entered  into a
cooperative  agreement with the  City of
Salem,  offering financial aid  for sewer
repair work in the Missouri  basin.  A
variety of techniques and equipment for
service lateral work were  to be used and
evaluated as part of the Missouri basin
repair program.
  The investigations of  the  Missouri
sewers paralleled the Skyline investiga-
tions. Beginning  in the fall of 1981, flow
monitoring and recording equipment was
installed in a manhole at the downstream
end of the sewer basin, where it has since
been maintained  during the wet weather
months. Smoke  tests  were conducted
and revealed seven leaking service later-
als and several apparent interconnections
with storm  drainage piping.  All  sewer
mains were inspected, revealing 33 leak-
ing service laterals, 129  visibly leaking
main joints,  26 holes in main pipes, 101
broken  pipes, and 46 root  intrusions.
Night-time wet weather flow measure-
ments  were made  to determine the
amount of I/I entering each  section of
sewer pipe.
  Major system repairs began  in October
1983 and were completed by May 1984.
City crews  chemically grouted  sewer
mains, repaired faulty manholes,  dug up
and  replaced broken  pipes, and made
other repairs where excavation and back-
fill were required. Gelco Grouting Service
crews tested, inspected, and repaired
service lateral  pipes.  Night-time flow
measurements had revealed that some
sections of sewer pipe contributed very
little I/I. Consequently, little or no repair
work was performed on those sewers. Of

-------
the 68 sections of sewer mam, 47 were
chemically grouted.
  Likewise, service laterals were tested
and  repaired  in  selected  areas only.
Eighty-six service laterals were  tested,
and  most were repaired. Every service
lateral connection at the main failed an
air test and was sealed. Numerous dead
tees and abandoned service laterals were
sealed off.
  Where service lateral work was to be
done, permission from property owners
was obtained to install cleanouts and to
make repairs to private service laterals.
Work on private service lateral pipes was
done at  city expense because  of the
experimental nature of the project. Access
to service laterals was gained in one of
these ways:
  1.   By  installing a cleanout,  usually
      adjacent to the house.
  2.   By  excavating  and sectioning the
      service lateral  pipe, usually  near
      the property line.
  3.   By  using the Cues Lateral Sealing
      System* from  within the sewer
      main.

  Service lateral inspections was made
using a 1.5-in.-diameter TV camera rod-
ded through the pipe. Most service later-
als were air-tested using a double-ball air
test unit developed for the project. Service
lateral repair methods included chemical
grouting  using the Cues Lateral Sealing
System or the Westech/Gelco snake,
installation of polyethylene liners, instal-
lation of  Insituform liners, and replace-
ment. Many service  lateral pipes in the
Missouri basin were in very poor condition
and could not be repaired  by chemical
grouting.
  Sewer repairs in the Missouri basin
reduced peak I/I flows from 1.6 million
gpd to approximately 386,000 gpd at  a
cost of about $375,000.

Findings and Conclusions
  The Skyline and  Missouri projects
revealed  a  great deal  about effective
repair of sewer systems. Some lessons
and conclusions are listed as follows:

  1.   Sewer repairs  should  be done by
      sewer basin to reduce I/I.  During
      wet  weather,  stormwater and
      groundwater  gravitate  into and
      collect in the  backfilled  sewer
      trenches. The granular bedding
•Mention of trade names or commercial products
 does not constitute endorsement or recommenda-
 tion for use
    materials and pipe zone materials
    usually allow this  water to  move
    freely along the sewer trenches
    outside the sewer pipe. Even a few
    sewer faults  can  allow  large
    amounts of this trench water  to
    enter the sewers. This trench water
    can and often does flow into service
    lateral faults several  feet from the
    main. Because the water moves
    easily along the old sewer trenches,
    repairing only the obvious  leaks
    usually  causes the  level of the
    trench water to rise somewhat,
    thereby causing it  to migrate into
    other sewer system faults.
2.  The importance of repairing service
    laterals was well demonstrated. If
    these are faulty, particularly near
    the sewer  main, repairing mains
    and manholes alone will do little to
    reduce peak I/I.
3.  Sewer repair needs to be a compre-
    hensive program. Flows from the
    basin selected for repair need to be
    measured during wet weather be-
    fore, during, and after repairs are
    made so that the effectiveness  of
    the repair program can be deter-
    mined. The repair  of  all faults
    initially  identified  is  not  usually
    sufficient to greatly reduce I/I flows.
    Usually  a  few  major undetected
    faults are discovered after initial
    repairs are made. When these faults
    are prepared, I/I flows are dramati-
    cally reduced.
4.  Rubber-ring-jointed piping systems
    are usually  easier and less expen-
    sive to repair than older mortar joint
    systems where more extensive
    repairs are  necessary. Because  of
    the granular backfills, some newer
    sewer systems contribute more I/I
    per foot of sewer main than do the
    older, more delapidated sewer sys-
    tems.
5.  Repairing sewer systems and effec-
    tively reducing I/I  is challenging,
    difficult, and demanding. To do it
    successfully requires  both know-
    how and persistence.
6.  Quality control is extremely impor-
    tant  in repairing sewers. Many
    repair difficulties encountered  in
    these two basins were caused by
    repair efforts (particularly chemical
    grouting work)  that did not ade-
    quately seal the pipe and manhole
    faults.
7.  Relatively little experience has been
    gained in testing, inspecting, and
repairing service laterals. The fol-
lowing  observations have been
made about service lateral work.
a. Locating faulty service laterals.
  Smoke testing  identified  less
  than  10 percent of the faulty
  service laterals. TV inspection of
  sewer mains located most leak-
  ing service laterals when the
  work was performed during per-
  iods  of high  groundwater.
  Approximately 40 to 50 percent
  of  the  service laterals  in the
  Skyline system leaked. Locating
  leaking service  laterals  by TV
  inspection  of mains  in  newer
  rubber-ring-jointed piping  sys-
  tems appears to be reasonably
  efficient. In older, mortar-jointed
  sewer  systems  such as the
  Missouri system, nearly all ser-
  vice laterals leak. Thus the most
  feasible approach to such a
  system is to systematically air
  test  all  service laterals or  to
  replace  or  repair  all of them
  without preliminary testing.

b. Access for testing, inspecting.
  and repairing. Service  lateral
  cleanouts  have several advan-
  tages. The most important is that
  access for  testing, inspection,
  and repairs is available as needed
  over an extended period. Excava-
  tion  and sectioning of service
  lateral piping usually affords the
  best  access for testing, inspec-
  tion, and repairs, but the excava-
  tion usually cannot be left open
  for an extended period. Conse-
  quently  all testing and  repair
  must be completed with a few
  days—often  a difficult  accom-
  plishment. Access from  within
  the sewer  main using the Cues
  equipment requires no excava-
  tion  and no contact with  or
  consent from property owners.
  However, only the few  down-
  stream feet of service lateral pipe
  can be  entered,  tested,  or re-
  paired.

c. Inspection and testing methods.
  The small-diameter TV camera
  equipment provides a reasonably
  good visual inspection of service
  lateral pipes. Visual inspection is
  usually necessary to  determine
  how  repairs should  be  made.
  Several  methods were used for
  leak  testing service piping. The
  hydrostatic  test is somewhat

-------
         slow. Air testing from the main
         to the service lateral cleanout is
         better, but it does not locate the
         service leaks. The double-ball air
         test unit provides rapid and ac-
         curate testing if a  cleanout  or
         excavation for access is available.
         This method locates pipe leaks
         but cannot test the connection to
         the main. The Cues Lateral Seal-
         ing System tests the connection
         to the  main but  cannot test
         farther than 6 or 8 ft upstream.
         Repair methods. No single repair
         method was best for all service
         lateral installations. Each faulty
         service pipe installation  had to
         be inspected, and pipe conditions,
         configurations, depths, and sur-
         face conditions were considered
         before a repair method was
         selected. In many cases,  replac-
         ing service piping was least
         expensive  and most  desirable.
         Where the existing  pipe was
         relatively straight,  polyethylene
         liners were competitive in price
         with other repair  methods and
         caused little disruption of surface
         facilities. The  Westech/Gelco
         snake was best  used  where
         service piping  was structurally
         sound with only a few leaking
         joints. Grouting these joints is
          usually less expensive than other
         repairs. The Cues Lateral Sealing
         System  is especially applicable
         where sewer mains are deep or
          inaccessible and wherethe serv-
          ice  lateral piping is structurally
              sound. Insituform liners may in
              time become an excellent method
              for service lateral  repairs,  but
              technical problems must be re-
              solved before this method can be
              widely used.

        The full report was submitted in fulfill-
      ment of Cooperative Agreement No. CS-
      811117 by the City of Salem, OR, under
      the sponsorship of the U.S. Environmental
      Protection Agency.
         C. H. Steketee is with Westech Engineering, Inc., Salem, OR 97302.
         Richard Field was the EPA Project Officer (see below for present contact).
         The complete report, entitled "Demonstration of Service Lateral Testing and
           Rehabilitation Techniques," (Order No.  PB 86-135 647/AS; Cost: $16.95,
           subject to change) will be available only from:
                National Technical Information Service
                5285 Port Royal Road
                Springfield,  VA 22161
                Telephone: 703-487-4650
         For further information. Carl A. Brunner can be contacted at:
                Water Engineering Research Laboratory
                U.S. Environmental Protection Agency
                Cincinnati. OH 45268
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
     BULK RATE
POSTAGE & FEES PAI
        EPA
   PERMIT No G-35
Official Business
Penalty for Private Use $300
EPA/600/S2-85/131
            0169064    WERL

-------